NextGen Michigan Project Management Guidebook
NextGen Michigan Project Management Guidebook
NextGen Michigan Project Management Guidebook
Table of Contents
Introduction ................................................................................................................................................ 2
Program and Project Governance ............................................................................................................ 4
Summary of Phase Gates .......................................................................................................................... 5
Program Office Phase Gate Review Process ................................................................................... 5
Project Management Capabilities ............................................................................................................ 7
Work Planning ........................................................................................................................................ 7
The Project Work Plan........................................................................................................................ 7
Standards in project plan ................................................................................................................... 8
Example of a Project Plan Hierarchy ............................................................................................... 8
Definitions............................................................................................................................................ 8
Multi-Workstream Projects ............................................................................................................... 9
Time Tracking Management ................................................................................................................. 9
Program Deliverable Management .................................................................................................... 11
Performance and Status Reporting .................................................................................................... 14
Issue Management................................................................................................................................ 17
Risk Management ................................................................................................................................. 22
Scope Change Control Management ................................................................................................. 28
Project Resource Requests ................................................................................................................... 32
Planning Phase ......................................................................................................................................... 33
Planning Deliverables .......................................................................................................................... 33
Analyze/Design ....................................................................................................................................... 35
Analyze/Design Deliverables ............................................................................................................ 35
Build/Test ................................................................................................................................................. 37
Build Deliverables ................................................................................................................................ 37
Test Deliverables .................................................................................................................................. 38
Service Pilot............................................................................................................................................... 40
Service Pilot Deliverables .................................................................................................................... 40
Deploy/Run .............................................................................................................................................. 42
Deploy/Run Deliverables ................................................................................................................... 42
Introduction
How to identify and resolve risks and issues, as well as how to escalate to the program
as necessary?
Define decision making authority, and determine who makes what decisions.
This deliverable is developed as part of Organize Project Resources and updated as needed.
A project may have unique governance requirements, which will need to be captured in the Project
Definition document during project chartering.
4.
Depending on the project status, Program Manager and Program Owner will share the
Phase Gate document with Program Sponsors or schedule a meeting with the Project
Owner and Project Manager if warranted.
The following chapters detail the exit criteria and final deliverables, as well as provide guidance
to complete these deliverables at each phase.
Work Planning
Work planning is an iterative effort that is typically performed at the end of each phase and/or
at scope changes. Re-planning includes re-estimating of work effort, resource needs, completion
schedule, and other cost figures. Throughout the lifecycle of the project, the Project Manager
continues to monitor the projects progress toward the Business Cases benefits, to analyze any
changes, to understand the potential effect on project metrics and Business Case, to work with
the PMO to correct any inconsistencies in the way benefits have been assigned to the project
and to communicate any additional opportunities identified for maximizing value. To learn
more about PMO responsibilities, refer to the PMO Guidebook.
The Project Managers monitor project progress against the work plan to ensure progress
remains within acceptable limits. The Project Managers should focus on high risk, high impact
aspects of the project and be appropriate to the project scale. To do this:
Review the start and finish dates for each task.
Determine the specific changes to be made to the start or finish dates.
Review the predecessor and successor tasks and understand the impact to other tasks
based on changes to dates.
Review the resources assigned to the task and the effort for each resources. Understand
the impact to resources and leveling based on changes.
For impacts across projects, ensure that changes are understood by the Project Managers
and issues discussed/resolved.
The Project Work Plan
The Project Work Plan includes the tasks, milestones, schedule, dependencies, resources,
start/end dates, and other information needed to manage the projects delivery. The Project
Manager is the plan owner, and the PMO office will interact with this person to understand and
discuss the project plan.
Definitions
Workstreams - are a focused collection of work (think of mini-projects); an example
would be a large project that may incorporate delivering a tool along with a process and
metric capability. In PlanView, workstreams require a WS prefix.
Deliverables - list the actual work products, located at the end of a hierarchy of
activities. In PlanView, deliverables require a DEL prefix.
Milestones - lists the key dates as determined by the project manager. A dependency is
created for each milestone to the appropriate activity in the deliverables section. This
predecessor can be any line item in the deliverables section that drives the milestone. No
work is assigned to any of these milestones and their duration is zero. In PlanView,
milestones require a MS or MMS prefix. MS for Milestone and MMS for Major Milestone.
Only Major Milestones will appear on the program status report.
Tasks large units of work with a single major outcome. Tasks are composed of
activities.
Activity smaller units of work that are performed by on individual or team to create a
single primary outcome.
Multi-Workstream Projects
Large complex projects will likely be organized into workstreams. As defined above,
workstreams are large collections of work within a project focused on a significant project
deliverable. In some cases it may not be practical to require all individual workstreams to
maintain the same gate review cadence throughout the projects life-cycle.
In order to deliver a multi-workstream project on-time, where the workstreams will exist in
multiple phases, project managers must set clear expectations with sponsors prior to gate
reviews. Sponsors will need to understand the process for the gate review, the expectation for
phase sign-off and what is being asked of them to approve. Clear and easily discernable
information regarding the status of workstreams at the gate review is critical and expected for
sponsorship sign-off.
For phase-gate review, projects with workstreams in multiple phases will need to account for
out of sequence workstreams in their phase-gate reviews. This means that projects will be
asking sponsors to approve funding and advancement of workstreams at the phase-gates
instead of the entire project. However, projects will need to get tentative acceptance of all
workstreams and full funding for the next phase of entire project. Funding for workstreams that
have not reached phase completion will be held for distribution by the PMO until the
worksteam has successfully completed.
Project Team Members are expected to record their time on a weekly basis. Project Managers
should review project time and collect status. This involves the following:
Review time reports and collect deliverable status on a weekly basis.
Track actual work, schedule, resource, and effort, against the Work Plan.
o Track actual work and identify variance between planned vs. actual hours spent
on tasks.
o Identify tasks that are past due. Highlight tasks that are past due in the Status
Reports (refer to Performance and Status Reporting) and/or raise an issue or
risk.
The following figure depicts the Work Plan and Time Management process. Notice the
interaction between the Project (PM and Team Member) and the PMO office.
Team Member
2. Complete actual
hours and submit
timesheets in
PlanView
4a. Complete
time adjustment
Yes
Project Manager
Yes
3. Review Actual
Hours
4. Timesheet
adjustment
needed?
NO
5. Monitor
project progress
6a. Scope
Change
Control
6. Work plan
adjustment
needed?
No
PMO
7. Review work
plans
Yes
8. Follow-up
needed?
No
9. Report on
project metrics
Responsible
Project
Managers
2. Complete actual
hours and submit
timesheet in
Planview.
3. Review Actual
Hours
Team Member
Project Manager
4. Timesheet
adjustment needed?
Project Manager
Team Member
5. Monitor project
progress
Project Manager
10
Description of Activity
Work plans are submitted to the PMO for approval
at each phase gate (refer to section Project Approval
Phase-Gate Process). Upon approval, load MS work
plan to Planview.
Submit timesheet on a weekly basis in Planview.
6. Work plan
adjustment needed?
Project Manager
Project Manager
7. Review work
plans
PMO
8. Follow-up
needed?
PMO
9. Report project
metrics
PMO
As a part of the NextGen Program, certain deliverables are required for each phase to ensure the
success of the Program. The following diagram outlines the required program deliverables by
phase:
11
To see the most current version of this document, please refer to the Program Deliverable Flow.
Many of these deliverables are to provide integration with the various capabilities in NextGen.
To understand proposed responsibility for each deliverable, please refer to the NextGen
Deliverable RACI, also shown below.
12
Build/Test
Service
Bundle
Delivera
A
A
A
R
R
R
R
I
A
A
A
A
I
C
I
I
I
I
I
I
I
I
I
I
I
C
I
C
R
R
I
R
C
C
R
C
I
C
Security Manager
IT Cost Manager
C
I
I
I
R
C
C
C
C
C
C
C
R
C
C
C
C
I
A
A
A
A
A
R
A
A
A
A
A
A
A
I
I
I
I
A
R
R
R
C
C
I
I
I
C
I
C
I
I
C
C
C
I
I
A
A
A
R
A
A
A
A
R
A
A
A
A
C
C
C
Capability Integration
Customer Relationship Manager
Technical Lead(s)
I
I
I
I
I
C
A
I
I
I
I
I
I
Communication Plan
Test Approach
Test Scenarios, Conditions & Expected Results
Build Documents
Service Pilot & Deployment Plan
Build/Test Executive Summary
Production Support Plan
Early Life Support Plan
Service Restoration Plan
Service Availability Plan
Service Capacity Plan
Org Readiness Assessment
Service Level Expectations (SLE)
Training Plan
Unit Readiness Plan
Workforce Plan
Change Management Summary
Service Bundle Test Approach*
Service Bundle Test Scenarios, Conditions & Expected
Results*
Service Bundle Deployment Plan*
I
I
I
C
C
I
I
Project Owner
Project Manager
Program Sponsors
Project Definition
Project Plan
Business Case and Benefits Realization
Planning Executive Summary
Service Definition
Requirements Traceability Matrix
Solution Architecture
Detailed Design Documents
Analyze/Design Executive Summary
Service Flow
Support Model
EA Questionaire
Information Assurance Questionnaire
Change Impact Analysis
Stakeholder Analysis
Risk Assessment
Project Team
Program Director(JG)
Planning
Deliverable
Analyze/Design
Program Team
Functional Lead/BSA
I
C
R
R
I
C
C
C
C
R
R
C
C
C
C
I
I
C
I
I
I
C
C
C
I
I
I
C
C
I
I
C
C
I
I
Manoj Krishnan
NextGen Program Office
Service Management
C NextGen Program Office
Chris Eagle
C
I
C
C
I
I
R
R
I
I
C
I
I
C
R
C
I
C
C
R
C
I
C
C
C
C
I
R
R
I
I
I
C
C
C
C
C
C
I
I
I
I
I
I
I
C
C
I
R
R
R
Communication Team
I
I
C
C
C
C
R
R
R
I
I
I
I
C
C
R
C
The RACI should be used as an initial guideline, project circumstance and scope may require
variance from this model. The RACI defines who is responsible, accountable, and should be
consulted and informed throughout the lifecycle of the deliverable. The RACI definitions are
outlined below:
Responsible
Those who do the work to achieve the task. There is typically one role with a participation type
of Responsible, although others can be delegated to assist in the work required.
Accountable
The one ultimately answerable for the correct and thorough completion of the deliverable or
task. Typically the Accountable role delegates the completion of the deliverable to the
Responsible role. There must be only one Accountable specified for each task or deliverable.
Consulted
Those who possess subject matter expertise or knowledge that is critical to the creation of a
deliverable or are highly dependent upon the deliverable.
Informed
Those who are kept up-to-date on status throughout the lifecycle of the deliverable, and with
whom there is just one-way communication. These are the "key consumers" of the information.
13
Each of the required Program deliverables are described in further detail below in the
corresponding phase section. For information on how to report the status of a deliverable,
please refer to the Performance and Status Reporting Section of this document below.
Performance and Status reporting involves evaluating and documenting the projects
performance against the work plan. Performance reporting addresses the NextGen Michigan
Program Management Office, and the Program Steering Committee. Performance assessment
must be objective to be reliable.
Project Managers are expected to complete Project Status reports on a weekly basis. The Project
Status report highlights project status based on deliverable/milestone status, summarizes recent
progress and upcoming plans, as well as quantitative metrics, such as baseline and actual dates.
Project Managers should analyze variances from project baselines to identify actual and
potential problems, i.e. issues and risks, as well as forecast future performance.
Project Managers are also expected to complete a monthly Project Status report for publishing
on the NextGen Michigan website. The monthly Project Status report provides campus with
insight on the progress made by each project.
The figure below displays a sample of the NextGen Michigan Program Office Scorecard that
consists of various project status reports.
14
The figure below depicts the Performance and Status Reporting process and the table provides
further detail on process steps and responsible parties.
PMO
Yes
4. Examine Project
Data Against
Baseline
2. Data
Complete?
5. Highlight Areas
of Concern
6. Publish Report
9. Communicate
Corrective Actions
Project
Manager
Report
No
3. Follow-up on
missing or invalid
data
Advisory/
Steering
Committee
1. Update Project
Progress in
Planview
10. Implement
Corrective Actions
7. Review Project
Performance
Report
8. Determine
Corrective Actions
Responsible
Project
Manager
Description of Activity
On a weekly basis, Project Managers are responsible for
submitting project progress updates in Planview. Each
submission should include updates on:
1. Health of project deliverables (Green, Yellow, Red).
2. Accomplishments for the week.
Refer to the table for Deliverable Health criteria.
PMO will review the data and request any
clarification/updates from the appropriate Project Manager.
This data will consist of issues, risks, scope changes,
progress status, schedule, benefits realization, etc.
Refer to Issue Management and Risk Management for a
description of the processes and data required.
2. Data
Complete?
PMO
3. Follow-Up on
Invalid or
Missing Data
4. Examine
Project Data
Project
Manager
PMO
15
Against Baseline
5. Highlight
PMO
Areas of Concern
6. Publish
Report
7. Review Report
PMO
8. Determine
Corrective
Actions
Advisory/
Steering
Committee
9. Communicate
Corrective
Actions
PMO
10. Implement
Corrective
Actions
Project
Manager
Advisory/
Steering
Committee
On a weekly basis, Project Managers are expected to provide the health status on major project
deliverables and/or milestones. The overall health of the project depends on the health of each
major deliverable and/or milestone. Use the table below to determine the health of each major
deliverable/milestone. The PMO office will determine the overall health of your project based
on your weekly input. The PMO will use the following criteria to determine the overall health
of a project:
Green The health status of all major deliverables/milestones is green.
Yellow The health status of one or more deliverables/milestones is yellow.
Red The health status of one or more deliverables/milestones is red.
The table below provides guidance on how to choose the health status of each deliverable.
Table 3: Deliverable Health Status Criteria
Category
Scope
16
Green
Scope is clearly
defined and stable.
Yellow
Scope is unstable with
expected impacts.
Red
Scope is not well
defined, is
unachievable or
differs substantially
Schedule
On schedule.
Resources
Overall
Deliverable
Status
Task/activity contributing to
the completion of the
deliverable likely to be
missed.
Risks and/or issues have not
been identified, or known
risk/issues pose a reasonable
threat to deliverable success.
Communication regarding project performance and overall project status, staffing, scope
changes, issues, risks, and related corrective actions should be an ongoing process which
includes both formal and informal interaction between the project manager, the project team,
program management, and external teams (third parties, sponsor, etc.).
It is important that the program manager always be aware of any issues affecting performance
of a project since there could be dependencies which could create a program-wide impact.
Besides providing regularly scheduled communications and reporting, the project manager
should understand when and how to escalate issues and/or risks to the program level to
prevent causing an unforeseen impact to schedule, budget, or quality.
Issue Management
An issue is a problem that is currently happening. An issue might adversely affect a projects
ability to deliver based on the agreed scope, schedule, budget, and quality, as well as ability to
meet key stakeholders expectations. An issue describes a situation where something has gone
wrong and/or a decision needs to be made. Since an issue has already been realized, it can no
longer be mitigated, and must instead be resolved. Issues may have started from risks that have
been realized; if this is the case, then the issue should be linked to the original risk.
17
Project issues occur at all phases of the project. Issue identification is an ongoing process. Any
team member can raise issues. The Issues Management process, established by the PMO office,
defines how the project should raise, document, and, if appropriate, escalate an issue, as well as
track it through closure. In addition, the PMO office has developed an Issue Log as tracking
mechanism; however, the issue log should not be used as sole means of communication. Both
formal (issues log) and informal (verbal communication with team members) should take place.
Project Managers and team members are expected to log issues on a continuous basis. Project
Managers are expected to review and validate that new issues have the correct level of
information needed. All project issues should be documented in Planview. If an issue started as
a risk that was realized, then link the issue with the associated risk.
Review the Issue Management Approach depicted on the figure below to understand the
process for identifying, analyzing, escalating, resolving, and reporting issues.
PMO
Issue Management
Start
Issue Creator
1. Identify Issue
2. Document Issue
Issue Log
Project Manager
3. Validate Issue
4. Issue or
Risk?
Issue
5. Reject
Issue?
Risk
Yes
9. Close Issue
9. Close Issue
Yes
7. Monitor Issue
9. Close Issue
8. Issue
Resolved?
End
No
Issue Owner
Risk
Management
End
6. Analyze and
Resolve Issue
Escalation
Management
The table below provides more details on the Issue Management process and responsible
parties.
18
Responsible
Issue Creator
2. Document
Issue
Issue Creator
3. Validate
Issue
Project
Manager
4. Issue or
Risk?
Project
Manager
5. Reject
Issue?
6. Analyze
and Resolve
Issue
Project
Manager
Issue Owner
7. Monitor
Issue
Project
Manager
8. Issue
Resolved?
Project
Manager
9. Close Issue
Project
Manager
19
Description of Activity
Issue identification is an ongoing process, which is monitored
and updated regularly. The Issue Creator will inform the
Project Manager that there is a new project issue.
Identified issues will be documented on the Issue Log (in
Planview). Projects will document issues through the lifecycle
of the project.
All Open issues are validated by the Project Manager to
ensure issue validity, priority assignment, and correct due date.
If the issue requires additional information or clarification, then
the Project Manager will request clarification from the Issue
Creator. Valid issues will be assigned to an Issue Owner and a
Target Resolution date.
Project Manager reviews Open submissions and assesses
their validity. Submissions assessed as risks rather than issues
are set to Closed status and deferred to the Risk Management
process. The Project Manager documents the rationale.
If the issue is not valid, then the Project Manager will set its
status to Rejected and document the rationale.
The Issue Owner analyzes the issue, determines level of impact,
researches resolution alternatives, and modifies the Due Date as
needed. During this stage, the issue status remains Open.
After the issue has been analyzed, the Issue Owner will
determine a feasible solution and update the issue log. The
Issue Owner communicates the issue progress to the Project
Manager. The implementation of the solution is planned
accordingly.
Project Manager regularly assesses the status of the issue
resolution progress and manages communication, notification,
and, if necessary, escalation. The Project Manager reviews and
agrees on an Action Plan, as well as monitors the resolution
progress and determines the necessary escalation with all
affected parties. The status will remain in Open until the
issue is resolved.
Once a solution has been implemented, the Project Manager
monitors progress to determine the success of the
implementation. If the issue cannot be resolved or
implementation was not successful, the issue is escalated up the
program governance and deferred to the Escalation
Management process.
Once the issue has been addressed and the resolution has been
implemented, then the Project Manager will document the
10. Monitor,
Control, and
Report
PMO
For each new issue, the following fields should contain information:
Description
CRI Status
Issue Owner
The person responsible for following up on the issue. Responsible person can be
selected from a list of Planview users.
The project name associated with the issue. Automatically generated in
Planview based on the project work plan.
Project
Name
20
The priority of the issue. Dropdown field with the following choices:
1 Critical: I cant move forward until this issue is resolved.
2 High: Im fine for right now, but unless this issue is resolved by the due
date, I wont be able to move forward.
3 Medium: Im fine for the right now, but this may impact my ability to
move forward in the near future.
4 Low: This issue is not impacting my ability to move forward.
Description
& Detail
Initiated On
Target
Resolution
Date
CRI Type
Action Plan
& Issue
Resolution
Resolution
Date
Clear and concise description of the proposed solution or final solution. May
reference other documents as needed. If other documents are referenced,
provide file name and location.
There are two fields in Planview that capture this information. Action Plan is a
text field where the user records the proposed solution to the issue. The Issue
Resolution is a text field that captures the final resolution once the issue is
closed.
Date on which the issue was closed or deferred. User must select the date.
21
PMO
Steering
Committee
Description
All issues should begin with a priority level equal to Low or Medium in order
to properly follow the escalation process. The PM is responsible for reevaluating the priority of each new issue. The PM determines the level of
impact, action plan, resolution alternatives, and Issue Owner. Along with the
Issues Owner, the PM will monitor the resolution progress. If the issue cannot
be resolved at the project level, the PM will change the priority to High. At this
point, the PMO will assess the issue.
The PMO is responsible for re-evaluating the priority of each new issue with a
status of High. Along with the Project Manager, the PMO will monitor the
progress of the issue. If the issue cannot be resolved at the PMO level, the
PMO will change the priority to Critical. At this point, the PMO will escalate
the issue to the Program Advisory/Steering Committee.
The Program Management team will escalate all issues with a status of Critical
to the Steering Committee is to guide and provide issue resolutions or
approving a contingency plan.
Risk Management
Risk management and issue management are closely related, but distinctly different. A risk is
an uncertain circumstance or event that could hinder a project from achieving its objectives.
Issues are problems that currently affect the projects planned execution.
Any risk that the project fails to adequately respond to results in failure to obtain benefits.
Conversely, approaches that successfully avoid risks and/or mitigate their impact clear the way
for achieving benefits. Remember these relationships when assessing project performance, and
highlight them in the project performance reporting.
Risk management is a systematic approach to identifying, evaluating, and mitigating risks. It is
not about being risk averse. Rather, it is based on taking action to either minimize the impact of
a risk and/or decreasing the likelihood of it occurring. It involves planning and being proactive.
Review the Risk Management Approach depicted and explained on the figure and table below.
This process will be used to identify and evaluate risks. Work with the PMO to address any
questions on the documented process. Reuse this process to evaluate all project-specific risks.
Document your project-specific needs in the Risk Log.
22
PMO
Risk Management
Start
Risk Creator
1. Identify Risk
2. Document Risk
Risk Log
No
End
4. Risk or
Issue?
Program Manager
3. Validate Risk
Risk
5. Determine
Approach and
Create Risk
Mitigation Plan
9. Monitor Risk
10. Risk
Condition
Triggered?
Risk Log
Issue
Yes
6. Create Risk
Contingency Plan
11. Issue
Generated?
Yes
Risk Log
No
End
Issue
Management
Escalation
Management
Issue
Management
Risk Owner
No
7. Risk
Mitigation
Required?
8. Implement Risk
Mitigation Plan
12. Implement
Risk Contingency
Plan
Yes
Responsible
Risk Creator
Description of Activity
Risk identification is an ongoing process, which is
monitored and updated regularly, of uncovering
circumstances, hazards, threats, and vulnerabilities that
could affect the work efforts or the projects ability to meet
its objectives. Risk sources are both internal and external.
To be effective, do not focus on identifying every possible
risk, but rather focus on identifying events that could
negatively impact any of the following project areas, cost,
scope, schedule, quality, or resources. In addition, please
note that risk identification is not a focus on placement of
blame.
A risk will be discussed with the Project Manager prior to
entering risk in Risk Log.
23
2. Document Risk
Risk Creator
3. Validate Risk
Project
Manager
4. Risk or Issue?
Project
Manager
5. Determine
Approach and
Create Risk
Mitigation Plan
Project
Manager
6. Create Risk
Contingency Plan
Project
Manager
24
7. Risk Mitigation
Required?
Risk Owner
8. Implement Risk
Mitigation Plan
Risk Owner
9. Monitor Risk
Project
Manager
Project
Manager
12. Implement
Risk Contingency
Plan
Risk Owner
Project
Manager
14. Monitor,
Control, and
Report
PMO
For each new risk, the following fields in Planview should contain information:
Table 8: Risk Log fields in Planview
Planview
25
Description
Confidential and Preliminary. For use within University of Michigan only.
Field Name
CRI#
CRI Status
Initiated By
Open: The potential risk has been entered into Risk Log, assigned to the
appropriate resource for analysis, and is being actively investigated.
Rejected: The potential risk has been rejected either because it is duplicate
or another valid reason.
Closed: The potential risk has been reviewed, a resolution has been
proposed, accepted, and acted upon.
The user who logs the risk is the risk creator.
Risk Owner
Project Name
Risk Horizon
and Risk
Priority
The user to whom the risk is assigned. Planview allows the risk creator to
assign a risk owner. Planview also records a risk owner's contact
information.
The project name associated with the risk. Automatically generated in
Planview based on the project work plan.
Naming convention: L8: DEL: Project PLAN: [Name of Project]
Planview does not track severity of impact; however, it does track the Risk
(Impact) Horizon and Risk Priority. The PMO will use these two fields to
determine if escalation is necessary.
Estimate the Risk Impact Horizon. This dropdown field has the following
options:
Short Term: within the next 3 months
Mid Term: 3-6 months
Long Term: greater than 6 months
The Risk Priority dropdown field has the following options:
1 Critical: Threatens the success of the project.
2 High: Significant disruption to project schedule, cost, and
products/services over the medium and long term.
3 Medium: Progress disrupted with large extensions to schedule and cost,
across short and medium terms.
4 Low: Exposure is marginal.
Probability
Description
26
The probability of the risk occurring. Text field. PMs should enter a
percentage in intervals of 25% as listed below:
100%: Expected occurrence
75% : Probable occurrence
50% : Possible occurrence
25% : Unlikely occurrence
This field serves as Risk Title. The Detail field should be used to provide
2-3 sentences describing the risk.
Initiated On
Resolution Date
CRI Type
Risk Triggers
Risk Response
Plan
(Mitigation/
Contingency)
The date the risk was identified. Automatically recorded when the risk is
created.
The date the risk will be realized or closed.
The type of risk being raised. The dropdown field has the following options:
Cost - Financial benefits, additional costs in changing/solving design,
application program, or operational problems.
Scope The work that needs to be accomplished to deliver a product,
service, or result with the specified features and functions.
Schedule Deliverables and/or Milestones deadlines.
Quality Deliverables or work products comply with project standards,
expectations, and goals. project leaves; the project may be significantly
impacted if it cannot replace the
Resources Lack of resources with the appropriate skills to complete
deliverables.
The risk trigger is the event that would need to happen in order for the
potential risk to become an issue. Risk triggers are usually expressed with
some sort of dependency, or qualifier. For example, a risk trigger might be
that a resource with critical skills or knowledge leaves project leaving a gap.
When the risk trigger occurs, the risk is no longer a risk, but has
materialized into an issue that needs resolution.
This is a text field that captures situations that would allow for risk
realization, or make it an issue.
The user will record both the Mitigation plan and Contingency plan in this
text field. The Mitigation plan is the proposed solution to lessen the
probability and/or impact of the risk. The contingency plan is the action to
take if the risk is triggered.
As part of the Mitigation plan, the Project Manager should document which
strategy will be employed to mitigate the risk. See below for definitions of
strategies.
Accept - These describe the factors that may directly affect the success of
the Project ABC, but are outside of the sphere of influence of the Project
ABC Manager, and can therefore only be accepted. In addition,
acceptance of risks as a response may be based on the costineffectiveness of any available response or solution. An example:
acceptance response could be created from a legislative or legal risk,
over which no control could be leveraged.
Avoid - Avoidance-based responses are employed at any point in the
development lifecycle where future planning work is performed.
Typically, most risk avoidance occurs during the project definition and
planning phases of a project, where objectives, scope, key success
factors, work breakdown, and project outputs or deliverables are
defined. An example of risk avoidance is the use of a stable, established
27
PMO
Steering
Committee
Description
All risks should begin with a priority level equal to Low or Medium in order to
properly follow the escalation process. The PM is responsible for re-evaluating
the priority of each new risk. The PM determines the level of impact, action
plan, resolution alternatives, and Risk Owner. Along with the Risk Owner, the
PM will monitor the resolution progress. If the issue cannot be resolved at the
project level, the PM will change the priority to High. At this point, the PMO
will assess the risk.
The PMO is responsible for re-evaluating the priority of each new risk with a
status of High. Along with the Project Manager, the PMO will monitor the
progress of the risk. If the risk cannot be addressed at the PMO level, the PMO
will change the priority to Critical. At this point, the PMO will escalate the
risk to the Advisory/Steering Committee.
The Program Steering Committee is responsible for assessing all new risks
with a status of Critical, re-prioritizing critical risks, approving/providing
mitigation/contingency plan.
28
implemented by the project. Program management can also issue Change Requests to reflect
approved changes requested by other stakeholders (e.g., sponsoring organization management,
program management itself, other projects that may impact the current project, etc.) A project
Change Request is an authorized (written and approved) material change to an active project
typically affecting the baseline requirements such as scope, cost, schedule, resources, acceptance
criteria, method of delivery, documentation, quality, risk, and/or performance characteristics.
Prepare this deliverable whenever a requested change affects the project baselines. If the change
does not affect the project baselines, preparation of this deliverable is unnecessary. This
deliverable is applicable to all projects.
Start
Project Manager
2. Document
Change Request
1. Identify Change
Request
9. Analyze and
Implement Change
Request
6. Revise Change
Request
Scope
Change Log
Scope
Change Log
Yes
3. Validate
Change Request
PMO
Risk
Management
5. Additional
Info Required?
Yes
Risk
Issue
Steering
Committee
Issue
Management
4. Associated
Risk/Issue
Identified?
7. Approve
Change
Request
8. Reject Change
Request
No
29
Responsible
Project
Manager
Description of Activity
Based on the project (work plan) progress and budget, the
Project Manager will determine if a change request is
needed in order to maintain the success of the project. The
Project Manager identifies, documents, and is responsible
for scope change follow through.
2. Document
Change Request
Project
Manager
3. Validate
Change Request
PMO
4. Associated
Issue or Risk
Identified?
5. Additional
Info Required?
PMO
PMO
6. Revise Change
Request
Project
Manager
7. Approve
Change Request
Steering
Committee
8. Reject Change
Request
Steering
Committee
9. Analyze and
Implement
Change Request
Project
Manager
PMO
If the scope change is not approved, then the PMO will set
its status to Rejected and document the rationale in the
Detailed Description.
The impacted project(s) is then responsible for assigning
responsibility for implementing the approved Scope
Change request. This includes updating the schedule(s),
milestone(s), budget(s), requirement(s), and any other
affected project deliverables in a synchronized manner.
The Project Managers are responsible for coordinating the
implementation of the changes across all impacted
deliverables, such as work plans, test cases, etc., in their
respective areas of responsibility.
The change request is closed once the request has been
resolved.
The Change Request template has the following required fields. Refer to the table below for
further description of each field.
Table 11: Change Request Fields on form
Field Name
Change Status
30
Description
The status of the scope change:
Open: The scope change has been entered into Scope Change Log,
assigned to the appropriate approver, and is awaiting approval.
Approved: The scope change has been reviewed, accepted, and
approved.
Rejected: The scope change has been rejected.
Closed: The scope change has been approved and work product has
Date of Request
Created By
Implementation
Date
Project Name
Type of Change
Description
Priority
Impact Severity
Benefits of
Proposed Change
Alternatives
List of Impacted
Deliverables
Financial Impact ($)
Schedule Impact (in
days)
Impact Summary
Authorized
Approver
31
Organization/Title
Date Approved
To request a project resource, please fill out the following forms and send them to the Program
Operations Lead.
ITS Resource Request
Campus Resource Request
32
Planning Phase
Planning is the first phase of the project lifecycle. During this phase the Project Manager
assembles and organizes all the necessary information to achieve the following objectives:
Establish project governance to provide leadership and decision making support for the
project.
In order for a project to exit the Planning phase and receive approval to move to the next phase,
the project must have:
Identified the Project Sponsor, Owner and Manager who will be held accountable to the
outcomes of the project.
Identified risks and issues, and provided mitigation and contingency plans for the key
business risks.
Defined a high-level business case, which includes benefit realization tracking that is
supported by the project sponsor.
Developed high-level work and resource plan with clear effort estimation for the next
phase of work.
Planning Deliverables
The following tables outlines the required program deliverables for the Planning phase.
Deliverable
Name & Link
to Template
Project
Definition
33
Description
The project manager creates the Project Definition to define the overall scope of
the project that is to be undertaken, as well as to maintain and operate the
project. The Project Definition includes:
Project Objectives
Project Scope
Assumptions, Risks, and Dependencies
Stakeholder Identification and Plan to Align
Communication Approvers
Governance Requirements
Project Plan
Business Case
Service Level
Expectations
(SLE) Draft
Planning
Executive
Summary
34
Analyze/Design
The Analyze/Design phase has the following objectives:
Use the business process requirements to drive out application and integration
requirements and metrics.
Create the test approach and leverage the business requirements to start developing test
conditions and expected results.
Identified business requirements and received sign-off by the sponsor and appropriate
stakeholders.
Identified technical requirements and received sign-off by the technical domain owners.
An approved blueprint of the solution that describes how the services, components, and
support capability come together to meet objectives of the project.
An agreed-upon functional and technical design that describes how the requirements
will be satisfied.
A Project Sponsor committed and accountable to manage the cost and deliver of the
controllable benefits described in the refined business case.
Analyze/Design Deliverables
The following tables outlines the required program deliverables for the Analyze/Design phase.
Deliverable
Name & Link
to Template
Solution
Architecture
Blueprint
35
Description
The Solution Architecture Blueprint outlines the target-state of the solution,
specifically the application or service, the technology or process, and training
required to support it. The Solution Architecture Blueprint contains the design
decisions for application, process, technology, as well as training and
performance support. The solution blueprint typically does not contain detail
specification of how each piece-part works; rather it defines what technology
parts are used and how they interact.
Requirements
Traceability
Matrix
Analyze/Desi
gn Executive
Summary
Service Flow
Support Model
Updated
Service Level
Expectations
(SLE)
EA
Questionnaire
Information
Assurance
Questionnaire
36
Build/Test
The objectives of the Build/Test phase are to:
Plan the testing of the product or application.
Build and test the components of the product/application.
Refine the customization, integration, and conversion of the product/service until they
are concrete and detailed enough to implement.
Prepare and execute the assembly test to ensure classes and components work correctly
when integrated into a complete application/solution.
Prepare and execute the test to ensure the solution meets the functional requirements
and that all components work together.
In order for a project to exit the Build/Test phase, it must have:
Verification and agreement by Project Sponsor that the service, component, or support
capability meets the defined requirements.
Commitment from pilot stakeholder group to participate in Service Pilot.
Actual and ETC costs within an acceptable range of tolerance from baseline.
Build Deliverables
The following tables outlines the required program deliverables for the Build portion of the
Build/Test phase.
Deliverable
Name & Link
to Template
Build
Documents
Test Approach
Production
Support Plan
Description
The program is intentionally not specific regarding this deliverable, as it varies
based on the type of service project being completed. This deliverable should
include the key the outputs of the project, and in many cases there may be more
than one. For an End User Computing deliverable, an example might be the
Windows Build Image it should be essentially whatever the project is
building during the Build/Test phase. This deliverable is called out specifically
in the methodology because it is important to track these items in the Work
Plan as they are critical path items for moving into the subsequent phases.
The first step in preparing for any test stage is to develop a test approach. This
deliverable outlines the specific test types to be performed, the scope and
objectives of each test type, a high-level schedule, the pass strategy, test
environments and any testing tools to be utilized as a part of the testing effort.
The production support plan is the authoritative document that defines how
ITS supports a service in its run state. It reinforces our commitment to adhere to
processes and procedures defined at an organizational level. It is followed by
all ITS staff.
ITS provides a pre-determined, base level of production support for all
operational services in a run state. This support is set forth in the Standard
Production Support Plan and establishes the roles and expectations critical to
37
providing all ITS users the same minimum amount of consistent, timely, and
effective service support across the organization.
Service
Capacity Plan
Service
Availability
Plan
The Service Availability Plan is to document assumptions and plans for service
availability.
Test Deliverables
The following tables outlines the required program deliverables for the Test portion of the
Build/Test phase.
Deliverable
Name & Link
to Template
Test Scenarios,
Conditions &
Expected
Results
Build/Test
Executive
Summary
Service
Restoration
Plan
Early Life
Support Plan
38
Description
Test Scenarios are high level descriptions of functional and technical areas to be
tested. Scenarios are broken down into detailed, testable conditions and
expected results based on the requirements defined in the Requirements
Traceability Matrix. This document should be used to define all test scenarios
and conditions, and to document testing activity during the testing process. The
Scenarios, Conditions & Expected Results assists with understanding test phase
status as well as tracking the work to ensure all conditions and scripts are
completed.
The Service Pilot & Deployment Plan outlines the projects approach to the
Service Pilot and Deployment. It includes key success factors,
relationships/dependencies with other projects, the scope of the Service Pilot
and Deployment, Key Stakeholders, Implementation Risks, Key Activities and
Timelines.This deliverable should be used to help prepare for the Service Pilot
and Deployment and should be highly integrated with the Program Service
Pilot & Deployment Plan.
The Executive Summary is a PowerPoint presentation summarizing key
information from the Built/Test Phase. The Project Manager will use the
Executive Summary presentation to obtain Sponsor buy-in. The Sponsor signs
off on the Executive Summary and the required phase deliverables. Upon
achieving this milestone, the project may move forward to the Service Pilot
Phase.
The Service Restoration Plan is a document to help establish Service Level
Expectation (SLE) compliance, Data Recovery, and Custom Significant Incident
guidelines for each service.
Early Life Support (ELS) is a time-limited, enhanced level of assistance to
ensure appropriate levels of support are provided during stabilization, issues
are addressed quickly, and knowledge transfer is occurring to the run
organization. All support staff participating in Early Life Support follow the
plan.
The objective of the Early Life Support plan is to establish specific activities to
occur that are above and beyond the standard production support plan. The
plan further establishes stabilization criteria that, once met, trigger the move to
standard production support. The plan is often considered the support plan
that is active during the pilot phase of a project.
Organizational
Readiness
Assessment
39
Service Pilot
The objectives of the Service Pilot phase are:
Prepare and execute the performance test to ensure the application or service meets all
the performance-related metrics, such as response time, availability, load/throughput,
and reliability.
Test all the components of the service including the enabling shared services such as
Integrated Service Desk, Service Management Processes and Metrics, Operations and
Availability, etc.
Prepare and execute the user acceptance test to ensure the application or service meets
user expectations.
Assess whether service will scale.
In order for a project to exit the Service Pilot phase, it must have:
Verification and agreement by pilot owner that the service, component, or support
capability met the defined requirements.
Identified and dispositioned enhancement and requirements gaps, as well as have
Project Stakeholder agreement.
Updated the work plan.
Updated the cost and benefit estimates and received sign-off by the project sponsor.
The following tables outlines the required program deliverables for the Service Pilot Phase.
Deliverable
Name & Link
to Template
Service Run
Book
Service Pilot
Lessons
Learned
Final Service
Level
Expectations
(SLE)
Description
The Service Run Book is created to support the transition of a service into a
run state by providing a detailed explanation of how the service should
operate and includes step-by-step procedures, general tips, and a list of SMEs.
The Service Pilot Lessons Learned Document is meant to document key
takeways and areas of improvement in relation to the Service Pilot phase.
The final version of the Service Level Expectations deliverable is intended to
provide the definitive description and expectations for a given service in its run
state. SLEs provide clarity to ITS staff, as well as customers and users by clearly
articulating the nature of the service and also the commitments which ITS
makes in delivering the service. This includes commitments for key service
attributes such as service availability, performance, and response times for
provisioning and support.
During the Service Pilot Phase (prior to Deployment), the final version of the
SLE should be completed. All sections of the document should be completed
unless there are sections that do not apply to that service. If there is not a
40
Service Pilot, the SLE should be finalized at the end of Build before moving to
deployment.
Service Pilot
Executive
Summary
41
Deploy/Run
The objectives of the Deploy/Run phase are:
Prepare the production and operating environments for application/service roll-out to
the users and other application stakeholders.
Enable users and other stakeholders to use or support the new application/service.
Roll-out the new application/service to the deployment groups.
If applicable, identify the requirements for transferring responsibility for operating and
maintaining the application to the operating group and developing the transfer plan.
In order for a project to exit the Deploy/Run phase, it must have:
Key stakeholders, service portfolio manager, and project sponsor sign-off on the User
Acceptance Test Plan and how it is executed.
The Deployment Plan sign-off, as well as verification of service management
requirements from Service Operations leadership.
Deploy/Run Deliverables
The following tables outlines the required program deliverables for the Deploy/Run Phase.
Deliverable
Name & Link
to Template
Project
Closeout
Checklist
Description
Project Lessons
Learned
Summary
The Project Closeout Checklist is meant to verify that all documentation has
been archived appropriately and all of the appropriate tasks complete prior to
closing the project. The Key Service Document Repositoryis the where all
service information documents should be stored at the completion of a project.
Each ITS service has a section for documents providing information about that
service. The Service Owner will be the ongoing person responsible for
maintaining this repository of information about their service for reference by
all ITS staff. This is an inward facing Sharepoint site and should provide onestop stop to obtain all information about an ITS service.
TheProject Lessons Learned Document is meant to document key takeways and
areas of improvement in relation to project execution throughout the entire
project lifecycle.
Customer
Lessons
Learned
Summary
Deploy/Run
Executive
Summary
42
43