Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Ichthys Gas Field Development Project, Blaydin Point: Assessment Report 65

Download as pdf or txt
Download as pdf or txt
You are on page 1of 126

ASSESSMENT REPORT 65

ICHTHYS GAS FIELD


DEVELOPMENT
PROJECT, BLAYDIN
POINT
INPEX BROWSE LTD

ENVIRONMENTAL ASSESSMENT REPORT


AND
RECOMMENDATIONS
by the
Environment and Heritage Division, NRETAS
May 2011

This page is intentionally blank

Table of Contents
Glossary......................................................................................................................5
Executive Summary ...................................................................................................9
1

Introduction and Background ..........................................................................19


1.1

Environmental Impact Assessment Process ..........................................19

1.2

Regulatory Framework..............................................................................20

1.3

Environmental Impact Assessment History............................................21

1.4

Ecologically Sustainable Development ...................................................22

1.5

Territory 2030 Strategy..............................................................................24

The Proposal ......................................................................................................25


2.1

The Proponent ...........................................................................................25

2.2

Project description ....................................................................................25

2.2.1

Offshore infrastructure ...............................................................27

2.2.2

Nearshore infrastructure ............................................................28

2.2.3

Onshore infrastructure ...............................................................28

2.3
2.3.1

Dredging.......................................................................................29

2.3.2

Installation of nearshore infrastructure ....................................30

2.3.3

Installation of onshore infrastructure .......................................31

2.4
3

Construction activities ..............................................................................29

Operational activities ................................................................................32

Regional Setting ................................................................................................38


3.1

Physical ......................................................................................................38

3.2

Biological....................................................................................................39

3.3

Socio-economic .........................................................................................40

3.4

Cultural/Historical......................................................................................40

Environmental Impact Assessment .................................................................42


4.1

Introduction................................................................................................42

4.2

Issues outside the scope of the assessment..........................................43

4.3

Alternative options ....................................................................................45

4.3.1

Product loading jetty...................................................................45

4.3.2

Dredge spoil disposal .................................................................47

4.3.3

Shipping Channel and Walker Shoal.........................................48

4.4

Walker Shoal Impacts................................................................................50

4.5

Dredging and dredge spoil disposal........................................................51

4.5.1

Predictive modelling ...................................................................51

4.5.2

Habitat mapping ..........................................................................54

4.5.3

Establishing zones of impact.....................................................55

4.5.4

Sensitive marine habitats (corals and seagrass) .....................56

4.5.5

Maintenance dredging requirements ........................................57

4.5.6

Darwin Harbour dredging policy................................................58

4.6

Biodiversity impacts..................................................................................58

4.6.1

Underwater noise ........................................................................58

4.6.2

Vessel collision and dredge entrainment .................................62

4.6.3

Cumulative marine impacts........................................................64

4.6.4

Shorebirds / Wader birds............................................................65

4.6.5

Barramundi ..................................................................................66

4.6.6

Mud crabs ....................................................................................67

4.6.7

Significant terrestrial habitats....................................................67

4.7

Emissions, discharges and wastes .........................................................69

4.7.1

Hydrotest water ...........................................................................69

4.7.2

Waste water discharge ...............................................................70

4.7.3

Oil Spills .......................................................................................73

4.7.4

Noise.............................................................................................74

4.7.5

Air emissions...............................................................................75

4.7.6

Greenhouse gas emissions........................................................76

4.8

Cultural impacts.........................................................................................80

4.9

Socio-Economic impacts ..........................................................................82

4.9.1

Impact on housing market..........................................................83

4.9.2

Accommodation strategy ...........................................................84

4.9.3

Cost of living................................................................................84

4.9.4

Employment.................................................................................85

4.9.5

Health ...........................................................................................85

4.9.6

Impact of temporary workforce..................................................86

4.9.7

Tourism ........................................................................................86

4.9.8

Visual Amenity.............................................................................87

4.10

Infrastructure and services ........................................................88

4.10.1

Road and Traffic Impacts ...........................................................88

4.10.2

Water supply................................................................................88

4.11

Safety hazards .............................................................................89

4.12

Decommissioning .......................................................................90

4.13

Environmental Management Program.......................................91

Conclusion .........................................................................................................95

References: ........................................................................................................96

Appendix 1................................................................................................................97

Glossary
AAPA

Aboriginal Areas Protection Authority

AFANT

Amateur Fishermans Association of the NT

AHD

Australian Height Datum

AIMS

Australian Institute of Marine Science

aMDEA

activated methyldiethanolamine

AMSTECI

Association of Mitigation Studies for Top End Cyclones Inc.

ANZECC

Australian and New Zealand Environment Conservation Council

CEMP

Construction Environmental Management Plan

CH4

Methane

CO2

Carbon dioxide

CPF

Central Processing Facility - offshore

CSD

Cutter-suction dredge

DCC

Darwin City Council

DCM

Department of the Chief Minister (NT Government)

DHAC

Darwin Harbour Advisory Committee

DoR

Department of Resources (NT Government)

DPC

Darwin Port Corporation

DPI

Department of Planning and Infrastructure (NT Government)

draft EIS

draft Environmental Impact Statement

EA Act

NT Environmental Assessment Act (1982)

EAAP

NT Environmental Assessment Administrative Procedures (1984)

ECNT

Environment Centre NT

EIA

Environmental Impact Assessment

EIS

Environmental Impact Statement, consisting of the draft EIS and the


Supplement (to the draft EIS)

EH Division

Environment and Heritage (EH) Division, of NRETAS

EMP

Environmental Management Plan

EPA

Environment Protection Authority of the Northern Territory

EPL

Environment Protection Licence under the WMPC Act

EPBC Act

Australian Environment Protection and Biodiversity Conservation Act


(1999)

ESD

Ecologically Sustainable Development

FEED

Front-End Engineering Design

FIFO

Fly-in, fly-out

FPSO

Floating production, storage and offtake facility - offshore

GHG

Greenhouse gas

GSP

Gross State Product

HIA

Health Impact Assessment

HSE

Health, Safety and Environment

H2S

Hydrogen sulphide

JPDA

Joint Petroleum Development Area

LAT

Lowest astronomical tide

LDC

Larrakia Development Corporation

LNG

Liquefied Natural Gas

LPG

Liquefied Petroleum Gas

MEG

Monoethylene Glycol

MOF

Materials offloading facility

NES

Matters of National Environmental Significance (EPBC Act)

NLC

Northern Land Council

NOx

Oxides of Nitrogen

N2O

Nitrous Oxide

NRETAS

Department of Natural Resources, Environment, the Arts and Sport


(NT Government)

NT

Northern Territory

NOI

Notice of Intent

OEMP

Operational Environmental Management Plan

OSCP

Oil Spill Contingency Plans

QRA

Quantitative Risk Assessment

Responsible Minister
NT Minister for Lands and Planning
RO

Reverse osmosis

SEL

Sound Exposure Level

SEWPaC

Australian Government Department of Sustainability, Environment,


Water, Population and Communities

SIMP

Social Impact Management Plan

SOx

Oxides of Sulfur

SO2

Sulfur Dioxide

Supplement

Supplement to the draft Environmental Impact Statement

the Minister

NT Minister for Natural Resources, Environment and Heritage

the Project

Ichthys Gas Field Development Project

the proponent

INPEX Browse Ltd

TPWC Act

Territory Parks and Wildlife Conservation Act

TSHD

Trailer suction hopper dredge

WMPC Act

Waste Management and Pollution Control Act (NT)

WWF

World Wildlife Fund

Units and Symbols


%

Percent

/d

Per day

/h

Per hour

/L

Per litre

dB re 1 Pa

Decibels re 1 micro pascal (underwater noise)

dB(A)

Decibels (A-weighted)

Degrees Celsius

MMbbl

Million barrels

ms

Millisecond

ha

Hectare

kg

Kilogram

km

Kilometre

km2

Square kilometre

Litre

Microsecond

Metre

Cubic metre

m3/h

Cubic metres per hour

Million
3

Mm

Million cubic metres

mg

Milligram

ML

Mega litres

mm

Millimetre

MPa

Mega Pascals

Mt

Mega tonne

Metric tonne

Definitions
CO2-equivalent: A unit of greenhouse gas emissions calculated by multiplying the
actual mass of emissions by the appropriate Global Warming
Potential. This enables emissions of different gases to be added
together and compared with CO2.
dB(A): decibels, A-weighted scale; unit used for most measurements of
environmental noise; the scale is based upon typical responses of the human
ear to sounds of different frequencies.
PM10: The fraction of dust with a particle size of 10 m or less; a health indicator for
the fine particles of respirable dust capable of being inhaled into the lungs.

This page is intentionally blank

Executive Summary
Environmental impact assessment (EIA) is the process of defining those elements of
the environment that may be affected by a development proposal and analysing the
risks associated with the potential impacts that have been identified. This
Assessment Report (the Report) assesses the environmental impact of the Ichthys
Gas Field Development Project, Blaydin Point (the Project).
The EIA process effectively allocates risk between the proponent, the government
and the community. Some risks associated with this project will be temporary, for
example some construction risks and some of the risks associated with sediment
from dredging. Some impacts will be permanent, for example the visual impact and
changes to the sea floor due to dredging. Some impacts, for example greenhouse
gas emissions will be ongoing. Complex impacts, for example, the precise nature of
the impacts from dredging are not predictable and so will need to be carefully
monitored and adaptively managed. A series of treatments for some of the more
complex risks are described below in this summary. Initially 17 management plans
are recommended to ensure that risks are minimised. These treatments will ensure
that the proponent will be able to minimise impacts, that Government will be able to
monitor and control uncertainties and the public will be informed of the Project as it
develops.
INPEX Browse Ltd (INPEX) proposes to develop the Ichthys Field in the Browse
Basin off the north-west coast of Australia to produce liquefied natural gas (LNG),
liquefied petroleum gas (LPG) and condensate.
The proposal includes the
installation and operation of offshore extraction and processing facilities in the
Ichthys Field, an onshore liquefaction (LNG) and fractionation (LPG) facility at
Blaydin Point, Darwin, and a 935km pipeline to transport the gas from the offshore
facilities to the onshore facilities.
The Project has been assessed jointly by the Northern Territory Government under
the Environmental Assessment Act 1982 and the Australian Government under the
Environment Protection and Biodiversity Conservation Act 1999. The Northern
Territory Government was responsible for assessing the nearshore and onshore
aspects of the proposal. Some assessment overlap with matters of national
environmental significance occurred where species were listed under both NT and
Commonwealth legislation. The Northern Territory Government led the assessment
on these matters.
This Report forms the basis of advice to the Minister for Natural Resources,
Environment and Heritage on the environmental issues associated with the project.
The Minister is required to make comment and/or recommendations with regard to
the proposal to the Minister for Lands and Planning (the responsible Minister) in the
first instance.
The Report is based on a review of the draft Environmental Impact Statement (draft
EIS), Supplement to the draft EIS (Supplement), and comments from the public and
Northern Territory Government agencies on the draft EIS. Government guidelines
and Government and public responses to the EIS have been rigorous and the
Supplement responded accordingly. There is still a lack of data to fully assess all
impacts so a comprehensive environmental management program, comprising a
series of management plans and targeted projects, will need to be implemented to
monitor and minimise impacts.

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65

The following plans will be important in mitigating risks associated with the project:

Acid Sulfate Soils Management Plan

Air Emissions Management Plan

Bushfire Prevention Management Plan

Cetacean Management Plan

Decommissioning Management Plan

Dredging and Dredge Spoil Disposal Management Plan

Heritage Management Plan

Greenhouse Gas Management Plan

Liquid Discharges, Surface Water Runoff and Drainage Management Plan

Onshore Spill Prevention and Response Management Plan

Piledriving Management Plan

Blasting Management Plan

Quarantine Management Plan

Social Impact Management Plan

Traffic Management Plan

Vegetation Clearing, Earthworks and Rehabilitation Management Plan

Waste Management Plan

This Project has garnered the greatest number of public submissions of any project
assessment in the NT. Comments received were not just about Project specifics but
more broadly demonstrated the complex tensions between peoples aspirations for
Darwin Harbour and the region, and the very considerable economic opportunity
offered by such a development.
Recommendations arising from this assessment address methods to identify,
mitigate and offset environmental impacts as far as possible.
Major Issues
This Project assessment has considered a wide range of factors and community
interests in analysing the potential impacts associated with such a large and complex
development. The major issues associated with the Project, and measures identified
to address them, are:

The levels of uncertainty that exist in predicting the extent and nature of potential
impacts due to the need for data specific to Darwin Harbour. There is significant
uncertainty associated with the effects of Project activities in the nearshore
environment such as dredging, dredge spoil disposal and blasting. Further
modelling, collection of baseline information and intensive monitoring by the
proponent is required to determine the significance of, and appropriate responses
to, key impacts. This will be expressed through a dredging plan and other
monitoring and management activities which need to be approved by
Government.
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65
10

The potential for dredging and dredge spoil disposal to significantly impact the
ecological communities of the nearshore environment in Darwin Harbour and the
regional coastline. The majority of impacts from these activities are likely to be
temporary and some degree of recovery in affected ecosystems is expected. The
extent and timing of recovery is, however, uncertain. There will also be
permanent changes to the Harbour within and directly adjacent to the dredged
footprint. The proponent is required to monitor the activities and implement
adaptive management actions to ensure impacts remain within predicted,
acceptable levels through a dredging plan to be approved by Government, and
other management plans and monitoring and research activities.

The potential for a sustained increase in underwater noise associated with


Project activities to affect iconic species in the Harbour, particularly coastal
dolphins. It is expected that Project activities will challenge these species, adding
pressure to their small and susceptible populations in the Harbour. Research
funding, further demonstration of mitigation methods and a relevant offset have
been recommended, particularly if the proponent is required to blast.

The proposed discharge to Darwin Harbour of contaminated waste water,


particularly sewage, on an ongoing basis for the life of the Project. Further
investigation of land-based disposal options is expected in the first instance. The
proponent will require a licence under the Waste Management and Pollution
Control Act to discharge contaminants at levels that must meet water quality
objectives for the Harbour.

The potential cumulative impacts on Darwin Harbour and regional marine


ecosystems from Project activities. The construction period for the Project is
lengthy and when combined impacts of underwater noise, movement of vessels,
turbidity and sedimentation and dredging activity over a sustained period has the
potential to be considerably greater. Added to permanent loss or modification of
habitat in the Harbour, such as the removal of Walker Shoal on the basis that it
reduces risks associated with damage to ships, and ongoing operational impacts,
the effects are difficult to predict. It is expected that there will be significant
residual detriment to the Harbour and the proponent is expected to implement
relevant programs to minimise and/or offset this detriment.

The significant greenhouse gas (GHG) emissions from Project operations. The
Proponent has committed to a number of technical abatement options to reduce
GHG emissions. Emissions will, however, be significant from a Northern Territory
and national perspective. Large scale GHG reductions could potentially be
achieved through geosequestration or offsets. GHG emissions will be regulated
by licence under the NT Waste Management and Pollution Control Act until
appropriate national regulation to reduce GHG emissions is in place. Regulation
will be informed by a Greenhouse Gas Management Plan, which is expected to
prominently feature commitments to GHG offsets.

The risk of negative social impacts such as the extra load on health and police
services, the cost of living, and housing affordability. A social impact
management plan developed by the proponent in collaboration with Government
is considered the appropriate mechanism to manage these risks and to ensure
that the benefits of the Project are maximised.

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65
11

Conclusions
The environmental impacts of the project can be managed by delivering the
commitments made in the EIS and the Supplement and by rigorously applying the
recommendations and management plans and strategies described in this
assessment.
Although the likely impacts of the Project have been identified and are relatively well
understood, there remains a high level of uncertainty in terms of the precise nature
and extent of impacts and changes, particularly to the ecology of Darwin Harbour and
the region. This uncertainty is largely due to the gaps in data informing the
environmental impact assessment process. Consequently, the proponent,
government and community will be reliant on intensive, post-assessment monitoring
to determine the significance of, and appropriate responses to, key impacts. These
monitoring requirements are captured in the commitments made by the proponent
and recommendations of this Report.
The less predictable impacts such as the modification of habitats and cumulative
effects on significant species in the Harbour will need to be managed to an
acceptable level. The proponent should demonstrate that it can achieve this by fully
implementing its management program with effective monitoring and appropriate
adaptive management tools. These programs will need to be rigorous and based on
sound, scientific information, and form the basis for relevant regulatory approvals.
Given the high profile of this Project, it is essential that the community are kept
informed of ongoing monitoring programs and the implementation of required
management actions.
This Report identifies areas where, despite efforts to mitigate impact, residual
environmental detriment is anticipated, such as the loss of monsoon vine forest and
the cumulative effects of the Project on significant marine biota in Darwin Harbour.
The proponent will be expected to implement appropriate offsets to reduce this
residual detriment or improve protection for relevant environmental aspects
elsewhere.
Based on its review of the EIS and the proponents response to submissions from
relevant Northern Territory Government agencies, affected stakeholders and the
public, and an understanding of the economic benefits of the project, the
Environment and Heritage Division considers that the project can be managed within
the bounds of acceptable environmental impacts, provided that the environmental
commitments, safeguards and recommendations detailed in the EIS, this
Assessment Report and in the final management plans are implemented and
managed under the environmental management program for the project and are
subject to regular reporting and compliance auditing.

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65
12

List of Recommendations
Recommendation 1
The proponent shall ensure that the proposal is implemented in accordance
with the environmental commitments and safeguards:
Identified in the Ichthys Gas Field Development Projects Environmental
Impact Statement (draft EIS and Supplement); and
Recommended in this Assessment Report.
All safeguards and mitigation measures outlined in the Environmental Impact
Statement are considered commitments by INPEX Browse Ltd and its joint
venture partners.
Recommendation 2
The proponent shall advise the Minister of any changes to the proposal in
accordance with clause 14A of the Environmental Assessment Administrative
Procedures, for determination of whether or not further assessment is
required.
Recommendation 3
Further hydrodynamic and sediment transport modelling on a refined dredging
proposal is required in consultation with the dredging contractor.
Recommendation 4
Prior to the commencement of dredging, INPEX should conduct particle tracer
studies based on the expected dredge spoil characteristics to validate the
modelling predictions for fate of dredged sediments during dredging in the
Harbour and offshore spoil disposal.
The studies should account for variations in tidal cycles.
Recommendation 5
The dredging and dredge spoil disposal management plan is to be informed by
the hydrodynamic modelling and sediment transport modelling, and particle
tracer studies. The plan should include monitoring of sedimentation and water
quality and appropriate ecological indicators. Contingencies to manage
dredging in the event that there is a significant departure from predicted
impacts need to be specified in the plan. The plan should be developed in
consultation with an expert panel (in accordance with Recommendation 24).
Long term monitoring of the spoil ground to determine the dispersion and fate
of this spoil over an appropriate timeframe should be included in the
management plan.

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65
13

Recommendation 6
An ecological monitoring program must be developed in consultation with
NRETAS and an expert panel (in accordance with Recommendation 24) to
detect impacts on significant biological communities associated with dredging
and dredge spoil disposal.
Recommendation 7
A reactive monitoring program must be developed in consultation with
NRETAS and an expert panel (in accordance with Recommendation 24) to
respond to dredging and spoil disposal impacts on significant communities.
The program should include:
Monitoring of appropriate coral species;
Monitoring of sediment plume impacts on existing sea grass communities
in the Harbour;
Water quality parameters that account for spatial variability of turbidity,
typical for the macrotidal environment of the Harbour;
Continuation of INPEXs current water quality program to improve the
association between logger turbidity and sample sediment concentrations;
Determination of appropriate trigger values of turbidity and sediment
concentration for biodiversity protection;
Monitoring of sedimentation rate; and
Appropriate contingency measures where impact is detected.
Recommendation 8
If INPEX must implement the drill and blast contingency for removing hard
rock, a management plan to protect coastal dolphins, dugongs and turtles
must be developed in consultation with NRETAS and an expert panel (in
accordance with Recommendation 24). The management plan must
demonstrate, through sound scientific studies, the effectiveness of measures
to minimise risks, detect fauna and manage impacts.
Recommendation 9
INPEX will continue to fund and support research into coastal cetaceans in
Darwin Harbour and the wider region to determine the importance of Darwin
Harbour for the regional coastal cetacean population and the potential impacts
of the Project, particularly drill and blast if it is to be used, on these
populations.

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65
14

Recommendation 10
Relevant EMPs are to be amended to include measures for minimising vessel
interactions / collisions with dolphins, turtles, dugongs and other large marine
fauna. The relevant plans should include:
details on procedures to reduce the risk of vessel strikes on large marine
vertebrates (marine turtles, dugongs and cetaceans) such as speed limits;
requirements for installation of propeller guards on vessels associated with
the Project;
details on procedures for monitoring and reporting of vessel strikes on
large marine vertebrates; and
plans to monitor for stranded, injured or dead large marine vertebrates.
Recommendation 11
In managing marine turtles during dredging activities, the dredging and dredge
spoil disposal management plan should:
Include details on procedures to manage and monitor entrainment of
marine turtles; and
Include details for monitoring of stranded turtles at the time of dredging
and ensure the involvement of NRETAS Marine Wildwatch.
Recommendation 12
An appropriate offset is necessary to compensate for the residual detriment
posed by Project activities to the ecological communities and marine fauna
within Darwin Harbour. The scale of offset should be commensurate with the
scale of residual detriment. If blasting is required, the offset must be increased
to compensate.
Recommendation 13
A monitoring program must be developed in consultation with NRETAS and an
expert panel (in accordance with Recommendation 24) for sedimentation in
mangrove communities of Darwin Harbour. The program should be informed
by the sediment transport modelling and particle tracer studies and be
included in the dredging and dredge spoil disposal management plan.
Recommendation 14
An offset for loss of monsoon vine forest on Blaydin Point is recommended. All
activities associated with offsetting the residual detriment of clearing monsoon
vine forests should:
be in perpetuity; and
include a management plan that demonstrates environmental benefits.

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65
15

Recommendation 15
Appropriate controls to mitigate risks from hydrotesting waste water must be
included in the Liquid Discharges, Surface Water Runoff and Drainage
Management Plan for Government approval. In preparing the plan, INPEX
should also:
Investigate options for land-based disposal where practicable; and
Select chemical additives that have the lowest practicable risk to the marine
environment.
Recommendation 16
An air monitoring program is required for the life of the Project. The program
will be developed as a requirement of the Environment Protection Licence
under the Waste Management and Pollution Control Act.
The following point-source emissions testing should be conducted for the
program:
Quarterly monitoring for the first year of operation and annual thereafter for
NOx (plus temperature, flow, O2, moisture) at each stack servicing the
compressor turbines, power turbines, and hot oil heaters; and
Quarterly monitoring for the first year of operation and annual thereafter for
SO2 (plus temperature, flow, O2, moisture) at each stack servicing the acid
gas incinerators.
Recommendation 17
That INPEX submit to the Northern Territory Government a Greenhouse Gas
Management Plan covering onshore GHG emissions prior to commissioning of
the onshore gas processing plant. The GHG Management Plan should be
submitted within a timeframe that enables its consideration in the issue of an
Environment Protection Licence under the Waste Management and Pollution
Control Act.
Recommendation 18
That the Greenhouse Gas Management Plan include, but not necessarily be
limited to, the following:
An updated greenhouse gas inventory for the proposal;
Measures adopted to mitigate greenhouse gas emissions;
Demonstration of the adoption of current best practice in the design and
operations of the onshore gas processing plant in terms of GHG emissions
by benchmarking technology against other national and overseas facilities;
Commitments to periodic review and, where practicable, continuous
improvement in technology and operational process to further mitigate
GHG emissions per tonne of LNG produced;
A report on the status of investigations into geosequestration; and

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65
16

Commitments to measures to offset the GHG emissions from the onshore


gas processing plant, preferably including measures implemented in the
Northern Territory.
Recommendation 19
INPEX should conduct a diver inspection/verification of anomalies identified in
the data from remote sensing surveys.
Additionally, to ensure the dredging footprint is adequately surveyed for
unlocated maritime heritage, INPEX should consider:
providing previously unavailable remote sensing raw data for further
analysis; and
Completing the magnetometer survey of the navigation channel, turning
basin, berthing pocket and MOF footprint in Darwin Harbour.
Recommendation 20
A Social Impact Management Plan (SIMP) is to be developed by INPEX in
collaboration with NT Government. The SIMP must address social issues that
have been raised in the EIS and this assessment report. The SIMP should also
be informed by the outcomes of a Health Impact Assessment undertaken as
part of the accommodation village assessment process.
Recommendation 21
The Blaydin Point gas facility must incorporate best-practice water
conservation measures into the design. The proponent must commit to
continuous improvement in minimising potable water use.
Recommendation 22
Prior to decommissioning, the proponent should lodge a notice with the
Minister for the Environment (or the appropriate authority at the time of
decommissioning) for assessment under the relevant legislation at the time
outlining the proposed action and its significance to the environment.
Recommendation 23
All Environment Management Plans for the Ichthys Gas Field Development
Project are to be submitted to Government for approval prior to
commencement of any works for which the plans apply.
In preparing each plan, the proponent will include any additional measures for
environmental protection and monitoring contained in this Assessment Report
and Recommendations. The plans shall be referred to relevant Northern
Territory Government agencies and key stakeholders for review prior to
finalisation. The plans shall form the basis for approvals and licences issued
under relevant legislation.
The proponent should provide public access to final environmental
management plans and a reporting mechanism to inform compliance with the
plans.
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65
17

Recommendation 24
An expert panel should be formed to provide objective and expert support in
the development of appropriate management plans and monitoring programs
for dredging and dredge spoil disposal, and for blasting if required, as
recommended in this Report. The final form of the expert panel will be
determined in agreement between Government and the proponent.

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65
18

1 Introduction and Background


This report assesses the environmental impact of the Ichthys Gas Field Development
Project, Blaydin Point (the Project).
INPEX Browse Ltd (INPEX) proposes to develop the Ichthys Field in the Browse
Basin off the north-west coast of Australia to produce liquefied natural gas (LNG),
liquefied petroleum gas (LPG) and condensate.
The proposal includes the
installation and operation of offshore extraction and processing facilities in the
Ichthys Field, an onshore liquefaction (LNG) and fractionation (LPG) facility at
Blaydin Point, Darwin, and a 935km pipeline to transport the gas from the offshore
facilities to the onshore facilities.
This Environmental Assessment Report (the Report) is based on a review of the draft
Environmental Impact Statement (draft EIS), Supplement to the draft EIS
(Supplement), and comments from the public and Northern Territory Government
agencies on the draft EIS. The draft EIS and Supplement are collectively referred to
as the EIS.
The EIS can be viewed on the Department of Natural Resources, Environment, the
Arts and Sport (NRETAS) website at:
http://www.nt.gov.au/nreta/environment/assessment/register/inpex/index.html

1.1 Environmental Impact Assessment Process


Environmental impact assessment (EIA) should:

identify potential impacts on the environment (where environment is defined


broadly according to the Environmental Assessment Act); and

evaluate the risks of those impacts occurring.

Through its assessment of Project risks the proponent must demonstrate:

that these risks can be satisfactorily managed within acceptable levels e.g.
impacts would not result in long term environmental detriment; and

the effectiveness/feasibility of management measures in a precautionary/risk


management framework.

Assessment gives weighted consideration to:

values and risks;

estimation of the likelihood of success of preventative and remedial measures;


and

the validity and comprehensiveness of programs established to provide ongoing


measures of the environmental effects of the proposed development.

This assessment considers that risks can be more reliably evaluated where there is a
substantial baseline of relevant information. Where this information is limited or not
available, risk assessment is inevitably constrained and far less precise, and it is
appropriate to use the precautionary principle in the evaluation of possible impacts. If
potential impacts are understood with a reasonable level of certainty, monitoring
programs can be better informed to detect impacts, and management measures can
be more effectively targeted to address those impacts.
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65
19

This Report evaluates the adequacy of commitments and environmental safeguards


proposed by the proponent to avoid or mitigate the risks of potential impacts
identified in the assessment process. The safeguards may be implemented at
various levels within the planning framework of a project and include (among other
approaches):

Design and layout of buildings and other infrastructure on the site/s;

Management of construction activities; and

Management of processes used in operations of the facility (e.g. inputs and


outputs).

A list of commitments made by the proponent is provided in Chapter 12 of the draft


EIS. Additional safeguards are recommended in this Assessment Report where
appropriate.
The contents of this Report form the basis of advice to the NT Minister for Natural
Resources, Environment and Heritage (the Minister) on the environmental issues
associated with the project.

1.2 Regulatory Framework


Environmental assessment was undertaken in accordance with the requirements of
the Northern Territory Environmental Assessment Act 1982 (EA Act).
The proposal was also declared a controlled action under the Environment Protection
and Biodiversity Conservation Act 1999 (EPBC Act) as it was considered likely to
have significant impacts on the following controlling provisions:

Sections 18 and 18A (Listed threatened species and communities);

Sections 20 and 20A (Listed migratory species); and

Sections 23 and 24A (Commonwealth marine waters).

As the proposal is located partly in Commonwealth waters, the NT and Australian


Governments assessed the project collaboratively rather than under the bilateral
agreement. Assessment was therefore undertaken in accordance with Clause 8 of
the Environmental Assessment Administrative Procedures (EAAP) of the Northern
Territory and to meet the requirements as provided for in Chapter 4 Division 6 of the
EPBC Act of the Australian Government.
Responsibilities within the assessment process were divided between the
jurisdictions as follows:

The Australian Government was responsible for all aspects of the offshore
proposal including the majority of the pipeline route, as well as the matters of
National Environmental Significance (NES) within the nearshore and onshore
portions of the project; and

The Northern Territory Government was responsible for assessing the nearshore
and onshore aspects of the proposal. Some assessment overlap with NES
matters occurred where species were listed under both NT and Commonwealth
legislation. The NT Government led the assessment on these matters.

This Report forms the basis of advice to the Minister on the environmental issues
associated with the project and informs the decision as to whether or not the project
should proceed. The Minister is required to make comment and/or recommendations
with regard to the proposal to the Minister for Lands and Planning (the responsible
Minister) in the first instance.
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65
20

The responsible Minister will then make a determination as to whether or not


development consent in the form of a development permit under the Planning Act will
be issued to INPEX Browse Ltd, to develop the site at Blaydin Point for a LNG gas
processing facility.
As well as a development permit, INPEX Browse Ltd will need to obtain a number of
other permits, licenses and approvals under various Northern Territory legislation
including an Environment Protection Approval and Licence under the Waste
Management and Pollution Control Act (WMPC Act) to construct and operate the
onshore gas facility respectively and a pipeline licence under the Energy Pipelines
Act to construct the gas pipeline through NT Waters to the Blaydin Point facility. The
operation will be licensed as a Major Hazard Facility by NT Worksafe. The Australian
Government Minister for Sustainability, Environment, Water, Population and
Communities (Australian Government Minister) will need to consider the Project for
an approval decision under the EPBC Act.
A more complete list of Government approvals and relevant legislation for the
regulation of the proposal is provided in Table 1-2, Chapter 1 of the draft EIS. It must
be noted that the most appropriate legislative process for undertaking some of the
construction activities in the nearshore environment, including dredging, dredge spoil
disposal and blasting, is still being determined.

1.3 Environmental Impact Assessment History


On 28 March 2008, INPEX Browse Ltd (INPEX) submitted a Notice of Intent for the
Ichthys Gas Field Development Project, Blaydin Point to the Minister. On 29 April
2008, the Minister determined that the project required formal assessment at the EIS
level. Draft Guidelines were prepared and advertised on 18 August 2008 and
underwent a 3-week public exhibition period. This extended period was to
accommodate the swearing in of new ministers following the 2008 Northern Territory
election. Final EIS Guidelines were issued to the proponent on 17 September 2008.
The draft EIS for the project underwent an 8-week public exhibition period from
15 July 2010 until 9 September 2010. A total of 1488 submissions were received on
the draft EIS. The majority (1353 submissions) were template submissions generated
from the Australian Marine Conservation Society web site.
From the public and Government submissions received, a range of issues were
identified associated with specific technical aspects of the Project and its
environmental impacts, as well as broader community issues such as employment
and social infrastructure needs. There were also statements of support for the project
and acknowledgement of its perceived benefits from some organisations. Issues
have been grouped broadly into the following categories:

Biodiversity impacts;

Noise;

Risk;

Value to NT society;

Alternative locations / proposals;

Pollution and waste;

Greenhouse gas emissions;

Regulatory responsibility and cost;


Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65
21

Site rehabilitation;

Resource use;

Provision of supporting infrastructure;

Blasting and dredging;

Sedimentation;

Social Impacts on Darwin region;

Sustainability;

Offsets;

Adequacy/quality of information contained in the draft EIS; and

Impacts on tourism.

A more detailed list of issues raised is included in Appendix 1 of this Report.


INPEX lodged the Supplement in response to the submissions with the Environment
and Heritage Division (of NRETAS) (EH Division) on 6 April 2011. The Supplement
was circulated amongst Government agencies for comment and INPEX then
published the Supplement in accordance with EPBC Act requirements on 19 April
2011. The Minister advised the proponent that he would extend the assessment
period beyond the standard 35 days under clause 14(4)(c) of the EAAP. This
extension accounted for a number of public holidays that fell within the assessment
period. The EH Division prepared this Report, and provided the Report to the
Minister. The Minister issued final advice and recommendations on the project to the
responsible Minister and the Australian Government Minister on 17 May 2011, 42
calendar days after receipt of the Supplement.

1.4 Ecologically Sustainable Development


The Australian Government affirmed its commitment to sustainable development at
United Nations conferences on environment and development, notably via the Rio
Declaration and Agenda 21 in 1992 and the Johannesburg Declaration at the United
Nations 2002 World Summit. Australia reaffirmed its commitment at the Summit to
promote the integration of the three components of sustainable development
economic development, social development and environmental protectionas
interdependent and mutually reinforcing pillars.
Australia developed the National Strategy for Ecologically Sustainable Development
(ESD) identifying four national principles. The Strategy also identified ways to apply
the principles to a range of industry sectors and issues such as climate change,
biodiversity conservation, urban development, employment, economic activity, and
economic diversity and resilience.
In December 1992 the NT Government endorsed the National Strategy and agreed,
along with all other States and Territories, to the Intergovernmental Agreement on
the Environment.
The Strategy defines ESD as:
Using, conserving and enhancing the communities resources so that ecological
processes, on which life depends, are maintained and the total quality of life now and
in the future can be increased.
ESD is development that aims to meet the needs of Australians today, while
conserving our ecosystems for the benefit of future generations.
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65
22

The NT Environment Protection Authority (EPA) has defined six principles of ESD for
the Northern Territory (NT EPA 2010). In addition to the four national principles (to
which the NT is already a signatory) the EPA recommended the principles of
integration as well as public participation. The NT Government is considering the
EPAs recommendations.
The principles of ESD as defined in the National Strategy are:
ESD Principle

Definition

Precautionary principle

Where there are threats of serious or


irreversible environmental damage, lack
of full scientific certainty should not be
used as a reason for postponing
measures to prevent environmental
degradation.

Inter- and intra-generational equity

The present generation should ensure


that the health, diversity and productivity
of the environment is maintained or
enhanced for the benefit of present and
future generations.

Conservation of biological diversity and


ecological integrity

The conservation of biological diversity


and ecological integrity should be a
fundamental consideration in decisionmaking

Improved valuation, pricing and incentive


mechanisms

Should be promoted to ensure that the


costs of environmental externalities are
internalised and that the polluter bears
the costs associated with environmental
pollution.

In response to the draft EIS, some submissions raised issues relating to the
application of ESD principles specifically the precautionary principle (where data
collection was perceived to be lacking), and the principle of biodiversity conservation
(in respect to vegetation removal and potential impacts to marine biodiversity).
The EPBC Act requires that in considering economic and social matters, the Minister
must take into account the principles of ESD. The Supplement states that INPEX
recognises that it has a responsibility to support these principles and that it has a
duty of care both to the natural environment and to the communities in which it
operates.
INPEX has included in the Supplement a discussion of the Projects consistency with
goals and principles of ESD (Section 4.12, page 156). It refers to examples of where
the principles of ESD have guided INPEXs project planning (to minimise
disturbance), its approach to information and data collection (drawing upon the
precautionary principle), and INPEXs public participation and consultation in
developing the Project.
To achieve the objective of ESD, the Project needs to continually be informed and
guided by the ESD principles. Accordingly, the assessment of this proposal, its
potential impacts (positive and negative) and the management measures used to
enhance positive and reduce negative impacts will be undertaken in the context of
ESD principles.
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65
23

Subsequent decision-making processes by approval bodies also need to be guided


by ESD principles and the continued project design and development, as well as the
development and implementation of management and monitoring programs by
INPEX, should all aim to meet the objective of ESD.

1.5 Territory 2030 Strategy


Territory 2030 is a 20-year strategic plan for the Northern Territory developed by an
independent Steering Committee and launched on 3 December 2009.
The Territory 2030 Strategic Plan was produced as a road map for the future.
Developed in consultation with the Territory community, Territory 2030 is a means to
setting priorities and guiding governments efforts over the next two decades.
As the principal policy document for the NT it is appropriate that the Project is
considered and assessed within the framework of Territory 2030. Identified as one of
the issues requiring immediate focus is the priority kick-starting key projects and
initiatives, recognising the lasting difference of key initiatives and projects to the
community because of their ability to create benefits beyond their initial investment.
The INPEX project is recognised as bringing economic opportunity to the Northern
Territory and Australia it is anticipated that the NT Gross State Product (GSP)
would experience an average increase of about 18% each year and the project would
create significant new employment opportunities, generating considerable growth in
exports and a stronger balance of trade, and further stimulating economic activities
and industry development.
The Territory 2030 document also identifies a wellbeing framework as a key
initiative for the NT suggesting a balanced decision making model that considers the
economic, social and environmental impacts of every funding and policy decision
made by government. The Territory 2030 document brings together targets across a
range of priority areas (education; society; economic sustainability; health and
wellbeing; the environment; and knowledge, creativity and innovation). This ensures
that policy and decision-makers critically examine the tensions that exist between
and across some of the targets. Accordingly, when decisions are made, all impacts
(positive and negative) across targets are taken into consideration.
It is appropriate to apply these same decision making principles when making an
assessment and decision on the INPEX project. Where appropriate, the Report will
draw from, and refer to, the targets contained in the Territory 2030 document when
reviewing and assessing the key elements of the INPEX proposal.
Importantly, Territory 2030 is, over the medium to longer term, intended to work as a
whole-community plan. Accordingly, it is anticipated that the private and community
sectors will share ownership of, and become directly involved in, progressing targets
within the plan. Industries and organisations will be encouraged to own targets and
contribute to them in meaningful ways. This provides the opportunity for INPEX to
offset some of the challenges that arise through its Project by contributing to other
targets (such as employment, and investment in green energy targets to overcome
increases in emissions).

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65
24

2 The Proposal
2.1 The Proponent
INPEXs parent company INPEX CORPORATION has been involved in the
development of oil and gas resources for more than four decades and has been
steadily increasing its exploration and development activities in many countries
around the world. It is, for example, currently taking part in a number of projects in
Australian waters. These include the Van Gogh and Ravensworth oil extraction
projects in the southern part of the North West Shelf in Western Australia, and, until it
ceased production in October 2009, the nearby Griffin Fields oil and gas project.
INPEX is also a partner in the BayuUndan oil and gas project in the Timor Sea Joint
Petroleum Development Area (JPDA).
In early 1998, INPEX CORPORATION (as Indonesia Petroleum, Ltd.) bid for a
petroleum exploration permit for permit area WA-285-P in the northern Browse Basin
about 200km off Western Australias Kimberley coast, at the western edge of the
Timor Sea. This petroleum exploration permit was awarded to INPEX
CORPORATION on 19 August 1998. The subsidiary company INPEX Browse, Ltd.
was established immediately after the grant of the permit and became the permit
holder, 100% equity holder and Operator.
The companys drilling program from March 2000 to February 2001 in the
north-western portion of the permit area resulted in a significant gas and condensate
discovery in the Ichthys Field. Shortly afterwards INPEX commenced the Ichthys Gas
Field Development Project.
In August 2004 the original permit expired and a new permit, WA-285-P R1, was
issued for a reduced area.
In 2006 INPEX transferred a 24% participating interest in the Project to Total E&P
Australia (Total). Total has had a long-standing partnership with INPEX elsewhere in
the world and also has experience with LNG and LPG projects in other countries.
In September 2009 Retention Lease WA-37-R was awarded to INPEX as the
Operator of the Ichthys Field. The area covered by the lease is approximately
912km2.

2.2 Project description


The Ichthys Field is located within the WA-285-P exploration permit area in the
Browse Basin, 440km north of Broome and 800km south-west of Darwin. It is an area
of approximately 800km2 with water depths ranging from 90m to 340m.
Estimates of the recoverable hydrocarbon resource indicate over 10 trillion cubic feet
of gas and around 300 million barrels (MMbbl) of condensate. INPEX expects that
approximately 25 million tonnes (Mt) of LPG will be extracted from this gas during
gas processing. The carbon dioxide content averages 8.6% in the Brewster Member
and 16.8% in the Plover Formation.
It is proposed that the hydrocarbon gas and liquids be extracted from up to 50 subsea wells to a floating platform or central processing facility (CPF), in-situ.
Condensate and produced formation water would be transferred from the CPF to a
Floating Production and Storage Offloading vessel (FPSO). Condensate would be
stabilised and stored within the FPSO for periodic offloading to export tankers.
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65
25

Produced formation water would be treated at the FPSO to meet regulatory


requirements and disposed of offshore.
Gas with a small quantity of condensate would be transported from the CPF via
subsea pipeline (approximately 930km) to an onshore gas processing facility at
Blaydin Point on Middle Arm Peninsula in Darwin Harbour.
The submerged pipeline is proposed to follow the Bayu-Undan pipeline route through
Darwin Harbour. It would then continue past Wickham Point before approaching a
suitable shore crossing point where it would proceed east onshore through Middle
Arm Peninsula to Blaydin Point. The sub-sea pipeline would be trenched and
possibly rock-armoured to ensure stability and protection and suitable subtidal sands
may be required as bedding and backfill material.
The gas processing facility proposal consists of the following components:

A gas reception area;

Two LNG liquefaction trains;

An LNG fractionation plant;

A condensate stabilisation plant;

Gas turbines for power generation;

LNG, LPG and condensate storage facilities;

A product offloading jetty;

Emergency gas flare systems (ground flares);

A materials offloading facility (MOF);

A wastewater treatment plant; and

Roads, utilities and other infrastructure (workshops, office, control room, storage,
etc).

Liquids (condensate and LPGs) would be separated and processed, and gas treated
and liquefied. All products would then be stored for later export via an offloading jetty.
Design life of the processing plant would be nominally 40 years with an LNG
processing capacity of approximately 8 Mt/annum.
It is expected that 2-3 tankers of LNG and 1-2 tankers of LPG would be exported
each week, and one condensate ship every month.
Construction activities would include:

Dredging for a navigation channel, ship-turning basin and the pipeline approach.
An estimated 16 million m3 of material could be dredged and would need to be
disposed of in a suitable spoil ground;

Processing facility assembly consisting of the on-site construction of purpose-built


modules and the importation of pre-assembled modules;

Increased shipping movements including heavy-lift vessels and barges, pipelaying vessels and pipe transport barges, cargo ships and dredging vessels. The
MOF would be used for heavy-lift vessels and the East Arm Wharf would be used
for general cargo;

Clearing of approximately 362ha of vegetation, including removal of monsoon


vine forest and infilling of mangroves, at the Blaydin Point site;
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65
26

The import and storage of some earth and rock material to complete earth works.
Borrow material may be sourced from a location on Middle Arm Peninsula.
Concrete batching would also take place on site;

The use of public utilities such as water and electricity for construction and
operation;

Construction of a wastewater treatment plant;

Road transport of construction materials and equipment;

Workforce in the order of 2000 to 3000, primarily fly-in fly-out (FIFO) with local
content where possible, housed in a construction camp external to the Blaydin
Point site, and possibly in residences around Darwin and Palmerston where
available.

Construction and operation of the proposed LNG facility in Darwin would produce the
following waste streams and emissions:

Construction wastes including packaging, waste oils, steel offcuts, putrescibles


and sewage;

Dredge spoil from the initial dredging campaign and maintenance dredging
operations;

Air emissions, including greenhouse gases, such as sulphur oxides, nitrogen


oxides, carbon dioxide, carbon monoxide, methane, particulates, and volatile
organic compounds; and

Hydrotest and treated process waste water discharge into the nearshore
environment.

The offshore component of the proposal would be administered under Australian


Government legislation and the nearshore and onshore facilities under Northern
Territory legislation.

2.2.1 Offshore infrastructure


Subsea infrastructure at the offshore development area will consist of the following:

approximately 50 subsea wells drilled from between 12 and 15 drill centres,


developed over a period of 40 years; and

control umbilicals, service lines and wet-gas, corrosion-resistant infield flowlines.

The subsea infrastructure will be tied back to a floating CPF by a series of flexible
risers, flowlines and umbilicals. The CPF in turn will be connected to a FPSO facility
by a transfer system consisting of flexible risers and flowlines as well as by a
communications umbilical. Both the CPF and FPSO will be moored in position for the
expected 40-year life of the Project.
These facilities will provide the following services:

The CPF will be used for gasliquid separation; gas dehydration; gas export;
future inlet compression; and export of a co-mingled stream of condensate,
monoethylene glycol (MEG) and water to the FPSO (the MEG is used to prevent
the formation of hydrates, primarily between methane and water); and

The FPSO will be used for condensate dewatering and stabilisation, condensate
storage and export, MEG regeneration, and produced-water treatment.

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65
27

The offshore components also include approximately 900km of gas export pipeline
which will connect the offshore infrastructure with the onshore gas facility.
The offshore components of the Ichthys proposal are outside the scope of the
Northern Territory assessment process and will be assessed by the Australian
Government.

2.2.2 Nearshore infrastructure


Nearshore infrastructure will consist of the following:

an approximately 27km length of the subsea gas export pipeline from the mouth
of Darwin Harbour parallel to the existing BayuUndan Gas Pipeline to the
western side of Middle Arm Peninsula (Figure 1);

a pipeline shore crossing on the western side of Middle Arm Peninsula south of
the Darwin LNG pipeline crossing;

a materials offloading facility on Blaydin Point at the mouth of the Elizabeth River
for receiving prefabricated gas-processing modules and some construction
materials;

a product loading jetty on the north-western end of Blaydin Point with one berth
for LNG export and one for LPG and condensate export;

a shipping channel, approach area, turning basin and berthing area for the
product tankers; and

a dredge spoil disposal ground outside Darwin Harbour, 12km north-west of Lee
Point.

Further detail on the nearshore infrastructure for the Project is contained in Chapter
4, Sections 4.3 (gas export pipeline) and 4.4 of the draft EIS.

2.2.3 Onshore infrastructure


Onshore infrastructure will consist of the following:

a 6 km long onshore pipeline corridor from the shore crossing area to the Blaydin
Point gas processing plant site (Figure 2);

a gas reception area with a pig receiver and a slug catcher;

two gas liquefaction trains (each producing approximately 4.2Mt/a of LNG);

gas treatment facilities (for acid gas removal, dehydration, and mercury removal);

a propane and butane fractionation plant;

a condensate stabilisation plant;

utilities distribution and storage (power generation, fuel, water, nitrogen,


compressed air);

storage tanks (two tanks for LNG; two large and one small tank for condensate;
and one tank each for propane and butane) and LNG and LPG recovery units for
boil-off gas;

an emergency gas flare system consisting of a ground flare and enclosed


tankage flares;

a wastewater drainage and treatment system; and


Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65
28

various other installations, including a warehouse, workshops, a fuel storage


area, firefighting facilities, a guard room and security buildings, and a control
room.

Onshore permanent supporting facilities such as communications, security and


administration buildings will be located in a combined operations complex at the end
of the Blaydin Point access road near the causeway area in the central part of Middle
Arm Peninsula.
A more-detailed description of the facilities on Blaydin Point is contained in Chapter
4, Section 4.5 of the draft EIS and updated in Section 3.3 of the Supplement.

2.3 Construction activities


2.3.1 Dredging
INPEX intends to conduct a dredging program within Darwin Harbour. The purpose
of the dredging is as follows:

to extend the existing safe shipping access from the vicinity of East Arm Wharf to
the proposed product loading jetty at Blaydin Point;

to provide a turning basin large enough to permit the safe manoeuvring of ships
that are more than 350m in length overall;

to provide a safe approach and departure area to and from the product loading
jetty;

to provide two berthing pockets at the product loading jetty to accommodate two
product export tankers;

to provide an approach apron with a berthing pocket capable of accommodating


up to four barges at any one time at the module offloading facility area; and

to provide a trench to accommodate the subsea gas export pipeline to Middle


Arm Peninsula.

The dredging program would be carried out by a dredging contractor engaged after
conclusion of the environmental assessment process. Only a limited number of
specialised dredging companies with the capacity to undertake the scale of dredging
required for the Project are available worldwide. Therefore, until the dredging
contractor has been engaged, INPEX have provided conceptual dredging methods
and the dredging program will only be finalised once the contractor has been
appointed.
Preliminary estimates outlined in the draft EIS indicated a total of 16.9Mm3 of
material would be generated during the dredging program. Estimated volumes from
various components originally included:

15.1Mm3 from the shipping channel, turning basin and berthing area (Figure 3);

1.2Mm3 from the module offloading facility (Figure 3); and

0.6Mm3 from the subsea section of the gas export pipeline from the mouth of
Darwin Harbour to Middle Arm Peninsula.

This has been reduced by 1Mm3 due to reduced under-keel clearance requirements
with the revised total now around 16Mm3. The dredged spoil would be transported to
the offshore spoil disposal ground outside Darwin Harbour (Figure 4). A number of
dredging vessels are required and these would operate for 24 hours a day and
7 days a week during specified periods.
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65
29

The draft EIS stated that drilling and blasting would also be necessary to fracture
hard rock intrusions existing within the dredge footprint, which were initially
considered immovable by conventional dredging methods. As discussed later, a drill
and blast program may no longer be required.
Walker Shoal, which lies at the entrance to the proposed shipping channel, is the
most significant of the hard rock intrusions. As the top of the Shoal rises to 4.2m
below lowest astronomical tide (LAT), INPEXs base case is to remove the Shoal to
allow for safe navigation. INPEX explored options to realign the shipping channel in
order to avoid the Shoal, but claim that the constraints posed by the heritage-listed
wreck of the coal hulk Kelat, the hazards posed to shipping navigation in the future
and the proximity of the East Arm Wharf facilities prevent any realignment.
The conceptual dredging program would require the following vessel types:

a trailing suction hopper dredger (TSHD);

a cutter-suction dredger (CSD);

a backhoe dredger or a grab dredger;

self-elevating drilling platforms for the drill-and-blast operations, if required; and

hopper barges.

Further detail is provided in Section 4.4.4 of the draft EIS. Alternative shipping
channel alignments to avoid removal of Walker Shoal are discussed in Section 4.10.1
of the Supplement. Key potential impacts as a consequence of the dredging and
removal of the Shoal include sedimentation and turbidity effects to flora and fauna,
including threatened and data deficient species, habitats and ecosystems;
degradation of water quality; restrictions to recreational activities in the Harbour;
increased underwater ambient noise levels and blast impacts on marine fauna;
diminished visual amenity of the Harbour; increased marine traffic; and disturbance
to maritime heritage.
The impacts of dredging and the removal of Walker Shoal are discussed further in
Sections 4.5 and 4.6 of this Report.

2.3.2 Installation of nearshore infrastructure


Product loading jetty
The deck level of the product loading jetty will be approximately 16m above LAT.
There will be two berths along the jetty, one solely for LNG loading and the other for
propane, butane and condensate loading. Based on safety assessments there will be
a separation distance of 500m between the berths.
The most likely construction method would involve pile driving and installation of
concrete prefabricated deck sections using cranes on jack-up barges until the
desired jetty length is reached. The pipe racks for the jetty trestle would be
transported by self-propelled module transporters over land.
The piles, precast deck beams and other materials would be brought to the jack-up
barge by a support barge. Rock anchors to stabilise the piles might also be required.
These would be installed after the deck sections are installed.
Materials offloading facility
The plan for the MOF is to construct with steel sheet piles, or with a concrete deck on
steel piles, or using a combination of these two methods. Various design techniques
are being considered for a causeway to the facility. The techniques may include use
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65
30

of granular fill compacted in layers sourced from the site or from a local quarry, or by
a combination of these two, together with the installation of rock armouring along the
causeway for support and protection from wave action. Since the draft EIS was
published, the MOF design has been refined and now includes a finger wharf and
mooring dolphins added to the end of the loading berth to improve accessibility for
the period when modules and associated materials are being offloaded.
Nearshore pipeline
The pipeline route through Darwin Harbour will be excavated using a backhoe
dredger. The trench will be relatively shallow (to a depth of 3m) and will form a gutter
that will provide stability to the pipeline.
The pipeline inside the Harbour will likely require partial burial and rock-armouring to
minimise any risk of damage.
Rock-armouring will be put in place over the top of the pipeline once it has been
constructed on the seabed. Approximately 850 000t of rock, which will likely be
sourced from existing quarries, will be transported by road to East Arm Wharf where
specialised rock-dumping vessels will take it offshore for dumping directly over the
pipeline.
The construction techniques considered for the pipeline shore crossing included
open-trench excavation, micro-tunnelling and horizontal directional drilling. These
techniques are all described in more detail in Section 4.3.2 of the draft EIS.
The key potential impacts associated with construction of nearshore infrastructure
include: direct and indirect affects on habitat from increased turbidity and
sedimentation; loss of habitat; potential acid sulphate sediments; disturbance of
maritime heritage; waste generation and spills; restrictions to recreational use of the
Harbour; underwater noise from piling; and increased marine traffic.

2.3.3 Installation of onshore infrastructure


The construction of the gas-processing facilities and supporting infrastructure in the
onshore development area will take place over a period of five to six years. The
onshore development area, consisting of the LNG, LPG and condensate processing
plant area, the flare pad, the administration area, the construction laydown areas,
borrow area and the onshore pipeline route and easement, will require approximately
413ha of land.
The construction approach for the onshore infrastructure will be to install a
combination of prefabricated gas-processing modules and facilities constructed on
site.
Prior to installation and hook-up of the modules, significant site preparation and civil
works will need to be undertaken. Vegetation on the site will be cleared. Earthworks
to level the site will involve relocating material cut from around the borrow pit at
Blaydin Point and from other material sources if required.
The key potential impacts from construction of the onshore facility are likely to be
clearing of 362ha of native vegetation, including significant mangroves and monsoon
vine forest; management of storm water and sediment; exposure of acid sulphate
soils; disturbance of culturally significant sites; noise; dust; greenhouse gas (GHG)
emissions from plant and machinery; and social impacts associated with the
temporary workforce.

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65
31

2.4 Operational activities


The pipeline from the Ichthys Field will arrive at the Blaydin Point site through the
onshore arrival facility. The purpose of this facility is to separate the feed into gas and
liquid streams and to deliver these streams at a constant pressure to the LNG trains
and a condensate stabilisation system. Gas supply for start-up power generation is
also taken off here.
Condensate stabilisation reduces vapour pressure of the condensate (liquid stream)
by heating to liberate the lighter hydrocarbon elements as vapours that can be mixed
with feed gas for the LNG trains. Mercury is then removed and the stabilised
condensate is then stored ready for export.
Mercury is also removed from LNG feed gas before it is sent to the acid-gas removal
process for chemical separation of carbon dioxide (CO2) and sulfur compounds such
as hydrogen sulfide (H2S) using activated methyldiethanolamine (aMDEA). These
compounds are then flashed off from the aMDEA (which can be recharged for reuse)
and then incinerated to emit sulfur dioxide, carbon dioxide and water vapour.
Water is then removed from the gas stream through the dehydration unit to prevent
the formation of hydrates in the liquefaction process and the dry gas moves through
the mercury guard bed, which backs up the initial mercury removal process. The
mercury bed material from the mercury removal unit and guard bed has to be
disposed of by a specialised contractor at an approved facility.
A LPG recovery system extracts the heavier components or LPGs from the dry gas
stream through demethanisation and distillation. The removed LPG is then sent to
the fractionation unit to produce streams of ethane, propane, butane and
condensate. Some of these fractions are used as refrigerant and fuel in the process
but the majority is stored and exported as saleable LPG and condensate product.
Any remaining light hydrocarbon fractions from fractionation primarily methane
join the main gas stream for LNG production at the liquefaction and refrigeration unit.
After LPG separation, the predominantly-methane feed gas stream will be
compressed in the inlet gas compressor of the main cryogenic heat exchanger,
cooled against air and four levels of propane chilling, then directed to the main
cryogenic heat exchanger and associated refrigeration where the gas will be chilled
to -160oC and liquefied at nearly atmospheric pressure to create LNG. The final LNG
product is stored in cryogenic tanks ready for export.
Ancillary activities and infrastructure to support the operation would include water
supply, fuel storage, power generation, waste water treatment system, and a ground
flare.
The key impacts from the operation of the plant include GHG and other atmospheric
emissions, approximately 2ML/d of potable water use from Darwins water supply,
nutrients and other contaminants from discharge of waste water into Darwin Harbour,
hazardous waste disposal, visual amenity, ongoing social impacts and noise.

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65
32

Figure 1: Gas export pipeline route through Darwin Harbour to Blaydin Point (draft EIS)

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65
33

Figure 2: Layout of onshore development infrastructure (Supplement)

34

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65

Figure 3: Short jetty concept and indicative dredged shipping channel (Supplement)

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65
35

Figure 4: Dredge spoil disposal ground (draft EIS)

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65
36

Figure 5: Long jetty concept

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65
37

3 Regional Setting
3.1 Physical
Darwin Harbour is a large ria system about 500km2 in extent. The Harbour is fed by
three main arms arising from its catchmentEast Arm, West Arm and Middle Arm
that merge into a single unit, along with the smaller Woods Inlet, before joining the
open sea. Large freshwater inflows to the Harbour occur from January to April during
the Wet season.
The nearshore portion of the pipeline route, some 27km long, extends from the
mouth of Darwin Harbour to the low-water mark at the pipeline shore crossing south
of Wickham Point on the western shore of Middle Arm Peninsula (Figure 1). The
proposed pipeline route for the Project runs adjacent and parallel to the existing
BayuUndan Gas Pipeline. Seabed features near the pipeline route include Kurumba
Shoal, Plater Rock and Weed Reef to the west of the alignment. Channel Island is
located in Middle Arm, around 1.5km south-west of the proposed pipeline shore
crossing.
The nearshore development area also includes the marine environment below the
low-water mark around Blaydin Point. This area is located on the southern bank of
East Arm, at the mouth of the Elizabeth River. Subsea features of this area include
South Shell Island, Old Man Rock and Walker Shoal, which is proposed to be
removed. Immediately to the west of Blaydin Point on Middle Arm Peninsula are two
narrow tidal creeks known as Lightning Creek and Cossack Creek (Catalina Creeks).
An offshore site 1520km north of the mouth of Darwin Harbour is also considered to
be part of the nearshore development area as INPEX proposes to use this site as a
disposal area for material dredged from Darwin Harbour (Figure 4). Surveys of this
area recorded a flat featureless seabed of siltsand, at water depths of 1520m.
The coastline of the outer section of the Harbour is comprised mainly of sandy
beaches and rocky foreshores. Within the Harbour, shores are characterised by
extensive intertidal mud flats and mangroves. Corals exist in several areas within the
Harbour.
The main channel of the Port of Darwin is around 1525m deep. The channel favours
the eastern side of the Harbour, with broader, shallower areas occurring on the
western side. The channel continues into East Arm, towards Blaydin Point, at water
depths of more than 10m below LAT; the bathymetry in this area has been modified
by dredging for the development of East Arm Wharf.
Mean sea level is approximately 4.0m above LAT. Spring tides can produce tidal
ranges of up to 7.5m, while the neap-tide range can be as low as 1.4m. Tidal
excursions and flows are large and produce strong currents. Sediments of the
seabed vary from fine muds to coarse sands, shell grit and coral rubble. Hard rock
outcrops are also present.
Many wrecks are found within Darwin Harbour. These include ships and aircraft from
World War II, wrecks from cyclones and deliberately scuttled boats for use as fishing
and diving sites.
The onshore development area is proposed for Blaydin Point on the northern side of
Middle Arm Peninsula above the low-water mark (Figure 2). Blaydin Point is a
low-lying peninsula, which juts out into East Arm. At its highest, the peninsula rises to
approximately +10m Australian Height Datum (AHD). Blaydin Point is separated from
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65

38

the mainland by a salt flat, across which a low causeway has been constructed by
INPEX to provide access to Blaydin Point during spring-tide periods. This salt flat is
sub-aerially exposed, except during spring tides when it becomes inundated to a
depth of approximately 1m for periods of up to an hour. Blaydin Point is currently
undeveloped. The onshore development area also extends on to the main area of
Middle Arm Peninsula and includes the proposed onshore pipeline corridor leading
from the western shore of the peninsula across country to Blaydin Point.
Middle Arm Peninsula is currently traversed by a road and services corridor leading
to the Darwin LNG plant at Wickham Point as well as to a power station and an
aquaculture centre on Channel Island.

3.2 Biological
Darwin Harbour has a diverse assemblage of species typical of the Indo-west Pacific
Biogeographical province. Protected species in the Harbour include turtles, seasnakes, sea horses, dugongs and several species of coastal dolphin, including the
snub-fin dolphin. These species are all listed under the Australian Government EPBC
Act and some under the Territory Parks and Wildlife Conservation Act (TPWC Act).
Coral communities occur where the substrate is rocky in the lower intertidal and
shallow subtidal zones and hydrodynamic conditions permit. The intertidal platform
between Channel Island and the mainland is listed on the Register of the National
Estate and has been declared a Heritage Place under the NT Heritage Conservation
Act 1991. This declaration was based on the presence of an unusually diverse coral
community.
Other intertidal communities include rocky shores and pavements, sand beaches and
sand and mud flats.
Other areas of conservation significance include the Charles Darwin National Park,
Casuarina Coastal Reserve, East Point Aquatic Life Reserve and Doctors Gully
Aquatic Life Reserve.
Blaydin Point is considered to be part of the Darwin Coastal Bioregion. The flora of
the Blaydin Point island is dominated by woodland and monsoon vine forest with
fringing patches of mixed species low woodland and Melaleuca forest. The woodland
community mostly consists of Eucalyptus miniata (Darwin woollybutt) and E.
tetrodonta (Darwin stringybark) with mixed mid-storey including Cycas armstrongii,
which is listed as vulnerable under the TPWC Act.
Blaydin Point is fringed by an extensive mangrove community, typical of the majority
of the shoreline of Darwin Harbour.
A total of 148 vertebrate species were recorded in the fauna survey conducted on
Blaydin Point, including nine species of mammal (of which four were bats), 106 birds,
22 reptiles and 11 frogs. None of the animal species recorded in field surveys of the
onshore development area are listed as threatened under the TPWC Act or EPBC
Act. Publicly available databases suggest, however, that there are a number of
threatened animal species that could potentially occur in and around the onshore
development area. These are: northern quoll, water mouse, red goshawk, partridge
pigeon, red-tailed black-cockatoo, gouldian finch and floodplain monitor. Most of
these are unlikely to occur at the Blaydin Point site.
The Project would result in clearing of approximately 133ha of Eucalyptus woodland,
61ha of monsoon vine forest, 73ha of melaleuca communities, and 95ha of
mangroves and high-intertidal communities.
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65

39

3.3 Socio-economic
The total population in the NT in 2006 was estimated to be about 192 898 with
106 000 of those people living in the Darwin region. The nearest community to
Blaydin Point is Palmerston, with a population in 2006 of about 25 000. In 2006,
approximately 5% of the NT Aboriginal population lived in the Darwin region and this
has been increasing. Based on 2004 population estimates, by 2021 the Northern
Territorys population is expected to grow to between 215 300 and 279 200 people
with the greater part of this growth likely to occur in the Darwin region. The age
structure of Darwins population is much younger than that of the general Australian
population.
At present, there is limited heavy industry in the Darwin region. The Darwin LNG
facility operated by ConocoPhilips is adjacent to the Blaydin Point site at Wickham
Point. Other major industry occupies land in the region of East Arm Port, which has
become a major point of export for access by the resource sector to Asia. Other
important industries in the Northern Territory are commercial fishing, tourism, the
pastoral industry, mining and defence.
Darwin Harbour is widely used for a variety of activities. Commercial fishing effort is
low in the Harbour whereas recreational fishing is a well established activity,
concentrating on mud crabs, barramundi and a wide variety of reef fish. Aquaculture
activities focus on prawns and pearl oysters. Scuba diving and boating are other
important recreational activities that occur in the Harbour.
Blaydin Point itself is undeveloped and has been used for limited recreation
purposes.

3.4 Cultural/Historical
Middle Arm Peninsula is within the traditional country of the Larrakia people.
According to INPEXs draft EIS, the majority of the archaeological sites and objects
recorded in the area are associated with past Aboriginal use of marine resources and
contain shells either as a midden (mound of debris) or a scatter. Other sites also
have stone artefacts present on the surface. Most sites are located within 300m of
the shoreline.
Eight sites and one isolated artefact are located close to, or within, the boundary of
the onshore development area. These sites are protected under the NT Heritage
Conservation Act.
The Aboriginal Areas Protection Authority (AAPA) identified six sacred sites in the
vicinity of the nearshore development area. Sacred sites are surrounded by
restricted works areas in which, under the provisions of the Northern Territory
Aboriginal Sacred Sites Act (NT), no land or maritime development works of any kind
are allowed.
Three non-Aboriginal historical sites were identified within the onshore development
area. These sites are associated with World War II structures and artefacts but of
which very little remains.
Six Catalina flying-boat wrecks are located in the vicinity of the nearshore and
onshore development areas. A number of World War II shipwrecks sunk in Japanese
air raids are located near the pipeline corridor through Darwin Harbour. The SS
Ellengowan, which is the oldest known shipwreck in Darwin Harbour and is one of
the earliest examples of shipping associated with European settlement in the area, is
located south of the proposed pipeline shore crossing for the onshore processing
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65

40

plant. The wreck of the coal barge Kelat, built in 1881, is located near the entrance to
INPEXs proposed shipping channel. It was damaged during the Japanese air raid on
Darwin in 1942 and sank five days later. These are protected under the Heritage
Conservation Act and / or the Historic Shipwrecks Act

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65

41

4 Environmental Impact Assessment


4.1 Introduction
The purpose of this Report is to evaluate the Project and to determine whether it can
proceed without unacceptable environmental impacts. This is achieved by identifying
the potentially-significant risk of an environmental impact occurring as a result of
Project components and activities, and evaluating the proponents corresponding
safeguards or prevention measures to remove or mitigate the risks. Where the
proposed safeguards are considered insufficient, or where a safeguard is deemed
particularly important, recommendations are made in this Report to add to or
emphasise those commitments made by the proponent.
The environmental acceptability of this project is based on analysis of the following
from the EIS:

Adequacy of information outlining the proposal (particularly which components or


activities are likely to impact the environment);

Adequacy of information on the existing environment (particularly environmental


sensitivities);

Adequacy of information on the range and extent of potential impacts and the
risks of those impacts occurring within the Project context; and

Adequacy of the proposed safeguards to avoid or mitigate potential impacts.

Conclusions and recommendations are then based on comments from the review of
the draft EIS by relevant government agencies and the public, and responses from
the proponent to those comments in the Supplement.
In this Report, the recommendations (in bold) are preceded by text that identifies
concerns, suggestions and undertakings associated with the project. For this reason,
the recommendations should not be considered in isolation.
As minor and insubstantial changes are expected in the design and specifications of
the proposal following the conclusion of the EIS process, it will be necessary for
approval mechanisms to accommodate subsequent changes to the environmental
safeguards described in the EIS and the recommendations in this Report. If the
proponent can demonstrate that such changes are not likely to significantly increase
the risks of an impact on the environment, an adequate level of environmental
protection may still be achieved by modifying the conditions attached to relevant
statutory approvals governing this project. Otherwise, further environmental
assessment may be required.
Therefore, subject to decisions that authorise / permit the project to proceed, the
primary recommendations of this assessment are:
Recommendation 1
The proponent shall ensure that the proposal is implemented in accordance
with the environmental commitments and safeguards:

Identified in the Ichthys Gas Field Development Projects Environmental


Impact Statement (draft EIS and Supplement); and

Recommended in this Assessment Report.

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65

42

All safeguards and mitigation measures outlined in the Environmental Impact


Statement are considered commitments by INPEX Browse Ltd and its joint
venture partners.
Recommendation 2
The proponent shall advise the Minister of any changes to the proposal in
accordance with clause 14A of the Environmental Assessment Administrative
Procedures, for determination of whether or not further assessment is
required.

4.2 Issues outside the scope of the assessment


A number of submissions to the draft EIS included issues associated with aspects of
the proposal that are beyond NTG jurisdiction or could not be considered the
responsibility of the proponent and are therefore deemed outside the Project scope in
the NT. This section provides some consideration of these aspects.
Offshore gas field
Environmental assessment of all Project components within Commonwealth waters,
including the majority of the pipeline route, is the responsibility of the Australian
Government under the EPBC Act. INPEX requires an approval from the Australian
Government Minister under this Act.
LNG Gas facility site selection
Blaydin Point on Middle Arm Peninsula is zoned for Development under the NT
Planning Scheme. This followed an amendment to the Planning Scheme in 2007
(Amendment 37) and INPEXs decision to revisit alternative sites for the processing
facility due to the time constraints and uncertainty relating to INPEXs preferred Maret
Islands option in the Kimberley region (draft EIS, Section 4.1.2).
The Darwin region is an attractive site for the Project as it is close to pre-existing
services and infrastructure (transport, communications, health, education, housing,
etc), supporting industry and port facilities, and access to an established labour
market. There is relevant industry experience in Government and the community
based on projects such as the Darwin LNG plant at Wickham Point. Darwin is also
considered to be a gateway to Asia, INPEXs principal export market.
Part of the Northern Territory Governments economic development strategy for the
Territory is securing additional LNG developments.
Land is an important element to attract further LNG developments. The Northern
Territory Government undertook a high level site scan to identify suitable sites for
further LNG development. Key elements in selecting a site included:

Certainty regarding the ability of the Northern Territory Government to offer


tenure in a timely manner;

Proximity to deep water;

Suitable zoning for the site;

Adequate separation from other developments and residential sites;

Reasonable proximity to workforce, services and utilities; and

Comparative development cost.


Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65

43

This scan identified Middle Arm, specifically Blaydin Point as the only available site,
due to technical and other constraints for other possible locations, to attract further
LNG development to the Northern Territory.
The Northern Territory Government, aware that INPEX was reviewing its site
selection for the Ichthys LNG onshore development, took the opportunity to offer
Blaydin Point as an alternative site.
INPEX undertook a preliminary assessment of the site and determined that it was
technically feasible. Subsequently, INPEX determined that it would proceed with
Front End Engineering and Design (FEED) and environmental assessment on the
Blaydin Point site.
Accommodation Village
The draft EIS estimates a construction workforce of between 2000 and 3000 at the
peak of the five- to six-year construction period. INPEX proposes to construct a
dedicated accommodation village to house most of the workforce. Normal operations
and periodic maintenance accommodation for personnel will also be required during
the operations phase. An accommodation strategy is being developed to identify and
investigate accommodation requirements and options during the operations phase
(See Section 4.9.2 of this Report). In addition, INPEX indicate that part of the
accommodation village may be needed during the operations phase to support
accommodation requirements during maintenance shutdowns when personnel
requirements increase.
A number of potential locations for the accommodation village were presented to
INPEX by both the private sector and Government. The preferred location was
chosen from a short list of sites with consideration of stakeholder input and the
criteria listed below:

There should be land potentially available for development.

The area of available land should be sufficient to accommodate a workforce of


20003000 people.

There should be access to adequate transport infrastructure.

The location should have access to and be in close proximity to domestic utilities
such as power, water and sewerage.

The location should be in proximity to the onshore development area at Blaydin


Point.

INPEX made a decision to seek approvals for the accommodation village separately
from the environmental assessment process for this Project claiming that the village
would have to be completed and available prior to the start of construction of the
onshore component of the Project.
INPEX initially applied for a lease over Crown land on parcels 2819, Part Lot 2818
and Part Lot 273 in the Hundred of Bagot, along Howard Springs Road, for the
accommodation village. Issues were raised by the community and Government
during the lease application process under the Planning Act and INPEX responded to
some Government concerns. INPEX then gained approval to undertake surveys and
geotechnical investigations on the site.
Although the accommodation village itself is being assessed separately, discussion
of the social impacts associated with the operation of the village and the workforce
for the Project was included in the draft EIS (Chapter 10). The social issues which
INPEX aimed to address included increased pressure on local infrastructure,
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65

44

increased traffic, and social interactions between the local community and the new
workforce.
Social issues associated with the Project are discussed later in this Report (Section
4.9) and will require further analysis by Government during assessment of the
accommodation village.
INPEX is yet to lodge a Development Application under the Planning Act for
construction of the village. The application would be considered as a notification
under the EA Act. The significance of environmental factors such as the impacts of
clearing native vegetation, sediment management on the site, water supply and
sewage would be considered to determine the level of assessment. The Minister
would also need to consider social, cultural and economic matters in making a
determination.
Marine Supply Base and Rock Load-out Facility
As INPEX has yet to decide on the location of the mainland supply base, it has not
been described in detail in the draft EIS. Existing facilities are being investigated but
a new mainland supply base may be required which would be subject to a separate
environmental assessment process. Locations being investigated include Darwin,
Broome, Point Torment near Derby, and Derby. The mainland supply-base location
will be determined during the detailed-design phase of the Project. The NT
Government proposes to construct a marine supply base and rock load-out facility at
East Arm Wharf as part of the East Arm Expansion Project. The proposal is
undergoing separate environmental assessment at the EIS level under the bilateral
agreement between the Australian and NT Governments.
Source of fill and rock armour
INPEX will require approximately 150 000m3 of fill for the Blaydin Point site after
available sources have been used. Approximately 850 000t of rock will be required to
armour the submerged section of the gas export pipeline through the Harbour. Most
of this material is expected to be available from existing quarries.
Assessment of material sources not already approved will be undertaken through
processes outside of this assessment.

4.3 Alternative options


There are a number of components associated with the onshore gas facility that
contribute disproportionately to key potential impacts for Darwin Harbour and the
community. As a result, INPEX has explored alternative options for these
components in an attempt to find the most acceptable option from a business case
while taking into account social and cultural issues as well as the Harbour
environment. This presents a very complex challenge for decision makers as
discussed below.

4.3.1 Product loading jetty


Two jetty concepts were considered by INPEX during the early FEED phase: a short
jetty, with a position and orientation as indicated in Figure 2; and a long jetty,
approximately 3km long with a westerly orientation directly across the entrance to
Lightning and Cossack creeks (Figure 5). INPEXs preferred option is for the shorter
jetty.

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65

45

A number of submissions requested that INPEX revisit the long jetty concept for the
product loading jetty to reduce dredging volumes.
The location of Blaydin Point in Darwin Harbour provides limited alternatives for
approach by ships. Unlike Wickham Point and East Arm Port, which have adjacent
naturally-deep channels, the approach to Blaydin Point is relatively shallow and
constricted. There are significant submerged World War II heritage features scattered
around the approach and the Point is bounded by the Elizabeth River and two tidal
creeks (Lightning and Cossack Creeks), which are considered important areas for
some recreational fishers. These are some of the tensions that contribute to the
complexity in determining the location of the product loading jetty for the Project, both
for the proponent and the Government decision maker.
INPEX consulted with key stakeholders and identified the following design influences:

maintaining access to Catalina creeks for recreational fishing;

ensuring the protection of World War II Catalina flying boat wrecks located north
west of Blaydin Point;

minimising the visual amenity impact of the jetty;

minimising the ecological impact of the jetty; and

minimising congestion and shipping risks at East Arm Wharf.

INPEX also considered its own safety and technical requirements in making a
decision.
INPEX developed a decision-support process to assist in determining which of the
concepts should be selected as the preferred jetty option. The EIS indicates that this
process integrated principles of sustainable development into the decision making
and clarified the objectives, drivers and priority considerations for selecting the most
appropriate jetty design. INPEX claimed that for the evaluation, economic weightings
were set to zero so that the decision support process was not influenced by costs
associated with the alternative jetty concepts. A description of the decision-support
process can be found in the Supplement, Section 4.10.2.
INPEXs process acknowledges that outcomes for the ecology and short term
amenity of the Harbour would be better if the long-jetty concept were adopted. This is
due to the considerable reduction in the volumes of sediment that would require
dredging; early estimates put this at less than half the volume of spoil that would be
dredged from the short-jetty concept.
However, INPEXs decision process identified that the health, safety and security,
socio-political, Project risk and technical viability categories all scored better for the
short-jetty concept.
The Supplement outlines the key advantages of the short jetty concept as follows:

a reduction in the risk of recreational vessels travelling into the jetty safety
exclusion zones and taking potentially unsafe short cuts under the jetty trestle;

a reduction in safety risks from the Projects product loading jetty because of the
increased separation distances for vessels berthing at East Arm Wharf;

a reduction in the long-term impact on visual amenity from Darwins central


business district and other vantage points around Darwin Harbour;

the elimination of the need for jetty piledriving and jetty construction works in
close proximity to the World War II Catalina flying boat wrecks and its associated
risks;
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65

46

a reduction in leak paths for products (LNG, LPGs and condensate) from the jetty
loading lines;

potential for access to Lightning and Cossack Creeks maintained; and

significantly reduced piledriving operations with reduced noise impacts on marine


fauna.

INPEX claim that the short-term environmental and social disadvantages caused by
an increased dredge volume with the short jetty are mitigated by improved safety
outcomes, a reduction in long-term visual amenity impact, and a reduction in the
extent of the area excluded by safety requirements for recreational users in East
Arm.
The latter point was one of contention, particularly for the Amateur Fishermans
Association of the NT (AFANT), as the draft EIS did not provide assurance that
access to the Catalina Creeks would be guaranteed with the short jetty, despite
access being one of INPEXs key social factors in determining the selection of this
option. Some draft EIS respondents viewed the exclusion of recreational anglers
from the Catalina Creeks as a positive arguing that they could become Marine
Protected Areas, Conservation Reserves and nurseries for the fish and crabs of
Darwin Harbour.
However, INPEXs preliminary quantitative risk analysis (QRA) indicates that public
access to recreational fishing areas in the Catalina Creeks can be maintained with
safety exclusion zones likely to apply to the eastern fingers of Lightning Creek.
Access is still subject to the results of the final QRA to be completed in the
detailed-design phase and the demonstration to, and acceptance by, the Northern
Territory safety regulator, NT WorkSafe, that safety risks to the public engaged in
recreational activities in this area are as low as reasonably practicable.
Selection of either jetty option will result in impacts, both direct and indirect. The most
significant impacts from the preferred short-jetty option are predicted to occur as a
result of the substantially increased dredge volumes. The concern for decisionmakers is whether the risks of impact to Darwin Harbour from dredging can be
managed to acceptable levels. Analysis of these risks has been undertaken in the
relevant sections of this Report and includes the management measures proposed
by INPEX to mitigate these risks. Section 4.5 of this Report discusses the modelling
predictions, habitat mapping and analysis of impacts to significant habitats that has
been undertaken by the proponent to determine the ecological risks of dredging for
the Project.

4.3.2 Dredge spoil disposal


Concerns were raised in submissions to the draft EIS about the potential impacts to
habitats and fisheries in Darwin Harbour, Shoal Bay, Clarence Strait and Adam Bay
from suspended sediments originating at the dredge spoil disposal ground. In
particular, barramundi and mud crab spawning were considered to be issues as well
as the long-term stability of the spoil in the disposal site.
Material dredged from Darwin Harbour will need to be relocated to ensure that the
completed channel remains clear of sediment and navigable in the short to medium
term. INPEX was encouraged to explore options to dispose of dredge spoil on shore
as a preferred option. Preliminary geotechnical studies by the proponent initially
indicated that approximately 80% of the material would be suitable for use as fill for
reclamation activities. At the time, a major expansion of the East Arm Port area was
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65

47

proposed and it was apparent that mutual benefits to INPEX and Government were
possible and were keenly anticipated. However, a number of barriers arose. INPEX
continued to undertake geotechnical investigations and studies on the dredge
material and found that the consolidated phyllite material below the soft sediments
was easily macerated into fine, unconsolidated material when mechanically
disturbed. Dredging methods that might be used to maintain material integrity, such
as backhoe dredging, were not practical to transfer consolidated spoil for land-based
disposal. Added to this was the inability for the Port to accept unconsolidated
sediments due to the engineering challenges presented in reclaiming this material for
hardstand use in the medium term. Additionally, it became apparent that Government
would not be ready to take any material that became available due to the timing of
planning and approval processes.
In order to identify a suitable location for offshore dredge spoil disposal, INPEX
consulted with NRETAS, the Department of Planning and Infrastructure (DPI), the
Darwin Port Corporation (DPC), AFANT and local shipping companies. The draft EIS
states some of the key concerns raised through consultations included the following:

the possibility of impacts from sediment remobilisation on to Darwins northern


beaches and at Fannie Bay, and on to sensitive seagrass beds adjoining these
beaches;

the possibility of creating navigation hazards for vessels entering and leaving
Darwin Harbour;

the possibility of sediment remobilising back into Darwin Harbour or into the
DPC-proposed Charles Point Patches navigation channel and thus interfering
with safe navigation;

the possibility of sediment remobilisation adversely affecting fishing grounds in


the inner Charles Point Patches and Charles Point area as well as disrupting
recreational fishing boat movements between these areas and the outer fishing
grounds of South Gutter and Fenton Patches;

the possibility of disturbing significant maritime heritage sites such as the wreck
of the Booya; and

the possibility of sediment remobilisation adversely affecting recreational fishing


activities at the series of artificial reefs off Lee Point.

In addition, the shortest possible distance to the spoil disposal ground was preferred,
to minimise vessel travel times and to avoid extending the overall duration of the
dredging program in Darwin Harbour.
Issues identified with the proponents predictive modelling and habitat mapping and
recommendations for this component of the Project are discussed in Section 4.5 of
this Report.

4.3.3 Shipping Channel and Walker Shoal


INPEX states that a critical component of the project is the ability to efficiently and
safely move, berth and load product tankers at the proposed product loading jetty. As
with the alternative options for the jetty (see Section 4.3.1 of this Report), there are a
number of tensions associated with determining the optimal channel alignment for
safe navigation to Blaydin Point.
At the entrance to INPEXs proposed navigation channel in the vicinity of East Arm
Wharf, submerged in 4.2 metres of water at LAT sits the hard rock intrusion known
locally as Walker Shoal.
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65

48

Walker Shoal in its natural state is a potential navigational safety hazard and an
impediment to future expansion of the East Arm Wharf facility. INPEX considers that
the Shoal would not allow safe transit for the Project's product tankers, regardless of
tidal height. Groundings on the Shoal would also be possible for the majority of larger
vessels transiting to and from East Arm Wharf should they accidentally pass over this
hazard. One possible consequence of vessel grounding on Walker Shoal would be
loss of containment of fuel oil or product, which could have a significant adverse
environmental impact on Darwin Harbour.
INPEX proposes to fracture and remove this shoal to facilitate safe navigation to the
product loading jetty. INPEX presented the worst-case scenario for the fracturing of
Walker Shoal in the draft EIS. The original proposal required that all hard rock in the
Shoal (60 000m3) would need to be fractured by drill and blast methods involving the
use of 300kg charges three times each day for 57 weeks. The blasting program was
based on assumptions derived from preliminary geotechnical data and, at the time,
the apparent absence of alternative techniques that were suited to the task of
removing the very hard rock forming the Shoal.
INPEXs proposal to drill and blast Walker Shoal was not viewed favourably by a
large number of respondents to the draft EIS. Questions were asked about
alternatives to avoid the need for removal of Walker Shoal and there were many
comments about the impacts to fauna in the Harbour, in particular, marine mammals
and turtles.
As a result of respondents concerns about the need to remove the Shoal, INPEX
explored alternative shipping channel options in the Supplement to avoid the Shoal,
including:

Option 0 - Moving the shipping channel to the north of Walker Shoal;

Option 1 - Swinging the shipping channel 200m to the south of the Shoal;

Option 2 - Moving the shipping channel 400m to the south; and

Option 3 - Moving the shipping channel 650m to the south.

A full explanation of the options is given in the Supplement (Section 4.10.1, page
146).
Option 0 was discounted immediately by INPEX as the product tankers would breach
the safety requirement of a 500m exclusion zone around LNG tankers by coming too
close to vessels moored at East Arm Wharf.
Table 1 illustrates the factors that informed INPEXs decision on a preferred option
and the current base case for removing Walker Shoal.
Table 1: Comparison of shipping channel alignment alternatives to avoid Walker Shoal

Factors

Base case

Additional
dredge volume
Volume of hard
rock

60 000m3

Option 1

Option 2

Option 3

0.5 1Mm3

3 4Mm3

5 6Mm3

60 000m3

40 000m3

Unknown, hard
rock assumed

Table 1 illustrates the apparent additional dredge spoil volumes associated with more
southerly realignments of the shipping channel from Walker Shoal. INPEX argued
that the potential ecological benefits of preserving Walker Shoal would be countered
by the significant increases in dredge spoil from channel realignment. However, an
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65

49

additional alternative involving a combination of the long-jetty option (discussed in


Section 4.3.1 above) and realignment of the channel south of the Shoal was
suggested in a number of submissions. This configuration could arguably have
resulted in a net reduction in dredging volumes, not an increase as claimed by the
proponent. Added to that, this option would appear to reduce hard rock volumes by
30% or more, a significant benefit. While there are other aspects of this option that
would counteract the benefits, such as the ongoing hazard presented by the Shoal to
navigation, and the safety and visual amenity issues of the long jetty, INPEX has
missed an opportunity to demonstrate that all viable alternatives were
comprehensively evaluated.
INPEX concluded that Walker Shoal needed to be removed and continued to pursue
alternative methods to remove it. Following further geotechnical investigations
involving drill core sampling of the Shoal and investigation of alternative techniques
for fracturing the hard rock, INPEX re-evaluated the requirement for blasting as the
primary means for removing the Shoal. The current proposal is to use a specialised
cutter suction dredge with the capacity to remove hard rock greater than 50 mega
pascals (MPa). INPEX claims that seven such dredgers will exist when required and
this increases the chances of successfully sourcing one for the dredging campaign.
As a back-up to the jumbo dredge, INPEX have proposed to use a drop chisel or
hydraulic hammer (hydro-hammer) to fracture stubborn rock. INPEX is confident that
these techniques will succeed. If this is the case, blasting would not be necessary. A
no-blasting alternative is strongly supported by all parties; however, INPEX cannot
guarantee that all hard rock can be removed by alternative means. The proponent
therefore maintains the need for a blasting approval in the event that all other
methods to remove the hard rock prove inadequate during actual works.
INPEX are seeking approval for a total of four weeks of drill and blast as a
contingency for removal of about half of the high-strength rock at Walker Shoal. This
is considered by INPEX to be a conservative (worse-case) scenario and INPEX
states that it is likely that all rock will be successfully fractured and removed by
alternative methods.

4.4 Walker Shoal Impacts


As drill and blast techniques remain a contingency option, these are discussed within
the EIS in the context of potential impacts in Darwin Harbour. INPEX acknowledges
that the following impacts are likely to occur as a result of removing Walker Shoal:

Loss of hard substrate habitat type;

Changes to hydrodynamics; and

Injury and possible mortality of marine fauna.

The Supplement places the removal of Walker Shoal into context in terms of loss of
habitat from the Harbour. Removal of Walker Shoal would result in a predicted loss of
0.07% of hard substrate (at equivalent depth). Surveys of other hard substrate areas
in the Harbour indicated that the ecological communities on Walker Shoal are not
unique and that there are three other shoals in the area with similar ecological
function that will not be disturbed. Further information on habitat mapping for the
Project, which was used to define the extent of habitat loss and indirect impacts of
dredging on habitats and key biological communities, is contained in Section 4.5.2 of
this Report.
NRETAS questioned the assessment of the potential alteration of hydrodynamics
and tidal energy from the removal of Walker Shoal. There were concerns that the
potential for altered bathymetry and the resulting change of deposition sites in East
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65

50

Arm were not properly considered. INPEX stated that the alterations to the
bathymetry of East Arm for the Project predicted through the nearshore
geomorphological modelling, which included consideration of the removal of Walker
Shoal, would result in only small decreases in the flushing rate at some locations, but
no significant alteration to the flushing capacity of East Arm and Elizabeth River as a
whole. INPEX conducted a more detailed review of the model under the no Walker
Shoal condition, which supported the original predictions (Supplement, Section
5.2.2.11, page 321).
In considering the complex range of competing issues associated with navigation to
Blaydin Point, in particular the hazard that Walker Shoal presents to shipping, and
INPEXs decision to use drill and blast only as a fall-back, there is no longer a strong
case to realign the channel and preserve the Shoal. The permanent loss of a
relatively small area of Darwin Harbour habitat appears to be justified when weighed
up against the ongoing risk of a grounding event resulting in the potential loss of
containment of LNG or LPG in the Harbour.
Management of the activity by the proponent to ensure impacts are within acceptable
levels is essential. INPEX has committed to management measures to reduce the
risk of environmental harm to as low as reasonably practicable within a dredging and
dredge spoil disposal management plan. Provisional plans were provided in the draft
EIS and further development of these plans will occur in consultation with regulatory
authorities. If blasting is required, INPEX has committed to develop a final blasting
management plan that would include best-practice methods for management of
blasting impacts. However, there are considerable concerns that remain with a
blasting program, including the potential impacts of underwater noise. Underwater
noise issues associated with blasting are discussed further in Section 4.6.1.
The risks associated with dredging and their management are considered in Sections
4.5.4 and 4.6.2 of this Report.

4.5 Dredging and dredge spoil disposal


The significant dredging campaign proposed by the proponent (summarised in
section 2.3.1 of this Report and detailed in Chapter 4 of the draft EIS) prompted
considerable interest from respondents to the draft EIS. Concerns raised in
submissions included the effects on various habitats within the Harbour and
associated ecological communities, as well as effects on water quality. A number of
respondents also raised the issue of cumulative impacts to the Harbour; the reliability
and uncertainty of the predictive modelling; and the potential differences between the
dredging concept in the EIS and the actual campaign. These issues are discussed in
more detail below.
It must be noted that INPEX has revised the required depth of dredging since the
draft EIS was published. A reduction in the required under-keel clearance of product
transport ships from 2m to 1.5m has resulted in a reduction of estimated dredge spoil
volumes of approximately 1 Mm3 or 6% of the estimated total dredge spoil volumes
with the short jetty option.

4.5.1 Predictive modelling


Respondents on this issue were concerned about the various assumptions made by
INPEX in selecting the model used and determining the model inputs, and the
relevance of model predictions given that the dredging methodologies would differ
from those described in the EIS.
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65

51

Early in the project assessment, INPEX used a 3-dimensional model. The algorithms
in the model were complex requiring modelling to be conducted over a lengthy
timeframe. The outputs of the initial business case dredging campaign modelled
showed significant impact on the Harbour environment as the business case was
essentially a worse-case scenario. Factors such as the overflow of turbid water from
the trailer suction hopper dredge contributed to significant sediment inputs to the
Harbour. INPEX determined that further modelling runs would be needed to predict
the impacts of more environmentally-responsible scenarios. To ensure that the
public could consider an improved dredging concept within the EIS timeframe,
NRETAS agreed that INPEX could use a 2-dimensional model, based on the
assumption that the Darwin Harbour water is well-mixed.
The proponent relied heavily on assumptions to draw conclusions about the potential
impacts of dredging and spoil disposal due to the lack of measured data. It is
acknowledged that this is customary practice as detailed facts about all aspects of a
complex environment can never be fully known. Throughout the assessment
process, INPEX asserted that all assumptions used in the predictive modelling were
either appropriate, as determined through peer-reviewed literature or measured data,
or were deliberately conservative to provide a buffer against inherent uncertainty.
However, some of the assumptions made in predicting impacts were not clearly
evident in the draft EIS making it difficult to assess their conservatism or otherwise.
NRETAS and the Australian Government Department of Sustainability, Environment,
Water, Population and Communities (SEWPaC) contracted a number of consultants
to review the modelling. Both the Australian Institute of Marine Science (AIMS) and
WorleyParsons questioned assumptions made by the proponent, particularly within
the sediment transport modelling.
INPEX has since provided more details of the conservative assumptions as claimed
(Supplement, Section 4.1.3.2, Table 4-5, page 47) and on the advice of
WorleyParsons conducted sensitivity analyses on the sediment transport model to
test the effects on some assumptions by varying the assumed values. The
assumptions claimed to be conservative include:

loss rates from various types of plant such as the trailer suction hopper dredge
draghead; cutter suction dredge cutter head and spoil placement; backhoe
dredge; and barge dumping;

critical shear stress values for erosion and deposition;

values assumed for spoil deposition and re-suspension at the spoil ground;

exclusion of freshwater flows originating from the catchment, therefore assuming


no change in seaward sediment transport in the Wet season;

enhanced duration and continuous operation assumed in schematisation of the


dredging program;

exclusion of intertidal sediment erosion from raindrop agitation and runoff,


arguably enhancing assumed deposition values;

exclusion of wind-wave action in mangrove areas, therefore enhancing deposition


values in the intertidal zone; and

coarse grain size for offshore disposal represented by fine sand, therefore
assuming enhanced sediment re-suspension in offshore areas.

INPEX also claims to have established conservative impact thresholds for habitats in
the development of indicative zones for predicting the extent of impacts. This will be
discussed further in Sections 4.5.2 and 4.5.3 of this Report.
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65

52

INPEX therefore considers that the outputs of the modelling for suspended sediment,
and sedimentation intensity and distribution, overestimate the potential magnitude of
environmental impacts and is confident that the predictions of potential impacts
encompass the full range of activities and risks that may occur as a consequence of
the proposed dredging activities.
Nevertheless, the proposed dredging campaign is significant in scale and duration.
As will be discussed, there remain a number of concerns not least of which is the
uncertainty of relying on modelling predictions to determine the likely areas impacted
by such a large dredging proposal.
The dredging tender released by INPEX specified that the method of dredging
selected by the successful contractor should not result in any significant change to
the predicted levels of impact described within the draft EIS.
INPEX has committed to further sediment dispersion modelling once the dredging
and spoil disposal design is finalised. Following this modelling, it is considered
prudent that INPEX conduct particle tracer studies to provide physical validation of
the predictions in respect of the fate of simulated dredge material. This should be
conducted for both dredging activities in the Harbour and for off shore spoil disposal.
Modelling and tracer studies need to inform the final dredging and dredge spoil
disposal management plan, which will require approval by Government.
Further, if changes to the proposed dredging occur that result in changes to the
predicted environmental significance of the proposal, then INPEX is required to
submit a variation under clause 14A of the EAAP for reassessment under the EA Act,
in accordance with Recommendation 2 of this Report.
Recommendation 3
Further hydrodynamic and sediment transport modelling on a refined dredging
proposal is required in consultation with the dredging contractor.
Recommendation 4
Prior to the commencement of dredging, INPEX should conduct particle tracer
studies based on the expected dredge spoil characteristics to validate the
modelling predictions for fate of dredged sediments during dredging in the
Harbour and offshore spoil disposal.
The studies should account for variations in tidal cycles.
Recommendation 5
The dredging and dredge spoil disposal management plan is to be informed by
the hydrodynamic modelling and sediment transport modelling, and particle
tracer studies. The plan should include monitoring of sedimentation and water
quality and appropriate ecological indicators. Contingencies to manage
dredging in the event that there is a significant departure from predicted
impacts need to be specified in the plan. The plan should be developed in
consultation with an expert panel (in accordance with Recommendation 24).
Long term monitoring of the spoil ground to determine the dispersion and fate
of this spoil over an appropriate timeframe should be included in the
management plan.

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65

53

4.5.2 Habitat mapping


Concerns were raised regarding the lack of an adequate habitat map for the Darwin
Harbour and wider region. A habitat map was requested to enable adequate
assessment of the extent and intensity of potential impacts from dredging and dredge
spoil disposal on marine habitats and the biological communities these habitats
support.
The map produced by INPEX for the draft EIS was limited in extent and based on
limited data, primarily substrate data, collected in large part by Government and the
proponents of previous projects in the Harbour. Although INPEX undertook some
sampling within the proposed footprint of the dredging and at selected coral reef
features, the additional data did not contribute significantly to a wider understanding
of the Harbour such as the extent of various habitat types that would potentially be
disturbed or the proportion of particular habitat types that could be impacted or lost
as a result of dredging and spoil disposal activities.
INPEX commissioned a number of studies following the publication of the draft EIS to
provide additional information to assist the environmental assessment of the Project
(Supplement, Section 4.1 Marine). Various surveys (including aerial, tow-video
camera and diving) contributed to an expansion of the marine benthic data sets for
nearshore habitats in Darwin Harbour and its surrounds. Biodiversity was primarily
described and mapped at a broad (feeding guild) level (e.g. corals, filter feeders,
seagrass).
INPEX subsequently collated and processed these and other ancillary data sets to
produce an improved habitat and benthic community map of Darwin Harbour and
surrounding areas predicted to be influenced by the Project. Based on this
information, INPEX was able to:

spatially map and therefore calculate areas occupied by significant communities


(e.g. corals, reefs, seagrass, mudflats) in predicted zones of direct impact;

use existing knowledge and compiled data sets to develop models to predict the
distribution of habitat classes in the zones of impact and influence for dredging
and spoil disposal; and

identify significant habitats that could be threatened by dredging activities.

The proponent also conducted a desktop review of available data in an effort to


establish appropriate benthic environmental thresholds and indicators and to assess
impacts at the ecosystem level for Darwin Harbour and the wider, nearshore marine
environment.
INPEX presented the habitat mapping methods to key NRETAS advisory bodies
following a period of consultation prior to and during the survey period.
The improved mapping has provided INPEX with a better understanding of the areas
that could be influenced by dredging and spoil disposal activities but relies largely on
inferences. The habitat map could have been improved through field validation within
areas predicted to be influenced by dredging and/or where monitoring for potential
impacts and habitat recovery is desirable. If combined with baseline information on
the environmental conditions in which particular marine habitats occur, this mapping
would have enabled a more realistic assessment of the impacts to marine habitats
and consequently to marine organisms reliant on those habitats.

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65

54

The methodology employed, although not as comprehensive as a fine-scale


sampling regime covering all areas influenced by the Project, provides a reasonable
and cost-effective description of the relevant regional habitats for environmental
assessment purposes.
Habitat impacts and their management, and the constraints presented by INPEXs
current approach, will be discussed in subsequent sections of this Report.

4.5.3 Establishing zones of impact


As previously discussed, a number of submissions raised concerns about INPEXs
ability to predict impacts to marine ecosystems. This was due in part to the gaps in
knowledge about the types and extent of habitats in Darwin Harbour and the wider
region, and questions about the assumptions used in INPEXs modelling, both of
which have been discussed in previous sections of this assessment report.
INPEX undertook to better define the Projects predicted impacts by delineating
areas that would be subject to specific levels of impact. In the EIS, these areas are
termed the Zones of high and moderate impacts, the Zone of influence and the Zone
of no effect. This approach closely follows that of the Western Australian
Environmental Protection Authority in its marine dredging guidelines. A full definition
of these zones and how they have been derived can be found in the Supplement
(Section 4.1.3).
To do this, INPEX initially defined sedimentation thresholds using available literature
for mangroves and seagrass. There is scant information available for Darwin
Harbour. The literature used by the proponent to establish thresholds generally
originates from elsewhere in Australia and other countries. This calls into question its
applicability to Darwin Harbour conditions.
INPEX also established suspended sediment concentration thresholds for benthic
communities (corals, seagrass, filter feeders and macroalgae) using the percentageof-existing-condition approach. However, no threshold values were defined for softsediment infaunal communities as INPEX argued that the high variability in the
tolerance of different species to both sedimentation and suspended sediments
challenged the selection of an appropriate value. INPEX continues to question the
usefulness to Project impact assessment of characterising and monitoring soft
sediment benthos.
The extent of the zone boundaries was then predicted by over-laying the sediment
transport modelling outputs onto the habitat map and applying statistical limits on the
relevant sediment thresholds for the various habitats.
INPEX was then able to use these tools to predict the extent of impacts in various
phases of the dredging program both in the Harbour and the spoil ground (Figures 49 4-13 in the Supplement).
This is considered to be a significant improvement on the approach taken for the
draft EIS and an acceptable one. However, the veracity of predictions is questioned
given some of the limitations associated with data sources.
One particular aspect of the approach that is considered to have major limitations is
the paucity of baseline data. The EIS states that dredging and dredge-spoil disposal
will impact on environmental conditions, like light availability, turbidity, suspended
solids and sedimentation. However, the EIS does not provide robust baseline
information to characterise the range of environmental conditions that determine
ecological niches in the Project area. For example, there have been no
measurements of light availability within habitats that are dependent on light for
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65

55

survival (e.g. coral, algae and seagrass dominated habitats) and the turbidity dataset
is very limited, particularly in light of the high spatial variability of turbidity in the
Harbour.
Consequently, the risk analysis of potential impacts from dredging and dredge spoil
disposal relies heavily on modelled data and INPEXs risk assessment, which INPEX
draws on to prioritise impacts and determine monitoring requirements.
Considering the scale of dredging operations and its potential for impact this
approach on its own does not provide certainty to decision makers that the dredging
can be undertaken and managed in a way to ensure impacts will be acceptable. In
developing ecological monitoring programs for the dredging campaign, INPEX will
need to continue to collect water quality data to establish baseline conditions. The
monitoring programs need to be robust, site-specific and have measurable,
attainable and realistic objectives. To achieve this, the baseline data set must be
robust enough to develop effective adaptive-management measures.
INPEX must be able to establish that the extent of impact from dredging and spoil
disposal is within the range predicted by the modelling and impacts to significant
habitats/species are within acceptable levels. Monitoring should also determine the
recovery of disturbed habitats within zones of moderate impact and influence.
The detail of the environment monitoring programs for the receiving environment will
be developed in consultation with regulatory authorities prior to the commencement
of construction activities within a Government approval as part of INPEXs
Environmental Management Program, in accordance with Recommendation 23 in
Section 4.13 of this Report.
Recommendation 6
An ecological monitoring program must be developed in consultation with
NRETAS and an expert panel (in accordance with Recommendation 24) to
detect impacts on significant biological communities associated with dredging
and dredge spoil disposal.

4.5.4 Sensitive marine habitats (corals and seagrass)


Coral habitats have the highest biodiversity of marine invertebrates and fish of all
marine community types, and seagrasses provide shelter and food sources for
dugong and marine turtles. Both habitats belong to the most productive communities
in tropical waters and are not widely distributed in Darwin Harbour.
The scientific and technical review of the draft EIS conducted by the NT Government
highlighted that elevated levels of suspended sediments from dredging would likely
increase light attenuation and lead to increased sedimentation in sensitive habitats. A
combination of these factors can seriously impact or even kill some coral
communities and sea grass meadows. Loss or degradation of these communities
has the potential to significantly decrease biodiversity in the Harbour and reduce the
extent of dugong feeding areas.
The most important, well-developed coral communities in the Harbour are confined to
three locations (Channel Island, Wickham Point and Weed Reef). The conditions
most suited for these coral refuges include relatively high water clarity and low
sedimentation rate, which are normally associated with highly hydrodynamic areas.
Conversely, in the NT, seagrass meadows tend to occur predominantly in low
intertidal to shallow, sub-tidal areas where sunlight still reaches the sea floor and
where hydrodynamic conditions are such that ambient sediment deposition and
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65

56

erosion processes are gradual. Sustained dredging and spoil disposal adjacent to
these areas may alter these conditions.
The draft EIS did not provide adequate description and assessment of coral and sea
grass communities in Darwin Harbour or data describing the essential environmental
characteristics required to support these significant marine habitats. INPEX
concluded that potential impacts from dredging to significant habitats were likely to
be minor and monitoring and management actions to mitigate impacts were limited
or not proposed in the EIS. It is considered that INPEX has overstated the capacity
for corals and sea grass communities to recover from impacts caused by dredging in
view of the limited supporting data.
INPEX has provided an outline of some relevant environmental monitoring programs
and has committed to developing the detail in consultation with regulatory authorities
prior to the commencement of construction activities. It is only with robust reactive
monitoring programs and appropriate adaptive management measures that
Government and the community will have the assurance that INPEXs claims of
minimal impact can be supported.
Recommendation 7
A reactive monitoring program must be developed in consultation with
NRETAS and an expert panel (in accordance with Recommendation 24) to
respond to dredging and spoil disposal impacts on significant communities.
The program should include:

Monitoring of appropriate coral species;

Monitoring of sediment plume impacts on existing sea grass


communities in the Harbour;

Water quality parameters that account for spatial variability of turbidity,


typical for the macrotidal environment of the Harbour;

Continuation of INPEXs current water quality program to improve the


association between logger turbidity and sample sediment
concentrations;

Determination of appropriate trigger values of turbidity and sediment


concentration for biodiversity protection;

Monitoring of sedimentation rate; and

Appropriate contingency measures where impact is detected.

4.5.5 Maintenance dredging requirements


Based on the preliminary results of the modelling it was estimated that approximately
200 000m3 of sandy material might be deposited within the proposed dredge footprint
after 10 years, in which case maintenance dredging might be necessary.
Extraordinary events such as cyclones may necessitate more frequent maintenance
dredging. The actual volumes of sediment to be removed will be determined through
annual surveys of the shipping channel by INPEX.
Any maintenance dredging will need to be supported by a notification to the Minister
until a strategic plan for dredging in Darwin Harbour is developed by NT Government.

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65

57

4.5.6 Darwin Harbour dredging policy


A number of respondents expressed concern about the lack of dredging policy for
Darwin Harbour.
The 2003 DHAC publication Management Issues for the Darwin Harbour Region
states that the Office of Environment and Heritage (now the Environment and
Heritage Division within NRETAS) was involved in the development of two
documents aimed at increasing the efficiency and effectiveness of EIA for dredging
proposals: NT Dredging and Disposal Guidelines and A Dredging Strategy for
Darwin Harbour. During this period a Technical Advisory Committee (TAC) for
Dredging in Darwin Harbour was formed. This TAC provided advice on the Darwin
LNG proposal as well as the Darwin City Waterfront Development.
The NT Government is aware that a more strategic approach to dredging needs to be
taken and is working to achieve this.

4.6 Biodiversity impacts


4.6.1 Underwater noise
The Project will create additional underwater noise in various forms and intensity
above current ambient levels in Darwin Harbour. Marine mammals (three species of
coastal dolphins and dugongs) and marine turtles (green, hawksbill, flatback and
olive ridley) are an iconic part of Darwin Harbour and may be significantly impacted
by increased noise in the underwater environment.
There are a number of ways in which this could occur. Apart from direct concussion
injuries from a blast; impacts from intense and/or prolonged noise, for example,
temporary threshold shift (hearing loss), can have profound effects on the fitness of
individual animals. These effects include masking of important signals such as
echolocation signals, intra-species communication, and predator-prey cues;
disrupting important behaviours through startle and repellence; or acting as an
attractive nuisance. These responses individually or in combination can result in
avoidance and abandonment of habitats.
Some of these effects are particularly pertinent to cetaceans. Coastal dolphins see
with sound (echolocate). In muddy waters, sight is often of little use and these
species are reliant on echolocation to explore their environment. Significantly
increased underwater noise levels can compromise a dolphins ability to carry out
normal activities.
Direct Impacts
Substantial underwater noise would be generated by a number of activities
associated with construction of the Project including cutter-suction dredging and pile
driving. A protracted campaign of drill and blast was originally proposed and was
considered to be the most significant potential source of underwater noise in the
Project. Alternative methods have since been proposed, including the use of a
specialised CSD and hydro-hammer, and blasting may no longer be required. This
change in methodology is considered to be a very positive outcome of the
assessment process. However, INPEX will retain a reduced drill and blast option as a
contingency (see Section 4.3.3 of this Report) and therefore blasting noise from a
reduced campaign will still need to be considered.
Blasting is a fall-back option for INPEX in the event that the specialised CSD and
hydro-hammer fail to remove all of the hard rock at Walker Shoal. The contingency
blasting program, though considerably shorter in duration, is expected to be identical
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65

58

to the original proposal with respect to charge sizes and blasting frequency. The
explosive blast pressure wave from a 50kg charge is predicted to have an extremely
high peak pressure of about 270db re 1 Pa at the source with very rapid rise time
(<1ms). The peak pressure level received from a single blast pulse expected to
cause tissue damage is 230dB re 1 Pa. The sound exposure level (SEL) calculated
for six 50kg charges on 25ms delays is 212dB re 1 Pa2.s; the SEL criteria for injury
from blast exposure is 198dB re 1 Pa2.s. This would suggest that if blasting was
undertaken, the risks to any animals in the vicinity of the blast would be extreme.
INPEX conducted underwater acoustic modelling to predict impacts from noise
generated by pile driving and blasting activities. The modelling predicted sound
pressure levels and SELs at different distances from expected noise sources and
applied a range of frequency weightings, representing hearing ranges for significant
marine fauna, to SEL estimates. The outputs were measured against received noise
criteria adopted by INPEX for marine mammals, turtles and fish from Southall et al
(2007) (as cited in the Supplement). The veracity of these criteria was not able to be
comprehensively verified, but the criteria are generally considered to be the best
available.
INPEX conducted an assessment of pile driving noise based on the assumption that
pile driving would take up to 18 months for construction of the MOF and 8 months for
construction of the jetty using a single piling rig; duration would be shorter if multiple
rigs were used. Pile driving results in repeated noise pulses with a hydraulic impact
hammer applying 60 blows per minute (assumed) and each blow lasting 90ms. The
draft EIS estimated the peak sound pressure level at the pile driving source to be
about 210dB re 1 Pa for a typical piling operation. This exceeds the received level
criteria for all marine animals and the bulk of the source noise falls within the lower to
mid hearing range of the coastal dolphin species. At noise levels of this magnitude,
animals are likely to suffer injury but would have to be very close to the noise source.
Animals would more likely avoid the area of impact during the works if given an
opportunity to move away. Although modelling appears to be conservative and actual
noise received is likely to be less than predicted, pile driving is still considered to be a
significant source of underwater noise in the near shore project environment.
The dredge concept includes a CSD for removal of the more-consolidated material in
the Harbour. The CSD would be used primarily in Phase 6 for approximately six
weeks, 24 hours per day, 7 days per week. Additionally, a specialised CSD is
proposed to be used in place of drill and blast methods to remove hard rock at
Walker Shoal. The Supplement provides no indicative timeline for the use of the
specialised CSD. The noise source spectrum level has been assumed to be 6dB
above that of a standard CSD as the underwater noise intensity is also not known.
Standard dredgers normally generate low-frequency noise with source levels around
160-170dB re 1 Pa. Source levels from the specialised CSD are therefore not
expected to exceed 180dB re 1 Pa, which is considered to be at the lower end of
the adopted noise criteria. At these levels, direct injury to animals is unlikely but
avoidance of the area by marine mammals is expected.
A drop chisel or hydraulic hammer (hydro-hammer) is proposed to be used on hard
rock in the event that the specialised CSD is unsuccessful. Again, there is no
estimate of duration of this method should it be required. Source noise levels from
this method are pulses derived from hammer blows assumed to have similar
characteristics to pile driving. The maximum source level for the hydro-hammer is
estimated to be about 165dB re 1 Pa at a frequency of 200Hz. This is well below
the underwater noise criteria for marine mammals, turtles and fish designated in the
EIS and the risk of injury is considered to be very unlikely. The noise from the hydroIchthys Gas Field Development Project, Blaydin Point
Assessment Report 65

59

hammer is of less concern than noise from piling and blasting; however, it will add to
the noise levels in the East Arm area if used.
INPEX has proposed a number of measures to mitigate and manage underwater
noise and blasting impacts on cetaceans, dugongs and marine turtles during Project
construction, including:

Undertaking pile driving and any blasting activities during daylight hours to
maximise visibility for fauna observers. Additionally, blasting would only occur
during benign sea conditions;

Employing a soft start approach when pile driving, which entails gradually
ramping up the activity over five minutes;

Using confined blasting methods, with micro-delays inserted between six, 50kg
charges to reduce peak pressure levels of the total 300kg of explosive detonated
during each blast;

Maintaining watch for animals using trained marine fauna observers within a
500m radius for piledriving and 1000m for blasting;

Observation for at least 30 minutes prior to pile driving and blasting. If any animal
is observed in that period, a 20-minute watch would commence until the animal
was observed to move outside the zone or not seen again within that period. The
30-minute observation period would then begin again and soft start piling or
blasting would not proceed until no animals were observed in this time;

Temporary cessation of piling, once commenced, only if an animal is observed


within 100m of the activity. Piling would recommence once the relevant conditions
outlined above were met;

Utilising an appropriate combination of passive and active acoustic monitoring


techniques to detect and monitor the movement of large marine fauna in the work
area and adjacent safe zone during blasting activities;

Use of explosive casings to minimise toxic floating debris and retrieval of killed
fish on the surface to minimise harm to scavenging or predatory fauna;

Marine workforce induction to include information on marine mammal


management requirements;

Training of vessel masters in marine mammal interaction procedures; and

INPEX vessels will operate at no wash speed when within 50 to 150m of a


marine mammal and will not intentionally approach within 50m of a marine
mammal.

In summary, it would appear from the modelling that the risks of significant direct
impacts to marine fauna from underwater noise as a result of pile driving and
dredging are relatively low and these risks can be managed through the proponents
Environmental Management Program. The Fisheries Division of DoR accepts that
some fish mortality will occur if blasting is required but is accepting of this risk as the
impacts are likely to be short-term. Fish deaths due to blasting will need to be
recorded and reported as a requirement of any permit issued under section 16 of the
Fisheries Act for the blasting activity.
There are still serious concerns, however, for the safety of marine mammals and
turtles if drill and blast is employed. There is limited certainty that the current
management measures proposed for safeguarding these species will be effective. In
particular, the current dependence on marine mammal protection zones and
observers is of concern. The macro-tidal environment of Darwin Harbour creates
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65

60

relatively turbid, low-visibility conditions while the low surface profile and cryptic
nature of some dolphin species, and the duration that some marine fauna can remain
submerged, makes them very challenging to detect. INPEXs commitment to using
alternative methods for breaking hard rock is supported but continued investigation of
marine fauna detection techniques such as acoustic monitoring is necessary to
determine a more robust detection method in the event that blasting is required. The
proponent must be able to demonstrate through sound scientific studies that any
mitigative strategies and monitoring techniques used can adequately safeguard
these significant species.
Recommendation 8
If INPEX must implement the drill and blast contingency for removing hard
rock, a management plan to protect coastal dolphins, dugongs and turtles
must be developed in consultation with NRETAS and an expert panel (in
accordance with Recommendation 24). The management plan must
demonstrate, through sound scientific studies, the effectiveness of measures
to minimise risks, detect fauna and manage impacts.
Cumulative Impact
A further risk associated with the Project is the potential indirect impacts to marine
fauna of cumulative increases in Harbour noise.
The cumulative impacts of noise from concurrent sources in the Harbour, including
dredging, piling and blasting, were modelled. However, Appendix S7 of the
Supplement qualified that the inherent uncertainty of underwater noise propagation
and the interaction of multiple noise sources made this extremely complex and a
fraught undertaking. Given the uncertainty associated with data deficiency, there is
considered to be significant risk that cumulatively, these noise levels have the
potential to adversely impact marine fauna over an extended duration, particularly if
blasting is added to the underwater noise environment. A precautionary approach in
protecting these fauna is therefore necessary.
As discussed previously, the key noise-generating activities are likely to provoke
avoidance of the impacted area over a sustained period. It is believed that coastal
dolphins could be particularly susceptible because of their reliance on echolocation.
The three species of dolphin known to occur in Darwin Harbour are present in low
numbers. Detection of population trends in coastal dolphins is difficult because of the
low abundances and studies have confirmed small populations are more prone to
extinction than large, stable populations. Even with unbiased and precise abundance
estimates, population trends in coastal dolphins are likely to be extremely difficult to
detect in short-term studies unless changes in population size are dramatic (greater
than 20% per year). Within this time, there is potential for an undetected, irreversible
population decline. Furthermore, both Indo-Pacific humpback and snubfin dolphins
are likely to exist as meta-populations (small and partially, or completely, isolated
populations). Limited research by NRETAS indicates patterns of residency within the
Darwin Harbour populations. This makes them susceptible to extinction if rates of
dispersal between populations are adversely affected. Without knowledge of the
meta-population structure, the degree of dispersal and hence, an understanding of
how to manage the meta-populations, the future of these species in the Darwin
region is unknown.
The underwater noise environment of East Arm is predicted to become a challenging
environment for marine fauna, particularly the coastal dolphin species, and it is
presumed that these species will be excluded from the Eastern part of Darwin
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65

61

Harbour for an extended period during construction. The medium to long-term


prospects for populations of coastal dolphin species in Darwin Harbour as a result of
this exclusion are not known.
Given the iconic status of these animals, the uncertainty associated with their
population structure, and the increasing pressure being placed on their environment
in Darwin Harbour and elsewhere, NRETAS considers that appropriate offsets be
implemented to preserve sustainable populations of coastal dolphins in the Darwin
Region.
Recommendation 9
INPEX will continue to fund and support research into coastal cetaceans in
Darwin Harbour and the wider region to determine the importance of Darwin
Harbour for the regional coastal cetacean population and the potential impacts
of the Project, particularly drill and blast if it is to be used, on these
populations.

4.6.2 Vessel collision and dredge entrainment


A number of respondents, including WWF Australia, ECNT, La Laguna University,
the Northern Land Council (NLC), and NRETAS raised the issue of increased injuries
to, or mortalities of, marine fauna from Project-related shipping and dredging
activities in the Harbour. The main concerns were boat strike to dolphins, turtles and
dugongs, and the possible entrainment of marine animals, particularly turtles, in the
trailer suction hopper dredge (TSHD).
Marine turtles are listed as threatened under the EPBC Act and the TPWC Act and
four species are known to occur in Darwin Harbour. Large marine vertebrates are
iconic and are visible to fishers, boaters and beach walkers when stranded. The
stranding of injured or dead animals could attract considerable attention from the
public and conservation groups.
The provisional cetacean management plan broadly outlined measures to minimise
risks to coastal dolphins by requiring that INPEX vessels will:

not intentionally approach within 50m of a dolphin;

operate at a no wash speed when they are between 50m and 150m of a
dolphin;

attempt not to approach cetaceans from an angle of less than 60 into or away
from the direction of travel of the cetacean(s); and

not encourage bow-riding by cetaceans. Should any cetacean(s) commence


bow-riding in front of a vessel, the vessel master will not change course or speed
suddenly.

INPEX acknowledges that there could be occasions in Darwin Harbour where


maintenance of approach angles or distances might not be possible and provides
assurances that all efforts would be made to minimise vessel interactions with, or
disturbance to, cetaceans, while still allowing operations to continue.
The proponent asserts that the increase in the number of vessels using the Harbour
(1-2% monthly) as a consequence of Project construction is not significant and that
typically, fast moving vessels present most risk to these animals while the larger,
slower vessels present very low risk. The proponent concluded that the residual risk
of vessel collisions after implementation of proposed controls was low as the
probability of an incident was considered to be unlikely and only individual animals
would be affected.
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65

62

The management measures proposed by INPEX are borrowed from the Australian
National Guidelines for Whale and Dolphin Watching. They apply to the tourism
industry where observing cetaceans is the objective and their appropriateness in the
context of vessel movements of various sizes specific to this Project in Darwin
Harbour is questioned. While it is acknowledged that the risk of collisions with slower
vessels such as ships is likely to be relatively low, particularly for dolphins, faster
vessels are considered to present significantly higher risk. This is primarily due to the
difficulty in seeing these animals and the consequences of collision. Additionally,
there are no relevant measures proposed for dugongs and turtles.
As discussed in Section 4.6.1 of this Report, it is considered that increased mortality
of some of these species could place their populations in Darwin Harbour at risk of
decline and potentially, extinction. Using INPEXs definitions of consequence, low
numbers of individuals seriously injured or killed locally within the Project
construction period, could have massive or even catastrophic consequences for a
population.
It should also be noted that sea turtles use deeper water refuges, such as dredged
channels, when under threat. This makes them susceptible to large propellers from
slow moving vessels (Scott Whiting pers. comm. 2011) and therefore increases the
likelihood of undetected collision. Coupled with the accumulation of impact risks from
other Project-related and existing sources, this will add further to the stress on
marine fauna in the Harbour.
The current proposed management measures are not considered satisfactory and it
is recommended that smaller, Project-related vessels should be required to moderate
their speeds to lower the risks of collision and have propeller guards fitted to reduce
the impacts of collision. All boat handlers associated with the Project should be
educated to watch for large marine fauna and minimise vessel interactions with these
fauna. Any collisions should be reported. INPEX should consider involving NRETAS
Marine Wildwatch in monitoring for stranded fauna.
These additional measures must be included in the relevant management plans for
approval by Government as part of INPEXs Environmental Management Program in
accordance with Recommendation 23 in Section 4.13 of this Report.
Recommendation 10
Relevant EMPs are to be amended to include measures for minimising vessel
interactions / collisions with dolphins, turtles, dugongs and other large marine
fauna. The relevant plans should include:

details on procedures to reduce the risk of vessel strikes on large


marine vertebrates (marine turtles, dugongs and cetaceans) such as
speed limits;

requirements for installation of propeller guards on vessels associated


with the Project;

details on procedures for monitoring and reporting of vessel strikes on


large marine vertebrates; and

plans to monitor for stranded, injured or dead large marine vertebrates.

INPEX assessed the residual risk to marine turtles from TSHD entrainment as
medium. The Supplement states that the possibility of entrainment is remote;
however, monitoring detected entrainment of a marine turtle within the first 5 days of
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65

63

dredging during construction of the Gorgon Project in Western Australia. Preventative


measures are therefore considered necessary as a precaution.
INPEX has committed to develop practical methods to minimise marine animal
entrainment risks and to provide further detailed description of management
measures in the final dredging and dredge spoil disposal management plan.
Possible mitigation options offered by INPEX include:

installing deflectors on dragheads;

using turtle tickler chains on the trailing arms; and

engaging suction of the TSHD only when the draghead is close to the substrate,
not as it is raised or lowered through the water column.

The use of a combination of the above preventative measures is strongly encouraged


as the practicality of monitoring in the context of INPEXs current dredging concept
may be limited. The EIS states that the dredging contractor will be required to
demonstrate that the proposed management measures are effective by monitoring
screens used to capture entrained fauna. Monitoring screens are typically fitted
where excess water in the hopper barges is decanted before spoil disposal and
INPEX proposes to retain excess water in the hopper barges (no-overflow mode) to
minimise suspended sediments in the Harbour. Alternative monitoring techniques
may need to be explored.
INPEX has deferred the decision to employ any of the above mitigation and
monitoring measures or similar until a dredging contractor is appointed and can be
consulted. Any measures determined in consultation with the contractor must be
included in the dredging and dredge spoil disposal management plan as part of
INPEXs Environmental Management Program. The plan should include any practical
solutions to detect turtles or turtle remains in no-overflow mode.
Additionally, the plan should include a program to monitor for animals that have been
injured or subsequently died from entrainment injuries within Darwin Harbour during
dredging operations. This should include procedures for retrieval and post-mortem.
Recommendation 11
In managing marine turtles during dredging activities, the dredging and dredge
spoil disposal management plan should:

Include details on procedures to manage and monitor entrainment of


marine turtles; and

Include details for monitoring of stranded turtles at the time of dredging


and ensure the involvement of NRETAS Marine Wildwatch.

4.6.3 Cumulative marine impacts


The NT Government and the community set a target within the Territory 2030
Strategy: Ensure no deterioration in the health of biodiversity in the Northern
Territory
The marine environment of Darwin Harbour will be permanently impacted by the
Ichthys Project. The most significant impacts are expected to occur in the
construction phase associated with dredging of the navigation channel and in so
doing, the removal of Walker Shoal, possibly through blasting. Some secondary
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65

64

impacts may be temporary, perhaps lasting as long as the construction period and
others will continue during the life of the Project. These impacts have been discussed
in the previous sections of this Report.
The risks of impact to ecological communities and marine fauna have been predicted
by INPEX to be medium to low for most Project activities; however, it is considered
in some cases that the information presented has not been adequate to support
these assertions of risk. There is still much uncertainty.
Furthermore, Project activities will not be carried out in isolation; the accumulation of
various impacts during construction and through Project operations is considered to
be significant and the implications of these additive impacts are largely unknown.
When placed in the context of a Harbour that is coming under increasing
development pressure, the residual detriment from the project warrants the
implementation of an appropriate marine offset.
Although INPEXs influence on the Harbour will be considerable, it is recognised that
INPEX is not the sole operator. Government also has a role and there is an
opportunity for the NT Government and INPEX to collaborate in establishing a
suitable offset that is relevant for the permanent changes that will occur to the natural
environment of Darwin Harbour.
Recommendation 12
An appropriate offset is necessary to compensate for the residual detriment
posed by Project activities to the ecological communities and marine fauna
within Darwin Harbour. The scale of offset should be commensurate with the
scale of residual detriment. If blasting is required, the offset must be increased
to compensate.

4.6.4 Shorebirds / Wader birds


Two main issues were raised during the review of the draft EIS in relation to potential
impacts on shorebirds. These included the effects of sedimentation from the dredging
on the intertidal mudflat feeding areas, which are utilised by shorebirds and seabirds
listed under the EPBC Act, and the susceptibility of shorebirds to oil spills. Other
issues raised included the effect of lighting from the Project and construction of a
causeway at the southern end of the Blaydin Point island.
The modelling presented in the draft EIS predicts low levels of sedimentation and
indicates that these levels are not likely to have a significant effect on shorebird
feeding. The EIS also states that shorebirds are highly mobile and can move to
unaffected areas. Consequently, no management actions were proposed for
migratory bird foraging habitat.
Although the more significant shorebird sites are mentioned, Darwin Harbour is home
to thousands of shorebirds spread throughout the inter-tidal habitats and there is
potential for these habitats to be affected by sedimentation.
Shorebirds are mobile and do move long distances on migrations. However, banding
studies show they can also be very faithful to their breeding sites in the northern
hemisphere and their over-wintering final destination feeding sites in locations such
as Darwin Harbour.
While the risks to shorebirds from sedimentation impacts are acknowledged to be low
based on the conditions predicted by modelling for the current dredging concept,
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65

65

there is the potential for parameters to change in the actual dredging campaign.
There is also inherent uncertainty associated with the model and the possibility of
sedimentation exceeding predicted levels needs to be considered. Furthermore, the
threshold values applied to these habitats by the proponent have been questioned
and will need to be determined through further baseline studies (Section 4.5).
The possible need for shorebird monitoring should be re-assessed when the
dredging campaign is fully defined, further sediment fate modelling and particle tracer
studies are conducted, and appropriate monitoring and adaptive management
measures are being developed for sediment transport issues.
Impacts from Project dredging activities are not considered to present a significant
threat to shorebirds at this stage and will be managed through other mechanisms
within INPEXs Environmental Management Program (see Section 4.13).
The risk of, and potential impacts from, oil spills is discussed in Section 4.7.3 of this
Report.

4.6.5 Barramundi
Increased suspended material and deposition of silt from dredging and spoil dumping
operations may impact on barramundi populations, specifically on breeding and
recruitment. Barramundi is a popular target for recreational fishers and is an
important commercial fisheries resource in the Top End.
The draft EIS reports that suspended sediment concentrations greater than 500mg/L
have an impact on larvae of most species and 100mg/L would affect some species if
exposed for longer than 96 hours. It predicted a suspended sediment concentration
of no greater than 20mg/L in the lower reaches of the Howard River and predicted
this would not impact on the barramundi larvae and recruitment.
Subsequent to the publication of the draft EIS, a study was undertaken into the
effects of simulated dredge material from Darwin Harbour on eggs and larvae of
barramundi (Supplement, Appendix S5). The study provided additional information
on predicted impacts on the barramundi population and presented data from
experiments that were commissioned to test the survival of barramundi larvae under
different suspended-sediment concentrations. The results of the experiments
predicted minimal impact on barramundi larvae from elevated levels of suspended
solids. The Fisheries Division of DoR is satisfied that the dumping of dredge spoil is
unlikely to impact the spawning and recruitment of barramundi in the Shoal Bay area.
INPEX has committed to operate under an approved dredging and dredge spoil
disposal management plan. The management plan will include water quality
thresholds relevant to barramundi larvae protection. INPEX has also committed to
work with regulatory agencies and other stakeholders to manage actual impacts
during construction through adaptive and proactive practices.
Monitoring measures will be contained within the dredging and dredge spoil disposal
management plan, which will be developed in consultation with regulatory authorities,
including the Fisheries Division of DoR.

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65

66

4.6.6 Mud crabs


Recreational fishing for mud crabs is considered to be a locally important pastime in
Darwin Harbour. Increased suspended material and deposition of silt from dredging
and spoil dumping operations has the potential to impact on mud crab populations.
According to some respondents, the draft EIS did not present adequate consideration
of impacts to mud crabs. INPEX subsequently commissioned a study on the potential
impacts of the Project on mud crabs in the Darwin Harbour and Shoal Bay
(Supplement, Appendix S8). The study report identified and described the potential
direct and indirect impacts that dredging and spoil disposal activities could have on
aspects of key life history stages of mud crabs. It also provided information on
mitigating factors for these potential impacts.
This study supports the prediction of a low impact from the Project on mud crab
populations. The proponents understanding of the low impact on mud crabs of high
suspended-solid levels is correct. Therefore it is considered unlikely that the dumping
of dredge spoil would impact the spawning and recruitment of mud crabs in the
Darwin Harbour or Shoal Bay areas.
Similar to the barramundi management commitments, INPEX states that construction
will be undertaken in accordance with an approved dredging and dredge spoil
disposal management plan. The management plan will include water quality
thresholds relevant to mud crab protection. INPEX has committed to working with
regulatory agencies and other stakeholders to manage actual impacts during
construction through adaptive and proactive practices.
Monitoring measures will be contained within the dredging and dredge spoil disposal
management plan, which will be developed in consultation with regulatory authorities,
including the Fisheries Division of DoR.

4.6.7 Significant terrestrial habitats


The construction of the onshore processing plant will require clearing of monsoon
vine forest and mangroves. In addition, mangrove vegetation may be lost or
degraded due to sedimentation from dredging. Both native vegetation communities
have high biodiversity conservation values and are classified as significant under the
Planning Act. Furthermore, the threatened plant Cycas armstrongii (Vulnerable
under TPWC Act) occurs within the processing plant footprint and therefore a
significant number of individuals will be destroyed.
The clearing of monsoon vine forest and mangroves appears to be unavoidable for
the development of the processing plant on the Blaydin Point site. INPEX has
attempted to design the site to minimise clearing and since publication of the draft
EIS has reduced the clearing requirements of monsoon vine forest by 7ha; although,
re-design of the administrative facilities associated with the onshore facility has
resulted in an increase in the total area of mangroves and salt-marsh to be cleared.
INPEX suggests in the EIS that opportunities to reuse cycads from the clearing
activities at the onshore development and accommodation village sites will be
investigated during detailed design. This is encouraged.
The predicted levels of sedimentation in mangrove habitats remain unchanged
following revision of the modelling. Sedimentation in mangroves as a result of
dredging and spoil disposal is predicted to be greater than 100mm within two
hectares of mangrove habitat. These levels have the potential to cause tree deaths in
sensitive mangrove species. A further 28ha of mangroves is expected to be at risk of
decreased growth or death with sedimentation levels predicted to be above 50mm
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65

67

over four years. Generally, sediment deposition of 17 to 35mm per year is expected
in the zones of moderate impact.
As stated in the draft EIS, if mangrove tree deaths result because of sedimentation
from the dredging program, the proponent proposes to rehabilitate the affected areas
after the completion of dredging activities through a combination of natural
recruitment, facilitated natural recruitment and active planting. INPEX has maintained
its initial approach to managing risks of sedimentation to mangroves. This
assessment relies on the adequacy of model predictions and monitoring would be
used to validate the model. Significant uncertainty remains in the model predictions
and to a certain extent this has been acknowledged by INPEX.
To deal with this uncertainty, INPEX has proposed the following:
Monitoring of mangrove health and sediment deposition within Darwin Harbour will
be designed such that actual sedimentation can be compared with predicted
sedimentation rates. It is proposed that such monitoring will be conducted at 3monthly intervals. In the unlikely event that sedimentation rates in mangroves exceed
those predicted, or mangrove health is impacted at lower levels of sedimentation
than assumed in the draft EIS, the monitoring program will detect such changes early
and adaptive management practices can be identified and discussed with NRETAS
to facilitate protection of mangrove communities.
Development of mangrove health and sedimentation monitoring has not progressed
since publication of the draft EIS. Therefore, considerable reliance has been placed
on the post-approval development of environmental management plans.
The loss of mangroves from sedimentation is an acceptable risk at current predicted
levels. The model assumptions and predictions will need to be validated however,
through a combination of particle tracer studies prior to commencement of works,
and monitoring during dredging activities, in accordance with Recommendations 4
and 5 of this Report. A monitoring program should be included as part of the
Environmental Management Program for Government approval in accordance with
Recommendation 23 in in Section 4.13 of this Report.

Recommendation 13
A monitoring program must be developed in consultation with NRETAS and an
expert panel (in accordance with Recommendation 24) for sedimentation in
mangrove communities of Darwin Harbour. The program should be informed
by the sediment transport modelling and particle tracer studies and be
included in the dredging and dredge spoil disposal management plan.
The proponent has identified the potential use of offsets to manage the residual
detriment associated with the loss of monsoon vine forest.
The use of offsets is a rational approach to managing the issue. It is important to note
that the loss of monsoon vine forest will be permanent. The proponent has indicated
that protection of monsoon vine forest could also be incorporated in fire
management programs within the Daly River and Wagait areas, which would
principally be designed for greenhouse gas abatement. The loss of monsoon vine
forest is considered to be an acceptable risk of the Project if there is commitment to
permanent protection of regionally significant monsoon vine forests, particularly in the
Darwin Harbour catchment.
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65

68

Recommendation 14
An offset for loss of monsoon vine forest on Blaydin Point is recommended.
All activities associated with offsetting the residual detriment of clearing
monsoon vine forests should:

be in perpetuity; and

include a management plan that demonstrates environmental benefits.

4.7 Emissions, discharges and wastes


This Report has focused on the key waste discharges from the Project, particularly in
the context of Darwin Harbour as the receiving environment. INPEX is responsible for
managing and disposing of all wastes generated from the construction and operation
of the Project and will need to reach agreement on appropriate waste management
strategies with the relevant authorities.

4.7.1 Hydrotest water


Concerns were raised through the assessment about the fate of hydrostatic test
water from the pipeline and onshore facility; the use of potable, reticulated water to
conduct hydrostatic testing; and the lack of information about the chemicals to be
used in the water.
Hydrostatic pressure-testing is required to verify the integrity of all onshore process
and storage vessels, tanks and pipework, as well as the pipeline from the Browse
Field to the onshore facility. The EIS indicates that hydrotest water would be
discharged during pre-commissioning as well as during the early stages of operation
of the onshore facilities. In most cases, INPEX proposes to use potable water and no
chemicals would be added. In these cases the water may be reused several times
(e.g. to leak-test one tank after another). Where potable water is used, this is strongly
encouraged as reuse will reduce pressure on Darwins water supply (see Section
4.10.2).
Another option would be to consider the use of seawater although it is acknowledged
that this would require treatment with the addition of chemicals. If the hydrotest water
is chemically treated, this typically involves the addition of biocides to prevent
bacterial formation, scale inhibitors to prevent the build-up of pipe scale, and
corrosion inhibitors and/or oxygen scavengers to prevent internal pipe corrosion.
INPEX has not determined the types or characteristics of the chemicals to be used in
hydrotesting, but would undertake a chemical selection process, based on water
quality, ecotoxicity and efficacy of the chemical agents with its contractor.
The EIS indicates that the gas export pipeline from the Browse Field will be tested
with filtered seawater from Darwin Harbour and dewatered at the offshore facility.
During dewatering, the 1 000 000m3 of treated water in the pipeline will be
discharged at the offshore facility. No emergency discharge of hydrotest water from
the gas export pipeline to Darwin Harbour will be necessary as was suggested in the
draft EIS.
INPEX proposes to discharge hydrotest water from the onshore gas-processing
facilities at either the combined outfall on the product loading jetty or through
inspection pits, or similar structures, to the open-drain systems depending on water
quality and the availability of the jetty outfall.
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65

69

It was suggested in response to the draft EIS that INPEX investigate alternative
options for disposal of hydrotest water rather than discharge to the Harbour. INPEX
indicated that opportunities for irrigation to land at Blaydin Point would be limited;
however, no detailed explanation was provided in the EIS. INPEX needs to provide
further justification that discharge to land is not viable.
Total hydrotest discharges from the onshore facility are predicted to peak at
7200m3/d (7.2ML) when the tanks are being tested but INPEX claims that the
average discharge volumes will be substantially lower than this for the duration of the
six-to-nine-month pre-commissioning period.
INPEX have committed to:

minimising the amount of water needed for hydrotesting;

minimising the types and amounts of treatment chemicals that may need to be
added; and

assessing chemical additives to understand their environmental risks.

If discharge to the Harbour is required, INPEX will need to undertake an ecotoxicity


assessment. These commitments and requirements of an Environment Protection
Licence (EPL) under the WMPC Act will be undertaken through the proponents
Liquid Discharges, Surface Water Runoff and Drainage Management Plan.
Recommendation 15
Appropriate controls to mitigate risks from hydrotesting waste water must be
included in the Liquid Discharges, Surface Water Runoff and Drainage
Management Plan for Government approval. In preparing the plan, INPEX
should also:

Investigate options for land-based disposal where practicable; and

Select chemical additives that have the lowest practicable risk to the
marine environment.

4.7.2 Waste water discharge


A number of submissions contained comments about INPEXs requirement for liquid
waste streams from the operating plant to be discharged to Darwin Harbour,
particularly in view of contamination risks and the potential for reuse.
Recommendations were made for closed circuit systems and on-site management,
including irrigation to terrestrial sinks and reuse in the facility to reduce the demand
on the local reticulated water supply. Any discharge was recommended to be tertiary
treated.
INPEX intends to treat and discharge wastewater from the process water streams,
the potentially-contaminated drainage system, the demineralisation plant and the
sewage treatment plant, into the Harbour from the end of the product loading jetty,
300m offshore.
Volumes would fluctuate due to the co-mingling of intermittent sources and
continuous streams, which are predicted as follows:

Sewage waste and grey water would be generated throughout the life of the
Project with the volumes fluctuating depending on the number of people on the
site. Approximately 220m3/h of treated sewage will be produced during the
operations phase.
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65

70

Demineralisation reject water from the reverse osmosis (RO) demineralisation


plant will be a continuous discharge with a flow rate of between 716m3/h.

Process waste water from the processing plant will be made up almost
exclusively of water drained from the bottom of condensate tanks and volumes
will fluctuate depending on maintenance activities at the time. If a combined-cycle
system is chosen as the preferred technology for power generation, then
condensed steam loop bleed water will add a continuous stream of 8-13m3/h of
potable water.

Operational stormwater runoff from potentially-contaminated areas in the process


plant would also be directed to wastewater treatment and this would fluctuate
significantly between Wet and Dry seasons.

When accounting for all waste streams, it is estimated in the draft EIS that minimum
discharge volumes from the outfall would be around18m3/h in the Dry season.
Maximum discharge is expected to be 160m3/h in Wet season peak storm events
with 110m3/h of this the stormwater contribution.
The wastewater would contain a range of contaminants fluctuating according to
contributions from the various liquid waste streams. Key contaminants expected
include nutrients (phosphorus [P] and nitrogen [N]) and faecal coliforms from
sewage; scale and salts from demineralisation; and hydrocarbons from process
waste water and contaminated stormwater. Physical characteristics of the water
would also vary from ambient conditions of the receiving environment. Expected
contaminant characteristics of Project wastewater are provided in Table 2.

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65

71

Table 2: Characteristics of liquid discharges to Darwin Harbour against water quality


criteria for Darwin Harbour.

Parameters

Unit

Water Quality
Objectives for the
Darwin Harbour
Region (Feb
2010)1

pH

7.0-8.5

59

Total nitrogen
(Total N)

g/L

<270

40 000

Total
phosphorus
(Total P)

g/L

<20

10 000

Faecal coliform bacteria

cfu/100mL

Not specified

< 400

Total petroleum
hydrocarbons

g/L

<6002

10 000

BOD

mg/L

Not specified

20

Temperature

Not specified

2635 C

Nutrients

INPEX
Estimated
wastewater
characteristics

1. Indicator for Environmental Use: Aquatic Ecosystem Protection and Cultural, Mid Estuary.
2. Adopted from Environmental Quality Objectives in the Netherlands, 1994

A number of physicochemical and bacteriological parameters identified in the Water


Quality Objectives for the Darwin Harbour Region have not been included in INPEXs
predicted characteristics for treated waste water. These include: dissolved oxygen,
NOx, ammonia nitrogen, filterable reactive phosphorus, chlorophyll , Escherichia
coli, and Enterococci spp. ANZECC Toxicant criteria (including BTEX and heavy
metals) were also omitted.
AFANT were concerned about the cumulative effects of discharges from existing and
future developments upstream of Blaydin Point and gave the view that treated
sewage and grey water should not be discharged to the Harbour. Recent beach
closures associated with Escherichia coli (E. Coli) bacterial contamination has
elevated the concern about faecal contamination and sewage in the Harbour.
INPEX commits to treating sewage to a high enough standard to allow all sewage
treatment plant waste water to be irrigated, however, as discussed in Section 4.7.1,
INPEX claim the requirements and opportunities for irrigation on Blaydin Point are
limited. INPEX predict that the operational contributions to annual loads of total N
and total P (after treatment) would amount to 0.5% and 0.9% respectively, when
compared with existing East Arm annual loads. This is based on INPEX meeting the
estimated wastewater characteristics for total N and total P in Table 2.
The Darwin LNG plant at Wickham Point implemented a closed-circuit re-use system
for normal operations with contingency for Wet season flows. Darwin LNG plant has
a Waste Discharge Licence authorising dry weather harbour discharge of reject water
from the demineralising RO plant and Wet season harbour discharge of reject water
from the RO plant, turbine air humidifier system and boiler blowdown , and water
from the treated water holding tank (including tertiary treated sewage effluent).
Darwin LNG plant actively discharges reject water from the RO plant to the Harbour
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65
72

year round. All other waste water is irrigated onsite. Darwin LNG operational waste
water volumes were predicted to average 288m3/d,.
INPEXs proposed daily discharge rate is calculated to be approximately 432m3/d.
Irrigable land surface may be a limiting factor for INPEX in undertaking similar landbased disposal to Darwin LNG. Further investigation of land-based disposal is
needed to clearly demonstrate that this is not a viable option for all Project waste
water, in Dry season conditions. INPEX needs to explore further the potential for reuse of treated water in the process, which would potentially reduce reticulated water
demand as well as discharge volumes.
If the discharge from the Harbour outfall is required after all other options are
exhausted, any waste water discharge would be regulated through the Environment
Protection Licence (EPL) under the WMPC Act. Discharges to the Harbour would
be required to meet Water Quality Objectives for the Darwin Harbour Region. Where
these are unable to be met INPEX would be expected to show just cause for seeking
approval for discharge to the Harbour.
All discharges to the Harbour require
monitoring for a period prior to commencement of discharge to establish baseline
data for determining impact of the discharge; validation of mixing zones where
applicable (i.e. where water quality objectives can not be met); monitoring during the
life of the activity; and during remediation of the site on cessation of the activity.
Monitoring would be conditional to any approval or licence which authorises a
discharge to the Harbour and would incorporate biological and chemical parameters.
INPEX should continue to seek and implement waste water reduction, re-use and
treatment within the plant design and for the life of the Project in accordance with
continuous improvement principles.

4.7.3 Oil Spills


The draft EIS provided a primary risk assessment of the potential for hydrocarbon
spills in the nearshore environment as a result of a gas export pipeline rupture or
leak, a leak of condensate at the jetty and a refuelling spill at East Arm Wharf.
Modelling of the expected dispersion patterns was also conducted to provide an
indication of the secondary risk of hydrocarbons reaching the shoreline.
The draft EIS also described the characteristics of the hydrocarbons that would be
implicated in a spill. For example, INPEX claims that that 70-80% of spilled
condensate would evaporate within the first day of release due to its high volatility
and complete evaporation would occur within 6 hours if spilled at the sea surface.
The Montara incident in the Timor Sea and Macondo well (Deepwater Horizon)
incident in the Gulf of Mexico drew the publics attention to the offshore oil and gas
industry and the possibility of significant hydrocarbon contamination in the marine
environment. Most of the concerns raised in the draft EIS were associated with
offshore well blow-outs in the Browse Basin, however, a number of respondents were
concerned that pipeline rupture scenarios had not been adequately covered.
INPEX subsequently modelled extra spill scenarios in Darwin Harbour and northwest of the Harbour associated with pipeline rupture. An increase in condensate
production at the Blaydin Point site was also flagged by INPEX, with a predicted
small increase in oil spill risk.
Analysis of the risks to the nearshore environment of Darwin Harbour from a worsecase pipeline rupture based on hydrocarbon characteristics and dispersion modelling
predictions indicates shoreline contamination by very low volumes of condensate
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65
73

would be likely; however, the likelihood of a pipeline rupture would be extremely low
and the impacts very localised. Further away from the Harbour, the risk to the NT
coastline is predicted to become negligible. The greater risk of spills comes from
leaks of fuels and condensate at the East Arm Wharf and INPEXs product loading
jetty respectively.
INPEX has an oil spill contingency plan (OSCP) that will be finalised and submitted to
the NT Government for approval under the Disaster Act prior to the commencement
of construction, commissioning and operations.
INPEX, in cooperation with industry partners, is also developing an operational and
scientific monitoring program to ensure that oil spill combat efforts are effective and
that timely and appropriate monitoring of environmental receptors at risk during a
large oil spill is undertaken. This is more applicable to the offshore component of the
proposal, however, there may be linkages with Darwin Harbour monitoring programs
to ensure that baseline knowledge is available in the event of an incident. Relevant
lessons arising from the Montara and the Macondo inquiries will be incorporated into
the proponents oil spill contingency plans and into the proponents selection,
resourcing and positioning of oil spill combat equipment and personnel.
Monitoring plans will de developed as part of the oil spill monitoring and management
procedures. It is expected that any monitoring activities following an oil spill would
include assessment of impacts on marine fauna including mammals, turtles, fish and
shore birds. Long-term monitoring of fish populations following an oil spill would be
required to determine whether the event caused recruitment failure.
The potential for oil spills is correctly identified as a risk in the EIS. The proponent
has detailed the measures it will take to monitor and manage oil spills, including the
development of site specific oil spill response plans. It is noted that the proponent
has access to a significant amount of expertise and equipment in the event of an oil
spill.

4.7.4 Noise
There were a few concerns relating to airborne noise attributed to the Project. These
included shipping noise in the evenings, in relation to the Deckchair Cinema; impacts
on Palmerston; and perceived noise modelling deficiencies.
Underwater noise issues are discussed in Section 4.6.1 of this Report.
INPEX assessed the potential impacts of noise from plant operations, emergency
flaring and pile driving on the community through noise modelling. Shipping noise
was not modelled.
The Deckchair Cinema, although an open-air venue, is situated in a relatively quiet
area on the edge of the Darwin CBD overlooking the Harbour. A concern was raised
that the standards required for background noise in cinemas could be affected by
noise from LNG tankers and the accompanying tugs and no relevant noise
predictions were provided in the draft EIS. INPEX used worse-case, predicted
impacts in Darwin from operating plant noise (in the 2535 dB(A) range) and the
measured ambient noise levels at various locations around Darwin to conclude that
noise levels at the Deckchair Cinema would not be affected by the Blaydin Point
plant or shipping at night. INPEX argued that the cinema would more likely be
affected by natural and other pre-existing sources (e.g. wind or traffic noise) and that
shipping would be conducted similarly to current shipping from the Darwin LNG plant.
The draft EIS indicated that the operating gas plant is not expected to cause ambient
noise levels in Palmerston to rise above around 40 dB(A); however, further modelling
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65
74

shows that with upset flaring, noise levels could be 45-55 dB(A) in Palmerston three
or four times per year for short periods if wind speed and wind direction are
unfavourable at these times.
To demonstrate relative levels of noise from recognised sources, INPEX provided
comparative examples of noise levels in the draft EIS. A noise level of 40 dB(A) is
equivalent to quiet radio music, a level of 50 dB(A) is equivalent to low
conversation, and a level of 60 dB(A) is equivalent to normal conversation.
It is accepted that the Project will create some noise and at times the noise levels
might exceed ambient noise levels in some residential areas. The noise is not
expected to be significant.

4.7.5 Air emissions


A small number of respondents to the draft EIS questioned the appropriateness of
the National Environment Protection (Ambient Air Quality) Measure (Air NEPM) for
the Darwin Region ambient conditions as well as the adequacy of proposed
monitoring for gas facility emissions at Blaydin Point. The Territory 2030 air quality
target aims to continue to meet or better national air quality standards across the
Territory.
INPEX conducted an assessment of existing ambient air quality in the Darwin
airshed, including inputs from Darwin LNG, the Channel Island Power Station,
Weddell Power Station and other area source emissions, and then considered the
additional emission sources from the Project to determine predicted ground-level
concentrations of key air pollutants produced by the Project.
EH Division contracted an air quality consultant to review the air emissions modelling
conducted by INPEX.
Use of the NEPM Ambient Air Quality criteria was determined by the Divisions
consultant to be appropriate for the Darwin Regional airshed in the absence of
specific impact assessment criteria specified for the Northern Territory, provided that:

They are compared to 100th percentile dispersion modelling predictions; and

Existing background concentrations of pollutants are considered.

INPEXs predictive air quality modelling showed that after the addition of the
emissions from the INPEX facilities, ground-level air quality in the Darwin region
would remain well within the criteria prescribed in the Air NEPM at all times for NOx,
photochemical oxidants (as ozone (O3)), and sulfur dioxide (SO2). PM10 could be
expected to exceed the criterion at times, which is allowed for to an extent in the
NEPM due to ambient spikes caused by natural events such as bushfires and dust
storms.
There is a small predicted increase in levels of pollutants resulting from the Project
and generally the risk of significant and wide spread air quality impacts from the
Project is considered to be low. Therefore, an extensive ambient air quality
monitoring program is not warranted. INPEX has committed to ambient air quality
monitoring during the operations phase to validate the assumptions used in the
modelling and demonstrate that ambient concentrations are broadly commensurate
to the levels predicted. INPEX will also consider sampling for particulates during the
Wet season and/or Dry season.
Additionally, an ongoing stack emission monitoring program is considered necessary
to ensure emissions remain within prescribed limits. The air quality monitoring will
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65
75

form part of the proponents Environmental Management Program and a requirement


of the EPL under the WMPC Act.
Recommendation 16
An air monitoring program is required for the life of the Project. The program
will be developed as a requirement of the Environment Protection Licence
under the Waste Management and Pollution Control Act.
The following point-source emissions testing should be conducted for the
program:

Quarterly monitoring for the first year of operation and annual thereafter
for NOx (plus temperature, flow, O2, moisture) at each stack servicing
the compressor turbines, power turbines, and hot oil heaters; and

Quarterly monitoring for the first year of operation and annual thereafter
for SO2 (plus temperature, flow, O2, moisture) at each stack servicing the
acid gas incinerators.

4.7.6 Greenhouse gas emissions


It is estimated that the Project will emit approximately 280Mt of greenhouse gases
over its 40-year lifetime. The majority of emissions (278Mt) will be emitted during the
operational phase, with approximately 2Mt emitted during the construction phase
(draft EIS, Section 9.6).
The draft EIS interchanges between presenting project GHG emissions as CO2
emissions and carbon dioxide equivalent units (CO2-e). The Supplement clarifies
(Supplement, page 259) that the draft EIS has been written on the basis that GHG
emissions over the 40-year life of the project are estimated to be 280Mt CO2-e,
comprising approximately 96% CO2 and 4% other GHGs (primarily methane (CH4)
and nitrous oxide (N2O)).
Average annual GHG emissions are estimated at approximately 7.0Mt of CO2-e,
noting that annual emissions will vary over the life of the project. On an average
annual basis, 5.2Mt of CO2-e will be emitted in the Northern Territory (74%), sourced
from onshore combustion emissions and reservoir emissions (Table 3).

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65
76

Table 3: CO2-e emissions as estimated in the draft EIS

40 year
Project
life (Mt)

40 year
annual
average, MT
per annum
(Mt/a)

Construction phase

2.0

n.a.

Operational
Phase

Offshore

72

1.8

Onshore
combustion

110

2.8

Reservoir
gas

96

2.4

Onshore

206

5.2

278

7.0

Annual average
as % of
Australian
emissions 2009

Annual average
as % of NT
emissions 2009

30

sub-total
Operational
sub-total
Total

280

1.2

Estimated average annual emission levels are equivalent to 1.2% of Australias GHG
emissions in 2009. Estimated onshore emission levels are equivalent to 30% of the
Northern Territorys GHG emissions in 2009.
The Australian Government has committed to reduce Australias carbon pollution to
25% below 2000 levels by 2020 if the world agrees to stabilise levels of GHG in the
atmosphere at 450 parts per million or lower. If global agreement is unable to be
reached on a 450 parts per million target, the Australian Government has committed
to reduce Australias emissions by between 5 and 15% below 2000 levels by 2020.
The Australian Government has also committed to a long-term GHG emissions
reduction target of at least 60% below 2000 levels by 2050.
The Northern Territory Governments Climate Change Policy sets an aspirational
goal of reducing the Northern Territorys emissions by 60% by 2050, compared to
2007 levels.
Average annual GHG emissions from the INPEX project would represent
approximately 3.2% of the Australian Governments long term reduction target for
2050, and 76% of the Northern Territorys aspirational goal for 2050 (refer Table 4).

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65
77

Table 4: Comparison of Project annual average operational GHG emissions against


National and NT targets

Target

GHG Emissions
Target
Mt/CO2-e/annum

INPEX 40-year
annual average
operational GHG
emissions Mt/CO2e/annum

INPEX contribution
as a % of Target

National target:
60% below 2000*
levels by 2050

221.88

7.0

3.2%

Northern Territory
goal: 60% below
2007# levels by
2050

6.879

5.2

75.6%

*According to the National Greenhouse Gas Inventory (May 2011), 2000 levels are
estimated to be 554.7Mt CO2-e.
# According to the State and Territory Greenhouse Gas Inventory (2009), 2007 levels
are estimated to be 17.197Mt CO2-e.
The INPEX project would generate a significant increase in national and Northern
Territory GHG emissions. The INPEX project would be the largest single industry
emitter of GHG in the Northern Territory.
The draft EIS compares life cycle GHG emissions from the use of LNG and coal for
electricity generation. It states that a primary advantage of the use of LNG as an
energy source is that the quantity of GHGs emitted over the full life cycle is
significantly less than the comparable life cycle emissions from either coal or fuel oil,
as a means of delivering the same amount of energy (draft EIS, page 428). The draft
EIS further states that in a global context, the use of Ichthys LNG to generate
electricity in Asia will therefore likely result in a significant reduction in CO2 emissions
(draft EIS, page 429). The substitution of gas for coal is questioned by a number of
respondents to the draft EIS.
INPEX LNG does have the potential to replace the use of coal, which would result in
a reduction of GHG emissions over the full life cycle. There is no guarantee,
however, that this will be the case. As stated in the Supplement (page 253), the
degree of fuel displacement by Ichthys LNG cannot be known until the LNG is
consumed. The emissions generated in the consuming country are more
appropriately addressed by that sovereign state.
Comparisons in the draft EIS and Supplement reveal that the project would be more
emissions intensive than many other LNG projects around the world. This is largely
due to the high proportion of CO2 naturally present in the Brewster and Plover gas
reservoirs, and the relatively energy-intensive offshore facilities.
The draft EIS outlines a number of technical abatement measures that have been
identified for the project (draft EIS, Section 9.8). These measures represent a
reduction in GHG emissions of 0.39Mt/a and have been included in INPEXs annual
average production estimate of 7Mt/a. In the Supplement, INPEX commits to
additional measures in its base-case design, including a combined cycle power plant
for onshore electricity production and a subsea electrical power-sharing cable
between the offshore infrastructure components. Emission reductions from these
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65
78

measures are estimated to be 0.3 0.35Mt/a and 0.1 0.2Mt/a respectively from the
annual average of 7Mt estimated in the draft EIS.
INPEX commits to producing a detailed GHG management plan prior to the
commissioning of the onshore facilities that will include an updated GHG emission
estimate and consolidate measures for technical emissions abatement and offsets.
Benchmarking the technology of the onshore gas processing plant and related
abatement measures detailed in the GHG management plan would inform the
relevant NT approval under the WMPC Act.
Large scale GHG emission reductions beyond technical abatement measures could
potentially be achieved through geosequestration and offsetting GHG emissions from
the project. The draft EIS outlines INPEXs investigations into geosequestration of
reservoir CO2 and states that INPEX may consider its implementation if technically
feasible and commercially viable.
INPEX is investigating reforestation as a GHG offset and has established a
biosequestration assessment project in Western Australia. In the Supplement INPEX
expresses its interest in two savanna fire management projects in the Northern
Territory to achieve GHG emission reductions and biodiversity protection. INPEX
states that it is continuing to examine the feasibility and cost-effectiveness of offsets,
with no firm commitments made by INPEX in the draft EIS and Supplement.
Submissions to the draft EIS commented on the scale of GHG offsets, with many
seeking 100% offset of the projects GHG emissions. Given the significance of the
projects GHG emissions, commitments to GHG offsets are expected to feature
prominently in the GHG management plan to be provided by INPEX as additional
measures to reduce the GHG impact of the project.
The Australian Government is pursuing the implementation of a carbon price
mechanism that will start with a fixed price period for three to five years before
transitioning to an emissions trading scheme. The Australian Government is aiming
to commence the carbon price on 1 July 2012, subject to the ability to negotiate
agreement with a majority in both houses of Parliament and pass legislation in 2011.
The extent of coverage of the LNG sector in the proposed mechanism is uncertain at
this point in time.
The GHG emissions from the onshore component of the Ichthys LNG project will be
regulated by the Northern Territory Government through an EPL under the WMPC
Act. The ongoing application of the Northern Territory regulatory framework will need
to be reviewed should there be progress in establishing a national carbon pricing
mechanism or alternative national regulation of GHG emissions. If, at any time in the
future, the GHG emissions from the Ichthys LNG Project are regulated under national
legislation to reduce GHG emissions, then INPEX may no longer be subject to
Northern Territory regulation of GHG emissions.
INPEX has recognised in the draft EIS that it will be required to report its GHG
emissions to the National Greenhouse and Energy Reporting System.
This assessment concludes that the project will result in a significant increase in NT
and Australian GHG emissions.

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65
79

Recommendation 17
That INPEX submit to the Northern Territory Government a Greenhouse Gas
Management Plan covering onshore GHG emissions prior to commissioning of
the onshore gas processing plant. The GHG Management Plan should be
submitted within a timeframe that enables its consideration in the issue of an
Environment Protection Licence under the Waste Management and Pollution
Control Act.
Recommendation 18
That the Greenhouse Gas Management Plan include, but not necessarily be
limited to, the following:

An updated greenhouse gas inventory for the proposal;

Measures adopted to mitigate greenhouse gas emissions;

Demonstration of the adoption of current best practice in the design and


operations of the onshore gas processing plant in terms of GHG
emissions by benchmarking technology against other national and
overseas facilities;

Commitments to periodic review and, where practicable, continuous


improvement in technology and operational process to further mitigate
GHG emissions per tonne of LNG produced;

A report on the status of investigations into geosequestration; and

Commitments to measures to offset the GHG emissions from the


onshore gas processing plant, preferably including measures
implemented in the Northern Territory.

4.8 Cultural impacts


The potential for significant but unlocated maritime heritage to exist within the project
footprint was not adequately addressed in the draft EIS.
Remote sensing surveys were conducted at the dredge spoil ground and parts of the
dredge footprint in Darwin Harbour. These surveys were designed to assess the
bathymetry of INPEXs proposed work area and, in particular, to detect any
significant seabed features that might be impacted. INPEX did not engage the
services of a maritime archaeologist during the remote sensing surveys and
questions were raised about the appropriateness of the surveys to specifically detect
potential maritime heritage.
Although the surveys detected high-relief wrecks, the most notable being the
Catalina Six, many of the remaining, unlocated wrecks in the Harbour are thought to
be very low-relief and might not be detected through non-targeted survey methods.
It was recommended in response to the draft EIS that the raw remote sensing data
be provided to a qualified maritime archaeologist to determine whether:

The surveys themselves were sufficient in terms of the equipment used, the
areas they covered, their objectives and their calibration to identify sites; and

Whether anomalies that had characteristic signatures (associated with maritime


sites) were identified and then verified.
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65
80

The scope of work for the consultancy included a review of the potential resource, an
assessment of the survey work (in terms of its context, function and parameters), a
review of the raw data, and a final recommendation as to whether further work was
necessary.
Two consultants were engaged, URS and Cosmos Archaeology. Each consultant
provided a desktop review of the potential maritime heritage resource that could exist
in Darwin Harbour, a critical exercise as it defined the search objective and the risk.
The reports then assessed the suitability of the various remote sensing tools to
detect the potential maritime heritage as defined in the resource.
The URS report concluded that nine shipwrecks remain unlocated and that these
wrecks would have been detected by the sonar methods used, had they been
present. Cosmos Archaeology concluded that the unlocated resource is closer to 39
with up to 25 planes also lost in Darwin Harbour. Further, the Cosmos report
concluded that the potential characteristics of some of these wrecks would limit
detection using sonar, but could possibly be located through appropriately-calibrated
magnetometer surveys. Both magnetometer and sonar methods are considered valid
techniques, with sonar able to detect relatively high-relief anomalies and
magnetometers able to detect very low-relief anomalies with high ferrous (iron)
content.
It is considered that URS did not have sufficient understanding of the potential
heritage resource, particularly the range of site types and the number of wrecks that
might exist, to conclude that the surveys were adequate. A significant limitation of the
URS assessment was the failure to recognise the mass deposition of small pearling
luggers following the cyclone of 1897. These are potentially highly significant, but low
relief, wrecks which need to be carefully considered in relation to this Project.
The Cosmos Archaeology report found that INPEXs remote sensing reports did not
appear to have assessed the data for the potential to locate low-profile, timber-hulled
wrecks. The report also found that a series of anomalies identified in the surveys
had not been properly verified or were new findings based on a review of the raw
data. It noted that non-targeted remote surveys or dive verification were not sufficient
to identify maritime heritage and made three recommendations:

Raw data that had not been provided previously by INPEX should be provided for
further analysis;

The magnetometer survey of Area A (the navigation channel, turning basin and
berthing pocket dredging footprint) should be completed; and

A diver inspection/verification should be carried out on the anomalies identified in


the remote sensing surveys.

INPEX has not stated whether it will accept or reject the recommendations presented
by either consultant.
The Heritage Branch of NRETAS has an overarching responsibility to act on behalf of
the Northern Territory Government to conserve the unique and diverse cultural
heritage of the Territory, including maritime heritage. This includes, but is not limited
to, identifying places and objects that may warrant protection under the NT Heritage
Conservation Act. The Branch also acts on behalf of the Commonwealth Government
in administering the Commonwealth Historic Shipwrecks Act, which applies in Darwin
Harbour. There is an obligation under this Act to notify the Australian Government of
the discovery of any wreck older than 75 years old, which are automatically protected
under the Act.

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65
81

In light of these obligations, the Cosmos Archaeology report recommendations are


supported. It would be prudent for INPEX to adopt these recommendations, in
particular, the recommendation to verify the anomalies identified in the surveys. If
these measures are adopted by INPEX, it would be considered that all reasonable
steps have been taken to address the issue of unlocated maritime heritage.
Recommendation 19
INPEX should conduct a diver inspection/verification of anomalies identified in
the data from remote sensing surveys.
Additionally, to ensure the dredging footprint is adequately surveyed for
unlocated maritime heritage, INPEX should consider:

providing previously unavailable remote sensing raw data for further


analysis; and

Completing the magnetometer survey of the navigation channel, turning


basin, berthing pocket and MOF footprint in Darwin Harbour.

4.9 Socio-Economic impacts


Key priorities of Territory 2030 are Economic Sustainability and Society, which
include a series of targets relevant to the INPEX project.
The INPEX project is key in meeting the following Territory 2030 targets:
The Territory continues to secure new private sector investment to drive economic
growth and expansion.
Support the continued contribution of the resources sector in the NT economy.
Expand the manufacturing industry with a particular focus on gas-based industry.
Establish Darwin as a key centre for oil and gas operations, maintenance and
workforce.
The development of the INPEX gas project would generate strong economic growth
in the Northern Territory and Australia, creating significant new employment
opportunities, generating considerable growth in exports and a stronger balance of
trade, and further stimulating economic activities and industry development. This is in
keeping with the Territory 2030 target continue to grow the Territory economy.
Economic analysis by the NT Government concurs with the economic benefits
outlined by INPEX in the draft EIS. In summary:

The Northern Territory GSP is expected to grow by $4095 million annually from
the base case, an increase of about 18%.

While the GSP captures increase in output and production, the changes in private
consumption expenditure in the Territory provides a useful indicator of actual
expenditure in the Territory and the impact on the welfare of Territorians. The
INPEX gas project is estimated to increase real private consumption in the
Territory by $175 million annually from the base case, an increase of 1.6%.

At the peak of construction phase over 2000 jobs would be created and
approximately 300 people would be employed on an ongoing basis in the
operational phase of the proposed project. The proposed project would also
indirectly generate significant employment in the Territory economy.

The INPEX project has the potential to assist the NT to meet a number of identified
targets in the Territory 2030 document.
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65
82

As set out in the Territory 2030 strategy, consideration of targets across all key
priority areas is necessary and while the project meets targets outlined in Economic
Sustainablity it will have a greater net positive impact if negative impacts are
identified, mitigated and managed effectively.
Impacts to the social fabric of the local and regional community are expected to be
significant and consideration of these issues is required by Territory 2030, which
includes the (Society) targets:
Ensure there is sufficient serviced land to support investment and population growth.
Develop Darwin as one of Australias most affordable cities.
Improve access to accommodation.
A balanced housing market offering good value for money and affordability, ultimately
becoming one of Australias most affordable housing markets, across all market
segments.
While the direct economic benefits and the flow-on impacts to the Northern Territory
and Australia are expected to be substantial over the economic life of the project
there may be negative social aspects that require careful management, such as
maintaining labour availability for existing industries. The degree to which the INPEX
project will impact on these aspects has been assessed to some extent in the EIS,
however it is considered that ongoing review and management of impacts will be
necessary.
Recommendation 20
A Social Impact Management Plan (SIMP) is to be developed by INPEX in
collaboration with NT Government. The SIMP must address social issues that
have been raised in the EIS and this assessment report. The SIMP should also
be informed by the outcomes of a Health Impact Assessment undertaken as
part of the accommodation village assessment process.
Specific issues for consideration in the SIMP are discussed further in the sections
below.

4.9.1 Impact on housing market


The construction workforce is expected to number between 2000 and 3000 people
during the five years it will take to construct the onshore processing plant, with
around 300 personnel required for the normal operations of the plant.
Potential impacts on housing affordability and availability are key issues, with
stakeholder concerns that the Project, particularly during the construction phase, will
place significant pressure on Darwins already constrained housing market.
INPEX has acknowledged and addressed the issue in the EIS, which outlines
controls to manage and reduce additional pressures on the housing market. INPEX
proposes to construct an accommodation village to house construction workers and
is developing an accommodation strategy to identify accommodation solutions for
regular personnel during the operations phase.
INPEX did not consider it practical to apply risk assessment to the effects of the
Ichthys Project on the Darwin housing market as wider economic conditions also
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65
83

affect property values and an accurate assessment of any impacts directly


attributable to the project cannot be made.
Housing affordability is an issue also identified in Territory 2030, which includes
targets aimed at achieving affordable housing markets and ensuring Darwin
becomes one of the most affordable cities. The inclusion of these targets indicates a
Government commitment to this issue and Government will therefore need to
consider and account for INPEXs influence on housing affordability. Examples exist
in other parts of the country which can be referred to for example, the effect on
housing affordability associated with the development of the LNG industry in
Gladstone, Queensland.

4.9.2 Accommodation strategy


The proposed accommodation village at Howard Springs will house the majority of
the construction workforce and seeks to minimise short-term impacts on the housing
market that might otherwise be caused by a large influx of project personnel.
As previously discussed, the accommodation village is not considered within the
scope of this assessment. The assessment of the environmental and social impacts
of the accommodation village will be undertaken separately and is scheduled for later
in 2011.
An accommodation strategy is being developed to identify and investigate
accommodation requirements and options for regular project personnel during the
operational phase, as well as for short term visitors during the construction phase.
The strategy will identify means of accommodating up to 450 additional people in
facilities to be developed in conjunction with private developers.
The aim of the accommodation strategy is to minimise the impact of INPEX
personnel on the local housing market while maximising the opportunities to attract
and retain suitable employees.
Due consideration has been given to measures to help minimise potential pressure
on the housing market as a result of the Project and the overall approach is
considered to be appropriate.

4.9.3 Cost of living


Territory 2030 has identified affordability as one of its targets Develop Darwin as
one of Australias most affordable cities and has stated that a sub-committee
(under the auspices of the Capital Cities Committee) will be appointed to develop a
strategy to achieve this goal.

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65
84

The potential influence of the Project on housing affordability has already been
discussed and is one of the factors that will need to be considered by the appointed
sub-committee. The impact of increased demand on services resulting from the
Project (due to increases in population from INPEX workforce) and the associated
impact on cost of living will also need to be considered.

4.9.4 Employment
INPEX and its Ichthys Project joint venture partner Total have donated $3 million
towards the construction of a trade training centre in recognition of the Larrakia
people who are the traditional owners of the land and sea where the proposed
INPEX onshore plant will be located (Blaydin Point). The Larrakia Trade Training
Centre (the Centre) was officially opened in April 2011.
The Centre will provide training and facilitate employment opportunities for youth
from all sectors of the community including Larrakia and other Aboriginal and Torres
Straight Islander peoples.
Approximately 300 students are already enrolled to learn professional skills such as
electrical, automotive mechanics, metal fabrication and plumbing.
Similarly, business opportunities in the pre-construction, construction and the
operational phases for the local industries and businesses have been formalised in
an Industry Participation Plan.
These initiatives are in keeping with the Territory 2030 targets The Territory
continues to grow the size and skills of its workforce to meet the growth target,
increase Indigenous/ non-Indigenous business partnerships and improve
Indigenous employment rates.

4.9.5 Health
The EIS states that the Projects most intense socio-economic impacts are likely to
be associated with the construction phase of nearshore and onshore development
areas, and from a health perspective, it is the proposed accommodation village at
Howard Springs that is of key interest. The construction of a 2000 3000 person
accommodation village equates to the development of an entire new suburb in an
existing rural area with limited infrastructure and services.
As stated earlier in this report, the accommodation village is being assessed under a
separate approvals process. Social and environmental issues expected with this
component of the proposal will therefore be assessed further in subsequent approval
requirements.
To assist in the assessment of the accommodation village the Department of Health
has requested that INPEX conduct an appropriate Health Impact Assessment (HIA)
of the potential adverse effects to health from the proposed accommodation village,
considering a range of potential outcomes for acute and chronic effects as well as the
potential risks to the provision of health services. INPEX has undertaken extensive
consultation, which will have assisted in identifying a range of environmental, social
and health factors.
It is understood that INPEX has committed to undertaking a HIA of the
accommodation village element of its proposal.

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65
85

4.9.6 Impact of temporary workforce


As quoted in the above section, the construction phase was identified by INPEX as
having the most intense socio-economic impacts, and this would include the impact
of a temporary workforce, not only in terms of increased demand placed on public
and private services and infrastructure but due to the integration of 2000 3000
people within the existing social fabric of Darwin.
The Territory 2030 document has targets specific to public amenity of centres,
personal safety, road safety, social inclusion, access to healthcare services, alcohol
consumption, illicit drug use, etc. In meeting these targets the potential impact of
INPEX needs to be taken into account and managed. At the very minimum, an
assessment needs to occur to determine potential stresses on social services (e.g.
health, emergency and policing).
Some of the management measures that could be implemented include:

Requiring workers to undertake health assessments;

Developing a personal code of conduct for workers;

Implementing a complaints procedure to investigate any complaints of


unacceptable behaviour from construction workers and action taken where
necessary;

Drug and alcohol management procedures;

Employing a Community Relations Manager;

Including cross-cultural training during site induction;

The provision of recreational facilities for construction workers.

INPEX has a role in ensuring that the negative socio-economic impacts of its
temporary workforce are minimised, however, the success of any measures
implemented by the company will be dependent upon management responses and
measures put in place by Government.
Some of the issues to be considered by Government include the availability of health
services, the adequacy of police services during construction, and the adequacy of
existing recreation facilities to cater for construction workers.
There are examples within Australia that can be drawn upon to understand the
potential socio-economic impacts a FIFO or temporary workforce can have on an
existing community. This information can be used to undertake a social impact
analysis and to develop a SIMP in accordance with Recommendation 20 of this
Report. The dual role of both INPEX and the Government in managing social impacts
demands a collaborative approach when developing a SIMP.

4.9.7 Tourism
A number of concerns were raised about issues that are likely to have impact on the
tourism industry:

The potential for the project to impact on the labour market which will place
pressure on the availability of labour for the tourism industry;

Impacts on housing availability and affordability (having flow on effects for


seasonal influx of staff in peak tourism season);

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65
86

Competing demand for construction workers driving up construction costs and


potential to undermine investment in new tourism infrastructure;

Impact on the clean, green image of the NT; and

Impact on tourism value of the Harbour through reduced visual amenity, marine
pests and impact on marine flora and fauna.

The varied perspectives of different segments of the tourism industry were


acknowledged and INPEX have committed to engage on an ongoing basis with the
tourism industry to mitigate issues and maximise opportunities.
It is recognised that the Project is likely to benefit the industry through increased
visitation associated with the Project workforce.
INPEXs commitment to ongoing engagement with the tourism industry is
encouraged and supported.

4.9.8 Visual Amenity


Many submissions raised the issue of the visual impact of the LNG Plant on Darwin
Harbour and the associated loss of amenity. The natural look of Darwin Harbour
was seen as being important, and submissions referred to loss of visual amenity,
particularly from Stokes Hill Wharf. This is also captured by the target our
communities are more in touch with their location, climate, people and sustainability
identified within the Territory 2030 document, which refers to the importance of urban
design (relating to the amenity of a location).
INPEX acknowledges the loss of some visual amenity in Darwin Harbour because of
the onshore facilities at Blaydin Point but notes that vistas will be mitigated to some
extent because the project is a further 3km than the existing Darwin LNG plant when
viewed from Stokes Hill Wharf.
The fact that a large proportion of Darwin Harbour remains undeveloped is significant
from a tourism perspective. The NT is promoted on the basis of nature and culture
and the beauty of Darwin Harbour is an important tourism asset. Accordingly, any
development that reduces the visual amenity of Darwin Harbour needs careful
consideration in terms of the impact on the destination from a tourism perspective.
However, the location of the development is not an area of the Harbour that actively
conflicts with current marine based tourism activity, other than recreational and
possibly some commercial fishing tours.
The impact on the visual amenity of Darwin Harbour is a significant social issue and
must be taken into consideration by INPEX when designing the site facilities. INPEX
has already considered this to some extent in the design of the product loading jetty.
Visual amenity is also recognised as an issue requiring consideration at the strategic
planning level when Government identifies areas for specific land use types. In this
respect, Government has accepted that the amenity in the East Arm area will be
changed to accommodate this Project.

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65
87

4.10 Infrastructure and services


4.10.1 Road and Traffic Impacts
The EIS is light in detail regarding the social and economic impacts that the transport
component of the Project would have. In addition to the significant increase in wear
and tear on the Darwin road network, there are likely issues with road safety traffic
congestion and delays to the travelling public. The transport component of the
Project may also require vehicles and personnel that are not available in the NT at
present. The impact the transport component will have on the existing commuters
and the flow on effects is of concern.
The Department of Lands and Planning is working closely with INPEX through the
Transport Subcommittee of the Gas Taskforce. The Subcommittee is continuing to
develop strategies and options to resolve transport issues and mitigate key risks that
result from the flow of logistics in support of the Project.
Road transport and traffic issues will need to be managed through INPEXs traffic
management plan. This plan should be prepared in consultation with Government
and will form part of the proponents Environmental Management Program, in
accordance with Recommendation 23 in Section 4.13 of this Report.

4.10.2 Water supply


Concerns were raised in submissions to the draft EIS that INPEX propose to use
significant volumes of potable water from Darwins water supply during construction
and operation as the current supply is being challenged by existing demand.
The draft EIS separated levels of water demand by Project phase as follows:

Construction: potable-water demand would gradually increase to approximately


1200m3/d with increased personnel and construction requirements including
service water and water required for concrete batching and dust suppression (in
the Dry season).

Precommissioning: Peak water demand for this phase would be during the tank
hydro-static testing. During this period of approximately 16 months, water
demand could peak at approximately 7800m3/d, which would be required
24 hours a day, intermittently for a few weeks. INPEX committed to reuse tank
hydrotest water where technically feasible.

Operations: Approximately 2000m3/d would be required over the plants projected


lifetime of approximately 40 years with some variation during periodic shutdowns.

INPEX stated that recent advice from the Power and Water Corporation (PWC)
indicated that there would be sufficient capacity to accommodate the water demands
of the Project, however, INPEX are continuing to investigate alternatives to using
PWC water. These include incorporating water efficiency measures into the design of
the onshore gas-processing facility and the preparation of a water conservation
management plan that will form the framework for the identification and capture of
water-efficiency, conservation and management initiatives.
Although INPEX has committed to water conservation, specific strategies such as
ensuring that the onshore plant has a water reuse component on the wastewater
stream have not yet been built into the project design. INPEX has indicated that its
power generation may utilise air-cooling technology. This would considerably reduce
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65
88

the water requirements of the plant and is supported, provided that any negative
impacts specific to this technology are considered.
The Territory 2030 Strategic Plan encourages Government, industry and the
community to deliver on the objectives, and meet targets where ever possible.
Efficient use of water is such a target that INPEX and Government will need to work
towards.
Water conservation is becoming increasingly important in the Darwin Region due to
the growing demand on the resource and the need to plan for future water supply.
INPEX must ensure that water conservation measures are built into the plant design
and commit to continuous improvement in minimising its water use.
Recommendation 21
The Blaydin Point gas facility must incorporate best-practice water
conservation measures into the design. The proponent must commit to
continuous improvement in minimising potable water use.

4.11 Safety hazards


There were a number of concerns about the hazards of the proposed gas facility and
the safety of LNG. Many of the questions related to structural stability of the plant and
equipment, and environmental conditions impacting on plant safety and security. The
design of the plant during the FEED carefully considered many of these issues (i.e.
cyclonic conditions, lightning protection, tank construction, societal safety, etc). Other
NT Government Agencies were also consulted in the FEED stage including the NT
Police, Ambulance, Fire and Emergency Services.
Under current legislative processes within the Northern Territory, and given its size,
this facility will be classed as a Major Hazard Facility, which requires a Major Hazard
Facility Licence. As part of the licence requirements the proponent will be required to
develop and present for acceptance a document called a Safety Case.
The Safety Case documents the operators commitments to reducing risks to a level
that is as low as reasonably practicable given current technology and safety
information. The safety case describes arrangements for health and safety that are
used by managers, supervisors and the workforce to understand health and safety
issues and their controls.
Safety Cases address the following matters regarding the health and safety of people
at or near a facility:

Identification of hazards and assessment of risks;

The implementation of measures to eliminate the hazards or otherwise control the


risks;

A comprehensive and integrated system for management of the hazards and


risks; and

Monitoring, auditing, review and continuous improvement.

The Safety Case will need to demonstrate that all credible major risks have been
identified, control measures considered and implemented appropriately, and then
provide a system whereby these controls are assessed and finally demonstrated to
be adequate for the risks identified. It specifies the risk prevention measures as well
as strategies for reducing the effects of any major credible accident should one
occur.
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65
89

The Safety Case also requires the proponent to address safety issues including:
hazard identification, assessment and control of risks, safety management systems,
induction training and education, emergency planning, reporting of incidents and near
misses, employee responsibilities, community information and security. It is prepared
in consultation with other relevant Government agencies and local councils.
This safety assessment is a separate process and will be undertaken after the
environmental assessment process but prior to the commissioning of the facility and
plant (first gas).
Although there will be relevant information provided by the proponent to the public in
relation to dealing with emergency requirements, other information including the
Safety Case cannot be released by NT Worksafe for public comment due to the
legislative, security and proprietary aspects of this operation.
INPEX has provided within the draft EIS a QRA to analyse the risk of particular
hazards associated with an operating facility.
To improve public confidence, it is considered that greater transparency in this
process is needed. Government could achieve this by providing the community with
Project-specific information about the decision-making that informs the Safety Case
for the Major Hazard Facility Licence.

4.12 Decommissioning
The community expectations of a project, once it is at the end of its life are:

the site will be decommissioned;

the community will not be subject to the consequence of legacy issues from the
former use of the site; and

the land is suitable for a subsequent use.

This requires the proponent to consider the need to decommission the site in its initial
planning, as well as how a site may be decommissioned and the likely appropriate
beneficial use for the site. It is difficult to determine the requirements for
decommissioning for a site at the start of a long project. This is in part due to new
technologies and processes that may be developed in the intervening period and
changes in community expectations leading to changes in what is considered best
practice. However, consideration must be given to decommissioning early in the
event that the Project does not continue for its full predicted life.
This need to consider decommissioning at the start of the project is acknowledged by
INPEX in its Provisional Decommissioning Management Plan While the
requirements of decommissioning will depend upon the regulations at the end of the
useful life of the Project, consideration of decommissioning feasibility will be
incorporated into the design of each facility.
The primary issue raised by respondents to the draft EIS was the management of
waste arising from the decommissioning process. The Provisional Management Plan
states that detailed waste management documents will be developed and
implemented, as will a series of other management plans to address matters such as
noise, dust and acid sulphate soils.
The decommissioning process outlined in Chapter 4 of the draft EIS corresponds
broadly with the process agreed by the proponent and the Northern Territory
Government on July 18 2008, within the Ichthys LNG Project Development
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65
90

Agreement. The Agreement contemplates a process for the decommissioning and


eventual transfer of the site back to the Northern Territory. The Agreement stipulates
the notice period, process to come to an agreed end use for the site, development
and approval of a decommissioning plan, security, eventual transfer of the site to the
Northern Territory Government and interaction with legislation.
The process of decommissioning the onshore facility does have the potential to
significantly impact upon the environment.
Recommendation 22
Prior to decommissioning, the proponent should lodge a notice with the
Minister for the Environment (or the appropriate authority at the time of
decommissioning) for assessment under the relevant legislation at the time
outlining the proposed action and its significance to the environment.

4.13 Environmental Management Program


A number of environmental management plans (EMPs) have been proposed through
the course of the assessment process for the Ichthys Gas Field Development
Project. All management plans and procedures proposed to be developed for the
project must be approved by, or developed to the satisfaction of, relevant
government agencies and in consultation with key stakeholders in the timeframes
specified.
These approved plans and procedures will be one of the primary tools by which the
proponent will implement management and monitoring commitments made in the EIS
and the recommendations detailed in this Report.
The proponent employs a structured approach to the management of Health, Safety
and Environment (HSE) issues via a formal and documented HSE Management
Process based on a continuous improvement model as defined in internationally
recognised standards (AS/NZS ISO 14001:2004, Environmental management
systemsRequirements with guidance for use; and AS/NZS 4801:2001,
Occupational health and safety management systemsSpecification with guidance
for use).
This system will form the overarching framework for the management of
environmental, health and safety issues. A key component of the HSE Management
Process is the development and implementation of EMPs which detail the
environment protection and management measures and controls necessary to avoid,
reduce or mitigate the environmental impacts of the Project.
The implementation of the HSE Management Process should provide for continual
improvement in the management plans and performance of the Project as the
management system elements and the requirements within each of these are applied
i.e.. policy, planning, implementation, audit and review.
It is vital to the performance of the project that the requirements in management
processes, plans and procedures are incorporated into the proponents tendering and
contracting procedures and that all contractors are fully aware of, and act in
compliance with, relevant management plans. INPEX intends to develop work
instructions and procedures to support the EMPs and ensure that they are effectively
implemented.

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65
91

The provisional EMPs referred to in the EIS have been structured by the proponent
to provide the core information required to guide the development of construction
EMPs (CEMPs) and operations EMPs (OEMPs).
Provisional Environmental Management Plans (Construction and Operations)
developed for onshore and nearshore activities in the EIS included:

Acid Sulfate Soils Management Plan

Air Emissions Management Plan

Bushfire Prevention Management Plan

Cetacean Management Plan

Decommissioning Management Plan

Dredging and Dredge Spoil Disposal Management Plan

Heritage Management Plan

Greenhouse Gas Management Plan

Liquid Discharges, Surface Water Runoff and Drainage Management Plan

Onshore Spill Prevention and Response Management Plan

Piledriving and Blasting Management Plan

Quarantine Management Plan

Traffic Management Plan

Vegetation Clearing, Earthworks and Rehabilitation Management Plan

Waste Management Plan

A number of the above plans also apply to EPBC Act matters. The EMPs applicable
to the management of impacts on the Commonwealth marine environment include:

Provisional Decommissioning Management Plan

Provisional Liquid Discharges, Surface Water Runoff and Drainage Management


Plan

Provisional Waste Management Plan

The EMPs applicable to the management of impacts on marine threatened and


migratory species are:

Provisional Cetacean Management Plan

Provisional Piledriving and Blasting Management Plan.

The EMP applicable to management of impacts on terrestrial threatened and


migratory species is:

Provisional Vegetation Clearing, Earthworks and Rehabilitation Management


Plan.
Any management actions contained within these plans that are applicable to the
offshore area are considered to be the responsibility of the Australian and Western
Australian Governments.
As the proponent is not intending to undertake drill and blast activities except as a
contingency, the Provisional Piledriving and Blasting Management Plan will be
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65
92

divided into two separate plans, a Piledriving Management Plan and if required, a
Blasting Management Plan.
In addition to the above management plans, Recommendation 20 of this Report
provides for the preparation of a SIMP collaboratively with Government. The SIMP
will need to be included as part of the Environmental Management Program and will
include a HIA.
Proposed monitoring programs are associated with many of the EMPs. These
monitoring plans may be detailed in the management plans or developed as separate
documents linked to the relevant management plans.
Another important consideration for this Project is transparency and accountability in
impact management. Some regulatory instruments provide for public availability of
management plans; others do not. The proximity and importance of this development
to Darwin Harbour and the Darwin regional community increases the importance of
transparency. Therefore, as well as seeking engagement with key stakeholders in the
preparation of these management plans, the proponent is encouraged to make the
final EMPs available to the wider public.
Similarly, the proponent is encouraged to continue to engage and inform the
community as development progresses. It is expected that this would include
reporting of monitoring outcomes and ongoing management actions to minimise
impact.
EMPs are to be provided to Government for approval ahead of the activity for which
the EMP is intended to manage or prior to the commencement of any works. For
the purposes of this Assessment Report, works means any tasks which would
require/cause any physical disturbance to any project area offshore or onshore.
Examples include drilling, clearing vegetation above the ground surface, trenching,
grading, discharging, dredging, etc.
Recommendation 23
All Environment Management Plans for the Ichthys Gas Field Development
Project are to be submitted to Government for approval prior to
commencement of any works for which the plans apply.
In preparing each plan, the proponent will include any additional measures for
environmental protection and monitoring contained in this Assessment Report
and Recommendations. The plans shall be referred to relevant Northern
Territory Government agencies and key stakeholders for review prior to
finalisation. The plans shall form the basis for approvals and licences issued
under relevant legislation.
The proponent should provide public access to final environmental
management plans and a reporting mechanism to inform compliance with the
plans.
A number of key recommendations in this Report include requirements for the
proponent to consult with an expert panel in developing the relevant management
plans. The expert panel would be called upon to provide advice on scope and
appropriate methodologies in management plans for the key issues associated with
the Project. This is important where advice from objective experts is essential in
developing effective monitoring programs and management tools to minimise
impacts. The relevant activities for which impacts are expected to be most significant
and recommendations have been provided include:

Dredging and dredge spoil disposal; and


Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65
93

Blasting, if required.

The form of the expert panel will need to be determined in agreement with
Government and the proponent. It is expected that the model used in Chevrons
Gorgon Project in Western Australia could be used for this Project.
Recommendation 24
An expert panel should be formed to provide objective and expert support in
the development of appropriate management plans and monitoring programs
for dredging and dredge spoil disposal, and for blasting if required, as
recommended in this Report. The final form of the expert panel will be
determined in agreement between Government and the proponent.

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65
94

5 Conclusion
The environmental impacts of the project can be managed by delivering the
commitments made in the EIS and the Supplement and by rigorously applying the
recommendations and management plans and strategies described in this
assessment.
Although the likely impacts of the Project have been identified and are relatively well
understood, there remains a high level of uncertainty in terms of the precise nature
and extent of impacts and changes, particularly to the ecology of Darwin Harbour and
the region. This uncertainty is largely due to the gaps in data informing the
environmental impact assessment process. Consequently, the proponent,
government and community will be reliant on intensive, post-assessment monitoring
to determine the significance of, and appropriate responses to, key impacts. These
monitoring requirements are captured in the commitments made by the proponent
and recommendations of this Report.
The less predictable impacts such as the modification of habitats and cumulative
effects on significant species in the Harbour will need to be managed to an
acceptable level. The proponent should demonstrate that it can achieve this by fully
implementing its management program with effective monitoring and appropriate
adaptive management tools. These programs will need to be rigorous and based on
sound, scientific information, and form the basis for relevant regulatory approvals.
Given the high profile of this Project, it is essential that the community are kept
informed of ongoing monitoring programs and the implementation of required
management actions.
This Report identifies areas where, despite efforts to mitigate impact, residual
environmental detriment is anticipated, such as the loss of monsoon vine forest and
the cumulative effects of the Project on significant marine biota in Darwin Harbour.
The proponent will be expected to implement appropriate offsets to reduce this
residual detriment or improve protection for relevant environmental aspects
elsewhere.
Based on its review of the EIS and the proponents response to submissions from
relevant Northern Territory Government agencies, affected stakeholders and the
public, and an understanding of the economic benefits of the project, the
Environment and Heritage Division considers that the project can be managed within
the bounds of acceptable environmental impacts, provided that the environmental
commitments, safeguards and recommendations detailed in the EIS, this
Assessment Report and in the final management plans are implemented and
managed under the environmental management program for the project and are
subject to regular reporting and compliance auditing.

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65
95

6 References:
Department of the Chief Minister 2009, Territory 2030 Strategic Plan, Northern
Territory Government.
NT EPA (2010) Ecologically Sustainable Development in the Darwin Harbour Region:
Review of Governance Frameworks.
Southall, B.L., Bowles, A.E., Ellison, W.T., Finneran, J.J., Gentry, R.L., Greene Jr,
C.R., Kastak, D., Ketten, D.R., Miller, J.H., Nachtigall, P.E., Richardson, W.J.,
Thomas, J.A. and Tyack, P.L. 2007. Marine mammal noise exposure criteria: initial
scientific recommendations. Aquatic Mammals 33 (4): 411521.

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65
96

Appendix 1
A summarised list of issues raised from public review of the draft EIS corresponding with the individuals / organisations responsible for raising
those issues. The NRETAS submission on the draft EIS is not included in this summary but can be read in its entirety on the NRETAS website:
http://www.nt.gov.au/nreta/environment/assessment/register/inpex/index.html.

Public Submissions
Issue - Impacts

Raised By

Pollution and Waste Issues


Noise

AFANT

Shipping noise, particularly during the evenings.


Modelling of noise for SE winds is lacking (ie impact from operations and shipping on city).
Increase in ambient underwater noise from shipping direct impacts to fish and some whales
(soniferous fish reproduction, communication and foraging).
No consideration of cumulative impacts of underwater noise.
Water

Catherine Martel

Water pollution (in light of E coli and lack of dispersion).


Claims information used for establishing current water quality out of date.
Impact of blasting and dredging on water quality.
Impact associated with oil spills and discharge/ spill of drilling fluids.
Pollution from potentially contaminated sediments within the Harbour being disturbed.
The draft EIS does not provide specific values for water quality or other wastes that might trigger a
management response.
Pollutant loads of hydrotest water as well as other waste waters from construction, commissioning
and operation of the facility. Avoidance of discharge into the Harbour is requested or treatment of
the highest quality.
Cumulative impact on water quality from INPEX and other proposed and existing proposals.

97

Cheryl Billing Smith


Christine Cox
Cristina Reyes
Deckchair
DHAC
ECNT
Ed Valk
Heather Moorcroft and Robert Curry
Heather Ryan
Helen Lindstrom
HELP NT

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65

Issue - Impacts

Raised By

Concern on water quality indicators used by the draft EIS and quality of discharge.
The proponent must contribute financially to the development of a monitoring program that would,
among other things, track water quality, including sediment load.
Monitoring and adaptive management necessary to support this proposal, specifically in response to
sedimentation associated with spoil disposal.
Ongoing comprehensive, post and pre condition water quality monitoring programs need to be
conducted in conjunction with the development of a suite of suitable triggers and management
actions.
Air
Question proposed air emission limits.
Management of ozone depleting substances.
The appropriateness of the air quality NEPM to understand/ judge impacts to airshed is questioned.

Jodi Kirkby
Morris Pizzutto
Natacha Aguilar de Soto
Patrick Barrie
Roberta Dixon
Sue Mornane
Warren Clancy
World Wildlife Fund
DCC

Waste
Questions waste management/ capacity associated with site as well as increase in population.
Onshore waste disposal of both onshore and offshore wastes (cannot assume Shoal Bay Landfill).

Risk
AMSTECI

Risk - general
Accuracy of risk modelling (dependent upon input data) (including relevance to the NT due to its
climatic conditions).
Proximity to ConocoPhillips (reference to overseas restrictions on distance limits as well as
ConocoPhillips EIS and EMP).
Cumulative risk arising from both ConocoPhillips and INPEX operating in such close proximity.
Ensuring risk evaluation is continually reviewed.
Design standards and sourcing of expertise.
References DVD The Risks and Dangers of LNG Tim Riley and Hayden Riley.
Refers to website www.lngdanger.com.
Cites international examples of catastrophic failure within the industry.

98

Duncan Dean
ECNT
Greg Chapman
Heather Ryan
HELP NT Parts 1,2, 3 and 4
Pro-forma submission
Rose Kubatov
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65

Issue - Impacts

Raised By

Questions whether all potential scenarios of risk have been modelled or tested.
Judgment that the QRA falls short of the government guideline requirements. The 20 pages of the
INPEX QRA is in stark contrast to the 128 pages of the Hazard and Risk Assessment Report (HRAP)
which Bechtel Corporation and their consultants Quest Consultants Inc. prepared for Phillips
Petroleum Australia Pty Ltd as part of the March 2002 Public Environment Report for the 10 MTPA
Facility at Wickham Point.
Modelling of oil spill risk omitted from draft EIS.

The Mahonys

Risk to the population

Questions readiness of the community for catastrophic risk and INPEXs responsibility towards getting
the community ready/ protected/ evacuated.
Questions Darwins emergency and health capacity to respond to a catastrophic event.
Cost to Darwin being emergency ready.

Risk to the environment


From spills and vapour clouds.
Causes of Risk
Risk associated with natural phenomena (cyclone, sea surge, earthquakes) and engineering design
standards to minimise risk.
Terrorism to plant and to ships and how this is managed.
Risks associated with shipping in the Harbour.

99

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65

Issue - Impacts

Raised By

Greenhouse Gas Emissions


Amanda McLennan

Policy Position
Concern that INPEX is trying to avoid GHG reporting/ tax/ policy.
Cannot make claim that proposal will reduce overall global GHG emissions. INPEX cannot
demonstrate that this LNG product will in any way displace dirtier fuels. There are no Australian or
international mechanisms for leaving any coal in the ground. Australia (the producer) has not
committed to export any less coal, and Japan (the consumer) have not committed to shutting down
any coal fired power stations.
The fact that INPEX has conformed to the NT's EIS guidelines and has avoided any commitment to
action, or realistic appraisal of the projects carbon impacts is a concern. The draft EIS highlights the
NT Governments failure to make any progress towards an effective policy framework for addressing
carbon heavy development proposals such as this one.

Atmospheric Solutions
Brigid Oulsnam
Catherine Martel
Catherine Orme
Christine Cox
DCC
Deborah Hall & Andris Bergs
Debra Mills

Emissions created by the Operation

ECNT

The INPEX project will add another 7Mt per year to the Australian account more than a 1%
increase.
Questions how INPEX will reduce CO2 equivalent emissions.
How is plant going to be designed for energy efficiency.
Significantly increase NT contribution to global GHG emissions NT unable to meet targets and will
damage NT from tourism perspective.
The project represents a net carbon burden, a net climate detriment, and a real barrier to effective
action to manage climate change.

Ed Valk
Georgia Phillips
Greening Australia
Helena Bond
HELP NT
Jaemie Page
James Treloar
Justin Tutty
Keren Parnell
Lynne Higgs

100

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65

Issue - Impacts

Raised By
M. F. McAuliffe
Magdalena Szaszorowska Pawel Komisarski
Maria Papadopoulou
Mark Gregson
Michael Cauce
Morgana Robb
Patrick Barrie
Robert E. Rutkowski
Roberta Dixon
Robin Ellis
S. Sankar
Sean Corrigan
Suzanne Rosenberg
Tanya Rodden
Teresa Assem
Teresa Jaworska
Tida Nou
Tina Sykes
Tourist Industry
Wilderness Society WA
World Wildlife Australia

101

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65

Issue - Impacts

Raised By

Biodiversity Impacts
Terrestrial

Alana Corr

Limited survey work (restricted to Dry) and too much reliance on desktop studies.
Direct clearance of Monsoon Vine Forest and Mangroves (sensitive/ significant vegetation
communities identified in governments Land Clearing Guidelines).
Loss of habitat and movement corridors.
Loss of feeding areas (specifically for frugivorous birds).
Weed ingress.
Claim that trees in residential areas offset removal of vegetation not acceptable.
INPEX fails to acknowledge natural values of regionally-significant monsoon vine forest including
what has been described as one of the best patches of monsoon vine forest on the Harbour
foreshore.
There is a 100m corridor shown to the east of the LNG Plant on Blaydin Point. This corridor is for a
future road across East Arm and years away from construction, therefore the monsoon vine forest
should be retained, not cleared. Monsoon vine forest is a special eco type and should be retained
where possible.
Vegetation clearing and the sealing of surfaces on Blaydin Point may reduce groundwater recharge,
and in turn, lead to saltwater intrusion and impacts on groundwater-dependent ecosystems and built
infrastructure.
Marine

Amanda McLennan

Concern that information re dolphin numbers and movement in Harbour is incorrect.


Questions adequacy of the proposed management measures for minimising blasting impacts on
dolphins, turtles and dugongs (ie spotting).
Destruction of shoals and associated impacts on marine life.
Loss of seagrasses and impacts on dugongs.
Impacts on dolphins, turtles and dugongs and marine life from blasting and shipping not acceptable.
Cumulative impact of this development to habitat loss and impacts on marine life.
Pest species introduced in ballast water.
Shipping strike with marine mammals.
Impacts from decrease in water quality.
Impacts to migratory birds.

102

Andrew Raith
Brigid Oulsnam
Catherine Orme
Cheryl Billing Smith
Christine Cox
Clive Pearce
Cristina Reyes
DCC
Deborah Hall & Andris Bergs
DHAC
Dianne Rickard
Don Franklin
Duncan Carson
ECNT
Ed Valk
Francine Bartlett
Gerry Wood
Greening Australia
Heather Moorcroft and Robert Curry
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65

Issue - Impacts

Raised By

While mangrove communities are common in the Harbour, at a global level, mangroves are now one
of the most threatened tropical ecosystemsmore threatened than rainforests and coral reefs.
Oil spill risks and potential impacts on biota have been inadequately evaluated through modelling and
other processes.

Heather Ryan
Helen Lindstrom
Helena Bond
HELP NT
Ian Kitney
Jaemie Page
Jane Herrador
Jennie Renfree
Jodi Kirkby
John Roodenrys
Judy Flynn
Justin Tutty
Keren Parnell
Kitri Cardwell
Kree Eyre
Laura Smith
Louise Harrison
M. F. McAuliffe
Magdalena Szaszorowska
Maria Papadopoulou
Megan Lawrance
Michael Cauce

103

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65

Issue - Impacts

Raised By
Michael Webb
Mirjam Kaestli
Morgana Robb
Morris Pizzutto
Natacha Aguilar de Soto
Nicolas Mialaret
Patrick Barrie
Rick Murray
Robert E. Rutkowski
Roberta Dixon
Robin Ellis
Roy Beames
Sam Ryan
Sea Darwin
Sean Corrigan
Susan Lloyd
Teresa Assem
Teresa Jaworska
Tida Nou
Tiffany Theden
Top End Tourism
Tourist Industry

104

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65

Issue - Impacts

Raised By
Wendy Sykes
World Wildlife Fund

Impacts of Specific Activities


AFANT

Blasting
Potential impacts of blasting are not acceptable direct death to marine mammals, turtles and fish.
Lack of scientific studies to support this part of the operations (to understand and manage impacts
appropriately).
Proposed management measures ineffective for turtles and fish and limited for marine mammals.
Noise from blasting impacting upon marine mammals, turtles and fish foraging and
communication there are relevant studies that show impact.

105

AMSTECI
Andrew Raith
Brigid Oulsnam
Catherine Martel
Catherine Orme

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65

Issue - Impacts

Raised By

Dredging impacts

Cheryl Billing Smith

Noise from dredging impacting on fish and turtles as well as whales.


Lack of Dredging Policy for Darwin Harbour on which to examine the acceptability of the proposal.
Impact on SCUBA divers.
Concern about how this project sits with other potential dredging required in the Harbour.
Movement of sediment within the Harbour associated with spoil dumping.
Impacts of sedimentation on seagrasses (and dugongs).
Impacts of sedimentation on rock outcrops and corals and associated flora/ fauna.
Disturbance of existing, potentially contaminated sediment.
Impact of sedimentation on mangrove areas and their habitat value.
Impact of sedimentation on crabs.
Impacts of sedimentation on the Howard River the only known Barramundi nursery in the Darwin
Harbour.
Fate of dredge material at off-site disposal area in the event of a cyclone.

Christine Cox
Cristina Reyes
DCC
Deborah Hall & Andris Bergs
Debra Mills
Derek Archer
DHAC
Don Franklin
ECNT
Ed Valk
Francine Bartlett
Gerry Wood
Greening Australia
Heather Moorcroft and Robert Curry
Helena Bond
Ian Kitney
Jaemie Page
James Treloar
Jane Herrador
Jennie Renfree
Jodi Kirkby

106

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65

Issue - Impacts

Raised By
John Hart
John Roodenrys
Judy de Groot
Keren Parnell
Kitri Cardwell
Kree Eyre
Lindsay Mugglestone
Louise Harrison
Lynne Higgs
Magdalena Szaszorowska
Margie West
Maria Papadopoulou
Marnie Cooper
Megan Lawrance
Michael Cauce
Morgana Robb
Morris Pizzutto
Natacha Aguilar de Soto
Nicolas Mialaret
Patrick Barrie
Pro-forma Submission
Raphael Kunzli

107

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65

Issue - Impacts

Raised By
Rebecca Savage
Robert E. Rutkowski
Roberta Dixon
Roy Beames
S. Sankar
Sam Ryan
Sean Corrigan
Susan Lloyd
Tanya Rodden
Teresa Assem
Teresa Jaworska
The Mahony's
Tida Nou
Top End Tourism
Warren Clancy
Wendy Sykes
World Wildlife Fund

108

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65

Socio- Economic Impacts


Catherine Martel

Generic
Governments failure to negotiate gas towards its own power generation.
Poor state of some Indigenous communities evidence that local population does not receive economic
advantage associated with a resource development.
Community left with cost of unusable site when plant ceases to operate.
Impact on housing costs and availability.
Impact on cost of everyday household items (eg fuel).
Ability for local companies to compete to retain staff and/ or engage contracts with INPEX (including
tourism).
Fly in/ fly out.
Social impacts associated with temporary workforce.
The last election result demonstrated the value of the project to Darwin society.
No evidence that it will bring value to Darwins population.
The public should be informed of any land and capital costs and risks to be borne by Government in
support of the INPEX project. These may relate to land development at Middle Arm Peninsula, road
and transport corridor upgrades, and provision of enhanced emergency service response capabilities
for potential accidents.

DCC
ECNT
Heather Ryan
HELP NT Parts 1,2
Sea Darwin
The Mahony's
Tourist Industry

AFANT

Impacts on the Harbour


Impact to the tourism value of the Harbour and Darwin.
Darwin Harbour has one of the richest coastal environments anywhere in the Asia Pacific region, and
occurs within one of the worlds least impacted marine regions.
Change to the value of Darwin Harbour.
Access within the Harbour (impact of exclusion zones on recreational and tourist operators).
Increase in boating traffic and associated risk.
Lack of strategic vision for Darwin Harbour.
Any development in or near Darwin Harbour must be carried out to ensure no detrimental impacts on
Darwins lifestyle or on recreational fishing.
Access must be maintained in the Harbour (East Arm) and the environmental services in the area

109

Angela Roodhouse
Catherine Martel
Cheryl Billing Smith
DCC
Deborah Hall & Andris Bergs
Derek McCarthy
Don Franklin

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65

must be preserved to ensure fish, marine life and other wildlife continue to thrive there.
The Project will change the nature of Darwin Harbour currently a unique environment of international
conservation significance (as identified by NTG).

ECNT
Ed Valk
Gerry Wood

Societal Impacts

Greening Australia

Much of the employment generated by this project will be for workers from elsewhere, while local
people will be confronted with a range of negative social and local economic impacts, such as
increased housing stress, constriction of the labour market and trade sectors (as experienced during
the Wickham Pt construction) and dramatically altered demographics.
Recognise and acknowledge the potential economic contribution that the Project can make to
Australia, the Northern Territory and Darwin but, at the end of the day, it is not possible to manage a
project of this magnitude without any impacts and it will be the people of Darwin who will be most
affected by the development. INPEX and the Northern Territory Government have responsibility to
ensure that, wherever possible, there are local benefits and these continue for the life of the project.
The workers accommodation at Howard Springs will have an impact on the surrounding residential
and retail area. Some of these affects are mentioned in the Socio-Economic Impacts however a more
detailed study needs to be done. (eg the effect on the local roads due to the increase in traffic
travelling to and from the accommodation village? Will there be sufficient water storage in the
Whitewood Road water tank to supply the accommodation village without effecting local supplies and
pressure?
Proximity to Palmerston.
Location of the workers residence.
Visual pollution.
Impacts to Roads

Heather Moorcroft and Robert Curry

There needs to be clarification of the routes that will be used for the transport of equipment and
materials and accordingly the effect this may have on transport routes. The construction of the
workers accommodation village will also have an effect on local roads.
Increase of traffic (including heavy vehicles) and associated risk.

110

Helena Bond
HELP NT
Jennie Renfree
Jodi Kirkby
Judy Flynn
Justin Tutty
Louise Harrison
Robert E. Rutkowski
Roberta Dixon
Sea Darwin
Sue Mornane
Susan Lloyd
The Mahony's
Tourist Industry

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65

Impacts on Tourism
Concerns

Sea Darwin

NT tourism dependent upon experiential travellers therefore need to protect natural and cultural
assets.
Impact on accommodation and short-term housing.
Tourism provides economic opportunity to remote communities, and is an industry that contributes
towards preservation and enhancement of landscapes this benefit is threatened by the INPEX
proposal. The proposal will impact NT Clean Green Image.
This project will generate many opportunities for Tourism Development but will also create some
pressures on the Tourism Industry particularly all industry that interacts with Darwin Harbour.
The draft EIS has limited reference to Tourism collectively, that operates within the Darwin Harbour.
There is limited reference to the value of Eco Tourism yet there is considerable identification of the
significant plant and wildlife with in Darwin Harbour.
Scenic harbour cruises and general leisure Tourism appears to be not identified or addressed in the
draft EIS.
Many operators would like the plant to be invisible and located in an area that required less
construction activity on Darwin Harbour sea bed.
INPEX will compete for resources and infrastructure.
Does not recognise that tourism is more than fishing.

111

Susan Lloyd
Tourist Industry (Rick Murray)
Tourism Top End

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65

Issues Information presented in the draft EIS

Raised By

Generic

Pro-forma submission

Inaccuracy of Maps in the draft EIS.


Does not cite or recognise eco-tourism operations on Harbour.
Tourism is only referenced as fishing.
Relevance and age of information/ scientific studies relied upon.
Lack of modelling to understand full impacts.
Lack of peer review on scientific studies.
The draft EIS is deficient in excluding a presentation and assessment of some important aspects of
the Project, including:
o The proposed accommodation village at Howard Springs;
o Quarries for the supply of fill, rock and aggregate;
o A rock load-out facility and stockpile area;
o A maritime supply base;
o A tug harbour;
o Waste disposal resources; and
o Utility corridors.
Information provided not sufficient to determine impact or inform management/ monitoring.
The draft EIS lacks description of the protocols and methodology on how ongoing risk identification
and management will be done.
The description of impacts and risks would have been more complete had socio-economics and the
conservation significance of species been considered in terms of Aboriginal cultural tradition and
patterns of natural resource use.
EMPs should be included in the draft EIS and available for public scrutiny.
Information regarding acid sulfate soils should have been included in draft EIS, as well as proposed
management plan.
Studies on the impact to hydrodynamics are only local to the East Arm area. Studies are needed on
the exchange rates of water from East Arm and the Elizabeth River into the main body of the
Harbour.
There has been no quantitative analysis of overall boat traffic in the vicinity of, or upstream of, the
main nearshore project area.
The information provided in the draft EIS to examine alternatives is minimal and unacceptable.

112

Sophie Chapman
HELP NT
Heather Ryan
Terry Lustig
Christine Cox
Tourist Industry (Rick Murray)
Mirjam Kaestli
Cristina Reyes
Morris Pizzutto
Sea Darwin
Ed Valk
Roberta Dixon
Helen Lindstrom
Kris Garrein
Glen Osboldstone
Helena Bond
Nicolas Mialaret
Teja Lipold & David Grace
Cheryl Billing Smith
Catherine Martel

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65

Issues Information presented in the draft EIS


Storm surge levels appear to be based on the Northern Territory Governments 2003 edition of the
map for the Municipality of Darwin Darwin Storm Surge Zones which does not take into account
current sea level rise estimates and predictions / findings in order to arrive at a considered
assessment of risk.

Raised By
Tida Nou
Don Franklin
Jaemie Page
Mick Guinea

Noise

World Wildlife Fund

In assessing potential underwater noise impacts on marine species the draft EIS draws only loosely
on the considerable body of literature available, omits key recent references, and makes little attempt
to analyse the broad thrust of the research.
The draft EIS provides insufficient consideration of the impacts of blasting on Darwin Harbour marine
wildlife, no underwater noise modelling has been done, proposed mitigation measures are
inadequate and the proposed acoustic monitoring techniques have never been tested.

Brigid Oulsnam
Atmospheric Solutions
NLC
Greening Australia
John Roodenrys

Biodiversity

Justin Tutty

Land-based flora and fauna surveys not representative.


Limited study on marine organisms no pre-disturbance, baseline studies required.
A lack of detail in the Management of Marine Megafauna and in the Provisional Dredging and Dredge
Spoil Disposal Management Plan.
The section on important habitats for marine species and the sections on the impacts of
sedimentation and other stressors on marine species are significantly deficient in terms of the
references cited, lack of up-to-date information and lack of recognition of existing knowledge on
critical habitats for many key species. There are also unsubstantiated claims of possible benefits.
The draft EIS lacks information to support claim that Darwin Harbour is not a significant breeding or
feeding habitat for dolphins and other marine species accordingly it has incorrectly identified level of
risk to these species by its operations.
Whole of Darwin Harbour habitat map required.
Lack of information on susceptibility of sea snakes to oil spills.
More detailed information on the possible impacts of dredge spoil on coral, blue holes, fish and other
marine life in the Gunn Point and Vernon Islands area should be included in the Supplementary EIS.
To imply that a particular species or habitat is well represented in the Harbour and therefore some
loss would be not be considered a problem, is questionable. Particularly in view of the lack of data for

113

Louise Harrison
AFANT
ECNT
DCC

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65

Issues Information presented in the draft EIS

Raised By

Darwin Harbour, along with the potential for more new harbour developments adopting the same
views.
Greenhouse
The draft EIS does not adequately describe detailed sequestration and mitigation pathways, and the
contribution that these pathways would make to the overall CO2 footprint of the Project.
The additional volumes of greenhouse gases expected to emanate from the accommodation village
should be quantified and reported in the EIS.
INPEX fails to acknowledge predicted increase in intensity and frequency of extreme weather,
including cyclone events. (Scientific projections identified by the CSIRO report 'Climate Change
Under Enhanced Greenhouse Conditions In Northern Australia' as referenced in NT Government's
'Strategy for Greenhouse Action'). It remains unclear how INPEX's commitments to engineer for
anticipated cyclone activities will factor in the projected increased intensity and frequency of these
extreme weather events over the project lifetime.
Why have emissions of methane (CH4) and nitrous oxide (N2O) and other greenhouse gases been
excluded from the greenhouse assessment of the draft EIS? Methane emissions in particular will be
significant, and all significant greenhouse emissions should be detailed in the EIS.
Why have venting and fugitive emissions sources been excluded from the greenhouse assessment of
the draft EIS? All sources should be detailed in the EIS.
In regards to the benchmarking in relation to NT and Australian emissions, Table 93 should state
explicitly that the project will increase Northern Territory (NT) emissions by 40% (on average) or 53%
(peak) over the project life.
The greenhouse emissions benchmarking of Ichthys against similar projects should be carried out on
the established basis of t CO2e / t LNG. This measure shows that Ichthys will be among the most
carbon intensive LNG projects in the planet, and does not represent best practice.
The Draft Statement avoids mentioning the true carbon burden of downstream burning of the LNG
product, and INPEX representatives were unable to provide this number to community consultations
held upon release of the Draft.
INPEX offers no rationale for why they are comparing LNG to coal instead of solar.
Dredging

114

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65

Issues Information presented in the draft EIS

Raised By

Studies and modelling of dredging impacts lacking and based upon assumptions.
The draft EIS contains an inadequate and incomplete assessment of the direct and indirect impacts
of dredging and dredge spoil disposal on coastal dolphins, marine turtles and dugong.
The incidence of cyclones in the Darwin area is considered in the dredge spoil dispersal modelling,
however only a category 2 is mentioned. It is unclear the impact of re-mobilisation of sediments with
more severe cyclones.
The draft EIS presents only a dredging concept which could be vastly different to the actual dredging
operations however the public dont get a chance to comment on the actual dredge operations.
It is unsatisfactory to rely on limited geotechnical information and present instead assumptions when
describing dredge operations and potential impact.
It is difficult to find specific reference to material amounts to be transported to the offshore disposal
site in both the draft EIS and appendices.
The assumption that particles > 75 m are coarse is challenged based upon international
standards. To make the assumption that only fines <75m will be mobile in solution and therefore
responsible for plume and sediment deposition is questioned, particularly as the draft EIS states
something different when discussing offshore disposal.
Questions correct understanding of tidal movements within the whole Harbour.
Blasting
The draft EIS contains inadequate and incomplete assessment of the direct and indirect impacts of
blasting Walker Shoal for the shipping channel and inadequate exploration of alternative channel and
jetty options.
Waste Water and pollutants
Information regarding specific water and waste pollutants fate, disposal methods and impact has
not been provided
Marine discharges do not appear to have been assessed against the ANZECC trigger limits for
marine water quality.
The draft EIS lacks substantive ecological research or measurement of ecotoxicology of some of the
chemicals to be use. There is a reliance on industry-based standards and an inherent assumption

115

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65

Issues Information presented in the draft EIS

Raised By

that the ocean provides infinite dilution for toxicants.


MSDS documents for the chemicals to be used in bulk missing from the draft EIS and Appendices.
The addition of these documents would be useful to assist in understanding specific risks associated
with these chemicals to people accessing the nearby environment, if not the impacts on marine
organisms.
The waste water discharges during operations are said to be continuous but quantities of the
proposed discharges have not been specified or what, if any, environmental risks they may pose.
Engineering and Design
The proponent must demonstrate that engineering standards are set to projected exacerbation of
extreme weather events, including cyclones.
There is no discussion of the impacts that increases in sea level, wave height and wave action may
have on the onshore project infrastructure. Nor is there mention of any plan or an outline of actions
that would be taken to avoid accidents at the onshore facilities should Darwin be threatened by these
types of events.

Issue Approach taken by Proponent

Raised By

Consultation

AFANT

LDC acknowledges principles of support and consultation to Larrakia and other traditional owners.
LDC satisfied concerns have been addressed respecting social and cultural significance of land to be
impacted by the development.
LDC satisfied with management of archaeological sites.

116

Larrakia Development Corporation

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65

Issue - Proposal

Raised By

Support

AFANT Brendan J Anderson

Australia needs development.


LDC has been working with INPEX to ensure benefit from the construction and infrastructure
development for the Larrakia people.
The LDC is interested in the community and economic benefits that could arise from the Ichthys Gas
Field Development.
LDC commends INPEX desire to maximise the opportunities for participation in the Ichthys Gas Field
Project by the Larrakia and all Territorians. Wants to ensure opportunities are real and not tokenistic.
LDC commends INPEX for supporting its initiative to construct and operate a Trade Training Centre.
The Ichthys Project will bring very significant economic and development benefits to Darwin, the
Northern Territory and Australia and AFANT is not opposed to the location of its main onshore
processing, product shipping and offshore support activities in Darwin Harbour.

Larrakia Development Corporation

Top End Tourism

Benefits derived from the project


Proposed management measures for INPEX to adopt, including a tourism policy.
The project will bring opportunities for tourism Construction and the resulting economic activity from
the project will help build the business and corporate travel market and consequently support
increased airline services by full service airlines.
The project may stimulate investment in commercial tourism accommodation stocks and boost the
economic development of the Top End that will generate confident investment in new Tourism
Infrastructure.
Additional labour force required during construction could deliver positively to the Tourism Sector
from temporary workforce and its visiting friends and relatives sector with a focus on regional
dispersal.

Alternatives

Many submissions objected to the proposal based upon the options presented.
Other sites not considered.
Submissions propose alternate sites in Harbour.
Submissions propose site sharing with ConocoPhillips.

117

HELP NT
Heather Ryan
Pro-forma submissions
Ichthys Gas Field Development Project, Blaydin Point
Assessment Report 65

Issue - Proposal

Raised By

Submissions argue WA a better option.


Alternate pipeline routes (to minimize blasting) should be examined.
Alternate options for wharf/ jetty development (to minimize dredging) should be examined.
Concern that option presented which addresses AFANTs issues comes at the cost of the
environment.
Land based disposal of dredge spoil should be considered.

Duncan Carson
Tina Sykes
Mark Gregson
Georgia Phillips
Mirjam Kaestli
M. F. McAuliffe
Morris Pizzutto
Rachel Bury
Glen Osboldstone
Sean Corrigan
Jane Herrador
Francine Bartlett
Maria Papadopoulou
Debra Mills
Lynne Higgs
Tanya Rodden
Morgana Robb
Marnie Cooper
Patrick Barrie
Meredith Tyburczy
Kitri Cardwell
Sam Ryan

118

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65

Issue - Proposal

Raised By
Lindsay Mugglestone
Rebecca Savage
Magdalena Szaszorowska Pawel Komisarski
Teresa Jaworska
Teresa Assem
Grahame Hubbard
Julie Weston
James Treloar
Helena Bond
Megan Lawrance
Robert E. Rutkowski
Ken Hooke
Andrew Raith
Raphael Kunzli
Judy de Groot
Robin Ellis
Sue Pratt
Cheryl Billing Smith
Catherine Martel
Tida Nou
Catherine Orme
Jaemie Page

119

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65

Issue - Proposal

Raised By
Brigid Oulsnam
Michael Cauce
Jennie Renfree
Diane M. Kastel and family
Megan Clementi
Keren Parnell
John Roodenrys
Justin Tutty
Louise Harrison
Margie West
AMSTECI
DHAC
ECNT

Pro-forma submissions

Sustainability Issues

Project does not represent sustainable development.


Project does not represent industry best practice.
Wastewater reuse; rainwater harvesting.
Lack of consideration of cumulative impacts.
Seeking for INPEX to demonstrate good corporate citizen.
The challenge for Darwin is to learn how to engineer a new economics that is based on sustainability,
not unconstrained growth.
Seek INPEX support for broader strategic study.
Lack of recent/ relevant scientific analysis/ data to support elements of the proposal.
Compromises the success of other economically valuable sectors within the NT (ie tourism).

120

Dianne Rickard
Duncan Carson
Tourist Industry
Cristina Reyes
Sea Darwin
Cynthia Miall
Liz Thorton

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65

Issue - Proposal

Raised By

The onus of proof should lay with the proponent that the project will not impact, not on the population
to prove environmental worth.
Not in keeping with the principles of ESD:
o Biodiversity conservation and ecological protection
o Inter-generational equity
o Improved valuation and pricing
o Precautionary principle

Wendy Sykes
Clive Pearce
Glen Osboldstone
Jane Herrador
Francine Bartlett
Greg Chapman
Angela Snow
Brian Cotgrove
Helena Bond
Kylie Ellis
Catherine Martel
Atmospheric Solutions
NLC
Greening Australia
John Roodenrys
Justin Tutty
Louise Harrison
DHAC
ECNT
DCC

121

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65

Site rehabilitation
Post-operations land use?
Lack of rehabilitation planning and funding.
Greening Australia

Resource Use
No information on water usage or sourcing.

DCC

DCC

Provision of supporting Infrastructure


Impacts to existing (roads, sewage).
Costs of new.
Infrastructure required to meet water requirements.

Issue Operations and Regulation of the Proposal

Raised By

Offsets
Pro-Forma Submissions

Greenhouse
GHG emissions offset program - locally based.
Creation of a carbon Fund.
Substantial offshore greenhouse emissions are forecast for the facility arising from the extraordinarily
long pipeline and corresponding compression requirements (stated in the draft EIS as 100 MW).
These should be offset to bring the greenhouse emissions intensity of the facility in line with standard
/ current facilities.
INPEX should commit to not waiting for governments to set an 'acceptable' level of pollution, and
should instead aim to offset all their carbon emissions.
Why is geosequestration (as per Gorgon) not being considered, nor an appropriate offset strategy (as
required for Pluto) developed should geosequestration be proven infeasible?

122

Duncan Carson
Tina Sykes
Mark Gregson
Georgia Phillips
Tourist Industry
Sea Darwin
Ed Valk

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65

Roberta Dixon

Biodiversity
Measures to compensate for the destruction of habitats.
Creation of new national parks and/ or conservation zones suggestions of Ludmilla Bay, Bynoe
Harbour to be locally based.
Suggests that IPEX should invest into research of Dolphins.

Sean Corrigan
Jane Herrador
Maria Papadopoulou
Debra Mills
Lynne Higgs
Tanya Rodden
Morgana Robb
Patrick Barrie
Sam Ryan
Lindsay Mugglestone
Rebecca Savage
Magdalena Szaszorowska Pawel Komisarski
Teresa Jaworska
Teresa Assem
Grahame Hubbard
Julie Weston
James Treloar
Helena Bond
Robert E. Rutkowski
Ken Hooke
Kree Eyre
Raphael Kunzli

123

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65

Judy de Groot
S. Sankar
Amanda McLennan
Suzanne Rosenberg
Sue Pratt
Catherine Martel
Heather Moorcroft and Robert Curry
Tida Nou
Wilderness Society WA
Catherine Orme
Jaemie Page
Brigid Oulsnam
Michael Cauce
Atmospheric Solutions
Diane M. Kastel and family
Megan Clementi
Keren Parnell
Greening Australia
John Roodenrys
Louise Harrison
ECNT

124

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65

Regulatory responsibility and management (and cost)

Shipping movements and ballast;


Pollution control;
Port usage;
Risk identification and ongoing management and regulation;
Road maintenance and usage.
INPEX should work with Govt and invest in an appropriate regulatory system.
INPEX should sign up to the proposed Integrated Monitoring Program.
A technical project of this size and complexity should have a fully and independently auditable HSE
Management system that ensures compliance and offers maximum environmental protection.
Regimes for assessment, compliance monitoring and enforcement of environmental requirements
and objectives remain sub-standard in the NT.
Policy regime within the NT is lacking/ non-existent dredging, Greenhouse.
Planning Scheme ineffective zoning areas conservation does not guarantee their protection.
The lack of adequate regulatory environment in the NT emphasises the importance of INPEX
conducting a thorough risk assessment for all aspects of its Project, and on the basis of this
assessment, putting in place a comprehensive, detailed Environmental Management Program.

Heather Ryan
Sea Darwin
Catherine Martel
NLC
Justin Tutty
AFANT
DHAC
ECNT
DCC

NT Government Submission
Issue

Raised By

Options/ alternatives

DCM coordinated response

Detailed reasons required for the selection/ rejection of jetty options.


Analysis required to support blasting options.
DCM coordinated response

Studies required
Appropriate baseline surveys (including habitat mapping) required for areas potentially impacted by the Project
required as part of the integrated monitoring program.
125

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65

Issue

Raised By

Monitoring

DCM coordinated response

Indication of support for the integrated marine monitoring program noted in draft EIS.
Monitoring to extend to areas adjacent to dredge disposal areas.
Permit issued under s16 of the Fisheries Act for dredge spoil site and removal of Walker Shoal include monthly
monitoring on aquatic life, including fish kills (this information then informs subsequent blasting and dredging activity.
DCM coordinated response

Engagement
Determined that project will have a significant impact on Darwin and the region throughout life of project; accordingly
INPEX to maintain communication with community, business and government to ensure measures proposed to ensure
socio-economic benefits of the project are realised.
Specific Comment

Traffic advice;
Clarification of DHF role;
Provision of supporting information regarding waste water treatment and DHF requirements;
Clarification sought on proposed disposal method for medical waste;
Information sought on relationship of the proposal and the NT Planning Scheme;
Information provided regarding biting insect hazards;
Clarification of requirement/ role of the Fisheries Act as well as the Radiation Protection Act;
Statement that safety is a significant issue and accordingly risk identification and hazard management will be
undertaken as part of the licensing of the facility (as opposed to during the EIA process?).

126

Ichthys Gas Field Development Project, Blaydin Point


Assessment Report 65

You might also like