G.R. No. L-30056 August 30, 1988 MARCELO AGCAOILI, Plaintiff-Appellee GOVERNMENT SERVICE INSURANCE SYSTEM, Defendant-Appellant. Narvasa, J.
G.R. No. L-30056 August 30, 1988 MARCELO AGCAOILI, Plaintiff-Appellee GOVERNMENT SERVICE INSURANCE SYSTEM, Defendant-Appellant. Narvasa, J.
G.R. No. L-30056 August 30, 1988 MARCELO AGCAOILI, Plaintiff-Appellee GOVERNMENT SERVICE INSURANCE SYSTEM, Defendant-Appellant. Narvasa, J.
a deprivation of the GSIS at the same time of the reasonable rental value of the
property. 11
Ruling:
Yes. There was a perfected contract of sale. However, Agcaoilis act of letting his
homeless friend to stay as a watchman of the property without GSIS consent did
not operate as repudiation by Agcoali of the award.
There was then a perfected contract of sale between the parties; there had been a
meeting of the minds upon the purchase by Agcaoili of a determinate house and lot
in the GSIS Housing Project at Nangka Marikina, Rizal at a definite price payable in
amortizations at P31.56 per month, and from that moment the parties acquired the
right to reciprocally demand performance. 13 It was, to be sure, the duty of the GSIS,
as seller, to deliver the thing sold in a condition suitable for its enjoyment by the
buyer for the purpose contemplated , 14 in other words, to deliver the house subject
of the contract in a reasonably livable state. This it failed to do.
. Since GSIS did not fulfill that obligation, and was not willing to put the house in
habitable state, it cannot invoke Agcaoili's suspension of payment of amortizations
as cause to cancel the contract between them. It is axiomatic that "(i)n reciprocal
obligations, neither party incurs in delay if the other does not comply or is not ready
to comply in a proper manner with what is incumbent upon him." 15
Nor may the GSIS succeed in justifying its cancellation of the award to Agcaoili by
the claim that the latter had not complied with the condition of occupying the house
within three (3) days. The record shows that Agcaoili did try to fulfill the condition;
he did try to occupy the house but found it to be so uninhabitable that he had to
leave it the following day. He did however leave a friend in the structure, who being
homeless and hence willing to accept shelter even of the most rudimentary sort,
agreed to stay therein and look after it. Thus the argument that Agcaoili breached
the agreement by failing to occupy the house, and by allowing another person to
stay in it without the consent of the GSIS, must be rejected as devoid of merit.
2.
Yes.
assuming it to be feasible to still finish the construction of the house at this time, to
compel the GSIS to do so so that Agcaoili's prestation to pay the price might in turn
be demanded, without modifying the price therefor, would not be quite fair. The cost
to the GSIS of completion of construction at present prices would make the
stipulated price disproportionate, unrealistic.
The situation calls for the exercise by this Court of its equity jurisdiction, to the end
that it may render complete justice to both parties.
In this case, the Court can not require specific performance of the contract in
question according to its literal terms, as this would result in inequity. The prevailing
rule is that in decreeing specific performance equity requires 17
... not only that the contract be just and equitable in its provisions, but that the
consequences of specific performance likewise be equitable and just. The general
rule is that this equitable relief will not be granted if, under the circumstances of the
case, the result of the specific enforcement of the contract would be harsh,
inequitable, oppressive, or result in an unconscionable advantage to the plaintiff . .
In the exercise of its equity jurisdiction, the Court may adjust the rights of parties in
accordance with the circumstances obtaining at the time of rendition of judgment,
when these are significantly different from those existing at the time of generation
of those rights.
The completion of the unfinished house so that it may be put into habitable
condition, as one form of relief to the plaintiff Agcaoili, no longer appears to be a
feasible option in view of the not inconsiderable time that has already elapsed. That
would require an adjustment of the price of the subject of the sale to conform to
present prices of construction materials and labor. It is more in keeping with the
realities of the situation, and with equitable norms, to simply require payment for
the land on which the house stands, and for the house itself, in its unfinished state,
as of the time of the contract.
Hence, GSIS instead of completing the house is ordered that the contract between
the parties relative to the property be modified by adding to the cost of the land, as
of the time of perfection of the contract, the cost of the house in its unfinished state
also as of the time of perfection of the contract, and correspondingly adjusting the
amortizations to be paid by Agcaoili, after of the value of said house on the basis of
the agreement of the parties, or if this is not possible by such commissioner or
commissioners