Integrated Management System Handbook
Integrated Management System Handbook
Integrated Management System Handbook
Environmental Management
Corporate Social Responsibility
CONTENT:
GENERAL .................................................................................................................... 4
1.1
1.2
SCOPE ..................................................................................................................... 4
1.3
Certifications ........................................................................................................... 5
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
3.1
3.2
3.3
REFERENCES ............................................................................................................ 26
VALIDATION ..................................................................................................................... 28
7
RELEASE ........................................................................................................................... 28
Author
Owner
Wally Walia
Bernhard Wiehler - VP QM
File Name: Integrated Management System Handbook.docx
Version
Date
Status
Page/Pages
4.0
29.10.2014
>Approved<
3 / 28
GENERAL
1.1
Purpose
Goal / Mission
statement
1.2
SCOPE
Details on validity
Limitation
Author
Owner
Wally Walia
Bernhard Wiehler - VP QM
File Name: Integrated Management System Handbook.docx
Version
Date
Status
Page/Pages
4.0
29.10.2014
>Approved<
4 / 28
1.3
Certifications
Certificates
Quality System
Overview
Measurements/
Factual approach to decision making
2.7
2.6
Mutual beneficial
supplier relationships
a mutually beneficial relationship
enhances the ability to create value
(win-win).
2.5
Involvement of People/
all parties (stakeholders)
Management Responsibility/
Senior Executive Leadership
2.8
Continuous
Improvement
should be
everybodys aim
Communication rules
Process Management
Process approach (SIPOC)
Process Landscape
- core processes
- enabler/support processes
- ownerships
Owner
Wally Walia
Bernhard Wiehler - VP QM
File Name: Integrated Management System Handbook.docx
Planned Development/Training
Employee Performance/Recognition
Author
a permanent objective
of the organization
2.4
2.2
Version
Date
Status
Page/Pages
4.0
29.10.2014
>Approved<
5 / 28
2.1
CUSTOMER FOCUS
Customer
satisfaction
ADVA
Optical
Networking
continually strives to improve its
responsiveness to its customers,
to
anticipate
customer
requirements, and to provide
world class products and services.
To succeed these challenges,
customer
inquiries
for
our
products
and
services
are
scrutinized very carefully to make
sure that customer requirements
and expectation are fully and
correctly understood.
Customer responses are managed through the Customer Satisfaction
(CSAT) process, incl. annual surveys and the Continual Improvement
processes. Data obtained are analyzed to identify product and process
improvement initiatives. Upon completion, customers are informed of the
progress made as a result of their feedback.
2.2
MANAGEMENT RESPONSIBILITY
Top down
responsibility
Author
Owner
Wally Walia
Bernhard Wiehler - VP QM
File Name: Integrated Management System Handbook.docx
Version
Date
Status
Page/Pages
4.0
29.10.2014
>Approved<
6 / 28
Management
System
Responsibility
Management
Business Reviews
Author
Owner
Wally Walia
Bernhard Wiehler - VP QM
File Name: Integrated Management System Handbook.docx
process
assessments,
continual
Version
Date
Status
Page/Pages
4.0
29.10.2014
>Approved<
7 / 28
to
for
Quality
Quality
Planning
projects.
R&D
Author
Owner
Wally Walia
Bernhard Wiehler - VP QM
File Name: Integrated Management System Handbook.docx
Version
Date
Status
Page/Pages
4.0
29.10.2014
>Approved<
8 / 28
Figure 1:
Author
Owner
Wally Walia
Bernhard Wiehler - VP QM
File Name: Integrated Management System Handbook.docx
Version
Date
Status
Page/Pages
4.0
29.10.2014
>Approved<
9 / 28
2.3
Process
Management
Process
Landscape
Document
Management
CONTROLLED DOCUMENTS
Author
Owner
Wally Walia
Bernhard Wiehler - VP QM
File Name: Integrated Management System Handbook.docx
Version
Date
Status
Page/Pages
4.0
29.10.2014
>Approved<
10 / 28
2.4
PROCESS MANAGEMENT
Process
Structure
Process
performance
Core Processes
Sub-processes
Support Processes
Supporting Documents
(i.e. policies, guidelines, instructions, forms, etc.)
Author
Other self-assessments
Owner
Wally Walia
Bernhard Wiehler - VP QM
File Name: Integrated Management System Handbook.docx
Version
Date
Status
Page/Pages
4.0
29.10.2014
>Approved<
11 / 28
2.5
RESOURCE MANAGEMENT
Allocation
Human Resources
2.6
SLM processes
Author
Owner
Wally Walia
Bernhard Wiehler - VP QM
File Name: Integrated Management System Handbook.docx
Version
Date
Status
Page/Pages
4.0
29.10.2014
>Approved<
12 / 28
1. Commodity Management
Process Strategic SLM
2. Supplier Life Cycle Processes
(SLCP) Operational SLM
(E2E Supplier / Manufacturer
Lifecycle)
3. Request for Quote (RFQ)
processes Operational SLM
(Supplier prices / Contract Manufacturer prices / cost updates)
The Commodity Management Process defines the commodity strategy
and the supplier strategy on a yearly basic to have a strategic direction
defined for the operational SLM processes.
The Supplier Life Cycle Processes (SLCP) consider 5 sub processes
related to the overall life cycle phases of a Supplier and/or Manufacturer:
The Request for Quote (RFQ) processes describes the methods and
procedures for the:
2.7
General
requirements
Author
Customer satisfaction
Employee satisfaction
Product characteristics
Process performance
Supplier performance
Financial results
Owner
Wally Walia
Bernhard Wiehler - VP QM
File Name: Integrated Management System Handbook.docx
Version
Date
Status
Page/Pages
4.0
29.10.2014
>Approved<
13 / 28
Internal audits
Author
Wally Walia
Bernhard Wiehler - VP QM
File Name: Integrated Management System Handbook.docx
Version
Date
Status
Page/Pages
4.0
29.10.2014
>Approved<
14 / 28
Internal complaints
Top priority has always been to avoid any non-conformities. The identified
non-conforming material or product is clearly marked, blocked, contained
and separated from conform items to prevent further product processing
and/or shipments to the customer.
To ensure this, purchase, production and/or shipments of any nonconforming material is stopped accordingly across the whole supply chain.
Fast and exhaustive investigation of non-conformity supports the
identification of the real root cause and derivation of adequate corrective
and preventive action to rectify fault and avoid recurrence.
In our processes rules, actions and responsibilities are defined to decide
based on risk assessment whether clearly identified and recorded non-
Author
Owner
Wally Walia
Bernhard Wiehler - VP QM
File Name: Integrated Management System Handbook.docx
Version
Date
Status
Page/Pages
4.0
29.10.2014
>Approved<
15 / 28
2.8
CONTINUOUS IMPROVEMENT
General
The ADVA
Efficiency Engine
(AEE)
Author
Owner
Wally Walia
Bernhard Wiehler - VP QM
File Name: Integrated Management System Handbook.docx
Version
Date
Status
Page/Pages
4.0
29.10.2014
>Approved<
16 / 28
CORE PROCESSES
3.1
Product
Development
The Product Life Cycle Process or PLCP refers to the process of bringing a
new product from concept through all activities required until it is fully
deployed in its markets as a mature product and finally throughout its
end of life. The lifecycle methodology is applicable to all projects. It
explains the lifecycle and how it must
be practically applied for any project/
product being introduced, managed or
withdrawn.
Product Life Cycle Process or PLCP is a
team
oriented
management
and
delivery process, which provides a
guideline to successfully bringing a
new product from concept through all
activities required until it is fully
deployed in its markets as a mature product and finally until end of life. It
establishes the concept of Key Dates and Phases.
Key Dates are gateways between the phases. PLCP establishes
requirements for moving from one phase to the next phase. A team of
people performs this activity.
Design and development inputs involve functional and performance
requirements, applicable statutory and regulatory requirements stated
form customers or suppliers or information derived from previous similar
designs. Outputs from the design and development phase are verified
against the requirements/inputs and are approved prior to release.
Goals of the Product Life Cycle Process are:
Author
Owner
Wally Walia
Bernhard Wiehler - VP QM
File Name: Integrated Management System Handbook.docx
Version
Date
Status
Page/Pages
4.0
29.10.2014
>Approved<
17 / 28
3.2
Sales
Customer Service
Author
Owner
Wally Walia
Bernhard Wiehler - VP QM
File Name: Integrated Management System Handbook.docx
Version
Date
Status
Page/Pages
4.0
29.10.2014
>Approved<
18 / 28
3.3
Supply Chain
Management
The Product Order and Fulfillment Process (POFP) describes the full
process that is planning, manufacturing, and delivery. POFP is triggered
by demand, in the form of a Customer Purchase Order and shuts off at
his/her doorstep. The Customer PO and our invoice on delivery are
bookends to this process.
POFP follows the traditional Plan, Source, Make, Deliver (SCOR/ Supply
Chain Operations Reference) model. Planning consists of Make-To-Order
(MTO) and Make-To-Stock (MTS) production planning and delivery
scheduling. Our ERP system, SAP, is the environment where the process
is launched and managed.
Author
Owner
Wally Walia
Bernhard Wiehler - VP QM
File Name: Integrated Management System Handbook.docx
Version
Date
Status
Page/Pages
4.0
29.10.2014
>Approved<
19 / 28
EMS
Representative:
EMS Organization
EMS Program
Author
Wally Walia
Bernhard Wiehler - VP QM
File Name: Integrated Management System Handbook.docx
Version
Date
Status
Page/Pages
4.0
29.10.2014
>Approved<
20 / 28
Environmental
Aspects
and
Impacts process to identify and
prioritize the significant environmental aspects associated with
operations.
Author
Owner
Wally Walia
Bernhard Wiehler - VP QM
File Name: Integrated Management System Handbook.docx
Version
Date
Status
Page/Pages
4.0
29.10.2014
>Approved<
21 / 28
CSR &
Sustainability
Representative:
CSR &
Sustainability
Program
ADVA CSR & Sustainability program is built on four pillars, including: our
employees, local communities, our suppliers and the environment. These
four items represent the areas of biggest impact to our business and
reflect where we want to be judged.
Author
Owner
Wally Walia
Bernhard Wiehler - VP QM
File Name: Integrated Management System Handbook.docx
Version
Date
Status
Page/Pages
4.0
29.10.2014
>Approved<
22 / 28
Reporting
ADVA Optical Networking cares deeply about its CSR programs and we
want to share our progress with our customers, partners, suppliers and
other critical audiences. We have selected the GRI (Global Reporting
Initiative) framework for that reporting, that allows us to evaluate
performance improvements period-to-period within the same structure.
Environment
Author
Owner
Wally Walia
Bernhard Wiehler - VP QM
File Name: Integrated Management System Handbook.docx
Version
Date
Status
Page/Pages
4.0
29.10.2014
>Approved<
23 / 28
Author
Owner
Wally Walia
Bernhard Wiehler - VP QM
File Name: Integrated Management System Handbook.docx
Version
Date
Status
Page/Pages
4.0
29.10.2014
>Approved<
24 / 28
Employee Programs
ADVA has developed specialized programs designed to benefit our
company and our team. For example, ADVA Global Idea Bank rewards
team members who suggest ideas that drive savings or business growth.
Another example is our Leadership Development program. This involves
individual mentoring of future company leaders.
Author
Owner
Wally Walia
Bernhard Wiehler - VP QM
File Name: Integrated Management System Handbook.docx
Version
Date
Status
Page/Pages
4.0
29.10.2014
>Approved<
25 / 28
Supply Chain
We Act as One
ADVAs suppliers are an extension of our company. We hold them to the
same exacting standards that we demand of ourselves. We know that our
customers expect the same level of service and expertise from our
suppliers as they would from any member of our team. To do this, we
work closely with our suppliers. In our relationships, transparency is
everything.
REFERENCES
1. GENERAL
4.1
4.1
4.3.1/4.3.2/4.3.3
5.1/5.3/5.4/5.5/5.6/8.5.1
4.2/4.3/4.6
4.1
4.1
4.1/4.2/8.2.3
4.1/4.4.4/4.4.5/4.5.1
6.1/6.2
4.4.1/4.4.2
7.4.1/7.4.2
4.4.6
8.1/8.2.2/8.2.4/8.3
4.5
4.3.3
Author
Owner
Wally Walia
Bernhard Wiehler - VP QM
File Name: Integrated Management System Handbook.docx
Version
Date
Status
Page/Pages
4.0
29.10.2014
>Approved<
26 / 28
7.1/7.3
4.4.6
7.2/7.5
4.4.6
7.4/7.5
4.4.6
4. ENVIRONMENTAL / SAFETY
MANAGEMENT PROGRAM
8.3/ 7.2.1
4.3.1/4.3.2/4.4.7
Author
Owner
Wally Walia
Bernhard Wiehler - VP QM
File Name: Integrated Management System Handbook.docx
Version
Date
Status
Page/Pages
4.0
29.10.2014
>Approved<
27 / 28
Document Owner
Validation
Areas of validity
Range of products
All purchased, designed and manufactured products and services sold and
marketed by ADVA Optical Networking.
Document History
Revision & Date
Version 3.0/ April 2013
Description of Changes
TL 9000 QMS Handbook: To address the needs of the aimed audience of
this document, the former TL9000 Handbook was completely and renamed
to call Integrated Management System Handbook.
ISO 14001 EMS Manual: The main topics from the former ADVA EMS
Manual were integrated in this document to address the needs of the
aimed audience of this document. The EMS Manual became obsolete with
the official release of this document.
Release
Role
Author
Name
Department / Function
Author
QM Department
Verifier
Wally Walia
Director QM
Approver
Brian Protiva
CEO
Releaser
Bernhard Wiehler
VP QM
Owner
Wally Walia
Bernhard Wiehler - VP QM
File Name: Integrated Management System Handbook.docx
Version
Date
Status
Page/Pages
4.0
29.10.2014
>Approved<
28 / 28