Weinland Park Community Mobility Plan
Weinland Park Community Mobility Plan
Weinland Park Community Mobility Plan
Prepared By:
Mayor
Michael B. Coleman
Columbus City Council
Michael C. Mentel
Hearcel F. Craig
Andrew J. Ginther
A. Troy Miller
Eileen Y. Paley
Charleta B. Tavares
Priscilla R. Tyson
Department of Public Service
Mark Kelsey, Director
Division of Mobility Options
Randall J. Bowman, Administrator
William A. Lewis, Chief Mobility Engineer
Nicholas J. Popa, Bikeways and Community
Mobility Manager
Terry L. Stewart, Project Engineer
Jodi M. Stefanik, EIT
Project Team
Stantec Consulting Services Inc.
HKI Associates, Inc.
Mid-Ohio Regional Planning Commission
University Area Enrichment Association
Walkable Communities, Inc.
Acknowledgements
Acknowledgements
Executive Summary
Table of Contents
Introduction
Mobility Planning
The Community Mobility Planning Process
Mobility Planning in Weinland Park
ii
iii
1
2
3
3
9
10
12
16
Existing Conditions
Guiding Plans and Studies
Automobiles
Pedestrians
Bicycles
Transit
19
20
24
35
44
45
Recommended Solutions
Toolbox of Treatments
Automobile Tools
Pedestrian Tools
Bicycle Tools
Transit Tools
Other Tools
Location Based Recommendations
Neighborhood Improvements
Corridor Improvements
Site Specific Improvements
47
48
48
53
57
59
61
63
63
65
71
83
84
86
90
Historically, the need for vehicular traffic to access downtown from outlying areas of the city has been
prioritized over other modes and the travel needs of local residents in Weinland Park. The result is that
several streets, Summit and Fourth in particular, have become barriers to mobility, hindering multi-modal
connectivity and segmenting the community. Prompted by resident concerns (expressed through 311
requests) as well as other issues such as high incidences of pedestrian crashes and traffic violations, the
City initiated the Weinland Park Community Mobility Plan (WPCMP) to improve mobility conditions
throughout the the neighborhood. The recommendations included in the WPCMP will work to achieve the
following goals:
Balance the transportation system for moving people and goods by all modes (pedestrian,
bicycle, automobile, transit, truck, and rail)
Reduce traffic violations (speeding, failure to yield to pedestrians, running red-lights,
etc)
Recognize and strengthen the connection between land use and mobility (coordination
with other planning efforts)
Promote distinct and vibrant neighborhoods
Address issues identified by community residents
Recommend comprehensive yet implementable solutions
Through a combination of extensive community input and technical data collection, the project team first
worked to identify the existing conditions and most significant barriers to mobility in the neighborhood. The
public input opportunities included several community open house and workshop meetings, neighborhood
walk audits, resident surveys, meetings with stakeholder groups, and informal porch chats. These efforts
resulted in the compilation of approximately 1,000 comments regarding mobility conditions in Weinland
Park.
The most frequent concerns expressed by the public were for pedestrian safety when crossing High, Summit,
and Fourth streets; issues with driving in Weinland Park (most of these related to conversion of Summit
and Fourth streets from one to two-way operation); and concerns over driver behavior (predominantly
speeding). These three categories accounted for over 50% of all comments recevied. Resident concerns
were confirmed by traffic studies which identified excess vehicular capacity and speeding problems along
Executive Summary
Located just north of downtown Columbus and south of The Ohio State University, Weinland Park is a
densely populated community consisting primarily of single and multi-family residences. With a strong
grid style street network and traversed by several north-south and east-west arterial streets, Weinland
Park is well connected to the surrounding city and central Ohio region. This connectivity presents both
opportunities and challenges for mobility within and through the neighborhood.
iii
iv
Recommended
Improvement
Location
Bicycle Parking
Various Locations
Shared Signed
Roadway
11
Improved Signal
Timing
12
16
HAWK Beacon*
Summit St at south
park path
17
HAWK Beacon*
18
Intersection Safety
Improvements**
19
Crosswalk with
Rapid Flash Beacon
20
Crosswalk with
Rapid Flash Beacon
23
Curb Extensions
with Lane Shift
27
Curb Extension
31
Curb Extensions
32
Curb Extensions
33
Curb Extensions
34
Curb Extensions
with Raised Median
47
Mini Circle
48
Mini Circle
49
Mini Circle
Summit and Fourth Streets. Additionally, several offset intersections along these corridors
create poor sight distance for turning vehicles and crossing pedestrians. These factors all result
in high occurrences of pedestrian and vehicular crashes in several locations. Comments related
to bicycle safety and lack of facilities, crime and personal safety, and sidewalk issues each
accounted for 8%, while the remaining 25% of comments were scattered throughout a variety
of other mobility issues.
The next step in the community mobility planning process was the development of a Toolbox
of Treatments, which consists of numerous mobility improvements that were selected
to address the array of issues and concerns expressed through public input and observed
during data collection. The Toolbox is intened to serve as an ongoing resource for use by the
City and residents of Weinland Park to diagnose and address future mobility issues in the
neighborhood.
Drawing on the Toolbox of Treatments, a list of 54 location based recommendations was
develoved to address the existing issues throughout Weinland Park. For each location, a tool,
or combination of tools, was selected and applied to address the identified mobility problem.
Some recommended improvements apply to the entire neighborhood, some to a roadway
corridor, and others to specific sites or intersections.
Once the list of recommended projects was developed, members of the public and the WPCMP
Steering Committee worked with the project team to prioritize the projects. Based on this
prioritization along with factors such as location, effectiveness at achieving the plan goals,
estimated cost, and funding source, an implementation strategy was developed that groups
the projects into short-term (0-3 years), medium-term (4-7 years), and long-term (7+ years)
recommendations and identifies a responsible party for each.
This strategy will help to ensure that the WPCMP is implemented in a way that consistently
improves mobility conditions throughout the neighborhood over the coming years. However,
given the changing nature of funding and community priorities, this plan should be re-evaluted
and updated every five years to reflect completed projects, adapt to new issues, and ensure that
it continues to address the mobility needs of Weinland Park and its residents.
* A warrant analysis has not been conducted to determine whether HAWK Beacons are warranted. If the standard is not met, pedestrian-activated LED rectangular rapid flashing beacons may substitute.
** The Exclusive Pedestrian Phase was determined by preliminary traffic analysis to not be feasible. This being
said, the WPCMP recommends further study. See Intersection Safety Improvements (18) for alternative approaches and more information.
Introduction
Mobility Planning
Through the Community Mobility Planning (CMP) Program, the City of Columbus is
taking a new approach to transportation planning and engineering that acknowledges
and responds to key changes in how residents view and use the transportation system.
It recognizes the role that well designed facilities play in creating healthy and vibrant
communities. Recent focuses on environmental awareness, rising fuel prices, and a
renewed desire for urban living in Columbus have all combined to increase demand for
multi-modal options and improved connectivity between business, retail, and residential
areas. The Mobility Planning Program is one of many steps the City is taking to promote
sustainable development, revitalize urban areas, and improve transportation options for
all residents. Since 2008, the City has adopted a Complete Streets resolution, developed
the Bicentennial Bikeways Plan, updated the Citys Bike Law to promote safe cycling and
require the provision of bicycle facilities, been designated a Bicycle Friendly Community,
and implemented the GreenSpot Program.
In general, traditional transportation planning methods analyze the street system to
maximize operational efficiency for motorized vehicles, often at a municipal or regional
scale. Such plans have lead to the creation of auto-centric networks that often overlook
or even determine the types of land uses that surround them, and frequently discourage
or preclude travel by other modes. Often, older residential neighborhoods near the
urban core bear the marks of such development patterns as interstates and arterial roads
were built through them to connect new suburban developments to the central business
district. Recognizing the importance of complete streets and the need for improved
mobility, particularly in older urban neighborhoods, the City of Columbus developed
the Community Mobility Planning Program to achieve the following goals:
Balance the transportation system for moving people and goods by all modes
(pedestrian, bicycle, automobile, transit, truck, and rail)
Reduce traffic violations (speeding, failure to yield to pedestrians, running redlights, etc)
Recognize and strengthen the connection between land use and mobility
(coordination with other planning efforts)
Promote distinct and vibrant neighborhoods
Address issues identified by community residents
Recommend comprehensive yet implementable solutions
Figure 1: Community
Mobility Planning Process
Existing
Policies
Public
Input
Technical
Data
Toolbox
of
nts
Treatme
Prioritization &
Implementation
in recent years after long periods of disinvestment. It is located adjacent to The Ohio State
University and the Short North and is less than one mile from downtown Columbus, all
of which are major activity generators used by a wide range of people with different
mobility needs. Weinland Park is also a densely populated neighborhood and, at onehalf square mile in area, is conducive to travel by various modes.
Resident concerns recorded by the City of Columbus Call Center (3-1-1) as service requests,
and other issues such as a high number of pedestrian crashes and traffic violations have
also prompted City officials to take actions to improve mobility in and around Weinland
Park. Many of the factors and concerns leading to the selection of Weinland Park for a
CMP are discussed in more detail in the following sections and in subsequent chapters
of this plan.
While the plan was initially intended to focus strictly on the Weinland Park neighborhood,
the City received requests from adjacent neighborhoods to extend the study area along
Summit and Fourth Streets. The entire corridor from I-670 to Hudson Street was included
in the scope because any changes to these streets in Weinland Park would impact traffic
along the rest of the corridor as well.
Weinland Park Transportation Network
The streets in Weinland Park are laid-out in a traditional grid network. High Street and
the one-way pair of Fourth and Summit Streets serve as the main north/south arterial
streets through the community, providing quick access to and from downtown Columbus.
Fifth and Eleventh Avenues are the primary east/west arterial streets, providing access
to High Street and I-71 and generally framing the neighborhood on the north and south.
Seventh Avenue serves as a key route through the center of Weinland Park for local
traffic; it connects to Weinland Park Elementary School, Kroger grocery store, and High
Street. The rest of the street network consists of residential streets running both north/
south and east/west.
This arrangement is highly conducive to neighborhood mobility as block sizes are small
and direct connections are easily made to area destinations. In contrast to conventional
suburban development, where loop and cul-de-sac streets create long circuitous routes,
the streets in Weinland Park are better at facilitating a direct route for pedestrians,
bicyclists, and transit as well as cars. The grid network also provides numerous entry
and exit points to and from the neighborhood and offers multiple parallel routes of travel,
thus reducing the importance of any one intersection or roadway. It is because of the
existing transportation framework and mix of land uses in Weinland Park that this area
is a good location for mobility improvements. A better balance of transportation modes
can be achieved simply through repairing, upgrading, and supplementing the existing
infrastructure, rather than requiring a redesign of the street network.
Figure 4: The Godman Guild moved to its current location on the corner of Sixth Ave and
Sixth St in Weinland Park in 1994.
Since the mid-1990s, renewed attention and investment has been focused on the Weinland
Park neighborhood by public, private, and non-profit organizations. Active and dedicated
community groups like the Weinland Park Community Civic Association, long-standing
organizations like the Godman Guild, newer groups such as Campus Partners and
Community Properties of Ohio, and public agencies such as the City of Columbus and
MORPC have all begun working in concert to effect positive and sustainable changes in
Weinland Park. Their efforts generally focused on crime prevention, increasing home
ownership, and improving and deconcentrating Section 8 housing.
As current residents and agencies work for improvements in the neighborhood and new
residents and businesses move in, this is an ideal opportunity to improve the safety and
function of the transportation system for all users, but for pedestrians, cyclists, and transit
riders in particular.
Figure 6: The Seventh Avenue improvements,
shown here under construction, included
complete reconstruction of the road and the
installation of sidewalks.
4
3
7
9
1
2
In order for the project team to successfully study and recommend solutions to the
mobility issues of the Weinland Park community, it was important to first identify and
begin to understand what those problems are. The most effective way of gaining this
understanding was through input from neighborhood residents and stakeholders. This
process began before the project was even initiated with the tabulation of 311 service
requests, and continued through the entire planning process. The project team sought
to engeage the community and capitalize on the knowledge and input of residents
to identify key locations of concern to study, develop solutions, and prioritize the
recommendations.
10
Number
of Calls
141
70
20
15
8
7
2
1
264
Within the study area, a total of 3,060 service requests were recorded since 2005, of which
264 were transportation related. The 264 relevent concerns were further broken down
by type of request as shown in Table 1 and Exhibit 3 in order to identify any trends. The
majority of 3-1-1 calls were regarding maintenance issues such as potholes or other poor
pavement conditions and sweeping or plowing the streets. These were spread evenly
throughout the entire study area.
Most of the calls regarding signage and signals were to report a damaged sign or request
a new sign. However, the type of sign requested was not available for most calls so
conclusions could not be drawn about specific mobility issues. Multiple requests for
signal timing changes at the Summit Street/Fifth Avenue and Fourth Street/Fifth Avenue
intersections were recorded.
Pedestrian related requests focused on damaged sidewalks in various locations. However,
two calls requested pedestrian safety improvements at the Seventh Avenue/Summit
Street intersection. All but two of the calls concerned with vehicle speeds were along
High Street. These asked for traffic calming, a speed trailer, and a change to the speed
limit.
11
The city of Columbus is working on a plan to address the issues you have moving around
your community every day either on foot, by bike, bus, car, or wheelchair.
Your input is key for city engineers to use in the analysis and will lead to potential solutions.
We need your help to identify the issues that need to be addressed in the plan!
October 4, 2008
Neighborhood Walk Audit - see other side
With one of the primary goals of the Community Mobility Planning Program being to address
transportation issues identified by community residents, public input and involvement played a
vital role throughout the planning process. From the initial development of plan goals, to the
identification of mobility issues, to the selection and prioritization of solutions, residents of the
Weinland Park community and area stakeholders were involved throughout the planning process.
All public involvement materials from the project are included in Appendix B.
The City conducted numerous public involvement events, in a variety of venues and
formats, in order gain participation from as wide a range of residents as possible. At the
outset of the planning process, a Communication Plan (See Appendix B) was created to
act as a guide for public involvement throughout the project. The goals and objectives of
the Communications Plan are to identify activities that are:
Engaging and informational to the public, stakeholders, and the project team
Comprehensive in nature
Result-oriented
Inclusive of other government organizations
In order to ensure members of the community were made aware of and had the
opportunity to participate in the planning process, multiple methods of notification were
used for all of the scheduled public events. A project website was established on which all
meeting materials and additional project information was made available. Prior to each
event, the City issued press releases, posters were hung in businesses and community
facilities throughout the neighborhood, and fliers were distributed during door knocking
campaigns by team members and representatives from the Weinland Park Community
Civic Association. Additionally, emails were sent out on multiple listservs and to any
resident or stakeholder who provided their contact information.
The following is a brief description of the approaches the City took to engage and facilitate
discussions with the public during the planning process:
12
Community Open House Held on September 24, 2008 at the OSU Schoenbaum Family
Center, the purpose of this meeting was to kick-off the WPCMP and introduce the planning
process to the community. Residents were also asked to share their general mobility
concerns with the project team. Approximately 40 people attended the meeting.
CABS
Campus Partners
City Departments
Community Properties of Ohio
Central Ohio Transit Authority
(COTA) (2)
Directions for Youth and Families
Godman Guild
Huckleberry House
Indianola Math, Science, and
Technical School
Italian Village Society (2)
Kroger
Living Hope Fellowship Church
Maynard Blake Group
National Youth Advocate Program
Neighborhood Services, Inc.
Neighbors In Action
North Central Mental Health
Ohio Department of Transportation
(ODOT)
Seventh Avenue Community Baptist
Church
St. Joseph Montessori School
University Area Commission (1 project
introduction & 4 meetings)
University Community Association
University Community Business
Association
University District Organization
Wagenbrenner Company (2)
Weinland Park Community Civic
Association
Weinland Park Elementary School
13
Resident Surveys Surveys about the existing conditions and barriers to mobility in
Weinland Park were distributed throughout the study area as another means of collecting
comments and gauging the perceptions of mobility in the neighborhood. An initial
round of surveys was primarily collected from residents living within the Weinland
Park neighborhood while a second round was distributed to residents living north
of Weinland Park. In all, over 100 surveys were completed and returned. The survey
results showed that more than 50% of residents reported problems in almost all facets of
community mobility, with the greatest problem areas being related to road surfaces and
driver behavior impacting safety for pedestrians and cyclists.
www.columbusmobility.info
Porch Chats This method of data collection and public involvement was employed to
gain input from residents who were unable to attend any of the formal public events for
the project and would have otherwise not been engaged in the planning process. The
porch chats involved over 40 informal interviews conducted at residents houses, various
businesses, and other community gathering places. These informal conversations, which
occurred among small groups of individuals and generally covered the same questions
as the surveys, captured input from residents in all geographical areas and walks of life
across the Weinland Park neighborhood.
Closing Workshop Held at Grace Baptist Church on November 17, 2008, the closing
workshop provided a summary of the planning process and public input to date, as well as
information about the effectiveness of various traffic calming tools. Attendees then broke
into four groups and used mapping of Weinland Park to recommend potential solutions
for specific locations throughout the neighborhood. Approximately 40 attendees were at
the meeting.
University Area Commission Public (UAC) Meeting A presentation and opportunity
for public input on the WPCMP was incorporated into the January 15, 2009 UAC Executive
Committee meeting at the Eleventh Avenue Community Policing Center. UAC members
and other attendees were asked to share any comments or questions about the planning
process or transportation issues in the community. The resident survey was also handed
out to representatives of neighborhoods to the north of Weinland Park for distribution,
and the deadline for submittal moved back to allow for more input. About 20 people
attended this meeting.
14
Stakeholder Update Meeting On May 28, 2009 a project update meeting was held at
the Eleventh Avenue Community Policing Center. All stakeholders who, during the
initial interviews, expressed an interest in continued involvement in the project were
invited to attend. Team members presented the results of the public input process and
the technical data analyses along with the preliminary toolbox of solutions and location
specific recommendations for each tool.
Final Community Open House A second community open house meeting was held on
June 24, 2009 at the OSU Schoenbaum Family Center. The team presented the results of
the public input and technical study portions of the plan and were shown the preliminary
solutions recommended for the neighborhood. Attendees had the opportunity to discuss
questions and concerns regarding the plan with City engineers and to rank the solutions
based on which they felt should be given the highest priority. These rankings are
summarized in the Prioritization and Implementation chapter.
Several attendees expressed concern that safety issues on Summit and Fourth Streets,
which had been removed from the scope of the plan due to uncertainty of future traffic
demand and the potential for light rail, were not adequately addressed. Based on input
received at this meeting, the City determined that Summit and Fourth Streets would
again be included in the plan and that more detailed analyses of the corridor should be
done in order to adequately address the Communitys concerns.
15
Universal Design
4%
Education
2%
Maintenance
6%
Pedestrian
Crossing
21%
General
Comment
7%
Transit
7%
Pedestrian
Sidewalks
8%
Automobile
19%
Crime
8%
Bike
8%
Driver
Behavior
11%
16
Automobile (179) traffic flow and safety, parking, issues affecting motorists
Bike (78) concerns regarding the safety and comfort of cyclists
Crime (77) concerns for personal safety
Driver Behavior (108) issues with motorists impacting the safety and comfort of
other travel modes
Education (20) concerns to be addressed through education rather than
infrastructure
Maintenance (57) surface conditions, broken signs and signals, overgrown
vegetation, trash
Pedestrian Crossings (193) concerns for pedestrians crossing streets
Pedestrian Sidewalks (77) issues pedestrians face walking along sidewalks/
streets
Transit (66) comments regarding COTA, CABS, and other transit options
Universal Design (35) ADA and accessibility issues
General Comment (65) comments that do not fit into any of the other categories
The comments were then sorted by category in order to identify the key issues that are
of greatest concern to the community and by location to identify hot spot areas most
in need of attention. Figure 16 shows the percentage of comments for each of the eleven
categories mentioned above, while Figure 17 shows the most frequently discussed corridors
and intersection locations respectively. The most comments (21%) dealt with concerns
regarding unsafe pedestrian crossings. These comments were overwhelmingly related
to issues with crossing High, Summit, and Fourth Streets, with the most pertaining to the
offset intersection at Summit Street and Seventh Avenue.
Auto-oriented concerns were the second most prominent issue, comprising 19% of all
comments. Many of these comments related to discussions about converting Summit
and Fourth Streets from one-way to two-way operation; a topic consistently mentioned
at each public forum. Generally, opinions on the issue were split, with a slight majority
in favor of two-way operation. Those in favor tended to cite better traffic calming, slower
vehicle speeds improving pedestrian and bike safety, and better integration into the
neighborhood. Those opposed to conversion felt that traffic calming could be achieved
through other measures, access to downtown would be impaired, and that two-way
traffic would result in reduced safety and increased noise. Others felt that more public
input was needed outside of the Weinland Park area.
In addition to discussions about Summit and Fourth Streets, the automobile category
encompassed concerns about unsafe driving conditions. The most repeated concern
was poor sight distances, making for hazardous intersections. Parking too close to
the intersection was one reason cited for poor visibility, as were the numerous offset
intersections in the neighborhood.
Figure 18: Resident Chris Orban describes safety
concerns on Summit and Fourth Streets at a
public meeting.
Corridor
Intersection
20
40
60
80
Number of Comments
100
120
17
Speeding is the most prevalent concern in the driver behavior category (11%), especially
on Summit and Fourth Streets, where people feel it divides the neighborhood and makes
walking and biking unsafe. The general consensus was that the speed limit should be
lowered on these streets or at least enforced at 35mph. Fifth, Indianola, and Euclid
avenues were also mentioned repeatedly with regards to speeding.
The bike, crime, and pedestrian sidewalk categories each accounted for 8% of the total.
Comments in each of these areas were fairly consistent among individuals. Bike concerns
centered around the lack of facilities and connection to downtown, especially on Summit
and Fourth Streets. Crime was mentioned as a deterrent to biking and walking and
the need for better lighting was consistently suggested. The generally poor condition
of sidewalks was mentioned repeatedly and observed on the walk audits. Attendees
identified poor walking conditions and locations of sidewalks in need of repair. Comments
about sidewalks were also closely tied to maintenance issues.
Comments regarding transit were generally favorable, stating that the area is one of the
best served by COTA; a few comments cited the need for more bus shelters and problems
getting to outlying areas. The general category encompassed all comments that did not
fit into other categories or were outside the scope of the mobility planning process. Some
of these were related to aesthetics and expressed a desire for better streetscaping and
gateway features. The maintenance and universal design categories generally called for
improved maintenance by the City and property owners and for improved accessibility.
Finally, some comments called for a need to better educate users of the transportation
system, particularly motorists, to safely travel with all modes.
18
Existing Conditions
LE
E
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!
KIT
ZM
ILLE
R
BABBITT
DIXON
WAGGONER
MORRISON
BRICE
!!
!
!!!
!!
!!
!!
!
NOE-BIXB
Y
HAMILTON RD
(SR 317)
TAYLOR
!!
!!
!
!
!
!
!
!!!
STYGLER
STELZER
CASSADY
JAMES
ALUM CREEK
EBRIGHT
!
!
!
HAMILTON
KARL
CLEVELAND
JOYCE
OHIO
LOCKBOURNE
AL
AN
C
!!
!!
!!
33
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
R3
TUSSIC
SUNBURY
T (S
ES
SPRING
ST
AT
I 71
SINCLAIR
MAIZE
AVERY
OLENTANGY RIVER
SAWMILL
REED
KENNY
PARSONS
!
!
!
!
!
!
!!
!
!
!
!
!
!
!
!
!
!
!
!
!
!!
!
!
!
!!
!!
GA
!!
!! LLOWA
Y
!!
!!
!
!
!
!!
!!
GANT
Z
US
GROVEP
HAYES
LIT
PO
HO
LIS
!!
!!
!!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!!
!!
!!
!!
!
!!
!!
HOOVER
!
!!
!!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!!
!!
!!
!!
!!
!
!
!!
!!
!!
!!
!!
BIXBY
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!!!
!!
!!
RO
WE
REFUGEE RD
LO
N
ORT
PONTIUS
!
!!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!!
!!
!!
!!
! JACKSO
!
N
!
TUSSIN
TE
R
MAIN
ROHR
!
!
!
!
!
!
!
!
!
!
!
!
!
ES
HOLT
WILLIAMS
CH
)
(SR 16
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!!
!!
W
IN
!
!
!
!
!
!
!
!
!
!
!
!
BROA
ST (SR 16)
!
!!
!
!
!
!
LIVINGSTON
D ST
BROAD
!
!
!
!
!!
!!
!
MAIN
TAYLOR
!!
!
!!!
!!
!!
o
FIFTH
FREBIS
DYER
1
I7
(SR 665
!
!!
!!
!!
!!
!!
!!
!!
!!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!!
!!
!!
!
!
!!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
ALKIRE
AR
CL
AT
ST
!!
!
!
!!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!!
!!
!!
!!
!!
!
!
!
!!
!!
!!
STIMMEL
CLIM
E
!!
!!
!
!
!
!
!
!
!
!
!
!
!
!
!
!!
!
!
!
!
!
!
!
!
!
!!
!!
!!
!!
!
!
!!
!!
!!
!
!
!
!
!
LO
!
NDON
!
!
-GROV
!
!
EPORT
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!!
!!
!!
!!
!
!
!
!
!
!
!
!
!
!
!
!
HIGH
GU
LONG
IVAN
!!
!!
!!
!!
!!
70
I6
HA
ON
HALL
MORSE
!!
!!
!!
!!
SR 31
S
WIL
SULL
EAKIN
!!
!!
!
!
!
!
!
!
!
!
!
!!
!!
!
PER
DUBLIN
LEAP
I 67
COO
DUBLIN
I 270
WILCOX
COSGRA
ELLIOTT
NB
MOCK
FIFTH
FEDE
!!
!!
!!
!!
!!
!
!
!
!
!
!
!
!
!!
!!
!!
!!
!
SU
COLLEGE
161
SR
AGLER
WEBER
LANE
BEVELHEIMER
CENTRAL
Y
UR
FERRIS
!!
!!
!!
!
!
!
!
!
!
!
!
!
!!
!!
!!
!
!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
5)
HOUCHARD
BETHEL
!
!!
!!
!
!
!!
!!
!
!
!
!!!
!
R 74
PARK
ROBERTS
RENNER
!
!!
!!
!!
!!
!!
HARD
POST
RINGS
!!
!!
EM
HARL
D (S
33
SUMMIT VIEW
!
!!
!
!
!
!
!
!
!
!
!
!
!
!!
!
!!
!!
!!
!
!
!!
!!
!
!
!
!
!
!
!
!
!
!
!
!
!!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!!
!!
ND
POWELL
!
!!
!!
!
!
!
!
!
!
!
!
!
!
!
!
!!
!!
!!
!!
!!
!!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!!
!!
!!
!!
!!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!!!
!!
IN R
DUBL
BRA
!
!
!
!
!
!
!
!!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!!
!
!
!
!
!
!
!
!
!
!!
!!
!!
!!
!!
!
!!
!!
!!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!!
!!
!!
!!
!!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
HAYDEN RUN
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
ROBERT
!
S
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!!
!!
I 70
!
!
!!
!!
!!
!
!
!!
ST CLAIR
40)
TYPE
6-2DS
6-2D
MAIN
MAIN
OHIO
6-2
BRYDEN
4-2DS
4-2D
COLE
LIVIN
GSTO
(US 23)
WHITTIER
CHAMPION
NEIL AVE
LONG
AD ST (US
PARSONS
I 70
GRANT
I 71
ON
HARM
HIGH ST
FRONT
62)
RNON
MT VE
BRO
23)
(US
TOWN ST
SPRIN
GRANT
ST (US
MARCON
SOUDER
SR 315
OOD
GLENW
UN
MO
SOUDER
20
33)
FRONT
SR 315
RD (US
FOURTH
DUBLIN
I 670
MCKINLEY
LEONAR
HIGH
I-6
70
GOODALE
I 670
I 71
NEIL
ES
HW
SR 31
RT
NO
SECOND
JOYC
4-2
3-1
2-1
C
Scenic Byway
Columbus 2010 Planning Area
21
22
23
Automobiles
Road Network
As was discussed earlier, the streets in and around Weinland Park are laid out in a grid network.
The neighborhood is bounded by arterial streets on the north (Eleventh Avenue), south (Fifth
Avenue), and west (High Street). Fourth and Summit Streets, which run north-south through the
center of the neighborhood, are a one-way pair that also function as arterial roadways. Two eastwest collector streets (Chittenden and Seventh Avenues) and one north-south collector (Indianola
Avenue) provide further connectivity to the arterial roads and key locations throughout the
neighborhood for area residents. The remaining streets in Weinland Park are residential in nature
and generally serve only those users who live on them. These three different types of roadways
create a system that serves a wide range of motorists, from those traveling through Weinland Park,
to those making strictly local trips within the neighborhood.
Within the study area, the pavement width of Summit and Fourth Streets ranges from 40 to 52 feet,
with the majority of each being 46 feet wide. Currently, the typical section for Summit and Fourth
Streets, between Warren Street and Eleventh Avenue, includes a permanent parking lane that is
not striped, two variable width travel lanes, and one lane that functions as a travel lane during
the peak hour and a parking lane for the remainder of the day. From Weinland Park to Hudson
Street, Summit Street is wider both roads widen to provide three travel lanes with permanent onstreet parking on both sides. Fourth Street has the same section from Weinland Park to Wyandotte
Avenue where it narrows to three travel lanes and one unmarked permanent parking lane. Both
Summit and Fourth Streets have 35mph speed limits.
Through the study area, the Summit and Fourth Street corridor is the most prominent feature
of the transportation network. This one-way pair carries US 23 north of downtown Columbus
and is heavily used by commuters going to and from downtown from northern suburbs such as
Clintonville and Worthington; however, the importance of Summit and Fourth Streets as access
routes to and from downtown has diminished in recent years. With the completion of I-670,
motorists can easily travel between I-71 and SR 315, both of which provide freeway access to
communities north of downtown.
24
Between Fifth and Ninth Avenues, High Street is 48 feet wide with two travel lanes in each direction
and a center turn lane. North of Ninth Avenue, it widens between intersections to provide on-street
parking on one or both sides of the street, but remains 50 feet wide at intersections through the use
of curb extensions. The speed limit on High Street is 25 mph. Fifth Avenue is 44 feet in width,
has two lanes in each direction, and a posted speed of 25mph. With the exception of some sections
of residential street that are one-way, all other streets in the study area have one travel lane in each
direction and a speed limit of 25mph. Most streets also have on-street parking on at least one
side of the road.
Although it runs north-south along the entire eastern edge of Weinland Park, Grant Avenue is
not included in the analyses or recommendations of this plan. As part of the project to redevelop
the Columbus Coated Fabrics site, the entire road within Weinland Park is being reconstructed.
The improved Grant Avenue will consist of one travel lane in each direction, on-street parking
on both sides of the road, curb extensions at intersections, and a posted speed of 25mph (See
Appendix D). Construction of the Grant Avenue improvements is scheduled to begin in 2010.
Existing Volumes, Capacity, and Speeds
Existing traffic volumes and speeds in Weinland Park and along the Summit and Fourth
Street corridors were analyzed in order to gain the necessary understanding of traffic
conditions to develop mobility recommendations for the neighborhood. Traffic counts
conducted by the City between 2003 and 2007 were supplemented with new counts
at key locations (Exhibit 4). The vehicular speed and volume information collected
during these counts was then analyzed to determine if and where any capacity and/or
speeding problems exist. A summary of the traffic counts is included in Appendix E.
Determining the existing capacity of major roads in the study area is important in trying
to understand what changes to the system can be accommodated. Traffic capacity
is generally expressed in levels of service (LOS). LOS is a measure of vehicle delay
and is rated from A to F, with A being the best (no delay) and F being the worst
(gridlock). Table 2 shows LOS A through F and the corresponding delay in second per
vehicle for signalized intersections. In the past, LOS C has been the accepted standard
for transportation planning. However, in urban areas, particularly on roads where
multi-modal options and slower vehicle speeds are desired, LOS D and even E are
increasingly being recognized as acceptable standards. Because the capacity of a road
is generally constrained at its intersections, these are the locations on which analysis
was performed.
The intersections that most influence the roadway capacity in Weinland Park and their
associated LOS for the AM and PM peak hours are shown in Table 3. This analysis
shows that, even during the highest volume hours of the day, current traffic levels
on Summit and Fourth Streets are well within acceptable levels of service. This also
indicates that, for the remaining hours of the day, there is likely excess capacity on both
of these roads, which can contribute to excessive traffic speeds.
Delay in Seconds
< 10 sec
> 80
AM Peak
PM Peak
C (24.4)
C (24.6)
B (14.4)
C (24.7)
B (15.2)
B (16.6)
B (15.2)
B (19.1)
B (14.7)
C (24.4)
25
26
The speed data collected for Summit and Fourth Street further confirm that, with
current traffic volumes, there is excess capacity in the corridor. Figures 25 and 26 show
the 85th percentile speeds for the locations where counts were taken along Summit
and Fourth Streets. With few exceptions, the 85th percentile vehilce speeds along
both roads are at or above 40mph, with some locations exceeding 45mph. This means
that a normal motorist is comfortable driving between five and twelve miles over the
speed limit through the study area. This poses safety concerns for motorists as well as
pedestrians and cyclists.
How is it Used?
Figure 25: 85th percentile vehicle speeds on Summit Street (35mph posted speed limit)
50
40
35
30
25
20
15
10
5
South of
Warren St.
North of
Warren St.
South of 2nd
Ave.
South of 5th
Ave.
South of 6th
Ave.
Between 8th
& 9th Ave.
At
Chittenden
Ave.
Between
Chittenden &
12th Ave.
0
North of
Clinton St.
45
Location
27
50
45
40
35
30
25
20
15
10
5
South of
Warren Ave.
At Warren
Ave.
South of 2nd
Ave.
At 2nd Ave.
South of 5th
Ave.
At 5th Ave.
South of 6th
Ave.
Between 8th
Ave. and 9th
Ave.
Between
Chittenden &
12th Ave.
North of
Clinton St.
Location
28
Several of the factors discussed above contribute to the high vehicle speeds along
Summit and Fourth Streets. The excess green band in the signal cycles allows motorists
to speed through multiple intersections unstopped, while the number of lanes and
relatively low vehicular volumes cause a lack of friction between moving vehicles and
fixed objects along the edges of the road such as parked cars.
Summit and Fourth Streets are not the only roads in Weinland Park on which speeding
is a problem. Figure 27 shows the streets with 25mph speed limits that have 85th
percentile speeds over 30mph. This information indicates that speeding on Fifth
Avenue is of particular concern given that most of the count locations registered 85th
percentile speeds near or above 35mph. Similar to Summit and Fourth Streets, the
excess lane capacity on Fifth Avenue allows vehicles to speed without being slowed by
congestion.
85th Percentile Speed on Streets with 25 MPH Posted Speed Limit
Figure 27: 85th percentile vehicle speeds on streets with a 25mph posted speed limit
45
40
35
30
25
20
15
10
5
High St South of
King Ave
High St South of
5th Ave
Chittenden Ave
between High St
and Summit St
Chittenden Ave
between 4th St
and Grant Ave
Location
* Note: This segment lies partially outside of the study area.
Vehicular Crashes
The most recent three-year crash data (2005-2007) was obtained from the Ohio
Department of Public Safety and reviewed to identify trends that might indicate
locations in need of safety improvements. A total of 1,571 crashes were recorded during
that period within the study area. Of those, 1,036 occurred within the Weinland Park
neighborhood, and the other 535 occurred along Summit and Fourth Streets to the north
and south of the neighborhood.
29
# of Crashes
47
44
41
37
36
33
32
31
30
Exhibits 5-7 illustrate the locations and number of crashes for each road segment
and intersection in the study area. As could be expected, the vast majority of crashes
occurred on or at the intersections of arterial streets, where traffic volumes are the
highest. Approximately one-third (357) of the crashes in Weinland Park occurred on
High Street, and another 30% occurred on Summit or Fourth Street, which saw 144
and 160 crashes respectively. A total of 168 crashes occurred along Fifth Avenue, 121
of which were at the High, Summit, or Fourth Street intersection. Similarly, Eleventh
Avenue had 176 crashes, with 104 occurring at the High, Summit, or Fourth Street
intersection. The nine highest crash intersections all had 30 or more crashes and are all
located on one of these three streets (Table 4).
A review of the crash severity shows that 81% (1,272) of the crashes resulted in no
damage or property damage only. There were also 304 injury accidents and one fatality
over the three year period. The fatality occurred at the intersection of Seventh Avenue
and Fifth Street and resulted from a vehicle running the stop sign and colliding with
another vehicle.
While fewer than 20% of all crashes in the study resulted in injury, there are several
corridors and intersections that had higher than average injury rates, suggesting that
safety may be of particular concern in those locations. Fifth Avenue presents the
greatest concerns, as 33% of the crashes along that corridor were injury crashes. The
injury rates for the full length of Summit and Fourth Streets (Warren Street to Hudson
Street) were comparable to one another and the rest of the study area. However, within
the boundaries of Weinland Park, the injury rates for both streets increase to about 25%.
For intersections in the study area, just over 20% of all accidents resulted in injury.
The intersections of Fifth Avenue with both Summit and Fourth Streets both have
significantly higher than average injury occurrences at 32% and 45% respectively.
The intersection of Seventh Avenue with High Street also has a higher than average
percentage at 32%. The high number of crashes combined with the high percentage of
injuries at these three intersections raises particular concern for the safety of motorists,
pedestrians, and cyclists, and may indicate that better intersection design, signal timing,
and/or speed control measures are necessary.
30
31
Exhibit 5: Recorded Vehicular Crashes (2005-2007) Summit and Fourth Streets Northern Section
32
33
Exhibit 7: Recorded Vehicular Crashes (2005-2007) Summit and Fourth Streets Southern Section
Geometric Issues
The intersection of Ninth Avenue with Indianola Avenue, and the intersections of
Summit Street with both Seventh and Eighth Avenues are all offset. This means
that two legs of the intersection do not line up across from each other creating safety
issues for drivers and pedestrians. Problems include poor visibility of vehicles and
pedestrians, and confusing signing and vehicle priority for drivers. The most extreme
example of this issue in Weinland Park is the intersection of Seventh Avenue and
Summit Street. Confusion regarding vehicle priority and driver expectations is created
when the light turns green for both the eastbound and westbound traffic at the same
time. Westbound vehicles turning left have difficulty determining whether vehicles
turning right onto Summit Street from Seventh Avenue are continuing east on Seventh
Avenue or south on Summit Street. Further exacerbating the problem, obstructions at
the intersection make it difficult for drivers to see pedestrians crossing the street. These
factors combine to create a confusing condition for motorists to manuever.
The intersection of High Street and Seventh/King Avenue contains an abrupt deflection
for vehicles traveling east and west. The change in direction in the middle of the
intersection makes it difficult to see oncoming vehicles while turning left, and to see
hazards on the far side of the intersection. These geometric deficiencies are likely a key
contributing factor to the high number and above average percentage of injury crashes
that occur at this intersection.
34
Pedestrians
Sidewalks
During October 2008, a sidewalk inventory was performed that graded the condition
of all 22.1 miles of sidewalk and all 818 curb ramps in the study area. While the City
of Columbus does have existing standards regarding sidewalks for the purposes of
code enforcement, it does not currently have an inventory rating system. Therefore, a
sidewalk and curb ramp rating system developed and used by the City of Richmond,
Virginia was utilized for this study. This system was selected because it is easy to
record and update and it can be conducted by a person with little to no engineering or
code enforcement knowledge, thus allowing members of the community to assist in
maintaining the sidewalk ratings in the future.
The rating system assigns grades from A (best) to F (worst) for a section of sidewalk
depending on the number of demerits present (Table 5). The individual conducting the
inventory identifies minor demerits (those that may be an inconvenience to mobility)
and major demerits (those that may make a section of sidewalk impassable, particularly
for someone using a mobility aid) in order to determine the appropriate grade. For
this inventory, examples of minor demerits include cracks that are less than one inch,
obstructions that slightly narrow the sidewalk, sidewalk widths that are below standard
but more are than three feet, and some trash and/or debris. Examples of serious
demerits include cracks and heaving that are greater than one inch, obstructions or
sidewalk widths that provide less than three feet of passable space (minimum required
for wheelchairs and some strollers), and substantial trash and/or debris. Similarly,
the curb ramp rating system assigns ratings of O (outstanding), S (satisfactory), or U
(unsatisfactory) depending on the number of demerits present (Table 6).
Level of Service
Criteria
Excellent
Good
Fair
Exhibits 2-3 minor demerits or 1 major demerit and overall viewed as average
Poor
Exhibits 4-5 minor or 2-3 major demerits and overall viewed as below average
Very Poor
Exhibits more than 3 major demerits and overall viewed as well below average
Failing
Missing
No sidewalk present
UC
Under Construction
New or recently improved: continuous for whole block, uniform material (brick, concrete), even surface with no
ponding, no trash/debris/dirt, no cracking/heaving/spalling, no roots or grass present, and having an overall
aesthetically pleasing appearance
Exhibits only 1-2 minor demerits but overall still viewed as above average
N/A
35
Level of Service
Criteria
Above Average
Average
Failing/No Ramp
Under Construction
N/A
UC
A
B
C
D
E
F
Number of
Segments
9
32
75
160
83
13
Percent Within
Study Area
2%
8%
19%
41%
21%
3%
M
UC
8
16
2%
4%
Grade
36
Grade
Number of Ramps
O
S
U
UC
195
281
334
8
Percent Within
Study Area
24%
34%
41%
1%
Sidewalks were divided into sections by breaks at streets and alleys. This resulted
in sections of varying lengths, meaning that a longer section would be more likely to
have demerits than a shorter section. This variation was minimized by photographing
every section and reviewing each grade once the entire inventory had been completed;
however, given the variation in length of sidewalk sections and the observational
nature of the grading system, the inventory must be viewed in the proper context. It is
not intended to be used for code enforcement, but rather as a tool to identify the overall
state of the sidewalk network in the neighborhood and to help prioritize the need for
repair and replacement efforts.
As shown in Table 7, 65% of the sidewalks in the Weinland Park and along the Fourth
and Summit Street corridors received a rating of poor (D) or worse. This means that
three-quarters of the sidewalks in the study area have at least two serious faults that
may make them impassable for some pedestrians. Exhibits 8-10 shows each section of
sidewalk that was inventoried and the rating it received. In general, High Street has the
best sidewalk conditions in the neighborhood, while all of the other arterials are badly
in need of repair, with D and E being the most common ratings. Of particular
concern along Summit and Fourth Streets are the presence of major obstructions (i.e.
utility poles, sign posts, debris) that reduce the clear walking zone to less than three
feet, making the route impassible for anyone using a mobility aid. With the completion
of the Seventh Avenue improvements in late 2008 and the upcoming reconstruction
of Grant Avenue, a small section of Sixth Avenue just east of Fifth Street is the only
location in Weinland Park with no existing or planned sidewalk.
Similar to the sidewalk inventory, Table 8 shows that many of the curb ramps in
Weinland Park are also in need of repair or replacement, with the greatest number
(41%) receiving a rating of unsatisfactory.
37
38
39
Exhibit 10: Sidewalk Inventory Summit and Fourth Streets Southern Section
Pedestrian Crossings
In order to identify the areas of concern for pedestrian crossings, the results of the
public input process were reviewed along with reported pedestrian crash data from
2000-2007 (Exhibit 11). While vehicular crash data is analyzed in three year segments,
pedestrian crashes are comparatively infrequent. For this reason, a longer time period
was analyzed in an attempt to identify trends that could indicate an unsafe crossing
location. Despite being relatively few in number, crashes involving pedestrians are far
more likely to involve injuries and/or fatalities than crashes only involving vehicles.
Therefore, even a few crashes over several years can justify safety improvements at a
pedestrian crossing location.
40
A total of 105 crashes involving pedestrians were recorded within the study area from
2000 to 2007. Of those, 90 (86%) resulted in injury, 15 (14%) involved property damage
only, and no reported fatal pedestrian crashes were reported. Just over half of the
crashes (54) occurred along High Street; Summit Street experienced the second most
crashes (22). Although the number of pedestrian crashes on High Street is substantially
higher than on any other street in the study area, a fact that can not be overlooked, there
are several factors that must be considered when reviewing these statistics. Foremost,
High Street has far more pedestrian traffic than any other street in the area, particularly
at the northern end of the neighborhood, adjacent to the Ohio State campus and an area
where there was a cluster of crash activity. Additionally, the completion of the South
Campus Gateway in late 2005 drastically improved the pedestrian environment along
High Street between Ninth and Chittenden Avenues. While these facts do not mean
that safety concerns do not exist along High Street, they do suggest that the number of
crashes may not be as disproportionately high as the raw numbers suggest.
Crossing locations that were identified by residents and that have a high number
of crashes were given the highest priority in the evaluation of existing conditions.
The locations of greatest concern for pedestrian crossings include the following
intersections:
Summit Street at Seventh Avenue: This offset intersection is located at the
northwest corner of Weinland Park Elementary School and is therefore used by
large numbers of students. It was the single most frequently identified safety
concern of area residents. The misalignment of Seventh Avenue creates longer
crossing distances for pedestrians and confusion for motorists. Utility poles and
signs on the southwest corner of the intersection also obstruct motorist views of
pedestrians in the south crosswalk of the intersection. Jaywalking was observed
frequently during both the walk audit and other field observations at this
intersection. Four crashes involving pedestrians were reported during the study
period, including one teacher who was struck during school dismissal.
High Street at Fifth Avenue: This intersection of high volume arterials, located
at the southwest corner of Weinland Park, had the highest number of crashes
involving pedestrians in the study area with eight. The combination of high
vehicular volumes, speeding on Fifth Avenue, and high pedestrian volumes (due
in part to the presence of four bus stops at this intersection) all lead to substantial
safety concerns for pedestrians crossing at this location.
High Street at Seventh/King Avenues: This intersection is a vital access point
into the Weinland Park neighborhood. The presence of Kroger on the southeast
corner draws significant pedestrian and vehicular traffic, and the presence of
Vision and Vocational Services on the southwest corner brings many vision
impaired pedestrians to the intersection. Despite being somewhat skewed, the
excessive width (42 feet for three lanes) and downward grade of Seventh Avenue
as it approaches the intersection accommodates motorist speeding to beat
the light at High Street. This creates a particularly unsafe situation for both
pedestrian and motorists. There were four recorded pedestrian crashes at this
location.
Summit Street at Fifth Avenue: Concerns regarding vehicle speeds on both
streets were raised by members of the public. The pedestrian walk phase was
also observed to be extremely short, providing less than ten seconds of walk time
before changing to a flashing dont walk. Since 2000, five crashes involving
pedestrians have been recorded at this intersection.
Residents also expressed a need for more crossing locations on both Summit and
Fourth Streets, and to a lesser degree across High Street. One resident commented that
there are not enough legal spaces to cross (Summit and Fourth Streets), particularly
between Fifth and Eighth Avenues. Beyond the comment, many pedestrians have been
observed crossing at indiscriminant locations between signalized intersections. While a
lack of pedestrian education (as to the legality of crossing at unmarked crosswalks) and
enforcement may provide some explanation, the lack of crosswalks where pedestrians
want to cross (and are crossing) is presumably the most significant factor contributing
to the prevalence of jaywalking in the area. Though there are marked crossings in
the area, these are often out of the way and located at signals with long cycle lengths
further delaying pedestrians. No marked crosswalks are located in convenient locations
for those traveling to or from the park or the south side of the school facility.
41
Finally, although Weinland Park covers a relatively small area, it has numerous
resources and public facilities that are used by people from outside the neighborhood.
Those who are unfamiliar with the area have little to no guidance to find key
destinations such as the Godman Guild and the OSU Schoenbaum Center, both of
which are located in the core of Weinland Park away from High Street and Fifth
Avenue. A lack of good directional signage can prove very frustrating and even
intimidating for a pedestrian trying to find a destination in an unfamiliar area.
42
43
Bicycles
The Columbus City Code identifies three distinct types of transportation facilities for
bicycles: Class I, Class II, and Class III Bikeways. As defined in the Code:
Bikeway means a facility that explicitly provides for bicycle travel. A bikeway may
vary from a completely separated facility to simple signed streets as follows:
(a) Bike path (Class I Bikeway) is a facility for the exclusive use of bicycles
separated from motor vehicle traffic except at bike crossings.
(b) Bike lane (Class II Bikeway) utilizes existing roadways and is contiguous
thereto but provides a separate lane of travel for the exclusive or semi-exclusive
use of bicycles. The bike lane is physically separated from motor vehicle traffic by
painted lines, pavement coloration, curbing, parked vehicles or other barriers.
(c) Bike route (Class III Bikeway) utilizes existing streets and roads. No separation
of motor vehicle and bicycle traffic is provided as only signs are present to indicate
the course of the bike route. (Ord. 1050-77.)
Currently the only bikeways in the Weinland Park neighborhood are Fourth and
Summit Streets, which function as a one-way pair Class III bikeway.
Bike parking facilities, while not prevalent in the neighborhood, have been incorporated
into many new buildings and developments in recent years such as the South Campus
Gateway and the new Community Policing Center. The majority of the bicycle parking
facilities are concentrated near the Ohio State campus as well as along High Street,
while they are conspicuously absent from other locations, such as the new Weinland
Park Elementary School and Schoenbaum Center.
44
Although Weinland Park, like many other Columbus neighborhoods, has for years
suffered from a lack of bicycle facilities, the City has made strong commitments and
tangible strides toward becoming much more bicycle friendly. Approved in May
2008, the Bicentennial Bikeways Plan is a bicycle master plan for the City that sets an
ambitious path for facility development, enhanced funding, and increased ridership
over the next 10 years. Additionally, in January 2009, City Council adopted several City
Code revisions that improve cyclist safety and better guide the development of quality
facilities.
Transit
With High Street abutting the western edge of the neighborhood, and its close
proximity to both downtown and Ohio State, Weinland Park is currently one of the
best served areas of the City by transit service. However, available data and public
comments indicate a further need for increased and improved transit service in the
neighborhood.
The Central Ohio Transit Authority (COTA) operates multiple bus routes through and
adjacent to the neighborhood; these include five local routes, two crosstown routes,
and three express routes, as well as Project Mainstream (on-call paratransit service).
Table 9 and Exhibit 12 show the existing transit routes and stops within the study area.
The majority of these routes can be accessed by Weinland Park residents along the
High Street corridor with the exception of the #4 (Fourth and Summit Streets) and #8
(Hamilton Ave) Local Routes, the #96 (Fifth Ave) Crosstown Route, and the #52 (OSU/
Airport) Express Route. Additionally, the OSU Campus Area Bus Service (CABS) East
Residential Route runs along Summit and Fourth Streets in the northern half of the
corridor.
Type
Local
Local
Local
Local
21
31
Express
52
Express
54
Express
84
Crosstown
96
Crosstown
East Residential
Campus
45
46
Recommended Solutions
The recommendations chapter of this plan is divided into two sections, a Toolbox
of Treatments and location based recommendations. The Toolbox of Treatments
describes numerous mobility improvements, grouped by travel mode. These tools
were selected to address the numerous issues and concerns expressed through public
input and observed during the planning process. The Toolbox is intended to serve as
an ongoing resource for use by the City and residents of Weinland Park to diagnose and
address future mobility issues in the neighborhood. Each tool includes a description
of its intended use and effects, pros and cons to consider, and a planning-level cost
estimate (or range of costs) for installation. Actual costs may widely vary based on
whether the improvement is completed at the same time as others to take advantage of
economies of scale.
The Location Based Recommendations section applies the tools from the Toolbox of
Treatments to specific locations throughout the study area. For each location, the
most appropriate tool, or combination of tools, was selected and applied to address
the identified mobility problems. Some of the recommended improvements apply
to the entire neighborhood, some to a roadway corridor, and others to specific sites
or intersections. For each location, there is an explanation of the recommended
improvement(s) and a justification for why that tool was selected.
Toolbox of Treatments
Automobile Tools
Curb Extensions
Curb extensions are improvement measures that are used in locations with on-street
parking to improve pedestrian crossings and help control vehicle speeds by narrowing
the roadway. Also called bump-outs, chokers, or curb bulbs, curb extensions can be
installed at intersections or mid-block to reduce or reinforce lane widths by bringing the
curb line out into the parking lane and closer to the travel lane (Figure 38).
48
When used at intersections, curb extensions improve both pedestrian and driver safety.
Crossing distances are shortened and pedestrians are made more visible to drivers
by moving them out from behind parked cars. Driver safety is improved by slowing
vehicle speeds and by preventing vehicles from parking too close to the intersection,
thus improving sight conditions. At mid-block locations they are most effective at
reinforcing lane widths where on-street parking is allowed but not heavily used, and at
Mini circles are relatively easy and cheap to install as little to no modification to the
existing intersection is required. A landscaped mini-circle generally costs about $6,000.
Maintenance responsibilities for the landscaping can also be taken on by property
owners or a neighborhood association to help defray the costs of the improvement,
particularly when the mini circle serves as a gateway feature into a residential area.
Figure 41: Mini circles can be installed along
with curb extensions to provide maximum
speed control at an intersection.
49
Raised Medians
This traffic calming measure controls vehicle speeds by introducing a raised barrier
in the middle of a street, forcing drivers to the outside. Medians narrow the roadway
(either physically or visually), provide motorists with left-turn pockets out of the flow
of traffic, and serve as a crossing refuge for pedestrians. Adding landscaping and/or
gateway signage to a median also serves as a cue to drivers that they are in a pedestrian
environment where high speeds are not appropriate. Similar to mini circles, medians
can be used in combination with curb extensions to calm traffic along a street corridor.
Landscaping in a median must not obstruct the view of motorists on the road,
particularly from pedestrians using the median as a crossing refuge. On streets without
a center turn lane, on-street parking will likely have to be removed in order to maintain
adequate lane widths; therefore, medians may not be an appropriate treatment on
streets where parking is in high demand.
Raised medians tend to be higher cost measures, costing between $15,000 and $30,000
per 100 feet. Cost can be minimized by installing two small medians with a break
in the middle for a pedestrian refuge (Figure 43). This also ensures that persons
using mobility aids and pushing strollers can easily navigate the crossing. As with
mini circles, landscaping maintenance can be taken on by property owners or a
neighborhood association to help reduce costs.
50
On-Street Parking
The provision of on-street parking presents multiple mobility benefits to motorists as
well as users of other transportation modes. The availability of ample on-street parking
improves convenience for residents and other motorists with destinations in the area,
particularly in many urban neighborhoods where off-street parking is scarce or nonexistent. Additionally, on-street parking helps to control vehicle speeds by creating
some friction along the sides of a road. The presence of cars parked on the street
forces drivers to slow down and raises their peripheral awareness. Finally, on-street
parking creates a vertical barrier between the sidewalk and roadway, which improves
both the safety and comfort of pedestrians. In commercial locations where parking is in
particularly high demand, metered parking can be installed and function as a source of
revenue for the City.
The cost to implement on-street parking in areas where it is restricted is often minimal,
requiring only the removal of parking restriction signs and/or installation of parking
signs. The cost of a new parking sign is approximately $300 installed.
Road Diet
A road diet is a tool that can be used to slow vehicle speeds by narrowing a roadway
corridor either visually, by narrowing travel lanes, or by reducing the number of
travel lanes, generally from four (two lanes in each direction) to three (one lane in each
direction with either a two-way left turn lane or a median). The extra space created by
a road diet is then often dedicated to improving multi-modal travel along the corridor
through the creation of bike lanes, wider sidewalks, on-street parking, or landscaped
buffers. The mobility benefits of road diets can include lower vehicle speeds, improved
safety and comfort for pedestrians and cyclists, shorter crossing distances, and
improved visibility and access to businesses.
Road diets offer benefits for motorists as well as pedestrians and bicyclists. By
eliminating turning movements from the left through travel lane in each direction,
motorist behavior becomes more predictable. Reducing the road to one lane in each
direction also prevents the faster moving vehicles from weaving to pass slower moving
vehicles. A road diet can generally be implemented on roads with average daily traffic
(ADT) volumes of up to 18,000 with little impact to roadway capacity, although ADTs
of over 20,000 can be converted following detailed analysis.
Road diets can quickly and effectively be implemented for very little cost (as little
as $5,000/mile) by simply re-striping the road and altering signal operations. They
can also be completed as long-term projects that include construction of landscaped
medians, curb extensions, new pedestrian scale lighting, and gateway signage. These
longer-term, more complex projects can cost up to $100,000 per mile.
Improved Lane Striping
Restriping a roadway to better define and narrow the lanes is a low cost but effective
solution to improving safety. Narrowing the lanes to 10 or 11 feet can effectively slow
vehicle speeds while providing room for on-street parking and/or bike lanes. When
considering a change in road striping, it is important to consider the lane configuration
at intersections and potential impacts on the level of service of the road, as significant
changes could push unwanted traffic onto local streets. Additionally, the interaction of
bicycles with traffic and parked cars must be considered. Generally, the cost to remove
old lane striping and restripe new lanes is between $5,000 and $10,000 per mile.
51
52
Pedestrian Tools
Sidewalks
Of utmost importance to pedestrian mobility is the presence of a comprehensive, well
maintained sidewalk network that connects neighborhood residents to key destinations
such as shopping and employment centers, entertainment venues, and other
transportation modes such as transit.
The Columbus City Code calls for the provision of sidewalks in all subdivisions and
site developments, and states that the abutting property owner is responsible for the
construction, maintenance, and repair of sidewalk facilities. It also stipulates that the
minimum width for sidewalks is four feet when there is a three foot buffer present and
six feet when the sidewalk is next to the curb. While four feet is the minimum standard,
the Federal Highway Administration (FHWA) and the Institute of Transportation
Engineers (ITE) both recommend a minimum width of five feet to allow two people to
pass or walk side-by-side comfortably, and a buffer of four to six feet.
In locations of heavy pedestrian activity such as schools, neighborhood retail centers,
and parks, wider sidewalks and additional features such as street furniture and bike
racks should be provided to accommodate multiple users and promote a vibrant and
comfortable pedestrian environment. Roads with heavy vehicular traffic volumes and
higher speeds should also have wider sidewalks and buffers between pedestrians and
traffic to ensure safe and comfortable walking.
In developed areas such as Weinland Park, sidewalk construction and repair often
occurs in bits and pieces over time. Key sections in need of repair or replacement
should therefore be identified and addressed first. It is important to provide a smooth
and continuous surface so that the sidewalk network is accessible to all users. This
means extending the sidewalk through driveway aprons and alleys or including
ADA compliant curb ramps. Equally important to the provision of sidewalks is
the maintenance of a clear walking zone, which requires the clearing of debris and
overgrown vegetation. While these maintenance issues are relatively easy to address,
other obstructions such as street furniture, signs, and utility poles present greater
challenges. If it is infeasible to move or remove these obstructions on their own, these
changes should be incorporated into a larger roadway or utility improvement project.
The cost to install a concrete sidewalk is approximately $11 per square foot
53
Crosswalk Markings/Upgrades
Well positioned and well marked crosswalks are important features of a good
pedestrian network. Crosswalks designate crossing locations for pedestrians, and
indicate to motorists the presence of pedestrian activity and the need to yield to
pedestrians crossing the street. Crosswalks should generally be located at intersections
where other traffic control measures are often in place and motorists are more aware
and expectant of pedestrians and vehicles crossing their paths. However, when
crossing at the nearest intersection forces pedestrians to travel out of their way, it
may be necessary to install a mid-block crosswalk. In locations where a significant
number of pedestrians choose to cross a street mid-block rather than walk to the
nearest crosswalk, it likely indicates the need for a crosswalk. Efforts should be made
to create a safe, legal crossing at these locations, if possible, rather than trying to force
pedestrians to use existing but inconvenient facilities.
54
Heavy pedestrian traffic areas often require high visibility crosswalks to alert drivers to
increased pedestrian activity. These crosswalks are particularly important near schools
where large numbers of children cross the street during school arrival and dismissal.
High visibility crosswalks can be installed using various striping patterns, colored
pavement, and/or textured paving materials (Figures 48 and 49). The effectiveness of
high visibility crosswalk markings is contingent on them catching a drivers attention.
For this reason, they should only be installed at a few key crossing locations so that
they remain distinctive. The materials and design of high visibility crosswalks must
also be carefully considered. Some striping and paving materials such as thermoplastic,
stamped/colored asphalt, and cobblestone can become slippery when wet. Ladderstyle striping should be designed such that vehicle wheels pass between the stripes to
maximize the durability of the striping. Both standard and high visibility crosswalks
should be accompanied by some other form of traffic control, traffic calming, and/or
signage in order to provide a benefit to pedestrian safety (Safety Effects of Marked Versus
Unmarked Crosswalks at Uncontrolled Locations. 2005. FHWA. Publication Number: HRT04-100).
The cost to install standard crosswalk markings is approximately $400 per intersection,
while the cost to install high visibility crosswalks can range from $1,200 per intersection
for ladder-style crosswalk markings to $80,000 per intersection for textured pavement.
55
pedestrians in the crosswalk. Finally, the flashing red light returns to dark, allowing
traffic to proceed, while pedestrians see a solid dont walk sign and must activate the
beacon to cross.
HAWK beacons create less vehicular traffic delay than a standard signal, and have been
shown to improve pedestrian safety and motorist compliance (Improving Pedestrian
Safety at Unsignalized Crossings. 2006. Transportation Research Board. TCRP Report 112/
NCHRP Report 562). This treatment was included for the first time in the 2009 Edition
of the Manual of Uniform Traffic Control Devices (MUTCD). As of late 2009, this device
has yet to be added to the Ohio Manual of Uniform Traffic Control Devices (OMUTCD)
and may require provisional approval before the device can be installed in Weinland
Park.
The cost to construct a HAWK beacon on a one-way road is approximately $50,000; the
cost for a two-way road is approximately $75,000. A warrant analysis will be necessary
before proceeding with an installation. If the standard is not met, a pedestrian-activated
LED rectangular rapid flashing beacon may substitute for each HAWK beacon.
Figure 52: Diagram of a HAWK beacon cycle.
56
Bicycle Tools
Bike Lanes
A bike lane is a striped or otherwise separated travel lane for the exclusive or semiexclusive use of bicycles. They are most commonly found on major collectors and
arterial streets where vehicle speeds and volumes warrant separation of the two modes.
In addition to providing a designated space for cyclists on the road, bike lanes help to
control vehicles speed by narrowing the roadway and improve pedestrian safety and
comfort by creating a buffer between the sidewalk and vehicle travel lanes. When
installing bike lanes, it is critical to provide adequate room from on-street parking to
prevent dooring issues. The merging of right-turning vehicles and cyclists in a bike
lane is also an important consideration, particularly when an intersection includes
a dedicated right turn lane. One issue that should be addressed through education
rather than design is the perception that cyclists are required to use a bike lane if one
is provided. This misconception often leads to driver frustration and safety concerns
when a cyclist is seen using other travel lanes.
The cost to re-stripe an existing roadway with bike lanes is approximately $5,000 per
mile for the pavement markings. Upgrades such as new signage, colored pavement,
and signal alterations will all increase the cost of installation.
Shared Lane Markings (Sharrows)
The sharrow is a relatively new type of pavement marking that indicates the
recommended location for cyclists to ride in a shared travel lane. It also serves as a
reminder to motorists to be attentive to bicycles using the road. Sharrow markings
consist of two chevrons above a bicyclist symbol and are most often placed on the righthand side of wide outside lanes (14+ feet wide).
Although not yet officially approved for general use by FHWA (will be included in
the next update to the MUTCD), sharrows have been widely tested and well received.
They are most effective in locations where dooring is a problem and where aggressive
motorist behavior squeezes cyclists to the outside edge of the road.
The cost to place sharrows along a mile of road is approximately $5,000 (assumes
markings every 100 feet at $100 per marking).
57
Bike Boulevard
A bicycle boulevard is a public street on which bicycles are given priority over other
modes of travel. Cut-through vehicular traffic is often prohibited by allowing through
movements only to cyclists. This can be accomplished through signage, pavement
markings, traffic calming measures, signalization or more commonly some combination
of these. Bike boulevards can be implemented on low volume roads to connect gaps
in a bicycle route or to provide a safe alternative parallel to an arterial roadway that is
not conducive to bicycle travel. Some of the most common tools used to create a bike
boulevard include: pavement marking and signs identifying the facility, mini-circles
and curb extensions to calm traffic, and diverters and medians which force vehicles to
turn while allowing the through movement by cyclists.
Careful consideration must be given to the location and design of bike boulevards,
because they often involve limiting vehicular movements along a road, creating
potential access problems for residents and businesses. Adequate directional and
identification signage alerting cyclists to the bike boulevard is also important since they
are often on smaller, less obvious streets.
58
There can be a wide range of costs associated with the construction of a bike boulevard.
If only signage and pavement markings are used, the cost can be very similar to that of
bike lanes or sharrows at approximately $5,000 per mile. As traffic calming measures
and signalization elements are added the cost can elevate quickly to well over $100,000.
Bike Parking
As with the motorized transportation network, a complete bicycle network must
include adequate and convenient parking for its users once they reach their
destinations. Bike racks should be readily visible and accessible at key destinations
such as retail locations, places of employment, and entertainment destinations. Onstreet bicycle parking should also be provided within the right-of-way along major
transportation corridors. Bike lockers should also be made available in certain locations
where longer-term, more secure parking is required.
Nearly as important as the provision of bicycle parking is the type and location of the
parking facilities. Bike racks that support the frame of a bike (preferably two points
of contact), such as the U-style and serpentine racks, are preferable to traditional fence
style racks, which only support the wheel and are more likely to damage bikes attached
to them. Bike racks/lockers should be installed on a paved surface and be located near
building entrances, transit stops, and other high traffic, highly visible areas. Installing
bike parking behind buildings, in poorly lit areas, or otherwise out of sight not only
makes them less convenient to find and use, but it also makes them less secure due to a
lack of surveillance.
The cost to install bike racks can range greatly based on style and materials. Bike racks
generally cost between $75 and $150 per bike to install; bike lockers cost between $500
and $2,000 per bike to install, but are usually paid for through rental fees.
Transit Tools
Increased Frequency and Span of Service
Increasing the frequency and/or extending the hours of service on existing bus routes
can be a low cost way to improve mobility options for area residents for whom transit
is not currently convenient or feasible. An increase in the frequency of buses along a
route reduces the potential wait time for riders by increasing the likelihood that a bus
will come when the rider needs it. This improved convenience can play an important
role in the decision making process of potential riders, particularly if it means getting to
work on time or if the travel time becomes comparable to driving and parking.
Extending the hours of service of an existing route can be an even more important factor
in making transit a viable transportation option. Reliable transit service during off-peak
hours is especially important to individuals who work evening and nighttime jobs.
Many people can currently take the bus to work, but service does not run late enough
for them to make the return trip home. Along with serving people who work evening
and night shifts, late night/early morning transit service also provides people with an
alternative to driving to entertainment venues.
There may be no cost associated with increasing the frequency of service on a route
if the number of stops can be condensed by eliminating those that are under-utilized.
However, if no stops can be eliminated it may be necessary to add an additional bus to
the route, of which may cost around $250,000 per year.
Upgraded Bus Stops
The comfort, safety, and accessibility of the stops along a bus route can have a
significant impact on how individuals perceive, and whether or not they use public
transit. Because every transit rider begins and ends their trip as a pedestrian, the
59
presence of good pedestrian facilities around a bus stop is important. Easy access to bus
stops for disabled and elderly users is of particular importance because these groups are
often more reliant on transit service than other members of the community.
In addition to good pedestrian facilities adjacent to a bus stop, there are also several
other amenities that can improve the comfort and safety of users while waiting for the
bus. The provision of benches and shelters improves comfort, especially for elderly and
disabled users, while waiting for the bus. Route maps and schedules provide important
wayfinding information to non-regular users of the system. Good lighting increases
visibility at the stop, thus improving safety and comfort while waiting at night. Finally,
trash receptacles help to keep the stop and surrounding area free of trash and debris,
which improves the aesthetic character of the stop and the comfort of users.
Figure 60: COTAs new standards for bus stop
design provide riders with key amenities such
as shelters, benches, trash recepticles, and maps.
60
In 2004, COTA developed new standards for bus stop design, location, and amenities
(see Figure 60, and in this Plans appendix). These include new typical sections and
plans, as well as an updated shelter design and route mapping. According to COTA
policy, a new shelter can be installed at a stop if a daily average of at least 25 riders
board at that location, while benches, trash receptacles, and signage can be installed
by special request. When considering the installation of a new bus shelter or bench,
it is important to ensure that there is enough space to maintain adequate pedestrian
facilities. In areas with limited right-of-way, this may mean that an easement needs to
be acquired that allows the bus stop facilities to be placed outside of the right-of-way.
Neighborhood Circulator (LINK) Route
A neighborhood circulator is a bus route that serves a small area with frequent service.
The purpose of a circulator route is to connect residents of the neighborhood to larger
regional transit routes, such as High Street and Eleventh Avenue in Weinland Park,
and key local destinations, such as grocery stores, community facilities, and/or large
employment centers. COTA currently runs one circulator route, called a LINK, in the
Linden neighborhood. The vehicle used for the LINK route is smaller (30 feet long)
than a normal bus (40 feet) and is much quieter, allowing it to primarily run on collector
and residential streets. The Linden LINK operates on a 30 minute loop through the
neighborhood, which is designed to maximize convenience and access. The cost to ride
the LINK is $0.50. Opperating costs for a LINK route in Weinland Park may range from
between $300,000 and $500,000 per year.
Other Tools
Gateway Features
Whether on a grand scale, such as a signature development or roundabout, or on a
smaller scale, such as landscaping or distinct signage, gateways serve many important
purposes for a community. Most importantly, they create a focal point that reinforces
the unique identity of a neighborhood and can foster a sense of pride and belonging
among residents.
Gateway features also serve as physical and psychological cues to motorists that htey
are entering a different type of driving environment, one in which pedestrians and
slower speeds should be expected. In order to ensure their effectiveness as a traffic
calming measure, gateways should be combined with other tools such as medians, curb
extensions, or roadway narrowing.
Wayfinding Signage
Similar to motorists following street signs, pedestrians and cyclists rely on visual cues
to orient themselves and navigate their surroundings. For this reason, wayfinding and
destination signage are important components of a multi-modal environment. The
scale, appearance, placement, and visibility of signage should be consistent and easily
understood by both local and visiting travelers. Wayfinding signage also benefits area
businesses by making them more visible and easily accessible to potential customers.
The cost of wayfinding map kiosks like those in downtown Columbus (Figure 62) is
approximately $5,000-$6,000 installed, while the cost of destination signs like those
downtown (Figure 63) is approximately $1,000 installed.
61
Streetscape Improvements
The presence of landscaping and street furniture (benches, trash receptacles, bus
stops, etc.) along a road can improve safety for all users while greatly enhancing the
pedestrian environment and aesthetics of a corridor. A street that is lined with trees
and other landscaping appears narrower to motorists than the same street without
any vegetation. This induces slower vehicle speeds and helps differentiate the
vehicular and pedestrian environments. More concretely, street trees and other vertical
treatments such as benches and planters provide a physical barrier between vehicles
and pedestrians, which reduces the potential for conflicts between the two modes.
A welcoming pedestrian environment should include benches and other furniture that
improves comfort and encourages interaction and activity on the street. These features,
along with aesthetic landscape enhancements have positive benefits for adjacent
properties as well, adding vibrancy to commercial and residential areas. Landscaping
can also reduce the environmental impacts of a road corridor by capturing and treating
stormwater on-site rather than allowing it to flow directly into the sewer.
In urban areas, where right-of-way is often tight, it can be difficult to identify adequate
space for streetscape improvements. Street furniture and landscaping should not be
installed at the expense of the clear walking zone; however, in many locations this
can be overcome by combining them with other improvements such as medians,
mini-circles, and curb extensions. Continued maintenance cost is another issue that
must be considered in the planning and budgeting of improvements. The cost of
streetscape improvements can range from as little at $1,000 to over $10,000 depending
on the planting materials and use of street furniture. As suggested with previous
tools, some of the maintenance costs can be offset by having residents take-on upkeep
responsibilities for the landscaping.
62
Neighborhood Improvements
Sidewalk maintenance and replacement program (1)
Given the number of resident concerns related to poor sidewalk conditions, the extensive
need for improvements identified during the sidewalk inventory, and the importance of
creating a safe and continuous network, sidewalk improvements should be addressed
at a neighborhood scale. In Columbus, installation and maintenance of sidewalks is the
responsibility of the adjacent property owner. In Weinland Park, this has resulted in
inconsistent sidewalk conditions, with some owners performing necessary maintenance
and others allowing the sidewalk to fall into disrepair.
In order to achieve a consistently high quality sidewalk network it is recommended that
an assessment program be instituted throughout the neighborhood. Upon agreement
by a certain percentage of property owners in the neighborhood (generally 60%) an
assessment would be applied to each property. The funds generated by the assessment
would then be used to pay for sidewalk improvements using the Citys existing
contracts to reduce costs. The sidewalk inventory completed for this plan should be
used to prioritize the improvements, with those sections rated F (impassible or complete
disrepair) being completed first. The key benefit of a neighborhood-wide assessment
program is that the cost of sidewalk improvements is spread among all property owners.
This reduces the impacts on any given resident, and, over several years, will result in
improved sidewalk conditions throughout the entire neighborhood, which benefits all
residents.
As an alternative to developing a neighborhood assessment program, the Weinland
Park Community Civic Association could begin a systematic code enforcement
initiative to improve sidewalks. Specific streets could be selected by the community
for code enforcement efforts by the City as a way to spur property owners to repair
63
their sidewalks. A certain percentage of residents on the street should agree to the
enforcement efforts to ensure it is supported. Existing City contracts could be used to
repair sidewalks along selected streets using this approach as well.
Bicycle Parking (2)
Convenient and secure bicycle parking is needed throughout Weinland Park. Numerous
comments highlighted the lack of bike parking, particularly at major destinations, in the
neighborhood. Bike racks should be installed in highly visible locations, preferably near
the main entrance of the following facilities/businesses:
COTA stop at Fifth Avenue and High Street
Third Hand Bike Co-op Fifth Avenue between Summit and Fourth Streets
Godman Guild corner of Sixth Avenue and Sixth Street
Weinland Park between Fourth and Summit Streets
Weinland Park Elementary corner of Seventh Avenue and Fourth Street
Schoenbaum Family Center corner of Seventh Avenue and Summit Street
Kroger southeast corner of Seventh Avenue and High Street
Dollar Tree plaza northeast corner of Seventh Avenue and High Street
Indianola Park Indianola Avenue between Eighth and Ninth Avenues
Directions for Youth and Families corner of Ninth and Indianola Avenues
Kellys Carry-Out corner of Eleventh Avenue and Fourth Street
The City of Columbus currently installs bike racks within the public right-of-way upon
request using its 311 Call Center. Residents or business owners can simply place a
request and, as long as adequate right-of-way exists, a rack will be installed. This service
can be used to install racks at some of the above listed locations, as well as other high
demand locations in the neighborhood.
64
The University Area Commission has been working on a project to develop gateway
signage for the entire district for several years. Gateway features at these locations for
Weinland Park are consistent with those efforts, and could be completed as a part of that
project. Arches would be ideal gateway features for the neighborhood as they would
provide continuity with other gateway signs installed in adjacent neighborhoods and
would maintain a link to the history of th area.
Wayfinding/Destination Signage (4)
The presence of wayfinding signage throughout Weinland Park will help guide
pedestrians, cyclists, and motorists alike to key destinations in and around the area.
A wayfinding system should be developed for the entire University Area to provide
continuity for users and to ensure the inclusion of all important businesses and attractions
in the area. Examples of some destinations in Weinland Park could include the South
Campus Gateway, Weinland Park, Indianola Park, and the Godman Guild, along with
any other businesses and/or facilities identified by the community.
Neighborhood Circulator (LINK) Route (5)
A COTA LINK route through Weinland Park would add transit connections from the
residential areas of the neighborhood to nearby retail, employment, and community
destinations. Additionally, the circulator would connect residents to larger transit routes,
thus improving access to other areas of the City. A potential route for the circulator is
shown in Exhibit 13.
Corridor Improvements
65
66
The Bicentennial Bikeways Plan calls for the installation of bike lanes on Fifth Avenue, a
need that was also raised during the public input stage of the project. Implementation of
the road diet on Fifth Avenue may result in the space necessary to install a five-foot bike
lane in each direction. The bike lane will not only provide cyclists with dedicated space
on the road, but will also help to control vehicle speeds and provide a buffer between
vehicular traffic and pedestrians on the sidewalk.
Sidewalk Installation on Sixth Avenue (7)
Installing new sidewalk along Sixth Avenue from Indianola Avenue to Summit Street and
from Fifth Street to Sixth Street will complete the sidewalk network in Weinland Park.
These improvements will make connections to key pedestrian destinations including
Weinland Park and Godman Guild from the residential areas of the neighborhood.
Sharrows on Eleventh Avenue (8)
The addition of sharrows along Eleventh Avenue between High Street and Grant Avenue
will create an east-west bike route on the north side of Weinland Park. This improvement
is recommended in the Bicentennial Bikeways Plan and was expressed as a need in public
comments.
Shared Signed Roadway on High Street (9)
The bike safety improvements along High Street coincide with the recommendations of
the Bicentennial Bikeways Plan, which include the installation of sharrows, Share the
Road signage, and a public education campaign. Given the high volume of vehicles and
cyclists, this is a high priority project for the City and some of these improvements are
already in place.
Bicycle Boulevard on Pearl Street and Courtland Avenue (10)
The conversion of Pearl Street and Courtland Avenue to a bike boulevard from Fifth
Avenue to Twelfth Avenue would provide cyclists with an alternative route to High,
Summit, and Fourth Streets, all of which are high volume and higher speed streets. The
Bicentennial Bikeways Plan calls for a bike boulevard on Pearl Street; however, it would
only extend as far south as Seventh Avenue. Continuing the facility south to Fifth
Avenue on Courtland Avenue will connect the bike boulevard with the bike lanes to be
installed on Fifth Avenue, thus creating a more continuous network. It also allows for the
extension of the bike boulevard further south into the short north along Pearl Street.
67
Street
Existing
Excessive Speed
Posted Speed
11th
7th
5th
0
60
120
180
Time (sec)
Street
Proposed
Excessive Speed
Posted Speed
11th
7th
5th
0
60
120
Time (sec)
68
180
Efforts to plan for how to improve the corridor were complicated by several transit initiatives, specifically plans to build a regional light rail transit line or streetcar on either
Fourth and Summit or High Street. Though these initiatives would provide significant
mobility enhancements to the Weinland Park neighborhood, both proposals had the potential to significantly affect Fourth and Summit streets by changing traffic volumes and/
or adding transit vehicles to the corridor. Both possibilities made it particularly difficult
for project planners to establish reasonable future vehicular volumes.
Both transit proposals have since stalled out and this now permits project planners and
engineers to make reasonable assumptions about the future of the Fourth and Summit
streets corridor. Of those reasonable assumptions, project planners and engineers need
to determine if projected traffic volumes would be accommodated within certain levels
of service within 20 years given any changes made to the corridor. These traffic capacity
analyses are currently under study and will impact what improvements are able to be
made. A preliminary engineering analysis will determine which improvements to include and which may not be possible at this time.
Providing guidance, this plan recommends the following improvements for Fourth and
Summit streets:
Improved signal timing (11)
This improvement will help to address the speeding issue on Summit and Fourth
Streets, thereby improving safety as well. The timing of traffic signals throughout
the corridor will be altered to encourage vehicles to travel at or below the posted
speed limit rather than rewarding motorists for traveling above it. This will be
accomplished by reducing the green band of the signals so that vehicles traveling above the speed limit will be stopped at red lights while vehicles traveling at or
below the speed limit will receive green lights (see Figures 64 and 65). Altering the
signal timing will also improve connectivity across Summit and Fourth Streets by
decreasing the amount of time a pedestrian has to wait to cross them at a signalized
intersection. Future changes to signal timing must be compatible with any and all
other recommended projects for the Fourth and Summit corridor.
curb extensions should be placed at signalized and unsignalized intersections to shorten crossing distances, improve
pedestrian (and driver) visibility, and better manage the duration of pedestrian signal walk phases at signals. Figures 66
and 67 show the existing and recommended typical sections
for Summit and Fourth Streets.
Existing
Figure 66: The existing lane striping on Summit and 4th St is poorly defined and
provides overly travel lanes, which can lead to higher intances of speeding and
crashes
Proposed
Though peak-hour level of service may experience an acceptable reduction at some intersections, the conversion of the
typical section from three to two appropriately sized travel
Figure 67: The proposed lane striping will better define the travel lanes, provide room
for a bicycle lane, and increase permanent on-street parking, all within the existing right- lanes will improve the multi-modal level of service and, more
importantly, is a critical need to address a present and pressof-way.
ing safety problem affecting all users of the corridor. The reduction in the number of lanes
will better control vehicular speeds, a significant hazard for pedestrians and bicyclists.
Other safety benefits include a reduction in instances side-swipe crashes, a reduction of the
risk of multiple threat pedestrian (or vehicular) crashes at unsignalized intersections, the
accommodation of a needed bike lane, and a reduction of the number of locations where a
travel lane ends at the bumper of a parked vehicle.
70
Though the plan provides recommendations that continue maintaining Fourth and Summit
Streets as a one-way pair, the intent of this plan is not to suggest that one-way operation is
preferable to two-way operation in the long-term. Conversion of the corridor to two-way
operation would be a more permanent solutionone that would require substantial alterations to both streets, greatly affecting corridor traffic patterns. Solutions provided in this
plan are intermediate steps that are comparatively easier to implement, generally signal
timing, signing and striping, and minor hardscape improvements (curb extensions).
71
72
speeds and volumes on Summit and Fourth Streets, and the presence of substantial
pedestrian destinations, the beacons were identified as an appropriate measure. There
use would be on an experimental basis until the MUTCD-approved beacons are included
in the Ohio-MUTCD. Should warrants for the beacons not be met, highly visible
pedestrian-activated LED Rectangular Rapid Flashing Beacon may substitute. These
beacons should be located on curb extensions to be more visible to drivers, and include
signage indicating motorists should yield to pedestrians in the crosswalk.
Intersection Safety Improvements at Summit Street/Seventh Avenue (18)
This intersection was the most frequently noted problem location by residents, is the site
of several pedestrian crashes, and is heavily used by children walking to school and the
park. Problems at the intersection are linked to several factors notably that the intersection
is off-set and there is a desire for users to cross through the middle of the offset
intersection when walking toward High Street (Kroger). Whereas an exclusive pedestrian
phase was studied and discussed during public involvement, preliminary traffic analysis
indicates this method would result in excessive delay on Summit Street during the AM
peak, resulting in queues for motorists and transit users starting north of 8th Avenue.
Continued study is necessary to develop a package of improvements that will eliminate
or at least reduce potential conflicts between pedestrians and vehicles. This Plan
recommends such improvements reduce the width (i.e. curb extensions) and length
(e.g. consolidate to one of the two T intersections) size of the intersection, permit
the placement of a crosswalk between the southwest and northeast corners of the
current intersection, and include a leading pedestrian phase to improve the visibility
of pedestrians). These improvements should coincide with a pedestrian education
effort primarily targeted toward students at Weinland Park Elementary School. Such a
program could be incorporated into a Safe Routes to School program.
Crosswalk, Improved Pedestrian Signage, and Pedestrian Refuge on High Street (21, 54)
Through resident input, the need for a new marked pedestrian crossing of High Street at
Euclid Avenue (21) was identified to improve safe access to the library on the west side
of High Street. Similarly, a refuge island is recommended for an existing crosswalk at the
intersection of E 6th Avenue and High Street, just south of Kroger (54).
The provision of a refuge island with ladder style crosswalk markings and high visibility
signage at these locations (south leg of the intersection of Euclid Avenue and High Street,
and the south leg of the intersection of E 6th Avenue and High Street) is recommended to
73
74
provide safer pedestrian crossings across High Street, and improve access to community
amenities such as the library and other retail establishments in the area.
Raised Median on Eighth Avenue at Pearl Street (22)
The installation of a raised median at this location will aid in the creation of a bike
boulevard along Pearl Street by managing access. The intersection will become a
right-in/right-out for vehicles, while a small break in the median will allow cyclists to
make left turns and through movements on Pearl Street as well. This will reinforce the
priority of cyclists on Pearl Street and encourage vehicles to use High Street.
Curb Extensions
These measures are recommended for numerous intersections throughout Weinland
Park as a means of improving walkability by reducing pedestrian crossing distances.
The curb extensions may provide some vehicular speed reduction on long straight
stretches of road, particularly when used in conjunction with other tools. Preliminary
analysis of vehicle turning movements indicates that buses and fire trucks can navigate
these devices even on the local streets in Weinland Park. However, the final dimensions
for these improvements will need to be developed for each location individually during
detailed design. Curb extensions are recommended at the following locations:
Seventh Avenue east of High Street (23) North side of Seventh Avenue from
High Street to Pearl Street. This will better align the Seventh Avenue/High
Street intersection and help control vehicle speeds. The lanes on Seventh Avenue
will shift slightly to better align with King Avenue to the west of High Street. It
will also shorten the crossing distance for pedestrians and help control the speed
of westbound traffic on Seventh Avenue. Speeding at this location was raised as
a concern in public comments and verified with speed and volume counts.
Euclid Avenue east of High Street (24) Both sides of Euclid Avenue for
approximately 300 feet. This section of road is overly wide for a local street (38
feet), which encourages cut-through traffic and speeding. The curb extensions
will narrow the west end of Euclid to match the width along the rest of the street
(26 feet), creating a uniform width that is appropriate for a residential street.
Ninth Avenue east of High Street (25) South side of Ninth Avenue for
approximately 330 feet. This will narrow the eastbound travel lane on Ninth
Avenue, which is currently 16 feet wide.
Courtland Avenue at Sixth Avenue (26) This split intersection is approximately
halfway between Fifth and Seventh Avenues. It is a good location for curb
extensions as a way to break-up the long straight stretch that otherwise has no
traffic controls for vehicles on Courtland. The offset alignment will create a
75
76
chicane effect that will effectively control speeds. Curb extensions here will also
help to emphasize Courtland Avenue as a bike boulevard.
Courtland Avenue at Seventh Avenue (27) Along the north side of Seventh
Avenue at this intersection. This will help shorten crossing distances and
improve sight distance for pedestrians walking to Kroger. The curb extension
should prevent parking in the crosswalk.
Pearl Street at Eleventh Avenue (28) All but the northwest corner (which is
required for a right turn lane) of this split intersection. They will control vehicle
speeds and improve walkability along Eleventh Avenue and help to reinforce
Pearl Street as a bicycle boulevard.
Pearl Street at Chittenden Avenue (29) The eastern two corners of the
intersection. Provides vehicular speed control and continues bicycle boulevard
on Pearl Street.
Pearl Street at Twelfth Avenue (30) The eastern two corners of the intersection.
Provides vehicular speed control and enforces bicycle boulevard on Pearl Street.
Indianola Avenue at Fifth Avenue (31) Will help to define the transition from
Fifth Avenue, a minor arterial street, to Indianola Avenue, which is residential in
nature. They should only be located on the Indianola Avenue side of the corners
to avoid conflicts with the new bike lanes, which are recommended as a part of
the Fifth Avenue road diet.
Indianola Avenue at Seventh Avenue (32)
Indianola Avenue at Euclid Avenue (33) The two western corners of the
intersection. This will continue traffic calming along both streets and discourage
cut-though traffic on Euclid Avenue.
Indianola Avenue at Ninth Avenue (34) - The addition of curb bulbs in
combination with a raised median will provide enforced vehicle path deflection
and controlled speeds through this intersection.
Indianola Avenue at Chittenden Avenue (35)
Indianola Avenue at Twelfth Avenue (36)
Hamlet Street at Seventh Avenue (37) Two northern corners of the intersection.
Provides speed control and shortens the crossing distance at the entrance to
Weinland Park Elementary School and the Schoenbaum Center.
Hamlet Street at Eighth Avenue (38)
Hamlet Street at Eleventh Avenue (39)
Fifth Street at Fifth Avenue (40) Helps to define the transition from Fifth
Avenue, a minor arterial street, to Fifth Street, a residential street. They should
only be located on the Fifth Street side of the corners to avoid conflicts with the
new bike lanes, which are recommended as a part of the Fifth Avenue road diet.
Fifth Street at Sixth Avenue (41)
Fifth Street at Eighth Avenue (42)
Fifth Street at Eleventh Avenue (43)
Sixth Street at Seventh Avenue (44)
Sixth Street at Ninth Avenue (45)
Sixth Street at Eleventh Avenue (46)
Indianola Avenue at Eleventh Avenue (49) Public comments and traffic counts
identified speeding along Indianola Avenue.
Mini Circles
These traffic calming measures are recommended for numerous intersections
throughout Weinland Park as a means of controlling vehicle speeds and improving
intersection safety. They are most effective when alternated with curb extensions
in order to break-up long straight stretches of road. As with the curb extensions,
preliminary analysis indicates that these tools can be navigated by buses and emergency
vehicles in the neighborhood, but the final dimensions will be set during detailed
design. Mini circles are recommended at the following locations:
Indianola Avenue at Sixth Avenue (47) Public comments and traffic counts
identified speeding along Indianola Avenue. Will work in conjunction with curb
extensions to calm traffic along the corridor.
Indianola Avenue at Eighth Avenue (48) Public comments and traffic counts
identified speeding along Indianola Avenue. Will work in conjunction with
curb extensions to calm traffic along the corridor. Consultation with the fire
department must occur during design to ensure that access is not impeded.
Hamlet Street at Ninth Avenue (50)
Fifth Street at Seventh Avenue (51) Addresses comments received regarding
speeding at this intersection.
Fifth Street at Ninth Avenue (52)
Sixth Street at Eighth Avenue (53)
77
78
79
80
81
82
Prioritization and
Implementation
Possibly the most important part of any plan is the prioritization of recommendations
and development of an implementation strategy. Without these key elements, it is
unlikely that the improvements called for in the plan will ever come to fruition. During
this final stage of the planning process, members of the project team and City staff
worked closely with the Steering Committee, consisting of Weinland Park residents
and stakeholders, to identify which mobility improvements are the most critical to the
community and how to best implement those solutions over the coming years.
This stage also represents a transition of roles in the planning process. Up to this
point, the City and the project team have guided the planning process through the
identification and analysis of issues and the development of recommendations.
From this point forward, the community is responsible for working with the City to
implement the plan according to the strategy set forth in this chapter.
Plan Prioritization
As with the identification of critical mobility concerns and locations, the community
was called upon to prioritize the recommended improvements. The first step in
this process was to gain preliminary input from the entire community regarding the
recommendations called for by the project team. As previously mentioned in the
Issues and Concerns chapter, a community open house meeting was held in June 2009
at which the draft recommendations were presented and attendees were given the
opportunity to identify those which they felt should be given the highest priority, as
well as those that they felt should be given the lowest priority. Several blank spaces
also allowed residents to write-in improvements that they felt should be included.
Those improvements that garnered the most positive and negative support at the open
house are shown in Table 10. Of those solutions, one that was written-in (converison of
Summit and Fourth Streets to two-way operation) and two that were recommended by
the team (curb extensions on Summit and Fourth Streets at Fifth Avenue) were deemed
infeasible due to the need to consider light rail accommodation in the future. However,
they are still shown in this table to reflect the level of support each gained.
84
Table 10: Initial prioritization of improvements from June 2009 open house meeting
Recommendation
Rec #s
Exclusive Pedestrian Signal*
18
Improved Signal Timing
11
Bike Lanes
12
Gateway Feature
3
Road Diet
6
Conversion to two-way
-Curb extensions
-Bicycle parking
2
Curb extensions
-HAWK signal
17
Shared signed roadway
9
Textured pavement crosswalk
13
Mini circle
49
Location
Positive Votes Negative Votes
Seventh Ave/Summit St intersection
8
0
Summit and Fourth St - Warren St to Hudson St
8
0
Summit and Fourth St - Warren St to Hudson St
7
0
Fifth Ave at Fourth St
5
0
Fifth Ave - High St to railroad tracks
5
0
Summit and Fourth St - Warren St to Hudson St
4
2
Fifth Ave/Summit St intersection
3
0
Third Hand Bike Co-op
3
0
Fifth Ave/Fourth St intersection
3
0
Summit St at south park path
3
0
High St - Fifth Ave to Twelfth Ave
3
0
Fifth Ave/High St intersection
0
1
Indianola Ave at Eleventh Ave
0
1
Using this initial input from the community open house, the Steering Committee
worked to further refine and prioritize the recommended improvements. Prior to the
first Steering Committee meeting, held in February 2010, the group reviewed the draft
plan and recommendations. At the meeting, the Steering Committee went through a
two-step prioritization exercise to rank all of the recommendations in the plan.
For the first step, the individual recommendations were combined into 16 groups by
like projects, and the Steering Committee ranked the groups (Table 11). This provided
the team with general guidance on which types of projects were of most importance to
the community. For the second step, the Steering Committee considered each individual
project and assigned a priority level of high, medium, or low. High priority projects are
those that should be implemented within the next three years, medium priority projects
within three to seven years, and low priority projects in greater than seven years. When
assigning the priority levels, members were asked to consider the benefits of the project,
the estimated cost, the complexity of design and implementation, and logical grouping
with other projects. The resulting prioritization of groups and individual projects was
used by the City to develop the plan implementation strategy.
*The Exclusive Pedestrian Phase was determined by preliminary traffic analysis to be unfeasible. See recommendation Intersection Safety Improvements (18) for alternative approaches and more information.
Group Name
Sidewalk Improvements
High St - Crossings
Bicycle Parking
10
11
12
Gateway Features
13
14
Wayfinding/Destination Signage
15
16
85
Implementation Strategy
In sum, the Weinland Park Community Mobility Plan includes 54 separate recommendations with a construction cost of approximately $2.5-$3 million. As with any plan,
implementation of these projects will occur over a period of several years as funding and other resources can be obtained. Because mobility improvements throughout
Weinland Park will occur incrementally, it is critical to establish a plan for implementation that will guide these efforts and consistently improve conditions throughout the
community.
86
Tables 12-14 group the projects into short-term (0-3 years), medium-term (4-7 years),
and long-term (7+ years) recommendations for development. These groupings were
based on the following evaluation criteria:
Project location - In identifying timeframes for project implementation, projects
that address safety or other mobility concerns at key locations were given top
priority. Projects along a corridor, particularly those aimed at calming traffic
speeds, were also clustered together to maximize effectiveness. Additionally, an
attempt was made to evenly spread improvements throughout the community
while also considering other evaluation factors.
Steering Committee input - The group ranking and the individual project priority assigned by the Steering Committee were considered in tandem. Those
projects that were individually ranked as high priority and that were are a part
of a highly ranked group were given the greatest preference. However, a project
with a high group ranking but that was individually designated as low priority
may be recommended for construction after a project from a lower ranked group
that was individually identified as a high priority.
Effectiveness at achieving the plan goals - Each project was evaluated for its
ability to achieve the goals of the plan. Projects that will result in progress toward several goals and benefit multiple transportation modes were considered
highly effective, those that improve only one or two goals or benefit only one
mode of transportation were listed as medium, and those that work toward only
one goal and benefit only one mode were listed as low having low effectiveness.
Estimated cost and availability of funding from various sources - The design
and construction cost of improvements, along with potential funding sources
were important factors in determining the implementation strategy. Numerous funding sources were identified to expedite the implementation of projects.
Those projects that rely on different funding sources could be recommended
simultaneously, while those reliant on the same source were dispersed over time
Project
Number
Recommended
Improvement
Location
Steering
Committee Input
Group Project
Rank
Priority
Effectiveness
Cost
Potential Funding
Sources
CIP, OSU, Private,
SRTS
Responsible
Party
DOMO, RPD,
OSU, Private
Bicycle Parking
Various Locations
High
Low
$22,000
Sidewalk Installation
High
High
Shared Signed
Roadway
16
Low
Medium
11
Improved Signal
Timing
High
High
City Staff
Time
12
High
High
$310,000^ Safety
16
HAWK Beacon#+
High
Medium
DOMO, ODOT
17
HAWK
Beacon#+
High
Medium
DOMO, ODOT
18
Exclusive Pedestrian
Signal Phase*, **
High
High
$35,000 Safety
DOMO,
DOPO, ODOT
19
n/a ^^
Medium
$25,000 Safety
DOMO, ODOT
20
n/a ^^
Medium
$25,000 Safety
DOMO, ODOT
$2,000 CIP
CIP
# A warrant analysis has not been conducted to determine whether HAWK Beacons are warranted. If the standard is not met, pedestrian-activated
LED rectangular rapid flashing beacons may substitute.
* The Exclusive Pedestrian Phase was determined by preliminary traffic analysis to not be feasible. See recommendation Intersection Safety Improvements (18) for alternative approaches and more information.
** These projects will require additional study and may likely cost more than their estimates based on information discussed in their respective project
descriptions (pages 63-77).
^ Project costs may be significantly less if implemented as a part of a repaving project.
^^ These projects were not included in prioritization activities.
+ Per city policy, a pedestrian volume threshold must be met to justify marking a crosswalk.
DOMO
DOMO
DOMO,
DOPO, ODOT
DOMO, ODOT
87
Steering
Committee Input
Group Project
Rank
Priority
Project
Number
Recommended
Improvement
23
Medium
High
DOMO
27
Curb Extension
Low
Medium
DOMO
31
Curb Extensions
Medium
Medium
DOMO
32
Curb Extensions
Medium
Medium
DOMO
49
Curb Extensions
Medium
Medium
DOMO
21
Crosswalk, Improved
Pedestrian Signage,
and Refuge Island
High
High
DOMO
54
Crosswalk, Improved
Pedestrian Signage,
and Refuge Island
n/a ^^
n/a ^^
High
DOMO
Location
Effectiveness
Cost
Potential Funding
Sources
Responsible
Party
Project
Number
88
Recommended
Improvement
Location
Steering
Committee Input
Group Project
Rank
Priority
Effectiveness
Cost
Potential Funding
Sources
Responsible
Party
33
Curb Extensions
Low
Medium
DOMO
34
Medium
Medium
DOMO
47
Mini Circle
Medium
Medium
DOMO
48
Mini Circle
Medium
Medium
DOMO
10
Medium
Low
DOMO
High
High
DOMO
** This projects will require additional study and may likely cost more than their estimates based on information discussed in their respective project
descriptions (pages 63-77).
^ Project costs may be significantly less if implemented as a part of a repaving project.
^^ These projects were not included in prioritization activities.
Project
Number
Recommended
Improvement
Location
Steering
Committee Input
Group Project
Rank
Priority
Effectiveness
Cost
Potential Funding
Sources
Responsible
Party
10
Bicycle Boulevard
11
Medium
Medium
$12,000
BBC, CIP, TE
DOMO
13
Textured Pavement
and Right Turn on
Red Restriction
Medium
High
$30,000
DOMO
14
Raised Median
11
Medium
Medium
$10,000
CDBG, CIP, TE
DOMO
22
Raised Median
11
Medium
Medium
DOMO
24
Curb Extensions
Medium
Medium
DOMO
28
Curb Extensions
11
Medium
Medium
DOMO
37
Curb Extensions
High
Medium
DOMO
39
Curb Extensions
Medium
Medium
DOMO
40
Curb Extensions
Medium
Low/Medium
DOMO
41
Curb Extensions
Medium
Low/Medium
DOMO
42
Curb Extensions
Medium
Low/Medium
DOMO
43
Curb Extensions
Medium
Low/Medium
DOMO
50
Mini Circle
Medium
Low
DOMO
51
Mini Circle
Medium
Low/Medium
DOMO
52
Mini Circle
Medium
Low/Medium
DOMO
89
Project
Number
90
Recommended
Improvement
Location
Steering
Committee Input
Group Project
Rank
Priority
Effectiveness
Cost
Potential Funding
Sources
$50,000CDBG, Private,
$100,000/
Operation Safewalks
year
Responsible
Party
Sidewalk Installation
and Replacement
Program
Medium
High
Gateway Features
Various Locations
12
Low
Low
$600,000
CDBG, Private, TE
UDO
Wayfinding/
Destination Signage
University Area
14
Low
Low
$80,000
CDBG, Private, TE
UDO
Neighborhood
Circulator Route
(LINK)
13
Medium
Low
COTA
25
Curb Extensions
Low
Low
$39,000
CDBG, CIP, TE
DOMO
26
Curb Extensions
11
Low
Low
$26,000
DOMO
29
Curb Extensions
11
Medium
Medium
DOMO
30
Curb Extensions
11
Medium
Medium
DOMO
35
Curb Extensions
Low
Medium
DOMO
36
Curb Extensions
Low
Medium
DOMO
38
Curb Extensions
Medium
Low
DOMO
44
Curb Extensions
Low
Low/Medium
DOMO
45
Curb Extensions
Low
Low/Medium
DOMO
46
Curb Extensions
Low
Low/Medium
DOMO
53
Mini Circle
Medium
Low/Medium
DOMO
Sidewalk Installation
High
High
WPCCA,
DOMO
DOMO
91