Don't Let The Pinch
Don't Let The Pinch
Don't Let The Pinch
CHEMICAL ENGINEERING PROGRESS DECEMBER 1999 Copyright 1999 American Institute of Chemical Engineers. All rights reserved. Copying and downloading permitted with restrictions.
H E AT T R A N S F E R
Figure 1.
Initial network design
for an aromatics plant.
40
160
83.4
C
119
220
327
10
4.34
220
60
79
C
1.14
60
103.5
C
149.9
2
215.8
189
220
159.5
160
17.39
100
201
85.9
35
3.56
85
141
10.1
3.86
1.61
141
6.6
(1)
0.2
190.3 243.8
189
9.6
an additional 40 m2 of surface in a
unit of 200 m2 nominal size. Since in
network optimization it is often possible to compensate for the removal
of one unit by adding additional surface elsewhere, the designer should
seek to eliminate small exchangers
from the network in favor of large
ones.
Figure 2 shows how much additional surface can be purchased in another single exchanger with the
C = 4,600 +
920A0.7
138
170
140
9.9 164
18.55
60
differ from that for the overall process. The pinch point resumes its role
as a guide to process changes rather
than acting as the point underpinning
the design.
300
300
H
0.25
10.7 11.25
300
A = 100 m2
A = Area of
Exchanger
Removed
250
200
A = 50 m2
150
A = 25 m2
100
A=0
50
0
25
50
100
150
200
250
300
350
400
450
500
Reactor
1
Gas
Separator
1
Distillation
Column 1
5
4
Distillation
Column 2
Gas
Separator
2
Reactor
2
7
Unit E
9
Source: Redrawn from (6).
H E AT T R A N S F E R
Figure 4.
Three simple
subnetworks.
C
1
a.
b.
2
1
c.
First Division
Group 1
Stream 1
(TAC)
Second Division
Streams 2
Group 1
Streams 1
2
(TAC)
Third Division
Group 1
Stream 1
2
(TAC)
Streams 3
Streams 4
Group 2
5
6
(TAC)
5
6
(TAC)
5
6
(TAC)
And so on...
Sequential
decomposition
of a process
integration
analysis.
Observations regarding
network design
Networks that contain the minimum number of units generally have
a quite simple structure that can be
broken down into a number of even
simpler self-contained subnetworks.
Typical examples of such structures
are shown in Figure 4.
The structure in Figure 4a consists
of just one heat-recovery exchanger
and a heater. Full use is made of
available process heat. There is no
scope for capital cost saving, because
in terms of duty, the structure is already optimal.
The structure in Figure 4b consists
of a single heat-recovery unit, a
heater, and a cooler. Varying the size
of the heat-recovery unit affects both
the capital and energy costs of the
system, which poses an optimization
problem. However, it is a straightforward problem that can be solved by
applying integration range targeting
to the two-stream problem. A sophisticated optimization program is not
required.
The structure in Figure 4c has
three process streams and two heatrecovery units plus one heater and
one cooler. Here, too, an optimization
problem exists. However, the structure can be decomposed into two
parts: Exchanger A, which as a standalone unit does not need to be optimized, and a structure similar to that
already considered (in Figure 4b),
which can be optimized using a targeting program.
Amidpour and Polley (5) intro-
Figure 6.
Process flow diagram
for the aromatics
plant in the example.
1
2
R1
T1
T2
T3
T6
13
T4
10
12
11
14
6
16
T5
17
R2
20
22
T10
T7
18
15
21
19
Problem
decomposition procedure
The following procedure for problem decomposition (Figure 5) can be
applied using simple process-integration targeting software:
1. Number the streams sequentially.
2. Apply range targeting to the full
stream set and establish a reference
total annual cost (TAC).
3. Split the stream set into two
parts, the first set consisting of
Stream 1 and the second set consisting of the remaining streams (here,
Streams 2 to 9).
Stagewise application
of problem decomposition
The order in which the streams are
listed affects the results of the decomposition analysis. By arranging them
in the order in which they appear on
the PFD, the designer can identify
cost-effective local integration (as opposed to cross-plant integration). This
has benefits in terms of piping cost,
plant operability, and plant simplicity.
But, once these opportunities are exhausted, this ordering has no benefit.
For general thermal integration,
H E AT T R A N S F E R
Overall ordering of a
process integration study
A process integration analysis
using this approach involves the following five stages.
1. Problem simplification removal of streams from problem.
2. Identification of process
changes improved overall efficiency through energy and utility cost
savings, and capital cost reduction.
3. Setting of final problem selection of utility levels, specification
of utility costs, selection of heattransfer parameters, and adjustment
of stream ordering, if desirable.
4. Decomposition analysis on the
basis of the layout identification of
cost-effective local integration.
5. Decomposition analysis on a
thermal basis development of the
remainder of the network.
Example:
aromatics solvent plant
Figure 6 is the PFD for an aromatics solvent plant. We will use it to
Name
CP, kW/C
Make-up
T1 Tops
T1 Bottoms
T2 Reboiler
T2 Condenser
T2 Bottoms
T3 Feed
T6 Reboiler
T6 Condenser
Raffinate
T4 Preheat
T4 Reboiler
T4 Condenser
T4 Bottoms
T5 Reboiler
T5 Condenser
R2 Feed
R2 Effluent
T10 Reboiler
T10 Condenser
T7 Reboiler
T7 Condenser
8
72
30
12,000
12,400
14
46
7,600
5,900
46
16
4,100
3,500
18
8,000
9,500
75.2
52.8
2,200
2,000
3,800
3,460
Stage 1
Simplify the problem
The stream data are entered into a
process-integration targeting program. (We have used INTEGRITY,
developed by ESDU, which already
incorporates the problem decomposition procedure.)
Ts, C
Tt, C
Load, kW
20
38
38
140
66
140
65
79
56
80
38
120
59
121
110
59
88
188
66
48
114
50
80
80
49
141
65
30
38
80
55
30
80
121
58
38
111
58
204
8
67
47
115
49
480
3,024
330
12,000
+12,400
+1,540
+1,242
7,600
+5,900
+2,300
672
4,100
+3,500
+1,494
8,000
+9,500
7,564
+5,228
2,200
+2,000
3,800
+3,46
350
300
Internal Temperature , C
250
200
T2
150
T5
100
T7
T4
T6
T10
T2
50
T5
T4
T7
T10
0
0
5,000
10,000
15,000
20,000
25,000
30,000
35,000
Enthalpy, kW
Minimum temperature difference = 10C
Figure 7. Heat demand and supply diagram for the aromatics plant in the example.
temperature deficits, heat recovery
from these units is not justified.
Therefore, assume that the reboilers on Columns T2, T4, T5, and T7
are driven by hot utility, and delete
these streams from the problem. Also
assume that the condensers on
Columns T4, T5, T6, T7, and T10 are
cooled using cold utility, and delete
these streams from the problem.
Stage 2
Identify process changes
The condenser on Column T2 is
below and close to the pinch while
the reboilers on Columns T6 and T10
are above and close to the pinch. In
addition, the load on the condenser is
close to the combined reboiler loads.
The pressure at which Column T2
operates can be increased. This would
result in an increase in the temperature at which the overheads condense.
It may be possible to use this vapor to
drive the two reboilers. If the temperature of the overheads could be raised
high enough, very-low-pressure
Stage 3
Set the final problem
Utility levels and costs. Examination of the HDS diagram suggests
(2)
H E AT T R A N S F E R
Stage 4 Decomposition
based on layout
The streams are ordered in accordance with their appearance on the
PFD. A range target for the full problem is then determined. The minimum TAC is found to be
$581,000/yr. This is a theoretical
minimum cost. The TAC of the final
design can be expected to be 1015%
higher than this.
Range targeting can now be applied systematically to different data
sets to identify how the problem can
be cost-effectively decomposed into
local integration problems.
Decomposition into two parts, one
group containing Streams 1 to 8 and
one group containing Streams 9 and
10, yields a system with a theoretical
minimum TAC of $611,000/yr. This
is made up of a theoretical cost of
$194,000/yr (at an optimum approach
temperature difference of 15C) for
the first group and an actual optimized cost of $417,000/yr (at an optimum temperature difference of 10C)
for the heat-recovery system involving the reactor streams (Streams 9
and 10).
Comparing this decomposed cost
of $611,000/yr with the theoretical
minimum of $581,000/yr indicates a
potential cost penalty associated with
this real match of $30,000/yr. This is
5.2 % of the theoretical minimum
cost.
Separate the reactor feed stream
(Stream 9) and reactor effluent stream
Ts, C
Tt, C
38
38
140
65
80
80
49
30
38
30
T1 Tops
T1 Bottoms
T2 Bottoms
T3 Feed
Raffinate
Load, kW
3,024
330
1,540
1,242
2,300
(Stream 10) from the problem and develop a separate subnetwork for this
system. It consists of a heater having
114 m2 of surface, a heat-recovery
exchanger of 714 m2, and a cooler of
10 m2.
Decomposition analysis of the remaining eight streams is now undertaken. The minimum TAC for the
subsystem is $194,000/yr. The analysis indicates that the problem can
again be broken down into two sections, the first containing Streams 1 to
6 (TAC = $204,000/yr) and the second containing just Streams 7 and 8
(TAC = $25,000/yr). Here, too, the
second group is an actual heat-recovery match. The TAC for the decomposed problem is $229,000/yr, with a
potential cost penalty of $35,000/yr
(6% of the theoretical minimum).
Separate the T4 preheat (Stream 7)
and the T4 bottoms (Stream 8) from
the problem and integrate them separately. The optimum temperature difference for this subsystem is 41C
and the associated TAC is $25,000/yr.
The network consists of two units, a
heat-recovery unit of 39 m2 and a
cooler of 36 m2.
Decomposition analysis of the remaining six streams is now undertaken. First consider using utility to heat
the make-up stream (Stream 1). The
TAC for the six-stream problem is, as
noted above, $204,000/yr. For the decomposed problem, the TAC is
$206,000/yr.
Heat the make-up stream using hot
utility. This requires a heater of 4 m2
and has a TAC of $59,000/yr.
Decomposition analysis is applied
to the remaining five streams. All
possible decompostions are found to
involve significant penalty. Thus, attention should now be directed to applying decomposition analysis on a
thermal basis.
Stage 5 Decomposition
on a thermal basis
The five streams remaining
listed in Table 2. These streams
now ordered in accordance with
hottest target temperatures for
are
are
the
the
Figure 8.
30
48
80
48
140
Raffinate
828
30
Structure derived
using the pinch
design method.
T2 Bottoms
252
T1 Tops
38
80
1472
264
1288
cold streams and hottest supply temperatures for the hot streams. Temperature spans and stream heat loads
provide secondary guidance with regard to the ordering.
Stream 1 should be T1 tops (the
cold stream with the hottest target
temperature). The next stream should
be the hot stream with the highest
supply temperature, which is T2 bottoms. This hot stream has insufficient
load to fully handle the cold stream.
So, the next stream should also be a
hot stream. Of the remaining hot
streams, the raffinate has the highest
supply temperature. The remaining
two streams can be placed in either
order. We choose to place the hot
stream first. So, the ranking is now:
Stream 1 = T1 tops;
Stream 2 = T2 bottoms;
Stream 3 = raffinate;
Stream 4 = T3 feed; and
Stream 5 = T1 bottoms.
Decomposition analysis is then applied to this order. The TAC of the
overall subsystem remains at
$147,000/yr. However, there is now a
suitable decomposition involving a
system containing Streams 1 to 3 and
one containing an actual match between Streams 4 and 5. The actual
cost of the match between the T3 feed
and the T1 bottoms is found to be
$28,000/yr. The minimum theoretical
cost for the three-stream system is
$131,000/yr. The combined costs are
$159,000/yr, which has a potential
cost penalty of $12,000/yr.
Match Streams T3 feed and T1
bottoms. A point target exists at the
identified optimum approach of 16C.
H E AT T R A N S F E R
Literature Cited
1. Umeda, T., et al., Heat Exchange System Synthesis, Chem. Eng. Progress, 74
(7), pp. 7076 (July 1978).
2. Umeda, T., T. Harada, and K. Shiroko,
A Thermodynamic Approach to the
Synthesis of Heat Integration Systems in
Chemical Processes, Computers and
Chemical Engineering, 3, pp. 273282
(1979).
3. Umeda, T., K. Niida, and K. Shiroko,
A Thermodynamic Approach to to Heat
Integration in Distillation Systems,
AIChE Journal, 25 (3), pp. 423429
(May 1979).
4. Itoh, J., K. Shiroko K., and T. Umeda,
Extensive Use of the T-Q Diagram to
Heat Integrated System Synthesis, presented at the International Symposium
on Process Systems Engineering, Kyoto,
1982, and published in Computers and
Chemical Engineering, 10, pp. 5966
(1986).
5. Amidpour, M., and G. T. Polley, Application of Problem Decomposition in
Process Integration, Transactions of
IChemE, 75A, pp. 5363 (1997).
6. Ahmad, S., and B. Linnhoff, Supertargeting: Different Process Structures for
Different Economics, Journal of Energy Resources Technology, 111, pp.
131136 (1989).
7. ESDU International, PLC, Costing of
Shell-and-Tube
Heat
Exchangers,
ESDU, London (1999).
8. Amidpour, M., and G. T. Polley, Dealing With Piping Constraints in Heat Exchanger Network Synthesis, IChemE
Symposium on Process Integration and
Fluid Separations, Manchester, U.K.
(June 1994).
9. Ponton J. W., and R. A. B. Donaldson,
A Fast Method for the Synthesis of Optimal Heat Exchanger Networks, Chem.
Eng. Sci., 29, pp. 23752377 (1974).
10. Ahmad S., B. Linnhoff, and R. Smith,
Design of Multipass Heat Exchangers:
An Alternative Approach, Journal of
Heat Transfer, 110, pp 304309 (May
1990).
11. Saunders, E. A. D., Heat Exchangers:
Selection, Design and Construction,
Longman Group, London, copublished
in the U.S. by John Wiley & Sons, New
York (1988).