Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                
0% found this document useful (0 votes)
313 views3 pages

Construion Contract IAS

Download as docx, pdf, or txt
Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1/ 3

Construction Contracts IAS 11

1. Miracle Construct Inc. is executing a gigantic project of constructing


the tallest building in the country. The project is expected to take three
years to complete.
The company has signed a fixed price contract of $12,000,000 for the
construction of this prestigious tower. The details of the costs incurred
to date in the first year are
Site labor costs
$1,000,0
00
Cost of construction material
3,000,00
0
Depreciation of special plant and equipment used
in-contracting to build the tallest building
500,0
00
Marketing and selling costs to get the tallest
building-in the country the right exposure
1,000,0
00
Total
$5,500,0
00
Total contract cost estimated to complete
$5,500,0
00
Required
Calculate the percentage of completion and the amounts of revenue,
costs, and profits to be recognized under IAS 11.
1. Lazy Builders Inc. has incurred the following contract costs in the first
year on a two-year fixed price contract for $4.0 million to construct a
bridge:
Material cost = $2 million
Other contract costs (including site labor costs) = $1 million
Cost to complete = $2 million
How much profit or loss should Lazy Inc. recognize in the first year of
the three-year construction contract?
(a) Loss of $0.5 million prorated over two years.
(b) Loss of $1.0 million (expensed immediately).
(c) No profit or loss in the first year and deferring it to second year.
(d) Since 60% is the percentage of completion, recognize 60% of loss
(i.e., $0.6 million).

2. Brilliant Inc. is constructing a skyscraper in the heart of town and has


signed a fixed price two-year contract for $21.0 million with the local
authorities. It has incurred the following cost relating to the contract by
the end of first year:
Material cost = $5 million
Labor cost = $2 million
Construction overhead = $2 million
Marketing costs = $0.5 million
Depreciation of idle plant and equipment = $0.5 million
At the end of the first year, it has estimated cost to complete the
contract = $9 million.
What profit or loss from the contract should Brilliant Inc. recognize at
the end of the first year?
(a) $1.5 million (9/18 3.0)
(b) $1.0 million (9/18 2.0)
(c) $1.05 million (10/19 2.0)
(d) $1.28 million (9.5/18.5 2.5)
3. Mediocre Inc. has entered into a very profitable fixed price contract for
constructing a high-rise building over a period of three years. It incurs
the following costs relating to the contract during the first year:
Cost of material = $2.5 million
Site labor costs = $2.0 million
Agreed administrative costs as per contract to be reimbursed by the
customer = $1 million
Depreciation of the plant used for the construction = $0.5 million
Marketing costs for selling apartments when they are ready = $1.0
million
Total estimated cost of the project = $18 million
The percentage of completion of this contract at the year-end is
(a) 50% (= 6.0/18.0)
(b) 27% (= 4.5/16.5)
(c) 25% (= 4.5/18.0)
(d) 39% (= 7.0/18)
4. A construction company is in the middle of a two-year construction
contract when it receives a letter from the customer extending the
contract by a year and requiring the construction company to increase
its output in proportion of the number of years of the new contract to
the previous contract period.
This is allowed in recognizing additional revenue according to IAS 11 if

(a) Negotiations have reached an advanced stage and it is probable


that the customer will accept the claim.
(b) The contract is sufficiently advanced and it is probable that the
specified performance
Standards will be exceeded or met.
(c) It is probable that the customer will approve the variation and the
amount of revenue
arising from the variation and the amount of revenue can be reliably
measured.
(d) It is probable that the customer will approve the variation and the
amount of revenue
arising from the variation, whether the amount of revenue can be
reliably measured or not.
5. A construction company signed a contract to build a theater over a
period of two years, and with this contract also signed a maintenance
contract for five years. Both the contracts are negotiated as a single
package and are closely interrelated to each other.
The two contracts should be
(a) Combined and treated as a single contract.
(b) Segmented and considered two separate contracts.
(c) Recognized under the completed contracted method.
(d) Treated differentlythe building contract under the completed
contract method and
maintenance contract under the percentage of completion method.

You might also like