COMAH
COMAH
COMAH
I have taken the points from the COMAH report that I found relevant to
each element as a direct quote.
UNIT 7
Element 12: management of change
-
Management of change system ensures that only competent personnel approves any
change
The Management of Change forms covers the following details: - Location of the work;
- Description of the work;
- Hazardous Substances;
- Risk Assessment completion;
- Equipment;
- General comments; and
- Approvals
The Company operates a Management of Change Form system for all minor changes
Terminal Manager.
For minor changes, qualified competent staff assess the impact the change would
have by either forming a team, carrying out a Risk Assessment, conducting a site
audit or a combination of all three.
Designated areas are provided for vehicles held for inspection and documentation
planned inspections
All equipment is subjected to regular inspection within time periods that are in
accordance with known, historically established low corrosion rates for petroleum
products.
The storage tanks are visually inspected at a frequency of once in six months, 5
yearly internal inspection and subjected to a non-destructive test (NDT) at least
every 10 years to monitor the corrosion rate and the expected life of the tank (see
Appendix 4). This is consistent with industry practice and the known low corrosion
rates.
Visual inspection is carried out at every ship discharge (walk on import procedure).
Mechanical failure can be caused by fatigue (the effect of vibrations weakening the
equipment over sustained period) or inadequate welding. The pump is the only
source of vibration but the vibration level is low. If any fatigue were present or
inadequate welds the regular condition monitoring inspections are designed to
-
detect this.
Corrosion of a storage tank could lead to a release of its contents into the bund. If
a source of ignition is present then a fire could develop. The storage tanks are
designed to BS 2654 or API 650 and the periodic inspection procedures are
Pressure gauges
Levels sensors
Shut off valves for emergencies
Fire alarms
Emergency lighting
Emergency response system to alert emergency services
All injuries are reported, even if it is minor, and logged in the Accident Book
All incidents and near misses are reported, investigated and recorded via the
OilCompany Loss Prevention System
UNIT 8
The energy institutes high level framework for process safety management states that
element 20 is; Audit, assurance, management review & intervention
Regular review and audit of compliance with the EI PSM framework is important to ensure
that HS&E and process safety performance continue to meet the defined targets.
This can be addressed by analysing the given COMAH report.
-
All the systems in place are regularly audited including third party
Unit 10
Permits to work are important to make sure the qualified people undertake the work and
by doing this, major accidents are avoided:
-
facilities
Isolation isolating machinery or equipment from energy or toxic
substances
Height work prevent falls and injuries
Submitting a request for a permit to work takes time and the intention of this is to give
the site staff time to prepare the area destined for maintenance. The request necessitates
an accompanying method statement and risk assessment to ensure safety to the highest
degree.
Issuing authority (site staff, project managers etc.) will visit the site that needs
maintenance with the contractor to check that all safety precautions and risks are
correctly addressed after this permit is agreed.
During and after the work is complete, the issuing authority will check that the work has
been done to industry standards and once it has been approved, the work will be signed
off by both parties.
UNIT 11
-
species;
If insoluble in water and less dense the rate of transfer of gases between
the air and the water reduced directly affecting fauna (lack of oxygen)
change;
If insoluble in water and with a higher density than water so that it can