Process CheckLists P&ID Rev 3
Process CheckLists P&ID Rev 3
Process CheckLists P&ID Rev 3
PROCESS
P&ID
XXXX-XX-D1225-XXX-XX-XX
Document No.
ERF Title
Rev.
__
of __
Document Title
ERF No.
2095
Initial
Sign
Date
DESCRIPTION
Item No.
1.0 General
1.01 Latest soft file taken from EDL and got locked there.
1.02
Drawing are shared with the other discipline. (Piping and Instrument)
1.02
1.03
Proper isolation for the line new line or existing line are provided.
1.05
All the P&IDs to be modified under current ERF have been As-Built.
1.06
1.07
1.08
1.09
1.10
1.11
For AFC, Approved By is filled with the BPP Authority for P&IDs approval.
1.12
To keep the previous revision clouds, confirmation has been got from FOE.
Generally, all previous revision clouds shall be hide using a different layer.
1.13
1.14
Connectivity, i.e., P&ID Nos. in connectors of the connecting sheets and the
Line Nos. are matching.
1.15
1.16
1.17
Control and Shutdown Philosophies have been agreed and frozen and
discussed with I&E
1.18
1.19
2.0
2.01
Drawing Presentation:
Drawing professionally presented and well balanced
2.02
2.03
If existing drawing is modified, new modifications are shown in thick layer and
existing system is shown dim layer.
2.04
2.05
If any existing item is replaced with new item, existing item is shown in
Demolishing cloud with Tag "TO BE DEMOLISHED" and new item is shown
in scope cloud.
2.06
L.E.
Date:
CHECKER
ORIGINATOR
ED/3-108-01-P&ID
0
Page
Remarks
XXXX-XX-D1225-XXX-XX-XX
Document No.
Rev.
ED/3-108-01-P&ID
0
Page
__
of __
3.01
3.02
In case the vessel is relocated from one facility/location to other, it has been
verified/confirmed that the vessel's DP/DT are safe against the new operating
conditions.
3.03
3.04
For the relocated vessel, PSH, PSHH, PSL, PSLL, LSLL, LSL, LSH, LSHH
are verified/marked for the new service. (Calculation must be save in the ERF
/ Process / Calculation folder.)
3.05
For new vessel, no. and tags of nozzles as per data-sheet / fabrication dwg.
3.06
The PCV and LCV relocated with the vessel are checked for the new
conditions (data provided to for rating / evaluation purpose must be save in
soft form.).
3.07
For the relocated vessel, PSV set pressure and orifice size are evaluated
under new conditions.
4.0
4.01
Follow the pipe thickness sch#, in light of Pakistan regulatory authority, and
discussed in the K.O meeting with F.O.E. In case if not yet addressed kingly
communicate with piping engineer and follow the pipe thickness after 3mm
corrosion allowance.
As per ENTS-400
4.02
Incorporated in STD
Drawings
5.0
5.01
If instructed by client
5.02
If instructed by FOE
5.03
Review if instructed by
client in SOW
5.04
5.05
Mini blow case capacity must be discussed. (this shall be discussed during
conceptual stage, however if not discussed kindly address)
6.0
6.01
Piping
Tie-in points consulted with Piping (for the piping ease) and marked properly
under the current revision cloud.
GENERAL NOTES & REFERENCES
6.02
6.03
6.04
6.05
6.06
6.07
UEP Standard
XXXX-XX-D1225-XXX-XX-XX
Document No.
Rev.
ED/3-108-01-P&ID
0
Page
__
of __
Triangle Shown
6.09
6.10
6.11
6.12
6.13
In case BPP asks to use a higher Piping Class than that required (and
communicated by DH to BPP), put a Note on P&ID for such particular case
that;
"Piping Class XX has been used against the required YY, due to material
availability."
6.14
6.15
6.16
6.17
6.18
6.19
If instructed by client
6.20
6.21
6.22
6.23
6.24
For the Wellhead P&ID, it has been confirmed from BPP whether Chemical
Injection shall be done at a Single or at Two points.
6.25
Normal Open (NO), Normal Close (NC), Lock Open (LO) or Lock Close (LC)
marked at manual valves, as per requirement.
6.26
If Pump is relocated to another facility, new suction / discharge line sizes are
verified against pump rated Head and NPSHA.
6.27
6.28
Before AFC discussed the tie-in points with the piping engineer.
7.0
7.01
Instrumentation
For Control Valve, it has been confirmed from BPP whether Isolation &
Bypass valves shall be required or not.
7.02
7.03
7.04
Local / remote indications and alarms / trips are shown on P&ID as per
control & shutdown philosophy.
Note:- Any check item marked NA by Originator should be verified by Checker and LE
UEP Standard
Incorporated in STD
Wellhead drawing
As instructed by client
If instructed by client