RCM Handbook-1
RCM Handbook-1
RCM Handbook-1
Table of Contents
Chapter 1-Background ........................................................................................................ 1−1
1.1 Introduction ..................................................................................................... 1−1
1.2 Historical Evolution of RCM ........................................................................... 1−1
1.3 Purpose of This Guide...................................................................................... 1−4
1.4 Applicability and Use of This Guide ................................................................ 1−4
February 2000 i
NASA Reliability Centered Maintenance Guide for Facilities and Collateral Equipment
ii February 2000
NASA Reliability Centered Maintenance Guide for Facilities and Collateral Equipment
List of Tables
iv February 2000
NASA Reliability Centered Maintenance Guide for Facilities and Collateral Equipment
List of Figures
February 2000 v
NASA Reliability Centered Maintenance Guide for Facilities and Collateral Equipment
vi February 2000
NASA Reliability Centered Maintenance Guide for Facilities and Collateral Equipment
Chapter 1 - Background
1.1 Introduction
Reliability Centered Maintenance (RCM) is the process that is used to determine the most
effective approach to maintenance. It involves identifying actions that, when taken, will reduce
the probability of failure and which are the most cost effective. It seeks the optimal mix of
Condition-Based Actions, other Time- or Cycle-Based actions, or a Run-to-Failure approach, as
shown in Figure 1-1. The principal features of each strategy are shown below their block in
Figure 1-1. RCM is an ongoing process that gathers data from operating systems performance
and uses this data to improve design and future maintenance. These maintenance strategies,
rather than being applied independently, are integrated to take advantage of their respective
strengths in order to optimize facility and equipment operability and efficiency while minimizing
life-cycle costs. The elements of RCM are developed in Chapter 2 and the maintenance
strategies are defined and discussed in Chapter 3.
Reliability
Centered
Maintenance
1
F. Stanley Nowlan and Howard F. Heap. Reliability-Centered Maintenance. United Airlines and Dolby Press,
sponsored and published by the Office of Assistant Secretary of Defense, 1978.
From approximately 1960 until the late 1980s, Preventive Maintenance (PM) was the most
advanced technique used by progressive facilities maintenance organizations. PM is based on
two principles - 1) a strong correlation exists between equipment age and failure rate, and 2)
individual component and equipment probability of failure can be determined statistically, and
therefore, parts can be replaced or rebuilt prior to failure.
PM assumes that failure probabilities can be determined statistically for individual machines and
components and parts or adjustments can be replaced or performed in time to preclude failure.
For example, a common practice in the past was to replace or renew bearings after some number
of operating hours based on the assumption that bearing failure rate increases with time in
service. This has proven to be ineffective.
Figure 1–2 shows the failure distribution of a group of thirty identical 6309 deep groove ball
bearings installed on bearing life test machines and run to failure. The wide variation in bearing
life is obvious and precludes the use of any effective time-based maintenance strategy2. The X-
axis is the individual bearing being tested while the Y-axis is the number of revolutions achieved
prior to fatigue failure of the individual bearing. It should be noted that the bearings are tested at
above-design loads to accelerate the failure rate. This is the standard procedure used to test
bearings in order to determine the expected life of a bearing.
In all the studies, it was noted that a difference existed between the perceived and the intrinsic
design life for the majority of equipment and components. In fact, it was discovered that in
many cases equipment bearing life greatly exceeded the perceived or stated design life. For
example, SKF Industries proposed changes in the method for evaluating bearing life - from the
original method (empirical) proposed by Lundberg and Palmgren3 to one where "bearings exhibit
a minimum fatigue life; that is, 'crib deaths' due to rolling contact fatigue are non-existent when
the aforementioned operating conditions (properly lubricated, mounted, operated and protected
from dirt and moisture) are achieved."4 This lack of a predefined fatigue life for bearings greatly
impacts the concept of a predetermined design life for rotating equipment where rolling element
bearings are used and provides the basis for extending the time between overhauls and
equipment replacement.
This process, known as Age Exploration (AE), was used by the U.S. Submarine Force in the
early 1970's to extend the time between periodic overhauls and to replace time based tasks with
condition based tasks. While the initial program was limited to Fleet Ballistic Missile (FBM)
submarines, it was continuously expanded until it included all submarines, aircraft carriers, other
major combatants, and ships of the Military Sealift Command (MSC). Furthermore, the Navy
has invoked the requirements of RCM and condition monitoring as part of new ship design
specifications.
It should not be inferred from the above that all interval based maintenance should be replaced
by condition based maintenance. In fact, interval based maintenance is often appropriate for
2
Eschmann, et al, Ball and Roller Bearings: Theory, Design, & Application, John Wiley & Sons, 1985
3
G. Lundberg and A. Palmgren, Dynamic Capacity of Roller Bearings, Acra Polytech, Mechanical Engineering
Series 1, R.S.A.E.E., No. 3, 7, 1947.
4
Tedric A. Harris, Roller Bearing Analysis, Second Edition, John Wiley and Sons, New York, 1984
those instances where an abrasive, erosive, or corrosive wear takes place, material properties
change due to fatigue, embrittlement, etc. and/or a clear correlation between age and functional
reliability exists.
Development of new technologies during the 1990's, including affordable microprocessors and
increased computer literacy in the work force, has made it possible to determine the actual
condition of equipment and not have to rely upon estimates of when the equipment might fail
based on age. These new cost effective technologies and the lack of correlation between age and
failure in many equipment items have increased the emphasis on condition monitoring.
Condition monitoring, commonly called Predictive Testing and Inspection (PT&I) within the
NASA facilities maintenance environment, has resulted in a need to review existing Preventive
(PM) and Programmed (PGM) Maintenance efforts and ensure that the most effective approach
is being used. RCM provides the structure for developing that approach.
Closely aligned with determining what maintenance approach to use are the subjects of who
should do the work and what parts and material will be needed to ensure that the work is done in
the most cost efficient manner.
Most recently, RCM has taken on a prominent role in NASA's facility and equipment
maintenance and operations program. RCM principles have been integrated into the
SPECSINTACT (See Appendix K, Clauses with RCM Applications) wherein designs now have
requirements for designing to maintainability. PT&I is used within the construction contractor's
quality control program before and during commissioning to ensure that there are no latent
manufacturing and installation defects at the time of equipment acceptance. PT&I and proactive
1 5 10 15 20 25 30
Bearing Number From: Ball and Roller Theory,
Design, & Application.
Eschmann, et al
John Wiley & Sons, 1985
analyses are used as tools by NASA Quality Assurance Evaluators (QAEs) to monitor the
contractor's compliance with the specific requirements of performance based contracts. RCM is
used in developing Condition Assessments and in determining the Backlog of Maintenance and
Repair (BMAR). RCM principles and procedures are used every day in the maintenance of
NASA's facilities where methods, frequencies, periodicities and other criteria are identified in the
Annual, 5-Year, and more frequent Work Plans.
This guide is intended to provide detailed information for aiding in the implementation of RCM
concepts and supporting programs within the NASA facilities community. Intended users
include facility planners, designers, equipment procurement specialists, construction managers,
systems engineers, and maintenance and operations (M&O) contract planners and managers.
Figure 1-3 provides a visual representation of the RCM strategy and process relationship.
• An Overview of RCM
RCM Strategy
RCM Process
Maintenance
Outcomes Performance Optimization
Time- or Cycle-Based actions Determine who will perform the
including Inspection, Calibration, maintenance and repair actions.
and Condition Monitoring.
Condition-Based actions
including Overhaul and Repair.
5
NASA NPG 8831.2, Facilities Maintenance Management Handbook
2.1 Philosophy
The RCM philosophy employs Preventive Maintenance (PM), Predictive Testing and Inspection
(PT&I), Repair (also called reactive maintenance) and Proactive Maintenance techniques in an
integrated manner to increase the probability that a machine or component will function in the
required manner over its design life cycle with a minimum of maintenance. The goal of the
philosophy is to provide the stated function of the facility, with the required reliability and
availability at the lowest cost. RCM requires that maintenance decisions be based on
maintenance requirements supported by sound technical and economic justification. As with any
philosophy, there are many paths, or processes, that lead to a final goal. This is especially true
for RCM where the consequences of failure can vary dramatically.
Rigorous RCM analysis has been used extensively by the aircraft, space, defense, and nuclear
industries where functional failures have the potential to result in large losses of life, national
security implications, and/or extreme environmental impact. A rigorous RCM analysis is based
on a detailed Failure Modes and Effects Analysis (FMEA) and includes probabilities of failure
and system reliability calculations. The analysis is used to determine appropriate maintenance
tasks to address each of the identified failure modes and their consequences.
While this process is appropriate for these industries, it is not necessarily the most practical or
best approach to use for facilities systems maintenance. For these systems a streamlined or
intuitive RCM analysis process may be more appropriate. This is due to the high analysis cost of
the rigorous approach, the relative low impact of failure of most facilities systems, the type of
systems and components maintained, and the amount of redundant systems in place. The
streamlined approach uses the same principles as the rigorous, but recognizes that not all failure
modes will be analyzed. NASA has reviewed the various processes in use and has determined
that the most economical and efficient approach is to use a combination of rigorous (formal) and
intuitive analysis depending on system criticality and failure impact. Candidates for rigorous
analysis include, but are not limited to, wind tunnel drive motors, supercomputer facilities, and
mission support systems where single points of failure exist. In addition, a more rigorous
analysis may be needed for those systems and components where the streamlined or intuitive
RCM process has been utilized and the resultant reliability is still unacceptable in terms of
safety, cost, or mission impact.
• What can be done to reduce the probability of the failure, identify the onset of
failure, or reduce the consequences of the failure?
Figures 2-1 and 2-2 illustrate the RCM approach and the interactive streamlined process.
· System Input
Identify System · System Output
and Boundary · Resources
· Constraints
Identify
To what level?
Sub-systems and
- Inconsequential
Components
· Primary or support?
Examine Function · Continuous or intermittent?
· Active or Passive?
Failure
Define Failure and
· Hidden Failure
Failure Modes
· Potential Failure
h. RCM Tasks Must Be Applicable—The tasks must address the failure mode and
consider the failure mode characteristics.
i. RCM Tasks Must Be Effective—The tasks must reduce the probability of failure
and be cost effective.
Yes Candidate
Develop &
schedule PT&I
Is there an
effective Interval-
No
For
task to monitor
Based task?
condition.
Yes Yes
j. RCM Acknowledges Three Types of Maintenance Tasks - These tasks are time-
directed (PM), condition-directed (PdM), and failure finding (one of several
aspects of Proactive Maintenance). Time-directed tasks are scheduled when
appropriate. Condition-directed tasks are performed when conditions indicate they
are needed. Failure-finding tasks detect hidden functions that have failed without
giving evidence of pending failure. Run-to-Failure is a conscious decision and is
acceptable for some equipment.
k. RCM is a Living System—It gathers data from the results achieved and feeds this
data back to improve design and future maintenance. This feedback is an
important part of the Proactive Maintenance element of the RCM program.
Note that the maintenance analysis process, as illustrated in Figure 2-2, has only four possible
outcomes:
A formal RCM analysis of each system, subsystem, and component is normally performed on
new, unique, high-cost systems such as aircraft and spacecraft systems and structures. This
approach is rarely needed for most facilities and collateral equipment items because their
construction and failure modes are well understood. Regardless of the technique used to
determine the maintenance approach, the approach must be reassessed and validated. Figure 2-3
depicts an iterative RCM process that can be used for a majority of NASA facilities and
collateral equipment.
2.4 Failure
Failure is the cessation of proper function or performance. RCM examines failure at several
levels: the system level, sub-system level, component level, and sometimes even the parts level.
The goal of an effective maintenance organization is to provide the required system performance
at the lowest cost. This means that the maintenance approach must be based upon a clear
understanding of failure at each of the system levels. System components can be degraded or
even failed and still not cause a system failure (A simple example is the failed headlamp on an
automobile. That failed component has little effect on the overall system performance).
Conversely, several degraded components may combine to cause the system to have failed even
though no individual component has itself failed.
NO YES
YES NO NO YES
NO YES
Is PT&I cost
and priority-
justified?
NO YES
NO YES
Is establishing
redundancy cost- and
Priority-justified?
NO YES
Functional failures are descriptions of the various ways in which a system or subsystem can fail
to meet the functional requirements designed into the equipment. A system or subsystem that is
operating in a degraded state but does not impact any of the requirements addressed in paragraph
2.4.1 (Systems and System Boundary) has not experienced a functional failure.
It is important to determine all the functions of an item that are significant in a given operational
context. By clearly defining the functions' non-performance, the functional failure becomes
clearly defined. For example, it is not enough to define the function of a pump to move water.
The function of the pump must be defined in terms of how much water, at what pressure, at what
efficiency, etc.
Dominant failure modes are those failure modes responsible for a significant proportion of all the
failures of the item. They are the most common modes of failure.
Not all failure modes or causes warrant preventive or predictive maintenance because the
likelihood of their occurring is remote or their effect is inconsequential.
2.4.4 Reliability
Reliability is the probability that an item will survive a given operating period, under specified
operating conditions, without failure. The conditional probability of failure measures the
probability that an item entering a given age interval will fail during that interval. If the
conditional probability of failure increases with age, the item shows wear-out characteristics.
The conditional probability of failure reflects the overall adverse effect of age on reliability. It is
not a measure of the change in an individual equipment item.
Failure rate or frequency plays a relatively minor role in maintenance programs because it is too
simple a measure. Failure frequency is useful in making cost decisions and determining
maintenance intervals, but it tells nothing about which maintenance tasks are appropriate or
about the consequences of failure. A maintenance solution should be evaluated in terms of the
safety or economic consequences it is intended to prevent. A maintenance task must be
applicable (i.e., prevent failures or ameliorate failure consequences) in order to be effective.
Type C - Low failure probability when the item is new or just overhauled, followed by a
quick increase to a relatively constant level.
Type F - Gradually increasing failure probability, but no identifiable wear-out age. Age
limit usually not applicable. (Typical of turbine engines.)
Types A and E are typical of single-piece and simple items such as tires, compressor blades,
brake pads, and structural members. Most complex items have conditional probability curves of
types B, C, D, and F.
The basic difference between the failure patterns of complex and simple items has important
implications for maintenance. Single-piece and simple items frequently demonstrate a direct
relationship between reliability and age. This is particularly true where factors such as metal
fatigue or mechanical wear are present or where the items are designed as consumables (short or
predictable life spans). In these cases an age limit based on operating time or stress cycles may
be effective in improving the overall reliability of the complex item of which they are a part.
Type A
2% 1% 17%
Type F
5% 4% 3%
Time
Type C
7% 11% 6%
Type D
14% 15% 42%
Type B
68% 66% 29%
Time
Complex items frequently demonstrate some infant mortality, after which their failure
probability increases gradually or remains constant, and a marked wear-out age is not common.
In many cases scheduled overhaul increases the overall failure rate by introducing a high infant
mortality rate into an otherwise stable system. The failure characteristics shown in Figure 2-4
were first noted in the previously cited book, Reliability-Centered Maintenance6. Follow-on
studies in Sweden in 1973, and by the U.S. Navy in 1983, produced similar results. In these
three studies, random failures accounted for 77-92% of the total failures and age related failure
characteristics for the remaining 8-23%.
a. Decreasing the amount of stress applied to the item. The life of the item is
extended for the period f0-f1 by the stress reduction shown.
b. Increasing or restoring the item’s resistance to failure. The life of the item is
extended for the period f1-f2 by the resistance increase shown.
Stress is dependent on use and may be highly variable. It may increase, decrease, or remain
constant with use or time. A review of the failures of a large number of nominally identical
simple items would disclose that the majority had about the same age at failure, subject to
statistical variation, and that these failures occurred for the same reason. If one is considering
preventive maintenance for some simple item and can find a way to measure its resistance to
failure, one can use that information to help select a preventive task.
Adding excess material that wears away or is consumed can increase resistance to failure.
Excess strength may be provided to compensate for loss from corrosion or fatigue. The most
common method of restoring resistance is by replacing the item.
The resistance to failure of a simple item decreases with use or time (age), but a complex unit
consists of hundreds of interacting simple items (parts) and has a considerable number of failure
modes. In the complex case, the mechanisms of failure are the same, but they are operating on
many simple component parts simultaneously and interactively so that failures no longer occur
for the same reason at the same age. For these complex units, it is unlikely that one can design a
maintenance task unless there are a few dominant or critical failure modes.
6
F. Stanley Nowlan and Howard F. Heap, Reliability Centered Maintenance, United Airlines and Dolby Press,
sponsored and published by the Office of Assistant Secretary of Defense, 1978
Increase or
Restore Resistance
Resistance
Decrease Rate
of Degradation
Stress
f0 f1 f2 f3
Life Extension
Operating Age
Even though there are multiple failure modes, often the effects of the failure are the same or very
similar in nature. That is, from a system function perspective, the outcome of any component
failure may result in the system function being degraded.
Likewise, similar systems and machines will often have the same failure modes. However, the
system use will determine the failure consequences. For example, the failure modes of a ball
bearing will be the same regardless of the machine. However, the dominate failure mode will
often change from machine to machine, the cause of the failure may change, and the effects of
the failure will differ.
Figure 2-6 provides an example of a FMEA worksheet. The key elements identified on the
worksheet reflect the items identified in the RCM analysis (see Figure 2-1). There are two new
terms identified in Figure 2-6: Criticality and Probability of Failure Occurrence.
7
Reliability, Maintainability, and Supportability Guidebook, Third Edition, Society of Automotive Engineers, Inc.,
Warrendale, PA, 1995.
February 2000
Identify Center, Building, Time
System Name
: If Used
: Who prepared this FMEA
3-19
NASA Reliability Centered Maintenance Guide for Facilities and Collateral Equipment
NASA Reliability Centered Maintenance Guide for Facilities and Collateral Equipment
The Probability of Occurrence (of Failure) is also based on work in the automotive industry.
Table 2-2 provides one possible method of quantifying the probability of failure. If there is
historical data available, it will provide a powerful tool in establishing the ranking. If the
historical data is not available, a ranking may be estimated based on experience with similar
systems in the facilities area. The statistical column in Table 2-2 can be based on operating
hours, day, cycles, or other unit that provides a consistent measurement approach. Likewise, the
statistical bases may be adjusted to account for local conditions. For example, one organization
changed the statistical approach for ranking 1 through 5 to better reflect the number of cycles of
the system being analyzed.
Each of the individual components that makes up the chilled water system would then have a
similar analysis performed, as illustrated in Table 2-4:
Source of
Function Functional Failure Failure Mode
Failure
Table 2-5 focuses on one failure mode, the seized bearing. Similar information will be needed
for each failure mode. This information can become extensive for even the simplest of systems
and can require a significant amount of effort and expense to compile. Table 2-5 is an
abbreviated and simplistic compilation.
Notice that through the iterative, albeit simplified, process illustrated above, the engineer or
technician performing the analysis is able to determine the root cause of the problem by
deducting non-indicative symptoms and conditions. Medical doctors follow similar reasoning in
their determination of patients' health problems - they eliminate the non-symptoms, then through
an iterative process, deduct each possible cause of the problem, starting with the most likely first.
• To ensure realization of the inherent safety and reliability levels of the equipment.
8
F. Stanley Nowlan and Howard F. Heap, Reliability Centered Maintenance, United Airlines and Dolby Press,
sponsored and published by the Office of Assistant Secretary of Defense, 1978
• To obtain the information necessary for design improvement of those items where
their inherent reliability proves to be inadequate.
2.7.1 Safety
Per NPD 8700.1, NASA Policy for Safety and Mission Success, NASA policy is to "Avoid loss of
life, personal injury or illness, property loss or damage, or environmental harm from any of its
activities and ensure safe and healthful conditions for persons working at or visiting NASA
facilities." By its very features, including analysis, monitoring, taking decisive action on systems
before they become problematic, and thorough documentation, RCM is highly supportive of and
an integral part of the NASA Safety policy.
2.7.2 Cost
Due to the initial investment required for obtaining the technological tools, training, and
equipment condition baselines, a new RCM Program typically results in a short-term increase in
maintenance costs. This increase is relatively short-lived. The cost of repair decreases as
failures are prevented and preventive maintenance tasks are replaced by condition monitoring.
The net effect is a reduction of both repair and a reduction in total maintenance cost. Often
energy savings are also realized from the use of PT&I techniques.
2.7.3 Reliability
RCM places great emphasis on improving equipment reliability, principally through the feedback
of maintenance experience and equipment condition data to facility planners, designers,
maintenance managers, craftsmen, and manufacturers. This information is instrumental for
continually upgrading the equipment specifications for increased reliability. The increased
reliability that comes from RCM leads to fewer equipment failures and, therefore, greater
availability for mission support and lower maintenance costs.
2.7.4 Scheduling
The ability of a condition-monitoring program to forecast maintenance provides time for
planning, obtaining replacement parts, and arranging environmental and operating conditions
before the maintenance is done. PT&I reduces the unnecessary maintenance performed by a
time-scheduled maintenance program which tends to be driven by the minimum “safe” intervals
between maintenance tasks.
A principal advantage of RCM is that it obtains the maximum use from equipment. With RCM,
equipment replacement is based on equipment condition, not on the calendar. This condition-
based approach to maintenance thereby extends the operating life of the facility and its
equipment.
2.7.5 Efficiency/Productivity
Safety is the primary concern of RCM. The second most important concern is cost-effectiveness.
Cost-effectiveness takes into consideration the priority or mission criticality and then matches a
level of cost appropriate to that priority. The flexibility of the RCM approach to maintenance
ensures that the proper type of maintenance is performed on equipment when it is needed.
Maintenance that is not cost effective is identified and not performed.
Decisions made early in the acquisition cycle profoundly affect the life-cycle cost of a facility.
Even though expenditures for plant and equipment may occur later during the acquisition
process, their cost is committed at an early stage. As shown conceptually in Figure 2-7, planning
(including conceptual design) fixes two-thirds of the facility’s overall life-cycle costs. The
subsequent design phases determine an additional 29% of the life-cycle cost, leaving only about
5% of the life-cycle cost that can be impacted by the later phases.
Thus, the decision to include a facility in an RCM program, including PT&I and condition
monitoring, which will have a major impact on its life-cycle cost, is best made during the
planning phase. As RCM decisions are made later in the life cycle, it becomes more difficult to
achieve the maximum possible benefit from the RCM program.
Even though maintenance is a relatively small portion of the overall life-cycle cost, typically 3%
to 5% of a facility’s operating cost, RCM is still capable of introducing significant savings
during the M&O phase of the facility’s life. Savings of 30% to 50% in the annual maintenance
budget are often obtained through the introduction of a balanced RCM program.
100%
95%
75% 66%
Life-
cycle
Cost 50%
25%
Conceptual Construction/
Design Final Commissioning
Planning Maintenance
Design
& Operations
Blanchard, B.S., Design and
Manage to Life Cycle Cost,
Forest Grove, OR, MA
Life-Cycle
Press, 1978.
Priority
Application
Number Description
1 Emergency Safety; mission impact.
Examples of components where RTF is applicable are non-critical electric motors less than 7.5
HP, comfort cooling, restroom exhaust fans, water heaters, and items where the consequences of
failure are negligible.
Traditional PM is keyed to failure rates and times between failures. It assumes that these
variables can be determined statistically, and therefore one can replace a part due for failure
before it fails. The availability of statistical failure information tends to lead to fixed schedules
for the overhaul of equipment or the replacement of parts subject to wear. PM is based on the
assumption that the overhaul of machinery by disassembly and replacement of worn parts
restores the machine to a like-new condition with no harmful effects. In addition, this renewal
task is based on the perception new components are less likely to fail than old components of the
same design. See Figures 1–2 and 2–3.
For some items, while failure is related to age, it is not equally likely to occur throughout the life
of the item. In fact, the majority of equipment is not subject to wear-out (sharply increasing
conditional probability of failure at a specific operating age). Therefore, timed maintenance can
often result in unnecessary maintenance. In summary, PM can be costly and ineffective when it
is the sole type of maintenance practiced.
3.2.2.1 PM Tasks
Although numerous ways have been proposed for determining the correct periodicity of
preventive maintenance tasks, none are valid unless the in-service age-reliability characteristics
of the system or equipment affected by the desired task are known. This information is not
normally available and must always be collected for new systems and equipment. PT&I
techniques should be used as an aid in determining equipment condition vs. age.
Careful analysis of similar kinds of hardware in industry has shown that, overall, more than 90%
of the hardware analyzed showed no adverse age-reliability relationship. This does not mean
that individual parts do not wear; they do. It means that the ages at failure are distributed in such
a way that there is no value in imposing a preventive maintenance task. In fact, in a large
number of cases, imposing an arbitrary preventive task increases the average failure rate through
“infant mortality.”
The Mean Time Between Failures (MTBF) is often used as the initial basis for determining PM
interval. This approach is incorrect in that it does not provide any information about the effect of
increasing age on reliability. It provides only the average age at which failure occurs, not the
most likely age. In many cases a Weibull distribution, as used by the bearing industry to specify
bearing life, will provide more accurate information on the distribution of failures.
The best thing that can be done if good information on the effect of age on reliability is not
available, is to monitor the equipment condition.
For some equipment, failure history and personal experience provide an intuitive feel as to when
equipment failure may be expected. In these cases, failure is time related. The monitoring
periodicity should be selected such that there are at least three monitoring intervals before the
anticipated onset of failures. It is prudent in most cases to shorten the monitoring interval as the
wear-out age is approached.
In using statistics to determine the basis for selecting task periodicity, the distribution and
probability of failure should be known. Weibull distributions can provide information on the
probability of an equipment exceeding some life. For example, bearings are normally specified
by their B10 life; i.e., the number of revolutions that will be exceeded by 90% of the bearings.
The most common practice in industry is to monitor the equipment biweekly or monthly due to a
lack of information and poor monitoring techniques. This often results in excessive monitoring.
In these cases, significant increases in the monitoring interval may be made without adverse
impact on equipment reliability.
When indications of impending failure become apparent through trending or other predictive
analysis methods, the monitoring interval should be reduced and additional analysis should be
performed in order to gain more detailed information on the condition of the equipment.
The PT&I data collected is used in one of following ways to determine the condition of the
equipment and identify the precursors of failure. The methods of analysis include:
• Trend analysis
• Pattern recognition
• Data comparison
PT&I does not lend itself to all types of equipment or possible failure modes and therefore
should not be the sole type of maintenance practiced.
Figure 3–1 depicts a simplified Chilled Water System and the various components that can be
monitored using the aforementioned correlated PT&I technologies. For example, a chilled water
system would require the following PT&I techniques to be used for the entire system to be
evaluated:
j. Eddy Current—Eddy current would be used to determine and locate leaking tubes.
• Failed-part analysis
• Reliability engineering
• Rebuild certification/verification
• Age Exploration
• Recurrence Control
A proactive maintenance program is the capstone of the RCM philosophy. The seven most
commonly recognized proactive techniques listed above are described in the following.
To solve this problem, reliability engineers must write proper specifications, test the equipment
of different vendors, and document problems. These specifications should include, as a
minimum, vibration, alignment, and balancing criteria. Documenting historical data, so
engineers can write verifiable purchasing and installation specifications for new and rebuilt
equipment, is the basis of this proactive technique. Performance testing is then conducted (1) in
the factory prior to shipment, (2) as the equipment is installed prior to acceptance, and (3) to
establish a performance baseline as the equipment begins operation.
In addition, the use of PT&I for measuring equipment condition are not normally contained in
the procurement specifications. It is rare to see a banded-vibration criteria, a quantifiable
alignment/ balance specification, or a complex phase impedance for an electric motor.
3.4.2.1 Balance
Bearings are the machine components that support and transfer the forces from the rotating
element to the machine frame. This results in the perception that bearings are inherently a
reliability problem due to the fact that only 10% to 20% of rolling element bearings achieve their
design life. One of the leading causes of premature rolling element bearing failure is parasitic
load due to excessive vibration caused by imbalance and misalignment. The resulting parasitic
loads result in increased dynamic loads on the bearings. The design formulas (SKF, 1973) used
to calculate theoretical rolling element bearing life are:
a. Ball Bearings
16,667 C
L10 Life Hours = ( ) X ( )3
RPM P
b. Roller Bearings
16,667 C 10
L10 Life Hours = ( ) X ( )9
RPM P
Where, L10 is the number of hours 90% of a group of bearings should attain or exceed under a
constant load (P) prior to fatigue failure; C is the bearing load which will result in a life of one
million revolutions; and P is the actual bearing load, static and dynamic. C is obtained from a
bearing manufacturer’s catalogue and P is calculated during equipment design.
As shown, bearing life is inversely proportional to speed and more significantly, inversely
proportional to the third power of load for ball and to the 10/9 power for roller bearings.
Vr
Ur = xM
Ve
Where Ur is the amount of residual imbalance, Vr is the actual imbalance, Ve is the trial mass
imbalance, and M is the trial mass. This equation can be expressed as follows:
Permissible imbalance is related to equipment type and rotor mass. In general, the greater the
rotor mass, the greater the permissible imbalance. The following equation can be used to
determine the relationship between permissible residual imbalance (Uper) based on the rotor mass
(m) and a required or target permissible imbalance (eper):
U per
e per =
m
The relationship between speed and imbalance can be expressed by the following equation:
e per x ω = a constant
Table 3–3 below contains the ISO1940/1-1986 balance quality grades for various groups of
representative rigid rotors.
9
The following equations and discussion of permissible imbalance is based on ISO 1940/1, Mechanical vibration—
Balance quality requirements of rigid rotors. 1986
Product of
Balance The
Quality Relationship Rotor Types—General Examples
Grade (eper x ) 1,2
mm/s
Product of
Balance The
Quality Relationship Rotor Types—General Examples
Grade (eper x ) 1,2
mm/s
Flywheels
Pump impellers
Machine-tool and general machinery parts
Medium and large electric armatures (of electric motors
having at least 80 mm shaft height) without special
requirements
Small electric armatures, often mass produced, in
vibration insensitive applications and/or with vibration
isolating mountings
Individual components of engines under special
requirements
Gas and steam turbines, including marine turbines
(merchant service)
Rigid turbo-generator rotors
Computer memory drums and discs
Turbo-compressors
G2.5 2.5 Machine-tool drives
Medium and large electric armatures with special
requirements
Small electric armatures not qualifying for one or both of
the conditions specified for small electric armatures of
balance quality grade G6.3
Turbine-driven pumps
Tape recorder and phonograph (gramophone) drives
G1 1 Grinding-machines drives
Small electric armatures with special requirements
Table 3–3. Balance Quality Grades for Various Groups of Representative Rigid Rotors (ISO
1940/1-1986)
Notes:
1. ω=2πn/60≈n/10, if n is measured in revolutions per minute and ω is in radians per
second
2. For allocating the permissible residual unbalance to correction planes.
3. A crankshaft/drive is an assembly which, includes a crankshaft, flywheel, clutch,
pulley, vibration damper, rotating portion of connecting rod, etc.
4. For the purposes of this part of ISO 1940, slow diesel engines are those with a piston
velocity of less than 9 m/s; fast diesel engines are those with a piston velocity of
greater than 9 m/s.
5. n complete engines, the rotor mass comprises the sum of all masses belonging to the
crankshaft/drive described in note 3 above.
Calculate the amount of centrifugal force due to imbalance as shown below, where:
mr(2πf )2
F = mA = mr ω 2 = = 0.102 mrf 2
g
F = Force
m = imbalance (lbs)
r = radius of imbalance (in)
f = rotational speed (Hz)
g = 386.4 in/sec2
1
F = 0.102 x ( ) x (12) x (60 )2 = 275 lbs.
16
Thus, 1 oz. of imbalance on a 12" radius at 3600 RPM creates an effective centrifugal force of
275 lbs. Now calculate the effect of this weight on bearing life. Suppose that the bearings were
designed to support a 1000 lb. rotor. The calculated bearing life is less than 50% of the design
life as shown below.
1000 3
Actual L 10 Life = (Design L 10 Life) x ( )
1000 + 275
= 0.48 Design L 10 Life
3.4.2.4 Alignment
The forces of vibration from misalignment also cause gradual deterioration of seals, couplings,
drive windings, and other rotating elements where close tolerances exist. The use of precision
equipment and methods, such as reverse dial and laser systems to bring alignment tolerances
within precision standards, is recommended. Contrary to popular belief, both laser alignment
and reverse dial indicator equipment offer equal levels of precision; however, laser alignment is
considerably easier and quicker to learn and use. Recommended specifications for precision
alignment are provided in Table 3–4.
Tolerance
Maximum Angularity
Coupling Type Horizontal & Vertical
Speed (RPM) (Inch/10 inch of
Parallel Offset (IN.)
Coupling Dia.)
600 0.005 0.010
900 0.0053 0.007
1200 0.0025 0.005
Short Coupling
1800 0.002 0.003
3600 0.001 0.002
7200 0.0005 0.001
600 0.005 N/A
Coupling with 900 0.0018 N/A
Spacer 1,200 0.0012 N/A
(Meåsurement
is per inch of 1,800 0.0009 N/A
spacer length) 3,600 0.0006 N/A
7,200 0.00015 N/A
In addition to the alignment specifications, Table 3–5 contains the following additional tolerance
recommendations.
Parameter Tolerance
Soft Foot 0.002" max
Foot Centerline Deformation (No load to full load) 0.001" max
Single Steel Base Plate Thickness 1.0" min
Foot Movement Caused by Pipe Flange Tightening 0.002" max
Total Shim Pack 5
Minimum Shim Pack Size 0.125" min
Axial Shaft Play 0.125" max
Table 3–6 and Figure 3–2 provide limitations and effect of misalignment on rolling element
bearings, respectively. The maximum acceptable misalignment is based on experience data in
bearing manufacturers’ catalogs.
Misalignment Angle
Bearing Type
Minutes Radians
Cylindrical Roller 3–4 0.001
Tapered Roller 3–4 0.001
Spherical Roller 30 0.0087
Deep Groove Ball 12–16 0.0035–0.0047
160
140
120
100
90
80
Percent of Standard Life
70
60
50
40
30
20
5 10 20
Misalignment (min.)
Bearings are generally the weakest equipment components. Only 10 to 20 percent of bearings
achieve their design life. The root causes of bearing failures may relate to improper installation,
poor lubrication practices, excessive balance and alignment tolerances, or poor storage and
handling techniques. Failed-bearing analysis provides methods to categorize defects such as
scoring, color, fretting, and pitting and to relate these findings to the most probable cause of
failure.
Over half of all bearing problems result from contamination or improper installation. While
indicators of contamination normally appear on the internal surfaces of bearings, indicators of
installation problems generally are evident on both internal and external surfaces.
While a PT&I program can identify most equipment faults at such an early stage that they never
lead to an equipment failure, the program often does not include discovering the underlying
reason for the faults. For example, a bearing may fail repeatedly because of excessive bearing
loads caused by an underlying misalignment problem. PT&I would most likely predict a bearing
failure and thus allow the bearing to be replaced before it fails, but if no one recognizes the
misalignment and eliminates it, conditions causing the failure will remain and failures will recur
and continue to require unnecessary corrective work and downtime.
RCFA proactively seeks the fundamental causes that lead to facility and equipment failure. Its
goals are to:
• Provide information that can help prevent the problem from recurring.
MTBF should be calculated from data collected from machinery history information stored in the
Computerized Maintenance Management Software. Other sources of MTBF data are operator
logs, parts usage, and contractor records. Reliability can be expressed by the following
reliability function:
R(t) = 1 - F(t)
where F(t) is the probability the system will fail by time t. F(t) is basically the failure distribution
function, or the “unreliability” function. If the random variable t has a density function of f(t),
then the expression for reliability is:
Assuming that the time to failure is described by an exponential density function, then
f(x) = 1/L(e-t/L)
where L is the mean life, t is the time period of interest and e is the natural logarithm base
(2.7183...). The reliability at time t is:
Mean life (L) is the arithmetic average of the lifetimes of all items considered. The mean life (L)
for the exponential function is equivalent to mean time between failures (MTBF).
Where, F is the instantaneous failure rate and M is the MTBF. If an item has a constant failure
rate, the reliability of that item at its mean life is approximately 0.37. In other words, there is a
37% probability that a system will survive its mean life without failure. Mean life and failure
rates are related by
Fr = 1/L
b. Failure Rate
The rate at which failures occur in a specified time interval is called the failure rate
during that interval. The failure rate (Fr) is expressed as:
Example:
Unit Failed at time (operating hours)
1 75
2 125
3 130
4 325
5 525
All five units operated for 525 hours following failure for a total of 2,625 hours. In addition Unit
1 experienced failure at 75 hours, Unit 2 at 125 hours, Unit 3 at 130 hours, Unit 4 at 325 hours,
and Unit 5 at 525 hours.
When assuming the negative exponential distribution, the failure rate is assumed to be relatively
constant during normal system operation if the system design is mature. That is, the system is
operating beyond the infant mortality period of decreasing failure rate and either before the wear
out region of increasing failure rate, or as in the majority of cases a period of increasing failure
rate does not exist.
1. Series networks
In a series network each component is a single point of failure. For example, there is
normally only one labeler for each packaging line. If the labeler fails, the line stops.
If a series configuration is expected to operate for a specified time period, its overall reliability
can be derived.
RS = e-(l +l +...+l )t
2. Parallel networks
In a parallel network, multiple redundant equipment exists. For example, parallel packaging
lines and/or redundant chilled water pumps.
3. Series-parallel networks
Figure 3–3 provides examples of how to calculate network reliability for series and parallel
components within a system. As with electrical circuits, analyze the parallel portions to create
an equivalent and then complete the analysis by combining all components and equivalents
serially.
1. Availability (A)
(1) The probability that a system or equipment, when used under stated
conditions in an ideal support environment, will operate satisfactorily at
any point in time as required.
(1) The probability that a system or equipment, when used under stated
conditions in an ideal support environment, will operate satisfactorily at
any point in time.
(2) Preventive (scheduled) maintenance is included.
(3) Excludes logistics delay time and administrative delay time.
(1) The probability that a system or equipment, when used under stated
conditions in an actual operational environment, will operate satisfactorily
when called upon.
(2) Includes active maintenance time, logistics delay time and administrative
delay time.
e. `Weibull Distributions
The Weibull distribution is generally used to determine probability of the failure due to fatigue.
The original work was conducted in 1933 and titled, A Statistical Theory of the Strength of
Materials. While the original work was not directly related to bearings, it was modified in 1947
by Lundberg and Palmgren (Lundberg, 1947) to account for the effectiveness of the lubricant
and the fact not all cracks propagate to the bearing surface.
The importance of the Weibull distribution is that the fatigue behavior of a group of identical
bearings can be assessed and changes in the failure distribution used to identify the introduction
of new sources of failure, i.e., changes in operating condition, lubrication/installation practices,
etc.
k
F(t) = 1 - e-(t/T)
where, F(t) is the failure probability, T is the point in time at which 63.2% of the bearings have
failed, and k is corresponds to the gradient. The value of k for bearings is 10/9 for ball bearings
and 27/20 for roller bearings. In addition, F(t) for bearings should be in the range of 0.07-0.60.
In order to use the Weibull distribution to determine failure probability for bearings, it is
necessary to have a minimum of ten (10) identical bearings operating under as close to identical
conditions as possible.
The AE process examines the applicability of all maintenance tasks in terms of the following:
a. Technical Content—The technical content of the tasks are reviewed to ensure all
identified failure modes are addressed and that the existing maintenance tasks
produce the desired amount of reliability.
Repetitive failures are defined as the recurring inability of a system, subsystem, structure or
component to perform the required function, i.e.:
a. Monitor performance and identify failures by reviewing Trouble Calls and machinery
history contained in the CMMS and PT&I databases.
2. Component monitoring will identify possible generic failure problems that may
affect multiple plant systems.
4. Provide a schedule which allows for effective feedback and timely completion
of the task.
f. Analyze the problem and recommend corrective action based on the following:
Ser.#: Location:
Parts Replaced:
Labor: $ $ $
Material: $ $ $
Total Cost: $
Individual system reliability and M&O costs, number of Trouble Calls normalized to operating
hours and plotted over service life can be tracked by the CMMS. Equipment condition relative
to other similar equipment can be tracked by reviewing the PT&I data and statistically
determining the selected component relationships with respect to the mean and standard
deviation. For example, a facility has X number of centrifugal water pumps of similar but not
identical design in the range of 15–25 Hp. All of the pumps receive quarterly vibration
monitoring, which includes a visual inspection, and annual insulation resistance check or motor
circuit test. The insulation resistance checks are temperature corrected so they may be trended.
In addition, where possible, flow and/or discharge pressure are noted during the vibration
surveys and trended.
Each pump/motor combination is assigned a value of 1, 4, or 9 based on its relationship with the
mean. For example, as illustrated in Figure 3-5, 50% of the equipment would be in better
condition than the mean, 68.3% better than the mean plus 1 σ (sigma), 95.4% better than the
mean plus two σ (sigma), and 99.7% better than the mean plus three σ (sigma).
Mean + 2 sigma
Mean + 3 sigma
f(x)
For example, if the vibration amplitude is below mean + 1σ (sigma) the unit would be scored as
1, below mean + 2σ it would be scored as 4, and above mean + 2σ it would be scored as a 9.
Table 3–7 provides an example.
For more complex equipment and/or for equipment where more PT&I technologies are used, the
table would be expanded. In addition, similar Tables should be prepared for Trouble
Calls/Repairs normalized to operating hours, M&O costs, PT&I alarms normalized to operating
hours, Availability, etc. The sum of all the Tables will result in a rank ordering of the equipment
in terms of condition. This approach will address the functional condition in terms of availability
and cost to maintain function.
Structures can be treated in a similar manner. In these cases, a periodic inspection by the Facility
Manager of the common spaces, hallways, equipment rooms, roofs, and grounds combined with
PT&I data from thermography, airborne ultrasonics, etc.
While the preceding technique is appropriate for equipment and structures, private spaces, such
as offices, should be handled by the user. A form similar to Figure 3-6 can be used to obtain user
input and address more subjective issues related to morale and appearance.
The office user should fill out a form similar to Figure 3 – 6 on an annual or semiannual basis to
identify problems with the space. This information is then used to generate a work order which,
can be prioritized and tracked.
DESK
Comments:____________________________________________________________________________
____________________________________________________________________________
____________________________________________________________________________
____________________________________________________________________________
Work Control No.
Date Received
Date Cleared
Signature
4.1 Introduction
This chapter describes each of the primary PT&I technologies in terms of its purpose,
techniques, application, effect, equipment required, operators, training available, and cost.
A variety of methods are used to assess the condition of systems/equipment to determine the
most effective time to schedule and perform maintenance. The information below provides an
introduction on how the technologies are currently utilized and their respective benefits. These
technologies include both intrusive and non-intrusive methods as well as the use of process
parameters to determine overall equipment condition. The data acquired permits an assessment
of system/equipment performance degradation from the as designed and/or required condition.
In addition, these techniques should also be used to assess the quality of new and rebuilt
equipment installations and operational checks. The approaches covered include:
Figure 4–1 provides information on the applicability of the technologies to various facility and
production components. Data should be correlated as described in Section 3 and Appendix F.
a. Arbitrary Value—Set an arbitrary value for change from a baseline value. In this
situation an increase in the reading by a predetermined amount over the initial
reading is used to determine maintenance requirements. This approach was widely
used by the U.S. Navy submarine force until the middle 1980s at which time it was
abandoned in favor of a more statistical approach as described below.
HEAVY EQUIPMENT/CRANES
ELECTRICAL SYSTEMS
APPLICATIONS
DIESEL GENERATIORS
HEAT EXCHANGERS
CIRCUIT BREAKERS
ELECTRIC MOTORS
TRANSFORMERS
TANKS, PIPING
CONDENSERS
VALVES
PUMPS
TECHNOLOGIES
VIBRATION MONITORING/ ANALYSIS l l l l
LUBRICANT, FUEL ANALYSIS l l l l l
WEAR PARTICLE ANALYSIS l l l l
BEARING, TEMPERATURE/ANALYSIS l l l l
PERFORMANCE MONITORING l l l l l l
ULTRASONIC NOISE DETECTION l l l l l l l l
ULTRASONIC FLOW l l l l
INFRARED THERMOGRAPHY l l l l l l l l l l
NON-DESTRUCTIVE TESTING
(THICKNESS) l l l
VISUAL INSPECTION l l l l l l l l l l l
INSULATION RESISTANCE l l l l l
MOTOR CURRENT SIGNATURE
ANALYSIS l
MOTOR CIRCUIT ANALYSIS l l l
POLARIZATION INDEX l l l
ELECTRICAL MONITORING l l
Figure 4-1. PT&I Applications
c. Failure Analysis—Refine the alert and alarm values by performing analysis of the
failed parts and then correlating the as-found condition to the PT&I data. This is
why it is important to document trends, the values at which failures occur, and the
operating environment for future reference. Changing the alert and alarm values is
the mechanism to fine tune the condition monitoring process and should be based
on the best information available.
Machinery and system vibration is the periodic motion of a body about its equilibrium position.
For example, imagine driving a car at a constant speed through a series of potholes with each one
being larger than the last. The shock and resulting vibration increases with each encounter until
at some point it destroys the suspension, wheel, or tire. This analogy depicts what occurs as
bearing and gear defects begin and then increase in size with each additional impact.
4.2.1.3 Accuracy
Studies by the U.S. Navy have found probabilities of detection as high as 0.92 and as low as
0.76. The corresponding false alarm rate was found to be 0.08. Selecting the appropriate
monitoring intervals and alarm criteria optimizes probability of detection and false alarm rates.
equipment failures (due to mechanical degradation) prior to failure. Waveform analysis, or time
domain analysis, is another extremely valuable analytical tool. While not employed as regularly
as spectrum analysis, the waveform often aids the analyst in a more correct diagnosis of the
machine problem.
The practice of using a hand-held probe severely limits the upper vibration frequency that can be
accurately measured. When combined with the failure to mark the measurement points and the
use of different individuals to collect data, the repeatability of the vibration data analysis
significantly decreases.
The discs are to be manufactured from a magnetic stainless steel such as alloy 410 or
416.
Identify each monitoring point and epoxy magnetic corrosion resistant steel discs (sound discs)
at every location. Sound discs should be a minimum of one inch in diameter and 3/16 to 3/8 inch
thick. The discs can be purchased10 with prices ranging from $0.25 to $6.00 each or can be
manufactured by fly cut from 1" alloy 410 or 416 bar stock. Figure 4–2 provides a dimensional
drawing of a sound disc. The surface finish should be a minimum 63 micro-inch. Good
frequency response is more related to placing the magnet on a clean surface with a lubricant
between the magnet and the disk than a highly polished surface. When using a stud to mount the
accelerometer directly to the disk or finished surface, the minimum surface finish is 32 micro-
inch. The disk or surface face must be level to prevent the magnet from rocking. Surface must
be level within 1 degree or .001 inch.
Use a tested epoxy such as Hysol Gray Epoxy Patch (available from Structural Adhesives) or
Loctite Depend 330 to adhere the sound disc to the equipment. Prepare the surface for the epoxy
by grinding or spot facing with a portable milling machine and wiping down with a solvent. If
the portable milling machine is used to spot face the surface, ensure that the face diameter is
¼ inch in diameter larger than the disc diameter. The use of superglue type adhesives is not
recommended, the sound discs do not adhere well when this type adhesive is used. Wielding the
discs to the machine is also an option, but it is not recommended because of possible damage to
the machine and distorting of the disc surface.
As an alternative, the monitoring locations may simply be the spot faced area machined on the
equipment surface. The same conditions identified for the sound disc apply to the machined
surface.
10
Michoud Assembly Facility gets inexpensive sound discs from a washer supplier. They simply special order the
washers without holes. Supplier is Phoenix Specialty Mfg.. Co., PO Box 418, Bamberg, SC 29003 Phone 800-845-
2813, fax 803-245-5734. Be sure to specify "washers with no holes."
The sound disc or machined surface should be marked (using a label or plate) "Vibration data
collection point - Do Not Paint"
4.2.2 Limitations
The effectiveness of vibration monitoring is dependent on sensor mounting and resolution, the
analyst’s knowledge and experience, machine complexity, and data collection techniques.
Complex, low speed (<120 RPM), variable speed, and reciprocating machinery are extremely
difficult to monitor effectively.
Additionally, single channel analysis cannot always accurately determine the source of the
vibration on complex machines.
4.2.3 Logistics
4.2.3.2 Operators
• Requires personnel who have the ability to understand the basics of vibration
theory and who have a basic knowledge of machinery and failure modes.
• Staffing requirements are site specific
IRT inspections are identified as either qualitative or quantitative. The quantitative inspection is
interested in the accurate measurement of the temperature of the item of interest. To perform a
quantitative inspection requires detailed knowledge and understanding of the relationship of
temperature and radiant power, reflection, emittance, environmental factors, and the detection
instrument limitations. This knowledge and understanding must be applied in a methodical
fashion to properly control the imaging system and obtain highly accurate temperature
measurements. Quantitative inspections are rarely needed in facilities applications.
The qualitative inspection is interested in relative differences, hot and cold spots, and deviations
from normal or expected temperature ranges. The knowledge and understanding discussed
above is needed in order to perform a meaningful inspection. However, qualitative inspections
are significantly less time consuming because the thermographer is not concerned with highly
accurate temperature measurement. What the thermographer does obtain is highly accurate
temperature differences (∆ T) between like components. For example, a typical motor control
center will supply three-phase power, through a circuit breaker and controller, to a motor.
Current flow through the three-phase circuit should be uniform which means that the
components within the circuit should have similar temperatures, one to the other. Any uneven
heating, perhaps due to dirty or loose connections, would quickly be identified with the IRT
imaging system. Because the many variables that influence the quantitative inspection
(reflection, emittance, etc.) are the same between like components, the thermographer can
quickly focus on the temperature differences. The factors so important to a highly accurate
temperature measurement have very little influence on the temperature differences between like
components.
4.3.1 Applications
IRT can be utilized to identify degrading conditions in facilities electrical systems such as
transformers, motor control centers, switchgear, substations, switchyards, or power lines. In
mechanical systems, IRT can identify blocked flow conditions in heat exchanges, condensers,
transformer cooling radiators, and pipes. It can also be used to verify fluid level in large
containers such as fuel storage tanks and identify insulation system condition in building walls
and roof or refractory in boilers and furnaces. Temperature monitoring, infrared thermography
in particular, is a reliable technique for finding the moisture-induced temperature effects that
characterize roof leaks and for determining the thermal efficiency of heat exchangers, boilers,
building envelopes, etc.
Deep-probe temperature analysis can detect buried pipe energy loss and leakage by examining
the temperature of the surrounding soil. This technique can be used to quantify energy losses
and their cost. IRT can also be used as a damage control tool to locate mishaps such as fires and
leaks. Unless requested otherwise, the thermographer will normally only provide an exception
report consisting of finds/faults.
In-service condition for electrical and mechanical systems can be assessed and work prioritized
based upon the temperature difference criteria (∆T) guideline. IRT criteria are provided in
Section 8.2.3.
4.3.2 Limitations
Thermography is limited to line of sight. The infrared camera has limited ability to see through
material. Most items that are usually considered transparent to the human eye, such as glass and
plastic, are opaque to the infrared camera. Errors can be introduced due to type of material,
material geometry, and by environmental factors such as solar loading and wind effects.
4.3.3 Logistics
4.3.3.2 Operators
• Operators and mechanics can perform temperature measurements and analysis
using contact-type devices with minimal training on how and where to take the
temperature readings.
• Because thermographic images are complex and difficult to measure and analyze,
training is required to obtain and interpret accurate and repeatable thermal data
and to interpret the data. With adequate training (Level I and Level II) and
certification, electrical/mechanical technicians and/or engineers can perform this
technique.
a. Tone Generator—An ultrasonic source is placed inside the area to be tested (one
tone generator required for each 4,000 cubic feet of volume), the instrument is set
on scanning mode, log position, and fixed band. The tone generator can be
attached to an adapter at the end of a pipe to flood the pipe, heat exchanger shell,
or tube bundle with ultrasonic noises. A scan is then performed on the pipe or
tubes.
4.4.1.3 Boilers
Boiler casing surveys should be performed using the blowdown valves; the test equipment’s
fixed band, and the contact probe.
For facilities with a periodic steam trap monitoring program, the following distribution of
degradations were discovered during each survey:
The numbers above can be used to estimate the number of leaks for a facility and combined with
the data in Table 4 – 1 then used to approximate the total steam loss due to the steam leaks.
Once the estimated amount of steam loss is calculated, the cost of producing or buying a pound
of steam should be calculated. The following should be considered when calculating the cost of
producing steam:
• Cost of fuel
• Operator cost
• Maintenance cost
• Chemical treatment cost
• Depreciation of steam plant
Steam traps should be monitored on the downstream side of the trap using the test equipment’s
contact mode, if applicable, in the 25kHz band and the log position. Each type of steam trap
produces a distinct sound as briefly described below. To gain experience with the difference in
the sound produced by steam and condensate, the operator should listen to a condensate and a
steam line.
a. Intermittent Traps—The operator will hear an opening and closing sound. The trap
normally fails in the open position, producing a continuous, rushing sound.
d. Float and Thermostatic (Continuous Load)— Flow and noise associated with these
traps are usually modulated. Failed traps are normally cold and silent.
e. Continuous Flow—This type of trap, when operating normally, produces the sound
of condensate flow only. If it has failed in the open position, a continuous flow sound
should be heard.
4.4.1.5 Bearings
Airborne ultrasonics can be used to detect bearing problems but it is not the preferred method.
Vibration analysis is recommended.
4.4.2 Limitations
Airborne ultrasonics are subjective and dependent on perceived differences in noises. To
maximize the usefulness of this technology, care should be taken when setting test equipment
controls for frequency ranges, sensitivity, and scale. Additionally, the operator should be
cognizant of the fact that piping bends and the presence of moisture and solids may dissipate
and/or block the ultrasonic signal.
4.4.3 Logistics
4.4.3.2 Operators
Maintenance technicians and engineers.
4.5.1 Purpose
Lubricating oil analysis is performed for three reasons: to determine the machine mechanical
wear condition, to determine the lubricant condition, and to determine if the lubricant has
become contaminated. There are a wide variety of tests that will provide information regarding
one or more of these areas. The test used will depend on the test results sensitivity and accuracy,
the cost, and the machine construction and application. Note that the three areas are not
unrelated as changes in lubricant condition and contamination, if not corrected, will lead to
machine wear. Because of the important relationships, commercial analysis laboratories will
often group several tests in cost effective “packages” that provide information about all three
areas.
following “topping off” or reconditioning the oil is performed. The root cause of any oil
contamination needs to be determined and eliminated in order to avoid machine damage.
Lubricating oil analysis is performed on in-service machines to monitor and trend emerging
conditions, confirm problems identified through other PT&I and observations, and to
troubleshoot known problems. As previously discussed, lubricating oil analysis is performed for
three reasons: to determine the machine mechanical wear condition, to determine the lubricant
condition, and to determine if the lubricant has become contaminated. Tests have been
developed to address indicators of these conditions and vary in cost dependent upon time and
materials needed to accomplish the testing. The tests selected for use in the PT&I program must
balance the need for understanding the lubrication condition and the cost of the testing.
4.5.2.2 Viscosity
Indicates oil flow rate at a specified temperature. An increase or decrease in viscosity over time
measures changes in the lubricant condition or lubricant contamination. Viscosity can be tested
using portable equipment, or more accurately in a laboratory using ASTM D445 procedure.
Viscosity is measured in Centistoke (cSt) and minimum and maximum values are identified by
ISO grade. Testing is usually part of a commercial laboratory standard test package.
4.5.2.3 Water
Water in lubricating oil and hydraulic fluid contributes to corrosion and formation of acids.
Small amounts of water (less than 0.1%) can be dissolved in oil and can be detected using the
crackle test or infrared spectroscopy (minimum detectable is .05% or approximately 500 PPM;
both methods), the ASTM D95 distillation method (minimum detectable is .01%/100 PPM), or
the ASTM D1744 Karl Fischer method (minimum detectable is .001%/10 PPM). Greater than
0.1% water, if suspended or emulsified in the oil, will appear cloudy or hazy. Free water in oil
collects in the bottom of reservoirs and can be found by draining from the bottom.
12
Annual Book of ASTM Standards, Section 5, Petroleum Products, Lubricants, and Fossil Fuels, American Society
for Testing and Materials
4.5.3.3 Foaming
Some oil may have anti-foam agents added to improve the lubrication capability in specific
applications such as gearboxes or mixers. ASTM test D892 can be used to test the oils foam
characteristics. The test blows air through a sample of the oil and then the foam volume is
measured. Cost of the test is moderately high.
4.5.4 Application
All machines with motors 7.5 HP or larger, and critical or high cost machines should be
evaluated for routine lubricating oil analysis. The analysis schedule should be adjusted in the
same way that the vibration analysis schedule is adjusted. It is important that there is a dynamic
process for addressing the adjustment of periodicity for all equipment in both the PM and PT&I
programs. Analyze more frequently for machines that are indicating emerging problems; less
frequently for machines that have stable conditions and are not run on a continuous basis. A new
baseline analysis will be needed following machine repair or oil change out. All hydraulic
systems, except mobile systems, should be analyzed on a quarterly basis. Mobile systems should
be considered for analysis based upon the machine size and the cost effectiveness of performing
the analysis. Generally speaking, it is more cost effective in mobile equipment to maintain the
hydraulic fluid based upon the fluid condition. However, for small systems, the cost to flush and
replace the hydraulic fluid on a time basis may be lower than the cost to analyze the fluid on a
routine basis. Grease is usually not analyzed on a regular basis. Although most of the testing
that is done on oil can also be done on grease, there is a problem getting a representative sample.
In order to get a representative sample- one that is a homogeneous mixture of the grease,
contaminants, and wear- the machine must usually be disassembled. Analysis of grease to
diagnose a failure can sometimes be useful.
A concern common to all machines with lubricating oil systems is keeping dirt and moisture out
of the system. Common components of dirt, such as silica, are abrasive and naturally promote
wear of contact surfaces. In hydraulic systems, particles can block and abrade the close
tolerances of moving parts. Water in oil promotes oxidation and reacts with additives to degrade
the performance of the lubrication system. Ideally, there would be no dirt or moisture in the
lubricant; this, of course, is not possible. The lubricant analysis program must therefore monitor
and control contaminants. Large systems, with filters, will have steady state levels of
contaminates. Increases in contaminates indicate breakdown in system integrity (leaks in seals,
doors, heat exchangers, etc.) or degradation of the filter. Unfiltered systems can exhibit steady
increases during operation. Operators can perform a weekly visual and odor check of lubricating
systems and provide a first alert to contamination. Some bearing lubricating systems have such a
small amount of oil that a weekly check may be impractical.
For machines with more than 5 gallons of oil in the system, add infrared spectroscopy (minimum
amount of water detectable is .05%) and particle counting. Changes in particle count can
indicate increased contamination or increased wear; correlate particle count with spectrometric
metals. The rate of particle count change indicates how quickly the lubricant is degrading.
Visual particle counting can be used to identify the source of the contamination. In addition,
perform DR ferrography for high cost or critical machines. In all machines, changes in
spectrometric metals or DR should be investigated further using analytical ferrography and
correlated with vibration analysis.
4.5.4.2 Gearboxes
Same as above, with the following additions. For all gearboxes, including those with less than 5
gallons of oil, add particle counting. Include DR ferrography for high cost or critical gearboxes.
Monitor trends and correlate with vibration readings.
4.5.4.3 Chillers
In addition to the items identified above, add TAN and Direct Read ferrography.
4.5.4.5 Compressors
Centrifugal compressors; same as chillers. Reciprocating compressors; same as diesel engines.
4.5.5 Sampling
Oil samples must be collected safely and in a manner that will not introduce dirt and other
contaminates into the machine/system or into the sample. It may be necessary to install
permanent sample valves in some lubricating systems to do this. The oil sample should be
representative of the oil seen in the machine. The sample should, therefore, be collected from a
mid-point in reservoirs and prior to filtering in circulating systems. Sample collection bottles
and tubing can be procured through testing laboratories. The testing laboratory will also be able
to provide guidance as regards to the cleanliness level needed. Oil sample pumps for extracting
oil from reservoirs must be used properly to avoid contamination. Samples must be collected
from the same point in the system in order to assure consistency in the test analysis; therefore,
the maintenance procedure must provide detailed direction on where and how to collect samples.
The equipment operators can collect samples. Each sample is marked with the system/machine
name, sample location point (the system may have multiple sample points), date, elapsed
operating time for the system/machine, and other comments such as last “topping off” or filtering
operation. The analyst will also need to know the amount of oil in the reservoir in order to make
recommendations to correct abnormalities.
Monitoring key electrical parameters provides the information to detect and correct electrical
faults such as high resistance connections, phase imbalance and insulation breakdown. Since
faults in electrical systems are seldom visible, these faults are costly (increased electrical usage),
present safety concerns (fires) and life cycle cost issues (premature replacement of equipment).
According to the Electric Power Research Institute13, voltage imbalances of as little as 5% in
motor power circuits result in a 50% reduction in motor life expectancy and efficiency in 3 phase
AC motors. A 25% increase in motor temperatures can be generated by the same 5% voltage
imbalance accelerating insulation degradation.
4.6.1 Techniques
• Infrared Thermography
• Insulation Power Factor Testing
• Insulation Oil Analysis
13
EPRI is a nonprofit membership corporation, established by U.S. electric utilities, to manage a national research
program on behalf of its members.
• Gas-in-Oil Analysis
• Megohmmeter Testing
• High Potential Testing (HiPot)
• Airborne Ultrasonics
• Battery Impedance Testing
• Surge Testing
• Motor Circuit Analysis (MCA)
• Motor Current Signature (Spectrum) Analysis
• Very Low Frequency Testing (VLF)
• Circuit Breaker Timing Tests
• Circuit Breaker Contact Resistance
(Note: HiPot and surge testing should be performed with caution. The high voltage applied
during these tests may induce premature failure of the units being tested. For that reason these
tests are normally performed only for acceptance testing, not for condition monitoring.)
flowing to ground, also until such a time that the voltage level exceeds the voltage capacity of
the insulation.
Ic IT
Current (I)
)
V = Applied Voltage
IT= Total Current
IR = Resistive Current
IC = Capacitive Current
Dissipation Factor = tan)
Power Factor = cos2
IR
2
Referring back to Figure 4 - 4, it can be seen that IR is in phase with the applied voltage V and IC
is leading the voltage by a phase angle of 90 degrees. The total current is the resultant
combination of both IR and IC. The tangent of the angle between the applied voltage and
resultant current is called the dissipation factor and the cosine of the angle between the resultant
current and the capacitive current is called the power factor.
As the impedance of the insulation changes due to aging, moisture, contamination, insulation
shorts, or physical damage the ratio between IC and IR will become less. The resulting phase
angle between the applied voltage and resultant current then becomes less, and the power factor
will rise. Consequently, the power factor test is primarily used for making routine comparisons
of the condition of an insulation system. The test is non-destructive, and regular maintenance
testing will not deteriorate or damage insulation. It is one of the best electrical PT&I tests.
14
Annual Book of ASTM Standards, Section 5, Petroleum Products, Lubricants, and Fossil Fuels, American Society
for Testing and Materials
a. Karl Fischer, ASTM D-1533-88—Tests for water in insulating fluids. This test
reveals total water content in oil, both dissolved and free. High readings could indicate
a leak in the equipment housing or insulation breakdown.
e. Color, ASTM D-1524—as insulating oils in electrical equipment age, the color of the
oil tends to gradually darken. A marked color change from one year to the next could
indicate a deteriorating oil.
g. Power Factor, ASTM D-924—taken at 25 o C, this test can reveal the presence of
moisture, resins, varnishes, or other products of oxidation or foreign contaminates such
as motor or fuel oil. The power factor of new oil should always be below 0.05%.
h. Visual Examination, ASTM D-1524—insulating oil is clear and sparkling, not cloudy
and dull. Cloudiness indicates the presence of moisture or other contaminates. This is
a good “quick look” field test and can be used to trigger a Karl Fischer or Dielectric
Breakdown test.
combustible gas generation can change dramatically. In most cases these stresses can be
detected early on; the presence and quantity of the individual gases can be measured and the
results analyzed to indicate the probable cause of generation.
A small oil sample (50cc) is drawn from a transformer with a glass syringe15. To obtain a
reliable reading this must be accomplished with the unit energized. A transformer cools after
being taken off-line. As the transformer cools, dissolved gases in the oil will migrate into the
windings so the sample must be taken when the transformer is energized and at operating
temperature.
The oil is analyzed using ASTM D-3612-90, Standard Test Method for Analysis of Gases
Dissolved in Electrical Insulating Oil by Gas Chromatography. While there are over 200 gasses
present in insulating oils there are only nine that are monitored. They are:
• Nitrogen (N2)
• Oxygen (O2)
• Carbon Dioxide (CO2)
• Carbon Monoxide (CO)
• Methane (CH4)
• Ethane (C2H6)
• Ethylene (C2H4)
• Hydrogen (H2)
• Acetylene (C2H2)
Different combinations of these gasses reveal different conditions. Large amounts of CO and CO2
indicates overheating in the windings, CO, CO2, and CH4 show the possibility of hot spots in the
insulation, H2, C2H6, and CH4 are indicative of corona discharge, and C2H2 is a sign of internal
arcing. Various industry publications exist to help determine potential problems.
15
ASTM D3613 provides a detailed procedure. D3613, Standard Test Methods of Sampling Electrical Insulating
Oils for Gas Analysis and Determination of Water Content, American Society for Testing and Materials.
There are no set guidelines and limits for this test. Each type, style, and configuration of battery
will have its own impedance so it is important to take these measurements early in a battery's
life, preferably at installation. It should take less than an hour to perform this test on a battery
bank of 60 cells.
acceptance, go/no-go test. Data is provided as a comparison of waveforms between two phases
indicating the relative condition of the two phases with regard to the insulation system (short
circuits). Because of the repeated stress of the insulation system, Surge testing is not
recommended for routine condition monitoring.
The total resistance of a conductor is the sum of its resistance, capacitive and inductive
impedance. Accurate measurement of the conductor’s impedance allows minor degradations in a
motor to be detected and addressed prior to a failure. The condition of the insulation system can
be determined by measuring the capacitance between each phase and ground. The presence of
moisture or other conducting substance will form a capacitor with the conductor being one plate,
the insulation the dielectric, and the contaminate forming the second plate. Maintaining proper
inductive balance is imperative to efficient operation and realizing full lifetime of electrical
equipment. An electrical imbalance leads to elevated winding temperatures and reduced
insulation life.
MCSA can be performed in an indirect manner by measuring the magnetic flux produced by the
motor and analyzing the data using the FFT process to identify the presence of electrical fault
frequencies.
For in-service circuit breakers, a digital contact and breaker analyzer can be used to measure the
contact velocity, travel, over travel, bounce back, and acceleration to indicate the condition of the
breaker operating mechanism. A voltage is applied to the breaker contacts and a motion
transducer is attached to the operating mechanism. The breaker is then closed and opened. The
test set measures the timeframe of voltage changes, and plots the voltage changes over the
motion waveform produced by the motion transducer. The numbers are normally printed out
from the test set, and the chart is stored in memory for downloading into a computer.
Analyzing and trending this information allows for adjustments to the breaker operating
mechanism when necessary. This test is not applicable to molded case breakers or low voltage
breakers.
Most manufacturers of high and medium voltage circuit breakers will specify a maximum
contact resistance for both new contacts and in-service contacts. The contact resistance is
dependent on two things, the quality of contact area and the contact pressure. The contact
quality can degrade if the breaker is called upon to open under fault conditions. The contact
pressure can lessen as the breaker springs fatigue due to age or a large number of operations.
To measure the contact resistance a DC current, usually 10 or 100 amps, is applied through the
contacts. The voltage across the contacts is measured and the resistance is calculated using
Ohms law. This value can be trended and compared with maximum limits issued by the breaker
or switch manufacturer. It should be noted that for oil filled breakers, using a 100 amp test set is
recommended because oil tends to glaze on contact surfaces and, in some cases, 10 amps is not
enough current to overcome the glaze.
indicate the location of the discontinuity. This technology is used for power cables to help locate
faults within a cable run. The test is performed with the cable de-energized.
Harmonic distortion is a result of having non-linear loads on the power system. These loads
include laser printers, desktop computers, and SCRs found in variable speed motor controls.
High levels of harmonic current cause excessive heating in transformers and cables, which
reduce service life and cause spurious tripping of circuit breakers, which can be a major
inconvenience. A harmonic analyzer is used to measure the harmonic current and identify the
source. Filters can then be placed on the circuit to minimize the impact. This test is performed
with the system energized.
The test is performed by applying a voltage across the primary windings and measuring the
resulting voltage across the secondary winding. The ratio of active windings can be calculated.
This measurement can be used to determine the condition of the transformers inductive
capability. The turns ratio measurement can show that a fault exists but can not determine the
reason or location of the fault. This test is done with the transformer de-energized.
4.6.3 Applications
.4.6.3.4 Accuracy
Accuracy is dependent on the testing technique applied and rating of the instrument.
4.6.3.5 Limitations
The technologies presented can be divided into two categories:
Each technology will require specific initial conditions to be set prior to conducting the test. For
instance, prior to an Infrared Thermography survey, typical equipment powered through the
switchboard should be running to bring the distribution equipment to normal operating
temperatures. Higher load accentuates problem areas. Conducting the survey at low load
conditions may allow a problem to remain undetected.
4.6.4 Logistics
4.6.4.2 Operations
Electricians, electrical technicians, and electrical engineers should be trained in electrical PT&I
techniques such as motor current signature analysis, motor circuit analysis including complex
phase impedance and insulation resistance readings and analysis.
4.6.3.4 Cost
a. Equipment—Equipment costs vary from $20 for a simple multi-meter to
approximately $40,000 for integrated motor-current analysis (MCA) testers. A full
inventory of electrical testing equipment can cost in excess of $100,000.
b. Training—Training averages between $750 and $1,000 per week per person trained
for each technology.
Conduct
Define Establish Evaluate
Failure Modes
System Equipment Regulatory
& Effects
Boundaries Criticality Requirements
Analysis
Define
Establish
Information Evaluate
Failure Modes
Required Safety & Evaluate Cost
To Be
From Access Per Point
Addressed By
NDT Constraints
NDT
Technique
Select NDT
Technique Refer To
Determine Based on Establish Section XX To Document &
Skills Information, Sampling Establish Formalize
Requried Access, Cost Locations Sampling Program
& Skills Intervals
Requried
associated with welding of large high stress components such as pressure vessels and structural
supports. Process plants such as refineries or chemical plants use NDT techniques to assure
integrity of pressure boundaries for systems processing volatile substances.
4.7.1 Techniques
a. Radiography—Detection of deep sub-surface defects. Radiography or x-ray is one of
the most powerful NDT techniques available in industry. Depending on the strength of
the radiation source, radiography can provide a clear representation (radiograph) of
discontinuities or inclusions in material several inches thick. X-ray or gamma ray
sensitive film is placed on one surface of the material to be examined. The radiation
“source” is positioned on the opposite side of the piece. The source may be either a
natural gamma emitter or a powered X-ray emitter. The source is accurately aligned to
assure the proper exposure angle through the material (Figure 4–6). When all
preparations and safety precautions are complete, radiation source energized or
unshielded. The gamma or x-rays passing through the material to the film expose the
film.
Once the type, size and orientation of each inclusion are defined, these can be classified
into either acceptable inclusions or unacceptable defects.
Radiography, though a versatile tool, is limited by the potential health risks. Use of
radiography usually requires the piece be moved to a special shielded area (Figure 4–6)
or personnel evacuated from the vicinity to avoid exposure to the powerful radiation
source required to penetrate several inches of dense material. Temporary shielding may
also be installed, but the installation and removal of thousands of pounds of lead is
labor intensive. Radiography technicians are trained in radiation health physics and
material properties. These technicians can visually distinguish between welding slag
inclusions, porosity, cracking and fatigue when analyzing radiographic images.
Radiography Area
Shielded Walls
Radiation Hazard
Area
Radiation Source
Positions
Welded Radiographic
Joint Film
Three scan types are most commonly used; A Scan, B Scan and C Scan. A-Scan
systems analyze signal amplitude along with return time or phase shift as the signals
travel between a specific surface and discontinuities. B Scan systems add signal
intensity modulation and capability to retain video images. C Scan systems include
depth gating to eliminate unwanted returns.
UT inspection is a deliberate process covering a small area (four to eight square inches)
at each sampling. Consistency in test method and interpretation of results is critical to
the reliable test results. Surface preparation is also critical to reliable UT results. Any
surface defects such as cracks, corrosion, or gouges will adversely affect the reliability
of UT results.
Due to the time and effort involved in surface preparation and testing, UT inspections
are often conducted on representative sites such as high stress, high corrosion areas and
large welds. By evaluating the same sites at regular intervals, monitoring of the
condition of the material can be accomplished. 100% UT inspection is typically
reserved for original construction of high stress components such as nuclear reactor
vessels or chemical process vessels.
A major advantage for MT is its portability and speed of testing. The electrodes are
hand-held which allows the orientation of the test to be changed in seconds. This
allows for inspection of defects in multiple axes of orientation. Multiple sites can be
inspected quickly without interrupting work in the vicinity. The equipment is portable
and is preferred for on-site or in-place applications. The results of MT inspections are
recordable with a high quality photograph or transfer to tape. Fixing compounds are
available to “glue” the particle pattern in-place on the test specimen. Interpretation of
results is dependent on the experience of the operator.
Base Metal
fluid. The system is then sealed and pressure increased to approximately 1.5 times
operating pressure.
This pressure is held for a defined period. During the test, inspections are conducted
for visible leaks as well as monitoring pressure drop and make-up water additions. If
the pressure drop is out of specification, the leak or leaks must be located and repaired.
The principle of hydrostatic testing can also be used with compressed gases. This type
of test is typically called an air drop test and is often used to test the integrity of high-
pressure air or gas systems.
A set of magnetizing coils are used to induce electrical currents (eddy currents) into the
component being tested. The induced currents produce magnetic fields, which are then
detected by a set of sensing coils. Typically the two sets of coils are combined into a
single probe. In some systems Hall effect devices are used instead of sensing coils.
The frequency of the AC signal used (5 to 10M Hz) determines the depth of penetration
through the material for the eddy currents. Lower excitation frequencies increase the
penetration depth and improve the effectiveness in detecting deeper defects. Higher
frequencies are utilized to enhance detection of surface defects. Analysis equipment
senses several parameters including magnitude, time lag, phase angles and flow
patterns of the resulting magnetic fields. Automated analysis methods reduce the
reliance on operator experience for consistent results.
4.7.2.1 Intervals
When establishing sample intervals or frequency, several factors must be weighed. Operating
cycle of the system, historical failure rate, type of container material, type of contained
substance, chemistry control, major corrosion mechanisms, expected corrosion rate, erosion
mechanisms, expected erosion rate, proximity of existing material to minimum wall thickness,
consequences of system breach and type NDT techniques applicable to the situation will affect
the inspection interval (Table 4–2). Other factors may enter into consideration, if warranted.
American Petroleum Institute (API 570) recommends the following criteria for establishing
intervals for NDT inspection.
Piping service classification where Class 1 has the highest potential of resulting in an immediate
emergency and Class 3 has the lowest potential if a leak were to occur.
Relevant regulatory requirements must be taken into account when determining NDT inspection
intervals. With the multitude of professional codes and government regulations this section will
not attempt to cover specific regulations. Many government regulations provide sufficient
leeway for the experts within an organization to set intervals in accordance with technically
sound methods. Some regulations simply require a technically sound plan that the organization
follows.
Before accepting what seems like an unreasonable interval simply in the name of regulatory
compliance, investigate the document that originates the requirement. In industry, many
regulatory requirements have been needlessly made more stringent by the philosophy, “If a little
is good, a lot must be better.” In an effort to avoid falling afoul of regulatory inspectors,
inspection costs were significantly increased without a corresponding increase in plant safety or
reliability. Investigate basic requirements; if these are unclear ask the originating agency for
clarification of their expectations.
After the base inspection intervals have been established based on corrosion rate, class and
regulatory requirements; specific system intervals can be modified based on actual conditions,
historical data and operating parameters. Evaluate intervals based on operating conditions,
previous history, current inspection results or other indications of other than normal conditions.
By conducting statistical analysis on historical NDT results and failure rates, intervals can be
refined with a higher level of confidence. Pareto and Weibul analysis techniques can be applied
to indicate systems where unusual failure rates are occurring. Coupons can be utilized to provide
specific information on the corrosion rate, allowing further refinement of inspection intervals.
Process parameters can be used as a “trigger” for specific NDT inspections (Figure 4–8). As
thermodynamic properties change, they can provide an indication of increased corrosive product
deposits. Analysis of fluids transported within the system can also indicate changes in corrosion
activity allowing NDT inspection schedules to be appropriately adjusted. Procedures for
addressing adverse events such as over-pressurization and out of specification temperatures
should include the requirement for more frequent or immediate NDT inspections. Details of
type, location, parameter of concern and acceptable value should be indicated to facilitate a safe
and expeditious recovery from the incident.
4.7.2.2 Locations
The following should act as guidelines for locating NDT sampling points:
• Abrupt changes in direction of flow (elbows) and changes in pipe diameter will
cause turbulence that may accelerate many corrosion mechanisms.
• Presence of “Dead-Heads” that can create turbulence or stagnant areas where
material may accumulate and set up corrosion cells.
• Junctions of dissimilar metals. Galvanic corrosion is prevalent in these areas
unless specific steps are taken to prevent it.
• Stressed areas, welds, high stress fasteners and areas that undergo cyclic
temperature, pressure, or flow changes.
• Some applications may warrant specifying top, middle or bottom of pipe or areas
where more than one phase of a substance is present.
• Areas where accelerated corrosion/erosion mechanisms have been identified.
• Areas susceptible to cavitation.
4-96
Development Process
Compare
Determine Define Alert Define Alarm Minimum Calculate
Determine Define Corrosion
Methods To Determine Corrosion Corrosion Rate Interval Is Calculate Maximum
Expected Acceptable Rates Wiith
Address Inspection Rate (Prompts Time To Reach Material Life Allowable
Corrosion Corrosion NDT
These Locations (Prompts Corrective Repeatable Remaining Working
Rate Rate Repeatable
Failure Modes Inspections) Action) Sensitivity Pressure
Sensitivity
Establish Establish
If Regulatory Investigate Establish Define
Inspection Evaluate Effect Process Formalize &
Establish Requirement Other Methods Inspection Axis, Establish Financial
Interval Based Of P & T Cycles Indicators, Document
Regulatory Most Stringent, To Meet Number of Control Impact Of
On 80% Of Or Abnormal Coupons & NDT Plan &
Requirements Meet Regulatory Positions Each Group Program
Shortest Transients Chemistry Process
Requirement Requirements Location Modifications
Interval Sampling
NASA Reliability Centered Maintenance Guide for Facilities and Collateral Equipment
February 2000
NASA Reliability Centered Maintenance Guide for Facilities and Collateral Equipment
4.7.3 Applications
a. Radiography—Radiographic techniques are readily applicable to metal components
including weld deposits. Specialized applications for plastics or composite materials
are possible, though typically these materials are not most economically inspected
with radiography. For thick cross-sections, radiography is often the only reliable
method for inspection.
d. Dye Penetrant—DP inspections are applicable for any non-porous material that is
chemically compatible with the dye and developer. This is the simplest NDT
technique in which to gain proficiency.
e. Hydrostatic Testing—Hydros test the integrity of pressure boundaries for
components and completely assembled systems that contain pressurized fluids or
gases. Identification of defects that penetrate the entire pressure boundary is the
primary application for hydrostatic testing.
f. Eddy Current—Eddy current techniques are used to detect internal defects such as
cracks, seams, holes or laminations separation on both flat sheets and more complex
cross-sections as well as monitoring the thickness of metallic sheets, plates and tube
walls. Portable systems are used extensively in the condition monitoring of installed
heat exchanger and chiller tube wall thickness. Where coating thickness is an
important factor, there is sufficient difference in electrical or magnetic properties
between the base material, and the coating. Eddy Current Testing can determine the
actual coating thickness. In more production-oriented applications, installed systems
can determine material composition, uniformity and thickness of materials being
produced.
4.7.4 Limitations
a. Radiography—Effective use of radiography mandates expensive equipment,
extensive safety precautions and skilled technicians to interpret the images.
Expensive tracking and security for radiation sources is mandatory. Safety
precautions often demand evacuation of areas adjacent to the piece being examined or
installation of extensive shielding.
Even with these limitations, radiography is often the most effective method of
assuring integrity of critical welds, structural members and pressure boundaries. As
material thickness increases, radiography is often the only acceptable method to
achieve a 100% penetration.
Hydros will not identify defects that are present, but have not completely penetrated a
pressure boundary. The pressure applied to the system is generally not sufficient to
enlarge existing defects to the point of detection by the test. Hydrostatic testing
requires a pressure source capable of expeditiously filling and pressurizing the
f. Eddy Current—Eddy Currents tend to flow parallel to the surface to which the
exciting field is applied. Some orientations of laminar discontinuities parallel to this
surfaces tend to remain undetected by this method. Eddy Current Testing will not
penetrate deeply into the material of interest, so it is limited to shallow sub-surface
and surface defects.
4.8 Photography
Videotaping is often used to record complex machines during operation. The tape is played back
at a slow speed in order to what is happening. This is especially good tool for analyzing and
troubleshooting packaging machines.
This chapter discusses RCM requirements during the acquisition stage of the facilities life cycle;
i.e., during facilities planning, design, and construction.
5.1 Planning
Early in the planning of a new facility, consideration must be given to the extent RCM analysis
and PT&I techniques will be used to maintain the facility and its equipment. This is likely an
issue that crosses organizational lines (i.e. between operations, maintenance and engineering)
which should be addressed in the SOP with prior commitment from managers in those
organizations. The fundamental determination is the amount of built-in condition monitoring,
data transfer, and sensor connections to be used. It is more economical to install this monitoring
equipment and connecting cabling during construction than later. Planning, designing, and
building in the condition monitoring capability ensures that it will be available for the units to be
monitored. Continuously monitored equipment tied into performance analyzers permits
controlling functions and monitoring degradation. In the future, on-line monitors will become
increasingly capable and important. Installed systems also reduce manpower requirements as
compared with collecting sensor data with a portable data collector. However, for many uses,
portable condition monitoring equipment does provide the advantages of lower cost and
flexibility of application as compared with post-acquisition installed systems.
5.2 Design
The following should be considered during the design phase:
a. Maintainability factors that are within the control of the designer are:
1. Access - Equipment, its components, and facilities should be accessible for mainte-
nance.
1. Access - Provide clear access to collect equipment condition data with portable data
loggers or fluid sample bottles.
2. On-line Data Collection - Installed data collection sensors and links (wire, fiber
optics, or radio frequency (RF) links are possible) may be justified for high-priority,
high-cost equipment or inaccessible equipment.
a. PT&I Review - Conducting a PT&I technology review at an early stage of the design is
necessary to establish which technologies are to be used in the RCM program.
b. Maintenance Review - A continuing review of other maintenance programs for new and
emergent predictive technologies assists in keeping the program current by incorporating
the latest technological developments.
c. Feedback - Update or improve the design based on feedback, prior experience, and
lessons learned.
d. Scope of Work - Clearly establish in the Architect & Engineering (A&E) contract scope
of work that RCM maintainability and ease of monitoring requirements must be met.
1. The designer has a major impact on the life-cycle cost of the equipment by
incorporating the RCM lessons learned from the history of similar or identical
equipment.
5.3 Construction
During the construction phase, a major concern is to monitor the progress and quality of
construction to ensure that the planning and design work from earlier phases is effectively
implemented. This includes monitoring for conformance to specifications, drawings, bills of
material, and installation procedures. The following important steps should be taken during
construction:
b. RCM Analyses—It is during this phase that RCM analyses are done, the maintenance
program tasks should be chosen, and maintenance procedures and instructions should be
written.
This chapter discusses RCM requirements during the operational stage of the facilities life cycle
(maintenance and operations).
It is important for RCM maintenance costs, cost avoidance, and program savings to be
documented as they occur. A good Computerized Maintenance Management System (CMMS)
has the capability to track this information. Direct maintenance program savings are usually
apparent, but maintenance personnel must become attuned to recognizing and documenting the
less obvious “costs avoided.” This data also becomes a key part of the Continuous Improvement
(CI) process in that it is the feedback that reinforces the behavior created by the RCM
organization.
One use of maintenance data is in tracking the maintenance burden; i.e., the man-hours and/or
labor costs expended for all types of maintenance on a particular equipment. By identifying the
equipment on which maintenance effort is spent and categorizing the type of maintenance (i.e.,
RM, PM or PT&I), the maintenance burden may be allocated to end use. With labeled
maintenance man-hour expenditures, both the high burden items and the distribution of the
burden within the facility can be tracked over time. The use of Pareto analysis, or some other
method of prioritization of maintenance resource assignment, will permit the easy identification
of areas that demand attention from the standpoint of maintenance effectiveness or the need for
modification to improve reliability. As the intensive PT&I efforts take hold, the effects on
themaintenance burden can be analyzed to determine their costs and relative values, especially as
increased availability and improved quality impacts each activity.
The task of maintaining and updating drawings and specifications to keep facility documentation
abreast of the modifications and alterations should not be neglected. If not already part of the
Standard Operating Procedures (SOP), it should be added. The effectiveness of the facility and
the RCM program will reflect the degree to which this updating is accomplished.
documented and returned to the designers as feedback. Again, this needs to be a part of the
operating culture and should be added to the SOP.
An important function of feedback during the life cycle of any facility is to improve and optimize
the performance of the equipment. The RCM organization can be tasked with this function and,
if done properly, will become a crucial asset to future designs. As shown in Figure 6–1, design
improvements from one generation of equipment to the next can have a significant effect on
reliability. The feedback that the designer integrates into each successive generation yields
lower overall failure rates and extended equipment life. These improved characteristics reduce
maintenance costs as well, thus contributing to a lower life-cycle-cost, which is one of the goals
of the RCM and Continuous Improvement process.
a. Labor Force—The RCM program requires a labor force with the special skills
necessary to accomplish the program’s reactive, preventive, and PT&I tasks
successfully. The quality of the maintenance accomplished is reflected in the equipment
post-maintenance, infant mortality rate. The quality of maintenance is influenced by: 1)
the skill of the maintenance technicians, 2) their workmanship, 3) the quality of
supporting documentation and procedures, and 4) the technologies in use.
The involvement of a single person in all maintenance actions for the equipment or
system(s) for which they are responsible is the heart of the system expert concept and is
an excellent way to provide continuity of experience and expertise with regard to the
equipment and systems. The system expert is the person responsible for monitoring and
analyzing the maintenance data for an assigned equipment or system. The system expert
should receive all the related data, work requests, and test documents for review,
analysis, and filing. The system experts designated to maintain expertise and provide
continuing oversight, analysis, and continuity for designated facility systems or
equipment. The system expert concept results in a significant contribution to better
overall management of facility maintenance and provides the critical elements of the
organization’s memory and its analysis.
Pcond
Infant Random Wearout
Mortality Failures
Time
Time
Infant
Mortality Reduced by
Less Maintenance and
Better Commissioning
The system expert is not intended to replace or supplant the technical expertise normally
found within the design organization of the original equipment manufacturer (OEM), the
facility, or at the Center or NASA headquarters. The system expert is expected to be a
member of the facility maintenance team who is conversant with the maintenance
history of their assigned equipment and systems. The system expert is also involved
with integrating maintenance support from facility resources outside of the normal
maintenance organization.
c. Training—Training plays a major role in reaching and maintaining the required RCM
workforce skill level. The training is both technology/equipment specific and of a more
general nature. Management and supervisory personnel benefit from training which
presents an overview of the RCM process, its goals, and methods. Technician training
includes the training on specific equipment and technologies, RCM analysis, and PT&I
methods.
Root Cause/
Maintenance Technology/
Position/Title RCM/PT&I Predictive
Overview Equipment
Analysis
Managers/
X X X
Supervisors
System
X X X X
Experts
Maintenance
X X X X
Technicians
Support
Personnel X
(Logistics)
An important function of feedback during the life of the facility is to improve the
performance of the facility and its equipment. The M&O-to-designer linkage is crucial
in this improvement process. As shown in Figure 6–1, design improvements from one
generation of equipment to the next have a significant effect on operability,
maintainability and reliability.
2. It contains the data that is analyzed to trend and forecast equipment failure.
3. It forms the basis for analysis of long-term equipment and system performance
trends.
4. It provides the statistics used to determine the failure rates, which influence spare
part stock levels.
The use of standard procedures in PT&I ensures that data is collected in a consistent and
comparable manner without being dependent on the experience of the collecting
technician. Improvements in data collection techniques can be applied to all similar
collection efforts by modifying the standard procedures.
There are several basic contract purposes involved in the facility and equipment life cycle. They
are as follows:
There is a need for RCM-related clauses in each of these types of contracts. Standard clauses
have been developed for this purpose.
This chapter contains recommended standard RCM contract clauses. Clauses are grouped by
equipment and the applicable technology. Tables 7–11 through 7–14 identify and cross-
reference the applicability of each RCM contract clause, component, and type of contract for
each phase of the contract.
The applicable RCM contract clause and criteria should be included in all Requests for Proposals
(RFPs), Requests for Quotations (RFQs), and in the contracts themselves.
The clauses may be used without modification; however, they will have to be renumbered to fit
the organization of the specification in which they are used.
For example, the vibration data listed in paragraphs 7.1.7 through 7.1.8 should be included in
contract specifications if vibration analysis is to be performed as part of the RCM program.
b. Bearing Data—The contractor shall provide to the procuring organization the bearing
manufacturer and part number for all bearings used in all rotating equipment supplied
under this contract. The information shall be included on the sectional drawings for each
bearing location.
c. Operating Data—The required equipment data the contractor shall provide the
procuring organization under this contract shall include the operating speed for constant
speed units and the normal operating speed range for variable speed equipment.
7.1.4 Pumps
The contractor shall provide to the procuring organization the following information on all
pumps supplied under the contract:
7.1.6 Fans
The contractor shall provide to the procuring organization the following information on all fans
supplied under the contract:
The contractor shall provide to the procuring organization the following additional information if
the fans/air handlers are belt driven:
• Number of belts
• Belt lengths
• Diameter of the drive sheave at the drive pitch line
• Diameter of the driven sheave at the drive pitch line
For all fans supplied under the contract, the contractor shall ensure sufficient access to the fan is
present to allow for cleaning and in-place balancing of the fan.
a. For machines operating at or below 1,800 RPM, the frequency spectrum provided shall
be in the range of 5 to 2,500 Hz.
b. For machines operating greater than 1,800 RPM, the frequency spectrum provided shall
be in the range of 5 to 5,000 Hz.
c. Two narrowband spectra for each point shall be obtained in the following manner:
Frequency In Hz
1. For all machines regardless of operating speed, a 5 to 500 Hz spectrum with 400 lines
of resolution shall be used to analyze balance, alignment, and electrical line frequency
faults.
4. The contractor shall ensure that the equipment provided meets the following
acceptable vibration amplitudes for each machine:
(5) Compare this mean vibration signature to the specifications and guidelines
provided in this guide.
(6) Note any deviations from the guidelines and determine if the unknown
frequencies are system related; e.g., a resonance frequency from piping
supports.
(7) Collect vibration data on the new component at the recommended positions.
(8) Compare the vibration spectrum with the mean spectrum determined in step
(5) above as well as with the criteria and guidelines provided in this guide.
(9) Any new piece of equipment should have a vibration spectrum which is no
worse than a similar unit of equipment which is operating satisfactorily.
Vibration tests are recommended under the following situations if the equipment
fails the initial test and/or if problems are encountered following installation:
Broken rotor bars will often produce sidebands spaced at two times the slip
frequency. The presence of broken rotor bars can be confirmed through the
use of electrical testing.
(2) Balance—The vibration criteria listed in Table 7–1 are for the vibration
amplitude at the fundamental rotational frequency or one times running
speed (1X). This is a narrowband limit. An overall reading is not
acceptable.
(4) Rewound Electric Motors—Due to the potential of both rotor and/or stator
damage incurred during the motor rewinding process (usually resulting
from the bake-out of the old insulation and subsequent distortion of the pole
pieces) a rewound electrical motor should be checked both electrically and
Note: Rewinding a motor will not correct problems associated with thermal
distortion of the iron.
2X RPM 0.02
Harmonics 0.01
(7) Belt Driven Fans—Use the criteria in Table 7–4 for belt-driven fans:
1X RPM 0.1
2X RPM 0.04
Harmonics 0.03
5. The contractor shall collect vibration data at normal operating load, temperature, and
speed.
6. The contractor shall supply all critical speed calculations. In addition, the contractor
shall perform a check for machine resonance following installation and correlated
with all known forcing frequencies; i.e., running speed, bearing, gear, impeller
frequencies, etc.
Class Condition
A Good
B Satisfactory
C Unsatisfactory
D Unacceptable
7. The contractor shall analyze all motor vibration spectra at the following forcing
frequencies and provide the results to the procuring organization:
e. Generators—The contractor shall install sound discs in the horizontal and vertical planes
on the free ends of the motor and generator bearing assemblies. Pedestal bearings
between the motor and generator should be monitored in the vertical direction radial to
the shaft. Thrust bearings shall be monitored in the axial direction.
f. Gear Boxes—The contractor shall install sound discs radial to the input and output shafts
in the horizontal and vertical directions. Additional discs shall be installed in the axial
direction as close to the input and output shafts as possible.
g. Compressors—The contractor shall install sound discs radial to the input and output
shafts in the horizontal and vertical directions. Additional discs shall be installed in the
axial direction as close to the input and output shafts as possible.
i. Blowers & Fans—Motors on blowers and fans shall have sound discs installed in the
radial and axial directions as previously described. Fan bearings shall be monitored
radially in the vertical direction.
j. Chillers
1. Centrifugal—The contractor shall mount sound discs in the horizontal and vertical
planes radial to the shaft at the free and coupled ends of the motor and compressor as
close to the bearings as possible. Accelerometers shall be mounted to solid structures
and not on drip shields or other flexible structures. Mounting locations shall be in
line with each other, perpendicular to the compressor discharge, and located at the
free end, at the coupled end of the motor and compressor, and in the axial direction on
compressor and motor.
2. Reciprocating—The contractor shall install sound discs radial to the input and output
shafts in the horizontal and vertical directions. Additional discs shall be installed in
the axial direction as close to the input and output shafts as possible.
a. Liquid Lubricants
Z = pt(0.22s-180/s)
pt = pr-0.00035(t-60)
b. Grease Lubricants
Dropping point
Base oil viscosity range in SUS or centipoise
The following formula shall be used to calculate SUS and absolute viscosity:
Z = pt(0.22s-180/s)
pt = pr-0.00035(t-60)
c. Lubricant Tests—The contractor shall draw lubricants and perform the lubricant tests
listed in Table 7–8 on all lubricants supplied by him and shall submit the results of the
tests to the procuring organization.
Lubricant Tests
Visual for color & clarity Cloudiness or Presence of water or TAN Routine
darkening particulates. Oxidation of
lubricant.
Spectrometals (IR spectral Metals Presence of contaminants, wear Particle count Routine
analysis) products and additives
Particle count Particles >10 Metal & wear product particles Spectro-metals Routine
µm
d. Hydraulic Fluids—All bulk and equipment-installed hydraulic fluids supplied under this
contract shall meet the cleanliness guidelines in Table 7–9. The procuring organization
will specify System Sensitivity. In Table 7–9, the numbers in the 5 micron and 15
micron columns are the number of particles greater than 5 microns and 15 microns in a
100-milliliter sample.
The particle counting technique utilized shall be quantitative. Patch test results are not
acceptable.
The ISO numbers in the right-hand column of Table 7–9 are based on the concentration
of particles greater than 5 microns and greater than 15 microns per 100-milliliter sample.
The concentration can then be converted to the ISO number using an ISO Range Number
Table that should be available from a hydraulic fluid vendor or lubrication laboratory.
e. Insulating Fluids—The contractor shall identify the type of oil used as an insulating
fluid for all oil-filled transformers supplied under the contract. In addition, the contractor
shall test the insulating oil using the American Society for Testing Materials (ASTM) test
listed in Table 7–10 and provide the results to the Government. Any deviation from the
typical properties listed below shall be corrected by the contractor before the Government
will accept the transformer.
f. Sampling Points—The contractor shall install sampling points and lines in accordance
with Method No.1 as recommended by the National Fluid Power Association (NFPA).
Method No. 1 is published as NFPA T2.9.1-1972 titled Method for Extracting Fluid
Samples from the Lines of an Operating Hydraulic Fluid Power System for Particulate
Particle Contamination Analysis as follows:
1. For Pressurized Systems—A ball valve is placed in the fully opened position with a
downstream capillary tube (ID> 1.25 mm) of sufficient length to reduce downstream
pressure and control flow in the desired range. The sampling point shall be located in
a turbulent flow region and upstream of any filters.
2. For Reservoirs and Non-Pressurized Systems—A 1/8" stainless steel line and ball
valve is placed in the side of the oil sump or tank. The line shall be located as close
to the midpoint of the structure as feasible. In addition, the sample line shall extend
internally to and as close to the center of the tank as possible.
7.1.10 Thermography
a. Electrical—The contractor shall perform a thermographic survey on all electrical
distribution equipment, motor control centers, and transformers during the start-up phase
of the installation unless the thermographic survey is waived by the procuring
organization.
Any voids in the piping insulation shall be corrected by the contractor at no additional
cost to the procuring organization. The contractor shall resurvey repaired areas to assure
proper corrective action has been taken.
ASTM C1153-90 Standard Practice for the Location of Wet Insulation in Roofing
Systems Using Infrared Imaging.
ASTM E1186-87 Standard Practices for Air Leakage Site Detection in Buildings.
For areas where the moisture content of the insulation or building envelope is
questionable, the contractor shall use either destructive or non-destructive testing
techniques that confirm the amount of moisture. Specific testing procedures to be used
shall be proposed by the contractor and approved by the procuring organization.
The contractor shall perform a thermographic survey of all repaired areas prior to final
acceptance by the procuring organization.
g. Motors and Bearings— Large machines should be scanned closely. Abnormal hot spots
on the body may indicate flaws in the stator windings. The surface temperature of a
motor is normally 7.5% lower than the winding temperature. Bearing temperatures are
normally 5–20 degrees F higher than the housing temperature.
Any defects or exceptions noted by the use of airborne ultrasonics shall be corrected by the
contractor at no additional expense to the procuring organization. The contractor shall re-survey
repaired areas to assure proper corrective action has been taken.
• Coast-down time
• Peak starting current
For example, mobile industrial equipment shall be equipped with fluid sampling ports on the
engine and hydraulic systems. Accessibility to these ports shall facilitate periodic fluid sampling
and system monitoring.
7.1.8
7.1.9 Blower/fan Lubricant & wear particle
analysis
7.1.2; 7.1.3; 7.1.8 Gearbox Vibration
7.1.9 Gearbox Lubricant & wear particle
analysis
7.1.10 Boiler, furnace Infrared thermography
7.1.11 Piping Passive ultrasound
7.1.12 Piping/pressure vessel Pulse echo ultrasound
7.1.10 Piping insulation Infrared thermography
7.1.10 Chiller/refrigeration Infrared thermography
7.1.9 Chiller/refrigeration Lubricant & wear particle
analysis
7.1.2; 7.1.7; 7.1.8 Chiller/refrigeration Vibration
7.1.11 Electrical switchgear /circuit breakers Passive ultrasound
7.1.10 Electrical switchgear /circuit breakers Infrared thermography
7.1.15 Electrical switchgear /circuit breakers Insulation resistance
7.1.15 Motor & motor circuit Insulation resistance
7.1.13 Motor & motor circuit Motor circuit analysis
7.1.14 Motor & motor circuit Motor current spectrum analysis
7.1.17 Motor & motor circuit Start-up tests
7.1.10 Building envelope Infrared thermography
7.1.10 Heat exchanger/condenser Infrared thermography
7.1.11 Heat exchanger/condenser Passive ultrasound
7.1.2; 7.1.7; 7.1.8 Electric motor (new and rewound) Vibration
7.1.16 Electric motor (new and rewound) Surge testing
7.1.2; 7.1.7; 7.1.8 Electrical generator Vibration
7.1.13 Electrical generator Motor circuit analysis
7.1.15 Electrical generator Insulation resistance
7.1.10 Transformer Infrared thermography
7.1.9 Transformer Oil analysis
7.1.1 Measurements/surveys N/A
7.1.19 Rotating Equipment- Electrical & Mechanical Equipment leveling upon
installation
Table 7–14. RCM Clauses for M&O Contracts
8.1 Baselines
Baseline data is that condition monitoring data representative of an equipment in a new and/or
properly operating condition. The baseline data is the foundation of the predictive trending
analysis required to forecast equipment condition. It is important that this baseline data is
established as early as possible in the life of the equipment. The baseline readings and periodic
monitoring data should be taken under the same conditions (or as close as can be achieved).
These conditions should be recorded. It is only under identical conditions that the relative
comparison of data is valid. Significant changes in conditions often affect the data in
unquantifiable ways because of unknown or complex relationships. Baseline readings should be
re-established each time equipment undergoes major maintenance.
The vibration specifications provided in this guide are based on International Standards
Organization (ISO), American Petroleum Institute (API), American Gear Manufacturers
Association (AGMA), American National Standards Institute (ANSI), MIL-STD-167-1, MIL-
STD 740-2 (Appendix C), General Motors Vibration Specifications, and field data acquired on a
variety of machinery.
Equipment failing the vibration criteria should be rejected by the Government prior to
shipment.
Vibration tests are recommended under the situations listed in paragraph 7.1.7.1.c.(4)(b)
if the equipment fails the initial test and/or if problems are encountered following
installation.
2. Balance - The vibration criteria listed in Table 7–1 are for the vibration amplitude at
the fundamental rotational frequency or one times running speed (1X). This is a
narrowband limit. An overall reading is not acceptable.
d. Rewound Electric Motors—Due to the potential of both rotor and/or stator damage
incurred during the motor rewinding process (usually resulting from the bake-out of the
old insulation and subsequent distortion of the pole pieces) a rewound electrical motor
should be checked both electrically and mechanically. The mechanical check consists of
post-overhaul vibration measurements at the same location as for new motors. The
vibration level at each measurement point should not exceed the reference spectrum for
that motor by more than 10%. In addition, vibration amplitudes associated with electrical
faults such as slip, rotor bar, and stator slot should be noted for any deviation from the
reference spectrum.
Note: Rewinding a motor will not correct problems associated with thermal
distortion of the iron.
1. If rolling element bearings are utilized in either the driver or driven component of a
unit of equipment (e.g., a pump/motor combination), no discrete bearing frequencies
should be detectable. If a discrete bearing frequency is detected, the equipment
should be deemed unacceptable.
3. If no specific criteria are available, the ISO 3945 acceptance Class A guidelines
(Appendix C) should be combined with the motor criteria contained in Table 7–2 and
used as the acceptance specification for procurement and overhaul.
f. Specific Equipment—Use the criteria shown in Table 7–3 on boiler feedwater, split
case, and progressive cavity pumps.
g. Belt Driven Fans—Use the criteria in Table 7–4 for belt-driven fans:
In wear particle analysis, analysts examine the amount, makeup, shape, size, and other
characteristics of wear particles and solid contaminants in the lubricants as indicators of internal
machine condition. With experience and historical information, one can project degradation
rates and estimate the time until machine failure. Wear particle analysis includes ferrography,
which is a technique used to analyze metal wear products and other particulates. Elemental
spectrographic analysis is used to identify the composition of small wear particles and provide
information regarding wear sources. Analyzing and trending the amount, size, and type of wear
particles in a machine’s lubrication system can pinpoint how much and where degradation is
occurring. Figure 8–1 illustrates the relationship between wear particle size, concentration and
equipment condition.
µ m)
Wear Particle Size (µ
8.2.3 Thermography
There are two basic criteria for evaluating temperature conditions. They are differential
temperature (∆T) and absolute temperature. Each is described below.
The typical ∆T criteria, which may be modified easily based on experience, are as shown
in Table 8–1:
A very useful summary of temperature criteria is found in the Guideline for Infrared
Inspection of Electrical and Mechanical Systems, published by the Infraspection Institute
of Shelburne, Vermont (Appendix C).
Table 8–2 provides absolute temperature limits for materials commonly found in the
Government Plants:
• Individual phase resistance from bus disconnect through the motor windings
(milli-ohms)
During the same test series, one can measure resistance to ground of each phase (megohms)
through the use of low voltages (both AC & DC) and low currents, which are not harmful to the
motor or motor circuits.
The following procedure is recommended for use when performing motor current analysis
(MCA):
R high - R avg
% Imbalance = X 100
R avg
( R1 + R 2 + ... Rn )
Where : R avg =
n
Greater than 10%—Schedule effort to locate and eliminate problem in order to preserve
motor life
Inductive Imbalance Guidelines
Less than 10%—Acceptable from OEM or rewind shop
10-15%—Acceptable in service
Greater than 15%—Isolate cause(s), increase monitoring frequency
Greater than 25%—Begin planning for motor repair or replacement
Greater than 40%—Be prepared for failure, within weeks
X high - XR avg
% Imbalance = X 100
X avg
( + + ... X n )
Where : X avg = X 1 X 2
n
Capacitance imbalance is reflective of moisture and dirt in the vicinity of motor circuit
components.
As the difference between the amplitude of the power line frequency and the pole pass sideband
frequencies decrease in magnitude, the greater the concern should be for the condition of the
rotor. Results indicate:
• A moderate decrease may indicate increasing resistance between the rotor bars
and the end ring or that a crack is developing in either
• Current, which polarizes the molecules of the insulation surrounding the motor
circuit conductor path and fades slowly from its initial value.
The ratio of readings taken at two different times indicates the condition of the insulation,
as follows:
greater than1.5—OK
less than 1.25—Danger
Surge Testing, in the view of the Electric Power Research Institute, accomplishes the following:
• The surge test could be destructive, inducing failure in weakened turn to turn
insulation. For this reason, test impulse voltage levels and rise times should be
carefully selected.
• This is a go/no-go proof test and, as such, does not provide information that will
allow making an assessment of remaining life.
• Experience is required to perform the test and to interpret the results, especially if
complete windings rather than individual coils are tested.
a. Coast-down time—A simple and often overlooked test. In this test the time for the
motor to coast to a stop after the removal of power is recorded and trended. This data
tracks the mechanical condition of the motor bearings over the life of the machine.
b. Peak starting current—Another simple test which involves periodically recording the
peak starting current of a motor. This test also provides an indication of the mechanical
condition of the motor.
9.1 Planning
Table 9–1 contains some factors to be considered in the planning phases of facilities acquisition.
Planning QA Checklist 3
Has the use of performance data for condition monitoring been considered
and planned?
Is the collection of cost, cost avoidance, and cost savings incorporated?
Have PT&I technologies that are appropriate for the equipment been
selected?
9.2 Design
Table 9–2 contains some factors to be considered for quality assurance during the design phase
of facilities acquisition.
Design QA Checklist 3
Access
Material
Standardization
Access
Performance indicators
Has the distribution of raw data to those who could use it been incorporated?
9.3 Construction
Table 9–3 lists some factors to consider during the construction phase of facilities acquisition.
Construction QA Checklist 3
Were acceptance testing requirements established (prior to construction mobilization)?
Are maintenance cost, cost avoidance and cost savings data collected, analyzed
and disseminated?
Is baseline condition and performance data updated following
major repair or replacement of equipment?
Are appropriate measures of maintenance performance (metrics) in use?
10.1 General
There are a number of management indicators used to measure the effectiveness of an RCM
program. The most useful indicators are numerical. The numerical, or quantified indicators,
often referred to as Ametrics,@ can be expressed as goals and objectives, measured and displayed
in several ways for the purpose of analysis and management decision making. This chapter
addresses the description, benefits and methods for using metrics as an integral part of the
Reliability Centered Maintenance (RCM) implementation process. These quantifiable indicators
can be expressed as goals and objectives, measured and displayed in several ways for the
purpose of analyzing the effectiveness of the RCM program and to support the decision making
process.
RCM is described as a maintenance strategy that logically incorporates the optimum mix of
reactive, preventive, predictive, and proactive maintenance practices. Since these maintenance
practices, rather than be applied independently, are integrated to take advantage of their
respective strengths in order to maximize facility and equipment operability and efficiency
while minimizing life cycle costs, Metrics must be in place to measure how well the following
are achieved:
• Maintenance integration
• Maintenance optimization
These are all areas that require a method to manage and to describe the effectiveness of
implementing RCM. Metrics are the key to measuring, managing and benchmarking all phases
of the RCM implementation process.
16
Metrics and Benchmarks developed by Mr. Alan Pride, Mr. Robin Rubrecht and Ms. Nancy Bray and presented
presentation to the Association for Facilities Engineering’s Facilities America ’99 conference October 16-20, 1999.
To management, Metrics are used in the strategic planning process for the development,
optimization and direction of management objectives. Metrics should reveal the effectiveness
of the management program, and measure costs (to support the budget process). Management is
responsible for the translation of technical level metrics into overall facilities maintenance
management metrics, which support NASA goals and objectives. Metrics can be used to support
the functions of staffing, budget formulation, training, contracting, and to ensure compliance
with certain regulatory requirements.
Metrics are needed to monitor and control the performance of specific equipment, systems, and
processes. Supervisors, Engineers, Technicians, and Crafts use these metrics to support
optimization and continuous improvement of the maintenance program.
10.2.2.1 Descriptor
A descriptor is a word or group of words describing the units, the function, or the process to be
measured. Examples are the number of corrective actions developed by the PT&I program, the
number of hours of equipment run-time, and the equipment availability expressed as a ratio of
equipment hours available to equipment hours required.
10.2.2.2 Benchmark
A benchmark is a numerical expression of a goal or objective to be achieved. It is that against
which one measures one=s performance. It can be an absolute number or a range. For example,
the benchmark for equipment availability might be 90%. The metric (descriptor and benchmark)
would therefore be:
Metric Benchmark
Metric Benchmark
A = 70% PM/PT&I
B = 30% Reactive Maintenance
A% + B% = 100%
$ A monthly record of the accumulated economic benefits or cost avoidance for the
various PT&I techniques.
$ Number of spare parts eliminated from inventory as the result of the PT&I
program.
$ Number of overdue PM work orders at the end of the month. (Total number of
PM actions should decrease.)
This metric includes CoF as well as center-level funded projects that are identified
but not funded. BMAR does not include routine recurring work with a frequency of
less than one year.
17
KSC letter IM-FEO-A from Nancy Bray dated June 7, 1996, Final Recommendation of Agency wide Facilities
Maintenance Metrics.
d. Log of Unplanned Failures and Avoided FailuresC C The purpose of this metric is to
demonstrate the impact of the overall maintenance program effectiveness by tracking
failures and failures avoided by detection of the failure precursor through either PM
or PT&I.
The tracking and publication of Metrics informs the people of what is important, what are the
goals, and where do they stand with respect to performance expectations. The impact of
displaying Metrics often has an immediate effect on the workers in the functional area being
measured. In addition, Metrics are an integral part of any Team Charter as they allow the Team
and Management to determine Team productivity.
When using Benchmarks it is important to focus on patterns and not individual data points. For
example, if the maintenance budget as a percent of Current Replacement Value (CRV) is below
1% it could be either 1) due to an effective maintenance program or 2) an indicator that the
facility is being consumed.
Notes: 1. If a maintenance budget is below 2% of Current Replacement Value (CRV) the overall condition of
the facility should be evaluated to determine if the infrastructure is under-going slow degradation or if
an excessive number of projects are required to maintain the facilities.
2. Either High or Low is acceptable depending on the strategic plans for the facility, i.e., if the decision
has been made to out source either a portion or all of the maintenance function.
Total Estimated Labor Hrs. for Completed Work Orders for Week
%=
Total Actual Labor Hrs. for Completed Work Orders for Week
5. BACKLOG OF LOGBOOK JOBS (Target - Less than half the number of Logbook jobs
competed in a single week)
Number of open jobs in the Electronic Logbook at the end of the month.
Number of Unplanned Repair Work Orders over 30 days old at the end of the month per
Planner.
Total number of open Work Orders at the end of the month. (Trending down or level)
Total number of closed Work Orders during the month. (Trending up or level)
Appendix A—Glossary
Age Exploration The process of determining the most effective intervals for maintenance
tasks. Its called age exploration because it is often associated with identifying age related
maintenance actions such as overhaul and discard tasks and then extending the interval between
tasks.
Availability (1) Informally, the time a machine or system is available for use. (2) From the
Overall Equipment Effectiveness calculation, the actual run time of a machine or system divided
by the scheduled run time. Note that Availability differs slightly from Asset Utilization
(Uptime) in that scheduled run time varies between facilities and is changed by factors such as
scheduled maintenance actions, logistics, or administrative delays.
Benchmarking To seek out the best examples of methods, processes, procedures, and
products in order to establish a standard and assess ones own performance in terms of quality,
productivity, or cost.
B-Life The time at which a set percentage of failures are expected. For example, the B1 life is
when 1% of the units being examined will have failed; B10 is when 10% of the units will have
failed.
Building Commissioning The systematic process for achieving, verifying, and documenting
that the performance of NASA Faculties and Collateral Equipment meets the design intent. The
process extends through all phases of a project and culminates with occupancy and operation.
The process includes the testing and accepting of new or repaired building, system or component
parts to verify proper installation.
affixed to, or installed in real property in such a manner that the installation cost,
including special foundations or unique utilities service, or the facility restoration work
required after its removal is substantial.
Commissioning The process of testing and accepting a system, line, building and other plant
component. It is often the first (and sometimes last) opportunity for the "maintenance
department" to identify a design or build defect. Also see Building Commissioning.
a. Facility/Equipment Inventory
b. Facility/Equipment History
c. Work Input Control
d. Job Estimating
e. Work Scheduling and Tracking
f. Preventive and Predictive Maintenance
g. Facility Inspection and Assessment
h. Material Management
i. Utilities Management
Condition-Based Maintenance Facility and equipment maintenance scheduled only when the
condition of the facility or equipment requires it. CBM replaces maintenance scheduled at
arbitrary time or usage intervals. It usually involves the application of advanced technology to
detect and assess the actual condition
Current Replacement Value (CRV) Approximate cost to replace an existing facility in its
present form. NASA calculates CRV by escalating facility and collateral equipment acquisition
cost, and any incremental book value changes of $1,000 or more to present-year dollars using the
Engineering News Record (ENR) Building Cost Index (BCI). The NASA Real Property Data
System program or NASA Headquarters-approved equivalent is used in performing the required
calculations.
Critical Failure A failure involving a loss of function or secondary damage that could have a
direct adverse effect on operating safety, on mission, or have significant economic impact.
Critical Failure Mode A failure mode that has significant mission, safety or maintenance
effects that warrant the selection of maintenance tasks to prevent the critical failure mode from
occurring.
Dominant Failure Mode A single failure mode that accounts for a significant portion of the
failures of a complex item.
Effective Maintenance The application of the maintenance approach that will produce the
required availability, at the lowest cost, without compromising human safety or health, the
environment, or any other conditions the organization specifies.
Effective Maintenance Task A task that is characterized as performing its defined function
with a high degree of success for a specified cost. A maintenance task must be both applicable
and effective. The benefit of performing the task must be evaluated against the cost. Cost
includes many elements; the cost of the task, repair costs when failure occurs, collateral damage
caused by failure, and the cost of lost mission (such as production, space and flight operations,
research, and administrative support) due to the loss of the facilities and collateral equipment
function.
Failure Mode: The manner of failure. For example, the motor stops is the failure, the reason the
motor failed was the motor bearing seized which, is the failure mode.
Failure Modes and Effects Analysis (FMEA) Analysis used to determine what parts fail,
why they usually fail, and what effect their failure has on the systems in total. An element of
Reliability Centered Maintenance (RCM).
Failure Rate The number of failures divided by an interval such as time or cycles. The failure
rate will change over time and can be greater than one (but will never be less than zero).
Fiscal Year In the Federal Government, it is the 12-month period from Oct. 1 of one calendar
year through Sept. 30 of the following year.
Function Defined performance standard. Usually quantitative in nature (flow rate, cooling
capacity, etc.).
Infrared Thermography A predictive technique that uses infrared imaging to identify defects
in electrical and electro-mechanical devices such as fuse boxes, circuit breakers, and switchgear.
It also can be used effectively in a non-predictive manner to detect thermal cavities and leaks in
walls, ceilings, and rooftops, the correction of which can result in sizeable reductions in heating
and air conditioning expenses. Thermal imaging is extremely sensitive, and since it evaluates the
heat an object emits, emittance and reflective factors of the object and environment must be
considered.
Key Performance Indicator (KPI) Critical few (key) indicators aligned throughout the
organization that measure controllable performance and contribute towards achieving the
organization objectives.
Maintainability The ability to retain or restore function within a specified period of time,
when provided with an identified level of tools, training, and procedures. Maintainability factors
include machine and systems access, visibility, simplicity, ease of monitoring or testing, special
training requirements, special tools, and capability of local work force
Maintenance Action taken to retain function (i.e., prevent failure). Actions include Preventive
Maintenance, Predictive Testing & Inspection, lubrication and minor repair (such as replacing
belts and filters), and inspection for failure. Also see Preventive Maintenance and Predictive
Testing & Inspection.
Maintenance Approach The plan to prevent failure and, when failure occurs, perform repair.
Mean Time Between Failure (MTBF) The reciprocal of the failure rate; the average time to
fail. The MTBF is sometimes called the Mean Time To Fail (MTTF).
Mission Critical A building, area, or system that is critical to the Center/Facility mission or
essential for Center of Excellence performance. Also see Mission Support and Center/Facility
Support.
Mission Support A building, area, or system that provides support to the Center/Facility
primary mission or Center of Excellence assignment. Also see Mission Critical and
Center/Facility Support.
Motor Circuit Analysis (MCA)— A predictive technique whereby the static characteristics
(i.e.; impedance, capacitance to ground, inductance) of a motor or generator are measured as
indicators of equipment condition.
Motor Current Spectrum Analysis (MCSA)— A predictive technique whereby motor current
signatures provide information on the electro-mechanical condition of AC induction motors. It
detects faults such as broken rotor bars, high resistance joints, and cracked rotor end rings by
collecting motor current spectrums with clamp-on sensors and analyzing the data.
Non-collateral Equipment— All equipment other than collateral equipment. Such equipment,
when acquired and used in a facility or a test apparatus, can be severed and removed after
erection or installation without substantial loss of value or damage thereto or to the premises
where installed. Noncollateral equipment imparts to the facility or test apparatus its particular
character at the time, e.g., furniture in an office building, laboratory equipment in a laboratory,
test equipment in a test stand, machine tools in a shop facility, computer in a computer facility,
and it is not required to make the facility useful or operable as a structure or building. (See also
Collateral Equipment.)
Pareto Analysis A problem solving tool that breaks data down into manageable groups and
identifies the greatest opportunity for return on investment. The analysis is based on the Pareto
Principle, also known as the 80:20 Rule. Simply stated, the principle says that 20% of a
population will cause 80% of the problems associated with the population.
Predictive Testing & Inspection (PT&I) The use of advanced technology to assess machinery
condition. The PT&I data obtained allows for planning and scheduling preventive maintenance
or repairs in advance of failure. Also see Condition Monitoring and Condition-Based
Maintenance.
(2) Time- or cycle-based actions performed to prevent failure, monitor condition, or inspect for
failure.
Proactive Maintenance The collection of efforts to identify, monitor and control future
failure with an emphasis on the understanding and elimination of the cause of failure. Proactive
maintenance activities include the development of design specifications to incorporated
maintenance lessons learned and to ensure future maintainability and supportability, the
development of repair specifications to eliminate underlining causes of failure, and performing
root cause failure analysis to understand why in-service systems failed.
Programmed Maintenance (PGM) Those maintenance tasks whose cycle exceeds one year,
such as painting a building every fifth year. (This category is different from PM in that if a planned
cycle is missed the original planned work still remains to be accomplished, whereas in PM only the
next planned cycle is accomplished instead of doing the work twice, such as two lubrications, two
adjustments, or two inspections.)
Reliability-Centered Maintenance (RCM) The process that is used to determine the most
effective approach to maintenance. It involves identifying actions that, when taken, will reduce
the probability of failure and which are the most cost effective. It seeks the optimal mix of
Condition-Based Actions, other Time- or Cycle-Based actions, or Run-to-Failure approach.
Repair That facility work required to restore a facility or component thereof, including
collateral equipment, to a condition substantially equivalent to its originally intended and
designed capacity, efficiency, or capability. It includes the substantially equivalent replacements
of utility systems and collateral equipment necessitated by incipient or actual breakdown. Also,
restoration of function, usually after failure. Also see Planned Repair.
Root Cause Failure Analysis (RCFA) The process of exploring, in increasing detail, all
possible causes related to a machine failure. Failure causes are grouped into general categories
for further analysis. For example, causes can be related to machinery, people, methods,
materials, policies, environment, and measurement error.
Time- or Cycle-Based Actions Maintenance activities performed from time-to-time that have
proven to be effective in preventing failure. Items such as lubrication and restoration of wear fit
this description. Other items that are Time- or Cycle-Based are inspection and condition
monitoring. Also see Predictive Testing and Inspection.
Vibration Analysis— The dominant technique used in predictive maintenance. Uses noise or
vibration created by mechanical equipment to determine the equipment’s actual condition. Uses
transducers to translate a vibration amplitude and frequency into electronic signals. When
measurements of both amplitude and frequency are available, diagnostic methods can be used to
determine both the magnitude of a problem and its probable cause. Vibration techniques most
often used include broadband trending (looks at the overall machine condition), narrowband
trending (looks at the condition of a specific component), and signature analysis (visual
comparison of current versus normal condition). Vibration analysis most often reveals problems
in machines involving mechanical imbalance, electrical imbalance, misalignment, looseness, and
degenerative problems.
Appendix B—Abbreviations/Acronyms
AC Alternating Current
AE Age Exploration
CI Continuous Improvement
DC Direct Current
DP Dye Penetrant
HP Horsepower
PF Pumping Frequency
PI Polarization Index
PM Preventive Maintenance
RF Radio Frequency
UT Ultrasonic
Appendix C—Bibliography
Annual Book of ASTM Standards, Section 5 (for lubricating oil tests), American Society for
Testing and Materials, Philadelphia, PA.
Chemistry & Technology of Lubricants, editors R.M. Mortier and S.T. Orszulik, VCH
Publishers, New York, NY, 1992.
Contamination Control For The Fluid Power Industry, Second Edition, Fitch, E.C. and I.T.
Hong, Pacific Scientific Company, 1990, Silver Spring, MD.
Fuchs, Sheldon J. Complete Building Equipment Maintenance Desk Book, Second Edition,
Prentice-Hall, Englewood, NJ, 1992.
General Motors Specification A 1.0-1993, Laser Alignment Specification for New and Rebuilt
Machinery and Equipment, 1993.
Guideline For Infrared Inspection of Building Envelopes and Insulated Roofs, Infraspection
Institute, Shelburne, VT.
Guideline For Infrared Inspection of Electrical and Mechanical Systems, Infraspection Institute,
Shelburne, VT.
Guideline For Measuring and Compensating for Reflected Temperature, Emittance and
Transmittance, Infraspection Institute, Shelburne, VT.
Guideline For Measuring Distance/Target Width Ratios for Quantitative Thermal Imaging
Cameras, Infraspection Institute, Shelburne, VT.
Harris, Tedric A., Rolling Bearing Analysis, John Wiley & Sons, New York, NY, 1984.
Hewlett Packard Application Note 243-1, Effective machinery Measurement using Dynamic
Signal Analyzers, 1990.
Hewlett Packard Application Note 243, The Fundamentals of Signal Analysis, 1991.
Infraspection Institute, Guidelines for Infrared Inspection of Electrical and Mechanical Systems,
Shelburne, VT, 1993.
Jackson, Charles, The Practical Vibration Primer. Gulf Publishing Company, Houston, Texas.
1979.
Machinery Oil Analysis, Larry A. Toms, Pensacola, FL, 1995. (Contact at 5018 High Pointe Dr.,
Pensacola, FL 32505-1825).
MIL-STB-2194 (SH), Infrared Thermal Imaging Survey Procedure for Electrical Equipment.
Mitchell, John S., Machinery Analysis and Monitoring, Penn Well Books, Tulsa, OK, 1981.
National Fluid Power Association, NFPA T2.9.1-1972, Method for Extracting Fluid Samples
from the Lines of an Operating Hydraulic Fluid Power System for Particulate Particle
Contamination Analysis, 1992.
Nowlan, F.S. and Heap, H.F. Reliability-Centered Maintenance, Dolby Access Press, San
Francisco, CA 1978.
Proceedings of the 44th Meeting of the Mechanical Failures Prevention Group, Current
Practices and Trends in Mechanical Failure Prevention, Vibration Institute, 1990.
CSI http://www.compsys.com
Datastream http://www.dstm.com
Entek/IDR http://www.entekird.com
Flir Systems http://www.flir.com
HSB ReliabilityTech. http://www.hsbrt.com
Inframetrics http://www.inframetrics.com
Infraspection Institute http://www.infraspection.com
JB Sysytems http://www.jbsystems.com
Ludeca Inc. http://www.ludeca.com
Maintenance Technology Mag. http://www.mt-online.com
MIMOSA http://www.hsb.com/pcm/mimosa/mimosa.com
National Reliability Eng. Center http://www.enre.umd.edu/mainnojs.html
Monarch Monitoring http://www.easylaser.com
Penn State University http://wisdom.arl.psu.edu/
Plant Engineering Online http://www.manufacturing.net/magazine/planteng
PdMA http://www.pdma.com
Predict http://www.predict.com/
Raytek http://www.raytek.com
Reliability Center http://www.reliability.com
Reliability Magazine http://www.reliability-magazine.com
SPM Instrument http://www.spminstrument.se
UE Systems http://www.uesystems.com
Vibra-Metrics http://www.vibrametrics.com
VibrAlign, Inc. http://www.vibralign.com/
Vibration Specialty http://www.vib.com/
The vendors listed here are representative of those producing PT&I equipment, services, and/or
training.
VIBRATION MONITORING
INFRARED THERMOGRAPHY
ULTRASONICS—Airborne Passive
ULTRASONICS—Active Pulse
CABLE TESTING
FORWARD
It is recommended that Vibration Certification of all new and rebuilt machinery and equipment
be a part of implementation of Reliability Centered Maintenance. Vibration analysis and
certification, as a part of machine performance evaluation will:
• Allow verification of machine performance and condition throughout the machine's life
This appendix provides engineering performance guidelines for use by Facilities Operations and
Maintenance as well as machinery and equipment builders during the design, development, and
building of new equipment and the rebuild of existing equipment. The vibration limits specified
by the user and acknowledged by the contractor establish a common goal of acceptability by
both parties. Such limits also enable contractors to provide evidence of the superiority and build
integrity of their product.
18
Acknowledgments: We wish to thank General Motors for the free use of their alignment and vibration
specifications, which are included in this document. This document may be copied in whole or in part for the use of
providing standards for maintainability of equipment.
TABLE OF CONTENTS
1.0 PURPOSE
2.0 SCOPE
3.0 INSTRUMENTATION
3.1 FFT ANALYZER
3.2 MEASUREMENT SYSTEM ACCURACY
3.3 MEASUREMENT SYSTEM CALIBRATION
3.4 VIBRATION TRANSDUCERS
9.2 FANS
9.3 PUMPS
9.4 GEARBOXES
9.5 DEFAULT VIBRATION LEVEL LIMITS
9.6 COMPLETE MACHINE
GLOSSARY
FIGURES
Figure 1 Measurement System Frequency Response
Figure 9.3.1 Line Amplitude Acceptance Limits for Positive Displacement & Centrifugal
Pumps
Figure 9.3.2 Band-Limited Overall Amplitude Acceptance Limits for Positive Displacement &
Centrifugal Pumps
Figure 9.5.1 Default Line Amplitude Acceptance Limits for Non-Machine Tools
Figure 9.5.2 Default Band-Limited Overall Amplitude Acceptance Limits for Non-Machine
TABLES
Table 9.3 Maximum Allowable Vibration Levels for Positive Displacement & Centrifugal Pumps
VIBRATION STANDARD
FOR NEW AND REBUILT MACHINERY AND EQUIPMENT
1.0 PURPOSE
• Reduce operating costs by establishing acceptable vibration levels for new and
rebuilt rotating machinery and equipment.
2.0 SCOPE
• Acceptable limits for vibration levels generated by new and rebuilt rotating
machinery and equipment.
Vibration measurements will be made with an FFT analyzer. The type, model, serial
number(s) and latest certified calibration date of all equipment used in the measurement
of vibration levels for machine certification, shall be recorded and made available upon
request.
The measurement system (FFT analyzer, cables, transducer and mounting) used to
take vibration measurements for machine certification and acceptance shall have a
measurement system Amplitude accuracy over the selected frequency range as
follows:
Amplitude
+R%
Relative
0
Response
-R%
3.4.2 The mass of the accelerometer and its mounting shall have minimal
influence on the frequency response of the system over the selected
measurement range. (Typical mass of accelerometer and mounting should
not exceed 10 % of the dynamic mass of the structure upon which the
accelerometer is mounted.) Reference Appendix for Dynamic Mass
definition and Procedure to Determine Mass Effect
4.1 AXIAL DIRECTION (A) shall be parallel to the rotational axis of the machine
(reference Figures 2 and 3.
For motors or pumps that are end mounted, vertical readings shall be taken in a
radial direction relative to axial readings on a surface opposite the machine to
which the motor or pump is attached (reference Figure 3).
• In the direction of the shaft (rotor) rotation (Reference Figure 2 and 3).
4.5 OTHER:
A
MACHINE TOP VIEW
H
A = AXIAL
V = VERTICAL
H = HORIZONTAL
V
A
H
MACHINE SIDE VIEW V
A
DIRECTION V
OF SHAFT
ROTATION
PUMP H
AND/OR DIRECTION
MACHINE MOTOR OF SHAFT
ROTATION PUMP AND/OR MOTOR
H
V
A MACHINE
5.1 CONVENTIONS
Follow the convention specified in Sections 4.0 and 5.0, unless specified
otherwise by the purchaser.
5.1.2 Measurement locations used for machine certification and acceptance shall be
identified on the machine layout drawing and/or machine as mutually agreed
upon by the purchaser and the contractor.
5.2 ACCESSIBILITY
5.2.2 In the event that vibration monitoring points will be rendered inaccessible
after the machine is built or access to the measurement points would present a
safety problem during measurement, the purchaser shall be contacted to
determine if Permanently mounted transducers are to be installed.
Position 1 designates the "out-board" Starting Power Point bearing location of the
driver unit of the machine. Position N designates the bearing location at the
"terminating" Power Point bearing location of the driven machine. (Reference
Figure 4)
MACHINE
MACHINE #2
5.4 DOCUMENTATION
• Station or Machine
• Component (Reference Table 1)
• Position
• Orientation
COMPONENT
EQUIPMENT ID
POSITION
ORIENTATION
RP0645-00 M O V
6.1.3 For a stud mounted transducer the machine's surface at which vibration
measurements are to be taken shall be in accordance with that specified by
the transducer manufacturer (torque, grease, etc.) Designated transducer
type to be specified by the purchaser.
6.1.5 The vibration transducer as mounted must be such that the measurement
system Amplitude accuracy over the selected frequency range equals or
exceeds the requirements specified in Section 3.1.
6.2.1 Where a machine can be tested as an individual unit (e.g. motor, spindle,
etc.) the machine must be mounted as specified in Section 9.
6.2.2 Where an individual machine can be tested only as an assembled unit (e.g.
motor/pump, motor/fan, etc.), the machine mounting conditions shall be as
1(H,V) 2(H,V,A)
1(H,V,A)
2(H,V)
4(H,V,A) 3(H,V,A)
3(H,V,A)
4(H,V,A)
MOTOR & FAN
(a) FLUID TRANSFER PUMP
(b)
679 RPM
Vibration data for machine certification and acceptance shall be expressed in the
following measurement units:
7.2.1 Mandatory Bands Band 1 shall be (0.3 - 0.8) X Running Order. Band 2
shall be (0.8 - 1.2) X Running Order. Band 3 shall be (1.2 - 3.5) X
Running Order
To be Determined for
Specific Machine Classification
A
M
P BAND BAND BAND BAND BAND BAND
L 1 2 3 4 5 N
I
T
U
D
E
• A line of resolution will have a band width ∆f = 300 CPM unless specified
otherwise (Reference Section 7.4 requirement for total energy in a peak), or
unless the ∆f = 300 CPM restriction would result in less than 400 lines of
resolution over the frequency range specified for certification, in which case
the resolution requirement will default to 400 lines. (Greater resolution may
be required to resolve "Side Bands," or in Band 1 to resolve machine
vibration between 0.3X and 0.8X Running Speed.
as defined by the following equation, shall not exceed the Overall Amplitude
Acceptance Limit specified for the Band
∑ A
2
i
A = i =1
1 .5
A = Overall vibration level in the Band
Ai = Amplitude in the ith line of resolution in the Band
(I=1) = The first line of resolution in the Band
(i=N) = The last line of resolution in the Band
N = The number of lines of resolution in the Band
7.4.2 The amplitude range sensitivity of the FFT Analyzer shall be set to the
maximum input sensitivity possible without overloading such that the
actual measurement uses at least 60 dB of the Dynamic Range.
• Hanning Window.
7.4.4 The transducer mounting shall be such that the measurement system
Amplitude accuracy over the selected frequency range equals or exceeds
the requirements specified in Section 3.1. This may require the use of
more than one accelerometer where potentially high frequencies might
occur (such as gear mesh or harmonics of gear mesh) along with lower
frequencies (such as due to unbalance, misalignment, looseness, etc.)
7.5 ALIGNMENT
Consideration shall be given to any "thermal growth" that may occur during the
normal operation of the machine that would cause the machine to "grow out of
alignment" to the extent that the alignment tolerances of this specification would
not be met.
7.6 BALANCING
7.6.1 STANDARD KEY. For rotating machines and machine components with
a keyed shaft, balancing will achieved using a standard one-half key in the
key seat in accordance with ISO 8821-1989. If a "full key",
corresponding to the half key used for balancing, is not provided with the
rotating machine, a tag, as shown in Figure 8, will be attached to the
machine indicating the dimension of the key used to perform the balance
test.
7.6.2 The use of solder or similar deposits to achieve rotor balance is not
acceptable. Any parent metal removed to achieve dynamic or static
balance shall be drilled out in a manner which will maintain the structural
integrity of the rotor.
8.1 QUOTATION
8.1.1 The Quotation shall specify that the equipment will meet the applicable
vibration level limits in Section 9 of this Specification - or the vibration
level limits (if different from Specification V1.0 (Latest Version) specified
by the purchaser in the "Request for Quote."
8.1.2 The Quotation shall state the applicable specification vibration level limits
being quoted.
8.1.3 Any additional costs required to meet the specification limits shall be
grouped in a separate section of the Quotation and titled "VIBRATION
LIMITS." Costs must be itemized and sufficiently detailed to permit a
complete evaluation by the Purchaser.
8.2.3 Vibration data for machine certification shall be measured during "run-off'
at the vendor's facility. Where it is impractical to set-up and test a
complete machine at the vendor's facility, arrangements shall be made to
perform the test at the purchaser's facility. Under this circumstance,
shipment of the equipment does not relieve the vendor of the
responsibility for meeting the specified vibration level limits.
8.2. 4 The purchaser shall have the option to verify vibration data of equipment
during machine "run-off' at the vendor's test site prior to shipment - or at
the plant site per Section 8.2.3 - prior to final acceptance authorization.
8.2.5 The machine layout drawing shall be submitted as a part of the Machine
8.3 ACCEPTANCE
9.1 ELECTRIC MOTORS -- Refer to Section 9.1 Vibration Standards for Electric
Motors."
SECTION 9.1
9.1.1.4.2 All new and rebuilt motors shall conform to the vibration limits
specified in Table 9.1 when tested in accordance with this
specification.
FIRST ACTUAL
CRITICAL SPEED LOCATION
ROTOR DESIGN
Rigid Shaft At least 25% Above Rated Motor Speed
Flexible Shaft Maximum of 85% of Motor Speed
9.1.1.6 LIMITS
9.1.2.1 The amplitude of vibration at bearing locations (Ref. Section 5) in any direction
(radial and axial as defined in Section 4) shall not exceed the values listed in
Table 9.1.
9.1.2.2 Vibration signatures of velocity and acceleration, and a listing of the maximum
peak velocity in each band for vibration measurements taken at position 1
horizontal, position 2 vertical, and position 3 axial shall be submitted as part of
the motor certification. The data shall be identified with the Motor Serial
Number, Frame Number, Model Number, Horsepower and Synchronous speed.
1 2 3 4 5 6 7 8 9 10 11 Fmax = 1 2 3 4 5 6 7 8 9 10 11 Fmax =
cpm cpm
.025 0. BAND 1
.02 .02 8
0.7
.020 0.6
.015 0.5
.01 .01
0.4 0.5g STANDARD MOTOR & SPECIAL MOTOR
.010
0.3
.005 .005
.005 0.2
BAND BAND BAND BAND BAND BAND
1 2 3 4 6 0.25g PRECISION MOTOR
5 0.1
1 2 3 4 5 6 7 8 9 10 11 Fmax = 1 2 3 4 5 6 7 8 9 10 11 Fmax =
cpm cpm
9. 1.2.4 Vibration data and signatures must be submitted with the motor to the NASA
Maintenance organization or other authorized representative before acceptance
of the motor will be authorized.
SECTION 9.2
VIBRATION STANDARDS
FOR FANS
All non-positive displacement air handling units including Induced Draft (ID) Fans,
Forced Draft (FD) Fans, Overhung Fans, Centerhung Fans, Centrifugal, Vaneaxial,
Tubeaxial, Blowers, etc.
9.2.2 BALANCING
9.2.2.3 Access to the fan rotor for field balancing shall be designed in to the system.
NOTE: It is recommended that components (rotor, shafts, sheaves) be balanced individually and then trim balanced
as a total assembly.
Fan shaft diameter shall meet bearing manufacturer specifications for shaft tolerances.
9.2.4 RESONANCE
Natural frequencies of the completely assembled fan unit shall not be excited at the
operating speed. (Running speed should be at least 25% removed from a natural
frequency of the system.)
9.2.5 LIMITS
9.2.5.1 New and Rebuilt/Repaired Fans shall conform to the vibration limits specified
in Table 9.2 when operating at specified system CFM and Fan Static Pressure.
9.2.5.2 The frequency range for fan certification shall be from Fmin = 0.3 X Running
Speed of Fan to 60,000 CPM for velocity and to 120,000 CPM for
acceleration.
9.2.5.3 For fan speeds up to 3600 RPM, the maximum velocity amplitude (inch/sec-
Peak) of vibration at bearing locations (ref. Section 5) in any direction (as
defined in Section 4) shall not exceed the Line Amplitude Band Limit values
specified in Table 9.2 and graphed in Figure 9.2.1 when determined in
accordance with Section 7.2.1 using the frequency range defined in Section
9.2.5.2.
9.2.5.4 For fan speeds up to 3600 RPM, the Band-Limited Overall vibration level of
acceleration (g's Peak) at bearing locations (ref. Section 5) in any direction (as
defined in Section 4) shall not exceed the Band-Limited Overall Amplitude
Acceptance Limit values specified in Table 9.2 and graphed in Figure 9.2.2,
when determined in accordance with Section 7.2.2 using the frequency range
defined in Section 9.2.5.2.
9.2.5.5 Acceptance limits for fans running over 3600 RPM shall be specified by the
purchaser.
.10
V .09
E .08 .075 .075
L .07
O .06
C .05 .04
. 04 .03
I .04
T .03
Y .02
BAND 1 BAND 2 BAND 3 BAND 4
.01
A
C 1.0
C 0.9
E 0.8
L 0.7
E 0.6 0.5g (Peak)
R 0.5
A 0.4
T 0.3
I 0.2 BAND 1
O 0.1
N
Fmax = 120K
FREQUENCY - CPM
Figure 9.2.2 Band Limited Overall Amplitude Acceptance Limits for Fans
9.2.6.1 Variable speed or adjustable sheaves shall not be used in the final installation.
9.2.6.2 Drive sheave and driven sheave should differ in size by 20 % or more to avoid
"beat" vibration.
SECTION 9.3
VIBRATION STANDARDS
FOR PUMPS
• Positive Displacement --including, but not limited to Piston, Gear, and Vane.
• Centrifugal.
9.3.2.5 Certification shall be performed while pumps are operating within design
specifications
9.3.3.2 Excluding the lines of resolution contained in the Pumping Frequency (PF)
Band, the Velocity Amplitude (Inch/sec-Peak) of any line of resolution,
measured at bearing locations (ref. Section 5) in any direction (as defined in
Section 4) shall not exceed the Line-Amplitude Band Limit values specified in
Table 9.3. and graphed in Figure 9.3.1, when determined in accordance with
Section 7.2.1 using the frequency range from 0.3 X Running Speed (pump
RPM) to Fmax = 120,000 CPM (2,000 Hertz)
determined in accordance with Section 7.22 using the frequency range from 0.8
X PF to 1.2 X PF.
PUMPING VELOCITY
FREQUENCY
FREQ. (INCH/SEC - PEAK)
RANGE (CPM)
BAND (PF)
5 Lines of resolution 0.075 PISTON
BAND 5
centered on PF. 0.05 VANE
Table 9.3 Maximum Allowable Vibration Levels For Positive Displacement And Centrifugal
Pumps
.10
V .09
.08 .075 .075 PISTON
E
.07 PF BAND
L
O .06
.05 .05 VANE
C .04 .04
I .04
.03 .03
T
Y .02
BAND 1 BAND 2 BAND 3 BAND 5 BAND 4
.01
NOTE: BAND 5 IS A FLOATING BAND BANDWIDTH OF THE PUMPING FREQUENCY +- 2 LINES OF RESOLUTION
ACCEPTANCE LIMITS FOR BAND 5 ARE LINE AMPLITUDE VIBRATION LEVELS
Figure 9.3.1 Line Amplitude Acceptance Limits for Positive Displacement & Centrifugal Pumps
A
C BAND 1
2.0
C 1.8
E 1.6
L 1.4 1.5g POSITIVE DISPLACEMENT
E 1.2
R 1.0
A 0.8
T 0.6 1.0g NON-POSITIVE DISPLACEMENT
I 0.4
O 0.2
N
(g’s) Fmax = 300K
FREQUENCY - CPM
Figure 9.3.2 Band-Limited Overall Amplitude Acceptance Limits for Positive Displacement &
Centrifugal Pumps
9.3.4.1 Vertically mounted pump systems with a "Vertical Mount Height" greater than
5 feet will have an allowable increase in Velocity Amplitude Acceptance
Limits in Bands 1, 2, and 3 of 5% per foot of "Vertical Mount Height" greater
than 5 feet. (e.g. A 7 foot Vertical Mount Height would yield a 10% increase
[(7 ft - 5 ft) x 5%/ft] in the Table 9.3. A Velocity Amplitude Acceptance
Limits specified for Bands 1, 2, and 3. Therefore the limit for Band 1 would be
[0.4 Inch/sec + (0.4 Inch/sec x 0.1)] = 0.44 Inch/sec-Peak.
9.3.4.2 Vertical Mount Height is defined as the furthest measurable distance from the
machine mounting to the end of the driver or the end of the pump, which ever
is greater.
SECTION 9.4
VIBRATION STANDARDS
FOR GEARBOXES
9.4.1 Gearboxes shall not exceed the Vibration Limits specified in Figures 9.4.1 and 9.4.2
GEAR BOX
LINE AMPLITUDE ACCEPTANCE LIMITS
.10
V .09
E .08 .075
L .07
O .06
C .05
.04 .04 .04
I .03 .03 .03
T .03
Y .02
BAND 1 BAND 2 BAND 3 BAND 4 BAND 5 BAND 6
.01
(IN/SEC) 1 2 3 4 5 6 7 8 9 10 11 Fmax = 120K
cpm
RUNNING SPEED
GEAR BOX
BAND LIMITED OVERALL AMPLITUDE ACCEPTANCE LIMITS
A
C 1.0g (Peak)
C 1.0
E 0.9
L 0.8
E 0.7
R 0.6 BAND 1
A 0.5
T 0.4
I 0.3
O 0.2
N 0.1
(g’s) Fmax = 3.5 X GMF
FREQUENCY - or 600K
CPM (Which ever is greater)
SECTION 9.5
VIBRATION STANDARDS
If Vibration Limit values are not available for the machine being considered, the Specification
Limit shall (unless specified otherwise by the purchaser) default to the following:
Non-machine Tools shall not exceed the Vibration Limits specified in Table 9.5 and
graphically illustrated in figures 9.5.1 and 9.5.2.
Figure 9.5.1 DEFAULT Line Amplitude Acceptance Limits for Non-Machine Tools
FREQUENCY -
GLOSSARY
ACCELERATION: The time rate of change of velocity. Typical units are ft/sec2 and g's (1 g =
32.17 ft/sec2 = 386 in/sec2 = 9.81 meter/sec2). Acceleration measurements are made with
accelerometers.
Note: By international agreement, the value 9.80665 m/s2 = 980,665 cm/s2 =
386.089 in/s2 = 32.174 ft/s2 has been chosen as the standard acceleration due to
gravity (g). ISO 2041 (1990)
ACCELEROMETER: Transducer whose output is directly proportional to acceleration. Most
commonly used are mass loaded piezoelectric crystals to produce an output proportional to
acceleration.
AMPLITUDE: A measure of the severity of vibration. Amplitude is expressed in terms of
peak-to-peak, zero-to-peak (peak), or rms. For pure sine waves only:
• Peak (P) = 1.414 x RMS
• Peak-to-Peak = 2 x Zero-to-Peak (Peak)
ANTI-ALIASING FILTER: A low-pass filter designed to filter out frequencies higher than
1/2 the sample rate in order to prevent aliasing.
ANTI-FRICTION BEARING: See ROLLING ELEMENT BEARING.
AVERAGE: The sum of the values of the measurements taken divided by the number of
measurements taken.
BALANCE: When the mass center line and rotational center line of a rotor are coincident.
BALANCING: A procedure for adjusting the radial mass distribution of a rotor by adding or
removing weight, so that the mass centerline approaches the rotor geometric centerline achieving
less vibration amplitude at rotational speed.
BAND-LIMITED OVERALL AMPLITUDE: For vibration level limits specified in terms of
"BAND-LIMITED OVERALL
AMPLITUDE LIMITS: The total vibration level "A" in a band, as defined by the following
equation, shall not exceed the Overall Amplitude Acceptance Limit specified for the Band
N
∑ A
2
i
A = i=1
W
A = Overall vibration level in the Band
Ai = Amplitude in the ith line of resolution in the Band
(i = 1) = The first line of resolution in the Band
(i=N) = The last line of resolution in the Band
N = The number of lines of resolution in the Band
FFT ANALYZER: Vibration analyzer that uses the Fast Fourier Transform to display vibration
frequency components.
IMBALANCE: Unequal radial weight distribution of a rotor system; a shaft condition such that
the mass and shaft geometric centerlines do not coincide.
INTEGRATION: A process producing a result that when differentiated, yields the original
quantity. Integration of acceleration, for example, yields velocity. Integration is performed in an
FFT Analyzer by dividing by 2πf where f is the frequency of vibration. Integration is also used
to convert velocity to displacement.)
LARGE APPARATUS AC/DC MOTORS: Reference NEMA Publication No. MG 1, Motors
and Generators, Section III
LARGE MACHINES: Part 20. Induction Machines, Part 21. Synchronous Motors, and Part
23. DC Motors.
LINEAR NON-OVERLAPPING AVERAGE: An averaging process where each Time block
sample used in the averaging process contains data not contained in other Time blocks (i.e. Non-
overlapping) used in the averaging. Linear averaging is performed in the Frequency Domain,
and each sample is weighted equally.
LINES: The total number of data points in a spectrum (e.g. 400, 800, 1600, etc.)
LINE AMPLITUDE LIMIT: The maximum amplitude of any line of resolution contained
within a band shall not exceed the Line Amplitude Acceptance Limit for the Band.
LINE OF RESOLUTION: A single data point from a spectrum which contains vibration
amplitude information. The Line of Resolution amplitude is the Band Overall Amplitude of the
frequencies contained in the ∆f Frequency Resolution.
MEASUREMENT POINT: A location on a machine or component at which vibration
measurements are made.
MICROMETER (MICRON): One millionth (0.000001) of a meter. (1 micron = 1 x 10-6
meters = 0.04 mils.)
MIL: One thousandth (0.001) of an inch. (1 mil = 25.4 microns.)
NATURAL FREQUENCY: The frequency of free vibration of a system when excited with an
impact force. (Bump Test).
ORDER: A unit of frequency unique to rotating machinery where the first order is equal to
rotational speed. See FREQUENCY
BAND LIMITED OVERALL READING: The vibration severity amplitude measured over a
frequency range defined by a FMIN and a FMAX
PEAK: Refers to the maximum of the units being measured, i.e., peak velocity, peak
acceleration, peak displacement.
PEAK-TO-PEAK: Refers to the displacement from one travel extreme to the other travel
extreme. In English units, this is measured in mils (.001 inch) and in metric units it is expressed
in micro-meter µM (.000001 meters).
PERIOD: The amount of time, usually expressed in seconds or minutes, required to complete
one cycle of motion of a vibrating machine or machine part. The reciprocal of the period is the
frequency of vibration.
PHASE (PHASE ANGLE): The relative position, measured in degrees, of a vibrating part at
any instant in time to a fixed point or another vibrating part. The Phase Angle (usually in
degrees) is the angle between the instantaneous position of a vibrating part and the reference
position. It represents the portion of the vibration cycle through which the part has moved
relative to the reference position .
PRECISION SPINDLE: Spindles used in machining processes which require high accuracy,
high speed, or both.
RADIAL MEASUREMENT: Measurements taken perpendicular to the axis of rotation.
RADIAL VIBRATION: Shaft dynamic motion or casing vibration which is in a direction
perpendicular to the shaft centerline.
RESONANCE: The condition of vibration amplitude and phase change response caused by a
corresponding system sensitivity to a particular forcing frequency. A resonance is typically
identified by a substantial amplitude increase and related phase shift.
RIGID ROTOR: A rotor that does not deform significantly at running speed. A rotor whose
parts do not take up motion relative to each other, i.e., all points move in the same direction at
the same instant of time. A rotor is considered rigid when its speed is less than 75% of its lowest
natural frequency in bending.
RMS: (Root mean square) Equal to 0.707 times the peak of a sinusoidal signal.
ROLLING ELEMENT BEARING: Bearing whose low friction qualities derive from rolling
elements (balls or rollers), with little lubrication.
ROTATIONAL SPEED: The number of times an object completes one complete revolution
per unit of time, e.g., 1800 RPM.
SIDE BAND: Equals the frequency of interest plus or minus one times the frequency of the
exciting force.
SIGNATURE (SPECTRUM): Term usually applied to the vibration frequency spectrum
which is distinctive and special to a machine or component, system or subsystem at a specific
point in time, under specific machine operating conditions, etc.
Usually presented as a plot of vibration amplitude (displacement, velocity or acceleration) versus
time or versus frequency. When the amplitude is plotted against time it is usually referred to as
the TIME WAVE FORM.
SMALL (FRACTIONAL) AND MEDIUM (INTEGRAL) HORSEPOWER AC/DC
MOTORS: Reference NEMA Publication No. MG 1, Section II SMALL (FRACTIONAL)
AND MEDIUM (INTEGRAL) MACHINES. Part 12. Tests and Performance - AC and DC
Motors.
TIME DOMAIN: Presentation of a signal whose amplitude is measured on the Y axis and the
time period is measured on the X axis.
TRANSDUCER (PICKUP) -VIBRATION: A device that converts shock or vibratory motion
into an electrical signal that is proportional to a parameter of the vibration measured. Transducer
selection is related to the frequencies of vibration which are important to the analysis of the
specific machine(s) being evaluated/analyzed.
This appendix contains the correlation relationships between the various PT&I technologies (see paragraph 3.3.1).
Advanced Filtration/ Debris For all lubricated bearings indication that damage to
Trending Confirm bearing damage.
Analysis bearing surfaces has occurred.
Advanced Filtration/ Trending Major bearing damage has occurred when material appears
Routinely, with every filter cleaning or change.
Debris Analysis Time coincident in lubricating system filters.
Table F–3. Correlation of Lubricant & Wear Particle Analysis with Other Technologies
Vibration Time coincident Significant vibration accompanies rising temperatures. On condition of suspected bearing or coupling problem.
Electrical Circuit Testing Time coincident High resistance generating heat. On condition of suspected circuit problem.
Debris analyzed and source identified by spectrographic or Routine oil samples show marked increase in level of
Lubricant Analysis Trending
other means. foreign material.
Table F–5. Correlation of Advanced Filtration & Debris Analysis with Other Technologies
Thermal Analysis (Differential Increasing T as flow decreases due to blockage or pump On condition of flow decrease/ T change across heat
Time coincident
temperatures) degradation. exchanger.
Visual inspection Trending Heat exchanger inspection shows internal fouling. To confirm reduced flow.
Moisture induced corrosion and clogging of orifices and Periodically, frequency depending on dew point
Dew Point Monitoring Trending
binding of operators. readings.
Dirt and contaminants clog orifices, restrictors and bind Periodically, frequency depending on contamination
Hydraulic oil testing Trending
valve operators. buildup.
Distinguish between unbalance, rotor bar or end ring On condition - when routine vibration analysis indicates
Vibration analysis Time coincident (MCSA)
breakage, or high resistance. possible rotor bar or end ring problems.
Thermal analysis (IRT High temperatures/high resistance in motor control and On condition. Either technology can confirm a finding of
Time coincident (TDR)
imaging) electrical cabling/circuits. the other.
Insulation and connector discoloration, corrosion, pitting and Periodically, when access is available to the busses,
Visual inspection Time coincident
other signs of deterioration caused by heat. cabling and terminal boards.
RF Monitoring Time coincident Arcing in the windings of large generators. Continuous monitoring where RF system installed.
Visual evidence of damage to valve discs and seats When valve internals are open and available for
Visual inspection Trending
sufficient to cause leakage. inspection.
Lubricant Wear Particle Abnormal wear indicating increased internal friction within Before shutdown to conduct investigation of a
Trending
Analysis machine. suspected problem.
Visual inspection (including Time coincident Physical condition of flask/pressure vessel. Wall thickness On condition of long periods (>10%) of "wet" gas in
fiber optics) Trending reduced. system.
Time coincident Physical condition of flask/pressure vessel. Wall thickness On condition of long periods (>10%) of "wet" gas in
Ultrasonic imaging
Trending reduced. system.
Trending (Post For each condition where damaged parts are found after
Vibration Analysis Physical condition of parts are deteriorated or worn.
replacement analysis) detection by vibration analysis.
Thermal Analysis Time coincident Visual and infrared images of suspected faults. Visual image taken to accompany each IRT image.
Internal corrosion of system components (particularly When system internals are open and available for
Dew Point Measurement Trending
HP air). inspection.
Metal fatigue/intergranular stress corrosion cracking Confirms whether or not acoustic emission indications
Acoustic emission Trending
detectable in large metal vessels using ultrasonic imaging. of metal lattice breakdown are valid.
In Service Stress/Strain, Monitored stress exceeds yield point of monitored To confirm whether actual damage in the form of
Trending
Torque Measurement component. cracking or thinning has occurred.
Condition of objects being inspected for erosion, corrosion, When the item being inspected has a surface subject to
Radiography Trending
cracking or exfoliation. wall thinning or an internal volume subject to cracking.
Metal fatigue/intergranular stress corrosion cracking Confirms whether or not acoustic emission indications
Acoustic Emission Trending
detectable in large metal vessels using ultrasonic imaging. of metal lattice breakdown are valid.
In Service Stress/Strain, Abnormal strain coincident with indication of a strain-related To confirm whether actual damage in the form of
Trending
Torque Measurement defect. cracking or thinning has occurred.
Condition of objects whose near-surface volume can be Where confirmation of a defect is required before
Ultrasonic imaging Trending
scanned. opening for repair.
Relationship between temperature, temperature cycles and When needed to understand the relationships to devise
Thermal Analysis Time coincident
strain. better control measures.
Lubricant Wear Particle Trending On condition when position indicator shows bearing
Confirmation of bearing wear.
Analysis Time coincident wear.
Thermal analysis Time coincident Confirmation of bearing wear. On condition when position indicator shows wear.
Table F–18. Correlation of Ultrasonic, Eddy Current, and Photonic Position Sensors with Other Technologies
Figure F–1 depicts a simplified Chilled Water System and the various components that can be
monitored using the aforementioned correlated PT&I technologies.
Chiller
Fan
Chilled Water Line
Isolation
Valve
For example, a chilled water system would require the following PT&I techniques to be used in
order for the entire system to be evaluated:
a. Flow Rates—Chiller water flow would be measured using precision, non-intrusive flow
detectors.
d. Electrical—Motor power consumption and motor circuit testing would be used to assess
the condition of the motor circuits and to correlate with pump efficiencies.
g. Lubricant Analysis—Oil condition and wear particle analysis would be used to identify
problems with the lubricant and correlated with vibration when wear particle
concentrations exceed pre-established limits.
j. Eddy Current—Eddy current would be used to determine and locate leaking tubes.
FORWARD
It is recommended that laser alignment be used on all shaft coupled machines be a part of
implementation of Reliability Centered Maintenance. Laser alignment designed into the
machine will:
19
Acknowledgments: We wish to thank General Motors for the free use of their alignment and vibration
specifications which are included in this document. This document may be copied in whole or in part for the use of
providing standards for maintainability of equipment.
TABLE OF CONTENTS
1.0 PURPOSE
2.0 SCOPE
GLOSSARY
1.0 PURPOSE:
The purpose of this specification is to ensure that provisions for laser alignment are
designed into all new and rebuilt machine.
2.0 SCOPE:
This document addresses the use of laser alignment systems for SHAFT ALIGNMENT
NASA operations require laser alignment on all shaft coupled machines to maximize part
quality and productivity, and to eliminate premature machine failure due to
misalignment.
Coupled shaft alignment is the positioning of two or more machines so that the rotational
centerlines of their shafts are colinear at the coupling center under operating conditions.
Coupling Center
The Laser Alignment System used for Coupled Shafts Alignment shall use either a
combined laser emitter and laser target detector unit or separate units for its laser emitter
and laser target detector.
3.5.1 Laser alignment will be performed at the purchaser’s facility on all shaft
coupled machines during installation of the equipment.
3.5.2 When verifying the alignment of coupled shafts the contractor must
document and provide the following data for each set of coupled shafts:
3.6.1.2 Where bases are constructed using concrete or grouts final shaft
alignment shall not be conducted until ample curing time has
taken place. (A minimum of Thirty days is recommended)
3.6.1.6 After all welding and machining is completed, stress relieve the
entire base.
The stiffness of the machine base shall be sufficient that no foot centerline
shall deform or deflect more that .001” (.0254 mm) over the operating
range from alignment conditions to full load conditions.
3.6.4.1 After all welding and machining has been completed and the
base has been stress relieved, the surface of all pads or flats for
each machine to be installed on the base must be co-planar,
within .001 inch (0.0254 mm). (refer to figures 3a and 3b)
The feet of the driver and driven machines must not overhang the machine
base.
3.7 JACKBOLTS
Jackbolts shall be located at the front and rear feet of the movable machine for
horizontal alignment positioning. (This requirement also applies to vertically
mounted units and vertically mounted flanged units). Jackbolts shall be parallel
to the flat/pad surface and align on the center line formed by the hold down bolts
in the cross machine direction. Ample room shall be left for removal and
insertion of shims used in the vertical alignment of the coupled machines.
The use of hold down bolts is the preferred method of fastening components to
the base. Hold-down bolts shall meet the following specifications:
a. Hold-down bolts for both the driver and the driven machine(s) (in pairs or
in trains) shall be positioned (spotted) after the machine’s shafts have been
aligned.
b. Hold-down bolts shall be centered in the hole of the machine foot.
c. Hold-down bolts shall be the preferred method of fastening machines to
the base.
d. Hold-down bolts shall not be undercut (“Chicagoed”) to achieve
HORIZONTAL adjustment.
3.9 PIPING
Piping must be fitted, supported, and sufficiently flexible such that soft foot due
to movement caused by tightening pipe flanges doesn’t exceed .002” (.051 mm).
Piping must not restrict the minimum 180 degree rotation requirement of the laser
alignment system.
3.10 SHIMS
a. Commercially die-cut.
b. Made of corrosion and crush resistant stainless steel, which is
dimensionally stable when subjected to high compression over long
periods of time.
c. Consistent over the whole shim area, without seams or folds from
bending.
d. Clean, free from burrs, bumps, nicks and dents of any kind.
e. Size numbers or trademarks etched into the shim, not printed or stamped.
f. The smallest commercial shim that will fit around the hold down bolts
without binding shall be used.
g. The overall shim pack shall not exceed a total of three (3) shims.
h. Shims must rest on bare metal, not paint or other coatings.
All machines shall be installed with a minimum of .125 inch (3.0 mm)
dimensionally stable shims under each surface mounting point for vertical
mobility.
OEM’s must use only the couplings specified by the Government unless
otherwise agreed upon by the purchaser. During the alignment process coupling
play or backlash must be eliminated to accomplish a precision shaft alignment.
Axial shaft play or end-play must be no greater than .125 inch (3.175 mm).
Accommodation of end movement must be done without inducing abnormal loads
in the connecting equipment.
Elevation
Elevation
Elevation
For attachment to
existing rough surface
or structure of uncertain
condition
Elevation
4.1.1 Motors will be provided with adjustable motor bases unless otherwise
specified.
4.1.2 Motors over 5600 watts of power will be provided with adjustable, pivoted
motor bases.
4.2 RUNOUT
4.2.2 After sheaves are installed on the motor and driven shafts, the sheaves will
be checked to ensure that they are true on the shaft.
4.3.2 Unless otherwise specified, drive and driven sheaves will be aligned by
the four-point method.
4.3.3 If the sheave web thickness is not the same on the drive and driven sheave,
shims of the appropriate thickness will be used on the narrower sheave for
the alignment. The thickness of the shims will be recorded and supplied
with the machine information.
GLOSSARY
ACCESSIBLE: The ability to reach and adjust the aligning feature. Consideration should be
given to confined space restrictions, removing guards, bushing plates, hydraulic lines, lubrication
lines, electric lines etc.
ALIGNMENT TARGET SPECIFICATIONS: Desired intentional offset and angularity at
coupling center to compensate for thermal growth and/or dynamic loads. Most properly
specified as an OFFSET, and an angle in two perpendicular planes, horizontal and vertical.
ANGULAR ERROR: A misalignment condition characterized by the angular error between the
desired centerline and the actual centerline. This misalignment condition may exist in planes
both horizontal and vertical to the axis of rotation. (Reference Figure 2)
ANGULARITY: The angle between the rotational centerlines of two shafts. Angularity is a
“slope” expressed in terms of a rise (millimeters or thousandths of an inch) over a run (meter or
inches). (Reference Figure 2).
A.S.M.E.: American Society of Mechanical Engineers
345 East 47th Street
New York, NY 1017
212-705-7722
AXIAL PLAY, AXIAL FLOAT, END FLOAT: Shaft axial movement along its centerline
caused by axial forces, thermal expansion or contraction, and permitted by journal bearings,
sleeve bearings and/or looseness.
BASE PLATE: The surface, often made of steel plate or cast iron, to which the feet of a
machine are attached. (Reference Figure 3a and 3b)
CO-LINEAR: Co-linear means two lines that are positioned as if they were one line. Co-linear
as used in alignment means two or more centerlines of rotation with no offset or angularity
between them. Two or more lines are co-linear when there is no offset or angularity between
them (i.e. they follow the same path).
COPLANAR: The condition of two or more surfaces having all elements in one plane. (per
ANSI Y14.5)
COUPLING POINT: The phrase “COUPLING POINT” in the definition of SHAFT
ALIGNMENT is an acknowledgment that vibration due to misalignment originates at a the point
of power transmission, the coupling. The shafts are being aligned and the coupling center is just
the measuring point.
FULL BEARING FITTING SPACER BLOCK: A single spacer block used for aligning the
machine tool in the vertical plane.
FLATNESS: The condition of a surface having all elements in one plane. (Per ANSI Y 14.5.)
Note: As used in this specifications, a flat is a small surface flush with or cut into a
BASE PLATE, machined flat, and co-planar with the other flats in the base plate. The
flats support the Shims and/or feet of the machine to be installed. A pad is a small block
of metal that serves to elevate the feet of the machine above the surface of the base plate.
Pads are commonly used compensate for differences in machine center line heights, and
for increased corrosion resistance by raising the machine feet out of any possible standing
fluids. Pads and flats have holes drilled and tapped in their centers to accept hold down
bolts.
HORIZONTAL: Parallel to the mounting surface.
JACKBOLTS, JACKSCREWS: Positioning bolts on the machine base which are located at,
each foot of the machine and are used to adjust the position of the machines.
LEVEL: Parallel to a reference plane or a reference line established by a laser.
MACHINE: The total entity made up of individual machine components such as motors,
pumps, spindles, fixtures, etc. Also reference MACHINE COMPONENT.
MACHINE BASE: The structure that supports the machine or machine components under
consideration.
MACHINE COMPONENT: An individual unit such as a motor, pump, spindle, fixture, etc.
often referred to as a machine in its own context.
MACHINE DEPENDENT: A condition that is dependent on the machining operation and the
design requirement of the part being machined.
N.I.S.T. : National Institute of Standards and Technology
Building 304, Room 139
Gaithersburg, MD 20899
301-975-3503
OFFSET: The distance (in thousands of an inch or in millimeters) between the rotational
centerlines of two parallel shafts. (Reference Figure 1).
PITCH: An angular misalignment in the vertical plane. (ANSI/ASME b5.54-1991)
POSITION ERROR (CENTERLINE/OFFSET MISALIGNMENT): A misalignment
condition that exist when the shaft centerline is parallel but not in line with (not coincidental)
with the desired alignment centerline. (Reference Figure 1).
QUALIFYING LEVEL POINTS: Qualified leveling points are locations that have their
heights defined and must be in same plane. That plane must be parallel to the mounting surfaces
of the slide assembly.
REPEATABILITY: The consistency of readings and results between consecutive sets of
measurements.
SHAFT ALIGNMENT: Positioning two or more machines (e.g. a motor driving a hydraulic
pump(s), etc.) so that the rotational centerlines of their shafts are collinear at the coupling center
under operating conditions. (Reference Figure 2)
SOFT FOOT: A condition that exists when the bottom of all of the feet of the machinery
components are not on the same plane (can be compared to a chair with one short leg). Soft foot
is present if the machine frame distorts when a foot bolt is loosened or tightened. It must be
corrected before the machine is actually aligned.
PARALLEL SOFT FOOT: A parallel gap between the machine foot and its support surface.
ANGULAR SOFT FOOT: An angled gap between the machine foot and its support surface.
INDUCED SOFT FOOT: A type of soft foot that is caused by external forces, ( pipe strain,
coupling strain, etc.,) acting on a machine independent of the foot to base plate connection.
“SQUISHY” SOFT FOOT: A type of soft foot characterized by material, (could be Shims,
paint, rust, grease, oil, dirt, etc.) acting, like a spring between the underside of the machine foot
and the base plate contact area.
SPACER BLOCKS: See FULL BEARING FITTING SPACER BLOCK.
STRESS FREE CONDITION: The condition that exists when there are no forces acting on the
structure of a machine, machine component, or machine base that would cause distortion in the
structure such as bending, twist, etc.
THERMAL EFFECTS (GROWTH OR SHRINKAGE): This term is used to describe
displacement of shaft axes due to machinery temperature changes (or dynamic loading effects)
during start-up.
TOLERANCE, DEADBAND, WINDOW, OR ENVELOPE: An area where all misalignment
forces sum to a negligible amount and no further improvement in alignment will reduce
significantly the vibration of the machine or improve efficiency.
TOLERANCE VALUES: Maximum allowable deviation from the desired values, whether
such values are zero or non-zero.
VERTICAL: Perpendicular to the horizontal plane.
YAW MISALIGNMENT: An angular misalignment in the horizontal plane.
FORWARD
It is recommended that Balance Certification of all new and rebuilt machinery and equipment be
a part of implementation of Reliability Centered Maintenance. Precision balance and
certification, as a part of machine performance evaluation will:
• Allow verification of machine performance and "health" throughout the machine's life.
The BALANCE STANDARD FOR NEW AND REBUILT MACHINERY AND EQUIPMENT
provides engineering performance guidelines for use by Facilities Operations and Maintenance
as well as machinery and equipment builders during the design, development, and building of
new equipment and the rebuild of existing equipment. The balance quality, specified by the user
and acknowledged by the contractor, establishes a common goal of acceptability by both parties.
Such quality, also enables contractors to provide evidence of the superiority and build integrity
of their product.
20
Acknowledgments: We wish to thank General Motors for the free use of their alignment and vibration
specifications which, are included in this document. This document may be copied in whole or in part for the use of
providing standards for maintainability of equipment.
TABLE OF CONTENTS
1.0 PURPOSE
2.0 SCOPE
GLOSSARY
Table 2 Balance Quality Grades for various groups of Representative Rigid Rotors
(ISO 1940/1-1986)
1.0 PURPOSE
• Reduce operating costs by establishing acceptable balance grades for new and
rebuilt rotating machinery and equipment.
2.0 SCOPE
This standard establishes acceptable quality for balance of new and rebuilt rotating
machinery and equipment purchased.
If no other limit is specified, the vibration criteria listed in Table 1 will be used for
acceptability of the machine in question. The vibration criteria are for the vibration
amplitude at the fundamental rotational frequency or one times running speed (1X).
This is a narrowband limit. An overall value is not acceptable.
Nominal
Shaft Speed Maximum Vibration Maximum Displacement
(RPM) (in/sec, Peak) (mils, Peak-to-Peak)
Table 2 provides the ISO1940/1-1986 balance quality grades for various groups of
representative rigid rotors. The RCM Guide contains more detailed information and
the complete ISO 1940/1 –1986 table.
Product of The
Balance
Relationship
Quality Rotor Types—General Examples
(eper x ω)1,2
Grade
mm/s
Crankshaft/drives of rigidly mounted fast diesel engines with six or more
G100 100 cylinders4
Complete engines (gas or diesel) for cars, trucks, and locomotives5
Grinding-machines drives
G1 1
Small electric armatures with special requirements
Table 2. Balance Quality Grades for Various Groups of Representative Rigid Rotors (ISO 1940/1-
1986)
For rotating machines and machine components with a keyed shaft, balancing will
achieved using a standard one-half key in the key seat in accordance with ISO 8821-
1989. If a "full key", corresponding to the half key used for balancing, is not
provided with the rotating machine, a tag, as shown in Figure 1, will be attached to
the machine indicating the dimension of the key used to perform the balance test.
A
A = Key length as used for balancing this rotor
B (usually in the form of a “half depth”
3.4.2 Clip-on" balancing weights can only be used on centrifugal type fans and
must be located and attached on the ID pitch of the blades such that the
rotational motion of the fan creates a positive seating of the "clip-on"
weight against the fan blade.
3.4.4 Any parent metal removed to achieve dynamic or static balance shall be
drilled out in a manner which will maintain the structural integrity of the
rotor or sheave.
3.4.5 Access to any fan rotor for field balancing shall be designed in to the
system.
4.1 QUOTATION
4.1.1 The Quotation shall specify that the equipment will meet the applicable
balance quality of this Specification - or the balance quality (if different
from Specification B1.0 Latest Version) specified by the purchaser in the
"Request for Quote."
4.1.2 The Quotation shall state the applicable specification balance quality
being quoted.
4.1.3 Any additional costs required to meet the specification quality shall be
grouped in a separate section of the Quotation and titled "BALANCE
QUALITY". Costs must be itemized and sufficiently detailed to permit a
complete evaluation by the Purchaser.
4.2.3 Balance quality for machine certification shall be measured prior to "run-
off' at the vendor's facility. Where it is impractical to set-up and test a
4.2.4 The purchaser shall have the option to verify balance quality of equipment
during machine "run-off' at the vendor's test site prior to shipment - or at
the plant site per Section 4.2.3 - prior to final acceptance authorization.
4.3 ACCEPTANCE
GLOSSARY
ACCELERATION: The time rate of change of velocity. Typical units are ft/sec2 and g's (1 g =
32.17 ft/sec2 = 386 in/sec2 = 9.81 meter/sec2). Acceleration measurements are made with
accelerometers.
Note: By international agreement, the value 9.80665 m/s2 = 980,665 cm/s2 =
386.089 in/s2 = 32.174 ft/s2 has been chosen as the standard acceleration due to
gravity (g). ISO 2041 (1990)
ACCESSIBLE: The ability to reach and adjust the aligning feature. Consideration should be
given to confined space restrictions, removing guards, bushing plates, hydraulic lines, lubrication
lines, electric lines etc.
AMPLITUDE: A measure of the severity of vibration. Amplitude is expressed in terms of
peak-to-peak, zero-to-peak (peak), or rms. For pure sine waves only:
• Peak (P) = 1.414 x RMS
• Peak-to-Peak = 2 x Zero-to-Peak (Peak)
BALANCE: When the mass centerline and rotational centerline of a rotor are coincident.
BALANCING: A procedure for adjusting the radial mass distribution of a rotor by adding or
removing weight, so that the mass centerline approaches the rotor geometric centerline achieving
less vibration amplitude at rotational speed.
CALIBRATION: A test to verify the accuracy of measurement instruments.
COMPLETE MACHINE: A complete machine is defined as the entire assembly of
components, sub-components, and structure, which is purchased to perform a specific task(s).
On a Complete Machine Assembly with all individual components operating in their normal
operating condition, mode, and sequence, the Component Balance Quality for the complete
machine acceptance are the same as when the component is tested individually.
DISPLACEMENT: The distance traveled by a vibrating object. For purposes of this
document, displacement represents the total distance traveled by a vibrating part or surface from
the maximum position of travel in one direction to the maximum position of travel in the
opposite direction (Peak-to-Peak) and is measured in the unit mil (1 mil = 0.001 inch).
FIELD BALANCING: The process of balancing a rotor in its own bearings and supporting
structure rather than in a balancing machine.
FLEXIBLE ROTOR: A rotor that deforms significantly at running speed. This term is used
for rotors that operate close to or above their first critical speed. A rotor is considered flexible
when its speed is more than 75% of its lowest natural frequency in bending.
FREQUENCY: The repetition rate of a periodic event, usually expressed in cycles per second
(Hertz -abr. HZ), cycles per minute (CPM), or multiples of rotational speed (Orders). Orders are
commonly referred to as IX for rotational speed, 2X for twice rotational speed, etc. Frequency is
the reciprocal of the Period.
NOTE: Vibration frequencies are expressed in Hertz (cycle per sec) or CPM (cycle per
minute). Rotational speed (Running Speed) is expressed in RPM (Revolutions per
minute).
HERTZ (Hz): The unit of frequency represented by cycles per second.
IMBALANCE: Unequal radial weight distribution of a rotor system; a shaft condition such that
the mass and shaft geometric centerlines do not coincide.
LARGE APPARATUS AC/DC MOTORS: Reference NEMA Publication No. MG 1, Motors
and Generators, Section III
LARGE MACHINES: Part 20. Induction Machines, Part 21. Synchronous Motors, and Part
23. DC Motors.
LEVEL: Parallel to a reference plane or a reference line established by a laser.
MACHINE: The total entity made up of individual machine components such as motors,
pumps, spindles, fixtures, etc. Also reference MACHINE COMPONENT.
MACHINE COMPONENT: An individual unit such as a motor, pump, spindle, fixture, etc.
often referred to as a machine in its own context.
MICROMETER (MICRON): One millionth (0.000001) of a meter. (1 micron = 1 x 10-6
meters = 0.04 mils.)
MIL: One thousandth (0.001) of an inch. (1 mil = 25.4 microns.)
N.I.S.T. : National Institute of Standards and Technology
Building 304, Room 139
Gaithersburg, MD 20899
301-975-3503
ORDER: A unit of frequency unique to rotating machinery where the first order is equal to
rotational speed. See FREQUENCY
PEAK: Refers to the maximum of the units being measured, i.e., peak velocity, peak
acceleration, peak displacement.
PEAK-TO-PEAK: Refers to the displacement from one travel extreme to the other travel
extreme. In English units, this is measured in mils (.001 inch) and in metric units it is expressed
in micro-meter µM (.000001 meters).
RIGID ROTOR: A rotor that does not deform significantly at running speed. A rotor whose
parts do not take up motion relative to each other, i.e., all points move in the same direction at
the same instant of time. A rotor is considered rigid when its speed is less than 75% of its lowest
natural frequency in bending.
RMS: (Root mean square) Equal to 0.707 times the peak of a sinusoidal signal.
ROTATIONAL SPEED: The number of times an object completes one complete revolution
per unit of time, e.g., 1800 RPM.
SMALL (FRACTIONAL) AND MEDIUM (INTEGRAL) HORSEPOWER AC/DC
MOTORS: Reference NEMA Publication No. MG 1, Section II SMALL (FRACTIONAL)
AND MEDIUM (INTEGRAL) MACHINES. Part 12. Tests and Performance - AC and DC
Motors.
TOLERANCE VALUES: Maximum allowable deviation from the desired values, whether
such values are zero or non-zero.
UNBALANCE: See IMBALANCE
VELOCITY: The time rate of change of displacement with respect to some reference position.
For purposes of this document, velocity is measured in the units Inch per second-Peak.
1.0 SCOPE
This specification together with the Data Sheets covers the Repair and Reconditioning of AC
Induction Motors. The purpose of this specification is to establish the minimum standards and
documentation recommended for the repair and refurbishment of 3-phase AC Motors.
These specifications are in addition to the industry accepted practices as stated in the following
Standards and Codes:
IEEE 1068-1990 Recommended Practice for the Repair and Rewinding of Motors
for the Petroleum and Chemical Industry
IEEE 43-1974 Recommended Practice for Testing Insulation Resistance of
Rotating Machinery
IEEE 95-1977 Recommended Practice for Insulation Testing of Large AC
Rotating Machinery with High Direct Voltage
NEMA MG 1-1987 Motors and Generators
ISO 1940 Unbalance Tolerance Guide for Rigid Rotors
ISO 3945-1977 Mechanical Vibration of Large Rotating Machines with Speed
range from 10-200 rev/s-Measurement and Evaluation of
Vibration Severity in Situ
EASA Standards for the Repair of Electrical Apparatus, February 1992
SKF Engineering Data Handbook dated December 1980
2.1 All repairs to Explosion-Proof, Dust Ignition-Proof, or other severe duty motors will
not compromise their original UL Certification.
3.1 Incoming Inspection: Each machine shall have all nameplate information, all
hardware (i.e., coupling, hub, lifting eyes, etc.), and general condition noted. In
addition, note any damaged or broken parts and, if possible, the primary cause of
failure. The endbells shall be matchmarked.
Visually inspect the stator windings for damage, tightness, cracked insulation, and the
general condition of the motor leads. Report all damage.
3.2 Cleaning: All windings and parts must be cleaned free from dirt, grit, grease, and
oil. Cleaning agents shall be completely removed by steam cleaning then, dried by
baking at a maximum temperature of 3000F. Winding temperature shall not exceed
1760F during the drying process.
3.3 Stripping: Defective windings will be removed in such a manner that no mechanical
damage is done to the laminations or frame. Winding burnout shall be done in a
temperature controlled environment to ensure the stator iron temperature does not
exceed 6500F.
3.4 Insulation System: All insulation and components which make up the insulation
system shall be rated NEMA Class F. All varnishes and coatings shall be compatible
with the insulation. Vacuum pressure impregnation (VPI) is the preferred method of
varnish application.
3.5 Motor Leads: The motor leads shall have a temperature and insulation rating equal
to or greater than the temperature and insulation rating of the insulation system.
Leads on totally enclosed fan cooled (TEFC) and explosion-proof apparatus shall be
properly sealed to meet the original classification of the motor.
3.6 Exterior Finish: The apparatus shall be externally cleaned, sandblasted, and
refinished with primer and a good quality enamel paint. Each repaired motor shall be
labeled with a metal tag which states the name of the repair company and the date of
repair.
3.7 Shipment: Block the shaft to prevent axial travel. Cover the motor with plastic to
protect from weather during shipment. For motors shipped without sufficient
lubricant for industrial operation, attach a red tag labelled "Lubrication Required" to
each fill point.
4.0 SHAFTS
4.1 Inspection: Shafts shall be checked for unusual wear, scoring, and straightness. On
motors greater than 100 HP, a dye penetrant inspection of the shaft is required.
4.2 Bearing Journals and Shaft Extensions: The bearing journals and shaft extension
shall be concentric with the shaft center, smooth polished, and of proper size and fit.
A minimum of two readings using a dial indicator per shaft are required. The
tolerance for total indicated runout (TIR) regardless of shaft size or motor horsepower
are:
4.3 Axial End Play: Total end play in sleeve bearing motors shall be approximately
1/16" per inch diameter of the shaft journal. For rolling element bearings, if
minimum end play tolerances are not provided on motor drawings a value of 0.003
inch should be used.
900 0.002
1200 0.002
1800 0.0015
3600 0.001
4.4 Balancing: All motors greater than 5 HP shall be balanced as close to operating
speed as possible to ISO 1940 G-2.5 using one of the following:
The balance report shall be included with the motor and include the following: Initial
and final imbalance, location and weight used, length of key stock used, and rotor
weight.
5.0 BEARINGS
All bearings are to be replaced unless otherwise specified. Replacement of the bearings
with a brand or model other than originally installed must be approved by the
Government.
The shaft bearings shall be grease lubricated, anti-friction bearings with minimum L-10
life rating of 40,000 hours in accordance with the Anti-Friction Bearing Manufactures'
Association (AFBMA) method in determining expected bearing life. Bearings must be
able to withstand the loads due to dead weight, unbalance and thrust of rotor assembly.
Bearings shall be rated for 24 hour per day continuous duty service.
5.1 Ball and Roller Bearings: Ball and roller bearings shall be free from defects or
contamination. As a minimum, Annular Bearing Engineers' Committee (ABEC) and
Roller Bearing Engineers' Committee (RBEC) Tolerance 1 bearings shall be used
unless otherwise specified.
For high speed motors (>1800 RPM) , a bearing with an internal clearance of C3 shall
be used.
5.2 Sleeve Bearings: Sleeve bearings are to be checked for cracks or babbitt disbonding
by performing a dye penetrant test.
5.2.1 Installation: Sleeve bearings shall be fitted to the journals using a nondrying
bluing compound. A minimum of 80% contact between the babbitt and the
shaft journal is required. Vendor to specify the method for determining
clearance.
6.1 Inspection: Visual inspect the rotor for iron damage, rub marks, and overheating of
the rotor bars. Magnetically inspect or Growler test the bars for cracks.
6.2.1 Insulation Resistance: Apply the following test voltage for one (1) minute:
200-600 1000
2400-4800 2500
6.2.2 Polarization Index (PI): Perform a ten (10) minute polarization index test on
the motor by applying a DC voltage equal to the motor nameplate voltage and
recording the readings at one(1) and ten (10) minutes. A minimum PI value
of 2.0 must be obtained before performing any overvoltage test.
6.2.4 High DC Potential and Comparative Surge Test: Perform the tests at the
following voltages (2X Rated Voltage +1000V):
6.2.5 Phase Imbalance Tests: The three phases of the motor shall be checked for
proper impedance balance by conducting a no-load test and recording the
voltage and current of all three phases. A maximum current imbalance of
4% is allowed and shall be calculated as follows:
I high - I avg
% Imbalance = X 100
I avg
( + + )
Where : I avg = I 1 I 2 I 3
3
6.3 Vibration Tests: Vibration data shall be acquired at each bearing location radial to
the shaft in the vertical and horizontal planes. In addition, readings shall be taken
axial to the shaft at both ends of the motor. The following guidelines and criteria
apply to all vibration readings:
6.3.1 Vibration Analyzer: The contractor shall use the type of instrumentation and
sensors specified. For example, for a 3,600 RPM machine an accelerometer
with a sensitivity of 100 mV/g and a resonant frequency of at least 15,000 Hz
is required.
A rare earth super magnet and a sound disc shall be used in conjunction with
any vibration data collector which has the following characteristics:
6.3.2 Vibration Data: The vendor shall provide the Government narrowband (400-
line) spectral vibration data for all motors as follows:
2X 0.02 0.5
This appendix provides NASA Maintenance Procedure Templates (called MPTs for short). The
MPTs have been developed to provide a sample source of time/cycle based maintenance actions,
test procedures and information. A section at the end of the MPT, identified as Engineers Notes,
provides technical information that may be useful when developing site-specific procedures.
The MPTs are based upon sample procedures provided by several NASA Centers, private
industry, and others. The objective of the MPT is to provide instructions without becoming
overly detailed. Simple steps, that provide little value for the typical work force, have not been
included. In some high-risk industry, like nuclear power, maintenance procedures are extremely
detailed and often do not allow even minor deviation when accomplishing. That is not the basis
for the NASA MPTs. The procedures were originally developed in a spreadsheet format and
were provided to the NASA Centers for use in developing site specific procedures.
The procedure layout is such that all actions are taken in sequence. A person performing the
procedure should arrive at the work site with all necessary tools and materials (including
reference material).
Procedure Number - The number is assigned for use in indexing the procedure. It is expected
that NASA Centers will change this number if the procedure is incorporated into the site-specific
CMMS.
System Description - This section is text that describes the machine/equipment application.
Procedure Description - Text that describes the procedure purpose. The body of the procedure
is often divided into sub-sections. Each sub-section has a heading and that heading is duplicated
in the Procedure Description. This ensures that the entire scope of work is well understood.
Related Tasks - Identifies other tasks that should be performed. Usually tasks with a shorter
periodicity. For example, an annual procedure will identify any semi-annual, quarterly, or
monthly procedures to ensure that all work is done during a single visit to the work site.
Periodicity - Describes how often the procedure is scheduled. NASA Centers will want to
modify the periodicity code to fit the site. Codes used in the MPTs are:
Multiples of the above are sometimes used and are identified by a number followed by a letter.
For example, 5A indicates that the procedure is scheduled every 5 years.
Labor (Hrs) - This information will usually be two numbers. First is number of people, second
is estimated time for each person. For example: 2-people/2 hrs each. The time estimate is to
perform the task. Because each site is different, no time was estimated to get to the job site.
Special Tools - Identifies tools and test equipment that the technician will need at the job site.
Common tools are not usually identified.
Materials - All materials that will be needed at the job site are listed in this section.
Reference Data - Identifies information, such as a test procedure, that the technician will need in
order to perform the task. This section does not identify reference data that may have been used
to develop the procedure. Only that reference data needed to perform the task is listed in this
section.
Warning Summary - A warning is identified in the procedure anytime there is the potential for
injury (including toxic release to the environment). This section lists every warning that is part
of the procedure. If a warning is used many times in the procedure, it is only listed once in this
section.
Note - Although not listed in a summary block, the procedure may also contain a Note. A note
provides relevant information to the person performing the procedure.
Preliminary - The first part of the procedure is identified as the preliminary section. This
section includes all steps taken before going to the job site, or if at the job site, before starting
work on the specified machine. Although there is not a maximum number of preliminary steps,
this section is usually less than 10 steps.
Procedure - The start of the procedure is clearly identified by the title “Procedure.” The first
step in the procedure is labeled “A” and is a phrase that identifies the work to be accomplished.
The next step is labeled “A1” and is an action item. Each subsequent action step is numbered in
ascending order, “A2, A3, ...” If the procedure can be broken into discrete sections, there maybe
a “B” , “C”, etc.
Inspection Data - If data is to be collected, there will usually be an Inspection Data section. The
procedure will identify the data and direct where it is to recorded in the Inspection Data section
or other location. The Inspection Data section is always located at the end of the Procedure
section.
A section at the end of the MPT is identified as Engineers Notes. The Engineers Notes provides
background information that may be useful when developing site-specific procedures. It is not
part of the procedure in that it is not intended to be provided (printed out) for use in the field or
entered into the site CMMS. The Engineers Notes are a tool for use in developing site-specific
procedures.
Table J-2
Caution Summary Protect semi-conductor control devices from potential high voltage. -
Similar to warning summary. A caution is identified in the procedure
anytime there is the potential for damage to the equipment or damage to
collateral equipment.
Reserved This section was reserved for future use by the Centers.
Preliminary This section includes all steps taken before going to the job site, or if at
the job site, before starting work on the specified machine.
1 Charge batteries and backup batteries. - This section is usually less than
10 steps.
2 Ensure equipment/component identification (name and/or number) is
legible and securely affixed to equipment. Repair as required.
Procedure The start of the procedure is clearly identified by the title “Procedure.”
A Test Insulation - The first step in the procedure is labeled “A” and is a
phrase that identifies the work to be accomplished.
A1 De-energize equipment and tag out in accordance with site safety
practices. - The next step is labeled “A1” and is an action item.
A2 Open motor control panels or doors to gain access to circuit to be tested.
- Each subsequent action step is numbered in ascending order, “A2, A3,
...”
A3 Perform next step. - Each step begins with an action verb such as Open,
Inspect, Test, Perform, etc. This keeps the procedure focused.
WARNING Test to ensure all circuits are de-energized. - A warning, if needed,
comes just before the step where potential for injury exists.
A4 Place thermometer in close ...
CAUTION Protect semi-conductor control devices from potential high voltage. - A
caution, if needed, comes just before the step where potential for
equipment damage exists.
A5 Attach ground cable (black cable) from tester to ground.
Note 1 A note can be inserted anywhere in the procedure. If there is more than
one Note, they are numbered. The note is information or direction for
the technician in the field.
Note 2 The note is not an action step. The note is used to clarify an action step
or to offer a decision. Avoid using the note to state why the action is
being taken.
A6 Test to ensure a ground established. - Keep the step as short and clear as
possible. Modifiers (such as "the") are not needed. Simple directions,
that provide little value for the typical work force, need not be included.
Note 3 In some high-risk industry, like nuclear power, maintenance procedures
are extremely detailed and often do not allow even minor deviation
when accomplishing. That is not the basis for the typical industry
procedure.
A7 Attach test cable (usually red cable) to circuit to be tested.
A8 Energize tester.
A9 Record test results at one minute intervals for 10 minutes. - Anytime
data is needed, the procedure states "Record...". A section for Inspection
A9 De-energize tester.
WARNING Circuit may have dangerous voltage potential following testing.
A10 Discharge circuit.
B Next Procedure - New procedure sub-section. This heading is
duplicated in the Procedure Description.
B1 Remove test cables.
B2 Remove thermometer, record temperature.
B3 Close access doors and panels.
B4 Return motor to service.
B5 Repeat steps A1 through A10 for next motor. - Repeat steps or reference
to other procedures can be used. Figures can also be used.
Note 4 The procedure layout is such that all actions are taken in sequence. A
person performing the procedure should arrive at the work site with all
necessary tools and materials (including reference material).
Engineer's Notes The Engineers Notes provides background information that may be
useful when developing site-specific procedures.
This section is not part of the procedure. It is not intended to be
provided (printed out) for use in the field or entered into the site CMMS.
Inspection Data
Engineer's Notes
EN1 For time estimating purposes, allow one minute per data point.
Approximately 10 to 12 minutes for a typical 4 bearing machine.
Triaxial accelerometers will require less time to collect data.
EN2 Periodicity can be adjusted after a baseline is established.
Engineer's Notes
EN1 Detailed information regarding safety guidelines is contained in OSHA
Regulations Part 1910.
EN1a See standard 1910.333 for electrical safety including closest approach
distances for energized circuits.
Inspection Data
ID-1 Insulation Resistance at 1 min (Megohm)
ID-2 Insulation Resistance at 2 min (Megohm)
ID-3 Insulation Resistance at 3 min (Megohm)
ID-4 Insulation Resistance at 4 min (Megohm)
ID-5 Insulation Resistance at 5 min (Megohm)
ID-6 Insulation Resistance at 6 min (Megohm)
ID-7 Insulation Resistance at 7 min (Megohm)
ID-8 Insulation Resistance at 8 min (Megohm)
ID-9 Insulation Resistance at 9 min (Megohm)
ID-10 Insulation Resistance at 10 min (Megohm)
ID-11 Temperature (degree C or F)
Engineer's Notes
EN1 Specify the Insulation Resistance test voltage as follows:
EN1a Circuit 480V or less, test voltage 500V
EN1b Circuit 600V, test voltage 1000V
EN1c Circuit 2400V, test voltage 2500V
EN1d Circuit 4160V and above, test voltage 5000v
EN2 Technical standards are updated by the sponsoring organization (such as
ASTM and IEEE). Often the update year is part of the standard number.
Check with the sponsoring organization for the current version of the
standard.
EN2a See IEEE Standard 43-1974, IEEE Recommended Practice for Testing
Insulation Resistance of Rotating Machinery, for guidance on insulation
condition and interpretation of polarization index test results.
Inspection Data
ID-1 Ground Test (ohms)
ID-2 Primary to Ground Insulation Resistance at 1 min (Megohm)
ID-3 Primary to Ground Insulation Resistance at 2 min (Megohm)
ID-4 Primary to Ground Insulation Resistance at 3 min (Megohm)
ID-5 Primary to Ground Insulation Resistance at 4 min (Megohm)
ID-6 Primary to Ground Insulation Resistance at 5 min (Megohm)
ID-7 Primary to Ground Insulation Resistance at 6 min (Megohm)
ID-8 Primary to Ground Insulation Resistance at 7 min (Megohm)
ID-9 Primary to Ground Insulation Resistance at 8 min (Megohm)
ID-10 Primary to Ground Insulation Resistance at 9 min (Megohm)
ID-11 Primary to Ground Insulation Resistance at 10 min (Megohm)
ID-12 Secondary to Ground Insulation Resistance at 1 min (Megohm)
ID-13 Secondary to Ground Insulation Resistance at 2 min (Megohm)
ID-14 Secondary to Ground Insulation Resistance at 3 min (Megohm)
ID-15 Secondary to Ground Insulation Resistance at 4 min (Megohm)
Engineer's Notes
EN1 Technical standards are updated by the sponsoring organization (such as
ASTM and IEEE). Often the update year is part of the standard number.
Check with the sponsoring organization for the current standard.
EN1a ANSI/IEEE Standard C57.12.90-1993; IEEE Standard Test Code for
Liquid-Immersed Distribution, Power, and Regulating Transformers.
EN1b ANSI/IEEE Standard C57.12.91-1979 (updated 1995); IEEE Test Code
for Dry-Type Distribution and Power Transformers .
EN2 Specify the Insulation Resistance test voltage as follows:
EN2a Circuit 480V or less, test voltage 500V
EN2b Circuit 600V, test voltage 1000V
EN2c Circuit 2400V, test voltage 2500V
EN2d Circuit 4160V and above, test voltage 5000v
EN3 The Polarization Index (PI) is the 10 minute insulation resistance
reading divided by the 1 minute insulation resistance reading. This
value should be monitored and trended to help determine the condition
of the windings. Guidelines are from S.D.Myers.
EN3a For liquid filled transformers: PI greater than 2.0 is good, 1.25 to 2.0 is
fair, 1.1 to 1.25 is poor, and less than 1.1 is bad.
EN3b For dry transformers the PI will normally be between 1.0 and 1.25.
Insulation resistance value should be greater than 10,000 megohms.
EN4 Procedure is written for a step-down transformer and assumes the high
voltage side is the line side. For step-up transformer, reverse the test
procedure to test the load side first.
EN4a If the line side of the primary switch is also de-energized, you can
modify this procedure to test the line and load sides of the primary
switch. Prior to step A22 close the primary switch and then take
insulation data. Add Warning to test the circuit.
EN5 Time estimate is based upon transformer already de-energized. Add
additional 2 to 3 hours to de-energize and tag out.
Inspection Data
ID-1 Phase-A to Ground Insulation Resistance at 1 min (Megohm)
ID-2 Phase-B to Ground Insulation Resistance at 1 min (Megohm)
ID-3 Phase-C to Ground Insulation Resistance at 1 min (Megohm)
ID-4 Temperature (degree C or F)
Engineer's Notes
EN1 Specify the Insulation Resistance test voltage as follows:
EN1a Circuit 480V or less, test voltage 500V
EN1b Circuit 600V, test voltage 1000V
EN1c Circuit 2400V, test voltage 2500V
EN1d Circuit 4160V and above, test voltage 5000v
EN2 Technical standards are updated by the sponsoring organization (such as
ASTM and IEEE). Often the update year is part of the standard number.
Check with the sponsoring organization for the current version of the
standard.
EN2a ANSI/IEEE Standard C37.50-1989; American National Standard for
Switchgear-Low Voltage AC Power Circuit Breakers Used in
Enclosures - Test Procedures .
EN2b ANSI/IEEE Standard C37.09-1979; IEEE Standard Test Procedures for
AC High-Voltage Breakers Rated on a Symmetrical Current Basis.
A1 Collect dissolved gas oil sample from transformer. Use 50cc glass
syringe and follow procedure in ASTM standard D-3613-92.
A2 Collect two additional oil samples in sample bottles. Record equipment
number, date, and oil temperature on one bottle.
B Perform Field Oil Tests
B1 Use oil in un-labeled bottle for steps B2 through B5.
B2 Perform Dielectric Withstand Test (ASTM D-877-87).
B3 Perform Field Acidity Test (ASTM D-1534-90).
B4 Perform Visual Examination (ASTM D-1524-84).
Note See Power Factor Test Set operating instructions for Oil Power Factor
test procedure.
B5 Perform Oil Power Factor.
B6 Record test results in the Inspection Data Section, item ID-1 to ID-4.
B7 Deliver oil sample in labeled bottle to supervisor or PT&I for analysis.
Inspection Data
ID-1 Dielectric Withstand Test (kV)
ID-2 Field Acidity Test (mg KOH/ml)
ID-3 Visual Examination (color scale)
ID-4 Oil Power Factor (percent)
Engineer's Notes
EN1 Technical standards are updated by the sponsoring organization (such as
ASTM and IEEE). Often the update year is part of the standard number.
Check with the sponsoring organization for the current version of the
standard.
EN1a ANSI/IEEE Standard C57.12.90-1993; IEEE Standard Test Code for
Liquid-Immersed Distribution, Power, and Regulating Transformers.
EN2 Send oil sample in the labeled bottle to test lab for a Karl Fischer
(ASTM D-1533-88), Acid Number (ASTM D-974-87), and Interfacial
Tension (ASTM D- 971-82) test.
EN3 Send 50cc syringe to test lab for gas-in-oil analysis (ASTM D-3613-92)
EN4 Field oil test results shall be as follows:
EN4a Dielectric Test: >30kV
EN4b Acidity Test: <.05 mg KOH/ml
EN4c Visual Examination: <4.0
EN4d Power Factor: <2.0%
EN5 Generate work order if tests fall outside minimum parameters
A5 Tie (short circuit) the primary bushings together using copper wire or
braid.
A6 Tie (short circuit) the secondary bushings, including neutral, together
using copper wire or braid.
Note 2 If transformer has on-load tap changer, mark the as found position. Test
can not be performed with the on-load tap changer in the neutral
position. Leave no-load tap changer, if installed, in normal operating
position.
A7 Move on-load tap changer (if installed) to minus 1 from neutral position.
A8 Connect test set high voltage lead to primary bushing.
A9 Connect test set return lead to secondary bushing.
A10 Connect test ground to transformer ground.
Note 2 For each test performed, record results in Inspection Data section.
WARNING Energized electrical circuits. Observe test device safety precautions.
A11 Perform primary-to-secondary test with ground circuit guarded.
A12 Perform primary-to-secondary test with secondary circuit guarded.
A13 Perform primary-to-secondary test with secondary and ground circuit
included.
WARNING Circuit may have dangerous voltage potential following testing.
A14 Discharge circuit.
A15 Connect test set high voltage lead to secondary bushing.
A16 Connect test set return lead to primary bushing.
WARNING Energized electrical circuits. Observe test device safety precautions.
A17 Perform secondary-to-primary test with ground circuit guarded.
A18 Perform secondary-to-primary test with ground circuit included.
WARNING Circuit may have dangerous voltage potential following testing.
A19 Discharge circuit.
A20 Remove shorting cables from primary and secondary bushings.
A21 Move on-load tap changer (if installed) to neutral.
Note 3 If transformer has no-load tap changer, leave in normal operating
position.
A22 Connect test set high voltage lead to primary bushing 1 (usually
identified as H1).
A23 Connect test set return lead to primary bushing 2 (usually identified as
H2).
WARNING Energized electrical circuits. Observe test device safety precautions.
A24 Perform excitation test H1 to H2.
WARNING Circuit may have dangerous voltage potential following testing.
A25 Discharge circuit.
A26 Connect test set high voltage lead to primary bushing 2 (usually
identified as H2).
A27 Connect test set return lead to primary bushing 3 (usually identified as
H3).
WARNING Energized electrical circuits. Observe test device safety precautions.
A28 Perform excitation test H2 to H3.
Engineer's Notes
EN1 Specify the Power Factor test voltage as follows:
Engineer's Notes
EN1 Specify the Power Factor test voltage as follows:
EN1a Circuit less than 2400V, test voltage 500V
EN1b Circuit 2400V to 4160V, test voltage 2500V
EN1c Circuit 4160V to 10,000V, test voltage 5000V
EN1d Circuit 10,000V and above, test voltage 10,000V
EN2 A Power Factor test measures the watts loss and the phase angle
between the current and voltage in the equipment under test. From this
information a determination can be made as to the integrity of the
insulation.
EN2a The Power Factor test is NOT a go-no/go test. Comparisons of past
readings are necessary to determine the insulation condition
Table J-11: Sample Procedure PT&I-0009, Oil Filled Bushing Power Factor Test
Engineer's Notes
EN1 Specify the Power Factor test voltage as follows:
EN1a Circuit less than 2400V, test voltage 500V
EN1b Circuit 2400V to 4160V, test voltage 2500V
EN1c Circuit 4160V to 10,000V, test voltage 5000V
EN1d Circuit 10,000V and above, test voltage 10,000V
EN2 A Power Factor test measures the watts loss and the phase angle
between the current and voltage in the equipment under test. From this
information a determination can be made as to the integrity of the
insulation.
EN2a The Power Factor test is NOT a go-no/go test. Comparisons of past
readings are necessary to determine the insulation condition
EN2b All test values must be temperature corrected to 20C.
EN2c Individual bushings should be less than 5% after cleaning. Large 115kV
and 230kV oil filled bushings will have the Power Factor baselines
etched on the bushing base.
EN3 Time estimate is based upon testing only. Allow an additional hour
(each person) to clean bushings.
Engineer's Notes
EN1 In order make effective use of time, this procedure for cleaning and
inspecting a transformer should be used in conjunction with other
procedures (identified in Related Task section) for testing transformers.
EN2 Technical standards are updated by the sponsoring organization (such as
ASTM and IEEE). Often the update year is part of the standard number.
Check with the sponsoring organization for the current standard.
EN2a ANSI/IEEE Standard C57.12.90-1993; IEEE Standard Test Code for
Liquid-Immersed Distribution, Power, and Regulating Transformers.
EN2b ANSI/IEEE Standard C57.12.91-1979 (updated 1995); IEEE Test Code
for Dry-Type Distribution and Power Transformers .
Engineer's Notes
EN1 Technical standards are updated by the sponsoring organization (such as
ASTM and IEEE). Often the update year is part of the standard number.
Check with the sponsoring organization for the current standard.
EN1a IEEE Standard 446-1995, "IEEE Recommended Practice for Emergency
and Standby Power Systems for Industrial and Commercial
Applications", IEEE Orange Book.
EN2 Battery impedance tests.
EN2a Battery cell impedance shall be within 10% of each other and within
10% from last test.
EN2b Battery strap impedance shall be less than 0.1 ohm. Readings above 0.1
ohm require cleaning and retorque.
EN-3 Battery voltage and trickle charge in standby to be within 5% of
manufacturer's specifications.
Engineer's Notes
EN1 Technical standards are updated by the sponsoring organization (such as
ASTM and IEEE). Often the update year is part of the standard number.
Check with the sponsoring organization for the current standard.
EN1a IEEE Standard 446-1995, "IEEE Recommended Practice for Emergency
and Standby Power Systems for Industrial and Commercial
Applications", IEEE Orange Book.
EN2 UPS should engage at less than 90% system voltage, + or - 2.5%.
EN3 Operational Parameters (for yearly reference)
EN-3a Voltage shall be within -5% to +5%
EN-3b Frequency shall be within -0.5% to +0.5%
EN-3c Output current shall be within -5% to +5% of rated current
EN-4 Battery voltage and trickle charge in standby to be within 5% of
manufacturer's specifications.
Engineer's Notes
EN1 Connector torque value, see specification SAE AIR1471. All values are
+ or - 12.5%.
EN1a 5/32-32: 25 in-lb.
EN1b 5/32-36: 26 in-lb.
EN1c 3/16-32: 42 in-lb.
EN1d 1/4-28: 95 in-lb.
EN1e 5/16-24: 185 in-lb.
EN1f 1/2-20: 800 in-lb.
Engineer's Notes
EN1 Technical standards are updated by the sponsoring organization (such as
ASTM and IEEE). Often the update year is part of the standard number.
Check with the sponsoring organization for the current version of the
standard.
EN1a IEEE C37.11-1997 IEEE Standard Requirements for Electrical Control
for AC High-Voltage Circuit Breakers Rated on a Symmetrical Current
Basis
EN1b ANSI/IEEE C37.09-1979, Standard Test Procedure for AC High-
Voltage Circuit Breakers Rated on a Symmetrical Current Basis.
EN2 Breaker timing test results should verify the integrity of the operating
mechanism. Compare current test with last test to confirm velocity,
travel, time, and contact wipe. Deviations from the manufacturers specs
indicate adjustment is required.
EN2a Contact resistance measurements normally range from 50 microhms to
1200 microhms. Consult manufacturers specifications for specific
values. Contact resistance of each phase should be within 10% of the
other phases.
EN2b Deviations indicate burnt or misaligned contacts, or misadjusted
operating mechanism.
EN3 A Vacuum Bottle Integrity Test and/or a DC High-Pot at 2.5 the rated
AC voltage level are go/no-go tests that verify the bottle is still in a
vacuum condition.
EN4 Oil tests for Oil Circuit Breakers can reveal the operating history and
condition of the contact assemblies. High acidity and low dielectric are
indicative of burning or arcing contacts, and/or high numbers of full load
operations
EN4a Levels outside the values identified in the procedure, Note 5, require the
oil to be filtered and the contact assemblies to be inspected.
EN5 Connector torque value, see specification SAE AIR1471. All values are
+ or - 12.5%.
EN5a 5/32-32: 25 in-lb.
EN5b 5/32-36: 26 in-lb.
EN5c 3/16-32: 42 in-lb.
A11 Inspect gages, thermometers, and indicators for proper calibration. Note
any overdue items on work order.
A12 Make minor repair. Contact supervisor if repairs are not possible. Note
on work order.
A13 Perform touchup painting as required.
A14 Perform related tasks, if any.
A15 Replace pulley and belt guards.
A16 Close access covers and doors and return air handler to service.
A17 Remove debris from work-site.
Engineer's Notes
EN1 Biological control tablets are used to control fungus and bacterial growth
in the condensate pan. Contact environmental control for the proper
agents/tablets.
EN2 PT&I group needs to know if belts are changed or aligned.
Engineer's Notes
EN1 See manufacturers have specification for limit regarding maximum
number of plugged tubes.
EN2 Notify PT&I group following this procedure to schedule condition
monitoring retest.
The following table includes reference numbers, titles, and general RCM application descriptions
for clauses where RCM principles have been integrated into the SPECSINTACT. They can be
used as a ready reference to access SPECSINTACT for more detail