Oracle® MRP: User's Guide Release 12.1
Oracle® MRP: User's Guide Release 12.1
Oracle® MRP: User's Guide Release 12.1
User's Guide
Release 12.1
Part No. E15188-05
July 2013
Contents
Setting Up
Overview of Setting Up............................................................................................................. 1-1
Related Product Setup Steps..................................................................................................... 1-1
Setup Checklist.......................................................................................................................... 1-4
Setup Steps................................................................................................................................ 1-6
Supply Chain Planning Setup Steps...................................................................................... 1-12
Defining Planning Parameters................................................................................................ 1-13
Starting the Planning Manager............................................................................................... 1-16
Defining Planners................................................................................................................... 1-17
Creating Planning Exception Sets........................................................................................... 1-17
Creating Demand Classes....................................................................................................... 1-19
Creating Source Lists............................................................................................................... 1-21
Setting Up Planner Workbench.............................................................................................. 1-22
Setting Up Line Scheduling Workbench................................................................................ 1-24
Changing Your Organization.................................................................................................. 1-25
Profile Options........................................................................................................................ 1-25
Forecasting
Overview of Forecasting ...........................................................................................................2-1
Generating Forecasts from Historical Information.................................................................. 2-4
Defining Forecast Sets............................................................................................................... 2-6
Defining Forecasts..................................................................................................................... 2-7
iii
Master Scheduling
Overview of Master Scheduling............................................................................................... 3-1
Master Demand Schedule......................................................................................................... 3-2
Master Production Schedule (MPS) ......................................................................................... 3-2
Main Features of Master Scheduling ....................................................................................... 3-3
Defining a Schedule Name ...................................................................................................... 3-6
Defining Schedule Entries Manually ...................................................................................... 3-7
Loading a Master Schedule from an Internal Source............................................................... 3-9
Interorg Planned Orders .........................................................................................................3-10
Specific MDS or Specific MPS ...............................................................................................3-11
Selecting Master Schedule Load Options .............................................................................. 3-12
Additional Factors Affecting a Master Schedule Load ..........................................................3-14
How Forecasted Discrete Items Appear in the Master Schedule........................................... 3-15
How Forecasted Repetitive Items Appear in the Master Schedule........................................3-17
Planning Spares Demand ....................................................................................................... 3-19
Schedule Relief........................................................................................................................ 3-20
Viewing Master Schedule Relief Information ...................................................................... 3-21
Profile Options for Master Schedule Relief .......................................................................... 3-22
Planning Manager and Schedule Relief ................................................................................ 3-22
Tracking Demand Schedule Reliefs ...................................................................................... 3-23
Rough Cut Capacity Planning................................................................................................. 3-24
iv
Planner Workbench
Overview of Planner Workbench............................................................................................. 6-1
Quick Access to Particular Documents .................................................................................... 6-2
Reviewing Planning Information ............................................................................................ 6-2
Reviewing Item Planning Information .................................................................................... 6-4
vi
vii
Demand Classes
Overview of Demand Classes................................................................................................... 7-1
Demand Class Forecasting ....................................................................................................... 7-2
Forecast Consumption .............................................................................................................. 7-3
Demand Class Master Scheduling ........................................................................................... 7-5
Demand Class ATP Calculation ............................................................................................... 7-6
Net Inventory by Demand Class .............................................................................................. 7-6
10
Repetitive Planning
Overview of Repetitive Planning .......................................................................................... 10-1
Overview of Repetitive Planning Concepts .......................................................................... 10-2
MPS and MRP Planning for Repetitive Assemblies ............................................................. 10-6
Safety Stock and Order Modifiers ......................................................................................... 10-7
Anchor Date ............................................................................................................................ 10-9
Repetitive Schedule Allocation .............................................................................................. 10-9
Firm Repetitive Schedules ................................................................................................... 10-10
Repetitive Planning Control ................................................................................................ 10-12
viii
11
Reports
Overview of Reports............................................................................................................... 11-1
Audit Information Report....................................................................................................... 11-1
Current Projected On Hand vs. Projected Available Graphical Report for Supply Chain
Planning................................................................................................................................... 11-7
Demand vs. Replenishment Graphical Report for Supply Chain Planning....................... 11-10
Financial Analysis Report for Supply Chain Planning........................................................11-13
Forecast Comparison Report ................................................................................................ 11-14
Forecast Detail Report........................................................................................................... 11-18
Late Order Report for Supply Chain Planning.....................................................................11-21
Master Schedule Comparison Report................................................................................... 11-23
Master Schedule Detail Report............................................................................................. 11-26
Master Schedule Status Report for Supply Chain Planning................................................11-30
Planning Manager Worker once-a-day tasks........................................................................ 11-32
Planning Parameters Report................................................................................................. 11-33
CRP Reports........................................................................................................................... 11-33
Order Reschedule Report for Supply Chain Planning.........................................................11-33
Planned Order Report for Supply Chain Planning.............................................................. 11-36
Planning Detail Report for Supply Chain Planning............................................................ 11-39
Planning Exception Sets Report ........................................................................................... 11-43
12
Kanban Planning
Overview of Kanban Planning .............................................................................................. 12-1
Using the Kanban Calculation Program ................................................................................ 12-5
Viewing and Updating Kanban Calculations.........................................................................12-8
Kanban Tools Menu.............................................................................................................. 12-10
13
Project MRP
Overview of Project MRP ....................................................................................................... 13-1
Establishing a Project MRP Environment ............................................................................. 13-2
Overview of Project MRP Setup Tasks...................................................................................13-2
Setting Up Project MRP in Oracle Projects.............................................................................13-3
Setting Up Project MRP in Oracle Inventory......................................................................... 13-3
Setting Up Project MRP in MRP ............................................................................................ 13-5
Reviewing or Adding Project MRP Plan Options Prerequisite ............................................ 13-6
Launching a Project MRP Plan................................................................................................13-7
Setting Up Project MRP in Oracle Project Manufacturing ....................................................13-7
ix
14
Parallel Processing
Overview of Parallel Processing............................................................................................. 14-1
Process Control........................................................................................................................ 14-1
Inter-process Communication................................................................................................. 14-2
Single Processor Machine....................................................................................................... 14-2
Snapshot.................................................................................................................................. 14-4
Snapshot Parallel Processing.................................................................................................. 14-8
Planner Parallel Processing..................................................................................................... 14-8
Planning Manager................................................................................................................... 14-9
Tools Menu
Tools Menu............................................................................................................................... A-1
Alerts
Alerts ........................................................................................................................................ C-1
Glossary
Index
xi
Send Us Your Comments
Oracle MRP User's Guide, Release 12.1
Part No. E15188-05
Oracle welcomes customers' comments and suggestions on the quality and usefulness of this document.
Your feedback is important, and helps us to best meet your needs as a user of our products. For example:
If you find any errors or have any other suggestions for improvement, then please tell us your name, the
name of the company who has licensed our products, the title and part number of the documentation and
the chapter, section, and page number (if available).
Note: Before sending us your comments, you might like to check that you have the latest version of the
document and if any concerns are already addressed. To do this, access the new Oracle E-Business Suite
Release Online Documentation CD available on My Oracle Support and www.oracle.com. It contains the
most current Documentation Library plus all documents revised or released recently.
Send your comments to us using the electronic mail address: appsdoc_us@oracle.com
Please give your name, address, electronic mail address, and telephone number (optional).
If you need assistance with Oracle software, then please contact your support representative or Oracle
Support Services.
If you require training or instruction in using Oracle software, then please contact your Oracle local office
and inquire about our Oracle University offerings. A list of Oracle offices is available on our Web site at
www.oracle.com.
xiii
Preface
Intended Audience
Welcome to Release 12.1 of the Oracle MRP User's Guide.
Casual User and Implementer
See Related Information Sources on page xvi for more Oracle E-Business Suite product
information.
Documentation Accessibility
For information about Oracle's commitment to accessibility, visit the Oracle
Accessibility Program website at
http://www.oracle.com/pls/topic/lookup?ctx=acc&id=docacc.
Structure
1 Setting Up
2 Forecasting
3 Master Scheduling
4 Material Requirements Planning
5 Supply Chain Planning
6 Planner Workbench
7 Demand Classes
8 Time Fence Control
9 Two-Level Master Scheduling
10 Repetitive Planning
xv
11 Reports
12 Kanban Planning
13 Project MRP
14 Parallel Processing
A Tools Menu
B Windows and Navigator Paths
C Alerts
D Customized Find Windows
E Workflow - Planning Exception Messages
F Forecasting - Statistical and Focus
G Memory-based Planning Engine
H Character Mode Forms and GUI Windows
Glossary
Online Documentation
All Oracle E-Business Suite documentation is available online (HTML or PDF).
xvi
Online Help - Online help patches (HTML) are available on My Oracle Support.
PDF Documentation - See the Oracle E-Business Suite Documentation Library for
current PDF documentation for your product with each release. The Oracle
E-Business Suite Documentation Library is also available on My Oracle Support and
is updated frequently.
Release Notes - For information about changes in this release, including new
features, known issues, and other details, see the release notes for the relevant
product, available on My Oracle Support.
database tables, forms, reports, and programs for each Oracle E-Business Suite
product. This information helps you convert data from your existing applications
and integrate Oracle E-Business Suite data with non-Oracle applications, and write
custom reports for Oracle E-Business Suite products. The Oracle eTRM is available
on My Oracle Support.
Related Guides
User Guides Related to All Products
xvii
xviii
1
Setting Up
Overview of Setting Up
This section contains an overview of each task you need to complete to set up Oracle
MRP.
Before you set up , you should:
Set up your Oracle Applications Set of Books. See: Defining Sets of Books, Oracle
General Ledger User's Guide.
Also, if your product uses Oracle Workflow to, for example, manage the approval of
business documents or to derive Accounting Flexfield values via the Account
Generator, you need to set up Oracle Workflow.
See also Oracle E-Business Suite Setup Guide, Oracle E-Business Suite Maintenance Guide,
Setting Up 1-1
Oracle E-Business Suite Concepts, Oracle E-Business Suite Security Guide, and Oracle
Workflow Guide
Oracle Inventory
Make sure you set up Inventory as described in Overview of Setting Up, Oracle
Inventory User's Guide. Ensure that all the following steps have been completed:
If you manufacture your assemblies repetitively ensure that you define your
repetitive planning information.
Oracle Purchasing
Make sure you set up Purchasing as described in Overview of Setting Up, Oracle
Purchasing User's Guide. Ensure that all the following steps have been completed:
Define locations
Set up personnel
Define buyers
Define resources
Define production lines and line rates for flow schedules if you have a Flow
Manufacturing environment
Oracle Capacity
Make sure you set up Capacity as described in Overview of Setting Up, Oracle Capacity
User's Guide. Ensure that all the following optional steps have been completed:
Perform setup steps in Oracle Projects. See: Setting Up Project MRP in Oracle
Projects.
Perform setup steps in Oracle Project Manufacturing. See: Setting Up Project MRP
in Oracle Project Manufacturing
Oracle Workflow
You can use the Enabled Exception Messages workflow to generate and distribute
messages to those who are the contacts for specific job tasks in order to resolve
problems. See: Setting Up Oracle Workflow, Oracle Workflow Guide.
Setting Up 1-3
Setup Checklist
Complete the following steps, in the order shown, to set up Oracle MRP:
Setup Checklist
Step
Required
Title
Required
Required
Required
Required
Set Up Organizations
Optional
Optional
Optional
Required
Optional
10
Optional
11
Optional
12
Optional
13
Required
14
Optional
Set Up Capacity
15
Step
Required
Title
16
Optional
17
Optional
18
Optional
19
Optional
Load MDS
20
Optional
21
Optional
22
Optional
23
Optional
24
Optional
25
Optional
26
Optional
27
Optional
28
Optional
29
Optional
Define your
Inter-organization Shipping
Network
30
Optional
31
Optional
32
Optional
33
Optional
Setting Up 1-5
Step
Required
Title
34
Required
35
Optional - Highly
Recommended
Setup Steps
Step 1 Set Up System Administrator (Required)
This step involves the following tasks:
Set up printers (optional). See: Setting Up Your Printers, Oracle E-Business Suite
Setup Guide.
Grade flexfield
Job flexfield
Position flexfield
Set up the following Inventory key flexfields. You may not need to set up these key
flexfields if you have already installed and set up Oracle Inventory or performed a
common-applications setup. See also: Oracle Inventory User's Guide.
System Items flexfield. After you set up the System Items flexfields and compile
them, the item flexfield view concurrent program is submitted automatically.
orders, you must still compile the respective flexfields because all
Oracle Inventory transactions (such as the Define Items window),
inquiries, and reports require a frozen flexfield definition. However,
you do not need to configure the flexfield in a specific way.
Set up calendars:
Setting Up 1-7
Define period types. See: Defining Period Types, Oracle General Ledger User's Guide.
Define accounting calendar. See: Defining Calendars, Oracle General Ledger User's
Guide.
Define currencies. See: Defining Currencies, Oracle General Ledger User's Guide.
Define conversion rate types. See: Defining Conversion Rate Types, Oracle General
Ledger User's Guide.
Assign your set of books to a responsibility. See: Oracle General Ledger User's Guide.
Set up accounting code combinations. See: Oracle General Ledger User's Guide.
Open and close accounting periods. See: Opening and Closing Accounting Periods,
Oracle General Ledger User's Guide.
Define business groups, if you want to define new business groups rather than
using the default Setup Business Group. See the section View-all Responsibility in:
Setting Up Security for Applications Using Some HRMS Windows, Oracle Human
Resources User's Guide.
Define organizations
Assign business groups and operating units to responsibilities. Make sure that the
profile option HR: Business Group is set at the responsibility level to the business
group you want to use for that responsibility. See: Oracle Human Resources User's
Guide
This is a necessary setup if you plan on importing purchase requisitions from the
Planner Workbench into Oracle Purchasing.
Step 8 Define your MRP Planning Parameters (Required)
You need to define different modes of operation and default values that affect other
functions in Oracle MRP. If you manufacture your assemblies repetitively, you can also
set up your repetitive item defaults. See: Defining Planning Parameters.
Setting Up 1-9
Setting Up 1-11
2.
Check Snapshot Lock Tables to lock tables during the snapshot process to ensure
consistent inventory on-hand quantities and order quantities.
3.
Enter a Default ABC Assignment Group to use as the default for items. See: ABC
Assignment Groups, Oracle Inventory User's Guide.
4.
In the Execution Defaults section, check Demand Time Fence Control to consider
any demand from forecasts within the demand time fence. The planning process
does not consider any demand from forecasts within the demand time fence, but
does consider demand from sales orders.
5.
Check Plan Safety Stock to calculate the safety stock for each item. Attention: You
must enter safety stock information for your items before Oracle MRP calculates
safety stock for the items. See: Defining Items, Oracle Inventory User's Guide.
6.
Setting Up 1-13
7.
Check Planning Time Fence Control to indicate whether the planning process
violates planning time fences for items. If you do not check this, the planning
process plans the items as if no planning time fences exist.
For discrete items or flow schedules, the planning process does not create
planned orders or recommend rescheduling in existing orders within the
planning time fence of the item. The planning process can still recommend
rescheduling orders out..
For repetitive items, the planning process can vary the suggested schedule from
the optimal schedule, within the planning time fence, by the acceptable rate
increase and/or decrease you specified for the item. Discretely planned items
include flow schedules
8.
Check Net WIP to consider standard discrete jobs, nonstandard discrete jobs, or
repetitive schedules when planning an item. If you do not check this, the planning
process does not recommend rescheduling of work orders, and may over plan the
item because it creates additional planned orders.
9.
Order start date: Schedule material to arrive in inventory for availability on the
work in process order start date.
11. Select the planned items or components to be included in the planning process. See:
Specifying Items for the Planning Process. Supply Chain Planning users can set
additional parameters in the Plan Options window. See: Specifying Items for the
Supply Chain Planning Process.
12. Enter a number of days before the current date to include past due MDS demand in
Include MDS Days. If you do not enter a value, the planning process considers all
past due MDS demand. If you enter zero, the planning process ignores all past due
MDS demand.
2.
Work dates: Calculate the repetitive planning periods using workdays. This
allows the periods to shift out due to holidays. If a start date falls on a holiday,
the start date is changed to the next valid working day. Each repetitive
planning period consists only of valid working days.
Calendar dates: Calculate the repetitive planning periods using calendar days.
This allows you to fix the length of the periods regardless of the timing of
holidays (non-workdays). A repetitive planning period can start on a holiday
and include holidays.
3.
Enter an Anchor Date from which to calculate the repetitive planning periods. If,
during the planning process, you change the repetitive planning anchor date, this
date is updated to the start date of the first repetitive planning period.
4.
Enter the number of workdays for the first repetitive bucket in First Bucket Days.
For example, you might enter 5 to signify that the first repetitive planning horizon
is grouped into buckets of 5 days.
5.
Enter the number of workdays for the first repetitive horizon in First Horizon. For
example, you might enter 30 to signify the first 30 days of production are grouped
into the first repetitive bucket size you specify.
6.
Enter the number of workdays for the second repetitive bucket in Second Bucket
Days. For example, you might enter 10 to signify that the second repetitive planning
horizon is grouped into buckets of 10 days.
7.
Enter the number of workdays for the second repetitive horizon in Second Horizon.
For example, you might enter 60 to signify the next 60 days of production are
grouped into the second repetitive bucket size you specify.
8.
Enter the number of workdays for the third repetitive bucket in Third Bucket Days.
For example, you might enter 40 to signify that the rest of the repetitive planning
horizon production is grouped into buckets of 40 days.
Setting Up 1-15
9.
Note: When it operates, the Planning Manager may run for a very short
2.
3.
Choose Start to start the Planning Manager for all organizations by issuing a
request to the concurrent manager. The Planning Manager executes tasks
periodically, based on the Processing Interval you entered.
4.
Review the date and time you sent the request to the concurrent manager to start
the Planning Manager. If an error occurs during the Planning Manager maintenance
tasks, the date and time of the error is displayed.
5.
Started: The Planning Manager is started. The processing interval and request
identifier sent to the concurrent manager to start the Planning Manager are
displayed.
Defining Planners
You can define and update material planners or planning entities for the current
organization and assign them to inventory items at the organization level. See:
Updating Organization Items, Oracle Inventory User's Guide and General Planning
Attribute Group, Oracle Inventory User's Guide.
To define and update material planners or planning entities
1.
2.
3.
4.
Optionally, enter a date on which the planner becomes inactive. From this date on,
you cannot assign this planner to an inventory item.
5.
Setting Up 1-17
Navigate to the Planning Exception Sets window. You will use this window to set
the conditions under which you want to see an exception message.
2.
Select a planning exception set name to identify items, orders, and resources that
require attention based upon a set of predefined action messages.
3.
2.
3.
4.
5.
Enter a user-defined time fence (in days) to use when you specify User-defined time
fence in the Exception Time Periods portion of the Planning Exception Sets
window.
6.
2.
Enter exception time period types for monitoring different types of exceptions
within a time period.
An exception will occur only if the type of exception occurs during the specified
time period. The different types of exceptions for which you must specify a time
period type are:
Shortage Exceptions: occur when the projected on-hand quantity of the item is
negative or below safety stock.
Excess Exceptions: occur when the projected on-hand quantity of the item exceeds
zero or safety stock by more than the value you entered in Excess Quantity.
Resource Shortage Exceptions: occur when capacity is overloaded by a percentage
greater than the value entered in the Resource Overloaded field in the Sensitivity
Controls portion of the Planning Exception Sets window. For example, an exception
will occur if you entered 10% in Resource Over-utilized and capacity is overloaded
by 15%.
Resource Excess Exceptions: occur when the capacity is underloaded by a percentage
greater than the value entered in the Resource Underloaded field in the Sensitivity
Setting Up 1-19
2.
Verify that the type of lookup you are creating is for a demand class.
3.
Review the Access Level to determine whether you can add new lookups or modify
existing lookups of this type:
4.
Extensible: New codes may be added, but you can only modify or disable
seeded codes if the application of your responsibility is the same as the
application of this lookup.
Enter a unique alphanumeric code that describes a demand class. You can define a
maximum of 250 lookups for a single lookup type.
Note: You cannot change the values in this field after committing
5.
6.
Enter an extended description of the demand class. You can display the description
along with the meaning to give more information about your lookup.
7.
Enter an effective date (in the From field) on which the demand class becomes
active.
Note: You cannot use the demand class before this date. If you do
8.
Enter a disable date (in the To field) on which this demand class expires.
Note: You cannot use the demand class after this date. Once a
9.
Check Enabled to indicate whether the demand class is enabled. If you do not check
this, you cannot insert additional records using your demand class, but can query
records that already use this demand class.
2.
3.
See the following table for type, source type, and button values for a source list:
4.
Button Name
Copy/Merge
Forecast
Load/Copy/Merge
Forecast Entries
Copy/Merge
Forecast
Load/Copy/Merge
MDS
Forecast Entries
MDS Entries MPS
Entries MPS Planned
Order Demand MRP
Planned Order
Demand DRP
Planned Order
Demand
Load/Copy/Merge
MDS
Load MPS
Copy/Merge MPS
Forecast Entries
MDS Entries MPS
Entries MPS Planned
Order Demand MRP
Planned Order
Demand DRP
Planned Order
Demand
Load/Copy/Merge
MPS
Setting Up 1-21
5.
Select the source forecast, forecast set, master demand schedule, or master
production schedule name(s) to create your list.
6.
7.
Copying/Merging Forecasts
planning data, and supply/demand detail are displayed for each item.
To define your display preferences
1.
2.
3.
Enter Display Bucket Type, Display Factor, Decimal Places, Field Width,
Independent Demand Type, and, optionally, Source List to define the way data is
displayed in the Horizontal Material Plan window.
4.
Check each type of plan information you want displayed in your horizontal plan.
Note: See the Oracle MRPg Glossary for descriptions of plan
information settings.
5.
6.
Check each type of plan information you want displayed in your horizontal
capacity plan.
Note: See the Oracle MRP Glossary for descriptions of plan
information settings.
7.
8.
In the Supply/Demand tabbed region, enter a Cutoff Date, and Default Job Status.
When the Planner Workbench creates discrete jobs from implemented planned
orders, it assigns the job status you enter in the Preferences window.
9.
Select a Default Job Class. When the Planner Workbench creates discrete jobs from
implemented planned orders, it assigns the job class you enter in the Preferences
window.
Note: Default Job Status and Job Class are used as defaults in the
10. Select a Requisition Load By default. When the Planner Workbench creates
Setting Up 1-23
supply/demand settings.
11. Choose Save to use and save your preference selections for current and subsequent
sessions.
12. Choose Apply to use your preference selections for the current session only.
13. Choose Reset to use your previously saved selections.
See Also
Overview of Job and Repetitive Schedule Statuses, Oracle Work in Process User's
Guide
Tools menu
Define resources for a flow manufacturing line. See: Overview of Flow Manufacturing
Procedures, Oracle Bills of Material User's Guide
Define Flow Routings
Items need to be associated to lines through routings. See: Creating a Flow Routing,
Oracle Bills of Material User's Guide
Run an MRP, DRP, or MPS plan if you are scheduling planned orders
This process is necessary to keep the planned order quantity in synch with the flow
schedules to prevent overstatement of demand.
2.
3.
Choose OK.
Profile Options
This section describes the Oracle MRP profile options. In addition to descriptions, you
can see the default value and updatable level.
Implementing Profile Options Summary
The table below indicates whether you (the User) can view or update the profile option
and at which System Administrator levels the profile options can be updated: at the
user, responsibility, application, or site levels.
A Required profile option requires you to provide a value. An Optional profile option
already provides a default value, so you only need to change it if you don't want to
accept the default.
Profile
Option
User
System
Administ
rator User
System
Administ
rator Responsi
bility
System
Administ
rator Applicati
on
System
Administ
rator Site
Required
?
Default
Value
Setting Up 1-25
MRP:AT
P
Assignme
nt Set
Required
No
Default
MRP:
Calculate
Excess
Exception
s on Time
Fence
Optional
No
MRP:
Calculate
Suggeste
d
Repetitiv
e
Schedule
s
Optional
No
Default
MRP:
Compute
Sales
Order
Changes
Optional
Yes
MRP:
Consume
Forecast
Set
Summary
Optional
No
Default
MRP:
Consume
Forecast
Optional
Yes
MRP:
Consume
MDS
Optional
Yes
MRP:
Consume
MPS
Optional
Yes
MRP:
Cutoff
Date
Offset
Months
Optional
12
MRP:
Debug
Mode
Optional
No
MRP:
Default
DRP Plan
Name
Optional
No
Default
MRP:
Default
Forecast
Date
Optional
Yes
Key
You can view the profile option but cannot change it.
Profile
Option
User
System
Administ
rator User
System
Administ
rator Responsi
bility
System
Administ
rator Applicati
on
System
Administ
rator Site
Required
?
Default
Value
MRP:
Default
Forecast
Name
Optional
No
Default
MRP:
Default
Plan
Name
Optional
No
Default
Setting Up 1-27
MRP:
Default
Schedule
Name
Optional
No
Default
MRP:
Default
Sourcing
Assignme
nt Set
Optional
No
Default
MRP:
Demand
Time
Fence
Days
Optional
No
Default
MRP:
Environ
ment
Variable
to Set
Path for
MRP
Files
Optional
No
Default
MRP:
Firm
Planned
Order
Time
Fence
Optional
Yes
MRP:
Firm
Requisiti
ons
within
Time
Fence
Optional
No
Default
MRP:
Include
Schedule
d
Receipts
in Use-up
Calculati
on
Optional
No
MRP:
Interface
Table
History
Days
Optional
No
Default
MRP:
Maintain
Original
Schedule
Version
Optional
No
MRP:
MPS
Relief
Batch
Size
Optional
No
Default
MRP:
MPS
Relief
Direction
Optional
Backwar
d, then
forward
MRP:
Perform
Planning
Manager
Functions
in Loads
Optional
Yes
MRP:
Plan
Revenue
Discount
Percent
Optional
Setting Up 1-29
MRP:
Plan
Revenue
Price List
Required
No
Default
MRP:
Planning
Manager
Batch
Size
Optional
No
Default
MRP:
Planning
Manager
Max
Workers
Optional
10
MRP:
Purchasi
ng by
Revision
Optional
No
Default
Key
You can view the profile option but cannot change it.
Profile
Option
User
System
Administ
rator User
System
Administ
rator Responsi
bility
System
Administ
rator Applicati
on
System
Administ
rator Site
Required
?
Default
Value
MRP:
Purge
Batch
Size
Optional
25000
MRP:
Requisiti
on Load
Group
Option
Optional
Suppliers
MRP:
Retain
Dates
within
Calendar
Boundary
Optional
Yes
MRP:
Snapshot
Pause for
Lock
(Minutes)
Optional
MRP:
Snapshot
Workers
Optional
MRP:
Sourcing
Rule
Category
Set
Optional
No
Default
MRP:
Time
Fence
Warning
Optional
Yes
MRP:
Trace
Mode
Optional
No
MRP: Use
Direct
Load
Option
Optional
No
MRP: Use
Ship
Arrived
Flag
Optional
No
Key
You can view the profile option but cannot change it.
Setting Up 1-31
The planning manager verifies the setting of this option before performing forecast
consumption. If it is set to No, the planning manager does not update forecast entries.
The planning manager processes any sales order demand occurring while this profile is
set to No when you set the profile option back to Yes.
This profile has a predefined value of Yes upon installation.
MRP:Consume MDS
Indicates whether to enable or temporarily disable shipment relief of a master demand
schedule. Available values are listed below:
Yes - Enable shipment relief.
No - Disable shipment relief.
The planning manager verifies the setting of this option before performing shipment
relief. If it is set to No, the planning manager does not update MDS entries. The
planning manager processes any sales order shipments occurring while this profile is
set to No when you set the profile option back to Yes.
This profile has a predefined value of Yes upon installation.
MRP:Consume MPS
Indicates whether to enable or temporarily disable production relief of a master
production schedule. Available values are listed below:
Yes - Enable production relief.
No - Disable production relief.
The planning manager verifies the setting of this option before performing production
relief. If it is set to No, the planning manager does not update MPS entries. The
planning manager processes any purchase requisitions and discrete jobs occurring
while this profile is set to No when you set the profile option back to Yes.
This profile has a predefined value of Yes upon installation.
MRP:Cutoff Date Offset Months
Specifies the number of months from today to default the cutoff date for all forecasting,
scheduling and planning forms. Oracle MRP loads the forecast, master scheduling, and
material requirement entries from the current date up to and including this date.
MRP:Debug Mode
Indicates whether to enable debug messages within Oracle MRP. Available values are
listed below:
Yes - Enable debug messages.
No - Do not enable debug messages.
This profile has a predefined value of No upon installation.
MRP:Default DRP Plan Name
Setting Up 1-33
Specifies the DRP plan name that defaults when navigating to the Plan Options
window, Plan Status window, or the Planner Workbench.
MRP:Default Forecast Date
Indicates whether to default the forecast date to the next valid day/week/period in the
Enter Forecast Entries window. Available values are listed below:
Yes - Default the forecast date to the next valid day/week/period in the Enter Forecast
Entries form.
No - Do not default the forecast date to the next valid day/week/period in the Enter
Forecast Entries form.
This profile has a predefined value of Yes upon installation.
MRP:Default Forecast Name
Specifies the forecast name that defaults when navigating to any of the forecasting
forms.
MRP:Default Plan Name
Specifies the MRP or MPS plan name that defaults when navigating to any of the
planning forms.
MRP:Default Schedule Name
Specifies the schedule name that defaults when navigating to any of the scheduling
forms.
MRP:Default Sourcing Assignment Set
Determines the sourcing assignment set that Oracle Purchasing uses to assign sources to
requisitions.
MRP:Demand Time Fence Days
Indicates the number of time fence days for forecast set consumption and MDS (sales
order) load.
MRP:Environment Variable to Set Path for MRP Files
Specifies the appropriate path for the MRP files. If this profile is not used, the files are
written to $MRP_TOP/$APPLOUT.
This profile contains no pathname following the installation.
MRP:Firm Planned Order Time Fence
Indicates whether to form natural time fences for your MRP firm planned orders when
launching the planning process. A MRP firm planned order is an order that is frozen in
quantity and time (unavailable for rescheduling). Available values are listed below:
Yes - Form natural time fences for your MRP firm planned orders when launching the
planning process.
No - Do not form natural time fences for your MRP firm planned orders when
Setting Up 1-35
Indicates the direction in which the production relief takes place when relieving master
production schedule entries. Available values are listed below:
Backward, then Forward - Oracle Master Scheduling relieves master production
schedule entries backwards from the discrete job due date, then forwards until it finds
enough schedule quantity to relieve.
Forward only - Oracle Master Scheduling relieves master production schedule entries
only forward from the discrete job due date until it finds enough schedule quantity to
relieve.
Attention: When you change any of these profile options you must restart the planning
manager to activate the new profil option.
This profile has a predefined value of Backward, then forward upon installation.
Note: The name of this profile option in Release 10 is MRP:Relief
Directional Control.
the example above, a value of 100 means that the Planning Manager could divide the
work across 10 processes, while a value of 200 means that only 5 processes could
operate simultaneously.
MRP:Planning Manager Max Workers
Indicates the maximum number of workers to be launched by the planning manager. If
there are many rows processing, the planning manager continues to spawn more
workers, until all rows have been processed, or the number of Planning Manager
Workers running or pending matches or exceeds the value of MRP:Planning Manager
Workers.
A larger value for this profile means that the Planning Manager can use more workers
to process tasks. However, a larger value could also mean that the concurrent manager
queue becomes filled with workers, and other processes do not run.
In general, do not define a value that exceeds the maximum number of concurrent
programs that can run simultaneously.
This profile has a predefined value of 10 upon installation.
MRP:Purchasing by Revision
Indicates whether to pass on item revision to the purchase requisition.
MRP:Purge Batch Size
Indicates the batch size for the number of rows that the planning purge process deletes
between commits. The larger the number, the faster the purge processes performs. The
lower the number, the smaller the rollback segments required.
This profile has a predefined value of 25000 upon installation.
MRP:Requisition Load Group Option
Indicates the group by option used when loading requisitions using the Planner
Workbench form. Available values are listed below:
All on one - Create one purchase requisition for all recommended orders.
Buyer - Create one purchase requisition for buyer. Within each requisition, create one
line for each planned order for the buyer.
Category - Create one purchase requisition for each category of items. Within each
requisition, create one line for each planned order for the category.
Inventory item - Create one purchase requisition for each inventory item. Within each
requisition, create one line for each planned order for the item.
One each - Create one purchase requisition for recommended order.
Planner - Create one purchase requisition for each planner. Within each requisition,
create one line for each planned order for the planner.
Supplier - Create one purchase requisition for each supplier. Within each requisition,
create one line for each planned order for the supplier.
Setting Up 1-37
at all levels.
MRP:Use Ship Arrived Flag
Indicates how to treat sales orders shipped to customers. You can automatically treat
sales orders as "arrived" at a customer site after the intransit lead time has expired, or
you can manually update the ARRIVED_FLAG in SO_PICKING_HEADERS.
This profile is used by the Memory-based Planning Engine when a customer is
modelled as an organization.
This profile has a predefined value of No upon installation. Available values are listed
below:
Yes - Use arrived flag in SO_PICKING_HEADERS.
No - Use intransit time between source and the destination organizations.
See Also
Setting Up 1-39
2
Forecasting
Overview of Forecasting
You can estimate future demand for items using any combination of historical,
statistical, and intuitive forecasting techniques. You can create multiple forecasts and
group complimenting forecasts into forecast sets.
Forecasts are consumed each time your customers place sales order demand for a
forecasted product. You can load forecasts, together with sales orders, into master
demand and production schedules, and use the master schedules to drive material
requirements planning.
Time Buckets
You can forecast with daily buckets in the short term, weekly buckets in the midterm,
and periodic buckets in the longer term.
Entry Options
You can define a forecast for a particular item by entering a single date and quantity.
You can also specify a start and end date, and a quantity.
Forecasting 2-1
Alternate Bills
You can associate alternate bills of material to multiple forecasts for the same item,
exploding different components, usages, and planning percentages.
Consumption
You can manually or automatically consume forecasted demand with sales order
(actual) demand.
Copy
To help manage and consolidate your forecast information, you can create new
forecasts from existing forecasts or forecast sets. You can copy forecasts from your own
organization or from any other organization.
Forecast Rules
You can define item forecast rules in Oracle Inventory to establish the forecast method,
bucket type, and sources of demand that are considered when compiling a statistical or
focus forecast.
Review
You can review all aspects of your forecasts using online inquiries and reports. This
information can be viewed by forecast set or individual forecast.
Forecasting 2-3
Statistical forecasting which you can use to forecast any number of periods into the
future
See Also
Generating a Forecast
To generate a focus or statistical forecast:
1.
2.
3.
Pick a range of items to forecast for: all items, a specific item, a category of items, or
all items in a category set.
4.
6.
Choose OK.
7.
See Also
Submitting a Request, Oracle Applications User's Guide
Forecast Levels
In addition to designating the minimum level of detail for which the forecast is defined,
the forecast level also serves as a consumption level. You can define the forecast level
with or without the demand class that also controls the consumption of forecasts. You
can define the following consumption levels for a forecast set:
item level
customer level
While attempting to consume a forecast, the consumption process looks for a forecast
containing an item that corresponds to the sales order information. When it finds an
entry, it checks the forecast using the criteria you defined for the forecast level. For
example, if you define the forecast level to be ship to, the forecast consumption process
searches the forecasts for the customer/ship - to address associated with the sales order.
Important: If you enter customer information but do not specify the
Forecasting 2-5
Group forecasts that represent different scenarios. See: Forecast Set Examples.
2.
3.
Select a bucket type to group forecast entries by days, weeks, or accounting periods.
4.
Select the level that determines how forecasts in the set are defined and consumed.
See: Forecast Levels.
Ship - To: Item, customer, and shipping identifier
Bill - To: Item, customer, and billing identifier
Customer: Item and customer
Item: This is the only option available if you are not using Oracle Order
Management or Oracle Receivables.
5.
6.
Important: All the items within a forecast set are shown, including
Enter a disable date. After this date, you can no longer define a forecast name for
the set. You can view disabled forecasts but not modify them.
Defining Forecasts
Forecasts by Region
You have three forecasts named FCA, FCB, and FCC within a forecast set. Salesperson
A, responsible for the Eastern region, maintains FCA. Salesperson B maintains FCB for
the Midwest. Salesperson C maintains FCC for the Western region. In this situation,
FCA, FCB, and FCC each represent a part of the whole forecast. Together, their sum
represents the total forecast.
Forecast Scenarios
You have three forecast sets named SETA, SETB, and SETC. These forecast sets
represent different scenarios. SETA is the forecast for the bestcase scenario year of sales,
while SETB is the planned scenario year of sales. SETC shows the worst-case scenario
year of sales. You may want to maintain all three forecast sets simultaneously, so you
can compare and contrast the effect each has on your material plan.
Defining a Forecast
A forecast shows predicted future demand for items over time.
You can assign any number of items to a forecast, and use the same item in multiple
forecasts. For each item you enter the days, weeks, or periods and the quantities that
you expect to ship.
A forecast entry with a forecast end date specifies the same quantity scheduled for each
day, week, or period until the forecast end date. A forecast entry without a forecast end
date is valid only for the date and time bucket specified.
Prerequisites
Define at least one forecast set. See: Defining a Forecast Set.
Forecasting 2-7
To define a forecast:
1.
2.
3.
4.
Choose the Forecast Items button to open the Forecast Items window.
You can choose the Folder menu to customize your display. See: Customizing the
Presentation of Data in a Folder, Oracle Applications User's Guide
5.
Enter an item.
6.
7.
8.
Enter a date. This is typically the date you expect to ship the item or the beginning
of the week or period that you expect to ship the item.
9.
Enter an optional end Date. This creates forecast entries of the same quantity for
each day, week, or period until the end date. A forecast entry without an end date is
valid just for the date and time bucket specified.
10. Enter a current quantity. This also becomes the original quantity and the total.
Forecast consumption reduces the current quantity. Forecast consumption plus the
current quantity equals the total.
11. Enter an optional confidence percentage that the forecasted item will become actual
demand. Oracle MRP multiplies this percentage by the forecast quantity when you
load it into a master schedule.
12. If you are working in a project environment, enter a valid project and task
reference. After entering a valid reference, you can select a price list and an average
discount in the flexfield.
Note: Your ability to enter project and task references is determined
2.
3.
4.
Select the forecast/load source list. Select either one of your source lists or one of
your forecasts, according to the source type you selected above.
5.
Forecasting 2-9
FCB.
6.
Enter the start and cutoff dates for the forecast merge. Forecast entries are merged
from the start date to the cutoff date. If you specify carry forward days, the number
of days are subtracted from the cutoff date so that all merged entries have dates
before the cutoff date.
7.
8.
9.
See Also
start date = start date + carry forward days backward consumption days
end date = cutoff date + carry forward days
If you specify backward consumption days for the forecast, Oracle MRP uses it to adjust
the start date because it defines the consumption window in which forecast
consumption consumes forecasts. Oracle MRP loads any forecast within that window so
that it can consider the forecast for consumption purposes. This may include past due
forecasts.
If you specify carry forward days, Oracle MRP uses them to determine which entries
are within the current time frame since they shift the forecast dates during the forecast
load. For example, if the start date is 16-MAR and you enter a cutoff date of 20-MAR
and specify four carry forward days, the forecast load process recalculates the current
time frame to 12-MAR through 16-MAR. Suppose the source forecast has entries of
13-MAR and 17-MAR. Based on this, Oracle MRP considers the forecast defined on
13-MAR as the only eligible forecast. When you load this forecast, the forecast load
process adjusts the date to 17-MAR to add in the carry forward days.
When you use weekly and period bucket types, these dates are recalculated by
identifying the beginning date of the workweek and period that the start date falls into.
The same calculation is applied to the end date.
A forecast entry with a forecast end date is considered current if the range that it covers
includes any part of the current time frame established above. This would include past
due entries.
order the components under it. If you want to ensure that you forecast
the components, as well as the planning item itself, you can explode the
planning item during a forecast merge.
When you explode a forecast for a model, you can track which forecasted end model
generated the forecast for the lower level components. This allows you to trace the
forecasted demand for a component if it is defined in more than one model. You can
also trace exploded forecasts to planning bills.
You can also explode a product-family forecast to the member items, and see which
product family generated the forecast for all the items at lower levels.
Forecasting 2-11
window. This window displays the same information as the Forecast Entries window
with the difference that it contains a listing of the all the items in a forecast set. From
here you can access bucketed and consumption details.
2.
See Also
2.
3.
Select the Include Entries Before Start Date check box if you want to display forecast
entries, bucketed in the first bucket, before the start date you enter.
4.
Select the quantity display for bucketed forecast entries: Units (item quantity) or
Values (item quantity multiplied by the standard cost).
5.
Select the date range for which you want to display forecast bucketed information.
You can enter dates in the past to review historic forecast information.
6.
If you select the check box that beside the bucket dates, the data in this window is
refreshed automatically. If the check box is blank, data is refreshed only in the fields
where you place the cursor.
7.
Choose Detail to view detail forecast entries for an item in the Forecast Entries
window. If you do not select a bucket range, detail forecast entries for an item for all
bucketed dates between the start date and cutoff date of the bucket options display.
Forecast Consumption
Overview of Forecast Consumption
Forecast consumption replaces forecasted demand with actual sales order demand.
Each time you create a sales order line, you create actual demand. If the actual demand
is already forecasted, the forecast demand must be decremented by the sales order
quantity to avoid counting the same demand twice.
For example, this table shows the forecast and sales orders for item 1.
Order Type
Quantity
Date
Forecast
50
June 1
10
June 1
SO2
25
June 1
This table shows the forecast and sales orders for item 1 after forecast consumption.
Order Type
Quantity
Date
Forecast
June 1
SO1
10
June 1
SO 2
25
June 1
Forecast consumption relieves forecast items based on the sales order line schedule
date. When an exact date match is found, consumption decrements the forecast entry by
the sales order quantity. Other factors that may affect the forecast consumption process
are backward and forward consumption days and forecast bucket type.
When you create a new forecast, especially from an external source, you can also apply
consumption that has already occurred for other forecasts to the new one.
Forecast Control
You control forecast consumption against each component by setting its organization
item attribute Forecast control:
Forecasting 2-13
Consume: Sales orders for this item consume forecasts for this item in the same
organization.
Consume and derive: Sales orders for this item consume forecasts for this item in
the same organization. Select this option if you will also do forecast explosion
against the item; see Forecast Explosion, page 2-26.
None: Sales orders for this item do not consume forecasts for this item.
Forecast Set #1 contains Forecast #1 and Forecast #2. The same item, Item A, belongs to
both forecasts within the set. Some possible scenarios and how consumption would
work are:
If the sales order quantity is less than the forecast quantity of each forecast, only one
of the forecasts for Item A is consumed.
If one of the two forecasts for Item A were on the same day as the sales order line
schedule date, that forecast would be consumed first.
If the forecast for Item A is for the same day in both forecasts, the forecasts are
consumed in alphanumeric order by forecast name.
For example, if each forecast for Item A is for a quantity of 100 and you place sales
order demand for 20, the consumption process would decrement only Forecast #1 to 80.
However, if the sales order quantity is for 120, Forecast #1 is decremented from
100 to zero and Forecast #2 is decremented from 100 to 80.
Suppose that the planning percentages for the member items are:
60% for B
40% for C
100 - 20 = 80 for A
60 - 20 = 40 for B
40 - 0 = 40 for C
Forecasting 2-15
Similarly, if item B is a model and if Forecast Control for both D and E is set to Consume
and Derive, then the forecast for item D gets consumed by 20 and the forecast for item E
gets consumed by 20. The forecasts for items F and G remain the same.
Forecast Set #1 contains Forecast #1 and Forecast Set #2 contains Forecast #2. The same
item, Item A, belongs to both forecasts within each set.
When you create a sales order, both forecasts for Item A in Forecast Set #1 and Forecast
Set #2 are consumed. This is because consumption occurs against each forecast set, and
Item A exists in both forecast sets.
For example, if each forecast for Item A is quantity 100 and you place sales order
demand for 20, the consumption process would decrement each forecast in each set
from 100 to 80.
Note: In this example, Forecast Set #1 and Forecast Set #2 are most
Consumption Level
You can specify consumption levels in the forecast set:
Item level: Consumption occurs when item numbers match between the forecast
entry and the sales order line.
Customer Level: Consumption occurs when item numbers and customer numbers
match between the forecast entry and the sales order line.
Ship-to level: Consumption occurs when item numbers, customer numbers, and
customer ship-to addresses match between the forecast entry and the sales order
line
Bill-to level: Consumption occurs when item numbers, customer numbers, and
customer bill-to addresses match between the forecast entry and the sales order line
You do not always have an exact match between the sales order line schedule dates
and forecast entry dates.
Your forecast entry quantity is not always sufficient to cover the sales order
quantities.
It searches backward from the sales order line schedule date, workday by workday,
for forecast quantities to consume.
If that search is not successful in consuming the entire sales order line quantity, it
searches forward from the sales order line schedule date, workday by workday, for
forecast quantities to consume.
If that search is not successful in consuming the entire sales order line quantity, it
creates an overconsumption (negative demand) entry on the sales order line
schedule date.
Forecasting 2-17
forecasts that match the default demand class for the organization first, and then
consumes forecast entries that have no demand class defined.
Overconsumption
When consumption cannot find an appropriate forecast entry to consume, it creates, for
information purposes only, a new forecast entry at the forecast set level. This entry has
a zero original quantity and a negative current quantity equal to the unconsumed
demand.
The entry is marked with an origination of overconsumption.
In the above example, daily forecast exists for 20 on the 2nd and the 9th with an outlier
update percent of 50 on each forecast. When you place sales order demand for 50 on the
9th, the forecast consumption process attempts to consume on the sales order line
schedule date only, since the forecast is stated in daily buckets and no backward
consumption days exist. Because an outlier update percent of 50 exists on the forecast,
the consumption process consumes only 50% of the forecast. The outlier update percent
applies to how much of the original forecast quantity, not the sales order, the
consumption process can consume. In this example, the consumption process consumes
50% of the forecast (10) and the rest of the sales order quantity (40) is overconsumed. If
there were a backward consumption days of 5, 50% of the forecast on the 2nd would
also be consumed, and the overconsumed quantity would be 30.
Using the same example, if another sales order for 50 is placed on the 9th, it consumes
50% of the original forecast quantity (10) and the current forecast quantity on the 9th
becomes zero. Overconsumption is increased by an additional 40 to a new total on the
9th (80).
Unconsumption
When you decrease the order quantity on a sales order line item, Oracle MRP
unconsumes (increments) the appropriate forecast entry, according to the criteria
described for consumption. This process is also called deconsumption.
This process attempts to remove overconsumption entries at the forecast set level first,
before searching for an appropriate forecast entry to unconsume. See:
Overconsumption.
Note: Return Material Authorizations (RMAs) do not trigger the
uncomsumption process.
If you change a sales order line schedule date, Oracle MRP unconsumes the sales order
quantity based on the old schedule date and reconsumes the sales order quantity based
on the new schedule date.
Note: You can create sales orders with due datesthe manufacturing
calendar to express future demand that has uncertain due dates. Oracle
MRP consumes the forecast on the last valid workday in the
manufacturing calendar. When the sales order schedule date is
changed, it unconsumes on the last workday and reconsumes on the
sales order line schedule date.
Forecasting 2-19
The process tries to consume a forecast entry on the 12th (the sales order date) because
the forecast is stated in daily buckets and no backward consumption days exist. Since
there are no forecasts on the 12th, an overconsumption entry is created on the 12th and
the forecasts remain the same.
Here, the process tries to consume a forecast entry between the 12th (the sales order
date) and the 9th (backward 3 days). The forecast entry of 20 each on the 9th is
consumed. The remaining sales order quantity of 5 creates an overconsumption entry.
In this example, the process tries to consume a forecast entry between the 2nd (back 3
days from the sales order date of the 5th) and the 10th (forward 3 workdays, skipping
the weekend). Going backward, the forecast entry of 20 each on the 2nd is consumed.
Going forward, the forecast entry of 20 on the 9th is reduced to 15 each.
In the above example, weekly forecasts exists for 20 on the 2nd and the 9th. When you
place sales order demand for 25 on the 12th, the forecast consumption process attempts
to consume in the week of the sales order only, since the forecast is stated in weekly
buckets and no backward consumption days exist. Since there is a forecast in the week
of the 12th, the entire forecast of 20 is consumed by the sales order for
25 and the remainder of the sales order becomes an overconsumption of 5 on the sales
order line schedule date.
Forecasting 2-21
In the above example, weekly forecasts exists for 20 on the 2nd and the 9th. When you
place sales order demand for 25 on the 12th, the forecast consumption process attempts
to consume in the week of the sales order first and then backwards for the number of
backward consumption days.
In this example, the backward consumption days of 5 causes the consumption process
to go into another weekly bucket where it also consumes anything from that week.
Since there is a forecast in the week of the 12th, the sales order for 25 consumes the
entire forecast of 20 and then consumes the remainder of the sales order quantity (5)
from the forecast on the 2nd.
Note: When you use weekly or periodic buckets and the consumption
days carry the consumption process into a different week or period, the
consumption process consumes from anywhere in the week or period,
regardless of whether the consumption days span the entire week or
period.
In this example, the process subtracts the backward consumption days from the 12th
(excluding non-workdays) to day 5. Since day 5 is in the previous week, it consumes
forecasts anywhere within the bucket; in this case, on the 2nd.
The consumption process consumes any forecasts that are included in the time fence
created by the backward or forward consumption days, and then any other forecasts
that are in the week or period. However, it does not consume a daily forecast that exists
in the week or period if it is not covered by the time fence. In the above example, a daily
forecast for the same item on the 4th would not have been consumed by the sales order;
however, a daily forecast on the 5th would have since it is in the period included in the
backward consumption days.
In the above example, a periodic forecast exists for 20 on the 2nd, the first day of the
period. When you place sales order demand for 25 on the 12th (assuming it is in the
same period), the forecast consumption process attempts to consume in the period of
the sales order only, since the forecast is stated in periodic buckets and no backward
consumption days exist. Since there is a forecast in the period starting on the 2nd, the
entire forecast of 20 is consumed by the sales order for 25 and the remainder of the sales
order becomes an overconsumption of 5.
In the above example, a periodic forecast exists for 20 on the 2nd, the first day of the
period. When you place sales order demand for 25 on the 12th (assuming it is in the
same period), the forecast consumption process attempts to consume in the period of
the sales order line schedule date first and then backwards for the number of backward
consumption days.
In this example, the backward consumption days does not cause the consumption
process to go into another periodic bucket. It behaves the same as if there were no
backward consumption days. Since there is a forecast in the period of the 2nd, the sales
order for 25 consumes, and the remainder of the sales order becomes an
Forecasting 2-23
entries, forecast consumption first consumes the daily entries, then the
weekly entries, and lastly the periodic forecast entries that are included
in the time fence created by the backward and/or forward consumption
days.
Navigate to the Forecast Sets window. Query the set name that includes the new
forecast. Choose the Consume button to open the Consume Forecast Set window.
or:
2.
Navigate directly to the Consume Forecast Set window. Select the set name that
includes the new forecast.
3.
Select a number of sales orders within the demand time fence to include. Including
only sales orders from today forward is useful if your forecast begins today, and/or
if the forecast begins on the first day of a period, rather than in the middle of a
period.
4.
Choose OK.
5.
See Also
Planning Manager
2.
3.
4.
2.
3.
Click the Forecast Set Items button to see which items on the forecast set were
overconsumed.
The Forecast Items window that appears shows both individual items and product
family items.
Note: Only overconsumed items are shown when you access the
Forecasting 2-25
Overconsumption
Forecast Explosion
You can define and maintain forecasts for any item, at any level on your bills of
material. Forecast explosion is a process that creates forecasts for components from the
forecasts of their parents. It occurs in the following situations:
Product family forecasts to product family member item forecasts. The planning
engine considers these exploded forecasts as independent demand and uses
pegging to link then to their product family forecast.
Model forecasts to other model, option class, option item, and included item
forecasts. See Configure to Order Forecast Explosion, Oracle Advanced Supply Chain
Planning Implementation and User's Guide.
In a product family bill of material, product family member item A has planning
percentage 30%, product family member item B has planning percentage 50%, and
After forecast explosion, the forecast quantity for product family member item A is
300, for product family member item B is 500, and for product family member item
C is 200.
See Creating a Bill of Material, Oracle Bills of Material User's Guide and attend to tab
Component Details, field Planning %.
The following table illustrates a planning bill for Training Computer, a planning item
that represents a planning bill for three types of computers: laptop, desktop, and server.
The planning percent assigned to each member of the planning bill represents
anticipated future demand for each product.
Level
Item
Planning %
Training Computer
Planning
.2
. Laptop Computer
Model
60%
.2
. Desktop Computer
Model
20%
.2
. Server Computer
Model
20%
The following table illustrates forecast explosion, via the planning bill described in the
previous table, for a forecast of 100 Training Computers. The table also illustrates
forecast consumption after you place sales order demand for 20 Laptop Computers.
Original forecast shows forecast quantities before forecast consumption. Current
forecast shows forecast quantities after consumption by sales order demand.
Level
Item
Original Forecast
Current Forecast
Training Computer
100
100
.2
. Laptop Computer
60
40
.2
. Desktop Computer
20
20
.2
. Server Computer
20
20
The planning percentages of all of the components of a parent can add to more than
100%.
Forecasting 2-27
You control forecast explosion to each component by setting its organization item
attribute Forecast control:
Consume and derive: There can be planning engine forecast explosion for models
depending on plan option Explode Forecast. The planning engine does not explode
multi-organization models.
None: There can be planning engine forecast explosion for product families
depending on plan option Explode Forecast.
For information about forecast explosion for model forecasts, see Configure to Order
Forecast Explosion, page 2-36.
Load/Copy/Merge Process
When you use the Load/Copy/Merge window to load a planning item forecast into
another forecast, you can choose to explode the aggregate forecast for the planning item
into detailed forecasts for each of the components defined on the planning bill. The
forecast quantities exploded to the components are calculated by extending the
planning item forecast by the component usages and planning percents defined on the
planning bill. You can also choose to explode forecasts when you load a planning item
forecast into a master schedule.
Option classes: A bill of material structure whose components are the options that
Standard items: The options from which the customer chooses, for example, red,
green, and blue. They are components of the option classes.
Included items (also known as mandatory components): A standard item that the
customer receives regardless of options selected, for example, an instruction
brochure. They are components of the model item.
Another model: For example, a personal computer. The customer chooses the main
components and the manufacturer assembles them into a case (assemble-to-order).
The customer also chooses peripheral items that the manufacturer or distributor
ships separately from the main unit and that the recipient attaches to the main unit.
The personal computer is a pick-to-order model, the main unit is an
assemble-to-order model component under the pick-to-order model, and the
peripherals are option class components under the pick-to-order model.
Item
Optional
Planning %
.2
. Laptop Computer
Model
No
60%
..3
. . Carrying Case
Standard
No
100%
..3
. . Keyboard
Standard
No
100%
..3
. . CPU
Option Class
No
100%
..3
. . Monitor
Option Class
No
100%
..3
. . Operating System
Option Class
Yes
90%
Forecasting 2-29
expected to be sold with an EGA monitor. Notice that the Monitor option class is not
optional. This means that customers must always choose one of the Monitor options
when ordering Laptop Computer. Of the 70% of Laptop Computers sold with a VGA
monitor, 50% are expected to be sold with the VGA1 monitor and 50% are expected to
be sold with the VGA2 monitor. The VGA option class also includes a mandatory
component, VGA Manual, that is always shipped with Laptop Computer if the VGA
monitor option class is chosen, regardless of the VGA option.
Level
Item
Optional
Planning %
..3
. . Monitor
Option Class
No
100%
...4
. . . VGA
Option Class
Yes
70%
....5
. . . . VGA Manual
Standard
No
100%
....5
. . . . VGA1
Standard
Yes
50%
....5
. . . . VGA2
Standard
Yes
50%
...4
. . . EGA
Option Class
Yes
30%
....5
. . . . EGA1
Standard
No
55%
....5
. . . . EGA2
Standard
Yes
45%
Forecasting 2-31
If you forecast demand for an item directly, and explode forecast demand to the item,
set Forecast Control to Consume and Derive.
Sales Order Demand
Sales order demand is demand that you place when your customers order
configurations. As your customers order configurations, Oracle Order Management
automatically places sales order demand for each model, option class, and option
selected by your customer when they place the order.
If you place sales order demand for an item, but do not forecast the item, set Forecast
Control to None.
Derived Sales Order Demand
Under normal circumstances, Oracle Order Management does not place sales order
demand for mandatory components when your customers order configurations. If you
are forecasting key mandatory components, however, you will usually want to
maintain your forecasts by generating sales order demand for the mandatory
components and consuming the forecasts as your customers place sales orders.
You can set the Forecast Control attribute to Consume or Consume and Derive to
automatically place demand and consume forecasts for mandatory components when
you place sales orders demand for configurations that include the mandatory
components.
If you forecast demand for a mandatory component, either directly or through forecast
explosion, set Forecast Control to Consume or Consume and Derive.
Summary
The following table summarizes, for each type of item, the types of demand that
configure to order assumes you place for different values of Forecast Control.
Item Type
Forecast
Control
Forecast
Expl
oded
Forec
ast
Exploded
Sales
Order
Derived Sales
Order
Consume
Yes
Yes
Consume and
Derive
Yes
Yes
Yes
Option
Consume
Yes
Yes
Option
Consume and
Derive
Option
None
Mandatory
Component
Consume
Mandatory
Component
Consume and
Derive
Mandatory
Component
None
Product Family
Consume
Product Family
Consume and
Derive
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Forecasting 2-33
forecast explosion
forecast consumption
planning
production relief
Shipment relief
Forecast Consumption (a) and Forecast Consumption (b) represent forecast consumption
before and after the Auto-Create Configuration process creates the configuration item
and single-level bill for a configuration. CD represents component demand, NR
represents net requirements, SO represents sales order demand, and FC represents
forecast demand.
Note: Notice that the only difference between the Consume option and
Forecast
Control
Process
Models and
Option Classes
Options
Mandatory
Components
Consume
Forecast
Explosion
Do not generate
exploded forecast
demand
Do not generate
exploded forecast
demand
Do not generate
exploded forecast
demand
Forecast
Consumptio
n (a)
Consume actual
sales order
demand
Consume actual
sales order demand
Consume derived
sales order demand
Forecast
Consumptio
n (b)
Consume
configuration
component
demand
Consume
configuration
component demand
Consume
configuration
component demand
MDS Load
Forecast
Control
Consume
and Derive
None
Process
Models and
Option Classes
Options
Mandatory
Components
Production
Relief
Relieve when
configuration
work order is
created
Relieve when
component work
order is created
Shipment
Relief
Relieve when
configuration sales
order is shipped
Relieve when
configuration sales
order is shipped
Relieve when
configuration sales
order is shipped
Forecast
Explosion
Generate exploded
forecast demand
Generate exploded
forecast demand
Generate exploded
forecast demand
Forecast
Consumptio
n (a)
As above
As above
As above
Forecast
Consumptio
n (b)
As above
As above
As above
MDS Load
As above
As above
As above
Production
Relief
As above
As above
As above
Shipment
Relief
As above
As above
As above
Forecast
Explosion
Not applicable
Do not generate
exploded forecast
demand
Do not generate
exploded forecast
demand
Forecast
Consumptio
n (a)
Not applicable
Consume actual
sales order demand
Do not consume
Forecast
Consumptio
n (b)
Not applicable
Do not consume
Do not consume
MDS Load
Not applicable
Forecasting 2-35
Forecast
Control
Process
Models and
Option Classes
Options
Mandatory
Components
Production
Relief
Not applicable
Relieve when
component work
order is created
Shipment
Relief
Not applicable
Do not relieve
Do not relieve
ATO
Model
ATO
Option
Class
ATO
Std. Item
PTO
Model
PTO
Option
Class
PTO
Std.
Item
Std. Item
Always
Always
Always
Never
Always
Always
Always
Never
Forecasting 2-37
Product
Family
Planning
Item
ATO
Model
ATO
Option
Class
ATO
Std.
Item
PTO
Model
PTO
Option
Class
PTO
Std.
Item
Std.
Item
Check
Check
Check
Check
Check
Check
Check
Check
Check
Item
BOM Item
Type
Forecast
Control
Optional
Plan %
FC
.2
. Laptop
Computer
Model
Consume
No
..3
. . Carrying
Case
Standard
Consume
and Derive
No
100%
100
..3
. . Keyboard
Standard
Consume
and Derive
No
100%
100
..3
. . CPU
Option
Class
Consume
and Derive
No
100%
100
...4
. . . 386
Processor
Standard
Consume
and Derive
Yes
65%
65
...4
. . . 486
Processor
Standard
Consume
and Derive
Yes
35%
35
100
Re-exploding Forecasts
You can change your planning and model forecasts at any time and reexplode new
forecasts to your option classes, options, and mandatory components. You can choose
to reconsume your new forecasts using the sales order demand history maintained by
Oracle MRP. This lets you quickly adjust your exploded forecasts in response to forecast
or bill of material changes.
Item
Customer
With inline forecast consumption, toe consumption occurs at the beginning of the
planning run, using the forecasts and sales orders that you use to drive the plan.
Consumption of Models
Forecast consumption takes place both before and after the AutoCreate Configuration
process creates a configuration item, bill, and routing for a configuration. The configure
to order process ensures that forecast consumption is consistent before and after the
creation of the configuration item.
Note: The fact that forecast consumption takes place twice, both before
Forecasting 2-39
Before you run the AutoCreate Configuration process, forecast consumption uses actual
sales order demand for models, option classes, options, and derived sales order demand
for selected mandatory components, to consume your forecasts.
Example: Before AutoCreate Configuration
The following example illustrates how forecast consumption consumes an exploded
forecast for 100 Laptop Computers when a customer places a sales order for 10 Laptop
Computers with 486 processors, VGA1 monitors, and DOS operating system. The SO
column shows sales order quantities. Notice that forecast consumption generates and
consumes derived sales order demand for each mandatory component where you have
set Forecast Control to Consume or Consume and Derive.
Forecast Consumption (1 of 2)
Level
Item
BOM Item
Type
Forecast
Control
Optional
Plan %
FC/ SO
.2
. Laptop
Computer
Model
Consume
90 10
..3
. . Carrying
Case
Standard
Consume
and Derive
No
100%
90 10
..3
..
Keyboard
Standard
Consume
and Derive
No
100%
90 10
Forecast Consumption (2 of 2)
Level
Item
BOM Item
Forecast
Optional
Plan
FC/
Type
Control
SO
..3
. . CPU
Option
Class
Consume
and Derive
No
100%
90 10
...4
. . . 386
Processor
Standard
Consume
and Derive
Yes
65%
65
...4
. . . 486
Processor
Standard
Consume
and Derive
Yes
35%
25 10
..3
. . Monitor
Option
Class
Consume
and Derive
No
100%
90 10
...4
. . . VGA
Option
Class
Consume
and Derive
Yes
70%
60 10
....5
. . . . VGA
Manual
Standard
Consume
and Derive
No
100%
60 10
....5
. . . . VGA1
Standard
Consume
and Derive
Yes
50%
25 10
....5
. . . . VGA2
Standard
Consume
and Derive
Yes
50%
35
...4
. . . EGA
Option
Class
Consume
and Derive
Yes
30%
30
....5
. . . . EGA1
Standard
Consume
and Derive
Yes
55%
16.5
....5
. . . . EGA2
Standard
Consume
and Derive
Yes
45%
13.5
...4
. . . Monitor
Manual
Standard
None
No
100%
..3
..
Operating
System
Option
Class
Consume
and Derive
Yes
90%
80 10
...4
. . DOS
Standard
Consume
and Derive
Yes
80%
62 10
Forecasting 2-41
..4
. . UNIX
Standard
Consume
and Derive
Yes
20%
18
Item
Optional
Laptop Computer001
Standard
No
Laptop Computer
Model
No
Carrying Case
Standard
No
Keyboard
Standard
No
CPU
Option Class
No
486 Processor
Standard
No
Monitor
Option Class
No
VGA
Option Class
No
VGA Manual
Standard
No
VGA1
Standard
No
Monitor Manual
Standard
No
Operating System
Option Class
No
DOS
Standard
No
In the post configuration stage, forecast consumption uses the sales order demand for
the new configuration item to consume forecasts. Typically, you do not have any
forecasts defined for unique configurations. Therefore, forecast consumption does not
find any forecasts to consume. If forecast explosion cannot find any forecasts to
consume, it explodes the configuration bill and consumes forecasts for each model and
option class on the bill. It also consumes forecasts for each standard item on the
configuration bill where Forecast Control is set to Consume or Consume and Derive.
To ensure that forecast consumption is consistent before and after the AutoCreate
Configuration process, forecast consumption only consumes forecasts for standard
items on configuration bills where Forecast Control is set to Consume or Consume and
Derive.
Note: If you set Forecast Control to None for an option, and then define
Forecasting 2-43
Item
BOM Item
Type
Forecast
Control
Optional
Plan %
FC/ SO
Laptop
Computer0
01
Standard
Consume
10
Forecast Consumption (1 of 2)
Level
Item
BOM Item
Type
Forecast
Control
Optional
Plan %
FC/ SO
Laptop
Computer
Model
Consume
90
.3
. Carrying
Case
Standard
Consume
and Derive
No
100%
90
Forecast Consumption (2 of 2)
Level
Item
BOM Item
Type
Forecast
Control
Optional
Plan %
FC/ SO
.3
. Keyboard
Standard
Consume
and Derive
No
100%
90
.3
. CPU
Option
Class
Consume
and Derive
No
100%
90
..4
. . 386
Processor
Standard
Consume
and Derive
Yes
65%
65
..4
. . 486
Processor
Standard
Consume
and Derive
Yes
35%
25
.3
. Monitor
Option
Class
Consume
and Derive
No
100%
90
..4
. . VGA
Option
Class
Consume
and Derive
Yes
70%
60
....5
. . . . VGA
Manual
Standard
Consume
and Derive
No
100%
60
....5
. . . . VGA1
Standard
Consume
and Derive
Yes
50%
25
....5
. . . . VGA2
Standard
Consume
and Derive
Yes
50%
35
...4
. . . EGA
Option
Class
Consume
and Derive
Yes
30%
30
....5
. . . . EGA1
Standard
Consume
and Derive
Yes
55%
16.5
....5
. . . . EGA2
Standard
Consume
and Derive
Yes
45%
13.5
...4
. . . Monitor
Manual
Standard
None
No
100%
..3
..
Operating
System
Option
Class
Consume
and Derive
Yes
90%
80
...4
. . . DOS
Standard
Consume
and Derive
Yes
80%
62
...4
. . . UNIX
Standard
Consume
and Derive
Yes
20%
18
Forecasting 2-45
Item
Optional
Laptop Basic
Standard
No
.2
. Laptop Computer
Model
No
.2
. Carrying Case
Standard
No
.2
. Keyboard
Standard
No
.2
. CPU
Option Class
No
.2
. 486 Processor
Standard
No
.2
. Monitor
Option Class
No
.2
. VGA
Option Class
No
.2
. VGA Manual
Standard
No
.2
. VGA1
Standard
No
.2
. Monitor Manual
Standard
No
.2
. Operating System
Option Class
No
.2
. DOS
Standard
No
The following table illustrates consumption of a forecast for 100 Laptop Basics after a
customer places a sales order for 10 units.
Forecast Consumption
Item
Original Forecast
Current Forecast
Laptop Basic
100
90
If you have not defined forecasts for the predefined configuration, forecast
consumption explodes the configuration bill and consumes forecasts for each model
and option class. Forecast consumption also consumes forecasts for each standard item
on the configuration bill where Forecast Control is set to Consume or Consume and Derive
.
The following table illustrates consumption of the same sales order for 10 Laptop Basics
when you have not defined a forecast for Laptop Basic. Note that the original forecast
quantities for Laptop Basic's components have not been exploded from Laptop Basic,
since you cannot explode forecasts from a standard item. Any forecasts that do exist for
Laptop Basic's components must have been entered manually or exploded from a
planning item, model, or option class forecast. This example assumes that Forecast
Control is set to Consume or Consume and Derive for all standard components on Laptop
Basic's configuration bill.
Forecast Consumption
Item
Original Forecast
Current Forecast
Laptop Computer
20
10
Carrying Case
20
10
Keyboard
20
10
CPU
30
20
486 Processor
50
40
Monitor
40
30
VGA
40
20
VGA Manual
50
40
VGA1
20
10
Forecasting 2-47
Monitor Manual
30
20
Operating System
30
20
DOS
30
20
3
Master Scheduling
demand management
scheduling production
You use the schedules generated by master scheduling as input to other manufacturing
functions, such as material requirements planning and rough-cut capacity planning.
Note: The planning products support Oracle Project Manufacturing's
end item model/unit effectivity. The end-item model Unit Number field
is visible if this featured is enabled allowing you to:
Load sales orders into a MDS, and have the specified unit number
carried over to the schedule entry
item forecasts
spares demand
sales orders
internal requisitions
Supply Chain Planning users can also manage interorganizational demand and create
distribution requirements plans (DRP) from an MDS. See: Master Scheduling in Supply
Chain Planning
Supply Chain Planning users can also run a multi-organization MPS and create
distribution requirements plans (DRP) from an MPS. See: Master Scheduling in Supply
Chain Planning
calculations.
Add MPS Firm Planned Orders
An order for an MPS Planned item can be modified or added in the Planner
Workbench.
Master Schedule at Any Level
You can master schedule items that exist at any level of the bill of material. The master
production schedule then operates separately from the material requirements plan,
although it might include demand for items that are also parents of MPS items.
Similarly, the MRP plan may also include both MPS planned and MRP planned items.
Project and Seiban References
If you are working in a project-based or Seiban environment, you can include
project/Seiban and task references to your schedule entries. These references will
accompany and drive the material planning process. See: Defining Schedule Entries
Manually
Loading the Master Schedule from Multiple Sources
You can derive the master schedule from a forecast, another master schedule, source
lists, or directly from sales orders. You can define your master schedule or modify
entries loaded from other sources.
Supply Chain Planning users can also load DRP planned orders. See: Loading the
Supply Chain Master Schedule from Multiple Sources
When you derive your master schedule from an existing schedule, you can modify your
master schedule quantities using a modification percentage or you can shift master
schedule dates by specifying a number of carry forward days.
Interorganization Orders
You can load planned order demand from a requesting organization into the master
demand schedule of the supplying organization. Supply Chain Planning users can run a
sequence of MRP processes for organizations to produce valid multi-organizational
material plans.
Supply Chain Planning users can define multiorganization replenishment strategies
with sourcing rules and bills of distribution. See: Sourcing Rules and Bills of
Distribution
valid workday.
Schedule Management
You can monitor your master demand schedule as customer shipments occur by
utilizing the MDS relief process.
You can maintain credible priorities or schedule dates and update your master
production schedule either manually or automatically through the MPS relief process.
You can report and implement the MPS by exception, only for those items that require
attention.
Various reports and inquiries are available to give you detailed information on your
master schedule status.
Automatic MPS Relief
You can automatically maintain your master production schedule with the auto-reduce
MPS attribute you specify for the item in the item master in Oracle Inventory. For each
item, you can specify a point in time after which you no longer want the item to appear
on the MPS. This point in time can be the demand time fence, the planning time fence,
or the current date depending on your business practices.
Master Scheduling by Demand Class
You can optionally associate a demand class to a master demand schedule or master
production schedule when you define the master schedule name. When you ship a sales
order or create a discrete job, that sales order or discrete job relieves the master
schedules that are associated with the demand class of the sales order or discrete job.
You can load a subset of the sales orders into your master schedule for a specific
demand class.
See also Overview of Capacity Planning, Oracle Capacity User's Guide
you are unsure of the lowest level that an MPS part exists, use the
default value. The explosion process explodes through the entire bill of
material. See: Defining Bills of Material Parameters, Oracle Bills of
Material User's Guide.
2.
3.
4.
In the MPS window check Inventory ATP. You can optionally include your MPS
plan as available supply when you calculate available to promise information in
Oracle Inventory.
2.
In the MPS window, check Feedback to monitor the quantity of the planned order
that has been implemented as discrete jobs, purchase orders, or purchase
requisitions. This provides the planner visibility of the status of the plan at any
point in time.
3.
1.
2.
1.
2.
3.
4.
2.
3.
Choose Items to open the Master Demand Schedule Items or Master Production
Schedule Items window.
You can choose the Folder menu to customize your display. See: Customizing the
Presentation of Data in a Folder, Oracle Applications User's Guide.
4.
Enter an item with an MRP planning method of MPS Planning. See: Defining Items:
Oracle Inventory User's Guide
5.
Enter a different MPS explosion level, if you want to change the default. See: MPS
Explosion Level
6.
Choose Detail to open the Master Demand Schedule Entries window or Master
Production Schedule Entries window.
7.
Enter a date.
For MDS, this is the date of shipment. For an MPS, this is the completion date of
production.
For repetitive items, whether MDS or MPS, this is the start date of production
8.
9.
10. If you are working in a project environment, enter a valid project and task
reference.
Note: Your ability to enter project and task references is determined
Note: The Unit Number. field is visible if you have enabled Oracle
11. Check Reliefs if you want this entry to be decremented when you create purchase
orders, purchase requisitions or discrete jobs - whether you define the purchase
requisitions or jobs manually or load them with the Planner Workbench.
12. Save your work.
See Also
Schedule Relief
Source Flag
2.
Load/Copy/Merge MDS
Copy/Merge MPS
Load MPS
3.
4.
5.
6.
7.
8.
Select from a number of load options. See: Selecting Master Schedule Load Options
9.
specific forecast
source lists
Loading a master schedule in Supply Chain Planning involves extra steps. See: Loading
a Supply Chain MPS from and Internal Source
Specific Forecast:
When you load a master schedule from a forecast, Oracle MRP includes forecast entries
as follows:
From
To
Cutoff date
The load converts forecast entries for repetitive items into repetitive entries in the
master schedule - even if the original forecast entry does not have a forecast end date.
Master demand and production schedule entries for repetitive items must fall on valid
workdays.
For example, Org 1 is the requesting organization. Org 1 considers the workstation an
MRP-planned item, internally replenished by Org 2. Org 2 manufactures the
workstation, where it is an MPS-planned item. The manufactured workstation includes
a monitor that Org 2 receives from Org 3.
To produce a valid multi-organization material plan, you:
load the master demand schedule for Org 2 with inter-organization planned orders
from Org 1
load the master demand schedule for Org 3 with inter-organization planned orders
from Org 2; this drives the planning process for Org 3
picture of demand. The load master schedule process does not pick up
any demand for sales orders that you place more recently than the last
execution of the planning manager.
This feature is most useful to copy an existing schedule and modify the copy. You can
apply a modification percent to the new schedule and/or move schedule entries forward
or backward by a specific number of days.
Modification Percent
To increase the quantity of the new schedule, specify a percent by which to multiply the
schedule entries. Oracle MRP adds the result of the multiplication to the existing
quantities. To decrease the new schedule, enter a negative percent.
For example, to increase an existing schedule entry of 100 by 10 percent, specify a
modification percent of 10. The resulting schedule entry is 110. To decrease an existing
schedule entry of 100 by 10 percent, enter a modification percent of -10. The resulting
schedule entry is 90.
Carry Forward Days
To move schedule entries forward in time, specify a number of workdays. To move
schedule entries backward, enter a negative number. Holidays are not recognized as
workdays; the previous valid workday is used instead.
For example, the existing schedule contains an entry of 100 on Monday. Wednesday is a
holiday. The following Saturday and Sunday are not workdays. If you wish to move the
schedule entry to the next Monday, specify four carry forward days.
Source Lists
consolidate master schedules, plans, and forecasts from multiple organizations into
a single source
All sales orders: Include sales orders past due, up to the cutoff date.
Sales orders from start date forward: Include sales orders up to the cutoff date.
Overwrite
Overwrite To overwrite the existing entries of the destination schedule, select: All
entries: Erase all existing master schedule entries associated with the master schedule
name and load new entries.
For example, if you load master schedules MS-A and MS-B into master schedule MS-C
the first time and then load master schedule MS-B into master schedule MS-C the
second time, the result is that MS-C contains master schedules from the second load of
MS-B.
Same source only: Erase only the entries with a source that has been previously loaded
into the master schedule. This allows you to update master schedule information with
the latest picture of the sales orders, updated forecasts or master schedules.
For example, if you load master schedules MS-A and MS-B into master schedule MS-C
the first time and then load master schedule MS-B into master schedule MS-C the
second time, the result is that MS-C contains master schedules from the first load of
MS-A and the second load of MS-B.
Or, if you load sales orders into master schedule MS-C the first time and then load sales
orders again using this option. Master schedule MS-C reflects all the current sales
orders including those booked in the interim of the first and second loads.
To add new entries to the destination schedule, select:
No: This loads new entries, but does not erase existing master schedule entries.
Start Date
Select the start date of your schedule.
If you specify a start date Oracle MRP first selects the planning BOM entries that start
outside the start date, then explodes those entries. When you load a forecast into an
MDS, the master schedule load inserts all the forecast entries after the start date minus
backward update consumption days for the forecast set. The start date does not apply
to exploded entries that fall before start date due lead time offsetting from planning
BOM entries that start after the forecast load start date.
Cutoff Date
Select the cutoff date of your schedule.
When you load a forecast into an MDS, the master schedule load inserts all the forecast
entries prior to the cutoff date and adds forward update consumptions days for the
forecast set.
Explode
Select Yes to explode the schedule entries, down to the MPS explosion level. See MPS
Explosion Level.
Quantity Type:
To load forecast quantities, select:
Current: This loads the original forecast quantity minus any consumption quantities.
When you choose this option, you cannot choose to consume the forecast, since the
forecast quantities have already subtracted sales order demand.
Original: This loads the forecast without any consumption. When you choose this
option, you should choose to consume the forecast if you intend to load the master
schedule using forecasts and sales orders. Consuming the original forecast ensures that
orders and forecasts during the same load process, rather then loading
them in two separate steps. If you load them separately, and you create
sales orders in the interim, you could overstate or understate demand.
For example, suppose you define a forecast entry for 100 on 01-FEB and
load it into the master schedule. You create a sales order for 30 on
01-FEB. The forecast is consumed to 70, but the master schedule
remains at 100. You then load sales orders as a separate step. The total
demand for 01-FEB becomes 130, which overstates the actual and
forecasted demand. If you launched a single process instead of two,
you would see a forecast of 100 and no sales order demand, or a
forecast of 70 and a sales order for 30. Either way, the correct demand
of 100 results
Consume
Modification Percent
Enter a percent by which to multiple the schedule entries.
Carry Forward Days
Enter a number of workdays to move the schedule forward in time. To move the
schedule backward, enter a negative number.
Note: When you specify carry forward days, the start date and cutoff
if the source dates do not fall on a valid workday, Oracle MRP adjusts them to a
previous valid workday.
When loading a forecast or master schedule from another organization where the
workday calendar is different, the load process ensures that the schedule dates
match the workday calendar of the destination organization.
When loading a forecast or master schedule from another organization and the item
planning method is different (for example, repetitive vs. discrete) the load process
converts the schedule quantities accordingly.
When loading a forecast or master schedule from another organization and the item
unit of measure is different, the load process converts the unit of measure from the
source organization to the unit of measure of the item at the destination
organization.
Source Flag
Oracle MRP stores the source of each master schedule entry. This allows you to later
trace the source of master schedule entries.
Note: If you manually update a master schedule entry in the item
Forecast Date
Forecast Quantity
Days
04-Jan
100
Weeks
17-Jan
200
Periods
31-Jan
400
Quantity
Daily Quantity
04-Jan
100
17-Jan
200
31-Jan
400
When you load a forecast entry with an end date into the master schedule, the schedule
entry consists of a schedule date and quantity. If the forecast is bucketed into days,
there is a schedule entry for each day between the forecast date and the forecast end
date. If the forecast entry is in weekly or periodic buckets, the schedule date is the first
day of either the weekly or periodic bucket.
For example:
Forecast for Discrete Item
Bucket
Forecast Date
Forecast Quantity
Days
04-Jan
06-Jan
100
Weeks
17-Jan
24-Jan
200
Periods
31-Jan
28-Feb
400
Quantity
Daily Quantity
04-Jan
100
05-Jan
100
06-Jan
200
17-Jan
200
Schedule Date
Quantity
Daily Quantity
24-Jan
200
31-Jan
400
28-Feb
400
Forecast Date
Forecast Quantity
Days
04-Jan
100
Weeks
17-Jan
200
Periods
31-Jan
400
Quantity
Daily Quantity
04-Jan
04-Jan.
100.
17-Jan
21-Jan.
40 (assuming 5
workdays)
Schedule Date
Quantity
Daily Quantity
31-Jan
26-Feb.
20 (assuming 20
workdays)
When you load a forecast entry with an end date into the master schedule for a
repetitively planned item, the schedule entry consists of a schedule date, a rate end
date, and a daily quantity. If the forecast is in daily buckets, the schedule date is the
same as the forecast date, and the rate end date is the same as the forecast end date. The
forecasted quantity becomes the daily quantity. If the forecast is in weekly or periodic
buckets, the schedule date is the first day of the week or period, and the schedule end
date is the end of that week or period. The daily quantity is what was forecast for that
week or period divided by the number of days in that time frame.
For example:
Forecast for Repetitive Item
Bucket
Forecast Date
Forecast Quantity
Days
04-Jan
06-Jan
100
Weeks
17-Jan
24-Jan
200
Periods
31-Jan
28-Feb
400
Quantity
Daily Quantity
04-Jan
04-Jan.
100.
17-Jan
21-Jan.
40 (assuming 5
workdays)
24-Jan
28-Jan
40
31-Jan
26-Feb.
20 (assuming 20
workdays)
Schedule Date
Quantity
Daily Quantity
28-Feb
26-Mar
20
If you specify rounding control for an item, the load process does round up any
fractional quantities. The load process considers any additional quantity calculated due
to rounding as excess when calculating future time buckets.
For example:
Forecast for Repetitive Item with Rounding
Bucket
Forecast Date
Forecast Quantity
Days
08-Feb
11-Feb
100
Weeks
14-Feb
11-Mar
518
Quantity
Daily Quantity
08-Feb
11-Feb
100.
14-Feb
18-Feb
104
21-Feb
25-Feb
104
28-Feb
04-Mar
103
07-Mar
11-Mar
104
Note the period from 28-FEB through 04-MAR only requires 103 a day since the
previous periods spanning 14-FEB through 25-FEB are overestimates due to rounding.
The planning method appropriate for spares demand may be MPS planning or MRP
planning. Use MPS planning if the item has spares demand and still requires personal
control. The MPS planning process plans the spares demand, and you can manually
adjust the quantities/dates of the resulting master schedule entries before you use the
master schedule for your material requirements plan.
To manually include spares demand in the master schedule:
Follow the procedure for defining a master schedule manually. See: Defining Schedule
Entries Manually.
To forecast spares demand and load results into the master schedule:
Follow the procedure for loading a master schedule from a forecast. See: Loading a
Master Schedule From an Internal Source.
Schedule Relief
Shipment Relief
Oracle MRP relieves (updates) MDS schedule quantities when you ship sales order
items. Shipment (MDS) relief prevents the duplication of demand that could result if
you load sales orders into the master demand schedule, but do not relieve the master
demand schedule upon shipment. Without relief, you would need to reload and replan
your master schedule just before planning material requirements each time to obtain an
accurate picture of supply and demand for your independent demand items.
Shipping a sales order item relieves each MDS name for which you set the check Relieve.
You set shipment relief when you define the master schedule name before you define or
load a schedule for that name. If you associate a demand class with your MDS, the
shipment relief process relieves the MDS entries that correspond to the demand class
associated with the sales order.
You can change the shipment relief option after initially creating your master schedule.
If you change the shipment relief on an MDS from On to Off, shipment relief stops
occurring against that master schedule. If you change the shipment relief option from
Off to On, shipment relief occurs on that master schedule from the date you change the
option onward.
For repetitive master demand schedule items, the Planning Manager begins at the start
date of the schedule rate and relieves the schedule entry by eliminating days according
to the rate. For example, suppose you have a master demand schedule with a daily
quantity of 10 per day over 5 days, beginning on Monday. You ship a sales order with a
quantity of 12. The planning manager consumes the first day of the rate, accounting for
10 out of 12 shipped units. For the remaining 2 units, the planning manager creates a
new schedule entry beginning and ending on Tuesday, with a daily quantity of 8 (10
minus 2). The planning manager then resets the start date of the first schedule entry
from Monday to Wednesday, and maintains the daily quantity of 10 per day.
Production Relief
Oracle MRP relieves (updates) MPS schedule quantities when you create purchase
orders, purchase requisitions or discrete jobs - whether you define the purchase
requisitions or jobs manually or load them with the Planner Workbench.
Production (MPS) relief prevents the duplication of supply. Without relief, you would
need to replan your master schedule just before planning material requirements each
time to obtain an accurate picture of supply and demand for your MPS planned items.
Creating a purchase order, purchase requisition, or discrete job relieves each MPS name
for which you check Relieve. You set production relief when you define the master
schedule name - before you enter or load a schedule for that name. If you associate a
demand class with your MPS, the production relief process relieves the MPS entries that
correspond to the demand class associated with the discrete job.
You can change the production relief option after initially creating your master
schedule. If you set or unset the production relief on an MPS name, production relief
stops occurring against that master schedule. If you change the production relief option
from Off to On, production relief occurs on that master schedule from the date you
change the option onward.
Oracle MRP also updates the MPS schedule quantities when you reschedule discrete
jobs, or when you change discrete job, purchase order, or purchase requisition
quantities.
Note: Oracle MRP does not consume MPS entries for repetitive items.
MDS Reliefs or MPS Reliefs window. The original schedule quantity shows you the
quantity before schedule relief. The current schedule quantity is the relieved schedule
quantity. The difference between the original and current quantity is the sum of all
relief activity against the master schedule entry.
To compare this picture of your master schedule with previous or future versions, you
can copy your master schedule periodically (by using the Load/Copy/Merge Master
Schedule window) and store the copy for later comparison. Use the Schedule
Comparison report to compare the different schedules.
For example, suppose you have MDS entries of 10 each on Monday, Tuesday, and
Wednesday. If you ship a sales order for 25 on Tuesday, the relief process deducts 10 on
Tuesday (leaving 0), deducts 10 on Monday (leaving 0), and deducts the remaining 5 on
Wednesday (leaving 5). Thus, the new master schedule entries are quantity 0, 0, and 5
on Monday, Tuesday, and Wednesday, respectively.
For production relief, the Planning Manager first looks at the discrete job due date to
find an MPS schedule entry to relieve. It then looks backward, up to the first schedule
entry, and then forward until it finds enough schedule quantity to relieve.
For example, suppose you have MPS entries of 10 each on Monday, Tuesday, and
Wednesday and you specify the MRP: MPS Relief Direction profile option as
Backward, then forward. If you create a discrete job for 25 on Tuesday, the relief
process deducts 10 on Tuesday (leaving 0), deducts 10 on Monday (leaving 0), and
deducts the remaining 5 on Wednesday (leaving 5). Thus, the new master schedule
entries are quantity 0, 0, and 5 on Monday, Tuesday, and Wednesday, respectively.
Note: When it operates, the Planning Manager may run for a very short
See Also
Starting the Planning Manager
2.
3.
4.
Click the Reliefs button to see the order quantity and relief quantity for each order.
See Also
Production Planning
See Also
4
Material Requirements Planning
Bills of material
Scheduled receipts
Lead times
Order modifiers
repetitive build rates, with first and last unit start dates
Oracle MRP assumes infinite capacity is available to meet the material requirements
plan. However, you can use capacity planning to verify that sufficient capacity exists to
support your material plan.
Supply Chain Planning users can also generate distribution requirements plans (DRP)
and manage their material requirements across multiple, interdependent organizations.
See: Material and Distribution Requirements Planning.
Note: The planning products support Oracle Project Manufacturing's
end item model/unit effectivity. The Unit Number field is visible if this
featured is enabled allowing you to do the following tasks:
Load sales orders into a MDS, and have the specified unit number
carried over to the schedule entry.
See Also
Overview of Planning Logic, Overview of Capacity Planning, Oracle Capacity User's
Guide Model/Unit Effectivity, Oracle Project Manufacturing Implementation Manual
bills of material
lead times
order modifiers
The purpose of the planning process is to derive an MPS, DRP or MRP that meets
schedule dates while maintaining inventory levels within your "material" policies.
You can validate a material plan against available capacity using rough cut capacity
planning (RCCP) or detailed capacity requirements planning (CRP).
You can create multiple MPSs, MRPs or DRPs for simulation purposes and for testing
different business scenarios. If you use the Memory-based Planning Engine, you can
simulate changes to any MPS or MRP.
Supply Chain planning logic is further described in Overview of Supply Chain
Planning Logic.
See Also
Overview of Material Requirements Planning
Overview of Supply Chain Planning Logic
Supply Chain Planning Methods
Inventory. Items that are considered by the planning process must have one of the
following MRP planning methods:
MPS Planning
MRP Planning
Oracle Supply Chain Planning users can define three additional attributes (See: Supply
Chain Planning Methods):
DRP Planning
MPS Planning
Select MPS planning for items that you want to master schedule and maintain personal
control. MPS planning is most effective for:
MRP Planning
If your demand is smooth or predictable, you may not require master production
scheduling. Select MRP Planning for these items and use the master demand schedule
to drive the material requirements plan.
Or, you can select MRP Planning for those items with dependent demand that you want
the planning process to plan and maintain. You can also select MRP Planning for those
items with independent demand that do not require personal control.
Suggestion: You can set the MRP planning method item attribute to MPS Planning so
that the long-term material requirements for an item are generated.
Inventory Planning Methods
In addition to an MRP planning method, you can use the following inventory planning
methods for an item:
Min-Max Planning Reorder Point Planning Min-Max Planning Select Min-max
planning to define a minimum quantity that you want on hand. When you reach this
quantity, you reorder. You also define a maximum on-hand quantity that you do not
want to exceed.Reorder Point Planning You may also want to set the Inventory
Planning Method item attribute to Reorder Point planning to facilitate automatic order
execution.
Refer to the topic Requesting the Reorder Point Planning Report, , in the Inventory
User's Guide.
See Also Defining Items, Oracle Inventory User's Guide
lead times
engineering changes
item information
It then calculates time-phased material requirements. Each item may have different
attributes that affect the recommendations generated by the planning process.
Supply Chain Planning users can also generate DRP and supply chain MRP and MPS
plans. Supply Chain Planning users should refer to Overview of Plan Generation in
Supply Chain Planning for further information.
MRP Generation
You can launch the planning process for an MRP plan from a master demand schedule
or a master production schedule. This generates planning recommendations for all
planned items.
Once you have generated an MRP plan, you can make a copy of the plan that is
identical to the original. You can then view, implement, and replan either copy,
discarding the altered plan at any time and preserving the original data.
From a Master Demand Schedule
If you do not need to smooth production or otherwise manually manipulate a master
production schedule, you can generate a plan directly from a master demand schedule.
The planning process overrides the MRP planning method and treats MPS planned
items as MRP planned items, DRP planned items, or DRP/MRP planned items. As a
result, the planning process generates planned orders and reschedules
recommendations for your MPS, MRP, and DRP planned items.
From a Master Production Schedule
You can also generate an MRP plan from a master production schedule. For each MPS
planned item, the planning process considers projected gross requirements, current
orders for the item, the master production schedule, and on-hand quantities over time.
The planning process calculates the projected quantity on hand and generates exception
messages to signal any potential imbalances in the material plan. By default, the
planning process generates firmed planned orders for MPS planned items.
Note: A warning message displays informing you when releasing MPS
See Also
2.
3.
Check Feedback to monitor the quantity of the planned order that has been
implemented as discrete jobs, purchase orders, or purchase requisitions. This
provides the planner visibility of the status of the plan at any point in time.
4.
5.
Enter an inactive on date on which to disable the plan. As of this date, you can no
longer update the plan, nor use the plan name in the planning process. You are still
able to view information and run reports for disabled names.
6.
Purchasing, you've set up logical orgs for P.O. receipts. Do not use
these logical orgs for planning purposes.
Supply Chain Planning users can also launch a DRP and supply chain MRP and MPS
plan. Supply Chain Planning users should refer to Launching the Supply Chain
Planning Process for further instruction.
Prerequisites
Before you can launch the planning process, you must:
For MPS or MRP: define at least one master demand schedule or master production
schedule. See: Defining a Schedule Name.
Define at least one master production schedule and create at least one MRP name.
See: Defining MRP Names.
2.
Snapshot.
Anchor Date: Enter a date, earlier or equal to the current date, that will act as a start
date for repetitive planning periods.
Plan Horizon: Enter a date, greater than the current date, up to which the planning
process creates an MRP or MPS. The default horizon is the current date plus the
number of offset months set in the profile MRP:Cutoff Date Offset Months.
Note: You may want to enter a date earlier than the default to save
3.
Choose OK.
4.
Define an MPS, MRP, or DRP name and run a plan under that name. This will be
Define a plan name of the same type as your source plan (MPS, MRP, DRP). This
will be your destination plan.
Restrictions
The source and destination plans must be the same type. For instance, you cannot
copy an MRP source plan into an MPS destination plan.
The same organization must own both source and destination plans.
You must log into the same organization that owns the source and destination
plans.
The responsibility of the user that generated the source plan must be the same as
the user that defined the destination plan. For instance, a source plan generated by
a user with material planner responsibilities cannot be copied into a destination
plan defined by a user with supply chain planner responsibilities.
The production and feedback flags, and all plan options are copied from the source
to the destination plan. Any flags or options you set will be overwritten during the
copy process.
2.
In the Parameters window, select a source plan name and a destination plan name.
Note: If you see the error message, No entries found for List of Values,
3.
Choose OK.
4.
the first time, the plan options you defined in the setup parameters are
displayed. Otherwise, the plan options you chose for the last launch of
the planning process are displayed.
Supply Chain Planning users can also launch a DRP and supply chain MRP and MPS
plan. Supply Chain Planning users should refer to Reviewing or Adding Supply Chain
Plan Options.
2.
3.
Outside planning time fence: For an MPS plan, overwrite all MPS entries outside the
planning time fence.
For an MRP, overwrite all planned orders and firm planned orders outside the
planning time fence.
Note: Be very cautious when using this option since it overwrites
MRP firm planned orders and master schedule entries outside the
planning time fence. If you do not want to overwrite MRP firm
None: Do not overwrite any firm planned orders for MPS or MRP plans and net
change replan.
4.
Check Append Planned Orders to append new planned orders in the following
situations:
If the MPS plan name has an existing schedule associated with it and you enter
None as the overwrite option, the planning process does not recommend
rescheduling or suggest new planned orders before the end of the existing MPS (the
last planned order) even if so indicated by new demand from the master demand
schedule. This is analogous to firming your master production schedule. By not
overwriting, the master scheduler is taking responsibility for manually planning
items. For an MRP plan name, this option creates planned orders where needed,
considering existing MRP firm planned orders.
Note: If you want to add firm planned orders using net change
If the plan name has an existing MPS or MRP associated with it and you enter All as
the overwrite option, the planning process deletes all previous planned entries and
creates new planned orders based on the source master schedule.
If the plan name has an existing MPS or MRP associated with it and you enter
Outside planning time fence as the overwrite option, the planning process deletes all
planned entries after the planning time fence and creates new planned orders after
that date. In this case, since you are overwriting after the planning time fence, you
are also appending new planned orders after that date.
If the plan name has an existing MPS or MRP associated with it and you enter None
as the overwrite option and do not check this, the planning process reports the
instances where the plan is out of balance with the source master schedule. It does
not recommend any new orders. Instead it lets you manually solve any problems in
the process. This gives maximum control to the master scheduler and/or material
planner.
5.
Check Demand Time Fence Control to indicate whether the planning process
considers any demand from forecasts within the demand time fence.
The planning process does not consider demand from forecasts within the demand
time fence, but considers demand from sales orders.
6.
Check Net WIP to indicate whether the planning process considers standard
discrete jobs, non-standard discrete jobs, or repetitive schedules when planning
items during the last plan execution.
7.
Check Net Reservations to indicate whether the planning process considers stock
designated for a specific order when planning the items during the last execution of
the plan.
8.
Check Snapshot Lock Tables to indicate whether tables are locked during the
snapshot process to guarantee consistent data.
This option temporarily prevents other users from processing certain transactions.
9.
Check Planning Time Fence Control to indicate whether the planning process
violates planning time fences for items.
For discrete items, the planning process does not create planned orders or
recommend to reschedule in existing orders within the planning time fence of the
item. The planning process can still recommend to reschedule orders out.
For repetitive items, the planning process can vary the suggested schedule from the
optimal schedule, within the planning time fence, by the acceptable rate increase
and/or decrease you specified for the item.
Note: For purchase requisitions and internal requisitions, the
10. Check Net Purchases to indicate whether the planning process considers approved
purchase requisitions when planning the items during the last execution of the plan
11. Check Plan Safety Stock to indicate whether the planning process calculates safety
Graphical Pegging. The planning process then traces supply information for an item
to its corresponding end demand details, which you then can view in a graphical
display.
15. If you are working in a project environment, set a Reservation Level and
(optionally) a Hard Pegging Level. See: Reviewing or Adding Project MRP Plan
Options.
16. Select a Material Scheduling Method:
Operation start date: Schedule material to arrive in inventory for availability on the
start date of a specific operation in the manufacturing process.
Order start date: Schedule material to arrive in inventory for availability on the work
in process order start date.
17. Specify which planned items or components you want included:
All planned items: Include all planned items in the planning process. You would
chose this option to be certain that all item are planned, such as those you add to a
job or schedule that are not components on any bill.
Note: You may want to plan using this option to avoid missing
items you want to plan. For items you do not want to plan, define
them with an MRP planning method of Not planned when you
define an item in Oracle Inventory.
Demand schedule items only Supply schedule items only Demand
and supply schedule items
See Also
Planner Status:
Planner Workbench
Order Modifier
Order sizing is a set of item attributes that allow you to control the recommended order
quantities for planned orders. The planning process creates planned orders using basic
lot-for-lot sizing logic.
Note: The planning process ignores order modifiers for items that have
Lot-for-Lot
Lot-for-lot generates planned orders in quantities equal to the net requirements for each
day. To modify the lot size recommended by the planning process, you can use several
different order modifiers.
Your company may have order policies for dependent demand items that differ from
the lot-for-lot order sizing technique. You can express your company's order policies for
these items using order modifiers. Order modifiers regulate the size and timing of
planned orders, both discrete (quantity) and repetitive (rate).
For a given inventory item, you can establish order quantities as fixed or variable.
Fixed order quantity fixes the size of the order, but the time interval between orders
depends on actual demand.
Variable order quantity policies include: fixed lot multiple, minimum and maximum
order quantity, and fixed days supply.
Fixed Order Quantity
The planning process places one or more orders for the user-defined quantity or
repetitive rate.
For discretely planned items, when the requirement for a given date exceeds the
fixed order quantity, place multiple orders.
For repetitively planned items, either recommend a rate equal to the fixed order
quantity or a rate of zero.
You can define, for each inventory item, whether the planning process should round
order quantities when the actual order quantity is calculated as a fraction. If you choose
to round, order quantities are rounded to the next highest whole number.
Note: By rounding up, the planning process may suggest a planned
order for more than what is actually needed. This extra quantity is
carried over into the next period as supply; therefore, the planning
engine rounds other orders down to account for the excess supply from
the last period.
See Also
Defining Items, Oracle Inventory User's Guide
Manufactured or Purchased
Three item attributes are evaluated to determine if planned orders are generated and
implemented into discrete jobs, repetitive schedules, or purchase requisitions.
Supply Chain Planning users can supplement and refine this behavior with sourcing
rules and bills of distribution. See: Sourcing Rules and Bills of Distribution
Make or Buy
This item attribute determines how the item is planned. The planning process looks at
the Make or Buy item attribute to determine whether to generate component
requirements. The attribute can have a value of Make or Buy and is directly related to
the Build in WIP and Purchasable item attributes.
When implementing orders via the Planner Workbench, the make or buy attribute is
used as the default for the type of planned order you can implement, either purchased
or manufactured.
Build in WIP
Build in WIP
Purchasable
Planning Recommendation
Make
Yes
No
Make
Yes
Yes
Buy
No
Yes
Buy
Yes
Yes
Bulk Items
Bulk items are those you issue in bulk to work in process, to cover a period of time, or
to fill a fixed size container. Normally, you do not issue these items to specific discrete
jobs, flow schedules, or repetitive schedules.
You might designate an item as Bulk for many reasons. Perhaps it is not cost effective to
transact these items for each individual job or schedule. Or, a bulk item might be easier
to manage if you place a large quantity in a central floor stock location.
For example, bulk items might be nuts, bolts, and other hardware used in the
manufacturing process. You issue quantities of 10,000, for instance, to a floor stock
location using the account issue transaction provided by Oracle Inventory. Work in
process obtains the hardware from floor stock when needed. By making this hardware
available in floor stock, and not pushing or pulling it to each job or schedule, you can
save the cost of performing additional transactions.
The planning process creates planned demand for bulk items by exploding their usage
on a bill of material. It creates recommendations to replenish bulk material based on
these demands and considering any on-hand inventory for the item. Note that when
you issue the material to the floor stock location, it is no longer seen as available supply.
During the planning cycle, the need for bulk items according to the material plan rise
and fall based on the timing of issues from nettable subinventories to the expense
account.
Suggestion: Designate a general ledger expense account as Floor stock. Periodically
issue large quantities of bulk items to this account.
Shrinkage Rate
For a particular inventory item, you can define a shrinkage rate to describe expected
scrap or other loss. Using this factor, the planning process creates additional demand
for shrinkage requirements for the item to compensate for the loss and maintain supply.
For example, if you have a demand of 100 and a discrete job for 60, the planning process
would suggest a planned order for 40 to meet the net requirements, assuming no
shrinkage rate exists.
With a shrinkage rate of .2 (20%), Oracle MRP assumes you lose 20% of any current
discrete jobs and 20% of any suggested planned orders. In this example, since you have
a discrete job for 60, assume you lose 20% of that discrete job, or 60 times 20%, or 12
units. The net supply from the discrete job is 48. Since you have a total demand of 100
and supply of 48, you have a net requirement of 52 units. Instead of suggesting a
planned order for 52, the planning process has to consider that 20% of that planned
order is also lost to shrinkage.
The planning process creates additional demand called shrinkage demand to create an
increased suggested planned order to provide for the lost supply. The planning process
inflates the planned order of 52 by dividing 52 by (1 - .2) = 65.
inflated planner order = demand / (1 - shrinkage rate)
shrinkage demand = [demand / (1 - shrinkage rate)] x
shrinkage rate
With the a shrinkage rate of .2, the planning process would result in:
total demand = original demand +
Component Yield
Component yield is the percentage of a component on a bill of material that survives
the manufacturing process. A yield factor of 0.90 indicates that only 90% of the usage
quantity of the component on the bill actually survives to be incorporated into the
finished assembly.
To account for the loss, the planning process inflates the demand quantities for the
component (similar in concept to shrink factor). To increase demand, the usage quantity
is divided by the yield factor.
For example, when you define the component usage quantity as 2 and the component
yield as 0.90, the usage is recalculated as 2 divided by 0.90, or 2.22.
new component usage = usage / yield factor
The difference between a shrink rate and component yield is that Oracle MRP applies
the same shrink rate to every use of an item on a bill, whereas you can vary the
component yield factor you assign to each occurrence of an item on a bill. Another
difference is that shrinkage demand is calculated at the parent assembly level and
passed down to components. Component yield is calculated at the component level.
Safety Stock
Safety stock is a quantity of stock you plan to remain in inventory to protect against
fluctuations in demand or supply. Safety stock is sometimes referred to as
overplanning, forecast, or a market hedge. In the context of master scheduling, safety
stock refers to additional inventory planned as protection against forecast errors or
short term changes in the backlog. You can specify safety stock days together with
safety stock percent as item attributes in Oracle Inventory.
You establish the default use of safety stock calculation when you define your planning
parameters. You can override this option for individual material plans when you
generate an MRP or MPS using the Launch window. See: Defining Planning Parameters
Lot Expirations
For items under lot control, you can define the shelf life of lots that controls when the
lot expires. The planning process tracks lots and their expiration dates. If the expiration
date for a lot occurs before the lot is used to satisfy gross requirements, the unused
portion of the lot as expired is considered. An expired lot gross requirement is created
to offset any remaining portion of the expired inventory lot.
For example, the following item has a quantity on hand of 300 that consists of 3 lots of
100 each, due to expire on days 5, 10, and 15 respectively. The item has gross
requirements of 150 on day 4 and 50 on day 12. The plan would look as follows:
Lot Expiration MRP Plan
Beginning QOH =
300
Demand Type
Quantity
Projected QOH
Day 4
Gross requirement
150
150
Day 10
Lot expiration
50
100
Day 12
Gross requirement
50
50
Only 50 units from the second inventory lot were used before they were due to expire
on Day 10. Therefore, a gross requirement with a type of lot expiration to offset the
quantity of the inventory lot that is projected to expire is created.
See Also
Creating a Bill of Material, Oracle Bills of Material User's Guide Defining Items, Oracle
Inventory User's Guide
current date of an order is Day 2. If the planning process determines that the actual due
date should be Day 3 or Day 4, the planning process does not suggest rescheduling of
the order. Oracle MRP suggests rescheduling only when the new need date is Day 5 or
later.
Note: Acceptable early days delivery only has an effect
On orders that are due to arrive earlier than they are needed. Oracle MRP always
generates a reschedule in message if an order is scheduled to arrive later than it is
required.
Although the planning process may suggest rescheduling some scheduled receipts and
may not suggest rescheduling others because of the acceptable early days limit, it does
not violate the order of the current scheduled receipts. In other words, if one scheduled
receipt is not rescheduled (because it falls within the acceptable early days delivery)
and the planning process wants to suggest rescheduling another scheduled receipt out
past the first scheduled receipt, Oracle MRP does not suggest rescheduling either.
For example, if the material plan for an item looks as follows:
Material Plan
Day 2
Day 3
Day 4
Day 5
Day 6
Day 7
Gross Requirements
100
100
Scheduled Receipts
100
100
You can determine whether to consider the time fence when planning a material plan or
a master schedule if you select Yes for Demand or Planning Time Fence Control on the
Plan Options window, or (for the Release Time Fence) if you check Production on the
DRP, MPS or MRP Names window. If you are using either the planning, demand, or
release time fence, the planning process looks at the item attributes for each item in the
Master Item window to determine the selected time fence for each item. The three time
fences are calculated by adding one of the following to the plan date (or the next valid
workday, if the plan was run on an invalid workday): total lead time, cumulative
manufacturing lead time, cumulative total lead time or a user-defined time fence.
For discrete items, you can recommend that an order be rescheduled out or cancelled,
but cannot recommend reschedule in messages or create new planned orders within the
planning time fence for an item. For repetitive items, you can limit the changes Oracle
MRP can recommend within the planning time fence by the acceptable rate increase or
decrease.
The planning time fence does not apply to purchase requisitions or internal requisitions.
If you specify demand time fence control when launching the planning process, the
planning process only considers actual demand within the demand time fence specified
for an item (such as forecasted demand is not considered).
must be for standard items (the planning process will not automatically release
models, option classes, and planning items)
DRP items in a DRP plan, MPS planned items in an MPS plan, or MRP planned
items in an MRP plan See: Implementing Planned Orders.
the release time fence option is defined as anything other than Do not auto-release,
Do not release (Kanban), or Null
Auto-release for WIP jobs is not applicable for repetitively planned items. No material
availability check is performed before WIP jobs are released.
See Also
Repetitive Planning
Define an employee, associate a user name to the employee entry, and associate the
employee to the application user. See Entering a New Person: Oracle Human
Resources.
Define a planner or planning entity and associate this planner with items you want
controlled by the auto-release function. See Defining Planners and Defining Items:
Oracle Inventory User's Guide.
Supply Chain Planning users must define a material planner, supply chain planner
or planning entity for the current organization and assign them to inventory items
at the organization level. See: Updating Organization Items, Oracle Inventory User's
Guide and General Planning Attribute Group, Oracle Inventory User's Guide.
Define Default Job Status and Job Class values for a user on the Planner Workbench
Preferences window. These settings are in the Supply/Demand region and are used
as defaults in the process of automatically releasing planned orders.
In addition, the planned orders must meet the following auto-release criteria:
the new start date lies within the auto-release time fence
the orders are for standard items (will not release models, option classes, and
planning items)
the orders are for DRP planned items in a DRP plan, MPS planned items in an MPS
plan, or MRP planned items in an MRP plan See: .Implementing Planned Orders.
the release time fence option is defined as anything other than Do not auto-release,
Do not release (Kanban), or Null
2.
3.
Check Feedback to monitor the quantity of the planned order that has been
implemented as discrete jobs, flow schedules, purchase orders, or purchase
requisitions.
This provides the planner visibility of the status of the plan at any point in time.
4.
5.
6.
past due - the due date of the order is moved to the plan date.
See Also
Profile Options
Overwrite Options
Overwrite When you launch the planning process, you generate new planned orders
and suggested repetitive schedules to meet your net requirements. Since you can firm a
DRP, MPS, or MRP planned order, you may not want the planning process to overwrite
any firm planned orders. You can use the Overwrite and Append plan level options to
limit how the planning process reacts to firm planned orders and to stabilize the short
term material plan.
When you enter All in the Overwrite field, the planning process overwrites all entries,
planned and firm planned, from the current material plan.
When you enter None in the Overwrite field, the planning process does not overwrite
any firm planned orders. It does, however, overwrite any suggested planned orders
that are not firm.
When you enter Outside planning time fence in the Overwrite field, the planning process
overwrites all entries from the current plan, planned and firm planned, outside the
planning time fence, and overwrites only planned orders inside the planning time
fence. It does not overwrite any firm planned orders within the planning time fence.
The planning time fence can be different for each item, so the planning process looks at
the planning time fence for each item when choosing what to delete.
Append Planned Orders
When you enter No in the Append Planned Orders field, the planning process does not
append any planned orders to the current plan. Additional demand does not cause
planned order recommendations. Instead, the projected quantity on hand may go
negative in response to demand that was not met by a suggested planned order.
When you enter Yes in the Append Planned Orders field, the planning process appends
additional planned orders after the last entry on the current material plan to meet any
additional demand.
The overwrite and append options work in combinations, as described below.
Overwrite All, Append Planned Orders
This option allows you to create a new material requirements plan for the plan name
you specify, deleting all previous planned and firm planned entries while regenerating
new planned orders. You can use this combination the first time you run your plan or if
Quantity
Order Status
01-FEB
100
Planned
08-FEB
200
15-FEB
300
Planned
And the following MDS is used to plan the material plan using All in the Overwrite
field and Yes in the Append Planned Orders field:
MDS Schedule
Schedule Date
Quantity
02-FEB
110
09-FEB
220
16-FEB
330
Quantity
Order Status
02-FEB
110
Planned
09-FEB
220
Planned
16-FEB
330
Planned
The planning process always suggests planned orders. You can change planned orders to
a firm status using the Items window in the Planner Workbench.
For example, if an existing MRP has the following orders for an item:
MRP Plan
Schedule Date
Quantity
Order Status
01-FEB
100
Planned
08-FEB
200
15-FEB
300
Planned
And the following MDS is used to plan the MRP using Outside Planning Time Fence
in the Overwrite field and Yes in the Append Planned Orders field:
MDS Schedule
Schedule Date
Quantity
02-FEB
110
09-FEB
220
16-FEB
330
Then the resulting material plan would have the following suggestions for planned
orders, assuming the planning time fence is 05-FEB:
Quantity
Order Status
05-FEB
110
Planned
09-FEB
220
Planned
16-FEB
330
Planned
Since the entry on 01-FEB is not firmed, the MRP planning process overwrites this
entry. If it was firmed, the process would not overwrite the entry. The additional
demand from the MDS of 110 on 02-FEB was appended on the planning time fence date
of 05-FEB. The MRP firm planned order on 08-FEB was deleted because it falls outside
the planning time fence of 05-FEB.
The planning process always suggests planned orders. You can change planned orders to
a MRP firm status using the Items window in the Planner Workbench.
Quantity
Order Status
01-FEB
100
Planned
08-FEB
200
15-FEB
300
Planned
And the following MDS is used to plan the MRP using None in the Overwrite field and
Yes in the Append Planned Orders field:
MDS Schedule
Schedule Date
Quantity
02-FEB
110
09-FEB
220
16-FEB
330
Quantity
Order Status
05-FEB
110
Planned
08-FEB
200
09-FEB
20
Planned
16-FEB
330
Planned
The firm order on 08-FEB remains on the MRP since the overwrite is None. However,
the planned entries are deleted. Although additional demand exists on the MDS, no
planned orders are suggested until the planning time fence (on 05-FEB). The MDS
demand of 110 on 02-FEB was satisfied by a new planned order for 110 on 05-FEB. The
demand for 220 on 09-FEB was partially met by the firm MRP planned order on 08-FEB.
Thus an additional planned order was suggested on 09-FEB for 20 to meet the MDS
demand of 220. A suggested planned order was created on 16-FEB for 330 to meet the
demand from the MDS on 16-FEB.
MRP Plan
Schedule Date
Quantity
Order Status
01-FEB
100
Planned
08-FEB
200
15-FEB
300
Planned
And the following MDS is used to plan the MRP using None in the Overwrite field and
No in the Append Planned Orders field:
MDS Schedule
Schedule Date
Quantity
02-FEB
110
09-FEB
220
16-FEB
330
Quantity
Order Status
08-Feb
200
The reason the additional demand from 02-FEB, 09-FEB, and 16-FEB was not planned
for is because with the Overwrite None and Do Not Append Planned Orders, you choose
not to overwrite firm planned orders nor create new planned orders to meet additional
demand. In this case, the projected quantity on hand would go negative since no
planned orders were suggested to meet the additional demand. The material planner
can use on-line inquiries and reports with exception messages to identify material
shortages.
Time-Phasing Requirements
See Also
Overview of Gross to Net Explosion
snapshot phase
planner phase
auto-release
calculates low-level codes and checks for loops in your bill of material structures
captures sourcing rules, bills of distribution, and master demand schedules for
supply chain planning
Planner Phase
The planner phase:
performs the gross-to-net explosion, calculating net requirements from gross
requirements, using on-hand inventory and scheduled receipts, exploding the
requirements down through the bill of material
suggests the rescheduling of existing orders and the planning of new orders based on
the net requirements
calculates the resource requirements for supply orders Note: This step is performed if
Capacity Plan is enabled.
Auto-Release Phase
The auto-release phase:
releases planned orders for items whose order date falls within their release time fence
Note: This step is performed for plans that have the Production flag
See Also
Planner
Snapshot
Available to Promise
Time-Phasing Requirements
The planning process time-phases material requirements and expresses future demand,
supply, and inventories by time period. Time-phasing delays release of orders for
components until they are needed and offsets the requirements by item lead time (lead
time offset). Oracle MRP plans to the exact date of demand, although some reports and
inquiries show requirements bucketed by weeks or months.
If you execute the planning process on a non-valid workday, the planning process
considers the next valid workday as the day the plan is generated.
For example, if you execute the planning process on a Saturday, the planning process
would generate planned orders at the earliest for the following Monday.
Past Due Supply and Demand
The planning process considers past due supply and demand as if it were due today (in
other words, the start date of the plan). Reports and on-line inquiries that bucket
demand in weeks or periods show past due demand in the first bucket.
Material Scheduling Method
The material scheduling method controls how the planning process calculates the exact
date of demand: the start date of the operation generating the demand, or the start date
of the order generating the demand.
For each material requirement, the planning process schedules material to arrive in
inventory on the day that corresponds to the method you choose. This affects
time-phasing of requirements for discrete jobs, flow schedules, repetitive schedules and
planned orders. See: Material Scheduling Method Example.
Lead Time Percent
Lead time percent is used when you choose a material scheduling method of Operation
start date when launching the planning process.
For a particular operation, the lead time percent is the percent of total lead time from
the start of the first operation on the routing to the start of the current operation.
For example, if the lead time of the assembly equals 10 days and this operation starts
after 2 days (on day 3) the lead time percent is 20%.
Oracle Bills of Material calculates lead time percent values when you calculate
manufacturing lead times.
Oracle MRP uses the lead time percent to schedule material requirements at a
particular operation.
Oracle Capacity uses the lead time percentage to plan capacity requirements at a
particular operation.
for planned orders generated by Oracle MRP. Dynamic lead times are more accurate
than fixed lead times because lead time can vary based on order quantity.
Lead time for planned orders is computed as:
planned order lead time = fixed lead time + (order quantity x variable leadtime)
See Also
Item Lead Time Attributes, Oracle Bills of Material User's Guide Manufacturing Lead
Time Computation, Oracle Bills of Material User's Guide
Overview of Lead Time Management, Oracle Bills of Material User's Guide Dynamic
Lead Time Offsetting, Oracle Bills of Material User's Guide
2.
Select one of the following options from the Planned Items poplist:
All planned items Demand schedule items only
Supply schedule items only
Demand and supply schedule items only
Suggestion: It is recommended that you use the All planned items option, to avoid
missing items you want to plan and to guarantee that all sources of demand are
considered by the planning process. Under certain circumstances, including
demand schedule item components or supply schedule item components only may
mean that not all demand for an item appears in the material plan. For items you do
not want to plan, assign an MRP Planning Method item attribute of Not planned
when you define an item in Oracle Inventory.
3.
2.
Check Net Purchases, Net WIP, and Net Reservations to net supply and demand for
these items.
3.
To net Subinventories
1.
Navigate to the Subinventory Netting window from the Plan Options window.
2.
Check Net to indicate that you want to net supply and demand for these
subinventories.
Note: You assign a netting type when you define a subinventory in
3.
Net Purchases
Net Reservations
Net Purchases
When you choose to net purchases, the planning process considers approved purchase
requisitions and approved purchase orders as scheduled receipts (supply). If you do not
choose to net purchases, the planning process ignores this purchasing information.
Note: This option may be useful when performing simulations to see
the impact on the material plan if scheduled purchase receipts are not
available as supply.
The planning process ignores unapproved purchase requisitions, but plans using
approved requisitions and both approved and unapproved purchase orders as valid
scheduled receipts.
Note: The planning process only nets purchase requisitions and
Planning Dates
Oracle Purchasing requires a promised-by date or need-by date on a purchase order for
planned items. If only one of these dates is defined, the planning process considers the
date specified (either the promised-by date or need-by date) to be the dock date for the
purchase order. If you have defined both dates on the purchase order, the planning
process considers the promised-by date to be the dock date when calculating order
dates.
Purchase requisitions and purchase orders are planned based on several key dates:
Promised-by DateOn a purchase order, this is the date the supplier promises to deliver.
Need-by date:On a purchase requisition and purchase order, this is the internal date of
need.
Dock date vs.order due date: If the promised-by date exists, the planning process
designates it as the dock date (the date you expect the order to arrive on the receiving
dock). Otherwise, the need-by date is the dock date. To the dock date, the planning
process adds post-processing lead time to arrive at the order planning date: the date
that the planning process plans the supply as available for use.
Internal Requisitions
The planning process plans internally sourced requisitions in the same manner as it
plans externally sourced requisitions. Oracle MRP recommends that you set up a
separate Planner Code and associate it to your internally sourced items. This lets you
manage your planned internal requisitions by requesting key reports and windows
using the Planner Code associated to your internally sourced items.
See Also
Net Reservations
Unreleased
Released
Complete
On hold
Note: If a job is released and firmed, and the component requirement is
past due - the due date of the order is moved to the plan date.
Repetitive Schedules
Since Oracle MRP uses different planning algorithms for repetitive manufacturing,
repetitive schedule statuses do not impact how repetitive schedule supplies and
demands are viewed.
MRP Net Quantity
MRP Net Component
Assembly supplies and component demands from non-standard discrete jobs with
the following statuses are included:
Unreleased
Released
Complete
Hold
Since a non-standard discrete job is created manually and does not explode a bill of
material, it does not automatically create material requirements. However, you can
manually create material requirements with the WIP Material Transactions window.
Oracle MRP recognizes only these requirements.
Note: The planning process does not recommend rescheduling of
In Oracle Work in Process, you can specify an MRP net quantity for the standard and
non-standard discrete jobs. The net quantity may differ from the job quantity for many
reasons.
For example, you would set the net quantity to zero if you receive the discrete job
quantity into a non-nettable completion subinventory.
When you choose to net WIP, the planning process uses the MRP net quantity on the
order header to calculate available supply. See: Defining Discrete Jobs Manually, Oracle
Work in Process User's Guide.
At the component level, you can enter a value for the MRP Net field to establish if the
planning process should net the requirement when calculating component demand.
You may choose to enter No for a particular component if it is issued from a
non-nettable subinventory.
When you choose to net WIP, the planning process uses the MRP net value at the
component level to determine if the component requirement is included as demand.
Supplier Components
Negative Requirements
If you specify a WIP supply type of supplier for an item or component, the planning
process ignores the requirement.
You can define negative usages for component items on a bill of material in Oracle Bills
of Material. You can add negative requirements (byproducts) to discrete jobs using
Oracle Work in Process. See: By-Product Recovery, Oracle Work in Process User's Guide.
Oracle MRP includes negative requirements on standard and non-standard discrete jobs
and components with a negative usage on a bill of material when netting supply and
demand. This type of component requirement is considered as supply available on the
job completion date. The MRP Net field on the Discrete Jobs window, in Oracle Work in
Process, must have a value in order for negative requirements to be treated as supply.
Note: You can manually add a negative requirement to a non-standard
See Also
Net Purchase
Net Reservations
Net Reservations
When you choose to net reservations, the planning process recognizes hard reservations
that represent sales order demand. If you do not choose to net reservations, the
planning process recognizes all sales order demand as soft reservations only. The
planning process always plans to satisfy hard reservations before soft reservations.
Note: By definition, sales order demand is a soft reservation. A hard
See Also
change orders when the start date of the planned order is later than the
effective date. Oracle MRP does not suggest a planned order using an
ECO if the planned order needs to start before the effective date of the
ECO.
For a pending ECO, you can specify whether to include the engineering changes during
the planning process. Set the MRP Active Flag to Yes in the Engineering Change Order
window if you want the planning process to consider the engineering changes on the
ECO.
Oracle MRP considers engineering changes when generating component requirements
for planned orders and suggested repetitive schedules. The quantity specified by an
engineering change order is considered if the scheduled effective date of the ECO is
before the suggested start date of the order.
For example, if you have defined the following bill of material:
Assembly A has a lead time of 2 days. Component B has a usage of 2. You defined an
engineering change order that changes the usage of B to 3. The ECO has a scheduled
effective date of Day 4. If the material plan for Assembly A is:
Material Plan for Assembly A
Day 2
Day 3
Day 4
Day 5
Day 6
Day 7
Gross Requirements
100
100
100
100
Planned Orders
100
100
100
100
The planned orders for Assembly A with due dates of Day 4 and Day 5 have start days
of Day 2 and Day 3 respectively when offset by the lead time of 2 days. Since neither
planned order has a start date that is on or after the scheduled effective date of the
engineering change order, the component requirements are generated based on the
current bill of material that specifies a usage of 2 Bs.
The planned orders for Assembly A with due dates of Day 6 and Day 7 have start dates
of Day 4 and Day 5 respectively when offset by the lead time of 2 days. Since both
planned orders have a start date that is on or after the scheduled effective date of the
engineering change order, the component requirements are generated based on the
revised usage of 3 Bs.
The material plan for component B is:
Day 3
Day 4
Day 5
Day 6
Day 7
Gross Requirements
200
200
300
300
Planned Orders
200
200
300
300
See Also
Use-Up Date
The use-up date determines when the current on-hand quantity for an item is exhausted
based on projected gross requirements. This date is calculated for all items during the
planning process. The use-up date is calculated by applying on-hand quantity in
inventory (supply) against any gross requirements (demand), and adding the next work
date to the day it is depleted. The planning process does not consider repetitive
schedules as supply when calculating the use-up date. It does consider schedule
receipts if the profile option, MRP:Include Scheduled Receipts in Use-up Calculation, is
set to yes.
For example, if the material plan for an item is as follows:
Material Plan for Item
Beginning QOH = 600
Day 2
Day 3
Day 4
Day 5
Day 6
Gross Requirements
200
200
300
300
Oracle MRP calculates, based on the projected gross requirements for this item, that the
current quantity on hand is exhausted on Day 4. Therefore, the planning process sets
the use-up date for this item to be Day 5.
When you define a revised item for an ECO, you can specify whether the planning
process should recommend a suggested effective date for the revised item. If you
indicate that the planning process should calculate the suggested effective date, you
also specify a use-up item. Oracle MRP recommends a suggested effective date based
on the use-up date of the use-up item.
For example, you may want to change how you build an assembly. You manufacture a
board, that has Chip A as a component:
You have decided to change the Assembly Board to use a new and improved Chip B
instead of Chip A.
You define an ECO with the Board assembly as the revised item. You specify Chip A as
a revised component with a usage quantity of 0, and Chip B as a revised component
with a usage quantity of 1. You'd like to use up the Chip A's you have in stock before
beginning to use the Chip B's. Therefore, you would define the ECO as use-up and set
the use-up item to be Chip A. Oracle MRP suggests an effective date based on the
use-up date of Chip A.
Note: While Oracle MRP calculates the use-up date as the basis for
suggesting an effective date for the ECO, the planning process uses the
current effective date instead of the suggested effective date when
generating component requirements. The only case where Oracle MRP
considers the suggested effective date of the ECO when generating
component demand is when the use-up item is the assembly (in our
example, the Board assembly) instead of one of the components.
See Also
5
Supply Chain Planning
Overview
Oracle Supply Chain Planning is a powerful tool that integrates manufacturing and
distribution into a single planning process. With Oracle Supply Chain Planning, you
can generate plans that include the entire supply chain. In a single step you can
schedule and plan material and distribution requirements for multiple organizations, or
centrally plan the entire enterprise. You can also include customer and supplier
inventories in the supply chain planning process.
Oracle Supply Chain Planning lets you plan finished products, as well as intermediate
assemblies and purchased items, for all facilities in your supply chain. Material plans
for feeder plants and distribution centers automatically consider requirements
originating from any number of other facilities. You can load planned order demand
from multiple using-organizations into the master schedule of supplying organizations.
In addition to planning the material requirements of your supply chain, you can plan
the requirements for your distribution network. This includes all warehouses,
distribution centers, and any location that ships products. You can use these
distribution requirements plans (DRPs) as input for your material plans.
You can combine centralized distribution and material planning, for items with
significant interorganization supply or demand, with decentralized planning, where
you prefer autonomous, local planning. Output from the central plan can go into plant
level material plans and vice versa.
Oracle Supply Chain Planning gives you a transparent view of the virtual enterprise,
where all inventory locations participate in the planning process.
Note: All help on Supply Chain Planning assumes a knowledge of MRP
and will refer users to MRP topics when they compliment Supply
Chain functionality
Use a graphical pegging display to directly identify the end customer orders
affected by shortages of items at any level in the supply chain
Consider supply and demand from customer and supplier inventories in plans
Use supply statements from many organizations in your overall supply chain
View exception messages for a consolidated supply chain material plan See:
Reviewing Planning Exceptions
Simulate and replan changes (e.g., quantity and date) to supply and demand
records See: Replanning Net Changes
Review updated exception messages to verify that your simulated changes resolve
supply or demand problems
Analyze supply and demand records across multiple organizations in the Supply
Chain Planner Workbench
See Also
The disadvantage is that this model requires at least two planning runs, as each
organization plans its own specific requirements. It also requires significant human
intervention to ensure that information generated by one organization is passed to the
other. If, for instance, SAC wanted to replenish its workstations from an additional
organization (NYC), SAC would have to maintain a separate set of plans, and manually
coordinate the supply coming from both.
Oracle Supply Chain Planning makes it possible to support a much more diverse and
flexible enterprise. Demand for an item may be met through one or more networks of
replenishment organizations. These organizations may be geographically remote,
clustered into interdependent groups, but remain semiautonomous within the
enterprise; they may also be members of a supplier's or customer's enterprise.
In the supply chain model, SAC produces final assemblies, which it distributes through
SFD and NYD. SAC is replenished by AUS, which supplies one purchased component
and one assembled component.
The advantage is that all this planning occurs with a single planning run, with
attendant gains in runtime and consistency. Requirements of different organizations are
planned transparently and seamlessly. You no longer need to load interorg planned
orders separately. The enterprise-wide distribution requirements have been
incorporated into the planning process. Sourcing strategies, formerly controlled
manually by a planner implementing planned orders, can now be automatically
assigned to the correct source, whether that is an internal organization or a supplier.
Oracle Supply Chain Planning also allows you to expand your planning capability as
your enterprise expands. SAC can easily incorporate NYC and Supplier 3 into the
global plan.
See Also
For each organization controlled by the plan, the planning engine loads firm
planned orders, supply and demand schedules, and sourcing information. Planned
order demand from one organization automatically and immediately appears in the
schedules of the supplying organization. The controlling plan can combine the
demand from multiple organizations, make rescheduling recommendations, and
generate exception messages on their behalf.
The netting process nets supply and demand for all items in your schedules, for all
organizations in your plan. In addition to creating and rescheduling planned
orders, the netting process assigns sources to the planned orders and generates
dependent demand. You can assign multiple sources to an item or category of
items, with split percentages, and these assignments can be phased in and out over
time.
DRP plans include intransit lead times when creating timephased demand and
create the corresponding demand in the shipping organization.
Demand Schedules
Demand schedules in Supply Chain Planning includes the master demand schedules,
and by extension all valid sources of demand. See: Master Schedule Typesfor a list of
valid sources.
Supply Schedules
Supply schedules can include MPS/MRP/DRP plans. If you include one of these supply
schedules in your supply chain plan, firm planned orders (along with orders for their
components) from the supply schedule will be treated as supply in the plan. Material
plans generated by the controlling organization can produce net requirements for all
organizations controlled by the plan. Distribution plans include distribution
requirements for all included items across multiple organizations. Included items can
be DRP planned, DRP/MPS planned, or DRP/MRP planned.
See Also
See Also
With supplier planned inventories you can integrate external supplier and customer
inventory information with that of manufacturing and distribution organizations. Such
information gives you an overall picture of the supply chain, including advanced
warning of stock outs, abnormal swings in demand, and capacity problems.
Once you model customers and suppliers as organizations, all relevant supply/demand
information for an item can be exchanged between your enterprise and supplier or
customer organizations. You can also net supply and demand of external organizations,
covert material needs of consuming organizations into demand at the replenishing
organization, and maintain capacity information (for the supplier organization).
Prerequisites
To model customers as organizations
1.
Define a customer name. See: Entering Customers, Oracle Receivables User's Guide.
2.
3.
Define a supplier name. See: Entering Suppliers, Oracle Payables User's Guide.
2.
3.
organizations
See Also
of distribution both describe sourcing supply; i.e., for any organization, they answer the
question "where do I get part A from?". (They never say "where do I send part A to".)
Sourcing rules apply the answer to one organization or all the organizations in your
enterprise. Bills of distribution define this behavior across multiple organizations (not
just one or all).
See Also
Sourcing rules and BODs both describe sourcing supply; in other words, for any
organization, they answer the question Where do I get part A? (They never ask Where
do I send part A?) Sourcing rules apply the answer to one organization or all the
organizations in your enterprise. BODs define this behavior across multiple
Tolerance fences
Sourcing Rules
Sourcing rules define inventory replenishment methods for either a single organization
or all organizations in your enterprise. Time-phasing in a sourcing rule determines
when each group of shipping method - ship org combinations is in effect, as in this
example:
In the first phase of SR-C01, SAC is replenished equally by AUS and NYC. From
01-JUL-1997, AUS no longer supplies SAC, which receives all transfers from NYC:
(mrp_suprulex.if)
This sourcing rule can apply to one org (SAC, in this example), or to all your
organizations. However, you cannot choose a single organization in one phase and all
organizations in another phase. That would require two sourcing rules, with
consecutive effectivity dates. If you assign the sourcing rule to one receiving
organization (SAC in this example), it is a local sourcing rule; if you assign it to multiple
organizations, it is a global sourcing rule.
You cannot apply sourcing rules and bills of distribution (make them Planning Active)
until the sum of the allocation percentages equals 100. Secondly, sourcing rules and bills
of distribution do not take effect until they are assigned to a part or a range of parts.
(See: Assigning Sourcing Rules and Bills of Distribution.)
Bills of Distribution
Bills of distribution define the sourcing strategies of several organizations. In other
words, a bill of distribution is library of sourcing strategies. For instance, the sourcing
strategy described in SRC01 could apply to different organizations at different periods.
You cannot do this with sourcing rules because you have to apply the strategy to one
organization or all organizations.
In another example, an item is made in a manufacturing center and supplied to a
distribution center, which in turn supplies three sales offices. Instead of using five
different local sourcing rules, you could set up a three-level replenishment hierarchy
with a bill of distribution for the item. This bill would specify how the item is sourced at
each level.
Both sourcing rules and bills of distribution have effective dates, periods during which
the scheme is valid. For each period, you can specify a list of sources, type, allocation
percentage, rank, shipping method, and intransit time.
You cannot apply sourcing rules and bills of distribution (make them Planning Active)
until the sum of the allocation percentages equals 100. Secondly, sourcing rules and bills
of distribution do not take effect until they are assigned to a part or a range of parts.
(See: Assigning Sourcing Rules and Bills of Distribution.)
Example - Sourcing Rule/Bills of Distribution
In the following scenario, distribution centers SFD and NYD receive finished goods
from manufacturing plan SAC:
Sourcing rule SR-C02 describes the replenishment of SFD by SAC. Since no other plants
supply the part (which is assigned to this rule separately), the allocation is 100%.
SR-C02 is a local sourcing rule because it applies to SFD only. Similarly, SR-C03
describes the replenishment of NYD by SAC.
The bill of distribution (BRE01 in this example) can define a specific set of receiving
organizations, and for each organization it can define any number of shipping
organizations - each with its own allocation percentage, ranking, and shipping method.
Bills of distribution are more flexible than sourcing rules because, for each organization
you list in the bill, you define a range of dates and a sourcing strategy to apply within
those dates. Sourcing rules can only define the dates and strategy for one organization
or all the organizations in your enterprise.
The following scenario illustrates this flexibility:
As the demand from NYD expands and exceeds SAC's capacity to meet the demand,
the enterprise decides to build a new plant, called NYC. While NYC is brought online,
SAC continues to meet 100% of demand from NYD. From 1-JUL, however, NYC begins
to supply a small percentage of this demand, taking some of the burden away from
SAC. The planning process can quickly and easily support this transition. Sourcing rule
SR-C04 can define the dates during which the transition will occur, include NYC, and
split the demand replenishment between it and SAC. Bill of distribution BR-E01 can
accomplish this as well, but the bill can incorporate it into an enterprisewide sourcing
strategy.
Organization-to-organization sourcing
Watch for conflicts between sourcing rules for external demands and sourcing rules for
internal demands. For example:
If you assign a sourcing rule for external demand at the item level, then you cannot
assign a sourcing rule for internal demand at that level.
Ship methods apply to Buy from and Transfer from sourcing rules. To create the ship
methods:
2.
3.
Indicate whether this sourcing rule is used for all organizations (global) or a single
organization (local). If the sourcing rule is local, you must enter an organization
name; otherwise, your current organization will be the receiving organization.
4.
Choose Copy From to copy the effectivity dates and shipping organization from
another sourcing rule into this one.
5.
Enter effectivity dates. You must enter a start date, but entering an end date is
optional.
6.
For each range of effectivity dates, you can include multiple shipping organizations.
For each shipping organization you want to include, select a sourcing type to
specify whether you make, buy, or internally transfer the item. You can also copy a
list of shipping organizations from an existing sourcing rule. If you enter a
customer organization as the receiving organization, then you cannot select a
supplier organization as the shipping organization.
7.
8.
Enter a numeric rank value to prioritize each sourcing type. If you have two sources
with the same allocation percentage, planned orders are sourced from the highest
rank first.
9.
Select a shipping method, such as FEDEX, UPS, or rail. (See: Defining Shipping
Methods, Oracle Inventory User's Guide.
Select a sourcing type to specify whether you make, buy, or internally transfer the
item.
2.
3.
In the Find window, select a sourcing rule that includes the shipping organizations
you want to duplicate in this new sourcing rule.
4.
Choose OK.
2.
Choose Purge.
2.
3.
If the allocation percentage for this bill of distribution equals 100, Planning Active is
greater than 100 for sourcing rules that are already assigned in
assignment sets
4.
Choose Copy From to copy the receiving and shipping organization information
from another bill of distribution into this one.
5.
Enter the effectivity dates for each receiving organization in this bill of distribution.
6.
For each receiving organization, you can enter a number of shipping organizations.
For each shipping organization, select a sourcing type to specify whether you make,
buy, or internally transfer the item. You can also copy a list of shipping
organizations from an existing bill of distribution.
Note: Suppliers and supplier sites must be predefined in Oracle
7.
sets, you cannot set the allocation percentage to less than or greater
than 10
8.
Enter a numeric rank value to prioritize each sourcing type. If you have two sources
with the same allocation percentage, planned orders are sourced in rank order.
9.
Select a shipping method, such as FEDEX, UPS, or rail. See: Defining Shipping
Methods, Oracle Inventory User's Guide.
Select a sourcing type to specify whether you make, buy, or internally transfer the
item.
2.
3.
In the Find window, select a bill of distribution that includes the shipping
organizations you want to duplicate in this new bill of distribution.
4.
Choose OK.
2.
Choose Purge.
Item-Instance: An item across all organizations. If the Item field is empty, use the
Reduce Criteria Window to restrict the selection.
These levels allow you to assign a replenishment rule to as many or as few items as
possible. For example, a category of items could be defined as packaging material, and a
sourcing rule that identifies the suppliers could be assigned.
When you specify a customer in an assignment:
The planning engine does not split planned orders by customer. If you want the
planning engine to split planned orders by customer, use project manufacturing.
Create one project per customer so all of the sales orders for each customer peg to
one project.
To assign a sourcing rule or bill of distribution
1.
2.
3.
4.
5.
Enter the name of the customer to which you want to assign a sourcing rule or bill
of distribution.
6.
Enter the specific site to which you want to assign a sourcing rule or bill of
distribution.
7.
8.
9.
10. Enter Condition if the source is Repair at or Transfer fromfective and usable items
2.
Choose Purge.
Assignments Hierarchy
In the following table, rows below override rows above them. Columns on the right
override columns on the left.
A global sourcing rule has an unspecified receiving organization.
Sourcing Rules vs. Bill of Distribution Assignments
Assignment Scope
Global Sourcing
Rule*
Local Sourcing
Rule
Bill of
Distribution
Global
Yes
No
Yes
Organization
No
Yes
No
Category of Item
Yes
No
Yes
Category of Items in an
Organization
No
Yes
No
Item
Yes
No
Yes
Items in an Organization
No
Yes
No
Since not all assignment types are valid for both sourcing rules and bills of distribution,
the effect of the Sourcing Rules vs. Bill of Distribution Assignments table is illustrated in
a linear hierarchy in the following table. The rows below override rows above them.
Assignment to Levels
Assignment Scope
Sourcing Mechanism
Global
Global
Bill of Distribution
Organization
Category of Item
Assignment Scope
Sourcing Mechanism
Category of Item
Bill of Distribution
Category of Items
in an Organization
Item
Item
Bill of Distribution
Items in an Organization
2.
Place your cursor in the Name or Description field and select Find or Find All from
the query menu.
3.
Choose View to launch the Object Navigator and display the graphical view of your
sourcing rule.
With the Object Navigator, you can display your sourcing rule in a visual hierarchy.
Each element in the sourcing rule is displayed in a rectangular node, with
connecting lines that depict the nodes' relationships to each another (known as the
data flow). The nodes are also color-coded for easy identification, and other aspects
of the data flow can be changed to meet specific requirements.
2.
Place your cursor in the Name or Description field and select Find or Find All from
the Query menu.
3.
Choose Assignment Set. The list that appears includes all sets in which the current
rule participates.
For each Sourcing Rule and Bill of Distribution in the Assignment Set, you can review
the following information:
A category of items
Customer and Customer Site: Rules or bills associated with a customer will also
display this information.
2.
Place your cursor in the Name or Description field and select Find or Find All from
the Query menu.
3.
Choose View to launch the Object Navigator and display the graphical view of your
bill of distribution.
With the Object Navigator, you can display your bill of distribution in a visual
hierarchy. Each element in the bill is displayed in a rectangular node, with
connecting lines that depict the nodes' relationships to each another (known as the
data flow). The nodes are also colorcoded for easy identification, and other aspects
of the data flow can be changed to meet specific requirements.
2.
Place your cursor in the Name or Description field and select Find or Find All from
the Query menu.
3.
Choose Assignment Set. The list that appears includes all sets in which the current
bill participates.
For each Sourcing Rule and Bill of Distribution in the Assignment Set, you can review
the following information:
A category of items
Customer and Customer Site: Rules or bills associated with a customer will also
display this information.
2.
Place your cursor in the Assignment Set or Description field and select Find or Find
All from the Query menu.
3.
For each Sourcing Rule and Bill of Distribution in the Assignment Set, you can review
the following information:
A category of items
In the Assignments region, place your cursor in any field on the row containing the
rule or bill you want.
2.
2.
3.
Enter an organization.
4.
5.
Choose View Indented Where Used to launch the Object Navigator and display the
graphical view of item's indented where used information.
With the Object Navigator, you can display your data in a visual hierarchy. Each
element in the sourcing rule is displayed in a rectangular node, with connecting
lines that depict the nodes' relationships to each another (known as the data flow).
The nodes are also colorcoded for easy identification, and other aspects of the data
flow can be changed to meet specific requirements.
See Also
2.
3.
Enter an organization.
4.
5.
Choose View Indented Bill to launch the Object Navigator and display the
graphical view of item's indented where bill information.
With the Object Navigator, you can display your data in a visual hierarchy. Each
element in the sourcing rule is displayed in a rectangular node, with connecting
lines that depict the nodes' relationships to each another (known as the data flow).
The nodes are also color-coded for easy identification, and other aspects of the data
flow can be changed to meet specific requirements.
See Also
2.
3.
Enter an organization.
4.
5.
See Also
Bills of material
Sourcing rules
Scheduled receipts
Order modifiers
and will refer users to MRP topics when they compliment Supply
Chain functionality
See Also
Planning Organizations
Sourcing strategies
Bills of material
Scheduled receipts
Order modifiers
The purpose of the planning process is to derive an MPS, DRP or MRP that meets
schedule dates while maintaining inventory replenishment policies.
The netting process:
Assigns sources to the planned orders, according to rank and sourcing percentages
When assigning sources to planned orders (according to the percentage splits defined
by the sourcing rules and bills of distribution), planning begins with the organization
that is immediately below its shipping percentage target. See: Assigning Sourcing Rules
and Bills of Distribution and Assignments Hierarchy.
When generating dependent demand for an organization different from the one in the
planned order, planning creates demand for the same item in the other organization
and offsets the demand by the transportation lead time.
Sourcing Assignment Logic
Oracle Supply Chain Planning uses the following components in sourcing assignment
logic in order to allocate planned orders.
Alternate Sources
If the primary supplier does not have the capacity to meet demand, alternate suppliers
can be specified according to your priority. The supplier capacity defined in Oracle
Purchasing is used to determine if the primary source can fulfill the order. The ranking
order specified in in the rules and bills determines which sources can be used as
alternates.
Delivery Frequency Calendars
You can specify delivery dates for each supplier or supplier/item combinations and
create a schedule to define the dates an organization is able to receive items. The
planning engine adjusts planned orders so deliveries are scheduled for the dates the
receiving organization is available. You enter processing lead times in Oracle
Purchasing, and then choose a Delivery Calendar pattern. The Delivery Calendar is
independent of your workday calendar.
Historical Allocations
Planning recognizes the historical allocation assigned to each source, organization, or
supplier in recommending sources to new planned orders. Historical allocation includes
all requisitions, purchase orders, and receipts in the case of suppliers. And all discrete
jobs, repetitive schedules, flow schedules, and organization transfers in the case of
Make At organizations.
Rank and Allocation
You can define a rank for each source of supply named in the rules and bills, and then
define a sourcing percentage for each source within a rank. You can also assign
sourcing percentages to these sources allowing you to allocate a portion of the total
orders to each source.
Splitting Of Demand According To Sourcing Percentages
Demand can be divided and allocated to multiple sources according to target sourcing
percentages set in the rules and bills.
The data in these tables demonstrate how allocation percentages for planned orders are
divided according to ranking information.
The demand for Item A on the date of 06/10 is:
Demand
Due Date
Quantity
07/15
300
Item
Source
Rank
Percentage
Effective
From
Effective To
S1
40
05/15
12/31
S2
30
05/15
12/31
S3
30
05/15
12/31
Demand is assigned using the ranking information and calculating the percentages
assigned to each source to calculate the planned orders.
Three planned orders are created for the quantities of 120, 90, and 90 respectively.
Note: All planned orders generated in this process are subject to item
order modifiers
Order modifiers can be specified at the supplier site level, this overrides item level
order modifiers.
Tolerance Fence
You can define capacity tolerance percentages that can vary for each of your items. The
tolerance fence data in Oracle Purchasing is used to adjust production according to
capacity changes for item/supplier combinations when the order is placed. Tolerance
fence values can be specified for the capacity fluctuation allowed for available to
promise; and used to determine demand based on the amount of advanced notice given
to the supplier.
See Also
MPS planning
MRP planning
Oracle Supply Chain Planning users can define three additional attributes:
DRP planning
DRP Planning
Select DRP planning for items that appear in a distribution requirements plan.
MPS and DRP Planning
Select MPS and DRP planning for items that appear in DRP and MPS plans that are
primarily planned in MPS plans.
MRP and DRP Planning
Select MRP and DRP planning for items that appear in MRP and DRP plans, but are
planned in MRP plans.
Note: You can set the MRP Planning method item attribute to MPS and
2.
3.
4.
Check Feedback to monitor the quantity of the planned order that has been
implemented as discrete jobs, purchase orders, or purchase requisitions. This
provides the planner visibility of the status of the plan at any point in time.
5.
6.
Follow the standard procedure in Defining MRP Names to complete this task.
See Also
Planner Workbench
For MPS, MRP, or DRP: define at least one demand or supply schedule. See:
Defining a Schedule Name and Defining a Supply Chain Schedule Name.
Create at least one MPS, DRP, or MRP plan name. See: Defining MRP Names and
Defining MRP/DRP Names.
2.
3.
Follow the standard procedure in Launching the Planning Process to complete this
task.
See Also
the first time, the plan options you defined in the setup parameters are
displayed. Otherwise, the plan options you chose for the last launch of
the planning process are displayed. If you are launching a plan for
simulation purposes, do not check these plan options.
2.
3.
4.
All: For an MPS plan, overwrite all entries and regenerate new MPS entries
based on the source master demand schedule.
For an MRP or DRP, overwrite all planned orders and firm planned orders for
MRP or MRP/DRP items.
This option is displayed when you generate a plan for the first time.
Caution: Be very cautious when using this option since it
Outside planning time fence: For an MPS plan, overwrite all MPS entries outside
the planning time fence.
For an MRP or DRP, overwrite all planned orders and firm planned orders
outside the planning time fence.
Caution: Be very cautious when using this option since it
5.
None: Do not overwrite any firm planned orders for MPS, MRP, or DRP plans
and net change simulation.
Check Append Planned Orders to append new planned orders in the following
situations:
If the MPS plan name has an existing schedule associated with it and you enter
None as the overwrite option, the planning process does not recommend
rescheduling or suggest new planned orders before the end of the existing MPS (the
last planned order) - even if so indicated by new demand from the master demand
schedule. This is analogous to firming your master production schedule. By not
overwriting, the master scheduler is taking responsibility for manually planning
items. For an MRP plan name, this option creates planned orders where needed,
considering existing MRP firm planned orders.
Note: If you want to simulate the addition of new planned orders
using net change replan, set overwrite to Outside planning time fence
or None
If the plan name has an existing MPS, MRP, or DRP associated with it and you enter
All as the overwrite option, the planning process deletes all previous planned
entries and creates new planned orders based on the source master schedule.
If the plan name has an existing MPS, MRP, or DRP associated with it and you enter
Outside planning time fence as the overwrite option, the planning process deletes all
planned entries after the planning time fence and creates new planned orders after
that date. In this case, since you are overwriting after the planning time fence, you
are also appending new planned orders after that date.
If the plan name has an existing MPS, MRP, or DRP associated with it and you enter
None as the overwrite option and do not check this, the planning process reports the
instances where the plan is out of balance with the source master schedule. It does
not recommend any new orders. Instead it lets you manually solve any problems in
the process. This gives maximum control to the master scheduler and/or material
planner.
6.
Check Demand Time Fence Control to indicate whether the planning process
considers any demand from forecasts within the demand time fence.
The planning process does not consider any demand from forecasts within the
demand time fence, but considers demand from sales orders.
7.
Check Snapshot Lock Tables to indicate whether tables are locked during the
snapshot process to guarantee consistent data.
This option temporarily prevents other users from processing certain transactions.
8.
Check Planning Time Fence Control to indicate whether the planning process
violates planning time fences for items.
For discrete items, the planning process does not create planned orders or
recommend to reschedule in existing orders within the planning time fence of the
item. The planning process can still recommend to reschedule orders out.
For repetitive items, the planning process can vary the suggested schedule from the
optimal schedule, within the planning time fence, by the acceptable rate increase
and/or decrease you specified for the item.
9.
Check Plan Capacity to indicate whether you want to generate a capacity plan.
Graphical Pegging. The planning process then traces supply information for an item
to its corresponding end demand details, which you then can view in a
diagrammatic display.
11. If you are working in a project manufacturing environment, set a Reservation Level
and a Hard Pegging Level. This option supports functionality planned for a future
release.
Reservation Level: Set the level at which the planning process will reserve supply
against demand.
Planning Group: Reserve project - specific supply and demand at the planning
group level. Supply for one project can be reserved against demand from
another project, if both projects belong to the same planning group.
Project: Reserve supply for a project against demand from the same project.
Supply for one project-task can be reserved for demand for another project-task,
if both project-tasks belong to the same project.
Task: Reserve supply for a project-task against demand for the same
project-tasks only.
Hard Pegging Level: Set the granularity of planned orders in a project manufacturing
environment.
Project: Create planned orders at the project level. The planning process will
generate planned orders with a project reference and associate it to demand at
the project level.
None: Create soft-pegging information for the item. This option is valid only
when the item attribute is soft pegging or hard pegging.
Operation Start Date: Schedule material to arrive in inventory for availability on the
start date of a specific operation in the manufacturing process.
Order Start Date: Schedule material to arrive in inventory for availability on the
work in process order start date.
13. Specify which planned items or components you want included:
All Planned Items: Include all planned items in the planning process. You would
chose this option to be certain that all items are planned, such as those you add to a
job or schedule that are not components on any bill.
Note: You may want to plan using this option to avoid missing
items you want to plan. For items you do not want to plan, define
them with an MRP Planning Method of Not planned when you
define an item in Oracle Inventory
Demand schedule items only: Include all the items specified in your demand
schedule(s). You can specify more than one MDS per organization.
Supply schedule items only: Include the items with Firm Planned Orders within the
specified supply schedule(s) only. Supply schedules could be MPS (where all
planned orders are firmed automatically), DRP, or MRP schedules.
Supply and demand schedule items only: Include items from both the specified demand
schedule(s) and the Firmed Planned Orders from any specified supply schedule(s).
14. Save your work.
See Also
Planner Workbench
Defining Items, Oracle Inventory User's Guide Viewing Pegged Supply and Demand
Planning Organizations
Order modifiers
Sourcing strategy
Engineering changes
Item information
It then calculates time-phased material requirements. Each item may have different
attributes that affect the recommendations generated by the planning process.
Review Plan Generation for information on plan generation in Oracle MRP.
Specifying Items for the Supply Chain Planning Process
The items included the planning process depends on the planning method set for them
(in their item attributes) and on whether you allow the planning process to include
them. In Oracle MRP, you select the type of item subject to the planning process in the
Planning Parameters window. In Oracle Supply Chain Planning, you make this
selection in the Plan Options window.
You can include:
The planning process interprets these options differently, depending on the type of plan
you choose to run. The following table compares the effect of the Planned Items option
on an MPS, MRP, and a DRP:
DRP includes...
MPS includes...
MRP includes...
DRP planning
MRP and DRP
planning
MPS and DRP
planning
MRP planned and
MPS planned items
that are in between
the above items in the
bill structure. All
items in the input
schedules.
Include demand
schedule items
only
MPS planning
MPS and DRP planning
MRP planned and
MRP/DRP planned
items that are in
between the above
items in the bill
structure.
All items in the input
schedules.
MPS planning
MRP planning
Plan Option
DRP includes...
MPS includes...
MRP includes...
Include supply
schedule items
only
MPS planning
MRP planning
DRP planning
MRP planning
DRP planning
MRP and DRP
planning
MPS and DRP
planning
MRP planned and
MPS planned items
that are in between
the above items in the
bill structure.
Include demand
and supply
schedule items
only
Chain Planning also plans any MRP planned items that have an MPS planned
component. This ensures that all derived demand is correctly passed down.
See Also
Plan Option
Included Items
DRP
Include demand
schedule items only
Plan Type
Plan Option
Included Items
Include supply
schedule items only
Plan Option
Included Items
MRP
Plan Type
Plan Option
Included Items
Planning Organizations
Planning organizations allows you to set plan options specific to each organization, and
to specify different demand and supply schedules.
Note: If you're using the Drop Shipment feature of Order Entry and
Purchasing, you don't need to add the logical org used for P.O. receipts
to the plan
2.
3.
4.
5.
If you have chosen to plan capacity (in the Plan Options window), enter values for
the following fields:
Bill of Resource: See: Bills of Resources, Oracle Capacity User's Guide.
Simulation Set: See: Capacity Modifications and Simulation, Oracle Capacity User's
Guide.
6.
In the Demand Schedules region, enter an MDS for each organization you include.
7.
In the Supply Schedules region, enter an MPS, MRP, or DRP for each organization
you include.
2.
Check Net Purchases, Net WIP, and Net Reservations to net supply and demand for
each.
Net WIP: Consider standard discrete jobs, non-standard discrete jobs, repetitive
schedules, or flow schedules when planning the items during the last execution of
the plan.
Net Reservations: Consider stock designated for a specific order
when planning the items during the last execution of the plan.
Net Purchases: Consider approved purchase requisitions and approved purchase
orders when planning the items during the last execution of the plan.
3.
and organizations when you generate an MPS, MRP or DRP plan from
the Launch MPS, Launch MRP, or Launch DRP windows. Choose Plan
Organizations in the Launch MPS Launch MRP, or Launch DRP
window
To net subinventories
1.
2.
3.
For each item, check Net to indicate that you want to net supply and demand for
these subinventories.
4.
Check the unlabeled, coordination check box (next to the Type field) if you want to
constantly update the coordination of records between the Plan Options and
Subinventory Netting windows. See: Masterdetail Relationships.
See: Master-detail Relationships, Getting Started and Using Oracle Applications.
5.
See Also
Net Purchases
Net Reservations
View the horizontal netting information for an item in several different inventory
locations at once
Display inventory status summary for an item for each organization that carries the
item, including onhand quantities, open customer orders, reservations, open
replenishment orders, and quantities available to reserve
Display data generated at the snapshot (the last planning run) or data in its current
state (including all changes to the plan)
Generate a graphical view of the relationship between item supply and end
demand - at all levels of the bill of materials and at any number of facilities in the
distribution network
Generate a graphical view of the supply chain bill for an item in an organization,
showing all item/location combinations
If you are using supplier planned inventories, the following restrictions apply to
implementing planned orders:
and will refer users to MRP topics when they compliment Supply
Chain functionality
2.
3.
4.
2.
3.
4.
See Also
You use the schedules generated by master scheduling as input to other manufacturing
functions, such as material requirements planning, distribution requirements planning,
and rough-cut capacity planning.
Note: All help on Supply Chain Planning assumes a knowledge of MRP
and will refer users to MRP topics when they compliment Supply
Chain functionality
See Also
Loading a Supply Chain MPS from an Internal Source Material and Distribution
Requirements Planning
Item forecasts
Spares demand
Sales orders
Internal requisitions
New products
Navigate to the Master Production Schedules window (called MPS Names in the
navigator). Master demand schedules are always associated with a single
organization.
2.
3.
4.
5.
Optionally, select Yes in the flexfield to enable the Memory-based Planning Engine.
Note: You must use the Memorybased Planning Engine to use
6.
Follow the standard procedure in Defining a Schedule Name: to complete this task.
See Also
Navigate to the Master Production Schedules window (called MPS Names in the
navigator).
2.
3.
4.
If you are creating entries for a demand schedule, enter an item with the following
MRP planning methods (see: Defining Items, Oracle Inventory User's Guide):
MPS
DRP and MPS
5.
See Also
Specific Forecast
Source Lists
6
Planner Workbench
You can select a predefined set of criteria or any combination of criteria when querying
on the recommendations generated by the DRP, MRP or MPS planning process. The
planner can then:
change parts of the plan, then replan changes and all items affected by them using
either a batch or an online process
firm a planned order or change its quantity and date to stabilize portions of the plan
generate a graphical view of the relationship between item supply and end demand
Supply Chain Planning users can also review and implement recommendations across
multiple, interdependent organization. See: Overview of the Supply Chain Planner
Workbench.
You can review planning exception messages, resource availability, item information,
supply details, the horizontal plan, and a summary of supply and demand.
Supply Chain Planning users can also get a summary of supply and demand for all
organizations included in the plan.
Note: The planning products support Oracle Project Manufacturing 's
See Also
Online Planner
2.
3.
4.
In the Find Items folder window, enter your search conditions. See: Customized
Find Windows.
5.
Choose Find.
This window specifies a plan's resources by department or line. In this window you
can also choose buttons to review a resource's items, availability, requirements, and
horizontal plans.
2.
3.
Choose Items to display planning information in the Items window. See: Defining
Items, Oracle Inventory User's Guide.
4.
In the Find Items folder window, enter your search conditions. See: Customized
Find Windows
5.
Choose Find.
6.
Select an item.
You can use this to highlight or drill down into other windows for selected items.
Choose the Attachments toolbar icon to use the Attachments feature. See Working with
Attachments, Oracle Applications User's Guide.
Note: BOM calendar periods are used, not accounting periods.
See Also
inventory.
2.
3.
From the Tools menu, select On Hand to display the View On Hand Quantities
window.
Planning Organizations
Preferences selection.
2.
3.
4.
5.
Choose Find.
6.
7.
Choose the Attachments toolbar icon to use the Attachments feature. See Working
with Attachments, Oracle Applications User's Guide.
8.
See Also
Online Planner
Tools Menu
Alternate BOM
Used for net change replanning.
Alternate Routing
Used for net change replanning.
BOM Item Type
Type of item, such as: Model, Option class, Planning Standard, and Product Family.
Build Sequence
Displays the build sequence used in releasing planned orders.
Category
Item category.
Compression Days
The number of days that the planning process suggests you compress the order, that is,
reduce the time between the start date and due date.
Days from Today
Displays demand or supply entries that are due within the specified number of days
from the current date.
Firm
Indicates if a supply order was firmed or not.
Implemented Quantity
The quantity of a supply order which has been implemented as a discrete job or
purchase requisition.
Item
The part number.
Last Unit Completion Date (LUCD)
For repetitive or aggregate repetitive schedules, this value is the the last unit completion
date. For repetitive demand, this value is the rate end date. This field name can be
changed to meet your requirements.
Last Unit Start Date (LUSD)
The last unit start date of a repetitive or aggregate repetitive schedule.
Line
Used for net change replanning.
New Date
The due date of a firmed supply order. This defaults to the suggested due date of the
order; however, you can manually override this value.
New Quantity
The order quantity of a firmed order. This defaults to the suggested quantity of the
order; however, you can manually override this value.
Old Due Date
The original due date of a rescheduled order.
Old Order Quantity
The original order quantity of a discrete job, repetitive schedule, or flow schedule.
Order Number
The order number of a purchase order, purchase requisition, discrete job, flow schedule,
or sales order.
Order Type
The order type of the supply or demand entry. The supply types are: Purchase order,
Purchase requisition, Discrete job, Suggested aggregate repetitive schedule, Flow
Schedule, Planned order, Non-standard job, PO in receiving, Intransit shipment,
Intransit receipt, Suggested repetitive schedule, Discrete job by-product, Nonstandard
job by-product, Repetitive schedule by-product, Planned order by-product, and
Payback Supply. The demand types are: Planned order, Non-standard job, Discrete job,
Flow Schedule, Repetitive schedule, Expired lot, Sales Order,, Forecast MDS, Manual
MDS, Other independent demand, Hard reservation, MDS independent demand, MPS
compiled demand, Copied schedule demand, Planned order scrap, Discrete job scrap,
Purchase order scrap, Purchase requisition scrap, PO in receiving scrap, Repetitive
schedule scrap, Model/option class/product family demand, Intransit shipment scrap,
Interorganization order, and Payback Demand.
Organization
The organization short code. Use this criteria to display supply or demand entries
within the specified organization.
Planner
The planner associated with an item. This criteria displays items or supply/demand
entries for items that belong to the specified planner.
Project Number
The project number associated with an order. Use this criteria to display
supply/demand associated with the specified project.
Quantity/Rate
The required quantity of a demand entry or the order quantity of a supply entry. For
repetitive demand, this field displays the daily demand quantity. For repetitive supply,
it displays the daily production rate.
Release Errors
Error messages associated with specific records not selected in the Select All for Release
processing.
Repetitive
Indicates if an item is repetitively planned. Use this criteria to display repetitive supply
or demand entries.
Rescheduled
Indicates if a supply order has been rescheduled.
Schedule Group
You can select a schedule group for a planned order and release.
Selected for Release
Indicates if a supply order has been selected for release.
Source Organization
Organization from which a specified supply order is sourced.
Source Supplier
The supplier associated with an item, used as the default for an order.
Source Supplier Site
The location of the source supplier.
Suggested Dock Date
Date that the planning process suggests the supply order is received.
Suggested Due Date
Supply: The date the planning process recommends the item should be available to use
in manufacturing. This is typically when you deliver the item to inventory. This is
calculated by adding any postprocessing lead times for the item to the new dock date.
Demand: The date the using assembly requires the item. If the demand is rate-based, the
start date of the rate of the demand is displayed.
Suggested Order Date
The date the planning process recommends to begin an order so it is completed by the
suggested due date, based on fixed and variable lead time.
Suggested Start Date
Start date of the supply order.
Task
The task number of an order. Use this criteria to display supply/demand associated
with the specified task.
Using Assembly
The parent assembly of an item.
Supplier
The supplier of a purchase order.
See Also
2.
3.
4.
Choose All Dates to specify the entire date range used to review supply/demand
detail information.
5.
Choose the Current button to view current supply/demand information; choose the
Snapshot button to view supply/demand information from the latest planning run.
6.
7.
Available to Promise
User's Guide
Tools Menu
2.
3.
4.
Choose the Current button to view current supply/demand information; choose the
Snapshot option button to view supply/demand information from the latest
planning run.
See Also
Available to Promise
Tools Menu
plans. Supply Chain Planning users can also compare snapshot and
current data from the Enterprise View window.
2.
3.
4.
Choose the Current option button to view current data; choose the Snapshot option
button to view snapshot data.
See Also
Reviewing the Horizontal Plan
2.
3.
4.
5.
Choose Graph.
See Also
you replan simulations, you can compare different versions of the same plan or analyze
the strengths and weaknesses of a single plan.
Note: You can only display detailed exception and item planning
You can use the Planning Exception Messages workflow to route messages to personnel
such as planners, buyers, and suppliers. This allows you to automate the processing of
reviewing exceptions in order to identify potential conflicts before they become
problems.
2.
Optionally, enter and run a query to narrow down the list of exceptions.
The types of exceptions you might see are:
Items allocated across projects: items whose supply for one project has been
allocated to the demand of a different project
Items below safety stock: items for which demand, less supply, brings the
projected quantity on hand to a negative level or below safety stock
Items that are over-committed: items for which ATP is negative or below safety
stock
Items with a shortage: items whose quantity on hand is less than the sum of the
requirements plus safety stock, within the exception time fence defined by the
item's planning exception set
Items with a shortage in a project: items whose demand exceeds supply with a
project/task for an item Items with excess inventory: items whose quantity on
hand exceeds the total requirements against the item, within the exception time
fence defined by the item's planning exception set
Items with excess inventory in a project: items whose supply exceeds demand with
a project/task for an item
Items with expired lot: lots that expire within the planning horizon
3.
Items with negative starting on hand: items with a negative onhand beginning
balance
Items with no activity: items with no demand or supply in the current plan
Items with repetitive variance: items with suggested aggregate schedules that
differ from current aggregate schedules by more than a user-defined repetitive
variance percentage, up to the exception date defined by the item's planning
exception set
Late order due to resource shortage: items that will cause a late order because a
resource required to manufacture the item is overloaded
Late supply pegged to forecast: items with shortages that prevent forecast demand
from being met, caused by component shortages
Late supply pegged to sales order: items with shortages that prevent sales order
demand from being met, caused by component shortages
Orders to be cancelled: items with orders that the planning process recommends
be cancelled
Orders to be rescheduled in: items with orders that the planning process
recommends be rescheduled to an earlier date
Orders to be rescheduled out: items with orders that the planning process
recommends be rescheduled to a later date
Orders with compression days: items with planned orders, discrete jobs and
purchase orders that have compression days and need to be expedited
Past due forecast: items with a forecast demand due date earlier than the plan
start date
Past due orders: items with planned orders, discrete jobs and purchase orders
that are past due
Past due sales orders: items with a sales order due date earlier than the plan start
date Resource Overloaded: a resource is overloaded, as defined by the load ratio
entered in the exception set
Exception Count: the number of exceptions for the given exception type
Category: the item category associated with items for which you see exceptions
Planner: the planner who is associated with the items for which you see
exceptions
Buyer: the buyer of the item for which this exception type occurred
Planning Group: the planning group, if any, that is associated with the items for
which you see exceptions; only appears if the exception occurred in a
project-related plan
Project: the project, if any, that is associated with the items for which you see
exceptions; only appears if the exception occurred in a project-related plan
Task: the specific project task, if any, that is associated with the items for which
you see exceptions; only appears if the exception occurred in a project-related
plan
Version: the version of the planning run for which this set of exceptions occurs;
the version number gets incremented each time you click Save Exceptions, even
if you do not make changes to the plan
Dept/Line: the department or production line for which this exception type
occurred
Resource Type: The resource type for which this exception occurred
If nothing appears in one of these fields, there are likely multiple values for that
field. For example, if the Item field is blank, there may be multiple items for which
the exception occurred. To find out more, query exceptions by the above-mentioned
fields or look at the exception details for the exception type that interests you.
2.
Click the box to the left of each exception type for which you want to see detailed
information. You can only check the current version of exceptions.
3.
Check the exceptions whose message details you want to display. You can only
check the current version of exceptions.
2.
Check the exceptions whose items you want to display in a horizontal plan. You
can only check the current version of exceptions.
2.
Assign the appropriate exception set to each item when you define or update the item.
Sensitivity controls that quantify excess and repetitive variance exceptions are:
excess quantity
resource underloaded
resource overloaded
Exception time period types that define the time period for overcommitted, shortage,
excess, and repetitive variance exceptions are:
If you choose to use a user-defined time fence, you must define the number of days that
this time fence corresponds to.
See Also
modifying alternate BOM and alternate designators for firm planned orders
Note: You cannot replan changes to supply for repetitive items. Items
Replanning is based on the snapshot data gathered during the original planning run,
including item, bill of material, resource availability, and sourcing information (if you
are a Supply Chain Planning user). Because the replan does not update this information
with new transactions, you can maintain sets of alternative scenarios, examine the
effects of different changes and implement the changes that best meet your business
requirements.
Note: Until you release your order or schedule, Net Change Replan will
change the item status back to that in effect at the last planning run. It
will also base any new recommendations on the original snapshot data.
Net Change
Replan will correctly replan changes to items only after the items have been released.
Net Change Replan does not consider the transactions that have occurred in the
execution system (including the planned orders released for the plan in question). It
reuses the snapshot of the prior run. Rerun the snapshot to include these changes.
demand, and available resource records without increasing database traffic. Starting an
online session loads all planning data into memory, afterwards, you can make changes
to that data, then replan the changes to see their effect on the rest of the plan. You can
implement and release your changes from within the session, or you can make changes
and replan as many times as necessary before the release.
As a simulation tool, the online planner quickly allows you to see the effect of the
changes you make in the Planner Workbench. As an implementation tool, it reduces
unnecessary database transactions and offers rapid plan revision and execution. As a
monitoring tool, it generates the full set of exception messages following a replan - it
also allows you to save the exceptions generated by previous sessions, offering you
feedback on successive planning decisions.
The online planner is particularly useful when performing frequent simulation on a
single plan. In online mode, you can do this without suffering a significant loss in
performance.
However, there are three restrictions to using the online planner. You cannot make
changes to either item attributes or plan options, the online planner will not evaluate
capacity constraints, and it will lock all other users out of the plan while the session is
active.
See Also
2.
3.
4.
5.
6.
In the Planner Workbench window, choose Batch in the Net Change Replan region,
then choose Plan.
7.
8.
Choose OK.
9.
Verify that the net change replanning process has completed. See: Using the
Concurrent Requests Windows, Oracle Applications User's Guide.
2.
3.
4.
5.
In the Planner Workbench window, choose Online in the Net Change Replan
region, then choose Plan.
Note: The online planner will clear and lock all other windows
In the Planner Workbench window, choose Online in the Net Change Replan
region, then choose Status. The online planner will display one of the following
status messages:
Concurrent Request [concurrent request number] pending Loading Data Ready for
Planning, Planning Complete
Loading Data Ready for Planning Planning Complete
In the Planner Workbench window, choose Online in the Net Change Replan
region, then choose Stop.
2.
Choose OK to confirm that you want to end your online planner session.
Note: The Net Change Replan region is not yet ready to start a new
close the window. You can now start another online planner session, or
start the batch mode planner
2.
When you first make changes in the window, the changed values are highlighted in
the color pink. After following the procedure for replanning, all changes created by
the online planner are now highlighted in the color blue.
If you make other changes in this replan session, those new changes are highlighted
in pink in the window.
See Also
work orders
purchase orders
planned orders
safety stock
sales orders
forecasts
You must have Pegging selected as a plan option. See: Reviewing or Adding Plan
Options.
2.
You must have the Pegging item attribute (in Oracle Inventory) set to one of the
following options:
Soft Pegging
2.
3.
4.
In the Find Supply/Demand folder window, enter your search conditions. See:
Using Query Find, Oracle Applications User's Guide, Using Query Operators, Oracle
Applications User's Guide, and Customizing the Presentation of Data in a Folder,
Oracle Applications User's Guide.
5.
Choose Find.
6.
7.
Choose Pegging to open the Object Navigator window for a graphical display of
supply/demand relationships for an item.
With the Object Navigator, you can display your data in a visual hierarchy. Each
element in the sourcing rule is displayed in a rectangular node, with connecting
lines that depict the nodes' relationships to each another (known as the data flow).
The nodes are color-coded for easy identification, and other aspects of the data flow
can be changed to meet specific requirements.
2.
3.
Choose Pegging to open the Object Navigator window for a graphical display of
supply/demand relationships for an item.
See Also
Available to Promise
You can monitor and coordinate customer delivery promises using the available to
promise information in the Horizontal Plan window and Planning Detail report. The
planning process calculates ATP based on the Calculate ATP item attribute. See:
MPS/MRP Planning Attribute Group, Oracle Inventory User's Guide.
ATP is based on a specific MPS, DRP or MRP plan and is non-cumulative. Changes to
on-hand quantities, scheduled receipts, and demands made after the planning process
is completed are not reflected in ATP until the next time the material plan is executed.
Note: Any ATP calculation done through Oracle MRP does not consider
Calculating ATP
Oracle MRP calculates the ATP quantity of an item for each day of planned production
by adding planned production during the period (planned orders and scheduled
receipts) to the quantity on hand, and then subtracting all committed demand for the
period (sales orders, component demand from planned orders, discrete jobs, flow
schedules, and repetitive schedules).
Note: Committed demand does not include forecasted demand or
I1: 40%
I2: 60%
Also assume that PF has Forecast Control set to Consume, and I1 and I2 both have
Forecast Control set to Consume and derive.
Now assume the following forecast and sales order:
Sales Order: I1 (SO) 10 After explosion and consumption, the forecast looks like
this:
Forecast: PF (F) 90
Forecast: I1 (F) 30
Forecast: I2 (F) 60
After loading the forecast and sales order to an MDS, the schedule looks like this:
Schedule: PF (F) 90
Schedule: PF (SO) 10
Schedule: I1 (F) 30
Schedule: I1 (SO) 10
Plan: PF (F) 90
Plan: PF (SO) 10
Plan: I1 (F) 30
Plan: I1 (SO) 10
Plan: I2 (F) 60
Negative ATP
If ATP goes negative in a period, it rolls backwards to find ATP from a previous period
to cover the demand.
Consider the following simple example:
Available to Promise
Type
Beg. Inventory
Period 1
Period 2
Period 3
Period 4
Sales Order
100
300
Schedule Receipt
300
200
ATP (before
adjustment)
200
-100
ATP
100
The available to promise for period 1 is calculated by subtracting the sales order
demand (100) from scheduled receipts (300) giving ATP (200). In period 2, however,
when subtracting sales orders (300) from scheduled receipts (200), the initial result is
negative ATP (-100). Oracle MRP borrows available ATP from the previous period to
compensate for the negative quantity.
Inventory Snapshot
Oracle MRP bases ATP information on the:
scheduled receipts
master schedule entries taken during the latest MPS, DRP or MRP plan
Suggestion: You should re-plan the master schedule or material requirements to get the
latest ATP information.
Choose whether to display ATP information for an item in the Horizontal Plan window
and on the Planning Detail report with the ATP calculation option. Set this option when
you define an item.
See Also
Capable to Promise
Snapshot
Capable to Promise
Capable to Promise (CTP) extends Available to Promise by taking into account capacity
information. Whereas ATP only considers material availability and assumes infinite
capacity resources, CTP considers availability of both materials and capacity, giving a
more realistic picture of whether demand can be satisfied within a given time fence.
You can enable the Capable to Promise feature by setting the INV:Capable to Promise
profile option to Enable Product Family ATP and CTP. See: Oracle Inventory Profile
Options, Oracle Inventory User's Guide.
CTP calculations take longer than ordinary ATP calculations, and in some cases you
may not want to spend the extra time considering capacity resources. Therefore, you
can choose at the item level whether you want to check only materials, only capacity
resources, or both in the ATP calculation. To do this, set the Check ATP item attribute in
the Order Management attribute group. See: Order Management Attribute Group,
Oracle Inventory User's Guide.
If you want an ATP calculation on the item to consider resources, you must also define
a CTP routing for the item and check the Capable to Promise check box in the Routing
form. (The CTP calculation only takes into account demand placed on resources by
items whose routings have the Capable to Promise flagged on.) See: Creating a Routing,
Oracle Bills of Material User's Guide. In addition, you must specify by department which
resources should be used in CTP calculations. See: Defining a Department, Oracle Bills of
Material User's Guide.
The ATP Rule can also be associated with a department and resource combination. This
is set in the Oracle Bills of Materials Resource window, or a line as set in the Oracle
Work In Process Production Lines window.
The following settings apply to the CTP function:
The CTP check is based on the ATP rule assigned to the Department/Resource
combination.
The ATP settings of Resource Only, and Material and Resource are allowed only for
ATO (Assembled to Order) models, option classes, and items.
A value is required for Past Due Demand/Supply Time Fence on an ATP Rule
associated with a Resource. It is recommended that Past Due Supply is set to zero,
since resource supply cannot be accumulated.
Item Attributes Used in Order Management, Oracle Order Management User's Guide.
release orders
Alternatively, you can enable the planning process to automatically release planned
orders, without modification to dates and quantities or implementation details.
However, you must manually implement and release repetitive schedules. See:
Auto-release Planned Orders.
Note: You cannot release kanban items. These items have item attribute
See Also
Online Planner
2.
3.
Check Firm and, optionally, update the firm date and firm quantity.
4.
2.
3.
4.
5.
6.
Check Firm and, optionally, update the firm date and firm quantity.
7.
8.
Optionally, enter the alternate BOM designator and alternate routing designator.
9.
See Also
Online Planner
The order type depends upon the Make or Buy item attribute. If an item is defined as
Make, but can be purchased, you can release it as a purchase requisition or a discrete
job. In addition, Supply Chain Planning users can determine the Make/Buy item
attribute with sourcing rules and bills of distribution. For more information, refer to
Sourcing Rules and Bills of Distribution
You can load discrete jobs as firmed and/or released and can view current discrete job
information.
2.
Optionally, override the default job class or requisition load group by opening the
Preferences window from the Tools menu.
3.
4.
5.
routing, and demand class can only be updated for planned orders
being released as discrete jobs or discrete jobs being rescheduled.
The schedule group has a list of values which lists all schedule
groups from WIP for the organization in the supply record. The
build sequence is a number and can only be updated when
schedule group is entered.
6.
Optionally specify line, alternate BOM designator and alternate routing designator.
If you are using Project MRP, optionally specify project and task. For a purchase
requisition, source organization, source supplier, or source supplier site, implement
a discrete job as firm by setting the firm flag.
7.
8.
9.
2.
Choose Select All for Release, or check Release for each planned order.
During Select All for Release processing, records are posted to the database for
server side processing. After processing is complete, records are automatically
required in the Supply/Demand window. All messages, both error and successful,
are tied to individual records and are displayed in a new field called Release Errors.
Records with error messages are highlighted. You can fix the records with errors
and resubmit them for processing.
3.
2.
From here navigate to the windows or fields that need to be changed or updated
4.
Choose Select All For Release processing again to process the records.
5.
You can also delete the error message associated with the record after correcting the
error condition.
After taking corrective action for a record, navigate to the Supply/Demand window.
2.
Delete the error message associated with the record in the Release Errors field.
For example, if the error message is Location is Missing and you corrected the error
by selecting a location on the Release window - you can now delete this message.
3.
4.
Check Release in the item row and complete the steps to release a single planned
order.
See Also
Implementing Repetitive
Online Planner
2.
Check Item.
Note: You can implement repetitive schedules as firm using the
Planner Workbench.
3.
4.
Review the implemented date and implemented quantity and change as necessary.
5.
Optionally, override the default job class or requisition load group by opening the
Preferences window from the Tools menu.
6.
See Also
Online Planner
Firm a planned order: the planning process will not reschedule the planned order.
Implement a planned order as a firm job: the planning process will reschedule the
planned order.
Release an order for a job that has been implemented as firm: the planning process
will treat the job as a firm scheduled receipt and will not reschedule the order.
Therefore, to prevent the planning process from making rescheduling suggestions, you
must either firm the planned order or release a planned order that has been
implemented as firm. See: Creating Firm Planned Orders.
2.
If you are creating a planned order manually, enter the firm date and firm quantity.
3.
4.
Review the implemented date and implemented quantity and change as necessary.
5.
Optionally, override the default job class by opening the Preferences window from
the Tools menu.
6.
7.
Choose Release.
8.
9.
See Also
Online Planner
See Also
Tools Menu
Profile Options
reschedule in
reschedule out
cancel
process jobs using the Planner Workbench. You must perform these
functions in Oracle Purchasing or Oracle Work in Process. Cancel
purchase requisitions using the Control Requisitions window. Firm or
reschedule purchase orders using the Purchase Orders window. Cancel
purchase orders using the Control Purchase Orders window.
2.
Check an Item.
3.
See Also
Online Planner
2.
3.
4.
window.
2.
2.
3.
4.
window
2.
2.
3.
See Also
Capacity Planning
Overview of Online Capacity Planning
Online capacity planning enables you to generate a material and a capacity plan
simultaneously. You can analyze and maintain material and capacity plans from the
same Planner Workbench. You can get immediate information about whether your
material requirements plan is realistic given your capacity constraints. You can also
identify capacity problems - overload or underload - and make changes to balance
capacity requirements with material requirements. Finally, you can run what-if
simulations to see the effects of changing part of your material or capacity plan before
you implement it.
CRP is a more detailed capacity planning tool than rough cut capacity planning in that
it considers scheduled receipts and on-hand inventory quantities when calculating
capacity requirements.
As with RCCP, you can perform detailed capacity planning at either the resource level,
routing-based, or production line level, rate-based.
See Also
Prerequisites
Before you can view capacity information from the Planner Workbench, you must:
To indicate that you want to plan both materials and capacity, check the Plan Capacity
check box in the Plan Options window before you run the plan. If the plan is an MPS
plan, also assign a Bill of Resource to at least one organization. See: Reviewing or
Adding Plan Options.
Note: The Plan Capacity flag is enabled only when CRP is installed.
2.
2.
Select the resource or resources for which you want to see detailed information.
3.
4.
2.
Select the resource for which you want to see available capacity.
3.
Choose Availability.
The Resource Availability window appears.
4.
2.
Click the check box next to each resource you want to check.
3.
Click the Horizontal Capacity Plan button. The Horizontal Plan window appears.
4.
In the Type column, look for Capacity Load Ratio. Then read across to see what
percentage of capacity is utilized for each time period.
5.
In the Type column, look for Cum capacity load ratio. Then read across to see what
percentage of capacity is utilized overall.
Note: The Type column only displays information that you've
2.
3.
Attach the exception set to the resource by choosing the Exception Set in the
Resources window in Oracle Bills of Material, and the Production Lines window in
Oracle Work in Process.
4.
2.
3.
To make changes to capacity available for this plan, navigate to the Available
Resources window. Then change the date, capacity units, or daily capacity for any
resource.
4.
5.
6.
In the Planner Workbench window, choose either Online or Batch in the Net
Change Replan region, then choose Plan.
7.
See Also
Overview of Net Change Replan, Identifying Capacity Problems
Plan Status
You can view the status of the planning options you have submitted and the run times
of the processes in the Plan Status window.
To view the status of your plan options
1.
Current Submitted Options: The information on this region is the same as the
data entered on the Plan Options window when you generate this plan.
Last Submitted Options: The information displayed in this region is the historical
record of the options submitted prior to the current job.
Dates: This window displays the run times of the three processes that comprise
the planning engine.
See Also
7
Demand Classes
find a forecast, it consumes entries that have no demand class. If you place sales order
demand that does not have an associated demand class, the forecast consumption
process attempts to consume forecast entries associated with the organizational default
demand class first, and then consume entries that have no demand class defined.
In the above diagram, your master scheduler has created three forecast names: FC
WHOLESL, FCRETAIL, and FCMAILORDER. You maintain and report on each
forecast independently. Note that these forecasts are defined within a forecast set.
Your master scheduler combines all sources of demand, including the three forecasts
and all sales orders, into a single statement of demandthe master demand schedule.
The master scheduler then plans the master production schedule and the MRP plan
with all the demand combined.
See Also: Overview of Forecasting, page 2-1
Forecast Consumption
You can associate a demand class with each sales order. When you place sales order
demand, the forecast consumption process consumes the forecast with the same
demand class. If the forecast consumption process does not find a forecast, it consumes
entries that have no demand class. If a sales order does not have an associated demand
class, the forecast consumption process attempts to consume forecast entries associated
with the organizational default demand class first, and then consume entries that have
no demand class defined.
Abnormal Demand
Certain sales orders should not consume the forecast, because they are not indicative of
what orders you expect in the future. For example, suppose you manufacture soft
drinks, and have 100 primary distributors to whom you sell. Your sales order demand
is roughly even across those distributors. One of those distributors has a special
promotion on your product, and places orders for ten times their normal amount. The
large order by this one distributor does not mean that your other distributors will order
less. Therefore, you might mark this particular order as abnormal.
To prevent a sales order from consuming forecasts, associate the sales order to a
demand class that does not have a corresponding forecast and is not the same as the
demand class for your organization. In this case, the forecast consumption process does
not consume any forecast for the sales order.
Tip: You should define a demand class for abnormal demand and
assign it to an order type that you can associate with sales orders you
might mark as abnormal.
In the above diagram, suppose your master scheduler has created three forecast names:
FCWHOLESL, FCRETAIL, and FCMAILORDER. You maintain and consume each
forecast independently. However, rather than combining all forecast and sales order
demand into a single master demand schedule, as was done in the previous diagram,
your master scheduler maintains three demand schedules: WHLSALMDS, RETAIL
MDS, and MAILMDS. Each demand schedule consists of the forecast and actual
demand associated to a specific demand class.
Your master scheduler also maintains three separate master production schedules:
WHLSALMPS, RETAILMPS, and MAILMPS. You plan each master production
schedule independently. In this manner, not only has the master scheduler broken out
the sources of demand into separate groupings, but has also segregated units of
production by demand class as well.
To drive the MRP plan, the master scheduler combines all sources of production into a
single master production schedule, thus driving the MRP plan by the aggregate master
production schedule. The master scheduler manually combines master schedules into a
single master schedule, using the Load/Copy/Merge Master Demand Schedule or Load
Master Production Schedule windows. See: Loading a Master Schedule From an
Internal Source, page 3-9
You can net items by subinventory. For example, items that are available to satisfy
Wholesale demand class are in a separate subinventory than those items that satisfy
the Retail demand class. You specify the Wholesale subinventory as nettable and
the Retail subinventory is nonnettable when planning the Wholesale demand
class, and vice versa when planning the Retail demand class. This relies upon you
manually overriding the subinventory netting when launching the planning
process.
You can reserve all items in a subinventory for a sales order. You can determine the
items in the subinventory reserved for the demand class by the sales order
associated with the demand class. Note that this method requires the full use of
hard reservations.
See Also
8
Time Fence Control
master schedule entries outside the planning time fence. For an MRP plan, you can
overwrite all planned orders as well as firm planned orders that fall outside the
planning time fence.
Planning Time Fences for Requisitions
Purchase requisitions and internal requisitions are not subject to planning time fence
processes.
the new due date lies within the auto-release time fence
the orders are for standard items (will not release models, option classes, and
planning items)
the orders are for DRP planned items in a DRP plan, MPS planned items in an MPS
plan, or MRP planned items in an MRP plan See: Auto-release Planned Orders.
the release time fence option is defined as anything other than Do not auto-release,
Do not release (Kanban), or Null
Fence to indicate whether to form natural time fences for your MRP
firm planned orders when launching the planning process.
Oracle MRP does not create a time fence for an MRP firm planned order if you set this
profile option to no. See: Setting Your Personal User Profile, Oracle Applications User's
Guide.
orders and the implicit time fences that they create even if you specify
not to use Planning Time Fence control. The planning process does not
apply Planning Time Fence logic to purchase requisitions or internal
requisitions.
Overwriting Entries
When you launch the planning process, you can also choose to overwrite the master
production schedule entries and firm planned orders that fall outside the planning time
fence for an item.
For an MPS plan, the planning process deletes all master production schedule entries
that lie outside the planning time fence, and replaces those entries with a new master
production schedule. The planning process does not modify master schedule entries
that fall within the planning time fence. You can use this option to induce short-term
stability of the master production schedule, while creating the optimal long-term master
production schedule.
When you use this option for an MRP or DRP plan, the planning process overwrites all
planned orders and firm planned orders outside the planning time fence.
See Also
Overwrite Options.
the option you choose. The planning manager deletes master production entries for
repetitive items.
None
You can use this option to leave master production schedule entries and not
automatically reduce them. Production relief decrements the master production
schedule entries through the creation of discrete jobs or purchase requisitions.
Past Due
You can use this option to automatically reduce master production schedule entries as
they become past due.
and decrease value is not entered (null), Oracle MRP is not restricted from increasing or
decreasing the repetitive schedule respectively.
Because the planning time fence restricts the actions that Oracle MRP can take, your
plan may have material imbalances that require the attention of the master scheduler or
planner. You can easily identify those elements of the plan that require the attention of
the planner by using the Exceptions window to review action messages. You can view
those items and orders based upon a set of predefined exception messages. You can also
run the Planning Detail Report or the Supply Chain Planning Detail Report for a
specific planner and exception message.
See Also
Reviewing Planning Exceptions Planning Detail Report
Period 2
Forecast Demand
Gross Requirements
MPS
Projected QOH
ATP
Period 3
Period 4
100
100
100
100
100
100
100
100
Period 3
Period 4
Period 2
Actual Demand
50
80
Gross Requirements
50
80
Planned orders
50
80
Projected QOH
50
80
Period 1
Period 2
Period 3
Period 4
50
50
50
80
Gross requirements
50
80
50
50
Projected QOH
Note the following: there is no demand for MODEL in the first two periods since
MODEL is not an orderable item it is used primarily for forecast and planning
purposes. Demand for MODEL after the demand time fence (period 2) consists entirely
of forecasted demand.
Demand for CONFIG1 in the first two periods consists entirely of actual demand. There
is no other demand for CONFIG1 because it is not forecasted.
Demand for item OPTION 2 in the first two periods consists entirely of demand passed
down from item CONFIG1, which is derived from actual sales order demand for
CONFIG1. After the first two periods, the demand for OPTION 2 consists of demand
generated from MODEL, which is based entirely on forecasted demand.
You have chosen to master schedule both the model and its options. This results in the
production is being driven by sales orders within the demand time fence and by
forecasts outside the demand time fence. Oracle MRP derives the master schedule for
the options entirely from the master schedule for the model. The options are master
scheduled for purposes of order promising. See: Available to Promise.
For this example, you have defined the planning time fence for MODEL as some
number of periods out from today, thereby providing stability for the short-term plan.
You have not defined a planning time fence for the option items 1, 2, and 3. If you
execute the planning process using demand time fence control and you choose to
overwrite the outside planning time fence, Oracle MRP overwrites the entire master
production schedule for the option items, and creates a new schedule based entirely on
actual sales orders for the option items within the demand time fence, and the master
production schedule for the model outside the demand time fence.
For this example, your company does not use Oracle Work in Process. Therefore,
discrete jobs are not created, and thus never consume the master production schedule
for MODEL. To effectively consume the master production schedule for MODEL, you
must set the Auto-reduce MPS attribute to Within Demand Time Fence when you define
the MODEL item. Whenever a master production schedule entry is within the demand
time fence, Oracle MRP automatically reduces it. See: Defining Items, Oracle Inventory
User's Guide.
If your company did use Oracle Work in Process and Oracle Purchasing, you could set a
release time fence for any planned orders generated by the planning process. If you
define OPTION2 with a release time fence of as many days as there are in period 1, then
the 50 planned orders for period 1 generated by the planning process would
automatically be released. They would be released to Oracle Work in Process as discrete
jobs or to Oracle Purchasing as purchase requisition, depending on their item attributes;
their job status, requisition load group, and other values would depend on the defaults
applicable to the item. With this time fence, the 80 planned orders generated for period
2 would not be released, and would require selection and implementation by the master
scheduler or material planner. See: Defining Items, Oracle Inventory User's Guide.
9
Two-Level Master Scheduling
Forecasting
You can forecast any item, anywhere on your bills of material, including planning
items, models, option classes, options, and mandatory components. You can also define
a configuration as a standard item and forecast it as you would any other standard
item.
Forecast Explosion
You can explode forecasts for planning items, models, and option classes to selected
components using the components, usages, and planning percents defined on your
planning, model, and option class bills. You can associate alternate bills of material to
multiple forecasts for the same item and explode the same forecast using different
components, usages, and planning percents. You can modify, re-explode, and
re-consume forecasts for planning items, models, and option classes.
Forecast Consumption
Oracle MRP automatically consumes forecasts for configurations, models, option
classes, options, and mandatory components as you place sales order demand for
configurations.
Master Scheduling
You can master schedule any planned item, anywhere on your bills of material,
including models, option classes, options, and mandatory components. You can also
define a configuration as a standard item and master schedule it as you would any
other standard item.
Production Relief
Oracle MRP automatically relieves master production schedules for configurations,
models, and option classes when you create final assembly orders for configurations.
Oracle MRP automatically relieves master production schedules for options and
mandatory components as you create work orders to build them.
Shipment Relief
Oracle MRP automatically relieves master demand schedules for configurations,
models, option classes, options, and selected mandatory components as you ship sales
orders for configurations.
Production Planning
Production Planning is one of the methods of two-level master scheduling used in
managing the supply chain. In creating a production plan, a company looks at the big
picture (the aggregate) rather than the level of the individual product or item,
predicting a level of manufacturing output in accordance with predicted sales and other
company goals and constraints.
Because production planning occurs at an aggregate level, creating a production plan
involves grouping products into product families. These groupings are based on
product's similarities in design, manufacturing process, and resource usage. You can
assign planning percentages to the members of the product family, and use the
relationship between product family items and its members in forecast explosion,
consumption, master scheduling, and capacity and materials planning. Production
Planning enables forecasts for the product family to be exploded down to the product
family members (based on the planning percentages and effectivity dates for the
member items) in a process similar to that of exploding a forecast for a model.
Sales orders for member items consume the forecast for the member items as well as for
the product family. Throughout the application, processing is done at both the
aggregate and the detail level. Thus, you will be able to get detailed and high-level
information about how well your organization is executing its production plans.
Prerequisites to Production Planning
Before you can start production planning, you must:
Define an item as a product family. See: Defining Items, Oracle Inventory User's
Guide.
Assign member items to the product family. See: Assigning Product Family
Members, Oracle Bill of Materials User's Guide.
Set planning percentages and effectivity dates for member items. See: Setting
Planning Percentages for Product Family Members, Oracle Bill of Materials User's
Guide.
See Also
Item
Description
Optional
Plan %
Training
Computer
Planning
No
--
.2
. Laptop
Computer
Model
No
60
..3
. . Carrying Case
Standard
No
100
..3
. . Keyboard
Standard
No
100
..3
. . Processing
Unit
Option Class
No
100
...4
. . . Processor A
Standard
Yes
65
...4
. . . Processor B
Standard
Yes
35
..3
. . Monitor
Option Class
No
100
...4
. . . VGA
Option Class
Yes
70
....5
. . . . VGA
Manual
Standard
No
100
....5
. . . . VGA1
Standard
Yes
50
....5
. . . . VGA2
Standard
Yes
50
...4
. . . EGA
Option Class
Yes
30
....5
. . . . EGA1
Standard
Yes
55
Level
Item
Description
Optional
Plan %
....5
. . . . EGA2
Standard
Yes
45
...4
. . . Monitor
Manual
Standard
No
100
..3
. . Operating
System
Option Class
Yes
90
...4
. . . Windows
Standard
Yes
80
....5
. . . . Windows
Manual
Standard
No
100
....5
. . . . Windows
CD
Standard
No
100
...4
. . . Linux
Standard
Yes
20
....5
. . . . Linux
Manual
Standard
No
100
....5
. . . . Linux CD
Standard
No
100
Planning item
Model
Option class
Standard item
Define the BOM Item Type for each of your items using the Define Item window in
Oracle Inventory. You can combine each of these item types to define complex bill of
material structures using the Define Bill of Material window in Oracle Bills of Material.
Planning Items
Use planning items to represent groups of related items. In a configure-to-order
environment, you might use planning items to represent groups for your models, and
state your high-level production plans in terms of these groups rather than individual
models. You can also use planning items for forecast explosion.
Models
Use models to represent products that include options chosen by customers during
order entry. For example, you might use a model to represent a computer with many
different CPU, monitor, and operating system options.
Assemble to Order Models vs. Pick-to-Order Models
Models can be assembled-to-order or picked-to-order. Use assemble-to-order models to
represent products whose options and mandatory components are assembled, using a
final assembly order, when customers order configurations. Use pick-to-order models
to represent products whose options and included items are picked and shipped
directly from stock, using a sales order pick slip, when customers order configurations.
Option Classes
Use option classes to group together related options. In a configure-to-order
environment, you might use an option class to group together the different processor
options that are available when customers order a computer.
Planning Bills
The following table illustrates a planning bill for Training Computer, a planning item
that represents a planning bill for three types of computers: laptop, desktop, and server.
The planning percent assigned to each member of the planning bill represents
anticipated future demand for each product. Although, in this example, the planning
percents add up to 100%, it is equally valid for the sum of the planning percents to be
less than or greater than 100%.
Planning Bill of Material for Training Computer
Level
Item Description
Planning %
Training Computer
Planning
--
Level
Item Description
Planning %
.2
. Laptop Computer
Model
60
.2
. Desktop Computer
Model
20
.2
. Server
Model
20
The following table illustrates forecast explosion, via the planning bill described in the
previous table, for a forecast of 100 Training Computers. The table also illustrates
forecast consumption after you place sales order demand for 20 Laptop Computers.
Original forecast shows forecast quantities before forecast consumption. Current
forecast shows forecast quantities after consumption by sales order demand.
Forecast Explosion and Forecast Consumption
Level
Item Description
Original Forecast
Current Forecast
Training Computer
100
100
.2
. Laptop Computer
60
40
.2
. Desktop Computer
20
20
.2
. Server
20
20
Forecasting Models
You can define model and option class bills, with multiple levels of option classes,
options, and mandatory components, to represent your complex configure-to-order
products in Oracle Bills of Material. You can then use forecast explosion to explode
model and option class forecasts the same way you explode forecasts for planning
items.
The logic for exploding models and option classes is the same as the logic used to
explode planning items.
Model Bills
The following table illustrates a model bill for Laptop Computer, a model that includes
two mandatory components and three option classes. The planning percent assigned to
optional option classes represents anticipated demand for the option class. In this
example, 90% of Laptop Computers are expected to be sold with an operating system,
and the remaining 10% are expected to be sold without.
Model Bill for Laptop Computer
Level
Item
Description
Optional
Planning %
.2
. Laptop
Computer
Model
No
60
..3
. . Carrying Case
Standard
No
100
..3
. . Keyboard
Standard
No
100
..3
. . Processing
Unit
Option Class
No
100
..3
. . Monitor
Option Class
No
100
..3
. . Operating
System
Option Class
Yes
90
Item
Description
Optional
Planning %
..3
. . Monitor
Optiion Class
No
60
Level
Item
Description
Optional
Planning %
...4
. . . VGA
Option Class
Yes
100
....5
. . . . VGA
Manual
Standard
No
100
....5
. . . . VGA1
Standard
Yes
100
....5
. . . . VGA2
Standard
Yes
100
...4
. . . EGA
Option Class
Yes
90
Overview of Forecasting
subassemblies, your options and mandatory components, since they are the highest
level buildable items in your model bills.
Although models, option classes, and product families are not buildable items, you may
want to master schedule them so that you can calculate available-to-promise (ATP)
information for promising order ship dates by model, option class, or product family.
You might also want to master schedule your models option classes, and product
families so that you can perform rough-cut capacity checks by model, option class, and
product family. This is particularly valid when different configurations of your models
have very similar capacity requirements.
Note: Oracle MRP does not support planning for pick-to-order models
For product family member items that have forecast control set to None, the planning
process explodes and passes the demand down to the member items based on the
product family allocation percentage. Since forecast control set to None means that the
item is not forecasted, demand for an item whose forecast control is set to None gets
passed down during the planning process. Thus, the resulting explosion is independent
of the quantity of existing sales orders for member items.
10
Repetitive Planning
Anchor Date
You can define a repetitive anchor date to stabilize the repetitive planning process
during subsequent planning runs within the same repetitive planning period.
Component Demand
You can pass demand down from repetitive assemblies to repetitive components, from
repetitive assemblies to discrete components and from discrete assemblies to repetitive
components.
a daily quantity
a start date
an end date
The first unit start date (FUSD) represents the date you plan to start production of the
first assembly on a repetitive schedule.
The last unit start date (LUSD) represents the date you plan to start production of the
last assembly on a repetitive schedule.
The first unit completion date (FUCD) represents the date you plan to complete
production of the first assembly on a repetitive schedule.
The last unit completion date (LUCD) represents the date you plan to complete
production of the last assembly on a repetitive schedule.
The difference between the FUSD and the FUCD represents the lead time of a repetitive
assembly, and is the amount of time that it takes to complete a single unit of the
assembly from start to finish. Oracle Work in Process calculates the lead time based on
the routing for lines with a lead time basis of Routing based. Oracle Work in Process
defaults the lead time from the production line for repetitive schedules on production
lines with a lead time basis of Fixed.
The difference between the FUSD and the LUSD represents the repetitive processing
days for your repetitive schedule. These are the number of days you plan to work on
your repetitive schedule.
Current aggregate repetitive schedules represent the sum of all current work in process
repetitive schedules for repetitive assemblies, across all production lines, for a specified
period. Current aggregate repetitive schedules are defined as an assembly, a daily
quantity, a start date and an end date.
Current repetitive schedules are a portion of current aggregate repetitive schedules.
They represent individual work in process repetitive schedules producing repetitive
assemblies on a single production line. Current repetitive schedules are defined as an
assembly, a daily quantity, a start date, an end date, and a production line.
Suggested aggregate repetitive schedules represent the optimal repetitive schedules
suggested by the repetitive planning process to satisfy the total demand for repetitive
assemblies within a given period. They represent suggested total production across all
production lines.
Suggested repetitive schedules are a portion of suggested aggregate repetitive
schedules. They represent individual suggested repetitive schedules producing
repetitive assemblies on a single production line. The repetitive planning process
generates suggested repetitive schedules during the repetitive schedule allocation
process. See: Repetitive Schedule Allocation.
The repetitive planning process calculates optimal rates by summing net requirements
for each repetitive assembly within each repetitive planning period. An average daily
demand is calculated by dividing the total demand for the period by the total number
of workdays within the same period. The repetitive planning process recommends an
optimal rate that matches the average daily demand.
Component Demand
The repetitive planning process passes down demand, from repetitive assemblies to
repetitive components as daily rates rather than discrete quantities. Component
requirements are offset from using assembly requirements in the same way lead time
offsets are used for discrete assemblies and components in discrete planning.
The following diagram illustrates how component demand is passed down as a rate.
Notice that when component requirements are offset from using assembly requirements
by the assembly lead time, the component demand can sometimes span multiple
planning periods. This can result in multiple suggested daily rates that differ from the
original demand rate.
Safety Stock
You can specify safety stock days, together with safety stock percent, as item attributes
using the Define Item window in Oracle Inventory. For discretely manufactured items,
the planning process calculates the safety stock quantity by multiplying the safety stock
percent by the average gross requirements for the period of time defined by the safety
stock days.
For repetitively manufactured items, the repetitive planning process multiplies the
safety stock percent by the average daily demand for each repetitive planning period.
The repetitive planning process calculates the safety stock quantity for each repetitive
period across the planning horizon.
Order modifiers for repetitive assemblies work in a similar way to order modifiers for
discrete assemblies.
Anchor Date
The anchor date introduces consistency into your material and distribution plans by
stabilizing your repetitive planning periods. The anchor date represents the start date of
your first repetitive planning period. The anchor date fixes your repetitive planning
periods as time passes so that a plan run on any day during the first planning period
does not see fluctuating average daily demand.
Without the anchor date, the planning periods shift each day and individual demands
can move from one planning period into the next. This can result in different average
daily demands and therefore different suggested daily rates.
Note that the actual demand never changes, it is only the time periods over which they
are averaged that move each day.
The anchor date must lie on or before the current date and is defined both manually
and automatically. You can manually enter a default anchor date as a planning
parameter. You can override the default anchor date when you plan material
requirements or when you plan your master schedules. Since the anchor date is a
system parameter, overriding the anchor date resets the system anchor date. Resetting
the anchor date always triggers a recalculation of the repetitive planning periods.
The anchor date is automatically updated to the beginning of the current planning
period when the current date moves out of a prior planning period. The anchor date is
also automatically updated when you plan material requirements, plan your master
schedules or change your repetitive planning parameters. This allows your planning
periods to be automatically rolled forward as time passes. The anchor date is always
updated to the start date of the current repetitive planning period.
Line Priorities
In the example, lines A and B have the same line priority, 1, while line C has a line
priority of 2. You assign line priorities to help the repetitive planning process decide
which lines it should allocate repetitive schedules to. In the example, you may have
customized lines 1 and 2 to manufacture your assembly with minimum waste and
optimum speed. It may be possible, but more expensive, to also build the assembly on
line C, so you assign it a lower priority.
Production Rates
You define production rates to represent the rate at which an assembly can be
manufactured on specific production lines. Different assemblies may require different
production rates on the same production line. Similarly, the same assembly may require
different production rates on different production lines. The production rate for an
assembly, on a given production line, must fall within the minimum and maximum
hourly rates defined for the production line in the Oracle Work in Process window,
Define Production Line. The example assumes production rates of 400/hour, 200/hour
and 100/hour for lines A, B and C, respectively.
previous depletion in supply caused by the firm rate being less than the optimal rate. If
the optimal rate was less than the firm rate, the repetitive planning process decreases
the suggested rate after the firm period in response to the previous build up of supply.
As an example, the repetitive planning process is 10 units short as a result of the firm
rate. The optimal rate is 12/day. However, for the duration of the firm schedule, the
suggested rate is restricted to 10/day. This creates a shortage of 2/day for 5 days,
resulting in a total shortage of 10 units. This increases the total demand in the next
planning period from 36 to 46 units. The firm schedule breaks up two planning periods
(Periods 2 and 3) into four smaller planning periods (Periods 2, 3, 4, and 5).
After the assembly lead time, the suggested rate is increased to address the previous
depletion in supply caused by the current aggregate rate being less than the optimal
rate. The firm schedule formed by the assembly lead time breaks the first planning
period into two smaller planning periods.
to the optimal rate. Using the same example, the repetitive planning process suggests a
daily rate equal to the optimal rate for any optimal rate between 100/day and 110/day.
Overrun Percent
You can also use the overrun percent item attribute to control the nervousness of your
material plans by allowing current repetitive schedules to overbuild by a small amount
without incurring new suggested daily rates. In this way, planning overrun amounts
reduces minor and unnecessary rate change suggestions.
The overrun amount is equal to the optimal rate for the planning period multiplied by
the overrun percent. For example, if your optimal rate is 100/day and your overrun
percent is 10%, the repetitive planning process calculates an overrun amount of 10/day.
The repetitive planning process only recommends a new repetitive schedule if the
current aggregate rate is greater than the optimal rate plus the overrun percent.
According to the previous example, the repetitive planning process only suggests a new
repetitive schedule if the current aggregate rate is greater than 110/day.
The overrun percent for repetitive planning is analogous to acceptable early days
delivery in discrete planning. Both attributes allow you to make the business decision
that you would prefer to carry additional inventory for a short time, rather than disrupt
your shop floor production schedules.
It is important to note that the overrun percent only applies for overproduction. As with
acceptable early days delivery, the repetitive planning process allows you to build
ahead and carry excess inventory, but does not allow you to plan a shortage. Because
the overrun percent often results in overproduction within planning periods, use of this
attribute can sometimes have an impact on subsequent planning periods. Later periods
may need to produce less as a result of the excess supply produced in earlier periods.
11
Reports
Overview of Reports
This section explains how to submit report requests and briefly describes each MRP
report. For additional information on capacity reports and processes, see Reports, Oracle
Capacity User Guide.
Report Submission
In the Submit Requests window, enter Audit Information Report in the Name field.
Report Parameters
Show
Reports 11-1
Application
Audit
Bills that are buy items: Identify bills that have an item
planning attribute of Buy.
Bills that do not exist in the item master: Identify bills that
do not exist in the item master.
Bills with BOM enabled flag set to No: Identify bills that
have their BOM enabled flag set to No.
Forecasted items that are not planned and are not planning
items or models: Identify forecasted items that are not
planned and are not planning items or models.
Reports 11-3
Items that are planned as make but are not made in WIP:
Identify items that have an item planning attribute of
Make but are not buildable in work in process.
Items that are planned but not in the planning category set:
Identify items that are planned but are not in the
planning category set.
Planned items with zero full lead time: Identify MPS and
Reports 11-5
Summary
Schedule date rows with sales order orig that have null
source sales order id: Identify schedule date rows with
sales order origination that do not have a source sales
order identifier.
No: Report a list of the items that match your audit. For
example, if you entered All audits in the Audit field,
Oracle MRP prints a list of the items that are discretely
planned, but have a schedule entry with a start date, a
rate, and an end date.
Yes: Report a list of the items that match your audit and
can cause your concurrent program to fail, and a count
of the items that match your audit that does not cause
your concurrent program to fail, but is still
questionable data. For example, if you entered All
audits in the Audit field, Oracle MRP prints a list of the
items that are discretely planned, but have a schedule
entry with a start date, a rate, and an end date. It also
prints a count of the items that are not planned.
Related Topics
Overview of Concurrent Processing, Oracle Applications Developer's Guide
Report Submission
In the Submit Requests window, enter Current Projected On Hand vs. Projected
Available Graphical Report in the Name field. Supply Chain Planning users should
enter Supply Chain Current Projected On Hand vs. Projected Available Graphical
Report in the Name field.
Report Parameters
Plan Name
Reports 11-7
organization.
First Sort
Second Sort
Select the second sort type for the item. Items are sorted by
the First Sort type and then by this sort type within the first
type.
Note: If you choose No sort here, the
Third Sort
Select the third sort type for the item. Items are sorted by
the First Sort type, then by the Second Sort type within the
first type, and finally by this sort type within the second
type.
For example, if you choose Planner as the First Sort type,
Category as the Second Sort type, and Inventory item as
the Third Sort type, the report is sorted by planner, then by
material category within planner, and finally by inventory
item within material category.
Note: If you choose No sort here, Oracle
Exception Type
Item has past due orders: Report all items that have past
due orders.
Planner
Buyer
Items From/To
Category Set
Categories From/To
Reports 11-9
ABC Class
Related Topics
Submitting a Request, Oracle Applications User's Guide
Report Submission
In the Submit Requests window, enter Demand vs. Replenishment Graphical Report in
the Name field. Supply Chain Planning users should enter Supply Chain Demand vs.
Replenishment Graphical Report in the Name field.
Report Parameters
Plan Name
Organization Selection
First Sort
Second Sort
Select the second sort type for the item. Oracle MRP sorts
the items by the first sort type and then by this sort type
within the first type.
If you choose No sort, the report is sorted by using just the
First Sort type.
Third Sort
Select the third sort type for the item. Oracle MRP sorts the
items by the first sort type, then by the second sort type
within the first type, and finally by this sort type within the
second type.
For example, if you choose Planner as the first sort type,
Category as the second sort type, and Inventory item as the
third sort type, the report is sorted by planner, then by
material category within planner, and finally by Inventory
item within material category.
If you choose No sort, the report is sorted by using just the
first and second sort types.
Exception Type
Reports 11-11
Item has past due orders: Report all items that have past
due orders.
Planner
Buyer
Items From/To
Category Set
Categories From/To
ABC Class
Related Topics
Submitting a Request, Oracle Applications User's Guide
This report also shows projected inventory turnover for each period and cumulative,
defined as the average inventory value divided by the master schedule value (which
approximates cost of sales).
Important: All calculations include asset items held in nettable expense
Report Submission
In the Submit Requests window, enter Financial Analysis Report in the Name field.
Supply Chain Planning users should enter Supply Chain Financial Analysis report in
the Name field.
Report Parameters
Plan Name
Organization Selection
Reports 11-13
organization.
Periods
Weeks
Cost Type
Related Topics
Submitting a Request, Oracle Applications User's Guide
Report Submission
In the Submit Requests window, enter Forecast Comparison Report in the Name field.
Report Parameters
Forecast Name
First Quantities
Second Organization
Second Quantities
Periods
Weeks
Reports 11-15
Include Costs
First Sort
Second Sort
Select the second sort type for the item. Items are sorted by
the First Sort type and then by this sort type within the first
type.
For example, if you choose Planner as the first sort type and
Category as the second sort type. Oracle MRP sorts the
report by planner, and then by material category within
planner.
Note: If you choose No sort here, the reort
Select the third sort type for the item. Oracle MRP sorts the
items by the first sort type, then by the second sort type
within the first type, and finally by this sort type within the
second type.
For example, if you choose Planner as the first sort type,
Category as the second sort type, and Inventory item as the
third sort type, the report is sorted by planner, then by
material category within planner, and finally by Inventory
item within material category.
If you choose No sort, the report is sorted by using just the
first and second sort types.
Planner
Buyer
Items From/To
Category Set
Categories From/To
Reports 11-17
ABC Class
Related Topics
Submitting a Request, Oracle Applications User's Guide
the period multiplied by the periods per year. The demand for the
period is the sum of the demand for up to one year. If there is more
than one year of demand, then it is not included in the calculation. The
period is the length of time between the plan date and the last demand
date. If there is more than one year of demand, then the period is one
year.
Report Submission
In the Submit Requests window, enter Forecast Detail Report in the Name field.
Report Parameters
Forecast Name
Quantities
Display
Enter a report start date from which Oracle MRP prints the
forecast. This restricts the information in the vertical
display and the detail sections of the report.
Periods
Weeks
Include Costs
Reports 11-19
First Sort
Second Sort
Select the second sort type for the item. Items are sorted by
the First Sort type and then by this sort type within the first
type.
For example, if you choose Planner as the first sort type and
Category as the second sort type. Oracle MRP sorts the
report by planner, and then by material category within
planner.
Note: If you choose No sort here, the
Select the third sort type for the item. Oracle MRP sorts the
items by the first sort type, then by the second sort type
within the first type, and finally by this sort type within the
second type.
Buyer
Items From/To
Category Set
Categories From/To
ABC Class
Cutoff Date
Related Topics
Submitting a Request, Oracle Applications User's Guide
Report Submission
In the Submit Requests window, enter Late Order Report in the Name field. Supply
Chain Planning users should enter Supply Chain Late Order Reports in the Name field.
Reports 11-21
Report Parameters
Plan Name
Enter a plan name.
Organization Selection
Select the planned organization (all or current) if this is a supply chain report. You can
select All Organizations for a multi-org plan if you are working in the organization that
owns the plan; otherwise, you can select only the current organization and report past
due information pertaining to the current organization.
Advance Notice Date
Enter a date to report the events that will be late as suggested by the planning process.
For example, if it is 11-JAN and you enter 15-JAN, the events that will be late within the
next 5 days (before 15-JAN) are reported. When you choose the current date, all events
that will be late as of tomorrow are reported; in other words, those orders that require
some action today.
Sort
Select one of the following options:
ABC class Sort items first by ABC class.
Buyer Sort first by buyer.
Category Sort first by material category.
Inventory item Sort first by inventory item.
No sort Do not employ a first sort for the report.
Organization Sort first by organization.
Planner Sort first by planner.
Planner
Select a planner to report only orders associated with this planner.
Buyer
Select a buyer to report only orders associated with this buyer.
Items From/To
To restrict the report to a range of items, enter the beginning and ending item numbers.
Category Set
Select a category set. Oracle MRP reports forecast entries associated with this category
set.
Categories From/To
To restrict the report to a range of categories, enter the beginning and ending category
names.
ABC Assignment Group
Select an ABC assignment group. Oracle MRP reports past due orders associated with
this ABC assignment group.
ABC Class
Select an ABC class associated with the ABC assignment group.
Categories From/To
ABC Assignment Group
See Also
Submitting a Request, Oracle Applications User's Guide
Current: Report the current version of the master demand or master production
schedule. When you first define a schedule, Oracle MRP creates a current version
and an original version that are identical. As you add new schedule entries, these
entries are added to both versions, keeping them consistent/ However, when you
change existing schedule entries, only the current schedule is updated.
Last submitted to MPS/MRP: Report the version of the schedule you last submitted
to the MRP or MPS. When you run the MRP or MPS, the current version is copied
to this version and is used as input to the planning process. After the MRP or MPS
is run, this version of the schedule is saved so that you can compare it to the
original version or to any changes you make to the new current version.
Reports 11-23
Original: Report the original version of the schedule. As noted, Oracle MRP only
updates this version when you add new entries to the schedule. Updates to existing
scheduling entries do not affect this version.
Second Organization: Select the organization of the second master schedule to compare
to the master schedule from your current organization.
Second Schedule: Select a master schedule to compare its schedule quantities to the first
schedule name. You can only choose a schedule of the same type as the first schedule
name.
Second Schedule Version
Current: Use the current version of the master demand or master production
schedule. When you first define a schedule, Oracle MRP creates a current version
and an original version that are identical. As you add new schedule entries, these
entries are added to both versions, keeping them consistent/ However, when you
change existing schedule entries, only the current schedule is updated.
Last submitted to MPS/MRP: Report the version of the schedule you last submitted
to the MRP or MPS. When you run the MRP or MPS, the current version is copied
to this version and is used as input to the planning process. After the MRP or MPS
is run, this version of the schedule is saved so that you can compare it to the
original version or to any changes you make to the new current version.
Original: Use the original version of the schedule. As noted, Oracle MRP only
updates this version when you add new entries to the schedule. Updates to existing
scheduling entries do not affect this version.
Second Quantities:
Report Start Date: Enter a report start date from which Oracle MRP prints the master
schedule comparison.
Periods: Select one of the following options:
Weeks: Enter the number of weeks. The number of weeks you choose, together with the
number of periods you choose, determines how many weeks and how many months
that display in the horizontal time-phased plan. For example, if you choose 24 as the
time Period and 10 as the number of weeks, 10 of these periods display as weeks, the
remaining 14 as months.
The number of weeks that displays in the List of Values is based on the workday
calendar and corresponds to the end of the working periods. For example, if you choose
12 as the time Period and it is the third week of a four week period calendar, Oracle
MRP calculates the number of weeks to the end of each period and displays the valid
List of Values Options as, 1, 5, and 9 weeks.
Include Costs: Select one of the following options:
No: Report the comparison information by units rather than value (standard cost
times units).
Yes: Report the comparison information by value (standard cost times units) in
addition to units.
No: Do not display forecast entries, bucketed in the first bucket, before the start date
you enter.
Yes: Display forecast entries, bucketed in the first bucket, before the start date you
enter.
First Sort: Select one of the following options. The report sorts items first in this order,
then in the order you specify for the second and third sort:
Second Sort: Select the second sort type for the item. Items are sorted by the First Sort
Reports 11-25
type and then by this sort type within the first type. For example, if you choose Planner
as the first sort type and Category as the second sort type. Oracle MRP sorts the report
by planner, and then by material category within planner.
Third Sort: Select the third sort type for the item. Oracle MRP sorts the items by the first
sort type, then by the second sort type within the first type, and finally by this sort type
within the second type. For example, if you choose Planner as the first sort type,
Category as the second sort type, and Inventory item as the third sort type, the report is
sorted by planner, then by material category within planner, and finally by Inventory
item within material category. If you choose No sort, the report is sorted by using just
the first and second sort types.
Planner: Select a planner to report master schedule entries associated with this planner.
Buyer: Select a buyer to report master schedule entries associated with this buyer.
Items From/To: To restrict the report to a range of items, enter the beginning and
ending item numbers.
Category Set: Select a category set. Oracle MRP reports forecast entries associated with
this category set.
Categories From/To: To restrict the report to a range of categories, enter the beginning
and ending category names.
ABC Assignment Group: Select an ABC assignment group. Oracle MRP reports master
schedule entries associated with this ABC assignment group.
ABC Class: Select an ABC class associated with the ABC assignment group.
See also Submitting a Request in Oracle Applications User's Guide.
the period multiplied by the periods per year. The demand for the
period is the sum of the demand for up to one year. If there is more
than one year of demand, then it is not included in the calculation. The
period is the length of time between the plan date and the last demand
date. If there is more than one year of demand, then the period is one
year.
Report Submission
In the Submit Requests window, enter Master Schedule Detail Report in the Name field.
Report Parameters
Schedule Name
Select a schedule name.
Schedule Version
Select one of the following options:
CurrentReport the current version of the master demand or master production schedule.
Note: When you first define a schedule, Oracle MRP creates a current
version and an original version that are identical. As you add new
schedule entries, these entries are added to both versions, keeping them
consistent. However, when you change existing schedule entries, only
the current schedule is updated.
Last submitted to MPS/MRP Report the version of the schedule you last submitted to the
MRP or MPS.
Note: When you run the MRP or MPS, the current version is copied to
this version and is used as input to the planning process. After the MRP
or MPS run, this version of the schedule is saved so that you can
compare it to the original version or to any changes you make to the
new current version.
OriginalReport original version of the schedule. As noted, Oracle MRP only updates this
version when you add new entries to the schedule. Updates to existing scheduling
entries do not affect this version.
Quantities
Select one of the following options:
Current: Print master schedule comparison information using current master schedule
quantities.
Original: Print master schedule comparison information using original master schedule
quantities.
Display
Select one of the following options:
Both horizontal and vertical Display the forecast as a horizontal timephased and vertical
listing. The horizontal timephased listing displays the future forecast requirements,
Reports 11-27
from today forward to the cutoff date, bucketed for the periods and number of weeks
you specify. The vertical listing displays the past (historical) forecast requirements in
detail up to the cutoff date.
Horizontal time phased: Display the forecast as a horizontal timephased listing.
Vertical: Display the forecast as a vertical listing.
Report Start Date
Enter a report start date from which Oracle MRP prints the master schedule
comparison.
Periods
Select one of the following options:
12: Report the forecast for 12 periods.
24: Report the forecast for 24 periods.
36: Report the forecast for 36 periods.
48: Report the forecast for 48 periods.
Weeks
Enter the number of weeks. The number of Weeks you choose, together with the
number of Periods you choose, determines how many weeks and how many months
that display in the horizontal time-phased plan.
For example, if you choose 24 as the time Period and 10 as the number of Weeks, 10 of
these periods display as weeks, the remaining 14 as months.
Note: The number of weeks that displays in the List of Values is based
Include Costs
Select one of the following options:
No: Report the comparison information by units rather than value (standard cost times
units).
Yes: Report the comparison information by value (standard cost times units) in addition
to units.
Include Before Start Date
Select one of the following options:
No: Do not display forecast entries, bucketed in the first bucket, before the start date
you enter.
Yes: Display forecast entries, bucketed in the first bucket, before the start date you enter.
First Sort
Select one of the following options. The report sorts items first in this order, then in the
order you specify for the second and third sort.
ABC Class: Sort items first by ABC class.
Buyer:Sort first by buyer.
Category: Sort first by material category.
Inventory Item: Sort first by inventory item.
No Sort: Do not employ a first sort for the report.
Planner: Sort first by planner.
Second Sort
Select the second sort type for the item. Items are sorted by the First Sort type and then
by this sort type within the first type.
For example, if you choose Planner as the first sort type and Category as the second sort
type. Oracle MRP sorts the report by planner, and then by material category within
planner.
Note: If you choose No sort here, the report is sorted using just the First
Sort type.
Third Sort
Select the third sort type for the item. Oracle MRP sorts the items by the first sort type,
then by the second sort type within the first type, and finally by this sort type within the
second type.
For example, if you choose Planner as the first sort type, Category as the second sort
type, and Inventory item as the third sort type, the report is sorted by planner, then by
material category within planner, and finally by Inventory item within material category.
If you choose No sort, the report is sorted by using just the first and second sort types.
Planner
Select a planner to report and associate master schedule entries.
Buyer
Select a buyer to report and associate master schedule entries.
Items From/To
To restrict the report to a range of items, enter the beginning and ending item numbers.
Category Set
Reports 11-29
Report Submission
In the Submit Requests window, enter Master Schedule Status Report in the Name field.
Supply Chain Planning users should enter Supply Chain Schedule Status Report in the
Name field.
Report Parameters
Schedule Name
Select a schedule name.
Organization Selection
Select the planned organization (all or current) if this is a supply chain report. You can
select All Organizations for a multi-org plan if you are working in the organization that
owns the plan; otherwise, you can select only the current organization and report
shipping/production activity pertaining to the current organization.
Schedule Version
are identical. As you add new schedule entries, these entries are added
to both versions, keeping them consistent. However, when you change
existing schedule entries, only the current schedule is updated.
Last submitted to Report the version of the schedule you last MPS/MRP submitted to the
MRP or MPS.
Note: When you run the MRP or MPS, the current version is copied to
this version, and is used as input to the planning process. After the
MRP or MPS run, this version of the schedule is saved so that you can
compare it to the original version or to any changes you make to the
new current version.
OriginalReport the original version of the schedule. As noted, Oracle MRP only updates
this version when you add new entries to the schedule. Updates to existing scheduling
entries do not affect this version.
Start Date
Enter a past or the current date to report activity for the schedule name, for the day,
week, and month, beginning on this date.
Periods
Select one of the following options:
12: Report the forecast for 12 periods.
24: Report the forecast for 24 periods.
36: Report the forecast for 36 periods.
48: Report the forecast for 48 periods.
Weeks
Enter the number of weeks. The number of Weeks you choose, together with the
number of Periods you choose, determines how many weeks and how many months
that display in the horizontal time-phased plan.
For example, if you choose 24 as the time Period and 10 as the number of Weeks, 10 of
these periods display as weeks, the remaining 14 as months.
Note: The number of weeks that displays in the List of Values is based
Reports 11-31
third week of a four week period calendar, Oracle MRP calculates the
number of weeks to the end of each period and displays the valid List
of Values options as 1, 5, and 9 weeks.
Sort
Select one of the following options:
Category: Report activity by category and then by inventory item within the category.
Inventory item: Report activity by inventory item.
Items From/To
To restrict the report to a range of items, enter the beginning and ending item numbers.
Category Set
Select a category set. Oracle MRP reports forecast entries associated with this category
set.
Categories From/To
To restrict the report to a range of categories, enter the beginning and ending category
names.
See
Submitting a Request, Oracle Applications User's Guide
Process Submission
In the Submit Requests window, enter Planning Manager Worker (once-a-day tasks) in
the Name field. See: Submitting a Request, Oracle Applications User's Guide.
Report Submission
In the Submit Requests window, enter Planning Parameters Report in the Name field.
See: Submitting a Request, Oracle Applications User's Guide.
Report Submission
In the Submit Requests window, enter Planning Parameters Report in the Name field.
See: Submitting a Request, Oracle Applications User's Guide.
CRP Reports
You can launch the following reports from MRP modules:
The CRP Rate Based Report shows a breakdown of required rate coming from four
possible sources: planned orders, non-standard jobs, discrete jobs, and repetitive
schedules. The RCCP Rate Based Report does not contain this detail information.
Because RCCP by nature is an estimate of resources required, a detailed breakdown of
required rate is not included in the report.
Report Submission
In the Submit Requests window, enter Order Reschedule Report in the Name field.
Supply Chain Planning users should enter Supply Chain Order Reschedule Report in
the Name field.
Report Parameters
Plan Name
Select a plan name.
Reports 11-33
Order Type
Select one of the following options:
All: Report all discrete jobs, purchase orders, and purchase requisitions the MRP or
MPS planning process recommends to reschedule.
Discrete job: Report the discrete jobs the MRP or MPS planning process recommends to
reschedule.
Purchase order: Report the purchase orders the MRP or MPS planning process
recommends to reschedule.
Purchase requisition Report the purchase requisitions the MRP or MPS planning process
recommends to reschedule.
Sort
Select one of the following options:
ABC class Sort the orders by item within an ABC class.
Buyer Sort the orders by item within a buyer.
You can choose this option only if you specified
Purchase order or Purchase requisition as the Order Type.
Category
Inventory item
Order number
Organization
Planner
Supplier
In Days Filter
Enter the number of reschedule in days to filter entries that are displayed on the report.
Use 0 days to allow the planning process to report all orders suggested to be
rescheduled.
Oracle MRP compares the current purchase or the work in process due date with the
suggested due date. It uses reschedule in days when the purchase or the work in
process due date is later than the suggested due date. If the difference between the
purchase or the work in process due date and the suggested due date is less than or
equal to the reschedule in days, the reschedule report excludes those orders.
For example, if the suggested due date is 01-JUN, the purchase order date is 04-JUN
and you specify 3 or more, the reschedule report excludes the purchase order. When
you specify 2 or less, the reschedule report includes the purchase order.
Planner
Select a planner to report orders associated with this planner.
Buyer
Select a buyer to report orders associated with this buyer.
Items From/To
To restrict the report to a range of items, enter the beginning and ending item numbers.
Reports 11-35
Category Set
Select a category set. Oracle MRP reports forecast entries associated with this category
set.
Categories From/To
To restrict the report to a range of categories, enter the beginning and ending category
names.
ABC Class
Select an ABC class associated with the ABC assignment group.
Cutoff Type
Select one of the following options:
Dock date: Report all orders whose dock date is before the cutoff date.
Note: Use this option if your processing and post-processing lead times
Due date: Report all orders whose due date is before the cutoff date.
Order date: Report all orders whose order date is before the cutoff date.
Start date: Report all orders whose start date is before the cutoff date.
Cutoff Date
Select the cutoff date to report orders with a new dock, due, or order date up to and
including this date.
See Also
Submitting a Request, Oracle Applications User's Guide
Report Submission
In the Submit Requests window, enter Planned Order Report in the Name field. Supply
Chain Planning users should enter Supply Chain Planned Order Reports in the Name
field.
Report Parameters
Plan Name (Required): Select a plan name.
Oracle Inventory.
Reports 11-37
Planner (Optional)
Select a planner to report only items associated with this planner.
Buyer (Optional)
Select a buyer to report only items associated with this buyer.
Items From/To (Optional)
To restrict the report to a range of items, enter the beginning and ending item numbers.
Category Set (Optional, Default)
Select a category set. Oracle MRP reports forecast entries associated with this category
set.
Categories From/To (Optional)
To restrict the report to a range of categories, enter the beginning and ending category
names.
ABC Assignment Group (Optional)
Select an ABC assignment group to reports associated planned orders.
ABC Class (Optional)
Select an ABC class associated with the ABC assignment group.
Cutoff Type (Required, Default)
Select one of the following options:
Dock Date: Report all planned orders whose dock date is before the cutoff date. Use this
option if your processing and postprocessing lead times are long and you want to
reduce the number of items reported.
Due Date: Report all planned orders whose due date is before the cutoff date.
Order Date: Report all planned orders whose order date is before the cutoff date.
Start Date: Report all planned orders whose start date is before the cutoff date.
Cutoff Date
(Required, Default)
Select the cutoff date to report new planned orders with a suggested dock, due, order,
or start date up to and including this date.
See Also
Submitting a Request, Oracle Applications User's Guide
percentage, if any, that you defined for the item. For non-MRP planned
safety stock, Oracle MRPdoes not print the safety stock percentage,
since the safety stock could be time phased. Information regarding
MRP and non-MRP Planned safety stock appears in the Horizontal
Listing section.
quantity.
The demand for the period is the sum of the demand for up to one year. If there is more
than one year of demand, it is not included in the calculation.
Report Submission
In the Submit Requests window, enter Planning Detail Report in the Name field. Supply
Chain Planning users should enter Supply Chain Planning Detail Reports in the Name
field.
Report Parameters
Plan Name
Select a plan name.
Reports 11-39
Organization Selection
Select the planned organization (all or current) if this is a supply chain report. You can
select All Organizations for a multi-org plan if you are working in the organization that
owns the plan; otherwise, you can select only the current organization and report
planning information pertaining to the current organization.
Vertical Display
Select one of the following options:
Detail Display
Select one of the following options:
No: Display vertical and horizontal listings only.
Yes: Display vertical and horizontal listings and detail sections showing gross
requirements, scheduled receipts, planned orders, bill of material and engineering
changes, repetitive schedules, substitute items, expired lot and by product information.
Periods
Select one of the following options:
12
24
36
48
Weeks
Enter the number of weeks. The number of Weeks you choose, together with the
number of Periods you choose, determines how many weeks and how many months
that display in the horizontal time-phased plan.
For example, if you choose 24 as the time Period and 10 as the number of Weeks, 10 of
these periods display as weeks, the remaining 14 as months.
Note: The number of weeks that displays in the List of Values is based
First Sort
Select one of the following options. The report sorts items first in this order, then in the
order you specify for the second and third sort.
Second Sort
Select the second sort type for the item. Items are sorted by the First Sort type and then
by this sort type within the first type.
For example, if you choose Planner as the first sort type and Category as the second sort
type, Oracle MRP sorts the report by planner, and then by material category within
planner.
Note: If you choose No sort here, the report is sorted using just the First
Sort type. If you choose No sort, the report is sorted by using just the
First Sort type.
Third Sort
Select the third sort type for the item. Oracle MRP sorts the items by the first sort type,
then by the second sort type within the first type, and finally by this sort type within the
second type.
Reports 11-41
For example, if you choose Planner as the first sort type, Category as the second sort
type, and Inventory item as the third sort type, the report is sorted by planner, then by
material category within planner, and finally by Inventory item within material category.
If you choose No sort, the report is sorted by using just the first and second sort types.
Buyer
Select a buyer to report only items associated with this buyer.
Items From/To
To restrict the report to a range of items, enter the beginning and ending item numbers.
Category Set
Select a category set. Oracle MRP reports forecast entries associated with this category
set.
Categories From/To
To restrict the report to a range of categories, enter the beginning and ending category
names.
ABC Class
Select an ABC class associated with the ABC assignment group.
Include Phantoms
Indicate whether to include phantoms in the report.
Cutoff Date
Select a cutoff date up to which you want to display the DRP, MRP or MPS plan. This
restricts the information in the vertical display and the detail sections of the report.
See Also
Submitting a Request, Oracle Applications User's Guide
Report Submission
In the Submit Requests window, enter Planning Exception Sets Report in the Name
field. See: Submitting a Request, Oracle Applications User's Guide
Reports 11-43
12
Kanban Planning
Kanban Terminology
The following terminology describes features or processes in a manufacturing
environment using kanbans.
Actual Production
Actual production refers to the discrete jobs, repetitive schedules, and flow schedules
that are scheduled to be produced on the manufacturing line. Actual production is one
of the demand types used in the Kanban Names window for calculating the kanban size
or number of cards.
Flow Manufacturing
A kanban system is most effective in flow shops manufacturing organizations with
well-defined material flows. Because the demand for customer-order items may be
discontinuous even in a shop where the material demand is steady, you might want to
only designate certain items as kanban items.
Kanban
The term kanban refers to a visual replenishment signal such as a card or an empty bin
for an item. In a kanban system, each work center has several bins, each containing a
certain number of the same item. When a bin becomes empty, the work center starts the
process of replenishing the empty bin by sending the replenishment signal, or a kanban.
Meanwhile, the work center can continue using the other (stocked) bins.
Kanban Cards
Kanban cards are the visual replenishment signals. Each kanban bin has one kanban
card, so the number of kanban cards is the same as the number of kanbans for each
item. Thus, if a work center must have 100 of the same kanban item within the
replenishment lead time, and the kanban size is 20, there must be five kanbans for the
item five kanban cards.
Kanban Items
An item that is pulled through the kanban system, rather than pushed by the planner, is
called a kanban-released item, or simply kanban item. Your planning system can have
kanban items as well as items released by the planner.
Kanban Location
The kanban location for a kanban item is the designated location where that item is
stored (and where replenishment is delivered). You can designate location as a
combination of subinventory and locator. You can use locators on kanbans even if the
locator control is off.
Kanban Plans
The kanban plan indicates the number of kanbans and the size of each kanban required
to satisfy the demand for all items that are either kanban released or have components
that have kanban released items on the bill.
Kanban Size
Kanban size refers to the number of items in each kanban. Because a kanban is only
replenished when it's empty, the kanban size should be a multiple of the lot size. For
example, if you would normally order an item in lots of 20, you should not make the
kanban size less than 20 because the supplier would not be able to fulfill such an order.
You can specify the lot size using the lot multiplier on the pull sequences.
Pull Sequences
For every kanban location, there is a pull sequence ? a grouping of information that
defines a kanban location, source data, and planning parameters.
In defining a pull sequence for a kanban item in Oracle Inventory, you specify the
replenishment source for a kanban item at a specific location. You also specify what you
want the kanban calculation program to calculate, the lead time for obtaining the
kanban item, the allocation percentage, and order modifiers that you want to affect the
calculation program.
See Also
Calculation Formula
Calculation Formula
One of the most important tasks of a kanban planning system is determining the
optimal number of kanban cards. The kanban planning software takes care of this
calculation provided you enter correct values for kanban size, average daily demand for
the kanban item, and the lead time to replenish one kanban.
We provide a package that you can use to customize the calculation. See the Oracle
Manufacturing, Distribution, Sales and Service Open Interfaces Manual.
By default, the standard calculation is:
(C - 1) * S = D * A * (L + SSD) where:
If you think through the kanban process, you will see why this formula works best
when the demand for the kanban item is steady.
In addition to this basic formula, when the calculation program calculates kanban size,
it takes into account the values for the following order modifiers (specified in the pull
sequence), in the following order:
Lot Multiplier
For example, suppose you've specified the Minimum Order Quantity for a particular
item to be 50. You want the formula to calculate the kanban size (S), so you enter values
for C and L. Even though strictly based on the values you enter for C and L?the formula
should yield 40, the actual kanban size will be 50 because of the Minimum Order
Quantity. If a Lot Multiplier of 15 is specified, the kanban size is rounded to 60 in oder
to meeth both the Minimum Order Quantity and Lot Multiplier order modifiers.
Note: The program uses order modifiers only when calculating the
kanban size. If you specify the kanban size and want the program to
calculate the number of kanban cards, the program does not use order
modifiers.
It identifies all the kanban items that you want to include in your kanban
calculation, using the parameters you enter when you launch a kanban calculation.
2.
3.
For each kanban item, it identifies every BOM in which the item appears so that it
can explode the demand from the assemblies down to the kanban item.
4.
Using the MDS, MPS, Actual Production, or forecast you specify in the Kanban
Names window - it identifies all the demand entries for each kanban item for which
the demand is independent. For example, suppose that from the forecast you
specified in Kanban Names, the program finds independent demand for 600 of
kanban item A.
5.
It uses the Allocation Percentage specified in the pull sequence for each kanban
item to determine how to distribute demand for the item among its different
locations. For example, if the allocation percentage for item A at location L1 is 20%,
then the program places demand of 120 (that is, 20% of 600) at location L1.
6.
Using the MDS, MPS, Actual Production, or forecast you specify in the Kanban
Names window - it calculates demand for each kanban item for which demand is
dependent on the demand for other items. It does so by using the following
information:
Quantity per Assembly. For example, if there are 2 of kanban item R per one
assembly of item K, and the demand for K is 10, then the demand for R is 20.
Component Yield. The program divides the demand for the child item by that
item's component yield to determine the actual demand for the child item. For
example, if the component yield for item R is 50%, the new demand for R is 40
7.
Reverse Cumulative Yield. The program further divides the demand for the
child item by the Reverse Cumulative Yield (specified in the operation sequence
of the flow routing for the parent item) to determine the actual demand for the
child item. For example, if the reverse cumulative yield for K is 10%, the new
demand for R is 400 (because 40 divided by 10% is 400).
Net Planning Percentage. The program then multiplies the demand for the
child item by the Net Planning Percentage (specified in the operation sequence
of the flow routing for the parent item) to determine the actual demand for the
child item. For example, if the net planning percentage for K is 80%, the new
demand for R is 320 (because 400 multiplied by 80% is 320).
Finally, the program sums up the demand entries that fall within the kanban
planning horizon for each kanban item at each location and divides the demand for
each item at each location by the number of workdays. For example, if the number
of workdays on the planning horizon is 20, then the average daily demand for item
A at location L1 is 6 (because the total demand for item A at location L1 for the
planning horizon is 120). The program prorates the demand from periodic forecasts
for those days between the Demand window specified for the calculation program.
See Also
Oracle Flow Manufacturing Implementation Manual
Prerequisites
Before you can run the kanban calculation program, you must:
Identify the kanban items in the system. See: Defining Kanban Items, Oracle
Inventory User's Guide.
Set up a bill of material for kanban items. See: Creating a Bill of Material, Oracle Bills
of Material User's Guide.
Define the pull sequence for the item. See: Defining Kanban Pull Sequences, Oracle
Inventory User's Guide.
Add kanban location information to either the parent assembly or the kanban item
master.
2.
3.
Enter a description to help you remember what's unique about this simulation plan.
4.
Select an input type to tell the quantity calculation program whether to use the
demand information from a forecast, an MDS, an MPS, or Actual Production.
A list of choices appears in the Forecast/Schedule field.
5.
Select the name of the specific forecast or schedule you want to use.
Choose the Forecast/Schedule button to see more detail about the selected forecast
or schedule. Then navigate back to the Kanban Names window.
6.
Optionally, enter the date on which this simulation plan is to become inactive.
2.
If the window displays more than one plan, choose which plan you want to do the
calculation.
3.
4.
Demand Start Date: the start date on which the demand entries are considered
Cutoff Date: the date up to which ' want demand entries to be considered
5.
6.
In the Launch Kanban window, make optional changes or choose Submit Request
to start the calculation program.
The calculation program uses all the information you entered, including the launch
parameters, the demand information, and the pull sequences, to calculate either the
kanban size or the number of kanban cards. It also takes into account several order
modifiers.
To specify options just before submitting a request for the calculation program:
1.
2.
Specify the options you want. See: Submitting a Request, Oracle Applications User's
Guide.
Note: The concurrent program will complete with a status of
Demand start and cutoff dates are outside the range of data in
your demand schedule.
See Also
Calculation Formula
2.
3.
4.
Choose Find to find all items in the plan or narrow down your search by entering
search criteria. To narrow your search, enter one of the following in the Field field:
Item: if you want to limit your search to only certain kanban items.
Kanban Number: if you want to limit your search to only items within a particular
range of kanban cards (for example, items requiring more than 10 kanban cards).
Kanban Size: if you want to limit your search by kanban size (for example, items
with kanbans that contain between 20 and 100 units).
Locator: if you want to limit your search to only items with a particular locator.
Subinventory: if you want to limit your search to only items with a particular
subinventory location.
Category: if you want to limit your search to only items in a particular category.
Planner: if you want to limit your search to those items planned by a employee
associated to the items.
Variance: if you want to limit your search to only items with a certain variance
percentage from the manually entered plan.
5.
6.
Choose Find to find the items that match the criteria you've entered. The Compare
Kanban Plans window appears.
7.
Notice the variances between your simulation plan and your production plan.
Some items may have higher variances than others. You can decide by item which
parts of the simulation plan to merge with the production plan, updating the
production plan with those parts of the kanban calculation that make sense to you.
Choose the check box next to each item for which you want to update the
production plan with the simulation plan. Then choose Update Production.
2.
3.
4.
Choose Find to find all items in the plan or narrow down your search by entering
search criteria and then choosing Find.
5.
In the window that appears, choose the check box next to each item for which you
want to make an adjustment.
6.
In the Calculate column for each item that you checked, choose what you want to
calculate.
7.
For each item that you checked, scroll to the field whose value you want to change
and enter a new value for the field.
You can change these fields: Kanban Size, # of Kanbans, Source Type.
8.
When you've made all the adjustments you want, choose Simulation Replan.
This button sends a request to the kanban calculation program to generate a new
simulation plan based on the new values you've entered. After the request has been
processed, you'll be able to see the results of the kanban calculation from the
Kanban Workbench, just as you would for any simulation plan.
9.
You can update your plan from these results by selecting pull sequences and
choosing Update Production.
From the Tools menu, select Kanban Cards. You can print kanban cards by
choosing Print Kanban Cards.
See
Using the Kanban Calculation Program
Kanban Tools Menu
Kanban Cards
Print Kanbans
See:
Reviewing Forecast Detail Information Generating Kanban Cards, Oracle Inventory
User's Guide
Printing Kanban Cards, Oracle Inventory User's Guide
13
Project MRP
include project or Seiban numbers and task references in forecast, MPS, and MDS
entries
load, copy, or merge forecast, MPS, and MDS entries with project or Seiban
numbers and task references recognize and allocate supply according to project or
Seiban numbers and task references combine project and Seiban related supply and
demand with nonproject and nonSeiban related supply and demand in the same
plan or schedule perform netting by planning groups, project or Seiban, and tasks
generate planned orders with project or Seiban number and task references execute
a plan (in the Planner Workbench) by project, Seiban, and task link sales order lines,
production orders, and purchase orders to projects, Seibans, and tasks, allocate
onhand inventory to projects, and issue inventory to projects
create a payback transaction as a supply for the lending project, and a demand for
the borrowing project and view these transactions in the Planner Workbench use
model/unit effectivity to create demand and generate planned orders with unit
number specified
See also:
Define projects and tasks in Oracle Projects. This phase is not necessary in a Seiban
environment.
Define subinventories.
To define a project:
1.
2.
To complete this task, refer to Creating a New Project from a Project Template or an
Existing Project, Oracle Projects User's Guide.
See also:
2.
3.
4.
Select a project control level (the project control level determines the level at which
the organization is allowed to control its project activity):
Project: You will be able to associate demand and supply records with project
references, as well as plan at the project level. Task references will be disabled in all
windows.
Task: You will be able to associate demand and supply records with project and task
references, as well as plan at the project level.
See: Defining Default Inventory Parameters, Oracle Inventory User's Guide for
defining additional organization parameters.
2.
3.
4.
In the Planning tabbed region, place your cursor in the Locator field to display the
Stock Locators parameter window.
5.
6.
2.
3.
Soft Pegging:The planning process will allocate supply for a projecttask (or
Seiban) to demand for the projecttask (or Seiban), according to the Reservation
Level set in the plan level options.
All reservations of supply to demand records is for a single item. Common,
nonproject supply is used to satisfy project demand. For a soft pegged item,
excess project supply (or common supply) is always available to another
project's demand.
No project references will be attached to planned orders issued to soft pegged
items.
You can also generate a graphical pegging display in a nonproject environment,
for plans with pegging enabled.
End Assembly Pegging:Also known as Where Used, this option traces the Pegging
end assembly the item is pegged to at the top of the bill of material. Even if you
do not select end assembly pegging, you can still calculate and view end
assemblies online.
You can also generate a graphical pegging display in a nonproject environment,
for plans with pegging enabled.
End Assembly/ Soft Pegging :Choose this option for both soft pegging and end
assembly pegging.
You can also generate a pegging display in a nonproject environment, for plans
with full pegging enabled.
Hard Pegging: The planning process will allocate supply for a projecttask (or
Seiban) to demand for the projecttask (or Seiban), according to the Reservation
Level set in the plan level options.
A hard pegged item will not have access to common, nonproject supply. Excess
supply from one project can only be shared among projects in the same
planning group, provided reservation level is set at planning group.
Project references are attached to planned orders for hard pegged items.
You can also generate a graphical pegging display in a project environment, for
plans with full pegging enabled.
End Assembly/ Hard Pegging:Choose this option for both hard pegging and end
assembly pegging.
You can also generate a graphical pegging display in a project environment, for
plans with full pegging enabled.
None: This option disables project material allocation, end assembly pegging,
and graphics in full pegging.
See: Defining Items, Oracle Inventory User's Guide for defining additional item
attributes. See: Viewing Pegged Supply and Demand for information on full
pegging.
See also:
2.
Place the cursor in the Code field, choose New from the File menu.
3.
4.
5.
Enter a start date, and optionally and end date to restrict the effectivity of the
Lookup.
6.
7.
2.
3.
Check Pegging. This will optionally allow you to set a Reservation Level and a
Hard Pegging Level when in a projects environment. (It will also allow you to
generate a graphical pegging display, if the pegging attribute for your item is not
set to None)
4.
In the Pegging region, set a Reservation Level and (optionally) a Hard Pegging
Level.
Reservation Level: Determine how the planning process will preallocate
project/Seiban supply to project/Seiban demand. This will control only those items
whose item attributes have been set to Soft Pegging, End Assembly/Soft Pegging, Hard
Pegging, or End Assembly/Hard Pegging.
Planning Group: Reserve projectspecific supply and demand at the planning
group level. Supply for one project can be reserved against demand from another
project, if both projects belong to the same planning group. Excess common supply
can be allocated to project demand for hard and soft pegged items.
if reservation level is project supply from due project, it cannot be given a demand
from another project. Only soft pegged items excess project supply can be allocated
to other projects.
Task: Reserve supply for a projecttask against demand for the same projecttask
only.
Project MRP
--
onhand quantity of 25 for P2 and no scheduled receipts, there is still demand for P2 of
75. The planning engine cannot apply excess from any other source to meet this
demand, the planning engine looks for the available supply for P2 and finds it in Period
2. This supply is rescheduled in to Period 1. This scheduled receipt is also used to
satisfy the P2 demand of 500 in Period 2.
Once again, the planning engine can only apply the excess P2 supply to P2 demand.
The last P2 demand is in Period 3 (for 300), consuming the excess of 25 from Period 2
and leaving a net requirement of 275, which the planning engine converts into planned
orders.
Because the item is hard pegged, and the hard pegging level (from the plan options) is
set to project, the P2 project reference is added to the suggested planned order.
In this diagram:
On hand (P1): 10
On hand (P2): 25
Entity
Period 1
Period 2
Period 3
Demand
200 (P1)
150 (P1)
300 (P2)
100 (P2)
500 (P2)
400 (common)
Scheduled receipts
265 (P1)
600 (P2)
600 (common)
Planned orders
--
75 (P1)
275 (P2)
Projected available
75 (P1)
0 (P1)
0 (P1)
-75 (P2)
25 (P2)
0 (P2)
-395 (common)
395 (common)
205 (common)
On hand (P1): 10
On hand (P2): 25
Entity
Period 1
Period 2
Period 3
Demand
200 (P1)
150 (P1)
300 (P2)
100 (P2)
500 (P2)
400 (common)
Scheduled receipts
265 (P1)
600 (P2)
600 (common)
Planned orders
--
75 (P1)
145
Projected available
75 (P1)
-75 (P1)
0 (P1)
-75 (P2)
25 (P2)
0 (P2)
-395 (common)
395 (common)
0 (common)
Netting Behavior
By combining the item pegging attribute with the plan options reservation and hard
pegging levels, you can exercise a high degree of control over how the planning process
preallocates supply for an item. The table below summarizes the possible
combinations and types of behavior you can enforce:
Project MRP Netting Behavior
Reservation Level
Item Pegging
Attribute
Netting Behavior
Planning Group
Project
Hard Pegging
Reserve supply at
planning group level,
excess common
supply used for
project demand, and
create planned orders
at project level
Reservation Level
Item Pegging
Attribute
Netting Behavior
Planning Group
Project-Task
Hard Pegging
Reserve supply at
planning group level,
excess common
supply used for
project demand, and
create planned orders
at project-task level
Planning Group
None
Hard Pegging
Reserve supply at
planning group level,
excess common
supply used for
project demand, and
create planned orders
without project
references
Project
Project
Hard Pegging
Reserve supply at
project-task level,
create planned orders
at project level
Project
Project-Task
Hard Pegging
Reserve supply at
project-task level,
create planned orders
at project-task level
Project
None
Hard Pegging
Reserve supply at
project-task level,
create planned orders
without project
references
Project-Task
Project
Hard Pegging
Reserve supply at
project-task level,
create planned orders
at project level
Project-Task
Project-Task
Hard Pegging
Reserve supply at
project-task level,
create planned orders
at project level
Reservation Level
Item Pegging
Attribute
Netting Behavior
Project-Task
None
Hard Pegging
Reserve supply at
project-task level,
create planned orders
without project
references
Planning Group
<any value>
Soft Pegging
Reserve supply at
project level, create
planned orders
without project
references
Hard Pegging
No reservations, full
pegging
Project
Project-Task
None
Excess Supply
Effects of the pegging item attribute on the netting of excess supply
Item Attribute
14
Parallel Processing
Configure Oracle MRP to run optimally on your machine. You can control how
Oracle MRP divides the work across separate processes, and how many processes
should perform the work.
These topics are technical and are not intended for most users. It is not necessary to
read them to be able to use Oracle MRP.
Process Control
Oracle MRP breaks tasks into smaller tasks that can be executed concurrently by
independent processes. Oracle MRP controls the execution of these processes,
independent of the hardware platform.
Concurrent Manager
Oracle MRP uses Oracle Application Object Library's concurrent manager for process
control.
Oracle MRP uses Oracle Application Object Library's Application Programmatic
Interface (API) to launch new concurrent programs via the concurrent manager by
inserting rows to Oracle Application Object Library's concurrent request table.
Oracle MRP also uses the concurrent manager to determine the status of processes that
are executing. One process can determine the status of another process by using an API
to examine the status of the request in the concurrent request table.
Since Oracle MRP uses the concurrent manager to launch new processes and does not
spawn processes directly, Oracle MRP is hardware independent and works on multiple
hardware platforms without modification.
Oracle MRP has no direct control over how the operating system distributes the
processes across processors. Oracle MRP divides the tasks optimally across separate
processes, but depends upon optimization logic on the part of the operating system to
distribute the workload effectively across multiple processors.
See also Managing Concurrent Programs and Requests inOracle Applications User's
Guide .
Inter-process Communication
Oracle MRP breaks tasks into smaller tasks that are executed concurrently by
independent processes (workers). The programs that execute these tasks concurrently
need to communicate to coordinate their actions.
Oracle MRP uses the Oracle Server for inter-process communication. For example, a
Snapshot Delete Worker needs to be able to communicate to the Snapshot Monitor that
it has finished deleting the old plan data from a specific table. The Snapshot Delete
Worker does so by updating the appropriate columns in the database and issuing a
database commit, instead of relying on hardware-dependent techniques such as signals
or sockets. The Snapshot Monitor can then query those columns to receive the message
that the data has been deleted and can launch the Loader Worker.
Oracle MRP also uses an Oracle Server feature, database pipes, as a port independent
mechanism of asynchronous communication. For example, when the Snapshot Monitor
needs to communicate the next task to be executed to the Memory-based Snapshot or
the Memory-based Snapshot Workers, it places the task number on a pipe. The
Memory-based Snapshot and its Workers listen to the pipe to receive the task number.
After the execution of the task, they use the same mechanism to communicate the
completion of task to the Snapshot Monitor.
See also Memory-based Planning Engine.
to access or retrieve the information requested, and not for the processors themselves to
compute.
The total time to execute two I/O bound tasks on a single processor machine is less if
they execute simultaneously rather than one after the other. While one task waits for
information to be brought back from disk, the single processor can execute the second
task.
When there are relatively few processes running, performance of a single processor
machine is similar to that of a multiprocessor machine. In general, performance of a
single processor machine degrades more quickly than a multiprocessor machine, as the
number of simultaneous processes increase.
Does data entry occur all at once, or is data at a relatively constant rate throughout
the day?
The best approach is to experiment. For example, first try running the snapshot with
three workers, then increase the number of workers. Assuming other factors are not
skewing the results, determine which option provides the best results.
Snapshot
The Snapshot takes a copy, or "snapshot," of all the information used by the planning
processes so that the planning processes can operate on a picture of the data frozen at a
point in time, and report against that snapshot at any future time.
Snapshot Tasks
The work performed by the Snapshot can be broken down into individual tasks. Some
tasks involve copying information into the MRP tables, such as inventory quantities,
master schedule data, discrete jobs, purchase orders, and repetitive schedules. Other
tasks involve deleting information from tables. For example, the information in the
MRP discrete job table needs to be deleted before MRP can reload the latest
information. Many of the tasks are independent of one another; for example, you can
load inventory information at the same time you load discrete job information. The
Snapshot launches workers to run these tasks concurrently.
When the Snapshot runs, it populates the Snapshot Task table with all the tasks that
need to be executed.
Each task has a start date and a completion date. The values of those columns indicate
the status of the tasks. A task with a null start date and null completion date has not
been executed yet. A task with a value for the start date but no value for the completion
date is currently being processed. A task with values for the start date and for the
completion date has been processed. The Snapshot looks at these columns to determine
which task should be processed next.
Some tasks may be dependent upon other tasks. For example, you must delete from the
MRP discrete job table before you reinsert values for the latest picture of the discrete
jobs; or, you must load information on current repetitive schedules before you can
calculate information on current aggregate repetitive schedules. The Snapshot ensures
that independent tasks are processed before the tasks that depend upon them are
processed.
Read Consistency
Certain tasks require a database lock to guarantee a consistent read. For example,
discrete job information and inventory quantities require a lock on the inventory
transactions table to guarantee a consistent read. Consider the situation where you have
a subinventory with a quantity of 100 units, and a discrete job for 25 units. Between the
time the Snapshot reads the inventory information and the time the Snapshot reads the
discrete job information, 10 units are completed from the job. The Snapshot needs to
guarantee that it populates the MRP tables with inventory of 100 and discrete job
quantity of 25, or inventory for 110 and discrete job quantity of 15. Because each task
may be processed by independent processes, the Snapshot cannot guarantee that both
tasks are executed at the same time. Therefore, by locking the inventory transactions
table, the Snapshot guarantees a consistent read.
Each task has an attribute which indicates whether the Snapshot needs to have acquired
the table lock before the task can be completed. Once the locks have been acquired by
the Snapshot, those tasks that require a lock are given highest priority, so that the time
the tables are locked is minimized. Once all tasks requiring locks have been completed,
the Snapshot releases the locks.
Sometimes it is not necessary to guarantee read consistency. For example, if you are
running the planning processes for simulation purposes to estimate medium-term and
long-term trends in your material requirements, it may not be necessary to guarantee
read consistency. Therefore, you may want to run the planning processes with Snapshot
Lock Tables turned off, so that you do not need to restrict or limit other users from
performing transactions.
Memory-based Planning Engine
One of the advantages of the Memory-based Planning Engine is its ability to get a
consistent image of all planning data without locking users out of the system. The planning
engine accomplishes this with the Oracle Server feature called "set transaction
read-only." With this option, you do not need to lock tables for the duration of the
planning run. To ensure total consistency, you need only synchronize the times when
the Snapshot Workers and the Memory-based Snapshot execute the set transaction
feature.
You can achieve two degrees of read consistency under the Memory-based Planning
Engine. Set the Snapshot Lock Tables field to Yes to force the Snapshot Workers and the
Memory-based Snapshot to execute the set transaction feature simultaneously. Locking
tables gives you the highest degree of data consistency, but you cannot perform any
transactions while this lock is on. If you set the Snapshot Lock Tables field to No, the
Snapshot Workers and the Memory-based Snapshot may execute the set transaction
feature at different times. There is a remote possibility of some inconsistencies with this
method.
Snapshot Configuration
You can configure the Snapshot to determine how many Snapshot Workers to launch
when you define the MRP: Snapshot Workers profile option. See Profile Options.
This provides the capability to perform multiple tasks in parallel. This is a function of
the hardware running your processes and the number of Standard Managers you have
in your Oracle Applications.
This is a detailed explanation of the Snapshot Process logic under the Standard
Planning Engine:
1.
Launch X Snapshot Workers via the Concurrent Manager, where X is the number of
Snapshot Workers to launch, as defined by the profile option MRP: Snapshot
Workers.
2.
3.
4.
Were we able to lock the tables? If No, check to see if we have exceeded the amount
of time specified by the user to wait for the table locks.
5.
The user specified a length of time to wait for the table locks.
6.
Create the lock file. The existence of the lock file signals to the workers that they can
execute tasks requiring a table lock, as well as those that do not.
7.
Keep looping until all tasks that require table locks have been completed.
8.
All tasks requiring a lock have completed. Therefore, there is no need to keep the
locks. Issue a database commit to free the table locks.
9.
Are there any tasks that have not yet been executed and do not have tasks upon
which they are dependent that have not yet completed? If so, execute those tasks.
10. Are there any other tasks to execute? If Yes, those tasks are waiting for the tasks
upon which they are dependent to complete. Loop back and try again.
11. Loop until the workers complete.
12. Check the completion status of the workers. If any of the workers exited with error,
The above diagram illustrates the Snapshot Worker Process logic. Below is a detailed
Check for the existence of the lock file. If the lock file exists, the Snapshot was able
to acquire table locks. Therefore, tasks requiring table locks may be executed.
2.
Are there tasks that have not yet been executed, that require a table lock, and do not
have tasks upon which they are dependent that have not yet completed? If so,
execute those tasks.
3.
Are there any tasks that have not yet been executed, and do not have tasks upon
which they are dependent that have not yet completed? If yes, execute those tasks.
4.
Have all tasks that require table locks been completed? If not, pause and return to
step 1.
Thus, the Memory-based Planner first loads all the supply, demand, BOM, and
low-level code information into memory. In order to maximize multithreading Oracle
MRP ensure that the Memory-based Planner loads the data from the Snapshot
generated flat files rather than waiting until the data is loaded into the MRP tables.
After it has performed the gross-to-net explosion, the Memory-based Planner flushes
the output of the plan to MRP tables. Similar to the Memory-based Snapshot, it writes
the data to flat files and launches Loader Workers to load the data to MRP tables.
You can configure the Memory-based Snapshot to control how many Snapshot Workers
and Snapshot Delete Workers should be launched. To do so, define the profile option
MRP: Snapshot Workers. See Profile Options.
See Also:
Defining Managers and Their Work Shifts, in Oracle Applications User's Guide
Snapshot
Available to Promise
Planning Manager
The Planning Manager periodically performs many tasks that require processing rows
in an interface table. These are tasks such as forecast consumption, master production
schedule consumption, forecast interface load, schedule interface load, and master
demand schedule relief.
The Planning Manager has been designed to:
Process the work itself, if there are only a few rows to process, rather than incurring
the overhead of launching a new concurrent program.
Divide the work across one or more Planning Manager Worker processes if there
are many rows to process.
Launch more Planning Manager Workers when there are more rows to process, and
fewer workers when there are fewer rows to process.
Avoid delaying the processing of one task due to another task. For example, relief
of the master production schedule should not be delayed because the Planning
Manager is busy processing rows for forecast consumption.
You can configure the Planning Manager to control how it divides the rows to be
processed, and across how many processes those rows are divided. You can define the
following profile options:
Consume the master production schedule when work orders or purchase orders are
created
Consume the master demand schedule when sales orders have shipped
Load forecasts from outside systems when rows are inserted into the interface table
from an outside system
Load master schedules from outside systems when rows are inserted into the
interface table from an outside system
Update rows in the interface table where the status indicates that they are waiting
to be processed. Update at most X rows, where X is the value of the profile option
MRP: Planning Manager Batch Size.
2.
Check to see if any rows were updated in Step 1. If not, there are no rows waiting to
be processed.
3.
Were the number of rows updated in Step 1 equal to the batch size? If not, all the
remaining rows in the interface table can be processed by this process. If the
number of rows updated equals the batch size, there could be more rows to process.
Go to Step 4 to try to launch a Snapshot Worker.
4.
The number of rows updated never exceeds the batch size, because we have limited
the update in Step 1 to be less than or equal to the batch size number of rows.
5.
6.
Is the number of Planning Manager Workers running or pending less than the
maximum number of workers? If yes, launch a Planning Manager Worker.
Otherwise, do not launch a new Planning Manager Worker.
7.
Process the rows that were updated in Step 1 according to the type of task being
performed. If any errors occur during processing, update the status of the row to "
Error". Otherwise, update the status of the row to "Processed".
8.
Is this process the Planning Manager or a Planning Manager Worker? If this is the
Planning Manager Worker, loop back to Step 1 and try to grab another set of rows
to process. If this is the Planning Manager itself that is running, there should be no
more rows to process. Do not grab more rows, as that may cause a delay in
processing other tasks.
9.
If this is the Planning Manager, move on to the next task to process. If there are no
other tasks to process this cycle, resubmit the Planning Manager to wake up again
after the interval of time set in the profile option. If this is a Planning Manager
Worker, terminate the program.
A
Tools Menu
Tools Menu
This appendix shows you the options available from the Tools menu
Tools Menu
Depending upon the currently active window and other conditions, the Tools menu
includes:
Work Dates
Displays work dates that are the beginning of the work period.
Preferences
On Hand
Copy Plan
Plan Status
SupplierItem Information
See Also
B
Windows and Navigator Paths
CST
Flex
GL
HR
IN
PO
SYS
User
Navigation Path
Available Resources
Bill of Distribution
Change Organization
Components
Copy/Merge Forecast
Navigation Path
Forecast > Items [Copy/Merge]
DEMAND_CLASS Lookups 1 29
Destinations
End Assemblies
Enterprise View
Exceptions
Navigation Path
MPS > Workbench [Exceptions]
MRP > View Plan > Status [Exceptions]
Exception Details
Exception Summary
Find Items
Navigation Path
MRP > Workbench [Items]
MPS > Workbench [Items]
Find Supply/Demand
Navigation Path
Forecast > Items [Detail] > [Consumptions]
Forecast > Sets [Forecast Set Items] > [Bucketed]
[Detail] > [Consumptions]
Forecast > Sets [Forecast Set Items] > [Detail]
[Consumptions]
Forecast > View Entries [Consumptions]
Forecast > View Items [Bucketed] > [Detail]
[Consumptions]
Forecast > View Items [Detail] > [Consumptions]
Forecast > View Sets [Forecast Set Items] >
[Bucketed] [Detail] > [Consumptions]
Forecast > View Sets [Forecast Set Items] > [Detail]
[Consumptions]
Inquiry > Forecast > View Entries [Consumptions]
Inquiry > Forecast > View Items [Bucketed] > [Detail]
[Consumptions]
Inquiry > Forecast > View Items [Detail] > [Consumptions]
Inquiry > Forecast > View Sets [Forecast Set Items] >
[Bucketed] [Detail] > [Consumptions]
Inquiry > Forecast > View Sets [Forecast Set Items] >
[Detail] [Consumptions]
Forecast > Items [Bucketed] > [Detail]
Forecast > Items [Detail]
Navigation Path
Forecast > Sets [Forecast Set Items] > [Bucketed]
[Detail]
Forecast > Sets [Forecast Set Items] > [Detail]
Forecast > View Items [Bucketed] > [Detail]
Forecast > View Items [Detail]
Forecast > View Sets [Detail]
Forecast > View Sets [Forecast Set Items] >
[Bucketed] [Detail]
Forecast > View Sets [Forecast Set Items] > [Detail]
Inquiry > Forecast > View Items [Bucketed] > [Detail]
Inquiry > Forecast > View Items [Detail]
Inquiry > Forecast > View Sets [Bucketed] > [Detail]
Inquiry > Forecast > View Sets [Detail]
Forecast > Items
Forecast > Sets [Forecast Items]
Forecast > Sets [Forecast Set Items]
Forecast > View Items
Forecast > View Sets [Forecast Set Items]
Forecast > View Sets [Forecast Items]
Inquiry > Forecast > View Items
Navigation Path
Inquiry > Forecast > View Sets [Forecast Items]
Inquiry > Forecast > View Sets [Forecast Set Items]
Forecast > Sets
Forecast > View Sets
Inquiry > Forecast > View Sets
Forecast > Source List
Generate Forecast
Horizontal Plan
Navigation Path
MPS > Workbench [Items] > [Horizontal Plan]
MPS > Workbench [Items] > [Sources] [Horizontal
Plan]
MPS > Workbench [Supply/Demand] > [Horizontal
Plan]
MPS > Workbench [Supply] > [Horizontal Plan]
MRP > Workbench [Demand] > [Horizontal Plan]
MRP > Workbench [Exceptions] > [Horizontal Plan]
MRP > Workbench [Items] > [Destinations] [Horizontal
Plan]
MRP > Workbench [Items] > [Horizontal Plan]
MRP > Workbench [Items] > [Sources] [Horizontal
Plan]
MRP > Workbench [Supply/Demand] > [Horizontal
Plan]
MRP> Workbench [Supply] > [Horizontal Plan]
Navigation Path
Kanban Details
Kanban Names
Kanban Workbench
Launch DRP
Navigation Path
DRP > Workbench > Launch Copy Plan
Launch Kanban
Launch MPS
Navigation Path
Navigation Path
Inquiry > MPS > View Items [Detail] > [Reliefs]
MPS > Entries [Reliefs]
MPS > Items [Bucketed] > [Detail] [Reliefs]
MPS > Items [Detail] > [Reliefs]
MPS > View Entries [Reliefs]
MPS > View Items [Bucketed] > [Detail] [Reliefs]
MPS > View Items [Detail] > [Reliefs]
MRP Names
Plan Options
Navigation Path
Plan Organizations
Plan Status
Navigation Path
MRP > View Plan Status
MRP > Workbench [Status]
Planner Tasks
PLANNING_GROUP Lookups
Planning Manager
Planning Parameters
Resource
Navigation Path
Snapshot Tasks
Sources
Navigation Path
Report
Inquiry > Report
Supply/Demand Detail
Navigation Path
DRP > View Plan [Exceptions] > [Supply]
DRP > View Plan [Items] > [Demand]
DRP > View Plan [Items] > [Supply/Demand]
DRP > View Plan [Items] > [Supply]
DRP > View Plan [Supply/Demand]
DRP > Workbench [Demand]
DRP > Workbench [Exceptions] > [Demand]
DRP > Workbench [Exceptions] > [Supply/Demand]
DRP > Workbench [Exceptions] > [Supply]
DRP > Workbench [Items] > [Demand]
DRP > Workbench [Items] > [Supply/Demand]
DRP > Workbench [Items] > [Supply]
DRP > Workbench [Supply/Demand]
DRP > Workbench [Supply]
Inquiry: MRP > View Plan [Demand]
Inquiry: MRP > View Plan [Exceptions] > [Demand]
Inquiry: MRP > View Plan [Exceptions] >
[Supply/Demand]
Inquiry: MRP > View Plan [Exceptions] > [Supply]
Inquiry: MRP > View Plan [Items] > [Demand]
Navigation Path
Inquiry: MRP > View Plan [Items] > [Supply/Demand]
Inquiry: MRP > View Plan [Items] > [Supply]
Inquiry: MRP > View Plan [Supply/Demand]
Inquiry: MRP > View Plan [Supply]
MRP > View Plan [Demand]
MRP > View Plan [Exceptions] > [Demand]
MRP > View Plan [Exceptions] > [Supply/Demand]
MRP > View Plan [Exceptions] > [Supply/Demand]
MRP > View Plan [Exceptions] > [Supply]
MRP > View Plan [Items] > [Demand]
MRP > View Plan [Items] > [Supply/Demand]
MRP > View Plan [Items] > [Supply]
MRP > View Plan [Supply/Demand]
MRP > View Plan [Supply]
MRP > Workbench [Demand]
MRP > Workbench [Exceptions] > [Demand]
MRP > Workbench [Exceptions] > [Supply/Demand]
MRP > Workbench [Exceptions] > [Supply]
MRP > Workbench [Items] > [Demand]
Navigation Path
MRP > Workbench [Items] > [Supply/Demand]
MRP > Workbench [Items] > [Supply]
MRP > Workbench [Supply/Demand]
MRP > Workbench [Supply]
Inquiry: MPS > View Plan [Demand]
Inquiry: MPS > View Plan [Exceptions] > [Demand]
Inquiry: MPS > View Plan [Exceptions] >
[Supply/Demand]
Inquiry: MPS > View Plan [Exceptions] > [Supply]
Inquiry: MPS > View Plan [Items] > [Demand]
Inquiry: MPS > View Plan [Items] > [Supply/Demand]
Inquiry: MPS > View Plan [Items] > [Supply]
Inquiry: MPS > View Plan [Supply/Demand]
Inquiry: MPS > View Plan [Supply]
MPS > View Plan [Demand]
MPS > View Plan [Exceptions] > [Demand]
MPS > View Plan [Exceptions] > [Supply/Demand]
MPS > View Plan [Exceptions] > [Supply]
MPS > View Plan [Items] > [Demand]
MPS > View Plan [Items] > [Supply/Demand]
Navigation Path
MPS > View Plan [Items] > [Supply]
MPS > View Plan [Supply/Demand]
MPS > View Plan [Supply]
MPS > Workbench [Demand]
MPS > Workbench [Exceptions] > [Demand]
MPS > Workbench [Exceptions] > [Supply/Demand]
MPS > Workbench [Exceptions] > [Supply]
MPS > Workbench [Items] > [Demand]
MPS > Workbench [Items] > [Supply/Demand]
MPS > Workbench [Items] > [Supply]
MPS > Workbench [Supply/Demand]
MPS > Workbench [Supply]
Navigation Path
MRP > Workbench [Items] Tools menu >Onhand
C
Alerts
Alerts
This appendix shows you the alerts for Oracle MRP.
Oracle MRP includes two precoded alerts you can use with or without customizing.
These alerts help you identify forecast overconsumption:
Forecast Overconsumption Summary
Forecast Overconsumption Detail
Periodic
Periodicity
Inputs
None
Distribution
Alerts C-1
See Also
Overview of Oracle Alert, Oracle Alert User's Guide Using Precoded Alerts, Oracle Alert
User's Guide
D
Customized Find Windows
can retrieve all available records by leaving all fields blank and choosing Find.
If you decide to narrow your search, you must enter a search string in the first row of
fields in the find window. If you enter more search strings on subsequent lines, a data
record must match both criteria to be retrieved. It will not be retrieved when it matches
only one of the search strings. Multiple search strings assume the logical form (string1)
AND (string2), where string1 and string2 are search strings entered on separate lines in a
find window.
To enter a search string:
1.
2.
Enter a search criteria in the Field field. This will direct the search to that column in
the relevant table.
3.
Enter an operator in the Condition field. You can choose from a list of valid
operators that determine the conditions you want the data records to satisfy.
Depending on the type of condition you enter, you may be required to enter a
single value (in the From field) or a range of criterion values (in the From and To
fields). Criterion values may be numbers or character strings.
4.
When you have finished entering your search string, choose Find to start the query.
2.
3.
4.
the one you are logged into, you must be logged into the
organization that generated the plan; otherwise, otherwise you can
search only for your current organization.
To retrieve all records, leave all fields blank and choose Find.
6.
The retrieve a subset of records, enter a search string. You can use just one string in
your search (containing a criterion, an operator, and a value), or you can enter
several strings to refine your search.
7.
Once you have entered at least one string, containing a field name, a condition, and
(optionally) a value, choose Find to start your search.
8.
Optionally, choose a folder to import a previously defined search strings and start
the search.
2.
3.
Item Details
ABC Class
Buyer
Exception Set
Make or Buy
Category
Forecast Control
Organization
Item
Nettable Quantity
Nonnettable quantity
Planner
Standard Cost
Repetitive
4.
To retrieve all records, leave all fields blank and choose Find.
5.
To retrieve a subset of records, enter a search string. You can use just one string in
your search (containing a criterion, an operator, and a value), or you can enter
several strings to refine your search.
6.
Once you have entered at least one string, containing a field name, a condition, and
(optionally) a value, choose Find to start your search.
7.
Optionally, choose a folder to import a previously defined search strings and start
the search.
See Also
Reviewing Item Planning Information
Supply/Demand Find Window
Using Query Find, Oracle Applications User's Guide
Using Query Operators, Oracle Applications User's Guide
Demand windows.
1.
2.
3.
Optionally, select a planner. When you open the planner Workbench and navigate
to one of the details windows (such as items or exceptions), you will be asked if you
want select a planner. Doing so may improve workbench performance, however
you will be asked to select a planner once for each session in the workbench.
4.
Category
Compression Days
Item
Implemented Quantity
Line
Planner
Make or Buy
Organization
Repetitive
Project Number
New Quantity
Rescheduled
Quantity in Process
Source Supplier
Quantity/Rate
Supplier
Selected to Release
Source Organization
Using Assembly
5.
To retrieve all records, leave all fields blank and choose Find.
6.
The retrieve a subset of records, enter a search string. You can use just one string in
your search (containing a criterion, an operator, and a value), or you can enter
several strings to refine your search.
7.
Once you have entered at least one string, containing a field name, a condition, and
Optionally, choose a folder to import a previously defined search strings and start
the search.
See Also
Reviewing Supply and Demand
Supply and Demand Fields
Items Find Window
Using Query Operators, Oracle Applications User's Guide
E
Workflow - Planning Exception Messages
View recipients, and have the system route exception messages accordingly
View approval steps and the flow the process will follow
You can view or modify this workflow in the Oracle Workflow Builder. See Oracle
Workflow Guide.
See Also
Choose Open from the File menu, and connect to the database. See: Opening and
Saving Item Types, Oracle Workflow Guide.
The display name of the exception messages workflow is Planning Exception
Messages. The name of its Workflow definition file is mrpexpwf.wft
2.
Expand the data source, then the Exception Message branch within that data
source.
3.
Expand the Processes branch, then choose the Exception Process activity to display
the diagram.
Required Modifications
There are no required modifications you need to make to this workflow.
Processes
If you modify a process, it is essential that the basic flow remain intact in order to
maintain data integrity in the database. However, you could add additional checks
(processes or function activities) before allowing data to be inserted into the tables.
If you modify any process, either by replacing a portion of its flow or by adding
additional function activities, remember the following:
Attributes that are set by default function activities in the default processes must
also be set if you replace default function activities with ones of your own. That is, if
a function activity in that process uses a SetItemAttr statement, then that function
activity is setting an attribute to be used by another function activity later.
Therefore, your new function activity must do the same. You should also preserve
SetItemUserKey and SetItemOwner statements, if any (You may also want to preserve
GetItemAttrstatements.)
Any database state maintained by the default processes must also be maintained by
processes you customize. That is, if a function activity in that process uses an
Update or Insert.
Into statement, then that function activity is updating or inserting rows in the
database. Therefore, your new function activity must maintain the same database
state.
Notifications
All of the notifications can be modified to meet your individual business needs.
However, if the notification has a reply code, you must make sure that the Result Type
of your customized notification matches the Result Type of the default notification.
Messages
All of the messages can be modified to meet your individual business needs. For a list of
the types of exceptions that may occur when you run your plan. See: Reviewing
Planning Exceptions.
Messages are sent to particular recipients depending on the exception type. For
example, in Process 3 of the Planning Exception Messages workflow, exception types 13
and 15 are sent at Node 5 after a planner is found. See:Summary of Exception Process 3.
To view messages by exception types, select Messages in the navigator tree, and expand
the file. A listing of all the messages in the Planning Exception Messages workflow
displays in order of the exception type. Select the message, you can see the text of the
message in the Description box.
Lookup Types
All of the lookup types can be modified to meet your individual business needs.
Note: If you change a lookup type, you must be sure that all
notifications and processes that use the lookup type allow for the
change. For example, if you change the lookup type from Yes/No to
something else, the activities that use that lookup type should also
change their Result Type from Yes/No to whatever new lookup type
you created.
Exception Process 1
Exception Process 2
Exception Process 3
Exception Process 4
If you examine the property page of Planning Exception Messages, you see that it calls a
selector function named MRP_EXP_WF. This selector function is an example PL/SQL
stored procedure that returns the name of the process to run when more than one
process exists for a given item type.
The Planning Exception Messages workflow item type also has a listing of attributes
associated with it. These attributes reference information in the demonstration
application tables. The attributes are used and maintained by function activities as well
as notification activities throughout the process.
To view descriptions of each item type attribute, select the attribute in the Workflow
Builder and choose Properties from the Edit menu. Look in the Description field.
Workflow Planning Exception Messages Workflow Type Attributes
Display Name
Description
Type
Found/Not Found
Text
Order Type
Number
Proceed/Stop
Display Name
Description
Type
Reschedule Action
Text
Start (Node 1)
This is a standard function activity that simply marks the start of the subprocess.
Function - WF_STANDARD.NOOP
Required - Yes
Function - MRP_EXP_WF.DETERMINPROCEED
Required - Yes
PLAN_NAME_ORGANIZATION_ID
End (Node 3, 5, 7)
This is a standard function activity that marks the end of the process.
Function - WF_STANDARD.NOOP
Required - Yes
Function - MRP_EXP_WF.SELECTPLANNER
Required - Yes
Function - WF_STANDARD.NOTIFY
Required - Yes
Start (Node 1)
This is a standard function activity that simply marks the start of the subprocess.
Function - WF_STANDARD.NOOP
Required - Yes
Function - MRP_EXP_WF.DETERMINPROCEED
Required - Yes
End (Node 3, 5, 7, 9, 12, 14, 16, 19, 21, 24, 26, 28)
This is a standard function activity that marks the end of the process.
Function - WF_STANDARD.NOOP
Required - Yes
Function - MRP_EXP_WF.DETERMINEORDERTYPE
Required - Yes
Function - MRP_EXP_WF.SELECTPLANNER
Required - Yes
Function - MRP_EXP_WF.SELECTBUYER
Required - Yes
FORWARD_TO_USERNAME
Function - MRP_EXP_WF.SELECTSUPPLIERCNT
Required - Yes
Function - WF_STANDARD.NOTIFY
Required - Yes
Function - WF_STANDARD.NOTIFY
Required - Yes
Function - WF_STANDARD.NOTIFY
Required - Yes
Function - WF_STANDARD.NOTIFY
Required - Yes
node. Only the messages which contain information related to purchase orders are
selected from this activity. When the notification is reviewed, the recipient responds to
it by selecting either Reschedule or Do Not Reschedule.
Function - WF_STANDARD.NOTIFY
Required - Yes
Function - MRP_EXP_WF.RESCHEDULE
Required - Yes
Function - WF_STANDARD.NOOP
Required - Yes
Function - MRP_EXP_WF.DETERMINPROCEED
Required - Yes
Function - WF_STANDARD.NOOP
Required - Yes
Function - MRP_EXP_WF.SELECTPLANNER
Required - Yes
Function - WF_STANDARD.NOTIFY
Required - Yes
Function - MRP_EXP_WF.SELECTSALESREP
Required - Yes
Function - MRP_EXP_WF.CUSTOMERCNT
Required - Yes
notification is only sent to the task manager. At Node 7 the information is passed to
Node 8 to determine if more than one task/project manager should receive notification.
If another recipient is found at Node 10, the workflow proceeds to Node 12. the
message and the activity is complete and the process ends at Node 13. If no other
recipient is found, the workflow proceeds directly to Node 13, the activity is complete
and the process ends.
Function - WF_STANDARD.NOOP
Required - Yes
Function - MRP_EXP_WF.DETERMINPROCEED
Required - Yes
Function - WF_STANDARD.NOOP
Required - Yes
Function - MRP_EXP_WF.SELECTPLANNER
Required - Yes
Function - WF_STANDARD.NOTIFY
Required - Yes
receives notification based on plan, organization F - 22 and item. This activity also
selects the appropriate message to be sent based on exception type.
Function - MRP_EXP_WF.SELECTTASKMGR
Required - Yes
Function - MRP_EXP_WF.ISTYPE19
Required - Yes
See Also
F
Forecasting - Statistical and Focus
method.
Demand Sources
A forecast rule may apply to demand from any or all of the following:
inter-organization issues
The forecast for this period is the actual demand for the previous period.
The forecast for this period is the average of the actual demands for the previous two
periods.
The forecast for this period is the actual demand for the same period last year
multiplied by the growth (or decline) since last year as
measured by the ratio of the previous period actual demand to the actual demand for
the same period last year.
The forecast for this period is the actual demand for the previous period multiplied by
the current growth (or decline) as measured by the ratio of the previous period actual
demand to the actual demand for the period before the previous period.
Important: When you use daily time buckets, a week is used instead of
These models are illustrated in the following table. Note that Models 1 and 4 require
over a year of historical data while the other three methods can be executed with only
two historical periods. Focus forecasting is restricted to only those models where
sufficient demand history exists.
To evaluate which forecasting model produced the best forecast last period, the
absolute percentage error (APE) is calculated for the five forecasts and the forecasting
model with the smallest APE is chosen. APE is the ratio of the difference between the
actual demand and forecast to the actual demand.
Forecast Year
January
February
March
April
2000
220
210
250
260
2001
270
255
290
Forecast Model
March 2001
Forecast
March 2001
Actual
Error (APE)
April 2001
Forecast
250
290
14%
260
255
290
12%
290
263
290
9%
273
304
290
5%
302
241
17%
330
In this table, the forecast for the previous month is calculated for Model 4 as follows:
Since 5% is the smallest error of the five models, Model 4 is chosen to calculate the April
2001 forecast:
Rather than calculate the exponential function for every period, it can be shown that the
ESF for period t can be easily calculated if we know the ESF for the prior period.
The initial value of ESFt is the actual demand for the prior period, At-1. The table shows
these calculations for three different values of.
Period t
Actual Demand
At
Forecast Eo = 0.9
Demand Eo = 0.5
ESFt Eo = 0.1
200
220
200
200
200
120
218
210
202
230
130
165
194
260
220
198
197
270
256
229
204
290
269
249
210
270
288
270
218
Forecast
272
270
223
Period 3 was an abnormal period, but otherwise the trend is clearly upward. It can be
seen that with the higher alpha, the forecast reacted intensely to the third period, and
produced a very low period 4 forecast, but was also faster to correct itself and adjust for
the trend. By period 9, the period we are forecasting, the abnormal period 3 has only a
negligible effect on the forecast. All three forecasts became more accurate when they
had more historical data upon which to draw.
It should be noted that, even though the higher alpha adjusted to the trend faster, plain
ESF always lags behind the trend by at least one period. Even if the demand in the
example had been smooth, all three scenarios would have lagged behind the trend.
Trend-Enhanced Forecast (TEF)
The statistical forecasting method provides an enhancement to the ESF that allows for
trend. The theory behind the trend-enhanced model is that we can take the ESF and add
a trend index, R, that reflects the current trend.
The ESF is no longer the forecast. We rename that term the base, Bt; since it is the base
value of the forecast to which we add the trend (and, in the case of a season-enhanced
forecast, seasonality indices). The formula becomes:
Finally, we need a way to figure out the trend index, Rt. To do this, we need another
smoothing factor to smooth out changes in the trend. Similar to ESF, the higher this
factor, the more responsive it is to changes in trend. However, it increasingly gets
thrown off by abnormal period demand.
The initial value of Rt is the change in demand from two periods ago to the last period,
At-1 - A-2.
Period t
Actual Demand
At
Forecast Base
Bt
Trend Index Rt
Forecast
Demand TEFt
200
220
200
20
230
120
210
15
190
230
175
17
226
260
243
18
261
270
266
19
284
290
287
19
306
270
288
17
305
Forecast
The table gives an example of forecasting using the trend-enhanced model. The forecast
for period 9 is found by first calculating the forecast base value:
And, finally, adding the two for the period 9 trend-enhanced forecast:
The seasonality index for the prior season is adjusted using yet another user-specified
smoothing factor.
Period t
Actual
Demand At
Old Season
Index St
Forecast
Base Bt
Forecast
Demand
SEFt
New Season
Index S't
200
1.05
220
1.00
190
190
1.05
120
0.65
200
130
0.63
230
0.95
195
185
1.02
260
1.05
210
221
1.11
270
1.10
223
245
1.13
290
1.15
230
265
1.18
270
1.15
238
273
1.15
Forecast
1.10
237
260
This table shows an example of season-enhanced forecasting. Notice how, since a drop
in demand was expected in period 3, the forecast dropped in the same period in
anticipation.
We begin by adjusting last period's seasonality index:
The period 9 forecast can now be found by calculating the forecast base-value:
When we receive period 9 results we can recalculate period 9's seasonality index and
then forecast for period 10.
Trend and Season-Enhanced Forecast (TSEF)
Despite the seasonal adjustments made in the SEF, there remained a trend element that
can be seen in the gradual increase in the forecast base, B. The TEF and the SEF may be
combined to make a trend and season-enhanced forecast (TSEF).
A combination of the TEF and SEF can be illustrated by showing the formulae and
example provided in the previous table. The TSEF uses all three smoothing factors.
Period
t
Actual
Demand
At
Old
Season
Index St
Forecast
Base Bt
200
1.05
220
1.00
190
120
0.65
200
230
0.95
260
Trend
Index Rt
Forecast
Demand
TSEFt
New Season
Index S't
190
1.05
10
137
0.63
201
199
0.99
1.05
221
10
242
1.07
270
1.10
236
11
272
1.10
290
1.15
247
11
296
1.14
270
1.15
255
10
306
1.11
Forecast
1.10
254
290
As with the SEF, we can calculate the new period 8 seasonality index as soon as period
8 results are in.
Add them together and multiply in the seasonality factor to get the period 9 trend and
season-enhanced forecast:
G
Memory-based Planning Engine
flexible configuration: you can specify the number of Workers available to perform
snapshot tasks, taking advantage of hardware resources
locked tables not required: the Memory-based Planning Engine gathers consistent
views of supply and demand data without locking users out of the system
byproduct planning
full pegging
See Also
Processing Steps
Processes
Snapshot Tasks
Read Consistency
Interprocess Communication
Processing Steps
The Memory-based Planning Engine executes the planning run in the following
sequence:
1.
Snapshot preprocessing. This is the first step preformed as a part of the Snapshot. It
consists of tasks that need to be done prior to the Snapshot. These tasks include
calculating repetitive planning periods for all the planned organizations and
auto-reducing the master production schedules.
2.
Item list determination. This step involves determining the items that will be
planned as part of the current planning run. The plan-level option included items
determines the items that will be planned. All other Snapshot activities cannot start
until this step is complete.
3.
Deleting old data. This step consists of cleaning all the snapshot and planner output
data from the previous planning run.
4.
Creating flat files of snapshot data. This step involves selecting the data from the
system tables and writing them to flat files. Since this data is written to flat files, the
deletes are not a prerequisite for this task.
5.
Loading flat files into the database. This step loads the Snapshot flat files into the
MRP Snapshot tables.
6.
Snapshot post-processing. This step consists of cleanup activity and execution of the
user-defined Snapshot tasks (such as updating item categories and ABC classes) in
MRP_SYSTEM_ITEMS.
7.
Netting. This step performs the gross-to-net explosion, during which suggested
supply orders are generated.
See Also
Read Consistency
Interprocess Communication
Parallel Processing
When executing the planning run, the above steps are carried out by one or more of the
following seven processes:
Snapshot monitor. This controls the rest of the planning process. It is launched by
the memory-based snapshot and it in turn launches the snapshot workers, delete
workers, loader workers, and the memory-based planner. The number of delete
worker launched by the snapshot monitor is determined by the MRP:Snapshot
Workers profile option. It launches the Delete Workers after it prepares the list of
delete tasks (see Figure 45). The snapshot monitor also maintains a list of snapshot
tasks and delete tasks and the current status of each task. It uses this list to provide
the next snapshot task to the memory-based snapshot and snapshot workers. It uses
the status of the delete tasks to determine if the flat files created by the
memory-based snapshot and snapshot workers can be loaded into the database by
the loader workers. The snapshot monitor is also responsible for ensuring the read
consistency of the data captured by the memory-based snapshot and the snapshot
workers.
Snapshot workers. The number of these workers launched by the snapshot monitor
is based on the MRP:Snapshot Workers profile; setting the number to one makes the
Snapshot run as a single-threaded process. The snapshot workers collect data on
bills of material, work in process, on-hand quantities, purchasing, firm planned
orders, routings and work in process job resource requirements. The snapshot
monitor controls the snapshot workers and receives instructions on which tasks to
perform next. The snapshot worker places the data into flat files and communicates
the completion of the task and the file name to the snapshot monitor.
Snapshot delete workers. These workers are launched by the snapshot monitor and
delete the planning data from the last planning run. Each worker reads
MRP_SNAPSHOT_TASKS to get the next delete task. After it completes the delete,
it updates the completion date in MRP_SNAPSHOT_TASKS.
Loader workers. The snapshot monitor launches one loader worker for each table
requiring a load. The snapshot monitor launches the loader worker after the flat file
for the snapshot data has been written and the last planning run data has been
deleted. The loader worker uses SQL*Loader to load the data. The profile option
MRP:Use Direct Load Option controls whether SQL*Loader uses direct loading or
conventional loading methods.
Warning: If you use Direct Load, the database grows, potentially
Figure 7-44 illustrates the Snapshot Monitor Process logic under the Memory-based
Planning Engine. Below is a detailed explanation of the logic.
1.
Launch X Snapshot Workers via the Concurrent Manager, where X is the number of
Snapshot Workers to launch, as defined by the profile option MRP:Snapshot
Workers.
2.
3.
List the items that the planning engine will include in the current run. The
plan-level option Included Items determines this list.
4.
The Snapshot Monitor launches Snapshot Delete Workers to clean old snapshot and
planning output from the tables.
5.
Snapshot Workers select data from system tables, including work in process,
inventory, purchasing, and bill of materials and write the data to flat files. Since the
data is written to flat files, the deletes are not a prerequisite for this step.
6.
Loader Workers load the flat files from step 5 into the MRP snapshot tables.
7.
Once the workers complete the list of items for planning, lock the tables if Snapshot
Lock Tables is set to Yes, then ask the Snapshot and Snapshot Workers to set
transaction to read-only.
8.
9.
After these steps, the Memory-based Planner performs the gross-to-net explosion and
creates new supply orders.
If the user ran the Memory-based Planner without the Snapshot, the Memory-based
Planning Engine launches Planner Delete Workers, which delete data from the planner
output tables.
See Also
Snapshot Tasks
Read Consistency
Interprocess Communication
Parallel Processing
Snapshot Tasks
Once MRP_SYSTEM_ITEMS is loaded, then all other tasks can proceed. Each of the
following tasks is responsible for creating a set of files that correspond to the database
tables:
Delete: deletes data from relevant MRP tables which belongs to the previous plan
Item information: loads inventory items, primary suppliers, item categories, item
classifications, quantity on hand and cost information
WIP and BOM component information: loads BOM structures, pending ECOs,
component requirements from discrete jobs, flow schedules, repetitive schedules,
and non-standard jobs; calculates low level codes and checks loops introduced by
both WIP components and BOMs
WIP information: loads discrete jobs, flow schedules, non-standard jobs, repetitive
schedules and calculates aggregate repetitive schedules
When a given file is complete, each tasks submits a request to the Snapshot Monitor.
The Snapshot Monitor then checks the dependency and begins loading the file, for use
by the Memory-based Planner.
See Also
Processing Steps
Processes
Read Consistency
Interprocess Communication
Read Consistency
Certain tasks require a database lock in order to guarantee a consistent read. For
example, discrete job information and inventory quantities require a lock on the
inventory transactions table in order to guarantee a consistent read. Consider the
situation where you have a subinventory with a quantity of 100 units, and a discrete job
for 25 units. Between the time the Snapshot reads the inventory information and the
time the Snapshot reads the discrete job information, 10 units are completed from the
job. The Snapshot needs to guarantee that it populates the MRP tables with inventory of
100 and discrete job quantity of 25, or inventory for 110 and discrete job quantity of 15.
Because each task may be processed by independent processes, the Snapshot cannot
guarantee that both tasks are executed at the same time. Therefore, by locking the
inventory transactions table, the Snapshot guarantees a consistent read.
One of the advantages of the Memory-based Planning Engine is its ability to get a
consistent image of all planning data without locking users out of the system. The planning
engine accomplishes this with the ORACLE RDBMS feature called "set transaction
read-only". With this option, you do not need to lock tables for the duration of the
planning run. The Memory-based Snapshot and Snapshot Workers capture all supply
and demand data as it existed after a snapshot of the item list has been taken. All
changes made to the data after that are not included.
The advantage in using the read-only option is that you do not need exclusive table
locks, which lock users out of the table for the entire duration of the Snapshot. Instead,
you simply co-ordinate the snapshots performed by the Memory-based Snapshot and
Snapshot Workers. Since the collection of data is performed by multiple processes, the
"set transaction read-only" feature has to be executed at the same time by the
Memory-based Snapshot and Snapshot Workers.
You can achieve two degrees of read consistency under the Memory-based Planning
Engine. Set the Snapshot Lock Tables field (Plan Options window) to Yes. This forces
the Snapshot Workers and the Memory-based Snapshot to execute the set transaction
feature simultaneously. It also ensures that no transactions are performed while the
snapshot processes are trying to set the transactions to read-only. To ensure this, the
Snapshot Monitor gains an exclusive lock on the tables and instructions the
Memory-based Snapshot and Snapshot Workers to execute the set transaction feature.
As soon as the Snapshot Monitor receives confirmation from the snapshot processes the
set transaction feature is complete, it releases the lock. In this way, you get a
read-consistent snapshot with little time spent locking users out of the system.
Locking tables gives you the highest degree of data consistency, but you cannot
perform any transactions while this lock is on. If you set the Snapshot Lock Tables field
to No, the Snapshot Workers and the Memory-based Snapshot may execute the set
transaction feature at different times. There is a remote possibility of some
inconsistencies with this method.
See Also
Processing Steps
Processes
Snapshot Tasks
Interprocess Communication
Parallel Processing
Oracle MRP breaks tasks into smaller tasks that are executed concurrently by
independent processes (workers). The programs that execute these tasks concurrently
need to communicate in order to coordinate their actions.
InterProcess Communication
The Memory-based Planning Engine uses a combination of database pipes and database
tables for inter-process communication. The Memory-based Snapshot and Snapshot
Workers communicate with the Snapshot Monitor via database pipes. These pipes carry
messages that include requests for new tasks, task completion, and initiate the set
transaction read-only RDBMS feature. The Snapshot Delete Workers communicate via
the database table MRP_SNAPSHOT_TASKS. See also: Interprocess Communication
See Also
Processing Steps
Processes
Snapshot Tasks
Read Consistency
Profile options
In addition to MRP:Snapshot Workers, you can define the following profile options to
improve Memory-based Planning Engine performance:
MRP:Snapshot Workers
leading to increased storage space. One way to counter this side effect
is to export and reimport the tables affected by the planning processes.
Setting up
To run the Memory-based Planning Engine, you must define a number of target
processes in the concurrent processes in the concurrent manager. Use the following the
formula to determine the number you require:
T=4+2S
where
T = the number of target processes required to run the Memory-based Planning Engine
S = the number of snapshot defined in MRP:Snapshot Workers
See: Managing Concurrent Programs and Requests, Oracle Applications User's Guide
See Also
Processing Steps
Processes
Snapshot Tasks
Read Consistency
Interprocess Communication
H
Character Mode Forms and GUI Windows
Change Organization
Change Organization
DEMAND_CLASS QuickCodes
Forecast Sets
Folder Menu
or
Navigator: Inquiry > MRP > Workbench > Demand >
[Folder Menu]
or
Navigator: Inquiry > MRP > Workbench > Items >
[Folder Menu]
or
Navigator: Inquiry > MRP > Workbench > Supply >
[Folder Menu]
or
Navigator: Inquiry > MRP > Workbench >
Supply/Demand > [Folder Menu]
Planning Parameters
MRP Names
Launch MPS
Planner Tasks
Navigator: MPS > Workbench > [Status] > [Planner
Tasks]
or
Navigator: Inquiry > MPS > Status > [Planner Tasks]
or
Navigator: MRP > Workbench > [Status] > [Planner
Tasks]
or
Navigator: Inquiry > MRP > Status > [Planner Tasks]
or
Snapshot Tasks
Navigator: MPS > Workbench > Status > [Snapshot
Tasks]
or
Navigator: Inquiry > MPS > View Plan > Status >
[Snapshot Tasks]
or
Navigator: MRP > Workbench > Status > [Snapshot
Tasks]
or
Navigator: Inquiry > MRP > View Plan > Status >
[Snapshot Tasks]
Load Forecast
Copy/Merge Forecast
Planner Workbench
or
Navigator: MRP > Workbench > [Demand]
or
Navigator: MRP > Workbench > [Supply]
or
Navigator: MRP > Workbench > [Supply/Demand]
or
Navigator: MRP > Workbench > [Items] > [Demand]
or
Navigator: MRP > Workbench > [Items] > [Supply]
or
Navigator: MRP > Workbench > [Items] >
[Supply/Demand]
Run Reports
\Navigate Reports
Planning Manager
Requests window
Forecast Consumptions
Components
Plan]
or
Navigator: MRP > Workbench > [Supply/Demand] >
[Horizontal Plan]
or
Navigator: MRP > Workbench > [Supply] >
[Horizontal Plan]
or
Items
Navigator: MPS > Workbench > [Items]
or
Navigator: MRP > Workbench > [Items]
or
Where Used
Navigator: MPS > Workbench > [Items] > [Where
Used]
or
Navigator: MRP > Workbench > [Items] > [Where
Used]
or
Navigator: Inquiry > MPS > View Items > [Detail]
or
Navigator: Inquiry > MPS > View Items > [Bucketed]
> [Detail]
or
Master Production Schedule Items
Navigator: Inquiry > MPS > View Items
or
Master Production Schedule Reliefs
Navigator: MPS > Entries > [Reliefs]
or
Navigator: MPS > Items > [Bucketed] > [Detail] >
[Reliefs]
or
Navigator: MPS > Items > [Detail] > [Reliefs]
or
Navigator: Inquiry > MPS > View Entries > [Reliefs]
or
Navigator: Inquiry > MPS > View Items > [Bucketed]
> [Detail] > [Reliefs]
or
Navigator: Inquiry > MPS > View Items > [Detail] >
[Reliefs]
View Orders
Supply/Demand
Exceptions
View Reports
Requests window
View Workdates
\Navigate Inquiry WorkDates
Glossary
Acceptable Early Days
An item attribute the planning process uses to decide when to suggest rescheduling
orders for the item to an earlier date. The planning process only suggests rescheduling
orders for the item if the order is due to be received into inventory before the acceptable
early date. This attribute is used when it is more economical to build and carry excess
inventory for a short time than it is to reschedule the order. This attribute applies to
discretely planned items only. The attribute for repetitively planned items is Overrun
Percentage
Acceptable Rate Decrease
An item attribute the planning process uses to decide how much to decrease current
daily rates for the item inside the planning time fence. The planning process does not
suggest a new daily rate less than the current daily rate minus the acceptable rate
decrease amount. If you do not define a value for this attribute, the planning process
assumes that there is no lower limit to the new daily rate it can suggest for the item
inside the planning time fence. If you set this attribute to zero, the planning process
assumes it cannot suggest any rate less than the current daily rate inside the planning
time fence. Inventory defaults the value of this attribute to zero. This attribute lets you
minimize short term disruption to shop floor schedules by restricting short term rate
change suggestions. This attribute applies to repetitively planned items only.
Acceptable Rate Increase
An item attribute the planning process uses to decide how much to increase current
daily rates for the item inside the planning time fence. The planning process does not
suggest a new daily rate that is greater than the current daily rate plus the acceptable
rate increase amount. If you do not define a value for this attribute, the planning
process assumes there is no upper limit to the new daily rate that it can suggest for the
item inside the planning time fence. If you set this attribute to zero, the planning
process assumes it cannot suggest any rate greater than the current daily rate inside the
planning time fence. Inventory defaults the value of this attribute to zero. This attribute
lets you minimize short term disruption to shop floor schedules by restricting short
term rate change suggestions and applies to repetitively planned items only.
Glossary-1
accounting period
The fiscal period a company uses to report financial results, such as a calendar month or
fiscal period.
action message
Output of the MRP process that identifies a type of action to be taken to correct a
current or potential material coverage problem.
action result
A possible outcome of an order cycle action. You can assign any number of results to a
cycle action. Combinations of actions/results are used as order cycle action
prerequisites. See also order cycle, cycle action.
actual demand
The demand from actual sales orders, not including forecasted demand.
aggregate repetitive schedule
The sum of detail schedules for an item across all work in process manufacturing lines
in terms of a daily rate, and a start and end date.
aggregate resources
The summation of all requirements of multi-department resources across all
departments that use it.
anchor date
The start date of the first repetitive planning period. It introduces consistency into the
material plan by stabilizing the repetitive periods as time passes so that a plan run on
any of the days during the first planning period does not change daily demand rates.
append option
Option or choice to append planned orders to an MRP plan or an MPS plan during the
planning process. Append either after the last existing planned order, after the planning
time fence, or for the entire plan. The append option is used with the overwrite option.
See overwrite option
application building block
A set of tables and modules (forms, reports, and concurrent programs) that implement
closely-related entities and their processing.
assemble-to-order (ATO)
An environment where you open a final assembly order to assemble items that
customers order. Assemble-to-order is also an item attribute that you can apply to
Glossary-2
Glossary-3
Glossary-4
Glossary-5
When loading schedules from a forecast, the confidence percent is multiplied by the
forecast quantity to determine the schedule quantity
configuration item
The item that corresponds to a base model and a specific list of options. Bills of Material
creates a configuration item for assemble-to-order models.
CRP planner
A process that may optionally be run as part of the planning process. The CRP planner
calculates capacity requirements for resources and production lines using the material
requirements calculated by the planning process.
current aggregate repetitive schedule
The sum of all current work in process repetitive schedules for an item for all lines for a
given period in terms of a daily rate, and a start and end date. Current aggregate
repetitive schedules can be firm or partially firm. If all current repetitive schedules for
an item are firm, then the current aggregate repetitive schedule for the item is also firm.
If some, but not all the current repetitive schedules for an item are firm, then the current
repetitive schedule is partially firm.
current date
The present system date.
cutoff date
An indication of the last date to be included in a plan or horizon.
daily rate
The number of completed assemblies a repetitive schedule plans to produce per day.
Also known as production rate. See repetitive rate
database diagram
A graphic representation of application tables and the relationships among them.
deliver-to location
A location where you deliver goods previously received from a supplier to individual
requestors.
demand class
A classification of demand to allow the master scheduler to track and consume different
types of demand. A demand class may represent a particular grouping of customers,
such as government and commercial customers. Demand classes may also represent
different sources of demand, such as retail, mail order, and wholesale.
Glossary-6
demand management
The function of recognizing and managing all demands for products, to ensure the
master scheduler is aware of them. This encompasses forecasting, order management,
order promising (available to promise), branch warehouse requirements, and other
sources of demand.
Demand Time Fence
Item attribute used to determine a future time inside which the planning process
ignores forecast demand and only considers sales order demand when calculating gross
requirements for an item. Use this attribute to identify a time fence inside which you
wish to build to sales order demand only to reduce the risk of carrying excess
inventory. A value of Cumulative manufacturing lead time means MRP calculates the
demand time fence for the item as the plan date (or the next workday if the plan is
generated on a non workday) plus the cumulative manufacturing lead time for the item.
A value of Cumulative total lead time means MRP calculates the demand time fence for
the item as the plan date (or the next workday if the plan is generated on a non
workday) plus the total manufacturing lead time for the item. A value of Total lead time
means MRP calculates the demand time fence for the item as the plan date (or the next
workday if the plan is generated on a non workday) plus the total lead time for the
item. A value of User-defined time fence means MRP calculates the demand time fence
for the item as the plan date (or the next workday if the plan is generated on a non
workday) plus the value you enter for Planning Time Fence Days for the item.
Demand Time Fence Days
Item attribute used when you set the Planning Time Fence attribute to User-defined
time fence. MRP calculates the demand time fence for the item as the plan date (or the
next workday if the plan is generated on a non workday) plus the value you enter here.
department
An area within your organization that consists of one or more people, machines, or
suppliers. You can also assign and update resources to a department.
dependent demand
Demand for an item that is directly related to or derived from the demand for other
items.
destination forecast
The forecast you load into when copying a forecast into another forecast.
disable date
A date when an Oracle Manufacturing function is no longer available for use. For
example, this could be the date on which a bill of material component or routing
operation is no longer active, or the date a forecast or master schedule is no longer
Glossary-7
valid.
discrete job
A production order for the manufacture of a specific (discrete) quantity of an assembly,
using specific materials and resources, in a limited time. A discrete job collects the costs
of production and allows you to report those costs including variances by job. Also
known as work order or assembly order.
distribution resource planning (DRP)
Application of replenishment inventory calculations to assist in planning of key
resources contained in a distribution system, such as sourcing and transport. DRP is an
extension of distribution requirements planning, which applies MRP logic to inventory
replenishment at branch warehouses
dock date
The date you expect to receive a purchase order.
DRP
See distribution resource planning
due date
The date when scheduled receipts are currently expected to be received into inventory
and become available for use.
effective date
Date when an Oracle Manufacturing function is available for use. For example, this
could be the date a bill of material component or routing operation becomes effective,
or the date you anticipate revised item changes become part of a bill of material and can
no longer be controlled by an ECO.
end assembly pegging
A Pegging item attribute option the planning process uses to decide when to calculate
and print end assemblies for the item on the Planning Detail Report. Even if you do not
select this option, you can still calculate and view end assemblies for the item on-line.
end date
Signifies the last date a particular quantity should be forecast on a forecast entry. From
the forecast date until the end date, the same quantity is forecast for each day, week or
period that falls between that time frame. An entry without an end date is scheduled for
the forecast date only.
end item
Any item that can be ordered or sold. See finished good and product
Glossary-8
Glossary-9
for the item exceed the fixed lot size multiplier quantity, the planning process suggests
a single order with an order quantity that is a multiple of the fixed lot size multiplier
quantity. For repetitively planned items, when average daily demand for a repetitive
planning period falls short of the fixed lot size multiplier quantity, the planning process
suggests a repetitive daily rate equal to the fixed lot size multiplier quantity. When
average daily demand for a repetitive planning period exceeds the fixed lot size
multiplier quantity, the planning process suggests a repetitive daily rate that is a
multiple of the fixed lot size multiplier quantity.
fixed order quantity
An item attribute the planning process uses to modify the size of planned order
quantities or repetitive daily rates for the item. When net requirements fall short of the
fixed order quantity, the planning process suggests the fixed order quantity. When net
requirements for the item exceed the fixed order quantity, the planning process
suggests multiple orders for the fixed order quantity. For discretely planned items, use
this attribute to define a fixed production or purchasing quantity for the item. For
repetitively planned items, use this attribute to define a fixed production rate for the
item. For example, if your suppliers can only supply the item in full truckload
quantities, enter the full truckload quantity as the fixed order quantity for the item.
flow manufacturing
Manufacturing philosophy utilizing production lines and schedules instead of work
orders to drive production. Mixed models are grouped into families and produced on
lines balanced to the TAKT time.
focus forecasting
A simulation-based forecasting process that looks at past inventory activity patterns to
determine the best simulation for predicting future demand.
forecast
An estimate of future demand on inventory items. A forecast contains information on
the original and current forecast quantities (before and after consumption), the
confidence factor, and any specific customer information. You can assign any number of
inventory items to the forecast and use the same item in multiple forecasts. For each
inventory item you specify any number of forecast entries.
forecast consumption
The process of subtracting demand generated by sales orders from forecasted demand
thereby preventing demand being counted twice in the planning period.
Forecast Control
An item attribute used to determine the types of demand you place for the item. MRP
uses the option you choose here to guide the behavior of the key processes involved in
two-level master scheduling: forecast explosion, forecast consumption, planning,
Glossary-10
production relief, and shipment relief. This attribute is only appropriate for items that
are models, option classes, options, or mandatory components of models and option
classes. A value of Consume means you forecast demand for the item directly, rather
than exploding forecast demand to the item using the forecast explosion process. A
value of Consume and derive means you forecast demand for the item directly, or you
explode forecast demand to the item using the forecast explosion process, or you use a
combination of both methods to forecast demand for the item. A value of None means
you place sales order demand but do not forecast demand for the item.
forecast date
The date for a forecast entry for an item. A forecast for an item has a forecast date and
an associated quantity.
forecast demand
A part of your total demand that comes from forecasts, not actual sales orders.
forecast end date
A forecast end date implies that until that date, the same quantity is scheduled for each
day, week, or period that falls between the forecast date and the end date. A forecast
date with no forecast end date is the quantity for that particular day, week, or period,
depending on the bucket size.
forecast end item
The parent item for components that receive exploded forecasts during forecast
explosion. Used to identify the highest level planning or model item from which
forecasts for a component can be exploded.
forecast entry
A forecast for an inventory item stated by a date, an optional rate end date, and
quantity.
forecast explosion
Explosion of the forecast for planning and model bills of material. The forecasted
demand for the planning or model bill is passed down to create forecasted demand for
its components. You can choose to explode the forecast when loading a forecast.
forecast level
The level at which a forecast is defined. Also, the level at which to consume a forecast.
Example forecast levels include items, customers, customer bill-to, and customer ship to
locations.
forecast load
The process of copying one or more source forecasts into a single destination forecast.
Glossary-11
When copying forecasts, you can choose to overwrite all or a subset of existing entries
in the destination forecast, specify whether to explode the source forecast, and specify
whether to consume the source forecast. You can choose to modify the source forecast
by a modification percent, or roll the source forecast forward or backward by a
specified number of carry forward days. You can also load compiled statistical and
focus forecasts from Inventory, and you can use the forecast interface table to load
forecasts into MRP from external sources.
forecast set
A group of complementing forecasts. For each forecast set, you specify a forecast level,
consumption use, update time fence days, outlier update percents, disable date, default
time bucket and demand class. A forecast set can have one or many forecasts within it.
forward consumption days
A number of days forward from the current date used for consuming and loading
forecasts. Consumption of a forecast occurs in the current bucket and as far forward as
the forward consumption days. If the forward consumption days enters another bucket,
the forecast consumes anywhere in that bucket, as well.
gross requirements
The total of independent and dependent demand for an item before the netting of
on-hand inventory and scheduled receipts.
hard reservation
Sales order demand that you firm by reserving selected inventory for the purposes of
material planning, available to promise calculations, and customer service issues.
independent demand
Demand for an item unrelated to the demand for other items.
internal requisition
See internal sales order, purchase requisition.
internal sales order
A request within your company for goods or services. An internal sales order originates
from an employee or from another process as a requisition, such as inventory or
manufacturing, and becomes an internal sales order when the information is transferred
from Purchasing to Order Management. Also known as internal requisition or purchase
requisition.
kanban
A visual signal to drive material replenishment. A Kanban system delivers material into
production as needed to meet demand.
Glossary-12
Glossary-13
Make or Buy
An item attribute the Planner Workbench uses to default an appropriate value for
implementation type when implementing planned orders for the item. A value Make
means the item is usually manufactured. The Planner Workbench defaults the
implementation type for planned orders for the item to Discrete job. The planning
process passes demand down from manufactured items to lower level components. A
value of Buy means the item is usually purchased. The Planner Workbench defaults the
implementation type for planned orders for the item to Purchase requisition. The
planning process does not pass demand down from purchased items to lower level
components.
manual rescheduling
The most common method of rescheduling scheduled receipts. The planning process
provides reschedule messages that identify scheduled receipts that have inconsistent
due dates and need dates. The impact on lower level material and capacity
requirements are analyzed by material planners before any change is made to current
due dates.
master demand schedule
The anticipated ship schedule in terms of rates or discrete quantities, and dates.
master production schedule (MPS)
The anticipated build schedule in terms of rates or discrete quantities, and dates.
master schedule
The name referring to either a master production schedule or a master demand
schedule. See master demand schedule and master production schedule
master schedule load
The process of copying one or more source forecasts, master schedules, or sales orders
into a single destination master schedule. When copying forecasts, you can choose to
include all or a subset of sales orders, specify whether to consider demand time fence,
and specify whether to consume the source forecast during the load. You can also
specify update options to control consumption of the source forecast during the load.
When copying master schedules, you can choose to modify the source master schedule
by a specified number of carry forward days. When loading sales orders, you can
choose to load all or a subset of sales orders, and you can specify whether to consider
the demand time fence during the load. You can use the master schedule interface table
to load master schedules from external sources.
material requirements planning (MRP)
A process that utilizes bill of material information, a master schedule, and current
inventory information to calculate net requirements for materials.
Glossary-14
Glossary-15
the minimum order quantity. For repetitively planned items, when average daily
demand for a repetitive planning period falls short of the minimum order quantity, the
planning process suggests the minimum order quantity as the repetitive daily rate. Use
this attribute, for example, to define an order quantity below which it is not profitable
to build the item.
minimum rate
The minimum number of completed assemblies a production line can produce per
hour.
mixed model map
Used to design balanced lines. The projected volume and mix of demand for a group of
products is used to calculate weighted average work content times. These averages are
compared to TAKT time in order to regroup events into balanced operations, and
reallocate resources.
model bill of material
A bill of material for a model item. A model bill lists option classes and options
available when you place an order for the model item.
modification percent
Used to modify the destination master schedule entries or forecast entries you are
loading by a percent of the source entries.
module
A program or procedure that implements one or more business functions, or parts of a
business function in an application. Modules include forms, concurrent programs, and
subroutines.
MPS
See master production schedule.
MPS explosion level
An option for a master demand schedule that lets you limit the explosion through
unnecessary levels during the MPS planning process. Set the explosion level to the
lowest level on the bill of material that an MPS-planned item exists so the planning
process does not need to search through all levels for MPS-planned items.
MPS plan
A set of planned orders and suggestions to release or reschedule existing schedule
receipts for material to satisfy a given master schedule for MPS-planned items or
MRP-planned items that have an MPS-planned component. Stated in discrete quantities
and order dates.
Glossary-16
MPS-planned item
An item controlled by the master scheduler and placed on a master production
schedule. The item is critical in terms of its impact on lower-level components and/or
resources, such as skilled labor, key machines, or dollars. The master scheduler
maintains control for these items.
MRP
See material requirements planning.
MRP plan
A set of planned orders and suggestions to release or reschedule existing schedule
receipts for material to satisfy a given master schedule for dependent demand items.
Stated in discrete quantities and order dates.
MRP Planning Method
An item attribute used to decide when to plan the item. A value of MPS planning
means the item is planned by the MPS planning process. It is an item that you master
schedule and for which you require manual control. Choose this option for items with
independent demand, items that are critical to your business, or items that control
critical resources. A value of MRP planning means the item is planned by the MRP
planning process. Choose this option for non-critical items that do not require manual
control. These are typically dependent demand items. A value of DRP planning means
the item is planned by the DRP planning process. A value of DRP & MRP means the
item is planned by either a DRP planning or MRP planning process. A value of DRP &
MPS means the item is planned by either a DRP planning or MPS planning process. A
value of None means the item is neither MPS-planned or MRP-planned. It does not
require long-term plan planning of material requirements. Choose this option for high
volume and/or low cost items that do not warrant the administrative overhead of
material requirements planning. These are typically dependent demand items.
MRP-planned item
An item planned by MRP during the MRP planning process.
multi-department resource
A resource whose capacity can be shared with other departments.
nervousness
Characteristic exhibited by MRP systems where minor changes to plans at higher bill of
material levels, for example at the master production schedule level, cause significant
changes to plans at lower levels.
net change simulation
Process used to make changes to supply and demand and re-plan them.
Glossary-17
net requirements
Derived demand due to applying total supply (on-hand inventory, scheduled receipts,
and safety stock quantities) against total demand (gross requirements and reservations).
Net requirements, lot sized and offset for lead time, become planned orders. Typically
used for rework, prototype, and disassembly.
option
An optional item component in an option class or model bill of material.
option class
A group of related option items. An option class is orderable only within a model. An
option class can also contain included items.
option class bill of material
A bill of material for an option class item that contains a list of related options.
option item
A non-mandatory item component in an option class or model bill of material.
order date
The date an order for goods or services is entered. See also work order date.
order modifier
An item attribute that controls the size of planned orders suggested by the planning
process to mimic your inventory policies.
organization
A business unit such as a plant, warehouse, division, department, and so on. Order
Management refers to organizations as warehouses on all Order Management windows
and reports.
origination
The source of a forecast entry or master schedule entry. When you load a forecast or
master schedule, the origination traces the source used to load it. The source can be a
forecast, master schedule, sales order, or manual entry.
outlier quantity
The amount of sales order left over after the maximum allowable amount (outlier
update percent) was used to consume a forecast.
outlier update percent
The maximum percent of the original quantity forecast that a single sales order
Glossary-18
Glossary-19
Glossary-20
Glossary-21
total lead time for the item. A value of User-defined time fence means MRP calculates
the planning time fence for the item as the plan date (or the next workday if the plan is
generated on a non workday) plus the value you enter for Planning Time Fence Days
for the item.
Planning Time Fence Days
An item attribute MRP uses when you set the Planning Time fence attribute to
User-defined time fence. MRP calculates the planning time fence for the item as the plan
date (or the next workday if the plan is generated on a non workday) plus the value you
enter here.
postprocessing lead time
The time required to receive a purchased item into inventory from the initial supplier
receipt, such as the time required to deliver an order from the receiving dock to its final
destination.
preprocessing lead time
The time required to place a purchase order or create a discrete job or repetitive
schedule that you must add to purchasing or manufacturing lead time to determine
total lead time. If you define this time for a repetitive item, the planning process ignores
it.
primary line
See lead time line.
processing lead time
The time required to procure or manufacture an item. For manufactured assemblies,
processing lead time equals the manufacturing lead time.
product
A finished item that you sell. See also finished good.
production line
The physical location where you manufacture a repetitive assembly, usually associated
with a routing. You can build many different assemblies on the same line at the same
time. Also known as assembly line.
production rate
Hourly rate of assemblies manufactured on a production line.
production relief
The process of relieving the master production schedule when a discrete job is created.
This decrements the build schedule to represent an actual statement of supply.
Glossary-22
project
A unit of work broken down into one or more tasks, for which you specify revenue and
billing methods, invoice formats, a managing organization, and project manager and
bill rates schedules. You can charge costs to a project, as well as generate and maintain
revenue, invoice, unbilled receivable and unearned revenue information for a project.
project job
A standard or non-standard WIP job with a project reference. The valuation accounts
associated with this type of job will be project work in process. Any balance remaining
in such a job when it is closed will be reported as a variance.
project task
A subdivision of Project Work. Each project can have a set of top level tasks and a
hierarchy of subtasks below each top level task. You can charge costs to tasks at the
lowest level only. See also Work Breakdown Structure.
projected available balance
Quantity on hand projected into the future if scheduled receipts are rescheduled or
cancelled, and new planned orders are created as per recommendations made by the
planning process. Calculated by the planning process as current and planned supply
(nettable quantity on hand + scheduled receipts + planned orders) minus demand (gross
requirements). Note that gross requirements for projected available includes derived
demand from planned orders. Note also that the planning process uses suggested due
dates rather than current due dates to pass down demand to lower level items. See
current projected on hand.
projected on hand
Quantity on-hand projected into the future if scheduled receipts are not rescheduled or
cancelled, and new planned orders are not created as per recommendations made by
the planning process. Calculated by the planning process as current supply: (nettable
quantity on hand + scheduled receipts) - gross requirements. Note that gross
requirements for projected on hand does not include derived demand from planned
orders. Note also that the planning process uses current due dates rather than
suggested due dates to pass down demand to lower level items. See projected available
balance
purchase order
A type of purchase order you issue when you request delivery of goods or services for
specific dates and locations. You can order multiple items for each planned or standard
purchase order. Each purchase order line can have multiple shipments and you can
distribute each shipment across multiple accounts. See standard purchase order and
planned purchase order.
Glossary-23
purchase requisition
An internal request for goods or services. A requisition can originate from an employee
or from another process, such as inventory or manufacturing. Each requisition can
include many lines, generally with a distinct item on each requisition line. Each
requisition line includes at least a description of the item, the unit of measure, the
quantity needed, the price per item, and the Accounting Flexfield you are charging for
the item. See also internal sales order.
rate-based capacity
Capacity planning at the production line level. Required capacity, available capacity,
and capacity load ratio are calculated for individual production lines. Required and
available capacity are stated in terms of production rate per line per week.
read consistency
A consistent view of all table data committed by transactions and all changes made by
the user, up to the time of the read.
Reduce MPS
An item attribute the Planning Manager uses to decide when to reduce the quantity on
master production schedule entries for the item to zero. A value of None means the
Planning Manager does not reduce order quantities on master production schedule
entries. A value of Past due means the planning process reduces order quantities on
master production schedule entries to zero when the due date for the entry becomes
past due. A value of Within demand time fence means the planning process reduces
order quantities on master production schedule entries to zero when the due date for
the entry moves inside the demand time fence. A value of Within planning time fence
means the planning process reduces order quantities on master production schedule
entries to zero when the due date for the entry moves inside the planning time fence.
repetitive MRP plan
A set of optimal repetitive schedules which satisfy a given master schedule for
repetitive items.
repetitive planning
The planning of demand or production for an item in terms of daily rates rather than
discrete quantities.
Repetitive Planning (item attribute)
An item attribute the planning process uses to decide whether to plan material
requirements for the item in terms of discrete quantities or repetitive daily rates.
repetitive planning period
A period, defined as a number of days, that smooths the production rate over time.
Glossary-24
With repetitive planning periods, you can prevent your planned repetitive production
rate from fluctuating too frequently.
repetitive processing days
The number of days you plan to work on a repetitive schedule, from the first unit start
date to the last unit start date.
repetitive rate
The daily rate for a repetitive schedule. See daily rate.
repetitive schedule
The process of dividing suggested aggregate repetitive schedules and allocating them
across individual production lines, based on predefined line priorities and production
rates.
repetitive schedule allocation
The process of dividing suggested aggregate repetitive schedules and allocating them
across individual production lines, based on predefined line priorities and production
rates.
required capacity
The amount of capacity required for a resource or production line.
required hours
The number of resource hours required per resource unit to build one unit of the bill of
resources item.
required rate
The production rate allocated to an individual production line by the repetitive
schedule allocation process.
requisition
See purchase requisition and internal sales order.
rescheduling assumption
A fundamental piece of planning process logic that assumes that existing open orders
can be rescheduled into closer time periods far more easily than new orders can be
released and received. As a result, the planning process does not create planed order
receipts until all scheduled receipts have been applied to cover gross requirements.
reservation
A guaranteed allotment of product to a specific sales order. A hold is placed on specific
Glossary-25
terms that assures that a certain quantity of an item is available on a certain date when
transacted against a particular charge entity. Once reserved, the product cannot be
allocated to another sales order or transferred in Inventory. Oracle Order Management
checks ATR (Available to Reserve) to verify an attempted reservation. Also known as
hard reservation.
resource
Anything of value, except material and cash, required to manufacture, cost, and
schedule products. Resources include people, tools, machines, labor purchased from a
supplier, and physical space.
resource group
Resources grouped together according to user-defined criteria to facilitate bill of
resource generation and capacity planning.
resource offset percent
An operation resource field that represents, as a percent of the processing lead time for
an item, the item when a resource is required on a routing. For example, if the
processing lead time for an item is 10 days, and the resource is required on the fourth
day, then the resource offset percent is 30%. Capacity uses resource offset percent to
calculate setback days during the bill of resource load process.
resource roll up
Rolls up all required resources for a end assembly based on the routing and bill of
material structure.
resource set
A grouping of bills of resources.
resource hours
The number of hours required by a repetitive schedule, discrete job or planned order.
resource units
The number of units of a resource available for this resource at this operation.
revision
A particular version of an item, bill of material, or routing.
rough cut capacity planning
The process of converting the master schedule into capacity needs for key resources. See
routing-based capacity and rate-based capacity
Glossary-26
Glossary-27
Glossary-28
committed after its execution. No transactions are written after the command is
executed. See read consistency.
setback days
The number of days set back from the assembly due date that a resource is required to
build the assembly.
shift
A scheduled period of work for a department within an organization.
ship-to address
A location where items are to be shipped.
shipment relief
The process of relieving the master demand schedule when a sales order ships. This
decrements the demand schedule to represent an actual statement of demand.
Shrinkage Rate
An item attribute the planning process uses to inflate the demand for the item to
compensate for expected material loss. Enter a factor that represents the average
amount of material you expect to lose during your manufacturing process. For example,
if an average 20% of all units of the item fail final inspection, enter a shrinkage rate for
the item of 0.2. In this example, the planning process always inflates net requirements
for the item by a factor of 1.25 (1 / 1 - shrinkage rate).
simulation schedule
Unofficial schedules for personal use that contain the most current scheduled item
information. You can print Simulation schedules, but you cannot confirm or send them
via EDI.
simulation set
group of capacity modifications for resource shifts to simulate, plan, or schedule
capacity.
snapshot
The only phase under the memory-based planning engine. The snapshot takes a
snapshot or picture of supply and demand information at a particular point in time. The
snapshot gathers all the information about current supply and demand that is required
by the planner to calculate net material requirements, including on-hand inventory
quantities and scheduled receipts. Under the memory-based planning engine, explosion
and planning occur in the snapshot phase.
Glossary-29
Glossary-30
Glossary-31
usage quantity
The quantity of a component, including component yield required to produce one
assembly in a discrete job or repetitive schedule as stated on the bill of materials.
utilization
Ratio of direct time charged to the clock time scheduled for the resource.
work order date
The date to begin processing the paperwork for the discrete job. This date is offset from
the start date by the preprocessing lead time.
worker
An independent concurrent process that executes specific tasks. Programs using
workers to break large tasks into smaller ones must coordinate the actions of the
workers.
Glossary-32
Index
A
Alerts
appendix, C-1
forecast overconsumption detail, C-1
forecast overconsumption summary , C-1
assignment sets
assignment hierarchy, 5-8
defining, 5-8
B
bills of distribution
See BODs, 5-8
BODs, 5-8
defining, 5-8
C
crp reports, 11-33
Customized Find Windows
find exceptions window, D-2
find items window, D-4
find supply/demand Window, D-5
Navigating through a customized find
window, D-1
Customized Find Windows
appendix, D-1
Customizing the Planning Exception Messages
Process
appendix, E-2
F
Find Exceptions Window
appendix, D-2
Find Items Window
appendix, D-4
Find Supply/Demand Window
appendix, D-5
forecast
explosion, 2-36
forecast explosion
logic, 2-36
Forecast Overconsumption Detail
appendix, C-1
Forecast Overconsumption Summary
appendix, C-1
Forecasts - Statistical and Focus
appendix, F-1
K
kanban calculations
viewing and updating, 12-8
kanban tools menu, 12-10
L
Late Order Report, 11-21
Index-1
N
Navigating through a Customized Find Window
appendix, D-1
O
On Hand vs. Available Report, 11-7
Oracle MRP Character Mode Forms and
Corresponding GUI Windows
appendix, H-1
P
parallel processing
inter-process communication, 14-2
overview, 14-1
planner parallel processing, 14-8
planning manager, 14-9
process control, 14-1
single processor machine, 14-2
snapshot, 14-4
snapshot parallel processing, 14-8
Planning Exception Messages Item Type
appendix, E-4
Planning Exception Messages Workflow
appendix, E-1
planning manager worker, 11-32
planning parameters, 11-33
Processing Steps
appendix, G-1
project MRP setup tasks, 13-2
R
Report
late order, 11-21
reports
master schedule comparison report, 11-23
Reports
on hand vs. available, 11-7
Index-2
W
Windows and Navigator Paths
appendix, B-1
Workflow - Planning Exception Messages
customizing the planning exception messages
process, E-2
exception process 1 activities , E-5
exception process 2 activities, E-8
planning exception messages item type, E-4
summary of exception process 1, E-5
summary of exception process 2, E-7
summary of planning exception messages
activities, E-5
supported and unsupported customizations,
E-2
workflow process forward (node 2), E-6, E-9
Workflow Process Forward
appendix, E-9
Workflow Process Forward (Node 2)
appendix, E-6