Contract Closeout, Reporting and Documentation System
Contract Closeout, Reporting and Documentation System
Contract Closeout, Reporting and Documentation System
REPORTING/DOCUMENTATION
SYSTEM
Construction Method and Management
Transfer of
Owner-purchased
material
Monitor
Contrator's
progress
Project
Documentation
System
Daily reporting
system#4. Slide
4
Administer QA
Monitor Cost
record
Establish Cash
Flow report
Prepare
Summary
To the Owner
Receive and
Evaluate notices
Communication
and
Exchange of
information
Review safety
plan
Establish a system
To control Contractor's
payment
Review drawings
Before approving
Final payment
Reporting System
Project
documentation
Requirements
Resolve Changes
Establish report
compilation,
organization and
turnover of these
materials
requirements for
spare parts and
warranties.
Final Inspections
with the owner
and designer
expedite
completion of the
Contractors
submittals
and compliance
of all permit
requirements
should provide
the owner with a
list of contacts for
remaining work
at the owners
request, the CM
should assist in
move-in/start up.
, summarizing the
project history
...reporting system
Daily Construction Report
PM
Area superintendent
Project engineers
inspectors
Report number
Date and day report
Project name and number
Weather conditions
Name of contractor whose work
was specifically involved
Workforce
Describe all works in progress
Problems and difficulties
encountered
Completed form should be signed
and dated.
...Documentation System
Capable of:
Recording
Storing
Retrieving information
Technical
Financial
administrative
reasons:
1. original contract
2. bonds and assurance certificates
3. pre-contract negotiation
4. plans and specifications issued for contruction
5. notice to proceed.
6. any notices or changed conditions, request for *CO,
or *CO proposals
7.directives
8. log of all requested, proposed and executed *CO.
9. formal contract.
10. request for final inspection.
11. punch lists.
12. certificate of final inspection.
*change order
1. daily reports
2. daily diaries
3. daily labour reports
4. accident reports
5. progress photos
6.material delivery
reports
1. directives
2. meeting minutes
3. general
correspondence
Contract Closeout
Closeout Document:
warranties/guarantees
Certifications
maintenance manuals
contractors' statements (tax forms)
Targeted Small Business Reporting forms (if applicable), etc.
Closeout
Process