Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Capital Cost

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 7

Capital Cost

Equipment
Mixer
Boiler
Granulator
Screening
Cooler
Crusher
Oil coating
Dust coating
Packaging
Conveying Machine &
belt
Pump

Quantity
1
1
1
2
1
1
1
1
1
1

Cost
4000
9200
32000
5000
280000
16000
4000
4000
9000
10000

2000
Total Cost

380200(RM1311690)

Based on Table 7.5, the basis for the chemical engineering plant cost index;
61% of the total plant cost are the equipment, while the other 39% is the
installation, labor, supervision and engineer.
So if the total cost of equipment is RM1311690 = 61%,
The value of 39% can be obtain by cross-multiply with 61% = RM1311690,
61% = RM1311690
39% = RM x
X = RM838621
61% + 39% = 100% total cost of the plant
RM1311690 + RM838621 = RM2150311
The total capital cost of this plant is RM2150311

Cost of Operating Labor

Equipment
Mixer
Granulator
Boiler
Dust Coating
Screener (2)
Cooler
Crusher
Packaging
Conveying belt & machine
Oil Coating

Workers
2
2
1
1
2
2
1
2
4
1
Total Workers 18

The total workers is 18 and there are 3 shift per day.


18 workers x 3 shift per day = 54 workers require per day
8 hour/day x 5.5 RM/hour x 343 day/year = 15092 RM/year
15092 RM/year x 54 workers = RM 814968/year
A single operator works on the average 49 weeks a year (3 weeks time off),
five 8-hour shifts a week. This is amounts to (49 weeks/year x 5 shifts/week)
245 shifts per operator per year. A chemical plant normally operates 24
hours/day. This requires (365 days/year x 3 shifts/day) 1095 operating shifts
per year. The number of operator needed to provide this number of shifts is
[(1095 shifts/year)/ (245 shifts/operator/y) or approximately 4.5 operators

Cost of Utilities

Electric
Equipment
Mixer
Granulator
Boiler
Dust Coating
Screener (2)
Cooler
Crusher
Packaging
Conveying belt & machine
Oil Coating

Power (KW/per cycle)


30
25
252
30
1.5
15
37
0.75
27.4
30
Total Power

448.65
The total power per cycle is 448.65 KW
448.65 KW/cycle x 12 cycle/day = 5383.8 KW/day
5383.8KW/day x 343 day/year = 1846643.4 KW/year
1846643.4 KW/year x RM0.288/KW = RM 531833/year
Water
Equipment
Boiler

Water (m3) per cycle


1.5

1.5m3/cycle x 12 cycle/day x 343 day/year x RM2.28/m3 = RM14076


Total Utilities
Water + Electric = RM14076 + RM 531833 = RM545909/year ~
RM550000/year (estimated)

Cost of Raw Material


Raw materials for the production of fertilizer is urea, triple superphosphate,
muriate of potash and German Kieserite.

Urea:
Mass flow rate of urea= 10556.4 kg/day
Price for urea per metric tonne= RM 895.31/ tonne
Yearly

cost

of

urea

(10556.4

kg/d)

(343

d)

(RM

895.31/tonne)

(1tonne/1000kg)
= RM 3241778.92
Triple Superphosphate
Mass flow rate of triple superphosphate= 9314.4 kg/d
Price for urea per metric tonne= RM1205.22 / tonne
Yearly

cost

of

triple

superphosphate=

(9314.4kg/d)(343

d)(RM

1205.22/tonne)(1tonne/1000kg)
= RM 3850484.10
Muriate Of Potash
Mass flow rate of muriate of potash= 6284.4 kg/d
Price for urea per metric tonne= RM 688.70/ tonne
Yearly cost of triple superphosphate= (6284.4kg/d)(343 d)(RM 688.70/tonne)
(1tonne/1000kg)
= RM 1484526.73

German Kieserite
Mass flow rate of german kieserite= 3844.8 kg/d
Price for urea per metric tonne= RM 619.83/ tonne
Yearly cost of german kieserite= (3844.8kg/d)(343 d)(RM 619.83/tonne)
(1tonne/1000kg)
= RM 817410.98
Total Amount Cash of raw material= RM 3241778.92 + RM 3850484.10 +RM
1484526.73
+ RM 817410.98
= RM 9394200.73

Estimating Manufacturing Cost


By referring to the Table 8.2, page 200, Analysis, Synthesis, and Design of
Chemical Processes:
Direct manufacturing Costs (A)
i)
ii)
iii)
iv)
v)
vi)
vii)

Patents and royalties


(0-0.06)COM = (0.05382)(15156228.64) = 815737.54
Laboratory charges
(0.1-0.2)COL = (0.2)(814968) = RM 292864
Operating supplies
(0.1-0.2)(line vi) = (0.2)(250000) = RM50000
Maintenance and repairs
(0.02-0.1)FCI = (0.1)(2500000) = RM250000
Direct supervisory and clerical labor
(0.1-0.25)COL = (0.25)(814968) = RM366080

Fixed Manufacturing Costs (B)


i)
ii)
iii)

Depreciation
0.1 FCI = 0.1(2500000) = RM250000
Local Taxes and insurance
(0.014-0.05)FCI = (0.05)(2500000) = RM125000
Plant overhead costs
(0.5-0.7)(line A.vii + line A.vi + COL) = (0.7)(2080400) = RM
1456280

Total Fixed Manufacturing Costs (C)


i)
ii)
iii)

Administration costs
0.15 (COL + line A.vii + line A.vi) = RM312060
Distribution and selling costs
(0.02-0.2)COM = (0.2)(15156228.64) = RM3031245.6
Research and development
(0.05)COM = (0.05)(15156228.64) = RM757811.4

TOTAL COST OF MANUFACTURING (COM) = RM 18909353.8

You might also like