Doe Net Metering
Doe Net Metering
Doe Net Metering
According to Wikipedia Net metering is an electricity policy for consumers who own
renewable energy facilities (such as solar power) which allows them to use
electricity whenever needed while contributing their production to the grid.
In the Philippines, net-metering is the first policy mechanism of the Renewable
Energy Act of 2008 which has been fully implemented.
The picture below illustrates the flow of electricity from power generation via high
voltage transmission and distribution utilities to the end-user who can now install a
renewable energy facility and send not needed electricity back into the distribution
grid and earn credit for this export.
This Frequently Asked Questions section of the guide addresses net-metering policy,
regulation and standards in the Philippines. Further clarification on the subject of
accumulated peso credits, exemption from the imposition of the Universal Charge,
Certificate of Compliance (COC) for Renewable Energy (RE) facilities, and the
treatment RE facilities with installed capacity greater then 100KW is provided in a
letter by the Energy Regulatory Commission dated November 25, 2013 in the
annexes.
Q3. What is the legal basis of ERC in approving a net-metering program for renewable
energy in the Philippines?
A3. Section 10 of the Renewable Energy Act of 2008 (Republic Act No. 9513)
provides that subject to technical considerations and without discrimination and
upon request by distribution end-users, DUs shall enter into net-metering
agreement with qualified end-users who will be installing the RE system. The ERC, in
consultation with the NREB and the electric power industry participants, shall
establish net-metering interconnection standards and pricing methodology and
other commercial arrangements necessary to ensure success of the net-metering
for renewable energy.
Q4. Why is there a capacity limit of 100 kW placed on RE systems under the net-metering
program?
A4. This is because net-metering, as defined under Section 4 (gg) of the RE Law,
refers only to a system appropriate for Distributed Generation (DG). DG, as defined
under Section 4 (j) of the RE Law, as small generation entities supplying directly to
the distribution grid, any one of which shall not exceed one hundred kilowatts (100
kW) in capacity.
Q5. What types of power generating facilities are eligible for net-metering?
A5. RE facilities such as solar, wind, biomass or biogas energy systems, or such
other RE Systems not exceeding 100 kW in power generating capacity, capable of
being installed within the customers premises, are eligible to participate in the netmetering program.
You also earn peso credits on any excess electricity exported to the DU equivalent
to the DUs blended generation cost, excluding other generation adjustments. The
peso credits earned is then used to reduce your electric bill/s.
Q11. How do I determine the DUs blended generation cost for a particular month?
A11. DUs are required to publish in their websites their monthly generation cost. You
only need to access your DUs websites to get the blended generation cost of your
DU for a particular month so that you will know how much credit you are entitled to
on any excess electricity you export to your DU.
Q12. Please give an example of a DUs blended generation cost, say for the billing month
of November 2013?
A12. Using Meralcos generation costs for November 2013 (as downloaded from its
website), its blended generation costs, excluding other generation adjustments, for
November 2013 is highlighted in yellow (see table).
Q14. Please give a simulation of how my electric bill would look like if I am a net-metering
customer with a 2kW solar-powered facility installed on my roof top?
A14. See assumptions and simulated electric bill below:
shorten to the extent possible the payback period of your investment in the solar
roof top facility.
If the conduct of a DAS is necessary, the DU issues an offer of DAS service to the
applicant. Within fifteen (15) days from receipt of the DAS offer, the applicant
informs the DU whether or not to proceed with the DAS. Upon acceptance of the
DAS offer and payment of the DAS fee by the applicant, the DU has thirty (30) days
to complete the study. Within five (5) days from completion of the DAS, the DU
informs the applicant of the results of the study.
2.D Energization
Once the construction is completed, the applicants installed facilities will undergo
testing and commissioning to be witnessed by the DU. Commissioning will include
inspection of the system components and functional tests to ensure compliance
with the Net-Metering Interconnection Standards.
The flow chart on the following page illustrates the application process for netmetering.
When all of the electrical systems have been installed, the applicant submits a
request for inspection to the Electrical Division. The Electrical Division then assesses
and evaluates the installation at the site for compliance with the National Building
Code and the Philippine Electrical Code, based on the plans and specifications of the
building that were submitted to the agency. If satisfied, the Electrical Division then
issues a Certificate of Final Electrical Inspection.
3.B Requirements
The following are the required documents to be submitted to the electrical division
of the concerned LGU:
3.C Timeline
3.D Fees
Generally, all LGUs adopt the schedule of fees set by the National Building Code of
the Philippines for electrical fees as per NBCDO Memorandum Circular No. 1 series
of 2004 issued last November 16, 2004. The following schedule (d.1 through d.6) is
used for computing electrical fees in residential, institutional, commercial, and
industrial structures for Quezon City, Manila and Makati City. Pasig City, however,
has a different schedule of fees that was enacted by the city government through a
City Ordinance.