Pump Room Method Statement
Pump Room Method Statement
Pump Room Method Statement
CONTRACT NO:
DATE :
S.
No
ACTIVITY
PREPARATION
FOR
INSTALLATION
EQUIPMENTS /
TOOLS
REQUIRED
SAFETY
PRECAUTIONS
WORK
SEQUENCE
PROCEDURE
1. Cleaning location area project
2. Preparation equipment scaffolding, jack hammer and stampping
3. Preparation material wooden, plywood, and rebar
1.
2.
3.
4.
5.
6.
7.
1.
2.
3.
4.
5.
1.
2.
3.
4.
REMARKS
DETAIL WORK
SECOND
Scaffolding
Body harness
Helmet
Ear plug
Safety shoes
Welding visor and face shield
Concrete vibrator
Perform safety talk before doing the work
Using of body harnes for working
Use a welding visor if required in the welding work
Use of safety shoes to avoid because of the nails and slippery
conditions
To work the chipping of the concrete piles have to use ear plugs
Chipping of concrete pile
leveling and compacting the soil before lean concrete
Instalation of rebar and form work column and beam concrete work
be done before casting
Casting work using a hanging bucket on a crane 50 T
DETAILED WORK SEQUENCE
Ref: AE-JMS-001
Page 1 of 5
CONTRACT NO:
DATE :
SHIPMENT
1. Concrete Slab Work :
Work was carried out after completion of work the concrete slab and
then proceed with the installation of rebar before work casting.
Implementation should use a vibrator to avoid a honey comb on the
concrete slab
2. Concrete Wall Work :
The first work is done prior to installation of scaffolding and working
steel rebar form work wall.
Second step after the completion of the working is the installation of
scafolding that serves as a peri formwork beam support of the wall
Assembly of steel rebar beams carried on top of the column, so do
safety by using a body harness in doing the steel rebar working on
the turbine installation to prevent falls from height at the location of
the wall
Implementation of the wall molding using a hanging concrete bucket
to a crane of capacity 50 ton.
3. Concrete Top Slab Work :
Demolish of formwork done before the pump room wall installation
work scaffolding.
Installation of scaffolding to work on the support of timber formwork
concrete top slab.
Implementation of the wall molding using a hanging concrete bucket
to a crane of capacity 50 ton.
Ref: AE-JMS-001
Page 2 of 5
CONTRACT NO:
DATE :
Ref: AE-JMS-001
Page 3 of 5
CONTRACT NO:
DATE :
Ref: AE-JMS-001
Page 4 of 5
CONTRACT NO:
DATE :
Reviewed By : PT AE MHS
Approved By :
Signature
Signature
Signature
Name
Name
Name
Date
Date
Date
Reviewed By :
Signature
Name
Date
Reviewed By :
Signature
Name
Date
Reviewed By :
Signature
Name
Date
Ref: AE-JMS-001
Page 5 of 5