3.16 SB: Managing A Stage Boundary: An Introduction To PRINCE2® 22
3.16 SB: Managing A Stage Boundary: An Introduction To PRINCE2® 22
3.16 SB: Managing A Stage Boundary: An Introduction To PRINCE2® 22
Corp..
Report Highlights Create Regular reports to the Project Board to let them know
how well the stage is going according to the plan.
By Frank Turley
Management-Plaza.com
Direction
(SB) Managing a
Stage Boundary
Highlight Reports
Give ad hoc
direction
Exception Report
Auth.
2 Proceed
Auth.next
stage
Authorize a Stage
or Exception Plan
Authorize Project
Approved PID
Management
22
Delivery
Work Package
Work Package
Accept a WP
Eig h t P M d a y to d a y a c tivitie s
Work Package activities
1) Authorize Work Package
2) Review Work Package status
3) Receive completed Work Packages
Monitoring & Reporting activities
4) Review the stage status
5) Report Highlights
Issues activities
6) Capture & examine issues & risks
7) Escalate issues & risks
8) Take corrective action
Work Package
Completed WP
As you can see, we have already covered four of these in the previous slides. One final comment:
These activities can be done numerous times by the Project Manager and there is no set order.
To confirm to the Project Board which products have been produced in the current stage
as documented in the stage plan, and also update the Project Plan to show what has
been done so far and forecast the planning for the next stage.
o So you see, the Project Plan is a living document (kept up to date)
Management Plaza