EOQ Problems
EOQ Problems
EOQ Problems
Problem Summary
Prob. #
Concepts Covered
8.1
8.2
8.3
8.4
8.5
8.6
8.7
8.8
8.9
8.10
8.11
8.12
8.13
8.14
8.15
8.16
8.17
8.18
8.19
8.20
8.21
8.22
8.23
8.24
8.25
8.26
8.27
8.28
8.29
Chapter 8 - 1
Level of
Difficulty
1
2
2
3
Notes
3
2
1
2
3
2
3
3
1
1
1
2
2
2
4
3
2
3
4
3
1
3
2
3
4
8.30
8.31
8.32
8.33
8.34
8.35
8.36
8.37
8.38
8.39
8.40
8.41
8.42
8.43
8.44
8.45
8.46
8.47
8.48
8.49
8.50
2
5
3
5
3
3
Chapter 8 - 2
3
1
2
8
5
6
3
1
3
6
1
4
3
7
Problem Solutions
8.1 See file Ch8.1.xls
Q* = 340
R = 25
Culton should order 340 bottles when the inventory reaches 25 bottles.
Chapter 8 - 3
INPUTS
Annual Demand, D =
Per Unit Cost, C =
Annual Holding Cost Rate, H =
Annual Holding Cost Per Unit, Ch =
OPTIMAL
OUTPUTS
Values
104000.00
16.00
0.15
2.4000
Order quantity, Q* =
Cycle Time (in years), T =
# of Cycles Per Year, N =
Reorder Point, R =
Total Annual Cost, TC(Q*)
=
200.00
Order Cost, Co =
Lead Time (in years), L =
Safety Stock, SS =
Values
10001
0.096163462
10.3989601
1426680.81
DISCOUNTS
Breakpoin
t
1
1001
5001
10001
Level
0
1
2
3
Discount
Price
16.0000
15.2000
14.4000
13.6000
Q*
4163
4271
4389
4516
Modified
Q*
4163
4271
5001
10001
TC(Q*)
1673992.00
1590538.99
1507160.25
1426680.81
Range
Unit Cost
Qi
Modified
Qi
Ordering
Cost
Holding
Cost
1 1000
1001 5000
5001 10000
10001 or more
16
15.2
14.4
13.6
4163
4271
4389
4516
4271
5001
10001
Non
200(104000)/4271
200(104000)/5001
200(104000)/10001
Purchasing
Cost
Total
Cost
Optimal
2.28(4271)/2
15.2(104000)
2.16(5001)/2
14.4(104000)
2.04(10001)/2 13.6(104000)
1590538
1507160
1426680
.15(15.2) = 2.28
Since 4163 falls above the range its unit cost applies it is non optimal
.15(14.4) = 2.16
Since 4271 falls inside the qualifying range it stays unmodified and the corresponding ordering, holding, and purchasing
cost need to be calculated.
Since 4389 falls to the left of the qualifying range it needs to be increased until at 5001it qualifies for the discounted cost of
$14.40. The same concept applies to Q3 = 4516.
Optimal policy: Order 10001 pairs because the minimum total cost of $1,426,680 is attained at Q = 10001.
Chapter 8 - 4
8.3
ADM should manufacture 2,000 units during each production run. There will be 3 production runs per
year.
Hand Calculations:
Annual demand = D = 12(500) = 6000
Annual production = P = 12(2000) = 24000
Set up cost = C0 = 2000
Unit cost = C = 40
Holding rate = H = .2
N= D/Q = 6000/2000 = 3
Chapter 8 - 5
Playhouse World should order 14 playhouses. Approximately 14% of customers will have to wait for
delivery.
Hand Calculations:
This is the EOQ model with planned shortages.
Cs = 50*52 = 2600; Cb = 10; C = 3500; D = 2(12) = 24; Co = 1500; L = 1 month. Ch = 1500.
After the substitutions of the parameter values we have Q * = 13.68, and S* = 1.94.
The percentage of customers who will have to wait is 1.94/13.68*100 = 14.18 (this is so because the cycle
demand is 13.68 of which 1.94 units are not sold on time).
Note: The reorder point is R = LD S = (1month)(monthly demand) shortage = 1(2) 1.94 = .06
Chapter 8 - 6
Chapter 8 - 7
Chapter 8 - 8
b. Re-order point
Chapter 8 - 9
INPUTS
Annual Demand, D =
Per Unit Cost, C =
Annual Holding Cost Rate, H =
Annual Holding Cost Per Unit, Ch =
Set Up Cost, Co =
Annual Production Rate, P =
Lead Time (in years), L =
Safety Stock, SS =
Values
54750.00
2.25
0.20
0.4500
90.00
146000.00
OPTIMAL
OUTPUTS
Order Quantity, Q* =
Cycle Time (in years), T =
# of Cycles Per Year, N =
Reorder Point, R =
Total Annual Variable Cost, TV(Q*) =
Total Annual Cost, TC(Q*) =
Chapter 8 - 10
Values
5919.46
Chapter 8 - 11
Chapter 8 - 12
Chapter 8 - 13
Chapter 8 - 14
Hand Calculations:
D = 7(365) = 2555; Ch = .2(.8) = .16; Co = 25. SS = 15
a. Buyright should order
Chapter 8 - 15
a. Buyright should order Q* = 864 Stick razors (6 lots of 144) and use a reorder point of R = 55
razors.
b. Days between orders = .3382*365 = 123 calendar days
c. Total Annual Cost (including holding cost of safety stock) = $2,190.25 and the Projected Net
Annual Profit = 2,555*($1.49) - $2,190.25 = $1,616.70.
This solution can also be obtained by adding a cell for NL, number of lots, in G13 and a constraint in
cell G14, =$H$5 - $G$14*144. Solver changes are Changing Cell becomes G13 with constraints G13
= Integer and G14 = 0.
Chapter 8 - 16
a. The order quantity is Q * = 2,200 boxes or 22 increments when the inventory level reaches R = 425
boxes.
b. The number of days between orders = .1303*365 = 47.6 calendar days
c. Total Annual Cost (including holding cost of safety stock) = $16,536.25 and the Projected Net
Annual Profit = 16,900*($1.29) - $16,536.25 = $5,264.75.
Chapter 8 - 17
Chapter 8 - 18
Chapter 8 - 19
Chapter 8 - 20
Chapter 8 - 21
D = 52*21 = 1092. From the sample the weekly mean demand based on the 8 weeks moving average
approach = 21. So for a 2-week lead time we have L = 21*2 = 42 and L = 5.45 (given).
a. The optimal order quantity is Q* = 177 (rounded) based on the EOQ model. A 96% cycle service
level corresponds to a z value of approximately 1.75. Hence, the reorder point equals + z.96*L = 42
+ 1.75*5.45 = 51.54 = 52 (rounded up).
b. Days between orders equals Q*/D = .1618 years = .1618*365 = 59 calendar days
c. Total annual inventory cost (including safety stock holding cost) = CoD/Q* + ChQ*/2 + ChSS + CD =
$9,946.93 (note that the safety stock = SS = z.96*L = 1.75(5.45) = 9.5375)
Comment: Suppose management decides to set the re-order point at R = 50 units. What is the new
cycle service level? From the reorder point formula we have 50 = L+zSLL = 42+zSL(5.45) which
yields zSL = (50 42)/5.45 = 1.47. The service level is found from the normal table or from
=normdist(1.47) = .929. The safety stock for this case is 50 42 = 8.
Chapter 8 - 22
Chapter 8 - 23
Hand Calculations
D = 25000(52) = 1,300,000; P = 10000(6)(52) = 3,120,000; Co = 325; Ch = .55
a. The optimal production batch is obtained from using the formula
Total annual ordering and holding cost =
= 51,320 bottles.
$16,465.24
c. Number of days between the start time of successive production runs = T = Q */D = .0395 years = .
0395*365 = 14.4 calendar days.
Chapter 8 - 24
We assumed that demand occurs at a constant rate and production will not be interrupted by work
stoppages.
Chapter 8 - 25
a. The optimal production batch size is Q* = 485,917 The length of a production run = 485,917/
(2*60*60) + 50/60 = 68.3 hours
b. Total annual inventory cost = $38,895.54
c. Number of days between the start time of successive production runs = .0231*365 = 8.43 calendar
days.
Chapter 8 - 26
d. The optimal production batch size would increase to Q * = 532,295 The length of a production run
would equal 532,295/(2*60*60) +50/60 = 74.76 hours
Chapter 8 - 27
a. The optimal order quantity is Q* = 77 with a reorder point of 22. The number of inventory cycles
per year = 3120/77 = 40.519. Hence, Click would like the cycle service level to be 1 - 1/40.519 =
97.52%. The z value corresponding to this service level is approximately z = 1.96. Hence, the reorder
point = + z* = 70 + 1.96*15 = 99.4 = 99 (See the Cycle Service Level worksheet) and the safety
stock is z* = 1.96*15 = 29. However, because this reorder point exceeds the order quantity of 77,
orders must be placed one inventory cycle early when the inventory level reaches 99 - 77 = 22.
b. There are 52*6 = 312 working days in a year. Hence, the number of days between orders = .
0248*312 = 7.74 working days.
c. Total annual cost (including holding cost of safety stock) = $1,632,364.75
d. Projected annual profit = 3120*($649.99) - $1,632,364.75 = $395,604.05
Chapter 8 - 28
a. The optimal order quantity becomes Q* = 1000 with a reorder point of 77. The number of inventory
cycles per year = 3120/1000 = 3.12. Hence, Click would like the cycle service level to be 1 - 1/3.12 =
67.95%. The z value corresponding to this service level is approximately z = .465. Therefore the
reorder point = + z* = 70 + .465*15 = 76.975 = 77 and the safety stock is z* = .465*15 = 7.
b. There are 52*6 = 312 working days in a year. Hence, the number of days between orders = .
3205*312 = 100 working days.
c. Total annual cost (including holding cost of safety stock) = $1,519,849.03.
d. Projected annual profit = 3120*($649.99) - $1,519,849.03 = $508,119.79
Chapter 8 - 29
Masks-R-Us should order Q* = 1,047. The expected profit would equal $1,534.83.
Chapter 8 - 30
a. Skip Gunther should produce 1817 plates (note goodwill cost is -$40).
b. Expected profit = $96,364.24
c. We assumed the company pays a royalty on plates produced even if they are destroyed.
Chapter 8 - 31
Chapter 8 - 32
Chapter 8 - 33
8.28
continued
Chapter 8 - 34
Chapter 8 - 35
8.29b.
Chapter 8 - 36
For French Roast Q* = 750 (Since they will not roast more than a 10-day supply of the coffee)
Note, finding this solution requires the Solver constraint, H5 <= 750.
Chapter 8 - 37
8.30 continued
For Amaretto Cream Q* = 200 (since the store will not roast more than a 10-day supply of the coffee)
Note, finding this solution requires the Solver constraint, H5 <= 750.
Chapter 8 - 38
Chapter 8 - 39
8.31 continued
Plan II
a. Pete's should adopt Plan I and give one pound of coffee free to backordered customers as the annual
inventory costs are slightly lower under this plan.
b. Under Plan I -- Q* = 44 and the reorder point is 17.
c. The expected annual profit = 180*($189) - $18,338.71 = $15,681.29
Chapter 8 - 40
a. The optimal order quantity is Q* = 111 and the reorder point is R = 39. .
b. The number of weeks between orders = .0285*52 = 1.48.
c. The percentage of customers who will be placed on backorder = 0%.
d. Annual profit on cash registers = 3900*($80) - $7,065.51 = $304,934.49
Note, profit can also be expressed as net sales less total costs as depicted in cell E16.
Chapter 8 - 41
Clothesline should order 9591 scarves. We assume Clothesline will only get one order delivered
during the season.
Chapter 8 - 42
a. If g = $.10, Q* = 201.
Chapter 8 - 43
8.34 b.
b. If g = $.50, Q* = 214.
Chapter 8 - 44
8.34 c.
c. If g = $1.00, Q* = 222.
Chapter 8 - 45
8.34 d.
d. If g = $5.00, Q* = 234
Chapter 8 - 46
g. In this case, with a safety stock of 28, the optimal order quantity is Q * = 250 - 28 = 222, the
reorder point equals 60 + 28 = 88, and the total annual cost = $12,479.94.
Chapter 8 - 48
Chapter 8 - 49
8.36 b.
b. The optimal order quantity is Q* = 46 with a reorder point R = 17. Profit = $22,484.28.
c. Yes, allowing for backorders increases profit by approximately $150 per year.
Chapter 8 - 50
a. The optimal order quantity is Q * = 11,051 and the reorder point is R = 9,632. Cycle Time = .
0789*365 = 29 calendar days. Total annual cost (including holding cost of safety stock) =
$1,773,527.99.
Chapter 8 - 51
8.37 b.
The optimal batch size is Q* = 44,143. The length of a production run = 44,143/2,000 = 22 working
days or 26 calendar days. Cycle Time = .3153*365 = 115 calendar days. Total annual cost (including
machine lease cost) = $1,719,144.58 + $5,000 = $1,724,144.58.
b.
c. Company should begin in-house production. It will save about $50,000 per year.
Chapter 8 - 52
Chapter 8 - 53
Chapter 8 - 54
Chapter 8 - 55
a. United Parcel Delivery should order Q* = 13 engines when the stock on hand reaches R = 5 engines.
b. Total annual cost = $143,615.38
Chapter 8 - 56
Because the frankfurters cannot be kept for more than three weeks, the production quantity must be
reduced from 370,032 down to 98,742. With this reduction in the production quantity, the profit is
lower using machine II than with machine I.
Note: To determine the maximum number of frankfurters that can be sold over the three weeks we
solve the following equation for x: 69,230.77 = (1 - 1,200,000/4,015,000)x, giving a value of x =
98,742.
Three week demand is (3/52)*(1,200,000) = 69,230.77.
During production,
(1,200,000/4,015,000)% of frankfurters satisfy the demand, the remainder (1-1,200,000/4,015,000) go
to inventory. The maximum inventory from a production level, x, cannot exceed the three week
demand.
Chapter 8 - 57
a. If Mercury purchases the laces the optimal order quantity is Q * = 164,702 and the reorder point R =
20,029. The number of days between orders = .3514*365 = 128 calendar days. The total annual cost
(including safety stock holding cost) = $17,064.18.
Chapter 8 - 58
8.43 b.
b. If Mercury produces the laces in-house the optimal production quantity is Q * = 445,730.
Production run time = 445,731/(2,000,000/(260*10)) + 4 = 579.45 + 4 = 583.45 hours and the number
of days between the start of successive production runs = .9707*365 = 354.3 calendar days. Total
annual cost (including machine lease cost) = $16,342.17 + $1,800 = $18,142.17.
c. Mercury should continue to purchase laces from Tiright as the cost would be over a $1,000 less per
year.
Chapter 8 - 59
8.44
Chapter 8 - 60
Chapter 8 - 61
a.
Ibex should order Q* = 2,471 chairs when the inventory level reaches R = 1,187 units. The
number of days between orders = .0752*365 = 27 calendar days.
b. Total annual costs (including holding cost of safety stock) = $324,142.53 + 500*($1.56) =
$324,922.53
Chapter 8 - 62
c. The order quantity would decrease to Q* = 2,230. An order would be placed when the inventory
level reaches R = 1,329 units.
Chapter 8 - 63
The cost of the new supplier is $330,942.92. Hence, it is not worth switching manufacturers.
Chapter 8 - 64
a.
Chapter 8 - 65
a.
The optimal order quantity is Q* = 170,941 pounds at a cost of $70,000 based on a price of
$0.4095 per pound.
b.
R = L*D + SS - Q* = 180,385 - 170,941 = 9,444 and it will occur in the previous inventory cycle.
c.
Chapter 8 - 66
a.
Chapter 8 - 67
8.50 c.
c. Since the sample mean = 84, we would estimate the mean lead time demand as 3*84 = 252. Since
the sample variance = 69.5556, we would estimate the variance of the lead time demand as
3*69.5556 = 208.6668. Hence, the standard deviation of the lead time demand = 208.6668 =
14.45.
Chapter 8 - 68
8.50 c. continued
Chapter 8 - 69