Generation and Control of Supplier Document Requirement Lists and Supplier Document Lists
Generation and Control of Supplier Document Requirement Lists and Supplier Document Lists
Generation and Control of Supplier Document Requirement Lists and Supplier Document Lists
Approved By:
#.#
Date
Author
0.0
0.1
1.0
David Shaw
David Shaw
David Shaw
GE PROPRIETARY
PAGE 1 OF 16
1. Purpose:
To define the standard process for the generation and control of equipment related Supplier Document
Requirement Lists (SDRLs), issued by the Profit and Loss Centre (P&L) to suppliers, and Supplier Document Lists
(SDLs), returned by the supplier to the P&L, for GE Oil and Gas Subsea project equipment.
NB. For each SDRL there will be a corresponding SDL. The SDRL is a GE request for document types required for a
particular item of purchased equipment contained in a purchase order (PO). The SDL is the suppliers response to
the SDRL and comprises a detailed list of documents to be supplied to fulfill the SDRL and purchase order item
requirements. The SDL, therefore, is considered to be the principal document for use within the project environment
when it has been approved, which may also include customer approval.
2. Scope:
2.1
One or more of the following reasons could initiate the need for a SDRL/SDL for a particular item of
equipment:through the process of Criticality Risk Assessment (CRA), an ITP is deemed to be required and, in turn,
the ITP requires items of documentation i.e. manufacturing data;
the Master Document Register requires the supply of certain items of documentation from the supplier
i.e. document deliverables for The Company (Client / Customer) e.g. Operating and Maintenance
Instructions;
Statutory and Regulatory requirements dictate the need for the supplier to provide certain documents
e.g. lifting equipment certificates.
The process is initiated during Product Engineering activity to establish the baseline, standard GE
requirements, and is completed during the Project phase of a contract to provide The Company
(customer/client), with equipment, documentation and services in accordance with contractual and other
requirements.
GE PROPRIETARY
PAGE 2 OF 16
3.0
BoM
Bill of Material
CRA
EPC
ePIC
ePIMS
eReq
ITO
ITP
Inquiry to Order
Inspection and Test Plan
MDR
MoW
MPP
Made on Works
Manufacturing Process Plan
MRB
NOI
Notification of Inspection
OTR
Order to Remittance
P&L
Prod
Eng
Product Engineer
Proj
Eng
Project Engineer
PPM
Pre-production meeting
PQE
RFQ
SDL
SDRL
SQR
ToC
Table of contents
GE PROPRIETARY
PAGE 3 OF 16
4.0
Procedure
4.1
General Requirements
4.1.1
When an ITP has been deemed necessary via CRA, the SDRL / SDL must contain those documents
required by the ITP e.g. material certificates, test reports, etc., and other, additional documents, as
listed in the Master Document Register (MDR). e.g. Operation and Maintenance Instructions, drawings, data
sheets etc. Hence, the SDRL / SDL should be considered as the primary document for specifying which
Supplier or P&L documents are required, including specific documents required for the MRB and other GE
and customer deliverables.
4.1.2
Equipment referred to is considered to be an assembly, sub-assembly, part or material falling into one or
more of the following categories:for controlling the production fluid;
load bearing;
pressure retaining/containing;
process wetted;
part of the control system;
other equipment should be considered where the risk level is deemed to be potentially high. E.g.
thermal insulation.
4..1.3
This process shall be used during the initial phase of all Subsea Production Equipment Projects. For Frame
Agreement projects (none EPC projects), this process shall be adopted for the first order call off, and shall
be re-used on subsequent call off without alteration provided there is no change of scope or technical
requirement affecting the documents needed.
4.1.4
When a decision to make, rather than buy an item of equipment has been taken, this removes the need
for a SDRL because the documentation will be generated internally in accordance with the ITP and agreed
MRB ToC.
4.1.5
The standard product, Supplier Document Requirement List (SDRL), is selected by the Product Engineer and
attached to the part in EPIMS.
The project SDRL is the standard product SDRL, amended in accordance with contractual requirements, if
necessary. Otherwise, the standard product SDRL is used.
At OTR, when a standard product SDRL has to be updated to align with Contract requirements, the original
SDRL may be copied and amended but the original file is NOT to be updated, as this will change the
standard level. Hence, a new document number must be created for the copied and amended SDRL.
The SDL is provided by the supplier and is based on the standard or project SDRL. The document types
required in the SDL are specified in the SDRL. Further document types may be added by the supplier, as
necessary. E.g. documents required to cover statutory and regulatory requirements.
GE PROPRIETARY
PAGE 4 OF 16
4.1.6
The product standard SDRLs shall be initiated, controlled, applied and updated in accordance with the
flowchart (Appendix A), by the Product Engineering Group, by utilizing the standard template for the
equipment type, and ensuring the stated manufacturing data documents agree with those required by the
ITP.
NB. No more than one SDRL may be attached to a part. The same SDRL may be attached to two or
more parts.
4.1.7
The timeliness of submission of SDRLs and SDLs shall be compatible with the project Tollgate deliverables
and the overall planning schedule.
Likewise, the specifying for the timing of document completions required by the SDRL, must also be
compatible with the overall planning schedule.
4.1.8
The user must regard the contents of this document as a minimum standard and contractual or purchase
order requirements must be taken into consideration.
4.2
4.2.1
Part and document control requirements for ePIMS based activity must be in accordance with the relevant
TOPPS procedures and business rules.
Where changes to the standard SDRL for the part type or class are deemed necessary, due to error,
omission or review and improvement activity, the change shall be undertaken in accordance with TOPPS
procedures and business rules.
4.2.2
4.2.3
GE PROPRIETARY
PAGE 5 OF 16
GE PROPRIETARY
PAGE 6 OF 16
4.2.4
NB.
Both the above SDRLs would then be considered as standard, populated templates for the
part class or commodity. It should also be noted that the additional PMI technical requirement would
require there to be a different part number from the standard in any case.
4.3
4.3.1
Lead Project Engineer / PQE - When preparing a RFQ, prior to the placement of a supplier Purchase Order,
select the required part for the project from ePIMS. If there is no SDRL attached to the part, select the
appropriate standard document for the part type or class and attach it to the part.
NB. In order for the Supplier or prospective Supplier to be able to view the SDRL or SDRLs (where
multiple parts of a different type or different part numbers are concerned) via the SIMON portal, ensure
that each part in the RFQ or PO scope, if necessary, has a SDRL attached to it.
If the SDRL is attached to the part, carry out a review of the SDRL with the PQE to ensure it is adequate for
the project requirements. i.e. The SDRL contains, as a minimum, those documents required by the ePIMS
BoM, MDR and ITP.
If no change to the standard SDRL is required, the subject part and associated SDRL may be used. If the
SDRL requires change, raise a new part in ePIMS (see 4.2.4 above).
On completion of the new SDRL, attach it to the new part in ePIMS.
If required PQE to issue SDRL to EPC DCC for issue to Company for comment.
On completion of satisfactory review, including satisfactory response to Company comments, release the
part in ePIMS, including the SDRL.
Initiate the Purchase Order Requisition (POR) and issue. Ensure that the SDRL is in the original file format to
allow editing by the supplier.
The RFQ is then processed according to Sourcing Procedures.
GE PROPRIETARY
PAGE 7 OF 16
4.4
Supplier
The SDL, to be produced by the supplier, is part of the same file containing the SDRL. See screenshot:-
To produce the SDL, review the SDRL minimum requirement document and supplement the SDL Supplier (see tab
on screenshot above) with additional documents, as required by the PO scope of work, ensuring that the minimum
requirement of the SDRL is met in the SDL. i.e. The SDRL, at this point, is converted to a SDL by utilizing the GE
format.
The README tab opens a sheet containing instructions and an explanation of how to use the SDL worksheet.
When completed, the supplier is to Issue the file containing the SDL to GE for review.
GE PROPRIETARY
PAGE 8 OF 16
4.4.1
4.4.2
PQE
Check the SDL against the SDRL to ensure that the minimum requirements for documents requested has
been met.
NB. The attachment of project SDRLs to standard, base or generic parts is not allowed as this
can result in the attachment of two or more of them to the same part, causing confusion to users.
5.0
Quality Records
The following quality records resulting from this process shall be controlled and maintained in accordance
with the requirements of GEEQMS 4.2.4 Record Control:Supplier document requirement list and supplier document lists.
6.0
Responsibilities
6.1
Process Ownership
For the three P&Ls, the owner of this process is the Executive Sourcing Leader (ESL).
The ESL or designated person, shall ensure the following:That collectively the SDRLs provide a comprehensive package for use in ITO and OTR and that they
are used in accordance with this procedure.
That the procedure and SDRL templates are periodically reviewed for suitability.
That changes in the process are adequately communicated internally and to suppliers.
That suppliers correctly use the SDRL to produce a SDL and that the SDL complies with the SDL
requirements and is produced in a timely manner by the supplier.
Provide the supplier interface to answer any related supplier queries.
6.2
Engineering
The engineering function shall carry out the following:Create and update standard SDRL documents as required.
In OTR, review standard SDRL requirements against project requirements and attach and release
updated SDRLs to parts.
Refer project SDRLs to the PQE for review and agreement before their release.
Review supplier engineering related comments and take action to resolve related queries.
Obsolete SDRLs, in ePIMS, that are no longer required.
GE PROPRIETARY
PAGE 9 OF 16
6.3
6.4
MRB Teams
Contribute to SDRL review to ensure that supplier document deliverables meet the requirements of
the MRB contents as specified in the standard and project inspection and test plan (ITP).
Review supplier documentation for completeness and correctness.
6.5
For EPC Projects, it is the responsibility of the the EPC Project Quality Manager to ensure that each P&L
Project Team is compliant with this process procedure.
For none EPC projects, it is the responsibility of the P&L Project Manager to ensure that this process
procedure is fully implemented at each of the P&Ls.
7.0
7.1
P-PM-09-001;
WI-PM-18-001;
WI-PM-07-002;
P-PM-18-003;
P-PM-18-002a;
NB. The prime location and point of control for this document, the documents referenced above and associated
unpopulated templates is contained and controlled within Documentum:QMS > Oil and Gas > O&G Drilling & Production Systems > D&P Subsea Projects > Global Project Procedures
7.2
Technical Operating Policies & Procedures (eTOPPS) for Engineers for the creation, review and release of
parts and their associated documents and data; located in the eBiz suite of applications.
GE PROPRIETARY
PAGE 10 OF 16
7.3
Sourcing procedures for the control and issue of Requests for Quotation and Purchase Orders; located in the GE
Energy Quality Management System
QMS > Oil and Gas > O&G Drilling & Production Systems > D&P Regions & Sites >
7.4
7.5
GE PROPRIETARY
PAGE 11 OF 16
7.6
7.7
7.8
GE PROPRIETARY
PAGE 12 OF 16
7.9
7.10
GE PROPRIETARY
PAGE 13 OF 16
Product Engineer
(Create)
Establish standard
SDRL for part
Product Engineer
(Review)
SDRL review for
product suitability
Product Engineering
Release part
Attach SDRL to
part
Product Eng
(Review)
SDRL Suitable for
Product type?
Yes
Lead
Project Engineer & PQE
Is there a suitable SDRL
attached to
the part?
Yes
No
PQE
Is Company
approval of SDRL
required?
Yes
Yes
EPC DCC
Receives and transmits
document
No
PQE
SDRL
Approved?
EPC DCC
Receives and transmits
documents
Company
Review and comment
PROJECT PHASE
GE PROPRIETARY
PAGE 14 OF 16
Lead Project
Engineer
Initiate POR
Issue PO to supplier
REQUEST FOR QUOTATION PHASE
PURCHASE ORDER PHASE
Supplier
Receives PO
Supplier
Issues PO acknowledgement
(agreement to SDRL)
CoE DCC
Creates ePIC profile &
workflow for SDL issue
& review
Supplier
Reviews GE SDRL & updates
file to provide SDL
PQE
SDL OK?
No
Yes
GE PROPRIETARY
PQE
Issue to DCC for
recording in
ePIC
PAGE 15 OF 16
Title:
Reference:
Revision:
Application Date:
Expiration Date:
Author:
External References:
GE PROPRIETARY
PAGE 16 OF 16