Concrete Specification
Concrete Specification
Concrete Specification
General Specifications
Volume 2 Part I
CEMENT
SULPHATE RESISTING CEMENT
4/1.1
The acid soluble alkali level measured as (Na 2 O+0.658 K 2 O) shall not
exceed 0.6% by weight determined in accordance with BS EN 196-2 :
2005
The heat of hydration shall not exceed 290 KJ/Kg at 7 days when tested in
accordance with BS 4550: Part 3 Section 3.8.
The specific surface shall be not greater than 375 m/Kg and not less than
280 m/Kg when tested as described in BS EN 196: Part 6: 1992.
The chloride content shall not exceed 0.1% when tested in accordance
with Clause 4 of BS EN 196-2 : 2005
The tricalcium aluminate content shall be 3.5% max when tested according
to the method BS EN 196-2 : 2005
ORDINARY PORTLAND CEMENT
4/1.2
March 2015
Tender Documents
Page 4/3
Volume 2 Part I
The chloride content shall not exceed 0.1% when tested in accordance
with Clause 4 of BS EN 196-2: 2013.
For any type of cement, the following physical & mechanical test shall also
to be included:
o
o
o
o
Moderate sulphate resisting Portland Cement shall comply with ASTM C150
Type II. It shall also comply with Clause 4/1.2. In addition the cement shall
comply with the following:-
The acid soluble alkali level measured as (Na 2 0+0.658 K 2 0) shall not
exceed 0.6% by weight determined in accordance with BS EN196 2
2005
The specific surface (fineness) shall not be greater than 375 sq.m/Kg and
not less than 280 sq.m/Kg when tested as described in BS EN 196: Part 6:
1992.
The chloride content shall not exceed 0.1% when tested in accordance
with Clause 4 of BS EN 196-2 : 2005
Contain not less than 4% and not more than 8% proportion of tricalcium
aluminate by weight when tested according to the method BS EN 196-2 :
2005
Contain less than 2.7% proportion of Sulphur trioxide by weight
For any type of cement, the following physical & mechanical test shall also be
included:
Consistency in accordance with BS EN 196-3: 2008
Setting time in accordance with BS EN 196-3: 2008
Soundness in accordance with BS EN 196-3: 2008
March 2015
Tender Documents
Page 4/4
Volume 2 Part I
Early Strength
2 days
7 days
32.5 N
16.0
32.5 R
10.0
42.5 N
10.0
42.5 R
20.0
52.5 N
20.0
52.5 R
30.0
Standard Strength
28 days
32.5
42.5
52.5
52.5
62.5
Initial
Setting
Time
min.
Soundness
(expansion)
mm
75
60
10
45
GENERAL
4/1.4
Each cement batch shall bear manufacturer's name and batch number. Type
of cement shall be the same as mentioned in the approved analysis report.
Each separate consignment of cement shall be tested by the manufacturer
before delivery and certified copies of such tests shall be supplied to the
Engineer before any part of the consignment is used in the works. The
Engineer reserves the right to order a re-test of cement at any time. Approval
of cement does not relieve the Contractor of the responsibility to produce
concrete of the specified strength.
4/1.5
Cement shall be delivered to site in bulk, or with the Engineer's approval, may
be supplied in sealed bags which shall bear the manufacturer's name and the
date of manufacture. Each consignment shall be accompanied by a copy of
the manufacturer's batch test certificate and certificate of guarantee.
4/1.6
4/1.7
Any consignment not used within 2 months from the date of manufacture will
not be allowed to be used in the works.
4/1.8
4/1.9
Each cement batch shall bear manufacturers name and batch number
March 2015
Tender Documents
Page 4/5
Volume 2 Part I
The Engineer reserves the right to order a re-test of cement at any time
4/2
4/2.1
Except as may be modified hereunder the aggregate (fine and coarse) for all
types of concrete shall comply in all respects with BS 882 "Concrete
aggregates from natural sources" and the fine aggregate shall also comply
with Dubai Municipality Administrative Order No. 143/91.
4/2.2
4/2.3
Before any material from a particular source is used, the Contractor shall
obtain representative samples of fine and coarse aggregates and carry out the
necessary tests and analyses to show that the samples comply with the
Specification. During the progress of the works, the grading and chemical
characteristics may be checked at frequent intervals.
4/2.4
The results of these tests, etc. shall be submitted to the Engineer and his
approval shall be obtained before any of the material is used in the works.
Part of each sample will be required for concrete trial mixes and part shall be
retained for comparison with subsequent deliveries.
4/2.5
Sampling for testing and analysis shall be carried out, where applicable, in
accordance with BS 812 Part 102:1989.
4/2.6
The maximum size of the aggregate shall not be larger than 1/5 of the
narrowest dimension between sides of the member for which the concrete is to
be used and not larger than 3/4 of the maximum clear distance between
reinforcing bars.
4/2.7
Fine aggregate shall be natural or crushed sand and beach sand shall not be
permitted for use in concrete mixes.
4/2.8
4/2.9
4/2.10
4/2.11
March 2015
Tender Documents
Page 4/6
Volume 2 Part I
SR.
NO.
KIND OF REQUIREMENT
1.
Grading
2.
Material finer
Than 0.075 mm
TEST METHODS
---------------------BS 812 / ASTM
BS EN 933-1: Standard
2012 (Dry)
Standard
BS EN 9331:2012 or
ASTM
C117:2004
(Wet)
Natural, uncrushed/
crushed
Crushed rock
3.
PERMISSIBLE LIMITS
----------------------------------FINES
COARSE
max.3%
max.7%
max.1%
max.1%
C142/C142M:
2010
max.1%
max.1%
C123
max.0.5%
max.0.5%
The color of
the
Supernatant
liquid is
lighter than
standard
color solution
max.2.3%
max.2.0%
min.2.60
min.2.60
4.
5.
6.
Water absorption
C128 : 2012a
C128 : 2012
7.
Specific Gravity
C128 : 2012a
C128 : 2012
(apparent)
8.
9.
Shell content in
aggregates
Coarser than 10 mm
Between 5mm-10mm
BS EN
7:1998
Particle shape
Flakiness index
BS 812:90
Part
105
:
Section 105.1
Part
105
:
Section 105.2
Elongation index
933max.5%
Max.15%
max.25
max.25
March 2015
Tender Documents
Page 4/7
Volume 2 Part I
SR.
NO.
KIND OF REQUIREMENT
TEST METHODS
---------------------BS 812 / ASTM
PERMISSIBLE LIMITS
----------------------------------FINES
COARSE
25
for
combined
aggregates but should
not exceed more than
30 for individual sizes.
9a.
10.
Acid soluble
Part 117,
Chlorides, CL
Appendix C
For reinforced
concrete made with
SRPC cements
OPC
&
MSRPC
cements
max.0.03%
max.0.03%
max.0.01%
max.0.02%
max.0.03%
max.0.03%
max.0.02%
max.0.04%
max.0.03%
max.0.01%
BS EN 17441:1998
max.0.3%
max.0.3%
Soundness, MgS04
(5 cycles)
C88 : 2013
max.12%
max.12%
Mechanical strength
10% fines value
or Impact value
Part 111
Part 112
min100KN
max.30%
C131 : 2014
C535 : 2014
max.30%
Part 120
max.0.05%
12.
13.
Acid soluble
sulphates, S03
Los Angeles
Abrasion
March 2015
100%.
14.
Drying Shrinkage
15.
Potential reactivity,
Tender Documents
Page 4/8
Volume 2 Part I
SR.
NO.
KIND OF REQUIREMENT
TEST METHODS
---------------------BS 812 / ASTM
PERMISSIBLE LIMITS
----------------------------------FINES
COARSE
Note 2
Of Aggregates,
Chemical Method
Of Cement-Aggregate
Combination
C289
Innocuous
C227
6 month
expansion
0.10% max.
Innocuous
Note 1 :
Note 2 :
March 2015
SR.
NO.
1.
Grading - BS EN 933-1:1997
Per 1,000m3
2.
- do -
3.
Per 4,000m3
4.
Per 2,000m3
5.
Water absorption
2007/C127 : 2007
- do -
6.
- do -
7.
- do -
8.
- do -
ASTM
Tender Documents
C128
Page 4/9
Volume 2 Part I
9.
Per 1,000m3
Each 12 concrete
days if result is
more than 75% of
the limit and each
month if result is
less than 75% of
the limit.
10.
11.
Each 48 concrete
Days or 2,000 m3
12.
Mechanical Strength
10% Fines or impact value
- BS 812 Parts 111, 112
Each 72 concrete
Days or 4,000 m3
- do -
13.
Twice daily
14.
Drying Shrinkage
BS 812 Part 120
15.
Potential Reactivity:
of aggregates
(ASTM C 295, C 289)
March 2015
Tender Documents
Page 4/10
Volume 2 Part I
of Cement aggregate
combination
(ASTM P214 and C 227)
16
Note :
Per 2,000 m3
4/3
FINE AGGREGATES
4/3.1
4/3.2
Each batch of aggregate delivered to site shall be kept separate from previous
batches and shall be stored for at least 3 (three) working days before use to
allow inspection and tests to be carried out.
4/3.3
4/3.4
The Contractor shall mechanically wash aggregate to remove salts and other
impurities in order to meet the requirement specified.
4/4
4/4.1
4/4.2
Aggregates that are deleteriously reactive with the alkalis in the cement in an
amount sufficient to cause excessive expansion of concrete shall not be used.
4/4.3
The Contractor shall mechanically wash aggregate to remove salts and other
impurities in order to meet the requirement specified.
March 2015
Tender Documents
Page 4/11
Volume 2 Part I
4/5
COMBINED AGGREGATE
4/5.1
4/5.2
4/6
4/6.1
The Contractor shall make his own arrangement and obtain approval for the
supply of water.
4/6.2
The mixing water should be clear, apparently clean and free from matter
harmful to concrete in its fresh or hardened state. Potable water can be used.
Water of questionable quality should comply with the physical tests of Table
4.3 and chemical limitation listed in Table 4.4. Water shall also meet the
requirement of BS EN 1008:2002.
4/6.3
The temperature of water for concrete should not be less than 5 degree
Celsius nor more 25 degree Celsius. Water may be cooled to not less than 5
degree Celsius by the gradual addition of chilled water or ice but on mixing, no
ice particles should be present in the mix. Alternatively, flaked ice may be
used. The ice to be used should be crushed and should be the product of
frozen water which complies with acceptance criteria of Tables 4.3 and 4.4.
4/6.4
Water for curing concrete shall not contain impurities in sufficient amounts to
cause discoloration of the concrete. Sources of Water shall be maintained at
such depth and the water shall be withdrawn in such a manner as to exclude
silt, mud, grass and other foreign matter.
TABLE 4.3
ACCEPTANCE CRITERIA AND PHYSICAL
TESTS FOR MIXING WATER
March 2015
Limits
ASTM Test
Compressive strength,min.%
control at 7 days
90
C 109 : 2002
C 191 :2004
Tender Documents
Page 4/12
Volume 2 Part I
Limit, ppm
Test Method
1.
Chloride as C1
250
ASTM D 512:
(2004)
2.
Sulphates as SO4
350
ASTM D 516:2002
3.
Alkali carbonates
and bicarbonates
500
ASTM D 513:2006
4.
Total dissolved
solids, including
1, 2 & 3 above
2000
BS 1377 : Part 3 :
1990:
Test 8
PH
min.7/max. 9
ASTM
1999
5.
D1293
4/7
4/7.1
All concrete, aggregate, cement, steel and water shall be tested during the
construction as per frequency in Tables 4.2 and 4.6 or as directed by the
Engineer. All test samples shall be supplied by the Contractor at his expense.
Samples shall be obtained in accordance with BS 812, BS EN 1008, BS 1881
and BS EN 196. Testing shall be at the frequencies stated above or relevant
standards. All sampling shall be carried out by the Engineer.
Table 4.6 Frequency of Routine Testing:
Sampling
Method
Test
Method
BS EN
196-7
BS EN-196
1. Deformed S. Bar as
BS
4449:2005
per BS 4449:2005
ASTM E415
2. Strand
as
per
BS
5896:1980
if
needed
BS 5896
BS 5896 APPENDIX
A
BSEN
12350-1
BSEN
123507:2009
ITEM
a.
Cement - as per BS EN
196
b.
Steel
c.
Concrete
1. Air content, as per BS
EN 12350-7:2009
March 2015
Tender Documents
Page 4/13
Volume 2 Part I
Sampling
Method
Test
Method
2. Flexural strength of
Prism as per BS EN
12390-5
BSEN
12350-1
BSEN
12390-5
3. Bleeding
as
per
ASTM C232/C232M14
BS EN
123501:2000
ASTM C
232/C32M14
4. Splitting Tensile of
Conc. Cylinder as per
ASTM C-496:1996 &
others
BS EN
123501:2000
C-496
5. Depth
of
Water
Penetration (BS EN
12390 P-8:2000)
BSEN
123501:2000
BS EN
12390-8
Each
2000m3
of
a
particular
grade
of
structural concrete or as
directed by the Engineer.
BS EN
123501:2000
BS 1881 208:1996
Each
2000m3
of
a
particular
grade
of
structural concrete or as
directed by the Engineer.
7. Water absorption of
Hardened Conc. As
per BS 1881 P122
BS EN
123501:2000
BS 1881122:1983
Each
2000m3
of
a
particular
grade
of
structural concrete or as
directed by the Engineer.
8. Rapid
permeability
chloride
BS EN
12350-1
:2000
ASTM C
1202
Each
2000m3
of
a
particular
grade
of
structural concrete or as
directed by the Engineer.
BS EN
12350-1
BS EN
123502:2009
ITEM
d.
BS EN
1339:2003
BS EN
1339:2003
Water
BS EN
1008:2002
BS EN
1008-:2002
March 2015
Tender Documents
Page 4/14
4/7.2
Volume 2 Part I
WORKABILITY
Workability shall be assessed by the following tests the requirements for which
shall be as specified elsewhere in the documents.
Slump test shall be performed according to BS EN 12350-2:2009
Compaction factor shall be performed according to BS EN 12350-4:2000
Vebe time shall be performed according to BS EN 12350-3:2000
Flow test shall be performed according to BS EN 12350-5:2000
4/7.3
COMPRESSION TEST
The Compression tests shall be performed on cubes 150 x 150 x 150 mm as
described in BS EN 12390-3:2002. Sampling, making test cubes and curing of
cubes shall be in accordance with BS EN (12350-1:2000 and 12390-1:2000)
respectively.
4/8
REINFORCEMENT BARS
4/8.1
4/8.2
4/8.3
Certification. Three (3) copies of a mill test report shall be furnished to the
Engineer for each lot of steel reinforcement bars proposed for use on the
project.
4/8.4
Identification. The bars in each lot shall be legibly tagged by the manufacturer
and/or fabricator before being offered for inspection. The tag shall show the
manufacturer's test number and lot number and other applicable data that will
identify the material with the certificate issued for that lot of steel.
4/8.5
The fabricator shall furnish three (3) copies of a certification which shows the
heat number or numbers from which each size of bar in the shipment was
fabricated.
4/8.6
The Engineer reserves the right to sample and inspect all reinforcement steel
upon its arrival at the work site. The Contractor shall provide a certificate
confirming that samples taken from the bars delivered to the works pass all the
required tests. The frequency of sampling and the method of quality control
shall be in accordance with BS 4449 2005.
4/8.7
All reinforcement bars shall be free from detrimental dirt, mill scale, loose rust,
paint, grease, oil or other foreign substance, fins, or tears. There shall be no
March 2015
Tender Documents
Page 4/15
Volume 2 Part I
evidence of visual flaws in the bars, test specimens or on the sheared ends of
the bars.
4/8.8
4/8.9
4/9
4/9.1
Before ordering reinforcing steel, the Contractor shall check the bar schedules
and adjust them if necessary to the approval of the Engineer. Bar schedules
shall show the weight of each bar, the total weight of each bar size and the
total weight of bars, and bending diagrams for bars in accordance with BS
4466.
4/9.2
The Contractor shall provide and submit to the Engineer for approval any
working drawings additional to the Contract Drawings which may be found
necessary for the production of revised bar schedules or for the completion of
the works.
4/9.3
4/10
4/10.1
4/10.2
Hot rolled high yield bars shall not be straightened or bent again, having once
been bent. If the Engineer gives approval to bend mild steel reinforcement
projecting from the concrete, the internal radius of bend shall not be less than
four times the nominal size of the bar.
4/11
4/11.1
March 2015
Tender Documents
Page 4/16
Volume 2 Part I
4/11.2
4/11.3
4/11.4
4/12
4/12.1
Welded wire fabric to be used for the reinforcement of concrete shall conform
to the following requirements:
-
Dimensions. Welded steel wire fabric shall conform to the size and
dimensions shown on the Drawings.
4/13
SPACER BLOCKS
4/13.1
4/13.2
Spacer blocks made from cement, sand and small aggregate shall match the
mix proportions of the surrounding concrete so far as is practicable with a view
to being comparable in strength, durability and appearance.
4/14
ADMIXTURES
4/14.1
4/14.2
Where the use of admixture had been agreed by the Engineer, they shall
conform to the requirements of Type A, Type D, Type F or Type G as specified
in ASTM C494 and shall be used in strict accordance with the manufacturer's
instructions.
Preliminary tests of cube strength and other tests shall be carried out using the
combination of aggregates cements and admixtures proposed for use.
4/14.3
March 2015
The Contractor shall be entirely responsible for the use of any approved
admixtures.
Tender Documents
Page 4/17
Volume 2 Part I
4/14.4
4/15
4/15.1
Concrete shall be as shown in the Table of 4.5. The number of mixes may
require to be increased.
The criteria given in the Table are designed to produce concrete of the
required strength and durability.
If the maximum aggregate size is 10 mm then the cement content stipulated
for the class of concrete given in table 4.5 shall be increased by 40 Kg per m3.
All concrete mixes shall be verified by DM - DCL
TABLE 4.5
TABLE OF MIXES WITHOUT ANY ADMIXTURE OR ADDITIVE
Concrete
Class
45/20
40/20
37/20
35/20
30/20
25/20
15/20
Max.
Size
Agg
Min.
Qty of
Cement
mm.
kg.per m3
20
20
20
20
20
20
20
400
370
350
330
310
275
250
Max.
Free
Water/
Cement
Ratio
0.425
0.475
0.50
0.525
0.55
0.60
0.65
Characteristic Cube
Strength
CCS
7-day
N/mm2
28-day
N/mm2
33
30
26
25
20
16
10
45
40
37
35
30
25
15
The CCSs are for concrete which has been cured at a temperature of 23
degrees C + 2 degree C, and are the values below which no more than 5% of
the test results fall. The 7-day strengths shall be used only as a guide.
4/15.2
March 2015
Tender Documents
Page 4/18
Volume 2 Part I
Concrete for water-retaining shall be watertight and shall comply with the
recommendations of BS 8007.
Concrete for paving or precast units shall be tested to BS EN 12390: Part 5:
2000 and shall have minimum flexural beam strength of 3.5N/mm2 at 28 days.
If the concrete has a specified CCS of 40N/mm2 or greater, then the minimum
flexural strength shall be 4N/mm2.
If concrete specimens are cured at higher temperatures or for longer periods
than BS EN 12390-1:2000 requires, the adjusted CCS shall be calculated as
follows:
100f'/f
f
f
T
D
A&B
=
=
=
=
=
adjusted CCS
specified CCS
curing temperature
age at testing in days
are coefficients given in the
following table.
10.0
20.0
30.0
67.5
60.0
52.5
4/15.4
Mixes for structural concrete shall be designed by the Contractor. The class of
concrete (shown on the drawings) is denoted by the 28 day characteristic cube
strength and the maximum size of aggregate.
March 2015
Tender Documents
Page 4/19
4/15.5
Volume 2 Part I
The chloride and sulphate levels in the concrete mix shall comply with the
following requirements:Maximum Limits of acid soluble Chloride and Sulphate content as a
percentage by Weight of Cement in the Mix.
TYPE OF CONCRETE
CHLORIDES
SULPHATES
AS Cl
AS SO3
ACCORDING TO BS-1881 : 1988
PART 124
Amd 01:1998
a.
b.
c.
Amd 06:2002
0.30
0.06
3.70
3.70
0.10
3.70
0.60
0.12
3.70
3.70
Note: BSEN 196-21: 1992 Clause 8, Method of Testing Cement Part 21 will be
used to determine the percentage chloride by weight of cement. The
OPC and MSRPC cements can also contain chlorides, the relevant
standard BS EN 197-1 allows up to 0.1% Cl. Therefore any chloride
content present in the cement has to be taken into account while
computing total Cl in the mix. In case the cement contains the
maximum limit of 0.1% Cl, then the aggregates, water and admixtures
used for prestressed concrete or heat cured reinforced concrete should
be absolutely free of chlorides.
4/16
4/16.1
March 2015
a)
b)
c)
Tender Documents
Page 4/20
Volume 2 Part I
d)
e)
Workability BS EN 12350-2:2000
f)
g)
h)
i)
j)
The Initial Surface Water Absorption Test as per BS 1881: P-208: 1996.
Maximum permissible limit for ISAT is 0.2 ml/m2/sec
k)
c)
d)
The average 28-day CCS of the three trial mixes shall not be less than the
designed mean strength, and the results of the above tests shall be
acceptable before the mix is approved.
Otherwise the mix shall be
re-designed.
March 2015
Tender Documents
Page 4/21
Volume 2 Part I
4/16.3
The Engineer will review the Contractor's trial-mixes and test the test cubes at
seven (7) and twenty-eight (28) days. The Engineer will then determine which
of the trial mixes shall be used. If none of the trial mixes for a class of
concrete meets the Specifications, the Engineer will direct the Contractor to
prepare additional trial-mixes. No class of concrete shall be prepared or
placed until its job-mix proportions have been approved by the Engineer.
4/16.4
4/16.5
The Engineer may also require practical tests to be made on the Site by filling
trial moulds to confirm the suitability of the mix for the works, the type of plant
used for mixing, the method of compaction used and the formwork face
intended for use in the works.
4/16.6
All costs connected with the preparations of trial-mixes and the design of the
job-mixes shall be borne by the Contractor.
4/16.7
In the event, any Concrete mix that is currently being used in another running
RTA projects, is proposed by the contractor for approval of using that mix in
this contract, then
1. Prior to according the approval or otherwise, the Engineer must ensure
that all copies of test results pertaining to another running RTA project
submitted by that contractor comply with all specifications as stated in this
contract and shall also ensure that the proposed mix complies with clause
4/16 by verifying that proposed mix at DCL.
2.
The Engineer has to make sure that all constituents of concrete are tested
and meeting the standard specified requirements. In case there are
changes in the materials or constituents, which may affect the properties of
the concrete. Then the mix design shall be re-verified. All the mix designs
verification shall be done at DCL.
NOTE: Any mix that is obsolete & currently not in use shall not be
accepted at all for re-approval.
4/17
QUALITY CONTROL
4/17.1
TEST CUBES
Cubes shall be manufactured in an on-site laboratory, specially equipped for
the purpose, in controlled conditions. They shall be made, cured, stored,
transported and tested to BS EN (12390-1 and 12390-3:2000). The method of
compacting cubes shall be as approved and shall be means of vibrating table
in the laboratory or 25mm vibrating poker on site.
4/17.2
March 2015
SAMPLING CUBES
Tender Documents
Page 4/22
Volume 2 Part I
ii)
No individual result of the sample is less than that (CCS which is the 28
days cube strength obtained in the approved trial mix minus 3 N/mm2),
iii)
If the above criteria is not satisfied, the unit represented by the sample is
questionable and the following actions may be instructed as appropriate:
i)
Cutting and testing cores from placed concrete.
ii)
Non-destructive testing of placed concrete.
iii) Load-testing relevant structural units.
iv) Cutting out and replacing defective concrete.
If the range of individual cube strengths made from the same sample
exceeds 15% of the mean, then the method of making, curing and
testing cubes shall be checked. In the event of a sample having a range
March 2015
Tender Documents
Page 4/23
Volume 2 Part I
exceeding 20%, then the result shall be unacceptable and the Engineer
may order any of the following actions:
a)
b)
c)
d)
In the event of cutting and testing of cores are required, the Contractor
shall cut cores from approved locations and test them to BS EN 125041:2009.
4/17.4
DURABILITY TESTS
Concrete shall be tested for durability properties by undertaking absorption
and permeability tests where appropriate, or directed by the Engineer, as
directed below:
Water absorption tests shall be carried out in the laboratory on 75mm diameter
cores cut at an age of 24 to 28 days to enable the tests to be carried out
between 28 and 32 days in accordance with BS 1881-122: 2011. The upper
acceptable limit for absorption after 30 minutes shall be 2%.
Effective permeability tests in accordance with the method described in BS EN
12390-8: 2009 shall be carried out. The maximum acceptable penetration at
seven days shall be 15 mm and the maximum acceptable penetration at 28
days shall be 10mm.
Initial surface absorption test as per BS 1881: P-208: 1996 shall be carried
out.
Maximum permissible limit for ISAT is 0.2 ml/m2/sec.
Rapid chloride penetration test as per ASTM C1202-12 shall be carried out.
4/17.5
OTHER TESTS
When instructed by the Engineer concrete shall be tested for drying shrinkage
and wetting expansion, for which 75x75mm prisms shall be prepared and
tested in accordance with BS ISO 1920-8:2009 or BS EN 772:98 and BS EN
771-2:2011. The maximum acceptable limits shall be:
Drying Shrinkage
Wetting Expansion
:
:
0.05%
0.03%
Cubes may be required and trials carried out to determine stripping times for
formwork, the duration of curing and to check testing and sampling errors.
The air content of air-entrained concrete shall be determined 12350-7:2009 for
each batch produced until consistency has been achieved, when batches may
be tested. The maximum value shall not exceed 2%.
Compaction factor, slump, veb or other workability tests shall be carried out as
required during concreting of permanent works to control workability at the
March 2015
Tender Documents
Page 4/24
Volume 2 Part I
batching plant at the site of the pour. The degree of workability shall be as for
the trial mixes; permitted tolerances shall be in accordance with BS 5328.
4/18
4/18.1
The following will be designated by the Engineer within the limits of the
Specifications.
4/19
a)
b)
c)
d)
e)
When, in the opinion of the Engineer, cement is being lost due to windy
conditions, the Contractor shall add additional amounts of cement as
directed by the Engineer. No additional payment shall be made for the
added cement.
f)
g)
Bleeding limitations
C232/C232M-14.
when
tested
in
accordance
with
ASTM
CONSISTENCY OF CONCRETE
4/19.1
4/20
4/20.1
CEMENT
In the case of bagged cement it shall be measured as packed by the
manufacturer: a sack of cement shall weigh fifty (50) kilograms. Measurement
for proportioning all cement shall be accurate to within two (2) percent
throughout the range of use. Only full bags, undamaged or unbroken will be
permitted.
4/20.2
WATER
The mixing water shall be measured by weight or by volume. In either case
the measurement shall be accurate to within one (1) percent throughout the
range of use.
March 2015
Tender Documents
Page 4/25
4/20.3
Volume 2 Part I
AGGREGATE
The aggregates shall be measured by weight to an accuracy within two (2)
percent through-out the range of use.
4/21
4/21.1
4/21.2
4/21.3
4/21.4
4/21.5
4/21.6
Segregated aggregates shall not be used until they have been thoroughly
remixed and the resultant pile is of uniform and acceptable gradation at any
point from which a representative sample is taken. The Contractor shall
re-mix aggregate piles when ordered by the Engineer.
TRANSPORTING Of AGGREGATES
4/21.7
March 2015
Tender Documents
Page 4/26
Volume 2 Part I
capacity to carry the full volume of materials for each batch of concrete.
Partitions separating batches shall be approved by the Engineer and shall be
adequate and effective to prevent spilling from one compartment to another
whilst in transit or being dumped.
CEMENT
4/21.8
Cement shall be stored in a dry weather-proof shed with a raised wooden floor
or in a silo and shall be delivered in quantities sufficient to ensure that there is
no suspension or interruption of the work of concreting at any time. If stored in
sheds, each consignment shall be kept separate and distinct.
4/22
MIXING CONCRETE
4/22.1
4/22.2
4/22.3
March 2015
Tender Documents
Page 4/27
Volume 2 Part I
4/22.4
Mixers which have been out of use for more than 30 minutes shall be
thoroughly cleaned before any fresh concrete is mixed.
4/22.5
4/22.6
The Contractor shall ensure that the constituent materials of the concrete are
sufficiently cool to prevent the concrete from stiffening in the interval between
its discharge from the mixer and compaction in its final position. Precautions
shall include the shading of aggregate stockpiles and the use of chilled water.
4/23
4/23.1
Ready mixed concrete as defined in BS 5328, batched off the site, may be
used only with the agreement of the engineer and shall comply with all
requirements of the Contract.
4/23.2
4/23.3
When truck mixed concrete is used, water shall be added under the
supervision, either at the Site or at the central batching plant as agreed by the
Engineer but in no circumstances shall water be added in transit.
4/23.4
Unless otherwise agreed by the Engineer, truck mixer units and their mixing
and discharge performance shall comply with the requirements of BS 4251.
Mixing shall continue for the number and rate of revolutions recommended in
accordance with Item 9 in Appendix B of BS 4251 or, in the absence of the
manufacturer's instructions, mixing shall continue for not less than 100
revolutions at a rate of not less than 7 revolutions per minute.
4/23.5
Pumping concrete through delivery pipes may be permitted but only with the
prior approval of the Engineer.
4/23.6
Re-mixing of concrete which has commenced to set shall not be allowed and
in no case shall such concrete be used in the Works.
Coarse aggregate shall be kept in identified stockpiles from which samples
can be collected and tested as specified.
4/23.7
4/23.8
The concrete supplier is required to certify that the Cl content in the mix being
delivered is within the limits specified in Clause 4/15.5. The Cl and SO3
content shall be checked at frequent intervals.
4/24
4/24.1
The method of transport and placing concrete shall be to the approval of the
Engineer. Concrete shall be so transported and placed that contamination,
segregation or loss of the constituent materials does not occur.
March 2015
Tender Documents
Page 4/28
4/24.2
Volume 2 Part I
All formwork and reinforcement shall be clean and free from standing water
immediately before placing concrete.
No concrete work shall be stopped or temporarily discontinued within forty-five
(45) centimeters of the top of any finished surface, unless such work is
finished with a coping having a thickness less than forty-five (45) centimeters
in which case the joint shall be made at the under edge of the coping.
Concrete in simple slab spans shall be placed in one (1) continuous operation
for each span, unless otherwise indicated on the drawings or approved by the
Engineer.
4/24.3
4/24.4
4/24.5
Concrete shall not be placed in any part of the Works until the Engineer's
approval has been given. If concrete has not started within 24 hours of such
approval being given, approval shall again be requested. Concreting shall
then proceed continuously over the area between construction joints. Fresh
concrete shall not be placed against in-situ concrete which has been in
position for more than 30 minutes unless a construction joint is formed in
accordance with the Specification. When the concrete has been in place for 4
hours, or less as directed by the Engineer, further concrete shall not be placed
against it for a further 20 hours.
4/24.6
Concrete when deposited shall have a temperature of not more than 32 deg. C
unless otherwise specified. Concrete shall be compacted in its final position
within 30 minutes of discharge from the mixer unless carried in purpose made
agitators operating continuously, when the time shall be within 1 hour of the
introduction of cement to the mix and within 30 minutes of discharge from the
agitator.
Except where otherwise agreed by the Engineer, concrete shall be deposited
in horizontal layers to a compacted depth not exceeding 400mm where
internal vibrators are used or 300mm in all other cases.
4/24.7
4/24.8
March 2015
Unless otherwise agreed by the Engineer, concrete shall not be dropped into
place from a height exceeding 2m. When trunking or chutes are used they
shall be kept clean and used in such a way as to avoid segregation. Where
steep slopes are required for placing concrete with chutes, the chutes shall be
equipped with baffle boards or be in short lengths that reverse the direction of
the movement. Chutes and the use of chutes must be approved by the
Engineer. All chutes shall be kept clean and free from coating of hardened
concrete by thoroughly flushing with water after each run. The water used for
flushing shall be discharged clear of the concrete already in place.
Tender Documents
Page 4/29
Volume 2 Part I
4/24.9
4/24.10
4/24.11
4/24.12
A complete record shall be kept of the date, time, temperature and conditions
of placing the concrete in each portion of the work and shall be available for
inspection by the Engineer at any time.
4/24.13
Unless otherwise shown on the drawings all concrete placed below ground
level shall have a minimum protection to its outside faces as follows:
Underside - Protected by the laying of a grade 1000 approved polyethylene
sheeting on the blinding concrete. The sheeting shall be returned up the
outside faces of the concrete and suitably sealed.
Sides - Coated with 3 coats of an approved bitumen rubber latex emulsion
flexible damp and vapour-proof liquid membrane conforming to BRE Digest
No. 54.
4/25
COMPACTION OF CONCRETE
4/25.1
4/25.2
4/25.3
4/25.4
March 2015
Tender Documents
Page 4/30