Construction and Building Materials: Yoon Suk Choi, Seong-Tae Yi, Myung Yu Kim, Woo Young Jung, Eun Ik Yang
Construction and Building Materials: Yoon Suk Choi, Seong-Tae Yi, Myung Yu Kim, Woo Young Jung, Eun Ik Yang
Construction and Building Materials: Yoon Suk Choi, Seong-Tae Yi, Myung Yu Kim, Woo Young Jung, Eun Ik Yang
Department of Civil Engineering, Gangneung-Wonju National University, 7, Jukheon-gil, Gangneung-si, Gangwon-do 210-702, South Korea
Department of Civil and Environmental Engineering, Inha Technical College, 100, Inha-road, Nam-gu, Inchon-si 402-752, South Korea
h i g h l i g h t s
The bond capacity is affected by the corrosion method of rebar in RC specimens.
The slip at failure was increased when the corrosion level was higher than 5%.
The bond strength was increased when corrosion level was lower than 1%.
The expansion pressure of corroded rebar ranged from 9.3 to 13.4 MPa.
The brittle failure pattern was observed when the area of corrosion exceeded 50%.
a r t i c l e
i n f o
Article history:
Received 13 May 2013
Received in revised form 18 December 2013
Accepted 19 December 2013
Available online 14 January 2014
Keywords:
Bond characteristics
Corrosion method
Articial corrosion
Natural corrosion
Reinforced concrete
a b s t r a c t
Reinforcing bars embedded in concrete structures are corroded, for example, by the ingression of chlorides from sea sand and deicing materials. Such corrosion induces interior pressure which is increased
in the surrounding concrete due to expansion of rebar. As a result, the bond strength and stiffness of reinforcing bar are reduced and the structure eventually undergoes deterioration of concrete which lead to
drastic shortening of service life of concrete structures. Accordingly, many researchers have investigated
on relationship of bond characteristics of reinforced concrete (RC) members and corrosion of the reinforcing bar. One technique to dene the relationship is to articially induce rapid corrosion of the reinforcing
bar. However, this articial corrosion method failed to provide an accurate representation of real conditions and led to overestimation of the performance of RC members in real situations. The objective of this
paper is to investigate the differences of bond characteristics in RC members corroded by articial rapid
and natural corrosion methods. The evaluation on technique suitability was also performed.
The results of this investigation indicated that the failure pattern and the critical corrosion level at
which the bond capacity failed, varied depending on the RC corrosion method. The RC specimens were
deteriorated at a low corrosion stage under natural corrosion conditions. More attention is needed to
be given to the rapid articial RC member corrosion method. Non-destructive test (NDT) methods were
also applied to RC specimens for investigation of the naturally corroded members. A formula of corrosion
area prediction from NDT was proposed.
2014 Elsevier Ltd. All rights reserved.
1. Introduction
When reinforcing bar is corroded, the durability of reinforced
concrete (RC) members will be severely fell and the service life will
be accordingly shortened. The big and long infrastructures become
more vulnerable to safety hazards as their size increase. Accurate
prediction of the service life of these members has become a considerable challenge [1,2]. Corrosion of reinforcing bars in concrete
Corresponding author. Tel.: +82 33 640 2418; fax: +82 33 646 1391.
E-mail addresses: yoons0305@gwnu.ac.kr (Y.S. Choi), eiyang@gwnu.ac.kr (E.I.
Yang).
1
Tel.: +82 33 640 2416; fax: +82 33 646 1391.
0950-0618/$ - see front matter 2014 Elsevier Ltd. All rights reserved.
http://dx.doi.org/10.1016/j.conbuildmat.2013.12.065
181
comparison purposes. The details of other test setups can be found in a research
report by Chapman and Shah [15]. After evaluating various setups, a modied
version of the setup proposed in Danish Standard (DS) 2082 [16] was chosen to
be used in this study (Fig. 1).
The test specimens were fabricated in cubic with 150 150 150 mm cubes
dimension by considering the appropriate size and shape for the pullout test and
current corrosion measurement. The bond length was set to four times the diameter
(db 25 mm) of rebar (i.e., 4db 100 mm). Moreover, the rebar exposed to air was
treated with a rust inhibitor to prevent its corrosion. After removal from the mold,
the specimen was water-cured in a water chamber for four weeks at a temperature
of 20 3 C. For the case of articially induced corrosion of the rebar (method A),
the bond test was conducted at 28 days. On the other hand, the specimens with
articially corroded rebar after placement (method B) were subjected to accelerated
corrosion for 14 days and a bond test was performed at 28 days. In contrast, the naturally corroded specimens (method C) were air-cured in an outdoor environment
until the occurrence of corrosion. The usual cylinder molds with diameter of
100 mm and height of 200 mm were used to prepare specimens for the compression test.
1
2 96; 500
qdt
In this equation, the amount of corrosion (mole) is the number of moles of corroded iron ion (Fe), and q (Ampere) is the amount of current passed through each
stage.
The articial corrosion accelerated test was carried out up to a 10% corrosion
level. However, the expansion pressure of the rebar caused corrosion cracks at only
above 2% of corrosion. When cracks occur, the durability and strength of the specimen were suddenly decreased [8,9]. Accordingly, the bond test was conducted on
the specimens with corrosion up to approximate 2%. Fig. 4 showed the cracks of
specimen due to excessive corrosion.
Table 1
Experimental variables.
W/C (%)
Corrosion method
40
Articial corrosion
Rebar corroded before placement (method A) (corrosion level: 0%, 2%, 5%, 7%, 10%)
Rebar corroded after placement (method B) (expected corrosion level: 0%, 2%, 5%, 7%, 10%)
Measurement
Bond capacities by pullout of rebar
60
Natural corrosion
Corrosion by chloride ion intrusion (method C) (0.6, 0.9, 1.2, 1.5, 1.8, 2.4, 3.0, 3.6 kg/m3)
182
Table 2
Physical properties of the aggregate.
Type
Specic
gravity
Absorptivity
(%)
Fineness modulus
(F.M.)
Fine aggregate
Coarse
aggregate
2.59
2.64
0.99
0.70
2.65
6.82
Table 3
Concrete mix proportion.
W/C (%)
40
60
S/a (%)
43
46
Admixture (kg)
Water
Cement
Sand
Gravel
170
172.5
425
288
716
813
1022
978
2.125
0.864
induce the natural corrosion surrounding reinforcing bar. The chloride contents
were 0.6, 0.9, 1.2, 1.5, 1.8, 2.4, 3.0, and 3.6 kg/m3. The specimens were put in a
chamber with 60% of RH and 20 C of temperature. Natural corrosion test (method
C) was performed within a period of two years. The corrosion progress of reinforcing bar in concrete was estimated by the NDT. Fig. 5 showed the method used to
compare the degree of corrosion measured by NDT methods and the actual amount
of corrosion of the rebar inside the concrete specimen. The surface of the rebar perpendicularly penetrated the cross-section of the reference electrode and was considered when measuring the polarization resistance. Then, the total cross-section
and the ratio of corrosion area were calculated as the corroded area of the total
cross-section.
When the half-cell potential method was applied, the concrete surface was
maintained in a condition of wetness for 30 min prior to the measurement. The
standard electrode (i.e., saturated copper sulfate electrode) was then connected
to the anode and the rebar inside the concrete was connected to the cathode. After
building a cell by combining these elements, the potential difference between cathode and anode of the assembly was measured [17].
In addition, the measurement of polarization resistance of the rebar was carried
out by using a PR-4500 model device from CC Technologies. The standard electrode
was a saturated copper sulfate electrode. A guard electrode was used to conne the
reference electrode and the polarization area. The rebar and electrodes were electrically conducted through a sponge wetted with liquid detergent. The shift range of
potential during the polarization resistance measurement was from 20 mV to
+20 mV based on the corrosion potential. The polarization area of the rebar was
then computed by measuring the surface area of rebar which was covered by the
vertical projection of the reference electrode cross-section [18].
2.5. Bond properties with corrosion of the reinforcing bar
The bond property evaluation of the corroded rebar was executed by a pullout
test by considering the corrosion degree of the rebar as the main variable. In this
test, a Universal Testing Machine (UTM) was used to apply the load. The experiment
was performed by using a load control method until the specimen failed. The
183
Fig. 4. Appearance of cracking for the specimen with 2% corrosion level (method B).
amount of relative slip by loading was measured by using two linear variable displacement transducers (LVDTs) which were installed between the rebar and concrete (Fig. 6). The displacement and loading value at each step were then
automatically recorded. The strain in the reinforcing bar was very low and its yielding was not observed in any tests.
184
60
50
40
30
ft A
20
W/C=0.4
W/C=0.6
10
0
0
300
600
900
1200
Age (days)
Fig. 7. Development of the compressive strength with age.
bond behavior of corroded RC members has been previously investigated through experimental and analytical studies and most of
them were focused on corroded bar experiencing severe corrosion.
However, not much attention was given to the bond behavior in
Lp
100
(b)
(a)
80
Load (kN)
80
Load (kN)
100
60
40
0%
2%
5%
7%
10 %
20
0
0.0
pD
0.2
0.4
0.6
Slip (mm)
0.8
60
40
0%
2%
5%
7%
10 %
20
1.0
0
0.0
0.2
0.4
0.6
Slip (mm)
Fig. 8. Loadslip curve with corrosion level (method A): (a) W/C = 0.4 and (b) W/C = 0.6.
0.8
1.0
185
100
100
80
80
60
40
W/C=0.4
W/C=0.6
20
0
0
60
40
W/C=0.4
W/C=0.6
20
0
0.0
10
0.5
1.0
1.5
2.0
2.5
Fig. 11. Maximum bond load versus corrosion level (method B).
100
100
(a)
(b)
80
Load (kN)
Load (kN)
80
60
40
0%
0.5 %
0.9 %
1.1 %
1.7 %
20
0
0.0
0.2
0.4
0.6
Slip (mm)
0.8
60
40
0%
0.8 %
1.3 %
1.8 %
2.3 %
20
1.0
0
0.0
0.2
0.4
0.6
Slip (mm)
Fig. 10. Loadslip curve with corrosion level (method B): (a) W/C = 0.4 and (b) W/C = 0.6.
0.8
1.0
186
100
100
(b)
(a)
80
Load (kN)
Load (kN)
80
60
40
0%
15 %
35 %
50 %
70 %
20
0
0.0
0.2
0.4
0.6
0.8
60
40
0%
15 %
50 %
80 %
95 %
20
1.0
0
0.0
0.2
0.4
Slip (mm)
0.6
0.8
1.0
Slip (mm)
Fig. 12. Loadslip curve with corrosion area rate ratio (method C): (a) W/C = 0.4 and (b) W/C = 0.6.
100
W/C=0.4
W/C=0.6
0.8
0.6
0.4
0.2
80
60
W/C=0.4
W/C=0.6
0.0
0
20
40
60
80
100
40
0
20
40
60
80
100
187
-200
-300
-400
-500
0.0
0.8
1.6
2.4
3.2
4.0
100
100
y=-0.34x-54.0
2
R =0.56
80
W/C=0.4
W/C=0.6
-100
60
40
20
0
-500
y=-23.4ln(x)+145.6
2
R =0.79
80
60
40
20
0
-400
-300
-200
-100
100
200
300
400
500
2
600
188
500
W/C=0.4
W/C=0.6
400
4. Conclusions
300
In this study, the bond property of corroded rebar at each corrosion stage due to different corroding methods of reinforcing
bar were compared and evaluated. The conclusions obtained from
this study are summarized below:
200
100
0
0
20
40
60
80
100
600
500
W/C=0.4
W/C=0.6
400
300
200
100
0
0.0
0.8
1.6
2.4
3.2
4.0
Acknowledgments
The data for Fig. 17 were used again in Fig. 18 to examine the
distribution of the polarization resistance according concrete properties. From the relationship, it is found that the value of polarization resistance is somewhat high when W/C is low for a corrosion
area ratio range from 10% to 60%. The difference in the polarization
resistance is attributed to the increase of concrete resistance since
concrete becomes water-tight when W/C is low or admixture is
added. Due to this resistance, the ow of micro-current also becomes faster. In the case of a corrosion area ratio of 80% or above,
corrosion was observed throughout the specimen. However, the effect of W/C was not signicant. Moreover, the effect of resistance
due to the corrosion products increased and was consistent with
the half-cell potential measurements.
Fig. 19 showed the changes in the polarization resistance
according to the amount of chlorides in concrete. The half-cell potential showed lower distribution as the amount of chlorides increased. On top of that, the value of polarization resistance was
also decreased with an increase of chloride content as the progression of corrosion due to the chlorides inside concrete.
In summary, the polarization resistance method was not greatly
affected by the physical properties of concrete. The value of
189
[14] ASTM C 234. Standards test method for comparing concretes on the basis of
the bond developed with reinforcing steel; 1991.
[15] Chapman RA, Shah SP. Early-age bond strength in reinforced concrete. ACI
Mater J 1987;84(6):50110.
[16] Danish Standards Organization, Pullout Test. DS 2082, Copenhagen; 1980. p. 2.
[17] ASTM C876. Standards test method for half-cell potentials of uncoated
reinforcing steel in concrete; 1999.
[18] ASTM G59. Standard test method for conducting potentiodynamic polarization
resistance measurements; 1997.
[19] Fu X, Chung L. Effect of watercement ratio, curing age, silica fume, polymer
admixtures, steel surface treatments, and corrosion on bond between concrete
and steel reinforcing bars. ACI Mater J 1998;95(6):72534.
[20] CEB Bulletin, No.243. Strategies for testing and assessment of, concrete; 1998.