Guidance Notes For Onshore Oil and Gas Field Development Plans
Guidance Notes For Onshore Oil and Gas Field Development Plans
Guidance Notes For Onshore Oil and Gas Field Development Plans
Toni Harvey
Sr Geoscientist
email: toni.harvey@decc.gsi.gov.uk
phone: +44 (0) 300 068 6037
fax: +44 (0) 300 068 5003
CONTENTS
INTRODUCTION
THE REGULATORY FRAMEWORK AND DEPARTMENTAL POLICY
THE DEVELOPMENT PLAN: PROCESS AND CONTENT
DEVELOPMENT PLAN AUTHORISATION AND PRODUCTION CONSENTS
ANNUAL FIELD REPORTS
CESSATION OF PRODUCTION
OPERATORSHIP AND LICENSEE RESIDENCE REQUIREMENTS
INTRODUCTION
These notes outline DECCs requirements for onshore oil and conventional gas field
development plans. There are also guidance notes for coalbed methane and mines gas fields
and gas storage into depleted fields here.
These notes cover only those field developments that are wholly onshore. Offshore fields that
are to be developed from an onshore location are covered by these guidance notes.
These notes also explain the arrangements for dealing with fields that cross licence
boundaries and where operations are undertaken by a contractor on behalf of Licensees. They
also cover licensee residence requirements, field operatorship requirements, the preparation of
Field Reports for onshore oil and gas fields and for cessation of production. The notes are
intended as a working guide and not as a definitive explanation of the requirements of the
model clauses or of the Secretary of States powers under them.
If you have any questions or comments on these notes please contact Toni Harvey
(toni.harvey@decc.gsi.gov.uk).
In order for the Licensees to understand what constitutes a Field for both Unit Development
and tax purposes, the Department will issue a proposed Field Determination at an early stage
in the Field Development Plan authorisation process, utilising the geological information that
is available to it at that time.
The Department may authorise extended periods of test production (Extended Well Tests)
from exploration or appraisal wells prior to development approval if it can be demonstrated
that the Licensees will thereby gain the technical understanding or confidence in the
performance of the field needed to progress towards a development. The EWT should have
realistic and definable appraisal objectives essential to the success of a development and not
be prejudicial to ultimate recovery. There are no strict criteria governing the maximum
volume to be produced or the duration of an EWT, although the duration of an EWT normally
is not expected to extend beyond 90 days. The duration may be extended if there is a technical
justification, but it should be noted that EWTs are not an alternative to production under an
approved Development Plan. There is no obligation to proceed with a development following
an EWT. An EWT consent requires a formal letter of application setting out the timetable and
objectives of the test and the quantities of oil and gas to be produced and saved or
flared/vented. Operators should note that if oil and gas is to be saved during the EWT, a Field
Determination may be required for the field in question. Throughout the duration of the test
the operator should submit monthly oil, gas and water production figures to DECC. These
should be e-mailed at the end of each month to david.roberts@decc.gsi.gov.uk.
With the exception of certain pipelines environmental management of onshore hydrocarbon
developments does not come within the jurisdiction of the Department. Environmental
legislation is implemented by DEFRA, the Environment Agency in England and Wales,
Scottish Environment Protection Agency (SEPA) and the relevant local authorities. The key
planning and environmental legislation affecting the onshore hydrocarbon industry is
summarised here. Any oil and gas development must have the relevant consent(s) from
these authorities for both construction and operations. The Department will require
proof that such consents have been obtained before consenting to any development.
A statement of intent towards any parts of the field not addressed by the Plan
including any commitment to later development of that area, or to the later stages of a
phased development. Any provision for the development of other hydrocarbons in the
area should also be identified.
A summary of the main and standby capacities of major utility and service systems,
together with the limitations and restrictions on operation.
A summary of the method of metering hydrocarbons produced and utilised.
A brief description of systems for collecting and treating oil, water and other discharges.
A brief description of any fluid treatment and injection facilities.
A brief description of the main control systems and their interconnections with other
facilities.
3.4 Costs
Cost information is not required at present.
3.5 Field Management Plan
A brief review is required that sets out clearly the principles and objectives that the Licensees
will hold to when making field management decisions and conducting field operations and, in
particular, how economic recovery of oil and gas will be maximised over field life. The
rationale behind the data gathering and analysis proposed in order to resolve the existing
uncertainties set out in Section 2 and understand dynamic performance of the field during
both the development drilling and production phases should be outlined.
The potential for workover, re-completion, re-perforation and further drilling should be
described. Where options remain for improvement to the development or for further phases of
appraisal or development, the criteria and timetable for implementing these should be given.
The extension itself will be granted nearer the time of expiry if it continues to be the case that
production will continue beyond the original licence term. The extension will cover the area
of production and the time needed to complete production from it.
INTRODUCTION
A brief review of the field operations and export route with any divergence from the
Development Plan should be summarised. Any changes in licence equity should be given. A
map showing the field extent and licence boundaries should be provided.
2.
FIELD DESCRIPTION
2.1
Hydrocarbons Initially In Place and Recoverable Reserves
Changes in estimates of hydrocarbons initially in place and reserves should be identified by
reference to the Development Plan base case and to the case in any previous FDPA.
2.2
Well Status and Operations
A table summarising changes in well status (e.g. producer/injector, suspended/abandoned,
perforated intervals, reservoir identifier, lift provision) should be included and should note
any well operations carried out during the reporting period (e.g. drilling, workovers, data
gathering, perforating, stimulation).
2.3
Geology and geophysics
A detailed depth structure map for key productive horizon with annotation of the max extent
(e.g. GDT or OWC) and well paths from the surface to top horizon is required along with an
interpreted seismic line across the field, or if none exists a schematic cross section is
acceptable. Where drilling, seismic re-processing or other work has had a significant impact
on the reservoir model a summary of the results should be provided.
2.4
Field Facilities and Infrastructure
An OS plat which shows the location of all field facilities is required. A brief report on the
performance of the field production facilities highlighting features that have impeded
operations and also valuable improvements should be added.
3.
3.1
Field Management
Any changes in development strategy should be reviewed. Important reservoir monitoring
results, reservoir monitoring limitations and specific production difficulties should be
summarised. Where appropriate, plots of reservoir pressure and voidage replacement should
be provided. Plans for reservoir monitoring in the coming year should be briefly discussed.
3.2
Studies
The results and relevance of any geoscience, reservoir or facilities/pipeline engineering
studies completed during the reporting period should be summarised. Plans and timescale for
ongoing and future studies should be briefly discussed.
3.3
Improved Oil Recovery (IOR)
Where appropriate the potential for IOR should be reviewed and the results of any studies or
operations discussed.
3.4
Forecasting
A table of the current forecast and the Development Plan production, vent and flare volumes
and injection profiles should be provided, together with the current estimate of the Cessationof-Production date.
3.5
Proposed Changes to the Development Plan
Proposed changes to commitments or to conditions in the development consent should be set
out clearly as should plans to extend the development beyond the Development Area. The
need to include other deviations should be discussed with the DECC. Where appropriate a
summary of longer term development opportunities within or around the field should be
provided.
3.6
Field Operating Costs
CAPEX and OPEX profiles should be provided for the previous two year period, together
with a three year projection of predicted expenditure; categorised as follows: new wells,
workovers, side-tracks, facilities upgrades. Any large variations from the previous Field
Report should be explained.
3.7 Other Regulatory issues
A summary of the status of other regulatory consents and permissions should be provided,
including the term of the planning consent and environmental permiting (e.g. W Sussex
Council planning permission for field operations is in place until 2017, status of EA permits
if re-starting production is proposed).
CESSATION OF PRODUCTION
Departmental consent is required before production ceases and the field is decommissioned.
In order that consent can be granted a Cessation of Production (COP) report is required. The
amount of detail to be included in the COP will depend on whether options to extend field life
have been appropriately covered in previous field reports.
The report should cover:
Definition of economic limit.
Determination of cut-off rates and timing.
Cash flow over the period up to this economic limit and approximately 2 years beyond.
The costs and any revenues associated with COP itself (capital and operating
expenditures and any residual value of field assets).
The form and costs of abandonment if these affect the timing of the economic limit.
Possible options for extending field life.
Production and injection profiles together with projections through to economic limit
and approximately 2 years beyond.
Details of any remaining licence obligations.
Appropriate reservoir maps indicating the estimated location and distribution of
remaining technically recoverable oil/gas that will be undrained at the time of Cessation of
Production. In addition some conception of likely changes in such distributions over time
should be given for completeness of the record.
Confirmation that all abandonment requirements in the relevant planning consents will
be met and details of what is involved
It is important that sufficient information is retained after COP to enable other interested
potential operators to take a reasonably informed view about the potential for field
redevelopment. Redevelopment may become feasible if, for example, new technology allows
a significantly improved recovery factor. For this reason COP documents will be released
once the licence(s) involved are relinquished.