Probe Test
Probe Test
Specification for Cavity and Slumpzone Probing and Compaction Grout Treatment
7 October 1999
1.0
GENERAL REQUIREMENTS
This specification is to be read in conjunction with the contract, the general specification and all
other specifications and drawings. The Contractor shall design and carry out compaction
grouting of slumpzone, soft or loose soils and voids, above and between rock layers to ensure
that the areas and depths specified for such treatment shall be so treated as to comply with the
Criteria of Acceptance.
In the event that the provisions of other specification clauses cause ambiguity or conflict with the
requirements of this specification, the latter shall take precedence unless otherwise approved
by the Engineer.
Where works are ordered to be performed by the Contractor, but are not specified in these
specifications, the Contractor shall carry them out with full diligence and expedience as are
expected for works of this nature.
2.0
In the event when conflicting requirements occur in different Standards, the most stringent
standard shall take precedence.
3.0
SUBMITTALS
Before commencement of the work, the Contractor shall submit to the Engineer for his approval
legible points of shop drawing, method statement and design calculations of the proposed
treatment. The method statement should include detailed procedures for probing, treatment
and full descriptions of the procedures, equipment and materials to be used.
After completion of works at site, the Contractor shall submit complete reports (6 copies) of the
probing and treatment that include actual locations of cavity/slump zone, summary of drilling
records with rate of drilling, anomalies and full details of materials used, pumping pressure and
other relevant information listed in Section 17.0.
4.0
PCG1
with drilling fluid of bentonite or polymer slurry unless otherwise agreed by the Engineer. The
head of the drilling fluid shall be kept at a level high enough to ensure sufficient stabilising
capacity in the cased or uncased drillholes.
The depth of probing into limestone bedrock shall be a minimum of 10m if no cavity is
encountered and 10m below the last cavity encountered unless otherwise directed by the
Engineer. The boring of soil below cavity roof or overhang shall be considered as boring in soil
and shall not be considered as coring in rock. Standard penetration tests (SPT) shall be carried
out in all cavities with soil at interval of 1m until the next layer of rock is encountered. The
Contractor will only be allowed not to carry out SPT in cavity if the drilling and treatment is to be
carried out simultaneously using method and equipment approved by the Engineer.
The penetration speed of the cavity probing shall be recorded in every 1.0m penetration
intervals starting from the ground level. The occurrence of slumpzone above rock or cavities
within the limestone strata will be determined upon a sudden increase of penetration speed.
The Engineer will decide whether to treat the slumpzone or cavities based on the penetration
speed records submitted by the Contractor. The Contractor shall plot the penetration speed
versus depth and submit or fax the plot together with the data to the Engineer immediately after
drilling so that the Engineer can decide on the treatment. If the penetration speed are not
properly recorded and submitted to the Engineer in time for his decision on treatment, the
Engineer can reject the hole and a replacement hole has to be carried out by the Contractor
with no claim of extension of time and addition cost.
The diameter of the drillhole shall be large enough to allow compaction grout to be carried out
immediately after reaching the required level without having to redrill the hole after probing of
cavities. The diameter of the drillhole shall be proposed by the Contractor and approved by the
Engineer. If treatment of slumpzone and cavity is not required, the drill hole shall be properly
backfilled with cement-grout (W/C = 0.6) or low strength sand-cement mortar to the existing
ground level.
5.0
SPECIALIST SUBCONTRACTOR
Compactions grouting shall be carried out by experienced specialist subcontractors who have
previously carried out this treatment successfully and to the agreement of the Engineer. The
Specialist Subcontractor shall
(i)
6.0
PERSONNEL
The Specialist Subcontractor shall employ sufficient of experience personnel who are familiar
with the type of cavity probing and compaction grouting described in this contract. All
personnel shall be to the agreement of the Engineer.
7.0
For soils within the treatment zone, the individual SPTN values at any point
PCG2
(ii)
(iii)
is not less than 20 and the average SPTN value is not less than 25; unless
otherwise agreed by the Engineer.
No void is encountered; and
Unconfined compression strengths of the cores are in excess of 2 N/mm2.
Grouting shall be repeated until compliance with the Criteria of Acceptance. Provisions have
been made in the Bills of Quantities for the boreholes constituting the first check for
compliance with the Criteria of Acceptance. Subsequent boreholes after subsequent grouting
due to the Contractor's inability to comply with the Criteria of Acceptance shall be at his own
cost.
All boreholes shall be grouted to the satisfaction of the Engineer immediately on completion.
8.0
MORTAR MATERIAL
The Contractor shall submit his proposed mortar material for the agreement of the Engineer.
Generally and unless demonstrated by field trials that the Criteria of Acceptance may
otherwise be achieved, the grain size distribution of the mortar material shall comply with the
grading limits given in Table 1.
British Standard
Sieve Size
Percentage Passing
5mm
2mm
600m
75m
2m
100%
90 to 100%
55 to 85%
7 to 15%
<1%
Table 1
9.0
MORTAR MIX
The Contractor shall submit his proposed mortar mix design for the agreement of the
Engineer. Generally and unless demonstrated by field trials that the Criteria for Acceptance
may otherwise be achieved, the mortar mix shall comply with the limits given in Table 2.
Chemicals like retarder have to be used if the injection time will be long and to prevent
clogging of pipe during injection. However, any other chemicals to be used shall be agreed
by the Engineer.
Material
Mortar Material
Portland Cement
Range
1000 to 1500 kg
360 to 500 kg
Table 2
The Contractor shall carry out trial mix at site to justify the workability and strength of the
proposed mortar mix.
10.0
SLUMP
The Contractor shall submit his proposed slump for the agreement of the Engineer. Slump
shall be in the range of 50 to 110mm and shall be tested on site for each batch of mix.
PCG3
11.0
12.0
13.0
14.0
15.0
EQUIPMENT
Equipment shall be such as to enable the anticipated high pressures and injection rates.
All grout pipes and connections are to withstand the anticipated high
pressures with adequate factors of safety.
16.0
PCG4
17.0
RECORDS
2 copies of completed records for grouting at each location shall be submitted to the
Engineer. The record shall include the following information:
(i)
(ii)
(iii)
(iv)
(v)
(vi)
(vii)
(viii)
(ix)
(x)
(xi)
(xii)
(xiii)
PCG5
TABLE OF CONTENTS
Description
Page
1.0
2.0
3.0
SUBMITTALS........................................................................................................................... PCG1
4.0
5.0
6.0
7.0
8.0
9.0
10.0
SLUMP..................................................................................................................................... PCG3
11.0
12.0
13.0
14.0
15.0
EQUIPMENT............................................................................................................................ PCG4
16.0
17.0
PCG i