Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

HW 7

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 13

HW-7

Chapter-13 page 445


Review questions-2, 3, 4, 5
Exercise-5 and 6(You may use Excel for calculations)

2. How does earned value give a clearer picture of project schedule and
cost status than a simple plan versus actual system?

Earned value gives a clearer picture than a simple plan versus actual system
because the earned value system includes the time variable in measuring
progress. Plan versus actual can lead to false conclusions. Earned value
measures what work was accomplished for the money spent.

3. Schedule variance (SV) is in dollars and does not directly represent


time. Why is it still useful?

SV gives a project view of how well all of the scheduled activities are meeting
planned dates. Research shows that after twenty percent of a large project is
complete, SV is a relatively good indicator of schedule performance (even
though it is in dollars or labor hours).

4. How would a project manager use the CPI?

The cost performance index (EV/AC) is a popular index. An index of .60 indicates
that 60 cents of work has been completed for each actual dollar spent. This
would suggest to the project manager that the project will be over budget or big
savings in remaining work will be needed to bring the project in on budget.

5. What are the differences between BAC and EAC?

BAC is the planned budget at completion. EAC is the estimate at completion.


EAC can be calculated two ways. First is simply by formula, which is used in
software programs; the formula applies a performance ratio from past work on
the project to the remaining work for an EAC. A second method uses new cost
estimates that have been made by project participants concerning specific work
packages; these new estimates are then factored into the EAC.
5. The following labor hours data have been collected for a
nanotechnology project for periods 1 through 6. Compute the SV, CV,
SPI, and CPI for each period. Plot the EV and the AC on the summary
graph provided (or a similar one). Plot the SPI, CPI and PCIB on the
index graph provided (or a similar one). What is your assessment of
the project at the end of period 6?

After 6 time periods the project is roughly 66% complete and so far work on the
project has taken 1,600 hours less work than planned. There is 400 hours worth
of work on Activity 4 which was supposed to have been done that has not done.
Since Activity 4 is on the critical path, the project is behind schedule. If schedule
is the number priority, the project manager may want to consider investing some
of the savings on accelerating critical activities.

Status Report: Ending Period 1


Task
1

%
Complete

EV

AC

PV

CV

SV

50%

1000

500

1000

+500

1000

500

1000

+500

Cumulative Totals

Status Report: Ending Period 2


Task
1

%
Complete

EV

AC

PV

CV

SV

Finished

2000

1500

2000

+500

2000

1500

2000

+500

Cumulative Totals

Status Report: Ending Period 3


Task

%
Complete

EV

AC

PV

CV

SV

Finished

2000

1500

2000

+500

0%

1600

-1600

10%

300

200

500

+100

-200

20%

500

500

1000

-500

2800

2200

5100

+600

-2300

Cumulative Totals

Status Report: Ending Period 4


Task

%
Complete

EV

AC

PV

CV

SV

Finished

2000

1500

2000

+500

50%

1200

1000

2400

+200

-1200

30%

900

800

1000

+100

-100

40%

1000

1500

2000

-500

-1000

Cumulative Totals

5100

4800

7400

+300

2300

Status Report: Ending Period 5


Task

%
Complete

EV

AC

PV

CV

SV

Finished

2000

1500

2000

+500

Finished

2400

2000

2400

+400

50%

1500

800

2000

+700

-500

60%

1500

1500

2200

-700

25%

400

400

400

7800

6200

9000

+160
0

1200

Cumulative Totals

Status Report: Ending Period 6


Task

%
Complete

EV

AC

PV

CV

SV

Finished

2000

1500

2000

+500

Finished

2400

2000

2400

+400

80%

2400

2100

2300

+300

+100

80%

2000

1800

2400

+200

-400

50%

800

600

800

+200

9600

8000

9900

+160
0

-300

Cumulative Totals

Indexes

Perio
d

SPI

CPI

PCIB

1.00

2.00

.07

1.00

1.33

.14

SPI = EV / PV

.55

1.27

.19

CPI = EV / AC

.69

1.06

.35

PCIB = EV /
BAC

.87

1.26

.54

.96

1.20

.66

6. The following data have been collected for a British health care IT
project for two-week reporting periods 2 through 12. Compute the SV,
CV, SPI, and CPI for each period. Plot the EV and the AC on the
summary graph provided. Plot the SPI, CPI and PCIB on the index
graph provided.
(You may use your own graphs.)
What is your
assessment of the project at the end of period 12?

Status Report: Ending Period 2


Task

EV

($00)
AC

PV

CV

SV

Complete
1

50%

Cumulative Totals

Status Report: Ending Period 4


Task

EV

AC

PV

CV

SV

Finished

10

-2

Cumulative Totals

10

-2

%
Complete

($00)

Status Report: Ending Period 6


Task

%
Complete

($00)

EV

AC

PV

CV

SV

10

-2

Finished

25%

10

15

10

-5

33%

10

12

10

-2

0%

10

-10

28

37

38

-9

-10

Cumulative Totals

Status Report: Ending Period 8


Task

%
Complete

($00)

EV

AC

PV

CV

SV

10

-2

Finished

30%

12

20

20

-8

-8

60%

18

25

25

-7

-7

0%

20

-20

38

55

73

-17

-35

Cumulative Totals

Status Report: Ending Period 10


Task

%
Complete

($00)

EV

AC

PV

CV

SV

10

-2

Finished

60%

24

30

30

-6

-6

Finished

30

40

30

-10

50%

10

20

20

-10

-10

0%

30%

18

24

20

-6

-2

90

124

108

-34

-18

Cumulative Totals

Status Report: Ending Period 12


Task

%
Complete

($00)

EV

AC

PV

CV

SV

Finished

10

-2

Finished

40

50

40

-10

Finished

30

40

30

-10

Finished

20

40

20

-20

50%

20

30

20

-10

50%

30

40

40

-10

-10

148

210

158

-62

-10

Cumulative Totals

Indexes
Perio
d

SPI

CPI

PCIB

4/4 = 1.0

4/4 = 1.0

4/248 = .02

8/8 = 1.0

8/10 = .80

8/248 = .03

SPI = EV / PV

28/38 = .74

28/37 = .76

28/248 = .
11

CPI = EV / AC

38/73 = .52

38/55 = .69

38/248 = .
15

PCIB = EV /
BAC

10

90/108 = .83

90/124 = .
73

90/248 = .
36

12

148/158 = .
94

148/210 = .
70

148/248 = .
60

After 12 time periods the project is roughly 60 percent and the project is only
getting 70 cents worth of work for each dollar spent. The project is currently
$6,200 over budget. There is $1,000 worth of work that supposed to have been
done that has not been completed according to plan. However, this work
involved a noncritical activity and the project is on schedule with regards to the
critical path.

PCIB = .60

You might also like