Supplier PPAP Manual 71813
Supplier PPAP Manual 71813
Supplier PPAP Manual 71813
(PPAP)
Production Part Approval Process (PPAP) defines generic requirements for production part
approval. The purpose of PPAP is to determine if all of Alto Shaams engineering design records
and specification requirements are properly understood by the supplier, and that the
manufacturing process has the potential to produce product that will consistently meet these
requirements during an actual production run at the quoted quantity.
NOTE: Submission Requirements will be provided to the Supplier via the Purchase Order.
Unless specified in the Purchase Order, PPAP will not be required.
Suppliers are not to ship production orders to Alto-Shaam until notified of PPAP Approval
2 PPAP Sample Parts are required for Level 3 Submission and are to be Identified as
Unapproved PPAP Sample Parts (See Pages 15 & 17) and must be provided and
approved prior to any production shipment.
Revision 1
July 18, 2013
Introduction
The Alto Shaam Purchasing staff has prepared this guide for new and existing
suppliers of raw material and components to Alto Shaam. Its purpose is to define
the approval process of new or revised parts, or parts that are from new or
significantly revised production methods. As a Supplier, it is your responsibility to
ensure that you ship only parts that have been approved and meet Alto Shaam
specifications.
If you have questions regarding the contents or processes described in this guide,
please contact the Supplier Development Engineer representative of Alto Shaam at
1-800-558-8744.
For further information about the contents of this guide, please refer to the
Automotive Industry Action Groups (AIAG) Production Part Approval Process (PPAP).
New Part
New Supplier
Engineering Change
New Process
New or Change to supplier manufacturing location
New or modified Tools
Material change
Alto Shaam has forms available at: http://supplierportal.alto-shaam.com/ . You can use those or any
AIAG compliant form with the exception of Element 1, Part Submission Warrant.
4
Submission Levels
Submission Levels define which elements are required to be submitted. The levels are used for different
reasons and applications and are defined by Alto Shaam. There are three submission levels. The Level of
submission required will be communicated via the Purchase Order:
Level 1
Level 2
Level 3
Regardless of Submission Level, all PPAP submissions must be sent in advance of any production
shipments.
As specified by the Purchase Order, a PPAP submission will be required for each Part Number.
Level 3
S
2
Level 2
PPAP Requirements
Reference AIAG PPAP
Element
Fourth Edition Important:
Order
Submit your documents
in this order
Level 1
Alto Shaam has a Quick Reference Guide that can be used for referencing and organizing a PPAP
submission. The Reference Guide lists all of the required elements for each Submission Level, 1 through 3.
N/A S
N/A N/A S
N/A N/A S
Control Plan
Required Documents
Alto - Shaam Part Submission Form only
Additional Comments
Alto - Shaam PSW is required for all submissions and is required for all Alto Shaam designed parts.
Include one clean copy of the current approved revision print with all
dimensions, applicable specifications, and notes, bubbled (circled with
corresponding number) on the print for reference to the dimensional report.
Indentifies all process steps from receiving to shipping. Process steps must
match PFMEA and Control Plan steps.
Process steps must match Process Flow Chart, Control Plan and address all
characteristics associate with each operation. Risk Priority Numbers must
be identified with critical processes and inspections identified.
Control Plan must match the Flow Chart and PFMEA process steps and
describe the actions of each phase of the manufacturing process from
receiving to shipping. All Critical Characteristics must be addressed within
the corresponding process step. Any dedicated check/testing fixtures that are
used will be identified along with the numbered characteristic it
measures/tests on the print
Include all characteristics on the print. Report results should correspond to
the "Bubbled" dimensions of the Print and be reported in the same scale as
the Print. Results of 3 parts is required (if parts are from a Multi-Cavitiy tool,
report results for 1 piece per cavity, and note cavity).
N/A N/A S
Dimensional Results
Records of Material /
Performance Test Results
N/A S
N/A S
N/A *
9
N/A N/A S
Certificates of Analysis for all primary raw materials such as steel, rubber,
chemicals, and plastic resins. Performance life testing results, such as Salt
Spray, heat, electrical performance, when required by Print or Specification.
Capability Study using any statistical package A short term study of process capability must come from a significant
or Alto - Shaam supplied format.
production run. For Critical Characteristics a minimum Cpk value of 1.33 is
required. For Multi-cavity tools, a separate study is required for each cavity.
Parts Tagged "PPAP Samples"
2 sample parts with every submission unless otherwise requested. Multicavity tools require 1 part per cavity.
Electronic Submission
Alto Shaam prefers that all PPAP submissions be submitted electronically via e-mail to:
supplierppap@alto-shaam.com
It is preferred that the PPAP be 1 PDF file for the entire submission.
Sampling should be taken from a representative production run, utilizing production equipment,
tooling and production employees.
The intent is that all data reflects the actual production process to be used during production.
Submission Status
The review and approval of the PPAP submission will be managed by Alto Shaam. Submissions will be
reviewed and dispositioned with one of the following statuses:
Approved: Acceptance of the PPAP submission within the specified guidelines set forth by Alto Shaam.
Rejected: The PPAP submission does not meet the specified guidelines and must be resubmitted for
approval.
Interim Approval: An interim approval may be given through an agreement with Alto Shaam engineering,
and the product must not affect final product quality. Interim approval is limited to a defined number of
days or quantity, and a corrective action plan must be identified to achieve full approval.
90.0
A bubbled drawing shows the parts in a part print with numbered bubbles that point to individual
dimensions and requirements of the part. The numbers on the bubbled drawing correspond to the
numbers found on the Dimensional Results form.
SUPPLIER:
PART NUMBER:
PART NAME:
ITEM
DIMENSION/SPECIFICATION
SPECIFICATION /
LIMITS
MEASUREMENT
TECHNIQUE (Gage)
TEST
DATE
QTY
TESTED
OK
NOT
OK
All Part requirements on the print must be bubbled and numbered for reference and measurement, and
may include: Dimensions, electrical requirements, visual features (color, finish, etc).
The Process Flow Diagram must include all key steps of the process and include activities, such as,
Inspection, Measurement, Scrap, and disposition of Non-Conforming material.
10
FMEA #
REVISION #
DATE
APPROVED BY
POTENTIAL
FAILURE MODE
PROCESS FUNCTION
POTENTIAL
EFFECT OF
FAILURE
S
E
V
E
R
I
T
Y
ACTION RESULTS
C
L
A
S
S
POTENTIAL CAUSE
OF FAILURE
O
C
C
U
R
CURRENT PROCESS
CONTROL
D
E
T
E
C
T
RISK
PRIORITY
NUMBER
RECOMMENDED
ACTION
RESPONSIBILITY
& TARGET
COMPLETION
DATE
ACTION(S)
TAKEN
S
E
V
E
R
I
T
Y
D
E
T
E
C
T
O
C
C
U
R
RISK
PRIORITY
NUMBER
5011234
John Doe, Mary Smith, Donald Brown, Sam Jones
APPROVED BY
Sam Jones
PROCESS
FUNCTION
010
PROCESS FUNCTION
POTENTIAL
FAILURE MODE
POTENTIAL
EFFECT OF
FAILURE
S
E
V
E
R
I
T
Y
FMEA #
REVISION #
DATE
ACTION RESULTS
C
L
A
S
S
POTENTIAL CAUSE
OF FAILURE
Supplier sent
w rong material
O
C
C
U
R
020
030
machining
blanking
oversized
diameter
001
A
1/5/2013
wrong program
entered
CURRENT PROCESS
CONTROL
material certifications
w ith each shipment
D
E
T
E
C
T
RISK
PRIORITY
NUMBER
RECOMMENDED
ACTION
84
none
48
Automatic Tool
retrieval system
RESPONSIBILITY &
TARGET
COMPLETION
DATE
ACTION(S)
TAKEN
S
E
V
E
R
I
T
Y
O
C
C
U
R
D
E
T
E
C
T
RISK PRIORITY
NUMBER
improper use of
gage
operator training
out of calibration
calibration procedure
Bill White
02/28/13
tool w ear
11
Criteria
No effect on reliability or safety
Very minor, no damage, no injuries, requires only maintenance
Low damage, possible light injuries, noticed by average customer
Moderate damage, injuries possible, most customers are annoyed
Causes loss of primary function, severe damage, severe injuries
Product becomes inoperable, may result in complete unsafe operation
Rank
1
23
45
6 -7
89
10
Rank
12
34
56
78
9 - 10
Detection is an assessment that the current control in place will detect a potential cause of the failure.
Detection
Almost Certain
High/Very High
Moderately High
Low
Almost impossible
Criteria
Current control(s) almost certainly will detect the failure
Very high likelihood that current control will detect failure
Moderately high likelihood that control(s) will detect failure
Very unlikely failure will be detected with current control(s)
No known or current technology available to detect failure
Rank
1-2
34
56
7-8
9 - 10
12
Rev:
Date (Orig):
Phone #:
Date (Rev):
Fax #:
Description:
Core Team
Supplier:
Part/
Process
Machine/
Process No. Name/Operation Device/ Jig/
Description
Tools for Mfg.
Characteristics
Product
Process
Critical
to
Quality
(CTQ)
Product/
Process
Measurement
Technique
Size
Methods
Sample
Reaction Plan
Control
Frq
Part Number
Description
Supplier
Key Contact/Phone
Core Team
Date (Orig)
Date (Rev)
Part / Process No.
Process Name / Operation
Description
Enter the part number being controlled. When applicable, enter the latest engineering revision.
Enter the name and description of the part or process being controlled.
Enter name of company providing and preparing the plan.
Enter the name and phone number of the primary contact responsible for completing the control plan.
Enter the name(s) and phone number(s) of the individual(s) responsible for preparing the control plan.
Enter the date the control plan was first created.
Enter the date of the latest revision to the control plan
This item usually corresponds and is referenced from the Process Flow Chart.
Identify the process/operation name from the flow diagram that best describes the activity being addressed.
Machine/Device/Jig/Tools
for Mfg.
CHARACTERISTICS
Product
Process
Special Characteristic
For each process described, identify the equipment, e.g. machine, fixtures, or other tools for manufacturing.
METHODS
Product/Process
Spec/Tolerance
Measurement Technique
Sample Size / Frequency
Control Method
Reaction Plan
Features or properties of a part that are described on drawings or other engineering information.
Are the process variables that have a cause and effect relationship with the Product characteristic.
Are uniquely identified by Alto - Shamm on drawings (bounded by "Obround"), that may significantly affect safety,
function, fit or appearance.
Product / Process specifications and tolerances that are obtained from various engineering documents, e.g. drawings.
Describes the measurement technique being used; could include gages, fixtures, tools or other test equipment required to
When sampling is required, list the sample size and frequency.
a brief description describing how the operation will be controlled, including inspection methods, e.g. 100% inspection,
visual, etc.
Specifies the corrective actions necessary to avoid producting nonconforming product, e.g. notify supervisor, adjust and recheck, etc.
13
PART NUMBER:
PART NAME:
ITEM
DIMENSION/SPECIFICATION
SPECIFICATION /
LIMITS
MEASUREMENT
TECHNIQUE (Gage)
TEST
DATE
QTY
TESTED
OK
Any dimension failing to meet the specified requirement will be cause for an unacceptable condition.
Failure to meet the specified requirement may result in Corrective Action being identified and addressed.
14
NOT
OK
15
Part Number
Nominal Measurement
Performed By
Tolerance
MEASUREMENTS
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
NOTES
X / 10
R = Highest Lowest =
2* R = 2 *
Capability Potential
Cp = (USL LSL) / 6
=(
Cpk = (USL X ) / 3 or ( X
- LSL) /
/3
/3
) /
3 (use smallest)
OR
16
Sample #_________
UNAPPROVED
SAMPLE PPAP PARTS
NOT INTENDED FOR
PRODUCTION USE
Supplier Name______________
17