Hindustan Powerprojects To Lighten Up The Anuppur District
Hindustan Powerprojects To Lighten Up The Anuppur District
Hindustan Powerprojects To Lighten Up The Anuppur District
The Anuppur project is the among the very few projects in the country that is operating at
more than 85% of availability from the very first year of operation
Betters the industry bench mark of synchronization to commissioning to three weeks from
three months
The phase 1 commissioned at a cost of INR 8,000 crore, is now a Mega project with the
commissioning of 1200 MW
Second phase (1320 MW) of its 2520 MW Anuppur thermal project to be completed within
4 years at an invest of INR 9000 crores
New Delhi, 14 April 2016: Indias leading integrated power player, Hindustan Power, announced
successful commissioning of its Phase 1 (1,200 MW) of its flagship 2,520 MW Anuppur thermal
power project in Madhya Pradesh. The project, commissioned on 30th March 2016 at a cost of Rs
8,000 crores, is one of the first thermal plants in the country that is operating at 100% availability for
last 5 months of the financial year 2015-16. The project has direct connectivity to the National Grid
to enhance reliability, economy and minimize system losses and is situated very close to coal source
making very attractive to all stakeholders.
While commissioning the Unit 2 (600 MW) of Phase 1, the company achieved the milestone of
synchronization and coal firing in a single day and in the process the project is now a Mega project .
The company had already entered into a Power Purchase Agreement (PPA) with Madhya Pradesh
and Uttar Pradesh for 35% and 361 MW, respectively. Coal for the project is secured through a Fuel
Supply Agreement with South Eastern Coalfields Ltd. The total capacity of the flagship thermal plant
is 2520 MW to be developed in two phases of 1,200 MW (2 x 600 MW) and 1,320 MW (2 x 660 MW).
Commenting on the commissioning, Ratul Puri, Chairman, Hindustan Power, said: India is going
through a phase where a lot is being done by the Union Government of India to address the peak
power deficit by way of upward revising the Renewable energy target and taking action to address
the stress in the sector. In this scenario, commissioning of 1200 MW thermal asset is a big boost to
address the base load requirement in the country and the Governments vision to provide power to
all by 2019. As the bulk of infrastructure needs of phase 2 (2 X 660 MW) of the project has been
secured, the same should be constructed out within next four years at an investment of INR 9000
crores.
Raghav Trivedi, President Thermal - Operations, Hindustan Power, said, Considering the focus on
efficiency and achieving maximum results in the minimum time, the engineering and construction
team innovated to ensure synchronization and coal firing process was achieved was achieved in a
day. The commissioning with all the systems in place for the commercial operations was achieved
on 30th March within two weeks of the first synchronisation against three months of industry norm.
We acknowledge the passion with which both the central government and State government along
with local bureaucracy supported the project towards its commissioning.
Malika Munjal
Ph.: +91 8587084378
Email: malika.munjal@hpppl.in
Sweta Singh
Ph : +91 9717128384
Email:
sweta.singh@adfactorspr.com