T0pic Comparing The Use of Precast and C
T0pic Comparing The Use of Precast and C
T0pic Comparing The Use of Precast and C
CHAPTER ONE
1.0 INTRODUCTION
Precast and cast in-situ concretes in Ghana, since times immemorial have been facing challenges
since the inception of technology in the construction industry. Whilst this happens, people are
ignorant or overlook the advantages and disadvantages of both precast and cast in-situ concretes.
For that matter, artisans are not careful in decisions involving concrete works hence, the many
problems of concrete structures which sometimes make them choose the wrong material and
create so much economic hardship on the project. This project seeks to highlight the importance
of the advantages and disadvantage of both concrete types, so that construction personnel could
make informed choice about which concrete type is most appropriate for a particular component
of a building.
1.3 AIM
The aim of the study is to compare the use of precast and cast in-situ concretes for construction.
1.4 MAIN QUESTION
Study to compare the use of precast and cast in-situ concrete in construction industry.
1.5 SUBQUESTION
The study is limited to advantages and disadvantages of precast and cast in-situ concretes in the
building industry. The study is therefore limited to the following areas:
Curing and protection of precast concrete.
The strength and durability of precast concrete and cast in-situ concrete.
1.9 SIGNIFICANCE OF STUDY
At end of the study, the dissertation submitted would serve as a guide for any individual or group
of persons in formulating rules and regulations with regards to compare precast and cast in-situ
concrete in the construction of low-rise buildings. It will also reveal to both the employer and
client their short falls and how best they can address and solve the problems on precast and cast
in-situ concretes. Again, the study highlights on the products to be made in large quantities at
reasonable prices in boosting a companys productivity and its profit assessment. In addition, it is
important to get an open product and a construction system that will meet functional
requirement. This study further provides measures which can help employers (Contractors) to
improve upon their products standards.
1.10 LIMITATIONS OF THE STUDY
There were a lot of problems faced when the research was undertaken. These problems are;
Time constraints.
Financial constraints.
CHAPTER TWO
LITERATURE REVIEW
2.0 INTRODUCTION
This chapter describes what others have already written in relation to the topic.
2.1 PRECAST CONCRETE
According to Frederick Raina (2001), precast refers to the process of construction in which a
concrete element is cast somewhere other than where it is to be used. The other place may be
somewhere else on the building site or away from the site, probably in a casting yard or factory.
The precast element may be pre-stressed, may be of ordinary reinforced concrete, or may even
be without reinforcement. The single precast elements may be component of a general precast
concrete system, or may serve as singular purpose in a construction system of mixed materials or
types of elements. In this project, I am going to research on advantage and disadvantage of
precast and cast in-situ concrete elements and the problems encountered in designing precast
element.
Precast concrete: precast concrete framed buildings are a factory produced alternative to casting
concrete in-situ. This has several advantages in the effects of the weather. Structural
improvement using pre-stressing techniques is also possible. On site concrete production plant,
handling equipment, formwork and associated labour are unnecessary, saving considerable
construction costs.
Additionally, semi-skilled labour may be employed for the relatively simple bolted assembly.
Design flexibility is restricted to the manufacturers specifications for span, height, spacing of
units, etc. but most systems incorporate sufficient variables to comply with the relatively regular
structural form expected of this types of construction.
The most common examples of precast the structural frame is in portal construction, although
precast columns, beams, and floor sections may be applied to multi-storey building.
2.2 PRE-FABRICATION OF PRECAST CONCRETE
The application of prefabrication techniques has brought a profound change in the development
of the construction industry worldwide. Several advantages are accrued from its use including
less time and reliance on site labour, easier site inspection, as well as greatly improved design
details and quality control. Prefabrication or precast in reinforced concrete involves a shape to
the required form, in which reinforcement is placed and concrete is then cast. The essential
feature is that the same mould is used many times without any modification such casting is done
either in factory or at a fixed location on the site. The completed elements are finally transported
to the erection area.
A period in which construction activity, production etc is reduced and conditions become worse,
construction industry has been under over-stringent pressure to heighten productivity, reduce
costs and upgrades the quality levels of constructed facilities. The need to deliver what the client
demands at the right time to the specified quality and at the affordable cost is ever increasing.
The quality of prefabricated elements is usually higher than that of the constructed in-situ
component. However, their site assembly is more sensitive to poor quality control, for examples,
at the joints when connecting components. As is common to all prefabrication, most of the work
is carried out in the factory, leaving little to be done on site. This increases the likelihood of more
efficient, high quality and faster construction being achieved. As a result of the fewer tasks that
must be undertaken on site, the shorter the overall duration and the more consistent the quality. A
shorter production time not only cuts down direct and overhead costs, but also allows the house
to be occupied sooner. The capability of the suppliers to produce these building components must
closely be monitored, and only those who pass the pre-qualification test are permitted to supply
the elements for the standard public housing projects.
This pre-qualification must regularly be updated, hence incorporated in all building contracts.
Only quality assured building materials and components should be used in standard housing
blocks. Unlike the traditional methods of construction, these prefabricated components have
higher inherent quality, as well as more accurate profiles and dimensions to that fast track
construction; will not be at the expense of poor quality. Testing requirements of the products
have to be met before they are supplied. (Source: http://www.google.com)
2.2.1 PRECAST CONSTRUCTION TECHNIQUES.
In multi-storey buildings, the intersection of structural elements can be achieved in several ways.
Difficulties may involve the fitting of individual forms, the meeting and fitting of reinforcement
bars and the casting of concrete. When circumstance allows, the number of reinforcement bars
can be reduced by using bars of larger bar diameter to reduce congestion. The basic principles to
be borne in mind are as follows:
Do not connect columns at intersections. Locate the connection somewhere between the
floor levels.
do not connect facade beams at the intersection connections should be located at points
within the spans allowing the use of cantilevered section
Beams perpendicular to the facade should not terminate in the place of a column axis.
The beam end should be slightly inside in the inner faces of the columns.
2.2.2 ASSEMBLY OF ELEMENTS.
2.2.2.1 DRY ASSEMBLY
When concrete rests directly on concrete, the load is transferred mainly by the stiffer
constituents i.e. the pieces of coarse aggregate in the concrete. Dry Assembly means that no
mortar is used and therefore the joints are not water proof. Only compressive forces can be
transmitted but amount of lateral force can be resisted as a result of friction. The magnitude of
frictional resistance depends on the magnitude of the vertical load. A simple pin connection is
sometimes used. Pin is necessary for structures which include inclined elements. The points to be
noted when using pin connections are:
Avoid the use of two pins wherever possible. This trend to restrain the deformation
and to cause cracks.
Grouting may be needed to protect a steel pin from corrosion small steel projections
may sometimes be sufficient to act as pins.
(Source: http://www.google.com)
2.2.2.2 WET ASSEMBLY
Joints of cement/mortar 10-20mm thick can be used between elements to transmit compression
and certain amount of shear. A joint with lapped reinforcement bars is able to transmit both
compressive and tensile forces in addition to some shear. Temporarily, formwork is re-used while
the joint is cast. Precaution should be taken to ensure that the water in the concrete does not
evaporate causing the joint materials to suffer excessive shrinkage. One disadvantage is its
delaying effect on the construction programme. Time must always be allowed for connection to
sail its necessary strength.
(Source: http://www.google.com)
2.2.2.3 TRANSPORTATION AND ERECTION
Ambrose, J. (1991), says, considering the transportation and erection requirements for precast
units involve the following points:
Traffic regulations limit the maximum length, weight, and size of individual units.
The reach and capacity of cranes and hoists imposed separate limits.
The load capacity of Lorries and trucks determine the weight and volumes which can be
carried.
When precast units are transported by road, typical maximum dimensions could be as follows:
Height: 4 4 m.
Length: 22m.
Transporting large box units by road can cause problem. The width of the box is generally
limited to a maximum of 2.8m. In a case of housing unit, this restricts the room width of about
2.5m.
2.2.4 HOISTING AND ERECTION ON SITE
There are some mode of transport and erection as follows:
Horizontal transport only.
Rotational transport, no horizontal movement e. g. walls and columns.
Horizontal and limited vertical movement.
Vertical and limited horizontal movement.
The use of jack.
2.2.5 DESIGN CONSIDERATION IN PREFABRICATION.
According to Frederick Raina (2001), one of the problems in prefabrication is that, it easily gives
rise to monotony, especially when the units are used in repetitive series. This has lead to
negative perceptions about the design and aesthetic possibilities. To avoid monotony while
maintaining uniformity, especially in the case of box units, new architectural concepts are needed
for both the interior and the exterior. The transmission of load to the support is affected by
several criteria including the magnitude of the load, the span of the units, and the materials used
for supporting the construction for concrete to concrete connection.
When heavy reactions and large rotational forms must be accommodated, other materials like
plastic and rubber are used. Rubber bearing pads have advantages of economy and little
maintenance. Under compressive load, a rubber pad absorbs irregularities; hence every part of
the concrete surfaces helps to support the load.
2.3 PRECAST CONCRETE FLOORS
According to Osbourn Derek (1985), with modern developments in construction technology,
precast beamslab units are now available with the help of which the floors can be constructed
easily and effective without the aid of any formwork. These precast units are available in about
25cm width, various depths, and various spans and can be supported either on walls or on rolled
steel joists. The sides of each unit are provided with groves to form connecting joggles for
adjacent unit. The joints are grouted with cement mortar using concrete guns, such floors are
economical, light weight, sound proof, and fire proof.
2.4 PRECAST WALLS
According to Ambrose J. (1991), precast walls are most commonly produced by the method of
casting them in flat possible at the site. When the concrete is sufficiently strong, they are lifted
and placed in the desired position. This method is commonly described as tiltup construction,
referring to its early development, when the walls were cast immediately next to their desired
location and placed with cranes which allow them to be cast away from the actual desired
locations. Wall units may also be factorycast, but the practice is more often used and is called
architectural concrete, meaning non-structural units such as those used for curtain wall
construction. A critical concern for precast construction is the problem of transporting elements
to the building site.
Precast walls are typically of conventional reinforced construction. Their structural design in
general is subjected to the same procedures as those used for cast-in place construction. A special
concern is the provisions that are required to permit lifting and handling of the units, whether
casting is done with the wall unit in a flat position. Picking it up from this position require
development of stress conditions that are not present once the wall is in a vertical position.
2.5 PRECAST CONCRETE
With the development of precast concrete constructions techniques, the precast units like floor,
slab, beams or girders, lintels etc. are being successfully manufactured by various factories. The
precast units of the designed depths are used in the floor construction. The members are made of
such sizes as can conveniently be handled and transported. The advantages and disadvantages of
this type of construction are given as:
2.5.1 ADVANTAGES.
The construction is quick.
Its resistance to fire.
Its resistance to sound.
No time is waste for curing of the floor.
It is economical.
It has good thermal insulation properties.
It does not require formwork in construction.
2.5.2 DISADVANTAGES
It required fairly uniform spacing of beams throughout the structure which becomes
practically difficult.
In order that the precast members may be able to resist handling, stresses, great care has
to be taken in their construction and design.
There is wastage due to breakages in transportation of the members from factory to the
site of erection.
Good supervision and skilled labour is required for manufacturing the units.
The forms used for casting the units are normally costly and as such the construction is
economical only when the units are manufactured on a large scale.
permit removal of forms, etc. Erection of precast elements is more akin to construction with steel
or timber structures, and the faster site work may be an advantage where construction time is
highly constrained. However, it is total building construction time that is significant not just the
time to get up the structure. If time cannot also be gained in other parallel construction activities,
the rapidly erected structure may just sit there and wait for the other project work to catch up.
2.8.2 FORMING ECONOMICS
For the ordinary cast in place concrete structure, a major portion of the total cost is represented
by the forming. This includes the cost of the construction, bracing and support, and removal of
the formwork. Some reuse of items may be possible, but the process tends to use materials up
rapidly. Precast offers more potential for reuse of forms, even with site-cast construction. Factory
processes involve extensive reuse of forms, leading to reduction of on site labour costs.
2.8.3 QUALITY CONTROL
Precision of detail, quality and uniformity of finishes, and uniformity of concrete properties
(colour, density, compaction etc) may be assured in factory production to a degree not possible
with site casting. Here it is not just pre casting but factory conditions that are the issue. All of this
is true if the element is standard manufactured, products subject to ongoing quality control its
production. This is obviously of greatest concern for construction elements exposed to view,
especially wall components.
2.8.4 USE OF PREDESIGNED ELEMENTS AND SYSTEM
Face-it design effort means time and money. Use of standard predesigned building
construction components means a short-cut in design development effort. If the component is
part of a system, with systemwide concerns for total building utilization carefully reconsidered
and standardized the saving in design effort and the relative assurance of end results may be
quite significant.
2.8.5 UTILIZATION OF HIGH QUALITY
Concrete and pre-stressing the potential for utilization of the structural properties of very high
strength concrete usually occurs in association with pre-stressing (versus ordinary reinforcing).
Factoryproduced concrete is routinely of higher quality than the concrete produced by site
casting. In some situations, denser surfaces, lower permeability, and reduced shrinkage may also
be significant. This may be a factor in the use of mixed systems of precast and cast in place
elements.
2.9 PROBLEMS FACED WITH PRECAST CONCRETE
The following are some major concerns that may be of significance in various situations:
2.9.1 HANDLING AND TRANSPORTING
Concrete construction is usually heavy; precast elements are usually of considerable size, and the
combination presents a major problem of handling and transporting the heavy and relatively
fragile units. Stresses induced during handlings and erecting of factory cast units is usually
feasible only within some reasonable distance from the factory.
2.9.2 COST
The cost of production, handling, and transporting of precast unit is considerable. There needs to
be some considerable list of other advantages to make this form of construction generally
competitive not so much with alternative cast in place concrete, but with other materials
and systems.
In the end, the total building construction cost is most significant, not just structural cost.
.
2.9.4 INTEGRATION
It refers to the general problem of incorporating the precast concrete elements into the general
building construction. A major problem to be dealt with in this regard is the loss of some
opportunities that are present with other types of construction. Installation of hidden items such
as wiring, piping, ducts, and housings for light switches, power out less, recessed lighting
fixtures, bath room medicine cabinets, fire hose cabinets and exist signed is made some more
difficult. With light wood frames, ordinary cast in place concrete, and most other types of
construction precise locations of these items and the actual installation can be done during site
construction work. With precast concrete construction, provisions must be made in advance a
procedure that is not impossible, but that does not fit with the routine operations with which most
designers and builders are familiar.
Although structural frame of a building represents about 10% of the total construction cost, the
choice of material for the frame has dramatic consequences for subsequent processes. Until
recently cast in situ concrete was commonly viewed. As the most economic frame material, but
hybrid construction can offer greater, Speed, quality and overall economy. Although the
elemental cost of hybrid concrete Frame may be higher, total projects costs are usually lower due
to time savings on site. Faster programme mean an earlier return on investment, lower interest
charges and reduced construction preliminaries.
2.11.2 SPEED
Speed of construction depends on designs which are easy to procure and construct. Essentially
HCC takes a proportion of work away from the site and into the factory, reducing the duration of
operations critical to the building programme on site.
The precast process takes place in a controlled environment, unaffected by weather. Rigorous
inspection before installation removes cause of delay on site. Some HCC techniques can reduce
or eliminate follow on trades, e.g. installing ceilings and finishes. This enables even faster
programme times but requires greater co-ordination and care in detailing and protection on site.
2.11.3 BUILDABILITY AND CONSTRUCTION.
The key advantage of HCC is its buildability. Because precast and cast in situ Concrete are
used where most appropriate, construction becomes relatively simple and logical. The use of
HCC encourages design and construction decisions to be resolved at design stage. This means,
for example, that precast elements can be manufactured, stored at the factory and delivered just
in time to site; they can be lifted from delivery truck to final position in a single crane
movement, eliminating the need for site storage and reducing crane book time. Traditional
formwork typically accounts for 40% of cast in situ frame costs. It is dependent on weather and
labour. The use of HCC means that percentage of the frame is manufactured by a skilled
workforce in a weatherproof factory, resulting in faster construction and other better quality.
2.11.4 SAFETY.
A high proportion of the work for hybrid concrete construction is carried out in the precast
factory by experienced personnel. On site, the innovative use of HCC and the fact that
buildability is a key concern helps ensure that each safety plain is drafted on the individual
projects merits. HCC can reduce the potential for accidents by providing successive work
platforms. On a generally less cluttered site, if precast spandrel beams are used they can provide
immediate edge protection.
2.11.5 SUSTAINABILITY
HCC also offers the opportunity to exploit the inherent thermal mass of concrete by exposing the
soffit of precast concrete floor slabs. This fabric energy storage (FES) of the structure can help to
control temperatures in the context of a naturally ventilated Low energy building. The finish
and shape of expose precast concrete units can also be used to help with the even distribution of
lighting and to reduce noise levels than structured from other materials. For all buildings the
operational energy Consumption is far more significant than during Construction, but concrete
buildings utilizing thermal mass can reduce this impact on the environment by minimizing the
need for aid conditioning.
2.11.6 OTHER BENEFITS
Concrete is a uniquely versatile material. It is a cast material of high strength which can be
shaped to product a vast variety of structural elements.
Concrete structures are stable, robust, fire resistant and adaptable, as well as, solid, quiet and
essentially vibration free. The composition of concrete can be varied to produce a variety of
colour, textures and finishes, some of which closely match natural stone.
Both the structural and the aesthetic advantages of concrete can be incorporated into the design
of an HCC structure. The structural versatility of concrete can be developed with HCC. Long
spans can be achieved by using large units, or by prestressing or post tensioning. Precast units
can be also be welded together.
2.12 HYBRID CONCRETE CONSTRUCTION (can provide):
faster construction
Improved safety on site.
Cost effective construction.
Simple, buildable structures.
Excellent fire performance.
Exceptional acoustic performance.
2.12.1 ADVANTAGES
Precast quality finish for walls and soffits.
No formwork for vertical structure.
Structural connection between wall and slabs is by standard reinforced concrete detail:
inherently robust and, for basements watertight
No permanent sealing at connections between precast units.
Flexible for casting in items.
2.12.2 DISADVANTAGES
Propping of precast required prior to sufficient strength gain of in situ Concrete.
The smaller dimension of the precast units can be a maximum of 2.8m, so joints in walls and
soffits must be dealt with: expressed or concealed.
Reduced flexibility of layout as there are walls rather than columns. Proponents of this
system claim.
Twice as fast as insitu concrete.
Cost neutral compared to in situ and cheaper than full precast.
2.13 PRECAST COLUMNS AND FLOOR UNITS WITH CAST IN-SITU BEAMS.
2.13.1 Advantages:
Vertical structure can be erected quickly, no formwork required.
Precast quality finish for columns and soffits.
2.14 CAST IN -SITU COLUMNS AND BEAMS WITH PRECAST FLOOR UNITS.
2.14.1 Advantages:
Precast floor structure can be erected quickly.
Precast quality finish for soffits.
In situ can account for site irregularities.
2.14.2 Disadvantage:
Precast flooring must be temporarily propped.
Sealing between precast units is required.
2.15 CAST IN-SITU COLUMNS AND FLOOR TOPPING WITH PRECAST BEAMS
AND FLOOR UNITS.
2.15.1 Advantages:
Precast flooring can be erected quickly.
Precast beams support precast floor planks minimizing floor propping.
Precast quality finish for soffits.
Formwork for in situ columns can be used to prop precast beams.
Structural connection between precast elements is via standard reinforced Concrete.
In situ topping to beam permits beams to be continuous over columns.
2.15.2 Disadvantage
Down stand beams need to be co-ordinate with services distribution.
Hybrid Concrete
Was also used to create a structure which allows full continuity to occur between the vertical and
horizontal structural elements, thus providing a stiff away framework. The combination of
elements allowed the whole frame to act as a composite structure without relying on expensive
mechanical fixings. This method of construction produces a rigid frame which is inherently
stable without the need for shear walls or bracing. HCC was the natural choice of material. It
fulfilled the design criteria for a visible expression of the structure; behind the delicate glazed
facades the precast column and beam structure is clearly visible, needing no further treatment
such as cladding for fire protection. In addition, by exposing the painted soffits of the concrete
floor slabs in the offices, the ventilation strategy could exploit the fabric energy storage potential
of the concrete construction.
The hybrid concrete structure consists of 430 mm diameter precast columns and precast floor
units connected together by means of cast in situ concrete spine beams.
Each floor unit takes the form of a double T section with end plates to each trough. At each
column connection the end plates are cast with a curved cut out to follow part of the column
profile.
Once the precast columns were fixed on site, the double T- section floor units were connected to
the, positioned so that the curved edge profiles trimmed the outer edge of the columns. The cast
in situ concrete spine beam was then cast between two rows of end plates stitching lower and
upper columns and adjacent units together. Between the longitudinal joints, loop connectors were
cast in to the units and continuous cast in situ beam join the units together. The floor units are
self finished and no screed or topping was required.
At the perimeter the same principle was used with a slightly different detail. The spine edge
beam was cast between the final rows of end plates (which ran up to the inner side of each
perimeter column) on one side and a special precast perimeter unit on the other side, which
creates a tapered edge to the ceiling soffits. The perimeter unit has a row of precast holes which
allow warm buoyant air rising up the faade to be effectively captured and cooled by the passive
chilled beam elements above return air paths to the central atrium. The precast perimeter units
were cast with a sculpted feature where they meet the column head. They were also used at the
atrium and core perimeters cast in the same moulds with minor adaptations. (Source:
http://www.pdf-search-engine.com)
2.16 WHAT MAKES PRECAST CONCRETE DIFFERENT FROM OTHER FORMS OF
CONCRETE CONSTRUCTION
The most obvious definition for precast concrete is that it is concrete which has been prepared
for casting, cast and cured in a location which is not its final destination. The distance travelled
from the casting site may only be a few meters, where on site pre casting methods are used to
avoid expensive haulage, or may be thousands of kilometers, in the case of high value added
products.
This is capable of splitting both elements unless the section is suitably reinforced. Flexural
rotations of the suspended element reduces the mating length ( bearing length) creating a stress
concentration until local crushing at the top of the pillar (the column) occurs, unless a bearing
pad is used to prevent the stress concentration forming if the bearing is narrow, dispersal of
stress from the interior to the exterior of the pillar causes lateral tensile strain, leading to bursting
of the concrete at some distance below the bearing unless the section is suitable reinforced.
Source: Emmitt Stephen and Gorse Christopher (2005).
2.17 PRECAST CONCRETE STRUCTURES.
A precast concrete structure is an assemblage of precast elements which, when suitably
connected together, form a 3D framework capable of resisting gravitation and wind (or even
earthquake) loads. The framework is ideally suited to buildings such as offices, retail units, car
parks, schools, stadia and other such buildings requiring minimal internal obstruction and multifunctional leasable space. The quantity of concrete in a precast framework is less than 4 percent
of the gross volume of the building, and of this is in the floors. The precast concrete elements are
columns, beams, floor slabs, staircases and diagonal bracing.
Source: Frederick Raina (2001)
2.18 CAST-IN PLACE CONCRETE
Most concretes for buildings are cast-in-place, that is, the wet mix is deposited and formed at the
place where the finished concrete is desired. This is now general referred to as site cast concrete,
since the location is usually at a building site. This is compared to precast concrete, which refers
to the process of casting elements and then moving them to the place they are to be used.
Concrete for site cast construction is typically brought to the site by the familiar concrete
transporting mixer trucks with the large rotating barrels. The mix is prepared at a central
batching plant, where controls of the materials may be carefully monitored. However, the
transporting to the site, proper mixing in truck, discharging from the truck and depositing in the
forms, and handling for placement, finishing, and curing are all subject to the level of
responsibility and craft exercised by the people involved. Site conditions in terms of accessibility
and weather can be highly critical to the work, requiring extreme measure in some situations to
control all the stages in the production process. This research is not about construction processes
or their management, but some awareness of the issues and limitations is helpful in developing
reasonable designs for concrete structures to control all the stages in the production process.
Source: Frederick Raina (2001)
introduces the possibility of excessive deflections. Sometimes the side forms of beams are
removed before the bottom forms. When this is done, posts or shoring are placed under the
bottoms of the members to give additional support. This is called reposting or restoring. The
minimum period during which forms must remain in place before stripping is usually governed
by the local building code. (Source: http://www.pdf-search-engine.com)
2.20 PLACING AND FINISHING.
As soon as cement is mixed with water, a chemical action begins that eventually results in the
hardening of the concrete. The first stage of this is the wet mix, which has the character of at
thick, viscous fluid. In a short time, however, an initial hardening (called set) occurs, and the
fluid nature of the mix fades. Before the initial set occurs, the concrete must be fully placed in
the forms a matter of only a few hours with ordinary mixes. Add up the time for loading the
trucks at the batching plant, driving the trucks to the site, emptying the trucks and moving the
mixed concrete to its desired location, and hand ling it to fill the forms and there is not much
time for leisure in the operation.
Despite the haste required, the wet concrete must be carefully handled so as not to cause
segregation, which consists of the partial separation of the ingredients. This can occur if the
concrete sits idly in its wet state, is dropped too far when deposited, or is moved around too
much in the forms before settling into place. This is a situation for careful supervision, but is
mostly up to the skills and care of the workers involved.
Surfaces of the concrete in contact with forms will derive a primary form and finish from the
surfaces of the forms. Unformed surfaces (usually the top) may receive various treatments, the
simplest being a simple struck surface, produced by smoothing with a board or rough wood tool.
This is essentially an unfinished surface, which may be additionally treated during the initial
hardening or later. (Source: http://www.google.com)
2.21 CURING AND PROTECTION
Curing is the method of keeping concrete units damp to prevent excessive drying.
Regardless of the care taken in proportioning , mixing, and placing, first- quality concrete can be
obtained only when due consideration and provision are made for curing. The hardening of
concrete is due to the chemical reaction between the water and cement. This hardening continues
indefinitely as moisture is present and the temperatures are favorable. The initial set does not
begin until two or three hours after the concrete has been mixed.
Moisture conditions can be maintained by spreading wet coverings of mats, waterproof paper or
plastic sheets over concrete, by spraying liquid curing compound on the surface of fresh
concrete, and by leaving the concrete in forms longer.
Ramsey and Sleeper (1984), identifies two physical conditions which profoundly affect the final
compressive strength and curing of concrete: the temperature and the rate at which water used
in mixing is allowed to leave the concrete
The optimum temperature for curing concrete is 22.8 . Any great variance from this mark
reduces its compressive strength.
In situ is most commonly a mixture of aggregate (known as builders mix) blended with
cement and clean water that is free of oils, acid etc.
According to Denis Walton (1995), cement is a combination of limestone and silica, which is
found in some types of clay. Alumina, iron oxide and magnesia are present in small quantities.
Cement is stored in a dry place such as small lockable shed.
In Willington it is sourced from quarries aggregate meanwhile is not commonly sand, gravel and
crushed stone and constitutes along the Western Hutt hills and in Hgaurange, where Greywacke
(sandstone) and argillite (mudstone) are sorted as aggregates and coarse sand before being
blended as builders mix.
2.23.1 WHERE MATERIALS ARE FOUND:
Lime: Lime is found throughout New Zealand, high quality lime from Te Kuiti and Nelson is
processed for export. A crystallized form of lime is mined in Nelson. It is used as filler and in
building construction.
Silica: Also a form of sand, found in Northland, North Auckland and Canterbury
Alumina: is extracted from cola ash and oil deposits.
Gypsum: Gypsum has been buried by the accumulation of slit and dust millions of years ago.
There is no gypsum in New Zealand, we import ours from Australia
2.24 MATERIAL PROPERTIES
In-situ concrete is strong, durable, stable, readily available and relatively economic in terms of
construction and life time maintenance. It is the ideal structural material in building sites that
have difficult access.
Other qualities that make it an ideal construction medium include:
The ability to control form and shape.
The enclosure of space and structure in one material.
The ability to form integral surface finishes.
Its compatibility with most other materials.
And excellent acoustic and fire resistant properties.
Also admixtures and other materials can be added to serve various functions ranging from freeze
proofing to creating translucency. It should be noted that the quality of such constituents has a
considerable effect on material properties.
Formwork
Is also a popular medium in which to shape, or mould a desired surface in order to create a
patterned or stamped finish. Rough timber boxing for instance will leave an imprint on your
finished surface. Brushing the concrete while curing the other options, while glass embedded in
the concrete itself will give the material a translucent quality.
Different concrete finishes can be achieved by:
Abrasive processes.
Chemical processes.
Mechanical processes.
Combination processes.
Colour
Is another way in which to alter finish. Coloured concrete is achieved by mixing a powered or
liquid pigment into the concrete at the time of batching. This has the advantage of providing a
consistent colour finish. For example Liquid Colour is a high solid liquid oxide dispersant,
produced from synthetic iron oxides available, which is normally added to ready mixed concrete
at a rate 5 % of the cement content in the mix.
Spray Concrete
Differs from conventional cast in place concrete with regard to the reinforcement and
application method and surface, resulting in a considerable range of
finishes. Spray concretes flexibility in applied with compressed air added at the nozzle via a
separate hose. (Source: http://www.pdf-search-engine.com)
It should also be noted that, admixtures (any substance that is added before or during the mixing
of the concrete) can act to reduce or augment the potential strength of the concrete mix. Long
term durability is compromised if the mixing, pouring, compacting and curing are not handled
carefully.