De La Cruz v. Meralco Case
De La Cruz v. Meralco Case
De La Cruz v. Meralco Case
20,
2011
DECISION
CRUZ, S. C., J.:
This treats of a Petition for Writ of Kalikasan (with prayer for the
issuance of a temporary environmental protection order) filed by
Gemma C. Dela Cruz, et al. (hereafter petitioners) against Manila
Electric Company et al., (hereafter respondents) under Rule 7 of
Administrative Matter No. 09-6-8-SC otherwise known as The Rules
of Procedure for Environmental Cases1 following the installation
and
subsequent energization of low-frequency power lines of the Manila
Electric Company (hereafter MERALCO) along 10th, 12th and
27th
Streets of Barangay 183, Zone 20, Pasay City and in certain areas
in
Magallanes Village in Makati City.
Petitioners aver that on July 13, 2009, Cesar Toledanes,
(hereafter Toledanes) the Chairman of Barangay 183, issued a
Working Permit Clearance2 in favor of MERALCO for the installation
of poles and 115 kilovolts (KV) sub-transmission lines along 10 th
and
12th Streets of the barangay without prior approval of and
authority
from the Barangay Council or consultation with the residents of the
Barangay.
Belatedly, on September 2, 2009, the Barangay Council
composed of Toledanes, Ruth Cortez, Ricardo Dimaano, Leonardo
Abad, Normita Castillo and Amante Cacho issued Barangay
Resolution No. 40-S-20093 authorizing Toledanes to issue a permit
in
favor of MERALCO to install high voltage power lines and poles
along
10th and 12th Streets of Barangay 183. Pursuant thereto,
MERALCO
began constructing posts along the foregoing streets including the
27th. The thirty-foot high poles hold transmission lines that supply
approximately one hundred fifteen (115) KV of electricity to the
Ninoy
Aquino International Airport III (NAIA 3). Unfortunately, none of the
respondents informed the residents of the proposed installation of
sub-transmission lines. Hence, they were surprised to see
MERALCO
putting up power lines that pass along the perimeter concrete wall
between Barangay 183 and Magallanes Village.
Fearful of their safety, petitioner Gemma Dela Cruz, on behalf
of the other petitioners, appealed to the members of the Barangay
Council to recall the Barangay Working Permit and Resolution No.
40-S-2009 issued in favor of MERALCO. Unheeded, petitioners now
seek the intervention of this Tribunal via Petition for Writ of
Kalikasan
to protect the affected residents from the alleged health risks (e.g.,
cancer, leukemia in children, Alzheimer's disease, headaches and
miscarriages to name a few) of the high-tension wires erected
within
close proximity from their houses.
For its part, MERALCO avers that the supply of electricity to
NAIA 3 was one of its major projects in Pasay City whose full and
efficient operation requires the installation of a power substation
and
115 KV sub-transmission lines in several areas in Metro Manila, one
of which is Barangay 183 in Pasay City. On July 27, 2000, Reynaldo
Gobaton, the Chairperson of Barangay 183, issued a certification 4
stating that he understood the implications of the development of
the
NAIA substation on the surrounding areas and that his constituents
had no objections thereto. Respondent also secured another
certification5 from the barangay in which the latter assured
MERALCO that none of its sectors and leaders have objections to
the
installation of MERALCO's substation, its power transmission lines
and distribution system in their area.
After finally deciding on 10th, 12th and 27th Streets in Barangay
183, (i.e., The first options were Sales Street and Andrew Avenue
which were disapproved, respectively, by the Philippine Air Force
and
the Department of Public Works and Highways) MERALCO
conducted a series of public meetings and consultations with the
affected residents of the Barangay in which it explained the NAIA 3
project while addressing concerns about the residents' health and
safety. Thereafter, respondent proceeded to secure the necessary
permits and compliance certificates6 for the construction and
installation of the 115 KV sub-transmission lines along the
foregoing
thoroughfares.
However, the operations were momentarily stopped on
September 15, 2009 due to the opposition of some residents of
Barangay 183. It resumed on November 23, 2009 but was
suspended
anew following the issuance of a cease-and-desist order dated
December 3, 2009 by the Office of the City Engineer of Pasay City.
On December 4, 2009, on the same day that the parties were
heard in the Office of the City Mayor of Pasay City, a group of
residents of Barangay 183 filed a case of preliminary injunction
and/or mandatory injunction with prayer for a temporary
restraining
order (TRO) before the Regional Trial Court (RTC) of Pasay City,
docketed as SCA No. 09-02222 7 entitled Evangeline M. Biocarles,
et
al., vs. Manila Electric Company, et al. The action prayed for the
following reliefs: (a) the suspension of the construction and
installation of the 115 KV sub-transmission lines along 10 th and
12th
Streets in Barangay 183; (b) the nullification of the Barangay
Working
Permit Clearance and the Barangay Resolution No. 40-S-2009; and
(c) the nullification of the permit issued by the Office of the City
Engineer of Pasay City. Without, however, issuing a TRO, the RTC
rendered the prayer for injunctive relief moot and academic.
Amidst the denial of the motion, the residents of Barangay 183
instituted the present action of Writ of Kalikasan pursuant to A.M.
No.
09-6-8-SC (Rules of Procedure for Environmental Cases) against
MIAA, MERALCO and the members of the Barangay Council of
Barangay 183.
To this, respondent MERALCO counters that the petition is
dismissible on three (3) specific grounds: First, petitioners' right to
health, which is why they sought the protective writ for, is not
within
the ambit of the Writ of Kalikasan. According to MERALCO, the
central purpose of the Writ is the protection and advancement of
the
Constitutional right of the people to a balanced and healthful
ecology whereas the petitioners are asking for the protection of
their
individual
was later lifted via an injunction order14 from the RTC of Pasay City
dated July 23, 2010. In compliance thereto, MERALCO commenced
and actually completed the installation of the 115 KV lines.
Meanwhile, the MIAA filed a separate petition for injunction
before the RTC of Pasay, docketed as SCA No. R-PSY-10-03913CV15 entitled MIAA vs. The City Government of Pasay, et al.,
seeking to lift the cease and desist order against MIAA and allow
MERALCO to continue installing its poles and sub-transmission lines
around Barangay 183. On July 23, 2010, the RTC acted favorably on
the petition and granted the issuance of the writ that lifted the
questioned cease and desist order. City Government of Pasay City
forthwith moved for the dissolution of the writ but was instantly
denied
on September 17, 2010.
xxxxxxxxx
(c) The environmental law, rule or regulation violated or
threatened to be violated, the act or omission complained of, and
the environmental damage of such magnitude as to prejudice the
life, health or property of inhabitants in two or more cities or
provinces.21
In addition to Section 2, Section 1, Rule 7 of the Rules requires
that there be a violation or, at least, a threatened violation of
the
people's constitutional right to a balanced and healthful ecology by
an unlawful act or omission of a public official or employee, or
private
individual or entity which involves an environmental damage of
such magnitude as to prejudice the life, health or property of
inhabitants in two or more cities or provinces. [emphasis
supplied]
There is no mistaking the scope of the law. The Writ of
Kalikasan should not be confused for anything but as an aim at
preventing or stopping unlawful acts (i.e., one that threatens or
violates the people's right to a balanced and healthful ecology)
that
upset the environment which, in effect, results in the violation of
the
people's right to a balanced and healthful ecology. It relates
primarily
to the protection of the environment under the precept that the
destruction of the environment redounds to the destruction of the
people's life, property and/or health. 22 This is better explained in
the
Rationale
of
the
Rules
which,
in
part,
states
that:
The discipline of ecology is based on the interconnectivity
and interdependence between organisms and the elements of the
environment. An appreciation of this link between all elements of
living things and nature would naturally instill a sense of urgency
to
protect
our
ecosystems.
Without
such
protection,
the
endangerment of the ecosystems would correlate to the
endangerment of humankind. Conversely, its protection would
benefit man and his ability to survive and sustain in the world.
Still, on the basis thereof, this Tribunal cannot rule out the fact
that apart from the environment, health risk is likewise one of the
ills
sought to be prevented by the writ. However, health per se or the
right thereto cannot be sought independently of the environmental
damage brought upon by the unlawful act. Section 1, Rule 7 of the
Rules is clear enough on this. The threat to health must emerge as
a
consequence or offshoot of the magnitude of the environmental
damage which the writ seeks to prevent and, in other cases, put an
end to it. Elsewise stated, petitioners cannot claim health risks
without display or proof of the environmental damage or threat
which
supposedly resulted from the activation of the subject
subtransmission lines. The former simply cannot stand in the
absence
of
the other.
Hence, to prosper, the petition must, at least, contain the
following allegations: (1 ) the environmental law, rule or statute
being
violated; (2) the threat or violation of one's constitutional right to a
balanced and healthful ecology; and (3) the corresponding
environmental damage that threatens or prejudices the life, health
or
property of those affected.
A reading of the petition shows that it made a decent enough a
specification of the first two requisites. Briefly, the petition asserts
that the installation and activation of MERALCO's sub-transmission
lines run afoul with Article 2, Section 15 of the Constitution on the
people's right to health. The petition further alleges that
MERALCO's
project is at loggerheads with Presidential Decree No. 856,
otherwise
known as The Code of Sanitation of the Philippines, specifically
7.3.1. of the Implementing Rules. The foregoing provision prohibits
the setting up of high-tension transmission lines over or
underneath
residential areas. Lastly, the petition states that MERALCO's posts
obstruct drainage systems of Barangay 183, in violation of Section
223 of Commonwealth Act 548 or the Regulation and Control of the
Use of and Traffic on National Roads and Constructions.
However, the petition fell short of asserting nay demonstrating
the environmental damage or the threat thereof, as the case may
be,
which the construction, installation, energization and/or activation
of
MERALCO's power lines have brought upon on the residents of
Barangay 183 and Magallanes Village. The action clearly centers
almost exclusively on the assertion that MERALCO's transmission
cables, when activated, may cause insurmountable health
problems,
foremost of which is leukemia among children, 24 without
establishing
the initial relation between the diseases feared and, if any, the
impairment of the environment resulting from MERALCO's actions.
There is admittedly a glaring absence of any allegation directed
against violations of petitioners' right to a balanced and healthful
ecology (or the right to health, as insisted by petitioners) and the
purported environmental damage arising from the installation and
energization
of
MERALCO's
sub-transmission
lines.
25
Such inadequacy may be deemed fatal to petitioners' cause,
more so in this case wherein the allegation of the environmental
damage is a vital component of the action. The Rules themselves,
specifically Section 2, Rule 7 thereof require its inclusion in the
petition. Furthermore, the provision used the word shall in
reference
to the inclusion of the statement pertaining to the damage to the
environment. In construction, the term shall is often considered a
word of command. 26 As such, failure of the petitioners to state the
environmental damage supposedly caused by MERALCO naturally
redounds to the dismissal of the case. It is settled view that a
complaint or petition should contain a plain, concise and direct
statement of the ultimate facts on which the party pleading relies
for
his claim or defense. 27 A fact is essential if it cannot be stricken
out
without leaving the statement of the cause of action inadequate.
28
The fact in question is without doubt an indispensable feature in an
action for Writ of Kalikasan such that the absence thereof renders
the
entire petition decidedly crippled.
With respect to the SECOND issue, petitioners believe and so
argue that MERALCO's high-tension wires emit an electromagnetic
field which causes leukemia in children. Invoking a study
conducted
results
as
to which part of the EMFs, if any, is toxic or important or could be
hazardous to [anyone's] health. 34 In fine, the studies (given that
the
sources of the article actually exist) mentioned in this article have
not
established on a scientific level the causation between EMF and the
diseases
commonly
associated
with
its
exposure.
The same is true for other studies herein presented by
petitioners. The study conducted by A. Ahlbom et al entitled A
Pooled Analysis of Magnetic Fields and Childhood Leukemia
published in 2000 is largely observational, with nary a scientific
explanation or illustration as to how EMF may provoke
physiological
imbalance among children thereby increasing the risk of
contracting
leukemia. The study does not even answer why EMF seems to
stimulate or heighten only the risk of leukemia in children. Hence,
the
uncertainty
of
their
findings:
We did not find any evidence of an increased risk of
childhood leukemia at residential magnetic field levels < 0.4 uT. We
did, however, find a statistically significant relative risk estimate of
two for childhood leukemia in children with residential exposure to
EMF > 0.4 uT during the year prior to diagnosis. Less than 1% of
the subjects were in the highest exposure category.
At best, the data gathered are purely statistical in nature with
no scientific evidence or conclusion as to whether the leukemia
suffered by the subjects had been caused initially by their exposure
to EMF-ELF or the direct impression of some other factor,
environmental or otherwise. Interestingly and rather ironically the
same study reveals an entirely antithetical result from parallel
experiments conducted in laboratories. Thus:
The results of numerous animal experiments and laboratory
studies examining biological effects of magnetic fields have
produced no evidence to support an aetiologic tole of magnetic
fields in leukaemogenesis (Portier and Wolfe, 1998). Four lifetime
exposure experiments have produced no evidence that magnetic
fields, even at exposure levels as high as 2000 uT, are involved in
the development of lymphopoietic malignancies. Several rodent
experiments designed to detect promotional effects of magnetic
fields on the incidence of leukaemia or lymphoma have also been
uniformly negative.
as
yet unknown. Additionally, animal studies have been largely
negative.
Thus, on balance, the evidence related to childhood leukaemia
is not strong enough to be considered causal. 42 As such, the fear
of contracting cancer and other related diseases (as emphasized
by
the petitioners) is entirely devoid of scientific basis. [emphasis
supplied]
In the meantime, while more studies are being conducted on
the subject, the WHO, through the International Commission on
NonIonizing Radiation Protection (ICNIRP) has set the standard for
or
level of exposure to ELF to 100 kHz to 300 GHz43 to which many
countries subscribe including the Philippines. 44 Thus, under
Administrative Order No. 033-0745 which, incidentally supersedes
the
Implementing Rules of the Sanitation Code, 46 the general public
exposure to time-varying electric and magnetic fields should not
exceed 83.33 micoTesla (uT) or 833 milliGauss (mG). It is
established - as no counter argument is being submitted to
contradict
the same - that the maximum EMF-ELF emission from MERALCO's
power lines as examined by the DOH itself does not exceed
16.7mG, way below the acceptable limits set forth under the law.
Thus,
in
view of MERALCO's compliance to ICNIRP and DOH standards, the
latter refused to recommend the suspension of the NAIA project
solely
on
the
basis
of
adverse
health
effects.
47
It is likewise important to note that in contrast to what was
earlier alleged by petitioners, MERALCO complied with other
standards as mandated under existing laws as evidenced by the
numerous clearances48 obtained thereby from pertinent
government
offices, foremost of which is the Environmental Compliance
Certificate49 issued by the Department of Environment and
Natural
Resources (DENR). This can only mean that MERALCO has taken
the necessary environmental precaution to avoid damaging the
immediate environs.
Also,
MERALCO
has
met
the
height
and
distance
requirements50 under The Philippine Electrical Code. A perusal of
the
photographic evidence51 shows that the horizontal clearance (i.e.,
distance of the electrical wire from the building) followed by
MERALCO in erecting its electric posts is approximately three (3)
meters which is far wider or longer than that which is required by
the
Code, i.e., 2.87 meters. 52 The same is true with respect to the
vertical
clearance (i.e., distance of the electrical wires from ground or
structural level directly below it). The Code requires height levels of
electrical wires to be 22.6 meters while those of MERALCO are
between 90 feet and 105 feet. The petitioners, however, challenge
the veracity thereof by alleging that the wires are strung too close
to
the houses while the posts tilted dangerously on the direction of
the
houses and obstructed the drainage system of Barangay 183. 53
Petitioners, however, failed to adduce an iota of evidence to
buttress
such claims. In fact, during the preliminary conference, petitioners
could not state with certainty the distance of the electrical wire
from the house of one of the petitioners, 54 let alone show the
alleged
tilting
of the posts or the consequent damage to the drainage system.
At this point, We emphasize that MERALCO's operation is not
illegal or unlawful to begin with. It must be remembered that the
Rules require the act that threatens or violates the people's right to
a
balanced and healthful ecology to be unlawful. 55 The Webster's
New
World Legal Dictionary56 defines unlawful act as behavior that
is
not authorized by law or the commission of or participation in an
activity that violates criminal or civil law. The construction of the
poles and the energization of the sub-transmission lines are far
from
unauthorized or unlawful. In fact, they are more of a necessity than
anything else. Without adequate power supply, NAIA Terminal 3 will
cease to operate which translates to disruption of hundreds of
flights
everyday, bringing in not just revenue losses in catastrophic
proportions but also insurmountable inconvenience to passengers
whose appointments and, sometimes, livelihood depend on the
timely
transmission
lines, has complied with minimum standards set forth under
existing
environmental laws. Unless, so revised and or revoked, these
certificates of compliance shall remain a source of authority to
operate by respondent MERALCO.
As such, no bases may be culled from any of petitioners'
evidence to warrant the issuance of a Writ of Kalikasan. It has been
the established rule in evidence that each party must prove his
affirmative allegations. 62 In the instance before Us, the burden of
proof lies with petitioners. In failing to prove the causal link
between
the illnesses feared and the EMF generating from MERALCO's
power lines, petitioners have, in fact, failed to discharge this
evidentiary burden. We cannot simply rely on or invoke the
precautionary principle as mandated under Section 1, Rule 20 of
the Rules to uphold the averments of the petitioners. The latter
provision states:
Section 1. Applicability. - When there is a lack of full
scientific certainty in establishing a causal link between human
activity and environmental effect, the court shall apply the
N.
DIAMANTE