Product Sprint Backlog
Product Sprint Backlog
Product Sprint Backlog
Incr.
1
2
Start
13.6.2006
25.7.2006
Days
42
42
End
24.7.2006
4.9.2006
Size
19
0
Status
Release Date
Template note: Increment plan is intended to collect individual sprints into larger releases. In smaller projects, this is not ne
Sprint Plan
Sprint
1
2
3
4
5
6
Start
6/13/2006
6/27/2006
7/11/2006
7/25/2006
8/8/2006
8/22/2006
Days
14
14
14
14
14
14
End
6/26/2006
7/10/2006
7/24/2006
8/7/2006
8/21/2006
9/4/2006
Unallocated stories
Size
8
3
8
0
0
0
-5
Status
Release Date
Planned
Planned
Planned
Planned
Planned
Planned
Unplanned
Unplanned
Unplanned
Unplanned
Unplanned
Unplanned
Unplanned
Unplanned
Unplanned
Goal
Goal
Planning
Specification and prototype development
Specification and prototype development
Specification and prototype development
Specification and prototype development, documentation
Usability test, documentation, prototype corrections
Increment
1
1
1
2
2
2
Product Backlog
Story ID Story name
1
This is a sample story
2
This is another sample story
3
4
5
6
Status
Done
Ongoing
Size
3
5
Sprint
1
1
Planned
Planned
Planned
Removed
3
8
13
5
2
3
Priority Comments
You can add comments here to add key detail or
explanation to the story. For larger definitions,
use external tools and materials.
137
3 sprints
30
25.0
25.0
25.0
25.0
25.0
12
10
Development Ve
12
10
Sprint
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
Remain.
Work
137
114
87
56
28
Planned
Work
23
29
31
28
28
Realized
Work
23
27
Current Total
Size
137
137
137
137
137
Planned Speed
Average Realized
Note:
In this chart, the tops of the bars show the amount of actual
(or planned) implemented functionality at the beginning of each sp
The bottoms of the bars show the changes in project scope
(i.e. if the amount of story points
in the project increases, the bottoms move lower). The length
of the bars indicate the estimated size of the project at the
beginning of each sprint.
The red line indicates the current planned scope.
Development Velocity
Planned Speed
Realized Speed
Average Realized
Avg. Last 8
t planned scope.
Daily Progress
Ideal Progress
Current Trend
35
Sprint 1 Backlog
30
25
20
15
10
5
0
5
5
Story ID
1
1
2
2
Days
Responsible
Danny Dev
Tina Tester
Danny Dev
Totals
Status
Done
Ongoing
Ongoing
Planned
Effort Remaining on im
33
33
Est.
1
5
5
7
7
12
12
9
9
35
30
25
20
15
10
5
0
Sprint 1 Backlog
Ideal Progress
Current Trend
Daily Progress
0.9
0.8
0.7
0.6
0.5
0.4
0.3
0.2
0.1
0
5
5
Days
Story ID Responsible
Totals
Status
.9
.8
.7
.6
.5
.4
.3
.2
.1
0
Story ID:
Task:
1
Story:
Example task
Story ID:
Task:
1
Story:
Example task 2
Work
Left
Story ID:
Task:
2
Story:
Example task 3
Work
Left
Story ID:
Task:
Work
Left
2
Story:
This is another sample story
<Delete these example lines>
Responsible Person:
Initial
Work
9
Estimate
Done
Work
Left