Process Overview Lesson Text
Process Overview Lesson Text
Document No.:
P11-X01-QTOPSGEN-001
Revision No.: 0
Process Overview
Lesson Text
Date: 06/24/16
ORIENTATION
PROCESS
OVERVIEW
LESSON TEXT
INTRODUCTION
Ras Laffan Liquefied Natural Gas Company Ltd.
Page 1 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
This manual is an overview of the RasGas LNG Project, the main emphasis
being placed on the Onshore Process Facilities. The manual has been
produced to give an introduction to Qatar, Ras Laffan Liquefied Natural Gas
Company and the overall LNG project. All Production and Process facilities are
covered in greater detail in later manuals.
The material has been produced as an aid to training and its use is limited to
that purpose. The document does not supersede RasGas Operating Manuals
and Procedures, Standing Instructions or Safety Procedures.
2
SHAREHOLDERS
The company was established in June 1993 as a joint venture between
Qatar General Petroleum Company (QGPC) and Mobil Corporation.
However, an agreement in principle was reached in December 1996 for
two Japanese Companies, Itochu Corporation and Nissho Iwai
Corporation, to acquire minor interests in the project. Negotiations for
the final agreement are now at an advanced stage and it is expected
that a Korean consortium will acquire an interest in the project.
63%
MOBIL
25%
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 2 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
KOREAN CONSORTIUM
5%
ITOCHU CORP.
4%
NISSHO IWAI
3%
QGPC
QGPC was established as a state owned corporation in 1974. It is
responsible for all aspects of the Qatar oil and gas industries. QGPC is
the sole owner of the North Field Phase 1 development, which supplies
local demand for gas and feedstock. QGPC is also the major
shareholder in Qatars first LNG producer Qatargas, which is also
situated at Ras Laffan and produced its first shipment of LNG in January
1997.
MOBIL
MOBIL is one of the major oil companies in the world. It is also a major
shareholder in Qatargas. MOBIL also has considerable experience in
the development of LNG plants in other countries, notably PT Arun in
Indonesia.
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 3 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
QGPC
63%
MOBIL
25%
NISSHO
IWAI
3%
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 4 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
ITOCHU
CORP.
4%
KOREAN
CONSORTIUM
5%
PROJECT BACKGROUND
RasGas drilled and tested a well in 1994, the results of which verified
gas quality, well deliverability and gas reserves of the Companys
development area in the Qatar North Field.
In October 1995, RasGas signed a Sales and Purchase Agreement with
Korea QTOPS
Gas Corporation of South Korea for 2.4 million tons per year of
Ras Laffan Liquefied Natural Gas
Page 5 of 77
Company Limited
ORIENTATION
Date: 06/24/16
Rev: 0
LNG. Then in June 1997 the agreement was increased to 4.8 million
tons per year of LNG. The first delivery is scheduled for July 1999.
The Engineering, Procurement and Construction (EPC) Contracts were
awarded in early 1996. The EPC Contract for the offshore platforms
was awarded to the joint venture of Mc Dermott-ETPM East Inc. and
Chiyoda Corporation, and Saipem, SpA will be responsible for the
subsea pipeline work. The EPC contract for the onshore facilities was
awarded to the joint venture of Japan Gas Corporation (JGC) and the M
W Kellogg Company.
2.1.4
OVERALL PROJECT
The RasGas LNG plant is situated at Ras Laffan, Qatars new industrial
development complex approximately 90 km north of Doha.
The offshore complex includes a process and utilities platform,
accommodation platform, riser platform, three wellhead platforms,
bridge support platform and flare tower. The riser platform contains;
infield flowlines from remote wellhead platforms and a 32 inch twophase gas-condensate pipeline to shore.
The onshore LNG plant consists of two parallel trains each capable of
producing 2.6 MTPA (Million Tons Per Annum) of LNG and 45,000
bbls/day of condensate.
The receiving facilities consists of process and utilities area that
include a slug catcher and condensate stabilisation unit complete with
flaring systems.
The plant also includes storage and loading facilities. RasGas will have
dedicated loading facilities at the Ras Laffan Port which is operated by
QGPC. A fleet of LNG carriers will deliver the LNG to Korea Gas
Corporation.
The plant is completely self-supporting and is designed for easy
expansion to six LNG trains, depending on market demand.
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 6 of 77
ORIENTATION
Date: 06/24/16
2 T r a in O p e r a tio n
1 .0 B C F /D G a s
4 5 ,0 0 0 B B L /D C o n d e n s a te
Rev: 0
OFFSHO RE
F A C IL IT IE S
O FFSHO RE
U n tre a te d G a s
In le t
F a c ilitie s
ONSHORE
F ie ld
C o n d e n s a te
C o n d e n s a te
T r e a tin g /
S ta b ilis a tio n
G a s T re a tin g
H 2S
A c id G a s
R em oval
A c id G a s
E n ric h m e n t
S u lp h u r
R e c o v e ry
Sweet G as
D e h y d r a tio n
M o lte n
S u lp h u r
S to ra g e &
L o a d in g
D ry G a s
C
R e f r ig e r a tio n
P re p a ra tio n
G a s C h illin g &
L iq u e f a c tio n
& M R
R e f.
M a k e -u p
R e f r ig e r a tio n
R e f.
C2 & C3
R e je c tio n
C o n d e n s a te
R e f r ig e r a tio n
M a k e -u p &
S to ra g e
3 6 6 M T /H
2 3 ,0 0 0 B B L /D
S o lid
S u lp h u r
1 5 5 T /D
ONPLOT
O FFPLOT
C5
LN G R undown
S to ra g e &
L o a d in g
C o n d e n s a te
R undown
S to ra g e &
L o a d in g
S o lid S u lp h u r
S to ra g e &
L o a d in g
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 7 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
Condensate Treating
INTRODUCTION
RasGas is a new company formed in 1993 by Emiri Decree, therefore all
staff will be recruited specifically for the operating company. There will
be a large number of nationalities employed within the company, as staff
will be recruited from Europe, The Middle East, Asia, Canada and USA.
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 8 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
The Managing Director (MD) has overall responsibility for the Company
and has the managers of the following Groups reporting to him:
Administration
Finance
Operations
Technical
Venture
2.2.2
Legal
Quality Management
OPERATIONS GROUP
The Operations Group is responsible for:
Operations Safety
Maintenance
Planning
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 9 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
Managing Director
Operations
Manager
Secretary
Head of
Planning
Production
Manager
Process
Manager
Maintenance
Manager
Materials &
Logistics
Manager
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 10 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
Process Coordination, Laboratory and Fire & Security. Figure 2.4 shows
an organigram of the Process Division.
The Production Manager is responsible for all offshore operations which
includes all Production Operations, Maintenance and Safety.
The Maintenance Manager has three sections reporting to him. These
are Maintenance Onshore, Planning and Services. The Maintenance
and Services Sections cover all three craft disciplines i.e. Mechanical,
Electrical and Instruments. Figure 2.5 shows an organigram of the
Maintenance Department.
The Material and Logistics Manager is responsible for Procurement,
Materials Control and Logistics Support.
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 11 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
P ro cess
M an ager
S h if t
S u p e r in te n d e n t s ( 4 )
S e c r e ta r y
T e c h . A s s is t
L a b o r a to r y
S u p e r in te n d e n t
C h ie f C h e m is t
L a b T e c h s ( S h if t) 8
L a b T e c h s (D a y s ) 2
P r o c e s s O p e r a t io n s
S u p e r in te d e n t
P ro cess C o -o rd .
S u p e r in te n d e n t
O ff s it e s O p e r a tio n s
S u p e r in t e n d e n ts
S h if t S u p e r v is o r
T r a in 1 ( 5 )
S h ift S u p e r v is o r
T r a in 2 ( 5 )
S h ift S u p e r v is o r
A G R /S R U (5 )
S h ift S u p e r v is o r
U t ilitie s ( 5 )
S h if t S u p e r v is o r
S to r a g e /L o a d (5 )
S n r. O p er ato r
T r a in 1 (5 )
S n r . O p e r a to r
T r a in 2 ( 5 )
S n r . O p e r a to r
A G R /S R U (5 )
S n r . O p e r a to r
U t ilitie s ( 5 )
S n r . O p e r a to r
S t o r e /L o a d (5 )
P a n e l O p e r a to r
T r a in 1 (5 )
O p e rato rs
T r a in 1 (5 )
P an e l O p e r a to r
T r a in 2 ( 5 )
O p era to rs
T r a in 2 ( 5 )
P a n e l O p e r a to r
A G R /S R U (5 )
O p e r a to r s
A G R /S R U (5 )
P a n e l O p e r a to r
P o w er G en (5 )
O p e r ato r s
P o w er G en (5 )
P r o c e s s P la n n in g
S u p e r in t e n d e n t
P a n e l O p e r a to r
S t o r e /L o a d (5 )
O p era to rs
S t o r e /L o a d (5 )
B udget &
A d m in
A d m in C le r k s ( 2 )
S nr. P rocess
E n g in e e r
P ro cess
E n g in e e r s ( 2 )
P la n n in g T e c h .
N O T E : A G R - A C ID G A S R E C O V E R Y
: S R U - S U L P H U R R E C O V E R Y U N IT
P a n e l O p e r a to r
U t ilitie s ( 5 )
H e a d o f F ir e
& S e c u r it y
S e n io r F ir e
M a s te r
S e n io r F ir e m e n
(1 0 )
F ir e m e n ( 2 8 )
F ir e T r a in in g
O ff ic e r
S e c u r ity O ff ic e r
S e c u r ity
G u a r d s (1 0 )
O p e r ato r
U t ilitie s ( 5 )
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 12 of 77
ORIENTATION
Date: 06/24/16
Maintenance
Manager
Rev: 0
Maint. Supt.
Onshore
Maint. Planning
Supt.
Maint. Services
Supt.
Tech. Assistant
Tech. Assistant
Tech. Assistant
Senior Planning
Engineer
Maint. Engineer
Train 1
Senior Maint.
Engineer
Mech. Eng. (1)
Inst. Eng. (2)
Elect. Eng. (1)
Senior Inspector
Materials Eng
Maint. Engineer
Train 2
Inspectors (2)
Planning Eng. (2)
Shutdown/Routine
Senior Rotating
E/Q Engineer
Contracts
Engineer
Maint. Engineer
I/S/L
Technicians (2)
Budget/Cost
Control Engineer
Maint. Engineer
Utilities
Senior Workshop
Supervisor
Inst. Supv.
Elect. Supv.
Mech. Supv.
Weld. Supv.
Weld. Tech.(2)
Comms. Eng
DCS Eng.
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 13 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
OFFSHORE FACILITIES
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 14 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
INTRODUCTION
A 32 inch sub-sea pipeline to transport the North Field gas to shore at Ras
Laffan
A Flare Platform
A Process/Utilities Platform
A Riser Platform
An Emergency Flare
An Accommodation Platform
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 15 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
PROCESS/UTILITIES PLATFORM
The process/utilities platform consists of an integrated 2 level deck and
a partial upper mezzanine deck supported on an eight leg jacket. The
platform accommodates two production trains, each rated at 550
MMSCFD. Each train consists of:
Condensate Coalescer
Glycol Contactor
Power Generation
Nitrogen Generator
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 16 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
RISER PLATFORM
The Riser Platform consists of an integrated 2 level deck supported on a
four leg jacket. This platform is bridge connected to the Process/Utilities
platform. The main items that are located on the riser platform are:
Flowline Manifold
The Riser Platform is the central collecting point for the sub-sea
pipelines that transport wellhead fluids from the three Wellhead
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 17 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
Platforms. The 32 inch export pipeline to the Ras Laffan LNG Plant
originates on this platform.
3.3.3
Production Header
Blowdown Header
Test Separator
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 18 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
EMERGENCY FLARE
The flare tower and support platform is of tubular construction with a
conventional three leg jacket. The tower supports the flareline and
provides access to the flare-tips for maintenance. Both HP and LP
flares terminate at the flare platform, each being fitted with pilot and
ignition lines. The pilots are equipped with flame-out sensors. The
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 19 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
Flare Platform is located down wind to the south of the Central Platform
Complex and is connected to the complex by a bridge structure.
3.3.5
ACCOMMODATION PLATFORM
The platform is located to the north of the Central Platform Complex and
consists of an integrated 2 level deck supported on a four leg jacket. It
is connected to the Process/Utilities platform by a permanent bridge
structure.
The platform consists of:
Laundry
Recreational Facilities
Telecommunications Facility
Helideck
Page 20 of 77
ORIENTATION
Date: 06/24/16
Boat Landings
Rev: 0
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 21 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
treatment plant. The condensate is then mixed with condensate from Train No.
2 before re-combining with the dried gas from Trains No. 1 and No. 2. The
combined gas/condensate mixture is passed to the riser platform for transport
through the 32 inch main export line to the onshore processing facility.
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 22 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 23 of 77
ORIENTATION
Date: 06/24/16
ONSHORE FACILITIES
SULPHUR
HANDLING
UTILITIES 1/2
COOLING
WATER 1/2
TRAIN 1
F/H GTG
UTILS
3/4
LAB
WWT
AGR
SRU STAB
TRAIN 3
AGR
SRU STAB
TRAIN 4
COOLING WATER
3/4
REF.
STORAGE
AGR
SRU STAB
TRAIN 2
CCR
Rev: 0
DRY/WET
FLARE
AGR
SRU STAB
FUTURE 5TH
PROCESS UNITS
SLUG
CATCHER
FUTURE 6TH
FUTURE UTILITIES PROCESS UNITS
FUTURE
FLARE
ADMINISTRATION
BUILDING
WAREHOUSE AND
DRILLING
SHOREBASE
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 24 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
4.1 INTRODUCTION
Refer to Figure 4.1.
The function of the onshore process facilities is to receive the combined gas
and condensate stream from the 32 inch sub-sea pipeline, separate the
combined stream into vapour and condensate, which are then treated in other
downstream units to meet product/process specifications. A brief description of
the onshore process facilities is given below.
4.2 GENERAL PROCESS OVERVIEW
Refer to Figure4.2
The Process Units are two parallel Liquefied Natural Gas (LNG) units based on
APCI (Air Products and Chemicals Inc.) Technology, utilised to produce the
desired total LNG of 5.0 Mpta. In addition to LNG, the Process Units produce
condensate and sulphur.
The Inlet Facilities receive feedstock from the two phase Feedgas/Condensate
Pipeline and provide gas/condensate separation. The gas pressure and
temperature are controlled prior to entering The Gas Treating Units, while the
Condensate is stabilized, treated for mercaptons and temperature
controlledprior to rundown to Condensate Rundown, Storage and Loading.
Feed gas from the upstream Inlet facilities is passed through a Feed Gas Filter
Separator Tag No. 11-V001 to ensure there is no liquid carryover into the
mercury removal beds and the downstream Sulfinol Absorber.
The Acid Gas Removal Unit (AGR) is designed to remove hydrogen sulfide,
carbon dioxide and other sulphur compounds by means of chemical/physical
absorption from the gas coming from the Gas Treating Unit.
The sweet gas leaving the Acid Gas Removal Unit is saturated with water. It is
dried in the Dehydration Unit using a propane precooler Tag No. 15-E001
followed by molecular sieves. The purpose is to avoid freezing of water in the
downstream Gas Chilling and Liquefaction Units.
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 25 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
The purpose of gas chilling is to remove heavy hydrocarbons from the treated
natural gas and then liquefy the natural gas. A Scrub Column removes heavy
hydrocarbons which would otherwise freeze in the Main Cryogenic Heat
Exchanger (MHE).
The Refrigeration Unit consists of two Refrigerant Systems. A Propane
Refrigerant (PR) System providing chilling to about -34C, and a Mixed
Refrigerant (MR) System comprising Methane, Ethane, Propane, and Nitrogen.
The Nitrogen Rejection Unit flashes off the nitrogen from the LNG product,
pumps the LNG product to storage and delivers the nitrogen-rich fuel gas at a
pressure of 27.2 bar.a to the Fuel Gas System.
Acid gas from the Acid Gas Removal Unit is processed to convert the hydrogen
sulfide (H2S) and other sulphur compounds in the gas into high purity sulphur.
The process facilities are composed of:
Inlet Facilities
(Unit 10)
Gas Treating
(Unit 11)
(Unit 12)
Dehydration
(Unit 13)
Liquefaction
(Unit 15)
Refrigeration
(Unit 16)
Refrigerant Preparation
(Unit 17)
Nitrogen Rejection
(Unit 18)
Sulphur Recovery
(Unit19)
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 26 of 77
ORIENTATION
Date: 06/24/16
2 Train Operation
1.0 BCF/D Gas
45,000 BBL/D Condensate
Rev: 0
OFFSHORE
FACILITIES
OFFSHORE
Untreated Gas
ONSHORE
Field
Condensate
Inlet
Facilities
Condensate
Treating/
Stabilisation
Gas Treating
H 2S
Acid Gas
Removal
Acid Gas
Enrichment
Sulphur
Recovery
Sweet Gas
Dehydration
Molten
Sulphur
Storage &
Loading
Dry Gas
Refrigeration
Preparation
C 2 & MR
Ref.
Refrigeration
C 2 Ref.
Make-up
C 2& C 3
N 2 Rejection
Solid
Sulphur
Condensate
Refrigeration
Make-up &
Storage
366 MT/H
23,000 BBL/D
155 T/D
ONPLOT
OFFPLOT
C5
Condensate
Rundown
Storage &
Loading
LNG Rundown
Storage &
Loading
Solid Sulphur
Storage &
Loading
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 27 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 28 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 29 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 30 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 31 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 32 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
cryogenic heat exchanger is fabricated from this material, the feed gas
must be treated to remove the mercury.
The mercury removal process consists of one activated carbon mercury
removal bed 11-V001. The carbon bed is also impregnated with
sulphur. As the North Field gas contains low concentrations of mercury,
the removal bed is expected to have an operating life of approximately
five years.
Field gas entering Unit 11 for mercury removal is pressure controlled by
12-PV278 before entering feed gas filter separator 11-V001. This
vessel removes any entrained condensate from the feed gas,
condensate is passed back to the pre-flash drum Tag No.10-V001 on
Unit 10. Dried gas from the filter separator passes into feed pre heater
11-E001 which is steam heated.
Heated gas from 11-E001 then passes through mercury removal vessel
11-V002 which is packed with activated carbon. Flow through the bed is
from the top of the vessel to the outlet situated at the bottom. Two
mercury removal effluent filters 11-S001 A/B located on the gas outlet
line remove any activated carbon dust particles. Treated gas is passed
to the acid gas removal unit (Unit 11).
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 33 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 34 of 77
ORIENTATION
4.2.3
Date: 06/24/16
Rev: 0
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 35 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 36 of 77
ORIENTATION
4.2.4
Date: 06/24/16
Rev: 0
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 37 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 38 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 39 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
The feed gas is liquefied in the feed coils at -130C to -140C and is
sub-cooled in the cold bundle of the MHE to a temperature of -149C at
a pressure of 18 bar.g.
4.2.6
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 40 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 41 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 42 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 43 of 77
ORIENTATION
4.2.7
Date: 06/24/16
Rev: 0
De-ethaniser
De-propaniser
De-butaniser
De-isopentanizer
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 44 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 45 of 77
ORIENTATION
4.2.8
Date: 06/24/16
Rev: 0
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 46 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 47 of 77
ORIENTATION
4.2.9
Date: 06/24/16
Rev: 0
Reaction Furnace
3 Sulphur Condensers
2 Claus Reactors
Each identical Sulphur Recovery Unit has a design capacity of 155 T/D
sulphur production. The sulphur produced is drained into the sulphur pit
where it is degassed. The tail gas exiting the selective oxidation stage,
as well as the sulphur pit vent gas are sent to the thermal tail gas
incinerator.
The Sulphur Recovery Process applied, known as the Claus process, is
based on the partial combustion of hydrogen sulphide (H 2S),
successively followed by two (2) catalytic Claus reactor stages and a
stage where the remaining H2S is selectively oxidized with air. The
partial combustion of H2S at the front end of the unit is achieved by
means of a ratio controlled flow of air.
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 48 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
ORIENTATION
Date: 06/24/16
Rev: 0
leads. Each tank capacity is 140,000 m, (the largest of their type in the
world for hydrocarbon storage). LNG Tanks 71-T001 and 71-T002 are
provided for Train 1 and Tank 71-T003 is provided for 2 Train operation.
The LNG tanks are above ground type. Each tank has a pre-stressed
concrete outer wall with a reinforced concrete roof and a separate 9%
nickel steel inner tank. Refer to Figure 4.14.
The LNG loading system is designed to transport LNG from the storage
tanks to the ship. The system consists of loading and circulation lines
which traverse the distance of approximately 3 km between the LNG
storage tanks and the LNG Jetty head.
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 50 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 51 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 52 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 53 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
ORIENTATION
Date: 06/24/16
Rev: 0
One LNG loading berth has been constructed for RasGas, however
there are interconnecting lines between RasGas and QatarGas loading
systems. This interconnection will allow both companies to use either of
the dedicated LNG loading berths. Upon arrival and connection of the
loading arms, a slip stream of LNG is used to cool the loading ships
manifold. Full loading commences when the cooling operation is
completed. Both the LNG circulation pumps and the LNG loading
pumps are on flow control, and are equipped with minimum flow control
valves.
4.3.4
4.3.5
Seawater Intake
Seawater Distribution
Seawater Outfall
The intake facilities are located at the Ras Laffan Harbour about 6 km
from the LNG plant. The intake is designed for the operational cooling
water demand, and utilities requirements to accommodate 2 Train
Operation.
Seawater (maximum temperature: 35C, minimum
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 55 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
ORIENTATION
Date: 06/24/16
Rev: 0
electrical power for the LNG train facilities over a wide range of
operating and environmental conditions.
Plant electrical loads include the LNG process trains, the
LNG/Condensate storage and loading facilities, utilities, offsites, marine
jetty and the administration and warehouse area.
The main power generation is located in the Utility area. Generator
drivers are GE Frame 6 gas turbine units which are equipped with
electric starter motors. Number four gas turbine is fitted with a
supplementary fired, Heat Recovery Steam Generator (HRSG).
During normal operating conditions the gas turbine equipped with
HRSG will be base loaded to maximise steam production by heat
recovery from the gas turbine exhaust. The other three gas turbines,
exhausting to atmosphere, will operate as two on line, one on standby.
A load shedding system is provided to ensure that power to selected
loads is maintained in the event of a system fault or partial loss of
generation.
Load shedding priorities are based on safety
considerations and process requirements.
For selected motors,
sequence of restart shall be controlled from individual motor starters
equipped with automatic restart modules.
Electrical power, generated at 11 kV 50 Hz stepped up to 33 kV through
captive transformers, is fed to the main 33 kV switchgear in the Main
Substation. Electric power is distributed from the 33 kV switchgear to
the following substations using 33 kV underground 100% redundant
feeders:
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 57 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 58 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 59 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
The Sulphur Recovery Units (SRU) 19 and 29 in the process area are
producers of high, medium and low pressure steams. Low pressure
steam is produced in the Sulphur Condensers and the MP Condensate
Flash Drums. About 60% of this LP steam is supplied to the users in the
AGR and the SRU Units.
Low pressure condensate is collected in the Condensate Flash Drums
and transferred to the Utility Condensate System. MP and LP steam are
collected in MP and LP steam headers and distributed to the users
throughout the LNG facilities.
4.4.3
Boil-Off Gas (BOG) leaving the LNG Storage and Loading Unit
Feed gas from the Metering Skid, in the Inlet Facilities Unit
ORIENTATION
Date: 06/24/16
Rev: 0
the LNG Train, mixes with the balance of the BOG/FFF in the Fuel Gas
Mixing Drum and is passed to the Packaged Boilers and HRSG.
The Sulphur Recovery Units consume fuel gas in the Main Burners,
No. 1, 2 and 3 Line Burners and the Incinerator Burner during normal
operations. During normal operation HP flash gas from the HP
Recontactor in the Acid Gas Removal Units is utilized as the fuel gas
source, via the Fuel Gas Drum, to process users described above.
Remaining HP flash gas is exported to the Fuel Gas System, via the
Fuel Gas Mixing Drum for use as boiler fuel.
Fuel Gas Source for Black Start is from the North Field Phase-1
Pipeline (domestic gas). Sufficient fuel gas is provided to start two
power generation GTGs and two Packaged Boilers.
The Diesel Fuel System consists of a Diesel Fuel Day Tank and a Diesel
Fuel Filter.
All diesel users have their own dedicated diesel fuel day tank which will
be supplied by diesel road tanker. Diesel fuel day tanks are provided
for the following users:
4.4.4
Diesel Fuel Day Tank For Local Use (Trucks and Cranes)
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 61 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
Remineralisation Unit
Softener Unit
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 62 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
Demineraliser Unit
The service water system supplies water for the utility hose stations,
sanitary use in various buildings in the Plant area, gas seals in
manholes in the Plant, and as dilution water for contaminated
condensate dump to the Oily Water Sewer. The service water header is
fed from the desalinated water supply header.
The potable Water System consists of the Remineralisation Unit,
Potable Water Storage Tanks, and Potable Water Pumps. The capacity
of this system is independent of the number of LNG trains.
Feedwater to the remineralisation Unit is desalinated water. Carbon
Dioxide gas is injected into the common feed to lower the pH. The feed
then splits to two remineralisation beds. After remineralisation, a
hypochlorite solution is injected into the common outlet for biological
control. Chlorinated potable water at 5.0 bar.a and 43C is then passed
to the Potable Water Tanks.
The Demineralised Water System consists of the Demineralization Unit,
a Demineralised Water Storage Tank, and Demineralised Water Pumps.
This system is sized, based on Online and Offline cleaning of a single
gas turbine at a time (Frame 7s and Frame 6s).
Feed water to the Demineralization Unit is desalinated water. The feed
splits to two Mixed Bed Polishers. After passing through the Mixed Bed
Polisher, the demineralised water at 5.0 bar.a and 43C is passed to the
Demineralised Water Storage Tank. A conductivity analyzer is provided
on the outlet of the Demineralization Unit with a high conductivity alarm
in the main control room.
From the storage tank, the Demineralised Water Pumps transfer
Demineralised Water at 8.5 bar a and 43C to the online Gas Turbine
Cleaning Water Header and to the Offline Cleaning Water Drum.
Cleaning agents are manually added to the drum. Offline Cleaning
Water Pumps circulate offline cleaning solution which is heated by LP
Steam.
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 63 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
The Softened Water System consists of the Water Softener Unit (Zeolite
Softeners complete with brine Regeneration System), Softened Water
Storage Tanks and Softened Water Pumps.
Feedwater to the Softener Unit is desalinated water. The feed splits to
three softeners. After passing through the Softener Unit, Softened
Water at 5.0 bar.a and 43C is passed to the Softened Water Tanks. A
hardness analyzer is provided on the outlet of the Softener Unit with a
high hardness alarm in the main control room.
From the storage tanks, the Softened Water Pumps transfer Softened
Water at 7.0 bar.a and 43C to the following locations:
Deaerators
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 64 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
Fresh Cooling Water Return at 2.5 bar.a and 47.3C is cooled by oncethru seawater in the Fresh Cooling Water Coolers and passed directly
to the Fresh Cooling Water Pump Suction Header.
Hydrocarbon gas detectors are provided on the vents from the Fresh
Cooling Water Tanks to indicate hydrocarbon leakage from the process
into the Fresh Cooling Water System.
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 65 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 66 of 77
ORIENTATION
4.4.5
Date: 06/24/16
Rev: 0
4.4.6
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 67 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
Instrument air is supplied to all users of instrument and plant air in the
Offplot areas. Remote instrument air holder vessels are provided in the
LNG Storage and BOG Compressor Area, LNG Jetty Area, Seawater
Intake Area and Condensate Storage Area. An automatic shutdown
valve provided on the service air header maintains air pressure in the
instrument air holder vessels.
Potable water is supplied to LNG Storage, LNG Jetty, Seawater Intake
and Condensate Storage areas as a source for potable and service
water.
Nitrogen in a vapor form is supplied from onplot LNG Plant Area to LNG
Storage and BOG Compressor Area, Condensate Storage Tank Area
and LNG Jetty Area. Nitrogen Holders (buffer tanks) are provided in
LNG Storage and Jetty Areas.
Diesel fuel oil is required only at the Seawater Intake Structure for the
diesel engine driven sea fire water pumps. Diesel fuel oil is supplied by
a diesel fuel tank truck.
Fuel gas is required at the Offplot facilities for LNG tankage and jetty
flare. The fuel gas can be supplied from the Boil Off Gas (BOG) system
and the LNG circulation when the LNG plant is in operation. LPG
bottles shall be provided for initial start up and as a backup to light off
the pilot and the flare.
Steam is not supplied to the Offplot areas. Electric heat tracing is sued
for heating instrument and instrument piping.
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 68 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
5.1 GENERAL
The fire protection systems provided for the LNG facilities are self sufficient
without any outside support. The systems are capable of dealing with any
potential fire source release and fire hazard. Automatic and/or remote actuation
capability for fire protection from the fire station and the local control room are
provided to minimise fire fighting manpower requirements. The facilities
handling LNG/LPG are furnished with all necessary protection to cover all
possible hazard scenarios such as gas release without fire, liquid release
without fire, torch fire and pool fire.
The following protection systems are provided:
Fire Hydrants
A Fire Water Storage Tank, (fresh water) has the capacity to hold maximum fire
water demand for four (4) hours is provided to fight a major single fire.
Provision is made to supply desalinated water from the Desalinated Water
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 69 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
Storage Tanks to this fire water storage tank to keep it full. A back-up seawater
connection from the seawater cooling lines is provided to this tank. Seawater
Fire Pumps are operated only when the Seawater Pumps are not in operation
and fresh fire water storage for four (4) hours is depleted.
A direct connection from the Seawater Fire Pumps, is provided to the fresh fire
water piping main. This supplies seawater as backup fire water to Condensate
Storage, LNG Storage and LNG Jetty Areas. This will allow isolation of any
single area without loss of fire water source. The following Fire Water Pumps
support the fire water system:
5.2.1
5.2.2
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 70 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
WATER MONITORS
The following monitor types are provided:
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 71 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
LNG Pump Platform and Tank PSV Tail Pipe on LNG Tanks
5.2.5
FOAM SYSTEMS
High expansion foam systems are provided for liquid spill containment
in process areas, LNG jetty and LNG storage tanks area.
A Rim Seal Foam System with tank shell mounted foam chambers and
wind girders are provided for the protection of open top floating roof
Condensate storage tanks.
5.2.6
Page 72 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
This system (FM200) must not be used at any other location without
specific approval. Automatic water sprinkler systems are provided for
the dining area of the Canteen, Laboratory, Maintenance Work Shop,
Warehouse, Garage and Administration Building.
Indoor hydrants are located inside the buildings except for gate houses,
Satellite Instrument Houses (SIHs), Control buildings and Substations.
For control rooms, substations and analyzer houses, 6.8 kg CO 2
extinguishers are provided with a maximum travel distance of 9 m. In
addition, 20 kg CO2 wheeled extinguishers are provided at the entrance
to substations. For other buildings, 9 kg portable extinguishers are
provided with a maximum travel distance of 22.8 m.
5.2.8
FIRE STATION
A dedicated Fire House is provided for the LNG facilities and includes
the following mobile fire equipment:
One (1) First Intervention Fire Truck
Dry Powder
: 500 kg
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 73 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
3% type AFFF
: 2,000 litres
Dry Powder
: 3,000 kg
Type AFFF
: 5,000 litres
5.2.9
The design of the fire and gas alarm, detection and control system (F&G
Systems), is based on programmable technology and fully distributed
control concept. The system is interfaced with the process DCS for the
purpose of monitoring only. The system has an interface with the Public
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 74 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
Address and General Alarm System (PA/GA System) for sounding F&G
audible alarms.
F&G panels are distributed at strategic locations such as Local Control
Shelters (LCSs), Satellite Instrument Houses (SIHs), Marine Terminal
Building (MTB), Central Control Building (CCB) and Fire Station. These
panels receive signals from field devices for remote/automatic actuation
of the fire fighting systems and for transferring the received signals to
other F&G panels and the process DCS.
Optical fibre cables are used for data network links between F&G
panels, while conventional electrical cables are used between field
devices and the F&G panels. The optical fibre cables are dual
redundant with separate routes.
Three types of F&G mimic panels are utilised:
Main mimic panels indicating zone alarms for the whole plant area
ORIENTATION
Date: 06/24/16
Rev: 0
located in its own building. Common alarms of the local panel are sent
to the relevant F&G panels by means of hard-wired connections.
The fire protection system can be summarised as shown below:
Fire and Gas Panels with hard-wired mimic panel, VDU and
operating panel in the CCB and the Fire House
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 76 of 77
ORIENTATION
Date: 06/24/16
Rev: 0
Safety Showers and Eye Wash Units are provided throughout the
LNG Plant facility where hazardous and/or toxic materials such as
caustic, acid, amine, sulfur etc. are handled and/or stored. These
units are located in safe and readily accessible locations.
At least two (2) air breathing stations are provided at the periphery
of each process unit. Each station contains at least five (5) Self
Contained Breathing Apparatus (SCBAs). One air breathing
station with two (2) SCBAs is provided near the electrochlorination
unit in the Seawater Intake Area.
In addition, at least one (1) Breathing Air Trailer (BAT) in the Acid
Gas Removal Units and Sulfur Recovery Units is provided. The
BAT contains at least four (4) breathing air cylinders and other
breathing accessories. A package breathing air compressor is
located in the Fire House to refill breathing air cylinders.
QTOPS
Ras Laffan Liquefied Natural Gas
Company Limited
Page 77 of 77