Module 12-Private STP
Module 12-Private STP
Module 12-Private STP
and
Points of Disposal
Septic Tank
Seepage Pit
Sanitary Drain Field/Leaching Field
Anaerobic Baffled Reactor
Soak Pit
SYSTEM DESIGNS.
SYSTEM COMPONENTS
Septic Tank:
Private Sewage Treatment System
Most urban and suburban areas in our country
do not have Public Sewage Treatment Plants.
It is therefore necessary the sanitary wastes in
every building be processed and neutralized by
means of a Private Sewage Treatment System
and Disposal Unit.
The General Scheme of a Private Treatment System is relatively simple, as enumerated below:
1. The sewage is retained in a submerged, tightly enclosed tank;
2. Solid wastes, known as sludge, are diverted to the bottom of the tank;
3. The action of bacteria present in the tank breaks up the solids and aids in purifying the fluids;
4. An amount of sludge builds up at the bottom of the tank while other organic matters, known as
scum, floats to the surface.
5. An outlet pipe is provided so that the partially purified effluent (the liquid content of the sewage)
will be disposed to a proper point of disposal.
The septic tank is the primary purification unit and should be installed close to the surface
of the soil, because correction of the effluent depends on oxidation and the presence of
aerobic bacteria that is usually found not more than 1500mm below the surface
Danilo V. Ravina NAMPAP-CEBU CHAPTER
1.50 meters
15.20 meters
Streams:
15.20 meters
Trees:
3.00 meters
Seepage pits or
Cesspools;
1.50 meters
Disposal Fields;
1.50 meters
1.50 meters
Pressure Public
Water Main:
3.00 meters
Minimum Width of
900 mm
228.6mm
Minimum Air
Space or
Freeboard
Liquid Depth:
600 mm
(minimum) to
1800 mm
(maximum)
2 cu.m. minimum
volume
304.8mm Minimum
Depth of Inlet and
Outlet Pipe below
the water surface
Septic tank shall be structurally designed to withstand all anticipated earth or other
loads. All septic tanks covers shall be capable of supporting an earth load of not
less than 14.4 kPa when the maximum coverage does not exceed 9000mm.
Method 1:
Standard Sizes of Septic Tanks (Section 233 Philippine National Plumbing Code of 1959)
Inside Dimension of the Digestive Chamber
Depth in meters
Width in meters
10
1.20
0.90
1.80
15
1.20
1.10
2.20
20
1.20
1.25
2.50
25
1.20
1.40
2.80
30
1.30
1.50
3.00
35
1.30
1.60
3.20
40
1.40
1.65
3.30
45
1.40
1.75
3.50
50
1.50
1.80
3.60
60
1.50
1.95
3.90
70
1.50
2.00
4.00
80
1.60
2.20
4.40
90
1.80
2.30
4.60
100
1.80
2.50
5.00
Danilo V. Ravina NAMPAP-CEBU
CHAPTER
REMARKS
Length in
meters
Number of
Person Served
Method 2a:
Estimated Waste/Sewage Flow Rates (Table B-2, 1999National Plumbing Code)
Capacity of Septic Tanks*
SINGLE
FAMILY
DWELLING
(NO. OF
BEDROOMS)
MULTIPLE
DWELLING
UNITS or
APARTMENTS
OTHER
USES:
MAX. DFU
SERVED
LITERS
CUBIC
METERS
1 or 2
---
15
750
2838
2.84
---
20
1000
3785
3.79
2 units
25
1200
4582
4.58
5 or 6
3 units
33
1500
5677.5
5.68
---
4 units
45
2000
7570
7.57
---
5 units`
55
2250
8516.3
8.52
---
6 units
60
2500
9462.5
9.46
---
7 units
70
2750
10,408.8
10.41
---
8 units
80
3000
11,355
11.36
---
9 units
90
3250
12,301.3
12.30
---
10 units
100
3500
13,247.5
13.25
Method 2b:
Estimated Waste/Sewage Flow Rates (Table B-3, 1999 National Plumbing Code)
Type of Occupancy
Type of Occupancy
15 + 4 per
passenger
Restaurant: Cafeteria
20/employee
75.7/employee
Churches (Sanctuary)
Restaurant: Toilet
7/customer
26.5/customer
Restaurant: Kitchen
waste
6/meal
22.7/meal
25/person/shift
94.6/person/shift
3.8/meal
Add 10/employee
Add 3.79/employee
1/meal
Factories: w/ showers
Factories: w/ cafeteria
Add 5/employee
Add 18.9/employee
2/customer
7.6/customer
Hospitals
25 per bed
20/person
75.7/person
40 per bed
60/bed (2 person)
227.1/bed (2
person)
70/bed(2 person)
264.95/bed
Offices
20/employee or
1.12/ sq.m. floor
area
75.7/employee or
4.23/sq.m. floor
area
Stores
20 /employee
75.7/employee
Add 1.2/sq.m. of
floor space
Add 4/sq.m. of
floor area
Schools: Elementary
56.8/person
Schools: intermediate
& High School
20/person
75.7/student
5/person
Add 18.9/student
Schools: w/ cafeteria
3/person
Add 11.4/student
Method 3.
Sizing of Septic Tank: Fixture Unit Method
Plumbing Fixture
Drainage Fixture
Unit (DFU)
Bathtub
Bidet
Drinking Fountain
Floor Drain
Grease Trap
Laundry Tub
Sink, residential
Sink,
Commercial/Industrial
Sink, service
Urinal. Wall-mounted
36
4*
Percolation Test
100
300
150
50
STEPS:
1. First fill the test hole with water and allow it to seep into the
surrounding soil.
2. Then refill the hole to a depth of at least 150mm while the
bottom of the hole is still wet.
3. Measure the depth of the water and record the time it takes for
all of it to be absorbed into the soil.
4. Calculate the time required for the water level to drop 25mm.
Danilo V. Ravina NAMPAP-CEBU CHAPTER
Seepage Pit
Seepage Pit a
loosely lined
excavation in the
ground, which
receives the discharge
of a septic tank and
designed to permit
the effluent from the
septic tank to seep
through the pit
bottom and sides.
216
2 MINUTES
175
5 MINUTES
130
10 MINUTES
94
15 MINUTES
73
20 MINUTES
61
30 MINUTES
45
45 MINUTES
33
60 MINUTES
20
REQUIRED AREA
OF LEACHING
(m/L)
MAXIMUM
ABSORPTION
CAPACITY IN
L/m OF
LEACHING AREA
FOR A 24 HOUR
PERIOD (L/m)
COARSE SAND
AND GRAVEL
0.005
203.7
FINE SAND
0.006
162.9
SANDY LOAM or
SANDY CLAY
0.010
101.9
CLAY WITH
CONSIDERABLE
SAND or GRAVEL
0.022
44.8
CLAY WITH
SMALL AMOUNT
OF SAND or
GRAVEL
0.029
33.8
Disposal Field
Disposal Field is a method of sewage
disposal which allows sewage to seep
directly into the soil.
Materials for distribution lines for disposal
fields are;
1. Clay tile with open joints
2. Perforated clay pipe
3. Perforated Bituminous Fiber Pipe
4. Perforated High Density Polyethylene
(HDPE) pipe
5. Perforated ABS pipe
6. Perforated PVC pipe
Application Level:
- Household
- Neighborhood
Management Level:
- Household
- Shared
- Public
Inputs: Blackwater and
Greywater
Outputs: Fecal Sludge
and effluent
Concept
Examples
The ABR under construction, down pipes and perforated slabs to support filter media in the Anaerobic Filter
(AF) sections, pouring ABRs concrete slab at Pestalozzi School, Zambia
Source: http://www.germantoilet.org/
Concept
Design principles
ABRs start with settling chamber for larger solids and impurities
followed by series of at least 2
, sometimes up to 5
upflow chambers
(SASSE 1998)
(SASSE 1998)
Hydraulic Retention Time (HRT) is relatively short and varies from only
a few hours up to two or three days (FOXON et al. 2004; MOREL & DIENER 2006; TILLEY et al. 2008)
up-flow velocity is the most crucial parameter for dimensioning,
especially with high hydraulic loading. It should not exceed 2.0 m/h
.
(SASSE
Treatment efficiency
(UNEP
Inlet
Inflow
ranges
from 2,000
to 20,000
liters per
day
Settlement
Chamber
As sludge is accumulating,
desludging is required
every 2 to 3 years.
Upflow Chambers
Outlet
Cham
ber
Outlet;
To point
of
disposal
Adequacy of Technology
This technology is easily
adaptable and can be
applied at the household
level or for a small
neighborhood that are
using a considerable
amount of water for clothes
washing, showering, and
toilet flushing.
This is most appropriate if
water use and supply of
wastewater are relatively
constant.
Health Aspects/Acceptance
Although the removal
of pathogens is not
high, the ABR is
contained so users do
not come in contact
with any of the
wastewater or disease
causing pathogens.
Maintenance
ABR will not operate at full
capacity for several months
after installation because of
the long start-up time
required for the anaerobic
digestion of the sludge.
To help the ABR to start
working more quickly, it can
be seeded, that is, active
sludge can be introduced so
that active bacteria can
begin working and
multiplying immediately.
Examples
Use of straight handle (left) and Z-handle (right) brushes for cleaning of down-ward pipes
Source: K.P. Pravinjith
Examples
ADVANTAGES
Resistant to organic and
hydraulic shock loads.
No electricity required.
Greywater can be
managed concurrently.
Can be built and repaired
with locally available
materials
DISADVANTAGES
Requires constant
source of water.
Effluent requires
secondary treatment
and/or appropriate
discharge.
Low reduction of
pathogens
Approximately 1 : 1 to 2 : 1
c. Length to Height Ratio:
Approximately 1.5 : 1
Step 5. Determine
number of Up-flow
Chambers.
* Use length to height
ratio = 0.5 to 0.6
Dimension Parameters:
a. Depth and width should be
equal to the settling chamber
(easier to construct).
Length of Up-flow Chamber
(Luc):
Luc = Vuc (W x H)
Danilo V. Ravina NAMPAP-CEBU CHAPTER
N = Design Population
Danilo V. Ravina NAMPAP-CEBU CHAPTER
INLET PIPE
MANHOLE
CLEANOUT
PLAN
OUTLET PIPE
VENT PIPE
DIGESTIVE
CHAMBER
SETTLING
CHAMBER
UPFLOW
CHAMBER
OUTLET
BOX
SECTION
Danilo V. Ravina
NAMPAP-CEBU
CHAPTER
ARTICULATED SEPTIC TANK
or THREE
CHAMBERED
SEPTIC TANK
Land requirement
1 x HOUSEHOLD UNIT
Internal
Decorative
capping
internal
dry sand
gravel
1.5m
limestone
Septic
tank
A = (t x Q) (n x z)
Where:
A = area of reed bed in
sq.meters
t = retention time, use 5
to 8 days
Q = flow rate in cubic
meter per day
n = gravel cavity rate, use
0.4 for sand & gravel
z = height in meters, use
0.70 to 1.00
Solution:
1. Determine the estimated sewage
flow rate. From the NPC, use 60 liters
per bed per day (double occupancy) :
Q = 20 beds x 60 liters/bed/day
Q = 1,200 liters/day
or 1.2 cubic meter/day
A=
SOAK PIT
Or
DRY WELL
STORM WATER DISPOSAL
SOAK PIT
109.00 mm
February
71.10 mm
March
54.60 mm
April
58.60 mm
May
120.90 mm
June
177.00 mm
July
196.70 mm
August
152.70 mm
September
186.70 mm
October
201.40 mm
November
162.30 mm
December
137.70 mm
The AverageDanilo
Annual
Rainfall
for Metro
Cebu is 1628.70 mm
V. Ravina
NAMPAP-CEBU
CHAPTER
C = (A x R ) 3
Where:
C = capacity in cubic meters
A = area to be drained in
square meters
R = rainfall rate in
meter/hour, use 0.05 to
0.125 m/h
Danilo V. Ravina NAMPAP-CEBU CHAPTER
Where:
S = storm water
catchment capacity in
cu.m.
C = runoff coefficient, use
Q = (60 x water level drop in mm) 5 min.
1 for hard surface areas
Q = __________mm/hour
Step 3. Assess the storm I = local rain intensity, use
125
water catchment
A = catchment area in
capacity (S):
hectares
S = 10 x C x I x A
Danilo V. Ravina NAMPAP-CEBU CHAPTER
GREASE INTERCEPTOR
GREASE INTERCEPTOR
GREASE INTERCEPTOR
SOAK PIT
End of Presentation