The AETNA CASUALTY AND SURETY CO., PLAINTIFF-DEFENDANT-APPELLANT-CROSS-APPELLEE v. ANIERO CONCRETE CO., INC., PLAINTIFF-APPELLEE—CROSS-APPELLANT, GENERAL ACCIDENT INSURANCE COMPANY OF AMERICA, DEFENDANT-COUNTER-CLAIMANT-APPELLEE, NEW YORK CITY SCHOOL CONSTRUCTION AUTHORITY, DEFENDANT-COUNTER-CLAIMANT-CROSS-APPELLEE, KREISLER BORG FLORMAN GENERAL CONSTRUCTION COMPANY, ACROM CONSTRUCTION SERVICES CO., INC., CONSTRUCTION MANAGERS, a JOINT VENTURE, DAVID M. PHARIS, S.T. HUDSON, DOING BUSINESS AS HUDSON INTERNATIONAL, HUDSON INTERNATIONAL, CREVANI BROS. REALTY, CREVANI CONCRETE CONSTRUCTION CO., INC., CREVANI FARMS 1979 TRUST AGREEMENT AND VERTOLOMO'S, INC., 404 F.3d 566, 2d Cir. (2005)
The AETNA CASUALTY AND SURETY CO., PLAINTIFF-DEFENDANT-APPELLANT-CROSS-APPELLEE v. ANIERO CONCRETE CO., INC., PLAINTIFF-APPELLEE—CROSS-APPELLANT, GENERAL ACCIDENT INSURANCE COMPANY OF AMERICA, DEFENDANT-COUNTER-CLAIMANT-APPELLEE, NEW YORK CITY SCHOOL CONSTRUCTION AUTHORITY, DEFENDANT-COUNTER-CLAIMANT-CROSS-APPELLEE, KREISLER BORG FLORMAN GENERAL CONSTRUCTION COMPANY, ACROM CONSTRUCTION SERVICES CO., INC., CONSTRUCTION MANAGERS, a JOINT VENTURE, DAVID M. PHARIS, S.T. HUDSON, DOING BUSINESS AS HUDSON INTERNATIONAL, HUDSON INTERNATIONAL, CREVANI BROS. REALTY, CREVANI CONCRETE CONSTRUCTION CO., INC., CREVANI FARMS 1979 TRUST AGREEMENT AND VERTOLOMO'S, INC., 404 F.3d 566, 2d Cir. (2005)
The AETNA CASUALTY AND SURETY CO., PLAINTIFF-DEFENDANT-APPELLANT-CROSS-APPELLEE v. ANIERO CONCRETE CO., INC., PLAINTIFF-APPELLEE—CROSS-APPELLANT, GENERAL ACCIDENT INSURANCE COMPANY OF AMERICA, DEFENDANT-COUNTER-CLAIMANT-APPELLEE, NEW YORK CITY SCHOOL CONSTRUCTION AUTHORITY, DEFENDANT-COUNTER-CLAIMANT-CROSS-APPELLEE, KREISLER BORG FLORMAN GENERAL CONSTRUCTION COMPANY, ACROM CONSTRUCTION SERVICES CO., INC., CONSTRUCTION MANAGERS, a JOINT VENTURE, DAVID M. PHARIS, S.T. HUDSON, DOING BUSINESS AS HUDSON INTERNATIONAL, HUDSON INTERNATIONAL, CREVANI BROS. REALTY, CREVANI CONCRETE CONSTRUCTION CO., INC., CREVANI FARMS 1979 TRUST AGREEMENT AND VERTOLOMO'S, INC., 404 F.3d 566, 2d Cir. (2005)
3d 566
Carella, Byrne, Bain, Gilfillan, Cecchi, Stewart & Olstein, Roseland, NJ,
for Plaintiff-Appellee-Cross-Appellant.
Vincent J. Zichello, Zichello & McIntyre, LLP, New York, NY, for
Defendant-Counter-Claimant-Appellee.
Fay NG (Pamela Seider Dolgow; Michael A. Cardozo, Corporation
Counsel, on the brief), Office of the Corporation Counsel of the City of
New York, New York, NY, for Defendant-Counter-Claimant-CrossAppellee.
Before: KEARSE, CABRANES and SACK, Circuit Judges.
PER CURIAM.
This case, brought in the United States District Court for the Southern District
of New York (Charles S. Haight, Jr., Judge) under the Court's diversity
jurisdiction, arises out of efforts to renovate the Morris High School in Bronx,
New York. The District Court held that a contract to complete the renovation
the "Completion Agreement" memorialized on March 18, 1994 by The
Aetna Casualty and Surety Company ("Aetna") and Aniero Concrete Company,
Inc. ("Aniero") was invalid due to an unsatisfied condition precedent. On
appeal, Aetna disputes the District Court's conclusion. We affirm.
In 1992, the New York City School Construction Authority ("SCA") contracted
with the P.J. Carlin Construction Company ("Carlin") to perform the Morris
High School renovation. The SCA's arrangement with Carlin subsequently
collapsed, leading Aetna, Carlin's surety, to solicit bids for completing the
work. See Aniero Concrete Co. v. N.Y. City Constr. Auth., 1997 WL 3268
(S.D.N.Y. Jan. 3, 1997). Aetna accepted Aniero's bid, and the two parties
memorialized the Completion Agreement. See id. at *1. After "mobiliz[ing]" on
the job site, Aniero claims to have discovered that it had been "given an
inaccurate and misleading description of the work completed by Carlin." Id. at
*1.
In December 1994, Aniero commenced this action, asserting tort and contract
claims against, inter alia, Aetna and the SCA. Aetna subsequently filed an
action against General Accident Insurance Company of America ("General"),
Aniero's surety, in New York state court; that action was removed to federal
court and consolidated with Aniero's action. On March 24, 1997, the SCA filed
a counterclaim against Aniero and a cross-claim against Aetna. Further
background facts, as well as the history of this litigation's motion practice, are
set forth in detail in the District Court's Memorandum Opinions and Orders
dated January 3, 1997 (reprinted below at Appendix A). see id.; February 27,
1997 (reprinted below at Appendix B), see Aniero Concrete Co. v. N.Y. City
Constr. Auth., 1997 WL 83308 (S.D.N.Y. Feb. 27, 1997); and March 30, 1998
(reprinted below at Appendix C), see Aniero Concrete Co. v. N.Y. City Constr.
Auth., 1998 WL 148324 (S.D.N.Y. Mar. 30, 1998). ("Aniero Summary
Judgment").
4
In due course, on March 30, 1998, the District Court issued a Memorandum
Opinion and Order addressing, inter alia, the parties' motions for summary
judgment. See id. The Court concluded that the Completion Agreement was
invalid due to an unsatisfied express condition precedent the SCA's written
consent to the assignment of the Carlin contract to Aniero. Id. Accordingly, the
SCA's counterclaim against Aniero was dismissed because it was premised on
the validity of the Completion Agreement. Id. Moreover, the Completion
Agreement having been declared invalid, the District Court held that "the
performance bond issued by General as security for the Completion Agreement
is also a nullity." Id. The District Court thus dismissed Aetna's claims against
General. Id. The Court further noted that Aniero and General had agreed not to
press their claims if the Completion Agreement were held invalid; the Court,
therefore, regarded as moot any motions seeking the dismissal of Aniero's or
General's actions, as well as General's own cross-motion for summary
judgment in its favor.1 Id. On May 19, 1998, the District Court denied Aetna's
motion for reconsideration.
On appeal, Aetna argues that the District Court incorrectly interpreted the
Completion Agreement and that, in any event, the Completion Agreement was
so ambiguous as to preclude summary judgment. Aniero cross-appeals, seeking
to reinstate its claims if we reverse the District Court's judgment and hold that
the Completion Agreement was valid.
For substantially the reasons stated in the District Court's Memorandum and
Order of March 30, 1998, we affirm. We therefore need not reach the question
raised by Aniero's protective cross-appeal, and we dismiss the cross-appeal as
moot.
APPENDIX A
7
v.
10
11
v.
12
13
14
v.
15
New York City School Construction Authority; Kreisler Borg Florman General
Construction Company, Inc.; Acrom Construction Services, Co., Inc.; Kreisler
Borg Florman General Construction Company, Inc. and Acrom Construction
Services Co., Inc., Construction Managers, a Joint Venture; David M. Pharis
and S.T. Hudson d/b/a Hudson International; Aniero Concrete Co., Inc.;
Crevani Construction Co., Inc.; Vertolomo's Inc.; Crevani Bros. Realty Co.,
Inc.; Crevani Farms 1979 Trust Agreement; Stephen G. Crevani, Jr. Trust
Agreement; Stephen G. Crevani, Jr. Business Buy-Pass Trust Agreement;
Stephen G. Crevani; and Stephen G. Crevan, Jr., Third-Party Defendants.
16
17
Jan. 3, 1977.
19
This action is before the Court on a motion by defendant The Aetna Casualty
and Surety Company ("Aetna"), to dismiss the complaint brought by Aniero
Concrete Company, Inc. ("Aniero"), pursuant to Rule (12)(b)(6), or in the
alternative for summary judgment. Defendant David M. Pharis and S.T.
Hudson d/b/a Hudson International ("Hudson")1 also moves to dismiss Aniero's
The instant action, brought under this Court's diversity jurisdiction, 2 arises out
of the collapse of a contractual arrangement for the renovation of Morris High
School in the Bronx ("the Project" or "the Morris Project"). Aniero's complaint
paints the following portrait of the events that led to the instant suit:
21
22
23
Aniero mobilized on the site on March 21, 1994. It soon discovered, however,
that the Project Documents had given an inaccurate and misleading description
of the work completed by Carlin, and that left to be done. The defects in
Carlin's work, moreover, could not previously have been discovered by a walk
through of the Morris site. As a result, Aniero commenced the instant action on
December 20, 1994, and ceased work on the Project two days later. In its
complaint, Aniero brought claims against Hudson and Aetna for fraudulent
concealment, fraudulent inducement, and negligent misrepresentation. Aniero
also stated claims against Hudson for negligence and breach of Hudson's
contract with Aetna, to which Aniero purported to be a third party beneficiary,
and against Aetna for breach of contract, anticipatory breach, rescission on the
grounds of unilateral or mutual mistake, and tortious interference with contract.
In support of its breach of contract claim, Aniero alleged, without detail, that
Aetna had failed to pay money owed for work performed by Aniero under the
Completion Agreement. Complaint 135. The tortious interference claim was
based on the assertion that Aetna interfered with the performance of the Carlin
Contract by demanding that it receive payment for change order work.
Complaint 170. Aniero also raised a variety of similar causes of action against
SCA and a party contracted by SCA to perform construction management
services, the joint venture known as Kreisler Borg Florman General
Construction Company, Inc. and Acrom Construction Services Company, Inc.
("KBF"). Finally, Aniero brought a claim of conspiracy against all the
defendants.
24
Aetna now moves to dismiss Aniero's complaint or, in the alternative, for
summary judgment. It supports its motion with affidavits by Aetna technical
consultant Kevin Gillen and attorney Arthur Lambert, as well as various
documents. The documents are appended to Lambert's affidavit, which contains
no factual assertions. Gillen's affidavit is restricted entirely to a description of
these documents, except in that it responds to Aniero's breach of contract claim.
Gillen asserts that Aniero received an $850,000 mobilization advance, and was
fully compensated on the first four requisitions for payment it submitted. Gillen
Aff. 19. According to Gillen, Aetna did not pay the fifth and final requisition
presented by Aniero because Aniero had abandoned the project. Gillen does not
aver that the information contained in his affidavit derived from personal
knowledge.
25
26
Aniero represents that it has reviewed any and all data it deems necessary or
28
The bid materials, submitted in the name of Aetna "[b]y: Hudson International"
and dated December 22, 1993, Lambert Aff. ex. 5A, contained similar
warnings. The bid invitation stated that the submission of a bid would be
"deemed a representation" that the bidder had verified all information contained
in the contract documents, examined the Morris facilities, based its bid on its
own specifications, and assumed all responsibility for defective work
performed by Carlin. Id. Similarly, an information sheet cautioned bidders that
they would be "responsible for determining the work completed to date as well
as the balance remaining to be completed." Lambert Aff. ex. 5B 14. A third
document stated that "[f]ailure of Bidder to ... examine [the Bid Documents]
and inform itself [with respect to conditions affecting the amount of its bid]
shall be at its sole risk and no relief for error or omission will be given."
Lambert Aff. ex. 5C 5.
29
30
Crevani maintains that three weeks after Aniero's and Delta's initial bid was
denied, Hudson contacted Delta, stating that the situation at Morris was an
"emergency," and asking that Delta and Aniero submit a bid for that project as
soon as possible. Crevani Aff. 29. One week later, after receiving the Project
Documents, Delta and Aniero submitted an $18,800,000 proposal.5
31
31
32
Hanjis also claims that Aetna failed to notify either Delta or Aniero that the
bidder who had originally been chosen to finish the Morris Project, A.F.C.
Enterprises ("AFC"), increased its bid by $7 million when it was given full
access to the project site. Id. 34; see also Crevani Aff. 53-55. In
supplemental filings, Aetna disputes the truth of this last assertion on the basis
of two letters it had received from AFC: one in which AFC requested
clarification as to $2,826,634 in materials which had been excluded from its bid
proposal on the mistaken assumption that they would be paid for by Aetna, and
a second in which AFC stated that it had re-evaluated its proposal in light of its
"understanding of how liability [would] be assumed by Aetna and the
responsibility of the completion contractor with respect to subcontractor and
vendor liabilities." Letter of Ruggiero to Lewis, Feb. 22, 1994. In response,
Aniero points out that these filings do not explain all of the purported $7
million augmentation in AFC's bid.
33
Crevani's affidavit also elaborates further on Aniero's allegation that Aetna had
breached its obligations under the completion agreement and had tortiously
interfered with the Carlin Contract, to which Aniero had been assigned Aetna's
rights. Crevani asserts that, although the Completion Agreement required Aetna
to turn over to Aniero money paid by the SCA for extra work completed by
Aniero pursuant to change orders, Aetna improperly withheld these funds.
Moreover, Crevani maintains that Aniero has yet to be paid for work done from
October through December, 1994, although payment for its October work was
approved by SCA. Crevani Aff. 60-65.
34
In addition to filing its motion in this action, Aetna also commenced suit in the
Supreme Court of New York, Nassau County against Aniero's surety, General.
General removed the case to the Eastern District of New York, and filed an
answer, counterclaim and third-party complaint. The counterclaim and thirdparty complaint essentially replicates Aniero's pleadings, while also raising
claims for indemnification against Aniero and various other companies that had
purportedly agreed to indemnify General for losses arising out of its surety for
Aniero's performance of the Completion Agreement.
35
While Aetna's suit was pending in the Eastern District, General moved to
35
While Aetna's suit was pending in the Eastern District, General moved to
intervene in the action before this Court, submitting a complaint that again
mirrored that presented by Aniero. Although General acknowledged that it
planned to request consolidation of the cases pending in the Eastern and
Southern Districts, it sought intervention because the court rules governing its
Eastern District action would not allow for the filing of an immediate motion
for transfer, and General was "[c]oncerned that in the interim its interest
[would] be impaired if this litigation proceeds without its involvement."
General's Mem. in Support of Mot. to Intervene at 5-6. After General's motion
to intervene was fully briefed, the Eastern District action was transferred to this
Court, and I signed a consent order consolidating these cases. General noted, in
a letter filed prior to the consent order, that the transfer of Aetna's suit might
render its intervention motion moot. Letter of Andretta to Court, May 9, 1995,
at 1.
36
General's filings did not represent the last of the motion practice in this case.
Hudson, for its part, sought the dismissal of both Aniero's complaint and
General's third party complaint. To the extent that the claims brought against
Hudson duplicated those raised against Aetna, Hudson's arguments for
dismissal replicate those presented by its co-defendant.
DISCUSSION
37
Before I proceed to address each of the specific causes of action placed at issue
by the instant motions, there are two preliminary matters whose determination
is essential to the motion's disposition. First, I must determine what documents I
may take into account in ruling on the Rule 12(b)(6) motions, or whether those
motions may best be viewed as seeking summary judgment. Second, I must
decide the extent to which the Waiver Clause is a bar to Aniero's claims. The
parties agree that the substantive legal issues are governed by New York law.
38
39
40
42
Aniero's other procedural contentions are without merit. The two affidavits
submitted in support of Aetna's motion are, concededly, inadequate. Lambert's
affidavit makes no factual assertions whatsoever, while that filed by Gillen
gives no indication as to whether the affiant has personal knowledge of the
events to which he avers. See Fed.R.Civ.P. 56(e); United States v. Bosurgi, 530
F.2d 1105, 1112 (2d Cir.1976). Nevertheless, as Aniero has not moved to strike
these affidavits, I may consider them in ruling on the instant motion. See 10A
C. Wright and A. Miller, Federal Practice and Procedure: Civil 2d. 2738, at
507-08 (1983). I also note that the primary outside document submitted by
Aetna, the Completion Agreement, is integral to Aniero's complaint, and could
be considered even if this motion were reviewed under Rule 12(b)(6). See San
Leandro Emergency Med. Group Profit Sharing Plan v. Philip Morris Cos., 75
F.3d 801, 808 (2d Cir.1996); Int'l Audiotext Network, Inc. v. AT & T, 62 F.3d
69, 72 (2d Cir.1995); see also Decker v. Massey-Ferguson, Ltd., 681 F.2d 111,
113 (2d Cir.1982)(where "many of plaintiff's allegations of wrongdoing center
upon" a document, the court may "properly refer to its contents"). Finally,
although Aetna did not initially submit a statement of undisputed facts as
required by Local Rule 3(g), it has now done so. Although the statement was
not appended to the initial motion, as required by Local Rule, I see no reason to
deny Aniero's motion on the basis of a procedural shortcoming that has now
been remedied.
43
44
Hudson's Reply Mem. at 1. I note, however, that the rule to be applied makes
no material difference for purposes of Hudson's motion. As discussed above,
the documents before the Court that are relevant to that motion may be
considered as integral to Aniero's complaint. Hudson contends that its motion
should be considered without reference to Aniero's affidavits. I see no reason,
however, to segregate the facts before me in discussing the two dispositive
motions at issue. While Aniero's affidavits, at times, flesh out the substance of
its complaint, they are not contradictory thereto so far as the claims against
Hudson are concerned. As I must grant a motion to dismiss unless "it is clear
that no relief could be granted under any set of facts that could be proved
consistent with the allegations" in the complaint, Hishon v. King & Spalding,
467 U.S. 69, 73, 104 S.Ct. 2229, 81 L.Ed.2d 59 (1984) (citing Conley v.
Gibson, 355 U.S. 41, 45-46, 78 S.Ct. 99, 2 L.Ed.2d 80 (1957)), the sharper
focus provided in the affidavits does not render invulnerable any claims which
would be subject to dismissal without their presence.
45
Finally, Hudson also seeks dismissal of General's claims. I will leave General's
status for the end of this opinion, after I have resolved all motions brought
against Aniero.
II. The Waiver Clause
46
47
The principles which govern a clause of this kind, under New York law, were
first set forth at length in Danann Realty Corp. v. Harris, 5 N.Y.2d 317, 184
N.Y.S.2d 599, 157 N.E.2d 597 (Ct.App.1959). In Danann, the purchaser of a
lease brought an action against the seller for fraud, alleging that the seller had
induced it to enter the transaction through false representations as to the
building's operating expenses and profitability. The defendant moved for
dismissal, citing the following clause in the contract:
48
The Purchaser has examined the premises agreed to be sold and is familiar with
the physical condition thereof. The Seller has not made and does not make any
Id. at 601. A second clause in the agreement reiterated this provision in similar
terms.
50
The New York Court of Appeals noted that a "general and vague merger
clause" is insufficient to warrant exclusion of parol evidence showing fraud. Id.
When a disclaimer of reliance is as specific as the one before the Danann court,
however, it "destroys the allegations in the plaintiff's complaint that the
agreement was executed in reliance upon... contrary oral representations." Id. at
602. A contrary result, the court found, would allow the plaintiff to
"deliberately misrepresent" its purported non-reliance in the contract, and
would make it impossible for "two businessmen dealing at arm's length to
agree that the buyer is not buying in reliance on any representations of the
seller as to a particular fact." Id. at 604.
51
The venerable principles established in Danann remain the law of New York
State. Thus, when a contract contains an "omnibus statement" disclaiming that
any representations outside the contract were made, it will not preclude a claim
for fraud. Manufacturers Hanover Trust Co. v. Yanakas, 7 F.3d 310, 315 (2d
Cir.1993) (citations omitted). When, however, the contracting party disclaims
"the existence of or reliance on specified representations," it will not be allowed
to claim it entered the contract in reliance thereon. Id. For a contract term to be
sufficiently specific under this standard, there need not be a "precise identity
between the misrepresentation and the particular disclaimer." Grumman Allied
Industries, Inc. v. Rohr Industries, Inc., 748 F.2d 729, 735 (2d Cir.1984).
Rather, "[t]he Danann rule operates where the substance of the disclaimer
provisions tracks the substance of the alleged misrepresentations,
notwithstanding semantical discrepancies." Id. The specificity requirement is
further relaxed when the contracting parties are "sophisticated business
people," and the disclaimer clause is the result of negotiations between them.
Citibank, N.A. v. Plapinger, 66 N.Y.2d 90, 495 N.Y.S.2d 309, 311-12, 485
N.E.2d 974 (Ct.App.1985). Thus, in Citibank, the Court enforced a guarantee of
corporate indebtedness which recited that it was absolute and unconditional
regardless of its enforceability or any available defense, although the Court
acknowledged that the term did not rise to the level of specificity described in
Danann. Id. at 312. Finally, there is one instance in which even an explicit
waiver will not be given effect "when the facts are peculiarly within the
knowledge of the party invoking the disclaimer." Banque Arabe Et
Internationale v. Md. Nat. Bank, 57 F.3d 146, 155 (2d Cir.1995). See also
Stambovsky v. Ackley, 169 A.D.2d 254, 572 N.Y.S.2d 672, 677 (1st Dep't
1991); Yurish v. Sportini, 123 A.D.2d 760, 507 N.Y.S.2d 234, 235 (2d Dep't
1986).
52
Turning to the case at hand, I concede that the Waiver Clause in the
Completion Agreement presents a close question. Nonetheless, I hold that it is
sufficiently specific to fall within the ambit of Danann. In reaching this
conclusion, I find instructive the holding of Galvatron Industries Corp. v.
Greenberg, 96 A.D.2d 881, 466 N.Y.S.2d 35 (2d Dep't 1983), cited by the
Second Circuit in Grumman as an exemplar of New York law. See 748 F.2d at
735-36. In Galvatron, the Court found that a contracting party could not assert a
fraud claim when it acknowledged, in the contract, that it had "full familiarity
with the financial condition ... of the corporation" and generally disclaimed
reliance on any representation by any signatory. 466 N.Y.S.2d at 36. Thus, a
general disclaimer that a party has relied on any representations of the other
signatory, coupled with the disclaiming party's assertion of familiarity with a
particular subject area, is specific enough to preclude a claim of reliance on
statements falling within that topic.
53
This describes, in essence, the contractual term I am faced with here. Aniero
gave a general disclaimer that it did not rely on any information provided by
Aetna, while specifically averring that it was familiar with the "current state of
the Construction Contract and requisites of performance thereunder." Aniero
now claims that, as a result of its reliance on the Project Documents, it was
unfamiliar with the full scope of the work it was required to complete. Such a
claim was specifically barred by the Waiver Clause.
54
I am further buttressed in this holding by the fact that the plaintiff is a business
sufficiently large and sophisticated to take on a project whose cost it estimated
at close to $19 million. Moreover, the contract states that both parties
participated in its drafting, Completion Agreement 15, and it is clear from the
specificity of the document that, to some extent, it was tailored to the matter at
issue, and was not merely a standard form agreement. See, e.g., Completion
Agreement 2 (defining Aniero's responsibility for change order work
unapproved as of date of Payment Requisition No. 15). In addition,
notwithstanding Aniero's assertions that it was forced to rush the submission of
its bid, about one month passed between the acceptance of that bid and the
finalization of the Completion Agreement. Aniero's sophistication and the
arms-length nature of the transaction compel application of the relaxed
Aniero contends that, whatever the scope of the disclaimer, it cannot be used by
Aetna to insulate itself from claims of fraud. Indeed, the Second Circuit has
clearly stated that "parties cannot use contractual limitation of liability clauses
to shield themselves from liability for their own fraudulent conduct." Turkish v.
Kasenetz, 27 F.3d 23, 28 (2d Cir.1994). This principle has been limited,
however, to situations in which "the party against which the disclaimer is
asserted is entirely unaware of the existence of the disclaimer," such as when it
is "inserted surreptitiously into the final draft of the contract." Grumman, 748
F.2d at 737. Aniero makes no allegation that this was the case here.
56
Thus, the Waiver Clause bars Aniero from claiming reliance on information
provided by Aetna unless it can demonstrate that its claims are based on facts
peculiarly within the knowledge of the defendant. To make this showing,
Aniero must prove that the Project was not readily accessible to investigation
by any interested party. See Banque Arabe, 57 F.3d at 157. I find that the extent
to which Aniero was able to investigate the Morris site is a matter sufficiently
in dispute to preclude granting summary judgment on this basis.
57
58
The presence of these warnings, however, is not dispositive of the scope of the
investigation Aniero was permitted to perform. Aniero avers that it did not
submit its bid for the Morris project in response to this initial invitation, but
rather did so in response to an emergency entreaty from Hudson made later. See
Crevani Aff. 29. It was in connection with the latter request, Aniero contends,
that Hudson provided Aniero with the allegedly misleading documentation at
the center of this litigation.7 Id. 30. Inasmuch as the statements in the bid
materials are binding at all, they certainly cannot be conclusive as to bids
submitted in response to an entirely different solicitation.8
59
Aniero was permitted to carry out prior to the Completion Agreement's signing.
In its memorandum of law, however, Aetna asserts that Aniero was "afforded
unfettered access to the construction site, the construction documents, the
owner, the defaulted contractor, and all subcontractors." Aetna's Mem. at 28.
Even if this unsworn assertion could be considered on a motion for summary
judgment, it is contradicted by Aniero's submissions. According to the Hanjis's
Affidavit, he was not allowed to independently explore the project site, but
rather were taken on a limited tour of selected areas, Hanjis Aff. 21-22, and
was not allowed to review Carlin's records concerning the project. Id. 31-32.
60
Hanjis's affidavit is spotty in some respects. It does not make clear when his
tour was made, nor does it specifically assert that either Aetna or Delta actually
sought permission to investigate further. Moreover, the tour was, according to
Hanjis, conducted by KBF and SCA, not by Aetna. Nonetheless, in the absence
of any contrary affidavits, Hanjis's assertions are sufficient to raise triable issues
of fact as to whether Aniero was denied access to information in Aetna's and
Hudson's possession regarding the state of the project.
61
62
Finally, I hold that principles articulated above in regard to Aetna hold true for
Hudson as well. Although the Waiver Clause makes specific reference only to
Aetna, Aniero's fraud claims against Hudson state explicitly that Hudson was
acting as Aetna's agent. See, e.g., Complaint 252. A Waiver Clause of the
kind at issue here renders non-existent authorized representations made by a
contracting party's agents. See Wittenberg v. Robinov, 9 N.Y.2d 261, 213
N.Y.S.2d 430, 431, 173 N.E.2d 868 (Ct.App.1961). Aniero may evade
application of this clause as to Hudson, however, if it can show that Hudson's
statements were not authorized by Aetna. Id. at 431-32.
63
In light of the above, I conclude that although the Waiver Clause meets the
specificity requirements of Danann and its progeny, it does not prohibit Aniero
from asserting that it reasonably relied on misrepresentations by Aetna and
Hudson, if it can show that the assertions relied on concerned information
uniquely in Hudson's and Aetna's possession, or, in the case of Hudson, if it can
demonstrate that Hudson was acting outside the scope of its agency
relationship. I will now proceed to address, in turn, the specific causes of action
alleged by Aniero's complaint.
64
1. Rule 9(b)
65
Aetna and Hudson argue that Aniero's fraud claims are not pled with sufficient
particularity to meet the requirements of Fed.R.Civ.P. 9(b). That rule provides:
"In all averments of fraud or mistake, the circumstances constituting fraud or
mistake shall be stated with particularity. Malice, intent, knowledge, and other
condition of mind of a person may be averred generally." As Aetna's motion
has been deemed to be seeking summary judgment, I may consider the
affidavits filed by Aniero in assessing whether its allegations are sufficient to
state a claim for fraud. See Connors v. Hallmark & Son Coal Co., 935 F.2d
336, 344 (D.C.Cir.1991); Ellis v. Carter, 291 F.2d 270, 275-76 (9th Cir.1961).
66
67
Rule 9(b) also requires that the plaintiff "allege the time, place, speaker and
2. Fraudulent Inducement
69
To state a claim for fraudulent inducement under New York law, a plaintiff
must show: (1) a representation of material fact, (2) which was untrue, (3)
which was known to be untrue or made with reckless disregard for the truth, (4)
which was offered to deceive another or induce him to act, and (5) which that
other party relied on to its injury. Helmsley-Spear v. Westdeutsche Landesbank,
692 F.Supp. 194, 203 (S.D.N.Y.1988)(citing Jo Ann Homes at Bellmore, Inc. v.
Dworetz, 25 N.Y.2d 112, 302 N.Y.S.2d 799, 803, 250 N.E.2d 214
(Ct.App.1969)). In its complaint, Aniero alleges that the Project Documents
"materially misrepresented" the status of the work that Carlin had performed on
the Project, the amount of work remaining to be completed, and the extent of
remediation done by Carlin. Complaint 37. These broad allegations are, by
themselves, insufficient to meet the requirements of Rule 9(b). Cf. Luce v.
Edelstein, 802 F.2d 49, 54 (2d Cir.1986)(general claims that plaintiff misstated
net worth does not pass muster under Rule 9(b)). Moreover, although Aniero
provides detailed lists of "overstated work" and "phantom work" approved by
the SCA, Complaint 371-m, it nowhere indicates that these data bear any
connection to the information set forth in the Project Documents, which form
the basis for Aniero's fraud claims. Indeed, a review of the Project Documents
does not reveal any clear connection between the information set forth thereon
and the work Aniero claims to have been overstated in its complaint.11 See
Hanjis Aff. exs. 1-3.
70
71
Moreover Aniero does not claim that the Project Documents were prepared by
either Hudson or Aetna.12 Complaint 31. It cannot be said that these
documents constituted fraudulent statements of the moving defendants unless
those defendants falsely represented that the documents were accurate
representations of the project, or provided the documents in such a manner that
could be construed as vouching for the truth of the data they contained. Cf.
Restatement (Second) of Torts 525 cmt. b (1977) (misrepresentation denotes
not only words, but also "conduct which amounts to an assertion not in
accordance with the truth"). Aniero, however, studiously avoids any such
portrayal of defendant's actions, restricting itself to conclusory allegations that
the Project Documents "purportedly presented an accurate picture," Complaint
1, or were "relied on by Aniero as accurately depicting the financial status of
the Project." Complaint 31.
72
I find, therefore, that Aniero has not spelled out its claim of fraudulent
inducement with sufficient specificity under Rule 9(b), and dismiss this claim.
Dismissals made pursuant to this Rule, however, are "almost always"
accompanied by a grant of leave to amend, unless the plaintiff has had a prior
opportunity to amend its complaint or the allegations were made after full
discovery in a related case. Luce, 802 F.2d at 56. Neither of these
considerations is applicable here. Moreover, while the liberal provisions for
amendment under the Federal Rules are restricted following the filing of a
motion for summary judgment and the completion of discovery, see Ansam
Assocs., Inc. v. Cola Petroleum Ltd., 760 F.2d 442, 446 (2d Cir.1985), in the
instant case, it appears that discovery had barely begun at the time the
defendants' motions were filed. See Walton v. Waldron, 886 F.Supp. 981, 984
(N.D.N.Y.1995)(leave to amend granted after filing of summary judgment
motion where "very little discovery" completed). I decline, moreover, to
conclude that plaintiff should not be permitted to amend its complaint because
it had the opportunity to rectify the shortcomings therein in the affidavits
submitted in opposition to the Aetna's summary judgment motion. Cf. Bay State
Mill. Co. v. Terranova Bakers Supplies Corp., 871 F.Supp. 703, 707
(S.D.N.Y.1995)(denying leave to amend, in part, where evidence submitted in
opposition to summary judgment did not clear up vague aspects of the
complaint). In the instant case, Aetna's Rule 9(b) challenge read, in pertinent
part, as follows: "Plaintiff, in pleading fraud, has failed to comply with Rule
9(b), inter alia, by failing to ascribe a single false or misleading statement to
Aetna." Aetna's Mem. at 33. Because this argument did not place Aniero on
notice of the precise nature of the defects which have led me to dismiss this
claim, I will not deem Aniero to have had sufficient opportunity to remedy
those failings in its affidavits.
73
3. Fraudulent Concealment
74
75
A duty to disclose arises in one of three circumstances: where the parties are in
a fiduciary relationship; under the "special facts doctrine," where "one party
possesses superior knowledge, not readily available to the other, and knows that
the other is acting on the basis of mistaken knowledge," Aaron Ferer & Sons
Ltd. v. Chase Manhattan Bank, 731 F.2d 112, 123 (2d Cir.1984); or where a
party has made a partial or ambiguous statement, whose full meaning will only
be made clear after complete disclosure, Brass v. Am. Film Technologies, Inc.,
987 F.2d 142, 150 (2d Cir.1993). Aetna again maintains that Aniero's warranty
in the Waiver Clause that it was fully familiar with the Project, and the
requirement set forth in the December 22 bid materials that all bidders make
full investigation of the site, preclude application of the special facts doctrine to
this case. For reasons discussed at length above, each of these arguments is
unavailing, as the question of whether Aetna and Hudson had "superior
knowledge" of the state of the Project cannot be resolved on summary
judgment.
76
This claim, however, like that for fraudulent inducement, must pass muster
under Rule 9(b). Aniero bases this cause of action on the absence of the New
Protocol and other change orders from the Change Order List. see Complaint
40-41. It also asserts that the Punchlists, which purported to set forth the
defective work which the completion contractor would be required to correct,
"grossly and materially misstated the quantity and scope" of that work, and that
Payment Requisition No. 15 "omitted numerous change orders." Complaint
37c-d. A list of specific defects in Carlin's work that Aniero maintains were
concealed from it by the defendants in general, and by Aetna and Hudson in
particular, is included in the complaint. Complaint 37n, 151, 251.
77
I find that these allegations suffer from the same defects present in plaintiffs'
fraudulent inducement claims. Aniero never contends that Project Documents
were prepared by Hudson or Aetna, and it affirmatively states that KBF
compiled the Punchlists. Complaint 31. This does not preclude the possibility
that the documents were presented to Aniero in such a manner from which it
could reasonably believe that they were exhaustive. There is nothing on the
face of the documents, however, which gives any such indication; indeed, the
Change Order List appears to indicate the opposite, as there are large gaps in
the numbers that identify the change orders cataloged thereon. While Hanjis
states that he was assured by KBF and SCA that the all defective work was set
forth on the punch list, Aniero never makes such an allegation against Aetna or
Hudson.13 The mere assertion that the moving defendants provided these
documents, by itself, does not indicate the nature of their fraudulent conduct.
78
In short, Aniero has failed to set forth the precise circumstances in which it
78
In short, Aniero has failed to set forth the precise circumstances in which it
received the Project Documents, and how those circumstances gave rise to a
reasonable belief on plaintiff's part that they were comprehensive. As a result,
this claim is dismissed under Rule 9(b) as to both Hudson and Aetna, with leave
to amend so that Aniero may specify defendants' fraudulent conduct with
greater precision.
B. Negligent Misrepresentation
79
80
For reasons set forth in III.A, supra, the allegations in Aniero's complaint
concerning the representations made to it by the moving defendants are not
presented with sufficient specificity to establish a claim for purposes of Rule
9(b). Moreover, as discussed above, Aniero's complaint clearly states that the
Project Documents were not created by Hudson, or drawn up for the purpose of
soliciting Aniero's bid. Under New York Law, however, a negligent
representation must be made "for the very purpose of inducing action," and the
action may not be merely "an indirect or collateral consequence thereof."
Prudential Insurance Co. v. Dewey Ballantine, Bushby, Palmer & Wood, 80
N.Y.2d 377, 590 N.Y.S.2d 831, 834, 605 N.E.2d 318 (Ct.App.1992) (citation
omitted). As Aniero has failed to allege with specificity any representation
made to it by the instant movants to induce its entry into the Completion
Agreement, I dismiss this claim under Rule 9(b).
81
Anderson LaRocca Anderson, 73 N.Y.2d 417, 541 N.Y.S.2d 335, 338, 539
N.E.2d 91 (Ct.App.1989), or if the defendant has fiduciary obligations to the
plaintiff, Stewart v. Jackson & Nash, 976 F.2d 86, 90 (2d Cir.1992); see also
Banque Arabe, 57 F.3d at 158 (negligent misrepresentation requires "a special
relationship of trust or confidence between the parties").15 A relationship is
considered "so close as to approach that of privity" when the following criteria
are met: 1) the defendant makes a statement with the awareness that the
statement was to be used for a particular purpose; 2) a known party or parties
rely on this statement in furtherance of that purpose; and 3) there is some
conduct by the defendant linking it to the party or parties and evincing
defendant's understanding of their reliance. Ossining Union, 541 N.Y.S.2d at
339, 539 N.E.2d 91 (citing Credit Alliance Corp. v. Arthur Andersen & Co., 65
N.Y.2d 536, 493 N.Y.S.2d 435, 483 N.E.2d 110 (Ct.App.1985)). In contrast,
where the statement at issue is directed at a "faceless of unresolved class or
persons," no duty of care arises. See White, 401 N.Y.S.2d at 477, 372 N.E.2d
315.
82
83
84
became apparent just prior to the commencement of the litigation at hand, the
delay would not be unreasonable. In the absence of any evidence on this point, I
will proceed to the merits of Aniero's claims.
85
Where the parties have entered into a contract because of a mutual mistake, that
contract "will generally be avoidable." Alden Auto Parts Warehouse, Inc. v.
Dolphin Equipt. Leasing Corp., 682 F.2d 330, 333 (2d Cir.1982). In contrast, a
party's unilateral mistake will not provide a basis for rescission unless it is
accompanied by some fraud committed by the other contracting party. See
National Union Fire Ins. Co. v. Walton Ins. Ltd., 696 F.Supp. 897, 902
(S.D.N.Y.1988)("Unilateral mistake without fraud or wrongful conduct,
however, is not a sufficient ground for contract rescission or reformation.");
Brandwein v. Provident Mutual Life Ins. Co., 3 N.Y.2d 491, 168 N.Y.S.2d 964,
967, 146 N.E.2d 693 (Ct.App.1957)("classic" grounds for reformation of
contract are "mutual mistake of the parties" or "mistake on plaintiff's part and a
fraud by defendant"). To rescind a contract because of unilateral mistake,
therefore, the plaintiff must show "misrepresentation, concealment or
nondisclosure of a material fact; an intent to deceive; and an injury resulting
from justifiable reliance by the aggrieved party." Allen, 945 F.2d at 44.
86
Aetna argues that Aniero's allegation of mutual mistake is inconsistent with its
fraud claims, as Aetna could not have deliberately misled the plaintiff if it was
unaware of the facts which it fraudulently misrepresented or concealed. Aniero
responds by citing its right to plead in the alternative. See Fed.R.Civ.P. 8(e)(2).
As a general matter, Aniero is correct. A party may "plead two or more
statements of a claim, even within the same count, regardless of consistency."
Henry v. Daytop Village, Inc., 42 F.3d 89, 95 (2d Cir.1994). Aniero cannot rely
on this principle, however, where it must state allegations which are at odds
with each other in order for it to make out all the elements of an individual
claim. This is precisely the case here.
87
To demonstrate that it entered into the contract as a result of its mistaken belief
concerning the validity of the Project Documents, Aniero must escape the
application of the Waiver Clause. As that clause stated that Aniero had
independently made itself familiar with the state of the Project, Aniero cannot
claim that it entered into the Completion Agreement as a result of its mistaken
reliance on the Project Documents so long as that clause is in force. For reasons
discussed above, the Waiver Clause will apply unless Aniero can show that the
information upon which it relied was "peculiarly within the knowledge" of the
defendant. See supra pp. 576-80. Such a showing, however, would vitiate
Aniero's assertion that Aetna was mistaken as to the state of the Project as set
forth in the Hudson documents. In short, Aniero's mutual mistake claim is at
war with itself, and cannot survive a motion for summary judgment.
88
89
Aniero presents two claims against Aetna arising out of the latter's purported
violation of the Completion Agreement. First, plaintiff alleges that Aetna
breached the contract by "failing to pay Aniero the amounts due and owing ...
for work duly performed in accordance with the Completion Agreement."
Complaint 134. Second, it charges that this failure constituted an anticipatory
breach of the Agreement, demonstrating Aetna's intent not to perform any
further obligations thereunder. Id. 138-39.
90
91
As stated supra, Gillen contends in his affidavit filed on Aetna's behalf that
Aniero presented Aetna with five requisitions for payment during the time it
was engaged on the Project. According to Gillen, Aetna paid Aniero for four of
these, but did not make payment of the fifth because Aniero had then ceased to
perform its part on the Agreement. Gillen Aff. 19. Aetna appended to its
motion copies of the requisitions alluded to, and of the checks made out to
Aniero for the amounts requested. Lambert Aff. ex. 10.
92
Crevani, in his affidavit, states that Aniero's request for payment for the month
of October was approved by SCA, and Aetna drew up a check for the requested
amount. According to Crevani, the check was provided to Aetna's
representative at the site "on or about December 21, 1994," the day before
Aniero abandoned the project, but was never turned over to Aniero. Crevani
Aff. 61. Crevani also claims that Aniero received no compensation for change
order work for which it was substantially responsible. Id. 60-61. Aetna, for
its part, has made no evidentiary showing regarding the change order payments
made to Aniero. Furthermore, Crevani contends that Aniero received no
compensation whatsoever for the work it performed in November and
December, although he does not make clear what steps Aniero took, in
accordance with the contractual procedures, to insure that such payment was
made.
93
The parties' filings demonstrate that there are unresolved issues of fact material
to Aniero's breach of contract claim. Aniero's affiant alleges facts which, if
proved at trial, would show that Aetna had not met its obligations under the
Completion Agreement. That Agreement required Aetna to compensate Aniero
for change order work it completed. Aniero has presented uncontested,
admissible evidence that it did not receive the requisite funds, while Aetna,
which bears the burden of demonstrating the absence of any disputed issue of
fact, has adduced no proof on this issue. Furthermore, Crevani's affidavit places
in dispute Aetna's contention that it made all the disbursements required in
response to Aniero's requisitions. Therefore, summary judgment will be denied
as to this cause of action.
94
Co., 894 F.2d 516, 523 (2d Cir.1990)(quoting REA Express, Inc. v. Interway
Corp., 538 F.2d 953, 955 (2d Cir.1976)), or otherwise advances an untenable
interpretation of the contract.16 SPI Communications, Inc. v. WTZA-TV Assoc.
Limited Partnership., 229 A.D.2d 644, 644 N.Y.S.2d 788, 790 (3rd Dep't
1996); see also Hampton v. District Council 37 Health & Sec. Plan, 97 Misc.2d
324, 411 N.Y.S.2d 124, 127 (N.Y.City Civ.Ct.1978) (interpretation must be on
matter of "essential substance").
95
Aniero's complaint alleges only one specific act by Aetna which purportedly
gave rise to the anticipatory breach its "failure to pay Aniero for work duly
performed." Complaint 138. According to Aniero, this act made performance
of the Completion Agreement impossible, and constituted an unequivocal
repudiation of Aetna's contractual obligations. Id.
96
Aetna's alleged failure to make full payments on the contract, however, cannot
be construed as an action by which it manifested an intent to fully breach the
Completion Agreement. In Crevani's own affidavit, he claims that when Aetna
received the December 21 check, its representative at the project site informed
Aniero's employees that he would hold the check until "after the holidays."
Crevani Aff. 63. Whatever the validity of this action under the Agreement,
this statement evinces a belief that the contract was to remain in place. For a
party's action to constitute repudiation, it must "make it actually or apparently
impossible for [that party] to perform." Restatement (Second) of Contracts
250 cmt. c (1981). The Restatement gives as an example of such behavior an
owner who contracts to sell a piece of land, and then sells the same to another
buyer prior to the contract's implementation. Id. illus. 5. In light of the
statement cited by Crevani, Aetna's purported failure to make timely payments
does not reveal the necessary intent to render performance impossible.
97
Aniero appears to contend that Aetna's failure to make timely payments was
equivalent to insisting upon terms not contained in the Completion Agreement.
See Aniero's Mem. at 53-55. The cases in which such an insistence was found
to constitute anticipatory breach, however, concerned instances where one party
demanded that the contract be governed by terms contrary to those agreed
upon. See REA Express, 538 F.2d at 955; Wester v. Casein Co. of America, 206
N.Y. 506, 100 N.E. 488 (1912); Estes v. Curtiss Aeroplane & Motor Corp., 191
A.D. 719, 182 N.Y.S. 25 (4th Dep't 1920), aff'd per curiam, 232 N.Y. 572, 134
N.E. 576 (1922). By doing so, that party "repudiated a material provision of the
contract," Estes, 182 N.Y.S. at 26, thereby revealing its intent not to perform.
98
Aniero, however, does not contend that Aetna demanded that the contract be
modified. Instead, it asserts that Aetna's performance fell short of the
To state a claim for tortious interference with contract under New York law, a
plaintiff must show that there existed a valid contract between the plaintiff and
a third party, the defendant knew of the contract, and the defendant
intentionally and improperly interfered therewith. Enercomp Inc. v. McCorhill
Pub., Inc., 873 F.2d 536, 541 (2d Cir.1989). Although the nature of Aniero's
claim appears to have changed during the course of this litigation, no version
advanced by plaintiff meets these elements.
100 In its complaint, Aniero alleges that Aetna wrongfully "assert[ed] the right to
receive payment for change order work with the intent and knowledge that by
doing so Aetna would cause SCA to commit a material and substantial brief of
SCA's contractual relationship with Aniero under the Carlin Contract."
Complaint. 170. Aniero claims that Aetna acted with the intent of causing
such a breach, but never asserts that SCA did, in fact, breach as a result of
Aetna's conduct.
101 These allegations, as they are formulated in the complaint, face a formidable
obstacle: The Completion Agreement states explicitly that "[a]ll payments
made by the SCA with respect to the Construction [i.e. Carlin] Contract,
whether for base contract work or change order work, are to be paid to Aetna."
Lambert Aff. ex. 9 6. Aetna then had the obligation to remit to Aniero
payments for the work the latter has completed. Id. 5.
102 A claim for tortious interference with contract cannot rest on conduct that is
"incidental to some other lawful purpose." Costanza Construction Corp. v. City
of Rochester, 135 A.D.2d 1111, 523 N.Y.S.2d 707, 708 (4th Dep't 1987); see
also Felsen v. Sol Cafe Mfg. Corp., 24 N.Y.2d 682, 301 N.Y.S.2d 610, 613-14,
249 N.E.2d 459 (Ct.App.1969)(quotation omitted)("Procuring the breach of a
contract in the exercise of an equal or superior right is ... justification for what
would otherwise be an actionable wrong"). As the complaint alleges nothing
more than Aetna's exercise of its contractual right, it cannot support a claim for
tortious interference with contract.
103 Aniero has altered the substance of its tortious interference claim in the
affidavits it has filed in opposition to summary judgment. Crevani, in his
affidavit, acknowledges that Aetna "was to be the conduit," under the
Completion Agreement, for change order payment. Crevani Aff. 59.
Nonetheless, he asserts that Aetna kept moneys from such payments to which
Aniero was entitled. Id. 59. Aniero's legal memorandum attempts to defend
this cause of action as it is stated in the Crevani Affidavit. See Aniero's Mem.
at 49.
104 Aniero's attempt to amend its complaint without leave of the Court must
ultimately fail. Even had Aniero introduced its current characterization of this
claim in its initial pleadings, I would have found it to be meritless. Aniero's
reformulation is entirely duplicative of its breach of contract claim; it alleges
nothing more than Aetna's failure to comply with the terms of the Completion
Agreement. Moreover, Crevani does not assert that SCA, the party with which
it was contracting, breached its obligations under the contract at issue. Instead,
he claims that SCA approved the payments destined for Aniero, and only
Aetna's misconduct prevented them from reaching the plaintiff. Crevani Aff.
60-61. Absent a showing that Aetna's conduct ultimately led to a breach,
Aniero's latest allegations cannot be read to state a proper claim for tortious
interference. See Jack L. Inselman & Co., Inc. v. FNB Financial Co., 41 N.Y.2d
1078, 396 N.Y.S.2d 347, 349, 364 N.E.2d 1119 (Ct.App.1977) ("In order for
the plaintiff to have a cause of action for tortious interference of contract, it is
axiomatic that there must be a breach of that contract by the other party.").
V. Claims Against Hudson Only
105 A. Breach of Contract Third Party Beneficiary
106 Aniero alleges, upon information and belief, that Hudson entered into an
agreement with Aniero, which required it, inter alia, to provide accurate
information to prospective bidders for the Morris Project. Complaint 242.
Aniero claims to be a third-party beneficiary of this contract, and asserts that
Hudson has failed to carry out its obligations thereunder. Id. 245-47.
According to Aniero, this gives rise to a breach of contract action against
Hudson.
107 In its answer, Hudson admitted that it "was retained by Aetna to provide surety
consulting services, including the preparation of a bid package and to perform
bond claim services." Answer 242. It maintains, however, that Aniero was
merely an incidental beneficiary of its agreement with Aetna. Hudson Mem. at
6.
108 To prevail on a claim for breach of contract as a third-party beneficiary, the
plaintiff must establish the existence of a valid and binding contract between
other parties; that the contract was intended for plaintiff's benefit; and the
benefit was immediate, and not incidental, so as to "indicate duty to compensate
[the plaintiff] if the benefit is lost." Burns Jackson Miller Summit & Spitzer v.
Lindner, 59 N.Y.2d 314, 464 N.Y.S.2d 712, 722, 451 N.E.2d 459
(Ct.App.1983). Hudson may well be right in its contention that whatever
benefits Aniero was to have derived from Hudson's contract with Aetna were
merely incidental to that agreement.17 Its claims however, can only be evaluated
by reviewing whatever documents, if any, memorialize the understanding
between the two contracting parties. Hudson, which presumably has access to
these materials, has failed to provide them to this Court.18
109 Nonetheless, Hudson maintains that the terms of the Waiver Clause make it
apparent that Aetna had no intent to benefit Aniero in its agreement with
Hudson. Reply Mem. at 4. According to this argument, the Completion
Agreement conferred upon Aniero the responsibility to independently
investigate the conditions of the Project, and is therefore inconsistent with an
intent by Aetna to benefit Aniero by insuring that it be provided with accurate
information.
110 While the Waiver Clause calls Aniero's contentions into question, it does not
allow for this issue to be resolved on a motion to dismiss. That clause disclaims
representations by Aetna alone, and makes no reference to Hudson. Completion
Agreement 18. Although Aniero's fraud claims are premised on the notion
that Hudson acted in Aetna's behalf, it is permissible for Aniero to plead in the
alternative, for purposes of this claim, that Hudson violated its understanding
with Aetna by providing Aniero with false information. Faced with a record that
lacks the relevant contractual documents, or any other attestations as to the
nature of the agreement between Hudson and Aetna, I cannot determine the
accuracy of such a theory on a motion brought under Rule 12(b)(6). Therefore,
I deny Hudson's motion to dismiss this claim.
B. Negligence
111 Aniero's complaint sets forth a claim against Hudson for "negligence,"
premised on Hudson's purported failure to investigate the Project and provide
Aniero with accurate documentation concerning its status. Complaint 269276. This cause of action is entirely duplicative with Aniero's negligent
may be alleged, "for the purpose of showing that a wrong was committed
jointly by the conspirators and that, because of their common purpose and
interest, the acts of one may be imputed to the others." Grove Press, Inc. v.
Angleton, 649 F.2d 121, 123 (2d Cir.1981). Therefore, Aniero maintains, its
conspiracy claim "serves a proper purpose." Aniero's Br. at 59.
118 The principles set forth in Grove Press do not permit a conspiracy cause of
action to survive a motion to dismiss so that it may serve a "proper purpose;"
they explain the role a factual allegation of conspiracy plays in a complaint.
Similarly, the proposition that conspiracy may be alleged "to connect a
defendant to an otherwise actionable tort," Buccieri v. Franzreb, 201 A.D.2d
356, 607 N.Y.S.2d 330, 333 (1st Dep't 1994), does not allow a plaintiff to
reallege a tort asserted elsewhere in the complaint in the guise of a separate
conspiracy claim. As this is precisely what Aniero has attempted to do, and as
the purported purpose of its conspiracy claim is already advanced by the
allegations of conspiracy set forth elsewhere in its complaint, Complaint 6770, this claim is dismissed as to all defendants. See Wachtler v. County of
Herkimer, 35 F.3d 77, 82 (2d Cir.1994)(district court may dismiss a complaint
sua sponte, for failure to state a claim, as to non-moving defendants).
VII. Punitive Damages
119 In its complaint, Aniero seeks punitive damages against Aetna and Hudson on
its fraud and tortious interference claims. Aetna argues that this demand is
deficient as a matter of law. Because the claims on which Aniero has sought
this relief have been dismissed, Aetna's application is moot. Aetna may, of
course, renew its objection should Aniero choose to seek such damages in an
amended complaint.
VIII. General
120 To this point, I have dealt only with the defendants' motions as they concern
Aniero. I turn now to consider the impact of these motions on General, whose
place in the instant litigation derives solely from its role as Aniero's surety.
121 As is made apparent in the Background section of this opinion, General's
motion to intervene has been rendered moot by this Court's order consolidating
Aetna's Eastern District action against General with the case brought here by
Aniero. As a result of that order, General's third party complaint and
counterclaim in the former action are now before this Court. Those pleadings
raise every factual allegation and legal claim that General sought to present as
contained in its agreement with Aetna, that it was "independently familiar" with
the Project. I determined that Aniero could not evade the impact of this
contractual clause unless it could show that Aetna had withheld from Aniero
information uniquely in Aetna's possession. This threshold finding, however,
would vitiate Aniero's claim that the mistaken impression it held as to the
project's status was shared by Aetna. As a result, I found this claim to be "at
war with itself," and granted Aetna's summary judgment motion.
141 General now argues that the Waiver Clause only addressed Aniero's reliance on
statements made by Aetna. Thus, according to General, both Aniero and Aetna
could have been mistaken as to the accuracy of the Project Documents, thereby
causing both parties to misapprehend the requisites of performance under the
contract.
142 I need not decide if General's construction of the Completion Agreement is
correct. Rather, I conclude that the factual allegations in General's complaint, as
well as the evidence presented by Aniero in its opposition to the summary
judgment motion, are directly contrary to the argument General now seeks to
advance. In its counterclaim, General cites allegations by Aniero stating that
Aetna "had complete and unfettered access to the Project Site as well as to
Carlin's former project manager," Counterclaim 44; that employees for Carlin
had disclosed to Aetna "the Phantom Work, the Overstated Work, the
Concealed Defective Work and the Phantom Materials," id. 45; and that Aetna
"had knowledge of the selective and limited documentation made available to
Aniero," id. 46. These allegations were repeated in the Crevani affidavit
presented by Aniero in opposition to Aetna's motion, Crevani Aff. 45-48,
and in General's prior brief, General's Mem. in Opp. to Sum. J. at 11.
143 Aniero clearly could not proceed on the mutual mistake claim as constructed by
General. Although, as I acknowledged in my prior opinion, plaintiffs are
permitted to plead in the alternative, Slip Op. at 39 (citing Fed.R.Civ.P. 8(e)
(2)), this rule "does not excuse a party from being bound by its own explicit
admissions of fact." Morse/Diesel, Inc. v. Fidelity and Deposit Co. of
Maryland, 763 F.Supp. 28, 32, modified on other grounds, 768 F.Supp. 115
(S.D.N.Y.1991). The mutual mistake claim now before the court is inconsistent
with Crevani's sworn submissions, and thus Aniero could not save it by resort to
principles of alternative pleading.
144 The question presented by General's present filing is whether it may, as a
surety, proceed on a claim which could not be successfully asserted by its
principal. On the facts of the instant case, I find it cannot. General's pleadings
are, in their entirety, "based upon allegations made and claims asserted by ...
156 v.
157 New York City School Construction Authority; Kreisler Borg Florman General
Construction Company, Inc.; Acrom Construction Services, Co., Inc.; Kreisler
Borg Florman General Construction Company, Inc. and Acrom Construction
Services Co., Inc., Construction Managers, A Joint Venture; David M. Pharis
and S.T. Hudson d/b/a Hudson International; Aniero Concrete Co., Inc.;
Crevani Construction Co., Inc.; Vertolomo's Inc.; Crevani Bros. Realty Co.,
Inc.; Crevani Farms 1979 Trust Agreement; Stephen G. Crevani, Jr. Trust
Agreement; Stephen G. Crevani, Jr. Business Buy-Pass Trust Agreement;
Stephen G. Crevani; and Stephen G. Crevani, Jr., Third-Party Defendants.
158 No. 94 CIV. 9111, 95 CIV. 3506.
159 March 30, 1998.
MEMORANDUM OPINION AND ORDER
160 HAIGHT, Senior District Judge.
161 The facts and circumstances of this case are set forth in Memorandum Opinions
and Orders dated January 3, 1997 and February 27, 1997, familiarity with
which is assumed. In the January 3 Opinion, I granted summary judgment for
defendant The Aetna Casualty and Surety Company ("Aetna") against certain
claims brought by plaintiff Aniero Concrete Company, Inc. ("Aniero"). In the
February 27 Opinion, I granted Aetna's summary judgment motion as to
identical claims brought by Aniero's surety, third-party plaintiff General
showing that there is a genuine issue for trial." Fed.R.Civ.P. 56(e). "The nonmovant cannot `escape summary judgment merely by vaguely asserting the
existence of some unspecified disputed material facts,' ... or defeat the motion
through `mere speculation or conjecture.'" Western World Ins. Co. v. Stack Oil,
Inc., 922 F.2d 118, 121 (2d Cir.1990) (citations omitted). While the party
resisting summary judgment must show a dispute of fact, it must also be a
material fact in light of the substantive law. "Only disputes over facts that might
affect the outcome of the suit under the governing law will properly preclude
the entry of summary judgment." Anderson v. Liberty Lobby, Inc., 477 U.S.
242, 248, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986).
165 II. The Cross-Motions Filed by Aetna, Aniero, and General
A. Summary Judgment Motions
166 Aniero's cross-motion seeks an order pursuant to Rule 56 dismissing Counts 1,
2, and 3 of the counterclaims filed by the SCA on the ground that the
Completion Agreement between Aetna and Aniero is invalid. General's crossmotion seeks an order pursuant to Rule 56 dismissing Aetna's complaint on the
same ground. In its November 6, 1997 motion, Aetna seeks summary judgment
in its favor against General on the claims asserted in Aetna's amended
complaint. For the reasons that follow, Aniero's cross-motion is granted to the
extent that it seeks dismissal of the SCA's counterclaims against Aniero,
General's cross-motion seeking dismissal of Aetna's complaint is granted, and
Aetna's motion seeking summary judgment in its favor on the claims asserted in
its amended complaint is denied.
1. Effectiveness of Completion Agreement
167 In their cross-motions, Aniero and General contend that the Completion
Agreement executed between Aniero and Aetna is invalid because Aetna failed
to obtain the SCA's written consent to Aetna's assignment of the Carlin
Contract,1 an express condition precedent to the formation of the contract.
168 Paragraph 24 of the Completion Agreement provides:
169 SCA Consent Required. This Completion Agreement shall have effect only if
and when the SCA consents in writing to the assignment of the [Carlin]
Contract to Aniero and Aniero's assumption of said [Carlin] Contract. Absence
[sic] such consent, Aetna shall have no liability hereunder.
170 The New York Court of Appeals explained the significance of such a condition
in Oppenheimer & Co. v. Oppenheim, Appel, 86 N.Y.2d 685, 636 N.Y.S.2d
734, 660 N.E.2d 415 (Ct.App.1995). In its words:
171 A condition precedent is `an act or event, other than a lapse of time, which,
unless the condition is excused, must occur before a duty to perform a promise
in the agreement arises' (Calamari and Perillo, Contracts 11-2, at 438 [3d
ed.]). Most conditions precedent describe acts or events which must occur
before a party is obliged to perform a promise made pursuant to an existing
contract, a situation to be distinguished conceptually from a condition precedent
to the formation or existence of the contract itself. In the latter situation, no
contract arises `unless and until the condition occurs' (Calamari and Perillo,
Contracts 11-5, at 440 [3d ed]).
172 Id. at 737 (citations omitted); see also Kapson Constr. Corp. v. ARA Plumbing
& Heating Corp., 227 A.D.2d 484, 642 N.Y.S.2d 701, 703 (1st Dep't 1996).
According to Aniero and General, no contract arose between Aniero and Aetna
because Aetna never obtained the SCA's written consent to the assignment.
173 Resisting this argument, Aetna contends that it secured the SCA's written
consent to the assignment and that even if it failed to secure the SCA's written
consent, the condition was excused through a unilateral waiver or substantial
performance.
174 To evaluate these contentions, it is first necessary to resolve a dispute between
the parties as to the proper interpretation of the term "assignment" as used in
the Completion Agreement. Black's Law Dictionary 119 (6th ed.1990) defines
"assignment" as "[a] transfer or making over to another of the whole of any
property, real or personal, in possession or in action, or of any estate or right
therein." See also Corbin, Assignment of Contract Rights, 74 U. Penn. L.Rev.
207 (1926). Aniero and General argue that "assignment" is used in this manner
in the Completion Agreement; accordingly, they maintain that the parties
intended to transfer contractual rights from Carlin and Aetna to Aniero. Aetna
contends that the term "assignment" in the Completion Agreement instead
means "delegation" that is, a transfer of duties only.
175 In interpreting a written contract, a trial court's primary goal is to effectuate the
intent of the parties as manifested by the language used in the contract. See
Seiden Assocs. v. ANC Holdings, Inc., 959 F.2d 425, 428 (2d Cir.1992). As the
Second Circuit has explained:
176 When the question is the contract's proper construction, summary judgment
may be granted when its words convey a definite and precise meaning absent
any ambiguity. Where the language used is susceptible to differing
interpretations, each of which may be said to be as reasonable as another, and
where there is relevant extrinsic evidence of the parties' actual intent, the
meaning of the words become an issue of fact and summary judgment is
inappropriate....
177 Id. Contract language is ambiguous if it is "capable of more than one meaning
when viewed objectively by a reasonably intelligent person who has examined
the context of the entire integrated agreement and who is cognizant of the
customs, practices, usages, and terminology as generally understood in the
particular trade or business." Eskimo Pie Corp. v. Whitelawn Dairies, Inc., 284
F.Supp. 987, 994 (S.D.N.Y.1968), quoted in Walk-In Medical Centers, Inc. v.
Breuer Capital Corp., 818 F.2d 260, 263 (2d Cir.1987). However, "[t]he
language of a contract is not made ambiguous simply because the parties urge
different interpretations. Nor does ambiguity exist where one party's view
`strain[s] the contract language beyond its reasonable and ordinary meaning.'"
Seiden Assocs. v. ANC Holdings, Inc., 959 F.2d 425, 428 (2d Cir.1992),
quoting Bethlehem Steel Co. v. Turner Constr. Co., 2 N.Y.2d 456, 161
N.Y.S.2d 90, 141 N.E.2d 590 (Ct.App.1957).
178 Applying these standards, the language of 24 is unambiguous. "Assignment"
is a legal term indicating a transfer of property or rights therein, and there is no
reason to doubt that the parties intended to use it as such in 24. The first
paragraph of Completion Agreement supports the conclusion that "assignment"
in 24 was intended to embrace a transfer of rights. Paragraph one provides:
179 Assignment and Delegation. Aetna, for itself and as attorney-in-fact for Carlin,
hereby assigns and delegates to Aniero, and Aniero hereby assumes, any and all
of the rights, title, interest, duties and responsibilities of Aetna and Carlin that
now exist or may hereafter arise in, to, or under the Aetna bond and the
Construction Contract....
180 This language demonstrates that the parties intended that Aetna and Carlin
would transfer to Aniero not only their duties under the performance bond and
the Carlin Contract, but also their rights under those agreements.2 Moreover,
the fact that the first paragraph refers to "[a]ssignment and [d]elegation" belies
Aetna's suggestion that the term "assignment" is interchangeable with
"delegation" in the agreement. I conclude that the term "assignment" in 24 of
the Completion Agreement unambiguously conveys the definite and precise
through the doctrine of substantial performance. However, the New York Court
of Appeals has held that "substantial performance is ordinarily not applicable to
excuse the non-occurrence of an express condition precedent." Oppenheimer &
Co. v. Oppenheim, Appel, 86 N.Y.2d 685, 636 N.Y.S.2d 734, 738, 660 N.E.2d
415 (Ct.App.1995). According to the Court of Appeals, "`if relief is to be had
under [a] contract [when an express condition precedent has not occurred], it
must be through excuse of the non-occurrence of the condition to avoid
forfeiture.'" Id. at 738 (quoting Restatement [Second] of Contracts 237,
comment d, at 220). "Forfeiture" is defined as "the denial of compensation that
results when the obligee loses [its] right to the agreed exchange after [it] has
relied substantially, as by preparation or performance on the expectation of that
exchange." Id. at 738 n. 2 (quoting Restatement (Second) Contracts 229,
comment b). The Restatement summarizes the forfeiture doctrine as follows: "
[t]o the extent that the non-occurrence of a condition would cause
disproportionate forfeiture, a court may excuse the non-occurrence of that
condition unless its occurrence was a material part of the agreed exchange."
Restatement [Second] of Contracts 229.
193 The forfeiture doctrine does not avail Aetna in this case for two reasons. First,
as explained above, the SCA's written consent was a material part of the agreed
exchange. Second, given the facts of this case, Aetna cannot claim that it will
suffer a disproportionate forfeiture absent enforcement of the Completion
Agreement. As General points out, "[a]ll Aetna has shown is that it stood by,
silently, while Aniero performed, pursuant to what it believed to be a binding
contract, solely due to misinformation provided to it by Aetna." General's Reply
Brief in Support of its Cross-Motion at 12. Accordingly, I conclude that the
Completion Agreement is invalid because Aetna failed to secure the SCA's
written consent to the assignment of rights to Aniero.
2. The SCA's Counterclaims against Aniero
194 The SCA's three counterclaims against Aniero allege: (1) that Aniero breached
the Carlin Contract and thereby damaged the SCA, see SCA's Answer to
Aniero's First Amended Complaint at 39-43, (2) that the SCA is a third-party
beneficiary of the Completion Agreement, see id. at 43-44, and (3) that the
SCA is entitled to liquidated damages against Aniero under the Carlin Contract,
see id. at 44-45. Each of these claims relies on the validity of the Completion
Agreement. Because the Completion Agreement is invalid, Aniero's motion is
granted to the extent it seeks the dismissal of the SCA's counterclaims against
Aniero.
3. Aetna's Claims against General
195 In its amended complaint, Aetna claims that General breached its obligations to
Aetna under the performance bond that General executed with Aniero in
connection with the Completion Agreement.5 Aetna now moves for summary
judgment declaring General's liability for these breaches. In its cross-motion for
summary judgment, General argues that Aetna's claims against it should be
dismissed because a surety bond is a nullity if the contract underlying the
surety bond is void.
196 General has the upper hand in this dispute. The Appellate Division has held that
"[a] surety bond attaches to the principal contract and must be construed in
conjunction therewith, so that, if no underlying agreement ever came into
existence, there is nothing to which the surety's obligation can attach and it is,
therefore, a nullity." Hall & Co. v. Continental Casualty Co., 34 A.D.2d 1028,
310 N.Y.S.2d 950, 952 (3d Dep't 1970), aff'd, 30 N.Y.2d 517, 330 N.Y.S.2d 64,
280 N.E.2d 890 (Ct.App.1972) (citations omitted); see also Walcutt v. Clevite
Corp., 13 N.Y.2d 48, 241 N.Y.S.2d 834, 838, 191 N.E.2d 894 (Ct.App.1963) (a
guarantor is not liable unless the principal is bound); Pro-Specialties, Inc. v.
Thomas Funding Corp., 812 F.2d 797, 799 (2d Cir.1987).6 Because the
Completion Agreement is invalid due to the absence of the SCA's written
consent, the performance bond issued by General as security for the
Completion Agreement is also a nullity.
197 Although General did not raise the invalidity of the Completion Agreement as
an affirmative defense prior to its cross-motion, I see no obstacle to awarding
General summary judgment dismissing Aetna's claims on this basis. "Absent
prejudice to the plaintiff, a defendant may raise an affirmative defense in a
motion for summary judgment for the first time." See Steinberg v. Columbia
Pictures Indus., Inc., 663 F.Supp. 706, 715 (S.D.N.Y.1987) (citations and
internal quotation marks omitted). No discovery has been conducted to date,
and Aetna has yet to serve an answer to any of the pleadings filed by Aniero or
General. Moreover, as General notes in its brief, "since SCA's lack of written
consent to the assignment was particularly within Aetna's knowledge, Aetna
can hardly claim that it is prejudiced by interposition of this affirmative defense
at this juncture." General's Brief in Support of its First Cross-Motion at 7-8.
Accordingly, I will grant (1) General's request for leave to amend its answer to
Aetna's complaint nunc pro tunc to assert SCA's failure to consent to Aetna's
attempted assignment of the Carlin Contract to Aniero as an affirmative defense
and (2) General's cross-motion for summary judgment dismissing Aetna's
complaint in its entirety based on the affirmative defense.7 Aetna's motion for
summary judgment on the issue of liability with respect to its causes of action
against General is denied.
be given freely when justice so requires, where, as here, there is no merit in the
proposed amendments, leave to amend should be denied."); S.S. Silberblatt,
Inc. v. East Harlem Pilot Block, 608 F.2d 28, 42 (2d Cir.1979) ("A trial court
does not abuse its discretion in denying leave to amend a complaint which even
as amended would fail to state a cause of action.") (citation omitted); Bank of
New York v. Sasson, 786 F.Supp. 349, 352 (S.D.N.Y.1992) (If "the claims
would be subject to dismissal under Fed.R.Civ.P. 12(b)(6), the court should
refuse to grant leave to amend rather than assent and then await a motion to
dismiss."). That is, the court must accept the facts alleged by the party seeking
to amend as true and construe them in the light most favorable to that party. A
claim may not be dismissed under Rule 12(b)(6) "unless it appears beyond
doubt that the plaintiff can prove no set of facts in support of his claim which
could entitle him to relief." Conley v. Gibson, 355 U.S. 41, 45-46, 78 S.Ct. 99, 2
L.Ed.2d 80 (1957).
203 Applying these standards, I conclude that amendment by Aniero and General to
include quantum meruit claims against Aetna is not futile. Under New York
law, "[t]he doctrine of quantum meruit allows a plaintiff to recover even where
an express contract has been rescinded, is unenforceable or has been abrogated
because it enforces the enriched party's implied promise to pay for benefits
conferred by the plaintiff." Eli Attia Architects v. Safra, 1996 WL 480721
(S.D.N.Y.1996). A plaintiff may recover in quantum meruit upon showing: "
(1) the performance of services in good faith, (2) the acceptance of the services
by the person to whom they are rendered, (3) an expectation of compensation
therefor, and (4) the reasonable value of the services." Moors v. Hall, 143
A.D.2d 336, 532 N.Y.S.2d 412, 414 (2d Dep't 1988), quoted in Longo v. Shore
& Reich, Ltd., 25 F.3d 94, 98 (2d Cir.1994). Aniero and General argue that they
can make this showing because Aniero worked on the SCA project in good
faith, Aetna accepted the services rendered, and Aniero expected
compensation.8 I conclude that there is merit in the proposed amendments, and
accordingly grant Aniero and General leave to amend their pleadings to include
quantum meruit claims against Aetna.9
204 As to Aniero's request for leave to amend to include a quantum meruit claim
against the SCA, the question is closer. "[U]nder New York law, a
subcontractor may recover from a landowner (and a sub-subcontractor from a
general contractor), even when a separate contract exists between the
subcontractor and general contractor, if the owner has agreed to pay the general
contractor's debt or if the circumstances surrounding the parties' dealings can be
found to have given rise to an obligation to pay." U.S. East
Telecommunications, Inc. v. U.S. West Communications Serv. Inc., 38 F.3d
1289, 1290 (2d Cir.1994); see also EFCO Corp. v. U.W. Marx, Inc., 124 F.3d
394, 401-02 (2d Cir.1997). The SCA contends that it would be futile for Aniero
to amend its complaint to include a quantum meruit claim against the SCA
because the SCA never agreed to pay Aetna's debt and Aniero cannot show that
the SCA undertook any obligation to pay Aniero for its work. See SCA's Reply
Brief in Support of its Summary Judgment Motion at 4-6. Aniero has not
submitted a proposed second amended complaint with its motion papers.
Without seeing Aniero's proposed amended pleading, I am unable to evaluate
whether Aniero's quantum meruit claim could survive a motion to dismiss
under Rule 12(b)(6). Accordingly, I will deny without prejudice Aniero's
request for leave to amend to assert a quantum meruit claim against the SCA.10
If Aniero wishes to press its request, it may renew its motion by submitting a
proposed second amended complaint.
205 I also find it impossible to reach a determination as to liability in quantum
meruit without first examining Aniero's second amended pleading. I therefore
deny without prejudice Aniero's motion to the extent that it seeks a judgment of
liability on Aniero's quantum meruit claims.
206 IV SCA's Summary Judgment Motion on its Cross-Claims Against Aetna
207 The SCA has asserted two cross-claims against Aetna based on the theory that
Aetna breached its obligations to the SCA under the performance bond
executed between Aetna and Carlin.11 The first cross-claim seeks damages for
additional costs that the SCA incurred in completing the SCA project after
Aetna failed to meet its obligations under the performance bond. The second
cross-claim seeks liquidated damages against Aetna under the Carlin Contract
for every day that the SCA project remained uncompleted after Carlin's
contractual date of completion. The SCA now moves for an order granting
summary judgment as to liability on these cross-claims and dismissing the
affirmative defenses that Aetna has raised in its answer.
208 In response, Aetna asserts that pursuant to Rule 56(f), the SCA's motion is
premature because Aetna requires additional discovery to respond to it
properly. Rule 56(f) allows a party faced with a motion for summary judgment
to request additional discovery. To oppose a motion on the basis of Rule 56(f),
a party must file an affidavit detailing: (1) what facts are sought and how they
are to be obtained; (2) how these facts are reasonably expected to create a
genuine issue of material fact; (3) what efforts the affiant has made to obtain
those facts; and (4) why these efforts were unsuccessful. See Sage Realty Corp.
v. Insurance Co. of North America, 34 F.3d 124, 128 (2d Cir.1994).
209 Aetna has not met the second prong of this test. In support of its Rule 56(f)
209 Aetna has not met the second prong of this test. In support of its Rule 56(f)
request, Aetna has submitted a skeletal affidavit from its counsel, Arthur N.
Lambert, indicating that it requires discovery of the SCA, other parties, and
non-parties pertaining to "among other things, Aniero's contentions that the
SCA gave its approval and paid to Carlin substantial sums of money for: (a)
items of work which were never performed (`Phantom Work') and not
completed in the amounts set forth in Carlin's requisitions (`Overstated Work')
and (b) materials which were not located and installed at the project (`Phantom
Materials')." Affidavit of Arthur N. Lambert of January 8, 1998 at 3.
Lambert's affidavit does not indicate how these facts are reasonably expected to
create a genuine issue of material fact. Moreover, for the reasons that follow,
none of the factual allegations made in Aetna's brief raise an issue of material
fact as to liability. Accordingly, Aetna's Rule 56(f) is denied.
In support of its motion, the SCA has provided evidence to support the
210 following: On June 5, 1992, Aetna issued a performance bond and an
incorporated payment bond in the penal sum of $28,863,000 naming Aetna as
surety, the SCA as obligee, and Carlin as principal. The performance bond
provides as follows:
211 The Surety, for value received, hereby stipulates and agrees, if requested to do
so by the Authority, to fully perform and complete the work to be performed
under the [Carlin Contract], pursuant to the terms, conditions, and covenants
thereof, if for any cause, the Principal fails or neglects to so fully perform and
complete such work. The Surety further agrees to commence such work of
completion within twenty (20) days after written notice thereof from the
Authority and to complete such work within such time as the Authority may
fix.
212 In November 1993, Carlin abandoned its work and ceased performing its
obligations under the Carlin Contract. On or about December 3, 1993, the SCA
demanded that Aetna fully perform and complete the work to be performed
under the Carlin Contract. Aetna retained Aniero in March 1994 to complete
the Carlin Contract. Aniero began work, but abandoned the project without
justification in December 1994. At that time, the project was only 70%
complete. On or about December 29, 1994, the SCA advised Aetna of Aniero's
unjustified abandonment and demanded that Aetna complete the work to be
performed under the Carlin Contract. Since Aniero ceased work on the project,
Aetna has not made any attempt to complete the project. In December 1994, the
SCA entered into an agreement with Kreisler Borg Florman General
Construction Company, Inc. to complete the project. The SCA has incurred
substantial costs and expenses since Aniero abandoned the project.
213 On the basis of these facts, the SCA contends that it is entitled to summary
judgment on its cross-claims. Aetna resists the SCA's motion by asserting the
following affirmative defenses: failure to state a claim, unclean hands, waiver,
estoppel, failure to mitigate damages, and discharge. For the reasons that
follow, none of these affirmative defenses serves to bar the entry of summary
judgment as to liability.
214 Aetna's first affirmative defense is that the SCA has failed to state a claim.
Because both of the SCA's cross-claims state a claim for breach of the
performance bond, this affirmative defense will be dismissed.
215 Aetna next asserts an affirmative defense of unclean hands. Unclean hands is an
equitable defense to equitable claims. See, e.g., In re Gulf Oil/Cities Service
Tender Litigation, 725 F.Supp. 712, 742 (S.D.N.Y.1989); Hasbro Bradley, Inc.
v. Coopers & Lybrand, 128 A.D.2d 218, 515 N.Y.S.2d 461, 463 (1st Dep't
1987); Pecorella v. Greater Buffalo Press, Inc., 107 A.D.2d 1064, 486
N.Y.S.2d 562, 563 (4th Dep't 1985). Because the SCA seeks damages in an
action at law, Aetna cannot avail itself of unclean hands as a defense.
216 Aetna next asserts that the SCA's claims are barred by waiver and estoppel.
The only factual support that Aetna provides for these defenses is its allegation
that the SCA overpaid Carlin. See Aetna's Brief in Opposition to the SCA's
Motion at 20. A waiver is an intentional and voluntary relinquishment of a
known right, see Nassau Trust Co. v. Montrose Concrete Prods. Corp., 56
N.Y.2d 175, 451 N.Y.S.2d 663, 667-68, 436 N.E.2d 1265 (1982), and a waiver
of contractual rights will not be inferred absent a clear intent to waive, see
Seven-Up Bottling Co. v. Pepsico, Inc., 686 F.Supp. 1015, 1023
(S.D.N.Y.1988). In this case, the SCA has not indicated an intent to waive its
rights as third-party beneficiary to the performance bond. To the contrary, the
SCA demanded that Aetna complete the project when Carlin defaulted and
again when Aniero stopped work on the project. Aetna's waiver defense
accordingly will be dismissed.
217 Estoppel is also unavailing as a defense to liability. "Equitable estoppel is
`imposed by law in the interest of fairness to prevent the enforcement of rights
which would work fraud or injustice upon the person against whom
enforcement is sought and who, in justifiable reliance upon the opposing
party's words or conduct, has been misled into acting upon the belief that such
enforcement would not be sought." Readco, Inc. v. Marine Midland Bank, 81
F.3d 295, 301 (2d Cir.1996), quoting Nassau Trust Co. v. Montrose Concrete
Prods. Corp., 56 N.Y.2d 175, 451 N.Y.S.2d 663, 436 N.E.2d 1265
(Ct.App.1982). Under New York law, "[t]he elements of estoppel are with
respect to the party estopped: (1) conduct which amounts to a false
representation or concealment of material facts; (2) intention that such conduct
will be acted upon by the other party; and (3) knowledge of the real facts. The
party asserting estoppel must show with respect to himself: (1) lack of
knowledge of the true facts; (2) reliance upon the conduct of the party
estopped; and (3) a prejudicial change in his position." Airco Alloys Div., Airco
Inc. v. Niagara Mohawk Power Corp., 76 A.D.2d 68, 430 N.Y.S.2d 179, 187
(4th Dep't 1980), quoted in International Minerals & Resources v. Pappas, 96
F.3d 586, 593 (2d Cir.1996).
218 Neither Aetna's answer nor its brief explains why Aetna believes that the
alleged overpayments give rise to an estoppel defense. Aetna never identifies
any reliance on its part upon the SCA's alleged overpayments or any resulting
prejudicial change in its position. Moreover, even if Aetna could properly raise
an estoppel defense, such a defense would not bar the entry of summary
judgment as to Aetna's liability under the performance bond. Estoppel is
defined as "a bar which precludes a person from questioning a fact which he
has by his conduct induced another person to believe and to act on to his
prejudice, or which has been admitted or determined under circumstances of
solemnity, such as by a matter of record or by deed." See 57 N.Y. Jur.2d 2;
Holm v. C.M.P. Sheet Metal, Inc., 89 A.D.2d 229, 455 N.Y.S.2d 429 (4th Dep't
1982) ("Th[e] doctrine [of equitable estoppel] precludes a party at law and in
equity from denying or asserting the contrary of any material fact which he has
induced a party to believe and to act in a particular manner."). The only fact that
the alleged overpayments could possibly estop the SCA from questioning is
whether Carlin performed all of the work for which it was paid. Even if the
SCA were forced to concede that Carlin performed all of the work for which it
was paid, Aetna would remain liable under the performance bond because at
the time of Carlin's default there remained substantial project work for which
Carlin had not been paid and it was Aetna's responsibility as surety to ensure
that the project was completed. Accordingly, Aetna's estoppel defense does not
preclude a judgment of liability.
219 Aetna next asserts that the SCA's cross-claims are barred because the SCA
failed to mitigate damages. Failure to mitigate damages is properly considered
in determining damages rather than liability. See, e.g., Grassi v. New York Life
Ins. Co., 1992 WL 249936, *11 (S.D.N.Y.1992); Rivas Paniagua, Inc. v. World
Airways, Inc., 673 F.Supp. 708, 715 (S.D.N.Y.1987). Accordingly, this
affirmative defense does not bar the entry of summary judgment as to liability.
220 Aetna next seeks to raise a discharge defense based on alleged overpayments
made by the SCA to Carlin. In its answer, Aetna alleges that the SCA and/or its
agents approved and paid for work that Carlin had not completed, work that
Carlin had not completed in the amounts set forth in Carlin's requisitions, and
materials that Carlin had not installed at the project. See Aetna's Brief in
Opposition to the SCA's Summary Judgment Motion at 5-6; Crevani Aff.
41(j)-(1).12 On the basis of these allegations, Aetna contends that it is
discharged from any further obligations on the performance bond because the
SCA and/or its agents failed to duly perform their obligations under the Carlin
Contract. See Aetna's Answer 28-30, 32-33, 34-36; Aetna's Brief in
Opposition to the SCA's Summary Judgment Motion at 5-6. Alternatively,
Aetna seeks to be discharged pro tanto to the extent that it was prejudiced by
the diminishment and impairment of Aetna's security in the Carlin contract
balances. See Aetna's Answer 32, 35; Aetna's Brief in Opposition to the
SCA's Summary Judgment Motion at 5-6. 13
221 In raising these issues, Aetna seeks to invoke the defense of discharge of a
surety by acts or omissions of the obligee. As a general rule, a material or
prejudicial variation of the terms of a building contract discharges a surety who
has guaranteed the contract. See, e.g., American Bonding Co. v. Kelly, 172 A.D.
437, 158 N.Y.S. 812 (2d Dep't 1916), aff'd, 225 N.Y. 641, 121 N.E. 852
(Ct.App.1919). In addition, "[a]ccording to the weight of authority in American
jurisdictions,... a material departure by the owner, without the consent of the
surety, from the express requirements of a construction contract with regard to
the times or amounts of payments made to the contractor, the retention of
percentages, or the exaction of certain certificates, estimates, or receipted bills,
operates to release or discharge the surety on the contractor's bond from
liability to the owner, at least to the extent that such unauthorized payments
result in injury or prejudice to the surety." 63 N.Y. Jur.2d, Guaranty and
Suretyship 574.
222 Citing these doctrines, Aetna insists that the overpayments that it has alleged
should discharge its obligations under the bond entirely or pro tanto. The Carlin
Contract provides that the SCA may make partial payments to Carlin based on
approved estimates provided by Carlin of the work performed and materials
stored on-site and off-site and specifies that the SCA is to retain five percent of
the estimated amounts. See General Conditions 16.01. Aetna suggests that its
obligations should be discharged because the SCA allegedly paid for work that
was not performed and materials that were not located and installed at the
project in violation of the Carlin Contract provisions.
223 The SCA responds convincingly that Aetna cannot avail itself of the discharge
defense because it waived its right to do so in the performance bond. As the
SCA points out, it is well settled that the discharge defense can be waived by
the terms of a particular performance bond. See, e.g., Restatement (3d) of
Suretyship & Guaranty 48(1) (1996); Smith v. Molleson, 148 N.Y. 241, 42
N.E. 669 (Ct.App.1869); Carrols Equities Corp. v. Villnave, 57 A.D.2d 1044,
395 N.Y.S.2d 800 (4th Dep't 1977); United States for Use & Benefit of H. & S.
Ind. v. Rich, 525 F.2d 760, 771 (6th Cir.1975); M.H. Walker Realty Co. v.
American Surety Co., 60 Utah 435, 211 P. 998, 1015 (1922); Price v. Seibel,
253 S.W. 212, 215 (Mo.Ct.App.1922); Zang v. Hubbard Bldg. & Realty Co.,
125 S.W. 85, 88 (Tex.Civ.App.1910); Enterprise Hotel Co. v. Book, 48 Or. 58,
85 P. 333, 335 (1906).
224 In this case, the performance bond could not be more explicit. It provides:
225 The Surety, for value received, for itself and its successors and assigns, hereby
stipulates and agrees that the obligation of said Surety and its bond shall in no
way be impaired or affected by any extension of time, modification, omission,
addition, or change in or to the said contract or the work to be performed
thereunder, or by any payment thereunder before the time required therein, or
by any waiver of any provisions, thereof, or by any assignment, subletting or
other transfer thereof or of any work to be performed or any moneys due or to
become due thereunder....
226 The performance bond also incorporates by reference the Carlin Contract,
which in turn provides that "[n]o payment, final or otherwise, shall operate to
release the Contractor or the Contractor's sureties from any obligations under
this Contract o[r] the performance or labor and material bonds." Carlin
Contract, General Conditions 16.02. Because Aetna waived its right to
complain that payments were not made at the time or in the manner stipulated
in the contract, it is barred from asserting a discharge defense.
227 Aetna suggests that notwithstanding the waiver, it should be allowed to assert a
discharge defense if it can show that the SCA did not make the alleged
overpayments in good faith reliance on Carlin's representations as to the work
that it had performed. See Aetna's Brief in Opposition to the SCA's Summary
Judgment Motion at 16. Whether the SCA made the payments in good faith
reliance on Carlin's estimates is immaterial to this issue. If Aetna had not
explicitly waived the discharge defense in the bond, whether the SCA relied in
good faith would be relevant because when a performance bond authorizes the
obligee to make payments based on a certificate of progress, "a surety is not
discharged by reason of an unauthorized payment made in good-faith reliance
on [the certificate of progress]" even in the absence of an explicit waiver of the
discharge defense in the bond. Argonaut Ins. Co. v. Town of Cloverdale, Ind.,
699 F.2d 417, 419 (7th Cir.1973); see also British-American Tobacco Co. v.
United States Fidelity & Guaranty Co., 177 A.D. 582, 164 N.Y.S. 406 (1st
Dep't 1917). However, in a case such as this, where a surety explicitly agrees in
the bond that prepayments by the obligee will not discharge its liability, the
surety cannot later be heard to complain that the obligee made a prepayment
without relying in good faith on a certificate of progress. Accordingly, Aetna
cannot raise an affirmative defense of discharge.
228 Finally, Aetna suggests for the first time in its opposition brief that the SCA's
actions may have rendered Aetna's performance impossible. See Aetna's Brief
in Opposition to the SCA's Summary Judgment Motion at 20 ("Further, Aniero
asserts, inter alia, that its performance of the completion contract was rendered
impossible by the SCA's aforesaid improper payments to Carlin, in the sum of
at least $2,600,000, and the SCA's refusal to issue change orders for labor and
materials which were necessary to complete the contract."). To the extent that
Aetna seeks to base such a defense on the alleged overpayments, the defense is
without merit because the mere fact that the completion of the project may
have cost Aetna more than the balance of contract funds held by the SCA did
not make performance impossible. To the extent that Aetna relies on other
grounds, the defense is inadequately pled as it does not appear in Aetna's
answer and receives only passing reference in Aetna's brief. See id.
229 The SCA's motion for summary judgment on its cross-claims is accordingly
granted.
IV. Other Motions
230 Aniero and General indicate in their briefs that they do not intend to press the
claims asserted in Aniero's First Amended Complaint and General's First
Amended Third-Party Complaint, given that the Completion Agreement is a
nullity. See, e.g., Aniero's Brief in Support of its Cross-Motion for Summary
Judgment at 2 ("[T]he only remaining issues before the Court are the value of
the work performed by Aniero, and whether Aniero has been fairly
compensated for its work by the beneficiaries of its labors SCA and Aetna.
All other issues and motions before the Court need not be considered because
they arise out of, and assume the existence of, what has proved to be a phantom
contract."); General's Memorandum in Support of its Cross-Motion for
Summary Judgment at 2 ("[T]his Court need not address the issues relating to
General's and Aniero's other claims against various defendants for fraud,
breach of contract, discharge of surety obligation, etc. The Court need only
consider Aniero's and General's claim against Aetna for quantum meruit
recovery, SCA's claim against Aetna for failure to complete the project, and
Notes:
1
In its Memorandum Opinion and Order of March 30, 1998, the District Court
also granted Aniero leave to amend its pleadings to include aquantum meruit
claim against Aetna. Aniero shortly asserted such a claim. Following a bench
trial, the District Court entered a judgment in Aniero's favor on the quantum
meruit claim in the amount of over $3.5 million. See Aniero Concrete Co. v.
Aetna Cas. & Sur. Co., No. 94 Civ. 9111 (S.D.N.Y. Feb. 3, 2004) (final
judgment); see also Aniero Concrete Co. v. Aetna Cas. & Sur. Co., 301
F.Supp.2d 302 (S.D.N.Y.2004). Because Aetna does not challenge the quantum
meruit judgment except to ask that it be vacated if we conclude that there was a
valid contract, and because we reach no such conclusion, we intimate no view
as to the merits of the Court's determination of Aetna's liability to Aniero in
quantum meruit.
There is some dispute between the parties as to the proper name for this
defendantSee infra. As discussed below, the resolution of the instant motions
does not appear to turn on this question.
This contention is borne out by the bid documents themselves, which clearly
invite bids for three separate projectsSee Lambert Aff. ex. 5A at 1.
Delta was ultimately disqualified by SCA, and Aniero agreed to take on the
Project alone. Crevani Aff. 34-36
Aniero's affidavits are vague as to whether this took place before or after the
bid was acceptedSee Hanjis Aff. 19; Crevani Aff. 32.
Aetna contends that these allegations contradict those set forth in Aniero's
complaint. Aetna's Reply Mem. at 11. In its complaint, however, Aniero alleged
that "Aetna through Hudson" solicited bids for the Morris Project in December
1993, and Aniero was "ultimately the successful bidder." Complaint 28-29.
While Aniero's pleadings are admittedly sparse in describing these events, they
are not inconsistent with the assertions made by Crevani and Hanjis
For the same reason, Aetna cannot rely on the portions of the bid materials
where Hudson and Aetna state that they "do not warrant the accuracy or
completeness of the information provided...." Lambert Aff. ex. 5B at 1
9
10
11
To the extent Aniero is alleging that the work defects were wrongfully omitted
from these documents, that claim is better dealt with under the rubric of
fraudulent concealment
12
Aniero's complaint states that the Punchlists were prepared by KBF. Complaint
31c. Payment Requisition No. 15 and the Change Order List delineate the
amount of work claimed to have been performed by Carlin and approved by
KBF and SCA. I note that, absent some representation made by Aetna or
Hudson concerning these documents, there is nothing on their face which
purports to describe the state of the Project. Payment Requisition No. 15 and
the Change Order List purport only to catalogue the value of the work which
Carlin asserted that it had completed, and the fact that Carlin's submissions
were approved. The Punchlists include no representation whatsoever as to the
meaning of their contents
13
Aniero's conclusory allegations that KBF, SCA, Aetna and Hudson engaged in
a conspiracy to defraud Aniero, Complaint 67-70, does not cure its failure to
explain how Aetna and Hudson acted fraudulently in providing Aniero with
purportedly incomplete documents that they played no role in preparingCf.
Segal v. Gordon, 467 F.2d 602, 608 (2d Cir.1972) ("The word `conspiracy'
does not alone satisfy the requisite specificity requirements of Rule 9(b)").
14
Aetna and Hudson only raise Rule 9(b) in opposition to Aniero's fraudulent
inducement claim. Although failure to assert a 9(b) objection can result in its
waiver,see Todaro v. Orbit Int'l Travel, Ltd., 755 F.Supp. 1229, 1234
(S.D.N.Y.1991); Stonehill v. Security Nat'l Bank, 68 F.R.D. 24, 44 n. 38
16
The Second Circuit has held that a claim for anticipatory breach also requires
that the plaintiff show that it "was ready, willing and able to perform its own
obligations under the contract when performance was due."Towers Charter,
894 F.2d at 523. Assuming that this is an accurate depiction of the current state
of New York law, but see American List Corp., 550 N.Y.S.2d at 594, 549
N.E.2d 1161 ("The non-repudiating party need not ... tender performance nor
prove its ability to perform the contract in the future...."), there is nothing in the
record demonstrating that Aniero could prove this element vel non. Because I
find that Aniero's claim of anticipatory breach must fail on other grounds, I
need not reach this question.
17
Hudson contends that Aniero failed even to allege that it was an intended
beneficiary. Hudson Mem. at 6. This is simply not the caseSee Complaint
243.
18
Although Hudson's motion seeks dismissal for failure to state a claim, and not
summary judgment, this Court could still review the terms of the contract to
resolve this motion, as it is clearly integral to the plaintiff's complaintSee supra
p. 576.
General's amended counterclaim echoes the assertion in its prior pleadings that
Aetna knew of the Project Documents' purported inaccuracy. Amended
Counterclaim 75c, 82, 90, 99-102
The "Carlin Contract" refers to the contract entered between the P.J. Carlin
Construction Company ("Carlin") and the SCA on July 1, 1992
The SCA maintains that Aetna could not assign rights under the Carlin Contract
to Aniero because it did not have any. However, as completing surety, Aetna
became subrogated to Carlin's rights under the Carlin contractSee, e.g.,
Pearlman v. Reliance Ins. Co., 371 U.S. 132, 141, 83 S.Ct. 232, 9 L.Ed.2d 190
(1962); United States Fidelity & Guaranty Co. v. Triborough Bridge Authority,
297 N.Y. 31, 74 N.E.2d 226 (Ct.App.1947). Moreover, according to the
Completion Agreement, Aetna was "empowered by agreement with Carlin to
act as Carlin's attorney-in-law for the purpose of assigning all or part of the
[Carlin] Contract."
Aetna also cites a letter dated April 5, 1994 from Aetna's counsel Charles
Lewis to SCA Senior Attorney Valerie Greaves as evidence that the SCA
consented to the assignmentSee Gillen's Affidavit in Opposition of October 20,
1997, Exh. B. In that letter, Lewis confirmed that Aniero would be Aetna's
completion contractor on the project and advised the SCA that "Aetna, on its
own behalf and on behalf of Carlin, has assigned to Aniero all of Carlin's
obligations to complete Carlin's contractor with the SCA on this project." After
instructing the SCA to send project payments to Kevin W. Gillen, Lewis
concluded: "Should the forgoing raise any questions on your behalf, please feel
free to contact the undersigned or Mr. Gillen immediately." Aetna argues that
by failing to respond to this letter, the SCA provided the consent required by
24 of the Completion Agreement. However, even if it were possible to construe
Lewis' letter as a request for the SCA's consent and to interpret the SCA's
silence as consent, the Completion Agreement explicitly required the SCA to
consent in writing, which it evidently did not do.
The only authority that Aetna cites in resisting General's argument isBoard of
Education v. Aetna Casualty & Surety, 453 F.2d 264 (2d Cir.1971). See Aetna's
Reply Brief in Support of its Summary Judgment Motion Against General at
14. At issue in that case was a public works contract that had been entered into
in violation of New York's competitive bidding statute, N.Y. Gen. Municipal
Law 103, and was consequently held void. Under the New York Court of
Appeals' decision in Gerzof v. Sweeney, 22 N.Y.2d 297, 292 N.Y.S.2d 640, 239
N.E.2d 521 (Ct.App.1968), a special set of equitable principles governs the
"remedy appropriate [in cases] where an illegal and void contract for public
work, entered into in defiance of the competitive bidding statute..., has been
performed in full on both sides." Id. at 645. These principles are designed to
maintain "the practical effectiveness and vigor of the bidding statutes." Id. In a
case related to Board of Education, involving the same contract, the district
court applied Gerzof and concluded that the principal on the bond at issue in
Board of Education might be liable to the school board for "damages which the
Board has suffered as a direct consequence of the illegal contract," though it
was not liable under the contract or in quantum meruit. Fabrizio & Martin, Inc.
v. Board of Educ., 290 F.Supp. 945, 955-56 (S.D.N.Y.1968). In the context of
that ruling, the Second Circuit held in Board of Education that the illegality of
the principal's construction contract did not necessarily absolve the surety of
liability on all of the claims against it. In the case at bar, there is no allegation
that the Completion Agreement was entered into in violation of the competitive
bidding statute and the Completion Agreement has not been performed in full
on both sides. Board of Education is accordingly inapposite.
7
General's request for leave to amend its Amended Third Party Complaint to
reflect the SCA's allegations that it did not consent to Aetna's purported
assignment is also granted
10
In its brief, Aniero suggests that it does not even require leave to amend
because its amended complaint already asserts a claim in quantum meruitSee
Aniero's Brief in Support of its Cross-Motion at 12. I disagree. To the extent
that the amended complaint raises a claim in quantum meruit, it is in the
context of a rescission of the Completion Agreement. If Aniero now wishes to
press a claim for quantum meruit on the basis of the failure of a condition
precedent, it must amend its complaint to so plead.
11
12
Conditions 3.01A, 4.01(B), 6.03, 6.04, 6.06. With regard to Carlin's written
requests for payment, the Carlin Contract states:
Any signatures on behalf of the Authority shall signify either acceptance of the
Request for Payment form or recommendation for payment. In no event shall
such signature signify acceptance of partially completed work. Furthermore,
any partial payment made shall not be construed as a waiver of the right of the
Authority to require the fulfillment of all the terms of the Contract.
Id. 16.01C; see also 16.02.
13
Aetna raises these issues in its answer in what it terms its sixth, seventh, and
eighth affirmative defenses. Aetna's brief makes clear, however, that all three
rely on the same legal theorydefense of discharge of a surety by acts or
omissions of the obligee. I therefore treat the three defenses as one for purposes
of this discussion