Pipe Coat & Lining
Pipe Coat & Lining
Pipe Coat & Lining
Note: The source of the technical material in this volume is the Professional
Engineering Development Program (PEDP) of Engineering Services.
Warning: The material contained in this document was developed for Saudi
Aramco and is intended for the exclusive use of Saudi Aramcos
employees. Any material contained in this document which is not
already in the public domain may not be copied, reproduced, sold, given,
or disclosed to third parties, or otherwise used in whole, or in part,
without the written permission of the Vice President, Engineering
Services, Saudi Aramco.
Engineering Encyclopedia
CONTENTS
PAGES
Engineering Encyclopedia
SAES-H-002
APCS-104
SAES-H-201
SAES-H-200
A description of the FBE application process follows; such applications are made under very controlled
conditions because of their importance.
Engineering Encyclopedia
FBE applied to pipe and equipment and to reinforcing steel for concrete construction is applied in generally the
same manner. First, the steel is decontaminated and abrasive blast cleaned to SSPC-SP-10 (SA 2 1/2). It is
then preheated by electrical induction heaters to a temperature prescribed by the epoxy coating powder
manufacturer. A differential electrostatic charge is generated between the powder application equipment and
the steel pipe or surface. Powder can then be applied uniformly and without holidays to the entire steel surface.
Inspection for holidays or damage and later repairs are made consistent with 09-AMSS-089. The dry film
thickness should be 17-22 mils. Figures 1 and 2, located in the figure sheets, are, respectively, FBE fieldapplied to pipe and a photomicrograph of an FBE internally and externally applied to a pipe wall and girth weld
section. It is important that the girth welds are coated properly because it has been shown that protective
coatings frequently fail there compared to the pipe body.
SAES-H-201 covers FBE applied to girth welds in the field. It directs that FBE be applied in the field in the
same manner as in the shop. The powder is not applied by electrostatic spray equipment, but it is blown onto
the surface. FBE is the preferred method for protecting field girth welds, but HDPE heat shrink sleeves may
also be used. See Figure 3. This application should follow APCS-110, APCS-111, and APCS-112 heat shrink
sleeve application instructions.
FBE Requires Strict Quality Control
FBE requires strict QA/QC precautions when it is applied, carried to the field, joined, and buried. These
precautions are enumerated in SAES-H-201. For example, a vendor's quality control program must include, but
not be limited to:
Metal inspection.
Coating thickness.
Adhesion.
Engineering Encyclopedia
The inspector, in addition to assuring that these QA/QC procedures have been carried out, must spot check:
Thickness.
Adhesion.
Shipment preparations.
This detailed inspection and quality control program and further inspection criteria are detailed in SAES-H-200.
After the pipeline is welded and joined in the field and the girth welds have been completely coated, the entire
surface is again inspected for holidays with a high-voltage spark test, and any holidays or damaged areas are
repaired prior to ditching the pipe. This holiday test is carried out at a potential of approximately 2400 V, a
much
lower voltage than what is specified for the hot-applied coal tar enamel or high density polyethylene coating
systems.
Hot-Applied Coal Tar Enamel Pipe Coating
Hot-applied coal tar enamel is specified for use on buried and also, on subsea pipelines, if a weight coating is
required. See APCS-106. As discussed in COE 108.02, it is a natural, convertible coating system based on the
use of coal tar pitch (a distillation product from the production of coal-based coke). It is received as a solid
block and then melted in kettles until the temperature of the coal tar liquid is approximately 375 F. It is shop
applied by a traveling weir to a length of rotating pipe. The coal tar cools and solidifies. At room temperature
it is black, glossy, hard, and very resistant to water and corrosion damage. It has been used for centuries as a
protective coating.
There are a number of components to a coal tar enamel protective coating system; these include the following:
Primer - Coal tar or synthetic primer thinly applied to a commercial abrasive blast cleaned surface.
Body Coat - Hot-applied enamel 3/32 1/32 in. thick; succeeding coats are applied 2/32 1/32 in. thick.
Reinforcement - Glass mat is wrapped into the coal tar enamel to strengthen the coating to increase
resistance to soils stress.
Engineering Encyclopedia
Felt Wrapping - A coal tar saturated tape is bonded to the outer layer of the coal tar enamel to increase
resistance to damage from backfilling the pipe trench.
Kraft Paper - A heavy duty wrapping paper is applied over the completed protective coating system in
order to support the applied system until the coal tar coating has cooled, hardened, and strengthened.
Rock Shield - This is a heavy duty shielding material to prevent damage to the coating system from
falling rocks during trench backfilling.
These coatings have a long, very successful history in ambient or slightly higher than ambient temperature
service pipelines. It may be used up to 70C when buried and up to 80C subsea. However, it should not be
used when benching of the pipe is required after coating application.
Coal Tar Systems - Principal Uses
A number of hot-applied coal tar enamel systems are used by the pipeline industry. Two of the most typical
ones are shown in Figures 4 and 5. Single-coat/single-wrap and single-coat/double-wrap systems (Figure 4) are
generally used in relatively dry, sandy, or loamy soils where little soils stress is expected. SAES-H-002
specifies that this coating is suitable for temperatures of 70C onshore and 80C offshore.
A double-coat/double-wrap system is pictured in Figure 5. This is generally applied with glass mat embedded
in the first layer of hot-applied coal tar enamel and felt wrapping embedded in the second layer. This is a
heavy-duty, anticorrosive system that is used for water immersion locations or for soil burial where there may
be severe soils stress.
Saudi Aramco Specification - Coal Tar Enamel
SAES-H-002 contains some information on coal tar enamel pipe coating but detailed information on hotapplied coal tar enamel applied to pipe is contained in 01-SAMSS-012, Submarine Pipe Weight Coating. The
reasons for the inclusion of the coal tar enamel system description within this specification are:
Hot-applied coal tar coating systems are used when concrete must be applied to a submarine pipeline to
provide negative buoyancy.
Engineering Encyclopedia
As specified in 01-SAMMS-012 the coating system must conform to American Water Works Association's
AWWA-C-203 -- double-coat/double-wrap -- as follows:
Primer.
Felt overwrap.
No Kraft paper wrap is applied, and the minimum coating thickness is designed to be 5/32 in.
In addition to the coal tar enamel coating, this specification also covers the requirements for the weight coating
concrete including the strength, reinforcement, and thickness (4 in. or more). The specification also sets the
requirements for placing bracelet zinc sacrificial anodes around the pipe to cathodically protect the pipeline.
Inspection procedures include, but are not limited to, requirements of AWWA-C-203 for the hot-applied coal
tar enamel coating and the purchase specification and its referenced documents for the concrete jacket coating.
Holiday detection is carried out with a high voltage spark detector at 15,000 V maximum. The compressive
strength of the concrete shall not be less than 4000 psi in order to insure a dense, strong concrete.
Storage, Handling, and Installation of Weight-Coated Pipe
The storage, handling, and installation of coal tar enamel weight-coated pipe are covered by SAES-H-220.
Note that when pipe sections are welded together, the girth weld must be protected with APCS-107 tape wrap,
which is applied in a unique manner as shown in Figure 6. After power tool cleaning (SSPC-SP-2), the tape
wrap is first applied directly over the weld; then to seal off the tar outerwrap joint, and finally over the entire
area with a 50% overlap, resulting in a minimum of two full layers of tape. To protect the tape, a heavy plastic
mesh, to be recommended by the Corrosion Control Division - Dhahran, should be applied over the taped joint.
The cavity, as shown in Figure 6, is then filled with a high density polyurethane foam encased in a steel sleeve.
This protective girth weld system is also used when weight coatings are applied with other specified subsea
coatings systems.
Engineering Encyclopedia
Engineering Encyclopedia
APCS-100 and -101 are used principally to line oil production drill pipe or tubing. These can only be applied
in the shop because of the heat curing step. APCS-103 (cement mortar lined pipe) is used to line corroded
water pipelines onsite. The APCS-102 system is a shop-applied FBE for new pipe to be used in corrosive water
service. It is important to note that the internal pipeline coatings specified in SAES-H-002 are not considered
mandatory unless required in other specifications and documents.
Internally Lined Pipe
Pipelines are internally coated for three reasons: to resist corrosion, to improve hydraulic
flow, or a combination of both reasons. The major reason Saudi Aramco internally lines pipe is for corrosion
resistance and to control the pickup of solids in the water; improvement of hydraulic flow is of minor
importance. Characteristics of several internal pipe linings are given in Figure 9, where corroded carbon steel is
compared to pipes lined with fusion bonded epoxy, cement mortar (CML), and coal tar enamel for water
service. As shown, the linings have much better frictional flow characteristics than carbon steel. These factors
play a major role in the design of a piping system since they reduce pipe diameter and pump capacity. They
also extend useful life and reduce the need for major pipe replacement.
In the past, Saudi Aramco specified thin-film, epoxy, or epoxy copolymer linings for pipelines. These thin-film
plastic linings are no longer used because of poor performance. The main reason these linings are not used for
welded pipe is that there is no practical method for internally coating the welded girth joint. These thin-film
plastic coatings continue to be used in production for oil field tubular goods where there are no welded joints
and the pipe is joined mechanically.
Engineering Encyclopedia
Specifically this document requires final inspection of the coated pipe by holiday detection, visual inspection,
dry film thickness and adhesion testing. Each of these are "special" techniques and instruction is required for
their correct use.
FBE Internal Pipe Linings
Pipe may be externally and internally coated with FBE (Figures 1 and 2). The Saudi Aramco specifications
covering both these applications are:
SAES-H-002
SAES-H-200
Storage, Handling, and Installation of Pipe Externally Coated with Fusion Bonded
Epoxy or Polyethylene.
09-SAMSS-089
09-SAMSS-091
Engineering Encyclopedia
SAES-H-201
Identical measures for application and quality assurance/quality control should be used for both internal lining
and external lining. If both an external coating and internal lining are applied simultaneously to pipe sections,
then both the coating and the lining must be inspected and evaluated.
If the diameter is 12 in. or greater, then the field girth weld may be coated from inside the pipe with suitable
pipeline crawlers. For detailed information concerning application and inspection, contact the responsible
organization, Corrosion Control Division - Dhahran. If the pipe is less than 12 in. in diameter, FBE internal
linings cannot be used. The pipeline must be internally lined onsite with a cement mortar lining. This type of
pipeline coating can be applied onsite to pipelines as small as 4 in. in diameter.
Cement Mortar Lined Pipe
CML pipe is also used for Saudi Aramco water services. It is also used worldwide for new construction and for
repair of existing pipelines that have suffered severe corrosion. The Saudi Aramco specifications concerning
CML pipeline applications are as follows:
SAES-H-002
APCS-103
01-SAMSS-005
AWWA-C-205
AWWA-C-602
Cement-Mortar Lining for Water Pipelines - 4 in. (100 mm) and larger - In Place.
Engineering Encyclopedia
CML linings are approximately 3/16-1/4 in. thick. They are recommended for most water services: salt,
aquifer, fresh, sweet, and potable water. Shop-coated pipe sections may be successfully welded in the field.
Figure 11 schematically depicts one design of a CML pipe fit up to achieve a sound weld. Other welded joint
designs for CML pipe are shown in standard Drawing L-AD-036090. Small openings at the weld of the CML
rapidly "choke" with scale and lime deposits, essentially stopping corrosion. The handling procedures detailed
in AWWA-C-205 must be followed; otherwise, flexing and bending of the CML pipe during transit will cause
early lining failure followed by pipe wall corrosion.
Other Pipeline Coatings
Other pipeline coatings such as pipeline tapes are not acceptable for use on new Saudi Aramco pipeline
facilities. Reasons for this include lack of durability and limited resistance to soil damage. In the case of
pipeline tapes, aggressive under-soil corrosion has occurred when there has been disbonding and a dielectric
barrier has formed around the pipe (Figure 12). As shown, this can occur on a pipeline that has been protected
by pipeline tape when ground water electrolytes have penetrated along the pipewall. Cathodic protection is not
effective because of the high IR drop in protective potential behind the tape; corrosion occurring behind the
tape cannot be prevented. This type of coating failure has occurred worldwide and includes Saudi Aramco,
Exxon and other facilities where extensive corrosive damage to pipelines has occurred. Pipeline tapes within
Saudi Aramco are limited to in-trench renovation coating of pipelines, as discussed in COE 108.07.
Conclusions
The preferred Saudi Aramco external pipeline coating for burial or immersion service is FBE. However, if a
FBE coated subsea pipeline requires a weight coating for negative buoyancy, it must be applied by the
compression coat method. All buried or subsea pipelines have cathodic protection applied to protect the
pipeline from corrosion at holidays or damaged areas in the coatings.
FBE is also preferred for internally lining pipe in water service if the lining will be applied in the shop. If the
pipeline is to be lined in situ, especially if the pipeline has been in service, then cement mortar linings should be
used.
For long-term durability, all internal and external pipeline coatings for use in Saudi Aramco facilities are
classified as critical coating applications.
10
Engineering Encyclopedia
Photo
Figure 1. Natural Gas Pipeline. A natural gas pipeline coated with a fusion bonded
epoxy and lined with an epoxy or epoxy-phenolic coating. Note the mechanical damage to
the FBE. The internal lining protects against light rusting from the dry gas and to improve
flow of the gas through the pipeline.
Photo
Figure 2. Pipe Wall. A photomicrograph of a pipe wall coated internally and externally
with a fusion bonded epoxy. Note the uniform thickness of the coating on the pipe wall and
its lack of uniformity at the weld.
11
Engineering Encyclopedia
Photo
Figure 3. Heat Shrink Sleeve. A heat shrink sleeve applied to a pipeline coated with a
fusion bonded epoxy. The pipeline has been placed in the ditch. Note the poor grade and
lack of proper bedding material.
12
Engineering Encyclopedia
Single-Coat, Single-Wrap
Clean
Pipe
Coal Tar
Primer
Coal Tar
Enamel
Glass Fiber
Wrap
Clean
Pipe
Coal Tar
Primer
Single-Coat, Double-Wrap
13
Engineering Encyclopedia
Glass Fiber
Wrap
Coal Tar
Enamel
Coal Tar
Enamel
Clean
Pipe
Coal Tar
Primer
Double-Coat, Double-Wrap
14
Engineering Encyclopedia
Girth Weld
Welded Joint
Metal Mold
Tape Wrap
Urethane Foam
15
Engineering Encyclopedia
Figure 6. Offshore Welded Joints. Single-Wrap with Urethane Foam Joint Filler. This schematic drawing
shows the specified procedure for protecting the girth weld of pipe coated and weight coated for subsea
application.
16
Engineering Encyclopedia
Extruder
for Adhesive
SSPC
SP-10
Induction
Heating
Extruder
for HDPE
Pipe
Movement
17
Engineering Encyclopedia
Figure 8. Large Diameter Pipe Coated with HDPE and Lined with Baked PhenolicEpoxy. The HDPE is ~ 6 mm thick. The baked phenolic-epoxy pipe lining is applied to
decrease frictional resistance and improve flow of gas through the pipeline.
Maximum Velocity
ft/s
Maximum Temperature F
Friction Factor
Hazel-Williams
Corroded
Carbon Steel
120
C80 - 120
CML
15
150 - 200
C140
FBE
8 - 10
180
C140
Coal Tar
8 - 10
80
C145
System
18
Engineering Encyclopedia
Mortar Mixer
Lining
Winch
Mortar Pump
Lining Machine
Mortar
Supply Hose
Lined Pipe
Trowel
Cleaned Pipe
Corroded Pipe
Up to 1000 ft.
Mortar Mixer
Trowels
Access Opening
Material
Lining
Machine
Lined Pipe
Mortar
Up to 2000/ft.
Cleaned Pipe
Mortar Supply
19
Engineering Encyclopedia
37 1/2
37 1/2
1/8 in.
Pipe Wall
1/16 in.
Cement Lining
2.
3.
Tack weld at four points 90 apart. Each tack weld should be one-quarter pipe diameter.
4.
The first layer of weld metal should be deposited with 1/8-in. electrode with welding machine set at 85 A and 23
V.
5.
The remaining process should be done with standard welding machine setting until 1/8 in. reinforcements is
obtained, as shown above.
Exposed Pipe
20