The Contractor is required to cover up and protect the whole of the works from damage caused by
weather.
1.11 PROGRESS PAYMENTS
The Contractor shall submit applications for progress payments to the Supervisor at the end of the first
four weeks work and thereafter at monthly intervals or as may be otherwise agreed. When requested,
applications are to be accompanied by wage sheets, delivery dockets, invoices or other information
relevant to the costs of labour and materials claimed. Claims are to include for authorised variations to
Contract carried out in the preceding month.
1.12 RETENTION SUM AND MAINTENANCE PERIOD
A sum equal to 5% of each Progress Claim will be retained by the Owner until the Date of Practical
Completion, after which date one half of this Retention Sum will be released and the remainder held
until expiration of the Defects Liability Period. Alternatively, the Builder may provide security in the
form of two Bank Guarantees, each such guarantee being for a sum equal to 2.5% of the Contract
Sum.
1.13 P.C. ITEMS
Refer to the Schedules at the back of this Specification and allow in the Tender Price the sums stated
opposite the various items for the supply only of these items. The Tender Sum is to include the
Contractor's allowance for the complete installation of all P.C. Items where applicable. In the final
account, the P.C. Sums listed in the Schedule will be adjusted against the nett costs of the Contractor
in the manner set out in the Contract Agreement.
1.14 PROVISIONAL SUMS
Refer to the Schedules and allow in the Tender Price the sums stated opposite the various items of
work and materials. In the final account the actual costs of these items to the Contractor will be
adjusted against the Provisional Sums allowed in accordance with the Contract Agreement.
8.1 EXTENT OF WORK
Work under this Part comprises the installation complete of all waste and stormwater drainage,
sanitary plumbing, hot and cold water service, grey water system and installation of all sanitary
fixtures and fitments.
8.2 GENERALLY
Carry out the whole of the soil and waste water drainage in strict accordance with this Specification,
the regulations of the relevant Local Government Ordinance(s), Council By-Laws and any specific
requirements of the Local Inspector. The whole of the work under this Part is to be carried out by or
under direct supervision of a fully licensed Plumber and Drainer. After inspection, testing and approval,
cover pipe runs by back-filling with sand to a minimum 75 mm depth above the pipe collars before
placing the remaining depth of approved filling material. All existing drainage lines, disturbed,
damaged and/or altered during the construction of the new building shall be made good, as required.
Drawings showing hydraulic services show the general layout and are diagrammatic only. The
Contractor is to prepare detailed layouts of services in conjunction with other trades, and to approval
of the Local inspector.
8.3 STORMWATER DRAINAGE
Refer to Engineers Drawings. Surface run-off and where possible sub-surface drainage, is to be
collected in a system of charged in-ground PVC pipework and directed to the stormwater silt-trap pit.
Drain pit into adjoining Public Reserve water-course with 150 diam PVC pipe and suitable anti-erosion
devices as directed on site.
8.4 ROOFWATER DRAINAGE
Roofwater drainage is to firstly be directed into the rainwater tank located under the building. Supply
and install a 5,000 litre rainwater storage tank where shown on plan. Refer to Gosford City Council's
"Guidelines For The Installation Of Rainwater Tanks" and install the system in full compliance with this
document and the requirements of Council's Development Control Plan No. 165 (DCP.165). Tank to be
fitted with a first flow diversion device to inlet. Provide overflow pipes connected to inground SW
drainage to flow to principal detention tank. Reticulate rainwater to all down-stream garden hosecocks
and to lower level toilet cistern. Provide top-up water supply to tank controlled by a float-operated
switch.
8.5 STORMWATER PITS
Where shown on the drawings, stormwater pits shall be precast concrete with fitted grated lids equal
to C.I. & D. Precast Pty Ltd Model DPM 450 x 450 x 600 deep. Inlets and outlet pipes are to be placed in
recessed knock-out sections of pit walls and inverts set min. 75mm above bottom of pit to form silttrap. Provide removable galvanised steel basket.
8.6 GRATED SW TRENCH
To cross driveway where shown on plan, provide and install a heavy duty grated pre-cast concrete
drainage trench equal to C.I. & D. Precast Pty Ltd Model No. TD3, full width and fitted with lengths of
610 x 225 x 20mm cast iron grating. Provide 90mm diam. PVC SW pipe drainage outlet and connect to
stormwater system.
8.7 WASTE DRAINAGE SYSTEM
Supply and connect all waste drainage from soil and wastes and fixtures. Provide all necessary pipes,
junctions, bends, back vents, gullies etc., and connect to existing sewer main. Allow for all excavation,
backfilling, testing and sundry equipment required to complete the installation. Provide and lay runs of
PVC drain pipes of required diameters in straight runs, bedded solid on the barrel and with uniform
falls. Make all jointing in accordance with current SAA Code. Insert inspection eyes at junctions and in
straight runs where directed but not more than 9m intervals. Connect all waste to inground wastewater collection tank where shown on the drawings. Provide and install a submersible maserating
pump and connect 50mm steel rising line to sewer manhole in Macdonald Street.