GTC-735 Scope of Works - R0
GTC-735 Scope of Works - R0
GTC-735 Scope of Works - R0
SECTION 3.1
PAGE 1 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
SECTION 3.1
SCOPE OF
WORKS
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 2 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
1.
2.
3.
PACKAGE S-1.......................................................................................................... 18
3.1.1
3.1.2
3.1.3
3.1.4
3.1.5
3.1.6
3.1.7
3.2
PACKAGE S-2.......................................................................................................... 58
3.2.1
3.2.2
3.2.3
3.2.4
3.3
PACKAGE S-3.......................................................................................................... 90
3.3.1
3.3.2
3.3.3
3.3.4
3.4
3.4.1
3.4.2
3.4.3
3.4.4
3.5
3.5.1
3.5.2
3.5.3
3.5.4
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 3 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
3.6
REV. 0
3.6.1
3.6.2
3.6.3
3.6.4
3.7
3.7.1
3.7.2
3.8
3.8.1
3.8.2
3.8.3
3.8.4
3.9
3.9.1
3.9.2
3.9.3
3.9.4
3.10
3.10.1
3.10.2
3.10.3
3.10.4
3.11
3.11.1
3.11.2
3.11.3
3.11.4
3.12
3.12.1
3.12.2
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 4 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
3.12.3
3.13
REV. 0
3.13.1
3.13.2
3.13.3
3.13.4
3.14
3.14.1
3.14.2
3.14.3
3.14.4
3.15
3.15.1
3.15.2
3.15.3
3.15.4
3.16
3.16.1
3.16.2
3.16.3
3.16.4
3.17
3.17.1
3.17.2
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 5 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
3.17.3
3.17.4
3.17.5
3.17.6
3.17.7
3.18
3.18.1
3.18.2
3.18.3
3.18.4
3.19
3.19.1
4.
5.
6.
7.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 6 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
1. SCOPE OF WORKS
Description of works
Kahramaa intends to expand the existing Power transmission network under the project entitled
Qatar Power Transmission System Expansion Phase 13 - Substations to meet with the
increased Power demand due to the developmental works in the State of Qatar. Details of the
complete project are summarized in the Section 2 below.
The following tenders are issued at the same time, and the contractor should be also aware of the
influence of the works covered by the other Tenders:
GTC 735/2015 Substations (This tender);
GTC 736/2015 Cables
The works of the Project are spread all over the State of Qatar including both newly and already
developed areas. The details which are available at the time of preparation of this Tender
Documents are shown on the Location maps enclosed. The exact coordinates and ground
elevation shall be coordinated with the concerned Authorities during the project execution stage.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 7 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 8 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
66/11kV Umm Al Amad - 1: New Transmission Substation incorporating 66kV GIS, 11kV metal
enclosed switchgear (GIS/AIS), 2 x 66/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary
Transformers, other associated equipment and works as required and indicated elsewhere in the
Tender document.
132/11kV Umm Garn: New Transmission Substation incorporating 132kV GIS, 11kV metal
enclosed switchgear (GIS/AIS), 2 x 132/11kV, 40MVA Power Transformers, 2 x 132kV, 15MVAr
Shunt Reactors, 11/0.415kV Auxiliary Transformers, other associated equipment and works as
required and indicated elsewhere in the Tender document.
66/11kV Abu Thailah (Upgrade): Existing 66/11kV substation (built under Phase 7 Project) shall
be expanded by addition of new 11kV metal enclosed switchgear (GIS/AIS), 2 x 66/11kV, 40MVA
Power Transformers and other associated equipment and works as required and indicated
elsewhere in the Tender document.
PACKAGE S-3 (NEW 132KV S/S)
132/11kV Al Jahhaniya 2: New Transmission Substation incorporating 132kV GIS, 11kV metal
enclosed switchgear (GIS/AIS), 2 x 132/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary
Transformers, other associated equipment and works as required and indicated elsewhere in the
Tender document.
132/11kV Izghawa North: New Transmission Substation incorporating 132kV GIS, 2 x 11kV metal
enclosed switchgears (GIS/AIS), 4 x 132/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary
Transformers, other associated equipment and works as required and indicated elsewhere in the
Tender document.
132/11kV Mesaieed Industrial-A: Existing 132/33/11kV substation shall be completely
refurbished with the new equipment incorporating 132kV GIS, 33kV GIS, 11kV metal enclosed
switchgear (GIS/AIS), 2 x 132/33kV, 100MVA and 2 x 132/11kV, 40MVA Power Transformers,
11/0.415kV Auxiliary Transformers, other associated equipment and works as required and
indicated elsewhere in the Tender document.
132/11kV Wakrah 3: New Transmission Substation incorporating 132kV GIS, 11kV metal
enclosed switchgear (GIS/AIS), 2 x 132/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary
Transformers, other associated equipment and works as required and indicated elsewhere in the
Tender document.
PACKAGE S-4 (REFURBISHMENT/REPLACEMENT OF THE EXISTING S/S and NEW 66KV
S/S)
66/11kV New Assiri (Replacement): Existing 66/11kV substation shall be completely replaced
with the New Transmission Substation incorporating 66kV GIS, 11kV metal enclosed switchgear
(GIS/AIS), 2 x 66/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary Transformers, other
associated equipment and works as required and indicated elsewhere in the Tender document.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 9 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
66/11kV Salwa Road (Replacement): Existing 66/11kV substation shall be completely replaced
with the New Transmission Substation incorporating 66kV GIS, 11kV metal enclosed switchgear
(GIS/AIS), 2 x 66/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary Transformers, other
associated equipment and works as required and indicated elsewhere in the Tender document.
66/11kV Bin Mahmoud North: New 66/11kV Transmission Substation incorporating 66kV GIS,
11kV metal enclosed switchgear (GIS/AIS), 2 x 66/11kV, 40MVA Power Transformers, 11/0.415kV
Auxiliary Transformers, other associated equipment and works as required and indicated
elsewhere in the Tender document.
66/11kV Musherib (Refurbishment): Existing 66/11kV substation shall be completely refurbished
with the new equipment incorporating 11kV metal enclosed switchgear (GIS/AIS), 2 x 66/11kV,
40MVA Power Transformers, 11/0.415kV Auxiliary Transformers, other associated equipment and
works as required and indicated elsewhere in the Tender document.
PACKAGE S-5 (UPGRADE OF THE EXISTING S/S and NEW 66kV S/S)
66/11kV Murrah South: New 66/11kV Transmission Substation incorporating 66kV GIS, 2 x 11kV
metal enclosed switchgear (GIS/AIS), 4 x 66/11kV, 40MVA Power Transformers, 11/0.415kV
Auxiliary Transformers, other associated equipment and works as required and indicated
elsewhere in the Tender document.
66/11kV Umm Al Seneem 2 New 66/11kV Transmission Substation incorporating 66kV GIS, 11kV
metal enclosed switchgear (GIS/AIS), 2 x 66/11kV, 40MVA Power Transformers, 11/0.415kV
Auxiliary Transformers, other associated equipment and works as required and indicated
elsewhere in the Tender document.
66/11kV Al Waab (Upgrade): Existing 66/11kV transformer feeder substation (built under Phase 6
Project by M/s Siemens) shall be expanded by addition of new 66kV GIS, 11kV metal enclosed
switchgear (GIS/AIS), 2 x 66/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary
Transformers and other associated equipment and works as required and indicated elsewhere in
the Tender document.
66/11kV Al Waab 2: New 66/11kV Transmission Substation incorporating 66kV GIS, 11kV metal
enclosed switchgear (GIS/AIS), 2 x 66/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary
Transformers, other associated equipment and works as required and indicated elsewhere in the
Tender document.
PACKAGE S-6 (UPGRADE OF THE EXISTING S/S and NEW 132kV S/S)
132/66/11kV Maither Central (Upgrade): Existing 132/66/11kV transformer feeder substation
(built under Phase 5 Project) shall be expanded by extension of the existing 66kV GIS, addition of
new 11kV metal enclosed switchgear (GIS/AIS), 2 x 66/11kV, 40MVA Power Transformers,
11/0.415kV Auxiliary Transformers and other associated equipment and works as required and
indicated elsewhere in the Tender document.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 10 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
66/11kV Museum Road (Upgrade): Existing 66/11kV substation (built under Phase 6 Project by
M/s ABB) shall be expanded by extension of the existing 66kV GIS, addition of new 11kV metal
enclosed switchgear (GIS/AIS), 2 x 66/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary
Transformers and other associated equipment and works as required and indicated elsewhere in
the Tender document.
132/11kV Ain Sinan: New Transmission Substation incorporating 132kV GIS, 11kV metal
enclosed switchgear (GIS/AIS), 2 x 132/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary
Transformers, other associated equipment and works as required and indicated elsewhere in the
Tender document.
132/11kV Jeryan Jenaihat-1: New Transmission Substation incorporating 132kV GIS, 11kV metal
enclosed switchgear (GIS/AIS), 2 x 132/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary
Transformers, other associated equipment and works as required and indicated elsewhere in the
Tender document.
PACKAGE S-7 (REPLACEMENT OF THE EXISTING 66KV S/S)
66/11kV New Doha E (Replacement): Existing 66/11kV substation shall be completely replaced
with the New Transmission Substation incorporating 66kV GIS, 2 x 11kV metal enclosed
switchgear (GIS/AIS), 4 x 66/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary
Transformers, other associated equipment and works as required and indicated elsewhere in the
Tender document.
66/11kV Salata (Replacement): Existing 66/11kV substation shall be completely replaced with the
New Transmission Substation incorporating 66kV GIS, 11kV metal enclosed switchgear (GIS/AIS),
2 x 66/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary Transformers, other associated
equipment and works as required and indicated elsewhere in the Tender document.
PACKAGE S-8 (NEW 132KV S/S at Wukair/Mashaf area)
132/11kV Mashaf 1: New Transmission Substation incorporating 132kV GIS, 11kV metal enclosed
switchgear (GIS/AIS), 2 x 132/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary
Transformers, other associated equipment and works as required and indicated elsewhere in the
Tender document.
132/11kV Mashaf 2: New Transmission Substation incorporating 132kV GIS, 11kV metal enclosed
switchgear (GIS/AIS), 2 x 132/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary
Transformers, other associated equipment and works as required and indicated elsewhere in the
Tender document.
132/11kV Mashaf 3: New Transmission Substation incorporating 132kV GIS, 11kV metal enclosed
switchgear (GIS/AIS), 2 x 132/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary
Transformers, other associated equipment and works as required and indicated elsewhere in the
Tender document.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 11 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
132/11kV Al Wukair 10: New Transmission Substation incorporating 132kV GIS, 11kV metal
enclosed switchgear (GIS/AIS), 2 x 132/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary
Transformers, other associated equipment and works as required and indicated elsewhere in the
Tender document.
PACKAGE S-9 (NEW 132KV S/S at Wukair area)
132/11kV Al Wukair 9: New Transmission Substation incorporating 132kV GIS, 11kV metal
enclosed switchgear (GIS/AIS), 2 x 132/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary
Transformers, other associated equipment and works as required and indicated elsewhere in the
Tender document.
132/11kV Al Wukair 8: New Transmission Substation incorporating 132kV GIS, 11kV metal
enclosed switchgear (GIS/AIS), 2 x 132/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary
Transformers, other associated equipment and works as required and indicated elsewhere in the
Tender document.
132/11kV Al Wukair 7: New Transmission Substation incorporating 132kV GIS, 11kV metal
enclosed switchgear (GIS/AIS), 2 x 132/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary
Transformers, other associated equipment and works as required and indicated elsewhere in the
Tender document.
132/11kV Al Wukair 6: New Transmission Substation incorporating 132kV GIS, 11kV metal
enclosed switchgear (GIS/AIS), 2 x 132/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary
Transformers, other associated equipment and works as required and indicated elsewhere in the
Tender document.
PACKAGE S-10 (NEW 132KV S/S at Wukair area)
132/11kV Al Wukair 5: New Transmission Substation incorporating 132kV GIS, 11kV metal
enclosed switchgear (GIS/AIS), 2 x 132/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary
Transformers, other associated equipment and works as required and indicated elsewhere in the
Tender document.
132/11kV Al Wukair 4: New Transmission Substation incorporating 132kV GIS, 2 x 11kV metal
enclosed switchgear (GIS/AIS), 4 x 132/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary
Transformers, other associated equipment and works as required and indicated elsewhere in the
Tender document.
132/11kV Al Wukair 3: New Transmission Substation incorporating 132kV GIS, 11kV metal
enclosed switchgear (GIS/AIS), 2 x 132/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary
Transformers, other associated equipment and works as required and indicated elsewhere in the
Tender document.
132/11kV Al Wukair 2: New Transmission Substation incorporating 132kV GIS, 11kV metal
enclosed switchgear (GIS/AIS), 2 x 132/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary
Transformers, other associated equipment and works as required and indicated elsewhere in the
Tender document.
GTC-735 SCOPE OF WORKS R0
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 12 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 13 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
One No. of 132/11kV Framework Substation Type C: New Transmission Substation incorporating
132kV GIS with Single busbar, 11kV metal enclosed switchgear (GIS/AIS), 2 x 132/11kV, 40MVA
Power Transformers, 11/0.415kV Auxiliary Transformers, other associated equipment and works
as required and indicated elsewhere in the Tender document.
PACKAGE S-14 (NEW 132KV FRAMEWORK S/S)
Two Nos. of 132/11kV Framework Substation Type A: New Transmission Substation
incorporating 132kV GIS, 2 x 11kV metal enclosed switchgear (GIS/AIS), 4 x 132/11kV, 40MVA
Power Transformers, 11/0.415kV Auxiliary Transformers, other associated equipment and works
as required and indicated elsewhere in the Tender document.
Two Nos. of 132/11kV Framework Substation Type B: New Transmission Substation
incorporating 132kV GIS, 11kV metal enclosed switchgear (GIS/AIS), 2 x 132/11kV, 40MVA Power
Transformers, 11/0.415kV Auxiliary Transformers, other associated equipment and works as
required and indicated elsewhere in the Tender document.
One No. of 132/11kV Framework Substation Type C: New Transmission Substation incorporating
132kV GIS with Single busbar, 11kV metal enclosed switchgear (GIS/AIS), 2 x 132/11kV, 40MVA
Power Transformers, 11/0.415kV Auxiliary Transformers, other associated equipment and works
as required and indicated elsewhere in the Tender document.
PACKAGE S-15 (NEW 66KV FRAMEWORK S/S)
Two Nos. of 66/11kV Framework Substation Type A: New Transmission Substation incorporating
66kV GIS, 2 x 11kV metal enclosed switchgear (GIS/AIS), 4 x 66/11kV, 40MVA Power
Transformers, 11/0.415kV Auxiliary Transformers, other associated equipment and works as
required and indicated elsewhere in the Tender document.
Two Nos. of 66/11kV Framework Substation Type B: New Transmission Substation incorporating
66kV GIS, 11kV metal enclosed switchgear (GIS/AIS), 2 x 66/11kV, 40MVA Power Transformers,
11/0.415kV Auxiliary Transformers, other associated equipment and works as required and
indicated elsewhere in the Tender document.
One No. of 66/11kV Framework Substation Type C: New Transmission Substation incorporating
66kV GIS with Single busbar, 11kV metal enclosed switchgear (GIS/AIS), 2 x 66/11kV, 40MVA
Power Transformers, 11/0.415kV Auxiliary Transformers, other associated equipment and works
as required and indicated elsewhere in the Tender document.
PACKAGE S-16 (NEW 66KV FRAMEWORK S/S)
Two Nos. of 66/11kV Framework Substation Type A: New Transmission Substation incorporating
66kV GIS, 2 x 11kV metal enclosed switchgear (GIS/AIS), 4 x 66/11kV, 40MVA Power
Transformers, 11/0.415kV Auxiliary Transformers, other associated equipment and works as
required and indicated elsewhere in the Tender document.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 14 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Two Nos. of 66/11kV Framework Substation Type B: New Transmission Substation incorporating
66kV GIS, 11kV metal enclosed switchgear (GIS/AIS), 2 x 66/11kV, 40MVA Power Transformers,
11/0.415kV Auxiliary Transformers, other associated equipment and works as required and
indicated elsewhere in the Tender document.
One No. of 66/11kV Framework Substation Type C: New Transmission Substation incorporating
66kV GIS with Single busbar, 11kV metal enclosed switchgear (GIS/AIS), 2 x 66/11kV, 40MVA
Power Transformers, 11/0.415kV Auxiliary Transformers, other associated equipment and works
as required and indicated elsewhere in the Tender document.
PACKAGE S-17 (NEW 66KV FRAMEWORK S/S without civil works or underground)
One No. of 66/11kV Framework Substation: New Transmission Substation incorporating 66kV
GIS, 2 x 11kV metal enclosed switchgear (GIS/AIS), 4 x 66/11kV, 40MVA Power Transformers,
11/0.415kV Auxiliary Transformers, other associated equipment and works as required and
indicated elsewhere in the Tender document. Civil works shall be done by others.
One No. of 66/11kV Framework Substation: New Transmission Substation incorporating 66kV
GIS, 11kV metal enclosed switchgear (GIS/AIS), 2 x 66/11kV, 40MVA Power Transformers,
11/0.415kV Auxiliary Transformers, other associated equipment and works as required and
indicated elsewhere in the Tender document. Civil works shall be done by others.
One No. of 66/11kV Underground Framework Substation: New Transmission Substation
incorporating 66kV GIS, 2 x 11kV metal enclosed switchgear (GIS/AIS), 4 x 66/11kV, 40MVA
Power Transformers, 11/0.415kV Auxiliary Transformers, other associated equipment and works
as required and indicated elsewhere in the Tender document. Civil works shall be done by others.
One No. of 66/11kV Underground Framework Substation: New Transmission Substation
incorporating 66kV GIS, 11kV metal enclosed switchgear (GIS/AIS), 2 x 66/11kV, 40MVA Power
Transformers, 11/0.415kV Auxiliary Transformers, other associated equipment and works as
required and indicated elsewhere in the Tender document. Civil works shall be done by others.
One No. of 66/11kV Underground Framework Substation: New Transmission Substation
incorporating 66kV GIS, 2 x 11kV metal enclosed switchgear (GIS/AIS), 4 x 66/11kV, 40MVA
Power Transformers, 11/0.415kV Auxiliary Transformers, other associated equipment and works
as required and indicated elsewhere in the Tender document.
One No. of 66/11kV Underground Framework Substation: New Transmission Substation
incorporating 66kV GIS, 11kV metal enclosed switchgear (GIS/AIS), 2 x 66/11kV, 40MVA Power
Transformers, 11/0.415kV Auxiliary Transformers, other associated equipment and works as
required and indicated elsewhere in the Tender document.
PACKAGE S-18 TELECOMMUNICATION
Telecommunication System: New telecommunication equipment shall be provided for
connection of new and refurbished substations to Kahramaa Telecommunication System including
all works necessary to connect these substations to NCC/ENCC/DCC and to keep existing
GTC-735 SCOPE OF WORKS R0
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 15 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
connections of existing substations being modified, replaced or upgraded under the scope of this
Tender - as per Detailed Technical Specification in Volume 3.
PACKAGE S-19 INSTALLATION OF CAPACITOR BANKS
New Capacitor banks installation at the existing 11kV switchgear of several primary substations.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 16 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 17 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
general arrangement drawings for the substation buildings. Commercial offer shall be based on the
subject drawings, considering specified minimum clearances and operation distance requirements
specified in Section 6.3 of this document and related specification, considering actual Scope of
Works and offered equipment. Bidder is obliged to ensure that buildings are properly sized and to
provide relevant layout drawings within the Technical offer. Accordingly, no price variations will be
allowed for change of the building size in the later stage of Contract. Part of civil works such as
perimeter wall/fence, access road and filling works will be measured and paid as per actual
quantities.
Remote end modifications: Specifications enclosed with the Contract shall be applicable for all
modification works at remote end substations constructed under all earlier Kahramaa projects and
which will be connected to substations, subject of this Contract. Therefore protection relays (Main
relays, Trip relays and TCS relays) need to be changed if required under new scheme. Also
replacement of CTs is anticipated, and for this work separate unit price shall be provided. However
for detailed scope please refer under remote end modification works for the concerned remote end
substations.
It shall be noted that many of the substations considered as Remote End Substations are
currently under construction and all the equipment/systems will be under warranty for a period of 2
years from its date of Taking Over. Hence, in case the equipment/system is still under warranty
during modification under the scope of this project, the Contractor shall execute the works in such
a way as not to dilute or nullify existing warranties in any way, whatsoever. All details of work such
as, method statements, interface requirements, intended subcontractors, etc. shall be discussed
and agreed with Kahramaa well in advance of the scheduled commencement date of such works
and full clarity shall be established. The same is applicable for modification on the cable lines
which are part of this Contract.
Connection to NCC/ENCC/DCC: All modification works at Kahramaa control centers
NCC/ENCC/DCC to include new and modified / upgraded / refurbished existing substations will be
covered under a separate Contract. The scope of substation Contractor under this project includes
all interfacing works with the above Contractor, necessary to include new substations and
modifications to existing substations into the NCC, ENCC and DCC, including interoperability and
end-to-end testing. This includes co-ordination works with above Contractor during all stages until
commissioning and end to end test.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 18 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
PACKAGE S-1
3.1
3.1.1
Establish 220kV, 4000A at 40C, 50kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Two (2) Nos. outgoing Transformer bays for 220/132kV Transformers suitable
for cable connection as per the approved connection arrangement;
- Two (2) Nos. Shunt Reactor bays suitable for cable connection as per the
approved connection arrangement;
- Six (6) Nos. cable feeder bays (four (4) Nos. spare);
- Space for four future bays, two on each side of the switchgear;
Establish 132kV, 3150A at 40C, 40kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Two (2) Nos. incoming Transformer bays for 220/132kV Transformers suitable
for GIB connection as per the approved connection arrangement;
- Two (2) Nos. outgoing Transformer bays for 132/11kV Transformers;
- Eight (8) Nos. Cable feeder bays (four (4) Nos. spare);
- Two (2) Nos. 132kV, 315MVA bus duct between 220/132kV Power
Transformers and 132kV GIS;
- Space for four future bays, two on each side of the switchgear;
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 19 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Two (2) Nos. 220kV, 60MVAr Shunt Reactors with terminal CTs, neutral CTs etc.
Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.5 ohm at 50C
rated for 750A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 32/40MVA Power Transformer.
Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 2000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%, 6%
impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformers to be supplied shall be of adequate capacity to cater to the total
station load with additional 30% margin. The capacity of the Transformer is to be
justified by calculation note which shall be subject to approval.
Protection:
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
(in line with remote end protection scope of works) shall be provided for feeders
connected to UAAS substation. The new relays to be installed at 220/132/11kV Al
Shahhaniyah Super substation shall match the protection at UAAS substation end.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 20 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.
For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.
Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.
Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 21 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
- Integrated HMI workstation for monitoring system including software for each
online condition monitoring system installed in S/S as well as for their remote
access;
- Necessary LAN & WAN equipment including router/firewall for connection to
remote end.
LV Power Cables, Control Cables with all accessories
Earthing & Lightning Protection
Small Power & Lighting
LV Service Equipment
Security Management System according to specification enclosed in section 3.3.15.
All civil works related to new 220/132/11kV substation including building services.
Note: The architectural appearance of the Substation buildings and boundary wall shall
aesthetically match with the structures in the surrounding area and is subject to approval
of concerned authorities. All design approvals in this regard shall be coordinated with the
concerned authorities.
220kV and 132kV GIS and Fire Pump room Cranes
Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
Fire Fighting System
Deluge Water Spray System for Power Transformers, Shunt Reactors & Auxiliary
Transformers
Fire hydrant and ring main piping (all around the substation buildings perimeter).
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Shunt Reactors, Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 22 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises
220kV, 1x1600mm2, XLPE, 315MVA, double circuit, single point earthed with
earth continuity conductor cable links between 220kV GIS and 220/132kV
Transformers, laid in unfilled concrete troughs with all accessories. Approx. route
length: 100m.
220kV, 1x500mm2, XLPE, 60MVA, double circuit, solid bonded cable links
between 220kV GIS and 220kV Shunt Reactors, laid in unfilled concrete troughs
with all accessories. Approx. route length: 100m.
132kV, 1x2000mm2, XLPE, 315MVA, double circuit, single point earthed with
earth continuity conductor cable links between 132kV GIS and 220/132kV Power
Transformers laid in unfilled concrete troughs with all accessories. Approx. route
length: 100m. (alternative to 132kV GI bus duct in case of layout difficulty)
132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
11kV, 1x500mm2, XLPE, 2000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 23 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
REMOTE END WORKS AT UAAS S/S
400/220/66/11kV Umm Al Amad Super is an existing substation with 400kV GIS, 220kV
GIS, 66kV GIS and 11kV Switchgear built by Alstom under Phase 8 Project. UAAS will be
connected to Al Shahhaniyah Super by the new 220kV Double Circuit cable connection.
All required modifications, End to End test, testing and commissioning and putting into
service of the two circuits shall be carried out under the scope of this project. Modification
works at UAAS shall be arranged in a way not to affect the Warranty Period, if still valid at
the time of new works.
The SOW includes but is not limited to the following:
Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.
Protection
Two 2x220kV existing bays to be connected to Al Shahhaniyah Super substation are with
Protection Relays/Equipments under GTC/144A/2006 Phase-8 project.
The relay provided at UAAS for Main-1 protection is Alstom make P545 and for
Main-2 Protection is Siemens make 7SD5. The new Relays/Equipment to be
installed at Al Shahhaniyah Super substation should match the protection at 220kV
UAAS Substation end (supplied under Phase-8 project).
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 24 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.
Alarms no more required shall be deleted and those related to modifications are to
be included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.
Protection
The relays provided at Al Thumamah Super for Main-1 protection is Siemens make
7SD5 and for Main-2 protection is Alstom make P545. The new relays/equipment
to be installed at Old Airport substation should match the protection at 132kV Al
Thumamah Super substation end (supplied under Phase-11 project).
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 25 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Retesting of the relays/equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.
Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.
Alarms no more required shall be deleted and those related to modifications are to
be included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.
Protection
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 26 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
3.1.2
REV. 0
The relays provided at Al Old Airport for Main-1 protection is ABB make RED670
and for Main-2 protection is Siemens make 7SD522. Relays shall match protection
at Al Thumamah Super.
Retesting of the relays/equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.
Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.
Establish 132kV, 3150A @ 40C, 40kA / 1 sec, 3-phase, 50Hz double bas bar
GIS consisting of following bays:
- Two (2) Bus section bays;
- Two (2) Bus coupler bays;
- Two (2) 40MVA outgoing Transformer feeder bays for 132/11kV Transformers;
- Six (6) cable feeder bays (four (4) Nos. spare);
- Space for four future bays, two on either side of the switchgear;
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. bus section bay rated 2500A;
- Two (2) Nos. Incomers for 132/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Bays for outgoing feeders rated 630A;
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 27 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 40MVA Power Transformer.
Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformers to be supplied shall be of adequate capacity to cater to the total
station load with additional 30% margin. The capacity of the Transformer is to be
justified by calculation note which shall be subject to approval.
Protection Systems
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote ends
(in line with remote end protection scope) shall be provided for feeders connected
to remote end substation.
For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.
For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the capacitor
bank bay.
Separate panel shall be provided for each of the 11kV incomer bays and each of
the Auxiliary Transformer bays. Separate load shedding panel shall be provided for
11kV outgoing feeders of each Switchgear, i.e., for a two Switchgear Substation (A
& B) there shall be two load shedding panels.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 28 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
132kV GIS shall be equipped with the internal UHF couplers so the retrofitting can
be easily done in the future (sensor location shall be done as per Specification for
PDM)
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 29 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
of connection points for installation of TEP System (if Kahramaa decides to adopt
this system in future).
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material for all the MEP openings
including HVAC & Fire/Smoke damper openings, floor openings such as panel
openings including future openings, cable openings (spare/future) & all other cable
openings such as substation cables, 11kV outgoing feeders and all cables inside
the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises.
132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary Transformers.
Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 30 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
The remote end substation, Al Shahhaniya Super, is also to be built under the same
package and will be connected to the new Shahhaniya South S/S with 2x132kV cable
circuits. The cables will be installed under separate contract (GTC/736/2015, Package
C3). The substation contractor shall coordinate with cable contractor and complete all
necessary works for putting these feeders into service.
3.1.3
Establish 132kV, 3150A @ 40C, 40kA / 1 sec, 3-phase, 50Hz double bas bar
GIS consisting of following bays:
- Two (2) Bus section bays;
- Two (2) Bus coupler bays;
- Two (2) 40MVA outgoing Transformer feeder bays for 132/11kV Transformers;
- Six (6) cable feeder bays (four (4) Nos. spare);
- Space for four future bays, two on either side of the switchgear;
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. bus section bay rated 2500A;
- Two (2) Nos. Incomers for 132/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Bays for outgoing feeders rated 630A;
- Two (2) Nos. Bays for future capacitor banks feeders;
- Two (2) Nos. Feeders for 11/0.415kV Auxiliary Transformers;
- Space for four future bays, two on either side of the switchgear;
Alternatively 11kV GIS is also acceptable.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 31 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 40MVA Power Transformer.
Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformers to be supplied shall be of adequate capacity to cater to the total
station load with additional 30% margin. The capacity of the Transformer is to be
justified by calculation note which shall be subject to approval.
Protection Systems
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote ends
(in line with remote end protection scope) shall be provided for feeders connected
to remote end substation.
For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.
For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the capacitor
bank bay.
Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 32 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
132kV GIS shall be equipped with the internal UHF couplers so the retrofitting can
be easily done in the future (sensor location shall be done as per Specification for
PDM)
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 33 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material for all the MEP openings
including HVAC & Fire/Smoke damper openings, floor openings such as panel
openings including future openings, cable openings (spare/future) & all other cable
openings such as substation cables, 11kV outgoing feeders and all cables inside
the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises.
132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary Transformers.
Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 34 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
cables will be installed under separate contract (GTC/736/2015, Package C3). The
substation contractor shall coordinate with cable contractor and complete all necessary
works for putting these feeders into service.
3.1.4
Establish 220kV, 4000A at 40C, 50kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Three (3) Nos. outgoing Transformer bays for 220/66kV Transformers suitable
for cable connection as per the approved connection arrangement;
- Six (6) Nos. cable feeder bays (three (3) Nos. spare);
- Space for four future bays, two on each side of the switchgear;
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 35 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Power Transformers
Protection Systems
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with the existing
equipment and with remote ends (in line with remote end protection scope) shall be
provided for the new feeders. However, the following specific requirements shall be
considered:
Contractor is responsible to lay control cables (as necessary) and fibre Optic
Cables from existing OTP installed in telecom room up to new 220kV control room
to complete the necessary connection and end-to-end test of protection for the said
links (New control room in Doha Super to Airport Super).
One new 66kV transformer LV bay shall be provided as detailed in Main Scope of
the Work. New protection relays based on Phase 13 specifications shall be
provided.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 36 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
panels and exact details shall be decided during detail engineering. Existing Cable
Differential relays provided 220kV HV panels and any other relays shall be
dismantled and returned to Kahramaa store according to the standard procedure.
Contractor shall ensure that the relays provided in 220kV Transformer HV Bays
protection panels and those installed in 66kV LV bay protection panels are
complete so as to achieve a complete functional protection for the Transformers.
Testing and commissioning of the new 200/66kV Transformers shall be done in
order to provide complete protection.
Existing AVR equipments shall be used which are connected to 220kV side. It is
not be required to shift to new 220kV Control room; however, it shall be decided
during detailed engineering. Existing AVR equipment shall be tested and its proper
functioning shall be ensured by the Contractor. Third AVR of new 200/66kV,
200MVA transformer may not be required to be integrated with two existing AVRs.
However, all other features which are not dependent on existing AVR schemes
shall be incorporated in accordance to specification requirement.
Modification of the existing 66kV bus bar protection, including conducting bus bar
stability and addition of modules required shall be the responsibility of the
Contractor.
Direct inter-trip for breaker failure, Pole discrepancy and Bus bar protection
operation are to be made available between the stations based on requirement.
All modification, testing and commissioning, relay setting calculation, relay testing
on final setting, Transformer differential and REF stability etc. and putting in service
is included in the scope.
Alarms no more required shall be deleted and those related to modifications are to
be included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.
GPS upgrade shall be carried out to accommodate CMS Time Synchronization for
SCS, CMS, Telecom, etc. The existing GPS shall be handed over to KM.
For new common alarms contractor will use additional BCUs to maintain 20%
spare availability.
SCS software upgrade to the latest stable version shall be carried out.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 37 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Min. 24 port Ethernet switch with VLAN capability shall be provided in NCC to
enable the PMR service.
Works necessary to shift the PMR server and existing Telecom link to new
switches in coordination with Telecom contractor. New CAT6 Ethernet cables shall
be laid from new switch to PMR servers and all Telecom ports.
LV Power Cables, Control Cables with all accessories for the new equipment as well
as for the connections to the existing equipment/systems. Sizing and Voltage drop
calculation shall be strictly carried out for the cables to be proposed from existing LV
services to the new building.
FO cable links to connect existing OTP to new OTP to maintain existing telecom
connectivity
Earthing & Lightning Protection including connection to the existing system
Small Power & Lighting
LV Service Equipment and Works comprising of:
The new LVAC Sub Distribution Board, for the new 220kV GIS building, 220/66kV
transformer and HVAC units, and will be connected to the existing LVAC
switchboard. Spare feeders are available in the existing LVAC Board.
Modifications, if any, required for the above connections shall also be carried out.
The existing LVAC switchboard shall be extended to enable connection of the new
LVAC Sub Distribution Board.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 38 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
The new LVDC Board, Battery and battery charger for the 220kV GIS & associated
protection systems accommodated in the new building and for the new 220/66kV
transformer.
New UPS to cater the additional load requirements in the new building.
Security management system shall cover both existing and new substation building
and open areas. If due to bidders design there are more than one control rooms,
the bidder shall be bound to provide additional SMS material, if required, for both
control rooms.
Laying, termination and testing of copper cables to extend Telephones from old to
new building.
Laying, termination and testing of two FO single mode cables (2 * 48F) from old to
new building including OTBs in new building.
Civil works:
All civil works related to new 220kV GIS, the new 220/66kV transformer including
building services and modifications of the existing building basement to enable
cable routing.
220kV and 66kV Cable troughs for laying cables between new GIS/Transformers
to existing transformers/GIS including duct banks and cross over arrangement with
existing cable corridors.
LV cable troughs/duct banks for routing LV power & control cables, FO cables of
SCADA/ Telecom etc between new and existing buildings.
New 220kV GIS building shall have space for 220kV GIS, 220kV Relay Panels
and LV AC/DC Sub Distribution Boards and Battery room.
Deluge Water Spray System for Power Transformer including related civil works
such as trenches (@ road crossing for deluge pipes as & where required).
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 39 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Tie-in works for connection with the existing deluge system / fire mains / fire
pumping station
Fire Detection & Alarm System for the Transformer, GIS building, other areas and
tie-in (connection/interfacing with existing fire detection & alarm system)
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all new cables (EHV, HV, MV &
LV including cable trays) for the entire length of the cable.
Passive fire protection system Fire Sealant material for all the MEP openings
including HVAC & Fire/Smoke damper openings, floor openings such as panel
openings including future openings, cable openings (spare/future) & all other cable
openings such as substation cables, 11kV outgoing feeders and all cables inside
the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises.
Required modification works with the existing system (tie-in) for Fire Detection and
Alarm System, testing & commissioning, battery calculations, replacement of
batteries (as per calculations, if required) etc. in the existing Fire Detection &
Alarm System (which must be verified during commissioning) are included in the
present scope of works.
EPC Contractor must engage the services of the vendor or specialist Fire
contractor involved in PH8 Contract during the tie-in works with the existing Fire
Detection & Alarm System. Commissioning works must be carried out only by the
authorized vendor or Fire contractor who has installed the existing system.
Existing Fire Protection & Fire Detection & Alarm System drawings shall be
updated. Connection to the existing Underground Remote Oil Containment
Tank, if available OR new underground Remote Oil Containment Tank shall be
constructed nearby to the 200MVA Transformer.
Power cables
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 40 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
220kV, 1x1200mm2, XLPE, 200MVA, double circuit, single point earthed with
earth continuity conductor cable link between 220kV GIS and the existing
220/66kV Transformers, laid in unfilled concrete troughs with all accessories.
Approx. route length: 100m.
220kV, 1x1200mm2, XLPE, 200MVA, single circuit, single point earthed with
earth continuity conductor cable link between 220kV GIS and the new 220/66kV
Transformer, laid in unfilled concrete troughs with all accessories. Approx. route
length: 50m.
66kV, 1x2000mm2, XLPE, 200MVA, single circuit, single point earthed with earth
continuity conductor, two (2) cables per phase cable link between 220/66kV
Transformers and 66kV GIS, laid in unfilled concrete troughs with all accessories.
Approx. route length: 100m.
Milestone A
Complete 220kV GIS, 220/66kV Transformer, remote end works at Naeeja Super
and energize substation from Naeeja Super.
Milestone B
Diversion of the existing 220kV Incoming Cables from the existing 220/66kV
transformers into new 220kV GIS and connect the existing 220/66kV transformers
on to new 220kV GIS. Remote end works at Airport Super.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 41 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
works including, wiring, testing & complete re-commissioning of the above GIS
bays.
Alarms no more required shall be deleted and those related to modifications are to
be included in SCS and TMMC/TDB/RTU.
Protection
Two 2x220kV existing (D30 and D40) bays to be connected to new GIS at Doha
Super substation are already equipped with the Protection Relays/Equipments
under GTC/144A/2006 Phase-8 project.
The relay provided at Airport Super for Main-1 protection is Alstom make P545 and
for Main-2 Protection is Siemens make 7SD5. The new Relays/Equipment to be
installed at Doha Super substation should match the protection at 220kV Airport
Super Substation end (supplied under Phase-8 project).
All the required modifications in existing bays with provision of additional auxiliary
relays, BCU/TMMC panels wiring etc. to meet the Phase-13 protection requirement
shall be responsibility of contractor.
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.
Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.
DTS
Re-commissioning of existing DTS Unit of SENSA make, model DTS 800 M12-6.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 42 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
220/132/66/11kV Naeeja Super is an existing Substation with 132kV GIS, 66kV and 11kV
Switchgear constructed by Siemens under Phase 6 and further upgraded with addition of
220kV GIS by Hyosung under Phase 10 Project. Naeeja Super will be connected with
Doha Super by 1x220kV Cable circuit under separate Contract (GTC/736/2015, Package
C2).
All required modifications, End to End test, Testing & Commissioning and putting into
service of the single new single circuit shall be carried out under the scope of this project.
The SOW includes but is not limited to the following:
Alarms no more required shall be deleted and Alarms related to modifications are
to be included in the SCS.
Protection:
1x220kV existing spare D30 bay to be connected to Doha Super Substation is with
Protection Relays/Equipments under GTC/371/2010 Phase-10 Project.
The Relay provided at Naeeja Super for Main-1 Protection is Siemens make
7SD522 and for Main-2 Protection is ABB make RED670. The new
Relays/Equipment to be installed at Doha Super substation should match the
protection at 220kV Naeeja Super Substation end (supplied under Phase-10
project).
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.
Minor modification of the existing Bus bar protection, including conducting Bus bar
stability and addition of modules if required, shall be provided under this Contract.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 43 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Direct inter-trip for Breaker failure, Gas pressure low and Bus bar protection
operation are to be made available between the Stations based on requirement.
3.1.5
Establish 220kV, 4000A at 40C, 50kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Three (3) Nos. outgoing Transformer bays for 220/132kV Transformers suitable
for cable connection as per the approved connection arrangement;
- Four (4) Nos. cable feeder bays (two (2) Nos. spare);
- Space for four future bays, two on each side of the switchgear;
Power Transformers
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 44 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with the existing
equipment and with remote ends (in line with remote end protection scope) shall be
provided for the new feeders. However, the following specific requirements shall be
considered:
Contractor is responsible to lay control cables (as necessary) and fibre Optic
Cables from existing OTP installed in telecom room up to new 220kV control room
to complete the necessary connection and end-to-end test of protection for the said
links (New control room in Al Waab Super to Mehairja Super).
One existing 132kV cable spare bay shall be converted to 132kV Auto transformer
LV bay as detailed in Main Scope of the Work. Contractor has to do proper CT
sizing calculation and check the adequacy of existing CTs. Existing Cable bay
protection panel shall be modified with provision of new 132kV transformer LV
protection based on Phase 13 specifications. Existing Cable differential relays, Trip
relays, TCS relays TBs, etc. shall be dismantled and returned to Kahramaa store
according to the standard procedure.
Existing 220/132kV Auto Transformer protection panels (D11 & D21) are provided
with one low impedance (7UT613) and one high impedance (DADN) differential
protection, also, no tertiary winding earth fault protection is provided. New
protection relays based on Phase 13 specifications (including two low impedance
differential protections from different manufacturers and REF protection) shall be
provided for existing 220/132kV Auto Transformer protection. The tertiary winding
shall be protected separately against earth faults (1ph O/C relay-51N/50N),
additional 1ph Ring CT on the neutral connection of the delta winding shall be
provided. In addition to existing bushing neutral CT, additional ring type CT (of the
similar characteristics) shall be provided on the neutral of the Auto-transformers.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 45 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
This Ring type CT shall be used for Protection applications and Bushing NCT shall
be kept shorted. Presently, transformer mechanical protections relays are provided
in the 220kV HV panels as per old protection philosophy. However, new provision
of transformer mechanical protections High Impedance relays based on new
200/132kV, 315MVA transformer protection Phase 13 philosophy shall be
contractors responsibility. Existing HV side panels shall be converted to LV side
protection panels and exact details shall be decided during detail engineering.
Existing Cable Differential relays provided 220kV HV panels and any other relays
shall be dismantled and returned to Kahramaa store according to the standard
procedure.
Contractor shall ensure that the new relays provided in 220kV Transformer HV
Bays protection panels and those installed in 132kV LV bays protection panels are
complete so as to achieve a complete functional protection for the existing and new
Auto Transformers. Testing and commissioning of the three 200/132kV Auto
Transformers shall be done in order to provide complete protection.
Existing AVR equipments shall be used which are connected to 220kV side. It is
not be required to shift to new 220kV Control room; however, it shall be decided
during detailed engineering. Existing AVR equipment shall be tested and its proper
functioning shall be ensured by the Contractor. Third AVR of new 200/132kV,
315MVA Auto transformer may not be required to be integrated with two existing
AVRs. However, all other features which are not dependent on existing AVR
schemes shall be incorporated in accordance to specification requirement.
Modification of the existing 132kV bus bar protection, including conducting bus bar
stability and addition of modules required shall be the responsibility of the
Contractor.
Direct inter-trip for breaker failure, Pole discrepancy and Bus bar protection
operation are to be made available between the stations based on requirement.
All modification, testing and commissioning, relay setting calculation, relay testing
on final setting, Transformer differential and REF stability etc. and putting in service
is included in the scope.
Alarms no more required shall be deleted and those related to modifications are to
be included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.
GPS upgrade shall be carried out to accommodate CMS Time Synchronization for
SCS, CMS, Telecom, etc. The existing GPS shall be handed over to KM.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 46 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
For new common alarms Contractor will use additional BCUs to maintain 20%
spare availability.
LV Power Cables, Control Cables with all accessories for the new equipment as well
as for the connections to the existing equipment/systems. Sizing and Voltage drop
calculation shall be strictly carried out for the cables to be proposed from existing LV
services to the new building.
Earthing & Lightning Protection including connection to the existing system;
Small Power & Lighting
LV Service Equipment and Works comprising of:
The new LVAC Sub Distribution Board, for the new 220kV GIS building, 220/132kV
transformer and HVAC units, connected to the existing LVAC switchboard. Spare
feeders are available in the existing LVAC Board. Modifications, if any, required for
the above connections shall also be carried out.
The existing LVAC switchboard shall be extended to enable connection of the new
LVAC Sub Distribution Board.
The new LVDC Board, Battery and battery charger for the 220kV GIS & associated
protection systems accommodated in the new building and for the new 220/132kV
transformer.
New UPS to cater the additional load requirements in the new building.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 47 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Security management system shall cover both existing and new substation building
and open areas. If due to bidders design there are more than one control rooms,
the bidder shall be bound to provide additional SMS material, if required, for both
control rooms.
Laying, termination and testing of copper cables to extend Telephones from old to
new building.
Laying, termination and testing of two FO single mode cables (2 * 48F) from old to
new building including OTBs in new building.
Civil works:
All civil works related to new 220kV GIS, the new 220/132kV transformer including
building services and modifications of the existing building basement to enable
cable routing.
New 220kV GIS building shall have space for 220kV GIS, 220kV Relay Panels
and LV AC/DC Sub Distribution Boards and Battery room.
220kV and 132kV Cable troughs for laying cables between new GIS/Transformers
to existing transformers/GIS including duct banks and cross over arrangement with
existing cable corridors.
LV cable troughs/duct banks for routing LV power & control cables, FO cables of
SCADA/ Telecom etc. between new and existing buildings.
Deluge Water Spray System for Power Transformer including related civil works
such as trenches (@ road crossing for deluge pipes as & where required).
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 48 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Tie-in works for connection with the existing deluge system / fire mains / fire
pumping station
Fire Detection & Alarm System for the Transformer, GIS building, other areas and
tie-in (connection/interfacing with existing fire detection & alarm system).
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all new cables (EHV, HV, MV &
LV including cable trays) for the entire length of the cable.
Passive fire protection system Fire Sealant material for all the MEP openings
including HVAC & Fire/Smoke damper openings, floor openings such as panel
openings including future openings, cable openings (spare/future) & all other cable
openings such as substation cables, 11kV outgoing feeders and all cables inside
the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises.
Required modification works with the existing system (tie-in) for Fire Detection and
Alarm System, testing & commissioning, battery calculations, replacement of
batteries (as per calculations, if required) etc in the existing Fire Detection & Alarm
System (which must be verified during commissioning) are included in the present
scope of works.
EPC Contractor must engage the services of the vendor or specialist Fire
contractor involved in PH7 Contract during the tie-in works with the existing Fire
Detection & Alarm System. Commissioning works must be carried out only by the
authorized vendor or Fire contractor who has installed the existing system.
Existing Fire Protection & Fire Detection & Alarm System drawings shall be
updated.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 49 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
220kV, 1x1600mm2, XLPE, 315MVA, double circuit, single point earthed with
earth continuity conductor cable link between 220kV GIS and the existing
220/132kV Transformers, laid in unfilled concrete troughs with all accessories.
Approx. route length: 150m.
220kV, 1x1600mm2, XLPE, 315MVA, single circuit, single point earthed with
earth continuity conductor cable link between 220kV GIS and the new 220/132kV
Transformer, laid in unfilled concrete troughs with all accessories. Approx. route
length: 150m.
132kV, 1x2000mm2, XLPE, 315MVA, single circuit, single point earthed with
earth continuity conductor, one (1) cable per phase cable link between 220/132kV
Transformer and 132kV GIS, laid in unfilled concrete troughs with all accessories.
Approx. route length: 125m.
Milestone A
Complete 220kV GIS, 220/132kV Transformer with corresponding cable
connections, convert one 220kV Incoming Cable from the existing 220/132kV
transformers into new 220kV GIS and the corresponding remote end works at
Mehairja Super.
Milestone B
Convert the remaining 220kV Incoming Cable from the existing 220/132kV
transformers into new 220kV GIS and connect the existing 220/132kV transformers
on to new 220kV GIS. Remaining remote end works at Mehairja Super.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 50 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Minor Modifications to SCS of ABB make supplied under Phase 11 project by M/s
L&T to include changes to 2x220kV Cable feeders in the SCS including Gateway
Data mapping to NCC/ENCC and S/S works necessary for NCC/ENCC End to
End testing.
Alarms no more required shall be deleted and Alarms related to modifications are
to be included in the SCS.
Protection:
2x220kV existing bays to be connected to Al Waab Super Substation are with Protection
Relays/Equipments under Phase-11 Project.
The relay provided at Mehairja Super for Main-1 protection is ABB make RED670
and for Main-2 Protection is Siemens make 7SD52. The new Relays/Equipment to
be installed at Al Waab Super substation should match the protection at 220kV
Mehairja Super Substation end (supplied under Phase-11 project).
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.
Minor modification of the existing Bus bar protection, including conducting Bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for Breaker failure, Gas pressure low and Bus bar protection operation
are to be made available between the Stations based on requirement.
3.1.6
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 51 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
double circuit 220kV cable lines and with Abu Hamour North by double circuit 220kV cable
lines. In addition to the existing connections, Abu Hamour Super S/S will be connected to
DSS by 1x220kV cable circuit. The cables will be installed under separate Contract
(GTC/736/2015, Package C2).
The scope of works shall be as follows:
Existing 220kV GIS D31 bay and 66kV GIS B38 bay shall be used for connecting
the additional Transformer.
Existing 220kV GIS D50 bay shall be used for connecting the new 220kV feeder
from DSS.
One (1) no. 66kV, 200MVA SF6 Gas Insulated bus duct between 220/66kV Power
Transformers & 66kV GIS including testing and commissioning.
The Relay provided at Abu Hamour Super substation for Main-1 Protection is
Siemens make 7SD522 and Main-2 Protection is ABB make RED670 relays. The
contractor shall ensure that the same Relays/Equipment installed at Abu Hamour
Super substation shall match the protection at 220kV DSS Substation end. At both
ends, existing relays shall be used. Retesting of the Relays/Equipment, all
modifications, End to End test, testing and commissioning and putting into service
of these two circuits is included in the Present Scope.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 52 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
All modification on the existing 220kV spare Transformer bay (D31 & B38)
protection as per standard specification, Protection SLD and Technical Schedules,
testing and commissioning, relay setting calculation, relay testing on final setting,
Transformer differential and REF stability test and putting in service are included in
the present Scope.
Contractor shall ensure all the required modifications including provision of any
trip/auxiliary relays, cabling/wiring to achieve Interlocks and Intertrips between
220kV HV side and 66kV LV switchgears and protection. Provision of additional
transformer mechanical protections relays based on new 200/66kV, 200MVA
transformer shall be contractors responsibility. Contractor shall ensure that the
existing relays provided in 220kV Transformer HV Bays protection panels and
those installed in existing relays 66kV LV bay protection panels are complete so
as to achieve a complete functional protection for the Transformers. Testing and
commissioning of the new 200/66kV Transformers shall be done in order to
provide complete protection.
Modification of the existing 220kV and 66kV bus bar protection, including
conducting bus bar stability and addition of modules required shall be the
responsibility of the Contractor.
Direct inter-trip for breaker failure, Pole discrepancy and Bus bar protection
operation are to be made available between the stations based on requirement.
All modification, testing and commissioning, relay setting calculation, relay testing
on final setting, Transformer differential and REF stability etc. and putting in
service is included in the scope.
Alarms no more required shall be deleted and those related to modifications are to
be included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 53 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
LV Service Equipment - Spare feeder outlets available in the existing LVAC board,
LVDC Board and UPS are to be utilized for the new equipment. If required additional
MCCB/MCBs are to be provided in the vacant blocks,
LV Power Cables, Control Cables with all accessories for the new equipment as
well as for the connections to the existing equipment/systems.
Earthing & Lightning Protection shall be extended.
Small Power & Lighting
Fire Fighting System
Deluge Water Spray System for Power Transformer including related civil works
such as trenches (@ road crossing for deluge pipes as & where required).
Tie-in works for connection with the existing deluge system / fire mains / fire
pumping station
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes all new
cables.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas related to the
installation of the new transformer.
Required modification works with the existing system (tie-in) for Fire Detection and
Alarm System, testing & commissioning, battery calculations, replacement of
batteries (as per calculations, if required) etc in the existing Fire Detection & Alarm
System (which must be verified during commissioning) are included in the present
scope of works.
EPC Contractor must engage the services of the vendor or specialist Fire
contractor involved in PH10 Contract during the tie-in works with the existing Fire
and
tie-in
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 54 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Detection & Alarm System. Commissioning works must be carried out only by the
authorized vendor or Fire contractor who has installed the existing system.
Introduction of loop card (if requires), interface modules & provision of required
number of relays in the existing Fire Alarm Control Panel for transmitting signals to
SCS.
Existing Fire Protection & Fire Detection & Alarm System drawings shall be
updated.
Civil Works
All required civil Works for the installation of the new Transformer.
Power cables
220kV, 1x1200mm2, XLPE, 200MVA, single circuit, single point earthed with
earth continuity conductor cable link between 220kV GIS and 220/66kV
Transformer, laid in unfilled concrete troughs with all accessories. Approx. route
length: 50m.
66kV, 1x2000mm2, XLPE, 200MVA, single circuit, single point earthed with earth
continuity conductor, two (2) cables per phase cable link between 220/66kV
Transformers and 66kV GIS, laid in unfilled concrete troughs with all accessories.
Approx. route length: 100m (alternative to 66kV GI bus duct in case of layout
difficulty).
Re-testing and Re-commissioning of one number of the existing GIS D10 bay,
including required modifications in the existing GIS bays along with Local Control
Panels including indicating meters in the local control Panels, inscription of
additional alarm facia as required, replacing of GIS name plates and any required
works including, wiring, testing & complete re-commissioning of the above GIS
bays.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 55 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Alarms no more required shall be deleted and those related to modifications are to
be included in the conventional control panels and S/S work necessary for remote
signaling to NCC/ENCC.
Protection
3.1.7
Relay Protection Equipment for the spare bay (D10 bay) as per standard
specification, Protection SLD and Technical Schedules.
The Relay provided at two bays connected to Al Thumamah Super at DSS are
Main-1 Protection is Siemens make 7SD522 and for Main-2 Protection is ABB
make RED670. The contractor shall ensure that the same Relays/Equipment
installed at Abu Hamour Super substation should match the protection at 220kV
DSS Substation end. Both end substations, existing shall be used.
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.
Minor modification of the existing Bus bar protection, including conducting Bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for Breaker failure, Gas pressure low and Bus bar protection
operation are to be made available between the Stations based on requirement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 56 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Relay Protection Equipment for new Bays as detailed in Main Scope of Work shall
be provided as per standard specification, Protection SLD and Technical
Schedules.
Existing Distributed ABB make Low Impedance 220kV Bus bar protection is
provided. Modification of the existing distributed 220kV bus bar protection,
including conducting bus bar stability and addition of modules required shall be the
responsibility of the Contractor. Direct inter-trip for breaker failure, Pole
discrepancy and Bus bar protection operation are to be made available between
the stations based on requirement.
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.
Direct inter-trip for breaker failure, Pole discrepancy and Bus bar protection
operation are to be made available between the stations based on requirement.
Alarms no more required shall be deleted and those related to modifications are to
be included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.
All required civil Works for the installation of the new bays.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 57 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
All required modifications, End to End test, testing and commissioning and putting into
service of one circuit shall be carried out under the scope of this project. Modification
works at Mehairja Super shall be arranged in a way not to affect the Warranty Period, if
still valid at the time of new works.
The SOW includes but is not limited to the following:
Minor Modifications to SCS of ABB make supplied under Phase 11 project by M/s
L&T to include changes to 1x220kV Cable feeder in the SCS including Gateway
Data mapping to NCC/ENCC and S/S works necessary for NCC/ENCC End to
End testing.
Alarms no more required shall be deleted and Alarms related to modifications are
to be included in the SCS.
Protection:
1x220kV existing bays to be connected to Al Wajbah Super Substation are with Protection
Relays/Equipments under Phase-11 Project.
The relay provided at Mehairja Super for Main-1 protection is ABB make RED670
and for Main-2 Protection is Siemens make 7SD52. The new Relays/Equipment to
be installed at Al Wajbah Super substation should match the protection at 220kV
Mehairja Super Substation end (supplied under Phase-11 project).
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.
Minor modification of the existing Bus bar protection, including conducting Bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for Breaker failure, Gas pressure low and Bus bar protection operation
are to be made available between the Stations based on requirement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 58 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
PACKAGE S-2
3.2
3.2.1
Establish 132kV, 3150A at 40C, 40kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus Section bays;
- Two (2) Nos. Bus coupler bays;
- Two (2) Nos. Outgoing Transformer bays for 132/66kV Transformers;
- Six (6) Nos. Cable feeder bays (four (4) Nos. spare);
- Space for four future bays, two on each side of the switchgear.
Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus Section bays;
- Two (2) Nos. Bus coupler bays;
- Two (2) Nos. incoming Transformer bays for 132/66kV Transformers suitable
for GIB connection as per the approved connection arrangement;
- Two (2) Nos. Outgoing Transformer bays for 66/11kV Transformers;
- Six (6) Nos. Cable feeder bays (two (2) spare bays);
- Two (2) nos. 66kV, 160MVA SF6 Gas Insulated bus duct between 132/66kV
Power Transformers & 66kV GIS.
- Space for four future bays, two on each side of the switchgear.
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 59 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Two (2) Nos. Power Transformers 66/11kV, 32/40MVA, Dyn1, with ONAN/ONAF
cooling, OLTC with +5% to -15% in steps of 1.25%, 13.6% impedance on ONAN
provided with AVR, terminal CTs, neutral CTs etc.
Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.5 ohm at 50C rated
for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV 32/40MVA Power Transformer.
Space for four (4) future capacitor banks along with space for four (4) vacuum
contactor panels for the future capacitor banks shall be provided for in the
substation layout.
Protection Systems
Relay Protection Equipment for all Primary Equipment (all Bays) as detailed in
Main Scope of Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
shall be provided for feeders connected to Al Sakhamah Super and Abu Thailah
substations (in line with remote end protection scope of works).
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 60 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.
For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the capacitor
bank bay.
Separate panel shall be provided for each of the 11kV incomer bays and each of
the Auxiliary Transformer bays. Separate load shedding panel shall be provided for
11kV outgoing feeders of each Switchgear, i.e., for a two Switchgear Substation (A
& B) there shall be two load shedding panels.
Note: OHL between new TC near Umm Ebairiya and Abu Thailah is equipped with
one OPGW (24fibres).
monitoring
system
for
132/66kV,
96/120/160MVA
- 132kV and 66kV GIS shall be equipped with the internal UHF couplers so the
retrofitting can be easily done in the future (sensor location shall be done as per
Specification for PDM)
- 40MVA Transformers shall have all provisions as mentioned in the TMS
specification so the retrofitting can be easily done in the future. Some are listed
as below:
Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 61 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
- Integrated HMI workstation for monitoring system including software for each
online condition monitoring system installed in S/S as well as for their remote
access;
- Necessary LAN & WAN equipment including router/firewall for connection to
remote end.
LV Power Cables, Control Cables with all accessories.
Small Power & Lighting
Earthing & Lightning Protection.
LV Service Equipment with all accessories, sized for the 132/66/11kV substation
including future 11kV (B) switchgear and future 2 x 66/11kV Transformers.
Security Management System according to specification enclosed in section 3.3.15.
Civil works:
All civil works related to new 132/66/11kV substation including building services,
The substation layout shall have space for future 11kV (B) switchgear and space
for future 2 x 66/11kV Transformers.
Control & relay room building shall be sized to accommodate the requirements of
the above future equipment such as control and relay panels, LV Service
equipment etc.
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 62 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation
132kV, 1x800 mm2, XLPE, 160MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/66kV Transformers laid in unfilled concrete troughs
with all accessories. Approx. route length: 50m.
66kV, 1x2000mm2, XLPE, 160MVA, double circuit, single point earthed with
earth continuity conductor cable links between 66kV GIS and 132/66kV Power
Transformers laid in unfilled concrete troughs with all accessories. Approx. route
length: 100m (alternative to 66kV GI bus duct in case of layout difficulty).
66kV, 1x500 mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 66kV GIS and 66/11kV Transformers laid in unfilled concrete troughs with
all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 66/11kV Power
Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, two single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20 m.
11kV, 1x500mm2, XLPE, 1600kVA, double circuit, solid bonded (one cable per
phase) between 11kV switchgear and Auxiliary Transformers. Approx. route length:
50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 63 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Alarms no more required shall be deleted and Alarms related to modifications are
to be included in the SCS.
Protection:
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.
Minor modification of the existing Bus bar protection, including conducting Bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for Breaker failure, Gas pressure low and Bus bar protection
operation are to be made available between the Stations based on requirement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 64 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Protection
2x66kV existing OHL bays to be connected to Umm Ebairiya Substation are with
Protection Relays/Equipments under Phase-7 Project.
The relay provided at Abu Thailah substation for Main-1 protection is Siemens
make 7SD5 an Existing 7SD532 relay shall be upgraded and new relay shall
be installed in place of existing P543 relay at Abu Thailah substation to match
the protection provided at Umm Ebairiya Substation.
Separate Three Phase Auto recloser relays and Auto recloser scheme shall be
provided in the 2x66kV existing OHL bays.
Existing trip relays / TCS relays shall be replaced with new relays.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 65 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
3.2.2
REV. 0
Note: OHL between new TC near Umm Ebairiya and Abu Thailah is equipped
with one OPGW (24fibres).
Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this
Contract. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.
Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus Section bays;
- Two (2) Nos. Bus coupler bays;
- Two (2) Nos. Outgoing Transformer bays for 66/11kV Transformers;
- Four (4) Nos. Cable feeder bays (two (2) Nos. spare);
- Space for four future bays, two on each side of the switchgear.
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 66 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Two (2) Nos. Power Transformers 66/11kV, 32/40MVA, Dyn1, with ONAN/ONAF
cooling, OLTC with +5% to -15% in steps of 1.25%, 13.6% impedance on ONAN
provided with AVR, terminal CTs, neutral CTs etc.
Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.5 ohm at 50C rated
for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV 32/40MVA Power Transformer.
Space for two (2) future capacitor banks along with space for vacuum contactor
panels for the future capacitor banks shall be provided for in the substation layout.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
Protection Systems
Relay Protection Equipment for all Primary Equipment (all Bays) as detailed in
Main Scope of Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
shall be provided for feeders connected to Umm Ebairiya substation.
For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.
For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the capacitor
bank bay.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 67 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Separate panel shall be provided for each of the 11kV incomer bays and each of
the Auxiliary Transformer bays. Separate load shedding panel shall be provided for
11kV outgoing feeders of each Switchgear, i.e., for a two Switchgear Substation (A
& B) there shall be two load shedding panels.
Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 68 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
Fire Fighting System
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation
66kV, 1x500 mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 66kV GIS and 66/11kV Transformers laid in unfilled concrete troughs with
all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 66/11kV Power
Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, two single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20 m.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 69 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) between 11kV switchgear and Auxiliary Transformers. Approx. route length:
50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
3.2.3
Establish 132kV, 3150A at 40C, 40kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Two (2) Nos. Shunt Reactor bays suitable for Double bus bar system with
single pole Circuit breakers
Note: Controlled switching device to be included and CB shall be capable for
reactor switching
- Alternatively, Two numbers of 132kV GIS Bay for Shunt Reactor without
Switching Device
Note: Contractor shall make study and confirm suitability of the proposed GIS
Bay without controlled switching device. This alternative item will be applicable
subject to such confirmation
- Two (2) Nos. outgoing Transformer bays for 132/11kV Transformers;
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 70 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
- Six (6) Nos. Cable feeder bays (two (2) Nos. spare);
- Space for four future bays, two on each side of the switchgear;
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 132/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.
Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.5 ohm at 50C
rated for 750A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 32/40MVA Power Transformer.
Two (2) Nos. 132kV, 15MVAr Shunt Reactors with terminal CTs, neutral CTs etc.
Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.
Protection:
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 71 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
(in line with remote end protection scope of works) shall be provided for feeders
connected to Al Sakhamah Super and Semaismah substations. The new relays to
be installed at 132/11kV Umm Garn substation shall match the protection at Al
Sakhamah Super and Semaismah substation ends.
For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.
For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.
Separate panel shall be provided for each of the 11kV incomer bays and each of
the Auxiliary Transformer bays. Separate load shedding panel shall be provided
for 11kV outgoing feeders of each Switchgear, i.e., for a two Switchgear
Substation (A & B) there shall be two load shedding panels.
Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 72 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
- Integrated HMI workstation for monitoring system including software for each
online condition monitoring system installed in S/S as well as for their remote
access;
- Necessary LAN & WAN equipment including router/firewall for connection to
remote end.
LV Power Cables, Control Cables with all accessories
Small Power & Lighting
Earthing & Lightning Protection
LV Service Equipment with all accessories.
Security Management System according to specification enclosed in section 3.3.15.
Civil works:
All civil works related to new 132/11kV substation including building services,
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 73 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Note: The architectural appearance of the Substation buildings and boundary wall shall
aesthetically match with the structures in the surrounding area and is subject to
approval of concerned authorities. All design approvals in this regard shall be
coordinated with the concerned authorities.
132kV GIS & Fire Pump room Cranes
Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
Fire Fighting System
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation
132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 74 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
132kV, 1x500mm2, XLPE, 15MVA, double circuit, solid bonded cable links
between 132kV GIS and 132kV Shunt Reactors laid in unfilled concrete troughs
with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 75 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Protection
2x132kV existing bays to be connected to Umm Garn substation are with Protection
Relays/Equipments under GTC/240B/2008 Phase-9 project.
The relay provided at Semaismah for Main-1 protection is Siemens make 7SD5
and for Main-2 Protection is ABB make RED670. The new Relays/Equipment to be
installed at Umm Garn substation should match the protection at 132kV
Semaismah Substation end (supplied under Phase-9 project).
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.
Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 76 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Alarms no more required shall be deleted and Alarms related to modifications are
to be included in the SCS.
Protection:
3.2.4
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope. The new Relays/Equipment to be installed at Umm Garn
substation should match the protection at 132kV Al Sakhamah Super Substation
end (supplied under Phase-12 project).
Minor modification of the existing Bus bar protection, including conducting Bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for Breaker failure, Gas pressure low and Bus bar protection
operation are to be made available between the Stations based on requirement.
Modification of the existing 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz,
double bus bar GIS to connect the new transformers on the existing bays:
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 77 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
- Convert the existing 2 x 66kV OHL feeder (B30 and B40) bay into the outgoing
Transformer bay for 66/11kV Transformer suitable for connection as per the
approved connection arrangement;
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
11kV Switchgear A:
- Existing switchgear shall be named Switchgear A;
11kV Switchgear B:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 66/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.
Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.
Space for four (4) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
Protection:
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 78 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in Main Scope
of the Work shall be provided as per standard specification, Protection SLD and Technical
Schedules. However, the following specific requirements shall be considered:
Two existing cable spare bays (B30 and B40 bays) shall be converted to 66kV
transformer bays as per above SOW. The Contractor shall provide complete
66/11kV transformer, HV side protection as per Phase-13 specification. CT
adequacy shall be checked. Contractor shall ensure all the required modifications
including provision of any trip/auxiliary relays, cabling/wiring to achieve Interlocks
and Intertrips between existing 66kV HV side and new 11kV LV switchgears and
protection. Contractor shall ensure that the new relays provided in 66kV
Transformer HV Bays protection panels and those installed in new 11kV LV bay
protection panels are complete so as to achieve a complete functional protection
for the Transformers. Testing and commissioning of the new 66/11kV
Transformers shall be done in order to provide complete protection.
Contractor is responsible to lay control cables (as necessary) and fibre Optic
Cables from existing OTP installed in telecom room up to new 66kV control room
to complete the necessary connection and end-to-end test of protection for the
said links (New control room in Abu Thailah to Umm Ebairiya).
For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.
For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.
Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 79 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
For new common alarms the contractor shall use additional BCUs to maintain 20%
spare availability.
Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
LV Power Cables, Control Cables with all accessories for the new equipment as well
as for the connections to the existing equipment/systems. Sizing and Voltage drop
calculation shall be strictly carried out for the cables to be provided from existing LV
services to the new building;
Small Power & Lighting
Earthing & Lightning Protection for new equipment and integration with existing
earthing system.
LV Service Equipment and Works for the newly installed equipment
The new LVAC Sub Distribution Board, for the new switchgear building, 66/11kV
transformers and HVAC units and will be connected to the existing LVAC
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 80 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
The new LVDC Board, Battery and battery charger for the 11kV switchgear &
associated protection systems accommodated in the new building and for the new
transformers
New UPS to cater the additional load requirements in the new building.
Security management system shall cover both existing and new substation building
and open areas. If due to bidders design there are more than one control rooms,
the bidder shall be bound to provide additional SMS material, if required, for both
control rooms.
Laying, termination and testing of copper cables to extend Telephones from old to
new building.
Laying, termination and testing of two FO single mode cables (2 * 48F) from old to
new building including OTBs in new building.
Civil works
All civil works related to new building for 11kV switchgear B & relay panels and
66/11kV transformers including building services,
Air-conditioning and ventilation systems to cover new 11kV switchgear and Control
& Relay buildings.
Fire Fighting System
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
including related civil works such as trenches (@ road crossing for deluge pipes
as & where required).
Tie-in works for connection with the existing deluge system / fire mains / fire
pumping station
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 81 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Fire Detection & Alarm System for the Transformer, SWGR Room and tie-in
(connection/interfacing with existing fire detection & alarm system)
Passive fire protection system Cable Coating for all new cables (EHV, HV, MV &
LV including cable trays) for the entire length of the cable.
Passive fire protection system Fire Sealant material for all the MEP openings
including HVAC & Fire/Smoke damper openings, floor openings such as panel
openings including future openings, cable openings (spare/future) & all other cable
openings such as substation cables, 11kV outgoing feeders and all cables inside
the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises.
Required modification works with the existing system (tie-in) for Fire Detection and
Alarm System, testing & commissioning, battery calculations, replacement of
batteries (as per calculations, if required) etc. in the existing Fire Detection &
Alarm System (which must be verified during commissioning) are included in the
present scope of works.
EPC Contractor must engage the services of the vendor or specialist Fire
contractor involved in PH7 Contract during the tie-in works with the existing Fire
Detection & Alarm System. Commissioning works must be carried out only by the
authorized vendor or Fire contractor who has installed the existing system.
Introduction of loop card (if requires), interface modules & provision of required
number of relays in the existing Fire Alarm Control Panel for transmitting signals to
SCS. In case of there is no space in the existing FACP to introduce loop card for
serving new SWGR & Transformer areas Fire alarm system, existing FACP shall
be upgraded or replaced with new FACP.
Existing Fire Protection & Fire Detection & Alarm System drawings shall be
updated. Deluge Water Spray System for Power Transformers & Auxiliary
Transformers
66kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 82 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
11kV, 1x630mm2, XLPE, two single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
66 KV OH/Line Double Circuit OH/Line Abu Thailah S/S / Umm Salal S/S
diversion to Umm Ebairiya S/S
This is an existing 66kV double circuit Overhead Transmission Line on Steel Lattice
towers with single Conductors per phase type ZEBRA and one earthwire type OPGW
(24 fibres) with an approximate total length of 13km and total number of 42 towers (to
be operated on 66kV level).
The Contractor shall install a cable compound near existing tower no. 10 close to new
Umm Eberia S/S in order to enable connection of the subject 66kV OHL and Umm
Eberia substation. The works shall include (but not be limited to) design, supply,
installation and commission of:
OHL jumpers between OHL gantries and cable sealing ends & lighting
arresters,
All necessary OHL conductor branches and OHL conductor connectors and
links,
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 83 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Dismantling of the complete 66kV OHL portion between Umm Salal S/S and
Umm Eberia S/S (10 OHL towers, two single gantries, conductors, OPGW,
insulators and cable compound in front Umm Salal S/S, completely together
with foundations to 2m depth under the ground).
Include installation of OPGW hood closure at new cable compound near Umm
Eberia S/S, OPGW suspension and tension fittings sets. After completion of
OPGW diversion work, the Contractor shall perform End to End testing of the
complete optical link.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 84 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Cable Compound Palisade Fence complete with gate, foundations, earthing, kerb
stone etc.,
OHL jumpers between OHL gantries and cable sealing ends & lighting arresters,
All necessary OHL conductor branches and OHL conductor connectors and links,
All related civil works (foundation, grading, levelling, backfilling, gravelling, etc.),
Dismantling of the complete 66kV OHL portion between Umm Salal S/S and Umm
Al Amad S/S (27 OHL towers, two single gantries, conductors, OPGW, insulators
and cable compound in front Umm Salal S/S, completely together with foundations
to 2m depth under the ground).
Replacement of existing earthwire (1x Steel 7/12) with new OPGW (48 fibres) on the
OHL portion between Umm Al Amad S/S and Umm Al Ghahab S/S, installation of
OPGW splice and hood closures, OPGW suspension and tension fittings sets, etc.
After completion of OPGW diversion work, the Contractor shall perform End to End
testing of the complete optical link.
The handling of the dismantled materials shall be in accordance with the
Environmental requirements and any benefit (e.g. payment for scrap material) shall be
to the Contractors account. Accordingly, the Bidder shall provide the price (Disposed
Material for OHL of Price schedules) which will be compensated to Kahramaa, i.e.
deducted from the corresponding item in Price schedule.
The Contractor shall submit detailed method statement for the above works, with
clearly indicated outage schedule, which shall be subject of final Kahramaa apprval.
All required modifications at Umm Al Amad S/S, Umm Al Ghahab S/S, LCC, SCS, etc.
shall be covered under this SOW Item.
Laying of new Cables
Lying of the new 66kV double circuit from TC to Um Ebariya S/S shall be done under
this project.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 85 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
In addition, laying of the new 66kV double circuit from TC to Umm Al Amad Super S/S
shall be done under this project.
Contractor should make all necessary arrangements to connect cable circuits at
Terminal Compounds near Umm Ebariya & Umm Al Amad Super substations.
2 x 66kV, Cable Sealing Ends suitable for terminating above UG Cables and 66kV
OHL feeders from Abu Thailah substation.
2 x 66kV, Cable Sealing Ends suitable for terminating above UG Cables and 66kV
OHL feeders from Umm Al Ghahab substation.
All required co-ordination with Telecom contractor as per the responsibility matrix
included in this scope of work.
Milestone A
Complete Substation extension, complete one new 66kV cable Um Ebariya to TC
and one new 66kV cable Umm al Amad Super to TC and the remote end works at
Umm al Amad Super, Umm AL Ghalab and Umm Salal S/Ss.
Milestone B
Complete the second new 66kV cable Um Ebariya to TC and second new 66kV
cable Umm al Amad Super to TC and the corresponding remote end works.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 86 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
become spare. All modifications to convert these existing OHL bays into spare bays shall
be carried out under the scope of this project.
The SOW includes but is not limited to the following:
Required modifications in the existing GIS bays into spare bays along with Local
Control Panels including indicating meters in the local control Panels, inscription of
additional alarm facia as required, replacing of GIS name plates and any required
works.
Protection
Four 4x66kV existing bays to be disconnected from Abu Thailah and Umm Al Ghahab
S/Ss are with Protection Relays/Equipments under Phase-6 project.
All modifications to change the OHL bays into spare are included in the Present
Scope.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 87 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.
Protection
Two 2x66kV existing bays to be connected to Umm Al Amad Super substation are with
Protection Relays/Equipments under Phase-10 project.
The relay provided at Umm Al Ghalab for Main-1 protection is Siemens make
7SD52 and for Main-2 Protection is ABB make RED670. The relay provided at
UAA Super substation for Main-1 protection is Alstom make P545 and for Main-2
Protection is make 7SD5 relays. The new Relays/Equipment (mainly, Main-2RED670 relay) to be installed and Main-1 as 7SD53 relay at Umm Al Amad
substation should match the protection at 66kV Umm Al Ghahab Substation end
(supplied under Phase-10 project).
The existing main relays provided at Umm Al Ghalab are not connected to any
fibre Optic/ OPGW and hence, new provision of fibre optic patch cords is included
in present scope.
Note: OHL between new TC near Umm Al Ghahab and Umm Al Ghahab shall be
equipped with one OPGW (48fibres).
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.
Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 88 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Al Ghahab into 66kV GIS at Umm Al Amad Super S/S. Construction of the new Terminal
Compound (TC), dismantling of the existing OHL from TC to Umm Salal S/S shall be done
under this project along with the laying of the new 66kV double circuit from TC to Umm Al
Amad Super S/S.
All modifications, End to End test, testing and commissioning and putting into service of
the two circuits required shall be carried out under the scope of this project.
The SOW includes but is not limited to the following:
Re-testing and Re-commissioning of two numbers of the existing GIS bays for new
OHL connection, including required modifications in the existing GIS bays along
with Local Control Panels including indicating meters in the local control Panels,
inscription of additional alarm facia as required, replacing of GIS name plates and
any required works including, wiring, testing & complete re-commissioning of the
above GIS bays.
Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.
Protection
Two 2x66kV existing bays to be connected to Umm Al Ghalab substation are with
Protection Relays/Equipments under GTC/144A/2006 Phase-8 project.
The relay provided at Umm Al Ghalab for Main-1 protection is Siemens make
7SD52 and for Main-2 Protection is ABB make RED670. The relay provided at
UAA Super substation for Main-1 protection is Alstom make P545 and for Main-2
Protection is make 7SD5 relays for UGC cable protection. All the modifications at
UAA Super substation shall be carried out to have OHL protection with new Auto
recloser relay and associated Autocloser scheme. The new Relays/Equipment
(mainly, Main-2-RED670 relay) to be installed and Main-1 as 7SD53 relay at Umm
Al Amad substation should match the protection at 66kV Umm Al Ghahab
Substation end (supplied under Phase-10 project).
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.
Note: OHL between new TC near Umm Al Ghahab and Umm Al Ghahab shall be
equipped with one OPGW (48fibres).
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 89 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 90 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
PACKAGE S-3
3.3
3.3.1
LILO of the cable circuits Bani Hajer Super Al Jahhaniya 1 and Al Jahhaniya 1
Barzan Camp 1 into Jahhaniya 2 are the scope of this project, while LILO of the cable
circuit Bani Hajer Super Barzan Camp 1 into Jahhaniya 2 shall be done through
separate cable contract (GTC-736/2015 Package C5).
The principal elements of new 132/11kV Al Jahhaniya 2 substation shall be as follows:
Gas Insulated/ Air Insulated Switchgear
Establish 132kV, 3150A at 40C, 40kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Two (2) Nos. outgoing Transformer bays for 132/11kV Transformers;
- Eight (8) Nos. Cable feeder bays (two (2) Nos. spare);
- Space for four future bays, two on each side of the switchgear;
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 132/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 91 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.5 ohm at 50C
rated for 750A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 32/40MVA Power Transformer.
Space for two (2) future capacitor banks and space for two (2) vacuum contactor
panels for the future capacitor banks shall be provided for in the substation layout.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation, load for two future 132/11kV Transformers, load for future
11kV switchgear B with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.
Protection:
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
(in line with remote end protection scope of works) shall be provided for feeders
connected to Bani Hajer Super, Barzan Camp 1 and Al Jahhaniya 1 substations.
The new relays to be installed at 132/11kV Al Jahhaniya 2 substation shall match
the protection at Bani Hajer Super, Barzan Camp 1 and Al Jahhaniya 1 substation
end.
For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.
For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.
Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 92 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
All civil works related to new 132/11kV substation including building services,
The substation layout shall have space for future 11kV switchgear-B and space
for future 2 x 132/11kV, 32/40MVA Transformers.
Control & relay room building shall be sized to accommodate the requirements of
the above future equipment such as control and relay panels, LV Service
equipment etc.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 93 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
Fire Fighting System
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises
132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 94 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
The substation Contractor should make all necessary arrangements to connect cable
circuits at Al Jahhaniya 2 substation. The Contractor shall be responsible to maintain
rating of the existing circuits after diversion. Refer to attached drawing no. TRANS-52015.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 95 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
All labels related to Power and fiber optic cables (within existing substations and
along cable route) shall be replaced based on new connection scheme after
diversion.
Milestone A
Complete Al Jahhaniya 2 substation, diversion of 1x132kV cable circuit between Al
Jahhaniya 1 S/S and Barzan Camp 1 S/S into Al Jahhaniya 2 and related remote
end works at Jahhaniya 1 S/S and Barzan Camp 1 S/S substations.
Milestone B
Diversion of 1x132kV cable circuit between Bani Hajer Super S/S and Al Jahhaniya
1 into Al Jahhaniya 2 and related remote end works at Bani Hajer Super S/S and Al
Jahhaniya 1 substations.
Milestone C
Remote end works at Bani Hajer Super S/S and Barzan Camp-1 substations
related to diversion of 1x132kV cable circuit between Bani Hajer Super S/S and
Barzan Camp-1 into Al Jahhaniya-2 by cable contractor
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 96 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
mapping to NCC/ENCC and S/S works necessary for NCC/ENCC End to End
testing.
Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.
Protection
Two 2x132kV existing bays to be connected to Al Jahhaniya 2 substation are with
Protection Relays/Equipments under GTC/144A/2006 Phase-8 project.
The relay provided at Bani Hajer Super for Main-1 protection is Alstom make P545
and for Main-2 Protection is Siemens make 7SD5. The new Relays/Equipment to
be installed at Al Jahhaniya 2 substation should match the protection at 132kV
Bani Hajer Super Substation end.
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.
Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 97 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.
Protection
Two 2x132kV existing bays to be connected to Al Jahhaniya 2 substation are with
Protection Relays/Equipments under GTC/371A/2006 Phase-10 project.
The relay provided at Barzan Camp 1 feeder connected to Bani Hajer Super for
Main-1 protection is Alstom make P545 and for Main-2 Siemens make 7SD5
relays.
The relay provided at Barzan Camp 1 feeder connected to Al Jahhaniya 1 for Main1 protection is Alstom make P545 and for Main-2 Protection Siemens make
7SD52.
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.
Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 98 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.
Protection
Two 2x132kV existing bays to be connected to Al Jahhaniya 2 substation are with
Protection Relays/Equipments under GTC/488C/2012 Phase-11 project.
3.3.2
The relay provided at Al Jahhaniya 1 feeder connected to Barzan Camp 1 for Main1 protection is Alstom make P545 and for Main-2 Siemens make 7SD5.
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.
Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
PAGE 99 OF 473
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Doha North Super S/S substation. The double circuit cable lines will be installed under
separate Contract (GTC/736/2015, Package C5).
The principal elements of new 132/11kV Izghawa North substation shall be as follows:
Gas Insulated/ Air Insulated Switchgear
Establish 132kV, 3150A at 40C, 40kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Four (4) Nos. outgoing Transformer bays for 132/11kV Transformers;
- Six (6) Nos. Cable feeder bays (four (4) Nos. spare);
- Space for four future bays, two on each side of the switchgear;
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
11kV Switchgear A:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 132/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
11kV Switchgear B:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 132/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Four (4) Nos. of 11kV Metallic Neutral Earthing Resistors 8.5 ohm at 50C
rated for 750A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 32/40MVA Power Transformer.
Space for four (4) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.
Protection:
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules.
For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.
For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.
Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
- 132kV GIS shall be equipped with the internal UHF couplers so the retrofitting
can be easily done in the future (sensor location shall be done as per
Specification for PDM);
- 40MVA Transformers shall have all provisions as mentioned in the TMS
specification so the retrofitting can be easily done in the future. Some are listed
as below:
Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation
132kV, 1x500mm2, XLPE, 40MVA, quadruple circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, quadruple circuit, single point earthed with
earth continuity conductor, four (4) cables per phase cable links between
132/11kV Power Transformers and 11kV switchgear, laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
11kV, 1x630mm2, XLPE, four single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
Existing BCUs in 2 x 132kV bays utilized for connection towards Izghawa North
substation shall be replaced with new BCUs. New BCUs shall be integrated with
the existing SCS. All wiring modifications in the relay panel, testing and
commissioning to make new BCU fully operational shall be Contractors
responsibility.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.
Protection
Two 2x132kV existing spare bays to be connected to Izghawa North substation are with
Protection Relays/Equipments under Phase-4 project.
3.3.3
For those 132kV Cable feeders connected to Izghawa North S/S, complete
functional protection system as per standard specification shall be provided. The
new relays/equipment shall be installed at Doha North substation to match the
(new) protection at Izghawa North substation end.
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.
Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.
QASCO S/S,
MPCL,
MIB S/S and
QVC & QAPCO S/S.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Establish 132kV, 3150A at 40C, 40kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Two (2) Nos. Shunt Reactor bays suitable for Double bus bar system with
single pole Circuit breakers
Note: Controlled switching device to be included and CB shall be capable for
reactor switching
- Alternatively, Two numbers of 132kV GIS Bay for Shunt Reactor without
Switching Device
Note: Contractor shall make study and confirm suitability of the proposed GIS
Bay without controlled switching device. This alternative item will be applicable
subject to such confirmation
- Two (2) Nos. outgoing Transformer bays for 132/33kV Transformers;
- Two (2) Nos. outgoing Transformer bays for 132/11kV Transformers;
- Twelve (12) Nos. Cable feeder bays (four (4) Nos. spare);
- Space for four future bays, two on each side of the switchgear;
Establish 33kV, 2500A at 40C, 31.5kA / 1 sec, double bus bar GIS, consisting
of the following:
- Two (2) Nos. Bus section bay rated 2500A;
- Two (2) Nos. Bus coupler bay rated 2500A;
- Two (2) Nos. Incomers for 132/33kV Transformers rated 2500A;
- Ten (10) Nos. Outgoing feeder bays rated 1250A (four (4) Nos. spare);
- Space for four future bays, two on each side of the 33kV switchgear.
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 132/11kV Transformers rated 2500A;
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Two (2) Nos. of 33kV Metallic Neutral Earthing Resistors 25.40 ohm @ 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/33kV 100MVA Power transformer.
Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.5 ohm at 50C
rated for 750A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 32/40MVA Power Transformer.
Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1600kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.
Protection:
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
SLD and Technical Schedules. Relay and equipment compatible with remote end
(in line with remote end protection scope of works) shall be provided for:
- 132kV feeders connected to QASCO extension, MESAC (MPCL), MIB and
QAPCO substations.
- 33kV feeders connected to NGL and Container Terminal Berth substations
Metering system: Tariff meters shall be provided on the 3 Nos. 132kV Cable
feeder bays connected to bulk consumer (QASCO extension and QAPCO
substation) and 3 Nos. 33kV Outgoing feeder bays connected to bulk consumer
(NGL substation). Standard specification for the bulk consumers shall apply.
Guidelines for Protection Energy Meter and System Control Requirements for
Power Supply to Bulk Consumers are included in the technical specification in
Volume 2 (along with the Scope of Works) as Annexures IV & V (ET-P26-G1,
issue 4 14/5/2014 & ES-EST-P1-G1, issue 0 10/3/2014). Tariff meters shall be
interfaced with SCS using communication protocol, preferable IEC61850, to
enable signal transfer from tariff metering system to NCC.
For 33kV outgoing feeders Numerical relay with fibre optic interphase (for Fibre
optic cable) and Numerical relay with fibre optic to pilot converter (for Pilot wire
cable) shall be provided which shall be decided during detail design. Other
protection and schemes as applicable in specification shall be provided.
For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.
For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.
Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
- Integrated HMI workstation for monitoring system including software for each
online condition monitoring system installed in S/S as well as for their remote
access;
- Integrated HMI shall include the existing TMS installed on the existing
transformers;
LV Power Cables, Control Cables with all accessories
Small Power & Lighting
Earthing & Lightning Protection
LV Service Equipment with all accessories.
Security Management System according to specification enclosed in section 3.3.15.
All civil works related to new 132/33/11kV substation including building services,
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Deluge Water Spray System for Power Transformers, Shunt Reactors & Auxiliary
Transformers
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Shunt Reactors, Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
links between new 132/33kV transformers and new 33kV GIS switchgear laid in
unfilled concrete troughs with all accessories Approx. route length : 50m
33kV, 1x500 mm2, XLPE, two singlecable links between 33kV NER and
132/33kV, 100 MVA Power Transformers. Approx. route length: 20 m.
132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bondedcable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
132kV, 1x500mm2, XLPE, 15MVA, double circuit, solid bondedcable links
between 132kV GIS and 132kV 15MVAr Shunt Reactor laid in unfilled concrete
troughs with all accessories. Approx. route length: 150m.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary Transformers.
Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
Diversion of the existing 132kV, 1x1000mm2, XLPE, 174MVA, double circuits,
from the existing 132kV GIS into new 132kV GIS, connected to MPCL S/S, laid in
unfilled concrete troughs with all accessories, including one FO cable per circuit.
Approx. route length: 150m. Existing cables are laid under separate project 2006
by M/s LC Cable.
Dismantling of the existing 132kV, 1x1600mm2, oil filled, 160MVA, double
circuits, from the existing 132kV GIS into new 132kV GIS, connected to QASCO
S/S, laid in unfilled concrete troughs with all accessories (with a necessary
transition joint), including single core Pilot Wire cable. Approx. route length: 200m.
Existing cables are laid under separate project.
Decommissioning (dismantling of termination) and draining of oil of the remaining
portion of cable is also a part of the Contractors Scope of Works as well as the
laying and termination of control cables from the oil pressure monitoring system to
the new MIA S/S control room.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Diversion of the existing 132kV, 3Cx350mm2, oil filled, 71MVA, single circuit,
from the existing 132kV GIS into new 132kV GIS, connected to QAPCO S/S, laid in
unfilled concrete troughs with all accessories (with a necessary transition joint),
including single core Pilot Wire cable. Approx. route length: 150m. Existing cables
are laid under separate project.
Necessary modification of oil pressure feeding system for the existing cable shall
be done according to the oil profile details of the existing cables. Design and
arrangement shall be submitted for approval (oil tank, alarm panel, oil pressure
gauge manometer, oil pipe feeding, all test required for oil filled cable and concrete
manhole for oil tank). Technical specification of the existing 3-core oil filled cable
circuits will be provided after award of works.
The correct phasing identification (R-Y-B) shall be done after cable is opened,
isolated and earthed for spiking. All required works for laying of new XLPE cable
shall include cutting and capping of redundant section of cable to prevent draining
of oil to the ground. The exact location of cutting cable or diversion points and
details design shall be responsibility of the Contractor and shall be covered by
Contract prices.
Decommissioning (dismantling of termination) and draining of oil of the remaining
portion of cable is also a part of the Contractors Scope of Works as well as the
laying and termination of control cables from the oil pressure monitoring system to
the new MIA S/S control room.
Diversion of the existing 132kV, 3Cx350mm2, oil filled, 71MVA, single circuit,
from the existing 132kV GIS into new 132kV GIS, connected to QVC S/S, laid in
unfilled concrete troughs with all accessories (with a necessary transition joint),
including single core Pilot Wire cable. Approx. route length: 150m. Existing cables
are laid under separate project.
Necessary modification of oil pressure feeding system for the existing cable shall
be done according to the oil profile details of the existing cables. Design and
arrangement shall be submitted for approval (oil tank, alarm panel, oil pressure
gauge manometer, oil pipe feeding, all test required for oil filled cable and concrete
manhole for oil tank). Technical specification of the existing 3-core oil filled cable
circuits will be provided after award of works.
The correct phasing identification (R-Y-B) shall be done after cable is opened,
isolated and earthed for spiking. All required works for laying of new XLPE cable
shall include cutting and capping of redundant section of cable to prevent draining
of oil to the ground. The exact location of cutting cable or diversion points and
details design shall be responsibility of the Contractor and shall be covered by
Contract prices.
Decommissioning (dismantling of termination) and draining of oil of the remaining
portion of cable is also a part of the Contractors Scope of Works as well as the
laying and termination of control cables from the oil pressure monitoring system to
the new MIA S/S control room.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Milestone A
Complete Substation, divert one cable from MIB from the existing 132kV GIS to the
new 132kV GIS, divert one cable from MPCL from the existing 132kV GIS to the
new 132kV GIS and the remote end works at MIB and MPCL.
Milestone B
Divert the other cables to the new 132kV GIS and the corresponding remote end
works.
Re-testing and Re-commissioning of one number of the existing GIS bay, including
required modifications in the existing GIS bays along with Local Control Panels
including indicating meters in the local control Panels, inscription of additional
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
alarm facia as required, replacing of GIS name plates and any required works
including, wiring, testing & complete re-commissioning of the above GIS bays.
Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.
Protection
1x132kV existing cable transformer bays to be connected to Mesaieed Industrial-A
substation is with Protection Relays/Equipments as per the earlier Kahramaa projects.
For the 132kV Cable transformer feeder connected to Mesaieed Industrial-A S/S,
complete functional protection system as per standard specification shall be
provided.
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.
Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.
Protection
Two 2x132kV existing bays to be connected to Mesaieed Industrial-A substation are with
Protection Relays/Equipments under separate project.
For those 132kV Cable feeders connected to MPCL S/S, complete functional
protection system as per standard specification shall be provided. The bays are
fully equipped with protection relays/equipment.
The relay provided at MESAC (MPCL) substation for Main-1 protection is Siemens
make 7SD5 and for Main-2 Protection is ABB make RED670 relays. The new
Relays/Equipment to be installed at Mesaieed Industrial-A substation should match
the protection at MESAC (MPCL) Substation end (supplied under Phase-9 project).
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.
Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
QAPCO & QVC will remain connected to Mesaieed Industrial-A by 132kV, Double Circuit,
Oil filled cables QAPCO Mesaieed Industrial A and QVC- MIA, associated with pilot wire.
All modifications, End to End test, testing and commissioning and putting into service of
two circuits required shall be carried out under the scope of this project.
For 2x132kV Cable transformer feeder bay connected at bulk consumer QAPCO, all the
requirements as per Kahramaa standard specification for the bulk consumers shall apply.
Contractor is required to obtain all the necessary permissions to work inside the bulk
consumer premises.
The SOW includes but is not limited to the following:
Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.
Protection
Two 2x132kV existing bays to be connected to Mesaieed Industrial-A substation is with
Protection Relays/Equipments as per earlier Kahramaa specification.
For the 132kV Cable transformer feeders connected to Mesaieed Industrial-A S/S,
complete functional protection system as per standard specification shall be
provided, for cable with pliot wire and associated protection.
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.
Existing BCUs in 3 x 132kV bays utilized for connection towards MIA substation
shall be replaced with new BCUs. New BCUs shall be integrated with the existing
SCS. All wiring modifications in the relay panel, testing and commissioning to make
new BCU fully operational shall be Contractors responsibility.
Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS and TMMC/TDB/RTU.
Protection
Three 3x132kV existing bays to be connected to Mesaieed Industrial-A substation is with
Protection Relays/Equipments as per earlier Kahramaa specifications.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
MIB MIA 132kV Cable Circuit#1 and Circuit#2, the bays are fully equipped with
one main protection relays/equipments supplied under Phase-4 project. The new
relays/equipment shall be installed at MIB substation to match the (new) protection
at MIA substation end.
MIB MIA 132kV Cable Circuit#3, the bays are fully equipped with protection
relays/equipments supplied under Phase-7 project. The relay provided at MIB
substation for Main-1 protection is Siemens make 7SD5 and for Main-2 Protection
is ABB make RED670 relays. The 87C relays are to be replaced to get Dual FO
port communication wherever applicable as per latest Kahramaa specifications.
Existing trip relays / TCS relays need to be replaced. The new Relays/Equipment
to be installed at Mesaieed Industrial-A substation should match the protection
upgraded at MIB Substation end, circuit-3 (supplied under Phase-7 project).
Existing trip relays / TCS relays need to be replaced in all three MIB MIA 132kV
Cable feeders.
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.
Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
plates and any required works including, wiring, testing & complete recommissioning of the above switchgear bays.
Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.
Protection
Three 3x33kV existing bays to be connected to Mesaieed Industrial-A substation is with
Protection Relays/Equipments as per the earlier Kahramaa specification.
For the 33kV Cable feeder connected to Mesaieed Industrial-A S/S, complete
functional protection system as per standard specification shall be provided for
cable with pliot wire and associated protection. For 33kV outgoing feeders
Numerical relay with fibre optic to pilot converter (for Pilot wire cable) shall be
provided which shall be decided during detail design. Other protection and
schemes as applicable in specification shall be provided.
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.
Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Contractor is required to obtain all the necessary permissions to work inside the bulk
consumer premises
The SOW includes but is not limited to the following:
Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.
Protection
Two 2x33kV existing bays to be connected to Mesaieed Industrial-A substation is with
Protection Relays/Equipments as per the earlier Kahramaa specification.
For the 33kV Cable feeder connected to Mesaieed Industrial-A S/S, complete
functional protection system as per standard specification shall be provided.
The relay provided at CTB7 substation for Main protection is ABB make RED670
relay and Back O/C ABB make REF615 relay. The new Relays/Equipment to be
installed at Mesaieed Industrial-A substation should match the protection at CTB7
substation end (supplied under bulk consumer project).
Tairff metering provided at Bulk consumer end CTB7 shall be remain connected as
per present arrangement.
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.
Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
3.3.4
REV. 0
Establish 132kV, 3150A at 40C, 40kA / 1 sec, 3-phase, 50Hz, single bus bar
GIS consisting of following bays:
- One (1) No. Bus section bays;
- Two (2) Nos. outgoing Transformer bays for 132/11kV Transformers;
- Four (4) Nos. Cable feeder bays (two (2) Nos. spare);
- Space for four future bays, two on each side of the switchgear;
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 132/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.
Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.5 ohm at 50C
rated for 750A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 32/40MVA Power Transformer.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.
Protection:
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
(in line with remote end protection scope of works) shall be provided for feeders
connected to RAF South and 132kV FACILITY D (QEZ-3) substations. The new
relays to be installed at 132/11kV Wakrah 3 substation shall match the protection
at RAF South and 132kV FACILITY D (QEZ-3) substation end.
For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.
For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.
Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises
132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Facility D 132kV GIS (QEZ-3) will be connected by 132kV single circuit cables to Wakrah
3 and Wakrah North substations. The cables will be installed under separate contract
(GTC/736/2015, Package-C5).
All required modifications, End to End test, testing and commissioning and putting into
service of two circuits shall be carried out under the scope of this project. Modification
works at 132kV FACILITY D (QEZ-3) shall be arranged in a way not to affect the Warranty
Period.
The SOW includes but is not limited to the following:
Alarms no more required shall be deleted and Alarms related to modifications are
to be included in the SCS.
Protection:
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these circuits is included in the Present
Scope. The new Relays/Equipment to be installed at Wakrah 3 and Wakrah North
substations should match the protection at 132kV FACILITY D (QEZ-3) Substation
end (supplied under IWPP project).
Minor modification of the existing Bus bar protection, including conducting Bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for Breaker failure, Gas pressure low and Bus bar protection
operation are to be made available between the Stations based on requirement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Alarms no more required shall be deleted and Alarms related to modifications are
to be included in the SCS.
Protection:
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of this circuit is included in the Present
Scope. The new Relays/Equipment to be installed at Wakrah 3 substation should
match the protection at 132kV RAF South Substation end (supplied under Phase12 project).
Minor modification of the existing Bus bar protection, including conducting Bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for Breaker failure, Gas pressure low and Bus bar protection
operation are to be made available between the Stations based on requirement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
132/11kV Wakrah North is a new Substation, being constructed under Phase 12 Project.
Wakrah North shall be connected to 132kV FACILITY D by single circuit 132kV Cable
Line.
All required modifications, End to End test, testing and commissioning and putting into
service of one circuit shall be carried out under the scope of this project. Modification
works at Wakrah North shall be arranged in a way not to affect the Warranty Period.
The SOW includes but is not limited to the following:
Alarms no more required shall be deleted and Alarms related to modifications are
to be included in the SCS.
Protection:
If there is mismatch between the Main Relays provided at Wakrah North substation
under Phase-12 project, to the relays already provided in 132kV FACILITY D
(QEZ-3) Substation, Swapping or changing with new relays at Wakrah North
substation is included in the Present Scope.
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of this circuit is included in the Present
Scope.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Minor modification of the existing Bus bar protection, including conducting Bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for Breaker failure, Gas pressure low and Bus bar protection
operation are to be made available between the Stations based on requirement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
PACKAGE S-4
3.4
3.4.1
Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Two (2) Nos. outgoing Transformer bays for 66/11kV Transformers;
- Six (6) Nos. Cable feeder bays (four (4) Nos. spare);
- Space for four future bays, two on each side of the switchgear;
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 66/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.
Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Space for two (2) future capacitor banks and space for two (2) vacuum contactor
panels for the future capacitor banks shall be provided for in the substation layout.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation, with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.
Protection:
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
(in line with remote end protection scope of works) shall be provided for feeders
connected to Ali Bin Abu Talib substation.
For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.
For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.
Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
All civil works related to new 66/11kV substation including building services,
Note: The architectural appearance of the Substation buildings and boundary wall
shall aesthetically match with the structures in the surrounding area and is subject
to approval of concerned authorities. All design approvals in this regard shall be
coordinated with the concerned authorities.
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation
66kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, two single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
The substation Contractor should make all necessary arrangements to connect cable
circuits at New Assiri substation. The Contractor shall be responsible to maintain rating
of the existing circuits after diversion.
Diversion of the existing 66kV, 1x240mm2, XLPE, 25MVA, double circuit, from
the existing 66/11kV Transformer into new 66kV GIS, connected to Ali Bin Abu
Talib S/S, laid in unfilled concrete troughs with all accessories. Approx. route
length: 500m.
All labels related to Power and fiber optic cables (within existing substations and
along cable route) shall be replaced based on new connection scheme after
diversion.
Milestone A
Complete Substation, divert the existing 66kV cable from Ali Bin Abu Talib S/S into
new 66kV GIS and the remote end works at Ali Bin Abu Talib S/Ss.
Milestone B
Divert the second cable from Ali Bin Abu Talib S/S into the new 66kV GIS and the
corresponding remote end works.
Existing BCUs in 66kV bays may not have necessary spare BI/BO to connect new
signals as per latest specification requirements. Hence Contractor shall install
additional BCU or other suitable device to transfer all the required signals to
SCS/NCC as per specification, including new VT connection and additional spare
BI/BO.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.
Protection
Two 2x66kV existing bays to be connected to New Assiri substation are with Protection
Relays/Equipments under Phase-5 project.
3.4.2
VTs are not available in 66kV GIS bays. New GIS 66kV VT shall be provided at Ali
Bin Abu Talib substation. The Contractor shall be fully responsible for all
associated works, Synchro. Functionality and extension of Local Sync. Scheme,
interlocks and required interfaces.
For those 66kV Cable feeders connected to New Assiri substation, complete
functional protection system as per standard specification shall be provided.
Existing main relay and trip relays / TCS relays need to be replaced with new one.
The new Relays/Equipment to be installed at Ali Bin Abu Talib substation should
match the new protection at New Assiri substation.
Existing Trip relays / TCS relays need to be replaced with new one.
All the required modifications in existing bays with provision of additional auxiliary
relays, BCU panels wiring etc. to meet the the new VT provisions and Phase-13
protection requirement shall be responsibility of contractor.
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.
Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, single bus bar
GIS consisting of following bays:
- One (1) No. Bus section bays;
- Two (2) Nos. outgoing Transformer bays for 66/11kV Transformers;
- Four (4) Nos. Cable feeder bays (two (2) Nos. spare);
- Space for four future bays, two on each side of the switchgear;
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 66/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.
Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.
Space for two (2) future capacitor banks and space for two (2) vacuum contactor
panels for the future capacitor banks shall be provided for in the substation layout.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation, with additional capacity of 30%. The capacity of the
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
(in line with remote end protection scope of works) shall be provided for feeders
connected to Ali Bin Abu Talib substation.
For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.
For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.
Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.
Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
All civil works related to new 66/11kV substation including building services,
Note: The architectural appearance of the Substation buildings and boundary wall
shall aesthetically match with the structures in the surrounding area and is subject
to approval of concerned authorities. All design approvals in this regard shall be
coordinated with the concerned authorities.
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises
66kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, two single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
Diversion of the existing 66kV, 1x240mm2, XLPE, 25MVA, double circuit, from
the existing 66/11kV Transformer into new 66kV GIS, connected to Ali Bin Abu
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Talib S/S, laid in unfilled concrete troughs with all accessories. Approx. route
length: 600m.
All labels related to Power and fiber optic cables (within existing substations and
along cable route) shall be replaced based on new connection scheme after
diversion.
Milestone A
Complete Substation, divert the existing 66kV cable from Ali Bin Abu Talib S/S into
new 66kV GIS and the remote end works at Ali Bin Abu Talib S/Ss.
Milestone B
Divert the second cable from Ali Bin Abu Talib S/S into the new 66kV GIS and the
corresponding remote end works.
Existing BCUs in 66kV bays may not have necessary spare BI/BO to connect new
signals as per latest specification requirements. Hence Contractor shall install
additional BCU or other suitable device to transfer all the required signals to
SCS/NCC as per specification, including new VT connection and additional spare
BI/BO.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
mapping to NCC/ENCC and S/S works necessary for NCC/ENCC End to End
testing.
Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.
Protection
Two 2x66kV existing bays to be connected to Salwa Road substation are with Protection
Relays/Equipments under Phase-5 project.
3.4.3
For those 66kV Cable feeders connected to Salwa Road substation, complete
functional protection system as per standard specification shall be provided. The
new Relays/Equipment to be installed at Ali Bin Abu Talib substation should match
the new protection at New Assiri substation.
VTs are not available in 66kV GIS bays. New GIS 66kV VT shall be provided at Ali
Bin Abu Talib substation. The Contractor shall be fully responsible for all
associated works, Synchro. Functionality and extension of Local Sync. Scheme,
interlocks and required interfaces.
Existing Trip relays / TCS relays need to be replaced with new one.
All the required modifications in existing bays with provision of additional auxiliary
relays, BCU panels wiring etc. to meet the new VT provisions and Phase-13
protection requirement shall be responsibility of contractor.
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.
Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Two (2) Nos. outgoing Transformer bays for 66/11kV Transformers;
- Six (6) Nos. Cable feeder bays (two (2) spare);
- Space for four future bays, two on each side of the switchgear;
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 66/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.
Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.
Space for four (4) future capacitor banks and space for four (4) vacuum
contactor panels for the future capacitor banks shall be provided for in the
substation layout.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation, load for two future 66/11kV Transformers & for future 11kV
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. All the necessary coordination with Al Sadd Super
Contractor for the compatibility of the relay and equipment (in line with remote end
protection scope of works) shall be provided for feeders connected to Al Sadd
Super substation. The new relays to be installed at 66/11kV Bin Mahmoud North
substation shall match the protection at Al Sadd Super substation end.
For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.
For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.
Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.
Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
All civil works related to new 66/11kV substation including building services,
The substation layout shall have space for future 11kV (B) switchgear and space
for future 2 x 66/11kV Transformers.
Control & relay room building shall be sized to accommodate the requirements of
the above future equipment such as control and relay panels, LV Service
equipment etc.
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation
66kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, two single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
All labels related to Power and fiber optic cables (within existing substations and
along cable route) shall be replaced based on new connection scheme after
diversion.
Milestone A
Complete Substation, LILO of the one existing 66kV cable circuit Al Sadd Super
and Musherib into Bin Mahmoud North S/S and the remote end works at Al Sadd
Super S/Ss.
Milestone B
LILO of the second existing 66kV cable circuit Al Sadd Super and Musherib into
Bin Mahmoud North S/S and the corresponding remote end works.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Alarms no more required shall be deleted and Alarms related to modifications are
to be included in the SCS.
Protection:
3.4.4
2x66kV existing bays to be connected to Bin Mahmoud North are with Protection
Relays/Equipments under separate Project.
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope. The new Relays/Equipment to be installed at Bin Mahmoud North
substation should match the protection at 66kV AL-SADD SUPER Substation end
(supplied under separate contract).
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.
Minor modification of the existing Bus bar protection, including conducting Bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for Breaker failure, Gas pressure low and Bus bar protection
operation are to be made available between the Stations based on requirement.
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 66/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.
Space for two (2) future capacitor banks and space for two (2) vacuum contactor
panels for the future capacitor banks shall be provided for in the substation layout.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation, with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.
Protection:
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. All the necessary coordination with Al Sadd Super
Contractor for the compatibility of the relay and equipment (in line with remote end
protection scope of works) shall be provided for feeders connected to Al Sadd
Super substation. The new relays to be installed at 66/11kV Musherib substation
shall match the protection at Al Sadd Super substation end.
For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.
For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.
Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.
SCS & Associated Equipment
Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
Fire hydrant and ring main piping (all around the substation buildings perimeter).
Fire Detection & Alarm System for the Switchgear buildings, Transformer Yards
(Power & Auxiliary), Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, two single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
All labels related to Power and fiber optic cables (within existing substations and
along cable route) shall be replaced based on new connection scheme after
diversion.
Dismantling/Demolition Works:
De-commissioning and dismantling of the existing 66/11kV Transformers, 11kV
Switchgears and all associated equipment, existing palisade fence etc. and handover
all the dismantled materials to Kahramaa stores or approved location. The existing
buildings and unused structures shall be demolished and all the debris, waste material,
garbage etc. shall be removed from the substation site and shifted to Municipality
designated/ approved location.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
PACKAGE S5
3.5
3.5.1
The principal elements of new 66/11kV Murrah South substation shall be as follows:
Gas Insulated/ Air Insulated Switchgear
Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Four (4) Nos. outgoing Transformer bays for 66/11kV Transformers;
- Eight (8) Nos. Cable feeder bays (four (4) spare);
- Space for four future bays, two on each side of the switchgear;
Establish two 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal
enclosed switchgear with vacuum circuit breakers, consisting of the following:
Switchgear A:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 66/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Switchgear B:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 66/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Four (4) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.
Space for four (4) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation, with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.
Protection:
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
(in line with remote end protection scope of works) shall be provided for feeders
connected to DIB and DIS substations. The new relays to be installed at 66/11kV
Murrah South substation shall match the protection at DIB and DIS substation end.
For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.
For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.
Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation
66kV, 1x500mm2, XLPE, 40MVA, quadruple circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, quadruple circuit, single point earthed with
earth continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, four single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
Re-testing and Re-commissioning of two numbers of the existing GIS (B30 and
B40) bays, including required modifications in the existing GIS bays along with
Local Control Panels including indicating meters in the local control Panels,
inscription of additional alarm facia as required, replacing of GIS name plates and
any required works including, wiring, testing & complete re-commissioning of the
above GIS bays.
Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.
Protection
Two 2x66kV existing spare (B30 and B40) bays to be connected to Murrah South
substation are with Protection Relays/Equipments under GTC/488D/2006 Phase-11
project.
The relay provided at Doha Industrial B for Main-1 protection is Siemens make
7SD5 and for Main-2 Protection is Alstom make P545. The new Relays/Equipment
to be installed at Murrah South substation should match the protection at 66kV
Doha Industrial B Substation end (supplied under Phase-11 project).
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.
Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.
Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.
Protection
Two 2x66kV existing bays to be connected to Murrah South substation are with Protection
Relays/Equipments under GTC/488D/2006 Phase-11 project.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
3.5.2
REV. 0
The relay provided at Doha Industrial Super for Main-1 protection is Alstom make
P545 and for Main-2 Protection is Siemens make 7SD5. The new
Relays/Equipment to be installed at Murrah South substation should match the
protection at 66kV Doha Industrial Super Substation end (supplied under Phase-11
project).
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.
Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.
Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Two (2) Nos. outgoing Transformer bays for 66/11kV Transformers;
- Six (6) Nos. Cable feeder bays (two (2) spare);
- Space for four future bays, two on each side of the switchgear;
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 66/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.
Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation, with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.
Protection:
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
(in line with remote end protection scope of works) shall be provided for feeders
connected to Ain Khalid North and Vegetable Market substation. The new relays to
be installed at 66/11kV Umm Al Seneem 2 substation shall match the protection at
Ain Khalid North and Vegetable Market substation end.
For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.
For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.
Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.
SCS & Associated Equipment
Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation
66kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, two single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
Diversion (Loop in / Loop out) of existing double circuit 66kV, 1x500mm2, XLPE,
40MVA underground cable line with fiber optic cable (24 Fibers) between
Vegetable Market and Ain Khalid North S/S into Umm Al Seneem 2 S/S.
Approximate route length: 500m. The Contractor shall include all necessary
modification works and equipment including all link boxes and earth continuity
conductors in the earthing arrangement (cross bonding, single point bonding or
mixed bonding) in order to ensure that required current rating of diverted circuit is
maintained. Necessary details, schematic drawings etc., with accurate lengths
shall be submitted for approval during detailed engineering stage. The terminations
shall be 66kV GIS type in Umm Al Seneem 2 S/S and cable joints at diversion
point. Refer to attached drawing no. TRANS-102-2014.
All labels related to Power and fiber optic cables (within existing substations and
along cable route) shall be replaced based on new connection scheme after
diversion.
Milestone A
Complete Substation, LILO of the one existing 66kV cable line Vegetable Market
and Ain Khalid North into Umm Al Seneem 2 S/S and the remote end works at
Vegetable Market and Ain Khalid North S/Ss.
Milestone B
LILO of the second existing 66kV cable line Vegetable Market and Ain Khalid North
into Umm Al Seneem 2 S/S and the remote end works at Vegetable Market and
Ain Khalid North S/Ss.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
66/11kV Ain Khalid North is an existing substation built under Phase 10 project by M/s
Hyosung. Ain Khalid North will be connected to Umm Al Seneem 2 by diversion (LILO) of
the existing 2x66kV cables between Ain Khalid North & Vegetable Market substations. All
modifications, End to End test, testing and commissioning and putting into service of these
two circuits shall be carried out under the scope of this project. Modification works at Ain
Khalid North shall be arranged in a way not to affect the Warranty Period, if still valid at the
time of new works.
The SOW includes but is not limited to the following:
Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.
Protection
Two 2x66kV existing bays to be connected to Umm Al Seneem 2 substation are with
Protection Relays/Equipments under Phase-10 project.
The relay provided at Ain Khalid North for Main-1 protection is Siemens make
7SD52 and for Main-2 Protection is ABB make RED670. The new
Relays/Equipment to be installed at Umm Al Seneem 2 substation should match
the protection at 66kV Ain Khalid North Substation end (supplied under Phase-10
project).
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.
Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Existing BCUs in 66kV bays may not have necessary spare BI/BO to connect new
signals as per latest specification requirements. Hence Contractor shall install
additional BCU or other suitable device to transfer all the required signals to
SCS/NCC as per specification, including new VT connection and additional spare
BI/BO.
Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.
Protection
Two 2x66kV existing bays to be connected to Umm Al Seneem 2 substation are with
Protection Relays/Equipments upgraded under Phase-10 project.
The relay provided at Vegetable Market Main-1 protection is Siemens make 7SD52
and for Main-2 Protection is ABB make RED670. The new Relays/Equipment to be
installed at Umm Al Seneem 2 substation should match the protection at 66kV
Vegetable Market Substation end (supplied under Phase-10 project).
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
3.5.3
REV. 0
Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.
Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Four (4) Nos. outgoing Transformer bays for 66/11kV Transformers;
- Six (6) Nos. Cable feeder bays;
- Space for four future bays, two on each side of the switchgear;
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
11kV Switchgear A:
- Existing switchgear shall be named Switchgear A and connected to the new
66kVGIS;
- Re-testing and re-commissioning of existing transformers and associated
GIS/switchgear bays
11kV Switchgear B:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 66/11kV Transformers rated 2500A;
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.
Space for four (4) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the existing substation as well for the new equipment, with additional
capacity of 30%. The capacity of the Transformer is to be justified by calculation
note which shall be subject to approval.
Protection:
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
(in line with remote end protection scope of works) shall be provided for feeders
connected to Vegetable Market, Al Waab Super and Mehairah Super substation.
However, the following specific requirements shall be considered: Protection at Al
Waab substation for 2x66kV cable feeders to be connected to Al Waab Super
substation shall be provided to be compatible with already installed relays at Al
Waab Super substation. End to End test, Testing and commissioning and putting
into service of these two circuits shall be substation Contractor's responsibility.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
New (HV side) protection for existing 66/11kV Power Transformer shall be
provided based on Phase 13 specifications, installed in new control room. All
modification on the 66kV and 11V sides of the 66/11kV Power Transformer
protection shall be done to make it compatible with 66kV side protection.
Contractor shall ensure all the required modifications including provision of any
trip/auxiliary relays, cabling/wiring to achieve Interlocks and Intertrips between
66kV HV side (new control building) and existing 11kV LV switchgears and
protection.
Presently, existing panels (B11 & B21), provided with transformer (HV) side
protection and line differential (F87C and F87C+T) protection shall be dismantled
and returned to Kahramaa store as per standard procedure. Transformer
mechanical protections relays are provided in the 66kV HV panels as per old
protection philosophy. However, new provision of transformer mechanical
protections relays based on new 66/11kV, 40MVA transformer protection
philosophy shall be contractors responsibility. Existing HV side panels shall be
converted to LV side protection panels. Alternatively, new LV protection panels
can be provided and exact details shall be decided during detail engineering.
Contractor shall ensure that the relays provided in new 66kV Transformer HV
Bays protection panels and those installed in existing 11kV LV bay protection
panels are complete so as to achieve a complete functional protection for the
Transformers. Testing and commissioning of the 66/11kV Transformers protection.
AVR panels with AVR relays are provided for existing two number 66/11kV
Transformers, located in existing control room. Existing AVR equipment shall be
tested and its proper functioning shall be ensured by the Contractor; however, any
AVR equipment modifications, testing and commissioning for AVR scheme due to
connection to new 66kV GIS shall be Contractor's responsibility.
Contractor is responsible to lay control cables (as necessary) and fibre Optic
Cables from existing OTP installed in telecom room up to new 66kV control room
to complete the necessary connection and end-to-end test of protection for the
said links (New control room in Al Waab to Vegetable Market).
For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.
Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.
Additional new BCUs shall be installed on existing 11kV Incomers to transfer the
existing signals and controls to new SCS.
For all signals from existing s/s towards NCC/DCC, integration at gateway level
shall be shall be done to have single channel towards control centers. Currently
NCC communication is on IEC-101 whereas DCC communication is on IEC-104.
Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Security management system shall cover both existing and new substation
buildings, control rooms and open areas.
Laying, termination and testing of copper cables to extend Telephones from old to
new building.
Laying, termination and testing of two FO single mode cables (2 * 48F) from old to
new building including OTBs in new building.
Civil works
All civil works related to new 66/11kV substation and 66/11kV transformers
including building services,
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
Fire Detection & Alarm System for the 66KV GIS Building, 11kV SWGR B,
Transformer Yards (Power & Auxiliary), and all other areas.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises
Required modification works with the existing system (tie-in) for Fire Detection and
Alarm System, testing & commissioning, battery calculations, replacement of
batteries (as per calculations, if required) etc in the existing Fire Detection & Alarm
System (which must be verified during commissioning) are included in the present
scope of works.
EPC Contractor must engage the services of the vendor or specialist Fire
contractor involved in PH6 Contract during the tie-in works with the existing Fire
Detection & Alarm System. Commissioning works must be carried out only by the
authorized vendor or Fire contractor who has installed the existing system.
66kV, 1x500mm2, XLPE, 40MVA, quadruple circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, two single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
All labels related to Power and fiber optic cables (within existing substations and
along cable route) shall be replaced based on new connection scheme after
diversion.
All labels related to Power and fiber optic cables (within existing substations and
along cable route) shall be replaced based on new connection scheme after
diversion.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Milestone A
Complete Substation extension, LILO of the existing 66kV cable line Al Waab
Super and Mehairja Super into Al Waab S/S and the remote end works at Al Waab
Super and Mehairja Super S/Ss.
Milestone B
Divert one circuit Al Waab S/S - Vegetable Market S/S from the existing 66/11kV
transformer into the new 66kV GIS, connect one existing 66/11kV transformer onto
the new 66kV GIS and the corresponding remote end works at Vegetable Market
S/S.
Milestone C
Divert second circuit Al Waab S/S - Vegetable Market S/S from the existing
66/11kV transformer into the new 66kV GIS, connect second existing 66/11kV
transformer onto the new 66kV GIS and the corresponding remote end works at
Vegetable Market S/S.
Existing BCUs in 66kV bays may not have necessary spare BI/BO to connect new
signals as per latest specification requirements. Hence Contractor shall install
additional BCU or other suitable device to transfer all the required signals to
SCS/NCC as per specification, including new VT connection and additional spare
BI/BO.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
mapping to NCC/ENCC and S/S works necessary for NCC/ENCC End to End
testing.
Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.
Protection
Two 2x66kV existing bays to be connected to Al Waab substation are with Protection
Relays/Equipments under Phase-5 project.
VTs are not available in 66kV GIS bays. New GIS 66kV VT shall be provided at
Vegetable Market substation. The Contractor shall be fully responsible for all
associated works, Synchro. Functionality and extension of Local Sync. Scheme,
interlocks and required interfaces.
All the required modifications in existing bays with provision of additional auxiliary
relays, BCU panels wiring etc. to meet the new VT provisions and Phase-13
protection requirement shall be responsibility of contractor.
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.
Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
220/132/11kV Mehairja Super is a new Substation with 220kV, 132kV GIS, and 11kV
Switchgear being constructed under Phase 11 Project. Mehairja Super is connected by
double circuit 66kV Cable Lines to Al Waab Super S/S S and this cable circuits shall be
diverted (by loop-in/loop-out) to Al Waab.
All modifications, End to End test, testing and commissioning and putting into service of
the two circuits shall be carried out under the scope of this project. Modification works at
Mehairja Super shall be arranged in a way not to affect the Warranty Period, if still valid at
the time of new works.
The SOW includes but is not limited to the following:
Alarms no more required shall be deleted and Alarms related to modifications are
to be included in the SCS.
Protection:
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.
Minor modification of the existing Bus bar protection, including conducting Bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for Breaker failure, Gas pressure low and Bus bar protection
operation are to be made available between the Stations based on requirement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Alarms no more required shall be deleted and Alarms related to modifications are
to be included in the SCS.
Protection:
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.
Minor modification of the existing Bus bar protection, including conducting Bus bar
stability and addition of modules if required, shall be provided under this Contract.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Direct inter-trip for Breaker failure, Gas pressure low and Bus bar protection
operation are to be made available between the Stations based on requirement.
3.5.4
Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Two (2) Nos. outgoing Transformer bays for 66/11kV Transformers;
- Four (4) Nos. Cable feeder bays (two (2) spare);
- Space for four future bays, two on each side of the switchgear;
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 66/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.
Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation, with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.
Protection:
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
(in line with remote end protection scope of works) shall be provided for feeders
connected to Abu Hamour North and Al Soudan South substations. The new
relays to be installed at 66/11kV Al Waab 2 substation shall match the protection
at Abu Hamour North and Al Soudan South substation end.
For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.
For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.
Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
- 66kV GIS shall be equipped with the internal UHF couplers so the retrofitting
can be easily done in the future (sensor location shall be done as per
Specification for PDM);
- 40MVA Transformers shall have all provisions as mentioned in the TMS
specification so the retrofitting can be easily done in the future. Some are listed
as below:
Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
Fire hydrant and ring main piping (all around the substation buildings perimeter).
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
provision of connection points for installation of TEP System (if Kahramaa decides
to adopt this system in future).
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises
66kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, two single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Existing 66kV double circuit cable lines between Abu Hamour North and Al Soudan
South substations shall be diverted (LILO) into the Al Waab 2 substation under the
present Scope of Work:
The substation Contractor shall make all necessary arrangements to divert the cable
circuits to Al Waab 2 substation. The Contractor shall be responsible to maintain rating
of the existing circuits after diversion.
Diversion (Loop in / Loop out) of existing single circuit 66kV, 1x2000mm2, XLPE,
120MVA underground cable line with fiber optic cable (24 Fibers) between Abu
Hamour North and Al Soudan South S/S into Al Waab 2 S/S. Approximate route
length: 500m. The Contractor shall include all necessary modification works and
equipment including all link boxes and earth continuity conductors in the earthing
arrangement (cross bonding, single point bonding or mixed bonding) in order to
ensure that required current rating of diverted circuit is maintained. Necessary
details, schematic drawings etc., with accurate lengths shall be submitted for
approval during detailed engineering stage. The terminations shall be 66kV GIS
type in Al Waab 2 S/S and cable joints at diversion point. Refer to attached drawing
no. TRANS-2-2015.
All labels related to Power and fiber optic cables (within existing substations and
along cable route) shall be replaced based on new connection scheme after
diversion.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.
Protection
One 1x66kV existing bay to be connected to Al Waab 2 substation are with Protection
Relays/Equipments under Phase-11 project.
The relay provided at Abu Hamour North for Main-1 protection is Siemens make
7SD522 and for Main-2 Protection is ABB make RED670. The new
Relays/Equipment to be installed at Al Waab 2 substation should match the
protection at 66kV Abu Hamour North Substation end (supplied under Phase-11
project).
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.
Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.
Protection
1x66kV existing bays to be connected to Al Waab 2 substation are with Protection
Relays/Equipments upgraded under Phase-11 project.
The relay provided at Al Soudan South Main-1 protection is Siemens make 7SD52
and for Main-2 Protection is ABB make RED670. The new Relays/Equipment to be
installed at Al Waab 2 substation should match the protection at 66kV Al Soudan
South Substation end (supplied under Phase-11 project).
Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.
PACKAGE S6
3.6
3.6.1
Modification (Extension) of the existing 66kV, 2500A at 40C, 31.5kA / 1 sec, 3phase, 50Hz, single bus bar GIS consisting of following bays:
- Two (2) Nos. outgoing Transformer bays for 66/11kV Transformers;
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Note: expansion of the existing 66kV GIS shall be done by the Original Equipment
Manufacturer.
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
11kV Switchgear A:
- Existing switchgear shall be named Switchgear A;
11kV Switchgear B:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 66/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.
Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.
Space for four (4) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the existing substation as well for the new equipment, with additional
capacity of 30%. The capacity of the Transformer is to be justified by calculation
note which shall be subject to approval.
Protection:
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in Main Scope
of the Work shall be provided as per standard specification, Protection SLD and Technical
Schedules. However, the following specific requirements shall be considered:
Two new 66kV transformer HV bays shall be provided as detailed in Main Scope
of the Work. New protection relays based on Phase 13 specifications shall be
provided. Contractor shall ensure all the required modifications including provision
of any trip/auxiliary relays, cabling/wiring to achieve Interlocks and Intertrips
between two new 66kV transformer HV bays and new 11kV LV switchgears and
protection. Contractor shall ensure that the new relays provided in 66kV
Transformer HV Bays protection panels and those installed in new 11kV LV bay
protection panels are complete so as to achieve a complete functional protection
for the Transformers. Testing and commissioning of the new 66/11kV
Transformers shall be done in order to provide complete protection.
Contractor is responsible to lay control cables (as necessary) and fibre Optic
Cables from existing OTP installed in telecom room up to new 66kV control room
to complete the necessary connection.
For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.
For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.
Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
New furniture shall be supplied to accommodate existing and new SCS system.
For new common alarms the contractor will use additional BCUs to maintain 20%
spare availability.
Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Security management system shall cover both existing and new substation
building and open areas. If due to bidders design there are more than one control
rooms, the bidder shall be bound to provide additional SMS material, if required,
for both control rooms.
Laying, termination and testing of copper cables to extend Telephones from old to
new building.
Laying, termination and testing of two FO single mode cables (2 * 48F) from old to
new building including OTBs in new building.
Civil works
All civil works related to new 11kV substation B and 66/11kV transformers
including building services,
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
Fire Detection & Alarm System for the new 11kV switchgear building, Transformer
Yards (Power & Auxiliary) and all other areas.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises
EPC Contractor must engage the services of the vendor or specialist Fire
contractor involved in PH5 Contract during the tie-in works with the existing Fire
Detection & Alarm System (if requires). Commissioning works must be carried out
only by the authorized vendor or Fire contractor who has installed the existing
system.
Existing Fire Protection & Fire Detection & Alarm System drawings shall be
updated.
66kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, two single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
3.6.2
REV. 0
Modification of the existing 66kV, 1850A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz,
single bus bar GIS consisting of following bays:
- Re-testing and Re-commissioning of two numbers of the existing switchgear
bays(B30 & B40), including required modifications in the existing switchgear
bays along with Local Control Panels including Indicating Meters in the Local
Control Panels, inscription of additional Alarm facia as required, replacing of
Switchgear Name plates and any required works including, wiring, testing &
complete re-commissioning of the above switchgear bays
- Two (2) Nos. outgoing Transformer bays for 66/11kV Transformers;
Note: expansion of the existing 66kV GIS shall be done by the Original Equipment
Manufacturer.
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
11kV Switchgear A:
- Existing switchgear shall be named Switchgear A;
11kV Switchgear B:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 66/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.
Power Transformers, NERs
Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.
Space for two (2) future capacitor banks and space for two (2) vacuum contactor
panels for the future capacitor banks shall be provided for in the substation layout.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the existing substation as well for the new equipment, with additional
capacity of 30%. The capacity of the Transformer is to be justified by calculation
note which shall be subject to approval.
Protection:
Relay Protection Equipment for all Primary Equipment (all new bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. However, the following specific requirements shall be
considered:
2x66kV Cable connection to New Salata (S7 package):
Two 2x66kV existing (B30 and B40) bays to be connected to New Salata substation
substation are with Protection Relays/Equipments under Phase-13, (S7 package) project.
For those 66kV Cable feeders connected to New Salata substation, complete
functional protection system as per standard specification shall be provided.
Presently Main relays REL316*4 and REL551 are provided. The new
Relays/Equipment to be installed at Museum Road substation should match the
new protection at New Salata substation. Existing relays including Over current
relay shall be dismantled and returned to Kahramaa store according to the
standard procedure.
Existing Trip relays / TCS relays need to be replaced with new one.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.
Existing CTs (800/400/1 A) for B30 and B40 bays shall be replaced with new CTs
to match with new 120MVA cable rating and protection/metering requirements.
Contractor has to do proper CT sizing calculation and check the adequacy of
existing CTs.
Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.
Extension of GIS for Two (2) Nos. outgoing Transformer bays for 66/11kV
Transformers:
Two new 66kV transformer HV bays shall be provided as detailed in Main Scope
of the Work. New protection relays based on Phase 13 specifications shall be
provided. Contractor shall ensure all the required modifications including provision
of any trip/auxiliary relays, cabling/wiring to achieve Interlocks and Intertrips
between two new 66kV transformer HV bays and new 11kV LV switchgears and
protection. Contractor shall ensure that the new relays provided in 66kV
Transformer HV Bays protection panels and those installed in new 11kV LV bay
protection panels are complete so as to achieve a complete functional protection
for the Transformers. Testing and commissioning of the new 66/11kV
Transformers shall be done in order to provide complete protection.
Modifications of the existing 66kV ABB make Distributed Low Impedance Busbar
protection, including conducting bus bar stability and addition of modules, shall be
provided under this Contract.
Contractor is responsible to lay control cables (as necessary) and fibre Optic
Cables from existing OTP installed in telecom room up to new 66kV control room
to complete the necessary connection.
For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.
For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.
Existing BCUs on 66kV feeders (B30 & B40) shall be replaced with the new ones
and connected to the new SCS. New protection relays to be connected to the new
SCS.
Minor modification required in existing ABB make SCS HMI screens to show the
new 66/11kV Transformer arrangements.
New furniture shall be supplied to accommodate existing and new SCS system.
For new common alarms the contractor will use additional BCUs to maintain 20%
spare availability.
Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
LVDC battery and battery charger for the new Transformers and switchgears;
New UPS;
Security management system shall cover both existing and new substation
building and open areas. If due to bidders design there are more than one control
rooms, the bidder shall be bound to provide additional SMS material, if required,
for both control rooms.
Laying, termination and testing of copper cables to extend Telephones from old to
new building.
Laying, termination and testing of two FO single mode cables (2 * 48F) from old to
new building including OTBs in new building.
Civil works
All civil works related to new 11kV substation B and 66/11kV transformers
including building services,
Demolition of existing boundary wall (one side only, refer tender Drg.) and
construction of new boundary wall as shown in the tender drawing.
Note: The architectural appearance of the Substation buildings and boundary wall
shall aesthetically match with the structures in the surrounding area and is subject
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Establish parking spaces at grade level on the adjacent plot to the allocated
substation plot once the construction of the substation is finalized.
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
Fire Detection & Alarm System for the new 11kV switchgear building, Transformer
Yards (Power & Auxiliary) and all other areas.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises
EPC Contractor must engage the services of the vendor or specialist Fire
contractor involved in PH6 Contract during the tie-in works with the existing Fire
Detection & Alarm System (if requires). Commissioning works must be carried out
only by the authorized vendor or Fire contractor who has installed the existing
system.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
new 11kV SWGR/Control building Fire alarm system, existing FACP shall be
upgraded or replaced with new FACP (if requires).
Existing Fire Protection & Fire Detection & Alarm System drawings shall be
updated.
66kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, two single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
Diversion of the existing 66kV, 1x300mm2, XLPE, 40MVA, double circuit, from
the existing 66kV GIS at Museum Road into 66kV GIS at Old Ghanem laid in
unfilled concrete troughs with all accessories. Approx. route length: 500m.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
All labels related to Power and fiber optic cables (within existing substations and
along cable route) shall be replaced based on new connection scheme after
diversion.
The remaining existing 66kV up to Museum Road S/S shall be disconnected and
capped at both ends.
Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.
Protection
Two 2x66kV existing bays to be connected to Old Ghanem substation are with Protection
Relays/Equipments under Phase-9 project.
For those 66kV Cable feeders connected to Old Ghanem substation, complete
functional protection system as per standard specification shall be provided to
match protection system at Old Ghanem substation. Presently Main relays
REL316*4 and REL551 are provided. The new Relays/Equipment to be installed at
Muntazah North substation should match the new protection at Old Ghanem
substation (Main-1 Siemens make 7SD5 shall be used for F87C protection and
Main-2 Protection ABB make RED670 shall be F87C+T protection). Existing Main
relays including over current relay shall be dismantled and returned to Kahramaa
store according to the standard procedure.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.
Modification of the existing Partial bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.
Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.
Protection
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Two 2x66kV existing (B50 & B60) bays to be connected directly to transformer at
Muntazah North substation are with Protection Relays/Equipments under GTC/240D/2008
Phase-9 project.
The relay provided at Old Ghanem for Main-1 protection is Siemens make 7SD5
and for Main-2 Protection is ABB make RED670. The new Relays/Equipment to be
installed at Muntazah North substation should match the protection at 66kV Old
Ghanem Substation end (supplied under Phase-9 project). The Main-1 Siemens
make 7SD5 shall be used for F87C protection and Main-2 Protection ABB make
RED670 shall be F87C+T protection.
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.
Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.
Establish 132kV, 3150A at 40C, 40kA / 1 sec, 3-phase, 50Hz, single bus bar
GIS consisting of following bays:
- One (1) No. Bus section bay;
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 132/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.
Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.5 ohm at 50C
rated for 750A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 32/40MVA Power Transformer.
Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.
Protection:
GTC-735 SCOPE OF WORKS R0
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
(in line with remote end protection scope of works) shall be provided for feeders
connected to Madinat Al Kabaan substation. The new relays to be installed at
132/11kV Ain Sinan substation shall match the protection at Madinat Al Kabaan
substation end.
For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.
For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.
Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.
Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation
132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
132kV Outdoor Cable Sealing Ends suitable for the 2x132kV OHL feeder
terminations with 132kV, XLPE, 250MVA, 1x2000sqmm UG cables including
structures, foundations etc. at Ain Sinan substation Terminal Compound
(Alternative to GIB, in case layout difficulty).
132kV GIS Sealing Ends suitable for the 2x132kV feeder terminations with
132kV, XLPE, 250MVA, 2000sqmm UG cables including necessary material and
accessories and steel structure at Ain Sinan Substation (Alternative to GIB, in
case layout difficulty).
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
The proposed construction of 132kV Double Circuit OH Line with twin bundle AAAC
FLINT conductor per phase for transmission of 250MVA of power of each circuit with a
total length of approximately 14km between the existing substation Madinat Al Kabaan
S/S (132/11kV) and new Ain Sinan S/S (132/11kV) Substation. The basic OH line
characteristics shall be as follows:
Steel lattice towers and gantries (with fencing if they are located outside substation
compound) complete with structure earthing,
The scope shall also include survey approvals from MMAA, mechanical design
considering the safety of the operation and maintenance of each individual line,
supply, installation testing and commissioning.
At existing Madinat Al Kabaan S/S (132/11kV) and new Ain Sinan S/S (132/11kV), the
132kV OH Line shall be terminated to the new OHL double Gantries which shall be
located within substation fences. Terminal towers, gantries, shall be provided in order
to lead in the lines; down leads to the gantries, down droppers, conductor links and
conductor branching clamps to the Cable Compound equipment shall be provided
also. All earthworks and earthing systems related to the OHL shall be provided also
under this Contract. Refer to attached drawing No. TRANS-13-2014.
Contractor is responsible for all works related to End-to-End testing of FO links (F#1,
F#2) between Madinat Al Kabaan S/S and new Ain Sinan S/S.
The Contractor shall coordinate with GTC 735/2015 Telecom Contractor to complete
the works.
All required modifications at existing Madinat Al Kabaan S/S (132/11kV), LCC, SCS,
etc. shall be covered under this SOW Item.
REMOTE END WORKS AT MADINAT AL KABAAN S/S
132/11kV Madinat Al Kabaan is an existing substation with 132kV GIS and 11kV
Switchgear built by L&T under Phase 10 Project. Madinat Al Kabaan will be connected to
Ain Sinan by new 132kV, double circuit OHL. All modifications, End to End test, testing
and commissioning and putting into service of the two circuits shall be carried out under
the scope of this project. Modification works at Madinat Al Kabaan shall be arranged in a
way not to affect the Warranty Period, if still valid at the time of new works.
GTC-735 SCOPE OF WORKS R0
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.
Protection
Two 2x132kV existing bays to be connected to Ain Sinan substation are with Protection
Relays/Equipments under GTC/371A/2006 Phase-10 project.
3.6.4
The relay provided at Madinat Al Kabaan for Main-1 protection is Alstom make
P545 and for Main-2 Protection is Siemens make 7SD52. The new
Relays/Equipment to be installed at Ain Sinan substation should match the
protection at 132kV Madinat Al Kabaan Substation end (supplied under Phase-10
project).
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.
Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
LILO of the cable circuit Jeryan Jenaihat Super S/S Al Khissa West S/S is scope of this
project.
The principal elements of new 132/11kV Jeryan Jenaihat 1 substation shall be as follows:
Gas Insulated/ Air Insulated Switchgear
Establish 132kV, 3150A at 40C, 40kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Two (2) Nos. outgoing Transformer bays for 132/11kV Transformers;
- Four (4) Nos. Cable feeder bays (two (2) Nos. spare);
- Space for four future bays, two on each side of the switchgear;
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 132/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.
Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.5 ohm at 50C
rated for 750A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 32/40MVA Power Transformer.
Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation, with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.
Protection:
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
(in line with remote end protection scope of works) shall be provided for feeders
connected to Jeryan Jenaihat Super and Al Khissa West substations. The new
relays to be installed at 132/11kV Jeryan Jenaihat 1 substation shall match the
protection at Jeryan Jenaihat Super and Al Khissa West substation end.
For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.
For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.
Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises
132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
The substation Contractor should make all necessary arrangements to divert and
connect cable circuits at Jeryan Jenaihat 1 substation. The Contractor shall be
responsible to maintain rating of the existing circuits after diversion.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
All labels related to Power and fiber optic cables (within existing substations and
along cable route) shall be replaced based on new connection scheme after
diversion.
Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.
Protection
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
One 1x132kV existing bays to be connected to Jeryan Jenaihat 1 substation are with
Protection Relays/Equipments under GTC/240A/2008 Phase-9 project.
The relay provided at Jeryan Jenaihat Super for Main-1 protection is Siemens
make 7SD52 and for Main-2 Protection is ABB make RED670. The new
Relays/Equipment to be installed at Jeryan Jenaihat 1 substation should match the
protection at 132kV Jeryan Jenaihat Super Substation end (supplied under Phase9 project).
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.
Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.
Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Protection
One 1x132kV existing bay to be connected to Jeryan Jenaihat 1 substation are with
Protection Relays/Equipments under GTC/371/2010 Phase-10 project.
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.
Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
PACKAGE S7
3.7
3.7.1
by looping in looping out (LILO) existing 66kV single cable circuit from West Bay
Super 2 New Doha A Super into New Doha E S/S,
by diverting the existing single cable circuit from West Bay Super 2 from the
existing 66kV GIS into new 66kV GIS at New Doha E and
by diverting the existing single cable circuit from New Doha A Super from the
existing 66kV GIS into new 66kV GIS at New Doha E.
The principal elements of new 66/11kV New Doha E substation shall be as follows:
Gas Insulated/ Air Insulated Switchgear
Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Four (4) Nos. outgoing Transformer bays for 66/11kV Transformers;
- Six (6) Nos. Cable feeder bays (two (2) Nos. spare);
- Space for four future bays, two on each side of the switchgear;
Establish two 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal
enclosed switchgears with vacuum circuit breakers, consisting of the following:
11kV switchgear A:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 66/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
11kV switchgear B:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 66/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Four (4) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.
Space for four (4) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation, with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.
Protection:
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
(in line with remote end protection scope of works) shall be provided for feeders
connected to New Doha A Super and West Bay Super 2 substations. The new
relays to be installed at 66/11kV New Doha E substation shall match the protection
at New Doha A Super and West Bay Super 2 substation end.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.
For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.
Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.
All civil works related to new multi-storey building, 66/11kV substation including
building services, as per relevant specification and drawings.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
The substation building shall also be provided with the rooms for the future 11kV
Capacitor Banks, as shown in the layout drawing.
Necessary number of sleeves for all outgoing feeders shall be provided on the
substation building and boundary wall
Outgoing feeder cable routing (66kV and 11kV) inside the basement to be
proposed by the contractor to facilitate convenient installation of future cables
upon requirement.
Independent Fire Fighting System for the multi-storey car parking building shall be
provided including Fire Pumping Station, Fire Pumps & Controllers, Fire Water
Tank, Fire Alarm & Detection System, Fire Hose Reels with cabinets/all
accessories, Dry Riser System and other necessary systems in accordance with
QCDD requirements.
Smoke Control System (Means of Escape & Means of Egress - Exit Access, Exitsstaircases/elevator shafts & exit discharge shall be pressurized) as per the QCDD
requirements & relevant NFPA standards.
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation
66kV, 1x500mm2, XLPE, 40MVA, quadruple circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, quadruple circuit, single point earthed with
earth continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, four single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
LILO of the 1 x 66kV New Doha A Super and West Bay Super 2,
1 x 66kV New Doha A Super from the existing 66kV GIS and
The substation Contractor should make all necessary arrangements to connect cable
circuits at New Doha E substation. The Contractor shall be responsible to maintain
rating of the existing circuits after diversion.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
details, schematic drawings etc., with accurate lengths shall be submitted for
approval during detailed engineering stage. The terminations shall be 66kV GIS
type in New Doha E S/S and cable joints at diversion point. Refer to drawing No.
TRANS-52-2014. The circuits are under installation under Phase 11 project.
All labels related to Power and fiber optic cables (within existing substations and
along cable route) shall be replaced based on new connection scheme after
diversion.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) between 11kV switchgear and 11/0.415, 1000kVA transformers. Approx.
route length: 30m.
Supply and installation of LVAC switchboard which will be used for power supply to
car park building. The contractor shall provide necessary equipment such as
distribution boards, LV cables, etc. and complete the works as specified and
required..
Supply and installation of 415V cables between 11/0.415kV transformer and LVAC
switchboard.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Supply & Installation of other required equipment and materials such as battery
chargers, batteries and any other materials as required for the completeness of the
work as per the scheme approved by Kahramaa distribution department ).
Milestone A
Complete Substation, LILO of the existing 66kV cable line New Doha A Super and
West Bay Super 2 into New Doha E S/S and the remote end works at New Doha A
Super and West Bay Super 2 S/Ss.
Milestone B
Divert the cables from the existing 66kV GIS into the new 66kV GIS and the
corresponding remote end works.
Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.
Protection
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Two 2x66kV existing bays to be connected to New Doha E substation are with Protection
Relays/Equipments under GTC/488B/2006 Phase-11 project.
The relay provided at New Doha A Super are provided under phase 11 project.
The new Relays/Equipment to be installed at New Doha E substation should match
the protection at 66kV New Doha A Super Substation end (supplied under Phase11 project).
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.
Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.
Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Protection
Two 2x66kV existing bays to be connected to New Doha E substation are with Protection
Relays/Equipments under GTC/488B/2006 Phase-11 project.
3.7.2
The relay provided at West Bay Super 2 feeder connected to New Doha E for Main
protection relays will be replaced during phase 11 project to match protection
equipment at New Doha A Super.
The relay provided at West Bay Super 2 feeder connected to New Doha A Super
for Main-1 protection is Siemens make 7SD5 and for Main-2 Protection is ABB
make RED670.
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.
Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.
Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 66/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.
Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation, with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.
Protection:
GTC-735 SCOPE OF WORKS R0
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
(in line with remote end protection scope of works) shall be provided for feeders
connected to Khalifat substation. The new relays to be installed at 66/11kV Salata
substation shall match the protection at Khalifat substation end.
For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.
For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.
Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
All civil works related to new multi-storey building, 66/11kV substation including
building services, as per relevant specification and drawings.
The substation building shall also be provided with the rooms for the future 11kV
Capacitor Banks, as shown in the layout drawing.
Necessary number of sleeves for all outgoing feeders shall be provided on the
substation building and boundary wall
Outgoing feeder cable routing (66kV and 11kV) inside the basement to be
proposed by the contractor to facilitate convenient installation of future cables
upon requirement.
Independent Fire Fighting System for the multi-storey car parking building shall be
provided including Fire Pumping Station, Fire Pumps & Controllers, Fire Water
Tank, Fire Alarm & Detection System, Fire Hose Reels with cabinets/all
accessories, Dry Riser System and other necessary systems in accordance with
QCDD requirements.
Smoke Control System (Means of Escape & Means of Egress - Exit Access, Exitsstaircases/elevator shafts & exit discharge shall be pressurized) as per the QCDD
requirements & relevant NFPA standards.
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation
66kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, two single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
The substation Contractor should make all necessary arrangements to connect cable
circuits at new GIS at Salata substation. The Contractor shall be responsible to
maintain rating of the existing circuits after diversion.
Diversion of the existing 66kV, 1x630mm2, XLPE, 60MVA, double circuit, from
the existing 66kV GIS into new 66kV GIS, connected to Khalifat S/S, laid in unfilled
concrete troughs with all accessories and communication cables. Approx. route
length: 500m. Existing cables are diverted under phase 9 project from the GIS at
old Khalifat S/S into new GIS by M/s Siemens. Refer to attached drawing No.
TRANS-113-2014.
All labels related to Power and fiber optic cables (within existing substations and
along cable route) shall be replaced based on new connection scheme after
diversion.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) between 11kV switchgear and 11/0.415, 1000kVA transformers. Approx.
route length: 30m.
Supply and installation of LVAC switchboard which will be used for power supply to
car park building. The contractor shall provide necessary equipment such as
distribution boards, LV cables, etc. and complete the works as specified and
required.
Supply and installation of 415V cables between 11/0.415kV transformer and LVAC
switchboard.
Supply & Installation of other required equipment and materials such as battery
chargers, batteries and any other materials as required for the completeness of the
work as per the scheme approved by Kahramaa distribution department ).
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
66/11kV Khalifat is an existing substation with 66kV GIS and 11kV Switchgear built by
Siemens under Phase 9 Project. Khalifat will be connected to Salata substation by
diverting the existing 2x66kV, Khalifat Salata cable circuits into new 66kV GIS. All
required modifications, End to End test, testing and commissioning and putting into
service of the two circuits shall be carried out under the scope of this project.
The SOW includes but is not limited to the following:
Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.
Protection
Two 2x66kV existing bays to be connected to Salata substation are with Protection
Relays/Equipments under GTC/240D/2008 Phase-9 project.
The relay provided at Khalifat for Main-1 protection is Siemens make 7SD5 and for
Main-2 Protection is ABB make RED670. The new Relays/Equipment to be
installed at Salata substation should match the protection at 66kV Khalifat
Substation end (supplied under Phase-9 project).
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.
Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Museum Road is an existing 66/11kV substation which will be upgraded under Package
(S-6) in this project. The Museum Road Substation will be connected to Salata Substation
with 2x66kV Cable circuit. The cables will be installed by a cable contractor under
separate contract. The substation Contractor shall coordinate with cable contractor and
Museum Road substation Contractor for the successful completion of all necessary works
for putting these feeders into service including end to end test, overall stability, coordination with NCC, SCS modification, etc. All contractors shall mutually agree and coordinate the activities. In case of any disputes in this regard, Kahramaa decision will be
final.
2x66 feeder bays at Salata substation will be connected by 2x66kV cable circuits to
Museum Road substation. All the required works at New Museum Road substation
shall be carried out under S6 package.
All protection coordination work with S6 package contractor including testing and
commissioning, relay testing on final setting, end to end test, overall stability and
putting in service are included in the present Scope.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
PACKAGE S8
3.8
3.8.1
Establish 132kV, 3150A at 40C, 40kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Two (2) Nos. outgoing Transformer bays for 132/11kV Transformers;
- Six (6) Nos. Cable feeder bays (two (2) Nos. spare);
- Space for four future bays, two on each side of the switchgear;
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 132/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.
Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.5 ohm at 50C
rated for 750A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 32/40MVA Power Transformer.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.
Protection:
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
(in line with remote end protection scope of works) shall be provided for feeders
connected to RAF South substation. The new relays to be installed at 132/11kV
Mashaf 1 substation shall match the protection at RAF South substation end.
For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.
For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.
Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation
132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Alarms no more required shall be deleted and Alarms related to modifications are
to be included in the SCS.
Protection:
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these circuits is included in the Present
Scope. The new Relays/Equipment to be installed at Mashaf 1 substation should
match the protection at 132kV RAF South Substation end (supplied under Phase12 project).
Minor modification of the existing Bus bar protection, including conducting Bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for Breaker failure, Gas pressure low and Bus bar protection
operation are to be made available between the Stations based on requirement.
3.8.2
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
circuits from Mashaf 3 and Al Wukair 10 substations and by 132kV double cable circuits
from Mashaf 1 substation. The cable circuits will be installed under separate Contract
(GTC/736/2015, Package C7).
The principal elements of new 132/11kV Mashaf 2 substation shall be as follows:
Gas Insulated/ Air Insulated Switchgear
Establish 132kV, 3150A at 40C, 40kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Two (2) Nos. outgoing Transformer bays for 132/11kV Transformers;
- Six (6) Nos. Cable feeder bays (two (2) Nos. spare);
- Space for four future bays, two on each side of the switchgear;
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 132/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.
Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.5 ohm at 50C
rated for 750A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 32/40MVA Power Transformer.
Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.
Protection:
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules.
For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.
For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.
Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.
Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation
132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
3.8.3
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Establish 132kV, 3150A at 40C, 40kA / 1 sec, 3-phase, 50Hz, single bus bar
GIS consisting of following bays:
- One (1) No. Bus section bays;
- Two (2) Nos. outgoing Transformer bays for 132/11kV Transformers;
- Four (4) Nos. Cable feeder bays (two (2) Nos. spare);
- Space for four future bays, two on each side of the switchgear;
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 132/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.
Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.5 ohm at 50C
rated for 750A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 32/40MVA Power Transformer.
Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
load of the substation with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.
Protection:
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
(in line with remote end protection scope of works) shall be provided for feeders
connected to Bul Hemmaid substation. The new relays to be installed at 132/11kV
Mashaf 3 substation shall match the protection at Bul Hemmaid substation end.
For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.
For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.
Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.
Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation
132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Alarms no more required shall be deleted and Alarms related to modifications are
to be included in the SCS.
Protection:
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these circuits is included in the Present
Scope. The new Relays/Equipment to be installed at Mashaf 3 substation should
match the protection at 132kV Bul Hemmaid Substation end (supplied under
Phase-12 project).
Minor modification of the existing Bus bar protection, including conducting Bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for Breaker failure, Gas pressure low and Bus bar protection
operation are to be made available between the Stations based on requirement.
3.8.4
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Establish 132kV, 3150A at 40C, 40kA / 1 sec, 3-phase, 50Hz, single bus bar
GIS consisting of following bays:
- One (1) No. Bus section bays;
- Two (2) Nos. outgoing Transformer bays for 132/11kV Transformers;
- Four (4) Nos. Cable feeder bays (two (2) Nos. spare);
- Space for four future bays, two on each side of the switchgear;
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 132/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.
Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.5 ohm at 50C
rated for 750A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 32/40MVA Power Transformer.
Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Protection:
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
(in line with remote end protection scope of works) shall be provided for feeders
connected to Bul Hemmaid substations. The new relays to be installed at
132/11kV Al Wukair 10 substation shall match the protection at Bul Hemmaid
substation end.
For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.
For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.
Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.
Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation
132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Alarms no more required shall be deleted and Alarms related to modifications are
to be included in the SCS.
Protection:
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these circuits is included in the Present
Scope. The new Relays/Equipment to be installed at Al Wukair 10 substation
should match the protection at 132kV Bul Hemmaid Substation end (supplied
under Phase-12 project).
Minor modification of the existing Bus bar protection, including conducting Bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for Breaker failure, Gas pressure low and Bus bar protection
operation are to be made available between the Stations based on requirement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
PACKAGE S9
3.9
3.9.1
Establish 132kV, 3150A at 40C, 40kA / 1 sec, 3-phase, 50Hz, single bus bar
GIS consisting of following bays:
- One (1) No. Bus section bays;
- Two (2) Nos. outgoing Transformer bays for 132/11kV Transformers;
- Four (4) Nos. Cable feeder bays (two (2) Nos. spare);
- Space for four future bays, two on each side of the switchgear;
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 132/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.
Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.5 ohm at 50C
rated for 750A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 32/40MVA Power Transformer.
Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.
Protection:
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
(in line with remote end protection scope of works) shall be provided for feeders
connected to Bul Hemmaid substations. The new relays to be installed at
132/11kV Al Wukair 9 substation shall match the protection at Bul Hemmaid
substation end.
For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.
For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.
Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation
132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Alarms no more required shall be deleted and Alarms related to modifications are
to be included in the SCS.
Protection:
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these circuits is included in the Present
Scope. The new Relays/Equipment to be installed at Al Wukair 9 substation should
match the protection at 132kV Bul Hemmaid Substation end (supplied under
Phase-12 project).
Minor modification of the existing Bus bar protection, including conducting Bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for Breaker failure, Gas pressure low and Bus bar protection
operation are to be made available between the Stations based on requirement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
3.9.2
REV. 0
Establish 132kV, 3150A at 40C, 40kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Two (2) Nos. outgoing Transformer bays for 132/11kV Transformers;
- Six (6) Nos. Cable feeder bays (three (3) Nos. spare);
- Space for four future bays, two on each side of the switchgear;
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 132/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.
Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.5 ohm at 50C
rated for 750A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 32/40MVA Power Transformer.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.
Protection:
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
(in line with remote end protection scope of works) shall be provided for feeders
connected to Bul Hemmaid substation. The new relays to be installed at 132/11kV
Al Wukair 8 substation shall match the protection at Bul Hemmaid substation ends.
For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.
For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.
Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation
132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Alarms no more required shall be deleted and Alarms related to modifications are
to be included in the SCS.
Protection:
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these circuits is included in the Present
Scope. The new Relays/Equipment to be installed at Al Wukair 8 substation should
match the protection at 132kV Bul Hemmaid Substation end (supplied under
Phase-12 project).
Minor modification of the existing Bus bar protection, including conducting Bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for Breaker failure, Gas pressure low and Bus bar protection
operation are to be made available between the Stations based on requirement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
3.9.3
REV. 0
Establish 132kV, 3150A at 40C, 40kA / 1 sec, 3-phase, 50Hz, single bus bar
GIS consisting of following bays:
- One (1) No. Bus section bays;
- Two (2) Nos. outgoing Transformer bays for 132/11kV Transformers;
- Four (4) Nos. Cable feeder bays (two (2) Nos. spare);
- Space for four future bays, two on each side of the switchgear;
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 132/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.
Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.5 ohm at 50C
rated for 750A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 32/40MVA Power Transformer.
Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.
Protection:
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
(in line with remote end protection scope of works) shall be provided for feeders
connected to Bul Hemmaid substations. The new relays to be installed at
132/11kV Al Wukair 7 substation shall match the protection at Bul Hemmaid
substation end.
For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.
For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.
Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation
132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Alarms no more required shall be deleted and Alarms related to modifications are
to be included in the SCS.
Protection:
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these circuits is included in the Present
Scope. The new Relays/Equipment to be installed at Al Wukair 7 substation should
match the protection at 132kV Bul Hemmaid Substation end (supplied under
Phase-12 project).
Minor modification of the existing Bus bar protection, including conducting Bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for Breaker failure, Gas pressure low and Bus bar protection
operation are to be made available between the Stations based on requirement.
3.9.4
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
cable circuits from Al Wukair 7, Al Wukair 8 and Al Wukair 5 substations. The cable
circuits will installed under separate Contract (GTC/736/2015, Package C8 and C9).
The principal elements of new 132/11kV Al Wukair 6 substation shall be as follows:
Gas Insulated/ Air Insulated Switchgear
Establish 132kV, 3150A at 40C, 40kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Two (2) Nos. outgoing Transformer bays for 132/11kV Transformers;
- Six (6) Nos. Cable feeder bays (three (3) Nos. spare);
- Space for four future bays, two on each side of the switchgear;
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 132/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.
Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.5 ohm at 50C
rated for 750A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 32/40MVA Power Transformer.
Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.
Protection:
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules.
For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.
For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.
Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.
Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation
132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
cables will be installed under separate contract (GTC/736/2015, Package C8). The
substation contractor shall coordinate with cable contractor and complete all necessary
works for putting these feeders into service.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
PACKAGE S10
3.10
3.10.1
Establish 132kV, 3150A at 40C, 40kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Two (2) Nos. outgoing Transformer bays for 132/11kV Transformers;
- Six (6) Nos. Cable feeder bays (one (1) No. spare);
- Space for four future bays, two on each side of the switchgear;
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 132/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.
Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.5 ohm at 50C
rated for 750A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 32/40MVA Power Transformer.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.
Protection:
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules.
For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.
For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.
Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation
132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
3.10.2
Establish 132kV, 3150A at 40C, 40kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Four (4) Nos. outgoing Transformer bays for 132/11kV Transformers;
- Six (6) Nos. Cable feeder bays (two (2) Nos. spare);
- Space for four future bays, two on each side of the switchgear;
Establish two 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal
enclosed switchgears with vacuum circuit breakers, consisting of the following:
Switchgear A:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 132/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Switchgear B:
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Four (4) Nos. of 11kV Metallic Neutral Earthing Resistors 8.5 ohm at 50C
rated for 750A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 32/40MVA Power Transformer.
Space for four (4) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.
Protection:
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
(in line with remote end protection scope of works) shall be provided for feeders
connected to 132kV FACILITY D substation. The new relays to be installed at
132/11kV Al Wukair 4 substation shall match the protection at 132kV FACILITY D
substation ends.
For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.
Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.
Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation
132kV, 1x500mm2, XLPE, 40MVA, quadruple circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, quadruple circuit, single point earthed with
earth continuity conductor, four (4) cables per phase cable links between
132/11kV Power Transformers and 11kV switchgear, laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
11kV, 1x630mm2, XLPE, four single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests,. Cables and terminations will be
supplied by Kahramaa. Contractor shall coordinate with concerned Kahramaa
department.
Alarms no more required shall be deleted and Alarms related to modifications are
to be included in the SCS.
Protection:
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these circuits is included in the Present
Scope. The new Relays/Equipment to be installed at Al Wukair 4 substation should
match the protection at 132kV Facility D Substation end (supplied under IWPP
project).
Minor modification of the existing Bus bar protection, including conducting Bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for Breaker failure, Gas pressure low and Bus bar protection
operation are to be made available between the Stations based on requirement.
3.10.3
Establish 132kV, 3150A at 40C, 40kA / 1 sec, 3-phase, 50Hz, single bus bar
GIS consisting of following bays:
- One (1) No. Bus section bays;
- Two (2) Nos. outgoing Transformer bays for 132/11kV Transformers;
- Four (4) Nos. Cable feeder bays (two (2) Nos. spare);
- Space for four future bays, two on each side of the switchgear;
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.5 ohm at 50C
rated for 750A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 32/40MVA Power Transformer.
Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.
Protection:
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules.
For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.
For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.
Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
Fire Fighting System
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation
132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
Al Wukair-2 & 5 Remote End S/S Works
The remote end substations, Al Wukair-2 & 5, are also to be built under the same package
and will be connected to the new Al Wukair-3 S/S with 1x132kV cable circuits. The cables
will be installed under separate contract (GTC/736/2015, Package C9). The substation
contractor shall coordinate with cable contractor and complete all necessary works for
putting these feeders into service.
3.10.4
Establish 132kV, 3150A at 40C, 40kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Two (2) Nos. outgoing Transformer bays for 132/11kV Transformers;
- Six (6) Nos. Cable feeder bays (three (3) No. spare);
- Space for four future bays, two on each side of the switchgear;
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 132/11kV Transformers rated 2500A;
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.5 ohm at 50C
rated for 750A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 32/40MVA Power Transformer.
Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.
Protection:
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules.
For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.
For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.
Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.
SCS & Associated Equipment
Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation
132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
Re-testing and Re-commissioning of one number of the existing GIS bay, including
required modifications in the existing GIS bays along with Local Control Panels
including indicating meters in the local control Panels, inscription of additional
alarm facia as required, replacing of GIS name plates and any required works
including, wiring, testing & complete re-commissioning of the above GIS bay.
Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.
Protection
One 1x132kV existing bay to be connected to AL WUKAIR 2 are with Protection
Relays/Equipments under GTC/488C Phase-11 project.
The relays provided at AL WUKAIR 1 are provided under phase 11 projects. The
new Relays/Equipment to be installed at AL WUKAIR 2 substation should match
the protection at 132kV AL WUKAIR 1 Substation end (supplied under Phase-11
project).
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.
Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
PACKAGE S11
3.11
3.11.1
Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
-
Space for four future bays, two on each side of the switchgear.
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
-
Space for four future bays, two on each side of the 11kV switchgear.
Two (2) Nos. Power Transformers 66/11kV, 32/40MVA, Dyn1, with ONAN/ONAF
cooling, OLTC with +5% to -15% in steps of 1.25%, 13.6% impedance on ONAN
provided with AVR, terminal CTs, neutral CTs etc.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Two (2) Nos. 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C rated
for 750A for 30 seconds (including NER monitoring system) for earthing the neutral
of 66/11kV 32/40MVA Power Transformer.
Space for two (2) future capacitor banks along with space for vacuum contactor
panels for the future capacitor banks shall be provided for in the substation layout.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the total load of the
substation with additional capacity of 30%. The capacity of the Transformer is to be
justified by calculation note which shall be subject to approval.
Protection Systems
Relay Protection Equipment for all Primary Equipment (all Bays) as detailed in
Main Scope of Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
(in line with remote end protection scope of works) shall be provided for feeders
connected to Al Wadi West substation. The new relays to be installed at 66/11kV
Abu Hamour West substation shall match the protection at Al Wadi West
substation end.
For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.
For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the capacitor
bank bay.
Separate panel shall be provided for each one of the 11kV incomer bays and each
one of the Auxiliary Transformer bays. Separate load shedding panel shall be
provided for 11kV outgoing feeders of each bus, i.e., for a two bus substation there
shall be two load shedding panels.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
- 66kV GIS shall be equipped with the internal UHF couplers so the retrofitting
can be easily done in the future (sensor location shall be done as per
Specification for PDM)
- 40MVA Transformers shall have all provisions as mentioned in the TMS
specification so the retrofitting can be easily done in the future. Some are listed
as below:
Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
provision of connection points for installation of TEP System (if Kahramaa decides
to adopt this system in future).
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation
66kV, 1x500 mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 66kV GIS and 66/11kV Transformers laid in unfilled concrete troughs with
all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 66/11kV Power
Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, two single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20 m.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) between 11kV switchgear and Auxiliary Transformers. Approx. route length:
50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Re-testing and re-commissioning of the GIS bays along with Local Control Panels
including indicating meters in the local control panels, inscription of additional
alarm facia as required, replacing of GIS name plates and any required works
including, wiring, testing & complete re-commissioning of the above GIS bays.
Alarms no more required shall be deleted and Alarms related to modifications are
to be included in the SCS.
Protection:
2x66kV existing bays to be connected to Abu Hamour West Substation are with Protection
Relays/Equipments under Phase-10 Project.
The relay provided at Al Wadi West for Main-1 protection is Siemens make 7SD52
and for Main-2 Protection is Alstom make P545. The new Relays/Equipment to be
installed at Abu Hamour West substation should match the protection at 66kV Al
Wadi West Substation end (supplied under Phase-10 project).
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.
Minor modification of the existing Bus bar protection, including conducting Bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for Breaker failure, Gas pressure low and Bus bar protection
operation are to be made available between the Stations based on requirement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
3.11.2
REV. 0
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
-
Space for four future bays, two on each side of the 11kV switchgear.
Two (2) Nos. Power Transformers 66/11kV, 32/40MVA, Dyn1, with ONAN/ONAF
cooling, OLTC with +5% to -15% in steps of 1.25%, 13.6% impedance on ONAN
provided with AVR, terminal CTs, neutral CTs etc.
Two (2) Nos. 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C rated
for 750A for 30 seconds (including NER monitoring system) for earthing the neutral
of 66/11kV 32/40MVA Power Transformer.
Space for two (2) future capacitor banks along with space for vacuum contactor
panels for the future capacitor banks shall be provided for in the substation layout.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the total load of the
substation with additional capacity of 30%. The capacity of the Transformer is to be
justified by calculation note which shall be subject to approval.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Protection Systems
Relay Protection Equipment for all Primary Equipment (all Bays) as detailed in
Main Scope of Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
(in line with remote end protection scope of works) shall be provided for feeders
connected Rawdat Al Khail substation. The new relays to be installed at 66/11kV
Rawdat Al Khail 2 substation shall match the protection at Rawdat Al Khail
substation end.
For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.
For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the capacitor
bank bay.
Separate panel shall be provided for each one of the 11kV incomer bays and each
one of the Auxiliary Transformer bays. Separate load shedding panel shall be
provided for 11kV outgoing feeders of each bus, i.e., for a two bus substation there
shall be two load shedding panels.
Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
Fire Detection & Alarm System for Transformer Yards (Power & Auxiliary), Control
& Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (MV & LV including
cable trays) for the entire length of the cable which includes also the substation
cables and all cables inside the Cable basement of all buildings including 11kV
outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Power Cables:
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 66/11kV Power
Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, two single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20 m.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) between 11kV switchgear and Auxiliary Transformers. Approx. route length:
50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
Re-testing and re-commissioning of the GIS bays along with Local Control Panels
including indicating meters in the local control panels, inscription of additional
alarm facia as required, replacing of GIS name plates and any required works
including, wiring, testing & complete re-commissioning of the above GIS bays.
Alarms no more required shall be deleted and Alarms related to modifications are
to be included in the SCS.
Protection:
2x66kV existing bays to be connected to Rawdat Al Khail 2 Substation are with Protection
Relays/Equipments under Phase-11 Project.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
3.11.3
REV. 0
The relay provided at Rawdat Al Khail for Main-1 protection is Alstom make P545
and for Main-2 Protection is Siemens make 7SD52. The new Relays/Equipment to
be installed at Rawdat Al Khail 2 substation should match the protection at 66kV
Rawdat Al Khail Substation end (supplied under Phase-11 project).
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.
Minor modification of the existing Bus bar protection, including conducting Bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for Breaker failure, Gas pressure low and Bus bar protection
operation are to be made available between the Stations based on requirement.
Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
-
Space for four future bays, two on each side of the switchgear.
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
-
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Space for four future bays, two on each side of the 11kV switchgear.
Two (2) Nos. Power Transformers 66/11kV, 32/40MVA, Dyn1, with ONAN/ONAF
cooling, OLTC with +5% to -15% in steps of 1.25%, 13.6% impedance on ONAN
provided with AVR, terminal CTs, neutral CTs etc.
Two (2) Nos. 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C rated
for 750A for 30 seconds (including NER monitoring system) for earthing the neutral
of 66/11kV 32/40MVA Power Transformer.
Space for two (2) future capacitor banks along with space for vacuum contactor
panels for the future capacitor banks shall be provided for in the substation layout.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the total load of the
substation with additional capacity of 30%. The capacity of the Transformer is to be
justified by calculation note which shall be subject to approval.
Protection Systems
Relay Protection Equipment for all Primary Equipment (all Bays) as detailed in
Main Scope of Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
(in line with remote end protection scope of works) shall be provided for feeders
connected to Mehairja Super substation. The new relays to be installed at 66/11kV
Luaib substation shall match the protection at Mehairja Super substation end.
For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.
For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the capacitor
bank bay.
Separate panel shall be provided for each one of the 11kV incomer bays and each
one of the Auxiliary Transformer bays. Separate load shedding panel shall be
provided for 11kV outgoing feeders of each bus, i.e., for a two bus substation there
shall be two load shedding panels.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
Fire Fighting System
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (MV & LV including
cable trays) for the entire length of the cable which includes also the substation
cables and all cables inside the Cable basement of all buildings including 11kV
outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation
66kV, 1x500 mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 66kV GIS and 66/11kV Transformers laid in unfilled concrete troughs with
all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 66/11kV Power
Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, two single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20 m.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) between 11kV switchgear and Auxiliary Transformers. Approx. route length:
50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
Re-testing and re-commissioning of the GIS bays along with Local Control Panels
including indicating meters in the local control panels, inscription of additional
alarm facia as required, replacing of GIS name plates and any required works
including, wiring, testing & complete re-commissioning of the above GIS bays.
Alarms no more required shall be deleted and Alarms related to modifications are
to be included in the SCS.
Protection:
2x66kV existing bays to be connected to Luaib Substation are with Protection
Relays/Equipments under Phase-11 Project.
The relay provided at Mehairja Super for Main-1 protection is Siemens make
7SD52 and for Main-2 Protection is ABB make RED670. The new
Relays/Equipment to be installed at Luaib substation should match the protection
at 66kV Mehairja Super Substation end (supplied under Phase-11 project).
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
3.11.4
REV. 0
Minor modification of the existing Bus bar protection, including conducting Bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for Breaker failure, Gas pressure low and Bus bar protection
operation are to be made available between the Stations based on requirement.
Establish 33kV, 2500A at 40C, 31.5kA / 1 sec, single bus bar GIS, consisting of
the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. outgoing Transformer bays for 33/11kV Transformers;
- Four (4) Nos. feeder bays rated 1250A (two (2) spare);
- Space for four future bays, two on each side of the 33kV switchgear.
Existing 11kV switchgear bays - Re-testing and re-commissioning of the existing A 18,
A 28 , A30 & A 40 switchgear bays and any required works/modifications including,
wiring, naming, label changes, testing & complete re-commissioning of the above
switchgear bays.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 500kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%, 4.75%
impedance, neutral CTs, etc. Existing 315kVA auxiliary transformers to be replaced
with 500kVA transformers as specified above at new location and existing power
cables from A 30 & A 40 11kV switchgear bays to be diverted to the new auxiliary
transformers
Dismantling of 315kVA aux Transformers and to hand over safely to KM store.
Protection:
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in Main
Scope of the Work shall be provided as per standard specification, Protection SLD and
Technical Schedules. Relay and equipment compatible with remote end (in line with
remote end protection scope of works) shall be provided for feeders connected to Ain
Hamad substation. However, the following specific requirements shall be considered:
GTC-735 SCOPE OF WORKS R0
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
New (HV side) protection for existing 33/11kV Power Transformer shall be
provided based on Phase 13 specifications, installed in new control room. All
modification on the 33kV and 11V sides of the 33/11kV Power Transformer
protection shall be done to make it compatible with 33kV side protection.
Contractor shall ensure all the required modifications including provision of any
trip/auxiliary relays, cabling/wiring to achieve Interlocks and Intertrips between
33kV HV side (new control building) and existing 11kV LV switchgears and
protection.
Presently, existing panels (E11 & E21), provided with transformer (HV) side
protection and OHL line differential protection. OHL line differential protection
shall be dismantled and returned to Kahramaa store as per standard procedure.
Transformer mechanical protections relays are provided in the 33kV HV panels as
per old protection philosophy. However, new provision of transformer mechanical
protections relays based on new 33/11kV transformer protection philosophy shall
be contractors responsibility. Existing HV side panels shall be converted to LV
side protection panels. Alternatively, new LV protection panels can be provided
and exact details shall be decided during detail engineering. Contractor shall
ensure that the relays provided in new 33kV Transformer HV Bays protection
panels and those installed in existing 11kV LV bay protection panels are complete
so as to achieve a complete functional protection for the Transformers. Testing
and commissioning of the 33/11kV Transformers protection.
AVR panels with AVR relays are provided for existing two number 33/11kV
Transformers, located in existing control room. Existing AVR equipment shall be
tested and its proper functioning shall be ensured by the Contractor; however, any
AVR equipment modifications, testing and commissioning for AVR scheme due to
connection to new 33kV GIS shall be Contractor's responsibility.
Contractor is responsible to lay control cables (as necessary) and fibre Optic
Cables from existing OTP installed in telecom room up to new 33kV control room
to complete the necessary connection and end-to-end test of protection for the
said links (New control room in Abu Samra to Ain Hamad).
Any required changes to existing protection relay settings, testing and recommissioning of existing 33/11kV transformer, 11kV Switchgear and earthing
transformer shall be the responsibility of the Contractor.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
The existing control system of Alstom PSCN 3020 with Gateways being modified
by M/s. Schneider is having IEC101 for communication to both DCC and NCC.
New SCS shall manage communication to NCC/ENCC/DCC of the new 33kV GIS,
the existing 11kV switchgear and existing station common alarms.
Existing 11kVA BCUs and Measurement Units shall be replaced to integrate with
new SCS. Old 11kV-A protection IEDs to be wired through new BCUs.
(alternatively communication module of protection IEDs can be replaced for
communication with new SCS)
For new common alarms the contractor will use additional BCUs to maintain 20%
spare availability.
Laying, termination and testing of copper cables to extend Telephones from old to
new building.
Laying, termination and testing of two FO single mode cables (2 * 48F) from old to
new building including OTBs in new building.
LV Power Cables, Control Cables with all accessories for the new equipment as well
as for the connections to the existing equipment/systems. Sizing and Voltage drop
calculation shall be strictly carried out for the cables to be proposed from existing LV
services to the new building.
Small Power & Lighting
Earthing & Lightning Protection including connection to the existing system,
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
LVAC Board with all accessories - LV cables from the new 500kVA auxiliary
transformers shall be connected to the new LVAC Board. Besides, two dedicated
feeders shall be provided with adequate capacity to feed existing LVAC board situated
in the existing control room building.
New LVDC Board, Battery, Battery charger and UPS to cater the load requirements
of new equipment and building.
Security Management System according to specification enclosed in section 3.3.15.
Security management system shall cover both existing and new substation
building and open areas. If due to bidders design there are more than one control
rooms, the bidder shall be bound to provide additional SMS material, if required,
for both control rooms.
Laying, termination and testing of copper cables to extend Telephones from old to
new building.
Laying, termination and testing of two FO single mode cables (2 * 48F) from old to
new building including OTBs in new building.
All civil works related to new 33kV GIS including building services,
Fire Detection & Alarm System for the 33KV GIS building & all other areas.
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement.
Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Required modification works with the existing system (tie-in) for Fire Detection and
Alarm System, testing & commissioning, battery calculations, replacement of
batteries (as per calculations, if required) etc in the existing Fire Detection & Alarm
System (which must be verified during commissioning) are included in the present
scope of works.
EPC Contractor must engage the services of the vendor or specialist Fire
contractor involved in execution of existing Fire Alarm System during the tie-in
works with the existing Fire Detection & Alarm System. Commissioning works
must be carried out only by the authorized vendor or Fire contractor who has
installed the existing system.
Power Cables:
33kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor between 33kV GIS and 33/11kV Power Transformers, laid in
unfilled concrete troughs with all accessories. Approx. route length: 50m.
Milestone A
Complete 33kV GIS, connect one cable from the 33kV existing transformer to the
new GIS and the remote end works at Ain Hamad.
Milestone B
Connect the second cable from the 33kV existing transformer to the new GIS and
the corresponding remote end works at Ain Hamad.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Alarms no more required shall be deleted and Alarms related to modifications are
to be included in the SCS.
Protection:
2x33kV existing bays connected to Abu Samra Substation are with Protection
Relays/Equipments under Phase-12 Project.
Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.
Minor modification of the existing Bus bar protection, including conducting Bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for Breaker failure, Gas pressure low and Bus bar protection
operation are to be made available between the Stations based on requirement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
PACKAGE S-12
3.12
3.12.1
Establish 220kV, 4000A at 40C, 50kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Three (3) Nos. outgoing Transformer bays for 220/132kV Transformers suitable
for cable connection as per the approved connection arrangement;
- Two (2) Nos. Shunt Reactor bays suitable for cable connection as per the
approved connection arrangement;
- Six (6) Nos. cable feeder bays;
- Space for four future bays, two on each side of the switchgear;
Establish 132kV, 3150A at 40C, 40kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Three (3) Nos. incoming Transformer bays for 220/132kV Transformers suitable
for GIB connection as per the approved connection arrangement;
- Two (2) Nos. outgoing Transformer bays for 132/11kV Transformers;
- Six (6) Nos. Cable feeder bays;
- Three (3) Nos. 132kV, 315MVA bus duct between 220/132kV Power
Transformers and 132kV GIS;
- Space for four future bays, two on each side of the switchgear;
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 132/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Two (2) Nos. 220kV, 60MVAr Shunt Reactors with terminal CTs, neutral CTs etc.
Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.5 ohm at 50C
rated for 750A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 32/40MVA Power Transformer.
Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 2000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%, 6%
impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the total load of the
substation with additional capacity of 30%. The capacity of the Transformer is to
be justified by calculation note which shall be subject to approval.
Protection:
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules.
For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.
For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.
Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
- Integrated HMI workstation for monitoring system including software for each
online condition monitoring system installed in S/S as well as for their remote
access;
- Necessary LAN & WAN equipment including router/firewall for connection to
remote end.
LV Power Cables, Control Cables with all accessories
Small Power & Lighting
GTC-735 SCOPE OF WORKS R0
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Deluge Water Spray System for Power Transformers, Shunt Reactors & Auxiliary
Transformers
Fire hydrant and ring main piping (all around the substation buildings perimeter).
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Shunt Reactors, Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Power Cables:
3.12.2
220kV, 1x1600mm2, XLPE, 315MVA, triple circuit, single point earthed with
earth continuity conductor cable links between 220kV GIS and 220/132kV
Transformers, laid in unfilled concrete troughs with all accessories. Approx. route
length: 100m.
220kV, 1x500mm2, XLPE, 60MVA, double circuit, solid bonded cable links
between 220kV GIS and 220kV Shunt Reactors, laid in unfilled concrete troughs
with all accessories. Approx. route length: 100m.
132kV, 1x2000mm2, XLPE, 315MVA, triple circuit, single point earthed with
earth continuity conductor cable links between 132kV GIS and 220/132kV Power
Transformers laid in unfilled concrete troughs with all accessories. Approx. route
length: 100m. (alternative to 132kV GI bus duct in case of layout difficulty)
132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
11kV, 1x500mm2, XLPE, 2000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
Establish 220kV, 4000A at 40C, 50kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
- Two (2) Nos. outgoing Transformer bays for 220/66kV Transformers suitable for
cable connection as per the approved connection arrangement;
- Two (2) Nos. Shunt Reactor bays suitable for cable connection as per the
approved connection arrangement;
- Six (6) Nos. cable feeder bays;
- Space for four future bays, two on each side of the switchgear;
Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Two (2) Nos. incoming Transformer bays for 220/66kV Transformers suitable
for GIB connection as per the approved connection arrangement;
- Two (2) Nos. outgoing Transformer bays for 66/11kV Transformers;
- Six (6) Nos. Cable feeder bays;
- Two (2) Nos. 66kV, 200MVA bus duct between 220/66kV Power Transformers
and 66kV GIS;
- Space for four future bays, two on each side of the switchgear;
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 66/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for future Capacitor bank;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Space for four future bays, two on each side of the 11kV switchgear.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Two (2) Nos. 220kV, 60MVAr Shunt Reactors with terminal CTs, neutral CTs etc.
Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.5 ohm at 50C
rated for 750A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 32/40MVA Power Transformer.
Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 2000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%, 6%
impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the total load of the
substation with additional capacity of 30%. The capacity of the Transformer is to
be justified by calculation note which shall be subject to approval.
Protection:
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules.
For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.
For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.
Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
- Integrated HMI workstation for monitoring system including software for each
online condition monitoring system installed in S/S as well as for their remote
access;
- Necessary LAN & WAN equipment including router/firewall for connection to
remote end.
LV Power Cables, Control Cables with all accessories
Small Power & Lighting
Earthing & Lightning Protection
LV Service Equipment
Security Management System according to specification enclosed in section 3.3.15.
All civil works related to new 220/66/11kV substation including building services.
220kV and 66kV GIS & Fire Pump room Cranes
Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
GTC-735 SCOPE OF WORKS R0
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Deluge Water Spray System for Power Transformers, Shunt Reactors & Auxiliary
Transformers
Fire hydrant and ring main piping (all around the substation buildings perimeter).
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Shunt Reactors, Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation
220kV, 1x1200mm2, XLPE, 200MVA, double circuit, single point earthed with
earth continuity conductor cable links between 220kV GIS and 220/66kV
Transformers, laid in unfilled concrete troughs with all accessories. Approx. route
length: 100m.
220kV, 1x500mm2, XLPE, 60MVA, double circuit, solid bonded cable links
between 220kV GIS and 220kV Shunt Reactors, laid in unfilled concrete troughs
with all accessories. Approx. route length: 100m.
66kV, 1x2000mm2, XLPE, 200MVA, double circuit, single point earthed with
earth continuity conductor cable links between 66kV GIS and 220/66kV Power
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Transformers laid in unfilled concrete troughs with all accessories. Approx. route
length: 100m. (alternative to 66kV GI bus duct in case of layout difficulty)
3.12.3
66kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, two single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
11kV, 1x500mm2, XLPE, 2000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
Re-testing and re-commissioning of the existing GIS spare bays along with Local
Control Panels including indicating meters in the local control panels, inscription of
additional alarm facia as required, replacing of GIS name plates and any required
works including, wiring, testing & complete re-commissioning of the above GIS
bays.
Direct intertrip for breaker failure, gas pressure low and busbar protection
operation to be made available between the stations based on requirement.
Alarms no more required shall be deleted and those related to modifications are to
be included in the SCS scope All necessary co-ordination with the cable contractor
for the termination of the EHV cables at both ends.
Other necessary works, depending of the substation built date, are divided into four
categories (types) which are described below.
Remote End Modification - TYPE-1: Substations Built During Phase 8 and Later
The spare bays at remote end Substations built under Phase 8 and later shall be
used for establishing the above underground cable connections between the two
substations. All the required modifications to the existing spare bays at remote end
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Super substations shall be carried out under the present scope of work. The scope
of work shall include but not limited to the following:
Contractor shall check suitability of the existing termination female part in GIS
considering the size of incoming cables from new typical substation. If necessary,
existing termination female parts shall be replaced by suitable one, including all
necessary material and works required for such modification and optional price for
the existing termination female part replacement and all associated works shall be
provided.
Protection scope:
- For Feeders to be connected to substation, the Bays will be equipped with
Protection relays.
- For those 220kV Cable feeders connected to new typical substation, complete
functional protection system as per Standard specification shall be provided.
The bays are fully equipped with protection relays/equipment. The 87C relays
are to be upgraded to get Dual FO port communication wherever applicable as
per latest Kahramaa specifications.
- New relays/equipment shall be installed at the new substation to match the
protection provided at respective Remote end substation bays.
- Contractor has to do proper CT sizing calculation for Kahramaa review and
Adequacy of existing CTs must be checked.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct intertrip for breaker failure, gas pressure low and busbar
protection operation to be made available between the stations based on
requirement.
- All modifications, testing and commissioning, relay setting calculations, relay
testing on final setting, end to end test, overall stability etc. and putting into
service is included in the Present Scope
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
The spare bays at remote end Substations built under Phase 7 shall be used for
establishing the above underground cable connections between the two
substations. All the required modifications to the existing spare bays at remote end
Super substations shall be carried out under the present scope of work. The scope
of work shall include but not limited to the following:
Contractor shall check suitability of the existing termination female part in GIS
considering the size of incoming cables from new typical substation. If necessary,
existing termination female parts shall be replaced by suitable one, including all
necessary material and works required for such modification and optional price for
the existing termination female part replacement and all associated works shall be
provided.
Protection scope:
- For Feeders to be connected to substation, the Bays will be equipped with
Protection relays.
- For those 220kV Cable feeders connected to new typical substation, complete
functional protection system as per Standard specification shall be provided.
The bays are fully equipped with protection relays/equipment. The 87C relays
are to be replaced to get Dual FO port communication wherever applicable as
per latest Kahramaa specifications. Replacement of the existing Trip relay and
TCS Relay.
- New relays/equipment shall be installed at the new substation to match the
protection provided at respective Remote end substation bays.
- Contractor has to do proper CT sizing calculation and check the adequacy of
existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable)..
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct intertrip for breaker failure, gas pressure low and busbar
protection operation to be made available between the stations based on
requirement.
- All modifications, testing and commissioning, relay setting calculations, relay
testing on final setting, end to end test, overall stability etc. and putting into
service is included in the Present Scope
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
- Alarms no more required shall be deleted and those related to modifications are
to be included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.
Remote End Modification - TYPE-3: Substations Built During Phase 5 & 6 and
GTC/53
All the required modifications in the remote end substations built under Phase 5 &
6 and GTC 53 projects shall be carried out under the present scope of work. The
scope of work shall include but not limited to the following:
Contractor shall check suitability of the existing termination female part in the GIS
considering the size of incoming cables from new typical substation. If necessary,
existing termination female parts shall be replaced by suitable one, including all
necessary material and works required for such modification and optional price for
the existing termination female part replacement and all associated works shall be
provided.
Protection:
- The required modification works for protection systems is detailed under
protection scope of work hereunder
- For those 220kV Cable feeders connected to new typical substation S/S,
complete functional protection system as per standard specification shall be
provided. Existing trip relays / TCS relays need to be replaced.
- New relays/equipment shall be installed at remote end substation to match the
(new) protection at new typical substation end.
- Contractor has to do proper CT sizing calculation and check the adequacy of
existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable). Installation of additional CT core or changing of the existing
CTs shall be the responsibility of the Contractor. Optional unit price for the
(132kV GIS) CT replacement and all associated works shall be provided.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Remote End Modification - TYPE-4: Substations Built During Phase 4 and Earlier
All the required modifications in the remote end substations with indoor/ outdoor
switchgear supplied under Phase 4 and earlier projects built in early 1980s shall be
carried out under the present scope of work.
The existing 220V control panels shall be modified as required to match with the
new cable feeder MVA rating. The new control panels shall be fully equipped with
ammeter, voltmeter, MW and MVAr meters etc. as per the technical specifications.
New Annunciations shall be provided in the local control cabinet in bays at remote
end substation.
Contractor shall check suitability of the existing termination female part in the GIS
considering the size of incoming cables from new typical substation. If necessary,
existing termination female parts shall be replaced by suitable one, including all
necessary material and works required for such modification and optional price for
the existing termination female part replacement and all associated works shall be
provided.
Replacement of existing 220kV CTs and VTs as detailed under protection scope of
work hereunder.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Protection:
- For the Cable feeders connected to New Typical Substation, complete
functional protection system as per standard specification shall be provided.
The new relays/equipment shall be installed at remote end substation to match
the new protection provided at 220kV New Typical Substation bays. Existing
trip relays / TCS relays need to be replaced.
- Remote end SLD to be incorporated in one of the 87C relay.
- Existing VTs installed under Phase 3 or earlier projects shall be replaced with
new three Phase, two core VTs.
- Replacement of the existing CTs to meet with new cable feeder rating. The new
CTs required parameters are given in Protection standard Specification and
standard CT ratio. The new CTs construction and other dimensions shall be
identical to the existing CTs so that it can be mounted in the limited space
available in the indoor switchgear bay (Or Outdoor switchgear bays). The
contractor shall be fully responsible for all associated works and required
interfaces. Contractor has to perform proper CT sizing calculation for Kahramaa
review.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
PACKAGE S-13
3.13
3.13.1
Establish 132kV, 3150A @ 40C, 40kA / 1 sec, 3-phase, 50Hz double bus bar
GIS consisting of following bays:
- Two (2) Bus section bays,
- Two (2) Bus coupler bays,
- Six (6) cable feeder bays,
- Four (4) 40MVA outgoing Transformer feeder bays
- Space for four future bays, two on either side of the switchgear
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
11kV switchgear A:
- Two (2) Nos. incomers rated 2500A
- One (1) No. bus section bay rated 2500A
- Eighteen (18) Nos. Bays for outgoing feeders rated 630A
- Two (2) Nos. Feeders for 11/0.415kV Auxiliary Transformers
- Two (2) Nos. Bays for future capacitor banks feeders
- Space for four future bays, two on either side of the switchgear
11kV switchgear B:
- Two (2) Nos. incomers rated 2500A
- One (1) No. bus section bay rated 2500A
- Eighteen (18) Nos. Bays for outgoing feeders rated 630A
- Two (2) Nos. Bays for future capacitor banks feeders
- Space for four future bays, two on either side of the switchgear
Alternatively 11kV GIS is also acceptable.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Four (4) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 40MVA Power Transformer.
Space for four (4) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformers to be supplied shall be of adequate capacity to cater to the total
station load with additional 30% margin. The capacity of the Transformer is to be
justified by calculation note which shall be subject to approval.
Protection Systems
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote ends
(in line with remote end protection scope) shall be provided for feeders connected
to remote end substation.
132kV GIS shall be equipped with the internal UHF couplers so the retrofitting can
be easily done in the future (sensor location shall be done as per Specification for
PDM)
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
6. Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
LV Service Equipment
LV Power Cables, Control Cables with all accessories
Small Power & Lighting
Earthing & Lightning Protection
132kV GIS & Fire Pump Room Crane
Power cables
132kV, 1x500mm2, XLPE, 40MVA, quadruple circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, quadruple circuit, single point earthed with
earth continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, four single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary Transformers.
Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material for all the MEP openings
including HVAC & Fire/Smoke damper openings, floor openings such as panel
openings including future openings, cable openings (spare/future) & all other cable
openings such as substation cables, 11kV outgoing feeders and all cables inside
the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises.
Establish 132kV, 3150A @ 40C, 40kA / 1 sec, 3-phase, 50Hz double bus bar
GIS consisting of following bays:
- Two (2) Bus section bays,
- Two (2) Bus coupler bays,
- Six (6) cable feeder bays,
- Two (2) 40MVA outgoing Transformer feeder bays
- Space for four future bays, two on either side of the switchgear
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 40MVA Power Transformer.
Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformers to be supplied shall be of adequate capacity to cater to the total
station load with additional 30% margin. The capacity of the Transformer is to be
justified by calculation note which shall be subject to approval.
Protection Systems
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote ends
(in line with remote end protection scope) shall be provided for feeders connected
to remote end substation.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
132kV GIS shall be equipped with the internal UHF couplers so the retrofitting can
be easily done in the future (sensor location shall be done as per Specification for
PDM)
LV Service Equipment
LV Power Cables, Control Cables with all accessories
Small Power & Lighting
Earthing & Lightning Protection
132kV GIS & Fire Pump Room Crane
Power cables
132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary Transformers.
Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material for all the MEP openings
including HVAC & Fire/Smoke damper openings, floor openings such as panel
openings including future openings, cable openings (spare/future) & all other cable
openings such as substation cables, 11kV outgoing feeders and all cables inside
the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises
Establish 132kV, 3150A @ 40C, 40kA / 1 sec, 3-phase, 50Hz single bus bar
GIS consisting of following bays:
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- Two (2) Nos. incomers rated 2500A
- One (1) No. bus section bay rated 2500A
- Eighteen (18) Nos. Bays for outgoing feeders rated 630A
- Two (2) Nos. Feeders for 11/0.415kV Auxiliary Transformers
- Two (2) Nos. Bays for future capacitor banks feeders
- Space for four future bays, two on either side of the switchgear
- Alternatively 11kV GIS is also acceptable.
Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 40MVA Power Transformer.
Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformers to be supplied shall be of adequate capacity to cater to the total
station load with additional 30% margin. The capacity of the Transformer is to be
justified by calculation note which shall be subject to approval.
Protection Systems
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote ends
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
(in line with remote end protection scope) shall be provided for feeders connected
to remote end substation.
SCS & Associated Equipment
132kV GIS shall be equipped with the internal UHF couplers so the retrofitting can
be easily done in the future (sensor location shall be done as per Specification for
PDM)
LV Service Equipment
LV Power Cables, Control Cables with all accessories
Small Power & Lighting
Earthing & Lightning Protection
132kV GIS & Fire Pump Room Cranes
Power cables
132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary Transformers.
Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material for all the MEP openings
including HVAC & Fire/Smoke damper openings, floor openings such as panel
openings including future openings, cable openings (spare/future) & all other cable
openings such as substation cables, 11kV outgoing feeders and all cables inside
the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
3.13.4
REV. 0
Re-testing and re-commissioning of the existing GIS spare bays along with Local
Control Panels including indicating meters in the local control panels, inscription of
additional alarm facia as required, replacing of GIS name plates and any required
works including, wiring, testing & complete re-commissioning of the above GIS
bays.
Direct intertrip for breaker failure, gas pressure low and busbar protection
operation to be made available between the stations based on requirement.
Alarms no more required shall be deleted and those related to modifications are to
be included in the SCS scope All necessary co-ordination with the cable contractor
for the termination of the EHV cables at both ends.
Other necessary works, depending of the substation built date, are divided into four
categories (types) which are described below.
Remote End Modification - TYPE-1: Substations Built During Phase 8 and Later
The spare bays at remote end Substations built under Phase 8 and later shall be
used for establishing the above underground cable connections between the two
substations. All the required modifications to the existing spare bays at remote end
Super substations shall be carried out under the present scope of work. The scope
of work shall include but not limited to the following:
Contractor shall check suitability of the existing termination female part in GIS
considering the size of incoming cables from new typical substation. If necessary,
existing termination female parts shall be replaced by suitable one, including all
necessary material and works required for such modification and optional price for
the existing termination female part replacement and all associated works shall be
provided.
Protection scope:
- For Feeders to be connected to substation, the Bays will be equipped with
Protection relays.
- For those 132kV Cable feeders connected to new typical substation, complete
functional protection system as per Standard specification shall be provided.
The bays are fully equipped with protection relays/equipment. The 87C relays
are to be upgraded to get Dual FO port communication wherever applicable as
per latest Kahramaa specifications.
- New relays/equipment shall be installed at the new substation to match the
protection provided at respective Remote end substation bays.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
The spare bays at remote end Substations built under Phase 7 shall be used for
establishing the above underground cable connections between the two
substations. All the required modifications to the existing spare bays at remote end
Super substations shall be carried out under the present scope of work. The scope
of work shall include but not limited to the following:
Contractor shall check suitability of the existing termination female part in GIS
considering the size of incoming cables from new typical substation. If necessary,
existing termination female parts shall be replaced by suitable one, including all
necessary material and works required for such modification and optional price for
the existing termination female part replacement and all associated works shall be
provided.
Protection scope:
- For Feeders to be connected to substation, the Bays will be equipped with
Protection relays.
- For those 132kV Cable feeders connected to new typical substation, complete
functional protection system as per Standard specification shall be provided.
The bays are fully equipped with protection relays/equipment. The 87C relays
are to be replaced to get Dual FO port communication wherever applicable as
per latest Kahramaa specifications. Replacement of the existing Trip relay and
TCS Relay.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Remote End Modification - TYPE-3: Substations Built During Phase 5 & 6 and
GTC/53
All the required modifications in the remote end substations built under Phase 5 &
6 and GTC 53 projects shall be carried out under the present scope of work. The
scope of work shall include but not limited to the following:
Contractor shall check suitability of the existing termination female part in the GIS
considering the size of incoming cables from new typical substation. If necessary,
existing termination female parts shall be replaced by suitable one, including all
necessary material and works required for such modification and optional price for
the existing termination female part replacement and all associated works shall be
provided.
Protection:
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Remote End Modification - TYPE-4: Substations Built During Phase 4 and Earlier
All the required modifications in the remote end substations with indoor/ outdoor
switchgear supplied under Phase 4 and earlier projects built in early 1980s shall be
carried out under the present scope of work.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
The existing 132V control panels shall be modified as required to match with the
new cable feeder MVA rating. The new control panels shall be fully equipped with
ammeter, voltmeter, MW and MVAr meters etc. as per the technical specifications.
New Annunciations shall be provided in the local control cabinet in bays at remote
end substation.
Contractor shall check suitability of the existing termination female part in the GIS
considering the size of incoming cables from new typical substation. If necessary,
existing termination female parts shall be replaced by suitable one, including all
necessary material and works required for such modification and optional price for
the existing termination female part replacement and all associated works shall be
provided.
Replacement of existing 132kV CTs and VTs as detailed under protection scope of
work hereunder.
Protection:
- For the Cable feeders connected to New Typical Substation, complete
functional protection system as per standard specification shall be provided.
The new relays/equipment shall be installed at remote end substation to match
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
the new protection provided at 132kV New Typical Substation bays. Existing
trip relays / TCS relays need to be replaced.
- Remote end SLD to be incorporated in one of the 87C relay.
- Existing VTs installed under Phase 3 or earlier projects shall be replaced with
new three Phase, two core VTs.
- Replacement of the existing CTs to meet with new cable feeder rating. The new
CTs required parameters are given in Protection standard Specification and
standard CT ratio. The new CTs construction and other dimensions shall be
identical to the existing CTs so that it can be mounted in the limited space
available in the indoor switchgear bay (Or Outdoor switchgear bays). The
contractor shall be fully responsible for all associated works and required
interfaces. Contractor has to perform proper CT sizing calculation for Kahramaa
review.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.
- All modifications, testing and commissioning, relay setting calculations, relay
testing on final setting, end to end test, overall stability etc. and putting into
service is included in the Present Scope
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
PACKAGE S-14
3.14
3.14.1
Establish 132kV, 3150A @ 40C, 40kA / 1 sec, 3-phase, 50Hz double bus bar
GIS consisting of following bays:
- Two (2) Bus section bays,
- Two (2) Bus coupler bays,
- Six (6) cable feeder bays,
- Four (4) 40MVA outgoing Transformer feeder bays
- Space for four future bays, two on either side of the switchgear
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
11kV switchgear A:
- Two (2) Nos. incomers rated 2500A
- One (1) No. bus section bay rated 2500A
- Eighteen (18) Nos. Bays for outgoing feeders rated 630A
- Two (2) Nos. Feeders for 11/0.415kV Auxiliary Transformers
- Two (2) Nos. Bays for future capacitor banks feeders
- Space for four future bays, two on either side of the switchgear
11kV switchgear B:
- Two (2) Nos. incomers rated 2500A
- One (1) No. bus section bay rated 2500A
- Eighteen (18) Nos. Bays for outgoing feeders rated 630A
- Two (2) Nos. Bays for future capacitor banks feeders
- Space for four future bays, two on either side of the switchgear
Alternatively 11kV GIS is also acceptable.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Four (4) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 40MVA Power Transformer.
Space for four (4) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformers to be supplied shall be of adequate capacity to cater to the total
station load with additional 30% margin. The capacity of the Transformer is to be
justified by calculation note which shall be subject to approval.
Protection Systems
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote ends
(in line with remote end protection scope) shall be provided for feeders connected
to remote end substation.
132kV GIS shall be equipped with the internal UHF couplers so the retrofitting can
be easily done in the future (sensor location shall be done as per Specification for
PDM)
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
6. Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
LV Service Equipment
LV Power Cables, Control Cables with all accessories
Small Power & Lighting
Earthing & Lightning Protection
132kV GIS & Fire Pump Room Cranes
Power cables
132kV, 1x500mm2, XLPE, 40MVA, quadruple circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, quadruple circuit, single point earthed with
earth continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, four single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary Transformers.
Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material for all the MEP openings
including HVAC & Fire/Smoke damper openings, floor openings such as panel
openings including future openings, cable openings (spare/future) & all other cable
openings such as substation cables, 11kV outgoing feeders and all cables inside
the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises.
Establish 132kV, 3150A @ 40C, 40kA / 1 sec, 3-phase, 50Hz double bas bar
GIS consisting of following bays:
- Two (2) Bus section bays,
- Two (2) Bus coupler bays,
- Six (6) cable feeder bays,
- Two (2) 40MVA outgoing Transformer feeder bays
- Space for four future bays, two on either side of the switchgear
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 40MVA Power Transformer.
Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformers to be supplied shall be of adequate capacity to cater to the total
station load with additional 30% margin. The capacity of the Transformer is to be
justified by calculation note which shall be subject to approval.
Protection Systems
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote ends
(in line with remote end protection scope) shall be provided for feeders connected
to remote end substation.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
132kV GIS shall be equipped with the internal UHF couplers so the retrofitting can
be easily done in the future (sensor location shall be done as per Specification for
PDM)
LV Service Equipment
LV Power Cables, Control Cables with all accessories
Small Power & Lighting
Earthing & Lightning Protection
132kV GIS & Fire Pump Room Cranes
Power cables
132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary Transformers.
Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material for all the MEP openings
including HVAC & Fire/Smoke damper openings, floor openings such as panel
openings including future openings, cable openings (spare/future) & all other cable
openings such as substation cables, 11kV outgoing feeders and all cables inside
the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises..
Establish 132kV, 3150A @ 40C, 40kA / 1 sec, 3-phase, 50Hz single bus bar
GIS consisting of following bays:
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- Two (2) Nos. incomers rated 2500A
- One (1) No. bus section bay rated 2500A
- Eighteen (18) Nos. Bays for outgoing feeders rated 630A
- Two (2) Nos. Feeders for 11/0.415kV Auxiliary Transformers
- Two (2) Nos. Bays for future capacitor banks feeders
- Space for four future bays, two on either side of the switchgear
- Alternatively 11kV GIS is also acceptable.
Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 40MVA Power Transformer.
Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformers to be supplied shall be of adequate capacity to cater to the total
station load with additional 30% margin. The capacity of the Transformer is to be
justified by calculation note which shall be subject to approval.
Protection Systems
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote ends
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
(in line with remote end protection scope) shall be provided for feeders connected
to remote end substation.
SCS & Associated Equipment
132kV GIS shall be equipped with the internal UHF couplers so the retrofitting can
be easily done in the future (sensor location shall be done as per Specification for
PDM)
LV Service Equipment
LV Power Cables, Control Cables with all accessories
Small Power & Lighting
Earthing & Lightning Protection
132kV GIS & Fire Pump Room Cranes
Power cables
132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary Transformers.
Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material for all the MEP openings
including HVAC & Fire/Smoke damper openings, floor openings such as panel
openings including future openings, cable openings (spare/future) & all other cable
openings such as substation cables, 11kV outgoing feeders and all cables inside
the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
3.14.4
REV. 0
Re-testing and re-commissioning of the existing GIS spare bays along with Local
Control Panels including indicating meters in the local control panels, inscription of
additional alarm facia as required, replacing of GIS name plates and any required
works including, wiring, testing & complete re-commissioning of the above GIS
bays.
Direct intertrip for breaker failure, gas pressure low and busbar protection
operation to be made available between the stations based on requirement.
Alarms no more required shall be deleted and those related to modifications are to
be included in the SCS scope All necessary co-ordination with the cable contractor
for the termination of the EHV cables at both ends.
Other necessary works, depending of the substation built date, are divided into four
categories (types) which are described below.
Remote End Modification - TYPE-1: Substations Built During Phase 8 and Later
The spare bays at remote end Substations built under Phase 8 and later shall be
used for establishing the above underground cable connections between the two
substations. All the required modifications to the existing spare bays at remote end
Super substations shall be carried out under the present scope of work. The scope
of work shall include but not limited to the following:
Contractor shall check suitability of the existing termination female part in GIS
considering the size of incoming cables from new typical substation. If necessary,
existing termination female parts shall be replaced by suitable one, including all
necessary material and works required for such modification and optional price for
the existing termination female part replacement and all associated works shall be
provided.
Protection scope:
- For Feeders to be connected to substation, the Bays will be equipped with
Protection relays.
- For those 132kV Cable feeders connected to new typical substation, complete
functional protection system as per Standard specification shall be provided.
The bays are fully equipped with protection relays/equipment. The 87C relays
are to be upgraded to get Dual FO port communication wherever applicable as
per latest Kahramaa specifications.
- New relays/equipment shall be installed at the new substation to match the
protection provided at respective Remote end substation bays.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
The spare bays at remote end Substations built under Phase 7 shall be used for
establishing the above underground cable connections between the two
substations. All the required modifications to the existing spare bays at remote end
Super substations shall be carried out under the present scope of work. The scope
of work shall include but not limited to the following:
Contractor shall check suitability of the existing termination female part in GIS
considering the size of incoming cables from new typical substation. If necessary,
existing termination female parts shall be replaced by suitable one, including all
necessary material and works required for such modification and optional price for
the existing termination female part replacement and all associated works shall be
provided.
Protection scope:
- For Feeders to be connected to substation, the Bays will be equipped with
Protection relays.
- For those 132kV Cable feeders connected to new typical substation, complete
functional protection system as per Standard specification shall be provided.
The bays are fully equipped with protection relays/equipment. The 87C relays
are to be replaced to get Dual FO port communication wherever applicable as
per latest Kahramaa specifications. Replacement of the existing Trip relay and
TCS Relay.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Remote End Modification - TYPE-3: Substations Built During Phase 5 & 6 and
GTC/53
All the required modifications in the remote end substations built under Phase 5 &
6 and GTC 53 projects shall be carried out under the present scope of work. The
scope of work shall include but not limited to the following:
Contractor shall check suitability of the existing termination female part in the GIS
considering the size of incoming cables from new typical substation. If necessary,
existing termination female parts shall be replaced by suitable one, including all
necessary material and works required for such modification and optional price for
the existing termination female part replacement and all associated works shall be
provided.
Protection:
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Remote End Modification - TYPE-4: Substations Built During Phase 4 and Earlier
All the required modifications in the remote end substations with indoor/ outdoor
switchgear supplied under Phase 4 and earlier projects built in early 1980s shall be
carried out under the present scope of work.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
The existing 132V control panels shall be modified as required to match with the
new cable feeder MVA rating. The new control panels shall be fully equipped with
ammeter, voltmeter, MW and MVAr meters etc. as per the technical specifications.
New Annunciations shall be provided in the local control cabinet in bays at remote
end substation.
Contractor shall check suitability of the existing termination female part in the GIS
considering the size of incoming cables from new typical substation. If necessary,
existing termination female parts shall be replaced by suitable one, including all
necessary material and works required for such modification and optional price for
the existing termination female part replacement and all associated works shall be
provided.
Replacement of existing 132kV CTs and VTs as detailed under protection scope of
work hereunder.
Protection:
- For the Cable feeders connected to New Typical Substation, complete
functional protection system as per standard specification shall be provided.
The new relays/equipment shall be installed at remote end substation to match
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
the new protection provided at 132kV New Typical Substation bays. Existing
trip relays / TCS relays need to be replaced.
- Remote end SLD to be incorporated in one of the 87C relay.
- Existing VTs installed under Phase 3 or earlier projects shall be replaced with
new three Phase, two core VTs.
- Replacement of the existing CTs to meet with new cable feeder rating. The new
CTs required parameters are given in Protection standard Specification and
standard CT ratio. The new CTs construction and other dimensions shall be
identical to the existing CTs so that it can be mounted in the limited space
available in the indoor switchgear bay (Or Outdoor switchgear bays). The
contractor shall be fully responsible for all associated works and required
interfaces. Contractor has to perform proper CT sizing calculation for Kahramaa
review.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.
- All modifications, testing and commissioning, relay setting calculations, relay
testing on final setting, end to end test, overall stability etc. and putting into
service is included in the Present Scope
PACKAGE S15
3.15
3.15.1
Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
-
Space for four future bays, two on each side of the switchgear
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
11kV Switchgear A:
-
Space for four future bays, two on each side of the switchgear
11kV Switchgear B:
-
Space for four future bays, two on each side of the 11kV switchgear
Four (4) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.
Space for four (4) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Protection Systems
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote ends
shall be provided for feeders connected to remote end substation.
66kV GIS shall be equipped with the internal UHF couplers so the retrofitting can
be easily done in the future (sensor location shall be done as per Specification for
PDM)
LV Service Equipment
LV Power Cables, Control Cables with all accessories
Small Power & Lighting
Earthing & Lightning Protection
66kV GIS & Fire pump Room Cranes
66kV GIS Room Crane
Power cables
66kV, 1x500mm2, XLPE, 40MVA, quadruple circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
11kV, 1x630mm2, XLPE, 40MVA, quadruple circuit, single point earthed with
earth continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, four single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material for all the MEP openings
including HVAC & Fire/Smoke damper openings, floor openings such as panel
openings including future openings, cable openings (spare/future) & all other cable
openings such as substation cables, 11kV outgoing feeders and all cables inside
the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
-
Space for four future bays, two on each side of the switchgear
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
-
Space for four future bays, two on each side of the 11kV switchgear
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.
Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
Protection Systems
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote ends
(in line with remote end protection scope) shall be provided for feeders connected
to remote end substation.
66kV GIS shall be equipped with the internal UHF couplers so the retrofitting can
be easily done in the future (sensor location shall be done as per Specification for
PDM)
LV Service Equipment
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
66kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, two single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material for all the MEP openings
including HVAC & Fire/Smoke damper openings, floor openings such as panel
openings including future openings, cable openings (spare/future) & all other cable
openings such as substation cables, 11kV outgoing feeders and all cables inside
the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises.
Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, single bus bar
GIS consisting of following bays:
-
Space for four future bays, two on each side of the switchgear
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
-
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Space for four future bays, two on each side of the 11kV switchgear
Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.
Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
Protection Systems
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote ends
(in line with remote end protection scope) shall be provided for feeders connected
to remote end substation.
66kV GIS shall be equipped with the internal UHF couplers so the retrofitting can
be easily done in the future (sensor location shall be done as per Specification for
PDM)
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
2. Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
3. Provision to install moisture sensor.
4. Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
5. Sensor for Transformer Load Current and voltage.
6. Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
LV Service Equipment
LV Power Cables, Control Cables with all accessories
Small Power & Lighting
Earthing & Lightning Protection
66kV GIS Room & Fire Pump Room Cranes
Power cables
66kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, two single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material for all the MEP openings
including HVAC & Fire/Smoke damper openings, floor openings such as panel
openings including future openings, cable openings (spare/future) & all other cable
openings such as substation cables, 11kV outgoing feeders and all cables inside
the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises.
Re-testing and re-commissioning of the existing GIS spare bays along with Local
Control Panels including indicating meters in the local control panels, inscription of
additional alarm facia as required, replacing of GIS name plates and any required
works including, wiring, testing & complete re-commissioning of the above GIS
bays.
Direct intertrip for breaker failure, gas pressure low and busbar protection
operation to be made available between the stations based on requirement.
All necessary co-ordination with the cable contractor for the termination of the EHV
cables at both ends.
Other necessary works, depending of the substation built date, are divided into four
categories (types) which are described below.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Remote End Modification - TYPE-1: Substations Built During Phase 8 and Later
The spare bays at remote end Substations built under Phase 8 and later shall be
used for establishing the above underground cable connections between the two
substations. All the required modifications to the existing spare bays at remote end
Super substations shall be carried out under the present scope of work. The scope
of work shall include but not limited to the following:
Contractor shall check suitability of the existing termination female part in GIS
considering the size of incoming cables from new typical substation. If necessary,
existing termination female parts shall be replaced by suitable one, including all
necessary material and works required for such modification and optional price for
the existing termination female part replacement and all associated works shall be
provided.
Protection:
- For Feeders to be connected to substation, the Bays will be equipped with
Protection relays.
- For those 66kV Cable feeders connected to new typical substation, complete
functional protection system as per Standard specification shall be provided.
The bays are fully equipped with protection relays/equipment. The 87C relays
are to be upgraded to get Dual FO port communication wherever applicable as
per latest Kahramaa specifications.
- New relays/equipment shall be installed at the new substation to match the
protection provided at respective Remote end substation bays.
- Contractor has to do proper CT sizing calculation and check the adequacy of
existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct intertrip for breaker failure, gas pressure low and busbar
protection operation to be made available between the stations based on
requirement.
- All modifications, testing and commissioning, relay setting calculations, relay
testing on final setting, end to end test, overall stability etc. and putting into
service is included in the Present Scope
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
- Alarms no more required shall be deleted and those related to modifications are
to be included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.
Remote End Modification - TYPE-2: Substations Built During Phase 7
The spare bays at remote end Substations built under Phase 7 shall be used for
establishing the above underground cable connections between the two
substations. All the required modifications to the existing spare bays at remote end
Super substations shall be carried out under the present scope of work. The scope
of work shall include but not limited to the following:
Contractor shall check suitability of the existing termination female part in GIS
considering the size of incoming cables from new typical substation. If necessary,
existing termination female parts shall be replaced by suitable one, including all
necessary material and works required for such modification and optional price for
the existing termination female part replacement and all associated works shall be
provided.
Protection:
- For Feeders to be connected to substation, the Bays will be equipped with
Protection relays.
- For those 66kV Cable feeders connected to new typical substation, complete
functional protection system as per Standard specification shall be provided.
The bays are fully equipped with protection relays/equipment. The 87C relays
are to be upgraded to get Dual FO port communication wherever applicable as
per latest Kahramaa specifications.
- New relays/equipment shall be installed at the new substation to match the
protection provided at respective Remote end substation bays.
- Contractor has to do proper CT sizing calculation and check the adequacy of
existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct intertrip for breaker failure, gas pressure low and busbar
protection operation to be made available between the stations based on
requirement.
- All modifications, testing and commissioning, relay setting calculations, relay
testing on final setting, end to end test, overall stability etc. and putting into
service is included in the Present Scope
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
All the required modifications in the remote end substations built under Phase 5 &
6 and GTC 53 projects shall be carried out under the present scope of work. The
scope of work shall include but not limited to the following:
Contractor shall check suitability of the existing termination female part in the GIS
considering the size of incoming cables from new typical substation. If necessary,
existing termination female parts shall be replaced by suitable one, including all
necessary material and works required for such modification and optional price for
the existing termination female part replacement and all associated works shall be
provided.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Remote End Modification - TYPE-4: Substations Built During Phase 4 and Earlier
All the required modifications in the remote end substations with indoor/ outdoor
switchgear supplied under Phase 4 and earlier projects built in early 1980s shall be
carried out under the present scope of work.
The existing 66V control panels shall be modified as required to match with the
new cable feeder MVA rating. The new control panels shall be fully equipped with
ammeter, voltmeter, MW and MVAr meters etc. as per the technical specifications.
New Annunciations shall be provided in the local control cabinet in bays at remote
end substation.
Contractor shall check suitability of the existing termination female part in the GIS
considering the size of incoming cables from new typical substation. If necessary,
existing termination female parts shall be replaced by suitable one, including all
necessary material and works required for such modification and optional price for
the existing termination female part replacement and all associated works shall be
provided.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Replacement of existing 66kV CTs and VTs as detailed under protection scope of
work hereunder.
Protection:
- For the Cable feeders connected to New Typical Substation, complete
functional protection system as per standard specification shall be provided.
The new relays/equipment shall be installed at remote end substation to match
the new protection provided at 66kV New Typical Substation bays. Existing trip
relays / TCS relays need to be replaced.
- Remote end SLD to be incorporated in one of the 87C relay.
- Existing VTs installed under Phase 3 or earlier projects shall be replaced with
new three Phase, two core VTs.
- Replacement of the existing CTs to meet with new cable feeder rating. The new
CTs required parameters are given in Protection standard Specification and
standard CT ratio. The new CTs construction and other dimensions shall be
identical to the existing CTs so that it can be mounted in the limited space
available in the indoor switchgear bay (Or Outdoor switchgear bays). The
contractor shall be fully responsible for all associated works and required
interfaces. Contractor has to perform proper CT sizing calculation for Kahramaa
review.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
PACKAGE S16
3.16
3.16.1
Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
-
Space for four future bays, two on each side of the switchgear
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
11kV Switchgear A:
-
Space four future bays, two on each side of the 11kV switchgear
11kV Switchgear B:
-
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Space for four future bays, two on each side of the 11kV switchgear
Four (4) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.
Space for four (4) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformers to be supplied shall be of adequate capacity to cater to the total
station load with additional 30% margin. The capacity of the Transformer is to be
justified by calculation note which shall be subject to approval.
Protection Systems
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote ends
shall be provided for feeders connected to remote end substation.
66kV GIS shall be equipped with the internal UHF couplers so the retrofitting can
be easily done in the future (sensor location shall be done as per Specification for
PDM)
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
LV Service Equipment
LV Power Cables, Control Cables with all accessories
Small Power & Lighting
Earthing & Lightning Protection
66kV GIS & Fire Pump Room Cranes
Power cables
66kV, 1x500mm2, XLPE, 40MVA, quadruple circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, quadruple circuit, single point earthed with
earth continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, four single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material for all the MEP openings
including HVAC & Fire/Smoke damper openings, floor openings such as panel
openings including future openings, cable openings (spare/future) & all other cable
openings such as substation cables, 11kV outgoing feeders and all cables inside
the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises.
3.16.2
Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
-
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Space for four future bays, two on each side of the switchgear
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
-
Space four future bays, two on each side of the 11kV switchgear
Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.
Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
SLD and Technical Schedules. Relay and equipment compatible with remote ends
(in line with remote end protection scope) shall be provided for feeders connected
to remote end substation.
SCS & Associated Equipment
66kV GIS shall be equipped with the internal UHF couplers so the retrofitting can
be easily done in the future (sensor location shall be done as per Specification for
PDM)
LV Service Equipment
LV Power Cables, Control Cables with all accessories
Small Power & Lighting
Earthing & Lightning Protection
66kV GIS & Fire Pump Room Cranes
Power cables
66kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
11kV, 1x630mm2, XLPE, two single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material for all the MEP openings
including HVAC & Fire/Smoke damper openings, floor openings such as panel
openings including future openings, cable openings (spare/future) & all other cable
openings such as substation cables, 11kV outgoing feeders and all cables inside
the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
Security Management System according to specification enclosed in section 3.3.15
3.16.3
Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, single bus bar
GIS consisting of following bays:
-
Space for four future bays, two on each side of the switchgear
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
-
Space for four future bays, two on each side of the 11kV switchgear
Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.
Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Protection Systems
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote ends
(in line with remote end protection scope) shall be provided for feeders connected
to remote end substation.
66kV GIS shall be equipped with the internal UHF couplers so the retrofitting can
be easily done in the future (sensor location shall be done as per Specification for
PDM)
LV Service Equipment
LV Power Cables, Control Cables with all accessories
Small Power & Lighting
Earthing & Lightning Protection
66kV GIS & Fire Pump Room Cranes
GTC-735 SCOPE OF WORKS R0
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Power cables
66kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, two single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material for all the MEP openings
including HVAC & Fire/Smoke damper openings, floor openings such as panel
openings including future openings, cable openings (spare/future) & all other cable
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
openings such as substation cables, 11kV outgoing feeders and all cables inside
the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises.
Re-testing and re-commissioning of the existing GIS spare bays along with Local
Control Panels including indicating meters in the local control panels, inscription of
additional alarm facia as required, replacing of GIS name plates and any required
works including, wiring, testing & complete re-commissioning of the above GIS
bays.
Direct intertrip for breaker failure, gas pressure low and busbar protection
operation to be made available between the stations based on requirement.
Alarms no more required shall be deleted and those related to modifications are to
be included in the SCS scope All necessary co-ordination with the cable contractor
for the termination of the EHV cables at both ends.
Other necessary works, depending of the substation built date, are divided into four
categories (types) which are described below.
Remote End Modification - TYPE-1: Substations Built During Phase 8 and Later
The spare bays at remote end Substations built under Phase 8 and later shall be
used for establishing the above underground cable connections between the two
substations. All the required modifications to the existing spare bays at remote end
Super substations shall be carried out under the present scope of work. The scope
of work shall include but not limited to the following:
Contractor shall check suitability of the existing termination female part in GIS
considering the size of incoming cables from new typical substation. If necessary,
existing termination female parts shall be replaced by suitable one, including all
necessary material and works required for such modification and optional price for
the existing termination female part replacement and all associated works shall be
provided.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Protection:
- For Feeders to be connected to substation, the Bays will be equipped with
Protection relays.
- For those 66kV Cable feeders connected to new typical substation, complete
functional protection system as per Standard specification shall be provided.
The bays are fully equipped with protection relays/equipment. The 87C relays
are to be upgraded to get Dual FO port communication wherever applicable as
per latest Kahramaa specifications.
- New relays/equipment shall be installed at the new substation to match the
protection provided at respective Remote end substation bays.
- Contractor has to do proper CT sizing calculation and check the adequacy of
existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct intertrip for breaker failure, gas pressure low and busbar
protection operation to be made available between the stations based on
requirement.
- All modifications, testing and commissioning, relay setting calculations, relay
testing on final setting, end to end test, overall stability etc. and putting into
service is included in the Present Scope
The spare bays at remote end Substations built under Phase 7 shall be used for
establishing the above underground cable connections between the two
substations. All the required modifications to the existing spare bays at remote end
Super substations shall be carried out under the present scope of work. The scope
of work shall include but not limited to the following:
Contractor shall check suitability of the existing termination female part in GIS
considering the size of incoming cables from new typical substation. If necessary,
existing termination female parts shall be replaced by suitable one, including all
necessary material and works required for such modification and optional price for
the existing termination female part replacement and all associated works shall be
provided.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Protection:
- For Feeders to be connected to substation, the Bays will be equipped with
Protection relays.
- For those 66kV Cable feeders connected to new typical substation, complete
functional protection system as per Standard specification shall be provided.
The bays are fully equipped with protection relays/equipment. The 87C relays
are to be upgraded to get Dual FO port communication wherever applicable as
per latest Kahramaa specifications.
- New relays/equipment shall be installed at the new substation to match the
protection provided at respective Remote end substation bays.
- Contractor has to do proper CT sizing calculation and check the adequacy of
existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct intertrip for breaker failure, gas pressure low and busbar
protection operation to be made available between the stations based on
requirement.
- All modifications, testing and commissioning, relay setting calculations, relay
testing on final setting, end to end test, overall stability etc. and putting into
service is included in the Present Scope
Remote End Modification - TYPE-3: Substations Built During Phase 5 & 6 and
GTC/53
All the required modifications in the remote end substations built under Phase 5 &
6 and GTC 53 projects shall be carried out under the present scope of work. The
scope of work shall include but not limited to the following:
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Contractor shall check suitability of the existing termination female part in the GIS
considering the size of incoming cables from new typical substation. If necessary,
existing termination female parts shall be replaced by suitable one, including all
necessary material and works required for such modification and optional price for
the existing termination female part replacement and all associated works shall be
provided.
Protection:
- The required modification works for protection systems is detailed under
protection scope of work hereunder
- For those 66kV Cable feeders connected to new typical substation S/S,
complete functional protection system as per standard specification shall be
provided. Existing trip relays / TCS relays need to be replaced.
- New relays/equipment shall be installed at remote end substation to match the
(new) protection at new typical substation end.
- Contractor has to do proper CT sizing calculation and check the adequacy of
existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.
- All modifications, testing and commissioning, relay setting calculations, relay
testing on final setting, end to end test, overall stability etc. and putting into
service is included in the Present Scope
All the required modifications in the remote end substations with indoor/ outdoor
switchgear supplied under Phase 4 and earlier projects built in early 1980s shall be
carried out under the present scope of work.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
The existing 66V control panels shall be modified as required to match with the
new cable feeder MVA rating. The new control panels shall be fully equipped with
ammeter, voltmeter, MW and MVAr meters etc. as per the technical specifications.
New Annunciations shall be provided in the local control cabinet in bays at remote
end substation.
Contractor shall check suitability of the existing termination female part in the GIS
considering the size of incoming cables from new typical substation. If necessary,
existing termination female parts shall be replaced by suitable one, including all
necessary material and works required for such modification and optional price for
the existing termination female part replacement and all associated works shall be
provided.
Replacement of existing 66kV CTs and VTs as detailed under protection scope of
work hereunder. Contractor has to do proper CT sizing calculation. CTs shall be
replaced (unit rates in Price Schedule 4.5 will be applicable).
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Protection:
- For the Cable feeders connected to New Typical Substation, complete
functional protection system as per standard specification shall be provided.
The new relays/equipment shall be installed at remote end substation to match
the new protection provided at 66kV New Typical Substation bays. Existing trip
relays / TCS relays need to be replaced.
- Remote end SLD to be incorporated in one of the 87C relay.
- Existing VTs installed under Phase 3 or earlier projects shall be replaced with
new three Phase, two core VTs.
- Replacement of the existing CTs to meet with new cable feeder rating. The new
CTs required parameters are given in Protection standard Specification and
standard CT ratio. The new CTs construction and other dimensions shall be
identical to the existing CTs so that it can be mounted in the limited space
available in the indoor switchgear bay (Or Outdoor switchgear bays). The
contractor shall be fully responsible for all associated works and required
interfaces. Contractor has to perform proper CT sizing calculation for Kahramaa
review.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.
- All modifications, testing and commissioning, relay setting calculations, relay
testing on final setting, end to end test, overall stability etc. and putting into
service is included in the Present Scope
PACKAGE S17
3.17
3.17.1
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
integrated in construction works in due time. High level of coordination between developer
and substation Contractor will be required during the complete construction period.
The principal elements of 66/11kV TYPE A Substation shall be as follows:
Gas Insulated/ Air Insulated Switchgear
Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
-
Space for four future bays, two on each side of the switchgear
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
11kV Switchgear A:
-
Space four future bays, two on each side of the 11kV switchgear
11kV Switchgear B:
-
Space for four future bays, two on each side of the 11kV switchgear
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Four (4) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.
Space for four (4) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformers to be supplied shall be of adequate capacity to cater to the total
station load with additional 30% margin. The capacity of the Transformer is to be
justified by calculation note which shall be subject to approval.
Protection Systems
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote ends
shall be provided for feeders connected to remote end substation.
Metering system: Tariff meters shall be provided on the 11kV sides of 40MVA
Power Transformers. Standard specification for the bulk consumers shall apply.
Guidelines for Protection Energy Meter and System Control Requirements for
Power Supply to Bulk Consumers are included in the technical specification in
Volume 2 (along with the Scope of Works) as Annexures IV & V (ET-P26-G1,
issue 4 14/5/2014 & ES-EST-P1-G1, issue 0 10/3/2014). Tariff meters shall be
interfaced with SCS using communication protocol, preferable IEC61850, to
enable signal transfer from tariff metering system to NCC.
66kV GIS shall be equipped with the internal UHF couplers so the retrofitting can
be easily done in the future (sensor location shall be done as per Specification for
PDM)
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
LV Service Equipment
LV Power Cables, Control Cables with all accessories
Small Power & Lighting
Earthing & Lightning Protection
66kV GIS & Fire Pump Room Cranes
Power cables
66kV, 1x500mm2, XLPE, 40MVA, quadruple circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, quadruple circuit, single point earthed with
earth continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, four single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material for all the MEP openings
including HVAC & Fire/Smoke damper openings, floor openings such as panel
openings including future openings, cable openings (spare/future) & all other cable
openings such as substation cables, 11kV outgoing feeders and all cables inside
the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Interface between EPC Contractor and civil design team of developer will be required in
the early stage of the project, to ensure that any specific requirements are defined and
integrated in construction works in due time. High level of coordination between developer
and substation Contractor will be required during the complete construction period.
The principal elements of 66/11kV TYPE B Substation shall be as follows:
Gas Insulated/ Air Insulated Switchgear
Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
-
Space for four future bays, two on each side of the switchgear
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
-
Space four future bays, two on each side of the 11kV switchgear
Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.
Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote ends
(in line with remote end protection scope) shall be provided for feeders connected
to remote end substation.
Metering system: Tariff meters shall be provided on the 11kV sides of 40MVA
Power Transformers. Standard specification for the bulk consumers shall apply.
Guidelines for Protection Energy Meter and System Control Requirements for
Power Supply to Bulk Consumers are included in the technical specification in
Volume 2 (along with the Scope of Works) as Annexures IV & V (ET-P26-G1,
issue 4 14/5/2014 & ES-EST-P1-G1, issue 0 10/3/2014). Tariff meters shall be
interfaced with SCS using communication protocol, preferable IEC61850, to
enable signal transfer from tariff metering system to NCC.
66kV GIS shall be equipped with the internal UHF couplers so the retrofitting can
be easily done in the future (sensor location shall be done as per Specification for
PDM)
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
LV Service Equipment
LV Power Cables, Control Cables with all accessories
Small Power & Lighting
Earthing & Lightning Protection
66kV GIS & Fire Pump Room Cranes
Power cables
66kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, two single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material for all the MEP openings
including HVAC & Fire/Smoke damper openings, floor openings such as panel
openings including future openings, cable openings (spare/future) & all other cable
openings such as substation cables, 11kV outgoing feeders and all cables inside
the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises.
Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
-
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Space for four future bays, two on each side of the switchgear
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
11kV Switchgear A:
-
Space four future bays, two on each side of the 11kV switchgear
11kV Switchgear B:
-
Space for four future bays, two on each side of the 11kV switchgear
Four (4) Nos. Power Transformers 66/11kV, 32/40MVA, Vector group of Dyn1,
OLTC with +5% to -15% in steps of 1.25%, 13.6% impedance at ONAN, AVR,
neutral CTs, etc. Due to absence of natural ventilation, substation Contractor is
obliged to perform detailed study of ventilation requirements and coordinate
design for the same with civil Contractor. Preferred are Transformers with
standard, ONAN / ONAF, cooling system and with FO winding temperature
monitoring which should be offered as optional item. Optionally, gas insulated
Transformer may be proposed. Bidders should include in their technical offer
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Four (4) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.
Space for four (4) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc. Consider rated Power and indoor installation
environment, Bidder may propose dry type Transformers. This needs to be clearly
indicated in the Technical Data Sheets.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformers to be supplied shall be of adequate capacity to cater to the total
station load with additional 30% margin. The capacity of the Transformer is to be
justified by calculation note which shall be subject to approval.
Protection Systems
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote ends
shall be provided for feeders connected to remote end substation.
Metering system: Tariff meters shall be provided on the 11kV sides of 40MVA
Power Transformers. Standard specification for the bulk consumers shall apply.
Guidelines for Protection Energy Meter and System Control Requirements for
Power Supply to Bulk Consumers are included in the technical specification in
Volume 2 (along with the Scope of Works) as Annexures IV & V (ET-P26-G1,
issue 4 14/5/2014 & ES-EST-P1-G1, issue 0 10/3/2014). Tariff meters shall be
interfaced with SCS using communication protocol, preferable IEC61850, to
enable signal transfer from tariff metering system to NCC.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
LV Service Equipment
LV Power Cables, Control Cables with all accessories
Small Power & Lighting
Earthing & Lightning Protection
66kV GIS & Fire Pump Room Cranes
Power cables
66kV, 1x500mm2, XLPE, 40MVA, quadruple circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, quadruple circuit, single point earthed with
earth continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, four single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material for all the MEP openings
including HVAC & Fire/Smoke damper openings, floor openings such as panel
openings including future openings, cable openings (spare/future) & all other cable
openings such as substation cables, 11kV outgoing feeders and all cables inside
the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises.
Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
-
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Space for four future bays, two on each side of the switchgear
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
-
Space four future bays, two on each side of the 11kV switchgear
Two (2) Nos. Power Transformers 66/11kV, 32/40MVA, Vector group of Dyn1,
OLTC with +5% to -15% in steps of 1.25%, 13.6% impedance at ONAN, AVR,
neutral CTs, etc. Due to absence of natural ventilation, substation Contractor is
obliged to perform detailed study of ventilation requirements and coordinate
design for the same with civil Contractor. Preferred are Transformers with
standard, ONAN / ONAF, cooling system and with FO winding temperature
monitoring which should be offered as optional item. Optionally, gas insulated
Transformer may be proposed. Bidders should include in their technical offer
detailed specification of the proposed cooling system and special construction
requirements for the same, if any.
Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.
Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc. Consider rated Power and indoor installation
environment, Bidder may propose dry type Transformers. This needs to be clearly
indicated in the Technical Data Sheets.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
load with additional 30% margin. The capacity of the Transformer is to be justified by
calculation note which shall be subject to approval.
Protection Systems
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote ends
(in line with remote end protection scope) shall be provided for feeders connected
to remote end substation.
Metering system: Tariff meters shall be provided on the 11kV sides of 40MVA
Power Transformers. Standard specification for the bulk consumers shall apply.
Guidelines for Protection Energy Meter and System Control Requirements for
Power Supply to Bulk Consumers are included in the technical specification in
Volume 2 (along with the Scope of Works) as Annexures IV & V (ET-P26-G1,
issue 4 14/5/2014 & ES-EST-P1-G1, issue 0 10/3/2014). Tariff meters shall be
interfaced with SCS using communication protocol, preferable IEC61850, to
enable signal transfer from tariff metering system to NCC.
LV Service Equipment
LV Power Cables, Control Cables with all accessories
Small Power & Lighting
66kV GIS & Fire Pump Room Cranes
Earthing & Lightning Protection
Power cables
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
66kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, two single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material for all the MEP openings
including HVAC & Fire/Smoke damper openings, floor openings such as panel
openings including future openings, cable openings (spare/future) & all other cable
openings such as substation cables, 11kV outgoing feeders and all cables inside
the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Civil works and building services for the substation buildings will be undertaken by
Developer. All necessary coordination with the Developer and their contractors shall be
the responsibility of the substation contractors.
Security Management System according to specification enclosed in section 3.3.15
3.17.5
66/11KV FRAMEWORK
(DOUBLE 11KV SWG)
UNDERGROUND
TYPE
A SUBSTATION
Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
-
Space for four future bays, two on each side of the switchgear
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
11kV Switchgear A:
-
Space four future bays, two on each side of the 11kV switchgear
11kV Switchgear B:
-
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Space for four future bays, two on each side of the 11kV switchgear
Four (4) Nos. Power Transformers 66/11kV, 32/40MVA, Vector group of Dyn1,
OLTC with +5% to -15% in steps of 1.25%, 13.6% impedance at ONAN, AVR,
neutral CTs, etc. Due to absence of natural ventilation, substation Contractor is
obliged to perform detailed study of ventilation requirements and coordinate
design for the same with civil Contractor. Preferred are Transformers with
standard, ONAN / ONAF, cooling system and with FO winding temperature
monitoring which should be offered as optional item. Optionally, gas insulated
Transformer may be proposed. Bidders should include in their technical offer
detailed specification of the proposed cooling system and special construction
requirements for the same, if any.
Four (4) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.
Space for four (4) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc. Consider rated Power and indoor installation
environment, Bidder may propose dry type Transformers. This needs to be clearly
indicated in the Technical Data Sheets.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformers to be supplied shall be of adequate capacity to cater to the total
station load with additional 30% margin. The capacity of the Transformer is to be
justified by calculation note which shall be subject to approval.
Protection Systems
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote ends
shall be provided for feeders connected to remote end substation.
Metering system: Tariff meters shall be provided on the 11kV sides of 40MVA
Power Transformers. Standard specification for the bulk consumers shall apply.
Guidelines for Protection Energy Meter and System Control Requirements for
Power Supply to Bulk Consumers are included in the technical specification in
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
LV Service Equipment
LV Power Cables, Control Cables with all accessories
Small Power & Lighting
Earthing & Lightning Protection
66kV GIS & Fire Pump Room Cranes
Power cables
66kV, 1x500mm2, XLPE, 40MVA, quadruple circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, quadruple circuit, single point earthed with
earth continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, four single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
Fire Fighting System
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material for all the MEP openings
including HVAC & Fire/Smoke damper openings, floor openings such as panel
openings including future openings, cable openings (spare/future) & all other cable
openings such as substation cables, 11kV outgoing feeders and all cables inside
the Cable basement of all buildings.
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises.
66/11KV FRAMEWORK
(SINGLE 11KV SWG)
UNDERGROUND
TYPE
SUBSTATION
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
-
Space for four future bays, two on each side of the switchgear
Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
-
Space four future bays, two on each side of the 11kV switchgear
Two (2) Nos. Power Transformers 66/11kV, 32/40MVA, Vector group of Dyn1,
OLTC with +5% to -15% in steps of 1.25%, 13.6% impedance at ONAN, AVR,
neutral CTs, etc. Due to absence of natural ventilation, substation Contractor is
obliged to perform detailed study of ventilation requirements and coordinate
design for the same with civil Contractor. Preferred are Transformers with
standard, ONAN / ONAF, cooling system and with FO winding temperature
monitoring which should be offered as optional item. Optionally, gas insulated
Transformer may be proposed. Bidders should include in their technical offer
detailed specification of the proposed cooling system and special construction
requirements for the same, if any.
Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.
Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.
Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
5.45% impedance, neutral CTs, etc. Consider rated Power and indoor installation
environment, Bidder may propose dry type Transformers. This needs to be clearly
indicated in the Technical Data Sheets.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformers to be supplied shall be of adequate capacity to cater to the total station
load with additional 30% margin. The capacity of the Transformer is to be justified by
calculation note which shall be subject to approval.
Protection Systems
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote ends
(in line with remote end protection scope) shall be provided for feeders connected
to remote end substation.
Metering system: Tariff meters shall be provided on the 11kV sides of 40MVA
Power Transformers. Standard specification for the bulk consumers shall apply.
Guidelines for Protection Energy Meter and System Control Requirements for
Power Supply to Bulk Consumers are included in the technical specification in
Volume 2 (along with the Scope of Works) as Annexures IV & V (ET-P26-G1,
issue 4 14/5/2014 & ES-EST-P1-G1, issue 0 10/3/2014). Tariff meters shall be
interfaced with SCS using communication protocol, preferable IEC61850, to
enable signal transfer from tariff metering system to NCC.
LV Service Equipment
LV Power Cables, Control Cables with all accessories
Small Power & Lighting
Earthing & Lightning Protection
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
66kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
11kV, 1x630mm2, XLPE, two single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.
11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department
Deluge Water Spray System for Power Transformers & Auxiliary Transformers
Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.
FM200 System for the control & relay room, LVAC/DC Room.
Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.
Passive fire protection system Fire Sealant material for all the MEP openings
including HVAC & Fire/Smoke damper openings, floor openings such as panel
openings including future openings, cable openings (spare/future) & all other cable
openings such as substation cables, 11kV outgoing feeders and all cables inside
the Cable basement of all buildings.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises.
Re-testing and re-commissioning of the existing GIS spare bays along with Local
Control Panels including indicating meters in the local control panels, inscription of
additional alarm facia as required, replacing of GIS name plates and any required
works including, wiring, testing & complete re-commissioning of the above GIS
bays.
Direct intertrip for breaker failure, gas pressure low and busbar protection
operation to be made available between the stations based on requirement.
Alarms no more required shall be deleted and those related to modifications are to
be included in the SCS scope All necessary co-ordination with the cable contractor
for the termination of the EHV cables at both ends.
Other necessary works, depending of the substation built date, are divided into four
categories (types) which are described below.
Remote End Modification - TYPE-1: Substations Built During Phase 8 and Later
The spare bays at remote end Substations built under Phase 8 and later shall be
used for establishing the above underground cable connections between the two
substations. All the required modifications to the existing spare bays at remote end
Super substations shall be carried out under the present scope of work. The scope
of work shall include but not limited to the following:
Contractor shall check suitability of the existing termination female part in GIS
considering the size of incoming cables from new typical substation. If necessary,
existing termination female parts shall be replaced by suitable one, including all
necessary material and works required for such modification and optional price for
the existing termination female part replacement and all associated works shall be
provided.
Protection:
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
The spare bays at remote end Substations built under Phase 7 shall be used for
establishing the above underground cable connections between the two
substations. All the required modifications to the existing spare bays at remote end
Super substations shall be carried out under the present scope of work. The scope
of work shall include but not limited to the following:
Contractor shall check suitability of the existing termination female part in GIS
considering the size of incoming cables from new typical substation. If necessary,
existing termination female parts shall be replaced by suitable one, including all
necessary material and works required for such modification and optional price for
the existing termination female part replacement and all associated works shall be
provided.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Protection:
- For Feeders to be connected to substation, the Bays will be equipped with
Protection relays.
- For those 66kV Cable feeders connected to new typical substation, complete
functional protection system as per Standard specification shall be provided.
The bays are fully equipped with protection relays/equipment. The 87C relays
are to be upgraded to get Dual FO port communication wherever applicable as
per latest Kahramaa specifications.
- New relays/equipment shall be installed at the new substation to match the
protection provided at respective Remote end substation bays.
- Contractor has to do proper CT sizing calculation and check the adequacy of
existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct intertrip for breaker failure, gas pressure low and busbar
protection operation to be made available between the stations based on
requirement.
- All modifications, testing and commissioning, relay setting calculations, relay
testing on final setting, end to end test, overall stability etc. and putting into
service is included in the Present Scope
Remote End Modification - TYPE-3: Substations Built During Phase 5 & 6 and
GTC/53
All the required modifications in the remote end substations built under Phase 5 &
6 and GTC 53 projects shall be carried out under the present scope of work. The
scope of work shall include but not limited to the following:
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Contractor shall check suitability of the existing termination female part in the GIS
considering the size of incoming cables from new typical substation. If necessary,
existing termination female parts shall be replaced by suitable one, including all
necessary material and works required for such modification and optional price for
the existing termination female part replacement and all associated works shall be
provided.
Protection:
- The required modification works for protection systems is detailed under
protection scope of work hereunder
- For those 66kV Cable feeders connected to new typical substation S/S,
complete functional protection system as per standard specification shall be
provided. Existing trip relays / TCS relays need to be replaced.
- New relays/equipment shall be installed at remote end substation to match the
(new) protection at new typical substation end.
- Contractor has to do proper CT sizing calculation and check the adequacy of
existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.
- All modifications, testing and commissioning, relay setting calculations, relay
testing on final setting, end to end test, overall stability etc. and putting into
service is included in the Present Scope
All the required modifications in the remote end substations with indoor/ outdoor
switchgear supplied under Phase 4 and earlier projects built in early 1980s shall be
carried out under the present scope of work.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
The existing 66V control panels shall be modified as required to match with the
new cable feeder MVA rating. The new control panels shall be fully equipped with
ammeter, voltmeter, MW and MVAr meters etc. as per the technical specifications.
New Annunciations shall be provided in the local control cabinet in bays at remote
end substation.
Contractor shall check suitability of the existing termination female part in the GIS
considering the size of incoming cables from new typical substation. If necessary,
existing termination female parts shall be replaced by suitable one, including all
necessary material and works required for such modification and optional price for
the existing termination female part replacement and all associated works shall be
provided.
Replacement of existing 66kV CTs and VTs as detailed under protection scope of
work hereunder. Contractor has to do proper CT sizing calculation. CTs shall be
replaced (unit rates in Price Schedule 4.5 will be applicable).
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Protection:
- For the Cable feeders connected to New Typical Substation, complete
functional protection system as per standard specification shall be provided.
The new relays/equipment shall be installed at remote end substation to match
the new protection provided at 66kV New Typical Substation bays. Existing trip
relays / TCS relays need to be replaced.
- Remote end SLD to be incorporated in one of the 87C relay.
- Existing VTs installed under Phase 3 or earlier projects shall be replaced with
new three Phase, two core VTs.
- Replacement of the existing CTs to meet with new cable feeder rating. The new
CTs required parameters are given in Protection standard Specification and
standard CT ratio. The new CTs construction and other dimensions shall be
identical to the existing CTs so that it can be mounted in the limited space
available in the indoor switchgear bay (Or Outdoor switchgear bays). The
contractor shall be fully responsible for all associated works and required
interfaces. Contractor has to perform proper CT sizing calculation for Kahramaa
review.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.
- All modifications, testing and commissioning, relay setting calculations, relay
testing on final setting, end to end test, overall stability etc. and putting into
service is included in the Present Scope
3.18
3.18.1
INTRODUCTION
The works under the subject project includes substation works for establishment of new
transmission substation as well as modification of existing remote end transmission
substation.
This particular scope of works for telecommunication system must be read in conjunction
with other items of the subject document to obtain all details of specified scope of works.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
3.18.2
REV. 0
DESCRIPTION OF WORKS
The works and services to be performed by the Contractor shall comprise the design,
manufacture, shop testing, packing, transport, insurance, unloading, storage at site,
construction works, erection, corrosion protection, site testing, submission of
documentation, commissioning, training of the Employers personnel and warranty of
works.
The Contractor is bound to provide complete works in order to provide a fully operational
telecommunication system even if the equipment or services required for this are not
specifically mentioned in the following description of the scope of works.
The obligation of the Contractor is to fully inform himself about the existing
telecommunication system and to provide all necessary new equipment, to make network
modification by upgrade of existing Kahramaas telecommunication equipment, and/or by
telecommunication system/network reconfiguration required for the connection of the new
and refurbished substations, as per Drawing Ref. No. TED-PH13-TEL-001 Rev. 0
Telecommunication Links Diagram, to existing Kahramaa Telecommunication
Network/System.
The Contractor shall make, based on Power Transmission Network and Fiber Optic
Cables network availability, the best design for the telecommunication connection of new
and refurbished/replaced S/Ss to Kahramaa Telecommunication Network/System.
The proposed design shall be based on the Power Transmission Network and shall
therefore consider necessary sizing of the Substations in terms of Optical Termination,
Optical Transmission System and cross connection facilities for potential future expansion
of the network.
The Contractor shall meet listed substations commissioning dates and therefore shall
establish telecom link to NCC/DCC/ENCC as required in order to allow energization of
S/Ss. In case that approved design cannot be applied at S/S commissioning date because
of FO links unavailability or any other reason, then the Contractor shall provide all
necessary temporary set up in order to establish the link on Kahramaa request and after
availability of the planned FO link the Contractor has to migrate to permanent link, as per
approved design, from such established temporary links. Cost of such temporary or
transitory works is assumed to be included in the contract price, and commissioning
spares shall be considered as required. Also, all necessary activity and materials required
and all coordination with concerned Kahramaa departments to shift telecom services
during outage from outage circuit to operational circuit shall be provided by the Contractor.
In case of refurbished/replaced S/S the Contractor is obliged, as mandatory, to maintain,
in addition to services for the new S/S, all telecommunication services at existing
substation until full power load is transferred to the new S/S.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
The final design for telecommunication equipment is subject to Kahramaa approval before
manufacturing.
Kahramaa shall receive a detailed design engineering of new and refurbished/replaced
S/Ss interface to telecom network for review and approval. A Telecom Design Workshop is
required after award of Contract to discuss the topology before submitting proposal to
Kahramaa.
The obligation of the Contractor is to conduct all necessary co-ordination and all
necessary site survey in order to provide complete works for:
Coordination shall be done with all Phase 13 Contractors (Substations and Cables) as well
with other Kahramaa's Contractors which are currently active as follows:
Contractor
GTC/371/2010,
Cable
Cable
Contractors
Contractors
The new fiber cables under this project are to be provided by the Substation
Contractor/Cable Contractor and are 1 x 48 cores FO cable/OPGW associated with each
new power cable/OHL.
The brief Scope of Telecommunication Works includes the following:
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
existing
Recovery of all services affected by the insertion of a new S/S in the network.
NOTE: For recovery of telecom services (in ALSTOM and ABB Telecom networks) due to
cable diversions only original system supplier is acceptable to conduct these works and
such works shall be subcontracted to the original Telecom Equipment Supplier directly, i.e.
either to ALSTOM or to ABB, as the case may be.
Updating of all Existing Drawings and to update general documents such like
routing tables, overall network, IP addresses list, etc.
The detailed technical requirement for telecommunication system is given under the
General Technical Requirements and Technical Specifications in Volume 2 and Volume
3, Section 3.3.11 of GTC/735/2015, Tender Documents.
In case if new telecommunication equipment is proposed by the Contractor at existing
substation all modification works, necessary modifications in SCS/NCC for alarm signals
from telecom equipment shall be arranged in coordination with S/S contractor, but in case
GTC-735 SCOPE OF WORKS R0
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
The Contractor shall provide only new equipment and he is not allowed to re-use
any of dismantled equipment. Re-use of dismantled equipment is allowed only in a
case if official approval from Kahramaa is received.
In case of Pilot Fiber Optic Cable laid along power cable inside substation
(Supply/installation, termination, splicing at joint closures and OTP/OTB,
including E2E test OTP/OTB - OTP/OTB) or in case of approach cable
within substation area to cable compound (Supply/installation, termination,
splicing at Hood Closure on Gantry and OTP/OTB, including E2E test
OTP/OTB - OTP/OTB) as it has been listed under price schedule for
substations package.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
The works required shall include all necessary works to include the new and
refurbished/replaced/upgraded substations into the existing Kahramaa Telecommunication
Network as per drawing ref. TED-PH13-TEL-001 Rev. 0 Telecommunication Links
Diagram, Technical Specification Section 3.3.11, and Appendix B Price Schedule.
The drawing TED-PH13-TEL-001 Rev. 0 Telecommunication Links Diagram indicates the
connections between substations. For more details, the Contractor shall refer to
Substations and Cables scope of works.
All S/Ss with fiber optic cable terminated shall have multiplexer equipment with optical
interface.
The scope of work is summarized as follows:
Establishment of dual SDH links STM-4 (400 kV and 220 kV substations shall have
STM-4 equipment as minimum). Kahramaa shall receive a detailed design
engineering of the telecom network for review and approval. A Telecom design
workshop is required after the award of contract to discuss the topology before
submission to Kahramaa.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Recovery of services and network re-configuration for all the S/S connected above
a modified S/S in all affected Kahramaa Network.
All necessary works for migration of existing communication links and services to
the new location at all refurbished/replaced substations.
Maintain 20% equipped spares or existing percentage of spares in case that less
than 20% spares are available in the Kahramaa Telecommunication System at
NCC/ENCC/DCC.
Since new Ethernet switch shall be provided in NCC to enable the PMR service. All
necessary Works to shift the PMR server and existing link to new switches in
coordination with SCS contractor.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Switchgear Room (1) and Telecom room (1).Each switchgear room (11kV
onwards) will have Telephone set, additional sets, other than six, shall be
considered by the contractor.
One unit 240 V AC outdoor bell for each new and refurbished/replaced substation
and all necessary related works.
Work for PAX configuration (Alcatel) to fully interconnect the telecom network.
Maintain 20% spares or existing percentage of spares in case that less than 20%
spares are available in the Kahramaa Telephone System at NCC/DCC (Alcatel).
Additional hardware shall be provided, so as to maintain the spare capacity.
All communication system shall be compatible with the existing NMS systems.
All necessary outstation equipment to connect telecom 48VDC power supply (UPS
at new and UPS or 48VDC at existing), Telecommunication Equipment alarms;
TMS alarm list is to be approved by Kahramaa (16 digital inputs minimum).
Works shall include the Software and Hardware Modifications of one or more
existing TMS System to connect the new Substations.
The NMS license should be upgraded for the required additional nodes keeping
20% spare.
All works for Telecom chargers and 48VDC Batteries at relative existing
substations to accept new equipment or modifications/upgrading of existing
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
All works for 240VAC UPS and 110VDC Batteries at relative existing substations to
accept new telecommunication equipment or modifications/upgrading of existing
equipment including, survey, calculations, connecting, documentation and AC
distribution extensions, etc.
240 VAC / 48 VDC converter shall be sized with enough spare power capacity for a
fully equipped cabinet.
All alarms related to dismantled PLC Equipment shall be removed from local
SCS/NMS/SCADA.
Works for migration of existing telecom services at/or routed via refurbished /
replaced substations.
Master Drawing shall be delivered updating the entire network delivered by the
Contractor during past projects (including bulk consumers) in editable format.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Routing Table.
IP addresses.
Updating of All general documents such like routing tables, overall network, IP
addresses list etc.
Name of substation
Al Shahhaniyah Super - New 220/132/11kV
S-1
S-2
S-3
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
Package
REV. 0
Name of substation
Wakrah 3 - New 132/11kV
Mesaieed Ind A (Upgrade) 132/11 kV
S-4
S-5
S-6
S-7
S-8
S-9
S-10
S-11
GTC-735 SCOPE OF WORKS R0
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
Package
REV. 0
Name of substation
Abu Hamour West - 66/11kV
Luaib - 66/11kV
Abu Samra (Upgrade) 33/11 kV
Parallel running of both new and old telecom equipment will be required at above
substations where (Upgrade) is notified. If by substation contractors SCADA channels are
shifted to new telecom, old telecom shall be dismantled and network reconfigured.
Scope of work includes necessary upgrade of remote end S/S to incorporate all the new
S/S to the Kahramaa Telecommunication Network.
Scope of work also includes recovery of all services at any existing S/S affected by the
addition of a new S/S or the insertion between 2 or more S/Ss. The Contractor shall inform
himself of Fiber Optic utilization and telecom network and to plan links accordingly. This
includes patching, network reconfiguration or any other action.
WORKS AT EXISTING SUBSTATIONS
Here below is an informative list of existing substations where modifications such as:
Provision / Upgrade of OTP/FOPPs, works for interfacing of new substations with
Kahramaa Telecom Network, necessary telecom routing of effected substations due to
new cable line LILO, etc., respectively, shall be done.
Package
Name of substation
400/220/66/11kVUmm Al Amad Super
S-1
S-2
400/132/11kV Al Sakhamah
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
Package
REV. 0
Name of substation
400/220/66/11kVUmm Al Amad Super
132/11kVSemaismah
S-3
S-4
S-5
66/11kVDoha Industrial B
220/132/66/11kVDoha Industrial Super
66/11kVAin Khalid North
66/11kVVegetable Market
220/132/11kVMehairja Super
220/132/66/11kV Al Waab Super
S-6
S-7
S-8
400/132/11kVBul Hemmaid
132/11kV Ras Abu Fontas South
S-9
400/132/11kVBul Hemmaid
S-10
132/11kV Al Wukair 1
132/11kV QEZ
S-11
GTC-735 SCOPE OF WORKS R0
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
Package
REV. 0
Name of substation
66/11kV Al Wadi West
220/132/11kVMehairja Super
S-1
S-1
S-2
Name of substation
Scope of Works
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
Package
Name of substation
REV. 0
Scope of Works
FOPP to be renamed.
Necessary telecom routing of
effected substations due to
diversion of OHL Umm Salal Abu Thailah from Umm Salal S/S
to Um Ebariya S/S.
Dismantling of PLC and
associated Teleprotection
equipment working over OHL
Umm Salal - Abu Thailah and
shifting of the same to KM store,
after packaging/labeling.
Dismantling of TSTU working over
OPGW and shifting of the same to
KM store, after
packaging/labeling.
Works for removal of all
applicable alarms from local
SCS/NMS/SCADA and all other
applicable places.
S-2
66/11kVAbu Thailah
(Upgrade)
S-2
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
Package
Name of substation
REV. 0
Scope of Works
S-3
S-4
S-4
S-4
S-5
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
Package
Name of substation
REV. 0
Scope of Works
substation.
If by substation contractors
SCADA channels are shifted to
new telecom, old telecom shall
be dismantled and shifted to KM
store.
S-6
If by substation contractors
SCADA channels are shifted to
new telecom, old telecom shall
be dismantled and shifted to KM
store.
S-6
S-7
Salata - 66/11kV
(Replacement)
S-11
S-7
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
Package
Name of substation
REV. 0
Scope of Works
33/11 kV
Abu Samra.
Parallel running of both new and
old telecom may be required
during commissioning of
substation.
3.18.3
DESCRIPTION OF WORKS
The Contractor is bound to provide complete works to provide fully operational
telecommunication equipment at Framework S/S even if the equipment or services
required for this are not specifically mentioned in the following description of the scope of
works.
The obligation of the Contractor is to fully inform himself about the existing Kahramaa
Telecommunication Network/System and to provide all necessary new equipment, to
make network modification by upgrade of the existing Kahramaas telecommunication
equipment, and/or by telecommunication system/network reconfiguration required for
connection of the new Framework S/S to existing Kahramaa Telecommunication
Network/System.
There will be two FO cables, each 48 cores, laid between Framework S/S and
downstream/upstream S/S, to be provided under Cable Contractors
(GTC/736/2015) and to be utilized for FO connectivity of Framework S/S to
Kahramaa Telecommunication Network/System.
The Contractor shall make, based on Power Transmission Network and Fiber Optic
Cables network availability, the best design for the telecommunication connection of
Framework S/S to Kahramaa Telecommunication Network/System.
In order to meet Framework S/S commissioning date the Contractor shall establish
telecom link to NCC/ENCC/DCC as required in order to allow energization of Framework
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
S/S. In case that approved design for telecommunication equipment cannot be applied at
Framework S/S commissioning date because of Fiber Optic Cables unavailability or any
other reason, then the Contractor shall provide all necessary temporary set up in order to
establish the telecom link for Framework S/S on Kahramaa request without any additional
cost impact and after Fiber Optic Cables availability of the planned FO link the Contractor
has to migrate to permanent FO link, as per approved design, for such temporary
established links.
The final design for telecommunication equipment is subject to Kahramaa approval before
manufacturing.
Kahramaa shall receive a detailed design engineering of the Framework S/S interface to
telecom network for review and approval. A Telecom design workshop is required after
the award of contract to discuss the topology before submitting proposal to Kahramaa.
The obligation of the Contractor is to conduct all necessary co-ordination and all
necessary site survey in order to provide complete works for:
Only personnel, certified by ALSTOM / ABB and, approved by Kahramaa and in presence
of Kahramaas staff, is allowed to work on existing telecom equipment belonging to
respective telecom vendors (ALSTOM; ABB).or such works shall be subcontracted to the
Telecom Equipment Supplier.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
The detailed technical requirement for new telecommunication equipment is given under
the General Technical Requirements and Technical Specifications in Volume 2 and
Volume 3, Section 3.3.11 of Tender Documents.
The Scope of Works is summarized as follows:
Works for Fiber Optical Indoor cables:
Works for fiber optic indoor cables to connect optical transmission equipment (SDH
or PDH equipment) to optical termination equipment (FOPP/OTP/OTB).
Works for Optical Termination Equipment
Fiber Optic Patch Panels (FOPP) and Optical Termination Panel Cubicle (OTP)
required for Framework Cables as well as to be installed at Framework S/S.
FO cables termination and E2E Tests of fiber optic cables shall be responsibility of
the cable contractor.
Works for SDH and PDH equipment
These works include connection of Framework substation into the existing Kahramaa
Telecommunication Network as per Technical Specification Section 3.3.11, and
Appendix B Price Schedule.
The following services are required to be transferred to NCC, ENCC and DCC for
Framework substation:
Two PAX extensions one for NCC PAX and one for DCC PAX with respectively 3
and 3 telephones connected in parallel at the Framework S/S (Minimum six
telephone sets and one outdoor bell). Telephone sets are required to be installed in
Control Room (2), LVAC/DC Room (1), Fire Pump House (1), each Switchgear
Room (1) and Telecom room (1).
Two IEC-104 64 kbps TCP/IP connections from SCS gateways to DCC (SCADA).
Two IEC-104 64 kbps TCP/IP connections from SCS gateways to NCC and
switching to ENCC (SCADA).
One Ethernet connection (2Mb/s minimum) to NCC for TMS / RMS Monitoring
System.
One Ethernet connection (2Mb/s minimum) to NCC for remote access to SCS LAN
at substation (For Fault recorder, Parameter settings ).
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
One Ethernet connection connected to PMR file server at NCC and ENCC.
REV. 0
Provision of one unit 240V AC outdoor bell at Framework S/S and all necessary
related works.
Maintain 20% spares or existing % of spares in case that less than 20% spares are
available in the Kahramaa Telephone System at NCC/DCC (Alcatel PAX).
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Works shall include the Software and Hardware Modifications of one or more
existing Telecommunication Management (TMS) Systems to include all new
telecommunication equipment at Framework S/S (allowing equipment monitoring,
reporting, controlling, configuring etc.).
The NMS license should be upgraded for the required additional node(s) keeping
20% spare.
All communication system shall be compatible with the existing NMS systems.
All necessary outstation equipment to connect telecom 48VDC power supply (UPS
at new and UPS or 48VDC at existing), telecommunication equipment alarms.
All works for Telecom chargers and 48VDC Batteries at relative existing
substations to accept new telecommunication equipment, if any, or
modifications/upgrading of existing equipment including, survey, calculations,
connecting, documentation and DC distribution extensions etc.
All works for 240VAC UPS and 110VDC Batteries at relative existing substations to
accept new telecommunication equipment, if any, or modifications/upgrading of
existing equipment including, survey, calculations, connecting, documentation and
AC distribution extensions etc.
The dismantled UPS, Batteries or Battery charger equipment shall be delivered to
Kahramaa stores packed and labeled as per Kahramaa regulations.
Engineering works, updating of the existing drawings
Updating of all existing network drawings in the same existing format shall be
done.
This shall include but not limited to:
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Routing Table.
IP addresses.
Name of substation
132 kV New Cables
C-11
C-12
132 kV New Cables
132 kV New Cables (LILO)
66 kV New Cables
66 kV New Cables
C-13
66 kV New Cables
66 kV New Cables (LILO)
C-14
66 kV New Cables
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
Package
REV. 0
Name of substation
66 kV New Cables
66 kV New Cables
66 kV New Cables (LILO)
Substations:
Package
S-12
Name of substation
Framework Substation - New 220/66/11kV
Framework Substation - New 220/132/11kV
Framework Substation Type A-1 - New 132/11kV
Framework Substation Type A-2 - New 132/11kV
S-13
S-14
S-15
S-16
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
Package
REV. 0
Name of substation
Framework Substation Type C-1 - New 66/11kV
Framework Substation Type A/C - New 66/11kV
Framework Substation Type A/U-1 - New 66/11kV
S-17
Scope of work includes necessary upgrade of remote end S/S to incorporate all the new
S/S to the Kahramaa Telecommunication Network.
Scope of work also includes recovery of all services at any existing S/S affected by the
addition of a new S/S or the insertion between 2 or more S/Ss. The Contractor shall inform
himself of Fiber Optic utilization and telecom network and to plan links accordingly. This
includes patching, network reconfiguration or any other action.
3.18.4
PACKAGE S19
3.19
3.19.1
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Some of the substations are currently under construction and the proposed commissioning
date for the capacitor banks shall match the substation commissioning should there be
any unforeseen delays in the substation commissioning.
Installation of the new Capacitor banks shall be as follows:
Gharafa 132/66/11kV S/S
Gharafa is existing substation built under phase 4 and further upgraded by M/s L&T under
Phase 10 project. Modification of the existing 132/66/11kV Gharafa substation shall be as
follows:
Install 4x11kV 6MVAr automatic shunt Capacitors utilizing the existing 11kV
Capacitor banks bays;
Space for the capacitor banks along with space for vacuum contactor panels for
the capacitor banks is available in the substation layout. Isolation fence shall be
modified to enable construction of the facilities.
All required civil works related to new building including building services.
11kV, 1x500mm2, XLPE, 6MVA, quadruple circuit, solid bonded (one cable per
phase) between 11kV switchgear and Capacitor Banks. Approx. route length: 80m.
Alternative Items
In case capacitor banks are of the outdoor type, all Civil Works including
foundations and substructure to accommodate the same shall be done.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Two (2) Nos. 11kV Bays for capacitor bank to be installed on spare space on 11kV
Busbar 1 and Busbar 3;
Convert the existing 11kV cable feeder bay in Busbar 2 into Capacitor bank bay,
including replacement of CTs;
Install one (1) 11kV cable feeder bay on spare space in Busbar 1 or 3;
Modification in Schematic Diagrams on 11kV Bus VT-1, VT-2 and VT-3 to provide
VT inputs for capacitor bank control panel.
Existing CTs (400/1A) shall be replaced with the new ones, as per the CT sizing
calculation.
11kV, 1x500mm2, XLPE, 8MVA, triple circuit, solid bonded (one cable per phase)
between 11kV switchgear and Capacitor Banks. Approx. route length: 80m.
Installation of one (1) 11kV outgoing cable feeder between new cable feeder bay
and service corridor outside the Substation boundary wall, included but not limited
to cable laying, cable supports, cable cleats, heat shrinkable caps and
commissioning tests. Cables and terminations will be supplied by KAHRAMAA.
Contractor shall coordinate with concerned KAHRAMAA department.
Space for the capacitor banks is available in the place of the old substation;
All required civil works related to new building including building services.
Alternative Items
In case capacitor banks are of the outdoor type, all Civil Works including
foundations and substructure to accommodate the same shall be done.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
SED is existing substation built under phase 3 and further refurbished by M/s L&T under
Phase 11 project. Modification of the existing 132/66/11kV SED substation shall be as
follows:
Install 4x11kV 6MVAr automatic shunt Capacitors utilizing the existing 11kV
Capacitor banks bays;
Space for the capacitor banks along with space for vacuum contactor panels for
the capacitor banks is available in the substation layout.
All required civil works related to new building including building services.
11kV, 1x500mm2, XLPE, 6MVA, quadruple circuit, solid bonded (one cable per
phase) between 11kV switchgear and Capacitor Banks. Approx. route length: 80m.
Alternative Items
In case capacitor banks are of the outdoor type, all Civil Works including
foundations and substructure to accommodate the same shall be done.
Install 4x11kV 6MVAr automatic shunt Capacitors utilizing the existing 11kV
Capacitor banks bays;
Space for the capacitor banks along with space for vacuum contactor panels for
the capacitor banks is available in the substation layout.
All required civil works related to new building including building services.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
11kV, 1x500mm2, XLPE, 6MVA, quadruple circuit, solid bonded (one cable per
phase) between 11kV switchgear and Capacitor Banks. Approx. route length: 80m.
Alternative Items
In case capacitor banks are of the outdoor type, all Civil Works including
foundations and substructure to accommodate the same shall be done.
Install 4x11kV 6MVAr automatic shunt Capacitors utilizing the existing 11kV
Capacitor banks bays;
Space for the capacitor banks along with space for vacuum contactor panels for
the capacitor banks is available in the substation layout
All required civil works related to new building including building services.
11kV, 1x500mm2, XLPE, 6MVA, quadruple circuit, solid bonded (one cable per
phase) between 11kV switchgear and Capacitor Banks. Approx. route length: 80m.
Alternative Items
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
In case capacitor banks are of the outdoor type, all Civil Works including
foundations and substructure to accommodate the same shall be done.
Two (2) Nos. 11kV Bays for capacitor bank to be installed on spare space on 11kV
Busbar 1 and Busbar 3;
Convert the existing 11kV cable feeder bay in Busbar 2 into Capacitor bank bay,
including replacement of CTs;
Install one (1) 11kV cable feeder bay on spare space in Busbar 1 or 3;
Modification in Schematic Diagrams on 11kV Bus VT-1, VT-2 and VT-3 to provide
VT inputs for capacitor bank control panel.
Existing CTs (400/1A) shall be replaced with the new ones, as per the CT sizing
calculation.
11kV, 1x500mm2, XLPE, 8MVA, triple circuit, solid bonded (one cable per phase)
between 11kV switchgear and Capacitor Banks. Approx. route length: 80m.
Installation of one (1) 11kV outgoing cable feeder between new cable feeder bay
and service corridor outside the Substation boundary wall, included but not limited
to cable laying, cable supports, cable cleats, heat shrinkable caps and
commissioning tests. Cables and terminations will be supplied by KAHRAMAA.
Contractor shall coordinate with concerned KAHRAMAA department.
All required civil works related to new building including building services.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Alternative Items
In case capacitor banks are of the outdoor type, all Civil Works including
foundations and substructure to accommodate the same shall be done.
Install 2x11kV 6MVAr automatic shunt Capacitors utilizing the existing 11kV
Capacitor banks bays.
Automatic shunt Capacitors shall be installed in the available space in the building.
Minor Civil Works shall be done to accommodate the Capacitor Banks in the
available space
Space for the capacitor banks along with space for vacuum contactor panels for
the capacitor banks is available inside the building.
11kV, 1x500mm2, XLPE, 6MVA, double circuit, solid bonded (one cable per phase)
between 11kV switchgear and Capacitor Banks. Approx. route length: 80m.
Two (2) Nos. 11kV Bays for capacitor bank to be installed on spare space on 11kV
Busbar 1 and Busbar 2;
All required civil works related to new building including building services.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
11kV, 1x500mm2, XLPE, 6MVA, double circuit, solid bonded (one cable per phase)
between 11kV switchgear and Capacitor Banks. Approx. route length: 80m.
Alternative Items
In case capacitor banks are of the outdoor type, all Civil Works including
foundations and substructure to accommodate the same shall be done.
Two (2) Nos. 11kV Bays for capacitor bank to be installed on spare space on 11kV
Busbar 1 and Busbar 2;
All required civil works related to new building including building services.
11kV, 1x500mm2, XLPE, 6MVA, double circuit, solid bonded (one cable per phase)
between 11kV switchgear and Capacitor Banks. Approx. route length: 80m.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Alternative Items
In case capacitor banks are of the outdoor type, all Civil Works including
foundations and substructure to accommodate the same shall be done.
Install 2x11kV 6MVAr automatic shunt Capacitors utilizing the existing 11kV
Capacitor banks bays.
Space for the capacitor banks along with space for vacuum contactor panels for
the capacitor banks is available in the substation layout.
All required civil works related to new building including building services.
11kV, 1x500mm2, XLPE, 6MVA, double circuit, solid bonded (one cable per phase)
between 11kV switchgear and Capacitor Banks. Approx. route length: 80m.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Alternative Items
4.
In case capacitor banks are of the outdoor type, all Civil Works including
foundations and substructure to accommodate the same shall be done.
NOTES TO BIDDERS
Sequence of documents: In the case of any discrepancy between Tender Documents, namely,
Price Schedules and Scope of Works, the Scope of Works will prevail.
Equipment/accessories: Not withstanding absence, if any, of specific mention in the Tender, all
equipment/accessories with all support structures etc., as required to meet the design requirement
of this project are deemed to be part of the scope of works. The end terminations shall be in line
with the end equipment and chosen appropriately after verifying the same.
Technical Requirement: The design, cable sizing etc., provided in the Tender documents are
only guiding principles. These shall be verified and it is the responsibility of the prospective
Contractor to ensure that the specified MVA rating for each cable circuit is achieved by adopting
appropriate method and/ or adequate cable sizing, considering thermally independent cable
circuits.
Technical parameters for all the equipment/ accessories required and offered shall be filled in by
Bidder even if certain specific formats are not provided in the Tender.
The total no of cable spans: The indicated cable spans are for pricing purposes. However,
necessary details, schematic drawings etc., with accurate lengths shall be submitted for approval
during detailed engineering stage.
Good engineering practice in all works shall be adapted to Kahramaas satisfaction.
Power cables for all voltage levels connecting different equipment within substation shall be
supplied and installed by the Substation Contractor which will present nominated subcontractor for
the Cable Works.
HV cables between the Transformers and switchgears and between cable gantry located within
substation boundary to Transformer / switchgear shall be laid in the unfilled concrete cable trough
which will be constructed by the substation civil works subcontractor.
HV Connections between outdoor sealing end and SF6 wall bushing: The Necessary Jumper
for connection between outdoor termination and SF6 wall bushing shall be part of scope of supply
of substation Contractor.
EHV Connections, disconnecting and dismantling of existing termination and their related
accessories, to connect new cable shall be part of scope of work for substation Contractor
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
No.
Name of S/S
Type of Design
Package S-1
1.
Prestigious
2.
Residential
3.
132/11kV Lebsayyer
Prestigious
Package S-2
4.
Residential
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
No.
Name of S/S
Type of Design
5.
Residential
6.
Prestigious
Package S-3
7.
132/11kV Al Jahhaniya 2
Residential
8.
Residential
9.
Industrial
10.
132/11kV Wakrah 3
Residential
Package S-4
11.
Prestigious
12.
Prestigious
13.
Residential
14.
66/11kV Musherib
Residential
Package S-5
15.
Prestigious
16.
Residential
Package S-6
17.
Residential
18.
Residential
Package S-7
19.
Residential
20.
Prestigious
Package S-8
21.
132/11kV Mashaf 1
Residential
22.
132/11kV Mashaf 2
Residential
23.
132/11kV Mashaf 3
Residential
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
No.
Name of S/S
Type of Design
24.
132/11kV Al Wukair 10
Residential
Package S-9
25.
132/11kV Al Wukair 9
Residential
26.
132/11kV Al Wukair 8
Residential
27.
132/11kV Al Wukair 7
Residential
28.
132/11kV Al Wukair 6
Residential
Package S-10
29.
132/11kV Al Wukair 5
Residential
30.
132/11kV Al Wukair 4
Residential
31.
132/11kV Al Wukair 3
Residential
32.
132/11kV Al Wukair 2
Residential
Package S-11
33.
Residential
34.
Residential
35.
66/11kV Luaib
Prestigious
Package S-12
36.
Prestigious
37.
Residential
Package S-13
38.
Prestigious
39.
Residential
40.
Prestigious
41.
Residential
42.
Residential
Package S-14
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
No.
Name of S/S
Type of Design
43.
Prestigious
44.
Residential
45.
Prestigious
46.
Residential
47.
Residential
Package S-15
48.
Prestigious
49.
Residential
50.
Prestigious
51.
Residential
52.
Residential
Package S-16
53.
Prestigious
54.
Residential
55.
Prestigious
56.
Residential
57.
Residential
Outdoor Cable Sealing End: Substation Contractor responsible for cable line connection with
outdoor type termination shall include following in their bid price for outdoor sealing end connection
at cable compound/gantry:
respective foundation, steel structure and all necessary material and accessories, surge arresters
including their foundation and steel structure, all material required for earthing of equipment and
structure connection to the earth grid, terminals for connection to OHL down leads, removing of
existing cables and sealing end, if any, and all related civil works. In case that existing foundation
is suitable to be used, Contractor may propose such solution and appropriate structural calculation
shall be provided for Kahramaa approval. Kahramaa decision will be followed in this regard.
Substation Contractor shall supply, install, erect and commission cable links within substation as
per execution plan of substation without any delay; all required interface arrangement shall be
cable Contractor responsibility.
GTC-735 SCOPE OF WORKS R0
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Cable Compounds: Where a Cable Compound is required, a Terminal Tower & Gantries with
their foundations and earthing system to provide no more than 5 resistance to earth for each
structure, Cable Compound Palisade Fence complete with gate, foundations, earthing, kerb stone
etc. shall be provided in order to lead the line in.
Earthing System of mesh type according to IEEE 80 shall be also provided for the whole cable
compound area. The earth conductor shall be of lead sheathed copper as elsewhere specified.
The earthing systems of all structures (tower, gantries, fence etc.) shall be connected to the
earthing mesh. All connections, including mesh earthing conductor intersections shall be made by
thermo weld process.
Testing Equipment: In addition to all related equipment required for cable installation and
commissioning test for cable feeders connected to GIS switchgear and cable feeders to
Transformers as well as necessary coordination with substation manufacturer/Contractor, the test
bushing and degassing, gassing and oil filling/derange shall be part of the substation Contractors
scope and responsibility.
Specifications, Technical schedules and Drawings: New route and relevant new drawings are
provided where necessary. For referring to the main contract information, please note that Single
line diagrams are in Appendix F Drawings, Technical Specifications are in Sections 3.2 & 3.3
and Technical Schedules in Section 3.4 of this Appendix.
Route Length: The quantities given for cable length in TED are approximated for Tendering
purposes and shall be adjusted according to actual results of survey.
Shutdown: The shutdown for diversion of cable circuits or connection of cable circuits to existing
substation shall be arranged by Kahramaa, circuit by circuit only, according to requirement of
Kahramaa network (operation & maintenance).
Earthing Continuity Conductor: Cross-section of earthing continuity conductor should be
provided in order to carry the full value of short circuit current, as specified.
Pilot Fiber optic cable and Pilot Copper cable:
A budget calculation note and cut over plan for diversion of the Pilot FO cables and Pilot Copper
cables shall be provided for Kahramaa approval.
For any of Power outages due to conversion/connection of OHL and/or cable line to cable and/or
OHL line, as specified under GTC 735/2015 and GTC 736/2015 Contracts, the following shall be
provided:
The Substation Contractor shall maintain/restore all protection services running on fibers of OPGW
and Pilot Fiber Optic cables and on copper wires of pilot copper cables associated with above
Power lines.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
The Telecom Contractor shall maintain/restore all telecom and/or IT services running on fibers of
OPGW and Pilot Fiber Optic cables and on copper wires of pilot copper cables associated with
above Power lines.
Coordination between Substation Contractor and Telecom Contractor during above
maintain/restore of services is required. The required Fibre Patch cords for above maintain/restore
of services shall be provided by Substation Contractor and/or Telecom Contractor and shall be
installed in flexible metallic pipes with one patch cord in single pipe, alternatively flexible sheath
patch cables can also be used, subject of Kahramaa approval in both cases.
Old OTBs and Pilot Wire termination equipment not in service, shall be dismantled (subject of
Kahramaa approval) and handed over to Kahramaa stores packed and labeled as per Kahramaa
regulations.
Pilot cable: Installation of gland for termination of pilot cable at relay panel of 11kV SWG is
included in the Scope of substation Contractor.
Cable diversion: Substation Contractor will be responsible to check the existing teleprotection
cable to match with new diversion.
Dismantling of Oil Filled Cable to install new XLPE cable: the following shall be under scope
of work for substation Contractor:
Excavation and related civil work
Removing oil tank
Disconnect Gauge/manometer panels and control/alarm cables
Cut and cap existing oil filled cables
Remove the existing termination
Delivery of dismantled material to Kahramaa store
Work inside Generation/industrial plant (Messaied,
Dukhan and Ras Laffan): All
activities/works inside Messaied, Dukhan and Ras Laffan subject require permission from
Messaied, Dukhan and Ras Laffan authority. Work shall be according to safety rules and
regulations of Messaied, Dukhan and Ras Laffan. Authorised persons for holding required permit
shall be interviewed at Messaied, Dukhan and Ras Laffan.
Alternative Offer (for HV Cable works): Optionally the Bidder is encouraged to submit an
alternative cost effective offer, if he wishes to do so, with complete design justifications,
calculations, parameters, drawings etc., as necessary. However, this optional offer, if submitted
shall be in addition to the main offer and not in lieu of it. Bidders must use the same price schedule
template with only change in the cable conductor for this alternative offer. This shall be submitted
in addition to the main offer.
GTC-735 SCOPE OF WORKS R0
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Warranty: In the event that a new cable requiring connection to an existing cable which is under
warranty by the original contractor, the new cable Contractor will make arrangements with the
original contractor of the existing cable to carry out the connection and to follow prudent
procedures in order to avoid the cancellation of the remaining warranty period on the existing
cable. The original contractor of the existing cable is expected to be cooperative and Kahramaa
will view any reluctance from the original contractor as unacceptable behavior which will have
impact on future approval of bids by such contractor. The new cable Contractor shall guarantee
that their work will be conducted as per normal procedures and will be responsible for the repair of
any damage they may cause to the existing circuit.
Third Party Damage During Warranty Period: No reduction to the Warranty Period "as specified
in Article 9.51 of the GCC" for the Works or any part of the Works, shall take place for whatsoever
reason during the Warranty Period. The Contractor is responsible to make good all defects that
may arise, in accordance with Article 9.53 of the GCC. If third party damage to the Works or any
part of the Works occurs; Kahramaa and the third party shall be responsible for the repair of the
damaged works in accordance with Kahramaa standard regulations and the specification of the
Contract.
Kahramaa may instruct the original Contractor to perform the repair of any third party damage to
the Works or any part of the Works, if the Contractor accepts Kahramaa instruction to perform the
repair or remedy of any third party damage. The cost of such repair shall be paid by Kahramaa to
the Contractor and shall be calculated based on the unit rates of the Contract or within a
reasonable range of.
If Kahramaa performs the repair works through any of its reputable Contractors, the repair work
shall be performed under the supervision of the original Contractor if available at seven (7) days
notice. Costs of supervisor shall be based on unit rates of the original Contract or reasonable
range of. If the original Contractor does not make available to Kahramaa the required resources for
the repair work or the supervisor within above notice period, Kahramaa may conduct the repairs
without further notice to the original Contractor or the presence of their supervisor or
representative but always in accordance with procedures agreed by Kahramaa and the original
Contractor and clearly specified in the original contract document, in absence of which Kahramaa
will operate within its standard practices.
The above repair works shall in no way be used by the Contractor as an excuse to limit or
terminate the Warranty of the Works or the repaired parts.
For outage required on Power cable and/or OH line in order to establish:
1)
2)
the obligation of the Contractor is to provide programme for outage, all necessary material and
works for shifting of existing communication traffic (protection, telecom, Kahramaa IT traffic)
running over FO cable, OPGW, and/or pilot copper cable associated to Power feeder coming
under the subject outage. Prior the restoration i.e. energisation of feeder being under outage the
GTC-735 SCOPE OF WORKS R0
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Contractor is obliged to restore/establish communication traffic as per his final design. The
Contractor is obliged to coordinate closely with Kahramaa System Control on the above
communication traffic shifting
The shutdown for diversion of OHL circuits or connection of OHL circuits to existing substation
shall be arranged by Kahramaa, circuit by circuit only, according to requirement of Kahramaa
network (operation & maintenance).
Foundation Classes (OHL): Foundation classes for OHL specified in the Schedule of Prices are
according to Foundation Design Particulars of Section 3.3.1, Volume 3.
5.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Depending on the connection scheme of the new substation the suitable type of remote end works
shall be applied.
Package S-13 and S-14
Containing of five nos. of 132/11kV substation with the specification and description as provided in
the clauses no. 3.13 and 3.14 of this SOW. Also, it should be noted that types of remote ends are
included (one for SS built after Phase 8, one for those built under Phase 7, one for those built
under Phase 5/6 and GTC 53 projects and one for very old substations with 132kV indoor/ outdoor
switchgear supplied under Phase 3 / 4, RAF A/ B projects built in early 1980s). Depending on the
connection scheme of the new substation the suitable type of remote end works shall be applied.
Package S-15 and S-16
Containing of five nos. 66/11kV substations with the specification and description as provided in
the clause no. 3.15 and 3.16 of this SOW. Also, it should be noted that types of remote ends are
included (one for SS built after Phase 8, one for those built under Phase 7, one for those built
under Phase 5/6 and GTC 53 projects and one for very old substations with 66kV indoor/ outdoor
switchgear supplied under Phase 3 / 4, RAF A/ B projects built in early 1980s).
Package S-17
Containing of four nos. 66/11kV substations, including underground with the specification and
description as provided in the clause no. 3.17 of this SOW. Also, it should be noted that types of
remote ends are included (one for SS built after Phase 8, one for those built under Phase 7, one
for those built under Phase 5/6 and GTC 53 projects and one for very old substations with 66kV
indoor/ outdoor switchgear supplied under Phase 3 / 4, RAF A/ B projects built in early 1980s).
The Bidders shall quote for the above typical substations as specified in the Scope of Works and
Price Schedules. It should be understood by the Bidders that these substations could be or not
implemented within the Contract Period of the Main Package. Also, the number of various
equipment like switchgear bays, Shunt Reactors, Transformers for various voltage levels and
similar could be modified at the time of implementation, depending on the actual requirements of
the Developer and network configuration where new substation is to be connected.
The following rules shall be applicable for award of the Framework Packages:
Price Schedules for Framework Packages shall be part of the Contract between Kahramaa
and successful Bidder(s) for Main Package(s), and shall be valid for period of 1 (one) year
from the Contract Effective Date.
At any time within the first year from the Contract Effective Date (CED), Kahramaa shall have
the option to award part (but minimum one complete substation) or the complete scope of the
Framework Package based on the prices stated in the Framework Package Price Schedules.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
The Contract Period for additional works from the Framework Package shall be calculated
from the date of the Instruction to Proceed. Duration shall be agreed between Kahramaa and
Contractor within the range given in Appendix H Contract Execution Plan for the particular
type of substation. Final Contract Period shall be based on the actual status of the equipment
and design approval, availability of the site plot, and other elements that can influence the
completion time.
Framework Package works award shall be covered by the Instruction to Proceed (similar to
Letter of Award), issued by Kahramaa in the form of letter to the Contractor. The Contractor
should confirm the acceptance of the Instruction to Proceed (including specified Price and
Completion Period, and any other conditions stated therein) by issuance of the letter of
Confirmation.
The awarded works shall be considered as separate Milestone within the existing Contract or
shall be covered by the separate Contract under the same conditions and specifications as
Main Packages Contract.
Any award from the Framework Package shall not affect the 20% limit for Variations as
specified in article 14.2 of General Conditions of Contract.
The criteria for the award to the Framework Packages shall be in the following order:
the Price,
Performance of the Contractor on the Main Packages,
However, the final decision shall be on Kahramaa.
The substation specification and quantities given in the Price Schedules are indicative. The
Kahramaa might decide the change some of the quantities based on the actual requirement,
i.e. alteration in number of xxkV switchgear bays, Shunt Reactors, Power Transformers, etc.
Final Price Schedule shall be established based on the rates derived from the Framework
Package Price Schedules.
Available rates for Remote End works shall be used as applicable to the actual substation
connection point.
LME and Currency adjustment shall be applied based on the date of Final Instruction to
Proceed issued by Kahramaa.
In case of the Framework Package award, the Contractor shall provide Performance Bond
with the value and duration corresponding to the agreed Final Price and Contract Duration
according to the General Conditions of the Contract.
After final price adjustment and approval of Final Price Schedules, Contract shall be amended
by signing and issuing Contract Amendment Agreement.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
6.
REV. 0
Advance Payment, if agreed for the Main Packages, shall be also applicable for Framework
Package.
IMPORTANT NOTES APPLICABLE FOR ALL PACKAGES
Following documents are included in Volume 2 (along with this document, section 3.1 Scope of
Works) of Tender which may be referred to understand Kahramaa requirements regarding
equipment numbering, interlock scheme, Protection energy meter & system control requirements
for Bulk customer:
Annexure I Interlocking Scheme Rev 3
Annexure II Equipment numbering scheme Rev 2
Annexure IV ET-P26-G1 Guidelines for Protection Energy Meter Requirements for Power Supply
to Bulk Consumers
Annexure V - ES-EST-P1-G1 Guideline for System Control Requirements for Power Supply to
Bulk Consumers.pdf
For applicable CT ratio for all voltage levels and bays refer to the document Annexure III - CT
ratios REV 2.xls in Section 3.3.8 of Vol. 3
All modification works at Kahramaa control centers NCC/ENCC/DCC to include new and modified /
upgraded / refurbished existing substations will be covered under a separate contract. The scope
of substation Contractors under this project includes all necessary works inside the substations to
complete the work successfully. This includes co-ordination works with the above Contractor and
Telecommunication Contractor during all stages until commissioning and end to end test.
If future Transformers / Reactors are envisaged elsewhere in the scope, space reserved for these
equipment and trenches of approach cables to these equipment shall be prepared in such a way to
avoid drilling, cutting etc. in future using heavy equipment so as to avoid damages to the existing
installations. To eliminate these difficulties in future, necessary excavations shall be done for
Transformer / Reactor foundations and trenches of approach cables. Finally, these cavities shall
be filled with loose sands making it convenient to construct the foundations and trenches in future.
Note for refurbishment/ modification/ replacement of substation works:
It is planned to modify / replace / upgrade some of the Kahramaa substations in this project. In
case of some of the substations UPDA has allocated new sites adjacent to the existing
substations. Other substations are to be built within the boundary of existing live substations. The
Contractor shall adopt safety procedures related to work in live environ. Wherever and whenever it
is required to obtain outage of any circuit or part of the substation the Contractor shall co-ordinate
with transmission network department to obtain necessary outage and safety documents. In this
respect please note that during the summer time, between months of April to month of October
none of the circuits on load can be released due to heavy load.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
The Contractor shall plan his works to minimize Power supply interruption. The dismantling and
reconstruction shall be done in phased manner which has been described in detail elsewhere.
Where the shifting of respective 400kV, 220kV, 132kV and 66kV OHL / Oil filled and /or XLPE
cables work is allocated to another Contractor under separate contract(s), all required coordination for work schedule, material management etc. shall be done with the other Contractor to
complete the works in full respect. The Contractor shall consider all such requirements and shall
take all necessary measures required for these works.
It may be noted that the diversion/ shifting of 11kV OHL / cable circuits, wherever applicable, to the
new substation is not within the scope of this contract unless specified otherwise in detailed scope
of works.
Wherever specified the Contractor shall supply set(s) of main protection relay e.g. cable differential
protection relay for each of the feeder for remote end stations.
If specified elsewhere some of the primary equipment (such as Reactor) may be reused as per
main scope of works. However completely new functional protection system for ALL equipment is
to be provided as per the specifications, standard drawings and technical schedules. All 400kV,
220kV, 132kV, 66kV, and 11kV Cable / OHL feeders are to be shifted from existing substation to
new switchgear. Hence all protections at remote end substations must be changed to be
compatible with new protections as described under protection scope of works. An extensive site
survey may be carried out by substation Contractor to study detailed scope of work to be
undertaken at remote substations presently connected to the substation. In case of underground
cable feeders care shall be taken to choose proper protection(s) to connect with existing oil filled
cable / XLPE Power cable and pilot cable /fiber optic cable. Remote end substation(s) where
panels are equipped with protections, the required modification to make it functional and
compatible with the new substation is under the Contractors scope as described under protection
scope of works.
Note for Remote End Modification works:
If the case that substation and its remote end works are not awarded to the same Contractor, all
necessary coordination works are deemed to have been included in the offered price of the both
awarded Contractors.
7.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
leave the plant complete and in full working order at the expiration of the warranty period in
accordance with the provisions of the substation Contract.
The establishment of new Overhead lines and LILO of the existing Overhead lines shall be
executed as a part of this substation EPC Contract.
The substation Contractor is bound to provide for all parts of the work to be completed in every
respect for commercial operation and to Kahramaas requirements notwithstanding that any
details, accessories, etc. required for the complete installation and satisfactory operation of the
plant are not specifically mentioned in the Specification. These are to be considered as included in
the Scope of Works and Contract Price.
5.1
7.1
SCOPE OF SUPPLY
The Scope of Supply is as specified in Technical Specifications, Technical Schedules, and
Appendix B: Price Schedules and Appendix F: Drawings.
The quantities indicated in the Schedule of Prices (Appendix B refers) and Drawings
(Appendix F refers) both attached to the Specification are provided for information only. The
substation Contractor is responsible to establish the exact details, quantities of the equipment
and accessories required to complete the whole of the works as described throughout the
Tender Documents, after the necessary approvals.
General Technical Requirements are given in Section 3.2 of Appendix A, while the specific
requirements for the various equipment and works are set forth in Section 3.3 Technical
Specification and Section 3.4 Technical Schedules of Appendix A.
5.2
7.2
SCOPE OF SERVICES
The Scope of Services shall include but be not limited to the following:
Preparation of the detailed specification for each piece of the equipment up to the satisfaction
of Kahramaa before commencement of manufacturing;
Establishment of the project administration and all site and installation procedures as detailed
in the Specification;
Project site organization, at Doha and site offices, stores, local transport etc.;
Detailed soil investigation report and excavation of trial pits and testing of the original soil
properties, including thermal properties;
Detailed site survey at the approved locations, detailed route survey (for underground cables),
preparation of appropriate topographical drawings and establishment of the project set-up;
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Circulate the location map and civil/architectural design drawing and approval requests to all
concerned government authorities. Follow up and obtain such approvals. Regular renewal of
the approvals and work permits as necessary;
Establish the subcontract agreement with the approved local civil Contractor. Follow up and
supervise the civil works and ensure timely and quality execution of the works;
Procurement of mutually compatible elements / accessories for all equipment and installation
of the same by competent personnel through active direct supervision to ensure highest levels
of quality and good engineering practice.
Local transport storage and delivery to the site / storage yard of the equipment;
Manufacturing, factory acceptance tests, packing and transport to site;
Interfaces with other Contractors of Phase 11 (GTC/488 and GTC/450), Phase 12 (GTC/643,
GTC642 and GTC641) and NCC control and equipment manufacturers at the existing
substations and make all necessary arrangement to facilitate the termination of cables/OHL to
the switchgear.
Civil Works including
Site survey, soil investigation work and testing of soils, water and materials used;
Collection of information required for detailed design and construction, including coordination
with the various government ministries and departments, obtaining of building permits, etc.;
Design, preparation of detailed construction drawings and bending schedules, completion and
maintenance of works;
Earthworks, grading and landscaping;
Site surfacing;
Switchgear, control / relay buildings including all building services, compound wall, gates,
structure and plant foundations, cable ways, toughing and ducts;
Temporary and permanent access roads to substation from public road and road works within
substation;
Site lighting system, including security lighting, small Power and lighting installations. Fire
detection & alarm system, FM200 system, passive fire protection (fire sealant works & cable
coating (for HV/ML/LV cables) inside the buildings and fire protection system & Transformer
explosion prevention system, wherever specified for the Transformers & reactors shall be in
accordance with Kahramaa HSE requirements
All cables in basement shall be coated with fire resistance material
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Personal access steps or similar where required above HV / EHV cable in basement.
To avoid damage of the Power cable terminations in substation basement before plugging in
all male part termination sealing ends shall be covered with permanent protective cap till
plugging.
In order to properly supervise the installation works permanent presence of your Power cables
and accessories manufacturer is required. Checking of Power cable system prior to
conducting LV and HV tests shall be performed by both main contractor and the manufacturer.
Air-conditioning and ventilation and smoke extract systems;
Transformer compounds; construction of foundations for all Transformers. Excavation and
backfilling for future Transformers and Reactors.
'E' type fire wall for Transformers, Reactors etc.;
Construction of common / combined oil containment tank other than Transformer oil dyke.
All necessary associated works;
Guard Rooms.
Installation of the equipment under the supervision of equipment manufacturers specialist
technicians;
Clearance of site (Removal of site offices, stores, disused materials, grading and landscaping
on completion, and necessary clearances from govt. / concerned authorities);
Testing & Commissioning;
Training of Kahramaas staff.
Defects Clearance;
Submission of final As-Built drawing
Provision of completion reports with the relevant documents;
Documentation in accordance with the requirements;
Warranty Period Services. The period of Warranty for all the works executed under this shall
be 2 years from the date of Taking Over.
The Warranty obligation and the warranty period shall NOT be changed or reduced by any
third party damages to the Works or any part of the Works, in case the Contractor perform the
repair of that damage or the damage has been repaired under the supervision of the
Contractor.
GTC-735 SCOPE OF WORKS R0
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
The Warranty obligation and the warranty period shall NOT be changed or reduced by any
third party damages to the Works or any part of the Works, in case the Contractor perform the
repair of that damage or the damage has been repaired under the supervision of the
Contractor.
5.3
7.3
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
Similarly, sufficient vertical free space shall be provided to facilitate removal of components
deemed to be withdrawn vertically.
For 33kV and 11kV metal enclosed SWG with withdrawable components: From the component
in draw-out position minimum clear space shall be 1.5m.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
5.4
7.4
REV. 0
TO BE PROVIDED BY
Sl.No
INTERFACE
POINT
SUBSTATION
DESCRIPTION / REQUIRED
CONTRACTOR
ACTIVITY
A.1
GENERAL
AND
CABLES - DESIGN
Substation
plot
layout
x
drawing with coordinates
Substation
plot
drawing
showing
routing inside SS
x
For existing SS
Provide
road
drawing
and
arrangement
at
required)
crossing
duct
s/s
(if
Provide
drawing
crossing
Provide
duct
size
and
arrangement at s/s basement x
and telecom room
10
fence
CABLE
CONTRACTOR
TELECOM
CONTRACTOR
HV
layout
cable x
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
TO BE PROVIDED BY
Sl.No
INTERFACE
POINT
SUBSTATION
DESCRIPTION / REQUIRED
CONTRACTOR
ACTIVITY
11
12
13
14
15
16
17
18
19
CABLE
CONTRACTOR
TELECOM
CONTRACTOR
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
TO BE PROVIDED BY
Sl.No
INTERFACE
POINT
SUBSTATION
DESCRIPTION / REQUIRED
CONTRACTOR
ACTIVITY
CABLE
CONTRACTOR
TELECOM
CONTRACTOR
20
21
Provide Transformer
box details
22
23
x
and Kahramaa
24
Phase Identification
25
26
Identification of
bays /
x
(circuits
and
Power
and Kahramaa
Transformer) numbers
27
28
Specify GIS
requirements.
29
30
test
Specify
cable
requirements
cable
bushing
HV
x
x
test
Specify
safety
clearance
required during the HV test as x
per Kahramaa Specifications.
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
TO BE PROVIDED BY
Sl.No
INTERFACE
POINT
SUBSTATION
DESCRIPTION / REQUIRED
CONTRACTOR
ACTIVITY
31
32
33
Questionnaire
for
data
required
for
protection
x
settings and milestone to
provide required data
34
A.2
GENERAL
AND
HV
CABLES - EQUIPMENT /
MATERIALS
Sealant
sleeves
for
utilized
CABLE
CONTRACTOR
TELECOM
CONTRACTOR
cable
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
TO BE PROVIDED BY
Sl.No
INTERFACE
POINT
SUBSTATION
DESCRIPTION / REQUIRED
CONTRACTOR
ACTIVITY
HV Test bushing
Testing leads
10
A.3
GENERAL
AND
HV
CABLES
WORKS
(Including all tools and
materials
required
for
completion)
Construction
of
cable
trenches / ducts inside SS
from the perimeter fence to
the
GIS
basement
/
Transformer
for
incomer
feeders.
Cables installation
Sealing
sleeves
of
utilized
x
For new SS
cable
CABLE
CONTRACTOR
TELECOM
CONTRACTOR
x
For existing SS
x
x
For existing SS
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
TO BE PROVIDED BY
Sl.No
INTERFACE
POINT
SUBSTATION
DESCRIPTION / REQUIRED
CONTRACTOR
ACTIVITY
CABLE
CONTRACTOR
TELECOM
CONTRACTOR
10
Link Installation
11
12
Enclosure
flange
intermediate plate
13
Seal
14
15
Intermediate gasket
x (if needed)
16
Flange
x (if needed)
17
Electrical
stress
component
18
Cable gland
19
x (if needed)
20
Insulating fluid
21
Seal
22
23
or
x
x
control
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
TO BE PROVIDED BY
Sl.No
INTERFACE
POINT
SUBSTATION
DESCRIPTION / REQUIRED
CONTRACTOR
ACTIVITY
CABLE
CONTRACTOR
TELECOM
CONTRACTOR
etc.)
x
24
HV Test performance
FO CABLES
GTC736/2015
FO
cable
design and all technical
details
GTC735/2015 - Telecom FO
cable design and all technical
details (in case of new and
old
buildings
telecom
connections)
Provision
drawing
of
S/S
layout
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
TO BE PROVIDED BY
Sl.No
INTERFACE
POINT
SUBSTATION
DESCRIPTION / REQUIRED
CONTRACTOR
ACTIVITY
10
FO
Patch
cords
from
x
protection relays to OTP/OTB
11
12
13
14
15
DTS
SYSTEM
Not
Applicable for New Lines
Provision
drawing
Provision of control
equipment layout
of
S/S
layout
room
CABLE
CONTRACTOR
TELECOM
CONTRACTOR
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
TO BE PROVIDED BY
Sl.No
INTERFACE
POINT
SUBSTATION
DESCRIPTION / REQUIRED
CONTRACTOR
ACTIVITY
CABLE
CONTRACTOR
TELECOM
CONTRACTOR
Milestones for FO
termination & testing
10
11
TELECOM EQUIPMENT
Provision
drawing
of
S/S
to x
For new SS
laying,
layout
x
For existing SS
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
TO BE PROVIDED BY
Sl.No
INTERFACE
POINT
SUBSTATION
DESCRIPTION / REQUIRED
CONTRACTOR
ACTIVITY
CABLE
CONTRACTOR
TELECOM
CONTRACTOR
Provision
of
TCP/IP
connections for OMS remote
x
access
and
non-SCADA
applications
10
11
12
13
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
TO BE PROVIDED BY
Sl.No
INTERFACE
POINT
SUBSTATION
DESCRIPTION / REQUIRED
CONTRACTOR
ACTIVITY
CABLE
CONTRACTOR
TELECOM
CONTRACTOR
equipment
14
Specify
Telecom
Barrier
Transformers Terminal Box
color to match with telecom
equipment
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
TO BE PROVIDED BY
Sl.No
INTERFACE
POINT
SUBSTATION
DESCRIPTION / REQUIRED
CONTRACTOR
ACTIVITY
Termination
of
all
GTC735/2015 SS copper
cables at Pilot Copper Cable
Terminal Box including E-E
test (Copper cable E2E test
x
shall include at least the
following tests: Continuity
test,
Isolation
test,
Attenuation test, Near End
Crosstalk, Far End Crosstalk)
10
Termination
of
all
GTC736/2015 copper cables
at
Pilot
Copper
Cable
Terminal Box including E-E
test (Copper cable E2E test
shall include at least the
following tests: Continuity
test,
Isolation
test,
Attenuation test, Near End
Crosstalk, Far End Crosstalk)
11
NCC / ENCC
CONNECTIONS
CABLE
CONTRACTOR
TELECOM
CONTRACTOR
DCC
TECHNICAL AFFAIRS
Electricity Projects Dept.
VOLUME 2
SECTION 3.1
GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS
REV. 0
TO BE PROVIDED BY
Sl.No
INTERFACE
POINT
SUBSTATION
DESCRIPTION / REQUIRED
CONTRACTOR
ACTIVITY
CABLE
CONTRACTOR
TELECOM
CONTRACTOR
ONLINE
MONITORING
SYSTEM (OMS)
TECHNICAL AFFAIRS
Electricity Projects Dept.