Instr 4 Vincent Tirilly
Instr 4 Vincent Tirilly
Instr 4 Vincent Tirilly
Technip has completed the Front End Engineering Design (FEED) of several FLNG projects. One of these is
presented as a perfect example of these designs specifically developed for offshore application as it
associates a front end NGL recovery unit comprising a deep LPG extraction fully integrated with a Dual
Mixed Refrigerant liquefaction process. The specific level of integration developed for the FLNG brings a
new step of complexity of the dynamic simulation by modelling the full integrated process units of the FLNG
and validating the process design based on very stringent design criteria fit for offshore application.
AN EXAMPLE OF FLNG WITH HARD CONSTRAINTS
Technip performed the FEED for a FLNG unit presenting several constraints that drove the design
development with the objective to maximize LNG, propane and butane productions i.e. to reach the best
available efficiency of production for a given quantity of feed gas. Aspen Technology Inc. was selected to
develop the model and to perform the dynamic simulations of this project.
The FLNG was to be located in open sea with relatively harsh waves and wind conditions. The initial concept
needed to be developed to minimize the effects on the safety and performances of the unit associated with
the relatively large motions of the FLNG. Several liquefaction processes can be considered for such
application, mainly divided between processes using refrigerant in vapour condition then less sensitive to
motion and processes with liquid refrigerant vaporised against the treated gas to liquefy. The Air Products
Dual Mixed Refrigerant (AP-DMRTM) process was selected for its high efficiency of liquefaction, its relative
flexibility to balance power of refrigeration between the two refrigeration loops combined with its better ability
to accommodate motions compared to other process with liquid refrigerant.
The selection of the drivers for the refrigeration compressors is a key step of the design development as
indeed the arrangement of the compressor train, the lay out, the maintenance and the availability of the unit
arise from this driver selection. Recognizing that such a project is carrying a number of first-of-a-kind
technologies including development of new components, combinations of proven subsystems, marinization
of onshore proven elements, the management of risk requires a careful attention to novelty in the design.
Aeroderivative gas turbines were selected both as mechanical drivers for refrigerant compressors and for
power generation. The refrigerant compressor arrangement included two parallel compressors (2x50%) for
each refrigeration loop (refer to figure 1). This selection brought the best compromises in term of layout, cost,
efficiency and management of risk and provided a high availability of the liquefaction.
LNG
Natural gas/LNG
Low pressure WMR
CMR
Vapour CMR
Liquid CMR
From
pretreatment
Precooling
Heat
Exchanger
CMR
accumulator
MCHE
WMR
condenser
CMR
Aftercooler
WMR Part.
condenser
LP WMR
Compressor A
HP WMR
Compressor A
CMR
Compressor A
The feed gas presented a large range of compositions with ethane content from 7% to 13%, propane content
from 5% to 8% and butane content from 2% to 3%. Those ranges combined with the ability to meet different
product specifications targeting both local and external markets requested the unit to be very flexible. The
extraction of ethane in particular required variable ratios of LPG recovery from low to high recovery. A high
recovery of propane and butane (>99%) was targeted for all operating cases. An NGL Recovery unit upfront
the Liquefaction section was the primary choice:
to produce a treated gas free from heavy components (including BTEX) to the Liquefaction section,
to produce a variable stream of ethane at a composition that could be used for make-up of the
refrigeration loops,
While NGL recovery technology is based on the cryogenic fractionation of the Natural Gas stream with the
help of a turbo-expander, several different schemes can be considered with different levels of
sophistications. In order to reach the above objectives, the FLEX-E scheme (part of Technips Cryomax
family) was selected (refer to Figure 2). This patented NGL Recovery scheme allows variable ethane
recovery through the addition of a reflux of ethane from the Deethanizer to the top of the recovery column.
Booster
compressor
Dry gas
Treated gas
C2
NGL
MR
To liquefaction
MR
To fuel
C2 to bullet
Demethanizer
Turbo-expander
Deethanizer
Natural Gas
LT Separator
MR
C3+ to
fractionation
Figure 3: Aspen HYSYS tools
The model comprises the following units (refer to figure 4):
Liquefaction section, including the LNG turbine, the flash gas drum and flash gas heat exchanger.
Figure 4: Aspen HYSYS Dynamics simulation model
In order to provide the best possible representation of plant dynamics as wells as to be able to re-use the
model for later project phases, the following fidelity aspects were taken into consideration:
Separators were modelled according to their design mechanical datasheets in what concerns volumes,
sizes and normal liquid holdups.
Shell and tube heat exchangers were configured by imposing the design UA values and with tubes side
and shell side volumes calculated from the mechanical datasheets.
Plate-fin heat exchangers and printed-circuit heat exchangers were configured by adjusting the geometry
of the exchangers to provide the correct fluid volumes in both sides (hot and cold) and by adjusting the U
value to get a good match with the design heat and material balances (HMB) outlet temperature values.
The fractionation columns were modelled using the actual diameter and number of theoretical separation
stages. The height of each separation stage was calculated based on the data available from the process
design sheets. Void spaces in between beds were modelled as an additional separation stage, with a
very low efficiency value to achieve the correct volumes without affecting the fractionation.
Parallel compressors were modelled according to the manufacturers provided compressor maps. Inertias
of the compressor, driver and connecting equipment were taken into account.
Compressor controllers were emulated using AspenTechs proprietary representations of the anti-surge,
load sharing and master performance control blocks (figure 5).
Detailed piping characteristics for a total of more than 250 pipelines were included.
Control valves, on/off valves, check valves and transmitters were rigorously modelled, including actual
characteristics and actuator time constants.
5
All unit operations within scope were rigorously modelled according to design and manufacturers data.
The performance of the turbo-expander was closely matched to the manufacturers data.
All relevant control loops were modelled and tuned.
Figure 6: Low Pressure (LP) stage WMR compressor B during trip and startup
Figure 7 shows the balance of flows of the two compressors during the CMR compressor B start-up. The
plant is operating initially at reduced capacity. At a time approximately equal to 1500 seconds, the discharge
flowrate of both CMR compressors equalises and remains balanced while the FLNG unit throughput is
progressively increased to full capacity. After approximately 2200 seconds the FLNG unit is operating
steadily at full capacity.
Figure 7: CMR compressors A and B discharge flow rate during CMR-B startup
When one refrigeration compressor trips, it is necessary to force a decrease of LNG production
(approximately 50% capacity) since the control system does not provide a fast enough response for avoiding
major disturbances in both refrigeration loops, which may result in losing the liquid levels in the WMR and
CMR accumulators. This is achieved by reducing both the WMR and CMR circulating flowrates with a preset ramp down which forces the set points of WMR and CMR Joule-Thomson (JT) valves around the
cryogenic exchangers to close in the range of 50-60% of their normal set points.
7
Figure 8 shows the CMR flowrate variations after the trip of the WMR compressor B. Following the trip event,
the openings of CMR JT valves are reduced to limit the unit capacity and the refrigeration loop circulating
flow to maintain the unit under steady conditions at a reduced capacity.
specifications LNG production. The unit capacity shall be decreased to be able to maintain the specifications
of the produced LNG with this lower duty available in JT mode.
A key parameter to increase cooling duties during expander trip is to increase the WMR at the inlet of the
NGL recovery to cool down the inlet feed gas before entering the LT separator. The figure 10 below shows
the variation of temperature at the inlet of the LT separator following an expander trip.
Figure 11:
Inlet NG flow rate after turbo-expander trip
Figure 12:
CMR mass flow rate after turbo-expander trip
9
Among the different scenarios, the NGL Recovery booster compressor trip is the most representative of the
integration of the NGL Recovery with the Liquefaction.
When the treated gas booster compressor trips, the liquefaction capacity decreases as the pressure of
liquefaction drops.
Figure 13 shows the treated gas fall of pressure at the inlet of the liquefaction after the booster compressor
trip. After approximately 2 minutes, the pressure in the liquefaction has decreased enough to equalise with
NGL recovery treated gas pressure: The natural gas flows through the booster compressor bypass and the
liquefaction pressure quickly stabilises.
10
Figure 15: CMR volumetric flowrate
The NGL Recovery booster compressor restart scenario needs also a careful analysis of the transient
phenomenon to restore the liquefaction pressure to its initial value and progressively increase the unit
throughput to full capacity.
Figure 16 illustrates the booster compressor restart performance while figure 17 shows the variations of LNG
production capacity after booster compressor restart.
Figure 17: Produced LNG flow rate at the top of the MCHE
during the booster compressor restart
11
CONCLUSIONS
Aspen HYSYS Dynamic models have proved in this and previous studies to be able to provide very valuable
insight on the operability of LNG plants under upset and transient situations. The models can be used early
in the design process to detect operational issues which can be more easily fixed during the design phases
to avoid later expensive operational issues, as well as to optimize the control and operating strategies. The
models are fully re-usable during the project life cycle1,2. A model created during the design phase of the
project can be easily upgraded with final design data and with plant test data during the EPC phase prior to
plant startup.
One important conclusion was to demonstrate that the process control systems allow LNG production to
continue, albeit at a reduced rate, following any machinery trip in the NGL recovery or liquefaction sections.
The use of a turbo-expander based cryogenic NGL recovery unit upstream of liquefaction is becoming
increasingly common for reasons that include the high pressure liquefaction as a source of improved
efficiency. Whereas the advantages of such schemes are increasingly recognised, the additional machinery
is a potential source of reduced reliability: The dynamic simulation study performed during the FEED stage
has served to confirm the operability and controllability of the FLNG unit in case of major disturbances. It has
also supported the Reliability, Availability and Maintainability (RAM) analysis by providing values for start-up
periods and partial productions. It finally highlighted few aspects of the control strategy and some
opportunities for optimisation to improve the control which are of real value to the project, considering that a
unit with stable operations, few trips and rapid start-up will offer higher annualised production and is
particularly advantageous for offshore operations where modifications and maintenance are more costly.
REFERENCES
[1] J. Contreras and J.M. Ferrer. Dynamic Simulation: a case study, Hydrocarbon Engineering, May 2005.
[2] J. Wu, J. Feng, S. Dasgupta and I. Keith. A realistic dynamic modeling approach to support LNG plant
compressor operations, LNG Journal, October 2007.
12