Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

MODU Part 7 E-July16

Download as pdf or txt
Download as pdf or txt
You are on page 1of 190

Part 7: Surveys

RULES FOR BUILDING AND CLASSING

MOBILE OFFSHORE DRILLING UNITS


2016
PART 7
SURVEYS

(Updated July 2016 see next page)

American Bureau of Shipping


Incorporated by Act of Legislature of
the State of New York 1862

2015 American Bureau of Shipping. All rights reserved.


ABS Plaza
16855 Northchase Drive
Houston, TX 77060 USA

Updates
July 2016 consolidation includes:
January 2016 version plus Notice No. 1

a n

o t

i c

1 6

Rule Change Notice (2016)


The effective date of each technical change since 1993 is shown in parenthesis at the end of the
subsection/paragraph titles within the text of each Part. Unless a particular date and month are shown, the
years in parentheses refer to the following effective dates:
(2000) and after
(1999)
(1998)
(1997)

1 January 2000 (and subsequent years)


12 May 1999
13 May 1998
19 May 1997

(1996)
(1995)
(1994)
(1993)

9 May 1996
15 May 1995
9 May 1994
11 May 1993

Listing by Effective Dates of Changes from the 2015 Rules


The reference date which is indicated in the parentheses following the title of the requirement in this Part is the date
that the requirement becomes effective [e.g., 7-1-4/41.5 Hydrostatic Tests of Shell Valves (2016) is to apply for
vessels undergoing survey on or after 1 January 2016].
EFFECTIVE DATE 1 January 2016 shown as (2016)
Part/Para. No.

Title/Subject

Status/Remarks

7-1-4/41.5

Hydrostatic Tests of Shell Valves

To align the requirements with 6-1-6/7.3.1 of the MODU Rules and


4-6-2/7.3.2 of the Steel Vessel Rules.

7-1-7/13.1

Installation of Loop-Seal and NonReturn Check Valve

To clarify the means to prevent the contamination of the non-hazardous


fluid system by the hazardous medium.

7-1-7/Figure 4

Typical Drain Connection

To clarify the means to prevent the contamination of the non-hazardous


fluid system by the hazardous medium.

7-1-9/9.1

Initial Jacking Test

To require climbing pinions be visually examined, as far as practical,


upon completion of jacking trials.

7-2-1/1.1

Chapter 2 Sections 1 through 11

To consolidate the survey requirements for MODU Habitability


notations in Part 7. To clarify that certain Rule requirements in the
MODU Rules are based on the Steel Vessel Rules.

7-2-1/17

Onboard Drawings and Manuals

To provide define the application of 7-2-1/17.

7-2-1/17.5
(New)

Survey Planning Document (SPD)

To require the Survey Planning Document to be mandatory.

7-2-1/19.9
(New)

Sea Trials and/or Stability Test

To include safety precautions to be taken during sea trials/stability test


to be conducted on an existing unit that has completed a major
modification.

7-2-3/1.1

Plan for UWILD

To clarify that all UWILD plans must be agreed by the ACS and later
discussed during the pre-planning meeting with attending Surveyor.

7-2-3/1.5

Survey Planning Document (SPD)

To clarify the requirements for the Survey Planning Document.

7-2-4/3.5
(Deleted)

Preventative Maintenance Techniques

To remove requirements superseded by new Subsection 7-2-4/5.

7-2-4/5
(New)

Annual Survey Preventative


Maintenance Program (PMP)

To clarify Annual Confirmation Survey of machinery enrolled into


PMP.

7-2-4/7

Annual Survey Thrusters for APS


or PAS Notations

To clarify and separate requirements for units classed with APS and
PAS notations.

7-2-4/9
(New)

Annual Survey Dynamic


Positioning Systems

To clarify and separate requirements for units classed with DPS


notation.

7-2-4/Table 1
(New)

Thruster Power System

To show Rule requirements to be verified by attending Surveyors.

7-2-4/Table 2
(New)

Power Distribution System

To show Rule requirements to be verified by attending Surveyors.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

iii

Part/Para. No.

Title/Subject

Status/Remarks

7-2-4/Table 3
(New)

System Performance

To show Rule requirements to be verified by attending Surveyors.

7-2-4/Table 4
(New)

Additional Alarms and Instruments


for DPS-2 and DPS-3

To show Rule requirements to be verified by attending Surveyors.

7-2-5/1.5

Nondestructive Testing (NDT)

To clarify the requirements.

7-2-5/1.13
(New)

Alternatives

To explain that certain alternative techniques may be used during SPS,


however, they must be pre-agreed by the offshore ACS office before
they are applied.

7-2-5/5.5.3

Nondestructive Testing (NDT)

To remove inadvertently retained requirement.

7-2-5/7.3.1

General Visual Inspection (GVI)

To clarify the requirements.

7-2-5/7.5.3

Nondestructive Testing (NDT)

To clarify the requirements.

7-2-5/15

Thrusters and Dynamic Positioning


Systems

To reflect similar changes made to the wording of Annual Surveys


that cover various notations.

7-2-6/Table 1

Examination of Mat or Spud Cans


during Drydocking Survey

To add note regarding internal examination of mats.

7-2-6/3

Underwater Inspection in Lieu of


Drydocking (UWILD)

To clarify that all UWILD plans must be agreed by the ACS and later
discussed during the pre-planning meeting with attending Surveyor.

7-2-6/3.11

Alternatives

To explain typical alternative techniques which may be used during


UWILD, in particular, the use of ROVs for swim-by (general exam)
during UWILD.

7-2-11
(New)

Crew Habitability

To consolidate the survey requirements for MODU Habitability


notations in Part 7. To clarify that certain Rule requirements in the
MODU Rules are based on the Steel Vessel Rules.

7-2-A2

Survey of Portable Modules

To remove sections that are proposed to be shown in 6-1-2/11 and to


indicate reference to survey requirements for portable accommodation
modules.

7-2-A4
(New)

Preventative Maintenance Program


(PMP)

To specify requirements for PMP for MODUs.

7-2-A5
(New)

Reliability Centered Maintenance


(RCM)

To separate the requirements for RCM from the requirements of PM


and CM plans for obtaining the PMP notation.

Listing by Effective Dates of Changes from the 2016 Rules


Notice No. 1 (effective on 1 July 2016) to the 2016 Rules, is summarized below.
EFFECTIVE DATE 1 July 2016 shown as (1 July 2016)
Part/Para. No.
Appendix 7-2-A1

iv

Title/Subject
Lay-up and Reactivation of Laid-up
Mobile Offshore Drilling Units

Status/Remarks
To refer to the ABS Guide for Lay-up and Reactivation of Mobile
Offshore Drilling Units, which updates the requirements for lay-up
and reactivation with more descriptive life cycle states in regards to
layup on the survey status. (Incorporates Notice No. 1)

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

PART

Table of Contents

Surveys
CONTENTS
CHAPTER 1

Surveys During Construction ............................................................... 1


Section 1
General ................................................................................ 11
Section 2
Surveys at Builders Yard Hull Structure and Outfitting .... 13
Section 3
Surveys at Builders Yard Machinery, Piping, Pressure
Vessels, and Outfitting ......................................................... 25
Section 4
Surveys at Builders Yard Mechanical and Piping
Systems ............................................................................... 37
Section 5
Surveys at Builders Yard Electrical Cables and
Equipment ............................................................................ 47
Section 6
Surveys at Builders Yard Electrical Systems ................... 59
Section 7
Surveys at Builders Yard Hazardous Areas .................... 72
Section 8
Surveys at Builders Yard Fire and Safety ........................ 80
Section 9
Surveys at Builders Yard Sea Trial .................................. 90
Appendix 1
Appendix 2

CHAPTER 2

Mooring Equipment and Systems ........................................ 98


Surveys of Computers for Stability Calculations ................ 100

Surveys After Construction............................................................... 102


Conditions for Surveys After Construction ......................... 109
Survey Intervals ................................................................. 118
Survey Pre-planning .......................................................... 121
Annual Surveys .................................................................. 123
Special Periodical Surveys ................................................ 130
Drydocking Surveys or Equivalent ..................................... 157
Specific Survey on Self-Elevating Units After Ocean
Transit Tow ........................................................................ 162
Section 8
Tail Shaft Surveys .............................................................. 163
Section 9
Boiler Surveys .................................................................... 164
Section 10
Automatic and Remote-control Systems ........................... 165
Section 11
Crew Habitability ................................................................ 166
Section 1
Section 2
Section 3
Section 4
Section 5
Section 6
Section 7

Appendix 1

Lay-up and Reactivation of Laid-up Mobile Offshore


Drilling Units ....................................................................... 168

Appendix 2
Appendix 3

Survey of Portable Modules ............................................... 169


Modification of a Self-Elevating Drilling Unit to Become
Site-Specific Fixed Offshore Installation ............................ 171

Appendix 4
Appendix 5

Preventative Maintenance Program (PMP) ....................... 173


Reliability Centered Maintenance (RCM) .......................... 182

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

This Page Intentionally Left Blank

PART

Chapter 1: Surveys During Construction

CHAPTER

Surveys During Construction (2012)

CONTENTS
SECTION 1

General .................................................................................................. 11
1
General ............................................................................................. 11
3
Survey at Builders Yard ................................................................... 11
5
Certification and Classification .......................................................... 12

SECTION 2

5.1

Validity of an Interim Class Certificate (ICC) ................................. 12

5.3

Certification of Incomplete Drilling Units ........................................ 12

Onboard Drawings and Manuals ...................................................... 12

Surveys at Builders Yard Hull Structure and Outfitting ................ 13


1
General ............................................................................................. 13
3
Survey of Hull Structure and Outfitting ............................................. 13
4
Hull Construction Monitoring Program (HCMP) ................................ 14

4.1

Critical Structural Area (CSA) ........................................................ 14

4.3

Determination of CSA .................................................................... 14

4.5

Details of Hull Construction Monitoring Program ........................... 14

Material ............................................................................................. 15
5.1

Material Traceability ...................................................................... 15

5.3

Material Selection .......................................................................... 15

5.5

Steel Forming ................................................................................ 15

Qualification of Welders and Welding Specifications ....................... 15

Production Welding ........................................................................... 15

11

13

9.1

Thickness in Excess of 50 mm (2 in.) ............................................ 15

9.3

Inspection of Welds ....................................................................... 15

9.5

Fillet Welds .................................................................................... 16

Nondestructive Testing (NDT) .......................................................... 16


11.1

NDT of Column-Stabilized Drilling Units ........................................ 16

11.3

NDT of Self-Elevating Drilling Units ............................................... 16

11.5

NDT of Surface-Type Drilling Units ............................................... 17

11.7

Type and Extent of NDT ................................................................ 17

11.9

NDT Personnel and Records......................................................... 17

11.11

NDT Acceptance Standards .......................................................... 17

Corrosion Protection ......................................................................... 18


13.1

Performance Standards for Protective Coatings (PSPC) .............. 18

15

Survey of Load Line .......................................................................... 18

17

Survey of Spaces (Damage Stability Criteria) .................................. 18


17.1

Damage Conditions for Self-Elevating Units.................................. 19

17.3

Damage Conditions for Column-Stabilized Drilling Units ............... 19

17.5

Surface-Type Drilling Units ............................................................ 20

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

19

Weathertight/Watertight Integrity ......................................................21


19.1

Weathertight Integrity..................................................................... 21

19.3

Watertight Integrity......................................................................... 21

19.5

Penetrations .................................................................................. 21

21

Onboard Computers for Stability Calculations ..................................22

23

Hull Testing During Construction ......................................................22


23.1

General .......................................................................................... 22

23.3

Testing of Watertight Boundaries, Tanks and Sliding Doors .......... 22

23.5

Hydrostatic Testing ........................................................................ 22

23.7

Structural Testing........................................................................... 22

23.9

Air Testing ..................................................................................... 22

23.11

Hose Testing ................................................................................. 23

23.13

Flood Testing ................................................................................. 23

25

Construction Booklet (Construction Portfolio) ...................................24

27

Hull Inspection and Maintenance Program (HIMP) (Optional) .........24


27.1

SECTION 3

TABLE 1

Nondestructive Testing (NDT) of Steel Structure Welds ........18

TABLE 2

Testing of Boundaries, Compartments, Tanks, and


Spaces ....................................................................................23

FIGURE 1

Damage Conditions for Self-Elevating Units


(for details see 7-1-2/17.1) ......................................................19

FIGURE 2

Damage Conditions for Column-Stabilized Units


(for details see 7-1-2/17.3) ......................................................20

FIGURE 3

Damage Conditions for Surface-Type Units


(for details see 7-1-2/17.5) ......................................................20

Surveys at Builders Yard Machinery, Piping, Pressure


Vessels, and Outfitting......................................................................... 25
1
General .............................................................................................25
3
Survey of Machinery, Piping, Pressure Vessels, and other
Outfitting items ..................................................................................25
5
Materials and Operational Conditions ...............................................26

5.1

Material Tests and Inspection ........................................................ 26

5.3

Materials Containing Asbestos ...................................................... 26

5.5

Minimum Angle of Inclination for Machinery .................................. 26

5.7

Ambient Temperature for Machinery ............................................. 26

Internal Combustion Engines ............................................................26


7.1

Foundation ..................................................................................... 26

7.3

Warning Notices ............................................................................ 26

7.5

Governor Control ........................................................................... 26

7.7

Onboard Testing ............................................................................ 26

Piping ................................................................................................26
9.1

HIMP Notation (Optional) ............................................................... 24

Piping Standards ........................................................................... 27

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

11

13

15

17

19

Piping Installation Details .................................................................. 27


11.1

Pipe Bending ................................................................................. 28

11.3

Protection of Pipes ........................................................................ 28

11.5

Leading of Pipes near Switchboards, Motor Controllers and


Control Centers, Transformers, and all other Electrical
Equipment or Panels used for Essential Services ......................... 28

11.7

Provision for Expansion or Contraction Stresses .......................... 28

11.9

Pipe Joints ..................................................................................... 28

11.11

Mechanical Joints .......................................................................... 29

11.13

Bulkhead, Deck or Tank-Top Penetrations .................................... 29

11.15

Collision-Bulkhead Penetrations.................................................... 29

11.17

Sluice Valves and Cocks ............................................................... 29

11.19

Relief Valves ................................................................................. 29

11.21

Common Overboard Discharge ..................................................... 29

11.23

Remote Operation ......................................................................... 29

11.25

Instruments.................................................................................... 29

11.27

Flexible Hoses ............................................................................... 30

11.29

Control of Static Electricity............................................................. 30

11.31

Leakage Containment ................................................................... 30

Metallic and Plastic Pipes ................................................................. 30


13.1

Steel Pipes .................................................................................... 30

13.3

Copper and Brass Pipes................................................................ 30

13.5

Plastic Pipes .................................................................................. 31

Valves ............................................................................................... 32
15.1

Material of Valves .......................................................................... 32

15.3

Standard of Valves ........................................................................ 32

15.5

Construction of Valves .................................................................. 32

15.7

Rating and Identification of Valves ................................................ 32

Pipe Fittings ...................................................................................... 33


17.1

Material of Fittings ......................................................................... 33

17.3

Manufacturers Testing, Marking, and Certification of Pipe


Fittings ........................................................................................... 33

17.5

Installation of Pipe Fittings............................................................. 33

Flanges ............................................................................................. 33
19.1

21

23

25

Material of Flanges ........................................................................ 33

Fluid Power Cylinders ....................................................................... 33


21.1

Material of Fluid Power Cylinders .................................................. 33

21.3

Manufacturers Testing, Marking, and Certification of Fluid


Power Cylinders ............................................................................ 33

Sea Inlets and Overboard Discharges .............................................. 34


23.1

Connections .................................................................................. 34

23.3

Valves and Fittings ........................................................................ 34

23.5

Power Operated Valves................................................................. 34

Scuppers and Drains on Surface-Type and Self-Elevating Drilling


Units .................................................................................................. 35
25.1

Connections .................................................................................. 35

25.3

Valves and Fittings ........................................................................ 35

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

27

29

SECTION 4

27.1

Connections ................................................................................... 36

27.3

Valves and Fittings ........................................................................ 36

27.5

Not-Fully Welded Shell Penetrations of Non-Integral Keel


Coolers .......................................................................................... 36

Penetrations Through Watertight Boundaries...................................36


29.1

Ventilation Systems ....................................................................... 36

29.3

Internal Drain Systems .................................................................. 36

Surveys at Builders Yard Mechanical and Piping Systems .......... 37


1
General .............................................................................................37
3
Jacking and Associated Systems .....................................................37

11

13

3.1

Materials ........................................................................................ 37

3.3

Jacking Gear Motors and Motor Controllers .................................. 37

3.5

Hydraulic System ........................................................................... 37

3.7

Instrumentation and Other Components ........................................ 37

Tank Vents and Overflows ................................................................38


5.1

Progressive Flooding Consideration .............................................. 38

5.3

Height of Vent Pipes ...................................................................... 38

5.5

Size of Vent Pipes ......................................................................... 38

5.7

Termination of Vent Pipes ............................................................. 38

5.9

Overflow Pipes .............................................................................. 38

Sounding ...........................................................................................38
7.1

Sounding Pipes ............................................................................. 38

7.3

Gauge Glasses and Tank Level Indicators .................................... 38

Bilge System .....................................................................................39


9.1

Bilge System for Surface-Type Units ............................................. 39

9.3

Bilge System for Column-Stabilized Units and Self-Elevating


Units .............................................................................................. 39

9.5

Bilge Piping (All Units) ................................................................... 39

9.7

Bilge Pumps (All Units) .................................................................. 39

9.9

Size of Bilge Suctions .................................................................... 39

Ballast System ..................................................................................39


11.1

Ballast Piping (All Units) ................................................................ 39

11.3

Ballasting Systems for Column-Stabilized Units ............................ 40

Fuel Oil System .................................................................................40


13.1

Fuel-oil Transfer and Filling ........................................................... 40

13.3

Fuel-oil Service System for Boilers ................................................ 40

13.5

Fuel-oil Service System for Internal Combustion Engines ............. 40

13.7

Shutdown Arrangements for Fuel Oil System Valves .................... 41

15

Low Flash Point Fuels.......................................................................41

17

Lubricating-Oil Systems ....................................................................41

19

Cooler Installations External to the Hull ............................................36

17.1

Sight Flow Glasses ........................................................................ 41

17.3

Turbines and Reduction Gears ...................................................... 41

17.5

Internal Combustion Engines and Reduction Gears ...................... 41

17.7

Electrical Machinery....................................................................... 41

Hydraulic Systems ............................................................................41


ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

21

23

25

27

Fixed Oxygen-Acetylene Installations............................................... 42


21.1

Application ..................................................................................... 42

21.3

Gas Storage .................................................................................. 42

21.5

Piping System Components .......................................................... 42

Fuel Storage for Helicopter Facilities ................................................ 42


23.1

General.......................................................................................... 42

23.3

Spill Containment .......................................................................... 42

Starting-air Systems.......................................................................... 42
25.1

Design and Construction ............................................................... 42

25.3

Starting-air Capacity ...................................................................... 42

Cooling-Water Systems for Internal Combustion Engines ............... 43


27.1

General.......................................................................................... 43

27.3

Sea Suctions, Strainers and Circulating Water Pumps ................. 43

29

Exhaust System ................................................................................ 44

31

Valves in Atomizing Lines ................................................................. 44

33

Helicopter Deck Drainage Arrangements ......................................... 44

35

Boilers and Associated Piping .......................................................... 44

37

Steering Gear Piping......................................................................... 44

39

Gas Turbine Piping ........................................................................... 44

41

Piping System Pressure Test............................................................ 44


41.1

Metallic Piping System Pressure Tests ......................................... 44

41.3

Pneumatic Test in Lieu of Hydrostatic Test ................................... 45

41.5

Hydrostatic Tests of Shell Valves .................................................. 46

41.7

Plastic Piping System Pressure Tests ........................................... 46

41.9

Fixed Oxygen-Acetylene Installation Test ..................................... 46

TABLE 1

SECTION 5

Starting Air Minimum Number of Consecutive Starts ............. 43

Surveys at Builders Yard Electrical Cables and Equipment ........ 47


1
General ............................................................................................. 47
1.1

Definitions...................................................................................... 47

Survey of Electrical Cables and Equipment...................................... 47

Cable Installation .............................................................................. 48


5.1

General Considerations ................................................................. 48

5.3

Insulation Resistance for New Installation ..................................... 48

5.5

Protection for Electric-Magnetic Induction ..................................... 48

5.7

Joints and Sealing ......................................................................... 49

5.9

Support and Bending ..................................................................... 49

5.11

Cable Run in Bunches ................................................................... 50

5.13

Deck and Bulkhead Penetrations .................................................. 50

5.15

Mechanical Protection ................................................................... 51

5.17

Emergency and Essential Feeders ................................................ 51

5.19

Mineral Insulated Cables ............................................................... 51

5.21

Fiber Optic Cables ......................................................................... 51

5.23

Battery Room ................................................................................ 52

5.25

Paneling and Dome Fixtures ......................................................... 52

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

5.27

Sheathing and Structural Insulation ............................................... 52

5.29

Splicing of Electrical Cables .......................................................... 52

5.31

Splicing of Fiber Optic Cables ....................................................... 52

5.33

Cable Junction Box ........................................................................ 52

Equipment Installation and Arrangement..........................................53


7.1

Materials ........................................................................................ 53

7.3

Grounding Arrangements .............................................................. 53

7.5

Insulation Material and Operation Temperature ............................ 53

7.7

Degree of Protection for Enclosure ................................................ 53

7.9

Temperature Ratings ..................................................................... 53

7.11

Clearances and Creepage Distances ............................................ 53

7.13

Equipment Location, Protection and Accessibility ......................... 53

7.15

Generators ..................................................................................... 54

7.17

Main Service Motors ...................................................................... 54

7.19

Accumulator Batteries.................................................................... 54

7.21

Switchboards ................................................................................. 56

7.23

Distribution Boards ........................................................................ 56

7.25

Motor Controllers and Control Centers .......................................... 56

7.27

Resistors for Control Apparatus ..................................................... 57

7.29

Lighting Fixtures ............................................................................ 57

7.31

Heating Equipment ........................................................................ 57

7.33

Magnetic Compasses .................................................................... 57

7.35

Portable Equipment and Outlets .................................................... 57

7.37

Receptacles and Plugs of Different Ratings .................................. 57

7.39

Installation Requirements for Recovery from Dead Ship


Condition ....................................................................................... 57

Earthing .............................................................................................58
9.1

General .......................................................................................... 58

9.3

Permanent Equipment ................................................................... 58

9.5

Connections ................................................................................... 58

9.7

Portable Cords ............................................................................... 58

9.9

Cable Metallic Covering ................................................................. 58

TABLE 1

SECTION 6

Surveys at Builders Yard Electrical Systems ................................ 59


1
General .............................................................................................59
3
Main Source of Power.......................................................................59

Minimum Bending Radii of Cables ..........................................50

3.1

Power Supply by Generators ......................................................... 59

3.3

Generator Driven by Propulsion Unit ............................................. 60

3.5

Sizing of AC Generator .................................................................. 60

Emergency Source of Power ............................................................60


5.1

Boundary and Alternate Arrangements.......................................... 60

5.3

Emergency Power Supply ............................................................. 60

5.5

Emergency Sources ...................................................................... 62

5.7

Transitional Source of Power ......................................................... 62

5.9

Emergency Switchboard ................................................................ 63

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

5.11

Ballast Pumps ............................................................................... 63

5.13

Starting Arrangements for Emergency Generator Sets ................. 63

5.15

Alarms and Safeguards for Emergency Diesel Engines ................ 64

Distribution System ........................................................................... 64


7.1

Main Service Distribution System .................................................. 64

7.3

Hull Return System ....................................................................... 65

7.5

Earthed Distribution Systems ........................................................ 65

7.7

External or Shore Power Supply Connection ................................ 65

7.9

Harmonics ..................................................................................... 65

Circuit Protection System.................................................................. 65

11

Systems for Steering Gear Installed in Self-Propelled Units ............ 66

13

15

17

19

21

11.1

Power Supply Feeder .................................................................... 66

11.3

Protection for Steering Gear Motor Circuit..................................... 66

11.5

Emergency Power Supply ............................................................. 66

11.7

Controls, Instrumentation, and Alarms .......................................... 66

Lighting and Navigation Light Systems............................................. 66


13.1

Lighting System ............................................................................. 66

13.3

Navigation Light System ................................................................ 67

13.5

Obstruction Light System .............................................................. 67

Interior Communication Systems ...................................................... 67


15.1

Interior Communication Systems for All Units ............................... 67

15.3

Interior Communication Systems for Self-Propelled Units ............. 68

Manually Operated Alarms ............................................................... 68


17.1

General Alarm (GA) System .......................................................... 68

17.3

Engineers Alarm for Self-Propelled Units ..................................... 69

17.5

Refrigerated Space Alarm ............................................................. 69

17.7

Elevator Alarm ............................................................................... 69

Fire Protection and Fire Detection Systems ..................................... 69


19.1

Emergency Stop ............................................................................ 69

19.3

Fire Detection and Alarm System .................................................. 69

Electrical System Testing.................................................................. 70


21.1

Auxiliary Systems .......................................................................... 70

21.3

Generators .................................................................................... 70

21.5

Auxiliary Motors ............................................................................. 70

21.7

Main Switches and Breakers ......................................................... 70

21.9

Lighting System ............................................................................. 70

21.11

Voltage Drop ................................................................................. 70

21.13

Public Address (PA) & General Alarm (GA) Systems .................... 70

21.15

Fire and Gas (F&G) Detection System .......................................... 70

21.17

Electrical Equipment in Hazardous Areas ..................................... 70

21.19

Hazardous Area Doors, Ventilation and Alarms ............................ 71

21.21

Mud Pit Level Alarm ...................................................................... 71

21.23

Shutdown of Ventilation Fans and Openings................................. 71

21.25

Emergency Shutdown System ...................................................... 71

21.27

Helicopter Deck Lighting................................................................ 71

21.29

Navigation and Obstruction Lights ................................................. 71

TABLE 1

Emergency Diesel Engine Alarms and Shutdowns ............. 64

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

SECTION 7

Surveys at Builders Yard Hazardous Areas ................................... 72


1
General .............................................................................................72
1.1

SECTION 8

Openings and Penetrations Affecting the Extent of Hazardous


Zones ................................................................................................72
3.1

Openings ....................................................................................... 72

3.3

Penetrations .................................................................................. 73

Access and Ventilation Conditions Affecting the Extent of


Hazardous Zones ..............................................................................73
5.1

Enclosed Zone 1 or Zone 2 Space with Direct Access to any


Zone 1 Location (see 7-1-7/Figure 1) ............................................ 73

5.3

Enclosed Zone 2 or Non-Hazardous Space with Direct Access


to any Zone 2 Location (see 7-1-7/Figure 2) .................................. 74

5.5

Enclosed Non-Hazardous Space with Direct Access to any


Zone 1 Location (see 7-1-7/Figure 3) ............................................ 75

5.7

Doors and Hatches ........................................................................ 76

5.9

Ventilation ...................................................................................... 76

Machinery Installations .....................................................................77

Equipment and Installation in Hazardous Area.................................77


9.1

General .......................................................................................... 77

9.3

Certified-Safe Type and Pressurized Equipment and Systems ..... 77

9.5

Electrical Equipment used After Rig Shutdown ............................. 78

11

Paint Stores and Battery Lockers .....................................................78

13

Piping and Installation in Hazardous Area ........................................78


13.1

Installation of Loop-Seal and Non-Return Check Valve ................. 78

13.3

Extent of Hazardous Areas ............................................................ 79

13.5

Electrically Conductive Plastic Piping in Hazardous Areas ............ 79

FIGURE 1

Access to Zone 1 ....................................................................74

FIGURE 2

Access to Zone 2 ....................................................................75

FIGURE 3

Access from Enclosed Non-Hazardous Areas to Zone 1 .......76

FIGURE 4

Typical Drain Connection ........................................................78

Surveys at Builders Yard Fire and Safety ...................................... 80


1
General .............................................................................................80
1.1

Administration Certification ............................................................ 80

Surveys of Fire and Safety Features ................................................80

Passive Fire Protection Systems ......................................................81

Definitions ...................................................................................... 72

5.1

Structural Fire Protection ............................................................... 81

5.3

Protection of Accommodation Spaces, Service Spaces and


Control Stations ............................................................................. 82

Active Fire Protection Fixed Systems ............................................84


7.1

Fire Control Plan ............................................................................ 84

7.3

Fire Pumps .................................................................................... 84

7.5

Fire Main ........................................................................................ 84

7.7

Hydrants, Hoses, Nozzles and International Shore


Connection .................................................................................... 84

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

11

13

Active Fire Protection Additional Fixed Systems ........................... 85


9.1

Gas Smothering System................................................................ 85

9.3

Foam System ................................................................................ 86

9.5

Fixed Pressure Water Spraying Systems ...................................... 86

9.7

Protection of Helicopter Decks ...................................................... 86

9.9

Paint and Flammable Liquid Lockers ............................................ 87

Active Fire Protection Portable Fire Fighting Systems .................. 87


11.1

Portable Fire Extinguishers and Sand ........................................... 87

11.3

Firefighters Outfit .......................................................................... 87

Fire Detection and Alarm Systems ................................................... 87


13.1

15

Flammable Gas Detection and Alarm Systems ................................ 88


15.1

17

19

Hydrogen Sulfide (H2S) Detection and Alarm System ................... 88

Outfitting ............................................................................................ 88
17.1

Means of Escape ........................................................................... 88

17.3

Means of Access and Egress ........................................................ 88

17.5

Guards and Rails ........................................................................... 89

17.7

Emergency Control Stations .......................................................... 89

17.9

Arrangements in Machinery Space ............................................... 89

17.11

Segregation of Fuel Oil Purifiers .................................................... 89

17.13

Fire Precautions for Machinery Spaces ......................................... 89

Emergency Shutdown Arrangements ............................................... 89


19.1

SECTION 9

Testing of Alarm Systems.............................................................. 87

Arrangements and Services .......................................................... 89

Surveys at Builders Yard Sea Trial ................................................. 90


1
General ............................................................................................. 90
3
Stability Test ..................................................................................... 90
5
Safety ................................................................................................ 91
7
Hull Structure Testing ....................................................................... 91
9
Testing on Self-Elevating Drilling Units............................................. 91

11

9.1

Initial Jacking Test ......................................................................... 91

9.3

Moveable Cantilever and Skid Beam Testing ................................ 91

Sea Trial ............................................................................................ 91


11.1

Operation of Machinery and Piping Systems................................. 91

11.3

Ballast System ............................................................................... 92

11.5

Bilge System ................................................................................. 92

11.7

Electrical Installation for Drilling Unit Main Services ...................... 92

11.9

Communication Facilities............................................................... 92

11.11

Fire Extinguishing System ............................................................. 92

11.13

Main Source of Power ................................................................... 92

11.15

Emergency Source of Power ......................................................... 92

11.17

Distribution System ....................................................................... 93

11.19

Circuit Protection System .............................................................. 93

11.21

Lighting and Navigation Light Systems ......................................... 93

11.23

Public Address (PA) and General Alarm (GA) Systems ................ 93

11.25

Fire Protection and Fire Detection Systems .................................. 93

11.27

Gas Detection System ................................................................... 93

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

13

15

17

Sea Trial for Self-Propelled Drilling Units .........................................94


13.1

Full Power Trial .............................................................................. 94

13.3

Reduced Power Trial ..................................................................... 94

13.5

Operation of Machinery, Electrical Systems and Safety


Features ........................................................................................ 94

13.7

Dead-Ship Start ........................................................................... 94

13.9

Steering Gear Trial ........................................................................ 94

13.11

Interior Communication Systems for Self-Propelled Units ............. 96

Anchoring/Mooring Trial ....................................................................96


15.1

Anchoring/Mooring System Foundations ....................................... 96

15.3

Anchor Windlass Trials .................................................................. 96

Dynamic Positioning System (DPS) .................................................97


17.1

Failure Mode and Effect Analysis (FMEA) ..................................... 97

17.3

DP Trials ........................................................................................ 97

APPENDIX 1 Mooring Equipment and Systems ....................................................... 98


1
General .............................................................................................98
1.1

Anchoring (Temporary Mooring) Equipment .................................. 98

1.3

Position Mooring Equipment .......................................................... 98

1.5

Position Mooring Systems ............................................................. 98

Mooring System Foundations ...........................................................99

Mooring Trial .....................................................................................99


5.1

Anchoring (Temporary Mooring) Equipment .................................. 99

5.3

Position Mooring Equipment .......................................................... 99

5.5

Position Mooring System ............................................................... 99

APPENDIX 2 Surveys of Computers for Stability Calculations ............................ 100


1
General ...........................................................................................100
3
Functional Requirements ................................................................100
3.1

Calculation Program .................................................................... 100

3.3

Computer Data/Indicators ............................................................ 100

Operation Manual ...........................................................................101

Installation Testing ..........................................................................101


7.1

10

Installation Test Steps to be Performed ....................................... 101

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

PART

Section 1: General

CHAPTER

Surveys During Construction

SECTION

General

General
This Chapter pertains to surveys and testing to be carried out during construction of a mobile offshore
drilling unit at the builders yard/facility. The requirements for design review are given in Parts 3, 4, and 5
of these Rules.
The requirements for specific surveys are included in subsequent Sections of this Chapter. Subsequent Sections
are titled as follows:

Section 2

Surveys at Builders Yard Hull Structure and Outfitting

Section 3

Surveys at Builders Yard Machinery, Piping, Pressure Vessels, and Outfitting

Section 4

Surveys at Builders Yard Mechanical and Piping Systems

Section 5

Surveys at Builders Yard Electrical Cables and Equipment

Section 6

Surveys at Builders Yard Electrical Systems

Section 7

Surveys at Builders Yard Hazardous Areas

Section 8

Surveys at Builders Yard Fire and Safety

Section 9

Surveys at Builders Yard Sea Trial

Subsection 1 titled General of every Section provides a brief explanation regarding purpose of that
Section.
All Rule contents covered by subsequent Sections of this Chapter and that require visual examination,
verification, testing, etc. are to be carried out in presence of and to the satisfaction of the attending Surveyor.

Survey at Builders Yard


During construction of a drilling unit, the attending Surveyor is to have access to the builders yard to witness
construction and testing, as required by these Rules. The builder is to contact the attending Surveyor to make
necessary arrangements. If the attending Surveyor finds reason to recommend repairs or additional surveys,
notice will be immediately given to the builders representative so that appropriate action may be taken.
A Quality Control Program (QCP) is to be developed by the builder and submitted to the Surveyor for review
and agreement. Required hold points on the QCP that is to form the basis for all future surveys throughout
the contract period at the builders yard/facilities shall be agreed upon by the attending Surveyor. As a
minimum, all of the items enumerated in the following applicable Sections are to be covered by the QCP.
Surveyor shall assure that all tests and inspections specified in the QCP are satisfactorily carried out by a
competent person, and surveys shall be considered to supplement and not replace inspections that should
be carried out by the builder.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

11

Part
Chapter
Section

7
1
1

Surveys
Surveys During Construction
General

7-1-1

Certification and Classification


Conditions for Classification are defined in Part 1 of these Rules.
Upon satisfactory completion of all required design review, Surveyors visual examination, and
confirmation/witness of applicable tests, dock-side trials, stability test, and the sea trials, an Interim Class
Certificate (ICC) may be issued by the attending Surveyor, recommending the vessel be classed in
accordance with the classification and certification agreement contained in the signed Request For Class
(RFC) submitted to ABS and applied to the vessels classification.

5.1

Validity of an Interim Class Certificate (ICC)


Validity of the ICC will depend upon condition of the vessel at time of delivery, but it is not to exceed five
(5) months.
An ICC issued without any outstanding item will be valid for five months and will recommend review and
acceptance by the ABS Classification Committee. The classification package containing required
documents/records, reports and certificates will be reviewed by ABS and processed for classification of the
vessel.
An ICC issued with an outstanding item will be valid for less than five months and may be issued provided
it is authorized by ABS, including conditions of classification.

5.3

Certification of Incomplete Drilling Units


In general, where the construction or trials of the drilling unit is incomplete and the unit is delivered for
towage to another site for completion of all required examination and testing, and trials, an ICC will not be
issued.
Issuance of the ICC will depend upon condition of the vessel at time of delivery and to be authorized by
ABS. If issuance of an ICC is authorized, its validity may not exceed the period for drilling units single
direct voyage to the new site.

Onboard Drawings and Manuals


All reviewed and endorsed documents referenced in 7-2-1/17 of these Rules, required to be verified by the
Surveyor during surveys after construction, are to be placed onboard the drilling unit.

12

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

PART

Section 2: Surveys at Builders Yard Hull Structure and Outfitting

CHAPTER

Surveys During Construction

SECTION

Surveys at Builders Yard Hull Structure and


Outfitting

General
This Section pertains to surveys and testing to be carried out on hull structure and hull outfitting items
during construction of a mobile offshore drilling unit at builders yard/facility. The requirements for design
review are given Parts 3, 4, and 5 of these Rules.
For typical surveys required to be carried out, see subsequent Subsections of Section 7-1-2. All surveys
and testing is to be carried out in presence of and to the satisfaction of the attending Surveyor, prior to the
sea trial. Testing of the onboard computer (7-1-2/21), and hull structure testing such as hydrostatic testing
(7-1-2/23.5) and hull structural testing (7-1-2/23.7) of tanks may be carried out during the sea trial as
referenced in Section 7-1-9 of these Rules.

Survey of Hull Structure and Outfitting (2014)


All items of the hull structure and associated outfitting are to be surveyed during construction, outfitting
and at sea trial. Surveys are to be carried out in accordance with the ABS approved Hull Construction
Monitoring Program referenced in 7-1-2/4 of these Rules.
Welding and fabrication of structural components are to be in accordance with Sections 2-4-1 and 2-4-3 of
the ABS Rules for Materials and Welding (Part 2), as applicable.
The Quality Control Program (QCP) for the construction of a drilling unit is to at least include the following
items, as appropriate:
i)

Material Quality, Suitability, and Traceability

ii)

Welder Performance Qualification and associated Records

iii)

Welding Procedure Specifications and Welding Procedure Qualification Records

iv)

Preparation for welding including; forming, edge preparation, fit-up, alignment, cleanliness, and
tack welds

v)

Inspection of production welding including: environmental conditions, welding sequence, pre-heat,


post-heat, back gouging, fairing, soundness of welds, and necessary repair procedure

vi)

Nondestructive Testing (NDT)

vii)

Corrosion Control Systems

viii)

Compartment testing

Where structure is assembled in blocks or modules, the Surveyor is to inspect the fit-up, piping and electrical
connections, and to witness the required tests on the completed assembly in guidance with the QCP, and in
accordance with the approved plans and Rule/Guide requirements. The progress and suitability of structural
fit-up and joining of constructed/fabricated blocks/modules are to be to the satisfaction of the attending
Surveyor. All erection joints of hull structure are to be visually examined, proven tight, and the extent of
Nondestructive Testing (NDT) carried out is to be to the satisfaction of the attending Surveyor. For further
details of Surveyor attendance, see 7-1-2/5 through 7-1-2/27.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

13

Part
Chapter
Section

7
1
2

Surveys
Surveys During Construction
Surveys at Builders Yard Hull Structure and Outfitting

7-1-2

Hull Construction Monitoring Program (HCMP) (2014)


Hull structure of a mobile offshore drilling units to be classed using the ABS Rules for Building and
Classing Mobile Offshore Drilling Units is to be constructed in presence of an ABS Surveyor using an
ABS approved Hull Construction Monitoring Program (HCMP) as specified herein.
The structural strength criteria specified in the ABS Rules are used by designers to establish acceptable
scantlings in order that a vessel constructed to such standards and properly maintained will have adequate
durability and capability to resist the failure modes of yielding, buckling and fatigue.
The application of the MODU Rules, associated Guides and other review techniques to assess a design for
compliance with rule criteria also gives the designer and ABS the ability to identify areas that are considered
critical to satisfactory in-service performance.
Knowing that the actual structural performance is also a function of construction methods and standards, it
is prudent to identify Critical Structural Areas (CSA), particularly those approaching design limits, and
use appropriate specified construction quality standards and associated construction monitoring and
reporting methods to limit the risk of unsatisfactory in-service performance.

4.1

Critical Structural Area (CSA)


Critical Structural Areas are locations which have been identified from calculation to require monitoring or
from the service history of the subject unit or from similar sister units to be sensitive to cracking, buckling
or corrosion which would impair the structural integrity of the unit.
CSA may have a higher probability of failure during the life of the drilling unit compared to the surrounding
areas, even though they may have been modified in the interest of reducing such probability. The higher
probability of failure can be a result of stress concentrations, high stress levels and high stress ranges due
to loading patterns, structural discontinuities or a combination of these factors. In order to provide an even
greater probability of satisfactory in-service performance, the areas that are approaching the acceptance
criteria can be identified so that additional attention may be paid during fabrication.
The objective of heightened scrutiny of building tolerance and monitoring in way of the critical areas is to
minimize the effect of stress increases incurred as a result of the construction process. Improper alignment
and fabrication tolerances may be potentially influential in creating construction-related stress.

4.3

4.5

14

Determination of CSA
A CSA can be determined in a number of ways, including but not limited to:
i)

The results of engineering strength and fatigue analyses, such as specified in the Drillship Guide,
Finite Element Analysis or a Dynamic Loading Approach analysis, particularly for areas approaching
the allowable criteria.

ii)

The application of the Steel Vessel Rules, such as 3-1-2/15.3.

iii)

Details where fabrication is difficult, such as blind alignment, complexity of structural details and
shape, limited access, etc.

iv)

Input from owners, designers and/or shipyards based on previous in-service experience from
similar vessels, such as corrosion, wear and tear, etc.

Details of Hull Construction Monitoring Program


A HCMP for CSAs, prepared by the shipyard and submitted for approval by ABS engineering prior to the
start of hull fabrication, is to include following data/details:
i)

Structural drawings indicating the location of critical structural areas as identified by the ABS review

ii)

Construction standards and QCP (see 7-1-2/3) to be applied

iii)

Verification and recording procedures at each stage of construction, including any proposed additional
NDT other than what is that required by 7-1-2/11

iv)

Procedures for defect correction


ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

7
1
2

Surveys
Surveys During Construction
Surveys at Builders Yard Hull Structure and Outfitting

7-1-2

Material

5.1

Material Traceability
The builder is to maintain a system of material traceability to the satisfaction of the attending Surveyor.
Data as to place of origin and results of tests for materials shall be retained and are to be readily available
to the attending Surveyor upon request.

5.3

Material Selection
When selecting material grades for the classification of drilling units, minimum expected service temperature
and structural element category is considered. Various parts of drilling units are grouped according to their
material application categories, such as:
i)

Special Application Structure, which are normally used for most critical structural areas

ii)

Primary Application Structure, which are normally used for critical structural areas

iii)

Secondary Application Structure, which are normally used for least critical structural areas

The structural elements falling into these categories are described in 3-1-4/5.3 through 3-1-4/5.7.

5.5

Steel Forming
When forming changes base plate properties beyond acceptable limits, appropriate heat treatments are to
be carried out to reestablish required properties. Unless approved otherwise, the acceptable limits of the
reestablished properties should meet the minimums specified for the original material before forming.
Formed members with the forming dimensional tolerances required by the design, are to be examined.

Qualification of Welders and Welding Specifications


Welders, welding specifications and associated welding procedures are to be qualified in presence of and
to the satisfaction of the attending Surveyor. Welders and welding techniques are to be qualified in
accordance with Section 2-4-3 of the ABS Rules for Materials and Welding (Part 2).
For qualification of welders and welding procedures, only the applicable ABS Rules are to be used. Other
alternative standards will be subject to special consideration and require prior review and approval by
ABS.

Production Welding
Production welding and forming of steel is to be to the satisfaction of the Surveyor and in accordance with
Section 2-4-1 of the ABS Rules for Materials and Welding (Part 2)

9.1

Thickness in Excess of 50 mm (2 in.)


Special precautions with regard to joint preparation, preheat, welding sequence, heat input and interpass
temperature are to be taken for welding thick sections. Ultrasonic Testing (UT) to insure the absence of
injurious laminations may be required for material used where through-thickness (Z direction) properties
are important. Stress relieving, when specified, is to be carried out using an approved method.

9.3

Inspection of Welds
All welds are to be subject to visual inspection. Representative Nondestructive Testing (NDT) is to be
carried out to the satisfaction of the Surveyor. Such testing is to be carried out after all forming and post
weld heat treatment. Welds which are inaccessible or difficult to inspect in service may be subjected to
increased levels of NDT.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

15

Part
Chapter
Section

9.5

7
1
2

Surveys
Surveys During Construction
Surveys at Builders Yard Hull Structure and Outfitting

7-1-2

Fillet Welds
Completed welds are to be to the satisfaction of the attending Surveyor. The gaps between the faying surfaces
of members being joined should be kept to a minimum. Where the opening between members being joined
exceeds 2.0 mm (1/16 in.) and is not greater than 5 mm (3/16 in.), the weld leg size is to be increased by the
amount of the opening. Where the opening between members is greater than 5 mm (3/16 in.), corrective
procedures are to be specially approved by the Surveyor.
Where small fillets are used to attach heavy plates or sections, special precautions such as the use of
preheat or low-hydrogen electrodes or low-hydrogen welding processes may be required. When heavy
sections are attached to relatively light plating, the weld size may be required to be modified.

11

Nondestructive Testing (NDT)


Prior to commencement of any NDT, an NDT plan is to be submitted to the attending Surveyor for review
and acceptance, and is to conform to 2-4-1/5.17 of the ABS Rules for Materials and Welding (Part 2) and
7-1-2/9.3 of these Rules. NDT is to be carried out in accordance with ABS Guide for Nondestructive
Inspection of Hull Welds.
All NDT procedures are to be reviewed and accepted by the Surveyor before commencement of NDT.
Radiographic Testing (RT), Ultrasonic Testing (UT), Magnetic Particle Inspection (MPI), Penetrant
Testing (PT), Eddy Current (EC) or Alternating Current Field Measurement (ACFM) is to be carried out to
the satisfaction of the Surveyor. With the exception of RT, the Surveyor may require to witness the NDT
carried out by a qualified technician.

11.1

11.3

16

NDT of Column-Stabilized Drilling Units


Complete Joint Penetration (CJP) butt welds, tee welds and corner welds, in following areas of a columnstabilized drilling unit are to be specifically subjected to NDT during construction:
i)

Fabrication/erection joints of pontoons, columns, bracings, diagonals, and upper deck structure
(forming a box girder)

ii)

Columns to pontoons or lower hulls

iii)

Column to braces

iv)

Columns to upper hull

v)

Braces to upper hull

vi)

Brace-to-brace intersections

vii)

Gussets and brackets in way of the above joints

viii)

Internal continuation or back-up structure of the above joints

ix)

Any temporary access closures or inserts in main structures

NDT of Self-Elevating Drilling Units


Complete Joint Penetration (CJP) butt welds, tee welds and corner welds, in following areas of a selfelevating drilling unit are to be specifically subjected to NDT during construction:
i)

Lattice-type leg structure; including chords, braces, racks and rack attachments

ii)

Lattice-type leg gussets

iii)

Cylindrical-type leg shell structure

iv)

Fabrication/erection joints of spud-cans or mat

v)

Leg to spud-can or mat connections

vi)

Jackcase (Jackhouse) to deck connections

vii)

Any temporary access closures or inserts in main structures


ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

11.5

7
1
2

Surveys
Surveys During Construction
Surveys at Builders Yard Hull Structure and Outfitting

7-1-2

NDT of Surface-Type Drilling Units


Complete Joint Penetration (CJP) butt welds, tee welds and corner welds, within the midship 0.6L of a
surface-type drilling unit are to be specifically subjected to NDT during construction:
i)

Intersections of butts and seams in the sheer strakes, bilge strakes, deck stringer plates and keel
plates

ii)

Intersections of butts in and about moonpool corners on main deck and bottom platings

iii)

In the vicinity of breaks in the superstructure

iv)

Any temporary access closures or inserts in main structures

At the discretion of the Surveyor, NDT outside the midship 0.6L is to be carried out at random.

11.7

Type and Extent of NDT


The percentage of weld joint to be subjected to NDT and type of NDT carried out (e.g., Radiographic
Testing (RT), Ultrasonic Testing (UT), Magnetic Particle Inspection (MPI), Penetrant Testing (PT), Eddy
Current (EC) or Alternating Current Field Measurement (ACFM)) will depend on the design of the unit
and the calculated fatigue life of the joint.
Minimum extent of NDT to be carried out is shown in Table 1 of this Section. Volumetric NDT techniques
include RT and UT. Surface NDT techniques include MPI, PT, EC or AFCM.
Additional NDT may be requested by the Surveyor if the quality of fabrication or welds is not in accordance
with these Rules and applicable Standards.

11.9

NDT Personnel and Records


Builders NDT department is to be independent from other departments and not working for production.
All NDT records are to be reviewed by a Level 2 NDT technician and signed prior to review and
endorsement by the attending Surveyor.
All NDT records are to be properly maintained at least until the delivery of the drilling unit, and be
available to the Surveyor upon request anytime during construction.

11.11 NDT Acceptance Standards


Class A and Class B acceptance standards of the ABS Guide for Nondestructive Inspection of Hull Welds
will be applicable as follows:
i)

Class A acceptance criteria are to be used for NDT of welds of hull structure categorized as
Special Application Structure or Primary Application Structure in accordance with 3-1-4/5.

ii)

Class B acceptance criteria are to be used for NDT of welds of hull structure categorized as
Secondary Application Structure in accordance with 3-1-4/5 and other locations where Class A
acceptance criteria do not apply.

iii)

Modified procedures and acceptance criteria are to be specified to reflect the application when
radiographic or ultrasonic inspection is specified for other type connections such as partial penetration
and groove type Tee or corner welds.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

17

Part
Chapter
Section

7
1
2

Surveys
Surveys During Construction
Surveys at Builders Yard Hull Structure and Outfitting

7-1-2

TABLE 1
Nondestructive Testing* (NDT) of Steel Structure Welds (2012)
Structural Member

100% Volumetric NDT plus 100% Surface NDT all CJP welds, where welded plate
thickness is 5/16 inch (8.0 mm); and
10% MPI of all fillet welds, where plate thickness is 5/16 inch (8.0 mm).

Primary Application Structure


(Intermediate)

20% Volumetric NDT plus 100% Surface NDT of all CJP welds, where plate
thickness is 5/16 inch (8.0 mm); and
10% Surface NDT of all fillet welds, where plate thickness is 5/16 inch (8.0 mm).

Secondary Application Structure


(Least Critical)

Random Volumetric NDT of CJP welds and Surface NDT of fillet welds, only if
considered suspect by the attending Surveyor during construction.

13

Extent and Type of NDT

Special Application Structure


(Most Critical)

NDT procedures and acceptance criteria is to at least satisfy the ABS Guide for Nondestructive Inspection of Hull Welds.

Corrosion Protection
Unless otherwise approved, all steel work is to be suitably coated. Tanks or preload spaces intended for
salt water ballast are to have a corrosion-resistant hard coating on all internal surfaces.

13.1

Performance Standards for Protective Coatings (PSPC)


Where requested by the Owner, a unit with protective coatings which are verified by a Surveyor to be in
compliance with the ABS Guide for the Class Notation Coating Performance Standard (CPS) will be
assigned and distinguished in the Record with the class notation CPS.

15

Survey of Load Line


Every drilling unit is to have marks which designate the maximum permissible draft when the unit is in the
afloat condition. Such markings are to be placed at suitable visible locations on the structure, to the satisfaction
of ABS. On column-stabilized units, where practical, these marks are to be visible to the person in charge
of mooring, lowering or otherwise operating the unit.
The load lines are to be established under the terms of the International Convention on Load Lines. Where
minimum freeboards cannot be computed by the normal methods laid down by the Convention, they are to
be determined on the basis of compliance with the intact or damage stability requirements for afloat modes
of operation. The requirement that the draft of the unit not exceed the assigned load line may be considered
temporarily not applicable for bottom-supported units when raising, lowering or resting on the sea bed.
The requirements of the International Convention on Load Lines with respect to weathertightness and
watertightness of decks, superstructures, deckhouses, doors, hatchway covers, other openings, ventilators,
air pipes, scuppers, inlets and discharges, etc., are to be taken as a basis for all units in the afloat condition.
Upon satisfactory completion of the load line survey, an ABS LL-11D report is prepared by the Surveyor,
which is to be maintained onboard the unit. Upon satisfactory completion of the deadweight or inclining
experiment (as applicable) carried out in presence of the Surveyor, the builders stability report is to be
submitted to ABS for review and issuance of the load line assignment. The Surveyor is to verify load line
marking onboard the unit in accordance with the assignment.

17

Survey of Spaces (Damage Stability Criteria)


In assessing the damage stability of drilling units, as required by 3-3-2/1.3.2, the following extent of damage
is assumed. If damage of a lesser extent results in a more severe condition, such lesser extent is to be assumed.
During the survey of spaces, all piping, ventilating systems, trunks, etc., within the assumed damage area
are to be considered damaged. Positive means of closure are to be provided to preclude progressive
flooding of other intact spaces. Assumed damage conditions are as follows.

18

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

17.1

7
1
2

Surveys
Surveys During Construction
Surveys at Builders Yard Hull Structure and Outfitting

7-1-2

Damage Conditions for Self-Elevating Units


For self-elevating units, the following extent of damage is to be assumed to occur between effective watertight
bulkheads:
i)

Horizontal depth of penetration 1.5 m (5 ft) from side shell

ii)

Vertical extent of damage from the bottom plating upwards without limit. Where the unit is mat
supported, assumed damage penetration simultaneous to both the mat and upper hull need only be
considered when the lightest draft allows any part of the mat to fall within 1.5 m (5 ft) vertically of
the waterline, and the difference in horizontal dimension of the upper hull and mat is less than
1.5 m (5 ft) in the area under consideration.

The recessed ends and sides of the drilling slot need not be subject to consideration of horizontal penetration,
provided precautions are taken to prevent boats from entering the drilling slot when the unit is afloat (see
7-1-2/Figure 1).

FIGURE 1
Damage Conditions for Self-Elevating Units
(for details see 7-1-2/17.1) (2012)

5.0 feet
1.5 m

17.3

Damage Conditions for Column-Stabilized Drilling Units


For column-stabilized units, the following assumptions apply at the designated operating drafts:
i)

Only those columns on the periphery of the unit are to be assumed damaged with the damage
confined to the exposed outer portions of the columns.

ii)

Damage is assumed to occur for a vertical distance of 3 m (10 ft) at any level between 5.0 m (16.4
ft) above and 3.0 m (10 ft) below the draft under consideration. Where a Watertight flat is located
within this zone, the damage is to be assumed to have occurred in both compartments above and
below the Watertight flat in question.

iii)

No vertical bulkhead is to be assumed damaged, except where bulkheads are spaced closer than a
distance one-eighth of the column perimeter at the draft under consideration, measured at the
periphery, in which case, one or more of the bulkheads is to be considered as damaged.

iv)

Damage to the columns is to assume a horizontal depth of penetration of 1.5 m (5 ft).

v)

Lower hulls or footings are to be treated as damaged when operating at a light or transit condition
in the same manner as indicated in i) through iv).

If damage of a lesser extent results in a more severe final equilibrium condition, such less extent is to be
assumed (see 7-1-2/Figure 2).
On certain modified existing units, the columns are exposed to collision in the full periphery outside the
lines that connect the center of the main columns. In 7-1-2/Figure 2, showing a modified column-stabilized
drilling unit with additional sponsons and single columns, the columns on each side are not aligned. Therefore,
the line that connects the center column to the two end columns is not a straight line.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

19

Part
Chapter
Section

7
1
2

Surveys
Surveys During Construction
Surveys at Builders Yard Hull Structure and Outfitting

7-1-2

Another notable aspect is the effect of sponsons and single columns that are often added to existing units to
enhance their performance. Since the sponsons and single columns are not the main columns, they do not
form the boundary of the protected area and they are fully exposed to a collision (see 7-1-2/Figure 2).

FIGURE 2
Damage Conditions for Column-Stabilized Units
(for details see 7-1-2/17.3) (2012)
5.0 feet
1.5 m

5.0 feet
1.5 m

5.0 feet
1.5 m

16.4 feet
5.0 m
A

Sponson

B
Collision
Penetration
Zone

Single Column

5.0 feet
1.5 m

Lightship
Draft

17.5

10.0 feet
3m

Surface-Type Drilling Units


For surface-type drilling units, the following extent of damage is to be assumed to occur between effective
Watertight bulkheads (see 7-1-2/Figure 3):
i)

Horizontal depth of penetration of 1.5 m (5 ft)

ii)

Vertical extent of damage from the bottom shell upwards without limit

FIGURE 3
Damage Conditions for Surface-Type Units
(for details see 7-1-2/17.5) (2012)

5.0 feet
1.5 m
Collision
Penetration
Zone
5.0 feet
1.5 m

20

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

19

7
1
2

Surveys
Surveys During Construction
Surveys at Builders Yard Hull Structure and Outfitting

7-1-2

Weathertight/Watertight Integrity
During confirmatory survey of weathertight and watertight integrity of drilling units, following requirements
are to be applied and arrangements are to be to the satisfaction of the Surveyor.

19.1

Weathertight Integrity
Closing appliances are to be as prescribed by applicable load line requirements. Special consideration will be
given to openings in the upper deck of column-stabilized units. In all cases, external openings whose lower
edges are below the levels to which weathertight integrity is to be ensured, as shown by the diagrams to be
submitted in accordance with 3-1-2/1, are to have weathertight closing appliances. The referenced diagrams
may define different extents of weathertight integrity for each mode of operation afloat (see 3-1-1/17). Openings
fitted with appliances to ensure weathertight integrity are to be tested. For further details of testing, see 7-1-2/23.

19.3

Watertight Integrity
All internal and external openings whose lower edges are below the levels to which watertight integrity is
to be ensured, as shown by the diagrams submitted in accordance with 1-1-4/1 of the Supplement to the
ABS Rules for Conditions of Classification Offshore Units and Structures (Part 1), are to be fitted with
appliances to ensure watertight integrity.
19.3.1 Internal Openings Used for Access While Afloat
Internal openings fitted with appliances to ensure watertight integrity, which are used during
operation of the unit while afloat, are to comply with 3-3-2/5.3.1:

All such openings together with their remote controls, warning indicators, signs and their means
for closing is to be examined and tested.
19.3.2 Internal Openings Secured Closed While Afloat
Internal openings fitted with appliances to ensure watertight integrity, which are normally to be
secured closed while the unit is afloat, are to comply with 3-3-2/5.3.2:

All such openings together with their signs and their means for closing are to be examined.
19.3.3 External Openings Used While Afloat
External openings which are used during operation of the unit while afloat are to comply with
3-3-2/5.3.3:

All such openings together with their warning indicators, signs and their means for closing is to be
examined and tested to the satisfaction of the attending Surveyor.
19.3.4 External Openings Secured Closed While Afloat
External openings fitted with appliances to ensure watertight integrity, which are normally to be
secured closed while the unit is afloat, are to comply with the requirements of 7-1-2/19.3.2
Internal Openings Secured Closed While Afloat.

All such openings together with their signs and their means for closing are to be examined to the
satisfaction of the attending Surveyor.

19.5

Penetrations (1 July 2013)


19.5.1 General
All penetrations through watertight and weathertight boundaries are to comply with 3-3-2/5.5 and
are to be tested in presence of and to the satisfaction of the Surveyor. For watertight closure
requirements, see 4-2-2/27. For further details, see 7-1-2/5.
19.5.2 Watertight and Fire-rated Deck and Bulkhead Cable Penetrations
During installation of deck and bulkhead watertight and fire-rated cable penetrations, the attending
Surveyor is to confirm that the installer is familiar with and has access to the manufacturers
installation procedures for stuffing tubes, transit devices or pourable materials.

After installation, all watertight and fire-rated cable penetrations are to be visually examined.
Watertight cable penetrations are to be tested as required by 7-1-2/Table 2.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

21

Part
Chapter
Section

21

7
1
2

Surveys
Surveys During Construction
Surveys at Builders Yard Hull Structure and Outfitting

7-1-2

Onboard Computers for Stability Calculations


The use of onboard computers for stability calculations is not a requirement of class; it is the Owners
option. However, if stability software is installed onboard, it should cover all stability requirements applicable
to the drilling unit and is to be approved by ABS for compliance with the requirements of Appendix 3-3-A2,
Onboard Computers for Stability Calculations and satisfactory operation of the onboard computer is to
be verified by the Surveyor and reported upon.
For functional requirements, operating manual, and installation testing of onboard computers, see Appendix
7-1-A2 Survey of Computers for Stability Calculations

23

Hull Testing During Construction


Surveyors attendance is required, typically for the following purposes.

23.1

General
Compartments and spaces which are designed to be watertight, gas-tight or fire-tight are to be tested in presence
of a Surveyor by a procedure approved by the attending Surveyor. Any access doors, hatches, manholes or
closures of such compartments and spaces as well as any type of pipe or electrical penetration pieces through
such boundaries is to be completed and tested in similar manner to the satisfaction of the attending Surveyor.

23.3

Testing of Watertight Boundaries, Tanks and Sliding Doors


After all hatches and watertight doors are installed, penetrations including pipe connections are fitted, and
before cement work, ceiling or special coatings are applied, all watertight bulkheads and flats, as indicated
on the watertight compartmentation plan 3-1-2/1 and all tanks are to be tested and proven tight. Shop
primer may be applied prior to testing.
After installation and welding of its framing, all watertight sliding doors are to be visually examined to
confirm proper fit and operation. Feeler gauges are to be used to verify manufacturers installation tolerance
for maintaining required watertight integrity. Watertight sliding doors will then be subjected to hose testing.
Final examination is to include confirmation and operational testing of required warning signs and devices
respectively.

23.5

Hydrostatic Testing
Unless air testing has been accepted as an alternative, tanks are to be tested with a head of water to the
overflow or to the highest point to which the contents may rise under service conditions, whichever is higher.
This may be carried out either before or after the drilling unit is launched. Special coating may be applied
before hydrostatic testing, provided all welded connections are visually examined to the satisfaction of the
Surveyor before application of the special coating.

23.7

Structural Testing
In order to demonstrate structural adequacy, tank testing of new or unusual design may be required in
connection with the approval of the design. Required structural testing is to be carried out in accordance
with the design approval letter issued by the hull structural engineering office. The testing method and the
medium used for testing is to be as indicated in the ABS approval letter.

23.9

Air Testing
Prior to the application of special coating, air testing by an approved procedure may be accepted as a
supplement or alternative to hydrostatic testing. All boundary welds, erection joints and penetrations, including
pipe and cable connections, are to be examined in accordance with an approved procedure and under a
pressure differential not less than 0.15 bar (0.15 kgf/cm2, 2.2 psi) with a leak indicating solution.
It is recommended that the air pressure in the tank be raised to and maintained at 0.20 bar (0.20 kgf/cm2,
2.9 psi) for approximately one hour, with a minimum number of personnel around the tank, before being
lowered to the test pressure.
A U-tube with a height sufficient to hold a head of water corresponding to the required test pressure is to
be arranged. The cross sectional area of the U-tube is to be not less than that of the pipe supplying air. In
addition to the U-tube, a master gauge or other approved means is to be provided to verify the pressure.

22

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

7
1
2

Surveys
Surveys During Construction
Surveys at Builders Yard Hull Structure and Outfitting

7-1-2

Other effective methods of testing, such as compressed air fillet weld testing or vacuum testing, may be
considered, provided full particulars of the testing procedure is reviewed and agreed by the Surveyor.

23.11 Hose Testing (1 July 2013)


Hose testing is to be carried out under simultaneous inspection of both sides of the joint being tested. The
pressure in the hose is to be not less than 2 bar (2 kgf/cm2, 30 psi) during the test. The nozzle is to have
minimum inside diameter of 12 mm (0.5 in.) and located at a distance to the joint not exceeding 1.5 m (5 ft).
Hose testing is usually applied to access or closures of boundaries. Where hose testing may result in damage
to structural outfit, machinery or electrical equipment located close to testing area, chalk testing may be
carried out in lieu of hose testing, provided it is carried out to the satisfaction of the attending Surveyor.
Chalk testing is not an acceptable substitute for hose testing of watertight and weathertight doors, or other
similar closures located along the outside perimeter of the hull.
For cable penetrations, where hose testing is not practical because of possible damage to machinery, electrical
equipment insulation or outfitting items, other methods of testing may be considered upon submission of
full particulars to the attending Surveyor.

23.13 Flood Testing


Flood testing is to be carried out in tanks that are not enclosed at top. Tank is to be filled to its overflow
height, with same density of liquid to be used in the tank during normal drilling operations. Where flood
testing is impractical, hose testing may be carried out as an alternative method of testing.

TABLE 2
Testing of Boundaries, Compartments, Tanks, and Spaces (2012)
Compartment/Space to be Tested
CSDU Bracings, Horizontals, and
Diagonals (Void)
CSDU Chain Lockers & Chain Pipes
CSDU Watertight Column Spaces
Drill Ship Chain Lockers & Chain Pipes
Drill Ship Hawse Pipes
SEDU Mat Tanks (Buoyant)
SEDU Pre-Load Tanks
SEDU Spud-Cans (Buoyant)
Ballast Tanks
Base Oil Tanks
Drill Water Tanks

Type of
Testing

Hydrostatic Head or Pressure

Air
Flood Test

To the top of the chain pipe.

Air
Flood Test

To the top of the chain pipe.

Hose
Hydrostatic

To the height equal to deepest operational water depth of the SEDU.

Air
Hydrostatic

To the height equal to deepest operational water depth of the SEDU.

Air
Hydrostatic

To the height of the tank vent.

Air

Fuel Oil Tanks

Hydrostatic

To the height of the tank vent.

Gas-tight Doors

Air or Hose

Tightness of doors may be confirmed whilst the ventilation system


is running under normal operating conditions.

Independent Tanks

Hydrostatic

To the height of the tank vent.

Mud Pits

Flood Test

To the top of the overflow.

Oily Water Holding Tanks

Hydrostatic

To the height of the tank vent.

Potable/Fresh Water Tanks

Air

Voids

Air

Watertight Boundary Closures/Manholes

Hose

Watertight Doors

Hose

Watertight Sliding Doors

Hose

Weathertight Boundary Closures/Manholes

Hose

Weathertight Doors

Hose

See 7-1-2/23.3.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

23

Part
Chapter
Section

25

7
1
2

Surveys
Surveys During Construction
Surveys at Builders Yard Hull Structure and Outfitting

7-1-2

Construction Booklet (Construction Portfolio)


A Construction Booklet is to be prepared and be readily available onboard the drilling unit. The booklet is
to be reviewed by the Surveyor for completeness, and endorsed to indicate verification.
The construction booklet is to at least contain the following information/documents:

27

i)

ABS reviewed and stamped drawings showing the location and extent of different grades and
strengths of structural materials, together with a description of the material.

ii)

Welding Procedure Specifications primarily employed for welding of Special Application Structures
and Primary Application Structures, as defined in 3-1-4/5.

iii)

ABS reviewed and stamped drawings showing Special Application Structures and Primary
Application Structures, as defined in 3-1-4/5. This will enable proper identification and wastage
allowances of these structures, as required by 7-2-5/3, 7-2-5/5, or 7-2-5/7, during each Special
Periodical Survey carried out throughout the life of the drilling unit

iv)

ABS reviewed and stamped drawings showing all applicable critical structural areas. This will
enable proper record keeping of the results found during close-up survey and Nondestructive
Testing (NDT) of these areas, as required by 7-2-5/3, 7-2-5/5, or 7-2-5/7, during each Drydocking
(or UWILD) and Special Periodical Survey carried out throughout the life of the drilling unit.

Hull Inspection and Maintenance Program (HIMP) (Optional)


(2014) The Hull Construction Monitoring Program (HCMP), applied per 7-1-2/4 of these Rules and used
during construction or modification of the drilling unit, will be used for development of a Hull Inspection
and Maintenance Program (HIMP).
In order to satisfy 7-2-5/1.5.1, ABS software program Hull Inspection and Maintenance Program (HIMP)
may be used and incorporate all of the items mentioned in 7-1-2/25.
The Hull Inspection module of HIMP helps to track the condition of a vessels structure throughout its
service life. Designed for owners and operators, the program provides a vessel-specific hull maintenance
manual that outlines the compartments/spaces to inspect, critical areas to examine and identifies intervals
for inspection.
The Maintenance module of HIMP records schedules and manages the data pertaining to maintenance
work performed on a drilling unit by the crew or outside contractors. The system also provides a complete,
planned machinery and vessel compartment maintenance history.

27.1

24

HIMP Notation (Optional)


Drilling units enrolled in the Hull Inspection and Maintenance Program (HIMP), in accordance with the
ABS Guide for Hull Inspection and Maintenance Program, will receive the HIMP notation.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

PART

Section 3: Surveys at Builders Yard Machinery, Piping, Pressure Vessels, and Outfitting

CHAPTER

Surveys During Construction

SECTION

Surveys at Builders Yard Machinery, Piping,


Pressure Vessels, and Outfitting

General
This Section pertains to surveys and testing to be carried out on machinery, piping, pressure vessels, and
mechanical outfitting items during construction, installation and testing of mobile offshore drilling units at
builders yard/facility.
The documentation requirements for design review are given Parts 3, 4, and 5 of these Rules.
Surveys and testing of mechanical and piping systems are referenced in Section 7-1-4 of these Rules.
ABS Surveyor attendance is required, typically for the following purposes. All surveys and testing required
in subsequent Subsections of this Section are to be carried out in presence of and to the satisfaction of the
attending Surveyor, prior to the sea trial as referenced in Section 7-1-9 of these Rules.

Survey of Machinery, Piping, Pressure Vessels, and other Outfitting


items
In general, all items of machinery are to be surveyed during onboard installation and at sea trial. Welding
and fabrication of piping, pressure vessels, and structural or machinery outfitting items are to be in accordance
with Sections 2-4-2 and 2-4-4 of the ABS Rules for Materials and Welding (Part 2).
The quality control program for the construction of a drilling unit is to at least include the following items,
as appropriate:
i)

Material Quality and Traceability

ii)

Welder Performance Qualification and associated Records

iii)

Welding Procedure Specifications and Welding Procedure Qualification Records

iv)

Preparation for welding including; forming, edge preparation, fit-up, alignment, cleanliness, and
tack welds

v)

Survey of production welding including; environmental conditions, welding sequence, pre-heat,


post-heat, back gouging, fairing, soundness of welds, and necessary repair procedure

vi)

Nondestructive Testing (NDT)


Note:

NDT is to be carried out in accordance with ABS Guide for Nondestructive Inspection of Hull Welds. In
Class I and Class II piping systems, carbon and carbon-molybdenum steel piping for all diameters where
the thickness exceeds 9.5 mm (0.375 in.) and other alloy-steel piping 76 mm (3 in.) in diameter and over
regardless of thickness, welds are to be subjected to 100% Radiographic Testing (RT). All NDT records
are to be reviewed by a Level 2 NDT technician and signed prior to review and endorsement by the
attending Surveyor.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

25

Part
Chapter
Section

7
1
3

Surveys
Surveys During Construction
Surveys at Builders Yard Machinery, Piping, Pressure Vessels, and Outfitting

7-1-3

Materials and Operational Conditions

5.1

Material Tests and Inspection


Materials are to be made in accordance with the requirements in Chapter 3 of the ABS Rules for Materials
and Welding (Part 2) and 4-1-1/7.11, 4-2-1/9, 6-1-4/3 and 6-1-5/3 of these Rules, as applicable.
Copies in duplicate of the purchase orders for material requiring test and inspection at the mills or place of
manufacture are to be forwarded to ABS for the information of the Surveyor.

5.3

Materials Containing Asbestos


Installation of materials, which contain asbestos, is prohibited.

5.5

Minimum Angle of Inclination for Machinery


All machinery, components and systems essential for propulsion or for safe operation of the unit are to be
designed and fabricated to operate under the inclinations as indicated for each of the conditions listed in
4-1-1/Table 1.
Operational suitability of machinery per above requirements is to be verified by the installation Surveyor.

5.7

Ambient Temperature for Machinery


All machinery, components and systems essential for propulsion or for safe operation of the unit are to be
designed and fabricated to operate under the ambient temperature as indicated in 4-1-1/Table 2.
Operational suitability of machinery per above requirements is to be reconfirmed by the Surveyor.

Internal Combustion Engines


Onboard installation of internal combustion engines are to be to the satisfaction of the attending Surveyor.

7.1

Foundation
Satisfactory alignment of the engine skid structure with hull back-up/foundation structure is to be confirmed
before commencement of any dock-side testing of the engines.

7.3

Warning Notices
Suitable warning notices are to be attached in a conspicuous place on each engine and are to caution
against the opening of a hot crankcase for a specified period of time after shutdown based upon the size of
the engine, but not less than 10 minutes in any case. Such notice is also to warn against restarting an
overheated engine until the cause of overheating has been remedied.

7.5

Governor Control
All engines are to be fitted with governors which will prevent the engines from exceeding the rated speed
by more than 15%. Governor control is to be verified.
For generator sets, see 4-2-1/7.5.1, 4-2-3/7.5.1 and 4-2-4/7.5.1 of the Steel Vessel Rules.

7.7

Onboard Testing
Auxiliary and emergency engine/generator sets are to be tested prior to and during sea trial carried out in
accordance with an agreed procedure and in compliance with these Rules.

Piping
All piping is to be installed and tested in accordance with the Rules or recognized standards.
Satisfactory installation and operation of the piping systems are to be verified, as far as practicable, during
the sea trial.

26

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

7
1
3

Surveys
Surveys During Construction
Surveys at Builders Yard Machinery, Piping, Pressure Vessels, and Outfitting

7-1-3

Piping systems are divided into three classes (Class I, II and III) according to service, design pressure and
temperature, as indicated in 4-2-1/Table 1 of these Rules. Each class has specific requirements for joint
design, fabrication and testing.
All piping system is to be visually examined in accordance with ABS approved plans that consist of a
diagrammatic drawing of each system, including piping size, wall thickness, maximum working pressure
and material of piping as well as the type, size, pressure rating and material of valves and fittings.
Pipe weld details are to comply with Chapter 4 of the ABS Rules for Materials and Welding (Part 2).
Requirements for valves, fittings and flanges are based upon standards of the American National Standards
Institute (ANSI).

9.1

Piping Standards
A booklet of standard piping practices and details, including such items as bulkheads, deck and shell
penetrations, welding details including dimensions, pipe joining details, etc. reviewed by ABS is to be used
during survey of piping systems.

11

Piping Installation Details


Installation of piping onboard is to be in compliance with 4-2-1/11 of these Rules. Following piping details
are to be verified after piping system is installed:
i)

Pipe bending

ii)

Protection of pipes, valves and operating rods

iii)

Pipes installed near switchboards or MCCs

iv)

Pipe expansion joints

v)

Pipe joints

vi)

Mechanical joints

vii)

Pipes penetrating bulkheads and decks. Penetrations are to be subjected to tests similar to the
bulkhead or deck is tested to. Alternative testing of penetration welds with suitable NDT is to be
to the satisfaction of the Surveyor.

viii)

Pipes penetrating collision bulkhead of surface-type drilling units. Penetrations are to be subjected
to tests similar to the bulkhead is tested to.

ix)

Sluice valves and cocks on surface-type drilling units. Satisfactory operation of these valves or
cocks together with their indicators is to be confirmed.

x)

Relief valves fitted on Class I and Class II systems are to be tested. Relief valves fitted on Class
III systems may be tested if required by the Surveyor.

xi)

Common overboard discharge piping

xii)

Remote operation of valves

xiii)

Instrument wells, similar protection on fuel oil tanks, and valve arrangements allowing isolation
and removal of instrument on pressure sensing devices

xiv)

Hose assemblies

xv)

Control of static electricity, testing of resistance between ground points along the length, across
joints and from pipe to ground, and verification of bonding straps where used

xvi)

Leakage containment and drain piping

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

27

Part
Chapter
Section

7
1
3

Surveys
Surveys During Construction
Surveys at Builders Yard Machinery, Piping, Pressure Vessels, and Outfitting

7-1-3

11.1

Pipe Bending
Pipe bending is to be in accordance with 2-3-12/25 of the ABS Rules for Materials and Welding (Part 2).
Alternatively, bending in accordance with a recognized standard (e.g. ASME B31.1 Section 129.1 and 129.3)
or other approved specification to a radius that will result in a surface free of cracks and substantially free
of buckles may be acceptable.

11.3

Protection of Pipes
Pipes, valves and operating rods are to be effectively secured and adequately protected. These protective
arrangements are to be fitted so that they may be removed to enable examination of the pipes, valves and
operating rods protected.

11.5

Leading of Pipes near Switchboards, Motor Controllers and Control Centers,


Transformers, and all other Electrical Equipment or Panels used for Essential
Services
The leading of pipes in the vicinity of switchboards, motor controllers and control centers, transformers,
and all other electrical equipment or panels is to be avoided as far as possible. When such leads are necessary,
care is to be taken to fit no flanges or joints over or near these equipment or panels unless provision is
made to prevent any leakage from injuring the equipment.

11.7

Provision for Expansion or Contraction Stresses


Ample provision is to be made to take care of expansion or contraction stresses in pipes due to temperature
changes or working of the hull. Suitable provisions include, but are not limited to, piping bends, elbows,
offsets, changes in direction of the pipe routing or expansion joints. See 4-2-1/11.5 of these Rules.
Where expansion joints are used, the following are to be verified:

Pipe support. Adjoining pipes are to be suitably supported so that the expansion joints do not carry
any significant pipe weight.

Alignment. Expansion joints are not to be used to make up for piping misalignment errors. Misalignment
of an expansion joint reduces the rated movements and can induce severe stresses into the joint material,
thus causing reduced service life. Alignment is to be within tolerances specified by the expansion joint
manufacturer.

Anchoring. Expansion joints are to be installed as close as possible to an anchor point. Where an
anchoring system is not used, control rods may be installed on the expansion joint to prevent excessive
movements from occurring due to pressure thrust of the line.

Mechanical damage. Where necessary, expansion joints are to be protected against mechanical damage.

Accessible location. Expansion joints are to be installed in accessible locations to permit regular
inspection and/or periodic servicing.

Mating flange. Mating flanges are to be clean and usually of the flat faced type. When attaching
beaded end flange expansion joints to raised face flanges, the use of a ring gasket is permitted. Rubber
expansion joints with beaded end flange are not to be installed next to wafer type check or butterfly valves.
Serious damage to the rubber flange bead can result due to lack of flange surface and/or bolt connection.

11.7.1 Molded Expansion Joints


Where molded expansion joints are fitted, compliance with 4-2-1/11.7 is to be verified.
11.7.2 Metallic Bellow Type Expansion Joints
Where metallic bellow type expansion joints are fitted, compliance with 4-2-1/11.9 is to be verified.

11.9

28

Pipe Joints
Where pipe joints are used, compliance with 4-2-1/11.11 is to be verified.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

7
1
3

Surveys
Surveys During Construction
Surveys at Builders Yard Machinery, Piping, Pressure Vessels, and Outfitting

7-1-3

11.11 Mechanical Joints


Where mechanical joints are used, compliance with 4-2-1/11.13 is to be verified.
11.13 Bulkhead, Deck or Tank-Top Penetrations
Where pipes pass through bulkheads, decks or tank tops, the penetrations are to be made by approved methods
which will maintain the watertight, firetight or smoketight integrity of the bulkhead, deck or tank top. Bolted
connections are to have the bolts threaded through the plating and welded connections are to be welded on
both sides or with full-strength welds from one side.
All pipe penetrations are to be verified and tested as necessary.

11.15 Collision-Bulkhead Penetrations


Pipes piercing the collision bulkhead on ship type units are to be fitted with suitable valves operable from
above the bulkhead deck and the valve chest is to be secured at the bulkhead generally inside the forepeak.
Cast iron is not to be used for these valves. The use of nodular iron, also known as ductile iron or
spheroidal-graphite iron will be accepted, provided the material has an elongation not less than 12%.
Tanks forward of the collision bulkhead on surface-type units are not to be arranged for the carriage of oil
or other liquid substances that are flammable.
All pipe penetrations are to be verified and tested as necessary.

11.17 Sluice Valves and Cocks


No valve or cock for sluicing purposes is to be fitted on a collision bulkhead on ship type units. Sluice
valves or cocks may be fitted only on other watertight bulkheads when they are at all times accessible for
examination.
Where sluice valves or cocks are fitted per approved drawings, compliance with 4-2-1/11.19 is to be verified.

11.19 Relief Valves


All systems which may be exposed to pressures greater than that for which they are designed are to be
safeguarded by suitable relief valves or the equivalent, and pressure containers such as evaporators, heaters,
etc., which may be isolated from a protective device in the line are to have such devices either directly on
the shell or between the shell and the cut-off valve.
In pumping systems such as boiler feed, oil piping and fire main, where ordinarily relief valves are required at
the pump, such valves need not be fitted when the system is served only by centrifugal pumps so designed
that the pressure delivered cannot exceed that for which the piping is designed.
All relief valves are to be confirmed to have been tested prior to installation and marked/tagged accordingly.

11.21 Common Overboard Discharge


In general, various types of systems which discharge overboard are to be verified not to be interconnected
without special approval; that is, closed pumping systems, deck scuppers, soil lines or sanitary drains are not to
have a common overboard discharge.
11.23 Remote Operation
Where valves of piping systems are arranged for remote control and are power operated, a secondary means
for either local or remote-manual control is to be provided.
Remote operation function testing is to be carried out, preferably before sea trial.

11.25 Instruments
Where instruments fitted to measure temperature or pressure of the piping system, compliance with
4-2-1/11.27 is to be verified.
Proper calibration of all instruments is to be verified.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

29

Part
Chapter
Section

7
1
3

Surveys
Surveys During Construction
Surveys at Builders Yard Machinery, Piping, Pressure Vessels, and Outfitting

7-1-3

11.27 Flexible Hoses


Hose assemblies may be installed between two points where flexibility is required, but are not to be subject
to torsional deflection (twisting) under normal operating conditions.
Where flexible hoses are fitted, compliance with 4-2-1/11.29 is to be verified.

11.29 Control of Static Electricity


Piping systems that are routed through hazardous areas are to be suitably grounded either by welding or
bolting the pipes or their supports directly to the hull of the unit or through the use of bonding straps.
11.29.1 Ground Resistance
In general, the resistance tested between ground points along the length, across joints and from
pipe to ground is not to exceed 1 megohm.
11.29.2 Bonding Straps
Where bonding straps are used, they are to be clearly visible, protected from mechanical damage
and of a type not affected by corrosive products and paint. Bonding straps are required for tanks
and piping systems which are not permanently connected to the hull, including independent tanks,
tanks and piping systems which are electrically separated from the hull, and pipe connections
arranged for removal of spool pieces.

Components of alarms and level indicating devices located within tanks are to account for conductivity.

11.31 Leakage Containment


11.31.1 Oil Leakage
For areas where leakage may be expected such as oil burners, purifiers, drains and valves under
daily service tanks, etc., means of containing the leakage are to be provided together with adequate
drainage, and compliance with 4-2-1/11.33 is to be verified.
11.31.2 Boiler Flats
Where boilers are located in machinery spaces on tween decks and the boiler rooms are not
separated from the machinery space by watertight bulkheads, the tween decks are to be verified to
have containment coaming height of at least 200 mm (8 in.). The containment area may be drained
to the bilges.

All leakage containment arrangements are to be examined and verified to satisfy above requirements of
7-1-3/11.31, as applicable.

13

Metallic and Plastic Pipes


The use of all metallic and plastic pipes in classed piping systems is to be verified to be in compliance with
4-2-2/5 of these Rules.

13.1

Steel Pipes
Pipe thicknesses referred to as Standard or Extra Heavy is the equivalent of American National Standards
Institute Schedule 40 and Schedule 80 pipe up to a maximum wall thickness of 9.5 mm (0.375 in.) and
12.5 mm (0.5 in.), respectively.
Material specifications for acceptable steel pipes are referenced in Section 2-3-12 of the ABS Rules for
Materials and Welding (Part 2).
Application of steel pipes is to be in compliance with 4-2-2/5.1 of these Rules.

13.3

30

Copper and Brass Pipes


Application of copper and brass pipes are to be in compliance with 4-2-2/5.3 of these Rules.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

13.5

7
1
3

Surveys
Surveys During Construction
Surveys at Builders Yard Machinery, Piping, Pressure Vessels, and Outfitting

7-1-3

Plastic Pipes
For the purpose of these Rules, plastic means both thermoplastic and thermosetting plastic materials,
with or without reinforcement, such as polyvinyl chloride (PVC) and fiber reinforced plastics (FRP).
13.5.1 Limitations
Pipes and piping components made of thermoplastic or thermosetting plastic materials, with or without
reinforcement, may be used in piping systems referred to in 4-2-2/Table 2, subject to compliance
with requirements of 4-2-2/7.
13.5.2 Marking of Plastic Pipes and other Components
Plastic pipes and other components are to be verified to have permanent marking with identification
in accordance with a recognized standard. Identification is to include pressure ratings, the design
standard that the pipe or fitting is manufactured in accordance with, and the material with which
the pipe or fitting is made and the date of fabrication.
13.5.3 Installation of Plastic Pipes
Installation of plastic pipes is to satisfy the following requirements:

i)

Selection and spacing of pipe supports in shipboard systems are to be determined as a


function of allowable stresses and maximum deflection criteria. Support spacing is not to
be greater than the pipe manufacturers recommended spacing. Each support is to evenly
distribute the load of the pipe and its contents over the full width of the support. Measures
are to be taken to minimize wear of the pipes where they contact the supports. Heavy
components in the piping system such as valves and expansion joints are to be independently
supported. The supports are to allow for relative movement between the pipes and the
units structure.

ii)

Pipes are to be protected from mechanical damage, where necessary.

iii)

Where pipes are joined, the strength of fittings and joints is not to be less than that of the
piping they connect. Pipes may be joined using adhesive-bonded, welded, flanged or other
joints. Tightening of flanged or mechanically coupled joints is to be performed in accordance
with manufacturers instructions. Adhesives, when used for joint assembly, are to be suitable
for providing a permanent seal between the pipes and fittings throughout the temperature
and pressure range of the intended application. Joining techniques are to be in accordance
with manufacturers installation guidelines. Personnel performing these tasks are to be
qualified to the satisfaction of ABS, and each bonding procedure is to be qualified before
shipboard piping installation commences. Requirements for joint bonding procedures are
in 4-2-2/7.11.

iv)

Where electrically conductive pipe is required by 4-2-2/7.5.8, the resistance to earth


(ground) from any point in the system is not to exceed 1 megohm. Where used, earthing
wires or bonding straps are to be accessible for inspection placed in visible locations.

v)

Where plastic pipes are permitted in systems connected to the shell of the unit, the valves
and the pipe connection to the shell are to be metallic. The side shell valves are to be
arranged for remote control from outside of the space in which the valves are located. For
further details of the shell valve installation, their connections and material refer to 4-2-2/21.

vi)

Integrity of watertight bulkheads and decks is to be maintained where plastic pipes pass
through them. Where plastic pipes pass through A or B class divisions, arrangements
are to be made to ensure that the fire endurance is not impaired. If the bulkhead or deck is
also a fire division and destruction by fire of plastic pipes may cause inflow for liquid
from tank, a metallic shut-off valve operable from above the bulkhead deck is to be fitted
at the bulkhead or deck.

vii)

Fire protection coatings are to be applied on the joints, where necessary for meeting the
required fire endurance criteria in 4-2-2/7.5.6. Coating is not to be applied until the piping
system is satisfactorily pressure tested. The fire protection coatings are to be applied in
accordance with the manufacturers recommendations using a procedure approved in each
particular case.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

31

Part
Chapter
Section

15

7
1
3

Surveys
Surveys During Construction
Surveys at Builders Yard Machinery, Piping, Pressure Vessels, and Outfitting

7-1-3

Valves
Valves in piping systems are to satisfy the following requirements:

15.1

Material of Valves
Materials of valves are to meet 4-2-2/17 of these Rules. Manufacturers material certificates are to be
available for verification, as deemed necessary by the Surveyor.

15.3

Standard of Valves
Valves that are in compliance with a recognized standard are acceptable to ABS, subject to compliance
with 4-2-2/9.5. Valves that are not certified by the manufacturer in accordance with a recognized standard,
may be accepted when valve design is reviewed by ABS and accepted.

15.5

Construction of Valves
Construction of valves is to be verified as satisfying the following requirements:

15.7

32

i)

All valves are to close with a right hand (clockwise) motion of the hand wheel when facing the
end of the stem and are to be either of the rising stem type or fitted with an indicator to show
whether the valve is open or closed.

ii)

All valves of Class I and Class II piping systems having nominal diameters exceeding 50 mm (2 in.)
are to have bolted, pressure seal or breech lock bonnets and fanged or welding ends. Welding ends
are to be butt welding type, except that socket welding ends may be used for valves having
nominal diameters of 80 mm (3 in.) or less, up to and including 39.2 bar (40.0 kgf/cm2) pressure
rating class (ANSI 600 Class), and for valves having nominal diameters of 65 mm (2.5 in.) or less,
up to and including 98.1 bar (100 kgf/cm2) pressure rating class (ANSI 1500 Class).

iii)

All cast iron valves are to have bolted bonnets or are to be of the union bonnet type. For cast iron
valves of union bonnet type, the bonnet ring is to be of steel, bronze or malleable iron.

iv)

Stems, discs or disc faces, seats, and other wearing parts of valves are to be of corrosion-resistant
materials suitable for intended service.

v)

Valves are to be designed for the maximum pressure to which they will be subjected. The design
pressure is to be at least 3.4 bar (3.5 kgf/cm2, 50 psi), except that valves used in open systems,
such as vent and drain lines, and valves mounted on atmospheric tanks which are not part of the
tank suction or discharge piping (for example, level gauge and drain cocks and valves in inert gas
and vapor emission control systems) may be designed for a pressure below 3.4 bar (3.5 kgf/cm2,
50 psi), subject to the requirements of 4-2-2/9.1. Large fabricated ballast manifolds which connect
lines exceeding 200 mm (8 in.) nominal pipe size may be specially considered when the maximum
pressure to which they will be subjected does not exceed 1.7 bar (1.75 kgf/cm2, 25 psi).

vi)

All valves for Class I and Class II piping systems and valves intended for use in steam or oil lines
are to be constructed so that the stem is positively restrained from being screwed out of the body
(bonnet). Plug cocks, butterfly valves and valves employing resilient material will be subject to
special consideration.

vii)

Valve operating systems for all valves which cannot be manually operated are to be submitted to
ABS engineering for approval.

Rating and Identification of Valves


All valves are to be subjected by the manufacturer to a hydrostatic test at a pressure equal to that stipulated
by the American National Standards Institute (ANSI) or other recognized standard. They are to bear the
trademark of the manufacturer legibly stamped or cast on the exterior of the valve and also the primary
pressure rating at which the manufacturer guarantees the valve to meet the requirements of the standards.
This is to be verified during installation.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

17

7
1
3

Surveys
Surveys During Construction
Surveys at Builders Yard Machinery, Piping, Pressure Vessels, and Outfitting

7-1-3

Pipe Fittings
All fittings in Class I and Class II piping are to have flanged or welded ends in sizes over 89 mm O.D. (3 in.
N.P.S). Screwed fittings may be used in Class I and Class II piping systems, provided the temperature does
not exceed 496C (925F) and the pressure does not exceed the maximum pressure indicated in 4-2-2/11.1.
The type of fittings used on Class I, Class II and Class III piping systems are to satisfy 4-2-2/11. See
4-2-2/19 for fluid power cylinders.

17.1

Material of Fittings
Materials of fittings are to meet 4-2-2/17 of these Rules. Manufacturers material certificates are to be
available for verification, as deemed necessary by the Surveyor.

17.3

Manufacturers Testing, Marking, and Certification of Pipe Fittings


All fittings are to be subjected by the manufacturer to a hydrostatic test at a pressure equal to that stipulated
by the American National Standards Institute (ANSI) or other recognized standard. They are to bear the
trademark of the manufacturer legibly stamped or cast on the exterior of the fitting and also the primary
pressure rating at which the manufacturer guarantees the fitting to meet the requirements of the standards.
This is to be verified during installation.

17.5

Installation of Pipe Fittings


The installation of mechanical pipe joints, as covered by 4-2-2/11.1 and 4-2-2/11.5, is to be in accordance
with the manufacturers assembly instructions. Where special tools and gauges are required for installation
of the joints, these are to be specified and supplied as necessary by the manufacturer. These special tools
are to be kept onboard.

19

Flanges
Flanges are to be in compliance with a recognized national or international standard. The type of flanges
and method of attachment used on Class I, Class II and Class III piping systems are to be in compliance
with 4-2-2/15.

19.1

Material of Flanges
Materials of flanges are to meet 4-2-2/17 of these Rules. Manufacturers material certificates are to be
available for verification, as deemed necessary by the Surveyor.

21

Fluid Power Cylinders


Fluid power cylinders subject to pressures or temperatures greater than those indicated in 4-2-2/19 are to
be in compliance with a recognized standard for fluid power cylinders.

21.1

Material of Fluid Power Cylinders


Materials of fluid power cylinders are to meet 4-2-2/19 of these Rules. Manufacturers material certificates
are to be available for verification, as deemed necessary by the Surveyor.

21.3

Manufacturers Testing, Marking, and Certification of Fluid Power Cylinders


Acceptance will be based on the manufacturers certification of compliance and on verification of permanent
identification on each cylinder bearing the manufacturer's name or trademark, standard of compliance and
maximum allowable working pressure and temperature.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

33

Part
Chapter
Section

23

7
1
3

Surveys
Surveys During Construction
Surveys at Builders Yard Machinery, Piping, Pressure Vessels, and Outfitting

7-1-3

Sea Inlets and Overboard Discharges


All sea inlet and discharge valves are to be examined and tested, and all shell penetration welds are to be
subjected to surface (inboard and outboard) NDT and the welds hose tested, before the drilling unit is
launched.

23.1

Connections
Piping connections bolted to the shell plating are to have the bolt heads countersunk on the outside and the
bolts threaded through the plating. Where a reinforcing ring of sufficient thickness is riveted or welded to
the inside of the shell, studs may be used.
Threaded connections outboard of the shell valves are not considered an acceptable method of connecting
pipe to the shell.
Pipe connections fitted between the shell and the valves are to have a minimum wall thickness not less than
that specified in 4-2-2/21.3 and be as short as possible.

23.3

Valves and Fittings


Wafer-type valves are not to be used for any connections to the units shell unless specially approved.
All shell fittings and the valves required by 4-2-2/21.9 and 4-2-2/23 are to be of steel, bronze or other
approved ductile material. Valves of ordinary cast iron or similar material are not acceptable. The use of
nodular iron, also known as ductile iron or spheroidal-graphite iron, will be accepted, provided the material
has an elongation not less than 12%.
All pipes to which this subsection refers are to be of steel or other equivalent material, subject to special
approval.
Overboard discharges are to have spigots extending through the shell plate. Boiler and evaporator blow-off
overboard discharges are to have doubling plates or heavy inserts fitted. The spigot is to extend through the
doubling and the shell and the external doubling plate, when fitted, but the spigot need not project beyond
the outside surface of the unit.
Positive closing valves are to be fitted at the shell in inlet and discharging piping. The controls are to be
readily accessible and are to be provided with indicators showing whether the valves are open or closed.
In order to be considered readily accessible, the controls, during normal operating conditions, are to be:
i)

Located in a space normally entered without using tools,

ii)

Clear of or protected from obstructions, moving equipment and hot surfaces that prevent operation
or servicing, and

iii)

Within operators reach.

Materials readily rendered ineffective by heat are not to be used for connection to the shell where the
failure of the material in the event of a fire would give rise to danger of flooding.

23.5

Power Operated Valves


Arrangement and operation of all power operated valves are to be verified to be in compliance with below
requirements.
Power-operated valves are to meet the requirements in 4-2-1/11.25. Position indicating systems for seawater inlet and discharge valves are to be independent of the valves control systems. Additionally, seawater valves necessary for the operation of propulsion machinery or generation of power required in
4-3-2/3.1 are to be designed to remain in the last ordered position upon loss of control power.
Valves for sea-water inlets and discharges are also to be in accordance with the following, as applicable.
i)

34

Column-Stabilized Units: Sea-water inlets and discharges below the assigned load line are to be
provided with valves which can be remotely operated from an accessible position outside of the
space.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

25

7
1
3

Surveys
Surveys During Construction
Surveys at Builders Yard Machinery, Piping, Pressure Vessels, and Outfitting

7-1-3

ii)

Self-Elevating and Surface-Type Units: Sea-water inlets and discharges in spaces below the
assigned load line which are not intended to be normally manned are to be provided with valves
which can be remotely operated from an accessible position outside of the space. If the valves are
readily accessible, the spaces containing the inlets and discharges may be provided with bilge
alarms in lieu of remote operation of the valves.

iii)

Self-Elevating Units: Mud pit discharges are to be provided with valves which can be operated
from an accessible position. These valves are to be normally closed and a sign to this effect is to
be posted near the operating position. Non-return valves need not be provided.

Scuppers and Drains on Surface-Type and Self-Elevating Drilling


Units
All scuppers and drains are to be examined and tested, and all shell penetration welds are to be subjected to
surface (inboard and outboard) NDT and the welds hose tested, preferably before the drilling unit is
launched.

25.1

Connections
Discharges led through the shell either from spaces below the freeboard deck or from within
superstructures and deckhouses on the freeboard deck, fitted with doors complying with the requirements
of 3-2-11/5 of the Steel Vessel Rules, are to be fitted with efficient and accessible means for preventing
water from passing inboard.

25.3

Valves and Fittings


Normally, each separate discharge is to have one automatic non-return valve with a positive means of closing
it from a position above the freeboard deck, or bulkhead deck, whichever is higher. Alternatively, one nonreturn valve and one positive closing valve controlled from above the freeboard deck may be accepted.
Where the vertical distance from the load waterline to the inboard end of the discharge pipe exceeds 0.01L, the
discharge may have two automatic non-return valves without positive means of closing, provided that the
inboard valves are always accessible for examination under service conditions. The inboard valve is to be above
the deepest load waterline. If this is not practicable, then, provided a locally controlled stop valve is interposed
between the two non-return valves, the inboard valve need not be fitted above the deepest load waterline.
Where that vertical distance from the summer load waterline to the inboard end of the discharge pipe exceeds
0.02L, a single automatic non-return valve without positive means of closing may be accepted provided it
is located above the deepest load waterline. If this is impracticable, a locally operated positive closing
valve may be provided below the single non-return valve in which case the non-return valve need not be
located above the specified deepest load waterline. The means for operating the positive-action valve is to
be readily accessible and provided with an indicator showing whether the valve is open or closed.
Where sanitary discharges and scuppers lead overboard through the shell in way of machinery spaces, the
fitting to shell of a locally operated positive closing valve, together with a non-return valve inboard, will be
acceptable.
Scuppers and discharge pipes originating at any level and penetrating the shell either more than 450 mm
(17.5 in.) below the freeboard deck or less than 600 mm (23.5 in.) above the summer load waterline is to
be provided with a non-return valve at the shell. This valve, unless required by 4-2-2/23.1, may be omitted
if the piping has a wall thickness at least equal to the thickness of the shell plating or extra-heavy pipe (see
4-2-1/3.9), whichever is less.
Scuppers leading from superstructures or deckhouse not fitted with doors complying with the requirements
of Section 3-2-11/5 of the Steel Vessel Rules are to be led overboard.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

35

Part
Chapter
Section

27

7
1
3

Surveys
Surveys During Construction
Surveys at Builders Yard Machinery, Piping, Pressure Vessels, and Outfitting

7-1-3

Cooler Installations External to the Hull


Cooler installations are to be examined and tested as applicable, welds on integral cooler channels and
welds on non-integral watertight enclosures are to be subjected to surface (inboard and outboard) NDT or
hose tested as deemed necessary by the attending Surveyor, before the drilling unit is launched.

27.1

Connections
The inlet and discharge connections of external cooler installations are to be verified to be in accordance
with 4-2-2/21.1, 4-2-2/21.3, 4-2-2/21.5 and 4-2-2/21.9, except that wafer type valves will be acceptable.

27.3

Valves and Fittings


The positive closing valves required by 4-2-2/27.1 need not be provided if the keel (skin) cooler installation is
integral with the hull. To be considered integral with the hull, the installation is to be constructed such that
channels are welded to the hull with the hull structure forming part of the channel. The channel material is
to be at least of the same thickness and quality as that required for the hull, and the forward end of the
cooler is to be faired to the hull with a slope of not greater than 4 to 1. If positive closing valves are not
required at the shell, all flexible hoses or joints are to be positioned above the deepest load waterline or be
provided with an isolation valve.
Where fitted, valves and fittings are to be verified.

27.5

Not-Fully Welded Shell Penetrations of Non-Integral Keel Coolers


Where non-integral keel coolers are used, if the shell penetrations are not fully welded, the penetration is to
be encased in a watertight enclosure.

29

Penetrations Through Watertight Boundaries


All penetrations through watertight boundaries are to be tested to prove the integrity of the boundary. For
further details of the required testing, see 7-1-2/25.
At the boundaries required to be maintained watertight for damage stability, valves or watertight closures
may be required (see 3-3-2/5). Check valves and spring or gravity-actuated, non-return valves are not to be
considered effective in preventing progressive flooding.

29.1

Ventilation Systems
Non-watertight ducts passing through subdivision bulkheads and watertight ducts servicing more than one
watertight compartment or which are within the extent of damage are to be verified to be provided with
valves at the subdivision boundary. Valve operators are to be fitted with position indicators. Control of
valves is to be either from the ballast control room (or other normally manned spaces), or from a readily
accessible location which is above the calculated immersion line in the damaged condition (see 3-3-2/1.3).

29.3

Internal Drain Systems


Where internal drain systems are led to a separate, watertight compartment fitted with bilge suction, positive
closing valves are to be provided with position indicators. Control of valves is to be verified to be either
from the ballast control room (or other normally manned spaces), or from a readily accessible location
which is above the calculated immersion line in the damaged condition (see 3-3-2/1.3).
Where the installation of a remote valve operator is impractical, drain lines may be fitted with quick-acting,
self-closing valves at the boundary of the space which is equipped with bilge suction.

36

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

PART

Section 4: Surveys at Builders Yard Mechanical and Piping Systems

CHAPTER

Surveys During Construction

SECTION

Surveys at Builders Yard Mechanical and


Piping Systems

General
This Section pertains to surveys and testing to be carried out on mechanical and piping systems during
construction, installation and testing of mobile offshore drilling units at builders yard/facility.
The documentation requirements for design review are given Parts 3, 4, and 5 of these Rules.
Installation surveys and testing of machinery, piping, pressure vessels, and outfitting items are referenced
in Section 7-1-3 of these Rules.
ABS Surveyor attendance is required, typically for the following purposes. All surveys and testing is to be
carried out in presence of and to the satisfaction of the attending Surveyor, prior to the sea trial as referenced
in Section 7-1-9 of these Rules.

Jacking and Associated Systems


All jacking and associated systems of self-elevating drilling units, constructed and certified by the Surveyor
at the manufacturers plant, are to be installed in accordance with approved plans. For further details, see
6-1-9/25 of these Rules.
Installation of the jacking or other elevating system is to be verified. Jacking trial is to be carried out in
accordance with an agreed procedure. For further details of the jacking trial, see 7-1-9/9 of these Rules.

3.1

Materials
Material certificates, satisfying 6-1-9/9 of these Rules are to be made available to the attending Surveyor.

3.3

Jacking Gear Motors and Motor Controllers


Jacking gear motors and motor controllers is to satisfy 6-1-9/15 of these Rules and verified as being
satisfactorily installed.

3.5

Hydraulic System
Hydraulic cylinder material is to satisfy 6-1-9/17 of these Rules. The hydraulic system is to satisfy 6-1-9/17
of these Rules and verified as being satisfactorily installed.

3.7

Instrumentation and Other Components


Instrumentation and other components of the jacking system satisfying 6-1-9/13 and 6-1-9/19 of these
Rules respectively, and verified as being satisfactorily installed.
Operation of the jacking system from its control stations are to be verified after installation. This verification
is to include the operation of the system by emergency controls (emergency stop) from the jack house.
Satisfactory operation of effective communication system is to be verified.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

37

Part
Chapter
Section

7
1
4

Surveys
Surveys During Construction
Surveys at Builders Yard Mechanical and Piping Systems

7-1-4

Tank Vents and Overflows


Tank vents and overflows are to be examined and tested to confirm compliance with 4-2-3/1 of these Rules.
The required examination and testing is to be carried out to verify systems compliance with below specific
requirements, prior to the sea trial.
When air/hydrostatic testing of tanks, vents and overflow pipes are to be examined and subjected to
air/hydrostatic testing.

5.1

Progressive Flooding Consideration


Tank vents and overflows are to terminate above the extent of water-tight integrity. Those terminating
within the extent of weather-tight integrity are to be fitted with automatic means of closure such as a ball
check valve or equivalent.
Location of tank vents and overflows are to prevent progressive flooding and to satisfy 4-2-3/1.3 of these
Rules, and verified as being satisfactorily installed.
Progressive flooding through tank vents and overflows, regardless of the means of closure, is to be
considered when tank vents and overflows from intact spaces terminate within a damaged compartment or
vice versa (see 7-1-2/19).

5.3

Height of Vent Pipes


Height of tank vents and overflows are to satisfy 4-2-3/1.5 of these Rules.

5.5

Size of Vent Pipes


Size of tank vents and overflows are to satisfy 4-2-3/1.7 of these Rules.

5.7

Termination of Vent Pipes


Termination of vents pipes is to satisfy 4-2-3/1.9 of these Rules.

5.9

Overflow Pipes
Arrangement and installation of overflow pipes and applicable alarms of overflow tanks are to satisfy
4-2-3/1.11 of these Rules.

Sounding
Sounding arrangements are to be examined and tested to confirm compliance with 4-2-3/3 of these Rules.
The required examination and testing is to be carried out to verify systems compliance with below specific
requirements, prior to the sea trial.
When air/hydrostatic testing of tanks/voids, sounding pipes are to be examined and subjected to air/hydrostatic
testing.

7.1

Sounding Pipes
Size, installation and termination arrangements of sounding pipes are to satisfy 4-2-3/3.3 of these Rules.

7.3

Gauge Glasses and Tank Level Indicators


Installation and closing arrangements of gauge glasses are to satisfy 4-2-3/3.5 of these Rules.
Where a level-indicating device or system is provided for determining the level in a tank containing
flammable or combustible liquid, they are also to satisfy 4-2-3/3.7 of these Rules.

38

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

7
1
4

Surveys
Surveys During Construction
Surveys at Builders Yard Mechanical and Piping Systems

7-1-4

Bilge System
Bilge system is to be examined and tested to confirm compliance with 4-2-4/1, 4-2-4/3, 4-2-4/5, 4-2-4/7,
and 4-2-4/9 of these Rules. The required examination and testing is to be carried out to verify systems
compliance with below specific requirements, prior to the sea trial.
Bilge system, together with its fitted alarms, is to be examined and tested prior to the sea trial.
Satisfactory operation of the bilge system together with its alarms is to be re-confirmed during the sea trial
(see Section 7-1-8).

9.1

Bilge System for Surface-Type Units


Minimum number of bilge pumps, arrangement of independent bilge suctions, and arrangement of direct
bilge suction on ship-type units are to satisfy 4-2-4/1 of these Rules.

9.3

Bilge System for Column-Stabilized Units and Self-Elevating Units


Bilge system arrangement of void compartments, chain lockers, and the bilge alarms fitted in propulsion
and pump rooms are to satisfy 4-2-4/3 of these Rules.

9.5

Bilge Piping (All Units)


Installation and arrangement of the piping, manifolds, cocks and valves, common-main-type bilge system,
strainers, gravity drains, and bilge suction from hazardous areas are to satisfy 4-2-4/5 of these Rules.
Bilge system piping is to be examined and tested.

9.7

Bilge Pumps (All Units)


Installation and arrangement of the bilge system pumps are to satisfy 4-2-4/7 of these Rules.
All bilge pumps, previously surveyed and certified by ABS at vendors facility, are to be installed and
tested prior to the sea trial.
Satisfactory operation of the bilge pumps together with bilge system alarms are to be re-confirmed during
the sea trial.

9.9

11

Size of Bilge Suctions


9.9.1

Surface-Type Units
Sizes of main and branch lines are to be verified in accordance with ABS reviewed P&ID
drawings and to comply with 4-2-4/9.1 of these Rules.

9.9.2

Column-Stabilized Units and Self-Elevating Units


Sizes of main and branch lines are to be verified in accordance with ABS reviewed P&ID
drawings and to comply with 4-2-4/9.3 of these Rules.

Ballast System
Examination and testing of the ballast manifolds is to be carried out to confirm compliance with below
specific requirements, prior to the sea trial.
Ballast control features are to be examined and tested to confirm compliance with below specific requirements,
prior to the sea trial. Satisfactory operation of the ballast control features is to be re-confirmed during the
sea trial.

11.1

Ballast Piping (All Units)


Installation and arrangement of the piping, manifolds, cocks and valves, and the controls for ballast tank
valves are to satisfy 4-2-4/11 of these Rules.
The arrangement of the ballast pumping system is to be such as to prevent the possibility of water or oil
passing into the machinery spaces, or from one compartment to another, whether from the sea, water
ballast or oil tanks. The ballast mains are to have separate control valves at the pumps.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

39

Part
Chapter
Section

11.3

7
1
4

Surveys
Surveys During Construction
Surveys at Builders Yard Mechanical and Piping Systems

7-1-4

Ballasting Systems for Column-Stabilized Units


Installation and arrangement of the piping, manifolds, pumps, and ballast control features are to satisfy
4-2-4/13 of these Rules.
The ballast system is to be designed and arranged such that the system can take suction from and de-ballast
any ballast tank under normal operating and transit conditions.
The system is to be capable of restoring the unit to a normal operating or transit draft and a level trim
condition, when subject separately to each of the following:
i)

The assumed damaged conditions as specified in 3-3-2/1.3.2(a) with any one pump inoperable.

ii)

The flooding specified in 3-3-2/1.3.2(b).

In addition, the system is to be capable of raising the unit, starting from a level trim condition at deepest
normal operating draft, either a distance of 4.6 m (15 ft) or to the severe storm draft, whichever distance is
greater, within three hours (calculations are to be submitted for review).
This capability test is to be carried out during the ballast trial.

13

Fuel Oil System


Arrangement of the system, piping, valves and fittings, oil-heating arrangements, and arrangement of fueloil purifiers are to satisfy 4-2-5/1 of these Rules.
Examination and testing of the fuel oil system together with its tanks, valves, fittings, heaters, and purifiers
(if fitted) is to be carried out to confirm compliance with below specific requirements, prior to the sea trial.
Satisfactory operation of the system is to be re-confirmed during the sea trial

13.1

Fuel-oil Transfer and Filling


Examination and testing of the fuel oil transfer and filling system together with its tanks, valves (including
their remote operation), fittings, and heaters, is to be carried out to confirm compliance with below specific
requirements, prior to the sea trial.
Satisfactory operation of the system is to be re-confirmed during the sea trial.
The fuel-oil pumping arrangements are to be distinct from the other pumping systems as far as practicable, and
the means provided for preventing dangerous interconnection in service are to be thoroughly effective.
Leakage detection (when heating coils are fitted), piping in oil tanks, control valves or cocks, and valves
on oil tanks, are to satisfy 4-2-5/3 of these Rules.

13.3

Fuel-oil Service System for Boilers


Where boilers are located in machinery spaces, they are to be fitted with guard plates and drip pans in way
of furnaces. Boilers installed for the purpose of providing power for auxiliaries are to have at least two
means of feeding and two fuel-oil service pumps. The construction of all boilers is to comply with the
requirements of Section 4-4-1 and Appendix 4-4-1A1 of the Steel Vessel Rules.
Examination and testing of the fuel oil service system for boilers, is to be carried out to confirm
compliance with above specific requirements, prior to the sea trial.
Satisfactory operation of the service system is to be re-confirmed during the sea trial.

13.5

Fuel-oil Service System for Internal Combustion Engines


Examination and testing of the fuel oil service system for internal combustion engines, is to be carried out
to confirm compliance with below specific requirements, prior to the sea trial as referenced in Section 7-1-9
of these Rules.
Satisfactory operation of the service system is to be re-confirmed during the sea trial.
Minimum number and arrangement of fuel-oil pumps, oil tanks and drains for the fuel-oil system, fuel-oil
pressure piping, fuel-oil injection system, and piping between booster pump and injections pumps are to
satisfy 4-2-5/7 of these Rules.

40

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

7
1
4

Surveys
Surveys During Construction
Surveys at Builders Yard Mechanical and Piping Systems

7-1-4

13.7

Shutdown Arrangements for Fuel Oil System Valves


Every fuel oil suction pipe from a storage, settling or daily service tank which emanates at such a level that
it will be subjected to a static head of oil from the tank is to be fitted with a positive shutoff valve capable
of being closed manually from a readily accessible location outside of the space in which the valve is
located and tested (see 5-3-1/9).

15

Low Flash Point Fuels


Where used, examination of the low flash point fuels and associated arrangements is to be carried out to
confirm compliance with 4-2-5/9 of these Rules.

17

Lubricating-Oil Systems
Examination and testing of the lube-oil system is to be carried out to confirm compliance with below
specific requirements, prior to the sea trial.
The lubricating-oil piping is to be entirely separated from other piping systems. In addition, the requirements
of 4-2-5/1.1.2, 4-2-5/1.3, and 4-2-5/1.5 of these Rules are applicable.
The requirements in 4-2-5/3.9 are also applicable for lubricating-oil tanks. However, arrangements for
remotely closing the valve from a position outside of the compartment need not be provided if inadvertent
valve closure could result in damage to the running machinery due to lack of lubricating-oil. Where the
machinery is arranged for automatic shutdown upon loss of lubricating-oil, the valve required by 4-2-5/3.9 is
to be provided with means to close it from a readily accessible and safe location outside of the
compartment in which the valve is located.
For ship-type units, the lubricating systems are to be so arranged that they will function satisfactorily under
the conditions specified in 4-1-1/7 of these Rules.

17.1

Sight Flow Glasses


Sight flow glasses may be used in lubricating systems provided they are fire-resistant.

17.3

Turbines and Reduction Gears


For turbines and their reduction gears, see 4-6-6/9.7.1 and 4-6-6/9.3.1 of the Steel Vessel Rules.

17.5

Internal Combustion Engines and Reduction Gears


Lubricating-oil systems for internal-combustion engines and their reduction gears are to satisfy 4-2-6/1.7
of these Rules.

17.7

Electrical Machinery
For electrical machinery, see 4-3-3/3.3, 4-3-3/3.5.1 and 6-1-7/5.13 of these Rules.

19

Hydraulic Systems
Examination and testing of the hydraulic systems is to be carried out to confirm compliance with below
specific requirements, prior to the sea trial.
The arrangements for Class I and II hydraulic piping systems are to be in accordance with the requirements
of this section, except that hydraulic systems which form part of an independent device or equipment not
covered by these Rules and which does not form part of the units piping system (such as a crane) are not
covered by this Section, unless it is relevant to an optional notation or certification requested for the unit.
The requirements for fuel oil tanks contained in 4-2-5/1.1.2 and 4-2-5/1.3 of these Rules are also applicable
for tanks containing hydraulic fluid.
Arrangement and installation of valves, piping, pipe fittings, hoses, accumulators, fluid power cylinders,
and the segregation of the high pressure hydraulic units, are to satisfy 4-2-6/3.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

41

Part
Chapter
Section

21

7
1
4

Surveys
Surveys During Construction
Surveys at Builders Yard Mechanical and Piping Systems

7-1-4

Fixed Oxygen-Acetylene Installations


Where fitted, examination and testing of the fixed oxygen-acetylene installations is to be carried out to
confirm compliance with below specific requirements.

21.1

Application
Provisions of 4-2-6/5.3 of these Rules apply to fixed oxygen-acetylene installations that have two or more
cylinders of oxygen and acetylene, respectively. Spare cylinders of gases need not be counted for this purpose.
Provisions of 4-2-6/5.5 and 7-1-4/41.9, of these Rules, as applicable, are to be complied with for fixed
installations regardless of the number of cylinders.

21.3

Gas Storage
Storage of gas cylinders, ventilation of storage rooms, and electrical installation in the storage rooms are to
satisfy 4-2-6/5.3 of these Rules.

21.5

Piping System Components


Pipe and fittings, pressure relief devices, and system arrangement are to satisfy 4-2-6/5.5 of these Rules.
21.5.1 Gas Cylinders
Gas cylinders are to be designed, constructed and certified in accordance with the provisions of
4-4-1/1.11.4 of the Steel Vessel Rules. Each cylinder is to be fitted with a suitable pressure relief
device such as a fusible plug or a rupture disc.

The area within 3 m (10 ft) of the pressure relief device discharge outlet is to be regarded as a
hazardous area.

23

Fuel Storage for Helicopter Facilities


Examination of the fuel storage facilities for helicopters is to be carried out to confirm compliance with
below specific requirements.

23.1

General
Isolation of fixed fuel storage and transfer facilities, construction of fuel storage tanks, fuel storage tank
vents and valves, are to satisfy 4-2-6/7.1. See Section 7-1-7 of these Rules for survey of hazardous areas.

23.3

Spill Containment
Arrangements for spill containment and drainage are to satisfy 4-2-6/7.3 of these Rules.

25

Starting-air Systems
Examination and testing of the starting air system is to be carried out to confirm compliance with below
specific requirements, prior to the sea trial.

25.1

Design and Construction


The design and construction of all air containers and piping systems are to be in accordance with the
applicable requirements of Section 4-4-1 and Appendix 4-4-1A1 of the Steel Vessel Rules and 4-2-6/9.1 of
these Rules.

25.3

Starting-air Capacity
Units having internal combustion engines arranged for air starting are to be provided with at least two
starting-air containers of approximately equal size. The total capacity of the starting-air containers is to be
sufficient to provide, without recharging the containers, at least the number of consecutive starts stated
below. If other compressed air systems, such as control air, are supplied from starting-air containers, the
aggregate capacity of the containers is to be sufficient for continued operation of these systems after the air
necessary for the required number of starts has been used.

42

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

7
1
4

Surveys
Surveys During Construction
Surveys at Builders Yard Mechanical and Piping Systems

7-1-4

Minimum number of consecutive starts as applicable, and as required per following conditions defined in
7-1-4/25.3.1 through 7-1-4/25.3.3, is to be verified prior to the sea trial.
25.3.1 Diesel Propulsion
The minimum number of consecutive starts (total) required to be provided from the starting-air
containers is to be based upon the arrangement of the engines and shafting systems as indicated in
the following 7-1-4/Table 1.

TABLE 1
Starting Air Minimum Number of Consecutive Starts (2012)
Single Screw Unit

Multiple Screw Unit

One engine
coupled to shaft
directly or through
reduction gear

Two or more engines


coupled to shaft
through clutch and
reduction gear

One engine
coupled to each shaft
directly or through
reduction gear

Two or more engines


coupled to each shaft
through clutch and
reduction gear

Reversible Engines

12

16

16

16

Non-reversible Engines

For arrangements of engines and shafting systems which differ from those indicated in the table, the
capacity of the starting-air containers will be specially considered based on an equivalent number of
starts.
25.3.2 Diesel-electric Propulsion
The minimum number of consecutive starts required to be provided from the starting-air containers
is to be determined from the following equation.

S = 6 + G(G 1)
where
S = total number of consecutive starts
G = number of engines necessary to maintain sufficient electrical load to permit vessel
transit at full seagoing power and maneuvering. The value of G need not exceed 3.
25.3.3 Non Self-Propelled Units
The minimum number of consecutive starts required to be provided from the starting-air containers
is three (3) per auxiliary engine, but the total capacity of the starting-air containers dedicated to
the auxiliary engines need not exceed eight (8) consecutive starts.
25.3.4 Protective Devices for Starting-air Mains
Installation of protective devices is to satisfy 4-2-6/9.5.

27

Cooling-Water Systems for Internal Combustion Engines


Examination and testing of the cooling-water system is to be carried out to confirm compliance with below
specific requirements, prior to the sea trial.

27.1

General
Means are to be provided to ascertain the temperature of the circulating water at the return from each
engine and to indicate that the proper circulation is being maintained. Drain cocks are to be provided at the
lowest point of all jackets. For relief valves, see 4-2-1/11.21.

27.3

Sea Suctions, Strainers and Circulating Water Pumps


Sea suctions, strainers and circulating water pumps for the cooling-water system are to satisfy 4-2-6/11.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

43

Part
Chapter
Section

29

7
1
4

Surveys
Surveys During Construction
Surveys at Builders Yard Mechanical and Piping Systems

7-1-4

Exhaust System
Examination of the exhaust system is to be carried out to confirm compliance with 4-2-6/13, prior to the
sea trial.

31

Valves in Atomizing Lines


Where air or steam is used to atomize well bore fluids prior to flaring, a non-return valve is to be fitted in
the line. This valve is to be part of the permanently installed piping, readily accessible and as close as
possible to the burner boom. Examination of these valves is to be carried out.

33

Helicopter Deck Drainage Arrangements


Helicopter decks are to be arranged and provided with means to prevent collection of liquids and to prevent
liquids from spreading to or falling on other parts of the unit.
Examination of the helicopter deck drainage is to be carried out.

35

Boilers and Associated Piping


Boilers and their associated steam, exhaust and feed systems are to be in accordance with the applicable
requirements of Part 4, Chapters 4 and 6 of the Steel Vessel Rules.
Examination and testing of the boilers and associated piping system are to be carried out to confirm
compliance with above specific requirements, prior to the sea trial.

37

Steering Gear Piping


Piping systems associated with steering gear systems are to be in accordance with Section 4-3-4 of the
Steel Vessel Rules.
Examination and testing of the steering gear piping is to be carried out to confirm compliance with above
specific requirements, prior to the sea trial.

39

Gas Turbine Piping


Piping systems associated with gas turbines are to be in accordance with 4-2-3/9 of the Steel Vessel Rules.
Examination and testing of the gas turbine piping is to be carried out to confirm compliance with above
specific requirements, prior to the sea trial.

41

Piping System Pressure Test


All piping systems are to be examined and tested after installation.

41.1

Metallic Piping System Pressure Tests


In addition to the testing and inspection of materials, as required in Chapter 3 of the ABS Rules for Materials
and Welding (Part 2), the following tests on the fabricated piping are to be carried out after satisfactory
pipe bending and the attachment of flanges.
Small bore pipes and tubes of less than 15 mm outside diameter may be exempted from the required hydrostatic
tests.
41.1.1 Fuel-oil Service System
Pressure lines are to be tested before installation to 1.5 times the design pressure of the system, but
not less than 3.4 bar (3.5 kgf/cm2, 50 psi).

Record of satisfactory hydrostatic testing is to be available to the Surveyor.

44

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

7
1
4

Surveys
Surveys During Construction
Surveys at Builders Yard Mechanical and Piping Systems

7-1-4

41.1.2 Fuel-Oil Suction and Transfer System

Transfer systems and fuel-oil suction lines are to be tested before installation to 3.4 bar (3.5 kgf/cm2,
50 psi).
Record of satisfactory hydrostatic testing is to be available to the Surveyor.
41.1.3 Starting-Air System
Piping in starting-air systems is to be tested, preferably before installation, to 1.5 times the design
pressure of the system.

Record of satisfactory hydrostatic testing is to be available to the Surveyor. If the piping could not
be tested before installation, Surveyors witness of testing after installation is required.
41.1.4 Hydraulic Power System
After fabrication, the hydraulic power piping system or each piping component is to be tested to
1.5 times the design pressure.

Record of satisfactory hydrostatic testing is to be available to the Surveyor.


41.1.5 Specific Systems
The following piping systems are to be hydrostatically tested to 1.5P, but not less than 4 bar
(4.1 kgf/cm2, 58 psi), after installation:

i)

Gas and liquid fuel systems

ii)

Heating coils in tanks

41.1.6 High Pressure Industrial Piping


High pressure industrial piping serving systems other than the marine systems (such as high pressure
supply lines for drilling systems), are to be hydrostatically tested to 1.5 times the systems maximum
allowable working pressure.

Due to very high working pressure of such systems, it is preferred that an initial low pressure air
leak test is carried out. Upon satisfactory completion of the leak test, the hydrostatic testing of the
piping is to be carried out preferably using calibrated pressure gauges with pressure chart recording
capability, and piping maintained under the hydrostatic pressure for minimum of 15 minutes.
Necessary safety precaution is to be taken by the builder during the high-pressure hydrostatic
testing of these piping systems.
41.1.7 All Piping Systems
After installation, all piping is to be tested under working conditions. Where it is not possible to carry
out the required hydrostatic tests for all segments of pipes and integral fittings before installation,
the remaining segments, including the closing seams, may be so tested after installation. Or, where
it is intended to carry out all of the required hydrostatic tests after installation, such tests may be
conducted in conjunction with those required by this Paragraph. In both these respects, testing
procedures are to be submitted to the Surveyor for acceptance.

Testing of the piping systems under working condition may be carried out during the sea trial,
provided the piping installation was visually examined and found satisfactory prior to commencement
of the sea trial.

41.3

Pneumatic Test in Lieu of Hydrostatic Test


In general, a pneumatic test in lieu of a hydrostatic test is not permitted. Where it is impracticable to carry
out the required hydrostatic test, a pneumatic test may be considered. In such cases, the procedure for carrying
out the pneumatic test, having regard to safety of personnel, is to be submitted to the applicable ABS
Divisional Offshore Survey Department for special consideration.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

45

Part
Chapter
Section

7
1
4

Surveys
Surveys During Construction
Surveys at Builders Yard Mechanical and Piping Systems

7-1-4

41.5

Hydrostatic Tests of Shell Valves (2016)


All valves intended for installation on the side shell at or below the load waterline, including those at the
sea chests, are to be hydrostatically tested in the presence of a Surveyor before installation to a pressure of
at least 5 bar (5.1 kgf/cm2, 72.5 psi).

41.7

Plastic Piping System Pressure Tests


Plastic piping systems are to be subjected to a hydrostatic test on board after installation at a pressure of
not less than 1.5 times the design pressure.
For plastic piping required to be electrically conductive, earthing is to be checked and random resistance
testing is to be conducted.

41.9

Fixed Oxygen-Acetylene Installation Test


Piping on the oxygen high-pressure side is to be tested before installation to at least 207 bar (211 kgf/cm2,
300 psi) and the piping on the acetylene high-pressure side is to be tested to 1.5 times its design pressure.
Manufacturers record of satisfactory hydrostatic testing is to be available to the Surveyor.
The entire system is to be leak-tested with nitrogen or a suitable inert gas after installation. Care is to be
taken to cleanse the piping with suitable medium to remove oil, grease and dirt and to blow-through with
oil-free nitrogen or other suitable medium before putting the system in service. After installation, the
system is to be operationally tested under working conditions.

46

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

PART

Section 5: Surveys at Builders Yard Electrical Cables and Equipment

CHAPTER

Surveys During Construction

SECTION

Surveys at Builders Yard Electrical Cables and


Equipment

General
This Section pertains to surveys carried out on electrical cables and equipment during construction, installation
and testing of mobile offshore drilling units at builders yard/facility, including required onboard testing
and trial. The documentation requirements for design review are given Parts 3, 4, and 5 of these Rules.
ABS Surveyor attendance is required, typically for the following purposes. All surveys and testing is to be
carried out in presence of and to the satisfaction of the attending Surveyor, prior to the sea trial as
referenced in Section 7-1-9 of these Rules.

1.1

Definitions
For definition of various terms, see 4-3-1/3.

Survey of Electrical Cables and Equipment


All electrical cables and equipment is to be installed and tested in accordance with the Rules or recognized
standards.
ABS reviewed booklet of the standard wiring practices and details, including such items as cable supports,
earthing details, bulkhead and deck penetrations, cable joints and sealing, cable splicing, watertight and
explosion-proof connections to equipment, earthing and bonding connections, etc., as applicable, is to be
available to the attending Surveyor. Where cable penetration methods for A- or B-class decks or bulkheads
are shown, an evidence of approval by an Administration signatory to 1974 SOLAS as amended is also to
be available.
The quality control program for the construction of a drilling unit is to at least include the following items,
as appropriate:
i)

Material Quality and Traceability

ii)

Inspection of cable trays, electrical cables, cable supports, and cable fastenings.

iii)

Inspection of electrical cable penetrations through weather-tight, water-tight, fire-tight or gas-tight


boundaries. Inspection of Multi-Cable Transits (MCTs).

iv)

Megger Tests.

Where cable splices need to be used, they are to be of an approved type.


Exposed metal parts of electrical machines or equipment which are not intended to be live, but which are
liable under fault conditions to become live, are to be earthed (see 4-3-3/7).
Electrical equipment and wiring essential for operational purposes may be installed in hazardous areas (see
7-1-7/9). For certified safe-type equipment, see 7-1-7/9.3.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

47

Part
Chapter
Section

7
1
5

Surveys
Surveys During Construction
Surveys at Builders Yard Electrical Cables and Equipment

7-1-5

Cable Installation

5.1

General Considerations
Electric cables are to be installed in continuous lengths between terminations at equipment or in cable
junction boxes (see 4-3-3/5.25). However, approved splices will be permitted at interfaces of new construction
modules, when necessary to extend existing circuits for a drilling unit undergoing repair or alteration, and
in certain cases to provide for cables of exceptional length (see 4-3-3/5.21).
The cross-sectional areas of conductors are to be confirmed to be in accordance with approved drawings.
Cables and wiring are to be installed and supported in such a manner as to avoid chafing or other damage.
Cables are to be located with a view to avoiding, as far as practicable, spaces where excessive heat and
gases may be encountered; also, spaces where they may be exposed to damage, such as exposed sides of
deckhouses. Cables are not to be installed in the bilge area unless protected from bilge water.
Where cables are installed in a cable draw box and horizontal pipes or the equivalent is used for cable
protection, means of drainage are to be verified.
Cables serving systems above 1 kV are not to be bunched with cables serving systems of 1 kV and below.
Where paint or any other coating is systematically and intentionally applied on the electric cables, it is to
be established that the mechanical and fire performance properties of the cable are not adversely affected.
In this regard:
i)

Fire retardant property is to be confirmed to be in compliance with 4-3-4/7.1.2.

ii)

It is to be confirmed that the paint and the solvent used will not cause damages to the cable sheath
(e.g., cracking).

Overspray on cables or painted exterior cables are not subject to the requirements of this section.

5.3

Insulation Resistance for New Installation


Each power and each light circuit is to have an insulation resistance between conductors and between each
conductor and earth of not less than the following values.
Up to 5 amperes load

2 megohms

10 amperes load

1 megohm

25 amperes load

400,000 ohms

50 amperes load

250,000 ohms

100 amperes load

100,000 ohms

200 amperes load

50,000 ohms

Over 200 amperes load

25,000 ohms

If the above values are not obtained, any or all appliances connected to the circuit may be disconnected for
this test.

5.5

48

Protection for Electric-Magnetic Induction


Protection of cables is to be verified. The following cables are to be protected as required by 4-3-3/5.5 of
these Rules:
i)

Multiple conductor cables

ii)

Single conductor cables

iii)

Non-shielded signal cables

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

5.7

5.9

7
1
5

Surveys
Surveys During Construction
Surveys at Builders Yard Electrical Cables and Equipment

7-1-5

Joints and Sealing


Cables not having a moisture-resistant insulation are to be sealed against the admission of moisture by
methods such as taping in combination with insulating compound or sealing devices. Following are to be
verified during installation survey:
i)

Stresses on the cable are not to be transmitted to the conductors.

ii)

Terminations and joints in all conductors are to be so made as to retain the original electrical,
flame retarding and, where necessary, fire resisting properties of the cable.

iii)

Terminal boxes are to be secured in place and the moisture-resistant jacket is to extend through the
cable clamp.

iv)

Enclosures for outlets, switches and similar fittings are to be flame-resistant and moisture-resistant
and of adequate mechanical strength and rigidity to protect the contents and to prevent distortion
under all likely conditions of service (see 4-3-3/5.17.1 and 4-3-3/5.21).

Support and Bending


5.9.1

Support and Fixing


Where cables are fixed by means of clips, saddles or straps, they are to have a surface area so large
and shaped such that the cables remain tight without their coverings being damaged. Metal clips
may be screwed directly to deck or bulkhead, except on watertight bulkheads.

The support and fixation measures are to be verified to be in compliance with the following.
5.9.1(a) The distances between supports are to be suitably chosen according to the type of cable
and the probability of vibration, and are not to exceed 400 mm (16 in.). For a horizontal cable run
where the cables are laid on cable supports in the form of tray plates, separate support brackets or
hanger ladders, the spacing between the fixing points may be up to 900 mm (36 in.), provided that
there are supports with maximum spacing as specified above. This exemption does not apply to
cable runs along weather decks when the cable run is arranged so that the cables can be subjected
to forces by water washing over the deck.
Note:

When designing a cable support system for single-core cables, consideration is also to be given to the
effects of electrodynamic forces developing on the occurrence of a short-circuit.
The above-given distances between cable supports are not necessarily adequate for these cables. Further,
other recognized standards for cable support and fixing will be considered.

5.9.1(b) The supports and the corresponding accessories are to be robust and are to be of
corrosion-resistant material or suitably treated before erection to resist corrosion.
5.9.1(c) Cable clips or straps made from an approved material other than metal (such as polyamide,
PVC) may be used.
5.9.1(d) When cables are fixed by means of clips or straps referred to in 7-1-5/5.9.1(c) above and
these cables are not laid on top of horizontal cable trays or cable supports, suitable metal cable
clips or saddles are to be added at regular distances not exceeding 2 m (6.5 ft) in order to prevent
the release of cables during a fire. This also applies to the fixing of nonmetallic conduits or pipes.
Note:

Item 7-1-5/5.9.1(d) does not necessarily apply in the case of cable runs with only one or a few cables
with small diameters for the connection of a lighting fitting, alarm transducer, etc.

5.9.1(e) Non-metallic clips, saddles or straps, are to be flame retardant in accordance with IEC
Publication 60092-101.
5.9.2

Bending Radius
For bending radius requirements, see 7-1-5/Table 1 of these Rules.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

49

Part
Chapter
Section

7
1
5

Surveys
Surveys During Construction
Surveys at Builders Yard Electrical Cables and Equipment

7-1-5

TABLE 1
Minimum Bending Radii of Cables (2012)
Insulation

Cable construction
Outer covering

Over all diameter,


D

Minimum internal
bending radius

Thermoplastic or
thermosetting with
circular copper
conductor

Unarmored or unbraided

D 25 mm (1 in.)

4D

D > 25 mm

6D

Metal braid screened or armored

Any

6D

Metal wire or metal-tape armored or


metal-sheathed

Any

6D

Composite polyester/metal laminate


tape screened units or collective tape
screening

Any

8D

Thermoplastic or
thermosetting with
shaped copper
conductor

Any

Any

8D

Mineral

Hard metal-sheathed

Any

6D

5.9.3

Plastic Cable Trays and Protective Casings


Where flame retardant plastic cable trays or protective casings are used, following details are to be
verified in compliance with 4-3-3/5.9.3:

i)

Installation details

ii)

Safe working load of the trays and covers

iii)

Cables passing through hazardous areas

iv)

Type testing record of trays and casings

Cable trays and protective casings made of plastic materials are to be supplemented by metallic
fixing and straps such that, in the event of a fire, they and the cables affixed are prevented from falling
and causing an injury to personnel and/or an obstruction to any escape route. See 7-1-5/5.9.1(d).
Cable occupation ratio in protective casing. The sum of the total cross-sectional area of all cables
on the basis of their external diameter is not to exceed 40% of the internal cross-sectional area of
the protective casing. This does not apply to a single cable in a protective casing

5.11

Cable Run in Bunches


Where cables, which may be expected to operate simultaneously, are laid close together in a cable bunch in
such a way that there is an absence of free air circulation around them, a reduction factor is applied to the
current rating obtained from 4-3-4/Table 2. See 4-3-3/5.11 for details, which is required to be verified.

5.13

Deck and Bulkhead Penetrations


Where cables pass through watertight, fire tight or gas tight bulkheads or decks, the penetrations are to be
made through the use of approved stuffing tubes, transit devices or pourable materials which will maintain
the integrity of the division. Additionally, each such stuffing tube, transit device or pourable material is to
be of a character so as not to damage the cable physically or through chemical action or through heat build-up.
When cables pass through (except collision bulkhead) decks and bulkheads, penetrations are to be verified
in compliance with 4-3-3/5.13 of these Rules. In general, where penetrations are designed to maintain
water/fire/gas tight integrity, they are to be tested by similar method how the structure is tested.
Where cables pass through deck beams or similar structural parts, all burrs are to be removed in way of the
holes and care is to be taken to eliminate sharp edges.

50

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

5.15

7
1
5

Surveys
Surveys During Construction
Surveys at Builders Yard Electrical Cables and Equipment

7-1-5

Mechanical Protection
5.15.1 Metallic Armor
Protection of electric cables installed in locations liable to damage during normal operation of the
drilling unit are to be verified during cable installation survey. Cables can either be provided with
braided metallic armor or other means to protect them from mechanical injury as appropriate.
5.15.2 Conduit Pipe or Structural Shapes
Protection of electric cables installed in locations in way of hatch openings, tank tops, open decks
subject to seas, and where passing through decks, are to be verified and confirmed to be protected
by substantial metal shields, structural shapes, pipe or other equivalent means. When expansion
bends are fitted, they are to be accessible for maintenance. The protection and its installation are to
be in compliance with 4-3-3/5.15 of these Rules.

5.17

Emergency and Essential Feeders


5.17.1 Services Required to be Operable under Fire Condition
At least the following services are required to be operable under a fire condition:

i)

Fire and general alarm system

ii)

Fire extinguishing system including fire extinguishing medium release alarms

iii)

Emergency fire pump

iv)

Fire detection system

v)

Control and power systems for all power operated fire doors and their status indicating
systems

vi)

Control and power systems for all power operated watertight doors and their status indicating
systems

vii)

Emergency lighting

viii)

Public address system

ix)

Remote emergency stop/shutdown arrangement for systems which may support the
propagation of fire and/or explosion

It is to be verified that, as far as practicable, cables and wiring for emergency and essential
services, including those listed above are not to pass through high fire risk areas. It is also to be
verified that these cables and wiring are run in such a manner as to preclude their being rendered
unserviceable by heating of the bulkheads that may be caused by a fire in an adjacent space (See
4-3-3/5.17).
5.17.2 Requirements by the Governmental Authority
Requirements (if any) of the Flag Administration for installation of emergency circuits required in
various types of drilling units, is to be taken into consideration.

5.19

Mineral Insulated Cables


At all points where mineral-insulated, metal-sheathed cable terminates, an approved seal is to be provided
immediately after stripping to prevent entrance of moisture into the mineral insulation. In addition, the
conductors extending beyond the sheath are to be insulated with an approved insulating material. When
mineral-insulated cable is connected to boxes or equipment, the fittings are to be approved for the conditions
of service. The connections are to be in accordance with the manufacturers installation recommendation.

5.21

Fiber Optic Cables


The installation of fiber optic cables is to be in accordance with the manufacturers recommendations to
prevent sharp bends where the fiber optic cables enter the equipment enclosure. Consideration is to be
given to the use of angled stuffing tubes. The cables are to be installed so as to avoid abrading, crushing,
twisting, kinking or pulling around sharp edges.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

51

Part
Chapter
Section

7
1
5

Surveys
Surveys During Construction
Surveys at Builders Yard Electrical Cables and Equipment

7-1-5

5.23

Battery Room
Where cables enter battery rooms, the holes are to be bushed as required for watertight bulkheads in
7-1-5/5.13. All connections within battery rooms are to be resistant to the electrolyte. Cables are to be
sealed to resist the entrance of electrolyte by spray or creepage.

5.25

Paneling and Dome Fixtures


Where cables are installed behind paneling, all connections are to be accessible and the location of
concealed connection boxes is to be indicated. Where a cable strip molding is used for cable installation on
the incombustible paneling, it is to be of incombustible material. Dome fixtures are to be installed so that
they are vented or they are to be fitted with fire-resistant material in such a manner as to protect the
insulated wiring leading to the lamps and any exposed woodwork from excessive temperature.

5.27

Sheathing and Structural Insulation


Cables may be installed behind sheathing, but they are not to be installed behind nor imbedded in structural
fire insulation. They are to pass through such insulation at right angles and are to be protected by a continuous
pipe with a stuffing tube at one end. For deck penetrations, this stuffing tube is to be at the upper end of the
pipe and for bulkhead penetrations, it is to be on the uninsulated side of the bulkhead. For refrigerated-space
insulation, the pipe is to be of phenolic or similar heat-insulating material joined to the bulkhead stuffing
tube, or a section of such material is to be inserted between the bulkhead stuffing tube and the metallic
pipe. Passage of cables through fire insulation and arrangement of penetration pieces are to be verified.

5.29

Splicing of Electrical Cables


In general, splicing of electrical cables is not allowed, especially in wet spaces. Where an electrical cable needs
to be spliced, the approved splicing is to be examined and to satisfy the basis of approval (See 4-3-3/5.21.1)
and the installation and protection of splices as follows:
5.29.1 Installation
All splices are to be made after the cable is in place and are to be accessible for inspection. The
conductor splice is to be made using a pressure type butt connector by use of a one-cycle compression
tool. See 4-3-3/9.1.4 for splices in hazardous area.
5.29.2 Protection
Splices may be located in protected enclosures or in open wireways. Armored cables having splices
will not be required to have the armor replaced, provided that the remaining armor has been earthed
in compliance with 4-3-3/7.9 or provided the armor is made electrically continuous. Splices are to
be so located such that stresses (as from the weight of the cable) are not carried by the splice.

5.31

Splicing of Fiber Optic Cables


Where fiber optic cables are spliced, the splicing is to be made by means of approved mechanical or fusion
methods.

5.33

Cable Junction Box


Installation of cable junction boxes throughout the vessel, except for propulsion cables, may be used.
Construction, suitability, separation, and the support and connection of cables within all junction boxes are
to be examined to be in compliance with 4-3-3/5.25 of these Rules and the following:
Cables are to be supported, as necessary, within junction boxes so as not to put stress (as from the weight
of the cable) on the cable contact mountings. The connections are to be provided with locking type connections.

52

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

7
1
5

Surveys
Surveys During Construction
Surveys at Builders Yard Electrical Cables and Equipment

7-1-5

Equipment Installation and Arrangement

7.1

Materials
Material of all electrical equipment is to be in compliance with 4-3-1/11 of these Rules.

7.3

Grounding Arrangements
Where not obtained through normal construction, arrangements provided to effectively ground metal
structures of derricks, masts and helicopter decks are to be verified. See also 4-2-6/7.1.3 for fuel storage
for helicopter facilities.
All grounding arrangements are to be verified before the drilling unit commences its sea trial.

7.5

Insulation Material and Operation Temperature


A critical factor in the reduced life of electrical equipment is heat. The type of insulation used in equipment
depends on the operating temperature that the equipment will experience. Average insulation life decreases
rapidly with increases in internal operating temperatures of the equipment.
For definitions and requirements of cable insulation materials, see 6-1-7/1.1.

7.7

Degree of Protection for Enclosure


The designation to indicate the degree of protection consists of the characteristic letters IP followed by two
numerals (the characteristic numerals) indicating conformity with conditions stated in 4-3-1/Table 2 and
4-3-1/Table 3. The characteristic numerals of equipment are to be verified at random as meeting the design
drawings.

7.9

Temperature Ratings
Temperature ratings of all electrical equipment are to be in compliance with 4-3-1/17 of these Rules. The
ratings of equipment are to be verified at random as meeting the design drawings.
7.9.1

Reduced Ambient Temperature


Where electrical equipment is installed within environmentally-controlled spaces, the ambient
temperature for which the equipment is to be rated may be reduced from 45C and maintained at a
value not less than 35C, provided all of the conditions in 4-3-1/17.3.1 are met, ratings of cables
are in compliance with 4-3-1/17.3.2, and the ambient temperature control equipment is verified for
its satisfactory function.

The equipment used for cooling and maintaining the lesser ambient temperature is to be classified
as a secondary essential service, in accordance with 4-3-1/3.5, and the capability of cooling is to
be witnessed at sea trial.

7.11

Clearances and Creepage Distances


Clearances and creepage distances of all electrical equipment are to be in compliance with 4-3-1/19 of
these Rules. The distances are to be verified at random as meeting the Rules.

7.13

Equipment Location, Protection and Accessibility


Equipment location, protection and accessibility of all electrical equipment are to be in compliance with
4-3-3/3 of these Rules. The distances are to be verified at random as meeting the Rules.
7.13.1 Equipment Location
Electrical equipment is to be so placed or protected as to minimize the probability of mechanical
injury or damage from the accumulation of dust, oil vapors, steam or dripping liquids. See
4-3-3/Table 1 for required degree of protection for various locations.

Where electrical and electronic equipment is located within areas protected by local fixed pressure
water-spraying or water-mist fire extinguishing system and those within adjacent areas exposed to
direct spray, equipment is to be verified for having a degree of protection not less than IP44.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

53

Part
Chapter
Section

7
1
5

Surveys
Surveys During Construction
Surveys at Builders Yard Electrical Cables and Equipment

7-1-5

7.13.2 Protection from Bilge Water


All generators, motors and electric couplings are to be so arranged that they cannot be damaged by
bilge water; and, if necessary, a water-tight coaming is to be provided to form a well around the
base of such equipment with provision for removing water from the well. Measures taken for
protection are to be verified.
7.13.3 Accessibility
The design and arrangement of electrical apparatus is to provide accessibility to parts requiring
inspection or adjustment. Armature and field coils, rotors and revolving fields are to be removable and
where air ducts are used, there are to be means of access. Proper accessibility is to be verified.

7.15

Generators
In general, all generators on ship-type drilling units are to be located with their shafts in a fore-and-aft direction
on the drilling unit and are to operate satisfactorily in accordance with the inclination requirements of
4-1-1/Table 1. Where it is not practicable to mount the generators with the armature shafts in the fore-andaft direction, their lubrication will require special consideration, and this arrangement will be confirmed
onboard.

7.17

Main Service Motors


Installation and arrangement of main service motors are to be in compliance with 4-3-3/3.5 of these Rules.
The arrangement, in accordance with the reviewed plans, is to be verified at random as meeting the Rules.
7.17.1 Pump Motors
Motors for operating plunger and close-coupled pumps are to be verified to have the driving end
entirely enclosed or designed to prevent leakage from entering the motor.
7.17.2 Motors on Weather Decks
Motors for use on weather decks are to be verified to have an enclosure of at least IP56 protection
or are to be enclosed in watertight housings.
7.17.3 Motors Below Decks
Motors below decks are to be verified to have been installed at a location as dry as practicable and
away from steam, water, and oil piping.

7.19

Accumulator Batteries
Permanently installed power, control and monitoring storage batteries of acid or alkaline types are to be so
arranged that the trays are accessible and provided with not less than 254 mm (10 in.) headroom. Where a
relief valve is provided for discharging excessive gas due to overcharge, arrangements are to be made for
releasing the gas to the weather deck away from any source of ignition.
7.19.1 Battery Installation and Arrangements
Installation and arrangement of large storage batteries, moderate size batteries, and small batteries
are to be verified in compliance with 4-3-3/3.7.2 of these Rules.

A low-hydrogen-emission battery with a battery charger having a charging rate of a large or moderate
battery size installation may be treated as a moderate or small battery installation, respectively, if
the following are met and verified:

54

i)

Calculations under the worst case charging conditions are submitted and reviewed by
Engineering; and

ii)

A warning notice is placed to notify maintenance personnel that additional batteries are
not to be installed, and batteries are only to be replaced by other batteries of the same or
lower hydrogen emission rate.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

7
1
5

Surveys
Surveys During Construction
Surveys at Builders Yard Electrical Cables and Equipment

7-1-5

7.19.2 Battery Trays


Trays for batteries are to be verified as being chocked with wood strips or equivalent to prevent
movement and each tray is to be fitted with nonabsorbent insulating supports on the bottom and
with similar spacer blocks at the sides or with equivalent provision to secure air-circulation space
all around each tray.
7.19.3 Lead-Acid Batteries and Alkaline Batteries In Same Compartment
Lead-acid batteries and alkaline batteries, when placed in the same battery compartment, are to be
verified as being effectively identified as to type and segregated.
7.19.4 Ventilation of Battery Rooms, Battery Lockers, and Deck Boxes
Where natural ventilation is employed, the ducts are to be verified as being run directly from the
top of the battery room to the open air above. Where natural ventilation is impractical, and instead
a mechanical exhaust ventilation is provided with fan intake at the top of the room, the fans are to
be verified as being of non-sparking construction in accordance with 4-3-3/9.7 and approved by
ABS to be capable of completely changing the air in the battery room substantiating that adequate
ventilation is available to maintain the flammable gases within the battery room to a level below
the Lower Explosive Limit (L.E.L.) at the maximum battery charging current. Where the
ventilation rate is based on low hydrogen emission type batteries, a warning notice to this effect is
to be verified as being placed in a visible place in the battery room. Openings for air inlet are to be
provided near the floor.
7.19.5 Ventilation of Battery Lockers
Where practicable, battery lockers are to be ventilated similarly to battery rooms by a duct led from
the top of the locker to the open air or to an exhaust ventilation duct. The ventilation arrangement as
well as provision of louvers or equivalent near the bottom for entrance of air is to be verified.
7.19.6 Ventilation of Battery Deck Boxes
Duct from the top of the box, terminating in a goose neck, mushroom head or equivalent to
prevent entrance of water, for a deck boxes is to be verified. Holes for air inlet are to be verified as
being provided on at least two opposite sides of the box. The entire deck box, including openings
for ventilation, is to be tested as being weathertight to prevent entrance of spray or rain. Boxes for
small batteries, not requiring ducted ventilation, are to be verified for having openings near the top
to permit escape of gas.
7.19.7 Corrosion Protection
Corrosion protection or alternative arrangement of battery rooms, lining of deck boxes and small
batteries are to be verified to be in compliance with 4-3-3/3.7.4 of these Rules.
7.19.8 Maintenance of Batteries
Where batteries are fitted for use for essential and emergency services, a maintenance schedule of
such batteries is to be provided and maintained.

The schedule and procedures put in place are to satisfy 4-3-3/3.7.5 of these Rules. Details of the
schedule, procedures, and the maintenance records are to be included in the drilling units maintenance
system and integrated into the drilling units operational maintenance routine, as appropriate, and
verified.
7.19.9 Replacement of Batteries
Where a vented type battery replaces a valve-regulated, sealed type battery, the requirements in
4-3-3/3.7.6 are to be confirmed.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

55

Part
Chapter
Section

7.21

7
1
5

Surveys
Surveys During Construction
Surveys at Builders Yard Electrical Cables and Equipment

7-1-5

Switchboards
7.21.1 Location and Protection
Arrangement of switchboards are to be confirmed as providing easy access, as may be needed, to
apparatus and equipment without danger to personnel. Switchboards are to be located in a dry place
so as to provide a clear working space of at least 914 mm (36 in.) at the front of the switchboard
and a clearance of at least 610 mm (24 in.) at the rear, which may be reduced to 457 mm (18 in.)
in way of stiffeners or frames. Arrangement and location of distribution boards are to be verified
to be in compliance with 4-3-3/3.9 of these Rules.
Note:

Where switchboards are enclosed at the rear and are fully serviceable from the front, clearance at the rear
will not be required unless necessary for cooling.

It is to be verified that switchboards are secured to a solid foundation, self-supported or braced to


the bulkhead or the deck above. In case the last method is used, means of bracing is to be flexible
to allow deflection of the deck without buckling the assembly structure.
Flanged connections of liquid piping are to be avoided over or near switchboards. If a connection
was necessary and agreed by the Surveyor, satisfactory provision to prevent any leakage from
injuring the switchboard is to be verified.
7.21.2 Notice Plate
A notice plate posted either at the entrance to the switchboard room or on the switchboard front
panel to state that the floor in the room is of electrically insulated construction is to be verified.

7.23

Distribution Boards
7.23.1 Location and Protection
Distribution boards are to be located in accessible positions. Location and enclosure of distribution
boards are to be verified to be in compliance with 4-3-3/3.11.1 of these Rules.

Flanged connections of liquid piping are to be avoided over or near distribution boards for essential
services. If a connection was necessary and agreed by the Surveyor, satisfactory provision to
prevent any leakage from injuring the boards is to be verified.
7.23.2 Switchboard-Type Distribution Boards
Distribution boards of the switchboard type, unless installed in machinery spaces or in compartments
assigned exclusively to electric equipment and accessible only to authorized personnel, are to be
verified as being completely enclosed or protected against accidental contact and unauthorized
operation.
7.23.3 Safety-Type Panels
It is to be verified that safety type panels are used only for controlling branch lighting circuits,
provided with dead front type panels where voltage to earth is in excess of 50 volts DC or 50 volts
AC rms between conductors.

7.25

Motor Controllers and Control Centers


7.25.1 Location and Installation
Motor control centers are to be located in a dry place. It is to be verified that a clear working space
is provided around motor control centers to enable doors to be fully opened and equipment removed
for maintenance and replacement.

It is to be verified that motor control centers are secured to a solid foundation, be self-supported or
be braced to the bulkhead.
Flanged connections of liquid piping are to be avoided over or near motor controllers and control
centers. If a connection was necessary and agreed by the Surveyor, satisfactory provision to
prevent any leakage from injuring the motor controllers and control centers is to be verified.

56

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

7
1
5

Surveys
Surveys During Construction
Surveys at Builders Yard Electrical Cables and Equipment

7-1-5

7.25.2 Disconnecting Arrangements


Means are to be provided for disconnecting the motor and controller from all supply conductors, except
that a manually operated switch or circuit breaker may serve as both controller and disconnecting
means (see 6-1-7/9.17.2).

Arrangement of disconnecting devices is to be verified to be in compliance with 4-3-3/3.13.2 of


these Rules.
It is to be verified that the disconnect switch, if not adjacent to the controller, is provided with an
identification plate.
It is to be verified that the disconnect device indicates by a position of the handle, or otherwise,
whether it is open or closed.
7.25.3 Indicating-Light Circuits
Where indicating-light circuits are employed, they are to be verified to be in compliance with
4-3-3/3.13.3 of these Rules.

7.27

Resistors for Control Apparatus


Protection of resistors against corrosion, location and mounting of resistors are to be verified to be in
compliance with 4-3-3/3.15 of these Rules. In addition, arrangement of the electrical equipment and wiring
located within these spaces is to be such as to prevent their exposure to ambient temperatures in excess of
that for which they have been designed.

7.29

Lighting Fixtures
Lighting fixtures are to be verified as being arranged as to prevent temperature rises which could damage
the cables and wiring, and to prevent surrounding material from becoming excessively hot.

7.31

Heating Equipment
Electric radiators, if used, are to be verified as being fixed in position and be so constructed as to reduce fire
risks to a minimum. It is to be confirmed that electric radiators of the exposed-element type are not used.

7.33

Magnetic Compasses
Precautions taken in connection with apparatus and wiring in the vicinity of the magnetic compass to
prevent disturbance of the needle from external magnetic fields, is to be verified.

7.35

Portable Equipment and Outlets


It is to be verified that portable equipment is not used in hazardous areas, and portable lights are not used
for berth lights in accommodations.

7.37

Receptacles and Plugs of Different Ratings


Receptacles and plugs of different electrical ratings are not to be interchangeable. In cases where it is
necessary to use 230 volts portable equipment, the receptacles for their attachment are to be verified for
being of a type which will not permit attaching 115 volts equipment.

7.39

Installation Requirements for Recovery from Dead Ship Condition


Where the emergency source of power is an emergency generator which complies with 4-3-2/5.15 and
4-3-2/3.1.4, this emergency generator may be used for restoring operation of the drilling units main
propulsion plant, boilers and auxiliary machinery, as applicable.
Where there is no emergency generator installed, the arrangements for bringing main and auxiliary
machinery into operation are to be such that the initial charge of starting air or initial electrical power and
any power supplies for engine operation can be developed onboard the drilling unit without external aid. If
for this purpose an emergency air compressor or an electric generator is required, these units are to be
powered by a hand-starting oil engine or a hand-operated compressor.
The arrangement for bringing the main and auxiliary machinery into operation is to be verified. It is also to
be verified by testing that recovery capacity is such that the starting energy and any power supplies for
propulsion engine operation are available within 30 minutes of a black out condition.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

57

Part
Chapter
Section

7
1
5

Surveys
Surveys During Construction
Surveys at Builders Yard Electrical Cables and Equipment

7-1-5

Earthing

9.1

General
Unless the machines or equipment are one of the type as listed in 4-3-3/7.1, the exposed metal parts of
electrical machines or equipment which are not intended to be live but which are liable under fault
conditions to become live are to be earthed. Earthing is to be verified.

9.3

Permanent Equipment
It is to be verified that the metal frames or cases of all permanently installed generators, motors, controllers,
instruments and similar equipment are permanently earthed through a metallic contact with the drilling
units structure. Alternatively, they may be connected to the hull by a separate conductor in accordance
with 4-3-3/7.5 of these Rules.
Where outlets, switches and similar fittings are of nonmetallic construction, all exposed metal parts are to be
verified as being earthed.

9.5

Connections
It is to be verified that all earthing conductors are of copper or other corrosion-resistant material and are
protected against damage. The nominal cross-sectional area of every copper earthing conductor is to be not
less than that required by 4-3-3/Table 2.
Earthed distribution system and connections to vessels hull are to be verified to be in compliance with
4-3-3/7.5.2 and 4-3-3/7.5.3 respectively.

9.7

Portable Cords
Receptacle outlets operating at 50 volts DC or 50 volts AC rms or more are to be confirmed for having an
earthing pole.

9.9

Cable Metallic Covering


It is to be verified that all metal sheaths, armor of cable and mineral-insulated, metal-sheathed cable are
electrically continuous and are earthed to the metal hull at each end of the run, except that final sub-circuits
may be earthed at the supply end only, and that all metallic coverings of power and lighting cables passing
through hazardous area or connected to equipment in such an area are earthed at least at each end.

58

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

PART

Section 6: Surveys at Builders Yard Electrical Systems

CHAPTER

Surveys During Construction

SECTION

Surveys at Builders Yard Electrical Systems

General
This Section pertains to surveys and testing to be carried out on electrical systems during construction,
installation and testing of mobile offshore drilling units at builders yard/facility. The documentation
requirements for design review are given Parts 3, 4 and 5 of these Rules.
ABS Surveyor attendance is required, typically for the following purposes. All surveys and testing is to be
carried out in presence of and to the satisfaction of the attending Surveyor, prior to the sea trial as referenced
in Section 7-1-9 of these Rules.

Main Source of Power


Units are to be provided with at least two main generator sets with combined capacity sufficient to maintain
the unit in normal operations (including the drilling mode) and habitable conditions to include at least adequate
services for cooking, heating, domestic refrigeration, mechanical ventilation, sanitary and fresh water.
Examination and testing of the main source of power is to be carried out to confirm compliance with below
specific requirements, prior to the sea trial as referenced in Section 7-1-9 of these Rules. For further details,
see 4-3-2/3.1.

3.1

Power Supply by Generators


The capacity of the generator sets, their fuel capacity and system arrangement are to satisfy 4-3-2/3.1.
3.1.1

Propulsion Capability with Multiple Generators


For drilling units having multiple generating sets providing power for both propulsion and auxiliary
services, the propulsion loads considered for normal operation need only include those necessary
to propel the unit at 3.6 m/s (7 kn) or one-half the design speed in calm water, whichever is the
lesser. Propulsion capability under these conditions is to be verified during sea trial as referenced
in Section 7-1-9 of these Rules.

3.1.2

Blackout and Dead Ship Start


The blackout and dead ship start testing is to be demonstrated prior to the sea trial. Same
demonstration is to be repeated during the sea trial as referenced in Section 7-1-9 of these Rules.

Examination and testing of the main source of power is to be carried out to confirm compliance
with below specific requirements. For further details, see 4-3-2/3.1.
A Blackout situation means the loss of the main source of electrical power resulting in the main
and auxiliary machinery being out of operation.
A Dead Ship condition means a condition under which:
i)

The main propulsion plant, boilers and auxiliary machinery are not in operation due to the
loss of the main source of electrical power, and

ii)

In restoring propulsion, the stored energy for starting the propulsion plant, the main source
of electrical power and other essential auxiliary machinery is assumed to be not available.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

59

Part
Chapter
Section

7
1
6

Surveys
Surveys During Construction
Surveys at Builders Yard Electrical Systems

7-1-6

For self-propelled drilling units, the generating sets are to be such that with any one generator or
its primary source of power out of operation, the remaining generating sets are capable of providing
the electrical services necessary to start the main propulsion plant from a dead ship condition, as
defined herein, within 30 minutes of the blackout. This is to be verified during sea trial as
referenced in Section 7-1-9 of these Rules.
In restoring the propulsion from a dead ship condition for self-propelled drilling units, no stored
energy is to be assumed available for starting the propulsion plant, the main source of electrical
power and other essential auxiliaries. It is assumed that means are available to start the emergency
generator at all times.
The emergency source of electrical power may be used to restore the propulsion, provided its
capability either alone or combined with that of any other source of electrical power is sufficient to
provide at the same time those services required to be supplied by 4-3-2/5.3.1 through 4-3-2/5.3.7.
The emergency generator and other means needed to restore the propulsion are to have a capacity such
that the necessary propulsion starting energy is available within 30 minutes of blackout. Emergency
generator stored starting energy is not to be directly used for starting the propulsion plant, the main
source of electrical power and/or other essential auxiliaries (emergency generator excluded).

3.3

Generator Driven by Propulsion Unit


Generator driven by propulsion unit is to satisfy 4-3-2/3.3.

3.5

Sizing of AC Generator
Sizing of the AC Generator is to satisfy 4-3-2/3.5.

Emergency Source of Power


A self-contained emergency source of electrical power together with its associated power transformer, if
any, transitional source of emergency power, emergency switchboard, and emergency lighting switchboard
is to be installed in a non-hazardous space and is to be located above the worst damage waterline (see
3-3-2/1.3.2), aft of the collision bulkhead, if any, and in a space which is not within the assumed extent of
damage defined in 3-3-2/3.5. Its location is to be readily accessible from the open deck. The arrangement is
to be such as to insure that a fire, flooding or other failure in a space containing the main source of electrical
power, or in any space containing internal combustion machinery for propulsion, any oil-fired or oil-fuel
unit, or internal combustion machinery with an aggregate total power of 375 kW (500 hp) or more, will not
interfere with the supply or distribution of emergency power.

5.1

Boundary and Alternate Arrangements


Boundaries of spaces containing emergency sources of power and associated equipment and alternate
arrangements of source of power are to satisfy 4-3-2/5.1.

5.3

Emergency Power Supply


The electrical power available is to be sufficient to supply all those services that are essential for safety in
an emergency. The emergency source of electrical power is to be capable of supplying simultaneously, at
least the following services for the period specified hereafter, if they depend upon an electrical source for
their operation.
5.3.1

60

Emergency Lighting
For a period of 18 hours, emergency lighting:

i)

At every embarkation station on deck and over the sides, their launching appliances and
the area of water into which they are to be launched.

ii)

In all service and accommodation alleyways, stairways and exits, personnel elevators and
their trunks.

iii)

In the machinery spaces and main generating stations, including their control positions.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

7
1
6

Surveys
Surveys During Construction
Surveys at Builders Yard Electrical Systems

7-1-6

iv)

In all control stations, machinery control rooms, and at each main and emergency
switchboard.

v)

In all spaces from which control of the drilling process is performed and where controls
of machinery essential for the performance of this process, or devices for emergency
switching-off of the power plant are located.

vi)

At all stowage positions for firemens outfits.

vii)

At the sprinkler pump, if any, at one of the fire pumps, if dependent upon emergency
generator for its source of power, at the emergency bilge pump, if any, and at the starting
positions of their motors.

viii)

On helicopter landing deck perimeter.

5.3.2

Navigation Lights and Signals


For a period of 18 hours, navigation lights, other lights and sound signals required by the
International Regulations for the Prevention of Collisions at Sea in force.

5.3.3

Marking of Offshore Structures


For a period of four days, any signaling lights or sound signals which may be required for marking
of offshore structures.

5.3.4

Internal Communications
For a period of 18 hours, all internal communication systems required in an emergency (see Note 1
below).

5.3.5

Fire and Gas Detection and Alarm Systems


For a period of 18 hours, the required fire and gas detection and alarm systems (see Note 1 below).

5.3.6

Emergency Signals
For a period of 18 hours, intermittent operation of the manually operated call points and all internal
signals that are required in an emergency (see Note 1 below).

5.3.7

Blow-Out Preventer (BOP) and Well Disconnection


For a period of 18 hours, blow-out preventer control systems and means for disconnecting the unit
from the well-head arrangement, if electrically controlled (see Note 1 below).

5.3.8

Fire Pump and Fire Extinguishing Systems


For a period of 18 hours, one of the fire pumps and other fire extinguishing systems, if dependent
upon the emergency generator for its source of power.

5.3.9

Diving Equipment
For a period of 18 hours, permanently installed diving equipment necessary for safe conduct of
diving operations, if dependent on the drilling units electrical power.

5.3.10 Column-Stabilized Units


On column-stabilized units, for a period of 18 hours:

i)

Ballast valve control system, ballast valve position indicating system, draft level indicating
system and tank level indicating system.

ii)

The largest single ballast pump required by 4-2-4/13.5.1. See also 4-3-2/5.11 of these Rules.

5.3.11 Self-propelled Drilling Units


On self-propelled drilling units:

i)

For a period of 18 hours, emergency lighting at the steering gear.

ii)

For a period of 18 hours, navigational aids as required by Chapter V of the 1974 SOLAS
Convention, as amended (see Note below).

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

61

Part
Chapter
Section

7
1
6

Surveys
Surveys During Construction
Surveys at Builders Yard Electrical Systems

7-1-6

iii)

For a period of 18 hours, intermittent operation of the daylight signaling lamp and the
units whistle (see Note 1 below).

iv)

For a period of at least 10 minutes, continuous operation of the steering gear (see 4-3-2/11.5
of these Rules).

5.3.12 Other Emergency Services


i)
For a period of 30 minutes, operation of watertight doors referred to in 3-3-2/5.3 of these
Rules (but not necessarily all of them simultaneously), including their controls and indicators,
unless an independent temporary source of stored energy is provided.

5.5

ii)

For a period of 30 minutes, free-fall lifeboat secondary launching appliance, if the secondary
launching appliance is not dependent on gravity, stored mechanical power or other manual
means.

iii)

For a period of 18 hours, intermittent operation of the general emergency alarm system
and other manually operated alarms required in 4-3-2/17.

Note 1

Unless independent supply from an accumulator battery suitably located for use in an emergency and
sufficient for the period of 18 hours is supplied.

Emergency Sources
Satisfactory operation and testing of the emergency source of electrical power and its protective devices
are to be carried out prior to the sea trial as referenced in Section 7-1-9 of these Rules.
The emergency source of electrical power may be either a generator or an accumulator battery in accordance
with 4-3-2/5.5.2 or 4-3-2/5.5.3. The emergency generator and its prime mover and any emergency accumulator
battery are to be designed to function at full rated power when upright and when inclined in static condition
up to a maximum angle of heel in the intact and damaged condition, as determined in accordance with
Section 3-3-2.
In no case need the equipment be designed to operate when inclined in static condition more than:

25 in any direction on a column-stabilized unit;

15 in any direction on a self-elevating unit, and

22.5 about the longitudinal axis and/or when inclined 10 about the transverse axis on a surface unit.

In all cases, the emergency source of electrical power is to be designed to operate as a minimum under the
angles of inclination defined in 4-1-1/7.1.

5.7

5.5.1

Generator
Where the emergency source of electrical power is a generator, it is to satisfy 4-3-2/5.5.2.

5.5.2

Accumulator Battery
Where the emergency source of electrical power is an accumulator battery, it is to satisfy 4-3-2/5.5.3.

5.5.3

Emergency Generator for Non-emergency Services


Emergency generator used for non-emergency services is to satisfy 4-3-2/5.5.4.

Transitional Source of Power


Satisfactory operation and testing of the transitional source of power is to be carried out prior to the sea
trial as referenced in Section 7-1-9 of these Rules.
The transitional source of emergency electrical power, where required by 4-3-2/5.5.2ii), is to consist of an
accumulator battery which is to satisfy 4-3-2/5.5.

62

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

5.9

7
1
6

Surveys
Surveys During Construction
Surveys at Builders Yard Electrical Systems

7-1-6

Emergency Switchboard
The emergency switchboard is to be installed as near as is practicable to the emergency source of electrical
power.
Satisfactory operation of the emergency switchboard is to be verified prior to the sea trial as referenced in
Section 7-1-9 of these Rules.
Installation of the emergency switchboard for generator, installation of accumulator batteries, arrangement
of inter-connector feeder between emergency and main switchboards, and arrangements made where
necessary to automatically disconnect the non-emergency circuits from the emergency switchboard, are to
satisfy 4-3-2/5.9.

5.11

Ballast Pumps
On column-stabilized units, arrangement of ballast pumps is to satisfy 4-3-2/5.11. It is to be possible to
supply each ballast pump required by 4-2-4/13.5.1 from the emergency source of power. The arrangement is
to be such that one of the pumps is connected directly to the main switchboard and the other pump is connected
directly to the emergency switchboard. For systems utilizing independent pumps in each tank, all pumps
are to be capable of being supplied from an emergency source of power. When sizing the emergency
source of power in accordance with 4-3-2/5.3, the largest ballast pump capable of being supplied from this
source is to be assumed to be operating simultaneously with the loads specified in 4-3-2/5.3, allowing for
suitable load and diversity factors.

5.13

Starting Arrangements for Emergency Generator Sets


5.13.1 Cold Conditions
Emergency generating sets are to be capable of being readily started in their cold condition at a
temperature of 0C (32F). If this is impracticable or if lower temperatures are likely to be
encountered, heating arrangements are to be provided for ready starting of the generating sets.
5.13.2 Number of Starts
Each emergency generator that is arranged to be automatically started is to be equipped with
approved starting devices with a stored energy capability of at least three consecutive starts.
Unless a second independent means of starting is provided, the source of stored energy is to be
protected to preclude critical depletion by automatic starting system, i.e., the automatic starting
system is only allowable for consumption of the stored energy source to a level that would still
provide the capability for starting the emergency generator upon intervention by personnel. In
addition, a second source of energy is to be provided for an additional three starts within 30
minutes unless manual starting can be demonstrated to be effective.
5.13.3 Charging of Stored Energy
The stored energy is to be maintained at all times, as follows:

i)

Electrical and hydraulic starting systems are to be maintained from the emergency
switchboard.

ii)

Compressed air starting systems may be maintained by the main or auxiliary compressed
air receivers through a suitable non-return valve or by an emergency air compressor
which, if electrically driven, is supplied from the emergency switchboard.

iii)

All of these starting, charging and energy storing devices are to be located in the
emergency generator space. These devices are not to be used for any purpose other than
the operation of the emergency generating set. This does not preclude the supply to the air
receiver of the emergency generating set from the main or auxiliary compressed air
system through the non-return valve fitted in the emergency generator space.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

63

Part
Chapter
Section

7
1
6

Surveys
Surveys During Construction
Surveys at Builders Yard Electrical Systems

7-1-6

5.13.4 Manual Starting


Where automatic starting is not required, manual (hand) starting is permissible, such as manual
cranking, inertia starters, manually charged hydraulic accumulators or power charge cartridges,
where they can be demonstrated as being effective.

When manual (hand) starting is not practicable, the requirements of 4-3-2/5.15.2 and 4-3-2/5.15.3
are to be complied with, except that starting may be manually initiated.

5.15

Alarms and Safeguards for Emergency Diesel Engines


Alarms and safeguards are to be fitted in accordance with 7-1-6/Table 1.
The safety and alarm systems are to be designed to fail safe.
Regardless of the engine output, if shutdowns additional to those specified in 7-1-6/Table 1 are provided,
except for the over-speed shutdown, they are to be automatically overridden when the engine is in
automatic or remote control mode.
The alarm system is to function in accordance with 4-9-2/3.1.2 and 4-9-2/7 of the Steel Vessel Rules, with
additional requirements that grouped alarms are to be arranged on the bridge. For drilling units that are not
self-propelled, the grouped alarms are to be arranged at an emergency control station.
In addition to the fuel oil control from outside the space, a local means of engine shutdown is to be provided.
Local indications of at least those parameters listed in 7-1-6/Table 1 are to be provided within the same
space as the diesel engines and are to remain operational in the event of failure of the alarm and safety
systems.

TABLE 1
Emergency Diesel Engine Alarms and Shutdowns (2012)
Systems
Fuel Oil

Monitored Parameters

Alarm

Auto
Shutdown

Notes
[X = Required]

A1

Leakage from pressure pipes

B1

Temperature high

For engines having a power of 220 kW or more.

B2

Lubricating oil pressure


low

B3

Oil mist concentration in


crankcase high

Cooling
Medium

C1

Pressure or flow low

C2

Engine

D1

Lubricating
Oil

For engines having a power of more than 2250 kW


(3000 hp) or having a cylinder bore of more than
300 mm (11.8 in.).

For engines having a power of 220 kW or more.

Temperature high

Over-speed activated

For engines having a power of 220 kW or more.

Distribution System

7.1

Main Service Distribution System


Current-carrying parts with potential to earth are to be protected against accidental contact.
For recognized standard distribution systems, see 4-3-1/7. Separate feeders are to be provided for essential
and emergency services.
Method of the distribution system is to satisfy 4-3-2/7.1.

64

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

7.3

7
1
6

Surveys
Surveys During Construction
Surveys at Builders Yard Electrical Systems

7-1-6

Hull Return System


The hull return system is not to be used for power, heating or lighting, except that the following systems
may be used:
i)

Impressed Current Cathodic Protective (ICCP) system;

ii)

Limited and locally earthed systems, provided that any possible resulting current does not flow
directly through any hazardous areas; or

iii)

Insulation level monitoring devices, provided the circulation current does not exceed 30 mA under
all possible conditions.

iv)

Current-carrying parts with potential to earth are to be protected against accidental contact.

Where the hull return system is used, arrangements are to satisfy 4-3-2/7.3.2.

7.5

Earthed Distribution Systems


System earthing is to satisfy 4-3-2/7.5.

7.7

External or Shore Power Supply Connection


Where arrangements are made for the supply of electricity from a source on shore or other external source,
they are to satisfy 4-3-2/7.7.
7.7.1

Information Plate
An information plate is to be provided at or near the connection box giving full information on the
system of supply and the nominal voltage (and frequency if AC) of the drilling units system and
the recommended procedure for carrying out the connection.

7.7.2

Securing of Trailing Cable


Provision is to be made for securing the trailing cable to a framework to absorb stress on the
electrical terminals by catenary tension of the cable.

7.9

Harmonics
The Total Harmonic Distortion (THD) is to satisfy 4-3-2/7.9.

Circuit Protection System


Examination and testing of the circuit protection system is to be carried out to confirm compliance with
these Rules as referenced below, and prior to the sea trial as referenced in Section 7-1-9 of these Rules.
i)

Generators is to satisfy 4-3-2/9.3

ii)

AC generators is to satisfy 4-3-2/9.5

iii)

DC generators is to satisfy 4-3-2/9.7

iv)

Accumulator batteries is to satisfy 4-3-2/9.9

v)

External or shore power supply is to satisfy 4-3-2/9.11

vi)

Motor branch circuits to satisfy 4-3-2/9.13

vii)

Transformer circuits is to satisfy 4-3-2/9.15

viii)

Meters, pilot lamps and control circuits is to satisfy 4-3-2/9.17

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

65

Part
Chapter
Section

11

7
1
6

Surveys
Surveys During Construction
Surveys at Builders Yard Electrical Systems

7-1-6

Systems for Steering Gear Installed in Self-Propelled Units


Examination and testing of the systems for steering gear installed on self-propelled drilling units is to be
carried out to confirm compliance with below specific requirements, as applicable, prior to the sea trial as
referenced in Section 7-1-9 of these Rules.

11.1

Power Supply Feeder


Arrangement of power supply circuits for the electric or electro-hydraulic steering gear system is to satisfy
4-3-2/11.1.

11.3

Protection for Steering Gear Motor Circuit


Short circuit protection and under voltage release arrangements are to satisfy 4-3-2/11.3.

11.5

Emergency Power Supply


Emergency power supply is to satisfy 4-3-2/11.5.

11.7

Controls, Instrumentation, and Alarms


See 4-3-4/5.7, 4-3-4/13, 4-3-4/15 and 4-3-4/17 of the Steel Vessel Rules.

13

Lighting and Navigation Light Systems


Examination and testing of the lighting and navigation light systems is to be carried out to confirm compliance
with below specific requirements, prior to the sea trial as referenced in Section 7-1-9 of these Rules.

13.1

Lighting System
13.1.1 Main Lighting System
A main electric lighting system is to provide adequate illumination throughout those parts of the
drilling unit normally accessible to and used by crew. It is to be supplied from the main source of
electrical power.
13.1.2 System Arrangement
The arrangement of the main electric lighting system is to be such that a fire or other casualty in
spaces containing the main source of electrical power, associated transforming equipment, if any,
the main switchboard and the main lighting switchboard will not render the emergency electric
lighting system required by 4-3-2/5.3ii) inoperative.

The arrangement of the emergency electric lighting system is to be such that a fire or other casualty
in spaces containing the emergency source of electrical power, associated transforming equipment, if
any, the emergency switchboard and the emergency lighting switchboard will not render the main
electric lighting system required by 4-3-2/13.1.1 inoperative.
13.1.3 Lighting Circuits
In machinery and accommodation spaces such as:

Public spaces

Category A machinery spaces

Galleys

Corridors

Stairways leading to boat-decks, including stair towers and escape trunks

There is to be more than one final subcircuit for lighting, one of which may be supplied from the
emergency switchboard, in such a way that failure of any one circuit does not leave these spaces in
darkness.

66

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

7
1
6

Surveys
Surveys During Construction
Surveys at Builders Yard Electrical Systems

7-1-6

13.1.4 Protection for Lighting Circuits


Lighting circuits are to be protected against overload and short circuit. For further details, see
4-3-2/13.1.4.

13.3

Navigation Light System


Feeders, navigation light indicators, and protection of the lighting circuits are to satisfy 4-3-2/13.3

13.5

Obstruction Light System


Feeders, obstruction light indicators, and protection of the lighting circuits are to satisfy 4-3-2/13.

15

Interior Communication Systems


Examination and testing of the interior communication system is to be carried out to confirm compliance
with below specific requirements, prior to the sea trial as referenced in Section 7-1-9 of these Rules.

15.1

Interior Communication Systems for All Units


15.1.1 Public Address (PA) System
For all type of units, self-propelled or not, the public address system is to comply with the following
requirements and verified accordingly:

i)

System Requirements. The system is to be a loud speaker installation enabling the broadcast
of messages which are clearly audible in all parts of the unit. The system is to provide for the
broadcast of messages from the navigation bridge, emergency control stations (see 7-1-8/17.7)
and other strategic points with an override function so that all emergency messages may
be broadcast if any loudspeaker in the locations concerned has been turned off, its volume
has been turned down or the public address system is in use for other purposes.

ii)

Minimum Sound Levels. With the drilling unit underway or in normal operating conditions,
the minimum sound levels for broadcasting emergency announcements are to be:

In interior locations, 75 dB (A) and at least 20 dB (A) above the speech interference level

In exterior locations, 80 dB (A) and at least 15 dB (A) above the speech interference level

iii)

Emergency Source of Power. The system is to be connected to the emergency source of


power.

iv)

Public Address System Combined with General Alarm System. Where a single system
serves for the public address and general emergency alarm functions, the system is to be
arranged so that a single failure is not to cause the loss of both systems and is to minimize
the effect of a single failure. The major system components, such as power supply unit,
amplifier, alarm tone generator, etc., are to be duplicated. The coverage provided by the
arrangement of the system loops and speakers is to be such that after a single failure, the
announcements and alarms are still audible in all spaces. Duplication of system loops and
speakers in each room or space is not required provided the announcements and alarms
are still audible in all spaces.

15.1.2 Voice Communications


Means of voice communication is to be available for transfer of information between all locations
where action may be necessary in case of an emergency. Such locations include the emergency
control stations required by 7-1-8/17.7, machinery spaces, SCR rooms and all locations vital to the
safety of the unit. Simultaneous talking among these locations is to be possible at all times and the
calling to these locations is always to be possible even if the line is busy.

Where an elevator is installed, a telephone is to be permanently installed in all cars and connected
to a continuously manned area. The telephone may be sound powered, battery operated or electrically
powered from the emergency source of power.
Final sub-circuit for power supply to these voice communication systems is to be independent of
other electrical systems and control, monitoring and alarm systems. See 7-1-6/5.3.4 for power supply.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

67

Part
Chapter
Section

15.3

7
1
6

Surveys
Surveys During Construction
Surveys at Builders Yard Electrical Systems

7-1-6

Interior Communication Systems for Self-Propelled Units


For self-propelled units, in addition to the requirements of 7-1-6/15.1, interior communication systems are
to comply with the following requirements and verified accordingly:
15.3.1 Navigation Bridge Communication
At least two independent means are to be provided for communicating orders from the navigation
bridge to the position in the machinery space or in the control room from which the speed and
direction of thrust of the propellers are normally controlled. Appropriate means of communication
are to be provided to any other positions from which the main propulsion machinery may be
controlled. See 4-3-2/5.3.4 for power supply.

One of the communicating means between the navigation bridge and the main propulsion control
position is to be an engine room telegraph which provides visual indication of the orders and
responses both in the machinery space and on the navigation bridge. Communication network and
power supply circuit for this may be combined with the engine order telegraph system specified in
4-3-2/15.3.
15.3.2 Main Propulsion Control Stations
A common talking means of voice communication and calling or engine order telegraph repeater
is to be provided between the main propulsion control station and local control positions for main
propulsion engines and controllable pitch propellers. Voice communication systems are to provide
the capability of carrying on a conversation while the drilling unit is being navigated. Final
subcircuit for power supply to these is to be independent of the other electrical system and the
control, monitoring and alarm systems. Communication network and power supply circuit for the
voice communication system may be combined with the system required in 4-3-2/15.5.
15.3.3 Voice Communications
In addition to 7-1-6/15.1.2, a common talking means of voice communication and calling is to be
provided between the navigation bridge, main propulsion control station and the steering gear
compartment so that the simultaneous talking among these spaces is possible at all times and the
calling to these spaces is always possible even if the line is busy.
15.3.4 Emergency and Interior-communication Switchboard
Emergency and interior-communication switchboards, when fitted, are to comply with the applicable
parts of 6-1-7/9 of these Rules, and attention is directed to the requirements of the governmental
authority whose flag the drilling unit flies.

17

Manually Operated Alarms


Examination and testing of the following manual alarm systems are to be carried out to confirm compliance
with below specific requirements, prior to the sea trial as referenced in Section 7-1-9 of these Rules.

17.1

General Alarm (GA) System


A general alarm system complying with requirements of 4-3-2/17.1.2 is to be provided to summon crew to
muster stations and initiate actions included in the muster list. The system is to be supplemented by
instructions over a public address system meeting the requirements of 4-3-2/15.9. Any entertainment sound
system is to be automatically turned off when the general emergency alarm is activated.
The general emergency alarm system is to be capable of sounding the general emergency alarm signal, fire
alarm signal and abandon unit signal on an electrically operated bell or klaxon or other equivalent warning
system, which is to be powered from the drilling units main supply and the emergency source of electrical
power required by 4-3-2/5. The system is to be capable of operation from the navigation bridge, emergency
control stations (see 7-1-8/17.7) and from other strategic points.
The system is to be clearly audible in all parts of the unit. The alarm is to continue to function after it has
been triggered until it is manually turned off or is temporarily interrupted by a message on the public
address system.

68

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

7
1
6

Surveys
Surveys During Construction
Surveys at Builders Yard Electrical Systems

7-1-6

i)

(2014) The minimum sound levels for the emergency alarm tone in interior spaces are to be 80 dB
and at least 10 dB (A) above ambient noise levels existing during normal equipment operation in
moderate weather.

ii)

The sound levels at the sleeping position in cabins and in cabin bathrooms are to be at least 75 dB
(A) and at least 10 dB (A) above ambient noise levels.

Note:

Refer to the Code on Alarms and Indicators adopted by IMO Resolution A.830(19).

17.1.1 General Alarm (GA) System on Self-Propelled Units


Self-propelled drilling units are to be capable of sounding the general emergency alarm on the
drilling units whistle, but which need only be capable of operation from the navigation bridge.

17.3

Engineers Alarm for Self-Propelled Units


An engineers alarm operable from the main propulsion control station or at the maneuvering platform, as
appropriate, is to be provided. It is to be audible in each engineers cabin and its sound pressure level is to
comply with 7-1-6/17.1. See 7-1-6/5.3.12iii) for power supply.

17.5

Refrigerated Space Alarm


Fan and diffuser rooms serving subfreezing compartments are to be provided with a device capable of
activating an audible and visual alarm in a manned control center and operable from within the latter space
for the protection of personnel. See 7-1-6/5.3.12iii) for power supply.

17.7

Elevator Alarm
A device which will activate an audible and visual alarm in a manned control center is to be provided in all cars.
Such alarm system is to be independent of power and control systems of the elevator. See 7-1-6/5.3.12iii)
for power supply.

19

Fire Protection and Fire Detection Systems


Examination and testing of the following systems are to be carried out to confirm compliance with below
specific requirements, prior to the sea trial as referenced in Section 7-1-9 of these Rules.

19.1

Emergency Stop
19.1.1 Ventilation System
All electrical ventilation systems are to be provided with means for stopping the motors in case of
fire or other emergency. These requirements do not apply to closed re-circulating systems within a
single space. See also 7-1-8/9.

The main machinery-space ventilation is to be provided with means for stopping the ventilation
fans, which is to be located in the passageway leading to, but outside of the space, or in the firefighting station, if provided.
A control station for all other ventilation systems is to be located in the fire-control room or
navigation bridge, or in an accessible position leading to, but outside of the space ventilated.
19.1.2 Other Auxiliaries
For emergency tripping and emergency stop for other auxiliaries such as forced and induced draft
fans, electric motor pressurization fans, oil fuel transfer pumps, fuel oil units, see 4-2-5/1.5 and
7-1-8/17.9.

19.3

Fire Detection and Alarm System


See 7-1-8/13.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

69

Part
Chapter
Section

21

7
1
6

Surveys
Surveys During Construction
Surveys at Builders Yard Electrical Systems

7-1-6

Electrical System Testing


All machinery and associated equipment is to be examined and tested prior to the sea trial as referenced in
Section 7-1-9 of these Rules.

21.1

Auxiliary Systems
All auxiliary apparatus is to be tried under working conditions.

21.3

Generators
Each generator is to be run for a time sufficient to show satisfactory operation, and parallel operation with
all possible combinations is to be demonstrated.
Generator safety devices and shutdowns are to be confirmed operational.
The emergency generator is to be run for a time sufficient to show satisfactory operation, and its alarms
and safeguard devices to be confirmed (see 4-3-2/5).

21.5

Auxiliary Motors
Each auxiliary motor necessary to the operation of the drilling unit is to be run for a time sufficient to show
satisfactory performance at such load as can readily be obtained.

21.7

Main Switches and Breakers


All main switches and circuit breakers are to be operated, but not necessarily at full load.

21.9

Lighting System
The operation of the lighting system, heaters, etc., is to be demonstrated satisfactorily (see 7-1-6/13.1).
Satisfactory operation the emergency lights after a black-out condition is to be confirmed. Sufficient lighting
in all control stations, egress routes, and embarkation stations are to be verified.

21.11 Voltage Drop


The entire installation is to operate and the drop in voltage on any part of the installation is not to exceed
6%. See 7-1-6/7.1.
21.13 Public Address (PA) & General Alarm (GA) Systems
The entire installation is to operate satisfactorily. Operation of the system with emergency source of power
is to be confirmed. In areas where background noise may be high, installation of additional light probes is
to be verified. (see 7-1-6/15.1 and 7-1-6/17.1)
21.15 Fire and Gas (F&G) Detection System
The entire installation is to operate satisfactorily. Operation of the system with emergency source of power
is to be confirmed. In areas where background noise may be high, proper installation of additional light
probes is to be verified. Each fire alarm call point is to be activated and proven operational, and each
smoke, heat, infra-red detector is to be tested per manufacturers test procedure. Ventilation shutdowns and
closure of fire dampers are to be verified during this test.
21.17 Electrical Equipment in Hazardous Areas
All electrical equipment installed in hazardous areas is to be verified in accordance with ABS approved
drawings. Upon satisfactory completion of the survey, a final list of electrical equipment is to be produced
by the builder, and the list is to be endorsed by the attending Surveyor. ABS endorsed electrical equipment
list and hazardous area drawings are to be placed onboard the drilling unit to be used during Survey After
Construction.
Where purge air system is used, the purge air system and satisfactory operation of the equipment with its
associated alarm is to be confirmed.
For further details, see Section 7-1-7.
70

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

7
1
6

Surveys
Surveys During Construction
Surveys at Builders Yard Electrical Systems

7-1-6

21.19 Hazardous Area Doors, Ventilation and Alarms


All doors, ventilators and alarms associated with hazardous areas are to be examined and tested (see
Section 7-1-7).
21.21 Mud Pit Level Alarm
See 7-1-8/13.
21.23 Shutdown of Ventilation Fans and Openings
Means provided for stopping ventilating fans serving machinery spaces and for closing all doorways,
ventilators, annular spaces around funnels and other openings to such spaces are to be tested. These means
are to be capable of being manually operated from outside of such spaces in case of fire.
Remote means provided for stopping machinery driving forced and induced draft fans, electric motor
pressurization fans, oil fuel transfer pumps, oil fuel unit pumps and other similar fuel pumps are to be
tested. These means are to be situated outside of such spaces in case of a fire arising in the space in which
they are located. See 7-1-6/19.1.2.
In addition to the remote shutdowns required above, a means to shut down the equipment is to be provided
within the space itself and tested.

21.25 Emergency Shutdown System


Selective or simultaneous emergency shutdown of all electrical equipment is to be tested and the shutdown
sequence is to be in accordance with recommended sequence provided in the drilling units Operating
Manual (see 4-3-5/7).
21.27 Helicopter Deck Lighting
Operation of the helicopter deck lighting is to be demonstrated. Satisfactory operation the lighting after a
black-out condition is also to be confirmed.
21.29 Navigation and Obstruction Lights
Operation of all navigation and obstruction lights is to be confirmed. See 7-1-6/13.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

71

PART

Section 7: Surveys at Builders Yard Hazardous Areas

CHAPTER

Surveys During Construction

SECTION

Surveys at Builders Yard Hazardous Areas

General
This Section pertains to survey of the following items onboard mobile offshore drilling units built at
builders yard/facility, including required onboard testing and trial. The documentation requirements for
design review are given Part 4 of these Rules. Following items are to be surveyed and tested in presence of
and to the satisfaction of the attending Surveyor, preferably prior to delivery of the drilling unit.
i)

Arrangement of hazardous areas (zones)

ii)

Openings and penetrations affecting the extent of hazardous areas

iii)

Installation and function of access doors and hatches between hazardous areas and adjoining
areas/spaces

iv)

Installation and function of ventilation of hazardous areas and adjoining areas/spaces

v)

Installation of machinery in hazardous areas

vi)

Installation of cables and electrical equipment in hazardous areas

vii)

Installation of cables and electrical equipment in paint stores and battery lockers

viii)

Piping systems serving the hazardous areas

Aforementioned items are further referenced in subsequent Subsections of this Section.

1.1

Definitions
For definition of various terms, see 4-3-1/3 and 4-3-6/1 of these Rules.

Openings and Penetrations Affecting the Extent of Hazardous Zones

3.1

Openings
Where there is an opening, not fitted with any gas-tight enclosure device, at boundary decks or bulkheads
between an area/space categorized as hazardous and a less hazardous or non-hazardous enclosed area/space,
the entire area/space categorized as less hazardous will be considered as the same category of the higher
category hazardous Zone.
Mitigation of this situation is possible only if the opening is permanently closed, fitted with a bolted gas-tight
closure or provided with doors satisfying the arrangements and provisions required by 7-1-7/3.1 through
7-1-7/3.5, as applicable.
Where there is an opening, not fitted with any gas-tight enclosure device, at boundary decks or bulkheads
between an area/space categorized as hazardous and a non-hazardous open space, hazardous Zone will
extend into the non-hazardous open space. The extended hazardous areas will be categorized as defined in
4-3-6/5 of these Rules, and any machinery or electrical equipment within the extended hazardous area is to
be verified as suitable for safe operation for that hazardous Zone.

72

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

3.3

7
1
7

7-1-7

Penetrations
Any structural, piping or electrical penetration located on a deck or a bulkhead between an area/space
categorized as hazardous and a less hazardous or non-hazardous enclosed area/space, is to maintain the
gas-tight integrity of the deck or bulkhead.
3.3.1

Surveys
Surveys During Construction
Surveys at Builders Yard Hazardous Areas

Testing of Penetrations
Completed penetrations are to be tested to prove the gas-tightness of the boundary. Testing can be
carried out by one of the following method:

i)

Hose test (mostly used for structural or piping penetrations)

ii)

An air-flow pressure test (mostly used for Multi-Cable Transit (MCT) penetrations)

iii)

Surface Nondestructive Testing (NDT), such as a dye-penetrate test, if accepted by the


Surveyor

Access and Ventilation Conditions Affecting the Extent of


Hazardous Zones
Where access is provided for operational purposes, any enclosed space not referred to under 4-3-6/3.3 or
4-3-6/3.5 and having a direct access to any Zone 1 location or Zone 2 location becomes the same zone as
the location, except that:

5.1

Enclosed Zone 1 or Zone 2 Space with Direct Access to any Zone 1 Location
(see 7-1-7/Figure 1)
5.1.1

Access between Enclosed Zone 1 to any Zone 1 Location


An enclosed Zone 1 space with direct access to a semi-enclosed Zone 1 location is to be fitted
with a door opening into the semi-enclosed Zone 1 space.

5.1.2

Access between Enclosed Zone 2 to any Zone 1 Location


An enclosed space with direct access to any Zone 1 location is considered as Zone 2, provided all
three conditions listed below are met:

i)

The access is fitted with a gas-tight door opening into the Zone 2 space; and

ii)

Ventilation is such that the air flow with the door open is from the Zone 2 space into the
Zone 1 location; and

iii)

Loss of positive (+) ventilation in Zone 2 location is alarmed at a normally manned station.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

73

Part
Chapter
Section

7
1
7

Surveys
Surveys During Construction
Surveys at Builders Yard Hazardous Areas

7-1-7

FIGURE 1
Access to Zone 1 (2012)
Broken lines represent open, semi-enclosed, or enclosed zone.

Zone 1

Zone 1

Self-closing Gastight
Door (having no hold
back device)
Zone 1

Air
Flow

Zone 2

Note: Loss of ventilation is to be alarmed at a normally manned


station

5.3

74

Enclosed Zone 2 or Non-Hazardous Space with Direct Access to any Zone 2 Location
(see 7-1-7/Figure 2)
5.3.1

Access between Enclosed Zone 2 to any Zone 2 Location


An enclosed Zone 2 space with direct access to a semi-enclosed Zone 2 location is to be fitted
with a door opening into the semi-enclosed Zone 2 space.

5.3.2

Access between Enclosed Zone 2 to any Non-Hazardous Location


An enclosed space with direct access to any Zone 2 location is considered non-hazardous, provided
all three conditions listed below are met:

i)

The access is fitted with self-closing gas-tight door that opens into the non-hazardous space;
and

ii)

Ventilation is such that the air flow with the door open is from the non-hazardous space
into the Zone 2 locations; and

iii)

Loss of positive (+) ventilation in Non-Hazardous location is alarmed at a normally manned


station.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

7
1
7

Surveys
Surveys During Construction
Surveys at Builders Yard Hazardous Areas

7-1-7

FIGURE 2
Access to Zone 2 (2012)
Broken lines represent open, semi-enclosed, or enclosed zone.

Zone 2

Zone 2

Self-closing Gastight
Door (having no hold
back device)
Zone 2

Air
Flow

Non-Hazardous

Note: Loss of ventilation is to be alarmed at a normally manned


station

5.5

Enclosed Non-Hazardous Space with Direct Access to any Zone 1 Location


(see 7-1-7/Figure 3)
5.5.1

Access between Enclosed Zone 1 to any Zone 1 Location


See 7-1-7/5.1.1.

5.5.2

Access between Enclosed Non-Hazardous Space to any Zone 1 Location


An enclosed space with access to any Zone 1 location is considered non-hazardous, provided all
three conditions listed below are met:

i)

The access is fitted with gas-tight self-closing doors forming an air lock, or a single selfclosing gas-tight door which opens toward the non-hazardous space and has no hold-back
device; and

ii)

Ventilation is such that the air flow with the door or air lock doors open is from the nonhazardous space into the Zone 1 location (i.e., non-hazardous space has ventilation
overpressure in relation to the Zone 1 location); and

iii)

Loss of ventilation overpressure is alarmed at a normally manned station.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

75

Part
Chapter
Section

7
1
7

Surveys
Surveys During Construction
Surveys at Builders Yard Hazardous Areas

7-1-7

FIGURE 3
Access from Enclosed Non-Hazardous Areas to Zone 1 (2012)
Broken lines represent open, semi-enclosed, or enclosed zone.

Zone 1

Air
Lock

Air
Flow
Non-Hazardous

Note: Loss of ventilation overpressure is to be alarmed at a normally manned station

Self-closing Gastight
Door (having no hold
back device)
Zone 1

Air
Flow

Non-Hazardous

Note: Loss of ventilation overpressure is to be alarmed at a normally manned station

5.7

Doors and Hatches


Any gas-tight door or a hatch on a deck or a bulkhead between an area/space categorized as hazardous and
a less hazardous or non-hazardous enclosed area/space, is to maintain the gas-tight integrity of the deck or
bulkhead.
Gas-tight doors or hatches are to be tested to prove the gas-tightness of the boundary. Testing can be
carried out by one of the following method:
i)

Hose test (mostly used where there is no machinery or electrical equipment that may be affected
by splashing of water)

ii)

An air-flow pressure test (recommended for all gas-tight doors fitted on bulkheads providing
direct access mentioned in 7-1-7/5.1 through 7-1-7/5.5 of these Rules

Note:

Where a gas-tight door is tested per 7-1-7/5.7 ii) above, the applied air pressure is to be natural and provided by the
ventilation system fitted in each adjoining area/space. During the test, all applicable ventilators are to be fully
operational, and the loss of positive (+) and loss of overpressure is to be preferably tested simultaneously with
testing of the doors.

Door alarms are to be clearly visible and audible during drilling units normal operational noise level.

5.9

Ventilation
Ventilation systems for the hazardous and non-hazardous areas are to be in accordance with 4-3-6/7 of
these Rules. All ventilation system ducts and associated ventilation alarms are to be examined and tested.
5.9.1

Ventilation Ducts
Gas-tight ventilation ducts fabricated to maintain either positive or negative internal pressure, as
required, are to be subjected to appropriate testing of the ducts, to verify its tightness, after
installation onboard the drilling unit and prior to function testing of the ventilation system and its
alarms required by 7-1-7/5.1 through 7-1-7/5.5 of these Rules.

5.9.2

Non Sparking Ventilation Fans


Fans used for the ventilation of the hazardous areas are to be of non-sparking construction in
accordance with 4-3-3/9.7 and 4-3-6/9.3 of these Rules.

Type tests on non-sparking fans are to be carried out using an acceptable national or international
standard. Such type test reports are to be made available when requested by the Surveyor.

76

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

7
1
7

5.9.3

Surveys
Surveys During Construction
Surveys at Builders Yard Hazardous Areas

7-1-7

Loss of Ventilation/Overpressure Alarms


Where fitted, loss of ventilation and ventilation overpressure alarms are to be clearly visible and
audible at local site and at the control stations during drilling units normal operational noise level.

Machinery Installations
Where installed in hazardous areas, machinery installation is to comply with 4-3-6/9 of these Rules.

Equipment and Installation in Hazardous Area


Where installed in hazardous areas, all electrical cables and equipment are to comply with 4-3-6/9 of these
Rules.
All electrical equipment installed as referenced in the drawings required by 4-3-3/1.5 of these Rules and
reviewed by ABS are to be verified for its satisfactory installation, and in compliance with these Rules.
Upon satisfactory completion of the survey, a final list of electrical equipment is to be produced by the
builder, and the list is to be endorsed by the attending Surveyor. ABS endorsed electrical equipment list
and hazardous area drawings are to be placed onboard the drilling unit to be used during Survey After
Construction.

9.1

9.3

General
9.1.1

Cables Installation
Installation of electrical cables is to be in compliance with 4-3-3/9.1.4 of these Rules.

9.1.2

Lighting Circuits
Installation of lighting circuits is to be in compliance with 4-3-3/9.1.5 of these Rules. The switches
and protective devices for lighting fixtures are to be suitably labeled for identification purposes.

9.1.3

Permanent Warning Plates


Permanent warning plates are to be installed in the vicinity of hazardous areas in which electrical
equipment is installed, such as pump room, to advise personnel carrying out maintenance, repair
or surveys of availability of the booklet/list of equipment in hazardous areas referenced in 4-3-3/1.5,
if required for their use.

Certified-Safe Type and Pressurized Equipment and Systems


Where permitted by the Rules and approved for installation, all electrical equipment of certified-safe type
equipment are to be type-tested and certified by a competent independent testing laboratory as suitable for
hazardous areas and the product satisfies the design so tested and approved. Certificates are to be readily
available to the Surveyor.
9.3.1

Intrinsically-Safe (IS) System


Intrinsically-Safe System is to be in compliance with 4-3-3/9.3.2 of these Rules.

The sub-compartment to separate intrinsically-safe components from non-intrinsically-safe systems,


as required by 4-3-3/9.3.2(b), is to have an identifying nameplate indicating that the equipment
within is intrinsically safe and that unauthorized modification or repairs are prohibited.
9.3.2

Pressurized Equipment
Pressurized equipment is to be in compliance with 4-3-3/9.3.3 of these Rules.

Where pressurized/purged air system is used, the purge air system and operation of the
pressurized/purged equipment with its associated loss of power or the ventilation and alarms
provided are to be tested for compliance with 4-3-3/9.3.3 of these Rules.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

77

Part
Chapter
Section

9.5

7
1
7

Surveys
Surveys During Construction
Surveys at Builders Yard Hazardous Areas

7-1-7

Electrical Equipment used After Rig Shutdown


As stated in 4-3-5/7.1 of these Rules, all electrical equipment in exterior locations which is capable of
operation after the rig shutdown is to be verified suitable for installation in Zone 2 locations.
The equipment installed or used on exterior locations of the rig and required after a rig shutdown includes
but not limited to; emergency lighting, general alarm system, blow-out preventer control system, public
address system, and distress and safety radio communications.

11

Paint Stores and Battery Lockers


Arrangement of access, ventilation and electrical equipment installed in the paint stores and battery lockers
are to comply with 4-3-3/9.5 and 4-3-3/3.7 of these Rules respectively.

13

Piping and Installation in Hazardous Area


Piping systems carrying non-hazardous fluids are to be segregated from piping systems which may contain
hazardous fluids. Cross connection of the piping systems may be made where means for avoiding possible
contamination of the non-hazardous fluid system by the hazardous medium are provided.
Piping systems such as drains and scuppers originating in a hazardous area are to be led to hazardous
collection facility/tank. Hazardous drains need not be separated from non-hazardous drains, provided the
connections do not create an unsafe condition where the back-up of hazardous liquids and gases into nonhazardous areas may be possible.

13.1

Installation of Loop-Seal and Non-Return Check Valve (2016)


Where an unsafe condition, due to interconnection of hazardous and non-hazardous piping is possible nonhazardous drains are to be fitted with a loop-seal to trap hazardous gases. If back-up of hazardous liquid into
the non-hazardous areas is possible, a non-return check valve is to be installed. Height of the loop-seal is to
be not less than 760 mm (30 inches) and the check valve is to be fitted downstream of the seal (see 7-17/Figure 4). Both the seal and the valve are to be accessible for maintenance by crew.

FIGURE 4
Typical Drain Connection (2016)
Hazardous Area
Non-Hazardous Area

760 mm
(30 inches)

If a back-up of hazardous liquid into


the non-hazardous areas is possible,
a non-return check valve is to be
installed.

78

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

7
1
7

Surveys
Surveys During Construction
Surveys at Builders Yard Hazardous Areas

7-1-7

13.3

Extent of Hazardous Areas


Piping systems such as sounding pipes and air vents of a non-hazardous space, originating or terminating
in hazardous space will cause the safe area to become hazardous and designated as same zone as the
hazardous space. Installation of all such piping is to prevent safe areas from becoming hazardous.

13.5

Electrically Conductive Plastic Piping in Hazardous Areas


Regardless of the fluid being conveyed, plastic piping passing through a hazardous area is to be electrically
conductive. The resistance per unit length of the pipes and fittings is not to exceed 1 105 ohm/m (3 104
ohm/ft). See also 7-1-3/13.5.3iv).
If the pipes and fittings are not homogeneously conductive, the conductive layers are to be protected
against the possibility of spark damage to the pipe wall.
Installation of electrically conductive plastic pipe is to be tested to confirm compliance with the following:
i)

The resistance to earth (ground) from any point in the system is not to exceed 1 megohm. The
resistance is to be checked in the presence of and to the satisfaction of the Surveyor.

ii)

Where used, earthing wires or bonding straps are to be accessible for inspection. The Surveyor is
to verify that they are in visible locations.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

79

PART

Section 8: Surveys at Builders Yard Fire and Safety

CHAPTER

Surveys During Construction

SECTION

Surveys at Builders Yard Fire and Safety

General
This Section pertains to surveys and testing to be carried out on fire and safety features during construction,
installation and testing of mobile offshore drilling units at builders yard/facility. The documentation
requirements for design review are given Part 5 of these Rules.
ABS Surveyor attendance is required, typically for the following purposes. All surveys and testing is to be
carried out in presence of and to the satisfaction of the attending Surveyor, prior to the sea trial.

1.1

Administration Certification
When an Administration or its Agent other than the ABS, issues the IMO Mobile Offshore Drilling Unit
Safety Certificate to a drilling unit, such certificate will be accepted as evidence that the unit is in compliance
with the requirements of 7-1-8/5. In all other cases, the required information and plans are to be reviewed
by ABS, and surveys completed by ABS Surveyors.

Surveys of Fire and Safety Features


All fire and safety features required by this Section are to be installed and tested in accordance with the
Rules or recognized standards to the satisfaction of the attending Surveyor.
Structural fire protection details, materials and methods of construction are to be in accordance with the
International Code for Application of Fire Test Procedures (Resolution MSC.61(67)) (FTP Code), as
applicable, and SOLAS Regulations II-2/5.3 and II-2/6, as applied to cargo ships.
ABS reviewed booklet of the standard passive and active fire protection practices and details, including
such items as fire insulation installation and supports, bulkhead and deck penetrations of pipes, cables and
ventilation trunks, joiner details, fire damper installation, etc., as applicable, is to be available to the attending
Surveyor. Where penetration methods for A- or B-class decks or bulkheads are shown, an evidence of
approval by an Administration signatory to 1974 SOLAS as amended is also to be available.
The quality control program for the fire and safety features of a drilling unit is to at least include the
following items, as appropriate:

80

i)

Material quality and traceability

ii)

Inspection of passive fire protection system

iii)

Inspection and testing of active fire protection systems

iv)

Inspection and testing of fire-extinguishing systems

v)

Inspection and testing of fire and gas detection systems

vi)

Inspection and testing of ventilation systems

vii)

Inspection and testing of shutdown arrangements

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

7
1
8

Surveys
Surveys During Construction
Surveys at Builders Yard Fire and Safety

7-1-8

Passive Fire Protection Systems


All passive fire protection systems are to be in accordance with ABS reviewed plans and in compliance
with this Subsection.
All mobile offshore drilling units are to meet the requirements of this Subsection with regard to structural
fire protection, protection of accommodation spaces, service spaces and control stations.

5.1

Structural Fire Protection


5.1.1

Construction Materials
All steel material used for construction is to be certified in accordance with Section 7-1-2 of these
Rules. Material other than steel is to be provided with manufacturers certification of compliance,
and be readily available to the attending Surveyor.

Installation of materials, which contain asbestos is prohibited.


5.1.2

Fire Integrity of Bulkheads and Decks


Bulkheads and decks are to be built and protected in compliance with applicable Paragraphs of
5-1-1/3 of these Rules including associated Tables defining fire integrity of bulkheads and decks,
and in accordance with ABS reviewed drawings. These requirements apply to all permanent
structures and temporary or portable accommodation (including workspaces).

Fire integrity of bulkheads and decks are to be confirmed only after the bulkheads and decks are
satisfactorily examined and tested for structural purposes.
5.1.3

Fire Resistance of Bulkheads and Decks


Fire resistance of bulkheads and decks are to be satisfactorily maintained when;

i)

A and B class divisions are penetrated for the passage of electrical cables, pipes,
trunks, ducts, etc.

ii)

A class divisions are penetrated for girders, beams or other structural members, or

iii)

B class divisions are penetrated for the fitting of ventilation terminals, lighting fixtures
and similar devices.

Pipes penetrating A or B class divisions are to be of materials approved by the Administration,


having regard to the temperature that such divisions are required to withstand.
For pipe penetration details on A class bulkheads and decks, see 5-1-1/3.21 and 5-1-1/Figure 1
of these Rules. For pipe penetration details on B class bulkheads and decks, see 5-1-1/3.23 and
5-1-1/Figure 2 of these Rules.
All of the above mentioned penetrations are to be examined and tested as deemed necessary by the
Surveyor. Pipe penetrations through A class divisions may be tested with surface NDT.
5.1.4

Structural Fire Protection Details in way of Intersections, Joints and Penetrations


Whilst examining the fire integrity of bulkheads and decks, special attention is to be paid to the
structural fire protection details in way of joints and penetrations. Areas in way of intersection or
terminal joints and penetrations of all types are to avoid the risk of heat transmission. Unless
specifically indicated otherwise on drawings, where protection against heat transmission is
required, an extension of insulation by a minimum 450 mm (18 in.) beyond the intersections or
terminal points is to be installed. For further details, see 5-1-1/3.13 of these Rules.

Structural fire protection of joints and penetrations is to be applied, preferably when fire integrity
is confirmed by the Surveyor and only after bulkheads and decks are satisfactorily examined and
tested for structural purposes.
5.1.5

Windows and Side-scuttles


Windows and side-scuttles are to be examined for compliance with 5-1-1/3.15 of these Rules, and
installation in accordance with ABS reviewed drawings.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

81

Part
Chapter
Section

7
1
8

5.1.6

Surveys
Surveys During Construction
Surveys at Builders Yard Fire and Safety

7-1-8

Fire Doors
Fire doors are to be examined for compliance with 5-1-1/3.17 of these Rules, and installation in
accordance with ABS reviewed drawings. For conditions of accepting installation of watertight
doors in fire tight boundaries, see 5-1-1/3.17. Record of tests in accordance with Fire Test Procedure
Code (Resolution MSC.61(67)) are to be available to the Surveyor.

Where the self-closing fire doors are allowed to be fitted with hold-back hooks that incorporate
remote release fittings of the fail-safe type, the remote-release mechanism is to be tested.

5.3

Protection of Accommodation Spaces, Service Spaces and Control Stations


Protection of all accommodation spaces, service spaces, and control stations are to be examined and verified
for compliance with ABS reviewed drawings. Following items are to be subjected to visual examination
and testing as required:
5.3.1

Accommodation Bulkheads
All accommodation bulkheads are to be examined prior to their enclosure behind joiner work. For
further details see 5-1-1/5.3 and 5-1-1/5.5 of these Rules.

5.3.2

Stairs and Stairways


All stairs and stairways are to be examined prior to their enclosure behind joiner work. For further
details, see 5-1-1/5.7 and 5-1-1/5.9 of these Rules.

All self-closing doors are to be tested for proper closure without any external force.

82

5.3.3

Draft Stops
All draft stops required by 5-1-1/5.11 of these Rules are to be examined prior to closing behind
joiner work. Structure, piping or electric cables penetrations through draft stops are to maintain the
integrity of the draft stop. Fire protection drawings reviewed by the ABS is to be used as guidance
for installation and penetration details.

5.3.4

Insulation and Framing Materials


All insulation and framing material are to be examined. For further details, see 5-1-1/5.13 and
5-1-1/5.15 of these Rules.

5.3.5

Low Flame-Spread Surfaces


Following surfaces are to have low flame-spread characteristics:

i)

All exposed surfaces in corridors and stairway enclosures

ii)

Surface in concealed or inaccessible spaces

iii)

Exposed surfaces of ceilings

5.3.6

Veneers
Where bulkheads, linings and ceilings are covered with combustible veneers, they are to be in
compliance with 5-1-1/5.19 of these Rules. Where veneers are used, appropriate certificates are to
be available to the Surveyor.

5.3.7

Primary Deck Coverings


Primary deck coverings, if applied (see 5-1-1/5.21 of these Rules), are to be of approved materials
which will not readily ignite or give rise to toxic or explosive hazards at elevated temperatures.
Where deck covering is used, appropriate certificates are to be available to the Surveyor.

5.3.8

Coating of Exposed Interior Surfaces


Paints, varnishes and other finishes used on exposed interior surfaces are not to be of a nature to
offer an undue fire hazard and are not to be capable of producing excessive quantities of smoke or
toxic fumes (see 5-1-1/5.23 of these Rules). Where exposed interior surfaces are coated, appropriate
certificates are to be available to the Surveyor.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

7
1
8

5.3.9

Surveys
Surveys During Construction
Surveys at Builders Yard Fire and Safety

7-1-8

Ventilation Ducts
Ventilation ducts are to be examined and tested for compliance with ABS reviewed drawings, and
they are to be in compliance with 5-1-1/5.25 of these Rules.

5.3.10 Ventilation Ducts Penetrating A Class Divisions


Ventilation ducts penetrating A class divisions are to be verified for compliance with ABS
reviewed drawings and 5-1-1/5.27 of these Rules, as applicable. Where provided, all ventilation
dampers are to be examined and tested.
5.3.11 Ventilation Ducts for Machinery Spaces Cat. A, Hazardous Areas, and Galleys
Construction and arrangement of ventilation ducts serving the machinery spaces of Cat. A,
hazardous areas, and galleys are to be examined and tested for compliance with ABS reviewed
drawings and 5-1-1/5.29 of these Rules.

Where provided, all ventilation dampers are to be examined and tested.


5.3.12 Ventilation Ducts for Accommodation and Service Spaces or Control Stations
Construction and arrangement of ventilation ducts for accommodation and service spaces or
control stations are to be examined and tested for compliance with ABS reviewed drawings and
5-1-1/5.31 of these Rules.

Where provided, all ventilation dampers are to be examined and tested.


5.3.14 Ventilation Ducts Penetrating B Class Divisions
Ventilation ducts penetrating B class divisions are to be verified for compliance with ABS
reviewed drawings and 5-1-1/5.33 of these Rules.
5.3.15 Exhaust Ducts from Galley Ranges and Galleys
Construction and arrangement of exhaust ducts from galley ranges and the galleys are to be
verified for compliance with ABS reviewed drawings, and 5-1-1/5.35 and 5-1-1/5.37 respectively.
5.3.16 Closure of Ventilation Systems
Closure of all main inlets and outlets of the ventilation system are to be verified as being fitted
outside the space being ventilated.
5.3.17 Stopping of Power Ventilation
Power ventilation of accommodation spaces, service spaces, control stations, machinery spaces
and hazardous areas are to be verified for compliance with 5-1-1/5.41 of these Rules, and their
means of stopping ventilation are to be tested.
5.3.18 Windows and Sidescuttles in A-60 Boundaries
Where windows and/or sidescuttles are fitted on A-60 bulkheads which face the drill floor area,
they are to be verified for compliance with 5-1-1/5.43 of these Rules.

Where they are fitted with shutters or water curtain, arrangements are to be function tested.
5.3.19 Arrangement of Ventilation for Accommodation Spaces and Control Stations
The ventilation for accommodation spaces and control stations are to be arranged in such a way as
to prevent the ingress of flammable, toxic or noxious gases, or smoke from surrounding areas.
5.3.20 Air Balancing Ducts (Jumper Ducts)
Where air balancing ducts are fitted, compliance with 5-1-1/5.47 of these Rules is to be verified.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

83

Part
Chapter
Section

7
1
8

Surveys
Surveys During Construction
Surveys at Builders Yard Fire and Safety

7-1-8

Active Fire Protection Fixed Systems


All active fire protection fixed systems are to be in accordance with ABS reviewed plans and in
compliance with this Subsection.
All mobile offshore drilling units are to meet the requirements of this Subsection with regard to fire control
plans, fire pumps, fire main, hydrants, fire hoses, nozzles and international shore connections.

7.1

Fire Control Plan


Onboard provision of an approved fire control plans in compliance with 5-2-1/3.3 is to be verified. Where
last-minute minor changes are necessary and the fire control plan is submitted to ABS engineering for final
approval, the Surveyor may verify the submitted plan, endorse it to signify its correctness, and the drilling
unit may use this plan until the ABS reviewed copy is received onboard.
Note:

7.3

The use of Surveyor-endorsed fire control plan per the above, is not considered to be an outstanding.

Fire Pumps
There are to be at least two independently-driven fire pumps. Following items affecting suitability and
performance of the fire pumps installed onboard and in compliance with 5-2-2/1.1 of these Rules are to be
verified:
i)

Examination of all certified fire pumps

ii)

Verification of location and operation of the fire pumps

iii)

Where provided, examination and testing of other type pumps used for active fire protection

iv)

Verification of the output pressure at hydrants


Note:

v)

Pressure is to be at least 3.5 bar (3.5 kgf/cm2, 50 psi) at the hydrant, and the maximum pressure at any
hydrant shall be such that the effective control of a fire hose can be demonstrated.

Testing of the fire pump capacity


Note:

Capacity is to be demonstrated and satisfy 5-2-2/1.1.5 of these Rules.

vi)

Where installed, testing of the relief valves (per 5-2-2/1.1.6 of these Rules)

vii)

Where installed, installation and testing of intermediate tank water supply (per 5-2-2/1.1.7 of these
Rules)

viii)

Where fire pumps take suction from a pressurized water main system (i.e., a system not utilizing
an intermediate tank supply as on self-elevating units), arrangement and precautions required by
5-2-2/1.1.8 are to be verified.

7.5

Fire Main
The fire main system is to be examined and tested for compliance 5-2-2/1.3 of these Rules and verified in
accordance with approved drawings.

7.7

Hydrants, Hoses, Nozzles and International Shore Connection


All hydrants, hoses nozzles, and the international shore connections are to be examined and tested as
necessary for compliance 5-2-2/1.5 of these Rules and verified in accordance with approved drawings.
7.7.1

Hydrants
The number and position of the hydrants are to be physically verified after completion and
installation of structure, machinery and equipment onboard the drilling unit.
Note:

84

Confirming that a single length of hose may reach any part of the unit normally accessible to the crew
while the drilling unit is being operated, is to be confirmed by actual measurements, to the extent
deemed necessary by the Surveyor.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

7
1
8

7.7.2

Surveys
Surveys During Construction
Surveys at Builders Yard Fire and Safety

7-1-8

Hoses
All fire hoses are to be in compliance with 5-2-2/1.5.2 of these Rules and provided with couplings
and nozzles. Additionally, at least one complete fire hose assembly is to be carried as a spare.

Certification of fire hoses by a competent independent testing laboratory as being constructed of


nonperishable material to recognized standard is to be verified.
The hoses are to be sufficient in length to project a jet of water to any of the spaces in which they
may be required to be used. Fire hoses are to have a length of at least 10 m, but not more than:
i)

15 m in machinery spaces

ii)

20 m in other spaces and open decks

iii)

25 m for open decks with a maximum width in excess of 30 m

See Note of 7-1-8/7.7.1 for required verification.


All fire hoses may be subjected to leak test as deemed necessary by the Surveyor before they are
placed onboard the drilling unit and used as part of the commissioned active fire protection
system. In general, this test may be done either before trials per Section 7-1-9 of these Rules or
delivery of the drilling unit.

7.7.3

Nozzles
Dual purpose combined jet spray nozzles fitted throughout the unit, and in compliance with
5-2-2/1.5.3 of these Rules, are to be verified.

7.7.4

International Shore Connection


For surface type drilling units, international shore connections fitted and in compliance with
5-2-2/1.5.4 of these Rules, are to be verified.

Active Fire Protection Additional Fixed Systems


All additional active fixed fire protection systems fitted in accordance with 5-2-3/1 of these Rules are to be
in accordance with ABS reviewed plans and in compliance with this Subsection.
All mobile offshore drilling units are to meet the requirements of this Subsection with regard to the
additional fixed fire fighting systems, particularly gas smothering, foam system, water spraying, protection
of helicopter decks, and protection of paint and flammable liquid lockers, where fitted.

9.1

Gas Smothering System


All additional active fixed fire protection systems fitted in accordance with 5-2-3/1 of these Rules are to be
in accordance with ABS reviewed plans.
9.1.1

Storage of Gas Smothering Medium


Storeroom for storage of gas smothering medium is to be located and effectively ventilated in
compliance with 5-2-3/3 of these Rules.

9.1.2

Fire-Extinguishing Gas Alarm


Means are to be provided for automatically giving audible warning of the release of fire extinguishing
gas into any space to which personnel normally has access. The alarm is to operate for at least a
20-second period before the gas is released. Alarms may be pneumatically (by the extinguishing
medium or by air) or electrically operated. Operation of alarms is to be arranged in accordance
with 5-2-3/3.1.3 of these Rules and tested.

9.1.3

Controls
Arrangement of independent manual controls is to be verified, and the controls are to be tested.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

85

Part
Chapter
Section

7
1
8

9.1.4

Surveys
Surveys During Construction
Surveys at Builders Yard Fire and Safety

7-1-8

Carbon Dioxide Systems


In addition to the applicable requirements of the Rules, fixed carbon dioxide fire extinguishing
systems are to be in accordance with Chapter II-2, Regulations 10.4.2 and 10.4.3 of the International
Convention for the Safety of Life at Sea (SOLAS) 1974 and Amendments in force, and with
Chapter 1.4 and Chapter 5 of the International Code for Fire Safety Systems. Fixed low pressure
carbon dioxide systems are to be in accordance with 4-7-3/3.5 of the Steel Vessel Rules.

Installation of the CO2 system is to be examined in accordance with reviewed drawings and the
system subjected to function testing with a gas safe for human health.

9.3

Foam System
Where fitted, installation of the foam system is to be examined in accordance with reviewed drawings and
function tested.
9.3.1

Fixed High Expansion Foam Systems


In addition to the applicable requirements of the Rules, fixed high expansion foam systems are to
be in accordance with Chapter 6.2.1 and 6.2.2 of the International Code for Fire Safety Systems.

Fixed foam fire-extinguishing systems using inside air are to be designed, constructed and tested
in accordance with the requirements identified in MSC.1/Circ. 1271 Guidelines for the Approval
of High-Expansion Foam Systems Using Inside Air for the Protection of Machinery Spaces and
Cargo Pump-Rooms.
Foam concentrates are to be of an approved type.*
* Note:

9.3.2

Reference is made to the International Maritime Organization MSC/Circular 670 Guidelines for the
Performance and Testing Criteria, and Surveys of High-Expansion Foam Concentrates for Fixed FireExtinguishing Systems.

Low Expansion Foam System


Low expansion foam systems may be fitted in machinery spaces in addition to the required fixed
fire extinguishing system.

In addition to the applicable requirements of the Rules, fixed low expansion foam systems are to
be in accordance with Chapter 6.2.1 and 6.2.2 of the International Code for Fire Safety Systems.
Foam concentrates are to be of an approved type.**
** Note: Reference is made to the International Maritime Organization MSC/Circular 582 Guidelines for the
Performance and Testing Criteria, and Surveys of Low-Expansion Foam Concentrates for Fixed FireExtinguishing Systems.

9.5

Fixed Pressure Water Spraying Systems


In addition to the applicable requirements of the Rules, fixed water spraying systems are to be in accordance
with Chapter 7 of the International Code for Fire Safety Systems.
Installation of the fixed pressure water spraying system is to be examined in accordance with reviewed
drawings and the system function tested using fresh water. Where use of water may cause physical damage
to surrounding outfit, machinery or equipment, testing with an alternate test medium may be accepted by
the Surveyor.

9.7

Protection of Helicopter Decks


Where areas of a unit are designated for helicopter operations, details of the facilities are to be in accordance
with reviewed drawings and provision of firefighting systems referenced in 5-2-3/9.3 are to be verified as
being stored near the access to those areas.
Deckhouse tops directly below helicopter decks are to be verified as to not having any opening that could
allow flammable liquid from the helideck to enter the deckhouse. See 4-2-6/17 for helicopter deck drainage.
9.7.1

86

Helicopter Decks with No Refueling Capability


Provision and arrangement of fire fighting equipment in compliance with 5-2-3/9.3 of these Rules,
are to be verified.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

7
1
8

9.7.2

Surveys
Surveys During Construction
Surveys at Builders Yard Fire and Safety

7-1-8

Helicopter Decks with Refueling Capability


Provision and arrangement of fire fighting system in compliance with 5-2-3/9.3 of these Rules, are
to be verified.

Function of the fixed-foam system is to be demonstrated and the rate of delivery of the foam solution is
to be measured.

9.9

Paint and Flammable Liquid Lockers


Fire-extinguishing systems for paint and flammable liquid lockers or any similar service spaces used for
the storage of flammable liquids (such as solvents, adhesives, lubricants etc.) provided in compliance with
5-2-3/11 of these Rules and installed in accordance with reviewed drawings, are to be examined and tested.

11

Active Fire Protection Portable Fire Fighting Systems


All portable fire fighting equipment fitted in accordance with Section 5-2-4 of these Rules are to be in
accordance with ABS reviewed plans and in compliance with this Subsection.
All mobile offshore drilling units are to meet the requirements of this Subsection with regard to portable
fire extinguishers and sand, and firemans outfit.

11.1

Portable Fire Extinguishers and Sand


11.1.1 Portable Fire Extinguishers
Installation of all portable and semi-portable extinguishers provided in the quantities and locations
indicated in 5-2-4/Table 1 and 5-2-4/Table 2 are to be verified, and confirmed to be visible and
readily accessible.
11.1.2 Sand
On self-propelled units fitted with main or auxiliary oil-fired boilers, each boiler space is to be
provided with a receptacle containing at least 0.28 m3 (10 ft3) of sand, sawdust impregnated with
soda or other dry material suitable for extinguishing oil fires. Alternatively, an approved portable
extinguisher may be substituted as indicated in ABS reviewed plans.

11.3

Firefighters Outfit
All firefighter outfits installed as indicated on ABS reviewed plans, are to be verified for compliance with
5-2-4/3 of these Rules. Every firefighters outfit is to be provided with a breathing apparatus, a lifeline, a
safety lamp, an axe, nonconductive boots and gloves, a rigid helmet and protective clothing as required by
5-2-4/3 of these Rules.
If provided, the apparatus for recharging air cylinders is to be confirmed to be in compliance with 5-2-4/3.5
of these Rules, and the recharging capacity is to be tested to confirm that it meets the requirements of
SOLAS regulation II-2/10.10.2.6.

13

Fire Detection and Alarm Systems


Fire detection and alarm systems installed in accordance with ABS reviewed plans, are to be examined and
tested for compliance with 5-2-5/1 of these Rules.
Other alarms systems, such as the general alarm system, ventilation alarms and mud tank/pit level alarms
fitted onboard the drilling unit, installed in accordance with ABS reviewed plans, are to be examined and
tested for compliance with 5-2-5/1 of these Rules.

13.1

Testing of Alarm Systems


Thorough examination and testing of the fire detection and other alarm systems are to be carried out,
preferably before the drilling unit commences its trials per Section 7-1-9 of these Rules. This is to at least
include testing of all detectors, manual fire alarm actuators, general alarms (including the public address
system), fire-detection indicator boards, and ventilation alarms. Remaining alarms may be tested before
delivery.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

87

Part
Chapter
Section

15

7
1
8

Surveys
Surveys During Construction
Surveys at Builders Yard Fire and Safety

7-1-8

Flammable Gas Detection and Alarm Systems


Flammable gas detection and alarm systems installed in accordance with ABS reviewed plans, are to be
examined and tested for compliance with 5-2-5/3 of these Rules.
Thorough examination and testing of the system and associated alarms are to be carried out, preferably
before the drilling unit commences its trials per Section 7-1-9 of these Rules. This is to include testing of
all detectors and gas-detection indicator boards.

15.1

Hydrogen Sulfide (H2S) Detection and Alarm System


Location and alarms of the fixed automatic hydrogen sulfide gas detection and alarm system is to be
verified and tested (See 5-2-5/3.1 and 5-3-1/7).
It is to be confirmed that if the alarm at the emergency control station is unanswered within 2 min, the
toxic gas (hydrogen sulfide) alarm and the helideck status light are automatically activated.
In addition to the fixed automatic hydrogen sulfide gas detection, minimum of two portable hydrogen
sulfide gas monitoring devices are to be provided on the unit.

17

Outfitting
Outfitting items fitted onboard the drilling unit, such as the systems covered by this Subsection are to be in
accordance with ABS reviewed plans and in compliance with this Subsection.
Thorough examination of the means of escape, means of access and egress, and guards and rails fitted along the
routes is to be carried out, before the drilling unit commences its trials per Section 7-1-9 of these Rules.

17.1

Means of Escape
Arrangement of escape routes from accommodation spaces, service spaces and control stations, from
category A machinery spaces, from other machinery spaces, superstructures or deckhouses, together with
stairways or ladders in way of any escape route, and the accessibility and access through the routes, are to be
in accordance with 5-3-1/1 of these Rules.
17.1.1 Gratings in way of Escape Routes
If deck gratings are used along designated escape route(s) in manned areas, category A machinery
spaces, other machinery spaces, or from the superstructure and deckhouses to the survival craft
embarkation areas, material of grating is to be of steel.

Gratings made of material other than steel, such as Fiber Reinforced Plastics (FRP), may be used,
provided the grating material meets the design criteria similar to requirements contained in
Section 4-2-2 of these Rules.
i)

Fire endurance of non-steel gratings used in way of escape routes of open decks and
spaces that may be directly subjected to hydrocarbon fire, is to meet requirements of
Level 1 fire endurance standard (L1).

ii)

Fire endurance of non-steel gratings used in way of escape routes of open decks and
spaces that may not be directly subjected to hydrocarbon fire, is to meet requirements of
Level 2 fire endurance standard (L2).

Manufacturers material test reports for any L1 and L2 grating material are to be available to the
attending Surveyor.
Gratings made of material other than steel may be used in spaces (e.g. walkways in service spaces,
normally unmanned spaces, mud pit rooms, machinery maintenance decks/platforms, etc.) that are
not along the designated escape route, provided the grating material meets the design criteria
similar to requirements contained in Section 4-2-2 of these Rules and requirements of Level 3
fire endurance standard (L3).

17.3

88

Means of Access and Egress


The means of access and egress is to be verified for compliance with 5-3-1/3 of these Rules.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

7
1
8

Surveys
Surveys During Construction
Surveys at Builders Yard Fire and Safety

7-1-8

17.5

Guards and Rails


All guards and rails provided along floor deck areas and openings, and helicopter landing deck is to be
verified for compliance with 5-3-1/5 of these Rules.

17.7

Emergency Control Stations


Emergency control stations are to be verified for compliance with 5-3-1/7 of these Rules.
Testing of contact makers to activate the General Alarm (GA) system, communication system between the
control stations and all locations vital to the safety of the unit, and emergency shut-down facilities (see
7-1-8/19 of these Rules) are to be carried out, before the drilling unit commences its trials per Section 7-1-9
of these Rules.

17.9

Arrangements in Machinery Space


Examination and testing, as applicable, for the following arrangements/items are to be carried out, before
the drilling unit commences its trials per Section 7-1-9 of these Rules.
i)

Ventilating fans and openings to be examined and tested (see 5-3-1/9.1 of these Rules)

ii)

Other auxiliaries (see 5-3-1/9.3 of these Rules)

iii)

Oil tank suction pipes (see 5-3-1/9.5 of these Rules)

iv)

Oil fuel unit (see 5-3-1/9.7 of these Rules)

17.11 Segregation of Fuel Oil Purifiers


Installation of purifiers and fire and safety provisions provided for enclosed spaces containing the purifiers
are to be examined for compliance with 5-3-1/11 of these Rules.
The examination and any testing required is to be carried out, before the drilling unit commences its trials
per Section 7-1-9 of these Rules.

17.13 Fire Precautions for Machinery Spaces


Fire precautions taken in machinery spaces, as required by 5-3-1/15 of these Rules, are to be examined. The
examination is to be carried out, before the drilling unit commences its trials per Section 7-1-9 of these Rules.

19

Emergency Shutdown Arrangements

19.1

Arrangements and Services


Arrangements are to be provided for the disconnection or shutdown, either selectively or simultaneously,
of all electrical equipment and devices, including the emergency generator, except for the services listed
under 7-1-8/19.1.2 from the emergency control station. Initiating of the above shut-downs may vary
according to the nature of the emergency. A recommended sequence of shut-downs is to be provided in the
units operating manual.
Note:

In the case of units using Dynamic Positioning System (DPS) as the only means of position keeping, special
consideration may be given to the selective disconnection or shutdown of machinery and equipment associated
with maintaining the operability of the DPS in order to preserve the integrity of the well.

19.1.1 Operation After Shutdown


The following services are to be operable after an emergency shutdown:

i)

Emergency lighting required by 7-1-6/5.3.1i), ii) iii), and iv) for half an hour

ii)

General Alarm (GA) system

iii)

Blow-Out Preventer (BOP) control system

iv)

Public Address (PA) system

v)

Distress and safety radio communications

All equipment in exterior locations which is capable of operation after shutdown is to be suitable for
installation in Zone 2 locations.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

89

PART

Section 9: Surveys at Builders Yard Sea Trial

CHAPTER

Surveys During Construction

SECTION

Surveys at Builders Yard Sea Trial

General
A sea trial procedure is to be developed by the builder and submitted to the attending Surveyor for review and
comments, well in advance, prior to commencement of the trial.
A pre-planning meeting in presence of the attending Surveyor(s) is to be carried out prior to the sea trial to
at least confirm the following:

Sea trial procedure to be followed

Sea trial schedule and estimated duration of tests to be carried out during the sea trial

Key personnel from the builder, owner, operator, and any other representative

Any specific test to be carried out that may be outside the scope of classification

During sea trial of a drilling unit, the operation of machinery, electrical systems and safety features
required by these Rules is to be demonstrated to the satisfaction of the attending Surveyor(s). Complete
function tests are to be carried out, including duration runs and tests for operation of all protective devices
and stability tests for control, in presence of and to the satisfaction of the attending Surveyor(s).
If the drilling unit is self-propelled, maneuvering tests which should include a reversal of the drilling unit
from full speed ahead to full speed astern, is also to be carried out in presence of and to the satisfaction of
the attending Surveyor(s).

Stability Test
A stability test is required to be performed on every vessel. The American Society and Materials Standard
(ASTM) Guide for conducting stability tests, Standard Guide for Conducting a Stability Test (Inclining and
Lightweight Survey) to Determine the Light Ship Displacement and Centers of Gravity of a Vessel may be
used for conducting stability test.
A stability test, in accordance with a procedure accepted by an ABS engineering office, is to be carried out in
protected waters, and in presence of and to the satisfaction of the attending Surveyor before commencement
of the sea trial. The Surveyor is then to attest to the satisfactory performance of the experiment in a report to
the ABS engineering office for evaluation.
For a subsequent drilling unit, in a series built from the same set of drawings of an inclined drilling unit, the
requirement for an Inclining Experiment may be waived, provided:

90

A weights and centers calculation is prepared, indicating the differences between the subsequent and
the inclined drilling unit, and

The calculated light ship properties are subsequently confirmed by a Lightweight Survey witnessed by
an ABS Surveyor and found to be within the limits specified in SOLAS Regulation II-1/B-1(5.2),
unless indicated otherwise by the Flag Administration. If the limits specified are exceeded, the Flag
Administration is to be contacted to determine the acceptability of such a deviation.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

7
1
9

Surveys
Surveys During Construction
Surveys at Builders Yard Sea Trial

7-1-9

Safety
Sea trial cannot be commenced in presence of an ABS Surveyor unless the Surveyor agrees with the builder
that suitable safety precautions are taken onboard the drilling unit. This may include but not limited to the
verification of following items by the attending Surveyor:

Operational preparedness of any additional portable fire extinguishing placed onboard

Posting of temporary fire control and safety plans to be used during the sea trial

Satisfactory condition and installation of life saving appliances for the sea trial personnel, particularly
if the number of personnel exceeds the drilling units Persons On Board (POB) capacity

Abandon Unit Drill with entire sea trial personnel

Fire Drill with designated fire fighters

An exemption to any of the above is the responsibility of the Coastal State Authority, and if an exemption
is issued, the written exemption is to be made readily available to the attending Surveyor for evaluation.

Hull Structure Testing


As mentioned in 7-1-2/1, hull structure testing such as hydrostatic testing and hull structural testing of
tanks may be carried out during the sea trial. Provided it is to be agreed upon by the attending Surveyor
before the commencement of the sea trial, if the tank boundaries were previously subjected to satisfactory air
test, complete filling of water ballast tanks during the ballast trial may be accepted as the hull structure test.

Testing on Self-Elevating Drilling Units

9.1

Initial Jacking Test (2016)


The test should include a trial jacking of the completed hull up to the limit of designed travel and then
down again, to prove alignment of leg racks, pinions and guides, effectiveness of lock or brake arrangements,
and proper functioning of jacking system together with electrical safety system monitoring indicators.
After the initial trial jacking test, all legs and leg to spud can or mat connections are to be visually examined
and verified free from damage or permanent deformation. All leg connections to spud cans or mat are to be
nondestructively tested with a suitable surface crack detection method. In addition, the climbing pinions
are to be visually examined, as far as practical, to the satisfaction of the attending Surveyor.

9.3

Moveable Cantilever and Skid Beam Testing


Prior to placing the drilling unit in service, a function test of the longitudinal skidding arrangements of the
moveable cantilever and skid beam as well as any transverse skidding arrangements such as the sub-base
(drill floor) is to be carried out by skidding the completed drilling structures with derrick assembly to the
maximum limits of travel.
This test is to be carried out after the entire marine and drilling systems have been installed on the drilling
unit that affects the function load of the beams. During the testing, the cantilever and rigs skid beams need
not be overloaded to loads over and above their maximum allowable design loads.

11

Sea Trial
During the sea trial, following tests is to demonstrate that each item of plant and the system as a whole is
satisfactory for drilling units service after construction:

11.1

Operation of Machinery and Piping Systems


Satisfactory operation of all machinery and piping systems required by the Rules are to be confirmed
throughout the sea trial period.
If any excessive vibration of piping is noted during the sea trial, it is to be rectified upon completion of the trial.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

91

Part
Chapter
Section

11.3

7
1
9

Surveys
Surveys During Construction
Surveys at Builders Yard Sea Trial

7-1-9

Ballast System
Ballast system is to operate satisfactorily throughout the sea trial period.
On column stabilized drilling units, ballast system is to be tested to demonstrate that it is capable of raising
the drilling unit, starting from a level trim condition at deepest normal operating draft, either a distance of
4.6 m (15 ft) or to the severe storm draft, whichever distance is greater, within three hours. The test is to
preferably follow the ballasting procedure that is to be provided to the drilling units operating personnel.
In addition, all controls and indication systems in the central ballast control station are to operate
satisfactorily throughout the sea trial period, particularly during the ballast test.

11.5

Bilge System
Bilge system is to operate satisfactorily throughout the sea trial period. Satisfactory operation of bilge
alarms and suction from bilge wells is to be verified during the trial by random activation/testing of the
system.
On column stabilized drilling units, two independent systems of high bilge water level detection, giving an
audible and visual alarm at the central ballast control station is to be demonstrated during the sea trial,
preferably when the drilling unit is operating under emergency power. High bilge water level audible and
visual alarm at the central ballast control station for propulsion rooms and pump rooms in lower hulls of
column-stabilized units are to be demonstrated during the trial.

11.7

Electrical Installation for Drilling Unit Main Services


All auxiliary apparatus is to be tried under working conditions. Each generator is to be run for a time sufficient
to show satisfactory operation, and parallel operation with all possible combinations is to be demonstrated.
Each auxiliary motor necessary to the operation of the drilling unit is to be run for a time sufficient to show
satisfactory performance at such load as can readily be obtained. All main switches and circuit breakers are to
be operated, but not necessarily at full load. The operation of the lighting system, heaters, etc., is to be
demonstrated satisfactorily. The entire installation is to operate to the satisfaction of the Surveyor and the
drop in voltage on any part of the installation is not to exceed 6%. See 4-3-3/5.1.3.

11.9

Communication Facilities
Satisfactory operation of the interior communications system required by 4-3-2/15 is to be demonstrated to
the Surveyor during sea trials. Particular attention is to be given to demonstrating that the voice communication
systems required by 4-3-2/15 provide the capability of carrying on a conversation while the drilling unit is
being navigated.

11.11 Fire Extinguishing System


Fire main system, main fire pumps, emergency fire pump, and foam pump are to operate satisfactorily
throughout the sea trial period.
Satisfactory operation of the fixed fire-water extinguishing system is to be demonstrated during the sea
trial with main fire pumps and the emergency fire pump. This includes confirmatory testing of the system
output pressure from fire hoses coupled to two separate hydrants located as far away from each other as
practicable, where one of which is to be at the drill floor. Minimum pressure measured at each fire hose
nozzle is to be 3.5 bar (3.5 kgf/cm2, 50 psi) and the maximum pressure shall be such that the effective
control of a fire hose by crew can be demonstrated.

11.13 Main Source of Power


Main source of power is to operate satisfactorily throughout the sea trial period. No specific testing is
required.
11.15 Emergency Source of Power
Automatic start of the emergency source of power is to be demonstrated during the sea trial. On SelfPropelled drilling units, this test is to be demonstrated preferably whilst the drilling unit is in motion and at
least in a dead-slow speed.

92

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

7
1
9

Surveys
Surveys During Construction
Surveys at Builders Yard Sea Trial

7-1-9

11.17 Distribution System


Main distribution system, hull return system, earthed distribution systems, external or shore power supply
connection, and harmonics, are to operate satisfactorily throughout the sea trial period. No specific testing is
required.
11.19 Circuit Protection System
Protection for generators, accumulator batteries, external or shore power supply, motor branch circuits,
transformer circuits, meters, pilot lamps and control circuits, are to operate satisfactorily throughout the sea
trial period. No specific testing is required.
11.21 Lighting and Navigation Light Systems
General lighting, emergency lighting, obstruction lights, helicopter landing lights and navigation lights are
to operate satisfactorily throughout the sea trial period.
The entire installation is to operate to the satisfaction of the Surveyor and the drop in voltage on any part of
the installation is not to exceed 6%.
Satisfactory operation the emergency lights after a black-out condition is to be confirmed. Sufficient
lighting in all control stations, egress routes, and embarkation stations are to be verified.

11.23 Public Address (PA) and General Alarm (GA) Systems


The PA system is to operate satisfactorily throughout the sea trial period. Satisfactory operation is to be
verified during the trial by random activation/testing of the system. With the drilling unit underway or in
normal operating conditions, the minimum sound levels for broadcasting emergency announcements are to be:
i)

In interior locations, 75 dB (A) and at least 20 dB (A) above the speech interference level

ii)

In exterior locations, 80 dB (A) and at least 15 dB (A) above the speech interference level

Particular attention is to be paid to machinery/working spaces where normal noise level is higher than
other areas of the drilling unit.
The GA system is to be clearly audible in all parts of the unit. The alarm is to continue to function after it
has been triggered until it is manually turned off or is temporarily interrupted by a message on the public
address system. The GA system is to operate satisfactorily throughout the sea trial period. Satisfactory
operation is to be verified during the trial by random activation/testing of the system. With the drilling unit
underway or in normal operating conditions, the minimum sound levels of the alarm is to be:
i)

The minimum sound levels for the emergency alarm tone in interior spaces are to be 80 dB and at
least 10 dB (A) above ambient noise levels existing during normal equipment operation in moderate
weather. In cabins without a loud speaker installation, an electrical alarm transducer is to be installed.

ii)

The sound levels at the sleeping position in cabins and in cabin bathrooms are to be at least 75 dB
(A) and at least 10 dB (A) above ambient noise levels.

11.25 Fire Protection and Fire Detection Systems


Emergency stops and emergency shutdown system is to be verified during the trial by random
activation/testing.
Fire detection system is to operate satisfactorily throughout the sea trial period. Satisfactory operation of
the system and its alarms is to be verified during the trial by random activation/testing of the system.
Particular attention is to be paid to machinery/working spaces where normal noise level is higher than
other areas of the drilling unit.

11.27 Gas Detection System


Gas detection system is to operate satisfactorily throughout the sea trial period. Satisfactory operation of
the system and its alarms is to be verified during the trial by random activation/testing of the system.
Particular attention is to be paid to machinery/working spaces where normal noise level is higher than
other areas of the drilling unit.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

93

Part
Chapter
Section

7
1
9

Surveys
Surveys During Construction
Surveys at Builders Yard Sea Trial

7-1-9

13

Sea Trial for Self-Propelled Drilling Units

13.1

Full Power Trial


A final under-way full-power trial is to be made of all machinery required for propulsion, the steering gear
and the anchor windlass.
For surface-type and self-elevating units, the trial is to be conducted at the draft corresponding to the
minimum freeboard.
For column-stabilized and self-elevating drilling units, the trial is to be conducted at transit draft or as near
transit draft as practicable.

13.3

Reduced Power Trial


Column-stabilized units are to conduct final under-way reduced-power trial of all machinery required for
propulsion at a design operating draft to the satisfaction of the Surveyor.

13.5

Operation of Machinery, Electrical Systems and Safety Features


The operation of other machinery, electrical systems and safety features required by the Rules is to be
demonstrated to the satisfaction of the Surveyor.

13.7

Dead-Ship Start
Restoring the propulsion system from a dead ship condition is to be demonstrated.
The emergency source of electrical power may be used to restore the propulsion, provided its capacity
either alone or combined with that of any other available source of electrical power is sufficient to provide
at the same time those services required to be supplied by 4-3-2/5.3.1 through 4-3-2/5.3.7.
The emergency source of electrical power and other means needed to restore the propulsion are to have a
capacity such that the necessary propulsion starting energy is available within 30 minutes of blackout, as
defined in 4-1-1/10.1. Emergency generator stored starting energy is not to be directly used for starting the
propulsion plant, the main source of electrical power and/or other essential auxiliaries (emergency
generator excluded).

13.9

Steering Gear Trial


Power supply feeder, protection for steering gear motor circuit, emergency power supply, controls,
instrumentation, and alarms, are to operate satisfactorily throughout the sea trial period. Verification of the
emergency power supply, controls, instrumentation, and alarms is to be to the satisfaction of the attending
Surveyor.
The steering gear is to be capable of:
i)

Putting the rudder from 35 on one side to 35 on the other side with the vessel running ahead at
the maximum continuous rated shaft rpm and at the summer load waterline and, under the same
conditions, from 35 on either side to 30 on the other side in not more than 28 seconds; and

ii)

With one of the power units inoperative, putting the rudder from 15 on one side to 15 on the
other side in no more than 60 seconds with the vessel running ahead at the summer load waterline
at one half of the maximum ahead service speed or 7 knots, whichever is the greater.

The steering gear trial is to be performed with the rudder fully submerged. Where full rudder submergence
cannot be obtained in ballast conditions, alternative procedures for trials with less than full rudder submergence
are to be submitted for consideration.

94

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

7
1
9

Surveys
Surveys During Construction
Surveys at Builders Yard Sea Trial

7-1-9

13.9.1 Full Speed Trial


Satisfactory performance is to be demonstrated under the following conditions:

i)

Changing the rudder position from 35 on either side to 30 on the other side in not more
than 28 seconds with the vessel running ahead at the maximum continuous rated shaft
rpm. For controllable pitch propellers, the propeller pitch is to be at the maximum design
pitch approved for the above maximum continuous ahead rated rpm.

ii)

Unless 7-1-9/13.9.2iii) is applicable, this test is to be carried out with all power units
intended for simultaneous operation for this condition under actual operating conditions.

13.9.2 Half Speed Trial


Satisfactory performance is to be demonstrated under the following conditions.

i)

Changing the rudder position from 15 on either side to 15 on the other side in not more
than 60 seconds while running at one-half of the maximum ahead speed or 7 knots whichever
is the greater.

ii)

This test is to be conducted with either one of the power units used in 7-1-9/13.9.1ii) in
reserve.

iii)

Half Speed Trial may be waived where the steering gear consists of two identical power
units with each capable of meeting the requirements in 7-1-9/13.9.1i).

13.9.3 Steering Gears with More than Two Power Units


Where three or more power units are provided, the test procedures are to be specially considered
on the basis of the specifically approved operating arrangements of the steering gear system.
13.9.4 Drilling Units Fitted with Propellers
The designed performance of the propeller at rated speed is to be demonstrated during sea trial.
13.9.5 Drilling Units Fitted with Azimuthal Thrusters
Steering systems for azimuthal thrusters are to meet the requirements of Section 4-3-4 of the Steel
Vessel Rules, as applicable, and the following requirements.

i)

For drilling units that are arranged with only one azimuthal thruster as the only means of
propulsion and steering, the thruster is to be provided with steering systems of a redundant
design such that a single failure in one system does not affect the other system.

ii)

For drilling units that are arranged with two azimuthal thrusters as the only means of
propulsion and steering, each thruster is to be provided with at least one steering system.
The steering system for each thruster is to be independent of the steering system for the
other thruster.

iii)

Each azimuthal thruster is to be capable of rotating at a speed of not less than 0.4 rpm
(from 35 degrees on either side to 30 degrees on the other side in not more than 28 seconds)
while steering the vessel with the vessel running ahead at the maximum continuous rated
shaft rpm and at the summer load waterline. Where the azimuthal thruster is arranged to
rotate for the crash stop or astern maneuver, the azimuthal thruster is to be capable of
rotating at the speed of not less than 2.0 rpm (180 degrees in not more than 15 seconds) to
account for the crash stop or astern maneuver.

13.9.6 Additional Items


The trial is also to include the operation and verification of the following:

i)

The power units, including transfer between power units

ii)

The emergency power supply, if applicable

iii)

The steering gear controls, including transfer of control and local control

iv)

The means of communication between the navigation bridge, engine room and the steering
gear compartment

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

95

Part
Chapter
Section

7
1
9

Surveys
Surveys During Construction
Surveys at Builders Yard Sea Trial

7-1-9

v)

The alarms and indicators required by 4-3-4/15 of the Steel Vessel Rules (test may be
done at dockside)

vi)

The storage and recharging system in 4-3-4/9.3 of the Steel Vessel Rules (test may be
done at dockside)

vii)

The isolation of one power actuating system and time for regaining steering capability
(test may be done at dockside)

viii)

Where the steering gear is designed to avoid hydraulic locking (4-3-4/9.1.3 of the Steel
Vessel Rules), this feature is to be demonstrated.

ix)

Where practicable, simulation of a single failure in the hydraulic system, and demonstration
of the means provided to isolate it and the regaining of steering capability, as in 4-3-4/5.5
and 4-3-4/9.1.3 of the Steel Vessel Rules.

x)

The stopping of the steering gear before the rudder stop is reached, as in 4-3-4/5.11 of the
Steel Vessel Rules.

13.11 Interior Communication Systems for Self-Propelled Units


Interior communication between the navigation bridge and main control stations is to operate satisfactorily
throughout the sea trial period. Satisfactory operation is to be verified during the propulsion trial.
The voice communication system is to be verified to provide the capability of carrying on a conversation
while the drilling unit is being navigated.

15

Anchoring/Mooring Trial
Where optional ABS symbols , or are requested, the drilling unit is to undergo trials to prove its
capability as applicable. For further details, see Appendix 7-1-A1 of these Rules.

15.1

Anchoring/Mooring System Foundations


Although the mooring system is an optional scope of classification, drilling units hull back-up structure/
foundations are required to be surveyed in compliance with ABS approved drawings, in presence of and to
the satisfaction of the attending Surveyor.
Proper fit-up, alignment and final weldments of hull foundations for mooring winches, fairleads and other
mooring system components are to be visually examined. Completed welds are to be subjected to surface
NDT (preferably Magnetic Particle Inspection) to the extent deemed necessary by the attending Surveyor,
before the drilling unit commences its mooring trial.

15.3

Anchor Windlass Trials


Each anchor windlass is to be tested under working conditions after installation onboard to demonstrate
satisfactory operation. Each unit is to be independently tested for braking, clutch functioning, lowering and
hoisting of chain cable and anchor, proper riding of the chain over the chain lifter, proper transit of the
chain through the hawse pipe and the chain pipe, and effecting proper stowage of the chain and the anchor.
It is to be confirmed that anchors properly seat in the stored position and that chain stoppers function as
designed if fitted.
The mean hoisting speed, as specified in 4-5-1/5.1.4 of the Steel Vessel Rules, is to be measured and
verified, with each anchor and at least 82.5 m (45 fathoms) length of chain submerged and hanging free.
The braking capacity is to be tested by intermittently paying out and holding the chain cable by means of
the application of the brake. Where the available water depth is insufficient, the proposed test method will
be specially considered.

96

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

17

7
1
9

Surveys
Surveys During Construction
Surveys at Builders Yard Sea Trial

7-1-9

Dynamic Positioning System (DPS)


Dynamic Positioning System is to be subjected to trial in presence of and to the satisfaction of the Surveyor,
and the test items mentioned in 7-1-9/17.3 are to demonstrate that each item of plant and the system as a
whole is satisfactory for drilling units service after construction.

17.1

Failure Mode and Effect Analysis (FMEA)


The purpose of an FMEA is to give a description of the difference failure mode of the equipment referred
to its function tasks. Drilling units classed with the DPS-2 or DPS-3 notations are required to have their
FMEA plans and data reviewed by ABS.

17.3

DP Trials
A detailed DP trial program, that includes schedule of tests, is to be submitted for ABS review prior to the
proposed date of testing. The DP trial program is to be prepared to demonstrate the level of redundancy
established in FMEA, as applicable.
The test environment is to reflect the limiting design operating conditions, as far as practicable. The DP
trial is to be a complete performance test of the dynamic positioning system, and to at least include the
following testing/verification:
i)

The complete DP system is to be tested in all operation modes, with simulation of different failure
conditions to try switching modes, backup system and alarm system such as:

Fail each automatic control computer at main station.

Verified automatic changeover to stand by DP control computer without manual intervention


and without any adverse effect on station keeping.

Fail two automatic control computers.

Verify manual changeover from automatic control system to back up automatic control computer
at emergency DP control station.

Verify manual changeover from automatic control system to independent joystick.

Computer program verification if single fault including loss of thruster or thruster group
(based on FMEA), sufficient thruster remains available in steady state and transient conditions.

ii)

Manual override is to be demonstrated during normal operation and failure conditions.

iii)

Resubmitted results for approval may be necessary if significant differences in expected/actual


results are found.

iv)

If transient excursion occurs, submit analysis of worst case not to exceed distance endangering
safe operation of vessel (Operation Envelope).

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

97

PART

Appendix 1: Mooring Equipment and Systems

CHAPTER

Survey During Construction

APPENDIX

Mooring Equipment and Systems

General
On self-propelled vessels, the symbol is required as a condition of classification and therefore it is a
mandatory to comply with the ABS Rules. On vessels that are not self-propelled (i.e., without the AMS
notation), the is an optional symbol that may be requested by the owner.
The symbols and are not required as a condition of classification. These are optional symbols that
may be requested by the owner.
All mooring equipment associated with below class symbols are to be fabricated and certified by ABS at
manufacturers facility. Installation of the mooring equipment/system is to be carried out in presence of
and to the satisfaction of the attending Surveyor. The mooring system is to be tested, per an agreed test
procedure, during sea trial of the unit.

1.1

Anchoring (Temporary Mooring) Equipment


The symbol is placed after the symbols of classification in the Record, thus: A1 , which will
signify that the equipment for anchoring (temporary mooring) of the drilling unit is in compliance with the
applicable requirements of Section 3-5-1 of the Steel Vessel Rules or of Section 3-3-1 of the Barge Rules.
This requirement may be met if position mooring equipment can be released in an emergency while the
unit is in the transit mode.
Fabrication tests of the mooring equipment; such as anchors, chains, wires, shackles, etc. are to be in
accordance with the ABS Rules for Materials and Welding (Part 2) for the respective sizes of equipment.
See Section 2-2-1 and Section 2-2-2.

1.3

Position Mooring Equipment


When requested by the owner, the symbol may be placed after the symbols of classification in the Record,
thus: A1 , which will signify that the mooring equipment, anchors, chain or wire rope which have
been specified by the owner for position mooring have been tested in accordance with the specifications of
the owner and in the presence of a Surveyor.
Fabrication tests of the position mooring equipment; such as anchors, chains, wires, shackles, etc. are to at
least satisfy the requirements of the ABS Rules for Materials and Welding (Part 2) for the respective sizes
of equipment. See Section 2-2-1 and Section 2-2-2. Compliance with ABS Guide for Certification of
Offshore Mooring Chain and the use of at least ABS RQ quality chains is also required.
In addition, it is to be confirmed that the position mooring equipment is in compliance with the owners
specification.

1.5

98

Position Mooring Systems


When requested by the owner, ABS is prepared to certify the position mooring capability of the unit in
accordance with the requirements outlined in Appendix 3-4-A1. A unit so certified for position mooring
will be designated in the Record by the symbol placed after the symbols of classification in the Record,
thus: A1 .

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
7
Chapter 1
Appendix 1

Surveys
Survey During Construction
Mooring Equipment and Systems

7-1-A1

Mooring System Foundations


Drilling units hull back-up structure/foundations are required to be surveyed in compliance with ABS
approved drawings, in presence of and to the satisfaction of the attending Surveyor.
Proper fit-up, alignment and final weldments of hull foundations for mooring winches, fairleads and other
mooring system components are to be visually examined. Completed welds are to be subjected to surface
NDT (preferably Magnetic Particle Inspection) to the extent deemed necessary by the attending Surveyor,
prior to the sea trial.

Mooring Trial
Mooring trial is to be carried out in accordance with ABS reviewed mooring trial test procedures, in
presence of and to the satisfaction of the attending Surveyor.

5.1

Anchoring (Temporary Mooring) Equipment


Each anchor windlass is to be tested under working conditions after installation onboard to demonstrate
satisfactory operation. Each unit is to be independently tested for braking, clutch functioning, lowering and
hoisting of chain cable and anchor, proper riding of the chain over the chain lifter, proper transit of the
chain through the hawse pipe and the chain pipe, and effecting proper stowage of the chain and the anchor.
It is to be confirmed that anchors properly seat in the stored position and that chain stoppers function as
designed if fitted. The mean hoisting speed, as specified in 4-5-1/5.1.4 of the Steel Vessel Rules, is to be
measured and verified, with each anchor and at least 82.5 m (45 fathoms) length of chain submerged and
hanging free. The braking capacity is to be tested by intermittently paying out and holding the chain cable
by means of the application of the brake. Where the available water depth is insufficient, the proposed test
method will be specially considered.

5.3

Position Mooring Equipment


The mooring system is to be tested under working conditions after installation onboard to demonstrate
satisfactory operation. Each unit is to be independently tested for braking, clutch functioning, lowering and
hoisting of chain cable and anchor, proper riding of the chain over the chain lifter, proper transit of the
chain through the hawse pipe and the chain pipe, and effecting proper stowage of the chain and the anchor.

5.5

Position Mooring System


The position mooring system is to be tested under working conditions after installation onboard to
demonstrate satisfactory operation. It is to be confirmed that the position mooring system is in compliance
with Owners specification and operates within required parameters specified by the Owner.
5.5.1

Control Stations for Position Mooring Systems


Following provisions are to be confirmed during the position mooring system trials:

i)

Suitable equipment to indicate anchor line tensions, wind speed and direction at a manned
central control station.

ii)

Reliable means of communication between locations critical to the anchoring operation.

iii)

Controls of each winch or windlass from a position which provides a good view of the
operation, and suitable equipment at each winch or windlass control positions to monitor
anchor line tension, winch or windlass power load, and to indicate the amount of anchor
line paid out.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

99

PART

Appendix 2: Surveys of Computers for Stability Calculations

CHAPTER

Surveys During Construction

APPENDIX

Surveys of Computers for Stability Calculations

General
This Appendix pertains to surveys and testing to be carried out on onboard computers for stability calculations.
As mentioned in 7-1-1/23, the use of onboard computers for stability calculations is not a requirement of
class, it is optional. However, if software is installed onboard for calculating stability of the unit, it is to be
surveyed and tested in presence of and to the satisfaction of the attending Surveyor.
Following subsections describe the requirements for survey of onboard computers. Satisfactory ABS design
review of the computer, in accordance with Appendix 3-3-A2 of the MODU Rules, is to be completed
before surveys are commenced onboard the unit.

Functional Requirements

3.1

Calculation Program
The calculation program is to present relevant parameters of each operating condition in order to assist the
Master in his judgment on whether the drilling unit is loaded within the approval limits. The following
parameters are to be presented for a given operating condition:

Deadweight data

Lightship data

Trim

Draft at the draft marks and perpendiculars

Summary of operating condition displacement, VCG, LCG and, if applicable, TCG

Down-flooding angle and corresponding down-flooding opening

Compliance with stability criteria: Listing of all calculated stability criteria, the limit values, the obtained
values and the conclusions (criteria fulfilled or not fulfilled)

If direct damage stability calculations are performed, the relevant damage cases according to the applicable
rules are to be pre-defined for automatic check of a given operating condition.

3.3

100

Computer Data/Indicators
The computer is to satisfy following requirements during operating condition.
3.3.1

Warning
A clear warning is to be given on screen and in hard copy printout if any of the operating limitations
are not complied with.

3.3.2

Data Printout
The data are to be presented on screen and in hard copy printout in a clear unambiguous manner.

3.3.3

Date and Time


The date and time of a saved calculation are to be part of the screen display and hard copy printout.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
7
Chapter 1
Appendix 2

Surveys
Survey During Construction
Surveys of Computers for Stability Calculations

7-1-A2

3.3.4

Information of Program
Each hard copy printout is to include identification of the calculation program with version number.

3.3.5

Units
Units of measurement are to be clearly identified and used consistently within an operating calculation.

Operation Manual
An ABS reviewed operation manual is to be placed onboard the unit and verified by the Surveyor. The
operation manual is to contain descriptions and instructions, as appropriate, for at least the following:

i)

Installation

ii)

Function keys

iii)

Menu displays

iv)

Input and output data

v)

Required minimum hardware to operate the software

vi)

Use of the test operating conditions

vii)

Computer-guided dialogue steps

viii)

List of warnings

Installation Testing
To ensure correct working of the computer after the final or updated software has been installed, it is the
responsibility of the drilling units master to have test calculations carried out according to the following
pattern in the presence of the Surveyor:
i)

From the approved test conditions at least one load case (other than lightship) is to be calculated.
Note:

ii)

7.1

Actual operating condition results are not suitable for checking the correct working of the computer.

Normally, the test conditions are permanently stored in the computer.

Installation Test Steps to be Performed


Following test steps are to be performed in presence of and to the satisfaction of the attending Surveyor:
i)

Retrieve the test load case and start a calculation run; compare the stability results with those in
the documentation.

ii)

Change several items of deadweight sufficiently to change the draft or displacement by at least
10%. The results are to be reviewed to ensure that they differ in a logical way from those of the
approved test condition.

iii)

Revise the above modified load condition to restore the initial test condition and compare the
results. The relevant input and output data of the approved test condition are to be replicated.

iv)

Alternatively, one or more test conditions shall be selected and the test calculations performed by
entering all deadweight data for each selected test condition into the program as if it were a
proposed loading. The results shall be verified as identical to the results in the approved copy of
the test conditions.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

101

PART

Chapter 2: Surveys After Construction

CHAPTER

Surveys After Construction

CONTENTS
SECTION 1

Conditions for Surveys After Construction ..................................... 109


1
Application.......................................................................................109
1.1

Definitions .......................................................................................109
3.1

Ballast Tank ................................................................................. 109

3.2

Coating Condition ........................................................................ 109

3.3

Corrosion ..................................................................................... 110

3.5

Corrosion Control System ............................................................ 110

3.7

Critical Structural Areas ............................................................... 110

3.9

Girth Belt (Transverse Section) ................................................... 110

3.11

Panel ........................................................................................... 110

3.13

Survey ......................................................................................... 111

3.15

Representative Spaces/Tanks ..................................................... 111

3.17

Spaces ......................................................................................... 111

3.19

Suspect Areas ............................................................................. 111

3.21

Wind and Water Strakes .............................................................. 111

Notification and Availability for Survey ............................................111

Damage, Failure and Repair ...........................................................111

7.1

Examination and Repair .............................................................. 111

7.3

Repairs ........................................................................................ 112

7.5

Representation ............................................................................ 112

7.7

Application of Rules ..................................................................... 112

Alterations/Modifications .................................................................112
9.1

11

Application of Rules ..................................................................... 112

Welding and Replacement of Materials ..........................................113


11.1

Ordinary and Higher-Strength Structural Steels .......................... 113

11.3

Special Materials ......................................................................... 113

13

Incomplete Surveys ........................................................................113

15

Lay-up and Reactivation .................................................................113

17

102

Chapter 2 Sections 1 through 11 ................................................. 109

15.1

Units for Unrestricted Service ...................................................... 113

15.3

Units Operating in Fresh Water ................................................... 113

Onboard Drawings and Manuals ....................................................114


17.1

Documents Reviewed and Stamped by ABS Engineering........... 114

17.3

Documents Issued, Reviewed, and/or Endorsed by ABS


Surveyor ...................................................................................... 115

17.5

Survey Planning Document (SPD)............................................... 115

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

19

SECTION 2

SECTION 4

19.1

Safe Access ................................................................................ 115

19.3

Accessing Spaces at Sea ............................................................ 116

19.5

Housekeeping (Cleanliness)........................................................ 116

19.7

Illumination and Ventilation.......................................................... 116

19.9

Sea Trials and/or Stability Test.................................................... 117

Survey Intervals ................................................................................. 118


1
Units Unrestricted Service ........................................................... 118

SECTION 3

Preparations for Safe Execution of Surveys ................................... 115

1.1

Annual Surveys ........................................................................... 118

1.3

Special Periodical Surveys .......................................................... 118

1.5

Continuous Surveys .................................................................... 118

1.7

In-line Surveys ............................................................................. 119

1.9

Drydocking Survey or Equivalent ................................................ 119

1.11

Tail Shaft Surveys ....................................................................... 119

1.13

Auxiliary Boiler Surveys ............................................................... 120

Units Operating in Fresh Water ...................................................... 120

Survey Pre-Planning .......................................................................... 121


1
Drydocking Surveys and Special Surveys ...................................... 121
1.1

Plan for UWILD ........................................................................... 121

1.3

Plan for Out-of-Water Drydocking and Special Periodical


Survey ......................................................................................... 121

1.5

Survey Planning Document (SPD) .............................................. 121

1.7

Critical Structural Areas ............................................................... 122

Annual Surveys .................................................................................. 123


1
Annual Survey Hull ...................................................................... 123

1.1

All Types of Mobile Offshore Drilling Units .................................. 123

1.3

Surface-Type Units ...................................................................... 125

1.5

Column-Stabilized Units .............................................................. 125

1.7

Self-Elevating Units ..................................................................... 125

Annual Survey Machinery and Electrical Systems ...................... 125


3.1

Non-Self-Propelled Units ............................................................. 125

3.3

Self-Propelled Units ..................................................................... 125

3.5

Examination during Overhaul ...................................................... 125

3.7

Examination at Shorter Intervals ................................................. 125

Annual Survey Preventative Maintenance Program (PMP)......... 125

Annual Survey Thrusters for APS or PAS Notations ................... 126


7.1

Thruster System (APS or PAS) ................................................... 126

Annual Survey Dynamic Positioning Systems ............................. 126


9.1

Units classed with DPS-0, DPS-1, DPS-2, DPS-3 Notations....... 127

TABLE 1

Thruster Power System ........................................................ 128

TABLE 2

Power Distribution System .................................................... 129

TABLE 3

System Performance ............................................................ 129

TABLE 4

Additional Alarms and Instruments for DPS-2 and DPS-3 ... 129

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

103

SECTION 5

Special Periodical Surveys ................................................................ 130


1
All Types of Units Special Periodical Survey Hull .....................130

11

13

104

1.1

General Visual Inspection (GVI) .................................................. 130

1.3

Close Visual Inspection (CVI) ...................................................... 131

1.5

Nondestructive Testing (NDT) ..................................................... 131

1.7

Hull Thickness Measurement (Gauging) ...................................... 132

1.9

Corrosion Control......................................................................... 132

1.11

Onboard Computers for Stability Calculations ............................. 133

1.13

Alternatives .................................................................................. 133

Surface-Type Drilling Units .............................................................133


3.1

Special Periodical Survey Hull No. 1 ........................................ 133

3.3

Special Periodical Survey Hull No. 2 ........................................ 134

3.5

Special Periodical Survey Hull No. 3 ........................................ 136

3.7

Special Periodical Survey Hull No. 4 and Subsequent Special


Surveys ........................................................................................ 137

Column-Stabilized Drilling Units .....................................................137


5.1

Special Periodical Survey Hull No. 1 ........................................ 137

5.3

Special Periodical Survey Hull No. 2 ........................................ 139

5.5

Special Periodical Survey Hull No. 3 ........................................ 140

5.7

Special Periodical Survey Hull No. 4 and Subsequent Special


Surveys ........................................................................................ 142

Self-Elevating Drilling Units.............................................................143


7.1

Special Periodical Survey Hull No. 1 ........................................ 143

7.3

Special Periodical Survey Hull No. 2 ........................................ 144

7.5

Special Periodical Survey Hull No. 3 ........................................ 146

7.7

Special Periodical Survey Hull No. 4 and Subsequent Special


Surveys ........................................................................................ 148

Special Periodical Survey Machinery ..........................................151


9.1

Correlation with Special Periodical Survey Hull ........................ 151

9.3

Parts to be Examined All Types of Mobile Offshore Drilling


Units ............................................................................................ 151

9.5

Parts to be Examined Self-Propelled Mobile Offshore Drilling


Units ............................................................................................ 152

Special Periodical Survey Electrical Equipment ..........................152


11.1

Correlation with Special Periodical Surveys Hull ...................... 152

11.3

Parts to be Examined .................................................................. 152

11.5

Self Propelled Units Main Propulsion Apparatus ...................... 153

11.7

Major Repairs .............................................................................. 153

Special Periodical Survey Special Features (All Types)..............153


13.1

Correlation with Special Periodical Surveys Hull ...................... 153

13.3

Hazardous Areas ......................................................................... 153

13.5

Remote Shutdown Arrangements ................................................ 154

13.7

Passive Fire Protection System ................................................... 154

13.9

Active Fire Protection Systems and Equipment ........................... 154

13.11

Outfitting ...................................................................................... 155

13.13

Piping Systems Supporting the Drilling System ........................... 155

13.15

Self-Elevating Drilling Units Leg Jacking Systems .................... 155

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

15

SECTION 6

Thrusters and Dynamic Position Systems ...................................... 155


15.1

Units Classed with APS or PAS Notations .................................. 155

15.3

Units Classed with DPS-1, DPS-2, or DPS-3 Notations .............. 155

TABLE 1

Thickness Gauging Requirements for Surface-Type


Units ...................................................................................... 149

TABLE 2

Thickness Gauging Requirements for Column-Stabilized


Units ...................................................................................... 150

TABLE 3

Thickness Gauging Requirements for Self-Elevating


Units ...................................................................................... 151

FIGURE 1

CVI and NDT during SPS Hull No. 2 of Drillships ................. 135

FIGURE 2

CVI and NDT during SPS Hull No. 3 of Drillships ................. 136

FIGURE 3

CVI and NDT during SPS Hull No. 3 of CSDUs ................... 141

FIGURE 4

CVI and NDT during SPS Hull No. 4 of CSDUs ................... 142

FIGURE 5

CVI and NDT during SPS Hull No. 2 of SEDUs.................... 145

FIGURE 6

CVI and NDT during SPS Hull No. 3 of SEDUs.................... 147

Drydocking Surveys or Equivalent ................................................... 157


1
Parts to be Examined...................................................................... 157

1.1

Surface-type Units (Ship or Barge Type Units)............................ 157

1.3

Column-Stabilized Units .............................................................. 157

1.5

Self-Elevating Units ..................................................................... 157

1.7

Ballast and Preload Spaces All units ........................................ 158

1.9

All Units ....................................................................................... 158

Underwater Inspection in Lieu of Drydocking (UWILD) .................. 159


3.1

Conditions ................................................................................... 159

3.3

Physical Features ........................................................................ 159

3.5

Procedures .................................................................................. 160

3.7

Crediting UWILD on a Self-Elevating Drilling Unit without


Completing the Examination of Spud Cans/Mat .......................... 160

3.9

Incomplete UWILD over a Five-Year Period Self-Elevating


Drilling Units ................................................................................ 160

3.11

Alternatives (2016) ...................................................................... 161

TABLE 1

Examination of Mat or Spud Cans during Drydocking


Survey ................................................................................... 157

SECTION 7

Specific Survey on Self-Elevating Units After Ocean Transit


Tow ...................................................................................................... 162
1
Ocean Transit Wet Tow .................................................................. 162
3
Ocean Transit Dry Tow ................................................................... 162

SECTION 8

Tail Shaft Surveys .............................................................................. 163

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

105

SECTION 9

Boiler Surveys .................................................................................... 164


1
Parts to be Examined......................................................................164
1.1

Internal and External Examination ............................................... 164

1.3

Mountings and Safety Valves ...................................................... 164

1.5

Operation of the Safety Valves .................................................... 164

1.7

Hydrostatic Pressure Testing ....................................................... 164

SECTION 10 Automatic and Remote-control Systems ......................................... 165


1
Annual Survey .................................................................................165
3
Special Periodical Surveys .............................................................165

3.1

Control Actuators ......................................................................... 165

3.3

Electrical ...................................................................................... 165

3.5

Unattended Plants ....................................................................... 165

Repairs or Alterations .....................................................................165

SECTION 11 Crew Habitability ................................................................................ 166


1
Annual Surveys ...............................................................................166
3
Special Periodic Surveys ................................................................166
3.1

Survey Requirements .................................................................. 166

Requirements for Vessel Alterations ..............................................167

APPENDIX 1 Lay-up and Reactivation of Laid-up Mobile Offshore Drilling


Units .................................................................................................... 168
1
Lay-up of Mobile Offshore Drilling Units .........................................168
1.1

Optional Verification of Lay-up ..................................................... 168

Reactivation of Mobile Offshore Drilling Units ................................168

APPENDIX 2 Survey of Portable Modules .............................................................. 169


1
General ...........................................................................................169
3
Survey of Portable Accommodation Modules .................................169
5
Survey of Portable Industrial Modules ............................................169
7
Certification of Drilling Unit Fitted with Portable Industrial
Modules...........................................................................................170
APPENDIX 3 Modification of a Self-Elevating Drilling Unit to Become
Site-Specific Fixed Offshore Installation .......................................... 171
1
General ...........................................................................................171
3
Application.......................................................................................171

106

3.1

Rules for Building and Classing Offshore Installations


(Offshore Installation Rules) ........................................................ 171

3.3

Rules for Building and Classing Mobile Offshore Drilling Units


(MODU Rules) ............................................................................. 171

3.5

Rules for Building and Classing Floating Production


Installations (FPI Rules) ............................................................... 171

3.7

Rules for Building and Classing Facilities on Offshore


Installations (Facilities Rules) ...................................................... 171

3.9

Guide for Building and Classing Floating Offshore Liquefied Gas


Terminals (FLGT Guide) .............................................................. 171

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Modification Survey......................................................................... 172


5.1

Hull .............................................................................................. 172

5.3

Jacking System ........................................................................... 172

5.5

Marine and Safety Systems......................................................... 172

5.7

Topside Systems ......................................................................... 172

APPENDIX 4 Preventative Maintenance Program (PMP) ...................................... 173


1
General ........................................................................................... 173

11

13

1.1

Definitions.................................................................................... 175

1.3

PMP Additional Notation.............................................................. 175

1.5

Cancellation of PMP .................................................................... 175

PMP Compliance Criteria................................................................ 176


3.1

Surveys ....................................................................................... 176

3.3

Maintenance and ABS Survey Intervals ...................................... 176

3.5

Computerized Maintenance Management Systems .................... 176

Program Description ....................................................................... 176


5.1

General........................................................................................ 176

5.3

Implementation Surveys .............................................................. 177

5.5

ABS Survey Status Indicators ..................................................... 177

5.7

Maintenance of Onboard Documentation .................................... 177

Overhauls and Damage Repairs .................................................... 177


7.1

Overhauls .................................................................................... 177

7.3

Damage Repairs ......................................................................... 178

Planned Maintenance (PM) ............................................................ 178


9.1

Machinery Items not Allowed on PM ........................................... 178

9.3

Implementation Survey for PM .................................................... 179

9.5

Administrative Requirements for PM ........................................... 179

9.7

Onboard Documentation for PM .................................................. 179

Condition Monitoring (CM) .............................................................. 179


11.1

Machinery Items not Allowed on CM ........................................... 179

11.3

Implementation Survey for CM .................................................... 180

11.5

Administrative Requirements for CM ........................................... 180

11.7

Onboard Documentation for CM .................................................. 180

11.9

Alternative Techniques for CM .................................................... 180

PMP Surveys and Reports.............................................................. 180


13.1

Annual Confirmation Surveys ...................................................... 180

13.3

ABS Survey Report ..................................................................... 180

FIGURE 1

Machinery Enrolled into PMP................................................ 174

APPENDIX 5 Reliability Centered Maintenance (RCM).......................................... 182


1
General ........................................................................................... 182
1.1

Definitions.................................................................................... 182

1.3

RCM Analysis .............................................................................. 182

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

107

RCM Additional Notations ...............................................................183


3.1

RCM for Propulsion System ........................................................ 183

3.3

RCM for Cranes ........................................................................... 183

3.5

RCM for Dynamic Positioning System ......................................... 183

3.7

RCM Indicators ............................................................................ 183

RCM Implementation Surveys ........................................................183

Administrative Requirements for RCM ...........................................184

Onboard Documentation for RCM ..................................................184

TABLE 1

108

RCM Tasks ...........................................................................183

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

PART

Section 1: Conditions for Surveys After Construction

CHAPTER

Surveys After Construction

SECTION

Conditions for Surveys After Construction

Application (2010)

1.1

Chapter 2 Sections 1 through 11 (2016)


The requirements for Surveys After Construction contained in Part 7, Chapter 2, Sections 1 through 10,
and Appendices 1 through 3 apply to the:

Rules for Building and Classing Mobile Offshore Drilling Units (MODU Rules)

And are referenced by the following ABS Rules and Guides:

Guide for Building and Classing Mobile Offshore Units

Rules for Building and Classing Floating Production Installations

Guide for Automatic or Remote Control and Monitoring for Machinery and Systems (other than
Propulsion) on Offshore Installations

Certain requirements of the MODU Rules are based on the requirements of the ABS Rules for Building and
Classing Steel Vessels (Steel Vessel Rules).

Definitions (2010)

3.1

Ballast Tank
A Ballast Tank is a tank which is used primarily for the carriage of salt water ballast.

3.2

Coating Condition (2014)


Coating Condition of hard coatings is defined as follows:
GOOD Condition with spot breakdown on less than 5% of the area under consideration without visible
failure of the coating, or non-perforated blistering. Breakdown at edges or welds is to be less than 20% of
edges or weld lines in the area under consideration.
FAIR Condition with breakdown of coating or penetration on less than 20% of the area under consideration.
Total paint failure should be less than 10% of the area under consideration. Breakdown at edges or welds is
to be less than 50% of edges or weld lines in the area under consideration.
POOR Condition with breakdown of coating or penetration on more than 20% or on total paint failure
more than 10% of the area under consideration or local breakdown concentrated at edges or welds on more
than 50% of edges or weld lines in the area under consideration.
Note:

Reference is made to IMO MSC.1/Circ.1399 Guidelines on Procedures for In-Service Maintenance and Repair of
Coating Systems for Cargo Oil Tanks or Crude Oil Tankers, and the IACS Recommendation No.87 Guidelines
for Coating Maintenance & Repairs for Ballast Tanks and Combined Cargo/Ballast Tanks on Oil Tankers.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

109

Part
Chapter
Section

3.3

7
2
1

Surveys
Surveys After Construction
Conditions for Surveys After Construction

7-2-1

Corrosion
Active Corrosion means gradual chemical or electrochemical attack on a metal resulting from a reaction
with its environment and producing loose scale.
Allowable Corrosion or Wastage Limit is the acceptable corrosion limit for the MODUs structure in a
given area. Also known as Allowable Limit.
Excessive Corrosion is an extent of corrosion that exceeds the allowable limit.
Extensive Area of Corrosion is corrosion of hard and/or loose scale, including pitting, over 70% or more of
the plating surface in question, accompanied by evidence of thinning.
Grooving Corrosion is a localized, linear corrosion which occurs at structural intersections where water
collects or flows. This corrosion is sometimes referred to as in line pitting attack and can also occur on
vertical members and flush sides of bulkheads in way of flexing.
Localized Corrosion is by name local in nature and may be caused by local breakdown in coating from
contact damage, insufficient preparation, or at areas of stress concentration.
Overall Corrosion appears as a non-protective rust which can uniformly occur on tank internal surfaces
that are uncoated, or where coating has totally deteriorated. The rust scale continues to break off, exposing
fresh metal to corrosive attack. Thickness cannot be judged visually until excessive loss has occurred.
Pitting Corrosion is a localized corrosion of a metal surface that is confined to a small area and takes the
form of cavities called pits.
Substantial Corrosion is an extent of corrosion such that assessment of corrosion pattern indicates wastage
in excess of 75% of the allowable corrosion, but within the acceptable limits.
Weld Metal Corrosion is defined as preferential corrosion of weld deposit. The most likely reason for this
attack is galvanic action with the base metal which may start as pitting and often occurs on hand welds as
opposed to machine welds.

3.5

Corrosion Control System


Corrosion Control System may be achieved by application of hard protective coating (usually epoxy coating
or equivalent), soft protective coating, impressed current cathodic protection (ICCP) system, sacrificial anodes,
etc., provided that they are applied and maintained in compliance with the manufacturer's specification.

3.7

Critical Structural Areas (2014)


Critical Structural Areas are locations which have been identified from calculation to have relatively low
fatigue life and therefore may require monitoring or from the service history of the subject unit or from
similar sister units to be sensitive to cracking, buckling or corrosion which would impair the structural integrity
of the unit. The units service history since last survey may also have an effect on identified critical structural
areas.

3.9

Girth Belt (Transverse Section)


A Girth Belt includes the following;

3.11

110

Surface-Type Units: Deck, bottom, side shell and longitudinal bulkhead plating and internal framing.

Column-Stabilized Units: Column and bracing plating and internals as deemed necessary. Deck sides
and bottom of lower hulls between columns, including internal stiffeners as deemed necessary.

Self-Elevating Units: Deck, bottom, side shell, internal framing of preload tanks and leg well structure.

Panel
Panel is the area between adjacent main frames from stiffener to stiffener.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

3.13

7
2
1

Surveys
Surveys After Construction
Conditions for Surveys After Construction

7-2-1

Survey (2014)
Overall Survey is a survey intended to report on the overall condition of the structure and to determine the
extent of additional close-up surveys. Overall Survey may be referred by the industry as General Visual
Inspection (GVI).
A Close-up Survey is a survey where the details of structural components are within close visual inspection
range of the Surveyor (i.e., normally within hand reach). Close-up Survey may be referred by the industry
as Close Visual Inspection (CVI). In general, a GVI carried out in spaces will be supplemented by CVI
of special or primary application structures, or identified structural critical areas. CVI may be accompanied
by surface or volumetric Nondestructive Testing (NDT), and/or hull thickness measurement. Areas showing
corrosion may also be subjected to CVI.

3.15

Representative Spaces/Tanks
Representative Spaces/Tanks are those which are expected to reflect the condition of other spaces of
similar type and service and with similar corrosion preventive systems. When selecting representative spaces,
account should be taken of the service and repair history onboard and identifiable critical and/or Suspect
Areas.

3.17

Spaces
Spaces are separate compartments including tanks, cofferdams, machinery spaces, voids and other internal
spaces.

3.19

Suspect Areas
Suspect Areas are locations showing substantial corrosion and/or are considered by the Surveyor to be
prone to rapid wastage.

3.21

Wind and Water Strakes


Wind and Water Strakes are the two (2) strakes or equivalent area located in the vicinity of the load
waterline, operating draft or operating depth of the unit. For Self-elevating Units this is the area of the leg
components in the vicinity of the operating water depth. For column stabilized units this will include
portions of columns and bracing members in the vicinity of the operating draft of the unit.
3.21.1 Splash Zone (for Self-Elevating and Column Stabilized Units) (2012)
Splash Zone is the external surfaces of a self-elevating or column-stabilized unit that are
periodically in and out of the water when the unit at its operating depth.

Notification and Availability for Survey (2012)


The Surveyors are to have access to classed units at all reasonable times. The Owners or their representatives
are to notify the Surveyors on occasions when parts of the structure not ordinarily accessible can be
examined. The Surveyors are to undertake all surveys on classed units upon request, with adequate notification,
of the Owners or their representatives and are to report thereon to ABS. Should the Surveyors find
occasion during any survey to recommend repairs or further examination, notification is to be given
immediately to the Owners or their representatives in order that appropriate action may be taken. The
Surveyors are to avail themselves of every convenient opportunity for carrying out periodical surveys in
conjunction with surveys of damages and repairs in order to avoid duplication of work. See also 1-1-8/5 of
the ABS Rules for Conditions of Classification Offshore Units and Structures (Part 1).

Damage, Failure and Repair (1996)

7.1

Examination and Repair


Damage, failure, deterioration or repair to hull, legs, columns or other structures, machinery or equipment,
which affects or may affect classification, is to be submitted by the Owners or their representatives for
examination by a Surveyor at first opportunity. All repairs found necessary by the Surveyor are to be
carried out to the Surveyors satisfaction.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

111

Part
Chapter
Section

7.3

7
2
1

Surveys
Surveys After Construction
Conditions for Surveys After Construction

7-2-1

Repairs
Where repairs to hull, legs, columns or other structures, machinery or equipment, which affect or may
affect classification, are planned in advance to be carried out, a complete repair procedure, including the
extent of proposed repair and the need for Surveyors attendance, is to be submitted to and agreed upon by
ABS reasonably in advance. Failure to notify ABS in advance of the repairs may result in suspension of
the units classification until such time as the repair is redone or evidence submitted to satisfy the Surveyor
that the repair was properly carried out.
Note:

The above applies also to repairs during voyage or on site.

The above is not intended to include maintenance and overhaul to hull, other structures, machinery and
equipment in accordance with the recommended manufacturers procedures and established marine practice
and which does not require ABS approval. However, any repair as a result of such maintenance and
overhauls which affects or may affect classification is to be noted in the units log and submitted to the
Surveyor as required by 7-2-1/7.1.

7.5

Representation
Nothing contained in this section or in a rule or regulation of any government or other administration, or
the issuance of any report or certificate pursuant to this section or such a rule or regulation, is to be deemed
to enlarge upon the representations expressed in 1-1-1/1 through 1-1-1/7 of the ABS Rules for Conditions
of Classification Offshore Units and Structures (Part 1), and the issuance and use of any such reports or
certificates are to be governed in all respects by 1-1-1/1 through 1-1-1/7 of the above-referenced Part 1.

7.7

Application of Rules (2012)


As referenced in 1-1-3/1.3 of these Rules, the Rules that is applicable to the units classification is to be
applied to any repair without changing the original design, carried out on the units structure, machinery or
equipment, that affects or may affect classification. Application of up-to-date Rules will be specially
considered only when so requested by the Owner or required by these Rules.

Alterations/Modifications (2012)
No alteration or modification which affect or may affect classification or the assignment of load lines are
to be made to the hull or machinery of a classed unit unless plans of the proposed alterations are submitted
and approved by the ABS Technical Office before the work of alteration or modification is commenced,
and such work, when approved, is to be carried out to the satisfaction of the Surveyor. Nothing contained
in this Section or in a rule or regulation of any government or other administration or the issuance of any
report or certificate pursuant to this section or such a rule or regulation is to be deemed to enlarge upon the
representations expressed in subsections 1-1-1/1 through 1-1-1/7 ABS Rules for Conditions of Classification
Offshore Units and Structures (Part 1) and the issuance and use of any such reports or certificates are to in
all respects be governed by subsections 1-1-1/1 through 1-1-1/7 of the above-referenced Part 1.

9.1

Application of Rules
As referenced in 1-1-3/1.3 of these Rules, the Rules that is applicable to the units classification is to be
applied to minor alteration/modification carried out on the unit, including its structure, machinery or equipment,
that affects or may affect classification. Application of up-to-date Rules will be specially considered only
when so requested by the Owner or required by these Rules.
The following cases may be considered as a major alteration or modification, and therefore require
compliance with up-to-date Rules for the section being altered or modified:

Changing configuration or material of structure that is defined as Special Application Structure or


Primary Application Structure in accordance with these Rules.
Note:

112

A cantilever extension is not considered to be a major modification.

Changing leg jacking system of self elevating units.

Changing a marine piping system (such as the ballast systems, bilge system, propulsion system, etc.)
with all of its components (piping, valves, pumps, etc.).
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

7
2
1

Surveys
Surveys After Construction
Conditions for Surveys After Construction

7-2-1

Changing a marine electrical system (such as the main power distribution, emergency power distribution,
electrical propulsion system, etc.) with all of its components (cabling, electrical motors/pumps, panels, etc.).

Changing layout and material used in the passive fire protection system, such as more than 10% of
deck area alteration or modification to the footprint of the accommodation deckhouse/superstructure or
its material used for fire protection.
Note:

Adding another deck on top of an existing accommodation deckhouse is not considered to be a major modification
of the entire deckhouse.

Changing an active fire protection system (such as the fixed-fire fighting system, fire and gas detection
system, etc.) with all of its components (piping, pumps, hoses, panels, alarms, detectors, etc.).

11

Welding and Replacement of Materials

11.1

Ordinary and Higher-Strength Structural Steels


Welding or other fabrication performed on the structural steels listed in 2-1-2/Table 5 and 2-1-3/Table 5 is
to be in accordance with the requirements in Section 2-4-1 of the ABS Rules for Materials and Welding
(Part 2).

11.3

Special Materials
Welding or other fabrication performed on other steels of special characteristics or repairs or renewals of
such steel or adjacent to such steel is to be accomplished with procedures approved for the special
materials involved. The procedures are to be in accordance with the information provided under 7-1-2/25
and Chapter 4 of the ABS Rules for Materials and Welding (Part 2). Substitution of steels differing from
those originally installed is not to be made without approval.

13

Incomplete Surveys (2012)


When a survey is not completed, the Surveyor is to report immediately upon the work done in order that
the Owners and ABS may be advised of the parts still to be surveyed.

15

Lay-up and Reactivation (2010)

15.1

Units for Unrestricted Service


ABS is to be notified by the Owner that a vessel has been laid-up. This status will be noted in the Record,
and surveys falling due during lay-up will then be held in abeyance until the vessel is reactivated. Lay-up
procedures and arrangements for maintenance of conditions during lay-up may be submitted to ABS for
review and confirmation by survey (See Appendix 7-2-A1 of these Rules).
In the case of units which have been laid-up for an extended period (i.e., six months or more), the requirements
for surveys on reactivation are to be specially considered in each case, with due regard being given to the
status of surveys at the time of the commencement of the lay-up period, the length of the period and
conditions under which the unit had been maintained during that period.
Where the lay-up preparations and procedures have been submitted to ABS for review and confirmed by
Annual Lay-up Surveys, consideration may be given to deducting part or all of the time in lay-up from the
progression of survey intervals.
For units returning to active service, regardless of whether ABS has been informed previously that the
vessel has been in lay-up, a Reactivation Survey is required.

15.3

Units Operating in Fresh Water (2012)


Where the lay-up preparations and procedures have been submitted to ABS for review and verified by
Annual Lay-up Surveys, consideration may be given to deducting part or all of the time in lay-up from the
progression of survey intervals.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

113

Part
Chapter
Section

7
2
1

Surveys
Surveys After Construction
Conditions for Surveys After Construction

7-2-1

When applying for deductions, Owners are to provide details of out of service intervals since last credited
surveys. For drilling units operating in the Great Lakes, this does not include the normal winter lay-up
months of January, February, and March.
Note:

17

The above requirements apply to drilling units operating in fresh water such as in the Great Lakes, and Lake Maracaibo.

Onboard Drawings and Manuals (2012)


(2016) The following documents are to be available onboard at all times.
7-2-1/17.1 and 7-2-1/17.3 are applicable to all drilling units built under a contract, signed between the Builder
and the Owner, on or after 1 January 2012.
7-2-1/17.5 is applicable to all drilling units built under a contract, signed between the Builder and the Owner,
on or after 1 January 2016.

17.1

Documents Reviewed and Stamped by ABS Engineering (2014)


As a minimum, the following documents reviewed and stamped by ABS are to be available onboard the
drilling unit for Surveyors verification and reference during survey after construction:
i)

Operating Manual.

ii)

Drawings indicating locations of all Special, Primary and Secondary application structures
as defined in 3-1-4/5 of these Rules.

iii)

Drawings indicating all Critical Structural Areas as defined in 7-2-1/3.7 of these Rules.

iv)

Drawings showing all watertight boundaries and access/closing devices for such boundaries.

v)

Drawings showing the Fire Protection Systems, clearly indicating all fire rated boundaries and
access/closing arrangements for such boundaries, including location of fire dampers for A class
divisions.

vi)

Drawings showing the Fire Extinguishing Systems, clearly indicating layout of all fixed and portable
fire extinguishing systems. Minor changes to these drawings may be accepted and endorsed by the
attending Surveyor, however the endorsed copy of the drawings are to be submitted to ABS
engineering at earliest opportunity for record purposes.

vii)

Drawings showing layout of all Hazardous Areas, clearly indicating layout of different class
hazardous divisions together with access/closing/ventilation arrangements for such division boundaries,
the arrangement of ventilation shutdown and alarms (referenced in 7-1-6/21.19 of these Rules),
and a listing of Electrical Equipment in Hazardous Areas (referenced in 7-1-6/21.17 of these Rules).

viii)

Drawings showing layout of the Emergency Shutdown Systems (referenced in 7-1-6/21.25 of


these Rules).

ix)

Where the drilling unit is classed with a notation affecting its Automation System (such as ACC
or ACCU), Automation System Operating Manual.

x)

Where the drilling unit is classed with a DPS notation, the Dynamic Positioning System (DPS)
Manual and the Failure Modes and Effects Analysis (FMEA).

xi)

Where the drilling unit is classed with a CDS notation, drawings showing layout of the Drilling
Systems and associated Equipment, and a listing of all equipment and components of the classed
drilling systems.

xii)

Where the drilling unit is classed with optional HIMP Notation, the Owners Hull Inspection and
Maintenance Program (HIMP) used for hull inspection and maintenance purposes is to be available
onboard the drilling unit.

Minor changes to the drawings regarding fire protection systems, fire extinguishing systems, and listing of
electrical equipment in hazardous areas, may be accepted by the attending Surveyor and revised documents
endorsed to show Surveyors verification, however the endorsed copy of the drawings are to be submitted
to ABS engineering at earliest opportunity for record purposes.

114

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

17.3

17.5

7
2
1

Surveys
Surveys After Construction
Conditions for Surveys After Construction

7-2-1

Documents Issued, Reviewed, and/or Endorsed by ABS Surveyor (2014)


As a minimum, the following documents endorsed by an ABS Surveyor are to be available onboard the
drilling unit for Surveyors verification and reference during any survey after construction:
i)

Certificate of Classification issued or endorsed by Surveyor reflecting the full class designation
assigned to the drilling unit.

ii)

Documents issued or endorsed by the Surveyor supporting any additional class notation, such as:
CRC; UWILD, etc., applicable to the unit and reflected in the ABS Record.

iii)

Construction Booklet reviewed and endorsed by the Surveyor.

iv)

ABS Certificates issued by Surveyor for anchoring gear such as the anchors, chains and/or wires,
and associated accessories (such as shackles, links, sockets, etc.) used for self-propelled drilling
units or installed on units with the symbol.

v)

ABS issued documents issued or endorsed supporting verification of mooring system equipment
installed on units classed with the or symbol.

vi)

Record of all Nondestructive Testing (NDT) of critical structural areas carried out during each
Drydocking Survey (or UWILD) or Special Periodical Survey of the Hull, reviewed and endorsed
by the Surveyor.

Survey Planning Document (SPD) (2016)


All units built or have completed a major modification under a contract, signed between the builder and the
owner, on or after 1 January 2016, are to have an ABS approved SPD available onboard the drilling unit
for Surveyors verification and reference.
All existing drilling units, due for an UWILD (either intermediate or associated with SPS) on or after 1 January
2019, are to have an ABS approved SPD available onboard the drilling unit for Surveyors verification and
reference.

19

Preparations for Safe Execution of Surveys (2014)


The Owner is to provide the necessary facilities for a safe execution of the surveys to be carried out by the
attending Surveyor. Tanks and spaces are to be safe for access (i.e., gas freed, well ventilated, sufficiently
illuminated, etc.).

19.1

Safe Access
For surveys, means are to be provided to enable the attending Surveyor to examine the hull structure in a
safe and practical way. It is to be confirmed, as far as practicable, that means of access to all spaces are in
good/sound and safe condition when examining internal and external spaces.
19.1.1 Internal Examination
For surveys inside ballast tanks, deep voids, or other type deep spaces one or more of the following
means for access, acceptable to the attending Surveyor, is to be provided:

i)

Permanent staging and passages through structures;

ii)

Temporary staging and passages through structures;

iii)

Lifts and moveable platforms;


Note:

Single person hoists/lifts are not acceptable means for access.

iv)

Boats or rafts; or

v)

Other equivalent means agreed by the attending Surveyor.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

115

Part
Chapter
Section

7
2
1

Surveys
Surveys After Construction
Conditions for Surveys After Construction

7-2-1

19.1.2 External Examination


For external examination of spaces and the units overall structure one or more of the following
means for access, acceptable to the attending Surveyor, is to be provided:

i)

Permanent staging;

ii)

Temporary staging;

iii)

Work basket operated by units deck crane;


Note:

19.3

Deck crane used for handling the work basket is to be either ABS classed (CRC) or accepted
by ABS to be suitable for IMO MODU Code Certification of the drilling unit.

iv)

Work boats; or

v)

Other equivalent means agreed by the attending Surveyor.

Accessing Spaces at Sea


If internal examination of a space is necessary whilst the unit is located at sea, a suitable communication
system is to be arranged between the survey party inside the space and the responsible Owners personnel
outside the space being examined. This communication system is also to include the personnel in charge of
ballast pump handling, especially if boats or rafts are used for internal examination.
Explosion-meter, oxygen-meter, breathing apparatus, life line and whistles are to be at hand during the
entire survey period.
19.3.1 Examination by Boats or Rafts
When boats or rafts are used for internal or external examinations, appropriate life jackets are to
be available for all persons onboard. Boats or rafts are to have satisfactory residual buoyancy and
stability, even if one chamber is ruptured. A safety checklist is to be provided.

Surveys of tanks or applicable internal spaces by means of boats or rafts may only be undertaken
with the agreement of the Surveyor, who is to take into account the safety arrangements provided,
including weather forecasting and ship response under foreseeable conditions and provided the
expected rise of water within the tank does not exceed 0.25 m and the water level is stationary.
Note:

19.5

Reference is made to the IACS Recommendation 39 Guidelines for use of Boats or Rafts for Close-up
Surveys.

Housekeeping (Cleanliness)
In preparation for required surveys and to allow for a thorough examination by General Visual Inspection
(GVI), Close Visual Inspection (CVI), Nondestructive Testing (NDT), or Gauging, all spaces are to be
cleaned including removal from surfaces of all loose accumulated corrosion scale.
Spaces are to be sufficiently clean and free from water, scale, dirt, oil residues etc. to reveal corrosion,
deformation, fractures, damages or other structural deterioration. However, those areas of structure whose
renewal has already been decided by the Owner need only be cleaned and descaled to the extent necessary
to determine the limits of the areas to be renewed.

19.7

Illumination and Ventilation


19.7.1 Illumination
Proper illumination is to be provided to enable safe entry, access and survey at all times. Spaces
are to be sufficiently illuminated to also reveal corrosion, deformation, fractures, damages or other
structural deterioration.
19.7.2 Ventilation
All spaces to be entered by the attending Surveyor is to be sufficiently ventilated in advance of
survey and considered satisfactory for safe entry. All spaces are to have mechanical air ventilation
supplied from and exhausted to non-hazardous areas.

Conditions for entry into confined spaces are to at least satisfy ABS safety standards and are to be
to the satisfaction of the attending Surveyor.
116

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

19.9

7
2
1

Surveys
Surveys After Construction
Conditions for Surveys After Construction

7-2-1

Sea Trials and/or Stability Test (2016)


Where major modification is carried out, a sea trial/a lightweight survey/an inclining experiment may need
to be carried out in presence of an ABS Surveyor. In such case, it cannot be commenced unless the Surveyor
agrees with the owner that suitable safety precautions are taken onboard the drilling unit. This may include
but not limited to the verification of following items by the attending Surveyor:

Operational preparedness of any additional portable fire extinguishing placed onboard

Posting of temporary fire control and safety plans to be used during the sea trial/lightweight survey/
inclining experiment

Satisfactory condition and installation of life saving appliances for the sea trial/lightweight survey/inclining
experiment personnel, particularly if the number of personnel exceeds the drilling units Persons On
Board (POB) capacity

Abandon Unit Drill with entire personnel

Fire Drill with designated fire fighters

An exemption to any of the above is the responsibility of the Flag Administration and the Coastal State
Authority. If an exemption is issued, the written exemption is to be made readily available to the attending
Surveyor for evaluation.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

117

PART

Section 2: Survey Intervals

CHAPTER

Surveys After Construction

SECTION

Survey Intervals (2010)

Units Unrestricted Service


The following requirements are to be followed on units for unrestricted service.

1.1

Annual Surveys
Annual Surveys are to be made within three months before or after of each annual anniversary date of the
crediting of the previous Special Survey Hull, or original construction date. For units on Continuous
Survey, all Continuous Survey requirements for those parts (items) due are generally to be completed each
year. The Annual Survey will not be credited and the Certificate of Classification will not be endorsed
unless Continuous Survey items which are due or overdue at the time of the Annual Survey are either
completed or granted an extension.

1.3

Special Periodical Surveys (2014)


A Special Periodical Survey is to be completed within five years after the date of build or after the
crediting date of the previous Special Periodical Survey. The interval between Special Periodical Surveys
may be reduced by ABS. If a Special Periodical Survey is not completed at one time, it will be credited as
of the completion date of the survey, but not later than five years from date of build or from the date
recorded for the previous Special Periodical Survey. If the Special Periodical Survey is completed
prematurely but within three months prior to the due date, the Special Periodical Survey will be credited to
agree with the effective due date.
Special consideration may be given to Special Periodical Survey requirements in the case of mobile offshore
drilling units of unusual design, in lay-up or in unusual circumstances. ABS reserves the right to authorize
extensions of Rule-required Special Periodical Surveys under extreme circumstances.
A Special Periodical Survey may be commenced at the fourth Annual Survey and be continued with a view
to completion by the due date. In connection with the preparation for the Special Periodical Survey,
thickness gaugings, as required for the forthcoming Special Periodical Survey, are to be taken to the extent
accessible and practical in connection with the fourth Annual Survey.
Where the Special Periodical Survey is commenced prior to the fourth Annual Survey, the entire survey is
normally to be completed within 15 months if such work is to be credited to the Special Periodical Survey.

1.5

Continuous Surveys (2012)


At the request of the Owner, and upon approval of the proposed arrangements, a system of Continuous
Survey may be undertaken whereby the Special Periodical Survey requirements are carried out in regular
rotation to complete all requirements of the particular Special Periodical Survey within a five-year period.
The completion date will be recorded to agree with the original due date of the cycle. If the Continuous
Survey is completed prematurely but within three months prior to the due date, the Special Periodical
Survey will be credited to agree with the effective due date.
ABS reserves the right to authorize extensions of Rule-required Special Continuous Surveys under extreme
circumstances.

118

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

7
2
2

Surveys
Surveys After Construction
Survey Intervals

7-2-2

Each part (item) surveyed becomes due again for survey approximately five years from the date of the
survey. For Continuous Surveys, a suitable notation will be entered in the Record and the date of completion
of the cycle published. If any defects are found during the survey, they are to be dealt with to the satisfaction
of the Surveyor.
At a survey approximately four years after each Continuous Survey of Hull has been credited, all
accessible thickness gaugings, as required for the forthcoming Special Periodical Survey, are to be taken.

1.7

In-line Surveys (2012)


All items required to undergo Special Periodical Surveys, including but not limited to hull, machinery, and
automation, are to be carried out at the same time and interval in order that they are recorded with the same
crediting date. In cases where damage has necessitated extensive repairs and examination, the survey thereon
may, where approved by ABS, be accepted as equivalent to Special Periodical Survey.

1.9

Drydocking Survey or Equivalent


For units operating in salt water, a minimum of two Drydocking Surveys are to be carried out in each fiveyear Special Survey period. One such examination is to be carried out in conjunction with the Special
Survey Hull. In all cases, the interval between any two Drydocking Surveys is not to exceed 36 months.
For units operating in salt water for less than six months each year, the maximum interval is not to exceed
three years. For units operating in fresh water the interval between Drydocking Surveys is not to exceed
five years.
Consideration may be given to special circumstances which may justify an extension of the interval. An
underwater inspection by a diver may be required for such extensions.
1.9.1

Self-Elevating Drilling Units Drydocking Survey Interval Exceeding 36 Months (2012)


Where a self-elevating drilling unit operating in salt water is unable to complete its Drydocking
Survey within a 36 month period, at Owners specific request, the Drydocking Survey due date
may be extended by ABS, provided the unit is attended for examination as required.

Where a self-elevating drilling unit operating in salt water is unable to complete its Drydocking
Survey within a 60 month period and remained operating in the same drilling site without any rig
move, the unit will be considered a site-specific self-elevating mobile offshore unit and required to
comply with 3/3.7.8 of the ABS Rules for Building and Classing Offshore Installations.

1.11

Tail Shaft Surveys


1.11.1 Water-Lubricated Bearings in Fresh Water Exclusively
Survey interval is five (5) years.
1.11.2 Water-Lubricated Bearings in Fresh Water and Sea Water
1.11.2(a) Single Screw. Survey interval is three (3) years.

1.11.2(b) Multiple Screw. Survey interval is five (5) years.


1.11.2(c) Continuous Liner or Equivalent. Survey interval of five (5) years provided:
i)

The tail shaft is protected by a continuous metallic liner, or continuous cladding per
4-3-2/5.17.5 of the Steel Vessel Rules or fiberglass reinforced plastic coating between liners
installed according to approved procedure per 4-3-2/5.17.4 of the Steel Vessel Rules which
effectively prevents seawater from contacting the steel shaft, or which have shafts of
corrosion-resistant materials.

ii)

In addition to the propeller hub details given in the 4-3-2/Figure 1 of the Steel Vessel Rules,
the design includes other features that would further reduce stress concentration in the
propeller assembly.

1.11.3 Oil-Lubricated Bearings


Survey interval is five (5) years.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

119

Part
Chapter
Section

7
2
2

Surveys
Surveys After Construction
Survey Intervals

7-2-2

1.11.4 Extensions Water-Lubricated Bearings


1.11.4(a) Extension up to Three (3) Months. An extension up to three (3) months may be granted
by the Surveyor, when requested by the Owner, provided a survey is carried out in accordance
with 7-5-1/5.1.1 of the ABS Rules for Survey After Construction (Part 7).

1.11.4(b) Extension up to One (1) Year. An extension up to one (1) year may be granted by the
Surveyor, when requested by the Owner, provided a survey is carried out in accordance with
7-5-1/5.1.2 of the ABS Rules for Survey After Construction (Part 7).
1.11.5 Extensions Oil-Lubricated Bearings
1.11.5(a) Extension up to Three (3) Months. An extension up to three (3) months may be granted
by the Surveyor, when requested by the Owner, provided a survey is carried out in accordance
with 7-5-1/5.3.1 of the ABS Rules for Survey After Construction (Part 7).

1.11.5(b) Extension up to One (1) Year. An extension up to one (1) year may be granted by the
Surveyor, when requested by the Owner, provided a survey is carried out in accordance with
7-5-1/5.3.2 of the ABS Rules for Survey After Construction (Part 7). An additional extension up to
one (1) year may be considered, when requested by the Owner, provided a survey is carried out at
the end of the first extension period, in accordance with 7-5-1/5.3.2 of the ABS Rules for Survey
After Construction (Part 7). No more than two (2) extensions may be granted.
1.11.5(c) Extensions not Exceeding Five (5) Years. In lieu of 7-2-2/1.11.4(b), an extension not
exceeding five (5) years may be granted by the Surveyor, when requested by the Owner, provided
a survey is carried out at the fifth year, in accordance with 7-5-1/5.3.3 of the ABS Rules for Survey
After Construction (Part 7). Consideration may be given to an additional extension not exceeding
five (5) years when requested by the Owner, provided a survey is carried out at the fifth year after
the first extension, in accordance with 7-5-1/5.3.3 of the ABS Rules for Survey After Construction
(Part 7). No more than two (2) extensions may be granted.

1.13

Auxiliary Boiler Surveys


Waste-heat or fired auxiliary boilers intended for working pressures above 3.4 bar (3.5 kgf/cm2, 50 psi), a
minimum of two surveys are to be carried out during each 5-year Special Periodical Survey period. One
such survey is to be carried out in conjunction with the Special Periodical Survey. In all cases, the interval
between any two such surveys is not to exceed 36 months.
An extension of the survey up to three (3) months may be granted by the Surveyor in exceptional
circumstances*, provided a survey is carried out in accordance with 7-7-1/11 of the ABS Rules for Survey
After Construction (Part 7).
In addition, annual examinations are to be carried out in accordance with 7-7-1/13 of the ABS Rules for
Survey After Construction (Part 7).
For units on continuous survey of hull, the two surveys are to be carried out during each 5 year cycle and may
be aligned with the dry dock survey dates as long as the interval between surveys does not exceed 36 months.
* Note: Exceptional circumstances means, e.g., unavailability of repair facilities, unavailability of essential materials,
equipment or spare parts, or delays incurred by action taken to avoid severe weather conditions.

Units Operating in Fresh Water (2012)


Applicable requirements of Section 7-2-2 of the ABS Rules for Survey After Construction (Part 7) are to
be followed on units operating in fresh water such as the Great Lakes, and Lake Maracaibo.

120

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

PART

Section 3: Survey Pre-planning

CHAPTER

Surveys After Construction

SECTION

Survey Pre-Planning (2012)

Drydocking Surveys and Special Surveys


Plans and procedures for Drydocking (or UWILD) and Special Surveys are to be made available onboard
for the purpose of carrying out an on-board pre-planning of the survey with the Surveyor.

1.1

Plan for UWILD (2016)


Owners plan for the UWILD is to be reviewed and agreed upon by the respective offshore Assistant Chief
Surveyors (ACS) Office before the survey commences and same is to be discussed during the preplanning meeting held onboard.
Owners request to carry out UWILD after Special Survey No. 4 is to be agreed upon by the respective
offshore ACS Office before the survey commences.

1.3

Plan for Out-of-Water Drydocking and Special Periodical Survey


Owners plan for the Out-of-Water Drydocking Surveys or Special Periodical Survey is to be reviewed and
agreed upon by the attending Surveyor before the survey commences and same is to be discussed during
the pre-planning meeting held onboard.
Owners request to carry out UWILD prior to or at time of Special Survey No. 4 is to be agreed upon by
the attending Surveyor before the survey commences.

1.5

Survey Planning Document (SPD) (2016)


A Survey Planning Document (SPD), as required by 7-2-1/17.5, is intended to confirm the records kept to
date in accordance with 7-2-5/1.5.1 and to verify that no changes have been made to drilling units critical
structural areas, and to stipulate the minimum extent, location and means of close visual inspection, extent
and type of NDT, and thickness measurements, as required.
The SPD is to be prepared by the owner and to be made available to the attending Surveyor, for review and
agreement, well in advance of the survey. Contents of the SPD normally cover all typical Special Surveys
and Drydocking Surveys to be carried out throughout every five-year classification cycle of the vessel.
SPDs are to contain a list of all areas that require General Visual Inspection (GVI), Close Visual Inspection
(CVI), Nondestructive Testing (NDT), and/or Gauging.
The SPD should typically contain at least the following information, as applicable:

Main particulars

Plans to include details of major brace and column connections on column-stabilized units and details
of leg and leg-to-spudcan connections

Jackhouse/jackcase-to-deck connections, on self-elevating units

Detailed information on NDT methods and locations

List of tanks with information on use, protection and condition of coating

Corrosion risk of tank and other major structural members

Design risk nomination of major structure

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

121

Part
Chapter
Section

1.7

7
2
3

Surveys
Surveys After Construction
Survey Pre-Planning

Method and extent of cleaning inspection points

Nomination of areas of structure for thickness measurement

Nomination of critical structural areas for close-up surveys and NDT.

7-2-3

Critical Structural Areas


The basis for nomination of the critical structural areas is an assessment in consideration of possible
deterioration and designated fatigue prone areas where the following elements on a particular unit are taken
into account:

Design feature with relatively low fatigue life

Former history available at Owners or ABS offices with respect to corrosion, cracking, buckling, indents
and repairs for the particular unit as well as similar units

Units service history since last survey (e.g., area of operation, environmental data, water depth, air gap
for SEDUs, length of time at each location etc.)

The degree of criticality should be judged and decided on the basis of recognized principles and practice, and
the units structural fatigue analyses if deemed necessary. ABS reviewed drawing showing all applicable
critical structural areas is to be available onboard, referenced during the pre-planning meeting and used
during applicable visual examination and NDT.

122

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

PART

Section 4: Annual Surveys

CHAPTER

Surveys After Construction

SECTION

Annual Surveys

Annual Survey Hull

1.1

All Types of Mobile Offshore Drilling Units


(2010) At each Annual Survey Hull, the exposed parts of the hull, the deck, deckhouses, structures attached
to the deck, derrick substructure, including supporting structure, accessible internal spaces, and the applicable
parts listed in 7-2-4/1.1.1 through 7-2-4/1.1.15 below are to be generally examined and placed in satisfactory
condition as found necessary and reported upon.
1.1.1

Openings in Freeboard Deck and Enclosed Superstructure Decks


Hatchways, manholes, and other openings in the freeboard deck (bulkhead deck) and enclosed
superstructure decks.

Machinery casings and covers, companionways, and deckhouses protecting openings in freeboard
or enclosed-superstructure decks.
1.1.2

Openings below the Freeboard Deck and Enclosed Superstructures


Portlights together with deadcovers, cargo ports, bow or stern entries, chutes, and similar openings
in hull sides or ends, below the freeboard deck or in way of enclosed superstructures.

1.1.3

Ventilators, Vent Pipes Overboard Discharges on or below Freeboard Deck


Ventilators, tank vent pipes together with flame screens, and overboard discharges from enclosed
spaces on or below the freeboard deck.

1.1.4

Bulkheads of Enclosed Superstructures


Watertight bulkheads and end bulkheads of enclosed superstructures.

1.1.5

Closing Appliances
Closing appliances for all of the above, including hatch covers, doors, check valves together with
their respective securing devices, dogs, sills, coaming, and supports.

1.1.6

Freeing Ports
Freeing ports together with bars, shutters, and hinges.

1.1.7

Protection of Crew, Guard Rails, Lifelines, Gangways, and Deckhouses


Protection of the crew, guard rails, lifelines, gangways, and deckhouses accommodating crew.

1.1.8

Suspect Areas
Suspect areas of the hull are to be overall examined and gauged as considered necessary.

Suspect areas identified at a previous survey and which are readily accessible are to be subject to
overall examination and Close-up Survey. Similarly, any areas of Substantial Corrosion identified
at previous surveys and which are readily accessible are to have thickness measurements taken.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

123

Part
Chapter
Section

7
2
4

1.1.9

Surveys
Surveys After Construction
Annual Surveys

7-2-4

Corrosion
Where extensive areas of corrosion are found or when considered necessary by the Surveyor,
thickness measurements are to be carried out and renewals and/or repairs made when wastage exceeds
allowable margins.

Where Substantial Corrosion is found, additional thickness measurements are to be taken to confirm
the extent of substantial corrosion. These extended thickness measurements are to be carried out
before the annual survey is credited as completed.
1.1.10 Corrosion Control Systems
At each Annual Survey Hull, the Surveyors are to be satisfied that the type, location and extent
of the corrosion control system as well as its continuous effectiveness is in satisfactory condition.
Repairs or renewals should be reported on at each survey. Particular attention is to be given to
corrosion control systems in ballast tanks, free-flooding areas and other locations subjected to sea
water from both sides.

1.1.10(a) Performance Standards for Protective Coatings (PSPC) (2012). For units with optional
class notation CPS, survey after construction are to comply with Section 6 of the ABS Guide for
the Class Notation Coating Performance Standard (CPS). See 7-1-2/13.1.
1.1.11 Alterations and Position of Load Lines
At each Annual Survey Hull, the Surveyors are to be satisfied that no material alterations have
been made to the unit, its structural arrangements, subdivision, superstructure, fittings and closing
appliances upon which the load line assignment is based.
1.1.12 Construction Booklet (Construction Portfolio) (2012)
ABS reviewed and stamped Construction Booklet is to be available onboard the drilling unit for
Surveyors verification.
1.1.13 Operating Manual (2012)
ABS reviewed and stamped Operating Manual is to be available onboard the drilling unit for
Surveyors verification.
1.1.14 HIMP Notation (optional) (2012)
Owners Hull Inspection and Maintenance Program (HIMP) used for hull inspection and
maintenance purposes is to be available onboard the drilling unit.
1.1.15 Onboard Computers for Stability Calculations (2014)
This Subparagraph is applicable to Mobile Offshore Drilling Units that were contracted for
construction on or after 1 July 2005 that have Stability Computers onboard the unit. This
Subparagraph is not applicable to Drilling units that were fabricated prior to 1 July 2005 or to
those that do not have Stability Computers.

If an onboard computer is used for stability calculations, satisfactory operation of the software with
the onboard computer(s) for stability calculations is to be verified in presence of the Surveyor.
Satisfactory functional requirements (see 7-1-A2/3) are to be confirmed by the Surveyor.
A copy of the approved test conditions and the operation manual (see 7-1-A2/5) for the computer/
software are to be available onboard.
1.1.15(a) Testing. It is the responsibility of the drilling units master to check the accuracy of the
onboard computer for stability calculations at each Annual Survey by applying at least one
approved test condition.
The testing is to be carried out to verify initial installation testing conditions.
If the Surveyor is not present for the computer check, a copy of the test condition results obtained
by the computer check is to be retained onboard as documentation of satisfactory testing for the
Surveyors verification.
For further details, see Appendix 7-1-A2.
124

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

1.3

1.5

1.7

7
2
4

Surveys
Surveys After Construction
Annual Surveys

7-2-4

Surface-Type Units (2012)


On Surface-Type Units, in addition to the requirements of 7-2-4/1.1, following areas are to be examined.

The hull and deck structure around the drilling well (moon pool) and in vicinity of any other structural
changes in section, slots, steps or openings in the deck or hull..

The back-up structure in way of structural members or sponsons connecting to the hull.

Column-Stabilized Units (2012)


On Column Stabilized Units, in addition to the requirements of 7-2-4/1.1, following areas are to be examined.

Columns, diagonals and other parts of the upper columns, diagonals and other parts of the upper hull
supporting structure as accessible above the waterline.

The upper hull structure around the drilling well (moon pool) and in vicinity of any other structural
changes-in section, slots, steps or openings in the upper hull structure.

Self-Elevating Units (2012)


On Self-Elevating Units, in addition to the requirements of 7-2-4/1.1, following areas are to be examined.

Jackhouse structures and attachment to upper hull or platform.

Jacking or other elevating systems and leg guides, externally.

Legs as accessible above the waterline.

Plating and supporting structure in way of leg wells.

Annual Survey Machinery and Electrical Systems (2016)


At each Annual Survey Machinery and Electrical Systems, the entire installation is to be generally examined
so far as can be seen and placed in satisfactory condition. The survey is also to include the following items,
as applicable.

3.1

Non-Self-Propelled Units (1996)


On non-self-propelled units, a general examination is to be made of items required for classification such
as auxiliary machinery, pumps, piping, electrical installations, including those in hazardous areas, and fireextinguishing apparatus as outlined in Part 5, Chapter 2 of these Rules. Fire mains are to undergo satisfactory
pressure testing.

3.3

Self-Propelled Units (1996)


On self-propelled units, a general examination in accordance with Section 7-6-2 of the ABS Rules for
Survey After Construction (Part 7) should be made of engines, boilers, steering machinery, windlass,
auxiliary machinery, pumps, piping, electrical installations, including those in hazardous areas, and fireextinguishing apparatus required for classification as outlined in Part 5, Chapter 2 of these Rules.

3.5

Examination during Overhaul (2010)


On all occasions of overhaul or adjustment, access is to be provided for the Surveyor to examine the parts
opened. In the event of defects being discovered, such other parts as may be considered necessary are to be
opened and examined.

3.7

Examination at Shorter Intervals (2012)


If it is found desirable, upon examination, that any part of the machinery should be examined at shorter
intervals than specified, it will be necessary for Owners to comply with ABS requirements in this respect.

Annual Survey Preventative Maintenance Program (PMP) (2016)


Where the unit has enrolled into ABS Preventative Maintenance Program (PMP) and satisfactorily completed its
implementation survey, and maintains the optional PMP additional notation, equipment or machinery covered
under the PMP are to be surveyed on the basis of Appendix 7-2-A4 Preventative Maintenance Program.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

125

Part
Chapter
Section

7
2
4

Surveys
Surveys After Construction
Annual Surveys

7-2-4

Annual Survey Thrusters for APS or PAS Notations (2016)


Where the unit maintains the optional APS or PAS notations, thrusters are to be surveyed on the basis of
Survey Requirements for Additional Systems and Services in accordance with the requirements of
Section 7-9-6 of the ABS Rules for Survey After Construction (Part 7).
Note:

7.1

Thruster System (APS or PAS)


At each Annual Survey, thruster system associated with vessels APS or PAS notations are to be generally
examined, so far as can be seen, and placed in satisfactory condition. The survey is also to include the
following items, as applicable:
7.1.1

The APS notation signifies that the self-propelled vessel is fitted with athwartship thrusters intended to assist in
the maneuvering of the vessel. The PAS notation signifies that the non-self-propelled vessel is fitted with thrusters
intended to assist in maneuvering or propelling while under tow.

Thruster Controls and Alarms


Verification of effective means of control from both the Navigation Bridge and local control
stations, including alarms and indicators. The following audible and visual alarms at each control
station are to be visually examined, verified operational and considered satisfactory, as applicable:

i)

Engine low lubricating oil pressure

ii)

Engine coolant high temperature

iii)

Motor overload

iv)

Thruster RPM

v)

Thrust direction (azimuthing type)

vi)

Thruster power supply failure

vii)

Controllable pitch propellers hydraulic low oil pressure

viii)

Controllable pitch propellers hydraulic high oil pressure

ix)

Controllable pitch propellers hydraulic oil high temperature

x)

Fire extinguishing systems

7.1.2

Thruster Room Communication


Means of voice communication between the bridge control station, main propulsion control station
and the thruster room are to be tested and found satisfactory.

7.1.3

Thruster Room Arrangement


Thruster room arrangements, including adequate ventilation, bilge system and alarms for enclosed
modules and firefighting systems are to be examined, tested and considered satisfactory.

Annual Survey Dynamic Positioning Systems (2016)


On drilling units built under a contract, signed between the Builder and the Owner, on or after 1 January
2016, if the unit maintains any one of the optional DPS notation, the thrusters designated for propulsion
and dynamic positioning may be enrolled into ABS Preventative Maintenance Program (PMP). In such
cases, thrusters are to be approved either under the Condition Monitoring (CM) plan or Reliability
Centered Maintenance (RCM).
Enrollment into ABS PMP and associated Annual Confirmation Survey is to be in accordance with applicable
Subsections of Appendix 7-2-A4.
In cases where testing may interfere with operations, verification of all different operational modes may
not be practicable. Operational status of the vessel may then be taken into consideration. When any
operational mode is not witnessed by the Surveyor, the dynamic positioning records are to be examined.
The Surveyor is to review the dynamic positioning records and examine the performance of the systems
throughout the period since the last survey and to establish if there has been any abnormal functioning or
failures and what corrective measures had been taken to preclude their recurrence.

126

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

7
2
4

Surveys
Surveys After Construction
Annual Surveys

7-2-4

At each Annual Survey of thrusters and Dynamic Positioning System (DPS), respective system and associated
machinery are to be generally examined, so far as can be seen, and placed in satisfactory condition. The
survey is also to include the following items, as applicable.

9.1

Units classed with DPS-0, DPS-1, DPS-2, DPS-3 Notations


At each Annual Survey, the thrusters are to be generally examined so far as can be seen and placed in
satisfactory condition. This survey is to be in accordance with 7-2-4/7.1 and also to include following, as
applicable:
9.1.1

Operation of DPS
The vessel is to be operated for duration of at least two hours to demonstrate that the dynamic
positioning system has been maintained properly and is in good working order. The operational
testing is to be carried out to the Surveyors satisfaction. The tests are to demonstrate the level of
redundancy established by the FMEA (Failure Modes and Effects Analysis, see Subsection 2/11 of
the ABS Guide for Dynamic Positioning Systems). Special consideration may be given, subject to
the discretion of the Surveyor, when sufficient test reports are in place demonstrating that the
vessel has been engaged in a DP testing program.

In addition, the following items are to be generally examined so far as can be seen and placed in
satisfactory condition.
9.1.2

DPS Controls and Alarms


Control system, including independent emergency shut-down facility for each thruster at the main
dynamic positioning control station, position keeping redundancy, and alarms and instrumentation
are to be generally examined and confirmed to be functioning satisfactorily.

9.1.3

DPS Environment Sensors


Wind sensors(s) and gyro-compass(s) are to be generally examined and confirmed to be functioning
satisfactorily.

9.1.4

Vessels Classed with DPS-1 Notation


The operation of the automatic control system and a manual position control system including manual
transfer of control between the two systems is to be confirmed to be functioning satisfactorily.

9.1.5

Vessels Classed with DPS-2 Notation


The operation of two automatic control systems and a manual position control system including
automatic transfer of one automatic control system to another upon failure is to be confirmed to be
functioning satisfactorily. Upon failure of the two automatic control systems, it is to be verified
that the manual position control is possible.

9.1.6

Vessels Classed with DPS-3 Notation


The operation of three automatic control systems and a manual position control system including
automatic transfer of one automatic control system to another upon failure is to be confirmed to be
functioning satisfactorily. Manual transfer of control is to be verified possible at the third automatic
control system located in the emergency back-up control station. Upon failure of the automatic
control systems, it is to be verified that the manual position control is possible.

9.1.7

Manual Position Control System for DPS-1, DPS-2, and DPS-3 Notations
The operation of the manual position control system using one joystick on the Navigation Bridge
or DP control station in accordance with Subsection 5/7 of the ABS Guide for Dynamic Positioning
Systems and supplemented by an automatic heading control is to be confirmed to be functioning
satisfactorily.

9.1.8

Manual Thruster Control System


In addition to above requirements of 7-2-4/9.1.1 through 7-2-4/9.1.7, satisfactory operation of the
manual thruster control system using individual levers on the navigation bridge or DP control station
in accordance with 4/9.5 of the ABS Guide for Dynamic Positioning Systems is to be confirmed.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

127

Part
Chapter
Section

7
2
4

Surveys
Surveys After Construction
Annual Surveys

9.1.9

7-2-4

DPS Alarms and Instrumentation


The audible and visual alarms, including indicators at each control station, are to be examined,
verified operational and confirmed to be functioning satisfactorily. For listing of alarms and
instrumentation, see 7-2-4/Tables 1 through 4.

9.1.10 Uninterruptible Power Systems (UPS) for DPS


UPS is to be operated and confirmed to be functioning satisfactorily. UPS is to be operated
without the normal main power input for 30 minutes to confirm that the batteries are capable of
supplying the output power and are in satisfactory condition. The schedule of batteries is to be
examined to verify that the batteries have been maintained. See 7-6-2/1.1.8 of the ABS Rules for
Survey After Construction (Part 7).
9.1.11 DPS Communication
A means of voice communication between the DP control position (Navigation Bridge), and the
thruster room(s) is to be tested and confirmed to be functioning satisfactorily.

A means of voice communication between the DP control position (Navigation Bridge), the
engine control position and any operational control centers associated with DP is to be tested and
confirmed to be functioning satisfactorily.
Note:

No back up required.

9.1.12 Operations Manual


DPS operations manual is to be confirmed being onboard and readily available. The manual is to
be up to date with any modifications performed on the vessels DPS installation.

It is to be verified that the failure modes and effects of any modifications or upgrades have been
considered and incorporated in the DPS operations manual.

TABLE 1
Thruster Power System (2016)
Alarm or Instrument

128

Alarm

Display

Engine lubricating oil pressure low

Engine coolant temperature high

CPP hydraulic oil pressure low and high

CPP hydraulic oil temperature high

CPP pitch

Thruster RPM

Thruster direction

Thruster motor/semiconductor converter coolant leakage

Thruster motor/semiconductor converter temperature

Thrust motor short circuit

Thruster motor exciter power available

Thruster motor supply power available

Thruster motor overload

Thruster motor high temperature

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

7
2
4

Surveys
Surveys After Construction
Annual Surveys

7-2-4

TABLE 2
Power Distribution System (2016)
Alarm

Display

Status of automatically controlled circuit breakers

Alarm or Instrument

Bus bar current and power levels

High power consumers current levels

TABLE 3
System Performance (2016)
Alarm

Display

Excursion outside operating envelope

Alarm or Instrument

Control system fault

Position sensor fault

Vessel target and present position and heading

Wind speed and direction

Selected reference system

TABLE 4
Additional Alarms and Instruments for DPS-2 and DPS-3 (2016)
Alarm or Instrument

Alarm

Thruster location (pictorial)

Display
X

Percentage thrust

--

Available thrusters on stand-by

DP alert through consequence analyzer

Position information of individual position reference systems connected

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

129

PART

Section 5: Special Periodical Surveys

CHAPTER

Surveys After Construction

SECTION

Special Periodical Surveys

All Types of Units Special Periodical Survey Hull (2014)


Special Periodical Survey Hull is to include compliance with the Annual Survey and Drydocking Survey
requirements and, in addition, the following requirements as listed below are to be carried out, as applicable,
the parts examined by General Visual Inspection (GVI), placed in satisfactory condition and reported upon.
Close Visual Inspection (CVI) and/or Nondestructive Testing (NDT) may be required of suspect areas and
critical structural areas, particularly those that are located in way of special or primary application structures.
Requirements contained in 7-2-5/1.1 through 7-2-5/1.11 apply to all types of mobile offshore drilling units.
Subsequent Subsections 7-2-5/3 through 7-2-5/7 are additional requirements of Special Periodical Survey,
as applicable to unit types.

1.1

General Visual Inspection (GVI)


1.1.1

External and Internal Examination


The hull or platform structure, including tanks, watertight bulkheads and decks, cofferdams, void
spaces, sponsons, chain lockers, duct keels, helicopter pad, machinery spaces, peak spaces, steering
gear spaces, and all other internal spaces, are to be subjected to General Visual Inspection (GVI)
externally and internally for damage, fractures or excessive wastage. Thickness gauging of plating
and framing may be required where wastage is evident or suspected.

1.1.2

Examination for Excessive Wastage or Damage


External and internal condition of all tanks, compartments and free-flooding spaces throughout the
drilling unit are to be subjected to GVI and found or placed to be free of excess wastage or damage.

1.1.3

Watertight Integrity
Watertight integrity of tanks, bulkheads, hull, bulkhead deck and other compartments is to be verified
by GVI. Suspect areas may be required to be subjected to CVI, tested for tightness, nondestructive
tested or thickness gauged. Tanks and other normally-closed compartments are to be ventilated,
gas-freed and cleaned as necessary to expose damage and allow for a meaningful examination for
excessive wastage.

1.1.4

Waiving Internal Examination and Testing


Internal examination and testing of void spaces, compartments filled with foam or corrosion
inhibitors, and tanks used only for lube oil, light fuel oil, diesel oil or other noncorrosive products
may be waived, provided that upon a general examination, the Surveyor considers their condition
to be satisfactory.

1.1.5

Hull Attachments
Hull attachments, as applicable, are to be examined by GVI. To supplement the GVI, CVI and/or
NDT may be required if deemed necessary by the attending Surveyor.

i)

130

Hull Attachments of Anchoring and Mooring System. Attachments of anchor racks, anchor
cable fairleads, and anchor windlasses are to be examined. For drilling units with ,
or Class Symbols, the anchors, chains, and cables and their respective handling means
are to be examined.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

7
2
5

1.1.6

Surveys
Surveys After Construction
Special Periodical Surveys

7-2-5

ii)

Hull Attachments of Drilling Apparatus. Foundations and supporting headers, brackets


and stiffeners for drilling-related apparatus, where attached to hull, deck, superstructure
or deck house.

iii)

Hull Attachments of other Structures. Structures such as derrick substructure and supporting
structure, skid-base structure, jackhouses, pipe racks, deck houses, superstructures, helicopter
landing areas, raw water (seawater intake) towers and their respective attachments to the
deck or hull.

Examination of Underwater Parts


Survey of parts of the unit which are underwater and inaccessible to the Surveyor may be accepted
on the basis of an examination by a qualified diver carried out in the presence of the Surveyor.
Video or photo records, nondestructive testing and thickness gauging may be required in addition
to the divers report. Refer to 7-2-6/3 of these Rules.

Where inspection of underwater joints is required, sufficient cleaning is to be carried out in way,
and water clarity to be adequate, to permit meaningful visual, video, camera or NDT examination,
as required. Every effort should be made to avoid cleaning damage to special coatings.
1.1.7

1.3

Anchor and Mooring Chain Cable


In addition to the requirements of 7-2-5/1.1.5i), at the first Special Periodical Survey and subsequent
Special Surveys the following is to be performed:

i)

For MODUs with or Class Symbols for Position Mooring; the Anchor and Mooring
Chains are to be examined and measured in accordance with the latest edition of API RP 2I
for the In-service Inspection of Mooring Hardware and Floating Structure.

ii)

For MODUs with the the Temporary Mooring Systems they are to be examined in
accordance with 7-3-2/5.1.4 of the ABS Rules for Survey After Construction (Part 7).

Close Visual Inspection (CVI)


Where examination by GVI indicates suspect areas, corrosion in way of special or primary application
structures, or corrosion in way of critical structural areas, additional examination by CVI is to be carried
out.
Areas that were required to be examined by CVI because of indication of suspect areas, corrosion in way
of special or primary application structures, or corrosion in way of critical structural areas, are to be
scheduled for re-examination by CVI during Special Periodical Survey Hull No. 2.

1.5

Nondestructive Testing (NDT) (2016)


Areas subjected to CVI may also be subjected to NDT to the extent deemed necessary by the attending
Surveyor.
In general, surface type NDT techniques are to be carried out for examination of welds. NDT by Magnetic
Particle Inspection (MPI), Penetrant Testing (PT), Eddy Current (EC) or Alternating Current Field
Measurement (ACFM) is to be carried out to the satisfaction of the Surveyor.
Where surface NDT shows unacceptable indications in way of the welds examined, additional volumetric
NDT by Ultrasonic Testing (UT) may be carried out to the satisfaction of the Surveyor.
The accuracy of the NDT equipment is to be proven to the attending Surveyor, as required.
NDT is to be carried out by a qualified technician.
The required NDT is to be witnessed by a Surveyor. The Surveyor is to be onboard to the extent necessary
to control the process. Where NDT is carried out in-water, the qualified diver is to be employed by a
diving firm certified by ABS and listed as Recognized Specialists in ABS records.
The NDT firms representative is to be part of the survey planning meeting to be held prior to commencing
the survey.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

131

Part
Chapter
Section

7
2
5

Surveys
Surveys After Construction
Special Periodical Surveys

7-2-5

In any kind of survey (i.e., Special Periodical, Intermediate, Annual or other surveys having the scope of
the foregoing ones), NDT of structures in areas where CVI is required are to be carried out simultaneously
with CVI.
Where CVI and NDT are carried out in-water, proper two-way audio and video communication lines are to
be established and maintained, throughout the entire in-water inspection period, between the specialized
technician(s) and the attending Surveyor.
Results of NDT are to be maintained as a permanent record of the drilling unit, and be readily available to
the attending Surveyors during subsequent periodical surveys of the hull.
1.5.1

1.7

Record Keeping
The following is an outline of what is expected as far as documentation of the NDT results for
each survey:

i)

Details of the areas surveyed and type of NDT carried out (i.e., sketches showing details
of joints plus any internal back-up structure that is considered part of the structural joint).

ii)

The Owner shall keep a detailed record of what has been previously surveyed, the type of
survey carried out (Visual, MPI, etc.) (e.g., list area/quadrant of joint surveyed, nature and
extent of indication found, and how it was repaired).

Note:

Although it is not a mandatory requirement for Classification, Owners Inspection and Maintenance Manual
could have information on the type of steel used in the construction, as built welding procedures, sketches
of each joint to be surveyed and structural inspection NDT methods to be carried out, and may be used as
a document maintained onboard for Record Keeping. If the Owners Inspection and Maintenance Manual is
used for Record Keeping, it is to be reviewed and accepted by the attending Surveyor during survey preplanning and commencement of respective UWILD.

Hull Thickness Measurement (Gauging)


Suspect areas of the hull are to be overall examined and gauged as considered necessary.
Gauging is normally carried out by means of UT equipment. The accuracy of the equipment is to be proven
to the attending Surveyor, as required.
Gauging is to be carried out by a qualified employee of a firm certified by ABS and listed as Recognized
Specialists in ABS records. Gauging firms are to be certified by ABS in accordance with Appendix 7-A-5
of the ABS Rules for Survey After Construction (Part 7).
The required gauging is to be witnessed by a Surveyor. The Surveyor is to be onboard to the extent
necessary to control the process.
The gauging firms representative is to be part of the survey planning meeting to be held prior to commencing
the survey.
In any kind of survey (i.e., Special Periodical, Intermediate, Annual or other surveys having the scope of the
foregoing ones), gauging of structures in areas where CVI is required are to be carried out simultaneously
with CVI.
At each Special Periodical Survey, thickness gauging is to be carried out where wastage is evident or suspected.
At Special Periodical Survey Hull No. 2 and subsequent Special Periodical Surveys, representative gauging
will be required in accordance with 7-2-5/Table 1, 7-2-5/Table 2 and 7-2-5/Table 3. Special attention should
be paid to splash zones on hulls, legs or related structure, and in ballast tanks, pre-load tanks, free-flooded
spaces, spud cans and mats. The thickness gauging requirements indicated in the tables may be reduced or
increased as deemed appropriate or necessary by the Surveyor in accordance with Notes 2 and 3 of the tables.

1.9

Corrosion Control
Where extensive areas of corrosion are found or when considered necessary by the Surveyor, thickness
measurements are to be carried out and renewals and/or repairs made when wastage exceeds allowable margins.
Where Substantial Corrosion is found, additional thickness measurements are to be taken to confirm the
extent of substantial corrosion. These extended thickness measurements are to be carried out before the
Special Periodical Survey is credited as completed.

132

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

7
2
5

Surveys
Surveys After Construction
Special Periodical Surveys

7-2-5

Suspect areas identified at a previous survey are to be subject to GVI and CVI. Similarly, any areas of
Substantial Corrosion identified at previous surveys are to have thickness measurements taken.
External thickness gauging may be required to confirm corrosion control.

1.11

Onboard Computers for Stability Calculations


This Paragraph is applicable to Mobile Offshore Drilling Units that were contracted for construction on or
after 1 July 2005 that have Stability Computers onboard the unit. This Paragraph is not applicable to
Drilling units that were fabricated prior to 1 July 2005 or to those that do not have Stability Computers.
If an onboard computer is fitted to satisfy 3-3-2/7 and is used for stability calculations, satisfactory operation
of the software with the onboard computer(s) for stability calculations is to be verified in presence of the
Surveyor.
Note:

Satisfactory operation of stability computer(s) fitted on drilling units contracted on or after 1 July 2005 is to be
verified onboard by the attending Surveyor and reported upon.

Satisfactory functional requirements (see 7-1-A2/3) are to be confirmed by the Surveyor.


A copy of the approved test conditions and the operation manual (see 7-1-A2/5) for the computer/software
are to be available onboard.
1.11.1 Testing Computers
Testing of such computers is to be carried out in accordance with the requirements stated in
7-2-4/1.1.15. At each Special Periodical Survey computer checking for all approved test operating
conditions is to be done in presence of the Surveyor.

1.13

Alternatives (2016)
ABS is open to any alternative survey process as long as the standards required by class rules and applicable
statutory requirements/recommendations are satisfactorily complied with.
In order to monitor structural integrity of units, alternative means of visual examination, NDT techniques,
gauging techniques, verification of corrosion control programs, and proper recording of all these alternatives
by the use of special equipment or machinery installed onboard, will be considered on a case-by-case basis.
All alternative survey processes used during Special Periodical Surveys are to be reviewed and agreed
upon by the respective offshore ACS Office, well in advance of the survey pre-planning meeting to be held
with the attending Surveyor.
1.13.1 UWILD with ROVs
Requirements and guidance provided in 7-2-6/3.11.1 is applicable to UWILD associated with Special
Survey.

Surface-Type Drilling Units (2014)


On surface-type drilling units, in addition to the general requirements of 7-2-5/1, the following vessel-specific
requirements are to be carried out to the satisfaction of the attending Surveyor.

3.1

Special Periodical Survey Hull No. 1


3.1.1

General Visual Inspection (GVI)


All spaces and tanks of the drilling unit are to be subjected to GVI. Structural appendages and
ducts for positioning units are to be included in the GVI.

If found suspect or considered necessary by the Surveyor, CVI as well as NDT of special and/or
primary application structures may be carried out to extent deemed necessary by the Surveyor.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

133

Part
Chapter
Section

7
2
5

3.1.2

Surveys
Surveys After Construction
Special Periodical Surveys

7-2-5

Close Visual Inspection (CVI)


All external surfaces of special application structures located on the main deck level at corners of
the moon pool opening are to be subjected to CVI.

If found suspect or considered necessary by the Surveyor, CVI of special application structures located
above the waterline and within amidships 0.4L may be carried out to extent deemed necessary by
the Surveyor.
3.1.3

Non-Destructive Testing (NDT)


To supplement this CVI, if suspect or considered necessary by the Surveyor, random NDT of
associated welds may be carried out to extent deemed necessary by the Surveyor.

Results of NDT are to be maintained as a permanent record of the drilling unit, and be readily
available to the attending Surveyors during subsequent periodical surveys of the hull.
3.1.4

Hull Thickness Measurement


See 7-2-5/Table 1.

Gauging reports completed by the ABS approved external specialists and endorsed by the Surveyor
are to be maintained as a permanent record of the drilling unit, and be readily available to the
attending Surveyors during subsequent periodical surveys of the hull.
3.1.5

Corrosion Control
If coating condition of special application structures is found to be in Poor condition, internal
surfaces of such structures are to be subjected to CVI and gauging to the extent deemed necessary
by the attending Surveyor.

Where gauging results indicate Substantial Corrosion and no immediate structural repair is carried
out before completion of this Special Periodical Survey, the corroded areas are to be subjected to
extensive GVI, CVI and Gauging, during subsequent Annual Surveys.

3.3

Special Periodical Survey Hull No. 2


3.3.1

General Visual Inspection (GVI)


Requirements of 7-2-5/3.1.1 are to be complied with.

3.3.2

Close Visual Inspection (CVI)


All external surfaces of special application structures located above the waterline and within
amidships 0.4L is to be subjected to CVI.

All four main deck moon pool corner plating is to be subjected to CVI. The CVI is to include
external surfaces as well as internal support members of these structures.
If found suspect or considered necessary by the Surveyor, CVI of special or primary application
structures located above the waterline and within amidships 0.4L may be carried out to extent
deemed necessary by the Surveyor.
As a visual guidance, 7-2-5/Figure 1 illustrates some of the typical special application structures
that may be subjected to CVI and NDT required by 7-2-5/3.3.

134

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

7
2
5

Surveys
Surveys After Construction
Special Periodical Surveys

7-2-5

FIGURE 1
CVI and NDT during SPS Hull No. 2 of Drillships (2014)

3.3.3

Nondestructive Testing (NDT)


To supplement this CVI, if suspect or considered necessary by the Surveyor, random NDT of
associated welds may be carried out to extent deemed necessary by the Surveyor.

Weld joints of at least one representative corner main deck plating of such special application
structure is to be subjected to surface NDT.
If any defect found during the initial NDT or considered suspect by the attending Surveyor, NDT
may be extended to the internal members or other corners of the moon pool opening.
Results of all CVI and NDT are to be maintained as a permanent record of the drilling unit, and be
readily available to the attending Surveyors during subsequent periodical surveys of the hull.
3.3.4

Hull Thickness Measurement


See 7-2-5/3.1.4.

3.3.5

Corrosion Control
If coating condition of special application structures is found to be in Poor condition, internal
surfaces of such structures are to be subjected to CVI and gauging to the extent deemed necessary
by the attending Surveyor.

Where gauging results indicate Substantial Corrosion and no immediate structural repair is
carried out before completion of this Special Periodical Survey, the corroded areas are to be
subjected to extensive GVI, CVI and Gauging, during subsequent Annual Surveys.
In addition, where gauging results indicate a global Substantial Corrosion and no immediate
structural repair is carried out before completion of this Special Periodical Survey, the Surveyor
may also require global strength analysis to be verified by ABS engineering before crediting the
Special Periodical Survey Hull.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

135

Part
Chapter
Section

3.5

7
2
5

Surveys
Surveys After Construction
Special Periodical Surveys

7-2-5

Special Periodical Survey Hull No. 3


3.5.1

General Visual Inspection (GVI)


Requirements of 7-2-5/3.1.1 are to be complied with.

3.5.2

Close Visual Inspection (CVI)


All special and primary application structures located within amidships 0.4L are to be subjected to CVI.

This CVI is to include external surfaces as well as internal support members of these structures.
If found suspect or considered necessary by the Surveyor, CVI of special or primary application
structures located within amidships 0.6L may be carried out to extent deemed necessary by the
Surveyor.
As a visual guidance, 7-2-5/Figure 2 illustrates some of the typical special and primary application
structures in way of amidships 0.4L that may be subjected to CVI and NDT required by 7-2-5/3.5.

FIGURE 2
CVI and NDT during SPS Hull No. 3 of Drillships (2014)

3.5.3

Nondestructive Testing (NDT)


To supplement this CVI, if suspect or considered necessary by the Surveyor, random NDT of
associated welds may be carried out to extent deemed necessary by the Surveyor.

Weld joints of all corner main deck and bottom shell plating of such special application structure
is to be subjected to surface NDT. This NDT is to include internal special and primary members of
all four corners of the moon pool opening.
Results of all CVI and NDT are to be maintained as a permanent record of the drilling unit, and be
readily available to the attending Surveyors during subsequent periodical surveys of the hull.
136

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

3.7

7
2
5

Surveys
Surveys After Construction
Special Periodical Surveys

3.5.4

Hull Thickness Measurement


See 7-2-5/3.1.4.

3.5.5

Corrosion Control
The requirements of 7-2-5/3.3.5 are to be complied with.

7-2-5

Special Periodical Survey Hull No. 4 and Subsequent Special Surveys


3.7.1

General Visual Inspection (GVI)


The requirements of 7-2-5/3.1.1 are to be complied with.

3.7.2

Close Visual Inspection (CVI)


All special and primary application structures located within amidships 0.6L are to be subjected to CVI.

This CVI is to include external surfaces as well as internal support members of these structures.
3.7.3

Nondestructive Testing (NDT)


To supplement this CVI, all special and primary application structures located within amidships 0.4L
are to be subjected to NDT. This NDT is to include external and internal members of the special
and primary structures.

Results of all CVI and NDT are to be maintained as a permanent record of the drilling unit, and be
readily available to the attending Surveyors during subsequent periodical surveys of the hull.

3.5.4

Hull Thickness Measurement


See 7-2-5/3.1.4.

3.7.5

Corrosion Control
The requirements of 7-2-5/3.3.5 are to be complied with.

Column-Stabilized Drilling Units (2014)


On column-stabilized drilling units, in addition to the general requirements of 7-2-5/1, the following
vessel-specific requirements are to be carried out to the satisfaction of the attending Surveyor.

5.1

Special Periodical Survey Hull No. 1


5.1.1

General Visual Inspection (GVI)


All spaces and tanks of the drilling unit are to be subjected to GVI.

Particular attention is to be paid to the following structural areas:

5.1.2

i)

Connections of columns and diagonals to upper hull or platform

ii)

Connections of columns and diagonals to lower hull or pontoons

iii)

Joints of supporting structure, including diagonals, braces and horizontals, together with
gussets and brackets

iv)

Internal continuation or back-up structure for the above

Close Visual Inspection (CVI)


All suspect areas found during GVI are to be subjected to CVI.

External surfaces of randomly selected areas of special application structures are to be subjected to
CVI. This random selection by the Surveyor is to at least include one typical connection of:
i)

A column to a lower hull

ii)

A column to the upper hull

iii)

A column to a bracing

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

137

Part
Chapter
Section

7
2
5

5.1.3

Surveys
Surveys After Construction
Special Periodical Surveys

7-2-5

iv)

A bracing to another bracing

Note:

Randomly selected area for CVI is to at least cover 10% of the overall length of the connection but not
less than 1 m in length.

Nondestructive Testing (NDT)


To supplement this CVI, if suspect or considered necessary by the Surveyor, random NDT of
associated welds may be carried out to extent deemed necessary by the Surveyor.

Results of NDT are to be maintained as a permanent record of the drilling unit, and be readily
available to the attending Surveyors during subsequent periodical surveys of the hull.
5.1.4

Hull Thickness Measurement


See 7-2-5/Table 2.

Gauging reports completed by the ABS approved external specialists and endorsed by the Surveyor
are to be maintained as a permanent record of the drilling unit, and be readily available to the
attending Surveyors during subsequent periodical surveys of the hull.
5.1.5

Corrosion Control
If coating condition of special application structures is found to be in Poor condition, internal
surfaces of such structures are to be subjected to CVI and gauging to the extent deemed necessary
by the attending Surveyor.

Where gauging results indicate Substantial Corrosion and no immediate structural repair is carried
out before completion of this Special Periodical Survey, the corroded areas are to be subjected to
extensive GVI, CVI and Gauging, during subsequent Annual Surveys.
5.1.6

Lightship Displacement (2015)


Effectiveness of the weight control program is to be verified throughout operational life of all
column stabilized units.

This verification is done by carrying out a lightweight survey (also referred as deadweight survey),
in presence of ABS, during Special Periodical Survey Hull No. 1. The lightweight survey is to
be carried out in accordance with ABS agreed survey procedure (see 3-3-1/3).
If the lightweight survey indicates a change from the light ship displacement shown in the Record and
in excess of 1% of the operating displacement of the drilling unit, an inclining experiment may have
to be carried out. In such cases, ABS Engineering shall be contacted to receive specific instructions.
During the lightweight survey, following verification and measurements are to be completed:
i)

Review of records to verify recorded weight changes that will affect lightweight of the
drilling unit;

ii)

Review of tank sounding readings done by tank level gauges (random manual sounding
may be done if required by ABS Surveyor to verify correctness of gauge readings);

iii)

Review of records to verify amount of liquids such as fuel oil, lube oil, waste oil, drilling
mud, drill water, etc. during the lightweight survey;

iv)

Review of units derrick loads on substructure (such as the hook load and setback loads);

v)

Review of other records showing weights other than the above affecting weight measurement;

vi)

Draft readings by visual sighting of draft marks from columns;

vii)

Verification of operational lightweight and displacement corresponding to the mean draft;


and

viii)

Verification of operational displacement corresponding to the mean draft.

Results of a lightweight survey or an inclining experiment are to be maintained onboard the


drilling unit and be readily available to the attending Surveyors. All such records are to have an
endorsement of the rig personnel (such as the OIM). All such records are also to be endorsed by
the attending ABS Surveyor to read The lightweight survey/inclining experiment (as applicable)
was witnessed by ABS.
138

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

5.3

7
2
5

Surveys
Surveys After Construction
Special Periodical Surveys

7-2-5

Special Periodical Survey Hull No. 2


5.3.1

General Visual Inspection (GVI)


Requirements of 7-2-5/5.1.1 are to be complied with.

5.3.2

Close Visual Inspection (CVI)


Randomly selected areas of special and primary application structures are to be subjected to CVI.

This CVI is to include external surfaces as well as internal support members of these structures,
and this random selection by the Surveyor is to at least include one typical connection of:

5.3.3

i)

Horizontal and diagonal bracing to columns and upper hull, together with gussets and brackets

ii)

Horizontal and diagonal bracing to pontoons, upper hull and columns, together with gussets
and brackets

iii)

Internal back-up structure for the above

iv)

Brace-to-brace connections, together with gussets and brackets

v)

Column connection to lower and upper hulls

vi)

Fairleader connections to columns

vii)

Highly stressed areas in way of the moon pool

Note:

Randomly selected area for CVI is to at least cover 10% of the overall length of the connection but not
less than 1 m in length.

Nondestructive Testing (NDT)


To supplement this CVI, surface NDT of associated welds is to be carried out in way of above
selected areas.

Results of NDT are to be maintained as a permanent record of the drilling unit, and be readily
available to the attending Surveyors during subsequent periodical surveys of the hull.
5.3.4

Hull Thickness Measurement


See 7-2-5/5.1.4.

5.3.5

Corrosion Control
If coating condition of special application structures is found to be in Poor condition, internal
surfaces of such structures are to be subjected to CVI and gauging to the extent deemed necessary
by the attending Surveyor.

Where gauging results indicate Substantial Corrosion and no immediate structural repair is carried
out before completion of this Special Periodical Survey, the corroded areas are to be subjected to
extensive GVI, CVI and Gauging, during subsequent Annual Surveys.
In addition, where gauging results indicate a global Substantial Corrosion and no immediate
structural repair is carried out before completion of this Special Periodical Survey, the Surveyor
may also require global strength analysis to be verified by ABS engineering before crediting the
Special Periodical Survey Hull.
5.3.6

Lightship Displacement (2015)


Effectiveness of the weight control program is to be verified throughout operational life of all
column stabilized units.

If the first lightweight survey carried out during SPS Hull No.1 demonstrated that the rig
personnel were satisfactorily maintaining an effective weight control program, a comprehensive
lightweight survey may be exempted during SPS Hull No. 2 and subsequent SPS Hull.
The above mentioned exemption may be granted by the ABS Surveyor only if a record of all
changes to units hull structure, machinery, outfitting and equipment that affect its light weight
value were properly maintained in a light ship data alterations log, and taken into account during
daily operations.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

139

Part
Chapter
Section

7
2
5

Surveys
Surveys After Construction
Special Periodical Surveys

7-2-5

Effectiveness of the weight control program may then be accepted based on review of onboard
records and observation of the units operating draft. This verification is done by carrying out a
weight verification survey.
Note:

If the weight verification survey indicates a change from the light ship displacement shown in the Record
and in excess of 1% of the operating displacement of the drilling unit, an inclining experiment may have
to be carried out. In such cases, ABS Engineering shall be contacted to receive specific instructions.

During the weight verification survey, following is to be carried out by the attending Surveyor:

5.5

i)

Review of records to verify recorded weight changes that will affect lightweight of the
drilling unit;

ii)

Review of tank sounding readings done by tank level gauges (random manual sounding
may be done if required by ABS Surveyor to verify correctness of gauge readings);

iii)

Review of records to verify amount of liquids such as fuel oil, lube oil, waste oil, drilling
mud, drill water, etc. during the lightweight survey;

iv)

Review of units derrick loads on substructure (such as the hook load and setback loads);

v)

Review of records showing weights other than the above affecting light weight measurement;
and

vi)

Confirm recorded light weight changes.

Special Periodical Survey Hull No. 3


5.5.1

General Visual Inspection (GVI)


The requirements of 7-2-5/5.1.1 are to be complied with.

5.5.2

Close Visual Inspection (CVI)


All special and primary application structures are to be subjected to CVI.

This CVI is to include external surfaces as well as internal support members of these structures.
Typical areas to be subjected to CVI are as follows:
i)

Horizontal and diagonal bracing to columns and upper hull, together with gussets and brackets

ii)

Horizontal and diagonal bracing to pontoons, upper hull and columns, together with gussets
and brackets

iii)

Internal back-up structure for the above

iv)

Brace-to-brace connections, together with gussets and brackets

v)

Column connection to lower and upper hulls

vi)

Fairleader connections to columns

vii)

Highly stressed areas in way of the moon pool

Note:

This CVI is to cover 100% of all areas listed above.

As a visual guidance, 7-2-5/Figure 3 illustrates some of the typical areas in way of column-to-lower
hull, column-to-brace, and brace-to-brace connections that may be subjected to CVI and NDT
required by 7-2-5/5.5.

140

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

7
2
5

Surveys
Surveys After Construction
Special Periodical Surveys

7-2-5

FIGURE 3
CVI and NDT during SPS Hull No. 3 of CSDUs (2014)

5.5.3

Nondestructive Testing (NDT) (2016)


To supplement this CVI, extensive surface NDT of associated welds is to be carried out within a
5-year period.
Note:

Extensive NDT means that at least 50% weld length of each and every typical area examined by CVI is
to be subjected to NDT within a 5-year period. For example; randomly chosen 25% weld length of every
brace-to-brace connection examined by surface NDT twice in 5-year period will satisfy NDT of such areas.

Amount of CVI and NDT may be divided between two UWILDs carried out during each five year
cycle.
The number of joints and associated internal continuation and back-up structure, plus any gussets
or brackets that are to be subjected to NDT may be determined by the Owner and ABS with
consultation of the records and NDT results of previous surveys.
Results of NDT are to be maintained as a permanent record of the drilling unit, and be readily
available to the attending Surveyors during subsequent periodical surveys of the hull.
5.5.4

Hull Thickness Measurement


See 7-2-5/5.1.4.

5.5.5

Corrosion Control
The requirements of 7-2-5/5.3.5 are to be complied with.

5.5.6

Lightship Displacement (2015)


The requirements of 7-2-5/5.3.6 are to be complied with.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

141

Part
Chapter
Section

5.7

7
2
5

Surveys
Surveys After Construction
Special Periodical Surveys

7-2-5

Special Periodical Survey Hull No. 4 and Subsequent Special Surveys


5.7.1

General Visual Inspection (GVI)


The requirements of 7-2-5/5.1.1 are to be complied with.

5.7.2

Close Visual Inspection (CVI)


The requirements of 7-2-5/5.5.2 are to be complied with.

As a visual guidance, 7-2-5/Figure 4 illustrates some of the typical areas in way of column-to-lower
hull, column-to-brace, and brace-to-brace connections that may be subjected to CVI and NDT
required by 7-2-5/5.7.

FIGURE 4
CVI and NDT during SPS Hull No. 4 of CSDUs (2014)

5.7.3

Nondestructive Testing (NDT)


To supplement this CVI, all welds associated with areas examined by CVI are to be subjected to
100% NDT within a 5-year period.

Amount of CVI and NDT may be divided between two UWILDs carried out during each five year
cycle, preferably 50% done twice in a 5-year period.
The number of joints and associated internal continuation and back-up structure, plus any gussets
or brackets that are to be subjected to NDT may be determined by the Owner and ABS with
consultation of the records and NDT results of previous surveys.
Results of NDT are to be maintained as a permanent record of the drilling unit, and be readily
available to the attending Surveyors during subsequent periodical surveys of the hull.

142

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

7
2
5

Surveys
Surveys After Construction
Special Periodical Surveys

5.7.4

Hull Thickness Measurement


See 7-2-5/5.1.4.

5.7.5

Corrosion Control
The requirements of 7-2-5/5.3.5 are to be complied with.

5.7.6

Lightship Displacement (2015)


The requirements of 7-2-5/5.3.6 are to be complied with.

7-2-5

Self-Elevating Drilling Units (2014)


On self-elevating drilling units, in addition to the general requirements of 7-2-5/1, the following vessel-specific
requirements are to be carried out to the satisfaction of the attending Surveyor.

7.1

Special Periodical Survey Hull No. 1


7.1.1

General Visual Inspection (GVI)


All spaces, tanks, and legs of the drilling unit are to be subjected to GVI. During the GVI, particular
attention is to be paid to the following areas:

i)

Bulkheads designated as primary application structures.

ii)

Legs

iii)

All legs, including chords, braces, diagonals, gussets, racks, joints, together with leg
guides are to be examined.

On rigs with tubular or similar type legs, the legs are to be examined externally and
internally, together with internal stiffeners and pinholes, as applicable.

The extent of GVI may be limited to legs in way of the splash zone.

Jack-House and Leg Wells

iv)

Leg Jacking or other Elevating Systems

v)

Leg jacking or other elevating systems externally.

Jetting Piping System

vi)

Structure in, around and under jack-houses and leg wells.

Jetting piping systems or other external piping, particularly where penetrating mats or
spud cans.

Spud Cans or Mats

Internal and external examination of spud cans or mat.


Note:

Spud cans and other bottom spaces subject to contact with, or accumulation of, bottom
soil should be thoroughly ventilated and carefully monitored for pocketing or emission of
hazardous gases prior to, and during, internal inspection.

Where the spud cans or the mat is partly or entirely obscured below the mud line
when the Special Periodical Survey is otherwise being completed, consideration may
be given to postponement of these examinations until the next rig move.
7.1.2

Close Visual Inspection (CVI)


If found suspect or considered necessary by the Surveyor, CVI of special or primary application
structures located above the waterline may be carried out to extent deemed necessary by the
Surveyor.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

143

Part
Chapter
Section

7
2
5

7.1.3

Surveys
Surveys After Construction
Special Periodical Surveys

7-2-5

Nondestructive Testing (NDT)


To supplement this CVI, if suspect or considered necessary by the Surveyor, random NDT of
associated welds may be carried out to extent deemed necessary by the Surveyor.

Results of NDT are to be maintained as a permanent record of the drilling unit, and be readily
available to the attending Surveyors during subsequent periodical surveys of the hull.
7.1.4

Hull Thickness Measurement


See 7-2-5/Table 3.

Gauging reports completed by the ABS approved external specialists and endorsed by the Surveyor
are to be maintained as a permanent record of the drilling unit, and be readily available to the
attending Surveyors during subsequent periodical surveys of the hull.
7.1.5

Corrosion Control
If coating condition of special or primary application structures is found to be in Poor condition,
such structures are to be subjected to CVI and gauging to the extent deemed necessary by the
attending Surveyor.

Where gauging results indicate a global Substantial Corrosion and no immediate structural repair
is carried out before completion of this Special Periodical Survey, the corroded areas are to be
subjected to extensive GVI, CVI and Gauging, during subsequent Annual Surveys.

7.3

Special Periodical Survey Hull No. 2


7.3.1

General Visual Inspection (GVI) (2016)


The requirements of 7-2-5/7.1.1 are to be complied with.

For the mat supported drilling units, alternative means of internal examination may be specially
considered on a case-by-case basis (see also 7-2-6/Table 1). Owners submitted alternative means
is to be reviewed and agreed upon by the respective offshore ACS Office before the survey commences
and the same is to be discussed during the pre-planning meeting held onboard.
7.3.2

Close Visual Inspection (CVI)


All special and primary application structures and identified critical structural areas are to be
subjected to extensive CVI.

The following is an outline of some of the areas that will be subjected to CVI:
i)

Leg-to-spudcan connections plus 2 bays (to extent deemed necessary by the Surveyor) of
leg above the top of the spudcan

ii)

Jackhouse/jackcase-to-deck connections

iii)

Brace-to-chord connection in areas of leg that have been predominately in way of the
upper and lower guides
Note:

iv)

Areas in way of the upper guides are to be examined and subjected to NDT to identify any
damage resultant from towing the drilling unit with its legs elevated. Areas in way of the lower
guides are to be examined and subjected to NDT to identify any damage as a consequence of
operating in the elevated/drilling mode.

Leg-to-mat connections
Note:

In general, these connections are considered to be Special Application Structures and are to
be treated accordingly. 100% of all leg-to-mat connections are to be subjected to CVI.

As a visual guidance, 7-2-5/Figure 5 illustrates some of the typical primary application structures
in way of leg-to-spud can connections that may be subjected to CVI and NDT required by 7-2-5/7.3.

144

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

7
2
5

Surveys
Surveys After Construction
Special Periodical Surveys

7-2-5

FIGURE 5
CVI and NDT during SPS Hull No. 2 of SEDUs (2014)
SPS #2
CVI and NDT may include areas in way of 2 bays above the leg-spudcan connection as
deemed necessary by the Surveyor.
CVI Surfaces are to be cleaned for a meaningful examination.
NDT To be examined by MPI or ACFM.

Port Leg

Fwd Leg

CVI

CVI

NDT

NDT

Stbd Leg

CVI

NDT

The leg-spudcan connections


are to be subjected to
extensive examination.

At least one leg-spudcan connection


(chosen at random) from each leg
should be examined.

CVI

NDT

7.3.3

Nondestructive Testing (NDT)


To supplement this CVI, if suspect or considered necessary by the Surveyor, random NDT of
associated welds may be carried out to extent deemed necessary by the Surveyor.

The following is an outline of some of the areas that will be subjected to CVI:
i)

Leg-to-spudcan connections plus 2 bays (to extent deemed necessary by the Surveyor) of
leg above the top of the spudcan
Note:

The number of leg joints and associated structure that is to be subjected to NDT is to be determined
by the Owner and ABS with consultation of the records and NDT results of previous surveys
and service history of the drilling unit. However, at least one such connection of each leg is to
be subjected to NDT.

ii)

Jackhouse/jackcase-to-deck connections

iii)

Brace-to-chord connection in areas of leg that have been predominately in way of the upper
and lower guides
Note:

iv)

Areas in way of the upper guides are to be examined and subjected to NDT to identify any
damage resultant from towing the drilling unit with its legs elevated. Areas in way of the lower
guides are to be examined and subjected to NDT to identify any damage as a consequence of
operating in the elevated/drilling mode.

Leg-to-mat connections
Note:

In general, these connections are considered to be Special Application Structures and are to
be treated accordingly. At least 25% of every leg-to-mat connections are to be subjected to NDT.

If any defect found during the initial NDT or considered suspect by the attending Surveyor, NDT
may be extended to other areas or leg joints.
Results of NDT are to be maintained as a permanent record of the drilling unit, and be readily
available to the attending Surveyors during subsequent periodical surveys of the hull.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

145

Part
Chapter
Section

7
2
5

Surveys
Surveys After Construction
Special Periodical Surveys

7-2-5

7.3.4

Hull Thickness Measurement


See 7-2-5/7.1.4.

7.3.5

Corrosion Control
If coating condition of special application structures is found to be in Poor condition, internal
surfaces of such structures are to be subjected to CVI and gauging to the extent deemed necessary
by the attending Surveyor.

Where gauging results indicate Substantial Corrosion and no immediate structural repair is carried
out before completion of this Special Periodical Survey, the corroded areas are to be subjected to
extensive GVI, CVI and Gauging, during subsequent Annual Surveys.
In addition, where gauging results indicate a global Substantial Corrosion and no immediate
structural repair is carried out before completion of this Special Periodical Survey, the Surveyor
may also require global strength analysis to be verified by ABS engineering before crediting the
Special Periodical Survey Hull.

7.5

Special Periodical Survey Hull No. 3


7.5.1

General Visual Inspection (GVI)


The requirements of 7-2-5/7.1.1 are to be complied with.

7.5.2

Close Visual Inspection (CVI)


All special and primary application structures and identified critical structural areas are to be
subjected to extensive CVI.

The following is an outline of some of the areas that will be subjected to CVI:
i)

Leg-to-spudcan connections plus 2 bays of leg above the top of the spudcan
Note:

All leg-to-spudcan connections plus 2 bays of leg above the top of the spudcan and associated
structure are to be subjected to 100% CVI.

ii)

Jackhouse/jackcase-to-deck connections

iii)

Brace-to-chord connection in areas of leg that have been predominately in way of the upper
and lower guides
Note:

iv)

Areas in way of the upper guides are to be examined and subjected to NDT to identify any
damage resultant from towing the drilling unit with its legs elevated. Areas in way of the lower
guides are to be examined and subjected to NDT to identify any damage as a consequence of
operating in the elevated/drilling mode.

Leg-to-mat connections
Note:

In general, these connections are considered to be Special Application Structures and are to
be treated accordingly. All leg-to-mat connections are to be subjected to 100% CVI.

As a visual guidance, 7-2-5/Figure 6 illustrates some of the typical primary application structures in
way of leg-to-spud can connections that may be subjected to CVI and NDT required by 7-2-5/7.5.

146

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

7
2
5

Surveys
Surveys After Construction
Special Periodical Surveys

7-2-5

FIGURE 6
CVI and NDT during SPS Hull No. 3 of SEDUs (2014)
SPS #3
CVI and NDT is to include areas in way of 2 bays above the leg-spudcan connections.
CVI Surfaces are to be cleaned for a meaningful examination.
NDT To be examined by MPI or ACFM.

Port Leg

Fwd Leg

CVI

CVI

NDT

NDT

NDT

Stbd Leg

NDT
CVI

CVI
All (100%) leg-spudcan
connections are to be
examined.

NDT

NDT

NDT

NDT
NDT

7.5.3

NDT

All (100%) leg-spudcan


connections of every leg
are to be examined.

Nondestructive Testing (NDT) (2016)


To supplement this CVI, if suspect or considered necessary by the Surveyor, random NDT of
associated welds may be carried out to extent deemed necessary by the Surveyor.

The following is an outline of some of the areas that will be subjected to CVI:
i)

Leg-to-spudcan connections plus 2 bays of leg above the top of the spudcan. Additional
bays may be subjected to NDT as deemed necessary by the attending Surveyor.
Note:

All leg-to-spudcan connections plus 2 bays of leg above the top of the spudcan and associated
structure are to be subjected to 100% NDT.

ii)

Jackhouse/jackcase-to-deck connections

iii)

Brace-to-chord connection in areas of leg that have been predominately in way of the upper
and lower guides
Note:

iv)

Areas in way of the upper guides are to be examined and subjected to NDT to identify any
damage resultant from towing the drilling unit with its legs elevated. Areas in way of the lower
guides are to be examined and subjected to NDT to identify any damage as a consequence of
operating in the elevated/drilling mode.

Leg-to-mat connections
Note:

In general, these connections are considered to be Special Application Structures and are to
be treated accordingly. Entire length of (100%) every leg-to-mat connections are to be subjected
to NDT.

If any defect found during the initial NDT or considered suspect by the attending Surveyor, NDT
may be extended to other areas or leg joints.
Results of NDT are to be maintained as a permanent record of the drilling unit, and be readily
available to the attending Surveyors during subsequent periodical surveys of the hull.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

147

Part
Chapter
Section

7.7

148

7
2
5

Surveys
Surveys After Construction
Special Periodical Surveys

7.5.4

Hull Thickness Measurement


See 7-2-5/7.1.4.

7.5.5

Corrosion Control
The requirements of 7-2-5/7.3.5 are to be complied with.

7-2-5

Special Periodical Survey Hull No. 4 and Subsequent Special Surveys


7.7.1

General Visual Inspection (GVI)


The requirements of 7-2-5/7.1.1 are to be complied with.

7.7.2

Close Visual Inspection (CVI)


The requirements of 7-2-5/7.5.2 are to be complied with.

7.7.3

Nondestructive Testing (NDT)


The requirements of 7-2-5/7.5.3 are to be complied with.

7.7.4

Hull Thickness Measurement


See 7-2-5/7.1.4.

7.7.5

Corrosion Control
The requirements of 7-2-5/7.3.5 are to be complied with.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

7
2
5

Surveys
Surveys After Construction
Special Periodical Surveys

7-2-5

TABLE 1
Thickness Gauging Requirements for Surface-Type Units (2012)
Special Periodical Survey
Number 1
1)

Suspect areas throughout


the unit.

Special Periodical Survey


Number 2
1)
2)

3)

Special Periodical Survey


Number 3

Suspect areas throughout


1)
the unit.
(2012) One transverse
2)
section of deck plating
abreast the moon pool
opening within the
amidships 0.6L, together
with internals in way as
deemed necessary. Where
unit is configured with
side ballast tanks, the
plating and internals of the
tanks are also to be gauged
in way of the section
chosen.
Moon pool boundary
bulkhead plating.
3)
4)

Suspect areas throughout


the unit.
(2012) Two girth belts of
deck, bottom and side
plating abreast the moon
pool and one hatch
opening within the
amidships 0.6L together
with internals in way as
deemed necessary. Where
unit is configured with
side ballast tanks, the
plating and internals of the
tanks to be gauged in way
of the required belts,
Remaining internals in
ballast tanks to be gauged
as deemed necessary.
Moon pool boundary
bulkhead plating.
Internal in forepeak tank
as deemed necessary.

Special Periodical Survey


Number 4
1)
2)

3)
4)

5)

6)

7)

8)

9)

Suspect areas throughout


the unit.
(2012) A minimum of
three girth belts of deck,
bottom, side, and
longitudinal-bulkhead
plating in way of the moon
pool and other areas within
the amidships 0.6L, together
with internals in way
(including in perimeter
ballast tanks, where fitted
in way of belts).
Moon pool boundary
bulkhead plating.
Internals in forepeak and
after peak tanks as deemed
necessary.
Lowest strake of all
transverse bulkheads in
hold spaces. Remaining
bulkhead plating to be
gauged as deemed
necessary.
All plates in two wind and
water strakes, port and
starboard, full length.
All exposed main deck
plating full length and all
exposed first-tier superstructure deck plating
(poop, bridge and
forecastle decks).
All keel plates full length
plus additional bottom
plating as deemed
necessary by the Surveyor,
particularly in way of
cofferdams and machinery
spaces.
Duct keel or pipe tunnel
plating or pipe tunnel
plating and internals as
deemed necessary.

Notes:
1

2
3

With reference to ballasting history and arrangement and condition of coatings, tanks and specific thickness gauging
locations should be selected which will provide the best representative sampling of areas likely to be most exposed
to corrosion effect.
Gauging requirements noted may be modified as deemed necessary or appropriate by the Surveyor if the structure
remains effectively protected against corrosion by a permanent type special coating.
In any case where excessive wastage is evident, additional gaugings may be required.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

149

Part
Chapter
Section

7
2
5

Surveys
Surveys After Construction
Special Periodical Surveys

7-2-5

TABLE 2
Thickness Gauging Requirements for Column-Stabilized Units (2012)
Special Periodical Survey
Number 1
1)
2)

Suspect areas throughout


the unit.
Columns and bracings
where wastage is evident
in Splash Zone.

Special Periodical Survey


Number 2
1)
2)

3)

Suspect areas throughout


the unit.
Representative gaugings
of columns and bracings
in Splash Zone together
with internals in way as
deemed necessary.
Special and primary
application structure
where wastage is evident.

Special Periodical Survey


Number 3
1)
2)

3)

4)
5)

6)

Suspect areas throughout


the unit.
Representative gaugings,
throughout, of special and
primary application
structures.
1 girth belt of each of 2
columns and 2 bracings in
Splash Zone together with
internals in way as
deemed necessary.
Chain locker internals as
deemed necessary.
Lower hulls in way of
mooring lines where
wastage is evident.
1 girth belt of each lower
hull between one set of
columns.

Subsequent Special Periodical


Survey
1)
2)

3)

4)
5)

6)

7)

Suspect areas throughout


the unit.
Comprehensive gaugings,
throughout, of special and
primary application
structures.
1 girth belt of each of onehalf of the columns and
bracings in Splash Zone
and internals in way as
deemed necessary (i.e.,
gauge half of the units
columns and bracings in
Splash Zone).
Chain locker internals as
deemed necessary.
Lower hulls in way of
mooring lines where
wastage is evident.
1 girth belt of each lower
hull between one set of
columns.
Representative gaugings
of substructure of drilling
derrick.

Notes:
1

2
3
4
5

150

With reference to the ballasting history and arrangement and condition of coatings, tanks and specific thickness
gauging locations should be selected which will provide the best representative sampling of areas likely to be most
exposed to corrosion effect.
Gauging requirements noted may be modified as deemed necessary or appropriate by the Surveyor if the structure
remains effectively protected against corrosion by a permanent type special coating.
In any case where excessive wastage is evident, additional gaugings may be required.
Structure application designations (special, primary, secondary) are defined in Section 3-1-4.
(2012) Splash Zone is to be considered as the structural area that has been periodically in and out of the water
when the unit was at its operating depth, most of the time during the past five-year period. Based on operational
record of the unit, additional zones may also be gauged.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

7
2
5

Surveys
Surveys After Construction
Special Periodical Surveys

7-2-5

TABLE 3
Thickness Gauging Requirements for Self-Elevating Units (2012)
Special Periodical Survey
Number 1
1)

Suspect areas throughout


the unit (particular attention
to be paid to the legs in
way of the Splash Zone).

Special Periodical Survey


Number 2
1)
2)
3)

4)

Suspect areas throughout


the unit.
Legs in way of Splash
Zone.
Primary application
structures where wastage
is evident.
Representative gaugings
of upper hull deck and
bottom plating and
internals of one preload
(ballast) tank.

Special Periodical Survey


Number 3
1)
2)

3)
4)

5)

Suspect areas throughout


the unit.
Representative gaugings,
throughout, of special and
primary application
structures.
Leg well structure.
Representative gaugings
of deck, bottom, and side
shell plating of hull and
mat.
Representative gaugings
of upper hull deck and
bottom plating and
internals of at least two
preload (ballast) tanks.

Special Periodical Survey


Number 4
1)
2)

3)
4)

5)
6)

Suspect areas throughout


the unit.
Comprehensive gaugings,
throughout, of special and
primary application
structures.
Leg well structure.
Representative gaugings
of deck, bottom, and side
shell plating of hull and
mat.
Substructure of derrick as
deemed necessary.
Representative gaugings
of internals of all preload
(ballast) tanks.

Notes:
1

2
3
4
5

With reference to the operating history and arrangement and condition of coatings, specific thickness gauging locations
should be selected which will provide the best representative sampling of areas likely to be most exposed to corrosion
effect.
Gauging requirements noted may be modified as deemed necessary or appropriate by the Surveyor if the structure
remains effectively protected against corrosion by a permanent type special coating.
In any case where excessive wastage is evident, additional gaugings may be required.
Structural application designation (special, primary, secondary) are defined in Section 3-1-4.
(2012) Splash Zone is to be considered as the structural area that has been periodically in and out of the water when
the unit was at its operating depth, most of the time during the past five-year period. Based on operational record
of the unit, additional zones may also be gauged.

Special Periodical Survey Machinery (2010)


Special Periodical Survey Machinery is to include compliance with the Annual Survey requirements and,
in addition, the following requirements as listed below are to be carried out, as applicable, the parts
examined, placed in satisfactory condition and reported upon.

9.1

Correlation with Special Periodical Survey Hull


Main and auxiliary engines of all types for drilling units are to undergo Special Periodical Survey at intervals
similar to those for Special Periodical Survey Hull in order that both may be recorded at approximately
the same time. In cases where damage has involved extensive repairs and examination, the survey thereon
may be considered as equivalent to a Special Periodical Survey.

9.3

Parts to be Examined All Types of Mobile Offshore Drilling Units


(2012) In addition to the requirements for Annual Survey, at each Special Periodical Survey, special
attention is to be given to the following requirements, as applicable.
9.3.1

Openings to the Sea and Fastenings


All openings to the sea, including sanitary and other overboard discharges together with the cocks
and valves connected therewith, are to be examined internally and externally while the drilling
unit is in drydock or at the time of underwater examination in lieu of drydocking, and the fastenings
to the shell plating are to be renewed when considered necessary by the Surveyor.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

151

Part
Chapter
Section

7
2
5

Surveys
Surveys After Construction
Special Periodical Surveys

7-2-5

9.3.2

Pumps and Pumping Arrangements


Pumps and pumping arrangements, including valves, cocks, pipes, and strainers, are to be examined.

9.3.3

Nonmetallic Expansion Pieces


Nonmetallic flexible expansion pieces in the main salt-water circulating system are to be examined
internally and externally.

9.3.4

Bilge and Ballast System, and other Systems


The Surveyor is to be satisfied with the operation of the bilge and ballast systems. Other systems
are to be tested as considered necessary.

9.3.5

Machinery Foundations (2012)


The foundations of machinery, particularly those categorized as Primary Application Structure
are to be examined.

9.3.6

Pressure Vessels
Heat exchangers and other unfired pressure vessels (except those used solely for drilling operations
and complying with a recognized standard) with design pressures over 6.9 bar (7 kgf/cm2, 100 psi)
are to be examined, opened out or thickness gauged and pressure tested as considered necessary,
and associated relief valves proven operable. Evaporators that operate with a vacuum on the shell
need not be opened, but may be accepted on the basis of satisfactory external examination and
operational test or review of operating records

9.5

Parts to be Examined Self-Propelled Mobile Offshore Drilling Units (2012)


On self-propelled units, in addition to the requirements for Annual Survey and the applicable requirements
of 7-2-5/9.3, the main and auxiliary machinery, including pressure vessels, should be surveyed in accordance
with the requirements of the latest edition of the ABS Rules for Survey After Construction (Part 7), as
applicable to self-propelled vessels constructed in accordance with the Steel Vessel Rules, and the following,
as applicable.

11

Special Periodical Survey Electrical Equipment (2010)


Special Periodical Survey Electrical Equipment is to include compliance with the Annual Survey requirements
and, in addition, the following requirements as listed below are to be carried out, as applicable, the parts
examined, placed in satisfactory condition and reported upon.

11.1

Correlation with Special Periodical Surveys Hull


The entire installation, including auxiliary and emergency equipment is to undergo Special Periodical
Survey at intervals similar to those for Special Periodical Survey Hull in order that both may be recorded
at approximately the same time. In cases where damage has involved extensive repairs and examination,
the survey thereon may be considered as equivalent to a Special Periodical Survey.

11.3

Parts to be Examined
11.3.1 Main Switchboards and Distribution Panels
Fittings and connections on main switchboards and distribution panels are to be examined, and
care is to be taken to see that no circuits are over fused.
11.3.2 Cables
Cables are to be examined as far as practicable without undue disturbance of fixtures.
11.3.3 Generator Run
All generators are to be run under load, either separately or in parallel; switches and circuit breakers
are to be tested.

152

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

7
2
5

Surveys
Surveys After Construction
Special Periodical Surveys

7-2-5

11.3.4 Equipment and Circuits


All equipment and circuits are to be inspected for possible development of physical changes or
deterioration. The insulation resistance of the circuits is to be measured between conductors and
between conductors and ground and these values compared with those previously measured. Any
large and abrupt decrease in insulation resistance is to be further investigated and either restored to
normal or renewed as indicated by the conditions found.
11.3.5 Electrical Auxiliaries, Generators and Motors
The specified electrical auxiliaries for vital purposes, generators and motors are to be examined
and their prime movers opened for inspection. The insulation resistance of each generator and motor
is to be measured.
11.3.6 Accumulator Batteries (2012)
The accumulator batteries are to be examined, including their maintenance schedule and ABS
reviewed procedure of maintenance.
11.3.7 Bilge Alarm (if fitted)
Bilge alarm system, if fitted, is to be tested and proven satisfactory.

11.5

Self Propelled Units Main Propulsion Apparatus


Where the unit maintains the optional AMS Notation, the windings of generators and motors are to be
thoroughly examined and found or made dry and clean. Particular attention is to be paid to the ends of the
windings of stator and rotors. After the winding have been cleaned and found dry, they are to be varnished,
if necessary, with a standard insulating varnish applied preferably by spraying.

11.7

Major Repairs
On the occasion of major repairs, the coils repaired or renewed are to be subjected to a dielectric strain test,
as specified under the applicable parts of Part 4, Chapter 3. In addition, the circuits containing the repairs
or renewals and coils which have been disturbed during repairs are to be subjected to dielectric strain tests
for one minute by application of a potential of 125% of the maximum operating voltage of the circuits to
which it is applied. The direct current fields of generators and motors are to be subjected for one minute to
a test potential equal to 50% of the value specified under the applicable parts of Part 4, Chapter 3 and the
whole apparatus operated under full-load conditions.

13

Special Periodical Survey Special Features (All Types) (2010)


Special Periodical Survey Special Features is to include compliance with the Annual Survey requirements
and, in addition, the following requirements as listed below are to be carried out, as applicable, placed in
satisfactory condition and reported upon.
Mobile offshore drilling units may have many items of machinery and electrical equipment not found on
conventional cargo vessels. Certain of these items are required for classification even if the unit is without
propulsion machinery. Items to be especially examined and reported upon at all Special Periodical Surveys
are listed in 7-2-5/13.3 through 7-2-5/13.13 for all types of Mobile Offshore Drilling Units, and additionally
7-2-5/13.15 for Self Elevating Drilling Units.

13.1

Correlation with Special Periodical Surveys Hull


The entire installation is to undergo Special Periodical Survey at intervals similar to those for Special Periodical
Survey Hull in order that both may be recorded at approximately the same time. In cases where damage
has involved extensive repairs and examination, the survey thereon may be considered as equivalent to a
Special Periodical Survey.

13.3

Hazardous Areas
Hazardous areas, delineated in accordance with the onboard copy of the ABS approved hazardous area
plan, are to be examined. The onboard copy of the ABS approved listing of electrical equipment is to be
used for survey of hazardous areas. The following items are to be especially examined, tested as necessary,
and proven satisfactory:

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

153

Part
Chapter
Section

7
2
5

Surveys
Surveys After Construction
Special Periodical Surveys

7-2-5

Gas-tight doors and closures in boundary bulkheads or decks of hazardous areas, including those fitted
in air-lock passages.

Drains and scuppers from hazardous areas, and associated loop-seal traps where fitted.

Explosion-proof or intrinsically safe electric lighting, electrical fixtures and instrumentation, in particular
any associated sealing arrangements.

Purged electrical equipment, including visual and audible indication of loss of purge alarms or shutdowns.

Electric motors, including closed-loop ventilating systems for large motors. Automatic power disconnect
to motors in case of loss of ventilating air.

Ventilating systems, including ductwork, fans, inlets and outlets for enclosed restricted areas.

Ventilation alarm systems, including pressure differential devices, if fitted.

For Units built prior to 1996 that may not have an onboard copy of the ABS approved listing of electrical
equipment in hazardous areas, the equipment in the hazardous areas are to be examined to the satisfaction
of the attending Surveyor.

13.5

Remote Shutdown Arrangements (1996)


Remote shutdown arrangements for fuel-oil transfer service pumps and ventilating equipment, together
with oil tank outlet valves, where capable of being remotely closed, are to be proven satisfactory. Emergency
switches, where required by the Rules, for all electrical equipment, including main and emergency generators,
except alarm and communication systems and lighting in vital areas such as escape routes and landing
platforms, are to be proven satisfactory.

13.7

Passive Fire Protection System


A general examination of the passive fire protection system is to be made in order that the Surveyor may
be satisfied as to its efficient state. The following items are to be especially examined:

13.9

154

Structural fire protection system and protection of accommodation spaces, service spaces and control
stations. This examination is to verify that fire integrity of bulkheads and decks, all openings and access
through enclosed spaces, as well as closing devices, satisfactorily maintain original integrity of these
spaces and in accordance with approved design and construction.

Active Fire Protection Systems and Equipment


A general examination of applicable active fire protection system is to be made in order that the Surveyor
may be satisfied as to its efficient state. The following items are to be especially proven in compliance with
the Rules:

Fire control plans are permanently exhibited for the guidance of operating personnel, showing clearly
for each deck provision, location, controls and particulars, as applicable, of the; fixed fire detection,
alarm and extinguishing systems, portable fire-fighting equipment and appliances, controls of fuel-oil
pumps and valves, ventilation system shut-downs and closing of openings, and locations and type of
fire retarding bulkheads. Where onboard conditions are found to have been modified, exhibited plans
are to reflect the onboard conditions, and fire control plans are to be submitted for review.

Fire main systems are to be examined and tested, as applicable, particularly to verify that; fire pumps,
including their relief valves (if fitted), fire main piping together with associated hydrants, hoses and
nozzles, and international shore connection remain in satisfactory condition. Pressure and operational
tests of the fire main system, as required by the Rules, are to be carried out.

Additional fixed fire fighting systems, such as those using gas smothering, foam, fixed pressure water
spraying, and systems protecting helicopter decks are to be examined and tested, and to be proven
satisfactory.

Portable and semi-portable fire extinguishers and sand (where provided) are to be examined, all portable
soda-acid and foam extinguishers are to be serviced, and all dry chemical and CO2 extinguishers are to
be weighed and recharged, as necessary, and proven satisfactory.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

7
2
5

Surveys
Surveys After Construction
Special Periodical Surveys

7-2-5

Firemans outfits, consisting of a breathing apparatus, a lifeline, a safety lamp, an axe, nonconductive
boots and gloves, a rigid helmet and protective clothing complying with the requirements of the Rules
are to be examined, and verified as to be easily accessible and ready for use, and stored in separate
positions so that a fire in one location would not block access to both outfits.

Fire detection system and its alarms, general alarms system, mud tank level alarms, ventilation system
alarms, and gas detection system and its alarms, are to be examined and tested, and proven satisfactory.

13.11 Outfitting
A general examination of following outfitting items is to be made in order that the Surveyor may be satisfied
as to its efficient state. The following items are to be especially proven in compliance with the Rules:

Means of escape

Means of access and egress

Guards and rails

Emergency control stations

Arrangements in machinery spaces

Segregation of fuel oil purifiers

Rotary table area

Fire precautions in machinery spaces

13.13 Piping Systems Supporting the Drilling System


Piping systems supporting the drilling system, but outside the scope of Certified Drilling System (optional
Classification) equipment and associated components and complying either with these Rules or a recognized
standard as required by 4-2-1/1 are to be examined, as far as practical, operationally or hydrostatically
tested to working pressure, to the satisfaction of the Surveyor.
13.15 Self-Elevating Drilling Units Leg Jacking Systems (2011)
On self-elevating type drilling units, leg jacking systems are to be examined and reported on. Pinions and
gears of the climbing pinion gear train of rack and pinion systems are to be examined as far as practicable,
to the Surveyors satisfaction, by an effective crack detection method.
At Special Periodical Survey No. 2 and subsequent Special Periodical Surveys, the leg jacking system is to
be examined in the presence of the Surveyor by the original equipment manufacturer or other third party
inspector mutually agreeable to the owner and the Surveyor.

15

Thrusters and Dynamic Position Systems (2016)


Special Periodical Surveys are to be carried out in accordance with 7-2-5/15.1 or 7-2-5/15.3, as applicable.

15.1

Units Classed with APS or PAS Notations


Where the unit maintains the optional APS or PAS notations, thrusters are to be surveyed on the basis of
Survey Requirements for Additional Systems and Services in accordance with the requirements of
Section 7-9-6 of the ABS Rules for Survey After Construction (Part 7).

15.3

Units Classed with DPS-1, DPS-2, or DPS-3 Notations


Requirements of Annual Survey of thrusters and Dynamic Positioning (DP) system is explained in 7-2-5/7.
In addition to the requirements of the Annual Survey, complete performance tests are to be carried out to
the Surveyors satisfaction. The schedule of these tests is to be designed to demonstrate the level of
redundancy established in the FMEA (Failure Modes and Effects Analysis, see Subsection 2/11 of the ABS
Guide for Dynamic Positioning Systems). For DPS-2 and DPS-3, see Subsection 7/5 of the ABS Guide
for Dynamic Positioning Systems.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

155

Part
Chapter
Section

7
2
5

Surveys
Surveys After Construction
Special Periodical Surveys

7-2-5

15.3.1 DP Thrusters
On units with DP system, component parts of oil-lubricated thrusters are to be opened for examination
at least every five years. Internal examination of oil-lubricated retractable thrusters may be waived
only if the thrusters are maintained under an ABS approved Condition Monitoring (CM) plan and
results recorded have proven satisfactory performance. Where the thrusters are maintained under
an ABS approved CM plan, the frequency for their major overhaul (including opening up thrusters
for internal examination) may be longer than five years, provided this is indicated in the CM plan.

156

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

PART

Section 6: Drydocking Surveys or Equivalent

CHAPTER

Surveys After Construction

SECTION

Drydocking Surveys or Equivalent

Parts to be Examined

1.1

Surface-type Units (Ship or Barge Type Units)


External surfaces of the hull, keel stem, stern frame, rudder, nozzles, and sea strainers are to be selectively
cleaned and examined together with appendages, the propeller, exposed parts of stern bearing assembly, rudder
pintle and gudgeon securing arrangements, sea chests and strainers and their fastenings. Propeller shaft
bearing, rudder bearing, and steering nozzle clearances are to be ascertained and reported upon.

1.3

Column-Stabilized Units
External surfaces of the upper hull or platform, footings, pontoons or lower hulls, underwater areas of
columns, bracing and their connections, as applicable, are to be selectively cleaned and examined.
Nondestructive testing may be required of areas found to be suspect.
Sea chests and strainers are to be cleaned and examined.

1.5

Self-Elevating Units (2014)


External surfaces of the upper hull or platform, spud cans, mat, underwater areas of legs, together with their
connections, as applicable, are to be selectively cleaned and examined.
At each Drydocking Survey (or equivalent), external examination of mat or spud cans is to be carried out.
Unless otherwise recommended by the Surveyor, internal examination of mat or spud cans, which is a
requirement of Special Survey, need not be carried out during intermediate Drydocking Surveys. See
7-2-6/Table 1 for types of examination of mat or spud cans required during Drydocking Survey.

TABLE 1
Examination of Mat or Spud Cans during Drydocking Survey (2016)
Drydocking Survey

Type of Examination

1.

Intermediate Drydock before Special Survey No. 1

1.

External

2.

Drydock associate with Special Survey No. 1

2.

Internal and External

3.

Intermediate Drydock associate with Special Survey No. 1 and No. 2

3.

External

4.

Drydock associate with Special Survey No. 2, and all subsequent


Drydocking Surveys associated with Special Surveys

4.

Internal(1) and External

5.

Intermediate Drydock between Special Survey No. 2 and No. 3, and


all subsequent intermediate Drydocking Surveys

5.

Internal(2) and External

Notes:
1

(2016) For mat supported drilling units, alternative means of internal examination may be specially
considered on a case-by-case basis (agreement by the respective offshore ACS Office is required).

Only if the mat or spud cans is readily accessible, and the attending Surveyor recommends doing so. If
there is a new indication of external damage on any can or mat, internal examination is to be carried out
to the extent recommended by the attending Surveyor.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

157

Part
Chapter
Section

7
2
6

Surveys
Surveys After Construction
Drydocking Surveys or Equivalent

7-2-6

The following is an outline of some of the areas that will be subjected to close visual and extensive NDT at
each UWILD not associated with Special Surveys:
i)

Leg-to-spudcan connections

ii)

Jackhouse/jackcase-to-deck connections

iii)

Brace-to-chord connection in areas of leg that have been predominately in way of the upper and
lower guides
Note:

iv)

Leg-to-mat connections
Note:

1.7

1.9

158

Areas in way of the upper guides are to be examined and subjected to NDT to identify any damage resultant
from towing the drilling unit with its legs elevated. Areas in way of the lower guides are to be examined
and subjected to NDT to identify any damage as a consequence of operating in the elevated/drilling mode.

In general, these connections are considered to be Special Application Structures and are to be treated
accordingly.

v)

Suspect areas

Note:

Spud cans and other bottom spaces subject to contact with, or accumulation of, bottom soil should be thoroughly
ventilated and carefully monitored for pocketing or emission of hazardous gases prior to, and during, internal inspection.
Where the spud cans or mat are partly or entirely obscured below the mud line when the UWILD is otherwise
being completed, consideration will be given to postponement of the underwater examination of the unit until the
next rig move.

Ballast and Preload Spaces All units


In conjunction with Drydocking Surveys (or equivalent) after Special Survey No. 1 and between
subsequent Special Surveys, the following ballast and preload spaces are to be internally examined and the
effectiveness of coatings or corrosion control arrangements are to be verified either visually, by indicator
strips or by thickness gauging (as considered necessary), placed in satisfactory condition, as found necessary,
and reported upon.
1.7.1

Surface-Type Units
One peak tank and at least two other representative ballast tanks between the peak tank bulkheads
used primarily for water ballast.

1.7.2

Column-Stabilized Units
Representative ballast tanks in footings, lower hulls or free-flooding compartments as accessible,
and at least two ballast tanks in columns or upper hull, if applicable.

1.7.3

Self-Elevating Units
Representative ballast tanks or free-flooding compartments in mat or spud cans, if accessible, and
at least two representative upper hull salt water tanks on mat supported units or two representative
preload tanks on independent leg units.

All Units
1.9.1

Internal Examinations of Tanks and Voids


All tanks and voids which are to be internally examined are to be thoroughly ventilated and gasfreed prior to being entered and are to be carefully monitored for pocketing or emissions of
hazardous gases during examination.

1.9.2

Sea Valves
For Underwater Inspection in Lieu of Drydocking Survey associated with Special Surveys, means
are to be provided to permit the opening up of all sea valves for internal examination.

1.9.3

External Portions of Propulsion Units (2010)


External portions of propulsion units are to be examined, where applicable.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

7
2
6

Surveys
Surveys After Construction
Drydocking Surveys or Equivalent

7-2-6

Underwater Inspection in Lieu of Drydocking (UWILD) (2010)


(2016) Underwater inspection equivalent to a Drydocking Survey may be carried out at each Drydocking
Survey up to and including Special Survey No. 4 using the UWILD plan previously agreed by the offshore
Assistant Chief Surveyors (ACS) Office. The underwater inspection is to be carried out in accordance
with this Section.
For each drydocking after Special Survey No. 4, requests to carry out an UWILD in accordance with previously
approved plans are to be submitted for consideration to the respective offshore ACS Office well in advance
of the proposed survey. Approvals to carry out the UWILD after Special Survey No. 4 are to be made
available onboard for the Surveyors reference.
The following are the procedures and conditions under which a properly conducted UWILD may be credited
as a Drydocking Survey.

3.1

3.3

Conditions
3.1.1

Limitations
UWILD may not be acceptable where there is record of abnormal deterioration or damage to the
underwater structure, or where damage affecting the fitness of the unit is found during the course of
the survey.

3.1.2

Thickness Gauging and Nondestructive Testing


Underwater or internal thickness gaugings of suspect areas may be required in conjunction with
the underwater inspection. Means for underwater nondestructive testing may also be required for
fracture detection.

3.1.3

Plans and Data (2012)


Approved plans and procedures for the survey are to be made available onboard for the purpose of
carrying out an onboard preplanning of the survey with the Surveyor. These should include
nomenclature of underwater parts and drawings or forms for laying out the areas to be surveyed,
the extent of hull cleaning, nondestructive testing locations (including NDT methods) and for mapping
damage or deterioration found. The examination of items associated with the Special or Continuous
Surveys and Tail Shaft Surveys is to be included in the plans.

3.1.4

Underwater Conditions
The areas to be surveyed are to be sufficiently clean and the sea water clear enough to permit
meaningful examination and photography (if necessary) by the diver. Overall or spot cleaning may
be required by the attending Surveyor.

Physical Features
The following physical features are to be incorporated into the units design in order to facilitate the underwater
inspection. When verified, they will be noted in the units Classification for reference at subsequent surveys.
3.3.1

Stern Bearing
For self-propelled units, means are to be provided for ascertaining that the seal assembly on oillubricated bearings is intact and for verifying that the clearance or wear-down of the stern bearing
is not excessive. For oil-lubricated bearings, this may only require accurate oil-loss-rate records
and a check of the oil for contamination by sea water or white metal. For wood or rubber bearings,
an opening in the top of the rope guard and a suitable gauge or wedge would be sufficient for checking
the clearance by a diver. For oil-lubricated metal stern bearings, wear-down may be checked by
external measurements between an exposed part of the seal unit and the stern tube bossing, or by
use of the units wear-down gauge, where the gauge wells are located outboard of the seals, or the
unit can be tipped. For use of the wear-down gauges, up-to-date records of the base depths are to
be maintained onboard. Whenever the stainless steel seal sleeve is renewed or machined, the base
readings for the wear-down gauge are to be re-established and noted in the units records and in
the survey report.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

159

Part
Chapter
Section

3.5

3.7

7
2
6

Surveys
Surveys After Construction
Drydocking Surveys or Equivalent

7-2-6

3.3.2

Rudder Bearings
For self-propelled units with rudders, means and access are to be provided for determining the
condition and clearance of the rudder bearings, and for verifying that all parts of the pintle and
gudgeon assemblies are intact and secure. This may require bolted access plates and a measuring
arrangement.

3.3.3

Sea Suctions
Means are to be provided to enable the diver to confirm that the sea suction openings are clear.
Hinged sea suction grids would facilitate this operation.

3.3.4

Sea Valves
Means must be provided to examine any sea valve for the UWILD associated with the Special Survey.

Procedures
3.5.1

Exposed Areas
An examination of the outside of the structure above the waterline is to be carried out by the Surveyor.
Means and access are to be provided to enable the Surveyor to accomplish visual inspection and
nondestructive testing, as necessary.

3.5.2

Underwater Areas (2012)


An examination of the entire unit below the waterline is to be carried out by a suitably qualified
diver using closed-circuit television with two-way communication capable of being monitored by
the Surveyor, as required, or photographic documentation, or both, depending on the age and type
of unit. This is to be supplemented by the divers report, describing and attesting to the conditions
found. A copy of this divers report and pertinent photographs are to be submitted to the attending
Surveyor for retention at the local office for five (5) years. Copies are also to be retained onboard,
together with any video recording, for reference.

3.5.3

Damage Areas
Damage areas are to be photographed. Internal examination, measurements, marking and thickness
gauging of such locations may be a necessary adjunct as determined by the attending Surveyor.
Means are to be provided for locating, orienting and identifying underwater surfaces in photographs
or on video tapes.

Crediting UWILD on a Self-Elevating Drilling Unit without Completing the Examination


of Spud Cans/Mat (2012)
As mentioned under the Note of 7-2-5/7.1.1vi) and 7-2-6/1.5, where the spud cans or mat are partly or
entirely obscured below the mud line when a Special Periodical Survey or a UWILD is otherwise being
completed, consideration will be given to postponement of these examinations until the next rig move.
In such cases, where requested by the Owner, the UWILD may be credited with an outstanding to complete
the remaining examination and NDT (as applicable) at the time of next rig move, but not later than next
scheduled Drydocking Survey (or UWILD).

3.9

Incomplete UWILD over a Five-Year Period Self-Elevating Drilling Units (2012)


Where a self-elevating drilling unit has been on same location without a move for a five year period, and
therefore its two consecutive drydocking surveys could not be completed within that five year cycle, the
drilling unit will be considered a site-specific offshore installation and compliance with the ABS Rules for
Building and Classing Offshore Installation (Offshore Installation Rules) will be required.
Under the above mentioned circumstances, in order to accept the completion of the UWILD and to maintain
classification of the unit as a mobile offshore drill unit, compliance with 3/3.7.8 of the Offshore Installation
Rules will be required and necessary data is to be submitted to ABS for review.

160

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

3.11

7
2
6

Surveys
Surveys After Construction
Drydocking Surveys or Equivalent

7-2-6

Alternatives (2016)
ABS is prepared to consider alternatives to the above guidelines and would be pleased to consult with
interested clients concerning means and details for accomplishing results no less effective.
Requirements and guidance for the use of Remotely Operated Vehicle (ROV) during a UWILD are explained
in 7-2-6/3.11.1 and are considered part of a typical alternative procedure.
3.11.1 UWILD with ROVs
Provided the underwater conditions are suitable for a meaningful examination and the same is agreed
upon by the attending Surveyor, the General Visual Inspection (GVI) process of the UWILD can
be carried out by a ROV in lieu of divers.

However, if the attending Surveyor does not consider the visual examination by the ROV to be
equivalent to that by a diver, then the examination by a diver is to be carried out prior to the crediting
of the UWILD. If the ROV examination is not considered to be sufficient for determining the condition
of the hull, services of a diver are to be provided.
Following are typical disadvantages to be considered for use of ROV during UWILD.

Depending on the amount of marine growth on the hull, sufficient cleaning may not be possible
when only ROV is used.

Large size ROVs tend to have difficulty working at shallow water depths, due to swells and
excessive movement.

Not all ROVs are able to clean sea chest grids for a meaningful visual examination.

Not all ROVs are capable of properly recording the UWILD by photographic images or video.

Where the use of ROV was allowed by the attending Surveyor and underwater examination was
satisfactorily but partly carried out in way of accessible areas of the unit, remaining survey items
of the UWILD are to be carried out with a recognized diving company, in the presence of the
attending Surveyor.
Where Close Visual Inspection (CVI) is required during a UWILD, the use of ROV may be allowed
on a case-by-case basis.
The use of ROV for underwater Nondestructive Testing (NDT) and Gauging may be allowed only
when agreed upon by ABS on a case-by-case basis. In such cases, office of the respective offshore
Assistant Chief Surveyor is to be contacted by the owner to request agreement and instructions.
However, the use of ROV for underwater NDT and/or Gauging for crediting UWILD is to be also
agreed upon by the attending Surveyor.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

161

PART

Section 7: Specific Survey on Self-Elevating Units After Ocean Transit Tow

CHAPTER

Surveys After Construction

SECTION

Specific Survey on Self-Elevating Units After


Ocean Transit Tow (2012)

Ocean Transit Wet Tow


There is no ABS requirement to survey the drilling unit before the tow. A specific survey is to be carried
out on self-elevating drilling units after the completion of an ocean transit wet tow.
This survey should be carried out prior to elevating the unit and should include a comprehensive visual
examination of the structure, including helicopter support structure, as well as surface Nondestructive Testing
(NDT) of critical structural areas.
If the survey is carried out by the Owner and damage is found which affects or may affect classification,
ABS is to be notified and arrangements are to be made for survey. If the survey is carried out by the Owner
and no damage is found which affect or may affect classification, ABS is to be advised of the details of the
tow, and a confirmation survey will be made at the next periodical survey.

Ocean Transit Dry Tow


There is no ABS requirement to survey the drilling unit before the tow. An overall survey is to be carried
out on self-elevating drilling units after the completion of an ocean transit dry tow.
This overall survey should be carried out prior to elevating the unit and should include a visual examination
of the structure, including helicopter support structure, as well as surface Nondestructive Testing (NDT) of
critical structural areas, as deemed necessary.
If a survey is carried out by the Owner and damage is found which affects or may affect classification,
ABS is to be notified and arrangements are to be made for survey equivalent to 7-2-7/1 of these Rules.
If a survey is carried out by the Owner and no damage is found which affect or may affect classification,
onboard records are to be available to the Surveyor at next periodical survey.

162

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

PART

Section 8: Tail Shaft Surveys

CHAPTER

Surveys After Construction

SECTION

Tail Shaft Surveys

Surveys are to be carried out in accordance with applicable paragraphs of the latest edition of the ABS
Rules for Survey After Construction (Part 7), as applicable to vessels constructed in accordance with the
Steel Vessel Rules. However, due to low running hours on tail shafts of drilling units, the interval between
tail shaft surveys may be extended based on the following being to the satisfaction of the Surveyor:
i)

Divers external examination of stern bearing and outboard seal area, including weardown check
as far as is possible.

ii)

Internal examination of the shaft area (inboard seals) in propulsion room(s).

iii)

Confirmation of lubricating oil records (satisfactory oil loss rate, no evidence of unacceptable
contamination).

iv)

Shaft seal elements are examined/replaced in accordance with the seal manufacturers
recommendations.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

163

PART

Section 9: Boiler Surveys

CHAPTER

Surveys After Construction

SECTION

Boiler Surveys

Parts to be Examined

1.1

Internal and External Examination


At each survey, the boilers, superheaters and economizers are to be examined internally (water-steam side)
and externally (fire side).

1.3

Mountings and Safety Valves


Boiler mountings and safety valves are to be examined at each survey and opened as considered necessary
by the Surveyor.

1.5

Operation of the Safety Valves


The proper operation of the safety valves is to be confirmed at each survey.

1.7

Hydrostatic Pressure Testing


When considered necessary by the Surveyors, the boilers and superheaters are to be subjected to hydrostatic
pressure test.

164

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

PART

Section 10: Automatic and Remote-control Systems

CHAPTER

SECTION

10 Automatic and Remote-control Systems

Surveys After Construction

Annual Survey
At twelve month intervals from the date of installation, a survey is to be carried out during which a general
examination of the automatic and remote-control system is to be made. The examination is to be made with
a generator in operation and the control system energized to permit random checking of function indicators,
alarms and such control actuators as may be operational. The Surveyor is to examine the machinery records
to check the performance of the control system throughout the period since the last survey and to establish
if there has been any abnormal functioning or failures and what corrective measures had been taken to
preclude their recurrence. The machinery-space fire-detecting and bilge water-level alarms are to be checked
for performance.

Special Periodical Surveys


Special periodical surveys are to be carried out at intervals of five years from the date of installation and
are to include compliance with all requirements for Annual Surveys and with those that follow.

3.1

Control Actuators
All mechanical, hydraulic, and pneumatic control actuators and their power systems are to be examined
and tested as considered necessary.

3.3

Electrical
The insulation resistance of the windings of electrical control motors or actuators is to be measured, with
all circuits of different voltages above ground being tested separately, and is to be on the order of one-half
to one megohm.

3.5

Unattended Plants
Control systems for unattended machinery spaces are to be subjected to dock trials at reduced power on the
propulsion engine to check the proper performance of all automatic functions, alarms, and safety systems.

Repairs or Alterations
Major repairs or alterations to the automatic and remote-control systems are to be made, in accordance
with approved plans, under the supervision and to the satisfaction of the Surveyor.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

165

PART

Section 11: Crew Habitability

CHAPTER

SECTION

11 Crew Habitability (2016)

Surveys After Construction

Annual Surveys
The following information is to be reviewed by the attending ABS Surveyor for issues that could affect the
MODU Habitability notation (HAB(MODU), HAB+(MODU), or HAB++(MODU)).
i)

Maintenance and Operations logs since the previous Initial, Annual or Special Periodical Survey,
if any

ii)

Fire, repair and damage reports since the previous Initial, Annual or Special Periodical Survey, if
any

iii)

A list of all structural or mechanical modifications to the drilling unit since the previous Initial,
Annual or Special Periodical Survey, if any

iv)

Verification that equipment and facilities continue to be fit for purpose and are operating in accordance
with the criteria stated within the ABS Guide for Crew Habitability on Mobile Offshore Drilling
Units (referred to as the Guide hereinafter)

During the attending ABS Surveyors review of the submitted information, a determination will be made
as to whether changes or alterations have taken place that could affect the MODU Habitability notation. As a
result, the drilling unit may be subject to the review, ambient environmental testing, and inspection requirements
of the Guide.

Special Periodic Surveys

3.1

Survey Requirements
The Survey is to be comprised of ABS Engineering reviews, ABS Surveyor accommodation verifications,
and witnessing of ambient environmental testing. The Survey will cover all applicable habitability aspects.
The following is to be submitted to ABS three (3) months prior to carrying out the ambient environmental
testing:

166

i)

Fire, repair or damage reports since previous Annual Survey, if any

ii)

A list of all structural or mechanical modifications to the drilling unit since previous Annual Survey,
if any

iii)

Drawings/arrangements of personnel spaces, HVAC, electrical, etc., affected by alterations, if any

iv)

Copies of the approved Initial Test Plans and Test Reports

v)

Copies of Test Plans and Test Reports resulting from Annual Surveys, if any

vi)

Previous Special Periodical Survey Test Plans and Reports

vii)

Proposed Special Periodical Survey Test Plans for the current survey.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
Chapter
Section

7 Surveys
2 Surveys After Construction
11 Crew Habitability

7-21

The Special Periodical Survey data submittal serves three purposes. The first is to perform an ABS Engineering
review of personnel spaces against any alterations to the drilling unit related to the criteria in Appendix 3
of the Guide since the Initial Survey, with measurements verified by an ABS Surveyor. The second purpose
is to provide a history of ambient environmental testing, as well as the Special Periodical Survey ambient
environmental Test Plans for review and approval by ABS Engineering. The third is to allow scheduling of
measurement verifications and ambient environmental testing by ABS Surveyor.
A Special Periodical Survey Test Plan for each ambient environmental aspect of Habitability is to be
submitted in accordance with the criteria stated below. The approved Initial Test Plans should be used as a
basis for creating the Special Periodical Survey Test Plans.
For creation of the Special Periodical Survey Test Plans, Subsection 6, Test Plan, and Subsection 7, Test
Requirements, of Section 3 through 6 of the Guide specify the requirements for each ambient environmental
aspect (i.e., 3/6, 3/7, 4/6, 4/7, etc.). For specifying measurement locations for the Special Periodical Survey
Test Plans, the following changes to 7.4.1, Selection of Spaces where Measurements are to be Conducted,
of each ambient environmental aspect of Habitability is to be followed:
i)

Measurements are to be taken in all areas affected by alterations, if any. Measurements are limited to
the ambient environmental aspect affected by the alteration. For example, structural changes require
both whole-body vibration and noise measurements. Structural changes do not necessarily require
indoor climate or lighting measurements. Changes to luminaires require lighting measurements but
not whole-body vibration, noise, or indoor climate measurements.

ii)

For all ambient environmental aspects, measurements are to be taken in all worst case or problem
area locations based on the requirements set forth in 7.4.1, Selection of Spaces where Measurements
are to be Conducted, of the appropriate Section of the Guide. [For example, worst case for wholebody vibration is described in 3/7.4.1i)].

iii)

For all ambient environmental aspects, measurements are to be taken in twenty-five (25) percent
of personnel cabins identified in the initial Test Plans. Any worst case locations can be considered
part of the representative sample for personnel cabins, if applicable.

iv)

For all ambient environmental aspects, measurements are to be taken where a single instance of one
(1) type of a manned space exists within the drilling unit (e.g., bridge, radio room, officers mess,
gymnasium, library, etc.). The worst case locations can be considered part of the single instance
representative sample, if applicable.

v)

Where multiple instances of the same type space exist, a representative sample of at least twenty-five
(25) percent of each type is to be selected for measurement for all ambient environmental aspects.
The worst case locations are to be considered part of the representative sample, if applicable.

For all ambient environmental conditions, visual/walk-through inspections are to be conducted in


accordance with 7.4.2 of the appropriate Section of the Guide.

Requirements for Vessel Alterations


No alterations which affect or may affect the MODU Habitability notation awarded (HAB(MODU),
HAB+(MODU), or HAB++(MODU)), including alterations to the structure, machinery, electrical systems,
piping, furnishings or lighting systems, are to be made to the drilling unit unless plans of the proposed
alterations are submitted to and approved by ABS before the work of alteration is commenced. If ABS
determines that the alteration will affect the MODU Habitability notation, the altered drilling unit may be
subject to the review, verification, and ambient environmental testing requirements of the Guide.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

167

PART

Appendix 1: Lay-up and Reactivation of Laid-up Mobile Offshore Drilling Units

CHAPTER

Surveys After Construction

APPENDIX

Lay-up and Reactivation of Laid-up Mobile


Offshore Drilling Units (1 July 2016)

Lay-up of Mobile Offshore Drilling Units


Upon the owners written notification to ABS of a units lay-up, the units life cycle status and the Record
will be updated to reflect the change in status. Surveys due during lay-up will be held in abeyance until the
unit reactivates, at which time the surveys are to be brought up to date.

1.1

Optional Verification of Lay-up


At the Owners request, ABS will review, survey, and confirm the actions taken to preserve and protect a
unit while in lay-up. The ABS Guide for Lay-up and Reactivation of Mobile Offshore Drilling Units contains
detailed guidance for Lay-up Procedures, along with the requirements for Initial Verification Surveys and
Annual Surveys.

Reactivation of Mobile Offshore Drilling Units


For units returning to service from lay-up, regardless of whether ABS has been informed that the unit has
been in lay-up or whether lay-up preparations have been reviewed by ABS, a Reactivation Survey is required.
The ABS Divisional Offshore Survey Department is to be contacted for details of the requirements.
The Reactivation Survey requirements for the unit are subject to special considerations based on the survey
status at the time of the commencement of lay-up, the length of the lay-up period, and the conditions under
which the unit has been maintained during that period. Additional information relating to Reactivation
Surveys can be found in the ABS Guide for Lay-up and Reactivation of Mobile Offshore Drilling Units.

168

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

PART

Appendix 2: Survey of Portable Modules

CHAPTER

Surveys After Construction

APPENDIX

Survey of Portable Modules (2016)

General
Where a portable module is installed onboard a drilling unit, it is to be subjected to survey in presence of
and to the satisfaction of the attending Surveyor. See 6-1-2/11.

Survey of Portable Accommodation Modules


The Survey of portable accommodation modules is to be carried out in accordance with Section 5 of the
ABS Guide for Portable Accommodation Modules to verify satisfactory condition of the structure, piping,
electrical, fire-fighting and life-saving equipment.

Survey of Portable Industrial Modules


Survey of portable industrial modules is to be carried out to verify satisfactory condition of the structure,
piping, and electrical equipment. The following are to be confirmed:
i)

The portable industrial module is free of any physical damage that may affect its strength and
effectiveness of its service.

ii)

Material used for flooring, ceiling, linings, etc. that is included in the interior of the portable industrial
module is in compliance with a similar standard as that applied to the main accommodation spaces
on the drilling unit.

iii)

The portable industrial module is secured onboard the deck by means of welding. Means of securing
other than welding may be accepted provided efficiency of tie downs are design reviewed by ABS.

iv)

Boundaries of the portable industrial module are constructed (and insulated where necessary) of
suitable material to withstand equal level of fire protection in the area where other service spaces
are installed. See Section 5-1-1.

v)

Access doors to and from the portable industrial module are of self-closing type, opening to the
outside, unobstructed by any means, without any hold-back device, and rated to withstand equal
level of fire protection of the module.

vi)

The portable industrial module is provided with suitable fire or smoke detection system.

vii)

The portable industrial module is provided with suitable number of general alarms bells. If the
external alarms of the general alarm and public address system are audible from inside the portable
industrial module during normal operation of the unit, installation of an internal system may be
waived.

viii)

The portable industrial module is to be maintained at overpressure relative to external areas. Ventilation
inlet(s) and outlet(s) are located in non-hazardous areas.

ix)

Piping of the portable industrial module is connected to the drilling units piping system(s), and
cross-connections do not affect the safety of the drilling unit. Under no circumstances, are drain
pipes of modules to be connected to any hazardous drain of the drill unit.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

169

Part
7
Chapter 2
Appendix 2

Surveys
Surveys After Construction
Survey of Portable Modules

7-2-A2

x)

The portable industrial module is located to provide easy and protected access to all escape routes
that lead to designated embarkation stations. The term easy and protected will be interpreted as
routes that provide protection from falling objects; heat from well fire; a walk path without any
structural, mechanical or electrical obstruction; and efficiently illuminated with main and emergency
power system.

xi)

All connections and/or penetrations on the portable industrial module for unit supplied piping and/or
electrical systems maintain the original integrity of the portable industrial module, and these
connections and/or penetrations are in compliance with a recognized standard.

xii)

Where the portable industrial module is located on the open deck of a surface unit and may be
subjected to wave impact loading, efficiency of the quarter is design reviewed by ABS.

xiii)

Where the portable industrial module is adjacent to hazardous areas and contains accommodation
spaces (such as an office), service spaces, or control stations an engineering evaluation of the fire
protection and blast resistance is to be carried out.

Certification of Drilling Unit Fitted with Portable Industrial Modules


The drilling units life-saving plan is to be amended to indicate installation and location of additional
portable industrial modules. The attending Surveyor is to endorse the onboard life-saving plan to indicate
ABS verification.

170

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

PART

Appendix 3: Modification of a Self-Elevating Drilling Unit to Become Site-Specific Fixed Offshore Installation

CHAPTER

Surveys After Construction

APPENDIX

Modification of a Self-Elevating Drilling Unit to


Become Site-Specific Fixed Offshore Installation
(2012)

General
An existing self-elevating drilling unit (SEDU) may be modified to become a site-specific fixed offshore
unit and used for purposes of oil/gas production, storage or both. Depending upon the requested classification,
the modified unit may need to comply with one or more of the Rules/Guides listed under 7-2-A3/3.
Before ABS commences any work associated with the modification, the owner is to submit a signed
request for class for ABSs review and signing of the service agreement.

Application
One or more of the following Rules/Guides may be applicable to the modification:

3.1

Rules for Building and Classing Offshore Installations (Offshore Installation Rules)
This Rule is applied if the unit is modified to become a site-specific fixed offshore unit, without its hull
jacking system, marine systems, safety systems and any of the production/process and/or storage system
classed by ABS. Only the main hull structure is considered within ABS scope of service.

3.3

Rules for Building and Classing Mobile Offshore Drilling Units (MODU Rules)
This Rule is applied if the unit is modified to become a site-specific mobile offshore unit, without its
marine systems, safety systems and any of the production/process and/or storage system classed by ABS.
Only the main hull structure and its jacking system is considered within ABS scope of service.

3.5

Rules for Building and Classing Floating Production Installations (FPI Rules)
This Rule is applied if the units topside production/process system is also requested to be classed by ABS.
The safety systems, particularly suitability of electrical equipment in hazardous areas, fixed and portable
fire extinguishing systems, fire and gas detection systems, and fire protection system is to be in compliance
with this Rule.

3.7

Rules for Building and Classing Facilities on Offshore Installations (Facilities Rules)
This Rule is applied if the units topside production/process system is also requested to be classed by ABS.
The production/process systems are to be in compliance with this Rule.

3.9

Guide for Building and Classing Floating Offshore Liquefied Gas Terminals (FLGT
Guide)
This Guide is applied if the unit is modified to become a site-specific offshore LNG terminal.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

171

Part
7
Chapter 2
Appendix 3

Surveys
Surveys After Construction
Modification of a Self-Elevating Drilling Unit to Become Site-Specific Fixed Offshore
Installation

7-2-A3

Modification Survey
Modification survey is to be carried out as instructed by ABS and in accordance with ABS approved drawings.
In general, following applicable surveys are to be completed during the modification:

5.1

Hull
The SEDU is to be placed in a dry-dock (UWILD is not allowed) to carry out following hull surveys:
i)

Annual Survey Hull. Annual Survey Hull is to be carried out in accordance with 7-2-4/1 of
these Rules.

ii)

Drydocking Survey. Units hull is to be subjected to visual examination and NDT, as applicable
and in accordance with Section 7-2-6 of these Rules. Non-hull items associated with Annual Hull
Survey are not required.

iii)

Special Periodical Survey Hull. Units hull is to be subjected to visual examination, close-up
survey, extensive NDT, and gauging, as applicable and in accordance with Section 7-2-5 of these
Rules. Non-hull items associated with Special Periodical Survey are not required.

5.3

Jacking System
Where the unit is modified to become a fixed installation, and if none of its non-structural items are to be
classed, and if the jacking system is only to be used once during the initial jacking of the unit on site,
jacking system survey may be excluded from ABSs scope of classification work. Condition of the jacking
system, its capability of jacking and satisfactory operation will not be the responsibility of ABS.

5.5

Marine and Safety Systems


Where the unit is modified to become a fixed installation, and if its marine and safety systems serving the
entire installation are requested to be classed by the Owner, ABSs scope of classification work is to include
the marine and safety systems and compliance with applicable ABS Rules and/or Guides, as referenced in
7-2-A3/3, is required.
A special note will be entered into ABS Record regarding the extent of services and the required Survey
After Construction.

5.7

Topside Systems
Where the unit is modified to become a fixed installation, and if its topside systems serving the entire
installation are requested to be classed by the Owner, ABSs scope of classification work is to include the
requested topside systems and compliance with applicable ABS Rules and/or Guides, as referenced in
Subsection 7-2-A3/3, is required.
Where topside systems are classed, compliance with 7-2-A3/5.5 is a prerequisite.
Recommended class designation will be in accordance with either the ABS Rules for Building and
Classing Offshore Installations (Offshore Installation Rules) or the ABS Guide for Building and Classing
Floating Offshore Liquefied Gas Terminals (FLGT Guide), as applicable.
A special note will be entered into ABS Record regarding the extent of services and the required Survey
After Construction.

172

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Appendix 4: Preventative Maintenance Program (PMP)

PART

CHAPTER

Surveys After Construction

APPENDIX

Preventative Maintenance Program (PMP) (2016)

General
The intent of the ABS Preventative Maintenance Program (PMP) is for Owners to maintain their drilling
units with updated machinery maintenance practices, which may increase a units reliability and/or operational
availability, hence possible reduction in operational down-time. Properly executed PMP may also show
that major overhaul or replacement cycles machinery can be greater than five years, provided this is proven
by design criteria and satisfactory maintenance without premature failure.
Where specifically requested by the Owner, any machinery item that has rotating or mobile components
and is subjected to surveys after construction for maintenance of ABS classification of a unit, and its
working condition can be periodically monitored by suitable means and properly recorded may be enrolled
into ABS PMP.
Machinery components/items that have static components (not rotating or mobile components) and are
usually subjected to visual examination and/or testing by suitable means, and not covered under a
maintenance system, will be outside the scope of ABS PMP. Such machinery items will be subjected to
surveys after construction in accordance with applicable requirements of the MODU Rules.
While ABS PMP may be applied to machinery items that are within the scope of classification, operational
testing of all machinery items in accordance with applicable rules, is to be carried out during periodic class
surveys in presence of and to the satisfaction of the attending Surveyor.
Requirements of ABS PMP may not be applicable to machinery that is outside the scope of classification,
where specific periodic inspection and testing of such machinery is required to be carried out by ABS on
behalf of the drilling unit's flag State Administration.
Few explanatory examples are noted below:

ABS PMP will not be applicable to rule required visual examination and testing of static machinery
items/parts such as piping, valves, pressure vessels of any kind, electrical cables, etc.

Scope of ABS PMP will not be extended to the structural foundation/supports of the machinery that is
enrolled into ABS PMP.

A fire pump may be enrolled into ABS PMP, however annual operational/capacity testing of the
pump, as part of the fixed fire extinguishing system, is to be carried out in presence of ABS no matter
what the pump's maintenance records indicate.

Machinery items of an oily water separating system cannot be enrolled into ABS PMP since these
items are outside the scope of classification and subjected to MARPOL requirements.

Machinery items of any life-saving appliances (such as winches for lifeboats) cannot be enrolled into
ABS PMP since these items are outside the scope of classification and subjected to SOLAS and IMO
MODU Code requirements.

Rotating machinery items of lifting appliances (such as deck cranes) may be enrolled into ABS PMP
only if the lifting appliance is classed with the CRC notation.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

173

Part
7
Chapter 2
Appendix 4

Surveys
Surveys After Construction
Preventative Maintenance Program (PMP)

7-2-A4

Maintenance of machinery in accordance with ABS agreed PMP, can be based either on a Preventative
Maintenance (PM) plan or Condition Monitoring (CM) plan, or any combination thereof. A PM or CM
plans can also be developed based upon Reliability Centered Maintenance (RCM) process.
See 7-2-A4/Figure 1, which shows a typical configuration of machinery items enrolled into PMP while
remaining machinery are either not enrolled into PMP or to be surveyed without any maintenance program
and in accordance with applicable ABS rules.
Example:

Not all machinery on the drilling unit named WXYZ is classed per the applicable ABS Rules/Guides. The
owner decided to enroll some of the machinery items into PMP using PM and CM plans. PM for certain machinery
items were developed using RCM process. CM for certain machinery were also developed using RCM process.
The remaining classed machinery items will be surveyed either under SPS or CMS. The drilling unit will be
classed with the PMP notation and will also have an additional RCM notation for applicable systems.

FIGURE 1
Machinery Enrolled into PMP (2016)

While some of the machinery items may be surveyed under a PMP, maintenance of remaining machinery
items can continue to be surveyed either under ABS Special Periodical Survey (SPS) or Special Continuous
Survey, as selected by the Owner.
Note:

Special Continuous Survey of machinery is also referred as Continuous Machinery Survey (CMS). Where more
than half of the total numbers of machinery items are enrolled into PMP, ABS recommends remaining other
machinery to be surveyed under CMS.

A unit of any age may be eligible to enroll into PMP. An existing unit applying for entrance into the
program will be subject to ABSs review of the units records to ascertain the historical performance of the
machinery to be enrolled into maintenance plans under PMP, and provided there is no historical problem
related to the maintenance of the machinery, request for enrollment will be considered eligible.
PMP does not supersede the judgment of an ABS Surveyor, or waives attendance of ABS Surveyor(s) for
damage, or where attendance is required by the MODU Rules, as explained in subsequent sections of this
Appendix.
The reference to an ABS recognized condition monitoring company refers to those companies whom ABS
has identified as an external Recognized Specialist.
Note:

174

ABSs website http://www.eagle.org/ contains listing of ABS approved condition monitoring firms, which is
located under the Resources / Equipment & Supplier Listings / Recognized Specialists menu.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
7
Chapter 2
Appendix 4

1.1

Surveys
Surveys After Construction
Preventative Maintenance Program (PMP)

7-2-A4

Definitions
Machinery The term machinery used throughout this Appendix means any mechanical or electrical
equipment and/or machinery item that is part of a non-structural system. All machinery items required to
be surveyed to maintain classification of a drilling unit will be listed in ABS Survey Manager of each unit.
Note:

ABS Survey Manager Survey Status shows machinery items under the Parts List.

Preventative Maintenance Program (PMP) A program that consists of Planned Maintenance and/or
Condition Monitoring plans. PMP is only applicable to machinery that has moving/rotating parts and not to
static machinery parts such as electrical cables, piping, pressure vessels, switchboards, etc. Static machinery
parts that are not normally subjected to any preventative maintenance will be subjected periodic inspection,
as required by the MODU Rules, in presence of and to satisfaction of the attending Surveyor. PMP of a
machinery may or may not be supported by an ABS approved Reliability Centered Maintenance process.
Planned Maintenance (PM) A PMP with a maintenance plan that uses time-based inspection, part
replacement and/or overhauls in an effort to prevent machinery failures. Timing can be based on calendar
days, cycles counter or equipment running hours. Such schedules are generally established by the machinery
manufacturer or the owner, and normally include lubrication servicing; filter, bearing and seal replacements;
as well as major overhaul.
Condition Monitoring (CM) A PMP with a maintenance plan that uses various technologies to determine
the condition of equipment, at a specific moment in time, using minimal or non-invasive means. Common
tools used in condition monitoring are vibration analysis, oil analysis, ferrography, thermography, electric
current wave form analysis and boroscopic examination. Supplemental technologies, such as demodulation,
ultrasonic analysis, shock-pulse, spike-energy, HFD, etc., for CM of roller bearing element, may be used in
addition to vibration analysis. An advanced means of CM is Condition-based Maintenance (CbM), which
is defined below.
Condition-based Maintenance (CbM) This is a CM plan. However, CbM is conducted on a frequent or
real-time basis, to determine when part replacement or other corrective action is required. This process
involves establishing a baseline and operating parameters, then frequently monitoring the machine and
comparing any changes in operating conditions to the baseline. Repairs or replacement of parts are carried
out before the machinery fails based upon the use of the tools prescribed for CM.
Reliability Centered Maintenance (RCM) See 7-2-A5/1.1.

1.3

1.5

PMP Additional Notation


The PMP additional notation added to the Record indicates compliance with the ABS Preventative
Maintenance Program (PMP) on one or more pieces of classed machinery onboard the unit.
1.3.1

PMP Surveys
All machinery items covered by either a PM and/or CM plan will be surveyed in accordance with
the MODU Rules during Annual Surveys and Special Periodical or Special Continuous Surveys,
and requirements of this Appendix. Machinery not covered by PMP are to be surveyed in accordance
with Annual Survey and Special Periodical Survey requirements contained in previous sections of
Part 7, Chapter 2 of these Rules.

1.3.2

PMP Indicators
An individual classed machinery item listed in Survey Status of a unit that has enrolled into ABS
PMP will have PM, CM, or CbM indicator, as applicable.

Cancellation of PMP
The survey arrangement for equipment or machinery under the PMP may be cancelled by ABS if the program is
not being satisfactorily carried out, as a result of insufficient maintenance records, lack of knowledge by
the crew of the units program, the general condition of the equipment or machinery, or agreed intervals
between overhauls are exceeded resulting in the annual survey not being completed within the survey
window as required.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

175

Part
7
Chapter 2
Appendix 4

Surveys
Surveys After Construction
Preventative Maintenance Program (PMP)

7-2-A4

Sale, change of unit management, change of Recognized Specialists, or transfer of class is to be cause for
reconsideration of the approval. If more than one occurs, the current plan will be cancelled and a new plan
will be required for ABS approval.
The Owner may cancel the survey arrangement for equipment or machinery under the PMP by informing
ABS in writing. For this case, items which have been inspected under the program since the last Annual
Survey may be credited for class at the discretion of the Surveyor.

PMP Compliance Criteria


For a PMP to be accepted, the following conditions are to be complied with.

3.1

Surveys
Surveys related to the unit are to be up-to-date, without outstanding recommendations which would affect
the implementation of PMP. Where an outstanding recommendation exists, after satisfactory repairs have
been performed on the equipment or machinery, ABS attendance is required as part of the implementation
survey of PMP.
A unit with its equipment or machinery enrolled in the PMP can either be on a Special Periodical Survey
or Special Continuous Survey cycle. However, where majority (50% or more) of moving/rotating machinery
items are enrolled into PMP, all other remaining machinery is recommended to be surveyed under CMS.
Example:

3.3

Dynamic positioning thrusters of a Column Stabilized Drilling Unit (CSDU) can be enrolled into CM while the
units remaining machinery is on Special Periodical Survey.

Maintenance and ABS Survey Intervals


Maintenance is to be carried out on the basis of intervals between overhauls recommended by the manufacturer
of equipment or machinery, documented owners experience and/or a condition monitoring system, where
applied.
In general, survey intervals for the PMP are not to exceed those specified for Special Periodical Survey.
However, for components where the maintenance is based on running hours or number of cycles, longer
intervals may be accepted as long as the intervals are based on the manufacturers or owners recommendations.
In addition, if an approved PMP is in effect, the opening of individual items of equipment or machinery
may not be required during the regular five-year cycle, based on satisfactory results recorded within the
applied PMP.
Note:

For example, while ABS carries out PMP Annual Confirmation Survey and issues a class certificate valid for five
years, equipment or machinery enrolled into PMP may not require intrusive surveys every five years and follow
the frequency recommended in the maintenance program, which could be shorter or longer than five years.

3.5

Computerized Maintenance Management Systems


The activities of the PMP are to be programmed into the Computerized Maintenance Management System
(CMMS) and the history of all maintenance tasks are to be recorded and stored in the CMMS by the units
Owner. These systems must include back-up devices, such as removable hard drives, thumb drives, CD-ROMs
or remote on-line back-up systems and are updated at regular intervals. Details of the system are to be
reviewed by the attending Surveyor during the implementation survey and during Annual Confirmation
Surveys.

Program Description
For general requirements, implementation, and other aspects of Planned Maintenance (PM) and Condition
Monitoring (CM) plans, refer to 7-2-A4/5.1 through 7-2-A4/5.7 below.

5.1

General
5.1.1

176

Enrollment into PM
To enroll equipment or machinery into PM, a comprehensive plan is to be submitted to the
attending Surveyor for review prior to conducting an implementation survey onboard the unit.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
7
Chapter 2
Appendix 4

5.1.2

5.3

5.5

5.7

Surveys
Surveys After Construction
Preventative Maintenance Program (PMP)

7-2-A4

Enrollment into CM
To enroll equipment or machinery into CM, the required documentation is to be submitted to the
responsible ABS Engineering for review, preferably prior to conducting an implementation survey
onboard the unit. The implementation survey can only be credited upon satisfactory completion of
review by ABS Engineering.

Implementation Surveys
Once the implementation survey is satisfactorily completed, a survey report confirming the implementation
of the PM and/or CM plan(s) will be issued by the attending ABS Surveyor, and the plan(s) may be put
into service.
5.3.1

Implementation of PM
The requirements for the implementation survey are provided in 7-2-A4/9.3 of these Rules.

5.3.2

Implementation of CM
The requirements for the implementation survey are provided in 7-2-A4/11.3 of these Rules.

ABS Survey Status Indicators


The owner is to communicate with the attending Surveyor to ensure that the Survey Status for a unit shows
the correct indicators for all listed equipment or machinery.
5.5.1

Indicators for PM
When the implementation survey is satisfactorily completed, the attending Surveyor will inform
ABS regarding equipment or machinery items to be covered by a PM plan and to be shown by a
PM indicator in Survey Status.

5.5.2

Indicators for CM
When the implementation survey is satisfactorily completed, the attending Surveyor will inform
ABS regarding equipment or machinery items to be covered by a CM plan and to be shown by a
CM indicator in Survey Status.

Maintenance of Onboard Documentation


The Offshore Installation Manager (OIM) or the Chief Engineer shall be ultimately responsible for maintenance
of onboard documents and records associated with PMP. If a computerized system is used for updating the
maintenance documentation and maintenance program, access is to be permitted only by the OIM, Chief
Engineer or other authorized person(s).
Additional requirements for onboard documentation are provided in 7-2-A4/9.7 (for PM plans) or 7-2-A4/11.7
(for CM plans).

Overhauls and Damage Repairs


After an overhaul or a damage repair to a machinery enrolled into PMP, following requirements are to be
complied with.

7.1

Overhauls
For machinery enrolled into a CM plan, following an overhaul, new baseline data is to be recorded in the
presence of an ABS recognized condition monitoring company as soon as possible. Recording of the new
baseline data is to be done either before the next Annual Confirmation Survey or within six months, whichever
date is sooner, and is to be included in the Annual Report. Documentation on overhauls of machinery items
covered by PMP is to be reported and signed by the OIM, Chief Engineer or other authorized person(s).

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

177

Part
7
Chapter 2
Appendix 4

7.3

Surveys
Surveys After Construction
Preventative Maintenance Program (PMP)

7-2-A4

Damage Repairs
Any damage to equipment or machinery enrolled into ABS PMP is to be reported to ABS. If damaged
equipment or machinery is replaced, the new equipment or machinery is to meet the requirements of the
rules applicable to the unit. Any replacement or repair carried out due to damage is to be recorded and
same verified by the attending Surveyor.
Records of all damages, replacement and/or repairs are to be readily available and verified by the attending
Surveyor during Annual Surveys, unless ABS requires verification at earliest.
When there is an overdue outstanding recommendations or a record of unrepaired damage that affects PMP,
relevant items are to be removed from the program until the recommendation is satisfactorily rectified or
the repair carried out to the satisfaction of the attending Surveyor.

Planned Maintenance (PM)


PM is to comply with subsequent paragraphs of subsection 7-2-A4/9.

9.1

Machinery Items not Allowed on PM


Owners may conduct PM on any item of machinery. However, following typical items, which are normally
listed under units Machinery Parts in the Survey Status, cannot be enrolled into an ABS PM plan.
9.1.1

9.1.2

Marine and Safety Systems (on all types of units)


i)
Operational testing of all marine and safety systems (including systems such as the ballast,
bilge, active fire extinguishing, fire and gas detection, general alarm, public address, fuel
oil transfer, power generation, propulsion, etc.)

ii)

Visual examination and/or testing of semi-portable and portable fire-extinguishing equipment,


and fire hoses.

iii)

Visual examination and/or testing of components associated with fixed gas smothering
system.

iv)

Visual examination and/or testing of breathing apparatus, firemans outfits and the
international shore connection.

v)

Visual examination and/or testing of arrangements for remote safety shutdown system.

vi)

Visual examination and/or testing of rigs Emergency Shut-Down (ESD) system.

vii)

Visual examination and/or testing of components associated with the general alarm and
public address systems.

viii)

Visual examination and/or testing of electrical machinery installed in hazardous areas,


together with verification of associated alarms and shutdowns.

ix)

Visual examination and/or testing of sea chests and ship-side valves.

Jacking System (on self-elevating units)


i)
Visual examination and/or testing of jacking system machinery.

ii)
9.1.3

Anchoring and Mooring Systems (on units with respective ABS symbols and notations)
i)
Operational testing of temporary anchoring system on units classed with .

ii)
9.1.4

Operational testing of mooring systems on units classed with or , or any other


assigned mooring notation (such as TAM).

Dynamic Positioning System (classed with any DPS- notation)


i)
Thrusters (fixed or retractable)

ii)

178

Operational testing of jacking systems.

Operational testing of dynamic positioning system, including FMEA trials.


ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
7
Chapter 2
Appendix 4

9.1.5

Surveys
Surveys After Construction
Preventative Maintenance Program (PMP)

7-2-A4

Drilling System
Refer to the ABS Guide for the Classification of Drilling Systems.

9.3

Implementation Survey for PM


Implementation survey for PM is to be carried out in accordance with 7-A-14/13.3 of the ABS Rules for
Survey After Construction (Part 7).

9.5

Administrative Requirements for PM


The contents of the submitted PM plan and the Owners annual PM report requirements are to be in
accordance with 7-A-14/13.5 of the ABS Rules for Survey After Construction (Part 7).

9.7

Onboard Documentation for PM


Documents required for PM are to be readily available onboard the unit and are listed in 7-A-14/13.7 of the
ABS Rules for Survey After Construction (Part 7).

11

Condition Monitoring (CM)


CM is to comply with subsequent paragraphs of subsection 7-2-A4/11.

11.1

Machinery Items not Allowed on CM


Owners may conduct CM on any item of machinery. However, following typical items, which are normally
listed under units Machinery Parts in the Survey Status, cannot be enrolled into an ABS CM plan.
11.1.1 Marine and Safety Systems (on all types of units)
i)
Operational testing of all marine and safety systems (including systems such as the ballast,
bilge, active fire extinguishing, fire and gas detection, general alarm, public address, fuel
oil transfer, power generation, propulsion, etc.)

ii)

Visual examination and/or testing of semi-portable and portable fire-extinguishing equipment,


and fire hoses.

iii)

Visual examination and/or testing of components associated with fixed gas smothering
system.

iv)

Visual examination and/or testing of breathing apparatus, firemans outfits and the
international shore connection.

v)

Visual examination and/or testing of arrangements for remote safety shutdown system.

vi)

Visual examination and/or testing of rigs Emergency Shut-Down (ESD) system.

vii)

Visual examination and/or testing of components associated with the general alarm and
public address systems.

viii)

Visual examination and/or testing of electrical machinery installed in hazardous areas,


together with verification of associated alarms and shutdowns.

ix)

Visual examination and/or testing of sea chests and ship-side valves.

11.1.2 Jacking System (on self-elevating units)


Operational testing of jacking systems.
11.1.3 Anchoring and Mooring Systems (on units with respective ABS symbols and notations)
i)
Operational testing of temporary anchoring system on units classed with .

ii)

Operational testing of mooring systems on units classed with or , or any other


assigned mooring notation (such as TAM).

11.1.4 Dynamic Positioning System (classed with any DPS- notation)


Operational testing of dynamic positioning system, including FMEA trials.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

179

Part
7
Chapter 2
Appendix 4

Surveys
Surveys After Construction
Preventative Maintenance Program (PMP)

7-2-A4

11.1.5 Drilling System


Refer to the ABS Guide for the Classification of Drilling Systems.

11.3

Implementation Survey for CM


Implementation survey for PM is to be carried out in accordance with 7-A-14/15.3 of the ABS Rules for
Survey After Construction (Part 7).

11.5

Administrative Requirements for CM


The contents of the submitted PM plan and the Owners annual PM report requirements are to be in
accordance with 7-A-14/15.5 of the ABS Rules for Survey After Construction (Part 7).

11.7

Onboard Documentation for CM


Documents required for CM are to be readily available onboard the unit and are listed in 7-A-14/15.7 of
the ABS Rules for Survey After Construction (Part 7).

11.9

Alternative Techniques for CM


Application of techniques of CM other than those mentioned above will be specially considered.

13

PMP Surveys and Reports


The following requirements are to be followed on units having systems operating and surveyed under the
ABS Preventative Maintenance Program (PMP).

13.1

Annual Confirmation Surveys


On units enrolled in a PMP and to maintain the PMP notation, an Annual Confirmation Survey is to be
carried out by the attending Surveyor. This survey is to be carried out simultaneously with each Annual
Survey of Machinery. The purpose of this survey is to verify that the program is being correctly operated
and that the machinery has been functioning satisfactorily since the previous survey.
The survey is to at least include the following:

13.3

i)

A general examination of the machinery items enrolled into PMP is to be carried out.

ii)

The Surveyor is to review the owners annual report, and the required onboard documentation.

iii)

The performance and maintenance records are to be examined to verify that the machinery has
functioned satisfactorily since the previous survey or action has been taken in response to machinery
operating parameters which are outside acceptable tolerances and the overhaul intervals have been
maintained.

iv)

Written details of breakdowns or malfunctions of equipment are to be made available.

v)

The description of repairs carried out is to be reviewed. Any machinery part, which has been replaced
with a spare due to damage, is to be retained onboard, where possible, until examined by the attending
Surveyor.

vi)

At the discretion of the Surveyor, operational function tests, testing of safety devices and/or trips,
confirmatory surveys and random check readings, are to be carried out as far as practicable and
reasonable.

ABS Survey Report


Satisfactory completion of Annual Confirmation Survey of PMP will enable attending Surveyor to credit
the survey and acceptance of the ABS PMP for its continued use.
The Surveyor may credit to the current SPS or CMS cycle of any of the listed machinery item that were
overhauled and tested in the presence of and to the satisfaction of the attending Surveyor. Additionally, any
of the listed machinery item that have been overhauled in accordance with the ABS PMP schedule may be
credited to the SPS or CMS cycle by the attending Surveyor after a satisfactory operational test.

180

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
7
Chapter 2
Appendix 4

Surveys
Surveys After Construction
Preventative Maintenance Program (PMP)

7-2-A4

Any machinery that has acceptable operating conditions as per the approved CM plan may also be credited
to the current SPS or CMS cycle by the attending Surveyor after a satisfactory operational test.
13.3.1 Owners Annual Preventative Maintenance Report
At time of the Annual Confirmation Survey, the units qualified representative is to present to the
attending Surveyor, an Annual PMP report via hard copy or approved alternative electronic formats
containing the information detailed in 7-2-A4/9.5 (for PM plans), 7-2-A4/11.5 (for CM plans).

Owners report is to be reviewed by the attending Surveyor for completeness and reported
data/information. If the machinery included in the PMP has changed, this is to be stated in the
report.
Any machinery to be added to the program is subject to the requirements of 7-2-A4/9.5 (for PM
plans), 7-2-A4/11.5 (for CM plans) and approval by ABS.
While acceptance of additional machinery item(s) under PM plan can be done by the attending
Surveyor, acceptance of item(s) under CM plan is to be carried out by ABS Engineering and the
attending Surveyor.
Where machinery items are added to the PMP, ABS is to be advised and the units Survey Status
updated accordingly. When removing machinery from ABS PMP, ABS is to be advised and the
units Survey Status updated accordingly.
13.3.2 Alternative Electronic Formats
Owners may opt to submit their annual PMP reports in a portable electronic format (e.g., thumb
drive, CD-ROM, or e-mail attachment), for review prior to or at the time of attendance onboard.
Acceptable file types are those which are compatible with MS Word, MS Excel, and/or PDF.
These reports are to contain all the required information. In addition, the owners are required to
submit, annually, in hard copy, the following to the attending Surveyor:

i)

A letter stating that the annual report is on an alternative electronic format and meets the
requirements of ABS required format and file type.

ii)

A summation and results of the annual vibration signatures or oil analysis (for machinery
enrolled in a CM plan).

iii)

A summation and analysis of all unscheduled maintenance and breakdowns of the


machinery item(s) enrolled into PMP.

iv)

Directions on how to retrieve the report from the alternative electronic format.

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

181

PART

Appendix 5: Reliability Centered Maintenance (RCM)

CHAPTER

Surveys After Construction

APPENDIX

Reliability Centered Maintenance (RCM) (2016)

General
By using RCM principles, maintenance is evaluated and applied in a rational manner. Functional failures
with the highest risk are identified and then focused on. Machinery items and their failure modes that will
cause high-risk functional failures are identified for further analyses. Maintenance tasks and maintenance
strategies that will reduce risk to acceptable levels are determined. Spare parts inventories are determined
based on the maintenance tasks developed and a risk assessment. An RCM sustainment procedure is
instituted to continually monitor and optimize maintenance. Accordingly, improved machinery and system
reliability can be expected.
Note:

1.1

Additional information and explanations on how to develop a RCM program can be found in the ABS Guide for
Survey Based on Reliability Centered Maintenance (RCM Survey Guide), and the ABS Guidance Notes on
Reliability Centered Maintenance (RCM Guidance Notes).

Definitions
Machinery The term machinery used throughout this Appendix means any mechanical or electrical
equipment and/or machinery item that is part of a non-structural system. All machinery items required to
be surveyed to maintain classification of a drilling unit will be listed in ABS Survey Manager of each unit.
Note:

ABS Survey Manager Survey Status shows machinery items under the Parts List.

Reliability Centered Maintenance (RCM) RCM is not defined as a PMP. RCM is a process that is used to
determine the most effective approach to maintenance. It involves identifying actions that when taken will
reduce the probability of failure and which actions are most cost effective. ABS has developed a maintenance
program which uses RCM analysis of installed equipment to develop a PMP, a spare parts holdings list and
includes a sustainment plan. Two different RCM maintenance strategies, the reactive maintenance and
one-time change are explained below.
Reactive Maintenance A RCM maintenance strategy in which machinery is run until failure before
corrective action is taken. This is useful for items which are low-cost and have no impact on operational,
environmental or safety concerns as a result of failure.
One-Time Change A RCM maintenance strategy in which machinery or systems, that have been determined
to present an unacceptable level of risk and have no potential mitigations, are replaced or significantly
altered in order to provide an acceptable level of risk.

1.3

182

RCM Analysis
A RCM analysis as defined by the RCM Guidance Notes will generate additional types of maintenance
tasks which are not previously defined by the Preventative Maintenance Program. In order to simplify the
RCM program plan approval process, implementation survey and annual surveys, the following groupings
of these tasks will be used to determine the applicable requirements:

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

Part
7
Chapter 2
Appendix 5

Surveys
Surveys After Construction
Reliability Centered Maintenance (RCM)

7-2-A5

TABLE 1
RCM Tasks (2016)
PM Type Tasks

CM Type Tasks

PM

CM

Failure finding

Combination of PM and CM

Other applicable and effective tasks

RCM Additional Notations


Applicable RCM additional notation added to the Record indicates compliance with the ABS Reliability
Centered Program on one or more pieces of equipment or machinery that have been enrolled in a PMP.
Owner may select desired systems or equipment items for which a RCM analysis will be conducted and
will be used to develop a PMP.
The RCM process is to be approved by an ABS engineering office. Upon completion of a satisfactory
implementation survey, units class certificate will be issued with an additional RCM notation, as
appropriate, and this will be entered in the Record.
Where Owner elects to apply RCM to an operational subsystem of the rig, specific RCM notation will
indicate the scope of ABS approved RCM. Such typical RCM notations are, but not limited to, RCM
(AMS), RCM (CRC), RCM (DPS).
Note:

System specific RCM additional notations are recorded similar to how other class additional notations such as
CRC, etc., are recorded by ABS. However, they will not be part of the class designation indicated on the class
certificate of the vessel.

3.1

RCM for Propulsion System


On self-propelled units assigned with AMS notation, where an RCM analysis is carried out, and the resulting
RCM is applied to the propulsion system, including as applicable: prime mover(s), reduction gears, shafting,
propeller or other thrusting device, all auxiliary systems providing, cooling, control, electrical power,
exhaust, fuel, lubrication and equipment related to the steering or other directional control system, the
RCM Program will be assigned and distinguished in the Record with the class notation RCM (AMS).

3.3

RCM for Cranes


On units where deck cranes are classed with CRC notation, where an RCM analysis is carried out, and the
resulting RCM is applied to the cranes machinery, the RCM Program will be assigned and distinguished
in the Record with the class notation RCM (CRC).

3.5

RCM for Dynamic Positioning System


On dynamically positioned units assigned with DPS-1, DPS-2 or DPS-3 notations, where an RCM analysis
is carried out, and the resulting RCM is applied to the dynamic positioning system, including as applicable:
prime mover(s), reduction gears, shafting, thrusters, all auxiliary systems providing, cooling, control, electrical
power, exhaust, fuel, lubrication and equipment related to the dynamic positioning system, the RCM
Program will be assigned and distinguished in the Record with the class notation RCM (DPS).

3.7

RCM Indicators
An individual classed machinery item listed in Survey Status of a unit that has enrolled into ABS PMP and
used the RCM process for developing its PM or CM plan will also have an RCM indicator.

RCM Implementation Surveys


Implementation survey for RCM is to be carried out in accordance with 7-A-14/17.5 of the ABS Rules for
Survey After Construction (Part 7).

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

183

Part
7
Chapter 2
Appendix 5

Surveys
Surveys After Construction
Reliability Centered Maintenance (RCM)

7-2-A5

Administrative Requirements for RCM


The contents of the submitted RCM and the Owners annual RCM report requirements are to be in
accordance with 7-A-14/17.7 of the ABS Rules for Survey After Construction (Part 7).

Onboard Documentation for RCM


Documents required for RCM are to be readily available onboard the unit and are listed in 7-A-14/17.9 of
the ABS Rules for Survey After Construction (Part 7).

184

ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016

You might also like