MODU Part 7 E-July16
MODU Part 7 E-July16
MODU Part 7 E-July16
Updates
July 2016 consolidation includes:
January 2016 version plus Notice No. 1
a n
o t
i c
1 6
(1996)
(1995)
(1994)
(1993)
9 May 1996
15 May 1995
9 May 1994
11 May 1993
Title/Subject
Status/Remarks
7-1-4/41.5
7-1-7/13.1
7-1-7/Figure 4
7-1-9/9.1
7-2-1/1.1
7-2-1/17
7-2-1/17.5
(New)
7-2-1/19.9
(New)
7-2-3/1.1
To clarify that all UWILD plans must be agreed by the ACS and later
discussed during the pre-planning meeting with attending Surveyor.
7-2-3/1.5
7-2-4/3.5
(Deleted)
7-2-4/5
(New)
7-2-4/7
To clarify and separate requirements for units classed with APS and
PAS notations.
7-2-4/9
(New)
7-2-4/Table 1
(New)
7-2-4/Table 2
(New)
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
iii
Part/Para. No.
Title/Subject
Status/Remarks
7-2-4/Table 3
(New)
System Performance
7-2-4/Table 4
(New)
7-2-5/1.5
7-2-5/1.13
(New)
Alternatives
7-2-5/5.5.3
7-2-5/7.3.1
7-2-5/7.5.3
7-2-5/15
7-2-6/Table 1
7-2-6/3
To clarify that all UWILD plans must be agreed by the ACS and later
discussed during the pre-planning meeting with attending Surveyor.
7-2-6/3.11
Alternatives
7-2-11
(New)
Crew Habitability
7-2-A2
7-2-A4
(New)
7-2-A5
(New)
iv
Title/Subject
Lay-up and Reactivation of Laid-up
Mobile Offshore Drilling Units
Status/Remarks
To refer to the ABS Guide for Lay-up and Reactivation of Mobile
Offshore Drilling Units, which updates the requirements for lay-up
and reactivation with more descriptive life cycle states in regards to
layup on the survey status. (Incorporates Notice No. 1)
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
PART
Table of Contents
Surveys
CONTENTS
CHAPTER 1
CHAPTER 2
Appendix 1
Appendix 2
Appendix 3
Appendix 4
Appendix 5
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
PART
CHAPTER
CONTENTS
SECTION 1
General .................................................................................................. 11
1
General ............................................................................................. 11
3
Survey at Builders Yard ................................................................... 11
5
Certification and Classification .......................................................... 12
SECTION 2
5.1
5.3
4.1
4.3
4.5
Material ............................................................................................. 15
5.1
5.3
5.5
11
13
9.1
9.3
9.5
11.3
11.5
11.7
11.9
11.11
15
17
17.3
17.5
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
19
Weathertight Integrity..................................................................... 21
19.3
Watertight Integrity......................................................................... 21
19.5
Penetrations .................................................................................. 21
21
23
General .......................................................................................... 22
23.3
23.5
23.7
Structural Testing........................................................................... 22
23.9
23.11
23.13
25
27
SECTION 3
TABLE 1
TABLE 2
FIGURE 1
FIGURE 2
FIGURE 3
5.1
5.3
5.5
5.7
Foundation ..................................................................................... 26
7.3
7.5
7.7
Piping ................................................................................................26
9.1
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
11
13
15
17
19
11.3
11.5
11.7
11.9
11.11
11.13
11.15
Collision-Bulkhead Penetrations.................................................... 29
11.17
11.19
11.21
11.23
11.25
Instruments.................................................................................... 29
11.27
11.29
11.31
13.3
13.5
Valves ............................................................................................... 32
15.1
15.3
15.5
15.7
17.3
17.5
Flanges ............................................................................................. 33
19.1
21
23
25
21.3
Connections .................................................................................. 34
23.3
23.5
Connections .................................................................................. 35
25.3
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
27
29
SECTION 4
27.1
Connections ................................................................................... 36
27.3
27.5
29.3
11
13
3.1
Materials ........................................................................................ 37
3.3
3.5
3.7
5.3
5.5
5.7
5.9
Sounding ...........................................................................................38
7.1
7.3
9.3
9.5
9.7
9.9
11.3
13.3
13.5
13.7
15
17
19
17.1
17.3
17.5
17.7
Electrical Machinery....................................................................... 41
21
23
25
27
Application ..................................................................................... 42
21.3
21.5
General.......................................................................................... 42
23.3
Starting-air Systems.......................................................................... 42
25.1
25.3
General.......................................................................................... 43
27.3
29
31
33
35
37
39
41
41.3
41.5
41.7
41.9
TABLE 1
SECTION 5
Definitions...................................................................................... 47
5.3
5.5
5.7
5.9
5.11
5.13
5.15
5.17
5.19
5.21
5.23
5.25
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
5.27
5.29
5.31
5.33
Materials ........................................................................................ 53
7.3
7.5
7.7
7.9
7.11
7.13
7.15
Generators ..................................................................................... 54
7.17
7.19
Accumulator Batteries.................................................................... 54
7.21
Switchboards ................................................................................. 56
7.23
7.25
7.27
7.29
7.31
7.33
7.35
7.37
7.39
Earthing .............................................................................................58
9.1
General .......................................................................................... 58
9.3
9.5
Connections ................................................................................... 58
9.7
9.9
TABLE 1
SECTION 6
3.1
3.3
3.5
5.3
5.5
5.7
5.9
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
5.11
5.13
5.15
7.3
7.5
7.7
7.9
Harmonics ..................................................................................... 65
11
13
15
17
19
21
11.1
11.3
11.5
11.7
13.3
13.5
15.3
17.3
17.5
17.7
19.3
21.3
Generators .................................................................................... 70
21.5
21.7
21.9
21.11
21.13
21.15
21.17
21.19
21.21
21.23
21.25
21.27
21.29
TABLE 1
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
SECTION 7
SECTION 8
Openings ....................................................................................... 72
3.3
Penetrations .................................................................................. 73
5.3
5.5
5.7
5.9
Ventilation ...................................................................................... 76
General .......................................................................................... 77
9.3
9.5
11
13
13.3
13.5
FIGURE 1
FIGURE 2
FIGURE 3
FIGURE 4
Definitions ...................................................................................... 72
5.1
5.3
7.3
7.5
7.7
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
11
13
9.3
9.5
9.7
9.9
11.3
15
17
19
Outfitting ............................................................................................ 88
17.1
17.3
17.5
17.7
17.9
17.11
17.13
SECTION 9
11
9.1
9.3
11.3
11.5
11.7
11.9
Communication Facilities............................................................... 92
11.11
11.13
11.15
11.17
11.19
11.21
11.23
11.25
11.27
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
13
15
17
13.3
13.5
13.7
13.9
13.11
15.3
17.3
DP Trials ........................................................................................ 97
1.3
1.5
5.3
5.5
3.3
10
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
PART
Section 1: General
CHAPTER
SECTION
General
General
This Chapter pertains to surveys and testing to be carried out during construction of a mobile offshore
drilling unit at the builders yard/facility. The requirements for design review are given in Parts 3, 4, and 5
of these Rules.
The requirements for specific surveys are included in subsequent Sections of this Chapter. Subsequent Sections
are titled as follows:
Section 2
Section 3
Section 4
Section 5
Section 6
Section 7
Section 8
Section 9
Subsection 1 titled General of every Section provides a brief explanation regarding purpose of that
Section.
All Rule contents covered by subsequent Sections of this Chapter and that require visual examination,
verification, testing, etc. are to be carried out in presence of and to the satisfaction of the attending Surveyor.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
11
Part
Chapter
Section
7
1
1
Surveys
Surveys During Construction
General
7-1-1
5.1
5.3
12
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
PART
CHAPTER
SECTION
General
This Section pertains to surveys and testing to be carried out on hull structure and hull outfitting items
during construction of a mobile offshore drilling unit at builders yard/facility. The requirements for design
review are given Parts 3, 4, and 5 of these Rules.
For typical surveys required to be carried out, see subsequent Subsections of Section 7-1-2. All surveys
and testing is to be carried out in presence of and to the satisfaction of the attending Surveyor, prior to the
sea trial. Testing of the onboard computer (7-1-2/21), and hull structure testing such as hydrostatic testing
(7-1-2/23.5) and hull structural testing (7-1-2/23.7) of tanks may be carried out during the sea trial as
referenced in Section 7-1-9 of these Rules.
ii)
iii)
iv)
Preparation for welding including; forming, edge preparation, fit-up, alignment, cleanliness, and
tack welds
v)
vi)
vii)
viii)
Compartment testing
Where structure is assembled in blocks or modules, the Surveyor is to inspect the fit-up, piping and electrical
connections, and to witness the required tests on the completed assembly in guidance with the QCP, and in
accordance with the approved plans and Rule/Guide requirements. The progress and suitability of structural
fit-up and joining of constructed/fabricated blocks/modules are to be to the satisfaction of the attending
Surveyor. All erection joints of hull structure are to be visually examined, proven tight, and the extent of
Nondestructive Testing (NDT) carried out is to be to the satisfaction of the attending Surveyor. For further
details of Surveyor attendance, see 7-1-2/5 through 7-1-2/27.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
13
Part
Chapter
Section
7
1
2
Surveys
Surveys During Construction
Surveys at Builders Yard Hull Structure and Outfitting
7-1-2
4.1
4.3
4.5
14
Determination of CSA
A CSA can be determined in a number of ways, including but not limited to:
i)
The results of engineering strength and fatigue analyses, such as specified in the Drillship Guide,
Finite Element Analysis or a Dynamic Loading Approach analysis, particularly for areas approaching
the allowable criteria.
ii)
iii)
Details where fabrication is difficult, such as blind alignment, complexity of structural details and
shape, limited access, etc.
iv)
Input from owners, designers and/or shipyards based on previous in-service experience from
similar vessels, such as corrosion, wear and tear, etc.
Structural drawings indicating the location of critical structural areas as identified by the ABS review
ii)
iii)
Verification and recording procedures at each stage of construction, including any proposed additional
NDT other than what is that required by 7-1-2/11
iv)
Part
Chapter
Section
7
1
2
Surveys
Surveys During Construction
Surveys at Builders Yard Hull Structure and Outfitting
7-1-2
Material
5.1
Material Traceability
The builder is to maintain a system of material traceability to the satisfaction of the attending Surveyor.
Data as to place of origin and results of tests for materials shall be retained and are to be readily available
to the attending Surveyor upon request.
5.3
Material Selection
When selecting material grades for the classification of drilling units, minimum expected service temperature
and structural element category is considered. Various parts of drilling units are grouped according to their
material application categories, such as:
i)
Special Application Structure, which are normally used for most critical structural areas
ii)
Primary Application Structure, which are normally used for critical structural areas
iii)
Secondary Application Structure, which are normally used for least critical structural areas
The structural elements falling into these categories are described in 3-1-4/5.3 through 3-1-4/5.7.
5.5
Steel Forming
When forming changes base plate properties beyond acceptable limits, appropriate heat treatments are to
be carried out to reestablish required properties. Unless approved otherwise, the acceptable limits of the
reestablished properties should meet the minimums specified for the original material before forming.
Formed members with the forming dimensional tolerances required by the design, are to be examined.
Production Welding
Production welding and forming of steel is to be to the satisfaction of the Surveyor and in accordance with
Section 2-4-1 of the ABS Rules for Materials and Welding (Part 2)
9.1
9.3
Inspection of Welds
All welds are to be subject to visual inspection. Representative Nondestructive Testing (NDT) is to be
carried out to the satisfaction of the Surveyor. Such testing is to be carried out after all forming and post
weld heat treatment. Welds which are inaccessible or difficult to inspect in service may be subjected to
increased levels of NDT.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
15
Part
Chapter
Section
9.5
7
1
2
Surveys
Surveys During Construction
Surveys at Builders Yard Hull Structure and Outfitting
7-1-2
Fillet Welds
Completed welds are to be to the satisfaction of the attending Surveyor. The gaps between the faying surfaces
of members being joined should be kept to a minimum. Where the opening between members being joined
exceeds 2.0 mm (1/16 in.) and is not greater than 5 mm (3/16 in.), the weld leg size is to be increased by the
amount of the opening. Where the opening between members is greater than 5 mm (3/16 in.), corrective
procedures are to be specially approved by the Surveyor.
Where small fillets are used to attach heavy plates or sections, special precautions such as the use of
preheat or low-hydrogen electrodes or low-hydrogen welding processes may be required. When heavy
sections are attached to relatively light plating, the weld size may be required to be modified.
11
11.1
11.3
16
Fabrication/erection joints of pontoons, columns, bracings, diagonals, and upper deck structure
(forming a box girder)
ii)
iii)
Column to braces
iv)
v)
vi)
Brace-to-brace intersections
vii)
viii)
ix)
Lattice-type leg structure; including chords, braces, racks and rack attachments
ii)
iii)
iv)
v)
vi)
vii)
Part
Chapter
Section
11.5
7
1
2
Surveys
Surveys During Construction
Surveys at Builders Yard Hull Structure and Outfitting
7-1-2
Intersections of butts and seams in the sheer strakes, bilge strakes, deck stringer plates and keel
plates
ii)
Intersections of butts in and about moonpool corners on main deck and bottom platings
iii)
iv)
At the discretion of the Surveyor, NDT outside the midship 0.6L is to be carried out at random.
11.7
11.9
Class A acceptance criteria are to be used for NDT of welds of hull structure categorized as
Special Application Structure or Primary Application Structure in accordance with 3-1-4/5.
ii)
Class B acceptance criteria are to be used for NDT of welds of hull structure categorized as
Secondary Application Structure in accordance with 3-1-4/5 and other locations where Class A
acceptance criteria do not apply.
iii)
Modified procedures and acceptance criteria are to be specified to reflect the application when
radiographic or ultrasonic inspection is specified for other type connections such as partial penetration
and groove type Tee or corner welds.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
17
Part
Chapter
Section
7
1
2
Surveys
Surveys During Construction
Surveys at Builders Yard Hull Structure and Outfitting
7-1-2
TABLE 1
Nondestructive Testing* (NDT) of Steel Structure Welds (2012)
Structural Member
100% Volumetric NDT plus 100% Surface NDT all CJP welds, where welded plate
thickness is 5/16 inch (8.0 mm); and
10% MPI of all fillet welds, where plate thickness is 5/16 inch (8.0 mm).
20% Volumetric NDT plus 100% Surface NDT of all CJP welds, where plate
thickness is 5/16 inch (8.0 mm); and
10% Surface NDT of all fillet welds, where plate thickness is 5/16 inch (8.0 mm).
Random Volumetric NDT of CJP welds and Surface NDT of fillet welds, only if
considered suspect by the attending Surveyor during construction.
13
NDT procedures and acceptance criteria is to at least satisfy the ABS Guide for Nondestructive Inspection of Hull Welds.
Corrosion Protection
Unless otherwise approved, all steel work is to be suitably coated. Tanks or preload spaces intended for
salt water ballast are to have a corrosion-resistant hard coating on all internal surfaces.
13.1
15
17
18
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
17.1
7
1
2
Surveys
Surveys During Construction
Surveys at Builders Yard Hull Structure and Outfitting
7-1-2
ii)
Vertical extent of damage from the bottom plating upwards without limit. Where the unit is mat
supported, assumed damage penetration simultaneous to both the mat and upper hull need only be
considered when the lightest draft allows any part of the mat to fall within 1.5 m (5 ft) vertically of
the waterline, and the difference in horizontal dimension of the upper hull and mat is less than
1.5 m (5 ft) in the area under consideration.
The recessed ends and sides of the drilling slot need not be subject to consideration of horizontal penetration,
provided precautions are taken to prevent boats from entering the drilling slot when the unit is afloat (see
7-1-2/Figure 1).
FIGURE 1
Damage Conditions for Self-Elevating Units
(for details see 7-1-2/17.1) (2012)
5.0 feet
1.5 m
17.3
Only those columns on the periphery of the unit are to be assumed damaged with the damage
confined to the exposed outer portions of the columns.
ii)
Damage is assumed to occur for a vertical distance of 3 m (10 ft) at any level between 5.0 m (16.4
ft) above and 3.0 m (10 ft) below the draft under consideration. Where a Watertight flat is located
within this zone, the damage is to be assumed to have occurred in both compartments above and
below the Watertight flat in question.
iii)
No vertical bulkhead is to be assumed damaged, except where bulkheads are spaced closer than a
distance one-eighth of the column perimeter at the draft under consideration, measured at the
periphery, in which case, one or more of the bulkheads is to be considered as damaged.
iv)
v)
Lower hulls or footings are to be treated as damaged when operating at a light or transit condition
in the same manner as indicated in i) through iv).
If damage of a lesser extent results in a more severe final equilibrium condition, such less extent is to be
assumed (see 7-1-2/Figure 2).
On certain modified existing units, the columns are exposed to collision in the full periphery outside the
lines that connect the center of the main columns. In 7-1-2/Figure 2, showing a modified column-stabilized
drilling unit with additional sponsons and single columns, the columns on each side are not aligned. Therefore,
the line that connects the center column to the two end columns is not a straight line.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
19
Part
Chapter
Section
7
1
2
Surveys
Surveys During Construction
Surveys at Builders Yard Hull Structure and Outfitting
7-1-2
Another notable aspect is the effect of sponsons and single columns that are often added to existing units to
enhance their performance. Since the sponsons and single columns are not the main columns, they do not
form the boundary of the protected area and they are fully exposed to a collision (see 7-1-2/Figure 2).
FIGURE 2
Damage Conditions for Column-Stabilized Units
(for details see 7-1-2/17.3) (2012)
5.0 feet
1.5 m
5.0 feet
1.5 m
5.0 feet
1.5 m
16.4 feet
5.0 m
A
Sponson
B
Collision
Penetration
Zone
Single Column
5.0 feet
1.5 m
Lightship
Draft
17.5
10.0 feet
3m
ii)
Vertical extent of damage from the bottom shell upwards without limit
FIGURE 3
Damage Conditions for Surface-Type Units
(for details see 7-1-2/17.5) (2012)
5.0 feet
1.5 m
Collision
Penetration
Zone
5.0 feet
1.5 m
20
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
19
7
1
2
Surveys
Surveys During Construction
Surveys at Builders Yard Hull Structure and Outfitting
7-1-2
Weathertight/Watertight Integrity
During confirmatory survey of weathertight and watertight integrity of drilling units, following requirements
are to be applied and arrangements are to be to the satisfaction of the Surveyor.
19.1
Weathertight Integrity
Closing appliances are to be as prescribed by applicable load line requirements. Special consideration will be
given to openings in the upper deck of column-stabilized units. In all cases, external openings whose lower
edges are below the levels to which weathertight integrity is to be ensured, as shown by the diagrams to be
submitted in accordance with 3-1-2/1, are to have weathertight closing appliances. The referenced diagrams
may define different extents of weathertight integrity for each mode of operation afloat (see 3-1-1/17). Openings
fitted with appliances to ensure weathertight integrity are to be tested. For further details of testing, see 7-1-2/23.
19.3
Watertight Integrity
All internal and external openings whose lower edges are below the levels to which watertight integrity is
to be ensured, as shown by the diagrams submitted in accordance with 1-1-4/1 of the Supplement to the
ABS Rules for Conditions of Classification Offshore Units and Structures (Part 1), are to be fitted with
appliances to ensure watertight integrity.
19.3.1 Internal Openings Used for Access While Afloat
Internal openings fitted with appliances to ensure watertight integrity, which are used during
operation of the unit while afloat, are to comply with 3-3-2/5.3.1:
All such openings together with their remote controls, warning indicators, signs and their means
for closing is to be examined and tested.
19.3.2 Internal Openings Secured Closed While Afloat
Internal openings fitted with appliances to ensure watertight integrity, which are normally to be
secured closed while the unit is afloat, are to comply with 3-3-2/5.3.2:
All such openings together with their signs and their means for closing are to be examined.
19.3.3 External Openings Used While Afloat
External openings which are used during operation of the unit while afloat are to comply with
3-3-2/5.3.3:
All such openings together with their warning indicators, signs and their means for closing is to be
examined and tested to the satisfaction of the attending Surveyor.
19.3.4 External Openings Secured Closed While Afloat
External openings fitted with appliances to ensure watertight integrity, which are normally to be
secured closed while the unit is afloat, are to comply with the requirements of 7-1-2/19.3.2
Internal Openings Secured Closed While Afloat.
All such openings together with their signs and their means for closing are to be examined to the
satisfaction of the attending Surveyor.
19.5
After installation, all watertight and fire-rated cable penetrations are to be visually examined.
Watertight cable penetrations are to be tested as required by 7-1-2/Table 2.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
21
Part
Chapter
Section
21
7
1
2
Surveys
Surveys During Construction
Surveys at Builders Yard Hull Structure and Outfitting
7-1-2
23
23.1
General
Compartments and spaces which are designed to be watertight, gas-tight or fire-tight are to be tested in presence
of a Surveyor by a procedure approved by the attending Surveyor. Any access doors, hatches, manholes or
closures of such compartments and spaces as well as any type of pipe or electrical penetration pieces through
such boundaries is to be completed and tested in similar manner to the satisfaction of the attending Surveyor.
23.3
23.5
Hydrostatic Testing
Unless air testing has been accepted as an alternative, tanks are to be tested with a head of water to the
overflow or to the highest point to which the contents may rise under service conditions, whichever is higher.
This may be carried out either before or after the drilling unit is launched. Special coating may be applied
before hydrostatic testing, provided all welded connections are visually examined to the satisfaction of the
Surveyor before application of the special coating.
23.7
Structural Testing
In order to demonstrate structural adequacy, tank testing of new or unusual design may be required in
connection with the approval of the design. Required structural testing is to be carried out in accordance
with the design approval letter issued by the hull structural engineering office. The testing method and the
medium used for testing is to be as indicated in the ABS approval letter.
23.9
Air Testing
Prior to the application of special coating, air testing by an approved procedure may be accepted as a
supplement or alternative to hydrostatic testing. All boundary welds, erection joints and penetrations, including
pipe and cable connections, are to be examined in accordance with an approved procedure and under a
pressure differential not less than 0.15 bar (0.15 kgf/cm2, 2.2 psi) with a leak indicating solution.
It is recommended that the air pressure in the tank be raised to and maintained at 0.20 bar (0.20 kgf/cm2,
2.9 psi) for approximately one hour, with a minimum number of personnel around the tank, before being
lowered to the test pressure.
A U-tube with a height sufficient to hold a head of water corresponding to the required test pressure is to
be arranged. The cross sectional area of the U-tube is to be not less than that of the pipe supplying air. In
addition to the U-tube, a master gauge or other approved means is to be provided to verify the pressure.
22
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
7
1
2
Surveys
Surveys During Construction
Surveys at Builders Yard Hull Structure and Outfitting
7-1-2
Other effective methods of testing, such as compressed air fillet weld testing or vacuum testing, may be
considered, provided full particulars of the testing procedure is reviewed and agreed by the Surveyor.
TABLE 2
Testing of Boundaries, Compartments, Tanks, and Spaces (2012)
Compartment/Space to be Tested
CSDU Bracings, Horizontals, and
Diagonals (Void)
CSDU Chain Lockers & Chain Pipes
CSDU Watertight Column Spaces
Drill Ship Chain Lockers & Chain Pipes
Drill Ship Hawse Pipes
SEDU Mat Tanks (Buoyant)
SEDU Pre-Load Tanks
SEDU Spud-Cans (Buoyant)
Ballast Tanks
Base Oil Tanks
Drill Water Tanks
Type of
Testing
Air
Flood Test
Air
Flood Test
Hose
Hydrostatic
Air
Hydrostatic
Air
Hydrostatic
Air
Hydrostatic
Gas-tight Doors
Air or Hose
Independent Tanks
Hydrostatic
Mud Pits
Flood Test
Hydrostatic
Air
Voids
Air
Hose
Watertight Doors
Hose
Hose
Hose
Weathertight Doors
Hose
See 7-1-2/23.3.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
23
Part
Chapter
Section
25
7
1
2
Surveys
Surveys During Construction
Surveys at Builders Yard Hull Structure and Outfitting
7-1-2
27
i)
ABS reviewed and stamped drawings showing the location and extent of different grades and
strengths of structural materials, together with a description of the material.
ii)
Welding Procedure Specifications primarily employed for welding of Special Application Structures
and Primary Application Structures, as defined in 3-1-4/5.
iii)
ABS reviewed and stamped drawings showing Special Application Structures and Primary
Application Structures, as defined in 3-1-4/5. This will enable proper identification and wastage
allowances of these structures, as required by 7-2-5/3, 7-2-5/5, or 7-2-5/7, during each Special
Periodical Survey carried out throughout the life of the drilling unit
iv)
ABS reviewed and stamped drawings showing all applicable critical structural areas. This will
enable proper record keeping of the results found during close-up survey and Nondestructive
Testing (NDT) of these areas, as required by 7-2-5/3, 7-2-5/5, or 7-2-5/7, during each Drydocking
(or UWILD) and Special Periodical Survey carried out throughout the life of the drilling unit.
27.1
24
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
PART
Section 3: Surveys at Builders Yard Machinery, Piping, Pressure Vessels, and Outfitting
CHAPTER
SECTION
General
This Section pertains to surveys and testing to be carried out on machinery, piping, pressure vessels, and
mechanical outfitting items during construction, installation and testing of mobile offshore drilling units at
builders yard/facility.
The documentation requirements for design review are given Parts 3, 4, and 5 of these Rules.
Surveys and testing of mechanical and piping systems are referenced in Section 7-1-4 of these Rules.
ABS Surveyor attendance is required, typically for the following purposes. All surveys and testing required
in subsequent Subsections of this Section are to be carried out in presence of and to the satisfaction of the
attending Surveyor, prior to the sea trial as referenced in Section 7-1-9 of these Rules.
ii)
iii)
iv)
Preparation for welding including; forming, edge preparation, fit-up, alignment, cleanliness, and
tack welds
v)
vi)
NDT is to be carried out in accordance with ABS Guide for Nondestructive Inspection of Hull Welds. In
Class I and Class II piping systems, carbon and carbon-molybdenum steel piping for all diameters where
the thickness exceeds 9.5 mm (0.375 in.) and other alloy-steel piping 76 mm (3 in.) in diameter and over
regardless of thickness, welds are to be subjected to 100% Radiographic Testing (RT). All NDT records
are to be reviewed by a Level 2 NDT technician and signed prior to review and endorsement by the
attending Surveyor.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
25
Part
Chapter
Section
7
1
3
Surveys
Surveys During Construction
Surveys at Builders Yard Machinery, Piping, Pressure Vessels, and Outfitting
7-1-3
5.1
5.3
5.5
5.7
7.1
Foundation
Satisfactory alignment of the engine skid structure with hull back-up/foundation structure is to be confirmed
before commencement of any dock-side testing of the engines.
7.3
Warning Notices
Suitable warning notices are to be attached in a conspicuous place on each engine and are to caution
against the opening of a hot crankcase for a specified period of time after shutdown based upon the size of
the engine, but not less than 10 minutes in any case. Such notice is also to warn against restarting an
overheated engine until the cause of overheating has been remedied.
7.5
Governor Control
All engines are to be fitted with governors which will prevent the engines from exceeding the rated speed
by more than 15%. Governor control is to be verified.
For generator sets, see 4-2-1/7.5.1, 4-2-3/7.5.1 and 4-2-4/7.5.1 of the Steel Vessel Rules.
7.7
Onboard Testing
Auxiliary and emergency engine/generator sets are to be tested prior to and during sea trial carried out in
accordance with an agreed procedure and in compliance with these Rules.
Piping
All piping is to be installed and tested in accordance with the Rules or recognized standards.
Satisfactory installation and operation of the piping systems are to be verified, as far as practicable, during
the sea trial.
26
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
7
1
3
Surveys
Surveys During Construction
Surveys at Builders Yard Machinery, Piping, Pressure Vessels, and Outfitting
7-1-3
Piping systems are divided into three classes (Class I, II and III) according to service, design pressure and
temperature, as indicated in 4-2-1/Table 1 of these Rules. Each class has specific requirements for joint
design, fabrication and testing.
All piping system is to be visually examined in accordance with ABS approved plans that consist of a
diagrammatic drawing of each system, including piping size, wall thickness, maximum working pressure
and material of piping as well as the type, size, pressure rating and material of valves and fittings.
Pipe weld details are to comply with Chapter 4 of the ABS Rules for Materials and Welding (Part 2).
Requirements for valves, fittings and flanges are based upon standards of the American National Standards
Institute (ANSI).
9.1
Piping Standards
A booklet of standard piping practices and details, including such items as bulkheads, deck and shell
penetrations, welding details including dimensions, pipe joining details, etc. reviewed by ABS is to be used
during survey of piping systems.
11
Pipe bending
ii)
iii)
iv)
v)
Pipe joints
vi)
Mechanical joints
vii)
Pipes penetrating bulkheads and decks. Penetrations are to be subjected to tests similar to the
bulkhead or deck is tested to. Alternative testing of penetration welds with suitable NDT is to be
to the satisfaction of the Surveyor.
viii)
Pipes penetrating collision bulkhead of surface-type drilling units. Penetrations are to be subjected
to tests similar to the bulkhead is tested to.
ix)
Sluice valves and cocks on surface-type drilling units. Satisfactory operation of these valves or
cocks together with their indicators is to be confirmed.
x)
Relief valves fitted on Class I and Class II systems are to be tested. Relief valves fitted on Class
III systems may be tested if required by the Surveyor.
xi)
xii)
xiii)
Instrument wells, similar protection on fuel oil tanks, and valve arrangements allowing isolation
and removal of instrument on pressure sensing devices
xiv)
Hose assemblies
xv)
Control of static electricity, testing of resistance between ground points along the length, across
joints and from pipe to ground, and verification of bonding straps where used
xvi)
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
27
Part
Chapter
Section
7
1
3
Surveys
Surveys During Construction
Surveys at Builders Yard Machinery, Piping, Pressure Vessels, and Outfitting
7-1-3
11.1
Pipe Bending
Pipe bending is to be in accordance with 2-3-12/25 of the ABS Rules for Materials and Welding (Part 2).
Alternatively, bending in accordance with a recognized standard (e.g. ASME B31.1 Section 129.1 and 129.3)
or other approved specification to a radius that will result in a surface free of cracks and substantially free
of buckles may be acceptable.
11.3
Protection of Pipes
Pipes, valves and operating rods are to be effectively secured and adequately protected. These protective
arrangements are to be fitted so that they may be removed to enable examination of the pipes, valves and
operating rods protected.
11.5
11.7
Pipe support. Adjoining pipes are to be suitably supported so that the expansion joints do not carry
any significant pipe weight.
Alignment. Expansion joints are not to be used to make up for piping misalignment errors. Misalignment
of an expansion joint reduces the rated movements and can induce severe stresses into the joint material,
thus causing reduced service life. Alignment is to be within tolerances specified by the expansion joint
manufacturer.
Anchoring. Expansion joints are to be installed as close as possible to an anchor point. Where an
anchoring system is not used, control rods may be installed on the expansion joint to prevent excessive
movements from occurring due to pressure thrust of the line.
Mechanical damage. Where necessary, expansion joints are to be protected against mechanical damage.
Accessible location. Expansion joints are to be installed in accessible locations to permit regular
inspection and/or periodic servicing.
Mating flange. Mating flanges are to be clean and usually of the flat faced type. When attaching
beaded end flange expansion joints to raised face flanges, the use of a ring gasket is permitted. Rubber
expansion joints with beaded end flange are not to be installed next to wafer type check or butterfly valves.
Serious damage to the rubber flange bead can result due to lack of flange surface and/or bolt connection.
11.9
28
Pipe Joints
Where pipe joints are used, compliance with 4-2-1/11.11 is to be verified.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
7
1
3
Surveys
Surveys During Construction
Surveys at Builders Yard Machinery, Piping, Pressure Vessels, and Outfitting
7-1-3
11.25 Instruments
Where instruments fitted to measure temperature or pressure of the piping system, compliance with
4-2-1/11.27 is to be verified.
Proper calibration of all instruments is to be verified.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
29
Part
Chapter
Section
7
1
3
Surveys
Surveys During Construction
Surveys at Builders Yard Machinery, Piping, Pressure Vessels, and Outfitting
7-1-3
Components of alarms and level indicating devices located within tanks are to account for conductivity.
All leakage containment arrangements are to be examined and verified to satisfy above requirements of
7-1-3/11.31, as applicable.
13
13.1
Steel Pipes
Pipe thicknesses referred to as Standard or Extra Heavy is the equivalent of American National Standards
Institute Schedule 40 and Schedule 80 pipe up to a maximum wall thickness of 9.5 mm (0.375 in.) and
12.5 mm (0.5 in.), respectively.
Material specifications for acceptable steel pipes are referenced in Section 2-3-12 of the ABS Rules for
Materials and Welding (Part 2).
Application of steel pipes is to be in compliance with 4-2-2/5.1 of these Rules.
13.3
30
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
13.5
7
1
3
Surveys
Surveys During Construction
Surveys at Builders Yard Machinery, Piping, Pressure Vessels, and Outfitting
7-1-3
Plastic Pipes
For the purpose of these Rules, plastic means both thermoplastic and thermosetting plastic materials,
with or without reinforcement, such as polyvinyl chloride (PVC) and fiber reinforced plastics (FRP).
13.5.1 Limitations
Pipes and piping components made of thermoplastic or thermosetting plastic materials, with or without
reinforcement, may be used in piping systems referred to in 4-2-2/Table 2, subject to compliance
with requirements of 4-2-2/7.
13.5.2 Marking of Plastic Pipes and other Components
Plastic pipes and other components are to be verified to have permanent marking with identification
in accordance with a recognized standard. Identification is to include pressure ratings, the design
standard that the pipe or fitting is manufactured in accordance with, and the material with which
the pipe or fitting is made and the date of fabrication.
13.5.3 Installation of Plastic Pipes
Installation of plastic pipes is to satisfy the following requirements:
i)
ii)
iii)
Where pipes are joined, the strength of fittings and joints is not to be less than that of the
piping they connect. Pipes may be joined using adhesive-bonded, welded, flanged or other
joints. Tightening of flanged or mechanically coupled joints is to be performed in accordance
with manufacturers instructions. Adhesives, when used for joint assembly, are to be suitable
for providing a permanent seal between the pipes and fittings throughout the temperature
and pressure range of the intended application. Joining techniques are to be in accordance
with manufacturers installation guidelines. Personnel performing these tasks are to be
qualified to the satisfaction of ABS, and each bonding procedure is to be qualified before
shipboard piping installation commences. Requirements for joint bonding procedures are
in 4-2-2/7.11.
iv)
v)
Where plastic pipes are permitted in systems connected to the shell of the unit, the valves
and the pipe connection to the shell are to be metallic. The side shell valves are to be
arranged for remote control from outside of the space in which the valves are located. For
further details of the shell valve installation, their connections and material refer to 4-2-2/21.
vi)
Integrity of watertight bulkheads and decks is to be maintained where plastic pipes pass
through them. Where plastic pipes pass through A or B class divisions, arrangements
are to be made to ensure that the fire endurance is not impaired. If the bulkhead or deck is
also a fire division and destruction by fire of plastic pipes may cause inflow for liquid
from tank, a metallic shut-off valve operable from above the bulkhead deck is to be fitted
at the bulkhead or deck.
vii)
Fire protection coatings are to be applied on the joints, where necessary for meeting the
required fire endurance criteria in 4-2-2/7.5.6. Coating is not to be applied until the piping
system is satisfactorily pressure tested. The fire protection coatings are to be applied in
accordance with the manufacturers recommendations using a procedure approved in each
particular case.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
31
Part
Chapter
Section
15
7
1
3
Surveys
Surveys During Construction
Surveys at Builders Yard Machinery, Piping, Pressure Vessels, and Outfitting
7-1-3
Valves
Valves in piping systems are to satisfy the following requirements:
15.1
Material of Valves
Materials of valves are to meet 4-2-2/17 of these Rules. Manufacturers material certificates are to be
available for verification, as deemed necessary by the Surveyor.
15.3
Standard of Valves
Valves that are in compliance with a recognized standard are acceptable to ABS, subject to compliance
with 4-2-2/9.5. Valves that are not certified by the manufacturer in accordance with a recognized standard,
may be accepted when valve design is reviewed by ABS and accepted.
15.5
Construction of Valves
Construction of valves is to be verified as satisfying the following requirements:
15.7
32
i)
All valves are to close with a right hand (clockwise) motion of the hand wheel when facing the
end of the stem and are to be either of the rising stem type or fitted with an indicator to show
whether the valve is open or closed.
ii)
All valves of Class I and Class II piping systems having nominal diameters exceeding 50 mm (2 in.)
are to have bolted, pressure seal or breech lock bonnets and fanged or welding ends. Welding ends
are to be butt welding type, except that socket welding ends may be used for valves having
nominal diameters of 80 mm (3 in.) or less, up to and including 39.2 bar (40.0 kgf/cm2) pressure
rating class (ANSI 600 Class), and for valves having nominal diameters of 65 mm (2.5 in.) or less,
up to and including 98.1 bar (100 kgf/cm2) pressure rating class (ANSI 1500 Class).
iii)
All cast iron valves are to have bolted bonnets or are to be of the union bonnet type. For cast iron
valves of union bonnet type, the bonnet ring is to be of steel, bronze or malleable iron.
iv)
Stems, discs or disc faces, seats, and other wearing parts of valves are to be of corrosion-resistant
materials suitable for intended service.
v)
Valves are to be designed for the maximum pressure to which they will be subjected. The design
pressure is to be at least 3.4 bar (3.5 kgf/cm2, 50 psi), except that valves used in open systems,
such as vent and drain lines, and valves mounted on atmospheric tanks which are not part of the
tank suction or discharge piping (for example, level gauge and drain cocks and valves in inert gas
and vapor emission control systems) may be designed for a pressure below 3.4 bar (3.5 kgf/cm2,
50 psi), subject to the requirements of 4-2-2/9.1. Large fabricated ballast manifolds which connect
lines exceeding 200 mm (8 in.) nominal pipe size may be specially considered when the maximum
pressure to which they will be subjected does not exceed 1.7 bar (1.75 kgf/cm2, 25 psi).
vi)
All valves for Class I and Class II piping systems and valves intended for use in steam or oil lines
are to be constructed so that the stem is positively restrained from being screwed out of the body
(bonnet). Plug cocks, butterfly valves and valves employing resilient material will be subject to
special consideration.
vii)
Valve operating systems for all valves which cannot be manually operated are to be submitted to
ABS engineering for approval.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
17
7
1
3
Surveys
Surveys During Construction
Surveys at Builders Yard Machinery, Piping, Pressure Vessels, and Outfitting
7-1-3
Pipe Fittings
All fittings in Class I and Class II piping are to have flanged or welded ends in sizes over 89 mm O.D. (3 in.
N.P.S). Screwed fittings may be used in Class I and Class II piping systems, provided the temperature does
not exceed 496C (925F) and the pressure does not exceed the maximum pressure indicated in 4-2-2/11.1.
The type of fittings used on Class I, Class II and Class III piping systems are to satisfy 4-2-2/11. See
4-2-2/19 for fluid power cylinders.
17.1
Material of Fittings
Materials of fittings are to meet 4-2-2/17 of these Rules. Manufacturers material certificates are to be
available for verification, as deemed necessary by the Surveyor.
17.3
17.5
19
Flanges
Flanges are to be in compliance with a recognized national or international standard. The type of flanges
and method of attachment used on Class I, Class II and Class III piping systems are to be in compliance
with 4-2-2/15.
19.1
Material of Flanges
Materials of flanges are to meet 4-2-2/17 of these Rules. Manufacturers material certificates are to be
available for verification, as deemed necessary by the Surveyor.
21
21.1
21.3
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
33
Part
Chapter
Section
23
7
1
3
Surveys
Surveys During Construction
Surveys at Builders Yard Machinery, Piping, Pressure Vessels, and Outfitting
7-1-3
23.1
Connections
Piping connections bolted to the shell plating are to have the bolt heads countersunk on the outside and the
bolts threaded through the plating. Where a reinforcing ring of sufficient thickness is riveted or welded to
the inside of the shell, studs may be used.
Threaded connections outboard of the shell valves are not considered an acceptable method of connecting
pipe to the shell.
Pipe connections fitted between the shell and the valves are to have a minimum wall thickness not less than
that specified in 4-2-2/21.3 and be as short as possible.
23.3
ii)
Clear of or protected from obstructions, moving equipment and hot surfaces that prevent operation
or servicing, and
iii)
Materials readily rendered ineffective by heat are not to be used for connection to the shell where the
failure of the material in the event of a fire would give rise to danger of flooding.
23.5
34
Column-Stabilized Units: Sea-water inlets and discharges below the assigned load line are to be
provided with valves which can be remotely operated from an accessible position outside of the
space.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
25
7
1
3
Surveys
Surveys During Construction
Surveys at Builders Yard Machinery, Piping, Pressure Vessels, and Outfitting
7-1-3
ii)
Self-Elevating and Surface-Type Units: Sea-water inlets and discharges in spaces below the
assigned load line which are not intended to be normally manned are to be provided with valves
which can be remotely operated from an accessible position outside of the space. If the valves are
readily accessible, the spaces containing the inlets and discharges may be provided with bilge
alarms in lieu of remote operation of the valves.
iii)
Self-Elevating Units: Mud pit discharges are to be provided with valves which can be operated
from an accessible position. These valves are to be normally closed and a sign to this effect is to
be posted near the operating position. Non-return valves need not be provided.
25.1
Connections
Discharges led through the shell either from spaces below the freeboard deck or from within
superstructures and deckhouses on the freeboard deck, fitted with doors complying with the requirements
of 3-2-11/5 of the Steel Vessel Rules, are to be fitted with efficient and accessible means for preventing
water from passing inboard.
25.3
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
35
Part
Chapter
Section
27
7
1
3
Surveys
Surveys During Construction
Surveys at Builders Yard Machinery, Piping, Pressure Vessels, and Outfitting
7-1-3
27.1
Connections
The inlet and discharge connections of external cooler installations are to be verified to be in accordance
with 4-2-2/21.1, 4-2-2/21.3, 4-2-2/21.5 and 4-2-2/21.9, except that wafer type valves will be acceptable.
27.3
27.5
29
29.1
Ventilation Systems
Non-watertight ducts passing through subdivision bulkheads and watertight ducts servicing more than one
watertight compartment or which are within the extent of damage are to be verified to be provided with
valves at the subdivision boundary. Valve operators are to be fitted with position indicators. Control of
valves is to be either from the ballast control room (or other normally manned spaces), or from a readily
accessible location which is above the calculated immersion line in the damaged condition (see 3-3-2/1.3).
29.3
36
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
PART
CHAPTER
SECTION
General
This Section pertains to surveys and testing to be carried out on mechanical and piping systems during
construction, installation and testing of mobile offshore drilling units at builders yard/facility.
The documentation requirements for design review are given Parts 3, 4, and 5 of these Rules.
Installation surveys and testing of machinery, piping, pressure vessels, and outfitting items are referenced
in Section 7-1-3 of these Rules.
ABS Surveyor attendance is required, typically for the following purposes. All surveys and testing is to be
carried out in presence of and to the satisfaction of the attending Surveyor, prior to the sea trial as referenced
in Section 7-1-9 of these Rules.
3.1
Materials
Material certificates, satisfying 6-1-9/9 of these Rules are to be made available to the attending Surveyor.
3.3
3.5
Hydraulic System
Hydraulic cylinder material is to satisfy 6-1-9/17 of these Rules. The hydraulic system is to satisfy 6-1-9/17
of these Rules and verified as being satisfactorily installed.
3.7
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
37
Part
Chapter
Section
7
1
4
Surveys
Surveys During Construction
Surveys at Builders Yard Mechanical and Piping Systems
7-1-4
5.1
5.3
5.5
5.7
5.9
Overflow Pipes
Arrangement and installation of overflow pipes and applicable alarms of overflow tanks are to satisfy
4-2-3/1.11 of these Rules.
Sounding
Sounding arrangements are to be examined and tested to confirm compliance with 4-2-3/3 of these Rules.
The required examination and testing is to be carried out to verify systems compliance with below specific
requirements, prior to the sea trial.
When air/hydrostatic testing of tanks/voids, sounding pipes are to be examined and subjected to air/hydrostatic
testing.
7.1
Sounding Pipes
Size, installation and termination arrangements of sounding pipes are to satisfy 4-2-3/3.3 of these Rules.
7.3
38
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
7
1
4
Surveys
Surveys During Construction
Surveys at Builders Yard Mechanical and Piping Systems
7-1-4
Bilge System
Bilge system is to be examined and tested to confirm compliance with 4-2-4/1, 4-2-4/3, 4-2-4/5, 4-2-4/7,
and 4-2-4/9 of these Rules. The required examination and testing is to be carried out to verify systems
compliance with below specific requirements, prior to the sea trial.
Bilge system, together with its fitted alarms, is to be examined and tested prior to the sea trial.
Satisfactory operation of the bilge system together with its alarms is to be re-confirmed during the sea trial
(see Section 7-1-8).
9.1
9.3
9.5
9.7
9.9
11
Surface-Type Units
Sizes of main and branch lines are to be verified in accordance with ABS reviewed P&ID
drawings and to comply with 4-2-4/9.1 of these Rules.
9.9.2
Ballast System
Examination and testing of the ballast manifolds is to be carried out to confirm compliance with below
specific requirements, prior to the sea trial.
Ballast control features are to be examined and tested to confirm compliance with below specific requirements,
prior to the sea trial. Satisfactory operation of the ballast control features is to be re-confirmed during the
sea trial.
11.1
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
39
Part
Chapter
Section
11.3
7
1
4
Surveys
Surveys During Construction
Surveys at Builders Yard Mechanical and Piping Systems
7-1-4
The assumed damaged conditions as specified in 3-3-2/1.3.2(a) with any one pump inoperable.
ii)
In addition, the system is to be capable of raising the unit, starting from a level trim condition at deepest
normal operating draft, either a distance of 4.6 m (15 ft) or to the severe storm draft, whichever distance is
greater, within three hours (calculations are to be submitted for review).
This capability test is to be carried out during the ballast trial.
13
13.1
13.3
13.5
40
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
7
1
4
Surveys
Surveys During Construction
Surveys at Builders Yard Mechanical and Piping Systems
7-1-4
13.7
15
17
Lubricating-Oil Systems
Examination and testing of the lube-oil system is to be carried out to confirm compliance with below
specific requirements, prior to the sea trial.
The lubricating-oil piping is to be entirely separated from other piping systems. In addition, the requirements
of 4-2-5/1.1.2, 4-2-5/1.3, and 4-2-5/1.5 of these Rules are applicable.
The requirements in 4-2-5/3.9 are also applicable for lubricating-oil tanks. However, arrangements for
remotely closing the valve from a position outside of the compartment need not be provided if inadvertent
valve closure could result in damage to the running machinery due to lack of lubricating-oil. Where the
machinery is arranged for automatic shutdown upon loss of lubricating-oil, the valve required by 4-2-5/3.9 is
to be provided with means to close it from a readily accessible and safe location outside of the
compartment in which the valve is located.
For ship-type units, the lubricating systems are to be so arranged that they will function satisfactorily under
the conditions specified in 4-1-1/7 of these Rules.
17.1
17.3
17.5
17.7
Electrical Machinery
For electrical machinery, see 4-3-3/3.3, 4-3-3/3.5.1 and 6-1-7/5.13 of these Rules.
19
Hydraulic Systems
Examination and testing of the hydraulic systems is to be carried out to confirm compliance with below
specific requirements, prior to the sea trial.
The arrangements for Class I and II hydraulic piping systems are to be in accordance with the requirements
of this section, except that hydraulic systems which form part of an independent device or equipment not
covered by these Rules and which does not form part of the units piping system (such as a crane) are not
covered by this Section, unless it is relevant to an optional notation or certification requested for the unit.
The requirements for fuel oil tanks contained in 4-2-5/1.1.2 and 4-2-5/1.3 of these Rules are also applicable
for tanks containing hydraulic fluid.
Arrangement and installation of valves, piping, pipe fittings, hoses, accumulators, fluid power cylinders,
and the segregation of the high pressure hydraulic units, are to satisfy 4-2-6/3.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
41
Part
Chapter
Section
21
7
1
4
Surveys
Surveys During Construction
Surveys at Builders Yard Mechanical and Piping Systems
7-1-4
21.1
Application
Provisions of 4-2-6/5.3 of these Rules apply to fixed oxygen-acetylene installations that have two or more
cylinders of oxygen and acetylene, respectively. Spare cylinders of gases need not be counted for this purpose.
Provisions of 4-2-6/5.5 and 7-1-4/41.9, of these Rules, as applicable, are to be complied with for fixed
installations regardless of the number of cylinders.
21.3
Gas Storage
Storage of gas cylinders, ventilation of storage rooms, and electrical installation in the storage rooms are to
satisfy 4-2-6/5.3 of these Rules.
21.5
The area within 3 m (10 ft) of the pressure relief device discharge outlet is to be regarded as a
hazardous area.
23
23.1
General
Isolation of fixed fuel storage and transfer facilities, construction of fuel storage tanks, fuel storage tank
vents and valves, are to satisfy 4-2-6/7.1. See Section 7-1-7 of these Rules for survey of hazardous areas.
23.3
Spill Containment
Arrangements for spill containment and drainage are to satisfy 4-2-6/7.3 of these Rules.
25
Starting-air Systems
Examination and testing of the starting air system is to be carried out to confirm compliance with below
specific requirements, prior to the sea trial.
25.1
25.3
Starting-air Capacity
Units having internal combustion engines arranged for air starting are to be provided with at least two
starting-air containers of approximately equal size. The total capacity of the starting-air containers is to be
sufficient to provide, without recharging the containers, at least the number of consecutive starts stated
below. If other compressed air systems, such as control air, are supplied from starting-air containers, the
aggregate capacity of the containers is to be sufficient for continued operation of these systems after the air
necessary for the required number of starts has been used.
42
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
7
1
4
Surveys
Surveys During Construction
Surveys at Builders Yard Mechanical and Piping Systems
7-1-4
Minimum number of consecutive starts as applicable, and as required per following conditions defined in
7-1-4/25.3.1 through 7-1-4/25.3.3, is to be verified prior to the sea trial.
25.3.1 Diesel Propulsion
The minimum number of consecutive starts (total) required to be provided from the starting-air
containers is to be based upon the arrangement of the engines and shafting systems as indicated in
the following 7-1-4/Table 1.
TABLE 1
Starting Air Minimum Number of Consecutive Starts (2012)
Single Screw Unit
One engine
coupled to shaft
directly or through
reduction gear
One engine
coupled to each shaft
directly or through
reduction gear
Reversible Engines
12
16
16
16
Non-reversible Engines
For arrangements of engines and shafting systems which differ from those indicated in the table, the
capacity of the starting-air containers will be specially considered based on an equivalent number of
starts.
25.3.2 Diesel-electric Propulsion
The minimum number of consecutive starts required to be provided from the starting-air containers
is to be determined from the following equation.
S = 6 + G(G 1)
where
S = total number of consecutive starts
G = number of engines necessary to maintain sufficient electrical load to permit vessel
transit at full seagoing power and maneuvering. The value of G need not exceed 3.
25.3.3 Non Self-Propelled Units
The minimum number of consecutive starts required to be provided from the starting-air containers
is three (3) per auxiliary engine, but the total capacity of the starting-air containers dedicated to
the auxiliary engines need not exceed eight (8) consecutive starts.
25.3.4 Protective Devices for Starting-air Mains
Installation of protective devices is to satisfy 4-2-6/9.5.
27
27.1
General
Means are to be provided to ascertain the temperature of the circulating water at the return from each
engine and to indicate that the proper circulation is being maintained. Drain cocks are to be provided at the
lowest point of all jackets. For relief valves, see 4-2-1/11.21.
27.3
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
43
Part
Chapter
Section
29
7
1
4
Surveys
Surveys During Construction
Surveys at Builders Yard Mechanical and Piping Systems
7-1-4
Exhaust System
Examination of the exhaust system is to be carried out to confirm compliance with 4-2-6/13, prior to the
sea trial.
31
33
35
37
39
41
41.1
44
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
7
1
4
Surveys
Surveys During Construction
Surveys at Builders Yard Mechanical and Piping Systems
7-1-4
Transfer systems and fuel-oil suction lines are to be tested before installation to 3.4 bar (3.5 kgf/cm2,
50 psi).
Record of satisfactory hydrostatic testing is to be available to the Surveyor.
41.1.3 Starting-Air System
Piping in starting-air systems is to be tested, preferably before installation, to 1.5 times the design
pressure of the system.
Record of satisfactory hydrostatic testing is to be available to the Surveyor. If the piping could not
be tested before installation, Surveyors witness of testing after installation is required.
41.1.4 Hydraulic Power System
After fabrication, the hydraulic power piping system or each piping component is to be tested to
1.5 times the design pressure.
i)
ii)
Due to very high working pressure of such systems, it is preferred that an initial low pressure air
leak test is carried out. Upon satisfactory completion of the leak test, the hydrostatic testing of the
piping is to be carried out preferably using calibrated pressure gauges with pressure chart recording
capability, and piping maintained under the hydrostatic pressure for minimum of 15 minutes.
Necessary safety precaution is to be taken by the builder during the high-pressure hydrostatic
testing of these piping systems.
41.1.7 All Piping Systems
After installation, all piping is to be tested under working conditions. Where it is not possible to carry
out the required hydrostatic tests for all segments of pipes and integral fittings before installation,
the remaining segments, including the closing seams, may be so tested after installation. Or, where
it is intended to carry out all of the required hydrostatic tests after installation, such tests may be
conducted in conjunction with those required by this Paragraph. In both these respects, testing
procedures are to be submitted to the Surveyor for acceptance.
Testing of the piping systems under working condition may be carried out during the sea trial,
provided the piping installation was visually examined and found satisfactory prior to commencement
of the sea trial.
41.3
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
45
Part
Chapter
Section
7
1
4
Surveys
Surveys During Construction
Surveys at Builders Yard Mechanical and Piping Systems
7-1-4
41.5
41.7
41.9
46
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
PART
CHAPTER
SECTION
General
This Section pertains to surveys carried out on electrical cables and equipment during construction, installation
and testing of mobile offshore drilling units at builders yard/facility, including required onboard testing
and trial. The documentation requirements for design review are given Parts 3, 4, and 5 of these Rules.
ABS Surveyor attendance is required, typically for the following purposes. All surveys and testing is to be
carried out in presence of and to the satisfaction of the attending Surveyor, prior to the sea trial as
referenced in Section 7-1-9 of these Rules.
1.1
Definitions
For definition of various terms, see 4-3-1/3.
ii)
Inspection of cable trays, electrical cables, cable supports, and cable fastenings.
iii)
iv)
Megger Tests.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
47
Part
Chapter
Section
7
1
5
Surveys
Surveys During Construction
Surveys at Builders Yard Electrical Cables and Equipment
7-1-5
Cable Installation
5.1
General Considerations
Electric cables are to be installed in continuous lengths between terminations at equipment or in cable
junction boxes (see 4-3-3/5.25). However, approved splices will be permitted at interfaces of new construction
modules, when necessary to extend existing circuits for a drilling unit undergoing repair or alteration, and
in certain cases to provide for cables of exceptional length (see 4-3-3/5.21).
The cross-sectional areas of conductors are to be confirmed to be in accordance with approved drawings.
Cables and wiring are to be installed and supported in such a manner as to avoid chafing or other damage.
Cables are to be located with a view to avoiding, as far as practicable, spaces where excessive heat and
gases may be encountered; also, spaces where they may be exposed to damage, such as exposed sides of
deckhouses. Cables are not to be installed in the bilge area unless protected from bilge water.
Where cables are installed in a cable draw box and horizontal pipes or the equivalent is used for cable
protection, means of drainage are to be verified.
Cables serving systems above 1 kV are not to be bunched with cables serving systems of 1 kV and below.
Where paint or any other coating is systematically and intentionally applied on the electric cables, it is to
be established that the mechanical and fire performance properties of the cable are not adversely affected.
In this regard:
i)
ii)
It is to be confirmed that the paint and the solvent used will not cause damages to the cable sheath
(e.g., cracking).
Overspray on cables or painted exterior cables are not subject to the requirements of this section.
5.3
2 megohms
10 amperes load
1 megohm
25 amperes load
400,000 ohms
50 amperes load
250,000 ohms
100,000 ohms
50,000 ohms
25,000 ohms
If the above values are not obtained, any or all appliances connected to the circuit may be disconnected for
this test.
5.5
48
ii)
iii)
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
5.7
5.9
7
1
5
Surveys
Surveys During Construction
Surveys at Builders Yard Electrical Cables and Equipment
7-1-5
ii)
Terminations and joints in all conductors are to be so made as to retain the original electrical,
flame retarding and, where necessary, fire resisting properties of the cable.
iii)
Terminal boxes are to be secured in place and the moisture-resistant jacket is to extend through the
cable clamp.
iv)
Enclosures for outlets, switches and similar fittings are to be flame-resistant and moisture-resistant
and of adequate mechanical strength and rigidity to protect the contents and to prevent distortion
under all likely conditions of service (see 4-3-3/5.17.1 and 4-3-3/5.21).
The support and fixation measures are to be verified to be in compliance with the following.
5.9.1(a) The distances between supports are to be suitably chosen according to the type of cable
and the probability of vibration, and are not to exceed 400 mm (16 in.). For a horizontal cable run
where the cables are laid on cable supports in the form of tray plates, separate support brackets or
hanger ladders, the spacing between the fixing points may be up to 900 mm (36 in.), provided that
there are supports with maximum spacing as specified above. This exemption does not apply to
cable runs along weather decks when the cable run is arranged so that the cables can be subjected
to forces by water washing over the deck.
Note:
When designing a cable support system for single-core cables, consideration is also to be given to the
effects of electrodynamic forces developing on the occurrence of a short-circuit.
The above-given distances between cable supports are not necessarily adequate for these cables. Further,
other recognized standards for cable support and fixing will be considered.
5.9.1(b) The supports and the corresponding accessories are to be robust and are to be of
corrosion-resistant material or suitably treated before erection to resist corrosion.
5.9.1(c) Cable clips or straps made from an approved material other than metal (such as polyamide,
PVC) may be used.
5.9.1(d) When cables are fixed by means of clips or straps referred to in 7-1-5/5.9.1(c) above and
these cables are not laid on top of horizontal cable trays or cable supports, suitable metal cable
clips or saddles are to be added at regular distances not exceeding 2 m (6.5 ft) in order to prevent
the release of cables during a fire. This also applies to the fixing of nonmetallic conduits or pipes.
Note:
Item 7-1-5/5.9.1(d) does not necessarily apply in the case of cable runs with only one or a few cables
with small diameters for the connection of a lighting fitting, alarm transducer, etc.
5.9.1(e) Non-metallic clips, saddles or straps, are to be flame retardant in accordance with IEC
Publication 60092-101.
5.9.2
Bending Radius
For bending radius requirements, see 7-1-5/Table 1 of these Rules.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
49
Part
Chapter
Section
7
1
5
Surveys
Surveys During Construction
Surveys at Builders Yard Electrical Cables and Equipment
7-1-5
TABLE 1
Minimum Bending Radii of Cables (2012)
Insulation
Cable construction
Outer covering
Minimum internal
bending radius
Thermoplastic or
thermosetting with
circular copper
conductor
Unarmored or unbraided
D 25 mm (1 in.)
4D
D > 25 mm
6D
Any
6D
Any
6D
Any
8D
Thermoplastic or
thermosetting with
shaped copper
conductor
Any
Any
8D
Mineral
Hard metal-sheathed
Any
6D
5.9.3
i)
Installation details
ii)
iii)
iv)
Cable trays and protective casings made of plastic materials are to be supplemented by metallic
fixing and straps such that, in the event of a fire, they and the cables affixed are prevented from falling
and causing an injury to personnel and/or an obstruction to any escape route. See 7-1-5/5.9.1(d).
Cable occupation ratio in protective casing. The sum of the total cross-sectional area of all cables
on the basis of their external diameter is not to exceed 40% of the internal cross-sectional area of
the protective casing. This does not apply to a single cable in a protective casing
5.11
5.13
50
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
5.15
7
1
5
Surveys
Surveys During Construction
Surveys at Builders Yard Electrical Cables and Equipment
7-1-5
Mechanical Protection
5.15.1 Metallic Armor
Protection of electric cables installed in locations liable to damage during normal operation of the
drilling unit are to be verified during cable installation survey. Cables can either be provided with
braided metallic armor or other means to protect them from mechanical injury as appropriate.
5.15.2 Conduit Pipe or Structural Shapes
Protection of electric cables installed in locations in way of hatch openings, tank tops, open decks
subject to seas, and where passing through decks, are to be verified and confirmed to be protected
by substantial metal shields, structural shapes, pipe or other equivalent means. When expansion
bends are fitted, they are to be accessible for maintenance. The protection and its installation are to
be in compliance with 4-3-3/5.15 of these Rules.
5.17
i)
ii)
iii)
iv)
v)
Control and power systems for all power operated fire doors and their status indicating
systems
vi)
Control and power systems for all power operated watertight doors and their status indicating
systems
vii)
Emergency lighting
viii)
ix)
Remote emergency stop/shutdown arrangement for systems which may support the
propagation of fire and/or explosion
It is to be verified that, as far as practicable, cables and wiring for emergency and essential
services, including those listed above are not to pass through high fire risk areas. It is also to be
verified that these cables and wiring are run in such a manner as to preclude their being rendered
unserviceable by heating of the bulkheads that may be caused by a fire in an adjacent space (See
4-3-3/5.17).
5.17.2 Requirements by the Governmental Authority
Requirements (if any) of the Flag Administration for installation of emergency circuits required in
various types of drilling units, is to be taken into consideration.
5.19
5.21
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
51
Part
Chapter
Section
7
1
5
Surveys
Surveys During Construction
Surveys at Builders Yard Electrical Cables and Equipment
7-1-5
5.23
Battery Room
Where cables enter battery rooms, the holes are to be bushed as required for watertight bulkheads in
7-1-5/5.13. All connections within battery rooms are to be resistant to the electrolyte. Cables are to be
sealed to resist the entrance of electrolyte by spray or creepage.
5.25
5.27
5.29
5.31
5.33
52
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
7
1
5
Surveys
Surveys During Construction
Surveys at Builders Yard Electrical Cables and Equipment
7-1-5
7.1
Materials
Material of all electrical equipment is to be in compliance with 4-3-1/11 of these Rules.
7.3
Grounding Arrangements
Where not obtained through normal construction, arrangements provided to effectively ground metal
structures of derricks, masts and helicopter decks are to be verified. See also 4-2-6/7.1.3 for fuel storage
for helicopter facilities.
All grounding arrangements are to be verified before the drilling unit commences its sea trial.
7.5
7.7
7.9
Temperature Ratings
Temperature ratings of all electrical equipment are to be in compliance with 4-3-1/17 of these Rules. The
ratings of equipment are to be verified at random as meeting the design drawings.
7.9.1
The equipment used for cooling and maintaining the lesser ambient temperature is to be classified
as a secondary essential service, in accordance with 4-3-1/3.5, and the capability of cooling is to
be witnessed at sea trial.
7.11
7.13
Where electrical and electronic equipment is located within areas protected by local fixed pressure
water-spraying or water-mist fire extinguishing system and those within adjacent areas exposed to
direct spray, equipment is to be verified for having a degree of protection not less than IP44.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
53
Part
Chapter
Section
7
1
5
Surveys
Surveys During Construction
Surveys at Builders Yard Electrical Cables and Equipment
7-1-5
7.15
Generators
In general, all generators on ship-type drilling units are to be located with their shafts in a fore-and-aft direction
on the drilling unit and are to operate satisfactorily in accordance with the inclination requirements of
4-1-1/Table 1. Where it is not practicable to mount the generators with the armature shafts in the fore-andaft direction, their lubrication will require special consideration, and this arrangement will be confirmed
onboard.
7.17
7.19
Accumulator Batteries
Permanently installed power, control and monitoring storage batteries of acid or alkaline types are to be so
arranged that the trays are accessible and provided with not less than 254 mm (10 in.) headroom. Where a
relief valve is provided for discharging excessive gas due to overcharge, arrangements are to be made for
releasing the gas to the weather deck away from any source of ignition.
7.19.1 Battery Installation and Arrangements
Installation and arrangement of large storage batteries, moderate size batteries, and small batteries
are to be verified in compliance with 4-3-3/3.7.2 of these Rules.
A low-hydrogen-emission battery with a battery charger having a charging rate of a large or moderate
battery size installation may be treated as a moderate or small battery installation, respectively, if
the following are met and verified:
54
i)
Calculations under the worst case charging conditions are submitted and reviewed by
Engineering; and
ii)
A warning notice is placed to notify maintenance personnel that additional batteries are
not to be installed, and batteries are only to be replaced by other batteries of the same or
lower hydrogen emission rate.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
7
1
5
Surveys
Surveys During Construction
Surveys at Builders Yard Electrical Cables and Equipment
7-1-5
The schedule and procedures put in place are to satisfy 4-3-3/3.7.5 of these Rules. Details of the
schedule, procedures, and the maintenance records are to be included in the drilling units maintenance
system and integrated into the drilling units operational maintenance routine, as appropriate, and
verified.
7.19.9 Replacement of Batteries
Where a vented type battery replaces a valve-regulated, sealed type battery, the requirements in
4-3-3/3.7.6 are to be confirmed.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
55
Part
Chapter
Section
7.21
7
1
5
Surveys
Surveys During Construction
Surveys at Builders Yard Electrical Cables and Equipment
7-1-5
Switchboards
7.21.1 Location and Protection
Arrangement of switchboards are to be confirmed as providing easy access, as may be needed, to
apparatus and equipment without danger to personnel. Switchboards are to be located in a dry place
so as to provide a clear working space of at least 914 mm (36 in.) at the front of the switchboard
and a clearance of at least 610 mm (24 in.) at the rear, which may be reduced to 457 mm (18 in.)
in way of stiffeners or frames. Arrangement and location of distribution boards are to be verified
to be in compliance with 4-3-3/3.9 of these Rules.
Note:
Where switchboards are enclosed at the rear and are fully serviceable from the front, clearance at the rear
will not be required unless necessary for cooling.
7.23
Distribution Boards
7.23.1 Location and Protection
Distribution boards are to be located in accessible positions. Location and enclosure of distribution
boards are to be verified to be in compliance with 4-3-3/3.11.1 of these Rules.
Flanged connections of liquid piping are to be avoided over or near distribution boards for essential
services. If a connection was necessary and agreed by the Surveyor, satisfactory provision to
prevent any leakage from injuring the boards is to be verified.
7.23.2 Switchboard-Type Distribution Boards
Distribution boards of the switchboard type, unless installed in machinery spaces or in compartments
assigned exclusively to electric equipment and accessible only to authorized personnel, are to be
verified as being completely enclosed or protected against accidental contact and unauthorized
operation.
7.23.3 Safety-Type Panels
It is to be verified that safety type panels are used only for controlling branch lighting circuits,
provided with dead front type panels where voltage to earth is in excess of 50 volts DC or 50 volts
AC rms between conductors.
7.25
It is to be verified that motor control centers are secured to a solid foundation, be self-supported or
be braced to the bulkhead.
Flanged connections of liquid piping are to be avoided over or near motor controllers and control
centers. If a connection was necessary and agreed by the Surveyor, satisfactory provision to
prevent any leakage from injuring the motor controllers and control centers is to be verified.
56
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
7
1
5
Surveys
Surveys During Construction
Surveys at Builders Yard Electrical Cables and Equipment
7-1-5
7.27
7.29
Lighting Fixtures
Lighting fixtures are to be verified as being arranged as to prevent temperature rises which could damage
the cables and wiring, and to prevent surrounding material from becoming excessively hot.
7.31
Heating Equipment
Electric radiators, if used, are to be verified as being fixed in position and be so constructed as to reduce fire
risks to a minimum. It is to be confirmed that electric radiators of the exposed-element type are not used.
7.33
Magnetic Compasses
Precautions taken in connection with apparatus and wiring in the vicinity of the magnetic compass to
prevent disturbance of the needle from external magnetic fields, is to be verified.
7.35
7.37
7.39
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
57
Part
Chapter
Section
7
1
5
Surveys
Surveys During Construction
Surveys at Builders Yard Electrical Cables and Equipment
7-1-5
Earthing
9.1
General
Unless the machines or equipment are one of the type as listed in 4-3-3/7.1, the exposed metal parts of
electrical machines or equipment which are not intended to be live but which are liable under fault
conditions to become live are to be earthed. Earthing is to be verified.
9.3
Permanent Equipment
It is to be verified that the metal frames or cases of all permanently installed generators, motors, controllers,
instruments and similar equipment are permanently earthed through a metallic contact with the drilling
units structure. Alternatively, they may be connected to the hull by a separate conductor in accordance
with 4-3-3/7.5 of these Rules.
Where outlets, switches and similar fittings are of nonmetallic construction, all exposed metal parts are to be
verified as being earthed.
9.5
Connections
It is to be verified that all earthing conductors are of copper or other corrosion-resistant material and are
protected against damage. The nominal cross-sectional area of every copper earthing conductor is to be not
less than that required by 4-3-3/Table 2.
Earthed distribution system and connections to vessels hull are to be verified to be in compliance with
4-3-3/7.5.2 and 4-3-3/7.5.3 respectively.
9.7
Portable Cords
Receptacle outlets operating at 50 volts DC or 50 volts AC rms or more are to be confirmed for having an
earthing pole.
9.9
58
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
PART
CHAPTER
SECTION
General
This Section pertains to surveys and testing to be carried out on electrical systems during construction,
installation and testing of mobile offshore drilling units at builders yard/facility. The documentation
requirements for design review are given Parts 3, 4 and 5 of these Rules.
ABS Surveyor attendance is required, typically for the following purposes. All surveys and testing is to be
carried out in presence of and to the satisfaction of the attending Surveyor, prior to the sea trial as referenced
in Section 7-1-9 of these Rules.
3.1
3.1.2
Examination and testing of the main source of power is to be carried out to confirm compliance
with below specific requirements. For further details, see 4-3-2/3.1.
A Blackout situation means the loss of the main source of electrical power resulting in the main
and auxiliary machinery being out of operation.
A Dead Ship condition means a condition under which:
i)
The main propulsion plant, boilers and auxiliary machinery are not in operation due to the
loss of the main source of electrical power, and
ii)
In restoring propulsion, the stored energy for starting the propulsion plant, the main source
of electrical power and other essential auxiliary machinery is assumed to be not available.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
59
Part
Chapter
Section
7
1
6
Surveys
Surveys During Construction
Surveys at Builders Yard Electrical Systems
7-1-6
For self-propelled drilling units, the generating sets are to be such that with any one generator or
its primary source of power out of operation, the remaining generating sets are capable of providing
the electrical services necessary to start the main propulsion plant from a dead ship condition, as
defined herein, within 30 minutes of the blackout. This is to be verified during sea trial as
referenced in Section 7-1-9 of these Rules.
In restoring the propulsion from a dead ship condition for self-propelled drilling units, no stored
energy is to be assumed available for starting the propulsion plant, the main source of electrical
power and other essential auxiliaries. It is assumed that means are available to start the emergency
generator at all times.
The emergency source of electrical power may be used to restore the propulsion, provided its
capability either alone or combined with that of any other source of electrical power is sufficient to
provide at the same time those services required to be supplied by 4-3-2/5.3.1 through 4-3-2/5.3.7.
The emergency generator and other means needed to restore the propulsion are to have a capacity such
that the necessary propulsion starting energy is available within 30 minutes of blackout. Emergency
generator stored starting energy is not to be directly used for starting the propulsion plant, the main
source of electrical power and/or other essential auxiliaries (emergency generator excluded).
3.3
3.5
Sizing of AC Generator
Sizing of the AC Generator is to satisfy 4-3-2/3.5.
5.1
5.3
60
Emergency Lighting
For a period of 18 hours, emergency lighting:
i)
At every embarkation station on deck and over the sides, their launching appliances and
the area of water into which they are to be launched.
ii)
In all service and accommodation alleyways, stairways and exits, personnel elevators and
their trunks.
iii)
In the machinery spaces and main generating stations, including their control positions.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
7
1
6
Surveys
Surveys During Construction
Surveys at Builders Yard Electrical Systems
7-1-6
iv)
In all control stations, machinery control rooms, and at each main and emergency
switchboard.
v)
In all spaces from which control of the drilling process is performed and where controls
of machinery essential for the performance of this process, or devices for emergency
switching-off of the power plant are located.
vi)
vii)
At the sprinkler pump, if any, at one of the fire pumps, if dependent upon emergency
generator for its source of power, at the emergency bilge pump, if any, and at the starting
positions of their motors.
viii)
5.3.2
5.3.3
5.3.4
Internal Communications
For a period of 18 hours, all internal communication systems required in an emergency (see Note 1
below).
5.3.5
5.3.6
Emergency Signals
For a period of 18 hours, intermittent operation of the manually operated call points and all internal
signals that are required in an emergency (see Note 1 below).
5.3.7
5.3.8
5.3.9
Diving Equipment
For a period of 18 hours, permanently installed diving equipment necessary for safe conduct of
diving operations, if dependent on the drilling units electrical power.
i)
Ballast valve control system, ballast valve position indicating system, draft level indicating
system and tank level indicating system.
ii)
The largest single ballast pump required by 4-2-4/13.5.1. See also 4-3-2/5.11 of these Rules.
i)
ii)
For a period of 18 hours, navigational aids as required by Chapter V of the 1974 SOLAS
Convention, as amended (see Note below).
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
61
Part
Chapter
Section
7
1
6
Surveys
Surveys During Construction
Surveys at Builders Yard Electrical Systems
7-1-6
iii)
For a period of 18 hours, intermittent operation of the daylight signaling lamp and the
units whistle (see Note 1 below).
iv)
For a period of at least 10 minutes, continuous operation of the steering gear (see 4-3-2/11.5
of these Rules).
5.5
ii)
For a period of 30 minutes, free-fall lifeboat secondary launching appliance, if the secondary
launching appliance is not dependent on gravity, stored mechanical power or other manual
means.
iii)
For a period of 18 hours, intermittent operation of the general emergency alarm system
and other manually operated alarms required in 4-3-2/17.
Note 1
Unless independent supply from an accumulator battery suitably located for use in an emergency and
sufficient for the period of 18 hours is supplied.
Emergency Sources
Satisfactory operation and testing of the emergency source of electrical power and its protective devices
are to be carried out prior to the sea trial as referenced in Section 7-1-9 of these Rules.
The emergency source of electrical power may be either a generator or an accumulator battery in accordance
with 4-3-2/5.5.2 or 4-3-2/5.5.3. The emergency generator and its prime mover and any emergency accumulator
battery are to be designed to function at full rated power when upright and when inclined in static condition
up to a maximum angle of heel in the intact and damaged condition, as determined in accordance with
Section 3-3-2.
In no case need the equipment be designed to operate when inclined in static condition more than:
22.5 about the longitudinal axis and/or when inclined 10 about the transverse axis on a surface unit.
In all cases, the emergency source of electrical power is to be designed to operate as a minimum under the
angles of inclination defined in 4-1-1/7.1.
5.7
5.5.1
Generator
Where the emergency source of electrical power is a generator, it is to satisfy 4-3-2/5.5.2.
5.5.2
Accumulator Battery
Where the emergency source of electrical power is an accumulator battery, it is to satisfy 4-3-2/5.5.3.
5.5.3
62
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
5.9
7
1
6
Surveys
Surveys During Construction
Surveys at Builders Yard Electrical Systems
7-1-6
Emergency Switchboard
The emergency switchboard is to be installed as near as is practicable to the emergency source of electrical
power.
Satisfactory operation of the emergency switchboard is to be verified prior to the sea trial as referenced in
Section 7-1-9 of these Rules.
Installation of the emergency switchboard for generator, installation of accumulator batteries, arrangement
of inter-connector feeder between emergency and main switchboards, and arrangements made where
necessary to automatically disconnect the non-emergency circuits from the emergency switchboard, are to
satisfy 4-3-2/5.9.
5.11
Ballast Pumps
On column-stabilized units, arrangement of ballast pumps is to satisfy 4-3-2/5.11. It is to be possible to
supply each ballast pump required by 4-2-4/13.5.1 from the emergency source of power. The arrangement is
to be such that one of the pumps is connected directly to the main switchboard and the other pump is connected
directly to the emergency switchboard. For systems utilizing independent pumps in each tank, all pumps
are to be capable of being supplied from an emergency source of power. When sizing the emergency
source of power in accordance with 4-3-2/5.3, the largest ballast pump capable of being supplied from this
source is to be assumed to be operating simultaneously with the loads specified in 4-3-2/5.3, allowing for
suitable load and diversity factors.
5.13
i)
Electrical and hydraulic starting systems are to be maintained from the emergency
switchboard.
ii)
Compressed air starting systems may be maintained by the main or auxiliary compressed
air receivers through a suitable non-return valve or by an emergency air compressor
which, if electrically driven, is supplied from the emergency switchboard.
iii)
All of these starting, charging and energy storing devices are to be located in the
emergency generator space. These devices are not to be used for any purpose other than
the operation of the emergency generating set. This does not preclude the supply to the air
receiver of the emergency generating set from the main or auxiliary compressed air
system through the non-return valve fitted in the emergency generator space.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
63
Part
Chapter
Section
7
1
6
Surveys
Surveys During Construction
Surveys at Builders Yard Electrical Systems
7-1-6
When manual (hand) starting is not practicable, the requirements of 4-3-2/5.15.2 and 4-3-2/5.15.3
are to be complied with, except that starting may be manually initiated.
5.15
TABLE 1
Emergency Diesel Engine Alarms and Shutdowns (2012)
Systems
Fuel Oil
Monitored Parameters
Alarm
Auto
Shutdown
Notes
[X = Required]
A1
B1
Temperature high
B2
B3
Cooling
Medium
C1
C2
Engine
D1
Lubricating
Oil
Temperature high
Over-speed activated
Distribution System
7.1
64
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
7.3
7
1
6
Surveys
Surveys During Construction
Surveys at Builders Yard Electrical Systems
7-1-6
ii)
Limited and locally earthed systems, provided that any possible resulting current does not flow
directly through any hazardous areas; or
iii)
Insulation level monitoring devices, provided the circulation current does not exceed 30 mA under
all possible conditions.
iv)
Current-carrying parts with potential to earth are to be protected against accidental contact.
Where the hull return system is used, arrangements are to satisfy 4-3-2/7.3.2.
7.5
7.7
Information Plate
An information plate is to be provided at or near the connection box giving full information on the
system of supply and the nominal voltage (and frequency if AC) of the drilling units system and
the recommended procedure for carrying out the connection.
7.7.2
7.9
Harmonics
The Total Harmonic Distortion (THD) is to satisfy 4-3-2/7.9.
ii)
iii)
iv)
v)
vi)
vii)
viii)
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
65
Part
Chapter
Section
11
7
1
6
Surveys
Surveys During Construction
Surveys at Builders Yard Electrical Systems
7-1-6
11.1
11.3
11.5
11.7
13
13.1
Lighting System
13.1.1 Main Lighting System
A main electric lighting system is to provide adequate illumination throughout those parts of the
drilling unit normally accessible to and used by crew. It is to be supplied from the main source of
electrical power.
13.1.2 System Arrangement
The arrangement of the main electric lighting system is to be such that a fire or other casualty in
spaces containing the main source of electrical power, associated transforming equipment, if any,
the main switchboard and the main lighting switchboard will not render the emergency electric
lighting system required by 4-3-2/5.3ii) inoperative.
The arrangement of the emergency electric lighting system is to be such that a fire or other casualty
in spaces containing the emergency source of electrical power, associated transforming equipment, if
any, the emergency switchboard and the emergency lighting switchboard will not render the main
electric lighting system required by 4-3-2/13.1.1 inoperative.
13.1.3 Lighting Circuits
In machinery and accommodation spaces such as:
Public spaces
Galleys
Corridors
There is to be more than one final subcircuit for lighting, one of which may be supplied from the
emergency switchboard, in such a way that failure of any one circuit does not leave these spaces in
darkness.
66
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
7
1
6
Surveys
Surveys During Construction
Surveys at Builders Yard Electrical Systems
7-1-6
13.3
13.5
15
15.1
i)
System Requirements. The system is to be a loud speaker installation enabling the broadcast
of messages which are clearly audible in all parts of the unit. The system is to provide for the
broadcast of messages from the navigation bridge, emergency control stations (see 7-1-8/17.7)
and other strategic points with an override function so that all emergency messages may
be broadcast if any loudspeaker in the locations concerned has been turned off, its volume
has been turned down or the public address system is in use for other purposes.
ii)
Minimum Sound Levels. With the drilling unit underway or in normal operating conditions,
the minimum sound levels for broadcasting emergency announcements are to be:
In interior locations, 75 dB (A) and at least 20 dB (A) above the speech interference level
In exterior locations, 80 dB (A) and at least 15 dB (A) above the speech interference level
iii)
iv)
Public Address System Combined with General Alarm System. Where a single system
serves for the public address and general emergency alarm functions, the system is to be
arranged so that a single failure is not to cause the loss of both systems and is to minimize
the effect of a single failure. The major system components, such as power supply unit,
amplifier, alarm tone generator, etc., are to be duplicated. The coverage provided by the
arrangement of the system loops and speakers is to be such that after a single failure, the
announcements and alarms are still audible in all spaces. Duplication of system loops and
speakers in each room or space is not required provided the announcements and alarms
are still audible in all spaces.
Where an elevator is installed, a telephone is to be permanently installed in all cars and connected
to a continuously manned area. The telephone may be sound powered, battery operated or electrically
powered from the emergency source of power.
Final sub-circuit for power supply to these voice communication systems is to be independent of
other electrical systems and control, monitoring and alarm systems. See 7-1-6/5.3.4 for power supply.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
67
Part
Chapter
Section
15.3
7
1
6
Surveys
Surveys During Construction
Surveys at Builders Yard Electrical Systems
7-1-6
One of the communicating means between the navigation bridge and the main propulsion control
position is to be an engine room telegraph which provides visual indication of the orders and
responses both in the machinery space and on the navigation bridge. Communication network and
power supply circuit for this may be combined with the engine order telegraph system specified in
4-3-2/15.3.
15.3.2 Main Propulsion Control Stations
A common talking means of voice communication and calling or engine order telegraph repeater
is to be provided between the main propulsion control station and local control positions for main
propulsion engines and controllable pitch propellers. Voice communication systems are to provide
the capability of carrying on a conversation while the drilling unit is being navigated. Final
subcircuit for power supply to these is to be independent of the other electrical system and the
control, monitoring and alarm systems. Communication network and power supply circuit for the
voice communication system may be combined with the system required in 4-3-2/15.5.
15.3.3 Voice Communications
In addition to 7-1-6/15.1.2, a common talking means of voice communication and calling is to be
provided between the navigation bridge, main propulsion control station and the steering gear
compartment so that the simultaneous talking among these spaces is possible at all times and the
calling to these spaces is always possible even if the line is busy.
15.3.4 Emergency and Interior-communication Switchboard
Emergency and interior-communication switchboards, when fitted, are to comply with the applicable
parts of 6-1-7/9 of these Rules, and attention is directed to the requirements of the governmental
authority whose flag the drilling unit flies.
17
17.1
68
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
7
1
6
Surveys
Surveys During Construction
Surveys at Builders Yard Electrical Systems
7-1-6
i)
(2014) The minimum sound levels for the emergency alarm tone in interior spaces are to be 80 dB
and at least 10 dB (A) above ambient noise levels existing during normal equipment operation in
moderate weather.
ii)
The sound levels at the sleeping position in cabins and in cabin bathrooms are to be at least 75 dB
(A) and at least 10 dB (A) above ambient noise levels.
Note:
Refer to the Code on Alarms and Indicators adopted by IMO Resolution A.830(19).
17.3
17.5
17.7
Elevator Alarm
A device which will activate an audible and visual alarm in a manned control center is to be provided in all cars.
Such alarm system is to be independent of power and control systems of the elevator. See 7-1-6/5.3.12iii)
for power supply.
19
19.1
Emergency Stop
19.1.1 Ventilation System
All electrical ventilation systems are to be provided with means for stopping the motors in case of
fire or other emergency. These requirements do not apply to closed re-circulating systems within a
single space. See also 7-1-8/9.
The main machinery-space ventilation is to be provided with means for stopping the ventilation
fans, which is to be located in the passageway leading to, but outside of the space, or in the firefighting station, if provided.
A control station for all other ventilation systems is to be located in the fire-control room or
navigation bridge, or in an accessible position leading to, but outside of the space ventilated.
19.1.2 Other Auxiliaries
For emergency tripping and emergency stop for other auxiliaries such as forced and induced draft
fans, electric motor pressurization fans, oil fuel transfer pumps, fuel oil units, see 4-2-5/1.5 and
7-1-8/17.9.
19.3
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
69
Part
Chapter
Section
21
7
1
6
Surveys
Surveys During Construction
Surveys at Builders Yard Electrical Systems
7-1-6
21.1
Auxiliary Systems
All auxiliary apparatus is to be tried under working conditions.
21.3
Generators
Each generator is to be run for a time sufficient to show satisfactory operation, and parallel operation with
all possible combinations is to be demonstrated.
Generator safety devices and shutdowns are to be confirmed operational.
The emergency generator is to be run for a time sufficient to show satisfactory operation, and its alarms
and safeguard devices to be confirmed (see 4-3-2/5).
21.5
Auxiliary Motors
Each auxiliary motor necessary to the operation of the drilling unit is to be run for a time sufficient to show
satisfactory performance at such load as can readily be obtained.
21.7
21.9
Lighting System
The operation of the lighting system, heaters, etc., is to be demonstrated satisfactorily (see 7-1-6/13.1).
Satisfactory operation the emergency lights after a black-out condition is to be confirmed. Sufficient lighting
in all control stations, egress routes, and embarkation stations are to be verified.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
7
1
6
Surveys
Surveys During Construction
Surveys at Builders Yard Electrical Systems
7-1-6
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
71
PART
CHAPTER
SECTION
General
This Section pertains to survey of the following items onboard mobile offshore drilling units built at
builders yard/facility, including required onboard testing and trial. The documentation requirements for
design review are given Part 4 of these Rules. Following items are to be surveyed and tested in presence of
and to the satisfaction of the attending Surveyor, preferably prior to delivery of the drilling unit.
i)
ii)
iii)
Installation and function of access doors and hatches between hazardous areas and adjoining
areas/spaces
iv)
v)
vi)
vii)
Installation of cables and electrical equipment in paint stores and battery lockers
viii)
1.1
Definitions
For definition of various terms, see 4-3-1/3 and 4-3-6/1 of these Rules.
3.1
Openings
Where there is an opening, not fitted with any gas-tight enclosure device, at boundary decks or bulkheads
between an area/space categorized as hazardous and a less hazardous or non-hazardous enclosed area/space,
the entire area/space categorized as less hazardous will be considered as the same category of the higher
category hazardous Zone.
Mitigation of this situation is possible only if the opening is permanently closed, fitted with a bolted gas-tight
closure or provided with doors satisfying the arrangements and provisions required by 7-1-7/3.1 through
7-1-7/3.5, as applicable.
Where there is an opening, not fitted with any gas-tight enclosure device, at boundary decks or bulkheads
between an area/space categorized as hazardous and a non-hazardous open space, hazardous Zone will
extend into the non-hazardous open space. The extended hazardous areas will be categorized as defined in
4-3-6/5 of these Rules, and any machinery or electrical equipment within the extended hazardous area is to
be verified as suitable for safe operation for that hazardous Zone.
72
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
3.3
7
1
7
7-1-7
Penetrations
Any structural, piping or electrical penetration located on a deck or a bulkhead between an area/space
categorized as hazardous and a less hazardous or non-hazardous enclosed area/space, is to maintain the
gas-tight integrity of the deck or bulkhead.
3.3.1
Surveys
Surveys During Construction
Surveys at Builders Yard Hazardous Areas
Testing of Penetrations
Completed penetrations are to be tested to prove the gas-tightness of the boundary. Testing can be
carried out by one of the following method:
i)
ii)
An air-flow pressure test (mostly used for Multi-Cable Transit (MCT) penetrations)
iii)
5.1
Enclosed Zone 1 or Zone 2 Space with Direct Access to any Zone 1 Location
(see 7-1-7/Figure 1)
5.1.1
5.1.2
i)
The access is fitted with a gas-tight door opening into the Zone 2 space; and
ii)
Ventilation is such that the air flow with the door open is from the Zone 2 space into the
Zone 1 location; and
iii)
Loss of positive (+) ventilation in Zone 2 location is alarmed at a normally manned station.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
73
Part
Chapter
Section
7
1
7
Surveys
Surveys During Construction
Surveys at Builders Yard Hazardous Areas
7-1-7
FIGURE 1
Access to Zone 1 (2012)
Broken lines represent open, semi-enclosed, or enclosed zone.
Zone 1
Zone 1
Self-closing Gastight
Door (having no hold
back device)
Zone 1
Air
Flow
Zone 2
5.3
74
Enclosed Zone 2 or Non-Hazardous Space with Direct Access to any Zone 2 Location
(see 7-1-7/Figure 2)
5.3.1
5.3.2
i)
The access is fitted with self-closing gas-tight door that opens into the non-hazardous space;
and
ii)
Ventilation is such that the air flow with the door open is from the non-hazardous space
into the Zone 2 locations; and
iii)
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
7
1
7
Surveys
Surveys During Construction
Surveys at Builders Yard Hazardous Areas
7-1-7
FIGURE 2
Access to Zone 2 (2012)
Broken lines represent open, semi-enclosed, or enclosed zone.
Zone 2
Zone 2
Self-closing Gastight
Door (having no hold
back device)
Zone 2
Air
Flow
Non-Hazardous
5.5
5.5.2
i)
The access is fitted with gas-tight self-closing doors forming an air lock, or a single selfclosing gas-tight door which opens toward the non-hazardous space and has no hold-back
device; and
ii)
Ventilation is such that the air flow with the door or air lock doors open is from the nonhazardous space into the Zone 1 location (i.e., non-hazardous space has ventilation
overpressure in relation to the Zone 1 location); and
iii)
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
75
Part
Chapter
Section
7
1
7
Surveys
Surveys During Construction
Surveys at Builders Yard Hazardous Areas
7-1-7
FIGURE 3
Access from Enclosed Non-Hazardous Areas to Zone 1 (2012)
Broken lines represent open, semi-enclosed, or enclosed zone.
Zone 1
Air
Lock
Air
Flow
Non-Hazardous
Self-closing Gastight
Door (having no hold
back device)
Zone 1
Air
Flow
Non-Hazardous
5.7
Hose test (mostly used where there is no machinery or electrical equipment that may be affected
by splashing of water)
ii)
An air-flow pressure test (recommended for all gas-tight doors fitted on bulkheads providing
direct access mentioned in 7-1-7/5.1 through 7-1-7/5.5 of these Rules
Note:
Where a gas-tight door is tested per 7-1-7/5.7 ii) above, the applied air pressure is to be natural and provided by the
ventilation system fitted in each adjoining area/space. During the test, all applicable ventilators are to be fully
operational, and the loss of positive (+) and loss of overpressure is to be preferably tested simultaneously with
testing of the doors.
Door alarms are to be clearly visible and audible during drilling units normal operational noise level.
5.9
Ventilation
Ventilation systems for the hazardous and non-hazardous areas are to be in accordance with 4-3-6/7 of
these Rules. All ventilation system ducts and associated ventilation alarms are to be examined and tested.
5.9.1
Ventilation Ducts
Gas-tight ventilation ducts fabricated to maintain either positive or negative internal pressure, as
required, are to be subjected to appropriate testing of the ducts, to verify its tightness, after
installation onboard the drilling unit and prior to function testing of the ventilation system and its
alarms required by 7-1-7/5.1 through 7-1-7/5.5 of these Rules.
5.9.2
Type tests on non-sparking fans are to be carried out using an acceptable national or international
standard. Such type test reports are to be made available when requested by the Surveyor.
76
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
7
1
7
5.9.3
Surveys
Surveys During Construction
Surveys at Builders Yard Hazardous Areas
7-1-7
Machinery Installations
Where installed in hazardous areas, machinery installation is to comply with 4-3-6/9 of these Rules.
9.1
9.3
General
9.1.1
Cables Installation
Installation of electrical cables is to be in compliance with 4-3-3/9.1.4 of these Rules.
9.1.2
Lighting Circuits
Installation of lighting circuits is to be in compliance with 4-3-3/9.1.5 of these Rules. The switches
and protective devices for lighting fixtures are to be suitably labeled for identification purposes.
9.1.3
Pressurized Equipment
Pressurized equipment is to be in compliance with 4-3-3/9.3.3 of these Rules.
Where pressurized/purged air system is used, the purge air system and operation of the
pressurized/purged equipment with its associated loss of power or the ventilation and alarms
provided are to be tested for compliance with 4-3-3/9.3.3 of these Rules.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
77
Part
Chapter
Section
9.5
7
1
7
Surveys
Surveys During Construction
Surveys at Builders Yard Hazardous Areas
7-1-7
11
13
13.1
FIGURE 4
Typical Drain Connection (2016)
Hazardous Area
Non-Hazardous Area
760 mm
(30 inches)
78
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
7
1
7
Surveys
Surveys During Construction
Surveys at Builders Yard Hazardous Areas
7-1-7
13.3
13.5
The resistance to earth (ground) from any point in the system is not to exceed 1 megohm. The
resistance is to be checked in the presence of and to the satisfaction of the Surveyor.
ii)
Where used, earthing wires or bonding straps are to be accessible for inspection. The Surveyor is
to verify that they are in visible locations.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
79
PART
CHAPTER
SECTION
General
This Section pertains to surveys and testing to be carried out on fire and safety features during construction,
installation and testing of mobile offshore drilling units at builders yard/facility. The documentation
requirements for design review are given Part 5 of these Rules.
ABS Surveyor attendance is required, typically for the following purposes. All surveys and testing is to be
carried out in presence of and to the satisfaction of the attending Surveyor, prior to the sea trial.
1.1
Administration Certification
When an Administration or its Agent other than the ABS, issues the IMO Mobile Offshore Drilling Unit
Safety Certificate to a drilling unit, such certificate will be accepted as evidence that the unit is in compliance
with the requirements of 7-1-8/5. In all other cases, the required information and plans are to be reviewed
by ABS, and surveys completed by ABS Surveyors.
80
i)
ii)
iii)
iv)
v)
vi)
vii)
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
7
1
8
Surveys
Surveys During Construction
Surveys at Builders Yard Fire and Safety
7-1-8
5.1
Construction Materials
All steel material used for construction is to be certified in accordance with Section 7-1-2 of these
Rules. Material other than steel is to be provided with manufacturers certification of compliance,
and be readily available to the attending Surveyor.
Fire integrity of bulkheads and decks are to be confirmed only after the bulkheads and decks are
satisfactorily examined and tested for structural purposes.
5.1.3
i)
A and B class divisions are penetrated for the passage of electrical cables, pipes,
trunks, ducts, etc.
ii)
A class divisions are penetrated for girders, beams or other structural members, or
iii)
B class divisions are penetrated for the fitting of ventilation terminals, lighting fixtures
and similar devices.
Structural fire protection of joints and penetrations is to be applied, preferably when fire integrity
is confirmed by the Surveyor and only after bulkheads and decks are satisfactorily examined and
tested for structural purposes.
5.1.5
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
81
Part
Chapter
Section
7
1
8
5.1.6
Surveys
Surveys During Construction
Surveys at Builders Yard Fire and Safety
7-1-8
Fire Doors
Fire doors are to be examined for compliance with 5-1-1/3.17 of these Rules, and installation in
accordance with ABS reviewed drawings. For conditions of accepting installation of watertight
doors in fire tight boundaries, see 5-1-1/3.17. Record of tests in accordance with Fire Test Procedure
Code (Resolution MSC.61(67)) are to be available to the Surveyor.
Where the self-closing fire doors are allowed to be fitted with hold-back hooks that incorporate
remote release fittings of the fail-safe type, the remote-release mechanism is to be tested.
5.3
Accommodation Bulkheads
All accommodation bulkheads are to be examined prior to their enclosure behind joiner work. For
further details see 5-1-1/5.3 and 5-1-1/5.5 of these Rules.
5.3.2
All self-closing doors are to be tested for proper closure without any external force.
82
5.3.3
Draft Stops
All draft stops required by 5-1-1/5.11 of these Rules are to be examined prior to closing behind
joiner work. Structure, piping or electric cables penetrations through draft stops are to maintain the
integrity of the draft stop. Fire protection drawings reviewed by the ABS is to be used as guidance
for installation and penetration details.
5.3.4
5.3.5
i)
ii)
iii)
5.3.6
Veneers
Where bulkheads, linings and ceilings are covered with combustible veneers, they are to be in
compliance with 5-1-1/5.19 of these Rules. Where veneers are used, appropriate certificates are to
be available to the Surveyor.
5.3.7
5.3.8
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
7
1
8
5.3.9
Surveys
Surveys During Construction
Surveys at Builders Yard Fire and Safety
7-1-8
Ventilation Ducts
Ventilation ducts are to be examined and tested for compliance with ABS reviewed drawings, and
they are to be in compliance with 5-1-1/5.25 of these Rules.
Where they are fitted with shutters or water curtain, arrangements are to be function tested.
5.3.19 Arrangement of Ventilation for Accommodation Spaces and Control Stations
The ventilation for accommodation spaces and control stations are to be arranged in such a way as
to prevent the ingress of flammable, toxic or noxious gases, or smoke from surrounding areas.
5.3.20 Air Balancing Ducts (Jumper Ducts)
Where air balancing ducts are fitted, compliance with 5-1-1/5.47 of these Rules is to be verified.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
83
Part
Chapter
Section
7
1
8
Surveys
Surveys During Construction
Surveys at Builders Yard Fire and Safety
7-1-8
7.1
7.3
The use of Surveyor-endorsed fire control plan per the above, is not considered to be an outstanding.
Fire Pumps
There are to be at least two independently-driven fire pumps. Following items affecting suitability and
performance of the fire pumps installed onboard and in compliance with 5-2-2/1.1 of these Rules are to be
verified:
i)
ii)
iii)
Where provided, examination and testing of other type pumps used for active fire protection
iv)
v)
Pressure is to be at least 3.5 bar (3.5 kgf/cm2, 50 psi) at the hydrant, and the maximum pressure at any
hydrant shall be such that the effective control of a fire hose can be demonstrated.
vi)
Where installed, testing of the relief valves (per 5-2-2/1.1.6 of these Rules)
vii)
Where installed, installation and testing of intermediate tank water supply (per 5-2-2/1.1.7 of these
Rules)
viii)
Where fire pumps take suction from a pressurized water main system (i.e., a system not utilizing
an intermediate tank supply as on self-elevating units), arrangement and precautions required by
5-2-2/1.1.8 are to be verified.
7.5
Fire Main
The fire main system is to be examined and tested for compliance 5-2-2/1.3 of these Rules and verified in
accordance with approved drawings.
7.7
Hydrants
The number and position of the hydrants are to be physically verified after completion and
installation of structure, machinery and equipment onboard the drilling unit.
Note:
84
Confirming that a single length of hose may reach any part of the unit normally accessible to the crew
while the drilling unit is being operated, is to be confirmed by actual measurements, to the extent
deemed necessary by the Surveyor.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
7
1
8
7.7.2
Surveys
Surveys During Construction
Surveys at Builders Yard Fire and Safety
7-1-8
Hoses
All fire hoses are to be in compliance with 5-2-2/1.5.2 of these Rules and provided with couplings
and nozzles. Additionally, at least one complete fire hose assembly is to be carried as a spare.
15 m in machinery spaces
ii)
iii)
7.7.3
Nozzles
Dual purpose combined jet spray nozzles fitted throughout the unit, and in compliance with
5-2-2/1.5.3 of these Rules, are to be verified.
7.7.4
9.1
9.1.2
9.1.3
Controls
Arrangement of independent manual controls is to be verified, and the controls are to be tested.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
85
Part
Chapter
Section
7
1
8
9.1.4
Surveys
Surveys During Construction
Surveys at Builders Yard Fire and Safety
7-1-8
Installation of the CO2 system is to be examined in accordance with reviewed drawings and the
system subjected to function testing with a gas safe for human health.
9.3
Foam System
Where fitted, installation of the foam system is to be examined in accordance with reviewed drawings and
function tested.
9.3.1
Fixed foam fire-extinguishing systems using inside air are to be designed, constructed and tested
in accordance with the requirements identified in MSC.1/Circ. 1271 Guidelines for the Approval
of High-Expansion Foam Systems Using Inside Air for the Protection of Machinery Spaces and
Cargo Pump-Rooms.
Foam concentrates are to be of an approved type.*
* Note:
9.3.2
Reference is made to the International Maritime Organization MSC/Circular 670 Guidelines for the
Performance and Testing Criteria, and Surveys of High-Expansion Foam Concentrates for Fixed FireExtinguishing Systems.
In addition to the applicable requirements of the Rules, fixed low expansion foam systems are to
be in accordance with Chapter 6.2.1 and 6.2.2 of the International Code for Fire Safety Systems.
Foam concentrates are to be of an approved type.**
** Note: Reference is made to the International Maritime Organization MSC/Circular 582 Guidelines for the
Performance and Testing Criteria, and Surveys of Low-Expansion Foam Concentrates for Fixed FireExtinguishing Systems.
9.5
9.7
86
Part
Chapter
Section
7
1
8
9.7.2
Surveys
Surveys During Construction
Surveys at Builders Yard Fire and Safety
7-1-8
Function of the fixed-foam system is to be demonstrated and the rate of delivery of the foam solution is
to be measured.
9.9
11
11.1
11.3
Firefighters Outfit
All firefighter outfits installed as indicated on ABS reviewed plans, are to be verified for compliance with
5-2-4/3 of these Rules. Every firefighters outfit is to be provided with a breathing apparatus, a lifeline, a
safety lamp, an axe, nonconductive boots and gloves, a rigid helmet and protective clothing as required by
5-2-4/3 of these Rules.
If provided, the apparatus for recharging air cylinders is to be confirmed to be in compliance with 5-2-4/3.5
of these Rules, and the recharging capacity is to be tested to confirm that it meets the requirements of
SOLAS regulation II-2/10.10.2.6.
13
13.1
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
87
Part
Chapter
Section
15
7
1
8
Surveys
Surveys During Construction
Surveys at Builders Yard Fire and Safety
7-1-8
15.1
17
Outfitting
Outfitting items fitted onboard the drilling unit, such as the systems covered by this Subsection are to be in
accordance with ABS reviewed plans and in compliance with this Subsection.
Thorough examination of the means of escape, means of access and egress, and guards and rails fitted along the
routes is to be carried out, before the drilling unit commences its trials per Section 7-1-9 of these Rules.
17.1
Means of Escape
Arrangement of escape routes from accommodation spaces, service spaces and control stations, from
category A machinery spaces, from other machinery spaces, superstructures or deckhouses, together with
stairways or ladders in way of any escape route, and the accessibility and access through the routes, are to be
in accordance with 5-3-1/1 of these Rules.
17.1.1 Gratings in way of Escape Routes
If deck gratings are used along designated escape route(s) in manned areas, category A machinery
spaces, other machinery spaces, or from the superstructure and deckhouses to the survival craft
embarkation areas, material of grating is to be of steel.
Gratings made of material other than steel, such as Fiber Reinforced Plastics (FRP), may be used,
provided the grating material meets the design criteria similar to requirements contained in
Section 4-2-2 of these Rules.
i)
Fire endurance of non-steel gratings used in way of escape routes of open decks and
spaces that may be directly subjected to hydrocarbon fire, is to meet requirements of
Level 1 fire endurance standard (L1).
ii)
Fire endurance of non-steel gratings used in way of escape routes of open decks and
spaces that may not be directly subjected to hydrocarbon fire, is to meet requirements of
Level 2 fire endurance standard (L2).
Manufacturers material test reports for any L1 and L2 grating material are to be available to the
attending Surveyor.
Gratings made of material other than steel may be used in spaces (e.g. walkways in service spaces,
normally unmanned spaces, mud pit rooms, machinery maintenance decks/platforms, etc.) that are
not along the designated escape route, provided the grating material meets the design criteria
similar to requirements contained in Section 4-2-2 of these Rules and requirements of Level 3
fire endurance standard (L3).
17.3
88
Part
Chapter
Section
7
1
8
Surveys
Surveys During Construction
Surveys at Builders Yard Fire and Safety
7-1-8
17.5
17.7
17.9
Ventilating fans and openings to be examined and tested (see 5-3-1/9.1 of these Rules)
ii)
iii)
iv)
19
19.1
In the case of units using Dynamic Positioning System (DPS) as the only means of position keeping, special
consideration may be given to the selective disconnection or shutdown of machinery and equipment associated
with maintaining the operability of the DPS in order to preserve the integrity of the well.
i)
Emergency lighting required by 7-1-6/5.3.1i), ii) iii), and iv) for half an hour
ii)
iii)
iv)
v)
All equipment in exterior locations which is capable of operation after shutdown is to be suitable for
installation in Zone 2 locations.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
89
PART
CHAPTER
SECTION
General
A sea trial procedure is to be developed by the builder and submitted to the attending Surveyor for review and
comments, well in advance, prior to commencement of the trial.
A pre-planning meeting in presence of the attending Surveyor(s) is to be carried out prior to the sea trial to
at least confirm the following:
Sea trial schedule and estimated duration of tests to be carried out during the sea trial
Key personnel from the builder, owner, operator, and any other representative
Any specific test to be carried out that may be outside the scope of classification
During sea trial of a drilling unit, the operation of machinery, electrical systems and safety features
required by these Rules is to be demonstrated to the satisfaction of the attending Surveyor(s). Complete
function tests are to be carried out, including duration runs and tests for operation of all protective devices
and stability tests for control, in presence of and to the satisfaction of the attending Surveyor(s).
If the drilling unit is self-propelled, maneuvering tests which should include a reversal of the drilling unit
from full speed ahead to full speed astern, is also to be carried out in presence of and to the satisfaction of
the attending Surveyor(s).
Stability Test
A stability test is required to be performed on every vessel. The American Society and Materials Standard
(ASTM) Guide for conducting stability tests, Standard Guide for Conducting a Stability Test (Inclining and
Lightweight Survey) to Determine the Light Ship Displacement and Centers of Gravity of a Vessel may be
used for conducting stability test.
A stability test, in accordance with a procedure accepted by an ABS engineering office, is to be carried out in
protected waters, and in presence of and to the satisfaction of the attending Surveyor before commencement
of the sea trial. The Surveyor is then to attest to the satisfactory performance of the experiment in a report to
the ABS engineering office for evaluation.
For a subsequent drilling unit, in a series built from the same set of drawings of an inclined drilling unit, the
requirement for an Inclining Experiment may be waived, provided:
90
A weights and centers calculation is prepared, indicating the differences between the subsequent and
the inclined drilling unit, and
The calculated light ship properties are subsequently confirmed by a Lightweight Survey witnessed by
an ABS Surveyor and found to be within the limits specified in SOLAS Regulation II-1/B-1(5.2),
unless indicated otherwise by the Flag Administration. If the limits specified are exceeded, the Flag
Administration is to be contacted to determine the acceptability of such a deviation.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
7
1
9
Surveys
Surveys During Construction
Surveys at Builders Yard Sea Trial
7-1-9
Safety
Sea trial cannot be commenced in presence of an ABS Surveyor unless the Surveyor agrees with the builder
that suitable safety precautions are taken onboard the drilling unit. This may include but not limited to the
verification of following items by the attending Surveyor:
Posting of temporary fire control and safety plans to be used during the sea trial
Satisfactory condition and installation of life saving appliances for the sea trial personnel, particularly
if the number of personnel exceeds the drilling units Persons On Board (POB) capacity
An exemption to any of the above is the responsibility of the Coastal State Authority, and if an exemption
is issued, the written exemption is to be made readily available to the attending Surveyor for evaluation.
9.1
9.3
11
Sea Trial
During the sea trial, following tests is to demonstrate that each item of plant and the system as a whole is
satisfactory for drilling units service after construction:
11.1
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
91
Part
Chapter
Section
11.3
7
1
9
Surveys
Surveys During Construction
Surveys at Builders Yard Sea Trial
7-1-9
Ballast System
Ballast system is to operate satisfactorily throughout the sea trial period.
On column stabilized drilling units, ballast system is to be tested to demonstrate that it is capable of raising
the drilling unit, starting from a level trim condition at deepest normal operating draft, either a distance of
4.6 m (15 ft) or to the severe storm draft, whichever distance is greater, within three hours. The test is to
preferably follow the ballasting procedure that is to be provided to the drilling units operating personnel.
In addition, all controls and indication systems in the central ballast control station are to operate
satisfactorily throughout the sea trial period, particularly during the ballast test.
11.5
Bilge System
Bilge system is to operate satisfactorily throughout the sea trial period. Satisfactory operation of bilge
alarms and suction from bilge wells is to be verified during the trial by random activation/testing of the
system.
On column stabilized drilling units, two independent systems of high bilge water level detection, giving an
audible and visual alarm at the central ballast control station is to be demonstrated during the sea trial,
preferably when the drilling unit is operating under emergency power. High bilge water level audible and
visual alarm at the central ballast control station for propulsion rooms and pump rooms in lower hulls of
column-stabilized units are to be demonstrated during the trial.
11.7
11.9
Communication Facilities
Satisfactory operation of the interior communications system required by 4-3-2/15 is to be demonstrated to
the Surveyor during sea trials. Particular attention is to be given to demonstrating that the voice communication
systems required by 4-3-2/15 provide the capability of carrying on a conversation while the drilling unit is
being navigated.
92
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
7
1
9
Surveys
Surveys During Construction
Surveys at Builders Yard Sea Trial
7-1-9
In interior locations, 75 dB (A) and at least 20 dB (A) above the speech interference level
ii)
In exterior locations, 80 dB (A) and at least 15 dB (A) above the speech interference level
Particular attention is to be paid to machinery/working spaces where normal noise level is higher than
other areas of the drilling unit.
The GA system is to be clearly audible in all parts of the unit. The alarm is to continue to function after it
has been triggered until it is manually turned off or is temporarily interrupted by a message on the public
address system. The GA system is to operate satisfactorily throughout the sea trial period. Satisfactory
operation is to be verified during the trial by random activation/testing of the system. With the drilling unit
underway or in normal operating conditions, the minimum sound levels of the alarm is to be:
i)
The minimum sound levels for the emergency alarm tone in interior spaces are to be 80 dB and at
least 10 dB (A) above ambient noise levels existing during normal equipment operation in moderate
weather. In cabins without a loud speaker installation, an electrical alarm transducer is to be installed.
ii)
The sound levels at the sleeping position in cabins and in cabin bathrooms are to be at least 75 dB
(A) and at least 10 dB (A) above ambient noise levels.
93
Part
Chapter
Section
7
1
9
Surveys
Surveys During Construction
Surveys at Builders Yard Sea Trial
7-1-9
13
13.1
13.3
13.5
13.7
Dead-Ship Start
Restoring the propulsion system from a dead ship condition is to be demonstrated.
The emergency source of electrical power may be used to restore the propulsion, provided its capacity
either alone or combined with that of any other available source of electrical power is sufficient to provide
at the same time those services required to be supplied by 4-3-2/5.3.1 through 4-3-2/5.3.7.
The emergency source of electrical power and other means needed to restore the propulsion are to have a
capacity such that the necessary propulsion starting energy is available within 30 minutes of blackout, as
defined in 4-1-1/10.1. Emergency generator stored starting energy is not to be directly used for starting the
propulsion plant, the main source of electrical power and/or other essential auxiliaries (emergency
generator excluded).
13.9
Putting the rudder from 35 on one side to 35 on the other side with the vessel running ahead at
the maximum continuous rated shaft rpm and at the summer load waterline and, under the same
conditions, from 35 on either side to 30 on the other side in not more than 28 seconds; and
ii)
With one of the power units inoperative, putting the rudder from 15 on one side to 15 on the
other side in no more than 60 seconds with the vessel running ahead at the summer load waterline
at one half of the maximum ahead service speed or 7 knots, whichever is the greater.
The steering gear trial is to be performed with the rudder fully submerged. Where full rudder submergence
cannot be obtained in ballast conditions, alternative procedures for trials with less than full rudder submergence
are to be submitted for consideration.
94
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
7
1
9
Surveys
Surveys During Construction
Surveys at Builders Yard Sea Trial
7-1-9
i)
Changing the rudder position from 35 on either side to 30 on the other side in not more
than 28 seconds with the vessel running ahead at the maximum continuous rated shaft
rpm. For controllable pitch propellers, the propeller pitch is to be at the maximum design
pitch approved for the above maximum continuous ahead rated rpm.
ii)
Unless 7-1-9/13.9.2iii) is applicable, this test is to be carried out with all power units
intended for simultaneous operation for this condition under actual operating conditions.
i)
Changing the rudder position from 15 on either side to 15 on the other side in not more
than 60 seconds while running at one-half of the maximum ahead speed or 7 knots whichever
is the greater.
ii)
This test is to be conducted with either one of the power units used in 7-1-9/13.9.1ii) in
reserve.
iii)
Half Speed Trial may be waived where the steering gear consists of two identical power
units with each capable of meeting the requirements in 7-1-9/13.9.1i).
i)
For drilling units that are arranged with only one azimuthal thruster as the only means of
propulsion and steering, the thruster is to be provided with steering systems of a redundant
design such that a single failure in one system does not affect the other system.
ii)
For drilling units that are arranged with two azimuthal thrusters as the only means of
propulsion and steering, each thruster is to be provided with at least one steering system.
The steering system for each thruster is to be independent of the steering system for the
other thruster.
iii)
Each azimuthal thruster is to be capable of rotating at a speed of not less than 0.4 rpm
(from 35 degrees on either side to 30 degrees on the other side in not more than 28 seconds)
while steering the vessel with the vessel running ahead at the maximum continuous rated
shaft rpm and at the summer load waterline. Where the azimuthal thruster is arranged to
rotate for the crash stop or astern maneuver, the azimuthal thruster is to be capable of
rotating at the speed of not less than 2.0 rpm (180 degrees in not more than 15 seconds) to
account for the crash stop or astern maneuver.
i)
ii)
iii)
The steering gear controls, including transfer of control and local control
iv)
The means of communication between the navigation bridge, engine room and the steering
gear compartment
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
95
Part
Chapter
Section
7
1
9
Surveys
Surveys During Construction
Surveys at Builders Yard Sea Trial
7-1-9
v)
The alarms and indicators required by 4-3-4/15 of the Steel Vessel Rules (test may be
done at dockside)
vi)
The storage and recharging system in 4-3-4/9.3 of the Steel Vessel Rules (test may be
done at dockside)
vii)
The isolation of one power actuating system and time for regaining steering capability
(test may be done at dockside)
viii)
Where the steering gear is designed to avoid hydraulic locking (4-3-4/9.1.3 of the Steel
Vessel Rules), this feature is to be demonstrated.
ix)
Where practicable, simulation of a single failure in the hydraulic system, and demonstration
of the means provided to isolate it and the regaining of steering capability, as in 4-3-4/5.5
and 4-3-4/9.1.3 of the Steel Vessel Rules.
x)
The stopping of the steering gear before the rudder stop is reached, as in 4-3-4/5.11 of the
Steel Vessel Rules.
15
Anchoring/Mooring Trial
Where optional ABS symbols , or are requested, the drilling unit is to undergo trials to prove its
capability as applicable. For further details, see Appendix 7-1-A1 of these Rules.
15.1
15.3
96
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
17
7
1
9
Surveys
Surveys During Construction
Surveys at Builders Yard Sea Trial
7-1-9
17.1
17.3
DP Trials
A detailed DP trial program, that includes schedule of tests, is to be submitted for ABS review prior to the
proposed date of testing. The DP trial program is to be prepared to demonstrate the level of redundancy
established in FMEA, as applicable.
The test environment is to reflect the limiting design operating conditions, as far as practicable. The DP
trial is to be a complete performance test of the dynamic positioning system, and to at least include the
following testing/verification:
i)
The complete DP system is to be tested in all operation modes, with simulation of different failure
conditions to try switching modes, backup system and alarm system such as:
Verify manual changeover from automatic control system to back up automatic control computer
at emergency DP control station.
Computer program verification if single fault including loss of thruster or thruster group
(based on FMEA), sufficient thruster remains available in steady state and transient conditions.
ii)
iii)
iv)
If transient excursion occurs, submit analysis of worst case not to exceed distance endangering
safe operation of vessel (Operation Envelope).
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
97
PART
CHAPTER
APPENDIX
General
On self-propelled vessels, the symbol is required as a condition of classification and therefore it is a
mandatory to comply with the ABS Rules. On vessels that are not self-propelled (i.e., without the AMS
notation), the is an optional symbol that may be requested by the owner.
The symbols and are not required as a condition of classification. These are optional symbols that
may be requested by the owner.
All mooring equipment associated with below class symbols are to be fabricated and certified by ABS at
manufacturers facility. Installation of the mooring equipment/system is to be carried out in presence of
and to the satisfaction of the attending Surveyor. The mooring system is to be tested, per an agreed test
procedure, during sea trial of the unit.
1.1
1.3
1.5
98
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
7
Chapter 1
Appendix 1
Surveys
Survey During Construction
Mooring Equipment and Systems
7-1-A1
Mooring Trial
Mooring trial is to be carried out in accordance with ABS reviewed mooring trial test procedures, in
presence of and to the satisfaction of the attending Surveyor.
5.1
5.3
5.5
i)
Suitable equipment to indicate anchor line tensions, wind speed and direction at a manned
central control station.
ii)
iii)
Controls of each winch or windlass from a position which provides a good view of the
operation, and suitable equipment at each winch or windlass control positions to monitor
anchor line tension, winch or windlass power load, and to indicate the amount of anchor
line paid out.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
99
PART
CHAPTER
APPENDIX
General
This Appendix pertains to surveys and testing to be carried out on onboard computers for stability calculations.
As mentioned in 7-1-1/23, the use of onboard computers for stability calculations is not a requirement of
class, it is optional. However, if software is installed onboard for calculating stability of the unit, it is to be
surveyed and tested in presence of and to the satisfaction of the attending Surveyor.
Following subsections describe the requirements for survey of onboard computers. Satisfactory ABS design
review of the computer, in accordance with Appendix 3-3-A2 of the MODU Rules, is to be completed
before surveys are commenced onboard the unit.
Functional Requirements
3.1
Calculation Program
The calculation program is to present relevant parameters of each operating condition in order to assist the
Master in his judgment on whether the drilling unit is loaded within the approval limits. The following
parameters are to be presented for a given operating condition:
Deadweight data
Lightship data
Trim
Compliance with stability criteria: Listing of all calculated stability criteria, the limit values, the obtained
values and the conclusions (criteria fulfilled or not fulfilled)
If direct damage stability calculations are performed, the relevant damage cases according to the applicable
rules are to be pre-defined for automatic check of a given operating condition.
3.3
100
Computer Data/Indicators
The computer is to satisfy following requirements during operating condition.
3.3.1
Warning
A clear warning is to be given on screen and in hard copy printout if any of the operating limitations
are not complied with.
3.3.2
Data Printout
The data are to be presented on screen and in hard copy printout in a clear unambiguous manner.
3.3.3
Part
7
Chapter 1
Appendix 2
Surveys
Survey During Construction
Surveys of Computers for Stability Calculations
7-1-A2
3.3.4
Information of Program
Each hard copy printout is to include identification of the calculation program with version number.
3.3.5
Units
Units of measurement are to be clearly identified and used consistently within an operating calculation.
Operation Manual
An ABS reviewed operation manual is to be placed onboard the unit and verified by the Surveyor. The
operation manual is to contain descriptions and instructions, as appropriate, for at least the following:
i)
Installation
ii)
Function keys
iii)
Menu displays
iv)
v)
vi)
vii)
viii)
List of warnings
Installation Testing
To ensure correct working of the computer after the final or updated software has been installed, it is the
responsibility of the drilling units master to have test calculations carried out according to the following
pattern in the presence of the Surveyor:
i)
From the approved test conditions at least one load case (other than lightship) is to be calculated.
Note:
ii)
7.1
Actual operating condition results are not suitable for checking the correct working of the computer.
Retrieve the test load case and start a calculation run; compare the stability results with those in
the documentation.
ii)
Change several items of deadweight sufficiently to change the draft or displacement by at least
10%. The results are to be reviewed to ensure that they differ in a logical way from those of the
approved test condition.
iii)
Revise the above modified load condition to restore the initial test condition and compare the
results. The relevant input and output data of the approved test condition are to be replicated.
iv)
Alternatively, one or more test conditions shall be selected and the test calculations performed by
entering all deadweight data for each selected test condition into the program as if it were a
proposed loading. The results shall be verified as identical to the results in the approved copy of
the test conditions.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
101
PART
CHAPTER
CONTENTS
SECTION 1
Definitions .......................................................................................109
3.1
3.2
3.3
3.5
3.7
3.9
3.11
3.13
3.15
3.17
3.19
3.21
7.1
7.3
7.5
7.7
Alterations/Modifications .................................................................112
9.1
11
11.3
13
15
17
102
15.1
15.3
17.3
17.5
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
19
SECTION 2
SECTION 4
19.1
19.3
19.5
19.7
19.9
SECTION 3
1.1
1.3
1.5
1.7
1.9
1.11
1.13
1.3
1.5
1.7
1.1
1.3
1.5
1.7
3.3
3.5
3.7
TABLE 1
TABLE 2
TABLE 3
TABLE 4
Additional Alarms and Instruments for DPS-2 and DPS-3 ... 129
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
103
SECTION 5
11
13
104
1.1
1.3
1.5
1.7
1.9
1.11
1.13
3.3
3.5
3.7
5.3
5.5
5.7
7.3
7.5
7.7
9.3
9.5
11.3
11.5
11.7
13.3
13.5
13.7
13.9
13.11
13.13
13.15
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
15
SECTION 6
15.3
TABLE 1
TABLE 2
TABLE 3
FIGURE 1
CVI and NDT during SPS Hull No. 2 of Drillships ................. 135
FIGURE 2
CVI and NDT during SPS Hull No. 3 of Drillships ................. 136
FIGURE 3
CVI and NDT during SPS Hull No. 3 of CSDUs ................... 141
FIGURE 4
CVI and NDT during SPS Hull No. 4 of CSDUs ................... 142
FIGURE 5
FIGURE 6
1.1
1.3
1.5
1.7
1.9
3.3
3.5
3.7
3.9
3.11
TABLE 1
SECTION 7
SECTION 8
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
105
SECTION 9
1.3
1.5
1.7
3.1
3.3
3.5
106
3.1
3.3
3.5
3.7
3.9
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
5.3
5.5
5.7
11
13
1.1
Definitions.................................................................................... 175
1.3
1.5
3.3
3.5
General........................................................................................ 176
5.3
5.5
5.7
7.3
9.3
9.5
9.7
11.3
11.5
11.7
11.9
13.3
FIGURE 1
Definitions.................................................................................... 182
1.3
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
107
3.3
3.5
3.7
TABLE 1
108
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
PART
CHAPTER
SECTION
Application (2010)
1.1
Rules for Building and Classing Mobile Offshore Drilling Units (MODU Rules)
Guide for Automatic or Remote Control and Monitoring for Machinery and Systems (other than
Propulsion) on Offshore Installations
Certain requirements of the MODU Rules are based on the requirements of the ABS Rules for Building and
Classing Steel Vessels (Steel Vessel Rules).
Definitions (2010)
3.1
Ballast Tank
A Ballast Tank is a tank which is used primarily for the carriage of salt water ballast.
3.2
Reference is made to IMO MSC.1/Circ.1399 Guidelines on Procedures for In-Service Maintenance and Repair of
Coating Systems for Cargo Oil Tanks or Crude Oil Tankers, and the IACS Recommendation No.87 Guidelines
for Coating Maintenance & Repairs for Ballast Tanks and Combined Cargo/Ballast Tanks on Oil Tankers.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
109
Part
Chapter
Section
3.3
7
2
1
Surveys
Surveys After Construction
Conditions for Surveys After Construction
7-2-1
Corrosion
Active Corrosion means gradual chemical or electrochemical attack on a metal resulting from a reaction
with its environment and producing loose scale.
Allowable Corrosion or Wastage Limit is the acceptable corrosion limit for the MODUs structure in a
given area. Also known as Allowable Limit.
Excessive Corrosion is an extent of corrosion that exceeds the allowable limit.
Extensive Area of Corrosion is corrosion of hard and/or loose scale, including pitting, over 70% or more of
the plating surface in question, accompanied by evidence of thinning.
Grooving Corrosion is a localized, linear corrosion which occurs at structural intersections where water
collects or flows. This corrosion is sometimes referred to as in line pitting attack and can also occur on
vertical members and flush sides of bulkheads in way of flexing.
Localized Corrosion is by name local in nature and may be caused by local breakdown in coating from
contact damage, insufficient preparation, or at areas of stress concentration.
Overall Corrosion appears as a non-protective rust which can uniformly occur on tank internal surfaces
that are uncoated, or where coating has totally deteriorated. The rust scale continues to break off, exposing
fresh metal to corrosive attack. Thickness cannot be judged visually until excessive loss has occurred.
Pitting Corrosion is a localized corrosion of a metal surface that is confined to a small area and takes the
form of cavities called pits.
Substantial Corrosion is an extent of corrosion such that assessment of corrosion pattern indicates wastage
in excess of 75% of the allowable corrosion, but within the acceptable limits.
Weld Metal Corrosion is defined as preferential corrosion of weld deposit. The most likely reason for this
attack is galvanic action with the base metal which may start as pitting and often occurs on hand welds as
opposed to machine welds.
3.5
3.7
3.9
3.11
110
Surface-Type Units: Deck, bottom, side shell and longitudinal bulkhead plating and internal framing.
Column-Stabilized Units: Column and bracing plating and internals as deemed necessary. Deck sides
and bottom of lower hulls between columns, including internal stiffeners as deemed necessary.
Self-Elevating Units: Deck, bottom, side shell, internal framing of preload tanks and leg well structure.
Panel
Panel is the area between adjacent main frames from stiffener to stiffener.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
3.13
7
2
1
Surveys
Surveys After Construction
Conditions for Surveys After Construction
7-2-1
Survey (2014)
Overall Survey is a survey intended to report on the overall condition of the structure and to determine the
extent of additional close-up surveys. Overall Survey may be referred by the industry as General Visual
Inspection (GVI).
A Close-up Survey is a survey where the details of structural components are within close visual inspection
range of the Surveyor (i.e., normally within hand reach). Close-up Survey may be referred by the industry
as Close Visual Inspection (CVI). In general, a GVI carried out in spaces will be supplemented by CVI
of special or primary application structures, or identified structural critical areas. CVI may be accompanied
by surface or volumetric Nondestructive Testing (NDT), and/or hull thickness measurement. Areas showing
corrosion may also be subjected to CVI.
3.15
Representative Spaces/Tanks
Representative Spaces/Tanks are those which are expected to reflect the condition of other spaces of
similar type and service and with similar corrosion preventive systems. When selecting representative spaces,
account should be taken of the service and repair history onboard and identifiable critical and/or Suspect
Areas.
3.17
Spaces
Spaces are separate compartments including tanks, cofferdams, machinery spaces, voids and other internal
spaces.
3.19
Suspect Areas
Suspect Areas are locations showing substantial corrosion and/or are considered by the Surveyor to be
prone to rapid wastage.
3.21
7.1
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
111
Part
Chapter
Section
7.3
7
2
1
Surveys
Surveys After Construction
Conditions for Surveys After Construction
7-2-1
Repairs
Where repairs to hull, legs, columns or other structures, machinery or equipment, which affect or may
affect classification, are planned in advance to be carried out, a complete repair procedure, including the
extent of proposed repair and the need for Surveyors attendance, is to be submitted to and agreed upon by
ABS reasonably in advance. Failure to notify ABS in advance of the repairs may result in suspension of
the units classification until such time as the repair is redone or evidence submitted to satisfy the Surveyor
that the repair was properly carried out.
Note:
The above is not intended to include maintenance and overhaul to hull, other structures, machinery and
equipment in accordance with the recommended manufacturers procedures and established marine practice
and which does not require ABS approval. However, any repair as a result of such maintenance and
overhauls which affects or may affect classification is to be noted in the units log and submitted to the
Surveyor as required by 7-2-1/7.1.
7.5
Representation
Nothing contained in this section or in a rule or regulation of any government or other administration, or
the issuance of any report or certificate pursuant to this section or such a rule or regulation, is to be deemed
to enlarge upon the representations expressed in 1-1-1/1 through 1-1-1/7 of the ABS Rules for Conditions
of Classification Offshore Units and Structures (Part 1), and the issuance and use of any such reports or
certificates are to be governed in all respects by 1-1-1/1 through 1-1-1/7 of the above-referenced Part 1.
7.7
Alterations/Modifications (2012)
No alteration or modification which affect or may affect classification or the assignment of load lines are
to be made to the hull or machinery of a classed unit unless plans of the proposed alterations are submitted
and approved by the ABS Technical Office before the work of alteration or modification is commenced,
and such work, when approved, is to be carried out to the satisfaction of the Surveyor. Nothing contained
in this Section or in a rule or regulation of any government or other administration or the issuance of any
report or certificate pursuant to this section or such a rule or regulation is to be deemed to enlarge upon the
representations expressed in subsections 1-1-1/1 through 1-1-1/7 ABS Rules for Conditions of Classification
Offshore Units and Structures (Part 1) and the issuance and use of any such reports or certificates are to in
all respects be governed by subsections 1-1-1/1 through 1-1-1/7 of the above-referenced Part 1.
9.1
Application of Rules
As referenced in 1-1-3/1.3 of these Rules, the Rules that is applicable to the units classification is to be
applied to minor alteration/modification carried out on the unit, including its structure, machinery or equipment,
that affects or may affect classification. Application of up-to-date Rules will be specially considered only
when so requested by the Owner or required by these Rules.
The following cases may be considered as a major alteration or modification, and therefore require
compliance with up-to-date Rules for the section being altered or modified:
112
Changing a marine piping system (such as the ballast systems, bilge system, propulsion system, etc.)
with all of its components (piping, valves, pumps, etc.).
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
7
2
1
Surveys
Surveys After Construction
Conditions for Surveys After Construction
7-2-1
Changing a marine electrical system (such as the main power distribution, emergency power distribution,
electrical propulsion system, etc.) with all of its components (cabling, electrical motors/pumps, panels, etc.).
Changing layout and material used in the passive fire protection system, such as more than 10% of
deck area alteration or modification to the footprint of the accommodation deckhouse/superstructure or
its material used for fire protection.
Note:
Adding another deck on top of an existing accommodation deckhouse is not considered to be a major modification
of the entire deckhouse.
Changing an active fire protection system (such as the fixed-fire fighting system, fire and gas detection
system, etc.) with all of its components (piping, pumps, hoses, panels, alarms, detectors, etc.).
11
11.1
11.3
Special Materials
Welding or other fabrication performed on other steels of special characteristics or repairs or renewals of
such steel or adjacent to such steel is to be accomplished with procedures approved for the special
materials involved. The procedures are to be in accordance with the information provided under 7-1-2/25
and Chapter 4 of the ABS Rules for Materials and Welding (Part 2). Substitution of steels differing from
those originally installed is not to be made without approval.
13
15
15.1
15.3
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
113
Part
Chapter
Section
7
2
1
Surveys
Surveys After Construction
Conditions for Surveys After Construction
7-2-1
When applying for deductions, Owners are to provide details of out of service intervals since last credited
surveys. For drilling units operating in the Great Lakes, this does not include the normal winter lay-up
months of January, February, and March.
Note:
17
The above requirements apply to drilling units operating in fresh water such as in the Great Lakes, and Lake Maracaibo.
17.1
Operating Manual.
ii)
Drawings indicating locations of all Special, Primary and Secondary application structures
as defined in 3-1-4/5 of these Rules.
iii)
Drawings indicating all Critical Structural Areas as defined in 7-2-1/3.7 of these Rules.
iv)
Drawings showing all watertight boundaries and access/closing devices for such boundaries.
v)
Drawings showing the Fire Protection Systems, clearly indicating all fire rated boundaries and
access/closing arrangements for such boundaries, including location of fire dampers for A class
divisions.
vi)
Drawings showing the Fire Extinguishing Systems, clearly indicating layout of all fixed and portable
fire extinguishing systems. Minor changes to these drawings may be accepted and endorsed by the
attending Surveyor, however the endorsed copy of the drawings are to be submitted to ABS
engineering at earliest opportunity for record purposes.
vii)
Drawings showing layout of all Hazardous Areas, clearly indicating layout of different class
hazardous divisions together with access/closing/ventilation arrangements for such division boundaries,
the arrangement of ventilation shutdown and alarms (referenced in 7-1-6/21.19 of these Rules),
and a listing of Electrical Equipment in Hazardous Areas (referenced in 7-1-6/21.17 of these Rules).
viii)
ix)
Where the drilling unit is classed with a notation affecting its Automation System (such as ACC
or ACCU), Automation System Operating Manual.
x)
Where the drilling unit is classed with a DPS notation, the Dynamic Positioning System (DPS)
Manual and the Failure Modes and Effects Analysis (FMEA).
xi)
Where the drilling unit is classed with a CDS notation, drawings showing layout of the Drilling
Systems and associated Equipment, and a listing of all equipment and components of the classed
drilling systems.
xii)
Where the drilling unit is classed with optional HIMP Notation, the Owners Hull Inspection and
Maintenance Program (HIMP) used for hull inspection and maintenance purposes is to be available
onboard the drilling unit.
Minor changes to the drawings regarding fire protection systems, fire extinguishing systems, and listing of
electrical equipment in hazardous areas, may be accepted by the attending Surveyor and revised documents
endorsed to show Surveyors verification, however the endorsed copy of the drawings are to be submitted
to ABS engineering at earliest opportunity for record purposes.
114
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
17.3
17.5
7
2
1
Surveys
Surveys After Construction
Conditions for Surveys After Construction
7-2-1
Certificate of Classification issued or endorsed by Surveyor reflecting the full class designation
assigned to the drilling unit.
ii)
Documents issued or endorsed by the Surveyor supporting any additional class notation, such as:
CRC; UWILD, etc., applicable to the unit and reflected in the ABS Record.
iii)
iv)
ABS Certificates issued by Surveyor for anchoring gear such as the anchors, chains and/or wires,
and associated accessories (such as shackles, links, sockets, etc.) used for self-propelled drilling
units or installed on units with the symbol.
v)
ABS issued documents issued or endorsed supporting verification of mooring system equipment
installed on units classed with the or symbol.
vi)
Record of all Nondestructive Testing (NDT) of critical structural areas carried out during each
Drydocking Survey (or UWILD) or Special Periodical Survey of the Hull, reviewed and endorsed
by the Surveyor.
19
19.1
Safe Access
For surveys, means are to be provided to enable the attending Surveyor to examine the hull structure in a
safe and practical way. It is to be confirmed, as far as practicable, that means of access to all spaces are in
good/sound and safe condition when examining internal and external spaces.
19.1.1 Internal Examination
For surveys inside ballast tanks, deep voids, or other type deep spaces one or more of the following
means for access, acceptable to the attending Surveyor, is to be provided:
i)
ii)
iii)
iv)
Boats or rafts; or
v)
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
115
Part
Chapter
Section
7
2
1
Surveys
Surveys After Construction
Conditions for Surveys After Construction
7-2-1
i)
Permanent staging;
ii)
Temporary staging;
iii)
19.3
Deck crane used for handling the work basket is to be either ABS classed (CRC) or accepted
by ABS to be suitable for IMO MODU Code Certification of the drilling unit.
iv)
Work boats; or
v)
Surveys of tanks or applicable internal spaces by means of boats or rafts may only be undertaken
with the agreement of the Surveyor, who is to take into account the safety arrangements provided,
including weather forecasting and ship response under foreseeable conditions and provided the
expected rise of water within the tank does not exceed 0.25 m and the water level is stationary.
Note:
19.5
Reference is made to the IACS Recommendation 39 Guidelines for use of Boats or Rafts for Close-up
Surveys.
Housekeeping (Cleanliness)
In preparation for required surveys and to allow for a thorough examination by General Visual Inspection
(GVI), Close Visual Inspection (CVI), Nondestructive Testing (NDT), or Gauging, all spaces are to be
cleaned including removal from surfaces of all loose accumulated corrosion scale.
Spaces are to be sufficiently clean and free from water, scale, dirt, oil residues etc. to reveal corrosion,
deformation, fractures, damages or other structural deterioration. However, those areas of structure whose
renewal has already been decided by the Owner need only be cleaned and descaled to the extent necessary
to determine the limits of the areas to be renewed.
19.7
Conditions for entry into confined spaces are to at least satisfy ABS safety standards and are to be
to the satisfaction of the attending Surveyor.
116
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
19.9
7
2
1
Surveys
Surveys After Construction
Conditions for Surveys After Construction
7-2-1
Posting of temporary fire control and safety plans to be used during the sea trial/lightweight survey/
inclining experiment
Satisfactory condition and installation of life saving appliances for the sea trial/lightweight survey/inclining
experiment personnel, particularly if the number of personnel exceeds the drilling units Persons On
Board (POB) capacity
An exemption to any of the above is the responsibility of the Flag Administration and the Coastal State
Authority. If an exemption is issued, the written exemption is to be made readily available to the attending
Surveyor for evaluation.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
117
PART
CHAPTER
SECTION
1.1
Annual Surveys
Annual Surveys are to be made within three months before or after of each annual anniversary date of the
crediting of the previous Special Survey Hull, or original construction date. For units on Continuous
Survey, all Continuous Survey requirements for those parts (items) due are generally to be completed each
year. The Annual Survey will not be credited and the Certificate of Classification will not be endorsed
unless Continuous Survey items which are due or overdue at the time of the Annual Survey are either
completed or granted an extension.
1.3
1.5
118
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
7
2
2
Surveys
Surveys After Construction
Survey Intervals
7-2-2
Each part (item) surveyed becomes due again for survey approximately five years from the date of the
survey. For Continuous Surveys, a suitable notation will be entered in the Record and the date of completion
of the cycle published. If any defects are found during the survey, they are to be dealt with to the satisfaction
of the Surveyor.
At a survey approximately four years after each Continuous Survey of Hull has been credited, all
accessible thickness gaugings, as required for the forthcoming Special Periodical Survey, are to be taken.
1.7
1.9
Where a self-elevating drilling unit operating in salt water is unable to complete its Drydocking
Survey within a 60 month period and remained operating in the same drilling site without any rig
move, the unit will be considered a site-specific self-elevating mobile offshore unit and required to
comply with 3/3.7.8 of the ABS Rules for Building and Classing Offshore Installations.
1.11
The tail shaft is protected by a continuous metallic liner, or continuous cladding per
4-3-2/5.17.5 of the Steel Vessel Rules or fiberglass reinforced plastic coating between liners
installed according to approved procedure per 4-3-2/5.17.4 of the Steel Vessel Rules which
effectively prevents seawater from contacting the steel shaft, or which have shafts of
corrosion-resistant materials.
ii)
In addition to the propeller hub details given in the 4-3-2/Figure 1 of the Steel Vessel Rules,
the design includes other features that would further reduce stress concentration in the
propeller assembly.
119
Part
Chapter
Section
7
2
2
Surveys
Surveys After Construction
Survey Intervals
7-2-2
1.11.4(b) Extension up to One (1) Year. An extension up to one (1) year may be granted by the
Surveyor, when requested by the Owner, provided a survey is carried out in accordance with
7-5-1/5.1.2 of the ABS Rules for Survey After Construction (Part 7).
1.11.5 Extensions Oil-Lubricated Bearings
1.11.5(a) Extension up to Three (3) Months. An extension up to three (3) months may be granted
by the Surveyor, when requested by the Owner, provided a survey is carried out in accordance
with 7-5-1/5.3.1 of the ABS Rules for Survey After Construction (Part 7).
1.11.5(b) Extension up to One (1) Year. An extension up to one (1) year may be granted by the
Surveyor, when requested by the Owner, provided a survey is carried out in accordance with
7-5-1/5.3.2 of the ABS Rules for Survey After Construction (Part 7). An additional extension up to
one (1) year may be considered, when requested by the Owner, provided a survey is carried out at
the end of the first extension period, in accordance with 7-5-1/5.3.2 of the ABS Rules for Survey
After Construction (Part 7). No more than two (2) extensions may be granted.
1.11.5(c) Extensions not Exceeding Five (5) Years. In lieu of 7-2-2/1.11.4(b), an extension not
exceeding five (5) years may be granted by the Surveyor, when requested by the Owner, provided
a survey is carried out at the fifth year, in accordance with 7-5-1/5.3.3 of the ABS Rules for Survey
After Construction (Part 7). Consideration may be given to an additional extension not exceeding
five (5) years when requested by the Owner, provided a survey is carried out at the fifth year after
the first extension, in accordance with 7-5-1/5.3.3 of the ABS Rules for Survey After Construction
(Part 7). No more than two (2) extensions may be granted.
1.13
120
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
PART
CHAPTER
SECTION
1.1
1.3
1.5
Main particulars
Plans to include details of major brace and column connections on column-stabilized units and details
of leg and leg-to-spudcan connections
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
121
Part
Chapter
Section
1.7
7
2
3
Surveys
Surveys After Construction
Survey Pre-Planning
7-2-3
Former history available at Owners or ABS offices with respect to corrosion, cracking, buckling, indents
and repairs for the particular unit as well as similar units
Units service history since last survey (e.g., area of operation, environmental data, water depth, air gap
for SEDUs, length of time at each location etc.)
The degree of criticality should be judged and decided on the basis of recognized principles and practice, and
the units structural fatigue analyses if deemed necessary. ABS reviewed drawing showing all applicable
critical structural areas is to be available onboard, referenced during the pre-planning meeting and used
during applicable visual examination and NDT.
122
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
PART
CHAPTER
SECTION
Annual Surveys
1.1
Machinery casings and covers, companionways, and deckhouses protecting openings in freeboard
or enclosed-superstructure decks.
1.1.2
1.1.3
1.1.4
1.1.5
Closing Appliances
Closing appliances for all of the above, including hatch covers, doors, check valves together with
their respective securing devices, dogs, sills, coaming, and supports.
1.1.6
Freeing Ports
Freeing ports together with bars, shutters, and hinges.
1.1.7
1.1.8
Suspect Areas
Suspect areas of the hull are to be overall examined and gauged as considered necessary.
Suspect areas identified at a previous survey and which are readily accessible are to be subject to
overall examination and Close-up Survey. Similarly, any areas of Substantial Corrosion identified
at previous surveys and which are readily accessible are to have thickness measurements taken.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
123
Part
Chapter
Section
7
2
4
1.1.9
Surveys
Surveys After Construction
Annual Surveys
7-2-4
Corrosion
Where extensive areas of corrosion are found or when considered necessary by the Surveyor,
thickness measurements are to be carried out and renewals and/or repairs made when wastage exceeds
allowable margins.
Where Substantial Corrosion is found, additional thickness measurements are to be taken to confirm
the extent of substantial corrosion. These extended thickness measurements are to be carried out
before the annual survey is credited as completed.
1.1.10 Corrosion Control Systems
At each Annual Survey Hull, the Surveyors are to be satisfied that the type, location and extent
of the corrosion control system as well as its continuous effectiveness is in satisfactory condition.
Repairs or renewals should be reported on at each survey. Particular attention is to be given to
corrosion control systems in ballast tanks, free-flooding areas and other locations subjected to sea
water from both sides.
1.1.10(a) Performance Standards for Protective Coatings (PSPC) (2012). For units with optional
class notation CPS, survey after construction are to comply with Section 6 of the ABS Guide for
the Class Notation Coating Performance Standard (CPS). See 7-1-2/13.1.
1.1.11 Alterations and Position of Load Lines
At each Annual Survey Hull, the Surveyors are to be satisfied that no material alterations have
been made to the unit, its structural arrangements, subdivision, superstructure, fittings and closing
appliances upon which the load line assignment is based.
1.1.12 Construction Booklet (Construction Portfolio) (2012)
ABS reviewed and stamped Construction Booklet is to be available onboard the drilling unit for
Surveyors verification.
1.1.13 Operating Manual (2012)
ABS reviewed and stamped Operating Manual is to be available onboard the drilling unit for
Surveyors verification.
1.1.14 HIMP Notation (optional) (2012)
Owners Hull Inspection and Maintenance Program (HIMP) used for hull inspection and
maintenance purposes is to be available onboard the drilling unit.
1.1.15 Onboard Computers for Stability Calculations (2014)
This Subparagraph is applicable to Mobile Offshore Drilling Units that were contracted for
construction on or after 1 July 2005 that have Stability Computers onboard the unit. This
Subparagraph is not applicable to Drilling units that were fabricated prior to 1 July 2005 or to
those that do not have Stability Computers.
If an onboard computer is used for stability calculations, satisfactory operation of the software with
the onboard computer(s) for stability calculations is to be verified in presence of the Surveyor.
Satisfactory functional requirements (see 7-1-A2/3) are to be confirmed by the Surveyor.
A copy of the approved test conditions and the operation manual (see 7-1-A2/5) for the computer/
software are to be available onboard.
1.1.15(a) Testing. It is the responsibility of the drilling units master to check the accuracy of the
onboard computer for stability calculations at each Annual Survey by applying at least one
approved test condition.
The testing is to be carried out to verify initial installation testing conditions.
If the Surveyor is not present for the computer check, a copy of the test condition results obtained
by the computer check is to be retained onboard as documentation of satisfactory testing for the
Surveyors verification.
For further details, see Appendix 7-1-A2.
124
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
1.3
1.5
1.7
7
2
4
Surveys
Surveys After Construction
Annual Surveys
7-2-4
The hull and deck structure around the drilling well (moon pool) and in vicinity of any other structural
changes in section, slots, steps or openings in the deck or hull..
The back-up structure in way of structural members or sponsons connecting to the hull.
Columns, diagonals and other parts of the upper columns, diagonals and other parts of the upper hull
supporting structure as accessible above the waterline.
The upper hull structure around the drilling well (moon pool) and in vicinity of any other structural
changes-in section, slots, steps or openings in the upper hull structure.
3.1
3.3
3.5
3.7
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
125
Part
Chapter
Section
7
2
4
Surveys
Surveys After Construction
Annual Surveys
7-2-4
7.1
The APS notation signifies that the self-propelled vessel is fitted with athwartship thrusters intended to assist in
the maneuvering of the vessel. The PAS notation signifies that the non-self-propelled vessel is fitted with thrusters
intended to assist in maneuvering or propelling while under tow.
i)
ii)
iii)
Motor overload
iv)
Thruster RPM
v)
vi)
vii)
viii)
ix)
x)
7.1.2
7.1.3
126
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
7
2
4
Surveys
Surveys After Construction
Annual Surveys
7-2-4
At each Annual Survey of thrusters and Dynamic Positioning System (DPS), respective system and associated
machinery are to be generally examined, so far as can be seen, and placed in satisfactory condition. The
survey is also to include the following items, as applicable.
9.1
Operation of DPS
The vessel is to be operated for duration of at least two hours to demonstrate that the dynamic
positioning system has been maintained properly and is in good working order. The operational
testing is to be carried out to the Surveyors satisfaction. The tests are to demonstrate the level of
redundancy established by the FMEA (Failure Modes and Effects Analysis, see Subsection 2/11 of
the ABS Guide for Dynamic Positioning Systems). Special consideration may be given, subject to
the discretion of the Surveyor, when sufficient test reports are in place demonstrating that the
vessel has been engaged in a DP testing program.
In addition, the following items are to be generally examined so far as can be seen and placed in
satisfactory condition.
9.1.2
9.1.3
9.1.4
9.1.5
9.1.6
9.1.7
Manual Position Control System for DPS-1, DPS-2, and DPS-3 Notations
The operation of the manual position control system using one joystick on the Navigation Bridge
or DP control station in accordance with Subsection 5/7 of the ABS Guide for Dynamic Positioning
Systems and supplemented by an automatic heading control is to be confirmed to be functioning
satisfactorily.
9.1.8
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
127
Part
Chapter
Section
7
2
4
Surveys
Surveys After Construction
Annual Surveys
9.1.9
7-2-4
A means of voice communication between the DP control position (Navigation Bridge), the
engine control position and any operational control centers associated with DP is to be tested and
confirmed to be functioning satisfactorily.
Note:
No back up required.
It is to be verified that the failure modes and effects of any modifications or upgrades have been
considered and incorporated in the DPS operations manual.
TABLE 1
Thruster Power System (2016)
Alarm or Instrument
128
Alarm
Display
CPP pitch
Thruster RPM
Thruster direction
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
7
2
4
Surveys
Surveys After Construction
Annual Surveys
7-2-4
TABLE 2
Power Distribution System (2016)
Alarm
Display
Alarm or Instrument
TABLE 3
System Performance (2016)
Alarm
Display
Alarm or Instrument
TABLE 4
Additional Alarms and Instruments for DPS-2 and DPS-3 (2016)
Alarm or Instrument
Alarm
Display
X
Percentage thrust
--
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
129
PART
CHAPTER
SECTION
1.1
1.1.2
1.1.3
Watertight Integrity
Watertight integrity of tanks, bulkheads, hull, bulkhead deck and other compartments is to be verified
by GVI. Suspect areas may be required to be subjected to CVI, tested for tightness, nondestructive
tested or thickness gauged. Tanks and other normally-closed compartments are to be ventilated,
gas-freed and cleaned as necessary to expose damage and allow for a meaningful examination for
excessive wastage.
1.1.4
1.1.5
Hull Attachments
Hull attachments, as applicable, are to be examined by GVI. To supplement the GVI, CVI and/or
NDT may be required if deemed necessary by the attending Surveyor.
i)
130
Hull Attachments of Anchoring and Mooring System. Attachments of anchor racks, anchor
cable fairleads, and anchor windlasses are to be examined. For drilling units with ,
or Class Symbols, the anchors, chains, and cables and their respective handling means
are to be examined.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
7
2
5
1.1.6
Surveys
Surveys After Construction
Special Periodical Surveys
7-2-5
ii)
iii)
Hull Attachments of other Structures. Structures such as derrick substructure and supporting
structure, skid-base structure, jackhouses, pipe racks, deck houses, superstructures, helicopter
landing areas, raw water (seawater intake) towers and their respective attachments to the
deck or hull.
Where inspection of underwater joints is required, sufficient cleaning is to be carried out in way,
and water clarity to be adequate, to permit meaningful visual, video, camera or NDT examination,
as required. Every effort should be made to avoid cleaning damage to special coatings.
1.1.7
1.3
i)
For MODUs with or Class Symbols for Position Mooring; the Anchor and Mooring
Chains are to be examined and measured in accordance with the latest edition of API RP 2I
for the In-service Inspection of Mooring Hardware and Floating Structure.
ii)
For MODUs with the the Temporary Mooring Systems they are to be examined in
accordance with 7-3-2/5.1.4 of the ABS Rules for Survey After Construction (Part 7).
1.5
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
131
Part
Chapter
Section
7
2
5
Surveys
Surveys After Construction
Special Periodical Surveys
7-2-5
In any kind of survey (i.e., Special Periodical, Intermediate, Annual or other surveys having the scope of
the foregoing ones), NDT of structures in areas where CVI is required are to be carried out simultaneously
with CVI.
Where CVI and NDT are carried out in-water, proper two-way audio and video communication lines are to
be established and maintained, throughout the entire in-water inspection period, between the specialized
technician(s) and the attending Surveyor.
Results of NDT are to be maintained as a permanent record of the drilling unit, and be readily available to
the attending Surveyors during subsequent periodical surveys of the hull.
1.5.1
1.7
Record Keeping
The following is an outline of what is expected as far as documentation of the NDT results for
each survey:
i)
Details of the areas surveyed and type of NDT carried out (i.e., sketches showing details
of joints plus any internal back-up structure that is considered part of the structural joint).
ii)
The Owner shall keep a detailed record of what has been previously surveyed, the type of
survey carried out (Visual, MPI, etc.) (e.g., list area/quadrant of joint surveyed, nature and
extent of indication found, and how it was repaired).
Note:
Although it is not a mandatory requirement for Classification, Owners Inspection and Maintenance Manual
could have information on the type of steel used in the construction, as built welding procedures, sketches
of each joint to be surveyed and structural inspection NDT methods to be carried out, and may be used as
a document maintained onboard for Record Keeping. If the Owners Inspection and Maintenance Manual is
used for Record Keeping, it is to be reviewed and accepted by the attending Surveyor during survey preplanning and commencement of respective UWILD.
1.9
Corrosion Control
Where extensive areas of corrosion are found or when considered necessary by the Surveyor, thickness
measurements are to be carried out and renewals and/or repairs made when wastage exceeds allowable margins.
Where Substantial Corrosion is found, additional thickness measurements are to be taken to confirm the
extent of substantial corrosion. These extended thickness measurements are to be carried out before the
Special Periodical Survey is credited as completed.
132
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
7
2
5
Surveys
Surveys After Construction
Special Periodical Surveys
7-2-5
Suspect areas identified at a previous survey are to be subject to GVI and CVI. Similarly, any areas of
Substantial Corrosion identified at previous surveys are to have thickness measurements taken.
External thickness gauging may be required to confirm corrosion control.
1.11
Satisfactory operation of stability computer(s) fitted on drilling units contracted on or after 1 July 2005 is to be
verified onboard by the attending Surveyor and reported upon.
1.13
Alternatives (2016)
ABS is open to any alternative survey process as long as the standards required by class rules and applicable
statutory requirements/recommendations are satisfactorily complied with.
In order to monitor structural integrity of units, alternative means of visual examination, NDT techniques,
gauging techniques, verification of corrosion control programs, and proper recording of all these alternatives
by the use of special equipment or machinery installed onboard, will be considered on a case-by-case basis.
All alternative survey processes used during Special Periodical Surveys are to be reviewed and agreed
upon by the respective offshore ACS Office, well in advance of the survey pre-planning meeting to be held
with the attending Surveyor.
1.13.1 UWILD with ROVs
Requirements and guidance provided in 7-2-6/3.11.1 is applicable to UWILD associated with Special
Survey.
3.1
If found suspect or considered necessary by the Surveyor, CVI as well as NDT of special and/or
primary application structures may be carried out to extent deemed necessary by the Surveyor.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
133
Part
Chapter
Section
7
2
5
3.1.2
Surveys
Surveys After Construction
Special Periodical Surveys
7-2-5
If found suspect or considered necessary by the Surveyor, CVI of special application structures located
above the waterline and within amidships 0.4L may be carried out to extent deemed necessary by
the Surveyor.
3.1.3
Results of NDT are to be maintained as a permanent record of the drilling unit, and be readily
available to the attending Surveyors during subsequent periodical surveys of the hull.
3.1.4
Gauging reports completed by the ABS approved external specialists and endorsed by the Surveyor
are to be maintained as a permanent record of the drilling unit, and be readily available to the
attending Surveyors during subsequent periodical surveys of the hull.
3.1.5
Corrosion Control
If coating condition of special application structures is found to be in Poor condition, internal
surfaces of such structures are to be subjected to CVI and gauging to the extent deemed necessary
by the attending Surveyor.
Where gauging results indicate Substantial Corrosion and no immediate structural repair is carried
out before completion of this Special Periodical Survey, the corroded areas are to be subjected to
extensive GVI, CVI and Gauging, during subsequent Annual Surveys.
3.3
3.3.2
All four main deck moon pool corner plating is to be subjected to CVI. The CVI is to include
external surfaces as well as internal support members of these structures.
If found suspect or considered necessary by the Surveyor, CVI of special or primary application
structures located above the waterline and within amidships 0.4L may be carried out to extent
deemed necessary by the Surveyor.
As a visual guidance, 7-2-5/Figure 1 illustrates some of the typical special application structures
that may be subjected to CVI and NDT required by 7-2-5/3.3.
134
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
7
2
5
Surveys
Surveys After Construction
Special Periodical Surveys
7-2-5
FIGURE 1
CVI and NDT during SPS Hull No. 2 of Drillships (2014)
3.3.3
Weld joints of at least one representative corner main deck plating of such special application
structure is to be subjected to surface NDT.
If any defect found during the initial NDT or considered suspect by the attending Surveyor, NDT
may be extended to the internal members or other corners of the moon pool opening.
Results of all CVI and NDT are to be maintained as a permanent record of the drilling unit, and be
readily available to the attending Surveyors during subsequent periodical surveys of the hull.
3.3.4
3.3.5
Corrosion Control
If coating condition of special application structures is found to be in Poor condition, internal
surfaces of such structures are to be subjected to CVI and gauging to the extent deemed necessary
by the attending Surveyor.
Where gauging results indicate Substantial Corrosion and no immediate structural repair is
carried out before completion of this Special Periodical Survey, the corroded areas are to be
subjected to extensive GVI, CVI and Gauging, during subsequent Annual Surveys.
In addition, where gauging results indicate a global Substantial Corrosion and no immediate
structural repair is carried out before completion of this Special Periodical Survey, the Surveyor
may also require global strength analysis to be verified by ABS engineering before crediting the
Special Periodical Survey Hull.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
135
Part
Chapter
Section
3.5
7
2
5
Surveys
Surveys After Construction
Special Periodical Surveys
7-2-5
3.5.2
This CVI is to include external surfaces as well as internal support members of these structures.
If found suspect or considered necessary by the Surveyor, CVI of special or primary application
structures located within amidships 0.6L may be carried out to extent deemed necessary by the
Surveyor.
As a visual guidance, 7-2-5/Figure 2 illustrates some of the typical special and primary application
structures in way of amidships 0.4L that may be subjected to CVI and NDT required by 7-2-5/3.5.
FIGURE 2
CVI and NDT during SPS Hull No. 3 of Drillships (2014)
3.5.3
Weld joints of all corner main deck and bottom shell plating of such special application structure
is to be subjected to surface NDT. This NDT is to include internal special and primary members of
all four corners of the moon pool opening.
Results of all CVI and NDT are to be maintained as a permanent record of the drilling unit, and be
readily available to the attending Surveyors during subsequent periodical surveys of the hull.
136
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
3.7
7
2
5
Surveys
Surveys After Construction
Special Periodical Surveys
3.5.4
3.5.5
Corrosion Control
The requirements of 7-2-5/3.3.5 are to be complied with.
7-2-5
3.7.2
This CVI is to include external surfaces as well as internal support members of these structures.
3.7.3
Results of all CVI and NDT are to be maintained as a permanent record of the drilling unit, and be
readily available to the attending Surveyors during subsequent periodical surveys of the hull.
3.5.4
3.7.5
Corrosion Control
The requirements of 7-2-5/3.3.5 are to be complied with.
5.1
5.1.2
i)
ii)
iii)
Joints of supporting structure, including diagonals, braces and horizontals, together with
gussets and brackets
iv)
External surfaces of randomly selected areas of special application structures are to be subjected to
CVI. This random selection by the Surveyor is to at least include one typical connection of:
i)
ii)
iii)
A column to a bracing
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
137
Part
Chapter
Section
7
2
5
5.1.3
Surveys
Surveys After Construction
Special Periodical Surveys
7-2-5
iv)
Note:
Randomly selected area for CVI is to at least cover 10% of the overall length of the connection but not
less than 1 m in length.
Results of NDT are to be maintained as a permanent record of the drilling unit, and be readily
available to the attending Surveyors during subsequent periodical surveys of the hull.
5.1.4
Gauging reports completed by the ABS approved external specialists and endorsed by the Surveyor
are to be maintained as a permanent record of the drilling unit, and be readily available to the
attending Surveyors during subsequent periodical surveys of the hull.
5.1.5
Corrosion Control
If coating condition of special application structures is found to be in Poor condition, internal
surfaces of such structures are to be subjected to CVI and gauging to the extent deemed necessary
by the attending Surveyor.
Where gauging results indicate Substantial Corrosion and no immediate structural repair is carried
out before completion of this Special Periodical Survey, the corroded areas are to be subjected to
extensive GVI, CVI and Gauging, during subsequent Annual Surveys.
5.1.6
This verification is done by carrying out a lightweight survey (also referred as deadweight survey),
in presence of ABS, during Special Periodical Survey Hull No. 1. The lightweight survey is to
be carried out in accordance with ABS agreed survey procedure (see 3-3-1/3).
If the lightweight survey indicates a change from the light ship displacement shown in the Record and
in excess of 1% of the operating displacement of the drilling unit, an inclining experiment may have
to be carried out. In such cases, ABS Engineering shall be contacted to receive specific instructions.
During the lightweight survey, following verification and measurements are to be completed:
i)
Review of records to verify recorded weight changes that will affect lightweight of the
drilling unit;
ii)
Review of tank sounding readings done by tank level gauges (random manual sounding
may be done if required by ABS Surveyor to verify correctness of gauge readings);
iii)
Review of records to verify amount of liquids such as fuel oil, lube oil, waste oil, drilling
mud, drill water, etc. during the lightweight survey;
iv)
Review of units derrick loads on substructure (such as the hook load and setback loads);
v)
Review of other records showing weights other than the above affecting weight measurement;
vi)
vii)
viii)
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
5.3
7
2
5
Surveys
Surveys After Construction
Special Periodical Surveys
7-2-5
5.3.2
This CVI is to include external surfaces as well as internal support members of these structures,
and this random selection by the Surveyor is to at least include one typical connection of:
5.3.3
i)
Horizontal and diagonal bracing to columns and upper hull, together with gussets and brackets
ii)
Horizontal and diagonal bracing to pontoons, upper hull and columns, together with gussets
and brackets
iii)
iv)
v)
vi)
vii)
Note:
Randomly selected area for CVI is to at least cover 10% of the overall length of the connection but not
less than 1 m in length.
Results of NDT are to be maintained as a permanent record of the drilling unit, and be readily
available to the attending Surveyors during subsequent periodical surveys of the hull.
5.3.4
5.3.5
Corrosion Control
If coating condition of special application structures is found to be in Poor condition, internal
surfaces of such structures are to be subjected to CVI and gauging to the extent deemed necessary
by the attending Surveyor.
Where gauging results indicate Substantial Corrosion and no immediate structural repair is carried
out before completion of this Special Periodical Survey, the corroded areas are to be subjected to
extensive GVI, CVI and Gauging, during subsequent Annual Surveys.
In addition, where gauging results indicate a global Substantial Corrosion and no immediate
structural repair is carried out before completion of this Special Periodical Survey, the Surveyor
may also require global strength analysis to be verified by ABS engineering before crediting the
Special Periodical Survey Hull.
5.3.6
If the first lightweight survey carried out during SPS Hull No.1 demonstrated that the rig
personnel were satisfactorily maintaining an effective weight control program, a comprehensive
lightweight survey may be exempted during SPS Hull No. 2 and subsequent SPS Hull.
The above mentioned exemption may be granted by the ABS Surveyor only if a record of all
changes to units hull structure, machinery, outfitting and equipment that affect its light weight
value were properly maintained in a light ship data alterations log, and taken into account during
daily operations.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
139
Part
Chapter
Section
7
2
5
Surveys
Surveys After Construction
Special Periodical Surveys
7-2-5
Effectiveness of the weight control program may then be accepted based on review of onboard
records and observation of the units operating draft. This verification is done by carrying out a
weight verification survey.
Note:
If the weight verification survey indicates a change from the light ship displacement shown in the Record
and in excess of 1% of the operating displacement of the drilling unit, an inclining experiment may have
to be carried out. In such cases, ABS Engineering shall be contacted to receive specific instructions.
During the weight verification survey, following is to be carried out by the attending Surveyor:
5.5
i)
Review of records to verify recorded weight changes that will affect lightweight of the
drilling unit;
ii)
Review of tank sounding readings done by tank level gauges (random manual sounding
may be done if required by ABS Surveyor to verify correctness of gauge readings);
iii)
Review of records to verify amount of liquids such as fuel oil, lube oil, waste oil, drilling
mud, drill water, etc. during the lightweight survey;
iv)
Review of units derrick loads on substructure (such as the hook load and setback loads);
v)
Review of records showing weights other than the above affecting light weight measurement;
and
vi)
5.5.2
This CVI is to include external surfaces as well as internal support members of these structures.
Typical areas to be subjected to CVI are as follows:
i)
Horizontal and diagonal bracing to columns and upper hull, together with gussets and brackets
ii)
Horizontal and diagonal bracing to pontoons, upper hull and columns, together with gussets
and brackets
iii)
iv)
v)
vi)
vii)
Note:
As a visual guidance, 7-2-5/Figure 3 illustrates some of the typical areas in way of column-to-lower
hull, column-to-brace, and brace-to-brace connections that may be subjected to CVI and NDT
required by 7-2-5/5.5.
140
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
7
2
5
Surveys
Surveys After Construction
Special Periodical Surveys
7-2-5
FIGURE 3
CVI and NDT during SPS Hull No. 3 of CSDUs (2014)
5.5.3
Extensive NDT means that at least 50% weld length of each and every typical area examined by CVI is
to be subjected to NDT within a 5-year period. For example; randomly chosen 25% weld length of every
brace-to-brace connection examined by surface NDT twice in 5-year period will satisfy NDT of such areas.
Amount of CVI and NDT may be divided between two UWILDs carried out during each five year
cycle.
The number of joints and associated internal continuation and back-up structure, plus any gussets
or brackets that are to be subjected to NDT may be determined by the Owner and ABS with
consultation of the records and NDT results of previous surveys.
Results of NDT are to be maintained as a permanent record of the drilling unit, and be readily
available to the attending Surveyors during subsequent periodical surveys of the hull.
5.5.4
5.5.5
Corrosion Control
The requirements of 7-2-5/5.3.5 are to be complied with.
5.5.6
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
141
Part
Chapter
Section
5.7
7
2
5
Surveys
Surveys After Construction
Special Periodical Surveys
7-2-5
5.7.2
As a visual guidance, 7-2-5/Figure 4 illustrates some of the typical areas in way of column-to-lower
hull, column-to-brace, and brace-to-brace connections that may be subjected to CVI and NDT
required by 7-2-5/5.7.
FIGURE 4
CVI and NDT during SPS Hull No. 4 of CSDUs (2014)
5.7.3
Amount of CVI and NDT may be divided between two UWILDs carried out during each five year
cycle, preferably 50% done twice in a 5-year period.
The number of joints and associated internal continuation and back-up structure, plus any gussets
or brackets that are to be subjected to NDT may be determined by the Owner and ABS with
consultation of the records and NDT results of previous surveys.
Results of NDT are to be maintained as a permanent record of the drilling unit, and be readily
available to the attending Surveyors during subsequent periodical surveys of the hull.
142
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
7
2
5
Surveys
Surveys After Construction
Special Periodical Surveys
5.7.4
5.7.5
Corrosion Control
The requirements of 7-2-5/5.3.5 are to be complied with.
5.7.6
7-2-5
7.1
i)
ii)
Legs
iii)
All legs, including chords, braces, diagonals, gussets, racks, joints, together with leg
guides are to be examined.
On rigs with tubular or similar type legs, the legs are to be examined externally and
internally, together with internal stiffeners and pinholes, as applicable.
The extent of GVI may be limited to legs in way of the splash zone.
iv)
v)
vi)
Jetting piping systems or other external piping, particularly where penetrating mats or
spud cans.
Spud cans and other bottom spaces subject to contact with, or accumulation of, bottom
soil should be thoroughly ventilated and carefully monitored for pocketing or emission of
hazardous gases prior to, and during, internal inspection.
Where the spud cans or the mat is partly or entirely obscured below the mud line
when the Special Periodical Survey is otherwise being completed, consideration may
be given to postponement of these examinations until the next rig move.
7.1.2
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
143
Part
Chapter
Section
7
2
5
7.1.3
Surveys
Surveys After Construction
Special Periodical Surveys
7-2-5
Results of NDT are to be maintained as a permanent record of the drilling unit, and be readily
available to the attending Surveyors during subsequent periodical surveys of the hull.
7.1.4
Gauging reports completed by the ABS approved external specialists and endorsed by the Surveyor
are to be maintained as a permanent record of the drilling unit, and be readily available to the
attending Surveyors during subsequent periodical surveys of the hull.
7.1.5
Corrosion Control
If coating condition of special or primary application structures is found to be in Poor condition,
such structures are to be subjected to CVI and gauging to the extent deemed necessary by the
attending Surveyor.
Where gauging results indicate a global Substantial Corrosion and no immediate structural repair
is carried out before completion of this Special Periodical Survey, the corroded areas are to be
subjected to extensive GVI, CVI and Gauging, during subsequent Annual Surveys.
7.3
For the mat supported drilling units, alternative means of internal examination may be specially
considered on a case-by-case basis (see also 7-2-6/Table 1). Owners submitted alternative means
is to be reviewed and agreed upon by the respective offshore ACS Office before the survey commences
and the same is to be discussed during the pre-planning meeting held onboard.
7.3.2
The following is an outline of some of the areas that will be subjected to CVI:
i)
Leg-to-spudcan connections plus 2 bays (to extent deemed necessary by the Surveyor) of
leg above the top of the spudcan
ii)
Jackhouse/jackcase-to-deck connections
iii)
Brace-to-chord connection in areas of leg that have been predominately in way of the
upper and lower guides
Note:
iv)
Areas in way of the upper guides are to be examined and subjected to NDT to identify any
damage resultant from towing the drilling unit with its legs elevated. Areas in way of the lower
guides are to be examined and subjected to NDT to identify any damage as a consequence of
operating in the elevated/drilling mode.
Leg-to-mat connections
Note:
In general, these connections are considered to be Special Application Structures and are to
be treated accordingly. 100% of all leg-to-mat connections are to be subjected to CVI.
As a visual guidance, 7-2-5/Figure 5 illustrates some of the typical primary application structures
in way of leg-to-spud can connections that may be subjected to CVI and NDT required by 7-2-5/7.3.
144
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
7
2
5
Surveys
Surveys After Construction
Special Periodical Surveys
7-2-5
FIGURE 5
CVI and NDT during SPS Hull No. 2 of SEDUs (2014)
SPS #2
CVI and NDT may include areas in way of 2 bays above the leg-spudcan connection as
deemed necessary by the Surveyor.
CVI Surfaces are to be cleaned for a meaningful examination.
NDT To be examined by MPI or ACFM.
Port Leg
Fwd Leg
CVI
CVI
NDT
NDT
Stbd Leg
CVI
NDT
CVI
NDT
7.3.3
The following is an outline of some of the areas that will be subjected to CVI:
i)
Leg-to-spudcan connections plus 2 bays (to extent deemed necessary by the Surveyor) of
leg above the top of the spudcan
Note:
The number of leg joints and associated structure that is to be subjected to NDT is to be determined
by the Owner and ABS with consultation of the records and NDT results of previous surveys
and service history of the drilling unit. However, at least one such connection of each leg is to
be subjected to NDT.
ii)
Jackhouse/jackcase-to-deck connections
iii)
Brace-to-chord connection in areas of leg that have been predominately in way of the upper
and lower guides
Note:
iv)
Areas in way of the upper guides are to be examined and subjected to NDT to identify any
damage resultant from towing the drilling unit with its legs elevated. Areas in way of the lower
guides are to be examined and subjected to NDT to identify any damage as a consequence of
operating in the elevated/drilling mode.
Leg-to-mat connections
Note:
In general, these connections are considered to be Special Application Structures and are to
be treated accordingly. At least 25% of every leg-to-mat connections are to be subjected to NDT.
If any defect found during the initial NDT or considered suspect by the attending Surveyor, NDT
may be extended to other areas or leg joints.
Results of NDT are to be maintained as a permanent record of the drilling unit, and be readily
available to the attending Surveyors during subsequent periodical surveys of the hull.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
145
Part
Chapter
Section
7
2
5
Surveys
Surveys After Construction
Special Periodical Surveys
7-2-5
7.3.4
7.3.5
Corrosion Control
If coating condition of special application structures is found to be in Poor condition, internal
surfaces of such structures are to be subjected to CVI and gauging to the extent deemed necessary
by the attending Surveyor.
Where gauging results indicate Substantial Corrosion and no immediate structural repair is carried
out before completion of this Special Periodical Survey, the corroded areas are to be subjected to
extensive GVI, CVI and Gauging, during subsequent Annual Surveys.
In addition, where gauging results indicate a global Substantial Corrosion and no immediate
structural repair is carried out before completion of this Special Periodical Survey, the Surveyor
may also require global strength analysis to be verified by ABS engineering before crediting the
Special Periodical Survey Hull.
7.5
7.5.2
The following is an outline of some of the areas that will be subjected to CVI:
i)
Leg-to-spudcan connections plus 2 bays of leg above the top of the spudcan
Note:
All leg-to-spudcan connections plus 2 bays of leg above the top of the spudcan and associated
structure are to be subjected to 100% CVI.
ii)
Jackhouse/jackcase-to-deck connections
iii)
Brace-to-chord connection in areas of leg that have been predominately in way of the upper
and lower guides
Note:
iv)
Areas in way of the upper guides are to be examined and subjected to NDT to identify any
damage resultant from towing the drilling unit with its legs elevated. Areas in way of the lower
guides are to be examined and subjected to NDT to identify any damage as a consequence of
operating in the elevated/drilling mode.
Leg-to-mat connections
Note:
In general, these connections are considered to be Special Application Structures and are to
be treated accordingly. All leg-to-mat connections are to be subjected to 100% CVI.
As a visual guidance, 7-2-5/Figure 6 illustrates some of the typical primary application structures in
way of leg-to-spud can connections that may be subjected to CVI and NDT required by 7-2-5/7.5.
146
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
7
2
5
Surveys
Surveys After Construction
Special Periodical Surveys
7-2-5
FIGURE 6
CVI and NDT during SPS Hull No. 3 of SEDUs (2014)
SPS #3
CVI and NDT is to include areas in way of 2 bays above the leg-spudcan connections.
CVI Surfaces are to be cleaned for a meaningful examination.
NDT To be examined by MPI or ACFM.
Port Leg
Fwd Leg
CVI
CVI
NDT
NDT
NDT
Stbd Leg
NDT
CVI
CVI
All (100%) leg-spudcan
connections are to be
examined.
NDT
NDT
NDT
NDT
NDT
7.5.3
NDT
The following is an outline of some of the areas that will be subjected to CVI:
i)
Leg-to-spudcan connections plus 2 bays of leg above the top of the spudcan. Additional
bays may be subjected to NDT as deemed necessary by the attending Surveyor.
Note:
All leg-to-spudcan connections plus 2 bays of leg above the top of the spudcan and associated
structure are to be subjected to 100% NDT.
ii)
Jackhouse/jackcase-to-deck connections
iii)
Brace-to-chord connection in areas of leg that have been predominately in way of the upper
and lower guides
Note:
iv)
Areas in way of the upper guides are to be examined and subjected to NDT to identify any
damage resultant from towing the drilling unit with its legs elevated. Areas in way of the lower
guides are to be examined and subjected to NDT to identify any damage as a consequence of
operating in the elevated/drilling mode.
Leg-to-mat connections
Note:
In general, these connections are considered to be Special Application Structures and are to
be treated accordingly. Entire length of (100%) every leg-to-mat connections are to be subjected
to NDT.
If any defect found during the initial NDT or considered suspect by the attending Surveyor, NDT
may be extended to other areas or leg joints.
Results of NDT are to be maintained as a permanent record of the drilling unit, and be readily
available to the attending Surveyors during subsequent periodical surveys of the hull.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
147
Part
Chapter
Section
7.7
148
7
2
5
Surveys
Surveys After Construction
Special Periodical Surveys
7.5.4
7.5.5
Corrosion Control
The requirements of 7-2-5/7.3.5 are to be complied with.
7-2-5
7.7.2
7.7.3
7.7.4
7.7.5
Corrosion Control
The requirements of 7-2-5/7.3.5 are to be complied with.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
7
2
5
Surveys
Surveys After Construction
Special Periodical Surveys
7-2-5
TABLE 1
Thickness Gauging Requirements for Surface-Type Units (2012)
Special Periodical Survey
Number 1
1)
3)
3)
4)
5)
6)
7)
8)
9)
Notes:
1
2
3
With reference to ballasting history and arrangement and condition of coatings, tanks and specific thickness gauging
locations should be selected which will provide the best representative sampling of areas likely to be most exposed
to corrosion effect.
Gauging requirements noted may be modified as deemed necessary or appropriate by the Surveyor if the structure
remains effectively protected against corrosion by a permanent type special coating.
In any case where excessive wastage is evident, additional gaugings may be required.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
149
Part
Chapter
Section
7
2
5
Surveys
Surveys After Construction
Special Periodical Surveys
7-2-5
TABLE 2
Thickness Gauging Requirements for Column-Stabilized Units (2012)
Special Periodical Survey
Number 1
1)
2)
3)
3)
4)
5)
6)
3)
4)
5)
6)
7)
Notes:
1
2
3
4
5
150
With reference to the ballasting history and arrangement and condition of coatings, tanks and specific thickness
gauging locations should be selected which will provide the best representative sampling of areas likely to be most
exposed to corrosion effect.
Gauging requirements noted may be modified as deemed necessary or appropriate by the Surveyor if the structure
remains effectively protected against corrosion by a permanent type special coating.
In any case where excessive wastage is evident, additional gaugings may be required.
Structure application designations (special, primary, secondary) are defined in Section 3-1-4.
(2012) Splash Zone is to be considered as the structural area that has been periodically in and out of the water
when the unit was at its operating depth, most of the time during the past five-year period. Based on operational
record of the unit, additional zones may also be gauged.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
7
2
5
Surveys
Surveys After Construction
Special Periodical Surveys
7-2-5
TABLE 3
Thickness Gauging Requirements for Self-Elevating Units (2012)
Special Periodical Survey
Number 1
1)
4)
3)
4)
5)
3)
4)
5)
6)
Notes:
1
2
3
4
5
With reference to the operating history and arrangement and condition of coatings, specific thickness gauging locations
should be selected which will provide the best representative sampling of areas likely to be most exposed to corrosion
effect.
Gauging requirements noted may be modified as deemed necessary or appropriate by the Surveyor if the structure
remains effectively protected against corrosion by a permanent type special coating.
In any case where excessive wastage is evident, additional gaugings may be required.
Structural application designation (special, primary, secondary) are defined in Section 3-1-4.
(2012) Splash Zone is to be considered as the structural area that has been periodically in and out of the water when
the unit was at its operating depth, most of the time during the past five-year period. Based on operational record
of the unit, additional zones may also be gauged.
9.1
9.3
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
151
Part
Chapter
Section
7
2
5
Surveys
Surveys After Construction
Special Periodical Surveys
7-2-5
9.3.2
9.3.3
9.3.4
9.3.5
9.3.6
Pressure Vessels
Heat exchangers and other unfired pressure vessels (except those used solely for drilling operations
and complying with a recognized standard) with design pressures over 6.9 bar (7 kgf/cm2, 100 psi)
are to be examined, opened out or thickness gauged and pressure tested as considered necessary,
and associated relief valves proven operable. Evaporators that operate with a vacuum on the shell
need not be opened, but may be accepted on the basis of satisfactory external examination and
operational test or review of operating records
9.5
11
11.1
11.3
Parts to be Examined
11.3.1 Main Switchboards and Distribution Panels
Fittings and connections on main switchboards and distribution panels are to be examined, and
care is to be taken to see that no circuits are over fused.
11.3.2 Cables
Cables are to be examined as far as practicable without undue disturbance of fixtures.
11.3.3 Generator Run
All generators are to be run under load, either separately or in parallel; switches and circuit breakers
are to be tested.
152
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
7
2
5
Surveys
Surveys After Construction
Special Periodical Surveys
7-2-5
11.5
11.7
Major Repairs
On the occasion of major repairs, the coils repaired or renewed are to be subjected to a dielectric strain test,
as specified under the applicable parts of Part 4, Chapter 3. In addition, the circuits containing the repairs
or renewals and coils which have been disturbed during repairs are to be subjected to dielectric strain tests
for one minute by application of a potential of 125% of the maximum operating voltage of the circuits to
which it is applied. The direct current fields of generators and motors are to be subjected for one minute to
a test potential equal to 50% of the value specified under the applicable parts of Part 4, Chapter 3 and the
whole apparatus operated under full-load conditions.
13
13.1
13.3
Hazardous Areas
Hazardous areas, delineated in accordance with the onboard copy of the ABS approved hazardous area
plan, are to be examined. The onboard copy of the ABS approved listing of electrical equipment is to be
used for survey of hazardous areas. The following items are to be especially examined, tested as necessary,
and proven satisfactory:
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
153
Part
Chapter
Section
7
2
5
Surveys
Surveys After Construction
Special Periodical Surveys
7-2-5
Gas-tight doors and closures in boundary bulkheads or decks of hazardous areas, including those fitted
in air-lock passages.
Drains and scuppers from hazardous areas, and associated loop-seal traps where fitted.
Explosion-proof or intrinsically safe electric lighting, electrical fixtures and instrumentation, in particular
any associated sealing arrangements.
Purged electrical equipment, including visual and audible indication of loss of purge alarms or shutdowns.
Electric motors, including closed-loop ventilating systems for large motors. Automatic power disconnect
to motors in case of loss of ventilating air.
Ventilating systems, including ductwork, fans, inlets and outlets for enclosed restricted areas.
For Units built prior to 1996 that may not have an onboard copy of the ABS approved listing of electrical
equipment in hazardous areas, the equipment in the hazardous areas are to be examined to the satisfaction
of the attending Surveyor.
13.5
13.7
13.9
154
Structural fire protection system and protection of accommodation spaces, service spaces and control
stations. This examination is to verify that fire integrity of bulkheads and decks, all openings and access
through enclosed spaces, as well as closing devices, satisfactorily maintain original integrity of these
spaces and in accordance with approved design and construction.
Fire control plans are permanently exhibited for the guidance of operating personnel, showing clearly
for each deck provision, location, controls and particulars, as applicable, of the; fixed fire detection,
alarm and extinguishing systems, portable fire-fighting equipment and appliances, controls of fuel-oil
pumps and valves, ventilation system shut-downs and closing of openings, and locations and type of
fire retarding bulkheads. Where onboard conditions are found to have been modified, exhibited plans
are to reflect the onboard conditions, and fire control plans are to be submitted for review.
Fire main systems are to be examined and tested, as applicable, particularly to verify that; fire pumps,
including their relief valves (if fitted), fire main piping together with associated hydrants, hoses and
nozzles, and international shore connection remain in satisfactory condition. Pressure and operational
tests of the fire main system, as required by the Rules, are to be carried out.
Additional fixed fire fighting systems, such as those using gas smothering, foam, fixed pressure water
spraying, and systems protecting helicopter decks are to be examined and tested, and to be proven
satisfactory.
Portable and semi-portable fire extinguishers and sand (where provided) are to be examined, all portable
soda-acid and foam extinguishers are to be serviced, and all dry chemical and CO2 extinguishers are to
be weighed and recharged, as necessary, and proven satisfactory.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
7
2
5
Surveys
Surveys After Construction
Special Periodical Surveys
7-2-5
Firemans outfits, consisting of a breathing apparatus, a lifeline, a safety lamp, an axe, nonconductive
boots and gloves, a rigid helmet and protective clothing complying with the requirements of the Rules
are to be examined, and verified as to be easily accessible and ready for use, and stored in separate
positions so that a fire in one location would not block access to both outfits.
Fire detection system and its alarms, general alarms system, mud tank level alarms, ventilation system
alarms, and gas detection system and its alarms, are to be examined and tested, and proven satisfactory.
13.11 Outfitting
A general examination of following outfitting items is to be made in order that the Surveyor may be satisfied
as to its efficient state. The following items are to be especially proven in compliance with the Rules:
Means of escape
15
15.1
15.3
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
155
Part
Chapter
Section
7
2
5
Surveys
Surveys After Construction
Special Periodical Surveys
7-2-5
15.3.1 DP Thrusters
On units with DP system, component parts of oil-lubricated thrusters are to be opened for examination
at least every five years. Internal examination of oil-lubricated retractable thrusters may be waived
only if the thrusters are maintained under an ABS approved Condition Monitoring (CM) plan and
results recorded have proven satisfactory performance. Where the thrusters are maintained under
an ABS approved CM plan, the frequency for their major overhaul (including opening up thrusters
for internal examination) may be longer than five years, provided this is indicated in the CM plan.
156
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
PART
CHAPTER
SECTION
Parts to be Examined
1.1
1.3
Column-Stabilized Units
External surfaces of the upper hull or platform, footings, pontoons or lower hulls, underwater areas of
columns, bracing and their connections, as applicable, are to be selectively cleaned and examined.
Nondestructive testing may be required of areas found to be suspect.
Sea chests and strainers are to be cleaned and examined.
1.5
TABLE 1
Examination of Mat or Spud Cans during Drydocking Survey (2016)
Drydocking Survey
Type of Examination
1.
1.
External
2.
2.
3.
3.
External
4.
4.
5.
5.
Notes:
1
(2016) For mat supported drilling units, alternative means of internal examination may be specially
considered on a case-by-case basis (agreement by the respective offshore ACS Office is required).
Only if the mat or spud cans is readily accessible, and the attending Surveyor recommends doing so. If
there is a new indication of external damage on any can or mat, internal examination is to be carried out
to the extent recommended by the attending Surveyor.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
157
Part
Chapter
Section
7
2
6
Surveys
Surveys After Construction
Drydocking Surveys or Equivalent
7-2-6
The following is an outline of some of the areas that will be subjected to close visual and extensive NDT at
each UWILD not associated with Special Surveys:
i)
Leg-to-spudcan connections
ii)
Jackhouse/jackcase-to-deck connections
iii)
Brace-to-chord connection in areas of leg that have been predominately in way of the upper and
lower guides
Note:
iv)
Leg-to-mat connections
Note:
1.7
1.9
158
Areas in way of the upper guides are to be examined and subjected to NDT to identify any damage resultant
from towing the drilling unit with its legs elevated. Areas in way of the lower guides are to be examined
and subjected to NDT to identify any damage as a consequence of operating in the elevated/drilling mode.
In general, these connections are considered to be Special Application Structures and are to be treated
accordingly.
v)
Suspect areas
Note:
Spud cans and other bottom spaces subject to contact with, or accumulation of, bottom soil should be thoroughly
ventilated and carefully monitored for pocketing or emission of hazardous gases prior to, and during, internal inspection.
Where the spud cans or mat are partly or entirely obscured below the mud line when the UWILD is otherwise
being completed, consideration will be given to postponement of the underwater examination of the unit until the
next rig move.
Surface-Type Units
One peak tank and at least two other representative ballast tanks between the peak tank bulkheads
used primarily for water ballast.
1.7.2
Column-Stabilized Units
Representative ballast tanks in footings, lower hulls or free-flooding compartments as accessible,
and at least two ballast tanks in columns or upper hull, if applicable.
1.7.3
Self-Elevating Units
Representative ballast tanks or free-flooding compartments in mat or spud cans, if accessible, and
at least two representative upper hull salt water tanks on mat supported units or two representative
preload tanks on independent leg units.
All Units
1.9.1
1.9.2
Sea Valves
For Underwater Inspection in Lieu of Drydocking Survey associated with Special Surveys, means
are to be provided to permit the opening up of all sea valves for internal examination.
1.9.3
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
7
2
6
Surveys
Surveys After Construction
Drydocking Surveys or Equivalent
7-2-6
3.1
3.3
Conditions
3.1.1
Limitations
UWILD may not be acceptable where there is record of abnormal deterioration or damage to the
underwater structure, or where damage affecting the fitness of the unit is found during the course of
the survey.
3.1.2
3.1.3
3.1.4
Underwater Conditions
The areas to be surveyed are to be sufficiently clean and the sea water clear enough to permit
meaningful examination and photography (if necessary) by the diver. Overall or spot cleaning may
be required by the attending Surveyor.
Physical Features
The following physical features are to be incorporated into the units design in order to facilitate the underwater
inspection. When verified, they will be noted in the units Classification for reference at subsequent surveys.
3.3.1
Stern Bearing
For self-propelled units, means are to be provided for ascertaining that the seal assembly on oillubricated bearings is intact and for verifying that the clearance or wear-down of the stern bearing
is not excessive. For oil-lubricated bearings, this may only require accurate oil-loss-rate records
and a check of the oil for contamination by sea water or white metal. For wood or rubber bearings,
an opening in the top of the rope guard and a suitable gauge or wedge would be sufficient for checking
the clearance by a diver. For oil-lubricated metal stern bearings, wear-down may be checked by
external measurements between an exposed part of the seal unit and the stern tube bossing, or by
use of the units wear-down gauge, where the gauge wells are located outboard of the seals, or the
unit can be tipped. For use of the wear-down gauges, up-to-date records of the base depths are to
be maintained onboard. Whenever the stainless steel seal sleeve is renewed or machined, the base
readings for the wear-down gauge are to be re-established and noted in the units records and in
the survey report.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
159
Part
Chapter
Section
3.5
3.7
7
2
6
Surveys
Surveys After Construction
Drydocking Surveys or Equivalent
7-2-6
3.3.2
Rudder Bearings
For self-propelled units with rudders, means and access are to be provided for determining the
condition and clearance of the rudder bearings, and for verifying that all parts of the pintle and
gudgeon assemblies are intact and secure. This may require bolted access plates and a measuring
arrangement.
3.3.3
Sea Suctions
Means are to be provided to enable the diver to confirm that the sea suction openings are clear.
Hinged sea suction grids would facilitate this operation.
3.3.4
Sea Valves
Means must be provided to examine any sea valve for the UWILD associated with the Special Survey.
Procedures
3.5.1
Exposed Areas
An examination of the outside of the structure above the waterline is to be carried out by the Surveyor.
Means and access are to be provided to enable the Surveyor to accomplish visual inspection and
nondestructive testing, as necessary.
3.5.2
3.5.3
Damage Areas
Damage areas are to be photographed. Internal examination, measurements, marking and thickness
gauging of such locations may be a necessary adjunct as determined by the attending Surveyor.
Means are to be provided for locating, orienting and identifying underwater surfaces in photographs
or on video tapes.
3.9
160
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
3.11
7
2
6
Surveys
Surveys After Construction
Drydocking Surveys or Equivalent
7-2-6
Alternatives (2016)
ABS is prepared to consider alternatives to the above guidelines and would be pleased to consult with
interested clients concerning means and details for accomplishing results no less effective.
Requirements and guidance for the use of Remotely Operated Vehicle (ROV) during a UWILD are explained
in 7-2-6/3.11.1 and are considered part of a typical alternative procedure.
3.11.1 UWILD with ROVs
Provided the underwater conditions are suitable for a meaningful examination and the same is agreed
upon by the attending Surveyor, the General Visual Inspection (GVI) process of the UWILD can
be carried out by a ROV in lieu of divers.
However, if the attending Surveyor does not consider the visual examination by the ROV to be
equivalent to that by a diver, then the examination by a diver is to be carried out prior to the crediting
of the UWILD. If the ROV examination is not considered to be sufficient for determining the condition
of the hull, services of a diver are to be provided.
Following are typical disadvantages to be considered for use of ROV during UWILD.
Depending on the amount of marine growth on the hull, sufficient cleaning may not be possible
when only ROV is used.
Large size ROVs tend to have difficulty working at shallow water depths, due to swells and
excessive movement.
Not all ROVs are able to clean sea chest grids for a meaningful visual examination.
Not all ROVs are capable of properly recording the UWILD by photographic images or video.
Where the use of ROV was allowed by the attending Surveyor and underwater examination was
satisfactorily but partly carried out in way of accessible areas of the unit, remaining survey items
of the UWILD are to be carried out with a recognized diving company, in the presence of the
attending Surveyor.
Where Close Visual Inspection (CVI) is required during a UWILD, the use of ROV may be allowed
on a case-by-case basis.
The use of ROV for underwater Nondestructive Testing (NDT) and Gauging may be allowed only
when agreed upon by ABS on a case-by-case basis. In such cases, office of the respective offshore
Assistant Chief Surveyor is to be contacted by the owner to request agreement and instructions.
However, the use of ROV for underwater NDT and/or Gauging for crediting UWILD is to be also
agreed upon by the attending Surveyor.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
161
PART
CHAPTER
SECTION
162
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
PART
CHAPTER
SECTION
Surveys are to be carried out in accordance with applicable paragraphs of the latest edition of the ABS
Rules for Survey After Construction (Part 7), as applicable to vessels constructed in accordance with the
Steel Vessel Rules. However, due to low running hours on tail shafts of drilling units, the interval between
tail shaft surveys may be extended based on the following being to the satisfaction of the Surveyor:
i)
Divers external examination of stern bearing and outboard seal area, including weardown check
as far as is possible.
ii)
iii)
Confirmation of lubricating oil records (satisfactory oil loss rate, no evidence of unacceptable
contamination).
iv)
Shaft seal elements are examined/replaced in accordance with the seal manufacturers
recommendations.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
163
PART
CHAPTER
SECTION
Boiler Surveys
Parts to be Examined
1.1
1.3
1.5
1.7
164
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
PART
CHAPTER
SECTION
Annual Survey
At twelve month intervals from the date of installation, a survey is to be carried out during which a general
examination of the automatic and remote-control system is to be made. The examination is to be made with
a generator in operation and the control system energized to permit random checking of function indicators,
alarms and such control actuators as may be operational. The Surveyor is to examine the machinery records
to check the performance of the control system throughout the period since the last survey and to establish
if there has been any abnormal functioning or failures and what corrective measures had been taken to
preclude their recurrence. The machinery-space fire-detecting and bilge water-level alarms are to be checked
for performance.
3.1
Control Actuators
All mechanical, hydraulic, and pneumatic control actuators and their power systems are to be examined
and tested as considered necessary.
3.3
Electrical
The insulation resistance of the windings of electrical control motors or actuators is to be measured, with
all circuits of different voltages above ground being tested separately, and is to be on the order of one-half
to one megohm.
3.5
Unattended Plants
Control systems for unattended machinery spaces are to be subjected to dock trials at reduced power on the
propulsion engine to check the proper performance of all automatic functions, alarms, and safety systems.
Repairs or Alterations
Major repairs or alterations to the automatic and remote-control systems are to be made, in accordance
with approved plans, under the supervision and to the satisfaction of the Surveyor.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
165
PART
CHAPTER
SECTION
Annual Surveys
The following information is to be reviewed by the attending ABS Surveyor for issues that could affect the
MODU Habitability notation (HAB(MODU), HAB+(MODU), or HAB++(MODU)).
i)
Maintenance and Operations logs since the previous Initial, Annual or Special Periodical Survey,
if any
ii)
Fire, repair and damage reports since the previous Initial, Annual or Special Periodical Survey, if
any
iii)
A list of all structural or mechanical modifications to the drilling unit since the previous Initial,
Annual or Special Periodical Survey, if any
iv)
Verification that equipment and facilities continue to be fit for purpose and are operating in accordance
with the criteria stated within the ABS Guide for Crew Habitability on Mobile Offshore Drilling
Units (referred to as the Guide hereinafter)
During the attending ABS Surveyors review of the submitted information, a determination will be made
as to whether changes or alterations have taken place that could affect the MODU Habitability notation. As a
result, the drilling unit may be subject to the review, ambient environmental testing, and inspection requirements
of the Guide.
3.1
Survey Requirements
The Survey is to be comprised of ABS Engineering reviews, ABS Surveyor accommodation verifications,
and witnessing of ambient environmental testing. The Survey will cover all applicable habitability aspects.
The following is to be submitted to ABS three (3) months prior to carrying out the ambient environmental
testing:
166
i)
ii)
A list of all structural or mechanical modifications to the drilling unit since previous Annual Survey,
if any
iii)
iv)
v)
Copies of Test Plans and Test Reports resulting from Annual Surveys, if any
vi)
vii)
Proposed Special Periodical Survey Test Plans for the current survey.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
Chapter
Section
7 Surveys
2 Surveys After Construction
11 Crew Habitability
7-21
The Special Periodical Survey data submittal serves three purposes. The first is to perform an ABS Engineering
review of personnel spaces against any alterations to the drilling unit related to the criteria in Appendix 3
of the Guide since the Initial Survey, with measurements verified by an ABS Surveyor. The second purpose
is to provide a history of ambient environmental testing, as well as the Special Periodical Survey ambient
environmental Test Plans for review and approval by ABS Engineering. The third is to allow scheduling of
measurement verifications and ambient environmental testing by ABS Surveyor.
A Special Periodical Survey Test Plan for each ambient environmental aspect of Habitability is to be
submitted in accordance with the criteria stated below. The approved Initial Test Plans should be used as a
basis for creating the Special Periodical Survey Test Plans.
For creation of the Special Periodical Survey Test Plans, Subsection 6, Test Plan, and Subsection 7, Test
Requirements, of Section 3 through 6 of the Guide specify the requirements for each ambient environmental
aspect (i.e., 3/6, 3/7, 4/6, 4/7, etc.). For specifying measurement locations for the Special Periodical Survey
Test Plans, the following changes to 7.4.1, Selection of Spaces where Measurements are to be Conducted,
of each ambient environmental aspect of Habitability is to be followed:
i)
Measurements are to be taken in all areas affected by alterations, if any. Measurements are limited to
the ambient environmental aspect affected by the alteration. For example, structural changes require
both whole-body vibration and noise measurements. Structural changes do not necessarily require
indoor climate or lighting measurements. Changes to luminaires require lighting measurements but
not whole-body vibration, noise, or indoor climate measurements.
ii)
For all ambient environmental aspects, measurements are to be taken in all worst case or problem
area locations based on the requirements set forth in 7.4.1, Selection of Spaces where Measurements
are to be Conducted, of the appropriate Section of the Guide. [For example, worst case for wholebody vibration is described in 3/7.4.1i)].
iii)
For all ambient environmental aspects, measurements are to be taken in twenty-five (25) percent
of personnel cabins identified in the initial Test Plans. Any worst case locations can be considered
part of the representative sample for personnel cabins, if applicable.
iv)
For all ambient environmental aspects, measurements are to be taken where a single instance of one
(1) type of a manned space exists within the drilling unit (e.g., bridge, radio room, officers mess,
gymnasium, library, etc.). The worst case locations can be considered part of the single instance
representative sample, if applicable.
v)
Where multiple instances of the same type space exist, a representative sample of at least twenty-five
(25) percent of each type is to be selected for measurement for all ambient environmental aspects.
The worst case locations are to be considered part of the representative sample, if applicable.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
167
PART
CHAPTER
APPENDIX
1.1
168
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
PART
CHAPTER
APPENDIX
General
Where a portable module is installed onboard a drilling unit, it is to be subjected to survey in presence of
and to the satisfaction of the attending Surveyor. See 6-1-2/11.
The portable industrial module is free of any physical damage that may affect its strength and
effectiveness of its service.
ii)
Material used for flooring, ceiling, linings, etc. that is included in the interior of the portable industrial
module is in compliance with a similar standard as that applied to the main accommodation spaces
on the drilling unit.
iii)
The portable industrial module is secured onboard the deck by means of welding. Means of securing
other than welding may be accepted provided efficiency of tie downs are design reviewed by ABS.
iv)
Boundaries of the portable industrial module are constructed (and insulated where necessary) of
suitable material to withstand equal level of fire protection in the area where other service spaces
are installed. See Section 5-1-1.
v)
Access doors to and from the portable industrial module are of self-closing type, opening to the
outside, unobstructed by any means, without any hold-back device, and rated to withstand equal
level of fire protection of the module.
vi)
The portable industrial module is provided with suitable fire or smoke detection system.
vii)
The portable industrial module is provided with suitable number of general alarms bells. If the
external alarms of the general alarm and public address system are audible from inside the portable
industrial module during normal operation of the unit, installation of an internal system may be
waived.
viii)
The portable industrial module is to be maintained at overpressure relative to external areas. Ventilation
inlet(s) and outlet(s) are located in non-hazardous areas.
ix)
Piping of the portable industrial module is connected to the drilling units piping system(s), and
cross-connections do not affect the safety of the drilling unit. Under no circumstances, are drain
pipes of modules to be connected to any hazardous drain of the drill unit.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
169
Part
7
Chapter 2
Appendix 2
Surveys
Surveys After Construction
Survey of Portable Modules
7-2-A2
x)
The portable industrial module is located to provide easy and protected access to all escape routes
that lead to designated embarkation stations. The term easy and protected will be interpreted as
routes that provide protection from falling objects; heat from well fire; a walk path without any
structural, mechanical or electrical obstruction; and efficiently illuminated with main and emergency
power system.
xi)
All connections and/or penetrations on the portable industrial module for unit supplied piping and/or
electrical systems maintain the original integrity of the portable industrial module, and these
connections and/or penetrations are in compliance with a recognized standard.
xii)
Where the portable industrial module is located on the open deck of a surface unit and may be
subjected to wave impact loading, efficiency of the quarter is design reviewed by ABS.
xiii)
Where the portable industrial module is adjacent to hazardous areas and contains accommodation
spaces (such as an office), service spaces, or control stations an engineering evaluation of the fire
protection and blast resistance is to be carried out.
170
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
PART
Appendix 3: Modification of a Self-Elevating Drilling Unit to Become Site-Specific Fixed Offshore Installation
CHAPTER
APPENDIX
General
An existing self-elevating drilling unit (SEDU) may be modified to become a site-specific fixed offshore
unit and used for purposes of oil/gas production, storage or both. Depending upon the requested classification,
the modified unit may need to comply with one or more of the Rules/Guides listed under 7-2-A3/3.
Before ABS commences any work associated with the modification, the owner is to submit a signed
request for class for ABSs review and signing of the service agreement.
Application
One or more of the following Rules/Guides may be applicable to the modification:
3.1
Rules for Building and Classing Offshore Installations (Offshore Installation Rules)
This Rule is applied if the unit is modified to become a site-specific fixed offshore unit, without its hull
jacking system, marine systems, safety systems and any of the production/process and/or storage system
classed by ABS. Only the main hull structure is considered within ABS scope of service.
3.3
Rules for Building and Classing Mobile Offshore Drilling Units (MODU Rules)
This Rule is applied if the unit is modified to become a site-specific mobile offshore unit, without its
marine systems, safety systems and any of the production/process and/or storage system classed by ABS.
Only the main hull structure and its jacking system is considered within ABS scope of service.
3.5
Rules for Building and Classing Floating Production Installations (FPI Rules)
This Rule is applied if the units topside production/process system is also requested to be classed by ABS.
The safety systems, particularly suitability of electrical equipment in hazardous areas, fixed and portable
fire extinguishing systems, fire and gas detection systems, and fire protection system is to be in compliance
with this Rule.
3.7
Rules for Building and Classing Facilities on Offshore Installations (Facilities Rules)
This Rule is applied if the units topside production/process system is also requested to be classed by ABS.
The production/process systems are to be in compliance with this Rule.
3.9
Guide for Building and Classing Floating Offshore Liquefied Gas Terminals (FLGT
Guide)
This Guide is applied if the unit is modified to become a site-specific offshore LNG terminal.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
171
Part
7
Chapter 2
Appendix 3
Surveys
Surveys After Construction
Modification of a Self-Elevating Drilling Unit to Become Site-Specific Fixed Offshore
Installation
7-2-A3
Modification Survey
Modification survey is to be carried out as instructed by ABS and in accordance with ABS approved drawings.
In general, following applicable surveys are to be completed during the modification:
5.1
Hull
The SEDU is to be placed in a dry-dock (UWILD is not allowed) to carry out following hull surveys:
i)
Annual Survey Hull. Annual Survey Hull is to be carried out in accordance with 7-2-4/1 of
these Rules.
ii)
Drydocking Survey. Units hull is to be subjected to visual examination and NDT, as applicable
and in accordance with Section 7-2-6 of these Rules. Non-hull items associated with Annual Hull
Survey are not required.
iii)
Special Periodical Survey Hull. Units hull is to be subjected to visual examination, close-up
survey, extensive NDT, and gauging, as applicable and in accordance with Section 7-2-5 of these
Rules. Non-hull items associated with Special Periodical Survey are not required.
5.3
Jacking System
Where the unit is modified to become a fixed installation, and if none of its non-structural items are to be
classed, and if the jacking system is only to be used once during the initial jacking of the unit on site,
jacking system survey may be excluded from ABSs scope of classification work. Condition of the jacking
system, its capability of jacking and satisfactory operation will not be the responsibility of ABS.
5.5
5.7
Topside Systems
Where the unit is modified to become a fixed installation, and if its topside systems serving the entire
installation are requested to be classed by the Owner, ABSs scope of classification work is to include the
requested topside systems and compliance with applicable ABS Rules and/or Guides, as referenced in
Subsection 7-2-A3/3, is required.
Where topside systems are classed, compliance with 7-2-A3/5.5 is a prerequisite.
Recommended class designation will be in accordance with either the ABS Rules for Building and
Classing Offshore Installations (Offshore Installation Rules) or the ABS Guide for Building and Classing
Floating Offshore Liquefied Gas Terminals (FLGT Guide), as applicable.
A special note will be entered into ABS Record regarding the extent of services and the required Survey
After Construction.
172
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
PART
CHAPTER
APPENDIX
General
The intent of the ABS Preventative Maintenance Program (PMP) is for Owners to maintain their drilling
units with updated machinery maintenance practices, which may increase a units reliability and/or operational
availability, hence possible reduction in operational down-time. Properly executed PMP may also show
that major overhaul or replacement cycles machinery can be greater than five years, provided this is proven
by design criteria and satisfactory maintenance without premature failure.
Where specifically requested by the Owner, any machinery item that has rotating or mobile components
and is subjected to surveys after construction for maintenance of ABS classification of a unit, and its
working condition can be periodically monitored by suitable means and properly recorded may be enrolled
into ABS PMP.
Machinery components/items that have static components (not rotating or mobile components) and are
usually subjected to visual examination and/or testing by suitable means, and not covered under a
maintenance system, will be outside the scope of ABS PMP. Such machinery items will be subjected to
surveys after construction in accordance with applicable requirements of the MODU Rules.
While ABS PMP may be applied to machinery items that are within the scope of classification, operational
testing of all machinery items in accordance with applicable rules, is to be carried out during periodic class
surveys in presence of and to the satisfaction of the attending Surveyor.
Requirements of ABS PMP may not be applicable to machinery that is outside the scope of classification,
where specific periodic inspection and testing of such machinery is required to be carried out by ABS on
behalf of the drilling unit's flag State Administration.
Few explanatory examples are noted below:
ABS PMP will not be applicable to rule required visual examination and testing of static machinery
items/parts such as piping, valves, pressure vessels of any kind, electrical cables, etc.
Scope of ABS PMP will not be extended to the structural foundation/supports of the machinery that is
enrolled into ABS PMP.
A fire pump may be enrolled into ABS PMP, however annual operational/capacity testing of the
pump, as part of the fixed fire extinguishing system, is to be carried out in presence of ABS no matter
what the pump's maintenance records indicate.
Machinery items of an oily water separating system cannot be enrolled into ABS PMP since these
items are outside the scope of classification and subjected to MARPOL requirements.
Machinery items of any life-saving appliances (such as winches for lifeboats) cannot be enrolled into
ABS PMP since these items are outside the scope of classification and subjected to SOLAS and IMO
MODU Code requirements.
Rotating machinery items of lifting appliances (such as deck cranes) may be enrolled into ABS PMP
only if the lifting appliance is classed with the CRC notation.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
173
Part
7
Chapter 2
Appendix 4
Surveys
Surveys After Construction
Preventative Maintenance Program (PMP)
7-2-A4
Maintenance of machinery in accordance with ABS agreed PMP, can be based either on a Preventative
Maintenance (PM) plan or Condition Monitoring (CM) plan, or any combination thereof. A PM or CM
plans can also be developed based upon Reliability Centered Maintenance (RCM) process.
See 7-2-A4/Figure 1, which shows a typical configuration of machinery items enrolled into PMP while
remaining machinery are either not enrolled into PMP or to be surveyed without any maintenance program
and in accordance with applicable ABS rules.
Example:
Not all machinery on the drilling unit named WXYZ is classed per the applicable ABS Rules/Guides. The
owner decided to enroll some of the machinery items into PMP using PM and CM plans. PM for certain machinery
items were developed using RCM process. CM for certain machinery were also developed using RCM process.
The remaining classed machinery items will be surveyed either under SPS or CMS. The drilling unit will be
classed with the PMP notation and will also have an additional RCM notation for applicable systems.
FIGURE 1
Machinery Enrolled into PMP (2016)
While some of the machinery items may be surveyed under a PMP, maintenance of remaining machinery
items can continue to be surveyed either under ABS Special Periodical Survey (SPS) or Special Continuous
Survey, as selected by the Owner.
Note:
Special Continuous Survey of machinery is also referred as Continuous Machinery Survey (CMS). Where more
than half of the total numbers of machinery items are enrolled into PMP, ABS recommends remaining other
machinery to be surveyed under CMS.
A unit of any age may be eligible to enroll into PMP. An existing unit applying for entrance into the
program will be subject to ABSs review of the units records to ascertain the historical performance of the
machinery to be enrolled into maintenance plans under PMP, and provided there is no historical problem
related to the maintenance of the machinery, request for enrollment will be considered eligible.
PMP does not supersede the judgment of an ABS Surveyor, or waives attendance of ABS Surveyor(s) for
damage, or where attendance is required by the MODU Rules, as explained in subsequent sections of this
Appendix.
The reference to an ABS recognized condition monitoring company refers to those companies whom ABS
has identified as an external Recognized Specialist.
Note:
174
ABSs website http://www.eagle.org/ contains listing of ABS approved condition monitoring firms, which is
located under the Resources / Equipment & Supplier Listings / Recognized Specialists menu.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
7
Chapter 2
Appendix 4
1.1
Surveys
Surveys After Construction
Preventative Maintenance Program (PMP)
7-2-A4
Definitions
Machinery The term machinery used throughout this Appendix means any mechanical or electrical
equipment and/or machinery item that is part of a non-structural system. All machinery items required to
be surveyed to maintain classification of a drilling unit will be listed in ABS Survey Manager of each unit.
Note:
ABS Survey Manager Survey Status shows machinery items under the Parts List.
Preventative Maintenance Program (PMP) A program that consists of Planned Maintenance and/or
Condition Monitoring plans. PMP is only applicable to machinery that has moving/rotating parts and not to
static machinery parts such as electrical cables, piping, pressure vessels, switchboards, etc. Static machinery
parts that are not normally subjected to any preventative maintenance will be subjected periodic inspection,
as required by the MODU Rules, in presence of and to satisfaction of the attending Surveyor. PMP of a
machinery may or may not be supported by an ABS approved Reliability Centered Maintenance process.
Planned Maintenance (PM) A PMP with a maintenance plan that uses time-based inspection, part
replacement and/or overhauls in an effort to prevent machinery failures. Timing can be based on calendar
days, cycles counter or equipment running hours. Such schedules are generally established by the machinery
manufacturer or the owner, and normally include lubrication servicing; filter, bearing and seal replacements;
as well as major overhaul.
Condition Monitoring (CM) A PMP with a maintenance plan that uses various technologies to determine
the condition of equipment, at a specific moment in time, using minimal or non-invasive means. Common
tools used in condition monitoring are vibration analysis, oil analysis, ferrography, thermography, electric
current wave form analysis and boroscopic examination. Supplemental technologies, such as demodulation,
ultrasonic analysis, shock-pulse, spike-energy, HFD, etc., for CM of roller bearing element, may be used in
addition to vibration analysis. An advanced means of CM is Condition-based Maintenance (CbM), which
is defined below.
Condition-based Maintenance (CbM) This is a CM plan. However, CbM is conducted on a frequent or
real-time basis, to determine when part replacement or other corrective action is required. This process
involves establishing a baseline and operating parameters, then frequently monitoring the machine and
comparing any changes in operating conditions to the baseline. Repairs or replacement of parts are carried
out before the machinery fails based upon the use of the tools prescribed for CM.
Reliability Centered Maintenance (RCM) See 7-2-A5/1.1.
1.3
1.5
PMP Surveys
All machinery items covered by either a PM and/or CM plan will be surveyed in accordance with
the MODU Rules during Annual Surveys and Special Periodical or Special Continuous Surveys,
and requirements of this Appendix. Machinery not covered by PMP are to be surveyed in accordance
with Annual Survey and Special Periodical Survey requirements contained in previous sections of
Part 7, Chapter 2 of these Rules.
1.3.2
PMP Indicators
An individual classed machinery item listed in Survey Status of a unit that has enrolled into ABS
PMP will have PM, CM, or CbM indicator, as applicable.
Cancellation of PMP
The survey arrangement for equipment or machinery under the PMP may be cancelled by ABS if the program is
not being satisfactorily carried out, as a result of insufficient maintenance records, lack of knowledge by
the crew of the units program, the general condition of the equipment or machinery, or agreed intervals
between overhauls are exceeded resulting in the annual survey not being completed within the survey
window as required.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
175
Part
7
Chapter 2
Appendix 4
Surveys
Surveys After Construction
Preventative Maintenance Program (PMP)
7-2-A4
Sale, change of unit management, change of Recognized Specialists, or transfer of class is to be cause for
reconsideration of the approval. If more than one occurs, the current plan will be cancelled and a new plan
will be required for ABS approval.
The Owner may cancel the survey arrangement for equipment or machinery under the PMP by informing
ABS in writing. For this case, items which have been inspected under the program since the last Annual
Survey may be credited for class at the discretion of the Surveyor.
3.1
Surveys
Surveys related to the unit are to be up-to-date, without outstanding recommendations which would affect
the implementation of PMP. Where an outstanding recommendation exists, after satisfactory repairs have
been performed on the equipment or machinery, ABS attendance is required as part of the implementation
survey of PMP.
A unit with its equipment or machinery enrolled in the PMP can either be on a Special Periodical Survey
or Special Continuous Survey cycle. However, where majority (50% or more) of moving/rotating machinery
items are enrolled into PMP, all other remaining machinery is recommended to be surveyed under CMS.
Example:
3.3
Dynamic positioning thrusters of a Column Stabilized Drilling Unit (CSDU) can be enrolled into CM while the
units remaining machinery is on Special Periodical Survey.
For example, while ABS carries out PMP Annual Confirmation Survey and issues a class certificate valid for five
years, equipment or machinery enrolled into PMP may not require intrusive surveys every five years and follow
the frequency recommended in the maintenance program, which could be shorter or longer than five years.
3.5
Program Description
For general requirements, implementation, and other aspects of Planned Maintenance (PM) and Condition
Monitoring (CM) plans, refer to 7-2-A4/5.1 through 7-2-A4/5.7 below.
5.1
General
5.1.1
176
Enrollment into PM
To enroll equipment or machinery into PM, a comprehensive plan is to be submitted to the
attending Surveyor for review prior to conducting an implementation survey onboard the unit.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
7
Chapter 2
Appendix 4
5.1.2
5.3
5.5
5.7
Surveys
Surveys After Construction
Preventative Maintenance Program (PMP)
7-2-A4
Enrollment into CM
To enroll equipment or machinery into CM, the required documentation is to be submitted to the
responsible ABS Engineering for review, preferably prior to conducting an implementation survey
onboard the unit. The implementation survey can only be credited upon satisfactory completion of
review by ABS Engineering.
Implementation Surveys
Once the implementation survey is satisfactorily completed, a survey report confirming the implementation
of the PM and/or CM plan(s) will be issued by the attending ABS Surveyor, and the plan(s) may be put
into service.
5.3.1
Implementation of PM
The requirements for the implementation survey are provided in 7-2-A4/9.3 of these Rules.
5.3.2
Implementation of CM
The requirements for the implementation survey are provided in 7-2-A4/11.3 of these Rules.
Indicators for PM
When the implementation survey is satisfactorily completed, the attending Surveyor will inform
ABS regarding equipment or machinery items to be covered by a PM plan and to be shown by a
PM indicator in Survey Status.
5.5.2
Indicators for CM
When the implementation survey is satisfactorily completed, the attending Surveyor will inform
ABS regarding equipment or machinery items to be covered by a CM plan and to be shown by a
CM indicator in Survey Status.
7.1
Overhauls
For machinery enrolled into a CM plan, following an overhaul, new baseline data is to be recorded in the
presence of an ABS recognized condition monitoring company as soon as possible. Recording of the new
baseline data is to be done either before the next Annual Confirmation Survey or within six months, whichever
date is sooner, and is to be included in the Annual Report. Documentation on overhauls of machinery items
covered by PMP is to be reported and signed by the OIM, Chief Engineer or other authorized person(s).
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
177
Part
7
Chapter 2
Appendix 4
7.3
Surveys
Surveys After Construction
Preventative Maintenance Program (PMP)
7-2-A4
Damage Repairs
Any damage to equipment or machinery enrolled into ABS PMP is to be reported to ABS. If damaged
equipment or machinery is replaced, the new equipment or machinery is to meet the requirements of the
rules applicable to the unit. Any replacement or repair carried out due to damage is to be recorded and
same verified by the attending Surveyor.
Records of all damages, replacement and/or repairs are to be readily available and verified by the attending
Surveyor during Annual Surveys, unless ABS requires verification at earliest.
When there is an overdue outstanding recommendations or a record of unrepaired damage that affects PMP,
relevant items are to be removed from the program until the recommendation is satisfactorily rectified or
the repair carried out to the satisfaction of the attending Surveyor.
9.1
9.1.2
ii)
iii)
Visual examination and/or testing of components associated with fixed gas smothering
system.
iv)
Visual examination and/or testing of breathing apparatus, firemans outfits and the
international shore connection.
v)
Visual examination and/or testing of arrangements for remote safety shutdown system.
vi)
vii)
Visual examination and/or testing of components associated with the general alarm and
public address systems.
viii)
ix)
ii)
9.1.3
Anchoring and Mooring Systems (on units with respective ABS symbols and notations)
i)
Operational testing of temporary anchoring system on units classed with .
ii)
9.1.4
ii)
178
Part
7
Chapter 2
Appendix 4
9.1.5
Surveys
Surveys After Construction
Preventative Maintenance Program (PMP)
7-2-A4
Drilling System
Refer to the ABS Guide for the Classification of Drilling Systems.
9.3
9.5
9.7
11
11.1
ii)
iii)
Visual examination and/or testing of components associated with fixed gas smothering
system.
iv)
Visual examination and/or testing of breathing apparatus, firemans outfits and the
international shore connection.
v)
Visual examination and/or testing of arrangements for remote safety shutdown system.
vi)
vii)
Visual examination and/or testing of components associated with the general alarm and
public address systems.
viii)
ix)
ii)
179
Part
7
Chapter 2
Appendix 4
Surveys
Surveys After Construction
Preventative Maintenance Program (PMP)
7-2-A4
11.3
11.5
11.7
11.9
13
13.1
13.3
i)
A general examination of the machinery items enrolled into PMP is to be carried out.
ii)
The Surveyor is to review the owners annual report, and the required onboard documentation.
iii)
The performance and maintenance records are to be examined to verify that the machinery has
functioned satisfactorily since the previous survey or action has been taken in response to machinery
operating parameters which are outside acceptable tolerances and the overhaul intervals have been
maintained.
iv)
v)
The description of repairs carried out is to be reviewed. Any machinery part, which has been replaced
with a spare due to damage, is to be retained onboard, where possible, until examined by the attending
Surveyor.
vi)
At the discretion of the Surveyor, operational function tests, testing of safety devices and/or trips,
confirmatory surveys and random check readings, are to be carried out as far as practicable and
reasonable.
180
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
7
Chapter 2
Appendix 4
Surveys
Surveys After Construction
Preventative Maintenance Program (PMP)
7-2-A4
Any machinery that has acceptable operating conditions as per the approved CM plan may also be credited
to the current SPS or CMS cycle by the attending Surveyor after a satisfactory operational test.
13.3.1 Owners Annual Preventative Maintenance Report
At time of the Annual Confirmation Survey, the units qualified representative is to present to the
attending Surveyor, an Annual PMP report via hard copy or approved alternative electronic formats
containing the information detailed in 7-2-A4/9.5 (for PM plans), 7-2-A4/11.5 (for CM plans).
Owners report is to be reviewed by the attending Surveyor for completeness and reported
data/information. If the machinery included in the PMP has changed, this is to be stated in the
report.
Any machinery to be added to the program is subject to the requirements of 7-2-A4/9.5 (for PM
plans), 7-2-A4/11.5 (for CM plans) and approval by ABS.
While acceptance of additional machinery item(s) under PM plan can be done by the attending
Surveyor, acceptance of item(s) under CM plan is to be carried out by ABS Engineering and the
attending Surveyor.
Where machinery items are added to the PMP, ABS is to be advised and the units Survey Status
updated accordingly. When removing machinery from ABS PMP, ABS is to be advised and the
units Survey Status updated accordingly.
13.3.2 Alternative Electronic Formats
Owners may opt to submit their annual PMP reports in a portable electronic format (e.g., thumb
drive, CD-ROM, or e-mail attachment), for review prior to or at the time of attendance onboard.
Acceptable file types are those which are compatible with MS Word, MS Excel, and/or PDF.
These reports are to contain all the required information. In addition, the owners are required to
submit, annually, in hard copy, the following to the attending Surveyor:
i)
A letter stating that the annual report is on an alternative electronic format and meets the
requirements of ABS required format and file type.
ii)
A summation and results of the annual vibration signatures or oil analysis (for machinery
enrolled in a CM plan).
iii)
iv)
Directions on how to retrieve the report from the alternative electronic format.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
181
PART
CHAPTER
APPENDIX
General
By using RCM principles, maintenance is evaluated and applied in a rational manner. Functional failures
with the highest risk are identified and then focused on. Machinery items and their failure modes that will
cause high-risk functional failures are identified for further analyses. Maintenance tasks and maintenance
strategies that will reduce risk to acceptable levels are determined. Spare parts inventories are determined
based on the maintenance tasks developed and a risk assessment. An RCM sustainment procedure is
instituted to continually monitor and optimize maintenance. Accordingly, improved machinery and system
reliability can be expected.
Note:
1.1
Additional information and explanations on how to develop a RCM program can be found in the ABS Guide for
Survey Based on Reliability Centered Maintenance (RCM Survey Guide), and the ABS Guidance Notes on
Reliability Centered Maintenance (RCM Guidance Notes).
Definitions
Machinery The term machinery used throughout this Appendix means any mechanical or electrical
equipment and/or machinery item that is part of a non-structural system. All machinery items required to
be surveyed to maintain classification of a drilling unit will be listed in ABS Survey Manager of each unit.
Note:
ABS Survey Manager Survey Status shows machinery items under the Parts List.
Reliability Centered Maintenance (RCM) RCM is not defined as a PMP. RCM is a process that is used to
determine the most effective approach to maintenance. It involves identifying actions that when taken will
reduce the probability of failure and which actions are most cost effective. ABS has developed a maintenance
program which uses RCM analysis of installed equipment to develop a PMP, a spare parts holdings list and
includes a sustainment plan. Two different RCM maintenance strategies, the reactive maintenance and
one-time change are explained below.
Reactive Maintenance A RCM maintenance strategy in which machinery is run until failure before
corrective action is taken. This is useful for items which are low-cost and have no impact on operational,
environmental or safety concerns as a result of failure.
One-Time Change A RCM maintenance strategy in which machinery or systems, that have been determined
to present an unacceptable level of risk and have no potential mitigations, are replaced or significantly
altered in order to provide an acceptable level of risk.
1.3
182
RCM Analysis
A RCM analysis as defined by the RCM Guidance Notes will generate additional types of maintenance
tasks which are not previously defined by the Preventative Maintenance Program. In order to simplify the
RCM program plan approval process, implementation survey and annual surveys, the following groupings
of these tasks will be used to determine the applicable requirements:
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
Part
7
Chapter 2
Appendix 5
Surveys
Surveys After Construction
Reliability Centered Maintenance (RCM)
7-2-A5
TABLE 1
RCM Tasks (2016)
PM Type Tasks
CM Type Tasks
PM
CM
Failure finding
Combination of PM and CM
System specific RCM additional notations are recorded similar to how other class additional notations such as
CRC, etc., are recorded by ABS. However, they will not be part of the class designation indicated on the class
certificate of the vessel.
3.1
3.3
3.5
3.7
RCM Indicators
An individual classed machinery item listed in Survey Status of a unit that has enrolled into ABS PMP and
used the RCM process for developing its PM or CM plan will also have an RCM indicator.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016
183
Part
7
Chapter 2
Appendix 5
Surveys
Surveys After Construction
Reliability Centered Maintenance (RCM)
7-2-A5
184
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2016