Dear Elijah,: Comments For Shopping Mall, Mushin Mechanical Designs 17-05-2016
Dear Elijah,: Comments For Shopping Mall, Mushin Mechanical Designs 17-05-2016
Dear Elijah,: Comments For Shopping Mall, Mushin Mechanical Designs 17-05-2016
1) INCLUDE LEGEND & SCHEDULES TO DEFINE ALL SYMBOLS USED IN THE DRAWINGS
17-05-2016
6) ARCHITECT HAS INFORMED INTRODUCTION OF ROLLER SHUTTER DOORS. WHATS THE IMPLICATION
TO A/C PIPING.
8) PLS UPDATE MECH DWG WITH ATTACHED. DOING THE VIEW PORT AGAIN AS I HAVE CORRECTED
THE TITILE BLOCK
9) PLS NOTE THAT ELECT. RM HAS MOVE TO THE LEFT BECAUSE OF PROJECT PHASING AS INFORMED
BY THE ARCHITECT. (SEE ATTACHED RESERVATION SENT TO THEM) ADJUST FIRE FIGHTING
ACCORDINGLY.
ATTACHED IS THE DRAWINGS, U CAN USE MY TITLE BLOCK.( JUST COPY YOUR MECH DWG IN TO IT
AND ADJUST ALL ACCORDINGLY)
Thank you,
Olayinka