Testing of Arresters
Testing of Arresters
Testing of Arresters
The above tests are considered to be type tests (design tests) but some of these may also be
performed during the manufacturing process and/or assembly as a part of a manufacturers quality
assurance.
Testing of Surge Arresters
To ensure safe operation and an appropriate lifetime of surge arresters, type and routine tests are to
be performed. The most important standards covering type and routine testing of surge arresters are
IEC 60099-4 [1] and IEEE C62.11 [2]. While the type tests validate the general functionality of a surge
arrester design, the purpose of the routine tests is to ensure the quality of each individual arrester unit.
In the following the type and routine test as required by IEC 60099-4 are explained briefly.
Type tests (Design Tests)
The development of an arrester design generally ends with type tests. The type tests are also known
as design tests since the results of these tests validate a particular design. Surge arrester type tests
demonstrate the general ability of an arrester design to withstand the electrical, mechanical, thermal
and environmental stresses which might occur within the lifetime of a surge arrester. They are the
proof that the arrester construction is adequate to satisfy the requirements of the applicable standards.
These tests are performed once on a certain number of samples and are to be repeated when
significant changes of the arrester design and construction are introduced which cause changes to its
already proved characteristics. In such cases, only the affected tests need be repeated.
Routine tests
A surge arrester may contain a large number of ZnO blocks and if just one of these blocks fails
during an overvoltage the probability for a failure of the complete arrester is significant. The
failure rate for a single ZnO varistor, therefore, must be extremely small to obtain a high
reliability of the complete arrester. One way to guarantee a low failure rate is to routine-test all
manufactured varistors with an energy considerably exceeding the corresponding varistor energy at
the given rated energy for the arrester.
Surge arrester routine tests are performed on every single arrester unit in order to ensure the correct
manufacturing and assembly of the arrester. Thus, routine testing is an important part of the quality
assurance system of every manufacturer of surge arresters.
Acceptance tests:
Tests which are made, upon agreed between the manufacturer and the purchaser that the arresters or
representative samples of an order are to be tested. As per the standard the minimum number of
samples to be tested is equal to the nearest cube root of the number of samples to be supplied.
Impulse Current Generator Facility at CPRI
The Impulse Current Laboratory has been established in 1996 as a comprehensive test facility for
testing of Zinc Oxide elements and ZnO arrester pro-rated sections up to 11 kV rating as per IEC
60099-4 considering the importance of ZnO arresters which are being increasingly used by several
Utilities. Its superiority lies in the fact that, it has a unique Computer-controlled Impulse Current
Generator of rating 100 kA, 150 kJ incorporating all conceivable features in a single consolidated
design and is perhaps the only one of its kind in this part of the world at the time of its commissioning.
The generator has the capacity to generate 8/20 S lightning impulse current of 40kA magnitude, 4/10
S high current impulse of 120kA magnitude, 1/20 S steep impulse current of 40kA magnitude, 36/80
S switching impulse current of 2kA magnitude with a 36/90 S and long duration rectangular impulse
current with a maximum duration of 4000 S and a maximum magnitude of 1kA. The generator is
equipped with an advanced Dr. Strauss make impulse recording and analyzing system (TRAS 100-12,
4 channel, 100 MS/s, 12 bit) With this generator set up all type tests on ZnO arrester blocks up to 6 kV
voltage rating as per National (IS 3070) and International Standards (IEC 60099-4) can be carried out.
*
*
*
*
*
*
*
Lightning and switching impulse Residual Voltage tests on full arrester upto a
maximum of 10kA.
Reference Voltage, Power loss and Leakage current measurement on complete
arrester.
Bending moment test including moisture ingress test in addition to mechanical loads
Figure 1(c). General Circuit of a Current Generator for Rectangular current impulse .
Figure 1(d). Long duration current impulse generated by the above circuit.
The time T10 and T90 depends on the inductance and capacitance used in the circuit. These values are
adjusted to get the proper wave shape T90 2 ((n-1)/n)L/C.
Where L = total inductance, C= Total Capacitance.
Figure 1 (e) shows the generator facility at High Voltage division of CPRI, Bangalore.
based on residual voltage can be determined at a suitable lightning impulse current in the range 0.01
to 2 times the nominal discharge current which will be declared by the manufacturer. The maximum
residual voltage at a lightning impulse current used for routine tests shall be specified and published in
manufacturers data.
Procedure to measure residual voltage of the blocks:
All residual voltage tests shall be made on the same three samples of the complete arrester or arrester
sections. The time between discharges shall be sufficient to permit the samples to return to
approximately ambient temperature. There are three types of impulse residual voltage test:
1. Steep current impulse residual voltage test
2. Lightning impulse residual voltage test
3. Switching impulse residual voltage test
2.1.1 Lightning impulse residual voltage test:
Lightning current impulse: Current impulse with the wave shape 8/20 s. The virtual front time is 8
s and the time to half-value on the tail is 20 s. It represents the current rise time to crest of a surge
generated by a direct lightning strike on a transmission line.
One lightning current impulse of 8/20s wave shape with limits on the adjustment of equipment such
that the measured values are from 7s to 9s for the virtual front time and from 18s to 22s for the
time to half value on the tail, shall be applied to each of the three samples for each of the three peak
values of approximately 0.5, 1 and 2 times the nominal discharge current of the arrester.
The maximum values of the measured residual voltages shall be drawn in a residual voltage versus
discharge current curve. The residual voltage read on such a curve corresponding to the nominal
discharge current is defined as the lightning impulse protection level of the arrester.
The figure 2.1.1.1 below shows variation of measured residual voltage with respect to measured
lightning impulse current of 8/20 S wave. From this curve , the residual voltage at any current can be
read. Figure 2.1.1.2 shows the residual voltage and current waveforms recorded during the
measurement.
Figure 2.1.1.1 Graph showing the residual voltage vs lightning impulse current
TB2=100.00MS/s
No.3
0kA
CH1 Current
-1.0kA
-3.1kA
-5.2kA
No.: 7707
CH1
Eval.:
IC
Ip=
-10.4kA
T1=
8.44s
T2=
20.2s
CH2
Eval.:
Up=
-7.3kA
PK
11.8kV
-9.4kA
-10.4kA
20.0s
40.0s
60.0s
80.0s
100s
TB2=100.00MS/s
11.8kV
10.6kV
8.3kV
5.9kV
3.5kV
CH2 Res.Volt
1.2kV
0kV
20.0s
40.0s
60.0s
80.0s
100s
Fig 2.1.1.2 Oscillogram recorded during Lightning current impulse residual voltage test
TB2=100.00MS/s
No.16
-1.0kA
CH1 Current
-3.0kA
-5.1kA
No.: 7758
CH1
Eval.:
IC
Ip=
-10.114kA
T1=
1.0142s
T2=
17.678s
CH2
Eval.:
Up=
-7.1kA
PK
13.04kV
-9.1kA
-10.1kA
0
TB1=100.00MS/s
13.0kV
11.7kV
10.0s
20.0s
30.0s
TB2=100.00MS/s
9.1kV
CH2 Res.Volt
6.5kV
3.9kV
1.3kV
0kV
10.0s
20.0s
30.0s
No.1
0A
CH1 Current
-49A
-148A
-247A
No.: 7887
CH1
Eval.:
IC
Ip=
-494A
T1=
44.0s
T2=
105s
CH2
Eval.:
Up=
-346A
PK
8.72kV
-445A
-494A
50.0s
TB2=50.00MS/s
100s
150s
200s
250s
8.72kV
7.85kV
6.10kV
4.36kV
CH2 Res.Volt
2.62kV
0.87kV
0kV
50.0s
100s
150s
200s
250s
Fig 2.1.3 Oscillogram recorded during Switching current impulse residual voltage test
High current impulse : Peak value of discharge current having a 4/10 s impulse shape. The high
current impulse should reproduce the current through the arrester when lightning stroke occurs on
the line very close to the substation. It is used for arresters of the distribution and line discharge
class 1 not only for injecting energy before establishing thermal stability but also proves the
dielectric strength of the arrester block when a high current impulse of 100 kA is injected which
produces a high residual voltage.
transmission systems. Table 2.1.4 gives the duration of long duration current impulse for class 2 to
class 5 blocs as defined in the standard. The discharge currents during various switching operations
are found to be of short duration as compared to the normal power frequency cycle. The surge travel
time of the line is short compared to one power frequency cycle and it is assumed from the response
time of the gapped arresters that the switching currents are almost rectangular in shape and the
duration is around 2mS to 4mS depending upon the system voltage level and surge impedance. The
Figure 2.1.4.2 below shows the sequence of impulses applied during the test.
Figure 2.1.4.1 The energy requirement for testing class 1 to class 5 arrester blocks
Table 2.1.4
blocks
Test Procedure
The test shall be conducted on 3 samples. Before starting the test the residual voltage of the three
samples shall be measured at the nominal discharge current. After this, a set of long duration current
impulses as explained in the above paragraph is to be applied. After the application of the impulses,
the residual voltage measurement made before the test is to be repeated.
Test Evaluation: The samples are declared as pass if the change in residual voltage before and after
the test does not change by more than 5% and if there is no puncture or flashover of the blocks.
TB2=250.00KS/s
No.51
0A
CH1 Current
-15A
-46A
-76A
No.: 7978
CH1
Eval.:
RECT
Ip=
-152A
Td=
1.04E3s
Tt=
1.55E3s
tmin=
0.00s
tmax=
1.55E3s
CH2
Eval.:
Up=
-106A
-137A
PK
5.87kV
-152A
500s
1.00ms
1.50ms
2.00ms
TB2=250.00KS/s
5.87kV
5.28kV
4.11kV
2.94kV
1.76kV
0.59kV
0kV
CH2 Res.Volt
500s
1.00ms
1.50ms
2.00ms
Figure 2.1.4.3 Typical long duration current impulse recorded during the test.
2.5 Operating Duty test
AIM: To demonstrate the ability of the arrester to withstand maximum specified energy, (high current
energy for distribution, class 1 and switching surge energy for class 2 and above) followed by a
possible temporary overvoltage sequence and thereafter show thermal stability when energized at
Continuous Operating Voltage.
The sequence of impulses to be applied and the test procedure is demonstrated thorough the Figure
2.5.1 and 2.5.2 shown below. The typical voltage and current oscillograms recorded duringt he test
are shown in Fig. 2.5.3
Fig. 2.5.1 The sequence of impulses to be applied for the Switching Surge operating duty test
Fig. 2.5.2 The sequence of impulses to be applied for the High Current operating duty test
TB1=100.00MS/s
0kA
TB2=100.00MS/s
No.77
CH1 Current
-1.00kA
-3.00kA
-5.00kA
No.: 8429
CH1
Eval.:
IC
Ip=
-9.99kA
T1=
8.39s
T2=
20.2s
CH2
Eval.:
Up=
-6.99kA
PK
12.0kV
-8.99kA
-9.99kA
12.0kV
TB1=250.00KS/s
10.8kV
10.0s
TB3=50.00KS/s
20.0s
30.0s
8.4kV
6.0kV
CH2 Res.Volt
3.6kV
1.2kV
0kV
-36.8ms
100ms
284ms
468ms
653ms
arrester shall be able to withstand the various stresses and be thermally stable. In order to check
thermal stability of the arresters at the end of its life cycle, the standards specify conditioning of the
blocks by applying a series of lightning impulses and high current impulses before subjecting the
blocks to the energy stresses which may lead to the thermal instability of the blocks.
The arresters must be designed in such a way that the ZnO blocks will withstand the lightning impulse
energy and lightning current without failing dielectrically. Additionally the arrester must be able to
withstand the absorbed switching surge energy thermally, i.e., it must be able to cool and come back to
normal operating voltage condition without thermal un stability.
Thus the standard specifies the operating duty test to subject the arrester blocks to the sequence of
stresses it is subjected to in its real life service (as explained above) and check if its design is
adequate for withstanding these stresses without puncture, flashover or any unacceptable electrical
performance.
2.6 Temporary Over voltage (TOV) Test:
The purpose of the TOV test is to demonstrate the ability of the arrester to withstand maximum
specified energy, followed by a possible temporary overvoltage sequence and thereafter show thermal
stability energized at MCOV. The reason for this specified energy application is that it is quite likely that
an arrester in a substation will sustain a switching surge prior to an overvoltage event. In this test, the
TOV applied is a power-frequency overvoltage for time periods from 0,1 s to 3600 s. Manufacturers
published data shall include curves with abscissa scaled in time and ordinate in per unit of Ur. In
addition, the manufacturer shall publish a table of TOV values listed in per unit of Ur to three significant
digits, for times 0.1 s, 1 s, 10 s, 100 s, and 1000 s. Values shall be taken from the curves and shall
include data without prior duty and with prior duty. The published curve and table shall state the
range of arrester ratings for which they apply. The TOV value "with prior duty" and 10 s time duration
shall be at least equal to Ur.
2.7 Short Circuit / pressure relief Test
Purpose of Test:
To demonstrate the ability of an arrester, in the event of an overload (due to any reason causing
internal failure), to conduct the resulting system short-circuit current and also to verify that the short
circuit failure mode / pressure relief mechanism of surge arresters functions without violent shattering
of the arrester housing which may damage nearby equipment or injure personnel. After such an
operation, the arrester must be replaced. Figure 2.7.1 shows the pressure relief of a porcelain housed
arrester and Figure 2.7.2 shows the successful pressure relief test.
The system short-circuit current may be high or low depending on the system impedance and earthing
conditions. Hence short-circuit capability is verified at different current levels.
4 2009 amendment 2 Edition 2 has incorporated changes into the earlier simple static bending
moment test. The 1000 cycle specified continuous load test was introduces as an initial part of the
bending moment. Next the moisture ingress test which was earlier a separate test was introduced as
part of the bending moment test.
General definition of loads:
Specified long-term load, SSL
The specified short-term load SSL is the greatest force perpendicular to the longitudinal
axis of an arrester, allowed to be applied during service for short periods and for relatively
rare events (for example, short-circuit current loads or extreme wind guts) without
causing any mechanical damage to the arrester. The SSL is a load that the arrester could
be subjected to even after many years in service, which is taken into consideration by the
related type test procedure (the SSL test follows the SLL test).
Specified long-term load, SLL
The specified long-term load SLL is a force perpendicular to the longitudinal axis of an
arrester, allowed to be continuously applied during service without causing any
mechanical damage to the arrester. It can be given in terms of force (in N) or bending
moment (in Nm); where in the latter case the related force can be calculated by dividing
the bending moment value with the arrester length (in m). Short arresters, i.e. arresters
for system voltages not exceeding 52 kV, do not need to be type tested in a cyclic
manner but by a simple bending test. The same applies to porcelain-housed arresters in
general, where due to the fact that they are not deflected under mechanical loads a
simple bending test is considered sufficient as well.
Objective of the test: To verify that the arrester design will not decrease in performance under
thermo-mechanical and moisture conditions.
The bending moment test for polymer arresters consists of the following test sequence.
1.
For voltages >52kV
Subject all three samples to 1000 cycles of bending moment, each cycle comprising loading
from zero to specified long-term load (SLL) in one direction, followed by loading to SLL in the
opposite direction, then returning to zero load. The cyclic motion shall be approximately
sinusoidal in form, with a frequency in the range 0,01 Hz 0,5 Hz.
Subject two of the samples from step 1 bending moment test by applying Specified short
term load for 60 to 90 sec duration. Measure the deflection, release the load slowly. The
deflection shall be measured.
The third sample form step 1 shall be subjected to the specified long-term load (SLL) in four
directions and in thermal variations as described in Figures 2.8.1, 2.8.2 and 2.8.3 below.
All the three samples to be subjected to Water immersion test. The test samples shall be
kept immersed in a vessel, in boiling deionized water with 1 kg/m 3 of NaCl, for 42 h. At the
end of the boiling, the arrester shall remain in the vessel until the water cools to
approximately 50 C and shall be maintained in the water at this temperature until
verification tests can be performed. The arrester shall be removed from the water and cooled
to ambient temperature
2.
For Voltages < 52kV
The above test sequence applicable for voltages >52kV except the 1000 cycle test
In addition the following tests have to be carried out as a pre and post electrical checks to validate the
test results of bending moment.
Pre and Post electrical Checks:
- The residual voltage, (difference > 5%)
- Reference voltage measurement (difference > 2%)
- Seal leak check
- Partial discharge test (> 10 pc)
- Power loss measurement (difference >20%)
The applied static mechanical load shall be equal to SLL defined by the manufacturer. Its direction
changes every 24 h at any temperature in the transition from hot to cold, or from cold to hot, as defined
in Figure 2.8.1 and 2.8.2 and 2.8.3. The test may be interrupted for maintenance for a total duration of
4 h and restarted after interruption. The cycle then remains valid. Any residual deflection measured
from the initial no-load position shall be reported. The residual deflection shall be measured within 1
min to 10 min after the release of the load.
Fig.2.8.3 Test arrangement for the Thermo mechanical test and direction of the cantilever load
Bending moment test for porcelain arresters
It consists of the following steps
1. Determination of Mean Breaking load MBL
2. Application of SSL
Pre and post tests: Seal check and partial discharge test
Evaluation criteria:
- the mean value of breaking load, MBL, is 1,2 x SSL;
For SSL test
- there is no visible mechanical damage;
- the remaining permanent deflection is 3 mm or 10 % (whichever is greater) of maximum
deflection during the test;
- the test samples pass the leakage test
- the internal partial discharge level of the test samples >10pc
The flow chart of bending moment test procedure as given in IEC 60099-4 is given below for ready
reference.
duty test. Additionally a current time characteristic has to be given where the disconnector will
operate beyond a certain current at power frequency..
Considering the application of disconnectors for line arresters in transmission systems, and not only for
distribution arresters of LD class 1 or 2, additional tests may be needed. It might be necessary to
define two different classes for disconnectors, one for distribution systems, one for transmission
systems.
2.11 Seal leakage rate test
This type test provides information concerning the efficiency of the sealing system and is therefore
very sensitive. The gas and water tightness of the arrester units is essential for the reliability of an
arrester. This test demonstrates the gas/water tightness of the complete system. It applies to arresters
with polymer housings having seals and associated components essential for maintaining a controlled
atmosphere within the housing (arresters with enclosed gas volume and a separate sealing system).
The test shall be performed on one complete arrester unit. The internal parts may be omitted. If the
arrester contains units with differences in their sealing system, the test shall be performed on one unit
each, representing each different sealing system.
The acceptable methods are as follow:
a) Vacuum over water
b) Helium-mass spectrometer
c) Pressure or vacuum decay
d) Halogen detection
The arrester shall have passed the tests if the sample passes the leakage check before and after the
environmental test.
measurement performed before and after the test is satisfactory, i.e. the partial discharge level shall
not exceed 10 pC according to 10.8.11.
Weather ageing test for 5000Hrs:
To verify the ability of the arrester to withstand continuous salt fog conditions and endure
surface arcing and heating.
Test procedure: The surge arrester shall be subjected to various environmental stresses in a cyclic
manner while energized at UC for a period of 5000 hours. These stresses included solar radiation
simulation, artificial rain, dry heat, damp heat, high dampness at room temperature, and salt fog at low
concentration. The sample s shall undergo through various pre and post testing consisting of partial
discharge and reference voltage.
Test Evaluation: All samples met the test requirements if no housing punctures or housing erosion, no
internal breakdowns, no surface tracking is evident by physical examination, no over current trip out
occurs, the arrester reference voltage does not decrease by more than 5%, and the partial discharge
level does not exceed 10 pC.
3.0 Routine Tests
General
Routine tests are a limited number of tests that are to be performed on 100% of production. Although
not specifically stated as the purpose, they are intended to provide a degree of assurance that all
arresters supplied by a manufacturer will provide protective characteristics claimed in the
manufacturers literature, and that the arresters are suitable for application on systems whose line-toground voltage under normal conditions does not exceed the arresters MCOV. More than anything, the
tests provide reasonable assurance that arresters have been properly assembled, with the appropriate
amount of metal-oxide elements (verified by residual voltage test and power frequency test), without
internal assembly issues (verified by partial discharge test), and with sound sealing against moisture
ingress in service (verified by the seal test). In the case of arresters comprised of more than one
column in parallel, a current sharing test verifies that the columns share discharge current to within a
tolerance considered in the design stage. This is a critical test for such arresters because quite small
differences in the non-linear resistances of parallel columns can result in very large differences in the
apportioning of current between columns.
Routine are intended to detect faults in materials and workmanship and ascertain proper functioning of
the equipment. They shall be made on each individual piece of equipment.
3.1 Measurement of reference voltage :
The reference voltage is defined as the highest peak value independent of polarity of powerfrequency voltage, divided by the square root of 2, required to produce a resistive component
of current equal to the reference current of the arrester or arrester element. As an
approximation, the peak value of the reference voltage can be taken as per the standard as
the voltage at the instant of voltage peak where the capacitive current is zero and the current
is predominantly of resistive component. The reference current as defined as the peak value of
the resistive component of a power-frequency current high enough to make the effects of stray
capacitance of the arrester negligible. This current level shall be specified by the manufacturer.
The leakage current of the arrester is predominantly of capacitive in nature at the normal
power frequency voltage. As the applied voltage increases, the resistive component increases
and at reference current the arrester starts going into conduction mode thus increasing the
resistive current magnitude.
In the future the reference voltage will play a bigger role in arrester energy testing. The
upcoming editions of both IEC 60099-4 and IEEE C62.11 specify a pass/fail criteria based the
change in the reference voltage characteristic from before and after the impulse withstand
verification test.
-
Fig 3.1 below shows a typical reference voltage and current recorded during the measurement. The
first fig shows that the current is predominantly capacitive in nature at an applied voltage of 80% of the
rated voltage and second figure shows that the voltage is predominantly of resistive at reference
current. The oscillograms clearly indicate the change in current from purely capacitive at MCOV to
resistive at reference current.
One of the possible methods adopted makes use of the elasticity of the pressure relief membrane. As
shown in below, the pressure relief membrane lies flat in position 1 after assembly. However, if the
pressure around the arrester is decreased and kept constant, the pressure relief membrane will bend
upwards into position 2 forced by the constant internal pressure inside the arrester. If the arrester unit
is gas tight, the membrane will remain in position 2, if not, there will be a loss of pressure inside the
arrester and a relaxation of the membrane towards position 2 with time. In Figure 5 (right) the insertion
of an arrester unit into the test vessel can be seen.
Figure
Fig 3.2 Principle of leakage check (left) and test equipment (right)
witness testing can provide you a better understanding of your transformer's operation.
All surge arresters undergo two kinds of industry-standard tests, routine and Type / design, to ensure
that the surge arrester will perform as designed. Further optional tests explore the quality of the surge
arrester's construction, assurance, and adherence to standards. Some companys acceptance test
includes the Doble (Boston, Massachusetts, U.S.) watts-loss test, and a characterization of the
voltage-current (V-I) response of each unit in addition to regulat acceptance tests.
Factory acceptance test (FAT)- is carried out at Manufacturers Factory premises. The arrester be
acceptance tested upon delivery and prior to the supplier being paid.
Site acceptance test (SAT)- are carried out during commissioning/pre-commissioning at site.
Routine test - are intended to detect faults in materials and workmanship and ascertain proper
functioning of the equipment. They shall be made on each individual piece of\ equipment.
Type test - are intended to verify compliance of the design of given equipment with thi standard,
where applicable, and the relevant product standard.
Importance of witnessing Acceptance test: All new arresters are acceptance tested upon
delivery. An example of indicating the importance of this was for an order of 54 polymer-housed
station-class arresters for installation at system voltages of 115 kV, 138 kV and 230 kV executed
by a company in USA. The arresters originally passed acceptance tests, but several of them
failed the Doble watts-loss test on-site prior to energization (pre- commissioning test). The
problem was revealed to be moisture ingress due to a defective seal. The manufacturer replaced
the entire order with porcelain-housed units and addressed the cause of the vulnerability.
In another instance, an unusual number of polymer-housed distribution class arresters were
failing acceptance tests. These suspect units showed increased watts-losses, low voltages at the
1-mA resistive current and excessive partial discharge. The entire order was returned to the
manufacturer, which identified the cause of the failures as having been related to the assembly of
the units.
All arresters kept in stock for unplanned replacement purposes are tested every five years, while
salvaged station class arresters are re-acceptance tested and returned to stock.
Review the purpose of the tests and any associated procedures with the manufacturer's test
engineer prior to commencing the tests.
Discuss which tests are of particular importance so the manufacturer can give them extra
attention.
Allow sufficient time for tests. Some tests, such as operating duty test or long duration current
test may take few hours
Routine and /or sample test shall be carried out at the suppliers factory. Type tests shall be carried out
at an independent laboratory or shall be witnessed by a representative of an independent testing
laboratory or other representative acceptable to both parties.
When reviewing test results, limits are applied as specified in standards IEC 60099 and IEEE
C62.
5. Conclusions:
Testing of arrester basic manufacturing ZnO blocks design and the assembled arresters in the
laboratory by creating various stresses is very essential for a reliable protection performance.
6. References:
1.
IEC 60099-4, 2009 Edition 2 Standard Part 4 Metal Oxide Surge Arresters without gaps for
a.c. systems,
2.
3.
IEC 60099-5 Ed. 2.0: Surge arresters Part 5:Selection and application recommendations
4.
Design and Testing of Polymer Housed Surge arresters By Minoo Mobedjina Bengt
Johnnerfelt Lennart Stenstrm ABB Switchgear AB, Sweden
Arrester Facts 013 Understanding Arrester Discharge Voltage prepared by Jonathan
Woodworth Consulting Engineer Arrester Works