Procurement & Contract MGT
Procurement & Contract MGT
Procurement & Contract MGT
1. Defining a Contract
2. Contract Type
3. Contract Framework
4. Contract Preparation
5. Contract Award
6. Contract Administration
7. Contract Management Best Practice
Defining a Contract
Contract is a binding agreement between two or
more parties to perform or not to perform a task /
affair
A binding agreement is legally enforceable by governing Law. A
contract must exhibit clearly the OFFER, ACCEPTANCE and the
CONSIDERATION
Elements of a Contract
Following is the list of six conditions that must be fulfilled by the
contracting parties to ensure a formation of a legally binding
contract.
1. An Agreement
2. Competent Multiple parties (two or more)
3. Genuine consent / assent of the contracting parties
4. Supported by the Consideration
5. A legal objective / goal
6. In form required by the applicable law
There must be an agreement. The contracting parties must be
competent in getting into an agreement. Every party must
possess required mental capacity (i.e. not mentally impaired),
Every party must possess legal capacity (i.e. not children). The
objective that has planned to be achieved / the commodity to be
procured through the contract must be legal (i.e. must not be
marked to be illegal by the governing law, or terrorism, drugs
etc.). Every party must display genuine consent of getting into
the contract. (I.e. no party has been forced into the contract by
blackmailing etc.). The contract should be supported by the
consideration. The consideration must be of a fair value to the
receiving party.
The contract must clearly define the rights and obligation of
the parties to the contract.
It is NOT necessary for parties to have negotiations prior to
getting into a contract (E.g. There are non-negotiable
contracts like EULAs of software vendors etc.)
It is NOT necessary to have the contract in written form.
However, there are contracting situations where it is
required to have the contract in written form (E.g. Land
Dales, Copy Right etc.) Handshake would be enough to
form a contract.
If a written document is there, the written document is NOT
necessarily required to be consistent with parties
negotiations
If a written document is there, the parties should NOT
necessarily have read and understood it.
A signature is NOT necessarily be in the place
It does NOT matter whether the terms and conditions of the
contract are fair and reasonable.
A Contract is NOT necessarily be reviewed and approved by
a Lawyer / Attorney. However if you can have an attorney, it
would be nice.
The Metaphor
The parties
beneficiaries
are mentioned,
(if any)
3rd
What?
party
Where?
When?
Why?
How?
How
much?
What if?
Procurement route
Contents
1) Construction management
2) Custom build
3) Design and build
4) Design build finance and operate (PPP / PFI / DBO / BOOT)
5) Emerging cost contracts
6) Engineering procurement and construction contract (EPC) / turnkey contract
7) Engineering procurement and construction management contract (EPCM)
8) Fast-track construction
9) Furniture, fixtures and equipment (FF&E)
10)
Framework agreements
11)
12)
13)
Management contract.
14)
15)
16)
Partnering
17)
18)
19)
Public procurement
20)
21)
Self-build
22)
Single-stage tender
23)
24)
Two-stage tender
Introduction
Procurement is the process of purchasing goods or services.
There are many different routes by which the design and
construction of a building can be procured. The selected
procurement route should follow a strategy, which fits the
long-term objectives of the client's business plan.
When determining the appropriate procurement route, following
are considered:
Speed
Cost
Quality
Risk
Asset ownership
Financing
Construction management
Construction management is a procurement route in which the works are
constructed by a number of different trade contractors. These trade contractors are
contracted to the client but managed by a construction manager. The construction
manager, acts as an agent for the client, administering and co-ordinating the works
contracts.
The construction manager is generally appointed early in the design process so their
experience can be used to improve the buildability and packaging of proposals as they
develop.
For more information see: Construction management.
Custom build
Custom-build homes are a less 'hands-on' variation of self building in which the
prospective home owner works with a developer that can take on the design and
construction of the home on their behalf and may help find and acquire a site and
arrange finance.
See Custom-build home for more information.
Engineering
procurement
and
construction contract (EPC) / turnkey
contract
EPC contracts, sometimes called turnkey contracts are similar to design and build
contracts, in that there is a single contract for the design and construction of the
project, but generally with an EPC contract, the client has less say over the design of
the project and the contractor takes more risk. Generally, EPC contracts are used on
engineering and infrastructure projects, where the aesthetics of design might be
considered less important than performance and cost certainty.
For more information see: Engineering procurement and construction contract.
Engineering
construction
(EPCM)
procurement
and
management contract
EPCM contracts are similar to EPC contracts (see above), but the client employs the
necessary trade contractors to construct the works. The 'contractor' acts as a
construction manager, managing the trade contractors. Effectively they are
performing the roll of a consultant during the construction phase.
For more information see: Engineering procurement and construction management
contract.
Fast-track construction
Typically associated with construction management and management contract
projects, fast-track construction overlaps project tasks (such as design and
construction) to reduce the overall project duration.
For more information see: Fast-track construction.
Furniture,
(FF&E)
fixtures
and
equipment
FF&E refers to the procurement of Furniture, Fixtures and Equipment. This might be
procured separately to the main construction contract, particularly by clients that may
already have systems in place for procuring fixed and loose furniture, fittings and
equipment, for example schools or hospitals. It is very important under such
circumstances to define which contract every element of FF&E is within. It is also
important to ensure that any building work required for installation is identified and
procured, that any services required are identified and that installation is properly
integrated into the main contract.
For additional information see: Furniture Fixtures and Equipment.
Framework agreements
Clients that are continuously commissioning construction work might want to reduce
timescales, learning curves and other risks by using framework agreements. Such
arrangements allow the client to invite tenders from contracts to be carried out over a
period of time on a call off basis as and when required.
For more information see: Framework contract.
Management contract.
A management contract is one where the works are constructed by a number of
different works contractors who are contracted to and managed by a management
contractor. A management contract structure is similar to a traditional contract,
however, instead of taking the risk associated with a fixed price, the management
contractor is reimbursed the amounts paid to works contractors, and is paid a fee
usually in the form of a percentage.
For more information see: Management contractor.
Measurement
contract
(remeasurement or measure and value
contract)
Measurement contracts (sometimes called 're-measurement' or 'measure and value'
contracts) can be used where the design, or type of works can be described in
reasonable detail, but the amount cannot. For example, excavation, where the
quantity required is difficult to assess until after the works have begun. The contract
sum cannot be determined when the contract is entered into, but instead is calculated
on completion based on re-measurement of the work carried out.
For more information see: Measurement contract.
Partnering
Partnering arrangements are intended to enable full integration of design,
construction and operation. Partnering arrangements are linked by bi-party contracts
and can include contractors, suppliers and specialist designers. Collective and
individual incentive schemes for delivery can be included in cost reimbursement and
fee payments. Partnering requires heavy involvement from the client acting as
employer and adjudicator of disputes.
For more information see: Partnering.
Prime
contracting
contracting
prime-type
Prime contracting is a form of procurement in which the client enters into a long-term
relationship with a contractor who provides a single point of contact (prime contract)
for a supply chain to deliver one or more projects. This is one of the three
procurement routes recommended by Government Construction Strategy for
publicly-funded projects (where it is described as prime-type contracting).
For more information see: Prime contract.
Public procurement
The Common Minimum Standards, referred to in the Government Construction
Strategy, state that '... Procurement routes should be limited to those which
support integrated team working (PPP/PFI, Design & Build, the Prime-type Contracting
approach and framework arrangements...).' Under each of these, the client appoints a
single integrated supply team (including designers, contractors, suppliers and perhaps
facilities managers) based on an output-based specification before design
commences.
Public projects or publicly-subsidised projects may be subject to OJEU procurement
procedures.
For more information see: Public procurement, OJEU, PFI, Private developer scheme
and Crown build.
Self-build
Self building is an alternative to the traditional model of house building in the UK.
Traditionally, houses are built speculatively by a developer, and then people buy them
and move in. With self building, the prospective home owner instigates the
development of the home themselves, whether by purchasing a kit house, employing
a design and build contractor, employing consultants (such as an architect) and a
contractor, or managing the entire process and ordering all the goods and services
required themselves.
See Self-build home for more information.
Single-stage tender
Single-stage tendering is the traditional route for procuring in the construction
industry. It is used when all the information necessary to calculate a realistic price is
available when tendering commences and so the complete contract can be awarded
based on tenders received.
For more information see: Single-stage tender and Two-stage tender.
Two-stage tender
Two-stage tendering is used to allow early appointment of a contractor, prior to the
completion of all the information required to enable them to offer a fixed price. In the
first stage, a limited appointment is agreed allowing the contractor to begin work and
in the second stage, when more detail is available, a fixed price is negotiated for the
rest of the contract.
It can be used to appoint the main contractor early, or more commonly as a
mechanism for early appointment of a specialist contractor such as a cladding
contractor. It may also be adopted on a design and build project.
For more information see: Two-stage tender.
Procurement Routes
1. Traditional: Lump sum
2. Traditional: Re-measurement
3. Design & Build
4. Construction Management
5. Management Contracting
6. Partnering
7. Public Private Partnerships (PPP)
8. Other
construction
Criminal behavior
Non-negligent workmanship
Deliberate intention of wrongdoing
Incidents that has occurred before the date of obtaining
the PI insurance
The scope of policies can vary greatly and the policy should
be renewed annually.
Policy extensions can be provided to provide cover against
employee theft (fiduciary cover) and breach of duty.
Design-Build Characteristics
Typically, the owner prepares a request for qualification (RFQ)
where sources are analysed under fair competition based on
certain criteria and weighed factors. A design-build contract
is usually the preferred contracting method under a tight
schedule as it has intended to save time.
Preferred when it needs fast track schedules as the final project
can be obtained faster, and the return on investment (ROI) is
capitalized sooner.
Using a design-build contract, designers and builders work
hand-in-hand to produce construction drawings and analyse a
logical construction sequence.
Usually, the design process is scheduled in phases, just as the
builder is ready to start that particular phase.
Design-Build Advantages
Design builds contracting offers the following benefits:
Design-Build Drawbacks
The architects
contractor.???
vision
could
properly
appear
to
might
favor
be
the
and