Desai Sir
Desai Sir
Desai Sir
Presentation plan
I.
II.
III.
Process of approval
IV.
Audit Plan
V.
Execution Process
VI.
Report finalization
VII.
Approval
Onshore
Deep Waters
Category-IV:
Frontier basins with uncertain
prospects. Deemed prospective on
analogy with similar basins
4
worldwide
Well Logs
Reservoir Studies
Production
5
I. Exploration of Hydrocarbons by
Exploration
Licence
(PEL)
Nomination
Area
(Sq.Km)
No. of
blocks as
on
31.3.10
Area
retained
(Sq.Km)
PEL
108
128442
62
81997
NELP
39
302644
71
423093
Total
147
431086
133
505090
10
Seismic survey
Exploratory drilling
Total
2007-08
1656.29
2519.09
4715.38
2008-09
3071.83
4299.48
7371.31
2009-10
2158.72
7252.70
9411.42
2010-11
1656.74
8625.27
10282.01
Total
47748.34
22696.54
70444.88
12
ONGC took abnormally long time in finalising the shot hole drilling and data
acquisition service contracts resulting in idling of GPs for considerable periods
of time
14
Theme 2
Theme 3
Theme 4
Theme 5
To examine the
role of ONGC
leadership by
Management in
exploration
efforts
of
ONGC
To ascertain if
ONGC
exercised due
care in the
process
of
exploration
To verify the
reasonablene
ss of costs of
exploration
To
assess
ONGCs
capacity
(technology,
equipment
and
people)
for exploration
To enquire into
the results of
ONGCs
exploration
efforts
Objectives of the PA
19
Area
Block
'Basin'.
Population
Sample
size
200
94 (Random
selection)
191
Exploratory wells
457
88(based on
materiality in
descending
order)
93 (Random
Selection)
20 per cent
20
22
V. Execution Process
Deployment of manpower
Identification of teams
Entrustment of themes
Composition
Area of audit
2 Sr.AOs& 2
AAOs
II
2 Sr.AOs& 2
AAOs
III
1 AO & 3 AAOs
IV
1 AO & 3 AAOs
VI
VII
2 Sr.AOs& 1 AAO
VIII
1 Sr.AO& 2 AAOs
24
V. Execution Process
25
Responses
for the Draft
Report from
ONGC in
March 2012
Exit
conference
held in March
2012
26
VI. Approval
Report approved
by Chairman and
C&AG in August
2012
Scrutiny of report at
Hqrs
Visit of DG for
discussion June
2012
Second round of
discussion with
Chairman Audit
Board in July 2012
Document/
Evidences
verification June
2012
27
Laying of report
28
End of Session I
Thank you
29
Was
exploration
process
efficient
and
cost
effective?
Does
capacity for
exploration
exist?
Was governance
framework robust?
33
Results of Exploration
Reserve Accretion
Reserve Accretion
Finding Cost
Monetization
Discoveries
Reserve
Replacement
Ratio
34
Results of Exploration
Finding Cost
Reserve Accretion
Finding Cost
Discoveries
Monetization
Reserve
Replacement
Ratio
35
Results of Exploration
Discoveries
Though ONGC made 99 discoveries
in NELP and Nomination blocks over
2007-2011, they accreted a reserve of
only 80.98 MMT.
Reserve Accretion
Finding Cost
Oil
Gas
ONGC
13
GSPC
11
RIL
11
15
Monetization
Reserve
Replacement
Ratio
36
Results of Exploration
Monetisation
Monetised only 73 out of its 158
discoveries made during 2002
to 2011
The Company succeeded in
monetizing only 2 out of the 56
offshore discoveries
Non-monetised
offshore
discoveries
contain
major
reserve accreted
Success in monetizing marginal
fields is also limited. Only 53 out
of 165 marginal fields have so
far been monetized.
Reserve Accretion
Monetization
Finding Cost
Discoveries
Reserve
Replacement
Ratio
37
Results of Exploration
Reserve Replacement Ratio
Reserve Accretion
Discoveries
Monetization
Reserve
Replacemen
t Ratio
Production
has
remained
steady/ dipped somewhat
38
What is RRR?
RRR = Now Ultimate Reserve accreted during a year
Total production of hydrocarbon during a year
Was
performanc
e
satisfactory
in NELP
blocks?
Was
explorator
y drilling
adequate
and
efficient?
Was performance
satisfactory in
nomination blocks?
40
field season
Shortfall in
acquisition
41
Exploratory Drilling
Planning was deficient
42
Exploratory Drilling
NPT
Average non productive time of rigs was
19 % against 10% planned by ONGC
during 2008-2011.
International norm is 5 %.
Drilled
Depth
range
(in meters)
ONGC
Private/JV operators
1000-2000
61.9
2000-3000
54.43
GSPCL
SELAN
GSPCL
65.37
63.00
56.45
Mehsana
Cambay
2000-3000
1000-2000
35.4
48.58
Jodhpur
2000-3000
27.27
JOGPL
NIKO
SELAN
EOL
PEL
62.17
40.20
66.65
49.50
42.58
KG (off.)
2000-3000
47.36
Assam-Arakan
3000-6000
14.84(Sivasagar)
Assam-Arakan
3000-6000
32.35(Jorhat)
HEPI
GAZPRO
OIL
Canoco
OIL
Canoco
40.48
16.44
56.42
28.37
28.68
31.13
Ahmedabad
44
Performance in NELP
ONGC lost 69 blocks due to lack of aggression in
the NELP bids (lower work commitment). In 17 of
these, others made 67 discoveries.
ONGC paid liquidated damages of Rs 133.03 crores
for non-completion of MWP in respect of 13 blocks.
Poor performance in deepwater blocks (37% of
ONGCs blocks are deepwater blocks) even
though these have high prospectivity.
45
46
Human resources
Technology
Financial
resources
47
48
Financial Resources
Sufficient financial resources for exploration. Alloted budget
not spent as high as Rs.1324 crore (12.2 per cent) in 2009-10 .
Shortfall in budget utilisation to be viewed in context of underperformance on targets of survey (upto 60 per cent) as well as
exploratory drilling (upto 29 per cent).
49
Technology
ONGC unable to provide assurance on
status of technology to Planning Commission
Independent assessment by third party not
done.
50
Was vision of
Government and
ONGC emphasis in
exploration aligned?
Was the
reporting
against
these
targets
correct?
Whether
the MOU
targets
were fixed
properly?
Performance
measurement
systems in ONGC
51
While
ONGCs
strategy
objective
envisaged 2.2 BT by 2014, ONGCs XI five
year plan 2007-2012 planned for only 1.001
BT IIH. This leaves 1.2 BT IIH to be achieved
in the remaining two years if the strategic
objective is to be met. Achievement of IIH
of 1BT in two years is remote considering
the achievement during the four years
(2007-11) which was only 0.95BT (averaging
0.239BT per year).
52
Reporting on
MOU Targets
Year
Target
Reported
Achieve
ment
Achievement
through
Exploration
Efforts
2007-08
55
63.82
22.22
2008-09
64.5
68.9
8.67
2009-10
72.65
82.98
18.34
2010-11
76.9
83.56
31.77
54
Conclusion
ONGCs current exploration efforts are not
adequate to achieve envisaged strategic goals.
The current MOU performance indicators do not
highlight this inadequacy of exploration efforts
leading to a false sense of accomplishment.
ONGC mainly operates in its producing fields to
meet both, reserve accretion and production
targets. Lack of adequate efforts and results in new
fields, coupled with the ageing of producing fields,
is a matter of concern for future sustainability.
55
Conclusion
Producing Fields
Ageing Fields from where
Reserve Accretion (
reiniterpretation &
development drilling) and
Production ( IOR/EOR) mainly
takes place
New Fields
Shortfall in exploration
efforts, low reserve
accretion, few discoveries,
diminishing find size and
delay in monetization
56
Recommendations
Strengthen the performance accountability framework for
exploration
Setting MoU targets and measuring them accurately
Suitability of RRR as a KPI
Thank You
58
Background
Audit Objectives
A.
B.
Audit criteria
Block - KG-DWN-98/3
Operator - RIL
JV Partners RIL (60%), BP (30%), Niko
(10%)
Introduction
Report no 19 of 2011-12
Non-relinquishment of area
Development activities
IDP 2004
AIDP - 2006
Estimated Capex
$ 2.4 billion
$ 8.8 billion
40 mmscmd
80 mmscmd
August 2006
Mid-2008
The PSC is based on a scaled formula for profit sharing between GoI
and the private contractors:
This is based on a critical parameter the Investment Multiple
(IM) which is essentially an index of the capital-intensive nature
of the project i.e. IM = Cumulative Net Cash Income/ Cumulative
Exploration & Development Costs,
The more capital intensive the project, the lower the IM and GoI
share of profit petroleum (as low as 10%) and Higher the IM,
higher the GoI share (as high as 85%),
Private contractors have inadequate incentive to reduce capital
expenditure, and substantial incentive to increase/ front-end capital
expenditure
So as to retain the IM in lower slabs or to delay movement to
higher slabs.
10
Procurement activities
Report no 24 of 2014
12
Audit constraints
Incomplete list of Purchase Order
Audit uses sampling techniques for selection of cases for
detailed examination. In response to audit requests, the
Operator provided several lists of POs but none of the lists was
complete,
Due to this there could be some POs which may have fallen
outside the population and, therefore, were not picked up for
detailed scrutiny in Audit,
Restricted access to SAP
The Operator, inspite of having information on audit schedule,
gave restricted access to SAP and provided fragmented
information
13
Exploration
Discovery
Appraisal
Declaration of
Commerciality
14
15
Month/Year
May 2004
October 2006
August 2012
Recoverable Reserve
3.81 tcf
10.03 tcf
2.90 tcf
The Operator was required to drill, connect and put on stream 22 wells as
per approved Phase I of AIDP, however, the Operator had drilled,
completed and connected only 18 wells,
Production from the D1-D3 field commenced in April 2009 and started
declining in August 2010. While production level achieved in 2010-11 was
90 per cent of approved production profile, this decreased to 57 per cent
in 2011-12 and 26 per cent in 2012-13,
C&AG noticed that that, as of March 2012, out of 18 wells connected,
only 12 wells were producing gas and six wells had ceased to flow due to
water and sand ingress,
Due to non-drilling of wells and decline in production of gas, the facilities
created by the Operator remained underutilized / unutilized.
The Operators decision to not drill and connect the committed producer
wells as per the approved AIDP even after repeated reminders by the
DGH is a matter to be seriously considered and resolved by the MoPNG to
ensure the energy security of the country
19
20
22
Conclusion
Thank you
26
Discovery area
Exploratory wells were drilled in the entire contract area of the ONGC operated block
(left). In fact, ONGC had relinquished a part of the contract area as required under the
PSC.
In the RIL operated KG-DWN-98/3 (right), exploratory wells were drilled in the north
western part only. Post contract concession of non relinquishment of area was given to
RIL whereas this was not the case in respect of ONGC block.
28
Government
Share
Contractors Share
10 %
90%
16 %
84 %
28 %
72 %
85 %
15 %
33
Unjustified compensation
Case Study
As a part of its Redevelopment Plan, M/s Sea Oil Company invited international
competitive bids (ICB) in September 2002 for installation of platforms and laying
of pipeline segments in its Offshore Field. The likely date of issue of Notification
of Award (NOA) was 31 January 2003 with the completion of the project
scheduled by 30 April 2004. Offers from ten bidders were received.
Technical bids were opened on 3 January 2003 after one month of the scheduled
date.
Only two bidders viz., M/s Aqua and M/s Beta were found technically qualified.
Tender Committee (TC) revised the date of NOA to 14 March 2003 and
recommended (January 2003) opening of price bids of M/s Aqua and M/s Beta.
The bidders were asked to confirm unconditional compliance with the original
project completion schedule i.e. 30 April 2004, despite revision in the date of
NOA. As M/s Aqua did not agree, its offer was rejected. M/s Beta confirmed (4
March 2003) compliance with the project completion schedule with revised NOA
with a request for a grace period of 15 days before levy of liquidated damages
(LD).
On evaluation, TC recommended (13 March 2003) the award of work to M/s Beta
with grace period of 15 days. In view of likely delay in the award of contract, the
Apex Purchase Committee (APC) of M/s Sea Oil Company asked (31 March 2003)
M/s Beta to re-confirm project completion schedule of 30 April 2004 with NOA
by 15 April 2003 along with the negotiations for price reduction. During
negotiations M/s Beta did not offer any price reduction but confirmed (3 and 4
April 2003) compliance with the completion schedule subject to issue of NOA by
7 April 2003 with grace period of 15 days. TC recommended (4 April 2003)
placing of order on M/s Beta for $100 million stating that re-tendering would
delay the project by one year and would involve loss of oil production of 0.13
MMT1.
The APC, however, approved the award of contract to M/s Beta on 9 April 2003
without grace period. Accordingly, M/s Beta was asked (9 April 2003) by the TC
to confirm unconditional compliance with the original completion schedule
without grace period. As this was not in conformity with their offer, M/s Beta
refused the offer. Subsequently the offer (12 April 2003) by the TC with a grace
period of 15 days was also rejected by M/s Beta.
M/s Sea Oil Company re-invited (May 2003) fresh tenders and awarded Contract
(January 2004) to M/s Beta at a price of $147 million for installation of the same
facilities viz., platforms, laying of pipelines in Offshore Field.
Questions
1. How do you assess approach of M/s Beta in the above case?
2. Your comments on issue of NOA by M/s Sea Oil Company on 09 April 2009.
3. In your opinion, what were the financial implications for M/s Sea Oil
Company in the above case?
4. Do you think APC was right in its wisdom in non-allowing the grace period of
15 days to the bidder for completion of the said contract?
5. Do you have any suggestions for M/s Sea Oil Company as a way forward in
such cases in future?
Page
1. As part of the project plan, a sub-way was to be built in one of the slum area. For this
purpose, an expenditure of Rs. 31.86 lakh was incurred. The components of the above
expenditure include equipment costing Rs.9.83 lakh imported and stored at the Customs
bonded warehouse and other related expenditure of 22.03 lakh. The title to the equipment
has already been relinquished by the Company (4/2009) and the work has also been
abandoned due to other administrative reasons. Hence the cost of the asset and the
expenditure has to be written off. This has not been done which resulted in over statement
of miscellaneous expenditure and profit to that extent.
2. For the above project ADB has sanctioned a loan amount of Rs.12.90 crore. On verification
of the Balance Sheet, it was found that unsecured loans do not include interest amounting
to Rs. 1.15 crore payable on the project loan of Rs. 12.90 crore for the period from 1.04.10
to 28.03.11. Non provision has resulted in understatement of unsecured loans and
overstatement of profit to that extent.
3. The Development Reserve Fund includes a sum of Rs.4.22 lakh being the maintenance
expenses, which are of revenue nature (such as electricity charges) etc and to be charged to
Profit and Loss account under Prior period expenses. Consequently, profit is overstated
to the same extent.
4. For the purpose of development of housing, the Company has acquired land from owners
by paying the cost of the land at guideline value. However, the private land owners did not
accept the rate offered by the Company and have approached the court and won the case.
As per the Accounts the Free hold land is shown at Rs. 6430328/This does not include a sum of Rs. 54,88,756 being the difference in land cost between cost
already accounted for and higher rate of compensation payable along with interest as per
During the course of the audit of financial year 2010-11 following audit conclusions were derived:
Page
the Government Order. This has resulted in understatement of current liabilities and fixed
assets to that extent.
5. Capital Work in progress Rs. 36.50 lakh : This represents expenditure incurred on
construction of bore well during 2007-08 which has been abandoned due to dry well. Since
the company has not made use of this, it should have been written off. Non writing off has
resulted in overstatement of Capital Work in Progress and over statement of profit to that
extent.
6. Gross Block Rs.2,39,65,454/a) This does not include Rs. 19,06,695/- being the value of work completed during the
year at stage 1 of the project. This resulted in understatement of Fixed Assets.
Further depreciation and loss for the year is also understated by Rs. 59,523 while
Capital WIP stands overstated to the same extent.
b) The establishment cost of the officers in construction wing of the company had not
been apportioned to the respective capital works completed. The fact has also not
been suitably disclosed.