DESIGN GUIDE
INTRODUCTION
Those involved in the design of diffused aeration equipment
for wastewater treatment should understand the impact that
process type, maintenance issues and economic
considerations can have on the selection of equipment. Like
many other engineering challenges, these factors are
frequently interrelated and trade-offs of one aspect versus
another are required for most application. This design guide
presents information that has been obtained and developed
from a variety of sources. Some of this information has
been developed from actual test data, some is condensed
from other published sources, some is based on good
engineering judgement and practical field experience. The
information, formulas, values and methods, etc. should be
viewed as a design aid and may not be applicable in all
situations. The designer should always use good
professional engineering judgement for every application.
The following sections of this design guide will briefly
discuss the activated sludge process and biological treatment
oxygen demands. The guide provides a rational step-by-step
procedure to convert actual oxygen requirements (AOR) to
standard oxygen requirements (SOR). It illustrates how to
perform many of the oxygen transfer calculations including
approximating aerator sizing and selection. Final equipment
sizing and configurations should be referred to the factory
for confirmation.
Oxygen must be provided in biological treatment systems to
satisfy several types of demands. These are referred to as
actual oxygen requirements or AOR. AOR is always
expressed as field conditions. Each wastewater treatment
plant has its own unique field conditions that include site
elevation, temperature, working DO level, diffuser
submergence and alpha and beta factors. The designer
must use these factors to convert AOR to standard oxygen
requirements (SOR) to properly apply the aeration
equipment and determine the amount of process air
required to satisfy the biological treatment oxygen demands.
Common units of expression for AOR and SOR are pounds of
oxygen per day per unit volume. SOR values will always be
larger than AOR values. Confusion and misunderstanding
can be minimized between designer and equipment supplier
if the designer expresses his desired oxygen demands in
terms of SOR values. If this is not possible, then clearly
identify the oxygen demand as an AOR value and provide as
much information as possible for the equipment supplier to
assist you in making the appropriate AOR/SOR conversion.
Experienced aeration equipment manufacturers can provide
information to engineers and designers on the oxygen
transfer capability of particular equipment and
configurations when the equipment is aerating clear tap
water. These tests, when corrected for temperature and
elevation to standard conditions, become the basis for
determining the equipments standard oxygen requirement
or SOR. Equipment manufacturers cannot guarantee the
oxygen transfer capability of aeration equipment in
wastewater. Each wastewater treatment plant has its own
FIGURE 1
1. BOD LOADING
2. AMMONIA LOADING
The oxidation of one pound of ammonia requires 4.3 to 4.6
pounds of oxygen. Typical domestic wastewater contains
25-30 mg/l of ammonia. Do not underestimate the oxygen
demand to oxidize the ammonia. Oxidizing 25 mg/l of
ammonia is equivalent to an additional 115 mg/l of BOD
loading. Be award that even if a plant is not specifically
designed to nitrify, that under favorable loading,
temperature and SRT conditions, nitrification can and will
occur. This may exert a large unanticipated oxygen demand
30 deg.C
1.8
20 deg.C
1.6
Carbonaceous Oxidation
(O2 / CBOD5-load)
1.4
10 deg.C
1.2
0.8
0.6
0.4
0
10
20
30
SRT (days)
40
50
COMMENTARY
Equation 1
Pf
Csat DO field
PMSL
T 20
AOR = SOR( )
Csat
FIGURE 2
20
25
20
Nitrogen (mg/l)
Alpha() =
15
KLa wastewater
KLa tap water
Beta()
Pf
PMSL
DO field
10
T
Csat20
Effluent NH3-N
CsatT
0
0
10
15
20
25
30
SRT (days)
Alpha
Beta
Site Elevation
Dissolved Oxygen
Temperature
Saturation value for the device at the specified
submergence
= Saturation Factor
= Barometric pressure at jobsite
= Barometric pressure at mean sea level
= Working dissolved oxygen concentration in
wastewater
= Operating temperature of wastewater
= Surface DO saturation concentration at 20 C
and standard conditions for the particular
aeration equipment at the design submergence
= Surface DO saturation concentration at design
temperature T and 14.7 PSIA for the particular
aeration equipment at the design submergence
COMMENTARY
FIGURE 3
Temperature Correction Factor Theta
Temperature Correction Expression T-20 and = 1.024
T (C)
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
Value of T-20
.0789
.808
.827
.847
.867
.888
.909
.931
.953
.977
1.00
1.024
1.049
1.074
1.100
1.126
1.153
1.181
1.209
1.238
1.268
T (F)
50.0
51.8
53.6
55.4
57.2
59.0
60.8
62.6
64.4
66.2
68.0
69.8
71.6
73.4
75.2
77.0
78.8
80.6
82.4
84.2
86.0
FIGURE 4
FIGURE 6
12.5
11.5
Altitude (Feet)
-1000
-500
0
+500
1000
1500
2000
3000
4000
5000
6000
7000
8000
9000
10,000
Fine Bubble
Coarse Bubble
12.0
11.0
10.5
10.0
9.5
9.0
10
15
20
25
30
FIGURE 5
Temperature Correction for Csat
T (C)
0
2
4
6
8
10
12
14
16
18
20
22
24
26
28
30
Csatr = Csat20 x
Surface Csatr
Surface Csat20
= 10.0 mg/l
= 30 C
Find Csat30
3.
4.
5.
6.
35
Example:
Given an aeration tank with an AOR loading of 1500 pounds
of oxygen per day, find the air volume required for a coarse
bubble aeration system. Assume 15 foot deep tanks.
Solution:
1500 pounds per day O2 AOR divided by 0.5 equals 3000
pounds per day O2 SOR.
3000 pounds per day O2 SOR divided by 1440 minutes per
day equals 2.08 pounds per minute O2 required. Locate
diffusers 1 foot off tank floor or submergence equals 14
feet.
14 feet submergence times 0.75% OTE equals 10.5% OTE.
From Rules of Thumb #5, 1 SCFM contains 0.0173 pounds
of O2 and 10.5% is transferred to the waste, then 1 SCFM
will transfer 0.0018 pounds of O2 per minute.
Divide the demand of 2.08 pounds O2 per minute by 0.0018
pounds of O2 per minute transferred which equals 1156
SCFM required.
FIGURE 7
Power Required To Adiabatically Compress 1,000 SCFM
80.0
70.0
Blower Horesepower
7.
60.0
70%
50.0
80%
40.0
30.0
20.0
4
10
11
12
13
FIGURE 8
Equation 2
14.7 + P 0.283
BHP = SCFM(.23)
1.0
14.7
MECHANICAL EFFICIENCY
Where BHP (brake horsepower) = adiabatic horsepower
mechanical efficiency
P = Blower discharge pressure in PSIG
A good estimate of the blower, motor and coupling
mechanical efficiency is 70% when the blower is operating
at mid-range. Efficiency will increase somewhat when the
blower is operated at its maximum output and will decrease
when operated closer to the surge point.
Figure 7 is a graph of blower horsepower per 1000 SCFM at
various discharge pressures assuming 60%, 70% and 80%
mechanical efficiency. Figure 8 is a schematic diagram of an
14
5.
6.
7.
8.
9.
10.
11.
12.
13.
CALCULATE:
1. AOR
2. Aeration tank size
3. Air requirements
4. Actual coarse bubble and fine bubble AOR/SOR ratios
SOLUTION:
1. Calculate AOR:
From the list of givens, we will assume 30% BOD removal in
the primary clarifiers. The influent BOD loading to aeration
is then:
70% x 200 mg/l x 8.33 lbs. mg/l/MGD x 1 MGD
= 1166 lbs. BOD
The side stream BOD loading to aeration is then:
2000 mg/l x 8.33 lbs./mg/l/MGD x 0.05 MGD
= 833 lbs. BOD
Total lbs. BOD to aeration is 1999 or approximately 2000
lbs.
Ignore the BOD in the effluent and assume all 2000 lbs. BOD
must be oxidized in aeration tanks as an additional factor of
safety. We have previously determined that we will use 1.0
pounds of oxygen per pound of BOD applied. Therefore, the
average AOR for BOD is 2000 pounds of oxygen. In
addition, from the list of givens, we know that the minimum
loading will be 75% of the average and peak loading will be
150% of the average.
We now have:
Minimum day BOD AOR = 1500 lbs. O2
Average day BOD AOR = 2000 lbs. O2
Peak day BOD AOR
= 3000 lbs. O2
The influent ammonia loading to aeration is then:
30 mg/l x 8.33 lbs./mg/l/MGD x 1 MGD
= 250 lbs. ammonia
Ignore the ammonia in the effluent. We have previously
determined that 4.6 pounds of oxygen per pound of
ammonia applied is required or 1150 pounds of oxygen. In
addition, from our givens, the minimum loading will be 75%
of the average and there is no peak ammonia loading.
We now have:
Minimum day NH3N AOR = 863 lbs. O2
Average day NH3N AOR = 1150 lbs. O2
Peak day NH3N AOR
= 1150 lbs. O2
Combining the AOR numbers for BOD and NH3N yields the
following oxygen requirements:
Minimum day AOR
= 2363 lbs. O2
Average day AOR= 3150 lbs. O2
Peak day AOR
= 4150 lbs. O2
Remember that we have also defined a summer and winter
temperature range of 20 C and 15 C respectively.
2.
O2/min.
Submergence is 14 ft. OTE
= 14 ft.
14 ft. x 0.75% per ft.
= 10.5% OTE
1 SCFM contains 0.0173 lbs. O2
At 10.5% OTE, 1 SCFM will transfer 0.00182 lbs. O2/min.
4.375 lbs. O2/min. .00182 lbs. O2/min/SCFM
= 2404 SCFM required
COARSE BUBBLE
Example No. 1 uses a fixed header located at the side of the
tank. OTE is 9.17%, air required for summer average
conditions is 3058 SCFM and blower horsepower required is
126.77. The installed cost of the equipment is estimated to
be $27,000
= 3150 lbs. O2
= 0.33
= 9545 lbs. O2/day
= 6.628 lbs. O2/min
Temperature
15 C
20 C
15 C
20 C
Fine Bubble
AOR/SOR Ratio
0.460
0.448
0.310
0.303
Figure 9
Item
OTEcw%
OTEf%
SCFM
PSIG Top of Tank
PSIG of Blower
Blower HP
Annual Power Cost 1
Equip Cost 2
Installed Cost 2
Amortized Cost 3
Total Annual Cost 4
1234-
Example 1
Side Placement
Example 2
Center Placement
Example 3
2 Headers
Example 4
3 Headers
9.18
4.11
3149
6.3
6.6
127.4
$41,400
$27,000
$29,700
$3026
$44,426
10.3
4.61
2702
6.3
6.6
112.7
$36,700
$24,600
$27,000
$2,751
$39,451
12.2
5.47
2297
6. 3
6.6
95.8
$31,100
$30,000
$33,000
$3363
$34,463
12.5
5.6
2233
6.4
6.6
94.3
$30,650
$36,400
$40,000
$4,076
$34,726
FIGURE 10
Item
Example 5
AT/AD = 20
5% Diffuser
Density
Example 6
AT/AD = 10
10% Diffuser
Density
23.7
7.17
1747
7.45
7.3
82.2
$26,715
$20,000
$25,000
$2,547
$29,262
28.5
8.60
1456
6.6
6.9
63.1
$20,508
$25,200
$31,500
$3,210
$23,718
Example 3 - 2 Headers
$900,000
1234-
Example 4 - 3 Headers
$800,000
$700,000
Accumulated
Expenses
OTEcw%
OTEf%
SCFM
PSIG at Top of Drop
PSIG at Blower
Blower HP
Annual Power Cost 1
Equip Cost 2
Installed Cost
Amortized Cost 3
Total Annual Cost 4
$1,000,000
FIGURE 11
$600,000
$500,000
$400,000
$300,000
$200,000
$100,000
$0
0
10
12
14
16
18
Years of Operation
20
Figure 12
Example 5 - 20 AtAd
$700,000
Example 6 - 10 AtAd
Accumulated
Expenses
$600,000
$500,000
$400,000
$300,000
$200,000
$100,000
$0
0
10
15
20
Years of Operation
REFERENCES
1. Recommended Standards for Sewage Works, Great
Lakes Upper Mississippi River Board of State Sanitary
Engineers, 1978.
2. Summary Report Fine Pore (Fine Bubble) Aeration
Systems, US EPA, EPA/625/8-85/010,1985.
3. Activated Sludge Manual of Practice No. OM-9,
Water Pollution Control Federation, 1987.
4. A Standard for the Measurement of Oxygen Transfer in
Clean Water, American Society of Civil Engineers,
1984.
5. Operation of Extended Aeration Package Plants
Manual of Practice No. OM-7, Water Pollution Control
Federation, 1988.
6. Aeration Manual of Practice No. FD-13, Water
Pollution Control Federation, 1988.
7. Design Manual Fine Pore Aeration Systems, US EPA,
EPA/625/1-89/023, 1989.