AP Newsletter 2015
AP Newsletter 2015
AP Newsletter 2015
AP Technology newsletter
March 2015
aptechnology.com
AP Technology
Exceptional value delivery worldwide
AP60 Jonquire:
Well done!
In August 2014, the Arvida Aluminium Smelter, AP60 Technology
Centrepassed Rio Tinto Alcans rigorous internal certification confirming
thetechnologys effectiveness and reliability.
The performance test of the installed AP60 technology
was conducted over a 30-day period, with excellent
results, as summarised in the table below. The test
included a reinforced process and production follow-up
to assess thetechnologys full potential.
Result
4,407
Amperage (kA)
570.7
95.9
13,090
0.02
0.21
Cover picture:
Kitimat potline
02
AP Technology newsletter
Issue 19
March 2015
Editorial
AP60 technology is a reality
After one year of operation, the AP60 technology
solution installed at Arvida Technological Centre in
Jonquire, Canada, shows outstanding technical results.
The performances have been above expectations on
allcounts and the threshold of 600kA was reached in
January earlier this year. APXe, the low energy version
of AP60 technology operating at the Laboratoire de
Recherche des Fabrications (LRF) in France, achieved
its targeted specific energy consumption of 12.0MWh/t
at amperage above 500kA, successfully delivering the
promised step change in energy reduction.
Vincent Christ
Vice president,
Technology R&D,
Equipment Sales
&Services and
Carbonproducts
Routes to excellence
Aluminium smelters worldwide are working hard to keep
or improve their position on the industry cost curve.
Tolower expenditures in $/t, a plant can focus on costs,
overall production levels or both. One option is to launch
broad-based savings initiatives. While such programmes
are effective, their impact on the smelter's relative
position on the cost curve tends toremain limited.
Past experience has demonstrated that one of the best
ways to strengthen competitiveness is to improve pot
performances by implementing a pot modernisation
programme. Indeed, two smelters that initially used the
same pot technology can display very different targeted
pot performance, depending on factors such as:
Energy cost and availability
Bottlenecks in the carbon department
Remaining capacities in the gas treatment center,
substation andcarbondepartment
Forced cooling
Low-energy lining
High-productivity lining
Magnetic compensation loops
Jet Induced Boosted Suction (JIBS)
AP Technology newsletter
Issue 19
March 2015
Kitimat
The final countdown
At Kitimat, British Columbia, the new 384-pot potline,
installed in four separate rooms and hosting the latest
AP40 technology at 405kA and 13,150kWh/t, is gearing
up for action.
With an operation readiness plan established before
theproject kick-off and updated throughout the
construction phase, the Kitimat plant is ready for
thechallenge of stopping the remaining Soderberg
lines and starting the new AP40 line without any
additional external permanent manpower.
To support the transition over the coming months,
theAP Technology commissioning and start-up team
is mobilising on site to safely support the local teams
during the challenging months ahead.
04
AP Technology newsletter
Issue 19
March 2015
1 NALCO at a glance
A Situation:
The bauxite deposits are located at Damanjodi in a
beautiful plateau region. The 1,000 metre altitude is
high enough to avoid extreme heat, a major advantage
for both the staff and the machines.
Some of the alumina produced is sent by train to
Visakhapatnam inthe Bay of Bengal to be exported.
The smelter and captive power plant are situated
closeto coal deposits at Angul, a small rural town in a
rice-growing plain about 130 kilometres from the sea.
The main raw materials are carried there by train.
05
AP Technology newsletter
Issue 19
March 2015
B Capacity:
NALCO was built and developed in three stages, each
involving essentially the same technologies witha
fewimprovements.
Capacity
Facility
Originally
After expansion 1
After expansion 2*
Bauxite mines
2,400,000t
4,800,000t
6,300,000t
Alumina refinery
800,000t
1,575,000t
2,100,000t
Smelter
218,000t
345,000t
460,000t
Captive
power plant
600MW
960MW
1,200MW
* In progress
Communication:
The plant was built and started up without any real
operating outside phone line, telex or fax. Telephoning
to France meant going to Bhubaneswar, a round trip
ofabout six hours by car.
Communication within the plant was also complicated
due to the many different languages and dialects spoken
by the staff.
Red tape:
At the time, management of the public sector in India
was characterised by a certain amount of administrative
red tape, which could make life at the plant difficult.
Total absence of small local firms:
There were no small firms in the Angul region able to
provide quality subcontracted services, without which
the life of a smelter such as this is very difficult.
3 Engineering and construction:
06
AP Technology newsletter
Issue 19
March 2015
Angul: Smelter
4 Operations:
NALCOs teams were trained in 1985 and 1986 essentially
at Vlissingen (Netherland) and at Tomago (Australia). The
courses went well, the trainees being well received by
the plants and making a good impression on their hosts.
The first pot was started up in potline 1 on 28 March 1987
but it was only in May 1993 that an operating rate of
nearly 90% was achieved.
The first few years were challenging. In spite of the
early difficulties, NALCO and its environment slowly
began to ramp up, improving its performance and
Updates from
around the globe
BSL
The magnetic compensation
loop delivers
As mentioned previously, BoyneSmelterLtd in
Queensland, Australia, has installed an AP compensation
loop on its potline 2, with a view toimproving the
magnetic stability of its Sumitomo pots to unlock
furtheramperage increases.
One year after it was energised, the compensation
loophas successfully stabilised the pots, allowing
anamperage creep of over 16kA (equivalent to more
than7% in productivity), while maintaining and
insome cases improving all other technical KPIs.
Boyne Smelter
07
AP Technology newsletter
Issue 19
March 2015
Hindalco
Aditya
Sohar Aluminium
Full conversion to AP40 technology
Sohar Aluminium
08
AP Technology newsletter
Issue 19
March 2015
Alcoa Deschambault
Upgrading its AP anode baking furnace
After more than 20 years of operation, Aluminerie deDeschambault is implementing the latest
APTechnology improvements to renovate its twoanode baking furnaces and increase their capacity.
The renovation involves raising the concrete casing andincreasing the pit width to accommodate
the baking oflarger anodes, which will meet the needsof the reductionprocess.
The first bay of the first furnace was successfully rebuilt in 2014 and thesecond bay rebuild
isscheduled for the first half of 2015.
EMAL
New energy consumption benchmark achieved by the
APTechnology anode baking furnace at EGA Taweelah
The commissioning of the AP Technology Anode Baking
Furnace at EGA Taweelah (EMAL) was completed in 2014.
With four fires and 68 sections, the furnace has a
benchmark capacity of 330kt/year of baked anodes.
The technical performance evaluation showed that another
benchmark was set by the furnace as it achieved an energy
consumption as low as 1.53GJ/tonne.
This is the result of AP design efficiency, AP process
control principles and the excellent standard of operations
maintained by the EGA teams.
09
AP Technology newsletter
Issue 19
March 2015
Sustainable solutions
Assessment of GHG emissions
AP Technology deploys a wide range of sustainable solutions and services
toits clients. Below is a focus on the assessment of Green House Gases (GHG)
emissions in a smelter. Different approaches may be used to evaluate
GHGemissions inaccordance with IAI standards.
Technology specific
slope and overvoltage
coefficients for the
calculation of PFC
emissions per tonne
aluminium from AE
process data
Technology
SCF4
Uncertainty
(%)
OVC
Uncertainty
(%)
FC2F6/CF4
Uncertainty
(%)
CWPB
0.143
1.16
24
0.121
11
SWPB
0.272
15
3.65
43
0.252
23
VSS
0.092
17
NR
NR
0.053
15
HSS
0.099
44
NR
NR
0.085
48
a. C
entre Worked Prebake (CWPB), Side Worked Prebake (SWPB), Vertical Stud Sderberg (VSS), Horizontal Stud Sderberg (HSS).
b. S
ource: Measurements reported to IAI, US EPA sponsored measurements and multiple site measurements.
c. E
mbedded in each Slope and Overvoltage coefficient is an asumed ernissions collection efficiency as follows: CWPB 98%, SWPB
90%, VSS 85%, HSS 90%. These collection efficiencies have been assumed based on measured PFC collection fractions, measured
fluoride collection efficiencies and expert opinion.
d. T
he noted coefficients reflect measurements made at some facilities recording positive overvoltage and others recording algebraic
overvoltage. No robust relationship has yet been established between positive and algebraic overvoltage. Positive overvoltage
should provide a better correlation with PFC emissions than algebraic overvoltage.
e. O
vervoltage coefficients are not relevant (NR) to VSS and HSS technologies.
10
AP Technology newsletter
Issue 19
March 2015
ALPSYS @ ALBA
ALPSYS
More than a product: an array of opportunities!
Over the last 15 years, the ALPSYS team has shown
unwavering determination in developing the product
inorder to deliver ongoing performance improvement
opportunities in process and operation.
On the heels of the R&D work performed over the past
few years, 2014 saw the completion and validation of our
latest alumina control algorithm. With the new version
of the alumina feed procedure including the high/low
frequency instability treatment, the improved tracking
conditions and a broadened alumina control range on
unstable pots, the ALPSYS system isproviding concrete
and robust solutions to sustain optimal pot operation in
increasingly demanding operating conditions, typically
found in plants that arelowering their ACD.
Alongside the development of control procedures, 2014
was also a very successful year in consolidating our
% of ALPSYS controlled
production capacity
100%
80%
60%
40%
20%
0%
Robust Al203
control
RADAR
High/low
frequency instability
4A
Maintenance/
warranty
11
AP Technology newsletter
Issue 19
March 2015
MESAL
Breaking news
Kitimat
MESAL 4.0
MESAL 4.0 is now fully deployed at the Kitimat smelter, British Columbia. The last key user
training session was held in late January 2015. MESAL is now up and running, ready for Day 1
ofthe commissioning phase ofeach of the smelter shops. This will bring strong technical
monitoring to the teams in charge of the smelter ramp-up.
12
AP Technology newsletter
Issue 19
March 2015
Collaborative tools
Mobility (smartphone, tablet)
Real time
Advanced processing data
Cloud and big data
13
AP Technology newsletter
Issue 19
March 2015
AP60 pot
The AP60 and APXe technologies use the same optimised framework
(busbars, shell and superstructure) and operating equipment, while
anode assemblies, cathodes and linings, ventilation and gas flow
differ to suit the needs of each.
Feature
14
AP60
APXe
Busbar
Common
Shell
Common
Superstructure
Common
Common
Anode assembly
High productivity
Low energy
High productivity
Low energy
Shell ventilation
High productivity
Low energy
Gas flow
High productivity
Low energy
Common
Common
Building
Common
Operation
Common
AP Technology newsletter
Issue 19
March 2015
Unit
Last
5 months
2014
Amperage
kA
507.0
Current efficiency
94.5
kWh/tAl
12,240
Potline energy
consumption
By sharing the same platform as AP60, APXe automatically benefits from the industrial validation
of the key components of the pot technology implemented at Jonquire, such as the busbars,
the potshells, the pot superstructures (including gas collection), the alumina handling equipment,
the pot process control system and main operating equipment such as pot tending assemblies,
metal and anode transport vehicles. Full validation results from a combination of industrial
validation of AP60 at Jonquire and validation of APXe specific items tested on the pots operating
at the LRF.
AP60
Time
to market
APXe
1st generation
(Jonquire 2014)
2nd generation
(2015)
2015
Current (kA)
570
600
500
4.3
> 4.5
3.7
13.3
< 13.0
12.3
15
AP Technology newsletter
Issue 19
March 2015
AP30 Club
A unique forum for AP30 users
Club Members
visiting Muscat
16
AP Technology newsletter
Issue 19
March 2015
The AP Technology
smelter of the future
New concepts and solutions for the smart smelter
BAC
MAX
17
AP Technology newsletter
Issue 19
March 2015
TMS 2015
18
AP Technology newsletter
Issue 19
March 2015
19
aptechnology.com
riotintoalcan.com
Mailing address
PO Box 6090
Montreal, Quebec H3C 3A7
Canada
bernard.allais@riotinto.com
ivan.bauret@riotinto.com
francois.charmier@riotinto.com
benoit.feve@riotinto.com
claude.ritter@riotinto.com
christian.staub@riotinto.com
ALPSYS
Patrick Richard
patrick.richard@riotinto.com
MESAL
Pierre Trouiller
pierre.trouiller@riotinto.com
XX%