004 Annexure D Job Safety SAnalysis JSA
004 Annexure D Job Safety SAnalysis JSA
004 Annexure D Job Safety SAnalysis JSA
8kV
LV BUSHING&GASKETS REPLACEMENT
1. Transformer Leak
checking/Nitrogen filling
Potential Hazard
Falling/Tripping
Control Measure
Provide cylinder trolley to secure nitrogen cylinders.
Ensure proper wind up of hoses and housekeeping at
work site.
Ensure the equipments/tools to be used for gas filling
are in good condition and suitable for the pressure
rating of the system.
Ensure that all testing equipments are calibrated and
stamped with calibration certificates.
No one is allowed to work or strike on equipment while
it is under pressure.
Full body harness must be worn at all times and
secure 100% tie off while the activity is ongoing to
prevent fall incident from heights.
Over Pressure
Responsible Person
3. Vacuum Drying
Filling & circulation of oil
Potential Hazard
Fire
Electrocution
Control Measure
from any defect and suitable for the pressure rating of
the system.
Provide whip lash arrestor for hose connections
Barricade the area where activity is to be carried out.
Post warning signs.
Use only tools for intended purpose
All tools/ equipment should be inspected and monthly
color coded.
Make sure internal pressure in the transformer is at
zero gauges before opening manhole cover and
starting air flow into the transformer.
Ensure the equipments/tools to be used for vacuum
testing are free from any defect and suitable for the
pressure rating of the system.
Provide whip lash for hose connections
Provide GCFI using vacuum pump/ and filtration
machine.
Provide fire extinguisher in work area.
Ensure all electrical connection is in good condition no
damage and used 125volts and 380 & 480 volts power
for supply of the equipment.
Always shut off pump motor before opening or closing
Responsible Person
4. Insulation test
Prepared by:
HSE Officer
Potential Hazard
Electrocution
Control Measure
Responsible Person
Reviewed by:
HSE Manager
Responsible Person:
Approved by:
Electrical Engineer
Project Manager
Note: Detailed JSA will be submitted after performing the initial transformer assessment.