Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

004 Annexure D Job Safety SAnalysis JSA

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 3

YNGL TRANSFORMER 302A, 100MVA, 115kV/13.

8kV
LV BUSHING&GASKETS REPLACEMENT

JSA FOR REPAIRING OF POWER


TRANSFORMER
Basic Job Sequence

1. Transformer Leak
checking/Nitrogen filling

Potential Hazard

Falling/Tripping

Control Measure
Provide cylinder trolley to secure nitrogen cylinders.
Ensure proper wind up of hoses and housekeeping at
work site.
Ensure the equipments/tools to be used for gas filling
are in good condition and suitable for the pressure
rating of the system.
Ensure that all testing equipments are calibrated and
stamped with calibration certificates.
No one is allowed to work or strike on equipment while
it is under pressure.
Full body harness must be worn at all times and
secure 100% tie off while the activity is ongoing to
prevent fall incident from heights.

2. Dry Air Testing

Over Pressure

Scaffold shall be inspected, certified and tagged


according to procedures and guidelines by a
competent scaffold inspector.
Ensure the equipments/tools to be used for air test
(such as hoses, pump, pressure gauges etc) are free

Responsible Person

YNGL TRANSFORMER 302A, 100MVA, 115kV/13.8kV


LV BUSHING&GASKETS REPLACEMENT

JSA FOR REPAIRING OF POWER


TRANSFORMER
Basic Job Sequence

3. Vacuum Drying
Filling & circulation of oil

Potential Hazard

Fire
Electrocution

Control Measure
from any defect and suitable for the pressure rating of
the system.
Provide whip lash arrestor for hose connections
Barricade the area where activity is to be carried out.
Post warning signs.
Use only tools for intended purpose
All tools/ equipment should be inspected and monthly
color coded.
Make sure internal pressure in the transformer is at
zero gauges before opening manhole cover and
starting air flow into the transformer.
Ensure the equipments/tools to be used for vacuum
testing are free from any defect and suitable for the
pressure rating of the system.
Provide whip lash for hose connections
Provide GCFI using vacuum pump/ and filtration
machine.
Provide fire extinguisher in work area.
Ensure all electrical connection is in good condition no
damage and used 125volts and 380 & 480 volts power
for supply of the equipment.
Always shut off pump motor before opening or closing

Responsible Person

YNGL TRANSFORMER 302A, 100MVA, 115kV/13.8kV


LV BUSHING&GASKETS REPLACEMENT

JSA FOR REPAIRING OF POWER


TRANSFORMER
Basic Job Sequence

4. Insulation test

Prepared by:

HSE Officer

Potential Hazard

Electrocution

Control Measure

Responsible Person

valves to prevent equipment damage and injuries.


Make sure all electrical connection is in good condition
prior to start the job.
Only trained and competent person will be allowed to
execute work during testing.

Reviewed by:

HSE Manager

Responsible Person:

Approved by:

Electrical Engineer

Project Manager

Note: Detailed JSA will be submitted after performing the initial transformer assessment.

You might also like