Ch13 - Steel Fabrication Work
Ch13 - Steel Fabrication Work
Ch13 - Steel Fabrication Work
-A-249-
Table of Contents
1. Generals
2. Materials
2.1. Steel
2.2. Bolts/Nuts
2.3. High-Tension Bolts
2.4. Weld Rods
3. Transportation, Arrangement, and Storage of Materials
4. Preparing Shop Drawings
5. Shop Drawing Inspection
6. Preparing Full-Size Drawings and Molding
7. Inspection of Full-Size Drawings
8. Steel Fabrication
9. Steel Fabrication Inspection
10. Welding
11. Welding Inspection
12. Welding Correction
13. Assembly
14. Assembly Inspection
15. Inspection of Finished Steel Structure
16. Correction of Finished Steel Structure
17. Temporary Assembly
18. Painting
19.Transportation and Field Storage of Steel Structure
-A-250-
1. Generals
1.1. Start of Construction
(1) In Steel Fabrication Work shall comply with the applicable codes of the JIS & ASTM or equivalent. Other
materials or products shall be approved by the supervisor.
(2) The construction should be started within 3 days from the date of the contract and all administrative
documents required by the responsible person such as construction plans, fabrication plans, fabrication
schedules, field supervisor appointment, and other documents should be submitted.
-A-251-
1.3. Preparing Shop Drawings: The maker should prepare shop drawings in accordance with design
drawings and in the order of work priority, which should not interrupt the following construction and
be subject to the inspection by the responsible person.
1.4. Steel fabrication and assembly for this construction should be performed in accordance with
drawings and others not specified in this specification shall conform to the relevant standards of the
Ministry of Construction and Transportation.
1.5. Construction Status Report: The fabricators should make verbal and/or written report on overall
construction status required by the responsible person such as daily work status, manpower input
status, machinery and tool operational status, construction records, abnormal situations during
construction, and receipt of materials supplied by the company.
1.6. Photo Records: Photo records of steel fabrication should be made for each process, and especially
for the machining of important parts, photo records should be prepared in triplicate to submit to the
responsible person.
1.7. Company-Supplied Materials Management: The contractor should submit the lists of companysupplied materials required for the construction along with sub-material lists to the responsible
person within 7 days before use and manage these materials thoroughly to prevent deformation or
damage when it stacks them for storage, and shall be responsible for all managerial problems in
relation to the supplied materials.
-A-252-
1.8. Quality Control Tests: Materials procured by the contractor should be tested in accordance with the
quality control test standards of the Company, and the results shall be submitted to the responsible
person.
1.9. Responsibility for Safety Accident: Safety measures should be established and managed to prevent
unexpected accidents during main construction, any accident should be immediately report to the
responsible person of the worksite, and the contractor shall be responsible for all safety accidents.
1.10. Steel fabrication: The contactor should prepare shop drawings for the approval from the responsible
person and then perform cutting and steel fabrication, and any materials in shortage shall be
procured in the contactors expense for re-machining.
1.11. Inspection: The responsible person and the inspector shall perform inspection and let failure items
re-inspected after correction and steel re-fabrication.
1.12. Painting: Remove rust and/or foreign materials from the items completed for inspection through shot
blasting, and then immediately apply antirust paint on them once.
1.13. Transportation of Finished Steel Structure to Field for Erection: Transport the machined materials in
the order of steel frame erection process to the erection field after the confirmation of the
responsible person on the entire marking lists, inspection sheets, and weight and packing lists.
Finished Steel Structure Transportation: Loading and unloading the machined materials shall be
conducted by contract, and the contractor shall be responsible for all defects such as deformation
and damage that occur during the period from machining shops to the completion of unloading and
should correct the defects or make compensation in the contractors expense.
1.14. Section Steel Fabrication: When section steel fabrication is necessary, do it in such a way that the
section steel can withstand various stresses just like the original materials (H-Beams, CT Bards,
etc.).
-A-253-
1.15. Surplus Material Treatment: When the difference between the weight (gross) of materials for steel
fabrication and the weight (net) of finished materials is within 10% (7%, 5%) of the weight of the
product, 70% of the difference shall be deducted from the contact value based on the market scrap
unit price, and the surplus amount shall be deducted from the contract value when it exceeds 10%
(12%, 15%).
1.16. Non-destructive test and X-ray test for deposition inspection on welded parts shall be performed on
the positions designated by the responsible person, and the following process shall be progressed
after the approval from the responsible person.
1.17. The contractor shall be wholly responsible for any defects such as contact of factory-machined
product with other materials, excess tolerance of bolt holes, and other defects in assembly, and/or
trouble in construction schedule thereby during steel frame erection at the field.
1.18. Oxygen: Oxygen shall be priced based on the contract price for each area.
1.19. Others
Costs for normal temporary assembly, test, and inspection are included in indirect expenses.
2. Materials
2.1. Steel Materials: Steel materials to be used for the construction conform to the below specifications in
accordance with design drawings and a straight figure without any defect or serious rust.
(1) Rolled Steel for Normal Structures ( JIS G 3101 or equivalent.)
Class
1
2
Material
SS 330
SS 400
SS 490
SS 540
Applications
Steel Plates, Flat Steel, Steel Round Bars, and Steel Strips
Steel Plates, Steel Strips, Section Steel, Steel Round Bars, and Flat Steel
Steel Plates, Steel Strips, Flat Steel, and Section Steel with Thickness of 40
mm or Less.
Steel Round Bars of Which Diameter, Side, or Distance to Opposite Side is 40
mm or Less.
-A-254-
Class
Material
Class
SM 520B
SM 520C
Steel Plates, Steel Strips, Flat Steel, and Section Steel with
Thickness of 200 mm or Less
Steel Plates, Steel Strips, and Section Steel with Thickness of 100
mm or Less
Material
SM 490A
(SWS490A)
SM 490B
(SWS490B)
SM 490C
(SWS490C)
SM 490YA
SM 490YB
SM 400A
(SWS400A)
SM 400B
(SWS400B)
SM 400C
(SWS400C)
Applications
SM 570
Applications
Steel Plates, Steel Strips, Flat Steel, and Section Steel with
Thickness of 200 mm or Less
Steel Plates, Steel Strips, and Section Steel with Thickness of 100
mm or Less
Steel Plates, Steel Strips, Flat Steel, and Section Steel with
Thickness of 100 mm or Less
Steel Plates, Steel Strips, Flat Steel, and Section Steel with
Thickness of 100 mm or Less
Steel Plates, Steel Strips, and Section Steel with Thickness of 100
mm or Less
Steel Plates, Steel Strips, and Section Steel with Thickness of 100
mm or Less
-A-255-
Table 1. Comparison of Standard Strength for Design between Normal Steel and TMCP Steel
Category
Standard
Strength for
Design
Fy(kg/)
Thickness
()
40 or Less
40-100
TS 50 Kg Class
Normal Steel
(SM490B)
(PILACW33A)
3,300
3,000
3,300
2/1
1.10
TS 53 Kg Class
Normal Steel
(SM490B)
(PILACW33A)
3,600
3,400
3,600
1.06
2.2. Bolts/Nuts
Refer to Section 3 of Chapter 10 Metallic Materials and Miscellaneous Works in KRAKATAU POSCO Standard
Construction Specifications.
-A-256-
Mother Material
Covering Material
Ilmenite Type
Lime Titania Type
Ductile Steel
Applications
Normal Structures
Thin Plates, Temporary
Welding
Thin Plates, Steel Pipes
Flat Welding
Vertical Welding
All Positions
All Positions
All Positions
Position
All Positions
Flat Welding
Vertical Welding
Flat Welding
Overhead Welding
All Positions
Rimmed
Steel
Killed Steel
Semi-Killed
Steel
Applications
Thickness
Flux
Remarks
Steel
Plates
SS400
SM400 (Rolled Steel for
Welded Structures)
6 m/m or Less
6 ~ 25m/m
GR50
GR50
NO.36,29
NO.43,36
Steel
Pipes
25m/m or Greater
Multi-Layer Welding
GR58
GR50
NO.36
NO.43
Steel
Pipes
6 m/m or Less
6 m/m or Greater
Multi-Layer Welding
GR50
GR20
GR50
NO.36,29
NO.36,29
NO.36
SM 490
Normal Structures, Welded
Structures
GR585
GR38
NO.36
High-Tension
Steel
3.2. Limitation to Length of Materials: In Complex: 17 m or Less, Other Districts: 12 m or Less, Height: 3.5
m or Less
3.3. Transportation: The length of a projected material from the edge of the loading bay should be within 1
m to prevent material deformation during loading, unloading, and transportation. In the event of a
-A-257-
unavoidable situation (length of 13 m or greater), use an auxiliary trailer for transportation and install
support timbers (95 mm x 90 mm) every 90 cm to prevent deformation.
3.4. Arrangement and Storage
(1) Arrange and store materials by figure (material and thickness for steel plates, section figure for section steel)
and identify different kinds of materials with symbols or colors to prevent confusion during machining.
(2) Place materials on support timbers to prevent contact with the ground and have the interval between the
timbers within 90 cm to prevent damage of materials by foreign materials such as corrosive materials, dirt,
and/or oil.
-A-258-
4.2. Reference Drawings: Indicate basic dimensions of the building (columns, spacing, beams, floor
height, etc.), standards for connections, and interaction with other constructions.
4.3. Detail Drawings: Indicate the shapes, dimensions, hole locations of all materials and joint figures and
quantity of gusset plates, etc.
4.4. Exploded Drawings: Necessary for steel frame erection at the worksite. Prepare exploded drawings
with entry of material numbers for each process agreed with the responsible person of the worksite
to prevent an error during steel frame erection.
-A-259-
-A-260-
8. Steel Fabrication
8.1. Cautions for Steel Fabrication
The responsible person shall take necessary actions after reviewing the followings in advance:
(1) Performance of steel fabrication, production capacity, and amount of contracted projects
(2) Equipment and facilities for steel fabrication, template shop for preparing full-size drawings
(3) Level of fabrication technologies and field work management
(4) Welding technologies, qualified welding technicians, welding equipment, and testing equipment
(5) Product transportation conditions
(6) Overall management system for steel machining
-A-261-
8.3. Material Correction: Use mechanical methods such as rollers, press machines, or benders for steel
material correction, and be careful not to give damage to the materials.
8.4. Steel Material Identification: Perform investigation on materials by location to use in accordance with
the specifications and identify those with different materials by symbol and color.
8.5. Marking-Off
(1) Check the material before marking-off and correct deformation areas of the materials, and then carry out
marking-off using a die plate and tools. The number of times to use a die plate shall be within 20.
(2) Machining methods and assembly guidelines should be fully considered for marking-off to prevent an error.
(3) Regular and other measuring devices for marking-off must be inspected to prevent an error.
(4) Marking-off must be applied to the center line or joint areas on cut out surfaces of the die plate (mockup
plate).
(5) Do not use files, drills, or center punches on the outer surface of steel plates and steel materials of SM 490
or higher for bending.
(6) Since welded structures are subject to contraction, marking-off should be performed after welding.
(7) Take inspection from the responsible person and the inspector for marking on important parts after
completion.
-A-262-
8.6. Cutting
(1) Steel cutting should be performed by the optimum methods including mechanical cutting, gas cutting, and
plasma cutting in consideration of shape and dimensions. The squareness to the axial line of finished
surface shall be within 1.5/1000.
(2) Manual cutting is not allowed except for minor construction.
(3) If there are teeth marks, cutting marks, wave patterns, or slag attachments on cut surfaces, remove them
with a grinder.
(4) Steel cutting dimensions should consider deformation by contraction and finishing.
(5) The precision degree of gas cut surfaces shall be within 100 Ry and notch depth shall be 1 mm or less.
(6) Devices used for cutting are as follows:
Kinds of Steel
Applicable Devices
Die Plate
Angular Cutter
Section Steel
Steel Plate (t 10)
Steel Plate (t 10)
8.7. Bending
(1) Cold working and hot working methods shall be used for bending. Hot working should not be performed in
blue brittleness state (200 ~ 400) but in red heat state (800 ~ 900). In addition, the temperature
condition shall be in accordance with 8.8 Deformation Correction Standards.
(2) The radius of inner bending in cold working shall be in accordance with the table below:
Table - Radius of Inner Bending in Cold Bending (Refer to the specifications of the Ministry of Construction &
Transportation)
-A-263-
-A-264-
Bolt Diameter
Hole Diameter
38 - 80
19 - 25
8.11. Beveling
Beveling on welded surfaces shall be performed basically with a gas cutting machine. Gouging method may be
used.
-A-265-
10. Welding
10.1. General
Welding is a method to assemble a product according to design drawings, and requires full understanding of
shop drawings and works including a variety of knowledge in the selection weld rods, shape of joint, safety rules
for welding, inspection and treatment after welding to complete construction in schedule.
-A-266-
Object Materials
Thin Plate
Steel Plate
6.0 or Less
Medium Plate
Steel Plate
4.5 - 25.0
Thick Plate
Steel Plate
16 or Greater
Steel Plate
Steel Plate
SMAW
Welding
Consumable
Electrode
-A-267-
Arc
Welding
Spot Welding
NonConsuma
ble
Electrode
Oxyhydrogen Welding
Gas
Welding
Oxy-Acetylene Welding
Air-Acetylene Welding
Spot Welding
Gas Pressure
Welding
Pressure
Welding
Electric
Resistance
Welding
Dual
Welding
Spot Welding
Projection Welding
Butt
Welding
Forge Welding
Upset Welding
Flash Welding
Tend Seam Welding
(1) Welding methods in the box of the chart above are widely used for steel frame construction.
(2) Gas welding can be used only for steel materials with thickness from 2.3 mm to 4 mm.
-A-268-
-A-269-
10.9. Welding
(1) Basically perform shop welding inside a house and ensure that welding is not affected by wind, snow, and/or
rain for outside welding.
(2) Stop welding when temperature is 0 or less.
-A-270-
-A-271-
10.12. Pre-Heating
Pre-heating shall be performed in accordance with below based on the kind of steel and the thickness of the
plate when required.
-A-272-
Table 10-16
Main Welding
Steel
Conditions
SM 400
SS 400
SM 490
A. Temperature of worksite is
5 or lower
B. Great Constraint
C. Plate thickness is 25 or
greater
A. Temperature of worksite is
10 or lower
B. Great Constraint
C. Plate thickness is between
25 m/m and less than 38
m/m
Plate thickness is 38 m/m or
greater
Pre-heating
Temperature
50 or Higher
50 or Higher
100 or Higher
Temporary Welding
Pre-heating
Conditions
Temperature
A. Temperature of worksite
is 5 or lower
B. Great Constraint
50 or Higher
C. Plate thickness is 25
or greater
A. Temperature of worksite
is 10 or lower
B. Great Constraint
50 or Higher
C. Plate thickness is
between 19 m/m and
less than 32 m/m
Plate thickness is 38 m/m
100 or Higher
or greater
-A-273-
Minimum Length
30 or Longer
40 or Longer
25 or Greater
50 or Longer
Basically, the interval of tack welding shall be 15 ~ 30 times of the plate thickness.
(5) Cautions
A. Tack welding on welded parts of important materials is prohibited. When tack welding on the backside is
inevitable, it should be done on the surface and gouged to the main welding line. In that case, the tack
welded area should be sufficiently welded during the main welding to prevent a welding defect, and
inspected by the responsible person.
B. If tack welding beads remain, gouging is essential to remove remains of tack welding. Pay attention to the
location of tack welding to prevent cutout of the mother material by damage.
C. For tack welding of thick plates (SM 490 and thickness of 25 mm or greater), use low-hydrogen welding
rods in case of SMAW.
-A-274-
10.16. Back Chipping: Perform back chipping with arc gouging for dual-axis butt welding. Back chipping
shall be made in such a way that one layer is removed from the surface or pure metal part of the
surface appears with same depth and width.
10.17. Wrap-Around Welding
Finish fillet welded ends with reverse or wrap-around welding.
-A-275-
Causes
Preventive Measures
A. Dry weld rods properly.
B. Use low hydrogen-type weld
rods.
C. Perform pre-heating and postheating.
D. Slow down welding speed and
avoid rapid cooling.
Causes
Mixture of Slag
Undercutt
A. Lower current.
B. Pay attention to welding rod
operation.
C. Make arc length appropriate.
D. Select an appropriate welding rod.
Overlap
-A-276-
Overlap
A. Increase current.
B. Increase welding speed.
C. Select an appropriate welding
rod.
Transverse
Crack
Longitudinal Crack
Causes
E. Dry enough.
Root Crack
Sulfur Crack
Sulfur Bent
End
Crack
Longitudinal
Crack
Bead
MillCrack
Root
Crack
-A-277-
Deposited
Metal
Longitudinal Section
A cavity formed by
welded metal trapped in
hydrogen or gas during
cooling of the metal.
Causes
Causes
Ice-Flower
Structure
Deposited
Metal
C. Mixture of slag.
-A-278-
-A-279-
Causes
1. Electric Shock
2. Optical
Disorder
Preventive Measures
A. Use an insulative holder.
B. Use a arc preventive device for arc
welders.
C. Wear insulative boots and gloves.
D. Apply insulation tape immediately to
damaged parts.
A. Use the appropriate No. of lightshielding lens for arc current.
B. Use a light-shielding plate or a tent.
C. Prohibit access by unauthorized
persons.
3. Toxication
4. Burn
A. Scattered spatter.
B. Contact with preheated mother
material.
5. Explosion
-A-280-
-A-281-
Category
Welded Angle
Root Gap
Manual
Automatic
Bead Gap
Manual
Automatic
1.0m/m
0.6m/m
Inspection Methods
Treatment
r-RAY Inspection
JIS Z 3104
Undercut, Overlap,
Wrong Bend, Pin Holes
Visual Inspection
Thickness of Layer in
Excess or Shortage
Various Inspection
Methods
-A-282-
-A-283-
When using the heating-cooling method, be careful not to arouse transformation of the material.
12.2 Air bubbles in the inner part should be revised using methods such as GOUGING and perform re-
welding.
12.3 Defects such as shortages in length through the naked eye should be repair-welded and treated with
GRINDER.
13. Assembling
13.1 Generals
(1) In assembling, check tools needed for the assembling process(surface plate, cramp, JAKC, etc) to secure
the accuracy of assembling.
(2) Before assembling steel materials, check the height and levelness of the assembling table to prevent any
errors.
(3) Parts which are rusty or impossible to paint after assembling should be checked beforehand and be coated
with paint.
(4) Other materials should be coded to prevent confusion in assembling.
(5) Temporary welding should avoid short bend and follow Number 4 of 10-16 of this specification.
-A-284-
Owner
Incoming
Construction
Name
Part Name
Construction
No.
Material
Quantity
Machine
No.
Inspection
Items
Issued on DD/MM/YY
Inspected on DD/MM/YY
Inspection
Place
-A-285-
Item
Location
Tolerance ()
Main
Column
- 2 = A = +4
2.0
2.5
Width of Flange
Height of Web
3
2
H = 500 + 300
H = 500 5
2.0
4.0
Column
Girder
Main Axis
H Section Steel
Check end areas.
2.0
2.0
/1500
2.0
2.0
2.0
3.5
2.0
/1000
1.5
2.0
Beam Height
Bending rate to Overall
Length
2.0
/1000
3.5
Web corridor
-A-286-
Figure
Tolerance
A. Length (L)
B. Bend
D/L = 1/1000
C. Height (H)
H < 400 2
400 < H < 1000
: H/200
H 1000
5
-A-287-
Dimension
Figure
Tolerance
D. Width (B)
E. Slope of
Flange at Joint
(e)
B200
eB/100
B200
e<2
F. Bending of
Flange at Joint
(e)
b100
eb/100
b100
e1
G. Eccentricity
(e)
e2
H. Angle of
Customized
Steel Frame
1/500
3 or less
I. Web Strength
(el/H, e2, B)
1 / 150
-A-288-
Dimension
Figure
Tolerance
J. Hole (Pitch)
K. Difference in
Hole Center (e)
L. Separation of
Rivet Head from
Center (e/d)
1/5
M. Rivet Head
Gap
Gap O
N. Gap between
Members Joined
with HighTension Bolt
O. Gap of Butt
Welding
e5
P. Gap of Dual
Welding
(e)
Q. Misalignment
of Groove (P)
Welded Parts (e)
t15 : 1.5
15 t 30
: t/10
t30 : 3
a1 = 3 or less
a2 = 4 or less
-A-289-
Dimension
Figure
Tolerance
S. Root Gap
(for Back
Support) (a)
+5
-0
T. Root Surface
(a)
a3 mm1 mm
a3 mm2 mm
U. Side Wall
Angle (a1, a2)
-O
+ 10
V. Gap with
Bottom Support
Steel
W. Fillet Welding
Size (s)
+3
-O
-0.1 S is acceptable for
10% or less of welding
length.
X. Overlap for
Butt Welding
Y. Undercut (e)
Z. Bead Surface
Treatment
A) Difference of elevation
of bead surface: 2.5 mm /
150 mm of welding length
B) Difference in bead
width: 5 mm or less per
150 m/m of welding
length
-A-290-
-A-291-
18. Paint
18.1 Surface Preparation
Applying paint, the surface shall be prepared as required by SSPC - SP6, commercial blast cleaning.
-A-292-
-A-293-
d) Tests for selection and control of the above mentioned coats shall be in accordance with ASTM
Standards.
E. Heat Resistant Paint
-A-294-
Type
Set to Touch
Semi Hard
Minimum
Maximum
5 C
60 Minutes
3 Hours
48 Hours
6 Months
20 C
30 Minutes
2 Hours
24 Hours
6 Months
30 C
10 Minutes
1 Hour
12 Hours
6 Months
40 C
5 Minutes
45 Minutes
8 Hours
6 Months
-A-295-
c) Others
Substrate treatment level and coating thickness maintenance should be confirmed by the
responsible person to secure coating quality.
Heat resistant thinner should be used for dilution, and cleaning of substrates and coating devices.
c) Coating Specifications
- Dry Film Thickness: 150/Time X 2 Times
-A-296-
-A-297-
-A-298-
Measuring
Point
2 or more
4 or more
6 or more
8 or more
10 or more
10000 or more
14 or more
-A-299-
Ultra-High
Buildings
Normal
Buildings
Factory
Buildings
Gymna
siums
Steel Plants,
Power
Plants
Steel Pipe
Structures
Average
Loading
Factor
75
70
60
65
80
50
Remarks
Stack
Structures
(4) Fasten common bolts ( 16) to splice plates and gusset plates to prevent separation during transportation.
(5) Prepare protection measures when using wire ropes or hooks for loading / unloading.
(6) Use shock absorbing materials to prevent damage on coating by contact between materials.
(7) Do not use steel wires when attaching sub materials to main materials for transportation.
-A-300-
-A-301-
(i) Etc
-A-302-