SSR 16-17
SSR 16-17
SSR 16-17
Part 1
and
The annual Board of Chief Engineers meeting for finalization of Schedule of Rates (SoR)
for WR Dept. (Part-I), Road & Bridges (Part-II) and Public Health Items (Part-IV) was held on
16.07.2016 @ 3.00 PM and approved the SoR . Based on the approval of BoCEs, the SoR for WR
Dept. (basic input required for arriving unit item rate as per A.P. Revised Standard data), R&B
and Public Health Department items were communicated vide this office proceedings 3rd
cited.
By incorporating approved Labour, Material and Hire Charges for SoR 2016-17 &
Percentage Provision of 13.615% towards Contractors profit and overhead charges in the items,
the A.P. Revised Standard Data (unit rate for work items) for the year 2016-17 is finalized. Any
additions, modifications or deletions in the existing data must be approved by BoCEs. One soft
copy is herewith enclosed.
Encl: Soft copy of A.P. Revised Standard Data for WR Department for the year 2016-17
Sd/-M.V.Ravi Kumar,dt:26.07.2016,
Engineer-in-Chief(I.W.)
Chairman, BOCE(SoR)
Sd/-M.V.Ravi Kumar,dt:26.07.2016,
Engineer-in-Chief(I.W.)
Chairman, BOCE(SoR)
code and index for work items of standard data
PART-1 IRRIGATION
Abstract of Items - Irrigation 1-45
Abstract of Leads and Lifts 46-47
IRR-DAW Dam And Allied Works (48-99)
IRR-DAW-1 EXCAVATION & FOUNDATION TREATMENT WORKS: 48-58
IRR-DAW-2 REINFORCEMENT & CEMENT CONCRETE WORKS : 58-74
IRR-DAW-3 MASONRY & GUNITING WORKS : 74-80
IRR-DAW-4 CONTRACTION JOINT WORKS: 80-83
IRR-DAW-5 EARTH / ROCKFILL EMBANKMENT WORKS : 83-91
IRR-DAW-6 FILTER & PITCHING WORKS : 91-99
COM-LDLFT-2 344-344
LOADING AND UNLOADING CHARGES BY MANUAL
COM-LDLFT-3 MEANS (Idle hire charges of trucks are not added) 345-345
LOADING AND UNLOADING CHARGES BY MANUAL
COM-LDLFT-4 MEANS (including idle hire charges of trucks ) 345-345
LOADING AND UNLOADING CHARGES BY MECHANICAL
MEANS (including idle hire charges of trucks )
COM-LDLFT-5 345-345
COM-LDLFT-6 LIFT CHARGES FOR MATERIALS BY HEAD LOAD 345-345
COM-DTL-LDLFT-1 (Lead) Conveyance Charges for materials by head load 346-347
( Lead) Conveyance charges for machinery per kilometer for
transporting materials by tippers and trucks, excluding
loading, unloading and hire charges of machinery.
COM-DTL-LDLFT-2 347-353
LOADING AND UNLOADING CHARGES BY MANUAL
COM-DTL-LDLFT-3 MEANS (idle hire charges of trucks are not added) 353-354
LOADING AND UNLOADING CHARGES BY MANUAL
COM-DTL-LDLFT-4 MEANS (including idle hire charges of trucks ) 354-355
LOADING AND UNLOADING CHARGES BY MECHANICAL
MEANS (including idle hire charges of trucks )
COM-DTL-LDLFT-5 355-356
COM-DTL-LDLFT-6 LIFT CHARGES FOR MATERIALS BY HEAD LOAD 356-357
Hire Charges 358-359
A.P. REVISED STANDARD DATA
PREAMBLE
The AP Revised Standard data for various construction items has come into existence as
per the Government orders G.O.Ms.No.49, I & CAD (PW: Reforms) Dept., dt:.2-3-2009.
1. Government, in GO 7326 (GAD-GPM& AR), Dated 26-10-2005, has observed that the
age old Standard data requires revision and updation with reference to the latest
machinery and contemporary practices and has constituted a High Level
Committee to advise on updating and revision of standard data and schedule of
rates. The work has been taken up by CGG and SPIU-irrigation. The secretary
(Irrigation) is the member- convener of the committee
Accordingly the data has been revised adopting the procedures and
guidelines given by CWC, Report on committee on cost control of river valley Projects,
BIS specifications, NHAI, MORTH, MORD, CPWD and Government of Karnataka and
revised data and formulated schedule of rates for all infrastructure Departments
(I&CAD, R&B, PR and PH). The team of senior engineers interacted with the S.R
Committee of Karnataka on implementation and improvements needed. For irrigation
works, the data pattern as adopted by Karnataka has been considered and for other
Departments, the data adopted by MORTH,MORD and NHAI etc. is adopted
i
3. The Detailed draft data was communicated to all the HODs and interacted
through many seminars and discussions and incorporated the relevant
features. The Board of chief engineers in their meetings have recommended
for acceptance to the data formulated and schedule of rates. It was proposed
to examine the recommendations on important parameters, to refer to high
level committee, for their specific recommendations for adoption, as they are
common to all departments.
The committee made in depth study on the methodology and systems
followed by the reputed National organizations and other States and made
detailed deliberations with HODs and representatives of Builders Association of
India and made recommendations to the Government, on adoption of such
parameters in A.P.
ii
GUIDELINES
1) The Revised Standard Data is formulated under four Parts, which are applicable to all
the Engineering Departments and other Organisations.
PART -1: Irrigation& CAD (Dam and Allied Works, Canals and Allied Works,
Canal C.D. Works, Tunnels and Allied Works, Preliminary and
Maintenance Works, Hydraulic Gates and allied works and Leads and
Lifts applicable to all Departments
PART -2: Roads and Bridges
PART -3: Buildings including Electrical Works
PART -4: Drinking Water Supply and Public Health (ONLY FOR WORKS
DONE BY MANUAL MEANS)
iii
equipment planning and utilisation. The daily out-put is computed duly considering the
actual available working time and feed back from the field.
For gate and hoist works, it is the general practice to specify the quantity of
work in terms of number of sets of embedded parts / gates. The requirement of
machinery and work-force for cutting, bending, fabrication, erection, painting
etc., is assessed to commensurate with the task involved.
The data for gates and E.M. Parts is arrived per Ton quantity.
The data for Hoists and Gantry Cranes is worked out on the basis of capacity in
tonnage
4) The lead and lift charges provided in PART-I (B) are generally applicable and common
to all Departments. Any item is not covered in this part, the rates as provided in the
data of the relevant works may be adopted in preparation of estimates.
5) The basic material inputs needed for all works are listed and incorporated in the data.
The requirements are analyzed and the specifications adopted shall confirm to
Standards published by the BIS.
The labour and material rates will be communicated by the Board of Chief
engineers.
Unless otherwise specified, all material rates shall be inclusive of all taxes,
duties, levies, transportation and handling costs up to project area.
For sand, gravel , murum, stones , course aggregates etc, the rates are to be
fixed for delivery at Quarry, adding loading charges by machinery / manual
means and idle hire charges of machinery (as per table under chapter
conveyance or lead and lift charges), as applicable.
For steel, Cement, AC sheets, GI sheets, Hume pipes, wood and stone slabs, the
rates are to be taken prevailing at major commercial centre near project area.
The lead charges, as applicable are to be added in preparing estimates.
The specifications of the aggregates for sizes and gradation and its adoption
shall be as per IS 383.
iv
6) The labour component in the data is mentioned for unit work.
No allowance towards labour importation and labour amenities added extra as
they are included in the recommended overheads.
On Labour Component: Certain additional allowances are added extra to the
wages of labour (,i.e. only on labour component in the work item) in the form
of percentage, as recommended by the Government/Board of chief engineers
due to statutory and other provisions.
However, If more than one area allowances, such as those for (1) Municipalities
(2) Agency / Tribal areas (3) Industrial areas are applicable for a particular
situation, only the maximum out of the allowable percentages is to be allowed.
8) Lead Charges
The high level committee has recommended to adopt, for conveyance by head
load, a minimum lead of 50 meters and additional lead up to 150 meters in the
intervals of 50 meters. Beyond 150 meters lead, only machinery rates are to be
adopted.
The basic work item rates provided in the Standard Data & Schedule of rates
include 50 m or 1 km as initial lead and no lead charges shall be allowed where
the source of material is within the initial lead specified in item rate. Additional
lead charges shall be allowed for the lead exceeding initial lead specified in the
v
item rate. The Guidelines may be followed regarding adding Lead charges as
given against each chapter.
The lead charges per unit quantity for conveyance of the materials are worked
out, and included in the schedule of rates in increment of 50 m for head load
and in increment of 1 km for mechanical mode.
The rates for lead charges by head load up to 150 meters and by machinery up
to 5 km, shall be cumulative and inclusive of lead charges for preceding lead.
For lead beyond 5 km, the lead charges shall be worked out on per km basis.
The data includes initial lift charges of 3 meters ,for materials conveyance by
head load, Additional leads in the interval of 1.0 meters are worked out, as
additional labour input and incorporated in the chapter on Lead and lifts .
Where the conveyance / lifting of material is done by mechanical means, lift
charges shall not be considered, as the cycle time of operation of the machine
includes lifts involved.
The data and rates for lift charges is cumulative and are inclusive of rates for
preceding lifts also.
vi
II) steel: The wastage of steel @ 2.5% is allowed for gates and allied
structures. For RCC works the wastage is @2.5% for the reinforcement rods
above 36mm dia. and @ 5% for rods below 36mm dia. including overlaps, if
they are not welded. If welding is adopted for the reinforcement rods even for
below 36mm dia, 2.5% of wastage is only recommended.
13)In respect of RCC works the rate for cement concrete for 1 cum is worked separately
for all grades based on Indian Standards. The rate for ton is calculated separately and
to be added separately in the estimates of RCC works as a separate item.
1. all soils
2. Marshy soil
3. ordinary rock ( not requiring blasting),
4. hard rock
a. hard rock (requiring blasting)
b. hard rock (controlled blasting)
c. removable by chiseling(blasting prohibited)
Concrete admixtures such as Air-Entraining Agent ( AEA ) / Water reducing agent can be
used advantageously for better quality concrete. The high level committee has
recommended to adopt for super plasticizers and admixtures at 0.4% on cement for
concrete work as per MORTH standards for batching plants.
vii
16) Contractors overheads, profit and other provisions:
High Level Committee has recommended adding 14% towards contractor overheads
and profit including labour importation and amenities etc., as given below which
includes various items recommended in MORTH.
The provision for VAT at 5% or as fixed by the Government from time to time should
be made separately in Part-B of the estimate. In the agreements it should be
mentioned that it will be reimbursed as per actual. The provisions allowed in
G.O.Ms.No.94, I&CAD, dt: 01.07.03, need not be added separately for the items covered
in the contractor overhead charges.
The provision for labour Cess at 1% or as fixed by the Government from time to time
should be made separately in Part-B of the estimate.
The overhead charges include the following elements:
Site accommodation, setting up plant, access road, water supply, electricity and
general site arrangements.
Office furniture, equipment and communications
Expenditure on:
Corporate office of contractor
site supervision
Documentation and as built drawings
Mobilisation/ de-mobilisation of resources
Labour camps with minimum amenities and transportation to work sites.
Light vehicles for site supervision including administrative and managerial
requirements.
Laboratory equipment and quality control including field and laboratory testing.
Minor T & P and survey instruments and setting outworks, including verification of line,
dimensions, trial pits and bore holes, where required.
Watch and ward
Traffic management during construction
Expenditure on safeguarding environment
Sundries
Financing Expenditure
Sales/ Turn overtax
viii
Work Insurance/ compensation
In respect of gates, hoists and allied works, excise duty is applicable on the
value of fabricated components supplied to site. Excise duty is not applicable on erection
charges. Further, the excise duty shall not be considered in the rate analysis on material
component, as basic material rates are inclusive of excise duty.
Therefore, excise duty is considered in the rate analysis only on machinery and
labour components required for fabrication of gates and hoists at the central fabrication
yard. It is difficult to determine the machinery and labour components separately for
fabrication and erection.
For the purpose of computation of excise duty to be included in the rate analysis the
machinery and labour components may apportioned at 75 % for central fabrication yard
and 25 % for field erection and commissioning. Therefore, 75 % of the machinery and
labour components may be considered for assessing the extent of excise duty to be added
in the rate analysis.
18) DEWATERING & DESILTING:
The High level committee considering the local conditions of rainfall / seepage has
recommended towards de-watering and de-silting at 3 percent on the relevant work
component for which dewatering is required.
It is also proposed as per CWC guidelines, to keep a condition in the agreements shall be
incorporated, to fix a ceiling of 5% in extreme cases, with the specific approval of chief
engineer/Government.
19) Computerization Of Data :
ix
USER GUIDELINES OF REVISED STANDARD DATA
1. Please select the item of work, as given in Index Code, and view the relevant
data.
2. The common data items like, lead, lift, conveyance and manual excavation
(without involving contracting agencies ) is applicable to all Departments
(Volume-1)
3. The departments have to adopt the relevant data from other Departments, if
such works are executed by them.
4. The unit rate /hire charges, of machinery not covered in the Irrigation data,
the
MORTH data may be taken with the approval of Board of Chief Engineers.
x
5. ROLE OF CENTRAL COMPETENT AGENCY FOR SCHEDULE OF RATES
( BOARD OF CHIEF ENGINEERS)
a) The Board of Chief Engineers under the chairman ship of Engineer-in- chief,
(administration) I&CAD Department is the competent authority to finalise and
recommend the Schedule of Rates applicable for all engineering Departments. The
board has to assess and incorporate only the three basic inputs required to generate
unit work item rates as below.
Materials rates:
The basic input material rates common to all departmental works are listed out
and incorporated (in the chapter Basic inputs) The material specifications adopted
shall confirm to Standards published by the BIS.
The Prevailing market rates for all basic input materials shall be obtained from
the major commercial centers near the project areas. Average of the rates, ignoring
freak rates, shall be reckoned as the prevailing market rate.
Unless otherwise specified, all material rates shall be inclusive of all taxes,
duties, levies, royalty, transportation and handling costs up to project area.
For sand, gravel, murrum, stones, aggregates etc, the rates are for delivery at
Quarry including loading charges and idle hire charges. For steel, Cement, AC sheets,
xi
GI sheets, Hume pipes, wood and stone slabs, the rates prevailing at major
commercial centre near project area has to be adopted.
He shall communicate the uniform Schedule of rates arrived from Standard Data,
to all users for uniform and direct adoption in all infrastructure Departments, as
applicable
xii
Abstract of work items_UNit Rates for the year 2016-17
1
Abstract of work items_UNit Rates for the year 2016-17
Preparing foundation bed for cut-off trench filling in rock portion by removing
IRR-DAW-1-8 9 all loose materials by wedging / chiselling and disposing off the same as directed sqm 26.10
etc., complete with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads) sqm 26.10
The item rate for drilling through rock / masonry / concrete includes redrilling
through partially set grout, if any, in the portion of the hole drilled and grouted.
Flushing grout holes of all sizes with water and air jets alternatively for an
IRR-DAW-1-10 11 average period of 30 minutes including water intake observations after flushing, Rm 47.40
cost of all materials, machinery, labour etc., complete.
Labour Component (including contractor's profit and Overheads) Rm 20.00
Curtain grouting with neat cement grout mix of suitable consistency under
IRR-DAW-1- specified pressure as directed in drilled holes by stage grouting method including
13 tonne 11315.20
12(b) cost of all materials, machinery, labour, redrilling if necessary etc., complete with
initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads) tonne 4150.10
Providing and fixing 25 mm dia 3 m long cold twisted deformed steel dowel
bars with one end driven into 45 to 50 mm diameter 1.50 m deep hole drilled in
bed rock and other end provided with L-bend for embedding in concrete /
IRR-DAW-1-13 14 masonry of over flow / non-over flow blocks and other appertenant works Each 841.00
including cost of drilling and cleaning hole, filling hole with cement mortar 1 : 1
proportion, driving anchor rod, cost of all materials, machinery, labour etc.,
complete with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads) Each 119.20
Providing and fixing 25 mm dia. 2.75 m long ribbed steel anchor rods with
one end split and driven firmly using steel wedge into 1.25 m deep 45 to 50 mm
dia. hole drilled in bed rock and other end provided with L- bend for embedding
IRR-DAW-1-14 15 in concrete / masonry for spillway and appurtenant works including drilling and Each 780.50
cleaning hole, filling hole with thick cement slurry, driving anchor rod, cost of all
materials, machinery, labour, steel wedge etc., complete with initial lead upto 1
km and all lifts.
Labour Component (including contractor's profit and Overheads) Each 134.90
2
Abstract of work items_UNit Rates for the year 2016-17
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength
not less than 15 N / sq mm ) grade cement concrete using 80 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
IRR-DAW-2-2 18 cum 3668.40
placing in position, levelling, vibrating, finishing, curing etc.,complete for plain
concrete works with initial lead upto 1 km and all lifts. ( Cement content : 250
kg /cum with use of super plasticiser equla to 0.4% of cement content, CA :
0.98 cum, Blending Ratio of CA -- 40:30:20:10, FA : 0.35 cum ))
Labour Component (including contractor's profit and Overheads) cum 187.40
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sq mm ) grade cement concrete using 80 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
IRR-DAW-2-2A
machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
(new Item1 2010- 19 cum 3925.60
placing in position, levelling, vibrating, finishing, curing etc.,complete for plain
11)
concrete works with initial lead upto 1 km and all lifts. ( Cement content : 300
kg /cum with use of super plasticiser equla to 0.4% of cement content, CA :
0.90 cum, Blending Ratio of CA -- 40:30:20:10, FA : 0.4 cum ))
Labour Component (including contractor's profit and Overheads) cum 187.40
Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength
not less than 10 N / sq mm ) grade cement concrete using 80 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
IRR-DAW-2-3 20 cum. 3463.50
placing in position, levelling, vibrating, finishing, curing etc.,complete for plain
concrete works with initial lead upto 1 km and all lifts. ( Cement content : 220
kg /cum with use of super plasticiser, CA: 0.98 cum, Blending Ratio of CA --
40:30:20:10, FA: 0.37 cum )
Labour Component (including contractor's profit and Overheads) cum. 187.40
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
IRR-DAW-2-4 21 placing in position, levelling, vibrating, finishing, curing etc.,complete for RCC cum. 4902.60
works of gallery, sluice, spillway crest, spillway d / s face, energy dissipating
structures, training walls, piers, abutments and such other locations with initial
lead upto 1 km and all lifts. ( Cement content : 310 kg / cum with use of super
plasticiser, CA : 0.90 cum, blending ratio of CA--50:30:20, FA : 0.40 cum)
Providing and laying insitu vibrated M-25 ( 28 days cube compressive strength
not less than 25 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
IRR-DAW-2-4A
machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
(new Item2 2010- 22 cum. 5249.10
placing in position, levelling, vibrating, finishing, curing etc.,complete for RCC
11)
works of gallery, sluice, spillway crest, spillway d / s face, energy dissipating
structures, training walls, piers, abutments and such other locations with initial
lead upto 1 km and all lifts. ( Cement content : 360 kg / cum with use of super
plasticiser,CA : 0.90 cum, blending ratio of CA--50:30:20, FA : 0.40 cum)
Labour Component (including contractor's profit and Overheads) cum. 372.10
Providing and laying insitu vibrated M-25 ( 28 days cube compressive strength
not less than 25 N / sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
IRR-DAW-2-4B
machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
(new Item3 2010- 23 cum. 5361.10
placing in position, levelling, vibrating, finishing, curing etc.,complete for RCC
11)
works of gallery, sluice, spillway crest, spillway d / s face, energy dissipating structures,
training walls, piers, abutments and such other locations with initial lead upto 1 km
and all lifts. ( Cement content : 380 kg / cum with use of super plasticiser,CA : 0.90
cum, blending ratio of CA--65:35, FA : 0.40 cum)
Labour Component (including contractor's profit and Overheads) cum. 372.10
3
Abstract of work items_UNit Rates for the year 2016-17
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength
not less than 15 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
IRR-DAW-2-5 24 cum. 4597.40
placing in position, levelling, vibrating, finishing, curing etc.,complete for plain
concrete works with initial lead upto 1 km and all lifts. ( Cement content : 260
kg /cum with use of super plasticiser,CA : 0.90 cum, Blending Ratio of CA --
50:30:20, FA : 0.40 cum)
Labour Component (including contractor's profit and Overheads) cum. 1341.20
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength
not less than 15 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates with placing and sinking plums of size
150 to 80 mm upto 15 percent for gravity type structures including cost of all
IRR-DAW-2-6 25 materials, machinery, labour, formwork, scaffolding, cleaning, batching, mixing, cum. 4485.70
placing in position, levelling, vibrating, finishing, curing etc.,complete with initial
lead upto 1 km and all lifts. ( Cement content : 260 kg / cum of concrete with
use of plums and super plasticiser,, CA : 0.77 cum, Blending Ratio of CA :
50:30:20,FA : 0.34 cum, plums of size 150 to 80 mm : 0.25 cum)
Labour Component (including contractor's profit and Overheads) cum. 1310.20
Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength
not less than 10 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
IRR-DAW-2-7 26 cum. 4207.50
placing in position, levelling, vibrating, finishing, curing etc.,complete for plain
concrete works with initial lead upto 1 km and all lifts. ( Cement content 220
kg /cum with use of super plasticiser,CA : 0.90 cum, Blending Ratio of CA :
50:30:20, FA : 0.40 cum )
Labour Component (including contractor's profit and Overheads) cum. 1214.40
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength
not less than 15 N / sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
IRR-DAW-2-8 27 cum. 4470.60
placing in position, levelling, vibrating, finishing, curing etc.,complete for plain
concrete works with initial lead upto 1 km and all lifts. ( Cement content : 280
kg /cum with use of super plasticiser,CA : 0.80 cum, Blending Ratio of CA --
65:35, FA : 0.44 cum)
Labour Component (including contractor's profit and Overheads) cum. 1243.60
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
IRR-DAW-2-9 28 placing in position, levelling, vibrating, finishing, curing etc.,complete for RCC cum. 6262.70
works of spillway bridge, blockouts and such other similar structures with
conjested reinforcement with initial lead upto 1 km and all lifts. ( Cement
content : 330 kg / cum with use of super plasticiser, CA : 0.80 cum, Blending
Ratio of CA -- 65:35, FA : 0.44 cum).
Labour Component (including contractor's profit and Overheads) cum. 1760.90
Providing and forming porous concrete body drain of size 68.5 x 68.5 cm with 23
cm diameter central hole using cement and 20 mm down approved, clean, hard,
graded coarse aggregates in 1 : 3.50 proportion by volume including cost of all
IRR-DAW-2-10 29 Rm 2470.70
materials, machinery, labour, formwork, curing etc., complete with initial lead
upto 1 km and all lifts.(M15 Cement content : 400kg/cum, CA : 1cum, Blending
Ratio of CA -- 65:35)
Labour Component (including contractor's profit and Overheads) Rm 604.40
4
Abstract of work items_UNit Rates for the year 2016-17
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc.,complete for RCC
solid parapet consisting of 35 cm x 20 cm kerb, 35 cm x 35 cm x 1 m pillars
IRR-DAW-2-
30 spaced approximately at 3.35 m c / c, 12.5 cm thick wall 80 cm height with 12.5 Rm 2328.30
11(a)
cm thick and 35 cm wide coping slab for wall and 12 .5 cm thick 40 cm x 40 cm
coping for pillars with top edges of kerb and coping chamferred / rounded as
directed etc., complete ( excluding cost of providing and placing
reinforcement steel and gate ) with initial lead upto 1 km and all lifts. (
Cement content 350 kg / cum with use of super plasticiser( 0.4% by wt.of
cement), CA : 0.80 cum, Blending Ratio of CA--65:35, FA : 0.44 cum)
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc.,complete for RCC
ornamental parapet consisting of 35 cm x 20 cm kerb, 35 cm x 35 cm x 1 m
IRR-DAW-2-
31 pillars spaced approximately at 3.5 m apart, 20 cm x 15 cm posts 80 cm height Rm 2376.30
12(b)
approximately 30 cm c / c with 12.5 cm thick and 35 cm wide coping slab for
posts and pillars with top edges of kerb and coping chamferred or rounded as
directed etc., complete ( excluding cost of providing and placing reinforcement
steel and gate ) with initial lead upto 1 km and all lifts. ( Cement content : 350
kg / cum with use of super plasticiser, CA : 0.80 cum, Blending Ratio of CA--
65:35, FA : 0.44 cum)
Labour Component (including contractor's profit and Overheads) Rm 795.50
Providing and laying insitu M- 25 ( 28 days cube compressive strength not less
than 25 N / sq mm ) grade cement concrete using 20 mm down size approved,
clean, hard, graded aggregates for wearing coat including cost of all materials,
machinery, labour, formwork, cleaning, batching, mixing, placing in position in
IRR-DAW-2-13 32 cum 5244.60
alternate panels, levelling, compacting, finishing, curing, packing joints with
asphalt mortar etc., complete with initial lead upto 1 km and all lifts. ( Cement
content : 380 kg / cum with use of super plasticiser, CA : 0.80 cum, Blending
Ratio of CA--65:35, FA : 0.45 cum)
Labour Component (including contractor's profit and Overheads) cum 1509.70
Conveying and fixing elastomeric bearing for spillway bridge including cleaning
and preparing surface, mixing and applying adhesive, fixing bearing in correct
IRR-DAW-2-15 34 Each 374.20
position etc., including cost of all materials except bearings, machinery, labour
etc., complete with all leads and lifts.
Labour Component (including contractor's profit and Overheads) Each 321.90
Providing and constructing 150 mm dia hume pipe weep holes for concrete /
masonry walls including providing 20 x 20 x 20 cm size porous concrete block
IRR-DAW-2-16 35 made of cement and 20 mm down coarse aggregate in 1 : 4 proportion Rm 383.80
including 10 cm thick sand backing at the junction of wall and soil back fill, cost of
all materials, machinery, labour etc., complete with lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads) Rm 71.00
5
Abstract of work items_UNit Rates for the year 2016-17
Providing and constructing coursed rubble face stone masonry using approved
rubble stones in cement mortar 1 : 3 proportion including cost of all materials,
machinery, labour, scaffolding, ramps, cleaning, packing mortar, wedging stone
IRR_DAW-3-3 39 chips, curing etc., with initial lead upto 1 km and all lifts.( Thickness of the CR cum 3032.40
face assumed: 0.75 m, Cement content : 178 kg/cum of masonry, rubble stones
: 0.35 cum, stone chips : 0.15 cum/cum, FA : 0.375 cum, CR stones 30 x 30 x 45
cm : 9.75 No, CR stones 30 x 30 x 60 cm : 3.25 No)
Labour Component (including contractor's profit and Overheads) cum 1265.80
Providing and constructing coursed rubble face stone masonry using approved
rubble stones in cement mortar 1 : 4 proportion including cost of all materials,
machinery, labour, scaffolding,ramps, cleaning, packing mortar, wedging stone
IRR_DAW-3-4 40 chips, curing etc., with initial lead upto 1 km and all lifts. ( Cement content : cum 2764.90
134 kg/cum of masonry, rubble stones : 0.35 cum, stone chips : 0.15 cum/cum,
FA : 0.375 cum, CR stones 30 x 30 x 45 cm : 9.75 No, CR stones 30 x 30 x 60 cm :
3.25 No)
Labour Component (including contractor's profit and Overheads) cum 1265.80
Providing and constructing chisel drafted and hammer dressed face stone
masonry with approved stones in cement mortar 1 : 3 proportion including
cost of all materials, machinery, labour, scaffolding, ramps, cleaning, packing
IRR_DAW-3-5 41 mortar, wedging stone chips, curing etc.,complete with initial lead upto 1 km cum 3253.50
and all lifts.( Cement content : 167 kg/cum of masonry, rubble stones : 0.35
cum, stone chips : 0.15 cum/cum, FA : 0.35 cum, Dressed stones 30 x 30 x 45
cm : 10 No, Dressed stones 30 x 30 x 60 cm : 3.40 No)
Labour Component (including contractor's profit and Overheads) cum 1548.90
Providing and constructing chisel drafted and hammer dressed face stone
masonry with approved stones in cement mortar 1 : 4 proportion including
cost of all materials, machinery, labour, scaffolding, ramps, cleaning, packing
IRR-DAW-3-6 42 mortar, wedging stone chips, curing etc.,complete with initial lead upto 1 km cum 2998.20
and all lifts.( Cement content : 125 kg/cum of masonry, rubble stones : 0.35
cum, stone chips : 0.15 cum/cum, FA : 0.35 cum, Dressed stones 30 x 30 x 45
cm : 10 No, Dressed stones 30 x 30 x 60 cm : 3.40 No)
Labour Component (including contractor's profit and Overheads) cum 1548.90
6
Abstract of work items_UNit Rates for the year 2016-17
Providing cut-off trench filling using selected impervious soil from approved
borrow areas in layers of 25 to 30 cm before compaction including cost of all
materials, machinery, labour, all operations such as excavation, sorting out,
IRR-DAW-5-2 51 transportation, spreading soil to specified thickness, breaking clods, sectioning, cum 148.70
watering, compacting to density control of not less than 95 percent using Sheep
foot roller / Vibratory roller/ 8 to 10 tonne power roller as stipulated etc.,
complete with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads) cum 24.10
7
Abstract of work items_UNit Rates for the year 2016-17
Providing and constructing dry rubble rock-toe using rubble and stone chips
from approved source including cost of all materials, machinery, labour, hand
IRR-DAW-5-8 58 cum 511.30
packing rubble and stone chips, finishing top and sides to required slopes etc.,
complete with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads) cum 211.60
Providing and constructing dry rubble rock-toe with rubble and stone chips
from dump yard including cost of all materials, machinery, labour, hand packing
rubble and stone chips, finishing top and sides to required slopes etc., complete
with initial lead upto 1 km and all lifts.
IRR-DAW-5-9 59 cum 464.10
Note: Useful rubble and stone chips will be issued at dump yard at the issue rate
for usefull rubble /stone chips. Sorting out and breaking charges included in rate
analysis.
Labour Component (including contractor's profit and Overheads) cum 147.00
Providing and constructing Dry rock Pitching for Groynes using Un-Coursed
IRR-DAW-5-9-A rubble stone of size 300 mm thick and Un-Coursed rubble stone chips from
(New Item4-2012- 60 Quarry to site of work including cost of all materials, Machinery, Labour charge cum 677.40
13) hand packing Un-Course rubble stone &chips to the designed profile with all
leads and lifts etc
Labour Component (including contractor's profit and Overheads) cum 147.00
Providing and laying 30 cm diameter open jointed hume pipes with collars in
IRR-DAW-5-10 61 rock-toe for drainage including cost of all materials, machinery, labour etc., Rm 714.60
complete with lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads) Rm 32.90
8
Abstract of work items_UNit Rates for the year 2016-17
Providing and constructing longitudinal and cross graded filter drains using
sand and 80-20 mm and 20 mm down graded aggregates satisfying specified
IRR-DAW-6-2 63 filter creteria in layers as per specifications including cost of all materials, cum 790.20
machinery, labour, laying to required slopes, compaction etc. complete with
initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads) cum 156.20
Providing and constructing graded filter media below and behind rock-toe
consisting of 20 cm thick sand, 25 cm thick 20 - 4.75 mm and 40 cm thick 80 -
IRR-DAW-6-4 65 20 mm size graded coarse aggregates satisfying filter creteria as per cum 923.70
specifications including cost of all materials, labour, machinery, laying to required
slope, compaction etc., complete with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads) cum 140.30
Providing and constructing graded filter media below and behind rock-toe
IRR-DAW-6-4-A consisting of 30 cm thick, 80 - 20 mm size graded coarse aggregates
(New Item2 2011- 66 satisfying filter creteria as per specifications including cost of all materials, cum 1166.30
12) labour, machinery, laying to required slope, compaction etc., complete with
initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads) cum 52.80
Providing and laying filter media consisting of 2 layers of 250 gsm poly-
propeline non-woven filter fabric and 400 mm thick 20 mm down graded
IRR-DAW-6-5 67 coarse aggregate for vertical / inclined and horizontal filter blanket for sqm 955.50
embankment including cost of all materials, machinery, labour etc., complete
with lead upto 50 m for aggregate and all leads for fabric and all lifts.
Labour Component (including contractor's profit and Overheads) sqm 60.80
9
Abstract of work items_UNit Rates for the year 2016-17
Providing and constructing 60 cm thick hand packed rough stone riprap over
a backing of 45 cm thick graded filter media consisting of sand, 10 mm and 40
mm size graded approved aggregates laid in layers of 15 cm thick each
IRR-DAW-6-10 72 sqm 769.00
including cost of all materials, machinery, labour, laying to required slopes,
wedging with stone chips etc., complete with initial lead upto 50 m and all
lifts.
Labour Component (including contractor's profit and Overheads) sqm 139.20
Providing and constructing 75 cm thick hand packed rough stone riprap over
a backing of 45 cm thick graded filter media consisting of sand, 10 mm and 40
IRR-DAW-6-11 73 mm size graded approved aggregates laid in layers of 15 cm thick each including sqm 843.60
cost of all materials, machinery, labour, laying to required slopes, wedging with
stone chips, etc., complete with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads) sqm 151.70
Providing and constructing 90 cm thick hand packed rough stone riprap over
a backing of 45 cm thick graded filter media consisting of sand, 10 mm and 40
IRR-DAW-6-12 74 mm size graded approved aggregates laid in layers of 15 cm thick each including sqm 932.70
cost of all materials, machinery, labour, laying to required slopes, wedging with
stone chips etc., complete with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads) sqm 176.70
Providing and laying Hariyala or other approved quality turfing sods for the
slopes of earthen embankments over 20 mm thick sand backing including cost of
IRR-DAW-6-13 75 sqm 104.80
all materials, machinery, labour including preparing surface, spreading sand,
watering for 15 days etc., complete with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads) sqm 70.20
Chapter II
IRR-TAW TUNNEL AND ALLIED WORKS
IRR-TAW-1 EXCAVATION :
Excavation for adit by tunnelling methods in all types of rock including cost
of all materials, machinery, labour, scaling excavated surface, ventilation,
IRR-TAW-1-1 76 lighting, drainage, removing and hauling the excavated muck outside adit upto cum 1731.00
specified dump area and all other ancillary operations etc., complete with
initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads) cum 642.30
Excavation for vertical / inclined shaft in all types of soft / hard rock
including cost of all materials, machinery, labour, shoring, strutting, scaling
IRR-TAW-1-2 77 excavated surface, ventilation, lighting, drainage, removing and hauling cum 2309.90
excavated muck outside shaft upto specified dump area and all other ancillary
operations etc., complete with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads) cum 1289.10
10
Abstract of work items_UNit Rates for the year 2016-17
NOTE: Where mucking is to be carried out through shaft using winch and
mucking tub system increase the basic rates for items 3, 4 & 5 by 8 percent.
Providing and fixing 25 mm diameter steel rock bolts with resin bond cement
capsule anchorage including drilling 35 mm dia holes, inserting grout capsule,
driving bolt,fixing 10 mm thick plate washers and nuts and tightening the same
IRR-TAW-3-2 86 Rm 977.00
by torque wrench after hardening of cement grout, cost of all materials,
machinery, labour, ventilation, lighting, drainage and other ancillary operations
etc., complete with lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads) Rm 314.00
11
Abstract of work items_UNit Rates for the year 2016-17
Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength
not less than 10 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates crushed from tunnel excavated muck
for filling and levelling over-cuts in bed due to geological faults etc., including
IRR-TAW-5-2 92 cost of all materials, machinery, labour, cleaning bed, batching, mixing, cum 5259.20
conveying and laying, levelling, compacting, finishing, curing, lighting, ventilation,
drainage etc., complete with initial lead upto 1 km and all lifts. ( Cement
content : 220 kg / cum, CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40
cum, Superplasticizer 0.4% by wt. of cement)
Labour Component (including contractor's profit and Overheads) cum 864.00
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sqmm ) grade cement concrete using 40 mm and down size
approved clean, hard, graded aggregates crushed from tunnel muck for kerb and
bed lining including cost of all materials, machinery, labour, formwork, batching,
IRR-TAW-5-3 93 mixing, conveying upto placing point in agitator cars, placing in position, cum 6452.60
levelling, vibrating, finishing, curing, ventilation, lighting, drainage and all other
ancillary operations etc., complete with lead upto 1 km and all lifts. ( Cement
content 330 kg / cum for use of super plasticiser(0.4% by wt. of cement),CA :
0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
Labour Component (including contractor's profit and Overheads) cum 1075.90
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sqmm ) grade cement concrete using 40 mm and down size
approved clean, hard, graded aggregates crushed from tunnel muck for sides
and arch lining including cost of all materials, machinery, labour, formwork,
IRR-TAW-5-4 94 batching, mixing, conveying upto placing point in agitator cars, placing in cum 7191.70
position, levelling, vibrating, finishing, curing, ventilation, lighting, drainage and
all other ancillary operations etc., complete with lead upto 1 km and all lifts. (
Cement content 330 kg / cum for use of super plasticiser(0.4% by wt. of
cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
Labour Component (including contractor's profit and Overheads) cum 890.60
12
Abstract of work items_UNit Rates for the year 2016-17
Chapter III
IRR-CAW CANAL AND ALLIED WORKS
Excavation in all kinds of soil including boulders upto 0.30 m dia for field
channels, seating of embankment for field channels etc., including dressing of
bed and sides to required profile, cost of all materials, machinery, labour, placing
IRR-CAW-1-2 99 the excavated stuff for formation of service road / embankment as directed etc., cum 52.00
complete with lead upto 10 m and lift upto 3 m.
13
Abstract of work items_UNit Rates for the year 2016-17
Excavation in hard rock of all toughness including boulders above 1.2 m dia. by
approved controlled blasting methods for canals, cut-off trench of
embankment, filter / catch-water drains etc., including controlling fly-rock by
muffling arrangements such as placing 50 x 50 mm opening chain link mesh or
waste tyres and sand bags, monitoring ground vibrations at specified locations,
costof all materials, machinery, labour, placing excavated rock neatly in
approved dump area or other place as directed etc., complete with lead upto 1
IRR-CAW-1-7 (b) 104 cum 605.20
km and all lifts.
i) The rate under this item shall be adopted for canals designed for carrying
capacity of less than 15 cumecs or where the average depth excavation in hard
rock is less than 3 m.
ii ) The rate under this item shall be adopted where the control of fly-rock and
ground vibrations is required.
Labour Component (including contractor's profit and Overheads) cum 148.50
Excavation in hard rock of all toughness including boulders above 1.2 m dia.
for dressing canal sides neatly on either side to required profile by line drilling
and smooth blasting including removing under-cuts by chiselling / hammering,
placing the excavated rock neatly in dump area or other place as directed, cost
of all materials, machinery, labour etc., complete with lead upto 1 km and all
lifts.
i) For excavation of canal below free board level combination of normal
controlled blasting and line drilling and smooth blasting shall be adopted to
obtain neat side slopes. For the purpose of payment 1 m width of excavation on
either side shall be treated as excavation by line drilling and smooth blasting and
remaining portion shall be treated as excavation by normal / controlled blasting
IRR-CAW-1-8( c) 105 cum 1080.90
as the case may be.
ii ) The rate under this item shall be adopted for canals designed for carrying
capacity of less than 15 cumecs or where the average depth of excavation in
hard rock is less than 3 m.
iii ) The rate includes controlling fly-rock wherever required.
iv ) The rate under this item shall be paid only on ascertaining that the excavated
face has come off neatly as per specifications or atleast 50 percent of smooth
blast holes are visible for inspection and are spaced at specified interval.
v ) In case, where the above criteria is not fulfilled payment shall be restricted to
the rate provided for excavation by normal blasting or controlled blasting as the
case may be.
Labour Component (including contractor's profit and Overheads) cum 395.80
Excavation in hard rock by blasting including boulders above 1.2 m dia. for
canals, seating embankment etc., including levelling bed by removing all
projections by hammering / chiselling, cost of all materials, machinery, labour,
placing the excavated rock neatly in approved dump area and levelling the same
as directed etc.,complete with initial lead upto 1 km and all lifts.
IRR-CAW-1-9(a) 106 cum 299.40
i ) The rate under this item shall be adopted for canals designed for carrying
capacity of more than 15 cumecs or where the average depth of excavation in
hard rock is more than 3 m.
ii ) The rate includes levelling canal bed by hammering /chiselling all rock
projections wherever required.
Labour Component (including contractor's profit and Overheads) cum 47.40
Excavation in hard rock of all toughness including boulders above 1.2 m dia.
by approved controlled blasting methods for canals, cut-off trench of
embankment etc., including controlling fly-rock by muffling arrangements such
as placing 50 x 50 mm opening chain link mesh or waste tyres and sand bags,
monitoring ground vibrations at specified locations, cost of all materials,
machinery, labour, placing excavated rock neatly in approved dump area or
IRR-CAW-1-
107 other place as directed etc., complete with lead upto 1 km and all lifts. cum 449.10
10(b)
i ) The rate under this item shall be adopted for canals designed for carrying
capacity of more than 15 cumecs or where the average depth of excavation in
hard rock is more than 3 m.
ii ) The rate under this item shall be adopted where the control of fly-rock and
ground vibrations is required.
Labour Component (including contractor's profit and Overheads) cum 54.20
14
Abstract of work items_UNit Rates for the year 2016-17
15
Abstract of work items_UNit Rates for the year 2016-17
16
Abstract of work items_UNit Rates for the year 2016-17
Providing rubble and sand filling in layers of 22.5 to 30 cm including cost of all
IRR-CAW-5-1 128 materials, machinery, labour, watering, ramming etc., complete with initial lead cum 563.50
upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads) cum 159.10
17
Abstract of work items_UNit Rates for the year 2016-17
IRR-CAW-5-3-A Providing and laying sand blanket below embankment including cost of all
(New Item 3 - 131 materials, machinery, labour, spreading to specified thickness etc., complete cum 187.50
2011-12) with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads) cum 79.50
Providing and constructing dry rubble rock-toe using rubble and stone chips
from approved source including cost of all materials, machinery, labour, hand
IRR-CAW-5-4 132 cum 534.10
packing rubble and stone chips, finishing top and sides to required slopes etc.,
complete with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads) cum 112.50
Providing and constructing longitudinal and cross graded filter drains using
sand and 20 mm down graded aggregates satisfying specified filter creteria in
IRR-CAW-5-5 133 layers as per specifications including cost of all materials, machinery, labour, cum 532.60
laying to required slopes, compaction etc., complete with initial lead upto 50 m
and all lifts.
Labour Component (including contractor's profit and Overheads) cum 148.30
Laying Longitudinal Drains and Transverse drains of Size 600 x600 x750 mm
IRR-CAW-5-6 134 in Bed and filling with 12 mm to 40 mm HG machine Crushed metal and sand in Rm 265.10
bed including excavation of drains and Cost of procuring of all materials
133 Rm 28.10
Laying and fixing of 100 mm Dia 300 mm long precast porus CC plugs in bed
and sides using 1.181 Kgs of cement per each using 20 mm HG metal and
IRR-CAW-5-7 135 one plug 272.20
placing in local filters of size 600x600x750 mm in size including excavation of
drains and Cost of procuring of all materials
Labour Component (including contractor's profit and Overheads) one plug 119.30
Providing and constructing graded filter media below and behind rock-toe
consisting of 20 cm thick sand, 15 cm thick 20 mm down and 15 cm thick 40 mm
down size graded coarse aggregates satisfying filter creteria behind rock-toe and
IRR-CAW-5-9 137 15 cm thick sand, 20 cm thick 20 mm down coarse aggregate and 65 cm thick 40 cum 1055.30
mm down size coarse aggregate satisfying filter creiteria below rock-toe as per
specifications including cost of all materials, machinery, labour, laying to required
slope, compaction etc., complete with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads) cum 138.50
18
Abstract of work items_UNit Rates for the year 2016-17
Stones and spalls available in dump yard will be issued at specified issue rate.
Labour Component (including contractor's profit and Overheads) cum 76.10
Providing cohesive non-swelling ( CNS ) soil lining to canals using soil from
approved borrow area including spreading soil in layers of thickness not
IRR-CAW-7-1 142 more than 15 cm, breaking clods, watering, compacting to density control of not cum 216.80
less than 98 percent or as stipulated, dressing to required profile etc., complete
with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads) cum 71.00
Providing cohesive non-swelling ( CNS ) soil lining to canals using soil from
approved borrow area including spreading soil in layers of thickness not
IRR-CAW-7-2 143 more than 15 cm, breaking clods, watering, compacting to density control of not cum 211.90
less than 95 percent or as stipulated, dressing to required profile etc., complete
with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads) cum 70.10
Providing, fabricating and placing in position reinforcement steel bars for RCC
works including cleaning, straightening, cutting, bending, hooking, lapping, tying
IRR-CAW-7-5 146 with 1.25 mm dia.soft annealed steel wire, welding wherever required including kg 49.60
cost of all materials, machinery, labour etc., complete with initial lead upto 50
and all lifts.(1.05 tonne/tonne of steel)
Labour Component (including contractor's profit and Overheads) kg 8.20
19
Abstract of work items_UNit Rates for the year 2016-17
Providing and laying 100 mm thick in situ M-15 (28 days cube compressive
strength not less than 15 N /Sqmm ) grade cement concrete with 20 mm down
size approved, clean, hard, graded aggregates for canal lining using, vibrating,
cylinder type mechanical paver including cost of all materials, machinery, labour,
cleaning, batching, mixing, placing in position, finishing, forming contraction
IRR-CAW-7-8 149 joints, fixing PVC joint sealing strips, curing, shifting of paver from one side to sqm 516.70
othere side of canal etc., complete with initial lead upto 1 Km and all lifts. ( 43
Gr Cement content: (300kg /cum) 30 kg / sqm for use of super
plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35,
FA : 0.45 cum, equivalent concrete volume:88 cum including the extra
quantity of concrete for curvatures and bends etc.,)
Note: Local shifting and re-erection of paver for LH and RH side lining included
in concrete lining rates under items IRR-CAW-7-7 and IRR-CAW-7-8 and
saperate rate for shifting shall not be allowed.
Labour Component (including contractor's profit and Overheads) shifting 7026.40
Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength
not less than 10 N /sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates for bed and side lining of canal(150mm
thick) including finishing the junction of bed and sides to required curveture,
cost of all materials, machinery, labour, formwork including supports, cleaning,
IRR-CAW-7-10 151 batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., cum 4489.10
complete with initial lead upto 50 m and all lifts. ( 43 Gr Cement content: 250
kg / cum for use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum,
Blending Ratio of CA--50:30:20, FA : 0.40 cum)
Providing and laying insitu vibrated M-10 (28 days cube compressive strength
not less than 10 N/sqm) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregade for bed and side lining of canal(100
mm thick) including, finishing the junction of bed and sides to required
IRR-CAW-7-11 152 curveture, cost of all materials, machinery, labour, formwork including supports cum 4633.10
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing,
curing etc., complete with initial lead up to 50 m and all lifts ( 43 Gr Cement
content: 250 kg / cum for use of super plasticiser(0.4% by wt. of cement),CA :
0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
Labour Component (including contractor's profit and Overheads) cum 1297.90
Providing and laying 100mm thick insitu vibrated M-10 (28 days cube
compressive strength-not less than 10.00 N / sq mm) grade cement concrete
using 40 mm down size approved, clean, hard, graded aggregates for bed and
side lining of canal lining using vibrating cylindertype mechanical paver
IRR-CAW-7-12 153 including cost of all materials mechinery labour batching mixing placing in sqm 495.70
position forming contraction joints fixing pvc joint seiling strips shifting of paver
from one side of canal to other side etc.complete with all leads & lifts.
(Cement content: 250 kg / cum for use of super plasticiser(0.4% by wt. of
cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
20
Abstract of work items_UNit Rates for the year 2016-17
Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength
not less than 10 N /sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates for bed and side lining of canal
including finishing the junction of bed and sides to required curveture, cost of all
IRR-CAW-7-13 154 materials, machinery, labour, formwork including supports, cleaning, batching, cum 4503.80
mixing, placing in position, levelling, vibrating, finishing, curing etc., complete
with initial lead upto 50 m and all lifts. (Cement content: 250 kg / cum for use
of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA-
-65:35, FA : 0.45 cum)
Labour Component (including contractor's profit and Overheads) cum 1297.90
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength
not less than 15 N /sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates for bed and side lining(150 mm thick)
of canal including finishing the junction of bed and sides to required curveture,
IRR-CAW-7-14 155 cost of all materials, machinery, labour, formwork including supports, cleaning, cum 4891.10
batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts. (Cement content: 290 kg /
cum for use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum,
Blending Ratio of CA--50:30:20, FA : 0.40 cum)
Labour Component (including contractor's profit and Overheads) cum 1373.00
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength
not less than 15 N /sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates for bed and side lining(of thickness
100 mm) of canal including finishing the junction of bed and sides to required
IRR-CAW-7-15 156 curveture, cost of all materials, machinery, labour, formwork including supports, cum 5009.50
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing,
curing etc., complete with initial lead upto 50 m and all lifts. (Cement content:
300 kg / cum for use of super plasticiser(0.4% by wt. of cement),CA : 0.80 cum,
Blending Ratio of CA--65:35, FA : 0.45 cum)
Labour Component (including contractor's profit and Overheads) cum 1450.00
Providing and laying 150mm thick insitu vibrated M-15 (28 days cube
compressive strength-not less than 15.00 N / sq mm) grade cement concrete
using 20 mm down size approved, clean, hard, graded aggregates for bed and
side lining of canal lining using vibrating cylindertype mechanical paver including
cost of all materials mechinery labour batching mixing placing in position forming
IRR-CAW-7-16 157 sqm 685.20
contractiom joints fixing pvc joint seiling strips shifting of paver from one side of
canal to other side etc.complete with all leads & lifts. (Cement content: 300
kg / cum for use of super plasticiser(0.4% by wt. of cement),CA : 0.80 cum,
Blending Ratio of CA--65:35, FA : 0.44 cum)
(Paver)
Labour Component (including contractor's profit and Overheads) sqm 37.40
Providing and fixing pre-cast RCC template walls consisting of 0.05 cum M-15
grade concrete using 20 mm down size coarse aggregates and 10 kg
reinforcement steel moulded as per specifications and drawing in CM 1:4
IRR-CAW-7-17 158 proportion including cost of all materials, machinery, labour, formwork, Rm 904.30
fabricating and placing reinforcement steel, mixing, laying, conveying and fixing
in position including necessary excavation for seating, finishing joints in CM 1:4,
curing etc., complete with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads) Rm 286.90
21
Abstract of work items_UNit Rates for the year 2016-17
Providing and fixing 100 mm dia perforated PVC pipes 40 cm long for Weep
IRR-CAW-7-23 164 holes including cost of all materials, labour, drilling 8 mm dia holes etc. complete Each 217.60
with all leads and lifts.
Labour Component (including contractor's profit and Overheads) Each 24.40
Drilling 32 mm dia pressure relief hole below pressure relief pipe for bed and
IRR-CAW-7-24 165 side lining of canal laid on rock including cost of all materials, machinery, labour Each 272.30
etc., complete with all leads and lifts.
Labour Component (including contractor's profit and Overheads) Each 98.80
Providing and fixing LDPE sheet for bed and sides of canal including cost of all
materials, labour, laying, joining etc., complete with all leads and lifts.
IRR-CAW-7-30 171 sqm 127.90
Using 500 micron thick LDPE sheet.
Labour Component (including contractor's profit and Overheads) sqm 12.00
If the surface on which the LDPE sheet is to be laid is too rough and undulating
provide 75 mm thick sand backing to LDPE sheet. For providing 75 mm thick sqm 17.60
Sand for backing add
Labour Component (including contractor's profit and Overheads) sqm 9.50
Providing and fixing LDPE sheet for bed and sides of canal including cost of all
IRR-CAW-7-31 172 materials, labour, laying, joining etc., complete with all leads and lifts. sqm 186.50
22
Abstract of work items_UNit Rates for the year 2016-17
Providing and fixing LDPE sheet for bed and sides of canal including cost of all
IRR-CAW-7-32 173 materials, labour, laying, joining etc., complete with all leads and lifts. sqm 254.70
Providing and fixing 12 mm thick 380 mm depth tarfelt expansion joint filler
IRR-CAW-7-33 174 boards for stone masonry lining of canal including cost of all materials, labour Rm 191.20
etc., complete with all leads and lifts.
Labour Component (including contractor's profit and Overheads) Rm 8.50
Providing and fixing 20 mm thick 100 mm depth tarfelt expansion joint filler
IRR-CAW-7-34 175 boards for cement concrete lining of canal including cost of all materials, Rm 80.10
labour etc., complete with all leads and lifts.
Labour Component (including contractor's profit and Overheads) Rm 8.50
Providing and fixing 20 mm thick 150 mm depth tarfelt expansion joint filler
IRR-CAW-7-35 176 boards for cement concrete lining of canal including cost of all materials, Rm 118.00
labour etc., complete with all leads and lifts.
Labour Component (including contractor's profit and Overheads) Rm 8.50
Manufacturing 550 x 300 x 55 mm size PCC lug slabs in M-15 grade ( 28 days
cube compressive strength not less than 15 N / sqmm ) cement concrete using
20 mm down graded coarse aggregate including cost of all materials,
IRR-CAW-7-38 179 machinery, labour, batching, mixing, laying, compacting, formwork, finishing, Each 66.80
curing etc.,complete with initial lead upto 50 m and all lifts. ( Cement content :
300 kg / cum with super plastcizer (0.4% by wt. of cement), CA : 0.80 cum,
Blending Ratio of CA : 65:35, FA : 0.45cum)
Labour Component (including contractor's profit and Overheads) Each 27.00
Manucturing 450 x 150 x 30 mm size PCC lug slabs in M-15 grade ( 28 days
cube compressive strength not less than 15 N / sqmm ) cement concrete using
10 mm down graded coarse aggregate including cost of all materials,
IRR-CAW-7-40 181 machinery, labour, batching, mixing, laying, compacting, formwork, finishing, Each 26.90
curing etc.,complete with initial lead upto 50 m and all lifts. ( Cement content :
300 kg / cum with super plastcizer (0.4% by wt. of cement),CA : 0.68 cum, FA :
0.43cum)
Labour Component (including contractor's profit and Overheads) Each 17.40
Manufacturing 600 x 300 x 100mm size PCC lining slabs in M-15 grade (28
days cube compressive strength not less than 15 N/Sqmm) cement concrete
using 20 mm down grades coarse aggregate including cost of all materials,
IRR-CAW-7-41 182 machinery, labour, batching, mixing, laying, compacting, formwork, finishing, Each 80.40
curing etc., complete with initial lead upto 50 m and all lifts. ( Cement content
: 300 kg / cum with super plastcizer (0.4% by wt. of cement), CA : 0.80 cum,
FA : 0.45cum, Blending Ratio of CA--65:35)
Labour Component (including contractor's profit and Overheads) Each 17.20
23
Abstract of work items_UNit Rates for the year 2016-17
Manufacturing 400 x 150 x 30 mm size PCC lug slabs in M-15 grade ( 28 days
cube compressive strength not less than 15 N /sqmm ) cement concrete using
10 mm down graded coarse aggregate including cost of all materials,
IRR-CAW-7-43 184 machinery, labour, batching, mixing, laying, compacting, formwork, finishing, Each 26.30
curing etc.,complete with initial lead upto 50 m and all lifts. ( Cement content :
300 kg / cum with super plastcizer (0.4% by wt. of cement), CA : 0.68 cum, FA
: 0.43cum)
Labour Component (including contractor's profit and Overheads) Each 17.40
Providing and laying uncoursed rubble stone masonry in CM 1:5 proportion for
canal side lining using stones from approved quarry including cost of all
IRR-CAW-7-45 186 materials, machinery, labour, forming weep holes at specified intervals, finishing, cum 3297.50
curing etc., complete with initial lead upto 50m and all lifts.(with no pin
headers)(Thickness of the Masonry assumed:0.3 m, rubble stones : 1.1 cum)
Labour Component (including contractor's profit and Overheads) cum 2186.40
Providing and laying uncoursed rubble stone masonry in CM 1:5 proportion for
canal side lining using stones from canal excavation including cost of all
IRR-CAW-7-47 188 materials, machinery, labour, forming weep holes at specified intervals, cum 3094.30
finishing, curing etc., complete with initial lead upto 50m and all lifts.(with no
pin headers)( rubble stones : 1.1cum, cement : 98kg, sand 0.34 cum)
Labour Component (including contractor's profit and Overheads) cum 2186.40
Providing and constructing 25 cm thick dry rubble stone pitching with pin
headers at 2 per sqm including cost of all materials, labour, hand packing,
IRR-CAW-8-1 189 sqm 199.70
finishing etc., complete with initial lead upto 50 m and all lifts.( rubble stones :
0.23 cum/sqm, Stone Chips : 0.0375cum/sqm, Pin Headers 30cm : 2/sqm)
Labour Component (including contractor's profit and Overheads) sqm 51.70
If 15 cm thick murum bed is to be provided below pitching add sqm 49.60
Labour Component (including contractor's profit and Overheads) sqm 15.90
Providing and constructing 22.5 cm thick dry rubble stone pitching with pin
IRR-CAW-8-1-A headers at 2 per sqm including cost of all materials, labour, hand packing,
(New Item4 - 190 finishing etc., complete with initial lead upto 50 m and all lifts.( rubble stones : sqm 189.90
2011-12) 0.207 cum/sqm, Stone Chips : 0.3375cum/sqm, Pin Headers 30cm : 2/sqm)
(For Maintenance Works)
Labour Component (including contractor's profit and Overheads) sqm 51.70
24
Abstract of work items_UNit Rates for the year 2016-17
Providing and constructing 30 cm thick dry rubble stone pitching with pin
headers at 2 per sqm including cost of all materials, labour, hand packing,
IRR-CAW-8-3 193 sqm 218.90
finishing etc., complete with initial lead upto 50 m and all lifts.( rubble stones :
0.275 cum/sqm, Stone Chips : 0.045cum/sqm, Pin Headers 30cm : 2/sqm)
Labour Component (including contractor's profit and Overheads) sqm 51.70
Providing and constructing 45 cm thick dry rubble stone pitching with pin
headers at 2 per sqm including cost of all materials, labour, hand packing,
IRR-CAW-8-5 195 sqm 332.70
finishing etc., complete with initial lead upto 50 m and all lifts.( rubble stones :
0.40 cum/sqm, Stone Chips : 0.0675cum/sqm, Pin Headers 45cm : 2/sqm)
Labour Component (including contractor's profit and Overheads) sqm 72.70
25
Abstract of work items_UNit Rates for the year 2016-17
with no sand
Labour Component (including contractor's profit and Overheads) sqm 38.40
Chapter IV
IRR-CCDW CANAL CROSS DRAINAGE WORKS
Excavation in all kinds of soil including boulders upto 0.30 m dia. for
IRR-CCDW-1-1 205 foundations of canal cross drainage and other appurtenant structures and cum 251.40
placing the excavated stuff neatly in specified dump area or disposing off the
same as directed etc., complete with initial lead upto 50 m and initial lift upto
3 m.
Labour Component (including contractor's profit and Overheads) cum 251.40
26
Abstract of work items_UNit Rates for the year 2016-17
Providing and fixing 25 mm dia 2.50 m long cold twisted deformed steel
anchor rods with 1.25 m length driven into 32 mm dia hole drilled in bed rock
and remaining length embedded in concrete / masonry including cost of all
IRR-CCDW-1-8 212 Each 793.40
materials, machinery, labour, drilling and cleaning hole, driving anchor rod,
grouting hole with thick cement slurry etc., complete with initial lead upto 50 m
and all lifts.
Labour Component (including contractor's profit and Overheads) Each 218.50
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength
not less than 15 N /sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates for foundation filling including cost of
all materials, machinery, labour, formwork, cleaning, batching, mixing, placing in
IRR-CCDW-2-3 215 cum 4604.60
position, levelling, vibrating, finishing, curing etc., complete with initial lead
upto 50 m and all lifts. (Cement content: 260 kg / cum with use of super
plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--
50:30:20, FA : 0.40 cum)
Labour Component (including contractor's profit and Overheads) cum 1306.10
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength
not less than 15 N / sq mm ) grade cement concrete using 80 mm down size
approved, clean, hard, graded aggregates for foundation filling including cost of
all materials, machinery, labour, formwork, cleaning, batching, mixing, placing in
IRR-CCDW-2-4 216 cum 4589.90
position, levelling, vibrating, finishing, curing etc., complete with initial lead
upto 50 m and all lifts. (Cement content: 250 kg / cum with use of super
plasticiser(0.4% by wt. of cement),CA : 0.98cum, Blending Ratio of CA--
35:30:20:15, FA : 0.35 cum)
Labour Component (including contractor's profit and Overheads) cum 1360.40
Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength
not less than 10 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates for foundation filling including cost of
all materials, machinery, labour, formwork, cleaning, batching, mixing, placing in
IRR-CCDW-2-5 217 cum 4284.60
position, levelling, vibrating, finishing, curing etc., complete with initial lead
upto 50 m and all lifts. (Cement content: 220 kg / cum with use of super
plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--
50:30:20, FA : 0.40 cum)
Labour Component (including contractor's profit and Overheads) cum 1248.30
Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength
not less than 10 N / sq mm ) grade cement concrete using 80 mm down size
approved, clean, hard, graded aggregates for foundation filling including cost of
all materials, machinery, labour, formwork, cleaning, batching, mixing, placing in
IRR-CCDW-2-6 218 cum 4388.80
position, levelling, vibrating, finishing, curing etc., complete with initial lead
upto 50 m and all lifts. (Cement content: 220 kg / cum with use of super
plasticiser(0.4% by wt. of cement),CA : 0.98cum, Blending Ratio of CA--
35:30:20:15, FA : 0.35 cum)
Labour Component (including contractor's profit and Overheads) cum 1351.70
27
Abstract of work items_UNit Rates for the year 2016-17
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates for foundation filling including cost
of all materials, machinery, labour, formwork, cleaning, batching, mixing, placing
IRR-CCDW-2-7 219 cum 5000.50
in position, levelling, vibrating, finishing, curing etc., complete with initial lead
upto 50 m and all lifts. (Cement content: 310 kg / cum with use of super
plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--
50:30:20, FA : 0.40 cum)
Labour Component (including contractor's profit and Overheads) cum 1373.00
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates for sub-structure / super- structure
works including cost of all materials, machinery, labour, formwork, scaffolding,
IRR-CCDW-2-8 220 cum 5419.20
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing,
curing etc., complete with initial lead upto 50 m and all lifts.(Cement content:
320 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA :
0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
Labour Component (including contractor's profit and Overheads) cum 1367.90
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates for sub-structure / super- structure
works including cost of all materials, machinery, labour, formwork, scaffolding,
IRR-CCDW-2-9 221 cum 5414.90
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing,
curing etc., complete with initial lead upto 50 m and all lifts.(Cement content:
330 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA :
0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
Labour Component (including contractor's profit and Overheads) cum 1452.90
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength
not less than 15 N / sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates for sub-structure / super- structure
works including cost of all materials, machinery, labour, formwork, scaffolding,
IRR-CCDW-2-10 222 cum 5101.50
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing,
curing etc., complete with initial lead upto 50 m and all lifts.(Cement content:
280 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA :
0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
Labour Component (including contractor's profit and Overheads) cum 1455.50
Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength
not less than 10 N / sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates for sub-structure / super- structure
works including cost of all materials, machinery, labour, formwork, scaffolding,
IRR-CCDW-2-11 223 cum 4600.50
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing,
curing etc., complete with initial lead upto 50 m and all lifts. (Cement content:
220 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA :
0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
Labour Component (including contractor's profit and Overheads) cum 1352.90
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates for well kerb including cost of all
materials, machinery, labour, formwork, scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc., complete with
IRR-CCDW-2-12 224 initial lead upto 50 m and all lifts. (Cement content: 350 kg / cum with use of cum 6673.50
super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--
65:35, FA : 0.45 cum)
If water is to be brought from other place add only lead charges @ 500 ltr /
cum.
Labour Component (including contractor's profit and Overheads) cum 1755.40
28
Abstract of work items_UNit Rates for the year 2016-17
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates for well steining including cost of all
materials, machinery, labour, formwork, scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc., complete with
IRR-CCDW-2-13 225 cum 6069.10
initial lead upto 50 m and all lifts. (Cement content: 320 kg / cum with use of
super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--
50:30:20, FA : 0.40 cum)
If water is to be brought from other place add only lead charges @ 500 ltr /
cum.
Labour Component (including contractor's profit and Overheads) cum 1604.60
Providing and laying insitu M-15 ( 28 days cube compressive strength not less
than 15 N / sq mm ) grade cement concrete using 20 mm down size approved,
clean, hard, graded aggregates for well bottom plug by tremie or skip box
IRR-CCDW-2-14 226 cum 4675.40
method including cost of all materials, complete with initial lead upto 50 m and
all lifts.(Cement content: 350 kg / cum with use of super plasticiser(0.4% by
wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
Labour Component (including contractor's profit and Overheads) cum 1267.00
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength
not less than 15 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates for well top plug including cost of all
materials, machinery, labour, cleaning, batching, mixing, placing in position,
levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m
IRR-CCDW-2-15 227 cum 4322.80
and all lifts. (Cement content: 280 kg / cum with use of super plasticiser(0.4%
by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
If water is to be brought from other place add only lead charges @ 500 ltrs /
cum
Labour Component (including contractor's profit and Overheads) cum 1242.30
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates for well cap including cost of all
materials, machinery, labour, formwork, scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc., complete with initial
IRR-CCDW-2-16 228 lead upto 50 m and all lifts. (Cement content: 330 kg / cum with use of super cum 4792.70
plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35,
FA : 0.45 cum)
If water is to be brought from other place add only lead charges @ 500 ltr /
cum.
Labour Component (including contractor's profit and Overheads) cum 1264.10
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength
not less than 15 N / sq mm ) grade cement concrete using 80 mm down size
approved, clean, hard, graded aggregates for piers and abutments including
cost of all materials, labour, machinery, formwork, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc., complete with
IRR-CCDW-2-17 229 cum 5540.20
initial lead upto 50 m and all lifts. (Cement content: 250 kg / cum with use of
super plasticiser(0.4% by wt. of cement),CA : 0.98cum, Blending Ratio of CA--
35:30:20:15, FA : 0.35 cum)
If water is to be brought from other place add only lead charges @ 500 ltr /
cum.
Labour Component (including contractor's profit and Overheads) cum 1678.20
Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength
not less than 10 N / sq mm ) grade cement concrete using 80 mm down size
approved, clean, hard, graded aggregates for piers and abutments including
cost of all materials, labour, machinery, formwork, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc., complete with
IRR-CCDW-2-18 230 cum 5339.00
initial lead upto 50 m and all lifts. (Cement content: 220 kg / cum with use of
super plasticiser(0.4% by wt. of cement),CA : 0.98cum, Blending Ratio of CA--
35:30:20:15, FA : 0.35 cum)
If water is to be brought from other place add only lead charges @ 500 ltr /
cum.
Labour Component (including contractor's profit and Overheads) cum 1668.70
29
Abstract of work items_UNit Rates for the year 2016-17
Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength
not less than 10 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates for piers and abutments including
cost of all materials, labour, machinery, formwork, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc., complete with
IRR-CCDW-2-19 231 cum 5219.20
initial lead upto 50 m and all lifts. (Cement content: 220 kg / cum with use of
super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--
50:30:20, FA : 0.40 cum)
If water is to be brought from other place add only lead charges @ 500 ltr /
cum.
Labour Component (including contractor's profit and Overheads) cum 1543.50
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates for cantiliver / counterfort retaining
walls including cost of all materials, machinery, labour, formwork, scaffolding,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing,
IRR-CCDW-2-20 232 cum 5986.80
curing etc., complete with initial lead upto 50 m and all lifts. (Cement content:
320 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA :
0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
If water is to be brought from other place add only lead charges @ 500 ltr /
cum.
Labour Component (including contractor's profit and Overheads) cum 1597.90
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength
not less than 15 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates with placing and sinking plums of
size 150 to 80 mm upto 15 percent for gravity type retaining walls / piers /
abutments etc., including cost of all materials, machinery, labour, formwork,
scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating,
IRR-CCDW-2-21 233 cum 5288.90
finishing, curing etc.,complete with initial lead upto 50 m and all lifts.
(Cement content: 260 kg / cum with use of super plasticiser(0.4% by wt. of
cement),CA : 0.765cum, Blending Ratio of CA--50:30:20, FA : 0.34 cum,
plums of size 150 to 80 mm : 0.25cum )
If water is to be brought from other place add only lead charges @ 500 ltr /
cum.
Labour Component (including contractor's profit and Overheads) cum 1496.70
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength
not less than 15 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard,graded aggregates for cast in-situ pipes including cost of
all materials, machinery, labour, cleaning, batching, mixing, placing in position,
IRR-CCDW-2-22 234 levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m cum 5007.90
and all lifts.(Cement content: 260 kg / cum with use of super plasticiser(0.4%
by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
If water is to be brought from other place add only lead charges @ 500 ltr /
cum.
Labour Component (including contractor's profit and Overheads) cum 1413.70
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength
not less than 15 N / sq mm ) grade cement concrete using 80 mm down size
approved, clean, hard, graded aggregates for cast in-situ pipes including cost of
all materials, labour, machinery, formwork, cleaning, batching, mixing, placing in
position, levelling, vibrating, finishing, curing etc., complete with initial lead
IRR-CCDW-2-23 235 cum 4987.60
upto 50 m and all lifts. (Cement content: 250 kg / cum with use of super
plasticiser(0.4% by wt. of cement),CA : 0.98cum, Blending Ratio of CA--
35:30:20:15, FA : 0.35 cum)
If water is to be brought from other place add only lead charges @ 500 ltr /
cum.
Labour Component (including contractor's profit and Overheads) cum 1467.10
30
Abstract of work items_UNit Rates for the year 2016-17
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates for deck slab & kerb including cost of
all materials,machinery, labour, formwork, scaffolding, cleaning, batching,
mixing, placing in position, levelling, vibrating, finishing, curing etc., complete
IRR-CCDW-2-24 236 cum 8073.50
with initial lead upto 50 m and all lifts. (Cement content: 330 kg / cum with
use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio
of CA--65:35, FA : 0.45 cum)
If water is to be brought from other place add only lead charges @ 500 ltr /
cum.
Labour Component (including contractor's profit and Overheads) cum 2100.60
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates for columns and beams including
cost of all materials, labour, machinery, formwork, scaffolding, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing
IRR-CCDW-2-25 237 cum 7105.80
etc.,complete with initial lead upto 50 m and all lifts. (Cement content: 330 kg
/ cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum,
Blending Ratio of CA--65:35, FA : 0.45 cum)
If water is to be brought from other place add only lead charges @ 500 ltr /
cum.
Labour Component (including contractor's profit and Overheads) cum 1917.60
Providing and laying insitu M- 20 ( 28 days cube compressive strength not less
than 20 N / sqmm ) grade cement concrete using 20 mm down size approved,
clean, hard, graded aggregates for wearing coat including cost of all materials,
machinery, labour, formwork, cleaning, batching, mixing, placing in position in
alternate panels, levelling, compacting, finishing, curing, packing joints with
IRR-CCDW-2-26 238 cum 4707.10
asphalt mortar etc., complete with initial lead upto 50 m and all lifts. (Cement
content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA
: 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
If water is to be brought from other place add only lead charges @ 500 ltr /
cum.
Labour Component (including contractor's profit and Overheads) cum 1296.30
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates for troughs including cost of all
materials, machinery, labour, formwork, scaffolding, cleaning, batching, mixing,
placing in position,levelling, vibrating, finishing, curing etc., complete with initial
IRR-CCDW-2-27 239 lead upto 50 m and all lifts. (Cement content: 330 kg / cum with use of super cum 6488.20
plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35,
FA : 0.45 cum)
If water is to be brought from other place add only lead charges @ 500 ltr /
cum.
Labour Component (including contractor's profit and Overheads) cum 1779.60
Sinking RCC wells vertically for foundation of piers and abutments in all
kinds of soil, sand and soft rock by approved well sinking method including
cost of all materials, machinery, labour, kent - ledge arrangements, disposal of
IRR-CCDW-3-1 240 excavated material as disposal of excavated material as directed etc., complete *Rm 3847.70
with lead upto 50 m for disposal of excavated material.(diameter of well
6.00m) (Data adopted from MORTH)
31
Abstract of work items_UNit Rates for the year 2016-17
32
Abstract of work items_UNit Rates for the year 2016-17
Providing and fixing 10 cm thick roughly dressed burnt stone slabs for coping
set in CM 1: 6 proportion by volume with pointing to joints in CM 1 : 3 proportion
IRR-CCDW-5-1 252 by volume including cost of all materials, machinery, labour, finishing, curing sqm 628.90
etc., complete with initial lead upto 50 m and all lifts.(Cement content: 7.5 kg /
sqm, FA : 0.030 cum/sqm, Burnt stone slab 10 cm thick 1.05 sqm/ sqm)
Labour Component (including contractor's profit and Overheads) sqm 196.00
Providing and fixing 10 cm thick one line dressed burnt stone slabs for coping
set in CM 1: 6 proportion by volume with pointing to joints in CM 1 : 3 proportion
IRR-CCDW-5-2 253 by volume including cost of all materials, machinery, labour, finishing, curing sqm 785.70
etc., complete with initial lead upto 50 m and all lifts.(Cement content: 7.5 kg /
sqm, FA : 0.030 cum/sqm, Burnt stone slab 10 cm thick 1.05 sqm/ sqm)
Labour Component (including contractor's profit and Overheads) sqm 352.80
Providing and fixing 10 cm thick two line dressed burnt stone slabs for coping
set in CM 1: 6 proportion by volume with pointing to joints in CM 1 : 3 proportion
IRR-CCDW-5-3 254 by volume including cost of all materials, machinery, labour, finishing, curing sqm 988.00
etc., complete with initial lead upto 50 m and all lifts.(Cement content: 7.5 kg /
sqm, FA : 0.030 cum/sqm, Burnt stone slab 10 cm thick 1.05 sqm/ sqm)
Labour Component (including contractor's profit and Overheads) sqm 555.00
Providing and laying insitu M-15 ( 28 days cube compressive strength not less
than 15 N / sqmm ) grade cement concrete using 20 mm down size approved
clean, hard, graded aggregates for coping slab including cost of all materials,
machinery, labour, formwork, cleaning surface, batching, mixing, placing in
IRR-CCDW-5-4 255 cum 6222.40
position, levelling, compacting, finishing, curing etc., complete with initial lead
upto 50 m and initial lift upto 3 m. (Cement content: 300 kg / cum with use of
super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--
65:35, FA : 0.45 cum)
Labour Component (including contractor's profit and Overheads) cum 1689.20
Laying and jointing 300 mm dia. NP- 2 class or IRC standard hume pipes in
CM 1 : 2 proportion by volume including cost of all materials ( excluding pipes
IRR-CCDW-6-1 257 and collars ), machinery, labour, aligning, packing joints with hemp, finishing, Joint 330.80
curing etc., complete with initial lead upto 50 m and all lifts.(Cement content:
9.9 kg / joint, FA : 0.01cum/joint, Hemp Yarn : 0.091kg/joint)
Labour Component (including contractor's profit and Overheads) Joint 261.30
Laying and jointing 450 mm dia. NP- 2 class or IRC standard hume pipes in
CM 1 : 2 proportion by volume including cost of all materials ( excluding pipes
IRR-CCDW-6-2 258 and collars ), machinery, labour, aligning, packing joints with hemp, finishing, Joint 381.60
curing etc., complete with initial lead upto 50 m and all lifts.(Cement content:
17.4 kg / joint, FA : 0.022cum/joint, Hemp Yarn : 0.127kg/joint)
Labour Component (including contractor's profit and Overheads) Joint 261.30
Laying and jointing 600 mm dia. NP- 2 class or IRC standard hume pipes in
CM 1 : 2 proportion by volume including cost of all materials ( excluding pipes
IRR-CCDW-6-3 259 and collars ), machinery, labour, aligning, packing joints with hemp, finishing, Joint 497.20
curing etc., complete with initial lead upto 50 m and all lifts.(Cement content:
24.8 kg / joint, FA : 0.025cum/joint, Hemp Yarn : 0.22kg/joint)
Labour Component (including contractor's profit and Overheads) Joint 323.80
33
Abstract of work items_UNit Rates for the year 2016-17
Laying and jointing 800 mm dia. NP- 2 class or IRC standard hume pipes in
CM 1 : 2 proportion by volume including cost of all materials ( excluding pipes
IRR-CCDW-6-5 261 and collars ), machinery, labour, aligning, packing joints with hemp, finishing, Joint 659.70
curing etc., complete with initial lead upto 50 m and all lifts.(Cement content:
39.6 kg / joint, FA : 0.039cum/joint, Hemp Yarn : 0.31kg/joint)
Labour Component (including contractor's profit and Overheads) Joint 386.30
Laying and jointing 900 mm dia. NP- 2 class or IRC standard hume pipes in
CM 1 : 2 proportion by volume including cost of all materials ( excluding pipes
IRR-CCDW-6-6 262 and collars ), machinery, labour, aligning, packing joints with hemp, finishing, Joint 693.60
curing etc., complete with initial lead upto 50 m and all lifts.(Cement content:
44.6 kg / joint, FA : 0.045cum/joint, Hemp Yarn : 0.34kg/joint)
Labour Component (including contractor's profit and Overheads) Joint 386.30
Laying and jointing 1000 mm dia. NP- 2 class or IRC standard hume pipes in
CM 1 : 2 proportion by volume including cost of all materials ( excluding pipes
IRR-CCDW-6-7 263 and collars ), machinery, labour, aligning, packing joints with hemp, finishing, Joint 767.20
curing etc., complete with initial lead upto 50 m and all lifts.(Cement content:
49.5 kg / joint, FA : 0.05cum/joint, Hemp Yarn : 0.377kg/joint)
Labour Component (including contractor's profit and Overheads) Joint 426.10
Laying and jointing 1100 mm dia. NP- 2 class or IRC standard hume pipes in
CM 1 : 2 proportion by volume including cost of all materials ( excluding pipes
IRR-CCDW-6-8 264 and collars ), machinery, labour, aligning, packing joints with hemp, finishing, Joint 816.70
curing etc., complete with initial lead upto 50 m and all lifts.(Cement content:
56.9 kg / joint, FA : 0.058cum/joint, Hemp Yarn : 0.415kg/joint)
Labour Component (including contractor's profit and Overheads) Joint 426.10
Laying and jointing 1200 mm dia. NP- 2 class or IRC standard hume pipes in
CM 1 : 2 proportion by volume including cost of all materials ( excluding pipes
IRR-CCDW-6-9 265 and collars ), machinery, labour, aligning, packing joints with hemp, finishing, Joint 967.30
curing etc., complete with initial lead upto 50 m and all lifts.(Cement content:
66.8 kg / joint, FA : 0.069cum/joint, Hemp Yarn : 0.453kg/joint)
Labour Component (including contractor's profit and Overheads) Joint 511.30
Providing rubble / boulder and sand filling behind abutment and return
IRR-CCDW-7-1 266 walls in layers including cost of all materials, machinery, labour, watering, cum 634.50
ramming etc., complete with initial lead upto 50 m and initial lift upto 3 m.
Labour Component (including contractor's profit and Overheads) cum 230.10
Providing and filling murrum / gravely soil ( CNS soil ) for foundation or
around pipes including breaking clods, spreading in layers of 10 to 15 cm,
IRR-CCDW-7-2 267 cum 515.50
watering, compaction by earth masters to achieve density control of not less
than 95 percent etc., complete with lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads) cum 290.60
Providing and filling murum / gravely soil ( CNS soil ) for foundation or
above pipes including breaking clods, spreading in layers of 10 to 15 cm,
IRR-CCDW-7-3 268 cum 358.30
watering, compaction by power roller to achieve density control of not less
than 98 percent etc., complete with lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads) cum 115.70
Providing and fixing one line dressed 111x35x25 cm thick IRC standard
kilometre stone in cement concrete M-10 grade with 40 mm down size
aggregates including excavating pit of size 70x45x40 cm, embedding the stone
IRR-CCDW-7-4 269 by 30 cm in concrete, providing 2 coats synthetic enamel paint of approved Each 1440.90
quality and colour to exposed surfaces and lettering as directed, cost of all
materials, labour, finishing, curing etc., complete with initial lead upto 50 m and
all lifts.
34
Abstract of work items_UNit Rates for the year 2016-17
Providing and fixing one line dressed 65x15x10 cm thick IRC standard
hectometre stone in cement concrete M-10 grade with 40 mm down size
aggregates including excavating pit of size 50x45x40 cm, embedding the stone
IRR-CCDW-7-5 270 by 30 cm in concrete, providing 2 coats synthetic enamel paint of approved Each 1048.60
quality and colour to exposed surfaces and lettering as directed, cost of all
materials, labour, finishing, curing etc., complete with initial lead upto 50 m and
all lifts.
Labour Component (including contractor's profit and Overheads) Each 413.30
Chapter V
IRR-GAW GATES / HOISTS AND ALLIED WORKS
RADIAL GATES
fabrication, supply, erection, testing and commissioning of radial gate
consisting of skin plate, stiffeners, horizontal girders, radial arms, trunnion
assemblies, tie beam, pulley supports, bracings, rubber seals, clamps etc., with
all accessories for spillway/canals including cost of all materials, machinery,
IRR-GAW-1-2 272 tonne 131718.40
labour, seal fixing etc., complete as per specifications and approved
drawings
(without painting on sand-blasted or mechanical cleaning surfaces which are added
extra as per scedule of rates under itemsinthis chapter and add as applicable
separately)
Labour Component (including contractor's profit and Overheads) tonne 36058.60
RADIAL GATES
Walk way(cat walk)
Design, fabrication, supply, erection and commissioning of 1 metre wide
walkway connecting spillway piers / abutments at trunnion platform level
IRR-GAW-1-4 274 including cost of all materials, machinery, labour, cutting, etc., complete as per Rm 99196.50
specifications and approved drawings
(without painting on sand-blasted or mechanical cleaning surfaces which are added
extra as per scedule of rates under items in this chapter and add as applicable
separately)
Labour Component (including contractor's profit and Overheads) Rm 34366.80
35
Abstract of work items_UNit Rates for the year 2016-17
36
Abstract of work items_UNit Rates for the year 2016-17
37
Abstract of work items_UNit Rates for the year 2016-17
HOISTS:STRUCTURAL COMPONENTS--
painting structurals on sand blasted surfaces with two coats of zinc
phosphate primer (airless spray preferred) 40microns/coat and one coat 65+/-
IRR-GAW-3-4 292 sqm 457.00
5 of alkyd based micaccous iron oxide paint followed by two coats of synthetic
enamel paint 25 microns/coat cost of all materials, labour, scaffolding etc.,
complete with all leads and all lifts
Labour Component (including contractor's profit and Overheads) sqm 209.80
38
Abstract of work items_UNit Rates for the year 2016-17
HOISTS:machineryCOMPONENTS--
painting hoist machinery, on sand blasted surfaces with one coats of zinc
IRR-GAW-3-5 293 sqm 413.10
phosphate primer (airless spray preferred) 50microns/coat and three coats of
aluminium paint or synthetic enamel , 25 microns/coat cost of all materials,
labour, scaffolding etc., complete with all leads and all lifts
Labour Component (including contractor's profit and Overheads) sqm 209.80
Chapter VI
IRR-PMW PRELIMINARY AND MAINTENANCE WORKS
Clearing thick jungle growth ( less than 50 percent open space ) including
IRR-PMW-1-2 298 bushes upto 30 cm / parthenium and other weeds including burning or sqm 2.20
disposing off the same as directed etc., complete.
Labour Component (including contractor's profit and Overheads) sqm 2.30
Removing stumps, tree roots, roots of bamboo clusters etc., upto 1.50 m girth
IRR-PMW-1-3 299 including excavation, stacking the materials neatly and levelling the surface etc., Each 51.30
complete with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads) Each 51.20
Removing stumps, tree roots, roots of bamboo cluster etc., with girth above
IRR-PMW-1-4 300 1.50 m and upto 3.0 m including excavation, stacking the materials neatly and Each 115.40
levelling the area etc., complete with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads) Each 115.40
39
Abstract of work items_UNit Rates for the year 2016-17
Cutting and stacking bamboos excluding removing stumps and roots etc.,
IRR-PMW-1-7 303 Each 15.00
complete with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads) Each 15.00
Cutting and removing jauliflora bushes upto 1.5 m girth excluding removal
IRR-PMW-1-8 304 of stumps and including burning or disposing off the materials as directed with Each 14.50
initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads) Each 14.50
Cutting and removing jauliflora bushes above 1.5 m upto 3.0 m girth
IRR-PMW-1-9 305 excluding removal of stumps and including burning or disposing off the materials Each 29.00
as directed with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads) Each 29.00
Cutting trees above 0.3 m and upto 0.6 m girth excluding removal of stumps
IRR-PMW-1-10 306 and including stacking the materials neatly as directed with initial lead upto 50 Each 97.40
m and all lifts.
Labour Component (including contractor's profit and Overheads) Each 94.30
Cutting trees above 0.6 m and upto 1.2 m girth excluding removal of stumps
IRR-PMW-1-11 307 and including stacking the materials neatly as directed with initial lead upto 50 Each 340.80
m and all lifts.
Labour Component (including contractor's profit and Overheads) Each 330.20
Cutting trees above 1.2 m and upto 1.8 m girth excluding removal of stumps
IRR-PMW-1-12 308 and including stacking the materials neatly as directed with initial lead upto 50 Each 681.70
m and all lifts.
Labour Component (including contractor's profit and Overheads) Each 660.40
Cutting trees above 1.8 m and upto 2.4 m girth excluding removal of stumps
IRR-PMW-1-13 309 and including stacking the materials neatly as directed with initial lead upto 50 Each 1363.40
m and all lifts.
Labour Component (including contractor's profit and Overheads) Each 1320.80
Cutting trees above 2.4 m and upto 3.0 m girth excluding removal of stumps
IRR-PMW-1-14 310 and including stacking the materials neatly as directed with initial lead upto 50 Each 2201.30
m and all lifts.
Labour Component (including contractor's profit and Overheads) Each 2116.10
Cutting and burning or disposing off Apu / Jondu from marshy areas as
IRR-PMW-1-16 312 sqm 5.30
directed with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads) sqm 5.30
Earthwork excavation for trial pits / borrow pits and other investigation works
IRR-PMW-2-1 313 in all kinds of soil including boulders upto 30 cm dia and disposing off cum 264.20
excavated soil as directed with lead upto 10 m and lift upto 3 m.
Labour Component (including contractor's profit and Overheads) cum 264.20
Earthwork excavation for trial pits / borrow pits and other investigation works
IRR-PMW-2-2 314 in soft rock including disposing off the excavated rock as directed with lead cum 369.20
upto 10 m and lift upto 3 m.
Labour Component (including contractor's profit and Overheads) cum 369.20
40
Abstract of work items_UNit Rates for the year 2016-17
Drilling 80 mm dia hole through over-burden using casing shoe bit vertical or
inclined upto 10 degrees to vertical as directed including cost of all materials,
machinery, labour, water charges, reaming, collection of wash samples at
suitable intervals, logging and lebelling, supplying honne wood core box, fixing
casing pipes ( excluding cost of casing pipes ) etc., complete for depth
IRR-PMW-2-4 316 upto 30 m from surface. Rm 1206.50
1. For driiling through over-burden beyond 30 m from surface increase the rate
per Rm by 10 percent.
2. For providing HDPE or light black MS casing pipe add the cost of pipe per
Rm.
Labour Component (including contractor's profit and Overheads) Rm 456.70
Drilling 76 mm dia ( NX ) core hole in hard rock using diamond core bit
vertical / inclined upto 10 degree to vertical as directed including cost of all
materials, machinery, labour, water charges, collection of core samples, logging
and lebelling, supplying honne wood core box and redrilling in case of collapse of
IRR-PMW-2-5 317 sides etc., complete for depth upto 30 m from surface. Rm 6062.20
1. For driiling in hard rock beyond 30 m upto 60 m from surface increase the rate
per Rm by 25 percent.
2. For driiling in hard rock beyond 60 m upto 90 m from surface increase the rate
per Rm by 40 percent.
Labour Component (including contractor's profit and Overheads) Rm 1798.40
Drilling 76 mm dia ( NX ) core hole in all types of rocks (other than Hard
Rock) including Masonry/CC (where drilling is not possible by casing
shoe) using diamond core bit vertical / inclined upto 10 degree to vertical as
IRR-PMW-2-5-A directed including cost of all materials, machinery, labour, water charges, and
(New Item2015- 318 redrilling in case of collapse of sides etc., complete for depth upto 30 m from Rm 3879.90
16)-5 surface for Primary and Secondary Holes
1. For drilling in all types of rocks (other than hard rock) including masonry/CC
beyond 30 m upto 60 m from surface increase the rate per Rm by 25 percent.
2. For drilling in all types of rocks (other than hard rock) including masonry/CC
beyond 60 m upto 90 m from surface increase the rate per Rm by 40 percent.
Labour Component (including contractor's profit and Overheads) Rm 1073.10
Drilling 76 mm dia ( NX ) core hole in all types of rocks (other than Hard
Rock) including Masonry/CC (where drilling is not possible by casing
shoe) using diamond core bit vertical / inclined upto 10 degree to vertical as
directed including cost of all materials, machinery, labour, water charges,
IRR-PMW-2-5-B
(New Item2015- 319 collection of core samples, logging and lebelling, supplying honne wood core box Rm 4667.40
and redrilling in case of collapse of sides etc., complete for depth upto 30 m
16)-6
from surface for Test Holes
1. For drilling in all types of rocks (other than hard rock) including masonry/CC
beyond 30 m upto 60 m from surface increase the rate per Rm by 25 percent.
2. For drilling in all types of rocks (other than hard rock) including masonry/CC
beyond 60 m upto 90 m from surface increase the rate per Rm by 40 percent.
Labour Component (including contractor's profit and Overheads) Rm 1073.70
41
Abstract of work items_UNit Rates for the year 2016-17
Drilling 47 mm (BX )dia core hole in hard rock using diamond core bit vertical
/ inclined upto 10 degree to vertical as directed including cost of all materials,
machinery, labour, water charges,collection of core samples,logging, lebelling,
supplying honne wood core box and redrilling in case of collapse of sides etc.,
IRR-PMW-2-6 320 complete for depth upto 30 m from surface. Rm 5901.60
1. For drilling in hard rock beyond 30 m upto 60 m from surface increase the rate
per Rm by 25 percent.
2. For drilling in hard rock beyond 60 m upto 90 m from surface increase the rate
per Rm by 40 percent.
Labour Component (including contractor's profit and Overheads) Rm 1798.40
Drilling 47 mm (BX )dia core hole in all types of rocks (other than Hard
Rock) including Masonry/CC (where drilling is not possible by casing shoe)
IRR-PMW-2-6-A using diamond core bit vertical / inclined upto 10 degree to vertical as directed
(New Item2015- 321 including cost of all materials, machinery, labour, water charges, and redrilling Rm 3652.10
16)-7 in case of collapse of sides etc., complete for depth upto 30 m
1. For drilling in all types of rocks (other than hard rock) including masonry/CC
beyond 30 m upto 60 m from surface increase the rate per Rm by 25 percent.
2. For drilling in all types of rocks (other than hard rock) including masonry/CC
beyond 60 m upto 90 m from surface increase the rate per Rm by 40 percent.
Labour Component (including contractor's profit and Overheads) Rm 1073.10
Removing dry stone rock-toe / rivetment and filter layers below rock-toe/
IRR-PMW-3-1 325 rivetment including stacking all materials separately as directed with initial cum 212.60
lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads) cum 212.60
Re-constructing dry rubble rock-toe and filter media for rock-toe consisting
of sand 20 mm and 80 mm size graded aggregates satisfying filter criteria laid in
layers of 15 cm thick each using sand from approved quarry and stones and filter
IRR-PMW-3-3 327 cum 238.40
aggregates obtained from rock-toe removed for re-construction including cost of
all machinery, labour, laying filter and stones to specified slopes, wedging with
chips, finishing etc. complete with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads) cum 227.80
42
Abstract of work items_UNit Rates for the year 2016-17
Repairing rain cuts / resectioning canal slopes to required lines and grades
IRR-PMW-3-12 336 as directed using available soil including dressing, clod breaking, packing, sqm 3.70
tamping etc., complete with all leads and lifts.
Labour Component (including contractor's profit and Overheads) sqm 3.70
Cleaning dam parapet inner face and top using oxalic acid and water by
IRR-PMW-3-14 338 scrubbing / brushing and washing to remove all surface coatings etc., complete Rm 36.50
.
Labour Component (including contractor's profit and Overheads) Rm 23.90
43
Abstract of work items_UNit Rates for the year 2016-17
Excavation and removal of silt and silt mixed with sand from canal bed in
dry condition including disposing off the same in spoil bank or on the canal
IRR-PMW-3-20 339 cum 159.10
embankment in layers as directed etc., complete with initial lead upto 50 m and
all lifts.
Labour Component (including contractor's profit and Overheads) cum 159.10
Excavation and removal of silt or silt mixed with sand in slussy condition
from canal bed including disposing off the same in spoil bank or on the canal
IRR-PMW-3-21 340 cum 198.80
embankment in layers as directed etc., complete with initial lead upto 50 m and
all lifts.
Labour Component (including contractor's profit and Overheads) cum 198.80
COM-MWRK New extra items-- common item for all earth works using only manual labour for all other works
without involving contractors
44
Abstract of work items_UNit Rates for the year 2016-17
(Manual)Excavation in all kinds of soil including boulders upto 0.30 m dia. for
foundations of canal cross drainage and other appurtenant structures and
placing excavated stuff neatly in specified dump area or disposing off the same
COM-MWRK-1 351 cum 116.70
as directed etc., complete with initial lead upto 10 m and initial lift upto 1.5 m.
(WIthout involving the contractors for specified works )
With 3 Cum per day output
45
Abstract of leads and lifts - for the year 2016-17
COM-LDLFT Abstract
LEAD, LIFT, LOADING AND UNLOADING CHARGES FOR MATERIALS
FOR THE YEAR: 2016-17
COM-LDLFT 1 For total lead upto 150 m ( including initial lead ) lead charges by head load only shall be adopted irrespective of
mode of conveyance.
2 For total lead exceeding 150 m conveyance by mechanical means only shall be adopted irrespective of
mode of conveyance.
3 The rates for loading at quarry including idle hire charges of trucks and hire charges per for each kilometer and
upto 5 km are cumulative and inclusive of total charges for preceding lead.
4 Unless otherwise specified lead charges for Earth / Sand / Gravel / Aggregates and Stones are for loose volume and
not for compacted or in-situ volume.
5 The rates for lift charges,lead charges hire cahrges are cumulative are cumulative and inclusive of rates for preceding
lift,load and hire charges
6 Lift charges are not payable where conveyance of materials is by mechanical means to final placing point.
7 Loading and unloading charges are not payable for conveyance by head load.
8 Loading charges are not payable for conveyance by mechanical means for disposal of excavated materials beyond
initial lead of 50 m wherever specified.
9 Loading and unloading charges are not payable for conveyance by mechanical means for disposal of excavated
materials beyond initial lead of 1 km wherever specified.
10 The rates for unloading of materials except earth, sand, gravel, coarse aggregate, rubble, size stone and cut stone
are inclusive of stacking.
11 Hire charges are per 1KM for tippers and trucks for tranport of materials from work site
to dump yard and other places are cumulative& includes previous km upto 5 kms
12 The lead & lift charges are inclusive of contractor's profit and overhead charges of 13.615%
13 During the BoCE meeting held on 24-05-2014, it is observed that in some of the estimates, Lead
Charges are being added directly to the material basic rates for arriving the finished item rate. In view
of that, the BoCE has instructed to see that while arriving the finished item rate, the lead
charges are to be added to the material basic rates only after deducting the provision of
"Contractor's Profit and Overhead charges"
14
During the BoCE meeting held on 10.06.2015,the BoCEs has recommended to withdraw lead
charges,loading and unloading charges for Cement as per the Sub-Committee minutes of meeting for the
month of June -2015 dt:29.06.2015.(The conveyance charges ,loading & unloading charges for cement are
displayed for information purpose only).
46
Abstract of leads and lifts - for the year 2016-17
Note:The Lead & Lift Charges are inclusive of 13.615% Contractor's Profit and Over Head Charges
COM-LDLFT-3 C. LOADING AND UNLOADING CHARGES BY MANUAL MEANS (idle hire charges of trucks are not added)
COM-LDLFT-4 D. LOADING AND UNLOADING CHARGES BY MANUAL MEANS (including idle hire charges of trucks )
COM-LDLFT-5 E. LOADING AND UNLOADING CHARGES BY MECHANICAL MEANS (including idle hire charges of trucks)
Earth / Sand
/Gravel PCC slab/
Murrum/ Lime/ Cement/ Shahbad
Total lift Surki/ Reinforce- slab / CC
Sl No. ( Total lift includes Size stone / Cut ment steel block/ BS
initial lift ) stone Str steel slab / Laterite
Rubble / Coarse Rs / tonne / Wood
aggregate Rs / cum
Rs / cum
1 2 3 4 5
Note:The Lead & Lift Charges are inclusive of 13.615% Contractor's Profit and Over Head Charges
47
Dam and Allied Works - Item Unit Rates 2016-17
Chapter - I
3. The Leads for Steel shall be from the nearest market place to the Project area
4. For earth/rockfill embankments wherever initial lead of 1km is considered in the basic rate, the additional lead charges are to be added as follows:
Additional lead charges for Earth, Murrum etc., shall be worked out for total lead involved and 1 km lead charges included in basic rate shall be deducted from total
lead charges. No loading and unloading charges shall be allowed for any item. (same as above)
Example:
Total lead for earth from approved borrow area : 15 Km
Initial lead included in the basic rate in the SR : 1 Km
Additional lead charges : Lead charges for 5 km Rs. 84.00
Lead charges for next 10 km Rs. 126
Total lead charges for 15 km /cum Rs. 210.00
Less 1 km initial lead charges /cum Rs. 31.50 (-)
Net additional lead charges / cum Rs. 178.50
5. The initial lead up to 50 m as mentioned in some standard data items is meant for manual lead within the working area. For conveyance of materials, the
lead required from quarry/Borrow area/ Dump Area to worksite shall be added to the data without deducting the 50 m initial lead charges
IRR-DAW-1-1 Excavation for foundation in all kinds of soil including boulders upto
0.30 m diameter for dam, spillway, intake structure and other appurtenant
works and placing the excavated soil neatly in dump area or disposing off
the same as directed etc., complete with initial lead upto 1 km
and all lifts.
A. MATERIALS: UNIT
880 cum
Sl No Particulars Unit Quantity Rate Amount
in Rs. in Rs
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total cost of Materials Rs: 0.00
B. MACHINERY:
C. LABOUR:
48
Dam and Allied Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 73676.00
C. Cost of Labour Rs: 20263.60
Total Rs: 93939.60
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 12789.88
Total cost for 880.00 cum Rs: 106729.48
Rate per cum (A+B+C+D)/880 Rs: 121.30
IRR-DAW-1-2 Excavation for foundation in ordinary rock (including HDR) without blasting including
boulders above 0.3 m upto 0.6 m dia for dam, spillway, intake structure and
other appurtenant works and placing the excavated material neatly in dump
area or disposing off the same as directed etc., complete with initial lead
upto 1 km and all lifts.
A. MATERIALS: UNIT :
520 cum
Sl No Particulars Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total cost of Materials Rs: 0.00
B. MACHINERY:
C. LABOUR:
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 57986.40
C. Cost of Labour Rs: 15530.00
Total Rs: 73516.40
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 10009.26
Total cost for 520.00 cum Rs: 83525.66
Rate per cum (A+B+C+D)/520 Rs: 160.60
IRR-DAW-1-3 Excavation for foundation in hard rock (including F&F rock) requiring blasting including
boulders above 0.6 m upto 1.2 m dia. for dam, spillway, intake structure
and other appurtenant works and placing the excavated material neatly in
dump area or disposing off the same as directed etc., complete with initial
lead upto 1 km and all lifts.
DATA: RATE ANALYSIS
A. MATERIALS: UNIT :
520.00 cum.
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Use rate of 1.5 m drill rod Rm 216.00 20.14 4350.24
Reconditioning charges @ 10% 435.02
2 Use rate of air hose 4 Nos. Hour 26.00 11.56 300.63
3 Explosive small dia kg 104.00 70.00 7280.00
4 Electric detonators Nos 154.00 11.00 1694.00
5 Fuse coil Rm 320.00 9.00 2880.00
6 Sundries LS 5.00 30.00 150.00
Total cost of Materials Rs. 17089.89
B. MACHINERY:
49
Dam and Allied Works - Item Unit Rates 2016-17
4 Air compressor 8.5 cmm ( ele ) 2 Nos Hour 13.00 170.80 2220.40
Fuel / Energy charges Hour 13.00 315.20 4097.60
5 Jack hammers 4 Nos. Hour 26.00 19.80 514.80
Fuel / Energy charges Hour 26.00 0.00 0.00
Total hire charges of Machinery Rs: 64819.20
C. LABOUR:
ABSTRACT:
A. Cost of Materials Rs: 17089.89
B. Hire charges of Machinery Rs: 64819.20
C. Cost of Labour Rs: 27552.00
Total Rs: 109461.09
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 14903.13
Total cost for 520.00 cum. Rs: 124364.22
Rate per cum. (A+B+C+D)/520 Rs: 239.20
IRR-DAW-1-3A
New Item 2015-16-1 Excavation for foundation in hard rock (including F&F rock) including
boulders above 0.6 m upto 1.2 m dia. by controlled blasting and controlling fly rock by muffling arrangements
for dam, spillway, intake structure and other appurtenant works and other open foundation works and placing the excavated
material neatly in dump area or disposing off the same as directed etc., complete with initial lead upto 1 km and all leads
B. MACHINERY:
C. LABOUR:
50
Dam and Allied Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 68107.02
B. Hire charges of Machinery Rs: 67145.20
C. Cost of Labour Rs: 32543.60
Total Rs: 167795.82
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 22845.4
Total cost for 520.00 cum. Rs: 190641.22
Rate per cum. (A+B+C+D)/520 Rs: 366.60
UNIT
A. MATERIALS: 320.00 cum
Sl No Particulars Unit Quantity Rate Amount
in Rs. in Rs
1 Use rate of drill rod 1.5 m long Rm 310.00 26.85 8324.53
Reconditioning charges @ 10% 832.45
2 Use rate of air hose 4 Nos. Hour 48.00 11.56 555.00
3 Explosive small dia kg 95.00 70.00 6650.00
4 Ordinary detonators Nos 10.00 7.00 70.00
5 Electric detonators Nos 333.00 11.00 3663.00
6 Fuse coil Rm 450.00 9.00 4050.00
7 Sundries LS 5.00 30.00 150.00
Total cost of Materials Rs: 24294.98
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Shovel 0.85 cum capacity Hour 8.00 1706.60 13652.80
Fuel / Energy charges Hour 8.00 872.70 6981.60
2 Dumpers 5 cum capacity 3 Nos. Hour 24.00 580.70 13936.80
Fuel / Energy charges Hour 24.00 399.90 9597.60
3 Tipper 5 cum capacity 1 No Hour 4.00 446.70 1786.80
Fuel / Energy charges Hour 4.00 299.90 1199.60
4 Angle dozer 90 hp Hour 1.00 1715.50 1715.50
Fuel / Energy charges Hour 1.00 610.50 610.50
5 Air compressor 8.5 cmm (ele) 2 Nos. Hour 24.00 170.80 4099.20
Fuel / Energy charges Hour 24.00 315.20 7564.80
6 Jack hammers 4 Nos. Hour 48.00 19.80 950.40
Fuel / Energy charges Hour 48.00 0.00 0.00
Total hire charges of Machinery Rs. 62095.60
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Shovel Hour 8.00 236.60 1892.80
2 Crew for Dumper Hour 24.00 227.10 5450.40
3 Crew for Tipper Hour 4.00 177.50 710.00
4 Crew for Dozer Hour 1.00 236.60 236.60
5 Crew for Air compressor Hour 24.00 164.80 3955.20
6 Crew for Jack hammer Hour 48.00 329.60 15820.80
7 work inspector Day 1.00 450.00 450.00
8 Blaster Day 1.00 510.00 510.00
9 Helper blaster Day 1.00 400.00 400.00
10 Crowbarman Day 1.00 400.00 400.00
11 Stone breaker Day 2.00 400.00 800.00
12 mazdoor Day 6.00 350.00 2100.00
Total cost of Labour Rs. 32725.80
labour component/unit qty 102.30
Add contractor's profit and overhead charges 13.615% 13.90
labour component/unit qty (including contractor's profit) 116.20
ABSTRACT:
A. Cost of Materials Rs: 24294.98
B. Hire charges of Machinery Rs: 62095.60
C. Cost of Labour Rs: 32725.80
Total Rs: 119116.38
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 16217.7
Total cost for 320.00 cum Rs: 135334.08
Rate per cum (A+B+C+D)/320 Rs: 422.90
IRR-DAW-1-5 Excavation for foundation in hard rock of all toughness including boulders
(b) above 1.2 m dia. by controlled blasting method and controlling fly-rock
by muffling arrangements for dam, spillway, intake structure and other
appurtenant structures etc., including placing and levelling the excavated
rock neatly in dump area or other place as directed etc., complete with
lead upto upto 1 km and all lifts.
51
Dam and Allied Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Unit Quantity Rate Amount
Particulars in Rs. in Rs
1 Shovel 0.85 cum capacity Hour 12.00 1706.60 20479.20
Fuel / Energy charges Hour 12.00 872.70 10472.40
2 Angle dozer 90 hp Hour 2.00 1715.50 3431.00
Fuel / Energy charges Hour 2.00 610.50 1221.00
3 Dumpers 5 cum capacity 3 Nos. Hour 36.00 580.70 20905.20
Fuel / Energy charges Hour 36.00 399.90 14396.40
4 Tipper 5 cum capacity 1 No Hour 4.00 446.70 1786.80
Fuel / Energy charges Hour 4.00 299.90 1199.60
5 Air compressor 8.5 cmm ( ele ) 2 Nos Hour 35.00 170.80 5978.00
Fuel / Energy charges Hour 35.00 315.20 11032.00
6 Jack hammers 4 Nos. Hour 70.00 19.80 1386.00
Fuel / Energy charges Hour 70.00 0.00 0.00
Total hire charges of Machinery Rs: 92287.60
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Shovel Hour 12.00 236.60 2839.20
2 Crew for Angle dozer Hour 2.00 236.60 473.20
3 Crew for Dumper Hour 36.00 227.10 8175.60
4 Crew for Tipper Hour 4.00 177.50 710.00
5 Crew for Air compressor Hour 35.00 164.80 5768.00
6 Crew for Jack hammer Hour 70.00 329.60 23072.00
7 work inspector Day 4.50 450.00 2025.00
8 Blaster Day 1.50 510.00 765.00
9 Helper blaster Day 3.00 400.00 1200.00
10 Crowbarman Day 2.50 400.00 1000.00
11 Stone breaker Day 2.50 400.00 1000.00
13 mazdoor Day 20.00 350.00 7000.00
Total cost of Labour Rs. 54028.00
labour component/unit qty 112.60
Add contractor's profit and overhead charges 13.615% 15.30
labour component/unit qty (including contractor's profit) 127.90
ABSTRACT:
A. Cost of Materials Rs: 134822.49
B. Hire charges of Machinery Rs: 92287.60
C. Cost of Labour Rs: 54028.00
Total Rs: 281138.09
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 38276.95
Total cost for 480.00 cum Rs: 319415.04
Rate per cum (A+B+C+D)/480 Rs: 665.40
IRR-DAW-1-6 Excavation for foundation in hard rock of all toughness including boulders
( c) above 1.2 m dia. by line drilling and smooth blasting and controlling
fly-rock by muffling arrangements for dam, spillway, intake structure and
other appurtenant structures etc., including dressing sides and bed to
required level / profile, placing and levelling the excavated rock neatly in
dump area or other place as directed etc., complete with lead upto 1 km and
all lifts.
Note : i ) 1 m width of excavation along the face to be dressed shall be treated as
excavation by line drilling and smooth blasting.
ii) The rate includes controlling fly-rock wherever required.
iii ) The rate under this item shall be paid only on ascertaining that the
surface requiring dressing has come off neatly as per specifications or
atleast 50 percent of smooth blast holes are visible for inspection and are
spaced at specified interval.
iv ) In case, where the above criteria is not fulfilled payment shall be
restricted to the rate provided for excavation by normal or controlled blasting
as the case may be..
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Shovel 0.85 cum capacity Hour 1.00 1706.60 1706.60
Fuel / Energy charges Hour 1.00 872.70 872.70
52
Dam and Allied Works - Item Unit Rates 2016-17
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Shovel Hour 1.00 236.60 236.60
2 Crew for Angle dozer Hour 0.25 236.60 59.15
3 Crew for Dumper Hour 3.00 227.10 681.30
4 Crew for Air compressor Hour 11.00 164.80 1812.80
5 Crew for Jack hammer Hour 22.00 329.60 7251.20
6 work inspector Day 0.50 450.00 225.00
7 Blaster Day 0.50 510.00 255.00
8 Helper blaster Day 0.50 400.00 200.00
9 Crowbarman Day 0.50 400.00 200.00
10 Stone breaker Day 0.50 400.00 200.00
11 mazdoor Day 2.00 350.00 700.00
Total cost of Labour Rs. 11821.05
labour component/unit qty 295.50
Add contractor's profit and overhead charges 13.615% 40.20
labour component/unit qty (including contractor's profit) 335.70
ABSTRACT:
A. Cost of Materials Rs: 7919.72
B. Hire charges of Machinery Rs: 11884.21
C. Cost of Labour Rs: 11821.05
Total Rs: 31624.98
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 4305.74
Total cost for 40.00 cum Rs: 35930.72
Rate per cum (A+B+C+D)/40 Rs: 898.30
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Air compressor 8.5 cmm ( ele ) Hour 1.00 170.80 170.80
Fuel / Energy charges Hour 1.00 315.20 315.20
2 Pump 5 hp ( ele ) Hour 1.00 3.00 3.00
Fuel / Energy charges Hour 1.00 28.00 28.00
Total hire charges of Machinery Rs. 517.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Air compressor Hour 1.00 164.80 164.80
2 Crew for Pump Hour 1.00 83.30 83.30
3 Stone breaker Day 2.00 400.00 800.00
4 mazdoor Day 2.50 350.00 875.00
5 Crowbar man Day 2.00 400.00 800.00
Total cost of Labour Rs: 2723.10
labour component/unit qty 27.20
Add contractor's profit and overhead charges 13.615% 3.70
labour component/unit qty (including contractor's profit) 30.90
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 517.00
C. Cost of Labour Rs: 2723.10
Total Rs: 3240.10
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 441.14
Total cost for 100.00 sqm Rs: 3681.24
Rate per sqm (A+B+C+D)/100 Rs: 36.80
IRR-DAW-1-8 Preparing foundation bed for cut-off trench filling in rock portion by
removing all loose materials by wedging / chiselling and disposing off the
same as directed etc., complete with initial lead upto 50 m and all lifts.
53
Dam and Allied Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total cost of Machinery Rs. 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crowbar man Day 2.00 400.00 800.00
2 Stone breaker Day 2.00 400.00 800.00
3 mazdoor Day 2.00 350.00 700.00
Total cost of Labour Rs: 2300.00
labour component/unit qty 23.00
Add contractor's profit and overhead charges 13.615% 3.10
labour component/unit qty (including contractor's profit) 26.10
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 2300.00
Total Rs: 2300.00
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 313.15
Total cost for 100.00 sqm Rs: 2613.15
Rate per sqm (A+B+C+D)/100 Rs: 26.10
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Waggon drill Hour 8.00 188.50 1508.00
Fuel / Energy charges Hour 8.00 0.00 0.00
2 Air compressor 8.5 cmm ( ele ) Hour 8.00 170.80 1366.40
Fuel / Energy charges Hour 8.00 315.20 2521.60
3 Sundries LS 2.00 30.00 60.00
Total hire charges of Machinery Rs: 5456.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Waggon drill Hour 8.00 283.90 2271.20
2 Crew for Air compressor Hour 8.00 164.80 1318.40
3 mazdoor Day 2.00 350.00 700.00
Total cost of Labour Rs: 4289.60
labour component/unit qty 44.70
Add contractor's profit and overhead charges 13.615% 6.10
labour component/unit qty (including contractor's profit) 50.80
ABSTRACT:
A. Cost of Materials Rs: 6760.56
B. Hire charges of Machinery Rs: 5456.00
C. Cost of Labour Rs: 4289.60
Total Rs: 16506.16
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 2247.31
Total cost for 96.00 Rm Rs: 18753.47
Rate per Rm (A+B+C+D)/96 Rs: 195.30
54
Dam and Allied Works - Item Unit Rates 2016-17
IRR-DAW-1-10 Flushing grout holes of all sizes with water and air jets alternatively for an
average period of 30 minutes including water intake observations after
flushing, cost of all materials, machinery, labour etc., complete.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Air compressor 8.5 cmm ( ele ) Hour 8.00 170.80 1366.40
Fuel / Energy charges Hour 8.00 315.20 2521.60
2 Pump 5 hp ( ele ) Hour 8.00 3.00 24.00
Fuel / Energy charges Hour 8.00 28.00 224.00
3 Sundries LS 2.00 30.00 60.00
Total hire charges of Machinery Rs: 4196.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Air compressor Hour 8.00 164.80 1318.40
2 Crew for Pump Hour 8.00 83.30 666.40
3 mazdoor Day 4.00 350.00 1400.00
Total cost of Labour Rs: 3384.80
labour component/unit qty 17.60
Add contractor's profit and overhead charges 13.615% 2.40
labour component/unit qty (including contractor's profit) 20.00
ABSTRACT:
A. Cost of Materials Rs: 429.92
B. Hire charges of Machinery Rs: 4196.00
C. Cost of Labour Rs: 3384.80
Total Rs: 8010.72
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 1090.66
Total cost for 192.00 Rm. Rs: 9101.38
Rate per Rm. (A+B+C+D)/192 Rs: 47.40
B. MACHINERY:
55
Dam and Allied Works - Item Unit Rates 2016-17
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Grout pump Hour 8.00 263.60 2108.80
2 Crew for Pump Hour 2.00 83.30 166.60
3 mazdoor ( cement handling) Day 2.00 350.00 700.00
Total cost of Labour Rs: 2975.40
labour component/unit qty 2833.70
Add contractor's profit and overhead charges 13.615% 385.80
labour component/unit qty (including contractor's profit) 3219.50
ABSTRACT:
A. Cost of Materials Rs: 5799.98
B. Hire charges of Machinery Rs: 545.20
C. Cost of Labour Rs: 2975.40
Total Rs: 9320.58
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 1269
Lead Charges for 1Km for Cement 1.05 Tonne @ (including
Loading and Unloading Charges) 143.80 Rs/Tonne 150.99
Total cost for 1.05 tonne Rs: 10740.57
Rate per tonne (A+B+C+D)/1.05 Rs: 10229.10
IRR-DAW-1-12 Curtain grouting with neat cement grout mix of suitable consistency
(b) under specified pressure as directed in drilled holes by stage grouting
method including cost of all materials, machinery, labour, redrilling if
necessary etc., complete with initial lead upto 1 km and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Grouting equipment Hour 8.00 24.90 199.20
Fuel / Energy charges Hour 8.00 28.00 224.00
2 Pump 5 hp ( ele ) Hour 2.00 3.00 6.00
Fuel / Energy charges Hour 2.00 28.00 56.00
3 Sundries LS 2.00 30.00 60.00
Total hire charges of Machinery Rs: 545.20
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Grout pump Hour 8.00 263.60 2108.80
2 Crew for Pump Hour 2.00 83.30 166.60
3 Pipe fitter Day 1.00 510.00 510.00
4 mazdoor ( cement handling ) Day 3.00 350.00 1050.00
Total cost of Labour Rs: 3835.40
labour component/unit qty 3652.80
Add contractor's profit and overhead charges 13.615% 497.30
labour component/unit qty (including contractor's profit) 4150.10
ABSTRACT:
A. Cost of Materials Rs: 5943.74
B. Hire charges of Machinery Rs: 545.20
C. Cost of Labour Rs: 3835.40
Total Rs: 10324.34
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 1405.66
Lead Charges for 1Km for Cement 1.05 Tonne @ (including
Loading and Unloading Charges) 143.80 Rs/Tonne 150.99
Total cost for 1.05 tonne Rs: 11880.99
Rate per tonne (A+B+C+D)/1.05 Rs: 11315.20
IRR-DAW-1-13 Providing and fixing 25 mm dia 3 m long cold twisted deformed steel
dowel bars with one end driven into 45 to 50 mm diameter 1.50 m deep
hole drilled in bed rock and other end provided with L-bend for embedding in
concrete / masonry of over flow / non-over flow blocks and other appertenant
works including cost of drilling and cleaning hole, filling hole with cement
mortar 1 : 1 proportion, driving anchor rod, cost of all materials, machinery,
labour etc., complete with initial lead upto 1 km and all lifts.
Consider 25 anchor rods for analysis.
56
Dam and Allied Works - Item Unit Rates 2016-17
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Air compressor Hour 4.00 164.80 659.20
2 Crew for Waggon drill Hour 4.00 283.90 1135.60
3 Bar bender Day 0.50 555.00 277.50
4 Mason Cl- II Day 0.50 400.00 200.00
5 mazdoor Day 1.00 350.00 350.00
Total cost of Labour Rs: 2622.30
labour component/unit qty 104.90
Add contractor's profit and overhead charges 13.615% 14.30
labour component/unit qty (including contractor's profit) 119.20
ABSTRACT:
A. Cost of Materials Rs: 13137.73
B. Hire charges of Machinery Rs: 2698.00
C. Cost of Labour Rs: 2622.30
Total Rs: 18458.03
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 2513.06
Lead Charges for 1 Km for FA 0.05 cum @ 31.5 Rs./Cum 1.575
Lead Charges for 1Km for Steel (including Loading
and Unloading Charges) 0.30 tonne @ 168.6 Rs./Tonne 51.122892
Total cost for 25.00 Nos. Rs: 21023.79
Rate per Each (A+B+C+D)/25 Rs: 841.00
IRR-DAW-1-14 Providing and fixing 25 mm dia. 2.75 m long ribbed steel anchor rods
with one end split and driven firmly using steel wedge into 1.25 m deep 45
to 50 mm dia. hole drilled in bed rock and other end provided with L- bend
for embedding in concrete / masonry for spillway and appurtenant works
including drilling and cleaning hole, filling hole with thick cement slurry,
driving anchor rod, cost of all materials, machinery, labour, steel wedge
etc., complete with initial lead upto 1 km and all lifts.
Consider 25 anchor rods for analysis.
ABSTRACT:
A. Cost of Materials Rs: 12141.54
B. Hire charges of Machinery Rs: 2023.50
C. Cost of Labour Rs: 2968.60
Total Rs: 17133.64
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 2332.75
Lead Charges for 1Km for Steel (including Loading
and Unloading Charges) 0.28 tonne @ 168.6 Rs./Tonne 46.857312
Total cost for 25.00 Nos. Rs: 19513.25
Rate per Each (A+B+C+D)/25 Rs: 780.50
57
Dam and Allied Works - Item Unit Rates 2016-17
IRR-DAW-2-1A Providing, fabricating and placing in position reinforcement steel for RCC,below 36 dia rods
overlaps and wastages wherever required, tying with 1.25 mm diameter soft
annealed steel wire, including cost of all materials, machinery, labour etc.,
complete with initial lead upto 1 km and all lifts.
overlaps and wastage as per NHAI-data
Lap jointing considered for bars upto 36 mm diameter.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Bar bender Day 2.00 555.00 1110.00
2 mazdoor Day 6.84 350.00 2394.00
Total cost of Labour 3504.00
labour component/unit qty 3504.00
Add contractor's profit and overhead charges 13.615% 477.10
labour component/unit qty (including contractor's profit) 3981.10
A.MATERIAL 36240.00
B.MACHINERY 0.00
C. LABOUR 3504.00
Total 39744.00
D.Add for contractor's profit and overheads on A+B+C 13.615% 5411.15
Lead Charges for 1Km for Steel (including Loading
and Unloading Charges) 168.60 Rs/Tonne 177.03
Total cost for 1.00 tonne 45332.18
Rate per/ TON.=(A+B+C+D) / I 45332.18
IRR-DAW-2-1B Providing, fabricating and placing in position reinforcement steel for RCC
above 36 dia with welding and wastage at 2.5%, tying with 1.25 mm diameter soft
annealed steel wire, including cost of all materials, machinery, labour etc.,
complete with initial lead upto 1 km and all lifts.
overlaps and wastage as per NHAI-data
welding joints considered for bars above 36 mm diameter.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 welding machine hour 10.00 16.00 160.00
fuel charges hour 10.00 67.20 672.00
Total hire charges of Machinery Rs: 832.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 welder day 2.50 445.00 1112.50
2 Bar bender Day 2.00 555.00 1110.00
3 mazdoor Day 6.84 350.00 2394.00
Total cost of Labour 4616.50
labour component/unit qty 4616.50
Add contractor's profit and overhead charges 13.615% 628.50
labour component/unit qty (including contractor's profit) 5245.00
ABSTRACT:
A. Cost of Materials 35760.00
B. Hire charges of Machinery 832.00
C. Cost of Labour 4616.50
Total 41208.50
D.Add for contractor's profit and overheads on A+B+C 13.615% 5610.54
Lead Charges for 1Km for Steel (including Loading
and Unloading Charges) 168.60 Rs/Tonne 172.815
Total cost for 1.00 tonne 46991.86
Rate per/ TON.=(A+B+C+D) / I 46991.86
IRR-DAW-2-2 Providing and laying insitu vibrated M-15 ( 28 days cube compressive
strength not less than 15 N / sq mm ) grade cement concrete using 80 mm
down size approved, clean, hard, graded aggregates including cost of all
materials, machinery, labour, formwork, centering, scaffolding, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc.,complete for plain concrete works with initial lead upto 1 km and
58
Dam and Allied Works - Item Unit Rates 2016-17
all lifts. ( Cement content : 250 kg /cum with use of super plasticiser
equal to 0.4% of cement content , CA : 0.98 cum,
Blending Ratio of CA -- 40:30:20:10, FA : 0.35 cum )
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Batching plant Hour 8.00 620.70 4965.60
Fuel / Energy charges Hour 8.00 308.20 2465.60
2 Air compressor 7 cmm ( ele ) Hour 8.00 131.90 1055.20
Fuel / Energy charges Hour 8.00 252.20 2017.60
3 Tipper Hour 32.00 446.70 14294.40
Fuel / Energy charges Hour 32.00 299.90 9596.80
4 Tower crane 5 t Hour 16.00 867.10 13873.60
Fuel / Energy charges Hour 16.00 145.70 2331.20
5 Concrete bucket Hour 40.00 15.80 632.00
Fuel / Energy charges Hour 40.00 0.00 0.00
6 10 hp pump ( ele ) Hour 8.00 6.70 53.60
Fuel / Energy charges Hour 8.00 56.00 448.00
7 Needle vibrator 60 mm dia ( ele ) Hour 16.00 9.70 155.20
Fuel / Energy charges Hour 16.00 8.40 134.40
8 Sundries LS 10.00 30.00 300.00
Total hire charges of Machinery Rs: 52323.20
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Batching plant Hour 8.00 340.60 2724.80
2 Crew for Air compressor Hour 8.00 164.80 1318.40
3 Crew for Tipper ( 4 ) Hour 32.00 177.50 5680.00
4 Crew for Tower crane ( 2 ) Hour 16.00 189.30 3028.80
5 Crew for Pump Hour 8.00 83.30 666.40
6 Crew for Needle vibrator ( 2 ) Hour 16.00 158.20 2531.20
7 Mason Class-I Day 4.00 445.00 1780.00
8 Foreman Day 2.00 510.00 1020.00
9 mazdoor
for silo ( cement handling ) Day 2.00 350.00 700.00
for batching plant Day 2.00 350.00 700.00
for conveyor system Day 2.00 350.00 700.00
for laying & vibrating Day 6.00 350.00 2100.00
for cleaning / washing / curing Day 2.00 350.00 700.00
10 Labour cost for shuttering sqm 120.00 132.75 15930.00
Total cost of Labour Rs: 39579.60
labour component/unit qty 164.90
Add contractor's profit and overhead charges 13.615% 22.50
labour component/unit qty (including contractor's profit) 187.40
ABSTRACT:
A. Cost of Materials Rs: 607898.40
B. Hire charges of Machinery Rs: 52323.20
C. Cost of Labour Rs: 39579.60
Total Rs: 699801.20
Add for conveyor system @ 3.00% 20994.04
Add for electric sub-station/ Demand charges @ 2.5% 17495.03
Add for trestle bridge for tower crane track @ 4.0% 27992.05
Total Rs: 766282.32
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 104329.34
Lead Charges for 1 Km for FA 84.00 cum @ 31.5 Rs./Cum 2646
Lead Charges for 1 Km for CA 235.20 cum @ 30.4 Rs./Cum 7150.08
Total cost for 240.00 cum Rs: 880407.74
Rate per cum (A+B+C+D)/240 Rs: 3668.40
IRR-DAW-2-2A Providing and laying insitu vibrated M-20 ( 28 days cube compressive
New Item1-2010-11 strength not less than 20 N / sq mm ) grade cement concrete using 80 mm
down size approved, clean, hard, graded aggregates including cost of all
materials, machinery, labour, formwork, centering, scaffolding, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc.,complete for plain concrete works with initial lead upto 1 km and
all lifts. ( Cement content : 300 kg /cum with use of
0.4% of cement content super plasticiser , CA : 0.90 cum,
Blending Ratio of CA -- 40:30:20:10, FA : 0.40 cum )
59
Dam and Allied Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Batching plant Hour 8.00 620.70 4965.60
Fuel / Energy charges Hour 8.00 308.20 2465.60
2 Air compressor 7 cmm ( ele ) Hour 8.00 131.90 1055.20
Fuel / Energy charges Hour 8.00 252.20 2017.60
3 Tipper Hour 32.00 446.70 14294.40
Fuel / Energy charges Hour 32.00 299.90 9596.80
4 Tower crane 5 t Hour 16.00 867.10 13873.60
Fuel / Energy charges Hour 16.00 145.70 2331.20
5 Concrete bucket Hour 40.00 15.80 632.00
Fuel / Energy charges Hour 40.00 0.00 0.00
6 10 hp pump ( ele ) Hour 8.00 6.70 53.60
Fuel / Energy charges Hour 8.00 56.00 448.00
7 Needle vibrator 60 mm dia ( ele ) Hour 16.00 9.70 155.20
Fuel / Energy charges Hour 16.00 8.40 134.40
8 Sundries LS 10.00 30.00 300.00
Total hire charges of Machinery Rs: 52323.20
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Batching plant Hour 8.00 340.60 2724.80
2 Crew for Air compressor Hour 8.00 164.80 1318.40
3 Crew for Tipper ( 4 ) Hour 32.00 177.50 5680.00
4 Crew for Tower crane ( 2 ) Hour 16.00 189.30 3028.80
5 Crew for Pump Hour 8.00 83.30 666.40
6 Crew for Needle vibrator ( 2 ) Hour 16.00 158.20 2531.20
7 Mason Class-I Day 4.00 445.00 1780.00
8 Foreman Day 2.00 510.00 1020.00
9 mazdoor
for silo ( cement handling ) Day 2.00 350.00 700.00
for batching plant Day 2.00 350.00 700.00
for conveyor system Day 2.00 350.00 700.00
for laying & vibrating Day 6.00 350.00 2100.00
for cleaning / washing / curing Day 2.00 350.00 700.00
10 Labour cost for shuttering sqm 120.00 132.75 15930.00
Total cost of Labour Rs: 39579.60
labour component/unit qty 164.90
Add contractor's profit and overhead charges 13.615% 22.50
labour component/unit qty (including contractor's profit) 187.40
ABSTRACT:
A. Cost of Materials Rs: 657686.40
B. Hire charges of Machinery Rs: 52323.20
C. Cost of Labour Rs: 39579.60
Total Rs: 749589.20
Add for conveyor system @ 3.00% 22487.68
Add for electric sub-station/ Demand charges @ 2.5% 18739.73
Add for trestle bridge for tower crane track @ 4.0% 29983.57
Total Rs: 820800.18
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 111751.94
Lead Charges for 1 Km for FA 96.00 cum @ 31.5 Rs./Cum 3024
Lead Charges for 1 Km for CA 216.00 cum @ 30.4 Rs./Cum 6566.40
Total cost for 240.00 cum Rs: 942142.52
Rate per cum (A+B+C+D)/240 Rs: 3925.60
IRR-DAW-2-3 Providing and laying insitu vibrated M-10 ( 28 days cube compressive
strength not less than10 N / sq mm ) grade cement concrete using 80 mm
down size approved, clean, hard, graded aggregates including cost of all
materials, machinery, labour, formwork, centering, scaffolding, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc.,complete for plain concrete works with initial lead upto 1 km and
all lifts. ( Cement content : 220 kg /cum with use of super plasticiser,
CA: 0.98 cum, Blending Ratio of CA --40:30:20:10, FA: 0.37 cum)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Batching plant 2 x 1.5 cum Hour 8.00 620.70 4965.60
60
Dam and Allied Works - Item Unit Rates 2016-17
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Batching plant Hour 8.00 340.60 2724.80
2 Crew for Air compressor Hour 8.00 164.80 1318.40
3 Crew for Tipper ( 4 ) Hour 32.00 177.50 5680.00
4 Crew for Tower crane ( 2 ) Hour 16.00 189.30 3028.80
5 Crew for Pump Hour 8.00 83.30 666.40
6 Crew for Needle vibrator ( 2 ) Hour 16.00 158.20 2531.20
7 Mason Class-I Day 4.00 445.00 1780.00
8 Foreman Day 2.00 510.00 1020.00
9 mazdoor
for silo ( cement handling ) Day 2.00 350.00 700.00
for batching plant Day 2.00 350.00 700.00
for conveyor system Day 2.00 350.00 700.00
for laying & vibrating Day 6.00 350.00 2100.00
for cleaning / washing / curing Day 2.00 350.00 700.00
10 Labour cost for shuttering sqm 120.00 132.75 15930.00
Total cost of Labour Rs: 39579.60
labour component/unit qty 164.90
Add contractor's profit and overhead charges 13.615% 22.50
labour component/unit qty (including contractor's profit) 187.40
ABSTRACT:
A. Cost of Materials Rs: 568250.40
B. Hire charges of Machinery Rs: 52323.20
C. Cost of Labour Rs: 39579.60
Total Rs: 660153.20
Add for conveyor system @ 3.00% 19804.60
Add for electric sub-station/ Demand charges @ 2.5% 16503.83
Add for trestle bridge for tower crane track @ 4.0% 26406.13
Total Rs: 722867.76
D.Add for contractor's profit and overheads on (A+B+C+other 13.615% Rs. 98418.45
Lead Charges for 1 Km for FA 88.80 cum @ 31.5 Rs./Cum 2797.2
Lead Charges for 1 Km for CA 235.20 cum @ 30.4 Rs./Cum 7150.08
Total cost for 240.00 cum Rs: 831233.49
Rate per cum (A+B+C+D)/240 Rs: 3463.50
IRR-DAW-2-4 Providing and laying insitu vibrated M-20 ( 28 days cube compressive
strength not less than 20 N / sq mm ) grade cement concrete using 40 mm
down size approved, clean, hard, graded aggregates including cost of all
materials, machinery, labour, formwork, centering, scaffolding, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc.,complete for RCC works of gallery, sluice, spillway crest, spillway d / s
face, energy dissipating structures, training walls, piers, abutments and
such other locations with initial lead upto 1 km and all lifts.
( Cement content : 310 kg / cum with use of super plasticiser,
CA : 0.90 cum, blending ratio of CA--50:30:20, FA : 0.40 cum)
61
Dam and Allied Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Batching plant 2 x 1.5 cum Hour 8.00 620.70 4965.60
Fuel / Energy charges Hour 8.00 308.20 2465.60
2 Air compressor 7 cmm ( ele ) Hour 8.00 131.90 1055.20
Fuel / Energy charges Hour 8.00 252.20 2017.60
3 Tipper Hour 32.00 446.70 14294.40
Fuel / Energy charges Hour 32.00 299.90 9596.80
4 Tower crane 5 t Hour 16.00 867.10 13873.60
Fuel / Energy charges Hour 16.00 145.70 2331.20
5 Concrete bucket Hour 40.00 15.80 632.00
Fuel / Energy charges Hour 40.00 0.00 0.00
6 10 hp pump ( ele ) Hour 8.00 6.70 53.60
Fuel / Energy charges Hour 8.00 56.00 448.00
7 Needle vibrator 60 mm dia ( ele ) Hour 16.00 9.70 155.20
Fuel / Energy charges Hour 16.00 8.40 134.40
8 Sundries LS 10.00 30.00 300.00
Total hire charges of Machinery Rs: 52323.20
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Batching plant Hour 8.00 340.60 2724.80
2 Crew for Air compressor Hour 8.00 164.80 1318.40
3 Crew for Tipper ( 4 ) Hour 32.00 177.50 5680.00
4 Crew for Tower crane ( 2 ) Hour 16.00 189.30 3028.80
5 Crew for Pump Hour 8.00 83.30 666.40
6 Crew for Needle vibrator ( 2 ) Hour 16.00 158.20 2531.20
7 Mason Class-I Day 4.00 445.00 1780.00
8 Foreman Day 2.00 510.00 1020.00
9 mazdoor 0.00
for silo ( cement handling ) Day 2.00 350.00 700.00
for batching plant Day 2.00 350.00 700.00
for conveyor system Day 2.00 350.00 700.00
for laying & vibrating Day 6.00 350.00 2100.00
for cleaning / washing / curing Day 2.00 350.00 700.00
10 Labour cost for shuttering sqm 360.00 132.75 47790.00
11 Labour cost for scaffolding @ 15% 7168.50
Total cost of Labour Rs: 78608.10
labour component/unit qty 327.50
Add contractor's profit and overhead charges 13.615% 44.60
labour component/unit qty (including contractor's profit) 372.10
ABSTRACT:
A. Cost of Materials Rs: 807139.68
B. Hire charges of Machinery Rs: 52323.20
C. Cost of Labour Rs: 78608.10
Total Rs: 938070.98
Add for aggregate conveyor system @ 3.0% 28142.13
Add for electric sub-station / Demand charges @ 2.50% 23451.77
Add for trestle bridge for tower crane track @ 4.0% 37522.84
Total Rs: 1027187.72
D.Add for contractor's profit and overheads on (A+B+C+other 13.615% Rs. 139851.61
Lead Charges for 1 Km for FA 96.00 cum @ 31.5 Rs./Cum 3024
Lead Charges for 1 Km for CA 216.00 cum @ 30.4 Rs./Cum 6566.40
Total cost for 240.00 cum Rs: 1176629.73
Rate per cum (A+B+C+D)/240 Rs: 4902.60
IRR-DAW-2-4A Providing and laying insitu vibrated M-25 ( 28 days cube compressive
new Item2-2010-11 strength not less than 25 N / sq mm ) grade cement concrete using 40 mm
down size approved, clean, hard, graded aggregates including cost of all
materials, machinery, labour, formwork, centering, scaffolding, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc.,complete for RCC works of gallery, sluice, spillway crest, spillway d / s
face, energy dissipating structures, training walls, piers, abutments and
such other locations with initial lead upto 1 km and all lifts.
( Cement content : 360 kg / cum with use of super plasticiser,
CA : 0.90 cum, blending ratio of CA--50:30:20, FA : 0.40 cum)
62
Dam and Allied Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Batching plant 2 x 1.5 cum Hour 8.00 620.70 4965.60
Fuel / Energy charges Hour 8.00 308.20 2465.60
2 Air compressor 7 cmm ( ele ) Hour 8.00 131.90 1055.20
Fuel / Energy charges Hour 8.00 252.20 2017.60
3 Tipper Hour 32.00 446.70 14294.40
Fuel / Energy charges Hour 32.00 299.90 9596.80
4 Tower crane 5 t Hour 16.00 867.10 13873.60
Fuel / Energy charges Hour 16.00 145.70 2331.20
5 Concrete bucket Hour 40.00 15.80 632.00
Fuel / Energy charges Hour 40.00 0.00 0.00
6 10 hp pump ( ele ) Hour 8.00 6.70 53.60
Fuel / Energy charges Hour 8.00 56.00 448.00
7 Needle vibrator 60 mm dia ( ele ) Hour 16.00 9.70 155.20
Fuel / Energy charges Hour 16.00 8.40 134.40
8 Sundries LS 10.00 30.00 300.00
Total hire charges of Machinery Rs: 52323.20
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Batching plant Hour 8.00 340.60 2724.80
2 Crew for Air compressor Hour 8.00 164.80 1318.40
3 Crew for Tipper ( 4 ) Hour 32.00 177.50 5680.00
4 Crew for Tower crane ( 2 ) Hour 16.00 189.30 3028.80
5 Crew for Pump Hour 8.00 83.30 666.40
6 Crew for Needle vibrator ( 2 ) Hour 16.00 158.20 2531.20
7 Mason Class-I Day 4.00 445.00 1780.00
8 Foreman Day 2.00 510.00 1020.00
9 mazdoor 0.00
for silo ( cement handling ) Day 2.00 350.00 700.00
for batching plant Day 2.00 350.00 700.00
for conveyor system Day 2.00 350.00 700.00
for laying & vibrating Day 6.00 350.00 2100.00
for cleaning / washing / curing Day 2.00 350.00 700.00
10 Labour cost for shuttering sqm 360.00 132.75 47790.00
11 Labour cost for scaffolding @ 15% 7168.50
Total cost of Labour Rs: 78608.10
labour component/unit qty 327.50
Add contractor's profit and overhead charges 13.615% 44.60
labour component/unit qty (including contractor's profit) 372.10
ABSTRACT:
A. Cost of Materials Rs: 873979.68
B. Hire charges of Machinery Rs: 52323.20
C. Cost of Labour Rs: 78608.10
Total Rs: 1004910.98
Add for aggregate conveyor system @ 3.0% 30147.33
Add for electric sub-station / Demand charges @ 2.50% 25122.77
Add for trestle bridge for tower crane track @ 4.0% 40196.44
Total Rs: 1100377.52
D.Add for contractor's profit and overheads on (A+B+C+other 13.615% Rs. 149816.4
Lead Charges for 1 Km for FA 96.00 cum @ 31.5 Rs./Cum 3024
Lead Charges for 1 Km for CA 216.00 cum @ 30.4 Rs./Cum 6566.40
Total cost for 240.00 cum Rs: 1259784.32
Rate per cum (A+B+C+D)/240 Rs: 5249.10
IRR-DAW-2-4B Providing and laying insitu vibrated M-25 ( 28 days cube compressive
new Item3-2010-11 strength not less than 25 N / sq mm ) grade cement concrete using 20 mm
down size approved, clean, hard, graded aggregates including cost of all
materials, machinery, labour, formwork, centering, scaffolding, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc.,complete for RCC works of gallery, sluice, spillway crest, spillway d / s
face, energy dissipating structures, training walls, piers, abutments and
such other locations with initial lead upto 1 km and all lifts.
( Cement content : 380 kg / cum with use of super plasticiser,
CA : 0.90 cum, blending ratio of CA--65:35, FA : 0.40 cum)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Batching plant 2 x 1.5 cum Hour 8.00 620.70 4965.60
Fuel / Energy charges Hour 8.00 308.20 2465.60
2 Air compressor 7 cmm ( ele ) Hour 8.00 131.90 1055.20
Fuel / Energy charges Hour 8.00 252.20 2017.60
3 Tipper Hour 32.00 446.70 14294.40
Fuel / Energy charges Hour 32.00 299.90 9596.80
4 Tower crane 5 t Hour 16.00 867.10 13873.60
63
Dam and Allied Works - Item Unit Rates 2016-17
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Batching plant Hour 8.00 340.60 2724.80
2 Crew for Air compressor Hour 8.00 164.80 1318.40
3 Crew for Tipper ( 4 ) Hour 32.00 177.50 5680.00
4 Crew for Tower crane ( 2 ) Hour 16.00 189.30 3028.80
5 Crew for Pump Hour 8.00 83.30 666.40
6 Crew for Needle vibrator ( 2 ) Hour 16.00 158.20 2531.20
7 Mason Class-I Day 4.00 445.00 1780.00
8 Foreman Day 2.00 510.00 1020.00
9 mazdoor 0.00
for silo ( cement handling ) Day 2.00 350.00 700.00
for batching plant Day 2.00 350.00 700.00
for conveyor system Day 2.00 350.00 700.00
for laying & vibrating Day 6.00 350.00 2100.00
for cleaning / washing / curing Day 2.00 350.00 700.00
10 Labour cost for shuttering sqm 360.00 132.75 47790.00
11 Labour cost for scaffolding @ 15% 7168.50
Total cost of Labour Rs: 78608.10
labour component/unit qty 327.50
Add contractor's profit and overhead charges 13.615% 44.60
labour component/unit qty (including contractor's profit) 372.10
ABSTRACT:
A. Cost of Materials Rs: 895585.68
B. Hire charges of Machinery Rs: 52323.20
C. Cost of Labour Rs: 78608.10
Total Rs: 1026516.98
Add for aggregate conveyor system @ 3.0% 30795.51
Add for electric sub-station / Demand charges @ 2.50% 25662.92
Add for trestle bridge for tower crane track @ 4.0% 41060.68
Total Rs: 1124036.09
D.Add for contractor's profit and overheads on (A+B+C+other 13.615% Rs. 153037.51
Lead Charges for 1 Km for FA 96.00 cum @ 31.5 Rs./Cum 3024
Lead Charges for 1 Km for CA 216.00 cum @ 30.4 Rs./Cum 6566.40
Total cost for 240.00 cum Rs: 1286664.00
Rate per cum (A+B+C+D)/240 Rs: 5361.10
IRR-DAW-2-5 Providing and laying insitu vibrated M-15 ( 28 days cube compressive
strength not less than 15 N / sq mm ) grade cement concrete using 40 mm
down size approved, clean, hard, graded aggregates including cost of all
materials, machinery, labour, formwork, centering, scaffolding, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc.,complete for plain concrete works with initial lead upto 1 km and
all lifts. ( Cement content : 260 kg / cum with use of super plasticiser,
CA : 0.90 cum, Blending Ratio of CA -- 50:30:20, FA : 0.40 cum)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Concrete mixer 300 / 200 ltr ( ele ) Hour 8.0 51.70 413.60
Fuel / Energy charges Hour 8.0 28.00 224.00
2 10 hp pump ( ele ) Hour 1.0 6.70 6.70
Fuel / Energy charges Hour 1.0 56.00 56.00
3 Needle vibrator 40 mm dia ( ele ) Hour 8.0 8.00 64.00
Fuel / Energy charges Hour 8.0 5.60 44.80
Total hire charges of Machinery Rs: 809.10
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Concrete mixer Hour 8.00 219.70 1757.60
2 Crew for Pump Hour 1.00 83.30 83.30
3 Crew for Needle vibrator Hour 8.00 158.20 1265.60
4 Mason Class-I Day 1.00 445.00 445.00
5 mazdoor
for batching cement ( cement handling Day 2.00 350.00 700.00
for batching other materials Day 9.00 350.00 3150.00
for loading mortar pans Day 4.00 350.00 1400.00
64
Dam and Allied Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 38822.18
B. Hire charges of Machinery Rs: 809.10
C. Cost of Labour Rs: 16526.35
Total Rs: 56157.63
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 7645.86
Lead Charges for 1 Km for FA 5.60 cum @ 31.5 Rs./Cum 176.4
Lead Charges for 1 Km for CA 12.60 cum @ 30.4 Rs./Cum 383.04
Total cost for 14.00 cum Rs: 64362.93
Rate per cum (A+B+C+D)/14 Rs: 4597.40
IRR-DAW-2-6 Providing and laying insitu vibrated M-15 ( 28 days cube compressive
strength not less than 15 N / sq mm ) grade cement concrete using 40 mm
down size approved, clean, hard, graded aggregates with placing and
sinking plums of size 150 to 80 mm upto 15 percent for gravity type
structures including cost of all materials, machinery, labour, formwork,
scaffolding, cleaning, batching, mixing, placing in position, levelling,
vibrating, finishing, curing etc.,complete with initial lead upto 1 km and
all lifts. ( Cement content : 260 kg / cum of concrete with use of plums
and super plasticiser of 0.4% of cement quantity, CA : 0.77 cum,
Blending Ratio of CA : 50:30:20,FA : 0.34 cum,
plums of size 150 to 80 mm : 0.25 cum)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Concrete mixer 300 / 200 ltr ( ele ) Hour 8.00 51.70 413.60
Fuel / Energy charges Hour 8.00 28.00 224.00
2 10 hp pump ( ele ) Hour 1.00 6.70 6.70
Fuel / Energy charges Hour 1.00 56.00 56.00
3 Needle vibrator 60 mm dia ( ele ) Hour 8.00 9.70 77.60
Fuel / Energy charges Hour 8.00 8.40 67.20
Total hire charges of Machinery Rs: 845.10
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Concrete mixer Hour 8.00 219.70 1757.60
2 Crew for Pump Hour 1.00 83.30 83.30
3 Crew for Needle vibrator Hour 8.00 158.20 1265.60
4 Mason Class-I Day 1.00 445.00 445.00
5 work inspector Day 1.00 450.00 450.00
6 mazdoor
for batching cement ( cement handling Day 2.00 350.00 700.00
for batching other materials Day 9.00 350.00 3150.00
for loading mortar pans Day 4.00 350.00 1400.00
for loading plums Day 1.00 350.00 350.00
for laying concrete and plums Day 4.00 350.00 1400.00
for conveying concrete Day 13.99 350.00 4895.10
for conveying plums Day 3.00 350.00 1050.00
for cleaning / washing / curing Day 1.00 350.00 350.00
7 Labour for shuttering sqm 16.45 88.50 1455.83
8 Labour for scaffolding @ 15% 218.37
Total cost of Labour Rs: 18970.80
65
Dam and Allied Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 44527.75
B. Hire charges of Machinery Rs: 845.10
C. Cost of Labour Rs: 18970.80
Total Rs: 64343.65
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 8760.39
Lead Charges for 1 Km for FA 5.59 cum @ 31.5 Rs./Cum 176.1795
Lead Charges for 1 Km for CA and Plums 16.77 cum @ 30.4 Rs./Cum 509.88
Total cost for 16.45 cum Rs: 73790.10
Rate per cum (A+B+C+D)/16.45 Rs: 4485.70
IRR-DAW-2-7 Providing and laying insitu vibrated M-10 ( 28 days cube compressive
strength not less than 10 N / sq mm ) grade cement concrete using 40 mm
down size approved, clean, hard, graded aggregates including cost of all
materials, machinery, labour, formwork, centering, scaffolding, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc.,complete for plain concrete works with initial lead upto 1 km and all
lifts. ( Cement content 220 kg / cum with use of super plasticiser,
CA : 0.90 cum, Blending Ratio of CA : 50:30:20, FA : 0.40 cum)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Concrete mixer 300 / 200 ltr ( ele ) Hour 8.00 51.70 413.60
Fuel / Energy charges Hour 8.00 28.00 224.00
2 10 hp pump ( ele ) Hour 1.00 6.70 6.70
Fuel / Energy charges Hour 1.00 56.00 56.00
3 Needle vibrator 40 mm dia ( ele ) Hour 8.00 8.00 64.00
Fuel / Energy charges Hour 8.00 5.60 44.80
Total hire charges of Machinery Rs: 809.10
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Concrete mixer Hour 8.00 219.70 1757.60
2 Crew for Pump Hour 1.00 83.30 83.30
3 Crew for Needle vibrator Hour 8.00 158.20 1265.60
4 Mason Class-I Day 1.00 445.00 445.00
5 mazdoor
for batching cement ( cement handling Day 2.00 350.00 700.00
for batching other materials Day 9.00 350.00 3150.00
for loading mortar pans Day 4.00 350.00 1400.00
for laying Day 3.00 350.00 1050.00
for conveying concrete Day 16.53 350.00 5785.50
for cleaning / washing / curing Day 1.00 350.00 350.00
6 Labour cost of shuttering sqm 16.53 88.50 1462.91
7 Labour cost of scaffolding @ 15% 219.44
Total cost of Labour Rs: 17669.35
labour component/unit qty 1068.90
Add contractor's profit and overhead charges 13.615% 145.50
labour component/unit qty (including contractor's profit) 1214.40
ABSTRACT:
A. Cost of Materials Rs: 42155.02
B. Hire charges of Machinery Rs: 809.10
C. Cost of Labour Rs: 17669.35
Total Rs: 60633.47
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 8255.25
Lead Charges for 1 Km for FA 6.61 cum @ 31.5 Rs./Cum 208.278
Lead Charges for 1 Km for CA 14.88 cum @ 30.4 Rs./Cum 452.26
Total cost for 16.53 cum Rs: 69549.26
Rate per cum (A+B+C+D)/16.53 Rs: 4207.50
IRR-DAW-2-8 Providing and laying insitu vibrated M-15 ( 28 days cube compressive
strength not less than 15 N / sq mm ) grade cement concrete using 20 mm
down size approved, clean, hard, graded aggregates including cost of all
materials, machinery, labour, formwork, centering, scaffolding, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc.,complete for plain concrete works with initial lead upto 1 km and all
lifts. ( Cement content : 280 kg / cum with use of super plasticiser,
CA : 0.80 cum, Blending Ratio of CA -- 65:35, FA : 0.44 cum)
DATA: RATE ANALYSIS
UNIT:
A. MATERIALS: 15.87 cum
66
Dam and Allied Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Concrete mixer 300 / 200 ltr ( ele ) Hour 8.00 51.70 413.60
Fuel / Energy charges Hour 8.00 28.00 224.00
2 10 hp pump ( ele ) Hour 1.00 6.70 6.70
Fuel / Energy charges Hour 1.00 56.00 56.00
3 Needle vibrator 40 mm dia ( ele ) Hour 8.00 8.00 64.00
Fuel / Energy charges Hour 8.00 5.60 44.80
Total hire charges of Machinery Rs: 809.10
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Concrete mixer Hour 8.00 219.70 1757.60
2 Crew for Pump Hour 1.00 83.30 83.30
3 Crew for Needle vibrator Hour 8.00 158.20 1265.60
4 Mason Class-I Day 1.00 445.00 445.00
5 mazdoor
for batching cement ( cement handling Day 2.00 350.00 700.00
for batching other materials Day 9.00 350.00 3150.00
for loading mortar pans Day 4.00 350.00 1400.00
for laying Day 3.00 350.00 1050.00
for conveying concrete Day 15.87 350.00 5554.50
for cleaning / washing / curing Day 1.00 350.00 350.00
6 Labour cost of shuttering sqm 15.87 88.50 1404.50
67
Dam and Allied Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 43733.15
B. Hire charges of Machinery Rs: 809.10
C. Cost of Labour Rs: 17371.18
Total Rs: 61913.43
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 8429.51
Lead Charges for 1 Km for FA 6.98 cum @ 31.5 Rs./Cum 219.9582
Lead Charges for 1 Km for CA 12.70 cum @ 30.4 Rs./Cum 385.96
Total cost for 15.87 cum Rs: 70948.86
Rate per cum (A+B+C+D)/15.87 Rs: 4470.60
IRR-DAW-2-9 Providing and laying insitu vibrated M-20 ( 28 days cube compressive
strength not less than 20 N / sq mm ) grade cement concrete using 20 mm
down size approved, clean, hard, graded aggregates including cost of all
materials, machinery, labour, formwork, centering, scaffolding, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc.,complete for RCC works of spillway bridge, blockouts and such
other similar structures with conjested reinforcement with initial lead
upto 1 km and all lifts. ( Cement content : 330 kg / cum with use of
super plasticiser, CA : 0.80 cum, Blending Ratio of CA -- 65:35,
FA : 0.44 cum)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Concrete mixer 300 / 200 ltr ( ele Hour 8.00 51.70 413.60
Fuel / Energy charges Hour 8.00 28.00 224.00
2 10 hp pump ( ele ) Hour 1.00 6.70 6.70
Fuel / Energy charges Hour 1.00 56.00 56.00
3 Needle vibrator 40 mm dia ( ele ) Hour 8.00 8.00 64.00
Fuel / Energy charges Hour 8.00 5.60 44.80
Total hire charges of Machinery Rs: 809.10
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Concrete mixer Hour 8.00 219.70 1757.60
2 Crew for Pump Hour 1.00 83.30 83.30
3 Crew for Needle vibrator Hour 8.00 158.20 1265.60
4 Mason Class-I Day 1.00 445.00 445.00
5 mazdoor 0.00
for batching cement ( cement handling ) Day 2.00 350.00 700.00
for batching other materials Day 9.00 350.00 3150.00
for loading mortar pans Day 4.00 350.00 1400.00
for laying Day 3.00 350.00 1050.00
for conveying concrete Day 13.47 350.00 4714.50
for cleaning/ washing/ curing Day 1.00 350.00 350.00
6 Labour cost of shuttering sqm 33.68 88.50 2980.24
7 Labour cost of scaffolding @ 100% 2980.24
Total cost of Labour Rs: 20876.48
labour component/unit qty 1549.90
Add contractor's profit and overhead charges 13.615% 211.00
labour component/unit qty (including contractor's profit) 1760.90
ABSTRACT:
A. Cost of Materials Rs: 52111.40
B. Hire charges of Machinery Rs: 809.10
C. Cost of Labour Rs: 20876.48
Total Rs: 73796.98
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 10047.46
Lead Charges for 1 Km for FA 5.93 cum @ 31.5 Rs./Cum 186.6942
Lead Charges for 1 Km for CA 10.78 cum @ 30.4 Rs./Cum 327.59
Total cost for 13.47 cum Rs: 84358.72
Rate per cum (A+B+C+D)/13.47 Rs: 6262.70
IRR-DAW-2-10 Providing and forming porous concrete body drain of size 68.5 x 68.5 cm
with 23 cm diameter central hole using cement and 20 mm down
approved, clean, hard, graded coarse aggregates in 1 : 3.50 proportion by
volume including cost of all materials, machinery, labour, formwork, curing
etc., complete with initial lead upto 1 km and all lifts.
(M15 Cement content : 400kg/cum, CA : 1cum,
Blending Ratio of CA -- 65:35)
68
Dam and Allied Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Concrete mixer 300 / 200 ltr ( ele ) Hour 8.00 51.70 413.60
Fuel / Energy charges Hour 8.00 28.00 224.00
2 10 hp pump ( ele ) Hour 0.50 6.70 3.35
Fuel / Energy charges Hour 0.50 56.00 28.00
Total hire charges of Machinery Rs: 668.95
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Concrete mixer Hour 8.00 219.70 1757.60
2 Crew for Pump Hour 0.50 83.30 41.65
3 Mason Class-I Day 1.00 445.00 445.00
4 mazdoor
for batching cement ( cement handling Day 2.00 350.00 700.00
for batching other materials Day 6.00 350.00 2100.00
for loading mortar pans Day 2.00 350.00 700.00
for laying & packing concrete Day 2.00 350.00 700.00
for conveying concrete Day 8.56 350.00 2996.00
5 Fitter shuttering Day 3.00 400.00 1200.00
Total cost of Labour Rs: 10640.25
labour component/unit qty 532.00
Add contractor's profit and overhead charges 13.615% 72.40
labour component/unit qty (including contractor's profit) 604.40
ABSTRACT:
A. Cost of Materials Rs: 31953.63
B. Hire charges of Machinery Rs: 668.95
C. Cost of Labour Rs: 10640.25
Total Rs: 43262.83
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 5890.23
Lead Charges for 1 Km for CA 8.56 cum @ 30.4 Rs./Cum 260.22
Total cost for 20.00 Rm Rs: 49413.28
Rate per Rm (A+B+C+D)/20 Rs: 2470.70
IRR-DAW-2-11 Providing and laying insitu vibrated M-20 ( 28 days cube compressive
(a) strength not less than 20 N / sq mm ) grade cement concrete using 20 mm
down size approved, clean, hard, graded aggregates including cost of
all materials, machinery, labour, formwork, centering, scaffolding, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc.,complete for RCC solid parapet consisting of 35 cm x 20 cm kerb,
35 cm x 35 cm x 1 m pillars spaced approximately at 3.35 m c / c, 12.5 cm
thick wall 80 cm height with 12.5 cm thick and 35 cm wide coping slab for
wall and 12 .5 cm thick 40 cm x 40 cm coping for pillars with top edges of
kerb and coping chamferred / rounded as directed etc., complete
( excluding cost of providing and placing reinforcement steel and gate )
with initial lead upto 1 km and all lifts.
( Cement content 350 kg / cum with use of super plasticiser( 0.4% by wt.
of cement), CA : 0.80 cum, Blending Ratio of CA--65:35, FA : 0.44 cum)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
69
Dam and Allied Works - Item Unit Rates 2016-17
1 Concrete mixer 300 / 200 ltr ( ele ) Hour 8.00 51.70 413.60
Fuel / Energy charges Hour 8.00 28.00 224.00
2 Needle vibrator 40 mm ( ele ) Hour 8.00 8.00 64.00
Fuel / Energy charges Hour 8.00 5.60 44.80
3 10 hp pump ( ele ) Hour 0.50 6.70 3.35
Fuel / Energy charges Hour 0.50 56.00 28.00
Total hire charges of Machinery Rs: 777.75
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Concrete mixer Hour 8.00 219.70 1757.60
2 Crew for Pump Hour 0.50 83.30 41.65
3 Crew for Vibrator Hour 8.00 158.20 1265.60
4 Mason Class-I Day 2.00 445.00 890.00
5 work inspector Day 1.00 450.00 450.00
6 mazdoor
for batching cement ( cement handling ) Day 2.00 350.00 700.00
for batching other materials Day 9.00 350.00 3150.00
for loading mortar pans Day 4.00 350.00 1400.00
for laying & packing concrete Day 2.00 350.00 700.00
for conveying concrete Day 8.67 350.00 3034.50
for curing & miscellaneous Day 2.00 350.00 700.00
7 Labour for shuttering sqm 95.00 88.50 8407.50
8 Labour for scaffolding @ 15% 1261.13
Total cost of Labour Rs: 23757.98
labour component/unit qty 659.90
Add contractor's profit and overhead charges 13.615% 89.80
labour component/unit qty (including contractor's profit) 749.70
ABSTRACT:
A. Cost of Materials Rs: 48947.73
B. Hire charges of Machinery Rs: 777.75
C. Cost of Labour Rs: 23757.98
Total Rs: 73483.46
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 10004.77
Lead Charges for 1 Km for FA 3.81 cum @ 31.5 Rs./Cum 120.015
Lead Charges for 1 Km for CA 6.94 cum @ 30.4 Rs./Cum 210.98
Total cost for 36.00 Rm Rs: 83819.22
Rate per Rm (A+B+C+D)/36 Rs: 2328.30
IRR-DAW-2-12 Providing and laying insitu vibrated M-20 ( 28 days cube compressive
(b) strength not less than 20 N / sq mm ) grade cement concrete using 20 mm
down size approved, clean, hard, graded aggregates including cost of all
materials, machinery, labour, formwork, centering, scaffolding, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc.,complete for RCC ornamental parapet consisting of 35 cm x 20 cm
kerb, 35 cm x 35 cm x 1 m pillars spaced approximately at 3.5 m apart,
20 cm x 15 cm posts 80 cm height approximately 30 cm c / c with 12.5 cm
thick and 35 cm wide coping slab for posts and pillars with top edges of
kerb and coping chamferred or rounded as directed etc., complete
( excluding cost of providing and placing reinforcement steel and gate ) with
initial lead upto 1 km and all lifts.
( Cement content : 350 kg / cum with use of super plasticiser(0.4% by wt.
of cement, CA : 0.80 cum, Blending Ratio of CA--65:35, FA : 0.44 cum)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Concrete mixer 300 / 200 ltr ( ele Hour 8.00 51.70 413.60
Fuel / Energy charges Hour 8.00 28.00 224.00
2 Needle vibrator 40 mm ( ele ) Hour 8.00 8.00 64.00
Fuel / Energy charges Hour 8.00 5.60 44.80
70
Dam and Allied Works - Item Unit Rates 2016-17
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Concrete mixer Hour 8.00 219.70 1757.60
2 Crew for Pump Hour 0.50 83.30 41.65
3 Crew for Vibrator Hour 8.00 158.20 1265.60
4 Mason Class-I Day 2.00 445.00 890.00
5 work inspector Day 1.00 450.00 450.00
6 mazdoor
for batching cement ( cement handling ) Day 2.00 350.00 700.00
for batching other materials Day 9.00 350.00 3150.00
for loading mortar pans Day 4.00 350.00 1400.00
for laying & packing concrete Day 2.00 350.00 700.00
for conveying concrete Day 7.00 350.00 2450.00
for curing & miscellaneous Day 2.00 350.00 700.00
7 Labour for shuttering sqm 115.00 88.50 10177.50
8 Labour for scaffolding @ 15% 1526.63
Total cost of Labour Rs: 25208.98
labour component/unit qty 700.20
Add contractor's profit and overhead charges 13.615% 95.30
labour component/unit qty (including contractor's profit) 795.50
ABSTRACT:
A. Cost of Materials Rs: 49074.54
B. Hire charges of Machinery Rs: 777.75
C. Cost of Labour Rs: 25208.98
Total Rs: 75061.26
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 10219.59
Lead Charges for 1 Km for FA 3.08 cum @ 31.5 Rs./Cum 97.02
Lead Charges for 1 Km for CA 5.60 cum @ 30.4 Rs./Cum 170.24
Total cost for 36.00 Rm Rs: 85548.11
Rate per Rm (A+B+C+D)/36 Rs: 2376.30
71
Dam and Allied Works - Item Unit Rates 2016-17
IRR-DAW-2-13 Providing and laying insitu M- 25 ( 28 days cube compressive strength not
less than 25 N / sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates for wearing coat including cost
of all materials, machinery, labour, formwork, cleaning, batching, mixing,
placing in position in alternate panels, levelling, compacting, finishing,
curing, packing joints with asphalt mortar etc., complete
with initial lead upto 1 km and all lifts.
( Cement content : 380 kg / cum with use of super plasticiser(0.4% by
wt. of cement, CA : 0.80 cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Concrete mixer 300/200 ltr ( ele ) Hour 8.00 51.70 413.60
Fuel / Energy charges Hour 8.00 28.00 224.00
2 10 hp pump ( ele ) Hour 0.50 6.70 3.35
Fuel / Energy charges Hour 0.50 56.00 28.00
Total hire charges of Machinery Rs: 668.95
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Concrete mixer Hour 8.00 219.70 1757.60
2 Crew for Pump Hour 0.50 83.30 41.65
3 Mason Class-I Day 3.00 445.00 1335.00
4 work inspector Day 1.00 450.00 450.00
5 mazdoor
for batching cement ( cement handling ) Day 2.00 350.00 700.00
for batching materials Day 9.00 350.00 3150.00
for loading mortar pans Day 4.00 350.00 1400.00
for laying & compacting Day 5.00 350.00 1750.00
for conveying concrete Day 11.70 350.00 4095.00
for cleaning/ washing/ curing Day 1.00 350.00 350.00
6 Labour cost for shuttering sqm 5.85 88.50 517.73
Total cost of Labour Rs: 15546.98
labour component/unit qty 1328.80
Add contractor's profit and overhead charges 13.615% 180.90
labour component/unit qty (including contractor's profit) 1509.70
ABSTRACT:
A. Cost of Materials Rs: 37396.66
B. Hire charges of Machinery Rs: 668.95
C. Cost of Labour Rs: 15546.98
Total Rs: 53612.58
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 7299.35
Lead Charges for 1 Km for FA 5.27 cum @ 31.5 Rs./Cum 165.8475
Lead Charges for 1 Km for CA 9.36 cum @ 30.4 Rs./Cum 284.54
Total cost for 11.70 cum Rs: 61362.32
Rate per cum (A+B+C+D)/11.70 Rs: 5244.60
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Ice maker unit consisting of: Hour 24.00 170.20 4084.80
Compressor 125 hp - 1 No
Condenser with 30 hp motor - 1 No.
Ice makers 10 t / day each - 3 Nos.
Pump 2 hp for ice cutting - 3 Nos.
Pump 2 hp for pumping water-3 Nos.
Screw conveyor with 15 hp motor -1
Ice elevator with 5 hp motor - 1 No.
Fuel / Energy charges for system Hour 24.00 798.60 19166.40
Total hire charges of Machinery Rs: 23251.20
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
72
Dam and Allied Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 90.00
B. Hire charges of Machinery Rs: 23251.20
C. Cost of Labour Rs: 6313.20
Total Rs: 29654.40
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 4037.45
Total cost for 500.00 cum Rs: 33691.85
Rate per cum (A+B+C+D)/500 Rs: 67.40
IRR-DAW-2-15 Conveying and fixing elastomeric bearing for spillway bridge including
cleaning and preparing surface, mixing and applying adhesive, fixing bearing
in correct position etc., including cost of all materials except bearings,
machinery, labour etc., complete with all leads and lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Nil 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Marker / Erector Day 1.00 550.00 550.00
2 work inspector Day 1.00 450.00 450.00
3 mazdoor Day 2.00 350.00 700.00
Total cost of Labour Rs: 1700.00
labour component/unit qty 283.30
Add contractor's profit and overhead charges 13.615% 38.60
labour component/unit qty (including contractor's profit) 321.90
ABSTRACT:
A. Cost of Materials Rs: 276.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 1700.00
Total Rs: 1976.00
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 269.03
Total cost for 6.00 Nos. Rs: 2245.03
Rate per Each (A+B+C+D)/6 Rs: 374.20
IRR-DAW-2-16 Providing and constructing 150 mm dia hume pipe weep holes for
concrete / masonry walls including providing 20 x 20 x 20 cm size porous
concrete block made of cement and 20 mm down coarse aggregate in
1 : 4 proportion including 10 cm thick sand backing at the junction of wall
and soil back fill, cost of all materials, machinery, labour etc., complete
with lead upto 1 km and all lifts.
73
Dam and Allied Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Nil 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Mason Class-II Day 0.25 400.00 100.00
2 mazdoor Day 0.25 350.00 87.50
Total cost of Labour Rs: 187.50
labour component/unit qty 62.50
Add contractor's profit and overhead charges 13.615% 8.50
labour component/unit qty (including contractor's profit) 71.00
ABSTRACT:
A. Cost of Materials Rs: 825.25
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 187.50
Total Rs: 1012.75
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 137.89
Lead Charges for 1 Km for FA 0.02 cum @ 31.5 Rs./Cum 0.63
Lead Charges for 1 Km for CA 0.01 cum @ 30.4 Rs./Cum 0.24
Total cost for 3.00 Rm Rs: 1151.51
Rate per Rm (A+B+C+D)/3 Rs: 383.80
IRR-DAW-2-17 Providing and forming expansion joint for spillway bridge consisting of
75 x 75 x 6 mm angles 2 numbers provided with 25 cm long 12 mm dia.
anchors fixed to both flanges at 15 cm c /c and 140 x 6 mm plate welded
on top of one of the angle including cost of all materials, machinery, labour,
providing and fixing 38 mm thick joint filler board matching the thickness of
wearing coat, painting etc., complete with lead upto 1 km and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Welding set Hour 8.00 16.00 128.00
Fuel / Energy charges Hour 8.00 67.20 537.60
2 Sundries (cutting torch/ welding guns etc) LS 2.00 30.00 60.00
Total hire charges of Machinery Rs: 725.60
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Marker / Fabricator / Erector Day 1.50 550.00 825.00
2 Gas cutter / Welder Day 1.50 445.00 667.50
3 mazdoor Day 2.00 350.00 700.00
Total cost of Labour Rs: 2192.50
labour component/unit qty 292.30
Add contractor's profit and overhead charges 13.615% 39.80
labour component/unit qty (including contractor's profit) 332.10
ABSTRACT:
A. Cost of Materials Rs: 8331.53
B. Hire charges of Machinery Rs: 725.60
C. Cost of Labour Rs: 2192.50
Total Rs: 11249.63
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 1531.64
Lead Charges for 1Km for Steel (including Loading
and Unloading Charges) 0.18 tonne @ 168.6 Rs./Tonne 30.78636
Total cost for 7.50 Rm Rs: 12812.06
Rate per Rm (A+B+C+D)/7.50 Rs: 1708.30
74
Dam and Allied Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Concrete mixer 300 / 200 ltr ( ele ) Hour 8.00 51.70 413.60
Fuel / Energy charges Hour 8.00 28.00 224.00
2 10 hp pump ( ele ) Hour 1.00 6.70 6.70
Fuel / Energy charges Hour 1.00 56.00 56.00
Total hire charges of Machinery Rs: 700.30
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Concrete mixer Hour 8.00 219.70 1757.60
2 Crew for Pump Hour 1.00 83.30 83.30
3 work inspector Day 1.00 450.00 450.00
4 Mason Class-I Day 2.50 445.00 1112.50
5 Mason Class-II Day 4.00 400.00 1600.00
6 Chavali Day 16.00 400.00 6400.00
7 mazdoor
for batching cement ( cement handling ) Day 2.00 350.00 700.00
for batching sand Day 6.00 350.00 2100.00
for loading mortar pans Day 4.00 350.00 1400.00
for laying & packing mortar Day 10.00 350.00 3500.00
for loading chips Day 1.00 350.00 350.00
for washing rubble / finishing / curing Day 4.00 350.00 1400.00
for conveying mortar / chips Day 12.00 350.00 4200.00
Total cost of Labour Rs: 25053.40
labour component/unit qty 1002.10
Add contractor's profit and overhead charges 13.615% 136.40
labour component/unit qty (including contractor's profit) 1138.50
ABSTRACT:
A. Cost of Materials Rs: 35132.50
B. Hire charges of Machinery Rs: 700.30
C. Cost of Labour Rs: 25053.40
Total Rs: 60886.20
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 8289.66
Lead Charges for 1 Km for FA 10.00 cum @ 31.5 Rs./Cum 315
Lead Charges for 1 Km for Stones/Stone Chips 25.00 cum @ 30.4 Rs./Cum 760.00
Total cost for 25.00 cum Rs: 70250.86
Rate per cum (A+B+C+D)/25 Rs: 2810.00
IRR-DAW-3-2 Providing and constructing un-coursed rubble stone masonry using approved stones in
cement mortar 1 : 4 proportion including cost of all materials, machinery, labour, scaffolding,
cleaning, packing mortar, wedging stone chips, curing etc., complete with initial lead upto
1 km and all lifts.
( Cement content : 143 kg/cum of masonry, rubble stones : 0.85 cum,
stone chips : 0.15 cum/cum, FA : 0.4 cum)
For 1 cum masonry :-
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Concrete mixer 300 / 200 ltr(ele) Hour 8.00 51.70 413.60
Fuel / Energy charges Hour 8.00 28.00 224.00
2 10 hp pump Hour 1.00 6.70 6.70
Fuel / Energy charges Hour 1.00 56.00 56.00
Total hire charges of Machinery Rs: 700.30
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Concrete mixer Hour 8.00 219.70 1757.60
2 Crew for Pump Hour 1.00 83.30 83.30
3 work inspector Day 1.00 450.00 450.00
4 Mason Class-I Day 2.50 445.00 1112.50
5 Mason Class-II Day 4.00 400.00 1600.00
6 Chavali Day 16.00 400.00 6400.00
7 mazdoor
for batching cement ( cement handling ) Day 2.00 350.00 700.00
75
Dam and Allied Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 28846.25
B. Hire charges of Machinery Rs: 700.30
C. Cost of Labour Rs: 25053.40
Total Rs: 54599.95
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 7433.78
Lead Charges for 1 Km for FA 10.00 cum @ 31.5 Rs./Cum 315
Lead Charges for 1 Km for Stones/Stone Chips 25.00 cum @ 30.4 Rs./Cum 760.00
Total cost for 25.00 cum Rs: 63108.73
Rate per cum (A+B+C+D)/25 Rs: 2524.30
IRR-DAW-3-3 Providing and constructing coursed rubble face stone masonry using
approved rubble stones in cement mortar 1 : 3 proportion including cost
of all materials, machinery, labour, scaffolding, ramps, cleaning, packing
mortar, wedging stone chips, curing etc., with initial lead upto 1 km
and all lifts.
( Thickness of the CR face assumed: 0.75 m,Cement content : 178 kg/cum of masonry,
rubble stones : 0.35 cum, stone chips : 0.15 cum/cum, FA : 0.375 cum,
CR stones 30 x 30 x 45 cm : 9.75 No, CR stones 30 x 30 x 60 cm : 3.25 No)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Concrete mixer 300 / 200 ltr ( ele ) Hour 8.00 51.70 413.60
Fuel / Energy charges Hour 8.00 28.00 224.00
2 10 hp pump ( ele ) Hour 1.00 6.70 6.70
Fuel / Energy charges Hour 1.00 56.00 56.00
Total hire charges of Machinery Rs: 700.30
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Concrete mixer Hour 8.00 219.70 1757.60
2 Crew for Pump Hour 1.00 83.30 83.30
3 work inspector Day 1.00 450.00 450.00
4 Stone chiseller Cl -II Day 7.00 400.00 2800.00
5 Mason Class-I Day 2.50 445.00 1112.50
6 Mason Class-II Day 4.00 400.00 1600.00
7 Chavali Day 16.00 400.00 6400.00
8 mazdoor
for batching cement ( cement handling ) Day 2.00 350.00 700.00
for batching sand Day 6.00 350.00 2100.00
for loading mortar pans Day 4.00 350.00 1400.00
for laying & packing mortar Day 10.00 350.00 3500.00
for loading chips Day 1.00 350.00 350.00
for washing rubble / finishing / curing Day 4.00 350.00 1400.00
for conveying mortar / chips Day 12.00 350.00 4200.00
Total cost of Labour Rs: 27853.40
labour component/unit qty 1114.10
Add contractor's profit and overhead charges 13.615% 151.70
labour component/unit qty (including contractor's profit) 1265.80
ABSTRACT:
A. Cost of Materials Rs: 37193.38
B. Hire charges of Machinery Rs: 700.30
C. Cost of Labour Rs: 27853.40
Total Rs: 65747.08
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 8951.46
Lead Charges for 1 Km for FA 9.38 cum @ 31.5 Rs./Cum 295.3125
Lead Charges for 1 Km for Stones/Stone Chips 26.81 cum @ 30.4 Rs./Cum 815.02
Total cost for 25.00 cum Rs: 75808.87
Rate per cum (A+B+C+D)/25 Rs: 3032.40
IRR-DAW-3-4 Providing and constructing coursed rubble face stone masonry using
approved rubble stones in cement mortar 1 : 4 proportion including cost of
all materials, machinery, labour, scaffolding, ramps, cleaning, packing
mortar, wedging stone chips, curing etc., with initial lead upto 1 km and
all lifts.
( Cement content : 134 kg/cum of masonry, rubble stones : 0.35 cum,
stone chips : 0.15 cum/cum, FA : 0.375 cum,
CR stones 30 x 30 x 45 cm : 9.75 No, CR stones 30 x 30 x 60 cm : 3.25 No)
76
Dam and Allied Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Concrete mixer 300 / 200 ltr ( ele ) Hour 8.00 51.70 413.60
Fuel / Energy charges Hour 8.00 28.00 224.00
2 10 hp pump ( ele ) Hour 1.00 6.70 6.70
Fuel / Energy charges Hour 1.00 56.00 56.00
Total hire charges of Machinery Rs: 700.30
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Concrete mixer Hour 8.00 219.70 1757.60
2 Crew for Pump Hour 1.00 83.30 83.30
3 work inspector Day 1.00 450.00 450.00
4 Stone chiseller Cl -II Day 7.00 400.00 2800.00
5 Mason Class-I Day 2.50 445.00 1112.50
6 Mason Class-II Day 4.00 400.00 1600.00
7 Chavali Day 16.00 400.00 6400.00
8 mazdoor
for batching cement ( cement handling ) Day 2.00 350.00 700.00
for batching sand Day 6.00 350.00 2100.00
for loading mortar pans Day 4.00 350.00 1400.00
for laying & packing mortar Day 10.00 350.00 3500.00
for loading chips Day 1.00 350.00 350.00
for washing rubble / finishing / curing Day 4.00 350.00 1400.00
for conveying mortar / chips Day 12.00 350.00 4200.00
Total cost of Labour Rs: 27853.40
labour component/unit qty 1114.10
Add contractor's profit and overhead charges 13.615% 151.70
labour component/unit qty (including contractor's profit) 1265.80
77
Dam and Allied Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 31308.38
B. Hire charges of Machinery Rs: 700.30
C. Cost of Labour Rs: 27853.40
Total Rs: 59862.08
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 8150.22
Lead Charges for 1 Km for FA 9.38 cum @ 31.5 Rs./Cum 295.3125
Lead Charges for 1 Km for Stones/Stone Chips 26.81 cum @ 30.4 Rs./Cum 815.02
Total cost for 25.00 cum Rs: 69122.63
Rate per cum (A+B+C+D)/25 Rs: 2764.90
IRR-DAW-3-5 Providing and constructing chisel drafted and hammer dressed face
stone masonry with approved stones in cement mortar 1 : 3 proportion
including cost of all materials, machinery, labour, scaffolding, ramps,
cleaning, packing mortar, wedging stone chips, curing etc.,complete with
initial lead upto 1 km and all lifts.
( Cement content : 167 kg/cum of masonry, rubble stones : 0.35 cum,
stone chips : 0.15 cum/cum, FA : 0.35 cum,
Dressed stones 30 x 30 x 45 cm : 10 No, Dressed stones 30 x 30 x 60 cm : 3.40 No)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Concrete mixer 300 / 200 ltr ( ele ) Hour 8.00 51.70 413.60
Fuel / Energy charges Hour 8.00 28.00 224.00
2 10 hp pump ( ele ) Hour 1.00 6.70 6.70
Fuel / Energy charges Hour 1.00 56.00 56.00
Total hire charges of Machinery Rs: 700.30
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Concrete mixer Hour 8.00 219.70 1757.60
2 Crew for Pump Hour 1.00 83.30 83.30
3 work inspector Day 1.00 450.00 450.00
4 Stone chiseller Cl -I Day 14.00 445.00 6230.00
5 Stone chiseller Cl -II Day 7.00 400.00 2800.00
6 Mason Class-I Day 2.50 445.00 1112.50
7 Mason Class-II Day 4.00 400.00 1600.00
8 Chavali Day 16.00 400.00 6400.00
9 mazdoor
for batching cement ( cement handling ) Day 2.00 350.00 700.00
for batching sand Day 6.00 350.00 2100.00
for loading mortar pans Day 4.00 350.00 1400.00
for laying & packing mortar Day 10.00 350.00 3500.00
for loading chips Day 1.00 350.00 350.00
for washing rubble / finishing / curing Day 4.00 350.00 1400.00
for conveying mortar / chips Day 12.00 350.00 4200.00
Total cost of Labour Rs: 34083.40
labour component/unit qty 1363.30
Add contractor's profit and overhead charges 13.615% 185.60
labour component/unit qty (including contractor's profit) 1548.90
ABSTRACT:
A. Cost of Materials Rs: 35835.00
B. Hire charges of Machinery Rs: 700.30
C. Cost of Labour Rs: 34083.40
Total Rs: 70618.70
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 9614.74
Lead Charges for 1 Km for FA 8.75 cum @ 31.5 Rs./Cum 275.625
Lead Charges for 1 Km for Stones/Stone Chips 27.22 cum @ 30.4 Rs./Cum 827.34
Total cost for 25.00 cum Rs: 81336.40
Rate per cum (A+B+C+D)/25 Rs: 3253.50
IRR-DAW-3-6 Providing and constructing chisel drafted and hammer dressed face
stone masonry with approved stones in cement mortar 1 : 4 proportion
including cost of all materials, machinery, labour, scaffolding, ramps,
cleaning, packing mortar, wedging stone chips, curing etc.,complete with
initial lead upto 1 km and all lifts.
( Cement content : 125 kg/cum of masonry, rubble stones : 0.35 cum,
stone chips : 0.15 cum/cum, FA : 0.35 cum,
Dressed stones 30 x 30 x 45 cm : 10 No, Dressed stones 30 x 30 x 60 cm : 3.40 No)
78
Dam and Allied Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Concrete mixer 300 / 200 ltr ( ele ) Hour 8.00 51.70 413.60
Fuel / Energy charges Hour 8.00 28.00 224.00
2 10 hp pump ( ele ) Hour 1.00 6.70 6.70
Fuel / Energy charges Hour 1.00 56.00 56.00
Total hire charges of Machinery Rs: 700.30
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Concrete mixer Hour 8.00 219.70 1757.60
2 Crew for Pump Hour 1.00 83.30 83.30
3 work inspector Day 1.00 450.00 450.00
4 Stone chiseller Cl -I Day 14.00 445.00 6230.00
5 Stone chiseller Cl -II Day 7.00 400.00 2800.00
6 Mason Class-I Day 2.50 445.00 1112.50
7 Mason Class-II Day 4.00 400.00 1600.00
8 Chavali Day 16.00 400.00 6400.00
9 mazdoor
for batching cement ( cement handling Day 2.00 350.00 700.00
for batching sand Day 6.00 350.00 2100.00
for loading mortar pans Day 4.00 350.00 1400.00
for laying & packing mortar Day 10.00 350.00 3500.00
for loading chips Day 1.00 350.00 350.00
for washing rubble / finishing / curing Day 4.00 350.00 1400.00
for conveying mortar / chips Day 12.00 350.00 4200.00
Total cost of Labour Rs: 34083.40
labour component/unit qty 1363.30
Add contractor's profit and overhead charges 13.615% 185.60
labour component/unit qty (including contractor's profit) 1548.90
ABSTRACT:
A. Cost of Materials Rs: 30217.50
B. Hire charges of Machinery Rs: 700.30
C. Cost of Labour Rs: 34083.40
Total Rs: 65001.20
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 8849.91
Lead Charges for 1 Km for FA 8.75 cum @ 31.5 Rs./Cum 275.625
Lead Charges for 1 Km for Stones/Stone Chips 27.22 cum @ 30.4 Rs./Cum 827.34
Total cost for 25.00 cum Rs: 74954.07
Rate per cum (A+B+C+D)/25 Rs: 2998.20
IRR-DAW-3-7 Providing cement mortar pointing to coursed rubble face stone masonry
50 mm deep in CM 1 : 2 proportion by volume including raking and cleaning
joints, pressing mortar into joints, cost of all materials, labour, scaffolding,
finishing, curing etc., complete with initial lead upto 1 km and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 NIL 0.00 0.00 0.00
(Manual mixing ) 0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
79
Dam and Allied Works - Item Unit Rates 2016-17
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Mason Class-I Day 10.00 445.00 4450.00
2 mazdoor Day 10.00 350.00 3500.00
Total cost of Labour Rs: 7950.00
labour component/unit qty 79.50
Add contractor's profit and overhead charges 13.615% 10.80
labour component/unit qty (including contractor's profit) 90.30
ABSTRACT:
A. Cost of Materials Rs: 2557.91
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 7950.00
Total Rs: 10507.91
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 1430.65
Lead Charges for 1 Km for FA 0.74 cum @ 31.5 Rs./Cum 23.1525
Total cost for 100.00 sqm Rs: 11961.71
Rate per sqm (A+B+C+D)/100 Rs: 119.60
IRR-DAW-3-8 Providing cement mortar pointing to coursed rubble face stone masonry
50 mm deep in CM 1 : 3 proportion by volume including raking and cleaning
joints, pressing mortar into joints, cost of all materials, labour, scaffolding,
finishing, curing etc., complete with initial lead upto 1 km and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 NIL 0.00 0.00 0.00
Manual mixing ) 0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Mason Class-I Day 10.00 445.00 4450.00
2 mazdoor Day 10.00 350.00 3500.00
Total cost of Labour Rs: 7950.00
labour component/unit qty 79.50
Add contractor's profit and overhead charges 13.615% 10.80
labour component/unit qty (including contractor's profit) 90.30
ABSTRACT:
A. Cost of Materials Rs: 1842.91
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 7950.00
Total Rs: 9792.91
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 1333.3
Lead Charges for 1 Km for FA 0.74 cum @ 31.5 Rs./Cum 23.1525
Total cost for 100.00 sqm Rs: 11149.36
Rate per sqm (A+B+C+D)/100 Rs: 111.50
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Guniting equipment Hour 8.00 110.10 880.80
Fuel / Energy charges Hour 8.00 0.00 0.00
2 Air compressor 8.5 cmm ( ele ) Hour 8.00 170.80 1366.40
Fuel / Energy charges Hour 8.00 315.20 2521.60
3 Pump 10 hp ( ele ) Hour 1.00 6.70 6.70
Fuel / Energy charges Hour 1.00 56.00 56.00
4 Sundries LS 2.00 30.00 60.00
Total hire charges of Machinery Rs: 4891.50
80
Dam and Allied Works - Item Unit Rates 2016-17
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Guniting equipment Hour 8.00 219.70 1757.60
2 Crew for Air compressor Hour 8.00 164.80 1318.40
3 Crew for pump Hour 1.00 83.30 83.30
4 Mason Cl II Day 1.00 400.00 400.00
5 mazdoor
for cement handling Day 2.00 350.00 700.00
for sand Day 2.00 350.00 700.00
mazdoor for other works Day 2.00 350.00 700.00
Total cost of Labour Rs: 5659.30
labour component/unit qty 157.20
Add contractor's profit and overhead charges 13.615% 21.40
labour component/unit qty (including contractor's profit) 178.60
ABSTRACT:
A. Cost of Materials Rs: 3623.32
B. Hire charges of Machinery Rs: 4891.50
C. Cost of Labour Rs: 5659.30
Total Rs: 14174.12
Add for scaffolding 3% 354.35
Total Rs: 14528.47
D.Add for contractor's profit and overheads on (A+B+C+other 13.615% Rs. 1978.05
Lead Charges for 1 Km for FA 1.09 cum @ 31.5 Rs./Cum 34.335
Total cost for 36.00 sqm Rs: 16540.85
Rate per sqm (A+B+C+D)/36 Rs: 459.50
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Steam circulation arrangement LS 8.00 17.00 136.00
Fuel charges ( gas for heating ) LS 10.00 17.00 170.00
Total hire charges of Machinery Rs: 306.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Welder Day 1.00 445.00 445.00
2 Tinsmith Day 1.00 445.00 445.00
3 Bar bender Day 0.50 555.00 277.50
4 Pipe fitter Day 0.50 510.00 255.00
5 Mason Class-I Day 0.50 445.00 222.50
6 mazdoor Day 1.00 350.00 350.00
Total cost of Labour Rs: 1995.00
labour component/unit qty 166.30
Add contractor's profit and overhead charges 13.615% 22.60
labour component/unit qty (including contractor's profit) 188.90
81
Dam and Allied Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 162442.00
B. Hire charges of Machinery Rs: 306.00
C. Cost of Labour Rs: 1995.00
Total Rs: 164743.00
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 22429.76
Total cost for 12.00 Rm Rs: 187172.76
Rate per Rm (A+B+C+D)/12 Rs: 15597.70
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Steam circulation arrangement LS 8.00 17.00 136.00
Fuel charges ( gas for heating ) LS 10.00 17.00 170.00
Total hire charges of Machinery Rs: 306.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Welder Day 0.50 445.00 222.50
2 Bar bender Day 0.50 555.00 277.50
3 Pipe fitter Day 0.50 510.00 255.00
4 Mason Class-I Day 0.50 445.00 222.50
5 mazdoor Day 1.00 350.00 350.00
Total cost of Labour Rs: 1327.50
labour component/unit qty 110.60
Add contractor's profit and overhead charges 13.615% 15.10
labour component/unit qty (including contractor's profit) 125.70
ABSTRACT:
A. Cost of Materials Rs: 24277.00
B. Hire charges of Machinery Rs: 306.00
C. Cost of Labour Rs: 1327.50
Total Rs: 25910.50
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 3527.71
Total cost for 12.00 Rm. Rs: 29438.21
Rate per Rm. (A+B+C+D)/12 Rs: 2453.20
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Sundries such as soldering gun etc., LS 3.00 30.00 90.00
Fuel charges ( gas ) LS 5.00 17.00 85.00
Total hire charges of Machinery Rs: 175.00
82
Dam and Allied Works - Item Unit Rates 2016-17
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Welder Day 0.5 445.00 222.50
2 Tinsmith Day 0.5 445.00 222.50
3 Bar bender Day 0.5 555.00 277.50
4 Mason Class-I Day 0.5 445.00 222.50
5 mazdoor Day 0.5 350.00 175.00
Total cost of Labour Rs: 1120.00
labour component/unit qty 128.70
Add contractor's profit and overhead charges 13.615% 17.50
labour component/unit qty (including contractor's profit) 146.20
ABSTRACT:
A. Cost of Materials Rs: 54195.00
B. Hire charges of Machinery Rs: 175.00
C. Cost of Labour Rs: 1120.00
Total Rs: 55490.00
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 7554.96
Total cost for 8.70 Rm Rs: 63044.96
Rate per Rm (A+B+C+D)/8.70 Rs: 7246.50
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Sundries such as heater etc., LS 0.50 30.00 15.00
Fuel charges for heating LS 0.50 17.00 8.50
Total hire charges of Machinery 23.50
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Welder Day 0.50 445.00 222.50
2 Bar bender Day 0.50 555.00 277.50
3 Mason Class-I Day 0.50 445.00 222.50
4 mazdoor Day 0.50 350.00 175.00
Total cost of Labour Rs: 897.50
labour component/unit qty 103.20
Add contractor's profit and overhead charges 13.615% 14.10
labour component/unit qty (including contractor's profit) 117.30
ABSTRACT:
A. Cost of Materials Rs: 779.00
B. Hire charges of Machinery Rs: 23.50
C. Cost of Labour Rs: 897.50
Total Rs: 1700.00
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 231.46
Total cost for 8.70 Rm Rs: 1931.46
Rate per Rm (A+B+C+D)/8.70 Rs: 222.00
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Angle dozer 90 hp Hour 5.50 1715.50 9435.25
Fuel / Energy charges Hour 5.50 610.50 3357.75
2 Shovel 0.85 cum capacity Hour 8.00 1706.60 13652.80
Fuel / Energy charges Hour 8.00 872.70 6981.60
3 Tippers 5.00 cum capacity 5 Nos. Hour 40.00 446.70 17868.00
Fuel / Energy charges Hour 40.00 299.90 11996.00
83
Dam and Allied Works - Item Unit Rates 2016-17
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Dozer Hour 5.50 236.60 1301.30
2 Crew for Shovel Hour 8.00 236.60 1892.80
3 Crew for Tipper Hour 40.00 177.50 7100.00
4 Crew for Pump Hour 4.00 83.30 333.20
5 Crew for Water tanker Hour 8.00 177.50 1420.00
6 Crew for Roller Hour 6.50 263.60 1713.40
7 work inspector Day 2.00 450.00 900.00
8 mazdoor Day 4.00 350.00 1400.00
Total cost of Labour Rs: 16060.70
labour component/unit qty 19.50
Add contractor's profit and overhead charges 13.615% 2.70
labour component/unit qty (including contractor's profit) 22.20
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 84523.00
C. Cost of Labour Rs: 16060.70
Total Rs: 100583.70
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 13694.47
Total cost for 825.00 cum Rs: 114278.17
Rate per cum (A+B+C+D)/825 Rs: 138.50
IRR-DAW-5-2 Providing cut-off trench filling using selected impervious soil from
approved borrow areas in layers of 25 to 30 cm before compaction
including cost of all materials, machinery, labour, all operations such as
excavation, sorting out, transportation, spreading soil to specified thickness,
breaking clods, sectioning, watering, compacting to density control of not
less than 95 percent using Sheep foot roller / Vibratory roller/ 8 to 10 tonne power roller as stipulated etc.,
complete with initial lead upto 1 km and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Angle dozer 90 hp Hour 5.50 1715.50 9435.25
Fuel / Energy charges Hour 5.50 610.50 3357.75
2 Shovel 0.85 cum capacity Hour 8.00 1706.60 13652.80
Fuel / Energy charges Hour 8.00 872.70 6981.60
3 Tippers 5.00 cum capacity 6 Nos. Hour 48.00 446.70 21441.60
Fuel / Energy charges Hour 48.00 299.90 14395.20
4 Pump 5 hp ( ele ) Hour 4.00 3.00 12.00
Fuel / Energy charges Hour 4.00 28.00 112.00
5 Water tanker 8000 ltr Hour 8.00 402.50 3220.00
Fuel / Energy charges Hour 8.00 299.90 2399.20
6 Vibratory Roller 8 tonne Hour 6.50 1342.20 8724.30
Fuel / Energy charges Hour 6.50 1031.40 6704.10
7 Sundries LS 2.00 30.00 60.00
Total hire charges of Machinery Rs: 90495.80
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Dozer Hour 5.50 236.60 1301.30
2 Crew for Shovel Hour 8.00 236.60 1892.80
3 Crew for Tipper Hour 48.00 177.50 8520.00
4 Crew for Pump Hour 4.00 83.30 333.20
5 Crew for Water tanker Hour 8.00 177.50 1420.00
6 Crew for Roller Hour 6.50 263.60 1713.40
7 work inspector Day 2.00 450.00 900.00
8 mazdoor Day 4.00 350.00 1400.00
Total cost of Labour Rs: 17480.70
labour component/unit qty 21.20
Add contractor's profit and overhead charges 13.615% 2.90
labour component/unit qty (including contractor's profit) 24.10
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 90495.80
C. Cost of Labour Rs: 17480.70
Total Rs: 107976.50
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 14701
Total cost for 825.00 cum Rs: 122677.50
Rate per cum (A+B+C+D)/825 Rs: 148.70
84
Dam and Allied Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Angle dozer 90 hp Hour 4.00 1715.50 6862.00
Fuel / Energy charges Hour 4.00 610.50 2442.00
2 Shovel 0.85 cum Hour 8.00 1706.60 13652.80
Fuel / Energy charges Hour 8.00 872.70 6981.60
3 Tipper 5 cum Hour 32.00 446.70 14294.40
Fuel / Energy charges Hour 32.00 299.90 9596.80
4 Pump 5 hp ( ele ) Hour 3.00 3.00 9.00
Fuel / Energy charges Hour 3.00 28.00 84.00
5 Water tanker 8000 ltr Hour 5.00 402.50 2012.50
Fuel / Energy charges Hour 5.00 299.90 1499.50
6 Vibratory Roller 8 tonne Hour 5.00 1342.20 6711.00
Fuel / Energy charges Hour 5.00 1031.40 5157.00
7 Sundries LS 5.00 30.00 150.00
Total hire charges of Machinery Rs: 69452.60
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Dozer Hour 4.00 236.60 946.40
2 Crew for Shovel Hour 8.00 236.60 1892.80
3 Crew for Tipper Hour 32.00 177.50 5680.00
4 Crew for Pump Hour 3.00 83.30 249.90
5 Crew for Water tanker Hour 5.00 177.50 887.50
6 Crew for Roller Hour 5.00 263.60 1318.00
7 work inspector Day 2.00 450.00 900.00
8 mazdoor Day 4.00 350.00 1400.00
Total cost of Labour Rs: 13274.60
labour component/unit qty 21.10
Add contractor's profit and overhead charges 13.615% 2.90
labour component/unit qty (including contractor's profit) 24.00
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 69452.60
C. Cost of Labour Rs: 13274.60
Total Rs: 82727.20
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 11263.31
Total cost for 630.00 cum Rs: 93990.51
Rate per cum (A+B+C+D)/630 Rs: 149.20
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Angle dozer 90 hp Hour 4.60 1715.50 7891.30
Fuel / Energy charges Hour 4.60 610.50 2808.30
2 Shovel 0.85 cum Hour 8.00 1706.60 13652.80
Fuel / Energy charges Hour 8.00 872.70 6981.60
3 Tipper 5 cum Hour 48.00 446.70 21441.60
Fuel / Energy charges Hour 48.00 299.90 14395.20
4 Pump 5 hp ( ele ) Hour 4.00 3.00 12.00
Fuel / Energy charges Hour 4.00 28.00 112.00
5 Water tanker 8000 ltr Hour 8.00 402.50 3220.00
Fuel / Energy charges Hour 8.00 299.90 2399.20
6 Vibratory Roller 8 tonne Hour 7.00 1342.20 9395.40
Fuel / Energy charges Hour 7.00 1031.40 7219.80
7 Sundries LS 5.00 30.00 150.00
Total hire charges of Machinery Rs: 89679.20
85
Dam and Allied Works - Item Unit Rates 2016-17
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Dozer Hour 4.60 236.60 1088.36
2 Crew for Shovel Hour 8.00 236.60 1892.80
3 Crew for Tipper Hour 48.00 177.50 8520.00
4 Crew for Pump Hour 4.00 83.30 333.20
5 Crew for Water tanker Hour 8.00 177.50 1420.00
6 Crew for Roller Hour 7.00 263.60 1845.20
7 work inspector Day 2.00 450.00 900.00
8 mazdoor Day 4.00 350.00 1400.00
Total cost of Labour Rs: 17399.56
labour component/unit qty 17.90
Add contractor's profit and overhead charges 13.615% 2.40
labour component/unit qty (including contractor's profit) 20.30
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 89679.20
C. Cost of Labour Rs: 17399.56
Total Rs: 107078.76
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 14578.77
Total cost for 970.00 cum Rs: 121657.53
Rate per cum (A+B+C+D)/970 Rs: 125.40
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Angle dozer 90 hp Hour 4.60 1715.50 7891.30
Fuel / Energy charges Hour 4.60 610.50 2808.30
2 Shovel 0.85 cum Hour 8.00 1706.60 13652.80
Fuel / Energy charges Hour 8.00 872.70 6981.60
3 Tipper 5 cum Hour 48.00 446.70 21441.60
Fuel / Energy charges Hour 48.00 299.90 14395.20
4 Pump 5 hp ( ele ) Hour 4.00 3.00 12.00
Fuel / Energy charges Hour 4.00 28.00 112.00
5 Water tanker 8000 ltr Hour 8.00 402.50 3220.00
Fuel / Energy charges Hour 8.00 299.90 2399.20
6 Vibratory Roller 8 tonne Hour 7.00 1342.20 9395.40
Fuel / Energy charges Hour 7.00 1031.40 7219.80
7 Sundries LS 5.00 30.00 150.00
Total hire charges of Machinery Rs: 89679.20
86
Dam and Allied Works - Item Unit Rates 2016-17
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Dozer Hour 4.60 236.60 1088.36
2 Crew for Shovel Hour 8.00 236.60 1892.80
3 Crew for Tipper Hour 48.00 177.50 8520.00
4 Crew for Pump Hour 4.00 83.30 333.20
5 Crew for Water tanker Hour 8.00 177.50 1420.00
6 Crew for Roller Hour 7.00 263.60 1845.20
7 work inspector Day 2.00 450.00 900.00
8 mazdoor Day 4.00 350.00 1400.00
Total cost of Labour Rs: 17399.56
labour component/unit qty 17.90
Add contractor's profit and overhead charges 13.615% 2.40
labour component/unit qty (including contractor's profit) 20.30
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 89679.20
C. Cost of Labour Rs: 17399.56
Total Rs: 107078.76
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 14578.77
Total cost for 970.00 cum Rs: 121657.53
Rate per cum (A+B+C+D)/970 Rs: 125.40
Deduct Rate for Proctar's density Control of 95% using 8T roller as per IRR-PMW-3-23 45.80
Add Rate for Proctor's Density control of 90% using 2T Roller as per IRR-PMW-3-24 6.20
Rate per cum Rs. 85.80
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Angle dozer 90 hp Hour 5.40 1715.50 9263.70
Fuel / Energy charges Hour 5.40 610.50 3296.70
2 Shovel 0.85 cum capacity Hour 8.00 1706.60 13652.80
Fuel / Energy charges Hour 8.00 872.70 6981.60
3 Tippers 5.00 cum capacity 5 Nos. Hour 40.00 446.70 17868.00
Fuel / Energy charges Hour 40.00 299.90 11996.00
4 Pump 5 hp ( ele ) Hour 4.00 3.00 12.00
Fuel / Energy charges Hour 4.00 28.00 112.00
5 Water tanker 8000 ltr Hour 8.00 402.50 3220.00
Fuel / Energy charges Hour 8.00 299.90 2399.20
6 Vibratory Roller 8 tonne Hour 6.40 1342.20 8590.08
Fuel / Energy charges Hour 6.40 1031.40 6600.96
7 Sundries LS 2.00 30.00 60.00
Total hire charges of Machinery Rs: 84053.04
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Dozer Hour 5.40 236.60 1277.64
2 Crew for Shovel Hour 8.00 236.60 1892.80
3 Crew for Tipper Hour 40.00 177.50 7100.00
4 Crew for Pump Hour 4.00 83.30 333.20
5 Crew for Water tanker Hour 8.00 177.50 1420.00
6 Crew for Roller Hour 6.40 263.60 1687.04
7 work inspector Day 2.00 450.00 900.00
8 mazdoor Day 4.00 350.00 1400.00
Total cost of Labour Rs: 16010.68
labour component/unit qty 19.80
Add contractor's profit and overhead charges 13.615% 2.70
labour component/unit qty (including contractor's profit) 22.50
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 84053.04
C. Cost of Labour Rs: 16010.68
Total Rs: 100063.72
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 13623.68
Total cost for 807.00 cum Rs: 113687.40
Rate per cum (A+B+C+D)/807 Rs: 140.90
87
Dam and Allied Works - Item Unit Rates 2016-17
IRR-DAW-5-6 Providing embankment adjacent to masonry / concrete structures and filling trial pits
using impervious soil from approved borrow areas in layers of 10 to 15 cm and compacting
each layer to density control of not less than 95 percent using pneumatic tampers or by
vibratory earth rammers including cost of all materials, machinery, labour, picking previous
layer, spreading soil in layer, breaking clods, watering etc., complete with initial lead upto
1 km and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Angle dozer 90 hp Hour 0.15 1715.50 257.33
Fuel / Energy charges Hour 0.15 610.50 91.58
2 Shovel 0.85 cum Hour 0.80 1706.60 1365.28
Fuel / Energy charges Hour 0.80 872.70 698.16
3 Tipper 5 cum Hour 3.00 446.70 1340.10
Fuel / Energy charges Hour 3.00 299.90 899.70
4 Air compressor 8.5 cmm ( ele ) Hour 8.00 170.80 1366.40
Fuel / Energy charges Hour 8.00 315.20 2521.60
5 Pump 5 hp ( ele ) Hour 0.40 3.00 1.20
Fuel / Energy charges Hour 0.40 28.00 11.20
6 Water tanker 8000 ltr Hour 0.80 402.50 322.00
Fuel / Energy charges Hour 0.80 299.90 239.92
7 Pneumatic tampers 2 Nos. Hour 16.00 20.70 331.20
Fuel / Energy charges Hour 16.00 0.00 0.00
8 Sundries LS 1.00 30.00 30.00
Total hire charges of Machinery Rs: 9475.66
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Dozer Hour 0.15 236.60 35.49
2 Crew for Shovel Hour 0.80 236.60 189.28
3 Crew for Tipper Hour 3.00 177.50 532.50
4 Crew for Air compressor Hour 8.00 164.80 1318.40
5 Crew for Pump Hour 0.40 83.30 33.32
6 Crew for Water tanker Hour 0.80 177.50 142.00
7 Crew for Pneumatic tamper Hour 16.00 263.60 4217.60
8 work inspector Day 1.00 450.00 450.00
9 mazdoor Day 5.00 350.00 1750.00
Total cost of Labour Rs: 8668.59
labour component/unit qty 108.40
Add contractor's profit and overhead charges 13.615% 14.80
labour component/unit qty (including contractor's profit) 123.20
ABSTRACT:
A. Cost of Materials Rs: 185.00
B. Hire charges of Machinery Rs: 9475.66
C. Cost of Labour Rs: 8668.59
Total Rs: 18329.25
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 2495.53
Total cost for 80.00 cum Rs: 20824.78
Rate per cum (A+B+C+D)/80 Rs: 260.30
IRR-DAW-5-7 Providing and constructing rockfill embankment with 300 mm down graded stones and
quarry spalls from approved source including cost of all materials, machinery, labour, spreading
stones and spalls in layers, hand packing, wedging, finishing the surface to required slopes
etc., complete with initial lead upto 1 km and all lifts.
88
Dam and Allied Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Air compressor 8.5cmm( diesel )3 Nos Hour 30.00 275.60 8268.00
Fuel / Energy charges Hour 30.00 892.50 26775.00
2 Jack hammer 6 Nos Hour 60.00 19.80 1188.00
Fuel / Energy charges Hour 60.00 0.00 0.00
3 Angle dozer 90 hp Hour 4.00 1715.50 6862.00
Fuel / Energy charges Hour 4.00 610.50 2442.00
4 Shovel 0.85 cum Hour 8.00 1706.60 13652.80
Fuel / Energy charges Hour 8.00 872.70 6981.60
5 Tipper 5 cum Hour 24.00 446.70 10720.80
Fuel / Energy charges Hour 24.00 299.90 7197.60
Total hire charges of Machinery Rs: 84087.80
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Air compressor Hour 30.00 210.90 6327.00
2 Crew for Jack hammer Hour 60.00 329.60 19776.00
3 Crew for Shovel Hour 8.00 236.60 1892.80
4 Crew for Tipper Hour 24.00 177.50 4260.00
5 Crew for Dozer Hour 4.00 236.60 946.40
6 Blaster Day 1.00 510.00 510.00
7 Helper blaster Day 1.00 400.00 400.00
8 work inspector Day 2.00 450.00 900.00
9 Mason Class-II Day 2.00 400.00 800.00
10 mazdoor Day 10.00 350.00 3500.00
Total cost of Labour Rs: 39312.20
labour component/unit qty 98.30
Add contractor's profit and overhead charges 13.615% 13.40
labour component/unit qty (including contractor's profit) 111.70
ABSTRACT:
A. Cost of Materials Rs: 30607.60
B. Hire charges of Machinery Rs: 84087.80
C. Cost of Labour Rs: 39312.20
Total Rs: 154007.60
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 20968.14
Total cost for 400.00 cum Rs: 174975.74
Rate per cum (A+B+C+D)/400 Rs: 437.40
IRR-DAW-5-8 Providing and constructing dry rubble rock-toe using rubble and stone chips from
approved source including cost of all materials, machinery, labour, hand packing rubble
and stone chips, finishing top and sides to required slopes etc., complete with initial lead upto
1 km and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Air compressor 8.5 cmm ( diesel ) Hour 7.50 275.60 2067.00
Fuel / Energy charges Hour 7.50 892.50 6693.75
2 Jack hammer Hour 15.00 19.80 297.00
Fuel / Energy charges Hour 15.00 0.00 0.00
3 Shovel 0.85 cum Hour 2.00 1706.60 3413.20
Fuel / Energy charges Hour 2.00 872.70 1745.40
4 Tipper 5 cum Hour 6.00 446.70 2680.20
Fuel / Energy charges Hour 6.00 299.90 1799.40
Total hire charges of Machinery Rs: 18695.95
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Air compressor Hour 7.50 210.90 1581.75
2 Crew for Jack hammer Hour 15.00 329.60 4944.00
3 Crew for Shovel Hour 2.00 236.60 473.20
4 Crew for Tipper Hour 6.00 177.50 1065.00
5 Blaster Day 0.50 510.00 255.00
6 Helper blaster Day 1.00 400.00 400.00
7 work inspector Day 1.00 450.00 450.00
8 Mason Class-II Day 7.00 400.00 2800.00
9 mazdoor Day 19.00 350.00 6650.00
Total cost of Labour Rs: 18618.95
89
Dam and Allied Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 7686.12
B. Hire charges of Machinery Rs: 18695.95
C. Cost of Labour Rs: 18618.95
Total Rs: 45001.02
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 6126.89
Total cost for 100.00 cum Rs: 51127.91
Rate per cum (A+B+C+D)/100 Rs: 511.30
IRR-DAW-5-9 Providing and constructing dry rubble rock-toe with rubble and stone chips from dump
yard (Spoil Bank) including cost of all materials, machinery, labour, hand packing rubble and stone chips,
finishing top and sides to required slopes etc., complete with initial lead upto 1 km and all
lifts.
Note: Useful rubble and stone chips will be issued at dump yard at the issue rate for usefull rubble /
stone chips. Sorting out and breaking charges included in rate analysis.
DATA: RATE ANALYSIS
UNIT : 100 cum
A. MATERIALS:
Sl No Particulars Unit Quantity Rate Amount
in Rs. in Rs
1 Useful rubble ( at dump yard ) cum 100.00 155.00 15500.00
2 Useful stone chips ( at dump yard ) cum 15.00 185.00 2775.00
Total cost of Materials Rs: 18275.00
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Shovel 0.85 cum Hour 2.00 1706.60 3413.20
Fuel / Energy charges Hour 2.00 872.70 1745.40
2 Tipper 5 cum Hour 6.00 446.70 2680.20
Fuel / Energy charges Hour 6.00 299.90 1799.40
Total hire charges of Machinery Rs: 9638.20
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Shovel Hour 2.00 236.60 473.20
2 Crew for Tipper Hour 6.00 177.50 1065.00
3 Mason Class-II Day 7.00 400.00 2800.00
4 work inspector Day 1.00 450.00 450.00
6 Stone breaker Day 2.00 400.00 800.00
7 mazdoor Day 21.00 350.00 7350.00
Total cost of Labour Rs: 12938.20
labour component/unit qty 129.40
Add contractor's profit and overhead charges 13.615% 17.60
labour component/unit qty (including contractor's profit) 147.00
ABSTRACT:
A. Cost of Materials Rs: 18275.00
B. Hire charges of Machinery Rs: 9638.20
C. Cost of Labour Rs: 12938.20
Total Rs: 40851.40
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 5561.92
Total cost for 100.00 cum Rs: 46413.32
Rate per cum (A+B+C+D)/100 Rs: 464.10
IRR-DAW-5-9-A Providing and constructing Dry rock Pitching for Groynes using Un-Coursed rubble stone of size 300 mm thick
(New Item 4 -2012-13) and Un-Coursed rubble stone chips from Quarry to site of work including cost of all materials, Machinery, Labour charge
hand packing Un-Course rubble stone &chips to the designed profile with all leads and lifts etc
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
Shovel 0.85 cum for loading tipper at the
1 worksite Hour 2.00 1706.60 3413.20
Fuel / Energy charges Hour 2.00 872.70 1745.40
2 Tipper 5 cum Hour 6.00 446.70 2680.20
Fuel / Energy charges Hour 6.00 299.90 1799.40
Total hire charges of Machinery Rs: 9638.20
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Shovel Hour 2.00 236.60 473.20
2 Crew for Tipper Hour 6.00 177.50 1065.00
3 Mason Class-II Day 7.00 400.00 2800.00
4 work inspector Day 1.00 450.00 450.00
6 Stone breaker Day 2.00 400.00 800.00
7 mazdoor Day 21.00 350.00 7350.00
Total cost of Labour Rs: 12938.20
labour component/unit qty 129.40
Add contractor's profit and overhead charges 13.615% 17.60
90
Dam and Allied Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 37050.00
B. Hire charges of Machinery Rs: 9638.20
C. Cost of Labour Rs: 12938.20
Total Rs: 59626.40
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 8118.13
Total cost for 100.00 cum Rs: 67744.53
Rate per cum (A+B+C+D)/100 Rs: 677.40
IRR-DAW-5-10 Providing and laying 30 cm diameter open jointed hume pipes with collars in rock-toe for
drainage including cost of all materials, machinery, labour etc., complete with lead upto 1 km
and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Mason Cl- II Day 2 400.00 800.00
2 mazdoor Day 6 350.00 2100.00
Total cost of Labour Rs: 2900.00
labour component/unit qty 29.00
Add contractor's profit and overhead charges 13.615% 3.90
labour component/unit qty (including contractor's profit) 32.90
ABSTRACT:
A. Cost of Materials Rs: 60000.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 2900.00
Total Rs: 62900.00
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 8563.84
Total cost for 100.00 Rm Rs: 71463.84
Rate per Rm (A+B+C+D)/100 Rs: 714.60
IRR-DAW-6-1 Providing and constructing 1.20 m internal diameter and average 3 m height RCC manhole with
60 cm dia. top cover in M-15 grade cement concrete using 20 mm down graded, clean, hard
coarse aggregate, 20 cm thick for bed / sides / top slab / 1.5 m long cut-off wall and 7.5 cm
thick for cover including providing 12 mm dia reinforcement bars at 30 cm c / c bothways for
bed / sides / cut-off wall / top slab / rungs and 8 mm dia bars at 15 cm c / c bothways for cover,
excavation for foundation, providing 30 cm dia hume pipe outlet, cost of all materials, machinery,
labour, formwork, scaffolding, batching, mixing, laying, vibrating, finishing, curing etc., complete
with lead upto 1 km and all lifts.
( Cement content : 300 kg/cum , CA : 0.80 cum, Blending Ratioof CA -- 65:35,
FA : 0.44 cum, superplasticizer (0.4% by wt. of cement)
91
Dam and Allied Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Concrete mixer 300 / 200 ( ele ) Hour 4.00 51.70 206.80
Fuel / Energy charges Hour 4.00 28.00 112.00
2 Needle vibrator 40 mm dia ( ele ) Hour 4.00 8.00 32.00
Fuel / Energy charges Hour 4.00 5.60 22.40
3 Pump 5 hp ( ele ) Hour 0.50 3.00 1.50
Fuel / Energy charges Hour 0.50 28.00 14.00
4 Sundries LS 1.00 30.00 30.00
Total hire charges of Machinery Rs: 418.70
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Mason Cl- II Day 1.00 400.00 400.00
2 Bar bender Day 1.00 555.00 555.00
3 work inspector Day 1.00 450.00 450.00
4 mazdoor
for excavation for foundation Day 2.00 350.00 700.00
for bar bending Day 1.00 350.00 350.00
for concreting Day 5.00 350.00 1750.00
for excavation for foundation Day 2.00 350.00 700.00
for concreting Day 4.00 350.00 1400.00
for curing Day 1.00 350.00 350.00
5 Labour for shuttering sqm 36.00 88.50 3186.00
Total cost of Labour Rs: 9841.00
labour component/unit qty 9841.00
Add contractor's profit and overhead charges 13.615% 1339.90
labour component/unit qty (including contractor's profit) 11180.90
ABSTRACT:
A. Cost of Materials Rs: 27286.95
B. Hire charges of Machinery Rs: 418.70
C. Cost of Labour Rs: 9841.00
Total Rs: 37546.65
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 5111.98
Lead Charges for 1 Km for FA 1.95 cum @ 31.5 Rs./Cum 61.52454
Lead Charges for 1 Km for CA 3.55 cum @ 30.4 Rs./Cum 107.96
Lead Charges for 1Km for Steel (including Loading
and Unloading Charges) 0.16 tonne @ 168.6 Rs./Tonne 27.598977
Total cost for 1.00 Each Rs: 42855.71
Rate per Each (A+B+C+D)/1.0 Rs: 42855.70
IRR-DAW-6-2 Providing and constructing longitudinal and cross graded filter drains using sand and 80-20
mm and 20 mm down graded aggregates satisfying specified filter creteria in layers as per
specifications including cost of all materials, machinery, labour, laying to required slopes,
compaction etc. complete with initial lead upto 50 m and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 work inspector Day 1.00 450.00 450.00
2 mazdoor Day 38.00 350.00 13300.00
Total cost of Labour Rs: 13750.00
labour component/unit qty 137.50
Add contractor's profit and overhead charges 13.615% 18.70
labour component/unit qty (including contractor's profit) 156.20
92
Dam and Allied Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 55800.56
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 13750.00
Total Rs: 69550.56
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 9469.31
Total cost for 100.00 cum Rs: 79019.87
Rate per cum (A+B+C+D)/100 Rs: 790.20
IRR-DAW-6-3 Providing and constructing 1.40 m thick vertical or inclined graded filter media consisting of
20 cm thick sand layers, 25 cm thick 20 mm down coarse aggregate layers and 50 cm thick
80-20 mm coarse aggregate layer using approved materials satisfying specified filter creteria as
per specifications including cost of all materials, machinery, labour, laying to required slope,
compaction etc., complete with initial lead upto 50 m and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 work inspector Day 1.00 450.00 450.00
2 mazdoor Day 38.00 350.00 13300.00
Total cost of Labour Rs: 13750.00
labour component/unit qty 137.50
Add contractor's profit and overhead charges 13.615% 18.70
labour component/unit qty (including contractor's profit) 156.20
ABSTRACT:
A. Cost of Materials Rs: 70281.88
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 13750.00
Total Rs: 84031.88
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 11440.94
Total cost for 100.00 cum Rs: 95472.82
Rate per cum (A+B+C+D)/100 Rs: 954.70
IRR-DAW-6-4 Providing and constructing graded filter media below and behind rock-toe consisting of
20 cm thick sand, 25 cm thick 20 - 4.75 mm and 40 cm thick 80 - 20 mm size graded coarse
aggregates satisfying filter creteria as per specifications including cost of all materials, labour,
machinery, laying to required slope, compaction etc., complete with initial lead upto 50 m and
all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 work inspector Day 1.00 450.00 450.00
2 mazdoor Day 34.00 350.00 11900.00
Total cost of Labour Rs: 12350.00
labour component/unit qty 123.50
Add contractor's profit and overhead charges 13.615% 16.80
labour component/unit qty (including contractor's profit) 140.30
93
Dam and Allied Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 68951.25
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 12350.00
Total Rs: 81301.25
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 11069.17
Total cost for 100.00 cum Rs: 92370.42
Rate per cum (A+B+C+D)/100 Rs: 923.70
IRR-DAW-6-4-A Providing and constructing graded filter media below and behind rock-toe consisting of
(New Item2- 2011-12) 30 cm thick 80 - 20 mm size graded coarse
aggregates satisfying filter creteria as per specifications including cost of all materials, labour,
machinery, laying to required slope, compaction etc., complete with initial lead upto 50 m and
all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 work inspector Day 1.00 450.00 450.00
2 mazdoor Day 12.00 350.00 4200.00
Total cost of Labour Rs: 4650.00
labour component/unit qty 46.50
Add contractor's profit and overhead charges 13.615% 6.30
labour component/unit qty (including contractor's profit) 52.80
ABSTRACT:
A. Cost of Materials Rs: 98000.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 4650.00
Total Rs: 102650.00
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 13975.8
Total cost for 100.00 cum Rs: 116625.80
Rate per cum (A+B+C+D)/100 Rs: 1166.30
IRR-DAW-6-5 Providing and laying filter media consisting of 2 layers of 250 gsm poly-propeline non-woven
filter fabric and 400 mm thick 20 mm down graded coarse aggregate for vertical / inclined
and horizontal filter blanket for embankment including cost of all materials, machinery, labour
etc., complete with lead upto 50 m for aggregate and all leads for fabric and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 work inspector Day 1.00 450.00 450.00
2 mazdoor Day 14.00 350.00 4900.00
Total cost of Labour Rs: 5350.00
94
Dam and Allied Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 78750.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 5350.00
Total Rs: 84100.00
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 11450.22
Total cost for 100.00 sqm Rs: 95550.22
Rate per sqm (A+B+C+D)/100 Rs: 955.50
IRR-DAW-6-6 Providing and constructing 45 cm thick chimney filter using clean approved sand satisfying
filter creteria including cost of all materials, machinery, labour, compacting etc., complete with
initial lead upto 50 m and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 work inspector Day 1.00 450.00 450.00
2 mazdoor Day 30.00 350.00 10500.00
Total cost of Labour Rs: 10950.00
labour component/unit qty 109.50
Add contractor's profit and overhead charges 13.615% 14.90
labour component/unit qty (including contractor's profit) 124.40
ABSTRACT:
A. Cost of Materials Rs: 9975.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 10950.00
Total Rs: 20925.00
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 2848.94
Total cost for 100.00 cum Rs: 23773.94
Rate per cum (A+B+C+D)/100 Rs: 237.70
IRR-DAW-6-7 Providing and constructing 90 cm thick transition cum filter media behind rockfill using
approved sand and 80-20 mm and 20 mm down graded aggregates satisfying the filter creteria
in layers of 30 cm thickness each as per specifications including cost of all materials,
machinery, labour, laying each layer to required slope, compaction etc., complete with initial
lead upto 50 m and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 work inspector Day 1.00 450.00 450.00
2 mazdoor Day 40.00 350.00 14000.00
Total cost of Labour Rs: 14450.00
labour component/unit qty 144.50
Add contractor's profit and overhead charges 13.615% 19.70
labour component/unit qty (including contractor's profit) 164.20
ABSTRACT:
A. Cost of Materials Rs: 66002.50
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 14450.00
Total Rs: 80452.50
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 10953.61
95
Dam and Allied Works - Item Unit Rates 2016-17
IRR-DAW-6-8 Providing and constructing 60 cm thick hand packed rough stone revetment with 65 to
75 cm long through stones at 1.50 m c / c over a backing of 45 cm thick graded filter media
consisting of sand, 10 mm and 40 mm size approved graded aggregates laid in layers of 15 cm
thick each including cost of all materials, machinery, labour, laying to required slopes, wedging
with chips, finishing etc. complete with initial lead upto 50 m and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 work inspector Day 1.00 450.00 450.00
2 Mason Class-II Day 10.00 400.00 4000.00
3 mazdoor Day 33.00 350.00 11550.00
Total cost of Labour Rs: 16000.00
labour component/unit qty 160.00
Add contractor's profit and overhead charges 13.615% 21.80
labour component/unit qty (including contractor's profit) 181.80
ABSTRACT:
A. Cost of Materials Rs: 57263.80
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 16000.00
Total Rs: 73263.80
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 9974.87
Total cost for 100.00 sqm Rs: 83238.67
Rate per sqm (A+B+C+D)/100 Rs: 832.40
IRR-DAW-6-9 Providing and constructing 60 cm thick hand packed rough stone revetment with 65 to 75
cm long through stones at 1.50 m c / c over a backing of 60 cm thick graded filter media
consisting of sand, 10 mm and 40 mm size approved graded aggregates laid in layers of 20 cm
thick each including cost of all materials, machinery, labour, laying to required slopes, wedging
with chips, finishing etc. complete with initial lead upto 50 m and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
96
Dam and Allied Works - Item Unit Rates 2016-17
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 work inspector Day 1.00 450.00 450.00
2 Mason Class-II Day 10.00 400.00 4000.00
3 mazdoor Day 39.00 350.00 13650.00
Total cost of Labour Rs: 18100.00
labour component/unit qty 181.00
Add contractor's profit and overhead charges 13.615% 24.60
labour component/unit qty (including contractor's profit) 205.60
ABSTRACT:
A. Cost of Materials Rs: 68330.80
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 18100.00
Total Rs: 86430.80
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 11767.55
Total cost for 100.00 sqm Rs: 98198.35
Rate per sqm (A+B+C+D)/100 Rs: 982.00
IRR-DAW-6-10 Providing and constructing 60 cm thick hand packed rough stone riprap over a backing of
45 cm thick graded filter media consisting of sand, 10 mm and 40 mm size graded approved
aggregates laid in layers of 15 cm thick each including cost of all materials, machinery,
labour, laying to required slopes, wedging with stone chips etc., complete with initial lead upto
50 m and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 work inspector Day 1.00 450.00 450.00
2 Mason Class-II Day 5.00 400.00 2000.00
3 mazdoor Day 28.00 350.00 9800.00
Total cost of Labour Rs: 12250.00
labour component/unit qty 122.50
Add contractor's profit and overhead charges 13.615% 16.70
labour component/unit qty (including contractor's profit) 139.20
ABSTRACT:
A. Cost of Materials Rs: 55431.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 12250.00
Total Rs: 67681.00
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 9214.77
Total cost for 100.00 sqm. Rs: 76895.77
Rate per sqm. (A+B+C+D)/100 Rs: 769.00
IRR-DAW-6-11 Providing and constructing 75 cm thick hand packed rough stone riprap over a backing of
45 cm thick graded filter media consisting of sand, 10 mm and 40 mm size graded approved
aggregates laid in layers of 15 cm thick each including cost of all materials, machinery, labour,
laying to required slopes, wedging with stone chips, etc., complete with initial lead upto 50 m
and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
97
Dam and Allied Works - Item Unit Rates 2016-17
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 work inspector Day 1.00 450.00 450.00
2 Mason Class-II Day 6.00 400.00 2400.00
3 mazdoor Day 30.00 350.00 10500.00
Total cost of Labour Rs: 13350.00
labour component/unit qty 133.50
Add contractor's profit and overhead charges 13.615% 18.20
labour component/unit qty (including contractor's profit) 151.70
ABSTRACT:
A. Cost of Materials Rs: 60901.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 13350.00
Total Rs: 74251.00
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 10109.27
Total cost for 100.00 sqm Rs: 84360.27
Rate per sqm (A+B+C+D)/100 Rs: 843.60
IRR-DAW-6-12 Providing and constructing 90 cm thick hand packed rough stone riprap over a backing of
45 cm thick graded filter media consisting of sand, 10 mm and 40 mm size graded approved
aggregates laid in layers of 15 cm thick each including cost of all materials, machinery,
labour, laying to required slopes, wedging with stone chips etc., complete with initial lead upto
50 m and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 work inspector Day 1.00 450.00 450.00
2 Mason Class-II Day 8.00 400.00 3200.00
3 mazdoor Day 34.00 350.00 11900.00
Total cost of Labour Rs: 15550.00
labour component/unit qty 155.50
Add contractor's profit and overhead charges 13.615% 21.20
labour component/unit qty (including contractor's profit) 176.70
ABSTRACT:
A. Cost of Materials Rs: 66546.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 15550.00
Total Rs: 82096.00
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 11177.37
Total cost for 100.00 sqm Rs: 93273.37
Rate per sqm (A+B+C+D)/100 Rs: 932.70
IRR-DAW-6-13 Providing and laying Hariyala or other approved quality turfing sods for the slopes of earthen
embankments over 20 mm thick sand backing including cost of all materials, machinery,
labour including preparing surface, spreading sand, watering for 15 days etc., complete with
initial lead upto 1 km and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
98
Dam and Allied Works - Item Unit Rates 2016-17
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Cartman with double bullock cart Day 2.00 465.00 930.00
2 mazdoor Day 15.00 350.00 5250.00
Total cost of Labour Rs: 6180.00
labour component/unit qty 61.80
Add contractor's profit and overhead charges 13.615% 8.40
labour component/unit qty (including contractor's profit) 70.20
ABSTRACT:
A. Cost of Materials Rs: 2990.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 6180.00
Total Rs: 9170.00
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 1248.5
Lead Charges for 1 Km for FA 2.00 cum @ 31.5 Rs./Cum 63
Total cost for 100.00 sqm. Rs: 10481.50
Rate per sqm. (A+B+C+D)/100 Rs: 104.80
99
Tunnel and Allied Works - Item Unit Rates 2016-17
Chapter - II
3. The Leads for Steel shall be from the nearest market place to the Project area
4. For earth/rockfill embankments wherever initial lead of 1km is considered in the basic rate, the additional lead charges are to be added
as follows:
Additional lead charges for Earth, Murrum etc., shall be worked out for total lead involved and 1 km lead charges included in basic
rate shall be deducted from total lead charges. No loading and unloading charges shall be allowed for any item. (same as above)
Example:
Total lead for earth from approved borrow area : 15 Km
Initial lead included in the basic rate in the SR : 1 Km
Additional lead charges : Lead charges for 5 km Rs. 84.00
Lead charges for next 10 km Rs. 126
Total lead charges for 15 km /cum Rs. 210.00
Less 1 km initial lead charges /cum Rs. 31.50 (-)
Net additional lead charges / cum Rs. 178.50
5. The initial lead up to 50 m as mentioned in some standard data items is meant for manual lead within the working area. For
conveyance of materials, the lead required from quarry/Borrow area/ Dump Area to worksite shall be added to the data without
deducting the 50 m initial lead charges
TAW -Work Items
IRR-TAW-1 EXCAVATION :
IRR-TAW-1-1 Excavation for adit by tunnelling methods in all types of rock including cost of all materials,
machinery, labour, scaling excavated surface, ventilation, lighting, drainage, removing and
hauling the excavated muck outside adit upto specified dump area and all other ancillary
operations etc., complete with initial lead upto 1km and all lifts.
100
Tunnel and Allied Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Drilling jumbo Hour 8.00 368.40 2947.20
Fuel / Energy charges Hour 8.00 42.80 342.40
2 Air compressor 15 cmm ( ele ) Hour 5.00 138.80 694.00
Fuel / Energy charges Hour 5.00 700.50 3502.50
3 Jack hammer ( 4 x 5 hrs ) Hour 20.00 19.80 396.00
Fuel / Energy charges Hour 20.00 0.00 0.00
4 Pusher leg Hour 20.00 12.70 254.00
Fuel / Energy charges Hour 20.00 0.00 0.00
5 Convey mucker Hour 6.50 822.80 5348.20
Fuel / Energy charges Hour 6.50 195.00 1267.50
6 Dumper ( 1 x 6.5 hrs ) Hour 6.50 580.70 3774.55
Fuel / Energy charges Hour 6.50 399.90 2599.35
7 Pump 10 hp ( ele ) Hour 5.00 6.70 33.50
Fuel / Energy charges Hour 5.00 56.00 280.00
8 Ventilation fans 20 hp Hour 1.00 11.50 11.50
Fuel / Energy charges Hour 1.00 112.10 112.10
9 Sundries(explosive van / magazine ) LS 2.00 30.00 60.00
Total hire charges of Machinery Rs: 21622.80
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Drilling jumbo Hour 8.00 175.80 1406.40
2 Crew for Air compressor Hour 5.00 175.80 879.00
3 Crew for Jack hammer Hour 20.00 329.60 6592.00
4 Crew for Convey mucker Hour 6.50 175.80 1142.70
5 Crew for Dumper Hour 6.50 227.10 1476.15
6 Crew for Pump Hour 5.00 83.30 416.50
7 Crew for ventilation fans Hour 1.00 28.70 28.70
8 Surveyor Day 0.50 645.00 322.50
9 Foreman Day 1.00 510.00 510.00
10 Fitter / Mechanic Day 2.00 475.00 950.00
11 Blaster ( Licensed ) Day 1.00 510.00 510.00
12 Helper blasting Day 2.00 400.00 800.00
13 Hammerman Day 2.00 400.00 800.00
14 work inspector 1 in each shift Day 3.00 450.00 1350.00
101
Tunnel and Allied Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 10133.91
B. Hire charges of Machinery Rs: 21622.80
C. Cost of Labour Rs: 21763.95
Total Rs: 53520.66
Add for Air and Water line @ 1.00% Rs: 535.21
Add for Ventilation @ 4.50% Rs: 2408.43
Add for Lighting @ 1.60% Rs: 856.33
Add for Ele sub-station / Demand charges @ 2.50% Rs: 1338.02
Total Rs: 58658.64
D.Add for contractor's profit and overheads on (A+B+C+other
percentages) 13.615% Rs: 7986.37
Total cost for 38.50 cum Rs: 66645.01
Rate per cum (A+B+C+D)/38.50 Rs: 1731.00
IRR-TAW-1-2 Excavation for vertical / inclined shaft in all types of soft / hard rock including cost of all
materials, machinery, labour, shoring, strutting, scaling excavated surface, ventilation, lighting,
drainage, removing and hauling excavated muck outside shaft upto specified dump area and
all other ancillary operations etc., complete with initial lead upto 1 km and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Air compressor 15 cmm ( ele ) Hour 4.50 138.80 624.60
Fuel / Energy charges Hour 4.50 700.50 3152.25
2 Jack hammer ( 4 x 4 hrs ) Hour 16.00 19.80 316.80
Fuel / Energy charges Hour 16.00 0.00 0.00
3 Pump 10 hp ( ele ) Hour 4.00 6.70 26.80
Fuel / Energy charges Hour 4.00 56.00 224.00
4 Pump 20 hp electric Hour 2.00 12.30 24.60
Fuel / Energy charges Hour 2.00 112.10 224.20
5 Winch 35 hp electric Hour 28.00 129.40 3623.20
Fuel / Energy charges Hour 28.00 137.30 3844.40
6 Tipping tub 1.5 cum Hour 24.00 64.20 1540.80
Fuel / Energy charges Hour 24.00 0.00 0.00
7 Sundries(explosive van / magazine ) LS 2.00 30.00 60.00
Total hire charges of Machinery Rs: 13661.65
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Air compressor Hour 4.50 175.80 791.10
2 Crew for Jack hammer Hour 16.00 329.60 5273.60
102
Tunnel and Allied Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 7951.06
B. Hire charges of Machinery Rs: 13661.65
C. Cost of Labour Rs: 34037.80
Total Rs: 55650.51
Add for Air and Water line @ 1.00% Rs: 556.51
Add for Ventilation @ 4.50% Rs: 2504.27
Add for Lighting @ 1.60% Rs: 890.41
Add for Ele sub-station / Demand charges @ 2.50% Rs: 1391.26
Total Rs: 60992.96
D.Add for contractor's profit and overheads on (A+B+C+other
percentages) 13.615% Rs: 8304.19
Total cost for 30.00 cum Rs: 69297.15
Rate per cum (A+B+C+D)/30.0 Rs: 2309.90
IRR-TAW-1-3 Excavation for tunnel by tunnelling methods in rock not requiring supports including cost
of all materials,machinery, labour, scaling excavated surface, removing under-cuts, ventilation,
lighting, drainage, removing and hauling the excavated muck outside tunnel upto specified
dump area and all other ancillary operations etc., complete with initial lead upto 1 km and
all lifts.
103
Tunnel and Allied Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Drilling jumbo Hour 10.00 368.40 3684.00
Fuel / Energy charges Hour 10.00 42.80 428.00
2 Air compressor 15 cmm ( ele ) Hour 6.50 138.80 902.20
Fuel / Energy charges Hour 6.50 700.50 4553.25
3 Jack hammer ( 4 x 6.5 hrs ) Hour 26.00 19.80 514.80
Fuel / Energy charges Hour 26.00 0.00 0.00
4 Pusher leg Hour 26.00 12.70 330.20
Fuel / Energy charges Hour 26.00 0.00 0.00
5 Convey mucker Hour 6.00 822.80 4936.80
Fuel / Energy charges Hour 6.00 195.00 1170.00
6 Dumper ( 2 x 6 hrs ) Hour 12.00 580.70 6968.40
Fuel / Energy charges Hour 12.00 399.90 4798.80
7 Pump 10 hp ( ele ) Hour 6.50 6.70 43.55
Fuel / Energy charges Hour 6.50 56.00 364.00
8 Ventilation fans 20 hp Hour 2.00 11.50 23.00
Fuel / Energy charges Hour 2.00 112.10 224.20
9 Sundries(explosive van / magazine ) LS 2.00 30.00 60.00
Total hire charges of Machinery Rs: 29001.20
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Drilling jumbo Hour 10.00 175.80 1758.00
2 Crew for Air compressor Hour 6.50 175.80 1142.70
3 Crew for Jack hammer Hour 26.00 329.60 8569.60
4 Crew for Convey mucker Hour 6.00 175.80 1054.80
5 Crew for Dumper Hour 12.00 227.10 2725.20
6 Crew for Pump Hour 6.50 83.30 541.45
7 Crew for ventilation fans Hour 2.00 28.70 57.40
8 Surveyor Day 0.50 645.00 322.50
9 Foreman Day 1.00 510.00 510.00
10 Fitter / Mechanic Day 2.00 475.00 950.00
11 Blaster ( Licensed ) Day 1.00 510.00 510.00
12 Helper blasting Day 2.00 400.00 800.00
13 Hammerman Day 2.00 400.00 800.00
14 work inspector 1 in each shift Day 3.00 450.00 1350.00
15 Khalasi for mucking shift 4 Nos Day 4.00 445.00 1780.00
16 mazdoor
for mucking shift 8 Nos Day 8.00 350.00 2800.00
for other 2 shifts 1 No each shift Day 2.00 350.00 700.00
for cleaning & miscellaneous Day 2.00 350.00 700.00
Total cost of Labour Rs: 27071.65
labour component/unit qty 557.00
Add contractor's profit and overhead charges 13.615% 75.80
labour component/unit qty (including contractor's profit) 632.80
ABSTRACT:
A. Cost of Materials Rs: 12916.90
B. Hire charges of Machinery Rs: 29001.20
C. Cost of Labour Rs: 27071.65
Total Rs: 68989.75
Add for Air and Water line @ 1.00% Rs: 689.90
Add for Ventilation @ 4.50% Rs: 3104.54
Add for Lighting @ 1.60% Rs: 1103.84
Add for Ele sub-station / Demand charges @ 2.50% Rs: 1724.74
Total Rs: 75612.77
D.Add for contractor's profit and overheads on (A+B+C+other
percentages) 13.615% Rs: 10294.68
Total cost for 48.60 cum Rs: 85907.44
Rate per cum (A+B+C+D)/48.60 Rs: 1767.60
104
Tunnel and Allied Works - Item Unit Rates 2016-17
IRR-TAW-1-4 Excavation for tunnel by tunnelling methods including excavation for supports in all types of
soil / rock strata requiring supports ( excluding cost of providing supports ) including cost of
all other materials, machinery, labour, scaling excavated surface, ventilation, lighting, drainage,
removing and hauling the excavated muck outside tunnel upto specified dump area and all
other ancillary operations etc., complete with initial lead upto 1 km and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Drilling jumbo Hour 11.00 368.40 4052.40
Fuel / Energy charges Hour 11.00 42.80 470.80
2 Air compressor 15 cmm ( ele ) Hour 6.00 138.80 832.80
Fuel / Energy charges Hour 6.00 700.50 4203.00
3 Jack hammer ( 4 x 6 hrs ) Hour 24.00 19.80 475.20
Fuel / Energy charges Hour 24.00 0.00 0.00
4 Pusher leg Hour 24.00 12.70 304.80
Fuel / Energy charges Hour 24.00 0.00 0.00
5 Convey mucker Hour 6.00 822.80 4936.80
Fuel / Energy charges Hour 6.00 195.00 1170.00
6 Dumper ( 2 x 6 hrs ) Hour 12.00 580.70 6968.40
Fuel / Energy charges Hour 12.00 399.90 4798.80
7 Pump 10 hp ( ele ) Hour 6.00 6.70 40.20
Fuel / Energy charges Hour 6.00 56.00 336.00
8 Ventilation fans 20 hp Hour 2.00 11.50 23.00
Fuel / Energy charges Hour 2.00 112.10 224.20
9 Sundries(explosive van / magazine ) LS 2.00 30.00 60.00
Total hire charges of Machinery Rs: 28896.40
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Drilling jumbo Hour 11.00 175.80 1933.80
2 Crew for Air compressor Hour 6.00 175.80 1054.80
3 Crew for Jack hammer Hour 24.00 329.60 7910.40
4 Crew for Convey mucker Hour 6.00 175.80 1054.80
5 Crew for Dumper Hour 12.00 227.10 2725.20
6 Crew for Pump Hour 6.00 83.30 499.80
7 Crew for ventilation fans Hour 2.00 28.70 57.40
8 Surveyor Day 0.50 645.00 322.50
9 Foreman Day 1.00 510.00 510.00
10 Fitter / Mechanic Day 2.00 475.00 950.00
11 Blaster ( Licensed ) Day 1.00 510.00 510.00
12 Helper blasting Day 2.00 400.00 800.00
13 Hammerman 2 Nos Day 2.00 400.00 800.00
14 work inspector 1 in each shift Day 3.00 450.00 1350.00
15 Khalasi for mucking shift 4 Nos Day 4.00 445.00 1780.00
16 mazdoor
for mucking shift 8 Nos Day 8.00 350.00 2800.00
for other 2 shifts 1 No each shift Day 2.00 350.00 700.00
for cleaning & miscellaneous Day 2.00 350.00 700.00
Total cost of Labour Rs: 26458.70
labour component/unit qty 575.20
Add contractor's profit and overhead charges 13.615% 78.30
labour component/unit qty (including contractor's profit) 653.50
105
Tunnel and Allied Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 11911.72
B. Hire charges of Machinery Rs: 28896.40
C. Cost of Labour Rs: 26458.70
Total Rs: 67266.82
Add for Air and Water line @ 1.00% Rs: 672.67
Add for Ventilation @ 4.50% Rs: 3027.01
Add for Lighting @ 1.60% Rs: 1076.27
Add for Ele sub-station / Demand charges @ 2.50% Rs: 1681.67
Total Rs: 73724.44
D.Add for contractor's profit and overheads on (A+B+C+other
percentages) 13.615% Rs: 10037.58
Total cost for 46.00 cum Rs: 83762.02
Rate per cum (A+B+C+D)/46.0 Rs: 1820.90
IRR-TAW-1-5 Excavation for tunnel by heading and benching tunnelling methods including excavation
for supports in all types of soil / rock strata requiring supports ( excluding cost of providing
supports ) for roof before benching including cost of all other materials, machinery, labour,
scaling excavated surface, ventilation, lighting, drainage removing and hauling excavated muck
outside tunnel upto specified dump area and all other ancillary operations etc., complete with
initial lead upto 1 km and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Drilling jumbo Hour 12.00 368.40 4420.80
Fuel / Energy charges Hour 12.00 42.80 513.60
2 Air compressor 15 cmm ( ele ) Hour 6.50 138.80 902.20
Fuel / Energy charges Hour 6.50 700.50 4553.25
3 Jack hammer ( 4 x 6.5 hrs ) Hour 26.00 19.80 514.80
Fuel / Energy charges Hour 26.00 0.00 0.00
4 Pusher leg Hour 26.00 12.70 330.20
Fuel / Energy charges Hour 26.00 0.00 0.00
5 Convey mucker Hour 6.50 822.80 5348.20
Fuel / Energy charges Hour 6.50 195.00 1267.50
6 Dumper ( 2 x 6.5 hrs ) Hour 13.00 580.70 7549.10
Fuel / Energy charges Hour 13.00 399.90 5198.70
7 Pump 10 hp ( ele ) Hour 6.50 6.70 43.55
Fuel / Energy charges Hour 6.50 56.00 364.00
8 Ventilation fans 20 hp Hour 3.00 11.50 34.50
106
Tunnel and Allied Works - Item Unit Rates 2016-17
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Drilling jumbo Hour 12.00 175.80 2109.60
2 Crew for Air compressor Hour 6.50 175.80 1142.70
3 Crew for Jack hammer Hour 26.00 329.60 8569.60
4 Crew for Convey mucker Hour 6.50 175.80 1142.70
5 Crew for Dumper Hour 13.00 227.10 2952.30
6 Crew for Pump Hour 6.50 83.30 541.45
7 Crew for Ventilation fan Hour 3.00 28.70 86.10
8 Surveyor Day 0.50 645.00 322.50
9 Foreman Day 1.00 510.00 510.00
10 Fitter / Mechanic Day 2.00 475.00 950.00
11 Blaster ( Licensed ) Day 2.00 510.00 1020.00
12 Helper blasting Day 4.00 400.00 1600.00
13 Hammerman 2 Nos Day 2.00 400.00 800.00
14 work inspector 1 in each shift Day 3.00 450.00 1350.00
15 Khalasi
for pushing muck in heading portion Day 4.00 445.00 1780.00
for mucking shift 4 Nos Day 4.00 445.00 1780.00
16 mazdoor
for mucking shift 8 Nos Day 8.00 350.00 2800.00
for other 2 shifts 1 No each shift Day 2.00 350.00 700.00
for cleaning &miscellaneous Day 2.00 350.00 700.00
Total cost of Labour Rs: 30856.95
labour component/unit qty 617.10
Add contractor's profit and overhead charges 13.615% 84.00
labour component/unit qty (including contractor's profit) 701.10
ABSTRACT:
A. Cost of Materials Rs: 12881.06
B. Hire charges of Machinery Rs: 31436.70
C. Cost of Labour Rs: 30856.95
Total Rs: 75174.71
Add for Air and Water line @ 1.00% Rs: 751.75
Add for Ventilation @ 4.50% Rs: 3382.86
Add for Lighting @ 1.60% Rs: 1202.80
Add for Ele sub-station / Demand charges @ 2.50% Rs: 1879.37
Total Rs: 82391.49
D.Add for contractor's profit and overheads on (A+B+C+other
percentages) 13.615% Rs: 11217.60
Total cost for 50.00 cum Rs: 93609.09
Rate per cum (A+B+C+D)/50.0 Rs: 1872.20
NOTE: Where mucking is to be carried out through shaft using winch and mucking tub system
increase the basic rates for items IRR-TAW-1-3, IRR-TAW-1-4 & IRR-TAW-1-5 by 8 percent.
IRR-TAW-1-6 Removing and hauling muck overfallen due to natural causes such as geological faults
etc., out of tunnel including breaking large fragments by blasting if necessary and disposing off
the same in specified dump area or as directed including cost of all materials, machinery,
labour, ventilation, drainage, lighting and all other ancillary operations etc., complete with
initial lead upto 1 km and all lifts.
107
Tunnel and Allied Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Air compressor 15 cmm ( ele ) Hour 1.00 138.80 138.80
Fuel / Energy charges Hour 1.00 700.50 700.50
2 Jack hammer Hour 4.00 19.80 79.20
Fuel / Energy charges Hour 4.00 0.00 0.00
3 Pump 10 hp ( ele ) Hour 1.00 6.70 6.70
Fuel / Energy charges Hour 1.00 56.00 56.00
4 Convey mucker Hour 6.00 822.80 4936.80
Fuel / Energy charges Hour 6.00 195.00 1170.00
5 Dumper 4.5 cum Hour 12.00 580.70 6968.40
Fuel / Energy charges Hour 12.00 399.90 4798.80
6 Sundries LS 1.00 30.00 30.00
Total hire charges of Machinery Rs: 18885.20
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Air compressor Hour 1.00 175.80 175.80
2 Crew for Jack hammer Hour 4.00 329.60 1318.40
3 Crew for Pump Hour 1.00 83.30 83.30
4 Crew for Convey mucker Hour 6.00 175.80 1054.80
5 Crew for Dumper Hour 12.00 227.10 2725.20
6 Blaster ( Licensed ) Day 0.50 510.00 255.00
7 Helper blasting Day 0.50 400.00 200.00
8 mazdoor Day 8.00 350.00 2800.00
Total cost of Labour Rs: 8612.50
labour component/unit qty 86.10
Add contractor's profit and overhead charges 13.615% 11.70
labour component/unit qty (including contractor's profit) 97.80
ABSTRACT:
A. Cost of Materials Rs: 1589.33
B. Hire charges of Machinery Rs: 18885.20
C. Cost of Labour Rs: 8612.50
Total Rs: 29087.03
Add for Air and Water line @ 1.00% Rs: 290.87
Add for Ventilation @ 4.50% Rs: 1308.92
Add for Lighting @ 1.60% Rs: 465.39
Add for Ele sub-station / Demand charges @ 2.50% Rs: 727.18
Total Rs: 31879.38
D.Add for contractor's profit and overheads on (A+B+C+other
percentages) 13.615% Rs: 4340.38
Total cost for 100.00 cum Rs: 36219.76
Rate per cum (A+B+C+D)/100.0 Rs: 362.20
IRR-TAW-2-1 Dewatering tunnel by pumping out water collected by natural drainage inside tunnel including
providing sump wherever necessary, cost of all materials, machinery, labour, drainage, lighting,
ventilation and all other ancillary operations etc., complete.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Electric pump 20 hp Hour 1.00 12.30 12.30
2 Fuel / Energy charges Hour 1.00 112.10 112.10
3 Sundries(Starter/Switches ete) LS 0.10 30.00 3.00
108
Tunnel and Allied Works - Item Unit Rates 2016-17
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew charges for Pump Hour 1.00 83.30 83.30
2 Laying & dismantling pipe LS 0.05 30.00 1.50
3 mazdoor Day 0.10 350.00 35.00
Total cost of Labour Rs: 119.80
labour component/unit qty 8.00
Add contractor's profit and overhead charges 13.615% 1.10
labour component/unit qty (including contractor's profit) 9.10
ABSTRACT:
A. Cost of Materials Rs: 7.67
B. Hire charges of Machinery Rs: 127.40
C. Cost of Labour Rs: 119.80
Total Rs: 254.87
Add for Air and Water line @ 1.00% Rs: 2.55
Add for Ventilation @ 4.50% Rs: 11.47
Add for Lighting @ 1.60% Rs: 4.08
Add for Ele sub-station / Demand charges @ 2.50% Rs: 6.37
Total Rs: 279.33
D.Add for contractor's profit and overheads on (A+B+C+other
percentages) 13.615% Rs: 38.03
Total cost for 15.00 Kwhr Rs: 317.36
Rate per Kwhr (A+B+C+D)/15.0 Rs: 21.20
IRR-TAW-2-2 Providing 25 mm thick guniting to sides and arch of tunnel in cement mortar 1 : 3 proportion
by weight including cost of all materials, machinery, labour, ventilation, lighting, drainage
and all other ancillary operations etc., complete with lead upto 1 km and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Guniting equipment Hour 8.00 110.10 880.80
Fuel / Energy charges Hour 8.00 0.00 0.00
2 Air compressor 8.5 cmm ( ele ) Hour 8.00 170.80 1366.40
Fuel / Energy charges Hour 8.00 315.20 2521.60
3 Pump 10 hp ( ele ) Hour 1.00 6.70 6.70
Fuel / Energy charges Hour 1.00 56.00 56.00
4 Drilling jumbo Hour 4.00 368.40 1473.60
Fuel / Energy charges Hour 4.00 42.80 171.20
5 Sundries LS 2.00 30.00 60.00
Total hire charges of Machinery Rs: 6536.30
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Guniting equipment Hour 8.00 219.70 1757.60
2 Crew for Air compressor Hour 8.00 164.80 1318.40
3 Crew for pump Hour 1.00 83.30 83.30
4 Crew for Drilling jumbo Hour 4.00 175.80 703.20
5 Mason Cl I Day 1.00 445.00 445.00
6 mazdoor Day 6.00 350.00 2100.00
Total cost of Labour Rs: 6407.50
109
Tunnel and Allied Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 3572.00
B. Hire charges of Machinery Rs: 6536.30
C. Cost of Labour Rs: 6407.50
Total Rs: 16515.80
Add for Air and Water line @ 1.00% Rs: 165.16
Add for Ventilation @ 4.50% Rs: 743.21
Add for Lighting @ 1.60% Rs: 264.25
Add for Ele sub-station / Demand charges @ 2.50% Rs: 412.90
Total Rs: 18101.32
D.Add for contractor's profit and overheads on (A+B+C+other
percentages) 13.615% Rs: 2464.49
Lead Charges for 1 Km for FA 1.10 cum @ 31.5 Rs./Cum 34.65
Total cost for 36.00 sqm Rs: 20600.46
Rate per sqm (A+B+C+D)/36.0 Rs: 572.20
IRR-TAW-2-3 Shortcreting in two layers (each layer+38 mm thickness) for slabs duly fixing chain weld wire mesh
(new4 - 2011-
12) 100 x 100x5 mm in between the two layers including cost and conveyance of all materials,
labour charges, all heads, lifts, centering, scaffolding, machine mixing,
laying concrete with shortcrete machine etc. complete as per specification and as
directed by Engineer-in-Charge
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Guniting equipment Hour 8.00 110.10 880.80
Fuel / Energy charges Hour 8.00 0.00 0.00
2 Air compressor 8.5 cmm ( ele ) Hour 8.00 170.80 1366.40
Fuel / Energy charges Hour 8.00 315.20 2521.60
3 Pump 10 hp ( ele ) Hour 1.00 6.70 6.70
Fuel / Energy charges Hour 1.00 56.00 56.00
4 Drilling jumbo Hour 4.00 368.40 1473.60
Fuel / Energy charges Hour 4.00 42.80 171.20
5 Sundries LS 2.00 30.00 60.00
Total hire charges of Machinery Rs: 6536.30
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Guniting equipment Hour 8.00 219.70 1757.60
2 Crew for Air compressor Hour 8.00 164.80 1318.40
3 Crew for pump Hour 1.00 83.30 83.30
4 Crew for Drilling jumbo Hour 4.00 175.80 703.20
5 Mason Cl I Day 1.00 445.00 445.00
6 mazdoor Day 6.00 350.00 2100.00
Total cost of Labour Rs: 6407.50
labour component/unit qty 178.00
Add contractor's profit and overhead charges 13.615% 24.20
labour component/unit qty (including contractor's profit) 202.20
ABSTRACT:
110
Tunnel and Allied Works - Item Unit Rates 2016-17
IRR-TAW-3-1 Providing and fixing 25 mm diameter steel rock bolts with mechanical / wedge type
anchorage including drilling 35 mm dia holes, providing 15 cm long 20 mm thick steel tapered
wedge, 10 mm thick plate washers and nuts, tightening bolt by torque wrench, cost of all
materials, machinery, labour, ventilation, lighting, drainage and all other ancillary operations
etc., complete with lead upto 1 km and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Air compressor 15 cmm ( ele ) Hour 1.50 138.80 208.20
Fuel / Energy charges Hour 1.50 700.50 1050.75
2 Pump 10 hp ( ele ) Hour 1.00 6.70 6.70
Fuel / Energy charges Hour 1.00 56.00 56.00
3 Jack hammer Hour 6.00 19.80 118.80
Fuel / Energy charges Hour 6.00 0.00 0.00
4 Pusher leg Hour 6.00 12.70 76.20
Fuel / Energy charges Hour 6.00 0.00 0.00
5 Drilling jumbo Hour 4.00 368.40 1473.60
Fuel / Energy charges Hour 4.00 42.80 171.20
6 Sundries ( lathe, blower etc ) LS 5.00 30.00 150.00
Total hire charges of Machinery Rs: 3311.45
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Air compressor Hour 1.50 175.80 263.70
2 Crew for pump Hour 1.00 83.30 83.30
3 Crew for Jack hammer Hour 6.00 329.60 1977.60
4 Crew for Drilling jumbo Hour 4.00 175.80 703.20
5 Fitter Day 0.50 475.00 237.50
6 Gas cutter Day 1.00 445.00 445.00
7 Turner Day 1.00 510.00 510.00
8 Blacksmith Day 1.00 445.00 445.00
9 Khalasi ( 2 x 0.5 ) Day 1.00 445.00 445.00
10 Hammerman Day 0.50 400.00 200.00
11 mazdoor Day 2.00 350.00 700.00
111
Tunnel and Allied Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 7109.05
B. Hire charges of Machinery Rs: 3311.45
C. Cost of Labour Rs: 6010.30
Total Rs: 16430.80
Add for Air and Water line @ 1.00% Rs: 164.31
Add for Ventilation @ 4.50% Rs: 739.39
Add for Lighting @ 1.60% Rs: 262.89
Add for Ele sub-station / Demand charges @ 2.50% Rs: 410.77
Total Rs: 18008.16
D.Add for contractor's profit and overheads on (A+B+C+other
percentages) 13.615% Rs: 2451.81
Lead Charges for 1Km for Steel (including
Loading and Unloading Charges) 0.16 tonne @ 168.6 Rs./Tonne 26.81340638
Total cost for 20.00 Rm Rs: 20486.79
Rate per Rm (A+B+C+D)/20.0 Rs: 1024.30
IRR-TAW-3-2 Providing and fixing 25 mm diameter steel rock bolts with resin bond cement capsule
anchorage including drilling 35 mm dia holes, inserting grout capsule, driving bolt,fixing 10 mm
thick plate washers and nuts and tightening the same by torque wrench after hardening of
cement grout, cost of all materials, machinery, labour, ventilation, lighting, drainage and other
ancillary operations etc., complete with lead upto 1 km and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Air compressor 15 cmm ( ele ) Hour 1.50 138.80 208.20
Fuel / Energy charges Hour 1.50 700.50 1050.75
2 Pump 10 hp ( ele ) Hour 1.00 6.70 6.70
Fuel / Energy charges Hour 1.00 56.00 56.00
3 Jack hammer Hour 6.00 19.80 118.80
Fuel / Energy charges Hour 6.00 0.00 0.00
4 Pusher leg Hour 6.00 12.70 76.20
Fuel / Energy charges Hour 6.00 0.00 0.00
5 Drilling jumbo Hour 4.00 368.40 1473.60
Fuel / Energy charges Hour 4.00 42.80 171.20
6 Sundries ( lathe, etc ) LS 3.00 30.00 90.00
Total hire charges of Machinery Rs: 3251.45
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Air compressor Hour 1.50 175.80 263.70
2 Crew for pump Hour 1.00 83.30 83.30
3 Crew for Jack hammer Hour 6.00 329.60 1977.60
4 Crew for Drilling jumbo Hour 4.00 175.80 703.20
5 Fitter Day 0.50 400.00 200.00
6 Gas cutter Day 1.00 445.00 445.00
112
Tunnel and Allied Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 6892.65
B. Hire charges of Machinery Rs: 3251.45
C. Cost of Labour Rs: 5527.80
Total Rs: 15671.90
Add for Air and Water line @ 1.00% Rs: 156.72
Add for Ventilation @ 4.50% Rs: 705.24
Add for Lighting @ 1.60% Rs: 250.75
Add for Ele sub-station / Demand charges @ 2.50% Rs: 391.80
Total Rs: 17176.40
D.Add for contractor's profit and overheads on (A+B+C+other
percentages) 13.615% Rs: 2338.57
Lead Charges for 1Km for Steel (including
Loading and Unloading Charges) 0.15 tonne @ 168.6 Rs./Tonne 25.77114225
Total cost for 20.00 Rm Rs: 19540.74
Rate per Rm (A+B+C+D)/20.0 Rs: 977.00
IRR-TAW-3-3 Providing, fabricating and fixing in position permanent structural steel supports as per details
including cost of all materials, machinery, labour, cutting, bending, welding, grinding, lighting,
ventilation, drainage and all other ancillary operations etc., complete with initial lead upto
1 km and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Bending machine Hour 8.00 42.60 340.80
Fuel / Energy charges Hour 8.00 84.10 672.80
2 Welding set Hour 16.00 16.00 256.00
Fuel / Energy charges Hour 16.00 67.20 1075.20
3 Drilling Jumbo Hour 12.00 368.40 4420.80
Fuel / Energy charges Hour 12.00 42.80 513.60
4 Sundries ( lathe / drilling / grinder ) LS 30.00 30.00 900.00
Total hire charges of Machinery Rs: 8179.20
113
Tunnel and Allied Works - Item Unit Rates 2016-17
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Drilling Jumbo Hour 12.00 175.80 2109.60
2 Crew fir Bending machine Hour 8.00 131.80 1054.40
3 For cutting & preparing sections:
Structural steel Marker Day 1.00 550.00 550.00
Gas cutter Day 2.00 445.00 890.00
Fitter Day 2.00 475.00 950.00
Turner / Driller Day 3.00 510.00 1530.00
Khalasi Day 2.00 445.00 890.00
Helper fabrication Day 4.00 400.00 1600.00
4 For welding sections:
Welder Day 2.00 445.00 890.00
Helper fabrication Day 2.00 400.00 800.00
Khalasi Day 2.00 445.00 890.00
5 For erection of supports:
Foreman Day 1.00 510.00 510.00
Structural steel Erector Day 2.00 550.00 1100.00
Helper erector Day 2.00 400.00 800.00
Khalasi Day 4.00 445.00 1780.00
Total cost of Labour Rs: 16344.00
labour component/unit qty 16344.00
Add contractor's profit and overhead charges 13.615% 2225.20
labour component/unit qty (including contractor's profit) 18569.20
ABSTRACT:
A. Cost of Materials Rs: 44044.80
B. Hire charges of Machinery Rs: 8179.20
C. Cost of Labour Rs: 16344.00
Total Rs: 68568.00
Add for Air and Water line @ 1.00% Rs: 685.68
Add for Ventilation @ 4.50% Rs: 3085.56
Add for Lighting @ 1.60% Rs: 1097.09
Add for Ele sub-station / Demand charges @ 2.50% Rs: 1714.20
Total Rs: 75150.53
D.Add for contractor's profit and overheads on (A+B+C+other
percentages) 13.615% Rs: 10231.74
Lead Charges for 1Km for Steel (including
Loading and Unloading Charges) 1.03 tonne @ 168.6 Rs./Tonne 172.815
IRR-TAW-3-4 Providing, fabricating and fixing in position temperary structural steel supports as per details
and dismantling the same before concreting including cost of all materials, machinery, labour,
cutting, bending, welding, grinding, ventilation, lighting, drainage and all other ancillary
operations etc.,complete with initial lead upto 1 km and all lifts.
114
Tunnel and Allied Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 2224.74
B. Hire charges of Machinery for fabrication Rs: 162.24
C. Hire charges of Machinery for erection and dismantling Rs: 7701.60
D. Cost of Labour for fabrication Rs: 502.22
E. Cost of Labour for erection and dismantling Rs: 7691.40
Total Rs: 18282.20
Add for Air and Water line @ 1.00% Rs: 182.82
Add for Ventilation @ 4.50% Rs: 822.70
Add for Lighting @ 1.60% Rs: 292.52
Add for Ele sub-station / Demand charges @ 2.50% Rs: 457.06
Total Rs: 20037.29
D.Add for contractor's profit and overheads on (A+B+C+other
percentages) 13.615% Rs: 2728.08
115
Tunnel and Allied Works - Item Unit Rates 2016-17
IRR-TAW-3-5 Providing and fixing hard variety cut jungle wood for lagging / blocking locations in tunnel
wherever required including cost of all materials, machinery, labour, fixing in position, lighting,
ventilation, drainage etc complete with all leads and lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Drilling jumbo Hour 2.00 368.40 736.80
Fuel / Energy charges Hour 2.00 42.80 85.60
Total hire charges of Machinery Rs: 822.40
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Drilling jumbo Hour 2.00 175.80 351.60
2 Carpenter Cl II Day 1.00 400.00 400.00
3 mazdoor Day 2.00 350.00 700.00
Total cost of Labour Rs: 1451.60
labour component/unit qty 1451.60
Add contractor's profit and overhead charges 13.615% 197.60
labour component/unit qty (including contractor's profit) 1649.20
ABSTRACT:
A. Cost of Materials Rs: 24210.00
B. Hire charges of Machinery Rs: 822.40
C. Cost of Labour Rs: 1451.60
Total Rs: 26484.00
Add for Air and Water line @ 1.00% Rs: 264.84
Add for Ventilation @ 4.50% Rs: 1191.78
Add for Lighting @ 1.60% Rs: 423.74
Add for Ele sub-station / Demand charges @ 2.50% Rs: 662.10
Total Rs: 29026.46
D.Add for contractor's profit and overheads on (A+B+C+other
percentages) 13.615% Rs: 3951.95
Total cost for 1.00 cum Rs: 32978.42
Rate per cum (A+B+C+D)/1.0 Rs: 32978.40
IRR-TAW-4-1 Providing and constructing un-coursed rubble stone masonry with approved stones from
tunnel excavated muck in cement mortar 1 : 6 proportion for backfilling over cuts / slips on
tunnel sides due to geological faults etc., including cost of all materials, machinery, labour,
cleaning,scaffolding, packing mortar, wedging stone chips, curing, ventilation, lighting, drainage
complete with lead upto 1 km and all lifts.
(cement content : 95 kg/cum of masonry, Rubble stones : 0.83 cum, Stone chips : 0.13 cum,
FA : 0.40 cum)
116
Tunnel and Allied Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 10 hp pump ( ele ) Hour 1.00 6.70 6.70
Fuel / energy charges Hour 1.00 56.00 56.00
Total hire charges of Machinery Rs: 62.70
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Pump Hour 1.00 83.30 83.30
2 work inspector Day 1.00 450.00 450.00
3 Mason Class-I Day 1.00 445.00 445.00
4 Mason Class-II Day 2.00 400.00 800.00
5 mazdoor
for sorting out rubble in dump yard Day 1.00 350.00 350.00
for conveying rubble Day 2.00 350.00 700.00
for preparing mortar Day 2.00 350.00 700.00
for loading mortar pans Day 1.00 350.00 350.00
for laying & packing mortar Day 4.00 350.00 1400.00
for washing rubble / finishing / curing Day 1.00 350.00 350.00
for conveying mortar / chips Day 3.00 350.00 1050.00
TOTAL Rs: 6678.30
Add for labour for scaffolding @ 15.0% Rs: 1001.75
Total cost of Labour Rs: 7680.05
labour component/unit qty 768.00
Add contractor's profit and overhead charges 13.615% 104.60
labour component/unit qty (including contractor's profit) 872.60
ABSTRACT:
A. Cost of Materials Rs: 9039.89
B. Hire charges of Machinery Rs: 62.70
C. Cost of Labour Rs: 7680.05
Total Rs: 16782.63
Add for Air and Water line @ 1.00% Rs: 167.83
Add for Ventilation @ 4.50% Rs: 755.22
Add for Lighting @ 1.60% Rs: 268.52
Add for Ele sub-station / Demand charges @ 2.50% Rs: 419.57
Total Rs: 18393.76
D.Add for contractor's profit and overheads on (A+B+C+other
percentages) 13.615% Rs: 2504.31
Lead Charges for 1 Km for FA 4.00 cum @ 31.5 Rs./Cum 126
Lead Charges for 1 Km for Stones and Stone Chips9.55 cum @ 30.4 Rs./Cum 290.32
Total cost for 10.00 cum Rs: 21314.39
Rate per cum (A+B+C+D)/10.0 Rs: 2131.40
IRR-TAW-5-1 Providing, fabricating and placing in position reinforcement steel for tunnel RCC works
including cleaning, straightening, cutting, bending, hooking, lapping / welding joints wherever
required, tying with 1.25 mm dia.soft annealed steel wire, including cost of all materials, labour,
machinery, ventilation, lighting, drainage etc.,complete with initial lead upto 1 km and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
117
Tunnel and Allied Works - Item Unit Rates 2016-17
in Rs. in Rs.
1 Nil 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Bar bender Day 9.00 555.00 4995.00
2 mazdoor Day 15.00 350.00 5250.00
Total cost of Labour Rs: 10245.00
labour component/unit qty 10245.00
Add contractor's profit and overhead charges 13.615% 1394.90
labour component/unit qty (including contractor's profit) 11639.90
ABSTRACT:
A. Cost of Materials Rs: 36660.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 10245.00
Total Rs: 46905.00
Add for Air and Water line @ 1.00% Rs: 469.05
Add for Ventilation @ 4.50% Rs: 2110.73
Add for Lighting @ 1.60% Rs: 750.48
Add for Ele sub-station / Demand charges @ 2.50% Rs: 1172.63
Total Rs: 51407.88
D.Add for contractor's profit and overheads on (A+B+C+other
percentages) 13.615% Rs: 6999.18
Lead Charges for 1Km for Steel (including
Loading and Unloading Charges) 1.05 tonne @ 168.6 Rs./Tonne 177.03
Total cost for 1.00 tonne Rs: 58584.09
Rate per tonne (A+B+C+D)/1.0 Rs: 58584.10
IRR-TAW-5-2 Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than
10 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard,
graded aggregates crushed from tunnel excavated muck for filling and levelling over-cuts
in bed due to geological faults etc., including cost of all materials, machinery, labour, cleaning
bed, batching, mixing, conveying and laying, levelling, compacting, finishing, curing, lighting,
ventilation, drainage etc., complete with initial lead upto 1 km and all lifts. ( Cement
content : 220 kg / cum, CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum,
Superplasticizer 0.4% by wt. of cement)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Batching plant 2 x 1 cum Hour 8.00 405.40 3243.20
Fuel / Energy charges Hour 8.00 252.20 2017.60
2 Agitator car 2 cum Hour 16.00 758.40 12134.40
Fuel / Energy charges Hour 16.00 872.70 13963.20
3 10 hp pump ( ele ) Hour 8.00 6.70 53.60
Fuel / Energy charges Hour 8.00 56.00 448.00
4 Needle vibrator 40 mm dia Hour 8.00 8.00 64.00
Fuel / Energy charges Hour 8.00 5.60 44.80
5 Sundries LS 2.00 30.00 60.00
Total hire charges of Machinery Rs: 32028.80
C. LABOUR:
118
Tunnel and Allied Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 64037.20
B. Hire charges of Machinery Rs: 32028.80
C. Cost of Labour Rs: 21294.20
Total Rs: 117360.20
Add for Air and Water line @ 1.00% Rs: 1173.60
Add for Ventilation @ 4.50% Rs: 5281.21
Add for Lighting @ 1.60% Rs: 1877.76
Add for Ele sub-station / Demand charges @ 2.50% Rs: 2934.01
Total Rs: 128626.78
D.Add for contractor's profit and overheads on (A+B+C+other
percentages) 13.615% Rs: 17512.54
Lead Charges for 1 Km for FA 11.20 cum @ 31.5 Rs./Cum 352.8
Lead Charges for 1 Km for CA 25.20 cum @ 30.4 Rs./Cum 766.08
Total cost for 28.00 cum Rs: 147258.20
Rate per cum (A+B+C+D)/28.0 Rs: 5259.20
IRR-TAW-5-3 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sqmm ) grade cement concrete using 40 mm and down size approved clean, hard,
graded aggregates crushed from tunnel muck for kerb and bed lining including cost of all
materials, machinery, labour, formwork, batching, mixing, conveying upto placing point in
agitator cars, placing in position, levelling, vibrating, finishing, curing, ventilation, lighting,
drainage and all other ancillary operations etc., complete with lead upto 1 km and all lifts.
( Cement content 330 kg / cum for use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Batching plant 2 x 1.00 cum Hour 8.00 405.40 3243.20
Fuel / Energy charges Hour 8.00 252.20 2017.60
119
Tunnel and Allied Works - Item Unit Rates 2016-17
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Batching plant Hour 8.00 340.60 2724.80
2 Crew for Agitator car Hour 16.00 283.90 4542.40
3 Crew for vibrator Hour 8.00 158.20 1265.60
4 Crew for pump Hour 8.00 83.30 666.40
5 For scaling & cleaning bed
Hammerman Day 2.00 400.00 800.00
mazdoor Day 6.00 350.00 2100.00
6 For loading cement to BP bin
mazdoor Day 3.00 350.00 1050.00
7 For miscellaneous work at BP
mazdoor Day 2.00 350.00 700.00
8 For wetting C.A & curing
mazdoor Day 2.00 350.00 700.00
9 Laying concrete for kerb/ invert
Mason Cl I Day 2.00 445.00 890.00
Mason Cl II Day 2.00 400.00 800.00
mazdoor Day 21.00 350.00 7350.00
work inspector Day 1.00 450.00 450.00
10 Labour charges for shuttering sqm 28.00 88.50 2478.00
Total cost of Labour Rs: 26517.20
labour component/unit qty 947.00
Add contractor's profit and overhead charges 13.615% 128.90
labour component/unit qty (including contractor's profit) 1075.90
ABSTRACT:
A. Cost of Materials Rs: 85558.49
B. Hire charges of Machinery Rs: 32118.80
C. Cost of Labour Rs: 26517.20
Total Rs: 144194.49
Add for Air and Water line @ 1.00% Rs: 1441.94
Add for Ventilation @ 4.50% Rs: 6488.75
Add for Lighting @ 1.60% Rs: 2307.11
Add for Ele sub-station / Demand charges @ 2.50% Rs: 3604.86
Total Rs: 158037.16
D.Add for contractor's profit and overheads on (A+B+C+other
percentages) 13.615% Rs: 21516.76
Lead Charges for 1 Km for FA 11.20 cum @ 31.5 Rs./Cum 352.8
Lead Charges for 1 Km for CA 25.20 cum @ 30.4 Rs./Cum 766.08
Total cost for 28.00 cum Rs: 180672.80
Rate per cum (A+B+C+D)/28.0 Rs: 6452.60
IRR-TAW-5-4 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sqmm ) grade cement concrete using 40 mm and down size approved clean, hard,
graded aggregates crushed from tunnel muck for sides and arch lining including cost of all
materials, machinery, labour, formwork, batching, mixing, conveying upto placing point in
agitator cars, placing in position, levelling, vibrating, finishing, curing, ventilation, lighting,
drainage and all other ancillary operations etc., complete with lead upto 1 km and all lifts.
( Cement content 330 kg / cum for use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
120
Tunnel and Allied Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Air compressor ( Ele ) 8.5 cmm Hour 16.00 170.80 2732.80
Fuel / Energy charges @ 75 % load Hour 12.00 315.20 3782.40
2 Batching plant 2 x 1.00 cum Hour 12.00 405.40 4864.80
Fuel / Energy charges Hour 12.00 252.20 3026.40
3 Agitator car 2 cum ( 2 Nos ) Hour 32.00 758.40 24268.80
Fuel / Energy charges Hour 32.00 872.70 27926.40
4 Concrete placer pump Hour 16.00 1004.30 16068.80
Fuel / Energy charges Hour 16.00 336.20 5379.20
5 Needle Vibrator / Shutter vibrator Hour 8.00 8.00 64.00
Fuel / Energy charges Hour 8.00 5.60 44.80
6 Pump 10 hp ( Ele ) Hour 8.00 6.70 53.60
Fuel / Energy charges Hour 8.00 56.00 448.00
7 Sundries LS 5.00 30.00 150.00
Total hire charges of Machinery Rs: 88810.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew charges for Air compressor Hour 16.00 164.80 2636.80
2 Crew charges for Batching plant Hour 16.00 340.60 5449.60
3 Crew charges for Agitator car Hour 32.00 283.90 9084.80
4 Crew charges for placer pump Hour 16.00 164.80 2636.80
5 Crew charges for vibrator Hour 8.00 158.20 1265.60
6 Crew charges for Pump Hour 8.00 83.30 666.40
7 For scaling & cleaning
Stone chiseller Cl II Day 0.50 400.00 200.00
mazdoor Day 1.00 350.00 350.00
8 For dismantling / Laying track
Surveyer Day 0.50 645.00 322.50
Fitter shuttering Day 0.50 400.00 200.00
Helper shuttering 2 x 0.5 Day 1.00 400.00 400.00
Khalasi 6 x 0.5 Day 3.00 445.00 1335.00
mazdoor 2 x 0.5 Day 1.00 350.00 350.00
9 For Moving / Positioning gantry
Surveyer Day 0.50 645.00 322.50
Foreman Day 0.50 510.00 255.00
Fitter shuttering Day 0.50 400.00 200.00
Helper shuttering 2 x 0.5 Day 1.00 400.00 400.00
Khalasi 6 x 0.5 Day 3.00 445.00 1335.00
mazdoor 2 x 0.5 Day 1.00 350.00 350.00
10 For loading cement to BP bin
mazdoor Day 5.00 350.00 1750.00
11 For miscellaneous works of BP
mazdoor Day 2.00 350.00 700.00
12 For Erection/Dismantling bulk head sqm 6.00 88.50 531.00
13 For Laying concrete by placer
Masom Cl I Day 3.00 445.00 1335.00
121
Tunnel and Allied Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 149245.01
B. Hire charges of Machinery Rs: 88810.00
C. Cost of Labour Rs: 37626.00
Total Rs: 275681.01
Add for Air and Water line @ 1.00% Rs: 2756.81
Add for Ventilation @ 4.50% Rs: 12405.65
Add for Lighting @ 1.60% Rs: 4410.90
Add for Ele sub-station / Demand charges @ 2.50% Rs: 6892.03
Total Rs: 302146.38
D.Add for contractor's profit and overheads on (A+B+C+other
percentages) 13.615% Rs: 41137.23
Lead Charges for 1 Km for FA 19.20 cum @ 31.5 Rs./Cum 604.8
Lead Charges for 1 Km for CA 43.20 cum @ 30.4 Rs./Cum 1313.28
Total cost for 48.00 cum Rs: 345201.69
Rate per cum (A+B+C+D)/48.0 Rs: 7191.70
IRR-TAW-6-1 Drilling 32 mm diameter grout holes in concrete / rock by percussion drilling using jack
hammer or stooper drills as directed to specified depth for consolidation / contact grouting
including cost of all materials, machinery, labour, cleaning holes, ventilation, lighting, drainage
and all other ancillary operations etc., complete.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Air compressor 15 cmm ( ele ) Hour 8.00 138.80 1110.40
Fuel / Energy charges Hour 8.00 700.50 5604.00
2 Pump 10 hp ( ele ) Hour 4.00 6.70 26.80
Fuel / Energy charges Hour 4.00 56.00 224.00
3 Jack hammer Hour 32.00 19.80 633.60
Fuel / Energy charges Hour 32.00 0.00 0.00
4 Pusher leg Hour 32.00 12.70 406.40
Fuel / Energy charges Hour 32.00 0.00 0.00
5 Drilling jumbo Hour 8.00 368.40 2947.20
Fuel / Energy charges Hour 8.00 42.80 342.40
6 Sundries LS 5.00 30.00 150.00
Total hire charges of Machinery Rs: 11444.80
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew charges for Air compressor Hour 8.00 175.80 1406.40
2 Crew charges for Pump Hour 4.00 83.30 333.20
3 Crew charges for Jack Hammer Hour 32.00 329.60 10547.20
4 Crew charges for Drilling Jumbo Hour 8.00 175.80 1406.40
5 mazdoor Day 2.00 350.00 700.00
Total cost of Labour Rs: 14393.20
labour component/unit qty 143.90
122
Tunnel and Allied Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 5046.27
B. Hire charges of Machinery Rs: 11444.80
C. Cost of Labour Rs: 14393.20
Total Rs: 30884.27
Add for Air and Water line @ 1.00% Rs: 308.84
Add for Ventilation @ 4.50% Rs: 1389.79
Add for Lighting @ 1.60% Rs: 494.15
Add for Ele sub-station / Demand charges @ 2.50% Rs: 772.11
Total Rs: 33849.16
D.Add for contractor's profit and overheads on (A+B+C+other
percentages) 13.615% Rs: 4608.56
Total cost for 100.00 Rm Rs: 38457.72
Rate per Rm (A+B+C+D)/100.0 Rs: 384.60
IRR-TAW-6-2 Grouting cement slurry in grout holes under specified pressure for consolidation / contact
grouting including cost of all materials, machinery, labour, redrilling wherever necessary,
ventilation,lighting, drainage and other ancillary operations etc., complete with lead upto 1 km
and all lifts.
DATA:
RATE ANALYSIS UNIT : 1.50 tonne
A. MATERIALS:
Sl No Particulars Unit Quantity Rate Amount
in Rs. in Rs.
1 Cement tonne 1.50 5350.00 8025.00
2 Use rate of grouting hose 50 m Hour 8.00 11.56 92.50
3 Use rate of water hose 50 m Hour 8.00 11.56 92.50
4 Sundries LS 2.00 30.00 60.00
Total cost of Materials Rs: 8270.00
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Grouting machine Hour 8.00 24.90 199.20
Fuel / Energy charges Hour 8.00 28.00 224.00
2 Pump 10 hp ( ele ) Hour 2.00 6.70 13.40
Fuel / Energy charges Hour 2.00 56.00 112.00
3 Drilling jumbo Hour 2.00 368.40 736.80
Fuel / Energy charges Hour 2.00 42.80 85.60
4 Sundries LS 2.00 30.00 60.00
Total hire charges of Machinery Rs: 1431.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Grout pump Hour 8.00 263.60 2108.80
2 Crew for pump Hour 2.00 83.30 166.60
3 Crew for Drilling jumbo Hour 2.00 175.80 351.60
4 mazdoor Day 2.00 350.00 700.00
Total cost of Labour Rs: 3327.00
labour component/unit qty 2218.00
Add contractor's profit and overhead charges 13.615% 302.00
labour component/unit qty (including contractor's profit) 2520.00
ABSTRACT:
A. Cost of Materials Rs: 8270.00
B. Hire charges of Machinery Rs: 1431.00
C. Cost of Labour Rs: 3327.00
Total Rs: 13028.00
Add for Air and Water line @ 1.00% Rs: 130.28
Add for Ventilation @ 4.50% Rs: 586.26
Add for Lighting @ 1.60% Rs: 208.45
Add for Ele sub-station / Demand charges @ 2.50% Rs: 325.70
Total Rs: 14278.69
D.Add for contractor's profit and overheads on (A+B+C+other
percentages) 13.615% Rs: 1944.04
123
Tunnel and Allied Works - Item Unit Rates 2016-17
IRR-TAW-6-3 Drilling 75 mm diameter drainage holes vertical or inclined in rock / concrete in tunnel by
percussion drilling using waggon drill or other suitable drilling equipment including cost of all
materials, machinery, labour, ventilation, lighting, drainage etc., complete.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Waggon drill Hour 16.00 188.50 3016.00
Fuel / Energy charges Hour 16.00 0.00 0.00
2 Air compressor 15 cmm ( ele ) Hour 8.00 138.80 1110.40
Fuel / Energy charges Hour 8.00 700.50 5604.00
3 Pump 10 hp ( ele ) Hour 6.00 6.70 40.20
Fuel / Energy charges Hour 6.00 56.00 336.00
4 Sundries LS 2.00 30.00 60.00
Total hire charges of Machinery Rs: 10166.60
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Waggon drill Hour 16.00 283.90 4542.40
2 Crew for Air compressor Hour 8.00 175.80 1406.40
3 Crew for Pump Hour 6.00 83.30 499.80
4 mazdoor Day 2.00 350.00 700.00
Total cost of Labour Rs: 7148.60
labour component/unit qty 59.60
Add contractor's profit and overhead charges 13.615% 8.10
labour component/unit qty (including contractor's profit) 67.70
ABSTRACT:
A. Cost of Materials Rs: 16165.60
B. Hire charges of Machinery Rs: 10166.60
C. Cost of Labour Rs: 7148.60
Total Rs: 33480.80
Add for Air and Water line @ 1.00% Rs: 334.81
Add for Ventilation @ 4.50% Rs: 1506.64
Add for Lighting @ 1.60% Rs: 535.69
Add for Ele sub-station / Demand charges @ 2.50% Rs: 837.02
Total Rs: 36694.96
D.Add for contractor's profit and overheads on (A+B+C+other
percentages) 13.615% Rs: 4996.02
Total cost for 120.00 Rm Rs: 41690.98
Rate per Rm (A+B+C+D)/120.0 Rs: 347.40
124
Canal and Allied Works - Item Unit Rates 2016-17
Chapter III
3. The Leads for Steel shall be from the nearest market place to the Project area
4. For earth/rockfill embankments wherever initial lead of 1km is considered in the basic rate, the additional lead
charges are to be added as follows:
Additional lead charges for Earth, Murrum etc., shall be worked out for total lead involved and 1 km lead charges included
in basic rate shall be deducted from total lead charges. No loading and unloading charges shall be allowed for any item.
(same as above)
Example:
Total lead for earth from approved borrow area : 15 Km
Initial lead included in the basic rate in the SR : 1 Km
Additional lead charges : Lead charges for 5 km Rs. 84.00
Lead charges for next 10 km Rs. 126
Total lead charges for 15 km /cum Rs. 210.00
Less 1 km initial lead charges /cum Rs. 31.50 (-)
Net additional lead charges / cum Rs. 178.50
5. The initial lead up to 50 m as mentioned in some standard data items is meant for manual lead within the working area. For
conveyance of materials, the lead required from quarry/Borrow area/ Dump Area to worksite shall be added to the data without
deducting the 50 m initial lead charges
CAW-Work Items
IRR-CAW-1-1 Excavation in all kinds of soil including boulders upto 0.3 m diameter for canal, seating of
embankment, filter drains / catch water drains etc., including dressing bed and sides to
required level and profile, cost of all materials, machinery, labour, placing the excavated soil
neatly in dump area or for the formation of service road / embankment as directed etc.,
complete with initial lead upto 1 km and all lifts.
125
Canal and Allied Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Shovel 0.85 cum capacity Hour 8.00 1706.60 13652.80
Fuel / Energy charges Hour 8.00 872.70 6981.60
2 Tippers 5 cum capacity 6 Nos Hour 48.00 446.70 21441.60
Fuel / Energy charges Hour 48.00 299.90 14395.20
Total hire charges of Machinery Rs: 56471.20
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Shovel Hour 8.00 236.60 1892.80
2 Crew for Tipper Hour 48.00 177.50 8520.00
3 work inspector Day 1.00 450.00 450.00
4 mazdoor Day 30.00 350.00 10500.00
Total cost of Labour Rs: 21362.80
labour component/unit qty 23.10
Add contractor's profit and overhead charges 13.615% 3.10
labour component/unit qty (including contractor's profit) 26.20
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 56471.20
C. Cost of Labour Rs: 21362.80
Total Rs: 77834.00
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 10597.1
Total cost for 925.00 cum Rs: 88431.10
Rate per cum (A+B+C+D)/925 Rs. 95.60
IRR-CAW-1-2 Excavation in all kinds of soil including boulders upto 0.30 m dia for field channels, seating Excavation in all kinds of soil inc
of embankment for field channels etc., including dressing of bed and sides to required profile,
cost of all materials, machinery, labour, placing the excavated stuff for formation of service
road / embankment as directed etc., complete with lead upto 10 m and lift upto 3 m.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Shovel 0.50 cum capacity Hour 8.00 1003.10 8024.80
Fuel / Energy charges Hour 8.00 476.00 3808.00
Total hire charges of Machinery Rs: 11832.80
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Shovel Hour 8.00 236.60 1892.80
2 work inspector Day 1.00 450.00 450.00
3 mazdoor Day 17.00 350.00 5950.00
126
Canal and Allied Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 11832.80
C. Cost of Labour Rs: 8292.80
Total Rs: 20125.60
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 2740.1
Total cost for 440.00 cum Rs: 22865.70
Rate per cum (A+B+C+D)/440 Rs. 52.00
IRR-CAW-1-3 Excavation in ordinary rock (including HDR) without blasting including boulders above 0.30 m upto 0.6 m dia. for
canals, seating of embankment, filter drain / catch water drains etc., including dressing of
bed and sides to required level and profile, cost of all materials, machinery, labour, placing the
excavated soft rock neatly in dump area or for formation of service road as directed etc.,
complete with lead upto 1 km and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Shovel 0.85 cum capacity Hour 8.00 1706.60 13652.80
Fuel / Energy charges Hour 8.00 872.70 6981.60
2 Tippers 5 cum capacity 5 Nos Hour 40.00 446.70 17868.00
Fuel / Energy charges Hour 40.00 299.90 11996.00
Total hire charges of Machinery Rs: 50498.40
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Shovel Hour 8.00 236.60 1892.80
2 Crew for Tipper Hour 40.00 177.50 7100.00
3 work inspector Day 1.00 450.00 450.00
4 Crowbarman Day 11.00 400.00 4400.00
5 mazdoor Day 22.00 350.00 7700.00
Total cost of Labour Rs: 21542.80
labour component/unit qty 34.20
Add contractor's profit and overhead charges 13.615% 4.70
labour component/unit qty (including contractor's profit) 38.90
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 50498.40
C. Cost of Labour Rs: 21542.80
Total Rs: 72041.20
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 9808.41
Total cost for 630.00 cum Rs: 81849.61
Rate per cum (A+B+C+D)/630 Rs. 129.90
IRR-CAW-1-4 Excavation in ordinary rock (including HDR) without blasting including boulders above 0.3 m upto 0.60 m dia. for
field channels, seating of embankment for field channels etc., including dressing of bed and
sides to required profile, cost of all materials, machinery, labour, placing the excavated stuff
127
Canal and Allied Works - Item Unit Rates 2016-17
for formation of service road as directed etc.,complete with lead upto 10 m and lift upto 3 m.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Shovel 0.50 cum capacity Hour 8.00 1003.10 8024.80
Fuel / Energy charges Hour 8.00 476.00 3808.00
Total hire charges of Machinery Rs: 11832.80
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Shovel Hour 8.00 236.60 1892.80
2 work inspector Day 1.00 450.00 450.00
3 Crowbarman Day 5.00 400.00 2000.00
4 mazdoor Day 11.00 350.00 3850.00
Total cost of Labour Rs: 8192.80
labour component/unit qty 30.90
Add contractor's profit and overhead charges 13.615% 4.20
labour component/unit qty (including contractor's profit) 35.10
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 11832.80
C. Cost of Labour Rs: 8192.80
Total Rs: 20025.60
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 2726.49
Total cost for 265.00 cum Rs: 22752.09
Rate per cum (A+B+C+D)/265 Rs. 85.90
IRR-CAW-1-5 Excavation in hard rock (including F&F rock) requiring blasting including boulders
above 0.6 m upto 1.2 m dia. for canals, seating of embankment, filter drain / catch water drains
etc., including dressing bed and sides to required level and profile, cost of all materials,
machinery, labour, placing the excavated rock in dump area or for formation of service
road as directed etc., complete with lead upto 1 km and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Shovel 0.85 cum capacity Hour 8.00 1706.60 13652.80
128
Canal and Allied Works - Item Unit Rates 2016-17
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Shovel Hour 8.00 236.60 1892.80
2 Crew for Tipper Hour 40.00 177.50 7100.00
3 Crew for Air compressor Hour 12.00 210.90 2530.80
4 Crew for Jack hammer Hour 39.00 329.60 12854.40
5 work inspector Day 1.00 450.00 450.00
6 Blaster Day 1.00 510.00 510.00
7 Helper blaster Day 1.00 400.00 400.00
8 Crowbarman Day 16.00 400.00 6400.00
9 Stone breaker Day 16.00 400.00 6400.00
10 mazdoor Day 32.00 350.00 11200.00
Total cost of Labour Rs: 49738.00
labour component/unit qty 61.80
Add contractor's profit and overhead charges 13.615% 8.40
labour component/unit qty (including contractor's profit) 70.20
ABSTRACT:
A. Cost of Materials Rs: 25827.16
B. Hire charges of Machinery Rs: 65287.80
C. Cost of Labour Rs: 49738.00
Total Rs: 140852.96
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 19177.13
Total cost for 805.00 cum Rs: 160030.09
Rate per cum (A+B+C+D)/805 Rs. 198.80
IRR-CAW-1-6 Excavation in hard rock of all toughness by blasting including boulders above 1.2 m dia. for
(a) canals, seating of embankment, filter drain / catch water drains etc., including levelling the bed
by removing all projections by hammering / chiselling, cost of all materials, machinery, labour,
placing the excavated rock neatly in approved dump area and levelling the same as directed
etc., complete with initial lead upto 1 km and all lifts.
Note: i ) The rate under this item shall be adopted for canals designed for carrying capacity of less
than 15 cumecs or where the average depth of excavation in hard rock is less than 3 m.
ii ) The rate includes levelling canal bed by hammering / chiselling all rock projections wherever
required.
129
Canal and Allied Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Shovel 0.85 cum capacity Hour 1.10 1706.60 1877.26
Fuel / energy charges Hour 1.10 872.70 959.97
2 Angle dozer 90 hp Hour 0.25 1715.50 428.88
Fuel / Energy charges Hour 0.25 610.50 152.63
3 Tippers 5 cum capacity 4 Nos. Hour 4.40 446.70 1965.48
Fuel / Energy charges Hour 4.40 299.90 1319.56
Air compressor 8.5 cmm ( diesel ) 1
4 Nos Hour 6.50 275.60 1791.40
Fuel / Energy charges Hour 6.50 892.50 5801.25
5 Jack hammers 2 Nos. Hour 13.00 19.80 257.40
Fuel / Energy charges Hour 13.00 0.00 0.00
Total hire charges of Machinery Rs: 14553.82
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Shovel Hour 1.10 236.60 260.26
2 Crew for Dozer Hour 0.25 236.60 59.15
3 Crew for Tipper Hour 4.40 177.50 781.00
4 Crew for Air compressor Hour 6.50 210.90 1370.85
5 Crew for Jack hammer Hour 13.00 329.60 4284.80
6 work inspector Day 0.50 450.00 225.00
7 Blaster Day 1.00 510.00 510.00
8 Helper blaster Day 1.00 400.00 400.00
9 Crowbarman Day 0.50 400.00 200.00
10 Stone breaker Day 0.50 400.00 200.00
11 mazdoor Day 2.00 350.00 700.00
Total cost of Labour Rs: 8991.06
labour component/unit qty 132.20
Add contractor's profit and overhead charges 13.615% 18.00
labour component/unit qty (including contractor's profit) 150.20
ABSTRACT:
A. Cost of Materials Rs: 5692.10
B. Hire charges of Machinery Rs: 14553.82
130
Canal and Allied Works - Item Unit Rates 2016-17
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 3980.61
Total cost for 68.00 cum Rs: 33217.59
Rate per cum (A+B+C+D)/68 Rs. 488.50
IRR-CAW-1-7 Excavation in hard rock of all toughness including boulders above 1.2 m dia. by approved
(b) controlled blasting methods for canals, cut-off trench of embankment, filter / catch-water
drains etc., including controlling fly-rock by muffling arrangements such as placing
50 x 50 mm opening chain link mesh or waste tyres and sand bags, monitoring ground
vibrations at specified locations, costof all materials, machinery, labour, placing excavated rock
neatly in approved dump area or other place as directed etc., complete with lead upto 1 km
and all lifts.
Note: i ) The rate under this item shall be adopted for canals designed for carrying capacity of less
than 15 cumecs or where the average depth of excavation in hard rock is less than 3 m.
ii ) The rate under this item shall be adopted where the control of fly-rock and ground vibrations
is required.
131
Canal and Allied Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Shovel 0.85 cum capacity Hour 1.10 1706.60 1877.26
Fuel / Energy charges Hour 1.10 872.70 959.97
2 Angle dozer 90 hp Hour 0.25 1715.50 428.88
Fuel / Energy charges Hour 0.25 610.50 152.63
3 Tippers 5 cum capacity 3 Nos. Hour 4.40 446.70 1965.48
Fuel / Energy charges Hour 4.40 299.90 1319.56
Air compressor 8.5 cmm ( diesel ) 1
4 No Hour 6.50 275.60 1791.40
Fuel / Energy charges Hour 6.50 892.50 5801.25
5 Jack hammers 2 Nos. Hour 13.00 19.80 257.40
Fuel / Energy charges Hour 13.00 0.00 0.00
Total hire charges of Machinery Rs: 14553.82
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Shovel Hour 1.10 236.60 260.26
2 Crew for Angle dozer Hour 0.25 236.60 59.15
3 Crew for Tipper Hour 4.40 177.50 781.00
4 Crew for Air compressor Hour 6.50 210.90 1370.85
5 Crew for Jack hammer Hour 13.00 329.60 4284.80
6 work inspector Day 0.50 450.00 225.00
7 Blaster Day 0.50 510.00 255.00
8 Helper blaster Day 0.50 400.00 200.00
9 Stone chiseller Cl - II Day 0.50 400.00 200.00
10 Stone breaker Day 0.50 400.00 200.00
11 mazdoor Day 3.00 350.00 1050.00
Total cost of Labour Rs: 8886.06
labour component/unit qty 130.70
Add contractor's profit and overhead charges 13.615% 17.80
labour component/unit qty (including contractor's profit) 148.50
ABSTRACT:
A. Cost of Materials Rs: 12604.08
B. Hire charges of Machinery Rs: 14553.82
C. Cost of Labour Rs: 8886.06
Total Rs: 36043.96
Add for blasting studies & monitoring vibrations etc 0.50% Rs: 180.22
Total Rs: 36224.18
D. Add for contractor's profit and overheads on 13.615% Rs: 4931.92
Total cost for 68.00 cum Rs: 41156.10
Rate per cum (A+B+C+D)/68 Rs. 605.20
IRR-CAW-1-8 Excavation in hard rock of all toughness including boulders above 1.2 m dia. for dressing
( c) canal sides neatly on either side to required profile by line drilling and smooth blasting
including removing under-cuts by chiselling / hammering, placing the excavated rock neatly in
dump area or other place as directed, cost of all materials, machinery, labour etc., complete
with lead upto 1 km and all lifts.
Note: i) For excavation of canal below free board level combination of normal / controlled blasting and
line drilling and smooth blasting shall be adopted to obtain neat side slopes. For the purpose
of payment 1 m width of excavation on either side shall be treated as excavation by line drilling
and smooth blasting and remaining portion shall be treated as excavation by normal / controlled
blasting as the case may be.
ii ) The rate under this item shall be adopted for canals designed for carrying capacity of less
than 15 cumecs or where the average depth of excavation in hard rock is less than 3 m.
iii ) The rate includes controlling fly-rock wherever required.
iv ) The rate under this item shall be paid only on ascertaining that the excavated face has
come off neatly as per specifications or atleast 50 percent of smooth blast holes are visible for
132
Canal and Allied Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Shovel 0.85 cum capacity Hour 0.28 1706.60 477.85
Fuel / Energy charges Hour 0.28 872.70 244.36
2 Tippers 5 cum capacity 4 Nos. Hour 1.12 446.70 500.30
Fuel / Energy charges Hour 1.12 299.90 335.89
Air compressor 8.5 cmm ( diesel ) 1
3 Nos Hour 5.00 275.60 1378.00
Fuel / Energy charges Hour 5.00 892.50 4462.50
4 Jack hammers 2 Nos. Hour 10.00 19.80 198.00
Fuel / Energy charges Hour 10.00 0.00 0.00
Total hire charges of Machinery Rs: 7596.90
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Shovel Hour 0.50 236.60 118.30
2 Crew for Tipper Hour 1.12 177.50 198.80
3 Crew for Air compressor Hour 5.00 210.90 1054.50
4 Crew for Jack hammer Hour 10.00 329.60 3296.00
5 work inspector Day 0.50 450.00 225.00
6 Blaster Day 0.50 510.00 255.00
7 Helper blaster Day 0.50 400.00 200.00
8 Stone breaker Day 0.50 400.00 200.00
9 Stone chiseller Cl - II Day 0.50 400.00 200.00
10 mazdoor Day 1.00 350.00 350.00
Total cost of Labour Rs: 6097.60
labour component/unit qty 348.40
Add contractor's profit and overhead charges 13.615% 47.40
labour component/unit qty (including contractor's profit) 395.80
ABSTRACT:
A. Cost of Materials Rs: 2871.56
133
Canal and Allied Works - Item Unit Rates 2016-17
IRR-CAW-1-9 Excavation in hard rock by blasting including boulders above 1.2 m dia. for canals, seating
(a) embankment etc., including levelling bed by removing all projections by hammering / chiselling,
cost of all materials, machinery, labour, placing the excavated rock neatly in approved dump
area and levelling the same as directed etc.,complete with initial lead upto 1 km and all lifts.
Note: i ) The rate under this item shall be adopted for canals designed for carrying capacity of more
than 15 cumecs or where the average depth of excavation in hard rock is more than 3 m.
ii ) The rate includes levelling canal bed by hammering / chiselling all rock projections wherever
required.
134
Canal and Allied Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Tippers 5 cum capacity Hour 24.84 446.70 11096.03
Fuel / Energy charges Hour 24.84 299.90 7449.52
2 Shovel 0.85 cum capacity Hour 6.21 1706.60 10597.99
Fuel / Energy charges Hour 6.21 872.70 5419.47
3 Angle dozer Hour 2.00 1715.50 3431.00
Fuel / Energy charges Hour 2.00 610.50 1221.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Tipper Hour 24.84 177.50 4409.10
2 Crew for Shovel Hour 6.21 236.60 1469.29
3 Crew for Dozer Hour 2.00 236.60 473.20
4 Crew for Air compressor Hour 11.50 210.90 2425.35
5 Crew for Waggon drill Hour 10.50 283.90 2980.95
6 Crew for Jack hammer Hour 2.00 329.60 659.20
7 work inspector Day 2.00 450.00 900.00
8 Blaster Day 1.00 510.00 510.00
9 Helper blaster Day 1.00 400.00 400.00
10 Stone chiseller Cl - II Day 1.00 400.00 400.00
11 Stone breaker Day 1.00 400.00 400.00
12 mazdoor Day 3.00 350.00 1050.00
Total cost of Labour Rs: 16077.09
labour component/unit qty 41.70
Add contractor's profit and overhead charges 13.615% 5.70
labour component/unit qty (including contractor's profit) 47.40
ABSTRACT:
A. Cost of Materials Rs: 30967.84
B. Hire charges of Machinery Rs: 54667.00
C. Cost of Labour Rs: 16077.09
Total Rs: 101711.92
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 13848.08
Total cost for 386.00 Cum Rs: 115560.00
Rate per Cum (A+B+C+D)/386 Rs. 299.40
IRR-CAW-1-10 Excavation in hard rock of all toughness including boulders above 1.2 m dia. by approved
(b) controlled blasting methods for canals, cut-off trench of embankment etc., including
controlling fly-rock by muffling arrangements such as placing 50 x 50 mm opening
chain link mesh or waste tyres and sand bags, monitoring ground vibrations at specified
locations, cost of all materials, machinery, labour, placing excavated rock neatly in approved
dump area or other place as directed etc., complete with lead upto 1 km and all lifts.
135
Canal and Allied Works - Item Unit Rates 2016-17
Note: i ) The rate under this item shall be adopted for canals designed for carrying capacity of more
than 15 cumecs or where the average depth of excavation in hard rock is more than 3 m.
ii ) The rate under this item shall be adopted where the control of fly-rock and ground vibrations
is required.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
136
Canal and Allied Works - Item Unit Rates 2016-17
in Rs. in Rs.
1 Tippers 5 cum capacity Hour 30.00 446.70 13401.00
Fuel / Energy charges Hour 30.00 299.90 8997.00
2 Shovel 0.85 cum capacity Hour 10.00 1706.60 17066.00
Fuel / Energy charges Hour 10.00 872.70 8727.00
3 Angle dozer Hour 2.00 1715.50 3431.00
Fuel / Energy charges Hour 2.00 610.50 1221.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Tipper Hour 30.00 177.50 5325.00
2 Crew for Shovel Hour 10.00 236.60 2366.00
3 Crew for Dozer Hour 2.00 236.60 473.20
4 Crew for Air compressor Hour 12.50 210.90 2636.25
5 Crew for Waggon drill Hour 11.50 283.90 3264.85
6 Crew for Jack hammer Hour 2.00 329.60 659.20
7 work inspector Day 1.50 450.00 675.00
8 Blaster Day 0.50 510.00 255.00
9 Helper blaster Day 0.50 400.00 200.00
10 Stone chiseller Cl - II Day 1.00 400.00 400.00
11 Stone breaker Day 1.00 400.00 400.00
12 mazdoor Day 5.00 350.00 1750.00
Total cost of Labour Rs: 18404.50
labour component/unit qty 47.70
Add contractor's profit and overhead charges 13.615% 6.50
labour component/unit qty (including contractor's profit) 54.20
ABSTRACT:
A. Cost of Materials Rs: 63764.85
B. Hire charges of Machinery Rs: 69651.60
C. Cost of Labour Rs: 18404.50
Total Rs: 151820.95
Add for blasting studies & monitoring vibrations etc 0.50% Rs: 759.10
Total Rs: 152580.06
D. Add for contractor's profit and overheads on 13.615% Rs: 20773.78
Total cost for 386.00 cum Rs: 173353.84
Rate per cum (A+B+C+D)/386 Rs. 449.10
IRR-CAW-1-11 Excavation in hard rock of all toughness including boulders above 1.2 m dia. for dressing
( c) canal sides neatly on either side to required profile by line drilling and smooth blasting
including removing under-cuts by chiselling / hammering, placing the excavated rock neatly in
dump area or other place as directed, cost of all materials, machinery, labour etc., complete
with lead upto 1 km and all lifts.
Note: i ) For excavation of canal below free board level combination of normal / controlled blasting and
line drilling and smooth blasting shall be adopted to obtain neat side slopes. For the purpose
of payment 1 m width of excavation on either side shall be treated as excavation by line drilling
and smooth blasting and remaining portion shall be treated as excavation by normal / controlled
blasting as the case may be.
ii ) The rate under this item shall be adopted for canals designed for carrying capacity of more
than 15 cumecs or where the average depth of excavation in hard rock is more than 3 m.
iii ) The rate includes controlling fly-rock wherever required.
iv ) The rate under this item shall be paid only on ascertaining that the excavated face has
come off neatly as per specifications or atleast 50 percent of smooth blast holes are visible for
inspection and are spaced at specified interval.
v ) In case, where the above criteria is not fulfilled payment shall be restricted to rate provided
137
Canal and Allied Works - Item Unit Rates 2016-17
for excavation by normal blasting or controlled blasting as the case may be.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Tippers 5 cum capacity Hour 6.24 446.70 2787.41
Fuel / Energy charges Hour 6.24 299.90 1871.38
2 Shovel 0.85 cum capacity Hour 1.56 1706.60 2662.30
Fuel / Energy charges Hour 1.56 872.70 1361.41
3 Angle dozer Hour 0.50 1715.50 857.75
Fuel / Energy charges Hour 0.50 610.50 305.25
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Tipper Hour 5.24 177.50 930.10
2 Crew for Shovel Hour 1.56 236.60 369.10
138
Canal and Allied Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 23906.61
B. Hire charges of Machinery Rs: 28054.54
C. Cost of Labour Rs: 10417.36
Total Rs: 62378.50
Add for blasting studies & monitoring vibrations etc 0.50% Rs: 311.89
Total Rs: 62690.39
D. Add for contractor's profit and overheads on 13.615% Rs: 8535.3
Total cost for 97.00 cum Rs: 71225.69
Rate per cum (A+B+C+D)/97 Rs. 734.30
IRR-CAW-2-1 Providing impervious hearting embankment with selected soil from approved borrow areas in
layers of 25 cm before compaction including cost of all materials, machinery, labour,
all operations such as excavation, sorting out, transporting, spreading in layer of specified
thickness, breaking clods, sectioning, watering, compacting each layer to density control of
not less than 98 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc., complete with initial lead upto 1 km and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Angle dozer Hour 3.40 1715.50 5832.70
Fuel / Energy charges Hour 3.40 610.50 2075.70
2 Shovel 0.50 cum capacity Hour 8.00 1003.10 8024.80
Fuel / Energy charges Hour 8.00 476.00 3808.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Dozer Hour 3.40 236.60 804.44
139
Canal and Allied Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 58876.36
C. Cost of Labour Rs: 12953.80
Total Rs: 71830.16
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 9779.68
Total cost for 412.80 cum Rs: 81609.84
Rate per cum (A+B+C+D)/412.80 Rs. 197.70
IRR-CAW-2-2 Providing impervious hearting embankment with selected soil from approved borrow areas in
layers of 25 cm before compaction including cost of all materials, machinery, labour,
all operations such as excavation, sorting out, transporting, spreading in layer of specified
thickness, breaking clods, sectioning, watering, compacting each layer to density control of
not less than 95 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc., complete with initial lead upto 1 km and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Angle dozer 90 hp Hour 3.40 1715.50 5832.70
Fuel / Energy charges Hour 3.40 610.50 2075.70
2 Shovel 0.5 cum Hour 8.00 1003.10 8024.80
Fuel / Energy charges Hour 8.00 476.00 3808.00
3 Tippers 5 cum Hour 32.00 446.70 14294.40
Fuel / Energy charges Hour 32.00 299.90 9596.80
4 Pump 5 hp ( diesel ) Hour 2.00 10.20 20.40
Fuel / Energy charges Hour 2.00 79.30 158.60
5 Water tanker 8000 ltr Hour 4.00 402.50 1610.00
Fuel / Energy charges Hour 4.00 299.90 1199.60
6 Vibratory Roller 8 tonne Hour 4.18 1342.20 5610.40
Fuel / Energy charges Hour 4.18 1031.40 4311.25
7 Sundries LS 5.00 30.00 150.00
Total hire charges of Machinery Rs: 56692.65
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Dozer Hour 3.40 236.60 804.44
2 Crew for Shovel Hour 8.00 236.60 1892.80
3 Crew for Tipper Hour 32.00 177.50 5680.00
4 Crew for Pump Hour 2.00 111.10 222.20
5 Crew for Water tanker Hour 4.00 177.50 710.00
6 Crew for Roller Hour 4.18 263.60 1101.85
140
Canal and Allied Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 56692.65
C. Cost of Labour Rs: 12711.29
Total Rs: 69403.94
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 9449.35
Total cost for 412.80 cum Rs: 78853.29
Rate per cum (A+B+C+D)/412.80 Rs. 191.00
IRR-CAW-2-3 Providing semi-pervious / pervious casing embankment using soil from approved borrow area
in layers of 25 cm before compaction including cost of all materials, machinery, labour,
all operations such as excavation, sortingout, transporting, spreading in layer of specified
thickness, breaking clods, sectioning, watering, compacting to density control of not less
than 98 percent or as stipulated by Sheep foot roller / Vibratory roller/ 8 to 10 tonne power roller
etc., complete with initial lead upto 1 km and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Angle dozer 90 hp Hour 3.40 1715.50 5832.70
Fuel / Energy charges Hour 3.40 610.50 2075.70
2 Shovel 0.50 cum capacity Hour 8.00 1003.10 8024.80
Fuel / Energy charges Hour 8.00 476.00 3808.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Dozer Hour 3.40 236.60 804.44
2 Crew for Shovel Hour 8.00 236.60 1892.80
3 Crew for Tipper Hour 32.00 177.50 5680.00
4 Crew for Pump Hour 2.00 111.10 222.20
5 Crew for Water tanker Hour 4.00 177.50 710.00
6 Crew for Roller Hour 5.10 263.60 1344.36
7 work inspector Day 2.00 450.00 900.00
8 mazdoor Day 4.00 350.00 1400.00
Total cost of Labour Rs: 12953.80
labour component/unit qty 31.40
Add contractor's profit and overhead charges 13.615% 4.30
141
Canal and Allied Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 58786.36
C. Cost of Labour Rs: 12953.80
Total Rs: 71740.16
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 9767.42
Total cost for 412.80 cum Rs: 81507.58
Rate per cum (A+B+C+D)/412.80 Rs. 197.50
IRR-CAW-2-4 Providing semi-pervious / pervious casing embankment using soil from approved borrow area
in layers of 25cm before compaction including cost of all materials, machinery, labour,
all operations such as excavation, sortingout, transporting, spreading in layer of specified
thickness, breaking clods, sectioning, watering, compacting to density control of not less
than 95 percent or as stipulated by Sheep foot roller / Vibratory roller/ 8 to 10 tonne power roller
etc., complete with initial lead upto 1 km and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Angle dozer 90 hp Hour 3.40 1715.50 5832.70
Fuel / Energy charges Hour 3.40 610.50 2075.70
2 Shovel 0.5 cum Hour 8.00 1003.10 8024.80
Fuel / Energy charges Hour 8.00 476.00 3808.00
3 Tippers 5 cum Hour 32.00 446.70 14294.40
Fuel / Energy charges Hour 32.00 299.90 9596.80
4 Pump 5 hp ( diesel ) Hour 2.00 10.20 20.40
Fuel / Energy charges Hour 2.00 79.30 158.60
5 Water tanker 8000 ltr Hour 4.00 402.50 1610.00
Fuel / Energy charges Hour 4.00 299.90 1199.60
6 Vibratory Roller 8 tonne Hour 4.17 1342.20 5596.97
Fuel / Energy charges Hour 4.17 1031.40 4300.94
7 Sundries LS 5.00 30.00 150.00
Total hire charges of Machinery Rs: 56668.91
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Dozer Hour 3.40 236.60 804.44
2 Crew for Shovel Hour 8.00 236.60 1892.80
3 Crew for Tipper Hour 32.00 177.50 5680.00
4 Crew for Pump Hour 2.00 111.10 222.20
5 Crew for Water tanker Hour 4.00 177.50 710.00
6 Crew for Roller Hour 4.00 263.60 1054.40
7 work inspector Day 4.17 450.00 1876.50
8 mazdoor Day 4.00 350.00 1400.00
Total cost of Labour Rs: 13640.34
labour component/unit qty 33.00
Add contractor's profit and overhead charges 13.615% 4.50
labour component/unit qty (including contractor's profit) 37.50
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 56668.91
C. Cost of Labour Rs: 13640.34
142
Canal and Allied Works - Item Unit Rates 2016-17
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 9572.6
Total cost for 412.80 cum Rs: 79881.85
Rate per cum (A+B+C+D)/412.80 Rs. 193.50
IRR-CAW-2-5 Providing semi-pervious / pervious casing embankment using soil from approved borrow area
in layers of 25cm before compaction including cost of all materials, machinery, labour,
all operations such as excavation, sortingout, transporting, spreading in layer of specified
thickness, breaking clods, sectioning, compacting each layer without watering to density
control of not less than 95 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc., complete with initial lead upto 1 km and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Angle dozer 90 hp Hour 3.40 1715.50 5832.70
Fuel / Energy charges Hour 3.40 610.50 2075.70
2 Shovel 0.50 cum capacity Hour 8.00 1003.10 8024.80
Fuel / Energy charges Hour 8.00 476.00 3808.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Dozer Hour 3.40 236.60 804.44
2 Crew for Shovel Hour 8.00 236.60 1892.80
3 Crew for Tipper Hour 32.00 177.50 5680.00
4 Crew for Roller Hour 4.17 263.60 1099.21
5 work inspector Day 2.00 450.00 900.00
6 mazdoor Day 4.00 350.00 1400.00
Total cost of Labour Rs: 11776.45
labour component/unit qty 28.50
Add contractor's profit and overhead charges 13.615% 3.90
labour component/unit qty (including contractor's profit) 32.40
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 53590.31
C. Cost of Labour Rs: 11776.45
Total Rs: 65366.76
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 8899.68
Total cost for 412.80 cum Rs: 74266.44
Rate per cum (A+B+C+D)/412.80 Rs. 179.90
IRR-CAW-2-6 Providing hearting / casing embankment with homogeneous soil from approved borrow
areas in layers of 25 cm before compaction including cost of all materials, machinery,
labour, all operations such as excavation, sorting out, transporting, spreading in layer of
specified thickness, breaking clods, sectioning, watering, compacting each layer to density
143
Canal and Allied Works - Item Unit Rates 2016-17
control of not less than 98 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc., complete with initial lead upto 1 km and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Angle dozer Hour 6.06 1715.50 10395.93
Fuel / Energy charges Hour 6.06 610.50 3699.63
2 Shovel 0.50 cum capacity Hour 8.00 1003.10 8024.80
Fuel / Energy charges Hour 8.00 476.00 3808.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Dozer Hour 6.06 236.60 1433.80
2 Crew for Shovel Hour 8.00 236.60 1892.80
3 Crew for Tipper Hour 48.00 177.50 8520.00
4 Crew for Pump Hour 3.00 111.10 333.30
5 Crew for Water tanker Hour 6.00 177.50 1065.00
6 Crew for Roller Hour 7.53 263.60 1984.91
7 work inspector Day 2.00 450.00 900.00
8 mazdoor Day 4.00 350.00 1400.00
Total cost of Labour Rs: 17529.80
labour component/unit qty 25.90
Add contractor's profit and overhead charges 13.615% 3.50
labour component/unit qty (including contractor's profit) 29.40
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 84181.27
C. Cost of Labour Rs: 17529.80
Total Rs: 101711.07
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 13847.96
Total cost for 677.28 cum Rs: 115559.03
Rate per cum (A+B+C+D)/677.28 Rs. 170.60
IRR-CAW-2-7 Providing hearting / casing embankment with homogeneous soil from approved borrow
areas in layers of 25 cm before compaction including cost of all materials, machinery,
labour, all operations such as excavation, sorting out, transporting, spreading in layer of
specified thickness, breaking clods, sectioning, watering, compacting each layer to density
control of not less than 95 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc., complete with initial lead upto 1 km and all lifts.
144
Canal and Allied Works - Item Unit Rates 2016-17
A. MATERIALS:
Sl No particulars Unit Quantity Rate Amount
in Rs. in Rs.
1 Nill 0.00 0.00 0.00
0.00 0.00 0.00
Total cost of Materials Rs: 0.00
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Angle dozer 90 hp Hour 6.06 1715.50 10395.93
Fuel / Energy charges Hour 6.06 610.50 3699.63
2 Shovel 0.5 cum Hour 8.00 1003.10 8024.80
Fuel / Energy charges Hour 8.00 476.00 3808.00
3 Tippers 5 cum 3 Nos Hour 48.00 446.70 21441.60
Fuel / Energy charges Hour 48.00 299.90 14395.20
4 Pump 5 hp ( diesel ) Hour 3.00 10.20 30.60
Fuel / Energy charges Hour 3.00 79.30 237.90
5 Water tanker 8000 ltr Hour 6.00 402.50 2415.00
Fuel / Energy charges Hour 6.00 299.90 1799.40
6 Vibratory Roller 8 tonne Hour 6.16 1342.20 8267.95
Fuel / Energy charges Hour 6.16 1031.40 6353.42
7 Sundries LS 5.00 30.00 150.00
Total hire charges of Machinery Rs: 81019.44
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Dozer Hour 6.06 236.60 1433.80
2 Crew for Shovel Hour 8.00 236.60 1892.80
3 Crew for Tipper Hour 48.00 177.50 8520.00
4 Crew for Pump Hour 3.00 111.10 333.30
5 Crew for Water tanker Hour 6.00 177.50 1065.00
6 Crew for Roller Hour 6.16 263.60 1623.78
7 work inspector Day 2.00 450.00 900.00
8 mazdoor Day 4.00 350.00 1400.00
Total cost of Labour Rs: 17168.67
labour component/unit qty 25.30
Add contractor's profit and overhead charges 13.615% 3.40
labour component/unit qty (including contractor's profit) 28.70
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 81019.44
C. Cost of Labour Rs: 17168.67
Total Rs: 98188.11
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 13368.31
Total cost for 677.28 cum Rs: 111556.42
Rate per cum (A+B+C+D)/677.28 Rs. 164.70
IRR-CAW-2-8 Providing casing embankment using homogeneous soil from approved borrow area
in layers of 25 cm before compaction including cost of all materials, machinery, labour,
all operations such as excavation, sortingout, transporting, spreading in layer of specified
thickness, breaking clods, sectioning, compacting each layer without watering to density
control of not less than 95 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc., complete with initial lead upto 1 km and all lifts.
145
Canal and Allied Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Angle dozer 90 hp Hour 6.06 1715.50 10395.93
Fuel / Energy charges Hour 6.06 610.50 3699.63
2 Shovel 0.50 cum capacity Hour 8.00 1003.10 8024.80
Fuel / Energy charges Hour 8.00 476.00 3808.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Dozer Hour 6.06 236.60 1433.80
2 Crew for Shovel Hour 8.00 236.60 1892.80
3 Crew for Tipper Hour 48.00 177.50 8520.00
4 Crew for Roller Hour 6.16 263.60 1623.78
5 work inspector Day 2.00 450.00 900.00
6 mazdoor Day 4.00 350.00 1400.00
Total cost of Labour Rs: 15770.37
labour component/unit qty 23.30
Add contractor's profit and overhead charges 13.615% 3.20
labour component/unit qty (including contractor's profit) 26.50
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 76446.54
C. Cost of Labour Rs: 15770.37
Total Rs: 92216.91
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 12555.33
Total cost for 677.28 cum Rs: 104772.24
Rate per cum (A+B+C+D)/677.28 Rs. 154.70
IRR-CAW-3-1 Providing impervious hearting embankment with soil from approved dump areas in layers
of 25 cm before compaction including cost of all materials, machinery, labour, all
operations such as re-excavation, sorting out, transporting, spreading in layer of specified
thickness, breaking clods, sectioning, watering, compacting each layer to achieve density
control of not less than 98 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc.,complete with initial lead upto 1 km and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Angle dozer Hour 4.04 1715.50 6930.62
Fuel / Energy charges Hour 4.04 610.50 2466.42
2 Shovel 0.50 cum capacity Hour 8.00 1003.10 8024.80
Fuel / Energy charges Hour 8.00 476.00 3808.00
146
Canal and Allied Works - Item Unit Rates 2016-17
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Dozer Hour 3.58 236.60 847.03
2 Crew for Shovel Hour 8.00 236.60 1892.80
3 Crew for Tipper Hour 48.00 177.50 8520.00
4 Crew for Pump Hour 3.00 111.10 333.30
5 Crew for Water tanker Hour 6.00 177.50 1065.00
6 Crew for Roller Hour 7.50 263.60 1977.00
7 work inspector Day 2.00 450.00 900.00
8 mazdoor Day 6.00 350.00 2100.00
Total cost of Labour Rs: 17635.13
labour component/unit qty 24.00
Add contractor's profit and overhead charges 13.615% 3.30
labour component/unit qty (including contractor's profit) 27.30
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 79411.54
C. Cost of Labour Rs: 17635.13
Total Rs: 97046.67
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 13212.9
Total cost for 735.36 cum Rs: 110259.57
Rate per cum (A+B+C+D)/735.36 Rs. 149.90
IRR-CAW-3-2 Providing impervious hearting embankment with soil from approved dump areas in layers
of 25 cm before compaction including cost of all materials, machinery, labour, all
operations such as re-excavation, sorting out, transporting, spreading in layer of specified
thickness, breaking clods, sectioning, watering, compacting each layer to achieve density
control of not less than 95 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc.,complete with initial lead upto 1 km and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Angle dozer 90 hp Hour 4.04 1715.50 6930.62
Fuel / Energy charges Hour 4.04 610.50 2466.42
2 Shovel 0.5 cum Hour 8.00 1003.10 8024.80
Fuel / Energy charges Hour 8.00 476.00 3808.00
3 Tippers 5 cum Hour 48.00 446.70 21441.60
Fuel / Energy charges Hour 48.00 299.90 14395.20
4 Pump 5 hp ( diesel ) Hour 3.00 10.20 30.60
Fuel / Energy charges Hour 3.00 79.30 237.90
5 Water tanker 8000 ltr Hour 6.00 402.50 2415.00
Fuel / Energy charges Hour 6.00 299.90 1799.40
6 Vibratory Roller 8 tonne Hour 6.13 1342.20 8227.69
Fuel / Energy charges Hour 6.13 1031.40 6322.48
147
Canal and Allied Works - Item Unit Rates 2016-17
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Dozer Hour 4.04 236.60 955.86
2 Crew for Shovel Hour 8.00 236.60 1892.80
3 Crew for Tipper Hour 48.00 177.50 8520.00
4 Crew for Pump Hour 3.00 111.10 333.30
5 Crew for Water tanker Hour 6.00 177.50 1065.00
6 Crew for Roller Hour 6.13 263.60 1615.87
7 work inspector Day 2.00 450.00 900.00
8 mazdoor Day 6.00 350.00 2100.00
Total cost of Labour Rs: 17382.83
labour component/unit qty 23.60
Add contractor's profit and overhead charges 13.615% 3.20
labour component/unit qty (including contractor's profit) 26.80
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 76249.71
C. Cost of Labour Rs: 17382.83
Total Rs: 93632.54
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 12748.07
Total cost for 735.36 cum Rs: 106380.61
Rate per cum (A+B+C+D)/735.36 Rs. 144.70
IRR-CAW-3-3 Providing semi-pervious / pervious casing embankment using soil from approved dump area
in layers of 25 cm before compaction including cost of all materials, machinery, labour,
all operations such as re-excavation, sorting out, transporting, spreading in layer of specified
thickness, breaking clods, sectioning, watering, compacting each layer to density control of
not less than 98 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc., complete with initial lead upto 1 km and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Angle dozer 90 hp Hour 4.22 1715.50 7239.41
Fuel / Energy charges Hour 4.22 610.50 2576.31
2 Shovel 0.50 cum capacity Hour 8.00 1003.10 8024.80
Fuel / Energy charges Hour 8.00 476.00 3808.00
3 Tippers 5.00 cum capacity 6 Nos Hour 48.00 446.70 21441.60
Fuel / Energy charges Hour 48.00 299.90 14395.20
4 Pump 5 hp ( diesel ) Hour 3.00 10.20 30.60
Fuel / Energy charges Hour 3.00 79.30 237.90
5 Water tanker 8000 ltr Hour 6.00 402.50 2415.00
Fuel / Energy charges Hour 6.00 299.90 1799.40
6 Vibratory Roller 8 tonne Hour 7.82 1342.20 10496.00
Fuel / Energy charges Hour 7.82 1031.40 8065.55
7 Sundries LS 2.00 30.00 60.00
Total hire charges of Machinery Rs: 80589.77
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
148
Canal and Allied Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 80589.77
C. Cost of Labour Rs: 17870.90
Total Rs: 98460.68
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 13405.42
Total cost for 768.00 cum Rs: 111866.10
Rate per cum (A+B+C+D)/768 Rs. 145.70
IRR-CAW-3-4 Providing semi-pervious / pervious casing embankment using soil from approved dump area
in layers of 25 cm before compaction including cost of all materials, machinery, labour,
all operations such as re-excavation, sorting out, transporting, spreading in layer of specified
thickness, breaking clods, sectioning, watering, compacting each layer to density control of
not less than 95 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc., complete with initial lead upto 1 km and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Angle dozer 90 hp Hour 4.22 1715.50 7239.41
Fuel / Energy charges Hour 4.22 610.50 2576.31
2 Shovel 0.5 cum Hour 8.00 1003.10 8024.80
Fuel / Energy charges Hour 8.00 476.00 3808.00
3 Tippers 5 cum of 6 Nos Hour 48.00 446.70 21441.60
Fuel / Energy charges Hour 48.00 299.90 14395.20
4 Pump 5 hp ( diesel ) Hour 3.00 10.20 30.60
Fuel / Energy charges Hour 3.00 79.30 237.90
5 Water tanker 8000 ltr Hour 6.00 402.50 2415.00
Fuel / Energy charges Hour 6.00 299.90 1799.40
6 Vibratory Roller 8 tonne Hour 6.40 1342.20 8590.08
Fuel / Energy charges Hour 6.40 1031.40 6600.96
7 Sundries LS 5.00 30.00 150.00
Total hire charges of Machinery Rs: 77309.26
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Dozer Hour 4.22 236.60 998.45
2 Crew for Shovel Hour 8.00 236.60 1892.80
3 Crew for Tipper Hour 48.00 177.50 8520.00
4 Crew for Pump Hour 3.00 111.10 333.30
5 Crew for Water tanker Hour 6.00 177.50 1065.00
149
Canal and Allied Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 77309.26
C. Cost of Labour Rs: 17496.59
Total Rs: 94805.85
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 12907.82
Total cost for 768.00 cum Rs: 107713.67
Rate per cum (A+B+C+D)/768 Rs. 140.30
IRR-CAW-3-5 Providing semi-pervious / pervious casing embankment using soil from approved dump area
in layers of 25 cm before compaction including cost of all materials, machinery, labour,
all operations such as re-excavation, sorting out, transporting, spreading in layer of specified
thickness, breaking clods, sectioning, compacting each layer without watering to density
control of not less than 95 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc., complete with initial lead upto 1 km and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Angle dozer 90 hp Hour 4.22 1715.50 7239.41
Fuel / Energy charges Hour 4.22 610.50 2576.31
2 Shovel 0.50 cum capacity Hour 8.00 1003.10 8024.80
Fuel / Energy charges Hour 8.00 476.00 3808.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Dozer Hour 4.22 236.60 998.45
2 Crew for Shovel Hour 8.00 236.60 1892.80
3 Crew for Tipper Hour 48.00 177.50 8520.00
4 Crew for Roller Hour 6.40 263.60 1687.04
5 work inspector Day 2.00 450.00 900.00
6 mazdoor Day 6.00 350.00 2100.00
Total cost of Labour Rs: 16098.29
labour component/unit qty 21.00
Add contractor's profit and overhead charges 13.615% 2.90
labour component/unit qty (including contractor's profit) 23.90
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 72736.36
150
Canal and Allied Works - Item Unit Rates 2016-17
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 12094.84
Total cost for 768.00 cum Rs: 100929.49
Rate per cum (A+B+C+D)/768 Rs. 131.40
IRR-CAW-4-1 Providing impervious hearting embankment with soil collected in embankment area in
heaps as part of disposal of excavated soil from canal including cost of all materials,machinery,
labour, all operations such as sortingout, spreading in layer of 25 cm before compaction,
breaking clods,sectioning, watering and compacting each layer to density control of not less
than 98 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc., complete with lead upto 1 km for water.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Angle dozer 90 hp Hour 3.60 1715.50 6175.80
Fuel / Energy charges Hour 3.60 610.50 2197.80
2 Pump 5 hp ( diesel ) Hour 3.00 10.20 30.60
Fuel / Energy charges Hour 3.00 79.30 237.90
3 Water tanker 8000 ltr Hour 5.00 402.50 2012.50
Fuel / Energy charges Hour 5.00 299.90 1499.50
4 Vibratory Roller 8 tonne Hour 7.30 1342.20 9798.06
Fuel / Energy charges Hour 7.30 1031.40 7529.22
5 Sundries LS 2.00 30.00 60.00
Total hire charges of Machinery Rs: 29541.38
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Dozer Hour 3.60 236.60 851.76
2 Crew for Pump Hour 3.00 111.10 333.30
3 Crew for Water tanker Hour 5.00 177.50 887.50
4 Crew for Roller Hour 7.30 263.60 1924.28
5 work inspector Day 1.00 450.00 450.00
6 mazdoor Day 4.00 350.00 1400.00
Total cost of Labour Rs: 5846.84
labour component/unit qty 9.70
Add contractor's profit and overhead charges 13.615% 1.30
labour component/unit qty (including contractor's profit) 11.00
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 29541.38
C. Cost of Labour Rs: 5846.84
Total Rs: 35388.22
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 4818.11
Total cost for 600.00 cum Rs: 40206.33
Rate per cum (A+B+C+D)/600 Rs. 67.00
IRR-CAW-4-2 Providing impervious hearting embankment with soil collected in embankment area in
heaps as part of disposal of excavated soil from canal including cost of all materials,machinery,
labour, all operations such as sortingout, spreading in layer of 25 cm before compaction,
breaking clods,sectioning, watering and compacting each layer to density control of not less
151
Canal and Allied Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Angle dozer 90 hp Hour 3.60 1715.50 6175.80
Fuel / Energy charges Hour 3.60 610.50 2197.80
2 Pump 5 hp ( diesel ) Hour 3.00 10.20 30.60
Fuel / Energy charges Hour 3.00 79.30 237.90
3 Water tanker 8000 ltr Hour 5.00 402.50 2012.50
Fuel / Energy charges Hour 5.00 299.90 1499.50
4 Vibratory Roller 8 tonne Hour 6.06 1342.20 8133.73
Fuel / Energy charges Hour 6.06 1031.40 6250.28
5 Sundries LS 5.00 30.00 150.00
Total hire charges of Machinery Rs: 26688.12
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Dozer Hour 3.60 236.60 851.76
2 Crew for Pump Hour 3.00 111.10 333.30
3 Crew for Water tanker Hour 5.00 177.50 887.50
4 Crew for Roller Hour 6.06 263.60 1597.42
5 work inspector Day 2.00 450.00 900.00
6 mazdoor Day 4.00 350.00 1400.00
Total cost of Labour Rs: 5969.98
labour component/unit qty 9.90
Add contractor's profit and overhead charges 13.615% 1.30
labour component/unit qty (including contractor's profit) 11.20
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 26688.12
C. Cost of Labour Rs: 5969.98
Total Rs: 32658.09
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 4446.4
Total cost for 600.00 cum Rs: 37104.49
Rate per cum (A+B+C+D)/600 Rs. 61.80
IRR-CAW-4-3 Providing semi-pervious / pervious casing hearting embankment using soil collected in
heaps in embankment area as part of disposal of excavated soil from canal including cost of
all materials, machinery, labour, all operations such as sorting-out, spreading in layers of 25
cm before compaction, breaking clods, sectioning, watering and compacting each layer
to density control of not less than 98 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc., complete with lead upto 1 km for water.
B. MACHINERY:
152
Canal and Allied Works - Item Unit Rates 2016-17
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Dozer Hour 3.60 236.60 851.76
2 Crew for Pump Hour 3.00 111.10 333.30
3 Crew for Water tanker Hour 5.00 177.50 887.50
4 Crew for Roller Hour 7.30 263.60 1924.28
5 work inspector Day 1.00 450.00 450.00
6 mazdoor Day 4.00 350.00 1400.00
Total cost of Labour Rs: 5846.84
labour component/unit qty 9.70
Add contractor's profit and overhead charges 13.615% 1.30
labour component/unit qty (including contractor's profit) 11.00
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 29541.38
C. Cost of Labour Rs: 5846.84
Total Rs: 35388.22
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 4818.11
Total cost for 600.00 cum Rs: 40206.33
Rate per cum (A+B+C+D)/600 Rs. 67.00
IRR-CAW-4-4 Providing semi-pervious / pervious casing embankment using soil collected in heaps in
embankment area as part of disposal of excavated soil from canal including cost of all
materials, machinery, labour, all operations such as sorting-out, spreading in layers of 25
cm before compaction, breaking clods, sectioning, watering and compacting each layer
to density control of not less than 95 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc., complete with lead upto 1 km for water.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Angle dozer 90 hp Hour 3.60 1715.50 6175.80
Fuel / Energy charges Hour 3.60 610.50 2197.80
2 Pump 5 hp ( diesel ) Hour 3.00 10.20 30.60
Fuel / Energy charges Hour 3.00 79.30 237.90
3 Water tanker 8000 ltr Hour 5.00 402.50 2012.50
Fuel / Energy charges Hour 5.00 299.90 1499.50
4 Vibratory Roller 8 tonne Hour 6.1 1342.20 8133.73
Fuel / Energy charges Hour 6.1 1031.40 6250.28
5 Sundries LS 5.00 30.00 150.00
Total hire charges of Machinery Rs: 26688.12
153
Canal and Allied Works - Item Unit Rates 2016-17
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Dozer Hour 3.60 236.60 851.76
2 Crew for Pump Hour 3.00 111.10 333.30
3 Crew for Water tanker Hour 5.00 177.50 887.50
4 Crew for Roller Hour 6.1 263.60 1597.42
5 work inspector Day 2.00 450.00 900.00
6 mazdoor Day 4.00 350.00 1400.00
Total cost of Labour Rs: 5969.98
labour component/unit qty 9.90
Add contractor's profit and overhead charges 13.615% 1.30
labour component/unit qty (including contractor's profit) 11.20
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 26688.12
C. Cost of Labour Rs: 5969.98
Total Rs: 32658.09
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 4446.4
Total cost for 600.00 cum Rs: 37104.49
Rate per cum (A+B+C+D)/600 Rs. 61.80
IRR-CAW-4-5 Providing semi-pervious / pervious casing embankment using soil collected in heaps in
embankment area as part of disposal of excavated soil from canal including cost of all
materials, machinery, labour, all operations such as sorting-out, spreading in layers of 25
cm before compaction, breaking clods, sectioning and compacting each layer without
watering to density control of not less than 95 percent or as stipulated by Sheep foot roller /
Vibratory roller/ 8 to 10 tonne power roller etc., complete.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Angle dozer 90 hp Hour 3.60 1715.50 6175.80
Fuel / Energy charges Hour 3.60 610.50 2197.80
2 Vibratory Roller 8 tonne Hour 6.06 1342.20 8133.73
Fuel / Energy charges Hour 6.06 1031.40 6250.28
3 Sundries LS 2.00 30.00 60.00
Total hire charges of Machinery Rs: 22817.62
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Dozer Hour 3.60 236.60 851.76
2 Crew for Roller Hour 6.06 263.60 1597.42
3 work inspector Day 1.00 450.00 450.00
4 mazdoor Day 4.00 350.00 1400.00
Total cost of Labour Rs: 4299.18
labour component/unit qty 7.20
Add contractor's profit and overhead charges 13.615% 1.00
labour component/unit qty (including contractor's profit) 8.20
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 22817.62
154
Canal and Allied Works - Item Unit Rates 2016-17
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 3691.95
Total cost for 600.00 cum Rs: 30808.74
Rate per cum (A+B+C+D)/600 Rs. 51.30
IRR-CAW-4-6 Providing compacted embankment for field irrigation channels with gravely soil from
approved borrow area including sorting out, spreading in layers of 15 cm thickness, breaking
clods, watering, compacting, dressing sides to required slopes etc.,complete with lead upto
50 m and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 5 hp pump ( diesel ) Hour 1.00 10.20 10.20
Fuel / Energy charges Hour 1.00 79.30 79.30
Total hire charges of Machinery Rs: 89.50
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for pump Hour 1.00 111.10 111.10
2 work inspector Day 1.00 450.00 450.00
3 Crowbarman for loosening soil Day 2.50 400.00 1000.00
4 mazdoor
For excavation at borrow area Day 5.00 350.00 1750.00
5 Cartman with Bullock cart for water Day 1.00 435.00 435.00
6 Bullock drawn roller for rolling Day 1.00 435.00 435.00
Total cost of Labour Rs: 6806.10
labour component/unit qty 272.20
Add contractor's profit and overhead charges 13.615% 37.10
labour component/unit qty (including contractor's profit) 309.30
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 89.50
C. Cost of Labour Rs: 6806.10
Total Rs: 6895.60
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 938.84
Total cost for 25.00 cum Rs: 7834.44
Rate per cum (A+B+C+D)/25 Rs. 313.40
IRR-CAW-5-1 Providing rubble and sand filling in layers of 22.5 to 30 cm including cost of all materials,
machinery, labour, watering, ramming etc., complete with initial lead upto 50 m and all lifts.
155
Canal and Allied Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nil 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 mazdoor Day 4.00 350.00 1400.00
Total cost of Labour Rs: 1400.00
labour component/unit qty 140.00
Add contractor's profit and overhead charges 13.615% 19.10
labour component/unit qty (including contractor's profit) 159.10
ABSTRACT:
A. Cost of Materials Rs: 3560.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 1400.00
Total Rs: 4960.00
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 675.3
Total cost for 10.00 cum Rs: 5635.30
Rate per cum (A+B+C+D)/10 Rs. 563.50
IRR-CAW-5-2 Providing rubble and Murum filling in layers of 22.5 to 30 cm including cost of all materials,
machinery, labour, watering, ramming etc., complete with initial lead upto 50 m and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nil 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 mazdoor Day 4.00 350.00 1400.00
Total cost of Labour Rs: 1400.00
labour component/unit qty 140.00
Add contractor's profit and overhead charges 13.615% 19.10
labour component/unit qty (including contractor's profit) 159.10
ABSTRACT:
A. Cost of Materials Rs: 3840.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 1400.00
Total Rs: 5240.00
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 713.43
Total cost for 10.00 cum Rs: 5953.43
156
Canal and Allied Works - Item Unit Rates 2016-17
IRR-CAW-5-3 Providing and laying 25 cm thick sand blanket below embankment including cost of all
materials, machinery, labour, spreading to specified thickness etc., complete with initial lead
upto 50 m and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nil 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 mazdoor Day 5.00 350.00 1750.00
Total cost of Labour Rs: 1750.00
labour component/unit qty 17.50
Add contractor's profit and overhead charges 13.615% 2.40
labour component/unit qty (including contractor's profit) 19.90
ABSTRACT:
A. Cost of Materials Rs: 2375.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 1750.00
Total Rs: 4125.00
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 561.62
Total cost for 100.00 sqm Rs: 4686.62
Rate per sqm (A+B+C+D)/100 Rs. 46.90
IRR-CAW-5-3-A Providing and laying sand blanket below embankment including cost of all
(New Item3- 2011--
12) materials, machinery, labour, spreading to specified thickness etc., complete with initial lead
upto 50 m and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nil 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
157
Canal and Allied Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 9500.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 7000.00
Total Rs: 16500.00
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 2246.48
Total cost for 100.00 cum Rs: 18746.48
Rate per cum (A+B+C+D)/100 Rs. 187.50
IRR-CAW-5-4 Providing and constructing dry rubble rock-toe using rubble and stone chips from
approved source including cost of all materials, machinery, labour, hand packing rubble
and stone chips, finishing top and sides to required slopes etc., complete with initial lead upto
50 m and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nil 0.00 0.00
0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 1.00 450.00 450.00
2 Mason Class-II Day 7.00 400.00 2800.00
3 mazdoor Day 19.00 350.00 6650.00
Total cost of Labour Rs: 9900.00
labour component/unit qty 99.00
Add contractor's profit and overhead charges 13.615% 13.50
labour component/unit qty (including contractor's profit) 112.50
ABSTRACT:
A. Cost of Materials Rs: 37110.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 9900.00
Total Rs: 47010.00
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 6400.41
Total cost for 100.00 cum Rs: 53410.41
Rate per cum (A+B+C+D)/100 Rs. 534.10
IRR-CAW-5-5 Providing and constructing longitudinal and cross graded filter drains using sand and
20 mm down graded aggregates satisfying specified filter creteria in layers as per specifications
including cost of all materials, machinery, labour, laying to required slopes, compaction etc.,
complete with initial lead upto 50 m and all lifts.
158
Canal and Allied Works - Item Unit Rates 2016-17
A. MATERIALS:
Sl No particulars Unit Quantity Rate Amount
in Rs. in Rs.
1 Sand (Un-Screened ) cum 76.80 95.00 7296.00
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nil 0.00 0.00
0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 1.00 450.00 450.00
2 mazdoor Day 36.00 350.00 12600.00
Total cost of Labour Rs: 13050.00
labour component/unit qty 130.50
Add contractor's profit and overhead charges 13.615% 17.80
labour component/unit qty (including contractor's profit) 148.30
ABSTRACT:
A. Cost of Materials Rs: 33831.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 13050.00
Total Rs: 46881.00
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 6382.85
Total cost for 100.00 cum Rs: 53263.85
Rate per cum (A+B+C+D)/100 Rs. 532.60
IRR-CAW-5-6 Laying Longitudinal Drains and Transverse drains of Size 600 x600 x750 mm in Bed and
filling with 12 mm to 40 mm HG machine Crushed metal and sand in bed including
Excavation of drains and Cost of procuring of all materials including 50 m lead and for all lifts.
B. MACHINERY
Sl.No Description Unit Quantity Rate in Rs.
Amount in Rs.
C. LABOUR
Sl.No Particulars Unit Qty Rate in Rs
Amount in Rs.
1 Labour for Sand laying Cum 5.14 350.00 1799.00
2 Labour for Metal laying Cum 1.93 350.00 675.50
Total cost of Labour Rs. 2474.5
labour component/unit qty 24.70
Add contractor's profit and overhead charges 13.615% 3.40
labour component/unit qty (including contractor's profit) 28.10
ABSTRACT
A. Cost of Materials Rs. 19282.5
B. Hire charges of Machinery Rs. 1575
159
Canal and Allied Works - Item Unit Rates 2016-17
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 3176.65
Total cost for 100.00 mt Rs: 26508.65
Rate per mt (A+B+C+D)/100 Rs. 265.10
IRR-CAW-5-7 Laying and fixing of 100 mm Dia 300 mm long precast porus CC plugs in bed and sides
using 1.181 Kgs of cement per each using 20 mm HG metal and placing in local filters of size
600x600x750 mm in size including Excavation of drains and Cost of procuring of all materials
including 50 m lead and for all lifts.
A. MATERIALS:
Rate in Amount in
Sl.No Particulars Unit Qty Rs Rs.
1 Coarse aggregate Cum 0.08 1225.00 98.49
2 Sand (Un-Screened ) cum 0.203 95.00 19.29
3 Cement Kg 1.181 5.35 6.32
Total cost of Materials Rs. 124.09
B. MACHINERY
Rate in Amount in
Sl.No Description Unit Quantity
Rs. Rs.
C. LABOUR
Rate in Amount in
Sl.No Particulars Unit Qty Rs Rs.
1 Mazdoor Day 0.30 350.00 105.00
Total cost of Labour Rs. 105.00
labour component/unit qty 105.00
Add contractor's profit and overhead charges 13.615% 14.30
labour component/unit qty (including contractor's profit) 119.30
ABSTRACT
A. Cost of Materials Rs. 124.09
B. Hire charges of Machinery Rs. 10.51
C. Cost of Labour Rs. 105.00
Total Rs: 239.60
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 32.62
Total cost for 1.00 Plug Rs: 272.22
Rate per each plug (A+B+C+D)/1.0 Rs. 272.20
IRR-CAW-5-8 Providing and constructing 0.50 m thick vertical or inclined graded filter media consisting of
15 cm thick sand layers and 20 cm thick 20 mm down coarse aggregate layer using approved
materials satisfying specified filter creteria as per specifications including cost of all materials,
machinery, labour, laying to required slope, compaction etc., complete with initial lead upto
50 m and all lifts.
160
Canal and Allied Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nil 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 1.00 450.00 450.00
2 mazdoor Day 36.00 350.00 12600.00
Total cost of Labour Rs: 13050.00
labour component/unit qty 130.50
Add contractor's profit and overhead charges 13.615% 17.80
labour component/unit qty (including contractor's profit) 148.30
ABSTRACT:
A. Cost of Materials Rs: 51450.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 13050.00
Total Rs: 64500.00
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 8781.68
Total cost for 100.00 cum Rs: 73281.68
Rate per cum (A+B+C+D)/100.0 Rs. 732.80
IRR-CAW-5-9 Providing and constructing graded filter media below and behind rock-toe consisting of
20 cm thick sand, 15 cm thick 20 mm down and 15 cm thick 40 mm down size graded coarse
aggregates satisfying filter creteria behind rock-toe and 15 cm thick sand, 20 cm thick 20 mm
down coarse aggregate and 65 cm thick 40 mm down size coarse aggregate satisfying filter
creiteria below rock-toe as per specifications including cost of all materials, machinery, labour,
laying to required slope, compaction etc., complete with initial lead upto 50 m and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nil 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 1.00 450.00 450.00
2 mazdoors Day 60.00 350.00 21000.00
Total cost of Labour Rs: 21450.00
labour component/unit qty 121.90
Add contractor's profit and overhead charges 13.615% 16.60
labour component/unit qty (including contractor's profit) 138.50
ABSTRACT:
A. Cost of Materials Rs: 142033.15
B. Hire charges of Machinery Rs: 0.00
161
Canal and Allied Works - Item Unit Rates 2016-17
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 22258.23
Total cost for 176.00 cum Rs: 185741.38
Rate per cum (A+B+C+D)/176.0 Rs. 1055.30
IRR-CAW-5-10 Providing and laying filter media consisting of 2 layers of poly-propeline nonwoven filter
(a) fabric and 200 mm thick 20 mm down graded coarse aggregate for embankment including
cost of all materials, machinery, labour, forming toe drain etc., complete with lead upto 50 m
a. for aggregate and all leads for fabric and all lifts.
Using 200 gsm filter fabric.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nil 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 1.00 450.00 450.00
2 mazdoor Day 7.00 350.00 2450.00
Total cost of Labour Rs: 2900.00
labour component/unit qty 29.00
Add contractor's profit and overhead charges 13.615% 3.90
labour component/unit qty (including contractor's profit) 32.90
ABSTRACT:
A. Cost of Materials Rs: 50175.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 2900.00
Total Rs: 53075.00
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 7226.16
Total cost for 100.00 sqm Rs: 60301.16
Rate per sqm (A+B+C+D)/100.0 Rs. 603.00
162
Canal and Allied Works - Item Unit Rates 2016-17
IRR-CAW-5-11 Providing and laying filter media consisting of 2 layers of poly-propeline nonwoven filter
(b) fabric and 200 mm thick 20 mm down graded coarse aggregate for embankment including
cost of all materials, machinery, labour, forming toe drain etc., complete with lead upto 50 m
for aggregate and all leads for fabric and all lifts.
b. Using 250 gsm filter fabric.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nil 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 1.00 450.00 450.00
2 mazdoor Day 7.00 350.00 2450.00
Total cost of Labour Rs: 2900.00
labour component/unit qty 29.00
Add contractor's profit and overhead charges 13.615% 3.90
labour component/unit qty (including contractor's profit) 32.90
ABSTRACT:
A. Cost of Materials Rs: 54375.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 2900.00
Total Rs: 57275.00
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 7797.99
Total cost for 100.00 sqm Rs: 65072.99
Rate per sqm (A+B+C+D)/100.0 Rs. 650.70
IRR-CAW-6-1 Providing and constructing rockfill casing to canal embankment with graded stones and
spalls from approved quarry including cost of all materials, machinery, labour, spreading
stones and spalls in layers, hand packing, wedging, finishing surface to required slopes etc.,
complete with initial lead upto 50 m and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nil 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
163
Canal and Allied Works - Item Unit Rates 2016-17
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Mason Cl- II Day 6.00 400.00 2400.00
2 mazdoor Day 8.00 350.00 2800.00
Total cost of Labour Rs: 5200.00
labour component/unit qty 52.00
Add contractor's profit and overhead charges 13.615% 7.10
labour component/unit qty (including contractor's profit) 59.10
ABSTRACT:
A. Cost of Materials Rs: 37050.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 5200.00
Total Rs: 42250.00
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 5752.34
Total cost for 100.00 cum Rs: 48002.34
Rate per cum (A+B+C+D)/100.0 Rs. 480.00
IRR-CAW-6-2 Providing and constructing rockfill casing to canal embankment with graded stones and
spalls available in dump yard (spoil bank) including cost of all materials, machinery, labour, spreading
stones and spalls in layers, hand packing, wedging, finishing surface to required slopes etc.,
complete with initial lead upto 50 m and all lifts.
Note: Stones and spalls available in dump yard shall be issued at specified issue rate.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nil 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Mason Cl- II Day 6.00 400.00 2400.00
2 Crowbarman Day 2.00 400.00 800.00
3 mazdoor Day 10.00 350.00 3500.00
Total cost of Labour Rs: 6700.00
labour component/unit qty 67.00
Add contractor's profit and overhead charges 13.615% 9.10
labour component/unit qty (including contractor's profit) 76.10
ABSTRACT:
A. Cost of Materials Rs: 18275.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 6700.00
Total Rs: 24975.00
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 3400.35
Total cost for 100.00 cum Rs: 28375.35
Rate per cum (A+B+C+D)/100.0 Rs. 283.80
164
Canal and Allied Works - Item Unit Rates 2016-17
IRR-CAW-7-1 Providing cohesive non-swelling ( CNS ) soil lining to canals using soil from approved borrow
area including spreading soil in layers of thickness not more than 15 cm, breaking clods,
watering, compacting to density control of not less than 98 percent or as stipulated,
dressing to required profile etc., complete with initial lead upto 1 km and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Shovel 0.5 cum Hour 8.00 1003.10 8024.80
Fuel / Energy charges Hour 8.00 476.00 3808.00
2 Angle dozer 90 hp Hour 3.00 1715.50 5146.50
Fuel / Energy charges Hour 3.00 610.50 1831.50
3 Tipper 5 cum Hour 24.00 446.70 10720.80
Fuel / Energy charges Hour 24.00 299.90 7197.60
4 Pump 5 hp ( diesel ) Hour 4.00 10.20 40.80
Fuel / Energy charges Hour 4.00 79.30 317.20
5 Water tanker 8000 ltr Hour 4.00 402.50 1610.00
Fuel / Energy charges Hour 4.00 299.90 1199.60
6 Diesel road roller 8-10 tonne Hour 11.50 197.20 2267.80
Fuel / Energy charges Hour 11.50 714.00 8211.00
7 Sundries LS 5.00 30.00 150.00
Total hire charges of Machinery Rs: 50525.60
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Shovel Hour 8.00 236.60 1892.80
2 Crew for Dozer Hour 3.00 236.60 709.80
3 Crew for Tipper Hour 24.00 177.50 4260.00
4 Crew for Pump Hour 4.00 111.10 444.40
5 Crew for Water tanker Hour 4.00 177.50 710.00
6 Crew for Road roller Hour 11.50 210.90 2425.35
7 work inspector Day 2.00 450.00 900.00
8 mazdoor Day 38.00 350.00 13300.00
Total cost of Labour Rs: 24642.35
labour component/unit qty 62.50
Add contractor's profit and overhead charges 13.615% 8.50
labour component/unit qty (including contractor's profit) 71.00
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 50525.60
C. Cost of Labour Rs: 24642.35
Total Rs: 75167.95
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 10234.12
Total cost for 394.00 cum Rs: 85402.07
Rate per cum (A+B+C+D)/394.0 Rs. 216.80
IRR-CAW-7-2 Providing cohesive non-swelling ( CNS ) soil lining to canals using soil from approved borrow
area including spreading soil in layers of thickness not more than 15 cm, breaking clods,
watering, compacting to density control of not less than 95 percent or as stipulated,
dressing to required profile etc., complete with initial lead upto 1 km and all lifts.
165
Canal and Allied Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Shovel 0.5 cum Hour 8.00 1003.10 8024.80
Fuel / Energy charges Hour 8.00 476.00 3808.00
2 Angle dozer 90 hp Hour 3.00 1715.50 5146.50
Fuel / Energy charges Hour 3.00 610.50 1831.50
3 Tippers 5 cum Hour 24.00 446.70 10720.80
Fuel / Energy charges Hour 24.00 299.90 7197.60
4 Pump 5 hp ( diesel ) Hour 4.00 10.20 40.80
Fuel / Energy charges Hour 4.00 79.30 317.20
5 Water tanker 8000 ltr Hour 4.00 402.50 1610.00
Fuel / Energy charges Hour 4.00 299.90 1199.60
6 Diesel road roller 8-10 tonnes Hour 10.00 197.20 1972.00
Fuel / Energy charges Hour 10.00 714.00 7140.00
7 Sundries LS 5.00 30.00 150.00
Total hire charges of Machinery Rs: 49158.80
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Shovel Hour 8.00 236.60 1892.80
2 Crew for Dozer Hour 3.00 236.60 709.80
3 Crew for Tipper Hour 24.00 177.50 4260.00
4 Crew for Pump Hour 4.00 111.10 444.40
5 Crew for Water tanker Hour 4.00 177.50 710.00
6 Crew for Road roller Hour 10.00 210.90 2109.00
7 work inspector Day 2.00 450.00 900.00
8 mazdoor Day 38.00 350.00 13300.00
Total cost of Labour Rs: 24326.00
labour component/unit qty 61.70
Add contractor's profit and overhead charges 13.615% 8.40
labour component/unit qty (including contractor's profit) 70.10
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 49158.80
C. Cost of Labour Rs: 24326.00
Total Rs: 73484.80
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 10004.96
Total cost for 394.00 cum Rs: 83489.76
Rate per cum (A+B+C+D)/394.0 Rs. 211.90
IRR-CAW-7-3 Providing cohesive non-swelling ( CNS ) soil lining to canal using soil collected in heaps
along the edge of canal requiring CNS soil lining as part of the disposal of excavated soil from
canal excavation in CNS soil reach including spreading in layers of thickness not more than
15 cm, breaking clods, watering, compacting to density control of not less than 95 percent
or as stipulated, dressing to required profile etc., complete with lead upto upto 50 m and all
lifts.
166
Canal and Allied Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Angle Dozer 90 hp Hour 1.50 1715.50 2573.25
Fuel / Energy charges Hour 1.50 610.50 915.75
2 Pump 5 hp ( diesel ) Hour 5.00 10.20 51.00
Fuel / Energy charges Hour 5.00 79.30 396.50
3 Water tanker 8000 ltr Hour 5.00 402.50 2012.50
Fuel / Energy charges Hour 5.00 299.90 1499.50
4 Diesel road roller 8-10 tonne Hour 13.00 197.20 2563.60
Fuel / Energy charges Hour 13.00 714.00 9282.00
5 Sundries LS 5.00 30.00 150.00
Total hire charges of Machinery Rs: 19444.10
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Dozer Hour 1.50 236.60 354.90
2 Crew for Pump Hour 5.00 111.10 555.50
3 Crew for Water tanker Hour 5.00 177.50 887.50
4 Crew for Road roller Hour 13.00 210.90 2741.70
5 work inspector Day 2.00 450.00 900.00
6 mazdoor Day 38.00 350.00 13300.00
Total cost of Labour Rs: 18739.60
labour component/unit qty 47.60
Add contractor's profit and overhead charges 13.615% 6.50
labour component/unit qty (including contractor's profit) 54.10
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 19444.10
C. Cost of Labour Rs: 18739.60
Total Rs: 38183.70
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 5198.71
Total cost for 394.00 cum Rs: 43382.41
Rate per cum (A+B+C+D)/394.0 Rs. 110.10
IRR-CAW-7-4 Providing and fixing 20 x 20 x 75 cm size top surface neatly dressed canal bed level
stones including cost of all materials, labour, excavation, fixing in position to correct level etc.,
complete with lead upto 50 m and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nil 0.00 0.00
0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 1.00 450.00 450.00
2 Stone chiseller Cl- I Day 2.00 445.00 890.00
3 mazdoor Day 2.00 350.00 700.00
167
Canal and Allied Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 736.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 2040.00
Total Rs: 2776.00
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 377.95
Total cost for 32.00 Nos. Rs: 3153.95
Rate per each (A+B+C+D)/32.0 Rs. 98.60
IRR-CAW-7-5 Providing, fabricating and placing in position reinforcement steel bars for RCC works
including cleaning, straightening, cutting, bending, hooking, lapping, tying with 1.25 mm dia.
soft annealed steel wire, welding wherever required including cost of all materials, machinery,
labour etc., complete with initial lead upto 50 and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nil 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Bar bender Day 6.00 555.00 3330.00
2 mazdoor Day 11.00 350.00 3850.00
Total cost of Labour Rs: 7180.00
labour component/unit qty 7.20
Add contractor's profit and overhead charges 13.615% 1.00
labour component/unit qty (including contractor's profit) 8.20
ABSTRACT:
A. Cost of Materials Rs: 36480.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 7180.00
Total Rs: 43660.00
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 5944.31
Total cost for 1000.00 kg Rs: 49604.31
Rate per kg (A+B+C+D)/1000.0 Rs. 49.60
IRR-CAW-7-6 Providing and laying 75 mm thick in-situ M-15 ( 28 days cube compressive strength not less
than 15 N / sqmm ) grade cement concrete with 20 mm down size approved, clean, hard,
graded aggregates for canal lining using vibrating cylinder type mechanical paver including
cost of all materials, machinery, labour, cleaning, batching, mixing, placing in position,
finishing, forming contraction joints, fixing PVC joint sealing strips, curing, shifting of paver
from one side to other side of canal etc., complete with initial lead upto 1 km and all lifts.
(43 Gr Cement content: 300 kg /cum (22.5 kg/ sqm) for
use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35,
168
Canal and Allied Works - Item Unit Rates 2016-17
FA : 0.45 cum equivalent concrete volume:79.2 cum including the extra quantity of
concrete for curvatures and bends etc.,)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Batching plant Hour 8.00 405.40 3243.20
Lubricants etc @ 5 % Hour 8.00 20.27 162.16
2 Transit mixer 3 Nos Hour 24.00 758.40 18201.60
Fuel / Energy charges Hour 24.00 872.70 20944.80
3 Mechanical paver Hour 8.00 356.50 2852.00
Lubricants etc @ 5 % Hour 8.00 17.83 142.60
4 DG set for batching plant 50 KVA Hour 8.00 85.10 680.80
Fuel / Energy charges Hour 8.00 952.10 7616.80
5 DG set for paver 30 KVA Hour 8.00 65.80 526.40
Fuel / Energy charges Hour 8.00 634.70 5077.60
6 Shovel 0.5 cum / Loader Hour 2.00 1003.10 2006.20
Fuel / Energy charges Hour 2.00 476.00 952.00
7 Water tanker Hour 8.00 402.50 3220.00
Fuel / Energy charges Hour 8.00 299.90 2399.20
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Batching plant Hour 8.00 340.60 2724.80
2 Crew for Transit mixer Hour 24.00 283.90 6813.60
3 Crew for Concrete paver Hour 8.00 421.80 3374.40
4 Crew for DG set Hour 16.00 131.80 2108.80
5 Crew for Shovel Hour 2.00 236.60 473.20
6 Crew for Water tanker Hour 8.00 177.50 1420.00
7 Crew for Pump Hour 16 111.10 1777.60
8 Mason Class I Day 2 445.00 890.00
9 Mechanic Day 1 475.00 475.00
10 Fitter Day 1 475.00 475.00
11 Electrician Day 1 515.00 515.00
12 work inspector Day 2 450.00 900.00
13 mazdoor ( BP site ) Day 5 350.00 1750.00
14 mazdoor ( Paver site ) Day 10 350.00 3500.00
Total cost of Labour Rs: 27197.40
labour component/unit qty 28.30
Add contractor's profit and overhead charges 13.615% 3.90
labour component/unit qty (including contractor's profit) 32.20
ABSTRACT:
A. Cost of Materials Rs: 235930.20
B. Hire charges of Machinery Rs: 68891.36
C. Cost of Labour Rs: 27197.4
Total Rs:
332018.96
169
Canal and Allied Works - Item Unit Rates 2016-17
IRR-CAW-7-7 Providing and laying 80 mm thick in-situ M-15 ( 28 days cube compressive strength not less
than 15 N / sqmm ) grade cement concrete with 20 mm down size approved, clean, hard,
graded aggregates for canal lining using vibrating cylinder type mechanical paver including
cost of all materials, machinery, labour, cleaning, batching, mixing, placing in position,
finishing, forming contraction joints, fixing PVC joint sealing strips, curing, shifting of paver
from one side to other side of canal etc., complete with initial lead upto 1 km and all lifts.
(43 Gr Cement content: 300 kg /cum (24 kg/ sqm) for
use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35,
FA : 0.45 cum equivalent concrete volume:84.48 cum including the extra quantity of
concrete for curvatures and bends etc.,)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Batching plant Hour 8.00 405.40 3243.20
Lubricants etc @ 5 % Hour 8.00 20.27 162.16
2 Transit mixer 3 Nos Hour 24.00 758.40 18201.60
Fuel / Energy charges Hour 24.00 872.70 20944.80
3 Mechanical paver Hour 8.00 356.50 2852.00
Lubricants etc @ 5 % Hour 8.00 17.83 142.60
4 DG set for batching plant 50 KVA Hour 8.00 85.10 680.80
Fuel / Energy charges Hour 8.00 952.10 7616.80
5 DG set for paver 30 KVA Hour 8.00 65.80 526.40
Fuel / Energy charges Hour 8.00 634.70 5077.60
6 Shovel 0.5 cum / Loader Hour 2.00 1003.10 2006.20
Fuel / Energy charges Hour 2.00 476.00 952.00
7 Water tanker Hour 8.00 402.50 3220.00
Fuel / Energy charges Hour 8.00 299.90 2399.20
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Batching plant Hour 8.00 340.60 2724.80
2 Crew for Transit mixer Hour 24.00 283.90 6813.60
3 Crew for Concrete paver Hour 8.00 421.80 3374.40
4 Crew for DG set Hour 16.00 131.80 2108.80
170
Canal and Allied Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 249672.72
B. Hire charges of Machinery Rs: 68891.36
C. Cost of Labour Rs: 27197.4
Total Rs:
345761.48
Add for shifting & re-erection of BP @ 2% Rs: 6915.2296
Add for LH / RH shifting & erection of Paver @ 0.5% Rs: 1728.8074
Add for ledge cutting / erection of tracks etc @ 1% Rs: 3457.6148
Total Rs: 357863.13
D. Add for contractor's profit and overheads on (A+B+C+other 13.615% Rs: 48723.07
Lead Charges for 1 Km for FA 38.02 cum @ 31.5 Rs./Cum
1197.504
Lead Charges for 1 Km for CA 67.58 cum @ 30.4 Rs./Cum2054.55
Total cost for 960.00 sqm Rs: 409838.26
Rate per sqm (A+B+C+D)/960.0 Rs. 426.90
IRR-CAW-7-8 Providing and laying 100 mm thick in situ M-15 (28 days cube compressive strength not less than
15 N /Sqmm ) grade cement concrete with 20 mm down size approved, clean, hard, graded
aggregates for canal lining using, vibrating, cylinder type mechanical paver including cost of all
materials, machinery, labour, cleaning, batching, mixing, placing in position, finishing, forming
contraction joints, fixing PVC joint sealing strips, curing, shifting of paver from one side to othere
side of canal etc., complete with initial lead upto 1 Km and all lifts.
(43 Gr Cement content: 300 kg /cum (30 kg/ sqm) for
use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35,
FA : 0.45 cum equivalent concrete volume:88 cum including the extra quantity of
concrete for curvatures and bends etc.,)
B. MACHINERY:
Sl.No Particulars Unit Qty Rate in Rs.
Amount
1 Batching plant Hour 8 405.40 3243.20
2 Transit mixer 3 Nos Hour 24 758.40 18201.60
Fuel / Energy charges Hour 24 872.70 20944.80
3 Mechanical paver Hour 8 356.50 2852.00
lubricants etc @ 5% Hour 8 17.83 142.60
4 DG set for batching plant 50 KVA Hour 8 85.10 680.80
Fuel / Energy charges Hour 8 952.10 7616.80
5 DG set for paver 30 KVA Hour 8 65.80 526.40
Fuel / Energy charges Hour 8 634.70 5077.60
6 Shovel 0.5 cum / Loader Hour 2.00 1003.10 2006.20
171
Canal and Allied Works - Item Unit Rates 2016-17
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Batching plant Hour 8.00 340.60 2724.80
2 Crew for Transit mixer Hour 24.00 283.90 6813.60
3 Crew for Concrete paver Hour 8.00 421.80 3374.40
4 Crew for DG set Hour 16.00 131.80 2108.80
5 Crew for Shovel Hour 2.00 236.60 473.20
6 Crew for Water tanker Hour 8 177.50 1420.00
7 Crew for Pump Hour 8 111.10 888.80
8 Mason Class I Day 2 445.00 890.00
9 Mechanic Day 1 475.00 475.00
10 Fitter Day 1 475.00 475.00
11 Electrician Day 1 515.00 515.00
12 work inspector Day 2 450.00 900.00
13 mazdoor ( BP site ) Day 5 350.00 1750.00
14 mazdoor ( Paver site ) Day 10 350.00 3500.00
Total cost of Labour Rs: 26308.60
labour component/unit qty 32.90
Add contractor's profit and overhead charges 13.615% 4.50
labour component/unit qty (including contractor's profit) 37.40
ABSTRACT
A. Cost of Materials Rs. 253729
B. Hire charges of Machinery Rs. 68579.2
C. Cost of Labour Rs. 26308.60
TOTAL Rs. 348616.8
Add for shifting & re-erection of BP @ 2% Rs. 6972.336
Add for LH / RH shifting & erection of Paver @ 0.5% Rs. 1743.084
Add for ledge cutting / erection of tracks etc @ 1% Rs. 3486.168
Total Rs: 360818.39
D. Add for contractor's profit and overheads on (A+B+C+other 13.615% Rs: 49125.42
Lead Charges for 1 Km for FA 39.60 cum @ 31.5 Rs./Cum 1247.4
Lead Charges for 1 Km for CA 70.40 cum @ 30.4 Rs./Cum2140.16
Total cost for 800.00 Sqm Rs: 413331.37
Rate per Sqm (A+B+C+D)/800.0 Rs. 516.70
IRR-CAW-7-9 Dismantling, shifting and re-erecting mechanical concrete paver and DG set with all
accessories across canal CD work or other locations wherever shifting and re-erecting is
necessary including aligning paver correctly for continuing canal lining work, cost of all
materials, machinery, labour etc., complete with all leads and lifts.
Note: Local shifting and re-erection of paver for LH and RH side lining included in concrete lining rates
under items IRR-CAW-7-7 and IRR-CAW-7-8 and saperate rate for shifting shall not be allowed.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
172
Canal and Allied Works - Item Unit Rates 2016-17
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Tipper Hour 4.00 177.50 710
2 Crew for Paver Hour 8.00 421.80 3374.4
3 mazdoor Day 6.00 350.00 2100
Total cost of Labour Rs: 6184.40
labour component/unit qty 6184.40
Add contractor's profit and overhead charges 13.615% 842.00
labour component/unit qty (including contractor's profit) 7026.40
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 2116.70
C. Cost of Labour Rs: 6184.40
Total Rs: 8301.10
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 1130.19
Total cost for 1.00 Shifting Rs: 9431.29
Rate per Shifting (A+B+C+D)/1.0 Rs. 9431.30
IRR-CAW-7-10 Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than
10 N /sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for bed and side lining of canal(150mm thick) including finishing the junction of bed and sides
to required curveture, cost of all materials, machinery, labour, formwork including supports,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts. ( Cement content : 250 kg / cum )
( 43 Gr Cement content: 250 kg / cum for use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
173
Canal and Allied Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Concrete mixer Hour 16.00 219.70 3515.2
2 Crew for Pump Hour 0.50 111.10 55.55
3 Crew for Water tanker Hour 1.00 177.50 177.5
4 Crew for Needle vibrator Hour 16.00 158.20 2531.2
5 work inspector Day 1.00 450.00 450
6 Mason Class-I Day 2.00 445.00 890
7 Fitter Day 1.00 475.00 475
8 mazdoor
for batching materials Day 22.00 350.00 7700
for loading mortar pans Day 8.00 350.00 2800
for laying and moving paver Day 6.00 350.00 2100
for conveying concrete Day 28.17 350.00 9859.5
for cleaning/ washing/ curing Day 2.00 350.00 700
Total cost of Labour Rs: 31253.95
labour component/unit qty 1109.50
Add contractor's profit and overhead charges 13.615% 151.10
labour component/unit qty (including contractor's profit) 1260.60
ABSTRACT:
A. Cost of Materials Rs: 74857.33
B. Hire charges of Machinery Rs: 5191.95
C. Cost of Labour Rs: 31253.95
Total Rs: 111303.23
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 15153.93
Total cost for 28.17 cum Rs: 126457.16
Rate per cum (A+B+C+D)/28.17 Rs. 4489.10
IRR-CAW-7-11 Providing and laying insitu vibrated M-10 (28 days cube compressive strength not less than
10 N/sqm) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregade for bed and side lining of canal(100 mm thick) including, finishing the junction of bed and sides
to required curvature, cost of all materials, machinery, labour, formwork including supports
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead up to 50 m and all lifts (Cement content: 250 kg/cum)
( 43 Gr Cement content: 250 kg / cum for use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
A. MATERIALS:
Sl.No Particulars Unit Qty Rate in Rs. Amount
1 Cement for mix kg 6750 5.35 36112.50
174
Canal and Allied Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl.No Particulars Unit Qty Rate in Rs. Amount
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Concrete mixer Hour 16.00 219.70 3515.2
2 Crew for Pump Hour 0.50 111.10 55.55
3 Crew for Water tanker Hour 1.00 177.50 177.5
4 Crew for Needle vibrator Hour 16.00 158.20 2531.2
5 work inspector Day 1.00 450.00 450
6 Mason Class-I Day 2.00 445.00 890
7 Fitter Day 1.00 475.00 475
8 mazdoor
for batching materials Day 22.00 350.00 7700
for loading mortar pans Day 8.00 350.00 2800
for laying and moving paver Day 6.00 350.00 2100
for conveying concrete Day 27.00 350.00 9450
for cleaning/ washing/ curing Day 2.00 350.00 700
Total cost of Labour Rs: 30844.45
labour component/unit qty 1142.40
Add contractor's profit and overhead charges 13.615% 155.50
labour component/unit qty (including contractor's profit) 1297.90
ABSTRACT:
A. Cost of Materials including royalty charges Rs. 74382.66
B. Hire charges of Machinery Rs. 4875.15
C. Cost of Labour Rs. 30844.45
Total Rs. 110102.26
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 14990.42
Total cost for 27.00 cum Rs: 125092.68
Rate per cum (A+B+C+D)/27.0 Rs. 4633.10
IRR-CAW-7-12 Providing and laying100mm thick insitu vibrated M-10 (28 days cube compressive strength-not less than
10.00 N / sq mm) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for bed and side lining of canal lining using vibrating cylindertype mechanical paver
including cost of all materials mechinery labour batching mixing placing in position forming
contraction joints fixing pvc joint seiling strips shifting of paver from one side of canal to other
side etc.complete with 1 km lead & all lifts.
(Cement content: 250 kg / cum for use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
175
Canal and Allied Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl.No Particulars Unit Qty Rate in Rs. Amount
1 Batching plant Hour 8.00 405.40 3243.2
2 Transit mixer 3 Nos Hour 24.00 758.40 18201.6
Fuel / Energy charges Hour 24.00 872.70 20944.8
3 Mechanical paver Hour 5.00 356.50 1782.5
lubricants etc @ 5% Hour 5.00 17.83 89.125
4 DG set for batching plant 50 KVA Hour 8.00 85.10 680.8
Fuel / Energy charges Hour 8.00 952.10 7616.8
5 DG set for paver 30 KVA Hour 8.00 65.80 526.4
Fuel / Energy charges Hour 8.00 634.70 5077.6
6 Shovel 0.5 cum / Loader Hour 2.00 1003.10 2006.20
Fuel / Energy charges Hour 2.00 476.00 952.00
7 Water tanker Hour 8.00 402.50 3220
Fuel / Energy charges Hour 8.00 299.90 2399.2
Pump 5 hp (diesel) 2 Nos. 4 hrs
8 each Hour 8.00 10.20 81.6
Fuel / Energy charges Hour 8.00 79.30 634.4
Total hire charges of Machinery Rs. 67456.23
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Batching plant Hour 8.00 340.60 2724.80
2 Crew for Transit mixer Hour 24.00 283.90 6813.60
3 Crew for Concrete paver Hour 8.00 421.80 3374.40
4 Crew for DG set Hour 16.00 131.80 2108.80
5 Crew for Shovel Hour 2.00 236.60 473.20
6 Crew for Water tanker Hour 8 177.50 1420.00
7 Crew for Pump Hour 8 111.10 888.80
8 Mason Class I Day 2 445.00 890.00
9 Mechanic Day 1 475.00 475.00
10 Fitter Day 1 475.00 475.00
11 Electrician Day 1 515.00 515.00
12 work inspector Day 2 450.00 900.00
13 mazdoor ( BP site ) Day 5 350.00 1750.00
14 mazdoor ( Paver site ) Day 10 350.00 3500.00
Total cost of Labour Rs: 26308.60
labour component/unit qty 32.90
Add contractor's profit and overhead charges 13.615% 4.50
labour component/unit qty (including contractor's profit) 37.40
ABSTRACT:
A. Cost of Materials Rs. 240463.00
B. Hire charges of Machinery Rs. 67456.23
C. Cost of Labour Rs. 26308.60
TOTAL Rs.334227.83
Add for shifting & re-erection of BP @ 2% Rs. 6684.56
Add for LH / RH shifting & erection of Paver @ 0.5% Rs. 1671.14
Add for ledge cutting / erection of tracks etc @ 1% Rs. 3342.28
Total Rs: 345925.81
D. Add for contractor's profit and overheads on (A+B+C+other 13.615% Rs: 47097.8
Lead Charges for 1 Km for FA 35.20 cum @ 31.5 Rs./Cum 1108.8
Lead Charges for 1 Km for CA 79.20 cum @ 30.4 Rs./Cum2407.68
Total cost for 800.00 Sqm Rs: 396540.09
Rate per Sqm (A+B+C+D)/800.0 Rs. 495.70
176
Canal and Allied Works - Item Unit Rates 2016-17
IRR-CAW-7-13 Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than
10 N /sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for bed and side lining of canal including finishing the junction of bed and sides
to required curveture, cost of all materials, machinery, labour, formwork including supports,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts. ( Cement content : 250 kg / cum )
(Cement content: 250 kg / cum for use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Concrete mixer Hour 16.00 219.70 3515.2
2 Crew for Pump Hour 0.50 111.10 55.55
3 Crew for Water tanker Hour 1.00 177.50 177.5
4 Crew for Vibrator Hour 16.00 158.20 2531.20
5 Mason Class-I Day 2.00 445.00 890
6 work inspector Day 1.00 450.00 450
7 Fitter Day 1.00 475.00 475
8 mazdoor
for batching materials Day 22.00 350.00 7700
for loading mortar pans Day 8.00 350.00 2800
for laying and moving paver Day 6.00 350.00 2100
for conveying concrete Day 27.00 350.00 9450
for cleaning/ washing/ curing Day 2.00 350.00 700
Total cost of Labour Rs: 30844.45
labour component/unit qty 1142.40
Add contractor's profit and overhead charges 13.615% 155.50
labour component/unit qty (including contractor's profit) 1297.90
ABSTRACT:
A. Cost of Materials Rs: 70993.41
B. Hire charges of Machinery Rs: 5191.95
177
Canal and Allied Works - Item Unit Rates 2016-17
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 14572.11
Total cost for 27.00 cum Rs: 121601.92
Rate per cum (A+B+C+D)/27.0 Rs. 4503.80
IRR-CAW-7-14 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than
15 N /sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for bed and side lining of canal(150 mm thick) including finishing the junction of bed and sides
to required curveture, cost of all materials, machinery, labour, formwork including supports,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.
(Cement content: 290 kg / cum for use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Concrete mixer Hour 16.00 219.70 3515.2
2 Crew for Pump Hour 0.50 111.10 55.55
3 Crew for Water tanker Hour 1.00 177.50 177.5
4 Crew for Vibrator Hour 16.00 158.20 2531.20
5 Mason Class-I Day 2.00 445.00 890
6 work inspector Day 1.00 450.00 450
7 Fitter Day 1.00 475.00 475
8 mazdoor
for batching materials Day 22.00 350.00 7700
for loading mortar pans Day 8.00 350.00 2800
for laying Day 6.00 350.00 2100
for conveying concrete Day 24.92 350.00 8722
for cleaning/ washing/ curing Day 2.00 350.00 700
Total cost of Labour Rs: 30116.45
178
Canal and Allied Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 71970.80
B. Hire charges of Machinery Rs: 5191.95
C. Cost of Labour Rs: 30116.45
Total Rs: 107279.20
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 14606.06
Total cost for 24.92 cum Rs: 121885.26
Rate per cum (A+B+C+D)/24.92 Rs. 4891.10
IRR-CAW-7-15 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than
15 N /sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for bed and side lining of canal(100 mm thick) including finishing the junction of bed and sides
to required curveture, cost of all materials, machinery, labour, formwork including supports,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.
(Cement content: 300 kg / cum for use of super plasticiser(0.4% by wt. of cement),
CA : 0.80 cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Concrete mixer Hour 16.00 219.70 3515.2
2 Crew for Pump Hour 0.50 111.10 55.55
3 Crew for Water tanker Hour 1.00 177.50 177.5
4 Crew for Vibrator Hour 16.00 158.20 2531.2
5 Mason Class-I Day 2.00 445.00 890
6 work inspector Day 1.00 450.00 450
7 Fitter Day 1.00 475.00 475
8 mazdoor
179
Canal and Allied Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 67180.82
B. Hire charges of Machinery Rs: 5191.95
C. Cost of Labour Rs: 29479.45
Total Rs: 101852.22
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 13867.18
Total cost for 23.10 cum Rs: 115719.40
Rate per cum (A+B+C+D)/23.10 Rs. 5009.50
IRR-CAW-7-16 Providing and laying150mm thick insitu vibrated M-15 (28 days cube compressive strength-not less than
15.00 N / sq mm) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for bed and side lining of canal lining using vibrating cylindertype mechanical paver
including cost of all materials mechinery labour batching mixing placing in position forming
contractiom joints fixing pvc joint seiling strips shifting of paver from one side of canal to other
side etc.complete with 1km lead & all lifts.
(43 Gr Cement content: 300 kg /cum (45 kg/ sqm) for
use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35,
FA : 0.44 cum equivalent concrete volume:132 cum including the extra quantity of
concrete for curvatures and bends etc.,)
B. MACHINERY:
Sl.No Particulars Unit Qty Rate in Rs. Amount
1 Batching plant Hour 8.00 405.40 3243.2
2 Transit mixer 3 Nos Hour 24.00 758.40 18201.6
Fuel / Energy charges Hour 24.00 872.70 20944.8
3 Mechanical paver Hour 5.00 356.50 1782.5
lubricants etc @ 5% Hour 5.00 17.83 89.125
4 DG set for batching plant 50 KVA Hour 8.00 85.10 680.8
Fuel / Energy charges Hour 8.00 952.10 7616.8
5 DG set for paver 30 KVA Hour 8.00 65.80 526.4
Fuel / Energy charges Hour 8.00 634.70 5077.6
6 Shovel 0.5 cum / Loader Hour 2.00 1003.10 2006.20
Fuel / Energy charges Hour 2.00 476.00 952.00
7 Water tanker Hour 8.00 402.50 3220
Fuel / Energy charges Hour 8.00 299.90 2399.2
Pump 5 hp (diesel) 2 Nos. 4 hrs
8 each Hour 8.00 10.20 81.6
Fuel / Energy charges Hour 8.00 79.30 634.4
Total hire charges of Machinery Rs. 67456.23
180
Canal and Allied Works - Item Unit Rates 2016-17
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Batching plant Hour 8.00 340.60 2724.80
2 Crew for Transit mixer Hour 24.00 283.90 6813.60
3 Crew for Concrete paver Hour 8.00 421.80 3374.40
4 Crew for DG set Hour 16.00 131.80 2108.80
5 Crew for Shovel Hour 2.00 236.60 473.20
6 Crew for Water tanker Hour 8 177.50 1420.00
7 Crew for Pump Hour 8 111.10 888.80
8 Mason Class I Day 2 445.00 890.00
9 Mechanic Day 1 475.00 475.00
10 Fitter Day 1 475.00 475.00
11 Electrician Day 1 515.00 515.00
12 work inspector Day 2 450.00 900.00
13 mazdoor ( BP site ) Day 5 350.00 1750.00
14 mazdoor ( Paver site ) Day 10 350.00 3500.00
Total cost of Labour Rs: 26308.60
labour component/unit qty 32.90
Add contractor's profit and overhead charges 13.615% 4.50
labour component/unit qty (including contractor's profit) 37.40
ABSTRACT
A. Cost of Materials Rs. 368124.60
B. Hire charges of Machinery Rs. 67456.23
C. Cost of Labour Rs. 26308.60
TOTAL Rs.461889.43
Add for shifting & re-erection of BP @ 2% Rs. 9237.79
Add for LH / RH shifting & erection of Paver @ 0.5% Rs. 2309.45
Add for ledge cutting / erection of tracks etc @ 1% Rs. 4618.89
Total Rs: 478055.56
D. Add for contractor's profit and overheads on (A+B+C+other 13.615% Rs: 65087.26
Lead Charges for 1 Km for FA 58.08 cum @ 31.5 Rs./Cum1829.52
Lead Charges for 1 Km for CA 105.60 cum @ 30.4 Rs./Cum3210.24
Total cost for 800.00 Sqm Rs: 548182.58
Rate per Sqm (A+B+C+D)/800.0 Rs. 685.20
IRR-CAW-7-17 Providing and fixing pre-cast RCC template walls consisting of 0.05 cum M-15 grade
concrete using 20 mm down size coarse aggregates and 10 kg reinforcement steel moulded
as per specifications and drawing in CM 1:4 proportion including cost of all materials,
machinery, labour, formwork, fabricating and placing reinforcement steel, mixing, laying,
conveying and fixing in position including necessary excavation for seating, finishing joints in
CM 1:4, curing etc., complete with initial lead upto 1 km and all lifts.
181
Canal and Allied Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Hand mixer Hour 8.00 5.50 44
8.00 0.00 0
Total hire charges of Machinery Rs: 44.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 1.00 450.00 450
2 Mason Class I for fixing Day 1.00 445.00 445
3 Mason Class II for casting Day 2.00 400.00 800
4 Bar bender Day 1.00 555.00 555
5 mazdoor ( casting yard ) Day 4.00 350.00 1400
mazdoor ( for fixing ) Day 2.00 350.00 700
mazdoor for conveying Day 2.00 350.00 700
Total cost of Labour Rs: 5050.00
labour component/unit qty 252.50
Add contractor's profit and overhead charges 13.615% 34.40
labour component/unit qty (including contractor's profit) 286.90
ABSTRACT:
A. Cost of Materials including serignorage charges Rs: 10760.30
B. Hire charges of Machinery Rs: 44.00
C. Cost of Labour Rs: 5050.00
Total Rs: 15854.30
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 2158.56
Lead Charges for 1 Km for FA 0.50 cum @ 31.5 Rs./Cum 15.75
Lead Charges for 1 Km for CA 0.80 cum @ 30.4 Rs./Cum 24.32
Lead Charges for 1Km for Steel (including Loading
and Unloading Charges) 0.20 tonne @ 168.6 Rs./Tonne
33.72
Total cost for 20.00 templete Rs: 18086.65
Rate per templete (A+B+C+D)/20.0 Rs. 904.30
IRR-CAW-7-18 Providing and fixing 50 mm dia perforated GI pressure relief pipes 12.50 cm long with
one end closed with perforated GI plate and other end provided with alluminium lid hinged
to pipe including cost of all materials, labour, drilling 8 mm dia holes etc., complete with all
leads and lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Drilling 8 mm dia holes LS 0.50 30.00 15
0.00
Total hire charges of Machinery Rs: 15.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
182
Canal and Allied Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 687.50
B. Hire charges of Machinery Rs: 15.00
C. Cost of Labour Rs: 430.00
Total Rs: 1132.50
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 154.19
Total cost for 10.00 Nos. Rs: 1286.69
Rate per each (A+B+C+D)/10.0 Rs. 128.70
IRR-CAW-7-19 Providing and fixing 50 mm dia perforated GI pressure relief pipes 22.50 cm long with
one end closed with perforated GI plate and other end provided with alluminium lid hinged
to pipe including cost of all materials, labour, drilling 8 mm dia holes etc., complete with all
leads and lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Drilling 8 mm dia holes LS 5.00 30.00 150
0.00
Total hire charges of Machinery Rs: 150.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Pipe fitter Day 0.50 510.00 255
mazdoor Day 0.50 350.00 175
Total cost of Labour Rs: 430.00
labour component/unit qty 43.00
Add contractor's profit and overhead charges 13.615% 5.90
labour component/unit qty (including contractor's profit) 48.90
ABSTRACT:
A. Cost of Materials Rs: 997.50
B. Hire charges of Machinery Rs: 150.00
C. Cost of Labour Rs: 430.00
Total Rs: 1577.50
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 214.78
Total cost for 10.00 Nos. Rs: 1792.28
Rate per No. (A+B+C+D)/10.0 Rs. 179.20
IRR-CAW-7-20 Providing and fixing 50 mm dia perforated GI pressure relief pipes 30 cm long with
one end closed with perforated GI plate and other end provided with alluminium lid hinged
to pipe including cost of all materials, labour, drilling 8 mm dia holes etc., complete with all
leads and lifts.
183
Canal and Allied Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Drilling 8 mm dia holes LS 7.00 30.00 210.00
0.00
Total hire charges of Machinery Rs: 210.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Pipe fitter Day 0.50 510.00 255.00
mazdoor Day 0.50 350.00 175.00
Total cost of Labour Rs: 430.00
labour component/unit qty 43.00
Add contractor's profit and overhead charges 13.615% 5.90
labour component/unit qty (including contractor's profit) 48.90
ABSTRACT:
A. Cost of Materials Rs: 1230.00
B. Hire charges of Machinery Rs: 210.00
C. Cost of Labour Rs: 430.00
Total Rs: 1870.00
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 254.6
Total cost for 10.00 Nos. Rs: 2124.60
Rate per No. (A+B+C+D)/10.0 Rs. 212.50
IRR-CAW-7-21 Providing and fixing 50 mm dia perforated GI pressure relief pipes 45 cm long with
one end closed with perforated GI plate and other end provided with alluminium lid hinged
to pipe including cost of all materials, labour, drilling 8 mm dia holes etc., complete with all
leads and lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Drilling 8 mm dia holes LS 10.00 30.00 300.00
0.00
Total hire charges of Machinery Rs: 300.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Pipe fitter Day 0.50 510.00 255.00
mazdoor Day 0.50 350.00 175.00
184
Canal and Allied Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 1695.00
B. Hire charges of Machinery Rs: 300.00
C. Cost of Labour Rs: 430.00
Total Rs: 2425.00
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 330.16
Total cost for 10.00 Nos. Rs: 2755.16
Rate per No. (A+B+C+D)/10.0 Rs. 275.50
IRR-CAW-7-22 Providing and fixing 50 mm dia perforated GI pressure relief pipes 75 cm long with
one end closed with perforated GI plate and other end provided with alluminium lid hinged
to pipe including cost of all materials, labour, drilling 8 mm dia holes etc., complete with all
leads and lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Drilling 8 mm dia holes LS 15.00 30.00 450.00
0.00
Total hire charges of Machinery Rs: 450.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Pipe fitter Day 0.50 510.00 255.00
2 mazdoor Day 0.50 350.00 175.00
Total cost of Labour Rs: 430.00
labour component/unit qty 43.00
Add contractor's profit and overhead charges 13.615% 5.90
labour component/unit qty (including contractor's profit) 48.90
ABSTRACT:
A. Cost of Materials Rs: 2625.00
B. Hire charges of Machinery Rs: 450.00
C. Cost of Labour Rs: 430.00
Total Rs: 3505.00
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 477.21
Total cost for 10.00 Nos. Rs: 3982.21
Rate per No. (A+B+C+D)/10.0 Rs. 398.20
IRR-CAW-7-23 Providing and fixing 100 mm dia perforated PVC pipes 40 cm long for Weep holes
including cost of all materials, labour, drilling 8 mm dia holes etc. complete with all
leads and lifts.
185
Canal and Allied Works - Item Unit Rates 2016-17
A. MATERIALS:
Rate in Amount in
Sl.No Particulars Unit Qty Rs Rs.
1 PVC pipe 100 mm dia 10 Nos Rm 10.00 170.00 1700.00
Total cost of Materials Rs. 1700.00
B. MACHINERY
Rate in Amount in
Sl.No Description Unit Quantity
Rs. Rs.
1 Nill 0.00 0.00
0.00 0.00
Total hire chargs of Machinery Rs. 0.00
C. LABOUR
Rate in Amount in
Sl.No Particulars Unit Qty Rs Rs.
1 Pipe fitter Day 0.25 510.00 127.50
2 Mazdoor Day 0.25 350.00 87.50
Total cost of Labour Rs. 215.00
labour component/unit qty 21.50
Add contractor's profit and overhead charges 13.615% 2.90
labour component/unit qty (including contractor's profit) 24.40
ABSTRACT
A. Cost of Materials Rs. 1700.00
B. Hire charges of Machinery Rs. 0.00
C. Cost of Labour Rs. 215.00
Total Rs: 1915.00
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 260.73
Total cost for 10.00 Nos. Rs: 2175.73
Rate per No. (A+B+C+D)/10.0 Rs. 217.60
IRR-CAW-7-24 Drilling 32 mm dia pressure relief hole below pressure relief pipe for bed and side lining of
canal laid on rock including cost of all materials, machinery, labour etc., complete with all
leads and lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Air compressor 8.5 cmm diesel Hour 1.00 275.60 275.60
Fuel / Energy charges Hour 1.00 892.50 892.50
2 Jack hammer 2 Nos. Hour 2.00 19.80 39.60
Fuel / Energy charges Hour 2.00 0.00 0.00
Total hire charges of Machinery Rs: 1207.70
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Air compressor Hour 1.00 210.90 210.90
2 Crew for Jack hammer Hour 2.00 329.60 659.20
Total cost of Labour Rs: 870.10
labour component/unit qty 87.00
Add contractor's profit and overhead charges 13.615% 11.80
labour component/unit qty (including contractor's profit) 98.80
186
Canal and Allied Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 318.51
B. Hire charges of Machinery Rs: 1207.70
C. Cost of Labour Rs: 870.10
Total Rs: 2396.31
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 326.26
Total cost for 10.00 Nos. Rs: 2722.57
Rate per No. (A+B+C+D)/10.0 Rs. 272.30
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nil 0.00 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Mason Cl- II Day 0.10 400.00 40.00
2 mazdoor Day 0.10 350.00 35.00
Total cost of Labour Rs: 75.00
labour component/unit qty 7.50
Add contractor's profit and overhead charges 13.615% 1.00
labour component/unit qty (including contractor's profit) 8.50
ABSTRACT:
A. Cost of Materials Rs: 168.25
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 75.00
Total Rs: 243.25
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 33.12
Total cost for 10.00 Nos. Rs: 276.37
Rate per No. (A+B+C+D)/10.0 Rs. 27.60
IRR-CAW-7-26 Providing and fixing 25 to 40 mm thick Shahabad / Talikota / other similar stone slabs
with pointing and finishing joints neatly in CM 1:3 proportion for canal / field channel lining
including cutting slabs to required size, mixing mortar, finishing joints neatly, curing etc.,
complete with lead upto 50 m and all lifts.
187
Canal and Allied Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 5 hp pump ( diesel ) Hour 2.00 10.20 20.40
Fuel / Energy charges Hour 2.00 79.30 158.60
Total hire charges of Machinery Rs: 179.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Operator pump Hour 2.00 111.10 222.20
2 work inspector Day 1.00 450.00 450.00
3 Mason Class I Day 4.00 445.00 1780.00
4 Mason Class II Day 2.00 400.00 800.00
5 mazdoor Day 8.00 350.00 2800.00
Cartman with Double Bullock cart for
6 water Day 1.00 465.00 465.00
Total cost of Labour Rs: 6517.20
labour component/unit qty 65.20
Add contractor's profit and overhead charges 13.615% 8.90
labour component/unit qty (including contractor's profit) 74.10
ABSTRACT:
A. Cost of Materials Rs: 25811.00
B. Hire charges of Machinery Rs: 179.00
C. Cost of Labour Rs: 6517.20
Total Rs: 32507.20
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 4425.86
Total cost for 100.00 sqm Rs: 36933.06
Rate per sqm (A+B+C+D)/100.0 Rs. 369.30
IRR-CAW-7-27 Fixing PCC slabs of various sizes in CM 1 : 3 proportion to the side slopes of canal
including preparing bed, flush pointing joints in CM 1 : 3 propn, cost of all materials ( excluding
PCC slabs ), labour, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 5 hp pump ( diesel ) Hour 2.00 10.20 20.40
Fuel / Energy charges Hour 2.00 79.30 158.60
Total hire charges of Machinery Rs: 179.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Operator pump Hour 2.00 111.10 222.20
2 work inspector Day 1.00 450.00 450.00
3 Mason Class I Day 4.00 445.00 1780.00
4 mazdoor Day 9.00 350.00 3150.00
Cartman with Double Bullock cart for
5 water Day 1.00 465.00 465.00
188
Canal and Allied Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 1366.50
B. Hire charges of Machinery Rs: 179.00
C. Cost of Labour Rs: 6067.20
Total Rs: 7612.70
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 1036.47
Total cost for 100.00 sqm Rs: 8649.17
Rate per sqm (A+B+C+D)/100.0 Rs. 86.50
IRR-CAW-7-28 Fixing PCC lug slabs of various sizes in CM 1 : 3 proportion for supporting PCC slab lining
including necessary excavation, refilling, flush pointing joints in CM 1 : 3 propn, cost of all
materials ( excluding PCC lug slabs ), labour, finishing, curing etc., complete with initial lead
upto 50 m and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 5 hp pump ( diesel ) Hour 1.00 10.20 10.20
Fuel / Energy charges Hour 1.00 79.30 79.30
Total hire charges of Machinery Rs: 89.50
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Operator pump Hour 1.00 111.10 111.10
2 work inspector Day 1.00 450.00 450.00
3 Mason Class I Day 2.00 445.00 890.00
4 Mason Class II Day 1.00 400.00 400.00
5 mazdoor Day 5.00 350.00 1750.00
Cartman with Double Bullock cart for
6 water Day 1.00 465.00 465.00
Total cost of Labour Rs: 4066.10
labour component/unit qty 40.70
Add contractor's profit and overhead charges 13.615% 5.50
labour component/unit qty (including contractor's profit) 46.20
ABSTRACT:
A. Cost of Materials Rs: 330.10
B. Hire charges of Machinery Rs: 89.50
C. Cost of Labour Rs: 4066.10
Total Rs: 4485.70
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 610.73
Total cost for 100.00 Rm Rs: 5096.43
Rate per Rm (A+B+C+D)/100.0 Rs. 51.00
IRR-CAW-7-29 Fixing 30 cm height pre-cast drops for field channels as directed including excavation, etc.,
complete with all leads and lifts.
189
Canal and Allied Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nill 0.00 0.00
0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 1.00 450.00 450.00
2 Mason Cl- II Day 1.00 400.00 400.00
3 mazdoor Day 1.00 350.00 350.00
Total cost of Labour Rs: 1200.00
labour component/unit qty 171.40
Add contractor's profit and overhead charges 13.615% 23.30
labour component/unit qty (including contractor's profit) 194.70
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 1200.00
Total Rs: 1200.00
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 163.38
Total cost for 7.00 Nos. Rs: 1363.38
Rate per No. (A+B+C+D)/7.00 Rs. 194.80
IRR-CAW-7-30 Providing and fixing LDPE sheet for bed and sides of canal including cost of all materials,
labour, laying, joining etc., complete with all leads and lifts.
a. Using 500 micron thick LDPE sheet.
190
Canal and Allied Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nill 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
Joining & laying @ 10 % of sheet
1 cost sqm 250.00 9.20 2300.00
2 mazdoor Day 1.00 350.00 350.00
Total cost of Labour Rs: 2650.00
labour component/unit qty 10.60
Add contractor's profit and overhead charges 13.615% 1.40
labour component/unit qty (including contractor's profit) 12.00
ABSTRACT:
A. Cost of Materials Rs: 25484.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 2650.00
Total Rs: 28134.00
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 3830.44
Total cost for 250.00 sqm Rs: 31964.44
Rate per sqm (A+B+C+D)/250.0 Rs. 127.90
Note : i ) If the surface on which the LDPE sheet is to be laid is too rough and undulating provide
average 75 mm thick sand backing to LDPE sheet.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nill 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 mazdoor Day 6.00 350.00 2100.00
Total cost of Labour Rs: 2100.00
labour component/unit qty 8.40
Add contractor's profit and overhead charges 13.615% 1.10
labour component/unit qty (including contractor's profit) 9.50
ABSTRACT:
A. Cost of Materials Rs: 1781.25
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 2100.00
Total Rs: 3881.25
191
Canal and Allied Works - Item Unit Rates 2016-17
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 528.43
Total cost for 250.00 sqm Rs: 4409.68
Rate per sqm (A+B+C+D)/250.0 Rs. 17.60
IRR-CAW-7-31 Providing and fixing LDPE sheet for bed and sides of canal including cost of all materials,
labour, laying, joining etc., complete with all leads and lifts.
b. Using 750 micron thick LDPE sheet.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nill 0.00 0.00
0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
Joining & laying @ 10 % of sheet
1 cost sqm 250.00 13.50 3375.00
2 mazdoor Day 1.00 350.00 350.00
Total cost of Labour Rs: 3725.00
labour component/unit qty 14.90
Add contractor's profit and overhead charges 13.615% 2.00
labour component/unit qty (including contractor's profit) 16.90
ABSTRACT:
A. Cost of Materials Rs: 37309.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 3725.00
Total Rs: 41034.00
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 5586.78
Total cost for 250.00 sqm Rs: 46620.78
Rate per sqm (A+B+C+D)/250.0 Rs. 186.50
Note : i ) If the surface on which the LDPE sheet is to be laid is too rough and undulating provide
average 75 mm thick unscreened sand backing to LDPE sheet.
For providing average 75 mm thick sand backing add per sqm Rs: 17.60
IRR-CAW-7-32 Providing and fixing LDPE sheet for bed and sides of canal including cost of all materials,
labour, laying, joining etc., complete with all leads and lifts.
c. Using 1000 micron thick LDPE sheet.
192
Canal and Allied Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nill 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
Joining & laying @ 10 % of sheet
1 cost sqm 250.00 18.50 4625.00
2 mazdoor Day 1.00 350.00 350.00
Total cost of Labour Rs: 4975.00
labour component/unit qty 19.90
Add contractor's profit and overhead charges 13.615% 2.70
labour component/unit qty (including contractor's profit) 22.60
ABSTRACT:
A. Cost of Materials Rs: 51059.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 4975.00
Total Rs: 56034.00
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 7629.03
Total cost for 250.00 sqm Rs: 63663.03
Rate per sqm (A+B+C+D)/250.0 Rs. 254.70
Note : i ) If the surface on which the LDPE sheet is to be laid is too rough and undulating provide
average 75 mm thick unscreened sand backing to LDPE sheet.
For providing average 75 mm thick sand backing add per sqm Rs: 17.60
IRR-CAW-7-33 Providing and fixing 12 mm thick 380 mm depth tarfelt expansion joint filler boards for
stone masonry lining of canal including cost of all materials, labour etc., complete with all
leads and lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nill 0.00 0.00
0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Carpenter Cl- II Day 1.00 400.00 400.00
2 mazdoor Day 1.00 350.00 350.00
Total cost of Labour Rs: 750.00
labour component/unit qty 7.50
Add contractor's profit and overhead charges 13.615% 1.00
labour component/unit qty (including contractor's profit) 8.50
ABSTRACT:
A. Cost of Materials Rs: 16081.25
193
Canal and Allied Works - Item Unit Rates 2016-17
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 2291.57
Total cost for 100.00 Rm Rs: 19122.82
Rate per Rm (A+B+C+D)/100.00 Rs. 191.20
IRR-CAW-7-34 Providing and fixing 20 mm thick 100 mm depth tarfelt expansion joint filler boards for
cement concrete lining of canal including cost of all materials, labour etc., complete with all
leads and lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nill 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Carpenter Cl- II Day 1.00 400.00 400.00
2 mazdoor Day 1.00 350.00 350.00
Total cost of Labour Rs: 750.00
labour component/unit qty 7.50
Add contractor's profit and overhead charges 13.615% 1.00
labour component/unit qty (including contractor's profit) 8.50
ABSTRACT:
A. Cost of Materials Rs: 6300.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 750.00
Total Rs: 7050.00
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 959.86
Total cost for 100.00 Rm Rs: 8009.86
Rate per Rm (A+B+C+D)/100.00 Rs. 80.10
IRR-CAW-7-35 Providing and fixing 20 mm thick 150 mm depth tarfelt expansion joint filler boards for
cement concrete lining of canal including cost of all materials, labour etc., complete with all
leads and lifts.
194
Canal and Allied Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nill 0.00 0.00
0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Carpenter Cl- II Day 1.00 400.00 400.00
2 mazdoor Day 1.00 350.00 350.00
Total cost of Labour Rs: 750.00
labour component/unit qty 7.50
Add contractor's profit and overhead charges 13.615% 1.00
labour component/unit qty (including contractor's profit) 8.50
ABSTRACT:
A. Cost of Materials Rs: 9639.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 750.00
Total Rs: 10389.00
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 1414.46
Total cost for 100.00 Rm Rs: 11803.46
Rate per Rm (A+B+C+D)/100.00 Rs. 118.00
IRR-CAW-7-36 Providing and forming 35 mm wide and 10 mm thick construction / contraction joints
for concrete lining by mastic filler including cost of all materials, labour etc., complete with
all leads and lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nill 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Mason Cl- II Day 0.50 400.00 200.00
2 mazdoor Day 1.00 350.00 350.00
Total cost of Labour Rs: 550.00
labour component/unit qty 5.50
Add contractor's profit and overhead charges 13.615% 0.70
labour component/unit qty (including contractor's profit) 6.20
ABSTRACT:
A. Cost of Materials Rs: 1616.60
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 550.00
Total Rs: 2166.60
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 294.98
Total cost for 100.00 Rm Rs: 2461.58
195
Canal and Allied Works - Item Unit Rates 2016-17
IRR-CAW-7-37 Manufacturing 550 x 550 x 55 mm size PCC lining slabs in M-15 grade ( 28 days cube
compressive strength not less than 15 N /sqmm ) cement concrete using 20 mm down graded
coarse aggregate including cost of all materials, machinery, labour, batching, mixing, laying,
compacting, formwork, finishing, curing etc.,complete with initial lead upto 50 m and all lifts.
( Cement content : 300 kg / cum with super plastcizer (0.4% by wt. of cement),
CA : 0.80 cum, Blending Ratio of CA : 65:35, FA : 0.45cum
equivalent concrete volume: 3.74 cum)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
428.00
1 Concrete mixer 300/200 ltr ( diesel) Hour 8.00 53.50
Fuel / Energy charges Hour 8.00 79.30 634.40
2 5 hp pump ( diesel ) Hour 0.10 10.20 1.02
Fuel / Energy charges Hour 0.10 79.30 7.93
3 Water tanker 8000 ltr Hour 0.20 402.50 80.50
Fuel / Energy charges Hour 0.20 299.90 59.98
Total hire charges of Machinery Rs: 1211.83
Aportioned hire charges of
machinery for lining slab 90% Rs: 1090.65
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Concrete mixer Hour 8.00 219.70 1757.60
2 Crew for Pump Hour 0.10 111.10 11.11
3 Crew for Water tanker Hour 0.20 177.50 35.50
4 Mason Class-I Day 2.00 445.00 890.00
5 work inspector Day 1.00 450.00 450.00
6 mazdoor
for batching materials / laying CC Day 3.00 350.00 1050.00
for demoulding / oiling / laying Day 2.00 350.00 700.00
for shifting slabs to curing pond Day 1.00 350.00 350.00
for stacking after curing Day 1.00 350.00 350.00
for cleaning & miscellaneous Day 1.00 350.00 350.00
Total cost of Labour Rs: 5944.21
Aportioned cost of labour for lining
slabs 90% Rs: 5349.79
labour component/unit qty 23.80
Add contractor's profit and overhead charges 13.615% 3.20
labour component/unit qty (including contractor's profit) 27.00
ABSTRACT:
A. Cost of Materials Rs: 12211.82
B. Hire charges of Machinery Rs: 1090.65
C. Cost of Labour Rs: 5349.79
Total Rs: 18652.26
196
Canal and Allied Works - Item Unit Rates 2016-17
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 2539.51
Total cost for 225.00 Nos. Rs: 21191.77
Rate per each (A+B+C+D)/225.0 Rs. 94.20
IRR-CAW-7-38 Manufacturing 550 x 300 x 55 mm size PCC lug slabs in M-15 grade ( 28 days cube
compressive strength not less than 15 N / sqmm ) cement concrete using 20 mm down graded
coarse aggregate including cost of all materials, machinery, labour, batching, mixing, laying,
compacting, formwork, finishing, curing etc.,complete with initial lead upto 50 m and all lifts.
( Cement content : 300 kg / cum with super plastcizer (0.4% by wt. of cement),
CA : 0.80 cum, Blending Ratio of CA : 65:35, FA : 0.45cum,
equivalent concrete volume: 0.23 cum)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
428.00
1 Concrete mixer 300/200 ltr ( diesel) Hour 8.00 53.50
Fuel / Energy charges Hour 8.00 79.30 634.40
2 5 hp pump ( diesel ) Hour 0.10 10.20 1.02
Fuel / Energy charges Hour 0.10 79.30 7.93
3 Water tanker 8000 ltr Hour 0.20 402.50 80.50
Fuel / Energy charges Hour 0.20 299.90 59.98
Total hire charges of Machinery Rs: 1211.83
Aportioned hire charges of
machinery for lug slabs 10% Rs: 121.18
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Concrete mixer Hour 8.00 219.70 1757.60
2 Crew for Pump Hour 0.10 111.10 11.11
3 Crew for Water tanker Hour 0.20 177.50 35.50
4 Mason Class-I Day 2.00 445.00 890.00
5 work inspector Day 1.00 450.00 450.00
6 mazdoor
for batching materials / laying CC Day 3.00 350.00 1050.00
for demoulding / oiling / laying Day 2.00 350.00 700.00
for shifting slabs to curing pond Day 1.00 350.00 350.00
for stacking after curing Day 1.00 350.00 350.00
for cleaning & miscellaneous Day 1.00 350.00 350.00
Total cost of Labour Rs: 5944.21
Aportioned cost of labourfor lug
slabs 10% Rs: 594.42
labour component/unit qty 23.80
Add contractor's profit and overhead charges 13.615% 3.20
labour component/unit qty (including contractor's profit) 27.00
ABSTRACT:
A. Cost of Materials Rs: 753.28
197
Canal and Allied Works - Item Unit Rates 2016-17
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 199.99
Total cost for 25.00 Nos. Rs: 1668.88
Rate per each (A+B+C+D)/25.0 Rs. 66.80
IRR-CAW-7-39 Manufacturing 450 x 300 x 30 mm size PCC lining slabs in M-15 grade ( 28 days cube
compressive strength not less than 15 N / sqmm ) cement concrete using 10 mm down graded
coarse aggregate including cost of all materials, machinery, labour, batching, mixing, laying,
compacting, formwork, finishing, curing etc.,complete with initial lead upto 50 m and all lifts.
( Cement content : 300 kg / cum with super plastcizer (0.4% by wt. of cement),
CA : 0.68 cum, FA : 0.43cum)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Hand mixer 45 / 30 ltr Hour 8.00 5.50 44.00
Fuel / Energy charges Hour 8.00 0.00 0.00
2 5 hp pump ( diesel ) Hour 0.10 10.20 1.02
Fuel / Energy charges Hour 0.10 79.30 7.93
3 Water tanker 8000 ltr Hour 0.20 402.50 80.50
Fuel / Energy charges Hour 0.20 299.90 59.98
Total hire charges of Machinery Rs: 193.43
Aportioned hire charges of
machinery for lining slab 90% Rs: 174.09
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Pump Hour 0.10 111.10 11.11
2 Crew for Water tanker Hour 0.20 177.50 35.50
3 Mason Class-I Day 2.00 445.00 890.00
4 work inspector Day 1.00 450.00 450.00
5 mazdoor
for batching / mixing / laying Day 2.00 350.00 700.00
for demoulding / cleaning / oiling Day 2.00 350.00 700.00
for shifting slabs to curing pond Day 1.00 350.00 350.00
for stacking after curing Day 1.00 350.00 350.00
for cleaning & miscellaneous Day 1.00 350.00 350.00
Total cost of Labour Rs: 3836.61
Aportioned cost of labour for lining
slabs 90% Rs: 3452.95
labour component/unit qty 15.30
Add contractor's profit and overhead charges 13.615% 2.10
labour component/unit qty (including contractor's profit) 17.40
ABSTRACT:
A. Cost of Materials Rs: 3219.09
198
Canal and Allied Works - Item Unit Rates 2016-17
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 932.1
Total cost for 225.00 Nos. Rs: 7778.22
Rate per each (A+B+C+D)/225.0 Rs. 34.60
IRR-CAW-7-40 Manucturing 450 x 150 x 30 mm size PCC lug slabs in M-15 grade ( 28 days cube
compressive strength not less than 15 N / sqmm ) cement concrete using 10 mm down graded
coarse aggregate including cost of all materials, machinery, labour, batching, mixing, laying,
compacting, formwork, finishing, curing etc.,complete with initial lead upto 50 m and all lifts.
( Cement content : 300 kg / cum with super plastcizer (0.4% by wt. of cement),
CA : 0.68 cum, FA : 0.43cum)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Hand mixer 45 / 30 ltr Hour 8.00 5.50 44.00
Fuel / Energy charges Hour 8.00 0.00 0.00
2 5 hp pump ( diesel ) Hour 0.10 10.20 1.02
Fuel / Energy charges Hour 0.10 79.30 7.93
3 Water tanker 8000 ltr Hour 0.20 402.50 80.50
Fuel / Energy charges Hour 0.20 299.90 59.98
Total hire charges of Machinery Rs: 193.43
Aportioned hire charges of
machinery for lug slabs 10% Rs: 19.34
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Pump Hour 0.10 111.10 11.11
2 Crew for Water tanker Hour 0.20 177.50 35.50
3 Mason Class-I Day 2.00 445.00 890.00
4 work inspector Day 1.00 450.00 450.00
5 mazdoor
for batching / mixing / laying Day 2.00 350.00 700.00
for demoulding / cleaning / oiling Day 2.00 350.00 700.00
for shifting slabs to curing pond Day 1.00 350.00 350.00
for stacking after curing Day 1.00 350.00 350.00
for cleaning & miscellaneous Day 1.00 350.00 350.00
Total cost of Labour Rs: 3836.61
Aportioned cost of labour for lug
slabs 10% Rs: 383.66
labour component/unit qty 15.30
Add contractor's profit and overhead charges 13.615% 2.10
labour component/unit qty (including contractor's profit) 17.40
ABSTRACT:
A. Cost of Materials Rs: 188.08
199
Canal and Allied Works - Item Unit Rates 2016-17
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 80.48
Total cost for 25.00 Nos. Rs: 671.56
Rate per each (A+B+C+D)/25.0 Rs. 26.90
IRR-CAW-7-41 Manufacturing 600 x 300 x 100mm size PCC lining slabs in M-15 grade (28 days cube
compressive strength not less than 15 N/Sqmm) cement concrete using 20mm down
grades coarse aggregate including cost of all materials, machinery, labour, batching,
mixing, laying, compacting, formwork, finishing, curing etc., complete with initial lead upto 50 m
and all lifts.
( Cement content : 300 kg / cum with super plastcizer (0.4% by wt. of cement),
CA : 0.80 cum, FA : 0.45cum, Blending Ratio of CA--65:35)
A. MATERIALS :
B. MACHINERY :
C. LABOUR :
Sl. No Particulars Unit Quantity Rate Amount in
in Rs. Rs.
1 Crew for Pump Hour 0.1 111.10 11.11
2 Crew for water tanker Hour 0.2 177.50 35.50
3 Mason Class-I Day 2 445.00 890.00
4 Class II Mason Day 1 400.00 400.00
5 Mazdoor
For batching materials/laying Day 2 350.00 700.00
For demoulding/cleaning/oiling 2 350.00 700.00
For shifting slabs to curing pond 1 350.00 350.00
For stacking after curing 1 350.00 350.00
For cleaning & miscellaneous Day 1 350.00 350.00
Total Cost of Labour Rs. 3786.61
Aportioned cost of labour for lining 90% 3407.95
slabs Rs.
200
Canal and Allied Works - Item Unit Rates 2016-17
ABSTRACT :
A. Cost of Materials Rs. 11419.763
B. Hire Charges of machinery Rs. 1090.65
C. Cost of Labour Rs. 3407.95
Total Rs: 15918.36
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 2167.28
Total cost for 225.00 Nos. Rs: 18085.64
Rate per each (A+B+C+D)/225.0 Rs. 80.40
IRR-CAW-7-42 Manucturing 400 x 400 x 30 mm size PCC lining slabs in M-15 grade ( 28 days cube
compressive strength not less than 15 N / sqmm )cement concrete using 10 mm down graded
coarse aggregate including cost of all materials, machinery, labour, batching, mixing, laying,
compacting, formwork, finishing, curing etc.,complete with initial lead upto 50 m and all lifts.
( Cement content : 300 kg / cum with super plastcizer (0.4% by wt. of cement),
CA : 0.68 cum, FA : 0.43cum)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Hand mixer 45 / 30 ltr Hour 8.00 5.50 44.00
Fuel / Energy charges Hour 8.00 0.00 0.00
2 5 hp pump ( diesel ) Hour 0.10 10.20 1.02
Fuel / Energy charges Hour 0.10 79.30 7.93
3 Water tanker 8000 ltr Hour 0.20 402.50 80.50
Fuel / Energy charges Hour 0.20 299.90 59.98
Total hire charges of Machinery Rs: 193.43
Aportioned hire charges of
machinery for lining slab 90% Rs: 174.09
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Pump Hour 0.10 111.10 11.11
2 Crew for Water tanker Hour 0.20 177.50 35.50
3 Mason Class-I Day 2.00 445.00 890.00
4 work inspector Day 1.00 450.00 450.00
5 mazdoor
for batching / mixing / laying Day 2.00 350.00 700.00
for demoulding / cleaning / oiling Day 2.00 350.00 700.00
for shifting slabs to curing pond Day 1.00 350.00 350.00
for stacking after curing Day 1.00 350.00 350.00
for cleaning & miscellaneous Day 1.00 350.00 350.00
Total cost of Labour Rs: 3836.61
Aportioned cost of labour for lining
slabs 90% Rs: 3452.95
201
Canal and Allied Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 3642.79
B. Hire charges of Machinery Rs: 174.09
C. Cost of Labour Rs: 3452.95
Total Rs: 7269.83
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 989.79
Total cost for 225.00 Nos. Rs: 8259.62
Rate per each (A+B+C+D)/225.0 Rs. 36.70
IRR-CAW-7-43 Manufacturing 400 x 150 x 30 mm size PCC lug slabs in M-15 grade ( 28 days cube
compressive strength not less than 15 N /sqmm ) cement concrete using 10 mm down graded
coarse aggregate including cost of all materials, machinery, labour, batching, mixing, laying,
compacting, formwork, finishing, curing etc.,complete with initial lead upto 50 m and all lifts.
( Cement content : 300 kg / cum with super plastcizer (0.4% by wt. of cement),
CA : 0.68 cum, FA : 0.43cum)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Hand mixer 45 / 30 ltr Hour 8.00 5.50 44.00
Fuel / Energy charges Hour 8.00 0.00 0.00
2 5 hp pump ( diesel ) Hour 0.10 10.20 1.02
Fuel / Energy charges Hour 0.10 79.30 7.93
3 Water tanker 8000 ltr Hour 0.20 402.50 80.50
Fuel / Energy charges Hour 0.20 299.90 59.98
Total hire charges of Machinery Rs: 193.43
Aportioned hire charges of
machinery for lug slabs 10% Rs: 19.34
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Pump Hour 0.10 111.10 11.11
2 Crew for Water tanker Hour 0.20 177.50 35.50
3 Mason Class-I Day 2.00 445.00 890.00
4 work inspector Day 1.00 450.00 450.00
5 mazdoor
for batching / mixing / laying Day 2.00 350.00 700.00
for demoulding / cleaning / oiling Day 2.00 350.00 700.00
for shifting slabs to curing pond Day 1.00 350.00 350.00
for stacking after curing Day 1.00 350.00 350.00
for cleaning & miscellaneous Day 1.00 350.00 350.00
Total cost of Labour Rs: 3836.61
Aportioned cost of labour for lug
slabs 10% Rs: 383.66
202
Canal and Allied Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 175.71
B. Hire charges of Machinery Rs: 19.34
C. Cost of Labour Rs: 383.66
Total Rs: 578.71
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 78.79
Total cost for 25.00 Nos. Rs: 657.50
Rate per each (A+B+C+D)/25.0 Rs. 26.30
IRR-CAW-7-44 Providing and laying uncoursed rubble stone masonry in CM 1 : 5 proportion for canal side
lining using stones and chips from approved quarry including cost of all materials,
machinery, labour, forming weep holes at specified intervals, finishing, curing etc., complete
with initial lead upto 50 m and all lifts.
(Thickness of the masonry assumed: 0.3 m, rubble stones : 0.96 cum, Stone Chips : 0.15cum,
Through Stones 20 x 20 x 30cm : 1/sqm)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 5 hp pump ( diesel ) Hour 4.00 10.20 40.80
Fuel / Energy charges Hour 4.00 79.30 317.20
Total hire charges of Machinery Rs: 358.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Operator pump Hour 4.00 111.10 444.40
2 work inspector Day 1.00 450.00 450.00
3 Mason Class I Day 2.00 445.00 890.00
4 Mason Class II Day 2.00 400.00 800.00
5 mazdoor Day 8.00 350.00 2800.00
Cartman with Double Bullock cart for 465.00
6 water Day 1.00 465.00
Total cost of Labour Rs: 5849.40
labour component/unit qty 584.90
Add contractor's profit and overhead charges 13.615% 79.60
labour component/unit qty (including contractor's profit) 664.50
ABSTRACT:
A. Cost of Materials Rs: 11105.00
B. Hire charges of Machinery Rs: 358.00
C. Cost of Labour Rs: 5849.40
Total Rs: 17312.40
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 2357.08
Total cost for 10.00 cum Rs: 19669.48
Rate per cum (A+B+C+D)/10.0 Rs. 1966.90
203
Canal and Allied Works - Item Unit Rates 2016-17
IRR-CAW-7-45 Providing and laying uncoursed rubble stone masonry in CM 1:5 proportion for canal side
lining using stones from approved quarry including cost of all materials, machinery,
labour, forming weep holes at specified intervals, finishing, curing etc., complete
with initial lead upto 50m and all lifts.(without pin headers) : 1.1 cum)
(Thickness of the Masonry assumed: 0.3 m , rubble stones
A.
MATERIALS
:
B. MACHINERY :
C. LABOUR :
ABSTRACT :
A. Cost of Materials Rs. 9297.72
B. Hire Charges of Machinery Rs. 481.3
C. Cost of Labour Rs. 19244.40
Total Rs: 29023.42
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 3951.54
Total cost for 10.00 Cum Rs: 32974.96
Rate per Cum (A+B+C+D)/10.0 Rs. 3297.50
IRR-CAW-7-46 Providing and laying uncoursed rubble stone masonry in CM 1 : 5 proportion for canal side
lining using stones and chips from canal excavation including cost of all materials,
machinery, labour, forming weep holes at specified interval, finishing, curing etc., complete
with initial lead upto 50 m and all lifts.
( rubble stones : 0.96 cum, Stone Chips : 0.15cum, Through Stones 20 x 20 x 30cm : 1/sqm)
204
Canal and Allied Works - Item Unit Rates 2016-17
Note: Stones and chips will be issued from dump yard at specified issue rate.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 5 hp pump ( diesel ) Hour 4.00 10.20 40.80
Fuel / Energy charges Hour 4.00 79.30 317.20
Total hire charges of Machinery Rs: 358.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Operator pump Hour 4.00 111.10 444.40
2 work inspector Day 1.00 450.00 450.00
3 Mason Class I Day 2.00 445.00 890.00
4 Mason Class II Day 2.00 400.00 800.00
5 Crowbarman Day 1.00 400.00 400.00
6 mazdoor Day 9.00 350.00 3150.00
Cartman with Double Bullock cart for 465.00
7 water Day 1.00 465.00
Total cost of Labour Rs: 6599.40
labour component/unit qty 659.90
Add contractor's profit and overhead charges 13.615% 89.80
labour component/unit qty (including contractor's profit) 749.70
ABSTRACT:
A. Cost of Materials Rs: 9249.90
B. Hire charges of Machinery Rs: 358.00
C. Cost of Labour Rs: 6599.40
Total Rs: 16207.30
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 2206.62
Total cost for 10.00 cum Rs: 18413.92
Rate per cum (A+B+C+D)/10.0 Rs. 1841.40
IRR-CAW-7-47 Providing and laying uncoursed rubble stone masonry in CM 1:5 proportion for canal side lining
using stones from canal excavation including cost of all materials, machinery, labour, forming weep holes at
specified intervals, finishing, curing etc., complete with initial lead upto 50m and all lifts.
( rubble stones : 1.1cum, cement : 98kg, sand 0.34 cum)
B. MACHINERY :
205
Canal and Allied Works - Item Unit Rates 2016-17
C. LABOUR :
ABSTRACT :
A. Cost of Materials Rs. 7509
B. Hire Charges of Machinery Rs. 481.3
C. Cost of Labour Rs. 19244.40
Total Rs: 27234.70
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 3708
Total cost for 10.00 Cum Rs: 30942.70
Rate per Cum (A+B+C+D)/10.0 Rs. 3094.30
IRR-CAW-8-1 Providing and constructing 25 cm thick dry rubble stone pitching with pin headers at 2 per
sqm including cost of all materials, labour, hand packing, finishing etc., complete with initial
lead upto 50 m and all lifts.
( rubble stones : 0.23 cum/sqm, Stone Chips : 0.0375cum/sqm, Pin Headers 30cm : 2/sqm)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nill 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 1.00 450.00 450.00
2 Mason Class II Day 5.00 400.00 2000.00
3 mazdoor Day 6.00 350.00 2100.00
Total cost of Labour Rs: 4550.00
206
Canal and Allied Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 13026.50
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 4550.00
Total Rs: 17576.50
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 2393.04
Total cost for 100.00 sqm Rs: 19969.54
Rate per sqm (A+B+C+D)/100.0 Rs. 199.70
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nill 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 mazdoor Day 4.00 350.00 1400.00
Total cost of Labour Rs: 1400.00
labour component/unit qty 14.00
Add contractor's profit and overhead charges 13.615% 1.90
labour component/unit qty (including contractor's profit) 15.90
ABSTRACT:
A. Cost of Materials Rs: 2970.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 1400.00
Total Rs: 4370.00
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 594.98
Total cost for 100.00 sqm Rs: 4964.98
Rate per sqm (A+B+C+D)/100.0 Rs. 49.60
IRR-CAW-8-1-A Providing and constructing 22.5 cm thick dry rubble stone pitching with pin headers at 2 per
(New Item4 - 2011-
12) sqm including cost of all materials, labour, hand packing, finishing etc., complete with initial
lead upto 50 m and all lifts.
( rubble stones : 0.207 cum/sqm, Stone Chips : 0.03375cum/sqm, Pin Headers 30cm : 2/sqm)
(For Maintenance works)
207
Canal and Allied Works - Item Unit Rates 2016-17
4400.00
2 Pin header (Through stone) 30 cm Nos 200.00 22.00
3 Stone chips at quarry cum 3.375 350.00 1181.25
Total cost of Materials Rs: 12163.85
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nill 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 1.00 450.00 450.00
2 Mason Class II Day 5.00 400.00 2000.00
3 mazdoor Day 6.00 350.00 2100.00
Total cost of Labour Rs: 4550.00
labour component/unit qty 45.50
Add contractor's profit and overhead charges 13.615% 6.20
labour component/unit qty (including contractor's profit) 51.70
ABSTRACT:
A. Cost of Materials Rs: 12163.85
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 4550.00
Total Rs: 16713.85
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 2275.59
Total cost for 100.00 sqm Rs: 18989.44
Rate per sqm (A+B+C+D)/100.0 Rs. 189.90
IRR-CAW-8-2 Providing and constructing 25 cm thick dry rubble stone pitching including cost of all materials, labour,
hand packing, finishing etc., complete
( rubble stones : 0.275 cum/sqm)
B. MACHINERY :
C. LABOUR :
208
Canal and Allied Works - Item Unit Rates 2016-17
ABSTRACT :
A. Cost of Materials Rs. 8745
B. Hire Charges of Machinery Rs. 0
C. Cost of Labour Rs. 10862.50
Total Rs: 19607.50
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 2669.56
Total cost for 100.00 Sqm. Rs: 22277.06
Rate per Sqm. (A+B+C+D)/100.0 Rs. 222.80
If 15 cm thick murum bed is to be
NOTE: provided below pitching add in Rs. 49.60
( As per rate analysis under item IRR-CAW-8-1- Note )
IRR-CAW-8-2-A Providing and constructing 225 mm thick dry rubble stone pitching including cost of all materials, labour,
(New Item5 - 2011-
12) hand packing, finishing etc., complete
( rubble stones : 0.2475 cum/sqm) (For Maintenance Works)
B. MACHINERY :
C. LABOUR :
ABSTRACT :
A. Cost of Materials Rs. 4778.75
B. Hire Charges of Machinery Rs. 0
C. Cost of Labour Rs. 9776.25
Total Rs: 14555.00
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 1981.66
Total cost for 100.00 Sqm. Rs: 16536.66
Rate per Sqm. (A+B+C+D)/100.0 Rs. 165.40
IRR-CAW-8-3 Providing and constructing 30 cm thick dry rubble stone pitching with pin headers at 2 per
sqm including cost of all materials, labour, hand packing, finishing etc., complete with initial
lead upto 50 m and all lifts.
( rubble stones : 0.275 cum/sqm, Stone Chips : 0.045cum/sqm, Pin Headers 30cm : 2/sqm)
209
Canal and Allied Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nill 0.00 0.00
0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 1.00 450.00 450.00
2 Mason Class II Day 5.00 400.00 2000.00
3 mazdoor Day 6.00 350.00 2100.00
Total cost of Labour Rs: 4550.00
labour component/unit qty 45.50
Add contractor's profit and overhead charges 13.615% 6.20
labour component/unit qty (including contractor's profit) 51.70
ABSTRACT:
A. Cost of Materials Rs: 14720.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 4550.00
Total Rs: 19270.00
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 2623.61
Total cost for 100.00 sqm Rs: 21893.61
Rate per sqm (A+B+C+D)/100.0 Rs. 218.90
If 15 cm thick murum bed is to be
NOTE: provided below pitching add 49.60
( As per rate analysis under item
IRR-CAW-8-1- Note )
10494.00
1 Uncoursed rubble stones at Quarry Cum 33.00
318.00
B.MACHINERY :
Rate Amount
Sl No Description Unit Quantity
in Rs in Rs
210
Canal and Allied Works - Item Unit Rates 2016-17
C.LABOUR :
Rate Amount
Sl No Description Unit Quantity
in Rs in Rs
ABSTRACT
A.Cost of Materials including ryolty charges Rs: 10494.00
B. Hire charges of Machinery Rs: 0.00
C.Cost of Labour Rs: 13035.00
Total Rs: 23529.00
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 3203.47
Total cost for 100.00 sqm Rs: 26732.47
Rate per sqm (A+B+C+D)/100.0 Rs. 267.30
If 15 cm thick murum bed is to be
NOTE: provided below pitching Rs : 49.60
Add ( As per rate analysis under
item IRR-CAW-8-1 - Note)
IRR-CAW-8-5 Providing and constructing 45 cm thick dry rubble stone pitching with pin headers at 2 per
sqm including cost of all materials, labour, hand packing, finishing etc., complete with initial
lead upto 50 m and all lifts.
( rubble stones : 0.40 cum/sqm, Stone Chips : 0.0675cum/sqm, Pin Headers 45cm : 2/sqm)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nill 0.00 0.00
0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 1.00 450.00 450.00
2 Mason Class II Day 7.00 400.00 2800.00
3 mazdoor Day 9.00 350.00 3150.00
Total cost of Labour Rs: 6400.00
labour component/unit qty 64.00
Add contractor's profit and overhead charges 13.615% 8.70
labour component/unit qty (including contractor's profit) 72.70
ABSTRACT:
A. Cost of Materials Rs: 22882.50
211
Canal and Allied Works - Item Unit Rates 2016-17
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 3986.81
Total cost for 100.00 sqm Rs: 33269.31
Rate per sqm (A+B+C+D)/100.0 Rs. 332.70
If 15 cm thick murum bed is to be
NOTE: provided below pitching add 49.60
( As per rate analysis under item
IRR-CAW-8-1 - Note )
15741.00
1 Uncoursed rubble stones at Quarry Cum 49.50
318.00
( Included in material Rate)
Total Cost of materials Rs : 15741.00
B.MACHINERY :
Rate Amount
Sl No Description Unit Quantity
in Rs in Rs
C.LABOUR :
Rate Amount
Sl No Description Unit Quantity
in Rs in Rs
ABSTRACT
A.Cost of Materials including ryolty charges Rs: 15741.00
B. Hire charges of Machinery Rs: 0.00
C.Cost of Labour Rs: 19552.50
Total Rs: 35293.50
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 4805.21
Total cost for 100.00 sqm Rs: 40098.71
Rate per sqm (A+B+C+D)/100.0 Rs. 401.00
If 15 cm thick murum bed is to be
NOTE: provided below pitching Rs : 49.60
Add ( As per rate analysis under
item IRR-CAW-8-1 - Note)
IRR-CAW-8-7 Providing and constructing 30 cm thick rubble stone pitching set in CM 1: 5 proportion with
pin headers at 2 per sqm in including cost of all materials, labour, packing chips and mortar,
212
Canal and Allied Works - Item Unit Rates 2016-17
finishing, curing etc., complete with initial lead upto 50 m and all lifts.
( rubble stones : 0.275 cum/sqm, Stone Chips : 0.045cum/sqm, Pin Headers 30cm : 2/sqm)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 5 hp pump ( diesel ) 2.00 10.20 20.40
Fuel / Energy charges 2.00 79.30 158.60
Total hire charges of Machinery Rs: 179.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Pump Hour 2.00 111.10 222.20
2 work inspector Day 1.00 450.00 450.00
3 Mason Class II Day 5.00 400.00 2000.00
4 mazdoor Day 12.00 350.00 4200.00
5 Catrman with double bullock cart Day 2.00 465.00 930.00
Total cost of Labour Rs: 7802.20
labour component/unit qty 78.00
Add contractor's profit and overhead charges 13.615% 10.60
labour component/unit qty (including contractor's profit) 88.60
ABSTRACT:
A. Cost of Materials Rs: 32502.50
B. Hire charges of Machinery Rs: 179.00
C. Cost of Labour Rs: 7802.20
Total Rs: 40483.70
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 5511.86
Total cost for 100.00 sqm Rs: 45995.56
Rate per sqm (A+B+C+D)/100.0 Rs. 460.00
If 15 cm thick murum bed is to be
NOTE: provided below pitching add 49.60
( As per rate analysis under item
IRR-CAW-8-1 - Note )
IRR-CAW-8-8 Providing and Constructing 30 cm thick rubble stone pitching set in CM 1:5 Proportion
including cost of all materials,labour, packing chips and mortar ,finishing etc.,complete
( rubble stones : 0.33 cum/sqm )
10494.00
1 Uncoursed rubble stones at Quarry Cum 33.00
318.00
2 Cement Kg 3232.00 5.35 17291.20
3 Sand (Screened) Cum 11.22 165.00 1851.30
Total Cost of materials Rs : 29636.50
213
Canal and Allied Works - Item Unit Rates 2016-17
B.MACHINERY :
Rate Amount
Sl No Description Unit Quantity
in Rs in Rs
C.LABOUR :
Rate Amount
Sl No Description Unit Quantity
in Rs in Rs
ABSTRACT
A.Cost of Materials Rs: 29636.50
B. Hire charges of Machinery Rs: 0.00
C.Cost of Labour Rs: 1724.30
Total Rs: 31360.80
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 4269.77
Total cost for 100.00 Sqm Rs: 35630.57
Rate per Sqm (A+B+C+D)/100.0 Rs. 356.30
If 15 cm thick murum bed is to be
NOTE: provided below pitching Rs : 49.60
Add ( As per rate analysis under
item IRR-CAW-8-1 - Note)
IRR-CAW-8-9 Providing and constructing 30 cm thick dry khandki stone pitching using 20 to 25 cm size
khandki stones with pin headers at 2 per sqm including cost of all materials, labour, hand
packing, finishing etc., complete with initial lead upto 50 m and all lifts.
( Khandki stones 20- 25 cm height : 1200 Nos/sqm, Stone Chips : 0.045cum/sqm,
Pin Headers 30cm : 2/sqm)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nil 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 1.00 450.00 450.00
2 Mason Class II Day 5.00 400.00 2000.00
3 mazdoor Day 6.00 350.00 2100.00
214
Canal and Allied Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 23975.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 4550.00
Total Rs: 28525.00
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 3883.68
Total cost for 100.00 sqm Rs: 32408.68
Rate per sqm (A+B+C+D)/100.0 Rs. 324.10
If 15 cm thick murum bed is to be
NOTE: provided below pitching add 49.60
( As per rate analysis under item
IRR-CAW-8-1 - Note )
IRR-CAW-8-10 Providing and constructing 45 cm thick dry khandki stone pitching using 25 to 30 cm size
khandki stones with pin headers at 2 per sqm including cost of all materials, labour, hand
packing, finishing etc., complete with initial lead upto 50 m and all lifts.
( Khandki stones 25- 30 cm height : 1200 Nos/sqm, Stone Chips : 0.0675cum/sqm,
Pin Headers 45cm : 2/sqm)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nil 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 1.00 450.00 450.00
2 Mason Class II Day 7.00 400.00 2800.00
3 mazdoor Day 9.00 350.00 3150.00
Total cost of Labour Rs: 6400.00
labour component/unit qty 64.00
Add contractor's profit and overhead charges 13.615% 8.70
labour component/unit qty (including contractor's profit) 72.70
ABSTRACT:
A. Cost of Materials Rs: 22572.50
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 6400.00
Total Rs: 28972.50
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 3944.61
Total cost for 100.00 sqm Rs: 32917.11
Rate per sqm (A+B+C+D)/100.0 Rs. 329.20
If 15 cm thick murum bed is to be
NOTE: provided below pitching add 49.60
215
Canal and Allied Works - Item Unit Rates 2016-17
IRR-CAW-8-11 Providing and constructing 30 cm thick khandki stone pitching using 20 to 25 cm size
khandki stones with pin headers at 2 per sqm set in CM 1 : 5 proportion with pointing joints in
CM 1:3 proportion including cost of all materials, labour, packing chips and mortar, finishing,
curing etc.complete with initial lead upto 50 m and all lifts.
( Khandki stones 20- 25 cm height : 1200 Nos/sqm, Stone Chips : 0.045cum/sqm,
Pin Headers 30cm : 2/sqm)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 5 hp diesel pump Hour 2.00 10.20 20.40
Fuel / Energy charges Hour 2.00 79.30 158.60
Total hire charges of Machinery Rs: 179.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Pump Hour 2.00 111.10 222.20
2 work inspector Day 1.00 450.00 450.00
3 Cartman with double bullock cart Day 2.00 465.00 930.00
4 Mason Class II Day 5.00 400.00 2000.00
5 mazdoor Day 11.00 350.00 3850.00
Total cost of Labour Rs: 7452.20
labour component/unit qty 74.50
Add contractor's profit and overhead charges 13.615% 10.10
labour component/unit qty (including contractor's profit) 84.60
ABSTRACT:
A. Cost of Materials Rs: 41096.25
B. Hire charges of Machinery Rs: 179.00
C. Cost of Labour Rs: 7452.20
Total Rs: 48727.45
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 6634.24
Total cost for 100.00 sqm Rs: 55361.69
Rate per sqm (A+B+C+D)/100.0 Rs. 553.60
If 15 cm thick murum bed is to be
NOTE: provided below pitching add 49.60
( As per rate analysis under item
IRR-CAW-8-1 - Note )
IRR-CAW-8-12 Providing and constructing 45 cm thick khandki stone pitching using 25 to 30 cm stones
with pin headers at 2 per sqm set in CM 1 : 5 proportion with pointing joints in CM 1 : 3
proportion including cost of all materials, labour, packing chips and mortar, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.
( Khandki stones 25- 30 cm height : 730 Nos/sqm, Stone Chips : 0.0675cum/sqm,
Pin Headers 45cm : 2/sqm)
216
Canal and Allied Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 5 hp diesel pump Hour 4.00 10.20 40.80
Fuel / Energy charges Hour 4.00 79.30 317.20
Total hire charges of Machinery Rs: 358.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Pump Hour 4.00 111.10 444.40
2 work inspector Day 1.00 450.00 450.00
3 Cartman with double bullock cart Day 2.00 465.00 930.00
4 Mason Class II Day 7.00 400.00 2800.00
5 mazdoor Day 16.00 350.00 5600.00
Total cost of Labour Rs: 10224.40
labour component/unit qty 102.20
Add contractor's profit and overhead charges 13.615% 13.90
labour component/unit qty (including contractor's profit) 116.10
ABSTRACT:
A. Cost of Materials Rs: 46548.35
B. Hire charges of Machinery Rs: 358.00
C. Cost of Labour Rs: 10224.40
Total Rs: 57130.75
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 7778.35
Total cost for 100.00 sqm Rs: 64909.10
Rate per sqm (A+B+C+D)/100.0 Rs. 649.10
If 15 cm thick murum bed is to be
NOTE: provided below pitching add 49.60
( As per rate analysis under item
IRR-CAW-8-1 - Note )
IRR-CAW-8-13 Providing 10 cm thick approved type grass turfing to the side slopes of canal including cost of
all materials, labour, watering for minimum 15 days etc.,complete with lead 50 m and all lifts.
(FA : 2 cum/sqm)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nill 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
217
Canal and Allied Works - Item Unit Rates 2016-17
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 0.10 450.00 45.00
2 Cartman with double bullock cart Day 2.00 465.00 930.00
3 mazdoor Day 14.00 350.00 4900.00
Total cost of Labour Rs: 5875.00
labour component/unit qty 58.80
Add contractor's profit and overhead charges 13.615% 8.00
labour component/unit qty (including contractor's profit) 66.80
ABSTRACT:
A. Cost of Materials Rs: 2990.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 5875.00
Total Rs: 8865.00
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 1206.97
Total cost for 100.00 sqm Rs: 10071.97
Rate per sqm (A+B+C+D)/100.0 Rs. 100.70
IRR-CAW-8-14 Providing 10 cm Thick approved type gross turfing to the side slopes of canal including cost of
all materials ,labour,watering for minimum 15 days etc.,,complete.
with initial lead upto 50 m and all lifts ( WITHOUT USING SAND)
B.MACHINERY :
Rate Amount
Sl No Description Unit Quantity
in Rs in Rs
C.LABOUR :
Rate Amount
Sl No Description Unit Quantity
in Rs in Rs
ABSTRACT
A.Cost of Materials including ryolty charges Rs: 2800.00
B. Hire charges of Machinery Rs: 0.00
C.Cost of Labour Rs: 3380.00
Total Rs: 6180.00
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 841.41
Total cost for 100.00 Sqm Rs: 7021.41
Rate per Sqm (A+B+C+D)/100.0 Rs. 70.20
218
Canal Cross Drainage Works - Item Unit Rates 2016-17
CHAPTER-IV
3. The Leads for Steel shall be from the nearest market place to the Project area
4. For earth/rockfill embankments wherever initial lead of 1km is considered in the basic rate, the additional lead charges are to be
added as follows:
Additional lead charges for Earth, Murrum etc., shall be worked out for total lead involved and 1 km lead charges included
in basic rate shall be deducted from total lead charges. No loading and unloading charges shall be allowed for any item.
(same as above)
Example:
Total lead for earth from approved borrow area : 15 Km
Initial lead included in the basic rate in the SR : 1 Km
Additional lead charges : Lead charges forRs.5 km 84.00
Lead charges for next 10 km Rs. 126
Total lead charges for 15 kmRs./cum 210.00
Less 1 km initial lead charges
Rs./cum 31.50 (-)
Net additional lead chargesRs.
/ cum 178.50
5. The initial lead up to 50 m as mentioned in some standard data items is meant for manual lead within the working area. For
conveyance of materials, the lead required from quarry/Borrow area/ Dump Area to worksite shall be added to the data without
deducting the 50 m initial lead charges
IRR-CCDW-1-1 Excavation in all kinds of soil including boulders upto 0.30 m dia. for foundations of canal
cross drainage and other appurtenant structures and placing the excavated stuff neatly in
specified dump area or disposing off the same as directed etc., complete with initial lead upto
50 m and initial lift upto 3 m.
219
Canal Cross Drainage Works - Item Unit Rates 2016-17
A. MATERIALS:
Sl No Particulars Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total cost of Materials Rs: 0.00
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 0.25 450.00 112.50
2 mazdoor Day 6.00 350.00 2100.00
Total cost of Labour Rs: 2212.50
labour component/unit qty 221.30
Add contractor's profit and overhead charges 13.615% 30.10
labour component/unit qty (including contractor's profit) 251.40
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 2212.50
Total Rs: 2212.50
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 301.23
Total cost for 10.00 cum Rs: 2513.73
Rate per cum (A+B+C+D)/10.0 Rs. 251.40
IRR-CCDW-1-2 Excavation for Structures- Mechanical Means ( Data adopted from MORTH)
Earth work in excavation in all kinds of soils of foundation of structures as per drawing and
technical specification, including setting out, construction of shoring and bracing, removal of stumps
and other deleterious matter, dressing of sides and bottom and backfilling with approved material.
Depth upto 3 m
Unit = cum
DATA: Taking output = 240 cum Unit 240.00 cum
A. Materials:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
NIL 0.00 0.00 0.00
B. Machinery:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Hydraulic excavator 1.0 cum bucket hour 6.00 1706.60 10239.60
capacity
Fuel/ Energy charges hour 6.00 872.70 5236.20
Total in Rs. 15475.80
C. Labour:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector day 0.32 450.00 144.00
2 Mazdoor day 8.00 350.00 2800.00
3 crew for excavator hour 6.00 236.60 1419.60
Total in Rs. 4363.60
labour component/unit qty 18.20
Add contractor's profit and overhead charges 13.615% 2.50
labour component/unit qty (including contractor's profit) 20.70
Abstract
a) Material Rs 0.00
b) Machinery Rs 15475.80
c) Labour Rs 4363.60
Total Rs 19839.40
220
Canal Cross Drainage Works - Item Unit Rates 2016-17
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 2701.13
Total cost for 240.00 cum Rs: 22540.53
Rate per cum (A+B+C+D)/240.0 Rs. 93.90
IRR-CCDW-1-3 Excavation in ordnary rock (including HDR) without blasting including boulders above 0.3 m upto 0.60 m dia.
for foundations of canal cross drainage and other appurtenant structures and placing the
excavated stuff neatly in specified dump area or disposing off the same as directed etc.,
complete with initial lead upto 50 m and initial lift upto 3 m.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crowbarman Day 1.25 400.00 500.00
2 Stone breaker Day 1.25 400.00 500.00
3 work inspector Day 0.25 450.00 112.50
4 mazdoor Day 6.00 350.00 2100.00
Total cost of Labour Rs: 3212.50
labour component/unit qty 321.30
Add contractor's profit and overhead charges 13.615% 43.70
labour component/unit qty (including contractor's profit) 365.00
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 3212.50
Total Rs: 3212.50
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 437.38
Total cost for 10.00 cum Rs: 3649.88
Rate per cum (A+B+C+D)/10.0 Rs. 365.00
IRR-CCDW-1-4 Excavation in ordnary rock without blasting for foundations of canal cross drainage
and other appurtenant structures and placing the excavated stuff neatly in specified dump
area or disposing off the same as directed etc., complete with initial
lead upto 50 m and initial lift upto 3 m.
( Data adopted from MORTH)
Mechanical Means
Unit = cum
DATA: Taking output = 180 cum Unit: 180.00 cum
A. Materials:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
NIL 0.00 0.00 0.00
B. Machinery:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1.0 Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1706.60 10239.60
C. Labour:
Sl No Description Unit Quantity Rate Amount
221
Canal Cross Drainage Works - Item Unit Rates 2016-17
in Rs. in Rs.
1 work inspector day 0.24 450.00 108.00
2 Mazdoor day 6.00 350.00 2100.00
3 crew for excavator hour 6.00 236.60 1419.60
Total in Rs. 3627.60
Abstract
a) Material Rs 0.00
b) Machinery Rs 15475.80
c) Labour Rs 3627.60
Total Rs 19103.40
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 2600.93
Total cost for 180.00 cum Rs: 21704.33
Rate per cum (A+B+C+D)/180.0 Rs. 120.60
IRR-CCDW-1-5 Excavation in hard rock requiring blasting including boulders above 0.6 m upto 1.2 m dia. for
foundations of canal cross drainage and other appurtenant structures and placing the
excavated stuff neatly in specified dump area or disposing off the same as directed etc.,
complete with initial lead upto 50 m and initial lift upto 3 m.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Air compressor 8.5 cmm ( diesel ) Hour 3.00 275.60 826.80
Fuel / Energy charges Hour 3.00 892.50 2677.50
2 Jack hammers 2 Nos. Hour 6.00 19.80 118.80
Fuel / Energy charges Hour 6.00 0.00 0.00
Total hire charges of Machinery Rs: 3623.10
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Air compressor Hour 3.00 210.90 632.70
2 Crew for Jack hammer Hour 6.00 329.60 1977.60
3 work inspector Day 1.00 450.00 450.00
4 Blaster Day 0.50 510.00 255.00
5 Helper blaster Day 0.50 400.00 200.00
6 Crowbarman Day 6.00 400.00 2400.00
7 Stone breaker Day 3.00 400.00 1200.00
8 mazdoor Day 51.00 350.00 17850.00
Total cost of Labour Rs: 24965.30
labour component/unit qty 249.70
Add contractor's profit and overhead charges 13.615% 34.00
labour component/unit qty (including contractor's profit) 283.70
ABSTRACT:
A. Cost of Materials Rs: 3329.09
B. Hire charges of Machinery Rs: 3623.10
C. Cost of Labour Rs: 24965.30
Total Rs: 31917.49
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 4345.57
222
Canal Cross Drainage Works - Item Unit Rates 2016-17
IRR-CCDW-1-6 Excavation in hard rock of all toughness by blasting including boulders above 1.2 m dia. for
foundations of canal cross drainage and other appurtenant structures and placing the
excavated rock neatly in specified dump area or stack yard as directed etc., complete with
initial lead upto 50 m and initial lift upto 3 m.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Air compressor 8.5 cmm ( diesel ) Hour 8.00 275.60 2204.80
Fuel / Energy charges Hour 8.00 892.50 7140.00
2 Jack hammer 2 Nos Hour 16.00 19.80 316.80
Fuel / Energy charges Hour 16.00 0.00 0.00
Total hire charges of Machinery Rs: 9661.60
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Air compressor Hour 8.00 210.90 1687.20
2 Crew for Jack hammer Hour 16.00 329.60 5273.60
3 Blaster licensed Day 1.00 510.00 510.00
4 Helper blasting Day 1.00 400.00 400.00
5 work inspector Day 1.00 450.00 450.00
6 Crowbarman Day 6.00 400.00 2400.00
7 Stone breaker Day 6.00 400.00 2400.00
8 mazdoor Day 51.00 350.00 17850.00
Total cost of Labour Rs: 30970.80
labour component/unit qty 309.70
Add contractor's profit and overhead charges 13.615% 42.20
labour component/unit qty (including contractor's profit) 351.90
ABSTRACT:
A. Cost of Materials Rs: 7878.65
B. Hire charges of Machinery Rs: 9661.60
C. Cost of Labour Rs: 30970.80
Total Rs: 48511.05
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 6604.78
Total cost for 100.00 cum Rs: 55115.83
Rate per cum (A+B+C+D)/100.0 Rs. 551.20
IRR-CCDW-1-7 Excavation in hard rock with blasting prohibited for foundations of canal cross drainage
and other appurtenant structures and placing the excavated rock neatly in
or stack yard as directed etc., complete with specified dump area initial lead upto 50 m and
initial lift upto 3 m.
Hard Rock ( blasting prohibited ) ( Data adopted from MORTH)
Unit = cum
DATA: Taking output = 10 cum
Mechanical Means 10.00 cum
A.Materials:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
223
Canal Cross Drainage Works - Item Unit Rates 2016-17
b) Machinery
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1.0 Air Compressor 250 cft with 2 leads of hour 6.00 241.30 1447.80
pneumatic breaker
Fuel/ Energy charges hour 6.00 714.00 4284.00
Total in Rs. 5731.80
c) Labour
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector day 0.20 450.00 90.00
2 Mazdoor day 5.00 350.00 1750.00
3 crew for compressor hour 6.00 210.90 1265.40
Total in Rs. 3105.40
labour component/unit qty 310.50
Add contractor's profit and overhead charges 13.615% 42.30
labour component/unit qty (including contractor's profit) 352.80
Abstract
a) Material Rs 0.00
b) Machinery Rs 5731.80
c) Labour Rs 3105.40
Total Rs 8837.20
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 1203.18
Total cost for 10.00 cum Rs: 10040.38
Rate per cum (A+B+C+D)/10.0 Rs. 1004.00
IRR-CCDW-1-8 Providing and fixing 25 mm dia 2.50 m long cold twisted deformed steel anchor rods with
1.25 m length driven into 32 mm dia hole drilled in bed rock and remaining length embedded in
concrete / masonry including cost of all materials, machinery, labour, drilling and cleaning
hole, driving anchor rod, grouting hole with thick cement slurry etc., complete with initial lead
upto 50 m and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Air compressor 8.5 cmm ( diesel ) Hour 1.00 275.60 275.60
Fuel / Energy charges Hour 1.00 892.50 892.50
2 Jack hammer 2 Nos Hour 2.00 19.80 39.60
Fuel / Energy charges Hour 2.00 0.00 0.00
Total hire charges of Machinery Rs: 1207.70
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Air compressor Hour 1.00 210.90 210.90
2 Crew for Jack hammer Hour 2.00 329.60 659.20
3 Mason Class-II Day 0.50 400.00 200.00
4 Bar bender Day 0.50 555.00 277.50
5 work inspector Day 0.50 450.00 225.00
6 mazdoor Day 1.00 350.00 350.00
Total cost of Labour Rs: 1922.60
labour component/unit qty 192.30
Add contractor's profit and overhead charges 13.615% 26.20
224
Canal Cross Drainage Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 3853.11
B. Hire charges of Machinery Rs: 1207.70
C. Cost of Labour Rs: 1922.60
Total Rs: 6983.41
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 950.79
Total cost for 10.00 Nos. Rs: 7934.20
Rate per each (A+B+C+D)/10.0 Rs. 793.40
IRR-CCDW-2-1 Providing, fabricating and placing in position reinforcement steel bars for RCC works including
cleaning, straightening, cutting, bending, hooking, lapping, welding wherever required,tying with
1.25 mm dia soft annealed steel wire, including cost of all materials, machinery, labour etc.,
complete with initial lead upto 50 and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nil 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 1.00 450.00 450.00
2 Bar bender Day 6.00 555.00 3330.00
3 mazdoor Day 11.00 350.00 3850.00
Total cost of Labour Rs: 7630.00
labour component/unit qty 7.60
Add contractor's profit and overhead charges 13.615% 1.00
labour component/unit qty (including contractor's profit) 8.60
ABSTRACT:
A. Cost of Materials Rs: 36270.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 7630.00
Total Rs: 43900.00
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 5976.99
Total cost for 1000.00 kg Rs: 49876.99
Rate per kg (A+B+C+D)/1000.0 Rs. 49.90
IRR-CCDW-2-2 Providing, fabricating and fixing in position structural steel cutting edge consisting of 100 x
100 x 10 mm angle and 250 x 12 mm plate for sinking for sinking 4.50 m outer diameter
foundation wells foundation wells including cost of all materials, machinery, labour, bending,
welding, providing anchors etc., complete with initial lead upto 50 m and all lifts.
225
Canal Cross Drainage Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Bending machine Hour 8.00 42.60 340.80
Fuel / Energy charges Hour 8.00 84.10 672.80
2 Welding set Hour 30.00 16.00 480.00
Fuel / Energy charges Hour 30.00 67.20 2016.00
3 Sundries LS 10.00 30.00 300.00
Total hire charges of Machinery Rs: 3809.60
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Str. Steel fabricator Day 2.00 550.00 1100.00
2 Welder / Gas cutter Day 5.00 445.00 2225.00
3 work inspector Day 1.00 450.00 450.00
4 mazdoor Day 5.00 350.00 1750.00
Total cost of Labour Rs: 5525.00
labour component/unit qty 9.00
Add contractor's profit and overhead charges 13.615% 1.20
labour component/unit qty (including contractor's profit) 10.20
ABSTRACT:
A. Cost of Materials Rs: 27110.67
B. Hire charges of Machinery Rs: 3809.60
C. Cost of Labour Rs: 5525.00
Total Rs: 36445.27
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 4962.02
Total cost for 615.00 kg Rs: 41407.29
Rate per kg (A+B+C+D)/615.0 Rs. 67.30
IRR-CCDW-2-3 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than
15 N /sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for foundation filling including cost of all materials, machinery, labour, formwork,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.
(Cement content: 260 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
226
Canal Cross Drainage Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 53.50 428.00
Fuel / Energy charges Hour 8.00 79.30 634.40
2 5 hp pump ( diesel ) Hour 0.50 10.20 5.10
Fuel / Energy charges Hour 0.50 79.30 39.65
3 Water tanker 8000 ltr Hour 1.00 402.50 402.50
Fuel / Energy charges Hour 1.00 299.90 299.90
4 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 7.60 60.80
Fuel / Energy charges Hour 8.00 18.80 150.40
Total hire charges of Machinery Rs: 2020.75
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Concrete mixer Hour 8.00 219.70 1757.60
2 Crew for Pump Hour 0.50 111.10 55.55
3 Crew for Water tanker Hour 1.00 177.50 177.50
4 Crew for Needle vibrator Hour 8.00 158.20 1265.60
5 work inspector Day 1.00 450.00 450.00
6 Mason Class-I Day 1.00 445.00 445.00
7 mazdoor
for batching materials Day 11.00 350.00 3850.00
for loading mortar pans Day 4.00 350.00 1400.00
for laying Day 3.00 350.00 1050.00
for conveying concrete Day 15.38 350.00 5383.00
for cleaning/ washing/ curing Day 1.00 350.00 350.00
8 Labour cost for shuttering sqm 15.38 88.50 1361.13
Labour cost for scaffolding @ 10% 136.11
Total cost of Labour Rs: 17681.49
labour component/unit qty 1149.60
Add contractor's profit and overhead charges 13.615% 156.50
labour component/unit qty (including contractor's profit) 1306.10
ABSTRACT:
A. Cost of Materials Rs: 42629.51
B. Hire charges of Machinery Rs: 2020.75
C. Cost of Labour Rs: 17681.49
Total Rs: 62331.75
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 8486.47
Total cost for 15.38 cum Rs: 70818.22
Rate per cum (A+B+C+D)/15.38 Rs. 4604.60
IRR-CCDW-2-4 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than
15 N / sq mm ) grade cement concrete using 80 mm down size approved, clean, hard, graded
aggregates for foundation filling including cost of all materials, machinery, labour, formwork,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.
(Cement content: 250 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)
227
Canal Cross Drainage Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Concrete mixer 600/400 ltr ( diesel) Hour 8.00 92.70 741.60
Fuel / Energy charges Hour 8.00 158.70 1269.60
2 5 hp pump ( diesel ) Hour 0.50 10.20 5.10
Fuel / Energy charges Hour 0.50 79.30 39.65
3 Water tanker 8000 ltr Hour 1.00 402.50 402.50
Fuel / Energy charges Hour 1.00 299.90 299.90
4 Needle vibrator 60 mm dia ( petrol) Hour 8.00 8.20 65.60
Fuel / Energy charges Hour 8.00 28.20 225.60
Total hire charges of Machinery Rs: 3049.55
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Concrete mixer Hour 8.00 219.70 1757.60
2 Crew for Pump Hour 0.50 111.10 55.55
3 Crew for Water tanker Hour 1.00 177.50 177.50
4 Crew for Needle vibrator Hour 8.00 158.20 1265.60
5 Mason Class-I Day 1.00 445.00 445.00
6 work inspector Day 1.00 450.00 450.00
7 mazdoor
for batching materials Day 11.00 350.00 3850.00
for loading mortar pans Day 4.00 350.00 1400.00
for laying Day 3.00 350.00 1050.00
for conveying concrete Day 14.40 350.00 5040.00
for cleaning/ washing/ curing Day 1.00 350.00 350.00
8 Labour cost for shuttering sqm 14.40 88.50 1274.40
Labour cost for scaffolding @ 10% 127.44
Total cost of Labour Rs: 17243.09
labour component/unit qty 1197.40
Add contractor's profit and overhead charges 13.615% 163.00
labour component/unit qty (including contractor's profit) 1360.40
ABSTRACT:
A. Cost of Materials Rs: 37881.59
B. Hire charges of Machinery Rs: 3049.55
C. Cost of Labour Rs: 17243.09
Total Rs: 58174.23
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 7920.42
Total cost for 14.40 cum Rs: 66094.65
Rate per cum (A+B+C+D)/14.40 Rs. 4589.90
IRR-CCDW-2-5 Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than
10 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for foundation filling including cost of all materials, machinery, labour, formwork,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.
(Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
228
Canal Cross Drainage Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 53.50 428.00
Fuel / Energy charges Hour 8.00 79.30 634.40
2 5 hp pump ( diesel ) Hour 0.50 10.20 5.10
Fuel / Energy charges Hour 0.50 79.30 39.65
3 Water tanker 8000 ltr Hour 1.00 402.50 402.50
Fuel / Energy charges Hour 1.00 299.90 299.90
4 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 7.60 60.80
Fuel / Energy charges Hour 8.00 18.80 150.40
Total hire charges of Machinery Rs: 2020.75
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Concrete mixer Hour 8.00 219.70 1757.60
2 Crew for Pump Hour 0.50 111.10 55.55
3 Crew for Water tanker Hour 1.00 177.50 177.50
4 Crew for Vibrator Hour 8.00 158.20 1265.60
5 Mason Class-I Day 1.00 445.00 445.00
6 work inspector Day 1.00 450.00 450.00
7 mazdoor
for batching materials Day 11.00 350.00 3850.00
for loading mortar pans Day 4.00 350.00 1400.00
for laying Day 3.00 350.00 1050.00
for conveying concrete Day 16.36 350.00 5726.00
8 for cleaning/ washing/ curing Day 1.00 350.00 350.00
9 Labour cost for shuttering sqm 16.36 88.50 1447.86
Total cost of Labour Rs: 17975.11
labour component/unit qty 1098.70
Add contractor's profit and overhead charges 13.615% 149.60
labour component/unit qty (including contractor's profit) 1248.30
ABSTRACT:
A. Cost of Materials Rs: 41699.86
B. Hire charges of Machinery Rs: 2020.75
C. Cost of Labour Rs: 17975.11
Total Rs: 61695.72
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 8399.87
Total cost for 16.36 cum Rs: 70095.59
Rate per cum (A+B+C+D)/16.36 Rs. 4284.60
IRR-CCDW-2-6 Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than
10 N / sq mm ) grade cement concrete using 80 mm down size approved, clean, hard, graded
aggregates for foundation filling including cost of all materials, machinery, labour, formwork,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.
(Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)
229
Canal Cross Drainage Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Concrete mixer 600/400 ltr ( diesel ) Hour 8.00 92.70 741.60
Fuel / Energy charges Hour 8.00 158.70 1269.60
2 5 hp pump ( diesel ) Hour 0.50 10.20 5.10
Fuel / Energy charges Hour 0.50 79.30 39.65
3 Water tanker 8000 ltr Hour 1.00 402.50 402.50
Fuel / Energy charges Hour 1.00 299.90 299.90
4 Needle vibrator 60 mm dia ( petrol ) Hour 8.00 8.20 65.60
Fuel / Energy charges Hour 8.00 28.20 225.60
Total hire charges of Machinery Rs: 3049.55
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Concrete mixer Hour 8.00 219.70 1757.60
2 Crew for Pump Hour 0.50 111.10 55.55
3 Crew for Water tanker Hour 1.00 177.50 177.50
4 Crew for Vibrator Hour 8.00 158.20 1265.60
5 Mason Class-I Day 1.00 445.00 445.00
6 work inspector Day 1.00 450.00 450.00
7 mazdoor
for batching materials Day 11.00 350.00 3850.00
for loading mortar pans Day 4.00 350.00 1400.00
for laying Day 3.00 350.00 1050.00
for conveying concrete Day 14.55 350.00 5092.50
for cleaning/ washing/ curing Day 1.00 350.00 350.00
8 Labour cost for shuttering sqm 14.55 88.50 1287.68
Labour cost for scaffolding @ 10% 128.77
Total cost of Labour Rs: 17310.19
labour component/unit qty 1189.70
Add contractor's profit and overhead charges 13.615% 162.00
labour component/unit qty (including contractor's profit) 1351.70
ABSTRACT:
A. Cost of Materials Rs: 35844.73
B. Hire charges of Machinery Rs: 3049.55
C. Cost of Labour Rs: 17310.19
Total Rs: 56204.47
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 7652.24
Total cost for 14.55 cum Rs: 63856.71
Rate per cum (A+B+C+D)/14.55 Rs. 4388.80
IRR-CCDW-2-7 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for foundation filling including cost of all materials, machinery, labour, formwork,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts. ( Cement content : 220 kg / cum )
(Cement content: 310 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
230
Canal Cross Drainage Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 53.50 428.00
Fuel / Energy charges Hour 8.00 79.30 634.40
2 5 hp pump ( diesel ) Hour 0.50 10.20 5.10
Fuel / Energy charges Hour 0.50 79.30 39.65
3 Water tanker 8000 ltr Hour 1.00 402.50 402.50
Fuel / Energy charges Hour 1.00 299.90 299.90
4 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 7.60 60.80
Fuel / Energy charges Hour 8.00 18.80 150.40
Total hire charges of Machinery Rs: 2020.75
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Concrete mixer Hour 8.00 219.70 1757.60
2 Crew for Pump Hour 0.50 111.10 55.55
3 Crew for Water tanker Hour 1.00 177.50 177.50
4 Crew for Vibrator Hour 8.00 158.20 1265.60
5 Mason Class-I Day 1.00 445.00 445.00
6 work inspector Day 1.00 450.00 450.00
7 mazdoor
for batching materials Day 11.00 350.00 3850.00
for loading mortar pans Day 4.00 350.00 1400.00
for laying Day 3.00 350.00 1050.00
for conveying concrete Day 14.19 350.00 4966.50
for cleaning/ washing/ curing Day 1.00 350.00 350.00
8 Labour cost for shuttering sqm 14.19 88.50 1255.82
Labour cost for scaffolding @ 10% 125.58
Total cost of Labour Rs: 17149.15
labour component/unit qty 1208.50
Add contractor's profit and overhead charges 13.615% 164.50
labour component/unit qty (including contractor's profit) 1373.00
ABSTRACT:
A. Cost of Materials Rs: 43284.20
B. Hire charges of Machinery Rs: 2020.75
C. Cost of Labour Rs: 17149.15
Total Rs: 62454.10
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 8503.13
Total cost for 14.19 cum Rs: 70957.23
Rate per cum (A+B+C+D)/14.19 Rs. 5000.50
IRR-CCDW-2-8 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for sub-structure / super- structure works including cost of all materials,
machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,
levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
(Cement content: 320 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
231
Canal Cross Drainage Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 53.50 428.00
Fuel / Energy charges Hour 8.00 79.30 634.40
2 5 hp pump ( diesel ) Hour 0.50 10.20 5.10
Fuel / Energy charges Hour 0.50 79.30 39.65
3 Water tanker 8000 ltr Hour 1.00 402.50 402.50
Fuel / Energy charges Hour 1.00 299.90 299.90
4 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 7.60 60.80
Fuel / Energy charges Hour 8.00 18.80 150.40
Total hire charges of Machinery Rs: 2020.75
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Concrete mixer Hour 8.00 219.70 1757.60
2 Crew for Pump Hour 0.50 111.10 55.55
3 Crew for Water tanker Hour 1.00 177.50 177.50
4 Crew for Vibrator Hour 8.00 158.20 1265.60
5 Mason Class-I Day 1.00 445.00 445.00
6 work inspector Day 1.00 450.00 450.00
7 mazdoor
for batching materials Day 11.00 350.00 3850.00
for loading mortar pans Day 4.00 350.00 1400.00
for laying including lifting Day 4.00 350.00 1400.00
for conveying concrete Day 15.00 350.00 5250.00
for cleaning/ washing/ curing Day 1.00 350.00 350.00
8 Labour cost for shuttering sqm 15.00 88.50 1327.50
Labour cost for scaffolding @ 25% 331.88
Total cost of Labour Rs: 18060.63
labour component/unit qty 1204.00
Add contractor's profit and overhead charges 13.615% 163.90
labour component/unit qty (including contractor's profit) 1367.90
ABSTRACT:
A. Cost of Materials Rs: 51466.03
B. Hire charges of Machinery Rs: 2020.75
C. Cost of Labour Rs: 18060.63
Total Rs: 71547.41
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 9741.18
Total cost for 15.00 cum Rs: 81288.59
Rate per cum (A+B+C+D)/15.0 Rs. 5419.20
IRR-CCDW-2-9 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for sub-structure / super- structure works including cost of all materials,
machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,
levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
232
Canal Cross Drainage Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 53.50 428.00
Fuel / Energy charges Hour 8.00 79.30 634.40
2 5 hp pump ( diesel ) Hour 0.50 10.20 5.10
Fuel / Energy charges Hour 0.50 79.30 39.65
3 Water tanker 8000 ltr Hour 1.00 402.50 402.50
Fuel / Energy charges Hour 1.00 299.90 299.90
4 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 7.60 60.80
Fuel / Energy charges Hour 8.00 18.80 150.40
Total hire charges of Machinery Rs: 2020.75
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Concrete mixer Hour 8.00 219.70 1757.60
2 Crew for Pump Hour 0.50 111.10 55.55
3 Crew for Water tanker Hour 1.00 177.50 177.50
4 Crew for Vibrator Hour 8.00 158.20 1265.60
5 Mason Class-I Day 1.00 445.00 445.00
6 work inspector Day 1.00 450.00 450.00
7 mazdoor
for batching materials Day 11.00 350.00 3850.00
for loading mortar pans Day 4.00 350.00 1400.00
for laying Day 4.00 350.00 1400.00
for conveying concrete Day 15.76 350.00 5516.00
for cleaning/ washing/ curing Day 1.00 350.00 350.00
8 Labour cost for shuttering sqm 31.52 88.50 2789.52
Labour cost for scaffolding @ 25% 697.38
Total cost of Labour Rs: 20154.15
labour component/unit qty 1278.80
Add contractor's profit and overhead charges 13.615% 174.10
labour component/unit qty (including contractor's profit) 1452.90
ABSTRACT:
A. Cost of Materials Rs: 52937.38
B. Hire charges of Machinery Rs: 2020.75
C. Cost of Labour Rs: 20154.15
Total Rs: 75112.28
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 10226.54
Total cost for 15.76 cum Rs: 85338.817
Rate per cum (A+B+C+D)/15.76 Rs. 5414.90
IRR-CCDW-2-10 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than
15 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for sub-structure / super- structure works including cost of all materials,
machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,
levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
(Cement content: 280 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
233
Canal Cross Drainage Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 53.50 428.00
Fuel / Energy charges Hour 8.00 79.30 634.40
2 5 hp pump ( diesel ) Hour 0.50 10.20 5.10
Fuel / Energy charges Hour 0.50 79.30 39.65
3 Water tanker 8000 ltr Hour 1.00 402.50 402.50
Fuel / Energy charges Hour 1.00 299.90 299.90
4 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 7.60 60.80
Fuel / Energy charges Hour 8.00 18.80 150.40
Total hire charges of Machinery Rs: 2020.75
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Concrete mixer Hour 8.00 219.70 1757.60
2 Crew for Pump Hour 0.50 111.10 55.55
3 Crew for Water tanker Hour 1.00 177.50 177.50
4 Crew for Vibrator Hour 8.00 158.20 1265.60
5 Mason Class-I Day 1.00 445.00 445.00
6 work inspector Day 1.00 450.00 450.00
7 mazdoor
for batching materials Day 11.00 350.00 3850.00
for loading mortar pans Day 4.00 350.00 1400.00
for laying Day 4.00 350.00 1400.00
for conveying concrete Day 15.71 350.00 5498.50
for cleaning/ washing/ curing Day 1.00 350.00 350.00
8 Labour cost for shuttering sqm 31.42 88.50 2780.67
Labour cost for scaffolding @ 25% 695.17
Total cost of Labour Rs: 20125.59
labour component/unit qty 1281.10
Add contractor's profit and overhead charges 13.615% 174.40
labour component/unit qty (including contractor's profit) 1455.50
ABSTRACT:
A. Cost of Materials Rs: 48394.24
B. Hire charges of Machinery Rs: 2020.75
C. Cost of Labour Rs: 20125.59
Total Rs: 70540.58
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 9604.1
Total cost for 15.71 cum Rs: 80144.678
Rate per cum (A+B+C+D)/15.71 Rs. 5101.50
IRR-CCDW-2-11 Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than
10 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for sub-structure / super- structure works including cost of all materials,
machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,
levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
(Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
234
Canal Cross Drainage Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 53.50 428.00
Fuel / Energy charges Hour 8.00 79.30 634.40
2 5 hp pump ( diesel ) Hour 0.50 10.20 5.10
Fuel / Energy charges Hour 0.50 79.30 39.65
3 Water tanker 8000 ltr Hour 1.00 402.50 402.50
Fuel / Energy charges Hour 1.00 299.90 299.90
4 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 7.60 60.80
Fuel / Energy charges Hour 8.00 18.80 150.40
Total hire charges of Machinery Rs: 2020.75
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Concrete mixer Hour 8.00 219.70 1757.60
2 Crew for Pump Hour 0.50 111.10 55.55
3 Crew for Water tanker Hour 1.00 177.50 177.50
4 Crew for Vibrator Hour 8.00 158.20 1265.60
5 Mason Class-I Day 1.00 445.00 445.00
6 work inspector Day 1.00 450.00 450.00
7 mazdoor
for batching materials Day 11.00 350.00 3850.00
for loading mortar pans Day 4.00 350.00 1400.00
for laying Day 4.00 350.00 1400.00
for conveying concrete Day 18.00 350.00 6300.00
for cleaning/ washing/ curing Day 1.00 350.00 350.00
8 Labour cost for shuttering sqm 36.00 88.50 3186.00
Labour cost for scaffolding @ 25% 796.50
Total cost of Labour Rs: 21433.75
labour component/unit qty 1190.80
Add contractor's profit and overhead charges 13.615% 162.10
labour component/unit qty (including contractor's profit) 1352.90
ABSTRACT:
A. Cost of Materials Rs: 49430.74
B. Hire charges of Machinery Rs: 2020.75
C. Cost of Labour Rs: 21433.75
Total Rs: 72885.24
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 9923.33
Total cost for 18.00 cum Rs: 82808.569
Rate per cum (A+B+C+D)/18.0 Rs. 4600.50
IRR-CCDW-2-12 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for well kerb including cost of all materials, machinery, labour, formwork,
scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 350 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
235
Canal Cross Drainage Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 53.50 428.00
Fuel / Energy charges Hour 8.00 79.30 634.40
2 5 hp pump ( diesel ) Hour 0.50 10.20 5.10
Fuel / Energy charges Hour 0.50 79.30 39.65
3 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 7.60 60.80
Fuel / Energy charges Hour 8.00 18.80 150.40
Total hire charges of Machinery Rs: 1318.35
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Concrete mixer Hour 8.00 219.70 1757.60
2 Crew for Pump Hour 0.50 111.10 55.55
3 Crew for Vibrator Hour 8.00 158.20 1265.60
4 Mason Class-I Day 1.00 445.00 445.00
5 work inspector Day 1.00 450.00 450.00
6 mazdoor
for batching materials Day 11.00 350.00 3850.00
for loading mortar pans Day 4.00 350.00 1400.00
for laying Day 3.00 350.00 1050.00
for conveying concrete Day 15.00 350.00 5250.00
for cleaning/ washing/ curing Day 1.00 350.00 350.00
7 Labour cost for shuttering sqm 82.50 88.50 7301.25
Total cost of Labour Rs: 23175.00
labour component/unit qty 1545.00
Add contractor's profit and overhead charges 13.615% 210.40
labour component/unit qty (including contractor's profit) 1755.40
ABSTRACT:
A. Cost of Materials Rs: 63613.25
B. Hire charges of Machinery Rs: 1318.35
C. Cost of Labour Rs: 23175.00
Total Rs: 88106.60
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 11995.71
Total cost for 15.00 cum Rs: 100102.31
Rate per cum (A+B+C+D)/15.0 Rs. 6673.50
IRR-CCDW-2-13 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for well steining including cost of all materials, machinery, labour, formwork,
scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 320 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 53.50 428.00
236
Canal Cross Drainage Works - Item Unit Rates 2016-17
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Concrete mixer Hour 8.00 219.70 1757.60
2 Crew for Pump Hour 0.50 111.10 55.55
3 Crew for Vibrator Hour 8.00 158.20 1265.60
4 Mason Class-I Day 1.00 445.00 445.00
5 work inspector Day 1.00 450.00 450.00
6 mazdoor
for batching materials Day 11.00 350.00 3850.00
for loading mortar pans Day 4.00 350.00 1400.00
for laying Day 3.00 350.00 1050.00
for conveying concrete Day 15.00 350.00 5250.00
for cleaning/ washing/ curing Day 1.00 350.00 350.00
7 Labour cost for shuttering sqm 60.00 88.50 5310.00
Total cost of Labour Rs: 21183.75
labour component/unit qty 1412.30
Add contractor's profit and overhead charges 13.615% 192.30
labour component/unit qty (including contractor's profit) 1604.60
ABSTRACT:
A. Cost of Materials Rs: 57625.46
B. Hire charges of Machinery Rs: 1318.35
C. Cost of Labour Rs: 21183.75
Total Rs: 80127.56
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 10909.37
Total cost for 15.00 cum Rs: 91036.93
Rate per cum (A+B+C+D)/15.0 Rs. 6069.10
IRR-CCDW-2-14 Providing and laying insitu M-15 ( 28 days cube compressive strength not less than 15 N / sq
mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for well bottom plug by tremie or skip box method including cost of all materials,
machinery, labour, batching, mixing, placing in position as per detailed specifications etc.,
complete with initial lead upto 50 m and all lifts. ( Cement content : 350 kg / cum )
(Cement content: 350 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 53.50 428.00
Fuel / Energy charges Hour 8.00 79.30 634.40
2 5 hp pump ( diesel ) Hour 0.50 10.20 5.10
Fuel / Energy charges Hour 0.50 79.30 39.65
3 Sundries( Hopper etc. ) LS 5.00 30.00 150.00
Total hire charges of Machinery Rs: 1257.15
C. LABOUR:
237
Canal Cross Drainage Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 40740.88
B. Hire charges of Machinery Rs: 1257.15
C. Cost of Labour Rs: 15613.15
Total Rs: 57611.18
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 7843.76
Total cost for 14.00 cum Rs: 65454.94
Rate per cum (A+B+C+D)/14.0 Rs. 4675.40
IRR-CCDW-2-15 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than
15 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for well top plug including cost of all materials, machinery, labour, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with
initial lead upto 50 m and all lifts.
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 280 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 53.50 428.00
Fuel / Energy charges Hour 8.00 79.30 634.40
2 5 hp pump ( diesel ) Hour 0.50 10.20 5.10
Fuel / Energy charges Hour 0.50 79.30 39.65
3 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 7.60 60.80
Fuel / Energy charges Hour 8.00 18.80 150.40
Total hire charges of Machinery Rs: 1318.35
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Concrete mixer Hour 8.00 219.70 1757.60
2 Crew for Pump Hour 0.50 111.10 55.55
3 Crew for Needle vibrator Hour 8.00 158.20 1265.60
4 Mason Class-I Day 1.00 445.00 445.00
5 work inspector Day 1.00 450.00 450.00
6 mazdoor
for batching materials Day 11.00 350.00 3850.00
238
Canal Cross Drainage Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 37426.94
B. Hire charges of Machinery Rs: 1318.35
C. Cost of Labour Rs: 15625.25
Total Rs: 54370.54
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 7402.55
Total cost for 14.29 cum Rs: 61773.09
Rate per cum (A+B+C+D)/14.29 Rs. 4322.80
IRR-CCDW-2-16 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for well cap including cost of all materials, machinery, labour, formwork,
scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 53.50 428.00
Fuel / Energy charges Hour 8.00 79.30 634.40
2 5 hp pump ( diesel ) Hour 0.50 10.20 5.10
Fuel / Energy charges Hour 0.50 79.30 39.65
3 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 7.60 60.80
Fuel / Energy charges Hour 8.00 18.80 150.40
Total hire charges of Machinery Rs: 1318.35
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Concrete mixer Hour 8.00 219.70 1757.60
2 Crew for Pump Hour 0.50 111.10 55.55
3 Crew for Needle vibrator Hour 8.00 158.20 1265.60
4 Mason Class-I Day 1.00 445.00 445.00
5 work inspector Day 1.00 450.00 450.00
6 mazdoor
for batching materials Day 11.00 350.00 3850.00
for loading mortar pans Day 4.00 350.00 1400.00
for laying Day 3.00 350.00 1050.00
for conveying concrete Day 15.76 350.00 5516.00
for cleaning/ washing/ curing Day 1.00 350.00 350.00
7 Labour cost for shuttering sqm 15.76 88.50 1394.76
Total cost of Labour Rs: 17534.51
239
Canal Cross Drainage Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 47628.60
B. Hire charges of Machinery Rs: 1318.35
C. Cost of Labour Rs: 17534.51
Total Rs: 66481.46
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 9051.45
Total cost for 15.76 cum Rs: 75532.91
Rate per cum (A+B+C+D)/15.76 Rs. 4792.70
IRR-CCDW-2-17 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than
15 N / sq mm ) grade cement concrete using 80 mm down size approved, clean, hard, graded
aggregates for piers and abutments including cost of all materials, labour, machinery,
formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 250 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Concrete mixer 600/400 ltr ( diesel ) Hour 8.00 92.70 741.60
Fuel / Energy charges Hour 8.00 158.70 1269.60
2 5 hp pump ( diesel ) Hour 0.50 10.20 5.10
Fuel / Energy charges Hour 0.50 79.30 39.65
3 Needle vibrator 60 mm dia ( petrol ) Hour 8.00 8.20 65.60
Fuel / Energy charges Hour 8.00 28.20 225.60
Total hire charges of Machinery Rs: 2347.15
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Concrete mixer Hour 8.00 219.70 1757.60
2 Crew for Pump Hour 0.50 111.10 55.55
3 Crew for Needle vibrator Hour 8.00 158.20 1265.60
4 Mason Class-I Day 1.00 445.00 445.00
5 work inspector Day 1.00 450.00 450.00
6 mazdoor
for batching materials Day 11.00 350.00 3850.00
for loading mortar pans Day 4.00 350.00 1400.00
for laying Day 6.00 350.00 2100.00
for conveying concrete Day 14.40 350.00 5040.00
for cleaning/ washing/ curing Day 1.00 350.00 350.00
7 Labour cost for shuttering sqm 39.60 88.50 3504.60
Labour cost for scaffolding @ 30% 1051.38
Total cost of Labour Rs: 21269.73
labour component/unit qty 1477.10
Add contractor's profit and overhead charges 13.615% 201.10
240
Canal Cross Drainage Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 46602.29
B. Hire charges of Machinery Rs: 2347.15
C. Cost of Labour Rs: 21269.73
Total Rs: 70219.17
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 9560.34
Total cost for 14.40 cum Rs: 79779.513
Rate per cum (A+B+C+D)/14.40 Rs. 5540.20
IRR-CCDW-2-18 Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than
10 N / sq mm ) grade cement concrete using 80 mm down size approved, clean, hard, graded
aggregates for piers and abutments including cost of all materials, labour, machinery,
formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Concrete mixer 600/400 ltr ( diesel ) Hour 8.00 92.70 741.60
Fuel / Energy charges Hour 8.00 158.70 1269.60
2 5 hp pump ( diesel ) Hour 0.50 10.20 5.10
Fuel / Energy charges Hour 0.50 79.30 39.65
3 Needle vibrator 60 mm dia ( petrol ) Hour 8.00 8.20 65.60
Fuel / Energy charges Hour 8.00 28.20 225.60
Total hire charges of Machinery Rs: 2347.15
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Concrete mixer Hour 8.00 219.70 1757.60
2 Crew for Pump Hour 0.50 111.10 55.55
3 Crew for Needle vibrator Hour 8.00 158.20 1265.60
4 Mason Class-I Day 1.00 445.00 445.00
5 work inspector Day 1.00 450.00 450.00
6 mazdoor
for batching materials Day 11.00 350.00 3850.00
for loading mortar pans Day 4.00 350.00 1400.00
for laying Day 6.00 350.00 2100.00
for conveying concrete Day 14.55 350.00 5092.50
for cleaning/ washing/ curing Day 1.00 350.00 350.00
7 Labour cost for shuttering sqm 40.01 88.50 3541.11
Labour cost for scaffolding @ 30% 1062.33
Total cost of Labour Rs: 21369.69
labour component/unit qty 1468.70
Add contractor's profit and overhead charges 13.615% 200.00
labour component/unit qty (including contractor's profit) 1668.70
241
Canal Cross Drainage Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 44656.43
B. Hire charges of Machinery Rs: 2347.15
C. Cost of Labour Rs: 21369.69
Total Rs: 68373.27
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 9309.02
Total cost for 14.55 cum Rs: 77682.29
Rate per cum (A+B+C+D)/14.55 Rs. 5339.00
IRR-CCDW-2-19 Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than
10 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for piers and abutments including cost of all materials, labour, machinery,
formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 53.50 428.00
Fuel / Energy charges Hour 8.00 79.30 634.40
2 5 hp pump ( diesel ) Hour 0.50 10.20 5.10
Fuel / Energy charges Hour 0.50 79.30 39.65
3 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 7.60 60.80
Fuel / Energy charges Hour 8.00 18.80 150.40
Total hire charges of Machinery Rs: 1318.35
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Concrete mixer Hour 8.00 219.70 1757.60
2 Crew for Pump Hour 0.50 111.10 55.55
3 Crew for Needle vibrator Hour 8.00 158.20 1265.60
4 Mason Class-I Day 1.00 445.00 445.00
5 work inspector Day 1.00 450.00 450.00
6 mazdoor
for batching materials Day 11.00 350.00 3850.00
for loading mortar pans Day 4.00 350.00 1400.00
for laying Day 5.00 350.00 1750.00
for conveying concrete Day 16.36 350.00 5726.00
for cleaning/ washing/ curing Day 1.00 350.00 350.00
7 Labour cost for shuttering sqm 44.99 88.50 3981.62
Labour cost for scaffolding @ 30% 1194.48
Total cost of Labour Rs: 22225.85
labour component/unit qty 1358.50
Add contractor's profit and overhead charges 13.615% 185.00
labour component/unit qty (including contractor's profit) 1543.50
ABSTRACT:
A. Cost of Materials Rs: 51609.59
B. Hire charges of Machinery Rs: 1318.35
242
Canal Cross Drainage Works - Item Unit Rates 2016-17
IRR-CCDW-2-20 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for cantiliver / counterfort retaining walls including cost of all materials,
machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,
levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
(Cement content: 320 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 53.50 428.00
Fuel / Energy charges Hour 8.00 79.30 634.40
2 5 hp pump ( diesel ) Hour 0.50 10.20 5.10
Fuel / Energy charges Hour 0.50 79.30 39.65
3 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 7.60 60.80
Fuel / Energy charges Hour 8.00 18.80 150.40
Total hire charges of Machinery Rs: 1318.35
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Concrete mixer Hour 8.00 219.70 1757.60
2 Crew for Pump Hour 0.50 111.10 55.55
3 Crew for Needle vibrator Hour 8.00 158.20 1265.60
4 Mason Class-I Day 1.00 445.00 445.00
5 work inspector Day 1.00 450.00 450.00
6 mazdoor
for batching materials Day 11.00 350.00 3850.00
for loading mortar pans Day 4.00 350.00 1400.00
for laying Day 5.00 350.00 1750.00
for conveying concrete Day 16.25 350.00 5687.50
for cleaning/ washing/ curing Day 1.00 350.00 350.00
7 Labour cost for shuttering sqm 52.81 88.50 4673.91
Labour cost for scaffolding @ 25% 1168.48
Total cost of Labour Rs: 22853.63
labour component/unit qty 1406.40
Add contractor's profit and overhead charges 13.615% 191.50
labour component/unit qty (including contractor's profit) 1597.90
ABSTRACT:
A. Cost of Materials Rs: 61455.53
B. Hire charges of Machinery Rs: 1318.35
C. Cost of Labour Rs: 22853.63
243
Canal Cross Drainage Works - Item Unit Rates 2016-17
IRR-CCDW-2-21 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than
15 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates with placing and sinking plums of size 150 to 80 mm upto 15 percent for gravity
type retaining walls / piers / abutments etc., including cost of all materials, machinery,
labour, formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating,
finishing, curing etc.,complete with initial lead upto 50 m and all lifts.
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 260 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.765cum, Blending Ratio of CA--50:30:20, FA : 0.34 cum,
plums of size 150 to 80 mm : 0.25cum )
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 53.50 428.00
Fuel / Energy charges Hour 8.00 79.30 634.40
2 5 hp pump ( diesel ) Hour 0.50 10.20 5.10
Fuel / Energy charges Hour 0.50 79.30 39.65
3 Needle vibrator 60 mm dia ( petrol ) Hour 8.00 8.20 65.60
Fuel / Energy charges Hour 8.00 28.20 225.60
Total hire charges of Machinery Rs: 1398.35
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Concrete mixer Hour 8.00 219.70 1757.60
2 Crew for Pump Hour 0.50 111.10 55.55
3 Crew for Needle vibrator Hour 8.00 158.20 1265.60
4 Mason Class-I Day 1.00 445.00 445.00
5 work inspector Day 1.00 450.00 450.00
6 mazdoor
for batching materials Day 11.00 350.00 3850.00
for loading mortar pans Day 4.00 350.00 1400.00
for laying Day 5.00 350.00 1750.00
for placing plums Day 2.00 350.00 700.00
for conveying concrete Day 15.38 350.00 5383.00
for conveying plums Day 2.00 350.00 700.00
for cleaning/ washing/ curing Day 1.00 350.00 350.00
7 Labour for shuttering sqm 49.75 88.50 4402.65
Labour for scaffolding @ 30% 1320.80
Total cost of Labour Rs: 23830.20
labour component/unit qty 1317.30
Add contractor's profit and overhead charges 13.615% 179.40
labour component/unit qty (including contractor's profit) 1496.70
ABSTRACT:
A. Cost of Materials Rs: 58982.52
244
Canal Cross Drainage Works - Item Unit Rates 2016-17
IRR-CCDW-2-22 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than
15 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard,graded
aggregates for cast in-situ pipes including cost of all materials, machinery, labour, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with
initial lead upto 50 m and all lifts.
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 260 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 53.50 428.00
Fuel / Energy charges Hour 8.00 79.30 634.40
2 5 hp pump ( diesel ) Hour 0.50 10.20 5.10
Fuel / Energy charges Hour 0.50 79.30 39.65
3 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 7.60 60.80
Fuel / Energy charges Hour 8.00 18.80 150.40
Total hire charges of Machinery Rs: 1318.35
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Concrete mixer Hour 8.00 219.70 1757.60
2 Crew for Pump Hour 0.50 111.10 55.55
3 Crew for Needle vibrator Hour 8.00 158.20 1265.60
4 Mason Class-I Day 1.00 445.00 445.00
5 work inspector Day 1.00 450.00 450.00
6 mazdoor
for batching materials Day 11.00 350.00 3850.00
for loading mortar pans Day 4.00 350.00 1400.00
for laying Day 3.00 350.00 1050.00
for conveying concrete Day 15.38 350.00 5383.00
for cleaning/ washing/ curing Day 1.00 350.00 350.00
7 Labour for shuttering sqm 30.76 88.50 2722.26
Labour for scaffolding @ 15% 408.34
Total cost of Labour Rs: 19137.35
labour component/unit qty 1244.30
Add contractor's profit and overhead charges 13.615% 169.40
labour component/unit qty (including contractor's profit) 1413.70
ABSTRACT:
A. Cost of Materials Rs: 47335.89
B. Hire charges of Machinery Rs: 1318.35
C. Cost of Labour Rs: 19137.35
245
Canal Cross Drainage Works - Item Unit Rates 2016-17
IRR-CCDW-2-23 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than
15 N / sq mm ) grade cement concrete using 80 mm down size approved, clean, hard, graded
aggregates for cast in-situ pipes including cost of all materials, labour, machinery, formwork,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 250 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Concrete mixer 600/400 ltr ( diesel ) Hour 8.00 92.70 741.60
Fuel / Energy charges Hour 8.00 158.70 1269.60
2 5 hp pump ( diesel ) Hour 0.50 10.20 5.10
Fuel / Energy charges Hour 0.50 79.30 39.65
3 Needle vibrator 60 mm dia ( petrol ) Hour 8.00 8.20 65.60
Fuel / Energy charges Hour 8.00 28.20 225.60
Total hire charges of Machinery Rs: 2347.15
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Concrete mixer Hour 8.00 219.70 1757.60
2 Crew for Pump Hour 0.50 111.10 55.55
3 Crew for Needle vibrator Hour 8.00 158.20 1265.60
4 Mason Class-I Day 1.00 445.00 445.00
5 work inspector Day 1.00 450.00 450.00
6 mazdoor
for batching materials Day 11.00 350.00 3850.00
for loading mortar pans Day 4.00 350.00 1400.00
for laying Day 3.00 350.00 1050.00
for conveying concrete Day 14.40 350.00 5040.00
for cleaning/ washing/ curing Day 1.00 350.00 350.00
7 Labour cost for shuttering sqm 28.80 88.50 2548.80
Labour cost for scaffolding @ 15% 382.32
Total cost of Labour Rs: 18594.87
labour component/unit qty 1291.30
Add contractor's profit and overhead charges 13.615% 175.80
labour component/unit qty (including contractor's profit) 1467.10
ABSTRACT:
A. Cost of Materials Rs: 42273.08
B. Hire charges of Machinery Rs: 2347.15
C. Cost of Labour Rs: 18594.87
Total Rs: 63215.10
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 8606.74
246
Canal Cross Drainage Works - Item Unit Rates 2016-17
IRR-CCDW-2-24 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for deck slab & kerb including cost of all materials,machinery, labour, formwork,
scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 53.50 428.00
Fuel / Energy charges Hour 8.00 79.30 634.40
2 5 hp pump ( diesel ) Hour 0.50 10.20 5.10
Fuel / Energy charges Hour 0.50 79.30 39.65
3 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 7.60 60.80
Fuel / Energy charges Hour 8.00 18.80 150.40
Total hire charges of Machinery Rs: 1318.35
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Concrete mixer Hour 8.00 219.70 1757.60
2 Crew for Pump Hour 0.50 111.10 55.55
3 Crew for Needle vibrator Hour 8.00 158.20 1265.60
4 Mason Class-I Day 2.00 445.00 890.00
5 work inspector Day 1.00 450.00 450.00
6 mazdoor
for batching materials Day 11.00 350.00 3850.00
for loading mortar pans Day 4.00 350.00 1400.00
for laying Day 4.00 350.00 1400.00
for conveying concrete Day 15.76 350.00 5516.00
for cleaning/ washing/ curing Day 1.00 350.00 350.00
7 Labour cost for shuttering sqm 39.40 88.50 3486.90
Labour cost for scaffolding @ 250% 8717.25
Total cost of Labour Rs: 29138.90
labour component/unit qty 1848.90
Add contractor's profit and overhead charges 13.615% 251.70
labour component/unit qty (including contractor's profit) 2100.60
ABSTRACT:
A. Cost of Materials Rs: 81533.70
B. Hire charges of Machinery Rs: 1318.35
C. Cost of Labour Rs: 29138.90
Total Rs: 111990.95
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 15247.57
Total cost for 15.76 cum Rs: 127238.52
Rate per cum (A+B+C+D)/15.76 Rs. 8073.50
247
Canal Cross Drainage Works - Item Unit Rates 2016-17
IRR-CCDW-2-25 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for columns and beams including cost of all materials, labour, machinery,
formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating,
finishing, curing etc.,complete with initial lead upto 50 m and all lifts.
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 53.50 428.00
Fuel / Energy charges Hour 8.00 79.30 634.40
2 5 hp pump ( diesel ) Hour 0.50 10.20 5.10
Fuel / Energy charges Hour 0.50 79.30 39.65
3 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 7.60 60.80
Fuel / Energy charges Hour 8.00 18.80 150.40
Total hire charges of Machinery Rs: 1318.35
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Concrete mixer Hour 8.00 219.70 1757.60
2 Crew for Pump Hour 0.50 111.10 55.55
3 Crew for Needle vibrator Hour 8.00 158.20 1265.60
4 Mason Class-I Day 1.00 445.00 445.00
5 work inspector Day 1.00 450.00 450.00
6 mazdoor
for batching materials Day 11.00 350.00 3850.00
for loading mortar pans Day 4.00 350.00 1400.00
for laying Day 3.00 350.00 1050.00
for conveying concrete Day 15.76 350.00 5516.00
for cleaning/ washing/ curing Day 1.00 350.00 350.00
7 Labour cost for shuttering sqm 78.80 88.50 6973.80
Labour cost for scaffolding @ 50% 3486.90
Total cost of Labour Rs: 26600.45
labour component/unit qty 1687.80
Add contractor's profit and overhead charges 13.615% 229.80
labour component/unit qty (including contractor's profit) 1917.60
ABSTRACT:
A. Cost of Materials Rs: 70648.30
B. Hire charges of Machinery Rs: 1318.35
C. Cost of Labour Rs: 26600.45
Total Rs: 98567.10
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 13419.91
Total cost for 15.76 cum Rs: 111987.01
Rate per cum (A+B+C+D)/15.76 Rs. 7105.80
IRR-CCDW-2-26 Providing and laying insitu M- 20 ( 28 days cube compressive strength not less than 20 N /
248
Canal Cross Drainage Works - Item Unit Rates 2016-17
sqmm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for wearing coat including cost of all materials, machinery, labour, formwork,
cleaning, batching, mixing, placing in position in alternate panels, levelling, compacting,
finishing, curing, packing joints with asphalt mortar etc., complete with initial lead upto 50 m
and all lifts.
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. to the data
(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 53.50 428.00
Fuel / Energy charges Hour 8.00 79.30 634.40
2 5 hp pump ( diesel ) Hour 0.50 10.20 5.10
Fuel / Energy charges Hour 0.50 79.30 39.65
3 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 7.60 60.80
Fuel / Energy charges Hour 8.00 18.80 150.40
Total hire charges of Machinery Rs: 1318.35
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Concrete mixer Hour 8.00 219.70 1757.60
2 Crew for Pump Hour 0.50 111.10 55.55
3 Crew for Needle vibrator Hour 8.00 158.20 1265.60
4 Mason Class-I Day 2.00 445.00 890.00
5 work inspector Day 1.00 450.00 450.00
6 mazdoor
for batching materials Day 11.00 350.00 3850.00
for loading mortar pans Day 4.00 350.00 1400.00
for laying Day 4.00 350.00 1400.00
for conveying concrete Day 15.76 350.00 5516.00
for cleaning/ washing/ curing Day 2.00 350.00 700.00
7 Labour cost for shuttering sqm 7.88 88.50 697.38
Total cost of Labour Rs: 17982.13
labour component/unit qty 1141.00
Add contractor's profit and overhead charges 13.615% 155.30
labour component/unit qty (including contractor's profit) 1296.30
ABSTRACT:
A. Cost of Materials Rs: 45994.01
B. Hire charges of Machinery Rs: 1318.35
C. Cost of Labour Rs: 17982.13
Total Rs: 65294.49
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 8889.84
Total cost for 15.76 cum Rs: 74184.33
Rate per cum (A+B+C+D)/15.76 Rs. 4707.10
IRR-CCDW-2-27 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for troughs including cost of all materials, machinery, labour, formwork,
scaffolding, cleaning, batching, mixing, placing in position,levelling, vibrating, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.
249
Canal Cross Drainage Works - Item Unit Rates 2016-17
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. to the data
(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 53.50 428.00
Fuel / Energy charges Hour 8.00 79.30 634.40
2 5 hp pump ( diesel ) Hour 0.50 10.20 5.10
Fuel / Energy charges Hour 0.50 79.30 39.65
3 Needle vibrator 40 mm dia ( diesel ) Hour 8.00 7.60 60.80
Fuel / Energy charges Hour 8.00 18.80 150.40
Total hire charges of Machinery Rs: 1318.35
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Concrete mixer Hour 8.00 219.70 1757.60
2 Crew for Pump Hour 0.50 111.10 55.55
3 Crew for Needle vibrator Hour 8.00 158.20 1265.60
4 Mason Class-I Day 1.00 445.00 445.00
5 work inspector Day 1.00 450.00 450.00
6 mazdoor
for batching materials Day 11.00 350.00 3850.00
for loading mortar pans Day 4.00 350.00 1400.00
for laying Day 5.00 350.00 1750.00
for conveying concrete Day 15.76 350.00 5516.00
for cleaning/ washing/ curing Day 1.00 350.00 350.00
7 Labour cost for shuttering sqm 70.92 88.50 6276.42
Labour cost for scaffolding @ 25% 1569.11
Total cost of Labour Rs: 24685.28
labour component/unit qty 1566.30
Add contractor's profit and overhead charges 13.615% 213.30
labour component/unit qty (including contractor's profit) 1779.60
ABSTRACT:
A. Cost of Materials Rs: 63997.33
B. Hire charges of Machinery Rs: 1318.35
C. Cost of Labour Rs: 24685.28
Total Rs: 90000.95
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 12253.63
Total cost for 15.76 cum Rs: 102254.58
Rate per cum (A+B+C+D)/15.76 Rs. 6488.20
IRR-CCDW-3-1 Sinking RCC wells vertically for foundation of piers and abutments in all kinds of soil,
DATA: Unit = Running meter
Taking output = 1m
diameter of well = 6.00m
(i) Depth below bed level upto 3.0m
Rate of sinking = 0.50 m /hour
a) Labour
250
Canal Cross Drainage Works - Item Unit Rates 2016-17
IRR-CCDW-3-2 Filling foundation wells with sand in layers of 25 to 30 cm and compacting by watering,
ramming as directed including cost of all materials, machinery, labour etc., complete with
initial lead upto 50 m and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nill 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
251
Canal Cross Drainage Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 1496.25
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 1512.50
Total Rs: 3008.75
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 409.64
Total cost for 15.00 cum Rs: 3418.39
Rate per cum (A+B+C+D)/15.0 Rs. 227.90
IRR-CCDW-4-1 Providing and constructing un-coursed rubble stone masonry with approved stones in
CM 1 : 4 proportion for sub-structure portions of return walls / abutments etc., including
cost of all materials, machinery, labour, scaffolding, cleaning, packing cement mortar, wedging
stone chips, curing etc., complete with initial lead upto 50 m and all lifts.
(Cement content: 143 kg / cum of masonry, rubble stones : 0.85cum, FA : 0.40 cum,
Stone Chips : 0.15 cum)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Water tanker 8000 ltr Hour 1.00 402.50 402.50
Fuel / Energy charges Hour 1.00 299.90 299.90
2 5 hp pump ( diesel ) Hour 0.50 10.20 5.10
Fuel / Energy charges Hour 0.50 79.30 39.65
Total hire charges of Machinery Rs: 747.15
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Water tanker Hour 1.00 177.50 177.50
2 Crew for Pump Hour 0.50 111.10 55.55
3 work inspector Day 1.00 450.00 450.00
4 Mason Class-I Day 1.00 445.00 445.00
5 Mason Class-II Day 2.00 400.00 800.00
6 mazdoor
for conveying rubble stones Day 4.00 350.00 1400.00
for preparing mortar Day 2.00 350.00 700.00
for loading mortar pans Day 1.00 350.00 350.00
for laying & packing mortar Day 3.00 350.00 1050.00
for washing rubble / finishing / curing Day 1.00 350.00 350.00
for conveying mortar / chips Day 4.00 350.00 1400.00
Total cost of Labour Rs: 7178.05
labour component/unit qty 717.80
Add contractor's profit and overhead charges 13.615% 97.70
labour component/unit qty (including contractor's profit) 815.50
ABSTRACT:
A. Cost of Materials Rs: 11538.50
B. Hire charges of Machinery Rs: 747.15
C. Cost of Labour Rs: 7178.05
Total Rs: 19463.70
252
Canal Cross Drainage Works - Item Unit Rates 2016-17
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 2649.98
Total cost for 10.00 cum Rs: 22113.68
Rate per cum (A+B+C+D)/10.0 Rs. 2211.40
IRR-CCDW-4-2 Providing and constructing un-coursed rubble stone masonry with approved stones in
CM 1 : 4 proportion for super-structure portions of return walls / abutments etc., including
cost of all materials, machinery, labour, scaffolding, cleaning, packing cement mortar, wedging
stone chips, curing etc., complete with initial lead upto 50 m and all lifts.
(Cement content: 143 kg / cum of masonry, rubble stones : 0.85cum, FA : 0.40 cum,
Stone Chips : 0.15 cum)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Water tanker 8000 ltr Hour 1.00 402.50 402.50
Fuel / Energy charges Hour 1.00 299.90 299.90
2 5 hp pump ( diesel ) Hour 0.50 10.20 5.10
Fuel / Energy charges Hour 0.50 79.30 39.65
Total hire charges of Machinery Rs: 747.15
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Water tanker Hour 1.00 177.50 177.50
2 Crew for Pump Hour 0.50 111.10 55.55
3 work inspector Day 1.00 450.00 450.00
4 Mason Class-I Day 1.00 445.00 445.00
5 Mason Class-II Day 2.00 400.00 800.00
6 mazdoor
for conveying rubble stones Day 4.00 350.00 1400.00
for preparing mortar Day 2.00 350.00 700.00
for loading mortar pans Day 1.00 350.00 350.00
for laying & packing mortar Day 3.00 350.00 1050.00
for washing rubble / finishing / curing Day 1.00 350.00 350.00
for conveying mortar / chips Day 4.00 350.00 1400.00
TOTAL Rs: 7178.05
Add for labour for scaffolding @ 2.5% Rs: 179.45
Total cost of Labour Rs: 7357.50
labour component/unit qty 735.80
Add contractor's profit and overhead charges 13.615% 100.20
labour component/unit qty (including contractor's profit) 836.00
ABSTRACT:
A. Cost of Materials Rs: 11826.96
B. Hire charges of Machinery Rs: 747.15
C. Cost of Labour Rs: 7357.50
Total Rs: 19931.61
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 2713.69
Total cost for 10.00 cum Rs: 22645.30
Rate per cum (A+B+C+D)/10.0 Rs. 2264.50
IRR-CCDW-4-3 Providing and constructing coursed rubble masonry second sort in CM 1:4 proportion with
stones from approved source including cost of all materials, machinery, labour, scaffolding,
ramps, cleaning, packing mortar, wedging stone chips, finishing, curing etc., complete with
initial lead upto 50 m and initial lift upto 3m.
253
Canal Cross Drainage Works - Item Unit Rates 2016-17
(Cement content: 133 kg / cum of masonry, rubble stones : 0.45cum, FA : 0.35 cum,
Stone Chips : 0.15 cum, Khandki stones 25 x 25 x 30 cm : 180 Nos, Header stones
25 x 25x 45 cm : 60 Nos)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Water tanker 8000 ltr Hour 1.00 402.50 402.50
Fuel / Energy charges Hour 1.00 299.90 299.90
2 5 hp pump ( diesel ) Hour 0.50 10.20 5.10
Fuel / Energy charges Hour 0.50 79.30 39.65
Total hire charges of Machinery Rs: 747.15
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Water tanker Hour 1.00 177.50 177.50
2 Crew for Pump Hour 0.50 111.10 55.55
3 work inspector Day 1.00 450.00 450.00
4 Stone chiseller Cl -II Day 3.00 400.00 1200.00
5 Mason Class-I Day 1.00 445.00 445.00
6 Mason Class-II Day 2.00 400.00 800.00
7 mazdoor
for conveying stones / rubble Day 4.00 350.00 1400.00
for preparation of mortar Day 3.00 350.00 1050.00
for loading mortar pans Day 1.00 350.00 350.00
for laying & packing mortar Day 3.00 350.00 1050.00
for washing rubble / finishing / curing Day 1.00 350.00 350.00
for conveying mortar / chips Day 2.00 350.00 700.00
TOTAL Rs: 8028.05
Add for labour for scaffolding @ 2.5% Rs: 200.70
Total cost of Labour Rs: 8228.75
labour component/unit qty 822.90
Add contractor's profit and overhead charges 13.615% 112.00
labour component/unit qty (including contractor's profit) 934.90
ABSTRACT:
A. Cost of Materials Rs: 15425.23
B. Hire charges of Machinery Rs: 747.15
C. Cost of Labour Rs: 8228.75
Total Rs: 24401.13
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 3322.21
Total cost for 10.00 cum Rs: 27723.34
Rate per cum (A+B+C+D)/10.0 Rs. 2772.30
IRR-CCDW-4-4 Providing and constructing coursed rubble masonry first sort in CM 1:4 proportion with
stones from approved source including cost of all materials, machinery, labour, scaffolding,
ramps, cleaning, packing mortar, wedging stone chips, finishing, curing etc., complete with
initial lead upto 50 m and initial lift upto 3 m.
(Cement content: 133 kg / cum of masonry, rubble stones : 0.45cum, FA : 0.35 cum,
Stone Chips : 0.15 cum, Khandki stones 25 x 25 x 30 cm : 180 Nos, Header stones
25 x 25x 45 cm : 60 Nos)
254
Canal Cross Drainage Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Water tanker 8000 ltr Hour 1.00 402.50 402.50
Fuel / Energy charges Hour 1.00 299.90 299.90
2 5 hp pump ( diesel ) Hour 0.50 10.20 5.10
Fuel / Energy charges Hour 0.50 79.30 39.65
Total hire charges of Machinery Rs: 747.15
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Water tanker Hour 1.00 177.50 177.50
2 Crew for Pump Hour 0.50 111.10 55.55
3 work inspector Day 1.00 450.00 450.00
4 Stone chiseller Cl -II Day 6.00 400.00 2400.00
5 Mason Class-I Day 1.00 445.00 445.00
6 Mason Class-II Day 2.00 400.00 800.00
7 mazdoor
8 for conveying rubble/ stones Day 4.00 350.00 1400.00
for preparation of mortar Day 3.00 350.00 1050.00
for loading mortar pans Day 1.00 350.00 350.00
for laying & packing mortar Day 3.00 350.00 1050.00
for washing rubble / finishing / curing Day 1.00 350.00 350.00
for conveying mortar / chips Day 2.00 350.00 700.00
TOTAL Rs: 9228.05
Add for labour for scaffolding @ 2.5% Rs: 230.70
Total cost of Labour Rs: 9458.75
labour component/unit qty 945.90
Add contractor's profit and overhead charges 13.615% 128.80
labour component/unit qty (including contractor's profit) 1074.70
ABSTRACT:
A. Cost of Materials Rs: 15425.23
B. Hire charges of Machinery Rs: 747.15
C. Cost of Labour Rs: 9458.75
Total Rs: 25631.13
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 3489.68
Total cost for 10.00 cum Rs: 29120.81
Rate per cum (A+B+C+D)/10.0 Rs. 2912.10
IRR-CCDW-4-5 Providing cement mortar pointing to coursed rubble face stone masonry in CM 1 : 2
proportion by volume including raking and cleaning joints for 50 mm depth, pressing cement
mortar into joints, cost of all materials, labour, scaffolding, finishing, curing etc., complete with
initial lead upto 50 m and all lifts.
255
Canal Cross Drainage Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nil 0.00 0.00 0.00
( Manual mixing) 0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Mason Cl- I Day 10.00 445.00 4450.00
2 work inspector Day 1.00 450.00 450.00
3 mazdoor Day 10.00 350.00 3500.00
Total cost of Labour Rs: 8400.00
labour component/unit qty 84.00
Add contractor's profit and overhead charges 13.615% 11.40
labour component/unit qty (including contractor's profit) 95.40
ABSTRACT:
A. Cost of Materials Rs: 2627.43
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 8400.00
Total Rs: 11027.43
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 1501.39
Total cost for 100.00 sqm Rs: 12528.82
Rate per sqm (A+B+C+D)/100.0 Rs. 125.30
IRR-CCDW-4-6 Providing cement mortar pointing to coursed rubble face stone masonry in CM 1 : 3
proportion by volume including raking and cleaning joints for 50 mm depth, pressing cement
mortar into joints, cost of all materials, labour, scaffolding, finishing, curing etc., complete with
initial lead upto 50 m and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nil 0.00 0.00 0.00
( Manual mixing) 0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Mason Cl- I Day 10.00 445.00 4450.00
2 work inspector Day 1.00 450.00 450.00
3 mazdoor Day 10.00 350.00 3500.00
Total cost of Labour Rs: 8400.00
labour component/unit qty 84.00
Add contractor's profit and overhead charges 13.615% 11.40
labour component/unit qty (including contractor's profit) 95.40
ABSTRACT:
A. Cost of Materials Rs: 1892.61
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 8400.00
Total Rs: 10292.61
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 1401.34
Total cost for 100.00 sqm Rs: 11693.95
Rate per sqm (A+B+C+D)/100.0 Rs. 116.90
256
Canal Cross Drainage Works - Item Unit Rates 2016-17
IRR-CCDW-4-7 Providing 12 mm thick plastering in cement mortar 1:3 proportion by volume including cost
of all materials, machinery, labour, scaffolding, cleaning joints, smooth finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nil 0.00 0.00 0.00
( Manual mixing) 0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Mason Cl- I Day 10.00 445.00 4450.00
2 work inspector Day 1.00 450.00 450.00
3 mazdoor Day 20.00 350.00 7000.00
Total cost of Labour Rs: 11900.00
labour component/unit qty 119.00
Add contractor's profit and overhead charges 13.615% 16.20
labour component/unit qty (including contractor's profit) 135.20
ABSTRACT:
A. Cost of Materials Rs: 3672.52
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 11900.00
Total Rs: 15572.52
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 2120.2
Total cost for 100.00 sqm Rs: 17692.72
Rate per sqm (A+B+C+D)/100.0 Rs. 176.90
IRR-CCDW-4-8 Providing 12 mm thick plastering in cement mortar 1:4 proportion by volume including cost
of all materials, machinery, labour, scaffolding, cleaning joints, smooth finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nil 0.00 0.00 0.00
( Manual mixing) 0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
257
Canal Cross Drainage Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 2811.58
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 11900.00
Total Rs: 14711.58
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 2002.98
Total cost for 100.00 sqm Rs: 16714.555
Rate per sqm (A+B+C+D)/100.0 Rs. 167.10
IRR-CCDW-4-9 Providing 20 mm thick plastering in cement mortar 1:3 proportion by volume including cost
of all materials, machinery, labour, scaffolding, cleaning joints, smooth finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nil 0.00 0.00 0.00
( Manual mixing) 0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Mason Cl- I Day 15.00 445.00 6675.00
2 work inspector Day 1.00 450.00 450.00
3 mazdoor Day 25.00 350.00 8750.00
Total cost of Labour Rs: 15875.00
labour component/unit qty 158.80
Add contractor's profit and overhead charges 13.615% 21.60
labour component/unit qty (including contractor's profit) 180.40
ABSTRACT:
A. Cost of Materials Rs: 6130.01
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 15875.00
Total Rs: 22005.01
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 2995.98
Total cost for 100.00 sqm Rs: 25000.99
Rate per sqm (A+B+C+D)/100.0 Rs. 250.00
IRR-CCDW-4-10 Providing 20 mm thick plastering in cement mortar 1:4 proportion by volume including cost
of all materials, machinery, labour, scaffolding, cleaning joints, smooth finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.
258
Canal Cross Drainage Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nil 0.00 0.00 0.00
( Manual mixing) 0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Mason Cl- I Day 15.00 445.00 6675.00
2 work inspector Day 1.00 450.00 450.00
3 mazdoor Day 25.00 350.00 8750.00
Total cost of Labour Rs: 15875.00
labour component/unit qty 158.80
Add contractor's profit and overhead charges 13.615% 21.60
labour component/unit qty (including contractor's profit) 180.40
ABSTRACT:
A. Cost of Materials Rs: 4693.27
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 15875.00
Total Rs: 20568.27
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 2800.37
Total cost for 100.00 sqm Rs: 23368.64
Rate per sqm (A+B+C+D)/100.0 Rs. 233.70
IRR-CCDW-5-1 Providing and fixing 10 cm thick roughly dressed burnt stone slabs for coping set in
CM 1: 6 proportion by volume with pointing to joints in CM 1 : 3 proportion by volume including
cost of all materials, machinery, labour, finishing, curing etc., complete with initial lead upto
50 m and all lifts.
(Cement content: 7.5 kg / sqm, FA : 0.030 cum/sqm,
Burnt stone slab 10 cm thick 1.05 sqm/ sqm)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nil 0.00 0.00 0.00
( Manual mixing) 0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Mason Cl- II Day 1.00 400.00 400.00
2 Stone chiseller Cl- II Day 1.00 400.00 400.00
3 work inspector Day 0.50 450.00 225.00
4 mazdoor Day 2.00 350.00 700.00
Total cost of Labour Rs: 1725.00
labour component/unit qty 172.50
Add contractor's profit and overhead charges 13.615% 23.50
labour component/unit qty (including contractor's profit) 196.00
259
Canal Cross Drainage Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 3810.75
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 1725.00
Total Rs: 5535.75
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 753.69
Total cost for 10.00 sqm Rs: 6289.44
Rate per sqm (A+B+C+D)/10.0 Rs. 628.90
IRR-CCDW-5-2 Providing and fixing 10 cm thick one line dressed burnt stone slabs for coping set in
CM 1: 6 proportion by volume with pointing to joints in CM 1 : 3 proportion by volume including
cost of all materials, machinery, labour, finishing, curing etc., complete with initial lead upto
50 m and all lifts.
(Cement content: 7.5 kg / sqm, FA : 0.030 cum/sqm, Burnt stone slab 10 cm
thick 1.05 sqm/ sqm)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nil 0.00 0.00 0.00
( Manual mixing) 0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Mason Cl- II Day 1.00 400.00 400.00
2 Stone chiseller Cl- I Day 4.00 445.00 1780.00
3 work inspector Day 0.50 450.00 225.00
4 mazdoor Day 2.00 350.00 700.00
Total cost of Labour Rs: 3105.00
labour component/unit qty 310.50
Add contractor's profit and overhead charges 13.615% 42.30
labour component/unit qty (including contractor's profit) 352.80
ABSTRACT:
A. Cost of Materials Rs: 3810.75
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 3105.00
Total Rs: 6915.75
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 941.58
Total cost for 10.00 sqm Rs: 7857.33
Rate per sqm (A+B+C+D)/10.0 Rs. 785.70
IRR-CCDW-5-3 Providing and fixing 10 cm thick two line dressed burnt stone slabs for coping set in
CM 1: 6 proportion by volume with pointing to joints in CM 1 : 3 proportion by volume including
cost of all materials, machinery, labour, finishing, curing etc., complete with initial lead upto
50 m and all lifts.
(Cement content: 7.5 kg / sqm, FA : 0.030 cum/sqm, Burnt stone slab 10 cm
thick 1.05 sqm/ sqm)
260
Canal Cross Drainage Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nil 0.00 0.00 0.00
( Manual mixing) 0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Mason Cl- II Day 1.00 400.00 400.00
2 Stone chiseller Cl-I Day 8.00 445.00 3560.00
3 work inspector Day 0.50 450.00 225.00
4 mazdoor Day 2.00 350.00 700.00
Total cost of Labour Rs: 4885.00
labour component/unit qty 488.50
Add contractor's profit and overhead charges 13.615% 66.50
labour component/unit qty (including contractor's profit) 555.00
ABSTRACT:
A. Cost of Materials Rs: 3810.75
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 4885.00
Total Rs: 8695.75
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 1183.93
Total cost for 10.00 sqm Rs: 9879.68
Rate per sqm (A+B+C+D)/10.0 Rs. 988.00
IRR-CCDW-5-4 Providing and laying insitu M-15 ( 28 days cube compressive strength not less than 15 N /
sqmm ) grade cement concrete using 20 mm down size approved clean, hard, graded
aggregates for coping slab including cost of all materials, machinery, labour, formwork,
cleaning surface, batching, mixing, placing in position, levelling, compacting, finishing, curing
etc., complete with initial lead upto 50 m and initial lift upto 3 m.
(Cement content: 300 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 53.50 428.00
Fuel / Energy charges Hour 8.00 79.30 634.40
2 5 hp pump ( diesel ) Hour 0.50 10.20 5.10
Fuel / Energy charges Hour 0.50 79.30 39.65
3 Water tanker 8000 ltr Hour 1.00 402.50 402.50
Fuel / Energy charges Hour 1.00 299.90 299.90
Total hire charges of Machinery Rs: 1809.55
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Concrete mixer Hour 8.00 219.70 1757.60
2 Crew for Pump Hour 0.50 111.10 55.55
3 Crew for Water tanker Hour 1.00 177.50 177.50
261
Canal Cross Drainage Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 56724.00
B. Hire charges of Machinery Rs: 1809.55
C. Cost of Labour Rs: 21810.77
Total Rs: 80344.32
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 10938.88
Total cost for 14.67 cum Rs: 91283.20
Rate per cum (A+B+C+D)/14.67 Rs. 6222.40
IRR-CCDW-5-5 Providing and constructing protective railing consisting of in-situ railing posts of size 15 x
15 cm at bottom, 10 x 10 cm at top and 75 cm height at 2 m centre to centre in M-20 grade
concrete using 20 mm down size graded aggregates and with each post reinforced by 4 Nos.
of 8 mm dia main bars embedded in kerb concrete for a depth of 40 cm and 5 Nos. of 6 mm
dia. stirrups including fixing 3 rows of 40 mm dia. GI pipes with one coat of red oxide primer
and two coats of synthetic enamel paint, cost of all materials, machinery, labour, formwork,
finishing, curing etc., complete with lead upto 50 m and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nill 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Mason Class I Day 0.50 445.00 222.50
2 Bar bender Day 0.50 555.00 277.50
3 work inspector Day 0.50 450.00 225.00
4 mazdoor Day 1.50 350.00 525.00
5 Painter Cl- II Day 0.50 400.00 200.00
6 Fitter shuttering Day 0.50 400.00 200.00
Total cost of Labour Rs: 1650.00
labour component/unit qty 165.00
Add contractor's profit and overhead charges 13.615% 22.50
labour component/unit qty (including contractor's profit) 187.50
ABSTRACT:
A. Cost of Materials Rs: 9682.26
262
Canal Cross Drainage Works - Item Unit Rates 2016-17
IRR-CCDW-6-1 Laying and jointing 300 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
50 m and all lifts.
(Cement content: 9.9 kg / joint, FA : 0.01cum/joint, Hemp Yarn : 0.091kg/joint)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nill 0.00 0.00 0.00
( Manual mixing ) 0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Mason Cl- II Day 2.00 400.00 800.00
2 work inspector Day 1.00 450.00 450.00
3 mazdoor Day 3.00 350.00 1050.00
Total cost of Labour Rs: 2300.00
labour component/unit qty 230.00
Add contractor's profit and overhead charges 13.615% 31.30
labour component/unit qty (including contractor's profit) 261.30
ABSTRACT:
A. Cost of Materials Rs: 611.67
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 2300.00
Total Rs: 2911.67
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 396.42
Total cost for 10.00 Joints Rs: 3308.09
Rate per joint (A+B+C+D)/10.0 Rs. 330.80
Note: (1) For NP3 Class - 10% extra over the rates of NP2 Class
(2) For NP4 Class - 20% extra over the rates of NP2 Class
IRR-CCDW-6-2 Laying and jointing 450 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
50 m and all lifts.
(Cement content: 17.4 kg / joint, FA : 0.022cum/joint, Hemp Yarn : 0.127kg/joint)
263
Canal Cross Drainage Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nill 0.00 0.00 0.00
( Manual mixing ) 0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Mason Cl- II Day 2.00 400.00 800.00
2 work inspector Day 1.00 450.00 450.00
3 mazdoor Day 3.00 350.00 1050.00
Total cost of Labour Rs: 2300.00
labour component/unit qty 230.00
Add contractor's profit and overhead charges 13.615% 31.30
labour component/unit qty (including contractor's profit) 261.30
ABSTRACT:
A. Cost of Materials Rs: 1058.64
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 2300.00
Total Rs: 3358.64
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 457.28
Total cost for 10.00 Joints Rs: 3815.92
Rate per joint (A+B+C+D)/10.0 Rs. 381.60
Note: (1) For NP3 Class - 10% extra over the rates of NP2 Class
(2) For NP4 Class - 20% extra over the rates of NP2 Class
IRR-CCDW-6-3 Laying and jointing 600 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
50 m and all lifts.
(Cement content: 24.8 kg / joint, FA : 0.025cum/joint, Hemp Yarn : 0.22kg/joint)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nill 0.00 0.00 0.00
( Manual mixing ) 0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Mason Cl- II Day 2.50 400.00 1000.00
2 work inspector Day 1.00 450.00 450.00
3 mazdoor Day 4.00 350.00 1400.00
Total cost of Labour Rs: 2850.00
labour component/unit qty 285.00
Add contractor's profit and overhead charges 13.615% 38.80
labour component/unit qty (including contractor's profit) 323.80
ABSTRACT:
A. Cost of Materials Rs: 1526.45
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 2850.00
264
Canal Cross Drainage Works - Item Unit Rates 2016-17
Note: (1) For NP3 Class - 10% extra over the rates of NP2 Class
(2) For NP4 Class - 20% extra over the rates of NP2 Class
IRR-CCDW-6-4 Laying and jointing 700 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
50 m and all lifts.
(Cement content: 32.1 kg / joint, FA : 0.031cum/joint, Hemp Yarn : 0.25kg/joint)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nill 0.00 0.00 0.00
( Manual mixing ) 0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Mason Cl- II Day 2.50 400.00 1000.00
2 work inspector Day 1.00 450.00 450.00
3 mazdoor Day 4.00 350.00 1400.00
Total cost of Labour Rs: 2850.00
labour component/unit qty 285.00
Add contractor's profit and overhead charges 13.615% 38.80
labour component/unit qty (including contractor's profit) 323.80
ABSTRACT:
A. Cost of Materials Rs: 1948.50
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 2850.00
Total Rs: 4798.50
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 653.32
Total cost for 10.00 Joints Rs: 5451.82
Rate per joint (A+B+C+D)/10.0 Rs. 545.20
Note: (1) For NP3 Class - 10% extra over the rates of NP2 Class
(2) For NP4 Class - 20% extra over the rates of NP2 Class
IRR-CCDW-6-5 Laying and jointing 800 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
50 m and all lifts.
(Cement content: 39.6 kg / joint, FA : 0.039cum/joint, Hemp Yarn : 0.31kg/joint)
265
Canal Cross Drainage Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nill 0.00 0.00 0.00
( Manual mixing ) 0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Mason Cl- II Day 3.00 400.00 1200.00
2 work inspector Day 1.00 450.00 450.00
3 mazdoor Day 5.00 350.00 1750.00
Total cost of Labour Rs: 3400.00
labour component/unit qty 340.00
Add contractor's profit and overhead charges 13.615% 46.30
labour component/unit qty (including contractor's profit) 386.30
ABSTRACT:
A. Cost of Materials Rs: 2406.15
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 3400.00
Total Rs: 5806.15
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 790.51
Total cost for 10.00 Joints Rs: 6596.66
Rate per joint (A+B+C+D)/10.0 Rs. 659.70
Note: (1) For NP3 Class - 10% extra over the rates of NP2 Class
(2) For NP4 Class - 20% extra over the rates of NP2 Class
IRR-CCDW-6-6 Laying and jointing 900 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
50 m and all lifts.
(Cement content: 44.6 kg / joint, FA : 0.045cum/joint, Hemp Yarn : 0.34kg/joint)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nill 0.00 0.00 0.00
( Manual mixing ) 0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Mason Cl- II Day 3.00 400.00 1200.00
2 work inspector Day 1.00 450.00 450.00
3 mazdoor Day 5.00 350.00 1750.00
Total cost of Labour Rs: 3400.00
labour component/unit qty 340.00
Add contractor's profit and overhead charges 13.615% 46.30
labour component/unit qty (including contractor's profit) 386.30
ABSTRACT:
A. Cost of Materials Rs: 2705.15
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 3400.00
Total Rs: 6105.15
266
Canal Cross Drainage Works - Item Unit Rates 2016-17
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 831.22
Total cost for 10.00 Joints Rs: 6936.37
Rate per joint (A+B+C+D)/10.0 Rs. 693.60
Note: (1) For NP3 Class - 10% extra over the rates of NP2 Class
(2) For NP4 Class - 20% extra over the rates of NP2 Class
IRR-CCDW-6-7 Laying and jointing 1000 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
50 m and all lifts.
(Cement content: 49.5 kg / joint, FA : 0.05cum/joint, Hemp Yarn : 0.377kg/joint)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nill 0.00 0.00 0.00
( Manual mixing ) 0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Mason Cl- II Day 3.00 400.00 1200.00
2 work inspector Day 1.00 450.00 450.00
3 mazdoor Day 6.00 350.00 2100.00
Total cost of Labour Rs: 3750.00
labour component/unit qty 375.00
Add contractor's profit and overhead charges 13.615% 51.10
labour component/unit qty (including contractor's profit) 426.10
ABSTRACT:
A. Cost of Materials Rs: 3002.19
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 3750.00
Total Rs: 6752.19
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 919.31
Total cost for 10.00 Joints Rs: 7671.5
Rate per joint (A+B+C+D)/10.0 Rs. 767.20
Note: (1) For NP3 Class - 10% extra over the rates of NP2 Class
(2) For NP4 Class - 20% extra over the rates of NP2 Class
IRR-CCDW-6-8 Laying and jointing 1100 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
50 m and all lifts.
(Cement content: 56.9 kg / joint, FA : 0.058cum/joint, Hemp Yarn : 0.415kg/joint)
267
Canal Cross Drainage Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nill 0.00 0.00 0.00
( Manual mixing ) 0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Mason Cl- II Day 3.00 400.00 1200.00
2 work inspector Day 1.00 450.00 450.00
3 mazdoor Day 6.00 350.00 2100.00
Total cost of Labour Rs: 3750.00
labour component/unit qty 375.00
Add contractor's profit and overhead charges 13.615% 51.10
labour component/unit qty (including contractor's profit) 426.10
ABSTRACT:
A. Cost of Materials Rs: 3438.65
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 3750.00
Total Rs: 7188.65
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 978.73
Total cost for 10.00 Joints Rs: 8167.38
Rate per joint (A+B+C+D)/10.0 Rs. 816.70
Note: (1) For NP3 Class - 10% extra over the rates of NP2 Class
(2) For NP4 Class - 20% extra over the rates of NP2 Class
IRR-CCDW-6-9 Laying and jointing 1200 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
50 m and all lifts.
(Cement content: 66.8 kg / joint, FA : 0.069cum/joint, Hemp Yarn : 0.453kg/joint)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nill 0.00 0.00 0.00
( Manual mixing ) 0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Mason Cl- II Day 4.00 400.00 1600.00
2 work inspector Day 1.00 450.00 450.00
3 mazdoor Day 7.00 350.00 2450.00
Total cost of Labour Rs: 4500.00
labour component/unit qty 450.00
Add contractor's profit and overhead charges 13.615% 61.30
labour component/unit qty (including contractor's profit) 511.30
ABSTRACT:
A. Cost of Materials Rs: 4013.81
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 4500.00
Total Rs: 8513.81
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 1159.16
268
Canal Cross Drainage Works - Item Unit Rates 2016-17
Note: (1) For NP3 Class - 10% extra over the rates of NP2 Class
(2) For NP4 Class - 20% extra over the rates of NP2 Class
IRR-CCDW-7-1 Providing rubble / boulder and sand filling behind abutment and return walls in layers
including cost of all materials, machinery, labour, watering, ramming etc., complete with initial
lead upto 50 m and initial lift upto 3 m.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nill 0.00 0.00 0.00
( Manual mixing ) 0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 0.50 450.00 225.00
2 Mason Cl II Day 1.00 400.00 400.00
3 mazdoor Day 4.00 350.00 1400.00
Total cost of Labour Rs: 2025.00
labour component/unit qty 202.50
Add contractor's profit and overhead charges 13.615% 27.60
labour component/unit qty (including contractor's profit) 230.10
ABSTRACT:
A. Cost of Materials Rs: 3560.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 2025.00
Total Rs: 5585.00
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 760.4
Total cost for 10.00 cum Rs: 6345.4
Rate per cum (A+B+C+D)/10.0 Rs. 634.50
IRR-CCDW-7-2 Providing and filling murrum / gravely soil ( CNS soil ) for foundation or around pipes
including breaking clods, spreading in layers of 10 to 15 cm, watering, compaction by earth
masters to achieve density control of not less than 95 percent etc., complete with lead
upto 50 m and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nill 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
269
Canal Cross Drainage Works - Item Unit Rates 2016-17
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Cartman with double bullock cart Day 0.50 465.00 232.50
2 work inspector Day 0.50 450.00 225.00
3 mazdoor Day 6.00 350.00 2100.00
Total cost of Labour Rs: 2557.50
labour component/unit qty 255.80
Add contractor's profit and overhead charges 13.615% 34.80
labour component/unit qty (including contractor's profit) 290.60
ABSTRACT:
A. Cost of Materials Rs: 1980.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 2557.50
Total Rs: 4537.50
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 617.78
Total cost for 10.00 cum Rs: 5155.28
Rate per cum (A+B+C+D)/10.0 Rs. 515.50
IRR-CCDW-7-3 Providing and filling murum / gravely soil ( CNS soil ) for foundation or above pipes
including breaking clods, spreading in layers of 10 to 15 cm, watering, compaction by power
roller to achieve density control of not less than 98 percent etc., complete with lead upto
50 m and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Diesel road roller 8-10 tonne Hour 0.17 197.20 33.65
Fuel / Energy charges Hour 0.17 714.00 121.84
Total hire charges of Machinery Rs: 155.49
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Operator road roller Hour 0.17 210.90 35.99
2 Cartman with double bullock cart Day 0.50 465.00 232.50
3 work inspector Day 0.50 450.00 225.00
4 mazdoor Day 1.50 350.00 525.00
Total cost of Labour Rs: 1018.49
labour component/unit qty 101.80
Add contractor's profit and overhead charges 13.615% 13.90
labour component/unit qty (including contractor's profit) 115.70
ABSTRACT:
A. Cost of Materials Rs: 1980.00
B. Hire charges of Machinery Rs: 155.49
C. Cost of Labour Rs: 1018.49
Total Rs: 3153.98
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 429.42
Total cost for 10.00 cum Rs: 3583.40
Rate per cum (A+B+C+D)/10.0 Rs. 358.30
IRR-CCDW-7-4 Providing and fixing one line dressed 111x35x25 cm thick IRC standard kilometre stone in
cement concrete M-10 grade with 40 mm down size aggregates including excavating pit of
size 70x45x40 cm, embedding the stone by 30 cm in concrete, providing 2 coats synthetic
enamel paint of approved quality and colour to exposed surfaces and lettering as directed, cost
of all materials, labour, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
270
Canal Cross Drainage Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
( Manual mixing ) 0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Mason Cl- II Day 1.00 400.00 400.00
2 work inspector Day 1.00 450.00 450.00
3 mazdoor Day 1.00 350.00 350.00
4 Painter Cl- I Day 1.00 510.00 510.00
Total cost of Labour Rs: 1710.00
labour component/unit qty 427.50
Add contractor's profit and overhead charges 13.615% 58.20
labour component/unit qty (including contractor's profit) 485.70
ABSTRACT:
A. Cost of Materials Rs: 3362.75
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 1710.00
Total Rs: 5072.75
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 690.65
Total cost for 4.00 Nos. Rs: 5763.4
Rate per No. (A+B+C+D)/4.0 Rs. 1440.90
IRR-CCDW-7-5 Providing and fixing one line dressed 65x15x10 cm thick IRC standard hectometre stone in
cement concrete M-10 grade with 40 mm down size aggregates including excavating pit of
size 50x45x40 cm, embedding the stone by 30 cm in concrete, providing 2 coats synthetic
enamel paint of approved quality and colour to exposed surfaces and lettering as directed, cost
of all materials, labour, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
271
Canal Cross Drainage Works - Item Unit Rates 2016-17
in Rs. in Rs.
1 Mason Cl- II Day 1.00 400.00 400.00
2 work inspector Day 1.00 450.00 450.00
3 mazdoor Day 1.00 350.00 350.00
4 Painter Cl- I Day 0.50 510.00 255.00
Total cost of Labour Rs: 1455.00
labour component/unit qty 363.80
Add contractor's profit and overhead charges 13.615% 49.50
labour component/unit qty (including contractor's profit) 413.30
ABSTRACT:
A. Cost of Materials Rs: 2236.75
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 1455.00
Total Rs: 3691.75
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 502.63
Total cost for 4.00 Nos. Rs: 4194.38
Rate per No. (A+B+C+D)/4.0 Rs. 1048.60
272
Gates and Allied Works - Item Unit Rates 2016-17
CHAPTER-V
HYDRAULIC GATES AND ALLIED EQUIPMENT - Standard Data
1 All materials / bought out components for embedded parts, gates, hoists and allied works
shall conform to relevant Indian standards / technical specifications and approved drawings.
2 The basic rates are EXCLUSIVEof preparation of designs / drawings / material schedules etc.,
as per specifications and other technical data including revisions.
If designs &drawings are to be done by private agency 2% of estimated cost be added
3 The basic rates are inclusive of cost of all materials, machinery, labour, fabrication, erection,
commissioning and testing of gates, hoists and other related components as per technical
specifications.
4 The basic rates are inclusive of finishing, wastage of materials , incidental works, temperary
supports, all enabling works, profit, overheads, small tools / plants, hidden cost
on labour etc.
5 The basic rates are inclusive of taxes, duties (excise ), levies and all other incidental charges including
turn over tax/sales tax on works contract. Separate provision shall be made in the estimate towards such
tax on works contract at the rate prevailing at the time of preparation of estimate.
6 The basic rates are inclusive of all leads and lifts including rehandling.
8 The basic rates are inclusive of preparatory works such as rectification of damages, repairing
shop painting, cleaning, positioning and anchoring first stage embedments,
9 The basic rates are not inclusive of painting with or without sand blasting,and are to be added to the rate as
perschedule rates formulated in the same chapter as per applicability and specifications
10 The basic rates are exclusive of cost of river diversion arrangements, dewatering, desilting ,secondary concreting
of EM parts etc., which form part of civil works.
12 Add AREA ALLOWANCES AS APPLICABLE ON LABOUR COMPONENT ONLY ( SHOWN UNDER EACH ITEM)
14 Painting Charges added extra to the data items as per applicability wherver necessary
15 HOIST EQUIPMENT1.-where sand blasting is not possible, hand and power tool cleaning be
adopted - Guidance may be taken from Mechanical workshop in this regard
2. Machined surfaces should not be painted
3. for maintenance unless sand blasting is essential hand and power tool cleaning be adopted
16 Painting of Hoast Gates is to be done as per IS 14177:1994
273
Gates and Allied Works - Item Unit Rates 2016-17
as perscedule of rates under itemsinthis chapter and add as applicable separately)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Welding transformer Hour 1945.00 16.00 31120.00
Fuel / Energy charges Hour 1945.00 67.20 130704.00
Tower crane/heavy duty tyre
2 mounted crane Hour 16.00 867.10 13873.60
Fuel / Energy charges Hour 16.00 145.70 2331.20
3 Plate shearing machine Hour 16.00 41.90 670.40
Fuel / Energy charges Hour 16.00 112.10 1793.60
4 Pug cutting machine Hour 76.00 6.40 486.40
Fuel / Energy charges Hour 76.00 2.80 212.80
5 Mobile crane 16 Tonnes Hour 22.00 2278.10 50118.20
Fuel / Energy charges Hour 22.00 75.00 1650.00
6 Stationery derric crane Hour 64.00 86.10 5510.40
Fuel / Energy charges Hour 64.00 0.00 0.00
7 Grinding machine Hour 30.00 22.50 675.00
Fuel / Energy charges Hour 30.00 28.00 840.00
8 Drilling machines Hour 30.00 22.50 675.00
Fuel / Energy charges Hour 30.00 28.00 840.00
9 Planing machine Hour 100.00 117.80 11780.00
Fuel / Energy charges Hour 100.00 84.10 8410.00
10 Bending Machine Hour 30.00 42.60 1278.00
Fuel / Energy charges Hour 30.00 84.10 2523.00
11 Sundries LS 100.00 30.00 3000.00
Total hire charges of Machinery Rs: 268491.60
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Tower crane Hour 16.00 189.30 3028.80
2 Crew for Mobile crane 16 T Hour 22.00 526.70 11587.40
3 Crew for Shearing machine Hour 16.00 142.00 2272.00
4 Crew for Planing machine Hour 100.00 210.90 21090.00
5 Crew for Drilling machine Hour 30.00 198.90 5967.00
6 Crew for Grinding machine Hour 30.00 198.90 5967.00
7 Crew for Bending machine 30.00 131.80 3954.00
8 Foreman Day 15.00 510.00 7650.00
9 Marker / Fabricator / Erector Day 75.00 550.00 41250.00
10 Gas cutter Day 20.00 445.00 8900.00
11 Welder ( General ) Day 212.00 445.00 94340.00
12 Welder ( X - ray ) Day 48.00 510.00 24480.00
13 Khalasi Day 345.00 445.00 153525.00
14 Helper fabrication / erection Day 255.00 400.00 102000.00
15 Electrician Day 5.00 515.00 2575.00
Total cost of Labour Rs: 488586.20
274
Gates and Allied Works - Item Unit Rates 2016-17
Add towards highly skilled labour charges @ 30% on total cost of labour 146575.86
Total Cost of Labour 635162.06
ABSTRACT:
A. Cost of Materials Rs: 962659.23
B. Hire charges of Machinery Rs: 268491.60
C. Cost of Labour Rs: 635162.06
Total Rs: 1866312.89
D.Add for excise duty 0.00% Rs: 0.00
(on 75 percent cost excluding cost of materials) Total Rs: 1866312.89
E. Add for transportation upto work site @ 3% Rs: 55989.39
Total Rs: 1922302.28
F. Add for contractor's profit and overheads on
(A+B+C+D+E) 13.615% Rs: 261721.46
Add 2 leads
Add 1 km lead charges for fabricated parts Rs. 19.00 per tonne 581.4
Unloading charges of fabricated parts Rs 74.80 per tonne 2288.88
Total cost for 15.300 tonne Rs: 2186894.02
Rate per tonne Rs: 142934.20
RADIAL GATES
A-2 Gates
IRR-GAW-1-2 fabrication, supply, erection, testing and commissioning of radial gate consisting
of skin plate, stiffeners, horizontal girders, radial arms, trunnion assemblies, tie beam, pulley
supports, bracings, rubber seals, clamps etc., with all accessories for spillway/canals including cost
of all materials, machinery, labour, seal fixing etc., complete as per specifications and approved drawings
(without painting on sand-blasted or mechanical cleaning surfaces which are added extra
as perscedule of rates under itemsinthis chapter and add as applicable separately)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Welding transformer Hour 156.00 16.00 2496.00
Fuel / Energy charges Hour 156.00 67.20 10483.20
275
Gates and Allied Works - Item Unit Rates 2016-17
2 Plate shearing machine Hour 29.00 41.90 1215.10
Fuel / Energy charges Hour 29.00 112.10 3250.90
3 Pug cutting machine Hour 114.00 6.40 729.60
Fuel / Energy charges Hour 114.00 2.80 319.20
4 Bending machine Hour 116.00 42.60 4941.60
Fuel / Energy charges Hour 116.00 84.10 9755.60
5 Tower crane 5 t cpacity Hour 29.00 867.10 25145.90
Fuel / Energy charges Hour 29.00 145.70 4225.30
6 Mobile derric crane Hour 58.00 519.70 30142.60
Fuel / Energy charges Hour 58.00 299.90 17394.20
7 Stationery derric crane Hour 58.00 86.10 4993.80
Fuel / Energy charges Hour 58.00 0.00 0.00
8 Grinding machine Hour 58.00 22.50 1305.00
Fuel / Energy charges Hour 58.00 28.00 1624.00
9 Drilling machines Hour 58.00 22.50 1305.00
Fuel / Energy charges Hour 58.00 28.00 1624.00
10 Mobile Crane 30 T Hour 100.00 3096.80 309680.00
Fuel / Energy charges Hour 100.00 118.80 11880.00
11 Sundries LS 500.00 30.00 15000.00
Total hire charges of Machinery Rs: 457511.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Mobile crane 30T Hour 100.00 526.70 52670.00
2 Crew for Tower crane Hour 29.00 189.30 5489.70
3 Crew for Bending machine Hour 116.00 131.80 15288.80
4 Crew for Drilling machine Hour 58.00 198.90 11536.20
5 Crew for Grinding machine Hour 58.00 198.90 11536.20
6 Foreman Day 29.00 510.00 14790.00
7 Marker / Fabricator / Erector Day 145.00 550.00 79750.00
8 Gas cutter Day 29.00 445.00 12905.00
9 Welder ( General ) Day 17.00 445.00 7565.00
10 Welder ( X - ray ) Day 5.00 510.00 2550.00
11 Khalasi Day 493.00 445.00 219385.00
12 Helper fabrication / erection Day 667.00 400.00 266800.00
13 Electrician Day 15.00 515.00 7725.00
Total cost of Labour Rs: 707990.90
Add towards highly skilled labour charges @ 30% on total cost of labour 212397.27
Total Cost of Labour 920388.17
ABSTRACT:
A. Cost of Materials Rs: 1881612.80
B. Hire charges of Machinery Rs: 457511.00
C. Cost of Labour Rs: 920388.17
Total Rs: 3259511.97
D. Add for excise duty 0.00% Rs: 0.00
(on 75 percent cost excluding cost of materials) Total Rs: 3259511.97
E. Add for transportation upto work site @ 3% Rs: 97785.36
Total Rs: 3357297.33
F. Add for contractor's profit and overheads on
(A+B+C+D+E) 13.615% Rs: 457096.03
Add 2 leads
Add 1 km lead charges for fabricated parts Rs. 19.00 per tonne 1102
Unloading charges of fabricated parts Rs 74.80 per tonne 4338.4
Total cost for 29.000 tonne Rs: 3819833.76
Rate per tonne Rs. 131718.40
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Welding transformer Hour 566.00 16.00 9056.00
Fuel / Energy charges Hour 353.00 67.20 23721.60
2 Tower crane 5 t capacity Hour 4.00 867.10 3468.40
Fuel / Energy charges Hour 4.00 145.70 582.80
3 Pug cutting machine Hour 53.00 6.40 339.20
Fuel / Energy charges Hour 53.00 2.80 148.40
4 Mobile derric crane Hour 50.00 519.70 25985.00
Fuel / Energy charges Hour 50.00 299.90 14995.00
5 Grinding machine Hour 8.00 22.50 180.00
Fuel / Energy charges Hour 8.00 28.00 224.00
6 Drilling machines Hour 16.00 22.50 360.00
Fuel / Energy charges Hour 16.00 28.00 448.00
7 Sundries LS 100.00 30.00 3000.00
Total hire charges of Machinery Rs: 82508.40
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Mobile crane Hour 50.00 177.50 8875.00
2 Crew for Tower crane Hour 4.00 189.30 757.20
3 Crew for Drilling machine Hour 16.00 198.90 3182.40
4 Crew for Grinding machine Hour 8.00 198.90 1591.20
5 Foreman Day 35.00 510.00 17850.00
Marker / Fabricator / Erector /
6 Mechanic Day 58.00 550.00 31900.00
7 Gas cutter Day 18.00 445.00 8010.00
277
Gates and Allied Works - Item Unit Rates 2016-17
8 Welder ( General ) Day 53.00 445.00 23585.00
9 Khalasi Day 20.00 445.00 8900.00
10 Helper fabrication / erection Day 175.00 400.00 70000.00
11 Electrician Day 3.00 515.00 1545.00
Total cost of Labour Rs: 176195.80
Add towards highly skilled labour charges @ 30% on total cost of labour 52858.74
Total Cost of Labour 229054.54
ABSTRACT:
A. Cost of Materials Rs: 2998355.10
B. Hire charges of Machinery Rs: 82508.40
C. Cost of Labour Rs: 229054.54
Total Rs: 3309918.04
D. Add for excise duty 0.00% Rs: 0.00
(on 75 percent cost excluding cost of materials) Total Rs: 3309918.04
E. Add for transportation upto work site @ 3% Rs: 99297.54
Total Rs: 3409215.58
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Welding transformer Hour 150.00 16.00 2400.00
Fuel / Energy charges Hour 150.00 67.20 10080.00
2 Tower crane Hour 6.00 867.10 5202.60
Fuel / Energy charges Hour 6.00 145.70 874.20
3 Pug cutting machine Hour 12.00 6.40 76.80
Fuel / Energy charges Hour 12.00 2.80 33.60
4 Mobile CRANE 16T Hour 8.00 2278.10 18224.80
Fuel / Energy charges Hour 8.00 75.00 600.00
5 Grinding machine Hour 12.00 22.50 270.00
Fuel / Energy charges Hour 12.00 28.00 336.00
278
Gates and Allied Works - Item Unit Rates 2016-17
6 Drilling machines Hour 12.00 22.50 270.00
Fuel / Energy charges Hour 12.00 28.00 336.00
7 Bending Machine Hour 10.00 42.60 426.00
Fuel / Energy charges Hour 10.00 84.10 841.00
8 Sundries LS 10.00 30.00 300.00
Total hire charges of Machinery Rs: 40271.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Mobile crane 16T Hour 10.00 526.70 5267.00
2 Crew for Tower crane Hour 6.00 189.30 1135.80
3 Crew for Drilling machine Hour 12.00 198.90 2386.80
4 Crew for Grinding machine Hour 12.00 198.90 2386.80
5 Crew for Bending machine Hour 10.00 131.80 1318.00
6 Foreman Day 6.00 510.00 3060.00
7 Marker / Fabricator / Erector Day 25.00 550.00 13750.00
8 Gas cutter Day 5.00 445.00 2225.00
9 Welder ( General ) Day 20.00 445.00 8900.00
10 Helper fabrication / erection Day 200.00 400.00 80000.00
11 Electrician Day 2.00 515.00 1030.00
Total cost of Labour Rs: 121459.40
Add towards highly skilled labour charges @ 30% on total cost of labour 36437.82
Total Cost of Labour 157897.22
ABSTRACT:
A. Cost of Materials Rs: 243475.20
B. Hire charges of Machinery Rs: 40271.00
C. Cost of Labour Rs: 157897.22
Total Rs: 441643.42
D. Add for excise duty 0.00% Rs: 0.00
(on 75 percent cost excluding cost of materials) Total Rs: 441643.42
E. Add for transportation upto work site @ 3% Rs: 13249.30
Total Rs: 454892.72
F. Add for contractor's profit and overheads on
(A+B+C+D+E) 13.615% Rs: 61933.64
Add 2 leads
Add 1 km lead charges for fabricated parts Rs. 19.00 per tonne 198.36
Unloading charges of fabricated parts Rs 74.80 per tonne 780.912
Total cost for 5.22 MT Rs: 517805.64
Rate per MT Rs: 99196.50
279
Gates and Allied Works - Item Unit Rates 2016-17
10 Use rate welding holder set Hour 385.00 7.80 3003.00
11 Use rate gas cutting torch set Hour 225.00 24.17 5437.50
12 Sundries LS 40.00 30.00 1200.00
Total cost of Materials Rs: 392854.00
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Welding transformer Hour 385.00 16.00 6160.00
Fuel / Energy charges Hour 385.00 67.20 25872.00
2 Plate shearing machine Hour 8.00 41.90 335.20
Fuel / Energy charges Hour 8.00 112.10 896.80
3 Pug cutting machine Hour 110.00 6.40 704.00
Fuel / Energy charges Hour 110.00 2.80 308.00
4 Planing machine Hour 270.00 117.80 31806.00
Fuel / Energy charges Hour 270.00 84.10 22707.00
5 Mobile Crane 16 T Hour 24.00 2278.10 54674.40
Fuel / Energy charges Hour 24.00 75.00 1800.00
6 Stationery derric crane Hour 14.00 86.10 1205.40
Fuel / Energy charges Hour 14.00 0.00 0.00
7 Grinding machine Hour 14.00 22.50 315.00
Fuel / Energy charges Hour 14.00 28.00 392.00
8 Drilling machines Hour 21.00 22.50 472.50
Fuel / Energy charges Hour 21.00 28.00 588.00
9 Bending Machine Hour 14.00 42.60 596.40
Fuel / Energy charges Hour 14.00 84.10 1177.40
10 Sundries LS 40.00 30.00 1200.00
Total hire charges of Machinery Rs: 151210.10
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Mobile crane 16 T Hour 24.00 526.70 12640.80
2 Crew for Planing machine Hour 270.00 210.90 56943.00
3 Crew for Drilling machine Hour 21.00 198.90 4176.90
4 Crew for Grinding machine Hour 14.00 198.90 2784.60
5 Crew for Bending machine Hour 14.00 131.80 1845.20
6 Foreman Day 32.00 510.00 16320.00
7 Marker / Fabricator / Erector Day 35.00 550.00 19250.00
8 Gas cutter Day 9.00 445.00 4005.00
9 Welder ( General ) Day 46.00 445.00 20470.00
10 Welder ( X - ray ) Day 6.00 510.00 3060.00
11 Helper fabrication / erection Day 240.00 400.00 96000.00
12 Electrician Day 4.00 515.00 2060.00
Total cost of Labour Rs: 239555.50
Add towards highly skilled labour charges @ 30% on total cost of labour 71866.65
Total Cost of Labour 311422.15
ABSTRACT:
A. Cost of Materials Rs: 392854.00
B. Hire charges of Machinery Rs: 151210.10
C. Cost of Labour Rs: 311422.15
Total Rs: 855486.25
D. Add for excise duty 0.00% Rs: 0.00
(on 75 percent cost excluding cost of materials) Total Rs: 855486.25
E. Add for transportation upto work site @ 3% Rs: 25664.59
Total Rs: 881150.84
F. Add for contractor's profit and overheads on
(A+B+C+D+E) 13.615% Rs: 119968.69
Add 2 leads
Add 1 km lead charges for fabricated parts Rs. 19.00 per tonne 239.4
Unloading charges of fabricated parts Rs 74.80 per tonne 942.48
Total cost for 6.30 tonne Rs: 1002301.40
Rate per tonne Rs: 159095.50
vertical lift gates and stop log gate elements ( SLIDING GATES)
280
Gates and Allied Works - Item Unit Rates 2016-17
IRR-GAW-2-2 Design, fabrication, supply, erection, testing and commissioning of vertical lift gates and
stoplog gate elements, consisting of skin plate,
horizontal and vertical girders, stiffeners, lifting pins, bronze padded slide blocks/bearings, guide shoes,
rubber seals, clamps etc., with all accessories including cost of all materials,
machinery, labour, seal fixing etc.,complete as per specifications and approved drawings
(without painting on sand-blasted or mechanical cleaning surfaces which are added extra
as perscedule of rates under items in this chapter and add as applicable separately)
Drawing NO. CE/CDO/CL3/MRP/783/2002 (Spillway Stop log gate Elements of Madduvalasa Project)
Vent Size: 12.624 X 0.50 M 16 Elements
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Welding transformer Hour 12880.00 16.00 206080.00
Fuel / Energy charges Hour 12880.00 67.20 865536.00
2 Pug cutting machine Hour 6440.00 6.40 41216.00
Fuel / Energy charges Hour 6440.00 2.80 18032.00
3 Mobile crane 16 T Hour 360.00 2278.10 820116.00
Fuel / Energy charges Hour 360.00 75.00 27000.00
4 Stationery derric crane Hour 238.00 86.10 20491.80
Fuel / Energy charges Hour 238.00 0.00 0.00
5 Grinding machine Hour 238.00 22.50 5355.00
Fuel / Energy charges Hour 238.00 28.00 6664.00
6 Drilling machines Hour 357.00 22.50 8032.50
Fuel / Energy charges Hour 357.00 28.00 9996.00
7 Bending Machine Hour 240.00 42.60 10224.00
Fuel / Energy charges Hour 240.00 84.10 20184.00
8 Sundries LS 180.00 30.00 5400.00
Total hire charges of Machinery Rs: 2064327.30
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Mobile crane 16T Hour 360.00 526.70 189612.00
2 Crew for Drilling machine Hour 357.00 198.90 71007.30
3 Crew for Grinding machine Hour 238.00 198.90 47338.20
4 Crew for Bending machine Hour 240.00 131.80 31632.00
5 Foreman Day 120.00 510.00 61200.00
6 Marker / Fabricator / Erector Day 195.00 550.00 107250.00
7 Gas cutter Day 100.00 445.00 44500.00
8 Welder ( General ) Day 1442.00 445.00 641690.00
9 Welder ( X - ray ) Day 275.00 510.00 140250.00
10 Khalasi Day 2023.00 445.00 900235.00
11 Helper fabrication / erection Day 2727.00 400.00 1090800.00
12 Electrician Day 10.00 515.00 5150.00
Total cost of Labour Rs: 3330664.50
281
Gates and Allied Works - Item Unit Rates 2016-17
Add towards highly skilled labour charges @ 30% on total cost of labour 999199.35
Total Cost of Labour 4329863.85
ABSTRACT:
A. Cost of Materials Rs: 6890999.33
B. Hire charges of Machinery Rs: 2064327.30
C. Cost of Labour Rs: 4329863.85
Total Rs: 13285190.48
D. Add for excise duty 0.00% Rs: 0.00
(on 75 percent cost excluding cost of materials) Total Rs: 13285190.48
E. Add for transportation upto work site @ 3% Rs: 398555.71
Total Rs: 13683746.20
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Welding transformer Hour 187.00 16.00 2992.00
Fuel / Energy charges Hour 117.00 67.20 7862.40
2 Pug cutting machine Hour 60.00 6.40 384.00
Fuel / Energy charges Hour 60.00 2.80 168.00
3 Mobile derric crane Hour 4.00 519.70 2078.80
Fuel / Energy charges Hour 4.00 299.90 1199.60
4 Stationery derric crane Hour 8.00 86.10 688.80
Fuel / Energy charges Hour 8.00 0.00 0.00
5 Grinding machine Hour 2.00 22.50 45.00
282
Gates and Allied Works - Item Unit Rates 2016-17
Fuel / Energy charges Hour 2.00 28.00 56.00
6 Drilling machines Hour 2.00 22.50 45.00
Fuel / Energy charges Hour 2.00 28.00 56.00
7 Sundries LS 10.00 30.00 300.00
Total hire charges of Machinery Rs: 15875.60
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Mobile crane Hour 4.00 177.50 710.00
2 Crew for Drilling machine Hour 2.00 198.90 397.80
3 Crew for Grinding machine Hour 2.00 198.90 397.80
4 Foreman Day 10.00 510.00 5100.00
5 Marker / Fabricator / Erector Day 18.00 550.00 9900.00
6 Gas cutter Day 10.00 445.00 4450.00
7 Welder ( General ) Day 18.00 445.00 8010.00
8 Helper fabrication / erection Day 52.00 400.00 20800.00
9 Electrician Day 1.00 515.00 515.00
Total cost of Labour Rs: 50280.60
Add towards highly skilled labour charges @ 30% on total cost of labour 15084.18
Total Cost of Labour 65364.78
ABSTRACT:
A. Cost of Materials Rs: 256591.70
B. Hire charges of Machinery Rs: 15875.60
C. Cost of Labour Rs: 65364.78
Total Rs: 337832.08
D. Add for excise duty 0.00% Rs: 0.00
(on 75 percent cost excluding cost of materials) Total Rs: 337832.08
E. Add for transportation upto work site @ 3% Rs: 10134.96
Total Rs: 347967.04
F. Add for contractor's profit and overheads on
(A+B+C+D+E) 13.615% Rs: 47375.71
Add 2 leads
Add 1 km lead charges for fabricated parts Rs. 19.00 per tonne 134.064
Unloading charges of fabricated parts Rs 74.80 per tonne 527.788
Total cost for 3.528 tonne Rs: 396004.61
Rate per tonne Rs: 112246.20
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Welding transformer Hour 1197.00 16.00 19152.00
Fuel / Energy charges Hour 748.00 67.20 50265.60
2 Tower crane 5 t capacity Hour 6.00 867.10 5202.60
Fuel / Energy charges Hour 6.00 145.70 874.20
3 Pug cutting machine Hour 235.00 6.40 1504.00
Fuel / Energy charges Hour 235.00 2.80 658.00
4 Mobile derric crane Hour 100.00 519.70 51970.00
Fuel / Energy charges Hour 100.00 299.90 29990.00
5 Grinding machine Hour 32.00 22.50 720.00
Fuel / Energy charges Hour 32.00 28.00 896.00
6 Drilling machines Hour 16.00 22.50 360.00
Fuel / Energy charges Hour 16.00 28.00 448.00
7 Sundries LS 500.00 30.00 15000.00
Total hire charges of Machinery Rs: 177040.40
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Mobile crane Hour 100.00 177.50 17750.00
2 Crew for Tower crane Hour 6.00 189.30 1135.80
3 Crew for Drilling machine Hour 16.00 198.90 3182.40
4 Crew for Grinding machine Hour 32.00 198.90 6364.80
5 Foreman Day 74.00 510.00 37740.00
6 Marker / Fabricator / Erector Day 124.00 550.00 68200.00
7 Gas cutter Day 48.00 445.00 21360.00
8 Welder ( General ) Day 112.00 445.00 49840.00
9 Khalasi Day 20.00 445.00 8900.00
10 Helper fabrication / erection Day 350.00 400.00 140000.00
11 Electrician Day 10.00 515.00 5150.00
Total cost of Labour Rs: 359623.00
Add towards highly skilled labour charges @ 30% on total cost of labour 107886.90
Total Cost of Labour 467509.90
ABSTRACT:
A. Cost of Materials Rs: 4335261.10
B. Hire charges of Machinery Rs: 177040.40
C. Cost of Labour Rs: 467509.90
Total Rs: 4979811.40
284
Gates and Allied Works - Item Unit Rates 2016-17
D. Add for excise duty 0.00% Rs: 0.00
(on 75 percent cost excluding cost of materials) Total Rs: 4979811.40
E. Add for transportation upto work site @ 3% Rs: 149394.34
Total Rs: 5129205.74
F. Add for contractor's profit and overheads on
(A+B+C+D+E) 13.615% Rs: 698341.36
Add 2 leads
Add 1 km lead charges for fabricated parts Rs. 19.00 per tonne 1172.528
Unloading charges of fabricated parts Rs 74.80 per tonne 4616.058
Total cost for 30.856 tonne Rs: 5833335.69
25.000 t capacity Rs:
Rate per tonne Rs: 189050.30
Rate per tonne capacity Rs: 233333.40
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Welding transformer Hour 193.00 16.00 3088.00
Fuel / Energy charges Hour 121.00 67.20 8131.20
2 Mobile derric crane Hour 4.00 519.70 2078.80
Fuel / Energy charges Hour 4.00 299.90 1199.60
3 Grinding machine Hour 8.00 22.50 180.00
Fuel / Energy charges Hour 8.00 28.00 224.00
4 Drilling machines Hour 50.00 22.50 1125.00
Fuel / Energy charges Hour 50.00 28.00 1400.00
5 Sundries LS 10.00 30.00 300.00
Total hire charges of Machinery Rs: 17726.60
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Mobile crane Hour 4.00 177.50 710.00
2 Crew for Drilling machine Hour 50.00 198.90 9945.00
3 Crew for Grinding machine Hour 8.00 198.90 1591.20
4 Foreman Day 8.00 510.00 4080.00
5 Marker / Fabricator / Erector Day 32.00 550.00 17600.00
6 Gas cutter Day 17.00 445.00 7565.00
7 Welder ( General ) Day 18.00 445.00 8010.00
8 Helper fabrication / erection Day 52.00 400.00 20800.00
9 Electrician Day 1.00 515.00 515.00
Total cost of Labour Rs: 70816.20
Add towards highly skilled labour charges @ 30% on total cost of labour 21244.86
Total Cost of Labour 92061.06
ABSTRACT:
A. Cost of Materials Rs: 1124566.57
B. Hire charges of Machinery Rs: 17726.60
C. Cost of Labour Rs: 92061.06
Total Rs: 1234354.23
D. Add for excise duty 0.00% Rs: 0.00
(on 75 percent cost excluding cost of materials) Total Rs: 1234354.23
E. Add for transportation upto work site @ 3% Rs: 37030.63
Total Rs: 1271384.85
F. Add for contractor's profit and overheads on
(A+B+C+D+E) 13.615% Rs: 173099.05
Add 2 leads
Add 1 km lead charges for fabricated parts Rs. 19.00 per tonne 787.436
Unloading charges of fabricated parts Rs 74.80 per tonne 3100.012
Total cost for 200.000 Rm Rs: 1448371.35
Rate per Rm Rs: 7241.90
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Welding transformer Hour 500.00 16.00 8000.00
Fuel / Energy charges Hour 500.00 67.20 33600.00
2 Pug cutting machine Hour 85.00 6.40 544.00
Fuel / Energy charges Hour 85.00 2.80 238.00
286
Gates and Allied Works - Item Unit Rates 2016-17
3 Tower crane Hour 10.00 867.10 8671.00
Fuel / Energy charges Hour 10.00 145.70 1457.00
4 Mobile crane 16 T Hour 30.00 2278.10 68343.00
Fuel / Energy charges Hour 30.00 75.00 2250.00
5 Stationery derric crane Hour 20.00 86.10 1722.00
Fuel / Energy charges Hour 20.00 0.00 0.00
6 Grinding machine Hour 10.00 22.50 225.00
Fuel / Energy charges Hour 10.00 28.00 280.00
7 Drilling machines Hour 30.00 22.50 675.00
Fuel / Energy charges Hour 30.00 28.00 840.00
8 Bending machine Hour 10.00 42.60 426.00
Fuel / Energy charges Hour 10.00 84.10 841.00
9 Sundries LS 50.00 30.00 1500.00
Total hire charges of Machinery Rs: 129612.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Mobile crane 16 T Hour 30.00 526.70 15801.00
2 Crew for Tower crane Hour 10.00 189.30 1893.00
3 Crew for Drilling machine Hour 30.00 198.90 5967.00
4 Crew for Grinding machine Hour 10.00 198.90 1989.00
5 Crew for Bending machine Hour 10.00 131.80 1318.00
6 Foreman Day 16.00 510.00 8160.00
7 Marker / Fabricator / Erector Day 50.00 550.00 27500.00
8 Gas cutter Day 8.00 445.00 3560.00
9 Welder ( General ) Day 52.00 445.00 23140.00
10 Welder ( X - ray grade ) Day 14.00 510.00 7140.00
11 Khalasi Day 170.00 445.00 75650.00
12 Helper fabrication / erection Day 230.00 400.00 92000.00
13 Electrician Day 4.00 515.00 2060.00
Total cost of Labour Rs: 266178.00
Add towards highly skilled labour charges @ 30% on total cost of labour 79853.40
Total Cost of Labour 346031.40
ABSTRACT:
A. Cost of Materials Rs: 647076.37
B. Hire charges of Machinery Rs: 129612.00
C. Cost of Labour Rs: 346031.40
Total Rs: 1122719.77
D. Add for excise duty 0.00% Rs: 0.00
(on 75 percent cost excluding cost of materials) Total Rs: 1122719.77
E. Add for transportation upto work site @ 3% Rs: 33681.59
Total Rs: 1156401.36
F. Add for contractor's profit and overheads on
(A+B+C+D+E) 13.615% Rs: 157444.05
Add 2 leads
Add 1 km lead charges for fabricated parts Rs. 19.00 per tonne 380
Unloading charges of fabricated parts Rs 74.80 per tonne 1496
Total cost for 10.000 tonne Rs: 1315721.40
Rate per tonne Rs: 131572.10
VERTICAL LIFT GATES-ROPE DRUM HOIST UPTO 30 TON CAP. POWER OPERATED
IRR-GAW-2-7 Design, fabrication, supply, erection, testing and commissioning of adequate capacity rope
drum hoist consisting of hoist platform, rope drum, gear system, electric motor, electro-
magnetic brake system, hand operation assembly, control panel, wire rope, pulleys, ladder etc.,
with all accessories for operating river sluice / canal sluice service gate including cost of
all materials, machinery, labour, , complete as per specifications and drawings with all leads and lifts
(without painting on sand-blasted or mechanical cleaning surfaces which are added extra
as perscedule of rates under items in this chapter and add as applicable separately)
DATA:
RATE ANALYSIS UNIT : 6.243 tonne wt
A. MATERIALS: 25 t capacity
Sl No particulars Unit Quantity Rate Amount
in Rs. in Rs.
287
Gates and Allied Works - Item Unit Rates 2016-17
1 Structural steel
Angles / beams / channels / bars kg 1487.00 37.50 55762.50
Plates / flats kg 402.00 37.40 15034.80
Chequered plate kg 290.00 63.00 18270.00
2 Cast steel components :
Rope drums 2 Nos / Gears kg 1926.00 235.00 452610.00
Pinions kg 79.00 225.00 17775.00
Pulleys 3 Nos / Couplings 2 Nos kg 306.00 190.00 58140.00
Plummer blocks / Hubs kg 72.00 190.00 13680.00
3 Alloy steel components
Shafts kg 346.00 235.00 81310.00
Pins kg 73.00 450.00 32850.00
4 Bronze alloy components :
Bronze bearings / bush kg 57.00 970.00 55290.00
Wire rope 28 mm dia 6/37
5 construction kg 325.00 200.00 65000.00
6 MS Bolt / Nut / Washer kg 32.00 80.00 2560.00
7 Worm reducers No. 1.00 224400.00 224400.00
8 Electric motor 5 hp No. 1.00 33000.00 33000.00
9 Manual operating system No. 1.00 28820.00 28820.00
10 Gate position indicator No. 1.00 195800.00 195800.00
11 Ele-magnetic brake No. 1.00 35200.00 35200.00
Electric cable / switch / control panel
12 etc LS 1.00 50380.00 50380.00
13 Oxygen gas cum 45.00 42.00 1890.00
14 Acetyline gas cum 15.00 335.00 5025.00
15 Welding electrodes Nos 80.00 13.00 1040.00
16 Welding electrodes ( LH ) Nos 720.00 15.00 10800.00
17 Grease kg 50.00 275.00 13750.00
18 Use rate welding holder set Hour 85.00 7.80 663.00
19 Use rate gas cutting torch set Hour 16.00 24.17 386.67
20 Sundries LS 25.00 30.00 750.00
Total cost of Materials Rs: 1470186.97
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Welding transformer Hour 85.00 16.00 1360.00
Fuel / Energy charges Hour 53.00 67.20 3561.60
2 Tower crane 5 t capacity Hour 2.00 867.10 1734.20
Fuel / Energy charges Hour 2.00 145.70 291.40
3 Pug cutting machine Hour 15.00 6.40 96.00
Fuel / Energy charges Hour 15.00 2.80 42.00
4 Mobile derric crane Hour 10.00 519.70 5197.00
Fuel / Energy charges Hour 10.00 299.90 2999.00
5 Grinding machine Hour 2.00 22.50 45.00
Fuel / Energy charges Hour 2.00 28.00 56.00
6 Drilling machines Hour 2.00 22.50 45.00
Fuel / Energy charges Hour 2.00 28.00 56.00
7 Sundries LS 25.00 30.00 750.00
Total hire charges of Machinery Rs: 16233.20
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Mobile crane Hour 10.00 177.50 1775.00
2 Crew for Tower crane Hour 2.00 189.30 378.60
3 Crew for Drilling machine Hour 2.00 198.90 397.80
4 Crew for Grinding machine Hour 2.00 198.90 397.80
5 Foreman Day 15.00 510.00 7650.00
6 Marker / Fabricator / Erector Day 19.00 550.00 10450.00
7 Gas cutter Day 4.00 445.00 1780.00
8 Welder ( General ) Day 8.00 445.00 3560.00
9 Khalasi Day 4.00 445.00 1780.00
10 Helper fabrication / erection Day 44.00 400.00 17600.00
11 Electrician Day 2.00 515.00 1030.00
Total cost of Labour Rs: 46799.20
Add towards highly skilled labour charges @ 30% on total cost of labour 14039.76
Total Cost of Labour 60838.96
288
Gates and Allied Works - Item Unit Rates 2016-17
Add contractor's profit and overhead charges 13.615% 331.30
labour component/unit qty (including contractor's profit) 2764.90
ABSTRACT:
A. Cost of Materials Rs: 1470186.97
B. Hire charges of Machinery Rs: 16233.20
C. Cost of Labour Rs: 60838.96
Total Rs: 1547259.13
D. Add for excise duty 0.00% Rs: 0.00
(on 75 percent cost excluding cost of materials) Total Rs: 1547259.13
E. Add for transportation upto work site @ 3% Rs: 46417.77
Total Rs: 1593676.90
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Welding transformer Hour 394.00 16.00 6304.00
Fuel / Energy charges Hour 394.00 67.20 26476.80
2 Pug cutting machine Hour 52.00 6.40 332.80
Fuel / Energy charges Hour 52.00 2.80 145.60
3 Mobile crane 30 T Hour 30.00 3096.80 92904.00
Fuel / Energy charges Hour 30.00 118.80 3564.00
4 Stationery derric crane Hour 20.00 86.10 1722.00
Fuel / Energy charges Hour 20.00 0.00 0.00
5 Drilling machine Hour 20.00 22.50 450.00
Fuel / Energy charges Hour 20.00 28.00 560.00
6 Grinding machine Hour 20.00 22.50 450.00
Fuel / Energy charges Hour 20.00 28.00 560.00
7 Tower Crane Hour 20.00 867.10 17342.00
Fuel / Energy charges Hour 20.00 145.70 2914.00
8 Sundries LS 50.00 30.00 1500.00
Total hire charges of Machinery Rs: 155225.20
289
Gates and Allied Works - Item Unit Rates 2016-17
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Mobile crane 30 T Hour 30.00 526.70 15801.00
2 Crew for Drilling machine Hour 20.00 198.90 3978.00
3 Crew for Grinding machine Hour 20.00 198.90 3978.00
4 Crew for Tower Crane Hour 20.00 189.30 3786.00
5 Foreman Day 10.00 510.00 5100.00
6 Marker / Fabricator / Erector Day 50.00 550.00 27500.00
7 Gas cutter Day 14.00 445.00 6230.00
8 Welder ( General ) Day 53.00 445.00 23585.00
9 Helper fabrication / erection Day 400.00 400.00 160000.00
10 Electrician Day 6.00 515.00 3090.00
Total cost of Labour Rs: 253048.00
Add towards highly skilled labour charges @ 30% on total cost of labour 75914.40
Total Cost of Labour 328962.40
ABSTRACT:
A. Cost of Materials Rs: 530000.30
B. Hire charges of Machinery Rs: 155225.20
C. Cost of Labour Rs: 328962.40
Total Rs: 1014187.90
D. Add for excise duty 0.00% Rs: 0.00
(on 75 percent cost excluding cost of materials) Total Rs: 1014187.90
E. Add for transportation upto work site @ 3% Rs: 30425.64
Total Rs: 1044613.54
F. Add for contractor's profit and overheads on
(A+B+C+D+E) 13.615% Rs: 142224.13
Add 2 leads
Add 1 km lead charges for fabricated parts Rs. 19.00 per tonne 399
Unloading charges of fabricated parts Rs 74.80 per tonne 1570.8
Total cost for 10.500 tonne Rs: 1188807.47
Rate per tonne Rs: 113219.80
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Welding transformer Hour 47.00 16.00 752.00
Fuel / Energy charges Hour 47.00 67.20 3158.40
2 Tower crane 5 t capacity Hour 2.00 867.10 1734.20
Fuel / Energy charges Hour 2.00 145.70 291.40
3 Pug cutting machine Hour 9.00 6.40 57.60
Fuel / Energy charges Hour 9.00 2.80 25.20
4 Mobile derric crane Hour 10.00 519.70 5197.00
Fuel / Energy charges Hour 10.00 299.90 2999.00
5 Grinding machine Hour 2.00 22.50 45.00
Fuel / Energy charges Hour 2.00 28.00 56.00
6 Drilling machines Hour 2.00 22.50 45.00
Fuel / Energy charges Hour 2.00 28.00 56.00
7 Sundries LS 25.00 30.00 750.00
Total hire charges of Machinery Rs: 15166.80
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Mobile crane Hour 10.00 177.50 1775.00
2 Crew for Tower crane Hour 2.00 189.30 378.60
3 Crew for Drilling machine Hour 2.00 198.90 397.80
4 Crew for Grinding machine Hour 2.00 198.90 397.80
5 Foreman Day 13.00 510.00 6630.00
6 Marker / Fabricator / Erector Day 17.00 550.00 9350.00
7 Gas cutter Day 3.00 445.00 1335.00
8 Welder ( General ) Day 5.00 445.00 2225.00
9 Khalasi Day 4.00 445.00 1780.00
10 Helper fabrication / erection Day 36.00 400.00 14400.00
11 Electrician Day 2.00 515.00 1030.00
Total cost of Labour Rs: 39699.20
Add towards highly skilled labour charges @ 30% on total cost of labour 11909.76
Total Cost of Labour 51608.96
ABSTRACT:
A. Cost of Materials Rs: 1465313.60
B. Hire charges of Machinery Rs: 15166.80
C. Cost of Labour Rs: 51608.96
Total Rs: 1532089.36
D. Add for excise duty 0.00% Rs: 0.00
(on 75 percent cost excluding cost of materials) Total Rs: 1532089.36
E. Add for transportation upto work site @ 3% Rs: 45962.68
Total Rs: 1578052.04
DATA: Screw type hoist for operating gate consists of supporting structure, hoist body, hoist stem,
thrust bearings, operating wheel / handle with related accessories.
Consider screw type hoist for canal escape / regulator gate for vent opening of size 2 m x 2 m.
Actual capacity of hoist as per data : 3.000 tonnes
Weight of hoist with all accessories is assumed at 0.3 tonne per tonne capacity of hoist.
The actual weight of screw hoist as per data sheet : 0.871 tonnes
Consider actual weight for data rate analysis.
1 Requirement of materials:
a. Structural steel conforming to IS : 2062 :
Angles / Beams / Channels / Bars with 2.5 % wastage : 402.00 kg
Plates / Flats with 2.5 % wastage : 145.00 kg
Chequered plates with 2.5 % wastage : 176.00 kg
b. Cast iron components conforming to IS : 210 :
Hoist body / Lock nut / Main nut : 55.00 kg
c. Alloy steel components conforming to IS : 1570 :
Hoist stem : 75.00 kg
d. Alluminium/ Bronze alloy components conforming to IS : 305 :
Bearings / Bush : 4.00 kg
e. Bolt / Nut / Washers conforming to IS : 1363 :
MS Bolts / Nuts / Washers with 2.5 % wastage : 8.00 kg
MS pipe 32 mm dia : 8.8 Rm
f. Welding electrodes :
Welding electrodes for stitch welding at 10 % of total with 2.5 % wastage : 7 Nos
Welding electrodes for run welding at 90 % of total with 2.5 % wastage : 66 Nos
2 Cutting :
Total length of cutting assuming cutting for 2 sides : 18 Rm
Add for variations ( cutting for more than 2 sides / odd shapes etc ) at 10 %
: 2 Rm
Total : 20 Rm
For cutting structural steel sections to required sizes gas cutting is assumed.
Time for gas cutting manually assuming average cutting progress of 2 m /: hour 10 hours
Acetelyne gas @ 0.6 cum / hour ( 10 x 0.60 ) : 6 cum
Oxygen gas @ 1.8 cum / hour ( 10 x 1.80 ) : 18 cum
Use of gas cutting torch with 50 min / hr working ( 10 x 60 / 50 ) : 12 hours
3 Welding :
Length of welding : 10 Rm
For stich welding @ 2 hrs usage / shift & @ 15 electrodes / hr
( 7 / 15 ) x 8 / 2 : 2 hours
For run welding @ 6 hrs usage / shift & @ 15 electrodes / hr
( 66 / 15 ) x 8 / 6 : 6 hours
Total : 8 hours
Deploy welding transformer for 8 hours.
Fuel / Energy charges @ 25 % hrs for stitch welding & @ 75 % hrs for run welding.
( 2 x 0.25 + 6 x 0.75 ) : 5 hours
4 Requirement of other machinery :
For drilling holes for bolts 2 hours use of drilling machine considered.
For grinding and finishing weld joints 2 hours use of grinding machine considered
292
Gates and Allied Works - Item Unit Rates 2016-17
Excise duty is applicable on supply of fabricated parts. The cost of materials is inclusive of all
taxes/ duties. Therefore, for purpose of rate analysis 75 percent of total cost excluding the cost
of materials ( assuming 25 % erection cost ) is considered for assessing excise duty.
7 Use rate of materials :
Cost of welding set @ Rs:
7800.00 / Each Rs: 7800.00
Life of welding set : 1000 hours
Use rate of welding
( cost / life
set )per hour Rs: 7.80
Cost of gas cutting set @ Rs:
14500.00 / Each Rs: 14500.00
Life of gas cutting set : 600 hours
Use rate of gas
( cost
cutting
/ life )set per hr Rs: 24.17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Welding transformer Hour 8.00 16.00 128.00
Fuel / Energy charges Hour 5.00 67.20 336.00
2 Grinding machine Hour 2.00 22.50 45.00
Fuel / Energy charges Hour 2.00 28.00 56.00
3 Drilling machines Hour 2.00 22.50 45.00
Fuel / Energy charges Hour 2.00 28.00 56.00
4 Sundries LS 2.00 30.00 60.00
Total hire charges of Machinery Rs: 726.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Drilling machine Hour 2.00 198.90 397.80
2 Crew for Grinding machine Hour 2.00 198.90 397.80
3 Foreman Day 4.00 510.00 2040.00
4 Marker / Fabricator / Erector Day 5.00 550.00 2750.00
5 Gas cutter Day 2.00 445.00 890.00
6 Welder ( General ) Day 1.00 445.00 445.00
7 Helper fabrication / erection Day 9.00 400.00 3600.00
8 Electrician Day 0.50 515.00 257.50
Total cost of Labour Rs: 10778.10
Add towards highly skilled labour charges @ 30% on total cost of labour 3233.43
Total Cost of Labour 14011.53
ABSTRACT:
A. Cost of Materials Rs: 71441.23
B. Hire charges of Machinery Rs: 726.00
C. Cost of Labour Rs: 14011.53
293
Gates and Allied Works - Item Unit Rates 2016-17
Total Rs: 86178.76
D. Add for excise duty 0.00% Rs: 0.00
(on 75 percent cost excluding cost of materials) Total Rs: 86178.76
E. Add for transportation upto work site @ 3% Rs: 2585.36
Total Rs: 88764.13
F. Add for contractor's profit and overheads on
(A+B+C+D+E) 13.615% Rs: 12085.24
Add 2 leads
Add 1 km lead charges for fabricated parts Rs. 19.00 per tonne 33.098
Unloading charges of fabricated parts Rs 74.80 per tonne 130.302
Total cost for 0.871 tonne Rs: 101012.76
3.000 t capacity Rs:
Rate per tonne Rs: 115973.30
Rate per tonne capacity Rs: 33670.90
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Welding transformer Hour 73.00 16.00 1168.00
Fuel / Energy charges Hour 46.00 67.20 3091.20
2 Pug cutting machine Hour 8.00 6.40 51.20
Fuel / Energy charges Hour 8.00 2.80 22.40
3 Mobile derric crane Hour 4.00 519.70 2078.80
Fuel / Energy charges Hour 4.00 299.90 1199.60
4 Stationery derric crane Hour 8.00 86.10 688.80
294
Gates and Allied Works - Item Unit Rates 2016-17
Fuel / Energy charges Hour 8.00 0.00 0.00
5 Grinding machine Hour 8.00 22.50 180.00
Fuel / Energy charges Hour 8.00 28.00 224.00
6 Drilling machines Hour 16.00 22.50 360.00
Fuel / Energy charges Hour 16.00 28.00 448.00
7 Sundries LS 25.00 30.00 750.00
Total hire charges of Machinery Rs: 10262.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Mobile crane Hour 4.00 177.50 710.00
2 Crew for Drilling machine Hour 16.00 198.90 3182.40
3 Crew for Grinding machine Hour 8.00 198.90 1591.20
4 Foreman Day 14.00 510.00 7140.00
5 Marker / Fabricator / Erector Day 20.00 550.00 11000.00
6 Gas cutter Day 6.00 445.00 2670.00
7 Welder ( General ) Day 7.00 445.00 3115.00
8 Helper fabrication / erection Day 44.00 400.00 17600.00
9 Electrician Day 2.00 515.00 1030.00
Total cost of Labour Rs: 48038.60
Add towards highly skilled labour charges @ 30% on total cost of labour 14411.58
Total Cost of Labour 62450.18
ABSTRACT:
A. Cost of Materials Rs: 575266.10
B. Hire charges of Machinery Rs: 10262.00
C. Cost of Labour Rs: 62450.18
Total Rs: 647978.28
D. Add for excise duty 0.00% Rs: 0.00
(on 75 percent cost excluding cost of materials) Total Rs: 647978.28
E. Add for transportation upto work site @ 3% Rs: 19439.35
Total Rs: 667417.63
IRR-GAW-2-
12
New Item
2015-16-2 OT SLUICE SHUTTERS Screw Gear Hoist Including Platform for below 5 Tons Capacity (Small Gates)
As per Guidelines of Chief Engineer, Central Designs Organization, Hyderabad Specification drawing for
Krishna Delta System
Fabrication, supply, erection, testing and commissioning of Embedded parts consisting of supporting structure,
platform etc. with all accessories for operating canal escape/ regulator gate with all accessories including cost of all
materials, machinery, labour, cutting, bending, aligning, anchoring, welding, finishing etc. complete
as per Specification and approved drawings
(without painting on mechanical cleaning surfaces which are added extra as per schedule of rates
under items in this chapter and add as applicable separately)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Welding transformer Hour 30.00 16.00 480.00
Fuel / Energy charges Hour 30.00 67.20 2016.00
2 Pug cutting machine Hour 12.00 6.40 76.80
Fuel / Energy charges Hour 12.00 2.80 33.60
3 Drilling machine Hour 8.00 22.50 180.00
Fuel / Energy charges Hour 8.00 28.00 224.00
4 Grinding machine Hour 36.00 22.50 810.00
Fuel / Energy charges Hour 36.00 28.00 1008.00
5 Lathe machine (Screw Rod M/C) Hour 16.00 300.00 4800.00
6 Sundries LS 10.00 30.00 300.00
Total hire charges of Machinery Rs: 9928.40
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Drilling machine Hour 8.00 198.90 1591.20
2 Crew for Grinding machine Hour 36.00 198.90 7160.40
3 Foreman Day 2.00 510.00 1020.00
4 Marker / Fabricator / Erector Day 10.00 550.00 5500.00
5 Gas cutter Day 4.00 445.00 1780.00
6 Welder ( General ) Day 4.00 445.00 1780.00
7 Mazdoors Day 6.00 350.00 2100.00
8 Helper fabrication / erection Day 6.00 400.00 2400.00
Total cost of Labour Rs: 23331.60
labour component/unit qty 23331.60
Add contractor's profit and overhead charges 13.615% 3176.60
labour component/unit qty (including contractor's profit) 26508.20
ABSTRACT:
A. Cost of Materials Rs: 59039.95
B. Hire charges of Machinery Rs: 9928.40
C. Cost of Labour Rs: 23331.60
Total Rs: 92299.95
D. Add for excise duty 0.00% Rs: 0.00
(on 75 percent cost excluding cost of materials) Total Rs: 92299.95
E. Add for transportation upto work site @ 3% Rs: 2769.00
Total Rs: 95068.95
F. Add for contractor's profit and overheads on
(A+B+C+D+E) 13.615% Rs: 12943.64
Add 2 leads
Add 1 km lead charges for fabricated parts Rs. 19.00 per tonne 33.022
Unloading charges of fabricated parts Rs 74.80 per tonne 130.002
Total cost for 0.869 tonne Rs: 108175.61
Rate per tonne Rs: 124482.90
IRR-GAW-2-
13
New Item
2015-16-3 OT SLUICE SHUTTERS EM parts for Below 5 Tons capacity (small gates)
As per Guidelines of Chief Engineer, Central Designs Organization, Hyderabad Specification drawing for
Krishna Delta System
Fabrication, supply, erection, testing and commissioning of Embedded parts consisting of sil beam, slide tracks,
seal seats, Guide plates etc. with all accessories including cost of all materials, machinery, labour, etc.
complete as per specifications and approved drawings.
296
Gates and Allied Works - Item Unit Rates 2016-17
(without painting on mechanical cleaning surfaces which are added extra as per schedule of rates
under items in this chapter and add as applicable separately)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Welding transformer Hour 30.00 16.00 480.00
Fuel / Energy charges Hour 30.00 67.20 2016.00
2 Pug cutting machine Hour 20.00 6.40 128.00
Fuel / Energy charges Hour 20.00 2.80 56.00
3 Drilling machine Hour 4.00 22.50 90.00
Fuel / Energy charges Hour 4.00 28.00 112.00
4 Grinding machine Hour 20.00 22.50 450.00
Fuel / Energy charges Hour 20.00 28.00 560.00
5 Sundries LS 3.00 30.00 90.00
Total hire charges of Machinery Rs: 3982.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Drilling machine Hour 4.00 198.90 795.60
2 Crew for Grinding machine Hour 20.00 198.90 3978.00
3 Foreman Day 8.00 510.00 4080.00
4 Marker / Fabricator / Erector Day 6.00 550.00 3300.00
5 Gas cutter Day 2.00 445.00 890.00
6 Welder ( General ) Day 4.00 445.00 1780.00
7 Mazdoors Day 4.00 350.00 1400.00
8 Helper fabrication / erection Day 8.00 400.00 3200.00
Total cost of Labour Rs: 19423.60
labour component/unit qty 19423.60
Add contractor's profit and overhead charges 13.615% 2644.50
labour component/unit qty (including contractor's profit) 22068.10
ABSTRACT:
A. Cost of Materials Rs: 62540.91
B. Hire charges of Machinery Rs: 3982.00
C. Cost of Labour Rs: 19423.60
Total Rs: 85946.51
D. Add for excise duty 0.00% Rs: 0.00
(on 75 percent cost excluding cost of materials) Total Rs: 85946.51
E. Add for transportation upto work site @ 3% Rs: 2578.40
Total Rs: 88524.90
F. Add for contractor's profit and overheads on
(A+B+C+D+E) 13.615% Rs: 12052.67
Add 2 leads
Add 1 km lead charges for fabricated parts Rs. 19.00 per tonne 50.692
Unloading charges of fabricated parts Rs 74.80 per tonne 199.566
Total cost for 1.334 tonne Rs: 100827.83
Rate per tonne Rs: 75583.10
297
Gates and Allied Works - Item Unit Rates 2016-17
IRR-GAW-2-
14
New Item
2015-16 -4 OT SLUICE SHUTTERS for Below 5 Tons capacity (small gates)
As per Guidelines of Chief Engineer, Central Designs Organization, Hyderabad Specification drawing for
Krishna Delta System
Fabrication, supply, erection, testing and commissioning of Sluice Shutters consisting of skin plate, horizontal
and vertical angles, stiffeners, rubber seals, clamps with all accessories for sluice shutters including cost
of all materials, machinery, labour, seal fixing etc., complete as per specifications and approved drawings
(without painting on mechanical cleaning surfaces which are added extra as per schedule of rates
under items in this chapter and add as applicable separately)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Welding transformer Hour 14.00 16.00 224.00
Fuel / Energy charges Hour 14.00 67.20 940.80
2 Pug cutting machine Hour 4.00 6.40 25.60
Fuel / Energy charges Hour 4.00 2.80 11.20
3 Drilling machine Hour 2.00 22.50 45.00
Fuel / Energy charges Hour 2.00 28.00 56.00
4 Grinding machine Hour 4.00 22.50 90.00
Fuel / Energy charges Hour 4.00 28.00 112.00
5 Sundries LS 3.00 30.00 90.00
Total hire charges of Machinery Rs: 1594.60
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Drilling machine Hour 2.00 198.90 397.80
2 Crew for Grinding machine Hour 4.00 198.90 795.60
3 Foreman Day 2.00 510.00 1020.00
4 Marker / Fabricator / Erector Day 3.00 550.00 1650.00
5 Gas cutter Day 1.00 445.00 445.00
6 Welder ( General ) Day 4.00 445.00 1780.00
7 Mazdoors Day 4.00 350.00 1400.00
8 Helper fabrication / erection Day 6.00 400.00 2400.00
Total cost of Labour Rs: 9888.40
labour component/unit qty 9888.40
Add contractor's profit and overhead charges 13.615% 1346.30
labour component/unit qty (including contractor's profit) 11234.70
ABSTRACT:
A. Cost of Materials Rs: 15904.70
B. Hire charges of Machinery Rs: 1594.60
C. Cost of Labour Rs: 9888.40
Total Rs: 27387.70
D. Add for excise duty 0.00% Rs: 0.00
(on 75 percent cost excluding cost of materials) Total Rs: 27387.70
E. Add for transportation upto work site @ 3% Rs: 821.63
298
Gates and Allied Works - Item Unit Rates 2016-17
Total Rs: 28209.33
F. Add for contractor's profit and overheads on
(A+B+C+D+E) 13.615% Rs: 3840.70
Add 2 leads
Add 1 km lead charges for fabricated parts Rs. 19.00 per tonne 6.118
Unloading charges of fabricated parts Rs 74.80 per tonne 24.086
Total cost for 0.161 tonne Rs: 32080.24
Rate per tonne Rs: 199256.10
IRR-GAW-3-1 Cleaning gates / hoists / embedded parts/lifting beams etc, to expose fresh metal surface
for painting by sand blasting method as per specifications including cost of all materials, l
abour, machinery, scaffolding, etc., complete with initial lead for sand upto 1 km and all lifts.
ABSTRACT:
A. Cost of Materials Rs: 5805.80
B. Hire charges of Machinery Rs: 8523.20
C. Cost of Labour Rs: 8694.80
Total Rs: 23023.80
D. Add for excise duty 0.00% Rs: 0.00
(on 75 percent cost excluding cost of materials) Total Rs: 23023.80
E. Add for transportation upto work site @ 3% Rs: 690.71
Total Rs: 23714.51
F. Add for contractor's profit and overheads on
(A+B+C+D+E) 13.615% Rs: 3228.73
Total cost for 100.00 sqm Rs: 26943.25
Rate per sqm Rs: 269.40
IRR-GAW-3-2 painting of embedded metal parts and all types of gates, stoplogs,etc, on sand blasted
surfaces with one coat of inorganic zinc silicate (airless spray preferred)70+/- 5
and two super coats with a total thickness of 300 microns
(each 150+/- 5) of solventless coaltar epoxy paint each coat 150 microns ( total 300 microns)
cost of all materials, labour, scaffolding etc., complete with all leads and
all lifts
(Upstream surface of gates portion may be painted with solventless coaltar epoxy brown paint
299
Gates and Allied Works - Item Unit Rates 2016-17
instead of solventless coaltar black. The rate for coaltar epoxy brown shall be adopted in data
for Upstream side painting)
ABSTRACT:
A. Cost of Materials Rs: 18450.00
B. Hire charges of Machinery Rs: 6460.20
C. Cost of Labour Rs: 18465.40
Total Rs: 43375.60
D. Add for excise duty 0 Rs: 0.00
(on 75 percent cost excluding cost of materials) Total Rs: 43375.60
E. Add for transportation upto work site @ 0.03 Rs: 1301.27
Total Rs: 44676.87
F. Add for contractor's profit and overheads on
(A+B+C+D+E) 13.615% Rs: 6082.76 6082.76
Total cost for 100.00 sqm Rs: 50759.62
Rate per sqm Rs: 507.60
IRR-GAW-3-3
painting of Lifting beams,cat walks and other similar structures-painting hoist machinery,
on sand blasted surfaces with two coats of zinc phosphate primer (airless spray preferred)
40microns/coat and twocoats of alkyd based micaccous iron oxide paint , 65 microns/coat
cost of all materials, labour, scaffolding etc., complete with all leads and
all lifts
300
Gates and Allied Works - Item Unit Rates 2016-17
ABSTRACT:
A. Cost of Materials Rs: 10514.00
B. Hire charges of Machinery Rs: 6460.20
C. Cost of Labour Rs: 14165.40
Total Rs: 31139.60
D. Add for excise duty 0 Rs: 0.00
(on 75 percent cost excluding cost of materials) Total Rs: 31139.60
E. Add for transportation upto work site @ 0.03 Rs: 934.19
Total Rs: 32073.79
F. Add for contractor's profit and overheads on
(A+B+C+D+E) 13.615% Rs: 4366.85 4366.85
Total cost for 100.00 sqm Rs: 36440.63
Rate per sqm Rs: 364.40
ABSTRACT:
A. Cost of Materials Rs: 14129.00
B. Hire charges of Machinery Rs: 6460.20
C. Cost of Labour Rs: 18465.40
Total Rs: 39054.60
D. Add for excise duty 0 Rs: 0.00
(on 75 percent cost excluding cost of materials) Total Rs: 39054.60
E. Add for transportation upto work site @ 0.03 Rs: 1171.64
Total Rs: 40226.24
F. Add for contractor's profit and overheads on
(A+B+C+D+E) 13.615% Rs: 5476.80 5476.80
Total cost for 100.00 sqm Rs: 45703.04
Rate per sqm Rs: 457.00
ABSTRACT:
A. Cost of Materials Rs: 10372.00
B. Hire charges of Machinery Rs: 6460.20
C. Cost of Labour Rs: 18465.40
Total Rs: 35297.60
D. Add for excise duty 0 Rs: 0.00
(on 75 percent cost excluding cost of materials) Total Rs: 35297.60
E. Add for transportation upto work site @ 0.03 Rs: 1058.93
Total Rs: 36356.53
F. Add for contractor's profit and overheads on
(A+B+C+D+E) 13.615% Rs: 4949.94 4949.94
Total cost for 100.00 sqm Rs: 41306.47
Rate per sqm Rs: 413.10
303
Gates and Allied Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Hire Charges of Airless Spray Gun Hr 6.00 121.40 728.40
Hire Charges of Air Compressor-7
2 Cmm (diesel) Hr 6.00 241.30 1447.80
3 Fuel Charges of Air Compressor Hr 6.00 714.00 4284.00
Total cost of Machinery 6460.20
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew Charges of Air Compressor Day 6.00 210.90 1265.40
2 Painter Class-I Day 20.00 510.00 10200.00
3 Helper Day 20.00 350.00 7000.00
Total cost of Labour Rs: 18465.40
labour component/unit qty 184.70
Add contractor's profit and overhead charges 13.615% 25.10
labour component/unit qty (including contractor's profit) 209.80
ABSTRACT:
A. Cost of Materials Rs: 24912.00
B. Hire charges of Machinery Rs: 6460.20
C. Cost of Labour Rs: 18465.40
Total Rs: 49837.60
D. Add for excise duty 0.00% Rs: 0.00
(on 75 percent cost excluding cost of materials) Total Rs: 49837.60
E. Add for transportation upto work site @ 3% Rs: 1495.13
Total Rs: 51332.73
F. Add for contractor's profit and overheads on
(A+B+C+D+E) 13.615% Rs: 6988.95
Total cost for 100.00 sqm Rs: 58321.68
Rate per sq.meter Rs: 583.20
Surface cleaning of metal surfaces by chemical cleaners and then by hand and power tool cleaners
and removing dust. After cleaning,applying primary coat with two coats of Zinc chromite red oxide primer ,
followed by finishing coats 3 coats with synthetic enamel paint with material, labour,and all accessories
with all leads and lifts where surface cleaning by sand blasting is not feasible and based on specific
recommendations of designers, it is to adopt surface preperation done manually by hand and power tool
after cleaning by chemical treatment to remove grease, rust, scaling etc., and to form phasphate coating
to prevent further rusting, before applying primer painting.
B. MACHINERY:
304
Gates and Allied Works - Item Unit Rates 2016-17
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Hire Charges of Airless Spray Gun Hr 6.00 121.40 728.40
Hire Charges of Air Compressor-7
2 Cmm (diesel) Hr 6.00 241.30 1447.80
3 Fuel Charges of Air Compressor Hr 6.00 714.00 4284.00
Total cost of Machinery 6460.20
C. LABOUR
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew Charges of Air Compressor Day 6.00 210.90 1265.40
2 Painter Class-I Day 20.00 510.00 10200.00
3 Helper Day 20.00 350.00 7000.00
Total cost of Labour 18465.40
labour component/unit qty 184.70
Add contractor's profit and overhead charges 13.615% 25.10
labour component/unit qty (including contractor's profit) 209.80
ABSTRACT:
A. Cost of Materials Rs. 11772.00
B. Hire charges of Machinery Rs. 6460.20
C. Cost of Labour Rs. 18465.40
Total Rs: 36697.60
D. Add for excise duty 0.00% Rs: 0.00
(on 75 percent cost excluding cost of materials) Total Rs: 36697.60
E. Add for transportation upto work site @ 3% Rs: 1100.93
Total Rs: 37798.53
F. Add for contractor's profit and overheads on
(A+B+C+D+E) 13.615% Rs: 5146.27
Total cost for 100.00 sqm Rs: 42944.80
Rate per sq.meter 429.40
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Hire Charges of Airless Spray Gun Hr 6.00 121.40 728.40
Hire Charges of Air Compressor-7
2 Cmm (diesel) Hr 6.00 241.30 1447.80
3 Fuel Charges of Air Compressor Hr 6.00 714.00 4284.00
Total cost of Machinery Rs: 6460.20
305
Gates and Allied Works - Item Unit Rates 2016-17
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew Charges of Air Compressor Day 6.00 210.90 1265.40
2 Painter Class-I Day 13.00 510.00 6630.00
3 Helper Day 13.00 350.00 4550.00
Total cost of Labour Rs: 12445.40
labour component/unit qty 124.50
Add contractor's profit and overhead charges 13.615% 17.00
labour component/unit qty (including contractor's profit) 141.50
ABSTRACT:
A. Cost of Materials Rs: 22602.00
B. Hire charges of Machinery Rs: 6460.20
C. Cost of Labour Rs: 12445.40
Total Rs: 41507.60
D. Add for excise duty 0.00% Rs: 0.00
(on 75 percent cost excluding cost of materials) Total Rs: 41507.60
E. Add for transportation upto work site @ 3% Rs: 1245.23
Total Rs: 42752.83
F. Add for contractor's profit and overheads on
(A+B+C+D+E) 13.615% Rs: 5820.80
Total cost for 100.00 sqm Rs: 48573.63
Rate per sq.meter Rs: 485.70
306
Preliminary and Maintenance Works - Item Unit Rates 2016-17
CHAPTER-VI
3. The Leads for Steel shall be from the nearest market place to the Project area
4. For earth/rockfill embankments wherever initial lead of 1km is considered in the basic rate, the additional lead
charges are to be added as follows:
Additional lead charges for Earth, Murrum etc., shall be worked out for total lead involved and 1 km lead charges included
in basic rate shall be deducted from total lead charges. No loading and unloading charges shall be allowed for any item.
(same as above)
Example:
Total lead for earth from approved borrow area : 15 Km
Initial lead included in the basic rate in the SR : 1 Km
Additional lead charges : Lead charges
Rs. for 5 km 84.00
Lead charges for next 10Rs.km 126
Total lead charges for 15Rs.
km /cum 210.00
Less 1 km initial lead charges
Rs. /cum 31.50 (-)
Net additional lead charges
Rs./ cum 178.50
5. The initial lead up to 50 m as mentioned in some standard data items is meant for manual lead within the working area.
For conveyance of materials, the lead required from quarry/Borrow area/ Dump Area to worksite shall be added to the
data without deducting the 50 m initial lead charges
IRR-PMW-1-1 Clearing thin jungle growth ( more than 50 percent open space ) including bushes
upto 30 cm / parthenium and other weeds including burning or disposing off the same
as directed etc., complete.
307
Preliminary and Maintenance Works - Item Unit Rates 2016-17
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total cost of Materials Rs: 0.00
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 0.50 450.00 225.00
2 mazdoor Day 3.00 350.00 1050.00
Total cost of Labour Rs: 1275.00
labour component/unit qty 1.30
Add contractor's profit and overhead charges 13.615% 0.20
labour component/unit qty (including contractor's profit) 1.50
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 1275.00
Total Rs: 1275.00
D. Add for contractor's profit and overheads on
(A+B+C) 13.615% Rs: 173.59125
Total cost for 1000.00 sqm Rs: 1448.59
Rate per sqm (A+B+C+D)/1000.0 Rs. 1.40
IRR-PMW-1-2 Clearing thick jungle growth ( less than 50 percent open space ) including bushes
upto 30 cm / parthenium and other weeds including burning or disposing off the same as
directed etc., complete.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 0.50 450.00 225.00
2 mazdoor Day 5.00 350.00 1750.00
Total cost of Labour Rs: 1975.00
labour component/unit qty 2.00
Add contractor's profit and overhead charges 13.615% 0.30
labour component/unit qty (including contractor's profit) 2.30
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 1975.00
Total Rs: 1975.00
308
Preliminary and Maintenance Works - Item Unit Rates 2016-17
D. Add for contractor's profit and overheads on
(A+B+C) 13.615% Rs: 268.89625
Total cost for 1000.00 sqm Rs: 2243.90
Rate per sqm (A+B+C+D)/1000.0 Rs. 2.20
IRR-PMW-1-3 Removing stumps, tree roots, roots of bamboo clusters etc., upto 1.50 m girth
including excavation, stacking the materials neatly and levelling the surface etc., complete with
initial lead upto 50 m and all lifts.
DATA:
A. MATERIALS:
Sl No particulars Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total cost of Materials Rs: 0.00
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 0.25 450.00 112.50
2 mazdoor Day 2.00 350.00 700.00
Total cost of Labour Rs: 812.50
labour component/unit qty 45.10
Add contractor's profit and overhead charges 13.615% 6.10
labour component/unit qty (including contractor's profit) 51.20
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 812.50
Total Rs: 812.50
D. Add for contractor's profit and overheads on
(A+B+C) 13.615% Rs: 110.621875
Total cost for 18.00 Nos. Rs: 923.12
Rate per each (A+B+C+D)/18.0 Rs. 51.30
IRR-PMW-1-4 Removing stumps, tree roots, roots of bamboo cluster etc., with girth above 1.50 m
and upto 3.0 m including excavation, stacking the materials neatly and levelling the area etc.,
complete with initial lead upto 50 m and all lifts.
DATA:
A. MATERIALS:
Sl No particulars Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total cost of Materials Rs: 0.00
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
309
Preliminary and Maintenance Works - Item Unit Rates 2016-17
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 0.25 450.00 112.50
2 mazdoor Day 2.00 350.00 700.00
Total cost of Labour Rs: 812.50
labour component/unit qty 101.56
Add contractor's profit and overhead charges 13.615% 13.83
labour component/unit qty (including contractor's profit) 115.40
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 812.50
Total Rs: 812.50
D. Add for contractor's profit and overheads on
(A+B+C) 13.615% Rs: 110.621875
Total cost for 8.00 Nos. Rs: 923.10
Rate per each (A+B+C+D)/8.0 Rs. 115.40
IRR-PMW-1-5 Removing stumps, tree roots, roots of bamboo cluster etc., with girth
above 3.0 m and upto 5.0 m including excavation, stacking the materials neatly and levelling
the area etc., complete with initial lead upto 50 m and all lifts.
A. MATERIALS:
Sl No particulars Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total cost of Materials Rs: 0.00
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 0.50 450.00 225.00
2 mazdoor Day 4.00 350.00 1400.00
Total cost of Labour Rs: 1625.00
labour component/unit qty 325.00
Add contractor's profit and overhead charges 13.615% 44.20
labour component/unit qty (including contractor's profit) 369.20
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 1625.00
Total Rs: 1625.00
D. Add for contractor's profit and overheads on
(A+B+C) 13.615% Rs: 221.24375
Total cost for 5.00 Nos. Rs: 1846.24
Rate per each (A+B+C+D)/5.0 Rs. 369.20
IRR-PMW-1-6 Additional rate for every 0.5 m increase in girth of tree stump / stumps of bamboo cluster
beyond 5 m.
A. MATERIALS:
310
Preliminary and Maintenance Works - Item Unit Rates 2016-17
Sl No particulars Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total cost of Materials Rs: 0.00
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 0.22 450.00 99.00
2 mazdoor Day 0.88 350.00 306.25
Total cost of Labour Rs: 405.25
labour component/unit qty 57.90
Add contractor's profit and overhead charges 13.615% 7.90
labour component/unit qty (including contractor's profit) 65.80
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 405.25
Total Rs: 405.25
D. Add for contractor's profit and overheads on
(A+B+C) 13.615% Rs: 55.1747875
Total cost for 7.00 Nos. Rs: 460.42
Rate per each (A+B+C+D)/7.0 Rs. 65.80
IRR-PMW-1-7 Cutting and stacking bamboos excluding removing stumps and roots etc., complete with
initial lead upto 50 m and all lifts.
A. MATERIALS:
Sl No particulars Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total cost of Materials Rs: 0.00
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 0.50 450.00 225.00
2 mazdoor Day 5.00 350.00 1750.00
Total cost of Labour Rs: 1975.00
labour component/unit qty 13.17
Add contractor's profit and overhead charges 13.615% 1.79
labour component/unit qty (including contractor's profit) 15.00
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 1975.00
311
Preliminary and Maintenance Works - Item Unit Rates 2016-17
Total Rs: 1975.00
D. Add for contractor's profit and overheads on
(A+B+C) 13.615% Rs: 268.89625
Total cost for 150.00 Nos. Rs: 2243.90
Rate per each (A+B+C+D)/150.0 Rs. 15.00
IRR-PMW-1-8 Cutting and removing jauliflora bushes upto 1.5 m girth excluding removal of stumps and
including burning or disposing off the materials as directed with initial lead upto 50 m and all
lifts.
A. MATERIALS:
Sl No particulars Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total cost of Materials Rs: 0.00
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 0.50 450.00 225.00
2 mazdoor Day 3.00 350.00 1050.00
Total cost of Labour Rs: 1275.00
labour component/unit qty 12.80
Add contractor's profit and overhead charges 13.615% 1.70
labour component/unit qty (including contractor's profit) 14.50
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 1275.00
Total Rs: 1275.00
D. Add for contractor's profit and overheads on
(A+B+C) 13.615% Rs: 173.59125
Total cost for 100.00 Nos Rs: 1448.59
Rate per each (A+B+C+D)/100.0 Rs. 14.50
IRR-PMW-1-9 Cutting and removing jauliflora bushes above 1.5 m upto 3.0 m girth excluding
removal of stumps and including burning or disposing off the materials as directed
with initial lead upto 50 m and all lifts.
A. MATERIALS:
Sl No particulars Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total cost of Materials Rs: 0.00
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
312
Preliminary and Maintenance Works - Item Unit Rates 2016-17
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 0.50 450.00 225.00
2 mazdoor Day 3.00 350.00 1050.00
Total cost of Labour Rs: 1275.00
labour component/unit qty 25.50
Add contractor's profit and overhead charges 13.615% 3.50
labour component/unit qty (including contractor's profit) 29.00
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 1275.00
Total Rs: 1275.00
D. Add for contractor's profit and overheads on
(A+B+C) 13.615% Rs: 173.59125
Total cost for 50.00 Nos Rs: 1448.59
Rate per each (A+B+C+D)/50.0 Rs. 29.00
IRR-PMW-1-10 Cutting trees above 0.3 m and upto 0.6 m girth excluding removal of stumps and including
stacking the materials neatly as directed with initial lead upto 50 m and all lifts.
A. MATERIALS:
Sl No particulars Unit Quantity Rate Amount
in Rs. in Rs.
1 Use rate of ropes etc LS 0.25 150.00 37.50
0.00 0.00 0.00
Total cost of Materials Rs: 37.50
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 0.25 450.00 112.50
2 mazdoor Day 3.00 350.00 1050.00
Total cost of Labour Rs: 1162.50
labour component/unit qty 83.00
Add contractor's profit and overhead charges 13.615% 11.30
labour component/unit qty (including contractor's profit) 94.30
ABSTRACT:
A. Cost of Materials Rs: 37.50
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 1162.50
Total Rs: 1200.00
D. Add for contractor's profit and overheads on
(A+B+C) 13.615% Rs: 163.38
Total cost for 14.00 Nos. Rs: 1363.38
Rate per each (A+B+C+D)/14.0 Rs. 97.40
IRR-PMW-1-11 Cutting trees above 0.6 m and upto 1.2 m girth excluding removal of stumps and including
stacking the materials neatly as directed with initial lead upto 50 m and all lifts.
A. MATERIALS:
Sl No particulars Unit Quantity Rate Amount
in Rs. in Rs.
313
Preliminary and Maintenance Works - Item Unit Rates 2016-17
1 Use rate of ropes etc LS 0.25 150.00 37.50
0.00 0.00 0.00
Total cost of Materials Rs: 37.50
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 0.25 450.00 112.50
2 mazdoor Day 3.00 350.00 1050.00
Total cost of Labour Rs: 1162.50
labour component/unit qty 290.60
Add contractor's profit and overhead charges 13.615% 39.60
labour component/unit qty (including contractor's profit) 330.20
ABSTRACT:
A. Cost of Materials Rs: 37.50
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 1162.50
Total Rs: 1200.00
D. Add for contractor's profit and overheads on
(A+B+C) 13.615% Rs: 163.38
Total cost for 4.00 Nos. Rs: 1363.38
Rate per each (A+B+C+D)/4.0 Rs. 340.80
IRR-PMW-1-12 Cutting trees above 1.2 m and upto 1.8 m girth excluding removal of stumps and including
stacking the materials neatly as directed with initial lead upto 50 m and all lifts.
A. MATERIALS:
Sl No particulars Unit Quantity Rate Amount
in Rs. in Rs.
1 Use rate of ropes etc LS 0.25 150.00 37.50
0.00 0.00 0.00
Total cost of Materials Rs: 37.50
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 0.25 450.00 112.50
2 mazdoor Day 3.00 350.00 1050.00
Total cost of Labour Rs: 1162.50
labour component/unit qty 581.30
Add contractor's profit and overhead charges 13.615% 79.10
labour component/unit qty (including contractor's profit) 660.40
ABSTRACT:
A. Cost of Materials Rs: 37.50
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 1162.50
Total Rs: 1200.00
D. Add for contractor's profit and overheads on
(A+B+C) 13.615% Rs: 163.38
Total cost for 2.00 Nos. Rs: 1363.38
314
Preliminary and Maintenance Works - Item Unit Rates 2016-17
Rate per each (A+B+C+D)/2.0 Rs. 681.70
IRR-PMW-1-13 Cutting trees above 1.8 m and upto 2.4 m girth excluding removal of stumps and including
stacking the materials neatly as directed with initial lead upto 50 m and all lifts.
A. MATERIALS:
Sl No particulars Unit Quantity Rate Amount
in Rs. in Rs.
1 Use rate of ropes etc LS 0.25 150.00 37.50
0.00 0.00 0.00
Total cost of Materials Rs: 37.50
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 0.25 450.00 112.50
2 mazdoor Day 3.00 350.00 1050.00
Total cost of Labour Rs: 1162.50
labour component/unit qty 1162.50
Add contractor's profit and overhead charges 13.615% 158.30
labour component/unit qty (including contractor's profit) 1320.80
ABSTRACT:
A. Cost of Materials Rs: 37.50
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 1162.50
Total Rs: 1200.00
D. Add for contractor's profit and overheads on
(A+B+C) 13.615% Rs: 163.38
Total cost for 1.00 No. Rs: 1363.38
Rate per each (A+B+C+D)/1.0 Rs. 1363.40
IRR-PMW-1-14 Cutting trees above 2.4 m and upto 3.0 m girth excluding removal of stumps and including
stacking the materials neatly as directed with initial lead upto 50 m and all lifts.
A. MATERIALS:
Sl No particulars Unit Quantity Rate Amount
in Rs. in Rs.
1 Use rate of ropes etc LS 0.50 150.00 75.00
0.00 0.00 0.00
Total cost of Materials Rs: 75.00
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 0.25 450.00 112.50
315
Preliminary and Maintenance Works - Item Unit Rates 2016-17
2 mazdoor Day 5.00 350.00 1750.00
Total cost of Labour Rs: 1862.50
labour component/unit qty 1862.50
Add contractor's profit and overhead charges 13.615% 253.60
labour component/unit qty (including contractor's profit) 2116.10
ABSTRACT:
A. Cost of Materials Rs: 75.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 1862.50
Total Rs: 1937.50
D. Add for contractor's profit and overheads on
(A+B+C) 13.615% Rs: 263.790625
Total cost for 1.00 Nos. Rs: 2201.29
Rate per each (A+B+C+D)/1.0 Rs. 2201.30
IRR-PMW-1-15 Additional rate for cutting tree for every 0.5 m increase in girth of tree beyond 3 m.
A. MATERIALS:
Sl No particulars Unit Quantity Rate Amount
in Rs. in Rs.
1 Use rate of ropes etc LS 0.15 150.00 22.50
0.00 0.00 0.00
Total cost of Materials Rs: 22.50
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 0.10 450.00 45.00
2 mazdoor Day 1.75 350.00 612.50
Total cost of Labour Rs: 657.50
labour component/unit qty 657.50
Add contractor's profit and overhead charges 13.615% 89.50
labour component/unit qty (including contractor's profit) 747.00
ABSTRACT:
A. Cost of Materials Rs: 22.50
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 657.50
Total Rs: 680.00
D. Add for contractor's profit and overheads on
(A+B+C) 13.615% Rs: 92.582
Total cost for 1.00 No Rs: 772.58
Rate per each (A+B+C+D)/1.0 Rs. 772.60
IRR-PMW-1-16 Cutting and burning or disposing off Apu / Jondu from marshy areas as directed with
initial lead upto 50 m and all lifts.
A. MATERIALS:
Sl No particulars Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total cost of Materials Rs: 0.00
316
Preliminary and Maintenance Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 1.00 450.00 450.00
2 mazdoor Day 12.00 350.00 4200.00
Total cost of Labour Rs: 4650.00
labour component/unit qty 4.70
Add contractor's profit and overhead charges 13.615% 0.60
labour component/unit qty (including contractor's profit) 5.30
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 4650.00
Total Rs: 4650.00
D. Add for contractor's profit and overheads on
(A+B+C) 13.615% Rs: 633.0975
Total cost for 1000.00 sqm Rs: 5283.10
Rate per sqm (A+B+C+D)/1000.0 Rs. 5.30
IRR-PMW-2-1 Earthwork excavation for trial pits / borrow pits and other investigation works in all kinds of
soil including boulders upto 30 cm dia and disposing off excavated soil as directed with lead
upto 10 m and lift upto 3 m.
A. MATERIALS:
Sl No particulars Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total cost of Materials Rs: 0.00
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 0.50 450.00 225.00
2 mazdoor Day 6.00 350.00 2100.00
Total cost of Labour Rs: 2325.00
labour component/unit qty 232.50
Add contractor's profit and overhead charges 13.615% 31.65
labour component/unit qty (including contractor's profit) 264.20
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 2325.00
Total Rs: 2325.00
D. Add for contractor's profit and overheads on
(A+B+C) 13.615% Rs: 316.54875
Total cost for 10.00 cum Rs: 2641.55
317
Preliminary and Maintenance Works - Item Unit Rates 2016-17
Rate per cum (A+B+C+D)/100.0 Rs. 264.20
IRR-PMW-2-2 Earthwork excavation for trial pits / borrow pits and other investigation works in soft
rock including disposing off the excavated rock as directed with lead upto 10 m and lift
upto 3 m.
A. MATERIALS:
Sl No particulars Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total cost of Materials Rs: 0.00
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 0.50 450.00 225.00
2 Crowbarman Day 1.00 400.00 400.00
3 mazdoor Day 7.50 350.00 2625.00
Total cost of Labour Rs: 3250.00
labour component/unit qty 325.00
Add contractor's profit and overhead charges 13.615% 44.20
labour component/unit qty (including contractor's profit) 369.20
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 3250.00
Total Rs: 3250.00
D. Add for contractor's profit and overheads on
(A+B+C) 13.615% Rs: 442.4875
Total cost for 10.00 cum Rs: 3692.49
Rate per cum (A+B+C+D)/10.0 Rs. 369.20
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Electric resistivity meter Hour 8.00 99.00 792.00
Battery / charging cost etc @ 20% 158.40
Total hire charges of Machinery Rs: 950.40
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Geophysist / Geologist Day 2.00 860.00 1720.00
318
Preliminary and Maintenance Works - Item Unit Rates 2016-17
2 Graduate Engineer Day 1.00 860.00 860.00
3 Lab Assistant Day 1.00 520.00 520.00
4 mazdoor Day 4.00 350.00 1400.00
Total cost of Labour Rs: 4500.00
labour component/unit qty 225.00
Add contractor's profit and overhead charges 13.615% 30.60
labour component/unit qty (including contractor's profit) 255.60
ABSTRACT:
A. Cost of Materials Rs: 150.00
B. Hire charges of Machinery Rs: 950.40
C. Cost of Labour Rs: 4500.00
Total Rs: 5600.40
D. Add for contractor's profit and overheads on
(A+B+C) 13.615% Rs: 762.49446
Total cost for 20.00 Stages Rs: 6362.89
Rate per stage (A+B+C+D)/20.0 Rs. 318.10
IRR-PMW-2-4 Drilling 80 mm dia hole through over-burden using casing shoe bit vertical or inclined
upto 10 degrees to vertical as directed including cost of all materials, machinery, labour, water
charges, reaming, collection of wash samples at suitable intervals, logging and lebelling,
supplying honne wood core box, fixing casing pipes ( excluding cost of casing pipes ) etc.,
complete for depth upto 30 m from surface.
Note: 1. For drilling through over-burden beyond 30 m from surface increase the basic rate per
Rm by 10 percent.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Core drilling machine Hour 1.00 319.00 319.00
Fuel / Energy charges Hour 1.00 238.00 238.00
2 5 hp pump ( diesel ) 2 Nos. Hour 2.00 10.20 20.40
Fuel / Energy charges Hour 2.00 79.30 158.60
3 Sundries ( samplers etc ) LS 2.00 30.00 60.00
Total hire charges of Machinery Rs: 796.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Core drilling machine Hour 1.00 283.90 283.90
2 Crew for Pump Hour 2.00 111.10 222.20
3 mazdoor Day 2.00 350.00 700.00
Total cost of Labour Rs: 1206.10
labour component/unit qty 402.00
Add contractor's profit and overhead charges 13.615% 54.70
labour component/unit qty (including contractor's profit) 456.70
ABSTRACT:
A. Cost of Materials Rs: 1183.58
B. Hire charges of Machinery Rs: 796.00
C. Cost of Labour Rs: 1206.10
Total Rs: 3185.68
D. Add for contractor's profit and overheads on
(A+B+C) 13.615% Rs: 433.7303774
Total cost for 3.00 Rm Rs: 3619.41
Rate per Rm (A+B+C+D)/3.0 Rs. 1206.50
IRR-PMW-2-5 Drilling 76 mm dia ( NX ) core hole in hard rock using diamond core bit vertical / inclined
319
Preliminary and Maintenance Works - Item Unit Rates 2016-17
upto 10 degree to vertical as directed including cost of all materials, machinery, labour, water
charges, collection of core samples, logging and lebelling, supplying honne wood core box
and redrilling in case of collapse of sides etc., complete for depth upto 30 m from surface.
A. MATERIALS:
Sl No particulars Unit Quantity Rate Amount
in Rs. in Rs.
1 Use rate of diamond core bit Rm 3.00 848.00 2544.00
2 Use rate of reamer shell Rm 3.00 85.83 257.50
3 Use rate of double tube core barrel Rm 3.00 226.13 678.40
4 Use rate of extension rod set 16.5 m Rm 3.00 23.32 69.96
5 Use rate of honne core box Rm 3.00 556.88 1670.63
Total cost of Materials Rs: 5220.49
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Core drilling machine Hour 8.00 319.00 2552.00
Fuel / Energy charges Hour 8.00 238.00 1904.00
2 5 hp pump ( diesel ) 2 Nos. Hour 16.00 10.20 163.20
Fuel / Energy charges Hour 16.00 79.30 1268.80
3 Sundries LS 5.00 30.00 150.00
Total hire charges of Machinery Rs: 6038.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Core drilling machine Hour 8.00 283.90 2271.20
2 Crew for Pump Hour 16.00 111.10 1777.60
3 mazdoor Day 2.00 350.00 700.00
Total cost of Labour Rs: 4748.80
labour component/unit qty 1582.90
Add contractor's profit and overhead charges 13.615% 215.50
labour component/unit qty (including contractor's profit) 1798.40
ABSTRACT:
A. Cost of Materials Rs: 5220.49
B. Hire charges of Machinery Rs: 6038.00
C. Cost of Labour Rs: 4748.80
Total Rs: 16007.29
D. Add for contractor's profit and overheads on
(A+B+C) 13.615% Rs: 2179.391853
Total cost for 3.00 Rm Rs: 18186.68
Rate per Rm (A+B+C+D)/3.0 Rs. 6062.20
NOTE: 1. For drilling in hard rock beyond 30 m upto 60 m from surface increase the basic
rate per Rm by 25 percent.
2. For drilling in hard rock beyond 60 m upto 90 m from surface increase the basic
rate per Rm by 40 percent.
IRR-PMW-2-5-A
New Item 2015-16-
5 Drilling 76 mm dia ( NX ) core hole in all types of rocks (other than Hard Rock) including
Masonry/CC (where drilling is not possible by casing shoe) using diamond core bit vertical /
inclined upto 10 degree to vertical as directed including cost of all materials, machinery, labour,
water charges, and redrilling in case of collapse of sides etc., complete for depth upto 30 m from
surface for Primary and Secondary Holes Drilling 76 mm dia ( NX ) core hole in all types of rocks (other than Har
DATA: For drilling upto 30 m from surface the rate of drilling is assumed at 3 m per day for analysis.
For rate analysis combination of diamond bit and reamer shell is assumed.
500 m long 25 mm dia GI pipe line and 50 m long 25 mm dia water hose are assumed.
For 30 m drilling average 16.5 m extension rods with coupling sleeves required.
Use rate of materials :
Cost of NX diamond core bit @ Rs: 12720.00 / Each Rs: 12720.00
Life of diamond core bit in all types of rock (other than hard rock) : 10.57 m
Use rate of diamond core bit per m drilling ( cost / life ) Rs: 1203.41
320
Preliminary and Maintenance Works - Item Unit Rates 2016-17
Cost of reamer shell @ Rs: 5150.00 / Each Rs: 5150.00
Life of reamer shell in all types of rock (other than hard rock) : 100 m
Use rate of reamer shell per m drilling ( cost / life ) Rs: 51.50
Cost of 16.5 m extension rod @ Rs: 2120.00 / Rm Rs: 34980.00
Life of extension rods : 2500 m
Use rate of 16.5 m length extension rods ( cost / life ) Rs: 13.99
A. MATERIALS:
Sl No particulars Unit Quantity Rate Amount
in Rs. in Rs.
1 Use rate of diamond core bit Rm 3.00 1203.41 3610.22
2 Use rate of reamer shell Rm 3.00 51.50 154.50
4 Use rate of extension rod set 16.5 m Rm 3.00 13.99 41.98
Total cost of Materials Rs: 3806.69
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Core drilling machine Hour 4.78 319.00 1523.54
Fuel / Energy charges Hour 4.78 238.00 1136.69
2 5 hp pump ( diesel ) 2 Nos. Hour 9.55 10.20 97.43
Fuel / Energy charges Hour 9.55 79.30 757.47
3 Sundries LS 2.99 30.00 89.70
Total hire charges of Machinery Rs: 3604.84
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Core drilling machine Hour 4.78 283.90 1355.91
2 Crew for Pump Hour 9.55 111.10 1061.01
3 mazdoor Day 1.19 350.00 416.50
Total cost of Labour Rs: 2833.41
labour component/unit qty 944.50
Add contractor's profit and overhead charges 13.615% 128.60
labour component/unit qty (including contractor's profit) 1073.10
ABSTRACT:
A. Cost of Materials Rs: 3806.69
B. Hire charges of Machinery Rs: 3604.84
C. Cost of Labour Rs: 2833.41
Total Rs: 10244.94
D. Add for contractor's profit and overheads on 13.615% Rs: 1394.848717
Total cost for 3.00 Rm Rs: 11639.79
Rate per Rm (A+B+C+D)/3.0 Rs. 3879.90
NOTE: 1. For drilling in all types of rocks (other than hard rock) including masonry/CC beyond 30 m
upto 60 m from surface increase the basic rate per Rm by 25 percent.
2. For drilling in all types of rocks (other than hard rock) including masonry/CC m from
surface increase the basic beyond 60 m upto 90 rate per Rm by 40 percent.
IRR-PMW-2-5-B
New Item 2015-16-
6 Drilling 76 mm dia ( NX ) core hole in all types of rocks (other than Hard Rock) including
Masonry/CC (where drilling is not possible by casing shoe) using diamond core bit vertical /
inclined upto 10 degree to vertical as directed including cost of all materials, machinery, labour,
water charges, collection of core samples, logging and lebelling, supplying honne wood core box
and redrilling in case of collapse of sides etc., complete for depth upto 30 m from surface
for Test Holes
DATA: For drilling upto 30 m from surface the rate of drilling is assumed at 3 m per day for analysis.
For rate analysis combination of diamond bit and reamer shell is assumed.
500 m long 25 mm dia GI pipe line and 50 m long 25 mm dia water hose are assumed.
For 30 m drilling average 16.5 m extension rods with coupling sleeves required.
Use rate of materials :
Cost of NX diamond core bit @ Rs: 12720.00 / Each Rs: 12720.00
Life of diamond core bit in all types of rock (other than hard rock) : 10.57 m
Use rate of diamond core bit per m drilling ( cost / life ) Rs: 1203.41
Cost of reamer shell @ Rs: 5150.00 / Each Rs: 5150.00
321
Preliminary and Maintenance Works - Item Unit Rates 2016-17
Life of reamer shell in all types of rock (other than hard rock) : 100 m
Use rate of reamer shell per m drilling ( cost / life ) Rs: 51.50
Cost of double core barrel @ Rs: 13568.00 / Each Rs: 13568.00
Life of double tube core barrel : 100 m
Use rate of double tube core barrel per m drilling ( cost / life ) Rs: 135.68
Cost of 16.5 m extension rod @ Rs: 2120.00 / Rm Rs: 34980.00
Life of extension rods : 2500 m
Use rate of 16.5 m length extension rods ( cost / life ) Rs: 13.99
Honne wood core box 1.5 x 0.32 x 0.12 m
Honne wood 0.033 cum @ Rs: 54000.00 / cum Rs: 1782.00
Add for fixtures and painting @ 10% Rs: 178.20
Add for labour charges @ 15% Rs: 267.30
Cost of one box for storing 4 m samples Rs: 2227.50
Use rate of core box per m drilling Rs: 556.88
A. MATERIALS:
Sl No particulars Unit Quantity Rate Amount
in Rs. in Rs.
1 Use rate of diamond core bit Rm 3.00 1203.41 3610.22
2 Use rate of reamer shell Rm 3.00 51.50 154.50
3 Use rate of double tube core barrel Rm 3.00 135.68 407.04
4 Use rate of extension rod set 16.5 m Rm 3.00 13.99 41.98
5 Use rate of honne core box Rm 3.00 556.88 1670.63
Total cost of Materials Rs: 5884.36
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Core drilling machine Hour 4.78 319.00 1523.54
Fuel / Energy charges Hour 4.78 238.00 1136.69
2 5 hp pump ( diesel ) 2 Nos. Hour 9.55 10.20 97.43
Fuel / Energy charges Hour 9.55 79.30 757.47
3 Sundries LS 2.99 30.00 89.70
Total hire charges of Machinery Rs: 3604.84
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Core drilling machine Hour 4.78 283.90 1355.91
2 Crew for Pump Hour 9.55 111.10 1061.23
3 mazdoor Day 1.19 350.00 417.90
Total cost of Labour Rs: 2835.03
labour component/unit qty 945.00
Add contractor's profit and overhead charges 13.615% 128.70
labour component/unit qty (including contractor's profit) 1073.70
ABSTRACT:
A. Cost of Materials Rs: 5884.36
B. Hire charges of Machinery Rs: 3604.84
C. Cost of Labour Rs: 2835.03
Total Rs: 12324.23
D. Add for contractor's profit and overheads on 13.615% Rs: 1677.943669
Total cost for 3.00 Rm Rs: 14002.17
Rate per Rm (A+B+C+D)/3.0 Rs. 4667.40
NOTE: 1. For drilling in all types of rocks (other than hard rock) including masonry/CC beyond 30 m
upto 60 m from surface increase the basic rate per Rm by 25 percent.
2. For drilling in all types of rocks (other than hard rock) including masonry/CC m from
surface increase the basic beyond 60 m upto 90 rate per Rm by 40 percent.
IRR-PMW-2-6 Drilling 47 mm (BX )dia core hole in hard rock using diamond core bit vertical / inclined
upto 10 degree to vertical as directed including cost of all materials, machinery, labour, water
charges,collection of core samples,logging, lebelling, supplying honne wood core box
and redrilling in case of collapse of sides etc., complete for depth upto 30 m from surface.
322
Preliminary and Maintenance Works - Item Unit Rates 2016-17
A. MATERIALS:
Sl No particulars Unit Quantity Rate Amount
in Rs. in Rs.
1 Use rate of diamond core bit Rm 3.00 706.67 2120.00
2 Use rate of reamer shell Rm 3.00 85.83 257.50
3 Use rate of double tube core barrel Rm 3.00 226.13 678.40
4 Use rate of extension rod set 16.5 m Rm 3.00 23.32 69.96
5 Use rate of honne core box Rm 3.00 556.88 1670.63
Total cost of Materials Rs: 4796.49
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Core drilling machine Hour 8.00 319.00 2552.00
Fuel / Energy charges Hour 8.00 238.00 1904.00
2 5 hp pump ( diesel ) 2 Nos. Hour 16.00 10.20 163.20
Fuel / Energy charges Hour 16.00 79.30 1268.80
3 Sundries LS 5.00 30.00 150.00
Total hire charges of Machinery Rs: 6038.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Core drilling machine Hour 8.00 283.90 2271.20
2 Crew for Pump Hour 16.00 111.10 1777.60
3 mazdoor Day 2.00 350.00 700.00
Total cost of Labour Rs: 4748.80
labour component/unit qty 1582.90
Add contractor's profit and overhead charges 13.615% 215.50
labour component/unit qty (including contractor's profit) 1798.40
ABSTRACT:
A. Cost of Materials Rs: 4796.49
B. Hire charges of Machinery Rs: 6038.00
C. Cost of Labour Rs: 4748.80
Total Rs: 15583.29
D. Add for contractor's profit and overheads on
(A+B+C) 13.615% Rs: 2121.664253
Total cost for 3.00 Rm Rs: 17704.95
Rate per Rm (A+B+C+D)/3.0 Rs. 5901.60
NOTE: 1. For drilling in hard rock beyond 30 m upto 60 m from surface increase the
basic rate for drilling upto 30 m from surface by 25 percent per Rm.
2. For drilling in hard rock beyond 60 m upto 90 m from surface increase the basic
rate for drilling upto 30 m from surface by 40 percent per Rm.
IRR-PMW-2-6-A
New Item 2015-16-
7 Drilling 47 mm (BX )dia core hole in all types of rocks (other than Hard Rock) including
Masonry/CC (where drilling is not possible by casing shoe) using diamond core bit vertical /
inclined upto 10 degree to vertical as directed including cost of all materials, machinery, labour,
water charges, and redrilling in case of collapse of sides etc., complete for depth upto 30 m
DATA: For drilling upto 30 m from surface the rate of drilling is assumed at 3 m per day for analysis.
For rate analysis combination of diamond bit and reamer shell is assumed.
500 m long 25 mm dia GI pipe line and 50 m long 25 mm dia water hose are assumed.
For 30 m drilling average 16.5 m extension rods with coupling sleeves required.
Use rate of materials :
Cost of BX diamond core bit @ Rs: 10600.00 / Each Rs: 10600.00
Life of diamond core bit in all types of rock (other than hard rock) : 10.57 m
Use rate of diamond core bit per m drilling ( cost / life ) Rs: 1002.84
Cost of reamer shell @ Rs: 5150.00 / Each Rs: 5150.00
Life of reamer shell in all types of rock (other than hard rock) : 100 m
Use rate of reamer shell per m drilling ( cost / life ) Rs: 51.50
Cost of 16.5 m extension rod @ Rs: 2120.00 / Rm Rs: 34980.00
Life of extension rods : 2500 m
Use rate of 16.5 m length extension rods ( cost / life ) Rs: 13.99
323
Preliminary and Maintenance Works - Item Unit Rates 2016-17
Data: RATE ANALYSIS UNIT : 3.00 Rm
A. MATERIALS:
Sl No particulars Unit Quantity Rate Amount
in Rs. in Rs.
1 Use rate of diamond core bit Rm 3.00 1002.84 3008.51
2 Use rate of reamer shell Rm 3.00 51.50 154.50
4 Use rate of extension rod set 16.5 m Rm 3.00 13.99 41.98
Total cost of Materials Rs: 3204.99
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Core drilling machine Hour 4.78 319.00 1523.54
Fuel / Energy charges Hour 4.78 238.00 1136.69
2 5 hp pump ( diesel ) 2 Nos. Hour 9.55 10.20 97.43
Fuel / Energy charges Hour 9.55 79.30 757.47
3 Sundries LS 2.99 30.00 89.70
Total hire charges of Machinery Rs: 3604.84
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Core drilling machine Hour 4.78 283.90 1355.91
2 Crew for Pump Hour 9.55 111.10 1061.01
3 mazdoor Day 1.19 350.00 416.50
Total cost of Labour Rs: 2833.41
labour component/unit qty 944.50
Add contractor's profit and overhead charges 13.615% 128.60
labour component/unit qty (including contractor's profit) 1073.10
ABSTRACT:
A. Cost of Materials Rs: 3204.99
B. Hire charges of Machinery Rs: 3604.84
C. Cost of Labour Rs: 2833.41
Total Rs: 9643.24
D. Add for contractor's profit and overheads on 13.615% Rs: 1312.926862
Total cost for 3.00 Rm Rs: 10956.16
Rate per Rm (A+B+C+D)/3.0 Rs. 3652.10
NOTE: 1. For drilling in all types of rocks (other than hard rock) including masonry/CC beyond 30 m
upto 60 m from surface increase the basic rate per Rm by 25 percent.
2. For drilling in all types of rocks (other than hard rock) including masonry/CC m from
surface increase the basic beyond 60 m upto 90 rate per Rm by 40 percent.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 1.00 450.00 450.00
2 Stone chiseller Cl- I Day 1.00 445.00 445.00
324
Preliminary and Maintenance Works - Item Unit Rates 2016-17
3 mazdoor Day 3.00 350.00 1050.00
Total cost of Labour Rs: 1945.00
labour component/unit qty 108.10
Add contractor's profit and overhead charges 13.615% 14.70
labour component/unit qty (including contractor's profit) 122.80
ABSTRACT:
A. Cost of Materials Rs: 579.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 1945.00
Total Rs: 2524.00
D. Add for contractor's profit and overheads on
(A+B+C) 13.615% Rs: 343.6426
Total cost for 18.00 Nos. Rs: 2867.64
Rate per each (A+B+C+D)/18.0 Rs. 159.30
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 1.00 450.00 450.00
2 Stone chiseller Cl- I Day 3.00 445.00 1335.00
3 mazdoor Day 4.00 350.00 1400.00
Total cost of Labour Rs: 3185.00
labour component/unit qty 318.50
Add contractor's profit and overhead charges 13.615% 43.40
labour component/unit qty (including contractor's profit) 361.90
ABSTRACT:
A. Cost of Materials Rs: 1308.10
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 3185.00
Total Rs: 4493.10
D. Add for contractor's profit and overheads on
(A+B+C) 13.615% Rs: 611.735565
Total cost for 10.00 Nos. Rs: 5104.84
Rate per each (A+B+C+D)/10.0 Rs. 510.50
NOTE: For providing 30 cm thick compacted murum bed in B.C soil area including
additional excavation for thickness of murum bedding add per
Each Rs: 4.00
325
Preliminary and Maintenance Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 1.00 450.00 450.00
2 Stone chiseller Cl- I Day 0.50 445.00 222.50
3 Mason Cl- II Day 1.00 400.00 400.00
4 mazdoor Day 5.00 350.00 1750.00
Total cost of Labour Rs: 2822.50
labour component/unit qty 2822.50
Add contractor's profit and overhead charges 13.615% 384.30
labour component/unit qty (including contractor's profit) 3206.80
ABSTRACT:
A. Cost of Materials Rs: 2710.20
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 2822.50
Total Rs: 5532.70
D. Add for contractor's profit and overheads on
(A+B+C) 13.615% Rs: 753.277105
Total cost for 1.00 No. Rs: 6285.98
Rate per each (A+B+C+D)/1.0 Rs. 6286.00
IRR-PMW-3-1 Removing dry stone rock-toe / rivetment and filter layers below rock-toe/ rivetment
including stacking all materials separately as directed with initial lead upto 50 m and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 1.00 450.00 450.00
326
Preliminary and Maintenance Works - Item Unit Rates 2016-17
2 Mason Cl- II Day 6.00 400.00 2400.00
3 mazdoor Day 48.00 350.00 16800.00
Total cost of Labour Rs: 19650.00
labour component/unit qty 187.10
Add contractor's profit and overhead charges 13.615% 25.50
labour component/unit qty (including contractor's profit) 212.60
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 19650.00
Total Rs: 19650.00
D. Add for contractor's profit and overheads on
(A+B+C) 13.615% Rs: 2675.3475
Total cost for 105.00 cum Rs: 22325.35
Rate per cum (A+B+C+D)/105.0 Rs. 212.60
IRR-PMW-3-2 Re-constructing 60 cm thick hand packed rough stone revetment with through
stones at 1.5 m c / c over a backing of 45 cm thick graded filter media consisting of sand,
10 mm and 40 mm size graded aggregates satisfying filter criteria laid in layers of 15 cm thick
each using sand from approved quarry and stones and filter aggregates obtained from
revetment removed for re-construction including cost of all machinery, labour, laying filter and
stones to specified slopes, wedging with chips, finishing etc. complete with initial
lead upto 50 m and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 1.00 450.00 450.00
2 Mason Cl- II Day 5.00 400.00 2000.00
3 mazdoor Day 33.00 350.00 11550.00
Total cost of Labour Rs: 14000.00
labour component/unit qty 140.00
Add contractor's profit and overhead charges 13.615% 19.10
labour component/unit qty (including contractor's profit) 159.10
ABSTRACT:
A. Cost of Materials Rs: 1453.50
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 14000.00
Total Rs: 15453.50
D. Add for contractor's profit and overheads on
(A+B+C) 13.615% Rs: 2103.994025
Total cost for 100.00 sqm Rs: 17557.49
Rate per sqm (A+B+C+D)/100.0 Rs. 175.60
IRR-PMW-3-3 Re-constructing dry rubble rock-toe and filter media for rock-toe consisting of
sand 20 mm and 80 mm size graded aggregates satisfying filter criteria laid in layers of 15 cm
327
Preliminary and Maintenance Works - Item Unit Rates 2016-17
thick each using sand from approved quarry and stones and filter aggregates obtained from
rock-toe removed for re-construction including cost of all machinery, labour, laying filter and
stones to specified slopes, wedging with chips, finishing etc. complete with initial lead upto
50 m and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 1.00 450.00 450.00
2 Mason Cl- II Day 7.00 400.00 2800.00
3 mazdoor Day 48.00 350.00 16800.00
Total cost of Labour Rs: 20050.00
labour component/unit qty 200.50
Add contractor's profit and overhead charges 13.615% 27.30
labour component/unit qty (including contractor's profit) 227.80
ABSTRACT:
A. Cost of Materials Rs: 931.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 20050.00
Total Rs: 20981.00
D. Add for contractor's profit and overheads on
(A+B+C) 13.615% Rs: 2856.56315
Total cost for 100.00 cum Rs: 23837.56
Rate per cum (A+B+C+D)/100.0 Rs. 238.40
IRR-PMW-3-4 Removing and resetting disturbed Yarguntla / Shahabad / Talikot / PCC / Other types
of slab lining set in CM 1 : 3 including flush cement mortar pointing in CM 1 : 3 with
lead upto 50 m and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 1.00 450.00 450.00
328
Preliminary and Maintenance Works - Item Unit Rates 2016-17
2 Mason Class I Day 4.00 445.00 1780.00
3 mazdoor Day 6.00 350.00 2100.00
4 Cartman with Double Bullock cart for water Day 1.00 465.00 465.00
Total cost of Labour Rs: 4795.00
labour component/unit qty 48.00
Add contractor's profit and overhead charges 13.615% 6.50
labour component/unit qty (including contractor's profit) 54.50
ABSTRACT:
A. Cost of Materials Rs: 575.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 4795.00
Total Rs: 5370.00
D. Add for contractor's profit and overheads on
(A+B+C) 13.615% Rs: 731.1255
Total cost for 100.00 sqm Rs: 6101.13
Rate per sqm (A+B+C+D)/100.0 Rs. 61.00
IRR-PMW-3-5 Removing and resetting disturbed dry rubble / khandki stone pitching 25 to 45 cm
thick including packing, wedging, finishing etc., complete with all leads and lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 1.00 450.00 450.00
2 Mason Class II Day 6.00 400.00 2400.00
3 mazdoor Day 6.00 350.00 2100.00
Total cost of Labour Rs: 4950.00
labour component/unit qty 49.50
Add contractor's profit and overhead charges 13.615% 6.70
labour component/unit qty (including contractor's profit) 56.20
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 4950.00
Total Rs: 4950.00
D. Add for contractor's profit and overheads on
(A+B+C) 13.615% Rs: 673.9425
Total cost for 100.00 sqm Rs: 5623.94
Rate per sqm (A+B+C+D)/100.0 Rs. 56.20
IRR-PMW-3-6 Removing and refixing disturbed chainage / demarcation / hectometre / guard stones
including excavation, back filling etc., complete with all leads and lifts.
329
Preliminary and Maintenance Works - Item Unit Rates 2016-17
Total cost of Materials Rs: 0.00
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 1.00 450.00 450.00
2 mazdoor Day 2.00 350.00 700.00
Total cost of Labour Rs: 1150.00
labour component/unit qty 63.89
Add contractor's profit and overhead charges 13.615% 8.70
labour component/unit qty (including contractor's profit) 72.60
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 1150.00
Total Rs: 1150.00
D. Add for contractor's profit and overheads on
(A+B+C) 13.615% Rs: 156.5725
Total cost for 18.00 Nos. Rs: 1306.57
Rate per each (A+B+C+D)/18.0 Rs. 72.60
IRR-PMW-3-7 Removing and refixing disturbed km stone / sign board / hecto-metre stone etc., including
excavation, back filling with available stuff after refixing, forming base platform of size 90 x 90 x
7.5 cm including watering, ramming etc complete with all leads and lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 1.00 450.00 450.00
2 mazdoor Day 2.00 350.00 700.00
Total cost of Labour Rs: 1150.00
labour component/unit qty 143.75
Add contractor's profit and overhead charges 13.615% 19.57
labour component/unit qty (including contractor's profit) 163.30
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 1150.00
Total Rs: 1150.00
D. Add for contractor's profit and overheads on
(A+B+C) 13.615% Rs: 156.5725
Total cost for 8.00 Nos. Rs: 1306.57
Rate per each (A+B+C+D)/18.0 Rs. 163.30
330
Preliminary and Maintenance Works - Item Unit Rates 2016-17
IRR-PMW-3-8 Providing impervious hearting for breached / damaged portion of embankment
with soil from approved borrow areas in layers of 10 to 15 cm before compaction including
cost of all materials, machinery, labour, all operations such as collection of soil, sorting out,
spreading soil to specified thickness, breaking clods, sectioning, watering, compacting each
layer to density control of not less than 98 percent or as stipulated by rolling or
by using mechanical tampers etc., complete with initial lead upto 1 km and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Angle dozer Hour 5.00 1715.50 8577.50
Fuel / Energy charges Hour 5.00 610.50 3052.50
2 Shovel 0.50 cum capacity Hour 8.00 1003.10 8024.80
Fuel / Energy charges Hour 8.00 476.00 3808.00
3 Tippers 5.00 cum capacity 4 Nos. Hour 32.00 446.70 14294.40
Fuel / Energy charges Hour 32.00 299.90 9596.80
4 Pump 5 hp ( diesel ) Hour 2.00 10.20 20.40
Fuel / Energy charges Hour 2.00 79.30 158.60
5 Water tanker 8000 ltr Hour 4.00 402.50 1610.00
Fuel / Energy charges Hour 4.00 299.90 1199.60
6 Vibratory pad foot roller 8 tonne Hour 6.00 1342.20 8053.20
Fuel / Energy charges Hour 6.00 1031.40 6188.40
7 Sundries LS 2.00 30.00 60.00
Total hire charges of Machinery Rs: 64644.20
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Dozer Hour 4.00 236.60 946.40
2 Crew for Shovel Hour 8.00 236.60 1892.80
3 Crew for Tipper Hour 32.00 177.50 5680.00
4 Crew for Pump Hour 3.00 111.10 333.30
5 Crew for Water tanker Hour 5.00 177.50 887.50
6 Crew for Roller Hour 6.00 263.60 1581.60
7 work inspector Day 2.00 450.00 900.00
8 mazdoor Day 4.00 350.00 1400.00
Total cost of Labour Rs: 13621.60
labour component/unit qty 28.40
Add contractor's profit and overhead charges 13.615% 3.90
labour component/unit qty (including contractor's profit) 32.30
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 64644.20
C. Cost of Labour Rs: 13621.60
Total Rs: 78265.80
D. Add for contractor's profit and overheads on
(A+B+C) 13.615% Rs: 10655.88867
Total cost for 480.00 cum Rs: 88921.69
Rate per cum (A+B+C+D)/480.0 Rs. 185.30
331
Preliminary and Maintenance Works - Item Unit Rates 2016-17
Sl No particulars Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total cost of Materials Rs: 0.00
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Angle dozer 90 hp Hour 3.50 1715.50 6004.25
Fuel / Energy charges Hour 3.50 610.50 2136.75
2 Shovel 0.50 cum capacity Hour 8.00 1003.10 8024.80
Fuel / Energy charges Hour 8.00 476.00 3808.00
3 Tippers 5.00 cum capacity 3 Nos. Hour 24.00 446.70 10720.80
Fuel / Energy charges Hour 24.00 299.90 7197.60
4 Pump 5 hp ( diesel ) Hour 1.50 10.20 15.30
Fuel / Energy charges Hour 1.50 79.30 118.95
5 Water tanker 8000 ltr Hour 3.00 402.50 1207.50
Fuel / Energy charges Hour 3.00 299.90 899.70
6 Vibratory pad foot roller 8 tonne Hour 4.00 1342.20 5368.80
Fuel / Energy charges Hour 4.00 1031.40 4125.60
7 Sundries LS 2.00 30.00 60.00
Total hire charges of Machinery Rs: 49688.05
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Dozer Hour 3.50 236.60 828.10
2 Crew for Shovel Hour 8.00 236.60 1892.80
3 Crew for Tipper Hour 24.00 177.50 4260.00
4 Crew for Pump Hour 1.50 111.10 166.65
5 Crew for Water tanker Hour 3.00 177.50 532.50
6 Crew for Roller Hour 4.00 263.60 1054.40
7 work inspector Day 2.00 450.00 900.00
8 mazdoor Day 4.00 350.00 1400.00
Total cost of Labour Rs: 11034.45
labour component/unit qty 34.00
Add contractor's profit and overhead charges 13.615% 4.60
labour component/unit qty (including contractor's profit) 38.60
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 49688.05
C. Cost of Labour Rs: 11034.45
Total Rs: 60722.50
D. Add for contractor's profit and overheads on
(A+B+C) 13.615% Rs: 8267.368375
Total cost for 325.00 cum Rs: 68989.87
Rate per cum (A+B+C+D)/325.0 Rs. 212.30
IRR-PMW-3-10 Providing impervious hearting for breached / damaged portion of embankment with
soil from approved dump areas in layers of 10 to 15 cm before compaction including cost
of all materials, machinery, labour, all operations such as collection of soil,sorting out,
spreading soil to specified thickness, breaking clods, sectioning, watering, compacting each
layer to density control of not less than 98 percent or as stipulated by rolling or by using
mechanical tampers etc., complete with initial lead upto 1 km and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
332
Preliminary and Maintenance Works - Item Unit Rates 2016-17
1 Angle dozer Hour 4.00 1715.50 6862.00
Fuel / Energy charges Hour 4.00 610.50 2442.00
2 Shovel 0.50 cum capacity Hour 8.00 1003.10 8024.80
Fuel / Energy charges Hour 8.00 476.00 3808.00
3 Tippers 5.00 cum capacity 5 Nos. Hour 40.00 446.70 17868.00
Fuel / Energy charges Hour 40.00 299.90 11996.00
4 Pump 5 hp ( diesel ) Hour 4.00 10.20 40.80
Fuel / Energy charges Hour 4.00 79.30 317.20
5 Water tanker 8000 ltr Hour 7.00 402.50 2817.50
Fuel / Energy charges Hour 7.00 299.90 2099.30
6 Vibratory pad foot roller 8 tonne Hour 7.50 1342.20 10066.50
Fuel / Energy charges Hour 7.50 1031.40 7735.50
7 Sundries LS 2.00 30.00 60.00
Total hire charges of Machinery Rs: 74137.60
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Dozer Hour 4.00 236.60 946.40
2 Crew for Shovel Hour 8.00 236.60 1892.80
3 Crew for Tipper Hour 40.00 177.50 7100.00
4 Crew for Pump Hour 4.00 111.10 444.40
5 Crew for Water tanker Hour 7.00 177.50 1242.50
6 Crew for Roller Hour 7.50 263.60 1977.00
7 work inspector Day 2.00 450.00 900.00
8 mazdoor Day 6.00 350.00 2100.00
Total cost of Labour Rs: 16603.10
labour component/unit qty 27.10
Add contractor's profit and overhead charges 13.615% 3.70
labour component/unit qty (including contractor's profit) 30.80
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 74137.60
C. Cost of Labour Rs: 16603.10
Total Rs: 90740.70
D. Add for contractor's profit and overheads on
(A+B+C) 13.615% Rs: 12354.34631
Total cost for 612.00 cum Rs: 103095.05
Rate per cum (A+B+C+D)/612.0 Rs. 168.50
IRR-PMW-3-11 Providing pervious /semi-pervious casing for breached /damaged portion of embankment
with soil from approved dump areas in layers of 10 to 15 cm before compaction including
cost of all materials, machinery, labour, all operations such as collection of soil, sorting out,
spreading soil to specified thickness, breaking clods, sectioning, watering, compacting each
layer to density control of not less than 98 percent or as stipulated by rolling or by using
mechanical tampers etc., complete with initial lead upto 1 km and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Angle dozer 90 hp Hour 3.00 1715.50 5146.50
Fuel / Energy charges Hour 3.00 610.50 1831.50
2 Shovel 0.50 cum capacity Hour 8.00 1003.10 8024.80
Fuel / Energy charges Hour 8.00 476.00 3808.00
3 Tippers 5.00 cum capacity 4 Nos. Hour 32.00 446.70 14294.40
Fuel / Energy charges Hour 32.00 299.90 9596.80
4 Pump 5 hp ( diesel ) Hour 3.00 10.20 30.60
Fuel / Energy charges Hour 3.00 79.30 237.90
5 Water tanker 8000 ltr Hour 6.00 402.50 2415.00
333
Preliminary and Maintenance Works - Item Unit Rates 2016-17
Fuel / Energy charges Hour 6.00 299.90 1799.40
6 Vibratory pad foot roller 8 tonne Hour 5.50 1342.20 7382.10
Fuel / Energy charges Hour 5.50 1031.40 5672.70
7 Sundries LS 2.00 30.00 60.00
Total hire charges of Machinery Rs: 60299.70
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Dozer Hour 3.00 236.60 709.80
2 Crew for Shovel Hour 8.00 236.60 1892.80
3 Crew for Tipper Hour 32.00 177.50 5680.00
4 Crew for Pump Hour 3.00 111.10 333.30
5 Crew for Water tanker Hour 6.00 177.50 1065.00
6 Crew for Roller Hour 5.50 263.60 1449.80
7 work inspector Day 2.00 450.00 900.00
8 mazdoor Day 6.00 350.00 2100.00
Total cost of Labour Rs: 14130.70
labour component/unit qty 32.10
Add contractor's profit and overhead charges 13.615% 4.40
labour component/unit qty (including contractor's profit) 36.50
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 60299.70
C. Cost of Labour Rs: 14130.70
Total Rs: 74430.40
D. Add for contractor's profit and overheads on
(A+B+C) 13.615% Rs: 10133.69896
Total cost for 440.00 cum Rs: 84564.10
Rate per cum (A+B+C+D)/440.0 Rs. 192.20
IRR-PMW-3-12 Repairing rain cuts / resectioning canal slopes to required lines and grades as directed
using available soil including dressing, clod breaking, packing, tamping etc., complete with
all leads and lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 1.00 450.00 450.00
2 mazdoor Day 8.00 350.00 2800.00
Total cost of Labour Rs: 3250.00
labour component/unit qty 3.25
Add contractor's profit and overhead charges 13.615% 0.44
labour component/unit qty (including contractor's profit) 3.70
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 3250.00
Total Rs: 3250.00
D. Add for contractor's profit and overheads on
(A+B+C) 13.615% Rs: 442.4875
334
Preliminary and Maintenance Works - Item Unit Rates 2016-17
Total cost for 1000.00 sqm Rs: 3692.49
Rate per sqm (A+B+C+D)/1000.0 Rs. 3.70
IRR-PMW-3-13 Cleaning drainage gallery, adits, instrumentation galleries etc., by scrubbing / brushing
including chiselling and removing leached lime deposit and disposing off all the waste material
out side adits in specified location etc., complete with all leads and lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Chiseller Cl II Day 2.00 400.00 800.00
2 mazdoor Day 6.00 350.00 2100.00
Total cost of Labour Rs: 2900.00
labour component/unit qty 29.00
Add contractor's profit and overhead charges 13.615% 3.90
labour component/unit qty (including contractor's profit) 32.90
ABSTRACT:
A. Cost of Materials Rs: 715.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 2900.00
Total Rs: 3615.00
D. Add for contractor's profit and overheads on
(A+B+C) 13.615% Rs: 492.18225
Total cost for 100.00 Rm Rs: 4107.18
Rate per Rm (A+B+C+D)/100.0 Rs. 41.10
IRR-PMW-3-14 Cleaning dam parapet inner face and top using oxalic acid and water by scrubbing /
brushing and washing to remove all surface coatings etc., complete .
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
335
Preliminary and Maintenance Works - Item Unit Rates 2016-17
1 mazdoor Day 6.00 350.00 2100.00
Total cost of Labour Rs: 2100.00
labour component/unit qty 21.00
Add contractor's profit and overhead charges 13.615% 2.90
labour component/unit qty (including contractor's profit) 23.90
ABSTRACT:
A. Cost of Materials Rs: 1115.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 2100.00
Total Rs: 3215.00
D. Add for contractor's profit and overheads on
(A+B+C) 13.615% Rs: 437.72225
Total cost for 100.00 Rm Rs: 3652.72
Rate per Rm (A+B+C+D)/100.0 Rs. 36.50
IRR-PMW-3-20 Excavation and removal of silt and silt mixed with sand from canal bed in dry condition
including disposing off the same in spoil bank or on the canal embankment in layers as
directed etc., complete with initial lead upto 50 m and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 mazdoor Day 4.00 350.00 1400.00
Total cost of Labour Rs: 1400.00
labour component/unit qty 140.00
Add contractor's profit and overhead charges 13.615% 19.10
labour component/unit qty (including contractor's profit) 159.10
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 1400.00
Total Rs: 1400.00
D. Add for contractor's profit and overheads on
(A+B+C) 13.615% Rs: 190.61
Total cost for 10.00 cum Rs: 1590.61
Rate per cum (A+B+C+D)/10.0 Rs. 159.10
IRR-PMW-3-21 Excavation and removal of silt or silt mixed with sand in slussy condition from canal bed
including disposing off the same in spoil bank or on the canal embankment in layers as
directed etc., complete with initial lead upto 50 m and all lifts.
336
Preliminary and Maintenance Works - Item Unit Rates 2016-17
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 mazdoor Day 6.00 350.00 2100.00
Total cost of Labour Rs: 2100.00
labour component/unit qty 175.00
Add contractor's profit and overhead charges 13.615% 23.80
labour component/unit qty (including contractor's profit) 198.80
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 2100.00
Total Rs: 2100.00
D. Add for contractor's profit and overheads on
(A+B+C) 13.615% Rs: 285.915
Total cost for 12.00 cum Rs: 2385.92
Rate per cum (A+B+C+D)/12.0 Rs. 198.80
RATE ANALYSIS
A. MATERIALS: Unit: 807.00 cum
Sl No Particulars Unit Quantity Rate Amount
in Rs. in Rs
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total cost of Materials Rs: 0.00
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Angle dozer 90 hp Hour 2.70 1715.50 4631.85
Fuel / Energy charges Hour 2.70 610.50 1648.35
2 Shovel 0.85 cum capacity Hour 8.00 1706.60 13652.80
Fuel / Energy charges Hour 8.00 872.70 6981.60
3 Tippers 5.00 cum capacity 5 Nos. Hour 40.00 446.70 17868.00
Fuel / Energy charges Hour 40.00 299.90 11996.00
Total hire charges of Machinery Rs: 56778.60
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Dozer Hour 2.70 236.60 638.82
2 Crew for Shovel Hour 8.00 236.60 1892.80
3 Crew for Tipper Hour 40.00 177.50 7100.00
4 work inspector Day 1.00 450.00 450.00
5 mazdoor Day 2.00 350.00 700.00
Total cost of Labour Rs: 10781.62
labour component/unit qty 13.40
Add contractor's profit and overhead charges 13.615% 1.80
labour component/unit qty (including contractor's profit) 15.20
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 56778.60
C. Cost of Labour Rs: 10781.62
Total Rs: 67560.22
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 9198.32
Total cost for 807.00 cum Rs: 76758.54
337
Preliminary and Maintenance Works - Item Unit Rates 2016-17
Rate per cum (A+B+C+D)/807 Rs: 95.10
RATE ANALYSIS
A. MATERIALS: UNIT : 807.00 cum
Sl No Particulars Unit Quantity Rate Amount
in Rs. in Rs
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total cost of Materials Rs: 0.00
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Angle dozer 90 hp Hour 2.70 1715.50 4631.85
Fuel / Energy charges Hour 2.70 610.50 1648.35
2 Pump 5 hp ( ele ) Hour 4.00 3.00 12.00
Fuel / Energy charges Hour 4.00 28.00 112.00
3 Water tanker 8000 ltr Hour 8.00 402.50 3220.00
Fuel / Energy charges Hour 8.00 299.90 2399.20
4 Vibratory pad foot roller 8 tonne Hour 6.40 1342.20 8590.08
Fuel / Energy charges Hour 6.40 1031.40 6600.96
5 Sundries LS 2.00 30.00 60.00
Total hire charges of Machinery Rs: 27274.44
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Dozer Hour 2.70 236.60 638.82
4 Crew for Pump Hour 4.00 83.30 333.20
5 Crew for Water tanker Hour 8.00 177.50 1420.00
6 Crew for Roller Hour 6.40 263.60 1687.04
7 work inspector Day 1.00 450.00 450.00
8 mazdoor Day 2.00 350.00 700.00
Total cost of Labour Rs: 5229.06
labour component/unit qty 6.50
Add contractor's profit and overhead charges 13.615% 0.90
labour component/unit qty (including contractor's profit) 7.40
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 27274.44
C. Cost of Labour Rs: 5229.06
Total Rs: 32503.50
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 4425.35
Total cost
for 807.00 cum Rs: 36928.85
Rate per cum (A+B+C+D)/807 Rs: 45.80
New Item 7 - 2010-11 area in layers of 25 to 30 cm before compaction including cost of all
materials, machinery, labour, all operations such as compacting
to density control of not less than 90 percent or as stipulated using
2T roller etc., complete with initial lead upto 1 km and all lifts.
RATE ANALYSIS
A. MATERIALS: UNIT : 807.00 cum
Sl No Particulars Unit Quantity Rate Amount
in Rs. in Rs
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total cost of Materials Rs: 0.00
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
338
Preliminary and Maintenance Works - Item Unit Rates 2016-17
1 Tractor with 2T Roller Hour 10.00 345.00 3450.00
2 Sundries LS 2.00 30.00 60.00
Total hire charges of Machinery Rs: 3510.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 work inspector Day 0.50 450.00 225.00
2 mazdoor Day 2.00 350.00 700.00
Total cost of Labour Rs: 925.00
labour component/unit qty 1.10
Add contractor's profit and overhead charges 13.615% 0.10
labour component/unit qty (including contractor's profit) 1.20
ABSTRAC
T:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 3510.00
C. Cost of Labour Rs: 925.00
Total Rs: 4435.00
D.Add for contractor's profit and overheads on 13.615% Rs. 603.82525
Total cost for 807.00 cum Rs: 5038.83
Rate per cum (A+B+C+D)/807 Rs: 6.20
RATE ANALYSIS
Unit : 2000 Sqm
A. MATERIALS
B. MACHINERY
C. LABOUR
ABSTRACT:
A.COST OF MATERIALS Rs. 0.00
B.COST OF MACHINERY Rs. 0.00
C.COST OF LABOUR Rs. 11375.00
Total 11375.00
D. Add for Contractor's Profit and overheads 13.615% 1548.70625
Total Cost for removal weed in the extent of 2000 Sqm 12923.71
Rate per Sqm (A+B+C+D)/2000 6.5
RATE ANALYSIS
Unit : 2000 Sqm
A. MATERIALS
B. MACHINERY
339
Preliminary and Maintenance Works - Item Unit Rates 2016-17
C. LABOUR
ABSTRACT:
A.COST OF MATERIALS Rs. 0.00
B.COST OF MACHINERY Rs. 0.00
C.COST OF LABOUR Rs. 15550.00
Total 15550.00
D. Add for Contractor's Profit and overheads 13.615% 2117.1325
Total Cost for removal weed in the extent of 2000 Sqm 17667.13
Rate per Sqm (A+B+C+D)/2000 8.8
RATE ANALYSIS
Unit : 2000 Sqm
A. MATERIALS
B. MACHINERY
C. LABOUR
ABSTRACT:
A.COST OF MATERIALS Rs. 0.00
B.COST OF MACHINERY Rs. 0.00
C.COST OF LABOUR Rs. 10450.00
Total 10450.00
D. Add for Contractor's Profit and overheads 14% 1422.7675
Total Cost for removal weed in the extent of 2000 Sqm 11872.77
Rate per Sqm (A+B+C+D)/2000 5.9
RATE ANALYSIS
Unit : 2000 Sqm
A. MATERIALS
B. MACHINERY
C. LABOUR
340
Preliminary and Maintenance Works - Item Unit Rates 2016-17
ABSTRACT:
A.COST OF MATERIALS Rs. 0.00
B.COST OF MACHINERY Rs. 0.00
C.COST OF LABOUR Rs. 8825.00
Total 8825.00
D. Add for Contractor's Profit and overheads 14% 1201.52375
Total Cost for removal weed in the extent of 2000 Sqm 10026.52
Rate per Sqm (A+B+C+D)/2000 5
RATE ANALYSIS
Unit : 2000 Sqm
A. MATERIALS
B. MACHINERY
C. LABOUR
ABSTRACT:
A.COST OF MATERIALS Rs. 0.00
B.COST OF MACHINERY Rs. 0.00
C.COST OF LABOUR Rs. 10450.00
Total 10450.00
D. Add for Contractor's Profit and overheads 14% 1422.7675
Total Cost for removal weed in the extent of 2000 Sqm 11872.77
Rate per Sqm (A+B+C+D)/2000 5.9
RATE ANALYSIS
Unit : 2000 Sqm
A. MATERIALS
B. MACHINERY
C. LABOUR
341
Preliminary and Maintenance Works - Item Unit Rates 2016-17
ABSTRACT:
A.COST OF MATERIALS Rs. 0.00
B.COST OF MACHINERY Rs. 0.00
C.COST OF LABOUR Rs. 3340.00
Total 3340.00
D. Add for Contractor's Profit and overheads 14% 454.741
Total Cost for removal weed in the extent of 2000 Sqm 3794.74
Rate per Sqm (A+B+C+D)/2000 1.9
IRR-PMW-3-26
New Item 2015-16-
8 PAINTING OF SLUICES FOR MAINTENANCE WORKS
Surface cleaning of metal surfaces by chemical cleaners and then by hand and power tool cleaners
and removing dust. After cleaniong, applying primary coat with one coat of Zinc rich
epoxy primer to a thickness of 100 microns, followed by finishing coats 2 coats with
Coal tar epoxy with material, labour, and all accessories with all leads and lifts.
B. Machinery
Sl. No. Particulars Unit Quantity Rate in Rs. Amount in Rs.
NIL
Total Cost of Machinery 0
C. Labour
Sl. No. Particulars Unit Quantity Rate in Rs. Amount in Rs.
1 Painter Class-II Day 20 400.00 8000
2 Helper Day 20 350.00 7000
Total Cost of Machinery 15000
Labour Component/ Unit Qty. 150
Add Contractor's Profit and and Overhead Charges @ 13.615% 20.4225
Labour Component/ Unit Qty (including contractor' profit) 170.4225
ABSTRACT:
A. Cost of Materials: 20802
B. Hire Charges of Machinery 0
C. Cost of Labour 15000
Total 35802
D. Add for Excise Duty on 75% cost excluding cost of materials) 0% 0
Total 35802
E. Add for transportation Charges upto worksite @ 3% 1074.06
Total 36876.06
F. Add for Contractor's Profit and Overhead Charges @13.615% 13.615% 5020.68
Total Cost per 100 Sqm 41896.74
Rate per Sqm 419
342
Manual works - 2016-17
COM_MWRK-2 (Manual)Excavation in all kinds of soil/ HDR including boulders upto 0.30 m dia. for
foundations of canal cross drainage and other appurtenant structures
and placing excavated stuff neatly in specified dump area or disposing
off the same as directed etc., complete with initial lead upto 10 m and per cum 140.00
initial lift upto 1.5 m. (WIthout involving the contractors for specified works )
With 2.5 Cum per day output
COM_MWRK-3 (Manual)Excavation in soft rock (including F&F) without blasting, including boulders upto 0.30 m dia. for
foundations of canal cross drainage and other appurtenant structures
and placing excavated stuff neatly in specified dump area or disposing
off the same as directed etc., complete with initial lead upto 10 m and per cum 263.20
initial lift upto 1.5 m. (WIthout involving the contractors for specified works )
Soft rock 1.33 Cum/Day
COM_MWRK-4 (Manual)Excavation in hard rock, including boulders upto 0.30 m dia. for
foundations of canal cross drainage and other appurtenant structures
and placing excavated stuff neatly in specified dump area or disposing
off the same as directed etc., complete with initial lead upto 10 m and per cum 522.40
initial lift upto 1.5 m. (WIthout involving the contractors for specified works )
Hard rock 0.67Cum/ day
343
COM-LDLFT-2016-17
COM-LDLFT 1. For total lead upto 150 m ( including initial lead ) lead charges by head load only shall be
adopted irrespective of mode of conveyance.
2. For total lead exceeding 150 m conveyance by mechanical means only shall be adopted
irrespective of mode of conveyance.
3. The rates for loading at quarry including idle hire charges of trucks and hire charges per for
each kilometer and upto 5 km are cumulative and inclusive of total charges for preceding lead.
4. Unless otherwise specified lead charges for Earth / Sand / Gravel / Aggregates and Stones
are for loose volume and not for compacted or in-situ volume.
5. The rates for lift charges,lead charges, hire charges are cumulative and inclusive of
rates for preceding lift,lead and hire charges
6. Lift charges are not payable where conveyance of materials is by mechanical means to
final placing point.
7. Loading and unloading charges are not payable for conveyance by head load.
8. Loading charges are not payable for conveyance by mechanical means for disposal of
excavated materials beyond initial lead of 50 m wherever specified.
9. Loading and unloading charges are not payable for conveyance by mechanical means for
disposal of excavated materials beyond initial lead of 1 km wherever specified.
10. The rates for unloading of materials except earth, sand, gravel, coarse aggregate, rubble,
size stone and cut stone are inclusive of stacking.
11. Hire charges are per 1KM for tippers and trucks for tranport of materials from work site to dump
yard and other places are cumulative& includes previous km upto 5 kms
12. The lead & lift charges are inclusive of contractor's profit and overhead charges of 13.615%
Notes: 1. No loading or unloading charges are admissible for conveyance by head load.
2. For total lead exceeding 150 m conveyance charges by mechanical means only shall
be adopted irrespective of mode of conveyance.
3. The Lead Charges are inclusive of 13.615% Contractor Profit and Overhead charges
COM-LDLFT-2 B.( Lead) Conveyance charges for machinery per kilometer for transporting materials
by tippers and trucks excluding loading, unloading and idle hire charges of machinery.
FOR THE YEAR: 2016-17
( No loading and unloading charges allowed for machinery loading and unloading )
(Lead)
charges for (Lead) charges
(Lead) charges trucks and for trucks and
(Lead) charges for (Lead) (Lead)
for trucks and tippers for tippers per
trucks and tippers for charges charges
tippers for Earth Rubble/Size cu.meter for
Cement/ Steel/ RCC for per for trucks
Sl No. Distance / Sand /Gravel / stones/ Cut PCC slabs/
poles/ AC & GI sheets/ cu.meter per 1000
Murrum/ Lime/ Stones/ Shahabad
Packed for water/ Nos. of
Surki/ per Coarse slabs/ CC &
materials/tonne 1000 litres Bricks
cu.meter aggregate Laterite blocks/
per Wood/ cum
cu.meter
1 2 3 4 5 6 7 8
1 Lead upto 1 km 31.50 30.40 19.00 44.70 18.70 50.70
2 Lead upto 2 km 44.10 42.50 26.60 62.60 26.20 70.90
3 Lead upto 3 km 58.80 58.80 36.70 86.50 35.00 94.50
4 Lead upto 4 km 71.40 71.40 44.60 105.00 42.50 114.80
5 Lead upto 5 km 84.00 84.00 52.50 123.50 50.00 135.10
for Every km beyond 5 km
6 upto 30 km 12.60 12.60 7.90 18.50 7.50 20.30
344
COM-LDLFT-2016-17
COM-LDLFT-3 C. LOADING AND UNLOADING CHARGES BY MANUAL MEANS (idle hire charges of trucks are not added)
Rubble/ size
Earth / Sand stone/ cut
/Gravel stone/ brick work
steel in
Sl No. Description of item Murrum/ / Surki/ Coarse cement in Rs/tonne Rs/1000
Rs./tonne
aggregate,Li No
Rs / cum me in
Rs/cum
1 2 3 4 5 6 7
1 Loading 17.30 37.80 62.40 74.80 52.00
2 Unloading 8.65 18.90 62.40 74.80 52.00
Note: The Lead Charges are inclusive of 13.615% Contractor Profit and Overhead charges
COM-LDLFT-4 D. LOADING AND UNLOADING CHARGES BY MANUAL MEANS (including idle hire charges of trucks )
Rubble/ size
Earth / Sand stone/ cut
/Gravel stone/ brick work
steel in
Sl No. Description of item Murrum/ / Surki/ Coarse cement in Rs/tonne Rs/1000
Rs./tonne
aggregate,Li No
Rs / cum me in
Rs/cum
1 2 3 4 5 6 7
1 Loading 111.00 129.90 163.70 176.00 219.10
2 Unloading 40.00 64.95 163.70 176.00 219.10
Note: The Lead Charges are inclusive of 13.615% Contractor Profit and Overhead charges
E. LOADING AND UNLOADING CHARGES BY MECHANICAL MEANS (including idle hire charges of trucks)
Rubble/ size
Earth / Sand stone/ cut
/Gravel stone/
COM-LDLFT-5 Sl No. Description of item Murrum/ / Surki/ Coarse
aggregate,Li
Rs / cum me in
Rs/cum
1 2 3 4
1 Loading 52.00 103.90
2 Unloading 15.90 15.90
Note: The Lead Charges are inclusive of 13.615% Contractor Profit and Overhead charges
DETAILED DATA
Note: The Lead Charges are inclusive of 13.615% Contractor Profit and Overhead charges
For the purpose of working out conveyance charges by head load the category of materials as
classified in ( I ) above are grouped together as under :
CATEGORY : Earth / Sand / Gravel / Murrum / Lime / Surki / Coarse aggregate /
Rubble stone / Size stone / Cut stone
In this group materials which are comperatively lighter and generally conveyed by head load
by light / heavy mazdoor are included. Method of conveyance, approximate weight per load
and time required to cover specified additional distance will be generally same
Therefore common data is considered for conveyance by head load for materials under this category.
CATEGORY : PCC slab / Shahabad stone slab / CC block / Laterite stone / BS slab / Wood
In this group the materials in moulded condition / cut to standard size which are heavier per
load compared to materials under Category above are included.
345
COM-LDLFT-2016-17
CATEGORY : PCC slab / Shahabad stone slab / CC block / Laterite stone / BS slab / Wood
Lead: Upto 50 m :
This is initial lead and cost is covered under item basic rate.
346
COM-LDLFT-2016-17
No. of trips per day for lead upto 100 m ( 8 x 60 / 1.5 ) 320
Quantity of material by head load per load 0.017 cum
Quantity of material by head load per day ( 320 x 0.017 ) say 5.5 cum
Deploy one mazdoor for every 50 m additional lead beyond initial lead.
Unit: 5.5 cum
Sl No. Description Unit Quantity Rate in Rs. Amount in Rs.
1 Mazdoor Day 1 350 350
Total Rs: 350
Contractor's profit and
overhead charges 13.615% 47.65
Total for materials under this Category 5.5 cum Rs: 397.65
Rate per cum Rs: 72.30
COM-DTL-LDLFT-2 B.( Lead) Conveyance charges for machinery per kilometer for transporting materials by tippers and trucks
excluding loading, unloading and idle hire charges of machinery.
347
COM-LDLFT-2016-17
348
COM-LDLFT-2016-17
CATEGORY : Cement/ Steel/ Pipes/ RCC poles/ AC & GI sheets/ Packed materials
349
COM-LDLFT-2016-17
CATEGORY : PCC slabs/ Shahabad slabs/ BS slabs/ CC & Laterite blocks/ Wood
350
COM-LDLFT-2016-17
CATEGORY : water
351
COM-LDLFT-2016-17
352
COM-LDLFT-2016-17
Rate Amount
Sl No. Description Unit Quantity in Rs. in Rs.
1 Truck 10 T charges Hour 0.4 414.10 165.64
Fuel charges Hour 0.4 299.90 119.96
2 Crew charges Hour 0.4 177.50 71.00
Total Rs: 356.60
Contractor's profit and
overhead charges 13.615% 48.55
Total for 3000 bricks Rs: 405.15
Rate per 1000 bricks 135.10
COM-DTL-LDLFT-3 C. LOADING AND UNLOADING CHARGES BY MANUAL MEANS (idle hire charges of trucks are not added)
MORD -data
1 Loading of Lime, Aggregate, Stone Boulder,
a) Loading Brick Aggregate, Kankar, Building Rubbish, Unit Quantity Rate Rs. Amount Rs.
Building Rubbish, Crushed Slag, Stone for Masonry
Work by manual means including a lead upto 30 m
Unit = cum
Taking output = 5.5 cum
Labour
Head Mazdoor day 0.02 400.00 8.00
Mazdoor day 0.5 350 175.00
Total in Rs. 183.00
contractor's profit and
overhead charges 13.615% 24.92
Rate per cum = Rs. 37.80
Amount
2 Loading of Earth, Sand, Moorum, Manure, Flyash Unit Quantity Rate Rs. Rs.
a) Loading by manual means including a lead upto 30 m
Unit = cum
Taking output = 5.5 cum
Labour
Head Mazdoor day 0.01 375.00 3.75
Mazdoor day 0.25 320 80.00
Total in Rs. 83.75
contractor's profit and
overhead charges 13.615% 11.40
Rate per cum = Rs. 17.30
3 Loading of Bricks by manual means Unit Quantity Rate Rs. Amount Rs.
a) Loading including a lead upto 30 m
Unit = 1000 Nos.
Taking output = 2000 Nos
a) Labour
Head Mazdoor day 0.01 400.00 4.00
Mazdoor day 0.25 350 87.50
Cost for 2000 Nos. = 91.50
contractor's profit and
overhead charges 13.615% 12.46
Rate per cum = Rs. 52.00
4 Loading of Cement by manual means Unit Quantity Rate Rs. Amount Rs.
353
COM-LDLFT-2016-17
b) Unloading100%
+ stacking
of loading charges I.e.,62.40
Rs.
6 Loading of Bricks - 1000 Nos (Regular sizes - Unit Quantity Rate Rs. Amount Rs.
a) Loading 225x140x70 mm) by manual means including
Unit = 1000 Nos.
Taking output = 2000 Nos.
a) Labour
head Mazdoor day 0.01 400.00 4
Mazdoor day 0.25 350.00 87.50
Cost for 2000 Nos. = 91.50
contractor's profit and
overhead charges 13.615% 12.46
Rate per 1000 Nos. = Rs. 52.00
COM-DTL-LDLFT-4 D. LOADING AND UNLOADING CHARGES BY MANUAL MEANS (including idle hire charges of trucks )
2 Loading of Earth, Sand, Moorum, Manure, Flyash Unit Quantity Rate Rs. Amount Rs.
a) Loading by manual means including a lead upto 30 m
Unit = cum
Taking output = 5.5 cum
Labour
Head Mazdoor day 0.01 400.00 4.00
Mazdoor day 0.25 350 87.50
b) Machinery
Truck 10t hour 0.5 891.50 445.75
Cost for 5.5 cum = 537.25
contractor's profit and
overhead charges 13.615% 73.15
Rate per cum = Rs. 111.00
b) UnloadingUnloading of Earth, Sand, Moorum, Manure, FlyashUnit Quantity Rate Rs. Amount Rs.
by manual means including a lead upto 30 m
Unit = cum
Taking output = 5.5 cum
a) Labour
Mate day 0.005 400.00 2.00
Mazdoor(unskilled) day 0.125 350 43.75
354
COM-LDLFT-2016-17
b) Machinery
Truck 10t hour 0.166 891.50 147.99
Cost for 5.5 cum = 193.74
contractor's profit and
overhead charges 13.615% 26.38
Rate per cum = Rs. 40.00
b) Unloading100%
+ stacking
of loading charges i.e.,219.10
Rs.
b) Unloading100%
+ stacking
of loading charges i.e.,163.70
Rs.
b) Unloading100%
+ stacking
of loading charges i.e.,176.00
Rs.
COM-DTL-LDLFT-5 E. LOADING AND UNLOADING CHARGES BY MECHANICAL MEANS (including idle hire charges of trucks)
355
COM-LDLFT-2016-17
FOR CATEGORY : Earth / Sand / Gravel / Murrum / Lime / Surki / Coarse aggregate /
Rubble stone / Size stone / Cut stone
Lift : ADDITIONAL LIFT CHARGES FOR each 1 METER LIFT BEYOND 3 M INITIAL LIFT
Lift : ADDITIONAL LIFT CHARGES FOR each 1 METER LIFT BEYOND 3 M INITIAL LIFT
356
COM-LDLFT-2016-17
357
Hire Charges- for the year 2016-17
358
Hire Charges- for the year 2016-17
359