Replacement of Lip Seal Gasket For Heat Exchanger
Replacement of Lip Seal Gasket For Heat Exchanger
Replacement of Lip Seal Gasket For Heat Exchanger
Page 1 of 10
Rev. 0
SECTION TITLE
1.0 PURPOSE
2.0 SCOPE
3.0 EQUIPMENT
4.0 REFERENCES
5.0 SAFETY PRECAUTIONS
5.1 PREPARATION
5.2 DURING SITE EXECUTION
5.3 SAFETY INSPECTIONS
6.0 RESPONSIBILITIES
7.0 QUALITY
8.0 TOOLS AND EQUIPMENT TO BE USED
9.0 DOCUMENT SUBMISSION
10.0 SITE EXECUTION
10.1 PREPARATION
10.2 PRE SHUTDOWN ACTIVITIES
10.3 EXECUTION OF WORK
11.0 HOUSEKEEPING
1.0 PURPOSE
The purpose of this work method statement is to describe in detail all required measures taken
in order to execute the job on TUBE BUNDLE REPLACEMENT WITH CUTTING &
WELDING OF LIP SEAL GASKET.
2.0 SCOPE
This document is applicable to all employees and contractors working for TUBE BUNDLE
REPLACEMENT WITH CUTTING & WELDING OF LIP SEAL GASKET under the control
of.
3.0 EQUIPMENT
Page 2 of 10
Rev. 0
4.0 REFERENCES
General Engineering Practices.
Equipment Drawings
Applicable procedure, if any.
JSA (Job Safety Analysis) should be discussed with all concerned persons and to be
followed strictly.
Rigging Plan to be approved from <COMPANAY NAME > before start any lifting
activities and to be followed strictly.
Page 3 of 10
Rev. 0
It shall be responsibility of the Supervisor to routinely inspect the physical areas under
their control in any welding works. This inspection shall include determining Equipment,
Rigging, supports, scaffolds and ladders are appropriately installed or use, and if the job
site is cleaned up after the days work.
6.0 RESPONSIBILITIES:
The Project Manger & In charge will be responsible to manage and direct project
execution activities and ensure efficient implementation of works in accordance with the
Project Specification and standards.
Project Engineers & Supervisors will executed the job as instructed by Project Incharge.
The QA/QC Representative of Al Muzain & <COMPANAY NAME > shall witness all
activities and tests performed and ensure that all works are carried out to <COMPANAY
NAME > satisfaction.
Supervisor shall monitor the execution of the works.
Foreman shall lead the work force during the execution of the works.
7.0 QUALITY
All the Quality related documents / Procedures shall be submitted and get it approved
from <COMPANAY NAME > Inspection before proceed to work,
Submission of weld map / location map identifying the welding work shall be prepared
by the QA/QC Engineer if required.
Submission of ITP (Inspection Test Plan) shall be prepared by the QA/QC Engineer
Before Installation of the new equipment QC Inspector should verify the new equipment
& Existing equipment mating flange gasket face.
The Quality department (QAQC representative) shall ensure that the alignment is done to
<COMPANAY NAME > satisfaction
The required materials shall be checked for conformance before use.
All the calibrated inspection tools to be used.
QC inspector co-ordinate with <COMPANAY NAME > inspector for all inspection and
NDT activates.
They shall be responsible to assure, monitor & control quality activities for the tube
bundle replacement work.
Observe the stage wise inspection as per the approved inspection and test plan (ITP) for
the job.
Page 4 of 10
Rev. 0
Get clearance from <COMPANAY NAME > representative(s) at site before proceeding
for the subsequent stages.
Inspection report shall be prepared and get it signed from <COMPANAY NAME >
10.1 PREPARATIONS
Submitted documents to be followed up and get approval. Revision will be done, if
required.
Site facility to be mobilized to the site allocated area.
Check and receive free issue materials as per requirement. In case materials have any
discrepancy refer materials list, same shall be informed to <COMPANAY NAME >.
Page 5 of 10
Rev. 0
Rearrange & Install alternate stud bolts sequentially at the uncut lip seal locations.
After finishing the cutting, Hold the channel head lifting lug (02 nos.) using chain block
& crane and remove the balance stud bolts.
Remove the channel head cover for inspection and cleaning. Cleaning by team.
Tube Sheet inspection and cleaning followed by inspection.
After inspection and cleaning, centering pin shall be inserted to the shell flange.
Channel cover shall be installed using Crane by team.
Page 6 of 10
Rev. 0
Page 7 of 10
Rev. 0
After finishing the cutting, Hold the channel head lifting lug (02 nos.) using chain block
& crane and remove the balance stud bolts.
Remove the channel head cover for inspection and cleaning. Cleaning by team.
Remove the Tube sheet bundle using bundle puller by team.
Perform grinding to cut the gasket from Joint no: - GS -01 (Reference drawing no: -
D0553-E6301A/B-D -002, Rev. 03).
Carefully remove the gasket from both side of the tube sheet.
Gasket faces of new tube sheet shall be cleaned and DPT to be done.
Visual inspection to be done for the removed gasket by inspection team.
Page 8 of 10
Rev. 0
Page 9 of 10
Rev. 0
After completing all welding at both side of tube sheet flange, DPT and inspection shall
be carried out.
100% of torqueing value shall be applied to the stud bolt.
Reinstall the Jack bolts.
Pneumatic test shall be done for the final lip seal weld joint by applying soap solution to
identify integrity of joint ( Pneumatic test pressure value provided by <COMPANAY
NAME >).
Reinstall the disconnected channel inlet and outlet line with new gasket followed by
inspection.
De-blinding shall be done followed by inspection and torqueing.
11.0 HOUSEKEEPING
Al Muzain shall perform the house keeping activities on daily basis as per plant safety standard
requirement.
Maintain cleanliness and orderly stocking of material & tools.
Pick up and dispose wastes & other debris to <COMPANAY NAME > yard or ware
house prior to leaving site area.
Store tools, equipment and unused materials properly store at the end of the workday.
Page 10 of 10