201 93wa 4150
201 93wa 4150
201 93wa 4150
WATERAID
Technical Handbook
0
Foreword to 3rd Edition
Engineers in the field may not have ready access to technical literature,
and may be faced with unforeseen problems which need a quick solution.
Suggestions as to content were sought in the latter part of 1985. Data and
notes were compiled, and a first edition issued in 1987. Following helpful
comment, some corrections and additions were made for the 2nd edition,
issued in 1988, with a supplement in 1990.
C/93
Section 1 - Civil Engineering
Divider
Divider
D/93
INDEX - GROUP 1
Group 1 - General
Gl * Introduction
G2 - Design Philosophy and Check List
G3 - Reference Books
G4 - Safety
G5 - Setting Out
G6 - Water Related Diseases
D/93
Introduction
This handbook is issued by Water Aid for the use of its field personnel.
Whilst every effort has been made to ensure accuracy, the possibility of
error cannot be discounted, and earliest possible notification of any
identified errors would be appreciated.
B/3/88 Gl
Design Philosophy and Check List
(iv) Schemes should be designed to give value for money but where
extra capacity can be included without significant extra cost then
this can be done (eg choice of the next larger size of pipe when the
theoretical pipe diameter needed is in between two standard
diameters).
(vi) In most cases the most immediate health benefit will arise from the
use of greater quantities of water. Designers should strive to make
this possible. It may also be desirable that water quality should be
improved. It is acceptable to use a questionable source untreated
provided that no new or existing user receives a lower quality of
water than before (see Feachem, McGarry and Mara "Water,
wastes & health in hot climates" Wiley 1977), but provision should
then be made to upgrade quality as soon as practicable. It is
suggested that the following check-list be applied to each new
scheme:
C/93 G2/1
Have you:
5 Allowed for growth in population over the life of the project and
taken into account other factors which may affect the final
population figure?
9 Made provision for extension where this can easily be done (eg
deepening of wells or the provision of extra tap-stands)?
C/93 G2/3
Reference Books
The following is a selection from the reference books held, those marked111
are recommended for consideration in a field library.
1. Water Supply
C/93 G3/1
*A Handbook of Gravity Flow Water Systems - Thomas D Jordan Jnr.
ITP1984
"Hand Dug Wells and Their Construction - S B Watt & M E Wood - ITP
2. Sanitation
C/93 G3/2
3. Water & Sanitation
C/93 G3/3
Where There is No Doctor - A Village Health Care Handbook
David Werner - TALC 1987
*Just Stir Gently: The Way to Mix Hygiene Education with Water Supply
& Sanitation - M T Boot - IRC
5. Personal Health
6. Building/Construction
C/93 G3/4
Appropriate Building Materials - a catalogue of potential solutions.
Roland Stutz & Kivan Mukerji - SKAT/ITP/GATE 1988
7. Training
8. Evaluation
9. Development General
10. Other
C/93 G3/5
Safety
Design
Construction
This will be largely a matter of common sense. The main hazard may well
be in excavation. Don't allow local labour to take unnecessary risks, and
don't take any yourself. Unless the ground is exceptionally firm, dry and
free from fissures, some simple shoring should be insisted on, for vertical-
sided excavations more than l.S m deep (see T14). Don't forget hazards
of foul or explosive gases in deep excavations, often arising from methane
or hydrogen sulphide held in the strata and accumulating in unventilated
spaces. Never enter a confined excavation more than 2 m deep on your
own, or allow other people to do so, and always have someone available
with a safety line on the surface. Hard hats, goggles, gloves and safety
harness should be indented for when considered necessary.
D/93 G4
Setting Out Procedures
(d) "safe" locations for setting out stations, temporary bench marks
and off-set pegs (ie avoid locations where pegs and bench marks
are likely to be disturbed)
D/93 G5
Water Related Diseases
B/93 G6/1
Water Related Diseases
E Cholera bacillus;
vibrio cholera
R
Diarrhoea
Dysentery see above
W
A
T Worms Depends on type nematodes faeces, flies
E of infecting ascaris unwashed hands,
R worm (whipworm, not wearing shoes,
tapeworm) not using latrines
C Impetigo bacteria
L contact with infected
E people, many people
A Scabies parasites living close together
N arthopods
E
D Lice
A. The bacteria already present in intestines (intestinal flora) will fight new bacteria. This is why babies
get diarrhoea often; they do not have a well developed intestinal flora.
Continued/
5
C. Hydrochloric acid in the stomach has enough strength to fight the
foreign organisms entering our digestive system. Different
3 organisms have different survival capacities against the HC1. The
w
number of germs required to cause the following diseases are:
2- Basic Data
Bl - Constants
B2 - Metric/Imperial/US Conversion
B3 - Strength and Weight of Materials
B4 - Soil Bearing Pressures
B5 - Water Demand
B6 - Water Quality
B7 - Water Resources
B8 - Roughness Factors
B9 - Transport Velocities
BIO - Labour Requirements
C/93
Constants
= 981 cm/sec2
P. (fr) ^ 3.14
* 2.72
* Note
D/93 Bl
Metric/Imperial/US Conversion
(Metric units are generally used in this handbook, but imperial retained
where they are traditional and familiar)
C/93 B2/1
Miscellaneous 1 force-de-cheval (metric horse-power)
= 0.986 HP (British) = 735 Watts
1C = 5_(F-32)
9
C/93 B2/2
Strength and Weight of Materials
Characteristics
The table gives very approximate guideline data. (See also Tl).
The wide variations of material quality do not need stressing. The factor
of safety used to determine the safe tensile and crushing strengths will
depend on the situation, the assessment of load, and the variability of the
material. It is usual to take higher factors (5 or 6) with timber than with
man-made materials of good quality.
Laterite
Laterites are useful as fill material and for low cost roads with light traffic.
Crushed laterite and lateritic gravel may be used for low-strength concrete.
C/93 B3/1
Specific Ultimate Ultimate Modules of
Material Gravity Tensile Strength Crushing Strength Elasticity
o lO'N/m1 T/in1 ltfN/m1 T/in* 10*N T
o
Cast Iron 7 90-150 6 to 10 620-770 40 to 50 80 8000
Steel 7.9 390-540 25 to 35 160 16000
Aluminium 2.7 80-140 5to9 55 5500
kN/m2 I/ft2
Alluvium, made ground 1 Vi
B/3/88 B4
Water Demand
Water demand varies considerably with social habit, ease of access, and
quality of water.
Individual countries may have their own design criteria and local enquiries
should be made.
> 2,500 m 5
250-2,500 m 15
<250m 15-35
The WaterAid internal note records that consumption soars if the source is
within 100 m., and falls dramatically if the distance exceeds 1 km (or 30
minutes travel return time), so that health benefits related to quantity will
not be derived by providing new sources 200 m or more distant if the
existing source is within 1 km.
B/93 B5/1
Gravity supplies will be used (and wasted) more than those depending
on hand pumps.
Piped suDDhes
Type of supply Approx. water usage
(litres/head/day)
Yard or single
household tap 75
Schools: Day 25
Boarding 45
Government Offices 30
Livestock: Horses 35
Cattle 40
Pigs 15
Sheep 12.5
100 Chickens 15
To put this into perspective, the water needed for agricultural purposes for
irrigation is of the order of 750 litres per kilo of grain grown and 1,500
litres per kilo of rice grown. For small scale manufacturing 100 litres of
water are required per kilo of paper made, 4 litres per kilo of bread baked
and 100 litres per kilo of steel made.
B/93 B5/2
Water Quality
Water easily collects all kinds of impurities which give it colour, odour,
taste and turbidity. These may be either of organic origin, derived from
decomposition of plants and animals and wastes, or inorganic origin such
as soils, minerals and metals. In inhabited areas water can also be
contaminated with pathogens and parasitic organisms.
WHO also advise that for coliform counts per ml of 10 to 300, the water
should be treated before use, and over 300 the source should be regarded
as "unacceptable" (but in practice there may be no option - see Design
Philosophy, G2)
C/93 B6/1
Guidelines for Potable Water Quality
Maximum 200 600 2.0 1.0 150 100 400 400 6.5-9.2
(There are of course very wide variations in surface and groundwater quality - the examples
quoted should not be regarded as 'typical'.)
Rainwater 2 3 - 0 2 1 - 4 5.6
(SE Asia)
Surface 7.2 10 1 0.6 5.9 0.27 19 0.02 7.42
water (Sudan)
g Ground- 14 5.9 - 0 4.7 - 22 52 -
3 water
Water Resources
1. That there will be ample and sustainable source of safe water at all
times.
2. If in doubt, look for long term records of rainfall and stream flow
or water table levels.
A/93 B7
Roughness Factors
In the past, various empirical formulae were used for pipe and channel
flow, each using an arbitrary roughness factor specific to particular
materials and conditions. Thus the popular Hazen Williams formula (see
Fl), used a coefficient ' C and the Manning formula for open channel flow
(see F3), a constant based on the earlier Kutter roughness coefficient 'K'.
Modern flow formulae all use a roughness factor 'k' having a dimension in
millimetres, which can be used for pipes running full , or part full, and for
open channels, and this is used in the Colebrook White formula which
forms the basis of the flowcharts in F l . lake particular care not to
confuse 'k' with 'K' and ' C and coefficients used in other empirical
formulae. The recommended 'k' values are:
C/93 B8/1
Dirty (Surface)
Material Clean Water'" Water Sewage'2'
Alkathene 0.003
Perspex
Note: (1) These values are for new pipes or channels with well-made
joints. Mis-aligned joints, rust, tuberculation, slime etc. result
in increased loss at head, and in design it is prudent to use
larger 'k'values that those tabulated to allow for deterioration
in service.
C/93 B8/2
Transport Velocities
Rising Mains
For clean water the rate of flow and hence velocity for the available head
or pressure in rising (force) mains can be calculated using Hazen
Williams', or Colebrook-White formula.(see Fl) For dirty water, use
Colebrook-White but choose a high 'k' value (see B8).
Settling
Velocity
(m/sec)
Pipe Dia.(mm) 150 300 600
Coarse sand
(up to 2.5 mm) 0.4 Pick up velocity 0.6 0.6 0.6
(m/sec)
Grit
If ft it
(2.5 to 5.0 mm) 1.5 1.2 1.5 1.8
C/93 B9/1
Open Channels
C/93 B9/2
Labour Requirements for Common Tasks
The following are very approximate and must be adapted for use in each
location.
B. Nepal
Excavation (shallow) m3 1.4
Excavation in rock m33 0.3-0.4
Back filling m 3
Plain concrete m3 0.14
Cement plastering (lcm) m2 2
Ferrocement (5cm) m2 0.3
Barbed wire fence m 6
Jointing HDPE pipes Item 10
Jointing GI pipes Item 7
C/93 B/10
INDEX - Group 3
Group 3 - Formulae
B/3/88
Clean Water Flow in Pipelines
General
The most accurate formula for general application over a wide range of
conditions is Colebrook-White. This is not however convenient for simple
calculations, and is usually presented in chart form. Three simplified
charts are attached, for values of the roughness coefficient 'k'
corresponding to very smooth; fairly smooth; and average, and are for
clean water only. (See B8.) If extensive pipeline design is undertaken, the
full series of charts should be obtained from QAG.
A simple formula suitable for clean water in pipes flowing full which gives
sufficiently accurate results for most applications is Hazen Williams.
Metric Imperial
Continued/
C/93 Fl/1
Values for 'C for use in the Hazen Williams formula (this varies with material and size)
n
3 Pipe Material Nominal Diameter
100 mm (4"! or less 300 mm (\2n ) 600 mm (24*1
The formula is most accurate for pipes larger than 100 mm, for velocities
over 1 m/sec, and for values of C over 100.
Note Remember to use the actual internal diameter of the pipe in a calculation
- it may differ significantly from the notional size.
Continued/
Q (I/sec) flowing full
Dia (mm)
k = 0003 mm
1A O
CM rf\
Oia (mm)
k = 0.015 mm
1
IS
The flow chart in Fig. Fl/2 may be used for galvanised pipe and Fig. Fl/1
for new plastic pipe. Alternatively, the chart in Fig. F1/4 can be used for
MDPE pipes Class B to BS: 1972.
Pressure losses in tapping the service pipe to the main, in stopcocks, ball
valves and bibcocks may be much more significant. Average values of
head loss (m.) at fittings are:
7.5 15 25
C/93 Fl/3
Nominal size (mm)-Approx.O.D
20 25 32 50 63
E
= :(
S " ': s;
7
7
s.
_^ *
=
L[ s^
0.01 02 0.4 1 2 5 10 50
Q0SQ1
ail/sec) flowing ful
C/93 F2
SUDDEN CONTRACTION SUDDEN ENLARGEMENT
MITRED JOINTS
a = 115 a = 0.45 a = 0.25 a = 0.07
P=63 P=22 P=13
=71 =ZA ^ \ =E^\
90 | I 60 \ \ 45 \ \ 30 \
BENDS (90) T-JUNCTIONS FOOT VALVES, STRAINERS
a = 2.5
_|L\a=1
3 = 125
I I pipe rad) (Da =0.35 p = 18
a=0.3p=15 (2)a = 1 p=50
Expressed as Ah or Equivalent pipe length 1= $ diameters, for
pipes of average roughness (i.e roughness
coefficient Vc C - O ? )
inergy Losses
in Pipe Fittings Fig F2/1
Open Channel Flow
i = hydraulic gradient x
c = J_ (metric units)
K
x This is the slope of the free water surface and has no relevance to the
pipe gradient in pressure systems.
C/93 F3
Weirs and Orifices
Orifice Discharge
Q =CdaV
Cd = Discharge coefficient
a Area of orifice
V - Velocity =u/5gh where h is the head
over the orifice centre.
Q = 0.315 Tan a T ^ g l P
2
0 is notch angle
or Q (cusecs) = 2.53h2 5
when h is in ft.
B/3/88 F4/1
Rectangular (sharp-edged) Weir Discharge (free discharge)
Q = 0.67 Cd b JTglP
b = width
Cd = 0.623 (b - 0.2rri
Q - 0.385 Cd b J2gh1-5
Submerged Weirs
(NB When measuring h do not forget to allow for the kinetic head of
the approach velocity. Remember to use consistent units within
each formula.)
B/3/88 F4/2
Bending Moments, Shear and Deflections
In all cases :
The moment, shear or deflection due to the self-weight of the beam must
be added to that due to the imposed load.
C/93 F5/1
Condition Max.BM End Reaction Max .Deflection
Tl - Pipe Materials
T2 - Pipe Laying and Jointing
T3 - Pipe Supports
T4 - Stream Gauging
T5 - Water Sampling and Analysis
T6 - Water Treatment
T7 - Piling
T8 - Timber Struts and Columns
T9 - Concrete
T10 - Corrosion of Concrete
Til - Water Pipelines - Design
T12 - Site Roads
T13 - Groundwater Development
A. General
B. Well-siting
C. Boreholes and Tube Wells
D. Screens and Gravel Packs
E. Hand^dug Wells
T14 - Shallow Excavations
T15 - Thrust Blocks
T16 - Shuttering (Formwork)
T17 - Sanitation
T18 - Handpumps
T19 - The Eductor Set (for Dewatering)
D/93
Pipe Materials
General
Apart from size and strength, the choice of pipe material depends on cost,
suitability for intended use, durability and availability.
Tables 2 and 3 set out some limitations of commonly available pipes.
Asbestos Cement pipes are included, as they may still be met in some
areas, but following recognition of the danger in handling this material it
should be avoided if possible, and is not advisable for potable water
supply.
Plastic Pipes
As Tables 2 and 3 show, there is a very wide, and increasing, variety of
plastic pipes designed for different purposes - plumbing, rainwater goods,
building drainage, service ducts, water supply, sewerage etc. Advantages
are light weight and resistance to corrosion. All are usually classed as
'flexible', although small pipes in some plastic materials are semi-rigid.
The availability in size of the more common types is shown on Table 3.
Composite pipes such as GRP and reinforced plastic mortar are available
in size up to 2m dia.
In general terms, uPVC pipes are cheap, more rigid than most others,
more temperature sensitive, and more easily damaged. MDPE balances
strength and toughness and is preferred for distribution and service pipes.
MDPE pipes below 63mm O.D. are usually designed for a 12 bar test
pressure; larger diameters for 10 or 6 bar. MDPE pipes up to 90mm O.D.
are available in 50, 100 or 150m coils, larger pipes in 4 or 6m lengths -
consider transport problems.
Colour Coding Pigments are used for identification and to protect against
U.V. degradation. In UK, blue is used for clean water, yellow for gas,
but black pipes are better for pipes above ground and exposed to sunlight.
C/93 Tl/2
Table 2 - Recommended Uses
Material Use
Sewage Potable Water Pressure Rigid Flexible
Clay 2.3 5 - -
Concrete 2.3 It - - -
Asbestos Cement 2.0 10 - - 25
Ductile Iron 7.2 12 7 400
Steel 7.9 12.5 - 20 500
uPVC 1.4 up to 60 70 70 50
Polypropylene 0.9 " " 120 110 300 6
GRP 2.0 " " 40 - - 250
Polyethylene:
LDPE 0.91 " "280 80 500 5
MDPE 0.93 " " 150 110 500 9
HDPE 0.94 " "200 90 500 9
Nylon 1.1 " " 150 130 - 50
Pitch Fibre 1.2 25
Notes (1) These properties are generally the values at 20C.
(2) There are wide ranges for each material; the figures quoted are
indicative, to give a comparison between materials. For accurate values refer where
possible to the manufacturer.
Pipe Laying and Jointing
Most pipework for Water Aid projects will be small diameter, flexible,
pipes, which are best laid in shallow trench. The depth will rarely be*
greater than that needed to avoid exposure by erosion or damage by
cultivation or grass fires, and in these circumstances the strength of
commercially available pipes will usually be adequate if laid with a
suitable surround (see Installation below), but see note T15 on thrust
blocks for pressure pipes. See also Tl 1 (pipeline design)
Failure of rigid and semi-rigid pipes can originate from rough handling to
and on site as well as over-loading, and care in transit, in store and
laying is rewarding. Slings should be used in handling and pipes stored on
even surfaces. Flexible and semi-rigid pipes need support to the whole
length of the barrel - see more detailed notes under 'Pipe Materials'.
Installation
It is vital to ensure that large stones, rock or timber do not cause local
stress to pipes under load, and all except small plastic pipes in trench are
best laid with a granular or selected soil surround (sandy gravel passing
30mm sieve is ideal). Above ground supports must be adequate to avoid
sag, provision made for expansion, and protection given from direct
sunlight. (See also separate technical note on Pipe Supports T3.) Some
plastics - particularly polypropylene - have been subject to vermin attack,
but uPVC and HDPE appear free from this problem.
Additional loads will be imposed where pipes cross vehicle tracks, and in
this and similar situations, thought needs to be given to the structural
strength at the pipe. For most situations, provide not less than 0.75 m
cover over the pipe and surround the pipe with selected material (sandy
gravel is ideal) containing no material larger than 30 mm. This is
particularly important with plastic pipes, which can be damaged by large,
sharp stones. Careful consolidation and reinstatement is necessary to
avoid 'wheel thump'.
C/93 T2/1
Pipe Failures
Joints
For small pipes, push fit or compression joints or solvent welding are
suitable. Solvent welding of larger pipes (over 50mm diameter) requires
careful technique in accordance with manufacturers' instructions, and
should be avoided if possible.
Butt Welding
Butt weld properly executed is as strong as the original pipe. There are
two ways of executing these joints namely:-
(i) The hand held heating plate where a disc of approx 125mm
diameter and 15mm thick on the end of a handle is heated in a
naked flame to 205 degrees centigrade. This is achieved by
marking the plate with a thermal crayon which changes colour at
the right temperature. A teflon bag is then placed over the plate to
prevent the pipe sticking and the pipe ends are pressed onto the
C/93 T2/2
plate until melt occurs when they are removed and pushed together
to form the joint. This method is suitable for jointing coils of
small diameter pipe in the bush.
These machines are not complex, are easy to use, and if properly
maintained will give a long and satisfactory service.
The machine is based on a 125mm chassis (liners can be used for 90mm,
63mm and 50mm pipes) complete with trimmer and heater plates and a
hydraulic hand pump. Cost (1993) is around 3000 plus transport. A
small 2.8kVA petrol driven generator is also required to power the
welding machine (budget cost of 750) The whole of this equipment can
be supplied as a package from Fusion Group pic.
Fusion Welding
When first introduced it was not reliable and more costly than other
comparable systems. It is however now a standard for the British Gas
industry and a Water Standard is in the course of being written. As a
result of its increased use and quality control combined with automated
production the cost of fusion fittings has considerably reduced and it is
now comparable with butt welding.
The fittings have sealed in the sockets the necessary heating wires which
have an electric current passed through them to generate the heat required
to fuse the fitting to the pipe.
C/93 T2/3
Operationally the pipe end is cleaned to remove dirt, grease and plastic
impurities and the fitting is then clamped onto the pipe. The fitting has
two terminals which are connected to a controller, current is then passed
through the built in wires for a preset period of time fusing the fitting to
the pipe, the joint is then left to cool and the clamp removed. The more
modern fittings have a set resistance which is measured by the controller
and this automatically sets the correct time for the fusion process.
The cost of the control box is in the region of 1000 (1993). A small
petrol driven generator is also required, and a series of clamps to hold the
fittings firmly onto the pipe during the fusion operation. The budget cost
for control box, generator and clamps is around 2000 (1993 prices).
Push Fit
This type of joint is very simple and only requires the end of the pipe to be
chamfered and then simply pushed into the socket of the fitting. It has a
standard "O" ring to hold against pressure and a clamp ring to hold the
fitting firmly on the pipe which can be released with a simple tool allowing
the fitting to be reused. The chamfer and extractor tools are simple and
inexpensive.
Mechanical
This type of joint has been widely used by WaterAid especially in Sierra
Leone where it was specified as a cheaper alternative to the Push Fit. The
types used have been made of plastic and have the same life span as the
pipes. The fitting contains sealing rings and clamp rings to prevent the
fitting parting under pressure. The only tools required are a set of stilson
wrenches.
Its advantage is that it is easy to remove the fitting and it can be reused
although perhaps with new sealing rings.
C/93 T2/4
Pipe Supports
Where practicable, pipes are best laid in shallow trench for protection.
pipes are laid above ground they need support. Points to watch are:
C/93 T3/1
(a) in some countries timber cradles may be an acceptable
alternative if durability can be assured;
C/93 T3/2
Metal strap Bolts to be at (east 100mm
(loose fitting) from the edge of the
cradle
-In-situ pillar
B/93 T4
Water Sampling and Analysis
(a) Conductivity
(b) Turbidity
(c) Chlorine residual
(d) Odour
C/93 T5/1
Field test kits are also available for most physical and chemical
characteristics of interest, and for bacteriological analysis, and the
manufacturers' instructions on them should be carefully followed.
(b) Turbidity There are no accurate simple field test methods, but a
rough indication can be obtained by fixing a small interior mirror to a
graduated rod, and lowering in full daylight until it cannot be seen. The
depth of immersion corresponds roughly to the silica scale of turbidity as
follows:
80 10 Suitable for
sand filtration
C/93 T5/2
(c) Chlorine Residual All field testing depends on the depth of
colour developed by adding a reagent, and is best measured by using a
suitable test kit. If this is not available, but DPD reagent (Diethyl-para-
phenylene diamine) can be obtained, as foil-wrapped tablets or in liquid
form, add 3-5 drops of reagent to a 5ml sample in a clean glass bottle.
The table below gives a rough and ready relationship:
C/93 T5/3
Water Treatment
Many surface waters need treating before potable use. Untreated water is
only suitable for domestic use if it comes from an unpolluted source (e.g. a
stream or lake upstream of inhabited areas) or if the user can be trusted to
use simple disinfection methods for water used for drinking or food
preparation. (But see comment in B6)
C/93 T6/1
It is possible that the alkalinity from new concrete will effectively sterilise
water stored in concrete tanks, but this is unreliable and should not be
depended upon.
Iron Removal
C/93 T6/2
Piling
Construction may involve both sheet piling, and simple timber piling, for
support to intakes and similar application. The above source reference
will be found a useful guide.
Some points of note are:
1. The driving efficiency is related to the ratio between the weight of
the hammer and of the pile.
2. The Hiley formula is a simple and popular method of calculating
the driving resistance.
It is: R = Whn
S+0.5C
where R = the driving resistance, related to the working load by
an appropriate factor of safety
W = the weight of the hammer
h = the fall of the hammer
S = the set per blow
C = the total elastic compression of the pile, dolly
and ground
n = the efficiency of the blow
[The same units should be used for R & W (e.g. Tonnes); and for h, S and
C (e.g. mm)]
For timber piles, driven with a drop hammer, n varies from about 0.5
when the weight of the hammer is equal to the weight of the pile, to 0.2
when the pile is six times the weight of the hammer.
For steel piles driven with a drop bammer,n will be between 0.55 and 0.23
for the same ratios.
The value of C is made up of the temporary compression of the pile head
and dolly, that of the pile itself, and that of the ground under the pile.
C/93 Tll\
For timber piles, C (mm) will vary from 2 + L
3
(where L is the length of the pile in metres) for easy driving, to 10 + L
for hard driving, with 8 + 2L as an average condition.
3
Comparable values for steel piles range from
2 + L through 6 + L to 8 + 2L.
4 2 4
3. Sets of less than 2 nun should be avoided for continuous driving -
the stress in the pile is too large.
4. Similarly, hammer drops should be less than 1 V& m.
C/93 T7/2
Timber Struts, Columns and Compression Members
Hardwood - 60 to 90 N/mm2
5. Calculate the effective length (Le). This depends on the end fixing
and varies from 0.7 x the actual length (L) for fixed ends, to 2L
when the ends are not restrained. Most struts are pinned at both
ends (i.e. restrained in position but not in angular direction) and
for this condition Le = L, and this is usually a safe assumption.
Note Use consistent units throughout, e.g. kg and mm; or T and ins.
C/93 T8/1
Concrete
Introduction
All engineers are aware of the ideal requirements for producing good
concrete: suitable materials well proportioned, thoroughly mixed and
compacted and adequately cured. In many developing countries these
conditions cannot be easily realised, and die following notes are intended
to guide on the points to watch in more difficult circumstances. Obviously
no risks should be taken with concrete which is used for structural
purposes, where orthodox design and construction methods should be
followed.
Materials
These should ideally be clean and well graded. Materials of near single
size produce harsh concrete, difficult to work and liable to be porous.
High organic or silt content is very undesirable. A simple test for grading
and for silt is to mix the sand with several volumes of water in a jar, and
allow to settle for two hours; the grading between coarse and fine particles
can easily be seen and the silt which settles on the top should not
be greater than 20% by volume. Very silty sand should be washed. Some
salt (sodium chloride) can be tolerated for unreinforced concrete, but high (
sulphate content is most undesirable - in desert countries, sulphates can
C/93 T9/1
migrate and crystallise on the surface and the sand should be taken from a
lower layer. Beach sands, including coral and shell sands, can be used,
but are often saline and must be taken from well above high water; they
are usually poorly graded. See note below on a method of testing the
suitability of sand.
rdi Cement
(e\ Water
C/93 T9/2
Similarly, in the absence of a laboratory to crush cubes the quality of
concrete can be judged by a surface scratch test using a shovel or pick to
determine the hardness of the concrete after three or four days - hardness
is closely related to strength, but soft surface laitance can be ignored.
Mixing
It is, of course, important that the ingredients should be in the right and
consistent proportions. This cannot be obtained by such elementary
methods as 'Use 40 shovelfuls to one bag of cement.'
Placing
Curing
Loss of water from the concrete in the first 24 hours after placing is very
harmful and the concrete should be covered, or at least shaded, for at least
this period. With large volumes of concrete the heat of hydration may
drive off some of the contained water and the aggregates should, if
feasible, be kept in the shade and washed with water before mixing. Weak
concrete is less susceptible to this difficulty than strong concrete. Drying
conditions on the surface from exposure to sun or strong winds will also
lead to evaporation and loss of strength.
C/93 T9/3
Strength
9 7.5
8 10
7 15
6 20
5 25
Joints
Great care is needed in jointing new concrete to old (ie past the initial set).
The old concrete must be clean, dust-free, and scabbled to remove laitance
and roughen the surface. A 5mm layer of 1:1 cement mortar may be
placed before pouring the new concrete.
Temperature
C/93 T9/4
Reinforcement
Fibrous materials are useful, but note that asbestos fibres present a health
risk, and glass fibres must be of special quality as conventional glass is
attacked by the alkali in the cement. Chopped polypropylene string is
probably the most suitable material likely to be available.
Corrosion
Formwork
See T16.
(b) has more reinforcement (4 to 8%) in the form of wire mesh expanded
metal, or closely-spaced small wires distributed uniformly in both
directions;
(c) is made with a rich Portland cement mortar (sand/cement ratio 1.5 to
2.5, water/cement ratio 0.35 to 0.5, all by weight), without coarse
aggregate (use clean sand 2mm and uniform grading).
Ferrocement can be used for small tanks and slabs, to any shape without
formwork. It has a high tensile strength-to-weight ratio, and good
cracking behaviour. Galvanised wire may give problems due to reaction
with the alkaline cement.
C/93 T9/5
Ferrocement can be used for small tanks and slabs, to any shape without
formwork. It has a high tensile strength-to-weight ratio, and good
cracking behaviour. Galvanised wire may give problems due to reaction
with the alkaline cement.
Ferro-cement has been adapted for the construction of simple water tanks
using wire-reinforced mortar. These are commonly referred to as 'Ferro-
cement Water Tanks' and a design note (D5) under this heading is included
in Group 5; they differ from conventional ferro-cement in that wire is used
mainly for stress distribution, and is often less than would be needed to
carry the full tensile loads.
C/93 T9/6
Corrosion of Concrete
The most common forms of attack on Portland cement concrete are from
acids or sulphates. Acidic conditions may occur naturally in peats and |
other soils with high organic content, and protective measures are required
in the pH is less than 4.5. Many industrial wastes, especially from
agriculture of mines, are acidic. Sulphates are often found in groundwater
and if the concentration is in excess of about 1000 mg/l SO4 , protection is
necessary.
In general terms the better the quality of the concrete the higher the
resistance to all forms of attack. The following table shows some simple
protective measures.
Externally
A/12/86 T10/1
Method Degree of Protection
Internally
A/12/86 T10/2
Water Pipelines - Design
These notes reflect field experience:
1. Most water pipelines function as pressure pipes. They do not
need to be of constant diameter throughout, although normal
economic design would seek to keep a generally uniform velocity.
3. When screwed couplings are used (as with galvanised steel pipes)
provide screwed unions at key points and at intervals of say 300 m
to enable pipes to be removed without difficulty.
C/93 Tll/1
8. Ease of access to key points is important for maintenance and
control; measures should be taken to minimise accidental or
deliberate damage to the pipeline.
9. Provide permanent markers (eg concrete) at key points, junctions
and changes of direction to allow pipelines to be located.
10. Pipes in gravity schemes will often need to cross streams or rivers.
If these are shallow it is preferable to lay the pipe under the stream
bed, but ensure that it is well below scour level, or protected with
boulders etc.
C/93 Tll/2
reduction valves are expensive and difficult to maintain, and a
simple break-pressure chamber is preferable. This uses a float-
operated valve in a open chamber, similar to a W.C cistern ,
provided with a drain/washout and an overflow. This can also be
used as regulating reservoir. In some circumstances, a simple vent
pipe will serve the purpose, but the outflow pipe needs to have
more capacity than the in flow, to ensure that there is no outflow
from the vent.
12. Nepal practice is to keep the design velocity to 0.7 and 3m/sec; to
provide washouts at lkm intervals; and to allow a 'design length'
of 1.15 times the survey length.
13. Regulating reservoirs can be used to reduce pipe sizes, and avoid
interruption in supply when the source yield is less than peak
demand. In Nepal, they are sized at 0.37 daily demand, for
complete regulation, down to 0.1 d.d. to regulate flows to twice
the daily demand. In Uganda, 3 to 4 1/hd has been found useful.
C/93 Tll/3
Site Roads
Road design is not likely to fall into WaterAid activity, but occasionally it
may be necessary to construct short lengths of roads suitable for light
traffic to serve treatment, storage or other sites.
(a) The road material must spread the wheel load to limit the pressure
on the subsoil to within an acceptable limit.
(c) The subsoil must be kept as dry as feasible by good side drainage.
Suitable material for the road base should not contain more than 25% of
The material (passing No. 200 sieve) or particles larger than about 40mm.
The material should have a Liquid Limit less than about 30, and a
Plasticity Index less than about IS. Most laterite materials (see B3) are
suitable. (The Liquid Limit (LL) is the minimum moisture content at
which the soil will flow under its own weight; the Plastic Limit (PL) is the
minimum moisture content at which the soil can be rolled into a thread
0.125 in. diameter without breaking; and the Plasticity Index (PI) is the
difference between LL and PL. A soils laboratory is needed to determine
these values, but typically a sandy loam has an LL of 25 and a PI of 10;
and clays have LL between 55 and 75, and PI between 30 and 40.)
A/12/86 T12
(metres)
A. General
(1>
Groundwater does not flow in underground streams (except karstic
areas). It is present in pores and fractures in the soils and rocks
and moves excruciatingly slowly under gravity towards points of
discharge - river beds, etc. At these points the flow may be
concentrated in zones of higher permeability (fractures in rock,
natural pipes in weathered material) producing an illusion of a
linear stream discharging as a spring. Where permeabilities
remain the same throughout the system there is a continuous line
of seepage, e.g. along dambo0* or vlei3 floors or around the
edge of wetlands. Either way a point of discharge defines the
inter-section of the 'water table' with the surface, often due to an
underlying impermeable (clay) layer.
The 'water table' tends to follow the contours of the landscape, only it is
more subdued, being closest to the surface near valleys and deepest on the
top of ridges (Fig.T13/l). If there are any wells/boreholes in an area, by
measuring the rest water level and combining this with known points of
discharge, it may be possible to 'contour' the water table and use this to
predict water levels in a new well.
D/93 T13/1
.Ground surface
Water table
Rock surface
It should be at least 50m from pit latrines and cattle pens and protected
from waterlogging, surface run off and soil erosion.
C/93 T13/2
o Areas of seasonal waterlogging show up as darker patches in aerial
photographs. On the ground the change in vegetation may be quite
subtle and difficult to spot. The presence of low grey anthills may
indicate a water table close to the surface. Wells should be sited i
upslope from the edge of the waterlogged area.
These can be constructed using simple hand held drilling equipment e.g.
Vonder rig. This is possible in areas of deeply weathered bedrock or
unconsolidated sediments.
C/93 T13/3
a Fault Zone b. Dyke
c Inselberg
d Behind Spring
+ + + + + + + +
e Break in Slope
The top of the casing should be sealed with grout (see Fig.T13/3) the
bottom of the casing should be screened to allow water to enter and keep
aquifer particles out. The well should be 'developed' to pull all the fines {
into the well and remove them before the well is fitted with a permanent
pump (this also applies to gravel packed wells). This minimises siltation
and the damage caused by 'pumping sand'. The simplest method of
development is 'rawhiding' - over pump the well, stop and allow the water
level to recover and repeat until the water is clear.
The screen's aperture size depends on the size of the particles surrounding
it. This can be increased by adding an artificial gravel pack and is
necessary in silts and fine sands. (Fig.Tl3/4) 'Gravel packs' can be
uniform or graded within narrow limits. The mean diameter of the
particles should be 4 or 5 times that of particles in the aquifer. A
minimum annular space of 50mm should exist before a 'gravel pack' can
be emplaced. Some commercial screens come with a prebonded gravel
pack or wrapped with various configurations of mesh. This is more (
expensive than a loose pack.
C/93 T13/4
-Grout 1
? Sanitary seal
- d a y backfill J
Plain casing
Vfeter table
Bottom cap
X
Too much gravel causes
a sand lock pulling out
permanent plastic casing
with temporary drilling casing.
300mm
40mm
300mm
40mm [
Slot
300 mm
20 mm 20mm spine
Local screens can be made on site from the same material used for casing.
PVC pipe can be slotted if labour is available using a hacksaw (blade lmm
or less). Use Class 10 PVC.
Cut three rows of slots, each slot lcm apart in blocks 30cm. Leave a 4cm
gap before starting the next block. Leave a vertical spine of about 2cms
between adjacent rows. (Fig.T13/6)
For steel pipes, drilled holes or torch slots can be used to produce a 'poor
screen', which can be improved by wrapping with lmm mesh.
D/93 T13/5
the pump break down, they are thus more reliable. However they take
longer to construct and are more expensive. Of all the technologies which
WaterAid uses, they are potentially the most hazardous. (See Safety, G4)
Design All programmes use a similar basic design (see Fig. T13/7). The
common features are:
Total depths range from about 10m to some as deep a 20m deep in Ghana.
Wells are dug into the water table to that depth which produces a sufficient
yield for toe intended number of users, normally 250*300, that number
which can reasonably use a hand-pump. Each programme has developed
its own guidelines on how far this should be, for example the rule of
thumb in The Gambia was 3m. (It is important that this relates to the
lowest water table in the dry season, and provision made for sinking
deeper should die water table drop in the future).
Well Digging: Wells can be dug by the users, by skilled project staff or
by a combination of the two. With the exception of The Gambia where
there is a tradition of paid well-diggers, wells dug by the users; this keeps
the costs down and is the users' major contribution, but use a plumb line to
keep the well vertical, and watch the safety aspect. In most programmes
communities dig their well with only a few supervising visits from the
project staff until the water table has been reached. Lining is normally
carried out by skilled project staff, although in Ghana local masons living
in the communities lay concrete lining blocks.
D/93 T13/6
Cov/er
Well
Well Digging and lining: The principle well digging and lining methods
include:
Digging and lining in-situ in short lifts will deal with most ground
conditions and is safe in that only short lengths of well are unsupported at
any one time, but is time consuming and expensive.
Digging inside caisson rings is quicker since concrete takes place at the
surface and the rings can be stored ready for use. It is safe in that the
ground is always supported. However, the rings are heavy so that
substantial lifting equipment is required. Some skill is also needed to
ensure that the rings are sunk vertically. In some soils, the rings must be
tied together so that they do not part company.
Soils in Ghana and Uganda are such that it may be safe to dig to the water
table without supporting the sides of the well. The wells are then lined
with the cheapest appropriate material. Where it can be practised safely,
this method is the quickest and cheapest.
D/93 T13/7
Well Deepening: One of the advantages of hand- dug wells over boreholes
is that as if the water table drops the well can be deepened to maintain the
supply of water. This can be facilitated by the use of smaller diameter
caisson rings which can move relative to the fixed, permanent lining.
Water lifting Devices: Most wells are fitted with hand-pumps (see T18
on choice of pump). If using a pump, there is little possibility of
contamination in use. Some communities in the Upper East region of
Ghana cannot afford to maintain a pump. They buy single collapsible
rubber bucket which is kept by the well on a post and is the only bucket
allowed down the well.
The slab can be cast on the ground, with a ring of bricks if timber
formwork is not available; it can be cast in three sections to make it easier
to handle.
Yield: Where well storage is negligible and the yield is constant, the rate
of drawdown is greatest immediately after pumping starts and falls off
exponentially approaching an asymptote and steady state condition, when
pumping stops, the recovery curve should be a mirror image. (Fig.T13/9).
Therefore:
3. The radius of the cone influence expands with time, not with the
rate of pumping. The rate at which it expands depends on the
transmissivity (permeability x thickness of aquifer).
D/93 T13/8
Concrete slab Closed with
around the concrete cover
well
Closed lining to
prevent water from
the top aquifer
entering the well
Porous lining
below the water
level
Storage capacity
of at least 3m3
F Geophysics
Geophysical methods are often used in large scale initial surveys. They
require specialist input and the cost is relatively high - if the groundwater
is close to the surface, hand-dug wells are better and cheaper. Basically
they help to locate rock surfaces rather than water table level.
D/93 T13/9
Rest Water
Level
DRAWDOWN
1 *
Water level
Steady State Q-
TIME -~
PUMPING
Rest Water
Level
Steady State
TIME -
RECOVERY
Well Drawdown
and Recovery Fig T13/9
Shallow Excavations
This note gives guidance on excavation with vertical or battered sides for
depths up to about 3 m. The Reports cited above give more detailed
information and advice on excavations of up to 6 m depth. Still deeper
excavations should always be designed and supervised by competent and
experienced engineers.
1. Ground Types
These depend on many factors, including the type and condition of ground,
the presence of surface or groundwater, surcharge loading, and the time
the excavation is left open. Slopes indicated in the following table offer a
rough guide. They assume that the excavation is not open for more than
14 days, and that there is no surcharge and no hazard to adjacent
structures. Local conditions, such as Assuring or running sand, are
important and should be taken into account. (See Table 2).
For trenches, etc., less than 1.2 m deep, support is only required as
necessary to keep the excavations open. For trenches between 1.2 and 3 m
deep, timber sheeting should be used except in unfractured rock. Close
sheeting should always be used for gravels, sand, silt, soft clay and highly
compressible peat. Hit and miss sheeting can be used for firm clay and for
peat of low compressibility. Sheeting should be toed in at the formation
level and walings spaced at 1 to 1.5 m centres. Examples of suitable
waling and strut, assuming good quality softwood, are given in Table 3.
C/93 T14/1
Walings must be supported by hangers or puncheons, and struts by Up
blocks. Sheeting should be wedged tight against the walings after placing
the struts.
4. Groundwater Control
i) those that stop surface water from entering the excavation, e.g.
cut-off ditches, low height embankments.
ii) those that allow water to flow into the excavation and be pumped
out from sumps and ditches
iv) those that stop the groundwater entering the excavation by some
form of cut-off, such as sheet piling
The pros and cons of the more usual methods are summarised in Table 4.
C/93 T14/2
Tablet
Dry Wet
2.5 0.9 200 x 100 150 x75 150 x 100 150 x 150
3.0 0.9 225 x 150 150 x75 150 x 100 150 x 150
S Watt tin
n
Table 4
Pumping out tests from a well observing the steady state water level in
radial observation boreholes can be used to determine the coefficient
permeability in situ.
Q - k (H2 -h)
log e R
C/93 T14/7
TbbteS
Coefficients of Permeability
60
n
5
-Bible 6
1 9 30 95
2 19 60 190
3 28 90 285
4 38 120 379
5 47 ISO 474
7. Well points
Well points are essentially a series of shallow boreholes with 0.5-1 m long
screens on suction tubes of about SO nun dia. connected to a common
suction pipe. They are normally installed by jetting and in fine or sandy
soils a sand filter pack round the screen is desirable. Experience in laying
out and installing well points is desirable, but details of equipment and
installation can be obtained from wellpoint system manufacturers.
C/93 T14/10
9. Delivery Pipes
C/93 T14/11
Open * c h or stone-
filed agricultural
type drain
TJSump
(c) Sump Drainage
Note-
In impermeable stratum or if water table high, sump
will need to be pumped dry. If water table is below
formation in permeable stratum extend sump into
permeable layer for gravity drainage.
wSurface Water
Control Methods Fig T14
7. Well points
Well points are essentially a series of shallow boreholes with 0.5-1 m long
screens on suction tubes of about 50 mm dia. connected to a common
suction pipe. They are normally installed by jetting and in fine or sandy
soils a sand filter pack round the screen is desirable. Experience in laying
out and installing well points is desirable, but details of equipment and
installation can be obtained from wellpoint system manufacturers.
C/93 T14/12
9. Delivery Pipes
C/93 T14/13
Thrust Blocks
Calculation
Methods of Restraint
With buried pipelines the passive restraint of the soil, and the friction of
the ground round the pipes may be sufficient, but if in any doubt, use
concrete thrust blocks as shown in Fig.TIS, to increase the bearing area
and transmit forces to undisturbed ground.
A/8/88 T15/1
Joint Restraint
Even if the friction and passive support is judged adequate, there will be
some movement of the joints before the full resistance is developed
(depending on the nature of the ground). Some method of joint restraint
may then be necessary.
A/8/88 T15/2
Anchor block at gate valve
utilising puddle flange pipe.
Anchor block at taper reducer.
Anchor block at 45 bend
Anchor block at 90 bend.
Anchor block at blank end.
Anchor block at equal tee.
Typical Arrangement of
Concrete Anchor Blocks
used in conjunction with
P.V.C. pipework incorporating
rubber ring mechanical
joints when buried. Fig T15
Shuttering (Formwork)
Loading
Many factors affect the pressure on theformworkduring casting - the
nature of the concrete, the rate and method of placing, the method of
compaction, and the floor slope and depth of the cast section. The
maximum pressure is often less than the pressure which would be exerted
if the concrete behaved as a fluid.
e
(Ve$ure
urc
A/3/88 T16/1
A full discussion of this subject is contained in CIRIA Report 108
(Concrete Pressure on Formwork) 1985, but for field use using normal
Portland Cement concrete the approximate loading in Table 1 may suffice.
Access
Tall shutters will create access problems. Best to keep platforms, etc.
independent, but if they are attached to the formwork, remember to allow
for the weight of the people who will use them!
Striking
The time that should be allowed before formwork can safely be removed
depends on a variety of factors including the nature and load on the cast
section, the concrete mix, and the temperature, and is fully discussed in
CIRIA Report 73 ('Fonnwork Striking Times Method of Assessment',
1987). However, safe rules of thumb striking times are contained in
BS:811 of which Table 2 is an abstract.
Removal
A/3/88 T16/2
Tkble 1 Concrete Pressures on Formwork
1 10
2 45 50 50
3 55 65 75 75 75 75
4 65 70 85 85 100 100
2 40 45 50
10 3 45 55 70 65 75 75
4 50 60 75 75 90 100
35 45 50
15 40 50 65 60 75 75
45 50 70 65 85 95
A/3/88 T16/3
Table 2 - Minimum period before striking formwork (good quality
concrete made with ordinary Portland cement)
Support
Formwork can be braced end to end or supported by struts etc. externally,
or for wall sections supported by wire or bolt ties running through the
concrete. Ties can leave a water path through the wall and may corrode.
There are proprietary tie systems which avoid this problem, but these are
unlikely to be available and if wire ties are used the wire should be cut
back an inch or so from the face and die hole plugged with cement mortar:
if metal bolts are used they should be sleeved with plastic or cardboard,
allowing them to be withdrawn: plastic or cardboard should be removed
for at least an inch from the face, and the hole plugged.
/VH/3/88 T1674
Sanitation
A wide range of designs are available; all require care and attention to
detail during construction, use and maintenance. No latrine is ideal for all
situations and for all uses. The major options of latrine technologies are
sketched in Figure T17/1. Any material can be used. Those locally
available may have the shortest life, but will be more easy to replace.
Siting
The main reason for siting latrines well away from kitchen or living
quarters is smell nuisance, which can be controlled to some extent by good
ventilation and maintenance. The risk of aerial transmission of bacteria
and viruses is much less than the risk of poor personal and domestic
hygiene.
B/93 T17/1
vr (V(P)
Pit
\ \
\
\
Pour
pit")
Bas ic
b) the nearest well or borehole be at least 10 metres away if there is 4
metres of fine soil below the base of the pit, and up to SO metres
distant if the pit is close to the groundwater level, or if the stratum
is very porous or of fissured rock.
General Guidelines
Pits for latrines should be lined where the soil is unstable. Suitable linings
can be made from concrete, bricks, bamboo reinforced cement, timber etc.
The capacity of the pit should be calculated on the basis of 0.06 cu. metres
of sludge per person, per year where solids are used for anal cleansing or
0.04 where water is used. Composted sludge can be safely used as a soil
conditioner after standing for one year. Where it is locally unacceptable to
re-use sludge, full pits can be planted with fruit trees.
Superstructures can be built in any style or design to suit the user, except
for VIP latrines, where the provision of plenty of air flow and exclusion of
light is essential. Avoid constructing solid, permanent structures over
lined pits unless there is a removable cover for compost removal. Slabs
are the most critical part of all latrines and should be close-fitting to the
walls of the pit to isolate excreta from the environment.
Squatting holes can be made in a variety of shapes to suit the users, the
hole should be large enough to prevent fouling, but not so large that
children can fall down it. Footrests can be placed on either side, close
enough together for children to be able to use it. Typical dimensions are
shown in Figure T17/2. Covers for squatting holes can be made of wood
or other material, as available, and should be well-fitting to avoid fly
nuisance.
B/93 T17/2
Note
Footrest
Minimum 1m
PLAN
1
8mm reinforcement
bars
/ Hole Footrest
1 1 mnffH""^*"i
SECTION 1
Squatting Slab Fig
Hygiene
These are the cheapest latrines and can usually be made entirely out of
locally available materials. They can be smelly and fly ridden, especially
if they are too shallow, and should ideally be 3m deep and are usually 1 -
1.2m in diameter for ease of digging. A latrine of this size should last a
family of 10 people for up to 7 years. If the water table is high, or if there
is hard rock near the surface, it may be possible to mound the soil up to
give additional depth.
Slabs to cover the pit can be made of timber or thick bamboo and sealed
with mud mortar, but such slabs may have a life of less than 3 years and
are difficult to clean. A better solution is a simple concrete slab which can
be moved to a new pit when the original pit becomes full or unusable. A
flat concrete slab spanning a 1.2m diameter pit will need some simple bar
or mesh reinforcement, and will need to be 50 to 75mm thick. An
alternative is a dome shaped slab (Figure T7/4) unreinforced except for a
single 8mm circumferential bar to prevent damage when handling, cast on
a mound of earth with a circular former (more easily said than done!);
slabs of this size will weigh upwards of 275 kg. A satisfactory solution is
plaster the or pave the latrine floor or the ground around the pit - this helps
cleanliness but of course does nothing to control flies or odour, and is less
durable. A further alternative is the 'sanplat' - a small (0.6m3),
light,portable concrete slab sitting on a timber floor, which helps
cleanliness but has obvious limitations.
B/93 T17/3
Soap
^. T 17/3
SUb rotnj be
k-
Domed
. T17/4-
Squatting holes must be fitted with a lid to prevent access by flies. Odour
can be controlled by keeping the slab clean and throwing ash or similar
material down the squatting hole onto the sludge. A support lining may be
necessary, depending on the strata, and can be made of any available local
material, with open joints or similar arrangements to allow liquid to soak
into the adjacent soil. If the pit is lined, or in good soil, it may be
possible, when the pit is becoming full, to leave the sludge to compost for
12 months and then dig it out and reuse the pit. Alternatively a new pit
must be used.
Borehole latrines can be quickly constructed with a hand auger and are
especially useful where a quick sanitation solution is essential and where
people are likely to move around regularly, but the small diameter of the
hole means that it is likely to foul, block and fill quickly.
These have been designed to reduce smell by drawing odour away from
the squatting slab and to discourage flies and mosquitoes. They are more
expensive and must be regarded as more permanent, but are appropriate
where people are more prosperous and where the quality of construction
can be controlled. Ventilation is provided by a vent pipe with fly proof
netting. Wind blowing across the top of the vent pipe causes air to move
upwards, but when there is no wind, air in the vent pipe is moved upwards
when it is heated by the sun. The interior of the superstructure must be
kept relatively dark so that flies do not come up through the squatting
hole. Details of the design are therefore important and these will be found
in D15 in the Outline Design Section.
Pour flush (water seal) latrines are appropriate where people cleanse
themselves with water after excreting. Construction is more costly and
complex than a simple pit latrine and a reliable source of water in needed
for flushing purposes. The latrine hut can be sited directly over the pit, or
the pit can be offset, which is an advantage in that when the pit is full a
new one can be dug near it without removing the super structure. The
water seal pan can be moulded out of cement plaster, or plastic, glass fibre
or ceramic materials. The smoother the finish and smaller the water seal,
the less water is needed for flushing. D14 in the Outline Design Section
shows the details of an Offset Pit Pour Flush Latrine.
B/93 T17/4
Handpumps
These brief notes are intended to assist project staff and engineers in the
field to assess the type of handpump most suited to their requirements.
1. Type of Pump
The type of pumps commonly used can be classified in accordance with the
engineering principle of operation:
a) Suction Pumps
The pump rod operates inside the rising main and incorporates a
plunger which is pulled up and pushed down by hand, moving
within a cylinder at the bottom. At the same time, a foot valve in
the cylinder closes to retain the water. On the upstroke, the
plunger flat valve closes, and the bottom front valve opens.
A/93 T18/1
d) Progressive Cavity Pumps
A hand turning mechanism at the top of the well rotates the pump
rod turning a rotor in the cylinder at the bottom of the rising main,
forcing the water upwards. A foot valve may not be required.
e) Diaphragm Pumps
The solar pump is only now being developed fully for commercial
use and should be available in 1993. The concept is relatively
simple, alternatively using solar rays to heat and gasify a fluid
which is then cooled and refluidised. The associated change in
volumes is utilised to continually change the volume of oil inside a
flexible bag in a fixed container filled with water, developing a
negative pressure which lifts the column of water in the rising
main.
A/93 T18/2
The VLOM Concept
Advisers faced with pump selection should put some weight on this
concept. A pump which breaks down monthly but can be repaired
in a day using local labour is preferable to one breaking down once
a year but requiring a month before imported replacement parts
and skilled technicians are available to carry out the repairs.
Depth of water table will affect choice of pump. The World Bank
define shallow wells as being up to 12m to steady water level,
intermediate between 12m and 25m and deep between 25m and
45m.
A/93 T18/3
a) Shallow Wells
For the shallower depths in this range, open wells with bucket and
windlass are an option, as are suction pumps. Both are cheap to
install and service but are liable to pollution unless care is taken.
The direct action type is very suitable and pollution free but can be
tiring to operate at depth, producing less water. Reciprocating
action pumps are also used in this range but some designs use a
chain mechanism to lift the pump rod, which for shallow wells is
not heavy enough to drop quickly enough on the down stroke,
(e.g. India Mk II)
4. WaterAid Experience
(ii) Afridev
A/93 T18/4
(iii) Zimbabwe Bush Pump
A/93 T18/5
The Eductor Set (for Well Dewatering)
The clearances in the Eductor usually exceed 10mm and the unit is fitted
with a ball valve so that water is retained in the system after priming.
They are useful for suction lifts up to 50m, beyond this efficiency tends to
fall away. At best they are less efficient than borehole pumps but are
useful for test purposes, or for lifting silt-laden water.
A/93 T19
CoXica\ \ M
(return
Oich*-r<jc
i.t.
A
and.
vi e f
ic^ T\9
INDEX - GROUP 5
D/93
Spring Development and Protection
All springs have their own characteristics, so this general advice must be
adapted to the circumstances. The primary aims are to protect the
catchment area, collect water to a central point and provide collection
facilities easy to maintain and to keep clean. A secondary aim may be to
provide storage. Obviously it is wise to check the minimum flow in dry
season and the year-to-year reliability of the spring, by reference to
rainfall and water-table levels, and local knowledge.
Catchment Protection
B/93 Dl/1
C aXc)\ m e
Development
Collection Structure
This will have to suit the particular circumstances and might include:
In all instances provide an overflow, ensure good access and pave and
drain floor below the delivery pipes.
B/93 Dl/2
Removable cover slanted
to deflect rainwater
Tamped soil
Concrete apron
Water bearing l e v e l ~ :
. If
Dl/5
Intakes for Ponds
These are ideas for simple intakes from ponds and other bodies of still
water. The object is to take water from a clear area not too near the top or
bottom and well away from the bank. Sometimes two intakes are helpful
to allow a choice to suit varying circumstances.
B/93 D2/1
Pump weU-H
Anchors
Pump
Low level
Pump well|
Strainer
Note : Direct coupled pumps can be used if self- priming
and suction head is not too great.
Plug or cap
200mm
B. Infiltration Gallery.
The yield of riverside wells can be increased if necessary by
collecting pipes parallel to the river bank discharging into the well
(Fig.D3/2). The infiltration pipes should be laid 1 m below the
lowest water table, graded to the well, and surrounded with gravel
or broken stone. Use perforated or open-jointed pipes. If the
stream is seasonal, it may be practicable to lay infiltration pipes
under the steam bed at a depth of 0.3 to 0.5 m and filled with
gravel, graded from coarse (150 mm) next to the pipe to fine
(25 mm) carried up to the stream bed; this will only be successful
on stable stretches not subject to accretion or scour. Double-
walled, gravel packed, perforated or slotted pipes buried in
stable sand bars may also be suitable, and could be connected
direct to the pump suction, or discharge into a river-bank wet-well
if pumping is intermittent.
C. Gravity Intake.
If the stream bed and bank are stable and the lowest level
sufficient, a direct intake can be used, having an intake pipe with
strainer (see Intakes for Ponds, D2) protected by concrete or brick
wing wells. The intake pipes should be at least 0.5 m above the
bed of the stream. Large intakes may be further protected with a
bar screen across the wing walls, parallel to or facing downwards
from the stream flow. Bars should have at least 100 mm clear
spacing. Provide access to clean the screen, and ensure strainers
are accessible for cleaning, and preferably removal.
B/93 D3/1
D. Suspended (pumped) intake.
The suction from a pump may be suspended from a simple
structure, suitably protected (Fig.D3/3). For small, slow-flowing
streams, an intake similar to the fixed inlet for ponds may suffice,
but the danger of accumulation of weed etc on the pipe should not
be overlooked.
B/93 D3/2
'Top above maximum flood level and
covered with removable timber or
concrete slab
Well
Brick or concrete
1Sffl
in porous soil
Concrete abutment
Notes
t Detail pipework to aHow access
Strainer to Check valve and Strainer
2 Allow for maximum flood level
but desigrr structure robustly
25 mm gravel or
stone
Gravel or broken
/stone surround
Longitudinal Section
Infiltration Pipes Fig D3/2
Roof Catchments
Run-off
The run-off will be a direct function of the rainfall intensity and the
plan area of the roof. 1 m2 plan area yields one litre of water from 1
mm of rainfall, less evaporation, etc., losses. Wind effects may
increase or decrease the run-off - the effective roof area may be as
much as + or - 50% of the elevation area variation from the plan area,
but in most situations this refinement can be neglected.
The effective yield will be less than the theoretical if the capacity of the
gutter and/or down pipes is less than the peak rate of run-off, resulting
in uncontrolled spillage. This is likely to be significant in areas where
rainfall takes place in short-period, high-intensity storms, unless the
gutter and down pipes are designed to take the maximum rate of run-
off at the peaks of rainfall.
C/93 D4/1
Gutters
75 0.4
100 0.8
125 1.5
150 2.3
C/93 D4/2
Corrugated iron
sheeting,
Roofing nail (spiked to
bottom purlin)
Suspended wires
(22gge gaW. adjusted
to give slope to
C&I.'V gutter (150mm
gutter)
overlap at joints)
If the head over the entry (that is, the gutter depth when running full,
is less than one-third of the down pipe diameter, the entry acts as a
weir and the capacity can be calculated by
where Q ~ litres/sec
H = head over the entry in nun
D = entry diameter in mm
It is assumed that the down pipe is no smaller than the entry, so that
the entry condition controls the down pipe capacity.
If the head is greater than one-third of the gutter diameter, the down
pipe will act as an orifice and the entry capacity is
Q = D 2 x H'A
15000
C/93 D4/3
Quality
A. Diversion.
A length of flexible pipe, or swivel elbow, or diverter plate can be
used to manually divert the first flush from the storage cistern.
Storage
Storage jars and tanks can be constructed above or below ground from
a wide range of materials: pottery, concrete blocks, bricks, steel,
fibreglass, ferrocement, etc. Ferrocement or wire reinforced cement
mortar tanks are a widely applicable low cost option.
C/93 D4/4
Tank designs up to 150 m3 are described in 'Ferrocement Water
Tanks' by S B Watt, see (D5). Modified designs using stick basket
work reinforcement have proved successful for 10 m3 tanks.
Construction manuals are available from WaterAid.
C/93 D4/5
Downpipe.
Removable cover
Screened intake
Overflow
pipe
Downppe
Coarse screen
(removable).
Fine screen \
(removable)^ *
Gravel
Sand 0.5m to
Cistern (with access CnarcMi 10m
h3tCh)
\ Pea gravel
Tanks made from wire reinforced cement mortar are widely used in
many parts of the world and are built by hand-trowelling a cement-
rich mortar onto a mesh of reinforcement to form cylindrical tanks
with thin walls which vary in thickness from 3 - 10cm depending on
the size of the tank. The advantages of this form of construction are
that it uses locally available skills and materials, is of low cost but high
durability, is easy to repair, and is sufficiently light for very small
tanks and jars to be moved from a central construction point. The
fact that, weightwise, it uses less materials than the equivalent
masonry or RCC tank structure is particularly attractive in countries
such as Nepal, where construction materials have to be carried over
long distances to site on peoples backs.
A/93 D5/1
2. Main vertical reinforcement in the tank's cylindrical wall
consists of 8mm diameter high tensils steel bars tied onto starter
bars cast into the floor and spaced at around 50cm c/c. This
reinforcement is carried over to form radial reinforcement in the
roof.
A/93 D5/2
1. Good quality mortar is essential. Sand must be of uniform
grade and both sand and water should be clean. The mix should
be stiff but workable.
5. Pipework must enter and exit through the PCC floor and not
through the ferro-cement walls.
6. Water depths do not exceed 1.7m for the given wall section.
From Uganda:
(a) Tanks founded in active clay or weak soil should have mesh
reinforcement on the base slab.
(b) For the wells, one layer of 22 gauge mesh is adequate above the
bottom 90 cms. If 24 gauge mesh is used then 2 layers are
necessary for the whole depth, and possibly 3 near the base of
large tanks.
(d) Pipework can pass through tank walls if above the tap water
level.
A/93 D5/3
Standpipes and Tkps
Points to watch - either prevent the bucket being hung on the tap, or give it
support (e.g. a bracket for the bucket over the tap).
The WHO paper referenced has graphs of head v. flow for xh" (12mm) to
1 V4" g.s pipes/taps. Typically, lh" taps will give 800 1/hr at 10m head,
and 3/4 " (18mm) 1500 1/hr at 10m head.
C/93 D6/1
Taps
(3) The Talbot 'Taflo' spring loaded tap superior to (1) and (2) but
costs more.
B
(4) The 'Lane' tap, developed in Nepal - simple, can be made locally,
low maintenance, but not self closing and most suited to low
pressures.
For a tap stand serving up to 80 users, a tap-flow rate of 0.1 1/sec can
be assumed; pipeline branches should be designed in the assumption
that ajl taps on the branch flow simultaneously.
B/3/88 D6/2
1000
a
ftGunmetal elbow
20mm MOPE
PLAN
U No. 12mm
ms bars
.75mm pipe
Waste water to 15mm nominal bore
or gs socket elbow
15mm nominal
bore gs socket
ELEVATION
Hook bolts
15 mm nominal bore
medium gspipe.
i- 300
[Bucket star*
trl-
-'Gunmetal change
CST .coupling GL
MDP
Water supply from small rivers and streams may be interrupted in dry
weather, and storage is often used in developed countries to overcome
this difficulty. One of the simplest means of storage is to create a
reservoir or lake by building a dam across the stream, but in
developing countries it will rarely be possible to provide storage
capacity for more than a few days' supply, and consequently designs
should be usually based on minimum flow in dry weather.
Dam design is a job for a specialist, and advice must be sought for any
dam exceeding 2m height, and should be obtained where possible for
smaller dams.
The dam must obviously be stable when full - the 'middle third' rule is
safe.
Sand and sub-surface dams are the subject of Notes D8 and D9.
B/93 D7/1
Ponds and Surface Reservoirs
B/93 D7/2
Overflow weir
/Stop valve
XCD Draw off
Screened Net
(duplicated)
Sand dams can provide a simple and inexpensive way of storing water
in the beds of intermittent streams. The objective is to accumulate
coarse sediments behind a shallow weir which is raised in successive
steps. This reduces evaporation and overcomes some other problems
found with shallow water reservoirs, and reduces the load on the dam
(nevertheless, dam height^ pf more than 2 to 3m must not be attempted
without advice from an engineer experienced in dam design).
Fig. D8/1 shows the general principle; abstraction from the sand
reservoir can alternatively be by well or borehole. The dam is raised
in stages so as to maintain sufficient velocity when the stream flows to
prevent fine material silting behind the dam. Alternative designs for
the dam include concrete, stone masonry, or gabions with clay or
plastic film face or core (Fig. D8/2). The dam need not be watertight -
some downstream seepage may be beneficial if the loss of water can be
tolerated.
B/93 D8/1
Direction of ground water flow
Erosion protection
fa! UJ 1
a C o n c r e t e s a n d dam
Stone masonry
Erosion protection
Gabions or blocks
Erosion protection
Alternative Types _. _ Q / _
F|
of Sand Dam 9 D8/2
Groundwater (Sub-surface) Dams
B/93 D9/1
UPSTREAM Green vegetation DOWNSTREAM Dry vegetation
T-tl
"r^m" Trapped Water in sand . r '<-
y - ; ' ; ;: D r y . s a n d ; - . ';.. /
Ctaytsh soil /lL
V/ / / / / / / / /
77 /
Source - Water for the World Technical Notes RWS 3D1 and RWS
3D4.
C/93 D10/1
Drip Feed Chlorinators are suitable for liquid chlorine solutions - see
Fig.D10/3.
C/93 D10/2
Table- Quantity of material to be added
to 1 litre of water to give a
1 * solution of chlorine
%avilblc Approx.Otv
Material chlorine Required
per Litre
Calcium Hvoochlorite
High-test1 or
Perchloron Powder 70 IS gm> (1 level
table spoon)
Sodium HvDochlorite
C/93 D10/3
Cover
Overflow 50mm
above inlet
Inlet
Flat stone to
200 litre barrel prevent hollowing
out of sand
600 mm sand
30 mm pea-sized
gravel
Outlet
'12-25mm pipe
perforated with
Platform
2mm holes
Bleaching powder
and sand
Clay pot
Pea gravel
6*8mm holes
^-15-^
" M v.:
Drip
no Feed Chloriostor
nai Fig 0^3
Metal container Stopper
Liquid level
Liquid level
Pebbles
Rubber stopper
m
Taut nylon string
Outlet
Flexible rubber tube
Taut nylon string
Flexible hose
Detail of Bowl
This entails leaving the water exposed to the sun, and the following are
important:
B/93 Dll
Sedimentation Basins for Water
The outlet should be arranged to take water from the top of the basin,
but a shallow scum baffle is useful to exclude leaves and other floating
matter - see Fig.D12/2.
A rectangular plan with length about three times the width is usually
preferred but not essential. With a rectangular tank it is easy to show
that for perfect conditions without turbulence the performance is
independent of depth, and the settling rate of particles removed
equates to the rate of flow through the tank divided by the plan area.
But flow distribution in very shallow tanks is poor, and there is
insufficient sludge storage capacity, so that in practice tanks of 1.5 - 2
m depth are usual (although in Nepal silt removal is effected in tanks 0.8m
deep, with length 6 times the width).
B/93 D12/1
A simple jar test will show the rate of settlement of suspended
particles, but the following table gives some guidance.
article. Settling
Material Diameter Velocity
(mm) (m per hr)
For very small installations, it may be helpful to fill the basin with
large gravel or broken stone. This overcomes the difficulty of the
inflow disturbing settled solids, but makes cleaning difficult (it will be
necessary to wash sediment from the stone into the drain with a
hosepipe, or buckets of water).
B/93 D12/2
Inlet
1m
Drain
a Board Baffle
Inlet
1
Drain
b Box Baffle
=**-
- Drain
rrangement F g Dtt/2
Slow Sand Filters
(c) Sand support medium of graded pea gravel - ideally between 2 and
10mm.
(f) An outlet control weir and valve to enable the filtration velocity to
be adjusted to between 0.1 and 0.2 m/h.
(g) Start up at low flow, fill in reverse direction to avoid air pockets,
build up to full flow over 12 hours or more and run to waste for a
further 2 days, unless there is post-filter disinfection.
B/93 D13/1
(i) Personnel involved in cleaning and operation should be free from
infection, and wear clean footgear and clothes.
B/93 D13/2
, Drain valve
.Fill valve Outlet valve
Inlet valve Baffle Control valve Drain Ventilator Oram
Wafer
Schmutzedeefce
(bwiogicai film)
Sand
Drainage system
To storage
Fine sand
Storage and
pump well
Coarse sand - 4
Pebbles ^
Perforated pipes
Collection pipe or c p r T i n K I A A
channel SECTION A - A
Perforated pipes
V77//7777s
Inlet
-J
^^$7777777%
Collection pipe or
channel PLAN
A long pit service has the advantage of less frequent emptying but at
the expense of a deeper and hence more costly pit. In the present
design, pit service life of three years is recommended to keep the cost
low and to demonstrate to school children the recycling of waste as
manure for school gardening.
B/93 D14
-DOOR SUPERSTRUCTURE
X I
i U.LEACH PIT
I ! (ONE OF TWO
0 14"
VIP Latrine
The Pit For family use, 1.2 dia. and at least 3m deep. This should
last 10 people for 7 years.
Cover Slab Best in concrete. Essential to seal joint with pit lining.
Precasting useful, but watch weight and handling.
B/93 D15/1
Adaptation Capacity can be increased by:
B/93 D15/2
Odours Fly screen
r Top of roof below
- top of vent pipe
Thatch or similar
roof
3m min
Pit lined with cement
mortar or brick
1.6m
1.3Siti
O
-2.V -Vent pipe ^ o , / V e n t pipe
Alternative Plans of Superstructure
Schematic Diagram
of s Ventilated
Improved Pit Latrine Fig D15/1
63mm pvc effluent
discharge pipe
length 15m
Inspection cover
Inspection tube
Soakaway cover slabv Squat note
Plastered brick
'or btockwork
-Effluent
Floor drainage
VIP Latrine
with Flush Toilet Fig D15/J
Aqua Privies
The VIP latrine with flush toilet is essentially an aqua privy (see D1S).
B/93 D16
Section 2 - Electrical and Mechanical Engineering
B/3/88
Index - Group 1 (M & E) - Electrical
D/93
Units and Formulae
Common Units
Capacitance C Farad
Power W Watt
Formulae
(i) Ohm's Law The current flowing in a circuit depends upon the
voltage producing the current and the overall
resistance of the circuit:-
I - V
B/3/88 El/1
For DC (direct current) and single phase AC (alternating current)
2 wire circuits:-
Brake horse power (bhp) is the net available horse power at the
motor driving end after deducting all losses within the motor
itself.
Power input
Motor efficiency varies from 85% for small motors to 90% and
above for large motors.
Power factor varies with size, speed and loading of the motor, but,
if not known, an average figure of 0.8 can be used in approximate
calculations. The current taken by a 3 phase motor at foil load,
where E is the voltage between phases is :-
B/3/88 El/2
(iv) 'Water1 Horse Power
1,430 efficiency %
= 1/s x m x 100
75 efficiency
101.92 10
efficiency %
1000 x Efficiency
1,000
kVa = kW = hp x 746
pf 1000 x Efficiency x pf
1,000
B/3/88 El/3
Electrical Supply System
AC (alternating current)
This three phase voltage is used for motors and large appliances. For
domestic circuits one of the phases is used with a neutral (Fig. E2/2)
(single phase and neutral or SP and N) and the voltage is then equal to the
phase voltage divided by,/T. For example with a phase voltage of 415
volts, the single phase and neutral voltage would be 415 = 240 volts.
yf
The three phases of the supply have a normal frequency of 50Hz (cycles
per second) or, in some cases, 60Hz and the voltages are displaced at 120 s
to each other.
As can be seen from Fig. E2/1, the sum of the coordinates of the three
phases on any vertical line is zero. If the load on the three phases is
balanced then the algebraic sum of the currents in each phase will also be
zero. Thus the three windings of a three phase machine can be
interconnected and this is done using either a Star (A) or Delta (A)
connection. The three phases are usually designated as Red (R),
Yellow(Y) and Blue(B) lines.
Star Connection
This method is shown in Fig. E2/2 where it can be seen that the three
windings are connected in common at the neutral mid-point. At this point,
in a balanced circuit the current will be zero as the value of the current
flowing towards the mid-point in any one phase is balanced by the current
flowing away to the other two phases.
B/3/88 E2/1
Red phase volts
Yellow phase volts
Blue phase volts
Red Line ( R )
Yellow Line(Y)
Phase
Voltages
In the star connected supply system there are two different voltages.
There is the line voltage between any two of the three phases and the phase
voltage between any one of the three phases and the neutral.
The line current and the phase current are equal in a star connected circuit.
Delta Connection
Fig. E2/3 shows the windings connected to form a closed circuit. The
voltage across any phase is equal to the voltage between the lines
connected to that phase:
Protective Switchgear
B/3/88 E2/2
Automatic circuit breakers have many advantages. These can be oil
immersed or air break for large loads, but for the normal loads
experienced in the field miniature circuit breakers (MCB's) or moulded
case circuit breakers (MCCB's) will meet most applications. They are
tamperproof, have a high breaking capacity, accurate and reliable overload
protection and time-delay characteristics to avoid tripping on harmless
transient overloads. The cost and delays of fuse replacement are avoided
as the circuit breaker can be reset once the fault has been removed.
Thermally operated MCB's are sensitive to ambient temperatures, but
magnetic hydraulic types are not affected.
B/3/88 E2/3
Table 1 - Relative Sizes of Phase and Earthing Conductors
or Simitar Materials
1 1
1.5 1.5
2.5 2.5
4 4
6 6
10 10
16 16
25 16
35 16
50 25
70 35
95 50
120 50
150 70
185 95
240 120
Fuses alone cannot protect against many earth leakage fire risks. To
provide complete protection the maximum earth leakage current would
have to be limited to about 1 amp. This can be achieved with an earth
leakage circuit breaker capable of detecting 1 amp, which would give good
protection to a 60 amp circuit. However, if the same circuit was protected
only by a 60 amp fuse an earth leakage current of 100 amp could flow for
at least one minute, creating a serious fire hazard. Earth leakage circuit
breakers and monitoring devices are reasonably priced and readily
available.
B/3/88 E2/4
Overcurrent Protection
B/3/88 E2/5
Tfcble 2 - Sizes of Plain or Tinned Copper Fuse Wire,
(for use in semi-enclosed fuses)
B/3/88 E2/6
Red Line ( R )
f f
VRY V
Yellow Line(Y)
VYB
Blue Line ( B )
Delta Connected
Three Phase System Fig E2/3
Major . .
Fuse Link 80 amps
Minor . .
Link L J 30 amps
Fuse Link 20 amps 20 amps
Fault
Example Illustrating
Discrimination between
Overcurrent Protective
Devices Fig E2/4
Electric Motors
DC motors are included for completeness, but will seldom be met. Most
motors supplied by WaterAid will be squirrel cage.
C/93 E3/1
Table 1
n
2
Motor Characteristics Applications
DC Motors
Continued/
E3/2
o Tfeble 1 (Continued)
Single-Phase AC Motors
Series-wound:
a) Universal As for series-wound DC motors Normally in fractional
sizes only - vacuum
cleaners, sewing machines,
domestic appliances.
b) Repulsion Lifts.cranes.
Induction Motors
c) Shaded pole As for shunt-wound DC motors. Small fans.clocks.
d) Split-phase Non-reversing fractional
h.p drives
e) Capacitor Constant speed with
intermittent loads -
refrigerator compressors.
f) Repulsion- Machine tools, pumps, mixers.
Contuued/
TWle 1 (Continued)
Three-phase AC Motors
Induction Types
Squirrel Cage Can be designed for a wide range All applications except
of starting and maximum torques. where very high starting
Standard types have starting torque is needed or where
torques from 100% to 175% of starting currents have to be
full load torque, with starting severely limited.
currents from 500% to 800% of
full load current.
Slipring wound Relatively constant speed over Air compressors, ram pumps
roltir the load range. Speed/torque cranes, high inertia
m can be varied by addition of drives, variable speed duty.
resistance in the rotor circuit.
Tfcblel (Continued)
Synchronous Types
Approximate full load speeds (rpm) allowing for slip are shown in Table 4.
C/93 E3/6
Induction Motor Currents
3 phase Voltage
HP
380 400 415 440
C/93 E3/7
3-Phase Motor Fuse Ratings
0- 1.5 6 4
1.6-2.2 10 6
2.3-3.0 15 6
3.1-5.2 15 10
5.3-6.6 20 15
6.7 - 9.6 25 15
9.7 - 10.8 30 20
10.9 - 13.0 35 25
13.1 - 19.2 50 30
19.3-23.3 60 35
23.4 - 30.8 80 40
30.9 - 42.2 100 60
42.3 - 64.3 200 100
64.4 - 93.0 200 125
93.1 - 128.6 250 200
128.7 - 150.0 300 200
C/93 E3/8
For the assisted start ratings using star-delta, auto transformer or rotor
resistance starters, the recommendations are based on a starting current of
3.5 times full load current for a duration of 20 seconds.
C/93 E3/9
gffect of Voltage Variations
Voltage Change
Characteristic
Plus 10% Minus 10%
C/93 E3/10
Standard Methods or Starting AC Motors
C/93 E4/1
With a manually operated start the handle is held in the 'star'
position until the motor has accelerated to full speed. The handle
is then rapidly pushed over to the 'run' position. Preferably, an
automatic push button contactor starter should be used which
provides the following sequence when the 'star' button is pressed:-
C/93 E4/2
Starting torque
Starting current
Starting torque
Starting current
C/93 E4/3
Typical Connections of 3-Phase Induction Motors
Sequence:
C/93 E5/1
u
FI
TC. * C<>.
FX
OC*.
I
-LC| STC,
It
A.-
I. TC
z. It!
3. TC
i L.__
LC f*
Li L* t3
(tt (1) tB)
LI,
-1 FI
rx =
LC *
so
LC
of Ydn
sc
nn
1. LC
sw
t <
3. &C Al
two*
Ai L
L5^t. I 4;
^ . B5/2.
Motor Installation
Inspection
Ensure that no parts are broken or missing. If the motor has to be stored
before use keep in a dean, dry place, free from foundation vibrations.
Check that the supply details and rated output on the motor nameplate
conform with the specification. Check the insulation resistance of the
motor winding with a 500 volt insulation tester ('megger'). The insulation
resistance in megohms should be not less than
Check the bearings for correct lubrication. With sleeve bearings check
that the oil wells are filled to the level indicated and that oil rings are free
to rotate.
Ball and roller bearings are correctly packed with grease by the
manufacturer and require no additional lubrication during the first few
months of service. If stored for more than six months the grease may
deteriorate and may shrink away from the bearing cage. Before
commissioning the bearing caps should be removed and if the grease is dry
and hard it should be renewed.
Check for any bearing damage by spinning the rotor by hand and listening
at each bearing using a short stick held against the bearing cap. Check fit
of any coupling or pulley which has to be fitted to the motor shaft. A
pulley requires a 'tap-on' fit and a coupling should have a force fit. When
fitting a pulley or coupling on to the motor shaft ensure that the opposite
end of the shaft is supported.
Check the starter to ensure that it is the correct type as specified and that
protective devices are correctly rated and adjusted for the actual load
conditions.
B/3/88 E6/1
Alignment
With a belt drive, the tight side of the belt should be on the underside.
Minimum distance between pulleys should be four times the diameter of
the large pulley. Belts should be tightened just enough to prevent slipping.
Excessive tension will cause damage. Adjusting screws of slide rails
should be arranged as shown in Fig E6/1 and a cord used, as shown, for
alignment.
B/3/88 E6/2
n
Gap
Slide rail
Adjusting screw
Lubrication
Ball and roller bearings must not be overfilled with grease as this causes
overheating and bearing failure. When a bearing is filled with grease take
care to fill all the bearing space between the rolling elements, but the outer
bearing caps should be only two-thirds full. When the motor is operating a
small amount of additional grease should be added every 2000 running
hours.
Every two years completely renew the grease. Ensure that only grease
recommended by the manufacturer is used.
Except with totally enclosed motors dust and dirt will be drawn into the
motor by the rotor fan. This can lead to overheating and damage to the
windings. Clean out any dust regularly, preferably by using a powerful
suction cleaner. The use of a high powered blower can lead to dust
accumulating within the windings.
Temperature
B/3/88 E7/1
Single Phasiqg
To reduce the risk of such a break in one phase of the supply check that
the circuit main fuses have a capacity of at least three times the full load
current of the motor, that the overload trips are correctly set and that
protection is fitted, to ensure that rapid disconnection of the motor, should
there be reduced or nil voltage in one or more of the phases.
B/3/88 E7/2
Fault Diagnosis
a
Table of common electric motor faults
Detection by sight:
tn Continued/
oo
Table of common electric motor faults (Continued)
Detection by hearing:
Steady electrical Running single phase Check that all supply lines are alive
hum with balanced voltage.
Continued/
m
00
Table of common electric motor faults (Continued^
as
oo
OC Fault Possible Cause Remedy
Detection by touch:
Continued
m
00
Table of common electric motor faults (Continued)
Avoid frequent starts unless the motor has been specifically designed for
such duties. As a general guide:-
B/3/88 E9
INDEX - Group 2 (M & E) - Mechanical
D/93
Conversion Factors and Formulae
3,300 Efficiency %
1430 Efficiency %
85,800 Efficiency %
Fluid hp = 1/s x m x sg
Ml/1
Driver output kW required = Fluid kW x 100
Pump Efficiency %
kW input to pump
B/3/88 Ml/2
Pumps - Basic Types
There are three main categories - suction, direct action and lever action.
Suction Pumps: These are suitable where the water is close to ground
level and will only operate in practical terms to depths of less than 6m.
They are found in places such as Bangladesh and Nepal where tube wells
are easily sunk into the soft deposits in a river basin or delta.
Direct Action Pumps: These have a cylinder below water level. The
piston is operated by rods and there is a separate rising main. They are
suitable to depths of 15m.
Lever Action Pumps: When the water has to be pumped from a depth
greater than 15m a hand pump requires some form of lever operation, and
can then be operated to a depth of 45m.
A/93 M2/1
Reciprocating pumps have a piston driven by shafts from a surface power
unit moving within a cylinder below water level, and have inlet and outlet
valves. Water is drawn into the cylinder (normally by the downward
stroke) and forced into the rising main by the upward stroke. Whilst some
of these may still be met spares are very expensive and submersible
centrifugal pumps are preferred, which, together with the motor unit, are
submerged below water level. They have a number of disadvantages:-
(b) They depend on water for cooling and if installed without low
water level protection the motor or pump fails if the borehole runs
dry.
(c) Similarly, when the flow of water into the borehole is restricted,
insufficient water flows across the motor unit (which is below the
pump inlet) causing rapid overheating of the motor. This can be
overcome by fitting a shroud to the unit to ensure that water
always passes over the motor.
A/93 M2/2
Progressive cavity pumps are described for surface units, but in this case
the pump unit is attached to the rising main and driven by a shaft from the
surface which has bobbins to centralise it in the main. The shaft normally
has couplings every 3m and in many cases this also incorporates the
bobbin. The drive head and power unit are at ground level, usually
occupied by V-belts.
(b) The pumps can be driven by either petrol diesel engines or electric
motors and since the power unit is at ground level maintenance can
more easily be carried out.
(c) Since the weight of the pump unit is less, the rising main is
sometimes smaller and lighter.
(d) They are much better at handling waters which contain fine
abrasive particles and tend to have a much longer period of
operation between overhauls.
(i) Ensure that the load on the engine does not fall
below half the designed output as this will result in
excessive coking if the engine is run on light load.
D/93 M2/4
Pumps - Data Required for Ordering
To obtain the correct pump for a given application, factual data must be
supplied - remember it is better to give more information than required
than too little.
A. Site Conditions
B. Output required
(i) Surface
A/93 M3/1
(b) If replacement, are there any existing foundations to work
to - if so give details of any bolts, including their size and
the centres between them.
(ii) Borehole
G. Drive Unit
A/93 M3/2
Pump Installation
Surface Pumps
Location: The pump should be sited with the shortest possible suction
pipework as the easier the suction conditions the more efficiently it will
operate.
Ensure that it is located on a solid level foundation and leave ample floor
space and headroom for inspection and maintenance purposes.
Ensure that the suction pipework has a continuous rise to the pump to
avoid air traps and that all pipework is properly supported so that the
pump casing is not subject to externally induced stresses.
Check the pump: Rotate the pump by hand to ensure there is no binding
or seizure.
Ensure that the glands have been properly packed or that mechanical seals
have not been damaged; always allow a slight leak from the gland, and
never start a pump with new packing under compression.
Fully prime the pump and suction before starting and spin to check
rotation under closed valves conditions before pumping under load.
A/93 M4/1
Borehole Pumps
Pipework Ensure that the pipework is strong enough to carry the weight
of itself and the pump unit, and the stresses induced when the pump is
operational.
Electric Cables: Ensure that the cable size is adequate to avoid voltage
drops greater than those acceptable to the unit.
A/93 M4/2
Maximum Suction Lift at Varying Altitudes
A/93 M5
Centrifugal Pump Fault Finding
(a) No delivery
(d) Noise/Vibration
B/3/88 M6
Pumps - Starting and Stopping Procedures
Starting
Where fitted supply cooling water to:-
Bearing jackets.
Gland/mechanical seal connections.
Michell bearings.
Oil coolers.
Stopping
a) Close delivery valve.
b) Stop driver unit.
c) Close any auxiliary water supplies.
B/3/88 M7
Pumps - Gland Repacking
2) Check that the shaft runs true and is free from pitting, scoring or
sharp edges beneath the packing. Check the gland follower for
correct fit within the stuffing box. The maximum clearance
between the inside of the gland and the shaft should be 0.4mm.
The maximum clearance between the gland follower inside face
and the stuffing box inside face should be 0.25mm.
4) Metallic and extruded packing rings are spirally opened ready for
fitting.
5) Fit each ring separately using a tamping stick to ensure that the
ring is pushed hard home. NB. PTFE multi-filament yarns are just
slid into the box and must not be driven home.
6) Joints are staggered by 120. Before fitting each ring check that
the shaft turns freely. If a lantern ring is fitted, position below
inlet connection, allowing for slight compression of bottom
packing rings.
7) Bring the gland follower up squarely against the last packing ring
and tighten the nuts evenly to finest pressure, checking the shaft
turns freely.
8) With pumps, leakage should take place. After start-up the gland
nuts should be tightened by one-sixth of a full turn at 10 minute
intervals, until leakage is reduced to an acceptable level.
9) Ensure that the gland remains cool and re-adjust after a few hours'
running.
C/93 M8/1
10) With packing glands of valves tighten the gland nuts until the
packing offers moderate resistance to spindle movement.
(Acknowledgements to Crane Packing Ltd., for the above
procedure recommendations).
C/93 M8/2
Retaining Pressure Rubber
ringv spring, / seal
Packing
Running
land
face
Shaft bush
Shaft
maximum
ft
0.25
maximum
A/93 M9
V-Belt Drives
Where the manufacturer has fitted a multi belt pulley, ensure that all the
belts are fitted, as running with less will result in damage to the remaining
belts. Replacement should be made in matched sets and old and new belts
should not be mixed.
Do not use automotive belts for industrial purposes as they are designed
for and operate under quite different conditions, i.e. rapidly increasing and
decreasing speed loads. The V-Belt is manufactured with a core of high
tensile cord embedded in rubber or a synthetic and encased in a fabric and
rubber reinforcement and all belts have a standard angle of 40 deg. The
most common type are wedge belts and these come in four sizes, SPZ,
SPA, SPB, SPC, and the number which follows the code is the length of
the belt in mm.
It is particularly important that during the early life of the belt, when
bedding-in is taking place, belts are checked for tensioning as heat
generated if the belt slips causes severe damage.
A/93 M10
Petrol Engines - Fault Tracing
Continued/
Fault Tracing Chart (Continued^
Continued/
Petrol (Internal Combustion') Engines
oc
FAULTY IDLING
Continued/
Petrol flntemai Combustion) Engines
Fault Tracing Chart (Continued)
ERRATIC RUNNING
Continued/
' Petrol (Internal Combustion) g
Fault Tracine Chart (Continued)
ro
OO
oc ENGINE RUNNING NORMALLY
Mechanical noise:-
l/i
Diesel Engines - Fknlt Tracing
5. Lack of fuel
Starter turns engine normally 6. Choked filter.
7. Faulty fuel supply pump.
8. Air lock in fuel system.
9. Injection pump fault.
10. Loss of compression - defective valves.
Continued/
Diesel (Compression Ignition^ Engine Fault Tracing Chart (Continued)
oc
FAULTY RUNNING
to
to Continued/
Diesel fComDression lenttion) En&ine Fault Tracine Chart (Continued!
Fault 8
Excessive knocking 20. One or more injectors sticking.
(deonation) 21. Lack of water in cooling system.
22. Lack of engine lubricating oil.
23. Start of injection too far advanced.
24. Excessive carbon deposit.
Mechanical noise:-
D/93
Planned Preventative Maintenance (P.P.M.)
C/93 XI
Vehicle Maintenance and Loading
The following note refers specifically to Land Rovers, but the principles
apply to other vehicles.
Maintenance , s^n .
Every vehicle should be regularly serviced and in countries where
temperatures are high and conditions are dusty, service intervals should
not exceed 4000 kin's (2500 miles).
A/93 X2/1
A H l i g h t s i n c l u d i n g brtilsfe i n d i c a t o r te>: ^ 4 ES'^-J a:: M P * . C J ^ ' ^"i
I., ' r t f , ' ::;iiK> ;' l.qxf?-
(i) Look around for fluid leaks, especially on brake system
(ii) Wear on drive system ie. universal joints * t kM
(m) ^ s ft pressures are ever used vehicle speed should not
exceed 40 kph (25 mph) ?i ;,:>- -:
:. . . .'- ; .,.., iOt a?iv i : \ f feia ,Vi-ir.\r"-i<JT^:
Loading _ ' ...!!> v* X ? >**,./:* rvt
The total or GfVW for which the LandRover is designed is 3050 kg. This
consists of the kerb weight and payload and the followingtpayloads are
applicable:-
. fr:: ; . .jg ""?.:% ;j i'.-;
(a) 110 Station Wagon 1081 kgs
(b) 110 Pick Up ;- * H: ' - 1211 kgs
"-*: (c) i 10 High Capacity Pick Up ti?;. 117 kgs
But equally important is the fact that the vehicle designed to have
maximum axle weight of 1200 kg at the fronvdnd 1850 kg at the rear. So
the actual load you can carry may be limited by. the axle load factor.
If a roof rack is fitted the maximum load is 150 kg which includes the
weight of the rack itself and it should be remembered that a roof rack
allows you to carry more volume not extra weight. The roof raffle should
not be loaded on an empty vehicle and should not extend over the bonnet
of the vehicle. .;*'! j a : . : .....''? . . ..-''' '
A/93 * X2/2
Pump and \folve Maintenance
A. General
4. , n Screw valves can be either right left hand closing and the valve
] * Ihpuld have* an appropriate indication on the valve wheel. Valves
should never be left hard open against the stop as they can become
jammed.
6. Relief valves also should need little attention but turn the adjusting-
screw for setting the relief pressure from time to time to prevent
its becoming seized up. If possible the relief valve discharge
ho'iild beamed tp the suction. The relief valve setting should be
&.*> -M^^aL'! n^naaj maximum pressure.
8. Check the operation or air release valves and air vents on storage
" ,tanki pericKlicaIly.'s "'"'' . ' " '
r& t , , >
A/93 X3/1
B. Positive Displacement Pumps
,4^ .. If the pump is; belt driven ij is important that the^elt pension is
l: kept to the, supplier's recommendation - |oo tigh^wijjt cause
heaving damage and too slack belt slip.
4. Air compressors get hot and it is therefore essential that they are
sited in a well ventilated space.
A/93 ^ X3/2
5. Compressors are very susceptible to suction conditions and care
should be taken that the suction (inlet) filter is kept clean. Inlet,
outlet valves also are critical and their seating has to be perfect,
otherwise the compressor will be worked excessively and may not
attain its proper working pressure.
'!?
A/93 X3/3
Most field offices will have acces$r.to a commercial repajr hqp/workshop,
biit a basic set of hand tools is"always useful,,and thj^ fQjlpw^g is
offeirfed as a check list: ' '""'..''!. /;''.. 31 - > v '~<>^,ir'vi m ..;..!:
C/93 a?K:' : X4