PGCM 14
PGCM 14
PGCM 14
4
Estimation and Quantity
Surveying (PGCM-14)
Submitted to:-
National Institute for Construction
Management and Research (NICMAR)
School of Distance Education (SODE)
Submitted by:-
Dijeesh PD
PG PROGRAME IN CONSTRUCTION MANAGEMENT
Reg. No.216-05-11-50661-2183
PGCM-14 PGPCM
CONTENT
SECTION DESCRIPTION PAGE
NO.
1.0 Scope of Work 3
2.0 Estimation and Costing 4
2.1 Need for Estimation and Costing 4
2.2 Procedure of Estimating or Method of Estimating 4
2.3 Data Required Prepare an Estimate 4
3.0 Rate Analysis 5
3.1 Procedure of Rate Analysis 5
3.1. Cost of Material at Source and at Site of 5
1 Construction
3.1. Cost of Labour- Type of Labour, Standard Schedule 5
2 of rates
3.1. Lead Statement 5
3
4.0 Rate Analysis for Cement pointing in CM 1:4 7
5.0 Rate Analysis for Plastering in ceiling in CM 1:4 8
6.0 Assumption reference for Price, other parameter 9
6.1 Price Reference 9
6.2 Reference for CM 1:4 with Fine Sand 10
6.3 Reference for CM 1:4 with Coarse Sand 11
6.0 Bibliography/Readings 12
2 | Page NICMAR-
SODE
PGCM-14 PGPCM
SECTION-1
3 | Page NICMAR-
SODE
PGCM-14 PGPCM
SECTION-2
1. Estimate give an idea of the cost of the work and hence its feasibility can be
determined i.e. whether the project could be taken up with in the funds available or
not.
2. Estimate gives an idea of time required for the completion of the work.
3. Estimate is required to invite the tenders and Quotations and to arrange contract.
4. Estimate is also required to control the expenditure during the execution of work.
5. Estimate decides whether the proposed plan matches the funds available or not.
4 | Page NICMAR-
SODE
PGCM-14 PGPCM
5 | Page NICMAR-
SODE
PGCM-14 PGPCM
SECTION-3
The costs of materials are taken as delivered at site inclusive of the transport local
taxes and other charges.
Purpose of Analysis of rates:
1. To work out the actual cost of per unit of the items.
2. To work out the economical use of materials and processes in completing the
particulars item.
3. To work out the cost of extra items which are not provided in the contract bond, but
are to be done as per the directions of the department.
4. To revise the schedule of rates due to increase in the cost of material and labour or
due to change in technique.
3.1.2 Cost of labour -types of labour, standard schedule of rates
The distance between the source of availability of material and construction site is
known as "Lead and is expected in Km. The cost of conveyance of material depends
on lead. This statement will give the total cost of materials per unit item. It includes
first cost, conveyance loading, unloading stacking, charges etc. The rate shown in the
6 | Page NICMAR-
SODE
PGCM-14 PGPCM
lead statement are for metalled road and include loading and staking charges. The
environment lead on the metalled roads are arrived by multiplying by a factor
a) For metal tracks - Lead x 1.0
b) For carts tracks - Lead x 1.1
c) For Sandy tracks - Lead x 1.4
7 | Page NICMAR-
SODE
PGCM-14 PGPCM
SECTION-4
10
SECTION-5
8 | Page NICMAR-
SODE
PGCM-14 PGPCM
10
9 | Page NICMAR-
SODE
PGCM-14 PGPCM
SECTION-3
10 | P a g e NICMAR-SODE
PGCM-14 PGPCM
DSR Item Code : 3.4
11 | P a g e NICMAR-SODE
PGCM-14 PGPCM
Cement mortar 1:4 (1 cement : 4 fine sand)
Details of Cost for : 1.00 Cum
Cod Description Unit Quantity Rate Amount
e
MATERIALS
(0.268 cum. of cement = 0.38 tonne)
036 Cement tonne 0.38 6300.00 2394.00
7
220 Carriage of Cement tonne 0.38 94.65 35.97
9
098 Fine sand cum 1.07 700.00 749.0
3
226 Carriage of fine sand cum 1.07 106.49 113.94
1
LABOUR
For measuring, carrying, depositing and mixing-
011 Beldar Day 0.75 329.00 246.75
4
010 Bhisti Day 0.07 363.00 25.41
1
999 Hire and running charges of mechanical mixer L.S. 26.91 1.78 47.90
9
999 Sundries L.S. 13.52 1.78 24.07
9
Cost for 1.00 3637.04
Cum
12 | P a g e NICMAR-SODE
PGCM-14 PGPCM
13 | P a g e NICMAR-SODE
PGCM-14 PGPCM
One Cum : 05/-
14 | P a g e NICMAR-SODE
PGCM-14 PGPCM
SECTION-6
6. BIBLIOGRAPHY/ READING
A Text Book of Estimation and Costing (Civil), DD Kohli, Ar.RC Kohli
15 | P a g e NICMAR-