Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

PGCM 14

You are on page 1of 15

Assignment No.

4
Estimation and Quantity
Surveying (PGCM-14)

Submitted to:-
National Institute for Construction
Management and Research (NICMAR)
School of Distance Education (SODE)

Submitted by:-
Dijeesh PD
PG PROGRAME IN CONSTRUCTION MANAGEMENT
Reg. No.216-05-11-50661-2183
PGCM-14 PGPCM

CONTENT
SECTION DESCRIPTION PAGE
NO.
1.0 Scope of Work 3
2.0 Estimation and Costing 4
2.1 Need for Estimation and Costing 4
2.2 Procedure of Estimating or Method of Estimating 4
2.3 Data Required Prepare an Estimate 4
3.0 Rate Analysis 5
3.1 Procedure of Rate Analysis 5
3.1. Cost of Material at Source and at Site of 5
1 Construction
3.1. Cost of Labour- Type of Labour, Standard Schedule 5
2 of rates
3.1. Lead Statement 5
3
4.0 Rate Analysis for Cement pointing in CM 1:4 7
5.0 Rate Analysis for Plastering in ceiling in CM 1:4 8
6.0 Assumption reference for Price, other parameter 9
6.1 Price Reference 9
6.2 Reference for CM 1:4 with Fine Sand 10
6.3 Reference for CM 1:4 with Coarse Sand 11
6.0 Bibliography/Readings 12

2 | Page NICMAR-
SODE
PGCM-14 PGPCM

SECTION-1

1.0 SCOPE OF WORK

Do Rate analysis for the following materials?


Cement Pointing 1:4- Unit 1 sqm- take 100 sqm
12 mm cement plastering in ceiling 1:4 with coase sand unit 1 sqm. Take 100
sqm

3 | Page NICMAR-
SODE
PGCM-14 PGPCM

SECTION-2

2.0 ESTIMATING AND COSTING


Estimating is the technique of calculating or computing the various quantities and the
expected Expenditure to be incurred on a particular work or project. In case the funds
available are less than the estimated cost the work is done in part or by reducing it or
specifications are altered, the following requirement are necessary for preparing an
estimate.
a) Drawings like plan, elevation and sections of important points.
b) Detailed specifications about workmanship & properties of materials etc.
c) Standard schedule of rates of the current year.

2.1 NEED FOR ESTIMATION AND COSTING

1. Estimate give an idea of the cost of the work and hence its feasibility can be
determined i.e. whether the project could be taken up with in the funds available or
not.
2. Estimate gives an idea of time required for the completion of the work.
3. Estimate is required to invite the tenders and Quotations and to arrange contract.
4. Estimate is also required to control the expenditure during the execution of work.
5. Estimate decides whether the proposed plan matches the funds available or not.

2.2 PROCEDURE OF ESTIMATING OR METHOD OF ESTIMATING.

Estimating involves the following operations


1. Preparing detailed Estimate.
2. Calculating the rate of each unit of work
3. Preparing abstract of estimate

2.4 DATA REQUIRED TO PREPARE AN ESTIMATE

1. Drawings i.e. plans, elevations, sections etc.


2. Specifications.
3. Rates.

4 | Page NICMAR-
SODE
PGCM-14 PGPCM

5 | Page NICMAR-
SODE
PGCM-14 PGPCM

SECTION-3

3.0 RATE ANALYSIS


In order to determine the rate of a particular item, the factors affecting the rate of that
item are studied carefully and then finally a rate is decided for that item. This process
of determining the rates of an item is termed as analysis of rates or rate analysis.
The rate of particular item of work depends on the following.
1. Specifications of works and material about their quality, proportion and
constructional
Operation method.
2. Quantity of materials and their costs.
3. Cost of labours and their wages.
4. Location of site of work and the distances from source and conveyance charges.
5. Overhead and establishment charges
6. Profit

3.1 PROCEDURE OF RATE ANALYSIS


3.1.1 Cost of materials at source and at site of construction.

The costs of materials are taken as delivered at site inclusive of the transport local
taxes and other charges.
Purpose of Analysis of rates:
1. To work out the actual cost of per unit of the items.
2. To work out the economical use of materials and processes in completing the
particulars item.
3. To work out the cost of extra items which are not provided in the contract bond, but
are to be done as per the directions of the department.
4. To revise the schedule of rates due to increase in the cost of material and labour or
due to change in technique.
3.1.2 Cost of labour -types of labour, standard schedule of rates

The labour can be classified in to


1) Skilled 1st class
2) Skilled 2nd Class
3) Unskilled
The labour charges can be obtained from the standard schedule of rates 30% of the
skilled labour provided in the data may be taken as 1st class, remaining 70% as II
class. The rates of materials for Government works are fixed by the superintendent
Engineer for his circle every year and approved by the Board of Chief Engineers.
These rates are incorporated in the standard schedule of rates.
3.1.3 Lead statement:

The distance between the source of availability of material and construction site is
known as "Lead and is expected in Km. The cost of conveyance of material depends
on lead. This statement will give the total cost of materials per unit item. It includes
first cost, conveyance loading, unloading stacking, charges etc. The rate shown in the

6 | Page NICMAR-
SODE
PGCM-14 PGPCM

lead statement are for metalled road and include loading and staking charges. The
environment lead on the metalled roads are arrived by multiplying by a factor
a) For metal tracks - Lead x 1.0
b) For carts tracks - Lead x 1.1
c) For Sandy tracks - Lead x 1.4

7 | Page NICMAR-
SODE
PGCM-14 PGPCM

SECTION-4

4.0 RATE ANALYSIS FOR CEMENT POINTING IN CM 1:4


Pointing on brick work or brick flooring with cement mortar 1:4 (1 cement: 4 fine sand) : Flus
weathered pointing.
Details of Cost for : 100.00 Sqm
Code Description Unit Quantity
MATERIALS
3.4 Cement mortar 1:4 (1 cement : 3 fine sand) Cum 0.30
(rate as per item no. 3.3)
LABOUR
0155 Mason Day 5.00
0115 Coolie Day 6.00
0101 Bhisti Day 9.30
9999 Sundries L.S. 71.50
9999 Scaffolding and racking out joints including L.S. 143.00
sundries

Add water charges


@ 1% on

Add C.P & OH


@15% on

10

Rate per Rs.92.07/-


One Sqm:

SECTION-5

5.0 RATE ANALYSIS FOR PLASTERING IN CEILING IN CM 1:4


Cement plaster 1:4 (1 cement: 4 coarse sand) finished with a floating coat of neat ceme
plaster
Details of Cost for : 100.00 Sqm
Code Description Unit Quantity
MATERIALS
3.9 Cement mortar 1:4 (1 cement : 3 coarse Cum 1.44
sand)
LABOUR
0155 Mason Day 6.70
0115 Coolie Day 7.50

8 | Page NICMAR-
SODE
PGCM-14 PGPCM

0101 Bhisti Day 9.20


9999 Scaffolding and sundries L.S. 126.10
0367 Cement tonne 0.20
2209 Carriage of Cement tonne 0.20
0155 Mason Day 2.70
0115 Coolie Day 2.70
9999 Scaffolding and sundries L.S. 80.60

Add water charges


@ 1% on

Add C.P & OH


@15% on

10

Rate per Rs.212.20/-


One Sqm:

9 | Page NICMAR-
SODE
PGCM-14 PGPCM
SECTION-3

6.0 ASSUMPTION REFERENCE FOR PRICE AND OTHER PARAMETER

6.1 PRICE REFERENCE

Rate Description of Rate Unit


Sl.No. Code Rate
1 0101 Bhisti Day 363.00
2 0114 Beldar Day 329.00
3 0115 Coolie Day 329.00
4 0155 Mason (average) Day 417.00
5 0367 Portland Cement tonne 6300.00
6 0982 Coarse sand (zone III) cum 1200.00
7 0983 Fine sand (zone IV) cum 700.00
8 2203 Carriage of Coarse sand cum 106.49
9 2209 Carriage of Cement tonne 94.65
10 2261 Carriage of Fine sand cum 106.49

10 | P a g e NICMAR-SODE
PGCM-14 PGPCM
DSR Item Code : 3.4

11 | P a g e NICMAR-SODE
PGCM-14 PGPCM
Cement mortar 1:4 (1 cement : 4 fine sand)
Details of Cost for : 1.00 Cum
Cod Description Unit Quantity Rate Amount
e
MATERIALS
(0.268 cum. of cement = 0.38 tonne)
036 Cement tonne 0.38 6300.00 2394.00
7
220 Carriage of Cement tonne 0.38 94.65 35.97
9
098 Fine sand cum 1.07 700.00 749.0
3
226 Carriage of fine sand cum 1.07 106.49 113.94
1
LABOUR
For measuring, carrying, depositing and mixing-
011 Beldar Day 0.75 329.00 246.75
4
010 Bhisti Day 0.07 363.00 25.41
1
999 Hire and running charges of mechanical mixer L.S. 26.91 1.78 47.90
9
999 Sundries L.S. 13.52 1.78 24.07
9
Cost for 1.00 3637.04
Cum

Rate per One Rs.3637.0


Cum : 5/-

6.2 RATE REFERENCE FOR CM 1:4 WITH FINE SAND

12 | P a g e NICMAR-SODE
PGCM-14 PGPCM

6.3 RATE REFERENCE FOR CM 1:4 WITH COARSE SAND

DSR Item Code : 3.9


Cement mortar 1:4 (1 cement: 4 coarse sand).
Details of Cost for : 1.00 Cum
Cod Description Unit Quantity Rate Amount
e
MATERIALS
(0.214 cum. of cement = 0.31 tonne)
036 Cement tonne 0.38 6300.00 2394.00
7
220 Carriage of Cement tonne 0.38 94.65 35.97
9
098 Coarse sand cum 1.07 1200.00 1284.00
2
220 Carriage of Coarse sand cum 1.07 106.49 113.94
3
LABOUR
For measuring, carrying, depositing and
mixing-
011 Beldar Day 0.75 329.00 246.75
4
010 Bhisti Day 0.07 363.00 25.41
1
999 Hire and running charges of mechanical mixer L.S. 26.91 1.78 47.90
9
999 Sundries L.S. 13.52 1.78 24.07
9
Cost for 4172.04
1.00 Cum

Rate per Rs.4172.

13 | P a g e NICMAR-SODE
PGCM-14 PGPCM
One Cum : 05/-

14 | P a g e NICMAR-SODE
PGCM-14 PGPCM

SECTION-6
6. BIBLIOGRAPHY/ READING
A Text Book of Estimation and Costing (Civil), DD Kohli, Ar.RC Kohli

GOVERNMENT OF INDIA CENTRAL PUBLIC WORKS DEPARTMENT 2014 DELHI


SCHEDULE OF RATES

15 | P a g e NICMAR-
SODE

You might also like