大幅石矢的溫度控制措施 藍田邨重建基礎地盤案例 八月一日分享會
大幅石矢的溫度控制措施 藍田邨重建基礎地盤案例 八月一日分享會
大幅石矢的溫度控制措施 藍田邨重建基礎地盤案例 八月一日分享會
Measures for
Footings & Pile Caps
2006/10/6 1
Table of Contents
1. Introduction ()
2. Literature Review ()
3. Selection of TC Measures ()
4. Assessment of Peak Temperature and
Temperature Gradient ()
5. Instrumentation and Installation ()
6. Lesson Learnt from this Project ()
7. Cost Analysis ()
2006/10/6 2
1. Introduction ()
)includes
1.1 Massive Concrete (
1.1.1 1.5m Thick Footings (15m x 12m)
1.1.2 2.5m Thick Pilecaps (15m x 14m)
The Site
(4) Admixture = 2.4 liter/m3 Retarder delays hydration rate (not total heat generated)
(Daratard-17D)
(5) Water = 188 liter/m3 Max ice 60% by weight reduces material temperature
(6) Water/Cement Ratio = 0.39
(7) Aggregate/Cement Ratio = 3.51 Aggregate stores under shelter reduces material temperature
2006/10/6 5
1.2.2 Submit formwork type and insulation
Timber insulates better than steel formwork 20mm thick CELFILL NR Joint Filler
(19mm Plywood) (1m x 1m or 1m x 2m)
1.2.3 Curing Details Thermal Conductivity = 1.649 w/mK
2006/10/6 6
1.2.4 Calculations of forecast concrete temperature,
temperature gradients and resulting stresses.
=> Early Thermal Crack Control
2006/10/6 7
2. Literature Review ()
2.1 Crack Types ()
Shrinkage Aggregate
Physical
Drying Shrinkage
Corrosion of Rebar
Chemical
Alkali Aggregate Reaction
After Hardening
Freeze/Thaw Cycles
Thermal External Restraints
Early Thermal
Internal Restraints
Plastic Shrinkage
Before Hardening Plastic
Plastic Settlement
Before reabsorbing all bleeding water
(~2 to 3 hour after concreting)
Reproduced from Concrete Society (1992). Non-Structural Cracks in Concrete. Concrete Society technical report No 22, pp.48.
2006/10/6 8
2.2 Development of Early Thermal Cracks ()
Cement Hydration
Heat Generation
Yes No
Restraint
Present
2006/10/6 10
3. Selection of Temperature Control Measures ()
1 2 3 4
Temperature Additional Steel Cooling Pipes Liquid Quilt system
Control Bar Nitrogen *(Job Reference)
Methods
- No TC monitoring - Effective and direct TC - Effective and direct TC - Effective and indirect TC
Advantages:
- No further analysis - No further analysis - No TC monitoring - Inexpensive
- Little time implication - Little time implication - No further analysis - Flexible
- Little time implication - Quilt reusable
- Expensive (material and - TC monitoring required - Expensive (material cost) - Continuous TC monitoring
Disadvantages:
fabrication cost) - Expensive (material and - High technique and skill to required
- Ineffective method installation cost) control temperature at - Analysis and report
- Large working space for air concrete plant required
compressor - Substantial manpower to
- Backfilling cooling pipes install quilt material within
- Noisy Operation (24 hrs) specified period
- Time implication (~21 day)
- Affected by ambient temp
- Sensitive to workmanship
* (2004). .. .
* (1988). .().
2006/10/6 11
Option Time Cost Risk/Difficulty
Additional Steel Bar 3 2 4
Cooling Pipes 2 2 2
Liquid Nitrogen 5 1 1
Quilt System 1 5 4
1 Relative slowest Relative highest cost Relative highest risk/difficulty
2 Relative slow Relative high cost Relative high risk/difficulty
3 Moderate Moderate Moderate
4 Relative fast Relative low cost Relative low risk/difficulty
5 Relative fastest Relative lowest cost Relative lowest risk/difficulty
Time Time
5 5
Fast Fast
4 4
3 3
2 2
1 1
Low 0 Low 0
risk/difficulty Low cost risk/difficulty Low cost
Time Time
5 5
Fast Fast
4 4
3 3
2 2
1 1
Low 0 Low 0
risk/difficulty Low cost risk/difficulty Low cost
Risk/Difficulty
2006/10/6 Cost Risk/Difficulty Cost 12
Liquid Nitrogen (Method 3) Quilt System (Method 4)
4. Assessment of Peak Temperature and
Temperature Gradient ()
(a) Design Certifying Consultant Wong & Cheng
Consulting Engineers Ltd
(b) Physical modeling [Temperature Rise Evaluation Test (TRET)]
to obtain parameters on site for numerical modeling
(Adiabatic parameters = perfectly insulated condition)
(a) Plan
2006/10/6 14
Block 4
5. Instrumentation and Installation ()
5.1 Typical Thermocouple Locations ()
(b) Section
2006/10/6 15
5. Instrumentation and Installation ()
5.2 Installation and General Procedures
Thermocouple Thermocouple
Wire mounting on Rebar
2006/10/6 16
5. Instrumentation and Installation ()
5.2 Installation and General Procedures
Spray Curing
Concreting
Compound
2006/10/6 17
5. Instrumentation and Installation ()
5.2 Installation and General Procedures
2006/10/6 18
5. Instrumentation and Installation ()
5.2 Installation and General Procedures
View
Data
Download
Quilt System
Completed data
2006/10/6 19
5. Instrumentation and Installation ()
5.3 Monitoring Procedures
2006/10/6 20
5.4 Typical Monitoring Result
70
Temperature (C)
50
30
10
-10
2006/6/8 19:00 2006/6/10 7:00 2006/6/11 19:00 2006/6/13 7:00 2006/6/14 19:00
Time
2006/10/6 21
6. Lesson Learnt from This Project ()
6.1 General Attention to TC
2006/10/6 22
6. Lesson Learnt from This Project ()
6.2 Particular Attention to TC (Quilt System)
2006/10/6 23
7. Cost Analysis ()
(a) Total Quilt Area = 6,050 m2
Labour Cost (C1) = HK$ 27.78 /m2
(b) Total Quilt Material Cost = HK$ 119,112
or Quilt Material Cost (C2) = HK$ 19.69 /m2
(c) Installation & Monitoring = HK$ 20,000/Block
or Installation & Monitoring (C3) = HK$ 13.22 /m2
(d) Consultant Fee = HK$ 70,000 (Whole Project)
or Consultant Fee (C4) = HK$ 11.57 /m2
(e) Total Cost of Quilt System = HK$ 437,181
or Cost of Quilt System per m2
= C1 +C2 + C3 + C4 = HK$ 72.26 /m2
2006/10/6 24
End of Presentation
2006/10/6 25