QT00129 Vol4 Final PDF
QT00129 Vol4 Final PDF
QT00129 Vol4 Final PDF
Drainage Affairs
Contents
1.0 General ................................................................................................................................... 1
1.1 Introduction................................................................................................................................ 1
1.2 Standards .................................................................................................................................. 1
1.3 Master Planning of Landscape and TSE Irrigation Systems ..................................................... 1
1.3.1 Landscape Development Master Plan ....................................................................................... 1
1.3.2 Irrigation Budgets ....................................................................................................................... 1
1.3.3 Irrigation Master Plan ................................................................................................................. 2
1.4 Irrigation Water Quality.............................................................................................................. 2
1.4.1 General ....................................................................................................................................... 2
1.4.2 Public Health Factors in Effluent Use ......................................................................................... 2
1.4.3 Quality of TSE for Landscape Irrigation ..................................................................................... 3
1.4.4 Recommended TSE Quality for Landscape Irrigation ................................................................ 4
1.5 Documentation .......................................................................................................................... 4
1.6 Environmental Impact Assessment ........................................................................................... 4
1.7 Building Permit .......................................................................................................................... 4
2.0 Design of TSE Transmission and Distribution System ..................................................... 7
2.1 Definitions.................................................................................................................................. 7
2.2 Standards and Sources of Information ...................................................................................... 7
2.3 Principles of Design................................................................................................................... 8
2.4 Sizing and Flow Estimation ....................................................................................................... 8
2.5 Pipeline Materials .................................................................................................................... 14
2.5.1 Ductile Iron Pipes ..................................................................................................................... 14
2.5.2 Polyethylene Pipes ................................................................................................................... 14
2.5.3 GRP Pipes ................................................................................................................................ 15
2.5.4 Asbestos Cement Pipes (Safety Note) ..................................................................................... 15
2.6 Hydraulic Analysis ................................................................................................................... 15
2.7 General Design Considerations .............................................................................................. 20
2.7.1 Pipeline Horizontal Alignment .................................................................................................. 20
2.7.2 Pipeline Vertical Alignment ....................................................................................................... 21
2.7.3 Internal Pipe Pressures and Restraint of Thrust ...................................................................... 21
2.7.4 Air Release ............................................................................................................................... 22
2.7.5 Pipeline Maintenance Draining.............................................................................................. 22
2.7.6 Isolation Valves ........................................................................................................................ 22
2.7.7 Flow Metering and Remote Sensing ........................................................................................ 23
2.8 Pumping Installations .............................................................................................................. 25
2.8.1 Pumping Plant .......................................................................................................................... 25
2.8.2 Plant Layout.............................................................................................................................. 28
2.8.3 Primary Movers ........................................................................................................................ 29
2.8.4 Variable Speed Drives (VSD) ................................................................................................... 30
2.8.5 Motor Control Centre (MCC) .................................................................................................... 31
2.8.6 Instrumentation and Control ..................................................................................................... 33
The irrigation budgets may highlight issues related to 1.4 Irrigation Water
supply that will be dealt with by the Irrigation Master
Plan (see section 1.3.3), and they will also provide Quality
essential guidance to the landscape designers for the
1.4.1 General
quantities and types of vegetation that can be
sustained within each budget sector. Irrigation water quality is an issue of primary
concern wherever TSE is the source of irrigation
1.3.3 Irrigation Master Plan water for public amenity landscape. There are two
main areas of concern. Firstly, the chemical and
The Irrigation Master Plan derives from the
biological properties of the irrigation water must be
Landscape Development Master Plan and the
such that its application on areas of publicly
irrigation budgets, but needs to address a broader
accessible landscape presents negligible health
range of issues concerning irrigation supply. The
risk to members of the public, and in particular
objective of the irrigation master plan is to study and
those who by reasons of health or age may be
identify specific issues related to the supply and
more susceptible to pathogens or chemical
distribution of irrigation water. It will also make
contaminants. Secondly, the chemical, physical
recommendations, for example regarding future
and biological properties of the irrigation water
infrastructure requirements, or matters related to
should be entirely suitable for plant growth and for
irrigation water quality (refer to.1.4 below). The
the irrigation system through which the water will
Irrigation Master Plan should also contain a time-
be applied, or at least do not impose undue
scale or outline programme for execution of any
constraints on the type of landscaping possible.
proposed projects, co-ordinated with expected urban
growth, future effluent availability, and the proposed
1.4.2 Public Health Factors in
implementation of landscape projects.
Effluent Use
Examples of typical recommendations that will be
The potential risk to public health from wastewater
made in the Irrigation Master Plan may include the
is generally assessed in terms of biological quality,
following:
expressed as the ratio between biological oxygen
Requirements for new irrigation infrastructure; demand and total suspended solids (BOD:SS), and
also measured directly in terms of most probable
Recommendations for upgrading or number of coliform organisms. Although there are
refurbishing of existing effluent distribution no internationally applicable standards for these
networks, storage reservoirs, pumping parameters, the World Health Organisation (WHO)
stations etc.; has recommended BOD and SS less than 10mg/l
Proposals for control and telemetry and most probable number of coliform organisms
installations (e.g. SCADA); not to exceed 100/100ml.
Proposed measures related to irrigation water Qatar proposes to adopt a standard of 5:5 for
quality (salinity, chemical quality, and BOD:SS. This standard would ensure minimal risk
filtration); to public health from TSE irrigation water.
Recommendations related to existing use of However, although the final effluent from Doha
irrigation water, e.g. for improving efficiency, West STW is generally achieving 5:5, the final
or upgrading the irrigation systems; effluent from Doha South STW has not been able
to achieve this standard. It may therefore be some
Operational issues related to existing time before this could consistently be achieved in
irrigation infrastructure. practice.
associated with heavy industry, health issues related salinity can restrict quite severely the range of
to chemical contamination are less likely to be of plants that may be used, with consequences for the
significance where the principal source of TSE is landscape character and variety of landscape
domestic sewage. design options. Furthermore, the problem of salt
accumulation in the soil is exacerbated by the high
The likelihood of human contact with irrigation water water-table and poor drainage in many parts of
can not be practically avoided in amenity landscape Doha.
areas. There are several possible means by which
pathogenic organisms from irrigation water could be Qatar proposes to adopt a standard for Total
transferred to humans. The three most likely Dissolved Solids (TDS) not to exceed 2,000mg/l
methods are as follows: (equivalent to 3,500mhos/cm). However, this
level of salinity is still sufficiently high to be
Bodily contact with irrigation water or soil; detrimental to many salt-sensitive plant species
Breathing of air that contains fine droplets of and it would be highly beneficial if a lower figure
irrigation water; could be achieved. In fact, irrigation water having
TDS as low as 500-1,000mg/l is harmful to salt-
Consumption of contaminated food or drinks
sensitive plant species. Actual TDS figures for
sourced from TSE irrigated crops.
Doha West STW (for the period 21st 28th Sept
Picnicking on grass shortly after it has been irrigated, 2003) range from 1,311 to 1,411mg/l. On the other
or being in the immediate vicinity when sprinkler hand, TDS levels for Doha South STW were rather
systems are in operation are the most likely means higher over this period, ranging from 1,372 to
by which pathogens could be ingested. Bacteria may 2,492mg/l. Therefore in order to achieve a target
survive in the soil for two months or even one year in TDS of better than 2,000mg/l it will be necessary to
some cases, although sandy soils and high address the underlying problem of salinity in the
temperatures tend to decrease survival times. incoming sewage.
Ensuring that lawn sprinkler systems are scheduled
to operate in the early morning hours is a necessary The suitability of TSE for irrigation purposes also
depends upon its chemical properties, including
precaution. Exposure to irrigation water is less likely
sodium hazard, usually expressed as sodium
with drip irrigation and bubblers as compared to
spray sprinklers. absorption ratio (SAR), and the levels of harmful
ions. SAR is calculated from the ratio of sodium to
It should be noted that specific health risk is related calcium and magnesium. Continued use of
to an individuals threshold of susceptibility, and that irrigation water having a high SAR leads to the
infants, elderly persons, and those having weakened sodium being absorbed, causing the soil to become
immune systems are the most susceptible. Even hard and compact, and increasingly impervious to
with irrigation water of good biological quality, some water penetration. Leaching and soil additives,
degree of health risk cannot be entirely eliminated, particularly gypsum, are used to counter these
and it is essential that special attention be given to affects. Sandy soils with a low content of clay
protecting those members of the public who may be particles are less likely to be affected by high SAR.
vulnerable. For this reason, the grounds of hospitals Figures for SAR of Doha South TSE are available
should be irrigated with potable water, particularly in from the recent sampling analysis presented by the
those areas accessible to patients. For the same Quality and Safety Division. The analysis results
reason, vegetation within the grounds of nursery indicate that the SAR values for the TSE from Doha
schools and primary schools needs also to be South are in the range of 4.5 to 5.0, which is 50%
irrigated with potable water. of the acceptable long term limit for irrigation
(please refer to Table 1.4.1).
1.4.3 Quality of TSE for
The effect upon plant growth of the levels of
Landscape Irrigation different chemical constituents in irrigation water is
Salinity is the single factor most commonly affecting a complex subject and dependent upon a number
the suitability of TSE for use as irrigation water. Salt of variable factors. Each plant species has its own
is poisonous to plants. Even relatively low levels of tolerance threshold for each anion or cation, often
varying widely between species of the same genus. Guidance on typical content and requirements of
Furthermore, sensitivity depends upon other factors screening, scoping, EIA analysis, reports and data
such as the nature of the soil. The pH and overall collection is given in Volume 1, Sections 2.7, 3.7
chemical balance of the irrigation water also affect and 4.7. This guidance should be referred to for
the availability of different ions such as heavy metal any environmental studies associated with TSE
cations, which become more available to plants at system projects. Volume 5, Section 1.10 also
lower pH, i.e. at higher acidity levels. It can generally provides useful guidance information on the reuse
be expected that the levels of heavy metal cations in of treated sewage effluent.
TSE from domestic sewage will be below toxic
thresholds.
1.7 Building Permit
1.4.4 Recommended TSE
The requirements for application for building
Quality for Landscape permits are described fully in Volume 1 Section 4.6.
Irrigation
Table 1.4.1 provides interim recommendations for
TSE water quality criteria to be used for landscape
irrigation in Qatar. Proposed current and future
effluent discharge standards for Doha sewage
treatment works are provided in Table 1.4.2.
Contents of this table should be considered as
temporary standards, which will be modified by the
Environmental Section (ES) within Q&SD during
2004.
1.5 Documentation
Documentation required by the DA to be prepared by
consultants in relation to TSE system design is
described in Volume 1 Section 5.
Table 1.4.1 - Recommended Quality Standards for TSE Irrigation Water in Qatar (Interim)
Recommended
Limit for Irrigation
Parameter Units Remarks
Long Short
Term Term
Lower than the standard of 2000mg/l proposed
TDS mg/l 500 2000
for Doha - see text above
EC mho/cm 1500 - As for TDS
PH units 6.0 - 7.0 - Significant indirect effects on plant growth
SAR ratio 10.0 - See text above
BOD (5d @
mg/l 5.0 5.0 According to proposed new standard for Doha
20C)
SS mg/l 5.0 5.0 According to proposed new standard for Doha
Total coliforms No/100ml 100 100 Based on WHO recommendation
Ca mg/l - - No recommended limit, toxic to calcifuge plants
Mg mg/l 150.0 - Minor plant nutrient
Na mg/l 400.0 - Major component of salinity
K mg/l - - Essential plant nutrient, no recommended limit
Total P mg/l 30.0 - Essential plant nutrient
N (as NH3) mg/l 1.0 - According to proposed new standard for Doha
N (as NO3) mg/l 50.0 - Nitrogen is essential plant nutrient
Alkalinity
mg/l 200.0 - Affects soil pH
(HCO3 + CO3)
SO4 mg/l 400.0 - Not toxic to plants
Cl mg/l 650.0 - Major component of salinity
F mg/l 1.0 * 15.0 * Inactivated by neutral and alkaline soils
Al mg/l 5.0 * 20.0 * Only toxic in very acid soils
As mg/l 0.1 * 2.0 * Toxic to many plants at varying concentrations
B mg/l 0.75 * 2.0 * Essential nutrient, but toxic if too high
Fe mg/l 5.0 * 20.0 * Nutrient but at high levels affects soil chemistry
Cd mg/l 0.01 * 0.05 * Toxic to some plants at low concentrations
Co mg/l 0.05 * 5.0 * Toxic to some plants in acid soils
Be mg/l 0.1 * 0.5 * Toxic to many plants at varying concentrations
Cr mg/l 0.1 * 1.0 * Toxicity to plants is not well established
Cu mg/l 0.2 * 5.0 * Toxic to a number of plants
Cn mg/l 0.05 0.1
Mn mg/l 0.02 * 10.0 * Toxic to some plants at low concentrations
Se mg/l 0.02 * 0.02 * Toxic to plants at low concentrations
Pb mg/l 5.0 * 10.0 * Can be toxic to plants at high concentrations
V mg/l 0.1 * 1.0 * Toxic to many plants at low concentrations
Mo mg/l 0.01 * 0.05 * Not normally toxic to plants
Ni mg/l 0.2 * 2.0 * Toxic to some plants in acid soils
Zn mg/l 2.0 * 10.0 * Toxic to many plants at varying concentrations
Source: Based on wastewater quality limits adopted by Sultanate of Oman
* USEPA guidelines, cited by Rowe and Abdul-Magid in Wastewater Reclamation and
Reuse
A.C. Twort, D.D. Ratnayaka, M.J. Brandt, be recognised. As a whole, transmission and
2000, Water Supply, 5th edition, UK, Arnold distribution mains, TSE sources, pumping
and IWA Publishing. facilities, and storage facilities must be
designed so that, in combination, they will
Washington State Department of Health,
optimize the TSE system.
2001,Water System Design Manual,
Washington, State Department of Health.
Standards and manuals pertaining to specific pipe
materials and construction issues are quoted in the
relevant sections of this volume.
Hydraulic calculation should be carried out in order to design manuals. There are also many
demonstrate that the system will: computer software packages readily available
to aid in the design of complex systems. Apart
Satisfy the estimated demand; from the above mentioned SynerGEE
Operate within the required pressure range; (Advantica) other reputable software include
InfoWorks (Wallingford Software), InfoWater
Operate at acceptable velocities.
(MWH) and WaterCAD (Haestad Methods). It is
Network analysis by a computerbased mathematical expected that the design procedures used for
model should be used to analyse the performance of the irrigation system of Doha will be consistent
the existing system and proposed extensions to that with those widely applied and accepted by
system. Models representing both transmission and professionals world-wide as good engineering
distribution mains are required to assess system practice.
performance under a variety of supply and operating
conditions. A model would include elements The sizing procedure shall include the following
steps:
representing physical components of the irrigation
system like pipes, pumps, valves, regulators and 1. Establish demands and flows
tanks that make up the actual network. The usual
input data for any hydraulic model includes: pipe 2. Assume pipe diameters
diameter and length; friction factor according to the
formula which is applied; node elevation; ground 3. Carry out hydraulic analysis
elevation; pump curve or pump energy if the curve is 4. Correct the assumed pipe diameters,
unknown; pump speed; tank profiles; upstream and
as necessary
downstream pressure for regulators; valve status;
and flow coefficients. As an output, the model will 5. Carry out final hydraulic check
produce predicted flows, velocities, pressures and
head losses, which will indicate the network
performance. The results are then a basis for either
Minimum Size
increasing or decreasing pipe diameters, adding new
pipelines or replacing pumps etc.. Hydraulic analysis The minimum size for a transmission or
and computer models are discussed in Section 2.6. distribution main should be determined by
hydraulic analysis. In general, the minimum
The latest hydraulic model of the Doha irrigation
diameter of all distribution mains should not be
system was created using SynerGEE, and that model
less than 200mm internal bore. All sizes are to
should be referred to before starting any further
be metric sizes. Recommended flow rates,
analysis.
velocities and corresponding head losses for
Sizing Procedure different pipe diameters are shown in Tables
2.4.1. and 2.4.2. These examples are for pipes
Procedures for sizing distribution and transmission with an assumed hydraulic roughness factor ks
mains for irrigation systems have been established in of 0.15mm and 0.06mm.
many engineering textbooks, reference books, and
Table 2.4.1 - Recommended Flows, Velocities and Resulting Head Losses for Various Pipe Diameters (ks
0.15 mm)
Diameter Flow (l/s) Velocity (m/s) Head loss (m/km)
(mm) From To From To From To
Table 2.4.2 - Recommended Flows, Velocities and Resulting Head Losses for Various Pipe Diameters (ks
0.06 mm)
Diameter Flow (l/s) Velocity (m/s) Head loss (m/km)
(mm)
From To From To From To
Figure 2.4.1 Example of land elevation versus hydraulic grade (HGL) where HGL cuts the land elevation
under a flow of 650L/s due to high losses not desirable.
Figure 2.4.2 Example of land elevation versus hydraulic grade (HGL), where HGL lies above the land
elevation under a flow of 550L/s - acceptable.
Minimum Distribution System Pressure There are a variety of ways to provide surge
control. Methods include:
The distribution system should, in general, be able to
provide peak flows at no less than 30m water head Open surge tanks;
(300kPa), as agreed with the DA in the course of Pressurised surge tanks;
writing the Rationalisation of the TSE system report
Surge anticipator valves;
2. As various types of sprinklers and drip emitters
require different pressures, the actual requirements Vacuum relief valves;
for a given landscape area should be provided by the
Regulated air-release valves;
designer of the downstream irrigation system. In case
the irrigation water is discharged into a local irrigation Optimising main size and alignment;
reservoir, then the required pressure would be
Electric soft start/stop and variable speed
governed by the level of the inlet pipe.
drives for pumps;
Maximum and Minimum Flow Velocity Electric interlocks to prevent more than
one pump from starting at the same time;
In normal circumstances it will be desirable to avoid
unduly high or low velocities. A range from 0.5m/s to Slow opening and closing valves; and
2.0m/s under hourly peak demands may be
Increasing the polar moment of inertia of
considered appropriate. However, in special
the rotating pump/motor assembly.
circumstances, velocities up to 2.5m/s may be
acceptable in the main trunk and distribution A combination of methods may be necessary and
pipelines. For pumping mains, a financial appraisal care must be taken in the design so that the
should be undertaken to determine the most addition of a protection device does not cause a
economic diameter of pumping main, to minimise the secondary water hammer equal to or worse than
capital cost and discounted pumping cost. The the original design could cause.
Reliability of the surge protection facility is important. Ductile iron pipes should be protected externally
Where appropriate, redundancy should be provided in accordance with QCS. Internally as a
for essential equipment such as vacuum relief valves. minimum cement mortar lining should be
Adequate alarms should be provided on surge tanks provided. Fusion bonded epoxy, ceramic epoxy
and similar components to give operators early and polyurethane are also suitable for internal
warning. Consideration should be given to protection.
preventing the pumping system from operating if the
surge protection facilities are not operable. Ductile iron pipes can be considered as semi-
rigid. Bedding design should be in accordance
Surge suppression should always be provided where with the manufacturers recommendations.
modelling predicts negative pressure in excess of the
following: Ductile iron pipes have flexible joints and require
thrust restraint at bends.
GRP, cement lined DI -1metre
Recommended Use
Fusion bonded epoxy, ceramic epoxy or
polyurethane lined DI -3 metres DI pipes shall, in general, be used for
constructing transmission and distribution mains
HDPE, MDPE -3 metres of DN 400 up to DN 1600, for underground and
above ground applications. DI pipes smaller than
DN 400 are perfectly acceptable from the
2.5 Pipeline Materials technical point of view, however, may prove to be
less economical than their plastic equivalents. DI
The existing TSE transmission and distribution
pipes are also recommended for all pumping
system consists mainly of ductile iron (DI), glass
stations regardless of the manifold diameter.
reinforced plastic (GRP), asbestos cement (AC) and
polyvinyl chloride (PVC) pipes. Preferred materials 2.5.2 Polyethylene Pipes
for new pipelines are DI or polyethylene (PE). PVC
should not be used on account of its susceptibility to Polyethylene pipes are covered by BS EN
UV damage. It is known that PE is also susceptible to 12201(Draft European Standard)5, WIS 4-37-176
UV damage, but to a lesser degree, and it is also and a comprehensive reference is included in the
more generally robust AC is not permitted to be used Manual for PE Pipe Systems, 2002 edition, by
for new pipes on account of health risks. Water Research Centre and British Plastics
Federations Pipes Group7.
Due consideration should be given to internal and
external corrosion. Protection from external corrosion The material used for their production shall be in
should be employed in areas where corrosive or accordance with QCS. They are classified by
contaminated soils are prevalent, or when pipelines nominal outside diameter and Standard
leave the soil environment. This is especially true in Dimensional Ratio (SDR),which represents the
the coastal environment or other harsh environments. ratio between the nominal outside diameter and
Metal pipes should be evaluated for, and, if the minimum wall thickness (SDR=OD/e). For
appropriate, be protected against corrosion due to pressure applications and Doha climatic
stray electrical currents in the soil. This is most often conditions, a minimum of SDR 17 Class PE 100
found when such pipes are near, or cross other only shall be considered. The nominal pipe size
pipelines that are protected by impressed current. range is from DN 90 to DN 1000.
The various materials used in the TSE systems are The approved jointing method for PE is fusion
discussed more fully in Volume 1 Section 4.3. jointing (electrofusion and butt-welding). Fusion
jointing of PE pipes produces a fully restrained
2.5.1 Ductile Iron Pipes pipeline string and therefore thrust blocks and
anchorages are normally not required. A typical
Ductile iron pipes and fittings up to DN 2000 are
self bending radius for SDR 17 is 25 times the
covered under BS EN 5453. Installation of DI pipes is
pipe OD.
covered by BS 80104 Section 2.1.
For ks values for various pipe materials refer to Table D - pipe diameter (m)
2.6.1.
For C values for various pipe materials refer to
Table 2.6.2.
HL = KV2/2g
Equation 2.6.3
Computer Modelling of Irrigation A computer model of the Doha irrigation system was
Networks originally constructed using WATNET software and
then rebuilt using SynerGEE for Water, to suit the
The concept of the network model is fundamental to new concept of direct supply eliminating the need for
an irrigation distribution model. The network model water towers in the distribution system. The latter
contains all of the various components of the system model has not been calibrated as flow and pressure
and defines how those elements are interconnected. readings were not available. The type of simulation
Network models are comprised of nodes and node performed was a steady-state simulation. A demand
connecting elements (links). There are different types allocation was carried out for each node by assigning
of nodal elements, including junction nodes where relevant base flow (Q-base) for sprinklers and drip
pipes connect, tank nodes, pump nodes and control emitters and applying demand profiles. An
valve nodes. Models use link elements to describe assumption was made that the application system
the pipes connecting these nodes. Also, elements operates for 12 hrs with drip emitters operating for 12
such as valves, pumps and tanks are sometime hrs and sprinklers for 6 hrs. Places having their
classified as links rather than nodes. The most discrete irrigation systems, with service reservoirs
fundamental data requirement is to have an accurate and pumping stations, were assumed to be fed in the
representation of the network topology, which details off-peak time.
what the elements are and how they are
interconnected. While performing hydraulic analysis it is useful to
check the behaviour of the system by not only
A computer model is not necessarily an exact applying fixed demands but also allowing free
representation of all pipes in the distribution system. discharge at points where water is delivered e.g. at
For large systems in particular, simplification of the service reservoirs. That would allow identifying areas
system (skeleletonisation) may be undertaken. of starvation and proposing appropriate zoning. It is
Methods of reducing the size of the model via particularly important in areas of substantial ground
skeletonisation include: level variation.
(1) Consider only pipes above a certain size; Model Calibration
(2) Eliminate tree type pipe regions in the
If a hydraulic analysis is to be carried out on an
system;
existing system where values for pipe roughness are
(3) Replace series and parallel pipes with uncertain and/or the location and operation of valves
single equivalent pipes; and or pipes in a system are not clear, some adjustments
(4) Analyse distinct, separate pressure zones to a hydraulic model may be necessary. The model
should be calibrated, such that the system pressures
separately.
predicted for certain conditions are in general
In all cases, the demands to the regions not modelled agreement with field measurements. The calibration
can be shown at nodes (junctions) leading to the process is necessary if the computer model is
region eliminated. Skeletonisation shall by no means expected to provide accurate and reliable results.
result from limitations caused by computer hardware
or software. All major modelling packages are For simulations over extended periods, comparisons
suitable for analysing unlimited number of elements. are made between the predicted and observed flow
rates, pressures, and tank water levels.
There are two basic types of simulation: steady-state
simulation and extended period simulation (EPS). Deviations between the results of the model
The former computes the state of the system application and the field observations may be caused
assuming that hydraulic demands and boundary by several things, such as:
conditions do not change with respect to time, whilst
Erroneous model parameters (pipe
the latter determines the quasi-dynamic behaviour of
roughness values and node demand
the system over a period of time (a series of steady-
distribution);
state simulations in which hydraulic demands and
boundary conditions do change with respect to time). Erroneous network data (pipe diameters,
lengths, etc.);
Incorrect network geometry (pipes connected (2) Modelled trunk main flows (where the flow
to the wrong nodes); is less than 10% of the total demand)
10% of measured flow.
Errors in boundary conditions (incorrect
pressure-regulating valve settings, tank water Pressure
levels, pump curves, and so on);
(1) 85% of field test measurement 0.5m or
Errors in historical operating records (pumps 5% of maximum head loss across system
starting and stopping at incorrect times); whichever is greater.
Equipment measurement errors (pressure (2) 95% of field test measurement 0.75m or
gauges not properly calibrated); 7.5% of maximum head loss across
Measurement error (reading the wrong values system whichever is greater.
from measurement instruments); and (3) 100% of field test measurement 2m or
Field data collection error (e.g. moving too 15% of maximum head loss across
quickly from one field point to another without system whichever is greater.
allowing the system to stabilize between If after detailed calibration, any points still do not
readings). conform to the stated flow and pressure calibration
Elimination of errors will frequently require an criteria, they should be reported as anomalies and
iterative process, especially for modelling larger investigated.
systems. Generally, very old and corroded
The elevation of points to be used for field pressure
distribution systems, and water systems with little or
measurement should be determined by a field
no information, particularly regarding water use, are
levelling exercise (to within accuracy of 25mm).
the most difficult to calibrate.
conveyance systems or obstructions is necessary. need for dewatering, the maximum depth of cover will
Preferred angles for bends are 11 15, 22 30, 30, be limited to less than 3m wherever possible. This
45, and 90. will not apply to the non-disruptive road crossings
where a minimum cover of approximately 3m to the
Where pipelines must be laid around curves or small sleeve pipe will have to be maintained to avoid
changes of direction, the required alignment can be settlement.
achieved by angular deflection at joints or, if the pipe
is flexible, by bending the pipe itself. Product High and low points in the pipeline must be created to
standards, or the manufacturer, shall state the value encourage air to accumulate and to be released at
of allowable angular deflection at a joint, or pipe the higher points. The minimum recommended
minimum bending radius. The allowable angular gradients between air release valves and low points
deflection will depend on the type of joint and the are 1:250 (4mm/m) on descending pipeline sections,
pipe material. and 1:500 (2mm/m) on ascending pipeline sections.
The horizontal distance from foundations and other 2.7.3 Internal Pipe Pressures
pipeline or cable shall be not less than 0.40m in
and Restraint of Thrust
normal circumstances. At points of congestion, a
distance of at least 0.20m shall be maintained except Pipeline Design Pressure
where this distance cannot be achieved. In all cases,
suitable measures shall be taken to prevent direct In accordance with BS EN 805:20009 design
contact with obstructions. These measures shall be pressure (DP) is the maximum operating pressure of
agreed with the respective operators. There could be the system or of the pressure zone, fixed by the
cases where an operator has his own requirements designer considering future developments, but
and those will have to be confirmed during the design excluding surge.
stage. Maximum design pressure (MDP) is the maximum
operating pressure of the system or of the pressure
2.7.2 Pipeline Vertical Alignment zone, fixed by the designer considering future
The vertical alignment of transmission pipelines is developments, and including surge, where:
determined by a number of factors:
MDP is designated MDPa, when there is a
A minimum depth of cover; fixed allowance for surge;
Avoidance of other buried utilities and MDP is designated MDPc, when the surge is
underground structures; calculated.
A maximum depth of cover to limit the need For all pipelines, the system test pressure (STP) shall
for ground dewatering; be calculated from the maximum design pressure
(MDP).
The need to pass through road crossings;
To encourage the release of air liberated Surge calculated:
during operation. STP = MDPc +100 kPa
To provide protection to the transmission pipelines Equation 2.7.1
and to avoid minor buried utilities, the minimum depth Surge non calculated:
of cover adopted is generally 1.2m.
STP = MDPa x1.5
Wherever cables and pipelines cross, a clearance of Whichever is the least
at least 0.20m shall be maintained. If this is not STP = MDPa+500kPa
possible, measures shall be taken to prevent direct
Equation 2.7.2
contact.
The design pressure (DP) of the Doha TSE
The maximum depth of cover has been determined transmission and distribution system is 700kPa.
by the need to pass under existing large utilities, such
The fixed allowance for surge pressure included in
as surface water drains. However, to minimise the
the MDPa shall not be less than 200kPa. Using this
figure the minimum system test pressure shall be Air valve Size DN
Pipe Size (mm)
1350kPa (13.5 bar) and all the pipeline components (mm)
like line anchors, thrust blocks and other restraining DN250 50, 65
structures and joints shall be designed accordingly. DN 250 to 600 80, 100
All flanges shall be rated to PN16. DN 600 to 900 150
DN 900 to 1200 200
Pipelines shall be designed to withstand a transient
DN 1400 to 1800 2x200
pressure of 80kPa below atmospheric pressure
(approximately 20kPa absolute pressure).
The air valve assembly shall be installed in a
Restraint of Thrust
concrete chamber. For chambers, general
Restraint shall be provided to prevent pipelines requirements, refer to section 2.7.6.
moving under thrust arising from test and operating
pressures, including an allowance for surge effects. 2.7.5 Pipeline Maintenance
The pipeline test pressure, being greater than any Draining
operating pressure, will normally determine the thrust
Appropriate washout facilities, depending upon local
restraint required as described above.
conditions, shall be provided according to operational
Out-of-balance thrusts, which must be restrained, requirements for draining and flushing. The size of
arise at bends in the pipelines, but there will also be a the washout shall be related to the volume of water to
requirement at other thrust points, such as closed be drained, the time available and the capacity of the
valves and branches, and blank ends. For pipelines receiving watercourse. The discharge diameter
with joints which are not anchored by welded or should not normally exceed DN 200.
bolted flanges, etc, thrust blocks must be used. The
The wash out assembly will include an invert-level
size and shape of a thrust block is decided by; the
tee and a gate valve housed in a chamber. The
force to be restrained, the size and type of the pipe
discharge should be connected to a drainage system.
fitting, and local ground conditions. If adequate space
For chambers, general requirements, refer to item
is not available, construction of piled thrust blocks, or
2.7.6.
use of restraint piping systems should be considered.
2.7.6 Isolation Valves
2.7.4 Air Release
General Requirements
Mains shall be provided with facilities to release air
when the pipeline is being filled and also during The location of isolating valves (shut-off valves) shall
normal operation. On the other hand, it should be be planned to facilitate shut-off in an emergency, for
possible to permit the entry of air during draining. At maintenance, repair, replacement, or additions.
each high point, a double-orifice air valve with a
separate isolating gate valve shall be installed. The Isolating valves should be installed on all branches,
size of the air valve will normally be from DN 50 to as close as possible to the through main.
DN 200, depending on the main diameter, the
The distance and location of isolation valves should
predicted flow rate of air, and the configuration of the
be fixed according to local conditions. In general, the
system. A general guideline for an air valve selection
intervals between isolation valves should not exceed:
is included in Table 2.7.1 below. The spacing of the
air valves should be such that it corresponds to a in trunk mains (transmission mains)- 5km
maximum pressure drop of 0.3 bar in mains for a flow
rate induced by free flow for a given slope (sudden in principal distribution mains - 2km
break of a main). Reference shall be made to the in secondary distribution mains - 0.5-1km
appropriate product standards for final valve
In general, on mains up to and including DN 600,
selection.
gate valves should be used for isolating purposes.
For mains larger than DN 600, butterfly valves should
Table 2.7.1 - Typical Double Orifice Air Valve
be considered. Gate valves larger than DN 400 must
Selection
be equipped with a by-pass to overcome the problem to another should be made directly outside the valve
of opening a valve against unbalanced heads. It is chambers.
also acceptable for the gate valve to be between five-
eighths to three-quarters of the size of the pipeline. In Access Covers
such cases properly designed tapers should be used
Access covers should meet the requirements of BS
to minimise the head losses.
EN 12410. In general, the following classes of DI
Unlike butterfly valves, gate valves are not intended covers will be applicable:
for controlling the rate of flow of water through a pipe.
CLASS D400 - heavy duty, for streets and
Valve Operation roads;
For manually operated valves, extension spindles CLASS C250 - medium duty, for sidewalks,
must be arranged to run in brackets, rigidly attached gullies, parking areas accessible for lorries;
to the chamber walls. These extension spindles
CLASS B125 - light duty, for sidewalks,
should be fabricated to the exact length required to parking areas only accessible to passenger
allow easy operation from the top of the valve
cars.
chamber using a standard tee key. Clockwise rotation
of the tee key to close the valve is preferred. Where The covers should preferably be medium duty, unless
frequent opening and closing of a valve is required, they are subject to vehicular traffic. Wherever
such valves should be fitted with electric actuators. appropriate, Aluminium covers with locking devices
shall be used, e.g. in grassed areas.
Valve Chambers
Table 2.7.2 - Summary of Available Flow Metering Instruments and their Parameters
Power Straight Pipe Length
Instrument Accuracy Other Features
Supply Required
At major pipe junctions; The most suitable pumps for TSE are centrifugal
Along transmission/distribution mains at pumps as these are the only pumps which will
approximately 5km intervals. provide both the head and flow normally required.
In general, pressure transducer locations should Centrifugal pumps are available in a variety of
facilitate the day to day system monitoring and the configurations using the same principle; a centrifugal
network model calibration as discussed in section pump operates by passing the liquid through a
2.6. Pressure tappings outside buildings, and spinning impeller where energy is added to increase
associated data loggers, should be housed in the pressure and velocity of the liquid.
suitable concrete chambers. Refer to section 2.7.6.
For high head duties, a pump can be constructed
Level Instruments with multiple impellers on a common shaft. Internal
passages are provided to direct the discharge from
Level instruments are required for irrigation water each impeller to the inlet of the next; each impeller
balancing and storage reservoirs at sources. They increases the delivery head without increasing the
should also be located at local reservoirs fed off the flow. These pumps are known as multistage pumps.
primary distribution system.
In a similar manner, two impellers can be arranged
Residual Chlorine back to back on a common shaft, each with a
separate suction but with both discharging to the
In the TSE main pumping stations, the residual
same outlet. The flow from each impeller is
chlorine level should also be monitored. This can be
combined, with no increase in head. These pumps
achieved by sampling the TSE at the discharge from
are known as double entry pumps.
the pumping station. The local telemetry or SCADA
system should be programmed to raise an alarm if Due to the impeller configuration, double entry
the level drops too low. In some main pumping pumps have a casing constructed in two parts, split
stations, additional chlorine dosing equipment may along the shaft axis.
be required to increase the residual chlorine level
before the TSE enters the distribution system. It is Large multistage pumps are often constructed in a
good practice to leave a chlorine dosing connection similar manner but they can also be constructed with
point upstream of the residual chlorine monitor so solid stage casings which are assembled along the
that if a problem were to arise in the future, a shaft, this is the common arrangement for the
temporary chlorine dosing plant could be quickly smaller pumps. Other considerations include:
connected in an emergency.
Centrifugal pumps for TSE duties should
Salinity Meters have closed impellers with close fitting
suction neck ring seals to minimise
Salinity meters or conductivity meters are required discharge bypass;
on the main inlets to the distribution system. These
meters give an output which is directly proportional Single inlet pumps should have hydraulic
to the salinity of the TSE. This will be monitored by a balancing within the pump to remove end
telemetry system to warn of an increased salt thrust;
Large centrifugal pumps should have a Fs = suction entry and friction losses.
maximum running speed of 1450rpm (4 pole
In order to avoid cavitation, the NPSH available
motor) while smaller low flow pumps
should be at least 1m greater than the NPSH
typically have an operating speed of
required by the selected pump.
2900rpm (2 pole motor).
Performance Characteristics When calculating NPSH, absolute values for
atmospheric and liquid vapour pressures are used.
Centrifugal pump performance will be dependant on
both the head and flow, as the head increases the Cavitation is the formation and collapse of vapour
flow will decrease, and vice-versa. bubbles in a liquid. Vapour bubbles are formed
when the static pressure at a point within a liquid
Each type of centrifugal pump will have a different falls below the pressure at which the liquid will
performance characteristic according to the design vaporise. When the bubbles are subjected to a
of the impeller and casing. Works testing of a pump higher pressure they collapse, causing local shock
by accurately measuring the delivery against various waves. If this happens near a surface, erosion can
heads will give a series of performance curves occur.
including absorbed power and efficiency.
Cavitation will typically occur in the impeller of a
When selecting any centrifugal pump for a specific centrifugal pump, where it can cause noise and
duty the performance curves should be examined vibration, as well as affecting the pump efficiency. If
closely for the power consumption and efficiency at allowed to persist it can lead to damage to the
both the designed duty and the operational pump, or even breaking away of foundations.
extremes.
Pump Duty Point
The selected centrifugal pumps should have a
performance curve as flat as possible in the duty Each pump has a performance curve where the flow
area with the minimum drop in head as the flow is plotted against head.
increases. Each pipework system has a friction curve where
NPSH, Vibration, Cavitation and Noise the friction head is plotted against flow.
Net Positive Suction Head (NPSH) is the minimum The system curve is obtained by adding the static
total pressure head required in a pump at a head to the friction losses and plotting the total head
particular flow/head duty. It is normally shown as a against the flow.
curve on the pump performance sheet.
The pump duty point is where the pump
NPSH is used to check an installation for the risk of performance curve and the system curve cross. It
cavitation. shows the flow that a particular pump will deliver
through the pipework system, at a particular total
NPSH = Pa Vp + Hs Fs head at the pump duty level. For examples of pump
Equation 2.8.1 and systems curves refer to Figure 2.8.1.
Where: The duty point should be used when considering the
Pa = atmospheric pressure at liquid free surface suitability of alternative pumps for a particular duty
Vp = vapour pressure of liquid by comparing the efficiency and power requirements
for each pump at the duty point.
Hs = height of supply liquid free surface above eye
of pump impeller
2.8.2 Plant Layout Dry well design should incorporate the following
features:
TSE drywell pumping stations usually take their
suction from a storage tank. They do not need to be The pumps should be installed with sufficient
directly attached to a wet sump. space between them to allow access for
maintenance and repair (minimum of 1m);
The pumping station layout should be designed to
provide a flow route through the pumps and out to the The pumps should be arranged to draw from
TSE distribution system with the minimum number of and discharge to common manifolds;
bends and changes of direction. The common suction and discharge
manifolds should be located either side of the
The normal method of operation will be for the
pumps. The suction pipe should be recessed
storage tank to be filled at a steady rate, with the TSE
at a lower level and may require an open
pumps being run for extended periods discharging
mesh walkway over it at floor level with the
either directly to the TSE distribution system, filling
individual pump suction connections rising up
high level storage towers, or both.
through the covers. This solution is not
For distribution duty, the pumps should be operated practical in all situations, for example
under variable speed control to provide a constant hydraulic considerations such as NPSH
pressure under variable demands. available may require that the suction
pipework be as simple and as straight as
For storage tower filling, the pumps should be possible. Whatever design is implemented, a
operated at a constant speed, selected to fill the balance must be found between the
tower at a particular rate. competing factors in dry well design. Each
design is different and requires a bespoke
A flow meter and pressure sensor should be installed
solution;
in the discharge manifold to record the flow and
control the pressure. The common discharge manifold should be
designed to accommodate a magnetic flow
The pumps will usually be required to operate at meter, automatic filters and disinfection
particular times, rather than on storage tank level requirements;
control. Level sensors should be installed in the
suction storage tanks to ensure priming, and prevent Platforms and walkways should be provided
loss of suction of the pumps. Level sensors should to permit access to all equipment at a suitable
also be installed in all storage tanks to avoid over level for safe operation, maintenance and
filling and spillage. repair;
Craneage should be provided for the removal
All pumps should preferably have variable frequency
of all pumps, and valves 450mm dia and
drives and the control system should be designed to
over.
start/stop, ramp up/down, adjust and match the
speeds of all running pumps as required on changing Careful thought should also be given to the
demand, based on the system pressure. shipping route for removing equipment;
Fixed speed pumps utilising a smaller jockey pump Access to the dry well and machinery should
and bladder type pressure vessel are an alternative be by staircase so that tools and equipment
to the use of variable speed pumps particularly on can be carried in and out safely;
smaller systems. It is possible to omit the jockey The dry well floor should slope gently towards
pump for off peak network pressurisation duty if the one side wall and then to one end where a
pressure vessel volume is large enough to ensure the sump pump should be installed to keep the
main pumps do not repeatedly start and stop filling floor as dry as possible;
the vessel under low flow conditions.
The sump pump should be installed in a small
The control system should also be able to operate all well, large enough to accommodate the pump
pumps at constant speed for tower filling. and should discharge to the drainage system;
A high level alarm should be installed in the Long drive shafts should have intermediate
dry well to give a warning of flooding before support bearings supported from concrete
damage to machinery occurs. beams spanning the dry well.
Pump Installation 2.8.3 Primary Movers
Double entry pumps have the suction in the centre on Electric Motors
one side of the pump, with the discharge directly
opposite on the other side. Care should be taken in selecting the type of electric
motor, with regard to the characteristics of the driven
Multistage pumps have the suction and discharge at load and the starting method. Where motors are to
the opposite ends of the pump. The suction can be be used in conjunction with variable frequency drives,
on the end or the side, the discharge is on the side they should be designed for such applications, or
but can be in any direction relative to the suction. suitably de-rated. The complete drive system should
Both pumps can be installed with the pump shaft be matched to ensure compatibility. Other
horizontal or vertical. considerations include:
The most compact footprint arrangement is for the All motors should be of the squirrel cage
pump to be installed with the shaft vertical and the induction type, suitable for operation with a
motor above, this allows the suction to be on one 415V, 690V or 3.3kV 3-phase, or 50Hz
side with the discharge on the other, but this will supply;
require an upper floor for the motors.
The continuous maximum rating of a motor
Pumps installed with the shaft horizontal will have a should be a minimum of 5% above the
longer footprint with the motor in the dry well and at calculated maximum power requirements
possible risk from flooding. Horizontal pumps are under all conditions of operation;
generally easier to maintain than vertical pumps.
Consideration should be given to providing
Pumps should generally be installed in a close- thermistors for temperature protection on all
coupled horizontal shaft configuration, unless the motors rated above 7.5kW;
drywell is deep or liable to flooding, when a vertical
Where the motors are installed vertically they
installation should be considered. Other
should be specifically designed for that
considerations include:
purpose with adequately rated end thrust
The pumps should be installed with sufficient bearings;
space between them to allow access for
Motors should be protected to IP55 class F.
maintenance and repair;
Standby Pumping
The pumps should be supplied with a mid-
range impeller, which will meet the design Standby pumping should normally be provided by
duty. However, the pump casing should be electric motor driven pumps as this allows a greater
sized to accept the maximum sized impeller degree of control. In the absence of any electrical
for that pump and the motor should be sized power, the use of diesel engine driven pumps should
to drive the maximum sized impeller; be considered.
Consideration should be given to fitting
When providing permanently installed diesel driven
temperature and vibration sensors to each
pumps where the reservoir is below ground,
pump set and connecting them to the station
consideration should be given to installing the engine
PLC;
at ground level with a 900 drive gearbox to a vertical
Pumps and motors installed with a drive shaft shaft pump installed below:
having universal joints should not be installed
directly in line; they should be slightly offset to Automatic start/stop diesel engines can be
provide movement to the universal joints; used for standby pumping;
Permanently installed diesel engines should
be located in a sound proofed enclosure;
VSDs convert the incoming fixed frequency 3-phase The disadvantages of the flux vector control are:
AC power supply, into variable voltage and
Feedback required;
frequency, to control the speed of the motor.
Modulator required;
There are various types of variable speed drive in the
market. The main types can be categorised as High cost.
follows: Selection of VSDs
(1) DC motor drives;
The selection of the suitable VSD size should be
(2) AC drives - frequency control Pulse Width according to the following criteria:
Modulated (PWM);
Operating voltage (415V, 3.3kV, 6.6kV,11kV);
(3) AC drives - flux vector control (PWM).
Operating frequency (Operation range);
The construction of the above-mentioned
types varies from one to another according to Motor peak current;
the control process required as follows: Ambient temperature (site temperature).
For irrigation pumping applications the most suitable
type of VSD should give both variable torque and
a AC drives frequency control
variable speed. In normal applications, AC drives with
using (PWM)
PWM are recommended. The manufacturers
The speed control of the motor is achieved by guidance on the selection of the particular VSD
controlling both the voltage and frequency. should be sought for applications above 300kW for
LV applications, and for all sizes of HV application.
The advantage of the AC drive technology over DC HV applications should be avoided wherever
technology is that standard AC motors are less possible.
expensive.
Example of Control Philosophy with
The advantages of AC drive frequency control using VSDs
PWM are:
An example of a variable speed pump irrigation
Low cost; station can be seen in section 2.8.6.
No feedback required.
The disadvantages of AC drive frequency control
using PWM are:
The form of separation should be according This type of protection is required to protect
to BSEN60439-112 or suitable equivalent. The the equipment against short circuit which can
designer should consider Form-4 in all be caused by insulation failure/damage, or by
designs for high personal safety and incorrect switching operation. Short circuits
equipment protection. are associated with electrical arcs.
An Interlocking facility is required where more Wherever possible bottom access should be
than one incomer is used in the switchgear. provided with a man entry cable chamber
Some examples are as follows: extending under the entire control room.
Flow Meter Selection flow range. The repeatability of the result should be
within 0.2%.
Magnetic flow meters offer the designer the best
solution for TSE pumped flow. Magnetic-type flow In addition to the calibration certificate, the flow meter
meters use Faradays law of electromagnetic manufacturers should provide the following:
induction for making a flow measurement. That is,
when a conductor moves through a magnetic field of (1) Isolated 4-20mA DC and pulse outputs;
given field strength, a voltage level is produced in the (2) Programmable in-built alarm relays for
conductor that is dependent on the relative velocity empty pipe, low and reverse flows;
between the conductor and the field. Faraday
(3) In-built digital display for flow rate, total and
foresaw the practical application of the principle to
flow measurement, because many liquids are alarms;
adequate electrical conductors. So these meters (4) Transmitter enclosure shall be protecteto
measure the velocity of an electrically conductive IP67;
liquid as it cuts the magnetic field produced across
(5) Calibration and programming kit.
the metering tube. The principal advantages include
no moving components, no pressure loss, and no The earthing rings should be included according to
wear and tear in components. Magnetic flow meters the individual manufacturers instructions. The sensor
should always be installed with full pipe conditions. lining should be neoprene or an equivalent material
of similar or improved properties. In below-ground
Care should be taken during design to provide flow meter chamber installations, the installed
sufficient straight run, up-stream and down-stream of equipment should be submersible to the maximum
the flow meter in accordance with the manufacturers chamber depth.
installation instructions. As a general guideline, 12
pipe diameters of straight pipe on the inlet and 6 pipe Control Equipment
diameters on the outlet will ensure that the flow meter
is able to achieve the specified accuracy. If the PLC
amount of space available is restricted then the PLC stands for Programmable Logic Controller. The
minimum usually accepted by manufactures is inlet PLC is a microprocessor-based device which is
run > 5 pipe diameters and outlet run > 3 pipe programmed to perform certain controlling tasks. The
diameters. PLC is the brain of the overall process. It can receive
analogue and digital signals from the process
Refer to Volume 8 for standard installation details.
devices, analyse them and send digital and analogue
The installation should allow for the future removal
signals to control these devices or activate certain
and replacement of the flow meter. The
alarms.
manufacturers requirements should take
precedence. PLCs were originally used for controlling purposes.
Almost all PLCs are now equipped with signal
The following International and British Standards are
transmitters (i.e. they include some RTU features)
a good source of information on flow meter selection
that are capable of transmitting data to the network
and installation, and can be quoted in specifications:
operation centre.
BS EN ISO 6817: 1997: Measurement of
A redundant PLC system with hot standby
Conductive Liquid Flow in Closed Conduits13;
configuration is highly recommended for critical
BS 7405: 1991: Guide to Selection and applications where uninterrupted control is required.
Application of Flow meters for the The power Supply for a PLC system is usually 24Vdc
Measurement of Fluid Flow in Closed or 110Vac. In case of power failure, the equipment
Conduits14. should be backed up by a UPS system which can
supply the PLC with up to 8 hours of power
Flow meters should be pressure tested and
depending on the importance of the process.
calibrated by the manufacturer and certified to a
traceable international standard. As a minimum, the
overall accuracy should be better than 0.5% of the
The modular type CPU (Central Processing Unit) in the failure of one pump which will be classed
the PLC is capable of: solving application logic; as the standby pump, and the other two
storing the application program; storing numerical pumps will continue to run normally.
values related to the application processes and logic;
and interfacing with the I/O systems. RTU
RTU stands for Remote Telemetry Unit. This unit
The PLC carries out a significant task which is PID delivers remote information back to network
control. PID (Proportional-Integral-Derivative) control operation centres. Operations staff can access
allows the process control to accurately maintain set- remote sites that have RTUs, via a web browser,
point by adjusting the control outputs. For example, SNMP (Simple Network Management Protocol)
pump flow rate set-point is maintained by the Manager, and XML (Extensible Markup Language). If
following: an ethernet connection is not available, then the
RTU's may be accessed via PSTN (Public Switched
Proportioning Band: is the area around the
Telephone Network), normal dialup and even SMS
set-point where the controller is actually
(Short Message Service) messaging.
controlling the process. The output is at some
level other than 100% or 0%. The band is Earlier generation RTUs were hardwired and
generally centred around the set-point (on supported limited functionalitys such as data transfer
single output controls) causing the output to and alarming. The new generation RTUs are
be at 50% when the set-point and the flow equipped with a powerful processor which allows the
rate are equal; RTU to control certain instruments/devices, and
Automatic Reset (Integral): corrects for any receive/transmit analogue and digital I/O
offset (between set-point and process (input/output) signals.
variable) automatically over time by shifting
The microprocessor-based RTU has a proven track
the proportioning band. Reset redefines the
record within the water and wastewater industry, a
output requirements at the set-point until the
robust modular construction, and is constructed for
process variable (flow rate) and the set-point
ease of maintenance and repair. These are intelligent
are equal;
devices capable of handling data collection, logging,
Rate (Derivative): Shifts the proportioning reporting by exception, current data retrieval and
band on a slope change of the process pump sequence control programs.
variable. Rate in effect applies the "brakes" in
an attempt to prevent overshoot (or RTUs equipped with RS232/485 links are
undershoot) on process upsets or start-up. recommended for interconnection to standalone
Unlike Reset, Rate operates anywhere within control systems, standard equipment packages and
the range of the instrument. Rate usually has PLCs (Programmable Logic Controller). A dedicated
an adjustable time constant and should be serial port should be provided for connecting a hand
set much shorter than Reset. The larger the held programming unit or the PC.
time constant, the more effect the Rate will
The RTU software enables the RTU to process
have; locally input equipment information before
Modulated Simplex I/O system: is the transmitting it to the master station to reduce
preferred solution for safe process since the transmission overheads. A report by exception
duplex (redundant) I/O system is usually operation is necessary for cost effective
expensive. The modulated simplex I/O communication. The report is triggered by change of
configuration guarantees that any failure of a state of digital values or analogues reaching
single I/O card will not cause the relevant I/O threshold values or varying by specified amounts.
rack to fail. For instance, if a rack contains The RTU also reports when polled and when the
three I/O cards which control three pumps (2 memory buffer is full.
duty, 1 standby), the failure of one card will
cause the whole pumping process to fail. In SCADA and Telemetry Systems
Modulated Simplex I/O systems, it will cause
Supervisory Control and Data Acquisition (SCADA) is background. As the data changes in the field, the
an industrial measurement and control system foreground is updated, e.g. a valve may be shown as
consisting of a central host or master (usually called open or closed. Analogue data can be shown either
a master station, master terminal unit or MTU); one as a number, or graphically. The system may have
or more field data gathering and control units or many such displays, and the operator can select from
remotes (RTUs); and a collection of standard and/or the relevant ones at any time.
custom software used to monitor and control
remotely located field data elements. Contemporary The SCADA control centre in Doha City is currently
SCADA systems exhibit predominantly open-loop using Intouch Wonderware as the main software for
control characteristics and utilise predominantly long- control and networking between the controlled sites
distance communications, although some elements and the central station.
of closed-loop control and/or short distance Control Philosophy
communications may also be present.
The control philosophy is the way the system will act
Systems similar to SCADA systems are routinely
to process changes to achieve the objective required.
seen in factories, treatment plants etc. These are For the control philosophy to function according to
often referred to as Distributed Control Systems
the client requirements several points should by
(DCS). They have similar functions to SCADA
taken into account:
systems, but the field data gathering or control units
are usually located within a more confined area. Overall controlling plan. This involves
Communications may be via a local area network preparing an overall plan of how the task
(LAN), and will normally be reliable and high speed. required will be achieved. In other words
A DCS system usually employs significant amounts stating the main tasks which will allow
of closed loop control. performance of the general task required;
SCADA systems on the other hand generally cover Realistic operational function. The sequence
larger geographic areas, and rely on a variety of and the functions of the operation should be
communications systems that are normally less realistic and achievable. This means all
reliable than a LAN. Closed-loop control in this process restrictions and conflicts should be
situation is less desirable. identified and avoided while producing the
control philosophy document;
The main use of SCADA is to monitor and control
Compatibility of products. This is about
plant or equipment. The control may be automatic, or
verifying that the control philosophy planned
initiated by operator commands. The data acquisition
is accomplished firstly by the RTUs scanning the field is achievable by existing industrial products;
inputs connected to the RTU (it may be also called a Cost effective. The choice of the products
PLC - programmable logic controller). This is usually should be cost effective. That means
at a fast rate. The central host will scan the RTUs unnecessary items should be taken out. At
(usually at a slower rate). The data is processed to this stage, it is possible to change the control
detect alarm conditions, and if an alarm is present, it philosophy slightly if it will decrease the
will be displayed on special alarm lists. Data can be overall cost of the project, on the condition
of three main types: Analogue data (i.e. real that the overall control philosophy will be
numbers) will be trended (i.e. placed in graphs); unaffected;
Digital data (on/off) may have alarms attached to one
Hazard awareness. When designing the
state or the other; and Pulse data (e.g. counting
control philosophy, we should take into
revolutions of a meter) is normally accumulated or
account that a failure in the devices or an
counted.
error in the process might appear. In this
The primary interface to the operator is a graphical process, all possible hazards should be
display (mimic) which shows a representation of the located and their effect on the control
plant or equipment in graphical form. Live data is philosophy should be cleared or at least
shown as graphical shapes (foreground) over a static minimised.
Example Irrigation Station Control If three pumps are running and their speed has been
Philosophy Using VSDs reduced to the minimum operating set-point (default
70%) and the controller is still calling for the speed to
The main pump control shall be achieved using be reduced; the first pump to start (the duty 1 pump)
variable speed pumps controlled by a PID controller, should be stopped. The remaining two pumps should
usually resident in the PLC or RTU. The set-point then be controlled to allow the header pressure to
(SP), Proportional (P), Integral (I) and Derivative (D) equal the set-point value.
terms of the controller should be configurable locally
or be downloaded via the SCADA system. The Similarly, if two pumps are running and their speed
process variable (PV) shall be the discharge header has been reduced to the minimum operating set-point
pressure. and the controller is still calling for the speed to be
reduced, the pump that has been running the longest
Upon receipt of the pump permissive signal, the should be stopped and the remaining pump
control system shall start the duty 1 variable speed controlled until the pressure has reached the set-
drive and ramp its speed up to the 1 pump operation point value.
set-point (default 70%). A pre-determined
stabilisation period (default 30 seconds) should then 2.8.7 Pump Suction and
allow the pressure in the discharge header to settle.
Delivery Design
The PID controller should then alter the speed of the
pump to control the discharge header pressure to Pipework
equal the set-point pressure.
The pipework installation should incorporate the
The controller shall continue to modulate the speed following features:
of the variable speed drive based on changes in the
discharge header pressure. If the pressure rises The pipework should be designed to allow the
above the set point the pump speed shall be reduced pumps to draw from and discharge to
and if the pressure falls below the set-point, the pump common manifolds;
speed shall be increased. The common suction and discharge
manifolds should be located either side of the
When the duty pump reaches full speed and remains
pumps. The suction pipe should be recessed
at full speed for a pre-set time (Usually around 120
at a lower level and may require an open
seconds), the duty 2 pump should be started.
mesh walkway over it at floor level with the
The duty 2 pump should ramp up its speed to the 2 individual pump suction connections rising up
pump operational set-point (usually 75%), through the covers;
concurrently the duty 1 pump should be controlled to The pipework should be designed with
the same value. sufficient flange adapters or bends to allow
easy dismantling and removal of pumps, non-
Once both drives have reached the selected speed
return valves or other major items of
they shall be controlled together by the PID
equipment;
controller. With the speed being increased and
decreased based on changes in the discharge All flexible couplings will require restraint to
header pressure. prevent displacement under pressure. The
pipework design should allow the suction and
Similarly in the case of a three duty pump station the discharge pipework to and from the pumps to
third duty pump shall be started when two pumps are be completely bolted, with bends to allow
running and have reached maximum speed for the dismantling;
pre-set period (around 120 seconds). At this point the
duty 1 and duty 2 pumps shall be ramped down to Each pump should be installed with suction
the 3 pump operational speed set-point (usually 75%) and discharge isolating valves bolted directly
and concurrently the third pump ramped up to the to the common manifolds which permit
same set-point. isolation for maintenance, while allowing the
other pumps to continue operating normally;
Consideration should be given to providing an There are four common causes of surge in a pipeline:
isolating valve on the pumping main before
any over-pumping connection, to allow the pump starting;
pumping station to be fully isolated and the pump stopping/power failure;
fixed pipework drained for repair. valve action;
Consideration should also be given to improper operation of surge control devices.
providing a valved connection for draining the
discharge pipework. Suction velocities should The most likely one of these is the sudden stopping
not normally exceed 1.8m/s but should be as of all pumps caused by a power failure.
low as practical to improve the NPSH
An approximate calculation for a simple pipeline is:
available (see 2.8.1). Discharge velocities
should not normally exceed 2.5m/s; P = a x V
Sumps should be designed in accordance g
with the recommendations of the CIRIA guide
The hydraulic design of pump sumps and Equation 2.8.2
intakes15 which gives guidance on sump Where:
design, suction bellmouth clearances and P = Pressure change (m)
measures to avoid vortex formation.
a = pressure wave velocity (m/s)
Valves
V = flow velocity change in 1 cycle (m/s)
Valves should incorporate the following features:
Isolation valves for TSE should be of the g = acceleration of gravity (9.81m/s2)
double-flanged wedge-gate type with a bolt- The simple cycle time can be calculated with the
on bonnet. When fully open, the gate should formula:
be withdrawn completely from the flow. The
valve handwheel direction of operation should Cycle time = 2 x pipeline length
be clockwise to close. Station valves should Wave velocity
have metal seats;
All sluice valves above 500mm bore (300mm Equation 2.8.3
if power actuated) should be provided with
jacking screws; Table 2.8.1 below shows wave velocity in m/s for
Reflux valves for TSE should be of the double pipe materials.
flanged, quick action single door type,
Table 2.8.1 - Indicative Surge Wave Velocity
designed to minimise slam on closure by
Values for Selected Pipe Materials
means of heavy doors weighted as
Pipe Material Velocity (m/s)
necessary;
Ductile Iron 1000 1400
Reflux valves should be provided with covers
Reinforced Concrete 1000 1200
for maintenance without the need to remove
Plastics & GRP 300 500
the valve from the pipeline. The covers NOTE: As the wave velocity is partially dependent on
should be large enough to permit removal of the physical properties of the pipe, the wave velocity for
the flap and inspection of the seat. the particular pipe under consideration must be
assessed for each scheme.
If the surge pressure approaches zero or the pipeline Refilling is usually from a high-pressure cylinder and
maximum pressure, a full surge analysis should be care should be taken to avoid over pressurisation of
carried out. the bladder. Bladders should not lose pressure in
normal operation, but they can fail, leading to
Surge Suppression Methods absorption of the gas into the liquid, and a drop in
pressure.
Surge suppression could be achieved using one of
the following devices. The most appropriate device Vessels without a bladder are charged with air
will depend on the individual circumstances of the pressure from an air compressor, either manually or
installation: automatically. There is therefore additional machinery
Flywheel; and an additional maintenance requirement. This
type of surge vessel is not recommended.
Pressure vessel with bladder;
On pump start-up, liquid enters the vessel,
Dip-tube surge vessel;
compressing the gas until it equals the liquid
Surge tower. pressure. When the pump stops, the gas pressure
forces liquid back out into the pipe system, both
Air valves should not be used as a method of surge
actions slow the rate of pressure change, which
control, but their operation under surge conditions
reduces the peak surge pressure.
should be carefully considered.
To dampen oscillations, a non-return valve may be
Flywheels
fitted to the surge vessel outlet pipe, to allow
Flywheels absorb energy on start-up, slowing the rate unrestricted flow into the pipeline, and a bypass
of velocity change in the pipeline. In reverse, when around the NRV fitted with an orifice plate to restrict
the pump is stopping, the flywheel releases energy the flow back into the vessel.
again, slowing the rate of velocity change. Together
these two actions reduce the peak surge pressure. Dip Tube Surge Vessels
A dip tube surge vessel is pressure vessel, the top
As the flywheel must be located on the drive shaft it
portion forming a compression chamber limited by a
is not suitable for submersible pumps or close-
dipping tube with a shut off float valve.
coupled pumps. However, they are simple devices
for wet well/dry well pumps and are preferred where This type of vessel is particularly appropriate for use
possible. on rising mains with flat profiles.
All high points The Y-strainers will be installed on the suction line
from the reservoir and will have a relatively coarse
At least every 1000m
screen of typically about 20-mesh, or as necessary to
The valves shall be capable of handling TSE water at suit the recommendations of the pump manufacturer.
40C without any adverse effects and have 316
b Main Pressure Filters
stainless steel or Ethylene Propylene Diene
Monomer (EPDM) coated float balls. The main pressure filters need to provide filtration
that meets the requirements of the downstream
All air valves should be fitted with an isolating gate
irrigation system. They must be able to remove
valve.
particulates (sand etc.), which will clog drip emitters
The manufacturers data sheets should be referred to and which will also damage the valve seats of
for the performance data to be included in any surge solenoid valves. It is also essential that they are able
analysis. to remove biological organisms (especially algae)
that build up and clog drip emitters.
2.8.10 Filtration
The degree of filtration depends upon the selection of
Clean irrigation water is an essential requirement for drip emitters and other application devices, but 150-
trouble-free operation of irrigation systems and for mesh (equivalent to about 100 microns) is
helping to minimise maintenance commitments. Drip
recommended as a good specification that would spin round and release the filtered matter.
substantially reduce maintenance problems. They are relatively compact in size but should
be installed indoors, preferably in the
If there is algae growth in a TSE resevoir it can cause pumping station. Disc filters are well suited to
a particular problem with drip irrigation systems. medium-sized irrigation pumping stations but
Algae growth can be prevented by ensuring that light there is no technical reason why they should
does not enter the reservoir and also by chlorination. not be installed in a main centralised pumping
Algal slime or similar organic matter will readily facility.
squeeze through any type of filtration screen, even of
fine mesh, and it also attaches itself to the filter Irrespective of the type of filtration selected, the
screen where it will hold tiny particles that otherwise performance of the pump sets must take into account
would pass through. For these reasons, screen the head loss through the filtration system. Head
filters do not provide effective filtration against algae, loss through the filters increases with increased flow
and the overall effectiveness of filtration will also be as well as with the degree of filtration. The
reduced. The options for irrigation filtration that are requirements of the back-flushing cycle also need to
effective at removing algae as well as hard be taken into consideration in the specification of the
particulates are either media filters or disc filters. pump sets and design of the pumping station.
Selection of the most appropriate solution will depend
upon cost considerations, space availability, pump c Downstream Final Filtration
characteristics and pumping station configuration. Although not part of the pumping station installation,
The main characteristics of these two options are as
as a final line of defence, a Y-strainer should be
follows:
provided at the downstream end of the irrigation
Media Filters system in each solenoid valve. Refer to section
3.1.1.
Media filters work by forcing water through
large vessels containing uniform size crushed 2.8.11 Ventilation and Air
sand or similar medium. The sharp edges of Conditioning
the medium are able to trap organic matter
such as algae. Media filters are cleaned by a Ventilation systems should be designed so that in the
back-flushing process that lifts and separates event of a fire being detected in any area, all the air
the medium. A small amount of the medium conditioning equipment and ventilation systems are
escapes, and needs to be replenished from shut down. All supply and exhaust ventilation louvers
time to time. Media filters are less effective should shut automatically to compartmentalise the
for removing sand particles because these building to restrict the spread of the fire and smoke,
are not flushed out during back-flushing. and ensure effective use of automatic fire
Media filters are physically large in size and extinguishing systems.
therefore space availability may be an issue.
The air conditioning system and ventilation fans
It is necessary to place a screen filter on the
should be run together and ventilation fan louvers
outlet to trap the escaping particles of
should shut, when the fan stops.
medium. For optimal operation, media filters
need to be carefully matched to system flow Louvers should be sized to keep the air velocity
rates and do not work well with low flows; through them below 0.5m/s.
Disc Filters
Air ducts should be designed to ensure the velocity
Disc filters comprise stacks of plastic discs through them does exceed 6m/s in occupied areas.
with a special surface that catches both
inorganic and organic particles as the water is
forced between the discs. They are typically
factory-assembled into multiple batteries.
The back-flushing cycle pushes the discs
apart, loosening them and allowing them to
Air Conditioning Systems and one unit fail, the other unit will provide 75% of the
Ventilation Capacities required air conditioning capacity.
The required air conditioning systems and The required thermal load should be calculated on
ventilation capacities are shown in Tables 2.8.2 and the basis of peak conditions.
2.8.3.
Ventilation
Table 2.8.2 - Air Conditioning Systems The required quantity of exhaust air should be
Location Air Condition system removed from electrical switch gear rooms to the
Electric Switch Dual Split AC unit pump room by a fan with an actuated louver.
Gear system
Control Room Split AC unit system Air inlet should be by natural supply through a
filtered and actuated louver.
Table 2.8.3 - Ventilation Capacities In the event of a fire, the electrically actuated
Location Approx. air louvers should be closed to seal electrical switch-
changes per
hour.* gear rooms during the use of any fire extinguishing
Electric 1 system.
Switchgear
Room Control Rooms, Kitchens and Toilets
Pump hall, 12
motor room
and control Air Conditioning
rooms A single split AC unit should be provided for air
Kitchen 12 conditioning the control room. No air conditioning
and Toilet should be provided for the kitchen or toilet.
Exhaust air should be removed by either two or the generator must be capable of accepting the
three duty fans and one standby fan, depending on largest starting load last with all other loads
the size of the pump room. connected.
The exhaust fans should have approximately 5% Standby generators should have a fuel header tank
less flow capacity than the supply fans to keep the sized for a minimum of 24 hours running at full load.
building at a slight positive air pressure. This is to
avoid drawing unfiltered dust laden air into the pump A bulk fuel tank with a further 7 days fuel at full load
and MCC rooms. This reduces the amount of dust should also be provided on site.
in the rooms, which can enter electric motors and
The header tank size could be reduced if an
switchgear, drastically shortening the equipment life. automatic replenishment system from the bulk tank
Pump rooms should have 10 air changes an hour. is provided. The replenishment system should
The cable basement should also be ventilated as maintain the header tank contents at a level
part of the pump room ventilation system. providing sufficient time for someone to attend the
site in the event of failure.
2.8.12 Standby Generation
2.8.13 Maintenance Access and
Before selecting a generator, a list should be
compiled of all electrical loads which the generator Lifting Gear
will be required to support. There should be no Safe access should be provided to all equipment
diversity factor on the generator loads. Each load and local control panels at all times.
should have its maximum starting load calculated to
determine the largest starting load. Access walkways, platforms and stairs should be
designed so that no dismantling is required for
Standby generating sets with varying loads due to normal routine maintenance. Vertical access should
changes in pump numbers or speeds etc. should be be by staircase so that tools and equipment can be
rated for Prime Power (PRP) duty in accordance carried in and out safely. Ladder access should be
with BS 7698/ISO852816, taking into account the restricted to infrequent visual inspection points.
running and starting loads.
Access around equipment for operation should be
Where there is a requirement for continuous running installed at a level where all the controls can be
at high load for extended periods, Continuous reached and operated easily without excessive
Output (COP) duty rating should be considered. stretching or bending and where all indicators can
be seen.
Limited time running power (LTP) generating sets
should be avoided. LTP generators are unlikely to Access around equipment for maintenance and
have sufficient reserve power to handle the largest repair should be installed at a level where all the
starting load with all other loads connected. maintenance points can be reached, dismantled and
removed without excessive stretching or bending.
Standby generators should be sized to carry the full
Particular attention should be paid to lifting gear
load of all electrical equipment connected to it plus
access and operation where heavy equipment is
the largest starting load. Generators for high
involved.
starting load installations should be generously
sized. Access below ground to dry wells should be by
staircase so that tools and equipment can be carried
Electrical loads connected to a standby generator
in and out safely.
should include all pumps, compressors, ACUs and
controls essential for the operation of the pumping Permanent access to wet wells and screen
station. All other loads should be disconnected and chambers should be provided, using stainless steel
inhibited. or GRP to just above TWL to allow for cleaning. The
access arrangements should be designed such that
When loading a generator, it is preferable to connect
an operator could be rescued from the sump with a
the largest load first and the smallest load last, but
safety harness and man-winch.
When designing access to equipment, careful Suitable for single heavy loads outdoors which must
thought should be given to shipping routes for be moved in all directions i.e. large submersible
removing equipment to a suitable position for further pumps.
work, or for removing from the pumping station
completely. Exit routes for equipment should not be Location of lifting equipment
the same as for personnel access unless there is an Lifting equipment should be provided
alternative escape route.
adjacent to all heavy items that require
When the lifting gear has taken the weight of lifting;
equipment and the equipment is released from its Lifting equipment should be positioned to
position, the clearance in the shipping route should provide a straight lift of the load and also be
be large enough for the equipment to pass through able to lower the load directly to a suitable
without rearrangement. setting down position;
Permanent or temporary lifting facilities should be Where lifting through openings in floors, the
provided for equipment that can not be easily lifted. lifting gear should be positioned to allow a
Consideration should be given to the weight, shape direct single lift up through all floors without
and position of the item to be lifted. As a guide lifting moving the lifting point or rearranging the
facilities should be provided for anything over 25kg. load.
For long or heavy lifts, gantry cranes should be Controls for Lifting Equipment
powered in all motions. Trolley cranes should
Overhead electric cranes and chain blocks
generally be power lift with manual motion, but small
should be provided with a low voltage
units should be manual on all motions. pendant control suspended from a glide
The following types of lifting equipment are track, independent of the lifting block. The
available: pendant control should extend to within
500mm of the operating floor, but not touch
Lifting Eye and Chain Block the floor;
Suitable for single straight lifts only inside a building Electric chain blocks should be provided with
or dry well. Not suitable for side forces, but may be a low voltage pendant control suspended
used in conjunction with other suitable lifting eyes to from the block. The pendant control should
swing a load sideways. extend to within 500mm of the operating
floor but not touch the floor;
Davit, Socket and Chain Block
Hand operating chains should extend to
Suitable for most small single lifts i.e. submersible within 500mm of the operating floor but not
pumps up to 250kg. Above this, the davit becomes touch the floor;
too heavy to be manhandled.
Long travel drive chains should be located to
Runway Beam, Trolley and Chain Block avoid snagging, and allow the operator safe
passage;
Suitable when there are a number of loads in a
straight line, or where a single load must be moved With the load hook in its highest position, if a
sideways. For heavy loads or long lifts, the chain load chain touches the operating floor or any
block and trolley should be electrically powered. item of plant, a chain collection box should
be fitted.
Overhead Gantry Crane
Suitable for installations where there are dispersed
2.8.14 Geotechnical Information
or heavy loads that must be moved in all directions. Geotechnical investigation must be completed
before any structural design can be undertaken. A
Mobile Crane
specialised geotechnical engineering firm shall be
employed to design, procure, and supervise the
necessary field works, in-situ and laboratory testing Atterberg limits on fine grained fraction (less
works. than 425 microns);
The economic depths for rectangular concrete Ventilation facilities are required to permit air
reservoirs are listed in Table 2.10.1. movement caused by changing water levels. It is
preferred that this is achieved by natural ventilation.
Table 2.10.1 - Economic Depths for Rectangular
Reservoirs shall be designed to prevent the ingress
Concrete Reservoirs
3
of external water and other contaminants.
Size (m ) Depth of Water (m)
Although the temperature effect is not as critical as
Up to 3500 2.5-3.5
for potable water storage, thermal insulation
3500-15000 3.5-5.0 measures may need to be taken for above-ground
reservoirs.
Over 15000 5.0-7.0
Reservoirs shall be provided with access for routine
Reservoir Size visits and repair work. Facilities shall be provided to
permit cleaning of each compartment independently.
In the case of balancing storage, the required size Access to the water compartments, control buildings
should be calculated based on peak diurnal and all functional equipment shall be designed for
variations in the distribution system, source safety, including that of personnel, and for ease of
production capacity, and the mode of operation operation. Openings shall be dimensioned so as to
(either continuous pumping for a selected period of permit entry for materials and equipment for
time or by call-on-demand through use of reservoir cleaning, maintenance and repair.
level control switches). In case of uniform supply the
capacity of a balancing tank should be 25-35% of Inlet, outlet, overflow and washout pipework, the
the average daily demand. necessary valves, flow meters and level-measuring
devices shall all be provided for each compartment.
In order to meet contingencies as well as hourly and The overflow from each compartment shall be of
daily variations the recommended volume of storage adequate dimensions to permit the free escape of
is two times the systems average day demand. If excess water and shall normally allow for discharge
space is not available this volume can be reduced to of the maximum inflow capable of being delivered to
a days demand. the service reservoir. There shall be no isolation
valves on the overflow system. The overflow
Functional Requirements
arrangements shall not permit the contamination of
The following requirements shall be taken into the stored water.
consideration while designing a reservoir:
Design Life
Water circulation;
The design life for properly maintained concrete and
Ventilation; steel storage tanks is typically assumed to be about
50 years. Any other type of storage tank that does
Prevention of contamination;
not have the historical longevity of these tanks
Temperature effects; needs to be evaluated on a life cycle cost basis
Access and security; before being considered for use.
Auxiliary Buildings
However, the irrigation requirements of large turf solenoid valve, other valves, irrigation mains and
areas cannot realistically be met from a pressurised sub-mains, Y-strainer and flow meter will be
effluent distribution main, and such areas would minimised by careful sizing of components, but will
need the installation of a local booster pumping still amount to 1.0 to 1.5 bar.
station.
It is therefore recommended that the pressure
For reliable irrigation system operation, it is essential available at any connection point (tapping) to the
that the design working pressure at the application main effluent distribution network should preferably
device should be well within the recommended not be less than 4.0 to 4.5 bar. In case this is not
range for each device, i.e. in the range of 2.5 to 3.0 attainable for particular sections of the network, then
bar in order to accommodate normal fluctuations in it may be necessary to provide booster pumping
the incoming pressure. Pressure losses in the stations for the downstream irrigation systems,
should the proposed irrigation devices required a pressure in the TSE transmission and distribution
greater pressure. network will be not less than 3 bar (30m water head)
and the maximum available pressure will not exceed
It should be remembered, however, that most of the 6 bar (60m water head). The DA, or their appointed
town landscape will be watered using direct feeds consultants, will provide the necessary design
from the TSE transmission and distribution system guidance regarding the irrigation water budgets and
(via main distribution chambers) and the available available pressure in the network.
pressure may vary from place to place. The
landscape and irrigation system designers should Some further examples of typical working pressures
take this into consideration while preparing their of some common irrigation application devices are
designs. In general, the minimum available given in Table 3.1.2 below.
3.2 Landscape and This process will also have an effect upon the
irrigation requirements that may be impossible to
Irrigation Management foresee accurately, but implies that flexibility should
be built into the original system designs.
3.2.1 Irrigation Management
Irrigation management is concerned with the
effective and sustainable use of available irrigation
resources, for the long-term well-being of the
landscape. It involves planning and monitoring the
usage of irrigation water at a strategic level. The
irrigation budgets and Irrigation Master Plan
discussed in sections 1.3.2 and 1.3.3 are essential
tools for implementing this essential role. The
function of irrigation management will be undertaken
by the Qatari authorities at a departmental level, to
ensure co-ordination between all concerned parties.
5.0 References
13British Standards Institution, 1999, BS EN 60439-
1: Low Voltage Switchgear and Controlgear
Assemblies. Type-tested and PartiallyType-Tested
1State of Qatar, 2002, Law No. 30: Environmental Assemblies, London, BSI.
Protection, Qatar, State of Qatar.
14 British Standards Institution, 1991, BS EN ISO
2 World Health Organisation, WHO Guidelines for 6817: 1997: Measurement of conductive liquid flow
the Safe Use of Wastewater and Excreta in in closed conduits. London, BSI.
Agriculture and Aquaculture, World Health
Organisation. 15 British Standards Institution, 1991, BS 7405:
1991: Guide to selection and application of flow
3 Qatar DD, Rationalisation of the TSE system meters for the measurement of fluid flow in closed
report, Qatar. conduits. London, BSI.
4 British Standards Institution, 1989, BS EN 16 CIRIA & BHRA (Construction Industry Research
545:2002 Ductile Iron Pipes, Accessories, Fittings and Information Association, British
and their joints for Water Pipelines, UK, BSI. Hydromechanics Research Association). 1977. The
5 British Standards Institution, 1989, BS 8010- hydraulic design of pump sumps and intakes. CIRIA
1:1989 - Code of practice for Pipelines, Part 1: & BHRA. ISBN: 0-86017-027-6.
Pipelines on land: general, London BSI. 17 British Standards Institution, 1993-1999, BS
6 British Standards Institution, 2001, BS EN 7698 Reciprocating Internal Combustion Engine
12201:2002 Plastic Piping Systems for Water Driven Alternating Current Generator Sets, UK, BSI.
Supply Polyethylene(PE), UK, BSI. 18 British Standards Institution, 1990, BS1377:
7 WIS 4-37-17. 1990 - Methods of test for soils for civil engineering
purposes. London, BSI.
8 Water Research Centre and British Plastics
Federations Pipes Group, 2002, Manual for PE Pipe
20 British Standards Institution, 1999, BS 5930 -
Systems, by Water Research Centre and British Code of practice for site investigations, UK BSI.
Plastics Federations Pipes Group. 21 BSI. 1987. BS8007: 1987. Design of concrete
9Water Research Centre, year, Network analysis - structures for retaining aqueous liquids. London.
A code of practice, UK, Water Research Centre. British Standards Institution.